Parklands Ltd

THE MURRAY PARKWAYS to Wodonga to Wahgunyah

Implementation Plan High Country Rail Trail 2012 to 2015

Enhancing the river environment Improving community access Connecting Indigenous communities to country through co-management

Parklands Albury Wodonga Limited P.O. Box 1040 Wodonga VIC 3689

Phone: 02 6023 6714 Fax: 02 6023 2425 Email: [email protected]

Date: 29th June 2012 Updated: 6th Auguest 2012

CONTENTS

Overview of Strategic Plan 2010 to 2022 ...... 2 Summary of Action Plan 2010 to 2022 in Strategic Plan ...... 2 Summary of Action Plan 2012-2015 for High Country Rail Trail ...... 3 Resource Requirements 2012 to 2015 ...... 5 1. Short term ...... 5 2. Medium Term ...... 7 3. Longer Term ...... 9 Specific Sections - Action Plan 2012 to 2015 ...... 10 4. Gateway Island to Wodonga ...... 10 5. Wodonga to Whytes Road, Bandiana ...... 11 6. Whytes Road to Kiewa River, Bandiana ...... 12 7. Kiewa River to Gullivers Lane, Bonegilla...... 14 8. Gullivers Lane to Sandy Creek Inlet ...... 15 9. Sandy Creek Inlet to ...... 16 10. Tallangatta to ...... 17 11. Old Tallangatta to Road ...... 17 12. Granya Road to Darbyshire Wayside Stop ...... 18 13. Darbyshire to Shelley ...... 19 14. Shelley to Mansells Road ...... 20 15. Mansells Road to The Needles ...... 21 16. The Needles to Touzels Road ...... 22 17. Whiteheads Road ...... 23 18. Cudgewa Valley Road ...... 24 19. Back Cudgewa Road ...... 25 20. to Colac Colac ...... 25 21. Colac Colac to Corryong ...... 25

1 Overview of Strategic Plan 2010 to 2022 This Action Plan is part of Parklands Albury Wodonga’s 2010 to 2022 Strategic Planning Process;

Strategic Plan 2010 to 2022

Schedule of Works 2010 to 2022

Action Plan 2012-15 Action Plan 2012-15 Action Plan 2012-15 Action Plan 2012-15 High Country Kiewa River Wodonga Hills Rail Trail

Strategic Plan (2010 to 2022): identifies the focus for Parklands Albury Wodonga and the modus operandi: a partnership culture in the planning and implementation.

Strategic Plan – Schedule of Works (2010 to 2022): identifies the key works proposed that are unique to specific sites. Whilst not stated in these works schedules, consistent and continued pest plant and animal control and fire management strategies will be required to be undertaken for the length of this strategic plan.

Action Plan (2012 to 2015): prioritises works identified in the Schedule of Works and provides detailed maps and costings for the initial stages.

Summary of Action Plan 2010 to 2022 in Strategic Plan

Precinct D – High Country Rail Trail

Community Support Bonegilla Rail Trail Advisory Group, Tallangatta Rail Trail Advisory Involvement Group and Shelley Development Association. In short term, build relationship with Cudgewa community. In medium term, establish Wodonga Rail Trail Advisory Group when VicTrack lease of disused railway corridor issued. Recreational Maintain existing 55km rail trail (slash, spray and roll) facilities Upgrade trail surface between Wodonga and Tallangatta. In short term, restore 5 trestle bridges & install 1 low level footbridge In medium term, low level crossings at 12 other timber trestle bridges. In longer term, restore one or two of biggest timber trestle bridges. Biodiversity Maintain and enhance corridor with focus on pest plant and animal control. measures In short term, 7km of fencing and revegetation (Darbyshire). In medium term, 8km of fences and revegetation (Cudgewa). Fire Prevention Biannual spray and slash of track. Slash five metre strips at occupational crossings to establish breaks along linear corridor. Environmental burn every 5 years (important for native grasses).

