NPH, ERC Case No. 2015-206 RC IN THE MATTER OF THE APPLICATION FOR APPROVAL OF CAPITAL EXPENDITURE PROJECTS FOR 2015, NAMELY: 1) CONSTRUCTION OF 69kV SUB-TRANSMISSION LINE FROM CURVADA, KAPATAGAN TO LANECO MAIN OFFICE, AND 2) DOUBLE CIRCUITING OF • BACKBONE LINE FROM KAUSWAGAN SUB-STATION TO LARAPAN BRIDGE, LINAMON, WITH PRAYER FOR PROVISIONAL AUTHORITY ERC CASE NO. 2015-206 RC LANAO .DEL NORTE ELECTRIC COOPERATIVE, ( {JiJ or l!l D D J C.JAN. 0 5 2016 INC. (LANECO), nate:, 20./ ,=..-. Applicant. .. p.o/: _W ~.~._-llI )(- - - - - - - - - - - - - - - - - - - - - - -)( NOTICE OF PUBLIC HEARING TO ALL INTERESTED PARTIES: On 07 December 2015, the Lanao del Norte Electric Cooperative, Inc. (LANECO) filed an application for the approval of capital expenditure projects (CAPEX) for 2015, namely: construction of 69kV sub-transmission line from Curvada, Kapatagan to LANECO Main Office and double circuiting of backbone line from Kauswagan sub-station to Larapan bridge, Linamon, with prayer for the issuance of provisional authority. ERC CASE NO. 2015-206 RC NOTICE OF PUBLIC HEARING/10 December 2015 Page 2 of8 In the said application, LANECO alleged, among others, the following: 1. Applicant LANECO is a non-stock, non-profit electric cooperative duly organized and existing under and by virtue of the laws of the Republic of the Philippines, with principal office at Sagadan, Poblacion, Tubod, Lanao del Norte; 2. LANECOholds an exclusive franchise from the National Electrification Commission, to operate an electric light and power distribution service in all the municipalities of the province of Lanao del Norte, namely: Tagoloan, Linamon, Kauswagan, Matungao, Poona Piagapo, Bacolod, Mango, Munai, Kolambugan, Magsaysay, Tubod, Tangcal, Baroy, Salvador, Nunungan, Lala, Sapad, Kapatagan and Sultan Naga Dimaporo. Legal Basis for the Application 3. The instant application is being submitted to. the Commission for its evaluation and approval of LANECO's proposed capital expenditure projects for 2015 pursuant to ERC Resolution No.26, Series of 2009 and other pertinent laws, rules and regulations. The Proposed Projects 4. The proposed capital expenditure projects consist of the following: Proposed Projects Project Cost (PhP) 1 Construction of 18-kilometer 69kV Subtransmission Line from Curvada, Kapatagan to LANECO'smain office 88,864,173.22 2 Double circuiting of backbone line from the lOMV A Kauswagan Substation to Larapan Bridge, Linamon, for the tapping point of the GNPower Power Plant in 6,562,060.31 Libertad, Kauswagan Total 95,426,233.53 ERC CASE NO. 2015-206 RC NOTICE OF PUBLIC HEARING/10 December 2015 Page 3 of8 Statement of Facts 5. On 02 May 2011, the Commission rendered its decision on LANECO's application for approval of its Capital Projects for Years 2009-2013 under ERC Case No. 2010- 015 RC, approving the proposed projects. with modification; 6. Among the approved projects is the Construction of 18- kilometer 69kV Subtransmission Line from Curvada, Kapatagan to the cooperative's main office in Tubod, Lanao del Norte, which includes seventy (70) footer concrete poles and overhead electrical lines, intended to address present and future load requirements as well as to energize the 10 MVA Sagadan Substation; 7. As approved, the 18- kilometer 69kV Subtransmission Line Project has a horizontal structural design of construction, with a project cost ofPhP36,000,000.00; 8. However, due to internal problems encountered by LANECO, the implementation of the said project was set aside; 9. Due to the passage of time, or more than six (6) years from the time the approved project was designed, the implementation thereof has been rendered impractical, less feasible and disadvantageous to LANECO as well as its consumers; 10. Recently, due to the urgent necessity of implementing the construction of the 18-km 69kV subtransmission line, the cooperative sought permission from the Commission to revise the conceptual engineering design as well as transfer the location of the said project. The revised' project will necessitate an increase in the project cost;' 11. However, due to the substantial revision in the conceptual engineering design and significant increase in cost of the project, the Commission instead required LANECOto file a new application for approval ofthe revised project;2 'Copy of LANECO's letter to the Commission of 1October 2014 is attached hereto as Annex "A". 