BEUP Schemes of 16TH Bidhansabha 2016 to 2019

For the Month of March-2020 Sl. No. Name of A.C. Sl. No. Name of A.C.

1 259- (SC)A.C 9 267- A.C

2 260- DAKSHIN A.C 10 268- DAKSHIN A.C

3 261-RAINA (SC) A.C 11 269-PURBASTHALI UTTAR A.C

4 262-JAMALPUR (SC)A.C 12 270- A.C

5 263- A.C 13 271- A.C

6 264-KALNA (SC) A.C 14 272- A.C

7 265- A.C 15 273-AUSGRAM (SC) A.C

8 266-BARDHAMAN UTTAR (SC) A.C 16 274-GALSI (SC) A.C

2 Shri Nabin Chandra Bag Hon’ble M.L.A. of 259- Khandaghosh (SC) AC

3 COMPLETED SCHEMES

4 NABIN CHANDRA BAG, HON'BLE MLA-259 KHANDAGHOSH (SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Open Stage at Mogalisima Hat 2016 - Executive Officer, Report 1 2769/DP 28/11/2016 450000 420161 420161 100 Yes Tala F.P. School 2017 Galsi- II P.S. Wanting

Constn of Samsan Shed at Punia under 2016 - Executive Officer, Report 2 180/DP 16/01/2017 300000 276676 276676 100 Yes Khandagosh 2017 Khandaghosh P.S. Wanting

Instn of Solar Light of 18 watt at 2016 - Executive Officer, Report 3 180/DP 16/01/2017 200000 184800 184800 100 Yes Khandagosh BPHC 2017 Khandaghosh P.S. Wanting

Constn of Shed at Nischintapur Kabarsthan 2016 - Executive Officer, Report 4 180/DP 16/01/2017 400000 400000 400000 100 Yes under Khandagosh 2017 Khandaghosh P.S. Wanting

Constn of Samsan Shed at Khandagosh 2016 - Executive Officer, Report 5 180/DP 16/01/2017 300000 289871 289871 100 Yes Tantipara 2017 Khandaghosh P.S. Wanting

Constn of Samsan Chulli at under 2016 - Executive Officer, Report 6 180/DP 16/01/2017 480000 471026 471026 100 Yes Khandagosh 2017 Khandaghosh P.S. Wanting

Constn of Swasan Shed and Chully at Gopal 2016 - Executive Officer, Report 7 234/DP 18/01/2017 650000 560889 560889 100 Yes Bera 2017 Khandaghosh P.S. Wanting

Constn of Concrete road of Khandagosh 2016 - Executive Officer, Report 8 283/DP 29/01/2017 150000 140000 140000 100 Yes Girls School 2017 Khandaghosh P.S. 5Wanting Sanction UC Sl. Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Order Submitt No. Sanction Sanction Agency Released Utilized Progress Over Status No ed Constn of Culvert at Sankhari on 2016 - Executive Officer, Report 9 approach road of Sankari Boys High 798/DP 15/03/2017 800000 800000 800000 100 Yes 2017 Khandaghosh P.S. Wanting School

Constn of Drain from Berugram road to 2016 - Executive Officer, Report 10 798/DP 15/03/2017 300000 300000 300000 100 Yes Khandagosh Tanti Para F.P. School 2017 Khandaghosh P.S. Wanting

Constn of Samsan Shed and Chully at 2016 - Executive Officer, Report 11 798/DO 15/03/2017 650000 613352 613352 100 Yes Saranga village of G.P. 2017 Khandaghosh P.S. Wanting

Constn of Samsan Shed at Paharpur of 2016 - Executive Officer, Report 12 798/DP 15/03/2017 320000 312589 312589 100 Yes Sagrai G.P. 2017 Khandaghosh P.S. Wanting

Constn of Atchala at Madhpur village of 2016 - Executive Officer, Report 13 798/DP 15/03/2017 500000 496785 496785 100 Yes sagrai G.P. 2017 Khandaghosh P.S. Wanting

Constn of Atchala at Ghosh Para of Bhuri 2016 - Executive Officer, Report 14 904/DP 22/03/2017 250000 190472 190472 100 Yes G.P. 2017 Galsi- II P.S. Wanting

Constn of Atchala at Jahanpur Paschim 2016 - Executive Officer, Report 15 904/DP 22/03/2017 250000 170407 170407 100 Yes Hattala of Bhuri G.P. 2017 Galsi- II P.S. Wanting

Total 6000000 5627028 5627028

6 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Exe. Engg. PWD Constn of Boitarani scheme at Sanko 2017 - Report 16 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes village Jl.154 Plot No 4636 of Sanko G.P. 2018 Wanting Burdwan. Exe. Engg. PWD Constn of Boitarani scheme at Sasanga 2017 - Report 17 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes village Jl.58 Plot No 1581 of Sasanga G.P. 2018 Wanting Burdwan. Constn. of Baitorani Scheme at Exe. Engg. PWD 2017 - Report 18 Hakordanga village Jl 104 Plot no. 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 Wanting 60,61,62 under Khandaghosh P.S. Burdwan. Constn. of Baitorani Scheme at Khano Exe. Engg. PWD 2017 - Report 19 village JL104 Plot No. 8428 of Khano 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 Wanting G.P. under Galsi-II P.S. Burdwan. Constn of Boitarani scheme Berugram Exe. Engg. PWD 2017 - Report 20 village Jl.26 Plot No 6341 of Berugram 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 Wanting G.P. Burdwan. Constn of Plastering work Decorative 2017 - E.O., Report 21 Cement base paint at Rashbihari Ghosh 149/DP 24/01/2018 600000 600000 600000 100 Yes 2018 Khandaghosh P.S. Wanting Mahavidlaya at Ukhrid Constn of Atchala at Khandagosh 2017 - E.O., Report 22 149/DP 24/01/2018 400000 400000 400000 100 Yes Metepara 2018 Khandaghosh P.S. Wanting Constn of Swamsan Shed at Ukhrid 2017 - E.O., Report 23 149/DP 24/01/2018 300000 300000 300000 100 Yes Moralpukur 2018 Khandaghosh P.S. Wanting

Constn of Swamsan Shed at Keudia 2017 - E.O., Report 24 149/DP 24/01/2018 300000 300000 300000 100 Yes LatifpurMouza Khedua 2018 Khandaghosh P.S. Wanting Total 6050000 5829925 5829925 7 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Atchala at Nabagram Mouza 2018 - E.O., Report 25 NabagramPlot No.578 Jl.No 7 under C-283/DP 08/02/2018 400000 400000 400000 100 Yes 2019 Khandaghosh P.S. Wanting Khandagosh Constn. of ghat at Amral dighi under 2018 - E.O., Report 26 690/DP 27/02/2019 200000 195940 195940 100 Yes Gopalbera G.P. within Khandaghosh P.S. 2019 Khandaghosh P.S. Wanting Constn. of gate at Khandaghosh Tantipara 2018 - E.O., Report 27 Primary school under Khandaghosh G.P. 690/DP 27/02/2019 50000 49305 49305 100 Yes 2019 Khandaghosh P.S. Wanting within Khandaghosh P.S. Constn. of drain from Akale Majhi house to Bapi Roys house at Khandaghosh tantipara 2018 - E.O., Report 28 690/DP 27/02/2019 300000 292650 292650 100 Yes under Khandaghosh G.P. within 2019 Khandaghosh P.S. Wanting Khandaghosh P.S. Constn. of atchala at Manasatala of Dewan 2018 - E.O., Report 29 Dighir Par under Sagrai GP. within 1272/DP 28/05/2019 400000 390560 390560 100 Yes 2019 Khandaghosh P.S. Wanting Khandaghosh P.S.

Constn. of Chagram Paschimpara under 2018 - E.O., Report 30 1272/DP 28/05/2019 400000 370579 370979 100 No Ukhrid GP. within Khandaghosh P.S. 2019 Khandaghosh P.S. Wanting Constn. of passenger shed at Bamunari more main canel (Bridge 150 chains) of 2018 - E.O., Report 31 690/DP 27/02/2019 350000 341635 337066 75 Yes Berugram road under Lodna G.P. 2019 Khandaghosh P.S. Wanting within Khandaghosh P.S. Constn. of passenger shed at Garsankari 2018 - E.O., Report 32 more of Badulia Berugram road under 690/DP 27/02/2019 350000 341845 331213 95 Yes 2019 Khandaghosh P.S. Wanting Ukhrid G.P. within Khandaghosh P.S. 8 UC Handed Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Over No. Order No Sanction Sanction Agency Released Utilized Progress ed Status Constn. of ghat at South side Mosdapukur of Berugram village Jl. No. 26 Plot No. 2018 - E.O., Report 33 690/DP 27/02/2019 300000 292830 213383 75 Yes 5409 under Berugramm G.P. within 2019 Khandaghosh P.S. Wanting Khandaghosh P.S. Constn. of Atchala at Amral Charak 2018 - E.O., Report 34 dangapar under Berugram GP. within 1272/DP 28/05/2019 400000 390120 382495 95 Yes 2019 Khandaghosh P.S. Wanting Khandaghosh P.S. Total 3150000 2963591 2963591

Grand Total 4355000 14420544 14420544

9 ONGOING SCHEMES

10 NABIN CHANDRA BAG, HON'BLE MLA-259 Khandaghosh (SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Executive Work not started Constn. of Atchala at Gaitanpur 2018 - Officer, 1 4022/DP 05/11/2019 400000 294450 0 0 No & will start very village within Khandaghosh PS 2019 Khandaghosh soon. P.S. Executive Constn. of Atchala at Muidhara village 2018 - Officer, 2 4021/DP 05/11/2019 400000 288330 0 0 No Work just started. Daspara within Khandaghosh PS 2019 Khandaghosh P.S. Executive Work in progress Constn. of Atchala at Durgapur near 2018 - Officer, 3 4020/DP 05/11/2019 400000 294210 0 0 No & completed upto Masjidtala within Khandaghosh P.S. 2019 Khandaghosh plinth level. P.S. Executive Work in progress Constn. of Atchalaq at Sankari Village 2018 - Officer, 4 458/DP 05/02/2020 507326 380494 0 0 No & completed upto Barawaritala within khandaghosh P.S. 2019 Khandaghosh plinth level. P.S. Total 1707326 1257484 0

11 Dr. Rabiranjan Chottopadhyay, Hon’ble M.L.A. of 260-Bardhaman Dakshin A.C.

12 COMPLETED SCHEMES

13 RABIRANJAN CHOTTOPADHYAY, HON'BLE MLA-260 Bardhaman Dakshin A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Concrete road with drain 2016 - CEO, Burdwan Report 1 Sadarghat Rabindrapally from T. Dutta 302/DO 27/01/2017 394404 377773 377773 100 Yes 2017 Dev. Authority Wanting house to Sk. Mirchands Addl WorkStage Submersible and 2016 - CEO, Burdwan Report 2 Electrification ladies Park named Bande 302/DP 27/01/2017 484387 474359 474359 100 Yes 2017 Dev. Authority Wanting Mataram

Constn of Concrete road with drain at 2016 - CEO, Burdwan Report 3 Sarada Sukanta pally from R.Chakraborty 302/DP 27/01/2017 365623 291283 291283 100 Yes 2017 Dev. Authority Wanting house to G. Mondal house to A. Mondal

Constn of Concrete road from Malirbag to 2016 - CEO, Burdwan Report 4 Bhubaneswar road including Guard Wall of 302/DP 27/01/2017 914931 914931 914931 100 Yes 2017 Dev. Authority Wanting the ponds Constn of Concrete Road at Keshab Ganj Chotti from Sneha Mess to Mrghamallar 2016 - CEO, Burdwan Report 5 302/DP 27/01/2017 534429 420771 420771 100 Yes fromAlam house to Rasida Bhavan via P K. 2017 Dev. Authority Wanting Das

Constn of Pucca Drain at Western side of 2016 - CEO, Burdwan Report 6 302/DP 27/01/2017 306226 244760 244760 100 Yes Krishnapur Road Ward No.1 2017 Dev. Authority Wanting

Rep work at Burdwan Vivekananda Balika 2016 - CEO, Burdwan Report 7 968/DP 28/03/2017 195783 179347 179347 100 Yes Vidyalaya Arabindapally ward No. 8 2017 Dev. Authority 14Wanting UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Concrete road including guard 2016 - CEO, Burdwan Report 8 wall from P.Das house to Jail boundary 968/DP 28/03/2017 268971 194406 194406 100 Yes 2017 Dev. Authority Wanting ward no. 3

Constn of Concrete Road from A.Bhandari 2016 - CEO, Burdwan Report 9 house to Bidhannagar Athletic Club Gate 968/DP 28/03/2017 773440 773440 773440 100 Yes 2017 Dev. Authority Wanting No. 11

Constn of C. Rd. R. Rajjak house to C. 2016 - CEO, Burdwan Report 10 Mondal house and Rajbati Joswara house to 968/DP 28/03/2017 232903 190861 190861 100 Yes 2017 Dev. Authority Wanting S. Joswara house Wd No. 7

Supp. High Must Light at Tarun Sangha 2016 - CEO, Burdwan Report 11 Play Ground beside Borehat Kamalakanta 998/DP 30/03/2017 381604 370156 370156 100 Yes 2017 Dev. Authority Wanting Kalibari ward No. 28 Med.Suptd.-cum- Supply of One Transportation Van Carrying 2016 - Vice Princ, Report 12 Patient at Burdwan Medical College and 2208/DP 04/08/2017 129916 129916 129916 100 Yes 2017 Burdwan Med. Wanting Hospital College Ho

Dev. of Kabar Sthan at Kamal Sayer ward 2016 - CEO, Burdwan Report 13 2862/DP 09/11/2017 662119 662119 662119 100 Yes No. 26 2017 Dev. Authority Wanting

Total 5644736 5224122 5224122 15 UC Handed Sl. Sanction Date of Amount Amount Amount Physical Name of the Scheme Year Executing Agency Submitt Over No. Order No Sanction Sanction Released Utilized Progress ed Status

Constn of Boundary Wall Chain-link at the 2017 - CEO, Burdwan Report 14 side of Play Ground at Bharati Bhavan Boys 3048/DP 21/11/2017 200000 200000 200000 100 Yes 2018 Dev. Authority Wanting High School Parbirhata Burdwan

Constn of Boundary Wall at Rathtala 2017 - CEO, Burdwan Report 15 Adarsha Prathamic Vidyalaya Padma Pukur 3048/DP 21/11/2017 300000 287578 287578 100 Yes 2018 Dev. Authority Wanting Kanchannagar Constn of Class Room at Municipal Boys 2017 - CEO, Burdwan Report 16 School High School G.T. Road Burdwan 3048/DP 21/11/2017 1400000 1163365 1163365 100 Yes 2018 Dev. Authority Wanting Ward No. 34 Repair and Renovation of Exisisting School Building Burdwan Sri Sri Ramkrishna 2017 - CEO, Burdwan Report 17 3048/DP 21/11/2017 600000 598414 598414 100 Yes Saradapith Urban Junior Basic School, 2018 Dev. Authority Wanting Borehat Burdwan Wr No. 28

Repair and colouring works at Burdwan 2017 - CEO, Burdwan Report 18 Vivekananda Balika Vidyalaya 62/DP 09/01/2018 150000 141007 141007 100 Yes 2018 Dev. Authority Wanting Arabindapally Burdwan

Constn of Boundary Wall at Rathtala GSFP 2017 - CEO, Burdwan Report 19 62/DP 09/01/2018 300000 264752 264752 100 Yes Vidyalaya Rathtala Kanchan Nagar 2018 Dev. Authority Wanting

Constn of Concrete floor and drain 2017 - CEO, Burdwan Report 20 62/DP 09/01/2018 400000 397684 397684 100 Yes Batdhaman Banipith Girls high School 2018 Dev. Authority Wanting Constn of Class Room Bharati Balika 2017 - CEO, Burdwan Report 21 277/DP 08/02/2018 534000 534000 534000 100 Yes Bidyalaya at Borehat 2018 Dev. Authority Wanting 16 UC Handed Sl. Sanction Date of Amount Amount Amount Physical Name of the Scheme Year Executing Agency Submitt Over No. Order No Sanction Sanction Released Utilized Progress ed Status

Rep. and renovation of exsisting School 2017 - CEO, Burdwan Report 22 building Burdwan Shiv Kumar Harijan 277/DP 08/02/2018 500000 486954 486954 100 Yes 2018 Dev. Authority Wanting Bidyalaya

Rep and Renov of exsisting School 2017 - CEO, Burdwan Report 23 277/DP 08/02/2018 300000 300000 300000 100 Yes Building Burdwan Banipith High School 2018 Dev. Authority Wanting

Painting Work and other Ancilleary Works 2017 - CEO, Burdwan Report 24 Utsab Maidan at Parbirhata Burdwan Ward 993/DP 24/05/2018 109539 109539 109539 100 Yes 2018 Dev. Authority Wanting No. 35

Constn. of concrete road at Kamalsayer 2017 - CEO, Burdwan Report 25 Kabarsthan ward no.26 under Burdwan 2318/DP 30/08/2019 465817 456966 342725 75 No 2018 Dev. Authority Wanting Municipality

Constn. of concrete road with Guardwall at 2017 - CEO, Burdwan Report 26 Northside Samanta Pukur ward no. 9 under 2318/DP 30/08/2019 337744 331157 248368 75 No 2018 Dev. Authority Wanting Burdwan Municipality

Total 5597100 5271416 5271416

17 UC Handed Sl. Sanction Date of Amount Amount Amount Physical Name of the Scheme Year Executing Agency Submitt Over No. Order No Sanction Sanction Released Utilized Progress ed Status

Mural, artificial grass, cladding stone tiles and other decorative works at the multilevel 2018 - CEO, Burdwan Report 27 2283/DP 10/10/2018 2715790 2696881 2696881 100 Yes parking space and electrical works at 2019 Dev. Authority Wanting Mandela Park Mural, artificial grass cladding stone tiles 2018 - CEO, Burdwan Report 28 at Mendela park near Curzan gate 2nd 1336/DP 04/06/2019 1696664 1696664 1696664 100 Yes 2019 Dev. Authority Wanting phase

Beautification of Kamalsayer Kabarsthan, 2018 - CEO, Burdwan Report 29 Burdwan at ward no. 26 under Burdwan 1336/DP 04/06/2019 388275 194640 194640 100 Yes 2019 Dev. Authority Wanting Muty.

Writing and fixing of radium boards at the 2018 - CEO, Burdwan Report 30 poles of high mast light under Burdwan 3203/DP 14/12/2018 179798 134849 134849 100 Yes 2019 Dev. Authority Wanting Muty.

Fitting and Fixing of radium boards at the 2018 - CEO, Burdwan Report 31 3203/DP 14/12/2018 104412 104412 78309 100 No sites of new schemes under Burdwan Muty. 2019 Dev. Authority Wanting

Total 5084939 8427446 8427446

Grand Total 16326775 15322984 15322984

18 ONGOING SCHEMES

19 RABIRANJAN CHOTTOPADHYAY, HON'BLE MLA-260 Bardhaman Dakshin A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Dev. of Kabar sthan at South Side of 2016 - CEO, Burdwan Cancelled. Fund 1 2862/DP 09/11/2017 662119 662119 0 0 No Meen Bhavan at Indrapastha ward-27 2017 Dev. Authority not refunded.

Construction of concrete road with Guardwall at Northside Samanta 2017 - CEO, Burdwan Work order to be 2 4267/DP 27/11/2019 337744 331257 0 0 No Pukur, Ward No. 9 under Burdwan 2018 Dev. Authority submitted. Municipality. Construction of concrete road at 2017 - CEO, Burdwan Work order to be 3 Kamalsayer Kabarsthan Ward No. 4267/DP 27/11/2019 456966 456966 0 0 No 2018 Dev. Authority submitted. 26 under Burdwan Municipality. Total 1456829 1450342 0 0 Writing and fixing of radium 2018 - CEO, Burdwan 4 boards at the poles of high mast 3203/DP 14/12/2018 179798 179798 134849 75 No 2019 Dev. Authority light under Burdwan Muty. Total 179798 179798 134849

20 Shri Nepal Ghorui, Hon’ble M.L.A. of 261-Raina (SC) AC

21 COMPLETED SCHEMES

22 NEPAL GHORUI, HON'BLE MLA-261 RAINA(SC) A.C.

Physical UC Sl. Sanction Date of Amount Executing Amount Amount Handed Name of the Scheme Year Progres Submitt No. Order No Sanction Sanction Agency Released Utilized Over Status s ed

Report Constn of Concrete road from Kalupukur Par 2016 - Executive Officer, 1 2138/DP 15/09/2016 150000 150000 150000 100 Yes Wanting to Pirtala at Ausara of Sehara G.P. 2017 Raina- I P.S.

Constn of Concrete road from Hansir Kaltala 2016 - Executive Officer, Report 2 2138/DP 15/09/2016 350000 350000 350000 100 Yes Ahar to S.C. Mallik premises at Ausara 2017 Raina- I P.S. Wanting

Constn of Drain and cover by slab from the 2016 - Executive Officer, Report 3 premises of T.K.Nandi to the premises of 2138/DP 15/09/2016 150000 150000 150000 100 Yes 2017 Raina- I P.S. Wanting T.Puille at Alalpur

Constn of Drain and cover Slab from premises 2016 - Executive Officer, Report 4 2138/DP 15/09/2016 150000 150000 150000 100 Yes of D.Pullay to the pond of S. Malik at Alalpur 2017 Raina- I P.S. Wanting

District Purchase an Ambulance for Arui G.P. under 2016 - Report 5 2430/DP 21/10/2016 524879 Magistrate, 524879 524879 100 Yes Raina II P.S. 2017 Wanting Burdwan

District 2016 - Report 6 Purchase an Ambulance for G.P. 2509/DP 27/10/2016 524879 Magistrate, 524879 524879 100 Yes 2017 Wanting Burdwan 23 UC Handed Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Over No. Order No Sanction Sanction Agency Released Utilized Progress ed Status

Executive Constn of Community Room at Belsor 2016 - Report 7 2549/DP 03/11/2016 300000 Officer, Raina- I 300000 300000 100 Yes Purbapara of Hizalna G.P. 2017 Wanting P.S.

Executive Constn of Community Room at Belsor Shibtala 2016 - Report 8 2549/DP 03/11/2016 300000 Officer, Raina- I 300000 300000 100 Yes Para of Hizalna G.P 2017 Wanting P.S.

Executive Constn of Burning Ghat Chully and Waiting 2016 - Report 9 120/DP 08/01/2017 500000 Officer, Raina- I 500000 500000 100 Yes room at Shipta of Narugram 2017 Wanting P.S.

Executive Constn of Burning Ghat Chully and waiting 2016 - Report 10 799/DP 15/03/2017 500000 Officer, Raina- I 500000 500000 100 Yes Room at Bamunia of Hizala 2017 Wanting P.S.

Executive Constn of Burning Ghat Chully and Waiting 2016 - Report 11 799/DP 15/03/2017 500000 Officer, Raina- I 500000 500000 100 Yes Room at Palasan Paschim Para 2017 Wanting P.S.

Executive Constn of Boundary Wall of Uchha 2016 - Report 12 903/DP 22/03/2017 400000 Officer, Raina- II 400000 400000 100 Yes Vidyalaya of Uchalan G.P. 2017 Wanting P.S. 24 UC Handed Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitte Over No. Order No Sanction Sanction Agency Released Utilized Progress d Status

Executive Constn of waiting room at Hospital 2016 - Report 13 903/DP 22/03/2017 300000 Officer, Raina- 293677 293677 100 Yes more to Gotan G.P. 2017 Wanting II P.S. Executive Constn of Burning Ghat and waiting room at 2016 - Report 14 1086/DP 06/04/2017 500000 Officer, Raina- 488018 488018 100 Yes Kamardihi of Gotan G.P. 2017 Wanting II P.S. Constn. of burning ghat with chully and Executive 2016 - Report 15 waiting room at Shyamdasbati, Mouza C- 1312/DP 02/05/2017 500000 Officer, Raina- 500000 500000 100 Yes 2017 Wanting Shyamdasbati, Plot No. 200, JL No. 28 I P.S. Executive Constn of Boundary Wall of Ghustia 2016 - Report 16 406/DP 26/02/2018 350000 Officer, Raina- 349999 349999 100 Yes Nandanpur High School HS Uchalan G.P. 2017 Wanting II P.S. Total 5999758 5981452 5981452 Exe. Engg. Constn of Boitarani scheme at Bandgacha of 2017 - PWD (Social Report 17 1461/DP 17/05/2017 890000 843731 843731 100 Yes Hijalna G.P Plot No. 18 Jl No. 5. 2018 Sector), Wanting Burdwan. Exe. Engg. Constn of Boitarani scheme at Barabainan 2017 - PWD (Social Report 18 1461/DP 17/05/2017 890000 843730 843730 100 Yes Plot No. 5314, Kh.No. 1752 2018 Sector), Wanting Burdwan. Exe. Engg. Constn of Boitarani scheme at Bujrukdighi 2017 - PWD (Social Report 19 1461/DP 17/05/2017 890000 843730 843730 100 Yes Plot No. 394,JL No. 62 2018 Sector), 25Wanting Burdwan. UC Handed Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitte Over No. Order No Sanction Sanction Agency Released Utilized Progress d Status

Exe. Engg. Constn of Boitarani scheme at Chatadighi 2017 - PWD (Social Report 20 1461/DP 17/05/2017 890000 843730 843730 100 Yes Plot No. 4,JL No. 176 2018 Sector), Wanting Burdwan. Exe. Engg. Constn of Boitarani scheme at Dakshin 2017 - PWD (Social Report 21 1461/DP 17/05/2017 890000 843730 843730 100 Yes Gopalpur Plot No.1142,JL No. 177 2018 Sector), Wanting Burdwan. Executive Constn of Burning Ghat and Waiting Room 2017 - Report 22 970/DP 22/05/2018 500000 Officer, Raina- 499500 499500 100 Yes Belar Malik Para at Paitna G.P. 2018 Wanting II P.S. Executive Constn of New Drain Eklakhi bazar at 2017 - Report 23 970/DP 22/05/2018 300000 Officer, Raina- 300000 300000 100 Yes Uchalan G.P. 2018 Wanting II P.S. Executive Constn of Burning Ghat Haripur at Natu G.P. 2017 - Report 24 1113/DP 18/06/2018 250000 Officer, Raina- 240957 240957 100 Yes under Raina I P.S. 2018 Wanting I P.S. Executive Constn of Burning Ghat and waiting Room 2017 - Report 25 1310/DP 16/07/2018 500000 Officer, Raina- 499500 499500 100 Yes bantir Dhara Para at Hijalna G.P. 2018 Wanting I P.S. Total 6000000 5758608 5758608

26 UC Handed Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitte Over No. Order No Sanction Sanction Agency Released Utilized Progress d Status

Constn. of Mukta Mancha at Raina Executive 2018 - Report 26 Domepara village (Mouza-Rainagar, plot no 1376/DP 10/06/2019 400000 Officer, Raina- 400000 400000 100 Yes 2019 Wanting 1480) under Raina G.P. within Raina-I P.S. I P.S.

