Environmental Monitoring Report
Project Number: 40515-013 Annual Report June 2015
2696-BAN(SF): Sustainable Rural Infrastructure Improvement Project
Prepared by Local Government Engineering Department (LGED) for the People’s Republic of Bangladesh and the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Table of Contents 1. INTRODUCTION ...... 4
2. PROJECT LOCATION AND COMPONENTS ...... 4
3. ENVIRONMENTAL RESPONSIBILITIES AND INSTITUTIONAL SET UP ...... 5
4. PROJECT STATUS (CIVIL WORKS AND EMP IMPLEMENTATION) ...... 6
5. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS...... 7
6. ENVIRONMENTAL MONITORING REQUIREMENTS ...... 10
7. ENVIRONMENTAL MITIGATION MEASURES IMPLEMENTATION ...... 11
7.1 INVESTIGATION RESULT ON EMP MONITORING BY DIRECT SITE VISITS ...... 11
8. KEY ENVIRONMENTAL ISSUES AND ACTION PLAN ...... 11
8.1 KEY ISSUES IDENTIFIED ...... 11
8.2 ACTION PLAN OF ENVIRONMENTAL MITIGATION AND MONITORING IN BETWEEN JUNE 2014 AND AUGUST 2014...... 11
9. CONCLUSION AND RECOMMENDATION...... 13
Table 1: Environmental Responsibility Matrix ...... 6
Table 2: Compliance with National Laws ...... 8
Table 3: Compliance with Environmental Considerations of Loan Agreement...... 9
Table 4: Sampling Program Summary ...... 10
Table 5: Action Plan for Environmental Mitigation and Monitoring ...... 12
Table 6: Recommendations against identified problems ...... 15
1
Appendix 1: Specific sub-project wise monitoring status or compliance ...... 16
Appendix 2: EMP – Monitoring Compliance Check List and Overall status of the mitigation measures’ implementation against the impacts occurred from sub-project activities; ...... 36
Appendix 3: Environmental Management Plan and Environmental Monitoring Requirements ...... 41
Appendix 4: Consultant site visit reports ...... 48
2
ABBREVIATIONS AND ACRONYMS
ADB Asian Development Bank ADF Asian Development Fund BOD Biochemical Oxygen Demand BOQ Bill of Quantities BWQS Bangladesh Water Quality Standard CO Carbon Monoxide COD Chemical Oxygen Demand DO Dissolved Oxygen DOE Department of Environment DPP Development Project Proforma/Proposal EDD Environmental due diligence EMP Environmental Management Plan EMR Environmental Monitoring Report EMWS Environmental Management Implementation Works Schedule FC Faecal Coliform FSE Field Supervision Engineer GCC General Conditions of Contract GOB Government of Bangladesh IA Implementing Agency IEC Impacted Environmental Components NGO/INGO Non‐Governmental Organisation PCC Particular Conditions of Contract PD Project Director RDPP Revised Development Project Proforma/Proposal
PM10 Particulate Matter (≤ 10 micrometers or less) PPE Personal Protective Equipments RP Resettlement Plan SIEE Summary Initial Environmental Examination TDS Total Dissolved Solids TP Total Phosphates TSS Total Suspended Solids WHO World Health Organisation
3
1. INTRODUCTION Back Ground/Context of the Monitoring Report:
1. Majority people of Bangladesh live in the Rural area of Bangladesh. Rural area of Bangladesh has a significant contribution to the GDP of Bangladesh. But, rural area of Bangladesh is lacking of sufficient infrastructure. So, the Government of Bangladesh has given high priority for the infrastructure development of the rural areas. The underpinning strategic thrust and target of infrastructure is to improve the socioeconomic status and quality-of-life of the rural people. To achieve the targets, LGED has formulated the Sustainable Rural Infrastructure Improvement Project (SRIIP) aiming at the development of the rural infrastructure, which is also the main objective of the project. This includes the development of all-weather Upazila and Union roads to provide access to Growth Center Markets (GCMs) and Rural Markets (RMs) including providing better access to markets and social services, and the development of the necessary infrastructure in the GCMs/RMs to offer better trading facilities and the environment.
2. The Project aims at reducing poverty in the rural communities in 21 districts in Bangladesh through providing them better access to economic opportunities and social services. In addition, the Project will help improve the communication network to facilitate production and marketing of agricultural produce; The Project has an important objective to improve the existing environment by planting and maintaining trees along the roads and building with more effective drainage infrastructure & proper waste management system.
3. Environmental Monitoring is a mandatory one to check the likely environmental stresses that may happen due to the project interventions and to identify the likely potential environmental impacts of the sub-projects implementation. The environmental monitoring system seeks to oversee the performance obligations of the project authority with a view to ensure that there is no deviation from the contract. This also helps to assess the performance against the set standards. It also describes the compliance status of EMP and provides remedial measures and an action plan for taking corrective measures against defaults, especially when performance standards are not fulfilled.
4. The purpose of this Environmental Monitoring Report is to satisfy the environmental safeguard requirements of the Government of Bangladesh and the development partners (Asian Development Bank and KfW) as well as to fulfill the requirements written in the loan document of the Project. This report has been prepared on the status of compliance of the implemented environmental related works prescribed in the EMP. This report has been conceived based on the observations during the field visits performed by the Environment and Climate Change Specialist, ISMC and a review of the inspection reports of the Field Supervision Engineer. These reports relate to the monitoring carried out by the field office of the environmental safeguards during the different phases of the sub-project works. This monitoring report covers the period July, 2014 to June, 2015.
2. PROJECT LOCATION AND COMPONENTS
5. The project area covers 21 districts of Rangpur, Rajshahi & Khulna Division encompassing 140 Upazilas. All the 8 (Eight) Districts of Rangpur Division are included
4
in the SRIIP area and these are Panchagarh, Thakurgaon, Nilphamari, Dinajpur, Rangpur, Gaibandha, Kurigram and Latmortirhat; 7(Seven) Districts under the Rajshahi Division are included in the project such as Rajshahi, Natore, Joypurhat, Bogra, Naogaon and Chapai Nawabgonj and also 7(Seven) Districts in the Khulna Division have been included in the project areas and these are Kushtia, Chuadanga, Meherpur, Jessore, Jhenidah, Narail and Magura. 6. The components of the project include various physical activities such as the improvement of Upazila (700km) & Union roads (100 km) including pertaining structures like bridge and culvert (3270 m) additions; the improvement of Growth Centers (GC) /Rural Markets (RM) including the piloting of rural water supply and renewable energy (98 No.) and Union Parishad (20), road side tree Plantation (400 km). Besides, there are two consultancy services, one is Institutional Support and Monitoring Consultancy (ISMC) and another is Design and Supervision Consultancy.
3. ENVIRONMENTAL RESPONSIBILITIES AND INSTITUTIONAL SET UP
7. LGED is the executing agency of the project, headed by a Project Director. LGED is one of the largest Engineering Department in Bangladesh having offices with sufficient skilled and experienced manpower at every Upazilla (subdistrict) and District level. Hifab International is the lead firm for the ISMC (Intuitional Support and Monitoring Consultancy), and Mott MacDonald for the D & SC (Design and Supervision Consultancy) services.
The two consultancy services are leaded by two Team Leaders, one for ISMC and another for D&SC, who are fully responsible for the implementation of the project works under the Contractual Agreement.
The Environment and Climate Change Specialist working under the ISMC services, is responsible for overseeing and ensuring the Environmental monitoring safeguards issues of the project through direct field observation and reviewing the field reports.
The overall responsibilities of the persons for the environmental monitoring during the various phases of the project are shown in Table 1 below.
5
Table 1: Environmental Responsibility Matrix
Phase Agency Contact Responsibility Deliverables Executing Project Preparation of Agency: LGED Director EMP. Incorporation of EMP clauses into EMP, Bidding Design/ Preconstruction D&SC Consultant: bidding Documents Mott MacDonald Team Leader documents. & Associates Reporting to ADB/KfW. Executing Project Agency: LGED Director Monitoring of EMP Implementation/Construction Implementation An annual report implementation phase Consultant: Hifab to ADB/KfW. and Mott Team Leaders and reporting to MacDonald & ADB/KfW. Associates
Monitoring of Operation / Post Executing Project An annual report EMP Construction Agency: LGED Director to ADB/KfW. Implementation
4. PROJECT STATUS (CIVIL WORKS AND EMP IMPLEMENTATION)
• The average cumulative physical progress of civil works of the project is about 51.61%. Civil works of the most of the sub-projects are being carried out according to the set schedule and specifications. But the construction works of some sub-projects have not been started yet. The nos. of the completed subprojects are limited.
• As the first quarter of the reporting period has fallen in the rainy season, so there have been found not much progress during the reporting period. Most of the construction works especially the bituminous carpeting and bridge construction activities could not undertake due to heavy rainfall in the monsoon.
• Partially compliance to the environmental assessments and safeguards required by the Project, seems to have been applied to all the sub-projects at the outset of the projects. The three quality parameter test; air, noise and water for the sub-projects have not been done yet. In the most cases, the environmental quality tests have been delayed due to the delay in the implementation of the civil works. However, in other cases, the contractors simply signed that they had complied without actually doing so, because they didn’t have the resources in relation to environmental quality tests, they didn’t want to comply, or they did not know how to comply.
• The TL of ISMC with the Environmental Specialist has informed the PD, SRIIP regarding this issue and has requested the authorities to take immediate action with this regard. 6
The PD has issued a remainder letter to the relevant Executive Engineers to sum mon and challenge the contractors regarding their negligence in failing to do the tests mentioned. The contractors have replied against that the facility of air quality parameters test is not available at the District level but the facility of water quality tests is available, with limited parameters.
• However, none of the contractors who have been engaged in the construction works have submitted test results of air, noise and water quality parameters, despite the warning by PD & TL of ISMC. In most of the cases, they replied, “It is in the process of examination”. But this type of reply is not satisfactory because the construction period, for some of the sub-projects, is about to be ended.
• Contractors involved in the implementation of the sub-projects have requested the PD, SRIIP for arranging training on Environmental safeguards. Consequently, the PD has requested the ISMC TL for arranging a ‘Contractors training’ on this issue. Some contractors have also claimed that it is tough to bear the cost of environmental quality parameters tests as the fee of the tests are not included in BOQ separately although they signed on the agreement of the contracts, without understanding the reality on the issue, to comply all safeguards properly. However, owing to giving pressure by PD, SRIIP to the contractors to comply all the environmental safeguards especially on the environmental quality test reports, it is assuming that the said test results compliance would be ensured from next quarters of the year’14. On context of civil works, overall EMP implementation is under about to fair position of the grade shown in the Appendix-1. Scheme wise name, progress and compliance status are stated in details in Appendix-1 attached here with the report.
5. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS
• Compliance with National Environmental Laws, ADB guidelines, LGED guidelines, Environmental Assessment Review Framework etc. have been observed while assessing the sub-projects in all SRIIP activities in the field. These are stated below-
A. Compliance with National Environmental Laws:
• The environmental policies written in the laws of Bangladesh are being utilized to reduce the negative impacts and promote positive enhancement of infrastructure development projects. These relate closely to the National Environmental Policy 1992 that was established considering Agenda 21 of the Rio Conference as well as subsequent enactments of the Bangladesh Environmental Conservation Act (BECA) 1995 and Bangladesh Environmental Conservation Rules (BECR) 1997. As the SRIIP project has been categorized under the B category according to the ECR’97, an IEE report is needed to submit to the DOE for environmental clearance. Accordingly, the project has followed this requirement and in this context has already got environmental clearance from the DOE. However, the compliance with the national laws is as follows (Table-2):
7
Table 2: Compliance with National Laws
Environment Compliance Performance Policy/Rule Requirement
Bangladesh Requires The environmental clearance for the Environmental Environmental project was obtained from the DOE Conservation Act Clearance (EC) from on 6th April,2014 (BECA) 1995 and DOE Bangladesh Environmental Conservation Rules (BECR) 1997
B. Compliance with ADB Guidelines:
• According to the ADB’s Safeguard Policy Statement (2009) and environmental guidelines of ADB, the project falls under ‘Category B’ and hence an IEE is sufficient to meet the environmental requirements. An overall IEE report including the EMP for the project has been prepared by the Consultant (Environment and Climate Change Specialist) of ISMC and it has been funded by ADB/KfW.
C. Compliance with the Environmental Assessment Review Framework (EARF):
• EARF, prepared in 2011 has contained different clauses regarding the compliance with ADB Safeguard Policies. All standard requirements for environmental assessment for sector loans are being applied in accordance with ADB’s `Environmental Assessment Guidelines’. Since the project has very limited potential for adverse environmental impact (soil erosion, local drainage and flooding conditions), a full-blown EIA is not required, thus only an IEE is needed. In the task of compliance monitoring and supervision, the environmental assessment requirements and safeguard policies of ADB have been fully conformed to through the implementation of EARF.
• The implementation period is five years and it is recommended that the construction work involved in all the sub-projects should be closely monitored in order to evaluate the project’s efficiency and effectiveness. To get this, regular reviews are being carried out by ADB and KfW on a quarterly basis.
D. Compliance with Loan Agreement: • Schedule 5 of the Loan Agreement has stipulated environmental considerations. The project’s compliance with the contractual environmental safeguards requirements are stated below (Table-3).
8
Table 3: Compliance with Environmental Considerations of Loan Agreement
Loan Condition Compliance by the project
Complied. Screening the sub-projects to determine any Each subproject was screened before the potential environmental impacts, risks and their commencement of the implementation of significance. construction activities of the project. Complied. Initial Environmental examination (IEE) including If an environment impact assessment or initial Environmental Management Plan (EMP) has been environmental examination is required for any prepared for the Project. The SARs (Subproject Subproject pursuant to the EARF, PMO will Appraisal Report) have been prepared at the initial conduct IEE. stage of the project and has been sent to ADB/KfW for their approval which included details on IEE. The Subprojects have been designed, constructed, operated, and maintained in accordance with the applicable local Complied. environmental laws, rules, regulations and the Safeguard Policy Statement.
The environmental management plan is Complied. implemented in accordance with its terms so that The recommendations of IEE & EMP including EMP all adverse environmental impacts during budget (given gross allocation for environmental construction and operation of the Subprojects are input but allocation is not specific environmental mitigated; and if there is any events of the components wise) have been incorporated into the unanticipated adverse environmental impacts, construction contract document of the Project. such impacts are to be reported to ADB.
9
6. ENVIRONMENTAL MONITORING REQUIREMENTS
• One of the instruments of Environmental Monitoring Requirement is the EMP. This is a process that includes a Monitoring Compliance Check List for the Design, Construction and Operation phases of the project. Environmental Monitoring Compliance Data has been collected from different fields of the sub-projects using the EMP–Monitoring Compliance Check List. This has been collected by the Field Supervision Engineers who are involved in supervising all the construction works of the sub-project. EMP–Monitoring Compliance Check List as a sample basis is stated in Appendix-2. The SRIIP project has 246 sub-projects that are being implemented in different time based on its individual situation of the works. The specific sub- project wise monitoring status or compliance is stated in Appendix-1.
• The environmental monitoring requirements are presented in the EMP (Appendix-3) and the EMP’s environmental monitoring table (EMoT) is also described in the same Appendix. This plan considers the scope of monitoring; monitoring parameters; time and frequency; the outputs required and implementing and supervising agencies.
• Sampling Program is another monitoring requirement which is important to determine compliance of the sub-project works. The extent of the impacts of environmental pollution related to surface water, ground water, air quality and noise can be determined in quantitative terms by sampling a range of related parameters. Based on these results, the mitigation measures provided for in the EMP can be adjusted accordingly. Summary of the sampling program is mentioned in table-4.
Table 4: Sampling Program Summary
Construction Operating Period SL Impact During Parameter N Frequency Duration Frequency Years ph, TSS, BOD , DO, TP, Oil & 1 Surface Water quarterly 3 yrs 2X/yr. 1,3,5 5 grease, FC Not pH, TSP, As, Fe, Mn, S, Cl, 2 Ground Water 2X/yr 3 yrs 0 needed FC TPM, SO NO CO, Dust & 3 Air Quality quarterly 3 yrs 2X/yr 1,3,5 2, 2, Soot 4 Noise & Vibration quarterly 3 yrs 3X/yr 1,3,5 dBA
• The sampling follows the methodology provided in the Bangladesh national standard methods for monitoring pollutants. Other associated standards are national environmental quality standards and pollutant emission standards.
