Due Diligence Report – Social Safeguards

Document stage: Final Project number: 39295-013 December 2016

BAN: Third Urban Governance and Infrastructure Improvement (Sector) Project – Magura Pourashava Phase 2

Package Numbers: UGIIP-III-2/ MAGU /UT+DR/01/2016 UGIIP-III-2/ MAGU /UT+DR/02/2016 UGIIP-III-2/ MAGU /(UT+DR)/03/2016

Prepared by the Local Government Engineering Department, Government of , for the Asian Development Bank.

This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

ATTACHMENT 1: Revised DDR ON URBAN TRANSPORT & DRAIN

Sub-Project: Urban Transport + Drain

Package Numbers: UGIIP-III-2/ MAGU /UT+DR/01/2016 UGIIP-III-2/ MAGU /UT+DR/02/2016 UGIIP-III-2/ MAGU /(UT+DR)/03/2016

MAGURA POURASHAVA

DECEMBER, 2016

Prepared by: MDS Consultant, UGIIP-III

Revised Due Diligence Report – Social Safeguards

Document stage: Final Project number: 39295-013 December, 2016

BAN: Urban Governance and Infrastructure Improvement (Sector) Project (UGIIP-III) – Magura Pourashava Phase 2

Prepared by the Local Government Engineering Department, Government of Bangladesh, for the Asian Development Bank

ii Magura 2015

CURRENCY EQUIVALENTS (as of October 2016) Currency Unit = Tk. Tk1.00 = $0.0126 $1.00 = Tk. 78.95

ABBREVIATIONS ADB Asian Development Bank – AP affected person – ARIPO Acquisition and Requisition of Immovable Properties Ordinance – CCL Cash Compensation under Law – DC Deputy Commissioner –

DDR Due Diligence Report DPHE Department of Public Health Engineering –

EMP – environmental management plan FGD focus group discussion –

GICD Governance Improvement and Capacity Development

GRC – grievance redressal cell GRM grievance redress mechanism – IR involuntary resettlement – LGED Local Government Engineering Department – PDB Power Development Board – PIU project implementation unit – PMU project management office – PPTA project preparatory technical assistance – ROW right of way – RF resettlement framework – RP resettlement plan – SPS Safeguard Policy Statement – ToR terms of reference – RCC _ Reinforced Cement Concrete

_ CC Cement concrete BC _ Bituminous Carpeting

HBB _ Herring bone boned

GLOSSARY OF BANGLADESHI TERMS

I core 10 million (= 100 lakh) – Boat landing area along a river Ghat – Hat, hut, or haat – Market (bazaar) operating certain afternoons during the week when

sellers establish temporary shops. There are also some permanent shops in a Hat. Markets usually represent a significant source of

income for municipalities General strike Hartal – Khal drainage ditch/canal – Khas or khash land/property belonging to government –

Kutcha, katchha or kacca Structures built without bricks and mortar or without concrete Lakh or lac 100,000 –

Moholla or mohalla – Sub-division of a ward Mouza map Cadastral map of mouza showing plots and their numbers – Nasiman A 3-wheeler motorized vehicle – Councilor Parshad – Pourashava or Paurashava Government-recognized land area – Pucca or Puccha, puccha Structures built partly with bricks and mortar or concrete – Police station Thana – Administrative – unit below the district level. A district is called a Zila

iii

WEIGHTS AND MEASURES km – kilometer m – meter 2 m – square meter mm – Millimeter 3 m – cubic meter

NOTES (i) In this report, “$” refers to US dollars, (ii) BDT refers to Bangladeshi Taka

This social safeguard assessment- Due Diligence Report (DDR) is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. PREFACE The premises of this Due Diligence Report (DDR) are the MDS Consultant services presentation of an analysis of data and conclusions, together with its appendices. The key elements of the Due Diligence Report focus on: Assessment of Compliance Guidelines of Social Safeguards according to ADB and GoB policy. DISCLAIMER This Due Diligence Report (DDR) of Magura Pourashava under Third Urban Governance and Infrastructure Improvement (Sector) Project (UGIIP-III) has been prepared under the guidance of Team Leader and Deputy Team Leader of MDS consultant. All the data used to prepare this Due Diligence Report (DDR) have been collected from the Pourashava Development Plan (PDP). Some of the information’s have also been collected from the Pourashava personnel over telephone. Moreover some information’s have been collected by the respective experts of MDS consultant through intensive field visit which have been used in writing this report. If any information or data or any other things coincide with other project documents that are beyond our knowledge and fully coincidental event and we express apology for that.

.

iv

Table of Contents I. INTRODUCTION ...... 1 II. SUB-PROJECT DESCIPTION ...... 2 III. DUE DILIGENCE ...... 39 IV. FINDINGS ...... 42 V. FUTURE CONSULTATIONS AND DISCLOSURE ...... 66 VI. MITIGATION OF SOCIAL CONCERNS ...... 69 VII. CONCLUSIONS...... 70 VIII. APPENDIX 1:RECORDS OF PUBLIC CONSULTAION IN MAGURA POURASHAVA ...... 72 IX. Appendix 2: Involuntary Resettlement Impact Assessment Checklist (Magura Pourashava) ..... 93 X. Appendix 3: Indigenous People Check List/Small Ethnic Communities (SEC) Impacts ...... 100 XI. Appendix 4: Sample Grievance Registration Form ...... 103 XII. Appendix 5:: Land Ownership Certification of MaguraPourahsava ...... 105 XIII. Appendix - 6 : Photographs of alignments of proposed roads and drains of Magura Pourashava, Phase 2, UGIIP-III...... 106

List of Figures

Figure 1: Location Map of Magora Pourashava ...... 20 Figure 2: Map showing Proposed Roads & drains Improvement of Magora Pourashava Phase- 2 ...... 28 Figure 3: Strip Map Showing Sub-Project Roads and Drains ...... 35 Figure 4: Implementation work Schedule ...... 36 Figure 5: Typical Road, Drain sections ...... 38 Figure 6: Affected Person Grievance Redress System ...... 69

List of Tables

Table 1: Proposed Phase -2 Roads and Drain Components in Magura Pourashava ...... 3 Table 2: Assessment of Social Safeguard Impacts of Magura Pourashava Sub -Projects Package Nr: UGIIP-III-2/MAGU/(UT+DR)/01/2016/ Package Nr: UGIIP-III- 2/MAGU/(UT+DR)/02/2016 Package Nr: UGIIP-III-2/MAGU/(UT+DR)/03/2016 ...... 44 Table 3: Social Safeguards Cost Relevant to Sub-Project Implementation ...... 65

v

I. INTRODUCTION

1. The Government of Bangladesh is developing secondary towns to improve living standards, particularly in the poorer areas, and to provide an alternative destination for rural dwellers that would otherwise join the migration to larger metropolitan centres, through Third Urban Governance and Infrastructure Improvement (Sector) project (UGIIP-III). UGIIP-III is being implemented as a sector loan approach. After the successful implementation of Urban Governance and Infrastructure Improvement Projects (UGIIP I and II) in the selected Pourashavas, the Local Government Engineering Department(LGED) with the financial assistance of Asian Development Bank (ADB) have planned to implement a similar project (UGIIP-III) in pre-selected 31 Pourashavas over a period of 6 years (2014 to 2020).

2. The impact will be improved living environment tin project towns. The outcome will be improved municipal service delivery and urban governance in project towns. UGIIP-III will improve existing and provide new municipal infrastructures including (i) roads; (ii) Drainages; (iii) water supply system; (iv) solid waste management facilities; (v) slaughterhouses; (vi) markets, community centres/auditorium, bus and truck terminals and river ghats;(vii) public toilets; and (viii) others such as provision for street lighting and improvement of slums.

3. A sector-lending approach i s be ing used for the project as it has been well established and successfully practiced in the UGIIP-I and II. In accordance with ADB’s Safeguard Policy Statement (SPS), 2009 requirements a Resettlement Framework (RF) have been prepared.

4. During project preparation, resettlement plans (RPs) were prepared for 3 sample Pourashavas covering roads, drainage, kitchen market and solid waste management Sub- Projects. The RPs concluded that the project will have only temporary impacts and therefore, UGIIP-III has been categorized as resettlement Category B as per ADB SPS 2009. As a basic development principle, significant resettlement impacts (Category A type project) should be avoided to the extent possible in future Sub-Projects. For any components, the social and resettlement assessments documents will be formulated and approved by ADB before any physical activities start.

5. This Resettlement and Social Impact Assessment Report has been prepared for Roads and Drainage Improvement Sub-Project of Magura Pourashava. In Phase-2, the Pourashava has 03 (Three) Packages consist of 40 schemes (37 Nos. of roads and 03 Nos. of drains) without acquisition of land, affecting any structure and livelihood. After selection and completion of the designs of the proposed schemes, the safeguard team of the Management, Design and Supervision Consultants (MDSC) conducted resettlement and social impact assessments through thorough investigation of different social safeguard issues including land acquisition and resettlement requirements as per ADB’s Safeguard Policy Statement (SPS, 2009). The resettlement and social impact assessment report for Magura Pourashava has been prepared based on the feasibility study and detailed engineering designs.

1

6. During investigations, it was revealed that the roads and drains proposed for improvement under Packages will be implemented on the existing alignment of roads and drains and due to the improvement/ construction of the aforesaid roads are not expecting to have neither any physical nor any economic displacement of any people. As a result, there is no possibility of land acquisition and no structure affected, none found to require relocation, and consequently no involuntary resettlement (IR) impact are anticipating thus the Sub-Project is classified as Category C for IR. Under the circumstances, this report may be treated as due diligence report (DDR) with respect to social safeguard issues for the concern Sub-Project.

B. Institutional Set-up

7. The Local Government Engineering Department (LGED) and the Department of Public Health Engineering (DPHE), both under the Local Government Division (LGD) of the Ministry of Local Government, Rural Development and Cooperatives (M/O LGRD&C) and having experience in managing urban and water supply projects financed by ADB, are the executing agencies of the project. The participating Pourashavas are the implementing agencies (IAs) with a project implementation unit (PIU)) within the Pourashava structure. Implementation activities would be overseen by a Project Management Office (PMU). Management, Design and Supervision Consultants (MDSC) and Governance Improvement and Capacity Development (GICD) consultants are supposed to provide support for (i) detailed engineering design, contract documents preparation and safeguards facilitation; (ii) project management and administrative support; (iii) assistance in supervising construction; (iv) awareness raising on behavioural change activities. Safeguards officers have been appointed in PMU and PIUs and responsible to undertake day to day safeguards tasks and requirements including implementation of project’s grievance redress mechanism.

II. SUB-PROJECT DESCIPTION

8. Location: Magura Pourashava is an A class Pourashava, consists of 09 (nine) wards situated in Magura District under Division. It is bordered by on the East, Jhenidha District on the West, on the north & on the south. The area of Magura Pourashava is 44.36 sq. km. & its population is 1,14054. The river Nabaganga flows in the middle of the Pourashava.

9. The Component: To cope with the demand of increasing population in the Pourashava area, rapid development of different civic facilities for the city dwellers has now become imperative. Under the circumstances, this Sub-Project has been proposed comprising improvement/ construction of 37 roads, and 03 drains under Packages. The components of the Sub-Project, shown in Table 1 below will involve schemes (i) improvement/ construction of 47.219 KM roads length and 0.858 km drains length Table 1 shows the Sub-Project components including ownership of land.

2

Table 1: Proposed Phase -2 Roads and Drain Components in Magura Pourashava

Package –UGIIP-III-2/MAGU/UT+DR/01/2016

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) Rehabilitation & Improvement of Wazaid Ali Road by DBC ( from PART-A: Magura-  No IR impacts Jhenidha road near H/O Moniruzzaman to H/O  No requirement for Saleak, Ch.0+000 to Ch.2+350, PART-B= Link land acquisition Road at Ch.0+135 Near Soliman Hassary to R-1  Temporary Pourashava 9, 20 near H/O Soriful Islam, Ch. 0+000 to 2840.00 3.15 3.15 3.50 disturbance of Ch.0+330, PART-C= Near Abalpur Gov. Pedestrians and Primary School, Ch.0+000 to Ch.0+060, vehicle to be address PART-D=Link road From Wazed Ali road near of on the Sub-Project Water Pump House to Abalpur Mosque, E.M.P. Ch.0+000 to Ch0+100) Rehabilitation & Improvement of Abalpur  No IR impacts Purbopara Road by DBC (from PART=A:  No requirement for Wazed Ali road near H/O Sadoruddin land acquisition Khondokar to H/O Soleman Hachery via H/O R-2 Moshier Rahman Ch.0+000 to Ch.0+965,  Temporary Pourashava 11 1772.00 3.05 3.05 3.40 PART=B: Link road, at Ch.0+330, near H/O disturbance of Liton to S/O Sapon vai H/O Altab Hossen, Pedestrians and Ch.0+000 to Ch.0+515, & PART=C: Link road, vehicle to be address near H/O Altab Hossen to H/O Motiar, of on the Sub-Project Ch.0+000 to Ch.0+292) E.M.P.  No IR impacts  No requirement for Improvement of Abalpur Charpara Road by land acquisition DBC ( from PART=A: Wazad Ali road near H/O R-3 Emaroth to Abalpur Moddhoy para Eidgha,  Temporary Pourashava 3 1690.00 3.05 3.05 3.20 Ch.0+000 to Ch.1+390, PART-B= Link Road at disturbance of Ch.0+300 near Charpara Madrasha road, Pedestrians and Ch.0+000 to Ch. 0+300 ) vehicle to be address of on the Sub-Project E.M.P. 3

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm)  No IR impacts Rehabilitation & Improvement of Defulia-  No requirement for Napithpara Road by DBC ( From PART=A: land acquisition near Mozid Molla Rice Mills to near H/O R-4  Temporary Pourashava 5 Samser, Ch.0+000 to Ch.1+020, PART-B= 1250.00 3.05 3.05 3.50 disturbance of Link Road at Ch.0+737 near H/O Azaher Pedestrians and Shakh to H/O Barik Khan, Ch.0+000 to vehicle to be address Ch.0+230) of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition Rehabilitation of Sajiara Road (from Magura- R-5  Temporary Pourashava 22 Jhenidha road Sajiara Dhal to Power Gride, 1415.00 3.05 3.05 4.00 disturbance of Ch.0+000 to Ch.1+411 Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Improvement & Rehabilitation of Chotofalia  No IR impacts Road by DBC ( PART=A: from near H/O  No requirement for Kawser to near Chotofalia School Gate, Ch. land acquisition 0+000 to Ch. 0+835, PART=B: Link road Near R-6  Temporary Pourashava 6, 7, 27 Choto falia School to Dafulia Kushbaria road 1645.00 3.05 3.05 3.60 disturbance of near H/O Abdul Mozid, Ch.0+000 to Ch.0+390, Pedestrians and PART-C= Link road Near Choto falia School to vehicle to be address Dafulia Kushbaria road near H/O Nurul Islam, of on the Sub-Project Ch.0+000 to Ch.0+420) E.M.P.  No IR impacts Improvement of Kadirabad Road by DBC  No requirement for (from PART=A: Pathra more to Sattopur Union land acquisition R-7 road near H/O Anil, Ch.0+000 to Ch.0+475, Pourashava 22 575.00 3.05 3.05 3.50 PART=B: Link road at Ch.0+375 near H/O  Temporary Surjo to End of Pourashava , Ch0+000 to disturbance of Ch.0+100). Pedestrians and vehicle to be address 4

