DDHC Paper No. 9/2019 (for discussion on 25.3.2019) District Development and Housing Committee, Southern District Council Progress Report on Planning Works in the Southern District

Annex 1 Matters discussed at previous meetings that required follow-up actions (Progress as at 11.3.2019)

Annex 2 Planning Department-Progress Report on Planning Works in Southern District (Progress as at 28.2.2019)

Annex 3 Highways Department-Progress Report on Road Works in Southern District (Progress as at 28.2.2019)

Annex 4 Civil Engineering and Development Department-Progress Report on Other Works in Southern District (Progress as at 28.2.2019)

Annex 5 Housing Department-Progress Report on Public Housing Works in Southern District (Progress as at 28.2.2019)

Annex 6 Food and Environmental Hygiene Department-Progress Report on FEHD District Minor Works in Southern District (Progress as at 28.2.2019)

Annex 7 Lands Department-Progress Report on Lands Department Temporary Government Lands Allocation in Southern District (Progress as at 28.2.2019)

Annex 8 Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites (Progress as at 28.2.2019)

Abbreviations for government departments in this report: (in alphabetical order) ArchSD Architectural Services Department CEDD Civil Engineering and Development Department DSD Drainage Services Department EPD Environmental Protection Department FEHD Food and Environmental Hygiene Department HD Housing Department HyD Highways Department LandsD Lands Department LCSD Leisure and Cultural Services Department MTR Corporation Mass Transit Railway Corporation Limited PlanD Planning Department WSD Water Supplies Department

1

Annex 1

Matters discussed at previous meetings that required follow-up actions (Progress as at 28.2.2019)

Latest Progress on Matters Date of First Discussion (Date of updates) 1. Ex- Quarry 26.7.2010

PlanD/HyD/MTR Corporation/LandsD (19.11.2017)

The ex-Shek O Quarry site falls within an area zoned “Undetermined” on the and Shek O Outline Zoning Plan (OZP). The “Undermined” zoning, under which all proposed developments would require planning permission from the Town Planning Board, will ensure that any interim development will not jeopardise the future planning and development of the site.

In 1994, the then Civil Engineering Department commenced the Shek O Quarry rehabilitation works, including tree planting trials and artificial nesting sites, and the concept of developing the rehabilitated quarry into a water sports centre was considered. The rehabilitation works was completed in 2012, and the site has been used as a casting basin of immersed tube tunnel units for the Shatin to Central Link project since end 2014. Upon completion of the immersed tube project as well as the demolition, removal and reinstatement works of the site by the MTR Corporation Limited (MTRC), the concerned land is expected to be handed over to the Lands Department or before upon the expiry of the Temporary Government Land Allocation (i.e. 31.12.2019). PlanD will review the zoning of the subject site and consult the District Council on the proposal.

2

2. Request to Improve the Drainage System of the Villages in Southern District 16.5.2011

(I) On Pokfulam Village (13.3.2018)

DSD is now refining the project design.

3. Long-term Uses of the Site of Former Aberdeen Fire Station (AFS) 26.3.2012

Home Affairs Bureau (3.1.2018) The funding application on the project on “Development of Arts Space and a permanent office of the Arts Development Council at ex-Aberdeen Fire Station site (the site)” (the project) was approved by the Finance Committee of the Legislative Council on 22.4.2016. The approved project estimate of the project is $348.6 million in money-of-the-day (MOD) prices. Facilities to be provided include arts studios for renting to visual artists and media artists at affordable rates, an exhibition gallery and an arts information centre. The site will also accommodate a permanent office for the Hong Kong Arts Development Council (HKADC). The site has been included in the quarterly land sale programme for July – September 2016. The Lands Department announced in October 2016 that the tender for the site (Aberdeen Inland Lot No. 462 at Yip Kan Street and Road, Wong Chuk Hang, Hong Kong) was awarded to the Grand Apex Limited (parent company: Sino Land Company Limited and Empire Group Holdings Limited), on a 50-year land grant at a premium of $2,528 million. It is expected that the construction works can be completed in 2022. Details of the project are available in the Finance Committee documents. http://www.legco.gov.hk/yr15-16/english/fc/pwsc/papers/p15-54e.pdf

The Home Affairs Bureau noted that District Development and Housing Committee (DDHC) would like to have more details on the progress of the works project. As the project was at its initial preparatory stage, more information would be provided to DDHC when available.