2 Summary of Action Plan 2012-2015 for High Country Rail Trail

SECTION DISTANCE CONDITION SHORT TERM GOAL LONG TERM GOAL 1 Gateway Island to 4km Closed Use Gateway Island trail in the VicTrack lease to be confirmed Wodonga interim Hand rails on 3 bridges 2 Wodonga to 6.2km Closed Use Rail Trail Link trail in the VicTrack lease to be confirmed Whytes Road interim Paved surface 3 Whytes Road to 1km Gravel North East Water 5 year lease to Identify alternative route by 2022 Kiewa River 2017 4 Kiewa River to 1.5km Gravel Develop proposal to build Finns floodplain 400m boardwalk Gullivers Lane Inaccessible boardwalk Kiewa wetlands 400m boardwalk when flooded 5 Gullivers Lane to 17km Rough gravel Upgrade gravel surface Sealed trail Sandy Creek 6 Sandy Creek to 9km OK gravel Upgrade gravel surface Sealed trail Tallangatta 7 Tallangatta to Old 8km Sealed Tallangatta 8 Old Tallangatta to 6km Closed 4km off road Footbridge off Tallangatta Creek Granya Road 2km on road verge from Murray Valley Hwy bridge Tallangatta Creek 2km fences 9 Granya Road to 8.3km To be open by 7km fences Murray Valley October 2012 Low level access around 3 bridges Hwy Restore Dry Forest Creek bridge 10a Darbyshire to 10km Rough gravel Low level access around 3 bridges Restore Boggy Creek trestle Koetong Restore Darbyshire Creek bridge bridge as Icon of rail trail Upgrade trail surface Land swap (Firebrace Track) 10b Koetong to 10km Rough gravel Upgrade trail surface Mar 2013 Shelley Restore Edgars Rd trestle bridge Tracks around 2 Koetong bridges 11 Shelley to 10km Closed Cancel HPV lease Improve plantation road surface Mansells Rd Restore trestle bridge x 1 12a Mansells Rd to 4.7km Closed 2km fences in 2012/13 Low level crossings of bridges x 3 Lucyvale Rd Use quiet Mansells Rd in interim Junction 12b Lucyvale Rd to 2.5km Closed 2km fences in 2012/13 Murray Valley Use quiet Lucyvale Rd in interim Hwy 12c Lucyvale Rd 1.5km Closed In interim, use alternative bridge Restore Needles bridge Junction to the crossing via on road section (not Needles ideal as busy road) 13 The Needles to 6.3km Closed 3km fences in 2013/14 Cudgewa Creek footbridge Touzels Rd Low level crossing of Cudgewa Ck 14 Whiteheads Road 2.8km Quiet country Use 2.8km Whiteheads Road in 1.5km track & some fencing section road interim Safety hand rails on footbridge1 Closed Low level crossing of bridge x 1 15 Cudgewa Valley 3km Quiet country Use 1km Cudgewa Valley Rd Road road Use 2km off road on rail trail 2km Accessible (slash, spray & grade) Signage at start / end point 16 Back Cudgewa 4km Quiet country Signage Road road 17 Back Cudgewa 2km Busy highway Use 2km Murray Valley Hwy Construct off road trail Road to Colac Signage Colac 18 Colac Colac to 6km Quality Gravel Good condition Corryong bike trail 123.8km

3 Short Term (underway) Medium Term (priority works funded) Medium Term (need permission) Medium Term (contingent on funding) Longer Term