Constn. of gate at College Executive 2018 - Report 27 Math under Shyamasundar G.P.within Raina- 2010/DP 07/08/2019 500000 Officer, Raina- 490000 490000 100 Yes 2019 Wanting I P.S. I P.S.

AC high must tower, luminaries150 watt led Executive 2018 - Report 28 base at Machkhanda near High School under 4233/DP 25/11/2019 455000 Officer, Raina- 454363 454363 100 Yes 2019 Wanting Hijalna GP within Raina-I P.S. I P.S.

Constn. and purchase of 10 mtr. High must Executive 2018 - Report 29 light at Bolpur Bislaxmitala under Hijalna 4231/DP 25/11/2019 250000 Officer, Raina- 250000 250000 100 Yes 2019 Wanting G.P. within Raina-I P.S. I P.S.

AC high must tower, luminaries150 watt led Executive 2018 - Report 30 base at Belsor Tematha under Hijalna GP 4232/DP 25/11/2019 455000 Officer, Raina- 454363 454363 100 Yes 2019 Wanting within Raina-I P.S. I P.S.

Constn. of Burning Ghat at Dharan Vill. 2018 - Executive Report 31 (Mouza-Dharan, Plot No. 869) under 2019 171/DP 14/01/2020 350000 Officer, Raina- 349650 349650 100 Yes Wanting Palashan G.P. within Raina-I P.S. I P.S. Total 2060000 2398376 2398376 Grand Total 14409758 14138436 14138436

27 ONGOING SCHEMES

28 NEPAL GHORUI, HON'BLE MLA-261 RAINA(SC) A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Name of the Scheme Year Present Status No. Order No Sanction Sanction Agency Released Utilized Progress Submitted

Constn. of waiting room at Executive Roof shed completed 2018 - & ongoing work will 1 Mogholmari of Sehara G.P. under 2010/DP 07/08/2019 400000 Officer, Raina- I 400000 300000 75 No 2019 be completed on Raina-I P.S. P.S. 26/02/2020 Constn. of Mukta Mancha at Executive Roof Shed completed Machkhanda village (Mouza- 2018 - & ongoing work will 2 4613/DP 20/12/2019 400000 Officer, Raina- I 400000 300000 75 No Machkhanda, Plot No. 1430) under 2019 be completed on P.S. Hijalna G.P. within Raina-i P.S. 26/02/2020

Executive Constn. of Mukta Mancha at Alampur 2018 - Work just started & 3 90/DP 08/01/2020 400000 Officer, Raina- II 400000 300000 75 No expected completion under Arui G.P. within Raina-II P.S. 2019 P.S. dt.-15/03/2020

Constn. of Mukta Mancha at Executive 2018 - Work just started & 4 Rashbehari Basu Trust under 90/DP 08/01/2020 400000 Officer, Raina- II 400000 300000 75 No expected completion 2019 Barabainan G.P. within Raina-II P.S. P.S. dt.-15/03/2020

Constn. of Mukta Mancha at Pasra Executive 2018 - Work just started & 5 under Barabainan G.P. within Raina-II 90/DP 08/01/2020 400000 Officer, Raina- II 400000 300000 75 No expected completion 2019 P.S. P.S. dt.-15/03/2020

Constn. of Mukta Mancha at Lohai Executive Work just started & 2018 - expected completion 6 Sammilani Vidyaniketan under Arui 90/DP 08/01/2020 400000 Officer, Raina- II 400000 300000 75 No 2019 dt.-15/03/2020 G.P. within Raina-II P.S. P.S. Wanting29 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. and purchase of 10 mtr High Executive must light at near Aushara 2018 - Work completed UC 7 94/DP 06/02/2020 250000 Officer, Raina- 250000 187500 75 No will be submitted Barowarital;a under Sehara GP within 2019 I P.S. 14/02/2020 Raina-I P.S.

Installation of submersible at Executive 2018 - Work completed UC 8 Jotchillam F.P. School under Hijalna 774/DP 28/02/2020 120000 Officer, Raina- 120000 90000 75 No will be submitted 2019 G.P. within Raina-I P.S. I P.S. 14/02/2020

Total 2770000 2670000 1777500

30 Shri Samar Hazra, Hon’ble M.L.A. of 262-Jamalpur (SC) PC

31 COMPLETED SCHEMES

32 SAMAR HAZRA, HON'BLE MLA-262 JAMALPUR(SC) A.C.

UC Handed Sl.N Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitte Over o. Order No Sanction Sanction Agency Released Utilized Progress d Status Executive Constn of Bituminus Road from Maina Rail 2016 - Report 1 2373/DP 18/10/2016 1500000 Officer, Jamalpur 1053059 1053059 100 Yes Gate to Bituminus road at Nabagram 2017 Wanting P.S.

Executive Instn of Tubewell at Uttar Mohanpur Bandh at 2016 - Report 2 2548/DP 03/11/2016 35000 Officer, Jamalpur 35000 35000 100 Yes Jargram G.P. 2017 Wanting P.S.

Executive Instn of Tubwwell at Kashinathpur Tala of 2016 - Report 3 2548/DP 03/11/2016 35000 Officer, Jamalpur 35000 35000 100 Yes Kolsara village at Abujhati 2017 Wanting P.S.

Executive Inst of tubewell at Saswan of Salanpur village 2016 - Report 4 2548/DP 03/11/2016 35000 Officer, Jamalpur 35000 35000 100 Yes at Ajhapur 2017 Wanting P.S.

Executive Constn of Pucca Drain at Ramnathpur village 2016 - Report 5 2685/DP 18/11/2016 60000 Officer, Jamalpur 58462 58462 100 Yes from Sandani Mondal Shop to Biswa Pukur 2017 Wanting P.S.

Executive Constn of Pucca drain at Ramnathpur vill from 2016 - Report 6 2685/DP 18/11/2016 135000 Officer, Jamalpur 132178 132178 100 Yes house of N. Santra 2017 Wanting P.S.

Executive Constn of Black Top Toad from Badhpur 2016 - Report 7 2717/DP 21/11/2016 1000000 Officer, Jamalpur 995070 995070 100 Yes Raildhar to Bakultala at Jougram G.P. 2017 Wanting P.S. 33 UC Handed Sl.N Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitte Over o. Order No Sanction Sanction Agency Released Utilized Progress d Status Constn of Jhama Compaction road from Executive 2016 - Report 8 Nabagram MBF brick field to Verili Khalar 819/DP 16/03/2017 200000 Officer, 172845 172845 100 Yes 2017 Wanting math Jamalpur P.S. Exe. Engg. Purba Instt of four Nos Deep Tubewell for Irrigation 2016 - Report 9 1657/DP 09/06/2017 2168428 Bardhaman 1869486 1869486 100 Yes of Land 500 Bighas of Paratal -I G.P. 2017 Wanting (Agri-Irrign.) Divn. Constn of Bituminus road from Nabagram Executive 2016 - Report 10 MBF Brick field to Verili Khelar Math of 2337/DP 24/08/2017 478456 Officer, 478456 478456 100 Yes 2017 Wanting Ajhapur G.P. Jamalpur P.S. District 2016 - Report 11 Purchase an Ambulance for Panchra G.P. 2530/DP 13/09/2017 595204 Magistrate, 595204 595204 100 Yes 2017 Wanting Burdwan Executive Instn of five No Solar Light on the Math Rasta 2016 - Report 12 2711/DP 17/10/2017 101250 Officer, 101250 101250 100 Yes from Nabagram Rly. station to Musunda 2017 Wanting Jamalpur P.S.

Instn of one no Tubewell near Mahisgharia Executive 2016 - Report 13 Kalitala Adibasipara Nutanpukurpar of 3326/DP 19/12/2017 40000 Officer, 40000 40000 100 Yes 2017 Wanting Jargram Jamalpur P.S.

Executive Instn of one tubewell near Siali Kalitala of 2016 - Report 14 3326/DP 19/12/2017 40000 Officer, 40000 40000 100 Yes Jotsrirampur 2017 Wanting Jamalpur P.S.

Total 6423338 5641010 5641010 34 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitte No. Order No Sanction Sanction Agency Released Utilized Progress Status d

Constn of Swamsan Chulli at Bele Swasan Executive 2017 - Report 15 nearest to the Khelaghar ground 2771/DP 30/10/2017 318805 Officer, 318805 318805 100 Yes 2018 Wanting under Jamalpur Jamalpur P.S.

Constn of Concrete Road from Panchra Executive 2017 - Report 16 Simuldanga to Ghatakpukur of Panchra 3020/DP 17/11/2017 199993 Officer, 199993 199993 100 Yes 2018 Wanting G.P. Jamalpur P.S.

Executive Constn of Samsan Chulliand waiting 2017 - Report 17 3020/DP 17/11/2017 500000 Officer, 500000 500000 100 Yes Roomat Mugura Village near Kamarpukur 2018 Wanting Raina- I P.S.

Executive Constn of School Building of Basantapur 2017 - Report 18 3069/DP 23/11/2017 480291 Officer, 480291 480291 100 Yes Junior High School at Paratal G.P. 2018 Wanting Jamalpur P.S.

Instn of one No. Cycllinder well at Executive 2017 - Report 19 Shambhupur Purba Adibasipara under 3325/DP 19/12/2017 40000 Officer, 40000 40000 100 Yes 2018 Wanting Jamalpur Jamalpur P.S.

Constn of Moorum Road from Sankita to Executive 2017 - Report 20 Boro Road from Angona Asaktala to 83/DP 11/01/2018 1500000 Officer, 1500000 1500000 100 Yes 2018 Wanting Dalshinkul village Raina- I P.S.

Executive Constn. of Swasan Chulli and waiting room 2017 - Report 21 221/DP 01/02/2018 497500 Officer, 497500 497500 100 Yes at Karalgram 2018 Wanting Jamalpur P.S. 35 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitte No. Order No Sanction Sanction Agency Released Utilized Progress Over Status d

Constn of Samsan Chulli and waiting room at 2017 - Executive Officer, Report 22 221/DP 03/02/2018 497400 497400 497400 100 Yes Jharagram village 2018 Jamalpur P.S. Wanting

Constn of Samsan Chulli and waiting room at 2017 - Executive Officer, Report 23 Chaksanjadi vill near Khelar Math under 221/DP 03/02/2018 500000 500000 500000 100 Yes Jamalpur P.S. Jamalpur 2018 Wanting

Instn of one no. Cycllinder Tubewell at 2017 - Executive Officer, Report 24 680/DP 27/03/2018 39800 39800 39800 100 Yes Kamghosha village 2018 Jamalpur P.S. Wanting

Instn of one no. Cycllinder Tubewell at Sukpur 2017 - Executive Officer, Report 25 680/DP 27/03/2018 39620 39620 39620 100 Yes village 2018 Jamalpur P.S. Wanting

Instn of one no. Cycllinder Tubewell at 2017 - Executive Officer, Report 26 680/DP 27/03/2018 39740 39740 39740 100 Yes Ramchandrapur village 2018 Jamalpur P.S. Wanting

Installation of One no., Tubewell with Electric 2017 - Executive Officer, Report 27 Motor at Meral village under Mugura G.P. 1137/DP 21/06/2018 100000 100000 100000 100 Yes Raina- I P.S. within Raina-I P.S. 2018 Wanting

Constn. of one Community hall at Balarampur 2017 - Executive Officer, Report 28 470/DP 14/02/2019 500000 498500 498500 100 Yes village at Berugram G.P. under Jamalpur P.S. 2018 Jamalpur P.S. Wanting

Total 5253149 5251649 5251649

36 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ted Constn. of Toe Wall beside Uttarsura Majher District Ghosh Para road for widening and 2018 - Report 29 1997/DP 06/09/2018 600000 Magistrate, 541378 541378 100 Yes strengthing of village road under Jamalpur 2019 Wanting Burdwan P.S. Constn. of Bituminous road from Maina District Durgatala to Canelpul with drain from B. 2018 - Report 30 1997/DP 06/09/2018 1200000 Magistrate, 1200000 1200000 100 Yes Bag house to S. Bag House under Jamalpur 2019 Wanting Burdwan P.S Constn. of one shed at Jamalpur Block Executive 2018 - Report 31 Hospital under Jamalpur G.P. within 2121/DP 20/09/2018 200000 Officer, 200000 200000 100 Yes 2019 Wanting Jamalpur P.S. Jamalpur P.S. Installation of 1 no. Tubewell with Executive 2018 - Report 32 Submersible Motor Pump and pipe line 2282/DP 10/10/2018 100000 Officer, 99930 99930 100 Yes 2019 Wanting Kulingram High School within Jamalpur P.S. Jamalpur P.S. Constn. of Swasan Chulli with waiting room Executive 2018 - Report 33 at astai village under Abujhati-I GP within 3118/DP 07/12/2018 500000 Officer, 498250 498250 100 Yes 2019 Wanting Jamalpur Ps. Jamalpur P.S. Constn. of School Building (Class room) of Executive 2018 - Report 34 Meral FP School at Meral Village under 3118/DP 07/12/2018 500000 Officer, 499405 499405 100 Yes 2019 Wanting Mugura within Raina-I P.S. Raina- I P.S. Constn. of waiting shed for Jamudaha Executive 2018 - Report 35 Kalitala Swasan under Berugram G.P. 418/DP 06/02/2019 400000 Officer, 399880 399880 100 Yes 2019 Wanting within Jamalpur P.S. Jamalpur P.S. Installation of 1 no. cyllinder tube well at Executive Sially village near masjidtala JL no. 72 Plot 2018 - Report 36 844/DP 06/03/2019 45000 Officer, 45000 45000 100 Yes no. 1263 under Jotesriram G.P. within 2019 Wanting Jamalpur P.S. 37 Jamalpur P.S. UC Handed Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitte Over No. Order No Sanction Sanction Agency Released Utilized Progress d Status Installion of 1 no. cycillender tube well at Executive Mosagram Miarber para Plot no. 1731 near 2018 - Report 37 844/DP 06/03/2019 45000 Officer, 44775 44775 100 Yes Abdul Razek house under Panchra G.P. 2019 Wanting Jamalpur P.S. within Jamalpur P.S. Installation of 1 no. cyllinder tube well at Executive Mosagram Fotepur para near Sk. Ohidul 2018 - Report 38 844/DP 06/03/2019 45000 Officer, 45000 45000 100 Yes house at Mosagram village under Panchra 2019 Wanting Jamalpur P.S. G.P. within Jamalpur P.S.

Installation of 1 no. cyllinder tube well at Executive 2018 - Report 39 Uchitpur village JL no. 92 Plot no. 503 844/DP 06/03/2019 45000 Officer, Raina- I 45000 45000 100 Yes 2019 Wanting under Mugura G.P. within Raina-I P.S. P.S.

Installation of one Cylider Tube well with Executive subnersible motor with water tank and 2018 - Report 40 2009/DP 07/08/2019 100000 Officer, 100000 100000 100 Yes Pipeline at Nabagram Moyna L.S.B 2019 Wanting Jamalpur P.S. Vidyalya Installation of 1 no. tubewell at Meral Math Executive 2018 - Report 41 Para near Laltu Cycle Shop under Mugura 4235/DP 25/11/2019 45000 Officer, Raina- I 45000 45000 100 Yes 2019 Wanting G.P. P.S.

Executive Constn. of School Building at Junior High 2018 - Report 42 4514/DP 12/12/2019 499850 Officer, 499850 499850 100 Yes School at Duluk Village 2019 Wanting Jamalpur P.S.

Total 4324850 4263468 4263468 Grand Total 16001337 15156127 15156127 38 ONGOING SCHEMES

39 SAMAR HAZRA, HON'BLE MLA 262 JAMALPUR(SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submi Present Status No. Order No Sanction Sanction Agency Released Utilized Progress tted

Constn. of drain beside newly constn. Executive 2017 - 1 bituminus road at Moyna under 4271/DP 27/11/2019 201347 Officer, 201347 151313 75 No Balance Fund will be 2018 refunded. Ajhapur G.P. within Jamalpur P.S. Jamalpur P.S.

Constn. of one wall and one pucca Executive 2017 - 2 ghat at Ajhapur Hattala within 709/DP 24/02/2020 500000 Officer, 4999000 374250 75 No Work just started 2018 Jamalpur P.S. Jamalpur P.S. Total 701347 575597 151313 Constn. of bituminus road from Amarpur Bimola Krishi High School Executive 2018 - Local problem arised 3 to Damodar bandh at Amarpur 1307/DP 30/05/2019 500000 Officer, 375000 0 0 No 2019 work not started. village Palpara under Jotesriram G.P. Jamalpur P.S. within Jamalpur P.S.

Installa of one tubewell at Astai Executive 2018 - Work complete 1st 4 Sasan at Astai village under 523/DP 07/02/2020 45000 Officer, 45000 33750 75 No 2019 Phase UC submitted. Abujhati-i GP. within Jamalpur P.S. Jamalpur P.S.

Const. of one roof shed Jaragram Executive 2018 - Work in progress 1st 5 Makhanlal Pathagar at Jarogram 710/DP 24/02/2020 199900 Officer, 199900 149925 75 No 2019 RA bill on 05/03/2020 under Jarogram GP. Jamalpur P.S. Total 744900 619900 183675 40 Physi UC Sl. Sanction Date of Amount Executing Amount Amount cal Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess

Executive Constn. of Swasan Chulli at Sambhupur 2019 - Work in progress and 6 728/DP 25/02/2020 400000 Officer, 297750 0 0 No UC will be submitted village under Berugram G.P. 2020 Jamalpur P.S. soon.

Constn. of cycle stand at Ajhapur Executive 2019 - Work will be started 7 Balika Vidyalaya (High) under Ajhapur 728/DP 25/02/2020 400000 Officer, 297900 0 0 No 2020 very soon. GP. within Jamalpur P.S. Jamalpur P.S.

Total 800000 595650 0 Grand Total 2246247 6415897 709238

41 Shri Saikat Panja, Hon’ble M.L.A. of 263-Monteswar (SC) AC

42 COMPLETED SCHEMES

43 Lt. SAJAL PANJA & SAIKAT PANJA, HON'BLE MLA 263 MONTESWAR A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Handed Over Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

Constn of Concrete road from Bijur 2016 - Executive Officer, Report 1 230/DP 18/01/2017 200000 200000 200000 100 Yes Hattala to Doltala of Bijur G.P. 2017 Memari- II P.S. Wanting

Constn of Boundary Wall of Birta 2016 - Executive Officer, Report 2 230/DP 18/01/2017 300000 300000 300000 100 Yes Hospital of Bohar G.P. 2017 Memari- II P.S. Wanting

High Must Electric Light at 2016 - Executive Officer, Report 3 230/DP 18/01/2017 200000 174679 174679 100 Yes More Bijur G.P. 2017 Memari- II P.S. Wanting

High Must Electric Light at 2016 - Executive Officer, Report 4 230/DP 18/01/2017 200000 155830 155830 100 Yes Mondalgram Bazar 2017 Memari- II P.S. Wanting

High Must at Bitra Barowaritala of 2016 - Executive Officer, Report 5 230/DP 18/01/2017 200000 153902 153902 100 Yes Bohar G.P. 2017 Memari- II P.S. Wanting

Constn of waiting shed at Dhokolpur of 2016 - Executive Officer, Report 6 230/DP 18/01/2017 200000 182984 182984 100 Yes Bijur G.P. 2017 Memari- II P.S. Wanting

High Mast Electric Light at Bohar 2016 - Executive Officer, Report 7 230/DP 18/01/2017 200000 168638 168638 100 Yes Bazar of Bohar G.P. 2017 Memari- II P.S. Wanting

CConstn. of waiting room infront of 2016 - Executive Officer, Report 8 Rabindra Nazrul Mahavidyalaya of C- 522/DP 16/02/2017 300000 300000 300000 100 Yes 2017 Memari- II P.S. Wanting Satgachia- I GP 44 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Drinking Water Project at Majhergram Executive 2016 - Report 9 Bazar Source of Water I HP Motor of 743/DP 09/03/2017 300000 Officer, 210000 210000 100 Yes 2017 Wanting Majher Gram Monteswar P.S. Constn of C C Road from Bhagra Bara Executive 2016 - Report 10 Masjid towards Bagra village road upto 806/DP 15/03/2017 400000 Officer, 400000 400000 100 Yes 2017 Wanting Bagra-Mulgram Monteswar P.S. Executive High Mast Electric Light at Bijur Bazar 2016 - Report 11 2018/DP 18/07/2017 200000 Officer, Memari- 164607 164607 100 Yes Hattala of Bijur-I G.P. 2017 Wanting II P.S. Total 2700000 2410640 2410640 Executive High Mast Light at Sridhar Hattala of 2017 - Report 12 2288/DP 18/08/2017 200000 Officer, Memari- 135377 135377 100 Yes Satgachia I G.P. 2018 Wanting II P.S. Executive High Mast Light at Jhikra More of 2017 - Report 13 2288/dp 18/08/2017 200000 Officer, Memari- 134231 134231 100 Yes Satgachia i G.P. 2018 Wanting II P.S. Executive High Mast Light at Bohar Hattala of 2017 - Report 14 2288/DP 18/08/2017 200000 Officer, Memari- 132756 132756 100 Yes Bohar G.P. 2018 Wanting II P.S. Executive High Mast Light at Barapalason to 2017 - Report 15 2288/DP 18/08/2017 200000 Officer, Memari- 149319 149319 100 Yes Barapalason G.P. 2018 Wanting II P.S. Executive Constn of waiting Shedat Ashapur of 2017 - Report 16 2288/DP 18/08/2017 200000 Officer, Memari- 200000 200000 100 Yes Bijur G.P. 2018 Wanting II P.S. 45 Physical UC Sl. Sanction Date of Amount Executing Amount Amount Handed Over Name of the Scheme Year Progres Submitt No. Order No Sanction Sanction Agency Released Utilized Status s ed

Constn of Waiting Shed at Kala Dighi 2017 - Executive Officer, 17 2288/DP 18/08/2017 200000 200000 200000 100 Yes Report Wanting Par of Barapalason 2018 Memari- II P.S.

Constn of Waiting Shed at Begunia 2017 - Executive Officer, 18 2288/DP 18/08/2017 200000 200000 200000 100 Yes Report Wanting More of Bijur G.P. 2018 Memari- II P.S.

Constn of Concrete road from Bijur 2017 - Executive Officer, 19 2288/DP 18/08/2017 200000 200000 200000 100 Yes Report Wanting Hattala to Doltala 2018 Memari- II P.S.

Constn of Concrete road at Paharhati 2017 - Executive Officer, 20 2288/DP 18/08/2017 200000 200000 200000 100 Yes Report Wanting Golapmoni High School 2018 Memari- II P.S.

Constn of PCC Road from S. Banerjee 2017 - Executive Officer, 21 House to K. Mondal house of 2823/DP 06/11/2017 300000 300000 300000 100 Yes Report Wanting 2018 Monteswar P.S. Monteswar G.P.

Constn of PCC Road fromGarsona 2017 - Executive Officer, 22 Danga Ramchandra House to Hazra 2823/DP 06/11/2017 150000 149726 149726 100 Yes Report Wanting 2018 Monteswar P.S. Para Rasta of Mamudpur G.P.