2 Copy of the Commission's reply of 20 October 2014 is attached hereto as Annex "B", ERC CASE NO. 2015-206 RC NOTICE OF PUBLIC HEARING/10 December 2015 Page 4 of8 12. Hence, the present application was filed in order to revise the structural design of the project and relocate the installation of the poles to the opposite side of the road. As of finalization of the instant application, the updated proposed cost of the projects is PhP88,864,173.22, based on the National Electrification Administration (NEA) latest price index; 13. On the other hand, the GNPower Ltd. Co., a power generation company, will locate its 4-150MW Coal-Fired Power Plant in Barangay Libertad, Kauswagan, Lanao Del Norte, or within LANECO'sfranchise area; 14. Construction of the plant commenced in January 2015 and during its construction stage, it will require 4MW capacity from LANECO, to be sourced from its 10MVA Kauswagan Substation; 15. The Kauswagan Substation has a present loading of 4.56MW, and Linamon Feeder that will be serving GNPower has a present loading of 0.9MW; 16. The 3-kilometer old distribution line could not withstand the incoming load and needs rehabilitation by being converted into double-circuits construction wherein revisions on pole height, spanning/ distances and construction assemblies must be done. Hence, the instant application for the double circuiting of backbone line from Kauswagan Substation to Larapan Bridge, Linamon. Financial and Economic Evaluation 17. Project Financing. The total project cost of Ninety Five Million Four Hundred Twenty Six Thousand Two Hundred Thirty Three Pesos 53/100 (PhP95A26,233.53) will be funded through an approved loan availment from the National Electrification Administration (NEA) and the Land Bank of the Philippines (LBP) at an average interest rate of 6.125% for a term of fifteen (15)years. 18. Cash Flow. LANECO's CAPEX plan cash flow cost, shown below, has determined the viability of pursuing and implementing the proposed projects without necessarily causing a significant increase in its electricity rates, to wit: ERC CASE NO. 2015-206 RC NOTICE OF PUBLIC HEARING/10 December 2015 Page 5 of8 2015 (PhP) INFLOWS: PROJECTED SALES (kWh) 73,819,320 FUNDING SOURCES: Annual Revenue from RFSC (73,819,320 X PhPO-4004) 29,557,256 Financing: NEALoan 123,842,998 Landbank Loan 13,600,000 TOTAL (29,557,256 +123,842,998 +13,600,000) 167,000,254 OUTFLOWS: CASH FOR DEBT SERVICE Existing Loans - NEA 2,477,940 New Loans -NEA 12,975,248 - Bank/Others 5,217,137 SUB-TOTAL 20,670,325 BALANCE AFTER DEBT SERVICE ( 167,000,254- 20,670,~2S) 146,:-l2<},<}29 TOTAL CAPEX PROJECTS and ERC CAPEX PERMIT FEES 169-42:-l,512 BALANCE, END ( 146,329,929 - 169,423,512 ) (23,093,584 ) 19. Rate Impact. The instant projects were envisioned to have the least rate impact focusing on a capital expenditure plan that will bring the most value to LANECO's customers at the most reasonable and justifiable electricity rates or at the least cost of service. Shown below is the rate impact of the CAPEXProjects on its Reinvestment Fund for Sustainable CapEx (RFSC), to wit: Rate Imnact Comnutation Total (PhP) Pro;ected kWh Sales 7~,819,320 Annual Revenue from RFSC (RSEC-WR rate - PhPO-4004) 29,557,256 CAPEX Plan Cost Cash Flow Balance, End ( 23,093,584) Indicative Additional Rate (PhP 23,093,584 /73,819,320 ) 0.3128 Existing RSFC Rate 0-4004 CAPEX Plan Cost Cash Flow Rate ner kWh 0.7132 ERC CASE NO. 2015-206 RC NOTICE OF PUBLIC HEARING/10 December 2015 Page 6 of8 Allegations in Support of the Prayer for Provisional Authority 20. LANECO re-pleads the foregoing allegations in support of its application for the issuance of provisional authority; 21. The proposed construction of 69kV Line is intended to address present and future load requirements, as well as to energize the new 10 MVA Sagadan Substation which was among the approved projects under ERC Case No. 2010-015 RC; 22. Due to the influx of potential investors, it is imperative that the above proposed project be implemented as soon as possible to help lessen the critical load level of LANECO's 2-5MVA Kapatagan Substation. The 5MVA Power Transformer- Takaoka Brand has a current percentage loading of 89.55 % while the 5MVA Power Transformer - Brush Brand as a current percentage loading of 92-40 %; 23. The Kapatagan