1

2 4 3 9 10 8 11 5 16 17 7 19 21 6 15 18 14 20 12 13

4 Resource Requirements 2012 to 2015

1. Short term

SECTION PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY BUDGET

1 Gateway Island to Wodonga Short term Lease from VicTrack Time VicTrack tba 2 Wodonga to Whytes Road Short term Lease from VicTrack Time VicTrack   $0 3 Middle Creek corridor Short term Maintain Middle Creek Chemicals BAG & North East Water   $0 corridor per lease 3 Middle Creek corridor Short term Identify alternative route Time BAG   $0 4 Kiewa to Gullivers Road Short term Design boardwalk for all Time BAG & Wodonga TAFE $2,000 weather access 4 Kiewa to Gullivers Road Short term Build Kiewa River Timber & Labour BAG & Wodonga TAFE $100,000 boardwalk timber students 5 Gullivers Road to Sandy Creek Short term Upgrade rail trail surface - Granulite BAG, City of Wodonga & $50,000 gravel Indigo Shire Council 6 Sandy Creek to Tallangatta Short term Upgrade rail trail surface - Granulite TAG & Towong Shire $25,000 gravel Council 7 Tallangatta to Old Tallangatta Short term Woody weed removal Time & chemicals TAG   $0 8 Old Tallangatta to Granya Rd Short term On road including  $0 Tallangatta Creek bridge 9 Granya Road to VicRoads Short term 7km fences Fence materials & NECMA grant   Parking labour 9 Granya Road to VicRoads Short term Grade rail trail Grader & roller $5,000 Parking 9 Granya Road to VicRoads Short term Track around two trestle Dozer TAG & DSE   Parking bridges 9 Granya Road to VicRoads Short term Low level crossing of Dry Signs & stepping TAG $5,000 Parking Forest Creek stones 9 Granya Road to VicRoads Short term Risk management signage Steel pipe & signs DSE safety grant   Parking

5 SECTION PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY BUDGET

10 Darbyshire to Shelley Short term Grade rail trail Grader & roller Army Reserve, KSDA & HVP   10 Darbyshire to Shelley Short term Track around two Koetong Dozer KSDA & Army Reserve   Creek bridges 10 Darbyshire to Shelley Short term Low level crossing of Signs & stepping TAG   Darbyshire Creek stones 10 Darbyshire to Shelley Short term Risk management signage Steel pipe & signs DSE safety grant   & barriers 11 Shelley to Mansells Road Short term Start negotiations with Time KSDA & Hancock   Hancock Plantations to Plantations cancel lease of rail corridor 12 Mansells Road to the Needles Short term 4km fences Fence materials C4N grant   13 The Needles to Touzells Road Short term Utilise vehicular bridge and Steel & risk signage KSDA $6,000 Murray Valley Hwy as an & grader interim option 18 Colac Colac to Corryong Short term Utilise existing off road Towong Shire Council $0 gravel rail trail TOTAL SHORT TERM $193,000 BUDGET

6 2. Medium Term

SECTION PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY BUDGET

1 Gateway Island to Wodonga Medium term Establish track Bobcat & time Hume Building Society & North $2,000 Albury Rotary Club 1 Gateway Island to Wodonga Medium term Risk management signs Signs at crossings & Sponsor $2,000 bridges 1 Gateway Island to Wodonga Medium term Safety hand rails on Wodonga Steel hand railing & Sponsor $20,000 Creek bridge Grating for drainage 1 Gateway Island to Wodonga Medium term Safety hand rails on Flanagans Steel hand railing Sponsor $10,000 Creek bridge 1 Gateway Island to Wodonga Medium term Ramp off railway abutment to Fill Sponsor $1,000 Gateway Wetlands 2 Wodonga to Whytes Road Medium term Establish track Spray, signs & rails at Wodonga Rail Trail Advisory $5,000 roads Group 4 Kiewa to Gullivers Road Medium term Build Finns Creek boardwalk Timber & Labour BAG & Wodonga TAFE timber $100,000 students 5 Gullivers Road to Sandy Creek Medium term Seal 17km of rail trail Bitumen City of Wodonga & Indigo Shire $510,000 Council 6 Sandy Creek to Tallangatta Medium term Seal 8km of rail trail Bitumen TAG & Towong Shire Council $240,000 9 Granya Road to VicRoads Medium term Repair / replace Dry Forest Timber & contractor? Puffing Billy Association $50,000 Parking Creek bridge 10 Darbyshire to Shelley Medium term Restore Edgars Rd trestle bridge Timber DSE safety grant   10 Darbyshire to Shelley Medium term Restore Darbyshire Creek bridge Bridge contractor Puffing Billy Association   10 Darbyshire to Shelley Medium term Station Platform signs Steel & signwriter KSDA  $1,000 12 Mansells Road to the Needles Medium term Grade rail trail Grader & roller Cudgewa Rail Trail Group $5,000 12 Mansells Road to the Needles Medium term Low level crossing of three Signs & stepping stones Cudgewa Rail Trail Group $3,000 bridges 12 Mansells Road to the Needles Medium term Risk management signage & Steel pipe & signs Cudgewa Rail Trail Group $3,000 barriers 12 Mansells Road to the Needles Medium term Station Platform signs Steel & signwriter Cudgewa Rail Trail Group $1,000 (Beetoomba) 13 The Needles to Touzells Road Medium term Restore Needles Trestle bridge Timber & contractor Sponsor to be sourced $60,000 14 Whiteheads Road Medium term 2km fences Fence materials C4N grant   14 Whiteheads Road Medium term Grade rail trail Grader & roller Cudgewa Rail Trail Group $5,000