Constn of PCC Road at Susunia 2017 - Executive Officer, 23 2823/DP 06/11/2017 200000 200000 200000 100 Yes Report Wanting Ranibala Bidyamandir of Susunia G.P. 2018 Monteswar P.S. 46 UC Sl. Sanction Date of Amount Amount Amount Physical Handed Over Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed Constn of PCC Road from A.Pal 2017 - Executive Officer, Report 24 house to M. Santra house at 2823/DP 06/11/2017 100000 99278 99278 100 Yes 2018 Monteswar P.S. Wanting Daukadanga of Denur G.P. Constn of three Culvert between 2017 - Executive Officer, Report 25 Sahajadpur to Rakuspur road of Bohr 3065/DP 23/11/2017 300000 300000 300000 100 Yes 2018 Memari- II P.S. Wanting G.P Constn of PCC Road from Bandhupur 2017 - Executive Officer, Report 26 Durgatala to Uday Ghosh Kolghar of 3065/DP 23/11/2017 150000 150000 150000 100 Yes 2018 Monteswar P.S. Wanting Mamudpur G.P.

Constn of Community Hall at Ujna 2017 - Executive Officer, Report 27 3065/DP 23/11/2017 300000 299135 299135 100 Yes Adibasipara of Bhagra Mulgram G.P. 2018 Monteswar P.S. Wanting

Constn of PCC Road from pakka 2017 - Executive Officer, Report 28 3065/DP 23/11/2017 110000 110000 110000 100 Yes Rasta to N.Raj house at 2018 Monteswar P.S. Wanting Constn of Boundary Wall around 2017 - Executive Officer, Report 29 Banui Panchapali Vidyamandir of 3065/DP 23/11/2017 100000 100000 100000 100 Yes 2018 Monteswar P.S. Wanting Susunia G.P. Constn of PCC Road from Parulia 2017 - Executive Officer, Report 30 Tematha N. Chatterjee house to 3289/DP 13/12/2017 300000 298897 298897 100 Yes 2018 Monteswar P.S. Wanting Mirpur Bazar of Majher Gram

Constn of PCC Foot Path from S. 2017 - Executive Officer, Report 31 3289/DP 13/12/2017 50000 49492 49492 100 Yes Hazra to M. Hazra house at Kitsihi 2018 Monteswar P.S. Wanting

Constn of PCC Foot Path from T 2017 - Executive Officer, Report 32 Hazra house to N. Hazra House at 3289/DP 13/12/2017 50000 49799 49799 100 Yes 2018 Monteswar P.S. Wanting Katsihi 47 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Order Submitt No. Sanction Sanction Agency Released Utilized Progress Status No ed Constn of PCC Road from Daspara SSK Executive 2017 - Report 33 School via Kabarsthan to Bamunia Paka 3289/DP 13/12/2017 300000 Officer, 300000 300000 100 Yes 2018 Wanting rasta Monteswar P.S. Constn of PCC Road from Hafijul Sk Executive 2017 - Report 34 house to Ansar Mallick house via 3289/DP 13/12/2017 200000 Officer, 200000 200000 100 Yes 2018 Wanting Ibraham Sk house Monteswar P.S. Executive Constn of PCC Road from Nabagram 2017 - Report 35 1417/DP 01/08/2018 200000 Officer, 200000 200000 100 Yes towards Baishnab Danga High School 2018 Wanting Monteswar P.S. Constn of PCC Road from Khirod das Executive 2017 - Report 36 houseto Madhai Das House via 1820/DP 14/08/2018 200000 Officer, 199252 199252 100 Yes 2018 Wanting Panchanantala Monteswar P.S. Constn. of Baitarani Scheme at Exe. Engg. PWD 2017 - Report 37 Monteswar and Ghatak Para More 2459/DP 10/10/2018 890000 (Social Sector), 694916 694916 100 Yes 2018 Wanting (mouza-Satgachia) within Monteswar P.s. Burdwan. Total 5700000 5252178 5252178

48 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status Executive Constn. of cc road from Galatun to 2018 - Report 38 2077/DP 18/09/2018 300000 Officer, 299910 299910 100 Yes Denua Village 2019 Wanting Monteswar P.S. Constn of Concrete Road from Executive 2018 - Report 39 Tribarna Club to Baromatala of 2077/DP 18/09/2018 50000 Officer, 50000 50000 100 Yes 2019 Wanting Kusumgram Monteswar P.S. Constn. of cc road from Ansar Ali Executive 2018 - Report 40 Mondal to Gandgoria Masjid under 2077/DP 18/09/2018 250000 Officer, 250000 250000 100 Yes 2019 Wanting Mamudpur-I GP Monteswar P.S. Executive Constn. of Beneficiaries refreshment 2018 - Report 41 3217/DP 17/12/2018 548000 Officer, Memari- 548000 548000 100 Yes shed at Gargeswar 2019 Wanting II P.S. Executive Constn. of waiting shed at jamna 2018 - Report 42 3217/DP 17/12/2018 150000 Officer, 150000 150000 100 Yes Shivtala of Jamna G.P. 2019 Wanting Monteswar P.S. Total 1298000 1297910 1297910 Grand Total 9698000 8960728 8960728

49 ONGOING SCHEMES

50 SAIKAT PANJA, HON'BLE MLA 263 MONTESWAR A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Name of the Scheme Year Executing Agency Submitt Present Status No. Order No Sanction Sanction Released Utilized Progress ed

Nine mtr. mini High Mast tower Agro 2016 - Fund 1 lighting 6 nos. 120 watt at 2016/DP 10/09/2018 399898 Industries Corporation 399898 299924 75 No 2017 transferred Monteswar Kamar Shal More Ltd. 23 B Total 399898 399898 299924 Nine Mtr high Must tower lighting West Bengal Agro system 4 nos. 80 watt Led lighting 2018 - Fund 2 561/DP 20/02/2019 180000 Industries Corporation 180000 135000 75 No fitting with each complete with all 2019 transferred Ltd. 23 B accessories under Piplon G.P. 12 watt Led Solar Street Light West Bengal Agro 2018 - Fund 3 with 5 meter Satgachia near 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No 2019 transferred Sastitala under Satgachia-I G.P. Ltd. 23 B 12 watt Led Solar Street Light West Bengal Agro with 5 meter Katabari near 2018 - Fund 4 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No Kalitala under Barapalashon-II 2019 transferred Ltd. 23 B G.P. 12 watt Led Solar Street Light West Bengal Agro with 5 meter Barapalashon 2018 - Fund 5 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No Hazrapukur near Kalitala Under 2019 transferred Ltd. 23 B Barapalashon-II G.P. 12 watt Led Solar Street Light West Bengal Agro with 5 meter Barapalashon beside 2018 - Fund 6 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No Sankor Matha Under 2019 transferred Ltd. 23 B Barapalashon-II G.P. 51 UC Sl. Sanction Date of Amount Amount Amount Physical Present Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

12 watt Led Solar Street Light with West Bengal Agro 2018 - Fund 7 5 meter Ahira near Durgatala 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No 2019 transferred under Satgachia-I G.P Ltd. 23 B 12 watt Led Solar Street Light with West Bengal Agro 2018 - Fund 8 5 meter Shantidanga near 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No 2019 transferred Durgatala under Satgachia-I G.P Ltd. 23 B 12 watt Led Solar Street Light with West Bengal Agro 2018 - Fund 9 5 meter Mirzapur beside Gorer 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No 2019 transferred More Under Barapalashon-II G.P. Ltd. 23 B 12 watt Led Solar Street Light with West Bengal Agro 2018 - Fund 10 5 meter Satgachia Ghatakpara 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No 2019 transferred under Satgachia-I G.P Ltd. 23 B 12 watt Led Solar Street Light with West Bengal Agro 2018 - Fund 11 5 meter Kuroram Palli under 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No 2019 transferred Barapalashon-II G.P. Ltd. 23 B 12 watt Led Solar Street Light with West Bengal Agro 5 meter Near Dihipalashon 2018 - Fund 12 563/DP 20/02/2019 21420 Industries Corporation 21420 16065 75 No Shivtala under Barapalashon-II 2019 transferred Ltd. 23 B G.P.

Nine Mtr Mini high Must tower lighting system with 6 nos. 80 watt West Bengal Agro 2018 - Fund 13 Led light fitting with each 561/DP 20/02/2019 215475 Industries Corporation 215475 161606 75 No 2019 transferred complete with all accessories Ltd. 23 B under Jamna G.P. 52 UC Sl. Sanction Date of Amount Amount Amount Physical Present Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

Nine Mtr Mini high Must tower West Bengal Agro lighting system with 6 nos 80 watt 2018 - Industries Fund 14 Led light fitting with each complete 561/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred with all accessories under Mulgram 23 B G.P. Nine Mtr Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries Fund 15 light fitting with each complete with 561/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred all accessories under Monteswar 23 B G.P. Nine Mtr Mini high Must Tower West Bengal Agro lighting System with 6 nos 120 Watt 2018 - Industries Fund 16 Led Light Near Jabuldanga More 563/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred under Bijur-I G.P within Memari-II 23 B P.S. 12 watt Led Solar Street Light with 5 West Bengal Agro mtr tuble pole 40 AMPS Battery 2018 - Industries Fund 17 561/DP 20/02/2019 21420 21420 16065 75 No Near Bhadai Masjid under Bhagra 2019 Corporation Ltd. transferred Mulgram G.P. 23 B 12 watt Led Solar street light with 5 West Bengal Agro mtr tuble pole 40 AMPS Battery 2018 - Industries Fund 18 561/DP 20/02/2019 21420 21420 16065 75 No near kaltala under Bhagra Mulgram 2019 Corporation Ltd. transferred G.P. 23 B West Bengal Agro 12 watt Led Solar street light with 5 2018 - Industries Fund 19 mtr tuble pole 40 AMPS Battery 561/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Bhagra Mulgram G.P. 53 23 B UC Sl. Sanction Date of Amount Amount Amount Physical Present Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

West Bengal Agro 12 watt Led Solar street light with 5 2018 - Industries Fund 20 mtr tuble pole 40 AMPS Battery 561/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Bhagra Mulgram G.P... 23 B

12 watt Led Solar Street light with 5 West Bengal Agro mtr tuble pole40 AMPSb Battery 2018 - Industries Fund 21 561/DP 20/02/2019 21420 21420 16065 75 No near Boro Masjid under Bhagra 2019 Corporation Ltd. transferred Mulgram G.P. 23 B

Nine Mtr Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries Fund 22 light fitting with each complete with 561/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred all accessories under Kusumgram 23 B G.P. Nine Mtr Mini high Must Tower West Bengal Agro lighting System with 6 nos 120 2018 - Industries Fund 23 Watt Led Light at Bora Hazra Para 563/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred under Bohar-II G.P within Memari- 23 B II P.S. Nine Mtr Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries Fund 24 light fitting with each complete 561/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred with all accessories under Baghason 23 B G.P. 54 UC Sl. Sanction Date of Amount Amount Amount Physical Present Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

12.5 Mtr Mini high Must Tower West Bengal Agro lighting System with 6 nos 150 Watt 2018 - Industries Fund 25 Led Light at Malamba Bazar under 563/DP 20/02/2019 455000 454999 341250 75 No 2019 Corporation Ltd. transferred Barphalasan- I G.P within Memari-II 23 B P.S.

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 26 meter Near Jotram Primary School 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Under Bijur-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 27 meter at Begunia Aimapara Under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Bijur-II G.P. 23 B

9 Mtr Tubler pole with 4 nos 120 West Bengal Agro watt Led light fittings with each 2018 - Industries Fund 28 561/DP 20/02/2019 150000 150000 112500 75 No complete with all accressories under 2019 Corporation Ltd. transferred Kusumgram G.P. 23 B

Nine Mtr high Must tower lighting West Bengal Agro system 4 nos 80 watt Led lighting 2018 - Industries Fund 29 561/DP 20/02/2019 180000 180000 135000 75 No fitting with each complete with all 2019 Corporation Ltd. transferred accessories under Susuni G.P. 23 B 55 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Present Name of the Scheme Year Submitte No. Order No Sanction Sanction Agency Released Utilized Progress Status d

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 30 meter Dhunui near Haritala under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Bijur-II G.P 23 B

12 watt Led Solar Street light with 5 West Bengal Agro mtr. tuble pole 40 AMPS Battery 2018 - Industries Fund 31 561/DP 20/02/2019 21420 21420 16065 75 No near Masjidtala under Bhagra 2019 Corporation Ltd. transferred Mulgram G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 32 meter Koruri near Kalitala Under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Barapalashon-II G.P. 23 B

Twelve watt Led Solar Street Light West Bengal Agro with five meter near Bhadul Shivtala 2018 - Industries Fund 33 563/DP 20/02/2019 21420 21420 16065 75 No under Bijur-I G.P. within Memari-II 2019 Corporation Ltd. transferred P.S. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 34 meter Near Melna Barowari Bijur-I 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 35 meter Near Kandarpapur Haritala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Under Bijur-I G.P. 56 23 B UC Sl. Sanction Date of Amount Executing Amount Amount Physical Present Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 36 5 meter Near Munsidanga Primary 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred School Under Bijur-II G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 37 5 meter Ashapur Bangal Para Under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Bijur-II G.P. 23 B Nine Mtr Mini highn Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries Fund 38 light fitting with each complete with 561/DP 20/02/2019 215475 215475 161606 75 No 2019 Corporation Ltd. transferred all accessories under Kusumgram 23 B G.P. West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 39 5 meter Satgachia Paschimpara 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Satgachia-I G.P 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 40 5 meter Near Udaynala Club under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Barapalashon-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 41 5 meter Melna More Under Bijur-I 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred G.P. 23 B 57 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Present Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 42 5 meter Kathalia near Durgatala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Satgachia-I G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 43 5 meter Kalapukur near Durgatala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Satgachia-I G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 44 5 meter Benigram Paschimpara 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Bijur-II G.P 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 45 5 meter Bharkhanda beside 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Tematha under Satgachia-I G.P 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 46 5 meter Goaldingi near Durgatala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Satgachia-I G.P 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 47 5 meter Barapalashan Janapara near 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Kalitala under Barapalashon-II G.P. 23 B 58 UC Sl. Sanction Date of Amount Amount Amount Physical Present Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 48 meter Biskopa near Bankarpul 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. 23 transferred Under Bijur-II G.P. B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 49 meter Barowari beside Gachtala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. 23 transferred under Barapalashon-II G.P. B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 50 meter Nanna Dighirpara under Bijur- 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. 23 transferred II G.P B

West Bengal Agro 12 watt Led Solar Street Light with 5 2018 - Industries Fund 51 meter Benigram near Kalitala under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. 23 transferred Bijur-II G.P B

7.5 Mtr Tubler Pole with 4 nos. 100 West Bengal Agro watt Led Light fitting with each 2018 - Industries Fund 52 561/DP 20/02/2019 100000 100000 75000 75 No complete with all acceories 2019 Corporation Ltd. 23 transferred Majhergram G.P. B 59 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Present Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

7.5 Mtr Tubler Pole with 4 nos. 100 West Bengal Agro watt Led light fitting with each 2018 - Industries Fund 53 561/DP 20/02/2019 100000 100000 75000 75 No complete with all accessories Under 2019 Corporation Ltd. transferred Monteswar G.P. 23 B

Nine Mtr. Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries Fund 54 561/DP 20/02/2019 215475 215475 161606 75 No light fitting with each complete with 2019 Corporation Ltd. transferred all accessories under Piplon G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 55 5 meter Near Biskopa Monosatala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Under Bijur-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 56 5 meter Bilbari near Barowaritala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred under Bijur-II G.P 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 57 5 meter Beside Gargeswar Under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Bijur-II G.P. 23 B 60 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Present Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 58 5 meter Shridharpur near Durgatala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Under Satgachia-I G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 59 5 meter Near Shridharpur High 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred School Under Satgachia-I G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 60 5 meter Near Sarra Masjidtala 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Under Satgachia-I G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 61 5 meter Satgachia Bazarpara Under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Satgachia-I G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 62 5 meter Near Gorapur Club under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Barapalashon-II G.P. 23 B West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Fund 63 5 meter Dhunui Pulpara Under 563/DP 20/02/2019 21420 21420 16065 75 No 2019 Corporation Ltd. transferred Bijur-II G.P. 23 B Total 4111015 4111014 3083259 Grand Total 4510913 4510912 3383183 61 Hon’ble M.L.A. Shri Biswajit Kundu M.L.A of 264-Kalna (SC) AC

62 COMPLETED SCHEMES

63 BISWAJIT KUNDU, HON'BLE MLA-264 KALNA(SC) A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of Shed at Kusodanga 2016 - E.O., Kalna- II Report 1 2515/DP 28/10/2016 150000 150000 150000 100 Yes Champatala of Kalyanpur G.P. 2017 P.S. Wanting

Rep of School Building for 2016 - E.O., Kalna- II Report 2 Sadhupukur Jr. High School at 2515/DP 28/10/2016 498000 498000 498000 100 Yes 2017 P.S. Wanting Anukhal G.P.

Constn of New Pukur Ghat at 2016 - E.O., Kalna- II Report 3 Hanspukur Jangri Pukur of Satgachia 2515/DP 28/10/2016 100000 100000 100000 100 Yes 2017 P.S. Wanting G.P.

Constn of New Pukur Ghat at 2016 - E.O., Kalna- II Report 4 Nasipur Purba Satgachia of 2515/DP 28/10/2016 100000 100000 100000 100 Yes 2017 P.S. Wanting Satgachia G.P.

Constn of New Pukur Ghat at 2016 - E.O., Kalna- II Report 5 Sahapur Muso Pukur of Satgachia 2515/DP 28/10/2016 100000 100000 100000 100 Yes 2017 P.S. Wanting G.P.

Constn of Pay and used Toilet at 2016 - E.O., Kalna- II Report 6 2515/DP 28/10/2016 400000 400000 400000 100 Yes Rathtala of G.P. 2017 P.S. Wanting64 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Year No. Name of the Scheme Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of waiting Shed at Khagrakur 2016 - E.O., Kalna- II Report 7 Sesapota Baroyaritala of Kalyanpur 2515/dp 28/10/2016 150000 150000 150000 100 Yes 2017 P.S. Wanting G.P.

Constn of Pukur Ghat of Khadipara 2016 - E.O., Kalna- II Report 8 2655/DP 15/11/2016 120000 120000 120000 100 Yes San Bandha Pond at Akalpoush G.P. 2017 P.S. Wanting

Constn of Waiting Room infront of 2016 - E.O., Kalna- II Report 9 2655/DP 15/11/2016 150000 150000 150000 100 Yes Baradhamas G.P. 2017 P.S. Wanting

Repar. of School Building for 2016 - E.O., Kalna- II Report 10 2655/DP 15/11/2016 100000 100000 100000 100 Yes Balindar MSK at Baradhemas G.P. 2017 P.S. Wanting

Constn of Pukur Ghat at Narengha of 2016 - E.O., Kalna- II Report 11 2655/DP 15/11/2016 130000 130000 130000 100 Yes AkalpoushG.P. 2017 P.S. Wanting

Constn of New Waiting room and 2016 - E.O., Kalna- II Report 12 Burning Ghat at Boro Bohakuli of 2655/DP 15/11/2016 200000 200000 200000 100 Yes 2017 P.S. Wanting Badla G.P. 65 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of Pukur Ghat of Kulepara 2016 - E.O., Kalna- II Report 13 2655/DP 15/11/2016 150000 150000 150000 100 Yes Bedra Pond at Akalpoush G.P. 2017 P.S. Wanting

Constn of Burning Shade and Stage 2016 - E.O., Kalna- II Report 14 2655/DP 15/11/2016 100000 100000 100000 100 Yes at Noara Goara of Badla G.P. 2017 P.S. Wanting

Constn of Concrete drain for Biruha 2016 - E.O., Kalna- II Report 15 2655/DP 15/11/2016 150000 150000 150000 100 Yes Kshetrapalpara of Baradhemos G.P. 2017 P.S. Wanting

Constn of ACR Angerson MM High 2016 - E.O., Kalna- II Report 16 2959/DP 19/12/2016 400000 400000 400000 100 Yes School at Oindira G.P. 2017 P.S. Wanting

Constn of Road and Drain from 2016 - E.O., Kalna- I Report 17 Company Danga to ICDS Centre of 664/DP 02/03/2017 250000 250000 250000 100 Yes 2017 P.S. Wanting Hatkalna

Constn of Concrete road at Mirarpur 2016 - E.O., Kalna- I Report 18 664/DP 02/03/2017 250000 250000 250000 100 Yes to Hatkalna G.P. 2017 P.S. Wanting 66 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of Concrete Road 2016 - E.O., Kalna- I Report 19 Dharmadanga F.P. School to Mirpur 664/DP 02/03/2017 250000 250000 250000 100 Yes 2017 P.S. Wanting of Hatkalna

Constn of Concrete Road from Peari 2016 - E.O., Kalna- I Report 20 Nagar Health Centre to Biswajit 664/DP 02/03/2017 300000 300000 300000 100 Yes 2017 P.S. Wanting Dharas House

Constn of New Cycle Shed at 2016 - E.O., Kalna- I Report 21 664/DP 02/03/2017 200000 200000 200000 100 Yes Krishnadevpur High School 2017 P.S. Wanting

Constn of Concrete Road from 2016 - E.O., Kalna- I Report 22 Sikarpur Daksnhin Para Masjid to 664/DP 02/03/2017 150000 150000 150000 100 Yes 2017 P.S. Wanting ICDS Centre

District Constn of New gate at Mahishardini 2016 - Report 23 1126/DP 10/04/2017 200000 Magistrate, 200000 200000 100 Yes High School 2017 Wanting Burdwan

Constn of Guardwall of Pond of 2016 - E.O., Kalna- I Report 24 1126/DP 10/04/2017 250000 250000 250000 100 Yes Pathaigachia of Bagnapara G.P. 2017 P.S. Wanting 67 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of New Waiting Shade at 2016 - E.O., Kalna- I Report 25 1126/DP 10/04/2017 150000 150000 150000 100 Yes Kaikhali of Bagnapara G.P. 2017 P.S. Wanting

Constn of New Waiting Shade at 2016 - E.O., Kalna- I Report 26 1126/DP 10/04/2017 200000 200000 200000 100 Yes Shyamganj Para of Hatkalna G.P. 2017 P.S. Wanting

Constn of New Waiting Shed at 2016 - E.O., Kalna- I Report 27 1126/DP 10/04/2017 150000 150000 150000 100 Yes Alagarh of BagnaparaG.P. 2017 P.S. Wanting

Up Gradation of Waiting Shed at District 2016 - Report 28 SDO Office CompoundKalna 1st 1200/DP 17/04/2017 600000 Magistrate, 600000 600000 100 Yes 2017 Wanting phase Burdwan

Total 5948000 5948000 5948000 Exe. Engg. PWD Constn of Baitoroni scheme at Hasan 2017 - Report 29 2357/DP 28/08/2017 890000 (Social Sector), 781869 781869 100 Yes Hati Village Plot No 272 2018 Wanting Burdwan.

Exe. Engg. PWD Constn of Baitoroni scheme at 2017 - Report 30 2357/DP 28/08/2017 890000 (Social Sector), 781868 781868 100 Yes Balindar Village Plot No 75,76,77 2018 Wanting Burdwan. 68 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Exe. Engg. PWD Constn of Baitoroni scheme at 2017 - Report 31 2357/DP 28/08/2017 890000 (Social Sector), 781869 781869 100 Yes Gopaldas Village Plot No 455 2018 Wanting Burdwan. Exe. Engg. PWD Constn of Baitoroni scheme at Deara 2017 - Report 32 2357/DP 28/08/2017 890000 (Social Sector), 781868 781868 100 Yes Village Plot No 969 2018 Wanting Burdwan. New Constn of Pond Ghat at Tala of 2017 - E.O., Kalna- II Report 33 3349/DP 22/12/2017 150000 150000 150000 100 Yes Baidyapur 2018 P.S. Wanting

Inst of Submesible at Baradhamas Jl 2017 - E.O., Kalna- II Report 34 C-466/DP 07/03/2018 250000 250000 250000 100 Yes No 122 Plot No. 489 under Kalna-II 2018 P.S. Wanting

Inst of Submesible at Baradhamas Jl 2017 - E.O., Kalna- II Report 35 C-466/DP 07/03/2018 250000 250000 250000 100 Yes No 122 Plot No. 2603 under Kalna-II 2018 P.S. Wanting

Instn of Drinking Water supply 2017 - E.O., Kalna- II Report 36 Project for the Public Use adjacent to 971/DP 22/05/2018 90000 90000 90000 100 Yes 2018 P.S. Wanting Kalna BDO Office Total 4300000 3867474 3867474 Grand Total 10248000 9815474 9815474

69 ONGOING SCHEMES

70 BISWAJIT KUNDU, HON'BLE MLA 264 KALNA(SC) A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Present Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

NIL Nil Nil Nil Nil Nil Nil Nil Nil Nil Nil

71 Hon’ble M.L.A. Nargis Begum MLA 265 Memari AC

72 COMPLETED SCHEMES

73 NARGIS BEGUM, HON'BLE MLA 265 MEMARI A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Executive Constn of Mid Day Meal Shed at 2016 - Report 1 2048/DP 07/09/2016 262000 Officer, Memari- 262000 262000 100 Yes Radhakantapur High School 2017 Wanting I P.S. Constn of Kitchen Cum Store for Executive 2016 - Report 2 Mid Day Meal at Borea A.W. Centre 2048/DP 07/09/2016 235000 Officer, Memari- 235000 235000 100 Yes 2017 Wanting of Amadpur I P.S.

Executive Constn of Mid Day Meal Shed at 2016 - Report 3 2048/DP 07/09/2016 262000 Officer, Memari- 262000 262000 100 Yes Sashinara High School 2017 Wanting I P.S.