Substation will be relieved by transferring loads/ distribution lines to the 10MVA Sagadan Substation which is currently undergoing civil works construction at the main office headquarters of LANECO; 24. Further, new big load customers are rising soon in the municipalities of Kapatagan, Lala and Tubod, consisting of the Lanao del Norte Provincial Hospital and Jollibee - Maranding Branch, with a total 1MW load requirement; 25. On the other hand, the coal-fired power plant of the GNPower Ltd. Co., which will be located in Brgy. Libertad, Kauswagan, will require 4 MW capacity from LANECO during its construction stage, which has commenced in January 2015; 26. Considering the foregoing, LANECO prayed that upon filing and initial review hereof, it be granted provisional authority to implement the projects in order that the cooperative could deliver a reliable and efficient electric
Recommended publications
  • Philippines: Marawi Armed-Conflict 3W (As of 18 April 2018)
    Philippines: Marawi Armed-Conflict 3W (as of 18 April 2018) CITY OF Misamis Number of Activities by Status, Cluster & Number of Agencies EL SALVADOR Oriental 138 7,082 ALUBIJID Agencies Activities INITAO Number of CAGAYAN DE CLUSTER Ongoing Planned Completed OPOL ORO CITY (Capital) organizations NAAWAN Number of activities by Municipality/City 1-10 11-50 51-100 101-500 501-1,256 P Cash 12 27 69 10 CCCM 0 0 ILIGAN CITY 571 3 Misamis LINAMON Occidental BACOLOD Coord. 1 0 14 3 KAUSWAGAN TAGOLOAN MATUNGAO MAIGO BALOI POONA KOLAMBUGAN PANTAR TAGOLOAN II Bukidnon PIAGAPO Educ. 32 32 236 11 KAPAI Lanao del Norte PANTAO SAGUIARAN TANGCAL RAGAT MUNAI MARAWI MAGSAYSAY DITSAAN- CITY BUBONG PIAGAPO RAMAIN TUBOD FSAL 23 27 571 53 MARANTAO LALA BUADIPOSO- BAROY BUNTONG MADALUM BALINDONG SALVADOR MULONDO MAGUING TUGAYA TARAKA Health 79 20 537 KAPATAGAN 30 MADAMBA BACOLOD- Lanao TAMPARAN KALAWI SAPAD Lake POONA BAYABAO GANASSI PUALAS BINIDAYAN LUMBACA- Logistics 0 0 3 1 NUNUNGAN MASIU LUMBA-BAYABAO SULTAN NAGA DIMAPORO BAYANG UNAYAN PAGAYAWAN LUMBAYANAGUE BUMBARAN TUBARAN Multi- CALANOGAS LUMBATAN cluster 7 1 146 32 SULTAN PICONG (SULTAN GUMANDER) BUTIG DUMALONDONG WAO MAROGONG Non-Food Items 1 0 221 MALABANG 36 BALABAGAN Nutrition 82 209 519 15 KAPATAGAN Protection 61 37 1,538 37 Maguindanao Shelter 4 4 99 North Cotabato 7 WASH 177 45 1,510 32 COTABATO CITY TOTAL 640 402 6,034 The boundaries, names shown and the designations used on this map do not imply official endorsement or acceptance by the United Nations Creation date: 18 April 2018 Sources: PSA
    [Show full text]
  • Land Disputes in Conflict Affected Areas of Mindanao: Report of the Joint World Bank – International Organization for Migration Scoping Mission
    LAND DISPUTES IN CONFLICT AFFECTED AREAS OF MINDANAO: REPORT OF THE JOINT WORLD BANK – INTERNATIONAL ORGANIZATION FOR MIGRATION SCOPING MISSION MAY 2013 Table of Contents Acronyms and Abbreviations ............................................................................................................................. i Executive Summary .............................................................................................................................................. ii A. Background ..................................................................................................................................................... 1 B. Objectives ........................................................................................................................................................ 1 C. Findings ............................................................................................................................................................ 2 C. 1. General Observations ..................................................................................................................................... 2 C. 2. Findings on Competing and Overlapping Land Claims .................................................................... 4 C. 3. Institutions Involved in Land Management and Resolving Competing Land Claims ........ 14 C. 4. Availability of land tenure information (ownership and usage) ................................................ 17 C. 5. Ongoing Initiatives .......................................................................................................................................