7 14 Whiteheads Road Medium term Restore / replace Cudgewa Ck Timber & bridge Cudgewa Rail Trail Group $60,000 bridge builder 14 Whiteheads Road Medium term Station Platform signs Steel & signwriter Cudgewa Rail Trail Group $1,000

15 Cudgewa Valley Road Medium term Slash & spray 2km of old railway Spray rig and tractor VicRoads & Cudgewa Rail Trail ü  in road reserve and 1km to and time to get Group Whiteheads Rd permission 15 Cudgewa Valley Road Medium term Station Platform & distance Steel & signwriter Cudgewa Rail Trail Group  $1,000 signs

15 Cudgewa Valley Road Medium term Grade rail trail Grader & roller Cudgewa Rail Trail Group $5,000 16 Back Cudgewa Road Medium term Signage along Back Cudgewa Permission from TSC & Towong Shire Council & $500 Road to link from Cudgewa to distance signs Cudgewa Rail Trail Group Colac Colac 17 Murray Valley Hwy to Colac Medium term On road for 2km to Colac Colac Timeto get permission VicRoads, Towong Shire Council $500 Colac Caravan Park & signage & Cudgewa Rail Trail Group

Medium term TOTAL $1,086,000 MEDIUM TERM BUDGET

8 3. Longer Term

SECTION PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY BUDGET

1 Gateway Island to Wodonga Long term Seal or pave track Bitumen or cement City of Wodonga tba 2 Wodonga to Whytes Road Long term Seal or pave track Bitumen or cement City of Wodonga tba 3 Middle Creek corridor Long term Secure funding to relocate tba corridor 8 Old Tallangatta to Granya Rd Long term Grade rail trail Grader & roller $5,000 8 Old Tallangatta to Granya Rd Long term Fences (2km new) & repairs to Fence materials $10,000 existing 8 Old Tallangatta to Granya Rd Long term Footbridge off Murray Valley Hwy Bridge contractor $60,000 bridge 10 Darbyshire to Shelley Long term Land swap / trail west of Boggy Time DSE Creek 11 Shelley to Mansells Road Long term Risk management signage & Steel pipe & signs $3,000 barriers 11 Shelley to Mansells Road Long term Restore Mansells Road trestle Timber & bridge $60,000 bridge builder 15 Cudgewa Valley Road Long term Low level crossing x 2 or restore / Timber & bridge Cudgewa Rail Trail Group $20,000 replace 2 small trestle bridges builder 15 Cudgewa Valley Road Long term 1km fences and grade rail trail Fence materials & Cudgewa Rail Trail Group $10,000 corridor grader 17 Murray Valley Hwy to Colac Long term Off road 2km rail trail to Colac Gravel Sponsor to be sourced $60,000 Colac Colac Caravan Park Long term TOTAL $228,000 LONGER TERM BUDGET

TOTAL $1,507,000 BUDGET

9 Specific Sections - Action Plan 2012 to 2015

4. Gateway Island to Wodonga PRIORITY ACTION RESOURCES PARTNER / BUDGET STAKEHOLDER Short term Lease from VicTrack Time VicTrack tba Medium term Establish track Bobcat & time Hume Building $2,000 Society Medium term Risk management signs Signs at crossings & bridges Sponsor $2,000 Medium term Safety hand rails on Wodonga Creek bridge Steel hand railing Sponsor $20,000 Grating for drainage Medium term Safety hand rails on Flanagans Creek bridge Steel hand railing Sponsor $10,000 Medium term Ramp off railway abutment to Gateway Wetlands Fill Sponsor 1,000 Long term Seal or pave track City of Wodonga tba