10
7. ENVIRONMENTAL MITIGATION MEASURES IMPLEMENTATION • The implementation status of the mitigation measures during the pre-construction stage of the project was satisfactory. Checking of climate change resilient infrastructure design in all subprojects in association with DTL of D & SC of the project has been done effectively during design and pre-Construction Stage. In this stage, PMO of the project and Executive Engineers of the respective District have checked the present sub-projects environmental settings and identified the problems that might be occurred during construction and selected mitigation measures with implementation procedures. Prior to the subjects on Natural Environment and Ecological Environment, probable Environmental Pollution and Health and Safety issues in relation to construction of the sub-projects are considered to identify the environmental impacts and find out the best implementation procedure of probable mitigation measures. In construction and operation stages of the project, overall position of the mitigation measures’ implementation against the impacts that might be occurred from sub-project activities is also stated in Appendix-2. It could be mentioned that, most of the construction works of the sub- projects have stopped due to heavy rainfall in the month of June-July-August. Afterwards heavy rainfall, construction of the infrastructures of the sub-projects will be stared at full strerch.
7.1 INVESTIGATION RESULT ON EMP MONITORING BY DIRECT SITE VISITS
• For EMP monitoring, the construction site visits were held randomly at different times by the Environment and Climate Change Specialist and the investigation results are stated in Appendix-4
8. KEY ENVIRONMENTAL ISSUES AND ACTION PLAN
8.1 KEY ISSUES IDENTIFIED • Based on the results of monitoring and inspection, there are no significant environmental issues that have been raised during the reporting period. However, there are a number of areas where more action needs to be taken by the Contractor to ensure full compliance with the EMP.
8.2 ACTION PLAN OF ENVIRONMENTAL MITIGATION AND MONITORING IN BETWEEN July 2014 AND June 2015.
• It is expected that further substantial increase in construction activities will occur from July 2015.The focus of environmental monitoring will be on the following aspects: (a) better implementation of environmental management plan and mitigation measures to minimize the negative environmental impact of the work under construction; (b) Continue to improve water, air and noise quality sampling and analysis of the project by adhering to specific instructions provided by the monitoring personnel, FSE (Field Supervision Engineer)/ ECCS (Environmental and Climate Change Specialist), PMO (Project Management Office). Monitoring personnel should monitor, with particular care, the causes of non-compliance and remediation measures to secure safe water supply, air quality and acoustic environment; (c) Ensure soil erosion protection initiatives especially for the road and the bridge sites; and (d) Strengthen the implementation of the Health and Safety aspects of the EMP for the entire workforce. • FSE intends to strictly enforce the requirements mentioned above and with the help of LGED relevant personnel will be able to demonstrate a substantial improvement by the Contractor over the remaining periods of the project up to June 2016.
11
• The Health and Safety issues will need be continued and on-going attention with all of the site activities of the sub-projects. The action plan for Environmental Mitigation and Monitoring is stated in Table 5 and will be expanded on a needs basis by the contractor.
Table 5: Action Plan for Environmental Mitigation and Monitoring
Environmental Action Required Timeframe Implemented Supervision Parameter by by Landscape and Cleaning up of various work areas along the site as August 2014 to LGED through FSE/XEN future visual road, bridge and market development works proceed completion in Contractors intrusion to enable slope protection works and grassing, etc. to Nov 2015 be installed and become stabilized and minimize visual intrusion. Tree Felling Ensure trees felled are correctly recorded to enable August 2014 to LGED through FSE/XEN compensation if required to be made. Initiate planting completion in Contractors of trees along lower slope of the road where Nov 2015 completed to ensure sufficient time for their establishment. Fisheries, Fish Initiate consultation with relevant government April 2014 to LGED through FSE/XEN habitat and water agencies to obtain details relating to fisheries in the completion in Contractors courses major project site water reservoir / rivers. Nov 2015 Make appropriate arrangements for restoration of borrow pits for use as fish ponds wherever possible and where requested by local communities. Wildlife Initiate consultation with relevant government April 2014 to LGED through FSE/XEN agencies to obtain relevant details of wildlife in the completion in Contractors sub-project areas. Nov 2015 Surface Water Execute sampling in line with sampling program April 2014 to LGED through FSE/XEN Ground Water prescribed by PMO which the contractors have completion in Contractors agreed to implement; then present results with February 2016 Air Pollution analysis indicating impacts (if any) and mitigation Noise measures are needed to submit to PMO. Soil Sampling should be carried out in the presence of Contamination FSE with details of locations provided on plans and followed the standard procedure of sampling. Workforce Camp Ensure adequate waste bins are provided at camps April 2014 to LGED through FSE/XEN Conditions with regular disposal to suitable locations. Initiate completion in Contractors regular collections and disposal of garbage from February 2016 around camp sites and ensure the areas that may be remained hygienic. Provide safe potable water supply at all times in workforce camp. Construction Ensure all solid wastes at works sites and yards are April 2014 to LGED through FSE/XEN Waste contained in legal manner and then correctly disposed completion in Contractors Management of in the legal areas or land fields. May 2016 Personal Health Maintain effective operation and cleaning of sleeping, April 2014 to LGED through FSE/XEN and Safety cooking, washing and toilet facilities in camps. completion in Contractors Ensure potable water supply and conduct tests for April 2016 verification. Ensure First Aid Equipment and Medical Facilities are readily available at all times. Initiate further training and awareness sessions on the use of PPE for staff as well as labors and take steps to ensure these are used correctly at all times on site. Vector Borne Initiate treatment of abandoned borrow pits and clean April 2014 to LGED through FSE/XEN Diseases up areas where water is logged to reduce risks for completion in Contractors 12
Environmental Action Required Timeframe Implemented Supervision Parameter by by breeding of mosquitoes. Record of regular inspections April 2016 provided.
• For the enforcement of the environmental safeguard issues, the Contractor will have to undertake all activities focussing on the environmental concerns and to be documented through checklists, reports, test results and photographs as instructed by the PMO. Contractors have been instructed to do the forthcoming construction activities with better quality than done in the past.
• A range of enforcement actions will be implemented by LGED to ensure the contractor’s compliance of required activities which will include: • Issuance of warning letter by the PD, SRIIP for first-time detection of non-compliance including missed deadlines for submission of regular reports and immediate conduct of compliance to compel corrective actions. • FSE will recommend appropriate withholding of payments for recalcitrant/continuing non-compliance that exceeds 30-days from the date of detection. • Recommend stoppage of related works that are contributing to the non-compliance until corrective action are effectively implemented
9. CONCLUSION AND RECOMMENDATION
A. Overall Progress of Implementation of Environmental Safeguard Measures
• With some exceptions, most of the Contractors have followed the environmental safeguards during construction of the sub-projects. But air, water and noise quality tests are pending due to the various reasons which has been mentioned in the previous section of this report titled ‘Project Status. Besides, the results of water quality tests are arriving slowly. Due to lack of awareness, some contractors involved in the construction works have found reluctant to follow the safeguard measures of ECR’97 properly. To enforce the Environmental laws and regulations of Government of Bangladesh and the ADB/KfW guidelines properly, PD and TL of ISMC have issued show-cause letter to the non-complying contractors through respective Executive Engineers on the above discussed environmental issues involved in project works. • As a result of regular environmental monitoring by the Field Supervising Engineer (FSE) of D&SC and the Environment and Climate Change Specialist, ISMC, SRIIP, this have been found that the contractors have commenced to implement the environmental mitigation measures specified in the EMP although there are many areas where further action and improvement could be taken. The abstract of the environmental monitoring are summarized as follows. • The potential environmental adverse impact of the finished item of works especially contiguous to the major watercourses and drainage area of the sub-project area have been minimized ensuring the construction works strictly adhering with the approved design and following the specified construction methods of the road and other infrastructures. Most of the cases, the
13
potential environmental adverse impact of dust arising from earthworks has been minimized through application of the techniques prescribed in the EMP. • In most of the sub-projects, contractors could not carry out the environmental quality test analysis especially for air and noise tests. Earth works and bituminous carpeting are being done slowly. Most sub-projects have stopped this at present due to the heavy rainfall during the monsoon (June, July. and August). Most of the Contractors of the sub-projects have proposed that construction work will be re-commenced after the monsoon period. The water, air and noise quality tests results will be submitted to the PD, SRIIP by Contractors (who will be accessing assistance through DOE and Public Health Dept.) soon after re-commencing their activities in the field. However, more improvement is still needed to execute the monitoring of water and air quality, noise levels completely in line with the Sampling Program so that the impacts on these of the construction activities can be quantified and thereafter minimized wherever possible. • In most of the sub-projects, occupational health safety measures could not be implemented to a satisfactory level. The Environment Specialist and TL of ISMC have requested the PD, SRIIP to take immediate action on the non compliance of the safety measures in the sub-projects at field level. Meanwhile, the PD has issued a warning letter to the Executive Engineers to take action against contractors’ non compliance activities. So, further emphasis is also required on the Health and Safety issues related to the various camp sites and work sites with more training and awareness sessions needed regarding the use of personal protective equipment (PPE) for the workforce. B. Problems Identified and Actions Recommended • The noncompliance activities and problems regarding the implementation of the environmental safe guards identified by Environmental and Climate Change Specialist through direct site visits and monitoring in some District’s sub-projects are stated in the section point of the report 7.1, (details in Appendix-4) . Based on the site surveys and the monitoring of the implementation of the Environmental Safeguards program the relevant recommendations are included below.
14
Table 6: Recommendations against identified problems Recommendation Timeframe Implemented Supervision by by a) The Contractor must ensure that the sampling of the critical parameters for water quality, noise and air quality is carried out fully in line with the Sampling Program so that meaningful By Aug 2014 to results can be obtained enabling further mitigation measures to completion in Contractors FSE be determined and initiated if required. The test results of the February 2016 quantitative environmental quality parameters should be submitted immediately by contractors, those are not done yet. b) The on-site construction supervision and management of the Contractor should be strengthened so that actions taken especially on the issues related to the improvement of health By Aug 2014 to and safety can be maintained and not disappear over time. It is completion in Contractors FSE necessary to increase the events of training and awareness on February 2016 the health and safety issues for the construction workers with regular and repeated fashion presented & delivered by specialized personnel. c) The overall management of field camps and worksite must be By Aug 2014 to further improved in line with the best practices on occupational completion in Contractors FSE health and safety so that these areas of the site can be made April 2016 fully compliant. d) In terms of the measurements of the environmental quality By Aug 2014 to parameters, the contractors need to establish the output completion in Contractors FSE required namely quantitatively credible values. February 2015
15
Appendix 1: Specific sub-project wise monitoring status or compliance
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Appendix 2: EMP – Monitoring Compliance Check List and Overall status of the mitigation measures’ implementation against the impacts occurred from sub-project activities;
Implementation Project Impact Mitigation Measures Details of What work has Outputs/ Implementation/ Stages/ Monitoring Action undertaken/ and Evidence Compliance Status Environmental Undertaken where provided Parameters CONSTRUCTION STAGE 2.1 Natural Environment 2.1.1 Hydrology and Construction of The bridges and Regular site Construction of No records Some roads flood pattern road, market culverts are to be inspection for the infrastructures provided by constructions are structures, culverts designed and works in progress. are taken place Contractor. proceeding as and bridges would constructed properly Review and properly. FSE Site planned, some are create minimal considering climate approval of Drawings for inspection and ongoing and the impact on the local change infrastructure drawings for bridges are the EMP rest is almost hydrology. design requirements. bridges and approved with monitoring complete. Bridge culverts have been standard reports are works will be finalized according procedure. main output. proceeded after to project guideline. rainy season. COMPLIES 2.1.2 Drainage Earthwork activities To deal carefully at Regular site Road FSE Site COMPLIES congestion during construction bridge design and inspections of road construction inspection of the road may not planning stages after heavy rainfall works are reports, letters induce drainage based on and at end of ongoing. The are main congestion except hydrological data. monsoon season. works of bridge evidence. at culvert and Ensure all earthworks and culverts will bridge sites. and bridges are proceed during constructed dry season. according to design Some areas and specifications to have been minimize the rectified to drainage congestion overcome the hazard. drainage congestion. 2.1.3 Erosion and The erosion risk at Regular watering, Regular site Planting and re- FSE Site COMPLIES silt deposition bridge sites and grass turfing and inspections of road vegetation of inspection road slopes is either planting Vetiver/ and bridge sites grass in road reports, letters nothing or minimal. Napier grasses in after heavy rainfall slope where road are main However, erosion rows along the road to identify those is completed are evidence. along the road slopes and bridge areas of erosion being started to slope near to water approaches will that need to be implement. bodies during rainy reduce the soil addressed. season may occur erosion risk. and damage adjacent field crops Construction material for the construction containing fine stage. particles e.g. stone dust will/sand be stored in an enclosure away from water bodies to ensure that sediment laden water will not pollute the aquatic environment.
Earth carrying A professional Regular site Cleanup of No records PARTLY 2.1.4 Landscape: activities requiring landscape could be inspections of all borrow pits & provided by COMPLIES for road employed to create a activities including work sites has Contractor. future visual development will plan for earth fillings works. undertaken FSE Site intrusion affect the landscape beautification. consideration to inspection beauty. landscape beauty. keep landscape reports, letters better. are main evidence.
36
Implementation Project Impact Mitigation Measures Details of What work has Outputs/ Implementation/ Stages/ Monitoring Action undertaken/ and Evidence Compliance Status Environmental Undertaken where provided Parameters 2.1.5 Some contractor The EMWS should be EMWS Most of the Quarterly PARTLY The Environmental does not prepare a submitted by the requirements and cases, EMWS for monitoring COMPLIES Management work plan defining contractors to the preparation in next 12 months reports Implementation details on when Executive Engineer. discussed with could not including the Work Schedule mitigation and LGED prepare. So, it is issue should be (EMWS) monitoring actions Environmental needed to submit submitted by are to take place. Staff to enable immediately. Contractor. Consequently, the updated EMWS to EMP requirements be prepared. will not be implemented properly. 2.2 Ecological Environment If any tree is removed from the road due compensation should An inventory of be paid for removed live trees was Given the trees and planting carried out at the Resettlement Plan smaple The project requires trees at new sites as beginning of the has been made to investigated, it 2.2.1 Tree felling* to not remove any per the MOEF project. It was COMPLIES ensure the appears thah trees for widening (Ministry of envisage that no payment with due no live trees of the road Environment and live trees would compensation. have been cut forest) and LGED be required to be down guidelines. Large cut during the trees should be reporting period. planted on berms and in lower slopes. 2.2.2 Fisheries, Fish Bridge/culverts The bridge Regular inspection Quality and Records of habitat and water construction construction sites on the rivers and quantity of fish meetings & courses activities might across the rivers/ cannels with stocks have been discussions hinder fish canals need to be proposed bridges/ inspected from a provided by movement carefully monitored as culverts and taking sample survey. LGED temporarily. these are migratory initiative to protect Data collected waters supporting the fish habitat. indicates that no important local major negative COMPLIES fisheries. The borrow have affected pits /ponds excavated with the number, for the purpose of quality or filling materials for breeding stock. road could be used for aquaculture or fish stocking to compensate the loss. 2.2.3 Wildlife The terrestrial FSE will record the Site inspection to Inspection, data Quarterly PARTLY wildlife species wildlife those are be observed the collection & monitoring COMPLIES might be disturbed susceptible to wild life should be consultation with reports by FSE due to noise and damage if needed. carried out on relevant vibration at regular basis. stakeholders and construction sites government and tree felling (if agencies any) to cause regarding dislocation of inhibition of wild habitats. No report life migration for was available the development regarding the works have been presence of carried out. threatened or endangered wildlife species at project site. 2. 3 Environmental Pollution 2.3.1 Surface water The surface water Wastes, effluents and Inspections at all Sampling of Records of Water quality test at project site might other contaminant camps sites and water at rivers water sample reports are waiting be polluted due to materials at site major construction and Khals as per results provided to arrive at the faecal, organic and camp/work sites sites in bridges and sampling by the PMO office. The other should be stored, roads on regular program is now Contractor. initiatives have 37
Implementation Project Impact Mitigation Measures Details of What work has Outputs/ Implementation/ Stages/ Monitoring Action undertaken/ and Evidence Compliance Status Environmental Undertaken where provided Parameters contamination. handled, transported basis. Water being done been taken in this Disposed wastes and disposed in quality parameters partially by regards. and effluents from planned manners. of the surface contractors with PARTIALLY the construction Garbage, concrete water near to sub- the help of COMPLIES sites may cause refuses, slurry mud, project area should LGED. further degradation lubricant during pile be tested with of surface water. driving and other the proper sampling effluents should not program. to be disposed directly into natural waters. 2.3.2 Ground water Seepage of wastes Workforce camps will Inspections by FSE Sampling of Ground water Sampling & Testing from workers’ be located away from should be done at ground water sample test are in process. camps through the water resources. All all camps sites and from newly results would COMPLIES soil profile might be practical measures major construction established tube- be the evidence a source for ground such as provision of sites of bridges wells are being for the works water pollution. septic tanks, garbage and roads on started to collect mentioned. bags and other regular basis. by contractors in sanitation facilities Water quality presence of will be implemented parameters of the LGED personnel. at the construction ground water near camps to prevent the to sub-project wastewater and solid areas should be wastes from entering tested with proper well and groundwater sampling program. recharge areas 2.3.3 Air pollution Dust and other Regular watering and Inspections Regular Quarterly air PARTIALLY emissions from the grass turfing at the throughout the sampling of air quality analysis COMPLIES construction sites exposed sites are alignment. During quality is being reports would might be the cause needed to control dry season, check started by the be the of air pollution dust blowing. Monitor for dust and contractors authentication. during the of the air pollution undertake air construction and levels at different quality testing for operation stage. construction sites is SO2, NO2 and SPM needed. at construction sites. 2.3.4 Noise and Work sites will be Keep noise pollution Inspections Regular Records of the PARTIALLY vibration noisy due to at ≤ 60 dB throughout the sampling of noise levels COMPLIES vibration during pile (Bangladesh alignment and the noise levels are during driving, operation of standard) levels at area of equipments now being construction power generator, mosque, school, used for sub- started by the rock crushing/ and populated area and project where the contractors in movement of other sensitive sites. noise might occur. presence of construction Contractor should LGED personnel. vehicles. use only well maintained functioning equipment. 2.3.5 Soil Contamination of The chemicals, Inspections to Inspection to FSE’s COMPLIES contamination soils at camp and cement, petroleum observe the soil observe soil monitoring work sites due to derivatives and contamination contamination report accidental spillage bituminous materials, throughout the has been carried of noxious road filling sand alignment of the out by FSE. chemical, petroleum should be handled sub-projects Most of the derivatives and properly and stored should be ensured. cases, stack yard bituminous material cautiously. has been may happen. improved 2. 4 Health and Safety 2.4.1 Loss of Temporary Movements of the Regular inspection Inspection to FSE’s COMPLIES navigation route disruptions and loss navigational traffic to bridges and observe monitoring of navigation route will be maintained ensuring possible report might occur at through alternative navigation routes navigation route bridge construction arrangement, should be done. at bridge areas sites including proper has been carried channel markings out by FSE. and lighting.
