2018 Los Angeles County Regional Transportation Improvement Program december 2017 This page is left blank.

2018 REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM (2018 RTIP)

Table of Contents

Page Number

Cover Letter

A. Overview and Schedule Section 1. Executive Summary...... 1 Section 2. General Information……………………………………………………………… 3 Section 3. Background of Regional Transportation Improvement Program (RTIP)…… 4 Section 4. Completion of Prior RTIP Projects…………………………………...... 4 Section 5. RTIP Outreach and Participation…………………………………..…………... 5

B. 2018 STIP Regional Funding Request Section 6. 2018 STIP Regional Share and Request for Programming…………………. 8 Section 7. Overview of Other Funding Included With Delivery of RTIP Projects……….9 Section 8. Interregional Transportation Improvement Program (ITIP) Funding……….. 10 Section 9. Projects Planned Within the Corridor………………………………………….. 10

C. Relationship of RTIP to RTP/SCS/APS and Benefits of RTIP Section 10. Regional Level Performance Evaluation……………………………………...11 Section 11. Regional and Statewide Benefits of RTIP…………………………………….15

D. Performance and Effectiveness of RTIP Section 12. Evaluation of the Cost Effectiveness of RTIP……….…….…...... 17 Section 13. Project Specific Evaluation……………………………………………………..19

E. Detailed Project Information Section 14. Overview of Projects Programmed with RIP Funding……..……………….. 51

F. Appendices Section 15. Project Programming Request Forms Section 16. Board Resolution or Documentation of 2018 RTIP Approval Section 17. Links to Project Study Reports and Project Study Report Equivalents This page is left blank. A. Overview and Schedule

Section 1. Executive Summary

The 2018 Regional Transportation Improvement Program (RTIP) for Los Angeles County satisfies the State Transportation Improvement Program (STIP) requirements for an urbanized county. The RTIP is a listing of state highway and transit projects that Los Angeles County proposes for funding through the 2018 STIP covering the five-year period from Fiscal Year 2018/2019 to 2022/2023. The primary purpose of the RTIP is to help implement the 2009 Long Range Transportation Plan and the Southern California Association of Government’s adopted Regional Transportation Plan/Sustainable Communities Strategy.

The Los Angeles County Metropolitan Transportation Authority (Metro), as the County Transportation Commission for Los Angeles County, is responsible for developing the county’s funding priorities for the STIP, and for submitting the projects to the California Transportation Commission (CTC) by way of the RTIP.

On August 16, 2017, the CTC adopted the 2018 STIP Fund Estimate (Fund Estimate). According to the Fund Estimate there is sufficient capacity to restore the $754 million in statewide deletions that resulted from the negative Fund Estimate for the 2016 STIP. In addition, the Fund Estimate indicates that there is also $1.5 billion for the regions and the state to program additional projects, as well as $335 million in capacity to fund Advanced Project Development Element (APDE) work through the 2018 STIP period.

Consistent with STIP priorities, Metro has reprogrammed prior 2016 deletions and has introduced a modally balanced program of new projects proposed for the 2018 STIP. Table 1 on the following page summarizes our 2018 RTIP submittal.

2018 Los Angeles County Regional Transportation Improvement Program 1 Table 1 – 2018 RTIP Submittal for Los Angeles County ($ in 000s)

Tier 1 Requests (Total Target) Programming Year

Agency Rte Projects PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total Planning Programming & METRO 9001 Monitoring (PPM) 9001 4,002 4,002 4,002 12,005

Caltrans 138 SR 138 Segment 6 4356 19,750 19,750

Caltrans 138 SR 138 Segment 13 4357 4,000 67,000 71,000

Caltrans 138 SR 138 Segment 4 4353 5,250 15,700 19,000 39,950

Caltrans 71 SR 71 2741 20,000 20,000 East San Fernando Valley Transit METRO transit Corridor 4296 34,630 17,775 54,733 107,138

METRO transit Bus Acquisition-Project 1 30,246 30,246

METRO transit Bus Acquisition-Project 2 17,096 17,096

Total -Total Target Requests 29,000 45,946 58,632 40,777 142,831 317,185

Tier 2 Requests (APDE) Programming Year

Agency Rte Projects PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total Long 710 Early Action Project/ Beach 710 Shoemaker 14,000 14,000 I-605/I-5 Interchange Caltrans 605 Improvements 18,170 18,170 I-605/SR-91 Interchange Caltrans 605 Improvements 22,000 22,000

Total - Tier 2 APDE Requests 36,000 - 18,170 - - 54,170

Tier 3 Requests (Potential Additional Shares) Programming Year

Agency Rte Projects PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total East San Fernando Valley Transit METRO transit Corridor 4296 - 59,460 39,030 98,490 I-405 Crenshaw Blvd Ramp Caltrans 405 Improvement 12,000 12,000

Total - Tier 3 Requests - - - 71,460 39,030 110,490

Total of Tiers 1, 2 and 3 65,000 45,946 76,802 112,237 181,861 481,845

2018 Los Angeles County Regional Transportation Improvement Program 2 Section 2. General Information

- Regional Agency Name Los Angeles County Metropolitan Transportation Authority

- Agency website links for Regional Transportation Improvement Program (RTIP) and Regional Transportation Plan (RTP):

Regional Agency Website Link: http://www.metro.net/

RTIP document link: https://www.metro.net/projects/funding/

RTP link: http://scagrtpscs.net/Pages/default.aspx

- Regional Agency Executive Director/Chief Executive Officer Contact Information Name Phillip A. Washington Title Chief Executive Officer Email [email protected] Telephone (213) 922-7555

- RTIP Manager Staff Contact Information Name William Ridder Title Executive Officer Address One Gateway Plaza, MS: 99-23-3 City/State Los Angeles, CA Zip Code 90012 Email [email protected] Telephone (213) 922-2887 Fax (213) 922-2476

- California Transportation Commission (CTC) Staff Contact Information Name Teresa Favila Title Associate Deputy Director Address 1120 N Street City/State Sacramento, CA Zip Code 95814 Email [email protected] Telephone 916-653-2064 Fax 916-653-2134

2018 Los Angeles County Regional Transportation Improvement Program 3 Section 3. Background of Regional Transportation Improvement Program (RTIP)

A. What is the Regional Transportation Improvement Program?

The Regional Transportation Improvement Program (RTIP) is a program of highway, local road, transit and active transportation projects that a region plans to fund with State and Federal revenue programmed by the California Transportation Commission in the State Transportation Improvement Program (STIP). The RTIP is developed biennially by the regions and is due to the Commission by December 15 of every odd numbered year. The program of projects in the RTIP is a subset of projects in the Regional Transportation Plan (RTP), a federally mandated master transportation plan which guides a region’s transportation investments over a 20 to 25 year period. The RTP is based on all reasonably anticipated funding, including federal, state and local sources. Updated every 4 to 5 years, the RTP is developed through an extensive public participation process in the region and reflects the unique mobility, sustainability, and air quality needs of each region.

B. Regional Agency’s Historical and Current Approach to developing the RTIP

The Los Angeles County Metropolitan Transportation Authority (Metro) develops the biennial RTIP based on the projects identified in the 2009 Long Range Transportation Plan, 2014 Short Range Transportation Plan, Metro’s Measure R and Measure M Expenditure Plans and the Southern California Association of Governments 2016 Regional Transportation Plan/Sustainable Communities Strategy. Additionally, Metro coordinates with Caltrans District 7 as well as our local agency partners for identifying projects to be submitted in the RTIP. Further, for the 2018 RTIP, Metro employed the Metro Board-adopted Evaluative Criteria Framework to develop the program of projects proposed. All of the projects submitted in the RTIP from Los Angeles County have gone through thorough analysis and public outreach.

Section 4. Completion of Prior RTIP Projects (Required per Section 68)

Per Section 68 of the STIP Guidelines, reporting is required on RIP-funded projects completed since the last RTIP adoption. Project completion is defined as construction contract acceptance. Since the 2016 RTIP adoption, no RIP-funded projects have reached the milestone of construction contract acceptance, and therefore there is nothing to report at this time.

2018 Los Angeles County Regional Transportation Improvement Program 4 Section 5. RTIP Outreach and Participation A. RTIP Development and Approval Schedule

Action Date CTC adopts Fund Estimate and Guidelines August 16, 2017 Caltrans identifies State Highway Needs September 15, 2017 Caltrans submits draft ITIP October 13, 2017 CTC ITIP Hearing, South October 24, 2017 CTC ITIP Hearing, North October 19, 2017 Regional Agency adopts 2018 RTIP November 30, 2017 Regions submit RTIP to CTC December 15, 2017 Caltrans submits ITIP to CTC December 15, 2017 CTC STIP Hearing, South January 25, 2018 CTC STIP Hearing, North February 1, 2018 CTC publishes staff recommendations February 28, 2018 CTC Adopts 2018 STIP March 21-22, 2018

B. Public Participation/Project Selection Process

As noted in Section 3A, Metro selects projects which are identified in the 2009 Long Range Transportation Plan, 2014 Short Range Transportation Plan, Metro’s Measure R and Measure M Expenditure Plans and the Southern California Association of Governments Regional Transportation Plan/Sustainable Communities Strategy. Each one of these planning documents features extensive public outreach and involvement.

In terms of Metro’s public outreach and involvement, Metro has undertaken several initiatives to ensure the projects submitted in the RTIP have received the proper public vetting and meet the needs of the residents of Los Angeles County. This section will describe the outreach strategy for the 2009 Long Range Transportation Plan, the 2014 Short Range Transportation Plan, and the Measure M Expenditure Plan of 2016 as those are the documents directly developed by Metro.

2009 LRTP Outreach

Once the Draft 2008 LRTP and its companion Technical Document were released for public review from March 12 through April 28, 2008, an extensive local outreach process was initiated. Forty-two outreach meetings were held from February 14 through April 30, 2008. These meetings covered all nine sub-regional Council of Governments (COG) governing boards and their respective subcommittees, our Technical Advisory Committee (TAC) and respective subcommittees, and numerous public and private stakeholders. Seven community meetings were held across the County between March 26th and the close of the public comment period on April 23, 2008. Information was widely distributed by Metro’s website, LRTP phone Hotline, multi-lingual Fact Sheets on buses and trains, cable channels, and radio and newspaper advertisements. Over 200 comment letters and 1,000 e-mails were received. A response matrix was included in the June 2008 Board report. Board members received CD’s of all comment letters and e-mails.

2018 Los Angeles County Regional Transportation Improvement Program 5 Upon consideration of public comments, the Draft 2008 LRTP was submitted for Board action on June 26, 2008. At this meeting, the Board voted to defer action on the Draft 2008 LRTP until after the November 2008 General Election outcome of Measure R. The 2009 LRTP was adopted by the Board on October 22, 2009.

2014 Short Range Transportation Plan - Outreach

The Draft Plan and its companion Technical Document were released for public review in mid- April, and an extensive local outreach process was initiated. Twenty-seven outreach meetings were held between April 12 and the close of public comments on June 18, 2014. These meeting covered all the Subregions and Councils of Governments (COGs), seven community meetings across the County, Metro’s Technical Advisory Committee and respective subcommittees, and other public and private stakeholder groups.

In addition to the outreach and involvement performed for the adoption of the 2009 Long Range Transportation Plan and the 2014 Short Range Transportation Plan, Metro staff also sought Metro Board adoption of our 2018 RTIP submittal. This process included meetings with the Metro Technical Advisory Committee, meetings with affected stakeholders, as well as the standard Metro Board Committee and Board Meeting. The Metro Board adopted the proposed 2018 RTIP submittal in November 2017.

2016 Measure M Expenditure Plan – Outreach

Metro first solicited the transportation priorities and needs as identified by the Subregions, and these proposals were evaluated based on Board-adopted performance goals of mobility, economy, accessibility, safety, and sustainability & quality of life. As a result, the draft expenditure plan was developed and was approved by the Metro Board in March 2016. The Draft Expenditure Plan was then presented through a broad and an extensive public outreach process, which included nine community meetings, one virtual community meeting, thirteen telephone town hall meetings, meetings with stakeholder groups, polling, surveys, and numerous other engagement efforts. The final Expenditure Plan along with the Measure M Ordinance language was adopted by the Board in June 2016. In July 2016, the Measure M Ordinance, inclusive of the Expenditure Plan, was submitted to the Los Angeles County Board of Supervisors, who approved officially placing the ordinance on the November 6, 2016 ballot at their August 2016 meeting. On November 6, 2016, Measure M was approved by 71% of LA County voters.

C. Consultation with Caltrans District (Required per Section 17)

Caltrans District: 7

Metro and Caltrans District 7 have worked closely to develop the 2018 RTIP Submittal for Los Angeles County. Metro and Caltrans District 7 worked together to restore the previously deleted Segments 6 and 13 of the SR 138 in order to fully fund these projects through construction. Additionally, Metro and Caltrans identified RTIP funding to complete the final segment of the SR 138 (Segment 4) and to fund the portion of the SR 71 that was left unfunded after the larger

2018 Los Angeles County Regional Transportation Improvement Program 6 Grant Program was cancelled. Also, Metro and Caltrans worked together to identify project development needs and together proposed Advanced Planning and Development Element (APDE) programming for the I-605/I-5 Interchange and the I-605/SR 91 Interchange. The effort was done with detailed consideration of the current project schedules and needs. Additionally, Metro is also coordinating with Caltrans District 7 and Caltrans Headquarters to manage the projects programmed in the Interregional Transportation Improvement Program (ITIP) located in Los Angeles County. Metro and Caltrans will continue to work together to deliver the STIP-funded projects in Los Angeles County in the most efficient way possible.

2018 Los Angeles County Regional Transportation Improvement Program 7 B. 2018 STIP Regional Funding Request

Section 6. 2018 STIP Regional Share and Request for Programming

A. 2018 Regional Fund Share Per 2018 STIP Fund Estimate

Per the 2018 Fund Estimate, the total target for Los Angeles County is $317.2 million. Of the total target share, $90.8 million is proposed to complete projects previously deleted through the 2016 STIP process. The $226 million balance is proposed for new highway and transit projects.

B. Summary of Requested Programming

Project Name and Location Project Description Requested RIP Amount PPM1 PPM $12 million Los Angeles County SR-138 Segment 6 Widen Segment 6 to $19.8 million Los Angeles County improve corridor safety SR-138 Segment 13 Widen Segment 13 to $71 million Los Angeles County improve corridor safety SR-138 Segment 4 Widen Segment 4 to $39.5 million Los Angeles County improve corridor safety SR-71 Widen SR-71 and add an $20 million Los Angeles County HOV lane to improve congestion and corridor safety East San Fernando Valley Adding a high capacity $107.1 million Transit Corridor North-South transit corridor Los Angeles County to the East San Fernando Valley Bus Acquisition 1 Bus system fleet $30.2 million Los Angeles County replacement to maintain a state of good repair, improve reliability, and reduce emissions Bus Acquisition 2 Bus system fleet $17.1 million Los Angeles County replacement to maintain a state of good repair, improve reliability, and reduce emissions

1 PPM – Planning, Programming, and Monitoring. Funds are used to perform the planning and programming duties of Metro consultants and staff.

2018 Los Angeles County Regional Transportation Improvement Program 8 Section 7. Overview of Other Funding Included With Delivery of Regional Improvement Program (RIP) Projects

Metro uses a variety of sources to deliver transportation projects in Los Angeles County. Many projects are funded significantly through the local sales taxes devoted to transportation improvements in Los Angeles County. The balance is comprised of state and federal funds.

Other Funding Total RTIP RSTP/ Other Total Project Proposed 2018 RTIP ITIP Other State TDA Local CMAQ Federal Cost

PPM $12,005 $12,005

SR 138 Segment 6 $24,250 $ 7,900 $32,150

SR 138 Segment 13 $80,500 $ 10,500 $91,000

SR 138 Segment 4 $39,950 $39,950

SR 71 $21,592 $ 57,600 $ 58,047 $ 190,000 $327,239

East San Fernando Valley $107,138 $ 328,900 $ 61,700 $ 968 $ 1,048,894 $1,547,600 Transit Corridor

Bus Acquisition 1 $30,246 $ 22,704 $ 61,918 $ 66,987 $ 33,950 $215,805

Bus Acquisition 2 $17,096 $ 52,000 $ 83,400 $ 76,750 $ 83,000 $312,246

Totals $332,777 $0 $461,204 $80,100 $145,318 $202,752 $1,355,844 $2,577,995

The state’s investment of RIP is highly leveraged, maximizing the state’s investment in order to deliver significant transportation improvements.

2018 Los Angeles County Regional Transportation Improvement Program 9 Section 8. Interregional Transportation Improvement Program (ITIP) Funding

The purpose of the Interregional Transportation Improvement Program (ITIP) is to improve interregional mobility for people and goods in the State of California. As an interregional program, the ITIP is focused on increasing the throughput for highway and rail corridors of strategic importance outside the urbanized areas of the state. A sound transportation network between and connecting urbanized areas ports and borders is vital to the state’s economic vitality. The ITIP is prepared in accordance with Government Code Section 14526, Streets and Highways Code Section 164 and the STIP Guidelines. The ITIP is a five-year program managed by Caltrans and funded with 25% of new STIP revenues in each cycle. Developed in cooperation with regional transportation planning agencies to ensure an integrated transportation program, the ITIP promotes the goal of improving interregional mobility and connectivity across California.

The 2018 RTIP for Los Angeles County does not include a request for ITIP funding. However, Metro supported the Caltrans District 7 ITIP requests, including the $7 million in amended programming for the Rosecrans Marquardt Grade Separation Project that Caltrans Headquarters included in their Draft ITIP.

Section 9. Projects Planned Within the Corridor (Required per Section 20e)

Provide a description of the project’s impact on other projects planned or underway within the corridor as required per Section 20 of the STIP Guidelines.

SR-138 Segments 4, 6, and 13 are the final segments to be completed on the SR-138 Corridor. Caltrans District 7 is currently constructing the SR-138 Segment 9. This project will provide both capacity and safety improvements to the corridor. Once completed, SR-138 will have a consistent number of lanes, reducing weaving movements, as well as additional safety improvements. Delivering all three segments is critical to improving safety within the corridor.

The East San Fernando Valley Transit Corridor will connect with the Metro Orange Line, providing a North-South high capacity connection. This project along with the Orange Line BRT Improvement Project planned for FY19 will bring enhanced transit services and connectivity between the destinations accessed by Van Nuys Boulevard and those along the existing Orange Line.

2018 Los Angeles County Regional Transportation Improvement Program 10 C.Relationship of RTIP to RTP/SCS/APS and Benefits of RTIP

Section 10. Regional Level Performance Evaluation (per Section 19A of the guidelines)

STIP Guidelines require that RTIPs be modeled to evaluate how the proposed RTIPs further the goals of the Regional Transportation Plan (RTP). The Southern California Association of Governments (SCAG) performs this analysis on behalf of Los Angeles County and the other counties in the SCAG Region. Three projects proposed in Los Angeles County’s RTIP are not included in this analysis: the two Bus Acquisition projects and the East San Fernando Valley Transit Corridor. The Bus Acquisition projects were not expected to have outputs that could be reflected in the model because they are replacement vehicles, and therefore were not included in SCAG’s model exercise. The East San Fernando Valley Transit Corridor project is slated to have its Locally Preferred Alternative (LPA) adopted in January/February 2018. As such, the project’s mode has not been determined, complicating the ability to model it. However, Sections 13 and 14 include individual project analyses of benefits and costs for the Bus Acquisition projects and the East San Fernando Valley Transit Corridor, as well as for all other projects proposed herein. Please see pages 12 through 14 and page 17 for the analysis provided by SCAG in support of the STIP requirement specified in section 19A of the guidelines.

2018 Los Angeles County Regional Transportation Improvement Program 11 Pursuant to the State Transportation Improvement Program (STIP) guidelines recently adopted by the California Transportation Commission (Commission), the Southern California Association of Governments (SCAG) is pleased to submit the requested regional performance evaluation for SCAG region’s 2018 STIP.

SCAG is the largest Metropolitan Planning Organization (MPO) in the country and the region is home to approximately 19 million Californians. SCAG region’s STIP includes several, often partial projects included in SCAG’s 2016 Regional Transportation Plan (RTP)/Sustainable Communities Strategies (SCS). The RTP/SCS meets the GHG targets established by the California Air Resources Board (CARB) pursuant to Senate Bill 375 (SB 375) specific to the SCAG region. Given these projects are drawn from the conforming RTP/SCS, it is reasonable to affirm that these STIP projects move the region towards the successful implementation of the RTP/SCS. Please note the following related to the 2018 STIP‐RTIP:

• The STIP‐RTIP does not include system wide preservation investments. As such, it does not impact asset conditions on the State Highway System (SHS), local roads, or transit assets. However, life‐cycle costs are considered in the analysis for the capital projects proposed by these STIP‐RTIP Submittals. • This STIP‐RTIP does not include land use strategies and only modest transit and active transportation investments. Therefore, mode shift impacts are negligible. • The STIP‐RTIP includes several highway projects, several involving pricing on High Occupancy Toll (HOT) lanes. These projects work best in tandem with SCAG’s RTP/ SCS Travel Demand Management (TDM) strategies. As such, TDM strategies are included in the analysis. • The STIP‐RTIP does not include smart land use strategies or other broad based pricing strategies (mileage based user charges) included in the RTP/SCS. Therefore, impacts on several measures in the STIP guidelines are not considered (e.g., percent of housing and jobs within 0.5 miles of transit stops with frequent transit service).

The STIP guidelines list a number of measures to report, depending on available data and tools. A brief summary of the analysis results for the applicable measures is provided below.