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition Rehabilation of Road by DBC from Magura- R-8 Jhenaidha road near H/O Mohor Ali to CARE  Temporary Pourashava 188 1055.00 3.05 3.05 3.50 road near H/O Sulakha via Siddik More, Ch. disturbance of 0+000 to Ch. 1+055 ) Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Rehabilatation of Doarpar road by DBC (from  No IR impacts PART=A: Magura-Sreepur road near Sonali  No requirement for Bank to Magura-Sreepur road near Doarpar land acquisition Mosque via Doarpar Girza, Ch.0+000 to R-9  Temporary Pourashava TLCC Ch.0+720, PART=B: Link road, Gourportti road 937.00 3.05 3.05 3.75 disturbance of near Sonali Bank to Rashed Salim road Sarak, Pedestrians and Ch.0+000 to Ch.0+115, PART=C: Link road, at vehicle to be address Ch.+440 near H/O Kazi Samim to near H/O of on the Sub-Project Azizul, Ch.0+000 to Ch.0+102. E.M.P.  No IR impacts  No requirement for land acquisition  The required land for Construction of road by R.C.C (from PART=A: construction work is CARE road near S/O Rama Saha to Brick owned by Magura R-10 179 & field of Baki Imam, Ch.0+000 to Ch.0+590 & Pourashava Pourashava 771.00 2.25 2.50 3.50 185 PART=B: Link road at Ch.0+420, near H/O  There is no Sabur Khan to near H/O Adv. Kallol, Ch.0+000 possibility of any to Ch.0+181), adverse impact in terms of losing income or livelihood  Temporary disturbance of 5

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) Pedestrians and vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition  The required land for construction work is owned by Magura Pourashava Improvement of Road by DBC from Magura-  There is no R-11 Sreepur Moulovi Bazar near H/O Sabbir Pourashava 162 1100.00 2.55 3.05 3.75 possibility of any Master to near H/O Lalmia, Ch.0+000 to adverse impact in terms Ch.1+100 ) of losing income or livelihood  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Rehabilitation & Construction of Road by DBC  No IR impacts & RCC (from PART=A: Nautmondir to Magura  No requirement for Sreepur road near Amtola Mosque, Ch. land acquisition 0+000 to Ch. 0+415 & PART= B: Link road, R-12  Temporary Pourashava TLCC near H/O Enseruddin to Nutmondir road near 755.00 3.05 3.05 3.50 disturbance of H/O Deno, Ch.0+000 to Ch.0+340) at Pedestrians and Niznanduali. In Ward No-07). Total vehicle to be address Length=755.00m at Niznanduali. In Ward No- of on the Sub-Project 07. Magura Pourashava, Magura. E.M.P. Improvement of Road by DBC (from  No IR impacts R-13 Pourashava TLCC PART=A: Magura-Tangakhali road near 828.00 2.25 3.05 3.50  No requirement for Hazari More to Sheikhhpara Mosque, land acquisition 6

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) Ch.0+000 to Ch.0+420, PART=B: Link  The required land for road,near H/O Humaun Police to near H/O construction work is Aktar, Ch.0+000 to Ch.0+288, PART=C:Link owned by Magura road, near H/O Sohid Mistry to near H/O Pourashava Modhu Biswas, Ch.0+000 to Ch.0+075,  There is no PART=D:Link road, near H/O Dr. Binoy to possibility of any near S/O Millon, Ch.0+000 to Ch.0+045 ) adverse impact in terms of losing income or livelihood  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for 3.900 land acquisition Conctruction of RCC drain from Hazari more (Including D-1 near Shop of Millon to Seikhpara Musque at  Temporary Pourashava 45 261 0.700mm 0.700mm drain & disturbance of Boubazar Niznanduali, (Ch.0+000 to Ch.0+261) road’s Pedestrians and width) vehicle to be address of on the Sub-Project E.M.P.

Package UGIIP-III-2/MAGU/UT+DR/02/2016 –

 No IR impacts Improvement of Moad Baria- Babur Hat Road  No requirement for by DBC from PART=A: Naran Khali Bridge to land acquisition R-1 Atharokhada near H/O Siddique, Ch.0+000 to Pourashava 154 2040.00 3.00 3.05 3.50 Ch.1+580, PART=B: Link road at Ch.0+820,  Temporary near H/O Abul Hossen to Azahar Losker, disturbance of Ch.0+000 to Ch.0+460 ). Pedestrians and vehicle to be address

7

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) of on the Sub-Project E.M.P.  No IR impacts Improvement of road Niznanduali Purbo para  No requirement for road by RCC (from PART=A: Magura- land acquisition Tangakhali road near Boubazar to Majhepara R-2  Temporary Pourashava TLCC Mondir, Ch.o+000 to Ch.0+300 & PART=B- 601.00 2.50 2.50 3.50 disturbance of Link road at Ch.0+160 , near Agragami Pedestrians and Sporting Club towards River ghate via vehicle to be address Monowar Biswas, Ch.0+000 to Ch.0+301 of on the Sub-Project E.M.P.  No IR impacts  No requirement for Rehabilitation of road by DBC from PART=A: land acquisition Molla para mosque to Bitti para more,  The required land for Ch.0+000 to Ch.0+571 & (A-1) from house Dr. construction work is Nantu to house of Manna via Munshi Para owned by Magura Idghah, Ch.0+000 to Ch.0+355, and Pourashava Construction of Road (b) Molla para mosque to  There is no R-3 house of Tarek Munshi via house of Nantu Pourashava 141, 150 1812.00 2.60 3.05 3.30 possibility of any Khan, Ch.0+000 to Ch.0+362 (C) From house adverse impact in terms of Maha Munshi to house of Photo Mollah, of losing income or Ch.0+000 to Ch.0+119 (d) From House of livelihood Rahman Member to behind Bepari para  Temporary Gorstan, Ch.0+000 to Ch.0+205, (e) Munsi disturbance of Para Gorstan road, Ch.0+000 to Ch.0+200 at Pedestrians and Parnanduali. vehicle to be address of on the Sub-Project E.M.P. Rehabilitation of road by DBC from (a) Bepari  No IR impacts para mosque to Biswas para mosque via  No requirement for R-4 Pourashava 142 house of councilor Mr.Abdul Kader Goni 710.00 3.05 3.05 3.40 land acquisition MOHON Ch. 0+000 to Ch. 0+595). Link road  Temporary (b) Ch. 0+000-0+115m, disturbance of 8

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) Pedestrians and vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for Re-hbilitation of road DBC from PART=A: land acquisition Bepari para Godown of MAZED MOLLA to R-5 Munshipar house of MURAD MUNSHI via  Temporary Pourashava 146 1334.00 3.05 3.05 3.40 BOUBAZAR and puraton kheya ghat Ch. disturbance of 0+000 to Ch. 0+962) & PART=B: from BOU Pedestrians and BAZAR to Bitti para more (Ch.0+000-0+372) vehicle to be address of on the Sub-Project E.M.P.  No IR impacts Rehabilitation of Road by DBC from Parla-  No requirement for Saddoya Road from Chaulia Bus Stand More land acquisition to Parla Purba Para Mosque via Nangta Babar R-6 101& Ashram and nearby the H/O Daud Biswas  Temporary Pourashava 2469.00 3.05 3.05 3.75 102, 112 (Ch.0.0 to 2120.0 m) with a link Road at disturbance of Ch.1550.0 m, starting from the Goalkhali More Pedestrians and to Magura - Narail Highway (Ch. 0.0 to Ch. vehicle to be address 349.0 m ). of on the Sub-Project E.M.P.  No IR impacts Improvement of Road by RCC starting from the  No requirement for front of H/O Salam Master to the Mollah para land acquisition Mosque via shop of Harun (Ch.0.00 to 503.0  The required land for m) with Link Road - 1 at Ch.160.00 m, staring construction work is from the H/O. Olier Rahaman to the Gorosthan R-7 owned by Magura Pourashava 94, 109 Road (Ch. 0.00 t o Ch.0+135.0 m, Link Road - 777.00 2.65 3.00 3.50 Pourashava 2 at Ch.217.0 m, starting from the shop of Siraj to Biman Tower Office (Ch. 0.0 to 84.0 m) Link  There is no Road-3 at Ch.438m from nearby the H/O Iub possibility of any Ali to nearby the H/O Kazol Molla( Ch. 0.0 to adverse impact in terms 55.0 m ) of losing income or livelihood 9

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm)  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Construction of Mollapara Road by R.C.C  No IR impacts (from PART=A: Gorstan road near H/O Roise  No requirement for Shekh to Mollapara road near H/O Tazrul via land acquisition near H/O Mukti, Ch.0+000 to Ch.0+306, R-8  Temporary Pourashava 107 PART=B: Link road at Ch.0+ 065 near H/O 571.00 2.50 2.50 3.60 disturbance of Ahmmed Hossen to near H/O Mukt, Ch.0+000 Pedestrians and to Ch.0+225, PART=C, Link road at vehicle to be address Ch.0+151 toward near H/O Liton , Ch.0+000 of on the Sub-Project to Ch.0+040, ) E.M.P.  No IR impacts  No requirement for land acquisition  The required land for construction work is owned by Magura Improvement of Kukna Road by DBC (from Pourashava PART=A: Kukna road near H/O Pritos to near H/O Siraz Chairman, Ch.0+000 to  There is no R-9 Pourashava 36 Ch.1+450, PART=B: Link road, near Kukna 1530.00 2.50 3.05 3.40 possibility of any Uttarpara Mosque, Ch.0+000 to Ch.0+015, adverse impact in terms PART=C: Link road, near H/O Aziz to near of losing income or H/O Azahar, Ch.0+000 to Ch.0+065 ), livelihood  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P.

10

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) Construction of West Stadiumpara RCC Road  No IR impacts ( from PART=A: near H/O Ebadot to Asia  No requirement for Mohila College road via near H/O Delowar Sir, land acquisition Ch.0+000 to Ch.0+720, PART=B: Link Road R-10  Temporary Pourashava 41 towards near H/O Eng. Abdur Rahim, 945.00 2.50 2.50 3.00 disturbance of Ch.0+000 to Ch.0+150 & PART=C: Link Road Pedestrians and towards near H/O Tahazzat, Ch.0+000 to vehicle to be address Ch.0+075) of on the Sub-Project E.M.P. Re-habilitation & Improvement of Vitasair- Ghoramara road by DBC ( from PART=A:  No IR impacts Magura- Road near Vitasair Dal to end  No requirement for of Pourashava near Perfect School, Ch. 0+00 land acquisition m to Ch. 2+572, PART=B: Link road: Vitsir R-11  Temporary Pourashava 64 Primary School to Magura-Jessore road near 3393.00 3.05 3.05 3.50 disturbance of S/O Jahangir Ch. 0+00 m to Ch. 0+610 , Pedestrians and PART=C: Link road: near H/O Awal to near vehicle to be address H/O Abdur Rouf, Ch. 0+00 m to Ch. 0+211). of on the Sub-Project E.M.P.

 No IR impacts  No requirement for land acquisition 3.800  Temporary Conctruction of RCC drain from H/O Akbar to (Including D-1 disturbance of Pourashava TLCC existing Drain (Ch.0+000 to Ch.0+117) at 117 0.650mm 0.650mm drain & Pedestrians and Niznanduali road’s vehicle to be address width) of on the Sub-Project E.M.P.

Package –UGIIP-III-2/MAGU/UT+DR/03/2016

11

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm)  No IR impacts  No requirement for Rehabilitation of Laxmikandor road by DBC land acquisition (from PART= A: Magura- road near S/O R-1 Amoresh to Magura -Dhaka road near S/O  Temporary Pourashava 136 1410.00 3.05 3.05 4.00 Aslam, Ch.0+000 to Ch.1+260 & , PART=B: disturbance of Link road at Ch.0+430 near H/O Apan to near Pedestrians and H/O Komoles, Ch.0+000 to Ch0+150) vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition  The required land for Improvement of connecting Roads by DBC construction work is starting from Nut Mondir Road to Magura - owned by Magura Sreepur Road RHD Road) at different Pourashava Chainages, Part (A): From near by the H/O  There is no R-2 Shunil to near by H/O Pachu (Ch.0.0 to Pourashava TLCC 1161.00 2.50 3.05 3.75 possibility of any Ch.310.0 m) Part B : From near by the H/O adverse impact in terms Poritosh to near H/O Jenna via A.N.Sommiloni of losing income or Girls School , (Ch. 0.0 to Ch. 385.0 m ) & Part livelihood C : From nearby the H/O Liton to nearby H/O  Temporary Rashed Sheikh ( Ch.0.0 to Ch. 466.0 m ) disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Rehabilitation of Borunatail road by DBC (  No IR impacts from PART= A: Magura-Dhaka road near Bus-  No requirement for Terminal to Magura -Mohammadpur road near land acquisition R-3 Pourashava 138 H/O Salam Member, Ch.0+000 to Ch.0+740 & 1590.00 3.05 3.05 3.60  Temporary , PART=B: Link road at Ch.0+150 near H/O disturbance of Habibur Rahman to Mohammadpur road near Pedestrians and Vashani Sreeti Sangha, Ch.0+000 to Ch0+850) vehicle to be address 12

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) of on the Sub-Project E.M.P.  No IR impacts  No requirement for Re-hbilitation & Construction of Collage para land acquisition road by DBC & RCC (PART=A: near H/O R-4 AKBAR CHAIRMAN to Hazi Abdul Hamid road  Temporary Pourashava TLCC 759.00 3.05/2.50 3.05/2.50 3.55 near Govt.Library, Ch. 0+000 to 0+467 & disturbance of PART=B: Link Road, near H/O AKKAS ALI to Pedestrians and near H/O MANNU Sir.Ch. 0+000 to 0+292) vehicle to be address of on the Sub-Project E.M.P. Improvement of College Para road (Part:A : Kesob more to College para near H/O Kalam  No IR impacts via nearby H/O. Chandu Commissioner,  No requirement for ch.0+000 to Ch.0+500, Part: B Link road, land acquisition nearby Abu Bakkar to nearby H/O. Mozid R-5 223 &  Temporary Pourashava Nayeb, ch.0+000 to Ch.0+185, Part: C : Kesob 1483.00 3.05 3.05 3.40 225 disturbance of more to Habibur Rahman road to H/o. Pedestrians and Mahabub Sir, ch.0+000 to Ch.0+443 & Part: vehicle to be address D : Mahabub Sir to near H/O. of on the Sub-Project Boloram,ch.0+000 to Ch.0+355, E.M.P.