3

4. Planning Application for the “Comprehensive Development Area” Site in Wong Chuk Hang 26.11.2012

A motion was passed at the Southern District Council (SDC)’s meeting on 22.9.2016 that “This Council strongly urges (13.3.2017) MTRC to ensure that the (East) should be ready for commissioning as scheduled at the end of 2016, and that shopping malls, performance venues, community welfare facilities, public open space and improvement of the Public Traffic Interchange will be built simultaneously when building the first phase of the residential properties on the site of the previous .” DDHC on 23.1.2017 requested the construction of a footbridge connecting the Wong Chuk Hang Comprehensive Development Area and the provision of connection point for the potential footbridge should allow flexibility in meeting the actual community needs in future.

4

Annex 2

District Development and Housing Committee, Southern District Council Progress Report on Planning Works in Southern District (As at 28.2.2019) I. Outline Zoning Plan

District Plan No. Project Description Remarks

– –– – –

5

II. Planning Application Application submitted for Town Planning Board’s Consideration (1.1.2019 to 28.2.2019)

District Application No. Applied Use Location Consideration/Result Remarks

Stanley Y/H19/1 To Rezone the Application Site Maryknoll House, 44 On 4.1.2019, the Metro Planning from “Government, Institution or Stanley Village Road Committee (MPC) of the Town Community” to “Residential Planning Board (TPB) decided to (Group C)2” or “Other Specified partially agree to the application by Uses” annotated “Residential rezoning the application site to a Development with Historic specific “Other Specified Uses” zoning Building Preserved” to preserve the Grade 1 historic building, and MPC of the TPB also decided not to agree to the proposed rezoning of the application site to “Residential (Group C)” zone.

AP Lei A/H15/279 Ship-building, Ship-breaking and 29 On 18.1.2019, the MPC of TPB Chau Ship-repairing (excluding Praya Road decided to approve the application. building and / or repairing of steel ships or boats)

Ap Lei Y/H15/12 To Rezone the Application Site 111 Lee Nam Road On 1.2.2019, the MPC of TPB decided Chau from “Other Specified Uses” not to agree to the rezoning proposal. annotated “Business (3)” to “Residential (Group E)”

6

District Application No. Applied Use Location Consideration/Result Remarks

Shek O A/H18/84 Proposed ”Field The Swire Institute of On 22.2.2019, the MPC of TPB Study/Education/Visitor Center” Marine Science, decided to defer a decision on the (Extension of Academic Block) Faculty of Science, application pending the submission of for Site A and Proposed The University of further information from the applicant. “Residential Institution” Hong Kong, Cape (Extension of Residential Block) d’Aguilar Road for Site F and ancillary Utility Installation for Private Project and Excavation of Land

7

III. Hotel Developments in Wong Chuk Hang Business Area Approved by Town Planning Board with Planning Permission Still Valid

Location Remarks

Planning permission (No. A/H15/265) for conversion of existing industrial building into hotel valid until Nov 2019. The previous lease modification application for non-industrial use (including hotel) was withdrawn by the applicant in Nov 2012. The existing lease is for industrial use and hotel is not permitted. Application for special waiver for conversion of the existing building for hotel use was 1. 41-43 Wong Chuk Hang Road submitted by the applicant in Oct 2015. Subsequently, the applicant in Oct 2016 revised the proposed user from “hotel” to “office”. Applicant in Jul 2017 further revised the proposal to “26-storey hotel” and submitted other background information including the related planning permission obtained to LandsD in Aug 2017 and Oct 2017. Such revised application is being processed. Such application had been approved by LandsD and the concerned basic terms were accepted by the Applicant in Nov 2018.