Investment Effectiveness The 2018 STIP benefit/cost (B/C) analysis for the SCAG region utilizes the Cal‐B/C model to calculate regional network benefits. It calculates and aggregates scenario benefits after travel impacts are evaluated using a regional travel demand model. The benefit/cost ratio compares the incremental benefits with the incremental costs of transportation investments. The benefits are divided into several categories, including:

• Savings resulting from reduced travel delay; • Air quality improvements; • Safety improvements; and • Reductions in vehicle operating costs

2018 Los Angeles County Regional Transportation Improvement Program 12 For these categories, SCAG’s travel demand model results are used to estimate the benefits of the 2018 STIP Build planning scenario compared with the No Build planning scenario. Model data for the 2018 STIP were summarized in one mile per hour (1‐mph) speed bins to facilitate analysis. Consistent with the overall STIP performance evaluation, benefits associated with SCAG’s 2016 RTP/SCS TDM strategies are reflected in the analysis. Most of these benefits are a function of changes in Vehicle Miles Traveled (VMT) and Vehicle Hours Traveled (VHT). Costs included in the analysis reflect estimates of lifecycle costs including capital and ongoing operations and maintenance costs. The 2018 STIP provides a regional network‐level benefit/cost ratio of 4.01. Benefits and costs are estimated over the planning period from 2016 through 2040.

3 INVESTMENT ANALYSIS SUMMARY RESULTS

Total Over Average Life-Cycle Costs (mil. $) $602.9 ITEMIZED BENEFITS (mil. $) 20 Years Annual Life-Cycle Benefits (mil. $) $2,419.7 Travel Time Savings $2,516.4 $125.8 Net Present Value (mil. $) $1,816.8 Veh. Op. Cost Savings -$366.3 -$18.3 Accident Cost Savings $188.9 $9.4 Benefit / Cost Ratio: 4.01 Emission Cost Savings $80.7 $4.0 TOTAL BENEFITS $2,419.7 $121.0 Rate of Return on Investment: N/A

Payback Period: N/A

Please note that a regional travel demand model may not be as sensitive to individual project‐ level impacts. As such, this analysis is not necessarily comparable to the project‐ level assessments as the regional evaluation accounts for the complementary or duplicative benefits of combinations of projects with the scenarios modeled externally using SCAG’s regional travel demand model.

VMT per Capita Impacts are projected to increase VMT per capita by 0.019 miles per day, which is less than one‐tenth of a percent.

Percent of congested VMT at or below 35 mph Impacts are projected to reduce congested VMT by 3.0 percent.

Commute mode share (travel to work or school) Impacts are expected to reduce the percentage of drive alone trips to work by 0.04% with no increase in drive alone trips to colleges or universities.

Asset Conditions (State Highway and Local Streets)

2018 Los Angeles County Regional Transportation Improvement Program 13 Based on the 2013 Pavement Condition Survey, almost 20 percent of the State Highway System (SHS) lane miles are in some form of distress (i.e., major distress, minor distress, or poor ride). The average Pavement Condition Index (PCI) for the region’s local roads is 69. The STIP does not impact asset conditions in this cycle.

Percent of transit assets that have surpassed the FTA useful life period Not applicable

Highway Buffer Index (the extra time cushion that most travelers add to their average travel time when planning trips to ensure on‐time arrival)

The full implementation of the region’s STIP projects will improve travel time reliability since HOT lane implementations have been shown to improve overall travel time reliability. However, it is not possible to estimate these impacts with current tools.

Fatalities SCAG’s analysis projects that fatalities per million persons per day will decline from 0.26 to 0.25 and injuries will be reduced from 13.06 to 12.96 per million persons per day.

Fatalities and injuries per million VMT will remain relatively unchanged at 0.01 and 0.53 respectively.

Percent of housing and jobs within 0.5 miles of transit stops with frequent transit service Impacts are projected to increase the percentage of housing within 0.5 miles of frequent transit service area by 0.07%. The percentage of jobs within 0.5 miles are projected to increase 0.38%.

Mean commute travel time (to work or school) Impacts are projected to reduce mean work commute travel time by 0.05 minutes for automobiles and increase mean work commute time by transit by 0.03 minutes for transit. Impacts are also projected to increase mean school commute travel times by 0.01 minutes for automobiles and by 0.05 minutes for transit.

Change in acres of agricultural land Not applicable

GHG Impacts Impacts are not projected to change daily CO2 emissions/capita.

The table on the next page summarizes the performance measures results as suggested by the RTP guidelines. Note that the table compares future conditions, as opposed to comparing to current condition, without the STIP‐RTIP against future conditions with the STIP‐RTIP. This allows for isolating the impacts of the STIP‐RTIP without taking credit for other developments, such as improved fuel efficiencies or smart land use strategies.

2018 Los Angeles County Regional Transportation Improvement Program 14 Section 11. Regional and Statewide Benefits of RTIP

The projects proposed for the 2018 RTIP provide substantial benefits to California and Los Angeles County. The SR-138 is primarily designed to improve safety and address projected growth in flow of goods and services through this area. The existing SR-138 has experienced several serious accidents and is above the statewide average rate of fatalities. Between 2012 and 2015, the route experienced 13 deaths and 87 injuries. Therefore, safety is the strongest goal for this project. The widening of this corridor will not only improve safety but increase capacity. The forecasted average daily trips (ADT) with the project will increase over 140 percent compared to the forecasted ADT without the project. This corridor is the connection which links Los Angeles County, in the vicinity of the Cities of Palmdale and Lancaster, to San Bernardino County in the vicinity of the City of Victorville, Apple Valley and Adelanto. State Route 138 links Los Angeles County cities of Palmdale and Lancaster with San Bernardino County cities of Victorville, Apple Valley and Adelanto.

Route 71 is a major regional highway transportation facility traversing parts of Los Angeles, San Bernardino, and Riverside County. It is a connecting link for major east-west corridors passing through the area and serves as an inland passageway for interregional travel between San Diego and the eastern portion of the Los Angeles area. The route also serves heavy commute traffic originating in the communities of Chino, Ontario and Pomona that is destined for employment centers in Orange and Los Angeles Counties. The purpose of this project is to alleviate traffic congestion by increase capacity on State Route 71 from Interstate 10 to Route 60 to handle the forecasted traffic volumes in coming years due to extensive development in the region. The SR-71 is a component of the Freight Triangle in Los Angeles County, and, as such, supports the robust goods movement system in California. Improving the efficiency of this critical piece of the region’s goods movement infrastructure will support the goods movement- dependent industries, which provide 33% of the region’s jobs, and contribute 35% of the regional Gross Domestic Product according to SCAG’s 2016 Regional Transportation Plan.

The East San Fernando Valley Transit Corridor Project will provide connections to local, regional, statewide, and national passenger transportation networks. The project is regionally significant as it provides improved access to the Metrolink Commuter Rail System through connections at the Sylmar/San Fernando Valley and Van Nuys Metrolink stations. The project would also connect to the expanding LA Metro regional transit system, with connections to the Metro Orange Line station at Van Nuys Boulevard and with many Local/Rapid bus connections traversing the alignment. The East San Fernando Valley Transit Corridor project will also connect to the national Amtrak rail network at Van Nuys station. The project would also improve ambient air quality and reduce greenhouse gas (GHG) emissions and Vehicle Miles Traveled (VMT). These benefits would improve regional air quality in Southern California and would contribute to statewide environmental goals for reducing GHGs and the number of vehicle-miles traveled.

The Bus Acquisition projects will improve the reliability of the fleet by replacing the portion of Metro’s bus fleet that has exceeded its useful life. The vehicles purchased will support Metro’s operation of 170 bus routes throughout the 1,433 mile service area. Metro’s bus service serves Los Angeles County, providing residents with access to jobs, education, health care, goods and services, recreation, and other activities. Additionally, Metro’s bus system connects to the Southern California Regional Rail network, the national Amtrak rail system, and regional airports.

2018 Los Angeles County Regional Transportation Improvement Program 15 The Shoemaker Bridge connects State Route 710 (SR-710) from the west to Downtown Long Beach in the east and functions as a very important local and regional gateway to the City and the north via Interstate 710 (I-710). I-710 serves as the principal transportation connection for goods movement between the Port of Los Angeles and POLB, located at the southern terminus of I-710, and the Burlington Northern Santa Fe (BNSF) Railway/Union Pacific Railroad (UP Railroad) rail yards in the cities of Commerce and Vernon. I-710 also provides key interstate commerce connections to east-west freeways (Interstate 405 [I-405], State Route 91 [SR-91], Interstate 105 [I-105], SR-60, Interstate 10 [I-10], and I-5). SR-710 and the Shoemaker Bridge provide the primary connection between I- 710 and Downtown Long Beach. The existing Shoemaker Bridge has structural deficiencies and a high accident rate due to non-standard geometric features that cannot be upgraded to current State Highway Standards. The Project would replace the existing Shoemaker Bridge with a new bridge, that would address these structural deficiencies and nonstandard design features in an effort to improve safety.

I-605 and I-5 are major north-south facilities between Orange and Los Angeles Counties and carry international, interstate, interregional and intraregional travel. This area is projected to experience substantial growth for goods movement. Build-out of the area, as well as increased shipping traffic through the area, will generate additional traffic on the freeways and at the system interchange. Reconstruction of the system interchange and widening of the mainline facility will address existing deficiencies and accommodate projected growth. The project area includes the following cities within Los Angeles County: Bellflower, Downey, Norwalk, Pico Rivera, Santa Fe Springs, and Whittier.

The San Gabriel River Freeway, Interstate 605 (I-605) and is a major north-south transportation route running through both Los Angeles and Orange County. The Artesia Freeway, State Route 91 (SR-91) is a major east-west transportation route that travels through the counties of Los Angeles, Orange and Riverside. Both of these highways are integral parts of the freeway network for the Southern California metropolitan area. The proposed interchange project would help to improve the connection between these freeways, facilitating improved mobility for the Southern California Region.

I-405 is a major north-south Interstate Highway in Southern California that spans 72.7 miles with 48.5 miles in District 7, Los Angeles County. It begins with Interstate 5 (I-5) in the City of Irvine in Orange County and terminates with I-5 in the Mission Hills District of LA County. I-405 has played a crucial role in the development of dozens of cities and suburbs along its route through the Greater LA area. It is used for international, interstate, interregional and intraregional travel and shipping through an urbanized corridor serving the four major import/export terminals of Long Beach Municipal Airport, Los Angeles International Airport, and the ports of Long Beach and Los Angeles. It travels through several LA basin cities and is also used as a commuter route. It is a heavily-traveled thoroughfare by both commuters and by freight haulers and is the busiest and most congested freeway in the United States.

2018 Los Angeles County Regional Transportation Improvement Program 16 D. Performance and Effectiveness of RTIP Section 12. Evaluation of Cost Effectiveness of RTIP (Required per Section 19) Table B2 Evaluation Cost-Effectiveness Indicators and Measures Future Level of Performance Goal Indicator/Measure Projected Performance Improvement (2040) (Baseline) Reduce Vehicle Miles 20.78 Increase in VMT per capita = 0.019 miles per day Traveled/capita

Reduce Percent of congested VMT 10.54% Reduction of 3.0% (at or below 35 mph) Congestion Reduction

Change in commute mode share (travel to work or school) Travel to Work Travel to School Travel to Work Travel to School

Vehicle Trips Drive Alone 71.71% 8.46% Reduction of 0.04% 0%

Vehicle Trips 2 Person Carpool 3.69% ‐8.24% 0% 0%

Vehicle Trips 3+ Person Carpool 2.32% 10.26% 0% 0%

Auto Passenger Trips 9.51%% 40.45% 0% 0%

Transit Trips 7.83%% 4.88% Increase of 0.03% Increase of 0.01%

Non-Motorized Person Trips 4.94%% 27.71% Increase of 0.01% Reduction of 0.01%

Reduce percent of distressed state Not applicable Not applicable highway lane-miles

Improve Pavement Condition Index Not applicable Not applicable (local streets and roads) Infrastructure Condition Reduce percent of highway bridge lane-miles in need of replacement or Not applicable Not applicable rehabilitation (sufficiency rating of 80 or below)

Reduce percent of transit assets that have surpassed the FTA useful life Not applicable Not applicable period

Reduce Highway Buffer Index (the System time cushion added to the average Future conditions cannot be modeled Improvement cannot be modeled Reliability commute travel times to ensure on- time arrival).

Reduce fatalities and serious injuries Fatalities per million persons = 0.26 No Reduction in Fatalities per million persons per capita (daily) Injuries per million persons = 11.97 No Reduction in Injuries per million persons

Safety Reduce fatalities and serious injuries Daily Fatalities per million VMT = 0.01 No Reduction in Fatalities per million VMT per VMT Daily Injuries per million VMT = 0.52 No Reduction in Injuries per million VMT

Increase percent of housing and jobs Household % = 44.15% Household % = Increase of 0.07% within 0.5 miles of transit stops with Jobs % = 52.64% Jobs % = Increase of 0.38% frequent transit service

Economic Vitality Auto Home Based Work = 22.20 mins Auto Home Based Work Reduction = 0.05 mins Reduce mean commute travel time Auto School = 11.89 mins Auto School Increase = 0.01 mins (to work or school) Transit Home Based Work = 76.40 mins Transit Home Based Work Increase = 0.03 mins Transit School = 58.46 mins Transit School Increase = 0.05 mins

Change in acres of agricultural land Not applicable Not applicable Environmental Sustainability CO2 emissions reduction per capita 9.78 lbs Daily Reduction per capita = 0.00 lbs (daily)

2018 Los Angeles County Regional Transportation Improvement Program 17 In addition to the expected regional performance improvement outcomes above, there are several benefits that will result from the proposed RTIP projects. Table B3 summarizes the project outputs/outcomes of the RTIP projects.

Table B3 Evaluation – Project Changes or Increased Capacity Benefits Benefits or Performance Project Type Changes to the Improvement at Project Or Mode Built Environment Completion State Highway New general purpose lane-miles 23 lane-miles New HOV/HOT lane-miles 8 lane-miles Transit or Additional transit service miles 9.2 miles Intercity Rail New transit vehicles 610 new vehicles Station improvements 14-28 new and improved stations

2018 Los Angeles County Regional Transportation Improvement Program 18 Section 13. Project Specific Evaluation (Required per Section 19)

Project Title: Route 138 Widening, Segment 6

Description of Corridor

State Route 138, from Avenue T in the City of Palmdale to its junction with Route 18 in Llano currently consists of one lane of travel in each direction as well as a median lane and standard - width shoulders. The proposed project will increase the lanes from one to two in each direction.

State Route 138 has been divided into thirteen segments. Segments 1, 2, 5, 7, 9, 10, 11, and 12, are either currently under construction or completed. The remaining 3 segments (4, 6 and 13) are proposed for funding.

Project Description

This project, EA 28620, is approximately 1.0 mile (1.6 km) in length, and is located in the community of Littlerock. The limits of this segment are from 87th Street East to 96th Street East, PM 55.2 to PM 56.2.

Project Cost

$32.35 Million

Project Benefits

This project will serve to relieve congestion and enhance safety along the Route 138 Corridor. The area of Antelope Valley is one of the fastest growing areas in Los Angeles County. In addition, Route 138, between Route 14 in the West and I-15 in the East, has been designated as a safety corridor. Although minor improvements have been made, addition of 2 lanes will improve mobility and enhance safety.

Benefits Summary . Benefit Cost Ratio: 1.0 . Vehicle Hours of Delay Saved: 285,958 /yr . Delay Savings: $2.3 M . Current Daily Vehicle Occupants*: 23,595 . Daily Vehicle Occupants Forecast w/o Project*: 33,000 . Daily Vehicle Occupants Forecast w/ Project*: 36,300 . Safety Benefit: Nominal . Additional Jobs Created** 430

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding generates 13,000 jobs for one year

2018 Los Angeles County Regional Transportation Improvement Program 19 Safety and Capacity Increases This project will add one lane in each direction and a median turn lane.

Mobility Project will improve mobility through the corridor by increasing capacity by adding lanes through the project limits.

Connectivity Route 138 has become vital east-west route, linking Antelope Valley in northern Los Angeles County with San Bernardino County. The project will enhance connectivity by accommodating local traffic, recreational vehicles, and trucks, by connecting northern Los Angeles County to San Bernardino and Riverside Counties.

Multi-modal Corridor Improvements Investments In addition to capacity improvement, the project will analyze pedestrian needs, ADA curb ramp and sidewalk improvements, and bike lane analysis.

Mitigating the Project Risks The project team will actively be involved to identify and mitigate risks by managing risks to minimize impacts to schedule and cost. The team will keep open communications with all involved parties and meet regularly to monitor identified risks.

2018 Los Angeles County Regional Transportation Improvement Program 20 District: 7 EA: 28620 PROJECT: Route 138 Widening, Segment 6 PPNO: 2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles

3 INVESTMENT ANALYSIS SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $31.7 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $32.5 Travel Time Savings $37.9 $8.4 $46.3 $2.3 Net Present Value (mil. $) $0.8 Veh. Op. Cost Savings -$8.8 -$2.0 -$10.9 -$0.5 Accident Cost Savings -$2.4 -$0.3 -$2.7 -$0.1 Benefit / Cost Ratio: 1.0 Emission Cost Savings -$0.1 -$0.2 -$0.2 -$0.0 TOTAL BENEFITS $26.6 $5.9 $32.5 $1.6 Rate of Return on Investment: 4.1% Person-Hours of Time Saved 5,719,169 285,958

Payback Period: 17 years CO2 Emissions Saved (tons) 60 3

CO2 Emissions Saved (mil. $) -$0.1 -$0.0

Should benefit-cost results include: 1) Induced Travel? (y/n) Y Default = Y 2) Vehicle Operating Costs? (y/n) Y Default = Y 3) Accident Costs? (y/n) Y Default = Y 4) Vehicle Emissions? (y/n) Y

includes value for CO2e Default = Y 21 Project Title: Route 138 Widening, Segment 13

Description of Corridor

State Route 138, from Avenue T in the City of Palmdale to its junction with Route 18 in Llano currently consists of one lane of travel in each direction as well as a median lane and standard - width shoulders. The proposed project will increase the lanes from one to two in each direction.

State Route 138 has been divided into thirteen segments. Segments 1, 2, 5, 7, 9, 10, 11, and 12, are either currently under construction or completed. The remaining 3 segments (4, 6 and 13) are proposed for funding.

Project Description

Segment No. 13, EA 28630, approximately 4.98 miles in length, consists of 3.98 miles on Route 138 and 1.0 mile on Route 18, and is located in the community of Llano. The limits of this segment will be from 0.4 miles west of 190th Street East to 0.7 miles south of Route 138/18 separation, PM 66.0 to PM 70.0 on Route 138; and from Route 138/18 Separation to 1.0 mile East of Route 138/18 Separation, PM 0.0 to PM 1.0.

Project Cost

$91 Million

Project Benefits

This project will serve to relieve congestion and enhance safety along the Route 138 Corridor. The area of Antelope Valley is one of the fastest growing areas in Los Angeles County. In addition, Route 138, between Route 14 in the West and I-15 in the East, has been designated as a safety corridor. Although minor improvements have been made, addition of 2 lanes will improve mobility and enhance safety.

Benefits Summary . Benefit Cost Ratio: 3.9 . Vehicle Hours of Delay Saved: 1,735,840 /yr . Delay Savings: $16.0 M . Current Daily Vehicle Occupants*: 31,570 . Daily Vehicle Occupants Forecast w/o Project*: 38,500 . Daily Vehicle Occupants Forecast w/ Project*: 41,800 . Safety Benefit: Nominal . Additional Jobs Created** 1,180

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding generates 13,000 jobs for one year

2018 Los Angeles County Regional Transportation Improvement Program 22 Safety and Capacity Increases The existing facility consists of one lane of travel in each direction. The new facility will provide for two lanes of travel in each direction as well as a median lane and standard width shoulders which will improve safety and capacity.

Mobility The project will improve mobility through the corridor by increasing capacity by adding lanes through the project limits.

Connectivity Route 138 has become a vital east-west route, linking Antelope Valley in northern Los Angeles County with San Bernardino County. The project will enhance connectivity by accommodating local traffic, recreational vehicles, and trucks, by connecting northern Los Angeles County to San Bernardino and Riverside Counties.

Multi-modal Corridor Improvements Investments In addition to capacity improvement, the project will analyze pedestrian needs, ADA curb ramp and sidewalk improvements, and bike lane analysis.

Mitigating the Project Risks The project team will be actively involved in identifying and mitigating risks by managing risks to minimize impacts to the schedule and cost. The team will keep communications open with all involved parties and meet regularly to monitor identified risks.

2018 Los Angeles County Regional Transportation Improvement Program 23 District: 7 EA: 28630 PROJECT: Route 138 Widening, Segment 13 PPNO:

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles 3 INVESTMENT ANALYSIS SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $86.0 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $337.2 Travel Time Savings $262.2 $58.3 $320.5 $16.0 Net Present Value (mil. $) $251.3 Veh. Op. Cost Savings $7.5 $1.2 $8.7 $0.4 Accident Cost Savings -$3.9 -$0.4 -$4.3 -$0.2 Benefit / Cost Ratio: 3.9 Emission Cost Savings $5.1 $7.1 $12.2 $0.6 TOTAL BENEFITS $271.0 $66.2 $337.2 $16.9 Rate of Return on Investment: 19.4% Person-Hours of Time Saved 34,716,799 1,735,840

Payback Period: 5 years CO2 Emissions Saved (tons) 158,180 7,909

CO2 Emissions Saved (mil. $) $4.7 $0.2

Should benefit-cost results include: 1) Induced Travel? (y/n) Y Default = Y 2) Vehicle Operating Costs? (y/n) Y Default = Y 3) Accident Costs? (y/n) Y Default = Y 4) Vehicle Emissions? (y/n) Y

includes value for CO2e Default = Y 24 Project Title: Route 138 Widening, Segment 4

Description of Corridor

State Route 138, from Avenue T in the City of Palmdale to its junction with Route 18 in Llano currently consists of one lane of travel in each direction as well as a median lane and standard - width shoulders. The proposed project will increase the number of lanes from one to two in each direction.