Executive Constn of Mid Day Meal at Ularah 2016 - Report 4 2048/DP 07/09/2016 262000 Officer, Memari- 262000 262000 100 Yes Primary School of Daluibazar 2017 Wanting I P.S.

Constn of Meal Day Meal Shed at Executive 2016 - Report 5 Alipur Parimary School of Durgapur 2048/DP 07/09/2016 262000 Officer, Memari- 261610 261610 100 Yes 2017 Wanting G.P. I P.S.

Executive Constn of Mid Day Meal Shed at 2016 - Report 6 2048/DP 07/09/2016 262000 Officer, Memari- 262000 262000 100 Yes Gobindapur High School of Debipur 2017 Wanting I P.S. 74 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of Mid day Meal Shed at Executive 2016 - Report 7 Bholanath Bidyapith Gantey of 2295/DP 28/09/2016 262000 Officer, Memari- 262000 262000 100 Yes 2017 Wanting Kutuch G.P. II P.S.

Executive Constn of Samsan at Keja of 2016 - Report 8 327/DP 30/01/2017 200000 Officer, Memari- 162009 162009 100 Yes Amadpur G.P. under Memari -I 2017 Wanting I P.S.

Executive Constn of Samsan at Nudipur DVC 2016 - Report 9 327/DP 30/01/2017 200000 Officer, Memari- 200000 200000 100 Yes bridge side Bagila G.P. Burning Shed 2017 Wanting I P.S.

Executive Constn of Community Centre beside 2016 - Report 10 701/DP 07/03/2017 250000 Officer, Memari- 250000 250000 100 Yes Bonerdanga Foot Ball Ground 2017 Wanting I P.S.

Constn of Waiting Shed at 4 No Bus 2016 - Chairman, Report 11 778/DP 14/03/2017 200000 200000 200000 100 Yes Stand Ward No. 5 2017 Memari Muty. Wanting

Constn of waiting Shaed at Memari 2016 - Chairman, Report 12 College more bus Stopage under 778/DP 14/03/2017 300000 300000 300000 100 Yes 2017 Memari Muty. Wanting Memari Muty 75 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Repair of Baggoria F.P School Executive 2016 - Report 13 Building of Debipur G.P under C- 781/DP 14/03/2017 235000 Officer, Memari- 235000 235000 100 Yes 2017 Wanting Memari- I P.S I P.S.

PEC LTD, Unit Inst of Solar Light total five Nos 2016 - 22, 55, Report 14 from Krishnapur More to Sashinara 1157/DP 12/04/2017 125000 125000 125000 100 Yes 2017 Chowringhee Wanting School more of Bagila G.P. Rd.,Kolkata 71 Inst of Solar Light Total seven G.P. PEC LTD, Unit from Mahesdanga Camp 2016 - 22, 55, Report 15 1157/DP 12/04/2017 175000 175000 175000 100 Yes toMaheshdanga Camp Bazar of 2017 Chowringhee Wanting Nimo G.P Rd.,Kolkata 71 PEC LTD, Unit Inst of Solar Light Total Seven from 2016 - 22, 55, Report 16 Maheshpur Masjid Tala to 1157/DP 12/04/2017 175000 175000 175000 100 Yes 2017 Chowringhee Wanting Sikshaniketan More of Daluibazar Rd.,Kolkata 71 PEC LTD, Unit Inst of Solar Light Total Nine 2016 - 22, 55, Report 17 G.P.Kalitala DVC to Matiswar 1157/DP 12/04/2017 275000 275000 275000 100 Yes 2017 Chowringhee Wanting bazarunder Memari-I P.S. Rd.,Kolkata 71 Instn of six Nos of Solar light from PEC LTD, Unit Radhakantapur Bazar to Katna 2016 - 22, 55, Report 18 1157/DP 12/04/2017 175000 175000 175000 100 Yes Baroyari Sibtala of Gope Gantar II 2017 Chowringhee Wanting G.P. Rd.,Kolkata 71 76 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

PEC LTD, Unit Instn of Solar Light Nine G.P.from 2016 - 22, 55, Report 19 Chotkhanda Bazar Syrya Baroyari 1157/DP 12/04/2017 225000 225000 225000 100 Yes 2017 Chowringhee Wanting Tala under Memari I P.S. Rd.,Kolkata 71 PEC LTD, Unit Instn of Nine Nos Solar Light from 2016 - 22, 55, Report 20 Mamudour to Netaji Sattue of dalui 1157/DP 12/04/2017 225000 225000 225000 100 Yes 2017 Chowringhee Wanting bazarI G.P. Rd.,Kolkata 71 PEC LTD, Unit Inst. of Solar Light Total Eight G.P. 2016 - 22, 55, Report 21 from Keja Manasatala to 1157/DP 12/04/2017 200000 200000 200000 100 Yes 2017 Chowringhee Wanting Gopinathputpur Barwaritala Rd.,Kolkata 71 Instn of Ten Nos of Solar Light from PEC LTD, Unit Tarapur South Masjidtala to Parijat 2016 - 22, 55, Report 22 1157/DP 12/04/2017 200000 200000 200000 100 Yes Nagar Primary School of Nimo I 2017 Chowringhee Wanting G.P. Rd.,Kolkata 71 Inst of Solar Light Ganter Chandi PEC LTD, Unit talaGanter Football Busstand Ganter 2016 - 22, 55, Report 23 1157/DP 12/04/2017 100000 100000 100000 100 Yes G.P. Office Magra River canal River 2017 Chowringhee Wanting Bridge Rd.,Kolkata 71 PEC LTD, Unit Inst. of three Nos of Solar Light at 2016 - 22, 55, Report 24 Sikshs Niketan More to Parijat Nagar 1266/DP 25/04/2017 75000 75000 75000 100 Yes 2017 Chowringhee Wanting Primary School Rd.,Kolkata 71 77 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Executive Reconatn of Baggoria F.P. School of 2016 - Report 25 1425/DP 11/05/2017 150000 Officer, Memari- 150000 150000 100 Yes Debipur G.P 2ns phase. 2017 Wanting I P.S.

Executive Reconatn of Baggoria F.P. School of 2016 - Report 26 1425/DP 11/05/2017 108000 Officer, Memari- 108000 108000 100 Yes Debipur G.P 3rd phase 2017 Wanting I P.S.

Executive Constn of Patient Waiting Shed at 2016 - Report 27 C-1742/DP 19/06/2017 350000 Officer, Memari- 350000 350000 100 Yes Memari Rural Hospital OPD Building 2017 Wanting I P.S.

Constn of Patient Waiting Shed at Executive 2016 - Report 28 Memari Rural Hospital Emergency C-1742/DP 19/06/2017 250000 Officer, Memari- 250000 250000 100 Yes 2017 Wanting Building I P.S.

Total 6000000 5961619 5961619

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 29 Memari- I and Kenna , Mouza- 2207/DP 04/08/2017 890000 (Social Sector), 849856 849856 100 Yes 2018 Wanting Chamardighi (Plot. No. 3842 Jl 139) Burdwan.

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 30 Memari- I and Amadpur (Jl-128, 2207/DP 04/08/2017 890000 (Social Sector), 849855 849855 100 Yes 2018 Wanting Dag-467) Burdwan. 78 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status Constn. of Baitarani scheme at Exe. Engg. Memari- I and Shanui Mouza, 2017 - PWD (Social Report 31 2207/DP 04/08/2017 890000 849856 849856 100 Yes Shanui Binoypally, Jogomaya (Jl- 2018 Sector), Wanting 133, plot 1407 Burdwan. Building Repair and maitn of Executive 2017 - Report 32 Memari V.M. Institution for 3288/DP 13/12/2017 300000 Officer, 300000 300000 100 Yes 2018 Wanting Quasquicenteunial Celebration Memari- I P.S. National Small Inst of Solar Light StreetLED 2017 - Industries Report 33 Based Lumiaries SPV ModelNos of 43/DP 05/01/2018 660000 660000 660000 100 Yes 2018 Corporation Wanting Thirty Ltd. Constn of wooden Guard Wall Executive 2017 - Report 34 Mobarakpur Girls Junior High 972/DP 22/05/2018 200000 Officer, 200000 200000 100 Yes 2018 Wanting School Memari- I P.S. Executive Constn of Nimo Samsan Shed at 2017 - Report 35 972/DP 22/05/2018 200000 Officer, 200000 200000 100 Yes Nimo I G.P.under Memari I G.P. 2018 Wanting Memari- I P.S. Kendriya Inst. of Solar Street Light 12 Watt BhandarB-I 2017 - Report 36 Led Based Lumiaries SPV Model 1401/DP 30/07/2018 1435140 Shyamali 1435140 1435140 100 Yes 2018 Wanting under Mamari-I and II Housing state, Kolkata District Constn. of changing room including 2017 - Report 37 3918/DP 23/10/2019 150000 Magistrate, 148125 148125 100 No sitting bench at Hatpukur Shan ghat 2018 Wanting Burdwan Total 5615140 5492832 5492832 79 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn. of concrete road of Data Executive 2018 - Report 38 Rouza at Nawhati of Kuchut G.P. 2317/DP 12/10/2018 350000 Officer, Memari- 350000 350000 100 Yes 2019 Wanting within Memari-II P.S. II P.S. Constn. of Patient shed Paharhati Executive 2018 - Report 39 Hospital at Kuchut G.P. under 2317/DP 12/10/2018 500000 Officer, Memari- 500000 500000 100 Yes 2019 Wanting Memari-II P.S. II P.S. Constn. of culvert at Borowa near Executive 2018 - Report 40 Bhagar Site at Satgachia-II G.P. 2317/DP 12/10/2018 250000 Officer, Memari- 250000 250000 100 Yes 2019 Wanting within Memari-II P.S. II P.S. Kendriya AC High Mast Tower Luminaries 90 BhandarB-I 2018 - Report 41 watt Led Base Six Arm Bracket and 2460/DP 14/11/2018 200000 Shyamali 200000 200000 100 Yes 2019 Wanting Octagonal pole Housing state,Kolkata Constn. of Cycle shed at Executive 2018 - Report 42 Mohinimohan Basu School at 3297/DP 26/12/2018 300000 Officer, Memari- 300000 300000 100 Yes 2019 Wanting Durgapur G.P. under memari-I P.S. I P.S. Constn. of Cycle shed at Executive 2018 - Report 43 Radhakantapur School at Gantar-II 3297/DP 26/12/2018 300000 Officer, Memari- 299700 299700 100 Yes 2019 Wanting G.P. under Memari-I P.S. I P.S.

80 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn. of Auditoriam at Kanaidanga Executive 2018 - Report 44 under Daluibazer -II G.P. within 523/DP 18/02/2019 300000 Officer, Memari- 299880 299880 100 Yes 2019 Wanting Memari-I P.S. I P.S. Purchase of Dead Body Carrier Van 2018 - Prodhan, Bagila Report 45 under Bagila G.P. under Memari-I 2307/DP 29/08/2019 450000 450000 450000 100 Yes 2019 Gram Panchayat Wanting P.S. Total 2650000 2649580 2649580 Grand Total 14265140 14104031 14104031

81 ONGOING SCHEMES

82 NARGIS BEGUM, HON'BLE MLA 265 MEMARI A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. of RCC shed over the stage District Work is ongoing roof 2017 - 1 at Khanro Yubak Sangha under 4270/DP 27/11/2019 300000 Magistrate, 298500 0 0 No will custed on 2018 Memari Muty. Burdwan 13/02/2020

Constn. of in front of college campus District Work in progress UC 2017 - 2 of Memari College under Memari 730/DP 25/02/2020 148875 Magistrate, 148875 0 0 No will be submitted 2018 Muty. Burdwan soon. Total 448875 447375 0

Supply Transportation and National Small 2018 - 100% UC submitted 3 Installation of AC High Mast Tower 406/DP 05/02/2020 200000 Industries 200000 150000 75 No 2019 on 28/02/2020 at Memari P.S. under Memari Muty. Corporation Ltd.

Supply Transportation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 4 406/DP 05/02/2020 200000 Industries 200000 150000 75 No at Baneswarpur Samabai Samiti 2019 on 28/02/2020 Corporation Ltd. Bazar under Satgachia-II G.P. Supply Transportation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 5 446/DP 05/02/2020 200000 Industries 200000 150000 75 No at Gantar Busstand beside Najrul 2019 on 28/02/2020 Corporation Ltd. Smriti Sangha under Kuchut G.P.

83 NARGIS BEGUM, HON'BLE MLA 265 MEMARI A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 6 446/DP 05/02/2020 200000 Industries 200000 150000 75 No at Palla ACN high School stand 2019 on 28/02/2020 Corporation Ltd. under Daluibazar-II G.P.

Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 7 446/DP 05/02/2020 200000 Industries 200000 150000 75 No at Belut primary School Busstand 2019 on 28/02/2020 Corporation Ltd. under Daluibazar-I G.P.

Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 8 446/DP 05/02/2020 200000 Industries 200000 150000 75 No at Baror Kalitala Busstand under 2019 on 28/02/2020 Corporation Ltd. Durgapur G.P.

Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 9 446/DP 05/02/2020 200000 Industries 200000 150000 75 No at Mobarakpur DVC par under 2019 on 28/02/2020 Corporation Ltd. Debipur G.P.

Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 100% UC submitted 10 446/DP 05/02/2020 200000 Industries 200000 150000 75 No at Gantar Kachari Road Busstand 2019 on 28/02/2020 Corporation Ltd. under Gope Gantar-I G.P. 84 NARGIS BEGUM, HON'BLE MLA 265 MEMARI A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Supply Transporation and National Small 100% UC Installation of AC High Mast Tower 2018 - 11 446/DP 05/02/2020 200000 Industries 200000 150000 75 No submitted on at Kenna Bus Stand under Nimo-II 2019 Corporation Ltd. 28/02/2020 G.P. Supply Transporation and National Small 100% UC Installation of AC High Mast Tower 2018 - 12 446/DP 05/02/2020 200000 Industries 200000 150000 75 No submitted on at Nishanka Bazar under Amadpur 2019 Corporation Ltd. 28/02/2020 G.P. Total 2000000 2000000 1500000 Grand Total 2448875 2447375 1500000

85 Hon’ble M.L.A Shri Nisith Kumar Malik MLA 266-Bardhaman Uttar (SC) A.C.

86 COMPLETED SCHEMES

87 NISITH KUMAR MALIK, HON'BLE MLA 266-Bardhaman Uttar (SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Executive Purchase an Ambulance for 2016 - Report 1 1975/DP 01/09/2016 520467 Officer, 520467 520467 100 Yes Gobindapur G.P. 2017 Wanting Burdwan- II P.S. PEC LTD, 55, Constn of 13 PC Solar Street Light 2016 - Chowringhee Report 2 2901/DP 08/12/2016 325000 325000 325000 100 Yes five nos of G.P. 2017 Road, Kolkata- Wanting 71. PEC LTD, 55, Constn of 18 PC Solar Street Light 2016 - Chowringhee Report 3 2901/DP 08/12/2016 450000 450000 450000 100 Yes three nos of G.P. 2017 Road, Kolkata- Wanting 71. PEC LTD, 55, Constn of 17 PC Solar Street Light 2016 - Chowringhee Report 4 2901/DP 08/12/2016 425000 425000 425000 100 Yes four nos of G.P. 2017 Road, Kolkata- Wanting 71. Executive Constn of Busstand at Bhandardihi of 2016 - Report 5 2969/DP 19/12/2016 300000 Officer, 294467 294467 100 Yes Bondul-I G.P. 2017 Wanting Burdwan- I P.S.

Executive Constn waiting Hall at Haldi Bus 2016 - Report 6 2969/DP 19/12/2016 300000 Officer, 263000 263000 100 Yes Stand of Bhagar G.P 2017 Wanting Burdwan- I P.S. 88 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Electric High Mast at 2016 - Executive Officer, Report 7 2969/DP 19/12/2016 200000 198000 198000 100 Yes Bhandardihi of Bondul G.P. 2017 Burdwan- I P.S. Wanting

Constn of Burning Ghat at Talit 2016 - Executive Officer, Report 8 2969/DP 19/12/2016 350000 267540 267540 100 Yes Daspara of Bhagar G.P. 2017 Burdwan- I P.S. Wanting

Constn of Liabrary grant of 2016 - Executive Officer, Report 9 435/DP 08/02/2017 50000 50000 50000 100 Yes Krishnapur High School 2017 Burdwan- I P.S. Wanting

Constn of Waiting Hall at Alampur 2016 - Executive Officer, Report 10 655/DP 01/03/2017 300000 274351 274351 100 Yes Bus Stand of Bhagar-I 2017 Burdwan- I P.S. Wanting

Library Grant of Vidyasagar Uchha 2016 - Executive Officer, Report 11 704/DP 07/03/2017 50000 50000 50000 100 Yes Vidyalaya of Saraitikor G.P. 2017 Burdwan- I P.S. Wanting

Constn of Electric High Mast in front 2016 - Executive Officer, Report 12 945/DP 27/03/2017 200000 199500 199500 100 Yes of Nabastha I-G.P. 2017 Burdwan- II P.S. Wanting 89 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Busstand at Raipur of 2016 - Executive Officer, Report 13 1243/DP 21/04/2017 300000 272771 272771 100 Yes Gobindapur g.P. 2017 Burdwan- II P.S. Wanting

Constn of Burining Ghat waiting 2016 - Executive Officer, Report 14 Shed at Amirpur of baikunthapur 1243/DP 21/04/2017 170000 170000 170000 100 Yes 2017 Burdwan- II P.S. Wanting G.P.

Constn of Mukta Mancha at Nandur 2016 - Executive Officer, Report 15 Vivekananda F.P. School of 1358/DP 04/05/2017 100000 100000 100000 100 Yes 2017 Burdwan- II P.S. Wanting Baikunthapur

Purchase an Ambulance for Rayan - 2016 - Executive Officer, Report 16 2531/DP 13/09/2017 595204 595204 595204 100 Yes II G.P. 2017 Burdwan- I P.S. Wanting

Four PC Computer for Barsul CDP 2016 - Executive Officer, Report 17 3047/DP 21/11/2017 140000 140000 140000 100 Yes High School of Borsul II G.P. 2017 Burdwan- II P.S. Wanting

Constn of Green Room for 2016 - Executive Officer, Report 18 Community Hall Karanda of C-968/DP 22/05/2018 319834 318051 318051 100 Yes 2017 Burdwan- II P.S. Wanting Nabastha G.P.

90 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Community Hall Karanda 2016 - Executive Officer, Report 19 C-968/DP 22/05/2018 452493 450292 450292 100 Yes Of Nabastha G.P.under Burdwan-II 2017 Burdwan- II P.S. Wanting

Total 5547998 5363643 5363643

Constn of Boitarani scheme at Exe. Engg. PWD 2017 - Report 20 Bhandardihi, Jl. No. 36 of Bondul 1462/DP 17/05/2017 890000 (Social Sector), 857571 857571 100 Yes 2018 Wanting G.P. Burdwan.

Constn of Boitarani scheme at Exe. Engg. PWD 2017 - Report 21 Gopalpur, Plot No. 1713 of Bhagar 1462/DP 17/05/2017 890000 (Social Sector), 857572 857572 100 Yes 2018 Wanting G.P. Burdwan.

Exe. Engg. PWD Constn of Boitarani scheme at 2017 - Report 22 1462/DP 17/05/2017 890000 (Social Sector), 857571 857571 100 Yes Nabastha, Jl. No. 31 Plot No. 1950 2018 Wanting Burdwan.

Exe. Engg. PWD Constn of Boitarani scheme at 2017 - Report 23 1462/DP 17/05/2017 890000 (Social Sector), 857571 857571 100 Yes Chandul, Jl. No. 31 Plot No. 851 2018 Wanting Burdwan.

Library Grant of Sadhanpur 2017 - Executive Officer, Report 24 Vivekananda High School under 3356/DP 26/12/2017 50000 50000 50000 100 Yes 2018 Burdwan- I P.S. Wanting Saraitikar 91 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Electric High Mast Light at 2017 - Executive Officer, Report 25 Dewandighi More of Saraitikor 294/DP 09/02/2018 350000 350000 350000 100 Yes 2018 Burdwan- I P.S. Wanting Gram

Purchase of 25 Nos Electric Light 2017 - Executive Officer, 26 731/DP 05/04/2018 400000 397351 397351 100 Yes Led Based at Atagarh Bazar 2018 Burdwan- II P.S.

Purchase of 12.50 Mtr Electric Light 2017 - Executive Officer, Report 27 Led Based at Saktigarh Police 731/DP 05/04/2018 430000 426622 426622 100 Yes 2018 Burdwan- II P.S. Wanting Station to Barsul-I G.P.

Purchase of 25 Nos Electric Light 2017 - Executive Officer, Report 28 Led Based at Kestopur More to 731/DP 05/04/2018 400000 397462 397462 100 Yes 2018 Burdwan- II P.S. Wanting cannel Bridge

Constn of High School Main gate at 2017 - Executive Officer, Report 29 1400/DP 30/07/2018 100000 100000 100000 100 Yes Bondul-II G.P. 2018 Burdwan- II P.S. Wanting

Colouring of Wall of School 2017 - Executive Officer, Report 30 1478/DP 09/08/2018 400000 400000 400000 100 Yes Building at Saddaya High School 2018 Burdwan- II P.S. Wanting

Instn of 10 Mtr Electric Mini High 2017 - Executive Officer, Report 31 Mast Light at Jagadabad Shibtala 1819/DP 14/08/2018 200000 200000 200000 100 Yes 2018 Burdwan- I P.S. Wanting ofBhagar -I G.P. 92 UC Sl. Sanction Date of Amount Amount Amount Physical Handed Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Over Status ed

Constn. of Mid day meal shade at Kanthalgachi FP High School under 2018 - Executive Officer, Report 31 560/DP 20/02/2019 200000 199707 199707 100 Yes Baikunthapur-II GP. within 2019 Burdwan- II P.S. Wanting Burdwan-II P.S. Installation of 10 mtr.High Mast Light (Led Based) at Chandsona 2018 - Executive Officer, Report 32 560/DP 20/02/2019 200000 200000 200000 100 Yes under Baikunthapur-II G.P. within 2019 Burdwan- II P.S. Wanting Burdwan-II P.S. Constn. and purchase of 16 nos. Electric Street Light (Led Based) 2018 - Executive Officer, Report 33 near Gobindapur Kalitala Police 560/DP 20/02/2019 300000 280860 280860 100 Yes 2019 Burdwan- II P.S. Wanting Phanri under Gobindapur GP. within Burdwan-II P.S. Total 700000 680567 680567 Grand Total 12137998 11795930 11795930

93 ONGOING SCHEMES

94 NISITH KUMAR MALIK, HON'BLE MLA 266-Bardhaman Uttar (SC) A.C.

Physical UC Sl. Sanction Date of Amount Executing Amount Amount Name of the Scheme Year Progres Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized s ed

Executive Work Completed. Constn of Electric High Mast at 2016 - 1 945/DP 27/03/2017 200000 Officer, 200000 199500 95 No Balance fund will be Swastipally of Baikunthapur 2017 Burdwan- II P.S. refunded. Total 200000 200000 199500 Renovation and upgradation of Executive Community centre at Ullhas under 2018 - U.C. will be 2 4335/DP 29/11/2019 300000 Officer, 225000 225000 75 Yes Baikunthapur-II G.P. within 2019 submitted shortly. Burdwan- II P.S. Burdwan-II P.S. Constn. of Harinarayanpur Executive 2018 - Work not started site 3 Bidyasagar Culvert under Saraitikar 451/DP 05/02/2020 300000 Officer, 184433 0 0 No 2019 problem. G.P. within Burdwan-I P.S. Burdwan- I P.S. West Bengal Constn. of purchase 10 mtr. mini 2018 - Agro Industries Work started. 50% 4 high mast light at Dangapara front of 1022/DP 20/03/2020 299700 224775 0 0 No 2019 Corporation Ltd. completed Dangapara Pry. School 23 B West Bengal Mini High Mast Light at Balisha 2018 - Agro Industries Work started. 50% 5 1023/DP 20/03/2020 299700 224775 0 0 No Masjidtala, Bandul-I G.P. 2019 Corporation Ltd. completed 23 B West Bengal Mini High Mast Light near Jyotipally 2018 - Agro Industries Work started. 50% 6 1023/DP 20/03/2020 299700 224775 0 0 No football ground, Baikuntapur-I G.P. 2019 Corporation Ltd. completed 23 B 95 NISITH KUMAR MALIK, HON'BLE MLA 266-Bardhaman Uttar (SC) A.C.

Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess West Bengal Mini High Mast Light near Kastha 2018 - Agro Industries Work started. 50% 7 1023/DP 20/03/2020 299700 224775 0 0 No Kurumba Shibtala, Bandul-II G.P. 2019 Corporation Ltd. completed 23 B Total 1798800 1308533 225000 Grand Total 1998800 1508533 424500

96 Hon’ble M.L.A. Shri Subhash Mondal MLA 267 BHATAR A.C.

97 COMPLETED SCHEMES

98 SUBHAS MONDAL, HON'BLE MLA 267 BHATAR A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Executive Constn of Mouners waiting Room at 2016 - Report 1 3007/DP 22/12/2016 300000 Officer, 300000 300000 100 Yes Burning Ghat of Khetia G.P. 2017 Wanting Burdwan- I P.S.

Executive Instn of High Mast Light at 2016 - Report 2 3007/DP 22/12/2016 300000 Officer, 300000 300000 100 Yes Hospital of Kurmun G.P. 2017 Wanting Burdwan- I P.S.