Planning permission (No. A/H15/264) for hotel development valid until Mar 2020. 2. 43 Heung Yip Road According to the Modification Letter governing the subject lot, redevelopment for hotel use is permitted under lease.

8

Annex 3

District Development and Housing Committee, Southern District Council Progress Report on Road Works in Southern District (As at 28.2.2019)

I. Preliminary Project Plan of Construction Works

Project Est. (Actual) Start Est. (Actual) PWP No. / Cat. Type Agency Progress / Remarks Description Date Completion Date

– – – – – – –

9

Annex 4

District Development and Housing Committee, Southern District Council Progress Report on Other Works in Southern District (As at 28.2.2019)

I. Works Commenced

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Start Date Completion Date 191WC/A Replacement and WSD Contract No.12/WSD/10, which consists of construction (7.2011) 6.2019 Rehabilitation of works in Southern District, commenced on 18.7.2011. Water Mains Stage 4 Works are being carried out. The progress of works was Phase 1 affected by traffic, congested underground utilities, conflict with other utility undertakers or other circumstances stated below. Works in Southern District are as below: (a) Bisney Road Footpath and Carriageway (Completed) (1.2012) (10.2018) [100%] [Remark: The road reinstatement works is targeted to be completed in March 2019.]; (b) Wah King Street Footpath and Carriageway (In (1.2014) 6.2019 progress) [97%] [Reason: One of the Temporary Traffic Arrangement for connection work would be implemented outside Fire Station and the vehicular access for private cars would be affected. Extra time was required for coordination with Pok Fu Lam Fire Station and application for associated traffic advice / gazette.];

10

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Start Date Completion Date (c) Road Carriageway (near Belleview (1.2016) 3.2019 Drive) (Completed) [100%] [Remark: The road instatement works is targeted to be completed in March 2019.]; (d) Aberdeen Praya Road Carriageway (nearby sitting out (10.2015) 6.2019 area at Ap Lei Chau Bridge and nearby Wu Nam Street Public Toilet) (In progress) [55%] [Reason: As the works is located in a traffic sensitive route, carrying out the works during daytime is not allowed. Extra time is required to coordinate with Traffic Management Liaison Group (TMLG) members for carrying the works in daytime. The excavation permit (XP) was expired during this coordination period. Extra time for application of new XP was required.]; (e) Kai Lung Wan Fresh Water Service Reservoir (In (1.2014) 4.2019 progress) [97%] [Reason: As Kai Lung Wan Fresh Water Service Reservoir involves a large water supply zone including Wah Fu Estate, schools, Pok Fu Lam Fire Station, commercial centers, etc., additional time was required to liaise with local residents and DC members. Moreover, in order to reduce the frequency of planned water suspension, it is planned to carry out the connection work jointly with the connection work at Wah King Street (item c above) in Apr 2019.] ;

11

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Start Date Completion Date (f) Aberdeen Main Road (near Fung Tin Street) and (1.2017) 3.2019 Aberdeen Praya Road (near Bayshore Apartments) (In progress) [85%] (i) Aberdeen Main Road near Fung Tin Street (1.2019) (Completed) [100%] (ii) Aberdeen Praya Road (In progress) [75%] 3.2019 [Remark: Tunneling works (Completed) [100%], Mainlaying (In progress) [65%]]

12

Est. (Actual) Est. (Actual) PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Start Date Completion Date

(3.2013) 6.2019 Contract No.3/WSD/12, which consists of construction

works in Southern District, commenced on 15.3.2013.