State Route 138 has been divided into thirteen segments. Segments 1, 2, 5, 7, 9, 10, 11, and 12, are either currently under construction or completed. The remaining 3 segments (4, 6 and 13) are proposed for funding.

Project Description

This project, EA 28600, is approximately 1.0 mile (1.61 km) in length, and is located in the community of Littlerock. This segment is a combination of portion of previously identified Segment No. 3 and Segment No. 4. The limits of this segment are from 0.52 mile west of 72th Street East to 77th Street East, PM 53.2 to PM 54.2

Project Cost

$39.95 Million

Project Benefits

This project will serve to relieve congestion and enhance safety along the Route 138 Corridor. The area of Antelope Valley is one of the fastest growing areas in Los Angeles County. In addition, Route 138, between Route 14 in the West and I-15 in the East, has been designated as a safety corridor. Although minor improvements have been made, the addition of 2 lanes will improve mobility and enhance safety.

Benefits Summary . Benefit Cost Ratio: 1.2 . Vehicle Hours of Delay Saved: 273,971 /yr . Delay Savings: $2.5 M . Current Daily Vehicle Occupants*: 28,820 . Daily Vehicle Occupants Forecast w/o Project*: 36,300 . Daily Vehicle Occupants Forecast w/ Project*: 40,370 . Safety Benefit: Nominal . Additional Jobs Created** 500

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding generates 13,000 jobs for one year

2018 Los Angeles County Regional Transportation Improvement Program 25 Safety and Capacity Increases The existing facility consists of one lane of travel in each direction. The new facility will provide for two lanes of travel in each direction as well as a median lane and standard width shoulders which will improve safety and capacity.

Mobility The widening of this corridor will not only improve safety but increase capacity to address projected growth in demand by adding lanes through the project limits. The forecasted ADT with the project will increase over 140% compared to the forecasted ADT without the project.

Connectivity This corridor is the connection which links Los Angeles County, in the vicinity of the Cities of Palmdale and Lancaster to San Bernardino County in the vicinity of the City of Victorville, Apple Valley and Adelanto. The project will enhance connectivity by accommodating local traffic, recreational vehicles, and trucks, by connecting northern Los Angeles County to San Bernardino and Riverside Counties.

Multi-modal Corridor Improvements Investments In addition to capacity improvement, the project will analyze pedestrian needs, ADA curb ramp and sidewalk improvements, and bike lane analysis.

Mitigating the Project Risks The project team will actively be involved to identify and mitigate risks by managing risks to minimize impacts to schedule and cost. The team will keep open communications with all involved parties and meet regularly to monitor identified risks.

2018 Los Angeles County Regional Transportation Improvement Program 26 District: 7 EA: 28600 PROJECT: Route 138 Widening, Segment 4 PPNO:

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles 3 INVESTMENT ANALYSIS SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $38.9 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $46.5 Travel Time Savings $40.8 $9.1 $49.9 $2.5 Net Present Value (mil. $) $7.6 Veh. Op. Cost Savings -$2.7 -$0.7 -$3.4 -$0.2 Accident Cost Savings -$0.9 -$0.1 -$1.0 -$0.0 Benefit / Cost Ratio: 1.2 Emission Cost Savings $0.4 $0.5 $1.0 $0.0 TOTAL BENEFITS $37.7 $8.8 $46.5 $2.3 Rate of Return on Investment: 5.4% Person-Hours of Time Saved 5,479,420 273,971

Payback Period: 14 years CO2 Emissions Saved (tons) 15,823 791

CO2 Emissions Saved (mil. $) $0.4 $0.0

Should benefit-cost results include: 1) Induced Travel? (y/n) Y Default = Y 2) Vehicle Operating Costs? (y/n) Y Default = Y 3) Accident Costs? (y/n) Y Default = Y 4) Vehicle Emissions? (y/n) Y

includes value for CO2e Default = Y 27 Project Title: Route 71 Expressway to Freeway Conversion (Route 10 to Route 60)

Description of Corridor

The primary purpose for State Route 71 is to provide for the safe and efficient, interstate and interregional movement of people and goods. State Route 71 is a connecting link for major east-west corridors including Interstate 210, I-10, SR-60 and SR-91. With the Interstate 15 (I- 15), SR-71 serves as an alternative for interregional travel for Interstate 5 (l-5) between San Diego and the eastern portion of the Los Angeles metropolitan area. The route serves heavy commute traffic originating from the communities of Chino, Ontario and Pomona going to Orange and Los Angeles Counties. SR-71 also serves as an interregional route circulating significant volumes of local traffic.

Project Description

The purpose of this project is to alleviate traffic congestion by increasing capacity in Pomona on State Route 71 from Interstate 10 to Route 60 to handle the forecasted traffic volumes in coming years due to extensive development in the region. The project proposes to widen State Route 71 to add one mixed flow lane and one High Occupancy Vehicle (HOV) lane in each direction between Interstate 10 and Route 60, converting the existing 4-lane expressway to a full 8-lane standard freeway. The project includes replacing two existing bridge structures over railroads and an existing pedestrian overcrossing as well as constructing retaining walls and sound walls.

Project Cost

$ 327 Million

Project Benefits

This project proposes to upgrade three miles of existing four-lane express way to an eight lane freeway on Route 71 from Interstate 10 to Route 60 in Los Angeles County. The purpose of the project is to increase freeway capacity, relieve existing traffic congestion, increase traffic safety and accommodate future traffic demands resulting from regional growth. This segment is the last remaining segment to convert to a freeway and provide carpool lanes between Interstate 10 and Route 91. State Route 71 is a critical connector for distributing nationally significant truck flows between Interstate 10, State Route 60, and State Route 91 through Los Angeles, San Bernardino, and Riverside Counties.

2018 Los Angeles County Regional Transportation Improvement Program 28 Benefits Summary

. Benefit Cost Ratio: 3.1 . Vehicle Hours of Delay Saved: 3,789,876 Avg Yr . Delay Savings: $30 M /yr . Current Daily Vehicle Occupants*: 101,200 . Daily Vehicle Occupants Forecast w/o Project*: 118,800 . Daily Vehicle Occupants Forecast w/ Project*: 227,700 . Safety Benefit: $12.9 M /yr . Additional Jobs Created ** 3,942 /yr

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding generates 13,000 jobs for one year.

Safety and Capacity Increases The preferred alternative proposes to widen State Route 71 to a standard 8-lane freeway including three (3) general purpose and one (1) HOV lane in each direction. This alternative increases the capacity of the freeway, upgrades the freeway geometries to current standards, and improves safety by eliminating at grade intersections.

2018 Los Angeles County Regional Transportation Improvement Program 29 District: 7 EA: 21060 PROJECT: Route 71 Expressway to Freeway Conversion (Route 10 to Route 60) PPNO:

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles 3 INVESTMENT ANALYSIS SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $293.2 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $918.4 Travel Time Savings $491.7 $108.0 $599.7 $30.0 Net Present Value (mil. $) $625.1 Veh. Op. Cost Savings $29.8 $10.6 $40.3 $2.0 Accident Cost Savings $234.1 $23.2 $257.2 $12.9 Benefit / Cost Ratio: 3.1 Emission Cost Savings $4.9 $16.2 $21.1 $1.1 TOTAL BENEFITS $760.4 $158.0 $918.4 $45.9 Rate of Return on Investment: 13.6% Person-Hours of Time Saved 75,797,523 3,789,876

Payback Period: 9 years CO2 Emissions Saved (tons) 253,895 12,695

CO2 Emissions Saved (mil. $) $6.6 $0.3

Should benefit-cost results include: 1) Induced Travel? (y/n) Y Default = Y 2) Vehicle Operating Costs? (y/n) Y Default = Y 3) Accident Costs? (y/n) Y Default = Y 4) Vehicle Emissions? (y/n) Y

includes value for CO2e Default = Y 30 Project Title: East San Fernando Valley Transit Corridor

Description of Corridor

The proposed project would run along the busy Van Nuys Boulevard and San Fernando Road corridors serving the eastern San Fernando Valley for 9.2 miles. At the northern end, the project would connect with the Sylmar/San Fernando Metrolink Station, and from there run south to connect with the Metro Orange Line at the Van Nuys station.

The Van Nuys Boulevard corridor has the seventh highest total transit boardings on the Metro Bus system, and is currently served by Rapid Line 761 and Local Line 233, which have combined passenger boardings that are the second highest in the San Fernando Valley. The demand in passenger boardings is constituted by both transit dependent and discretionary riders. The project study area’s overall population density and the transit dependent population density are both more than double that of the County’s total urbanized area.

Project Description

The proposed project would provide 9.2 miles of high capacity transit service extending south from Sylmar/San Fernando Metrolink Station to the Metro Orange Line Van Nuys Station. The project would provide area residents, businesses, and transit-dependent populations with improved mobility and access to the regional transit system.

Currently, the Draft Environmental Document advances a number of alternatives including Bus Rapid Transit, Tram, Light Rail with tunneling, as well as no-build and Traffic System Management alternatives. The Locally Preferred Alternative (LPA) is slated for selection in February of 2018. For the purposes of characterizing and qualifying the anticipated benefits of the East San Fernando Valley Transit Corridor Project here, analysis and modeling was based on a Light Rail Alternative, as the voter- approved Measure M Expenditure Plan identifies a total project cost that is congruent with the cost of a Light Rail alternative. Upon selection of the LPA in February, the project mode and the associated benefits will be more clearly defined.

Project Cost

$ 1.5 Billion

Project Benefits

The East San Fernando Valley Transit Corridor Project is a vital public transit infrastructure investment that would provide improved transit service along the busy Van Nuys Boulevard and San Fernando Road corridors serving the eastern San Fernando Valley. The project would provide new service and/or infrastructure that would improve passenger mobility and connectivity to regional activity centers, increase transit service efficiency (speeds and passenger throughput), and make transit service more environmentally beneficial via reductions in greenhouse gas emissions. The project would also provide relief to an increasingly congested transportation corridor that traverses some of the most highly-dense communities in the San Fernando Valley.

In addition to mobility benefits, improved transit connectivity and service would also increase transit ridership, which in turn could result in environmental benefits due to reduced vehicle trips,

2018 Los Angeles County Regional Transportation Improvement Program 31 reductions in vehicle miles traveled, less roadway congestion, and improved air quality.

Improved mobility to and from the project area has the potential to boost economic development and improve social justice by providing better access to employment, educational and health facilities, and activity centers. The project would bring a high capacity transit service to economically disadvantaged and transit-dependent parts of the San Fernando Valley, including the communities of Panorama City, Pacoima, and Arleta.

The East San Fernando Valley Transit Corridor Project is included in the Southern California Association of Governments (SCAG) 2016-2040 Regional Transportation Plan /Sustainable Communities Strategy (RTP/SCS), adopted in April 2016. The RTP/SCS also outlines several projects in and around the project area aimed at maximizing the effectiveness, safety, and reliability of Southern California’s transportation system.

Safety and Capacity Increases The project’s Build Alternatives (BRT or LRT) would require 1-2 travel lanes in each direction along Van Nuys Boulevard and San Fernando Road in addition to changes to on-street parking. Based on the higher carrying capacity provided by each of the Build Alternatives, the number of people traveling through the corridor (person throughput) would be greater than what is currently possible with general purpose lanes and mixed- flow bus service.

Safety improvements to the corridor, including project-specific mitigation measures and implementation of first-last mile enhancements will aim to reduce safety impacts resulting from the project. First-last mile improvements for safety can include things such as increased lighting near station areas, high-visibility/convenient crosswalks for pedestrians, and sidewalk improvements.

Mobility The project would provide new service and infrastructure that would improve passenger mobility and connectivity to regional activity centers and the local, regional, and national transit system, through increased transit service efficiency (speeds and passenger throughput).

Connectivity The East San Fernando Valley Transit Corridor Project will provide connections to local, regional, statewide, and national passenger transportation networks. The project is regionally significant as it provides improved access to the Metrolink Commuter Rail System through connections at the Sylmar/San Fernando Valley and Van Nuys Metrolink stations. The project would also connect to the expanding LA Metro regional transit system, with connections to the Metro Orange Line station (which itself connects to the Metro’s North Hollywood Red Line station) at Van Nuys Boulevard and with many Local/Rapid bus connections traversing the alignment. The East San Fernando Valley Transit Corridor project will also connect to the national Amtrak rail network at Van Nuys station.

Multi-modal Corridor Improvements Investments In addition to facilitating connections to Metrolink, Amtrak, and the Metro Orange Line, the project will incorporate first-last mile improvements that will consider access improvements to/from stations that aim at improving the passenger experience for pedestrians, bicyclists, disabled passengers, the elderly, and persons transferring between the transit station to local buses and other modes. First-last mile improvements to improve mobility can include things such as

2018 Los Angeles County Regional Transportation Improvement Program 32 pedestrian-friendly crosswalks, safety barriers to protect people from trains, bicycle storage, and improved sidewalks, among other enhancements. These improvements could reach up to a half mile from each station area and would be planned through a process that engages local communities, officials, and other stakeholders.

Environmental Benefits The project would also improve ambient air quality and reduce greenhouse gas (GHG) emissions and Vehicle Miles Traveled (VMT). These benefits would improve regional air quality in Southern California and would contribute to statewide environmental goals for reducing GHGs and the number of vehicle-miles traveled.

Mitigating the Project Risks Metro is committed to satisfying applicable federal, state, and local environmental regulations and to applying reasonable mitigation measures to reduce adverse effects and significant impacts. Measures to mitigate potential effects and impacts for the project alternatives are identified in this Draft EIS/EIR. Metro Board of Directors authorizes the completion of the Final EIR when they approve a project alternative, the Board will also adopt a Mitigation Monitoring and Reporting Program (MMRP), which lists all of the committed mitigation measures and CEQA Findings. Upon approval of the proposed project, these mitigation measures will become part of the proposed project, and will be considered binding under CEQA.

2018 Los Angeles County Regional Transportation Improvement Program 33 District: 7 EA: PROJECT: East San Fernando Valley Transit Corridor PPNO: 4296

3

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles INVESTMENT ANALYSIS SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $1,888.1 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $1,273.1 Travel Time Savings $1,031.2 $58.3 $1,089.5 $54.5 Net Present Value (mil. $) -$615.0 Veh. Op. Cost Savings $173.9 $25.5 $199.4 $10.0 Accident Cost Savings -$46.6 $3.2 -$43.4 -$2.2 Benefit / Cost Ratio: 0.7 Emission Cost Savings $11.2 $16.3 $27.6 $1.4 TOTAL BENEFITS $1,169.8 $103.3 $1,273.1 $63.7 Rate of Return on Investment: 0.0% Person-Hours of Time Saved 139,292,042 6,964,602 Payback Period: 20+ years CO2 Emissions Saved (tons) 557,202 27,860 CO2 Emissions Saved (mil. $) $14.9 $0.7

Should benefit-cost results include: 1) Induced Travel? (y/n) Y Default = Y 2) Vehicle Operating Costs? (y/n) Y Default = Y 3) Accident Costs? (y/n) Y Default = Y 4) Vehicle Emissions? (y/n) Y includes value for CO2e Default = Y 34 Project Title: Bus Acquisition (Projects 1 and 2)

Program Description

Metro operates 170 bus routes that operate within the 1,433 square mile Metro service area. Metro’s fleet of 2,438 buses facilitates the operation of those 170 routes, providing over 17,800 service hours a day. In order to ensure vehicles are able to effectively operate service, buses are maintained throughout their useful life and are retired once their useful life has been exceeded. For the purposes of maintaining a fleet-wide state of good repair, Metro replaces the retiring portion of the fleet, which is currently being replaced at a rate of approximately 200 buses per year. The two bus acquisition projects will assist Metro in meeting these fleet replacement needs.

Goals and Objectives

The bus purchases will support Metro’s objectives of providing safe, reliable and high-quality transit service. Additionally, the Bus Acquisition projects will help Metro achieve its goal of maintaining its system in a state of good repair.

Project Cost

The total project cost for Bus Acquisition ( Project 1) $ 216 million

The total project cost for Bus Acquisition (Project 2) $312 million

Project Benefits

Reliability The vehicles being replaced are the oldest, lease reliable, and most maintenance intensive vehicles in the Metro fleet. The older vehicles in the fleet experience a higher rate of breakdowns mid-service, with fewer miles between mechanical failures. Vehicle breakdowns reduce the overall reliability of the system, and diminish the appeal of transit to the commuting public. The replacement of these vehicles with the newer fleet will ensure smoother operation, greater reliability and the ability to accommodate existing and grow future ridership.

Accessibility The Bus Acquisition projects will procure wheelchair accessible low floor transit buses, which accommodate the widest spectrum of passengers including children, adults, the elderly, and the physically disabled, conforming to all applicable ADA regulations.

Environmental Benefits Depending on the selected vehicle technology, the Bus Acquisition projects may result in no net reduction or a significant reduction of transit-generated GHG emissions. Additionally, reliable and frequent transit service can help encourage mode shift from auto trips to transit trips, leading to greater GHG emission reductions.

2018 Los Angeles County Regional Transportation Improvement Program 35 Cost Effectiveness of Bus Replacement Vehicles (Bus Acquisitions 1 and 2)

The Cal B/C model has a number of parameters required that are not compatible with a system- wide bus fleet replacement project. In order to compute the investment benefit for a transit- related project, the Cal B/C model requires information on parallel highways, as well as changes in ridership and vehicle miles for both a “no-build” and a “build” scenario. In the case of bus fleet replacement, the Cal B/C requires specifying a single parallel highway roadway class. For a bus project where the buses purchased would operate throughout Metro’s service area, it is not feasible to provide a single classification for the parallel roadway. With regard to measurements of ridership and mileage changes that would be expected with a new project, these figures are not expected to change under a fleet replacement project, as fleet replacement does not expand capacity or service. Additionally, the Cal B/C model specifies a model horizon of 20 years, and that is not relevant for vehicles with an estimated useful life of 14 years. Therefore, for the purposes of the RTIP, project lifecycle costs and benefits are detailed below using a simple gathering of data on the costs and benefits of the project.

Metro, along with many other bus operators, maintains a policy that requires its fleet to be interchangeable throughout the system, allowing the flexibility to operate vehicles on all routes. Metro is currently considering various fleet technologies for system-wide fleet replacement, including: CNG (the technology currently operated), Low-NOx CNG vehicles, and/or Electric Vehicles. Cost and benefit information is presented for the three alternative technologies under consideration.

Range in Lifecycle Costs by Vehicle Technology (through 2034 per the 14-year useful life expectancy) CNG Buses Lo-NOx Electric Bus Capital Expenditures $.16 billion $.17 billion $.23 billion Bus Operations $12.6 billion $12.6 billion $12.3 billion Expenditures Total $12.8 billion $12.8 billion $12.6 billion

Depending on the technology chosen, environmental benefits may or may not result from the retirement of old technology, and its replacement with new vehicle technology.

Range in CO2-e reductions by technology (through 2034 per the 14-year useful life expectancy) CNG Buses Low-NOx Electric CO2-e saved (tons) 0 98,474 2,909,109 CO2-e saved (millions $)* $0 $4.3 million $126 million * Dollars per ton based on Cal B/C 6.0 emissions parameters and the dollars per ton value given for CO2-e.

Additionally, there are other benefits related to fleet replacement. Newer vehicles provide greater reliability, and help reduce the Mean Miles Between Mechanical Failure (MMBMF),

2018 Los Angeles County Regional Transportation Improvement Program 36 resulting in fewer mechanical disruptions to service. Service reliability influences travel behavior and helps to sustain and grow ridership.

2018 Los Angeles County Regional Transportation Improvement Program 37 Project Title: Shoemaker Bridge Replacement Project (710 Early Action Project)

Description of Corridor The Shoemaker Bridge connects State Route 710 from the west to downtown Long Beach to the east and functions as a very important local and regional gateway to the City and the north via I-710. The limits of the proposed Project lie between the Port of Long Beach (POLB) and downtown Long Beach. The area within the Project limits contains a mix of uses. The area south of Broadway Avenue and west of the Los Angeles River is characterized by commercial development typical of a downtown area. The area north of Broadway Avenue contains residential development with Cesar E. Chavez Park, Cesar E. Chavez Elementary School, and industrial development adjacent to the river. Cesar E. Chavez Park is located south of Shoemaker Bridge and is currently separated from open space areas along the LA River by West Shoreline Drive. The west side of the LA River includes the POLB and supporting industrial development.

