Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Appendix B: Outstanding Florida Springs (OFS) BMAPs Table of Contents Introduction ...... 2 Jackson Blue Spring and Merritts Mill Pond BMAP ...... 5 BMAP ...... 11 BMAP ...... 37 and Springs BMAP ...... 45 Upper and Wakulla Springs BMAP ...... 91 , Rock Springs Run, and Little Wekiva Canal BMAP ...... 105

Page 1 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Introduction The Florida Springs and Aquifer Protection Act (Part VIII of Chapter 373, F.S.), provides for the protection and restoration of the state's OFS, which comprise 24 first magnitude springs, 6 additional named springs, and their associated spring runs. The act requires DEP to initiate an assessment by July 1, 2016, of any OFS or spring system for which a determination of impairment has not been made under the numeric nutrient criteria for spring vents.

In addition to the requirements of Section 403.067, F.S., the act provides specific requirements for OFS BMAPs, including an implementation plan designed with a target to achieve a TMDL no more than 20 years after adoption of the BMAP. These BMAPs provide for a phased implementation schedule (5-, 10-, and 15-year targets) designed to achieve incremental reductions within the first 15 years.

The act further specifies that a BMAP for an OFS must include the following provisions:

• The delineation of PFAs, to which statutory prohibitions on certain activities will apply.

• Identification of each point source or category of nonpoint sources and estimated pollutant loads within the springshed including, but not limited to: UTF, STF, agricultural fertilizer, OSTDS, which are also referred to as "septic systems" (the terms are used interchangeably throughout this document), WWTFs, animal wastes, and stormwater facilities.

• A list of all specific projects and programs identified to implement a nutrient TMDL.

o A priority rank, planning-level cost estimate, estimated completion date, and estimated nutrient load reduction for each listed project.

o The source and amount of financial assistance to be made available by DEP, a WMD, or other entity for each listed project.

• An OSTDS remediation plan if DEP identifies OSTDS as contributors of at least 20 % of the nonpoint source nitrogen pollution within a PFA, or if DEP determines remediation is necessary to achieve a TMDL.

o A list of all specific projects identified in an OSTDS remediation plan.

• A description of BMPs adopted by rule.

The tables in Appendix B list the implementation status of the BMAP projects as of December 31, 2017. The tables list the impairment reduction (in lbs/yr) attributable to each individual project. The list of projects is meant to be flexible enough to allow for changes that may occur

Page 2 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018 over time. During the annual review of BMAP implementation efforts, project-specific information may be revised and updated, resulting in changes to the estimated reductions for those projects. The revisions may increase or decrease estimated reductions, and DEP will work with stakeholders to address revisions as they are identified. The combination of the specific projects listed in Appendix B and the policies identified in the BMAPs is estimated to achieve the load reductions needed to meet the TMDL in 20 years. For BMAPs in Appendix B, DEP works in collaboration with Northwest Florida Water Management District (NWFWMD), St. Johns River Water Management District (SJRWMD), Water Management District (SRWMD), and Southwest Florida Water Management District (SWFWMD).

The project status column is standardized into the following four categories: • Canceled: Project or activity that was planned but will no longer take place. This includes the cessation of ongoing activities.

• Completed: Project, activity or task that is finished. This includes fully implemented activities (i.e., ongoing activities) that must continue indefinitely to retain assigned credits (such as street sweeping, BMP clean out, catch basin clean out, public education, fertilizer cessation/reduction and vegetation harvesting).

• Planned: Project or activity that is conceptual or proposed.

• Underway: Project or activity that has commenced or initiated but is not completed and is not yet reducing nutrient loads from the treated area.

Prior to reporting project information, DEP contacts each lead entity to gather new information on projects and confirm previously reported information. The terms used throughout the project tables are defined as follows:

• Not provided: Information was requested by DEP but was not provided by the lead entity.

• TBD: To be determined. Information is not currently available but will be provided by the stakeholder when it is available.

• N/A: Not applicable. Information for that category is not relevant to that project.

• 0: Zero. The numeric value for that category is zero.

These project tables are based on current information, and as further information becomes available project details may be updated. It is noted that while FDOT submits project information, there is no specific cost breakdown for water quality improvement projects, which are embedded into and implemented as part of larger transportation projects adopted in its Five- Year Work Program, pursuant to section 339.135, Florida Statutes.

Page 3 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

The management strategies in Appendix B are ranked with a priority of high, medium, or low. In 2016, the Florida Legislature amended the FWRA (Section 403.067, F.S.), creating additional requirements for all new or revised BMAPs. BMAPs must now include planning-level details for each listed project, along with their proposed priority ranking for implementation and funding needs. Project status was selected as the most appropriate indicator of a project's priority ranking based primarily on need for funding. Projects with a "completed" status were assigned a low priority. Projects classified as "underway" were assigned a medium priority because some resources have been allocated to these projects, but additional assistance may be needed for the project to be completed. High priority was assigned to projects listed with the project status "planned" as well as certain "completed" projects that are ongoing each year (any project with one of these project types: "street sweeping," "catch basin inserts/inlet filter clean out," "public education efforts," "fertilizer cessation," "fertilizer reduction," or "aquatic vegetation harvesting"), and select projects that are elevated because substantial, subsequent project(s) are reliant on their completion.

Page 4 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Jackson Blue Spring and Merritts Mill Pond BMAP

Background The Jackson Blue Basin encompasses 141 square miles in Jackson County, Florida (Figure B-1). Jackson Blue Spring, an OFS, forms the headwaters of the 270-acre Merritts Mill Pond, which forms the headwaters of Spring Creek, a tributary to the , an Outstanding Florida Water (OFW).

DEP determined that the Jackson Blue Spring segment, WBID 180Z, and Merritts Mill Pond, WBID 180A, were impaired by nitrate as nitrogen. In January 2013, DEP adopted a TMDL for nitrate to protect the aquatic flora and fauna in the spring and pond. To achieve the monthly average nitrate target of 0.35 mg/L in the Jackson Blue Basin, the nitrate loads from nonpoint sources need to be reduced by 90 %. The Jackson Blue BMAP was adopted in May 2016 to implement the nitrate TMDL in the watershed.

Status of Projects Through December 31, 2017, 2 projects have been completed. An additional 9 projects that are underway or planned have been added to the BMAP. The projects completed to date are estimated to achieve total reductions of 5,520 pounds of lb-N/yr. The projects that are underway are estimated to achieve total reductions of 3,294 lb-N/yr. These projects are primarily agricultural BMP and septic-to-sewer projects.

As an OFS BMAP, additional information will be provided when the BMAP reaches its 5-, 10-, and 15-year milestones. If the milestones or the 20-year target will not be met, an explanation of possible causes and potential solutions will be provided. These milestones will be specified in a revised BMAP document that is scheduled to be adopted by July 1, 2018, to meet the additional statutory requirements added by the 2016 Florida Legislature.

Page 5 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Figure B-1. Jackson Blue Spring and Merritts Mill Pond BMAP area

Page 6 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Table B-1. Jackson Blue BMAP projects

Estimated TN TP DEP Contract Project Project Project Project Completion Reduction Reduction Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Description Type Status Date (lb-N/yr) (lbs/yr) Location Acres Treated Cost Estimate O&M Source Amount Number DEP/ Northwest Indian Springs Convert 125 Wastewater Jackson Florida Water Sewer residential septic Jackson JC-01 Service Area Underway 2018 1,671 N/A Not provided $1,450,000 N/A DEP $1,450,000 S0866 County Management Extension systems to County Expansion District Phase 1 central sewer. (NWFWMD) Phase 2A includes Magnolia Blossom, Oak Indian Springs Dr., and part of Wastewater Jackson DEP/ Sewer Jackson JC-02 Seminole Dr. Service Area Planned TBD 695 N/A Not provided $2,000,000 N/A DEP $2,000,000 S0866 County NWFWMD Extension County segments Expansion Phase 2A (convert 89 residential systems to sewer). Provide central sewer service to Blue Springs Recreational Area and 74 homes in Blue Springs area. Project also Blue Spring includes Wastewater Jackson DEP/ Jackson JC-03 Rd. Sewer removing public Service Area Underway 2020 838 N/A Not provided $3,566,749 N/A DEP $3,566,749 LP01105 County NWFWMD County Extension park septic Expansion system at Jackson Blue Spring and providing sewer service to homes adjacent to Merritt's Mill Pond. Jackson Blue Spring BMP Jackson Stormwater Not Not Jackson N/A JC-04 Recreation Treatment Underway Not provided Not provided Not provided Not provided Not provided Not provided N/A County improvements. provided provided County Area Train Improvements Design and Jackson Blue construct Spring stormwater DEP – Recreation management Stormwater Jackson Jackson DEP/ $729,200 DEP/ Local JC-05 Area system to System Underway 2021 TBD N/A TBD $751,200 Not provided LP0110C County County Local Match Local – Stormwater capture and treat Upgrade $22,000 Improvement stormwater at Project Jackson Blue Spring. Project

Page 7 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Estimated TN TP DEP Contract Project Project Project Project Completion Reduction Reduction Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Description Type Status Date (lb-N/yr) (lbs/yr) Location Acres Treated Cost Estimate O&M Source Amount Number will also stabilize and restore 250 to 300 LF of shoreline. Landscape ordinance; Jackson Education Jackson N/A JC-06 Education implementation Completed 2017 120 N/A N/A N/A N/A N/A N/A N/A County Efforts County of FYN Program. Cost-share funding for agricultural BMPs and equipment to improve water Agricultural use efficiency DEP – DEP/ DEP/ BMPs and and reduce $4,239,500 S0676, S0809, Agricultural FDACS/ NWFWMD Agricultural. NWF-01 Equipment nutrient loading. Underway TBD TBD TBD Basinwide N/A $6,698,595 $0 Producers S0809 A1, BMPs Jackson Producers Cost-Share Assisted 50 Match – LP01106 SWCD Program producers $1,959,095 through 2017. 20 % reduction in TN reported. Cost estimate is cumulative since FY 2013–14. Fee-simple acquisition and Blue Springs protection of Land Jackson NWFWMD DEP NWF-02 Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Plantation, Inc. 394 ac adjacent Acquisition County to Jackson Blue Spring. Fee simple or less-than-fee acquisition and protection of Lakeshore 598 agricultural Land Jackson NWFWMD DEP NWF-03 Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Farms II, LLC acres in Jackson Acquisition County Blue groundwater contributing area. Less-than-fee acquisition and Pittman protection of Land Jackson NWFWMD DEP NWF-04 Property Land 167 agricultural Underway 2018 N/A N/A 167 $686,568 TBD DEP $686,568 S0900 Acquisition County Acquisition acres in Jackson Blue groundwater

Page 8 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Estimated TN TP DEP Contract Project Project Project Project Completion Reduction Reduction Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Description Type Status Date (lb-N/yr) (lbs/yr) Location Acres Treated Cost Estimate O&M Source Amount Number contributing area. Grants to producers to rotate sod in EPA/DEP – existing crop $480,032 EPA/ Sod-Based EPA/ DEP/ fields to improve Agricultural Jackson NWFWMD – NWFWMD Agricultural NWF-05 Crop Rotation Underway 2022 TBD N/A TBD $806,032 N/A Producers/ NF021 water quality BMPs County $256,000 Producers Grant Program NWFWMD and reduce water Producers – use demands $70,000 around Jackson Blue Spring. Apalachicola Implementation National Fish River and Bay and periodic and Wildlife Surface Water review and Apalachicola NWFWMD Foundation NWF-06 Improvement Study Completed 2017 N/A N/A N/A $99,290 N/A NFWF $99,290 N/A update of Watershed (NFWF)/ and Apalachicola Stakeholders Management SWIM Plan. (SWIM) Plan Testing of Claiborne aquifer in Jackson Blue Spring Claiborne contributing area NWFWMD DEP NWF-07 Aquifer Water Study Underway 2018 N/A N/A Malone N/A $440,000 $0 DEP $440,000 S0809 to determine Supply viability as alternative water source to offset demand on Floridan aquifer. Annual contract to support water quantity evaluations and Mobile FDACS/ retrofits with Agricultural Jackson NWFWMD NWF-08 Irrigation Underway TBD N/A N/A N/A $745,063 N/A NWFWMD $745,063 N/A NRCS producers across BMPs County Laboratory NWFWMD, but largely concentrated in Jackson County. Annual contract to provide education and Sod-Based outreach in Agricultural Jackson NWFWMD UF–IFAS NWF-09 Crop Rotation Underway TBD N/A N/A N/A $543,000 N/A NWFWMD $543,000 N/A NWFWMD BMPs County Education jurisdiction on sod-based crop rotation.

Page 9 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Estimated TN TP DEP Contract Project Project Project Project Completion Reduction Reduction Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Description Type Status Date (lb-N/yr) (lbs/yr) Location Acres Treated Cost Estimate O&M Source Amount Number BMPs implmented as Agricultural Agricultural Jackson NWFWMD NWF-10 BMPs part of WMD Completed 2014 5,400 N/A Not provided Not provided Not provided NWFWMD Not provided N/A Producers BMPs County FY 2013–14 funding cycle. Demonstration DEP – project for up to $480,032 DEP/ Sod-Based 4 sod farms to NWFWMD – DEP/ Agricultural Jackson NWFWMD/ UF–IFAS IFAS-01 Crop Rotation improve water Underway 2018 TBD TBD TBD $806,032 N/A $256,000 Not provided NWFWMD BMPs County Agricultural Pilot Project quality and Agricultural Producers quantity over 4- Producers – yr period. $70,000 Malone High Connect Malone School High School to Wastewater Town of DEP/ Jackson TM-01 Sanitary Sewer Malone WWTP, Service Area Underway 2020 90 N/A N/A $432,077 N/A DEP $432,077 LP0110D Malone NWFWMD County Connection abandoning 10 Expansion Project septic systems.

Page 10 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Rainbow Springs BMAP

Background The Rainbow Springs BMAP Basin covers an area of 679 square miles and includes portions of Marion and Levy Counties (Figure B-2). The BMAP area approximates the extent of the groundwater capture area determined by SWFWMD and includes the surface drainage for the Rainbow River. The eastern boundary of the BMAP area coincides with the western extent of the Silver Springs BMAP area and I-75.

DEP identified Rainbow Springs Group and the Rainbow Springs Group Run as impaired for nutrients because of an imbalance of flora and fauna evidenced by excessive algal growth and smothering of submerged aquatic vegetation (SAV). In 2013, DEP adopted the Rainbow Springs Group and Rainbow Springs Group Run TMDLs, which established a target concentration of 0.35 mg/L nitrate (NO3 as N) and an 82 % reduction in nitrate concentration for each impaired waterbody. The Rainbow Springs BMAP was adopted in December 2015 to implement the TMDLs.

Status of Projects Through December 31, 2017, 75 projects have been completed. An additional 10 projects that are underway or planned have been added to the BMAP. The projects completed to date are estimated to achieve total reductions of 40,720 lbs/yr of TN at the land surface.

Additional information will be provided when the OFS BMAP reaches its 5-, 10-, and 15-year milestones. If the milestones or the 20-year target will not be met, an explanation of possible causes and potential solutions will be provided. These milestones will be specified in a revised BMAP document. The revised Rainbow Springs BMAP is scheduled to be readopted by July 1, 2018, to meet the statutory requirements added by the 2016 Florida Legislature.

Page 11 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Figure B-2. Rainbow Springs BMAP area

Page 12 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Table B-2. Rainbow Springs BMAP Projects DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number TDR Program is designed to protect natural resources, especially those listed in Policy 1.1.2 of Conservation Element of Marion County Comprehensive Plan and locally important and prime farmlands in Marion County. These resources include, but are not Rainbow Marion County limited to, preservation of high- Spring Marion County Transfer of Not Not Not N/A B001 water recharge and underground Study Completed N/A N/A Basin, Silver N/A N/A Not provided N/A Growth Services Development Rights provided provided provided drainage basins, springs, karst Spring (TDR) areas, sinkholes, sinks, sinkhole Basin ponds, and other karst features. Land from which development rights are transferred is subject to conservation easement. Article 3 of Land Development Code (LDC) defines TDR Program and eligible sending and receiving areas. TVR Program is designed to minimize dense development of vested properties without central water and sewer systems, and/or other supporting infrastructure, and thus protect natural resources, encourage and Rainbow enhance development of larger Marion County Spring Marion County parcels, reduce county's Not Not Not N/A B002 Transfer of Vested Study Completed N/A N/A Basin, Silver N/A N/A Not provided N/A Growth Services inventory of vested properties, provided provided provided Rights (TVR) Spring and permit county to better plan Basin for future growth. Land from which vested rights are transferred is subject to conservation easement. Article 3 of LDC defines TVR Program and eligible sending and receiving areas.

Page 13 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Comprehensive Plan Future Land Use Element Policy 2.1.13 establishes Hamlet Development Option, designed to provide for clustered low- density development patterns in rural designated lands, while requiring permanent open spaces reserved from Rainbow Marion County development and some Spring Marion County Not Not Not N/A B003 Hamlet Design increased additional urban Study Completed N/A N/A Basin, Silver N/A N/A Not provided N/A Growth Services provided provided provided Option services (e.g., central water, Spring central sewer, designed/ Basin constructed stormwater systems) that comply with Marion County's design and development standards, including Springs Protection. Article 3 of LDC generally defines Hamlet design provisions. Comprehensive Plan Future Land Use Element Policy 2.1.18 establishes Rural Community future land use designation to provide for clustered urban density development patterns in rural designated lands, while requiring permanent open Rainbow Marion County spaces reserved from Spring Marion County Rural Community development and complete Not Not Not N/A B004 Study Completed N/A N/A Basin, Silver N/A N/A Not provided N/A Growth Services Land Use urban services (e.g., central provided provided provided Spring Designation water, central sewer, and Basin designed/constructed stormwater systems) that comply with Marion County's design and development standards, including Springs Protection. Article 3 of LDC generally defines Rural Community design provisions. Comprehensive Plan Future Land Use Element Objective 2.2 Rainbow Marion County establishes specific limited Spring Marion County Community density and specialized design Not Not Not N/A B005 Study Completed N/A N/A Basin, Silver N/A N/A Not provided N/A Growth Services Redevelopment standards for wetland and provided provided provided Spring Area Program floodplain areas slated for Basin development. Articles 5 and 6 of LDC set forth specific design

Page 14 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number and development criteria related to applicable areas. Comprehensive Plan Future Land Use Element Objective 7.2 establishes Springs Protection Overlay Zones (SPOZ) and Rainbow Marion County identifies extent of Primary and Spring Marion County Not Not Not N/A B006 Springs Protection Secondary Zones along with Study Completed N/A N/A Basin, Silver N/A N/A Not provided N/A Growth Services provided provided provided Zones other design and development Spring standards. Articles 5 and 6 of Basin LDC set forth specific design and development criteria related to applicable SPOZ. Ordinance sets enforceable Rainbow irrigation schedule and rates of Regulations, Marion County Spring Marion County irrigation for Marion County; Ordinances, Not Not Not Office of the N/A B007 Completed N/A N/A N/A Basin, Silver N/A Marion County N/A Irrigation Ordinance also identifies efficient irrigation and provided provided provided County Engineer Spring systems that are exempt from Guidelines Basin schedule. County's Florida-Friendly Landscaping™ (FFL) fertilizer use on urban landscapes ordinance regulates proper use of fertilizers by any applicator; requires proper training of commercial and institutional fertilizer applicators; establishes training and licensing Rainbow Regulations, Marion County requirements; and specifies Spring Marion County Ordinances, Not Not Not Office of the N/A B008 allowable fertilizer application Completed N/A N/A N/A Basin, Silver N/A Marion County N/A Fertilizer Ordinance and provided provided provided County Engineer rates and methods, fertilizer-free Spring Guidelines zones, low-maintenance zones, Basin and exemptions. It requires use of BMPs that provide specific management guidelines to minimize negative secondary and cumulative environmental effects associated with misuse of fertilizers. 2008 ordinance is now included in latest LDC. Covers silviculture lands in Rainbow and Silver Springs BMAP areas. BMPs for Rainbow silviculture are applicable to Silviculture BMP Spring Florida Forest public and private industrial and Agriculture Not Not Not N/A B009 Implementation and Completed N/A N/A N/A Basin, Silver N/A Not provided N/A Service nonindustrial forestlands. BMPs provided provided provided Compliance Spring Silviculture BMPs are minimum Basin standards for protecting and maintaining water quality during ongoing silviculture activities,

Page 15 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number including forest fertilization. Projects include biennial BMP surveys, targeted training, and technical assistance for landowners and forestry professionals. Clean Farms Initiative was designed to assist Marion County farm owners and managers with implementation of BMPs, and to recognize them for their cooperative efforts. As part of initiative, more than 7,500 surveys and brochures were mailed in October 2006 to owners of agricultural land, ranging from large operations of Rainbow Marion County several hundred acres to small Spring Clean Farms Agriculture Not Not Not Office of the N/A B010 tracts of land with fewer than a Completed N/A N/A N/A Basin, Silver N/A Not provided N/A Initiative BMPs provided provided provided County Engineer dozen animals. Survey measures Spring current manure management and Basin fertilization practices. Results of survey, and input from groups held in February and March 2007, were used to create Farm Outreach Coordinator position to educate horse farm owners and managers on water quality, targeting practices such as manure management and fertilization. Equine BMPs and Manure Management Education and Outreach Program sponsored by UF–IFAS Extension and Marion County. Between 2010 and 2013, program developed 44 Rainbow types of educational materials; UF–IFAS Water Quality Spring SWFWMD/ made 3,507 client consultations, Agriculture Not Not Not Extension Marion B011 Education and Completed N/A N/A N/A Basin, Silver N/A UF–IFAS N/A UF–IFAS 464 of which were in field; and BMPs provided provided provided County Equine Farm BMPs Spring 301 producers participated in Basin group education events including manure management summit and tour. Program website received 446 views during this period. Program is ongoing.