Executive Constn of Kurmun Girls School 2016 - Report 3 3007/DP 22/12/2016 300000 Officer, 300000 300000 100 Yes Building Boundary Wall 2017 Wanting Burdwan- I P.S. Building boundary wall between Executive Kherur Chhadni Khetronath Uchha 2016 - Report 4 3072/DP 28/12/2016 200000 Officer, Bhatar 200000 200000 100 Yes Bidlaya andKhetronath Prathomik 2017 Wanting P.S. Bidyalaya of Amru G.P. Constn of Mourners waiting room at Executive 2016 - Report 5 Burning ghat of Moragore Ghat 3072/DP 28/12/2016 250000 Officer, Bhatar 227995 227955 100 No 2017 Wanting Shilakote village P.S.

Executive Constn of Waiting Shelter at Bus 2016 - Report 6 206/DP 17/01/2017 300000 Officer, Bhatar 204576 204576 100 Yes Stand at Mahata G.P. 2017 Wanting P.S. 99 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Passenger of Waiting Shelter at Bus 2016 - Executive Officer, Report 7 206/DP 17/01/2017 300000 220541 220541 100 Yes Stand of Barabelun Daspara 2017 Bhatar P.S. Wanting

Passenger waiting shelter at Bus Stand 2016 - Executive Officer, Report 8 206/DP 17/01/2017 300000 197152 197152 100 Yes of Muratipur 2017 Bhatar P.S. Wanting

Constn of Bhamsore Gram Jr. High 2016 - Executive Officer, Report 9 School building Class Room of Bhatar 263/DP 20/01/2017 400000 400000 400000 100 Yes 2017 Bhatar P.S. Wanting G.P.

Constn of Boundary Wall with gate at 2016 - Executive Officer, Report 10 263/DP 20/01/2017 250000 187254 187254 100 Yes Health Centre at Bhnatakul village 2017 Bhatar P.S. Wanting

Constn of Mouners waiting Room at 2016 - Executive Officer, Report 11 700/DP 07/03/2017 300000 205484 205484 100 Yes Burning Ghat of Shalkuni Adibasipara 2017 Bhatar P.S. Wanting

Constn of Furnace and shed at Burning 2016 - Executive Officer, Report 12 700/DP 07/03/2017 300000 245080 245080 100 Yes Ghat at Bonpas Kamarpara 2017 Bhatar P.S. Wanting

100 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Executive Constn of Mouners waiting Room at 2016 - Report 13 700/DP 07/03/2017 300000 Officer, Bhatar 300000 300000 100 Yes Burning Ghat of Arur Gram 2017 Wanting P.S.

Executive Constn of Mouners waiting Room at 2016 - Report 14 700/DP 07/03/2017 300000 Officer, Bhatar 298105 298105 100 Yes Burning Ghat of Sunur Gram 2017 Wanting P.S.

Passenger of waitingshelter at Executive 2016 - Report 15 Busstand including Toilet of 700/DP 07/03/2017 250000 Officer, Bhatar 200631 200631 100 Yes 2017 Wanting DebpurShed P.S.

Executive Constn of Mouners waiting Room at 2016 - Report 16 700/DP 07/03/2017 300000 Officer, Bhatar 289497 289497 100 Yes Burning Ghat at Patuna village 2017 Wanting P.S.

Passenger Waiting Shelterat Executive 2016 - Report 17 Busstandof Kurmun Gram under 997/DP 30/03/2017 250000 Officer, Bhatar 177448 177448 100 Yes 2017 Wanting Bhatar P.S.

Constn. of burning furnance at Executive 2016 - Report 18 burning station of Nasigram C- 1588/DP 05/06/2017 300000 Officer, Bhatar 300000 300000 100 Yes 2017 Wanting Barabelun of Barbelun - II G.P. P.S.

Total 5200000 4553763 4553723

101 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Executive Constn of one new Class Room at 2017 - Report 19 2681/DP 13/10/2017 1200000 Officer, Bhatar 1200000 1200000 100 Yes Dasarathi Hazra Memorial College 2018 Wanting P.S. Exe. Engg. Constn. of Baitarani scheme at 2017 - PWD (Social Report 20 Bhatar Development Block and 2827/DP 06/11/2017 890000 845011 845012 100 No 2018 Sector), Wanting Orgram (Jl-011, Plot-8052) Burdwan. Exe. Engg. Constn. of Baitarani scheme at 2017 - PWD (Social Report 21 Bhatar Development Block and Palar 2827/DP 06/11/2017 890000 845011 845011 100 Yes 2018 Sector), Wanting (Jl. no. 063, Plot-2573) Burdwan.

Executive Constn of Cycle Stand Banpas 2017 - Report 22 771/DP 10/04/2018 350000 Officer, Bhatar 294156 294156 100 Yes Sikhsha Niketan under Banpas G.P. 2018 Wanting P.S.

Constn of New Passenger Waiting Executive 2017 - Report 23 Shelter at Busstop Rampur under 771/DP 10/04/2018 300000 Officer, Bhatar 260857 260857 100 Yes 2018 Wanting Aruar G.P. P.S.

102 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of burning furnance and Executive 2017 - Report 24 waiting room at the burning station at 771/DP 10/04/2018 500000 Officer, Bhatar 413980 413980 100 Yes 2018 Wanting Muraripur P.S. Constn. of new passenger waiting Executive shelter at bus stop Ramchandrapur 2017 - Report 25 2496/DP 15/11/2018 300000 Officer, Bhatar 215828 215828 100 Yes under Mahata G.P. within Bhatar 2018 Wanting P.S. P.S. Total 4430000 4074843 4074844 Constn. of Boundary wall at Executive Tulsidanga Burning Station (Plot No. 2018 - Report 26 1798/DP 22/07/2019 300000 Officer, Bhatar 251070 251070 Yes 117, J.L. no. 79, Tulsidanga) under 2019 Wanting P.S. Bolgona G.P. within Bhatar P.S. Total 300000 251070 251070 Grand Total 9930000 8879676 8879637

103 ONGOING SCHEMES

104 SUBHAS MONDAL, HON'BLE MLA 267 BHATAR A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Installation of X ray machine at West Bengal 2016 - Hard copy to be 1 Bhatar Hospital of Bhatar G.P. under 2294/DP 11/10/2018 567368 Medical Sevices 425526 0 0 No 2017 contact to at PV Dept. Bhatar P.S. Corporation Ltd. Total 567368 425526 0

Constn of New Passenger Waiting 2017 - Executive Officer, 2 Shelter at Busstop Bhubaneswarpur 771/DP 10/04/2018 300000 300000 218713 95 No Payment not made 2018 Bhatar P.S. Bus Stand under Barabelun G.P.

Constn. of burning furnace and waiting room at the burning station at 2017 - Executive Officer, 100% Completed. 3 771/DP 10/04/2018 500000 440886 375000 75 No Kharjuli of Khetia G.P. under 2018 Burdwan- I P.S. Payment not made Burdwan -I P.S.

Constn. of new passenger waiting 100% completed. 2017 - Executive Officer, 4 shelter at bus stop kurmun under 2285/DP 11/10/2018 350000 263000 249982 92 No Payment made rest 2018 Burdwan- I P.S. Kurmun G.P. within Burdwan-I P.S. amount refunded.

Constn. of new Class room at 2017 - Executive Officer, 5 Selrnda F.P. School at Bolgona G.P. 2496/DP 15/11/2018 400000 331960 200000 50 No Work completed 90% 2018 Bhatar P.S. under Bhatar P.S. Total 1550000 1335846 1043695 105 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Constn. of new passenger waiting Executive shelter at bus stop Nasigram Daspara 2018 - Land problem. 6 49//DP 04/01/2019 300000 Officer, Bhatar 225000 0 0 No More near Gramin Bank under 2019 Work not started. P.S. Barabelun-II G.P. within Bhatar P.S. Constn. of new passenger waiting shelter 100% Physically Executive at bus stop (Plot No. 262 Sodkhali 2018 - Completed. 7 616/DP 22/02/2019 400000 Officer, Bhatar 300000 300000 0 No Bhatar College under Arurar G.P. within 2019 Payment not P.S. Bhatar P.S. made. Constn. of new class room Arurar Executive 2018 - U.C. will be 8 BMDP Institution under Aurar within 1449/DP 18/06/2019 500000 Officer, Bhatar 421500 375000 0 No 2019 submitted shortly. Bhatar P.S. P.S. Constn. of waiting hall at Gramdihi Executive Burning Station (Plot No.-530 Gramdihi) 2018 - Work in progress 9 2333/DP 30/08/2019 300000 Officer, Bhatar 225000 22500 0 No under Sahebgunj-II G.P. within Bhatar 2019 60% completed. P.S. P.S. Constn. of Burning Furnace at Aimapara Executive Das para Burning Station (Plot No. 3213, 2018 - 10 2333/DP 30/08/2019 200000 Officer, Bhatar 150000 150000 0 No Work in progress. Aimapara, Das para) under Sahebgung-II 2019 P.S. G.P. within Bhatar P.S.

Constn. of Passenger waiting at Bus Executive 2018 - Work not started, 11 Stand at Jatradighi under Aruar G.P. 059/DP 07/01/2020 350000 Officer, Bhatar 262500 0 0 No 2019 work order given. within Bhatar P.S. P.S.

106 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Executive Constn of Stage of Bhatar College under 2018 - Work not started, 12 432/DP 04/02/2020 376150 Officer, Bhatar 282112 0 0 No Bhatar G.P. within Bhatar P.S. 2019 work order given. P.S.

Total 2426150 1866112 1050000

Grand Total 4543518 3627484 2093695

107 Hon’ble M.L.A. Shri Swapan Debnath 268 PURBASTHALI DAKSHIN A.C.

108 COMPLETED SCHEMES

109 SWAPAN DEBNATH, HON'BLE MLA 268 PURBASTHALI DAKSHIN A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Waiting Shed at Vill. 2016 - Executive Officer, Report 1 2630/DP 10/11/2016 400000 400000 400000 100 Yes Isabpur of Sultan G.P. 2017 Kalna- I P.S. Wanting

Constn of waiting Shed at village 2016 - Executive Officer, Report 2 2630/DP 10/11/2016 400000 400000 400000 100 Yes Durgapur of Nandai G.P. 2017 Kalna- I P.S. Wanting

Constn of Waiting Shed at Village 2016 - Executive Officer, Report 3 2630/DP 10/11/2016 200000 200000 200000 100 Yes Kasimpur of Sultanpur G.P. 2017 Kalna- I P.S. Wanting

Constn of waiting shed at village 2016 - Executive Officer, Report 4 2630/DP 10/11/2016 600000 538178 538178 100 Yes SandalpurAtgoria of Simlon G.P. 2017 Kalna- I P.S. Wanting

Sinking Tubewell with 1 H.P. Motor 2016 - Executive Officer, Report 5 and Tank for supplying drinking 2630/DP 10/11/2016 100000 100000 100000 100 Yes 2017 Kalna- I P.S. Wanting waterat vill Bhatra of Sultanpur G.P. Sinking Tubewell with 1 H.P. Motor 2016 - Executive Officer, Report 6 and Tank for supplying drinking 2630/DP 10/11/2016 100000 100000 100000 100 Yes 2017 Kalna- I P.S. Wanting waterat vill Kasirampur

Constn of Bathing Ghat at 2016 - Executive Officer, Report 7 2630/DP 10/11/2016 200000 160218 160218 100 Yes Nagragachi Uttarpara of Nandai G.P. 2017 Kalna- I P.S. Wanting 110 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of a Community Shed at 2016 - Executive Officer, Report 8 3092/DP 29/12/2016 140000 140000 140000 100 Yes Baghandanga vill begpur G.P. 2017 Kalna- I P.S. Wanting

Constn of Bathing Ghat at Kharama 2016 - Executive Officer, Report 9 3092/DP 29/12/2016 130000 130000 130000 100 Yes Pond vill Choughoria of Begpur G.P. 2017 Kalna- I P.S. Wanting

Constn of Bathing Ghat at Talbona 2016 - Executive Officer, Report 10 3092/DP 29/12/2016 130000 130000 130000 100 Yes pond vill Simalgoria of Begpur G.P. 2017 Kalna- I P.S. Wanting

Infrastructual Development of 2016 - Executive Officer, Report 11 152/DP 11/01/2017 200000 200000 200000 100 Yes Kulora Graveyard of Begpur G.P. 2017 Kalna- I P.S. Wanting

Infrastructual Development of 2016 - Executive Officer, Report 12 152/DP 11/01/2017 200000 200000 200000 100 Yes Fakirdanga Gravyard of Begpur G.P. 2017 Kalna- I P.S. Wanting

Infrastructual Development of 2016 - Executive Officer, Report 13 Kapurdanga Graveyard of Begpur 152/DP 11/01/2017 200000 200000 200000 100 Yes 2017 Kalna- I P.S. Wanting G.P.

Constn of addl work of 2016 - Executive Officer, Report 14 Flood Shelter Adjacent to 891/DP 22/03/2017 167000 167000 167000 100 Yes 2017 Purbasthali- I P.S. Wanting Police Station 111 UC Sl. Sanction Date of Amount Amount Amount Physical Present Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

Constn of waiting Shed at Duley 2016 - Executive Officer, Report 15 891/DP 22/03/2017 33000 32852 32852 100 Yes Para of Samudragarh G.P. 2017 Purbasthali- I P.S. Wanting

Setting of Solar street System at Babulitala Bazar of Sultanpur,Kalna 2016 - Executive Officer, Report 16 996/DP 30/03/2017 500000 500000 500000 100 Yes RoadBurdwan Road Bitra Road 2017 Kalna- I P.S. Wanting Memari Road Constn of waiting Shed at 2016 - Executive Officer, Report 17 Dakshinbati Samudragarh under 996/DP 30/03/2017 300000 294273 294273 100 Yes 2017 Purbasthali- I P.S. Wanting Purbasthali

Dev. of frist Floor Class Rooms at 2016 - Executive Officer, Report 18 Bhabatarini Roy Girls High School 1630/DP 08/06/2017 500000 490000 490000 100 Yes 2017 Purbasthali- I P.S. Wanting of Srirampur

Constn of bathing Ghat at Land of 2016 - Executive Officer, Report 19 Gopal BagDag No 140 Mouza 1368/DP 23/07/2018 300000 300000 300000 100 Yes 2017 Purbasthali- I P.S. Wanting Vidyanagar of Srirampur GP

112 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed Constn of Community Room with Toilet and bathroom at vhaktibhandar 2016 - Executive Officer, Report 20 1368/DP 23/07/2018 500000 500000 500000 100 Yes Jl No. 135Mouza Srirampurkh No 2017 Purbasthali- I P.S. Wanting 2270 of srirampur GP. Constn. of Bathing Ghat beside the house of R. Biswas on Khari river at 2016 - Executive Officer, Report 21 674/DP 27/02/2019 400000 399160 399160 100 Yes Nasaratpur G.P. under Purbasthali-I 2017 Purbasthali- I P.S. Wanting P.S. Total 5700000 5581681 5581681 Renovation and upgradation of flood 2017 - C- Executive Officer, Report 22 shelter at Nasaratpur (Dag No. 204, 04/08/2017 1300000 1231876 1231876 100 Yes 2018 2198/DP Purbasthali- I P.S. Wanting 1060) Mouza - Nasaratpur, JL No. 186. Constn of Bathing Ghat at Pado 2017 - Executive Officer, Report 23 Pukurin Bhabanipur village at 2287/DP 18/08/2017 300000 300000 300000 100 Yes 2018 Kalna- I P.S. Wanting G.P. Constn of Bathing Ghat on the Bank of 2017 - Executive Officer, Report 24 Bhgirathi River at Gram Kalna of 2287/DP 18/08/2017 300000 300000 300000 100 Yes 2018 Kalna- I P.S. Wanting Dhatrigram

Constn of Waiting Shed at Chakarpur 2017 - Executive Officer, Report 25 2287/DP 18/08/2017 300000 300000 300000 100 Yes of Dhatrigram G.P. 2018 Kalna- I P.S. Wanting Constn of Concrete Road from house 2017 - Executive Officer, Report 26 of Sri S Jar towards J. Mondal Pond at 2360/DP 28/08/2017 386000 386000 386000 100 Yes 2018 Purbasthali- I P.S. Wanting Bonpukur 113 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Dev of One Childern Park within the 2017 - Executive Officer, Report 27 Block Office Campus under 3031/DP 20/11/2017 500000 486412 486412 100 Yes 2018 Purbasthali- I P.S. Wanting Purbasthali-I Constn. of Dangapara Burial Ground under Nasaratpur G.P. (Mouza- 2017 - Executive Officer, Report 28 82/DP 08/01/2019 500000 479750 479750 100 Yes Nasaratpur, Jl-186, Plot-844) under 2018 Purbasthali- I P.S. Wanting Purbasthali-I P.s. Total 3586000 3484038 3484038 Grand Total 9286000 9065719 9065719

114 ONGOING SCHEMES

115 SWAPAN DEBNATH, HON'BLE MLA 268 PURBASTHALI DAKSHIN A.C.

Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess

Constn. of new room of bright Sishu Niketan Guptipara more under 2018 - Executive Officer, 1 4520/DP 12/12/2019 480100 360075 0 0 No UC pending. Atghoria Simlon G.P. within Kalna-I 2019 Kalna- I P.S. P.S.

Constn. of a new Class room of UC submitted & Sujoti Sishu Niketan Simlon more 2018 - Executive Officer, 2 4519/DP 12/12/2019 480100 360075 0 0 No balance fund will be under Atghoria Simlon G.P. within 2019 Kalna- I P.S. refunded shortly. Kalna-I P.s.

Constn. of waiting shed at vill- 2018 - Executive Officer, Layout will be done 3 Bhaidharpara Ashramunder Begpur 4558/DP 17/12/2019 452300 339225 0 0 No 2019 Purbasthali- I P.S. on 14/02/2020 G.P. within Purbasthali-I P.S. Total 1412500 1059375 0 Work in progress Constn. of waiting shed cum Night planning work 2019 - Executive Officer, 4 Shelter with drinking water facility at 4516/DP 12/12/2019 937640 703230 0 50 No ongoing & Part UC 2020 Purbasthali- I P.S. Srirampur within Purbasthali -I P.S. will be submitted on 14/02/2020 Total 937640 703230 0 Grand Total 2350140 1762605 0 116 Hon’ble M.L.A. Shri Pradip Kumar saha MLA 269 PURBASTHALI UTTAR A.C.

117 COMPLETED SCHEMES

118 PRADIP KUMAR SAHA, HON'BLE MLA 269 PURBASTHALI UTTAR A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Concrete road from Pakhi 2016 - Executive Officer, Report 1 Mondals house to Debu Mondals 1795/DP 12/08/2016 200000 200000 200000 100 Yes 2017 Monteswar P.S. Wanting house at Pursuri village Constn of Concrete road from Manju 2016 - Executive Officer, Report 2 Dafadar house to Madhu Dafadar 1795/DP 12/08/2016 150000 150000 150000 100 Yes 2017 Monteswar P.S. Wanting house at Monadanga

Constn of Concrte road Sashtitala to 2016 - Executive Officer, Report 3 1795/DP 12/08/2016 75000 75000 75000 100 Yes Narayan Ghar at Natun Gram 2017 Monteswar P.S. Wanting

Constn of Concrete road from Sibtala 2016 - Executive Officer, Report 4 to Manasa Talaat Gulita vill of 1795/DP 12/08/2016 150000 149622 149622 100 Yes 2017 Monteswar P.S. Wanting Bamunpara G.P.

Constn of Concrete road from Masjid 2016 - Executive Officer, Report 5 1795/DP 12/08/2016 75000 75000 75000 100 Yes to Kabarsthan at Narugram 2017 Monteswar P.S. Wanting

Constn of concrete road from Simul 2016 - Executive Officer, Report 6 Majhi House to Kebal Majhis house 1795/DP 12/08/2016 200000 200000 200000 100 Yes 2017 Monteswar P.S. Wanting at Pursuri village

Constn. of concrete road from Bindu 2016 - Executive Officer, Report 7 Ghosh house to Haru Ghosh house at C- 2043/DP 07/09/2016 150000 150000 150000 100 Yes 2017 Monteswar P.S. Wanting Goalbari villlage at Mamudpur G.P 119 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Concrete Rd. from Pucca 2016 - Executive Officer, Report 8 Rd. near Madra F.P. School to P.C. 2182/DP 20/09/2016 250000 250000 250000 100 Yes 2017 Purbasthali- I P.S. Wanting das house

Constn of CC Rd. from Brahamani 2016 - Executive Officer, Report 9 2259/DP 26/09/2016 200000 178046 178046 100 Yes Tala to Amal Sammadar house 2017 Purbasthali- I P.S. Wanting

Constn of CC Road from Dwaiper 2016 - Executive Officer, Report 10 Math Primary School to B. Deys 2259/DP 26/09/2016 200000 157580 157580 100 Yes 2017 Purbasthali- I P.S. Wanting house

Constn of CC Road from Hachai Sks 2016 - Executive Officer, Report 11 house to Salamat Sks house of 2259/DP 26/09/2016 400000 400000 400000 100 Yes 2017 Purbasthali- II P.S. Wanting Masjid

Constn of CC Road from Sardanga 2016 - Executive Officer, Report 12 2259/DP 26/09/2016 200000 200000 200000 100 Yes Srikanta Das house to H.Das house 2017 Purbasthali- II P.S. Wanting

Constn of CC Road from Khanpur 2016 - Executive Officer, Report 13 Masjid to Mehar Ali Sks house of 2259/DP 26/09/2016 350000 350000 350000 100 Yes 2017 Purbasthali- II P.S. Wanting Pilla G.P.

Constn of CC Road Kasthali Bazar to 2016 - Executive Officer, Report 14 Suku Sks house near Kasthali 2259/DP 26/09/2016 400000 400000 400000 100 Yes 2017 Purbasthali- II P.S. Wanting Khalpara 120 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Executive Constn of Concrete road from 2016 - Officer, Report 15 Kuchya Jalpara to Aswathatala to M. 654/DP 01/03/2017 250000 250000 250000 100 Yes 2017 Purbasthali- I Wanting Majhi house P.S. Executive Constn of Concrete road from Pakka 2016 - Officer, Report 16 Road near Simla F.P. School to Uttar 654/DP 01/03/2017 300000 300000 300000 100 Yes 2017 Purbasthali- II Wanting Sajiara Bridge P.S. Executive Constn of Concrete road from Pakka 2016 - Officer, Report 17 654/DP 01/03/2017 300000 300000 300000 100 Yes Road to Pratima Das house 2017 Purbasthali- II Wanting P.S. Executive Constn of Concrete Road from 2016 - Officer, Report 18 Rahamattullah to Atab Sks Shop at 654/DP 01/03/2017 300000 300000 300000 100 Yes 2017 Purbasthali- II Wanting Harishpur P.S. Executive Constn of Concrete road from 2016 - Officer, Report 19 Thandu Sks house to Hamed Ali Sks 654/D{ 01/03/2017 200000 200000 200000 100 Yes 2017 Purbasthali- II Wanting house P.S. Executive Constn of Jhama Moorum road from 2016 - Officer, Report 20 Nawpara Pakka Rastato 654/DP 01/03/2017 250000 250000 250000 100 Yes 2017 Purbasthali- II Wanting Harekrishnapur F.P. School P.S. Executive Constn of Concrete road from Atul 2016 - Officer, Report 21 654/DP 01/03/2017 200000 200000 200000 100 Yes Sks house to Akai Sks house 2017 Purbasthali- II 121Wanting P.S. UC Sl. Sanction Date of Amount Amount Amount Physical Handed Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Over Status ed

Repair of Black Top road Dakshin 2016 - Executive Officer, Report 22 Ghosh Para Harimandir to 1389/DP 05/05/2017 400000 400000 400000 100 Yes 2017 Purbasthali- II P.S. Wanting Patulia G.P.

Repair of Black Top Road from 2016 - Executive Officer, Report 23 Parulia Bus Stop to Parulia Park 1389/DP 05/05/2017 250000 250000 250000 100 Yes 2017 Purbasthali- II P.S. Wanting with small culvertof Kalekhanala

Constn of atchala at Jhawdanga 2016 - Executive Officer, Report 24 1484/DP 19/05/2017 100000 100000 100000 100 Yes Dakshin Para of Jhawdanga G.P. 2017 Purbasthali- II P.S. Wanting

Constn of atchala at Jhawdanga 2016 - Executive Officer, Report 25 1484/DP 19/05/2017 100000 100000 100000 100 Yes Dutta Para of Jhawdanga G.P. 2017 Purbasthali- II P.S. Wanting

Constn of atchala at Sarishgram of 2016 - Executive Officer, Report 26 1484/DP 19/05/2017 100000 100000 100000 100 Yes Jhawdanga G.P. 2017 Purbasthali- II P.S. Wanting

Constn. of Ghat Naopara Panfala pukur with guardwall of 2016 - Executive Officer, Report 27 C-3272/DP 21/12/2018 250000 249625 249625 100 Yes Mukshimpara G.P. under 2017 Purbasthali- II P.S. Wanting Purbasthali-II P.S. Total 6000000 5934873 5934873

Constn of Concrete road Barorpara 2017 - Executive Officer, Report 28 2570/DP 18/09/2017 200000 200000 200000 100 Yes village of Mukshimpara 2018 Purbasthali- II P.S. 122Wanting UC Sl. Sanction Date of Amount Amount Amount Physical Handed Name of the Scheme Year Executing Agency Submitte No. Order No Sanction Sanction Released Utilized Progress Over Status d

Constn of Concrete road Paschim 2017 - Executive Officer, Report 29 Tamaghata from J.Krtaniya houseT. 2570/DP 18/09/2017 175000 175000 175000 100 Yes 2018 Purbasthali- II P.S. Wanting Sarkar house of Majda G.P.

