Environmental Assessment Report

Initial Environmental Examination Project Number: 42252 August 2010

BHU: Rural Renewable Energy Development Project

Prepared by the Department of Energy, Government of for the Asian Development Bank (ADB).

The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Royal Government of Bhutan

Asian Development Bank

Technical Assistance

Project Number: 7318-BHU Preparing the Rural Renewable Energy Development Project

INITIAL ENVIRONMENTAL EXAMINATION (DRAFT)

TRASHIGANG ACCELERATED RURAL ELECTRIFICATION SUBPROJECT

MARCH 2010

1

Contents I. EXECUTIVE SUMMARY...... 8

II. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK...... 13

A. Policies relevant to the project ...... 13

B. Environmental Clearance Procedures ...... 15

III. DESCRIPTION OF THE PROJECT...... 17

A. Project description...... 17

B. Project budget and implementation ...... 22

IV. DESCRIPTION OF THE ENVIRONMENT ...... 24

A. Physical Resources ...... 24

B. Ecological Resources ...... 26

C. Economic Development...... 27

D. Social and Cultural Resources ...... 29

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 31

A. Environmental effects due to project location and design ...... 31

B. Environmental effects due to Construction ...... 31

i. Impact on Physical Resources ...... 34

ii. Impact on Ecological Resources...... 35

iii. Impact on Economic Development...... 37

iv. Impact on Social and Cultural Resources ...... 39

C. Environmental effects during Operation and Maintenance ...... 42

i. Impact on Physical Resources ...... 42

ii. Impact on Ecological Resources...... 42

iii. Impact on Economic Development...... 43

iv. Impact on Social and Cultural Resources ...... 43

VI. ANALYSIS OF ALTERNATIVES ...... 45

2

VII. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION...... 47

A. Project stakeholders...... 47

B. Consultation and disclosure to date ...... 47

C. Future consultation and disclosure ...... 48

VIII.GRIEVANCE REDRESS MECHANISM...... 50

IX.ENVIRONMENTAL MANAGEMENT PLAN ...... 53

A. Summary of environmental impacts and mitigation measures ...... 53

B. Environmental Monitoring Plan...... 53

C. Institutional Arrangement ...... 61

D. Environmental Management and Monitoring Costs...... 61

X.CONCLUSION AND RECOMMENDATION ...... 63

A. Project Findings...... 63

B. Recommendations ...... 64

C. Conclusion ...... 65

REFERENCES...... 66

ANNEXURES...... 68

Annex 1: List of species found in project area ...... 68

Annex 2: Summary of Public Consultation ...... 71

Annex 3: Photos from Project sites...... 76

Annex 4: MOU between BPC and Affected Persons...... 80

3

Abbreviations

ADB: Asian Development Bank BAP: Biodiversity Action Plan BHU: Basic Health Unit BPC: Bhutan Power Corporation CS: Community School DFO: Divisional Forest Officer DoF: Department of Forest DoE. Department of Energy DYT: Dzongkhag Yargay Tshogchhung EA: Environmental Assessment EA: Executing agency EC: Environmental Clearance EIA: Environmental Impact Assessment FYP: Five Year Plan EMP: Environmental Monitoring Program FNCA: Forest and Nature Conservation Act HH: Household HSS: Higher Secondary School IA: Implementing Agency H&S: Health and Safety JSWNP: National Park LSS: Lower Secondary School LV: Low Voltage MoA: Ministry of Agriculture MSS: Middle Secondary School MTI: Ministry of Trade and Industry MV: Medium Voltage NCD: Nature Conservation Division NEC: National Environment Commission NES: National Environment Strategy NGO: Non-Government Organization NWFP Non-Wood Forest Product O & M: Operation and Maintenance ORC: Out Reach Clinic PA: Protected Area PM: Project Manager/Park Manager PPE: Personal protective equipment PPTA: Project Preparatory Technical Assistance PS: Primary School RE: Rural Electrification RGOB: Royal Government of Bhutan RMNP: Royal Manas National Park RNR: Renewable Natural Resources RoW: Right of Way RSPN: Royal Society for the Protection of Nature TOR: Terms of Reference TNP: Thrumshingla National Park

4

Tables Table 1: Summary of distribution lines (length in metres) Table 2: Improvements in rural electrification infrastructure proposed Table 3: Length of distribution line through different types of land use (length in metres) Table 4: Length of MV line passing through private land (length in metres) Table 5: Comparison of alternatives Table 6: Details of public consultation conducted Table 7: Summary of public consultation Table 8: Length of distribution lines and affected persons/beneficiaries Table 9: Total length of feeder through government and private land (length in metres) Table 10: Environmental Impacts and Mitigation Table 11: Environmental Management Plan Table 12: Cost of implementing EMP and monitoring

Maps Map 1.1: Map of proposed distribution lines Map 1.2: Map of FeederARE101 Map 1.3: Map of Feeder ARE102 and Feeder ARE103 Map 2: Map of Bhutan highlighting Trashigang Map 3: Map of Protected Areas in Bhutan

Glossary of Bhutanese Terms

Chathrim: Act, statute Chiwog: A unit under a Gewog Chuzhing: Irrigated/Wetland : Sub-district Dungpa: Sub-district administrator Dzong: The administrative center as well as religious centre in the district Dzongdag: District administrator Gewog: Block/ County Gup: Head of a Gewog Kamzhing: Dryland Lhakhang: Temple Rabdeys: Monastic bodies in Dzongs other than and Sokshing: Area where dried leaf litter is collected to make manure Tsamdro: Pasture land Tseri: Shifting cultivation, Slash and burn cultivation Tshechu: Religious festival Tshogpa: Elected representative of a Chiwog

5

List of Terms AAAC All Aluminum Alloy Conductor ABC Arial bundle cable ACSR Aluminum Conductor Steel Reinforced ADB Asian Development Bank AEC Agriculture Extension Centre BHU Basic Health Unit BPC Bhutan Power Corporation BPC/ES BPC Environment Section BWS Bumdeling Wildlife Sanctuary DCS Distribution Construction Section DFO Divisional Forest Officer DOE Department of Energy, Ministry of Trade and Industry Dzongkhag District DYT Dzongkhag Yargye Tshogchung EIA Environment Impact Assessment ESD BPC Electricity Services Division FO Dzongkhag Forest Office Gewog Block GIS Geographic Information System (software) GYT Gewog Yargye Tshogchung IEE Initial Environment Examination JBIC Japan Bank for International Cooperation JDNP National Park JICA Japan International Cooperation Agency JSWNP Jigme Singye Wangchuck National Park LEC Livestock Extension Centre LV Low voltage ( 400V, 240 V) LUPP Land Use Planning Project MoA Ministry of Agriculture MTI Ministry of Trade and Industry MV Medium voltage (33 kV, 11 kV) NEC National Environment Commission NFE Non-Formal Education NRDCL Natural Resource Development Corporation Limited ORC Out Reach Clinic PC Public Consensus PPTA Project Preparatory Technical Assistance (ADB) RE Rural Electrification

6

RED BPC Rural Electrification Department The Integrated Master Plan Study for Dzongkhag-wise REMP Electrification in Bhutan RMNP Royal Manas National Park RNR Renewable Natural Resources RoW Right of way RWSS Rural Water Supply Schemes S/S Substation SAPROF Special Assistance for Project Formation (conducted by JBIC) SWS Sakten Wildlife Sanctuary ToR Terms of Reference TNP Thrumshingla National Park

(Unit) A Ampere V Volt kV Kilo Volt kVA Kilo Volt Ampere kW Kilo Watt MT Metric Ton MW Mega Watt (one million Watt) MVA Mega Volt Ampere

7

I. EXECUTIVE SUMMARY

1. Bestowed with abundant water supply from fast flowing rivers over mountainous terrain, Bhutan has long recognized the potential to generate hydropower generation and the possibility of enhancing its GDP from the energy sector. Since 2007, hydropower generation has quadrupled to 1,489 MW and is further expected to increase to 1,602 MW by the end of the Tenth Plan and possibly reach 10,000 MW by 2020 (GNHC, 2009). At the same time, the guiding philosophy of Gross National Happiness dictates that development planning essentially focuses on fulfilling the fundamental objectives of achieving broad based sustainable growth and improving the quality of life while ensuring the conservation of the natural environment.

2. The overall objective of the Energy Sector for the Tenth Plan is the sustainable development and efficient use of energy resources for socio-economic development. While hydro-power development will provide environmentally clean, safe and reliable energy as well as contribute to GDP, providing electricity aims to improve the quality of life and living standard of rural communities, while contributing to self reliance.

3. In its “Vision 2020, Electricity for All” the Royal Government of Bhutan’s (RGOB) pledged to provide 100% electrification by 2020. Accordingly the Rural Electrification Master Plan targeted 85.6% electrification under the 10th Five-Year Plan (FYP: 2008-2013). Since then, the new democratically elected government has placed even higher priority on the goal of achieving its vision of “Electricity for All” and has brought forward the target completion to 2013.

4. ADB has helped Bhutan expand rural electrification (RE) via four loans since 1995, covering over 20,000 households (HH). ADB has helped Bhutan expand rural electrification (RE) via four loans since 1995, covering over 19,250 households (HH) which along with other donors enabled the RGoB to achieve approximately 60% electrification of the nation’s total households. Since 2008, with two more on-going rural electrification projects being implemented with loan from JICA and grant from ADB, the electrification rate is expected to reach 84% by the end of 2012. That will leave approximately 8,960 households to be electrified to meet the goal of electricity for all by 2013

5. The Royal Government has sought the assistance ADB to assist the Ministry of Economic Affairs to i) Plan and prepare an investment program to assist the Government achieve its goal of providing electricity for all by 2013; (ii) Develop a sustainable business model for operating and maintaining off-grid and ongrid rural electrification services, and (iii) Develop a wind power pilot project and a biogas program. This TA has five components: (i) On-grid rural electrification project, (ii) Off-grid solar home lighting system project, (iii) Operation and maintenance (O&M) business models for off-grid and on-grid rural electrification services, (iv) Wind power pilot project, and (v) Biogas program.

6. The Accelerated Rural Electrification Project (ARE) is a component under the On-grid electrification project initiated to ensure that all remaining households are provided with either on-grid or off-grid/solar electrification. Under the ARE project a total of 8957 households in 478 villages from nineteen Dzongkhags (Thimphu, Paro, Punakha, Wangdue, Ha, Chukha, Samtse, Dagana, Gasa, , Zhemgang, Tsirang, Pema Gatshel, Mongar, Lhuentse, Trashi Yangtse, Trashigang, Samdrup Jongkhar and Sarpang) that can be connected through on-grid electrification have been identified.

8

7. From these the RGOB has requested further ADB assistance in providing power to 5172 rural households in 6 dzongkhags (Zhemgang, Mongar, Lhuentse, Trashi Yangtse, Trashigang, and Samdrup Jongkhar). When this project is completed, the on-grid electrification is expected to cover 88% of the total number of Households in the country while the remaining 12% will be provided electricity through off grid means.

8. Bhutanese law and ADB policy require that the environmental impacts of all development projects are identified and assessed as part of the planning and design process, and that action is taken to reduce those impacts to acceptable levels. This is done through the environmental assessment process, which has become an integral part of lending operations and project development and implementation worldwide. The Implementing Agency BPC has produced Environmental Clearance Applications required by national legislation for the sub- project.

9. IEES for all each sub-project has been prepared according to ADB Safeguard Policy (2009) and the Environmental Assessment Guidelines (2003) as well as the RGOB Environmental Assessment Act (2000).

10. This document is the IEE for Trashigang Rural electrification subproject. It is one of six IEE documents describing the environmental impacts and mitigation of all subprojects proposed by the Project Preparatory Technical Assistance conducted in 2009-2010. These documents were prepared from January 2010 - April 2010 by one Domestic Environmental Specialist via input of six months. These Environmental Impact applications have been endorsed and approved by the EA.

Sub-Project description and findings.

11. Through the Rural Electrification Project, the BPC aims to electrify 78 households and 4 temples in Merak and Uzdorong gewogs in Trashigang dzongkhag. There are three 33kV Medium Voltage distribution lines that will provide electricity to 5 villages that presently do not have access to power supply. These rural populations presently do not have access to power supply. This will assist the RGOB towards their target of providing electricity to all citizens by 2013; and it should also generate significant improvements in environmental and social conditions in the rural areas

12. ADB Environmental Assessment Guidelines require that an IEE should evaluate impacts due to the location, design, construction and operation of the project. Construction and operation are the two activities in which the project interacts physically with the environment, so these are the two activities during which the environmental impacts occur. In assessing the effects of these processes therefore, all potential impacts of the project have been identified, and mitigation devised for any negative impacts.

13. This is a rural electrification sub-project that is expected to generate significant improvements in environmental and social conditions in the rural areas. These include:  Improvements in the quality of life from the availability of electricity;  Reductions in production of greenhouse gases from burning of kerosene and wood;  Long-term reductions in environmental damage from the logging of trees for fuel;  Improvements in health from reduced exposure to smoke and other pollutants;  Reduction in time spent collecting and transporting firewood;  Opportunities for alternative livelihoods, generating socio-economic benefits;

9

 Contributing to the long term goals of Conservation of the RGOB.

14. Minimal negative impacts are expected from the project on Climate, Geology and seismology, Industries and Tourism. This is because the short-term production of dust is the only effect on atmosphere, excavation will not be large enough to Geology, there are no major industries in any areas to be affected by the project and there are very few tourists that visit these villages because of their remote locations.

15. As is the case with most RE schemes, the most significant impacts are the result of the design of the project, as they would not occur if off-grid methods of electrification, by the use of solar panels, had been proposed. Off-grid methods were considered during the planning stages and rejected because in Bhutan they only provide sufficient power for lighting, and have a high maintenance and environmental cost because of the need to replace and dispose of the batteries.

16. The one impact that is clearly a result of both design and location is the ecological impact of clearing the RoW through forested areas for the MV lines, because the target villages are located inside forested areas. While there are three distribution lines proposed for Trashigang, 5km of one Feeder (ARE101), passes through the Biological corridor connecting Sakteng Wildlife Sanctuary to Khaling Wildlife Reserve. This impacts however would not have occurred if the MV lines could have been routed through other government forest areas to these villages (which was not possible), or if the MV lines were run underground (which was not considered because of the excessive cost). The other two feeders RE102 and ARE103 do not traverse any protected areas.

17. It should be noted however that the environmental assessment did not consider this to be a major source of impact, because the provision of electricity to rural communities conserves more trees in the long term than are removed from the RoW, because of the reductions in the felling of trees for firewood. Also, only 17% of the total length of the distribution line for the entire district falls under the Biological Corridor area, which has been designated to ensure that there is adequate forest habitat to allow safe passage of wildlife between two Protected Areas.

18. Impacts from Construction are expected once the project implementation begins and have been segregated under Physical, Ecological, Development and Social and Cultural impacts. The only major impacts from Construction are those resulting from the need to clear fell a 12m RoW along 86% (25.3km in broadleaf forest and coniferous forest) of the distribution line. The removal of trees and other vegetation from along the MV line will have ecological impacts as it will destroy forest habitat and displace species that are living in these areas This negative impact, albeit a permanent one is not expected to be significant because;  The MV line routes have been chosen in close consultation with the Department of Forestry staff with the aim of minimizing as far as possible the need for forest clearance and the acquisition of private land. As such MV lines are aligned close to farm roads and main access routes to the villages used daily by local people,  Much of the Construction work involves clearing the by small teams or workers using chain saws to fell trees and lop larger branches. The RoW will be previously marked by Forestry staff and clearing of RoW will also be monitored by them,  Most of the construction work is small in scale (involving the excavation of small pits for pole foundations and erection of poles and stringing of conductors), and will be conducted by small teams without the use of heavy vehicles and machinery;

10

 Construction work is relatively straightforward and can be completed in a fairly short time (approximately one year for this subproject).  The long term effect of electrification of villages is expected to outweigh the short terms impacts of felling along the right of way of the distribution line as providing electricity to rural communities has frequently been shown to deliver major long-term ecological gains that greatly outweigh the short-term losses as people use electricity for cooking and heating instead of firewood, reducing the felling of trees;

19. All other physical impacts such as those on air quality, noise, soil stability and erosion, natural drainage and aesthetics are assessed as Not Significant, mainly because these impacts are limited temporarily to the construction period and spatially to the immediate surrounding along the distribution lines and excavation sites at pole locations. Another reason is the remote location of the target villages, surrounded by forest to absorb any dust or noise as well as buffer aesthetic impacts.

20. In terms of social impacts, the project will bring about positive socio-economic impacts by providing electricity for lighting, cooking and heating for individual households as well as government and religious institutions. A number of secondary impacts are expected to occur as a result of the project. These include positive impacts on the health and lifestyle of local people through the use of clean technology, improved communication, networking, security, and increase in opportunities for seeking other livelihood options. Residents can save time and money which would have been spent processing for fuelwood permits and kerosene coupons while students and religious practitioners will have more time for study.

21. Impact on agriculture and private land, facilities and social and cultural resources are also considered Not Significant because the quantity of private and agricultural land that will be affected is very small and dispersed and the harvested crop is mostly used for self consumption. There are four temples that also benefit from the project and impacts on these and other facilities can be mitigated through prior planning, scheduling of work, consultation with local communities and by giving due consideration to local priorities. Visual impacts are generally considered significant where they affect large numbers of people, and that will not be the case here because of the remote nature of these areas.