Project Description The proposed Project limits on I-710 extend from the eastern abutment of Shoemaker Bridge at the LA River to the 10th Street off-ramp (PM 6.0 to PM 6.4). On local streets, the north-south Project limits are on Golden Shore from 600 feet south of West Shoreline Drive in the south to Anaheim Street in the North. The east-west Project limits on local streets are from Atlantic Boulevard in the East to the Anaheim Street and 9th Street intersection in the West. The proposed Project would reconstruct Shoemaker Bridge ramp structures and realign West Shoreline Drive. The City of Long Beach, in cooperation with Caltrans, is proposing to replace the Shoemaker Bridge (West Shoreline Drive) in the City. The proposed Project is an Early Action Project of the I- 710 Corridor Project and is located at the southern end of I-710 in the City and is bisected by the Los Angeles River. Three alternatives, a No Build Alternative (Alternative 1), and two Build Alternatives (Alternatives 2 and 3) are being evaluated as part of the proposed Project. Both Alternatives 2 and 3 will replace the existing Shoemaker Bridge over the Los Angeles River with a new bridge located just south of the existing bridge. In both Build Alternatives the Shoemaker Bridge will accommodate bicycle and pedestrian use. Both Alternatives will include the evaluation of design options for a roundabout (Design Option A) or a “Y” intersection (Design Option B) at the easterly end of the bridge. The primary difference between Alternatives 2 and 3 is that Alternative 2 provides for the re-purposing of the existing bridge for non-motorized transportation and recreational use and Alternative 3 includes the removal of the existing bridge. Alternatives 2 and 3 will also provide improvements to associated roadway connectors to downtown Long Beach and along West Shoreline Drive from SR-710 and improvements along portions of 3rd Street, 6th Street, 7th Street, and Broadway Avenue from Cesar E. Chavez Park to Magnolia Avenue. The proposed improvements may include additional street lighting, re- striping, turn lanes, bicycle, pedestrian, and streetscape improvements. The Project also includes the removal of the Golden Shore Street Bridge over Shoreline Drive and modifications to Golden Shore Street to create a new controlled intersection at Golden Shore Street and Shoreline Drive. The Project will also evaluate street improvements on 6th and 7th Streets from Magnolia Avenue to Atlantic Avenue and on Anaheim Street between 9th and Atlantic Avenue.

Additionally as an Early Action Project of the I-710 Corridor Project, Alternatives 2 and 3 will

2018 Los Angeles County Regional Transportation Improvement Program 38 evaluate the impacts from the closure of the 9th and 10th Street ramp connections into downtown Long Beach.

Project Cost Project costs for Plans, Specifications, and Estimates, are $14 Million.

Project Benefits The proposed project is intended to achieve the following goals: • Provide a structure and highway facility that meets current structural and geometric design standards • Provide a facility that is compatible with planned freeway improvements and downtown development projects • Improve connectivity from the downtown area to surrounding communities and adjacent recreational use areas • Improve safety and operations for all modes of transportation

Safety and Capacity Increases The existing Shoemaker Bridge has structural deficiencies and a high accident rate due to non- standard geometric features that cannot be upgraded to current State highway standards. The Project would improve safety, operations, and connectivity between downtown Long Beach and regional transportation facilities. The Project would also accommodate planned improvements in the area, such as the City’s planned expansion of Cesar E. Chavez and Drake Parks. If the existing Shoemaker Bridge were to continue to be used for vehicular traffic, the existing nonstandard features would remain and the existing bridge alignment would preclude planned improvements by other locally and regionally significant projects, specifically, the I-710 Corridor Project. The implementation of the proposed Project would provide consistency with the improvements proposed as part of the I-710 Corridor Project and the Mobility Element of the City’s General Plan (adopted October 2013), in addition to meeting the needs for traffic safety and accommodating the projected increase in demand for non-motorized transportation facilities within the City. The existing Shoemaker Bridge was constructed in 1953 and needs to be reconstructed in order to bring it up to current structural and roadway design standards. The following items are assessed in the report: the deck condition is poor, the bridge rails are nonstandard, and the deck geometry is characterized as tolerable. Additionally, local traffic entering and exiting from ramps on either end of the bridge, northbound (NB) and southbound (SB), have nonstandard weaving distances. Accidents occurring on the bridge and ramps may be attributed in part to the short weaves. Evaluation of freeway mainline accident data, presented in Table 1-3, reveals that the most common type of accident reported for NB I-710 were sideswipe and rear-end, followed by collision with an object. On SB I-710 the most common accident was sideswipe, followed by rear-end and collision with an object.

2018 Los Angeles County Regional Transportation Improvement Program 39 Mobility The Project is intended to improve safety as well as improve connectivity from the Long Beach Downtown area to surrounding communities. The project will not increase capacity.

Connectivity I-710 serves as the principal transportation connection for goods movement between the Port of Los Angeles and POLB, located at the southern terminus of I-710, and the Burlington Northern Santa Fe (BNSF) Railway/Union Pacific Railroad (UP Railroad) rail yards in the cities of Commerce and Vernon. I-710 also provides key interstate commerce connections to east- west freeways I-405, SR-91, I-105, SR-60, I-10, and I-5. SR-710 and the Shoemaker Bridge provide the primary connection between I- 710 and downtown Long Beach.

Multi-modal Corridor Improvements Investments Within the City, public transportation is provided by Long Beach Transit (LBT), the City, and Metro. LBT is the principal provider of public transportation in the city and provides transportation via bus, shuttle, and water taxi. The following are descriptions of each service provided by LBT: • LBT currently operates 34 bus routes, and nearly 2,000 bus stops. LBT bus routes offer connections to local rail service and to the neighboring cities of Carson, Compton, Paramount, Bellflower, Artesia, Cerritos, Hawaiian Gardens, and Norwalk. • The Passport Shuttle is a free local bus service that serves various neighborhoods in Long Beach, including California State University, Long Beach (CSULB), downtown Long Beach, and Pine Avenue. • The AquaLink water taxi has four (4) stops and ferries up to 75 passengers to the most popular Long Beach Harbor and Alamitos Bay Landing attractions. The AquaLink operates daily from May 21 to September 5 and on weekends September 9 to October 303. • The AquaBus water taxi, which ferries up to 49 passengers to the most popular attractions on the Long Beach Waterfront, stops at five (5) locations, including the Aquarium of the Pacific and the Queen Mary. The AquaBus operates daily from May 21 to September 5 and on weekends from September 9 to October 30. In addition to services provided by LBT, the City administers a Dial-A-Lift service, which offers a curb-to-curb, shared-ride transit service exclusively for the mobility-impaired residing in and traveling throughout the cities of Long Beach, Lakewood, and Signal Hill. Metro operates the Metro Blue Line light rail transit in the city, which connects downtown Long Beach to downtown Los Angeles. The north-south Blue Line connects to east-west lines such as the Red and Purple Lines in downtown Los Angeles and the Green Line in Willowbrook. There are eight Blue Line stations located in the city. The Transit Mall and Pacific Stations are located within the neighborhoods adjacent to the Project limits, at Pacific Avenue/1st Street and Pacific Avenue/5th Street, respectively. Portions of the Los Angeles River and Rio Hondo (LARIO) Trail (a Class I Bikeway) are located within and adjacent to the proposed Project limits. Access points to the LARIO Trail are located throughout the City; however, two access points are located within or adjacent to the proposed Project. One access point is located adjacent to the SCE substation and another is located just north of Shoemaker Bridge near DeForest Avenue, on the east side of the river. In addition, other Class I, II, and III Bikeways are located throughout the City and the

2018 Los Angeles County Regional Transportation Improvement Program 40 neighborhoods adjacent to the proposed Project limits. Class I Bikeways are located along West Shoreline Drive, Broadway, and 3rd Street. Class II Bikeways are located along 6th Street and 7th Street. Class III Bikeways are located along Pacific Avenue and Chestnut Avenue.

Mitigating the Project Risks The environmental process is currently underway. Environmental approval is anticipated in 2018.

2018 Los Angeles County Regional Transportation Improvement Program 41 District: 7 EA: 27300 PROJECT: Shoemaker Bridge Replacement PPNO:

3 INVESTMENT ANALYSIS SUMMARY RESULTS 2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles

Total Over Average Life-Cycle Costs (mil. $) $171.4 ITEMIZED BENEFITS (mil. $) 20 Years Annual Life-Cycle Benefits (mil. $) $48.5 Travel Time Savings $0.0 $0.0 Net Present Value (mil. $) -$122.9 Veh. Op. Cost Savings -$0.0 -$0.0 Accident Cost Savings $30.5 $1.5 Benefit / Cost Ratio: 0.28 Emission Cost Savings $0.0 $0.0 Residual Value from Investment $18.0 $0.9 TOTAL BENEFITS $48.5 $2.4 Rate of Return on Investment: -0.6% Person-Hours of Time Saved 2,624 131 Payback Period: 20+ years

Should benefit-cost results include: Tons Value (mil. $) Total Over Average Total Over Average 1) Induced Travel? (y/n) N EMISSIONS REDUCTION 20 Years Annual 20 Years Annual Default = Y CO Emissions Saved 0 0 -$0.0 -$0.0

2) Vehicle Operating Costs? (y/n) Y CO2 Emissions Saved 5 0 $0.0 $0.0 Default = Y NOX Emissions Saved 0 0 $0.0 $0.0 3) Accident Costs Savings and Residual Value from Investment are included PM10 Emissions Saved 0 0 $0.0 $0.0 PM2.5 Emissions Saved 0 0 4) Vehicle Emissions? (y/n) Y SOX Emissions Saved 0 0 $0.0 $0.0 includes value for CO2e Default = Y VOC Emissions Saved 0 0 $0.0 $0.0

Benefits from 3) were estimated and added to Cal-B/C Corridor 42 Project Title: I-605/I-5 Interchange Improvements

Description of Corridor

The San Gabriel River Freeway, Interstate 605 (I-605), and the Golden State Freeway, Interstate 5 (I-5) are major north-south transportation routes and the Century Freeway, Interstate 105 (I-105) is a major east-west transportation route within Los Angeles County and are integral parts of the freeway network for the Southern California metropolitan area.

Project Description

The project limits along the I-605 are from Slauson Avenue to I-105 and along the I-5 between Paramount Boulevard and Florence Avenue. This project will environmentally clear and design direct connectors at the I-605/I-105 interchange, an additional HOV/GP or HOT lane on I-605 and an additional HOV lane on I-5. Project scope includes improvements to the mainline, freeway connectors and auxiliary lanes. All the on and off ramps within the project limits will also be evaluated for improvements.

Project Cost

$81.569 Million

Project Benefits

The project will enhance mobility by extending the I-5 South Widening/HOV project between the Orange County Line to Paramount Blvd. The project will also provide better connections for HOV/HOT connections on I-605 and reduce bottlenecks currently found on I-605.

Benefits Summary

. Benefit Cost Ratio: 4.1 . Vehicle Hours of Delay Saved: 34,583,512 /yr . Delay Savings: $328.8 M /yr . Current Daily Vehicle Occupants*: 545,600 . Daily Vehicle Occupants Forecast w/o Project*: 661,650 . Daily Vehicle Occupants Forecast w/ Project*: 705,000 . Safety Benefit: $1 M /yr . Additional Jobs Created ** 2300

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding generates 13,000 jobs for one year

Safety and Capacity Increases The purpose of the project is to reduce congestion and improve freeway operations (both mainline and ramps), improve safety, and improve local and system interchange operations and limit freeway improvements to within the existing State R/W to the maximum extent possible while also minimizing environmental and economic impacts.

2018 Los Angeles County Regional Transportation Improvement Program 43 District: 7 EA: 29821 PROJECT: I-605/I-5 Interchange Improvements PPNO:

INVESTMENT ANALYSIS

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $1,733.1 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $7,120.3 Travel Time Savings $5,492.9 $1,082.2 $6,575.3 $328.8 Net Present Value (mil. $) $5,490.9 Veh. Op. Cost Savings $371.3 $69.1 $440.4 $22.0 Accident Cost Savings $15.8 $1.5 $17.4 $1.0 Benefit / Cost Ratio: 4.1 Emission Cost Savings $85.8 $105.2 $190.9 $9.5 TOTAL BENEFITS $5,965.8 $1,258.0 $7,224.0 $361.3 Rate of Return on Investment: 34.8% Person-Hours of Time Saved 691,670,252 34,583,512 Payback Period: 6 years

Should benefit-cost results include:

1) Induced Travel? (y/n) Y

2) Vehicle Operating Costs? (y/n) Y

3) Accident Costs? (y/n) Y

4) Vehicle Emissions? (y/n) Y

includes value for CO2e 44 Project Title: SR-91 WB from Shoemaker Ave to I-605/SR-91 Interchange

Description of Corridor

The Interstate 605 (I-605), is a major north-south transportation route and the Artesia Freeway, State Route 91 (SR-91) is a major east-west transportation route within Los Angeles County and are integral parts of the freeway network for the Southern California metropolitan area. In an effort to improve traffic flow along the freeways, the Los Angeles County Metropolitan Transportation Authority (Metro), in cooperation with the Gateway Cities Council of Governments (GCCOG), the California Department of Transportation (Caltrans) District 7, and the County of Los Angeles, is proposing to construct improvements to the system interchange at I-605 and SR-91 and corridors approaching the interchange.

Project Description

This project is the first phase project of the larger project (EA 07-29810) that is to improve the entire interchange and all local interchange ramps up to 3 miles from/to the interchange. The objective for this project is to complete the Project Approval and Environment Document (PA&ED) work needed for the improvement work on Westbound SR-91 to I-605/SR-91 interchange to reduce congestion and improve freeway operations to main lines and connected ramps.

Project Cost

$ 30 Million ($8 M for PA&ED, 22 M for PS&E)

Project Benefits

The improvement of this first phase project proposes to add new lanes (General Purpose and/or auxiliary), modify on/off ramps and reduce numbers of existing non- standard features to SR-91 WB from Shoemaker Ave to I-605/SR-91 interchange. The project seeks to reduce congestion and improve freeway operations on the main lines and connected ramps.

Benefits Summary . Benefit Cost Ratio: 3.5 . Vehicle Hours of Delay Saved: 20,818,841 /yr . Delay Savings: $204.3 M . Current Daily Vehicle Occupants*: 567,600 . Daily Vehicle Occupants Forecast w/o Project*: 657,800 . Daily Vehicle Occupants Forecast w/ Project*: 684,000 . Safety Benefit: Nominal . Additional Jobs Created** 1084

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding

2018 Los Angeles County Regional Transportation Improvement Program 45 Safety and Capacity Increases The project will reduce congestion and improve freeway operations, improve local interchange operations, and improve safety. The project will improve the existing non- standard lane and shoulder widths, and will improve weaving distances between successive on and off ramps, which will improve safety for users.

Mobility The project will improve mobility for users within the project limits and in the project vicinity by eliminating operational deficiencies, reducing congestion, and improving traffic flow on the mainline and ramps.

Connectivity The project will facilitate connectivity between geographic areas as it improves a vital system to system connector (Westbound SR-91 to Northbound I-605), and will improve the westbound High Occupancy Vehicle (HOV) lane by improving the non-standard left shoulder width. It will also improve connectivity between the local streets in the Cities of Cerritos and Artesia, as the project improves the westbound ramps of local interchanges, including Bloomfield Ave, Norwalk Blvd, Pioneer Blvd, and Studebaker Ave Interchanges.

Multi-modal Corridor Improvements Investments At ramp terminus intersections, the local roadways will be improved for pedestrians and bicyclists, as well as for vehicular traffic. Improvements will include ADA improvements at crosswalks and sidewalks and bicycle refuge lanes at intersections between right turn lanes and through lanes. Sidewalk will be added to both sides of Gridley Road overcrossing, where it currently only exists on one side of the overcrossing bridge.

Mitigating the Project Risks The project development team actively manages the risks of the project, such as schedule and cost risks. These include designing improvements that minimize impacts to avoid elevating the mid-level environmental document to a high-level environmental document.

The project includes some residential and commercial full property acquisitions, which presents a risk of possible community resistance. The local agencies are in support of the project, and various forms of public outreach have been conducted to the public and local agency elected officials.

2018 Los Angeles County Regional Transportation Improvement Program 46 District: 7 EA: 29811 PROJECT: SR-91 WB from Shoemaker Ave to I-605/SR-91 Interchange PPNO:

INVESTMENT ANALYSIS

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $ $833.7 ITEMIZED BENEFITS (m Benefits Benefits 20 Years Annual Life-Cycle Benefits (mi $2,925.8 Travel Time Savings $3,351.6 $734.2 $4,085.8 $204.3 Net Present Value (mil. $2,092.3 Veh. Op. Cost Savin $343.1 $60.5 $403.5 $20.2 Accident Cost Savin $0.0 $0.0 $0.0 $0.0 Benefit / Cost Ratio: 3.5 Emission Cost Savi $76.0 $96.2 $172.2 $8.7 TOTAL BENEFITS $3,770.7 $890.9 $4,661.5 $233.1 Rate of Return on Inves 11.3% Person-Hours of Time Saved 416,376,815 20,818,841 Payback Period: 10 years

Should benefit-cost results include:

1) Induced Travel? (y/n) Y

2) Vehicle Operating Costs? (y/n) Y

3) Accident Costs? (y/n) Y

4) Vehicle Emissions? (y/n) Y

includes value for CO2e 47 Project Title: I-405 Crenshaw Blvd Ramp Improvement

Description of Corridor

I-405, within project limits, is a freeway that consists of a total of 10 lanes in which 2 are high occupancy vehicle (HOV) lanes. Crenshaw Blvd, within project limits, consists of a total of 7 lanes and has a posted speed limit of 40 mph. The through lanes currently have a width of 11- 12 feet, and the right and left turn lanes have a width of 12-13 feet and 10 feet respectively. Crenshaw Blvd is a truck route per the City of Torrance.

Project Description

The project is located on I-405 at the Crenshaw Blvd/182nd Street on/off ramps in the South Bay sub-region. The project will alleviate congestion, improve traffic flow and operational conditions on I-405 and the local arterials of Crenshaw and 182nd St in the City of Torrance. The proposed improvements will also add a new I-405 on/ramp at Crenshaw, additional storage on the on/off ramps and add an auxiliary lane on I-405 between Western Ave and Crenshaw Blvd.

Project Cost

$ 92 Million

Project Benefits

Benefits of this project include improvement of freeway and arterial operations, increase in safety and reduce delays by alleviating congestion on local arterials and the I-405 mainline.

Benefits Summary . Benefit Cost Ratio: 4.4 . Vehicle Hours of Delay Saved: 603,027 /yr . Delay Savings: $5.6 M . Current Daily Vehicle Occupants*: 277,200 . Daily Vehicle Occupants Forecast w/o Project*: 313,500 . Daily Vehicle Occupants Forecast w/ Project*: 313,500 . Safety Benefit: $5.4 M /yr. . Additional Jobs Created** 1,200

*Average Daily Traffic Data from the application is converted to “vehicle occupants” by multiplying by 1.1, the average occupancy of a vehicle in Los Angeles County today.

** According to the Council of Economic Advisers within the Executive Office of the President, every billion dollars of transportation funding generates 13,000 jobs for one year.

Safety and Capacity Increases The proposed project will increase the capacity of the interchange and provide new turning movements to enhance accessibility and safety, improve traffic flow, operational conditions and alleviate congestion. The need for the project stems from deteriorating operations condition on I-405 and Crenshaw/182nd on/off ramps, a forecasted increase in traffic volumes, increasing delays during AM and PM peak period travel periods, and higher than

2018 Los Angeles County Regional Transportation Improvement Program 48 average accident rates at some interfacing intersections.

Mobility There is a queue spillback from the existing SB I-405 on-ramp into Crenshaw Blvd due to the ramp being at excess capacity. The queuing adversely affects local street operation by causing congestion, excess idling, increased fuel consumption and greenhouse gas emissions. In addition, there is currently traffic congestion on 182nd St and Crenshaw Blvd due to insufficient storage space for vehicles on 182nd St, Crenshaw Blvd, and I-405 on- ramps. Vehicles, entering or exiting the freeway, weave and merge on I-405 mainline lanes which back up commuter traffic from I-405 on-and- off ramps at 182nd St and Crenshaw Blvd to Western Ave. The goal of this project is to improve operational conditions and mobility, reduce delays by decreasing congestion, while improving safety and implementing a long-life pavement strategy.

Connectivity I-405 is a major north-south Interstate Highway in Southern California that spans 72.7 miles with 48.5 miles in District 7, Los Angeles County. I-405 has played a crucial role in the development of dozens of cities and suburbs along its route through the Greater Los Angeles area. It is used for international, interstate, interregional and intraregional travel and shipping through an urbanized corridor serving the four major import-export terminals of Long Beach Municipal Airport, Los Angeles International Airport, and the ports of Long Beach and Los Angeles. It travels through several Los Angeles basin cities and is also used as a commuter route. It is a heavily-traveled thoroughfare by both commuters and by freight haulers and is the busiest and most congested freeway in the United States. The proposed improvements on the I-405 mainline as well as the on-and-off ramps at 182nd Street and Crenshaw Blvd to Western Avenue will improve the connectivity of the interchange and the I-405.

Mitigating the Project Risks Project risks will be monitored and mitigated as the project progresses during the different phases of its development. A risk register has been developed and it will be updated periodically.