 No IR impacts  No requirement for land acquisition Rehabilitation & Improvement of Road from  The required land for PART-A: Magura-Jhenidha road near H/O construction work is R-6 Azgar Ali to Wazad Ali road near H/O Foru owned by Magura Pourashava 12 1035.00 2.40 3.05 3.30 Biswas, Ch.0+000 to Ch.0+840, PART-B= Link Pourashava Road at Ch.0+135 Near H/O Mozahar to near  There is no H/O Nazrul, Ch. 0+000 to Ch.0+195) possibility of any adverse impact in terms of losing income or livelihood

13

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm)  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition Rehabilitation of Abalpur Khondokarpara Road R-7 by DBC from Wazed ali road near Mirer  Temporary Pourashava 18 715.00 3.05 3.05 3.20 Battola to near H/O Solaman Khondokar disturbance of Ch.0+000 to Ch.0+715 Pedestrians and vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition R-8 Rehabilitation of Road from Mirar Battola to  Temporary Pourashava TLCC 571.00 3.05 3.05 3.60 Darua Bridge , Ch0+000 to Ch.0+571). disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Construction of Dori Magura Kalkalia para  No IR impacts road by RCC (from Shibrampur road near  No requirement for

H/O Babul Shakh to near H/O Sattik Master, land acquisition Ch.0+000 to Ch.0+210, PART=B, Link road at  The required land for R-9 Ch.0+120 near H/O Gourango Saha to CARE construction work is Pourashava 178 1.95 2.50 3.50 road near H/O Sorap, Ch.0+000 to Ch.0+210, owned by Magura

PART=C, CARE road near Santoz Datter Pourashava Ambagan to Shibrampur road near H/O  There is no Prokash, Ch.0+000 to Ch.0+330 & PART=D, possibility of any Link Road at Ch.0+240 near H/O Deven adverse impact in terms 14

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) Biswas towards near H/O Biren Nayeb, of losing income or Ch.0+000 to Ch.0+060) livelihood 810  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P.  No IR impacts  No requirement for land acquisition  The required land for construction work is owned by Magura Improvement of Road by DBC ( from PART- Pourashava A= Magura-Sreepur road near H/O Emdadul  There is no R-10 169 & to near H/O Hakim Biswas, Ch.0+000 to Pourashava 710.00 2.10 3.05 3.60 possibility of any 170 Ch.0+410 & ,PART=B:Link road near H/O adverse impact in terms Zahidul to Future School , Ch. 0+000 to Ch. of losing income or 0+300)at Niznanduali. livelihood  Temporary disturbance of Pedestrians and vehicle to be address of on the Sub-Project E.M.P. Rehabilitation & Construction of Tati Para  No IR impacts Road Part A : Starting from Abu Ishaq Road  No requirement for near shop of Salauddin Moulavi to Norail Road land acquisition R-11 96, 110 near H/O Arad Mollah, Ch. 0.0 to Ch.165.0 m Pourashava 735.00 3.05/2.00 3.05/2.50 3.70 & 111 with link Road Part B : Starting from Ch. 55.0  Temporary m nrarby the H/O Dr. Sakir to Norail Road near disturbance of the H/O Salam, Ch.0.0 to Ch.240.0 m, Part C : Pedestrians and By link starting from the Ch.210.0 m of part B vehicle to be address

15

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm) to Tati Para RCC Road, Ch.0.0 to Ch.160.0 m, of on the Sub-Project Part D: By link from Ch. 20.0 m of Part C to E.M.P. Tanti Para RCC Road near H/O Ratan, Ch. 0.0 to Ch. 130.0 m, Part E : By link from Ch. 42.0 m of part-C near Tanti Para Mosque to Norail Road, Ch. 0.0 to Ch. 40.0 m Improvement of Khalkul Para Road by  No IR impacts Bituminous Dense Carpeting from Moulavir  No requirement for Garrage to nearby the H/O Satter Miah (Ch. land acquisition 0.0 to Ch. 0+ 661.o m) with link Road - 1 at Ch. R-12  Temporary Pourashava 97 & 98 223.0 m ( Ch0.0 to Ch.292.0 m ), link Road 1695.00 3.05/2.50 3.05/2.50 3.40 disturbance of 1(1) at Ch. 25.0 m ( Ch. 0.0 to Ch.415.0 m), Pedestrians and Link Road 1(2) at Ch.320.0 m (Ch. 0.0 + 151.0 vehicle to be address m), Link Road - 2 with Beltola Road at of on the Sub-Project Ch.285.0 m (Ch.0.0 to Ch. 0+ 176.0 m ) E.M.P.  No IR impacts  No requirement for land acquisition Rehabilatation & Construction of Vaina  The required land for Santibag Road by DBC & RCC (from PART=A: construction work is Magura -Jessore road near near H/O Nazrul to owned by Magura Gorstan road near H/O Abu-Zel Via Shakhpara Pourashava Jame Mosque, Ch.0+000 to Ch.1+255,  There is no R-13 PART=B: Link road Ch.0+420 to Near H/O Pourashava 92 1730.00 1.80 2.50 3.00 possibility of any Serzent Mosiur, Ch.0+000 to Ch.0+100, adverse impact in terms PART=C: Link road, near H/O Kamal Sheikh of losing income or to Sheikhpara Baitus Salahen Jame Mosque, livelihood Ch.0+000 to Ch.0+325, PART=D: Link road,  Temporary near H/O Eshak to H/O Awal, Ch.0+000 to disturbance of Ch.0+050), Pedestrians and vehicle to be address of on the Sub-Project E.M.P.

16

Existing Proposed Full Width PDP No Possible Social Impact Land Sl. Sub-Project Schemes (Description) Length (m) width width (m/mm) / IR impact Ownership No. (m/mm)  No IR impacts  No requirement for 3.900 land acquisition Conctruction of RCC drain from Bus-Tereminal (Including D-1 to Box Culvert of 3 No Halot at Parnanduali  Temporary Pourashava TLCC 480 0.700mm 0.700mm drain& disturbance of (Ch.0+000 to Ch.0+480) road’s Pedestrians and width) vehicle to be address of on the Sub-Project E.M.P.

17

10. The Sub-Project went through the process of meeting the selection criteria (general and technical), environmental and social safeguard screening and conforming to the municipal infrastructure development plan (PDP) and drainage master plan prepared for in UGIIP-II. Locations and sitting of the proposed infrastructures considered: (i) locating components on government-owned land and/or within existing right-of-way (ROW) to reduce acquisition of land, (II)prioritizing rehabilitation/ improvement over new construction; (IIi) taking all possible measures in design and selection of sites to avoid resettlement impacts; (iv) avoiding where possible locations that will result in destruction/disturbance to historical and cultural places/values; (v)avoiding tree-cutting where possible; and (vi) ensuring all planning and design interventions and decisions are made in consultation with local communities and reflecting inputs from public consultation and disclosure for site selection.

11. The components of the Sub-Project seek to upgrade and expand the urban services. The roads and drains are located in different wards of the Pourashava. The proposal is concerned with activities, which address the most acute needs for better urban services and facilities to inhabitants of the town/Pourashava. Figure 1 shows the location of Magura Pourashava and Figure 2 shows the location of Sub-Project’s schemes alignment of roads and drains proposed under the Sub-Project. No road needs resettlement, replacement or relocation. Strip diagrams of roads and drains are given as sample in Figures 3.

12. The roads proposed are all existing internal service roads. Most of the roads are lower than the houses beside them. So, water from houses flow over the roads and as a result, the roads damage. There are low lying areas and ditches by the side of many roads needing retaining walls for protection of road embankments including shoulders. The Pourashava is subjected to flood. All the roads will be improved by Dens bituminous carpeting (DBC) CC& RCC.

13. The Sub-Project contains drains to be constructed along the edge of the roads. All the drains will be constructed with RCC. 14. Appendix-06 provides photographs of proposed road and drains alignments of Magura Pourashava under Phase 2 of UGIIP-III.

15. Implementation Schedule. Substantial time is required spanning the continuum of Sub-Project preparation, approval, survey, design & estimate, contract award and contract execution. Efforts need to be made to follow the schedule of timely implementation of work. Normally the construction work season in Bangladesh runs from October through May (eight months). The Construction works are sometimes impeded for the following reasons:

 Early floods in April/May,  Late floods in September/October,

 Natural calamities (cyclone/tornado, excessive floods) occur in April/May and October/November.

18

16. Normally, the best construction period is only for 6 months a year (October to March). The construction period is sometimes squeezed to 4 months due to natural calamities. However, sometimes, based on time constraint or expediency, construction work may even need to be carried out in the monsoon. Whenever possible, parallel activities can be implemented and consequently, quantum of work can be maximized through efficient planning and adoption of best available practices.

17. Considering the above facts, it has been estimated that the implementation of phase 2 roads and drains of Magura Pourashava will cover 12-months period, and major works are advisable to take place between November, 2016 and November, 2017. A tentative time- schedule for implementation (only as an indication) is shown in Figure 4 below for period July, 2016 to December 2017 and Figure- 5 shows the typical cross sections of roads and drains.

19

Magura P.S.

Figure 1: Location Map of Magura Pourashava

20

Location of Magura Pourashva office in Google Map.

21

22

Map of Magura pourashava Showing Schemes and ward Boundaries (Roads)

23

Map of Magura pourashava Showing Schemes and ward Boundaries (Drains)

24

25

Map of Magura pourashava Showing Schemes and ward Boundaries (Roads)

Map of Magura pourashava Showing Schemes and ward Boundaries (Drains)

26

Map of Magura pourashava Showing Schemes and ward Boundaries (Roads)

Map of Magura pourashava Showing Schemes and ward Boundaries (Drains)

27

Map of Magura pourashava Showing Schemes and ward Boundaries ( Roads)

Map of Magura pourashava Showing Schemes and ward Boundaries (Drains) Figure 2: Map showing Proposed Roads & drains Improvement of Magura

28

Strip map of Road

29

Strip map of Road

30

Strip map of Road

31

Strip map of Road

32

Strip map of Drain

33

Strip map of Drain

34

Strip map of Drain

Figure 3: Strip Map Showing Sub-Project Roads and Drains

35

Period : June 2016 – December 2017 Item of Works 2016 2017 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 Assessment of the Sub-project

Supported by field visit

Compliance of Sub-project and approval

Preparation and approval of sub- projects

--- Preparation of the bid documents

-----Tendering of the sub-project

Evaluation of Tender and Work Order

Execution of physical Work

Final inspection and certification

Figure 4: Implementation work Schedule

36

DDd dd

Typical Road Sections (Bituminous Carpeting Road)

Typical Road Sections (Concrete Road)

37

DDd dd

Typical Drain Cross Section

Figure 5: Typical Road, Drain sections

38

DDd dd

III. DUE DILIGENCE

A. Objectives of the Study/ Investigation

18. This Social Impact Assessment Report/ Due Diligence Report has been prepared to meet the following objectives:  Thorough assessment of social safeguard issues and impacts. The major objective of the above study/ investigations was to assess and identify all the possible socioeconomic and resettlement impacts including impacts on women, poor and vulnerable.  To plan to avoid, minimize, mitigate or compensate for the potential adverse impact.  To describe the extent of land acquisition and involuntary resettlement impacts.  To inform and consult the affected people to make them aware about the project activities and take feedback to prepare safeguard plans summarizing mitigation measures, monitoring program/ mechanism, institutional arrangement and presenting budget for resettlement.  to describe the likely economic impacts and identified livelihood risks of the proposed project components;  to describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation;  to establish a framework for grievance redress mechanism for affected person (APs)  to describe the applicable national and local legal framework for the project, and define the IR policy principles applicable to the project;  to define entitlements of affected persons, and assistance and benefits available under the project;

B. Methodology used for Assessing Land Acquisition and Resettlement

19. Data collection. Necessary data regarding social, economic and gender information has been collected primarily through desk work, field visits to the proposed Sub-Projects item and one-on-one interviews with stakeholders.

20. Stakeholders and public consultations. Comprehensive discussions with MDSC consultants, Magura Pourashava officials, community people living near by the proposed Sub- Projects schemes, public representatives and other stakeholders to identify different issues, problems/ constraints and prospects and feedback from the participants in connection to roads

39

DDd dd

and drains construction under the Sub-Project. The consultation covers mainly information dissemination about the project/ Sub-Project and its scope, possible positive and negative impacts, involvement of local people in different activities of the project and employment in project works, etc. The public participation process included (i) identifying interested parties (stakeholders); (ii) information and providing the stakeholders with sufficient background and technical information regarding the proposed development; (iii) creating opportunities and mechanisms whereby they can participate and raise their views (issues, comments and concerns) with regard to the proposed development; (iv) giving the stakeholders feedback on process findings and recommendations; and (v) ensuring compliance to process requirements with regards to the environmental and related legislations.

21. The safeguard team of MDSC Visited Magura Pourashava From 17th August 2016 to 18th August 2016 and have a meeting with, Executive Engineer, councillors, Assistant Engineer, M.E, community local public representatives and different stakeholders at Pourashava office and at Sub-Project areas with local people, community leaders and local government representatives. Mayor of the Pourashava welcomed the team and stated ensuring all cooperation for investigation & data collection. During field visits, the consultants investigated about the existing condition of the roads and drainage alignments and emphasized on the issues like land acquisition, resettlement and rehabilitation., grievance redress mechanism and so on. The participants were also informed of the Sub-Project cut-off date of 30TH September 2016 (date of completion of census survey). The consultant team also talked to the local people living nearby the Sub-Project and nobody found affected. The required land for construction work is owned by Magura Pourashava and nobody found affected.

22. Relevant consultants and Pourashava officials arranged meetings at Pourashava office and different locations nearby subprojects. Four formal meetings were arranged by the Pourashava officials with the stakeholders. The meeting sites were at Parla uttar para (ward-04), Abalpur Mirer Bottola (ward-01) and Moulobi Bazer (ward-07) Doarpar shop of Rampodo saha (ward-08), at Magura Pourashava. About 60 participants were present in the consultation meeting. The subprojects are related to improvement, rehabilitation and reconstruction of roads and drains. There is no possibility of any adverse impact in terms of losing income or livelihood. Local residents, pedestrians who might be disturbed during construction work, community leaders and other stakeholders were also consulted through group meetings and one on one meeting. The subprojects are intensively visited to verify the likely impacts on the people with respect to land acquisition & resettlement, and other social safeguard issues. During site visits, concern Pourashava Assistant Engineer, Sub-Assistant Engineer, and a Surveyor accompanied by the consultants to assist identifying the locations of the roads & drains alignments. The Pourashava officials also facilitated to organizing consultations/ meetings.

23. During consultations and field visits, the issues and concerns raised were addressed by the Pourashava officials and MDSC safeguard team by informing the participants mainly that as per detailed designs private land would not be required. However, if in the course of Sub-Project implementation private land is needed to be acquired / purchased then the entitlement of the affected persons will follow the RF which has been developed based on government rules & laws and ADB safeguard policy. The participants were also informed that there would be no tree cutting, relocation of business, and mobile vendors/hawkers as the improvement works would be

40

DDd dd

done on the existing ROWs. The pedestrian safety would be taken care of by the contractors during construction period by providing alternate roads, safety signs & boards, and providing speed breakers where required. Moreover, mitigation measures as specified in EMPs would also be implemented by the contractors which would be closely supervised by the Pourashava officials and consultants. The participants were also informed that there would be local employment opportunity for skilled and unskilled labourers. Participation of women would be highly encouraged.

24. During discussions, the local people mentioned about the insufficiency of civic facilities, conditions of existing roads and coverage of drainage facilities, etc. The people expressed their happiness for getting project assistance for improvement of the Pourashava facilities. The roads and drain proposed under the Sub-Project were a long demand of the people of the Pourashava. The records of public consultations have been shown in Appendix-1.

25. Transect walks. The MDSC Regional Resettlement Specialist together with Magura Pourashava engineering staff conducted transect walks during June- August 2015 to do rapid appraisal of the proposed locations and alignments of Sub-Projects using a standard IR checklist annexed with this report as Appendix-2.

26. Reconnaissance Survey. The project social safe guard team (MDSC) visited Magura Pourashava during April -June 2016 to measure the widths of proposed roads and drains under Packages count the number of trees, structures, natural resources, mobile vendors/ hawkers, and other facilities, etc. along ROWs, conduct informal discussions with local communities, formal discussions with Pourashava engineers, and visual assessment of IR impacts. The output of the survey was discussed with the design engineers of the project to incorporate into the designs to minimize the IR impacts (if any).

27. Census of affected persons and inventory of affected assets. As nobody was found who may be affected by the sub-project activities, no structures to be removed/ relocated/demolished the census was not required. However, the social safeguard team found mobile hawkers/vendors within ROW who have been informed about the construction work to be implemented by Pourashava.

28. Social Safeguard Unit of MDSC, UGIIP-III has verified the roads and drains through the questionnaire that is titled” Initial Evaluation Assessment Format”. Through this format, the team members have organized consultation with users and gathered feedback on the sub projects. Finally, it has been concluded that there is no impacts on involuntary resettlement. scope of involuntary resettlement thus no impact would be occurred.

.

41

IV. FINDINGS

29. Involuntary Resettlement. As per results of the data gathering, detailed survey of the sites and alignments together with review of land records, the Sub-Project is considered as Category C, i.e., the Sub-Project does not require temporary or permanent land acquisition, and there are no impacts involving the loss of land, structures, crops and trees, businesses or income.

30. All roads components, drains under Packages will be used for construction work is duly owned by Pourashava itself. The character of the subprojects is improvement on existing roads. No new road construction or change of alignment would be involved in the subprojects. There are sufficient land within the ROWs required for widening the proposed roads and construction drains as mentioned in Table-1. MDSC together with PMU has confirmed ownership and land records of Magura Pourashava of the existing road and drain required widths in the ROWs therefore no land acquisition is required. Land ownership certificate is shown in Appendix-5.