22. Negative social impacts from the project may result if external workers are brought in from outside the gewog as this can sometimes cause social problems and there is also the risk of diseases like HIV/AIDs, Swine flu from socializing with contract workers as they may not have been properly screened for diseases. This impact is not expected to be significant because in any village work will probably be conducted by one or two small teams of 5-10 workers each, so individual locations will not experience a large influx of foreign workers. This can be mitigated through proper training, awareness raising and precautions and setting of rules and regulations for workers by contractors.

23. The Impacts from Operation and Maintenance are mainly those that occur from keeping the RoW clear of vegetation to reduce the risk of short-circuits and occasional repairs to address power outages and other problems during maintenance. Impacts on physical resources, ecological resources and economic development are not significant because RoW clearance is not as intensive and will not cause as much destruction and disturbance as during the construction Phase. Also, impacts will only occur during maintenance works and will be limited spatially to the same area as the construction Phase. This will not involve any major changes to the newly constructed project.

11

24. The main hazard to people from the operation and maintenance of the completed RE system is the risk of electrocution. This is a danger to rural consumers unaware of the risks of electrocution and to BPC workers conducting repair and maintenance work. BPC has already gained ample experience in implementing past Rural Electrification projects in all Dzongkhags, and staff are well aware of the risks of such projects. Also, there are established procedures for repair and maintenance of distribution lines which is being practiced very efficiently elsewhere.

25. Mitigation measures during the Construction Phase include those to reduce the impacts of forest cover, endangering vulnerable species, or reducing physical impacts such as air, noise, and drainage and land stability. The Contractor should be required to provide training to raise the awareness of all site workers and staff, prohibit any hunting, fishing or similar activities by site personnel, and ensure that labour camps are located in areas where no forest clearance is required and to ensure that labour camps are provided with adequate heating and lighting. The Contractor should also process for permits for firewood from the Forestry Office so that workers do not need to illegally collect firewood

26. Efforts should still be made to reduce the level of social disruption where possible, and to achieve this, the Implementing Agency should consult all affected communities in advance to inform them of the purpose, nature, duration, extent and timing of all work in and around their village and plan the work to avoid sensitive times.

27. During Operation and Maintenance, mitigation of impacts are easier than those during construction Phase as this involves following the procedures already laid out in the Operation and Maintenance (O&M) manuals and well as the Health and Safety (H&S) Manuals. BPC should also conduct regular training for all BPC staff to improve operation and maintenance works, improve supervision of field workers during all phases as well as conduct community education programs to raise the awareness of all target households before and after they are connected to the grid regarding the dangers of electricity, and the precautionary manner in which house systems should be used.

12

II. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. Policies relevant to the project

28. There are a number of laws and regulations that include elements that may apply to RE subprojects, depending upon their specific nature and location. These include the following:

a. Electrification Act 2001

29. Rural Electrification is strongly promoted in the Electricity Act, 2001. Part 7, Section 61.1 states that “The Minister Shall undertake to promote, support and provide rural electrification programmes through public and private sector participation in order to 1. achieve equitable regional distribution access to electricity; 2. maximize the economic, social and environmental benefits of rural electrification subsidies; 3. promote extension of the grid and development of off-grid electrification; 4. promote renewable energy.”

b. Forest and Nature Conservation Act (FNCA) 1995:

30. The Forest Act (1969) was the first environmental legislation in Bhutan and brought all forest resources under government custody to regulate utilization. This was repealed with the enactment of the FNCA in 1995, which allows community stewardship of forests, and aims to provide protection and sustainable use of forests, wildlife, and related natural resources. Schedule 1 lists those wild animals and plants that are given full protection under the Act and many of these may be found in areas through which rural electrification lines may pass. The FNCA establishes that all forests in Bhutan are Government Reserved Forests (GRF), and prohibits any development activity in these areas except with a permit.

c. Forest and Nature Conservation Rules

31. In Bhutan “Forest” means any land and water body, whether or not under vegetative cover, in which no person has acquired a permanent and transferable right of use and occupancy, whether such land is located inside or outside the forest boundary pillars, and includes land registered in a person’s name as Tsamdrog (grazing land) or Sokshing (Woodlot for collection of leaf litter)i . The Country currently has 72.5% forest cover. In 1974, a new Forest policy was promulgated wherein it was declared that at least 60 percent of the country must remain under forest cover for all times. This first declaration was followed in the next few decades by a series of positive initiatives by the RGOB to bring forest areas under protected area status.

32. Under powers established by the FNCA, the Ministry of Agriculture promulgated the FNCR in 2000, which was revised in 2006. Amongst other things the FNCR allows for:  Allotment of land and land rights in GRF;  Prohibitions, restrictions and concessions in GRF;  Transport and trade of forest produce;  Declaration and administration of protected areas;  Protection of wildlife and use of certain wild species;  Prevention of forest fires, land clearance, and activities potentially impacting soil, water and wildlife resources;  Enforcing penalties for offences related to these and other aspects of the FNCR. 13

33. As RE subprojects are likely to involve some of these activities, formal “No Objection” from the Department of Forests (DoF) will be required.

34. Since 2008, there are now five National Parks, four Wildlife Sanctuaries and one Strict Nature Reserve in Bhutan. These protected areas have conservation policies that state that all proposed development projects within the boundaries of the protected area will be subject to an EIA under the jurisdiction of the NEC. This initially included buffer zones outside the protected areas, but was extended to include Biological Corridors in 2006 by an addendum to the FNCR.

35. The Forest and Nature Conservation Act of 1995 defines "Protected Areas" as any national park, conservation area, wildlife sanctuary, wildlife reserve, nature reserve, strict nature reserve, research forest or critical watershed. The Act gives the Government the power to declare any land in the country to be a protected as defined above for the preservation of areas of natural beauty, protection of biological diversity, management of wildlife, conservation of soil and water and related purposes. If any private registered land is taken under this section, compensation or alternative land rights shall be provided as per the Land Act.

36. Biological Corridors (BC) are defined as “areas set aside to connect one or more protected areas, which shall be conserved and managed for the safe movement of wildlife.” Although BCs do not have the same status as protected areas, activities such as new settlements, quarrying and mining, and leasing of land for grazing are prohibited. All other development activities, including construction of roads, electricity transmission and distribution lines, or any other structures, require a permit from DoF and an EC application to NEC, supported by an EIA.

37. Since more than 79% of the population live in the rural areas and forests cover 72.5% of the land area, it is impossible to separate communities from protected areas. In Bhutan, people were residing inside the PAs before these areas were declared ‘protected’. Although extra effort was made to exclude settlements while rationalizing the location of the national parks, invariably some settlements had to be included in the protected areas, primarily to accommodate the ecosystem representativeness and adjustment of physio-geographical boundaries. Recognizing the fact that it would be a traumatic process to remove the residents out of the national parks by force or legislative means, a more benign policy of working with the local people has been adopted through balancing conservation goals while also providing for the socio-economic development of rural residents.

d. Land Act 1979 (revised 2007)

38. The Land Act 1979 which provides the basis for land tenure in Bhutan was revised in 2007 to streamline many provisions in the Land Act. One major change was the establishment of an autonomous National Land Commission Secretariat which has been given full responsibility for all matters pertaining to land registration. Also the 20 land categories Have been reduced to seven categories in the revised Act including i) Chhuzhing (wetland), ii) Kamzhing (dry land) including orchard, iii) Khimsa (Residential land), iv) Industrial land, v) Commercial land, vi) Recreational and vii) Institutional land. Powers over land management have now been decentralized to local authorities like the gewog Tshogdue, Dzongkhag Tshogdue, and . These are empowered to resolve land dispute, endorse land transaction and conversion of land categories more efficiently.

14

39. Under this Act, there are provisions for requisition of land by the government, if it is required for the benefit of the country. In such cases, the affected person will be compensated with substitute land from the same Dzongkhag or given cash compensation depending on the land classification as per the prevailing land compensation rate determined by the Act. If a house is acquired, compensation is paid on the basis of an evaluation carried out by a qualified engineer appointed by the competent authority.

e. RGOB Decentralization Policy 2002

40. The Dzongkhag and Gewog Yargay Tshogdue Acts were implemented in 2002 to support the Government’s decentralization policy and empower locally elected community bodies (DYTs and GYTs) with the authority and responsibility to plan and implement development programmes and activities, including those related to environmental management. Through this legislation the DYT is able to:  Make recommendations on activities with major environmental impacts;  Designate and protect sites and monuments of cultural or historical interest;  Designate and protect areas of special scenic beauty or biodiversity, such as Dzongkhag parks and sanctuaries;  Establish and enforce regulations to control noise pollution;  Prohibit construction of structures within 50 ft of highways;

41. The GYT is able to establish and enforce regulations to:  Control and prevent pollution of air, soil and water;  Ensure safe disposal of waste and adequate standards of sanitation;  Conserve and protect water resources, including rivers, streams, springs and lakes; and  The GYT also has custody of communal lands and community forests and can prevent encroachment onto land and forest.

42. Thus development projects such as Rural electrification can be subject to regulation promulgated by the local authorities, especially during project implementation.

B. Environmental Clearance Procedures a. Environmental Classification

43. The environmental classification of projects is decided by NEC on receipt of the Environmental Clearance (EC) application submitted by the proponent. There are three possible outcomes: i) NEC may grant Environmental Clearance on the basis of the EC application if the application contains sufficient information and it is clear that the proposed development will not have significant negative environmental impacts; ii) NEC may deny Environmental Clearance on the basis of the EC application if the application contains insufficient information and it is clear that the proposed development will have significant negative environmental impacts that cannot be suitably mitigated; and iii) If the EC application contains insufficient information on the likely nature and extent of the environmental impacts of the project or the manner in which they will be mitigated, NEC will determine that an EIA is required.

15

b. Preparation of EC Application and Environmental Impact Assessment

44. The requirements of the EC application are set down in sectoral guidelines that were revised with ADB assistance in 2006; and for RE projects the relevant document is entitled “Application for Environmental Clearance: Guidelines for Transmission and Distribution Lines”.

45. The information required for environmental clearance is very specific, and in all cases includes information on the applicant, the project, funding agency, the affected environment, potential impacts, mitigation, monitoring and public consultation. In the case of power transmission and distribution lines information on impacts includes details of affected: areas, types, uses and tenure of land; houses/infrastructure; protected areas; wildlife; cultural and heritage sites; etc. BPC surveyors collect most of the data during route surveys when they conduct land use and ownership surveys along proposed transmission/distribution line routes, and by consulting local communities and the Department of Forest.

46. There are three key elements of the EC application. These include the provision of signed ‘No Objection Certificates (NOC)’ from all affected stakeholders/households, Forestry clearance from the Department of Forest and Dzongkhag Administrative Approval.

47. The Environmental Assessment Act requires the proponent to prepare Terms of Reference (ToR) for the proposed EIA, which is submitted to NEC for their review. NEC will either approve the proposed ToR, or suggest amendments, which the proponent is required to incorporate before the revised scope is approved. The proponent is then required to conduct the EIA and submit the report as described in the ToR.

c. Approval process

48. A key element of the national Environmental Clearance application process is the provision of signed No Objection Certificates (NOC) from stakeholders that are specified in the guidelines, including all affected households, Department of Forest, and other relevant Government Agencies (Dept of Culture, Nature Conservation Division, etc). The National Environment Commission does not consider an EC application that does not contain the necessary NOC and Forestry Clearance. The latter for example is not granted by DoF until a forestry official has surveyed the whole length of any proposed route and has physically marked those trees that may be felled to create the RoW. The NEC in turn requires that all proposed routes are field examinations are conducted by the District Environment Officer and recommended by the District Environmental Committee. This process ensures that the least environmentally disruptive routes have been selected. This elaborate process of revisiting the proposed sites by different agencies ensures that all possible options have been explored, and the most suitable one adopted.

16

III. DESCRIPTION OF THE PROJECT

A. Project description

49. The sub-project is located in Trashigang Dzongkhag, in eastern Bhutan. Through this project, electricity will be provided to 5 villages in Merak and Uzdorong gewogs. The project activities comprise of three basic elements: (i) Medium Voltage lines to convey electricity from an existing distribution line to individual village, (ii) Pole mounted transformers in or near villages to reduce the voltage from 33 KV to the 230 or 415 V required for domestic supply, and (iii) Service lines supplying electricity to individual consumers.

50. Under this sub-project, there are three 33 kV MV lines that will run for a total of 29.45km via an estimated 420 poles. These will connect to 5 transformers located in or near villages to be electrified, and from these a 17.75km LV network of 230 or 415 V will supply electricity to 78 households and four temples.

Table 1: Summary of distribution lines (length in metres)

LV MV length Voltage length Total Feeder Name (m) kV (m) Villages Consumer ARE1O1 21845.2 33 2861.9 1 11 ARE1O2 3304.871 33 9412.4 2 41 ARE1O3 4299.756 33 5472.2 2 30 Total 29449.83 143 17746.5 4 82

Feeder No. ARE1O1.

51. This is a 33kV distribution line totalling 21.85km, which will be constructed from Trephu to Khashitheng in Merak gewog. It will be tapped from the Trephu substation (63kVA.) Depending on the technical feasibility, this line will serve as the tapping point for another distribution line from Phaju Goenpa till Diafam (with 32 sub-feeders to 56 villages) further south under Samdrup Jongkhar Dzongkhag (included under Samdrup Jongkhar IEE report). From this, 1.2km of Low Voltage (LV) lines (230V or 415 V) will run to 9 households and 2 lhakhangs in Khashitheng village.

52. 5km of this feeder (23%) passes through the Biological corridor connecting Sakteng Wildlife Sanctuary to Khaling Wildlife Reserve. Therefore the loss of forest cover and habitat along the corridor is one that is due to the project location and design as the target village is located in the buffer of Sakteng Wildlife Sanctuary. The remainder of the distribution line traverses about 5 government owned grazing/pasture land and government reserve forest. About 1.5km traverses private land.

Feeder No. ARE1O2.

53. This is a 33 KV distribution line located in Udzorong Gewog. The total length of the MV line is 3.3km and the LV line is 5.5km. It will be tapped from Baypam substation, and will extend

17

Feeder No. ARE1O3.

54. This is a 33 KV distribution line located in Udzorong Gewog. The total length of the MV line is 4.3km long and the LV line is 3.3km. This feeder will be tapped from Dothphu substation and extend to Mankhar and Lenchi villages. This feeder will provide electricity to 30 beneficiaries. This distribution line does not fall in any protected area. About 64% (2.75km) of this feeder traverses government reserve forest while the remainder (1.5km) traverses private land.

55. The MV lines will carry either 33 KV via three strands of aluminium conductors, mounted on poles located at intervals of around 50-70 m, depending on topography and terrain. Poles are of cast iron, with an iron cross-piece at the top on which insulators are mounted to hold the conductors. Section Poles have two legs and are located every 200-250 m, and between these are located a series of single-strut Interval Poles, to support the conductors and maintain them the requisite 5.8 m above ground level. Poles are 10 m in length and are held in the ground via earth and concrete foundations, 1.6-1.9 m in depth.

56. Conductors are either bare or covered. Bare conductors are of the Aluminium Conductor Steel Reinforced (ACSR) type, which consist of several strands of aluminium wire wound around a central steel core. Covered conductors are of the Aerial Bundle Cable (ABC) type, in which insulated strands of aluminium are wound together and covered with poly-ethylene insulation. Covered conductors are used for LV lines in inhabited areas, but may also be used for MV lines in locations where it is necessary to reduce the width of the Right of Way (RoW) cleared on either side of the line. In forested areas all vegetation is cleared from a specified width around the transmission or distribution line to prevent interruptions in supply from falling trees, or branches touching the line. For bare conductors the RoW is 12 m and for covered conductors it is 4 m (because the insulation reduces the risk of outage).

57. MV lines cross mainly forested areas, but as noted above, routes have been selected to run along existing farm roads, tracks and pathways where possible, because in these areas there has already been some clearance of trees and other vegetation, so this reduces the amount of new felling required. No clearance is required where routes cross public or agricultural land, and at farm sites, poles will be located on field boundaries where possible, to reduce the loss of productive land.

58. Transformers are ready-made components imported from overseas, which are located with associated components (junction box, fuses, lightning arrestors) on double-strut poles inside or outside the villages to be electrified. Transformers have an outer metal casing and measure around 1 x 1 x 0.25 m for the LV lines, and the junction box is slightly larger.

59. A local network of single LV covered conductors (230 or 415 V) will run from each transformer to the supplied village or villages, and branches will run to individual consumers (households, facilities or industries), terminating at a service meter on an outside wall. Conductors will be held on single-strut poles, located alongside the unpaved roadways and at other unobtrusive locations, at intervals of approximately 50 m.

18

Map 1.1: Proposed Distribution lines under this sub-project

19

Map 1.2: FeederARE101

20

Map 1.3: Feeder ARE102 and Feeder ARE103

21

B. Project budget and implementation

60. Detailed design of the project began in 2009 and should be completed by end of 2010, after which construction will be initiated. All the work should be completed by the end of 2013.

61. The project cost is presently estimated at Nu. 9.7million. This is an initial estimate and may change depending on change in prices in material cost as well as changes in regional and local transportation cost. Construction of this subproject should take approximately one year.