Page 16 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Small Equine BMP manual is intended to educate owners of noncommercial horse farms on BMPs to reduce nutrient loads. Outreach program will be developed for effective implementation of BMPs on noncommercial horse farms in Silver and Rainbow Springs BMAP areas. Implementation Rainbow Implementation of program will consist of Spring Outreach Program identification of key agencies Agriculture Not Not Not DEP TBD B012 Completed N/A N/A N/A Basin, Silver N/A Not provided N/A for Small Equine with existing public education BMPs provided provided provided Spring BMP Manual activities where BMP manual Basin can be incorporated, development or modification of existing recognition programs to provide measureable goals for both participants and also types of BMPs implemented, and identification of existing cost- share programs that may assist noncommercial operations in BMP implementation. 238719-1, SR 40 from CR 328 WBID State Road (SR) 40 to SW 80th Ave. (CR 225A) – Retention 1320A – Not Not Florida Not FDOT District 5 N/A B022 Design Project – Underway 2020 12 2 9.0 N/A Pond 3/dry retention; closed BMP Outside provided provided Legislature provided Pond 3 basin in poorly drained soils. PFA 238719-1, SR 40 from CR 328 WBID SR 40 Design to SW 80th Ave. (CR 225A) – Retention 1320A – Not Not Florida Not FDOT District 5 N/A B023 Underway 2020 16 2 12.5 N/A Project – Pond 4 Pond 4/dry retention; closed BMP Outside provided provided Legislature provided basin in poorly drained soils. PFA 238719-1, SR 40 from CR 328 WBID SR 40 Design to SW 80th Ave. (CR 225A) – Retention 1320A – Not Not Florida Not FDOT District 5 N/A B024 Underway 2020 14 2 10.9 N/A Project – Pond 5 Pond 5/dry retention; closed BMP Outside provided provided Legislature provided basin in poorly drained soils. PFA 238719-1, SR 40 from CR 328 WBID SR 40 Design to SW 80th Ave (CR 225A) – Retention 1320A – Not Not Florida Not FDOT District 5 N/A B025 Underway 2020 12 2 9.3 N/A Project – Pond 6 Pond 6/dry retention; closed BMP Outside provided provided Legislature provided basin in poorly drained soils. PFA Construction of drainage retention area lined with Bold Marion County Retention and Gold™ soil amendment to WBID Stormwater Marion County SW 85th St./ BMP with enhance nitrogen removal. Post- 1320A – Not Assessment, Not Office of the SWFWMD B028 SW 40th Ave. Nutrient- Completed 2012 98 N/A 32.0 $330,000 N/A construction event monitoring Outside provided SWFWMD provided County Engineer Stormwater Retrofit Reducing has shown 70 % reduction in PFA Cooperative Media TN through soil amendment Funding layer.

Page 17 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Proposed project to construct wet retention area to reduce nitrate in stormwater runoff Marion County West Hwy. 316 at from transportation and WBID Stormwater Marion County 119th Ave. residential land uses that is Retention 1320A – Not Assessment, Not Office of the SWFWMD B029 Completed 2016 29 0 55.6 $52,654 N/A Stormwater currently infiltrating to aquifer BMP Outside provided SWFWMD provided County Engineer Retrofit- CP #41 without treatment. Project is PFA Cooperative identified in adopted 2014 Funding Stormwater Implementation Plan. Proposed project to construct retention area to reduce nitrate in stormwater runoff from WBID Marion County West Hwy. 316 at transportation and residential Retention 1320A – Office of the N/A B030 Hwy. 329 land uses that is currently Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A BMP Outside County Engineer Stormwater Retrofit infiltrating to aquifer without PFA treatment. Project is identified in adopted 2014 Stormwater Implementation Plan. Marion County: Annual Stormwater Budget for Internal Repairs Part of ongoing stormwater WBID – $50,000; Marion County Sinkhole Repair system maintenance activities. Stormwater 1320A – Typical Annual Not Office of the N/A B032 Program in County Performed as needed by county System Completed N/A N/A N/A N/A N/A $50,000 N/A including Expenditure for provided County Engineer DRAs crews or contractors depending O&M PFA Contracted on size and scope of repair. Repairs from Stormwater Budget – $10,000 to $100,000 Sweeping of Marion County– maintained roads. Sweeping of roads with curb and gutter is WBID Marion County Street Sweeping of Marion County completed 9 times per year. Street 1320A – Not Office of the N/A B033 Marion County Completed N/A 194 124 N/A N/A $46,000 Stormwater N/A Benefits: Remove debris, Sweeping including provided County Engineer Roads Assessment sediment, and potential PFA pollutants from streets. Prevent entry into storm sewer system. Countywide WMPs prepared that include creation and Marion County WBID Marion County Marion County maintenance of comprehensive Watershed 1320A – Stormwater Not Office of the SWFWMD B034 geodatabase for Marion County Study Completed N/A N/A N/A N/A $337,000 N/A N/A Management Plan including Assessment/ provided County Engineer storm sewer system data, (WMP) PFA SWFWMD watershed boundaries, and hydrologic features.

Page 18 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Identification of vulnerable areas of aquifer. Project provided scientifically defensible water resource management and protection tool that facilitates planning of human activities to help minimize adverse impacts on groundwater quality. Aquifer vulnerability maps are displayed in classes of relative vulnerability (one area is more Marion County WBID Marion County vulnerable than another). Maps Marion County Aquifer 1320A – Office of the N/A B035 benefit local government, Study Completed 2007 N/A N/A N/A $82,850 N/A Stormwater $82,850 N/A Vulnerability including County Engineer planners and developers in Assessment Assessment PFA guiding growth into more appropriate areas (e.g., groundwater recharge areas) and improve site selection for expanding existing or establishing new well fields. Benefits: Identifies areas where aquifer is vulnerable to pollution. Potential for future management of activities in those areas to reduce groundwater pollution. Formation of public education coordination team consisting of representatives from local government, state agencies, Local, State and WMDs, and local interest WBID Marion County Federal Public Education groups. Purpose of groups Education 1320A – Not Not Not Office of the Not provided B036 Completed N/A N/A N/A N/A Agencies/ N/A Coordination would be to ensure consistent Efforts including provided provided provided County Engineer WMDs/ Local and accurate information on PFA Interest Groups pollution prevention is provided to citizens and maximize efforts among coordination team members. Public outreach and education programs including distribution of informational pamphlet, Marion County PSAs, and public outreach WBID Marion County Marion County Stormwater events. Other efforts include Education 1320A – Not Not Office of the N/A B037 Completed N/A N/A N/A N/A $3,500,000 Stormwater N/A Program – NPDES illicit discharge inspection and Efforts including provided provided County Engineer Assessment MS4 Permit education, mapping and PFA modeling efforts, construction site pollution prevention program, and pollution

Page 19 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number prevention program for municipal operations. FDOT conducts inspections and WBID provides annual illicit discharge, FDOT Districts 2 FDOT Public Education 1320A – Not Not Florida Not N/A B038 spill prevention and erosion and Completed N/A N/A N/A N/A N/A and 5 Education Efforts including provided provided Legislature provided sediment control training to staff PFA and contractors. Workshop for Marion County teachers and educators to WBID provide resources on springs, SWFWMD/ Rainbow River Springs Awareness Education 1320A – Not Not Not N/A B039 water issues, and wildlife that Completed N/A N/A N/A N/A Florida Springs N/A Conservation for Educators Efforts including provided provided provided can be used in classroom to Institute PFA enhance teaching common core standards. Proposed project to construct centralized collection center for septic tank pumpage in lieu of Rainbow current land application. Wastewater Collection Center River Basin Collection center would process Service Private Interest N/A B040 for Septic System Canceled N/A N/A N/A and Silver N/A N/A N/A N/A N/A N/A pumpage and discharge into Area Pumpage Spring municipal collection system. Expansion Basin Project is conceptual. SB 550 would ban land application of septic pumpage effective 2016. FDACS will provide at least WBID FDACS Cost-Share $250,000 in BMP cost-share for Agriculture 1320A – Not Not FDACS Cost- Not FDACS N/A B041 Underway 2020 N/A N/A N/A N/A Programs Silver Springs/Rainbow Springs BMPs including provided provided Share provided BMAP areas. PFA To help focus cost-share expenditures and BMP implementation follow-up, WBID FDACS Refinement FDACS will review rule- Agriculture 1320A – Not Not Not FDACS N/A B042 of Appropriate Underway 2020 N/A N/A N/A Not provided N/A adopted cow/calf and equine BMPs including provided provided provided BMPs BMPs to identify practices PFA likely to have greatest nutrient load reduction benefits. Formation of technical agriculture committee consisting of representatives from local interest groups, local WBID UF–IFAS Technical government, WMDs, and state Agriculture 1320A – Not Not Not Extension Marion N/A B043 Agriculture agencies. Purpose of the group Underway 2020 N/A N/A N/A Not provided N/A BMPs including provided provided provided County Committee would be to ensure consistent PFA and accurate information for pollutant load contribution associated with agricultural uses and evaluate BMP effectiveness.

Page 20 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number As part of BMAP, inventories have been developed to estimate relative nitrogen loading from different sources or categories of land use in basins. Concerns have been expressed that amount of nitrogen load allocated to cattle may not accurately reflect key characteristics of Florida cow- calf production system. Issues include typical cattle stocking rates on pasture, low inputs of commercial nitrogen fertilizer to pasture systems, diets that based Assessment of Role on C4 (i.e., warm climate) WBID UF–IFAS of Beef Cattle in grasses that have relatively low 1320A – Florida Not Extension Marion N/A B044 Nitrogen Loading in nitrogen concentration, nitrogen Study Underway 2019 N/A N/A N/A $495,000 N/A N/A including Legislature provided County Silver and Rainbow levels in dung and urine that are PFA Springs Basin not comparable to those of dairy animals or beef cattle on feedlots, significant gaseous losses of nitrogen from animal waste, capability of grass roots to efficiently capture nitrogen as it passes through rooting zone, and amount of nitrogen stored in below-ground organs of pasture grasses. More accurate quantification of these characteristics for specific conditions of regional production systems will aid assessments of nitrogen loading from cattle operations. In 2015, FDACS Office of Agricultural Water Policy (OAWP) adopted revised vegetable and agronomic crop WBID Revised Vegetable manual that includes specific Agriculture 1320A – Not Not Not FDACS N/A B045 and Agronomic Completed 2015 N/A N/A N/A Not provided N/A nutrient and irrigation BMPs including provided provided provided Crop BMP Manual management BMPs for plastic PFA mulch, bare ground, sugar cane, hay/silage, and greenhouse production systems. In early 2016, FDACS adopted WBID dairy manual targeting dairies Agriculture 1320A – Not Not Not FDACS N/A B046 Dairy BMP Manual Completed 2016 N/A N/A N/A Not provided N/A without DEP-issued NPDES BMPs including provided provided provided permits. PFA

Page 21 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number WBID Poultry BMP OAWP adopted poultry BMP Agriculture 1320A – Not Not Not FDACS N/A B047 Completed 2016 N/A N/A N/A Not provided N/A Manual manual in June 2016. BMPs including provided provided provided PFA Additional emphasis was given to IA in 2016 legislation, particularly Chapter 2016-1, Laws of Florida. Among its provisions, law requires enhancement and formalization of OAWP IA policies and procedures through rulemaking, which will be initiated prior to January 1, 2017. Once rulemaking is completed, FDACS will implement enhanced IA Program and more detailed reporting, as prescribed by legislation, onsite visits, and surveys will be provided annually. Enhanced IA Program, as component of FDACS BMP Enhanced Program, will be designed to: WBID Implementation • Provide accurate and timely Agriculture 1320A – Not Not Not FDACS N/A B048 Underway 2018 N/A N/A N/A Not provided N/A Assurance (IA) information on status of BMP BMPs including provided provided provided Program enrollments. PFA • Provide accurate and timely information on extent of BMP implementation. • Provide information from which reports on BMP enrollment and implementation can be made to BMAP stakeholders and to annual report required by Chapter 2016-1, Section 34, Laws of Florida. • Inform educational, research, and technical assistance efforts targeted to strengthen BMP implementation and effectiveness. • Guide review and potential revision of BMP manuals. Project objective is to design Septic Tank Rainbow and construct sanitary sewer Phase Out, Springs Fox Meadow Sewer system that will remove from Wastewater Basin and Not Not Not City of Ocala N/A B049 Planned 2020 TBD N/A N/A $4,705,000 City of Ocala Expansion Project service 275 septic tanks from Service Silver provided provided provided associated single-family Area Springs residential lots. Septic tanks Expansion Basin

Page 22 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number contribute to TN and TP impairment of Rainbow Springs and Rainbow River. Project objective is to design and construct sanitary sewer Package Rainbow system to remove from service Plant Phase Springs Fairfield Village package plant serving 350 Out, Basin and Not Not City of Ocala N/A B050 Sewer Expansion mixed-use residential lots and 1 Wastewater Planned 2020 TBD N/A N/A $875,000 N/A City Silver provided provided Project community center. Package Service Springs plant contributes to TN and TP Area Basin impairment of Rainbow Springs Expansion and Rainbow River. Project objective is to design and construct sanitary sewer Septic Tank Rainbow system that will remove from Phase Out, Springs service 180 septic tanks from Timberwood Sewer Wastewater Basin and Not Not Not City of Ocala N/A B051 associated single-family Planned 2020 TBD N/A N/A $3,316,000 City Expansion Project Service Silver provided provided provided residential lots. Septic tanks Area Springs contribute to TN and TP Expansion Basin impairment of Rainbow Springs and Rainbow River. City of Dunnellon River Protection Corridor Areas for both Rainbow and Withlacoochee Rivers. Corridor Regulations, extends 150 ft from ordinary Rainbow River Protection Ordinances, Not Not Not City of Dunnellon N/A R001 high-water line and implements Completed N/A N/A N/A Spring N/A Marion County N/A Corridors and provided provided provided specific standards for new Basin Guidelines development and for construction on existing lots with vested development rights after 2008. Rainbow River Corridor project will protect most undeveloped or minimally developed private land remaining along Rainbow River. Southern parcels would bring remaining large portion of undeveloped shoreline along eastern side of river into state Rainbow DEP – Division of Rainbow River ownership and provide Land Not Not FCT R002 Completed N/A N/A N/A Spring 1,175.0 $1,157,483 FCT N/A State Lands Corridor connection to southern end of Acquisition provided provided Basin Rainbow Springs State Park. Public acquisition will prevent further development and conflicting land uses that could further degrade ecological value of this area. In addition, potential restoration of altered habitats will help restore and

Page 23 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number maintain water quality and habitat along one of Florida's largest spring-run streams; 1,140 ac remain for acquisition, which will continue as funds and sales agreements allow; 32.44 ac were acquired for Blue Run of Dunnellon Park (R013) in 2008. Project to construct retention pond with control structure and pipe conveyance system to treat WBID Blue Cove and convey flood overflows Retention Not 1320B – Not Not Not Not City of Dunnellon SWFWMD R003 Emergency from Blue Cove to Rainbow Completed 2011 N/A City N/A BMP provided Outside provided provided provided provided Overflow Project River. Prior to construction, PFA overflows sheet flowed through residential neighborhood to river. Project retrofitted car and boat WBID Datesman Park trailer overflow parking lot with Retention Not 1320B – Not Not Not Not City of Dunnellon N/A R004 Overflow Parking Completed 2010 N/A City N/A pervious pavers and stormwater BMP provided Outside provided provided provided provided Lot Improvement retention pond. PFA Retrofit of existing drainage retention area with aerobic filtration cells for conversion of Wetland WBID County Marion County Village of Rainbow TN to nitrate and infiltration cell Treatment, 1320A – Not Stormwater Not Office of the SWFWMD R011 Springs Stormwater lined with Bold and Gold™ for Retention Completed 2015 29 N/A 91.0 $336,800 N/A Outside provided Assessment, provided County Engineer Retrofit nitrate removal. Project also BMP with PFA SWFWMD includes stormwater wetland to Media Filter treat runoff discharged into Section 16 lake. Construction of bioretention WBID County Marion County CR 484 Stormwater area and collection system to Retention 1320B – Not Stormwater Not Office of the SWFWMD R012 Completed 2010 5 1 0.5 $62,081 N/A Retrofit, Phase 1 treat runoff from bridge BMP Outside provided Assessment, provided County Engineer spanning Rainbow River. PFA SWFWMD Construction of wet detention WBID County Marion County Wet CR 484 Stormwater pond to treat runoff discharged 1320B – Not Stormwater Not Office of the SWFWMD R013 Detention Completed 2012 48 11 18.6 $73,890 N/A Retrofit, Phase 2 into Rainbow River from CR Outside provided Assessment, provided County Engineer Pond 484. PFA SWFWMD Upgrade limerock parking lot in Blue Run of Dunnellon Park with pervious brick paver County SWFWMD, parking area and paved aisles to WBID Marion County Wet Stormwater Marion County CR 484 Stormwater address sediment discharge into 1320B – Not Not Office of the R014 Detention Completed 2011 6 1 2.7 $223,700 Assessment, N/A Parks, City of Retrofit, Phase 3 Rainbow River. Three wet Outside provided provided County Engineer Pond County Parks, Dunnellon detention ponds were PFA SWFWMD constructed to treat stormwater runoff form new parking lot and CR 484 east of Rainbow River.