10 5. Wodonga to Whytes Road, Bandiana WHEN ACTION RESOURCES PARTNER BUDGET Short term Lease from VicTrack Time VicTrack nil Medium term Establish track Spray, signs & rails at roads Wodonga Rail Trail Advisory Group $5,000 Long term Seal or pave track Seal or pave track City of Wodonga tba

11 6. Whytes Road to Kiewa River, Bandiana PRIORITY ACTION RESOURCES PARTNER BUDGET High Maintain Middle Creek corridor per lease Chemicals BAG & North East Water High Identify alternative route Time BAG time Low Secure funding to relocate corridor

12

13 7. Kiewa River to Gullivers Lane, Bonegilla PRIORITY ACTION RESOURCES PARTNER BUDGET High Design boardwalk for all weather access Time BAG & Wodonga TAFE Medium Build Kiewa River boardwalk Timber BAG, Wodonga TAFE & Personnel Group est $200,000 Labour Medium Build Finns Floodplain boardwalk Timber BAG est $200,000 Labour Wodonga TAFE timber students

14 8. Gullivers Lane to Sandy Creek Inlet PRIORITY ACTION RESOURCES PARTNER BUDGET Short term Upgrade rail trail surface - gravel Granulite BAG $50,000 City of Wodonga Indigo Shire Council Medium term Seal 17km of rail trail Bitumen City of Wodonga $510,000 Indigo Shire Council

15 9. Sandy Creek Inlet to Tallangatta PRIORITY ACTION RESOURCES PARTNER BUDGET Short term Upgrade rail trail surface - gravel Granulite TAG 25,000 Towong Shire Council Medium term Seal 8km of rail trail Bitumen Towong Shire Council 240,000 Estimated Total 265,000

16 10. Tallangatta to Old Tallangatta PRIORITY ACTION RESOURCES PARTNER UNDERWAY / FUNDS PLANNED SOUGHT Short term Woody weed removal Time & chemicals TAG 

11. Old Tallangatta to Granya Road PRIORITY ACTION RESOURCES UNDERWAY / FUNDS PLANNED SOUGHT Short term On road including Tallangatta Creek bridge  Longer term (when all other sections finished) Grade rail trail Grader & roller 5,000 Longer term (when all other sections finished) Fences (2km new) & repairs to existing Fence materials 10,000 Longer term (when all other sections finished) Footbridge off Murray Valley Hwy bridge Bridge contractor 60,000 Estimated Total 75,000

Tallangatta Creek Granya Rd Moscrops Rd

Old Tallangatta

Open in longer term Open in short term

Open in short term Track from rail trail to Murray Valley Hwy Murray Valley Highway Tallangatta bridge then back onto Valley Rd rail trail

17 12. Granya Road to Darbyshire Wayside Stop PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / FUNDS PLANNED SOUGHT Short term 7km fences Fence materials & labour NECMA grant  Short term Grade rail trail Grader & roller 5,000 Short term Track around two trestle bridges Dozer TAG & DSE  Short term Low level crossing of Dry Forest Creek Signs & stepping stones TAG 5,000 Short term Risk management signage Steel pipe & signs DSE safety grant  Medium term Repair / replace Dry Forest Creek bridge Timber & contractor? Puffing Billy Association 50,000 Medium term Gazettal as rail trail Time Estimated Total 60,000

Track around Restore trestle bridge bridge

Track around Track around trestle bridge trestle bridge

Dry Forest Murray Valley Hwy Ck bridge

Avondale Rd

18 13. Darbyshire to Shelley PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY FUNDS SOUGHT Short term Grade rail trail Grader & roller Army Reserve, KSDA & HVP  Short term Track around two Koetong Creek bridges Dozer KSDA & Army Reserve  Short term Low level crossing of Darbyshire Creek Signs & stepping stones TAG  Short term Risk management signage & barriers Steel pipe & signs DSE safety grant  Medium term Restore Edgars Rd trestle bridge Timber DSE safety grant  Restore Darbyshire Creek bridge Bridge contractor Puffing Billy Association Medium term Station Platform signs Steel & signwriter KSDA  Longer term Land swap / trail west of Boggy Creek Time DSE Estimated Total Nil