Works are being carried out. Works in Southern District

are as below:

(a) Tin Wan Street Footpath and Carriageway (near the (1.2016) (10.2018) junction of Shek Pai Wan Road and Tin Wan Street) (Completed) [100%]; (b) Wong Chuk Hang Road Footpath and Carriageway (7.2016) (10.2018) (near the junction of Tong Bin Lane and Yip Hing Street) (Completed) [100%]; and (c) Road (near Remex Centre, No.42 of (11.2017) 6.2019 Wong Chuk Hang Road) [32%] [Status: The excavation permit has expired. New excavation permit application was in progress. Therefore, the works completion date needed to be postponed to June 2019.].

13

Est. Est. PWP No. / Project (Actual) Agency Progress / Remarks [Completion rate (%)] (Actual) Cat. Description Completion Start Date Date 341DS/A Harbour Drainage The item comprises upgrading of the Stonecutters Island Sewage Treatment Works (8.2011) (3.2018) Area Services and eight numbers of preliminary treatment works at . The project Treatment Department has been fully commissioned in Dec 2015. Scheme, Contract DC/2009/24 (Harbour Area Treatment Scheme Stage 2A Upgrading of stage 2A - Preliminary Treatment Works (PTWs) at Sandy Bay, , Wah Fu, Aberdeen Upgrading and Ap Lei Chau), being part of the works of the above item, has commenced on of 31.8.2011. Since the full commission of the project in Dec 2015, the treated Stonecutters effluent from Sandy Bay, Cyberport, Wah Fu, Aberdeen and Ap Lei Chau sewage Island treatment works has been intercepted and conveyed to the newly expanded sewage Stonecutters Island Sewage Treatment Works for further treatment. The water treatment quality of the nearby waters is improved, as there is no more direct discharge of works and treated effluent into the areas. The works of DC/2009/24 mainly include the preliminary upgrading of the sewage treatment and de-odourisation facilities in these PTWs. treatment About 100% of works under the contract has been completed. The upgrading works works of PTWs are listed below: Sandy Bay PTW: Completed Cyberport PTW: Completed Wah Fu PTW: Completed Aberdeen PTW: Completed Ap Lai Chau PTW: Substantially completed

14

Progress Report on Landslip Prevention and Mitigation Works

PWP No. / Project Description Agency Progress / Remarks [Completion rate (%)] Est. Est. (Actual) Cat. (Actual) Completion Start Date Date Head 705 Landslip Prevention CEDD Landslip prevention and mitigation works for 129 man-made slopes and Subhead and Mitigation 11 natural hillside study areas in the Southern District are completed. 5001BX/D Programme The natural hillside study areas are 11SW-C/SA3, 15NW-B/SA1, (LPMitP) 11SW-C/SA4, 11SW-D/SA12, 15NW-B/SA2, 15NW-B/SA5, 15NW-B/SA6, 11SW-A/SA5, 11SW-C/SA1, 11SW-C/SA2 and 15NE-A/SA3. Landslip prevention and mitigation works for 13 man-made slopes and 6 natural hillside study areas are currently in progress.

(1) Slope No. 15NW-B/C385 at Island Road [95%] (1.2018) 3.2019* (2) Slope No. 15NE-A/CR454 at Tai Tam Road Catchwater [95%] (1.2018) 3.2019* (3) Slope No. 15NE-A/C70 at Repulse Bay Road [65%] (3.2018) 9.2019 (4) Slope No. 15NE-A/C192 at Tai Tam Road [100%](Completed) (3.2018) (1.2019) (5) Slope No. 15NE-A/C193 at Tai Tam Road [75%] (3.2018) 6.2019 (6) Slope No. 11SW-C/F411 at Peel Rise [50%] (9.2018) 8.2019 (7) Slope No. 11SW-D/C1054 at Wong Chuk Hang Road (9.2018) (2.2019) [100%](Completed) (8) Slope No. 15NE-A/C118 near the junction of Repulse Bay Road (9.2018) 5.2019 and Headland Road [65%] (9) Slope No. 15NE-A/C240 near the junction of Stanley Gap Road (10.2018) 6.2019 and Headland Road [50%] (10) Slope No. 15NE-A/CR389 at South Bay Road [50%] (9.2018) 7.2019