2018 Los Angeles County Regional Transportation Improvement Program 49 District: 7 EA: 29360 PROJECT: I-405 Crenshaw Blvd Ramp Improvement PPNO:

2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles 3 INVESTMENT ANALYSIS SUMMARY RESULTS

Passenger Freight Total Over Average Life-Cycle Costs (mil. $) $86.9 ITEMIZED BENEFITS (mil. $) Benefits Benefits 20 Years Annual Life-Cycle Benefits (mil. $) $381.3 Travel Time Savings $94.9 $17.4 $112.2 $5.6 Net Present Value (mil. $) $294.4 Veh. Op. Cost Savings $130.9 $20.4 $151.3 $7.6 Accident Cost Savings $98.0 $9.7 $107.7 $5.4 Benefit / Cost Ratio: 4.4 Emission Cost Savings $6.5 $3.6 $10.1 $0.5 TOTAL BENEFITS $330.3 $51.1 $381.3 $19.1 Rate of Return on Investment: 28.3% Person-Hours of Time Saved 12,060,548 603,027

Payback Period: 4 years CO2 Emissions Saved (tons) 176,559 8,828

CO2 Emissions Saved (mil. $) $5.4 $0.3

Should benefit-cost results include: 1) Induced Travel? (y/n) Y Default = Y 2) Vehicle Operating Costs? (y/n) Y Default = Y 3) Accident Costs? (y/n) Y Default = Y 4) Vehicle Emissions? (y/n) Y

includes value for CO2e Default = Y 50 E. Detailed Project Information

Section 14. Overview of projects programmed with RIP funding

Route 138 Widening, Segment 6

2018 Los Angeles County Regional Transportation Improvement Program 51 Route 138 Widening, Segment 13

2018 Los Angeles County Regional Transportation Improvement Program 52 Route 138 Widening, Segment 4

2018 Los Angeles County Regional Transportation Improvement Program 53 Route 71 Expressway to Freeway Conversion (Route 10 to Route 60)

2018 Los Angeles County Regional Transportation Improvement Program 54 2018 Los Angeles County Regional Transportation Improvement Program 55 East San Fernando Valley Transit Corridor

2018 Los Angeles County Regional Transportation Improvement Program 56 Bus Acquisition Projects 1 and 2 (System Map)

A larger version of this map is available at https://media.metro.net/riding_metro/maps/images/system_map.pdf

2018 Los Angeles County Regional Transportation Improvement Program 57 710 Early Action Project/ Shoemaker Bridge

Regional Location Map:

2018 Los Angeles County Regional Transportation Improvement Program 58 710 Early Action Project/ Shoemaker Bridge

Project Limits Map:

2018 Los Angeles County Regional Transportation Improvement Program 59 I-605/I-5 Interchange Improvements

2018 Los Angeles County Regional Transportation Improvement Program 60 I-605/SR 91 Interchange Improvements 2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles 61 I-405 Crenshaw Blvd Ramp Improvement

2018 Los Angeles County Regional Transportation Improvement Program 62 F. Appendices

Section 15. Project Programming Request Forms

Section 16. Board Resolution and Documentation of 2018 RTIP Approval

Section 17. Links to Project Study Reports and Project Study Report Equivalents

2018 Los Angeles County Regional Transportation Improvement Program 63 This page is left blank.

2018 Los Angeles County Regional Transportation Improvement Program 64 Section 15 Project Programming Request Forms

2018 Los Angeles County Regional Transportation Improvement Program 65 This page is left blank.

2018 Los Angeles County Regional Transportation Improvement Program 66 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 0700021254 9001 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA Los Angeles County Metropolitan Transporation Authority MPO Element SCAG Mass Transit Project Manager/Contact Phone E-mail Address Diego Ramirez /MTA (213) 922-2468 [email protected] Project Title Planning, Programming and Monitoring (PPM) Location (Project Limits), Description ( Scope of Work) Planning, programming and monitoring.

Component Implementing Agency PA&ED Los Angeles County Metropolitan Transporation Authority PS&E Los Angeles County Metropolitan Transporation Authority Right of Way Los Angeles County Metropolitan Transporation Authority Construction Los Angeles County Metropolitan Transporation Authority Legislative Districts Assembly: Senate: Congressional: Project Benefits

Purpose and Need Project planning activities include: evaluating candidate projects; preparing and reviewing Project Study Reports (PSR's), PSR equivalants, major transportation investment studies. Program development activities include: developing the financial plan for th "Call for Projects" (STIP); coordinating with Caltrans in development of the RTIP; identifying cost components for programming; perparind and executing MOU's for STIP funds programmed to local agencies, project nomination sheets for RTIP projects; and preparing RTIP recommendations and STIP amendments. Metro Planning is responsible for transportation planning and programming functions legislated by the State of California.

Category Outputs/Outcomes Unit Total

ADA Improvements Y/N Bike/Ped Improvements Y/N Reversible Lane analysis No Includes Sustainable Communities Strategy Goals Y/N Reduces Greenhouse Gas Emissions Y/N Project Milestone Existing Proposed Project Study Report Approved 08/01/01 Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type N/A Draft Project Report End Environmental Phase (PA&ED Milestone) Begin Design (PS&E) Phase End Design Phase (Ready to List for Advertisement Milestone) Begin Right of Way Phase End Right of Way Phase (Right of Way Certification Milestone) Begin Construction Phase (Contract Award Milestone) End Construction Phase (Construction Contract Acceptance Milestone) Begin Closeout Phase End Closeout Phase (Closeout Report) For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 67 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 0700021254 9001 Project Title: Planning, Programming and Monitoring (PPM)

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan PS&E LosT Angeles i County Ahi Metropolitan R/W SUP (CT) LosT Angeles ti County A th Metropolitan it CON SUP (CT) LosT Angeles ti County A th Metropolitan it R/W LosT Angeles i County Ahi Metropolitan CON LosT Angeles ti County A th Metropolitan it TOTAL T ti A th it Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 99,153 2,309 2,308 4,002 4,002 4,002 115,776 TOTAL 99,153 2,309 2,308 4,002 4,002 4,002 115,776

Fund No. 1: RIP - State Cash (AB 3090) (SC 3090) Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 3,837 3,837 TOTAL 3,837 3,837

Fund No. 2: RIP - State Cash (ST-CASH) Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E $1000 CON voted 09/24/98 R/W SUP (CT) $1000 CON voted 07/01/99 $2100 CON voted 09/01/99 CON SUP (CT) $3115 CON voted 07/01/00 R/W $1342 CON voted 01/16/01 CON $4322 CON voted 10/25/01 TOTAL $3662 CON voted 03/03/05 $3772 CON t d 12/15/05 Proposed Funding ($1,000s) Notes E&P (PA&ED) Amending the prior $4.6m PS&E in programming for FY18/19 R/W SUP (CT) to $2.3m 18/19 and $2.3m CON SUP (CT) in FY 19/20. Additional R/W programming of 2018 STIP CON 91,787 2,309 2,308 4,002 4,002 4,002 108,410 PPM share for FY 20/21-FY TOTAL 91,787 2,309 2,308 4,002 4,002 4,002 108,410 22/23.

2018 Los Angeles County Regional Transportation Improvement Program 68 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 0700021254 9001 Project Title: Planning, Programming and Monitoring (PPM)

Fund No. 3: Local Funds - Local Transportation Funds (LTF) Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 3,529 3,529 TOTAL 3,529 3,529

Fund No. 4: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 5: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 69 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 0700021254 9001 SECTION 1 - All Projects Project Background

Programming Change Requested

Reason for Proposed Change

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 70 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing ProjecT) Yes Date: 8/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 28620 0713000217 4356 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA 138 55.2 56.2 Caltrans MPO Element SCAG Capital Outlay Project Manager/Contact Phone E-mail Address Anthony Kim (213)897-8812 [email protected] Project Title Route 138 Widening, Segment 6 Location (Project Limits), Description ( Scope of Work) Los Angeles County In Littlerock from 87th Street E to 96th Street E.

Widen conventional highway from 2 lanes to 4 lanes, with standard shoulder widths and median lane.

Component Implementing Agency PA&ED Caltrans PS&E Caltrans Right of Way Caltrans Construction Caltrans Legislative Districts Assembly: 36 Senate: 17 Congressional: 25 Project Benefits

The existing facility consists of one lane of travel in each direction. The new facility will provide for two lanes of travel in each direction as well as a median lane and standard width shoulders which will improve safety and capacity.

Purpose and Need This project will serve to relieve congestion and enhance safety along the Route 138 Corridor. The area of Antelope Valley is one of the fastest growing areas in Los Angeles County. In addition, Route 138, between Route 14 in the West and I-15 in the East, has been designated as a safety corridor. Although minor improvements have been made, the addition of 2 lanes will improve mobility and enhance safety. Category Outputs/Outcomes Unit Total State Highway Road Construction Mixed Flow lane-miles constructed Miles 3

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis No Includes Sustainable Communities Strategy Goals Yes Reduces Greenhouse Gas Emissions Yes Project Milestone Existing Proposed Project Study Report Approved 10/07/91 Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type EIR/FONSI 11/15/00 Draft Project Report End Environmental Phase (PA&ED Milestone) 03/30/01 Begin Design (PS&E) Phase End Design Phase (Ready to List for Advertisement Milestone) 06/09/17 Begin Right of Way Phase End Right of Way Phase (Right of Way Certification Milestone) 06/09/17 Begin Construction Phase (Contract Award Milestone) 12/02/18 End Construction Phase (Construction Contract Acceptance Milestone) 03/31/21 Begin Closeout Phase End Closeout Phase (Closeout Report) 03/31/23 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 71 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 8/14/17 Additional Information The corridor has been identified in 2001 (Project Report for EA 127200, 104830, 188410, 18420 and 188430). Since then various segments were created, identified and funded based on effectiveness and funding availability. The last supplemental report was completed in 2013 showing the latest update for the corridor. Since then, remaining segments 6, 9 and 13 were programmed. However, during the last programmng cycle (FY 16), RIP funding was removed from these projects.

Segment 6 has achieved RTL status, however, project needs support and capital funds. The District proposes that Los Angeles County Metropolitan Transportation Authority (LACMTA) fund the project.

As a prior STIP project, reversible lane consideration is not applicable to this project. Further, this project is a segment of a larger highway improvement and reversible lanes would not be compatible with the other highway segments constructed or being constructed.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 72 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 8/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA, , 138, , 28620 0713000217 4356 Project Title: Route 138 Widening, Segment 6

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) Caltrans PS&E 3,500 3,500 Caltrans R/W SUP (CT) 1,600 1,600 Caltrans CON SUP (CT) 3,000 3,000 Caltrans R/W 5,600 5,600 Caltrans CON 10,700 10,700 Caltrans TOTAL 10,700 13,700 24,400 Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E 3,500 600 4,100 R/W SUP (CT) 1,600 1,100 2,700 CON SUP (CT) 4,750 4,750 R/W 5,600 5,600 CON 15,000 15,000 TOTAL 10,700 21,450 32,150

Fund No. 1: RIP - National Hwy System (NH) Program Code Existing Funding ($1,000s) 20.XX.075.600 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) Los Angeles County Metropolitan T PS&E R/W SUP (CT) CON SUP (CT) R/W 4,500 4,500 CON TOTAL 4,500 4,500 Proposed Funding ($1,000s) Notes E&P (PA&ED) Proposed RIP Funding. PS&E Restored deletions from the R/W SUP (CT) 2016 STIP. CON SUP (CT) 4,750 4,750 R/W 4,500 4,500 CON 15,000 15,000 TOTAL 4,500 19,750 24,250

Fund No. 2: RSTP - STP Local (STPL) Program Code Existing Funding ($1,000s) 20.30.010.810 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 3,500 3,500 R/W SUP (CT) 1,600 1,600 CON SUP (CT) R/W 1,100 1,100 CON TOTAL 6,200 6,200 Proposed Funding ($1,000s) Notes E&P (PA&ED) Additional RSTP funding PS&E 3,500 600 4,100 per agreement R/W SUP (CT) 1,600 1,100 2,700 CON SUP (CT) R/W 1,100 1,100 CON TOTAL 6,200 1,700 7,900

2018 Los Angeles County Regional Transportation Improvement Program 73 Fund No. 3: Future Need - Future Funds (NO-FUND) Program Code Existing Funding ($1,000s) FUTURE Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E Propose RIP funding for support R/W SUP (CT) CON SUP (CT) 3,000 3,000 R/W CON 10,700 10,700 TOTAL 13,700 13,700 Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 4: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 5: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 74 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 8/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 138 28620 0713000217 4356 SECTION 1 - All Projects Project Background Route 138, from Avenue T in the City of Palmdale to junction with Route 18 in Llano, has been designated as a Corridor. This Corridor has been divided into several Segments, each of which is a separate project. Not all Segments (projects) are programmed. There are 7 Segments (projects) which are programmed in "Phase I". The first project is completed in construction, with the last project in Phase I scheduled to be in construction in Spring, 2012. This project is in Phase II and will be funded by Los Angeles County Metropolitan Transporation Authority (LACMTA).

Programming Change Requested Proposing construction support and capital needs to be programmed.

Reason for Proposed Change Project construction phase was un-programmed due to STIP funding shortfall during 2016 program cycle. Design continued and project achieved RTL status. However, additional Design and RW support is necessary to accommodate for contract advertisement, award and approval process and additional needs for RW efforts.

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 75 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 8/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 28630 0713000216 4357 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA 138 66 70 Caltrans 18 MPO Element SCAG Capital Outlay Project Manager/Contact Phone E-mail Address Anthony Kim (213)897-8812 [email protected] Project Title Route 138 Widening, Segment 13 Location (Project Limits), Description ( Scope of Work) In Los Angeles County In Llano, from 0.4 mile West of 190 th Street East to Route 18 Junction.

Widen conventional highway from 2 lanes to 4 lanes with standard shoulder widths and median lanes.

Component Implementing Agency PA&ED Caltrans PS&E Caltrans Right of Way Caltrans Construction Caltrans Legislative Districts Assembly: 36 Senate: 17 Congressional: 25 Project Benefits

The existing facility consists of one lane of travel in each direction. The new facility will provide for two lanes of travel in each direction as well as a median lane and standard width shoulders which will improve safety and capacity.

Purpose and Need This project will serve to relieve congestion and enhance safety along the Route 138 Corridor. The area of Antelope Valley is one of the fastest growing areas in Los Angeles County. In addition, Route 138, between Route 14 in the West and I-15 in the East, has been designated as a safety corridor. Although minor improvements have been made, the addition of 2 lanes will improve mobility and enhance safety. Category Outputs/Outcomes Unit Total State Highway Road Construction Mixed Flow lane-miles constructed Miles 9

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis No Includes Sustainable Communities Strategy Goals Yes Reduces Greenhouse Gas Emissions Yes Project Milestone Existing Proposed Project Study Report Approved 10/07/91 Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type ND/FONSI 11/15/00 Draft Project Report End Environmental Phase (PA&ED Milestone) 03/30/01 Begin Design (PS&E) Phase 07/31/18 End Design Phase (Ready to List for Advertisement Milestone) 07/31/20 Begin Right of Way Phase 07/31/18 End Right of Way Phase (Right of Way Certification Milestone) 07/31/20 Begin Construction Phase (Contract Award Milestone) 01/15/21 End Construction Phase (Construction Contract Acceptance Milestone) 01/16/23 Begin Closeout Phase End Closeout Phase (Closeout Report) 06/01/26 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 76 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 8/14/17 Additional Information The corridor has been identified in 2001 (Project Report for EA 127200, 104830, 188410, 18420 and 188430). Since then various segments were created, identified and funded based on effectiveness and funding availability. The last supplemental report was completed in 2013 showing the latest update for the corridor. Since then, remaining segments 6, 9 and 13 were programmed. However, during the last programmng cycle (FY 16), RIP funding was removed from these projects.

Segment 13 was in design and currently on-hold when the project funding was removed. The District proposes the Los Angeles County Metropolitan Transportation Authority (LACMTA) fund the project for PS&E, Right-of-Way, through Construction with RIP funds.

As a prior STIP project, reversible lane consideration is not applicable to this project. Further, this project is a segment of a larger highway improvement and reversible lanes would not be compatible with the other highway segments constructed or being constructed.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 77 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 8/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA, , 138, 18, 28630 0713000216 4357 Project Title: Route 138 Widening, Segment 13

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) Caltrans PS&E 6,000 6,000 Caltrans R/W SUP (CT) 6,500 6,500 Caltrans CON SUP (CT) Caltrans R/W 10,500 10,500 Caltrans CON 3,600 3,600 Caltrans TOTAL 23,000 3,600 26,600 Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E 4,000 4,000 8,000 R/W SUP (CT) 6,500 6,500 CON SUP (CT) 12,000 12,000 R/W 9,500 9,500 CON 55,000 55,000 TOTAL 20,000 4,000 67,000 91,000

Fund No. 1: RIP - National Hwy System (NH) Program Code Existing Funding ($1,000s) 20.XX.075.600 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) Los Angeles County Metropolitan T PS&E R/W SUP (CT) CON SUP (CT) R/W 9,500 9,500 CON TOTAL 9,500 9,500 Proposed Funding ($1,000s) Notes E&P (PA&ED) Carry over from previous PS&E programming R/W SUP (CT) CON SUP (CT) R/W 9,500 9,500 CON TOTAL 9,500 9,500

Fund No. 2: RSTP - STP Local (STPL) Program Code Existing Funding ($1,000s) 20.30.010.810 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 6,000 6,000 R/W SUP (CT) 6,500 6,500 CON SUP (CT) R/W 1,000 1,000 CON 3,600 3,600 TOTAL 13,500 3,600 17,100 Proposed Funding ($1,000s) Notes E&P (PA&ED) Allocate $2M from PS&E PS&E 4,000 4,000 Support and $1M from RW R/W SUP (CT) 6,500 6,500 Capital to Seg 9 RW CON SUP (CT) Capital. R/W CON TOTAL 10,500 10,500

2018 Los Angeles County Regional Transportation Improvement Program 78 Fund No. 3: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Restoring Prior Deletions PS&E 4,000 4,000 from 2016 STIP. Funding R/W SUP (CT) through Construction CON SUP (CT) 12,000 12,000 Phase. R/W CON 55,000 55,000 TOTAL 4,000 67,000 71,000

Fund No. 4: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 5: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 79 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 8/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 138 18 28630 0713000216 4357 SECTION 1 - All Projects Project Background Route 138, from Avenue T in the City of Palmdale to junction with Route 18 in Llano, has been designated as a Corridor. This Corridor has been divided into several Segments, each of which is a separate project. Not all Segments (projects) are programmed. There are 7 Segments (projects) which are programmed in "Phase I". The first project is completed in construction, with the last project in Phase I scheduled to be in construction in Spring, 2012. This project is in Phase II and will be funded by Los Angeles County Metropolitan Transportation Authority (LACMTA).

Programming Change Requested Programming PS&E and Construction with RIP

Reason for Proposed Change Project was un-programmed due to STIP funding shortfall during 2016 program cycle. Project is on-hold, until additional support funding is available to update the project. Capital cost estimate was adjusted to meet current forecast of construction capital cost.

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded In adidition to completing the design process, the project PS&E and documents need to be updated to meet current guidelines. The effort to meet current guidelines will require design team to revisit and modify/adjust the design package. The additional effort will be funded by RIP funding.

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 80 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 28600 0713000500 4353 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA 138 53.2 54.2 Caltrans MPO Element SCAG Capital Outlay Project Manager/Contact Phone E-mail Address Anthony Kim 213-897-8812 Anthony [email protected] Project Title Widen Conventional Highway (SEG 4) Location (Project Limits), Description ( Scope of Work) In Los Angeles County in Palmdale from 0.5 mile west of 72th Street East to 77th Street East

Widen conventional highway from 2 lanes to 4 lanes, with standard shoulder width and median lane.

Component Implementing Agency PA&ED Caltrans PS&E Caltrans Right of Way Caltrans Construction Caltrans Legislative Districts Assembly: 36 Senate: 21 Congressional: 25 Project Benefits

This project will serve to relieve congestion and enhance safety along the Route 138 Corridor. The area of Antelope Valley is one of the fastest growing areas in Los Angeles County. In addition, Route 138, between Route 14 in the West and I-15 in the East, has been designated as a safety corridor. Although minor improvements have been made, the addition of 2 lanes will improve mobility and enhance safety.

Purpose and Need The existing facility consists of one lane in each direction. The new facility will provide for two lanes in each direction as well as a median lane and standard width shoulders which will improve safety. The additional lanes will increase capacity. More vehicles will be able to use Route 138 as a by-pass route, thus relieving the congestion on such freeways as I-5, I-10 and I-15.

Category Outputs/Outcomes Unit Total State Highway Road Construction Mixed Flow lane-miles constructed Miles 3

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis Yes Includes Sustainable Communities Strategy Goals Y/N Reduces Greenhouse Gas Emissions Y/N Project Milestone Existing Proposed Project Study Report Approved 10/07/91 Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type EIR/FONSI 11/15/00 Draft Project Report End Environmental Phase (PA&ED Milestone) 03/30/01 Begin Design (PS&E) Phase 07/31/18 End Design Phase (Ready to List for Advertisement Milestone) 07/31/20 Begin Right of Way Phase 07/31/18 End Right of Way Phase (Right of Way Certification Milestone) 07/15/20 Begin Construction Phase (Contract Award Milestone) 12/14/20 End Construction Phase (Construction Contract Acceptance Milestone) 02/01/23 Begin Closeout Phase End Closeout Phase (Closeout Report) 02/01/25 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 2018654-6410 Los Angeles or TDD (916) County 654-3880 Regional or write RecordsTransportation and Forms ImprovementManagement, 1120 Program N Street, MS-89, Sacramento,81 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information The corridor has been identified in 2001 (Project Report for EA 127200, 104830, 188410, 18420 and 188430). Since then, various segments were created, identified, and built based on effectiveness and funding availability. The last supplemental report was completed in 2013 showing the latest update for the corridor. Since then, remaining segments 6, 9 and 13 were programmed.

Segment 4 is the last remaining segment that's identified in the original corridor that has not been constructed. Completion of this segment will ensure consistent facility capacity between major regions to facilitate freight movement and passenger vehicle interregional travel by closing the last gap of the corridor.

The District proposed to fund the design this project (PS&E) with IIP fund to finalize closing the "gap" of the corridor. The proposal was not included in the Draft ITIP.

The current proposal is for Los Angeles County Metropolitan Transportation Authority (LACMTA) to fund the design, right-of-way, and construction with RIP to finalize closing the "gap" of the corridor.