38
Implementation Project Impact Mitigation Measures Details of What work has Outputs/ Implementation/ Stages/ Monitoring Action undertaken/ and Evidence Compliance Status Environmental Undertaken where provided Parameters 2.4.2 Non- Contamination of Adequate provision FSE will inspect Most of the FSE’s quarterly PARTIALLY compliant work camp area for safe and hygienic the site properly for cases, monitoring COMPLIANCE Workforce Camp and vicinity might disposal of all waste escape the non- contractors have report Conditions occur with various should be remained compliant camp given emphasis wastes due to in workforce camp conditions. on occupational improperly handling sites health & safety and disposal. All workers living in conditions to camps must be comply the supplied with a cot, safeguards. standard bed mattress, and mosquito net. 2.4.3 Waste If the construction Contain all solid Site inspections by Systematic or FSE’s quarterly PARTIALLY Management camp wastes are wastes at designated FSE would be consistent waste monitoring COMPLIANCE often poorly location within continued. management report managed, it can construction sites. procedures has lead to chronic Service machinery to be pollution of surface and vehicles should established. and groundwater. be at designated maintenance workshops where waste oils and lubricants can be collected and recycled. 2.4.4 Personal and Undertake check and Site inspections by Water samples FSE’s quarterly PARTIALLY Occupational occupational health cleaning at all sites FSE used as drinking monitoring COMPLIES Health and Safety issues and disease and areas where purposes for the report contamination are clean conditions labors at camps common in labour should exist. and other sites camps that might Provision should be are not tested yet even spread in the for safe water, . Some work adjacent villages sanitary toilet facility sites have no during the and hygienic toilets or useable construction stage. accommodation for medical kits. In This would include workers at camp some cases, inadequate and sites. In addition, PPE is supplied unsanitary toilet ensure provision of but its use is not facilities, lack of PPEs and First-Aid consistent and potable water and facility for them. not enforced. sanitary washing Ensure that these areas. facilities are cleaned and disinfected at least 2X/week 2.4.5 Breeding Construction work Inspect the area Site Inspections by Limited action FSE’s quarterly PARTIALLY area for Pathogen might create areas which is susceptible FSE has been taken monitoring COMPLIANCE for water to form to stagnant water and at camps & stack report stagnant puddles, puddles, check the yards. ideal breeding stored construction areas for malaria materials such as and dengue tires and old oil mosquitoes etc. drums--empty to The pathogen and prevent water insets can also be ponding. grown in the area of puddles and also in old equipment storage and waste tire dumps area: 2.4.6 Environmental If the contractor Prepare a completion Contractors should Limited action Contractor’s NON Completion fails to prepare a report on prepare the has been taken quarterly report COMPLIANCE Reporting summary report environmental works completion report. in this regard.. defining the and deliver to the mitigation and Executive Engineer monitoring actions completed and what
39
Implementation Project Impact Mitigation Measures Details of What work has Outputs/ Implementation/ Stages/ Monitoring Action undertaken/ and Evidence Compliance Status Environmental Undertaken where provided Parameters needs to be continued during the operatinal period, the environmental safeguards program will be weakened.
40
Appendix 3: Environmental Management Plan and Environmental Monitoring Requirements
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters 3.0 Construction period
3.1 Natural Environment
3.1.1 Construction of road, The bridges and culverts Near and around water Weekly during LGED though FSE(Field Supervision Hydrology and flood market structures, are to be designed and bodies adjacent to construction period at all Contractors Engineer) pattern culverts and bridges built properly considering alignment sites would create minimal climate change impact on hydrology. infrastructure design. 3.1.2 Earthwork activities To deal carefully at Throughout alignment Inspect weekly to ensure LGED though FSE(Field Supervision Drainage congestion during construction of the bridge design and that drainage is properly Contractors Engineer) infrastructures may not planning stages based maintained at sub-project induce drainage on hydrological data. construction sites congestion except at Ensure all earthworks especially in the culvert and bridge sites. and bridges are earthwork portion. constructed according to design and specifications to minimize the drainage congestion hazard. 3.1.3 The erosion risk at Regular watering, grass Throughout the road Inspect weekly to insure LGED though FSE(Field Supervision Erosion and silt bridge sites and road turfing and planting alignment; at outlets of that drainage is properly Contractors Engineer) deposition slopes is either absent or Vetiver/ Napier grasses cross drainage structure maintained at earthworks minimal. However, in rows along the road with erosion potential. portion. erosion along the road slopes and bridge slope near to water approaches will reduce bodies during rainy the soil erosion risk. season may damage Construction material adjacent field crops containing fine particles during the construction e.g. limestone will be stage. stored in an enclosure away from water bodies to ensure that sediment laden water does not pollute the aquatic environment.
3.1.4 Earth transportation An appropriate plan for Throughout the alignment Twice per month LGED though FSE (Field Supervision Landscape: future activities for the ameliorsting the Contractors Engineer) 41
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters visual intrusion development may affect landscape beauty could the landscape beauty. be hired both for maintenance and quality control. 3.1.5 Some contractors do not FSE (Field Supervision The Environmental prepare environmental Engineer) Management work plan mentioning the The EMWS should be Within 1 month of the LGED though Implementation Work time line for mitigation submitted by the successful contractor NA Contractors Schedule (EMWS) and monitoring actions, contractors to the mobilizing consequently the EMP Executive Engineer. requirements are not implemented properly 3.2 Ecological Environment 3.2.1 The removing of any live If any tree require to At all sub- project sites. Throughout the LGED through FSE (Field Supervision Tree felling* standing trees will not be remove from the road construction period Contractors Engineer) required from the road section, then due section for the purpose compensatory processes of widening the road would be exercised according to MOEF (Ministry of Environment and forest) and LGED guidelines. Besides, large trees would be planted on the berms and at the toe of the slopes of the road. 3.2.2 Bridge/culverts The bridge construction All the bridges and Once a month during the LGED though FSE (Field Supervision Fisheries, Fish habitat construction activities sites across the rivers/ culverts construction period Contractors Engineer) and water courses might hinder fish canals need to be movement temporarily carefully monitored as affecting the capture these are migratory fisheries. waters supporting important local fisheries. The borrow pits /ponds dug for fill materials collection may be used for aquaculture or fish stocking to compensate the loss. 3.2.3 The terrestrial wildlife If applicable, FSE will Along the project Throughout the LGED though FSE (Field Supervision Wildlife species might be make a list of wildlife corridors construction and Contractors 42
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters disturbed due to noise susceptible to damage if operation period, Engineer) and vibration at there is any construction sites and may be a cause for dislocation of wildlife habitats if any tree removing becomes essential. No report was available regarding the presence of threatened or endangered wildlife species at the project site. 3.3 Environmental Pollution
3.3.1 The surface water at Wastes, effluents and Continuous inspection Throughout the LGED though FSE (Field Supervision Surface water project site might be other pollutants system should be construction period Contractors Engineer) polluted due to human generated at the site established to all work faecal, organic and other camp/work sites should camps and major pollutants. Disposed be stored, handled, construction sites such wastes and effluents transported and disposed as bridges and from the construction of in a planned manner. earthworks site. sites may cause further Garbage, concrete degradation of surface refuses, mud slurry & water. lubricant during pile driving and the other effluents should not to be disposed of directly into the natural stream. 3.3.2 Seepage of wastes from Workforce camps will be Throughout the When new wells are dug LGED though FSE (Field Supervision Ground water workers’ camps through located away from water alignment, especially and toilet facilities are Contractors Engineer) the soil profile might resources. All practical where the pile drilling to built near wells. occur ground water measures such as 30m depth is conducted, pollution. provision of septic tanks, and where any new wells garbage bags , and other were dug. sanitation facilities will be implemented at the construction camps to prevent the wastewater and solid wastes from entering well and 43
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters groundwater recharge areas 3.3.3 Dust and other Regular watering and Each work, bridges, rock During construction and LGED though FSE (Field Supervision Air pollution emissions from the grass turfing at the crushing and aggregate operation stage Contractors Engineer) construction sites might exposed sites are plants site. be the cause of air needed to control dust pollution during the blowing. Monitor of the construction and air pollution levels at operation stage. different construction sites is needed. 3.3.4 Work sites will be noisy Keep noise pollution at ≤ Construction and Throughout the LGED though FSE (Field Supervision Noise and vibration due to vibration during 60 dB (Bangladesh operation sites construction and Contractors Engineer) pile driving, operation of standard) levels at operation period power generator, rock mosque, school, crushing/ and movement populated area and other of construction vehicles. sensitive sites. Contractor should use only well maintained functioning equipment. 3.3.5 Contamination of soils at The chemicals, cement, At all work camps and Monthly during the LGED though FSE (Field Supervision Soil contamination camp and work sites due petroleum derivatives construction sites construction period Contractors Engineer) to accidental spillage of and bituminous noxious chemical, materials, road filling petroleum derivatives sand should be handled and bituminous material properly and stored may happen. cautiously. 3.4 Health and Safety
3.4.1 Temporary disruptions Movements of the All bridge construction Monthly LGED though FSE (Field Supervision Loss of navigation route and loss of navigation riverine transport will be sites Contractors Engineer) route might occur due to maintained by an bridge construction alternative arrangement, including proper channel markings and lighting. 3.4.2 Contamination at work Adequate provision for All construction camp Monthly LGED though FSE (Field Supervision Non-compliant camp area and vicinity safe and hygienic areas Contractors Engineer) workforce Camp might occur due to disposal of all waste conditions improperly handled and should be remained at disposed of wastes. workforce camp sites All workers living in
44
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters camps must be supplied with a cot, standard bed mattress, and mosquito net. 3.4.3 If the construction camp Contain all solid wastes All construction camp Monthly LGED though FSE (Field Supervision Waste Management wastes are often poorly at designated location areas Contractors Engineer) managed, it can lead to within construction sites. chronic pollution of Service machinery and surface and vehicles should be at groundwater. designated maintenance workshops where waste oils and lubricants can be collected and recycled.
3.4.4 Personal and Undertake check and LGED though FSE (Field Supervision Health and safety occupational health cleaning at all sites and Contractors Engineer) issues and disease areas where clean All work sites and contamination are conditions should exist. particularly at common in labour camps There should be Construction camps At least 2X/week that might even spread in provision of safe water, the adjacent villages sanitary toilet facility and during the construction hygienic accommodation stage. This would include for workers at camp inadequate and sites. In addition, ensure unsanitary toilet facilities, provision of PPEs and lack of potable water and First-Aid facility for them. sanitary washing areas. Ensure that these facilities are cleaned and disinfected at least 2X/week Construction work might FSE (Field Supervision Create areas of water to Engineer) form stagnant puddles, Inspect the stagnant ideal breeding areas for Water and puddles area malaria and dengue for every 3-days, check Regular construction site 3.4.5 All work areas and LGED though mosquitoes etc. The the stored construction Inspection and 3-4 days Vector-borne diseases Camps Contractors pathogen and insets can materials such as tires after every heavy rain also be grown in the area and old oil drums--empty of puddles and also in to prevent water ponding. old equipment storage and waste tire dumps 45
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters area: 3.5 If the contractor fails to Prepare a completion NA Complete within the last LGED though FSE (Field Supervision Environmental prepare a summary report and deliver to the 4 months of the sub- Contractors Engineer) Completion Reporting report defining the Executive Engineer project mitigation and monitoring actions completed and what needs to be continued during the operating period, the environmental safeguards program will be weakened. 4. OPERATING PERIOD
4.1 Degradation of local air Regular watering and NA Air Quality monitoring is LGED though FSE Air Quality quality due to increased grass turfing at the to continue for 2 years of Contractors mechanical transport and exposed sites are the operating period. traffic. needed to control dust blowing. 4.2 Movement of vehicles Contractor should use Near to power Year 1 of operations LGED though FSE Noise and operation of power only well maintained generators, around Contractors generator might occur functioning equipment. schools close-by noise. residences and hospitals 4.3 Without PPEs, labours Provision of safe water, Near to power Ensure that these LGED though FSE Safety can fall into accident. sanitary toilet facility and generators, area of the facilities are cleaned and Contractors Inadequate and hygienic accommodation market structure disinfected at least unsanitary toilet facilities, for workers should be at 2X/month lack of potable water sites. In addition, might cause disease provision of PPEs and infestation. First-Aid facility for labours should be near to operation sites. 4.4 Inspection of sites to be Inspect the whole sub- The entire area of the Within the first quarter of LGED though FSE Construction Period decommissioned by projects area to observe sub-projects operations and before Contractors Decommissioning contractor are: the situation final payment made to • borrow sites contractor. • work camps • fuels storage areas • waste dump sites, • access roads area
46
Project Period and Assessment of Who will Environmental Project Impact Mitigation Measures Location Timing/Duration Who will Implement compliance Supervise Parameters 4.5 Garbage and sewage Establish waste Toilets area, market Once per month LGED though FSE Waste Management discharge may pollute management system in area, garbage area. Contractors the environment. the sub-project areas. Establish strict fines for garbage throwing and provide abundant bins on sub-project sites.
47
Appendix 4: Consultant site visit reports
Rajshahi District:
Site visit was held by Environment and Climate Change Specialist at Rajshahi District during 6th May to 09th May, 2014 for EMP monitoring of the sub-projects of SRIIP, now involving in the phase of construction, to comply with ECR’97 and the guideline of ADB/KfW. Sub-project-wise observation result from EMP monitoring and necessary recommendation that should be taken immediate action to implement these in the sub-projects are stated below.
Road name- Ghodagari UP office to Narayonpur hat Observation: • In the construction area near to the road named Ghodagari UP office to Narayonpur hat, there were no PPEs (Personal Protective Equipment e.g. ear protection gear, mask, goggles, helmet, rain coat, safety shoes etc.) facilities. There were drinking water supply but toilet facilities for laborers near to construction areas were absent. Troubles shooting posters or informatory sign boards were not displayed in the said construction area. • Laborers informed that most of them were not aware on this (PPEs) and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, there was no potential loss of trees/ vegetation/ aesthetics in the scheme area. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stack- yard for storing construction materials, fuel and lubricants etc. was established near to the road. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was near to the construction area. • Office building/ campsites with drinking water and toilet facilities has been established properly. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land.
48
Contractor’s response:
The contractor felt sorry for not to follow the rules and regulations of Bangladesh Government and not to abide by ADB/KfW guideline. He has given commitment to obey the necessary environmental safe guards which are not done yet. They wished that we should require training on environmental safeguards to implement the environment related activities soundly. Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear,helmet, mask, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all environments related existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works.