15

PWP No. / Project Description Agency Progress / Remarks [Completion rate (%)] Est. Est. (Actual) Cat. (Actual) Completion Start Date Date (11) Slope No. 15NE-A/F229 at Ma Hang Prison [60%] (10.2018) 4.2019* (12) Slope No. 15NE-A/C90 at South Bay Road [50%] (10.2018) 6.2019 (13) Slope No. 15NE-A/F45 at Tai Tam Road [45%] (10.2018) 8.2019 (14) Slope No. 15NE-A/C241 at West of Eden View, Stanley Gap Road (12.2018) 12.2019 [20%] (15) Slope No. 15NW-B/C151 at above Lee Wing Street, Ap Lei Chau (12.2018) 3.2020 [10%] (16) 1 Natural hillside study area at Shek Pai Wan Road, Aberdeen (11.2014) 3.2019* (Study Area Number 11SW-C/SA5) [98%] (17) 1 Natural hillside study area Behind Police College at Wong Chuk (4.2016) 4.2019* Hang (Study Area Number 15NW-B/SA3) [96%] (18) 1 Natural hillside study area at Repulse Bay Road (Study Area (2.2018) 4.2020 Number 15NE-A/SA6) [45%] (19) 1 Natural hillside study area Behind Repulse Bay Apartments at (1.2018) 2.2020* Repulse Bay Road (Study Area Number 15NE-A/SA4) [45%] (20) 1 Natural hillside study area Behind Island Road (10.2018) 5.2020 (Study Area Number 15NW-B/SA4) [20%] (21) 1 Natural hillside study area Behind Lee Wing Street, Ap Lei Chau (10.2018) 6.2020 (Study Area Number 15NW-B/SA7) [20%]

* Anticipated completion dates are revised due to modification of works programme.

16

PWP No. / Project Description Agency Progress / Remarks [Completion rate (%)] Est. Est. (Actual) Cat. (Actual) Completion Start Date Date Head 705 Landslip Prevention CEDD In the coming year, CEDD is planning to progressively commence the Subhead and Mitigation landslip prevention and mitigation works for other 19 man-made slopes. 5001BX/D Programme (LPMitP)

(1) Slope No. 11SE-C/C237 at Repulse Bay Road 3.2019* 7.2019* (2) Slope No. 11SW-D/CR78 at Aberdeen Main Road 3.2019 9.2019 (3) Slope No. 15NW-B/C97 at Island Road 3.2019* 9.2019 (4) Slope No. 15NE-A/C195 at Tai Tam Road 4.2019* 4.2020* (5) Slope No. 15NE-A/C313 at Stanley Gap Road 3.2019* 11.2019* (6) Slope No. 11SW-D/C1846 at Deep Water Bay Road 3.2019* 11.2019* (7) Slope No. 15NE-A/C197 at Tai Tam Road 1.2020* 12.2020* (8) Slope No. 15NE-A/C13 at Repulse Bay Road 5.2019* 12.2019 (9) Slope No. 15NE-B/C235 at Shek O Road 3.2019* 12.2019* (10) Slope No. 11SW-D/R10 at Wong Chuk Hang Road 6.2019* 11.2019* (11) Slope No. 15NE-A/C176 at Tai Tam Road 9.2019 9.2020 (12) Slope No. 11SE-D/CR698 at Tai Long Wan Village 3.2019* 8.2019 (13) Slope No. 15NE-A/FR34 at Repulse Bay Road 9.2019 3.2020 (14) Slope No. 11SW-C/R342 at Pok Fu Lam Village 4.2019 1.2020 (15) Slope No. 11SW-D/FR651 at 7.2019 4.2020 (16) Slope No. 15NW-B/C435 at Island Road 4.2019* 1.2021* (17) Slope No. 15NE-A/C608 at Tai Tam Road 11.2019 9.2020 (18) Slope No. 11SE-C/C534 at Tai Tam Road 9.2019 2.2021 (19) Slope No. 11SW-C/CR187 at Sandy Bay Road 12.2019 3.2020

* Anticipated completion dates are revised due to modification of works programme.