This project is a segment of a larger highway improvement and reversible lanes would not be compatible with the other highway segments constructed or being constructed.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 82 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 138 28600 0713000500 4353 Project Title: Widen Conventional Highway (SEG 4)

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) Caltrans PS&E Caltrans R/W SUP (CT) Caltrans CON SUP (CT) Caltrans R/W Caltrans CON Caltrans TOTAL Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E 5,250 5,250 R/W SUP (CT) 6,700 6,700 CON SUP (CT) 4,000 4,000 R/W 9,000 9,000 CON 15,000 15,000 TOTAL 5,250 15,700 19,000 39,950

Fund No. 1: RIP Program Code Existing Funding ($1,000s) 20.XX.025.700 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Proposed RIP funding for PS&E 5,250 5,250 the project for design R/W SUP (CT) 6,700 6,700 through construction. CON SUP (CT) 4,000 4,000 Design to begin July 2018. R/W 9,000 9,000 CON 15,000 15,000 TOTAL 5,250 15,700 19,000 39,950

Fund No. 2: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 83 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 138 28600 0713000500 4353 SECTION 1 - All Projects Project Background Route 138 , from Avenue T in the City of Palmdale to junction with Route 18 in Llano, has been designated as a Corridor. This Corridor has been divided into several Segments, each of which is a separate project. Not all Segments (projects) are programmed.

Programming Change Requested Program new project with RIP funding for PS&E, ROW, and CON to close the gap of the previously identified corridor.

Reason for Proposed Change NA

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded NA

Other Significant Information This project will add one lane in each direction and a median turn lane.

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 84 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 21060 0700020800 2741 8349 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA 71 R0.5 R4.8 Caltrans MPO Element SCAG Capital Outlay Project Manager/Contact Phone E-mail Address John K. Lee (213)897-8623 [email protected] Project Title Route 71 Expressway to Freeway Conversion (Interstate 10 to Route 60) Location (Project Limits), Description ( Scope of Work) In Pomona, between Interstate 10 and Route 60. Add one mixed flow lane and one HOV lane in each direction on Route 71. (TCRP #50)

Component Implementing Agency PA&ED Caltrans PS&E Caltrans Right of Way Caltrans Construction Caltrans Legislative Districts Assembly: 59, 61 Senate: 29, 32 Congressional: 26, 38 Project Benefits This project proposes to upgrade 4 miles of existing four-lane expressway to an eight lane freeway on Route 71 from Interstate 10 to Route 60 in Los Angeles County. The purpose of the project is to provide freeway speeds and capacity, relieve existing traffic congestion, increase traffic safety and accomodate future traffic demands resulting from regional growth.

Purpose and Need Route 71 is a major regional highway transportation facility traversing parts of Los Angeles, San Bernardino, and Riverside County. The route serves heavy commute traffic originating in the communities of Chino, Ontario and Pomona that is destined for employment centers in Orange and Los Angeles Counties. The purpose of this project is to alleviate traffic congestion by increasing capacity to handle the forecasted traffic volumes in coming years due to extensive development in the region. Category Outputs/Outcomes Unit Total State Highway Road Construction HOV/HOT lane-miles constructed Miles 8 State Highway Road Construction Mixed Flow lane-miles constructed Miles 8

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis No Includes Sustainable Communities Strategy Goals No Reduces Greenhouse Gas Emissions No Project Milestone Existing Proposed Project Study Report Approved Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type Draft Project Report End Environmental Phase (PA&ED Milestone) Begin Design (PS&E) Phase 07/01/16 End Design Phase (Ready to List for Advertisement Milestone) 08/14/19 Begin Right of Way Phase 07/01/17 End Right of Way Phase (Right of Way Certification Milestone) 07/12/19 Begin Construction Phase (Contract Award Milestone) 02/21/20 End Construction Phase (Construction Contract Acceptance Milestone) 07/14/23 Begin Closeout Phase 08/15/23 End Closeout Phase (Closeout Report) 08/18/26 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 85 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information This was a prior STIP project. As it is not a new project, the reversible lane consideration does not apply.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 86 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO Alt Proj. ID 07 LA 71 21060 0700020800 2741 Project Title: Route 71 Expressway to Freeway Conversion (Interstate 10 to Route 60)

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) 4,049 4,049 Caltrans PS&E 21,343 21,343 Caltrans R/W SUP (CT) Caltrans CON SUP (CT) Caltrans R/W Caltrans CON Caltrans TOTAL 25,392 25,392 Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) 4,049 4,049 PS&E 21,343 21,343 R/W SUP (CT) 4,000 4,000 CON SUP (CT) 10,847 20,000 30,847 R/W 33,000 33,000 CON 234,000 234,000 TOTAL 62,392 244,847 20,000 327,239

Fund No. 1: RIP - State Cash (ST-CASH) Program Code Existing Funding ($1,000s) 20.XX.075.600 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) 1,592 1,592 Los Angeles County Metropolitan T PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 1,592 1,592 Proposed Funding ($1,000s) Notes E&P (PA&ED) 1,592 1,592 PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 1,592 1,592

Fund No. 2: TCRP (Committed) - Traffic Congestion Relief Fund (TCRF) Program Code Existing Funding ($1,000s) 20.XX.710.870 Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) 2,457 2,457 PS&E 11,143 11,143 R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 13,600 13,600 Proposed Funding ($1,000s) Notes E&P (PA&ED) 2,457 2,457 PS&E 11,143 11,143 R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 13,600 13,600

2018 Los Angeles County Regional Transportation Improvement Program 87 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO Alt Proj. ID 07 LA 71 21060 0700020800 2741 Project Title: Route 71 Expressway to Freeway Conversion (Interstate 10 to Route 60)

Fund No. 3: 2016 Earmark Repurpose Fund Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 10,200 10,200 R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 10,200 10,200 Proposed Funding ($1,000s) Notes E&P (PA&ED) Federal Repurposed funds PS&E 10,200 10,200 R/W SUP (CT) 4,000 4,000 CON SUP (CT) 10,847 10,847 R/W 33,000 33,000 CON TOTAL 47,200 10,847 58,047

Fund No. 4: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 2018 STIP request. Funds PS&E requested in 20/21 in order to R/W SUP (CT) avoid requesting more than the CON SUP (CT) 20,000 20,000 minimum share in the first 2 yrs. Sufficient earmark funding R/W in FY 20 to initiate CON construction. TOTAL 20,000 20,000

Fund No. 5: Measure M Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Measure M - local tax PS&E measure R/W SUP (CT) CON SUP (CT) R/W CON 190,000 190,000 TOTAL 190,000 190,000

2018 Los Angeles County Regional Transportation Improvement Program 88 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO Alt Proj. ID 07 LA 71 21060 0700020800 2741 Project Title: Route 71 Expressway to Freeway Conversion (Interstate 10 to Route 60)

Fund No. 6: SB 1 Funds Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) $44 million to be sought from PS&E SB 1 programs. If the project is R/W SUP (CT) not funded through SB 1 CON SUP (CT) programs, will complete the funding with local funding R/W sources. CON 44,000 44,000 TOTAL 44,000 44,000

Fund No. 7: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 8: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 89 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO Alt Proj. 07 LA 71 21060 0700020800 2741 SECTION 1 - All Projects Project Background Route 71 is a major regional highway transportation facitility transversing parts of Los Angeles, San Bernardino, and Riverside County. It is a connecting link for major east-west corridors passing through the area and serves as an inland passageway for interregional travel between San Diego and the eastern portion of the Los Angeles area. The route also serves heavy commute traffic originating in the communities of Chino, Ontario and Pomona that is destined for employment centers in Orange and Los Angeles Counties. The purpose of this project is to alleviate traffic congestion by increasing capacity on Route 71 from Interstate 10 to Route 60 to handle the forecasted traffic volumes in coming years due to extensive development in the region.

Programming Change Requested Metro is requesting 2018 RIP funds in anticipation of the construction support cost needs for the project.

Reason for Proposed Change Metro is requesting 2018 RIP funds to fully fund the construction support component of the project.

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date John K. Lee Project Manager

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 90 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 07-4296 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA Los Angeles County Metropolitan Transportation Authority MPO Element SCAG Mass Transit Project Manager/Contact Phone E-mail Address Vincent Lorenzo (213) 922-4320 [email protected] Project Title East San Fernando Valley North-South Transit Project (East) Location (Project Limits), Description ( Scope of Work) East San Fernando Valley North-South Transit Project was identified in the TCRP program as part of the Los Angeles-San Fernando Valley North-South Transit Extension. The design build project scope includes constructing a North-South transit corridor to improve north/south transit service in the eastern San Fernando Valley along the busy Van Nuys Boulevard and San Fernando Road Corridors. The transit service will travel between the Metro Orange Line to the south, and the Sylmar/San Fernando Metrolink Station to the north, via the median of Van Nuys Boulevard (6.7 miles) and along or adjacent to San Fernando Road to the north (2.5 miles), a total distance of 9.2 miles. A Locally Preferred Alternative (LPA) will be selected to determine whether this high capacity transit project will be a Bus Rapid Transit (BRT) or a Light Rail (LRT) project. Regardless of mode, the project will deliver 9.2 miles of high capacity transit service.

Component Implementing Agency PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Los Angeles County Metropolitan Transportation Authority Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts Assembly: 40, 41 Senate: 23, 20 Congressional: 27, 30 Project Benefits This design build project will improve north/south transit service in the eastern San Fernando Valley along the busy Van Nuys Boulevard and San Fernando Road Corridors. Ridership is anticipated to increase by 50-80% in the corridor by 2040. A Locally Preferred Alternative (LPA) will be selected to determine whether this high capacity transit project will be a Bus Rapid Transit (BRT) or a Light Rail (LRT) project. Regardless of mode, the project will deliver 9.2 miles of high capacity transit service. Purpose and Need The line will increase the intermodal connectivity between bus and commuter rail in the San Fernando Valley, connecting with the Metro Orange Line to the south, and the Sylmar/San Fernando Metrolink Station to the north.

Category Outputs/Outcomes Unit Total Intercity Rail/Mass Trans Miles of new track Miles 9.2 Intercity Rail/Mass Trans Station improvements each 14-28

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis No Includes Sustainable Communities Strategy Goals Yes Reduces Greenhouse Gas Emissions Yes Project Milestone Existing Proposed Project Study Report Approved 08/01/01 Begin Environmental (PA&ED) Phase 09/01/06 Circulate Draft Environmental Document Document Type EIR 09/01/17 Draft Project Report End Environmental Phase (PA&ED Milestone) 12/01/18 Begin Design (PS&E) Phase End Design Phase (Ready to List for Advertisement Milestone) Begin Right of Way Phase 07/01/20 End Right of Way Phase (Right of Way Certification Milestone) 11/01/21 Begin Construction Phase (Contract Award Milestone) 11/01/21 End Construction Phase (Construction Contract Acceptance Milestone) 06/31/27 Begin Closeout Phase 07/01/27 End Closeout Phase (Closeout Report) 06/31/29 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 91 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 07-4296 Project Title: East San Fernando Valley North-South Transit Project (East)

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan PS&E LosT Angeles i County Ahi Metropolitan R/W SUP (CT) LosT Angeles t ti County A th Metropolitan it CON SUP (CT) LosT Angeles t ti County A th Metropolitan it R/W LosT Angeles i County Ahi Metropolitan CON LosT Angeles t ti County A th Metropolitan it TOTAL T t ti A th it Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) 38,497 38,497 PS&E R/W SUP (CT) CON SUP (CT) R/W 125,000 125,000 CON 400,000 830,880 153,223 1,384,103 TOTAL 38,497 525,000 830,880 153,223 1,547,600

Fund No. 1: TCRP Tier (1) Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 1,900 1,900 PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 1,900 1,900

Fund No. 2: TCRP (Tier II) Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 27,000 27,000 TCRP in statute was only PS&E partially allocated prior to R/W SUP (CT) the TCRP program being CON SUP (CT) cancelled in 2017. $53 R/W million left unfunded from CON this source. TOTAL 27,000 27,000

2018 Los Angeles County Regional Transportation Improvement Program 92 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 07-4296 Project Title: East San Fernando Valley North-South Transit Project (East)

Fund No. 3: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) For ROW and design/ PS&E construction expenses R/W SUP (CT) expected to be completed CON SUP (CT) under a design-build R/W 34,630 34,630 contract. Cashflowed to CON 17,775 54,733 72,508 assist with STIP capacity TOTAL 34,630 17,775 54,733 107,138 balancing.

Fund No. 4: RIP Tier II Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Additional RIP shares PS&E requested. R/W SUP (CT) CON SUP (CT) R/W CON 98,490 98,490 TOTAL 98,490 98,490

Fund No. 5: FTA Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 968 968 PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 968 968

2018 Los Angeles County Regional Transportation Improvement Program 93 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 07-4296 Project Title: East San Fernando Valley North-South Transit Project (East)

Fund No. 6: Other Local Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 8,629 8,629 PS&E R/W SUP (CT) CON SUP (CT) R/W 90,370 90,370 CON 100,000 813,105 913,105 TOTAL 8,629 190,370 813,105 1,012,104

Fund No. 7: Other SB 1 Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) $300 million to be sought PS&E out of SB 1 programs and R/W SUP (CT) TIRCP. If SB 1 funds are CON SUP (CT) not secured, local sources R/W will be utilized to fully fund CON 300,000 300,000 the project. TOTAL 300,000 300,000

Fund No. 8: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 94 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 07-4296 SECTION 1 - All Projects Project Background

Programming Change Requested

Reason for Proposed Change

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 95 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 TBD County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA Los Angeles County Metropolitan Transportation Authority MPO Element SCAG Mass Transit Project Manager/Contact Phone E-mail Address

Project Title Bus Acquisition 1 Location (Project Limits), Description ( Scope of Work) Metro's bus acquisition project is designed to maintain a state of good repair of our bus fleet through the scheduled replacement of vehicles that allows Metro's buses to be retired and replaced after the end of their "service life" as defined by the FTA. The scope of this project includes 305 standard buses over three years, delivering approximately 150 buses a year.

Component Implementing Agency PA&ED PS&E Right of Way Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts Assembly: Senate: Congressional: Project Benefits

Bus replacement ensures the safest most reliable vehicles providing the highest quality service and passenger service. Improves the technology, reliability, and performance of Metro's bus fleet.

Purpose and Need The bus acquisition project is required to maintain a state of good repair of our bus fleet through the scheduled replacement of vehicles that allows Metro's buses to be retired and replaced after the end of their "service life" as defined by the FTA. The scope of this project includes 305 standard buses over three years, delivering approximately 150 buses a year.

Category Outputs/Outcomes Unit Total Intercity Rail/Mass Trans Rail cars/ transit vehicles each 305

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis No Includes Sustainable Communities Strategy Goals Yes Reduces Greenhouse Gas Emissions Yes Project Milestone Existing Proposed Project Study Report Approved Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type N/A Draft Project Report End Environmental Phase (PA&ED Milestone) Begin Design (PS&E) Phase End Design Phase (Ready to List for Advertisement Milestone) Begin Right of Way Phase End Right of Way Phase (Right of Way Certification Milestone) Begin Construction Phase (Contract Award Milestone) 07/01/19 End Construction Phase (Construction Contract Acceptance Milestone) 09/30/21 Begin Closeout Phase End Closeout Phase (Closeout Report) For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 96 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD Project Title: Bus Acquisition 1

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) Los Angeles County Metropolitan R/W T i Ahi CON Los Angeles County Metropolitan TOTAL T t ti A th it Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 215,805 215,805 TOTAL 215,805 215,805

Fund No. 1: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 30,246 30,246 TOTAL 30,246 30,246

Fund No. 2: TDA Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 61,918 61,918 TOTAL 61,918 61,918

2018 Los Angeles County Regional Transportation Improvement Program 97 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD Project Title: Bus Acquisition 1

Fund No. 3: 5307 Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) to be obligated over PS&E multiple years R/W SUP (CT) CON SUP (CT) R/W CON 29,197 29,197 TOTAL 29,197 29,197

Fund No. 4: 5339 Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) to be obligated over PS&E multiple years R/W SUP (CT) CON SUP (CT) R/W CON 37,790 37,790 TOTAL 37,790 37,790

Fund No. 5: STA Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 22,704 22,704 TOTAL 22,704 22,704

2018 Los Angeles County Regional Transportation Improvement Program 98 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD Project Title: Bus Acquisition 1

Fund No. 6: Other Local Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 33,950 33,950 TOTAL 33,950 33,950

Fund No. 7: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 8: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 99 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD SECTION 1 - All Projects Project Background

Programming Change Requested

Reason for Proposed Change

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 100 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) Yes Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 TBD County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA Los Angeles County Metropolitan Transportation Authority MPO Element SCAG Mass Transit Project Manager/Contact Phone E-mail Address

Project Title Bus Acquisition- Project 2 Location (Project Limits), Description ( Scope of Work) Metro's bus acquisition project is designed to maintain a state of good repair of our bus fleet through the scheduled replacement of vehicles that allows Metro's buses to be retired and replaced after the end of their "service life" as defined by the FTA. The scope of this project includes 305 standard buses over three years, delivering approximately 150 buses a year.

Component Implementing Agency PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts Assembly: Senate: Congressional: Project Benefits

Bus replacement ensures the safest most reliable vehicles providing the highest quality service and passenger service. Improves the technology, reliability, and performance of Metro's bus fleet.

Purpose and Need The bus acquisition project is required to maintain a state of good repair of our bus fleet through the scheduled replacement of vehicles that allows Metro's buses to be retired and replaced after the end of their "service life" as defined by the FTA. The scope of this project includes 305 standard buses over three years, delivering approximately 150 buses a year.

Category Outputs/Outcomes Unit Total Intercity Rail/Mass Trans Rail cars/ transit vehicles each 305

ADA Improvements Yes Bike/Ped Improvements No Reversible Lane analysis No Includes Sustainable Communities Strategy Goals Yes Reduces Greenhouse Gas Emissions Yes Project Milestone Existing Proposed Project Study Report Approved Begin Environmental (PA&ED) Phase Circulate Draft Environmental Document Document Type N/A Draft Project Report End Environmental Phase (PA&ED Milestone) Begin Design (PS&E) Phase End Design Phase (Ready to List for Advertisement Milestone) Begin Right of Way Phase End Right of Way Phase (Right of Way Certification Milestone) Begin Construction Phase (Contract Award Milestone) 07/01/22 End Construction Phase (Construction Contract Acceptance Milestone) 06/30/24 Begin Closeout Phase End Closeout Phase (Closeout Report) For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 101 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information Reversible lane consideration not applicable.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 102 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD Project Title: Bus Acquisition- Project 2

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan PS&E LosT Angeles i County Ahi Metropolitan R/W SUP (CT) T t ti A th it CON SUP (CT) Los Angeles County Metropolitan R/W T i Ahi CON Los Angeles County Metropolitan TOTAL T t ti A th it Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 312,246 312,246 TOTAL 312,246 312,246

Fund No. 1: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) LA County RIP funding PS&E proposed. R/W SUP (CT) CON SUP (CT) R/W CON 17,096 17,096 TOTAL 17,096 17,096

Fund No. 2: TDA Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 83,400 83,400 TOTAL 83,400 83,400

2018 Los Angeles County Regional Transportation Improvement Program 103 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD Project Title: Bus Acquisition- Project 2

Fund No. 3: 5307 Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 32,950 32,950 TOTAL 32,950 32,950

Fund No. 4: 5339 Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 43,800 43,800 TOTAL 43,800 43,800

Fund No. 5: STA Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 22,000 22,000 TOTAL 22,000 22,000

2018 Los Angeles County Regional Transportation Improvement Program 104 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD Project Title: Bus Acquisition- Project 2

Fund No. 6: SB 1 Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Will look to other SB 1 PS&E formula or discretionary R/W SUP (CT) funds. Local funds to be CON SUP (CT) substituted where SB1 R/W sources do not fully fund CON 30,000 30,000 the project. TOTAL 30,000 30,000

Fund No. 7: Local Funds Prop A/Prop C Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON 83,000 83,000 TOTAL 83,000 83,000

Fund No. 8: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 105 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA TBD SECTION 1 - All Projects Project Background

Programming Change Requested

Reason for Proposed Change

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 106 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) No Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 27300 0700021122 4071 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA 710 6 6.4 City of Long Beach MPO Element SCAG Project Manager/Contact Phone E-mail Address Traci Gleason 949.300.7910 [email protected] Project Title I-710 South Early Action Project - Shoemaker Bridge Replacement Location (Project Limits), Description ( Scope of Work) The Project is located at the southern segment of State Route 710 in the City and is bisected by the Los Angeles River. Project limits are generally bounded by 9th and 10th Street ramp connections and Shoreline Drive to the west, Magnolia Avenue to the east, Ocean Boulevard and West Shoreline Drive to the south, and Anaheim Street to the north. The Project limits on the east side extend beyond Magnolia Avenue along Anaheim, 7th and 6th Street to Atlantic Boulevard. The Project includes build alternatives containing the removal or repurposing of the existing Shoemaker Bridge and design options for the easterly end of the bridge. All of the build alternatives include the construction of a new bridge located just south of the existing Shoemaker Bridge

Component Implementing Agency PA&ED City of Long Beach PS&E City of Long Beach Right of Way TBD Construction TBD Legislative Districts Assembly: 70 Senate: 33 Congressional: 47 Project Benefits The proposed Project would result in improved safety operations and connectivity between downtown Long Beach and regional transportation facilities as well as accommodate future planned improvements and expansion of Cesar E. Chavez and Drake Parks.

Purpose and Need Purpose: 1) Provide a structure and highway facility that meets current structural and geometric design standards; 2) Provide a facility that is compatible with planned freeway improvements and downtown development projects; 3) Improve connectivity from the downtown area to surrounding communities and adjacent recreational use areas; and 4) Improve safety and operations for all modes of transportation.The existing bridge has structural deficiencies and a high accident rate due to non-standard geometric features that cannot be upgraded to current State highway standards. The Project is needed to improve safety, operations and connectivity between downtown Long Beach and regional transportation facilities. The Project is also needed to accommodate planned improvements in the adjacent areas.