Page 24 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Expansion and conversion of existing retention pond to Rainbow Springs County Marion County wetland/wet retention pond to WBID Country Club Wetland Not Stormwater Not Office of the SWFWMD R015 enhance nitrate removal from Completed 2012 10 N/A 1320A – In 61.7 $136,423 N/A Estates Stormwater Treatment provided Assessment, provided County Engineer runoff generated from county PFA Retrofit SWFWMD road, golf course, and residential land uses. Construction of 3 wet detention WBID County Marion County Rainbow Park Unit Wet ponds to treat runoff prior to 1320A – Not Stormwater Not Office of the SWFWMD R016 8 Stormwater Detention Completed 2013 42 8 79.0 $443,399 N/A discharge to relict karst feature Outside provided Assessment, provided County Engineer Retrofit Pond and isolated surface wetlands. PFA SWFWMD Construction of interconnected system of 4 retention ponds and WBID County Marion County BMP Rolling Hills Unit 5 1 wet retention pond to treat 1320A – Not Stormwater Not Office of the SWFWMD R017 Treatment Completed 2013 69 33 224.0 $484,097 N/A Stormwater Retrofit stormwater runoff from roads, Outside provided Assessment, provided County Engineer Train residential, and agricultural land PFA SWFWMD uses. WR01 Rainbow Implementation of restoration WBID River Phosphate alternatives in Lower Rainbow SWFWMD N/A R018 Restoration Canceled N/A N/A N/A 1320B – In N/A N/A N/A N/A N/A N/A Mine Pit River and adjacent phosphate PFA Restoration mine pits. Septic Tank Project constructed new sewer Phase Out, WBID system within city limits Sewer Conversion Wastewater 1320A – Not Not Not Not City of Dunnellon Not provided R019 allowing properties previously Completed 2012 3,347 N/A N/A Not provided Project, Phases 1-4 Service Outside provided provided provided provided on OSTDS (140 in Phase 2) to Area PFA hook up to central sewer. Expansion P301 Feasibility WBID Siting and feasibility assessment Phase – Wastewater Not 1320A – Not Not Not Not SWFWMD Not provided R020 for treatment wetlands to polish Study Completed 2015 N/A N/A Not provided Disposal Treatment provided including provided provided provided provided WWTP effluent. Wetlands PFA WBID FDOT Districts 2 Fertilizer 1320A – N/A R021 Fertilizer Cessation FDOT O&M fertilizer cessation. Completed N/A 10,285 N/A N/A N/A N/A N/A N/A N/A and 5 Cessation including PFA Includes hydrologic and hydraulic model and water WBID Marion quality treatment 1320A/B – City of Dunnellon County, R022 Dunnellon WMP recommendations for 9 Study Completed 2004 N/A N/A N/A $50,000 N/A City $50,000 N/A Outside SWFWMD stormwater discharge outfalls to PFA Rainbow and Withlacoochee Rivers. WR01 Rainbow Feasibility study to assess WBID River Phosphate restoration alternatives in lower 1320A – SWFWMD N/A R023 Study Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Mine Pit Feasibility Rainbow River and adjacent including Study phosphate mine pits. PFA Florida Efficient Irrigation Community presentations on Education WBID SWFWMD Irrigation R024 Completed 2005 N/A N/A N/A $2,500 N/A SWFWMD $2,500 N/A Workshops efficient irrigation practices. Efforts 1320A – Society

Page 25 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number including PFA UF; Charlotte, FFL Program educates Citrus, homeowners about how to Hernando, design, install and maintain Hillsborough, healthy landscapes that use WBID Manatee, minimal amounts of water, Education 1320A – SWFWMD R025 FFL Coordinator Completed N/A N/A N/A N/A $279,000 N/A SWFWMD $279,000 N/A Marion, Pasco, fertilizer, and pesticides. Efforts including Pinellas, Polk, SWFWMD funds programs in PFA Sarasota, and 11 of its 16 counties in Sumter partnership with county Counties governments and university. PSAs to promote SWFWMD "Restoring Our Springs!" media WBID Restoring Our campaign. Advertising will be in Education 1320A – SWFWMD N/A R026 Springs! Media Citrus, Hernando and Marion Completed 2016 N/A N/A N/A $35,698 N/A SWFWMD $35,698 N/A Efforts including Campaign Counties and will direct people PFA to "Join us in the community effort to restore our springs." In-depth look at springs in west- central Florida through Newspaper in Education Newspaper in WBID produced by Times. Education: Springs Education 1320A – SWFWMD N/A R027 Distributed to middle school Completed 2014 N/A N/A N/A $16,600 N/A SWFWMD $16,600 N/A in West-Central Efforts including students in Citrus, Hernando, Florida PFA and Marion Counties as well as Tampa Bay Times and Citrus County Chronicle readers. Messaging on how residents can / help protect quality of local WBID King's Bay/ springs through proper Education 1320A – SWFWMD N/A R028 Completed 2011 N/A N/A N/A $83,641 N/A SWFWMD $83,641 N/A Rainbow River application of fertilizer. Social Efforts including PSAs research was used to help PFA develop messages. Education effort to reduce water quality impacts from landscaping and other homeowner practices—such as overfertilization and leaking Crystal River/ OSTDS—that increase nitrates WBID King's Bay/ in springs. Targeted Education 1320A – SWFWMD N/A R029 Rainbow River Completed 2011 N/A N/A N/A $82,600 N/A SWFWMD $82,600 N/A homeowners, landscape Efforts including Outreach professionals, retail outlets, PFA Coordinator OSTDS maintenance companies and others. Included education effort entitled, "You want your lawn green, not your water. Don't overfertilize."

Page 26 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Event to educate public on protection of Marion County WBID Marion County springs and other water Education 1320A – SWFWMD N/A R030 Springs Festival resources. Event alternates Completed 2016 N/A N/A N/A $25,598 N/A SWFWMD $25,598 N/A Efforts including Sponsorship between Rainbow Springs State PFA Park and Silver Springs State Park. Festival supporting FFL Marion County WBID outreach and education Master Gardeners Education 1320A – SWFWMD N/A R031 including focus on water Completed 2011 N/A N/A N/A $30,750 N/A SWFWMD $30,750 N/A Spring Festival Efforts including conservation, watersheds, and Sponsorship PFA water quality. One-day workshop taught Howard T. Springs Awareness participants about water quality WBID Odum Florida Week – Springs issues specific to Rainbow Education 1320A – SWFWMD R032 Completed 2011 N/A N/A N/A $3,000 N/A SWFWMD $3,000 N/A Springs Neighborhood Springs and Crystal River/Kings Efforts including Institute Challenge Bay. Main focus was proper PFA fertilizer application. Guided canoe trip, hiking trip, and water quality demonstration Marion County WBID Get Out and Explore to educate residents about UF–IFAS Education 1320A – SWFWMD R033 Marion County aquatic ecology, karst geology, Completed 2012 N/A N/A N/A $1,945 N/A SWFWMD $1,945 N/A Extension Efforts including Springs native and invasive plants, water Office PFA sampling and human impacts to springs. Marion County WBID One-day event educated Marion UF–IFAS Marion County Education 1320A – SWFWMD R034 County residents about springs Completed 2011 N/A N/A N/A $1,500 N/A SWFWMD $1,500 N/A Extension Earth Day Efforts including and water quality protection. Office PFA Funding helped develop DVDs, Marion County brochures, and posters Board of WBID Rainbow River describing value of aquatic County Education 1320A/B – SWFWMD R035 Vegetation vegetation to sustainability of Completed 2011 N/A N/A N/A $4,800 N/A SWFWMD $4,800 N/A Commissioners Efforts including Education aquatic community and (BOCC), Clean PFA recommending proper etiquette Water Dept. for river use. Through 3 educational workshops and distribution of WBID microirrigation kits, project Rainbow River Microirrigation Education 1320A – SWFWMD R035 educated homeowners living in Completed 2011 N/A N/A N/A $2,690 N/A SWFWMD $2,690 N/A Conservation workshops Efforts including 55+ communities about FFL PFA principles and benefits of using microirrigation. Up to 200 soil analysis tests WBID were conducted as part of Education 1320A – SWFWMD UF–IFAS R037 Soil Analysis by UF Crystal River/King's Bay/ Completed 2010 N/A N/A N/A $1,400 N/A SWFWMD $1,400 N/A Efforts including Rainbow River Watershed PFA Education project.

Page 27 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Project educated equine enthusiasts on importance of Marion Soil WBID protecting water resources to and Water BMPs Awareness Education 1320A – SWFWMD R038 ensure water quality by using Completed 2010 N/A N/A N/A $4,988 N/A SWFWMD $4,988 N/A Conservation Campaign Efforts including proper manure management, District PFA fertilization techniques and water conservation practices. Marion County Project encouraged Marion WBID UF–IFAS County homeowners to reduce Education 1320A – SWFWMD R039 FFL Expo Completed 2010 N/A N/A N/A $4,999 N/A SWFWMD $4,999 N/A Extension water use by incorporating FFL Efforts including Office principles. PFA Marion County 30 volunteers learned how WBID Parks and Blue Run Aquatic aquatic plants help filter Education 1320A/B – SWFWMD Recreation/ R040 Completed 2009 N/A N/A N/A $2,000 N/A SWFWMD $2,000 N/A Planting stormwater and participated in Efforts including Rainbow River planting at Blue Run. PFA Conservation Rainbow River WBID Storm drain markers purchased Conservation, Education 1320A – SWFWMD R041 Storm drain markers to conduct storm drain marking Completed 2009 N/A N/A N/A $2,695 N/A SWFWMD $2,695 N/A Boy Scouts of Efforts including events in Marion County. America PFA Consultant evaluated 10 Community locations in 5 counties, WBID Landscape/Irrigation including Marion, and made Education 1320A – SWFWMD N/A R042 Completed 2009 N/A N/A N/A $6,000 N/A SWFWMD $6,000 N/A Evaluation recommendations for water Efforts including Specialist conservation in community PFA landscapes and irrigation. Educational program to inform WBID local officials, homeowners, Rainbow River Education 1320A – SWFWMD N/A R043 retail store managers, and lawn Completed 2009 N/A N/A N/A $1,500 N/A SWFWMD $1,500 N/A Springshed Tour Efforts including care providers on how fertilizer PFA impacts local springshed. 10-minute video showing value of submerged and emergent WBID Paul Aquatic Vegetation aquatic vegetation in Rainbow Education 1320A/B – SWFWMD Marraffino, R044 Completed 2009 N/A N/A N/A $4,289 N/A SWFWMD $4,289 N/A Video Springs Aquatic Preserve and Efforts including Tracy Colson impact of recreational use on PFA vegetation. FFL demonstration garden was WBID Friends of the FFL Demonstration installed to educate visitors to Education 1320A – SWFWMD Dunnellon R045 Garden at Completed 2009 N/A N/A N/A $4,550 N/A SWFWMD $4,550 N/A Dunnellon Library about Efforts including Library Dunnellon Library benefits of FFL principles. PFA Through series of 5 workshops, landowners, developers, and WBID Marion County TDR Program for citizens were educated about Education 1320A – SWFWMD Citizens R047 Watershed Completed 2007 N/A N/A N/A $3,000 N/A SWFWMD $3,000 N/A TDR Program and Farmland Efforts including Coalition, Inc. Protection Preservation Area in northwest PFA Marion County.

Page 28 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Marion County FYN Program – WBID FFL festival provided UF–IFAS Color in the Education 1320A – SWFWMD R048 information workshops on Completed 2006 N/A N/A N/A $5,000 N/A SWFWMD $5,000 N/A Extension Landscape Spring Efforts including practices. Office Festival PFA Various water resources grants; WBID Splash! Grants to Marion County most projects were directly Education 1320A – SWFWMD R049 Teachers in Marion Completed 2013 N/A N/A N/A $35,240 N/A SWFWMD $35,240 N/A School District related to education about Efforts including County Rainbow Springs. PFA Proposed project in vicinity of Oak St. and Palmetto Way in Rainbow River Acres Rainbow River Subdivision. Project would WBID Not Not Not Not Not Not Not City of Dunnellon N/A R050 Acres Stormwater construct stormwater pond to Planned N/A 1320B – City N/A provided provided provided provided provided provided provided Retrofit address flooding and to provide outside PFA water quality for untreated stormwater runoff that currently sheetflows to Rainbow River. Project proposes $1,400,000 through FY 2019 for retrofit of county-owned drainage retention areas (DRAs) in Rainbow Springs BMAP area. Number and location of DRAs Retention Bold and Gold™ retrofitted will depend on BMP Marion County Stormwater WBID County several factors, including Retrofit with Not Not Not Office of the N/A R051 Retrofits in Underway 2019 N/A 1320A – in $1,400,000 Stormwater $1,400,000 N/A potential load reductions, land Nutrient provided provided provided County Engineer Rainbow Springs PFA Assessment availability, and location in Reducing BMAP Area PFAs identified in BMAP. Media Project is currently in preliminary scoping stages and is identified in adopted 2014 Stormwater Implementation Plan. Coordination between county and city utilities to improve level of wastewater treatment in Wastewater Level of Rainbow Springs area. Project WBID Marion County WWTF Service would improve existing level of 1320A – Utilities/City of N/A R052 Nutrient Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Coordination – treatment provided by 4 city partially in Dunnellon Reduction System Upgrade treatment facilities by PFA constructing new facility that meets advanced wastewater treatment (AWT) standards.

Page 29 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Coordination between county and city utilities to improve level of wastewater treatment in Septic Tank Wastewater Level of Marion County Rainbow Springs area. It is also Phase Out, WBID Service Utilities/City of N/A R053 anticipated that project would WWTF Canceled N/A N/A N/A 1320A – in N/A N/A N/A N/A N/A N/A Coordination – Dunnellon initially allow 266 OSTDS to Nutrient PFA OSTDS Abatement hook up to central sewer, with Reduction potential for additional connections in future. Coordination between county and city utilities to improve Package Wastewater Level of level of wastewater treatment in Plant Phase Marion County Service Rainbow Springs area. It is also WBID SWFWMD/ Out, Not Not Not Not Not Utilities/ City of SWFWMD R054 Coordination – anticipated that project would Planned 229 N/A 1320A – in N/A City of WWTF provided provided provided provided provided Dunnellon Package Plant initially allow 5 package plants PFA Dunnellon Nutrient Abatement to hook up to central sewer, with Reduction potential for additional connections in future. P301 Design and WBID Permitting Phase – Design and permitting of WWTF 1320A – SWFWMD N/A R055 Wastewater treatment wetland(s) to polish Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Upgrade including Disposal Treatment WWTP effluent. PFA Wetlands P301 WBID Implementation Construction of treatment WWTF 1320A – SWFWMD N/A R056 Phase – Wastewater wetland(s) to polish WWTP Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Upgrade including Disposal Treatment effluent. PFA Wetlands Planned project will decommission Rio Vista WWTP WBID Rio Vista WWTP WWTF Not Not Not Not City of Dunnellon N/A R057 and convert existing lift station Completed 2015 56 N/A 1320A/B – N/A Not provided Decommissioning Phase Out provided provided provided provided to pump wastewater to Rainbow In PFA Springs plant. Companion project to Rio Vista WWTP decommissioning. Sanitary Rio Vista Collection Collection system is subject to WBID Sewer and Not Not Not Not Not City of Dunnellon N/A R058 System high infiltration into system Completed 2015 N/A 1320A/B – N/A Not provided WWTF provided provided provided provided provided Maintenance after storm events, resulting in In PFA Maintenance overflows from plant holding pond. Supervisory Control Planned phased project for WBID and Data installation of SCADA at city WWTF Not 1320A – Not Not Not City of Dunnellon N/A R059 Acquisition Planned N/A N/A N/A Not provided N/A WWTPs followed by Upgrade provided Including provided provided provided (SCADA) installation at lift stations. PFA Installation Marion County Construction of retention WBID County Sa-Te-Ke Village Retention Not Office of the SWFWMD R062 storage along Rainbow River to Completed 2011 2 3 1320B – In 6.4 $73,512 Stormwater $73,512 N/A Stormwater Retrofit BMP provided County Engineer treat direct discharge to river PFA Assessment

Page 30 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number from culvert discharging along SW 183rd Ct. and SW 102nd St. Project will retrofit 3 drainage Retention retention areas in Rainbow Rainbow Springs BMP County Marion County Springs 5th replat with nitrogen- WBID 5th Replat Retrofit with Not Stormwater Not Office of the SWFWMD R063 reducing Bold and Gold™ Underway TBD 250 N/A 1320A– In 81.4 $931,510 N/A Stormwater Nutrient- provided Assessment/ provided County Engineer media. Retrofit will prevent 250 PFA Retrofit- CP #67 Reducing SWFWMD lbs of TN from reaching aquifer Media annually. Load reduction estimated using efficiency for baffle box. Baffle WBID Blue Cove Lake City of However, box includes Bold and Boxes – 2nd 1320B – Not Not Florida Not FDOT District 5 R064 Water Quality Completed 2013 1 1 32.5 N/A Dunnellon Gold™ filter media, which may Generation Outside provided provided Legislature provided Structure reduce pollutant load more than with Media PFA estimated. Project will expand town's Septic Tank Levy Blue Spring existing wastewater collection Phase Out, WBID Florida Water Quality and transmission system and Wastewater Not 1320A – Not Not Not Town of Bronson SRWMD R065 Planned 1,434 N/A N/A Legislature/ N/A Improvement eliminate use of 60 OSTDS and Service provided Outside provided provided provided SRWMD Project holding tanks at no cost to Area PFA homeowners. Expansion Addition provides corridor from to Marjorie Harris Carr Cross-Florida Greenway State Recreation and Conservation Area along Withlacoochee River, and also links to Etoniah Cross-Florida Greenway Florida Forever Rainbow DEP – Division of project. One of primary Land Not N/A R066 South Goethe Underway TBD N/A N/A Springs 11,652.0 $11,574,303 FCT $11,574,303 TBD State Lands concepts of project is to protect Acquisition provided Basin Withlacoochee River Watershed by connecting Goethe State Forest with greenway. Another goal is to provide significant buffer along southern boundary of forest while eventually enhancing forest and associated habitat through restoration. Acquiring Bear Hammock project in southern Marion County would meet state goals of enhanced coordination of Rainbow DEP – Division of land acquisition efforts by Land Not N/A R067 Bear Hammock Underway TBD N/A N/A Springs 4,685.0 $32,576,529 FCT $32,576,529 TBD State Lands making conservation link that Acquisition provided Basin fills gap among several other properties. One goal of state conservation is to preserve areas of at least 50,000 ac, and Bear

Page 31 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Hammock provides connector between Goethe State Forest and Marjorie Harris Carr Cross- Florida Greenway, creating continuity of more than 200,000 ac. Carr Farm/Price's Scrub in southwestern Alachua County and northwestern Marion County includes scrub, upland mixed forest, scrubby flatwoods, Office of Rainbow FCT/ Office of DEP – Division of Carr Farm/Price's wet flatwoods, depression Land Not Greenways and R068 Underway TBD N/A N/A Springs 1,267.0 $2,061,144 Greenways and $2,061,144 TBD State Lands Scrub marsh, marsh lake, and sinkhole Acquisition provided Trails Basin Trails lake. It is one of northernmost examples of community in peninsular Florida; 962 ac, located in Marion County, have been acquired to date. WMD Springs Management Plan summarizes vision, issues, and solutions that district will address over next 5 yrs to manage and protect springs. Through strategic investments WBID and partnerships, district is 2013–17 Springs 1320A – Not Not SWFWMD SWFWMD R070 implementing projects to Study Underway 2014 N/A N/A N/A N/A SWFWMD N/A Management Plan Including provided provided conserve and restore ecological PFA balance of spring systems, thus supporting regional economies and quality of life. Plan lays out general restoration strategy, overview of goals and issues, and list of proposed projects. Local Utilities/ Develop strategy for addressing SJRWMD/ OSTDS and other wastewater WBID DEP/ Florida SWFWMD/ OSTDS 9-1-1 management issues. Goal is to Not 1320A – Not Not Dept. of Health R071 Study Planned N/A N/A N/A N/A Not provided N/A Other Strategy enhance communication and provided Including provided provided (FDOH) Interested coordination among utilities and PFA Parties agencies. Operational staff using WBID WWTF Bay Laurel Center Operational oxidation-reduction potential 1320A – Not Bay Laurel N/A R072 Nutrient Completed N/A 16,672 N/A N/A $1,500 $1,500 N/A CDD Improvements probes and cyclic aeration to Outside provided Center CDD Reduction provide denitrification. PFA Design and construction of reclaimed water system, WBID including pumping, storage, and Bay Laurel Center Public Access Reuse 1320A – Bay Laurel SWFWMD R073 distribution main that provides Completed 2010 6,025 N/A N/A $2,198,000 N/A $2,198,000 N/A CDD Reuse Project Outside Center CDD reclaimed water for irrigation at PFA On Top of the World and Candler Hills golf courses.