• Sanitary facilities (like temporary toilet facilities for both male and female) for laborers should be ensured within the short distance from construction area.
• Contractor has to prove his innocence on the environmental safeguards implementation especially on the issue of occupational safety. So, he has to submit the training documents to Executive Engineer of the District LGED office on the stated issue for labors which have been completed.
• Trouble shooting poster should be displayed during construction in the working area of the sub-project.
Road name: Kakonhat-Hatbakoil via Kooilhat
Observation: • There were no drinking water supply and toilet facilities for laborers near to construction areas. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • No Personal Protective Equipments (PPEs) for labors were supplied by the contractors. • Space for campsite has been hired and it is being used for the sub-project purposes. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. 49
• In the sub-project, there were some losses of trees in the scheme area beside the road. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stock- yard for storing construction materials, fuel and lubricants etc. was established near to the road. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land.
Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all related existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by project works.
• Drinking water supply and sanitary facilities for laborers should be ensured within the short distance from construction area.
• The trees should be planted besides the road as much as need.
• Labors should be trained on environmental safeguards with occupational health and safety. Contractor has to prove his innocence on the environmental safeguards implementation especially on the occupational health and safety. So, he has to submit the training documents to Executive Engineer of District LGED office on the stated issue for labors which have been completed.
• Trouble shooting poster should be displayed during construction in the working area in the sub-project.
50
Road name: Mohonpur UZ-Dhopagata GCM via Naonagar
Observation: • No Personal Protective Equipments (PPEs) for labors were supplied by the contractors. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • There were no drinking water supply and toilet facilities for laborers near to construction areas. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • In the sub-project, stock- yard for storing construction materials, fuel and lubricants etc. was established near to the road. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land. • In the sub-project, there was no potential loss of trees/ vegetation/ aesthetics in the scheme area. Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works.
51
• Drinking water supply and sanitary facilities for laborers should be ensured within the short distance from construction area.
• Labors should be trained on environmental safeguards with occupational health and safety. Contractor has to prove his innocence on the environmental safeguards implementation especially on the occupational health and safety. So, he has to submit the training documents to Executive Engineer of District LGED office on the stated issue for labors which have been completed.
Road name: Jholmolia Mominpur via Sayaidpur Bilmaria
Observation: • There were drinking water supply for laborers but toilet facilities near to construction areas were absent. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • No Personal Protective Equipments (PPE) for labors were supplied by the contractors. • Space for campsite has been hired and it is being used for the sub-project purposes. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement work. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stock- yard for storing construction materials, fuel and lubricants etc. was established near to the road. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land.
Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
52
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works.
• Sanitary facilities for laborers should be ensured within the short distance from construction area.
• Labors should be trained on environmental safeguards with occupational health and safety. Contractor has to prove his innocence on the environmental safeguards implementation especially on the occupational safety. So, he has to submit the training documents to Executive Engineer of District LGED office on the stated issue for labors which have been completed.
• Trouble shooting poster should be displayed during construction in the working area of the sub-project.
Here, some pictures/ photographs shown the statuses of environmental safeguard implementation for the sub-projects of Rajshahi are given below-
Labors having no PEPs are working on the road sub-project named Godagari UP office to Narayonpur hat road
53
Established office building for the sub-project, Godagari UP office to Narayonpur hat road
Labors having no PEPs are working on the road sub-project named Godagari UP office to Narayonpur hat road
54
Labors are waiting to take lunch on the stock yard of the road sub-project named Mohonpur Upazilla to Dhopaghata road. The necessary PPEs are not supplied by the contractors to workers.
Labors those have no PPEs are working on the sub-project named Jalmolia to mominpur hat via Bill maria road.
55
Chuadanga District:
Site visit was held by Environment and Climate Change Specialist at Chuadanga District during 25th June to 28th June, 2014 for EMP monitoring of the sub-projects of SRIIP, now involving in the phase of construction, to comply with ECR’97 and the guideline of ADB/KfW. Sub-project-wise observation result from EMP monitoring and necessary recommendation that should be taken immediate action to implement these in the sub-projects are stated below.
Market name- Development of Munshigonj GC Observation: • In the construction area, there were no PPEs (Personal Protective Equipment e.g. ear protection gear, mask, goggles, helmet, rain coat, safety shoes etc.) facilities for the labors. There were drinking water supply and toilet facilities in the construction area of the market for laborers. Troubles shooting posters or informatory sign boards were not displayed in the said construction area. • Laborers informed that most of them were not aware on this (PPEs) and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, there was no potential loss of trees/ vegetation/ aesthetics in the scheme area. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stack-yard for storing construction materials, fuel and lubricants etc. was not established near to the market • No ecological sensitive area was found adjacent to the scheme areas. • First AID box with 16 medicines was near to the construction area. • Office building/ campsites with drinking water and toilet facilities has been established properly. • Mixture machine (Sand/stone/brick) does not covered by any canopy to protect excessive noise. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land. Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear,helmet, mask, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
56
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all environments related existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works.
• Trouble shooting poster should be displayed during construction in the working area of the sub-project.
Road name: Gokulkhali GC - Bhogiratpur GC .
Observation: • There were no drinking water supply and toilet facilities for laborers near to construction areas. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • No Personal Protective Equipments (PPEs) for labors were supplied by the contractors. • Space for campsite has been hired and it is being used for the sub-project purposes. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stock- yard for storing construction materials, fuel and lubricants etc. was not established near to the road. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land.
57
Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all related existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by project works.
• Drinking water supply and sanitary facilities for laborers should be ensured within the short distance from construction area.
• Labors should be trained on environmental safeguards with occupational health and safety. Contractor has to prove his innocence on the environmental safeguards implementation especially on the occupational health and safety. So, he has to submit the training documents to Executive Engineer of District LGED office on the stated issue for labors which have been completed in the meantime.
• Trouble shooting poster should be displayed during construction in the working area in the sub-project.
Road name: Nilmonigonj GC-Dingadah GC
Observation: • No Personal Protective Equipments (PPEs) for labors were supplied by the contractors. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • There were drinking water supply and toilet facilities for laborers near to construction areas. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • In the sub-project, stock- yard for storing construction materials, fuel and lubricants etc. was established near to the road.
58
• Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land. • In the sub-project, there was some loss of trees/ vegetation/ aesthetics in the scheme area. Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works.
Road name: Gholdari GC - Sarajgonj R&H (Alamdanga Portion).
Observation: • There were drinking water supply for laborers but toilet facilities near to construction areas were absent. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • No Personal Protective Equipments (PPE) for labors were supplied by the contractors. • Space for campsite has been hired and it is being used for the sub-project purposes. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement work. • In the sub-project, no construction work was being carried out close to any streams or water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stack- yard for storing construction materials, fuel and lubricants etc. was not established near to the road. 59
• No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land. Recommendation: • Sufficient Personal Protective Equipments (PPEs) (eg.ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible. • Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO. • Laborers and all existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works. • Sanitary facilities for laborers should be ensured within the short distance from construction area. • Trouble shooting poster should be displayed during construction in the working area of the sub-project.
Here, some pictures/photographs shown the statuses of environmental safeguard implementation for the sub-projects of Chuadanga are given below-
Fish and meat shed are being constructed in Munsigonj GC where labors have no PPEs.
60
Labors having no PEPs are working on the road sub-project named Gokulkhali GC - Bhogiratpur GC road.
District: Magura
Site visit was held by Environment and Climate Change Specialist at Magura District during 8th June to 11th June, 2014 for EMP monitoring of the sub-projects of SRIIP, now involving in the phase of construction, to comply with ECR’97 and the guideline of ADB/KfW. Sub-project-wise observation result from EMP monitoring and necessary recommendation that should be taken immediate action to implement these in the sub-projects are stated below. Road name- Sreepur (Kamarpara) GC - Alypur RHD road.
Observation: • In the construction area of the sub-project, there were no PPEs (Personal Protective Equipment e.g. ear protection gear, mask, goggles, helmet, rain coat, safety shoes etc.) facilities. There were drinking water supply but toilet facilities for laborers near to construction areas were absent. Troubles shooting posters or informatory sign boards were not displayed in the said construction area. • Laborers informed that most of them were not aware on this (PPEs) and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, there was no potential loss of trees/vegetation/aesthetics in the scheme area. • In the sub-project, no construction work was being carried out close to any streams or water bodies. With a few exceptions, there was facility (Drain) to divert water flow through the construction sites to avoid flowing of fines, aggregates, spilled oil/ lubricants downstream to open water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder. • In the sub-project, stack- yard for storing construction materials, fuel and lubricants etc. was established near to the road. • No ecological sensitive area was found adjacent to the scheme areas. 61
• Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was not near to the construction area. • Office building/ campsites with drinking water and toilet facilities has been established. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land. Recommendation:
• Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, helmet, mask, goggles, safety shoes etc.) must be provided in the sub-project by the contractor to workers as soon as possible.
• Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO.
• Laborers and all environments related existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by the project works.
• Sanitary facilities (like temporary toilet facilities for both male and female) for laborers should be ensured within the short distance from construction area.
• Trouble shooting poster should be displayed during construction in the working area of the sub-project.
Road name: Binodpur GC-Nowpara GC via Chawbaria, Hatbaria bazar & nagra
Observation: • There were no drinking water supply and toilet facilities for laborers near to construction areas. Troubles shooting posters or informatory sign boards were not displayed in the construction area. • No Personal Protective Equipments (PPEs) for labors were supplied by the contractors. • Laborers informed that most of them were not aware on PPEs and in most cases they did not know how to use and also to handle it. • Drinking water (supplied for labors) quality test and Noise level with air quality test near to used equipments, hot mix plant, power generator and dust producing area (where applicable) are not done yet. • In the sub-project, no child labor was employed to do the improvement works. • In the sub-project, no construction work was being carried out close to any streams or water bodies. • Drainage channels were free from any obstacles for continuous water flowing preventing from nearby sites which might vulnerable to environmental disorder.
62
• In the sub-project, stack yard for storing construction materials, fuel and lubricants etc. was established near to the road. • No ecological sensitive area was found adjacent to the scheme areas. • Necessary palisading walls or protection walls have been constructed along the road sections to control deep soil cut or to protect against landslides or land erosion. • First AID box with 16 medicines was not there adjacent to the construction area. • No sandy soil/construction materials have been stored on or beside the road to protect run-off from construction area to agricultural land. Recommendation: • Sufficient Personal Protective Equipments (PPEs) (eg. ear protection gear, mask, helmet, rain coat, goggles, safety shoes etc.) and First Aid box must be provided in the sub-project by the contractor to workers as soon as possible. • Executive Engineer should ensure to determine the noise level, air and drinking water quality test during construction and operation period by the contractor and to collect the test reports for sending it to ADB through PMO. • Laborers and all related existing personnel including contractors and their related expert should be trained on EMP to become aware on environmental issues raised by project works. • Drinking water supply and sanitary facilities for laborers should be ensured within the short distance from construction area. • Labors should be trained on environmental safeguards with occupational health and safety. • Trouble shooting poster should be displayed during construction in the working area in the sub-project.
63
Appendix-1: Status of project and EMP Implementation Status of Compliance 1- Very Good, 2-Good, 3-Fair, 4-Very poor, 5-Not yet test 6-Test not avilable N.B. IV- Investigated Value, STD-Standard value,
Natural Economic Environmental Pollution Environment Environment Compliance Status Compliance Status Compliance Status Soil Noise Quality Air Quality Ground Water Contamination Surface Water water for labors SL No. District Upazila Road Name Quality/Drinking Hydrolozy 2 (µg/g) 2 (µg/g) 3 (mg/L) PH PH Health & Safty Physical Progress (%) SO NO Workforce Camps NO AS (ppm) AS TP (mg/L) TP TP (mg/L) TP Waste Management DO (mg/L) DO TSS(mg/L) Noise (dB) SPM (µg/g) SPM Vactor bone Disease Drainage Congestion BOD (mg/L) Ecoli (n/100g) Ecoli Erosion & Silt deposition Compliance Compliance Compliance Compliance Compliance Oil & Grease (mg/L) Oil & Grease Fuel & Chemical spills (mg/g) Landscape future visual Intrusion IV IV IV IV IV IV IV IV IV IV IV IV IV IV IV IV STD STD STD STD STD STD STD STD STD STD STD STD STD STD STD STD 1 Kushtia Daulatpur Improvement of Nawdapara GC‐DGT Dharmodah More to Khalishakundi RHD, Ch.1408m‐5620m, Link (Bridge Approach ch.00m‐ 100 2 2 2 2 3 3 3 2 5 5 5 5 5 205m ‐North, oo‐125m‐South) 2 Kushtia Daulatpur Improvement of Nawdapara GC to Dharmodah to Khalishakundi RHD, 61 2 2 2 2 3 3 2 2 5 5 5 5 5 Ch.9062m to Ch.16000m, 3 Kushtia Daulatpur Nawdapara GC to Dharmodah to Khalishakundi RHD, Ch.16000m to 85 2 2 2 2 3 3 3 2 5 5 5 5 5 Ch.22716m, 4 Kushtia Mirpur Improvement of UZR from Amla firm R&H to Hatboali GC via Khursha, Shutali, Malihad Bazar road, at Ch.2000m‐2200m & Ch. 5800m‐9700m, 65 2 2 2 2 3 3 3 2 (ID No.:205942009) Mirpur Upazila, Kushtia District. 5 Kushtia Mirpur Improvement of UZR from Amla firm R&H to Hatboali GC via Khursha, Shutali, Malihad Bazar road, at Ch.10533m‐16180m 90 2 2 2 2 3 3 3 2
6 Kushtia Kumarkhali A. Improvement of UZR from Kushtia ‐ Rajbari R&H (Fultala) to Shomoshpur GC, Ch.2050m‐Ch.2362m, and Ch.5200m‐Ch.6820m (ID:250712009) at Kumarkhali Upazial, Kushtia district. 65 2 2 2 2 3 3 3 2
7 Kushtia Khoksha Part‐B: Improvement of UZR from Khoksha ‐Ektarpur ‐ Banogram ‐ Katlagari, Ch.11935m‐Ch.12965m (ID:250632005), Khoksha Upazila, 60 2 2 2 2 3 3 3 2 Kushtia district 8 Kushtia Khoksha Improvement of Bhabanigonj bazar under Khoksha Under in Kushtia district. 65 2 2 2 2 3 3 3 2 9 Kushtia Daulatpur Improvement of Tekala bazar under Daulatpur Upazila in Kushtia 85 2 2 2 2 3 3 3 2 district. 10 Kushtia Kumarkhali A. Improvement of UZR from Kushtia ‐ Rajbari R&H (Fultala) to Shomoshpur GC, Ch.2050m‐Ch.2362m, and Ch.5200m‐Ch.6820m 25 2 2 2 2 3 3 3 2 (ID:250712009) at Kumarkhali Upazial, Kushtia district. 11 Jhenidah Kaligonj Improvement of Kola GC to Gazirbazar (Kala) GC Road, Ch.700m‐4070m 100 2 2 2 2 3 3 3 2 5 5 5 5 5
12 Jhenidah Harinakundu Improvement of Harinakundu GC to Bhabanipur GC via Narayankandi bazar, Ch. 8418m to 9810m 65 2 2 2 3 3 3 3 2 5 5 5 5 5 13 Jhenidah Sadar Improvement of Narkelbaria GC to Kola GC (DPP), Ch. 2536m to 6900m 90 2 2 2 3 3 3 3 2 5 5 5 5 5
17 SL 4Jeia oehu Improvement Moheshpur Jhenidah 14 0Jeia ocadu Improvement Kotchandpur Jhenidah 30 7Jeia oehu Improvement Moheshpur Jhenidah 27 1Jeia aiaud Improvement Harinakundu Jhenidah 21 8Jeia hlkp Improvement Shalikupa Jhenidah 18 5Jeia oehu Improvement Moheshpur Jhenidah 25 2Jeia aiojImprovement Kaligonj Jhenidah 22 5Jeia oehu Improvement Moheshpur Jhenidah 15 8Jeia oehu Improvement Moheshpur Jhenidah 28 3Jeia ocadu Improvement Kotchandpur Jhenidah 23 9Jeia hlkp Improvement Shalikupa Jhenidah 19 1Jeia aiajImprovement Kaliganj Jhenidah 31 6Jeia oehu Improvement Moheshpur Jhenidah 26 6Jeia oehu Improvement Moheshpur Jhenidah 16 0Jeia hlkp Improvement Shalikupa Jhenidah 20 4Jeia aiaud Construciton Harinakundu Jhenidah 24 9Jeia oehu Improvement Moheshpur Jhenidah 29 7Jeia oehu Improvement Moheshpur Jhenidah 17
No. District Upazila Harinakunda 2220 District sreerampur Sreerampur GC sreerampur Jhenaidah Sreerampur 1520m Jhenaidah Sreerampur Ch.6000m sreerampur 8200m Sreerampur Gazir sreerampur
–
‐
Sarajgonj Bazar 4820m., ‐ ‐ 2220m 9550m,
district district (ID:244422006)
GC
bazar, bazar, bazar, bazar, Bazar Bazar Bazar Bazar
GC of
of of of of of of of of of of of of of of of of of
Upazila
road road &
Ch.10650m 39m ‐
Gorabaria Tree Road Kulbaria Bhatai Road Ramchandrapur Gorabaria Road UZR Bhatai Tree Road Gorabaria Charirbil Bhatoi Gorabaria
Ch.4820m
Bhabanipur
to to to to Ch.9240m Ch.00 Ch.3240m Ch.
via at
Long Shapur Shapur Shapur Shapur
from
Plantation Plantation
Shailkupa Garabaria Garabaria Garabaria Garabaria
(Ch
6240m
Bhomradanga GC GC GC
to
Bazar
Bazar
‐
RCC
‐
at Sabdarpur 0+00 to to ‐
Pucca Pucca Pucca Pucca ‐ Ch 12500m Road Name
8200m Hatfazilpur to to to to
Kotchandpur
to to Hatfazilpur Hatfazilpur GC
to Girder
3240m
Kalihoda Kalihoda Kalihoda Kalihoda under
under
Ch. Ch.
to on on
Pacca Pacca
Pacca Pacca
Ch. Bazar via road road road road
4+4070
both both 12240m 6240m
& Narayankandi 9240m
Bridge GC
Horinakunda at
Shoilakupa
to to to to
Ch. Road Road Road Road under
GC
to to to to
(Ch
sides sides to GC GC Panchbaria Panchbaria Panchbaria Panchbaria
12500m
Upazila,
Km) Bathangachi Bathangachi Bathangachi Bathangachi
Road Sarojgonj ‐
over Panchbaria Panchbaria Panchbaria Panchbaria at at 3+350km
Kaligonj
of of
Shailkupa Shailkupa ,
(Effective at
road road
GK Upazila
‐
Jhenaidah Belemath Upazila 15450m Ch.