31. In Phase-2, Magura Pourashava has 03 (Three) Packages consist of 40 schemes (37 Nos. of roads and 03 Nos. of drains). The road schemes have been proposed for rehabilitation that would be implemented as improvement in the existing ROW and 03 Nos. of drains would be constructed in the existing damaged drains. All drains’ outfalls are connected to the river Nabaganga & the natural cannels.

32. The Social Safeguard Unit of MDSC for UGIIP-III further verified and checked the roads and drains through the questionnaire that is titled “Initial Evaluation Assessment Format”. Through this format, the team members have organized consultation with the sub-project users and gathered feedback on the sub-projects. There are no encroachers and squatters found but some mobile vendors and hawkers along the proposed roads and drains ROWs are found. They are noticed about the development works have been taken up by the Pourashava and they have given their consent to move to other suitable places. For recording and documentation purposes, the following are the socio-economic information and profile of survey participants.

(i) no BPLs along the proposed drain and roads alignments sites (ii) no indigenous people (IP) along roads and drain alignments sites

33. There is sufficient space along the ROWs for staging area, construction equipment, and stockpiling of materials. Besides, there is no possibility of affecting any structure needing relocation by the Sub-Project activities as per detailed design of the components. Moreover, there is no possibility of loss of livelihood, neither permanent nor temporary due to loss of land/ assets occupied or squatting by anybody, is expected for the proposed development. Therefore, the potential impact of the Sub-Project on privately owned land/ assets has been fully eliminated, and correspondingly, no issues relating to involuntary resettlement will occur during implementation of the Sub-Project. Thus, it has been concluded that there is no IR impact and the Sub-Project is classified as Category C for IR.

34. Since full road closures are not expected during construction, it might be occurred to halt movement of pedestrians and vehicles during the road construction and curing in relatively narrower roads to divert vehicles and pedestrians towards the alternative roads/ pathways. There are several roads in the locality. While a road is in full closure, there are others roads to be used. Digging of road and drain also interrupt pedestrians accessing their home/shop along-side the ROW. The contractors/authority have already been addressed the issue and redressing the grievances using alternative roads. Showing signboard for using alternative roads, deploying 42

persons, setting steel/wooden platform for helping vehicles and pedestrians to go on to the destination or another road are means for mitigating the problem.

35. Residents and businesses along the sub-project sites may experience temporary impacts such as increased noise, vibration, dust and restriction of vehicles movement during construction phase which can be mitigated through good construction practices as documented in the sub- project’s initial environmental examination (IEE) report and environmental management plan (EMP). However, the construction/improvement of the sub-project components may cause minor temporary disturbances limited to dust and noise, movement of people, etc. which will be limited to the construction period only, and can easily be mitigated by quick and timely completion of works, taking dust suppression measures, removal of debris regularly, providing alternate roads and access to houses during construction, erecting different road furniture where required, to make the vehicular movement safe and to minimize road accidents. For mitigating noise pollution, brick crushing yards, bituminous hot mix plants and concrete batching plants shall be located sufficiently away from habitation. Workers at the vicinity of strong noise shall wear earplugs.

36. Table-2 summarizes the findings of the data collection, field visits and surveys. If in the course of Sub-Project implementation land will be required and stakeholders are willing to donate any land, donation procedures will follow the RF and to be endorsed by an independent third party evaluator (e.g., civil society and non-ex officio representatives of the TLCC) to ensure there is no significant social and economic impact due to land donation.

43

Table 2: Assessment of Social Safeguard Impacts of Magura Pourashava Sub -Projects Package Nr: UGIIP-III-2/MAGU/(UT+DR)/01/2016/ Package Nr: UGIIP-III-2/MAGU/(UT+DR)/02/2016 Package Nr: UGIIP-III-2/MAGU/(UT+DR)/03/2016

Package Nr: UGIIP-III-2/MAGU/(UT+DR)/02/2016

44

PDP Type of NO/ Name of Resettlement Indigenous Sub-Project Schemes loss/ Possible social Impact Remarks NO Scheme Aps required or not people Affected no Rehabilitation & Improvement of Wazaid Ali Road by DBC ( from  No IR impacts PART-A: Magura-  No requirement for Jhenidha road near H/O land acquisition Moniruzzaman to H/O  The required land for Temporary Saleak, Ch.0+000 to construction work is disturbance of Ch.2+350, PART-B= owned by Magura Link Road at Ch.0+135 Pedestrians and Pourashava Near Soliman Hassary vehicles to be R-1 to near H/O Soriful No loss Not  There is no possibility addressed in the 9, 20 of any adverse impact in Not required Not found Islam, Ch. 0+000 to applicable applicable subproject terms of losing income Ch.0+330, PART-C= environmental Near Abalpur Gov. or livelihood management plan Primary School,  Temporary Ch.0+000 to Ch.0+060, disturbance for (EMP) PART-D=Link road pedestrians and From Wazed Ali road movement of vehicles to near Water Pump be addressed in the House to Abalpur Sub-project E.M.P. Mosque, Ch.0+000 to Ch0+100) Rehabilitation & Improvement of  No IR impacts Abalpur Purbopara  No requirement for Road by DBC (from land acquisition Temporary PART=A: Wazed Ali  The required land for disturbance of road near H/O construction work is Pedestrians and Sadoruddin Khondokar owned by Magura vehicles to be to H/O Soleman Pourashava R-2 No loss Not addressed in the 11 Hachery via H/O  There is no possibility Not required Not found applicable applicable subproject Moshier Rahman of any adverse impact in Ch.0+000 to Ch.0+965, terms of losing income environmental PART=B: Link road, at or livelihood management plan Ch.0+330, near H/O  Temporary (EMP) Liton to S/O Sapon disturbance for vai H/O Altab Hossen, pedestrians and Ch.0+000 to Ch.0+515, movement of vehicles to & PART=C: Link road, 45

near H/O Altab Hossen be addressed in the to H/O Motiar, Sub-project E.M.P. Ch.0+000 to Ch.0+292)

 No IR impacts  No requirement for Improvement of land acquisition Abalpur Charpara  The required land for Temporary Road by DBC ( from construction work is disturbance of PART=A: Wazad Ali owned by Magura Pedestrians and road near H/O Emaroth Pourashava vehicles to be to Abalpur Moddhoy R-3 No loss Not  There is no possibility addressed in the 3 para Eidgha, Ch.0+000 of any adverse impact in Not required Not found applicable applicable subproject to Ch.1+390, PART-B= terms of losing income Link Road at Ch.0+300 or livelihood environmental near Charpara  Temporary management plan Madrasha road, disturbance for (EMP) Ch.0+000 to Ch. 0+300 pedestrians and ) movement of vehicles to be addressed in the Sub-project E.M.P.  No IR impacts Rehabilitation &  No requirement for Improvement of land acquisition Temporary Defulia- Napithpara  The required land for disturbance of Road by DBC (from construction work is Pedestrians and PART=A: near Mozid owned by Magura vehicles to be Molla Rice Mills to Pourashava R-4 No loss Not addressed in the 5 near H/O Samser,  There is no possibility Not required Not found applicable applicable subproject Ch.0+000 to Ch.1+020, of any adverse impact in PART-B= Link Road at terms of losing income environmental Ch.0+737 near H/O or livelihood management plan Azaher Shakh to H/O  Temporary (EMP) Barik Khan, Ch.0+000 disturbance for to Ch.0+230) pedestrians and movement of vehicles to 46

be addressed in the Sub-project E.M.P.  No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of owned by Magura Rehabilitation of Pedestrians and Pourashava Sajiara Road (from vehicles to be R-5 Magura- Jhenidha road No loss Not  There is no possibility addressed in the 22 of any adverse impact in Not required Not found Sajiara Dhal to Power applicable applicable subproject terms of losing income Gride, Ch.0+000 to environmental Ch.1+411 or livelihood  Temporary management plan disturbance for (EMP) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P. Improvement & Rehabilitation of  No IR impacts Chotofalia Road by  No requirement for DBC ( PART=A: from land acquisition near H/O Kawser to  The required land for Temporary near Chotofalia School construction work is disturbance of Gate, Ch. 0+000 to Ch. owned by Magura Pedestrians and 0+835, PART=B: Link Pourashava vehicles to be road Near Choto falia R-6 No loss Not  There is no possibility addressed in the 6, 7, 27 School to Dafulia of any adverse impact in Not required Not found applicable applicable subproject Kushbaria road near terms of losing income H/O Abdul Mozid, or livelihood environmental Ch.0+000 to Ch.0+390,  Temporary management plan PART-C= Link road disturbance for (EMP) Near Choto falia School pedestrians and to Dafulia Kushbaria movement of vehicles to road near H/O Nurul be addressed in the Islam, Ch.0+000 to Sub-project E.M.P. Ch.0+420)

47

 No IR impacts  No requirement for land acquisition Improvement of  The required land for Temporary Kadirabad Road by construction work is disturbance of DBC (from PART=A: owned by Magura Pedestrians and Pathra more to Sattopur Pourashava vehicles to be Union road near H/O R-7 No loss Not  There is no possibility addressed in the 22 Anil, Ch.0+000 to of any adverse impact in Not required Not found applicable applicable subproject Ch.0+475, PART=B: terms of losing income Link road at Ch.0+375 or livelihood environmental near H/O Surjo to End  Temporary management plan of Pourashava , disturbance for (EMP) Ch0+000 to Ch.0+100). pedestrians and movement of vehicles to be addressed of on the Sub-project E.M.P.  No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of Rehabilitation of Road owned by Magura by DBC from Magura- Pedestrians and Pourashava Jhenaidha road near vehicles to be R-8 H/O Mohor Ali to No loss Not  There is no possibility addressed in the 188 of any adverse impact in Not required Not found CARE road near H/O applicable applicable subproject terms of losing income Sulakha via Siddik environmental More, Ch. 0+000 to Ch. or livelihood management plan 1+055)  Temporary disturbance for (EMP) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P.

48

Rehabilitation of Doarpar road by DBC  No IR impacts (from PART=A:  No requirement for Magura-Sreepur road land acquisition near Sonali Bank to  The required land for Temporary Magura-Sreepur road construction work is disturbance of near Doarpar Mosque owned by Magura Pedestrians and via Doarpar Girza, Pourashava vehicles to be Ch.0+000 to Ch.0+720, R-9 No loss Not  There is no possibility addressed in the TLCC PART=B: Link road, of any adverse impact in Not required Not found applicable applicable subproject Gourportti road near terms of losing income Sonali Bank to Rashed or livelihood environmental Salim road Sarak,  Temporary management plan Ch.0+000 to Ch.0+115, disturbance for (EMP) PART=C: Link road, at pedestrians and Ch.+440 near H/O Kazi movement of vehicles to Samim to near H/O be addressed in the Azizul, Ch.0+000 to Sub-project E.M.P. Ch.0+102.  No IR impacts  No requirement for land acquisition Construction of road by  The required land for Temporary R.C.C ( from PART=A: construction work is disturbance of CARE road near S/O owned by Magura Pedestrians and Rama Saha to Brick Pourashava vehicles to be field of Baki Imam, R-10 179 & No loss Not  There is no possibility addressed in the Ch.0+000 to Ch.0+590 of any adverse impact in Not required Not found 185 applicable applicable subproject & PART=B: Link road at terms of losing income Ch.0+420, near H/O or livelihood environmental Sabur Khan to near H/O  Temporary management plan Adv. Kallol, Ch.0+000 to disturbance for (EMP) Ch.0+181), pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P.

49

 No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of owned by Magura Improvement of Road Pourashava Pedestrians and by DBC from Magura- vehicles to be Sreepur Moulovi Bazar  There is no possibility R-11 No loss Not addressed in the 162 near H/O Sabbir Master of any adverse impact in Not required Not found applicable applicable to near H/O Lalmia, terms of losing income subproject Ch.0+000 to Ch.1+100 or livelihood environmental )  Temporary management plan disturbance for (EMP) pedestrians and movement of vehicles to be addressed of on the Sub-project E.M.P.

Rehabilitation &  No IR impacts Construction of Road by  No requirement for DBC & RCC (from land acquisition PART=A: Nautmondir  The required land for Temporary to Magura Sreepur road construction work is disturbance of near Amtola Mosque, owned by Magura Ch. 0+000 to Ch. 0+415 Pedestrians and Pourashava & PART= B: Link road, vehicles to be R-12 near H/O Enseruddin to No loss Not  There is no possibility addressed in the TLCC of any adverse impact in Not required Not found Nutmondir road near applicable applicable subproject terms of losing income H/O Deno, Ch.0+000 to environmental Ch.0+340) at or livelihood management plan Niznanduali. In Ward  Temporary No-07). Total disturbance for (EMP) Length=755.00m at pedestrians and Niznanduali. In Ward movement of vehicles to No-07. Magura be addressed in the Pourashava, Magura. Sub-project E.M.P.

50

Improvement of Road by DBC (from  No IR impacts PART=A: Magura-  No requirement for Tangakhali road near land acquisition Hazari More to  The required land for Sheikhhpara Mosque, Temporary construction work is Ch.0+000 to Ch.0+420, disturbance of owned by Magura PART=B: Link Pourashava Pedestrians and road,near H/O Humaun vehicles to be Police to near H/O  There is no possibility R-13 No loss Not addressed in the TLCC Aktar, Ch.0+000 to of any adverse impact in Not required Not found applicable applicable Ch.0+288, terms of losing income subproject PART=C:Link road, or livelihood environmental near H/O Sohid Mistry  Temporary management plan disturbance for to near H/O Modhu (EMP) Biswas, Ch.0+000 to pedestrians and Ch.0+075, movement of vehicles to PART=D:Link road, be addressed in the near H/O Dr. Binoy to Sub-project E.M.P. near S/O Millon, Ch.0+000 to Ch.0+045 )  No IR impacts  No requirement for land acquisition  The required land for construction work is owned by Magura Temporary Pourashava disturbance of . Construction of RCC  There is no possibility Pedestrians and drain from Hazari more of any adverse impact in vehicles to be near Shop of Millon to D-1 No loss Not terms of losing income addressed in the 45 Seikhpara Musque at or livelihood Not required Not found applicable applicable subproject Boubazar Niznanduali,  Temporary environmental (Ch.0+000 to Ch.0+261) disturbance for pedestrians and management plan movement of vehicles to (EMP) be addressed in the Sub-project E.M.P.

51

Package Nr: UGIIP-III-2/MAGU/(UT+DR)/02/2016

 No IR impacts  No requirement for land acquisition Improvement of Moad  The required land for Temporary Baria- Babur Hat Road construction work is disturbance of by DBC from PART=A: owned by Magura Naran Khali Bridge to Pedestrians and Pourashava Atharokhada near H/O vehicles to be R-1 Siddique, Ch.0+000 to No loss Not  There is no possibility addressed in the 154 of any adverse impact in Not required Not found Ch.1+580, PART=B: applicable applicable subproject terms of losing income Link road at Ch.0+820, environmental near H/O Abul Hossen or livelihood management plan to Azahar Losker,  Temporary Ch.0+000 to Ch.0+460 disturbance for (EMP) ). pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P.  No IR impacts  No requirement for Improvement of road land acquisition Niznanduali Purbo para  The required land for Temporary road by RCC (from construction work is disturbance of PART=A: Magura- owned by Magura Tangakhali road near Pedestrians and Pourashava Boubazar to Majhepara vehicles to be R-2 Mondir, Ch.o+000 to No loss Not  There is no possibility addressed in the TLCC of any adverse impact in Not required Not found Ch.0+300 & PART=B- applicable applicable subproject terms of losing income Link road at Ch.0+160 , environmental near Agragami Sporting or livelihood management plan Club towards River  Temporary ghate via Monowar disturbance for (EMP) Biswas, Ch.0+000 to pedestrians and Ch.0+301 movement of vehicles to be addressed in the Sub-project E.M.P.