Boggy Creek bridge Koetong Station

Murray Valley Highway

Restore Edgars Rd Bridge

Track around Bridge Track around Bridge Murray Valley Hwy Restore Darbyshire Bridge

Track around Bridge

Shelley Station

Avondale Rd

19 14. Shelley to Mansells Road PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / FUNDS PLANNED SOUGHT Short term Start negotiations with Hancock Time KSDA  Plantations to cancel lease of rail corridor Hancock Plantations Longer term Risk management signage & barriers Steel pipe & signs 3,000 Longer term Restore Mansells Road trestle bridge Timber 60,000 Bridge contractor Longer term Gazettal of corridor Time DSE Estimated Total 63,000

Shelley Station

Track around bridge

Track around bridge

Restore bridge

Track around bridge

End of Pine Plantations

20 15. Mansells Road to The Needles PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / PLANNED FUNDS SOUGHT Short term 4km fences Fence materials C4N grant  Medium term Grade rail trail Grader & roller Cudgewa Rail Trail Group 5,000 Medium term Low level crossing of three bridges Signs & stepping stones Cudgewa Rail Trail Group 3,000 Medium term Risk management signage & barriers Steel pipe & signs Cudgewa Rail Trail Group 3,000 Medium term Station Platform signs (Beetoomba) Steel & signwriter Cudgewa Rail Trail Group 1,000 Estimated Total 12,000

Restore The Needles Low level crossing Trestle bridge near bridge Needles Picnic Area

Murray Valley Highway

Lucyvale Road

Low level crossing near bridge

Low level crossing near bridge

Low level crossing near bridge Mansells Road

21 16. The Needles to Touzels Road PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / PLANNED FUNDS SOUGHT Short term Utilise vehicular bridge and Murray Steel & risk signage KSDA $6,000 Valley Hwy as an interim option Grader Cudgewa Rail Trail Group Medium term Restore Needles Trestle bridge Timber & contractor Sponsor to be sourced $60,000 Estimated Total $66,000

22 17. Whiteheads Road PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY/PLANNED FUNDS SOUGHT Medium term 2km fences Fence materials C4N grant  Medium term Grade rail trail Grader & roller Cudgewa Rail Trail Group 5,000 Medium term Restore / replace Cudgewa Ck bridge Timber & bridge builder Cudgewa Rail Trail Group 60,000 Medium term Station Platform signs Steel & signwriter Cudgewa Rail Trail Group 1,000 Estimated Total 66,000

23 18. Cudgewa Valley Road PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / FUNDS PLANNED SOUGHT Medium term Slash & spray 2km of old railway in road Spray rig and tractor Cudgewa Rail Trail Group  reserve and 1km to Whiteheads Rd Time to get permission VicRoads Medium term Station Platform & distance signs Steel & signwriter Cudgewa Rail Trail Group 1,000 Medium term Grade rail trail Grader & roller Cudgewa Rail Trail Group 5,000 Longer term Low level crossing x 2 or restore / Timber & bridge builder Cudgewa Rail Trail Group 20,000 replace 2 small trestle bridges Longer term 1km fences and grade rail trail corridor Fence materials & grader Cudgewa Rail Trail Group 10,000 Estimated Total 36,000

24 19. Back Cudgewa Road PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / PLANNED FUNDS SOUGHT Medium term Signage along Back Cudgewa Road to Permission from TSC Towong Shire Council 500 link from Cudgewa to Colac Colac Distance signs Cudgewa Rail Trail Group

20. Murray Valley Highway to Colac Colac PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / PLANNED FUNDS SOUGHT Medium term On road for 2km to Colac Colac Time VicRoads 500 Caravan Park Signage Towong Shire Council Cudgewa Rail Trail Group Longer term Off road 2km rail trail to Colac Colac Gravel Sponsor to be sourced 60,000 Caravan Park

21. Colac Colac to Corryong PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER UNDERWAY / PLANNED FUNDS SOUGHT Short term Utilise existing off road gravel rail Towong Shire Council nil trail Cudgewa Rail Trail Group

25