    [Show full text]
  • Sitrep 67 NDCC Update Idps in Mindanao
    OCD Region X turned over a total of Php465,000.00 worth of financial assistance to the claimants/beneficiaries of dead and injured victims of Kolambugan and Kauswagan, Lanao del Norte The NDCC continue to enjoin all humanitarian actors providing support to the IDPs to coordinate with the local authorities, government cluster leads and work within the NDCC/RDCC and LDCC framework to ensure complimentarily and unity of efforts, minimize duplication and prioritize the provision of assistance to the most in need UN Agencies, and NGOs/INGOs, Humanitarian partners/agencies are advised to coordinate all actions with the following OCDRCs Directors who were designated as principal coordinator for a more effective delivery of assistance and information/data management : Regional Centers OCDRC Director Contact Nos. OCDRC X Dir. Carmelito A. Lupo (088) 8573988, (08822) 725673, (0917) 613-4274, (0919) 416- 3343 OCDRC XII Dir. Lita B. Enok (083) 5532994, (0916) 870-6731, (0917) 398-4732 OCD-ARMM Dir. Armando Duque (064) 4250330, (0917) 504-6233 The International Committee of Red Cross (ICRC) and the Philippine Red Cross’ emergency operations complements the efforts of the Philippine government agencies and other international organizations. It continues to coordinate its activities with the authorities in Mindanao, in particular with the representatives of NDCC and DSWD at regional, provincial and municipal levels. ICRC has now 53 staff members in Mindanao A. IDPs (No changes from the last report) Total number of IDPs INSIDE evacuation centers: 19,481 families/97,037 persons Total number of IDPs OUTSIDE evacuation centers: 56,450 families/278,827 persons Total number of IDPs served inside and outside evacuation centers: 75,931 families/375,864 persons 2 B.
    [Show full text]
  • NARAN NG Department of Education EDUK Region X - Northern Mindanao DIVISION of LANAO DEL NORTE
    Republic of the Philippines NARAN NG Department of Education EDUK Region X - Northern Mindanao DIVISION OF LANAO DEL NORTE Gov. A. Quibranza Prov'1. Gov't. Compound nm , Pigcarangan, Tubod Lanao del Norte nwnstos NG (063)227-6633, (063)341-5109 lanac.norte @deped gov. ph d.C 1713 DATE DIVISION MEMORANDUM No. 94_s, 2020 SIGNATURE NE2 2ED MAME TO ASSISTANT SCHOOLS DIVISION SUPERINTENDENT RECIPIENT SCHOOLS OF SBFP PUBLIC OF FY 2020-2021 SCHOOL FEEDING CoORDINATORS SGOD PERSONNEL BUDGET SECTION HEAD ACCOUNTING SECTION HEAD CONCERNED BOOKEEPERSS SCHOOL HEALTH PERSONNEL This Division FROM EDILBERSO L. OPLENARIA, CESO V SchoolsDivision Superintendent SUBJECT 2020 SCH0OL- BASED FEEDING PROGRAM (SBFP) ORIENTATiON DATE DECEMBER 9, 2020 immune of learners in this time ensure the and and to boost the system of1. pandemic,To the DepEdgrowth -Lanaodevelopment del Norte adheres to DepEd Order No. 039, s. 2017, " Operational Guidelines on the Implementation