22

Table 2: Improvements in rural electrification infrastructure proposed

Infrastr Functi Description Location ucture on Medium Convey Six strands of 11 kV aluminium conductors (power None of the MV lines lie in protected Voltage electricity cables), strung between iron poles located every 50-70 areas. Howve, they do run through forest, (MV) Line from an m. Poles are 10 m long and project 8 m above the farmland and public land, and routes are existing ground, and are of cast iron with a cross-piece at the aligned along existing farm roads and distributio top containing insulators to which conductors are paths where possible. On farm land, poles n line to attached. Section Poles have two legs and are located will be located at field boundaries where a every 200-250 m, and between these are single-strut possible. transform Interval Poles. Bare conductors contain aluminium Feeder No. ARE1O1: Merak gewog er. strands wound around a steel core; and covered Feeder No. ARE1O2: Udzrong gewog conductors consist of insulated strands of aluminium, Feeder No. ARE1O3: Udzrong gewog wound together inside polyethylene insulation. Feeder No. ARE1O1: MV length = 21.85km, 437 poles Feeder No. ARE1O2: MV length = 3.3km, 66 poles Feeder No. ARE1O3: MV length = 4.3km, 86 poles Total length- 25.3km Transfor Reduce Pre-manufactured electrical component in metal Generally one transformer per electrified mer voltage casing, approximately 1 x 1 x 0.5 m. Numbers per village, on a pole inside or outside the from 33 gewog: village. Villages as follows: kV in the Feeder No. ARE1O1: 1 transformer Feeder No. ARE1O1: khashitheng plus MV line Feeder No. ARE1O2: 2 transformers villaged under Samdrup Jongkhar IEE report to 230 or Feeder No. ARE1O3: 2 transformers Feeder No. ARE1O2: Gyenkhar A and B 415 V in Feeder No. ARE1O3: Mankhar and Lenchi the LV Line. Low Convey Generally single strand of LV covered conductors (230 Total number of connections: 170 Voltage electricity V for single phase, 415 V for three phase), mounted Feeder No. ARE1O1: 29HH, 2 L (LV) Line from a on single poles at 50 m intervals. Each line terminates Feeder No. ARE1O2: 39HH, 2 L transform at a service meter on an external wall of the consumer Feeder No. ARE1O3: 30 HH er to (household, facility, industry). Length of LV line: Total 78 HH, 4 L each Feeder No. ARE1O1: 2.8 km individual Feeder No. ARE1O2: 9.4 km consume Feeder No. ARE1O3: 5.5km r Total length-17.7km

HH- households, S- School, L-Lhakhang, B-Basic health unit, R-Rice mill, G-Geog office

23

IV. DESCRIPTION OF THE ENVIRONMENT

A. Physical Resources

1. Location

62. Trashigang Dzongkhag covering an area of approximately 2966 km2 is the largest dzongkhag in the country. It is 555 km away from Thimphu and has Trashi Yangtse to the North, Mongar and Pema Gatshel to the East and Samdrup-Jongkhar Dzongkhag on its Southern side. India lies to the north-east and east border.

63. Due to its location at the eastern-most point on the East West highway, Trashigang town is an important center/market especially for farmers selling local produce from Mongar, Lhuentse and Trashi Yangtse as well as for travellers passing through to Samdrup-Jongkhar. At the same time, local farmers buy essential items imported from India via Samdrup Jongkhar. There are three namely Sakteng, Thrimshing and Wamrong and 15 gewogs (Bartsham, Bidung, Kanglung, Kangpara, Khaling, Lumang, Merak, Phongmey, Radi, Sakteng, Samkhar, Shongphu, Thrimshing, Yangneer and Udzarong) with 8,464 households.

Map 2: Map of Bhutan highlighting Trashigang

Source : RED, BPC and Dzongkhag Administration, Trashigang

64. The project sites are located in Merak and Udzorong gewogs. Merak gewog is located about 50+ km east of Trashigang close to Arunachal Pradesh, while Udzorong gewog is to the extreme east of the district. Merak gewog is one of the most remote gewogs in Trashigang. It has four villages with 255 households covering an area 867.7 sq. km with an extremely low population density. Udzorong gewog has eight villages with 544 households in an area of 100 sq.km which are also among the most remote villages in the gewog.

2. Topography, geology and soils

65. The elevation of Trashigang Dzongkhag ranges from 600 m to 4500 m above sea level. The valleys are deeply cut, with steep convex side slopes and narrow V shaped valley floors.

24

66. The Merak-Sakteng zone in Trashigang is an anomaly located on a Tethyan outcrop that is separated from the main Tibetan block. The block is aligned East-West and there are periglacial drift deposits on the dissected summits. The block disrupts the general North-South drainage pattern and prevents Nyera Amri from cutting back to the High Himalaya.

67. The surface drift comprises of Periglacial, Aeolian and colluvium on slopes and alluvium in high valleys. The soil types are temperate soils, stagnogleys, podzols, and alpine meadow soils (Norbu et al, 2003).

3. Climate

68. As Trashigang lies in the temperate zone, much of the Dzongkhag experiences warm summers and cold winters. Since Merak gewog is at higher altitudes the temperatures are colder and climate is sub-alpine and moist. The mean humidity per month ranges from 54-88, with highest humidity during the summer months (May-September). The total rainfall received per year fluctuates each year but ranges between 1000-1400mm. The average total rainfall received per year is 1223 mm per year. The mean maximum temperatures range from 13 Celsius in January to 25Celsius in August and during the cold months the minimum temperatures drop to as low as 5 Celsius.

4. Air Quality

69. There is no data available on the air quality of Trashigang, but as there is such a low population, very few vehicles and no heavy industry in the dzongkhag, then it is reasonable to assume that air quality is likely to be generally good. There should thus be low levels of pollutants associated with heavy industry, such as oxides of nitrogen (NOx) and sulphur (SOx), and exhaust emissions from vehicles, such as lead. However, as wood and kerosene are the main fuel for cooking and heating in non-electrified rural areas, then there may be localised increases in levels of smoke, soot and carbon dioxide in these areas at times when fuel usage is highest (in the evening and during the winter). Almost certainly within houses people are likely to be exposed to high levels of these pollutants.

70. In addition there are health impacts from the use of fire wood and kerosene lamp that causes eye and respiration problems. Use of electricity will contribute to the reduction of in- house air pollution from Bhukharis/stoves and fuel wood use.

5. Hydrology

71. The Dangme chu, one of the largest rivers in the country passes through the Dzongkhag Other rivers include the Gamri Chu which joins the Gongri chu and the Manas chu. The Jeri Chu flowing through joins the Dangme Chu further south, and the Jama Ri Chu flows south towards Samdrup Jongkhar dzongkhag. Rivers such as the Gamri are estimated to annually clear 105-106 m3 of soil and rock from the recently activated Shongri landslip complex at Radhi (Norbhu et al, 2003).

25

72. Merak is along the Nyera Ama chu while Sakteng is located on the lower valley along the Gamri Chu. Different streams such as Yengri Chu and Nyera Ama Chu, Gamri Chu, Bamukpa Chu and Sakteng Chu dissect the valleys in Sakteng Wildlife Sanctuary.

73. Because of the distinct dry and monsoon seasons and their greatly differing rainfall characteristics, flow in the rivers varies widely throughout the year. Most rivers swell to high levels in the summer when they carry large volumes of water and sediment brought in by the monsoon rains, but flow reduces dramatically during the dry season, when much of the sediment is left on the dry riverbanks. The mountainous terrain however ensures a continuing supply of water throughout the year, so most of the larger tributaries are perennial, even though dry season flow may be only a small percentage of the monsoon volumes.

B. Ecological Resources

1. Protected Areas

74. There are five National Parks in Bhutan, four Wildlife Sanctuaries and one Strict Nature Reserve, shown in Map 3. The protected area system was initially created in the 1960’s. However, these were mostly confined to the northern and southern regions of the country, so the PA system was revised to encompass all the different ecosystems and habitats in the country, resulting in 9 protected areas covering 26.5% of the country’s land area. In 1999, biological corridors were identified to link the various protected areas adding another 9% to the PA system. In 2008, a new park was created that further increased it to 48%. Now, Bhutan has one of the largest areas under protected area status.

Map 3: Protected Areas in Bhutan (source: WWF Bhutan)

75. The Sakteng Wildlife Sanctuary covers an area of 650 sq.km in Sakteng and Merak gewogs in Trashigang Dzongkhag. The Sanctuary is bordered by Arunachal Pradesh in the north and east, Phongmey Gewog and Kangpara Gewog in the west, and Shingkhar Lauri

26

2. Rare or Endangered Species

76. The Sakteng Wildlife Sanctuary is endowed with a wide variety of species, several of which are endangered or vulnerable, according to the International Union of Nature Conservation (IUCN) criteria, and others that are protected under the RGOB Forest and Nature Conservation Act (1995). SWS is also famous as it has the highest diversity of Rhododendrons in the country as well as the vast, pristine mixed conifer forest tracts. Local anecdotes have it that the Yeti or Migoe inhabits the Sanctuary (NCD, 2004) with footprints and hair evidence collected by the Department of Forest but yet to be verified.

77. In Trashigang species that can be found in the forest include Clouded leopard (Neofelis nebulosa), Red Panda (Ailurus fulgens), Red fox (Vulpes vulpes), Wild dog (Cuon alpinus), Himalayan yellow throated marten (Martes flavigula), Pikas and Squirrels (WII, 2005 and pers communication). In the project site, the species more commonly found include Common Leopard (Panthera pardus), Himalayan Black Bear (Selanarctos thibetanus), Capped langur (Trachypithecus pileatus), Serow (Capricornis sumatraensis), Goral (Naemorhedus goral), Wild pig (Sus scrofa), Porcupine (hysterix indica), Sambar (Muntjacus muntjak), Macaque (Macaca assamensis) and Barking deer (Muntiacus muntjac).

78. A total of 119 species of birds have been recorded in the sanctuary (WII, 2005), although there are no endangered species along the access routes. Many of the common species include Cuckoos, Pigeons, Dove, Nightjars, Thrushes, Bulbuls, Forktails, Redstarts, Wagtails, Choughs, Flycatchers, Swifts, Barbets and Sparrows.

3. Forest

79. 79% of the land area in Trashigang is under forest cover. The major forest types include broadleaf forest (36%) and conifer forest (30%). The remaining forest is mostly scrub forest. 4.8% of the land area is also under pasture.

C. Economic Development

1. Land use, industry and agriculture 80. Apart from the dense forest cover 14.2% of the land area is used for agriculture, 4.8% as pasture land, 0.1 % as settlement and 2% includes rocky outcrop or water bodies (DoF, 2002). Kamzhing (dry land) is the dominant agricultural land use followed by Chhuzhing (irrigated/wetland) and Tseri (slash and burn cultivation). Maize, wheat, millet potato, garlic, mustard, barley and chilli are the main annual crops which are sold in Samdrup Jongkhar. Limited arable land coupled with lack of farm infrastructure, in particular farm roads are the main constraints faced in farming. In the project areas, the main crops are also crop, followed by other cereals like paddy and buckwheat, pulses like rajma beans and soya beans, vegetables like chillies, potatoes and beans, and mustard. Quite often these crops are intercropped and most of this is grown for home consumption due to lack of access to market. The main fruits crops are orange, peach, walnut, apple, pear, plum, mango, guava, pomegranate and banana.

27

The nearest local market for any farm surplus is in Samdrup Jongkhar, which is 2 days walk from the project site.

81. Trashigang has one of the highest livestock populations in the country with almost 84,000 heads of livestock. Since the main source of livelihood is livestock rearing, the people of Merak and Sakteng keep large herds of cattle. Important livestock products are butter, cheese, zoedey (fermented cheese), yak meat and wool. Most of these products are bartered for food grains especially maize as no crops are grown due to high altitudes.

82. There are no large scale industries in Trashigang but there are 631 cottage industries, mostly service based, forest based or agro-based. There are also no large contract firms but there are about 60 Class C contractors and 393 petty contractors (National Statistics Bureau, 2007).

2. Infrastructure 83. The Dzongkhag administration is located close to Trashigang town, where all the major offices like the BPC, BDFC, Bank, Divisional Forest Office, Post Office, Police as well as automobile workshops are located. There are five smaller towns that are much smaller at Khaling, Rangjung, Kanglung, Wamrong and Reserbu. Sherubtse College is located at Kanglung and the Blind school is in Khaling. There are 60 academic institutions and 14 Shedras/Gomdras. In total there are 12,493 students and 468 teachers in the Formal Academic institutions (Department of Education, 2006).

84. Of the 72% residents that have access to piped drinking water supply, 11% have piped water inside the house. The remaining 17% use water from springs/rivers or ponds. There are 6800 sanitation facilities with pit latrines constructed outside the houses. Merak gewog has two rural drinking water supply schemes covering over 60% of the population while in Udzorong gewog 15 rural drinking water supply schemes deliver piped drinking water supply to over 70% of the population in the gewog.

85. Less than 40% of all households in the dzongkhag have electricity and most of the 500 telephone lines are in urban centres. The BMobile network is reachable in a few locations but not in the project area.

86. Currently there are 1384 households that are electrified in the dzongkhag which amounts to 39% of the total number of households in the dzongkhag. The majority of the un- electrified households are included for electrification under the Rural electrification IV and Accelerated Rural Electrification Project.

3. Transportation and access 87. Trashigang Dzongkhag is connected to both Samdrup-Jongkhar and the capital, Thimphu, by the lateral national highway. The dzongkhag has 121km of national highway, 5km of district road, 136.9km of feeder roads, 4km of urban road, 58.9km of farm road and 8.5km of forest road (total 334.3km)which amounts to only 7.4% of the road network in the country. There are still many villages that are inaccessible by motor roads with over 23% of the population living more than 3 hours from the nearest road head and remote villages like Merak and Sakteng take at least 2 days walk to reach the nearest road head.

28

88. In the 10th FYP farmroads from Chaling to Merak (20km) and from Phongmey to Sakteng (30km) were proposed under the Ministry of Agriculture under the Dzongkhag Rural Access Plan in the six eastern Dzongkhags and under Kangpara gewog, a farm road is being constructed till Kangpara which may be extended to Trephu. Transportation of Rural Electrification materials to Trephu will thus be easier once the farm road is constructed. As for Khashitheng, this village is easier to access from Samdrup Jongkhar dzongkhag.

89. Private minibuses provide a service to the dzongkhag from Samdrup Jongkhar and Thimphu. Due to lack of roads, there are few vehicles in the villages where transportation is mainly by foot or on horseback.

90. There is no air travel within Bhutan as the only airport is at Paro, 30 km west of Thimphu.

4. The tourist industry 91. Visitor numbers have continued to rise, particularly over the past few years, despite the requirement for all tourists to pay a non-refundable daily tariff of US $200 to the tour operator, for the cost of accommodation, food and internal travel. Tourism is now the third largest provider of foreign exchange in Bhutan, earning US$ 29 million in 2007, when 21,094 people visited.

92. Apart from Merak and Sakteng areas, there are not many open spaces with recreational values or cultural significance. Trashigang does have a number of tourists mostly travelling from Thimphu to Samdrup Jongkar and out of Bhutan via India. Because of the difficulty of internal travel in Bhutan, requiring long journeys on winding roads between and over mountains, only relatively few tourists venture to the east of the country, so there are few hotels or major attractions.

93. There are no visitors to the project sites only government employees. Tourism has had little impact in the villages, because of the difficulty of reaching most locations, so most villages remain much as they have for the past few centuries.

D. Social and Cultural Resources

1. Demography 94. The total population in Trashigang is 48,783. 90% of these are regular residents, 9% institutional residents and 1% transient people. There are 10, 813 households and the average family size is 4.3 persons per family. 13.3 % (6816) of the population lives in the urban areas. From the adult population 43% of the population are single, 50% married, 5% widowed and 1% divorced. The male to female sex ratio is 104:100. The total population of Merak in 2005 was 1621, which is 3.3% of the total population and which taking into account the size of the gewogs results in a density of less than 10 persons per sq.km.

95. The population of Bhutan includes many ethnic groups such as the Sharchops from the east, Ngalongs from the west, Khengpas from the central region, nomads from the north and Lhotshampas from the south. The majority of the population is Buddhist (around 70%) and the remainder are mainly Hindu.

2. Health, education and other facilities

29

96. There are 3 hospitals, 19 Basic Health Units (BHU’s) and 72 Out Reach Clinics (ORC’s) in the district which have successfully achieved over 90% immunization coverage. The 2005 Housing Census found that 91% of the households in Trashigang have visited a health facility and the reason for those that did not do so was because they did not get sick.

97. Merak gewog has one primary school with 140 students, one Basic Health Unit (BHU), one Livestock Extension Centre (LEC) while Udzorgong gewog has four community schools and one primary school catering to over 500 students.

98. There are also 28 RNR facilities including RNR Extension Centres, Agriculture Centres, Veterinary Hospitals and Forestry Offices spread throughout the dzongkhag.

3. History and culture 99. Apart from Merak and Sakteng areas, there are not many open spaces with recreational values or cultural significance. Rangjung and Radhi are considered two of Bhutan's most renowned weaving villages famous for naturally dyed raw silk textiles. Trashigang is better known for Sherubtse College which founded in 1978 and is located 25 kilometres south of Trashigang. Khashitheng the project site has no scenic, recreational or culturally significant sites.

100. The Dzong is used as the Spiritual, Judicial and Administrative Centre of Trashigang Dzongkhag. It was built in 1659 by Trongsa , Chogyel Minjur Tempa, the 3rd Deb of Bhutan and later expanded by the 4th Desi Tenzin Rabgye. The name Trashigang Dzong means “the Fortress of the Auspicious Mountain”.