17

PWP No. / Project Description Agency Progress / Remarks Cat. Head 705 Landslip Prevention CEDD CEDD is carrying out stability investigation for other 8 man-made slopes Subhead and Mitigation in the Southern District, which are in the early stage of the LPMit 5001BX/D Programme (LPMitP) Programme. The stability investigations of these slopes are not yet completed. Therefore, upgrading works to these slopes may not be required if it is later confirmed that the slopes meet the required safety standards.

(1) Slope No. 11SW-C/F398 at Pok Fu Lam Village (2) Slope No. 11SW-C/C1015 at Mount Davis Road (3) Slope No. 15NE-A/CR45 at Repulse Bay Road (4) Slope No. 15NE-A/CR62 at Belleview Drive (5) Slope No. 15NE-A/F116 at Tai Tam Road Catchwater (6) Slope No. 15NW-B/C54 at Island Road (7) Slope No. 11SW-D/C1058 at Hong Kong Police College (8) Slope No. 11SW-D/C1059 at Hong Kong Police College

18

Annex 5

District Development and Housing Committee, Southern District Council Progress Report on Public Housing Works in Southern District (As at 28.2.2019)

I. Planned Works / Works Commenced (up to the end of two financial years later)

Project Description Est. (Actual) PWP / Estate Responsible Team Est. (Actual) Start Date Remarks Completion Date Proposed Public Project Sub-division With the timely completion of With the timely completion of The Government has completed the procedures Housing 3, Development and all procedures (including all procedures (including of OZP amendments for rezoning the five sites Developments at Construction public consultation and public consultation, funding in Pokfulam South. On 21.8.2018, the Chief Pok Fu Lam South Division funding approval by the approval by the Legislative Executive in Council approved the Pok Fu and Wah Fu Estate Legislative Council, etc.), Council, execution of relevant Lam OZP. The department is preparing Redevelopment CEDD anticipated to works, etc.), the first phase of planning brief and carrying out preparation commence the concerned site reception units are expected to works for the geotechnical investigation and formation works and road complete in 2025 and a architectural design for the proposed public works in the first quarter of population intake is to launch housing developments. Upon completion of 2020. in 2026 the earliest. the planning brief and architectural design, the flat production, development programme and public housing type at the relevant sites will then be determined. Afterwards, the department will start studying the redevelopment proposal of Wah Fu Estate and consult relevant stakeholders.

19

Annex 6

District Development and Housing Committee, Southern District Council Progress Report on FEHD District Minor Works in Southern District (As at 28.2.2019)

I. Preliminary Project Plan of Construction Works

Date of First Discussion Latest Progress on Matters (Date of updates) On Wong Chuk Hang San Wai Village (31.10.2018)

FEHD advised that Railway Development Section of LandsD had requested MTRC to replant trees at the proposed location of Wong Chuk Hang San Wai Village Public Toilet according to the approved Tree Removal Application in 2011. FEHD has accordingly requested LandsD to waive to replant trees at the subject location so as to prevent affecting the construction works of the public toilet. Railway Development Section of LandsD replied that MTRC is not required to plant the compensatory trees on the proposed San Wai Village Public Toilet site. After communication with LandsD, FEHD obtained the reply from LandsD regarding the approval of the application of land allocation on 20.10.2016. FEHD informed ArchSD about LandsD’s approval of the application of land allocation so as to facilitate ArchSD’s consideration to grant the funding application for construction of the Wong Chuk Hang San Wai Village Public Toilet. Having approval by Minor Building Works Committee on mid-year of 2017 the funding for the project of Wong Chuk Hang San Wai Village Public Toilet, ArchSD proceeded the relevant design and planning work of the project. ArchSD has handed over the construction site to her contractor since 30.7.2018 for arrangement of construction works and anticipated that the construction of San Wai Village Public Toilet in Wong Chuk Hang completed around 3rd quarter of 2019. FEHD will report the progress in the committee when ArchSD provides the updated situation.