Page 32 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Program taught students basic land management techniques. Students also educated community, including Dunnellon High promotion of springshed WBID Marion County Education SWFWMD R074 School Legacy protection. In 2007, educational Completed 2007 N/A N/A 1320A – In N/A $11,853 N/A SWFWMD $11,853 N/A School District Efforts Program signage about watershed PFA protection was placed in kiosks at drop-in and take-out tubing sites at Rainbow River State Park. Dunnellon Students and families were WBID Marion County Education SWFWMD R075 Elementary School educated on use of rain barrels Completed 2003 N/A N/A 1320A – In N/A $2,975 N/A SWFWMD $2,975 N/A School District Efforts Rain Barrels for irrigation to conserve water. PFA County Retention Stormwater Rainbow Springs Retrofit of Drainage Retention BMP Marion County WBID Assessment; 5th Replat Areas 2166; biosorption Retrofit with Not Not Office of the N/A R076 Planned 2017 135 N/A 1320A – In 89.8 $414,000 SWFWMD N/A Stormwater Retrofit activated media for nitrogen Nutrient- provided provided County Engineer PFA Cooperative – CP #72 reduction. Reducing Funding Media (Potentially) Upgrade city WWTP to improve WWTF Rainbow City Matching Williston WWTP nitrogen removal. Currently, Not City of Williston N/A R077 Nutrient Underway 2020 1,535 N/A Springs N/A $3,021,000 TBD Funds, CDBG, N/A Upgrade facility does not have effluent provided Reduction Basin Springs Funding reporting limit for TN. Project educated equine community in Rainbow Springs Springshed about need for BMPs to protect springs. WBID Marion County Informational brochure was Save Our Springs, Education 1320A – SWFWMD UF–IFAS R078 created to accompany Planned 2016 N/A N/A N/A $1,600 N/A SWFWMD $1,600 N/A Manage the Manure Efforts including Extension promotional item passed out at PFA local tack stores. Goal was for Extension to meet and schedule one-on-one farm consultations to teach BMPs. FDOT O&M fertilizer cessation WBID on SR 121 and SR 500 (US Fertilizer 1320A – FDOT District 2 N/A R079 Fertilizer Cessation Completed N/A 3,670 N/A 168.5 N/A N/A N/A N/A N/A Hwy. 27A). Cessation began in Cessation including 2009 and is ongoing. PFA Nitrogen reduction from wet Wet detention/retention ponds on SR WBID Wet Detention/ Detention 500 (US Hwy. 27A). Ponds 1 1320A – Not Not Not FDOT District 2 N/A R080 Retention Ponds in Ponds, Completed 2004 133 N/A 68.6 Not provided N/A and 5 were completed in 2002, Outside provided provided provided FDOT Roads Retention and Pond 10 was completed in PFA BMPs 2004.

Page 33 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Proposed project located at Dinkins Park/City Beach. Project would construct Rainbow Dunnellon City riverwalk along Rainbow River Not Not Not Not Not Not City of Dunnellon N/A R081 Underway 2021 N/A Springs City N/A Beach and provide for water quality for provided provided provided provided provided provided Basin untreated stormwater runoff that currently sheetflows into Rainbow River. Research project will evaluate nutrient removal efficiency from composting animal waste. Project will investigate various Composting at Rainbow composting BMPs to determine Not Not SWFWMD UF–IFAS R082 Animal Stock Study Underway 2019 N/A N/A Springs N/A N/A SWFWMD N/A which is most effective. Project provided provided Facilities Basin will also compare nutrient leaching efficiency for manure stockpiling and composting facilities. Program will focus on implementation of management BMPs for commercial equine operations in Rainbow Springs BMAP area, specifically in areas of Marion County under SWFWMD jurisdiction. Effort UF–IFAS Marion County will be in conjuction and Agriculture Rainbow Marion Equine Compost coordination with UF–IFAS BMPs, FDACS/ Not FDACS R083 Underway 2019 TBD N/A Springs N/A $200,000 N/A N/A County, Facilities Pilot Marion County Extension Education SWFWMD provided Basin SWFWMD Project Service, in which education and Efforts outreach will be provided for commercial and small equine operations. It will also be in conjunction with Marion County Solid Waste Dept. to remove static manure piles on commercial equine operations. Rerate City of Dunnellon WRF to 0.50 mgd and construct force main from Rainbow Springs WRF to city's WRF and Package decommission Rainbow Springs Plant Phase Rainbow Springs WRF. City of Dunnellon Out, Rainbow Water Reclamation recognizes vital ecological and Not Not Not City of Dunnellon SWFWMD R084 Wastewater Planned TBD N/A Springs N/A N/A Not provided N/A Facility (WRF) economic importance of provided provided provided Service Basin Decommissioning Rainbow Springs and Rainbow Area River in community. Expansion Waterbodies are listed as OFWs and are classified as high priorities in SWIM Plan. Both are impaired under Chapter 62-

Page 34 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number 303(d), F.A.C., for TN, as identified in adopted TMDL. Primary project objective is to design and construct sanitary sewer system to remove from service Rainbow Springs WRF, which treats 0.15 mgd. Facility contributes to TN impairment of Rainbow Springs and Rainbow River. Removal will result in substantial and measurable reduction in identified pollutant sources. Project depends on rerating city WRF to 0.50 mgd. Golden Ocala WWTF expansion project is initiative by county to improve wastewater treatment and expand plant capacity. Project consists of constructing new 0.675 mgd oxidation ditch with biological nutrient Golden Ocala removal, 2 0.750 mgd clarifiers, WWTF Rainbow Marion County WWTP Nutrient County Utility Not N/A R085 2 flow-splitting structures for Nutrient Underway 2020 TBD N/A Springs N/A $17,300,000 $236,000 N/A Utilities and Capacity Funds/ Grants provided future oxidation ditches, 0.500- Reduction Basin Improvement million-gallon equalization basin, new headworks, and screening structure. Existing 0.2 mgd plant will be retrofitted into aerobic digester or sludge holding tank. Plant will be upgraded to AWT standards. Rainbow Springs sewer expansion project will determine feasibility of removing existing septic tanks and connecting to central sewer system. Project will improve water quality to Rainbow Springs and Rainbow Removal of Septic River. Subject to funding Tanks along limitations, consultant would Rainbow Marion County Not County Utility N/A R086 Rainbow River and develop feasibility study to Study Planned N/A N/A Springs N/A $20,000 N/A $20,000 N/A Utilities provided Funds Primary Protection include multiyear phased Basin Zone approach for planning projects in Primary Spring Protection Zone of Rainbow River. Feasibility study will focus on quantifying and locating existing OSTDS systems, estimating construction costs (for new infrastructure and

Page 35 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Contract Estimated TN TP Cost Agree- Project Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding ment Lead Entity Partners Number Project Name Project Description Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number system updates, including lift stations, gravity sewer mains, force mains, sewer laterals, eliminating septic tanks, and constructing new regional WWTF to meet current, future demands and BMAP water quality standards, and decommissioning package plants) as well as O&M costs of new infrastructure. Project will construct 10,750 ft of sanitary sewer force main along SR 200 corridor in Ocala. Project will connect existing development so that septic tanks Septic Tank can be abandoned, prevent Provide Central Phase Out, further installation of septic Rainbow Marion County Marion County Sewer Service to Wastewater N/A R087 tanks along corridor by making Underway 2018 TBD N/A Springs N/A $2,490,984 $4,730 Utility Funds/ $2,490,984 N/A Utilities Major Commercial Service central sewer available to new Basin Grants Corridor Area development, and reduce Expansion groundwater withdrawals by sending new sewer flows to WWTF that produces and distributes reclaimed water to customers. Springs Connection of 31 residential Rainbow Northwood Estates Septic Tank Not Funding/ City Not City of Williston N/A R088 properties in Northwood Estates Planned 2019 355 N/A Springs N/A $2,500,000 N/A Septic-to-Sewer Phase Out provided In-Kind provided to city central sewer. Basin Services Study will focus on estimating construction costs (for new infrastructure and system updates, including lift stations, gravity sewer mains, force mains, sewer laterals, Financial Feasibility eliminating septic tanks, Study for New upgrading existing WWTFs to Rainbow Marion County Not N/A R089 Centralized WRF meet future demands and county Study Planned N/A N/A Springs N/A $150,000 N/A County $150,000 N/A Utilities provided and Collection water quality standards, and Basin System decommissioning package plants), and O&M costs of new infrastructure. Study will determine cost-benefit ratio to determine feasibility of implementing OSTDS to central sewer in Rainbow Springs area.

Page 36 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Santa Fe River BMAP

Background The Santa Fe River Basin encompasses an area of over 1 million acres and includes all or portions of Alachua, Bradford, Columbia, Gilchrist, and Union Counties. Urban areas include Lake City and Fort White in Columbia County and Alachua, Archer, High Springs, La Crosse, and Newberry in Alachua County. The basin also includes the following OFS: Ichetucknee Spring Group, Hornsby Spring, Devil's Ear Spring, Poe Spring, Columbia Spring, and Treehouse Spring (Figure B-3).

DEP identified the lower portion of the Santa Fe River (from River Rise westward to its confluence with the Suwannee River) as impaired for DO and nutrients. In September 2008, DEP adopted the Santa Fe River TMDL for nitrate to protect the aquatic flora and fauna in the river. To achieve the annual average nitrate target of 0.35 mg/L in the Santa Fe River Basin, the nitrate loads from nonpoint sources need to be reduced by 35 %. The Santa Fe River BMAP was adopted in February 2012 to implement the nitrate TMDL in the watershed.

Status of Projects Through December 31, 2017, 3 projects have been completed. An additional 40 projects that are underway or planned have been added to the BMAP. The projects completed to date are estimated to achieve total reductions of 93,901 lb-N/yr. The projects that are underway are estimated to achieve total reductions of 620,288 lb-N/yr. These are primarily agricultural BMP projects. As an OFS BMAP, additional information will be provided when the BMAP reaches its 5-, 10-, and 15-year milestones. If the milestones or the 20-year target will not be met, an explanation of possible causes and potential solutions will be provided. These milestones will be specified in a revised BMAP document that is scheduled to be adopted by July 1, 2018, to meet the statutory requirements added by the 2016 Florida Legislature.

Page 37 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Figure B-3. Santa Fe River BMAP Area

Page 38 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Table B-3. Santa Fe BMAP projects DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lb-N/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Install new waterless restrooms with larger Poe Springs holding tanks adjacent County – Domestic Wastewater Alachua to springshed. Replace Not Alachua County/ $196,600 SRWMD AC-01 Sewage System Underway 2019 5,776 N/A $346,600 Not provided N/A County OSTDS with enhanced provided County SRWMD SRWMD – Infrastructure Upgrade passive nitrogen system $150,000 Upgrade using biosorption activated media (BAM). Install temporary aerator to improve DO County – conditions, remove Alachua Hornsby Spring Hydrologic Alachua County/ $20,000 DEP AC-02 sediment to improve Underway TBD 1,260 N/A TBD $443,480 N/A TBD County Restoration Restoration County DEP DEP – spring flow, and install $423,480 SAV to improve water quality. See AL-01 for Phase I Mill Creek project info. Phase II is Sink Water County – acquisition of 240 Alachua Quality Land Alachua County/ $1,300,000 DEP AC-03 additional acres Planned 2018 N/A N/A N/A $2,600,000 N/A TBD County Improvement Acquisition County DEP DEP – surrounding and Project – $1,300,000 upstream of Mill Creek Phase II Swallet. Implement social DEP/ Fertilizer marketing campaign Partnership Alachua Gainesville Social designed to reduce Education Alachua Partnership/ – $300,000 AC-04 Planned 2021 TBD TBD N/A $435,000 N/A NF033 County Clean Water Marketing fertilizer use and to Efforts County DEP DEP – Partnership Campaign estimate resultant load $135,000 reduction. Implement education by County/ coordinating 5 to 6 Wildlife interactive paddling Foundation County – Alachua Adventure Interactive trips on Santa Fe River Education Alachua of Florida $6,900 AC-05 Planned 2019 N/A N/A N/A $12,600 N/A N/A County Outpost Paddling Trips with 120 stakeholders to Efforts County Springs Grant – explore actions that Protection $5,700 affect health of springs License and groundwater. Plate Grant Interactive table-top Interactive model for teaching Gainesville Alachua Stormwater and children and adults Education Alachua Clean Water AC-06 Underway TBD N/A N/A N/A $6,500 N/A Partnership $6,500 N/A County Wastewater about difference Efforts County Partnership Model bewtween storm sewers and sanitary sewers. Project goal is to County/ document current Wildlife Santa Fe River Alachua condition of SAV at Alachua Foundation N/A AC-07 Springs SAV Study Underway 2019 N/A N/A N/A $24,500 N/A $24,500 N/A County selected springs (pools County of Florida Assessment and associated spring Springs runs) on Santa Fe River. Protection

Page 39 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lb-N/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number License Plate Grant Stream Bioassessment Study project includes Stream Condition Index (SCI) in-stream Gainesville Stream biological assessmens Monitoring/ Alachua Alachua Clean Water AC-08 Bioassessment and Hester-Dendy Data Underway 2019 N/A N/A N/A $85,970 N/A FDOT $85,970 N/A County County Partnership Study sampling and analysis Collection to provide ambient monitoring for TMDL and impaired watersheds. County/ Project seeks to Wildlife evaluate role of DO Hornsby Foundation temporally and spatially Alachua Springs DO Alachua of Florida Camp Kulaqua AC-09 and to explore what Study Planned 2019 N/A N/A N/A $14,000 N/A $14,000 N/A County and Faunal County Springs effect this may have on Study Protection organisms, particularly License macroinvertebrates. Plate Grant Project goal is to increase awareness County/ about springs of Santa Wildlife Fe River and current Foundation Santa Fe River Alachua Local and State springs issues and Education Alachua of Florida AC-10 Springs Planned 2019 N/A N/A N/A $12,600 N/A $12,600 N/A County Parks solutions. Interpretive Efforts County Springs Signage signs will be installed at Protection selected springs or License parks along Santa Fe Plate Grant River. Install new public restrooms with lift station and septic system in place of County – portable toilets. Install Columbia Rum Island Not Columbia County/ $150,000 SRWMD CC-01 BAM to reduce OSTDS Underway 2019 N/A N/A $300,000 N/A N/A County Park provided County SRWMD SRWMD – nutrients around septic $150,000 system. Project also involves bank restoration and dredging. Ichetucknee Construct swales, Trace – Clay canals, and stormwater Hole Creek/ canal structures to direct County – Regional Columbia Alligator Lake water to Alligator Lake Columbia Not County/ $300,000 DEP CC-02 Stormwater Underway 2018 30,000 N/A $2,560,000 Not provided LP6103A County Aquifer to provide erosion County provided DEP DEP – Treatment Recharge and control and water $2,260,000 Stormwater quality treatment before Mitigation water enters aquifer.

Page 40 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lb-N/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Provide flood mitigation, water quality improvement, County: Ichetucknee Columbia and aquifer recharge Wetland Columbia County/ $780,000 DEP CC-03 Trace – Cannon Planned TBD 10,000 N/A 13 $3,030,000 Not provided S0924 County through replacement of Treatment County DEP DEP – Creek Project old drainage well and $2,250,000 13 ac of wetland construction. Remove noncompliant WWTP that serves motel and connect motel to county's central County – Dream Inn Wastewater Columbia sewer system. This also Not Columbia County/ $210,437 DEP CC-04 Motel WWTP System Underway 2018 1,000 N/A $354,737 N/A N/A County includes relocating, provided County SRWMD SRWMD – Closure Upgrade upgrading, and $144,300 enlarging existing county WWTF to handle flow from motel. Replace boat ramp, add County – docks and canoe launch, Gilchrist Santa Fe Park Stormwater Not Not Gilchrist Not County/ $6,800 SRWMD GC-01 and remedy drainage to Underway 2019 $129,800 Not provided N/A County and Boat Ramp Improvements provided provided County provided SRWMD SRWMD – reduce sediment and $123,000 nutrients. Purchase property to install water quality Mill Creek BMPs to reduce DEP – Sink Water pollutant loads BMP City of Alachua Not DEP/ $1,000,000 DEP/SRWMD AL-01 Quality discharging directly into Treatment Underway 2020 TBD TBD $1,400,000 Not provided Alachua County provided SRWMD SRWMD – Improvement sink. Nutrient loading Train $400,000 Project should be reduced by 66 % and benefit Hornsby Spring. Increase storage in City – Holly Hills existing stormwater City of Stormwater Not Not Alachua Not City/ $4,000 SRWMD AR-01 Stormwater ponds to alleviate Underway 2018 $87,000 Not provided N/A Archer Improvements provided provided County provided SRWMD SRWMD – Improvements flooding and improve $83,000 water quality. Undertake study to City of Master Bradford TBD HA-01 address severe flooding Study Planned TBD N/A N/A N/A TBD N/A TBD TBD N/A Hampton Drainage Study County issues. Convert city's existing Infiltrative effluent sprayfield into Wetlands for infiltration wetlands; 10 City of WWTF of 20 ac will be Wetland Not Alachua DEP – High DEP/ SRWMD HS-01 Effluent Underway TBD 4,870 10 $1,708,500 Not provided DEP constructed in Phase I. Treatment provided County $1,708,500 Springs Treatment/ This will benefit water Disposal – quality in Hornsby and Phase I Poe Springs.

Page 41 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lb-N/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Wastewater Provide central sewer to City – City of Collection remaining areas served Wastewater Alachua $125,000 High DEP/ SRWMD HS-02 System by septic systems; Service Area Underway 2019 2,640 N/A N/A $3,432,700 N/A City/ DEP LP61037 County DEP – Springs Extension – eliminate 132 septic Expansion $3,307,700 Phase A1 systems. Remove onsite Camp Kulaqua- wastewater treatment DEP – City of Hornsby Spring Wastewater plant and effluent Not Alachua DEP/ $450,000 High DEP/ SRWMD HS-03 Water Quality System Underway 2018 97 N/A $500,000 Not provided S0889 disposal and install new provided County SRWMD SRWMD – Springs Improvement Upgrade wastewater line to city $50,000 Project WWTP. Eliminate 13 residential City – City of Wastewater Septic Tank septic systems and Alachua City/ $25,000 High SRWMD HS-04 Service Area Underway 2018 330 N/A N/A $175,000 N/A N/A Abatement connect to city's central County SRWMD SRWMD – Springs Expansion sewer system. $150,000 Wastewater Provide central sewer to City of Collection remaining areas served Wastewater Alachua High TBD HS-05 System by septic systems; Service Area Planned TBD 5,880 N/A N/A $3,453,600 $5,000 TBD TBD N/A County Springs Extension – eliminate 168 septic Expansion Phase A2 systems. WWTF upgrades to meet AWT standards. City of Wastewater WWTF Effluent will be futher Alachua High TBD HS-06 System Planned TBD TBD TBD N/A $4,800,000 TBD TBD TBD N/A Upgrade treated with constructed County Springs Upgrade infiltrative/treatment wetland. I-75/SR 47 Eliminate septic Cannon Creek systems from 30 City – Sink Wastewater City of businesses and 5 Columbia $1,703,415 DEP LC-01 Wastewater Service Area Planned 2019 11,950 N/A N/A $3,400,871 N/A City/ DEP Lake City residences to benefit County DEP – Improvement Expansion water quality in $1,697,456 Project – Ichetucknee Spring. Phase I Convert city wastewater City – effluent disposal system $200,000 Ichetucknee into 120 ac of DEP/ City/ DEP/ DEP – Springshed constructed wetlands City of SRWMD/ Wetland Columbia SRWMD/ $3,900,000 LC-02 Water Quality that provide 1.58 mgd Completed 2016 77,000 N/A 120 $5,005,175 Not provided S0675 Lake City Columbia Treatment County Columbia SRWMD – Improvement of recharge water to County County $805,175 Project aquifer and reduce County – nitrogen loads from $100,000 WWTP by 85 %. Upgrade existing Reclaimed City: system to allow City of Water System Reclaimed Columbia City/ $351,166 SRWMD LC-03 reclaimed water to be Underway 2018 TBD TBD TBD $545,470 Not provided N/A Lake City Upgrade – Water County SRWMD SRWMD – used by local golf Phase I $194,304 course and farmer. Replace existing water Wastewater City of Potable Water Alachua City/ City – SRWMD NEW-01 and wastewater lines System Underway 2018 TBD TBD TBD $650,000 Not provided N/A Newberry and Central County SRWMD $611,566 close to historic district, Upgrade