101. So far a total of 1619 religious structures (lhakhangs, goenpas, gomdeys) have been listed with the Special Commission. Trashigang has 201 such sites, which the highest in any dzongkhag. In the project site, there are 4 religious sites, 2 at Khashitheng in Merak Gewog and 2 in Gyenkhar in Udzorong gewog.

30

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. Environmental effects due to project location and design

102. Most of the impacts that occur in this project are due to project location and design. This is because these impacts would not occur if an alternative location or design such as off-grid methods of electrification, by the use of solar panels, had been proposed. However this is not a valid comparison because off-grid methods were considered during the planning stages and rejected because they only provide sufficient power for lighting, and have a high maintenance and environmental cost because of the need to replace and dispose of the batteries.

103. The one impact that is clearly a result of both design and location is the ecological impact of clearing the RoW through the Biological Corridor. As pointed out in Chapter III, 23% (5km) of Feeder ARE101 passes through the Biological corridor connecting Sakteng Wildlife Sanctuary to Khaling Wildlife Reserve. The total length of this feeder which will be constructed from Trephu to Khashitheng in Merak gewog is 21.85km. At present this line ends in one village Khashitheng but depending on the technical feasibility, it may serve as the tapping point for another distribution line from Phaju Goenpa till Diafam (with 32 sub-feeders to 56 villages) further south under Samdrup Jongkhar Dzongkhag (included under Samdrup Jongkhar IEE report).

104. Therefore the most significant environmental impact will be the loss of forest cover and habitat along the corridor. Therefore the loss of forest cover and habitat along the corridor is one that is due to the project location and design and is very difficult to avoid as the target village is located in the buffer of Sakteng Wildlife Sanctuary.

105. The impact on the forest as stated previously is unavoidable as trees and other vegetation would not need to be removed if the MV lines could have been routed through un- forested areas to these villages (which was not possible), or if the MV lines were run underground (which was not considered because of the excessive cost).

106. The assessment does not consider this impact on the biological corridors as significant because;  The selection of the feeder route has been done in close collaboration with the Department of Forest that has conducted the field verification and given the Clearance for the proposed alignments.  The proposed alignment through biological corridor is along the access route to the target village where the forest is already degraded to some extent and unlikely to contain endangered species,  The length of the MV line across the biological corridor amounts to only 17% of the total MV length for the district. The remainder of this particular distribution line (ARE101) traverses about 5 government owned grazing/pasture land and government reserve forest. About 1.5km traverses private land where little of no clearing for RoW is required.

107. Despite this mitigation measures may be undertaken to ensure that environmental impacts during construction are minimized. These are discussed in the following paragraphs.

B. Environmental effects due to Construction

108. The one impact that is clearly a result of both design and location is the ecological impact of clearing the RoW through 25.3km of forested area as a RoW of 12 m will be cleared of

31

109. The provision of electricity to 78households and 4 temples in the 2 gewogs will involve construction of:  Three 33 kV MV lines totaling 29.45km in length, of mainly 3-strand bare conductors, located on 589 poles, to convey electricity from existing distribution lines;  5 transformers, which depending on the voltage level and the number of phases are either 33/0.240 kV or 33/0.415 kV for single and three phase lines.  17.75km of LV lines, of mainly single-strand covered conductors on 355poles to carry electricity to meters outside individual households.

110. Construction will probably start at the tap-off point from the distribution line, and the MV line will be cleared and constructed in sequence, gradually proceeding along the route. It is not expected that the construction work will cause major negative impacts. This is mainly because:  The existing lack of access roads to the sites means that all construction components will be carried by manpower to the site from the nearest road.  All other construction work is small in scale (involving the excavation of small pits for pole foundations and erection of poles and stringing of conductors), and will be conducted by small teams without the use of heavy vehicles and machinery;  MV line routes have been chosen to minimize as far as possible the need for forest clearance and the acquisition of private land;  14% of the MV line will be in un-forested areas, where the RoW will not be cleared;  Most of the affected areas outside the villages are uninhabited, and in villages work can be conducted without causing major disruption to people;  Construction work is relatively straightforward and can be completed in a fairly short time (approximately one year for this subproject).

111. Once a length of RoW has been cleared, foundations for poles will be dug by hand, at intervals of approximately 200-250 m for double-structure Section Poles, and 30-70 m for single-structure Interval Poles. Foundations are a standard size of 600 x 700 mm, dug to 1900 mm for 33 kV lines, and after excavation, concrete (mixed on site) is poured into the cavity to create a solid floor, around 250 mm thick. Poles are fitted with a circular metal base plate, which stands on top of the dried concrete, after which the excavated soil and stone is replaced around the pole and compacted tightly by hand. A further layer of concrete is applied 250 mm above and below the ground surface to resist corrosion. The conductors are then attached to insulators at the top of each pole by hand, after which the team moves on to the next location. Where the MV line crosses areas of open ground or agricultural land there is no need to clear the RoW, so the procedure will involve erection of the poles and connection of the conductors only

112. Transformers are attached to double-structure poles, located inside or outside villages. The poles are erected as described above, and the pre-prepared transformers and other components (junction box, fuses, etc) are attached and joined up by hand. Signs are then attached to the pole warning people of the dangers of electrocution.

113. LV lines in the villages will be constructed in the same way as the MV lines but there will again be no need to clear the RoW as poles will mostly be located within the villages, and in this case foundations will be slightly smaller, as the standard size for LV lines is 600 x 700 mm, dug to 1600 mm. Excavated material will again be replaced on top of the foundations once the

32

114. All elements will be completed before commissioning tests are conducted and the final connection to the distribution line will then be opened.

1. Air quality. 115. There is no data available on the air quality in Trashigang but the major contributors to air pollution in Bhutan are industries and vehicular emissions and the former is absent while the latter is minimal in the project site. The main source of pollution in the rural areas is domestic emissions from burning firewood for cooking and heating, use of kerosene for lighting and diesel for mills. These emissions cause localized increases in levels of smoke, soot and carbon dioxide, especially at times when fuel usage is highest. However, once the project is in operation, it is expected that these levels of pollutants will reduce with use of electricity as the amount of fuelwood will reduce and people inside the houses are less exposed to such pollutants.

116. With the initiation of the project, the only impact on air quality is expected from movement of vehicles and from the dust pollution, as dust may blow in from cleared areas at the poles site. Dust pollution caused by pole construction will be localised at pole sites and RoW only and limited to the construction period only. Most of the foundation for poles will be dug by hand and other implements and equipment (including poles and transformers) will be carried to site by porters, from the nearest road. Air emissions from vehicular movement will be minor as this is limited to a few vehicles to the few selected drop off points. Thus the impact on air quality will be low with no impact at the regional/Dzongkhag level.

117. Mitigation measures which could be undertaken on site include;  To reduce the dust from cleared areas along RoW, the lower ground layer of grass and other low vegetation should be retained and cut vegetation apart from logs can be piled at the edge of the RoW and allowed to dry or to rot down in situ;  Avoid using large machinery to minimize dust and do not burn waste vegetation to prevent forest fires.

3. Noise generation.

118. The main source of noise will be from trucks during material drop off at designated points and to campsites near road access points. These however will be limited to the construction period. All other construction work is small in scale (involving the excavation of small pits for pole foundations and erection of poles and stringing of conductors), and will be conducted by small teams without the use of heavy machinery. Thus noise generation is not expected to be significant as the area is so remote and villages are scattered. Also, with the large forest cover most of the noise created will be buffered by the surrounding forest. There should be no need to mitigate this impact.

4. Natural Drainage.

119. Where distribution lines cross rivers and streams effects on local drainage and water quality can occur during construction period mainly from loose soils at the excavated site for the pole foundations. This impact is however small in scale, dispersed and will only occur at crossing points. 33

120. Excavation can also affect aquatic ecology and fisheries if large quantities of silt are washed into the river during rain, or if work is conducted within the river itself. This should not be the case here however, because there is no requirement for any construction in river-beds. Also, excavation for the pole foundations is small in scale and dispersed, and there will be no large stockpiles of soil that could create a major point-source of silt pollution. Almost all of the excavated soil will be replaced into the cavity within a few hours of removal, so any run-off would be short-lived and very small in scale. It should therefore also be unnecessary to mitigate potential impacts on aquatic ecology.

121. To minimize the quantity of soil being washed into the river, it is recommended wherever possible, poles will be located at a minimal distance of 30 m from the river on stable soil. Also, excavation works should be conducted during the dry season (which is expected as it may be impossible to work during the monsoons when the river is too high to be crossed).

5. Soil stability and erosion

122. The elevation along the distribution line ranges from 700 m to 4000 m above sea level and the slope is mostly medium to steep (15-45 degrees). The removal of vegetative cover and soil excavation work may cause some land instability and soil erosion but this impact is expected to occur only during excavation for poles. Also, the depth of the foundation for the 33kV poles is 1900mm and the area for the foundation is 600mmx700mm (BPC, 2007). There are 589 poles to be constructed. This means that the total volume of soil to be excavated is only 470 m3. Once the poles are ready to be erected, most of the excavated soil will be reused for backfilling and compaction to secure the poles. This impact can be mitigated easily since the size of the excavated area is small. Safety for workers while working on steep slopes should be covered under worker health and safety issues. i. Impact on Physical Resources

Forest cover

123. Clearing the RoW is the activity that will bring about the most significant physical changes, as areas that are presently covered with vegetation will be left bare and large quantities of waste brush and timber will be produced. Dust may blow from bare ground, and this could be a health hazard for workers and a nuisance where cleared areas are close to places where people live and work (villages, fields, farm roads, or footpaths). There would also be a serious risk of causing forest fires if contractors were to attempt to burn the waste vegetation.

124. The entire route was surveyed in the course of this study and observations were made regarding land use and ownership, as well as the type of forest and other factors. The Table below shows the main results.

Table 3: Length of distribution line through different land use (length in metres)

Feeder Broadleaf Conifer Sokshing Tseri Scrub Total length ARE101 8000 5850 0 0 6500 20,350 ARE102 0 2200 0 0 0 2200 ARE103 0 2750 0 0 0 2750

34

Total 8000 10800 0 0 6500 25300

125. This shows that along the 29.45km route of the MV line, 25.3km (86%) runs through forest, in which a total of 0.30 km2 will be cleared. In the context of the total of 30,000 km2 of forest in Bhutan, this may not be a major loss but efforts should still be made to reduce the physical impacts of this activity by limiting the generation of dust, and prohibiting the burning of waste material. The contractor appointed should be required to:  Leave a covering of grass and/or other naturally occurring low-growing vegetation where possible along the RoW to reduce dust;  Avoid burning waste vegetation and instead leave this material in situ after cutting, to rot down gradually, and discourage re-growth whilst it is decomposing;  Dispose of all cut trees as required by the Forestry department, who will put the timber to beneficial use, thus reducing the cutting of new trees.

126. The rest of the work involves the excavation of a series of pits for the foundations of the poles for the MV and LV lines and transformers. Excavation is physically invasive and can cause other impacts including: air pollution if dust is produced during digging or blown from piles of soil retained on site; pollution of rivers and groundwater if silt is washed from piles of soil during rainfall; and changes in drainage patterns if rainfall or groundwater collects in excavated areas. Most of these impacts should not be significant in this case because:

 Only a small quantity of material will be excavated, comprising 0.7-0.8 m3 per pole, and 470 m3 in total;  Almost all of the excavated material will be replaced and compacted around the pole foundations, so material will only be stockpiled for a few hours;  Poles are located 30-70 m apart (depending on the terrain), so there will be no large concentration of excavated or stockpiled material at any one location;  Contractors will almost certainly conduct excavation in the drier months to avoid the difficult and often dangerous working conditions of the monsoon.

It should therefore not be necessary to apply any mitigation measures to reduce the physical impacts of the excavation.

127. Construction will also affect the landscape, as in some locations the cutting of trees and erection of poles and conductors may be visible for some distance especially where the MV line runs along a hillside. However this should also be an impact that does not need to be mitigated, because:  The forest itself will provide a good natural screen as in many areas the trees outside the RoW will be taller than the electricity poles;  Visual impacts are generally considered significant where they affect large numbers of people, and that will not be the case here because of the remote nature of these scattered houses.

ii. Impact on Ecological Resources

128. During the field visit, there were not many signs of wildlife that could be observed for two reasons, lack of visibility due to rains and fog and probably because the disturbance caused by trampling probably scared away any animals that could be observed. Since the route is used by residents on a daily basis, no endangered species are expected to use these areas as core habitats.

35

129. The removal of trees and other vegetation from along the MV line will also have ecological impacts as it will destroy forest habitat and displace species that are living in these areas. This could affect large and small mammals, birds, reptiles, amphibians, insects and other invertebrates, which might include some of the rare or important or even possibly species that have yet to be recorded, given the unexplored nature of much of the Bhutanese forest. Larger and mobile inhabitants will simply move away to other areas, but some could be damaged or killed during the clearing process. Most of these impacts should not be significant in this case because;

 Providing electricity to rural communities has frequently been shown to deliver major long-term ecological gains that greatly outweigh the short-term losses as people use electricity for cooking and heating instead of firewood, reducing the felling of trees;

 Route alignments were selected along existing farm roads and footpaths where possible, as these areas are already disturbed and degraded to an extent, and are thus unlikely to contain key species;

 Although 0.30 km2 of forest will be lost, only 5km of one feeder passes through biological corridor. Also, although it falls in government reserve forest, there are five pasture/grazing land where little or no clearance for RoW is required,

 The motility of most animals means that they are very likely to move away in response to the disturbance caused by the felling activity, thus avoiding accidental damage or death.

Regardless of these factors, efforts should still be made to reduce the loss of forest where possible, particularly in densely forested parts where the habitats would be more ecologically valuable. To reduce ecological impacts and unnecessary damage to vegetation the contractor should undertake the following actions:  Ensure that the only trees to be felled are those that have previously been marked by the Department of Forests1;  Prohibit any hunting, fishing or similar activities by site personnel and enforce this measure strictly;  Provide training to raise the awareness of all site workers and staff on the value and fragility of wildlife and natural habitats, particularly those found in these locations;  If workers are housed in labor camps near the sites, ensure that these are located in areas where no forest clearance is required,  Ensure that labor camps are provided with adequate catering, heating and other services, so that workers do not need to hunt or collect firewood.

130. Excavation can also affect aquatic ecology and fisheries if large quantities of silt are washed into the river during rain, or if work is conducted within the river itself. This should not be the case here however, because:  Although the MV lines do cross rivers there is no requirement for any construction in river-beds;  It is very likely that Contractors will excavate in the dry season to avoid the difficult working conditions of the monsoon;

1 Before providing the No Objection Certificate that is required as part of the application for Environmental Clearance, staff from the Department of Forests inspect the proposed RoW and apply a paint mark to all trees that the contractor is permitted to fell. 36

 Excavation for the pole foundations is small in scale and dispersed, so there will be no large stockpiles of soil that could create a major point-source of silt pollution;  Almost all of the excavated soil will be replaced into the cavity within a few hours of removal, so any run-off would be short-lived and very small in scale.

131. It should therefore also be unnecessary to mitigate potential impacts on aquatic ecology. iii. Impact on Economic Development

1. Positive impacts 132. The primary positive impact of the project will be access to electricity for lighting, cooking and heating for individual households as well as governmental and religious institutions. A number of secondary impacts are expected to occur as a result of the project. These include positive impacts on the health and lifestyle of local people through the use of clean technology and reduction of exposure to smoke from use of fuelwood and kerosene, and other health risks. They will also save time processing for fuelwood permits from the Forestry office or getting coupons from the Gups office for kerosene.

133. The availability of electricity should bring significant economic benefits to the rural communities, because people will have more time available for work as less time will be spent cutting and carrying firewood, so incomes will increase. People will be able to use electrically powered machinery to process their farm products or to offer services to the community (e.g. rice mills), so again incomes will increase. Others can benefit from the project if employed during the construction period as porters or for clearing of RoW.

134. Once the telecommunication network is available, farmers can use mobile phones, especially during emergencies. With television and radio farmers can update themselves on current events around the country and the world while saving money spent on purchasing radio batteries. If budget is available, the RNR offices, BHU’s, ORC can be equipped with electrical ovens, sterilizers, fridges and other improved medical equipment and therefore provide better health services. Government institutions can also network with their offices in the district headquarters or Thimphu via internet.

135. School students will benefit from the project as electrification will enable them to have computers, internet connections and access to online educational materials. Use of electrical stoves can be promoted in schools to reduce demand for firewood as well as exposure to smoke. Students and monks/nuns/old people residing and meditating in the religious institutions can also live cleaner, healthier lifestyles while devoting more time for study in the early hours of the morning and late evenings.

2. Impact on private land holdings and agriculture

136. All designated forest in Bhutan is owned by the government, so there will be no need to purchase land for the MV line where it runs through the forest. Some of the un-forested areas are also owned by the government, and will also be provided by the appropriate agency. Some land is however privately-owned (mainly fields and other agricultural land), and the Table below shows the amounts in each gewog, as identified during the route surveys.

Table 4: Length of MV line passing through private land (length in metres)

37

Feeder wetland dry land tseri tsamdro sokshing Total ARE101 0 1500 0 0 0 1500 ARE1F02 0 1100 0 0 0 1100 ARE1F03 0 1550 0 0 0 1550 Total 0 4150 0 0 0 4150

137. Where poles cannot be located on government land, these will have to be located on private land. The general practise for most development projects is to acquire private land through the legal mechanism of the Land Act (revised 2007), through which the government provides owners with an equivalent allotment of substitute land in the same dzongkhag. However, for this project, the areas required for pole foundations are so small (around 0.5 m2 each) and residents are so eager to have electricity supplied to their homes, that landowners normally allow BPC to locate poles on their land, without the need for purchase or acquisition. Therefore, land acquisition for the alignment and poles will not be necessary.