LandsD advised that the land allocation application made by FEHD for construction of a new public toilet at Wong Chuk Hang San Wai Village was approved on 20.10.2016. The site was handed over to FEHD on 11.7.2018.

20

II. Commenced Works

Estimated Item Proposed Start Date Estimated Completion Date FEHD Contact ASD Contact Location Remarks No. Minor Works [Actual [Actual Completion Date] Person Person Start Date] Pending for completion analysis Senior Health Refurbishment of the portable water Inspector Property Services 1. of Repulse Bay Repulse Bay from relevant (Cleansing/Pest Manager/ PM14, Public Toilet Beach Road near department. The Control) Southern, [Apr 2017] Mar 2019 Mr. WONG (near Life Life Saving FEHD anticipates Mr. LAU Wing-lim, William Saving Association re-opening of this Wai-cheung 【2773 2426】 Association) refurbished public 【2903 0402】 toilet for public use in late-March. Senior Health Inspector Property Services Pokfulam Road Pokfulam Road Re-opened for public (Cleansing/Pest Manager/ PM13N, near Queen Jan 2019 2. near Queen [Mar 2017] use since 1 Feb Control) Southern, Ms. LI Mo-kwan, Mary Hospital [31 Jan 2019] Mary Hospital 2019. Mr. LAU Agnes Public Toilet Wai-cheung 【2773 2667】 【2903 0402】 Senior Health San Wai Inspector Project Manager/ Village, Wong San Wai (Cleansing/Pest PM344, Chuk Hang near 3. Village Public [Sep 2018] 3rd quarter of 2019 Works in progress Control) Southern, Miss KAN Wong Chuk Toilet Mr. LAU Ching-ching Hang Road Wai-cheung 【2867 3726】 Garden 【2903 0402】

21

Annex 7

District Development and Housing Committee, Southern District Council Progress Report on Lands Department Temporary Government Lands Allocation in Southern District (As at 28.2.2019)

Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

1. GLA-THK 1753 Renewal Government 126 Car Extend up to Hong Kong - - Regarding the 504/SHGS/82 land between parking 11.2.2020 Police objection from No. 24 and 25 spaces Force DDHC, Hong Kong Shum Wan Police Force Road, Wong responded that the Chuk Hang proposed parking was for its operational needs. TD had no comment and Security Bureau had given approval to the proposed extension. Case in progress.

22

Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

2. GLA-THK1892 Renewal Tin Wan Praya 820 Works Area Extend up to DSD - - DSD had been L/M Road, Aberdeen 30.6.2019 requested to provide 988/SHMS/82 A supplementary information before processing the application for renewal. DSD had provided supplementary information. DSD had further applied for extension period up to 30.6.2019. DSD request is being processed.

23

Type of TGLA Remarks Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of (Current No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn Situation)

3. GLA-THK950 Renewal At Stanley 127 Manoeuvring Extend up WSD - - Departmental 177/HGS/62 Gap Road and/or Parking to circulation of Waterworks 31.5.2020 completed. Vehicles to/from Pending approval. Stanley Mound Fresh Water Pumping Station & Extension

24

Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

4. GLA-THK Renewal Cyberport 6 855 Sewage Extended up DSD - - Objections received have 1785 Road, Pok Treatment to been forwarded to DSD for 394/SHGS/8 Fu Lam Plant 31.12.2020 their follow-up action. 2 DSD advised that objection had been resolved.

An application for time extension for proposed GLA-THK 1785 up to 31.12.2020 is under processing.

Meanwhile, DSD has applied for PGLA for the same use at the same site.