Page 42 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lb-N/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Wastewater reducing unaccounted SRWMD – Improvements water loss and $38,434 preventing potential sewage spills. Remove septic system DEP in wetlands at Florida Ichetucknee Dampier's Landing Bath Wastewater Not Columbia Not Not Park N/A FPS-01 Springs State House and connect to Service Area Planned TBD N/A TBD N/A DEP N/A provided County provided provided Service Park existing wastewater Expansion (FPS) treatment system in uplands. Information Fertilizer Eliminate fertilizer use Fertilizer Not Not Not Not Not FDOT FDOT-01 Completed 16,901 3,550 Basinwide 776 Not provided not provided Elimination in rights-of way. Cessation provided provided provided provided provided Construct recharge wetland at new Shands Gainesville GRU – Wetland facility to remove Regional Wetland Not Alachua $960,000 DEP GRU-01 Creation at nutrients from Canceled TBD N/A N/A $1,110,000 N/A GRU/ DEP S0906 Utilities Treatment provided County DEP – Shands Facility reclaimed water and (GRU) $150,000 stormwater and provide aquifer recharge. Provide reclaimed water Oakmont GRU – to irrigate 136 Reclaimed Reclaimed Alachua GRU/ $339,428 GRU SRWMD GRU-02 residential properties Underway 2018 TBD TBD TBD $452,571 Not provided N/A Water Main Water County SRWMD SRWMD – and 3 ac of common Extension $113,143 area. Construct recharge wetland in existing GRU – Oakmont stormwater retention Wetland Alachua Not GRU/ $250,000 GRU SRWMD GRU-03 Recharge Underway 2019 TBD TBD $400,000 Not provided N/A basin that will reduce Treatment County provided SRWMD SRWMD – Wetland nutrients while $150,000 recharging aquifer. Implementation and periodic review and Suwannee update of Suwannee DEP/ Local SRWMD – SRWMD SRWMD-01 River SWIM River SWIM Plan, Study Completed 2017 NA N/A Basinwide N/A $238,563 N/A SRWMD N/A Governments $238,563 Plan which includes Santa Fe River and . To date, 9 agreements Improved with dairies to install Nutrient screen separators to Application reduce wastewater DEP/ DEP and Dairy DEP/ SRWMD SRWMD-02 Practices in solid; 1 agreement with BMPs Underway TBD 1,485 TBD Basinwide TBD $309,600 N/A SRWMD – S0905 Producers SRWMD Dairy dairy in Santa Fe Basin. $309,600 Operations – DEP has allocated Phase 2 $2,120,000 for districtwide program. DEP/ Sustainable Agriculture operators DEP – SRWMD Producers/ SRWMD-05 Suwannee are invited to submit BMPs Underway 2019 187,500 TBD Basinwide N/A $2,500,000 N/A DEP LP61038 $2,500,000 Local Springs proposals to transition

Page 43 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lb-N/yr) (lbs/yr) Location Treated Estimate O&M Source Amount Number Governments/ Agriculture to less intensive Landowners/ Pilot Program – cropping systems, Private Low Input change type of cropping Companies Agriculture system, or change land use to fallow or native landscape for certain amount of time or permanent conservation easement. Priority is given to Convict, Fanning, and Itchetucknee Springsheds. Benefits of annual cost- share projects include improving wastewater facilities serving Agricultural Regional hundreds of residents Producers/ Initiative and commercial entities, Local Valuing preventing potential WWTF Not $1,500,000/ SRWMD – SRWMD Governments/ SRWMD-07 Environmental wastewater discharge Underway TBD TBD Basinwide N/A N/A SRWMD NA Upgrade provided annually $1,500,000 Landowners/ Resources into receiving waters Private (RIVER) during flood events, and Companies Program significantly reducing nutrient leaching by removing substantial number of septic systems. Provide cost-share funds to agricultural producers in BMAP area to implement Precision precision nutrient and Agricultural Not SRWMD – SRWMD SRWMD-08 Agricultural irrigation management BMPs Underway 312,500 TBD Basinwide N/A $625,000 N/A SRWMD NA Producers provided $625,000 Practices technology. Districtwide program benefits and dollars split between Santa Fe and Suwannee BMAPs. Assist nurseries in upgrading from DEP – overhead irrigation $940,000 DEP/ Nursery Water DEP/ methods to microspray Not SRWMD – SRWMD Agricultural SRWMD-09 Conservation BMPs Underway 45,000 TBD Basinwide N/A $1,321,150 N/A SRWMD/ S0796 or drip irrigation. To provided $39,325 Producers Initiative Producers date, 45 nurseries on Producers – 300 ac have received $341,825 assistance.

Page 44 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Silver River and Springs BMAP

Background The Silver Springs BMAP area is 989 square-miles in size (Figure B-4) and is located primarily in Marion County. The BMAP area approximates the extent of the 1,000-year modeled groundwater capture zone. The BMAP addresses the surface drainage basin for Silver River, but not other surface water basins located in the BMAP area. The western boundary of the BMAP area coincides with the eastern extent of the Rainbow Springs BMAP area and I-75.

DEP identified Silver Springs, Silver Springs Group, and Upper Silver River as impaired for nutrients, because of an imbalance of flora and fauna evidenced by excessive algal growth and smothering of SAV. In 2012, DEP adopted the TMDL, which established a concentration target of 0.35 mg/L nitrate (NO3 as N) and a 79 % reduction in nitrate concentration for each impaired waterbody. The Silver Springs BMAP was adopted in October 2015 to implement the TMDLs.

Status of Projects Through December 31, 2017, 124 projects have been completed. The projects completed to date are estimated to achieve total reductions of 265,461 lbs/yr of TN at the land surface.

Additional information will be provided when the OFS BMAP reaches its 5-, 10-, and 15-year milestones. If the milestones or the 20-year target will not be met, an explanation of possible causes and potential solutions will be provided. These milestones will be specified in a revised BMAP document. The revised Silver Springs BMAP is scheduled to be re-adopted by July 1, 2018, to meet the statutory requirements added by the 2016 Florida Legislature.

Page 45 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Figure B-4. Silver River and Springs BMAP area

Page 46 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Table B-4. Silver River and Springs BMAP projects DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number TDR Program is designed to protect natural resources, especially those listed in Policy 1.1.2 of Conservation Element of Marion County Comprehensive Plan and locally important and prime farmlands in Marion County. Resources include, but are not Rainbow Marion County Marion County limited to, preservation of Not Spring Basin, Not N/A B001 Study Completed N/A N/A N/A N/A Not provided Not provided N/A Growth Services TDR high-water recharge and provided Silver Spring provided underground drainage Basin basins, springs, karst areas, sinkholes, sinks, sinkhole ponds, and other karst features. Land from which development rights are transferred is subject to conservation easement. Article 3 of LDC defines TDR Program and eligible sending and receiving areas. TVR Program is designed to minimize dense development of vested properties without central water and sewer systems, and/or other supporting infrastructure, and thus protect natural resources, encourage and enhance development of larger Rainbow Marion County Marion County parcels, reduce county's Not Spring Basin, Not N/A B002 Study Completed N/A N/A N/A N/A Not provided Not provided N/A Growth Services TVR inventory of vested provided Silver Spring provided properties, and permit Basin county to better plan for future growth. Land from which vested rights are transferred is subject to conservation easement. Article 3 of LDC defines TVR Program and eligible sending and receiving areas.

Page 47 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Comprehensive Plan Future Land Use Element Policy 2.1.13 establishes Hamlet Development Option, designed to provide for clustered low- density development patterns in rural designated lands, while requiring permanent open spaces reserved from Rainbow Marion County Marion County development and some Not Spring Basin, Not N/A B003 Hamlet Design Study Completed N/A N/A N/A N/A Not provided Not provided N/A Growth Services increased additional urban provided Silver Spring provided Option services (e.g., central Basin water, central sewer, designed/constructed stormwater systems) that comply with Marion County's design and development standards, including Springs Protection. Article 3 of LDC generally defines Hamlet design provisions. Comprehensive Plan Future Land Use Element Policy 2.1.18 establishes Rural Community future land use designation to provide for clustered urban density development patterns in rural designated lands, while requiring permanent open spaces Marion County reserved from Rainbow Marion County Rural Community development and Not Spring Basin, Not N/A B004 Study Completed N/A N/A N/A N/A Not provided Not provided N/A Growth Services Land Use complete urban services provided Silver Spring provided Designation (e.g., central water, Basin central sewer, and designed/constructed stormwater systems) that comply with Marion County's design and development standards, including Springs Protection. Article 3 of LDC generally defines Rural Community design provisions.

Page 48 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Comprehensive Plan Future Land Use Element Objective 2.2 establishes specific limited density and specialized design Marion County Rainbow standards for wetland and Marion County Community Not Spring Basin, Not N/A B005 floodplain areas slated for Study Completed N/A N/A N/A N/A Not provided Not provided N/A Growth Services Redevelopment provided Silver Spring provided development. Articles 5 Area Program Basin and 6 of LDC set forth specific design and development criteria related to applicable areas. Comprehensive Plan Future Land Use Element Objective 7.2 establishes SPOZ and identifies extent of Primary and Rainbow Marion County Secondary Zones along Marion County Not Spring Basin, Not N/A B006 Springs Protection with other design and Study Completed N/A N/A N/A N/A Not provided Not provided N/A Growth Services provided Silver Spring provided Zones development standards. Basin Articles 5 and 6 of LDC set forth specific design and development criteria related to applicable SPOZ. Ordinance sets enforceable irrigation Regulations, Rainbow Marion County Marion County schedule and rates for Ordinances, Not Spring Basin, Not Not Office of the N/A B007 Irrigation Marion County; also Completed N/A N/A N/A County Not provided N/A and provided Silver Spring provided provided County Engineer Ordinance identifies efficient Guidelines Basin irrigation systems exempt from schedule. County FFL fertilizer use on urban landscapes ordinance regulates proper use of fertilizers by any applicator; requires proper training of commercial and institutional fertilizer Regulations, Rainbow Marion County Marion County applicators; establishes Ordinances, Not Spring Basin, Not Not Office of the N/A B008 Fertilizer Completed N/A N/A N/A County Not provided N/A training and licensing and provided Silver Spring provided provided County Engineer Ordinance requirements; and Guidelines Basin specifies allowable fertilizer application rates and methods, fertilizer- free zones, low- maintenance zones, and exemptions. It requires use of BMPs that provide

Page 49 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number specific management guidelines to minimize negative secondary and cumulative environmental effects associated with misuse of fertilizers; latest LDC now includes 2008 ordinance. Covers silviculture lands in Rainbow and Silver Springs BMAP areas. BMPs for silviculture are applicable to public and private industrial and nonindustrial forest lands. Silviculture BMPs are minimum standards for Rainbow Silviculture BMP Florida Forest protecting and Agriculture Spring Basin, Not Not N/A B009 Implementation Completed N/A N/A N/A N/A Not provided Not provided N/A Service maintaining water quality BMPs Silver Spring provided provided and Compliance during ongoing Basin silviculture activities, including forest fertilization. Projects include biennial BMP surveys, targeted training, and technical assistance for landowners and forestry professionals. Clean Farms Initiative was designed to assist Marion County farm owners and managers with implementation of BMPs, and to recognize their cooperative efforts. As part of initiative, more than 7,500 surveys and brochures were mailed in Rainbow Marion County 2006 to owners of Clean Farms Agriculture Spring Basin, Not Not Office of the N/A B010 agricultural land, ranging Completed N/A N/A N/A N/A Not provided Not provided N/A Initiative BMPs Silver Spring provided provided County Engineer from large operations of Basin several hundred acres to small tracts with fewer than 12 animals. Survey measures current manure management and fertilization practices. Results of survey, and input from focus groups held in February and March 2007, were used to

Page 50 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number create Farm Outreach Coordinator position to educate horse farm owners and managers on water quality, targeting practices such as manure management and fertilization. Equine BMPs and Manure Management Education and Outreach Program sponsored by UF–IFAS Extension and Marion County. From 2010 to 2013, program developed 44 types of Water Quality educational materials, Rainbow UF–IFAS SWFWMD, Education and made 3,507 client Agriculture Spring Basin, Not Not Extension B011 Completed N/A N/A N/A N/A UF–IFAS Not provided N/A UF–IFAS Equine Farm consultations, 464 of BMPs Silver Spring provided provided Marion County BMPs which were in field; 301 Basin producers participated in group education events, including manure management summit and tour. Program website received 446 views during this period. Program is ongoing. Small Equine BMP manual is intended to educate owners of noncommercial horse farms on BMPs to reduce nutrient loads. Outreach program will be developed for effective implementation of BMPs on noncommercial horse Implementation of Rainbow farms in Silver and Outreach Program Agriculture Spring Basin, Not Not DEP TBD B012 Rainbow Springs BMAP Completed N/A N/A N/A N/A Not provided Not provided N/A for Small Equine BMPs Silver Spring provided provided areas. Implementation BMP Manual Basin program will consist of identification of key agencies with existing public education activities where BMP manual can be incorporated, development or modification of existing recognition programs to provide measureable

Page 51 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number goals for both participants and types of BMPs implemented, and identification of existing cost-share programs that may assist noncommercial operations in BMP implementation. 238719-1, SR 40 from CR 328 to SW 80th Ave. SR 40 Design Retention WBID 1320A Not Not Florida FDOT District 5 N/A B022 (CR 225A) – Pond 3/dry Underway 2020 12 2 9.0 Not provided N/A Project-Pond 3 BMP – Outside PFA provided provided Legislature retention; closed basin in poorly drained soils. 238719-1, SR 40 from CR 328 to SW 80th Ave. SR 40 Design Retention WBID 1320A Not Not Florida FDOT District 5 N/A B023 (CR 225A) – Pond 4/dry Underway 2020 16 2 12.5 Not provided N/A Project-Pond 4 BMP – Outside PFA provided provided Legislature retention; closed basin in poorly drained soils. 238719-1, SR 40 from CR 328 to SW 80th Ave. SR 40 Design Retention WBID 1320A Not Not Florida FDOT District 5 N/A B024 (CR 225A) – Pond 5/dry Underway 2020 14 2 10.9 Not provided N/A Project-Pond 5 BMP – Outside PFA provided provided Legislature retention; closed basin in poorly drained soils 238719-1, SR 40 from CR 328 to SW 80th Ave. SR 40 Design Retention WBID 1320A Not Not Florida FDOT District 5 N/A B025 (CR 225A) – Pond 6/dry Underway 2020 12 2 9.3 Not provided N/A Project-Pond 6 BMP – Outside PFA provided provided Legislature retention; closed basin in poorly drained soils Construction of drainage retention area lined with Marion County Bold and Gold™ soil Retention SW 85th St/ Stormwater Marion County amendment to enhance BMP with SW 40th Ave WBID 1320A Not Assessment/ Office of the SWFWMD B028 nitrogen removal. Post- Nutrient- Completed 2012 98 N/A 32.0 $330,000 Not provided N/A Stormwater – Outside PFA provided SWFWMD County Engineer construction event Reducing Retrofit Cooperative monitoring shows 70 % Media Funding reduction in TN through soil amendment layer. Proposed project to construct wet retention area to reduce nitrate in stormwater runoff from Marion County West Hwy. 316 at transportation and Stormwater Marion County 119th Ave residential land uses that Retention WBID 1320A Not Assessment/ Office of the SWFWMD B029 Completed 2016 29 0 55.6 $52,654 Not provided N/A Stormwater is currently infiltrating to BMP – Outside PFA provided SWFWMD County Engineer Retrofit aquifer without treatment. Cooperative Project is currently Funding identified in adopted 2014 Stormwater Implementation Plan.

Page 52 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Proposed project to construct retention area to reduce nitrate in stormwater runoff from West Hwy. 316 at transportation and Marion County Hwy. 329 residential land uses that Retention WBID 1320A Office of the N/A B030 Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Stormwater is currently infiltrating to BMP – Outside PFA County Engineer Retrofit aquifer without treatment. Project is currently identified in adopted 2014 Stormwater Implementation Plan. County Annual Stormwater Budget for Part of ongoing Internal Repairs – stormwater system $50,000 Marion County Sinkhole Repair maintenance activities. WBID 1320A Stormwater Typical Annual Office of the N/A B032 Program in Performed as needed by Completed N/A N/A N/A – including N/A N/A $50,000 Not provided N/A System O&M Expenditure for County Engineer County DRAs county crews or PFA Contracted contractors depending on Repairs from size and scope of repair. Stormwater Budget – $10,000 to $100,000 Sweeping of county– maintained roads. Sweeping of roads with curb and gutter is Marion County Street Sweeping WBID 1320A County completed 9 times/yr. Street Office of the N/A B033 of Marion County Completed N/A 194 124 – including N/A N/A $46,000 Stormwater Not provided N/A Benefits: Remove debris, Sweeping County Engineer Roads PFA Assessment sediment, and potential pollutants from streets. Prevent entry into storm sewer system. Countywide WMPs prepare that include creation and maintenance County Marion County of comprehensive WBID 1320A Marion County Not Stormwater Office of the SWFWMD B034 geodatabase for county Study Completed N/A N/A – including N/A $337,000 N/A Not provided N/A WMP provided Assessment/ County Engineer storm sewer system data, PFA SWFWMD watershed boundaries and hydrologic features countywide.

Page 53 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Identification of vulnerable areas of aquifer. Project provided scientifically defensible water resource management and protection tool that facilitates planning of human activities to help minimize adverse impacts on groundwater quality. Aquifer vulnerability maps are displayed in classes of relative vulnerability (one area is Marion County Marion County more vulnerable than WBID 1320A County Aquifer Office of the N/A B035 another). Maps benefit Study Completed 2007 N/A N/A – including N/A $82,850 N/A Stormwater $82,850 N/A Vulnerability County Engineer local government, PFA Assessment Assessment planners and developers in guiding growth into more appropriate areas (e.g., groundwater recharge areas) and improve site selection for expanding existing or establishing new well fields. Benefits: Identifies areas where aquifer is vulnerable to pollution. Potential future management activities in those areas to reduce pollution of groundwater. Formation of public education coordination team consisting of representatives from local government, state agencies, WMDs, and Local, State, and Marion County WBID 1320A Public Education local interest groups. Education Not Not Federal Agencies/ Office of the Not provided B036 Completed N/A N/A N/A – including N/A Not provided N/A Coordination Purpose would be to Efforts provided provided WMDs/ Local County Engineer PFA provide consistent and Interest Groups accurate information on pollution prevention to citizens and maximize efforts among team members.

Page 54 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Public outreach and education programs including informational pamphlet distribution, PSAs, and public Marion County outreach events. Other Marion County Stormwater efforts include illicit WBID 1320A County Education Not Office of the N/A B037 Program – discharge inspection and Completed N/A N/A N/A – including N/A $3,500,000 Stormwater Not provided N/A Efforts provided County Engineer NPDES MS4 education, mapping and PFA Assessment Permit modeling efforts, construction site pollution prevention program, and municipal operations pollution prevention program. FDOT conducts inspections and provides annual illicit discharge, WBID 1320A FDOT Districts FDOT Public Education Not Not Florida N/A B038 spill prevention and Completed N/A N/A N/A – including N/A Not provided N/A 2 and 5 Education Efforts provided provided Legislature erosion and sediment PFA control training to staff and contractors. A workshop for Marion County teachers and educators to provide Springs resources on springs, WBID 1320A SWFWMD/ Rainbow River Education Not Not N/A B039 Awareness for water issues and wildlife Completed N/A N/A N/A – including N/A Florida Springs Not provided N/A Conservation Efforts provided provided Educators which can be used in PFA Institute classroom to enhance teaching common core standards. Proposed project to construct centralized collection center for septic tank pumpage in lieu of current land application. Collection Rainbow River Collection Center Wastewater center would process Basin and Private Interest N/A B040 for Septic System Service Area Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A pumpage and discharge Silver Spring Pumpage Expansion into municipal collection Basin system. Project is conceptual. SB 550 would ban land application of septic pumpage effective 2016. FDACS will provide at least $250,000 in BMP WBID 1320A FDACS Cost- Agriculture Not Not FDACS Cost- FDACS N/A B041 cost-share for Silver Underway 2020 N/A N/A – including N/A Not provided N/A Share Programs BMPs provided provided Share Springs/Rainbow Springs PFA BMAP areas.