Canal road road road road
GC,
from from Upazila to
00
to to to to Road Road Road Road
5+850km), Upazial, Upazial, in Ch.2900m
‐
via via via via
1520m Mirzapur Mirzapur Mirzapur Mirzapur Length
on
in
Sabdarpur Jhenaidah Kola
at
district. Via Via Via Via in
GC
Ch. Ch. = &
‐ ‐ to to to to
0 5 5 5 5 5 2 3 3 3 3 3 2 2 100 0 5 5 5 5 5 2 3 3 3 3 3 2 2 100 0 5 5 5 5 5 2 3 3 3 3 3 2 2 100 0 5 5 5 5 5 2 3 3 3 3 3 2 2 100 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 80 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 80 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 80 52233323255555 5 5 5 5 2 3 2 3 3 3 2 2 95 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 0 0 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 18 SL 7Mhru uingrImprovement Mujibnagar Meherpur 37 2Jeia hikp Impro Shailkupa Jhenidah 32 1CudnaDmruaPart Damurhuda Chuadanga 41 6CudnaDmruaConstruction Damurhuda Chuadanga 46 2CudnaChuadanga Chuadanga 42 8Mhru agiImprovement Gangni Meherpur 38 8CudnaAadnaTree Alamdanga Chuadanga 48 9Mhru Meherpur Meherpur 39 5Mhru agiImprovement Gangni Meherpur 35 3CudnaAadnaImprovement Alamdanga Chuadanga 43 0CudnaDmruaPart Damurhuda Chuadanga 40 3Jeia hikp Tree Shailkupa Jhenidah 33 6Mhru aa Improvement Sadar Meherpur 36 7CudnaAadnaConstruction Alamdanga Chuadanga 47 4CudnaAadnaImprovement Alamdanga Chuadanga 44 5CudnaAadnaImprovement Alamdanga Chuadanga 45 4Jeia ocadu Improvement Kotchandpur Jhenidah 34
No. District Sadar Upazila
aa Improvement Sadar
Chuadanga 0.00m Km Ch. Gokulkhali Strs. Improvement (ID:218312 Chuadanga Fazilpur Meherpur Upazila, road Meherpur 5075m Ch.1000m Panchbaria Mathabhanga Biddayadharpur, 4.00 5200m 218072010)
00.00m (Road ‐ ‐
A: B: Km) = Plantation Plantation at
‐ Tree 10
2850m
Gokulkhali (PAM) to7870m Gokulkhali (Ch:8+000
GC Chuadanga
under
nos.,
ID:
District District to
GC
‐ Plantation road district in road
3932m under
of Ch. of 208173026)
SRIIP of of of of of of of of of of to river
& Span
on on Alamdanga 42.00m 90.00m
Ch. Road Nilmonigonj Shahebnagor Baradi Rajpur Gholdari Gholdari Munshigonj Sabdarpur via at Ch.2025m 5200m Bhogirathpur UZR ‐
GC GC
SRIIP both both
(Ch Road
on
3+000
district Sreerampur of 6000m
to from to
on from
Munshigonj ‐ Strs.
5+000
GCM to
long Long
sides sides Bhogirathpur Bhogirathpur
ID:
both Gc Gc
under & Shohorbaria
‐ Meherpur ‐
in GC Upazila, Mohazonpur
Ch.5006m (m) Road Name
8050m,
257882006,
Ch:
RCC to to GCM
under Pre GC
of of
SRIIP
to
Hat ‐ sides GC
shorojgonj shorojgonj
Sarajgonj
=
‐ road road
Alamdanga 4+000 Bazar ‐
10+000 Dingadah
Girder Stressed
9.75m)
road bazar
under GC
Meherpur
District: (Effective of
from from
Dariapur ‐ GC,
GC, to
‐
road bazar at
Shapur
Bridge
under
5+800
Mujibnagar Km),
Alamdanga Pashurhat GC UZR
road
Ch.
Ch.
Ch.8235m Girder
GC GC GC Gholdari Garabaria
‐ from Upazila, Chuadanga,
Bamanpara
via
5+843Km
road 4785m (Ch.11+600
(Alamdanga (Alamdanga Length=4.900 Sadar at
via ‐ Gangni over GC Km)
Kalihoda
Jugirhupa
(Ch. Bridge
Bhatoi
Bhomradanga
via ID
(Effective road
Dhapari
‐ Upazila GC District: Upazila
‐
11745m,
6500m 8235m Pacca No.:244422006, Jadhobpur
Upazila
‐ in
over
(Road R&H ‐ at GC Sarajgonj ‐
Damurhuda
portion), portion), Bathangachi Ch.
12+600
Ch.
‐ road
in Km, ‐
Khal in
8350m)
Hat Length road
in
00
ID 0+000
‐ at Total
‐ to
on No:
at GC Ch.
Ch.
=
02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 95 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 40 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 65 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 95 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 65 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 82232333255555 5 5 5 5 2 3 3 3 2 3 2 2 98 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 19 SL 9CudnaChuadanga Chuadanga 49 1Mgr reu Improvement Sreepur Magura 51 9Mgr oamdu D. Mohammadpur Magura 59 2Mgr hlk A. Shalika Magura 62 5Mgr oamdu Improvement Mohammadpur Magura 55 2Mgr oamdu Improvement Mohammadpur Magura 52 0Mgr aa Improvement Sadar Magura 50 4Mgr ahraaImprovement Bagharpara Magura 64 0Mgr hlk Implementation Shalika Magura 60 5Mgr ahraaImprovement Bagharpara Magura 65 6Mgr oamdu B. Mohammadpur Magura 56 3Mgr Magura Magura 53 3Mgr reu Construction Sreepur Magura 63 7Mgr reu C. Sreepur Magura 57 4Mgr reu Improvement Sreepur Magura 54 1Mgr reu B. Sreepur Magura 61 8Mgr Magura Magura 58
No. District Sadar Upazila
aa A. Sadar aa Improvement Sadar
Tree Ch.8950m Sreekol GC from Magura Magura 255952004) Ch.3500 Ch.3500 Sadar SRIIP Magura Rahobdaier 00m Chowbari, Chowbari, Uzgram Uzgram Rahobdaier Shalika Magura Shalika district
Improvement Improvement Implementation Improvement Implementation Improvement
road
to Plantation at
Upazila,
Upazila, Upazila, 5540m,
on Ch.5500m
‐ ‐ and and District district. district district at 5500m 5500m
Hatbari Hatbari to15300m, Sreepur (Ch:6+500
UP UP in Dhalgram Dhalgram
of
of of of of of of of of
District:
Sreepur
Office Office
& on 22.00m Magura Magura
of of of of UZR Upazial Upazial UZR Road Road UZR UZR of
Ch.
‐
and and
both of of UNR Langolbandh Kalamdari Ramnagor Bithulia GC Ch.6585m
‐
from from from from
5675m UNR
at at &
UZR
from from
bazar bazar to Nagra Nagra Chuadanga, 8+350 Upazila,
long
sides from district district Ch. Ch.4500m Ch.4500m road road
Alaypur
Sreepur Sreepur Katakhali Katakhali from from
hat RHD RHD Road Name 17300m
from from
RCC
to
Bazar Bazar
Arpara of from from bazar Km)
hat (ID:255952004)
under
Magura
8950m
Arpara sreepur road GC at at
Girder
R&H
under at at (Effective ‐ ‐
(Kamarpar) (Kamarpar) Binodpur Binodpur (Road Datarasta Datarasta
10710m 10710m
under
under
GC GC Ch.6650m Ch.3400m to
UP
from Mohammadpur
road
17500m UP
to to
district Bridge Office Magura (Kamarpara)
ID
Mohammadpur
Sreepur Isakhada Isakhada Office Nilmonigonj
at No: Length
GC GC
to to
Ch. at
to ‐ ‐
GC GC over in
9960m 6650m
Narikelbari Narikelbari
to to 215232003)
Sadar
Sreepur
to Khilgati
SRIIP 0+460Km,
to to
Upazila Nawpara Nawpara
= R&H R&H Khilgati GK
Alypur Alypur GC 1.85
Upazila
Upazila
(ID:255853015) (ID:255853015)
Canal GC
to
via via
Bazar Upazial,
Km) Upazial in
‐
Alypur
GC, GC,
Bazar R&H, R&H,
GC GC
Dingadah under (Road
Magura
AT in
in under
via Ch.
via via
Purba
at at
via
in R&H
ID:
45 51 45 65 58 30 0 0 0 0 0 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 20 SL 6Jessore 76 Jessore 74 Jessore 72 Jessore 71 Jessore 70 Jessore 68 0Jessore 80 Jessore 79 6Mgr bongrImprovement Abhoynagor Magura 66 7Jessore 77 Jessore 69 3Jessore 73 1Jessore 81 8Jessore 78 7Jessore 67 5Jessore 75
No. District
hrh Improvement Sharsha Construciton Bagharpara Improvement Monirampur Part Chowgacha Jessore Improvement Bagharpara Jessore Improvement Monirampur hwah Improvement Chowgacha Improvement Abhoynagor hrh Improvement Sharsha oiaprConstruction Monirampur ahraaImprovement Bagharpara ahraaImprovement Bagharpara ahraaConstruction Bagharpara Upazila
aa Part Sadar aa Improvement Sadar Monirampur at district Biddaydhorpur GC Ch.8950m on district. bazar, Putkhali district. Construction district bazar, under 00m at on
Ch. Ch:
RHD RHD via ‐ ‐
A: B: to
5590m 17600m. SRIIP Ch.2364m Ch.2364m Fatepur
Improvement Improvement
5540m, at at
BOP
Datta Datta to15300m,
‐ Upazial of of for of
of of of of of of of of of of of
Jamtala,
UP
road. Under & 90m 1 42m
Rasta Rasta ‐ ‐ Gorpara Upazila Road Rajgonj Road Churamonkathi Chandpara Road UZR Narikelbaria Road Rajgonj
11600m 11600m (one)
Ch. Road.
Long Long
Ch.1889m
Ch.1400m from of
of 5675m
‐ ‐ & from from from from Bagharpara
at no
Narikelbaria
Upazial
Upazial Ch. Narikelbari from bazar Bazar Ch.2456m
GCM
Ch.
Pre RCC of Benapole
RHD Amtala Amtala RHD Road Name 17300m under
to
Exploratory GCM
‐ 3228m Kashipur
Stressed
under Girder in under ‐
‐
8950m 7000m road Road 3200m.
bazar at at Monirampur
Upazial, Chowgacha
‐
Under Datarasta Datarasta
GC GC 2996m GC
GC
Custom ‐ to
from
Monirampur Sharsha 4808m Bridge from
under
to to
(Kathaltola) Girder & via
17500m via
Drilling Peruli Peruli Ch. Bagharpara
Chandpara
Chaibaria
Jessore & Hakimpur Chaibaria
Over
Colony
& Sadar
Ch. 8380m to to
Upazila
Bridge Upazila,
Upazila Ch.6300
GC GC Narikelbari Narikelbari
and 5900m
Dhalgram
Upazila
District.
via via Upazila to
to ‐
&
30m7 C5555 5 5 5 PC 7 6 4 5 6 1 2 3 3 3 2 3 2 2 70 13300m
Over
Test &
GC
Upazila in
R&H
Hariharangor
in Chandrapur Chandrapur Jessore Goga Agra
‐ Agra
‐ 03m7 0 6 1 5 2 3 3 3 2 3 2 2 70 10035m Jessore ‐
9158m. Jessore
Tube in ‐ Chitra
in
GC, GC,
Uttarpara
Boro
Hashimpur Bazar Jessore Uttarpara
in Jessore
district ‐
Ch. Well Jessore district
River Khal ‐
at
5223233325160 6 1 5 2 3 3 3 2 3 2 2 65 5223233325160 6 1 5 2 3 3 3 2 3 2 2 65 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 40 022323332160 6 1 2 3 3 3 2 3 2 2 50 8223233325160 6 1 5 2 3 3 3 2 3 2 2 58 522323332060 6 0 2 3 3 3 2 3 2 2 25 5223233325160 6 1 5 2 3 3 3 2 3 2 2 55 0223233325160 6 1 5 2 3 3 3 2 3 2 2 50 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status
0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 AS (ppm) STD 9107 8107 9107 9107 8107 9108 9107 9106 IV Ground Water NO3 (mg/L) STD Quality/Drinking
IV water for labors
8.5 ‐ 6.5 8.5 ‐ 6.5 8.5 ‐ 6.5 8.5 ‐ 6.5 8.5 ‐ 6.5 8.5 ‐ 6.5 5 8. ‐ 6.5 8.5 ‐ 6.5 PH STD IV Ecoli (n/100g) STD C555 5 5 5 5 PC 5 5 5 5 5 5 5 PC 5 5 5 5 PC 5 PC 5 PC PC C555 5 5 PC PC Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 21 SL 4Nri Narail Narail 84 2Jessore 82 7Nri oaaaImprovement Lohagara Narail 87 2Rjhh oaaiImprovement Godagari Improvement Rajshahi Mohonpur 92 Rajshahi 91 8Nri ai Improvement Kalia Narail 88 0Rjhh aoeImprovement Tanore Rajshahi 90 5Nri Narail Narail 85 9Nri Narail Narail 89 6Nri Narail Narail 86 3Nri oaaaRoad Lohagara Narail 83
No. District
aepr Tree Bagerpara Upazila
aa Improvement Sadar aa Improvement Sadar aa Construction Sadar aa Improvement Sadar GC district. district. Ch.3520m, Narikelbaria Ch.5408m at district. Ch.4650m 6+200Km Krishnapur, Ch.6600m Ch.14+300 Bagherpara 18950m
Ch.
road
Plantation
from
2295m
in
over ‐ ‐
‐
Ch.6600m, Ch.10920m, Narail Siarbor (ID:265762007)
Phatakata Upazila,
15+300 GC
‐ of
6380m of of of of of of of of
Kajila
on 90.00m at
UZR Mithapur UNR Mohonpur Jogania road UZR UZR
Sadar
(Ch:1+381 to both
Km) District:
Khal
from from from
Mithapukur
from from
(ID:265762007) Duboul,
(ID:265762007)
Upazila,
Long
sides
Hat (Effective
River
Hat
Gabtala Gabtala Gabtala
Godagari Upazila Kakon
UZ Road Name
‐
GCM Jessore
RCC of
2+794
GCM
Koilhat to on
Narail road
GC
(Pre
Dhopaghata hat under
the
Length R&H R&H R&H Narail
under
UP
via
Km from
GC
‐
Upazila road road district Stressed)
Upazila ‐ ‐ ‐ ‐
Narayanpur Lahuria
Kalia
, to Maizpara Maizpara Maizpara Sadar,
= Ch.