52

Rehabilitation of road by DBC from PART=A: Molla para mosque to Bitti para more, Ch.0+000 to Ch.0+571 & (A-1) from house Dr.  No IR impacts Nantu to house of  No requirement for Manna via Munshi Para land acquisition Idghah, Ch.0+000 to  The required land for Temporary Ch.0+355, and construction work is disturbance of Construction of Road owned by Magura (b) Molla para mosque Pedestrians and Pourashava to house of Tarek vehicles to be R-3 141, Munshi via house of No loss Not  There is no possibility addressed in the of any adverse impact in Not required Not found 150 Nantu Khan, Ch.0+000 applicable applicable subproject terms of losing income to Ch.0+362 ( C ) From environmental house of Maha Munshi or livelihood management plan to house of Photo  Temporary Mollah, Ch.0+000 to disturbance for (EMP) Ch.0+119 ( d ) From pedestrians and House of Rahman movement of vehicles to Member to behind be addressed in the Bepari para Gorstan, Sub-project E.M.P. Ch.0+000 to Ch.0+205, e) Munsi Para Gorstan road, Ch.0+000 to Ch.0+200 at Parnanduali.  No IR impacts  No requirement for Temporary land acquisition Rehabilitation of road by disturbance of  The required land for DBC from (a) Bepari construction work is Pedestrians and para mosque to Biswas owned by Magura vehicles to be para mosque via house R-4 No loss Not Pourashava addressed in the 142 of councilor Mr.Abdul Not required Not found applicable applicable Kader Goni MOHON  There is no possibility subproject (Ch. 0+000 to Ch. of any adverse impact in environmental 0+595). Link road (b) terms of losing income management plan or livelihood Ch. 0+000-0+115m, (EMP)  Temporary disturbance for pedestrians and 53

movement of vehicles to be addressed in the Sub-project E.M.P.

 No IR impacts  No requirement for Re-habilitation of road land acquisition DBC from PART=A:  The required land for Temporary Bepari para Godown of construction work is disturbance of MAZED MOLLA to owned by Magura Pedestrians and Munshipar house of Pourashava vehicles to be MURAD MUNSHI via R-5 No loss Not  There is no possibility addressed in the 146 BOUBAZAR and of any adverse impact in Not required Not found applicable applicable subproject puraton kheya ghat terms of losing income (Ch. 0+000 to Ch. 0+96 or livelihood environmental ) & PART=B: from BOU  Temporary management plan BAZAR to Bitti para disturbance for (EMP) more ( Ch.0+000- pedestrians and 0+372) movement of vehicles to be addressed in the Sub-project E.M.P.  No IR impacts Rehabilitation of Road  No requirement for by DBC from Parla- land acquisition Saddoya Road from  The required land for Temporary Chaulia Bus Stand construction work is disturbance of More to Parla Purba owned by Magura Para Mosque via Pedestrians and Pourashava Nangta Babar Ashram vehicles to be 101& R-6 and nearby the H/O No loss Not  There is no possibility addressed in the 102, of any adverse impact in Not required Not found Daud Biswas ( Ch.0.0 to applicable applicable subproject 112 terms of losing income 2120.0 m ) with a link environmental Road at Ch.1550.0 m, or livelihood management plan starting from the  Temporary Goalkhali More to disturbance for (EMP) Magura - Narail pedestrians and Highway ( Ch. 0.0 to movement of vehicles to Ch. 349.0 m ). be addressed in the Sub-project E.M.P.

54

Improvement of Road by RCC starting from the front of H/O Salam  No IR impacts Master to the Mollah  No requirement for para Mosque via shop land acquisition of Harun ( Ch.0.00 to  The required land for Temporary 503.0 m ) with Link construction work is disturbance of Road - 1 at Ch.160.00 owned by Magura m, staring from the Pedestrians and Pourashava H/O. Olier Rahaman to vehicles to be R-7 the Gorosthan Road ( No loss Not  There is no possibility addressed in the 94, 109 of any adverse impact in Not required Not found Ch. 0.00 t o Ch.0+135.0 applicable applicable subproject terms of losing income m, Link Road - 2 at environmental Ch.217.0 m, starting or livelihood management plan from the shop of Siraj to  Temporary Biman Tower Office disturbance for (EMP) (Ch. 0.0 to 84.0 m ) Link pedestrians and Road-3 at Ch.438m movement of vehicles to from nearby the H/O Iub be addressed in the Ali to nearby the H/O Sub-project E.M.P. Kazol Molla( Ch. 0.0 to 55.0 m) Construction of  No IR impacts Mollapara Road by  No requirement for R.C.C (from PART=A: land acquisition Gorstan road near H/O  The required land for Temporary Roise Shekh to construction work is disturbance of Mollapara road near owned by Magura H/O Tazrul via near H/O Pedestrians and Pourashava Mukti, Ch.0+000 to vehicles to be R-8 Ch.0+306, PART=B: No loss Not  There is no possibility addressed in the 107 of any adverse impact in Not required Not found Link road at Ch.0+ 065 applicable applicable subproject terms of losing income near H/O Ahmmed environmental Hossen to near H/O or livelihood management plan Mukt, Ch.0+000 to  Temporary Ch.0+225, PART=C, disturbance for (EMP) Link road at Ch.0+151 pedestrians and toward near H/O Liton movement of vehicles to , Ch.0+000 to be addressed in the Ch.0+040,) Sub-project E.M.P.

55

 No IR impacts  No requirement for Improvement of Kukna land acquisition Road by DBC (from  The required land for Temporary PART=A: Kukna road construction work is disturbance of near H/O Pritos to owned by Magura near H/O Siraz Pedestrians and Pourashava Chairman, Ch.0+000 to vehicles to be R-9 Ch.1+450, PART=B: No loss Not  There is no possibility addressed in the 36 of any adverse impact in Not required Not found Link road, near Kukna applicable applicable subproject terms of losing income Uttarpara Mosque, environmental Ch.0+000 to Ch.0+015, or livelihood management plan PART=C: Link road,  Temporary near H/O Aziz to near disturbance for (EMP) H/O Azahar, Ch.0+000 pedestrians and to Ch.0+065), movement of vehicles to be addressed in the Sub-project E.M.P.  No IR impacts Construction of West  No requirement for Stadiumpara RCC land acquisition Road ( from PART=A:  The required land for Temporary near H/O Ebadot to construction work is disturbance of Asia Mohila College owned by Magura Pedestrians and road via near H/O Pourashava vehicles to be Delowar Sir, Ch.0+000 R-10 No loss Not  There is no possibility addressed in the 41 to Ch.0+720, PART=B: of any adverse impact in Not required Not found applicable applicable subproject Link Road towards near terms of losing income H/O Eng. Abdur Rahim, or livelihood environmental Ch.0+000 to Ch.0+150  Temporary management plan & PART=C: Link Road disturbance for (EMP) towards near H/O pedestrians and Tahazzat, Ch.0+000 to movement of vehicles to Ch.0+075) be addressed in the Sub-project E.M.P. Re-habilitation & Temporary  No IR impacts Improvement of  No requirement for disturbance of Vitasair- Ghoramara land acquisition Pedestrians and R-11 road by DBC (from No loss Not 64 Not required Not found vehicles to be PART=A: Magura- applicable applicable  The required land for Jessore Road near construction work is addressed in the Vitasair Dal to end of owned by Magura subproject Pourashava near Pourashava environmental 56

Perfect School, Ch.  There is no possibility management plan 0+00 m to Ch. 2+572, of any adverse impact in (EMP) PART=B: Link road: terms of losing income Vitsir Primary School to or livelihood Magura-Jessore road  Temporary near S/O Jahangir Ch. disturbance for 0+00 m to Ch. 0+610 , pedestrians and PART=C: Link road: movement of vehicles to near H/O Awal to near be addressed in the H/O Abdur Rouf, Ch. Sub-project E.M.P. 0+00 m to Ch. 0+211).  No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of owned by Magura Pedestrians and Construction of RCC Pourashava vehicles to be drain from H/O Akbar to D-1 No loss Not  There is no possibility addressed in the TLCC existing Drain of any adverse impact in Not required Not found applicable applicable subproject (Ch.0+000 to Ch.0+117) terms of losing income at Niznanduali or livelihood environmental  Temporary management plan disturbance for (EMP) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P. Package Nr: UGIIP-III-2/MAGU/(UT+DR)/03/2016

Rehabilitation of Laxmikandor road by  No IR impacts Temporary DBC ( from PART= A:  No requirement for Magura-Dhaka road land acquisition disturbance of near S/O Amoresh to  The required land for Pedestrians and R-1 No loss Not 136 Magura -Dhaka road construction work is Not required Not found vehicles to be applicable applicable near S/O Aslam, owned by Magura addressed in the Ch.0+000 to Ch.1+260 Pourashava subproject & , PART=B: Link road  There is no possibility environmental at Ch.0+430 near H/O of any adverse impact in Apan to near H/O 57

Komoles, Ch.0+000 to terms of losing income management plan Ch0+150) or livelihood (EMP)  Temporary disturbance for pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P. Improvement of connecting Roads by DBC starting from Nut  No IR impacts Mondir Road to Magura  No requirement for - Sreepur Road ( RHD land acquisition Road ) at different  The required land for Temporary Chainages, Part ( A ): construction work is disturbance of From near by the H/O owned by Magura Pedestrians and Shunil to near by H/O Pourashava vehicles to be Pachu ( Ch.0.0 to R-2 No loss Not  There is no possibility addressed in the TLCC Ch.310.0 m ) Part B : of any adverse impact in Not required Not found applicable applicable subproject From near by the H/O terms of losing income Poritosh to near H/O or livelihood environmental Jenna via  Temporary management plan A.N.Sommiloni Girls disturbance for (EMP) School , ( Ch. 0.0 to Ch. pedestrians and 385.0 m ) & Part C : movement of vehicles to From nearby the H/O be addressed in the Liton to nearby H/O Sub-project E.M.P. Rashed Sheikh ( Ch.0.0 to Ch. 466.0 m ) Rehabilitation of  No IR impacts Borunatail road by DBC  No requirement for Temporary ( from PART= A: land acquisition disturbance of Magura-Dhaka road  The required land for Pedestrians and near Bus-Terminal to construction work is vehicles to be Magura -Mohammadpur owned by Magura R-3 No loss Not addressed in the 138 road near H/O Salam Pourashava Not required Not found applicable applicable subproject Member, Ch.0+000 to  There is no possibility Ch.0+740 & , PART=B: of any adverse impact in environmental Link road at Ch.0+150 terms of losing income management plan near H/O Habibur or livelihood (EMP) Rahman to  Temporary Mohammadpur road disturbance for 58

near Vashani Sreeti pedestrians and Sangha, Ch.0+000 to movement of vehicles to Ch0+850) be addressed in the Sub-project E.M.P.

 No IR impacts  No requirement for Re-habilitation & land acquisition Construction of Collage  The required land for Temporary para road by DBC & construction work is disturbance of RCC (PART=A: near owned by Magura Pedestrians and H/O AKBAR Pourashava vehicles to be CHAIRMAN to Hazi R-4 No loss Not  There is no possibility addressed in the TLCC Abdul Hamid road near of any adverse impact in Not required Not found applicable applicable subproject Govt.Library, Ch. 0+000 terms of losing income to 0+467 & PART=B: or livelihood environmental Link Road, near H/O  Temporary management plan AKKAS ALI to near disturbance for (EMP) H/O MANNU Sir.Ch. pedestrians and 0+000 to 0+292) movement of vehicles to be addressed in the Sub-project E.M.P. Improvement of College  No IR impacts Para road (Part:A :  No requirement for Kesob more to land acquisition Collegepara near H/O  The required land for Temporary Kalam via nearby H/O. construction work is disturbance of Chandu Comissoner, owned by Magura Pedestrians and ch.0+000 to Ch.0+500, Pourashava vehicles to be Part: B Link road, R-5 223 & No loss Not  There is no possibility addressed in the nearby Abu Bakkar to of any adverse impact in Not required Not found 225 applicable applicable subproject nearby H/O. Mozid terms of losing income Nayeb, ch.0+000 to or livelihood environmental Ch.0+185, Part: C :  Temporary management plan Kesob more to Habibur disturbance for (EMP) Rahman road to H/o. pedestrians and Mahabub Sir, ch.0+000 movement of vehicles to to Ch.0+443 & Part: D : be addressed in the Mahabub Sir to near Sub-project E.M.P.

59

H/O. Boloram,ch.0+000 to Ch.0+355,  No IR impacts  No requirement for land acquisition Rehabilitation &  The required land for Temporary Improvement of Road construction work is disturbance of from PART-A: Magura- owned by Magura Jhenidha road near H/O Pedestrians and Pourashava Azgar Ali to Wazad Ali vehicles to be R-6 road near H/O Foru No loss Not  There is no possibility addressed in the 12 of any adverse impact in Not required Not found Biswas, Ch.0+000 to applicable applicable subproject terms of losing income Ch.0+840, PART-B= environmental Link Road at Ch.0+135 or livelihood management plan Near H/O Mozahar to  Temporary near H/O Nazrul, Ch. disturbance for (EMP) 0+000 to Ch.0+195) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P.  No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of Rehabilitation of owned by Magura Abalpur Khondokarpara Pedestrians and Pourashava Road by DBC from vehicles to be R-7 Wazed ali road near No loss Not  There is no possibility addressed in the 18 of any adverse impact in Not required Not found Mirer Battola to near applicable applicable subproject terms of losing income H/O Solaman environmental Khondokar or livelihood management plan Ch.0+000 to Ch.0+715  Temporary disturbance for (EMP) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P.