Page 55 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number To help focus cost-share expenditures and BMP implementation follow- FDACS up, FDACS will review WBID 1320A Refinement of Agriculture Not Not FDACS N/A B042 rule-adopted cow/calf and Underway 2020 N/A N/A – including N/A Not provided Not provided N/A Appropriate BMPs provided provided equine BMPs to identify PFA BMPs practices likely to have greatest nutrient load reduction benefits. Formation of technical agriculture committee consisting of representatives from local interest groups, local government, WMDs, and UF–IFAS Technical state agencies. Group WBID 1320A Agriculture Not Not Extension N/A B043 Agriculture purpose would be to Underway 2020 N/A N/A – including N/A Not provided Not provided N/A BMPs provided provided Marion County Committee ensure consistent and PFA accurate information for pollutant load contribution associated with agricultural uses and evaluate effectiveness of BMPs. As part of BMAP, inventories have been developed that estimate relative nitrogen loading from different sources or categories of land use in basins. Concerns have been expressed that amount of nitrogen load allocated to cattle may not accurately reflect key Assessment of characteristics of Florida Role of Beef UF–IFAS cow-calf production WBID 1320A Cattle in Nitrogen Florida Extension N/A B044 system. These issues Study Underway 2019 N/A N/A – including N/A $495,000 N/A Not provided N/A Loading in Silver Legislature Marion County include typical cattle PFA and Rainbow stocking rates on pasture, Springs Basin low inputs of commercial nitrogen fertilizer to pasture systems, diets that are based on C4 (i.e., warm climate) grasses which have relatively low nitrogen concentration, nitrogen levels in dung and urine that are not comparable to those of dairy animals or beef

Page 56 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number cattle on feedlot, significant gaseous losses of nitrogen from animal waste, capability of grass roots to efficiently capture nitrogen as it passes through rooting zone, and amount of nitrogen stored in below- ground organs of pasture grasses. More accurate quantification of these characteristics for specific conditions of regional production systems will aid assessments of nitrogen loading from cattle operations. In 2015, FDACS OAWP adopted revised vegetable and agronomic crop manual that includes Revised specific nutrient and WBID 1320A Vegetable and Agriculture Not Not FDACS N/A B045 irrigation management Completed 2015 N/A N/A – including N/A Not provided Not provided N/A Agronomic Crop BMPs provided provided BMPs for plastic mulch, PFA BMP Manual bare ground, sugar cane, hay/silage, and greenhouse production systems. In early 2016, FDACS adopted dairy manual that WBID 1320A Dairy BMP Agriculture Not Not FDACS N/A B046 targets dairies that do not Completed 2016 N/A N/A – including N/A Not provided Not provided N/A Manual BMPs provided provided have DEP-issued NPDES PFA permits. OAWP adopted poultry WBID 1320A Poultry BMP Agriculture Not Not FDACS N/A B047 BMP manual in June Completed 2016 N/A N/A – including N/A Not provided Not provided N/A Manual BMPs provided provided 2016. PFA Additional emphasis was given to IA in 2016 legislation, particularly Chapter 2016-1, Laws of Florida. Among its provisions, law requires WBID 1320A Enhanced IA enhancement and Agriculture Not Not FDACS N/A B048 Underway 2018 N/A N/A – including N/A Not provided Not provided N/A Program formalization of OAWP BMPs provided provided PFA IA policies and procedures through rulemaking. Rulemaking will be initiated prior to January 1, 2017. Once rulemaking is completed,

Page 57 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number FDACS will implement enhanced IA Program and more detailed reporting, as prescribed by legislation, on site visits and surveys will be provided on annual basis. Enhanced IA Program, as component of FDACS BMP Program, will be designed: • To provide accurate and timely information on status of BMP enrollments. • To provide accurate and timely information on extent of BMP implementation. • To provide information from which reports on BMP enrollment and implementation can be made to BMAP stakeholders and to annual report required by Chapter 2016-1, Section 34, Laws of Florida. • To inform educational, research, and technical assistance efforts targeted to strengthen BMP implementation and effectiveness. • To guide review and potential revision of BMP manuals. Project objective is to design and construct sanitary sewer system which will remove from Septic Tank Rainbow Fox Meadow service 275 septic tanks Phase Out, Springs Basin Not Not City of Ocala N/A B049 Sewer Expansion from associated single- Wastewater Planned 2020 TBD N/A N/A $4,705,000 City Not provided and Silver provided provided Project family residential lots. Service Area Springs Basin Septic tanks contribute to Expansion TN and TP impairment of Rainbow Springs and Rainbow River.

Page 58 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Project objective is to design and construct sanitary sewer system that will remove from service Package Plant Rainbow Fairfield Village package plant serving 350 Phase Out, Springs Basin Not City of Ocala N/A B050 Sewer Expansion mixed-use residential lots Wastewater Planned 2020 TBD N/A N/A $875,000 N/A City Not provided and Silver provided Project and 1 community center. Service Area Springs Basin Package plant contributes Expansion to TN and TP impairment of Rainbow Springs and Rainbow River. Project objective is to design and construct sanitary sewer system that will remove from service Septic Tank Rainbow Timberwood 180 septic tanks from Phase Out, Springs Basin Not Not City of Ocala N/A B051 Sewer Expansion associated single-family Wastewater Planned 2020 TBD N/A N/A $3,316,000 City Not provided and Silver provided provided Project residential lots. Septic Service Area Springs Basin tanks contribute to TN Expansion and TP impairment of Rainbow Springs and Rainbow River. County will adopt and enforce Fertilizer Management and Landscape Irrigation Ordinances. Benefits: Reduce volume Alachua County Regulations, Fertilizer and of runoff from over Environmental Ordinances, Not Silver Springs Not Not County General N/A S001 Landscape irrigation and reduce Completed N/A N/A N/A Not provided N/A Protection Dept. and provided Basin provided provided Fund Irrigation Codes nutrient loading from use (ACEPD) Guidelines of fertilizers. Implements Alachua County Comp Plan Conservation and Open Space Element – Surface Water Systems Objective 4.6 Regulations, Stormwater Adopted policy prohibits Villages Center Ordinances, Not Silver Springs Not Not N/A S002 Management- illicit discharges for Completed N/A N/A N/A CDD Not provided N/A CDD and provided Basin provided provided Policy Adoption VCDD No. 1 Guidelines Golf course resource management plans are applicable to unincorporated portion of Regulations, Lake County Golf Course Lake County for new and Ordinances, Not Silver Springs Not Not Economic N/A S003 Resource Completed N/A N/A N/A Lake County Not provided N/A existing golf courses; and provided Basin provided provided Growth Management Plan regulatory approach will Guidelines provide protection to groundwater and surface water.

Page 59 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Guide for lakefront land owners on water resource issues including shoreline protection, stormwater BMPs, erosion, and Regulations, Lake County Lake County aquatic plants. Outreach Ordinances, Not Silver Springs Not Not N/A S004 Shoreline Completed N/A N/A N/A County Not provided N/A Public Works program targeted at and provided Basin provided provided Protection Guide county residents. Inform Guidelines property owners of better land management practices to improve water quality protection. Acquisition of 4,400 ac of sandhills and pasture land previously known as Avatar property. Forest is within 2- and 10-yr modeled capture areas for Silver Springs and contains Indian Lake, karst feature directly Acquisition of DEP – Division Marion connected to Upper Land Silver Springs FCT/ Marion S005 Indian Lake State Completed 2007 N/A N/A 4,400.0 $78,000,000 N/A Not provided N/A of State Lands County Floridan aquifer (UFA), Acquisition Basin County Forest and numerous sinkholes. Restoration of native sandhills is underway. Forest was acquired with FCT contributing $76,000,000, with additional $2,000,000 provided by Marion County. Acquisition of 346 ac of undeveloped land directly across SR 35 from Silver Springs State Park. Land was acquired under Florida's First Magnitude Springs Project by Division of State Lands. Silver Springs By preserving land DEP – Division Marion Land Silver Springs S006 Conservation around springs, project Completed 2005 N/A N/A 346.0 $7,847,000 N/A FCT Not provided N/A of State Land County Acquisition Basin Area will aid in protection of springs, karst windows, and Floridan aquifer from effects of commercial, residential, and agricultural runoff; clearcutting and mining; and unsupervised recreation.

Page 60 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number No increase in surface runoff of pollutants County Fee because of land use Simple/ Wild change, continued aquifer Spaces and Public recharge and ecosystem/ Little Orange Places Sales Tax/ habitat preservation; Land Silver Springs ACEPD Not provided S007 Creek Land Completed 2012 N/A N/A 699.0 $795,438 N/A North American Not provided N/A implement Alachua Acquisition Basin Acquisition Wetland Act County Comp Plan Grant/ Alachua Conservation and Open Conservation Space Element – Alachua Trust County Forever Policy 6.2.1. No increase in surface runoff of pollutants because of land use change, continued aquifer Alachua Phifer Flatwoods recharge and ecosystem/ Conservation Land Acquisition habitat preservation; Land Silver Springs County Forever ACEPD Trust, Florida S008 Completed 2006 N/A N/A 600.0 $2,882,239 N/A Not provided N/A #1 – Lochloosa implement Alachua Acquisition Basin Bond Proceeds Conservation Creek County Comp Plan Trust Conservation and Open Space Element – Alachua County Forever Policy 6.2.1. No increase in surface runoff of pollutants because of land use change, continued aquifer Phifer Flatwoods recharge and ecosystem/ Land Acquisition habitat preservation; Land Silver Springs County Forever ACEPD N/A S009 #2 – Lochloosa Completed 2009 N/A N/A 380.0 $1,170,864 N/A Not provided N/A implement Alachua Acquisition Basin Bond Proceeds Creek; Little County Comp Plan Lochloosa Creek Conservation and Open Space Element – Alachua County Forever Policy 6.2.1. No increase in surface runoff of pollutants because of land use change, continued aquifer Longleaf recharge and ecosystem/ Flatwoods habitat preservation; Land Silver Springs County Forever ACEPD SJRWMD S010 Completed 2003 N/A N/A 1,388.5 $2,259,654 N/A Not provided N/A Preserve Land implement Alachua Acquisition Basin Bond Proceeds Acquisition County Comp Plan Conservation and Open Space Element – Alachua County Forever Policy 6.2.1.

Page 61 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number No increase in surface runoff of pollutants because of land use change, continued aquifer County Forever recharge and ecosystem/ Bond Proceeds/ Rayonier Tract habitat preservation; Land Silver Springs SJRWMD/ ACEPD SJRWMD S011 Acquisition Completed 2008 N/A N/A 1,450.0 $4,855,506 N/A Not provided N/A implement Alachua Acquisition Basin Federal Forest (River Styx) County Comp Plan Legacy Program Conservation and Open (FFLP) Space Element – Alachua County Forever Policy 6.2.1. No increase in surface runoff of pollutants because of land use change, continued aquifer recharge and ecosystem/ Freddy Wood County Forever habitat preservation; Land Silver Springs ACEPD NRCS S012 Land Tract Completed 2008 N/A N/A 600.0 $1,136,000 N/A Bond proceeds/ Not provided N/A implement Alachua Acquisition Basin Acquisition FFLP County Comp Plan Conservation and Open Space Element – Alachua County Forever Policy 6.2.1. Acquisition of land around Lochloosa Lake and around north side of SJRWMD Ad LochLoosa Orange Lake for Valorem/ Alachua Wildlife Lochloosa Wildlife Land Silver Springs SJRWMD S013 Completed 2003 N/A N/A 28,337.0 $16,058,211 N/A Preservation 2000/ Not provided N/A County Conservation Conservation Area. Acquisition Basin Alachua County Area Benefits: No increase in Cost-Share surface runoff of pollutants because of land use change. Addresses surface water discharge. Project provided water quality SJRWMD/ treatment for 4 drainage FDOT/ DEP/ City of Ocala basins in City of Ocala. Community SJRWMD, Silver Spring/ Silver Springs Not Not City of Ocala S014 Basins historically Not provided Completed 2018 617 207 738.3 $3,501,034 Budget Issue Not provided FDOT, DEP River Pollution Basin provided provided discharged untreated Request (CBIR)/ Reduction Project stormwater runoff to City Stormwater Half-Mile Creek via SR Utility Fees 40/Silver Springs Blvd. Storm sewer system.

Page 62 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Addresses surface water. Eastern urban area of Gainesville and Alachua County. Widening of SR 20 from 2- to 4-lane road with stormwater runoff treatment; 3 wet detention Wet Silver Springs Not FDOT District 2 N/A S015 SR 20 Widening ponds installed to treat Detention Completed 2006 3,665 362 355.0 $10,763,788 State Legislature $10,763,788 N/A Basin provided stormwater runoff along Pond with more than 100 ditch blocks to capture runoff. Benefits: Pollutant removal by treatment of stormwater runoff. No previous treatment. 238395-4, SR 500 (US Hwy. 441) from Martin SR 500 (US Hwy. Wet Luther King to Lake Ella Silver Springs Not Not FDOT District 5 N/A S017 441) Design Detention Completed 2014 11 8 13.9 State Legislature Not provided N/A Rd.– Basin C/ Wet Basin provided provided Project-Basin C Pond detention; open basin discharge to Lake Griffin. 238395-4, SR 500 (US Hwy. 441) from Martin SR 500 (US Hwy. Luther King to Lake Ella Retention Silver Springs Not Not FDOT District 5 N/A S019 441) Design Completed 2014 59 8 9.9 State Legislature Not provided N/A Rd.– Basin E/ Dry BMP Basin provided provided Project-Basin E retention; open basin discharge to Lake Griffin. 238677-1, SR 35 from SR SR 35 Design 464 (Maricamp Rd.) to Retention Silver Springs Not Not FDOT District 5 N/A S027 Completed 2012 3 0 3.3 State Legislature Not provided N/A Project-Pond 9 SR 40 – Basin 9 (Pond 9)/ BMP Basin provided provided Dry rRetention. Construction of stormwater wetland to treat runoff from US Hwy. 441 and adjacent commercial land uses prior to discharge to County Marion County 31st St. DEP/ active sinkhole. Project Wetland Silver Springs Not Stormwater Not Office of the S030 Stormwater Completed 2009 3 19 26.0 $600,000 Not provided SJRWMD was jointly funded by Treatment Basin provided Assessment/ provided County Engineer Retrofit Marion Conty, DEP, and SJRWMD/ DEP SJRWMD. Post- construction monitoring found 72 % reduction in nitrate concentrations in wetland.

Page 63 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Addresses surface water discharge. Construction of pump station to intercept runoff from 42.6 ac of SR 40 right-of-way and adjacent commercial land uses prior to Marion County discharge to Half-Mile County Marion County DEP/ Silver Creek, tributary of Silver Stormwater Retention Silver Springs Not Not Office of the SJRWMD/ S031 Springs/River River. Runoff is pumped Completed 2010 1,922 625 505.0 $1,766,828 Assessment/ Not provided BMP Basin provided provided County Engineer FDOT Pollution to retention pond located SJRWMD/ DEP/ Reduction Project on state lands across from FDOT Silver Springs Attraction. Marion County was lead agency for engineering design and construction. Project partners each contributed funds towards construction. Project was field-scale research installation of Bold and Gold™ soil amendment. Project goal was to assess pollutant- DEP/ Retention removal potential of 12 in University of BMP Retrofit County Marion County Hunter's Trace of Bold and Gold™. Central Florida with Not Silver Springs Not Stormwater Not Office of the S032 Retention Area Construction and Completed 2009 N/A 56.0 $500,000 Not provided (UCF)/ Nutrient- provided Basin provided Assessment/ provided County Engineer Retrofit postconstruction SJRWMD/ Reducing SWFWMD/ DEP monitoring conducted SWFWMD Media through UCF. Final report to DEP found 50 % removal of nitrogen through soil amendment layer. Proposed project to construct retention area to Marion County Country Gardens County treat stormwater runoff Retention Silver Springs Not Office of the N/A S033 Stormwater Planned 2017 14 3 33.2 $188,500 Stormwater Not provided N/A from residential land uses BMP Basin provided County Engineer Retrofit Assessment that currently discharge to relict sinkhole/quarry. Construction of new sewer line south of city along US Hwy. 441. Sewer line will allow DEP/ Marion US Hwy. 441 commercial and Wastewater County Economic City of DEP/ Marion Silver Springs Not Not S034 Sewer Main residential area to hook Service Area Completed 2016 1,889 N/A N/A $1,000,000 Development Not provided Belleview County Basin provided provided Expansion up to centralized system. Expansion Infrastructure Project will provide 79 Grant (EDIG) central sewer connections to rapidly developing corridor, with potential

Page 64 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number for up to 60 more connections. Project includes connection of remaining septic tanks in city at no DEP- cost to homeowners. $5,000,000, Citywide Septic City/ DEP, Septic tanks contribute 26 SJRWMD – DEP/ Tank and Well Septic Tank Silver Springs SJRWMD/ Not City of Ocala S035 % to 40 % of pollutant Underway 2018 20,321 N/A N/A $10,500,000 N/A $5,000,000 SJRWMD Elimination Phase Out Basin Florida provided load to groundwater in Florida Program Legislature springshed. Elimination Legislature – of septic tanks will reduce $500,000 nitrogen loading to Silver Springs by 20,321 lbs/yr. Connection of White Oak Package Plant Mobile Home Park Phase Out, Package Plant Silver Springs Not Not Not City of Ocala N/A S036 (MHP), Magnolia Wastewater Completed 2015–16 546 N/A N/A Not provided Not provided Abatement Basin provided provided provided Gardens, and 301 Plaza to Service Area central sewer. Expansion Install 3-mi-long force main that will reroute all County Divert sewage from Silver Utilities Fund Wastewater Flows Springs Regional Package Plant County Utilities – $563,057 from Silver wastewater plant to SSS Phase Out, Marion County DEP, Silver Springs Not Fund/, DEP DEP TMDL S037 Springs Regional WWTF. Route of new Wastewater Completed 2015 16,438 N/A N/A $1,023,114 S0628 Utilities SJRWMD Basin provided TMDL Fund/ Fund – WWTF to Silver force main will allow Service Area SJRWMD $463,056.96 Springs Shores other decentralized Expansion SJRWMD – (SSS) WWTF wastewater plants in $100,000 vicinity of Silver Springs to connect in future. Upgrading existing WWTP located in SSS to reclaimed quality effluent Marion County SSS WWTF standards. Utility WWTF Silver Springs Not N/A S038 Completed 2015 10,331 N/A N/A $5,031,738 County Utilities $5,031,738 N/A Utilities Upgrade customers are already Upgrade Basin provided paying $5,031,738 for treatment facility upgrades. Villages Center WWTP includes anoxic Service Area basin for denitrification of WWTF Villages Center Not Silver Springs Not Not N/A S039 (VCSA) WWTP – NO , which reduces NO Nutrient Completed 2012 N/A N/A CDD Not provided N/A CDD 3 3 provided Basin provided provided Anaerobic discharge in WWTP Reduction Denitrification effluent. Little Sumter WWTP includes anoxic Service Area basin for denitrification of WWTF Villages Center Not Silver Springs Not Not N/A S040 (LSSA) WWTP – NO , which reduces NO Nutrient Completed 2012 N/A N/A CDD Not provided N/A CDD 3 3 provided Basin provided provided Anaerobic discharge in WWTP Reduction Denitrification effluent. North Sumter WWTP includes anoxic WWTF Village Center Not Silver Springs Not Not North Sumter N/A S041 Utilities (NSU) basin for denitrification of Nutrient Completed 2012 N/A N/A Not provided N/A CDD provided Basin provided provided County Utility WWTP – NO3, which reduces NO3 Reduction

Page 65 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Anaerobic discharge in WWTP Dependent Denitrification effluent. District

Reuse projects to 3 golf courses and city parks and recreation sites. Courses Reclaimed Not Silver Springs Not Not Not City of Ocala Not provided S042 Reuse Projects may be served by any of Completed 2015–16 N/A N/A Not provided Not provided Water provided Basin provided provided provided sewer facilities because of infrastructure configuration. Public access reuse system provides Villages Center VCSA WWTP – Reclaimed Silver Springs Not Not N/A S043 reclaimed water for Completed 2012 21,706 N/A N/A CDD Not provided N/A CDD Reuse Water Basin provided provided irrigation of golf courses and roadways. Public access reuse system provides Villages Center LSSA WWTP – Reclaimed Silver Springs Not Not N/A S044 reclaimed water for Completed 2012 45,835 N/A N/A CDD Not provided N/A CDD Reuse Water Basin provided provided irrigation of golf courses and roadways. North Sumter Public access reuse North Sumter Villages Center County Utility NSU WWTP – system provides Reclaimed Silver Springs Not Not County Utility S045 Completed 2012 42,974 N/A N/A Not provided N/A CDD Dependent Reuse reclaimed water for Water Basin provided provided Dependent District irrigation of golf courses. District Public access reuse Villages Center Central Sumter CSU WWTP – system provides Reclaimed Silver Springs Not Not S046 Completed 2013 8,584 N/A N/A CSU Not provided N/A CDD Utility (CSU) Reuse reclaimed water for Water Basin provided provided irrigation of golf courses. Fertilizer FDOT O&M fertilizer Fertilizer Silver Springs FDOT District 5 N/A S047 Completed N/A 27,508 N/A N/A N/A N/A N/A N/A N/A Cessation cessation. Cessation Basin Train staff and certain subcontractors to aid in CDD/ North identification of illicit Sumter County Villages Center discharges as well as Education Silver Springs Not N/A S048 Staff Training Completed N/A N/A N/A N/A N/A Utility Dependent Not provided N/A CDD reduce/eliminate illicit Efforts Basin provided District/ Sumter discharges and improper Landing CDD disposal of waste internally. Pond maintenance to ensure optimal pollutant removal and verify performance is at design Villages Center Sumter criteria by monthly Stormwater Silver Springs Not CCD/ Sumter S049 Pond Maintenance Completed N/A N/A N/A N/A N/A Not provided N/A CDD Landing CDD checks and treating System O&M Basin provided Landing CDD nuisance species such as algae, grasses, hydrilla, spike rush, duckweed, cattails, etc., as necessary.