138. ADB safeguards policy (2009) requires that no-one should be worse-off as a result of an ADB-funded project, and if this is the case, the Executing Agency provides additional compensation (for loss of crops, structures and other assets) through the mechanism of a Resettlement Plan. This should however not be necessary in this case, because:

38

 Privately-owned areas are normally not forested so there is no need to acquire and clear a RoW, so the only land to be obtained is small parcels at each pole location;  Areas required are so small and dispersed (approximately every 50 m) that it is very unlikely that a significant proportion2 of the land of any one owner or tenant would be acquired;  Wherever poles are situated on farm land, these will be located at field boundaries as far as possible, to reduce the loss of productive land.

It should therefore not be necessary to provide additional measures to reduce the economic impacts of land acquisition.

139. Other features with economic implications that could be affected by construction of the MV and RV lines and transformers are infrastructure (as excavation in villages could damage water supply pipes) and agriculture (as transport of materials to site could temporarily block farm roads, making it difficult for farmers to export produce). These can both be avoided by straightforward consultation with affected local communities to determine the locations of all infrastructures and ensure that these are avoided, and to plan transportation schedules with farmers to avoid any conflict or disruption.

3. Impact on facilities.

140. Excavation works along the alignments may cause disruption to the target village in terms of disruption/damage to water pipes, impede or block access along routes with construction material, or disturbance during sensitive and religious times. To minimize this, the contractor should consult the Gup/Tsogpa and inform them of the intended project implementation process, so that they are aware when materials are being transported along the narrow routes, and facilities like drinking pipes, drainage, religious sites can be avoided. Also, the contractor should respect local tradition and culture and avoid working during religious festivals/times.

4. Aesthetic impacts.

141. Construction will also affect the landscape, because in some locations the cutting of trees and erection of poles and conductors may be visible from greater distances from across the valley. Visual impacts are generally considered significant where they affect large numbers of people, and that will not be the case here because of the remote nature of these areas.

142. This should also be an impact that does not need to be mitigated, because in many areas the trees outside the RoW will be taller than the electricity poles and because the surrounding forest itself will provide a good natural screen for the electricity poles. To ensure that the MV lines do not visually impair the beauty of the Lhakhangs and their surroundings, these should be aligned as close to the border of the forest and agricultural fields.

iv. Impact on Social and Cultural Resources

1. Impact on Cultural and Religious sites

2 ADB policy on Involuntary Resettlement considers loss of land to be significant if it amounts to 10% or more of the total land holding of any one owner. 39

143. In the project site there are a number of religious sites in different villages. The monasteries hold religious and historical texts, sacred murals, paintings and statues as well as valuable offerings made by the public. Electrification of these important structures will improve the security of these sacred facilities as miscreants will be less confident of committing robberies or vandalising them due to the increased risk of being caught. It will also benefit visitors, monks and senior citizens or caretakers residing there in terms of lighting, heating and cooking.

144. In order to minimize impacts on these sites, surveyors were instructed prior to conducting field surveys to consult closely with local representatives so that distribution lines could be aligned to avoid impacting them. During construction the contractors should also consult closely with the local caretakers so that construction activities do not impact or hinder religious activities

2. Social impacts.

145. The MV lines will be located in remote uninhabited areas, so it is very unlikely that construction will affect any locations or features that are of social or cultural importance, such as heritage sites, temples, or more modern facilities such as schools or clinics.

146. However the transformers and LV lines will be built within and near villages, so there could be impacts on inhabitants, their activities and locally important locations. As the work will involve excavation then the main impacts are likely to arise from construction noise, dust, visual intrusion, impeded access, and the presence of migrant workers. These are not expected to be major impacts, because: i) Most villages contain between 6-24 households, so the work should be short-in duration, being completed in a few weeks only; ii) Excavation will be very localized, affecting areas of 1 m2 roughly every 30-70 m, so the mounds of soil should not greatly impede access or produce significant dust; iii) In any one village work will probably be conducted by one or two small teams of 5- 10 workers each, so individual locations will not experience a large influx of foreign workers; iv) People will tolerate short-term temporary disruption if (as in this case) they are aware that they will gain significant benefits once the work is completed.

147. Efforts should still be made to reduce the level of disruption where possible, and to achieve this, the Executing Agency (DoE) should:  Consult all affected communities in advance to inform them of the purpose, nature, duration, extent and timing of all work in and around their village;  Determine the location of all sites that are of local social or cultural importance (temples, shrines, meeting places, etc) and ensure that no poles are located in the vicinity, and no conductors are strung overhead;  Consult the custodians of all social and cultural facilities that are to be electrified as part of this project (monasteries, schools, health centres) and plan the work to avoid sensitive times (such as key dates in the religious calendar, examination periods, etc).

148. The presence of migrant workers in communities can be disruptive if the workers do not follow local norms of behaviour, and if they bring other problems such as socially or sexually transmitted diseases. Such difficulties tend to be greater in rural areas where existing social and cultural bonds are stronger than in cities, and where inhabitants have less experience of people

40

149. In Bhutan RE Contractors prefer to employ local people because they are more accustomed to the difficult terrain and are more physically able than foreign labourers, who are normally imported from India. However it is generally still necessary to import some workers because the scattered rural population in Bhutan means that not enough people are available, particularly at times of intensive agricultural activity, when rural Bhutanese prefer to work in their fields.

150. These are complex issues, which need to be addressed by a range of measures. Contractors should first be required to ensure that they employ as many people as possible from communities in the vicinity of the construction sites, so that at least some economic benefits are directed to those residents who are most affected by the work.

151. If it is still necessary to employ foreign workers, then contractors should ensure;  that they are migrant workers housed in adequate, and properly cleaned camps with safe drinking water and temporary sanitation facilities away from water sources;  accommodation camps should be located in areas where no clearance of vegetation is required;  Solid waste must be collected and buried offsite  Workers must be made aware of required behavior when interacting with host communities;  Workers must be prohibited from hunting, fishing and logging;  Once construction is complete, campsites must be cleared, all temporary infrastructures demolished and all materials removed and the site restored.

152. Contractors should also protect the health of workers and the host community by controlling the spread of disease, and providing treatment where necessary. Contractors should therefore be required to:  Screen workers at their point of origin for the more virulent and contagious diseases, including HIV/AIDS, TB, Malaria, Swine flu and Bird flu or any other current disease;  Conduct regular screening of all workers for these and other infections;  Provide access to medical treatment for workers at the dzongkhag hospital if necessary;  Distribute pamphlets or posters to raise the awareness of workers and host communities of the risks of the various types of socially and sexually transmitted disease, and ways of avoiding infection;  Implement practical measures to reduce infection, for example by providing condoms free to workers.

153. Clearance of the RoW is an activity in which there is a significant element of danger, particularly to workers, but also to inhabitants of villages, should they stray into the vicinity. Contractors will be required to prepare and implement a Health and Safety Plan covering all elements of construction. This will include measures that are common to most construction sites, such as:

41

 Excluding the public from the site;  Ensuring that workers are provided with and use Personal Protective Equipment;  Health and Safety Training for all site personnel;  Documented procedures to be followed for all site activities;  Maintain accident reports and records;

154. In this case the H&S Plan should also include measures to reduce risks specific to tree felling, such as:  Ensuring that all trees and branches fall into the RoW when cut;  Liaison with all local communities to inform them of the nature, extent and timing of all clearance work and to raise awareness of the dangers.

C. Environmental effects during Operation and Maintenance i. Impact on Physical Resources

155. Maintaining the RoW by removing overhanging branches and high-growing vegetation from beneath the lines will have very little impact on the physical environment. In fact the general approach of BPC in allowing low-form vegetation to re-grow in the RoW will have benefits in reducing dust and improving soil cohesion and conservation, and helping to prevent landslides that are a risk throughout Bhutan during the monsoon rains.

156. Even though the repair of faults may involve excavation of new foundations and erection of new poles and conductors, this should also have few physical impacts as repairs generally affect short lengths of line, so the work is normally very limited in extent. Even where poles are brought down by landslides it is very rare for these to affect more than two or three poles, which can be repositioned without causing major physical changes. Similarly repairs of the LV lines in villages will be small in scale and thus unlikely to cause physical impacts.

157. Transformer maintenance can contaminate land and water if oil is spilled, so BPC staff should follow their established procedure carefully to prevent this, and should remove and dispose of any contaminated soil in a sealed drum if a spillage occurs. ii. Impact on Ecological Resources

158. Maintaining the RoW and repairing faults along the line will have no major ecological impacts as the work is very small in scale and infrequent, and involves few changes to the existing situation. The practice of allowing some re-growth of vegetation along the RoW will also have ecological benefits as it will allow plants and animals to re-colonize the area. Because the forest canopy is now open in these areas the species will be different from those that were originally present, which could be seen as a further gain as this will increase the diversity of Habitats.

159. The major ecological benefit will occur over the longer term, as the availability of electricity in these villages reduces the felling of trees for firewood. Current estimates are that each rural household in Bhutan consumes around 3.5 kg of firewood per person per day3, so these ecological gains should become highly significant over time and will greatly exceed the short-term losses from the original clearance of the RoW.

3 FAO (2001): National Strategy for Stoves and Other Alternative Energies, Project No BHU/99/005 42 iii. Impact on Economic Development

160. The routine maintenance of the RoW will not have economic impacts as it will not affect agricultural areas, or farm roads used for transporting produce. If a line failure requires the repositioning of poles, it should not be necessary to purchase land for the new foundations, as owners are very likely to donate the very small amounts of land required (1 m2 per pole) in order to restore the electricity supply. New foundations will be dug close to the old ones, so wherever possible land from the same owner should be used, so that the previously used area can be returned.

161. Power outages will have negative economic impacts as people will be unable to use machinery they have installed to diversify their means of livelihood, for the period in which the system is shut down. BPC should therefore keep such periods to a minimum, by responding to line problems rapidly; and repairing faults rapidly and effectively.

162. The Performance-Based Incentive schemes within BPC, whereby annual salary increments and bonus payments are linked to the performance of the electricity supply system, should improve the efficiency of the service. iv. Impact on Social and Cultural Resources

163. The main hazard to people from the operation and maintenance of the completed RE system is the risk of electrocution. This is a danger to i) Rural consumers who are not highly educated and are generally unaware of the dangers posed by electricity; and ii) BPC workers when repairing lines or components.

164. BPC have procedures set down in Operation and Maintenance (O&M) manuals, which describe how all work on distribution lines is to be conducted. They also have Health and Safety (H&S) Manuals, which describe the personal protective equipment that is to be provided (including safety helmets and belts for climbing poles), plus emergency procedures, etc. However there have been a small number of recent fatalities, which suggest that the systems are not functioning adequately. Some measures for BPC to undertake include:  Ensure that staff understand and comply with the BPC O&M and H&S manuals and procedures;  Continue providing regular training for all BPC operatives to raise awareness of the dangers of the work being conducted, the equipment that is to be used, and the procedures that must be followed;  Conduct regular supervision of field workers during both RoW clearing and repair of faults;  Conduct regular management reviews of safety records, and follow-up with remedial action where necessary; and  Continue to conduct community education programmes to raise the awareness of all target households before and after they are connected to the grid regarding the dangers of electricity, and the correct manner in which house systems should be used.

165. If these actions are implemented thoroughly, then the RE system should function without major accidents or fatalities from misuse or inappropriate operation. There should then be a wide variety of social benefits for the target households and their wider communities from the provision of electricity already discussed previously. Together these should greatly improve the

43

166. Once electricity is provided, people rapidly become used to and even become dependent upon the service and the new way of life it supports, and are not greatly tolerant of interruptions in the service. This reinforces the need for BPC to take the actions recommended above in order to minimise power outages by ensuring that the maintenance procedures (RoW clearing, routine checks of lines and transformers) are conducted regularly and diligently; and respond to faults rapidly and ensure that repairs are conducted quickly and effectively.

167. Any disturbance or disruption that residents may experience from the re-erection of poles or replacement of conductors in the villages will be viewed as very minor when compared to the inconvenience of being without electricity, so there should be no need for mitigation.

44

VI. ANALYSIS OF ALTERNATIVES

168. A number of alternatives were considered for the project. These included a) the no-build alternative, and b) use of solar energy (Photovoltaic panels) and c) on-grid electrification. Each alternative is discussed below.

a. Alternative 1. 169. Maintaining the status quo of not undertaking the project (i.e. the no-build alternative), there will be no ecological impact on the environment or biodiversity from this project. However, the total number of households electrified will remain less than 50%, and the government will fail to achieve its target of electricity for all by 2013.

b. Alternative 2. 170. Using solar energy (photovoltaic panels) is a better alternative than the ‘No project” one, in terms of development in the rural areas. There are a number of constraints with this alternative; for instance a) it can only be used for lighting purposes, so firewood consumption for heating and cooking will still remain high, b) high maintenance cost for repair of parts and c) need for technical knowledge and low durability.

c. Alternative 3. 171. Provide on-grid electrification. This is the alternative that is proposed by this project. Through this all target villages will be provided with electricity from the existing grid system. The project is expected to significantly reduce demand for firewood, as this is the primary source of heating and lighting in the remote communities. This alternative will contribute positively to improving the lives of the target communities through reduced exposure to smoke, improvement in living conditions, increased communication via use of mobiles and opportunities for seeking alternative livelihood options. Local government institutions like BHU, ORC, Schools, RNR centres and Religious institutions will also benefit through reduced time and money spent on sourcing firewood from local communities, as well as increase in accessibility to information through various media sources, internet and improved communication. Students will have extra time to study during early mornings and evenings.

Table 5: Comparison of alternatives Parameters No electricity Use of solar energy On grid Rural Electrification Economic cost Cost to farmers include cost - maintenance cost depends on -High cost to government of kerosene, location of households and -Cost of in house electrification access to repair facilities -Lack of technology for repair Developmental Village/gewog considered -Community is still considered -Community is considered impacts & underdeveloped ‘underdeveloped’ ‘developed’ people’s -Use limited to lighting purpose -Can explore other livelihood perception alone alternatives such as rice mills, Social benefit Household still exposed to -Clean and renewable energy Beneficiaries include smoke, dirt, and increasing -Benefit restricted to lighting only -Households distance/time spent in fuel -Schools wood collection -Government & Religious facilities Environmental Yearly increase in fuel wood -Yearly increase in fuel wood Main impacts are impacts consumption consumption per family -Impact from Right of Way of -Improper disposal of battery Distribution line may cause heavy metal pollution -Localized impact on endangered especially in rural areas wildlife -Aesthetic impacts -Aesthetic impacts

45

172. The third alternative ‘providing on-grid electrification for the proposed villages ‘ is the most feasible in light of the easy availability of hydropower in the country, the positive environmental benefits, and most importantly because this is what the local communities prefer. The first alternative is not feasible because electricity is included as a measure of development in a village and therefore is always given high priority in the list of developmental activities for any gewog plan. It is impossible for the government to overlook this demand especially since the country is a major generator of Hydropower energy. While there will be no environmental cost from this alternative, with increasing population it is expected that the demand for fuelwood will increase each year, putting very heavy pressure on the already dwindling forest resource.

173. The Solar PV system involves the utilization of renewable and clean energy, but it is considered a temporary measure for those villages where the cost of providing electricity is too high for the moment. The utility of the solar system depends on the location of the target villages. For instance, if villages are located close to access roads, then repair and maintenance is easy compared to remotely located villages where there are no such facilities available.

174. Based on the above comparisons the first two alternatives are no longer under consideration. However, there are still some villages that are too remote and it is too expensive or technically very difficult to provide on-grid electrification. In such cases, these villages will be provided off-grid electrification.

46

VII. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION

A. Project stakeholders

175. Most of the main stakeholders have already been identified and consulted during preparatory phase of this project. Primary stakeholders are  Residents of 78 households that will be electrified by this subproject;  Residents and users of 4 temples that will be electrified by this subproject;  People who work on agricultural land that will be crossed by the MV lines;  Owners or users of land that is acquired for the erection of poles for MV or LV lines; but who are not beneficiaries

176. Secondary stakeholders are:  DoE as the Executing Agency;  BPC as the Implementing Agency.  Department of Forest as the custodian of the government reserve forest  NEC as the agency granting Environmental Clearance; and  Dzongkhag Administration under whose jurisdiction the sub-project is being implemented; and  ADB

B. Consultation and disclosure to date

177. In order to involve various stakeholders during the preparation of the EIA, consultations were held with the Project Management Office at Thimphu and the Rural Electrification Staff at the Field office.

178. With the permission of the Dzongkhag, a public consultation was held at Khashitheng on the 13th of June, 2009. Being the cropping season, most households were busy with varied tasks and thus the meeting was held in the evening. The meeting was attended by residents of Khashitheng (9 participants) and Phaju Goenpa (22 participants). Appendix 2 contains a summary of the meeting.