of School- Based Feeding Program for School Years 2017-2022, Years 2018 and 2019. and by the supplemental guidelines issued by DepEd for the Fiscal ( FY) of the 2020 SBFP Nutritious Food Packs 2. In line with this, an orientation for the implementation Division Office on December 16, 2020 at and Milk Component shall be held at the DepEd-LDN selected SGOD and selected school 9:30 AM to 1:00 PM. Physical attendees shall be the personnel below: feeding coordinator of public elementary schools mentioned NAME OF SCHOOL FEEDING DISTRICTS NAMES OF SCHOOL COORDNATOR SHEILA CASPE KAPATAGAN EAST BALILI CS DISTRICT | KAPATAGAN WEST SIXTO MAGHANOY SMCS EVA PEREZ DISTRICT KAPATAGAN CENTRAL KAPATAGAN ECS LOURDEs CARPENTERO SND WEST DISTRICT FELIX SUSON ES FE APAT SND EAST DISTRICT SULTAN ALI DIMPORO MIS CABIBA DERIPOSUN SND CENTRAL SULTAN NAGA DIMAPORO MIS | ARLENE PIOGADO SAPAD DISTRICT SAPAD CS JHAIRA DIMPORO Meanagene #GO100 Syiem A s0 9001 2015 TUVRhemlan Republic of the Philippines ARAN NG Department of Education EDUKA Region X - Northern Mindanao DIVISION OF LANAO DEL NORTE Gov.
    [Show full text]
  • Energy Projects in Region X
    Energy Projects in Region X Lisa S. Go Chief, Investment Promotion Office Department of Energy Energy Investment Briefing – Region X 16 August 2018 Cagayan De Oro City, Misamis Oriental Department of Energy Empowering the Filipino Energy Projects in Northern Mindanao Provinces Capital Camiguin Mambajao Camiguin Bukidnon Malaybalay Misamis Oriental Cagayan de Oro Misamis Misamis Misamis Occidental Oroquieta Occidental Gingoog Oriental City Lanao del Norte Tubod Oroquieta CIty Cagayan Cities De Oro Cagayan de Oro Highly Urbanized (Independent City) Iligan Ozamis CIty Malaybalay City Iligan Highly Urbanized (Independent City) Tangub CIty Malayabalay 1st Class City Bukidnon Tubod 1st Class City Valencia City Gingoog 2nd Class City Valencia 2nd Class City Lanao del Ozamis 3rd Class City Norte Oroquieta 4th Class City Tangub 4th Class City El Salvador 6th Class City Source: 2015 Census Department of Energy Empowering the Filipino Energy Projects in Region X Summary of Energy Projects Per Province Misamis Bukidnon Camiguin Lanao del Norte Misamis Oriental Total Occidental Province Cap. Cap. Cap. Cap. No. No. No. No. Cap. (MW) No. No. Cap. (MW) (MW) (MW) (MW) (MW) Coal 1 600 4 912 1 300 6 1,812.0 Hydro 28 338.14 12 1061.71 8 38.75 4 20.2 52 1,458.8 Solar 4 74.49 1 0.025 13 270.74 18 345.255 Geothermal 1 20 1 20.0 Biomass 5 77.8 5 77.8 Bunker / Diesel 4 28.7 1 4.1 2 129 6 113.03 1 15.6 14 290.43 Total 41 519.13 1 4.10 16 1,790.74 32 1,354.52 6 335.80 96 4,004.29 Next Department of Energy Empowering the Filipino As of December 31, 2017 Energy Projects in Region X Bukidnon 519.13 MW Capacity Project Name Company Name Location Resource (MW) Status 0.50 Rio Verde Inline (Phase I) Rio Verde Water Constortium, Inc.
    [Show full text]
  • I-Td Il 1 ’?K{\..E..!