Constn of Drain from Saper Khans 2017 - Executive Officer, Report 30 house to Surat Alis house of 2570/DP 18/09/2017 200000 197635 197635 100 Yes 2018 Purbasthali- II P.S. Wanting Purbasthali house

Constn of Purba Atpara Mooram 2017 - Executive Officer, Report 31 Road by Jhama Bads and moorum 2570/DP 18/09/2017 250000 247491 247491 100 Yes 2018 Purbasthali- II P.S. Wanting Majhida G.P.

Constn of concrete road from M. Sks 2017 - Executive Officer, Report 32 house to s. Sks house of Purbasthali 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. Wanting G.P.

Constn of Concrete road from K. 2017 - Executive Officer, Report 33 2570/DP 18/09/2017 125000 125000 125000 100 Yes Biswas house to S. Mondal house 2018 Purbasthali- II P.S. Wanting

Constn of Concrete road from G. 2017 - Executive Officer, Report 34 Mondals house to Durga Mandap of 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. Wanting Mukshimpara

Constn of concrete road from Fakir 2017 - Executive Officer, Report 35 2570/DP 18/09/2017 200000 200000 200000 100 Yes Sks house to Ekai Sks house 2018 Purbasthali- II P.S. 123Wanting Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of concrete road from 2017 - Executive Officer, Report 36 Bakultala to Natun Laxmipur 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. Wanting Majhida

Constn of Concrete road Kaibati 2017 - Executive Officer, Report 37 Dhalai Panchkorais Banshtala 2570/dp 18/09/2017 250000 250000 250000 100 Yes 2018 Purbasthali- II P.S. Wanting towards Makshimpara

Constn of Concrete road from Dwan 2017 - Executive Officer, Report 38 High School to village of 2824/DP 06/11/2017 100000 100000 100000 100 Yes 2018 Monteswar P.S. Wanting G.P.

Constn of Concrete Drain from 2017 - Executive Officer, Report 39 Golam Mortajas Khamar house to 2824/DP 06/11/2017 200000 200000 200000 100 Yes 2018 Monteswar P.S. Wanting near Kandar of Putsuri G.P.

Constn of Concrete Road from near 2017 - Executive Officer, Report 40 Joy Ghosh house to Annapurnatala of 2824/DP 06/11/2017 300000 288298 288298 100 Yes 2018 Monteswar P.S. Wanting Mamudpur G.P.

Constn of concrete road from 2017 - Executive Officer, Report 41 Mujaharnagar Masjid to ICDS 2824/DP 06/11/2017 100000 100000 100000 100 Yes 2018 Monteswar P.S. Wanting Centre of Putsuri G.P.

Constn of Concrete Road from 2017 - Executive Officer, Report 42 Samashpur Jogadhatala to Milan 2824/DP 06/11/2017 150000 143877 143877 100 Yes 2018 Monteswar P.S. Wanting Mondal house of Bamunpara G.P. 124 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Over Status ed

Constn of Concrete road from 2017 - Executive Officer, Report 43 Sudpur U. Ghosh house to R. Das 3066/DP 23/11/2017 200000 200000 200000 100 Yes 2018 Purbasthali- I P.S. Wanting house of Dogachia

Constn of Concrete Road from 2017 - Executive Officer, Report 44 Bhandartikuri G,Debnath house to 3066/DP 23/11/2017 150000 149925 149925 100 Yes 2018 Purbasthali- I P.S. Wanting Ganga Ghat Road of Jahannagar

Constn of Concrete road from Madra 2017 - Executive Officer, Report 45 R. Mazumdar house to moram road 3066/DP 23/11/2017 75000 75000 75000 100 Yes 2018 Purbasthali- I P.S. Wanting of Dogachia G.P.

Constn of Concrete road from 2017 - Executive Officer, Report 46 Golahat G.Kar house to R. Debnath 3066/DP 23/11/2017 100000 99920 99920 100 Yes 2018 Purbasthali- I P.S. Wanting house of Jahanagar

Constn of Concrete Road from 2017 - Executive Officer, Report 47 behind of A. Debnath house to 3066/DP 23/11/2017 200000 199940 199940 100 Yes 2018 Purbasthali- I P.S. Wanting Paschimpara Kirtan Math

Constn of Concrete road from 2017 - Executive Officer, Report 48 Belgram M. Das house to P. Das 3066/DP 23/11/2017 200000 200000 200000 100 Yes 2018 Purbasthali- I P.S. Wanting house of Dogachia

Executive Officer, Constn of concrete Road 2017 - Report 49 3066/DP 23/11/2017 300000 Purbasthali- II 299839 299839 100 Yes Khondekarpara of Nimodaha G.P. 2018 Wanting P.S. 125 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of Atchala at Kashipur 2017 - Executive Officer, Report 50 3066/DP 23/11/2017 200000 200000 200000 100 Yes village of Jhaodanga 2018 Purbasthali- II P.S. Wanting

Constn of Concrete Drain Singhari of 2017 - Executive Officer, Report 51 3066/DP 23/11/2017 100000 100000 100000 100 Yes Majida G.P. 2018 Purbasthali- II P.S. Wanting

Constn of Concrete Road Near G. 2017 - Executive Officer, Report 52 3066/DP 23/11/2017 175000 175000 175000 100 Yes Mukherjee Pally Palashpuli 2018 Purbasthali- II P.S. Wanting

Constn of Road from Lohana 2017 - Executive Officer, Report 53 Primary School Gate towards 3281/DP 13/12/2017 150000 150000 150000 100 Yes 2018 Monteswar P.S. Wanting Sastipukur of Bamunpara

Constn of Metal Road from 2017 - Executive Officer, Report 54 3382/DP 28/12/2017 1000000 973470 973470 100 Yes Babuidanga Purbapara to Garbitala 2018 Purbasthali- II P.S. Wanting

Constn of Atchala at Nimdaha 2017 - Executive Officer, Report 55 64/DP 09/01/2018 100000 100000 100000 100 Yes Mahishya Para of Nimdaha G.P. 2018 Purbasthali- II P.S. Wanting

Constn of Atchala Mouza 2017 - Executive Officer, Report 56 Karishnabati, Plot No. 273 of Pila 64/DP 09/01/2018 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. Wanting G.P. 126 Total 6000000 5950395 5950395 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status Constn. of concrete road from the house of Habul Mallick towards Bhasan Seikh house 2018 - Executive Officer, Report 57 677/DP 27/02/2019 300000 298050 298050 100 Yes of Faleya under Kalekhanta -I G.P. within 2019 Purbasthali- II P.S. Wanting Purbasthali-II P.S. Constn. of concrete road from Dilip Kar towards the house of Litan Das vill. under 2018 - Executive Officer, Report 58 677/DP 27/02/2019 200000 198540 198540 100 Yes Mukshimpara G.P. within Purbasthali-II 2019 Purbasthali- II P.S. Wanting P.S. Constn. of concrete road from Purba Para Durgamandir towards Bama Charan 2018 - Executive Officer, Report 59 677/DP 27/02/2019 100000 99320 99320 100 Yes Mondal house under Mukshimpara G.P. 2019 Purbasthali- II P.S. Wanting within Purbasthali-II P.S. Constn. of concrete road from the house of Dilip Bhumi towards late Binoy Bhumi 2018 - Executive Officer, Report 60 677/DP 27/02/2019 200000 199200 199200 100 Yes under Kalekkhanta-I G.P. within 2019 Purbasthali- II P.S. Wanting Purbasthali-II P.S. Constn. of concrete road from the house of Patal Seikh towards the house of 2018 - Executive Officer, Report 61 677/DP 27/02/2019 300000 298800 298800 100 Yes Kutubuddin Seikh under Nimdaha G.P. 2019 Purbasthali- II P.S. Wanting within Purbasthali-II P.S. Constn. of cc road from the house of Mantu 2018 - Executive Officer, Report 62 Seikh house of Kalim Seikh under 677/DP 27/02/2019 250000 249800 249800 100 Yes 2019 Purbasthali- II P.S. Wanting Purbasthali G.P. within Purbasthali-II P.S. Cost of brick solling road from house of 2018 - Executive Officer, Report 63 Pradip Bhowal towards Bhandertikuri 3475/DP 11/09/2019 150000 128415 128415 100 Yes 2019 Purbasthali- I P.S. Wanting station under Jahannagar G.P . Total 1500000 1469162 1469162 Grand Total 13500000 13354430 13354430 127 ONGOING SCHEMES

128 PRADIP KUMAR SAHA, HON'BLE MLA 269 PURBASTHALI UTTAR A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Name of the Scheme Year Executing Agency Submitt Present Status No. Order No Sanction Sanction Released Utilized Progress ed

Constn. of Atchala near the house of Lintel level 2018 - Executive Officer, 1 Biswanath Sanyal under Pilla G.P. 081/DP 08/01/2020 199910 199910 149932 75 No complete. Part UC 2019 Purbasthali- II P.S. within Purbasthali-II P.S. on 15/03/2020

Constn. of Atchala near the house of Lintel level 2018 - Executive Officer, 2 Jadab Sadhu under Pila G.P. within 081/DP 08/01/2020 198800 198800 149100 75 No complete. Part UC 2019 Purbasthali- II P.S. Purbasthali-II P.S. on 15/03/2020

Constn. of Atchala at Gangapur Work not start, 2018 - Executive Officer, 3 Bakultala under Jhowdanga 081/DP 08/01/2020 250000 187500 0 0 No Local problem 2019 Purbasthali- II P.S. G.P.within Purbasthali-II P.S. arises. Constn. of Guard wall with earth Foundation level filling near Pirtala pukur par under 2018 - Executive Officer, 4 081/DP 08/01/2020 248250 248250 186187 75 No complete. Part UC Majida G.P. within Purbasthali -II 2019 Purbasthali- II P.S. on 15/03/2020 P.S. Constn. of Atchala at Telinipara Above lintal level Sabuj Sangha Club under 2018 - Executive Officer, 5 081/DP 08/01/2020 174912 174912 131184 75 No complete. Part UC Kalekhantala-II G.P. within 2019 Purbasthali- II P.S. on 05/03/2020 Purbasthali-II P.S. Roof just custed & Constn. of atchala at Dasghariya para 2018 - Executive Officer, plaster work 6 near the house of Janardhan Saha 081/DP 08/01/2020 174860 174860 131145 75 No 2019 Purbasthali- II P.S. ongoing, Part UC on vill-Parulia, dag-458 25/02/2020 129 PRADIP KUMAR SAHA, HON'BLE MLA 269 PURBASTHALI UTTAR A.C.

Physic UC Sl. Sanction Date of Amount Amount Amount al Name of the Scheme Year Executing Agency Submitt Present Status No. Order No Sanction Sanction Released Utilized Progr ed ess Repairing with black stone and 2018 - Executive Officer, Complete work & bill 7 bitumin from Parulia Bazar towards 526/DP 07/02/2020 450000 450000 3375000 75 No 2019 Purbasthali- II P.S. in process. Parulia KK H.S. under Kalekhantala

Purchase of Multi GYM equipment 2018 - Secy. Narayanpur Procurement process 8 for Narayanpur Evening Star Club 665/DP 18/02/2020 174900 131175 0 0 No 2019 Evening Star Club already started. within Purbasthali-II P.S. Constn. of Atchala at Telinipara near Amar Sangha Club Dag No. 13/439 2018 - Executive Officer, Work will be started 9 754/DP 28/02/2020 175000 131250 0 0 No under Kalekhantala-II G.P. within 2019 Purbasthali- II P.S. within 1 week. Purbasthali-II P.S Purchase of Multi GYM equipment 2018 - Secy. Patuli Procurement process 10 for Patuli Sporting Club within 755/DP 28/02/2020 174900 131175 0 0 No 2019 Sporting Club already started. Purbasthali-II P.S.

2018 - Constn. of atchala near the house of Puru Executive Officer, 11 Seikh (Charbattala) paschim under 2019 936/DP 13/03/2020 199000 149250 0 0 No Purbasthali- II P.S. Majida withhin Purbasthali-II P.S.

Total 2420532 2177082 4122548

130 Hon’ble M.L.A. Shri Rabindranath Chatterjee HON'BLE MLA 270 KATWA A.C.

131 COMPLETED SCHEMES

132 RABINDRANATH CHATTERJEE, HON'BLE MLA 270 KATWA A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn of High Drainat Choto 2016 - Executive Officer, Report 1 Kulgachi beside house of P.Hazra 2046/DP 07/09/2016 200000 136768 136768 100 Yes 2017 Katwa- II P.S. Wanting Culvert Upgradation Jhama Moorum Road at 2016 - Executive Officer, Report 2 Chandpur near house of Ajmat Skto 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. Wanting Lasker Sk. Constn of RCC drain at Natungram 2016 - Executive Officer, Report 3 near Bituminous road upto house of 2046/DP 07/09/2016 150000 150000 150000 100 Yes 2017 Katwa- II P.S. Wanting Anwar Sk

Constn of Bathing Ghat on the 2016 - Executive Officer, Report 4 Baram Pukurat Gourdanga of Singhi 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. Wanting G.P.

Constn of Boundary Wall of the Kabi 2016 - Executive Officer, Report 5 Sekhar Sri Kalidas Heritage house to 2046/DP 07/09/2016 150000 89493 89493 100 Yes 2017 Katwa- II P.S. Wanting Kauri vill

Constn of CC Road at Kurchi near 2016 - Executive Officer, Report 6 house of Mihir Samanta upto house 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. Wanting of M.Mondal Constn of CC Road at Panjoa near 2016 - Executive Officer, Report 7 house of Kalosona Para upto house 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. Wanting of Natun Majhi 133 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Executive Upgradation of Jhama Moorum Road 2016 - Report 8 2046/DP 07/09/2016 100000 Officer, Katwa- 100000 100000 100 Yes at Singhi near house of B.Santra 2017 Wanting II P.S.

Executive Const of Bathing Ghaton the Bakul 2016 - Report 9 2046/DP 07/09/2016 100000 Officer, Katwa- 100000 100000 100 Yes Garh Pukur at Choto Meyagachi 2017 Wanting II P.S.

Executive Constn of CC Road and drain at 2016 - Report 10 2046/DP 07/09/2016 500000 Officer, Katwa- 325277 325277 100 Yes Kalikapur beside Old Kalna 2017 Wanting II P.S.

Constn of Guard Wall Chotokulgachi Executive 2016 - Report 11 Suhasini Sishu Sikhsa Kendra of 2046/DP 07/09/2016 150000 Officer, Katwa- 150000 150000 100 Yes 2017 Wanting Gazipur II P.S.

Constn of Guard Wall and bathing Executive 2016 - Report 12 Ghat at Mustuli Moyragarh Pukur of 2046/DP 07/09/2016 200000 Officer, Katwa- 137900 137900 100 Yes 2017 Wanting Jaganandapur II P.S.

Constn of Guard Wall and Bathing Executive 2016 - Report 13 Ghat at Baro Kangi Dighi of 2046/DP 07/09/2016 200000 Officer, Katwa- 136060 136060 100 Yes 2017 Wanting Jaganandapur II P.S.

Constn of CC Road Ghumuria Near Executive 2016 - Report 14 house of Hamijul Mollah upto 2046/DP 07/09/2016 100000 Officer, Katwa- 100000 100000 100 Yes 2017 Wanting Masjid II P.S. 134 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of CC Road at Sutragachi Executive 2016 - Report 15 beside house of S. Mondal to 2046/DP 07/09/2016 200000 Officer, Katwa- 136278 136278 100 Yes 2017 Wanting K.Majhi II P.S.

Constn of CC Road at Purba Multi Executive 2016 - Report 16 Near the house of Sahidulla Mollah 2046/DP 07/09/2016 250000 Officer, Katwa- 138086 138086 100 Yes 2017 Wanting to Kalapukur II P.S.

Executive Constn of CC Road at Natun Gram 2016 - Report 17 2046/DP 07/09/2016 250000 Officer, Katwa- 191187 191187 100 Yes near the house of Abul Mallick 2017 Wanting II P.S.

Up gradation of Jhama moram road Executive 2016 - Report 18 at karaj Gram house of A. Pan uptoB. 937/DP 27/03/2017 200000 Officer, Katwa- 200000 200000 100 Yes 2017 Wanting Mondal of Karajgram I P.S.

Constn of C C road at Karaj Gram Executive 2016 - Report 19 near Jora Dharmatala to Kauri Katwa 937/DP 27/03/2017 200000 Officer, Katwa- 200000 200000 100 Yes 2017 Wanting road I P.S.

Constn of C C Road and Drain at Executive 2016 - Report 20 haripur from H.Sk. Shop upto M.R. 937/DP 27/03/2017 250000 Officer, Katwa- 250000 250000 100 Yes 2017 Wanting Shop I P.S.

Constn of C C Road at Mera Near Executive 2016 - Report 21 house of J.Sk upto house upto L. Sk 937/DP 27/03/2017 100000 Officer, Katwa- 100000 100000 100 Yes 2017 Wanting of Sudpur I P.S. 135 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Executive Constn of bathing Ghat North side to 2016 - Report 22 937/DP 27/03/2017 125000 Officer, Katwa- 125000 125000 100 Yes Dighirpukur at Khejurihi Sardar Para 2017 Wanting I P.S.

Constn of Bathing Ghat Hatgacha Executive 2016 - Report 23 Pukur at Bunidighi of 937/DP 27/03/2017 125000 Officer, Katwa- 125000 125000 100 Yes 2017 Wanting Khejurdihi G.P. I P.S.

Constn of C C Road at Panuhat Executive 2016 - Report 24 Baidyapara near house of S.Roy upto 937/DP 27/03/2017 125000 Officer, Katwa- 125000 125000 100 Yes 2017 Wanting house of Sudev Halder of Khajurdihi I P.S.

Constn of C C road at Sudpur Executive 2016 - Report 25 Bhattarchya Para to Radha 937/DP 27/03/2017 200000 Officer, Katwa- 200000 200000 100 Yes 2017 Wanting Karishnapur Bagdi Para I P.S.

Constn of C C Road at Tikarkhaji Executive 2016 - Report 26 near the Laxmi Mandir upto behind 937/DP 27/03/2017 200000 Officer, Katwa- 200000 200000 100 Yes 2017 Wanting the narayan Mandir I P.S.

Constn of Community Centre at Executive 2016 - Report 27 Auria on the K. Bharati Melatala of 937/DP 27/03/2017 200000 Officer, Katwa- 200000 200000 100 Yes 2017 Wanting Palason G.P. II P.S.

Constn of CC Road at Ronda near Executive 2016 - Report 28 house of G.Ghosh upto ICDS 937/DP 27/03/2017 200000 Officer, Katwa- 200000 200000 100 Yes 2017 Wanting Centreof Palason II P.S. 136 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of Bathing Ghat on the Bara Executive 2016 - Report 29 Bandh Pukur at Auria of Palason 937/DP 27/03/2017 100000 Officer, Katwa- 100000 100000 100 Yes 2017 Wanting G.P. II P.S.

Constn of drain at palikpara vill near Executive 2016 - Report 30 house of K. Sk. upto the house of M. 937/DP 27/03/2017 100000 Officer, Katwa- 100000 100000 100 Yes 2017 Wanting Sk of Jagadanandapur II P.S.

Constn of Cremation 2nd unit at 2016 - Chairman, Report 31 1020/DP 03/04/2017 322000 322000 322000 100 Yes Katwa Burrning Ghat 2017 Katwa Muty. Wanting

Constn of extn building at Katwa 2016 - Chairman, Report 32 Jhankar Ward No. 6 under Katwa 1959/DP 12/07/2017 150000 150000 150000 100 Yes 2017 Katwa Muty. Wanting Muty

Constn of Extn Building at Youth 2016 - Chairman, Report 33 Club Ward No. 17 under Katwa 1959/DP 12/07/2017 150000 150000 150000 100 Yes 2017 Katwa Muty. Wanting Muty

Constn of Gem Room at Jhankar 2016 - Chairman, Report 34 1959/DP 12/07/2017 178000 178000 178000 100 Yes Ward No6 under Katwa Muty 2017 Katwa Muty. Wanting

Total 5875000 5216049 5216049

Constn of Concrete Drain at Majhari Executive 2017 - Report 35 Joghadya tala to Bamun Pukur of 2286/DP 18/08/2017 97010 Officer, Katwa- 97010 97010 100 Yes 2018 Wanting Kauri G.P. II P.S. 137 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of CC Road at Panjoa Executive 2017 - Report 36 Apanjan Club to T.Bandhus house of 2286/DP 18/08/2017 146996 Officer, Katwa- 146996 146996 100 Yes 2018 Wanting Kauri G.P. II P.S.

Executive Constn of CC Road at Akhra Sheial 2017 - Report 37 2286/DP 18/08/2017 241480 Officer, Katwa- 241480 241480 100 Yes Mara Para of Jaganandapur G.P. 2018 Wanting II P.S.

Constn of CC Road at Dona Purba Executive 2017 - Report 38 Para Durga Mandir to K. Kundas 2286/DP 18/08/2017 148516 Officer, Katwa- 148516 148516 100 Yes 2018 Wanting house of Kuri G.P. II P.S.

Executive Constn of CC Road at Ekdela 2017 - Report 39 2286/DP 18/08/2017 250000 Officer, Katwa- 245000 245000 100 Yes Jogadhya Tala of Jaganandapur G.P. 2018 Wanting II P.S.

Constn. of CC road at Deriyapur Executive 2017 - Report 40 from the house of B. Kunda to 2461/DP 05/09/2017 250000 Officer, Katwa- 242424 242424 100 Yes 2018 Wanting Primary School II P.S.

Constn of CC Road at Agradwip Executive 2017 - Report 41 Sarawari from ICDS Centre to 2461/DP 05/09/2017 500000 Officer, Katwa- 500000 500000 100 Yes 2018 Wanting Beltala of Agradwip G.P. II P.S.

Constn. of CC road and drain at Executive 2017 - Report 42 Kuyara Danga from Masjid Tala to 2461/DP 05/09/2017 250000 Officer, Katwa- 244500 244500 100 Yes 2018 Wanting Jinnal Sk house of Palsona G.P. II P.S. 138 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of CC Road at Natungram Executive 2017 - Report 43 from Sultans house to Porkorer Par 2461/DP 05/09/2017 100000 Officer, Katwa- 97000 97000 100 Yes 2018 Wanting of G.P. II P.S.

Constn of Drain from the house of Executive 2017 - Report 44 A.Debnath house of R. Kanta 2825/DP 06/11/2017 125000 Officer, Katwa- 124403 124403 100 Yes 2018 Wanting Debnath at Ekaihat I P.S.

Constn of CC Road from Katwa Executive 2017 - Report 45 Karul Road to the house of Biduri 2825/DP 06/11/2017 125000 Officer, Katwa- 125000 125000 100 Yes 2018 Wanting Pal at Panchghora I P.S.

Constn of CC Road from Katrsj Executive 2017 - Report 46 Gram oad house of 2825/DP 06/11/2017 150000 Officer, Katwa- 150000 150000 100 Yes 2018 Wanting N.Pandit Durga Gram I P.S.

Constn of CC Road from Karajgram Executive 2017 - Report 47 from Paschimpara Simultala to 2825/DP 06/11/2017 250000 Officer, Katwa- 250000 250000 100 Yes 2018 Wanting Karajgram High School I P.S.

Constn of CC Road from the house Executive 2017 - Report 48 of M. Malik house of Gafur Sk at 2825/DP 06/11/2017 125000 Officer, Katwa- 125000 125000 100 Yes 2018 Wanting Natungram I P.S.

Constn of CC Road from the house Executive 2017 - Report 49 of R. Roy house ofR. Duttaat Char 2825/DP 06/11/2017 125000 Officer, Katwa- 125000 125000 100 Yes 2018 Wanting Panuhat I P.S. 139 Sl. Sanction Date of Amount Amount Amount Physical UC Handed Name of the Scheme Year Executing Agency No. Order No Sanction Sanction Released Utilized Progress Submitted Over Status

Constn of CC Road from Bandhmura 2017 - Executive Officer, Report 50 Bagdipara house of R. Hazra house 2825/DP 06/11/2017 100000 100000 100000 100 Yes 2018 Katwa- I P.S. Wanting of Asraf Sk of Karajgram Instn of High Mast Lightof different 2017 - Chairman, Report 51 1096/DP 14/06/2018 500000 500000 500000 100 Yes Location of Dainhat Town 2018 Muty. Wanting Constn of CC Road from Abdul 2017 - Executive Officer, Report 52 Baki Mallick to Choyer A. Mallick 1188/DP 26/06/2018 150000 150000 150000 100 Yes 2018 Katwa- II P.S. Wanting house at Garagacha vill Gazipur Constn of CC Road from S. Bairagya 2017 - Executive Officer, Report 53 house to S. Baiagya house at 1188/DP 26/06/2018 200000 200000 200000 100 Yes 2018 Katwa- II P.S. Wanting Suagachi vill

Constn of gate at DD Girls High 2017 - Chairman, Katwa Report 54 1403/DP 30/07/2018 200000 200000 200000 100 Yes School at Katwa Municipality 2018 Muty. Wanting

Instan. of color Doppler Ultrasound 2017 - Chairman, Katwa Report 55 1403/DP 30/07/2018 800000 800000 800000 100 Yes Machin at Dr. B.C. Roy Polytechnic 2018 Muty. Wanting Constn. of CC road from Brindaban Ghosh House to Gartala at Vijoy 2017 - Executive Officer, Report 56 472/DP 14/02/2019 200000 199300 199300 100 Yes Nagar Village at Sudpur G.P. under 2018 Katwa- I P.S. Wanting Katwa-I P.S.