Page 66 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Routine stormwater Stormwater system inspections, Villages Center Sumter Stormwater Silver Springs Not CDD/ Sumter S050 System cleaning, and Completed N/A N/A N/A N/A N/A Not provided N/A CDD Landing CDD System O&M Basin provided Landing CDD Inspections maintenance performed as needed. Improved stormwater conveyance system. Area Skyline Dr. Stormwater Town of Lady covers Skyline Dr. north Not Silver Springs Not DEO S051 Drainage System Completed 2014 N/A N/A $1,300,000 Town/ DEO Not provided N/A Lake to Ray St., west to provided Basin provided Improvement Rehabilitation Summit St., and east to High St.. Townwide curb and gutter cleaning and catch basin vacuuming. Lady Lake DEP/ City of Removes pollutants and Town of Lady Stormwater BMP Clean Not Silver Springs Not Ocala S052 debris before entering Completed N/A N/A N/A N/A Town Not provided N/A Lake System Out provided Basin provided (Potentially) storm sewer system. Maintenance Benchmark frequency for this routine maintenance is quarterly or as needed. O&M of pump station and collection system constructed as part of Marion County portion of Silver/Springs River Pollution Reduction Project. Activities include SR40 Stormwater servicing and repair of Stormwater Silver Springs Not FDOT District 5 N/A S053 Pump Station Completed N/A 249 33 42.6 $595,927 State Legislature Not provided N/A pump station and clean System O&M Basin provided O&M out of accumulated sediment. Construction cost is FDOT contribution to Marion County project. Treated acres are portion of drainage area in FDOT rights-of-way. Rehabilitation of 200 Sanitary Collection System City of brick manholes to date Sewer and Silver Springs Not Not N/A S054 Maintenance Completed 2010 N/A N/A N/A Not provided Not provided N/A Belleview and pipe replacement as WWTF Basin provided provided Program needed. Maintenance Maintenance program has used TV inspection on entire collection system. Slip lining of 175,000 ft Sanitary Collection System of clay pipe is complete Sewer and Silver Springs Not Not City of Ocala N/A S055 Maintenance Completed 2020 N/A N/A N/A Not provided Not provided N/A and 40,000 ft/yr WWTF Basin provided provided Program scheduled through 2020. Maintenance Lift stations are upgraded at rate of about 3 per yr. System and plants are

Page 67 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number SCADA controlled and flows can be rerouted.

Collection system maintenance program includes lift station maintenance and addition of SCADA. Capital Sanitary Collection System Marion County improvement plan (CIP) Sewer and Silver Springs Not N/A S056 Maintenance Completed N/A N/A N/A N/A N/A Not provided Not provided N/A Utilities calls for lift station WWTF Basin provided Program renovation every 10 yrs Maintenance and identifies pipe replacement needs. Pipes replaced as funding allows.

North Sumter Inspection of main Sanitary CDD/ North Villages Center County Utility Sanitary Sewer pipelines and manholes Sewer and Silver Springs Not Sumter County S057 Completed N/A N/A N/A N/A N/A Not provided N/A CDD Dependent Repairs and timely repair of sewer WWTF Basin provided Utility Dependent District, CSU and service line breaks. Maintenance District/ CSU

North Sumter Sanitary CDD/ North Villages Center County Utility Sanitary Sewer Cleaning of 10 % of Sewer and Silver Springs Not Sumter County S058 Completed N/A N/A N/A N/A N/A Not provided N/A CDD Dependent Cleaning collection system/yr. WWTF Basin provided Utility Dependent District/ CSU Maintenance District/ CSU North Sumter CDD/ North County Utility Sumter County Sanitary Dependent Utility Dependent Villages Center Lift Station VCSA Lift Station No. 12 Sewer and Silver Springs District/ CSU/ S059 Completed 2013 N/A N/A N/A $75,000 N/A District/ CSU/ Not provided N/A CDD Rehabilitation Rehabilitation. WWTF Basin Sumter Water Sumter Water Maintenance Conservation Conservation Authority Authority Sanitary VCSA Lift Station Nos. Villages Center Lift Station Sewer and Silver Springs N/A S060 4, 8, 13, and 14 Completed 2014 N/A N/A N/A $150,000 N/A CDD $150,000 N/A CDD Rehabilitation WWTF Basin Rehabilitation Maintenance VCSA List Station Nos. 16 and 33 Replace risers Sanitary Villages Center Lift Station and recoat wetwell; LSSA Sewer and Silver Springs N/A S061 Completed 2016 N/A N/A N/A $118,000 N/A CDD $118,000 N/A CDD Rehabilitation List Station No. 16 WWTF Basin Replace risers and recoat Maintenance wet well. Sanitary Villages Center Sanitary Sewer VCSA Sanitary Sewer Sewer and Silver Springs N/A S062 Completed 2016 N/A N/A N/A $250,000 N/A CDD $250,000 N/A CDD Replacement Replacement. WWTF Basin Maintenance

Page 68 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number All shopping centers and all 3 downtown areas Villages Center Street Not Silver Springs Not Villages Center N/A S063 Street Sweeping anywhere from 3 times Completed N/A N/A N/A N/A Not provided N/A CDD Sweeping provided Basin provided CDD per week to quarterly, depending on location. Street sweeping of state roads in urbanized areas that have curb and gutter. Includes US Hwy. 441, SR 26, SR 20, SR 24, SR 128, SR 222, and SR121. Areas are swept by City of Gainesville and contract personnel for City of SR Street FDOT. Minimum Street Silver Springs Not FDOT District 2 S064 Completed N/A 6,110 2,251 N/A N/A Not provided Not provided N/A Gainesville Sweeping benchmark sweeping Sweeping Basin provided frequency is quarterly. Performance benchmark for debris and sediment collected is 125 tons/yr. Benefits: Remove debris, sediment, and potential pollutants from streets. Prevent entry into storm sewer system. Townwide street sweeping to remove dirt and debris. Benchmark frequency is quarterly or as needed. Removal of Town of Lady Lady Lake – Street Silver Springs N/A S065 debris and potential Completed N/A 12 N/A N/A N/A $25,000 Town Not provided N/A Lake Street Sweeping Sweeping Basin pollutants prevents their entry into lakes. Performance benchmark is 250 cubic yds/yr of material removed. Lake Lochloosa and Orange Lake Watersheds. Study examined groundwater pathways through which nutrients Groundwater- enter Lakes Lochloosa U.S. Surface Water and Orange. Field Geological Interaction Study Silver Springs DEP S066 investigations to Study Completed 2007 N/A N/A N/A $64,000 N/A USGS $64,000 N/A Survey Lake Lochloosa Basin determine levels of TP (USGS) Area, Alachua and and TN in different Marion Counties aquifers associated with land use categories. Radon studies performed to estimate groundwater seepage into Lake

Page 69 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Lochloosa. Benefits: Better estimation of groundwater inputs of TP in TMDL models. SJRWMD has initiated Springs Protection Initiative and recognizes effort as strategic priority for agency. Initiative includes 3 major components: projects, regulation, and science. Science component (SPIS) acknowledges that effective management of springs requires understanding of relative influences and manageabilities of numerous natural and anthropogenic factors that affect their ecological health, and that additional interdisciplinary research is needed to achieve this goal. Workgroups include SJRWMD Springs Springshed Supergroup Protection Silver Springs Not SJRWMD UF S067 (Surface Water, Ground Study Completed 2017 N/A N/A N/A N/A SJRWMD Not provided N/A Initiative Science Basin provided Water, and Nitrogen (SPIS) Biogeochemistry) and Springs Ecosystem Supergroup (Hydrology and Hydrodynamics, Biology, and Physicochemistry). Also, WMD has contracted with UF Water Institute for support. Work will focus on Silver Springs system and its springshed. Interdisciplinary workgroups will build on existing work and develop and merge data and models focusing on goal of providing sound scientific foundation for development of cost- effective approaches for management of activities to address issues in Silver

Page 70 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Springs. Findings and results of 3-yr effort are expected to support future BMAP activities. SJRWMD has core monitoring in/on Silver Springs, Silver River, and contributing area to Silver Springs. Core monitoring consists of discharge monitoring, surface and groundwater levels, surface water and groundwater quality, and biological monitoring. As SJRWMD Water part of Springs Protection Monitoring/ Resource Initiative, WMD has Silver Springs Not SJRWMD USGS S068 Data Completed N/A N/A N/A N/A N/A SJRWMD Not provided N/A Information and added discharge Basin provided Collection Data Collection monitoring site, increased number and sampling frequency of surface water and groundwater quality sites, increased biological monitoring, and added continuous water quality monitoring at 5 sites in Silver River. Upon conclusion of SPIS, some monitoring sites were eliminated. Alachua County. Training and education for City of Water Quality contractors, government, Gainesville Clean Gainesville/ Education Silver Springs ACEPD S069 Protection BMP and citizens in Completed N/A N/A N/A N/A N/A $2,000 Water Partnership Not provided N/A FDOT Efforts Basin Training sedimentation and erosion Cost-Share District 2 control to improve stormwater quality. Alachua County. Implement social marketing campaign to motivate citizens to scoop, bag, and trash dog City of wastes at home and in Gainesville Clean Gainesville/ Pet Waste Education Silver Springs Not ACEPD S070 community. Benefits: Completed N/A N/A N/A N/A $40,655 Water Partnership Not provided N/A FDOT Outreach Efforts Basin provided Reduces bacteria and Cost-Share District 2 nutrient sources in all watersheds. Implements Alachua County Comp Plan Conservation and Open Space Element –

Page 71 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Surface Water Systems Objective 4.6. Alachua County. Implement social marketing campaign designed to get citizens to keep landscaping debris out of roads and City of stormwater collection Gainesville Clean Gainesville/ Landscape Debris systems. Benefits: Education Silver Springs Not Not ACEPD S071 Completed 2010 N/A N/A N/A Water Partnership Not provided N/A FDOT Social Marketing Reduces bacteria and Efforts Basin provided provided Cost-Share District 2 nutrient sources in all watersheds. Implements Alachua County Comp Plan Conservation and Open Space Element – Surface Water Systems Objective 4.6. Alachua County. Conduct targeted public outreach to encourage water conservation and rain City of harvesting. Includes rain Water Gainesville Clean Gainesville/ barrel sales and LID Education Silver Springs Not Not ACEPD S072 Conservation and Completed N/A N/A N/A N/A Water Partnership Not provided N/A FDOT promotion. Benefits: By Efforts Basin provided provided LID Cost-Share District 2 harvesting rainwater and keeping stormwater on site, stormwater and pollutants it transports is decreased. Gainesville urban area and Alachua County. Monitor and assess street sweepings to quantify nutrient reductions and subsequent potential water quality improvements. Benefits: Education City of Quantifying Provide data to quantify Efforts, Gainesville Clean Gainesville/ Nutrient Silver Springs Not ACEPD S073 nutrients in street Monitoring/ Completed 2016 N/A N/A N/A $38,940 Water Partnership Not provided N/A FDOT Improvement in Basin provided sweepings and assess Data Cost-Share District 2 Street Sweeping potential for water quality Collection improvement. Implements Alachua County Comp Plan Conservation and Open Space Element – Surface Water Systems Objective 4.6 and policies.

Page 72 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Gainesville urban area and Alachua County. Alachua County. Implement social marketing campaign designed to get citizens to make landscaping behavior changes that reduce nutrients in stormwater. Benefits: Reduces nutrient sources in all watersheds. Implements Alachua County Comp Plan Conservation and Open Space Element – Surface City of Landscaping Water Systems Objective Gainesville Clean Gainesville/ Education Silver Springs Not ACEPD S074 Behavior Change 4.6. Benefits: Behavior Underway TBD N/A N/A N/A $25,000 Water Partnership Not provided N/A FDOT District Efforts Basin provided Social Marketing changes to reduce nutrient Cost-Share 2 inputs to stormwater; implement Alachua County Comp Plan Conservation and Open Space Element – Education and Outreach Objective 2.2; Surface Water Systems Objective 4.6; Alachua County Unified Land Development Code (ULDC), Chapter 407 Article 4 Landscaping – 406.43 Water Resources Buffers; ULDC Article 9 Stormwater Management. North Sumter Stormwater Amenity bill inserts to CDD/ North Villages Center County Utility Management- address what residents Education Silver Springs Not Sumter County S076 Completed N/A N/A N/A N/A $2,600 Not provided N/A CDD Dependent Amenity Bill can do to reduce Efforts Basin provided Utility Dependent District Inserts stormwater impacts. District Villages Villages public service Media Group/ Stormwater telephone book aid CDD/ North Villages Center North Sumter Management- explaining purpose of Education Silver Springs Not Not Sumter County S077 Completed N/A N/A N/A N/A Not provided N/A CDD County Utility Telephone Book stormwater program and Efforts Basin provided provided Utility Dependent Dependent Aid how to participate in District District stormwater activities. Stormwater Created public service Management- newspaper column in Villages Center Villages Education Silver Springs Not Not S078 Public Service Villages newspaper to Completed N/A N/A N/A N/A Villages Not provided N/A CDD Media Group Efforts Basin provided provided Newspaper create awareness of Column effects of illicit

Page 73 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number discharges and illegal disposal. North Sumter CDD/ North County Utility Sumter County Dependent Stormwater Monthly public Utility Dependent Villages Center District/ CSU/ Management- Education Silver Springs Not S079 educational meeting with Completed N/A N/A N/A N/A $6,000 District/ CSU/ Not provided N/A CDD Sumter Water CDD School/ Efforts Basin provided residents. Sumter Water Conservation Hometown Social Conservation Authority/ Authority UF–IFAS Provide illicit discharge awareness notifications and educational material CDD/ North Illicit Discharge to area businesses to Villages Center North Sumter Education Silver Springs Not Sumter County S080 Awareness make them aware of Completed N/A N/A N/A N/A $250 Not provided N/A CDD County Efforts Basin provided Utility Dependent Notifications hazards associated with District illicit discharges and improper disposal of waste. Section of district website Stormwater Villages Center Sumter for residents provides Education Silver Springs Not Not CDD/ Sumter S081 Pollution on Completed N/A N/A N/A N/A Not provided N/A CDD Landing CDD education and links on Efforts Basin provided provided Landing CDD Website stormwater pollution. Town of Lady Lake uses consultant for education and outreach. Activities include PSAs in cooperation with City of Leesburg and SJRWMD, Lady Lake distribution of pamphlets, Town of Lady NPDES Permit Education Silver Springs Not N/A S082 educational website, illicit Completed N/A N/A N/A N/A $7,500 Town Not provided N/A Lake Education and Efforts Basin provided discharge inspection and Outreach education program, utility bill inserts, and informational displays for proper irrigation techniques and landscape management. Activities include distribution of pamphlets and recurring and nonrecurring public outreach events. Other Lake County efforts include Lake County NPDES Permit Education Silver Springs Not N/A S083 construction site pollution Completed N/A N/A N/A N/A $12,000 Lake County Not provided N/A Public Works Education and Efforts Basin provided prevention, illicit Outreach discharge inspection and education, resource support of County Extension training in FFL/FYN and Adopt-a-

Page 74 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Lake Program, formerly Watershed Action Volunteers (WAV) Program. Landscaper education about BMPs for landscapers and those who hire landscapers. Seminar was held in Lake County Landscaper BMP cooperation with Lake Education Silver Springs N/A S084 Completed 2010 N/A N/A N/A $1,276 N/A County $1,276 N/A Public Works training County Agricultural Efforts Basin Center to educate landscapers about BMPs and BMP brochures were mailed out countywide to landscape companies. Addresses drainage well discharge. Retrofit Section 319(h) SkimBoss DEP/ City Installation of SkimBoss Drainage Silver Springs Grant/ City Not City of Ocala S085 Filtration System Underway 2019 1,320 309 336.0 $236,397 $5,000 Not provided (Potentially) Filtration System with Well Basin Stormwater Utility provided – Tuscawilla Pond Bold and Gold™ media – Fees Tuscawilla Pond. Addresses drainage well SkimBoss discharge. Retrofit Section 319(h) DEP/ City Filtration System Installation of SkimBoss Drainage Silver Springs Grant/ City Not City of Ocala S086 Underway 2019 104 N/A 73.0 $236,397 $5,000 Not provided (Potentially) – Chazal Park Filtration System with Well Basin Stormwater Utility provided Pond Bold and Gold™ media – Fees Chazal Park Pond. Silver Springs Addresses surface water Protection/ discharge. Silver Springs TMDL/ FDOT/ DEP/ FDOT/ Stormwater Silver Springs Not City of Ocala S087 Protection/Stormwater Not provided Underway 2018 460 N/A 91.0 $3,000,000 $10,000 City Stormwater Not provided City Nutrient Basin provided Nutrient Reduction Utility Fees Reduction Project Project. (Cameo Pond) Project proposes $1,400,000 through FY 2019 for retrofit of county-owned drainage retention areas in Silver Springs BMAP area. Bold and Gold™ Retention Number and location of Marion County Stormwater BMP Retrofit County DRAs retrofited depends Not Silver Springs Not Not Office of the N/A S088 Retrofits in Silver with Nutrient Underway 2019 N/A $1,400,000 Stormwater $1,400,000 N/A on several factors provided Basin provided provided County Engineer Springs BMAP Reducing Assessment including potential load Area Media reductions, land availability and location in PFAs identified in BMAP. Project is currently in preliminary scoping stages and is

Page 75 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number identified in adopted 2014 Stormwater Implementation Plan. Management plan for Silver Springs State Park was formally amended in May 2014 to account for inclusion of former Silver Springs attraction into Silver River State Park. In addition to change in park name, management goals were developed to improve water quality, specifically to remove nitrate from surface discharges. Removal of animals and animal enclosures on Ross Allen Silver Springs Island will reduce nitrate DEP – Division State Park imputs to Silver River and Not Silver Springs Not Not of Recreation N/A S089 Management Plan Study Planned N/A N/A N/A N/A DEP Not provided allow for existing water provided Basin provided provided and Parks Amendment – retention berm to be Runoff breached to reconnect wetlands to river. Evaluation of stormwater management system of park and amount of impervious area, particularly in parking lots, will also be undertaken. Impervious areas in parking lots and buildings will be removed and restored to natural communities. Sheet flow will be restored and stormwater system improved and maintained. Management plan for Silver Springs State Park was formally amended in Silver Springs May 2014 to account for State Park inclusion of former Silver DEP- Division Management Plan Springs attraction into Septic Tank Silver Springs Not Not of Recreation N/A S090 Completed 2015 2,018 N/A N/A $977,490 DEP Not provided Amendment – Silver River State Park. In Phase Out Basin provided provided and Parks State Park Sewer addition to change in park Connection name, management goals were developed to connect park services in former Silver River State

Page 76 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Park to central sewer, eliminating nitrate inputs to aquifer and Silver River. Upgrade of WRF #2 to AWT treatment standard for TN and decommissioning of WRF #1. WRF #1, constructed in 1949, is trickling filter facility and is not designed for removal of City of Ocala WWTF nitrate. WRF #2 and #3 Silver Springs Not City – Not City of Ocala Not provided S091 Nitrogen Nutrient Completed 2016 42,311 N/A N/A $16,000,000 City have sufficient capacity to Basin provided $9,600,001 provided Reduction Project Reduction handle flows from WRF #1, and all plants will be interconnected to allow for routing of flows as needed. WRF #1 will remain operational as relay and to process stormwater for reuse. Upgrade existing WWTF to allow for advanced treatment and expand availability of reclaimed water for irrigation use. Project consists of construction of 2 3.25 mgd carrousels equipped with 3 100-horsepower mechanical surface City – aerators with variable- WWTF $8,304,000 City of Ocala frequency drives (VFDs) Nutrient City/ SJRWMD/ SJRWMD – Silver Springs Not City of Ocala SJRWMD S092 WRF 2 Nutrient and lower impeller and Reduction, Completed 2016 27,593 N/A N/A $12,144,000 Legislative $1,920,000 N/A Basin provided Reduction Plan anaerobic and anoxic Reclaimed Funding Legislative zone submersible mixers. Water Funding – This will allow City of $1,275,620 Ocala to reduce effluent TN to 3 mg/L or less; 500,000 gallons of day of public access reclaimed water will be made available from project, reducing draws on aquifer and increasing flows to springs. Management plan for DEP – Division Silver Springs Silver Springs State Park WWTF Not Silver Springs of Recreation N/A S093 State Park Planned TBD N/A N/A $1,976,335 N/A DEP $1,976,335 S089 was formally amended in Upgrade provided Basin and Parks Management Plan May 2014 to account for

Page 77 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Amendment – inclusion of former Silver Sewer Upgrades Springs attraction into Silver River State Park. In addition to change in park name, management goals were developed to provide maintenance of sewer system for former attraction. Existing system was in poor repair, potentially leaking nitrogen to headspring and river. DEP has developed BMPs for Enhancement of Environmental Quality on Florida Golf Courses manual, which highlights BMPs that can be implemented to offset impacts of golf courses on environment. Active sports complexes can have same impacts. One commonly used BMP is construction of closed system equipment Sports Field washdown area. Similar Regulations, Marion County Maintenance facilities would allow Ordinances, Silver Springs Not Not County General N/A S094 Planned N/A N/A N/A N/A Not provided N/A Parks Equipment Parks staff to wash down and Basin provided provided Fund Washdown Area mowers and other Guidelines equipment which have been used while maintaining sports fields. Four sites (Brick City Adventure Park, Rotary Sportsplex, Shocker Park and Ralph Russell Memorial Park) are all within 10 mi of Silver Springs and therefore should receive higher priority for scheduling construction of washdown facilities.