    7 ,m-7 ,Q! :s<> THIRTEENTH CONGRESS OF THE REPUBLIC OF THE PHILIPPINES Third Regular Session ?6ilC~‘?/E9;.?l SENATE COMMITTEE REPORT NO. ’! 6 2 Subnjt,ted join I by the Committees on Public Works; and on Finance on $,I-td il 1 ’?K{\..e..! Re : House Bill No. 41 15 Recommending its approval without amendment. Sponsor: Senator Revilla, Jr. MR. PRESIDENT The Committees on Public Works: and on Finance, to which was referred House Bill No, 41 15, introduced by Representatives Dimaporo and Badelles, entitled: “AN ACT CONVERTING THE ILlGAN - TAGOLOAN - BALOI - PANTAO RAGAT - MUNAI - TANGKAL - MAGSAYSAY - TUBOD - SALVADOR - SAPAD - NUNllNGAN - SULTAN NAGA DIMAPORO ROAD WHICH PASSES THROUGH ILIGAN CITY AND THE PROVINCE OF LANA0 DEL NORTE INTO A NATIONAL ROAD” have considered the same and have the honor to report it back to the Senate with the recommendationthat it be approved without amendment. Respectfully submitted: FR ON NG” REVILLA, JR. fee on Finance on Public Works ;Committee on Public Works Member, Corrimittee on Finance Committee Report 011HBNo.4115 - Conversion ofNationn1 Road in the Province of lanao Del Norfe. 2 .,I .-,._."1111... 111"11" .l_"l" ",",,"__lll__.. .".,-.,.I_ I.I__.__" ^_.l_l"..l ,.--- _II_ ....-. I.I"...xI,- ' !:::$En, Committee on Public Works Member. Committee on Finance Members: MANUEL "LITO" M. LAPID . Committee on Public Works ?- /Committee on Finance Committee on Finance / MIRIAM DEFENSOR SANTIAGO Commitfee on Public Works Committee on Finance Committee on Finance EDGARDO J.ANGARA Committee on Public Works Committee on Finance JINGGOY EJERCITO ESTRADA A Committee on Public Works Committee on Public Works Committee on Finance ~RGIOOSMENA 111 Committee on Public Works Cokmiflee on Public Works Cornmilfee on Finance Comhfiltec on Finance Committee Report on HBNo.41 IS - Conversion ofNafiona1 Road in the Province of lanao Del Norte.
    [Show full text]
  • Y Region X · © Q,'("I DIVISION of LANAO DEL NORTE I 3:=Ll4 - -- J/;1/F) ------I Carangan Od Anao Deino E ------�Pj G� � � � � � �,!T�Ub� � ��
    ' ...,_ I ' •) •r ; � (, , �i�. '• I"•·• _ �t)� ,;t� l I�. -r ll�ij ·-r ,"" • ' - t1 l ;.r ' _' .,. , , r JI , � , • :;...,- l ( -�·Department of Education Jo,y Region X · © q,'("i DIVISION OF LANAO DEL NORTE I 3:=lL4 - -- J/;1/f) -------------- i carangan od anao deINo e -------�Pj g� � � � � � �,!T�ub� � ��. L� � � � � � � rt� � :..__ _________-l-- _:� ,----..J�-• J "-----"_,.-_, _.;,•�- :::.n,.:.;J,=r:lJ NOTICE OF VACANCTES MINIMUM QUALIFICATIONS POSITION No. of Selection SC/SALARY School Assignment Remarks Education Training Experience Eligibility Pos, Board Bachelor's degree in Head Teacher for I year; RA 1080 Applicant from School Elementary Education; or 40 hours of or Teacher-in-charge for (Teacher)+ Fifteen Division outside Division Principal I 19/48, 3 I 3.00 Bachelor's degree w/ 18 relevant 2 years; or Master To be detemined by SOS NQESH ( 15) HRMPSB is welcome to (Elementary) professional education training Teacher for 2 years; or Passer apply units Teacher for 5 years . Applicant from 4 hours of RA 1080 Guidance Master's Degree in Guidance I yr of relevant Division outside Division 16/36, 628.00. relevant (Guidance Division Office Coordinator Ill and Counseling experience Two( 2) HRMPSB is welcome to training Counselor) aooly. Applicant from Guidance Master's Degree in None RA 1080 Division outside Division Coun elor II 12/26. 052.00 None Required One (I) To be detcmined by SDS Guidance and Counseling Required (Guidance HRMPSB is welcome to ( HS) Counselor) apply. I. Linamon District 2. Matungao District Completion of two-year Career 3. Munai District Administrative studies in college or High 4 hours of Service (Sub- 4.