Installation of water purifier for the 2017 - Chairman, Dainhat Report 57 255/DP 21/01/2020 125000 125000 125000 100 Yes student Dainhat High School 2018 Muty. Wanting

Total 5159002 5136629 5136629 140 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Constn. of C.C. road at Mahakhaltore Executive 2018 - Report 58 Dutta Para under Agradwip G.P. 484/DP 14/02/2019 500000 Officer, Katwa- 495250 495250 100 Yes 2019 Wanting within Katwa-II P.S. II P.S.

Supply of Funeral Car (Dead Body 2018 - Chairman, Report 59 Removal Van) under Dainhat 1301/DP 30/05/2019 468370 468370 468370 100 Yes 2019 Dainhat Muty. Wanting Municipality Constn. of drain at beside Executive Mukherjee Pukur to Muchi Pukur 2018 - Report 60 1301/DP 30/05/2019 150000 Officer, Katwa- 149250 149250 100 Yes under Sribati G.P. within Katwa-II 2019 Wanting II P.S. P.S. Constn. of drining sheed at Akhra Executive 2018 - Report 61 High School under Jagadanandapur 1301/DP 30/05/2019 300000 Officer, Katwa- 298500 298500 100 Yes 2019 Wanting G.P. within Katwa-II P.S. II P.S. Constn. of drain at Mulgram beside Executive Monduptala to Susanta Ghosh house 2018 - Report 62 1301/DP 30/05/2019 150000 Officer, Katwa- 149400 149400 100 Yes under Sribati G.P. within Katwa-II 2019 Wanting II P.S. P.S. Executive Constn. of Protection wall at Auria 2018 - Report 63 2043/DP 09/08/2019 200000 Officer, Katwa- 199000 199000 100 Yes Bandh pukur under Palsona G.P. 2019 Wanting II P.S.

141 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn. of community sheed at Musthuli Laha Para under 2018 - Executive Officer, Report 64 2325/DP 30/08/2019 200000 199000 199000 100 Yes Jaganandapur G.P. within Katwa-II 2019 Katwa- II P.S. Wanting P.S. Constn. of C.C. road with drain at Nandigram from Goutam Roy House 2018 - Executive Officer, Report 65 4234/DP 25/11/2019 200000 199000 199000 100 Yes to Sujit Roy House under Sribati GP. 2019 Katwa- II P.S. Wanting within Katwa-II P.S. Constn. of waiting room at Srirampur 2018 - Executive Officer, Report 66 Bus Stand under Karajgram G.P. 4692/DP 26/12/2019 500000 499000 499000 100 Yes 2019 Katwa- I P.S. Wanting within Katwa-I P.S. Constn. of CC road and drain at Haripur, beside the house of Mostafa 2018 - Executive Officer, Report 67 4692/DP 26/12/2019 400000 400000 400000 100 Yes Sk. to Surhok Sk. under Goai G.P. 2019 Katwa- I P.S. Wanting within Katwa-I P.S. Total 3068370 3056770 3056770 Grand Total 14102372 13409448 13409448

142 ONGOING SCHEMES

143 RABINDRANATH CHATTERJEE, HON'BLE MLA 270 KATWA A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Installation of Submersible pump set 2017 - Chairman, Bill under process UC 1 for drinking water at Keshia Masjid 431/DP 04/02/2020 125000 93750 0 0 No 2018 Katwa Muty. on 05/03/2020. under Katwa Municipality Total 125000 93750 0 Expected UC on Supply of Funeral Car (Dead Body) 2018 - Chairman, 2 212/DP 17/01/2019 500000 375000 0 0 No 28/02/2020 late due Removal van under Katwa Muty. 2019 Katwa Muty. to undelivered.

Instalation of High Mast Light (Mini) Executive Work completed & 2018 - 3 at Barakulgachi Bakultala at Gajipur 604/DP 13/02/2020 150000 Officer, Katwa- 150000 112500 75 No UC will be submitted 2019 G.P. II P.S. by 20/03/2020

Installation of High Mast Light Executive Work completed & 2018 - 4 (Mini) at Dewasin Bridge at Gajipur 604/DP 13/02/2020 150000 Officer, Katwa- 150000 112500 75 No UC will be submitted 2019 G.P. II P.S. by 20/03/2020

Executive Work completed & Instalation of High Mast Light (Mini) 2018 - 5 604/DP 13/02/2020 150000 Officer, Katwa- 150000 112500 75 No UC will be submitted at Gajipur Dasduari Bandh 2019 II P.S. by 20/03/2020

144 RABINDRANATH CHATTERJEE, HON'BLE MLA 270 KATWA A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Work completed & Instalation of High Mast Light (Mini) 2018 - Executive Officer, UC will be 5 at Agradwip Railbazar near 604/DP 13/02/2020 150000 150000 112500 75 No 2019 Katwa- II P.S. submitted by Allahadabad Bank 20/03/2020 Fencing for Development of Play Work completed & groundof Gibinda Bagan Play 2018 - Chairman, Katwa UC will be 6 644/DP 17/02/2020 897637 673228 0 0 No Ground at Kashigang para under 2019 Muty. submitted by Katwa Muty. 20/03/2020

Fencing for Development of Play 2018 - Chairman, Katwa 7 groundof Gibinda Bagan Play Ground at 644/DP 17/02/2020 897637 673228 0 0 No 2019 Muty. Kashigang para under Katwa Muty.

Constn. of Clock Tower at Duckbanglow 2018 - Chairman, Katwa 8 925/DP 13/03/2020 283036 212277 0 0 No road side in front of Municipal Office 2019 Muty.

Addition and Alteration of 1st floor of 2018 - Chairman, Katwa 9 College Canteen at Katwa College 924/DP 13/03/2020 800000 600000 0 0 No Campus 2019 Muty.

Total 3080673 2460505 450000 Grand Total 3205673 2554255 450000

145 Hon’ble M.L.A. Sekh. Saho Nawez MLA 271 KETUGRAM A.C.

146 COMPLETED SCHEMES

147 SEKH SAHO NEWAZ, HON'BLE MLA 271 KETUGRAM A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of Ghat at Ankhona Shattala 2016 - Executive Officer, Report 1 2727/DP 21/11/2016 150000 150000 150000 100 Yes Pond of Ankhona G.P. 2017 Ketugram- I P.S. Wanting

Constn of Ghat at Rikha ir Pukur of 2016 - Executive Officer, Report 2 2727/DP 21/11/2016 200000 200000 200000 100 Yes Rajoor G.P. 2017 Ketugram- I P.S. Wanting

Constn of Concrete Road from Madhusudan Bagdi house to D. 2016 - Executive Officer, Report 3 2727/DP 21/11/2016 300000 300000 300000 100 Yes Mukherjee house at Gonna Serandi 2017 Ketugram- I P.S. Wanting of Palita G.P.

Constn of Ghat at Kantari Dighir Par 2016 - Executive Officer, Report 4 2727/DP 21/11/2016 150000 150000 150000 100 Yes of Palita G.P. 2017 Ketugram- I P.S. Wanting

Constn of Ghat at Chenchuri 2016 - Executive Officer, Report 5 2727/DP 21/11/2016 150000 150000 150000 100 Yes Thakrun Pukur of Ankhona G.P. 2017 Ketugram- I P.S. Wanting

Constn of New Room Kandra 2016 - Executive Officer, Report 6 Ramjibanpur Hospital of Kandra 2958/DP 19/12/2016 500000 500000 500000 100 Yes 2017 Ketugram- I P.S. Wanting G.P.

Constn of entrance of Kandra RKK 2016 - Executive Officer, Report 7 3046/DP 27/12/2016 500000 500000 500000 100 Yes College of Kandra G.P. 2017 Ketugram- I P.S. Wanting 148 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of Road from Charsujapur 2016 - Executive Officer, Report 8 Chowrasta to Dyoam of Mougram 61/DP 05/01/2017 300000 299608 299608 100 Yes 2017 Ketugram- II P.S. Wanting G.P. Constn of Road from Bankim Nanda 2016 - Executive Officer, Report 9 house to D. Bhattacherjee house with 61/DP 05/01/2017 300000 300000 300000 100 Yes 2017 Ketugram- II P.S. Wanting drain at Nirol

Constn of Culvert at Baharan 2016 - Executive Officer, Report 10 61/DP 05/01/2017 300000 300000 300000 100 Yes Hazrapara of G.P. 2017 Ketugram- II P.S. Wanting

Constn of Culvert at Haldi to Srigram 2016 - Executive Officer, Report 11 742/DP 09/03/2017 625000 625000 625000 100 Yes Road near Fullaratala of Agardanga 2017 Ketugram- I P.S. Wanting

Constn of Guard Wall at Keoguri 2016 - Executive Officer, Report 12 742/DP 09/03/2017 300000 282964 282964 100 Yes High School of Sitahati G.P. 2017 Ketugram- II P.S. Wanting

Rep. of all Anganwari, SSK,MSK 2016 - Executive Officer, Report 13 742/DP 09/03/2017 500000 497894 497894 100 Yes Building under Ketugram-II 2017 Ketugram- II P.S. Wanting

Computer Set at Shibloon ACM 2016 - Executive Officer, Report 14 1152/DP 12/04/2017 100000 100000 100000 100 Yes High School of Nabagram 2017 Ketugram- II P.S. Wanting

Total 4375000 4355466 4355466 149 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn. of Baitarani scheme Exe. Engg. PWD 2017 - Report 15 Ketugram-II and Chakta, near Kuye 2248/DP 11/08/2017 890000 (Social Sector), 740653 740653 100 Yes 2018 Wanting River (Jl.-2, Dag-1681) Burdwan.

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 16 Ketugram-II and Kalyanpur 2248/DP 11/08/2017 890000 (Social Sector), 740653 740653 100 Yes 2018 Wanting Gangaghat (JL-111, Dag-324) Burdwan.

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 17 Ketugram-II and Jakdanga Srigram 2248/DP 11/08/2017 890000 (Social Sector), 740653 740653 100 Yes 2018 Wanting (Jl.-7, Dag.-1858) Burdwan.

Constn of ACR Dakshin Executive 2017 - Report 18 Muskim F.P. School of Srikhanda 2376/DP 29/08/2017 250000 Officer, Katwa- 250000 250000 100 Yes 2018 Wanting G.P. I P.S.

Executive Constn of Ghat at Majhipara Dighi 2017 - Report 19 2376/DP 29/08/2017 150000 Officer, 150000 150000 100 Yes Pukur at Sripur vill of Khandra G.P. 2018 Wanting Ketugram- I P.S.

Impv of Road from Badsahi road Executive 2017 - Report 20 towards Aargoon viilage of Rajoor 2376/DP 29/08/2017 300000 Officer, 300000 300000 100 Yes 2018 Wanting G.P. Ketugram- I P.S. Executive Constn of Boundary Wall Bara 2017 - Officer, Report 21 Purulia Mahendra Vidyalaya of 3280/DP 13/12/2017 200000 179748 179748 100 Yes 2018 Ketugram- II Wanting Nabagram P.S. 150 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of one ACR Bileswar 2017 - Executive Officer, Report 22 Binodilal Balika Vidyalaya under 146/DP 24/01/2018 300000 300000 300000 100 Yes 2018 Ketugram- II P.S. Wanting Ketugram

Rep of Room Gurpara High School 2017 - Executive Officer, Report 23 146/DP 24/01/2018 300000 298458 298458 100 Yes of Billeswar under Ketugram 2018 Ketugram- II P.S. Wanting

Constn of road from Nalipur More to 2017 - Executive Officer, Report 24 Keogari High School under 290/DP 09/02/2018 450000 450000 450000 100 Yes 2018 Ketugram- II P.S. Wanting Ketugram

Constn of Toilet at Rajoor Bandhab 2017 - Executive Officer, Report 25 1448/DP 06/08/2018 200000 200000 200000 100 Yes High School of Rajoor G.P. 2018 Ketugram- I P.S. Wanting

Constn. of ghat at Painfola ghat at Raghupur (daag no. 1358 Jl-65 of 2017 - Executive Officer, Report 26 2194/DP 28/09/2018 150000 150000 112500 100 No Pandugram G.P. under Ketugram-I 2018 Ketugram- I P.S. Wanting P.S. Constn. of ACR at Kulai High 2017 - Executive Officer, Report 27 638/DP 26/02/2019 300000 300000 300000 100 Yes School under Pandugram G.P. 2018 Ketugram- I P.S. Wanting

Total 5270000 4800165 4762665 Constn. of Cycle Stand Ketugram Asutosh Memorial Institution at 2018 - Executive Officer, Report 28 2138/DP 24/09/2018 200000 200000 200000 100 Yes Ketugram GP within Ketugram-II 2019 Ketugram- II P.S. Wanting P.S. 151 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn. of roade from Dakshin Para Kaltala To Football Ground at Belun 2018 - Executive Officer, Report 29 2138/DP 24/09/2018 200000 149850 149850 100 Yes of Nabagram GP within Ketugram-II 2019 Ketugram- II P.S. Wanting PS. Constn. of Boundary wall of Ketugram Jr. Girls High School 2018 - Executive Officer, Report 30 2138/DP 24/09/2018 200000 200000 200000 100 Yes under Ketugram G.P. within 2019 Ketugram- II P.S. Wanting Ketugram-II P.S.

Constn. of bondary wall of 2018 - Executive Officer, Report 31 Enayetpur FP School of Sitahati GP 2138/DP 24/09/2018 150000 150000 150000 100 Yes 2019 Ketugram- II P.S. Wanting within Ketugram PS.

Constn. of drain at Kandra from Kalu 2018 - Executive Officer, Report 32 Bairagya House to Akter within 2213/DP 10/10/2018 100000 100000 100000 100 Yes 2019 Ketugram- I P.S. Wanting Ketugram-I P.S.

Repairing of room at Srikhanda 2018 - Executive Officer, Report 33 High School of Srikhanda G.P. under 488/DP 14/02/2019 100000 99990 99900 100 No 2019 Katwa- I P.S. Wanting Katwa-I P.S.

Constn. of Hatmurgram High 2018 - Executive Officer, Report 34 Madrasha Ceremony Stage within 562/DP 20/02/2019 150000 150000 150000 100 Yes 2019 Ketugram- I P.S. Wanting Ketugram-I P.S.

Constn. of High must light at 2018 - Executive Officer, Report 35 Futisanko Bus stand within 562/DP 20/02/2019 540000 540000 540000 100 Yes 2019 Ketugram- I P.S. Wanting Ketugram -I P.S. 152 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn. of Community Hall at 2018 - Executive Officer, Report 36 Tourism Spot at Nowpara Ketugram- 562/DP 20/02/2019 300000 300000 300000 100 Yes 2019 Ketugram- I P.S. Wanting I P.S. Repairing of room at Srikhanda 2018 - Executive Officer, Report 37 Muslim primary School under 639/DP 26/02/2019 250000 249875 249875 100 Yes 2019 Katwa- I P.S. Wanting Katwa-I P.S. Constn. of Grave Ghat at 2018 - Executive Officer, Report 38 Gangulidanga under Srikhanda 843/DP 06/03/2019 150000 149970 149970 100 Yes 2019 Katwa- I P.S. Wanting G.P.within Katwa-I P.S. Constn. of road from Ajij Molla house to Harej Mollah House at 2018 - Executive Officer, Report 39 843/DP 06/03/2019 200000 199920 199920 100 Yes Chandrakota under Srikhanda G.P. 2019 Katwa- I P.S. Wanting within Katwa-I P.S. Constn. of road from Dhanu Mondal house to Islam Sk house at 2018 - Executive Officer, Report 40 843/DP 06/03/2019 200000 96653 96653 100 Yes Gangulidanga under Srikhanda G.P. 2019 Katwa- I P.S. Wanting within Katwa-I P.S. Constn. of Pukur Ghat at 2018 - Executive Officer, Report 41 Kodampukur under Srikhanda G.P. 843/DP 06/03/2019 150000 149970 149970 100 Yes 2019 Katwa- I P.S. Wanting within Katwa-I P.S. Constn. of bathroom and ghat at 2017 - Executive Officer, Report 42 Khaspukur Nawpukur of Rajoor G.P. 2123/DP 19/08/2019 250000 250000 250000 100 Yes 2018 Ketugram- I P.S. Wanting under Ketugram-I P.S. Total 3140000 2986228 2986138 Grand Total 12785000 12141859 12104269 153 ONGOING SCHEMES

154 SEKH SAHO NEWAZ, HON'BLE MLA 271 KETUGRAM A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Constn of Ghat to Bhagirathi Near 2017 - Executive Officer, Cancelled. But not 1 Dulal Sadhu Ashram at Sankhai of 998/DP 25/05/2018 150000 150000 0 0 No 2018 Ketugram- II P.S. refunded. Sitahati G.P. Constn of Ghat at Bannagara 2017 - Executive Officer, 2 2076/DP 18/09/2018 150000 149985 112500 75 No UC sent. Sukhmoy Pond of Srikhanda G.P. 2018 Katwa- I P.S. Work in progress Constn. of Culvet at Barnna Gara 2017 - Executive Officer, 3 1797/DP 22/07/2019 400000 399960 299970 75 No UC will be Kandar under Katwa-I P.S. 2018 Katwa- I P.S. submitted soon Constn. of Kalu pukur ghat and 2017 - Executive Officer, 4 Bathroom at Berugram G.P. JL (14, 826/DP 04/03/2020 1800000 135000 0 0 No Work Started 2018 Ketugram- I P.S. Dag-2727) within Kerugram-I P.S. Total 2500000 834945 412470 Constn. of Gopalsagar pond ghat and 2018 - Executive Officer, 5 Bathroom at Jl-90, Dag-2053 under 3499/DP 13/09/2019 160000 119952 0 0 No Work started 2019 Ketugram- II P.S. Ketugram-II P.S. Constn. of community hall at 2018 - Executive Officer, Work Started. 6 Tourism spot at (Chhoto) 3958/DP 31/10/2019 300000 224978 0 0 No 2019 Ketugram- II P.S. 80% completed under Ketugram-II P.S. Repairing of Aikyatan Community Work Started & 2018 - Executive Officer, 7 Hall at Pachundi under Ketugram-II 256/DP 21/01/2020 500000 369328 0 0 No 90% work has 2019 Ketugram- II P.S. P.S. been completed Total 960000 714258 0 155 Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess Constn. of Bolla Pukur Ghat, Plot- Executive 2019 - Work order given but 8 3061 under J-kandra G.P. within 825/DP 04/03/2020 150000 Officer, 112500 0 2020 not started. Ketugram-I P.S. Ketugram- I P.S.

Constn. of Bathing Ghat at Talbona Executive 2019 - Work order given but 9 pukur Plot-2217 under Rajoor G.P. 970/DP 17/03/2020 150000 Officer, 112500 0 2020 not started. within Ketugram-I P.S. Ketugram- I P.S.

Renovation of Community Hall at Executive 2019 - Work order given but 10 Janadas Path bari Plot-2781 under J- 970/DP 17/03/2020 200000 Officer, 150000 0 2020 not started. Kandra G.P. within Ketugram-I P.S Ketugram- I P.S.

Total 500000 375000 0 Grand Total 3960000 1924203 412470

156 Hon’ble M.L.A. Siddiqullah Chowdhury MLA 272 MONGALKOTE A.C.

157 COMPLETED SCHEMES

158 SIDDIQULLAH CHOWDHURY, HON'BLE MLA 272 MONGALKOTE A.C.

Sl. Sanction Date of Amount Amount Amount Physical UC Handed Over Name of the Scheme Year Executing Agency No. Order No Sanction Sanction Released Utilized Progress Submitted Status

District Purchase an Ambulance for Alampur Report 1 2016 - 2017 1979/DP 01/09/2016 488220 Magistrate, 488220 488220 100 Yes G.P. Wanting Burdwan District Purchase an Ambulance for Lakhuria Report 2 2016 - 2017 2459/DP 25/10/2016 492344 Magistrate, 492344 492344 100 Yes G.P. Wanting Burdwan District Purchase an Ambulance for Report 3 2016 - 2017 2459/DP 25/10/2016 492344 Magistrate, 492344 492344 100 Yes Bhalugram G.P. Wanting Burdwan

District Constn of Cycle Stand at Mathrun Report 4 2016 - 2017 892/DP 22/03/2017 450000 Magistrate, 444098 444098 100 Yes NC Institution (H.S)under Mathrun Wanting Burdwan

Constn of Addl Room for Patients Exe. Engg. PWD Report 5 with Sanitation and water supply at 2016 - 2017 892/DP 22/03/2017 1748000 (Social Sector), 1748000 1748000 100 Yes Wanting Mongalkote BPHC Burdwan.

Constn of Boundary Wall in the District Report 6 school Campus of Kowarpur High 2016 - 2017 3274/DP 12/12/2017 860000 Magistrate, 860000 860000 100 Yes Wanting School Burdwan

Constn of Concrete road from Ajay District Report 7 River Ghat to Liabrary and Hattala 2016 - 2017 417/DP 27/02/2018 490000 Magistrate, 487550 487550 100 Yes Wanting under Mongalkote Burdwan 159 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

District Constn of PCC road at Bhatpara from Nazu 2016 - Report 8 1916/DP 28/08/2018 390000 Magistrate, 385826 385826 100 Yes Sk House to A. Rauf house 2017 Wanting Burdwan Total 5410908 5398382 5398382 Constn of PCC Road at Village Pindira District 2017 - Report 9 from Abul Khair house to main Rd.Pucca 1811/DP 28/08/2018 750000 Magistrate, 639225 639225 100 Yes 2018 Wanting Udyan at Bhaligram Burdwan

Constn of PCC road at Village Dharsona District 2017 - Report 10 from Chand Sk house to L. Chand Sk house 1911/DP 28/08/2018 380000 Magistrate, 373267 373267 100 Yes 2018 Wanting Khioragram Burdwan

Constn of PCC road at Village at Musaru District 2017 - Report 11 Adibasipara from PWD Pacca Road to 1911/DP 28/08/2018 350000 Magistrate, 346080 346080 100 Yes 2018 Wanting Debu Hansda at Nigan Gram Burdwan District Constn of Cycle Stand Shade at majhigram 2017 - Report 12 1911/DP 28/08/2018 470000 Magistrate, 464970 464970 100 Yes Biswesri High School at Majhigram 2018 Wanting Burdwan Constn. of Mid-day meal shade for students District 2017 - Report 13 for Pindira High School under Mongalkote 2352/DP 29/10/2018 760000 Magistrate, 677920 677920 100 Yes 2018 Wanting P.S. Burdwan Constn. of Mid-day meal shade at Bazar District 2017 - Report 14 Bankapasi F.P. School under Mongalkote 2352/DP 29/10/2018 800000 Magistrate, 708903 708903 100 Yes 2018 Wanting P.S. Burdwan Total 3510000 3210365 3210365 Grand Total 8920908 8608747 8608747 160 ONGOING SCHEMES

161 SIDDIQULLAH CHOWDHURY, HON'BLE MLA 272 MONGALKOTE A.C.

Sl. Sanction Date of Amount Amount Amount Physical UC Present Name of the Scheme Year Executing Agency No. Order No Sanction Sanction Released Utilized Progress Submitted Status

Constn. of Fencing over Boundary wall at Nutunhat Milan Pathagar, West Bengal Agro Work not 1 under Jhiloo-I Gram Panchayat, Jl 2018-19 4753/DP 31/12/2019 200000 Industries 150000 0.00 0 No started No. 61, Plot No. 1214, Mouza- corporation Ltd. Halimpur Mongalkote P.S. Constn. of concrete road from PWD West Bengal Agro road to house of Kanai Chandra Work not 2 2018-19 4753/DP 31/12/2019 300000 Industries 224843 0.00 0 No Ghosh Vill.-Gherua, Mouza-Kherua, started corporation Ltd. Bhalyagram, within Mongalkote P.S. Constn. of concrete road from house of Sudhir Ghosh to house of Chand West Bengal Agro Work not 3 Mondal, Vill.- Buichi, Mouza- 2018-19 4753/DP 31/12/2019 300000 Industries 225000 0.00 0 No started Buichi, Bhalyagram, within corporation Ltd. Mongalkote P.S. Constn. of Community Hall at West Bengal Agro Work not 4 Buichi Sashtitala, Vill-Buichi, 2018-19 4753/DP 31/12/2019 700000 Industries 525000 0.00 0 No started Bhalyagram within Mongalkote P.S. corporation Ltd.