Lohagara
RHD
Gabtala at Hat 4.211
Narail
Upazila 3+122 Ch. GCM
Narail
bakoil at Narail Girder road,
9468m Km)
Dattarasta
GC GC GC
R&H
via
‐ Upazila Sadar, hat
Sadar, in
4+920
Ch.
via from from from under
itit 0 district.
Bridge Naonagor
Narail from ‐ to
30m2 5 2 3 3 3 2 3 2 2 25 13900m Kundain, 10750m
Narail
Maizpara
at at at in
Narail
Km ‐
Ch.00m
at Ch.00m Narail district
& Ch.
road
to
‐ ‐
5222233325 2 3 3 3 2 2 2 2 45 5223233325 2 3 3 3 2 3 2 2 25 0223233325 2 3 3 3 2 3 2 2 60 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution
STD
0.001 0.001 0.001
IV Compliance Status
0.05 0.05 0.05 AS (ppm) STD
IV Ground Water NO3 (mg/L)
STD Quality/Drinking
8 7.1
8 IV water for labors
8.5 ‐ 6.5 8.5 ‐ 6.5 8.5 ‐ 6.5 PH
STD
2 2
2 IV
0.09 0.09 0.09 Ecoli (n/100g)
STD
pc pc
pc 5555 Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD
55 55 5 55 5 55 Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 22 SL 1 ago osaImprovement Porsha Naogaon 112 0 .aagn C.Nawabgonj C.Nawabgonj 106 0 .aagn C.Nawabgonj C.Nawabgonj 107 0 .aagn ahlPart Nachol C.Nawabgonj 103 0 ago oaeprImprovement Mohadevpur Naogaon 109 0 asaiTnr Improvement Tanore Rajshahi 100 0 .aagn hbojImprovement Shibgonj C.Nawabgonj 101 0 .aagn ootprPart Gomostapur C.Nawabgonj 104 1 ago hmihtImprovement Dhamoirhat Naogaon 110 0 .aagn ootprImprovement Gomostapur C.Nawabgonj 102 0 .aagn hlhtImprovement Bholahat C.Nawabgonj 108 0 .aagn C.Nawabgonj C.Nawabgonj 105 1 ago ad Improvement Manda Naogaon 111 3Rjhh amr Improvement Bagmara Rajshahi 93 4Rjhh uhaImprovement Puthia Rajshahi 94 8Rjhh oopr Improvement Mohonpur Rajshahi 98 5Rjhh ah Part Bagha Rajshahi 95 9Rjhh ah Improvement Bagha Rajshahi 99 6Rjhh aoePart Tanore Rajshahi 96 7Rjhh amr Improvement Bagmara Rajshahi 97
No. District Sadar Sadar Sadar Upazila
(Niamotpur), Ch.5580m Improvement Ch.00m Krishnapur 1000m Ch. Ch.7215m 8346m Construction at GC road, road, Tanore Ch.850m approach Ch.8346m (Dhamoirhat Improvement
Bagha
to 00 ‐ ‐ ‐ ‐ A: B: B: A:
ID Ch. Kalinagor ‐
‐
13757m
Improvement Improvement Improvement Improvement Ch. ‐ 10500m
No.
‐ Ch.7215m
Upazila
00m 3850m road.
to to
16000m GPS
164502012
Part) Ch.13015m of 11246m, Ch.00m
‐ of of of of of of of of of of of of Ch.7595m
of of of at 48.00m GC
Nochnahar Hosnipur UZR Sonachandi Jholmoliahat Mohishbathan Mobarokpur Agradigun UNR UZR Hazigobindapur Ch. UZR
Sampur Digha Krisnopur
Ch.(4+180 Ch.00
via ‐ 20135m
4920m
‐
from from of of of of from 1040m from
Islampur
RCC Upazila GCM Upazila UZR ‐ UNR 5650m,
Hat Hat
Dhulauri Dhulauri
Daldali Hatgongopara GC
‐
Road Name Hat
RHD
5794m Girder ‐ GC from
7+610) ‐ at from
UP
at
at to
Mominpurhat
GC UP road road to at Bagha
‐
Mohonpur Bagmara
RHD UZR office shomnagor Modhuil
Sonaichandi
UP
Tanor
Akkelpur Fatepur to
Office bridge GC GC
ID:170183002 from
from
road, Khajur Chragpur office
Upazila to to (Tikoir
Upazila
at Kalinagor Kalinagor
to
on Upazila GC Kakonhat Arani
UP ID
‐
Upazila
GC
Ch.6140m ‐ Keshorhat,
R&H,
borogramhat Borgachi the
GC via o148076 5 5 5 5 5 2 3 3 3 2 3 2 2 60 No:164282007
hat)
in Office GC
to via
GC
in Rajshahi at Talandar road
in to
Bottoli
Ch.00 to
Raugram,
Rajshahi Puthia GC GC to in
GC Rajshahi
Akkelpur,
to Dhobra
Rajshahi from
Haripur
GC including via via ‐
Mallickpur Ch.00m ‐
4150m, Hatbakoil
Gc
via district.
‐ BOP, Islampur Islampur Upazila Shibpur
Dhulauri
district.
Ch.00m hat, district
hat
district.
‐
112m UZR
road
Ch.
GC
at GC, UP, UP,
‐
0 5 5 5 5 5 2 3 3 3 3 3 2 2 100 0 5 5 5 5 5 2 3 3 3 3 3 2 2 100 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 35 72233333255555 5 5 5 5 2 3 3 3 3 3 2 2 67 2223233325 2 3 3 3 2 3 2 2 12 0223233325 2 3 3 3 2 3 2 2 50 52233333255555 5 5 5 5 2 3 3 3 3 3 2 2 15 52233333255555 5 5 5 5 2 3 3 3 3 3 2 2 75 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 30 52233333255555 5 5 5 5 2 3 3 3 3 3 2 2 25 0 0 0 0 2 3 3 3 5 422323332 0 0 2 3 3 3 5 622323332 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution
STD 0.001
IV Compliance Status 0.05 AS (ppm)
STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking
8 IV water for labors
8.5 ‐ 6.5 PH STD
2 IV 0.09 Ecoli (n/100g)
STD 5555pc 5555 5555 Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD
55 55 Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 23 SL 1 ago Naogaon Naogaon 113 1 ago Naogaon Naogaon 119 1 ago imtu Improvement Niamotpur Naogaon 114 2 ago ad Construction Manda Naogaon 124 1 ago Naogaon Naogaon 117 2 ago hphrImprovement Shapahar Naogaon 122 1 ago antl Improvement Patnitola Naogaon 115 2 ago ta Improvement Atrai Naogaon 120 2 ago aagciConstruction Badalgachi Naogaon 125 1 ago Naogaon Naogaon 118 2 ago hphrImprovement Shapahar Naogaon 123 2 ago aagciImprovement Badalgachi Naogaon 121 1 ago Naogaon Naogaon 116
No. District Upazila
aa Improvement Sadar aa Construction Sadar aa Construction Sadar aa Construction Sadar aa Construction Sadar Parsomabri Road R&H Ch.3724 district. Ch. Portion) 164062011, R&H Gobindapur 5200.00m R&H from Shapahar Ch. Ch.5745m 3+500Km R&H
15221m 12902m ‐ ‐ ‐ ‐
Ch. in Katkhair Katkhair Katkhair Katkhair
Badalgachi
‐
from 3794m, 00m
Upazila, over
‐ over 10745m
Hat ‐ ‐ Badalgachi R&H
of of of of of of
Ch.18060m Ch.14242m Ch. to of of of of of of of
Kumarpur
GC, GC, GC, GC,
Shivo 70m 125.00m 20m 150.00m 42m 20m –NondaharKola
UZR UZR UZR UZR UZR Road Ch.5900m
Ch.3794
Hapania to
00m Naogaon
ID: ID: ID: ID: Upazila,
Cheragpur
RCC RCC RCC RCC
from from from from from river.
‐ From 164602005, 164602005, 164602005, 164602005, Ch.
Upazila
‐ RCC RCC Girder Girder Girder Girder
R&H (ID:164862003) and 4880m GC
Bottoli Modhuil Agradigun Patishor Modhuil 8650m),
Noagaon district. Road Name Kumarpur
to
Girder (Pre Ch.14553m
‐ Parshombari
GC Katkhoir Bridge Bridge Bridge Bridge Bottoli
&
‐ GC
Stressed)
Sadar Sadar Sadar Sadar
Road GC UZR Ch. GC GC
bridge
district. to GC
‐ ‐ R&H
to
at at at at 5600m
GC Chowbaria road,
Guala Guala
to Upazila, Upazila, GC Upazila, Upazila, at
‐ Shamaspara Shapahar Ch1280m Ch.14200m Ch13700m Ch.13450m
(ID:164472009)
Ch.15198m
Modhuil on Ch. (Chadpur
Hat
Girder at
ID
‐
UP UP the
Ch.10600m 6730m, ‐ 1000m Nandahar
No.:
Naogaon Naogaon Naogaon Naogaon ‐ ‐
road
Bridge GC
Nitpur Nitpur Upazila, on
GC
on
6621 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 20 164692010 Hat) on on
‐ GC
(Niamotpur Hapania 3500m, Road (ID:164862003)
from via Hapania
Hapania Hapania
(Barosauta)
‐ at GC GC ‐ –
Kola
itit 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 65 district. itit 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 district. itit 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 district. itit 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 district. at 14350m Talondar
Naogaon
Ch. ID:
Hazi
Ch. from from
GC
GC
GC
GC GC
at at
at
02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 55 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 30 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 50 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 24 SL 2 ago imtu Part Niamatpur Naogaon 126 3 Bogra 134 3 Bogra 131 4 Bogra 141 3 Bogra 137 3 Bogra 132 3 Bogra 135 2 Bogra 128 3 Bogra 138 3 Bogra 139 3 Bogra 136 3 Bogra 133 2 Bogra 129 4 Bogra 140 2 ago hphrconstruction Shapahar Naogaon 127 3 Bogra 130
No. District
hntImprovement Dhunot Bogra hbojImprovement Shibgonj oaaaImprovement Sonatala oaoaImprovement Sonatola adga Improvement Nandigram hru Improvement Sherpur Bogra atl Improvement Gabtali adga Improvement Nandigram hntImprovement Dhunot aikniPart Sariakandi hntImprovement Dhunat Sariakandi Upazila
aa Improvement Sadar aa Improvement Sadar 1000m Ch.3100m Ch.3300mto7300m Battali 5200m 14+366Km District Part Ch.3100m Ch.1000m Chowbaria district Panchullhat Kalmadanga Ch.2080 Part ‐ ‐ ‐
B: A: B: A:
‐ ‐
GC Improvemenof Construction Construction Improvement ‐ Ch.5200m Ch.9305m 4100m, ‐
‐
(ID:110672005) (ID:110672005) 2850m Road GC Chowbari
and
Khal of
of of of of of of of of of of of of (Manda)
99.00m
Kuchuapara, Sonmua UZR Bahopara Vair Karamja UZR UZR Sherpur Chandmuha Dhakhinpara UZR UZR ID:164862003
on
(ID:110952005)
(ID:110272008) (ID:110272008)
Modhuil of
of
Pukur from from from from from of GC
Kutubpur
BC 48.00m
road Long Fulbari
road NHW Hat Hat
(2Vent at at Ponditpukur Gossaibari Balua Ponditpukur Gossaibari NHW
Hat Road Name
(Niamatpur
Pre
Nandigram Nandigram Hat
at at Ch.15150m GC
Hat at
(Mohipur)
under
RCC
GC at Dhunat Sonatala
‐
to GC
Ch. via GC Stressed ‐ at
4.5mx4.50m) at Shibgonj at
to Ghoradhop
Dhunot Dhunot
Bogra Girder
to
Goala to Gabtali 2+441Km, Sonatola
GC GC Toronihat Shapahar
Rahbai
Goshaibari
GC GC Upazila
Upazila, Upazila, Portion) ‐ to to
Upazila
25367m to
Girder
Sadar
‐ ‐ UP
Bridge
Upazila Upazila, Upazila, Sonahata Sonahata
Upazila Kaligonj Kaligonj Ranirhat
to Upazila, NHW
Gc,
on Upazila, in
GC
Upazila
Nithpur
Bridge in Bogra Bogra
at
over Bogra
GC,
Battoli
Ch.1150m in
via
Bogra
Bogra Bogra Ch.3+250Km. via in
GC GC
GC GC GC Bogra
Bogra Bogra Durgahata Verendi
Boriahat itit 0 district. itit 0 district.
over
Noagaon , ,
in
district
via from from GC
Ch. Ch.
district GC
itit 0 district. itit 0 district. Bogra
district
road
‐ district itit 0 district. ‐ 00m 00m
3250m at at
Khal
Ch. Ch.
‐ ‐ at road,
on Ch.
82232333255555 5 5 5 5 2 3 3 3 2 3 2 2 18 82232333255555 5 5 5 5 2 3 3 3 2 3 2 2 78 32232333255555 5 5 5 5 2 3 3 3 2 3 2 2 93 82232333255555 5 5 5 5 2 3 3 3 2 3 2 2 68 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 25 SL 4 Bogra 142 5 Joypurhat 150 5 agu igcaImprovement Pirgacha Rangpur 158 4 opra acbb Improvement Panchbibi Joypurhat 146 4 opra aa Improvement Kalai Joypurhat 147 4 Bogra 143 5 opra aa Improvement Kalai Joypurhat 151 5 agu aagn Part Badargonj Rangpur 155 4 opra Joypurhat Joypurhat 148 5 agu ihpkrImprovement Mithapukur Rangpur 152 4 Bogra 145 5 agu ign Improvement Pirgonj Rangpur 153 4 opra keprImprovement Akkelpur Joypurhat 149 4 Bogra 144 5 agu anaImprovement Kaunia Rangpur 156 5 agu aagn Part Badargonj Rangpur 154 5 agu anaImprovement Kaunia Rangpur 157
No. District
dmih Improvement Adamdighi
Bogra hntConstruction Dhunat aikniImprovement Sariakandi acbb Improvement Panchbibi Upazila
aa Improvement Sadar
aa Improvement Sadar Ch.8100m (Ch. Durgahata district. Modhupur Ch.6650m road Km) Upazial, Upazila (Ch. Sadar Gossaibari Ch.3800m Ch.00m District: Ch.7000m
‐ ‐ 4680m 1180m under
A: B: at
Upazila,
Improvement Improvement
(Ch
Ch.
to Bogra District: ‐
(ID:138132008) to Ch. Ch. GC road Sariakandi ‐
GC
‐ 1000m 1+150 – 4680m),
Ch. of
7680m)
of of of of of of of of of of of of of of to District: Ch. 7000m 12400m in
75.00m at
Halalia Koriahat UZR UZR UZR Tree Beala Upazila Borobol Mondolerbazar UZR Tree UZR UZR Rangpur Sonahata SRIIP 10840m
1380m to ‐ (Ch 8180m
3+250
from from from from from from of of Plantation Plantation Upazila, ‐
2+080 Hat Bogra,
Long Hat
Nagerhat Nagerhat from
GC ‐ RM Ch.4500m
at Barodarga Panchibibi Punot Pukindipur Nabdigonj Nabdigonj RM GC
Km), Road Name
at to
Akkelpur RCC
to under
(Road Madhainagor
road District: Adamdighi
under Aftabgonj
‐ 4+100
of for
Torofkamalhat (Effective Bottoli
Girder GC GC
Baghopara at
Fulbari
Panchbibi ID (ID:185732003)
‐ Kalai –
– R R
GC Koria Ch.7600m
GC
Upazila, Bogra,
Km), No: Shyampur Shyampur K K ‐
Bridge ‐ (Damurchakla
road road
GC Moslemgonj Upazila
Upazila Vanderpur
‐ Length 110202007)
GC
Khangoirhat to (Effective
(Ch.
(Road
‐ to to NHW Upazila
Puranapoil Joypurhat
over (Cho.
Tornihat
under
Tepamodhupur Tepamodhupur
00m in GC
GC
= in
‐ ID 2.10 Bogra
Isamati
at Joypurhat Via Via
Ghoradhap
00m ‐ Length GC,
in
No: 2350m)
Rd.
Dhunot Pirgacha bazar) ‐
Atapara, Joypurhat Kather Kather
Km) GC
itit 0 District. road
Ch.745m
‐ district Ch.1500m 110812007) 3181m)
river via
= under
to
at 2.02 Upazila, district.