60

 No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of owned by Magura Pedestrians and Pourashava Rehabilitation of Road vehicles to be R-8 from Mirar Battola to No loss Not  There is no possibility addressed in the TLCC of any adverse impact in Not required Not found Darua Bridge, Ch0+000 applicable applicable subproject to Ch.0+571). terms of losing income or livelihood environmental  Temporary management plan disturbance for (EMP) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P. Construction of Dori Magura Kalkalia para road by RCC (from Shibrampur road near  No IR impacts H/O Babul Shakh to  No requirement for near H/O Sattik Master, land acquisition Ch.0+000 to Ch.0+210,  The required land for Temporary PART=B, Link road at construction work is disturbance of Ch.0+120 near H/O owned by Magura Pedestrians and Gourango Saha to Pourashava vehicles to be CARE road near H/O R-9 No loss Not  There is no possibility addressed in the 178 Sorap, Ch.0+000 to of any adverse impact in Not required Not found applicable applicable subproject Ch.0+210, PART=C, terms of losing income CARE road near or livelihood environmental Santoz Datter Ambagan  Temporary management plan to Shibrampur road disturbance for (EMP) near H/O Prokash, pedestrians and Ch.0+000 to Ch.0+330 movement of vehicles to & PART=D, Link Road be addressed in the at Ch.0+240 near H/O Sub-project E.M.P. Deven Biswas towards near H/O Biren Nayeb, Ch.0+000 to Ch.0+060)

61

 No IR impacts  No requirement for land acquisition Improvement of Road  The required land for Temporary by DBC ( from PART- construction work is disturbance of A= Magura-Sreepur owned by Magura road near H/O Emdadul Pedestrians and Pourashava to near H/O Hakim vehicles to be R-10 169 & Biswas, Ch.0+000 to No loss Not  There is no possibility addressed in the of any adverse impact in Not required Not found 170 Ch.0+410 & applicable applicable subproject terms of losing income ,PART=B:Link road environmental near H/O Zahidul to or livelihood management plan Future School , Ch.  Temporary 0+000 to Ch. 0+300)at disturbance for (EMP) Niznanduali. pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P. Rehabilitation & Construction of Tati Para Road Part A : Starting from Abu Ishaq Road near shop of  No IR impacts Salauddin Moulavi to  No requirement for Norail Road near H/O land acquisition Arad Mollah, Ch. 0.0 to  The required land for Temporary Ch.165.0 m with link construction work is disturbance of Road Part B : Starting owned by Magura Pedestrians and from Ch. 55.0 m nrarby Pourashava vehicles to be the H/O Dr. Sakir to R-11 96, 110 No loss Not  There is no possibility addressed in the Norail Road near the of any adverse impact in Not required Not found & 111 applicable applicable subproject H/O Salam, Ch.0.0 to terms of losing income Ch.240.0 m, Part C : By or livelihood environmental link starting from the  Temporary management plan Ch.210.0 m of part B to disturbance for (EMP) Tati Para RCC Road, pedestrians and Ch.0.0 to Ch.160.0 m, movement of vehicles to Part D: By link from Ch. be addressed in the 20.0 m of Part C to Sub-project E.M.P. Tanti Para RCC Road near H/O Ratan, Ch. 0.0 to Ch. 130.0 m, Part E : By link from Ch. 62

42.0 m of part-C near Tanti Para Mosque to Norail Road, Ch. 0.0 to Ch. 40.0 m

Improvement of Khalkul  No IR impacts Para Road by  No requirement for Bituminous Dense land acquisition Carpeting from Moulavir  The required land for Temporary Garrage to nearby the construction work is disturbance of H/O Satter Miah ( Ch. owned by Magura 0.0 to Ch. 0+ 661.o m ) Pedestrians and Pourashava with link Road - 1 at Ch. vehicles to be R-12 223.0 m ( Ch0.0 to No loss Not  There is no possibility addressed in the 97 & 98 of any adverse impact in Not required Not found Ch.292.0 m ), link Road applicable applicable subproject terms of losing income 1(1) at Ch. 25.0 m ( Ch. environmental 0.0 to Ch.415.0 m ), or livelihood management plan Link Road 1(2) at  Temporary Ch.320.0 m ( Ch. 0.0 + disturbance for (EMP) 151.0 m ), Link Road - 2 pedestrians and with Beltola Road at movement of vehicles to Ch.285.0 m ( Ch.0.0 to be addressed in the Ch. 0+ 176.0 m ) Sub-project E.M.P. Rehabilitation &  No IR impacts Construction of Vaina  No requirement for Santibag Road by DBC Temporary land acquisition & RCC ( From disturbance of  The required land for PART=A: Magura - construction work is Pedestrians and Jessore road near near owned by Magura vehicles to be H/O Nazrul to Gorstan R-13 No loss Not Pourashava addressed in the 92 road near H/O Abu-Zel Not required Not found applicable applicable Via Shakhpara Jame  There is no possibility subproject Mosque, Ch.0+000 to of any adverse impact in environmental Ch.1+255, PART=B: terms of losing income management plan or livelihood Link road Ch.0+420 to (EMP) Near H/O Serzent  Temporary Mosiur, Ch.0+000 to disturbance for Ch.0+100, PART=C: pedestrians and 63

Link road, near H/O movement of vehicles to Kamal Sheikh to be addressed in the Sheikhpara Baitus Sub-project E.M.P. Salahen Jame Mosque, Ch.0+000 to Ch.0+325, PART=D: Link road, near H/O Eshak to H/O Awal, Ch.0+000 to Ch.0+050),  No IR impacts  No requirement for land acquisition  The required land for Temporary construction work is disturbance of Construction of RCC owned by Magura Pedestrians and drain from Bus-Terminal Pourashava vehicles to be D-1 to Box Culvert of 3 No No loss Not  There is no possibility addressed in the TLCC of any adverse impact in Not required Not found Halot at Parnanduali applicable applicable subproject terms of losing income (Ch.0+000 to Ch.0+480) or livelihood environmental  Temporary management plan disturbance for (EMP) pedestrians and movement of vehicles to be addressed in the Sub-project E.M.P.

64

37. Indigenous People. There is no identified indigenous people/ethnic minority (adivasi) communities on the vicinity of the proposed Sub-Project components and no ethnic people will be affected by the Sub-Project activities. The IP Categorization form is attached as Appendix- 3. The Sub-Project has no IP impact and classified as Category C for IP.

38. Others. The Sub-Project will not (i) result in labour retrenchment or encourage child labour; or, (ii) directly or indirectly contribute to the spread of HIV/AIDS, human trafficking, or the displacement of girls and women. The Sub-Project will have no potential impact on any female- headed household.

39. Cost. Table 3 provides the costs and sources of funds to ensure social safeguards are considered in the Sub-Project implementation.

Table 3: Social Safeguards Cost Relevant to Sub-Project Implementation

Activities Amount (TK) Source of Funds (i) public consultation and disclosure 300,000 P I U

(ii) grievance redress mechanism 100,000 P I U

(iii) safeguards capacity building program 450,000 Under MDSC costs

(vi) materials for awareness raising and 3,30,000 Under GICDC costs implementation of consultation and participation plan

40. Outcome of the Sub-Project. However, the roads and drainage construction/ improvement under the project will improve transportation facilities and increase the capacity of receding waste water from industries, households, commercial premises, etc. The Sub-Project is expected to increase area coverage of drainage and improved road communication system and will guarantee health condition and will reduce transport cost of goods and services including travelling cost of the residents of the town.

41. The outcome of the Sub-Project is improved transport and drainage system within the Pourashava area which will improve communication facilities and will prevent water logging and unexpected flooding during monsoon.

42. Sub-Project Benefits. Improvement of roads and construction of drains proposed under the Sub-Project is expected to bring various quantifiable benefits for the citizens of Pourashava.. Road improvement will improve connectivity and as a result, vehicular movement will increase, journey will be safer, quicker and comfortable. Transportation costs will be lower and movement will be easier which will bring new avenues for investment and consequently commercial activities will

65

increase which will boost up economic development. Extended benefits will include employment opportunity for local people during construction and maintenance.

43. Construction of drainage facilities will improve effectiveness of drainage system causing increased and easy draining out of storm and waste water, will reduce water-logging and consequently, intensity of water borne diseases will decline which will help to improve both the quality of life and living condition of the residents of the Pourashava. The standards of individual and public health as well will rise. Extended benefits will include employment opportunity for local people during construction and maintenance.

42. Thus the Sub-Project implementation will bring economic gains to the local people in the form of increased employment and less spending on healthcare and transportation.

V. FUTURE CONSULTATIONS AND DISCLOSURE

43. This due diligence report and other relevant documents will be made available at public locations in the Pourashava and posted on the websites of LGED and ADB. The same information will be posted in Magura Pourashava and provided to members of TLCC and community representatives.

44. A consultation and participation plan is prepared for UGIIP-III; consultation activities will be coordinated by the PMU, PIU (Magura Pourashava) and consultant teams to ensure that the communities are fully aware of the activities at all stages of the project implementation. During construction phase, Magura Pourashava with assistance of consultant teams will conduct (i) public meetings with affected communities to discuss and plan work programs and allow issues to be raised and addressed once construction has started; and (ii) smaller-scale meetings to discuss and plan construction work with individual communities to reduce disturbance and other impacts, and to provide a mechanism through which stakeholders can participate in project monitoring and evaluation. The PIU will coordinate the schedule with the contractors and will ensure proper public consultations are held prior to start of civil works and during implementation. Documentation should be included in the social safeguard monitoring report.

45. The relevant information in this due diligence report together with following information on GRM will be translated to local language and disclosed to persons in the Sub-Project area. Documentation will be included during social safeguard monitoring report. The social safeguard officers (XEN) will disclose information.

46. Grievance Redress Mechanism. A project-specific grievance redress mechanism (GRM) has been established at Magura Pourashava to receive, evaluate, and facilitate the resolution of AP’s concerns, complaints, and grievances about the social and environmental performance. This outlined in figure 5 bellow. The GRM aims to provide a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project. The multi-tier GRM for

66

the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons’ advice at each stage, as required. The PMU, MDSC safeguards team and Governance Improvement and Capacity Development (GICD) team have been supporting the PIU in establishing the GRM and building the capacity of the GRC members to address project-related complaints/grievances. Along with Pourashava officials, contractors and local people are mobilizing and being informed about their role- responsibilities and procedures involved in the GRM through TLCC & WLC meeting, Miking (announcing/disseminating messages by loud speaker), leaflet distribution, etc. Consequently, awareness regarding quality infrastructure work and different municipal services have been raised. Grievance Redress Form has already been translated into Bengali (local language) is being shared during the consultations. It also attached the DDR as Appendix 3. Once contractors are mobilized, inform them of their role and responsibilities and procedures involved in the GRM.

47. PIU and governance improvement and capacity building consultants (GICDC) will conduct Pourashava wise awareness campaigns to ensure that people in the Sub-Project area are made aware of grievance redress procedures and entitlements, and will work with the PMU and MDSC to help ensure that their grievances are addressed.

48. Affected persons will have the flexibility of conveying grievances /suggestions by dropping grievance redress/suggestion forms in complaints/suggestion boxes that have already been installed by PIU or through telephone hotline 01711619238, and EXN 01711300509 [email protected], Secy.01718595477 at accessible locations, by post, or by writing in a complains register in PIU or Magura Pourashava office. Appendix 5 has the sample grievance registration form.

49. Careful documentation of the name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved have been undertaken in the Grievance Redress Cell (GRC) in the Pourashava. Safeguard Officers have the overall responsibility for redressing grievance timely on environmental and social safeguards issues against complain registered. Related disclosure and regular communication have been taking place with the concern persons through the PIU designated safeguard focal person.

50. Grievance redresses process. In case of grievances that are immediate and urgent in the perception of the complainant, the contractor and MDSC on-site personnel will provide the most easily accessible or first level of contact for quick resolution of grievances. Contact phone numbers and names of the concerned PIU safeguard focal person and contractors, will be posted at all construction sites at visible locations. 1st Level Grievance: The phone number of the PIU office should be made available at the construction site signboards. The contractors and PIU safeguard focal person can immediately resolve on-site in consultation with each other, and will be required to do so within 7 days of receipt of a complaint/grievance.

67

2nd Level Grievance: All grievances that cannot be redressed within 7 days at field/ward level will be reviewed by the Grievance Redress Cell (GRC) headed by Panel Mayor-1 of the Pourashava with support from PIU designated safeguard focal person and MDSC regional environment and resettlement specialists. GRC attempts to resolve them within 15 days 1 . The PIU designated safeguard focal person is responsible to see through the grievance redress mechanism.

3rd Level Grievance: The PIU designated safeguard focal person will refer any unresolved or major issues to the PMU safeguard officer and MDSC national environmental and resettlement specialists. The PMU in consultation with these officers/specialists will resolve them within 30 days.

51. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM.

52. In the event that the established GRM is not in a position to resolve the issue, the affected person also can use the ADB Accountability Mechanism (AM) through directly contacting (in writing) the Complaint Receiving Officer (CRO) at ADB headquarters or the ADB Bangladesh Resident Mission (BRM). The complaint can be submitted in any of the official languages of ADB’s DMCs. The ADB Accountability Mechanism information has been included in the PID to be distributed to the affected communities, as part of the project GRM

53. Recordkeeping. Records of all grievances received, including contact details of complainant, date the complaint was received, nature of grievance, agreed corrective actions and the date when these are affected and final outcome will be kept by PIU. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PMU office, Pourashava office, and on the web, as well as reported in monitoring reports submitted to ADB on a semi-annual basis.

54. Periodic review and documentation of lessons learned. The PMU safeguard officer will periodically review the functioning of the GRM in each Pourashava and record information on the effectiveness of the mechanism, especially on the project’s ability to prevent and address grievances.

55. Costs. All costs involved in resolving the complaints (meetings, consultations, communication and reporting/information dissemination) will be borne by the concerned PIU at Pourashava-level; while costs related to escalated grievances will be met by the PMU. Cost

1 Grievance Redress Committee (GRC) has been formed at Magura Pourashava. The GRC comprises of the Pannel mayor 01 as Chairperson, Concern Ward councillors (Male &femal ) -member, Mr. ,MD. Mahfazur Rahaman Khan S.AE Magura pourashava Member, Mr. Md. Abdul Halim Co-ordinator Saplil magura Member. 1(one), Representtative from A.P.S-Member,. For project related grievances, if arises, representatives of NGO, Community based organizations (CBOs), eminent citizens, will be invited as observers.

68

estimates for grievance redress are included in social safeguard implementation cost estimates for affected person if wises.

GRM Diagram Affected person

Yes Field/ward level Within 7 days Grievance 1st Level redressed and Grievance Contractor and PIU designated safeguard record keeping focal person

No Yes, Pourashava level (GRC) Grievance nd within 15 days 2 Level redressed and Grievance PIU designated safeguard focal person, record keeping MDSC regional environmental and

No Yes PMU level Grievance rd Within 30 days 3 Level redressed and Grievance PMU Safeguard Officer and MDSC national record keeping environmental and resettlement specialists

Note: GRC = Grievance Redress Cell;; PIU = Project Implementation Unit; MDSC = Management. Design and Supervision Consultants; PMU = Project Management Office

Figure 6: Affected Person Grievance Redress System

VI. MITIGATION OF SOCIAL CONCERNS

56. Although the road and drainage schemes under the Sub-Project of UGIIP-III construction/improvement is not expecting any land acquisition and involuntary resettlement, physical or economic displacement, or temporary restrictions to land use. However, some assumptions were made that during civil works for different schemes, pedestrians, residents and shop keepers/different business operators carrying out different economic activities particularly beside the road; customers might face temporary disturbances in connection to movement and operate their business. In order to avoid even minor temporary disturbances during the construction activities, the following measures are suggested to eliminate such impacts:  Informing all the residents, local households and traders about the nature and duration of works in advance, so that they can make necessary preparation to face the situation.

69

 Providing wooden walkways/ planks across trenches for pedestrians and metal sheets where vehicles access is required.  Increasing the workforce and using the appropriate equipment to complete the work in a minimum timeframe.  Suggest people to wear musk to protect from dust problem during construction.  Other social concern, if any, shall be properly solved by the Grievance Redress Committee (GRC) under the Grievance Redress Mechanism (GRM) of the project to be formed by the PIU.  Any other preventive measures to be adopted as required considering the situation during construction. 57. The above mitigation measures during construction activities will ease the temporary disturbances in connection to movement and operation business of the local residents, pedestrian customers and clients from shopping locally or using the usual services from local business.

VII. CONCLUSIONS

58. Important findings of the study in connection to social safeguard issues are (i) improvement of the roads will be carried out on the existing alignments and will not require land acquisition; (ii) no roads need resettlement, dislocation or relocation. So only08 (eight) strip maps are provided as a sample. (iii) there is no structure, houses, shops, trees or any other establishments on the ROWs of the proposed roads and drains alignments; (iv) the required land for construction work is owned by Magura Pourashava; (vi) the local people unanimously welcomed the project and showed positive attitude to the improvement of the proposed Sub-Project. None was found to oppose the Sub-Project; (vii) urban residents and the rural residents in surrounding hinterland will benefit from improvement of the propose roads for creating better access to urban markets & social services provided in the project town; (viii) no potential negative impact could be identified and (ix) business or economic activities will not be impeded resulting losses in income or asset.

59. A due diligence process was conducted for the Sub-Project to examine the IR issues particularly with respect to the requirements of the ADB’s SPS (2009) and ARIPO. The roads, drains and Street lighting proposed under the Sub-Project will be of straightforward construction on the existing ROWs. So, implementation of the Sub-Project will neither affect any land or structure. Any disturbances will be limited to construction period only. The likely impacts are short-term, localized and could easily be avoided or mitigated. The results of the study suggest that the impact of this Sub-Project does not incur any land acquisition, resettlement or economic displacement.

60. The Project Director (PD) will carry out internal monitoring through the PMU and PIUs with the support of the MDSC. For this Sub-Project, PIU will provide PMU on updates on (i) GRM establishment; (ii) report of public consultations and disclosures conducted; (iv) complaints/grievance received, if any, and resolutions conducted; and (iv) unanticipated IR impacts during Sub-Project implementation not included in this due diligence report.