Table 6: Details of public consultation conducted

Date Location Total participants 13th June, Khashitheng 31 2009

47

Table 7: Summary of public consultation Issue Participant’s opinion, comments and suggestions General perception about Participants were very happy that the project is finally being implemented. Residents have attended the project previously meetings to discuss the project which did not materialize. Now residents were confident that the project was really going to be implemented The participants said that they were happy that such isolated and remote villages like theirs were being considered for electrification and expressed their gratitude to the government as well as the donors for this initiative. Alignment of the Residents were informed that BPC was currently exploring two options for the route alignment, from distribution line Trephu to Khashitheng and the second one from Diafam. Residents said that although there will be more environmental impacts on the forest, they prefer the first route because the second route has more landslide prone areas, unstable hill slopes, lacks permanent bridges and hence there will be more risk of erratic supply. Project benefits Currently water mills are used for grinding maize but with the project owners will use electricity. Other benefits that the participants articulated included conservation of forest, improved protection of crops and livestock; cleaner smokeless and healthy surroundings and opportunities to improve their livelihood. Alternative energy Residents of Khashitheng were given solar systems twice, but many were not using them because the panels were too old and bulbs keep getting damaged. The closest market is located 2 days walk from the village and there are no facilities to repair defective systems in the village. Approximately 2 truckloads of fuel wood per year are used by each household and 20 liters of kerosene which has to be transported from the nearest town. Disadvantages of the The only negative impact of electricity is that it will be risky and dangerous as residents do not know electricity and its project- how to operate these or when there is a short circuit.

Public consensus They said they had no issues or concerns about the project and all of them have already signed the public consensus forms giving their consent to the project. Project implementation BPC staff had already conducted a meeting to discuss the project when they conducted the route and work options survey. During that meeting the community had requested BPC to include them in the electrification program and participants said that they were very happy to know about the positive development towards the fulfillment of their request. They hoped that the funds will be received soon and the project can be initiated as soon as possible. Any other issue Participants said that much of the topics discussed were similar to the previous meeting with BPC staff, so they did not have any queries and felt that the project will benefit all of them even though some may be affected at the individual level. Since it was for the greater good of the community, they are willing to make few sacrifices

179. This IEE will be disclosed to the public by making it available at RED offices in Trashigang and the project as a whole will be disclosed to a wider audience via the ADB website.

C. Future consultation and disclosure

180. DoE/BPC will extend and expand the consultation and disclosure process significantly during implementation of the project. They will conduct a wide range of activities in relation to all subprojects in each dzongkhag, to ensure that the needs and concerns of stakeholders are registered, and are addressed in project design, construction or operation where appropriate. The program of activities will be developed during the detailed design stage, and is likely to include the following:

48

181. Consultation during pre-construction stage:  Focus-group discussions with affected persons and other stakeholders (including women’s groups and NGOs) to hear their views and concerns, so that these can be addressed in subproject design where necessary;  Structured consultation meetings with the institutional stakeholders (government bodies such as Department of Roads, NEC, Department of Forest) to discuss and approve key aspects of the project;

182. Consultation during construction:  Public meetings with affected communities to discuss and plan work programmes and allow issues to be raised and addressed once construction has started;  Smaller-scale meetings to discuss and plan construction work in individual villages to reduce disturbance and other impacts, and provide a mechanism through which stakeholders can participate in subproject monitoring and evaluation;

183. Project disclosure:  Public disclosure meetings at key project stages to inform the public of progress and future plans.  Formal disclosure of completed project reports by making copies available at the RED field office and the BPC head office.

49

VIII.GRIEVANCE REDRESS MECHANISM

184. The target gewog that will be affected by the project has a total of 78 households and 4 temples.

185. The process of including these villages in the Project is pretty straightforward. Keeping Rural Electrification Masterplan 2005 as the reference, the un-electrified villages were included in the project scope based on the Dzongkhag’s priorities. The list of the targeted households was then provided to BPC for implementation. This preliminary list of non-electrified villages was further segregated into two, those that could easily be connected to the grid and those that were too far in terms of distance, or due to technical and economic reasons.

186. Using the list of villages selected on grid electrification, BPC fielded surveyors to conduct field studies to finalize which distribution lines could actually be included in the target areas. Criteria used for this include a) distance of the village to the nearest feeder, b) number of houses to be electrified, c) accessibility and means of transportation d) location of the villages (environmental sensitivity), e) topography, and f) material cost, transportation and head loading costs. Based on the field data, the list of distribution lines, number of beneficiaries, along with the technical route survey to ascertain length of MV and LV lines, number of substations, transformers etc. was finalized.

187. MV lines cross mainly forested areas but these routes have been selected to run along existing access routes, tracks and pathways where possible, because in these areas there has already been some clearance of trees and other vegetation, so this reduces the amount of new felling required. The Table shows the amounts along each distribution line, as identified during the route surveys.

Table 8: Length of distribution lines and affected persons/beneficiaries

LV MV length length Total Feeder Name (m) (m) Villages HHs LhakhangConsumer ARE1O1 21845.2 2861.9 1 9 2 11 ARE1O2 3304.87 9412.4 2 39 2 41 ARE1O3 4299.75 5472.2 2 30 0 30 Total 29449.83 17746.5 5 78 4 82

Table 9: Total length of feeder through government and private land (length in metres) Feeder Government land Private land Total length ARE101 20,350 1500 21,850 ARE1F02 2200 1100 3,300 ARE1F03 2750 1550 4,300 Total 25300 4150 29,450

188. The total length of all the distribution lines is 29.45km of which only 4km passes through privately-owned (mainly fields and other agricultural land) land in 5 villages, which amounts to 14% of the total line length. These areas that are traversed are so small and dispersed

50

4 of the land of any one owner or tenant would be acquired;

189. Along the distribution line it is estimated that 589 poles will be constructed, of which there will be 509 poles on government land and 80 poles on private land. Where the lines cut across private land, poles will be located on field boundaries where possible, to reduce the loss of productive land. The areas required for pole foundations are so small (around 0.5 m2 each) and residents are so eager to have electricity supplied to their homes, that landowners normally allow BPC to locate poles on their land, without the need for purchase or acquisition.

190. A key element of the national Environmental Clearance application process is the provision of signed No Objection Certificates (NOC) from stakeholders that are specified in the guidelines, including all affected households, Public consultation and participation was sought beginning from project planning and route identification phase wherein the local village representatives were called upon by the District authorities to conduct awareness on the prospective project and to seek the consensus from potential affected persons.

191. In the past, any grievance against RE projects have been approached personally to BPC office or forwarded through the Gup to the Dzongkhag and BPC office and resolved informally through mutual agreement wherever possible. In other cases, where the APs are not satisfied the case has been forwarded to the court for a resolution. There have been instances in the past when the APs put their grievances after the lines are constructed and commissioned. In such cases, it was very difficult for BPC to realign the distribution lines because shifting a pole required realigning 4 to 5 poles both up-stream and down-stream. Due to the high cost of the adhoc and unbudgeted realignment, the BPC has asked APS to do it at their own cost. To avoid such complications in the future, BPC now conducts awareness program during the preconstruction period.

192. ADB safeguards policy (2009) requires that no-one should be worse-off as a result of an ADB-funded project, and if this is the case, the Executing Agency provides additional compensation (for loss of crops, structures and other assets) through the mechanism of a Resettlement Plan. This should however not be necessary in this case, because privately- owned areas are normally not forested so there is no need to acquire and clear a RoW, so the only land to be obtained is small parcels at each pole location. BPC field staff has been clearly instructed to ensure that where poles are situated on farm land, these are located as field boundaries as far as possible, to reduce the loss of productive land. Besides, the distribution substations are pole-mounted for all RE works minimizing private land usage.

193. A memorandum of Agreement cum Application for Rural Electrification was prepared between the BPC and the beneficiaries through the local government (village headman/Gup) and forwarded to the BPC after being endorsed by the Dzongkhag administration. This agreement states that the applicants are aware of the ARE project and would like to be included for the electricity service connection as potential consumers. The applicants agree to provide the Right of Way for the construction, operation and maintenance of electricity lines passing through their private land, free of cost to the BPC as they are the primary beneficiaries. The BPC should avoid traversing existing khimsa (where the house exists) at all costs and try to avoid the use of cultivated land as much as possible.

4 ADB policy on Involuntary Resettlement considers loss of land to be significant if it amounts to 10% or more of the total land holding of any one owner. 51

194. Because the impact on the private land of any individual household is so small with no impact on infrastructure, RE schemes are not expected to have major negative socio-economic impacts as there will be no need for land acquisition or resettlement. Wherever possible, the project will avoid or minimize traversing private land by identifying possible alternative routes. For the loss of Crops and Fruit trees if any, the BPC will compensate the APs at the prevailing government approved rate, which shall be built into the project cost. A copy of the Memorandum of Agreement is in the Annex.

Complaints and Grievance Redress mechanism

195. During the process of project implementation, stakeholders may file complaints if they are not happy with the alignment of the distribution line, pole, substation or service center locations. Any person who believes that his/her land or structure has been expropriated or altered and believes that their private land, house, or agricultural crops are being unfairly affected by the project will be able to express their grievances through a grievance redressal mechanism that will be instituted under this project. Through this mechanism the Affected Person may submit their grievance to the Dzongkhag office, which will record the grievance and ensure that all complaints and resolutions are properly documented and also available for review for monitoring purposes. The Dzongkhag office will conduct the necessary field visit to verify and assess the grievance/complaint, determine the validity of the grievance, and resolve the grievance within 1 month of receipt of the complaint.

Grievance Redress Procedure

196. The grievance redress procedure will be as follows; 1. Each grievance must be dealt with within a two weeks of receipt of complaint from the AP. 2. The necessary field verification/assessment will be conducted and the AP informed of a decision in writing within 4 weeks/28 days 3. Issues may be resolved amicably through third party arbitration and negotiation but If APs are not satisfied they can take recourse to the civil court if he/she so desires, or resolve the issue by taking it to next level of Grievance Redress, which is the National Land Commission (NLC), the highest body to approve land replacement and compensation allotments in the country.

197. During Project implementation, the BPC will ensure that APs are briefed on the grievance redress mechanism and procedures.

198. In the unlikely case of unforeseen environmental impacts, any grievances regarding environmental impacts will be submitted to the Dzongkhag Environmental Officer and BPC, who will conduct a field assessment of the situation and recommend appropriate mitigation measures to be implemented by the BPC. Where the Environmental Officer unable to take a decision, the case will be referred to the National Environment Commission for advice on necessary corrective measures. Such grievances will also be documented for monitoring purposes. All environmental issues must be resolved within 21 days of receiving the complaint.

52

IX.ENVIRONMENTAL MANAGEMENT PLAN

A. Summary of environmental impacts and mitigation measures

199. All the potential adverse impacts of the project have been identified and discussed in the previous chapters. All the potential adverse impacts of the project have been identified and discussed in the previous chapters. The EMP table outlines potential environmental impacts and mitigation measures proposed to reduce these impacts to acceptable levels. It also identifies the agency responsible for a) planning and implementation as well as b) supervision and monitoring, for each phase of the project.

200. Taking off from the first table, the second table then describes: (i) mitigation measures, (ii)parameters to be monitored, (iii) location, (iv) measurement method, (v) frequency of monitoring, (vi) responsibility (for both mitigation and monitoring), and (vii) cost of monitoring. Most of the mitigation measures are fairly standard methods of reducing the impacts of RE schemes (preventing damage outside the RoW, providing suitable living conditions for imported workers, etc), and experienced domestic contractors should be familiar with most of the requirements.

B. Environmental Monitoring Plan

201. During the construction stage all mitigation activities are the responsibility of the Construction Contractors employed to build the infrastructure. Responsibility will be assigned via the contracts through which they are appointed (prepared by RED during the detailed design stage), so they will be legally required to undertake the necessary actions. Mitigation when the system is operating is the responsibility of the Electricity Services Divisions (ESD) as the agency responsible for maintaining the system in working order.

202. A senior Environmental Officer (EO) will be responsible for implementing the Environmental Monitoring Plan in the construction stage, and reporting the results to RED, with recommendations for remedial action if measures are not being provided or are not protecting the environment effectively. The senior EO will be assisted by more junior EOs who can make many of the routine observations on site. Post-construction/Operation monitoring will be conducted by BPC.

203. Monitoring of such measures normally involves making observations in the course of site visits, although some require more formal checking of records and other aspects. There will also be some surveys of residents and workers, to review those measures that are aimed at ensuring their safety and wellbeing. Based on the EMP, the environmental officer, BPC will prepare the necessary monitoring checklist and surveys for themselves and ESD staff to follow during their site visits during the construction and operation and maintenance phase. Monitoring may be conducted every two weeks during the construction phase and if field inspections and monitoring reveal good environmental performance, the frequency may be reduced. Conversely, if the opposite occurs, then the matter will be reported to the Environmental Officer who will in turn direct the Contractor to take necessary mitigative measures, and monitoring frequency will be stepped up.

53

Table 10: Environmental Impacts and Mitigation Project Activity Potential Environmental issues Management/Mitigation Measures Responsibility Planning and Supervision and Monitoring Implementation Pre-construction stage Design and Impact due to location of target 1.Route selection in close consultation with Department of Forest, RED, BPC Requires ‘No Objection’ Clearance location of three villages in the biological corridor BPC field staff to avoid sensitive areas; DoE from 33kV Distribution between Sakteng Wildlife 2. Route selection approved by National environment Commission i..Park Management/Department lines Sanctuary and Khaling Wildlife and District Authorities of Forest Sanctuary 3. Align routes alongside farm roads and footpaths where possible, ii.District Environmental Officer alongside forest edges where habitats are already degraded to an iii.National Environment extent, and will involve minimum tree felling to minimize design Commission effect. iv.District Administrative Approval v.Public Consensus from local residents

Construction Clearing of RoW Removal of forest cover in 1.Ensure that only those trees marked by the forestry staff are Contractor, BWS, Environmental Officer, BPC along Distribution biological corridor felled BPC District Env. Officer line 2.Follow standard BPC procedures and practices in clearing ROW NEC 3. Explore possibility of planting low growing vegetation in RoW 4. Reforestation or afforestation to make up for forest cover loss Workers could damage species & 1.Mark RoW boundary & prohibit cutting outside; Contractor Environmental Officer, BPC Habitats outside RoW 2.Only fell trees that have been marked by Forestry staff; 3.Prohibit hunting or fishing by workers and enforce strictly; 4.Train workers in importance of wildlife and habitats; 5.Locate labor camps where no forest clearance is needed; Impact on private land holdings 1.Route the distribution lines along edge of villages Contractor Environmental Officer, BPC 2.Where routes cross private land, avoid alignments too close to houses or cutting through the center of fields Risk of forest fires if cut 1.Leave cut material to rot down in situ and do not burn; Contractor Environmental Officer, BPC vegetation is burnt 2.Leave a covering of grass & other low vegetation in RoW; 3.Dispose of trees as required by Department of Forestry Delivery of RE Air pollution from vehicular Minimize number of deliveries through timely scheduling Contractor Environmental Officer, BPC materials to drop movement off points Carriage of materials to site could Consult Gup and farmers when transporting material Contractor Environmental Officer block access Excavation at Dust may blow from cleared Avoid using large machinery, Manual excavation at pole sites and pole sites areas minimize disturbance at excavated sites,

54

Effect on local drainage and soil Locate poles at a minimum distance of 30 m from rivers, and Contractor Environmental Officer erosion construct these on stable ground Excavation for poles could Consult community to identify and avoid infrastructure Contractor Environmental Officer damage water pipes in villages Work in villages may create 1.Inform communities of work in advance; Contractor Environmental Officer, BPC noise, dust & impede access 2.Identify sites of local significance; locate no poles nearby; 3.Consult custodians of facilities (monasteries, nunneries, schools, clinics, etc) and avoid working at sensitive and religious times; Social and Economic benefits if local people Employ as many local residents as possible in workforce Contractor Environmental Officer, BPC cultural impacts are employed Importing foreign workers can 1.Ensure imported workers are provided with housing that has Contractor Environmental Officer cause environmental and social ample toilets, proper drainage and treatment for sewage. problems at labour camps and in 2.Collect solid waste weekly and bury offsite. host community 3. Instruct workers on required behavior in host community and prohibit them from hunting and fishing. 4.Camps must be cleaned up and restored after project is completed. Diseases can be introduced into 1.Initial screening of workers for HIV/AIDS, TB, malaria, swine flu, Contractor Environmental Officer host communities from social and etc.; sexual contact with imported 2.Facilitate access to the nearest Health facility for check up; workers 3.Raise worker/community awareness of risks of socially & sexually transmitted disease; 4.Practical measures, e.g. free condoms for workers; Workers and villagers are at risk Prepare and implement a site Health and Safety Plan that includes Contractor Environmental Officer from accidents on site measures to: -Exclude the public from all construction sites; -Ensure that workers use Personal Protective Equipment; - Provide Health & Safety Training for all personnel; - Follow documented procedures for all site activities; - Keep accident reports and records; - Inform local communities about the work and dangers Impact on private land and Conduct awareness programs/meetings BPC Environmental Officer infrastructure Grievance Redress mechanism in place

55

Project Activity Potential Environmental issues Management/Mitigation Measures Responsibility Operation and Maintenance Provision, People cannot use new electrical Field personnel should report power outages to the ESD and repair faults ESD BPC Operation and machines during power cuts so quickly and effectively maintenance of income may suffer new RE system Consumers are at risk of 1.Train and supervise BPC field operatives to ensure that they check RED, BPC BPC electrocution if they do not house wiring carefully and reject if deficient; understand the dangers of 2.Public education to raise villagers’ awareness of dangers of electricity electricity and how to utilize the system safely. BPC workers are at risk if they do 1.Follow BPC O&M and H&S manuals and revise these manuals if RED and BPC not follow BPC procedures when necessary to increase safety of workers; ESD, BPC clearing RoW or repairing faults 2.Regular training of BPC workers to raise awareness of dangers and working procedures to be followed; 3.Improve supervision of field workers; 4.Regular management reviews of safety record, with remedial action where necessary. People will not be very tolerant of 1.As above: repair faults quickly and effectively; RED and BPC power cuts once they become 2.Conduct system maintenance regularly and diligently ESD, BPC used to the benefits of electricity