Bridge Bridge
GC, GC,
GCM Sadar on
‐
‐
0 5 5 5 5 5 2 3 3 3 2 3 2 2 100 0 5 5 5 5 5 2 3 3 3 2 3 2 2 100 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 45 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 95 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 50 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 45 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 75 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 55 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status Environment Hydrolozy Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 26 SL 5 agu igcaImprovement Pirgacha Rangpur 159 6 agu aaajb. Taraganj Rangpur 168 7 agu igcaImprovement Pirgacha Rangpur 173 6 agu agcaaImprovement Gangachara Rangpur 162 6 agu agcaaImprovement Gangachara Rangpur 160 6 agu igcac. Pirgacha Rangpur 169 6 agu ihpkrb. Mithapukur Rangpur 165 7 agu igcaImprovement Pirgacha Rangpur 172 6 agu Rangpur Rangpur 163 7 agu agcaaa. Gangachara Rangpur 170 6 agu ign c. Pirgonj Rangpur 166 6 agu agcaaImprovement Gangachara Rangpur 161 7 agu agcaaConstruction Gangachara Rangpur 171 6 agu aagn a. Badargonj Rangpur 167 6 agu ihpkrConstruction Mithapukur Rangpur 164
No. District Upazila
aa Improvement Sadar Rangpur, Rangpur 7631m Aftabganj near GC District. road district road Upazila, Rangpur Km), Rangpur GC Rangpur Rangpur, jamchowra road Ghaghot Km), district.
Improvement Improvement Improvement Improvement Improvement Improvement
(Dhamur (Dhamur
Tulshirhat (Effective (Effective from from from
(ID:185732003)
Rangpur
District. district. District. district.
river (Road (Road
GC at at at
Bazar.Ch1545m
Chakla Chakla
Ch.4620m Ch.6900m Ch.2340m of of Road
of of of of of of of on
Length Length
road
ID ID 54.00m 60.00m
of of of of of of UZR Tree UZR UZR Tree road UZR
District. the
No: No:
Deuty Chatra Khaleya Pathaner Okrabari chowdhury at
bazar) bazar)
at
road from from from
Ch. Plantation Plantation
from from
= = 185732003) 185732003)
‐ ‐ ‐ at at
Ch.6900m, Ch.10300m, Ch.4620m, long Long 6.176 6.176
Hat 2500m
Ch.
Prigacha ‐ ‐ Hat
from
Baithgati Baithgati Baithgati
‐ Borodarga Tapodhan Gonjupur
Madhupur Madhupur 6300m., Road Name
hat hat
RCC
RCC at 7+790Km
GC
Km) Km) Gopalpur
Betgari
Pirgacha at
at on on
in
Pre at Girder
Taraganj
Upazila, Badargonj
(ID:185272004), (ID:185272004), under under Mithapukur
both both
Pirgonj
to to to (ID:185272004), ‐ Upazial
hat Stressed
UP. GC
Kachua Kachua Kachua
GC GC GC in
Bridge hat sides sides
Upazila at
to Office Pirgacha Pirgacha
Gangachara ‐ road road
Kachua
Rangpur Upazila
Gangachara Upazila
Modhupur, Rangpur at
Upazila
Girder of of
GC GC GC
Mithapukur
at at Over Upazila,
to
in road road
via via via (Ch (Ch
GC Upazila, Upazila,
Gajaghanta
Rangpur in in Gangachar Gangachar
itit7 5 5 5 5 5 2 3 3 3 2 3 2 2 70 District
Borobol
Gangachar Bridge
Shellabari Shellabari Shellabari aa 0 Sadar ‐ ‐
in
Rangpur Rangpur from from via 1+380 1+380 Upazila,
Rangpur Ch.4500m Rangpur Upazila
Sharibari
District: District: Upazila Barodargah Barodargah
over district
to to GC
Rangpur district. GC district. Upazila, Upazila,
7+631 7+631 hat hat hat
in
‐ via
in
0 0 0 0 0 0 0 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 27 SL 7 agu ign Improvement Pirgonj Rangpur 174 8 amnra aiad a. Improvement Hatibanda Lalmonirhat 187 8 amnra aiojImprovement Kaligonj Lalmonirhat 183 8 amnra Lalmonirhat Lalmonirhat 181 7 amnra aga Improvement Patgram Lalmonirhat 178 7 amnra dtaiImprovement Aditmari Lalmonirhat 179 7 agu igcaImprovement Pirgacha Rangpur 176 8 amnra aiad b. Improvement Hatibanda Lalmonirhat 184 8 amnra Lalmonirhat Lalmonirhat 182 7 agu aagn Improvement Badargonj Rangpur 175 7 amnra aiad Improvement Hatibanda Lalmonirhat 177 8 amnra aiojImprovement Kaligonj Lalmonirhat 180 8 amnra Lalmonirhat Lalmonirhat 185 8 amnra dtaid. Improvement Aditmari Lalmonirhat 186
No. District Sadar Sadar Sadar Upazila
(ID:152552011) Upazial, Lalmonirhat Improvement Bazar (Effective Lalmonirhat Kushumbari 6100m) Luhakhuchihat Rangpur, Upazial, (ID:152552011) 3+181 0+000m at Improvement Rangpur, Upazila, in Kushumbari c. Improvement GC Luhakhuchihat district
Lalmonirhat Aditmari ‐ Shyampur ‐
Km), Torofkamal
District: District: District: to
(Road (Road Length
Ch.2+750m Upazila (Effective
from from district district.
of of of of of of of of of of
district from from GC
ID ID at at
Parulia Tree UNR UZR Jongra Upazila Nabdiganj
UZR Tree UNR
Lalmonirhat Lalmonirhat Rangpur of of = of of
at at
Sadar Sadar No: No:
via
4.620
hat
Ch.00m Millon Katkibari
Shathibari Panchim
Ch. Ch. Ch.4400m Ch.00m
from from
from Plantation from Plantation Length
Kather
185032003) 185763005)
via (Road
UP
GC 2391m 7575m road
Upazial, Upazial, Km)
Panchgharia Hat
Teesta Teesta
‐ Chandrapur Chandrapur ‐ to R 8720m Road Name ‐
‐
Chamterhat Haladabari
Hat =
Bridge
K ID under from Loskorerhat
Ch.
Hat ‐
3.00 ‐ ‐ under Road
Ch.5211m, Ch.8900m,
No: Ch. on on
District: District: under
4400m ZR ZR
under
Velabari
both
both
Badargonj road 8800m
‐ Km) 185732014) to to
Sadar Tepamodhupur
UP UP UP Mohendranagor Mohendranagor Hatibandha
Hat
under
sides sides Aditmari (ID:152393007) GC at Lalmonirhat Lalmonirhat
at
office Office Office and and
(ID:152393007) Upazila
GC (Ch
under (Ch. Patgram
of of
Upazila, ‐ Pirgonj Ch.5991m Ch.9238m to 1+180
road
under road road 1468m at at
Upazila
Shaptibari Hatibandha
in Upazila Tepur Tepur
Upazila, at Lalmonirhat GC from from
to
Upazila, Pirgacha District:
‐ via via (Ch
Ch.
at 6+000 ‐ ‐ (Part)
in Ch.7012m Ch.9480m Bazar Bazar
Mondoler Nagerhat in at Kaligonj ‐
0+00 4520m)
Zila
(Ch.00m Kaligonj
Upazila
District:
Ch.
‐ ‐ Km),
road
to
‐
02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 50 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 40 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 85 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 65 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 65 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 55 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 55 0 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 28 SL 8 amnra Lalmonirhat Lalmonirhat 188 9 amnra dtaiTree Aditmari Lalmonirhat 190 9 iaprFlaiImprovement Fulbari Dinajpur 193 0 iaprBrojImprovement Birgonj Dinajpur 201 9 iaprPbtprImprovement Pabatipur Dinajpur 197 9 iaprDinajpur Dinajpur 199 9 iaprKhrl Improvement Kaharole Dinajpur 194 8 amnra aiojTree Kaligonj Lalmonirhat 189 9 iaprBri Improvement Biroil Dinajpur 191 0 iaprDinajpur Dinajpur 200 0 iaprGoahtImprovement Ghoraghat Dinajpur 202 9 iaprBrojImprovement Birgonj Dinajpur 198 9 iaprHkmu Improvement Hakimpur Dinajpur 195 9 iaprKasm Improvement Khansama Dinajpur 192 9 iaprDinajpur Dinajpur 196
No. District Sadar Upazila
aa Improvement Sadar aa Improvement Sadar aa Improvement Sadar
Sundarban Construction Amtail Sadar Nagar road District Sundarban Amtail (Upto district Aditmari Sadar Parbatipur 9025m District Lohakuchihat road Km) Sonamukhi Nayanagar Hakimpur Ghoraghat
UNR
Plantation Plantation at at
Upazila, Upazila, Parbatipur via
Ch.00m Ch.2850m
in (Ch: Ch.00.00m
Upazila,
under
SRIIP Kursamari Upazila
Upazila Upazila, GC road road road
0+00
of
road
of of of of of of of of of of of of Dinajpur Dinajpur Road ‐
2850m
on on
42.00m Kaligonj
from from UZR, Madila UNR Road UZR UNR Kashidanga Road UNR UNR Road Pakerhat from
‐ ‐ Bordar) District: 5700m
‐
both both
8+7200 at 5250m, Dinajpur
at road
from
(Ch:4+400
from from from from
Ch.13650m Ch.10300m from at
From From From Ch. (ID:127123009)
Ditrict Ditrict
long hat
sides sides Upazila, Ch.980m
(ID:127123009)
at
at Lalmonirhat
GC
1945m
D.Shibpur
Km) Bhognagor Bottolihat Palash Bhognagor Road D.Shibpur
GC Ch. Road Name
Bhabanipur Rajigonj Hill Ch.2378m
to district RCC
to of of
Ramnagor
to (Effective
4020 ‐ GC Saidpur road road
ID: District: ‐ ‐ Girder ‐
‐ 8+800 17000m 13650m Ambari UP 4695m, Ch.4347m,
–Katla
127642005,
– ‐
to ‐
from from 15550m to to
Azad Jamtoli UP UP at in
Madhobpur
Balogary Bridge Bazar Km) Madhobpur RHD,
Lalmonirhat
Sadar at
Birgonj Length
hat Office Office via GC
Road
(ID:127642018) (ID:127642018)
Vhelabari Zila Kaharole Birgonj
(Effective
Ziaoly from
(ID.No.:127433005), GC,
Ch. – Road –
on
road Upazila,
Noshipur ID:
Ambari
to to
Dinajpur =
Upazila,
bazar 00 Ch.
Tista
3.000
Satkuri
Kaharole Kaharole
127472003,
Upazila, ‐ ID: (Ch.
‐ ‐ Chandarpur
7200m
GC, 8300m Birgaon GC Birgaon
Length
127772004,
road ZR
Rudrani Lalmonirhat
‐ 00m
Km)
Ch. Dinajpur – Sadar
‐
Saptibari Rail at at
Motunirhat
Mohendra
Dinajpur
‐
Upazial Upazial via
‐ 00m ‐ Dinajpur Dinajpur under 10870m)
‐
= 18450m Gate
pza 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 65 Upazial 4.400 road
UP ‐
Zila ‐
via
via via
0 5 5 5 5 5 2 3 3 3 2 3 2 2 100 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 50 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 70 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 20 52232333255555 5 5 5 5 2 3 3 3 2 3 2 2 75 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 50 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status
Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 29 SL 0 iaprGoahtImprovement Ghoraghat Dinajpur 203 1 hkranRnsaki Improvement Ranishankail Thakurgaon 216 0 iaprBrlImprovement Birol Dinajpur 205 1 hkranHrprImprovement Haripur Thakurgaon 215 1 hkranRnsaki Improvement Ranishankail Thakurgaon 217 1 hkranThakurgaon Thakurgaon 212 1 hkranProjImprovement Pirgonj Thakurgaon 210 0 iaprKasm Improvement Khansama Dinajpur 208 1 hkranBlaag Improvement Baliadangi Thakurgaon 213 0 iaprGoahtConstruction Ghoraghat Dinajpur 206 0 iaprBrlConstruction Birol Dinajpur 204 1 hkranThakurgaon Thakurgaon 211 1 hkranHrprImprovement Haripur Thakurgaon 214 0 iaprKhrl Improvement Kaharole Dinajpur 209 0 iaprSdrConstruction Sadar Dinajpur 207
No. District Sadar Sadar Upazila
Hi Hat, via Ch.3050m Motunirhat Debipur Part Ch.6100m meter) 4850m Ramnagar Sonamukhi Upazila, (ID.No.:127433005), Ch.4950m hat, GC
11725m Palash Purnabhava 7+200m), Upazila, Ziatli Part
Mutuni to
‐
Ch. ‐ Ch.
A: ghat B:
National
UP
to Improvement
under Improvement
Uil 4000m 1341m Dinajpur Dinajpur UP
‐ 5300m Office road Khansama Bazar (ID:194862009) (ID:194862009)
Ch.8550m
GC
road
office, via River
of of of
of of of of of of of of of of Kahrole
road
Highway ‐ ‐
Jamtoli at 7640m 60.00m 90.00m 30.00m Ch.4950m
Tk via Tree UNR UZR road UZR UZR Bhanga Tree Baliadangi UZR from to
district district. and on Ch.2+110km
Ch.7000
Bolagari
at Ziaoly
Ghoraghat
the
from from from from
Upazila, and
of from Plantation Plantation
ch.6240m (Tree
of at (Ch
Upazila, and
long long long
via
Shibgonj
Ruhia Madrassa Ch.4347m in road
‐ Ch.8657m
00 ghat
Ranishankail Ranishankail Mirdangihat Jadurani Mirdangihat Jadurani (ID:194512007)
‐
Palash SRIIP Nashipur College Camperhat
ii di 15200m Plnatation) Road Name Hat
RCC RCC RCC
to
District: from
UP
District: in
at
Upazila,
9025m), road to of
on GC Girder Girder Pre
Birol
Ch. UP office
‐
RHD 11500m
Bottoli to Ch.8844m, kashidanga GC GC
‐
both
‐ Ch.9220m to
road
at Stressed
to
0+00km
Moharaza Dinajpur
Upazial,
to to
Road from ‐
Dinajpur Choto R&H R&H
Upazila, Upazila,
Ch.8+890km Nakkati Balogary Bridge Bridge Dinajpur to
(Effective
sides
Mirdangi Mirdangi
at
Hat
at Eagoromile
Kashidanga to to Ch.4+295km
(Ch. Haripur
‐
‐ Khochabari
Girder
Ch.10488m of Dinajpur on over Kathihar Kathihar GC (ID:194512007),
10+870km Azad
GC Thakurgaon Thakurgaon GC,
0+00m district bazar Road
‐ Ranigonj
Length Ramnagar
R&H R&H via
Mahila
Ch.
in Kahrol Bridge Upazial,
NHW Bhabanigonj Ghoraghat road
from
district.
GC GC via Via 570m GC to
in
NHW, ‐ =
Ch.11470m
Ch.
–
River Ch.1315m Ch.3050m
Bagaon to
Bangaon 6041 Sadar Ferry
over district. district. via
via
Pakerhat
Bazar District:
to
Ch.
on
Ghat
via hat
‐ ‐
52 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 50 52 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 60 02232333255555 5 5 5 5 2 3 3 3 2 3 2 2 40 70 70 0 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 223255555 5 5 5 5 22323332 22 3255555 5 5 5 5 22323332 22 3255555 5 5 5 5 22323332 223255555 5 5 5 5 22323332 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 30 SL 1 hkranRnsaki Improvement Ranishankail Thakurgaon 218 2 acaahSdrImprovement Sadar Panchagarh 227 2 acaahBd Improvement Boda Panchagarh 229 2 acaahDbgn Improvement Debigonj Panchagarh 224 3 acaahBd Improvement Boda Panchagarh 232 1 hkranRnsnalImprovement Ranisankail Thakurgaon 219 2 hkranThakurgaon Thakurgaon 222 2 hkranThakurgaon Thakurgaon 220 2 acaahAwr Part Atwari Panchagarh 225 2 acaahSdrImprovement Sadar Panchagarh 228 2 hkranPrajTree Pirganj Thakurgaon 221 3 acaahBd Improvement Boda Panchagarh 230 2 acaahTtlaImprovement Tetulia Panchagarh 223 2 acaahAtwari Panchagarh 226 3 acaahBd Improvement Boda Panchagarh 231
No. District Sadar Sadar Upazila
Nakkati Atwari Ch.8200m Panchagorh District. Ch.9200m Tree 5764m, Egaromile road Ch.11700m Improvement Thakurgaon district. Putimari Panchagorh Boda, district. Shalshiri, Part Ch.47000m road hat,
‐ ‐ Ch.
B: A: Plantation Plantation from from
Panchagarh
road, Imp. Imp.