162 SIDDIQULLAH CHOWDHURY, HON'BLE MLA 272 MONGALKOTE A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Name of the Scheme Year Present Status No. Order No Sanction Sanction Agency Released Utilized Progress Submitted

Constn. of Meeting Room cum West Bengal office of Lakshimipur SKUS Ltd. Work not 5 2018-19 4753/DP 31/12/2019 700000 Agro Industries 524003 0.00 0 No Vill. Shyambazar , PO-Batra started corporation Ltd. Shyambazar within Mongalkote P.S. Constn. of boundary wall of West Bengal Work not 6 Nutunhat SDM Girls School under 2018-19 4753/DP 31/12/2019 171000 Agro Industries 128186 0.00 0 No started Mongalkote Dev. Block corporation Ltd. Arrangement for Drinking water at West Bengal Joykrishnapur Free Primary School, Work not 7 2018-19 4753/DP 31/12/2019 200000 Agro Industries 149940 0.00 0 No Vill.-Joykrishnapur, P.O.Chakulia started corporation Ltd. under Mongalkote Dev. Block Constn. of Class room Mongalkote- West Bengal II Sishu Siksha Kendra, Drinking Work not 8 2018-19 4753/DP 31/12/2019 300000 Agro Industries 224910 0.00 0 No water Gate and Boundary wall under started corporation Ltd. Mongalkote Dev. Block Total 2871000 2151882 0.00

163 Hon’ble M.L.A. Shri Abhedananda Thander MLA 273 AUSGRAM (SC) A.C.

164 COMPLETED SCHEMES

165 ABHEDANANDA THANDER, HON'BLE MLA 273 AUSGRAM (SC) A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn of Boundary wall for 2016 - Chairman, Report 1 Community Centre at Sukantapally 2724/DP 21/11/2016 115122 115122 115122 100 Yes 2017 Gushkara Muty. Wanting Ward No. 4 Constn of Boundary wall for 2016 - Chairman, Report 2 Community Centre at Purbopally 2724/DP 21/11/2016 183296 183296 183296 100 Yes 2017 Gushkara Muty. Wanting Ward No. 4

Constn of Road side Guard Wall at 2016 - Chairman, Report 3 2724/DP 21/11/2016 297902 297902 297902 100 Yes Ward No. 3 2017 Gushkara Muty. Wanting

Constn of CC Road at Ward No. 7 2016 - Chairman, Report 4 2724/DP 21/11/2016 98598 98598 98598 100 Yes under Muty 2017 Gushkara Muty. Wanting

Constn of CC Road at Ward No. 2 2016 - Chairman, Report 5 2724/DP 21/11/2016 100543 100543 100543 100 Yes under Guskara Muty 2017 Gushkara Muty. Wanting

Constn of CC Drain at Ward No. 10 2016 - Chairman, Report 6 2724/DP 21/11/2016 103003 103003 103003 100 Yes under Guskara Muty 2017 Gushkara Muty. Wanting

Constn of CC Road at Ward No. 1 2016 - Chairman, Report 7 2724/DP 21/11/2016 99435 99435 99435 100 Yes under Guskara Muty 2017 Gushkara Muty. Wanting 166 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

District Purchase an Ambulance for 2016 - Report 8 2770/DP 28/11/2016 540085 Magistrate, 540085 540085 100 Yes Billagram under Ausgram-I 2017 Wanting Burdwan

Constn of waiting shed at Executive 2016 - Report 9 Bannabagram BPHC of Ausgram 600/DP 27/02/2017 800000 Officer, 800000 800000 100 Yes 2017 Wanting G.P. Ausgram- I P.S.

Constn of waiting Shed with drinking Executive 2016 - Report 10 water facility at Ukhra PHC at Ukhra 645/DP 01/03/2017 900000 Officer, 900000 900000 100 Yes 2017 Wanting G.P. Ausgram- I P.S.

Executive Constn. of Samsan Chulli at Dharala 2016 - Report 11 905/DP 22/03/2017 250000 Officer, 250000 250000 100 Yes village under Ausgram-II P.S. 2017 Wanting Ausgram- II P.S.

Executive Constn of Boundary Wall at 2016 - Report 12 905/DP 22/03/2017 300000 Officer, 300000 300000 100 Yes Abhirampur F.P. School 2017 Wanting Ausgram- II P.S.

Executive Constn of Toilet including Flooring 2016 - Report 13 946/DP 27/03/2017 400000 Officer, 400000 400000 100 Yes at Bhedia Community Hall 2017 Wanting Ausgram- II P.S.

Executive Constn of Hatchala at Bishnupur 2016 - Report 14 946/DP 27/03/2017 400000 Officer, 400000 400000 100 Yes village under Ausgram 2017 Wanting Ausgram- II P.S. 167 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Executive Constn of Drain Palpukur toward 2016 - Report 15 2079/DP 25/07/2017 168300 Officer, 168300 168300 100 Yes Tulsey in Billwagram 2017 Wanting Ausgram- I P.S. Executive Constn of Busstand at Morebandh 2016 - Report 16 2173/DP 01/08/2017 500000 Officer, 500000 500000 100 Yes Mouza Chhora plot no. 1658 2017 Wanting Ausgram- II P.S. Executive Constn of Boundary wall at Jamtara 2016 - Report 17 2173/DP 01/08/2017 250000 Officer, 250000 250000 100 Yes BPHC of Bhalki G.P. 2017 Wanting Ausgram- II P.S. Constn of Community Hall at Parisha Executive Simultala, Mouza- Parisha, J.L. No. 2016 - Report 18 C- 2860/DP 29/11/2017 400000 Officer, 400000 400000 100 Yes 11, Plot No. 2024 under Ausgram- II 2017 Wanting Ausgram- II P.S. P.S Executive Constn of drain from Panja Pukur to 2016 - Report 19 3287/DP 13/12/2017 91600 Officer, 91600 91600 100 Yes P. Pals house at Belari of Billagram 2017 Wanting Ausgram- I P.S. Total 5997884 5997884 5997884 Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 20 Aushgram-II and Dighnagar (Jl-136, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Wanting Plot-6112) Burdwan.

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 21 Aushgram-II and Sitalgram, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Wanting Gangarampur, 3179 Burdwan. 168 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 22 Ausgram-II and Raghunathpur, Kota 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Wanting G.P. (Jl.-79, Plot-349) Burdwan.

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 23 Aushgram-I and Ramnagar, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Wanting Khanngar (Jl-44, Plot 202/209) Burdwan.

Constn. of Baitarani scheme at Exe. Engg. PWD 2017 - Report 24 Aushgram-II and Bhedia (Jl -88, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Wanting Dag-111, Plot-01) Burdwan. District Purchase An Ambulance for 2017 - Report 25 30/DP 04/01/2018 595204 Magistrate, 595204 595204 100 Yes Ausgram-II 2018 Wanting Burdwan Executive Constn of Siksha Charcha Kendra at 2017 - Report 26 145/DP 24/01/2018 300000 Officer, 300000 300000 100 Yes Amragarh under Ausgram-II 2018 Wanting Ausgram- II P.S.

Constn. of boundary wall of Executive 2017 - Report 27 Ramnagar PHC under Ramnagar 283/DP 24/01/2019 689106 Officer, 689106 689106 100 Yes 2018 Wanting G.P. within Ausgram-II P.S. Ausgram- II P.S.

Total 6034310 5879755 5879755 Constn. of Children Park and Executive beautification at Plot No. 2397 Jl-110 2018 - Report 28 2318/DP 01/10/2018 335000 Officer, 331167 331167 100 Yes Mouza-Guskara within Ausgram-I 2019 Wanting Ausgram- I P.S. PS. 169 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Beautification with Decorative LED Executive 2018 - Report 29 Light at Chandni Park (Phase-II) of 2212/DP 01/10/2018 300000 Officer, 288206 288206 100 Yes 2019 Wanting Dignagar-I G.P. Ausgram- I P.S.

Beautification with Decorative LED Executive Light at Chandni Park (Phase-I) of 2018 - Report 30 2212/DP 01/10/2018 300000 Officer, 298950 298950 100 Yes Dignagar-I G.P. within Ausgram-I 2019 Wanting Ausgram- I P.S. P.S. Constn. of Children Park and Executive beautification at Plot No. 2398 Jl-110 2018 - Report 31 2318/DP 01/10/2018 265000 Officer, 262282 262282 100 Yes Mouza-Guskara within Ausgram-I 2019 Wanting Ausgram- I P.S. PS. Constn. of Cultural centre at Executive Jadabganj Avarani FP School JL-104 2018 - Report 32 2318/DP 01/10/2018 300000 Officer, 297049 297049 100 Yes Plot-1539 Mouza-Jadabganj at 2019 Wanting Ausgram- I P.S. Dignagar-II within Ausgram-I PS.

Beautification of Chandni Park at Executive 2018 - Report 33 Chandni of Dignagar-I G.P. within 2212/DP 01/10/2018 260000 Officer, 258545 258545 100 Yes 2019 Wanting Ausgram-I P.S. Ausgram- I P.S.

Installation of Solar Light system Executive with all accessories at Chandni park 2018 - Report 34 2212/DP 01/10/2018 240000 Officer, 239040 239040 100 Yes at Dignagar-I GP. within Ausgram-I 2019 Wanting Ausgram- I P.S. P.S. 170 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Over Status

Beautification with Decorative LED Executive 2018 - Report 35 Light at Chandni Park (Phase-III) of 2212/DP 01/10/2018 300000 Officer, 283194 283194 100 Yes 2019 Wanting Dignagar-I G.P. Ausgram- I P.S.

Constn. of Atchala at Kalikapur Executive 2018 - Report 36 under Amarpur G.P. within 527/DP 18/02/2019 500000 Officer, 495000 495000 100 Yes 2019 Wanting Ausgram-II P.S. Ausgram- II P.S.

Total 2800000 2753433 2753433 Grand Total 14832194 14631072 14631072

171 ONGOING SCHEMES

172 ABHEDANANDA THANDER, HON'BLE MLA 273 AUSGRAM (SC) A.C.

Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess Constn. of Community Hall at Executive 75% work completed, 2018 - 1 Jamtara Gramin Club at Bhalki G.P. 2151/DP 20/08/2019 600000 Officer, 450000 0 0 No payment will be made 2019 under Ausgram-II P.S Ausgram- II P.S. within next week.

Solar system at Sajal Dhara prakalpa Executive 2018 - 2 at Kota Raghunathpur at Kota G.P. 3718/DP 24/09/2019 400000 Officer, 252000 0 0 No Work order issued. 2019 under Ausgram-II PS (1st Phase) Ausgram- II P.S.

Solar system at Sajal Dhara prakalpa Executive 2018 - 3 at Kota Raghunathpur (Phase-II) at 3717/DP 24/09/2019 400000 Officer, 252000 0 0 No Work order issued. 2019 Kota GP under Ausgram-II PS Ausgram- II P.S.

Constn. of Rest room at Maa Mati Executive 75% work completed, 2018 - 4 Park under Eral GP within Ausgram- 3764/DP 27/09/2019 500000 Officer, 375000 0 0 No payment will be made 2019 II PS Ausgram- II P.S. within next week.

Constn. of Community Hall at Executive 2018 - UC will submitted to 5 Nabagram Kaibartya para under 3920/DP 23/10/2019 400000 Officer, 397600 300000 75 No 2019 next week. Berenda G.P. within Ausgram-I P.S. Ausgram- I P.S.

Executive Upgradation of Sanhati Mancha 2018 - Payment will be made 6 3919/DP 23/10/2019 200000 Officer, 198800 150000 75 No (Meeting Hall) at Ausgram-I P.S. 2019 within next week. Ausgram- I P.S. 173 Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess Sinking of Submersible pump with drinking water supply at Tapuspure 2018 - Executive Officer, UC will submitted to 7 4001/DP 01/11/2019 200000 199980 150000 75 No under Debsala G.P. within Ausgram- 2019 Ausgram- II P.S. next week. II P.S.

Sinking of Submersible pump with 2018 - Executive Officer, UC will submitted to 8 drinking water supply at Debsala 4000/DP 01/11/2019 200000 199840 150000 75 No 2019 Ausgram- II P.S. next week. Dangapara within Ausgram-II P.S.

Sinking of Submersible pump with 2018 - Executive Officer, UC will submitted to 9 drinking water supply at Koucha 3998/DP 01/11/2019 200000 199900 150000 75 No 2019 Ausgram- II P.S. next week. Adibasipara within Ausgram-II P.S.

Total 3100000 2525120 900000

174 Hon’ble M.L.A. Shri Alok Kumar Majhi MLA 274 GALSI (SC) A.C.

175 COMPLETED SCHEMES

176 ALOK KUMAR MAJHI, HON'BLE MLA 274 GALSI (SC) A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Handed Over Name of the Scheme Year Executing Agency Submitte No. Order No Sanction Sanction Released Utilized Progress Status d Constn of CC Road at 2016 - Executive Officer, 1 Mollapara approach road of 2607/DP 09/11/2016 300000 300000 300000 100 Yes Report Wanting 2017 Galsi- I P.S. Kabarsthan at Budbud

Constn of Concrete Road approach to 2016 - Executive Officer, 2 2607/DP 09/11/2016 250000 250000 250000 100 Yes Report Wanting Narayanpur Junior High School 2017 Galsi- I P.S.

Constn of CC Road Gopaleswar Tala 2016 - Executive Officer, 3 to Ajay Mondal house of 2607/DP 09/11/2016 300000 300000 300000 100 Yes Report Wanting 2017 Galsi- I P.S. Ramgopalgram 1st Phase Constn of Concrete road at 2016 - Executive Officer, 4 Joykrishnapur Bagdipara at Kurkuba 2607/DP 09/11/2016 300000 300000 300000 100 Yes Report Wanting 2017 Galsi- II P.S. G.P.

Constn of BPHC Gate of at 2016 - Executive Officer, 5 2607/DP 09/11/2016 200000 158554 158554 100 Yes Report Wanting Adrahati G.P. 2017 Galsi- II P.S.

Constn of ACR at Basudebpur Upper 2016 - Executive Officer, 6 2645/DP 11/11/2016 500000 500000 500000 100 Yes Report Wanting Primary School 2017 Kanksa P.S.

Constn of Cycle Stand at 2016 - Executive Officer, 7 Ramgopalpur High School at Lowa 2844/DP 05/12/2016 200000 200000 200000 100 Yes Report Wanting 2017 Galsi- I P.S. Ramgopalpur High School 177 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitte No. Order No Sanction Sanction Agency Released Utilized Progress Status d

Executive Constn of Open Stage at Paraj HBM 2016 - 8 2844/DP 05/12/2016 200000 Officer, Galsi- I 200000 200000 100 Yes Report Wanting High School 2017 P.S.

Executive Constn of Boundary Wall new Setup 2016 - 9 2844/DP 05/12/2016 250000 Officer, Galsi- I 250000 250000 100 Yes Report Wanting Ramgopalpur Girls High School 2017 P.S.

Executive Constn of Cremation Shed at 2016 - 10 2844/DP 05/12/2016 250000 Officer, Galsi- I 250000 250000 100 Yes Report Wanting Nurkona Cremation Ground 2017 P.S.

Executive Constn of Cycle Stand at Jamdaha 2016 - 11 2844/DP 05/12/2016 200000 Officer, Kanksa 200000 200000 100 Yes Report Wanting School of Bidbihar G.P. 2017 P.S.

Constn of ACR with Cycle Stand at Executive 2016 - 12 Pursa High School at Potna Pursa 660/DP 02/03/2017 650000 Officer, Galsi- I 650000 650000 100 Yes Report Wanting 2017 G.P. P.S.

Constn of Cremation Shed at Executive 2016 - 13 Pandudaha Samsan Ghat at Lowa 660/DP 02/03/2017 250000 Officer, Galsi- I 250000 250000 100 Yes Report Wanting 2017 Krishnapur P.S.

Executive Repair of Puratan Gram High School 2016 - 14 660/DP 02/03/2017 100000 Officer, Galsi- I 100000 100000 100 Yes Report Wanting Building at Serorai G.P. 2017 P.S. 178 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Executive Constn of Asishu Uddyan Gate of 2016 - Report 15 884/DP 22/03/2017 150000 Officer, Galsi- II 150000 150000 100 Yes Galsi Bazar at Galsi G.P. 2017 Wanting P.S.

Constn of CC Road from G.Mondal Executive house to N. Bairagya house to 2016 - Report 16 1000/DP 30/03/2017 250000 Officer, Galsi- I 250000 250000 100 Yes Ramgopalpur Ghosh Para of Lowa 2017 Wanting P.S. Ramgopalpur 2nd ohase

Constn of Cremation Shed at Executive 2016 - Report 17 Mollasarul Malgore Samsan Ghat at 1085/DP 06/04/2017 250000 Officer, Galsi- I 250000 250000 100 Yes 2017 Wanting Serorai G.P. P.S.

Executive Constn of Atchala at 2016 - Report 18 1085/DP 06/04/2017 250000 Officer, Galsi- I 250000 250000 100 Yes Samshanghat at Mankar G.P. 2017 Wanting P.S. Executive Constn of Cremation Shed at 2016 - Report 19 1085/DP 06/04/2017 250000 Officer, Galsi- I 250000 250000 100 Yes Budbud Sadhunagar Samsanghat 2017 Wanting P.S. Executive Constn. of atchala at Uchchagram 2016 - Report 20 C- 1509/DP 24/05/2017 250000 Officer, Galsi- I 250000 250000 100 Yes G.P under Galsi- I P.SD (2nd Phase) 2017 Wanting P.S. Executive Constn of Gate of Galsi Samsan Ghat 2016 - Report 21 1975/DP 13/07/2017 150000 Officer, Galsi- II 99611 99611 100 Yes of Galsi at Galsi G.P. 2017 Wanting P.S. Total 5500000 5408165 5408165 179 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of Baitarani scheme at Galsi- Exe. Engg. PWD 2017 - 22 I and Galigram under Uchchagram 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes Report Wanting 2018 G.P. (Jl.-54, Plot.-5422, 11502) Burdwan.

Constn. of Baitarani scheme at Galsi- Exe. Engg. PWD 2017 - 23 I and Bhagabanpur Mouza, (Jl.-36, 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes Report Wanting 2018 Plot.-310, Kh.-184,238) Burdwan.

Exe. Engg. PWD Constn. of Baitarani scheme at Galsi- 2017 - 24 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes Report Wanting I and Ramgopalpur (Jl.-27, Plot.-496) 2018 Burdwan.

Constn. of Baitarani scheme at Galsi- Exe. Engg. PWD 2017 - 25 I and Ghagra Mouza (Jl.-30, Plot.- 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes Report Wanting 2018 2186, 2313) Burdwan.

Executive Constn of submersible for water 2017 - 26 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes Report Wanting resource at Mankar High School 2018 P.S.

Constn of submersible for water Executive 2017 - 27 resource at New Setup Ramgopalpur 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes Report Wanting 2018 Girls High School P.S.

Constn of submersible for water Executive 2017 - 28 resource at Budbud Mahakhali High 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes Report Wanting 2018 School P.S. 180 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn of submersible for water Executive 2017 - 29 resource at Lowa School at Lowa 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes Report Wanting 2018 Ramgopal G.P. P.S.

Executive Constn of Cremation Shed at 2017 - 30 2772/DP 30/10/2017 300000 Officer, Galsi- I 300000 300000 100 Yes Report Wanting Simasini Samsanghat at Serorai G.P. 2018 P.S.

Constn of concrete Ghat at Block Executive 2017 - 31 Krisak BazarFarm Pond of Mankatr 3228/DP 06/12/2017 300000 Officer, Galsi- I 300000 300000 100 Yes Report Wanting 2018 G.P. P.S. Exe. Eng. Constn of Baitoroni Scheme at 2017 - 215/DPC/P Asansol Divn 32 Kanksa Block Mouza Bonkati Jl No. 22/12/2017 890000 857672 857672 100 Yes Report Wanting 2018 SCHM Social Sector 33 plot No 371 PW Dte Executive Constn of Cycle stand at Mankar 2017 - 33 1332/DP 18/07/2018 250000 Officer, Galsi- I 250000 250000 100 Yes Report Wanting High School at Mankar G.P. 2018 P.S.

Upgradation of Morum Road and Executive 2017 - 34 Constn Concrete road from canal 1389/DP 26/07/2018 200000 Officer, Galsi- II 145340 145340 100 Yes Report Wanting 2018 Bandh to Ashram P.S.

Total 5900000 5683700 5683700 181 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of Corrugated Shed of Executive 2018 - 35 Ekalavya Model Residential School 132/DP 11/06/2019 1000000 Officer, Kanksa 804006 804006 100 Yes Report Wanting 2019 under Kanksa G.P. P.S.

Total 1000000 804006 804006 Grand Total 12400000 11895871 11895871

182 ONGOING SCHEMES

183 ALOK KUMAR MAJHI, HON'BLE MLA 274 GALSI (SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Executive Constn of Cremation shed at Railpar 2016 - Completed. Rest fund 1 792/DP 14/03/2017 250000 Officer, Kanksa 250000 160500 65 No Canel Samsanghat at Panagarh 2017 will be refunded P.S. Executive Constn of Atchala at Beldanga 2016 - Completed. Rest fund 2 792/DP 14/03/2017 250000 Officer, Kanksa 250000 160000 75 No Adibasipara under Kanksa 2017 will be refunded P.S. Total 500000 500000 320500

Upgradation of road and slab NH2 to Executive 2018 - UC will be sent 3 Amit Roy house at Galsi G.P. under 2537/DP 21/11/2018 55000 Officer, Galsi- II 41250 41250 75 Yes 2019 shortly. Galsi-II P.S. P.S.

Constn.of cement concrete road from Executive 2018 - UC will be sent 4 Kurie Sasan ghat to Sasan Chulli at 2537/DP 21/11/2018 150000 Officer, Galsi- II 112500 112500 75 Yes 2019 shortly. Galsi G.P. under Galsi-II P.S. P.S.

Constn. of boundary wall at Deypara Executive 2018 - UC will be sent 5 Graveyard at Kurkuba G.P. under 2537/DP 21/11/2018 210000 Officer, Galsi- II 208215 157500 75 No 2019 shortly. Galsi-II P.S. P.S.

Constn. of boundary wall at Executive 2018 - UC will be sent 6 Dayalpur Graveyard at Galsi G.P. 2537/DP 21/11/2018 200000 Officer, Galsi- II 150000 150000 75 Yes 2019 shortly. under Galsi-II P.S. P.S. 184 Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess Constn. of Boundary wall at Executive 2018 - UC will be sent 7 Darbarpur F.P. School at Galsi G.P. 2537/DP 21/11/2018 200000 Officer, Galsi- II 198300 150000 75 No 2019 shortly. under Galsi-II P.S. P.S. Installation of CCTV from NH2 to Executive Galsi Bazar (Fakir Ch. Roy Sarani) 2018 - UC will be sent 8 132/DP 11/01/2019 225000 Officer, Galsi- II 168750 168750 75 Yes via Galsi Sabji Market at Galsi under 2019 shortly. P.S. Galsi-II P.S. Constn. of pucca ghat at Executive 2018 - UC will be sent 9 Brindabanpur, Moralpukur at 2282/DP 28/08/2019 88842 Officer, Galsi- II 66632 0 0 No 2019 shortly. Kurkuba G.P. under Galsi-II P.S. P.S. Constn. of concrete cullvert with Executive 2018 - Rest fund will be 10 Hume Pipe at Pilgram Manasa Tala 2282/DP 28/08/2019 88904 Officer, Galsi- II 66678 0 0 No 2019 refunded of Kurkuba G.P. under Galsi-II P.S. P.S. Installation of High Mast Light on Executive plot no. 613/3913 mouza-Sukdal near 2018 - 11 824/DP 04/03/2020 379850 Officer, Galsi- I 284888 0 0 No Budbud Police Station within Galsi-I 2019 P.S. P.S. Installation of High Mast Light on Executive plot no. 8116 mouza-Mankar 2018 - 12 824/DP 04/03/2020 379850 Officer, Galsi- I 284888 0 0 No nearGalsi-I BDO office within Galsi- 2019 P.S. I P.S. Total 1977446 1582101 780000

Constn. of 10mtr. Mini High Mast 2019 - Prodhan, Galsi 1st phase U.C. 13 Light at near Uttar Galsi Cannel 4307/DP 28/11/2019 225000 224750 168562 0 No 2020 G.P. Submitted Bridge 3628 185 Physic UC Sl. Sanction Date of Amount Executing Amount Amount al Name of the Scheme Year Submitt Present Status No. Order No Sanction Sanction Agency Released Utilized Progr ed ess

Constn. of 10mtr. Mini High Mast 2019 - Prodhan, Galsi 1st phase U.C. 14 4307/DP 28/11/2019 225000 224480 168600 0 No Light at Galsi Sahapirtala plot-1041 2020 G.P. Submitted

Constn. of 10mtr. Mini High Mast 2019 - Prodhan, Galsi 1st phase U.C. 15 Light at Galsi Gargeshwar tala plot 4307/DP 28/11/2019 225000 224800 168600 0 No 2020 G.P. Submitted 6282/7065

Constn. of 10mtr. Mini High Mast 2019 - Prodhan, 1st phase U.C. 16 Light at Askaran Masjid tala plot no. 4306/DP 28/11/2019 225000 224950 168750 0 No 2020 Kurkuba G.P. Submitted 568

Constn. of 10mtr. Mini High Mast 2019 - Prodhan, 1st phase U.C. 17 Light at Joykrishnapur Paschimpara 4306/DP 28/11/2019 225000 224950 168750 0 No 2020 Kurkuba G.P. Submitted Kalitala

Total 1125000 1123930 843262 Grand Total 3545608 3206031 1100500

186 Thank You