56

Table 11: Environmental Management Plan

Potential impacts Mitigation measure Parameters to Location Method Monitoring Responsibi Cost be monitored Frequency lity Pre-construction Impact due to location of 1.Route selection in close consultation with Department of Forest, EC clearance MV lines Route selection n/a RED, n/a target villages biological BPC field staff to avoid sensitive areas; process and BPC corridor 2. Route selection approved by National Environment Commission EC Clearance MV lines Field n/a NEC n/a and District Authorities process investigation by Environmental officer 3. Route should be selected so that clearance along forested areas EC clearance MV lines Mapping of field n/a RED, n/a are avoided wherever possible; Where there is no alternative to process information BPC routing lines through forest, align routes alongside farm roads and footpaths where possible, alongside forest edges where habitats are already degraded to an extent, and will involve minimum tree felling. Construction Removal of forest cover in 1.Ensure that only those trees marked by the forestry staff are felled No.of MV lines Site Two weeks EO, BPC Include biological corridor 2.Follow standard BPC procedures and practices in clearing ROW violations Observations d in CB Explore possibility of planting low growing vegetation in RoW Revegetation MV lines Site Two weeks EO, BPC n/a of RoW Observations Workers could damage 1.Mark RoW boundary & prohibit cutting outside; No. of MV lines Site Two weeks EO, BPC n/a species & Habitats 2.Only fell trees that have been marked by Forestry staff; violations Observations outside RoW 3.Prohibit hunting or fishing by workers and enforce strictly Number of Camp sites Site Observation Monthly EO, BPC n/a illegal reports Surveys 4.Train workers in importance of wildlife and habitats; Number of Labour Contractor Monthly EO, BPC Include illegal reports camps records d in CB

5.Locate labour camps where no forest clearance is needed; Location of Labour Site Monthly EO, BPC Include camps camps observations d in CB 6.Provide adequate food supply so workers do not need to hunt or Illegal Labour Site Monthly EO, BPC Include fish activities camps observations d in CB Impact on private land Route feeders along edge of villages, avoid locating poles in the Feeder MV lines Site Monthly EO,BPC n/a holdings centres of fields alignment observations

57

Risk of forest fires if cut Leave cut material to rot down in situ and do not burn; No. Of fires MV lines Site Two weeks EO, BPC n/a vegetation is burnt Leave a covering of grass & other low vegetation in RoW; observations Dispose of trees as required by Department of Forest Disposal of MV lines Site Two weeks EO, BPC Include trees observations d in CB Delivery of RE materials Minimize number of deliveries through timely scheduling No. Of Drop off Site Monthly EO, BPC n/a to drop off points- Air deliveries points observations pollution from vehicular movement Carriage of materials to Consult Gup and farmers when transporting material No. Of MV and LV Site Monthly EO, BPC n/a site could block access consultations lines observations; Village survey Excavation at pole sites- Avoid using large machinery, Manual excavation at pole sites and Site MV lines Site Monthly EO, BPC n/a Dust may blow from minimize disturbance at excavated sites, observations observations cleared areas Effect on local drainage Locate poles at a minimum distance of 30 m from rivers, and MV lines Site Monthly EO, BPC n/a and soil erosion construct these on stable ground observations Excavation for poles could Consult community to identify and avoid infrastructure No. Of MV and LV Site Monthly EO, BPC n/a damage water pipes in consultations lines observations; villages Village survey Work in villages may 1.Inform communities of work in advance; MV and LV Site Monthly EO, BPC n/a create noise, dust & lines observations; impede access Village survey 2.Identify sites of local significance; locate no poles nearby; MV and LV Site Monthly EO, BPC n/a lines observations; Village survey 3.Consult custodians of facilities (monasteries, nunneries, schools, MV and LV Site Monthly EO, BPC n/a clinics, etc) and avoid working at sensitive and religious times; lines observations; village survey Economic benefits if local Employ as many local residents as possible in workforce No. of locals All sites Site Monthly EO, BPC n/a people are employed in employed observations; Contractor’s workforce worker survey Importing foreign workers 1. Ensure imported workers are provided with housing that has ample No. of All sites Site Monthly EO, BPC Include can cause environmental toilets, proper drainage and treatment for sewage. Observations observations; d in CB and social problems at from camp site worker survey labor camps and in host 2. Collect solid waste weekly and bury offsite. All sites Site Monthly EO, BPC community

58

observations 3. Instruct workers on required behavior in host community and All sites Site Monthly EO, BPC prohibit them from hunting and fishing. observations; worker survey 4. Camps must be cleaned up and restored after project is Labour Site Monthly EO, BPC completed. camps observations; worker survey Diseases can be 1.Initial screening of workers for HIV/AIDS, TB, malaria, swine flu, Contractors Labour Site Monthly EO, BPC Include introduced into host etc.; record on camps observations; d in CB communities from social Health issues worker survey and sexual contact with 2.Facilitate access to the nearest Health facility for check up; Labour Site Monthly EO, BPC imported workers camps observations; worker survey 3.Raise worker/community awareness of risks of socially & sexually Labour Site Monthly EO, BPC transmitted disease; camps observations; worker survey 4.Practical measures, e.g. free condoms for workers; Labour Site Monthly EO, BPC camps observations; worker survey Workers and villagers are Implement Health and Safety Plan that includes measures to: Health and Labour Site Monthly EO, BPC at risk from accidents on -Exclude the public from all construction sites; safety camps observations site -Ensure that workers use Personal Protective Equipment; mgt.plan - Provide Health & Safety Training for all personnel; - Follow documented procedures for all site activities; - Keep accident reports and records; - Inform local communities about the work and dangers Operation and Maintenance Provision, Operation and Field personnel should report power outages to the ESD and repair # reports and MV and LV Reports Monthly EO, BPC n/a maintenance of new RE faults quickly and effectively repairs lines observations system 1.Train and supervise BPC field operatives to ensure that they check Training and All sites Reports Monthly EO, BPC n/a house wiring carefully and reject if deficient; awareness Observations 2. Public education to raise villagers’ awareness of dangers of Reports electricity and how to utilize the system safely. 1.Follow BPC O&M and H&S manuals and revise these manuals if # trainings and All sites Reports Monthly EO, BPC n/a necessary to increase safety of workers; supervision Observations 2.Regular training of BPC workers to raise awareness of dangers and reports

59

working procedures to be followed; 3.Improve supervision of field workers; 4. Regular management reviews of safety record, with remedial action where necessary. 1.As above: repair faults quickly and effectively; # Repair and All sites Reports Monthly EO, BPC n/a 2.Conduct system maintenance regularly and diligently maintenance Observations reports ESD: Electricity Supply Division, Trashigang, RED: Rural Electrification Division, BPC, EO- Environmental officer

60

C. Institutional Arrangement

204. The subproject will be managed and implemented within the institutional framework that already exists in Bhutan for the provision of rural electrification services. The main agencies and their roles will be as follows:

 DoE is the Executing Agency (EA) responsible for management, coordination and execution of all activities funded under the loan.

 BPC is the Implementing Agency (IA), responsible for the successful construction and subsequent operation of all the RE subprojects. BPC is the Implementing Agency (IA), responsible for the successful construction and subsequent operation of all the RE subprojects. Implementation will be managed by the Rural Electrification Department (RED), headed by a General Manager in the Head Office and other Senior Managers in the Divisions.

 RED will coordinate construction of subprojects across all Dzongkhags, and ensure consistency of approach and performance. They will appoint Construction Contractors (CC) to build elements of the infrastructure in a particular Dzongkhag.

 Local implementation will be managed by the field offices of the RED in each of the target Dzongkhags, who will supervise the Construction Contractors, and will be responsible for quality control, contract supervision, monitoring and reporting, etc.

 Environmental issues will be coordinated by the BPC Environmental Unit, who will ensure that all subprojects comply with national environmental safeguards. The Environmental Monitoring Plan (EMP) involves observations and surveys to be conducted during construction and operation to ensure that mitigation measures are provided and that they protect the environment as intended. Construction monitoring will be conducted by RED field offices, and monitoring during operation will be co-ordinated by Distribution and Customer Services Department (DCSD), BPC.

D. Environmental Management and Monitoring Costs

205. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. Costs of mitigation by the contractors are included in the budgets for the civil works and do not need to be estimated separately here.

206. Mitigation that is the responsibility of BPC should be included as part of their management of the project. Environmental monitoring during construction must be conducted by BPC Environmental Officers, and budget is required for their travel. Customer satisfaction must be gauged and for this survey expenses may be incurred. There may also be unforeseen mitigation measures that may arise. The costs of these are shown in the following Table. The figures show that the total cost of environmental management and monitoring for the subproject as a whole (covering design, construction and operation) is Nu.2,44,800.00

61

Table 12: Cost of implementing EMP and monitoring (Nu.)

Activity Quantity Unit Cost Total Cost Source of (Nu.) Fund A Design phase Use of Covered conductors and reflectors To be ascertained To be To be Project ascertained ascertained B Construction phase Monitoring by Environmental Officer from BPC once every 1person x 2 weeks * 4 14000 56000 Project 1 quarter times Monitoring by project field staff every month 1personx1week * 12 4900 58,800 Project 2 times 3 Conducting awareness among public in each gewog 2 gewogs 15,000 30,000 Project 4 Capacity building and training for stakeholders & staff 1,00,000 1,00,000 Project 5 Compensation costs (social) 0 0 Project 6 Afforestation/Reforestation by E & GIS Div. 1,00,000 1,00,000 B Operation phase Unforeseen environmental impacts will be covered from project contingency cost Total 244,800.00 Assumptions:

-Construction works will be completed within one year of commencement -DSA rates for government officers/staff is as per prevailing rate -Environmental Division has adequate staff to cover all project sites

62

X.CONCLUSION AND RECOMMENDATION

A. Project Findings

207. The process described in this document has assessed the environmental impacts of all elements of the infrastructure proposed under the Rural Electrification Subproject. The findings of the assessment are as follows;

208. The primary positive impact of the project will be access to electricity for lighting, cooking and heating for individual households and religious institutions. At the same time the availability of an electricity supply should bring significant economic benefits to the rural communities, because:  There can be significant improvements in the health and lifestyle of local people through the use of clean technology and reduction of exposure to smoke from use of fuel wood and kerosene, and other health risks.  People will have more time available for work as they will not have to spend time for fuel wood permit, cutting and carrying firewood  People no longer have to purchase kerosene from the nearest town which is 2 days walk from the villages;  People will be able to use electrically powered machinery to process their farm products or to offer services to the community(e.g. rice mills), so again incomes should increase;  People will also be able to work and provide services during the evening because of the greater availability of lighting,  Individuals may be employed by the project during the construction period as porters or for clearing of RoW.

209. The major ecological benefit will occur over the longer term, as the availability of electricity in these villages reduces the felling of trees for firewood. Current estimates are that each rural household in Bhutan consumes around 3.5 kg of firewood per person per day5, so these ecological gains should become highly significant over time.

210. Potential negative impacts were identified in relation to design, construction and operation of the improved infrastructure. The impact on the biological corridor as stated previously is unavoidable as environmental impacts would not occur if the target villages were not selected and MV lines could have been routed through un-forested areas to these villages

211. The assessment did not consider that there would be any significant impacts due to the project design or location or construction and operation. Mitigation measures have been developed to reduce all negative impacts to acceptable levels. These were discussed with specialists responsible for the engineering aspects, and as a result some measures have already been included in the outline designs for the infrastructure. These include:  Routing MV lines along existing access routes and footpaths where possible, where the forest has already been partially cleared, thus reducing the felling of new trees as well as reducing the need to acquire private land;  Selection of MV line routes in close consultation with the Department of Forest and approved by the National Environment Commission after conducting field verification of alignments.

5 FAO (2001): National Strategy for Stoves and Other Alternative Energies, Project No BHU/99/005 63

 Public consultation to seek consensus of the affected households to construct poles on their land and to raise awareness of the project activities

212. Thus the planning process has already identified potential impacts and reduced their significance has already been reduced by amending the design and route alignment.

213. Regardless of these and various other actions taken during the IEE process and in developing the project, there will still be impacts on the environment when the infrastructure is built and when it is operating. This is mainly because most of the target villages are located in forested areas, so there will need to be some felling of trees along the MV lines and because of the dangers for workers and consumers that are inherent in maintaining or using an electricity supply system. Because of these factors the most significant impacts are on ecology and people.

214. During the construction phase, the main impacts mainly arise from the need to clear a 12 m right of way where MV lines pass through forested areas (to prevent shorting from branches touching bare conductors), and from the need to import foreign workers (which could lead to social and environmental problems in accommodation camps and neighbouring communities). These are common aspects of projects to provide rural electrification in remote areas (including Bhutan), and there are well developed methods for their mitigation. There were however no significant rare or endangered species sighted along the distribution line and discussions with the local people also revealed that there are no sensitive species in the project area. Most potential negative impacts identified were not considered significant because these are limited to the construction phase which is short in duration and due to the localised nature of impacts.

215. Although there will be areas where MV lines cross agricultural areas and private land, there will be no need to procure land as areas required are so small (ca 0.5 m2 each) and dispersed, so it is unlikely that a significant proportion of the land of any one owner will be acquired. The grievance redress mechanism will be constituted to take care in case of grievances against the project.

216. As many ARE villages are remote, isolated and not easily accessible; most of the environmental impacts are common across RE projects elsewhere in the country. Thus, BPC already has developed much experience in executing similar projects like these.

217. In order to ensure that environmental impacts are minimized as much as possible, mitigation measures have been proposed. Mitigation will be assured by a programme of environmental monitoring conducted during both construction and operation to ensure that all measures are provided as intended, and to determine whether the environment is protected as envisaged. This will include site observations, document checks, and interviews with workers and beneficiaries, and any requirements for remedial action will be reported to BPC. There will also be surveys to monitor the long-term benefits of the scheme and the adequacy of the service, and identify any deficiencies.

B. Recommendations

218. Recommendations to improve the project and reduce potential environmental impacts are;

64

 All mitigation and enhancement measures as well as the Environmental Monitoring Plan proposed in this report should be implemented in full; and  The Contractor, BPC and Department of Forest must work closely during the construction phase just to minimize environmental impacts as much as possible.

C. Conclusion

219. The environmental impacts of the proposed improvements in rural electrification infrastructure in Trashigang dzongkhag have been assessed by the Initial Environmental Examination reported in this document, conducted according to ADB guidelines.

220. The target villages in the project area are isolated, scattered and live a subsistence lifestyle, surviving on their crops and livestock products. There are no access roads, electricity and the communities feel they have been deprived of development as compared to other gewogs and dzongkhags. If the mitigation measures proposed are implemented thoroughly then the new infrastructure should provide major benefits for the recipient households and communities including greatly improved living conditions, improved health, increased incomes from new alternative livelihood opportunities, improved communication, access to information and improved education and health facilities.

221. The overall conclusion of this process is that providing the mitigation, compensation and enhancement measures are implemented in full, there should be no significant negative environmental impacts as a result of location, design, construction or operation of the subproject. There should in fact be some small benefits from recommended mitigation and enhancement measures, and major improvements in quality of life once the scheme is in operation.

65

REFERENCES

Bhargava, O.N (ed.). (1995). The Bhutan Himalaya: A geological account. Special publication 39. Geological Survey of India.

BPC. (2007). BPC monthly System Performance Reports of ESD

DGM (2002). Geology of Bhutan, Department of Geology and Mines, Ministry of Trade and Industry

DoE. (2007). Climatic data (Meteorology Division)

DoF. (1974). National Forest Policy 1974, Royal Government of Bhutan

DoF. (2002). Forestry in Bhutan, Facts and Figures 2002. Department of Forestry Services, MoA

DoF. (2007). “Rules on Biological Corridors” as an addendum to the Forest and Nature Conservation Rules 2006. MoA. RGOB

Geological Survey of India (1995). The Bhutan Himalaya: A Geological Account. Bhargava. O.N. (ed). Special publication 39. Geological Survey of India.

GNHC (2009): Tenth Five Year Plan 2008-2013. Gross National Happiness Commission. Royal Government of Bhutan

MoA. (1997). Atlas of Bhutan, Land cover & Area Statistics of 20 Dzongkhags, Land Use Planning Project. 1994. Ministry of Agriculture, Thimphu, Bhutan, RGOB.

MoA. (1997). Biodiversity Action Plan for Bhutan, Ministry of Agriculture, RGOB

MoA. (2002). Biodiversity Action Plan for Bhutan. 2002. Ministry of Agriculture, Royal Government of Bhutan

MoE. (2007). General Statistics, Policy and Planning Division, Ministry of Education, Royal Government of Bhutan

MoHCA .(2006). National Disaster Risk Management Framework. Reducing Disaster Risks for a Safe and Happy Bhutan. Disaster Management Division. Department of Local Governance. Ministry of Home and Cultural Affairs. Royal Government of Bhutan.

MoP. (1997). 9th FYP document, (2002-2007), Ministry of Planning, RGOB

MoWHS. (2006). Annual Information Bulletin, PPD, Ministry of Works and Human Settlement, RGOB

MPFD. (1991). Master Plan for Forestry Development, Main Report. 1991. Ministry of Agriculture, Department of Forestry, Royal Government of Bhutan.