70

61. Based on the findings presented in this due diligence report, the Magura Sub-Project Packages will not require land acquisition and will not cause involuntary resettlement impacts. No IP was identified in the Sub-Project area. Thus it has been concluded that the Sub-Project is Category C for IR and Category C for IP as per ADB SPS 2009.

71

VIII. APPENDIX 1: RECORDS OF PUBLIC CONSULTAION IN MAGURA POURASHAVA

Consultation Meeting 01 Venue/Location: Moulovi Bazer (ward-07) Date 19-10-2016 Time: 10AM No of Participants: 15 Agenda: Consultation meeting in planning improvement, construction / rehabilitation of roads and drains in Magura Pourashava in Phase -2

The public consultation meeting was presided over by Mr. Md.Sakib-AL–Hasan Tuhin, (Councilor) Magura Pourashava; Consultants from Social Safeguard Unit of MDS, UGIIP-III were present in the meeting. In the meeting, road users, beneficiaries of the drains, local elites, local government representatives, and businessmen were present.

The agenda of meeting was advising on the planning, improvement, reconstruction, rehabilitation of ADB funded roads, drains of the Pourashava under UGIIP-III within the participant’s area. The participating representatives of concerned communities, road users drainage beneficiaries, members of ward committees and representatives of local government agencies were important.

The Regional resettlement Specialist (UGIIP-III) briefed the participants regarding the goals and objectives of the projects and safeguard issues relating to public disturbance during construction period and also probable mitigation measures highlighting that there would be no land acquisition or public donation of land for Sub-Project implementation as the activities will be implemented inside the ROWs and also informed the meeting that no indigenous / tribal people will be affected. The issues raised during this public consultation have been addressed in this Due Diligence Report (DDR), noting these issues would not pose any significant constraint in the implementation of proposed Sub-Project. During open discussion session, participants raised following questions, queries and suggestions:

 Participants urged the Pourashava officials to ensure quality of the work  Does the sub project have any acquisition?  The participants want to know the detailed design of the sub projects, length, width etc.  Would the Sub-Project have any structure relocation or livelihood impact?  Payment modalities of losses incurred by the sub projects, if any  Positive regarding the development activities through the proposed Sub-Projects.  They urged the authority not disturb any mobile vendors. If any disturbance of their livelihood any way, proper compensation and livelihood restoration.  Ensuring proper safety measures during construction period and alternative road arrangement of passer-by.  Updating of the project issues by arranging consultation of the local people and project affected people if any.

The meeting concluded with thanks from the chair to the participants. List and Photographs of participants are given below:

72

Attendance Sheet

73

Consultation Meeting at Magura Pourashova on 19-10-16.

Public Consultation at Moulovi Bazar in Magura Pourashava on 19-10-16

74

Key Issue Discussion

SLNO Issues Discussed Major Findings 01 Purpose of the The consultant describes the purpose of the consultation consultation meeting meeting. The main focus was improvement of roads and and scope meeting and drains of different areas of the Pourashava. The ADB is the scope of subprojects main donor of the project. Project beneficiaries should be under UGIIP-III. included for control monitoring work during the construction.

The MDS consultants of UGIIP-III visited the all subprojects under UGIIP-III to Physically observe is there any IR impacts existing with the ROW and other relevant activities as per donor requirements and ADB SPS 2009. 02 Service use from Positive side is when the roads and drains construction Pourashava Possible will be completed all people will be benefited. positive and negative impacts 03 Access to supply Water People of this area have to rely on tube well for their all water needs as the area is without any water supply service. So, every household has its own tube well. 04 Local facilities and poor Some people asked is there any scope of local labour or any community to get supply works during the construction period. access 05 How the better road At some points the road is very narrow and at other points the communication will bends and curves need to be straightened, people on both bring better scopes for sides promised to sacrifice a part of their land if required the community to make the road wide and straight enough. They will get access to markets, hospitals and educational institutions, etc. 06 Scope of employment in Local people asked during the construction phase if there project works is any scope of local people recruitment. 07 Opinion of the local Local people of the area need road very much. There will not people regarding be any land acquisition occurred during the implementation of improvement of the sub-projects. Improved road and drainage system will existing road and the remove water logging during wet season. area as a whole Drainage system needs an outlet to another direction, not to end in the existing pond or private land. The alignment of the proposed drain will move toward the bridge and would not create any water pollution in the ponds. 08 Difficulties occurred for Local are noticed about the development work of Pourashava construction work and participants said they will accommodate their difficulties during construction work.

75

Public Consultation Meeting 02 Location/venue:Parla uttar Para (ward -4) Date:19-10-16 Time:11.00AM No of participants :15 Agenda: Consultation meeting in planning improvement, construction / rehabilitation of roads and drains in Magura Pourashava in Phase -2

The public consultation meeting was presided over by Mr. Md. Mokbul Hossin Panel Mayor -01, Magura Pourashava; Consultants from Social Safeguard Unit of MDS, UGIIP-III were present in the meeting. In the meeting, road users, beneficiaries of the drains, local elites, local government representatives, and businessmen were present.

During initial survey assessment, the Project follows a participatory approach involving local stakeholders. That is why stakeholder consultations were held in getting opinion of the local people. In addition to that for identification of affected person and assessing their socio economic condition socio-economic surveys were carried out as a part of project planning and initiation of PDPs by means of open, facilitated sessions for Pourashava visioning or planning. A project brief was prepared for each Pourashava that provided an overview of potential resettlement impacts and explained proposed entitlement for affected persons (APs).Present consultation meeting is a part of that approach.

Among the participants representatives of concerned communities, road users drainage beneficiaries, members of ward committees, and representatives of local government agencies are important. Some issues were raised during public consultations that have been addressed in the DDR, but the issues would not pose any significant constraint in the implementation of proposed sub- project.

The agenda of the meeting is the, planning, improvement, reconstruction, rehabilitation of ADB funded roads, drains of the Pourashava under UGIIP-III.

The Regional resettlement Specialist (UGIIP-III) briefed the participants regarding the goals and objectives of the projects. And also briefed safeguard issues relating public disturbance during construction period and also probable mitigation measures in view of ADB guideline of safeguard.

They raise the following issues for mitigation. During open discussion session, participants raised following questions, queries and suggestions:  Participants urged the Pourashava officials to ensure quality of the work  Does the sub project have any acquisition?  The participants want to know the detailed design of the sub projects, length, width etc  Would the Sub-Project have any structure relocation or livelihood impact?  Payment modalities of the losses incurred by the sub projects, if any.  Positive regarding the development activities through the proposed Sub-Projects.  They urged the authority not disturb any mobile vendors. If any disturbance of their livelihood any way, proper compensation and livelihood restoration.  Ensuring proper safety measures during construction period and alternative road arrangement of the Pedestrians.  Updating of the project issues by arranging routine consultation of the local people and project affected people if any.

The meeting concluded with thanks from the chair to the participants. List and Photographs of participants is given below:

76

Attendance Sheet

77

Consultation of with Local People’s in Magura Pourashava on 19-05-2016

78

Key Issue Discussion

Sl. Major No Issues Discussed Findings . 1 Purpose of the consultation The Meeting and scope of consultant Sub-projects under UGIIP-III. Project beneficiaries should Be included for control described monitoring work. the purpose the consultation meeting. The main focus was improvemen t of roads and drains at different areas of the Pourashava. The ADB is the main donor of the project. Project beneficiaries should be included for control monitoring work during the construction The MDS consultants of UGIIP-III visited the all subprojects under UGIIP-III to physically observe is there any IR impacts existing with the ROW and other relevant activities as per donor requirement 79

Sl. Major No Issues Discussed Findings . s and ADB SPS 2009. 2 Avoid livelihood impact of footpath vendors The road is very narrow, so when Heavy vehicles like tractors run side by side it sometimes causes destruction of household fences. 3 Ensure proper safety management In the rainy season, it gets worse and movement of vehicles comes to a stop at some time when it rains heavily. Sometimes accidents happen. 4 Main concern of the participants is the quality of the construction work. The Pourashava authority ensure that the quality of works will be closely monitored by the Pourashava and quality will be ensured for the better communicati on of householder s and during construction safety of workers and pedestrian will be ensured.

80

Sl. Major No Issues Discussed Findings . 5 Take proper suggestions from the grass root people to fulfill future demand During selection of the schemes local people were discussed and was prioritized accordingly. 6 How the better road The better communication will bring road better scopes for the condition will community greatly ease the pain of present sufferings in movement on the road. Business, education and health will be highly benefited and so will be people’s overall wellbeing. Poor women ponder over sunning their parboiled paddy on the medaled road and many poor men are planning to buy rickshaw or van to ply on the improved road and make a good fortune of its development . The road will be busier and so will be the lives of the people

81

Sl. Major No Issues Discussed Findings . living on its two sides

7 Opinion on services of the Pourashava The participants of the meeting expressed that the roads and drains will need to be maintained properly after construction. They also expressed that drains are inadequate, conditions of roads are not good, and the existing drains are not cleaned regularly. 8 Local facilities and poor community to get access Children of the locality go to the primary school which is not far from the area. But the nearest college is too far from the locality for students to go there on every day without much hassle. The poor condition of the road causes the most of their sufferings. So, local people want improved 82

Sl. Major No Issues Discussed Findings . roads to get access to markets, hospitals, educational institutions, etc. easily.

9 Willingness to support project The community is willing to support the rehabilitation of the sub- Project as no private land is needed for the implementati on of the subproject.

Public Consultation Meeting # 03

Location/venue: Abalpur mirer bottola (ward -01) Date:19-10-16 Time : 1.00 PM No of participants : 15 Agenda: Consultation meeting on planning, improvement, construction/rehabilitation of roads and drains in Magura Pourashava, under Phase -2.

The public consultation meeting was presided over by Mr. Md. Aminul Islam Polash Councilor (word -01), Magura Pourashava, Consultants from Social Safeguard Unit of MDS, UGIIP-III were present in the meeting. In the meeting, road users, beneficiaries of the drains, local elites, local government representatives, and businessmen were present.

The agenda of meeting included the planning, improvement, reconstruction, rehabilitation of ADB funded roads and drains of the Pourashava under UGIIP-III and a discussion was made with the participant’s on it. The representatives of concerned communities, road & drainage user, members of ward committee and representatives of local government agencies attended the meeting. The Regional resettlement Specialist (UGIIP-III) briefed the participants on the goals and objectives of the projects. The safeguard issues, noise pollution during construction and its mitigation measures were discussed in the meeting. It has been noted that no land acquisition for the implementation of the Sub-Project is needed. as all the activities will be located within the RoW. It was eminent that no indigenous/tribal people will be affected by the implementation of this project. These issues were raised in the public consultation meeting, which have been depicted in this Due Diligence Report (DDR). None of these issues would act as a significant hindrance in the 83

implementation of the proposed Sub-Project. During open discussion session, participants raised following questions, queries and suggestions:

 Participants urged the Pourashava officials to ensure quality of the work

 Does the sub project have any acquisition?  The participants want to know the detailed design of the sub projects, length, width etc.  Would the Sub-Project have any structure relocation or livelihood impact?  Payment modalities of losses incurred by the sub projects, if any  Positive regarding the development activities through the proposed Sub-Projects.  They urged the authority not disturb any mobile vendors. If any disturbance of their livelihood any way, proper compensation and livelihood restoration.  Ensuring proper safety measures during construction period and alternative road arrangement of passer-by.  Updating of the project issues by arranging consultation of the local people and project affected people if any.

The meeting concluded with thanks from the chair for participating beneficiaries and users in the meeting. Photograph showing consultation meeting, as below:

84

Attendance Sheet

85

Public Consultation at Mirer Bottola (ward -01), Magura Pourashava on 19-10-16

86

Key Issue Discussion

Sl. Key issues Major Findings No. 1. Existing condition of the The existing road is not in good condition. The pedestrians have road situation needs to be to face a lot of sufferings due to bad condition of the road. In the improved business area, there is traffic jam in the road. So, there is urgent need of rehabilitation of the road.

2. Local people’s opinions on Local people of the area need road very much. There will not be improvement of the any acquisition and requisition. Improved road condition will existing road system and remove water logging during wet season land issues. Drainage system needs an outlet to another direction, not to end in the existing pond or private land. The alignment of the proposed drain will move toward the bridge and would not create any water pollution in the ponds.

3. Community’s willingness to The community is willing to support the rehabilitation of the sub- support Pourashava project as no land is needed and all rehabilitation will be on existing condition thus no livelihood would be lost.

4. Local facilities and poor Children of the locality go to the primary school which is not far from community to get access the area. But the college is too far from the area. The poor condition of the road causes sufferings. The local people opined that if roads are improved their children would get easy access to educational institutions, health centres, etc..

5. Difficulties occurred for Local are noticed about the development work of Pourashava and construction work participants said they will accommodate their difficulties during construction work.

87

Public Consultation Meeting 04 Location/venue: Doarpar shop (ward -08) Date: 19-10-16 Time: 03PM No of Participants: 15 Agenda: Consultation meeting in planning improvement, construction / rehabilitation of roads and drains in Magura Pourashava in Phase -2

The public consultation meeting was presided over by Mr. Ashutosh saha, Councilor Magura Pourashava; Consultants from Social Safeguard Unit of MDS, UGIIP-III were present in the meeting. In the meeting, road users, beneficiaries of the drains, local elites, local government representatives, and businessmen were present.

During initial survey assessment, the Project follows a participatory approach involving parallel activities: stakeholder consultations, socio-economic surveys, and initiation of PDPs by means of open, facilitated sessions for Pourashava visioning or planning. A wide range of stakeholders were provided the opportunity to make substantive contributions concerning existing conditions and preferences. A project brief was prepared for each Pourashava that provided an overview of potential resettlement impacts and explained proposed entitlement for affected persons (APs). The councillor informed to the public consultation that during the implement of Sub-Project no public donation/land acquisition are required. The road will very much fruitful for communication for common people of Pourashava.

Participants came from u r b a n communities/road users/ drainage beneficiaries, members of ward committees, and representatives of local government agencies. Some issues were raised during public consultations that have been addressed in the (Resettlement Plan) RP, but these issues would not pose a significant constraint in the implementation of proposed sub- project. Also informed that no indigenous people will affected by the Sub-Project.

The agenda of the meeting is the, planning, improvement, reconstruction; rehabilitation of ADB funded roads, drains of the Pourashava under UGIIP-III.

The Regional resettlement Specialist (UGIIP-III) briefed the participants regarding the goals and objectives of the projects. And also briefed safeguard issues relating public disturbance during construction period and also probable mitigation measures in view of ADB guideline of safeguard.

They raise the following issues for mitigation. During open discussion session, participants raised following questions, queries and suggestions:

 Ensure timely completion of the civil work  Payment modalities of the losses incurred by the sub projects.  Positive regarding the development activities through the proposed Sub-Projects but avoid disturbance of pedestrians and vehicle by create alternative roads during construction and rehabilitation work.  Main concern of the participants is the quality of the construction work  The authority should not disturbing livelihood of low income group of the Pourashava  Ensuring proper safety measures during construction period

The meeting concluded with thanks from the chair for participating beneficiaries and users in the meeting. Photographs showing consultation meeting, as below:

88

Attendance Sheet

89

.

Pablic Conshltaion at Doarpar shop (ward -08) at Magura Pourashava on 19 -10-2016

90

Key Issue Discussion

SL Issues Discussed Major Findings No. 1 Purpose of the The consultant describes the purpose the consultation consultation meeting and meeting. The main focus was improvement of roads and scope of Sub-project drains of different areas of the Pourashava. The ADB is the under UGIIP-III. Project main donor of the project. Project beneficiaries should be beneficiaries should be included for control monitoring work. included for control monitoring work. The MDS consultants of UGIIP-III visited the all subprojects under UGIIP-III to Physically observe is there any IR impacts existing with the ROW and other relevant activities as per donor requirements and ADB SPS 2009. 2 Road drainage schemes All roads and drains construction/ improvement activities of social safeguard & IR the subproject will be done on the existing ROW of the issues. roads. 3 Local People opinions It is necessary to involve the local people during the /feedback on different construction to ensure the quality and monitoring of the social issues &concerns works and inform to Pourashava authority the progress of benefits etc. works and other information relevant to the construction. 4 Existing situation of the At some points the road is very narrow and at other points feeder road needs to be the bends and curves need to be straightened, people on improved both sides promised to sacrifice a part of their land if required to make the road wide and straight enough. The construction of roads will improve communication and will provide access to markets, business centre, health centers, etc. It will also reduce the transport cost. 5 Service of the Existing roads and drains should be maintained regularly Pourashava and its and properly and drains should be cleaned regularly to keep quality them free from clogging. There is a need for more drains.