The PGLA application is under processing. In the event that the PGLA is granted before the expiry of GLA-THK 1785, the application for time extension of GLA-THK 1785 will not be further processed. 25

Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

5. GLA-THK Renewal Sandy Bay, 3 460 Works Area Extended CEDD - - CEDD further applied to 2003 Pok Fu Lam up to extend the allocation up to 3/SHGS/201 20.4.2021 20.4.2021. 5 Departmental circulation and local consultation have been completed. Objection have been resolved. Pending approval.

6. GLA-THK New Sandy Bay, 8 485 Works Area From to be ArchSD - - To facilitate the proposed 2022 Pok Fu Lam (To be (Redevelopm confirmed trail works at Sandy Bay, the 4/SHGS/201 confirmed) ent of Queen to proposed site boundary is 7 Mary 31.12.2025 further revised. Liaising Hospital with Southern District Office and ArchSD.

26

Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

7. Proposed Re-tender No. 3 Ap 889 Ship or boat A fixed To be let by - - In accordance with STT No. of STT Lei Chau building or term of five open tender Transport and Housing SHX 1379 site Praya Road ship or boat years Bureau’s policy directives repairing or certain and and support, LandsD had both with option arranged re-tendering of the (excluding to extend up subject site. The tender building and/ to seven was closed on 28.12.2018. or repairing years in The tender was awarded on of steel ships total. 22.1.2019. or boats) 8. Proposed Re-tender No. 29 Ap 1,981 Ship or boat A fixed To be let by - - In accordance with STT No. of STT Lei Chau building or term of five open tender Transport and Housing SHX 1380 site Praya Road ship or boat years Bureau’s policy directives repairing or certain and and support, LandsD had both with option arranged re-tendering of the (excluding to extend up subject site. The tender building and/ to seven was closed on 28.12.2018. or repairing years in The tender was awarded on of steel ships total. 22.1.2019. or boats)

27

Type of TGLA Item TGLA No./ (New/ Proposed Proposed Proposed User Dept. Date of Date of Remarks No. File Ref. Renewal) Location Area (m2) User Term (Allocatee) Allocation Withdrawn (Current Situation)

9. GLA-THK Renewal No. 800 4,140 Government Extended Government - - Departmental circulation 1748 Victoria Laboratory up to Laboratory and local consultation have 5/HGS/63 III Road for Food 17.1.2022 been completed. Objection Testing Uses has been resolved. Pending approval.

28

Annex 8 District Development and Housing Committee, Southern District Council Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites (As at 28.2.2019)

Location Anticipated Approximate Managing Planned Use/Follow-up Actions Date of First Handover Area Size Agent (Provided by Managing Department/Agent) Discussion Date (m2) (Date of updates) Site next to Handed over in the end of June 6 230 LandsD Long-term planned use of the land is to be advised 26.1.2015 Ocean Park 2016 by PlanD. LandsD would facilitate any application for use of the land in accordance with (15.7.2016) applicable procedures.

(PlanD’s comments: The subject site falls within an area zoned “Government, Institution or Community” (“G/IC”) on the Aberdeen & Ap Lei Chau OZP and is reserved for provision of G/IC facilities.)

29

Location Anticipated Approximate Managing Planned Use/Follow-up Actions Date of First Handover Area Size Agent (Provided by Managing Department/Agent) Discussion Date (m2) (Date of updates) Chung Hom The site is had been granted by 6 400 + LandsD Long-term planned use of the land is to be advised 26.1.2015 Shan LandsD to Ocean Park 2 500 by PlanD. LandsD would facilitate any application Corporation Limited under a for use of the land in accordance with applicable (1.9.2017) short term tenancy for the site procedures. for storage purpose in two phases on 1.8.2017 and (PlanD’s comments: The subject site falls within 31.1.2018 respectively for a an area zoned “Other Specified Uses” annotated term up to 31.7.2019. “Composite Signals Organization Station Complex” on the Stanley OZP intended primarily to provide land for composite signals organization station complex and its ancillary facilities.)

30