Category Outputs/Outcomes Unit Total State Highway Road Construction Operational Improvements Miles 0.5 Local streets and roads Operational Improvements Miles 3 Local streets and roads Pedestrian/Bicycle Facilities miles constructed Miles 4

ADA Improvements Yes Bike/Ped Improvements Yes Reversible Lane analysis Yes Includes Sustainable Communities Strategy Goals Yes Reduces Greenhouse Gas Emissions Yes Project Milestone Existing Proposed Project Study Report Approved 07/01/08 Begin Environmental (PA&ED) Phase 07/01/10 Circulate Draft Environmental Document Document Type EIR/EIS 06/01/18 Draft Project Report 06/01/18 End Environmental Phase (PA&ED Milestone) 11/01/18 Begin Design (PS&E) Phase 12/09/16 End Design Phase (Ready to List for Advertisement Milestone) 11/01/19 Begin Right of Way Phase End Right of Way Phase (Right of Way Certification Milestone) Begin Construction Phase (Contract Award Milestone) End Construction Phase (Construction Contract Acceptance Milestone) Begin Closeout Phase End Closeout Phase (Closeout Report) For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654- ADA Notice 20186410 orLos TDD Angeles (916) 654-3880 County or Regionalwrite Records Transportation and Forms Management, Improvement 1120 N ProgramStreet, MS-89, Sacramento,107 CA STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information Reversible lanes were considered but are not applicable as this is a bridge replacement project.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 108 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 710 27300 0700021122 4071 Project Title: I-710 South Early Action Project - Shoemaker Bridge Replacement

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) City of Long Beach PS&E City of Long Beach R/W SUP (CT) TBD CON SUP (CT) TBD R/W TBD CON TBD TOTAL Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) PS&E 14,000 14,000 R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 14,000 14,000

Fund No. 1: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 2018 STIP Request R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Form LA County APDE PS&E 14,000 14,000 Share R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 14,000 14,000

Fund No. 2: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 109 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 710 27300 0700021122 4071 SECTION 1 - All Projects Project Background

Programming Change Requested

Reason for Proposed Change

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 110 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) No Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 29821 0716000208 4624 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency I-605 7.63 11.57 LACMTA I-5 6.3 8.9 MPO Element SCAG Project Manager/Contact Phone E-mail Address Mehdi Salehinik 213-897-7195 [email protected] Project Title I-605/I-5 Interchange Improvements Location (Project Limits), Description ( Scope of Work) The project limits along the I-605 are from Slauson Avenue to I-105 and along the I-5 between Paramount Boulevard and Florence Avenue. This project will environmentally clear and design direct connectors at the I-605/I-105 interchange, an additional HOV/GP or HOT lane on I-605 and an additional HOV lane on I-5. The project will include improvements to the mainline, freeway connectors and auxiliary lanes. All the on and off ramps within the project limits will also be evaluated for improvements.

Component Implementing Agency PA&ED LACMTA PS&E Right of Way Construction Legislative Districts Assembly: 57 & 58 Senate: 32 Congressional: 38 & 40 Project Benefits

The project will enhance mobility by extending the I-5 South Widening/HOV project between the Orange County line to Paramount Blvd. The project will also provide better connections for HOV/HOT connections on I-605 and reduce bottlenecks currently found on I-605.

Purpose and Need Population and goods movement are expected to place greater demands on the I-605 corridor as a whole. Operational and safety improvements are needed to ease current congestion and address projected growth. The project proposes to enhance mobility, improve public safety and reduce environmental impact.

Category Outputs/Outcomes Unit Total State Highway Road Construction Operational Improvements

ADA Improvements No Bike/Ped Improvements No Reversible Lane analysis Yes Includes Sustainable Communities Strategy Goals No Reduces Greenhouse Gas Emissions No Project Milestone Existing Proposed Project Study Report Approved Begin Environmental (PA&ED) Phase 10/01/15 Circulate Draft Environmental Document Document Type Draft Project Report End Environmental Phase (PA&ED Milestone) 07/01/21 Begin Design (PS&E) Phase 10/01/21 End Design Phase (Ready to List for Advertisement Milestone) 03/02/25 Begin Right of Way Phase 05/01/22 End Right of Way Phase (Right of Way Certification Milestone) 12/01/24 Begin Construction Phase (Contract Award Milestone) 08/01/25 End Construction Phase (Construction Contract Acceptance Milestone) 09/01/29 Begin Closeout Phase 02/01/30 End Closeout Phase (Closeout Report) 11/01/30 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 111 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information Reversible lanes are not applicable as this is an interchange inprovement to an existing highway.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 112 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 I-605, I-5 29821 0716000208 4624 Project Title: I-605/I-5 Interchange Improvements

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) LACMTA PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) 30,069 30,069 PS&E 51,500 51,500 R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 30,069 51,500 81,569

Fund No. 1: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 2018 STIP Request R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Proposed funding from PS&E 18,170 18,170 2018 STIP. Funding from R/W SUP (CT) LA County APDE Share CON SUP (CT) R/W CON TOTAL 18,170 18,170

Fund No. 2: Measure R Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 30,069 30,069 Los Angeles County to fund PS&E the Project Report/ R/W SUP (CT) Environmental Document CON SUP (CT) with Measure R under R/W Route 605 Hot Spots CON category. TOTAL 30,069 30,069

2018 Los Angeles County Regional Transportation Improvement Program 113 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 I-605, I-5 29821 0716000208 4624 Project Title: I-605/I-5 Interchange Improvements

Fund No. 3: Local Transportation Funds Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) Remaining balance needs PS&E 33,330 33,330 to be funded by LA Metro's R/W SUP (CT) funding. CON SUP (CT) R/W CON TOTAL 33,330 33,330

Fund No. 4: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 5: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 114 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 I-605 I-5 29821 0716000208 4624 SECTION 1 - All Projects Project Background In November 2008, Measure R was approved by a significant two-thirds majority, committing a projected $40 billion to traffic relief and transportation upgrades throughout Los Angeles County over the next 30 years. Metro has committed to the delivery of $7.2 billion in highway improvements as a significant component of the Measure R program, with $590 million specifically identified for improvements within the Gateway Cities SR-91/I-605/I-405 area.

Programming Change Requested Propose funding for PSE phase with LA county's share of RIP funding and Measure R funding.

Reason for Proposed Change Funding with RIP for PS&E due to the availability of APDE finds in the 2018 STIP.

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 115 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) No Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 29811 5388 REG0703 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA 91 16.94 19.81 Metro/Caltrans MPO Element SCAG Project Manager/Contact Phone E-mail Address Carlos Montez 213-814-3241 [email protected] Project Title SR-91 WB from Shoemaker Ave to I-605/SR-91 Interchange Location (Project Limits), Description ( Scope of Work) In LA County, In the cities of Artesia and Cerritos. On State Route 91, from Shoemaker Avenue to I-605 Interchange. This first phase improvement project proposes to add new lanes (General Purpose and/or auxiliary), modify on/off ramps and reduce numbers of existing non-standard features on SR-91 WB, from Shoemaker Ave to the I-605/SR-91 interchange.

Component Implementing Agency PA&ED LACMTA PS&E LACMTA Right of Way TBD Construction TBD Legislative Districts Assembly: 58 Senate: 32 Congressional: 38 Project Benefits

This first phase improvement project proposes to add new lanes (General Purpose and/or auxiliary), modify on/off ramps and reduce numbers of existing non-standard features on SR-91 WB, from Shoemaker Ave to the I-605/SR-91 interchange.

Purpose and Need • Reduce congestion and improve freeway operations • Improve local interchange operations • Improve safety

Category Outputs/Outcomes Unit Total State Highway Road Construction Mixed Flow lane-miles constructed Miles 2.9

ADA Improvements Yes Bike/Ped Improvements No Reversible Lane analysis Yes Includes Sustainable Communities Strategy Goals No Reduces Greenhouse Gas Emissions No Project Milestone Existing Proposed Project Study Report Approved 07/06/05 Begin Environmental (PA&ED) Phase 06/20/16 Circulate Draft Environmental Document Document Type 05/03/17 08/24/18 Draft Project Report 07/13/17 09/10/18 End Environmental Phase (PA&ED Milestone) 01/04/19 01/14/19 Begin Design (PS&E) Phase 02/01/19 End Design Phase (Ready to List for Advertisement Milestone) 02/01/21 Begin Right of Way Phase 02/01/20 End Right of Way Phase (Right of Way Certification Milestone) 02/01/21 Begin Construction Phase (Contract Award Milestone) 05/01/21 End Construction Phase (Construction Contract Acceptance Milestone) 10/01/22 Begin Closeout Phase 10/01/22 End Closeout Phase (Closeout Report) 01/01/23 For individuals with sensory disabilities, this document is available in alternate formats. For information call ADA Notice (916) 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89,

2018 Los Angeles County Regional Transportation Improvement Program 116 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information This project is the first phase project of the larger project (EA 07-29810) that is to improve the entire interchange and all local interchange ramps up to 3 miles from/to the interchange. The objective for this project is to complete the Project Approval and Environment Document (PA&ED) work needed for the improvement work on Westbound SR-91 to I-605/SR-91 interchange to reduce congestion and improve freeway operations to main lines and connected ramps.

Reversible lanes are not applicable as this is an interchange inprovement to an existing highway.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 117 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 91 29811 5388 Project Title: SR-91 WB from Shoemaker Ave to I-605/SR-91 Interchange

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) LACMTA PS&E LACMTA R/W SUP (CT) TBD CON SUP (CT) TBD R/W TBD CON TBD TOTAL Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) 8,539 8,539 PS&E 22,000 22,000 R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 8,539 22,000 30,539

Fund No. 1: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 2018 STIP Request R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) From LA County APDE PS&E 22,000 22,000 Share R/W SUP (CT) CON SUP (CT) R/W CON TOTAL 22,000 22,000

Fund No. 2: Measure R Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 8,539 8,539 Per Agreement 07-5084, PS&E 07-5085; $776,300 + R/W SUP (CT) $7,763,000= $8,539,300 CON SUP (CT) R/W CON TOTAL 8,539 8,539

2018 Los Angeles County Regional Transportation Improvement Program 118 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA 91 29811 5388 SECTION 1 - All Projects Project Background The Interstate 605 (I-605), is a major north-south transportation route and the Artesia Freeway, State Route 91 (SR-91) is a major east- west transportation route within Los Angeles County and are integral parts of the freeway network for the Southern California metropolitan area. In an effort to improve traffic flow along the freeways, the Los Angeles County Metropolitan Transportation Authority (LACMTA), in cooperation with the Gateway Cities Council of Governments (GCCOG), the California Department of Transportation (Caltrans) District 7, and the County of Los Angeles, is proposing to construct improvements to the system interchange at I-605 and SR-91 and corridors approaching the interchange.

Programming Change Requested This project is sponsored and implemented by Los Angeles County Metropolitan Transportaiton Authority (LACMTA), with oversight by Caltrans. This amendment is to program funds for PS&E work with the APDE funds available.

Reason for Proposed Change To continue to develop the project with additional funding programmed by LA Metro.

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded NA

Other Significant Information Project is managed by LA Metro, oversight by Caltrans.

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 119 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) General Instructions Amendment (Existing Project) No Date: 12/14/17 District EA Project ID PPNO MPO ID Alt Proj. ID 07 29360 0713000238 4451 County Route/Corridor PM Bk PM Ahd Project Sponsor/Lead Agency LA I-405 14.4 15.6 LACMTA MPO Element SCAG Project Manager/Contact Phone E-mail Address Mehdi Salehinik (213) 897-7195 [email protected] Project Title I-405 Crenshaw Blvd Ramp Improvement Location (Project Limits), Description ( Scope of Work) The project is located on I-405 at the Crenshaw Blvd/182nd street on/off ramps in the South Bay Subregion. The project will alleviate congestion, improve traffic flow and operational conditions on I-405 and the local arterials of Crenshaw and 182nd St in the City of Torrance. The proposed improvements will also add a new I-405 on/ramp at Crenshaw, additional storage on the on/off ramps and add an auxiliary lane on I-405 between Western Ave and Crenshaw Blvd.

Component Implementing Agency PA&ED LACMTA PS&E Right of Way Construction Legislative Districts Assembly: 64 & 66 Senate: 35 Congressional: 43 Project Benefits Benefits of this project include improvement of freeway and arterial operations, increase in safety and reduced congestion on local arterials and the I-405 mainline.

Purpose and Need The proposed project will increase the capacity of the interchange and provide new turning movements to enhance accessibility and safety, improve traffic flow, operational conditions and alleviate congestion. The need for the project stems from deteriorating operations condition on I-405 and Crenshaw/182nd on/off ramps, a forecasted increase in traffic volumes, increasing delays during AM and PM peak period travel periods and higher than average accident rates at some interfacing intersections. Category Outputs/Outcomes Unit Total

ADA Improvements No Bike/Ped Improvements No Reversible Lane analysis Yes Includes Sustainable Communities Strategy Goals No Reduces Greenhouse Gas Emissions No Project Milestone Existing Proposed Project Study Report Approved Begin Environmental (PA&ED) Phase 01/02/14 Circulate Draft Environmental Document Document Type Draft Project Report End Environmental Phase (PA&ED Milestone) 06/29/17 Begin Design (PS&E) Phase 09/28/17 End Design Phase (Ready to List for Advertisement Milestone) 03/13/20 Begin Right of Way Phase 03/06/18 End Right of Way Phase (Right of Way Certification Milestone) 03/02/20 Begin Construction Phase (Contract Award Milestone) 10/07/20 End Construction Phase (Construction Contract Acceptance Milestone) 04/03/23 Begin Closeout Phase 04/03/24 End Closeout Phase (Closeout Report) 04/03/26 For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) ADA Notice 654-6410 or TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento,

2018 Los Angeles County Regional Transportation Improvement Program 120 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 Additional Information Reversible lanes were considered, but are not applicable as this is a ramp improvement for an existing highway ramp.

For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or ADA Notice TDD (916) 654-3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

2018 Los Angeles County Regional Transportation Improvement Program 121 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA I-405 29360 0713000238 4451 Project Title: I-405 Crenshaw Blvd Ramp Improvement

Existing Total Project Cost ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Implementing Agency E&P (PA&ED) LACMTA PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Total Project Cost ($1,000s) Notes E&P (PA&ED) 1,700 1,700 PS&E 10,200 10,200 R/W SUP (CT) 2,200 2,200 CON SUP (CT) 12,000 12,000 R/W 5,900 4,430 10,330 CON 55,996 55,996 TOTAL 20,000 4,430 55,996 12,000 92,426

Fund No. 1: RIP Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E 2018 STIP Request R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) From LA County Share Tier PS&E II Requests R/W SUP (CT) CON SUP (CT) 12,000 12,000 R/W CON TOTAL 12,000 12,000

Fund No. 2: Measure R Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) 1,700 1,700 Per Agreement #MOU PS&E 10,200 10,200 MR312.25 A-1. Propose R/W SUP (CT) 2,200 2,200 RW Support with RIP CON SUP (CT) funding. Additional funding R/W 5,900 4,430 10,330 for RW and Construction to CON fully fund the capital. TOTAL 20,000 4,430 24,430

2018 Los Angeles County Regional Transportation Improvement Program 122 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA I-405 29360 0713000238 4451 Project Title: I-405 Crenshaw Blvd Ramp Improvement

Fund No. 3: SB 1 Funds Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) SB 1 funding will be sought PS&E for this project. Other locals R/W SUP (CT) sources will be used to fund CON SUP (CT) the project if SB 1 funding R/W is not approved for the CON 55,996 55,996 project. TOTAL 55,996 55,996

Fund No. 4: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

Fund No. 5: Program Code Existing Funding ($1,000s) Component Prior 18/19 19/20 20/21 21/22 22/23 23/24+ Total Funding Agency E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL Proposed Funding ($1,000s) Notes E&P (PA&ED) PS&E R/W SUP (CT) CON SUP (CT) R/W CON TOTAL

2018 Los Angeles County Regional Transportation Improvement Program 123 STATE OF CALIFORNIA ● DEPARTMENT OF TRANSPORTATION PROJECT PROGRAMMING REQUEST DTP-0001 (Revised July 2017) Complete this page for amendments only Date: 12/14/17 District County Route EA Project ID PPNO TCRP No. 07 LA I-405 29360 0713000238 4451 SECTION 1 - All Projects Project Background I-405 is a major north-south Interstate Highway in Southern California that spans 72.7 miles with 48.5 miles in District 7, LA County. It begins with Interstate 5 (I-5) in the City of lrvine in Orange County and terminates with I-5 in the Mission Hills area of LA County. I-405 has played a crucial role in the development of dozens of cities and suburbs along its route through the Greater LA area. It is used for international, interstate, interregional and intraregional travel and shipping through an urbanized corridor serving the four major import/export terminals of Long Beach Municipal Airport, Los Angeles International Airport, and the ports of Long Beach and Los Angeles. It is also used as a commuter route.Heavily-traveled by both commuters and by freight haulers, it's the busiest and most congested freeway in the US. It is part of the California Freeway and Expressway System. Programming Change Requested This project was previously partially funded with Metro's Measure R funding. The project is ready to be fully funded for the the remainder of the project. Metro proposes to use regional share of RIP to fund construction support.

Reason for Proposed Change Due to the availability of RIP funding for this programming cycle, Metro proposes to use the RIP funding for the remaining support component for CALTRANS work.

If proposed change will delay one or more components, clearly explain 1) reason the delay, 2) cost increase related to the delay, and 3) how cost increase will be funded

Other Significant Information This projects is funded with Measure R for SBCCOG

SECTION 2 - For TCRP Projects Only Alternative Project Request (Please follow Instructions at http://www.dot.ca.gov/tcrp/LETTERguidelines) Letter of No Prejudice (LONP) (Please follow Guidelines at http://www.dot.ca.gov/tcrp/docs/042706.pdf)

SECTION 3 - All Projects Approvals I hereby certify that the above information is complete and accurate and all approvals have been obtained for the processing of this amendment request.* Name (Print or Type) Signature Title Date

Attachments 1) Concurrence from Implementing Agency and/or Regional Transportation Planning Agency 2) Project Location Map 2018 Los Angeles County Regional Transportation Improvement Program 124 Section 16 Board Resolution and Documentation of 2018 RTIP Approval

2018 Los Angeles County Regional Transportation Improvement Program 125 This page is left blank.

2018 Los Angeles County Regional Transportation Improvement Program 126 Los Angeles County Metro Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Board Report Los Angeles, CA

File #:2017-0696, File Type:Program Agenda Number:16.

PLANNING AND PROGRAMMING COMMITTEE NOVEMBER 15, 2017

SUBJECT: 2018 REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM

ACTION: APPROVE 2018 REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM FOR LOS ANGELES COUNTY

RECOMMENDATION

APPROVE the programming of up to $481,845,000 for the 2018 Los Angeles County Regional Transportation Improvement Program (RTIP) as shown in Attachment A.

ISSUE

In August 2017, the California Transportation Commission (CTC) adopted the 2018 State Transportation Improvement Program (STIP) Fund Estimate, which provides new funding capacity over the five-year STIP period from Fiscal Year (FY) 2019 through FY 2023. In September 2017, the Board approved the State and Federal Funding Evaluative Criteria Framework designed to strategically guide Metro’s considerations and pursuits of state and federal discretionary and formula funding programs.

Board adoption of the 2018 Regional Transportation Improvement Program (RTIP) for Los Angeles (LA) County will help secure formula funds for projects that are less competitive for other discretionary programs and those that have a low tolerance for risk. Approving this recommendation is consistent with the Board-approved 2009 Long Range Transportation Plan priorities, and meets the State and Federal Funding Evaluative Criteria.

DISCUSSION

Background The STIP is a five-year capital improvement program of transportation projects on and off the State Highway System. Every two years, the CTC adopts a new STIP cycle adding two new years of funding capacity to the rolling five-year program. The last STIP was adopted by the CTC in May 2016. The 2018 STIP covers the five-year period from FY 2018-19 (FY 2019) through FY 2023. The STIP contains two portions. The first portion, the RTIP, accounts for 75% of the total STIP and is directly programmed by Regional Transportation Planning Agencies and County Transportation Commissions. The RTIP portion is the subject of the recommendations of this report. The second

Metro Page 1 of 4 Printed on 11/10/2017 2018 Los Angeles County Regional Transportation Improvement Program powered127 by Legistar™ File #:2017-0696, File Type:Program Agenda Number:16. portion is the Interregional Transportation Improvement Program (ITIP), which consists of the remaining 25% of the STIP and is directly programmed by Caltrans.

Relationship to the 2016 STIP In the 2016 STIP, the revised final STIP Fund Estimate (FE) was negative, resulting in project deletions rather than new programming. Roughly $74 million was deleted from LA County’s program. The 2018 STIP FE fully restores $754 million in statewide deletions. Additionally, it provides $1.5 billion for the regions and the state to program additional projects. In developing the 2018 RTIP, staff first restored prior funding commitments previously deleted from the 2016 STIP, consistent with CTC priorities (Attachment B). Next, staff utilized the Evaluative Criteria Framework to ensure that the program of projects proposed satisfies each of the principles the framework sets forth (Attachment C).

Proposed 2018 RTIP Consistent with the Evaluative Criteria Framework, staff aimed to strategically apply formula funds for projects that are less likely to compete well in discretionary programs and those that have a low tolerance for risk. In addition, staff looked to reduce the charge rate associated with Caltrans support activities by looking for opportunities to fund those costs with state dollars, which are subject to a lower Indirect Cost Rate Proposal (ICRP). Based on these considerations and the assessment of the other criteria, staff recommends programming STIP funds for the program of projects as shown in Attachment A and described in Attachment B.