    [Show full text]
  • Indigenous Peoples' Rights in the Bangsamoro Autonomous Region
    Working for the recognition, protection and fulfillment of indigenous peoples’ rights Indigenous Peoples’ Rights in the Bangsamoro Autonomous Region Addressing potential transboundary issues in a way that respects Indigenous Peoples’ Rights in the Bangsamoro Region Working for the recognition, protection and fulfillment of indigenous peoples’ rights Maguindanao (Téduray Lambangian, Dulangan Manobo & Blaan) Bumbaran & Balabagan, Lanao Del Sur(Higaonon & Teduray) Wao, Lanao del Sur (Matigsalog, Umayamnun, Talaandig, Teduray, Blaan, Pulangyun, Tiguhanun , Manobo, Igorot & Ibatan) Indigenous Peoples in the Bangsamoro Region Working for the recognition, protection and fulfillment of indigenous peoples’ rights Working for the recognition, protection and fulfillment of indigenous peoples’ rights Working for the recognition, protection and fulfillment Proposedof indigenous peoples’ territory rights of the Bangsamoro Autonomous Region the present geographical area of 39 barangays in the Municipalities of the ARMM Kabacan, Carmen, Aleosan, Pigkawayan, Pikit, and Midsayap in 6 Municipalities in the province of North Cotabato Lanao del Norte : Baloi, Munai, Nunungan, Pantar, Tagoloan and Tangkal the Cities of Cotabato and Isabela those qualified for inclusion in the plebiscite, by way of resolution or petition Subject to plebiscite on January 2019 Part of the Philippines Working for the recognition, protection and fulfillment of indigenous peoples’ rights ANCESTRAL DOMAINS Working for the recognition, protection and fulfillment of indigenous
    [Show full text]
  • Mindanaohealth Project Program Year 6 – Quarter 3 Accomplishment Report (April 2018-June 2018)
    1 MindanaoHealth Project Program Year 6 – Quarter 3 Accomplishment Report (April 2018-June 2018) Vol. 01: Quarterly Progress Report Submitted: August 3, 2018 Submitted by: Dolores C. Castillo, MD, MPH, CESO III Chief of Party MindanaoHealth Project E-mail: [email protected] Mobile phone: 09177954307 2 On the cover: Top left: Another pregnant woman who went to the Saguiran Rural Health Unit and completed her fourth antenatal care check-up receives her dignity package and maternity kit/bag from USAID, handed over by Department of Health-ARMM’s Universal Health Care Doctor-on-Duty Dr. Baima Macadato (2nd from left). (NJulkarnain/Jhpiego) Bottom left: USAID-trained Family Planning Nurse Ruby Navales (left) talks about Family Planning to postpartum mothers. (Jhpiego) Top right: USAID-trained Family Health Associate Ailleene Jhoy Verbo uses the material/toolkit that the MindanaoHealth Project provided to FHAs to aid them in delivering correct messages and in answering questions on Family Planning from her listeners. (Photo by: Jerald Jay De Leon, Siay Rural Health Unit, Zamboanga Sibugay) Bottom right: A teen mother and now advocate of the adolescent and youth reproductive health, Shanille Blase (extreme right) expresses her gratitude to USAID Mission Director to the Philippines Lawrence Hardy II (extreme left) for USAID’s support to the Brokenshire Hospital’s Program for Teens, which provided her free antenatal, birthing and postpartum care. Also in photo: Dr. Dolores C. Castillo (second from left), MindanaoHealth Project Chief of Party. (Photos: MCossid/Jhpiego) This report was made possible by the generous support of the American people through the United States Agency for International Development (USAID), under the terms of the Cooperative Agreement AID-492-A-13-00005.