6 Information dissemination The consultants described the purpose of the consultation about the Sub-project & meeting. The main focus was improvement of roads and its scope. drains at different areas of the Pourashava. The ADB is the main donor of the Project. Project beneficiaries should be included for control monitoring work during the construction. After construction of existing roads and widening of roads present situation will be improved.

8 How the better road The better road condition will greatly ease the pain of communication will bring present suffering in movement on the road. Business, better scopes for the education and health will be highly benefited and so community. will be people’s overall wellbeing.

91

SL Issues Discussed Major Findings No. Poor women ponder over sunning their parboiled paddy on the medaled road and many poor men are planning to buy rickshaw or van to ply on the improved road and make a good fortune of its development. 9 Opinion of the local Local people of the area need road very much. There will people regarding be neither any acquisition of land nor any possibility of improvement of existing demolition boundary walls, fences, trees. Improved road road and the areas as a condition will remove water logging during wet season whole. Drainage system needs an outlet to another direction, not to end in the existing pond or private land. The alignment of the proposed drain will move toward the bridge and would not create any water pollution in the ponds. 10 Willingness to support Willingness to provide tiny area of land, cut trees, ruin the project. homesteads & shops’ fences for the construction work have been discussed with the participants. They unanimously gave their consent for this.

The community is very eager to extend their all kinds of support for implementing the project.

92

IX. Appendix 2: Involuntary Resettlement Impact Assessment Checklist (Magura Pourashava)

Note: This is an expanded checklist based on ADB IR Impact Assessment Checklist. The modifications are indented to facilitate quick IR assessment by PIUs of a proposed Sub-Project. The checklist may be modified as deemed necessary during project implementation

A. Introduction

Each Sub-Project/component needs to be screened for any involuntary resettlement impacts which will occur or have already occurred. This screening determines the necessary action to be taken by the project team/design consultants.

B. Information on proposed scheme/Sub-Project: a. District name: Magura. b. Location: Magura Pourashava (District H.Q) c. Proposed scheme considered in this checklist: (check one) x roads slaughterhouse x drainages market water supply community center/auditorium solid waste management bus and truck terminals sanitation river ghats (toilets, septage management, etc.) Others (please specify) street lighting C. Screening Questions for Involuntary Resettlement Impact

PDP:R-

Involuntary Resettlement Not Yes No Remarks Impacts Known

Will the project include any X Construction/Reconstruction physical construction work? 37 roads & 03 drains

Does the proposed activity X include upgrading or rehabilitation of existing physical facilities?

A. Land (not applicable for public ROWs)

1. Ownership of land known? n/a n/a (if yes, check appropriate)

___ government

93

Involuntary Resettlement Not Yes No Remarks Impacts Known

___ private

___ trust/community

___ traditional (IPs/tribal)

__X_ Others

Roads and Drains

2. Land purchase/acquisition (answer required even for land donation and/or negotiated land purchase)- Not applicable a. permanent (owner/s required X (if yes, provide purpose) to transfer ownership/rights to Pourashava) b. temporary (owner/s retain X (if yes, provide purpose) rights/ownership)

c. not required X (check appropriate)

__X_ land owned by Pourashava

___ land owned by other government agency

___ proposal will not require land (scheme will be along right of way or existing facility)

3. Current usage of the land X if yes, check as appropriate: known? ___ agricultural

___ residential

___ commercial/business

___ community use

__X_ vacant/not used

94

Involuntary Resettlement Not Yes No Remarks Impacts Known

___ private access road

___ others (specify)______

4. Are there any non-titled X (if yes, provide description) people who live or earn their livelihood at the site/land?

5. Are there any existing X structures on land?

(if yes, complete the following Not information) applicable

- Residential X (if yes, provide number)

- Business/shops/stalls X (if yes, provide number)

- Fences X (if yes, provide description – brick, bamboo, wired, etc.)

- Water wells X (if yes, provide number)

- Sanitation facility X (if yes, provide description)

- Others (specify) X (if yes, provide description) ______

6. Are there any trees on land? X (if yes, provide number)

7. Are there any crops on land? X (if yes, provide if perennial or seasonal)

8. Will people lose access to: X

- any facility X (if yes, provide description)

- services X (if yes, provide description)

95

Involuntary Resettlement Not Yes No Remarks Impacts Known

- natural resources X (if yes, provide description)

9. Will any social or economic X activities be affected by land use-related changes?

10. Are any of the affected X (if yes, provide description) persons (AP) from indigenous or ethnic minority groups?

B. Linear Works

1. Within public RoW? X

2. Structures on RoW? X (applicable to full or partial parts, applicable to permanent/semi-permanent structures)

- Residential X

- Commercial/business/stalls X

- Fence/boundary walls X

- Sanitation facility X

- Community facility X

- School/educational facility X

- Religious structure X

- Service provision (light poles, X water wells, etc)

- Others (specify) X

3. Any mobile vendors/hawkers X using RoW?

96

Involuntary Resettlement Not Yes No Remarks Impacts Known

4. Will there be loss of X agricultural plots?

5. Will there be loss of trees? X

6. Will there be loss of crops? X

5. Will people lose access to:

- any facility X (if yes, provide description)

- services X (if yes, provide description)

- natural resources X (if yes, provide description)

6. Are any of the affected X (if yes, provide description) persons (AP) from indigenous or ethnic minority groups?

97

D. Attachments

1. Sub-Project with land requirement: Not applicable

a. Photograph/s of site/s: not applicable

b. Photograph/s of existing structure/s (permanent/semi-permanent): not applicable

2. Sub-Project along ROWs:

a. Photograph/s of each alignment (chain age wise at least 200 meters): not applicable

B. Photograph/s of existing structure/s (permanent/semi-permanent): not applicable

C. Photograph/s of trees/crops: not applicable

Prepared by: S.B.I.M. Safiq-ud-doula Verified by: Mr. Md. Abdul Karim

Signature: Signature:

Name: S.B.I.M. Safiq-ud-doula Name: Md. Abdul Karim

Position: Regional Resettlement Position: Deputy Team Leader Specialist UGIIP-III UGIIP-III

Date: 23th October 2016 Date: 23th October 2016

98

______

THIS PORTION IS FOR PMU AND MDSC SAFEGUARD TEAM USE ONLY

Date Checklist Received:

Database/Record Number:

Assigned category and further actions __x_ Category C

___ Category B (tentative)

_____ for verification of land purchase/acquisition

_____ for verification of land donation

_____ for verification of non-land donation

_____ for verification of voluntary resettlement

___ Category B

Assessed by: S.B.I.M. Safiq-ud-doula Noted by: Mr. Md. Abdul Karim

Signature: Signature:

Name: S.B.I.M. Safiq-ud-doula Name: Mr. Md. Abdul Karim

Position: Regional Resettlement Specialist Position: Deputy Team Leader

UGIIP-III UGIIP-III

Date: 23th October 2016 Date: 23th October 2016

99

X. Appendix 3: Indigenous People Check List/Small Ethnic Communities (SEC) Impacts

Introduction:

1. Each project/Sub-Project/component needs to be screened for any indigenous people impacts which will occur or have already occurred. This screening determines the necessary action to be taken by the project team.

B. Information on project/Sub-Project/component: a. District name: Magura

b. Location (km):_Magura Pourashava District Headquaters (H.Q). c. Civil work dates (proposed): July 2016 June 2017

d. Technical description: The Sub-Project contains 37 roads and 03 (Three) drain. The components of the Sub-Project will involve schemes of improvement/rehabilitation of 47.219 kilometers (km) of existing roads, and construction of 0.858 km of drainage in phase-2 of UGIIP- III.

Screening Questions for Indigenous People/SEC Impact

KEY CONCERNS NO NOT (Please provide elaborations YES Remarks KNOWN in the “Remarks” column) A. Indigenous Peoples/SEC Identification 1. Are there socio cultural groups present in or using the X project area who may be considered "tribes" (hill tribes, scheduled tribes, IP/SEC), "minorities" (ethnic or national minorities), or "indigenous communities"? 2. Are there national or local laws or policies as well as X anthropological researches/studies that consider these groups present in or using the project area as belonging to "ethnic minorities," scheduled tribes, IP/SEC, national minorities, or cultural communities? 3. Do such groups self-identify as being part of a distinct X social and cultural group? 4. Do such groups maintain collective attachments to X distinct habitats or ancestral territories and/or to the natural resources in these habitats and territories? 5. Do such groups maintain cultural, economic, social, and X political institutions distinct from the dominant society and culture? 6. Do such groups speak a distinct language or dialect? X

100

KEY CONCERNS NO NOT (Please provide elaborations YES Remarks KNOWN in the “Remarks” column) 7. Have such groups been historically, socially, and X economically marginalized, disempowered, excluded, and /or discriminated against? 8. .Are such groups represented as "indigenous X peoples,""ethnic minorities," "scheduled tribes," or "IP populations" in any formal decision-making bodies at the national or local levels?

B. Identification of Potential Impacts 9. Will the project directly or indirectly benefit or target Y indigenous peoples? 10. Will the project directly or indirectly affect indigenous X peoples' traditional socio cultural and belief practices (e.g.child-rearing, health, education, arts, and governance)?

11. Will the project affect the livelihood systems of X indigenous peoples (e.g., food production system, natural resource management, crafts and trade, employment status)? 12. Will the project be in an area (land or territory) X occupied, owned, or used by indigenous peoples, and/or claimed as ancestral domain? C. Identification of Special Requirements Will the project activities include: 13. Commercial development of the cultural resources X and knowledge of indigenous peoples? 14. Physical displacement from traditional or customary X lands? 15. Commercial development of natural resources (such X as minerals, hydrocarbons, forests, water, hunting or fishing grounds) within customary lands under use that would impact the livelihoods or the cultural, ceremonial, and spiritual uses that define the identity and community of indigenous peoples? 16. Establishing legal recognition of rights to lands and X territories that are traditionally owned or customarily used, occupied, or claimed by indigenous peoples? 17. Acquisition of lands that are traditionally owned or X customarily used, occupied, or claimed by indigenous peoples?

101

Indigenous People/SEC Impact

After reviewing the answers above, executing agency/safeguard team confirms that the proposed subsection/ section/Sub-Project/component (tick as appropriate):

[ ] has indigenous people (IP)/SEC impact, so an SECDP or specific SEC action plan is required.

[ ] has No IP/SEC impact, so no SECDP/specific action plan is required.

Prepared by: S.B.I.M. Safiq-ud-doula Verified by: Mr. Md. Abdul Karim

Signature: Signature: Name: S.B.I.M. Safiq-ud-doula Name: Mr. Md. Abdul Karim Position: Regional Resettlement Specialist UGIIP- Position: Deputy Team Leader UGIIP-III III

102

XI. Appendix 4: Sample Grievance Registration Form

The Project welcomes complaints, suggestions, queries and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing ‘CONFIDENTIAL’ above your name. Thank you.

Date Place of registration

Contact Information/Personal Details

Name Gender * Male Age

Home Address Place Phone no. E-mail Complaint/Suggestion/Comment/Question Please provide the details (who, what, where and how) of your grievance below:

If included as attachment/note/letter, please tick here:

How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY

Registered by: (Name of Official registering grievance)

Mode of communication:

Note/Letter E-mail Verbal/Telephonic

Reviewed by: (Names/Positions of Official(s) reviewing grievance)

Action Taken:

Whether Action Taken Disclosed:

Yes ( )

No ( )

Means of Disclosure:

103

104

XII. Appendix 5:: Land Ownership Certification of MaguraPourahsava

105

XIII. Appendix - 6 : Photographs of alignments of proposed roads and drains of Magura Pourashava, Phase 2, UGIIP-III.

Rehabilitation & Improvement of Wazid Ali Road by DBC Rehabilitation & Improvement of Abalpur Purbapara Road by DBC (PDP-9, 20) (PDP-11)

Improvement of Abalpur Charpara Road by DBC (PDP-03) Rehabilitation & Improvement of Defulia Napithpara Road by DBC (PDP-05)

Rehabilitation of Sajiara Road (Ward No.-01) (PDP-22) Improvement & Rehabilitation of Choto falia Road by DBC (PDP- 6,7&27)

106

Improvement of Kadirabad Road by DBC (from Patthra Rehabilitation of Road by DBC from Magura-Jhenaidha Road more) (PDP-22) (Ward No.-08)

Rehabilitation of Doarpar Road by DBC (from Magura- Construction of Road by RCC (CARE Road) (PDP-179 & 185) Sreepur Road) (TLCC)

Improvement of Road by DBC from Magura-Sreepur Rehabilitation & Construction of Road by DBC & RCC (Amtola Moulovibazar (PDP-162) Mosque) (TLCC)

Improvement of Road by DBC (Seikpara Mosque) (TLCC) Improvement of Road –Babur Hat Road by DBC (PDP-154)

107

Improvement of Road Niznanduah pubbo para Road by RCC (Bittipara (PDP- 141 & 150) Improvement of Road by DBC from Molla Para Mosque to Bittipara (PDP-141 & 150)

Rehabilitation of Road by DBC from Bepari Para (PDP-142) Rehabilitation of Road by DBC from Bepari Para Godown (PDP- 146)

Rehabilitation of Road by DBC Patia Saddoya Road from Improvement of Road by RCC from Molla Para Mosque (PDP-94 Chaulla Bus Stand More (PDP-101, 102 & 112) & 109)

108

Construction of Molla Para Road by RCC from Roise Improvement of Kukna Road by DBC to Siraz Chairman (PDP-36) Shekh to Molla Para Road (PDP-107)

Construction of West Stadium Para RCC Road (Ebadot Re-habilitation & Improvement of Vitasair Ghoramara Road by Asia Mohila College) (PDP-41) BDC from Magura-Jessore Road (PDP-64)

Rehabilitation of Caximkandor road by DBC from Magure- Improvement of connecting road by DBC from Nal Mondin Road Dhaka road (PDP-136) to Magure-Sreepur Road (TLCC)

109

Rehabilitation of Boranatail Road by DBC Magura-Dhaka Re-habilitation & Construction of College Para road by DBC & Bus Terminal (PDP-138) RCC (TLCC)

Improvement & College Para Road (Chandu Rehabilitation & Improvement of Road (Azgar Ali to Wazad Ali Commissioner) (PDP-223 & 225) Road) (PDP-12)

Rehabilitation of Abalpar khondokar Para Road by DBC Rehabilitation of Road from Miran Bottola to Dania Bridge (TLCC) (PDP-18)

110

Construction of Doni-Kalkalia Para Road by RCC from Improvement of Road by DBC from Magura-Sreepur road (PDP- Shibrampur (PDP-178) 169 & 170)

Rehabilitation & Construction of Tali Para Road from Abu Improvement of Road by DBC Magura-Sreepur Road (Hakim Ishaq Road (PDP-96, 110 & 111) Biswas) (PDP-97 & 98)

ehabilitation & Construction of Vaina Santi bag Road by DBC Construction of RCC drain from Hazari More Shop of Millon to & RCC from Magura-Jessore road (PDP-92) Seikpara Mosque (PDP-45)

111

Construction of RCC drain from Akbar to existing drain at Construction of RCC drain form Bus Terminal to Box culvert Niznanduall (TLCC) (Pamanduali) (TLCC)

112