ID:177342006, GC 00m
Road.Ch.0+460
Ch.00m ‐
NHW at at (ID:194862009) 11700m
‐ ‐ via
16465m 8200m
District. District. district. Of Of
Ch.6169m Ch.3790m Ch.1250m to
of of of of of of of of of of of
Bhabangonj
UZR UZR
on on 7094m,
via UZR UZR Road Srakarpara UZR Kathirhar Ramnath UZR UZR Bahazanpur UZR
to
district. both both
(ID: (ID: Debipur from from
(ID: Ch.3220m from from from from from from
From
Debigonj ‐ ‐
to
177252005) 177252005) ID:177903003, ‐ sides sides
4+350km.
177252005) Ch.6325m Ch.3790m Nurumandolhat Fakirgonjhat
Ch.11498m, hat hat Ranishankail
Mirdangihat Rajali Sakowa Rajali Sakowa Sakowa hat
Road Name R&H Sakowa U.P.
Gc
of of
(GC) (GC)
road
to road road
Upazial, R&H R&H Office to
Parabari GC GC GC at
(ID: at
(ID:17732010) (ID:17732010)
Kaligonj Upazila Upazila at GC
Upazila from from Sadar to to ‐ ‐ ‐ Ranisankail
GC
Ch.
Tetulia
‐ 177252005) road R&H Maidandigi Maidandigi Maidandigi Upazila,
Maidandeghi Nur Nur
Panchagarh
GC to
4000
Ruhia Bhanga
Upazila UP
Boda, Boda,
GC Goalpara at
to
Mandal Mandal to Boda,
Upazial,
Ch. office
Kathihar ‐
road, Panpara Thakurgaon 7640m
Upazila Cinema
Panchagarh Panchagarh
at at
70000
GC, GC, GC, Madrasha Panchagarh in under
GC GC
Sadar Sadar District. via Ch.
GC Thakurgaon R&H
Panchagarh
from from from
(Effective ‐
via via GC
Dungadhari Jholai
Via ‐
4284m in Hall
1520m Upazila
via Upazila Upazila
Jhalaihat Jhalaihat Ch.6100m
district. Ulipukuri at at at
‐
RHD
district. district. Puraton
‐
‐
in in
‐
100 100 60 10 10 15 0 0 0 0 0 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 223255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 31 SL 3 acaahTtlaImprovement Tetulia Panchagarh 233 3 abnh udrojPart Sundargonj Gaibandha 235 4 abnh oidgn Improvement Gobindagonj Gaibandha 240 3 abnh oidgn Improvement Gobindagonj Gaibandha 237 4 abnh udrojConstruction Sundargonj Gaibandha 247 4 abnh oidgn Improvement Gobindagonj Gaibandha 243 4 abnh Gaibandha Gaibandha 245 3 abnh Shaghata Gaibandha 238 3 abnh hgaaPart Shaghata Gaibandha 239 4 abnh hgaaPart Shaghata Gaibandha 241 3 abnh oahaiImprovement Polashbari Gaibandha 234 3 abnh Gaibandha Gaibandha 236 4 abnh udrojConstruction Sundargonj Gaibandha 246 4 abnh Gaibandha Gaibandha 244 4 abnh oidgn Part Gobindagonj Gaibandha 242
No. District Upazila
aa Improvement Sadar aa Improvement Sadar aa Improvement Sadar office, (DPP), from Schlller Kochashahara Taltola GC Ch.9995m Gaibanda Ch. B:
Bewwagram Badiakhali Baluabari 5+920 Mazumdarhat Upazila, Mojumdar District: Bewagram Upazial, Gobindagonj GC Gaibanda Part
Mazumdarhat ‐
at 7885m ‐ ‐ ‐ ‐ ‐ Buraburi
B: A: A A:
Mojumdarhat B Ch.2500m
Ch. Km),
Ch.
(UNR):
(UZR): bazar Improvement Mazumdarhat Improvement bazar,
Panchagarh, District Gaibandha
road
District. District. ‐
1370m
4300m
road, Ch.12200m) Hat from
(Effective
from Upazila, road
of of
UP
Improvement Improvement
of of of of of of of of Ch. bazar
GC from GC
54m 48m
‐ :
Ch. Ch.
Tree UNR From UNR UZR Polashbari Road UZR
8300m GC Office Gaibanda
‐
to
‐ to 2000. 8250m Ch. (ID.No.:132242011) Naldanga
GC
district
8590m 4000m
at road to Ch.
Naldanga
Long RCC
(Road
from from
of of District: from from Plantation Length
00m GC from
Katabari
Ch. to
Naldanga Sundargonj
road
UNR UZR to 4750m,
Girder to at
Naldanga
RCC
‐
(i) Gaibandha 1515m 4900m
Rajahar Rajahar
‐ ID
UZ to Boali Road Name
of Naldanga of Ch.
Ch.4000m
GC
road via Ch. = from Trimohini
Gaigandha
No:
Ch. GC, Girder Bharotkhali
0.750 HQ Kachuahat UP
2050m
Road bridge
Dungdungir on
6950m GC, Up
‐
from
9840m
177903003) Ch.2715m Salmara Ch.6000m to
to
UP UP upazila, both GC
office
Km)
Chatra Kamdia
bridge at Ch.
to GC,
from
Office Office
‐
(ID: at over Shaghata R&H 6160m
Ch: (ID:
Kamarzani
sides
3074m
under Sundargonj
Ch.00m
to
R&H to
132303008 UP
Gaibandha
at
5793m Langa 132303008)
over hat to Gc
Saghata (ID.No.:132242012) at at to GC Fulchari
of Ch.5100m (Railway
Tulshighat
via UZR UZR
to ch. Tetulia
road
(Tulot), to
road GC Bamnir
to
Nayabanda Khal
Kishoregari
9100m Sundargonj Ch. GC
to to
to
ch.
Hospital at Upazila,
Upazila from
at
district
Birat Birat via Mohimagonj 6000m, on Upazila, Station)
(Ch
3074m, Ch. ‐
at Khal Gobindagonj Ch.5224m,
GC Miapara the
‐ Bhajanpur
5+200 hat hat 1000m
via
via
on road
to road UP
Upazila, Part
to
GC GC
Part
Sadar
to
via via ‐ to
C: ‐
75 55 95 80 15 35 60 55 45 96 35 82 35 35 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 32 SL 4 abnh aht Construction Saghata Gaibandha 248 5 abnh udrojImprovement Sundargonj Gaibandha 252 5 abnh oidgn Improvement Gobindagonj Gaibandha 257 6 uirmUiu Improvement Ulipur Kurigram 261 5 abnh oidgn Improvement Gobindagonj Gaibandha 253 6 uirmNgsaiImprovement Nageswari Kurigram 262 4 abnh oahaiImprovement Polashbari Gaibandha 249 5 abnh oidgn Improvement Gobindagonj Gaibandha 256 5 abnh aht Construction Saghata Gaibandha 254 5 uirmFlaiImprovement Fulbari Kurigram 259 5 abnh aulprImprovement Sadullapur Gaibandha 250 6 uirmKurigram Kurigram 260 5 abnh udrojImprovement Sundargonj Gaibandha 255 5 abnh aht Improement Saghata Gaibandha 251 5 abnh Gaibandha Gaibandha 258
No. District Upazila
aa Improvement Sadar
aa Improvement Sadar (Road Fulchory road Upazila 6420m at (Effective Sundarganj Upazila, (Road Gaibandha 5+600Km Ch.00m district. UP Kurigram Km), Saghata Gaibandha Length Gaibandha.
UZR ‐
Kamdia (Effective at
ID ID
road
= ‐ (Ch road
Ch.4630m Upazila, Gaibanda
No: No: Upazila 2.00
Length over ‐
‐ Upazila, 00 (Road
GC
from of 132303006) 132243027) of of
Birat
Km) of of of of of of of of of of of of
to Kalpani Length
Munshir 75m 90.00m (Tulot)
Tree Panchpir Tree UZR Katakhalibalua UNR Talukzamari Tree Fulbari Mirpurkachari Zatinerhat Tree Gaibandha
via = 9100m),
ID
Saghata district.
under hat 1.00 (ID:149613030)
District: Schooler
long No:
from from Plantation Plantation Plantation Plantation
=
GC Khal road
Km)
long GC 2.00
hat Gobindaganj 132303008)
RCC hat road
(Effective
Ulipur GC ‐
Ramkhana to
on Fulbari
Road Name district
under at under
Gaibandha
RCC
Km) hat
Bazar
under to Girder
Mogolbassa
Saghata
(Ch via
hat hat
& on on of
Moimagonj
under (Pre GC under
‐
Bewargram
Caretaking Saghata Sadar 0+000
at to
Mojumdar
under road
both both under
Length ‐ Sundargonj
Bridge
‐ Nageswari
Nageswari Chuniar Stressed) Upazila, UP
GC
Polashbari Gobindaganj
at sides sides
Upazila,
Office
Sadullapur to
Gobindagonj
to
UP
Upazila, (Ch
=
over
7+885
GC Mohimagonj 8000
of
(Ch. Hat par of of ‐ District: at
3+500
Girder
to
Upazila, at
Upazial, Boali
UZR
road road Fackkatair (Ch District:
R&H, GC
Upazila,
00m Andharijhar Ch. meter) Km),
abnh 5 Gaibandha
‐
Upazila,
Upazila, 0+000 (3250
–
UP to from from
7600m Bridge
Gaibandha. ‐
Naldanga Upazila,
10)80 3130m) at
(Effective
abnh 5 Gaibandha 4+500
District
office
Gaibandha,
under
Ch. GC Gibandha
‐
Rajahar Katabari Khal 10 75 5150m to
District:
at Road Saghata
850m
6+690
Bazar,
Km), –
Ch. on :
GC
in UP
‐
80 0 0 5 0 5 5 0 5 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 33 SL 6 uirmRwaiImprovement Rowmari Kurigram 263 7 ipaaiNilphamari Nilphamari 276 6 uirmRwaiTree Rowmari Kurigram 268 7 ipaaiDmaPart Dimla Nilphamari 273 6 uirmRjra Improvement Rajarhat Kurigram 266 7 ipaaiNilphamari Nilphamari 270 6 uirmRwaiImprovement Rowmari Kurigram 264 7 ipaaiSydu Part Sayedpur Nilphamari 271 7 ipaaiKsoeojConstruction Kishoregonj Nilphamari 277 6 uirmKurigram Kurigram 267 6 uirmNgsaiImprovement Nageswari Kurigram 265 7 ipaaiDmrPart Domar Nilphamari 274 6 uirmUiu Tree Ulipur Kurigram 269 7 ipaaiKsoeojPart Kishoregonj Nilphamari 272 7 ipaaiNilphamari Nilphamari 275
No. District Sadar Sadar Sadar Upazila
aa Construction Sadar
GC, Ch.4630m Construction Ch.4082m Upazila, Kurigram Karigram ghat Badrijhar 9850m Babrijhar Nilphamari Ch. Bazar Ch.2400m Rowmari district. Hazarihat 1.00 Baravita (Durgapur ID:149523007) Upazila, Office, road Improvement 2685m
1275m Ch.2224m ‐ ‐ ‐ ‐
B: A: A: B: Km) via Plantation Plantation at
road
at
Improvement Improvement (ID:173643021), Improvement Improvement Ch.
mothertila District: Nilphamari GC
under Upazial,
Ch.00m GC GC GC ‐ ‐ ‐
‐ rail Ch.8137m Ch.4615m
at Ch.2633m, 850 Sadar
Ch.7000m road ‐
to
of of of road,
Ch.460m
‐ of of of of of Kachukata line)
6460m.
‐ Sadar
Kachukata on on Rowmari 60.00m 39.00m 30.00m 6420m
UZR UZR UZR
UNR UNR Kurigram,
‐ at
Upazila, District: 1300m
both both Ch.7922m
to
road Ch. district
from from from Upazila,
(ID:149613030) (ID.No.:149772004) of of of of from from Mogolbasa
‐ (ID:149792002) and
3800m (Effective
2+700Km,
long long Long Nilphamari
UNR Upazial sides sides Upazila UNR at
R&H Upazila,
Nilphamari
Karigram
R&H
Jadurchar Nazimkhan Jadurchar
Ch.3056m (Road (Ch:1+275 Ramkhana Sonaroy in Road Name
RCC RCC
from from
RCC ‐ of of
SRIIP Kurigram 9972m via ‐
road road road road Panchapukur
Length Girder Girder ID UP
Panchapukur District: Girder
(Road Dimla Dharanigonj
Sadar UP No:
at
to to ‐ from
from ‐ from from at
district.
Ch.3210m
UP GC at ‐
3+210 Ch.1+475Km, district
Char Char
Nageswari
149942010) Bridge Bridge
Simultali ID:173452002)
= Bridge UP
Rowmari
Office Rajarhat Upazila, to
Kurigram
4.00 Kishoregonj NHW Ulipur Jadurchar
(Post
Fakirerhat Fulbarighat Fulbarighat
Km) GC,
in
over on GC Km) Hat
on
to near (ID:149792002)
SRIIP
GC
Bazar,
Office)
Ch.00m
Nilphamari,
Kishoregonj (Effective
Upazila, Upazial, at Andharijhar Zatinerhat
Upazial,
Harichara
under Burikhora ‐
‐ Ch.5+950km Majhapara (Road Chuniarpar
GC Char GC
Kishoregonj
Ch.00m
via via to
‐
to Ulipur
from
Kurigram District:
District
Barovita
Jorgiga
Mothertila Mothertila Fulbari
Length Ch.
UP
River
GC Bazar,
at
‐
‐
at
R&H
to
:
=
on
40 50 70 50 20 40 20 0 0 0 5 0 0 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 34 SL 7 aoeNatore Natore 278 8 aoeBgtpr Tree Bagatipara Natore 285 8 aoeSnr Improvement Natore Singra Natore 284 Natore 283 8 aoeSnr Improvement Singra Natore 281 7 aoeBrirmImprovement Baraigram Natore 279 8 aoeSnr Improvement Singra Natore 282 8 aoeBgtpr Improvement Bagatipara Natore 280
No. District Upazila
aa Improvement Sadar aa Tree Sadar UNR Uil Uil Chalkaguasha Ch.5500m Dakmondop via Dakmondop Ch.2200m Dakmondop Bottola, d
Sayed
Plantation Plantation Bi d
Dodangi ii Di i Di
more ‐ ‐ 8919m, 4175m Sd
hat, Hat hat,
of of of of of of road
road on on
Road UZR Road Road UZR Road at Ch.8600m Ch.6350m Railgate N N Uil Uil
Road
both both (ID:169633018), at Ch.
at
from from
Ch. from From From From
4095m
Ch.
ID: sides sides
5640 Road ii Di ii Di
Khajortola Khajortola
5500
‐ ‐ 169152008,
Halsha Road Name Ch.10550m Ch.8600m Kajurtola Rajapur Tomaltola
of of ‐ ‐ 6350m,
9300m at
‐ road road 8800m
Ch.
N N
UP Upazila
GC
from from R&H R&H RHD 5640m
to GC (ID:169912013) (Effective Road
‐
(ID:169912013) Gopalpur Baraigram (Effective
Barobarihat
–
Rd (R Rd (R – to to
Sadar, Tomaltala Halsa
Dhigha
Shamaspar ID: ‐
Shamoshpur Shamoshpur 9300m
169912013,
Length
ID ID
Upto
GC Natore Length
Upazila Hat N N
Road Road
via GC
at Borobaria
GC
169633018) 169092006) GC at =
‐ Sayed
Singra
District =
2.00
GC GC Singra ID: Digahat
at
via Rd. 0.700
Singra
via via
Sajimara
Km) via Moure,
hat Km),
via
100 10 35 80 32 80 0 0 Physical Progress (%) opineSau ComplianceStatus Compliance Status 22 3255555 5 5 5 5 5 5 5 5 5 22323322 22323322 223255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 22 3255555 5 5 5 5 22323322 223255555 5 5 5 5 22323322 Hydrolozy Environment Natural Drainage Congestion
Erosion & Silt deposition
Landscape future visual Intrusion
Workforce Camps Environment Economic
Waste Management
Health & Safty
Vactor bone Disease IV TSS(mg/L) STD IV TP (mg/L) STD IV DO (mg/L) STD Surface Water IV BOD (mg/L) Quality STD IV PH STD IV Oil & Grease (mg/L) STD Compliance IV TP (mg/L) Environmental Pollution STD
IV Compliance Status AS (ppm) STD
IV Ground Water NO3 (mg/L) STD Quality/Drinking IV water for labors PH STD IV Ecoli (n/100g) STD Compliance IV SO STD 2 (µg/g) IV NO2 (µg/g) STD Air Quality IV SPM (µg/g) STD Compliance IV Noise (dB) STD Noise Compliance IV Fuel & Chemical STD spills (mg/g) Soil Contamination Compliance 35