Namgay, K. (2005). Biodiversity Conservation and Protected Area system in Bhutan, pp 129- 133, in People and Protected Areas in South Asia. Uday.R.Sharma and Pralad. B.

66

Yonzon. IUCN World Commission on Protected Areas

National Statistical Bureau. (2004). Statistical yearbook of Bhutan, 2004. National Statistical Bureau, RGOB

National Statistical Bureau. (2007). Statistical yearbook of Bhutan, 2007. National Statistical Bureau, RGOB

NCD. (2001). Bumdeling Wildlife Sanctuary: Conservation Management Plan July 2001-June 2007. Nature Conservation Division. Department of Forestry Services. MoA, RGOB

NCD. (2004). Bhutan Biological Conservation Complex (Living in Harmony with the Nature). A Landscape Conservation Plan: a way forward. Nature Conservation Division, DoFS, MoA

NEC (2000). Environmental Assessment Act, 2000. National Environment Commission. Royal Government of Bhutan

NEC. (2002). Regulation on Strategic Environmental Assessment, 2002, NEC, Royal Government of Bhutan

Norbu, C; Baillie, I; Dorji, T; Tamang, H.B; Tshering, K and Hutcheon, A. (2003). A provisional physiographic zonation of Bhutan. Journal of Bhutan Studies. 54.

REMP. (2004). Rural Electrification Master Plan, Japan International Corporation Agency (JICA)

RGOB. (1995). Forest and Nature Conservation Act of Bhutan. Royal Government of Bhutan

RGOB. (2001). Electricity Act of Bhutan, Royal Government of Bhutan

RGOB. (2002). GYT (Gewog Yargay Tshogdue) Act. Royal Government of Bhutan

RGOB. (2005). Population and Housing Census of Bhutan, 2005. Office of the Census Commissioner, Royal Government of Bhutan

RGOB. (2006). Forest and Nature Conservation Rules 2006 DoF. Royal Government of Bhutan

Special Commission (2007). List of Monasteries in Bhutan, Special Commission

67

ANNEXURES

Annex 1: List of species found in project area

Table 1.1: Flora recorded from project sites during field surveys for this project

Spiraea bella Benthamedia capitata Cotoneaster microphylla Rubus ellipticus Docynia indica Nepeta ribes alpestre Rhus chinensis Impatiens sulcata Rubus foliosus Betula utilis Pholidota articulata Hydrangea spp. Ablizzia spp. Toricellia tillifolia Cornus capitata Quercus Arthraxon Elsholtzia fruticosa Mussaenda roxburghii Geranium spp. Sorbus capitata Taxus baccata Aster albescens Mallotus nepaulensis Michelia champaca Potentilla spp. Morina polyphylla Macaranga peltata Fragaria nubicola Rosa sericea Quercus glauca Adiantum spp. Rosa macrophylla Quercus griffithii Anemone rivularis Ardisia spp. Quercus lamellosa Physalis spp. Viburnum erubescens Quercus lanata Triumfetta rhomboidea Rhapidophora spp. Quercus semicarpifolia Bidens pilosa Colocasia Rhododendron Gnaphalium affine Remus Pieris formosa Nepeta lemiopsis Grewia spp. Rhododendron arboreum Aster spp. Sorbus cuspidata Rhododendron edgeworthii Commenlina spp. Hedera nepaulensis Rhododendron triflorum Ranunculus spp. Berberis aristata Rhododendron kendrichii Thalictrum virgatum Castanopsis spp. Rhododendron Keysii Smilacina purpurea Coriaria nepalensis Ilex dipyrena Inula spp. Chirita spp. Myrsine semiserrata Cirsium falconeri Malva verticillata Acer campbellii Rubia spp. Artemesia spp.l Aconogonum molle Arisaema spp. Daphne spp. Alnus nepalensis Osbeckia stellata Smilacina purpurea Ardea spp. Podophyllum hexandrum Hedychium spicatum Arundinaria spp. Cassa tora Solanum khasianum Pinus wallichiana Oxyspora spp. Solanum torvum Abies densa Juniperus recurva Pilea umbrosa Ilex fragilis Lindera spp. Pteridium aquilinum Duabanga spp. Ficus spp. Eupatorium adenophorum Dichroa febrifuga Rhus chinensis Gaultheria fragrantissima Lyonia ovalifolia Sorbus microphylla Girardinia spp. Juglans regia Tsuga dumosa

68

Table 1.2: Fauna known to occur in Project sites

Common Name Scientific Name Leopard Panthera pardus Leopard cat Prionailurus bengalensis Wild dog Cuon alpinus Barking deer Muntiacus muntjak Indian porcupine Hysterix indica Sambar Cervus unicolor Wild pig Sus scrofa Goral Naemorhedus goral Serow Capricornis sumatraensis Sloth Bear Melursus ursinus Himalayan Black Selenarctos thibetanus Bear Clouded Leopard Neofelis nebulosa Capped Langur Trachypithecus pileatus

69

Table 1.3: Avifauna recorded in Project sites

Common Name Scientific Name 1 Aberrant Bush Warbler Cettia flavolivacea 2 Ashy Drongo Dicrurus leucophaeus 3 Ashy-throated Warbler Phylloscopus maculipennis 4 Bar-winged Wren Babbler Spelaeornis troglodytoides 5 Black Bulbul Hypsipetes leucocephlus 6 Black Eagle Ichtinaetus malayensis 7 Blacked-faced Laughingthrush Garrulax affinis 8 Black-tailed Crake Porzana bicolor 9 Black-throated Parrotbill Paradoxornis nipalensis 10 Blood Pheasant lthaginis cruentus 11 Blue Rock Thrush Monticola solitarius 12 Blue Whistling Thrush Myophonus caeruleus 13 Blyth's Tragopan Tragopan blythii 14 Brown Shrike Lanius cristatus 15 Common Myna Acridotheres tristis 16 Grey Bushchat Saxicola ferreus 17 Grey Treepie Dendrocitta formosae 18 Grey Wagtail Motacilla cinerea 19 Grey-bellied Cuckoo Cacomantis passerinus 20 Large-billed Crow Corvus macrorhynchos 21 Long-billed Thrush Zoothera monticola 22 Long-tailed Shrike Lanius schach 23 Mrs Gould's Sunbird Aethopyga gouldiae 24 Oriental Turtle Dove Streptopelia Orientails 25 Pale Blue Flycatcher Cyornis unicolor 26 Red-rumped Swallow Hirundo daurica 27 Rufous-breasted Bush Robin Tarsiger hyperythrus 28 Rufous-capped Babbler Stachyris ruficeps 29 Rufous-fronted Babbler Stachyris rufifrons 30 Rufous-winged Fulvetta Alcippe castaneceps 31 Russet Sparrow Passer rutilans 32 White-browed Shortwing Brachypteryx montana 33 White-tailed Robin Myiomela leucura

70

Annex 2: Summary of Public Consultation

With the permission of the Dzongkhag, a public consultation was held at Khashitheng on the 13th of June, 2009. Being the cropping season, most households were busy with varied tasks and thus the meeting was held in the evening. The meeting was attended by residents of Khashitheng (9 participants) and Phaju Goenpa (22 participants). The meeting was held as per the following agenda;

Introduction. The Tsogpa of Phaju Goenpa introduced the consultant and explained the purpose of the meeting to the participants. Following this the consultant began by speaking about the project, its objectives and how the target villages were included under this project.

EIA and Public consultation. An explanation on the Protected Area Conservation Policy and Environmental Assessment procedures was given. It was explained that an Environmental Clearance process has to be followed for all new development projects. Depending on the location, size and nature of the project, proposed activities are categorized by the NEC and accordingly Environmental Clearance Procedures have to be followed. Since the distribution line from Trephu to Khashitheng crosses a biological corridor and Khashitheng village itself lies in the buffer of the Sakteng Wildlife Sanctuary, an Environmental Impact Assessment was being conducted to determine the nature of the impacts that would arise from the proposed project. The assessment looked at social, cultural/religious, environmental and economic considerations and also involved conducting public consultation to seek the views of all stakeholders involved and incorporate any concerns.

Social considerations. It was explained that during the feasibility survey, it is very important that all the community members were aware that such field assessment was going on. The distribution line will be passing through different types of land use (Tsamdro, Sokshing, Pangshing and kamshing) and therefore a representative from the village was required to accompany the route surveyor to provide accurate information on land tenure and use. This would allow the route surveyor to determine the percentage of the line falling under such categories. Since the route surveyor is not a resident, a representative will be in a better position to ensure that encroachment on private land is minimized.

Cultural and Religious consideration. Since most villages have either a Lhakhang, Goenpa, Neys and Lu’s, which the surveyors are not aware of, the Tshogpa or community representative, should point out the location of these sites so that the MV line can be rerouted to avoid these.

Environmental consideration. It was explained that Bhutan is renowned for environmental conservation and therefore when donors are willing to pay for development projects, they are equally concerned that the environmental concerns are given due consideration. At the same time Environmental Conservation is one of the four pillars of Gross National Happiness and it is within the Forest Policy to maintain at least 60% forest cover at all times. In terms of forest cover, the RoW depends on the voltage of the distribution line. For 33kV, the RoW is 12m while for 11kV the RoW is 10m. People were reminded that this may not amount to much when calculated at the gewog level, but when calculated over the entire country it was quite substantial. Also, the forest provides critical habitat to many endangered species and loss of forest cover would in turn negatively impact these inhabitants.

Economic consideration. The process and the criteria used for selecting villages for inclusion in the 10th FYP were explained in detail. It was clarified that villages that were too far, very isolated and few in number were not included for on-grid electrification and will be included

71 under Solar Energy Program. The very remote location of such individual houses required very lengthy distribution lines which were not techno-economically feasible and very expensive for the government.

Public consensus. In order to seek the consensus of all affected households, the BPC was seeking public consensus from all households in the target villages. Through the Dzongkhag and Gup, individual households are asked to sign a public consensus form, basically a “No Objection” statement allowing the BPC to construct poles on their land and align the distribution line through their private land. In many areas, the Gup convened meetings to inform all households and the Tsogpa’s collected the signatures. Also, in case of absentee owners, it is the responsibility of the Gup and Tsogpa to inform them. It is crucial to ensure that all affected households are informed and sign the consensus forms so that no issues from absentee owners will arise in the future.

BPC Policy. According to the BPC policy, an individual household is fully responsible for incurring the financial cost of removal or shifting of distribution line and poles if the household wants these to be removed or placed elsewhere once the distribution line is already constructed. Therefore, to avoid such problems or disputes in the future, any changes to be made to the alignment should be incorporated during the planning stage

Aesthetics. The importance of aesthetics was also explained to the participants, especially in view of Lhakhangs, neys etc.

Environmental impacts. The positive impacts as well as the negative impacts of rural electrification was also highlighted and discussed. The village Tshogpa was asked to be actively involved during workers’ campsite selection and to raise awareness with contractors and workers on sanitation, waste generation and illegal activities such as poaching or felling of trees.

Clean Development Mechanism. The participants were informed that Bhutan is a member of a number of International Conventions, many of them related to environment and conservation because of our environmental legacy. As a member of one of the protocols, the Kyoto Protocol, the Country is interested to earn take advantage of the Clean Development Mechanism (CDM), which a mechanism in which Bhutan can earn credits for reducing Carbon emission.

Participant views. The participants were asked for their views on the project and their comments were solicited.

Summary of Discussions. Endorsement of the Project. The participants said that they were very happy that the project was finally coming through. There had been meetings in the past but they were not sure whether the project was really coming through.

Location and administrative jurisdiction. The participants explained that although the two villages are very close to each other, they actually fall under different Dzongkhags, Khashitheng under Trashigang, and Phaju Goenpa under Samdrup Jongkhar and hence all administrative procedures have to be followed through two different dzongkhags. Administratively Khashitheng village falls under the jurisdiction of Sakteng Wildlife Sanctuary as it falls near the PA boundary and residents are bound by PA regulations. A river separates the two villages so Phaju Goenpa falls under the jurisdiction of the Divisional Forest Office in Samdrup Jongkhar. It is due to this, that the two villages also do not enjoy the same benefits from their dzongkhags. For instance,

72

Khashitheng residents have been given solar systems but just across the river Phaju Goenpa residents were living in darkness.

Use of solar panels. The residents of Khashitheng had been given solar systems twice, but many had stopped using them, because they were either too old or because bulbs kept getting damaged. The closest market for the bulbs is Tintali, a small town located along the India/Bhutan border, 2 days walk from the village. There is also no facility to repair the defective systems so they remain disused.

Electrification and Public consultation. The participants said that a few months ago staff from BPC had come for the route survey and also conducted similar meetings in two villages, in Phaju Goenpa and at Trephu. At that time, residents split up and attended the meeting in one of the two villages. During that meeting the community had requested BPC to include them in the electrification program and participants said that they were very happy to know about the positive development towards the fulfillment of their request. They hoped that the funds will be received soon and the project can be initiated as soon as possible. As much of the topics were similar to the previous meeting with BPC staff, the participants did not have any queries and felt that the project will benefit all of them even though some may be affected at the individual level. Since it was for the greater good of the community, they are willing to make few sacrifices.

Alignment of the distribution line. The consultant explained that the BPC were exploring two options for the route alignment. One was from Trephu to Khashitheng while the other was from Diafam. Right now electricity has been provided till Jampa, a little above the dungkhag office. Along the alignment from Trephu to Khashitheng there were no villages and the distribution line was very long, passing through pasture land and forest area. Although there may be some environmental impact, the villagers felt that this may be a better route than the alternative from Diafam. The reason for choosing this over the Daifam alignment is because the route from Diafam northwards will have to pass through many landslide prone areas and unstable hill slopes. Also, there are no permanent bridges and the heavy rain during summers usually washes away the foot trails and access routes. There is currently a farm road being constructed till Tokaphu but due to unstable and huge rocky slopes, and the heavy rains, the construction has also been delayed. Since the distribution line from the south will have to pass through India, it may be risky as well as unreliable especially if and when there are strikes along the border areas.

Benefits of the project. The participants said that they generally use approximately 2 truckloads of fuel wood per year. In khashitheng, households can seek permit for 1 tree each year for firewood, but can collect any amount of dry wood without permit. Approximately 20 liters of kerosene is used in a year which does not amount to much but has to be transported from the border town where all the supplies are purchased. Currently water mills are used for grinding maize but with electrification, the owners may switch to electricity. Other benefits that the participants articulated included conservation of forest areas around the village through a reduction in tree felling. In and around the villages, farmers will be better able to protect their crops as well as livestock through improved sight/visibility at night. Households can also live in cleaner surroundings. Currently most of them cook inside the house and the smoke from the fireplace makes the house very dirty as well as smoky creating an unhealthy atmosphere for children, especially as their houses are not very large and gets filled with smoke easily. Due to the remote location and lack of facilities there are opportunities of improving their livelihood. There were 15 households that lived at Khashitheng previously but now there are

73 only 9 households as 6 have resettled elsewhere due to the harsh living conditions and lack of adequate land for farming.

The Consultant informed the meeting that the Forestry clearance had already been granted by the park but the alignment was currently under review for technical and economic feasibility. Thus it is not clear whether the line would be tapped from the north (Trephu) or the South (Diafam). The participants said that they were happy that such isolated and remote villages like theirs were being considered for electrification and expressed their gratitude to the government as well as the donors for this initiative. They said they had no issues or concerns about the project and all of them have already signed the public consensus forms giving their consent to the project.

74

List of participants at the Public consultation

Trashigang Participant list

No. Name 1 Karma Wangdi 2 Pema Dorji 3 Jomo Yangzom 4 Dorji Doma 5 Yanchen Lhamo 6 Sonam Tobgay 7 Ngawang Tshomo 8 Tshewang Tenzin 9 Norbu Jatsho 10 Yankey Zomba 11 Tshewang Gemo 12 Jigme Yozer 13 Dhendup 14 Thinley Wangdi 15 Phuntso Wangmo 16 Sonam Choden 17 Ngawang Dorji 18 Tenzing Dorji 19 Tashi Tshering 20 Jurmi Tsheltrim 21 Choki Dorji 22 Nima Yozer 23 Kinley Gyeltshen 24 Chenga Dorji 25 Sangay Khandu 26 Tobgay 27 Tshering Lhaden 28 Pema Tshering 29 Tshering Dorji 30 Sangay Phuntso 31 Rinchen Dawa

75

Annex 3: Photos from Project sites

Photo 1: Trephu village –first village Photo 2: Starting point for Feeder ARE101 for feeder ARE101 included in Re 4.

Photo 3: First Grazing land along alignment Photo 4: 2 grazing land/pasture

Photo 5: 3rd Pasture land Photo 6: Herder camps

76

Photo 7: Fir forest Photo 8: Broadleaf forest

Photo 1: Khashitheng village Photo 2: Phaju goenpa village

Photo 9: Khashitheng Photo 10: villages further south on slopes under Samdrup Jongkhar

Photo 11: Public consultation Photo 12: Participants at meeting

77

Photo 13: Temple at Khashitheng Photo 14: Stupa en-route to Khashitheng

78

Photo 15: Trashigang Dzong Photo 16: Gup office at Merak

Photo 17: Farmroad under construction to village Photo 18: Distribution line

79

Annex 4: Sample copy of MOU between BPC and individual households

Page 1/3

Page

80

2/3

81

Page 3/3

82

i Forest and Nature Conservation Act, 1995, RGOB

83