    [Show full text]
  • Response Clusters Situation Report #12 (As of 01 July 2017, 3PM)
    Response Clusters Philippines MARAWI SIEGE Situation Report #12 | 1 Situation Report #12 (as of 01 July 2017, 3PM) MARAWI SIEGE Situation Overview Emergency Observation Report: At around 1400H on 23 May 2017, a fire fight incident transpired between the Armed Forces of the Philippines (AFP) and members of the Maute Group and Bangsamoro Islamic Freedom Fighters (BIFF) who have pledged allegiance to the Islamic State of Iran and Syria (ISIS). The incident has affected all residents of Barangays Marawi Poblacion (Sarimanok Road), Basak Malutlut, Bangon, Tuca, Calocan East, Marinaut West, and Kilala of Marawi City. Residents of the city were not allowed to go out from their respective houses for security reasons. Exchange of gunfire in Barangays Tuca, Caloocan, and northern Marinaut has not stopped and roads leading to the city are being blocked both by government forces and Maute militants. REGIONAL COMMAND AND COORDINATION CENTER (RCCC): In the morning of 27 May 2017, at RED ALERT status, the First Coordination Meeting among the Marawi Siege responders was held at Tomas Cabili Gymnasium, Iligan City. In the afternoon of 27 May 2017, the RCCC of ARMM and Region X was set up at the 3rd floor of Frostie Bites, Iligan City upon national directive to have a centralized reporting and gathering of relevant information as well as efforts in responding to the prevailing situation in Marawi City through the activation of Inter-Regional Response Clusters. Likewise, the RCCC Logistics Hub was also established on this day in Iligan City. NDRRMC EMERGENCY OPERATIONS CENTER (NEOC): On 17 June 2017, the NEOC was set up in Mahogany Hills, Kaplag, Brgy.
    [Show full text]
  • Sitrep 48 NDCC Update Complex Emergency
    Members of various clusters, WASH, NUTRITION, HEALTH, FOOD, CAMP Coordination and Management in ARMM committed to regularly meet to discuss issues and concerns of IDPs The total cost of assistance extended to the IDPs is Php95.049 Million. Of this amount, Php74.982 Million was provided by the Government while Php20.067 Million was provided by NGOs, INGOs, ICRC and the UN System. Relief assistance provided were in the form of food assistance (rice and food packs); temporary shelter (construction of bunkhouses); health services (consultation and disease surveillance in ECs and provision of medicines); psychosocial services and WASH services (provision of latrines and construction of toilet facilities in evacuation sites. Intensified information, education campaign on proper hygiene; and training of volunteers in providing psychosocial support The NDCC enjoined all humanitarian actors on the grounds, both from the government and non-government organizations to continue coordinating to ensure the timely delivery of humanitarian aid to the most in need, resources are optimized and duplications/gaps are minimized The safety and security of those delivering humanitarian aid is one of the prime concerns of the Government, hence the NDCC encourage the optimization of existing coordination mechanism at all level of governance and the government cluster leads The NDCC and the Commission of Human Rights encourage the need for more information exchange between the NDCC and other humanitarian actors to improve on data collection, validation and disaggregated data for purposes of identifying further relief needs of IDPs by sex, age group and beliefs, etc. The Commission on Human Rights reported that there are no reports of sexual abuse and human trafficking in ECs DSWD deployed the Quick Response and Social Welfare and Development (QR/SWAD) teams to undertake data generation, relief distribution, operation/ management of evacuation centers, community kitchens, supplemental feeding to children, crisis counseling, etc.
    [Show full text]
  • ANNUAL ACCOMPLISHMENT REPORT January – December 2016
    TECHNICAL EDUCATION AND SKILLS DEVELOPMENT AUTHORITY LANAO NORTE NATIONAL AGRO-INDUSTRIAL SCHOOL ANNUAL ACCOMPLISHMENT REPORT January – December 2016 Introduction/Brief Profile Team LNNAIS fold sleeves in synergy for the year 2016. A year that boosts anew with a leadership that introduces for big changes in the national government and cascades down to the frontliners. Believing and supporting to the national agenda is a sure aim and automatic adaptability to institutional goals is a focused strategy in attaining and surpassing our targets as proudly presented in this report. I. TESD Policy Services LNNAIS runs first capability building program at the Inter-Franciscan Spirituality Center in Josefina, Zamboanga del Sur on March 21-23, 2016 participated by twenty-eight employees. The venue was secluded, tranquil and devoid of mundane distractions that enhances focus, reflection and enjoyment among the participants. The three-day workshop aimed at strengthening intra-office relationship and deepening work-related processes to understand the organization better and empower people with information. The gauge for effectiveness of this program is measured in the smooth attainment of all our targets throughout the year. Steadfast to support provincial operations, we hosted two Provincial Technical Education and Skills Development Committee (PTESDC) meetings on April 14, 2016 and October 14, 2016. Both meetings were nested in our Administration Office in Tubod extension campus. II.TESD Delivery Services In pursuit of servicing the training demands
    [Show full text]