In order to be positioned to receive funding up to the maximum LA County target of $481,845,000, Los Angeles County Metropolitan Transportation Authority (Metro) must prepare an RTIP proposing the programming of those dollars for eligible projects through the STIP period. In addition to the total target shares of $317,185,000, the 2018 STIP includes an Advanced Project Development Element (APDE) target for LA County of $54,170,000. Programming APDE would allow Metro to advance a portion of future STIP shares to fund project development work, including environmental and design elements. Up to an additional $110,490,000 could be advanced to LA County projects from future shares under the maximum target if other counties program less than their total targets. Board- approved programming must be submitted to the CTC by the December 15, 2017 deadline for the 2018 STIP process. Therefore, staff seeks board approval of the 2018 RTIP (Attachment A) and the three tiers of funding as follows:

Interregional Transportation Improvement Program Caltrans is responsible for developing the Interregional Transportation Improvement Program (ITIP), consistent with the Interregional Transportation Strategic Plan (ITSP), which the CTC adopts as a component of the STIP. Staff worked with Caltrans District 7 to propose three projects in LA County

Metro Page 2 of 4 Printed on 11/10/2017 2018 Los Angeles County Regional Transportation Improvement Program powered128 by Legistar™ File #:2017-0696, File Type:Program Agenda Number:16. for the 2018 ITIP, of which Caltrans Headquarters has included one in their Draft 2018 ITIP. The Draft ITIP includes $7 million for the Rosecrans Marquardt Grade Separation project, proposed in FY 2020. Staff continues to work with Caltrans and the CTC to include ITIP funding for the I-5 Corridor Improvements Project between the I-605 and the I-710, which is a part of Operation Shovel-Ready. We are seeking a total of $16 million for that project in FY 2019.

DETERMINATION OF SAFETY IMPACT

Adoption of the 2018 RTIP will authorize staff to seek funds to make safety and other mobility improvements in several areas of the county.

FINANCIAL IMPACT

Approval of the 2018 RTIP for LA County would have no negative financial impact to the county. The 2018 RTIP fulfills prior and anticipated funding commitments for transportation projects within LA County.

Impact to Budget

The approval of the 2018 RTIP has no impact to the FY 2018 budget.

ALTERNATIVES CONSIDERED

The Board could elect to reject the staff recommendation for the 2018 RTIP. This option is not recommended as it would force LA County to surrender the formula funds available through the 2018 STIP period. This would be detrimental to the project funding for the projects proposed herein. Staff has identified a geographically and modally balanced set of priority projects, which is consistent with state guidelines and the evaluation criteria framework approved by the Board in September 2017.

NEXT STEPS

With Board approval of our recommendation, staff will proceed with and monitor the following steps to securing the 2018 LA County RTIP submittal:

• Submit RTIP request to CTC - December 15, 2017

• CTC Southern California STIP hearing - January 25, 2018

• CTC publishes staff recommendations - February 28, 2018

• CTC adopts STIP - March 21-22, 2018

Metro Page 3 of 4 Printed on 11/10/2017 2018 Los Angeles County Regional Transportation Improvement Program powered129 by Legistar™ File #:2017-0696, File Type:Program Agenda Number:16.

ATTACHMENTS

Attachment A - 2018 RTIP for Los Angeles County Attachment B - Projects Proposed for Programming Attachment C - Evaluative Criteria Framework to Guide 2018 RTIP Development

Prepared by: Zoe Unruh, Principal Transportation Planner, Countywide Planning & Development, (213) 922-2465 Patricia Chen, Senior Director, Countywide Planning & Development, (213) 922-3041 Wil Ridder, EO, Countywide Planning & Development, (213) 922-2887 Laurie Lombardi, SEO, Countywide Planning & Development, (213) 418-3251

Reviewed by: Therese W. McMillan, Chief Planning Officer, (213) 922-7077

Metro Page 4 of 4 Printed on 11/10/2017 2018 Los Angeles County Regional Transportation Improvement Program powered130 by Legistar™ 2018 LOS ANGELES COUNTY REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM ($s in 000) Programming Year Project Phase Tier 1 Requests PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total R/W Con E&P PS&E R/W Sup Con Sup 1 Planning Programming & Monitoring (PPM) 9001 4,002 4,002 4,002 12,005 12,005 2 SR 138 Seg 6 4356 19,750 19,750 15,000 4,750 3 SR 138 Seg 13 4357 4,000 67,000 71,000 55,000 4,000 12,000 4 SR 138 Seg 4 4353 5,250 15,700 19,000 39,950 9,000 15,000 5,250 6,700 4,000 2018 Los Angeles County Regional Transportation Improvement Program Transportation County Regional 2018 Los Angeles 5 SR 71 2741 20,000 20,000 20,000 6 East San Fernando Valley Transit Corridor 07-4296 34,630 17,775 54,733 107,138 34,630 54,733 17,775 7 Bus Acquisition-Project 1 30,246 30,246 30,246 8 Bus Acquisition-Project 2 17,096 17,096 17,096 9 Total -Total Target Requests 29,000 45,946 58,632 40,777 142,831 317,185 43,630 187,075 12,005 27,025 6,700 40,750

Tier 2 Requests (APDE) PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total R/W Con E&P PS&E R/W Sup Con Sup 10 710 Early Action Project/ Shoemaker 14,000 14,000 14,000 11 I-605/I-5 Interchange Improvements 18,170 18,170 18,170 12 I-605/SR-91 Interchange Improvements 22,000 22,000 22,000 13 Total - Tier 2 APDE Requests 36,000 - 18,170 - - 54,170 - - - 54,170 - -

Tier 3 Requests (Potential Additional Shares) PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total R/W Con E&P PS&E R/W Sup Con Sup 14 East San Fernando Valley Transit Corridor 07-4296 - 59,460 39,030 98,490 - 39,030 59,460 15 I-405 Crenshaw Blvd Ramp Improvement 12,000 12,000 - 12,000 16 Total - Tier 3 Requests - - - 71,460 39,030 110,490 - 39,030 - 59,460 - 12,000

17 Total of Tiers 1, 2 and 3 65,000 45,946 76,802 112,237 181,861 481,845 43,630 226,105 12,005 140,655 6,700 52,750

2018 INTERREGIONAL TRANSPORTATION IMPROVEMENT PROGRAM PROJECTS IN LOS ANGELES COUNTY Highway PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total R/W Con E&P PS&E R/W Sup Con Sup 18 I-5 Corridor Improvements (I-605 to I-710) 16,000 16,000 16,000 Transit 19 Rosecrans Marquardt Grade Separation 7,000 7,000 7,000 20 Total 16,000 7,000 - - - 23,000 - 7,000 16,000 - - -

EXISTING 2016 STIP PROGRAMMING

Project PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total R/W Con E&P PS&E R/W Sup Con Sup 21 LRVs 4025 26,200 26,700 27,800 - - 80,700 80,700 22 Planning Programming & Monitoring (PPM) 9001 4,617 - - - - 4,617 4,617 23 Totals 30,817 26,700 27,800 - - 85,317 - 85,317 - - - - 131 AMENDMENT TO EXISTING PROGRAMMING PPNO FY18/19 FY19/20 FY20/21 FY21/22 FY22/23 Total R/W Con E&P PS&E R/W Sup Con Sup 24 Amended PPM 2016 9001 (2,309) 2,309 - 4,617 25 2016 STIP Program Amended Totals 28,508 29,009 27,800 - - 85,317 - 85,317 - - - -

5 Projects Proposed for Programming in the 2018 Los Angeles State Transportation Improvement Program

In developing the 2018 RTIP, staff utilized the Evaluative Criteria Framework to ensure that the program of projects proposed satisfies each of the principles the framework sets forth (ATTACHMENT C). Based on that assessment, staff recommends the following:

• The SR-138 Segment 6 is a project that will serve to relieve congestion and enhance safety along the Route 138 Corridor. Programming is proposed for FY 19 for the Construction Phase ($19.8 million). This project had been previously programmed in FY 17, but was deleted from the 2016 STIP due to negative funding capacity. Funding the 2016 deletions is the highest priority for the CTC and programming this project restores a prior funding commitment.

• The SR-138 Segment 13 is proposed for FY19 and FY23 for Design ($4 million) and Construction ($67 million). This project had been previously programmed in FY17, but was deleted from the 2016 STIP due to negative funding capacity. Funding the 2016 deletions is the highest priority for the CTC and programming this project restores a prior funding commitment.

• The SR-138 Segment 4 is proposed for FY19, FY 20 and FY22 for the Project Study and Engineering Phase ($5.3 million), Right of Way ($15.7 million) and Construction ($19 million). This project is the final segment of the SR 138, and completing it will allow the full benefits from the investments across the corridor to be realized.

• The SR-71 is a project that proposes to upgrade 3.2 miles of existing four-lane expressway to an eight-lane freeway on Route 71 from Interstate 10 to Route 60 in Los Angeles County. Programming is proposed for FY21 for the Construction Support Phase ($20 million).

• The East San Fernando Valley Transit Corridor Project will provide improved north/south transit service in the eastern San Fernando Valley along Van Nuys Boulevard and San Fernando Road. Programming is proposed for FY 21 for the Right-of-Way Phase ($34.6 million) and for FY22 and FY23 for the Design and Construction Phases ($72.5 million). The project is expected to be delivered under a design-build contract, and the funding proposed would support the design and construction of the project.

• The Bus Acquisition Project 1 is required to maintain a state of good repair of our bus fleet through a replacement schedule that allows Metro's buses to be retired and replaced after the end of their "useful life" as defined by the FTA. Programming is proposed for FY20 ($30.2 million). This funding supports the

2018 Los Angeles County Regional Transportation Improvement Program 132 ongoing fleet replacement and upgrading required to support Metro’s bus operations and ensure Metro’s fleet is in a state of good repair.

• Programming for the Bus Acquisition Project 2 is proposed for FY23 ($17.1 million). This funding will fund a scheduled future bus replacement. This project supports the ongoing fleet replacement and upgrading required to support Metro’s bus operations and ensure Metro’s fleet is in a state of good repair.

• Planning, Programming, and Monitoring (PPM) funds are proposed for continuation to fund the planning activities of Metro and is proposed for FY21 ($4 million), FY22 ($4 million), and FY23 ($4 million).

In addition to the projects programmed for Los Angeles County’s total target share, staff proposes to establish a second tier to utilize the full Advanced Project Development Element (APDE) target of 25% off the shares forecasted for the next STIP cycle to fund project development activities. Shares will be advanced from the next share period. The following projects are proposed for APDE, Tier II:

• The I-710 Early Action Shoemaker Bridge includes the replacement of the existing bridge and reconfiguration of the associated connector roads to downtown Long Beach. APDE would be proposed for FY19 to fund the Project Study and Engineering Phase ($14 million).

• The I-605/SR 91 Interchange Improvements Project is being collaborated by the Gateway Cities Council of Governments, the City of Cerritos, and the City of Artesia who are proposing to make improvements on the westbound SR-91 between Shoemaker Ave and the I-605/SR-91 interchange. APDE would be proposed for FY19 to fund the Project Study and Engineering Phase ($22 million).

• The I-605/I-5 Interchange Improvements Project proposes improvements Florence Ave to Paramount Blvd. APDE would be proposed for FY21 to fund the Project Study and Engineering Phase ($18.2 million).

Lastly, staff is recommending a third tier of projects should other regions under- program, leaving additional funding capacity available. Tier III is proposed as follows:

• The I-405 Crenshaw Blvd Ramp Improvement Project proposes to improve operational conditions on the I-405, and its on-and-off ramps at Crenshaw Boulevard and 182nd Street in Torrance. Programming is proposed for FY22 for the Construction Phase ($12 million).

• The East San Fernando Valley Transit Corridor Project (see description above) is being proposed to receive additional funding to be programmed for the Construction Phase in FY22 and FY23 for a total of ($98.5 million).

2018 Los Angeles County Regional Transportation Improvement Program 133 Additionally, staff is amending the $4.6 million in prior PPM programming for FY19 to instead be spread over FY19 ($2.3 million) and FY20 ($2.3 million) in order to avoid a gap in PPM funding in FY20. The CTC typically views PPM as a high priority for allocation.

2018 Los Angeles County Regional Transportation Improvement Program 134 Evaluative Criteria Framework to Guide the 2018 RTIP Development

In selecting projects to submit for funding through the 2018 State Transportation Improvement Program (STIP), staff used the Evaluative Criteria Framework. The framework was approved at the September 2017 Board meeting. The framework was applied as follows:

1. Sustain Measure M and other Pre-Measure M/LRTP Priorities and Schedules Staff evaluated Metro’s existing priorities as established in the LRTP, Measure R and Measure M expenditure plans to identify project schedules that coincide with the STIP programming and allocation constraints. The 2018 STIP includes funds in each of five years, FY 2018-19 through 2022-23. This step of the review consisted mainly of identifying projects ready either for:

1) pre-development funding only, such that they might compete for future cycle SB-1 or other discretionary programs for construction funds; or 2) funding through construction.

Many of Metro’s projects satisfy this criterion and have project phases underway within the 5-year STIP program, including all of the projects proposed in the 2018 RTIP.

2. Match competitiveness of Projects to New/Expanded Programs Criteria

STIP funding is relatively flexible. Eligibility is broad in the STIP program, and all projects identified in the first step of review were deemed eligible, however, the guidelines contain a number of points which staff took into consideration when identifying projects.

Firstly, projects deleted through the 2016 STIP are the first priority for funding from the 2018 STIP, and for Los Angeles County, these include:

• SR-138 Segment 6 • SR-138 Segment 13.

Secondly, performance information requirements established with the adoption of the 2016 STIP Guidelines places emphasis on projects which reduce greenhouse gas emissions, as well as other measures including efficiency and effectiveness. In building the program for the 2018 STIP, staff sought a modally balanced submittal to help ensure acceptable results for the performance reporting requirements. The inclusion of the bus acquisition projects and the East San Fernando Valley support the performance goals within the STIP.

Additional consideration is required to ensure all projects proposed are eligible for the mix of state and federal funds sources for the State Highway Account which funds the STIP. Beginning with the 2018 STIP Fund Estimate Public Transportation Account funds are no

2018 Los Angeles County Regional Transportation Improvement Program 135 longer available for the STIP. Therefore, staff analyzed all transit projects to determine whether they were eligible for either fuel excise tax funds protected by Article 19 (dedicated right-of-way, infrastructure only, no rolling stock) or federal funds. Projects not clearly eligible for federal funds or Article 19 state funds were screened out.

3. Certainty (Formula) vs. Risk (Competitive/Discretionary)

With the limited availability of formula funds, staff focused on the strategic use of STIP formula funds on projects that are less likely to compete well in discretionary programs and those that have a low tolerance for risk. Additionally, Caltrans applies a reduced Indirect Cost Rate Proposal (ICRP) for work they perform when that work is paid for by state dollars. Thus, staff also sought strategic programming opportunities that would achieve cost savings on the (ICRP) applied by Caltrans for projects on the state highway system. For the projects included in the RTIP, the following rationale was applied:

• State Route 71 had an existing funding gap due to the cancellation of the FASTLANES grants. In response to the funding gap, staff committed to looking at SB 1 funding sources to fully fund this project. Based on the project’s relative potential to compete for state discretionary programs, the significant risk to the existing funding commitment of repurposed federal earmarks, and the opportunity to secure ICRP savings, staff identified the SR 71 as an ideal candidate for STIP formula funds.

• The delivery of the SR 138 Segments 4, 6, and 13 are dependent on the availability of state funds, as there are no explicit funding commitments for these segments identified in Measure M. Lacking the potential to put forward any local match reduces the ability of these projects to seek funds through other SB 1 discretionary grant programs. Funding these projects with STIP formula funds makes it possible to complete the remaining segments of the SR 138 with certainty while securing a reduced ICRP rate for Caltrans support activities.

• The East San Fernando Valley Transit Corridor Project had a funding gap as a result of the state’s cancellation of the Traffic Congestion Relief Program (TCRP), which STIP formula funds provide opportunity to address. Additionally, this project assumes a large share of non-Measure M dollars, and thus is expected to compete in other SB 1 funding programs. Therefore, using formula funds for a portion of the non-Measure M share of the project cost offsets some of the risks associated with aiming to complete the projects non-Measure M funding entirely through discretionary grants.

• The Bus Acquisition projects are essential to Metro’s overall bus fleet management strategy, and Metro’s ability to maintain our fleet in a state of good repair. Any risk to the forecasted replacement schedule would have an impact on maintaining operating schedules and delivering bus service. These projects are best suited for the certainty afforded by formula funding sources.

2018 Los Angeles County Regional Transportation Improvement Program 136 With regard to the Advance Project Development Element (APDE) formula funds, staff sought opportunities to initiate project development work that could help support future SB 1 discretionary program candidate projects. The I-605/I-5 Interchange Improvements Project, I-605/SR-91 Interchange Improvements Project, and the I-710 Early Action Project/Shoemaker each had eligible phases of work within the 2018 STIP timeframe. In addition, with Caltrans performing the project development work, Metro is able to secure a reduced ICRP for these activities.

4. Geographic Balance

Including the Bus Acquisition project, the RTIP program funds projects in all of the nine subregions. The projects by subregion are as follows:

Gateway Cities:

• I-605/I-5 Interchange Improvements • I-710 Early Action Project/Shoemaker • I-605/SR-91 Interchange Improvements

North County:

• SR-138 Segment 6 • SR-138 Segment 13 • SR-138 Segment 4

San Fernando Valley:

• East San Fernando Valley Transit Corridor

San Gabriel Valley:

• SR-71

South Bay:

• I-405 Crenshaw Blvd. Ramp Improvement (Also included in the Measure R Expenditure Plan)

Arroyo Verdugo, Central Los Angeles, Gateway Cities, Las Virgenes/Malibu San Fernando Valley, San Gabriel Valley, South Bay, and Westside Cities:

2018 Los Angeles County Regional Transportation Improvement Program 137 • Bus Acquisition 1 • Bus Acquisition 2

5. Consistency with Board policies and directives

The projects identified for funding in the 2018 STIP are consistent with Board policies and directives. STIP funds are part of the state and federal funds assumed in the development of the Measure M Expenditure Plan. STIP funds as part of the funding plans of the Measure M projects will help to keep the projects fully funded and deliverable in a timely manner.

6. Consistency with Metro Long Range Transportation Plan and Southern California Association of Governments (SCAG) Regional Transportation Plan (RTP)

All of the projects identified for STIP funding are Measure M, Measure R and/or LRTP projects. Each project is consistent with the priorities set forth in the Metro LRTP and is included in the SCAG RTP.

2018 Los Angeles County Regional Transportation Improvement Program 138 Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room

Los Angeles, CA RECAP of Proceedings

Thursday, November 30, 2017 9:00 AM One Gateway Plaza, Los Angeles, CA 90012, 3rd Floor, Metro Board Room Board of Directors - Regular Board Meeting

DIRECTORS PRESENT: Eric Garcetti, Chair Sheila Kuehl, Vice Chair James Butts, 2nd Vice Chair Kathryn Barger Mike Bonin Jacquelyn Dupont-Walker John Fasana Janice Hahn Paul Krekorian Ara Najarian Mark Ridley-Thomas Hilda Solis Carrie Bowen, non-voting member Phillip A. Washington, Chief Executive Officer

CALLED TO ORDER AT: 9:17 a.m.

2018 Los Angeles County Regional Transportation Improvement Program 139 15. SUBJECT: CALTRANS PARK & RIDE LOTS 2017-0585

AUTHORIZED ON CONSENT CALENDAR:

A. acquisition of Lakewood and Norwalk Park & Ride Lots through execution of a Relinquishment Agreement; and

B. execution of a Memorandum of Understanding with Caltrans to enable a potential future joint development at El Monte Station on Caltrans-owned land.

16. SUBJECT: 2018 REGIONAL TRANSPORTATION IMPROVEMENT 2017-0696 PROGRAM

APPROVED the programming of up to $481,845,000 for the 2018 Los Angeles County Regional Transportation Improvement Program (RTIP) as shown in Attachment A.

PK JF JH MB HS JB EG SK KB JDW MRT AN RG Y Y Y Y Y Y Y Y Y Y Y Y A

17. SUBJECT: FY 2017 FEDERAL HOMELAND SECURITY AND STATE 2017-0616 PROPOSITION 1B SECURITY PROJECTS RECOMMENDATION APPROVED ON CONSENT CALENDAR:

A. APPROVING programming of up to $13.557 million from fiscal year (FY) 2017 federal Department of Homeland Security Transit Security Grant Program (TSGP) and state Proposition 1B California Transit Security Grant Program (Prop 1B Transit Security) funds that are available for eligible capital and operating transit security projects, as shown in Attachment A; and

B. ADOPTING the required FY 2017 resolution, as shown in Attachment B, authorizing the Chief Executive Officer to execute any actions necessary for obtaining state financial assistance that the California Office of Emergency Services (Cal OES) may provide.

2018 Los Angeles County Regional Transportation Improvement Program 140 Section 17 Links to Project Study Reports and Project Study Report Equivalents

2018 Los Angeles County Regional Transportation Improvement Program 141 This page is left blank.

2018 Los Angeles County Regional Transportation Improvement Program 142 State Route 138—PSR

State Route 71—PSR

East San Fernando Valley Transit Corridor—PSRE

Bus Acquisitions—PSRE

Shoemaker Bridge Replacement/Early Action Project—PSR

I-5 Interchange Improvements (605/5 and 605/91) —PSR

I-405 Crenshaw Blvd—PSR

2018 Los Angeles County Regional Transportation Improvement Program 143 This page is left blank.

One Gateway Plaza 213.922.9200 Tel Los Angeles, CA 90012-2952 213.922.5259 Fax metro.net 18-1412mr ©2017 lacmta ©2017 18-1412mr