Page 78 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Project is inventory of stormwater facilities in Marion County Parks to identify and prioritize them for potential retrofits to enhance nitrogen removal. Retrofits would involve removing layer of soil Marion County Parks Retention Not Silver Springs Not County General N/A S095 from bottom of basins and Study Planned N/A N/A N/A N/A Not provided N/A Parks Pond Retrofits provided Basin provided Fund then constructing engineered soil matrix. Project goal is to retrofit specific stormwater basins to reduce groundwater pollution. Inventory will be conducted using GIS asset management tools. Project focuses on removal of OSTDS and connection to centralized wastewater facilities. A few parks in BMAP area Septic Tank Septic System are close to existing or Phase Out, Marion County Connection planned wastewater Not Silver Springs Not Not County General N/A S096 Wastewater Completed 72 N/A N/A Not provided N/A Parks Removal in facilities (Brick City provided Basin provided provided Fund Service Area County Parks Adventure Park, Rotary Expansion Sportsplex, and Baseline Rd. Trailhead). Project goal would be to remove as many septic systems within area as possible. DEP has 1 package plant wastewater facility located at Gore's Landing, flood-prone area located along . Current system is antiquated, may not meet Gore's Landing current sewage disposal Wastewater Marion County Not Silver Springs Not Not County General N/A S097 Package Plant standards and should be System Planned 45 N/A N/A Not provided N/A Parks provided Basin provided provided Fund Upgrade upgraded. Project goal is Upgrade to bring existing sewage treatment system into compliance with current standards and regulations while being mindful of potential park expansion. Exact dollar figures for

Page 79 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number project are currently unknown. South Portion – Project will provide for delivery of reclaimed quality effluent and consists of reclaimed pumps, control valves, metering stations and 21,600 ft of 16-in pipeline from SSS WWTP to Spruce Creek Golf and Country Club (SCGCC) golf course located in southeast quadrant of Marion County 12 to 14 mi from Silver Springs. SSS WWTP is currently permitted to treat 1.5 mgd and has potential of generating close to 1.0 mgd of reuse quality water based on current flows. Removes 54,794 lbs-TN/yr. \ SJRWMD – SSS Reuse to SJRWMD/ $1,596,000 Marion County SJRWMD/ Spruce Creek Reclaimed Silver Springs Not S098 North Portion – Project Underway 2015 – 2017 54,794 N/A N/A $3,192,000 Florida Legislative N/A Utilities Legislature Golf and Country Water Basin provided will provide for delivery Legislature Funding – Club of reclaimed quality $1,275,620 effluent and consists of reclaimed pumps, control valves, metering stations and 8,000 ft of 12-in pipeline from SSS WWTP to SSS golf course and Lake Diamond located in southeast quadrant of Marion County 7 to 10 mi from Silver Springs. SSS WWTP is currently permitted to treat 1.5 mgd and has potential of generating close to 1.2 mgd of reuse quality water based on current flows. This will reduce use of potable water for irrigation, improve flow at Silver Springs, and reduce nutrient load to

Page 80 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Silver Springs and Silver River.

Project goal is to develop method of maintaining 67.77 ac (Wrigley Fields, Brick City Adventure Park, Shocker Park, Rotary Sportsplex, Ralph Russell Memorial Park, Marion/Aquifer- and Belleview Friendly Sportsplex) of sports Marion County Fertilizer Not Silver Springs Not Not County General N/A S099 Fertilization fields to reduce, if not Planned N/A N/A N/A Not provided N/A Parks Reduction provided Basin provided provided Fund Program for eliminate, pollutant Sports Facilities loading while keeping fields healthy and safe. Program includes creation and use of specific fertilizer formulas on playing fields at various sports complexes that Parks Dept. manages. Landscaping Ordinance 2009-062 implements Regulations, Lake County Lake County Water Wise and FFL, tree Ordinances, Silver Springs Not Not Growth N/A S100 Landscaping Completed N/A N/A N/A N/A County Not provided N/A protection, and buffer and Basin provided provided Management Ordinance requirements: Codified Guidelines into LDR. Irrigation Ordinance 2009-17 implements Regulations, Lake County Lake County SJRWMD watering Ordinances, Silver Springs Not Not Growth N/A S101 Irrigation requirements and Completed N/A N/A N/A N/A County Not provided N/A and Basin provided provided Management Ordinance encourages water efficient Guidelines landscape design: Codified into LDR. County codes and ordiances require FFL principles to be applied in design and of landscapes Regulations, Lady Lake Town of Lady and irrigation systems. Ordinances, Silver Springs Not Not N/A S102 Landscape Completed N/A N/A N/A N/A Town Not provided N/A Lake Fertilizer application and Basin provided provided Requirements restrictions require 30 % Guidelines or more slow-release nitrogen and restrict frequency to "as needed." SJRWMD irrigation Regulations, Lady Lake Town of Lady schedule is adopted, Ordinances, Silver Springs Not Not N/A S103 Irrigation Completed N/A N/A N/A N/A Town Not provided N/A Lake specific water and Basin provided provided Scedules conservation measures are Guidelines

Page 81 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number encouraged, and 7 basic principles of water- efficient landscaping are incorporated. Intent is to establish minimum standards for development, installation, and maintenance of landscaped areas onsite with water use efficiency as goal without inhibiting use of creative landscape design. County code related to Regulations, Lady Lake Pet Town of Lady illicit discharges includes Ordinances, Silver Springs Not Not N/A S104 Waste Completed N/A N/A N/A N/A Town Not provided N/A Lake provisions requiring and Basin provided provided Management removal of pet waste. Guidelines SCADA installation and Villages Center VCSA WWTP – operation at VCSA plant WWTF Not Silver Springs Not Not N/A S105 Completed N/A N/A N/A CDD Not provided N/A CDD SCADA and collection system lift Upgrade provided Basin provided provided stations. SCADA installation and Villages Center LSSA WWTP – operation at LSSA plant WWTF Not Silver Springs Not Not N/A S106 Completed N/A N/A N/A CDD Not provided N/A CDD SCADA and collection system lift Upgrade provided Basin provided provided stations. SCADA installation and Villages Center NSU WWTP – operation at NSU plant WWTF Not Silver Springs Not Not N/A S107 Completed N/A N/A N/A CDD Not provided N/A CDD SCADA and collection system lift Upgrade provided Basin provided provided stations. SCADAiInstallation and Villages Center CSU WWTP – operation at CSU plant WWTF Not Silver Springs Not Not CSU S108 Completed N/A N/A N/A CSU Not provided N/A CDD SCADA and collection system lift Upgrade provided Basin provided provided stations. Baseline Square, Truck Package Plant stops at CR 326 and I-75 Phase Out, Marion County Package Plant Silver Springs Not Not Not Not provided S109 package plants connected Wastewater Completed 2015 412 N/A N/A Not provided Not provided Utilities Abatement Basin provided provided provided to central system. Service Area Removes 412 lbs TN/yr. Expansion No increase in surface runoff of pollutants U.S. Dept. of because of land use Agriculture change, continued aquifer (USDA) Farm recharge and Wild Spaces and Cypress Point and Ranch ecosystem/habitat Land Silver Springs Public Places ACEPD S110 Creamery Land Completed 2014 N/A N/A 600.0 $461,000 N/A Not provided N/A Land preservation; implement Acquisition Basin Surtax/ FRPP Acquisition Protection Alachua County Comp Cost-Share Program Plan Conservation and (FRPP) Open Space Element – Alachua County Forever Policy 6.2.1.

Page 82 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number No increase in surface runoff of pollutants because of land use change, continued aquifer recharge and Wild Spaces and Higginbotham ecosystem/habitat Land Silver Springs Public Places ACEPD USDA FRPP S111 Completed 2014 N/A N/A 600.0 $756,000 N/A Not provided N/A Ranch Acquisition preservation; implement Acquisition Basin Surtax/ FRPP Alachua County Comp Cost-Share Plan Conservation and Open Space Element – Alachua County Forever Policy 6.2.1. Develop strategy for Local Utilities/ addressing OSTDS and SJRWMD/ other wastewater DEP, FDOH, SWFWMD/ OSTDS 9-1-1 management issues. Goal Silver Springs Not Not S112 Study Underway 2018 N/A N/A N/A N/A Not provided Not provided Marion County Other Strategy is to enhance Basin provided provided Interested communication and Parties coordination among utilities and agencies. Marion County has applied to have Silver Springs Sandhill acquisition project added to Florida Forever list. Project would preserve 470 ac of high-recharge sandhills within 1 mi of Silver Springs. Project is located just south of Indian Lake State Forest and east of Cohadjoe Park (county). Majority of acreage is zoned for Silver Springs medium- and high-density Marion County Land Silver Springs Florida Forever/ N/A S113 Sandhill residential use, but 221 ac Completed 2017 N/A N/A 470.0 $4,432,979 N/A Not provided N/A Parks Acquisition Basin County Acquisition are currently used for improved cattle, with balance in pasture unmanaged hardwoods. Acquisition has been assigned to third-party nonprofit organization to close sale. Site has been acquired and is under management by Marion County Parks and Recreation. Consultants are being solicited to write state-required Unit Management Plan.

Page 83 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Project involves acquisition of 4,900 ac of managed forest land, owned by Rayonier, east of Indian Lake State DEP – Forest and west of CR $2,000,000 315. Acquired land will SJRWMD – DEP/ Marion Silver Springs be restored to appropriate Land Silver Springs DEP/ SJRWMD/ Not SJRWMD S114 Completed 2016 N/A N/A 4,900.0 $11,617,000 N/A $8,700,000 County Forest ecosystem and opened for Acquisition Basin Marion County provided Marion recreational use. Tract is County – identified in Heather $917,000 Island Florida Forever Project and as U.S. Forest Service Forest Legacy Project: Silver Springs Watershed (Phase 1). Wastewater Miscellaneous extension Service Area Miscellaneous of existng water, sewer, Not Silver Springs Not City of Ocala N/A S115 Expansion, Underway 2020 N/A N/A $500,000 City $500,000 N/A Water and Sewer and reuse facilities to provided Basin provided Reclaimed provide services. Water Sanitary sewer Sanitary Smoke testing and smoke testing, TV Sewer and Silver Springs City of Ocala N/A S116 inspection of existing Underway 2020 N/A N/A N/A $3,000,000 N/A City $3,000,000 N/A inspecting, and WWTF Basin sanitary sewer system lining program Maintenance Project would establish conservation easement on 5,223 ac of privately owned forest land east of CR 315 along Oklawaha River. Tract is part of Heather Island Heather Island Florida Marion County Land Silver Springs Not Not Not provided S117 Conservation Forever project and is Completed 2016 N/A N/A 5,223.0 N/A Not provided Not provided Parks Acquisition Basin provided provided Easement identified as Phase 2 of Silver Springs Watershed Forest Legacy project. Land has been aquired by SJRWMD with plans for surface water improvements underway. Remove existing WWTF from service. Construct Fruitland Park lift station to allow City of Fruitland WWTF Silver Springs Not Not Not provided S118 WWTF transfer of wastewater to Underway 2020 1,506 N/A N/A $1,500,000 Not provided Not provided Park Upgrade Basin provided provided Decommisioning Lady Lake for treatment. Improved treatment at Lady Lake facility. New WWTF constructed WWTF City of Fruitland Construction of Silver Springs N/A S119 with improved treatment Nutrient Canceled N/A N/A N/A N/A N/A N/A N/A N/A N/A Park New WWTF Basin and SCADA system. Reduction

Page 84 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Expected 9 to 10 yrs for project completion. Street Sweeping Sweep streets 4 times/yr City of Fruitland Street Not Silver Springs Not N/A S120 and Storm Drain and clean out 12 storm Completed N/A N/A N/A N/A City Not provided N/A Park Sweeping provided Basin provided Inlet Cleaning drain inlets. Landscaping, irrigation, fertilizer, and pet waste ordinances. City of Fruitland Park uses consultant for education and outreach. Activities include PSAs in Fruitland Park cooperation with City of City of Fruitland NPDES Permit Leesburg and SJRWMD, Education Silver Springs Not Not N/A S121 Completed N/A N/A N/A N/A City Not provided N/A Park Education and distribution of pamphlets, Efforts Basin provided provided Outreach educational website, illicit discharge inspection and education program, utility bill inserts, and informational displays for proper irrigation techniques and landscape management. Provide educational materials including information about importance of protecting Education and Silver Springs and Education Silver Springs Not Not Putnam County N/A S122 Completed N/A N/A N/A N/A County Not provided N/A Outreach implementing small farm Efforts Basin provided provided equine BMPs at Ft. Gates Ferry kiosks and at agricultural center and county fair. Project will retrofit two drainage retention areas in SSS Unit 55 with nitrogen-reducing Bold and Gold™ media. Both DRAs are adjacent to Retention Baseline Golf Course. In Marion County SSS Unit 55 BMP Retrofit County addition to surface runoff Silver Springs Not Office of the N/A S123 Stormwater with Nutrient Underway 2016 106 N/A 30.1 $370,000 Stormwater $370,000 N/A from SSS Unit 55, runoff Basin provided County Engineer Retrofit Reducing Assessment is also discharged into Media DRAs from golf course through pipes and as overland flow. retrofit will prevent 106 lbs of TN from reaching aquifer annually.

Page 85 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Installation of SkimBoss City of Ocala – Filtration Systems using Retrofit Bold and Gold™ media to TMDL/ FY 2016 Installation of treat water leaving ponds Legislative DEP/ City of Drainage Silver Springs Not City of Ocala S124 SkimBoss and flowing into recharge Underway 2019 610 N/A 140.0 $485,650 $15,000 Appropriation/ Not provided Ocala Well Basin provided Filtration System wells at 613 SE 13th City Stormwater with Bold and Ave., NE 10th St @ 1200 Utility Fees Gold™ Block, NE 14th St. and 12th Ct. Fertilizer FDOT O&M fertilizer Fertilizer Silver Springs FDOT District 2 N/A S125 Completed N/A 4,273 N/A N/A N/A N/A N/A N/A N/A Cessation cessation. Cessation Basin Town provides Town of information at city hall Town of McIntosh Education Silver Springs Not Not N/A S126 about FFL, OSTDS Completed N/A N/A N/A N/A Town Not provided N/A McIntosh Education and Efforts Basin provided provided maintenance, and Outreach agricultural BMPs. Sanitary Sewer Economic engine to and Water Main promote residential and Wastewater Special City of Loop along SE Not Not Silver Springs Not N/A S127 commercial growth along Service Area Planned N/A N/A $1,300,000 Legislative Not provided N/A Belleview 132nd from US provided provided Basin provided SE 132nd St. (Belleview Expansion Appropriation Hwy. 441/27 to Beltway). CR 484 Provide Reuse Meets requirement of City of Irrigation Water Springs Protection Act by Reclaimed Not Silver Springs Not N/A S128 Planned N/A N/A N/A $500,000 City $500,000 N/A Belleview to Belleview reducing groundwater Water provided Basin provided Sportplex withdrawals. Multiyear project would serve over 1,200 single- family units currently on septic tanks and individual wells between US Hwy. 441 and - new Providing Water SE 92nd Loop and from and Sewer to SE 105th Pl. south to SE Residents in 135th St. Meets City of Reclaimed Not Silver Springs Not N/A S129 Utility Service requirement of Springs Planned 28,689 N/A N/A $100,000 Not provided Not provided N/A Belleview Water provided Basin provided Area Adjacent to Protection Act by and West of SE reducing and/or 92nd Loop eliminating groundwater withdrawals and septic tank leachates. First year would consist of study to define phases and estimate construction costs of each phase. County Retrofit of drainage Retention Marion County SSS Unit 7 Stormwater retention areas 7244 and BMP Retrofit Silver Springs Not Office of the SJRWMD S130 Stormwater Planned 2017 318 N/A 148.0 $1,400,000 Assessment/ Not provided N/A 7396 with Bold and with Basin provided County Engineer Retrofit – CP #77 SJRWMD Gold™ biosorption Nutrient- Cooperative

Page 86 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number activated media for Reducing Funding/ Florida nitrogen reduction. Media Legislature (Springs Funds) Project is being funded via grant from SJRWMD and DEP to remove existing wastewater package plant in subdivision and replace it with new duplex lift station and 1,830 LF of SJRWMD – Sleepy Hollow new 6-in force main along Package Plant $309,000 Package Plant SE 4th St. to tie into Phase Out, SJRWMD/ Marion County SJRWMD/ Silver Springs Not County Not S131 Abatement existing 16-in force main Wastewater Underway 2016 365 N/A N/A $456,025 County Utilities Utilities DEP Basin provided Utilities provided (lift station and along SE 58th Ave. Service Area Funding Funding – force main) Nutrient reduction Expansion $117,388.58 expected from project is 365 lbs/yr nitrates that are currently being discharged from Sleepy Hollow WWTF annually. This will reduce amount of nutrients reaching Silver Springs. Installation of new 12-in polyvinyl chloride (PVC) force main with valves and appurtenances, using installation methods of open-cut trenching, jack and boring, horizontal directional drilling, to Marion County make connections to WWTF Not Silver Springs Not N/A S132 CR464 FM Completed 2015 N/A N/A $654,416 County Utilities $654,416 N/A Utilities existing force mains and Upgrade provided Basin provided reconnection of services. Upsizing of force main will allow county to handle future flows at SSS WWTP from OSTDS abatement in primary protection zone for Silver Springs. Provide training and exam to private construction and local Erosion Control government employees Lake County Inspection Education Silver Springs Not Not DEP S133 through qualified county Completed N/A N/A N/A N/A County Not provided N/A Public Works Training and Efforts Basin provided provided staffer for free annually. Certification Conduct ongoing site inspections for use of erosion control BMPs at

Page 87 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number all construction sites throughout unincorporated Lake County. Education of contractors and municipal employees on construction erosion control measures Project will address water resources at site and in receiving system with hydrology, attenuation, and sediment transport improvements. Project SJRWMD – DEP/ Marion Silver Springs will provide reduction of Hydrologic Silver Springs $1,895,000 Not SJRWMD S134 Completed 2018 TBD N/A 4,900.0 $2,370,000 N/A SJRWMD/ DEP County Forest turbid water discharges to Restoration Basin DEP – provided Silver River and will $475,000 reduce nutrient loading by up to 13,000 lbs/yr. Evaluation of final project elements is still underway. Creation of wetland park that will primarily use treated wastewater, along with some stormwater. Wetland area will be over 30 ac in size and will receive 3 to 5 mgd of treated wastewater/ stormwater. This water SJWRMD Cost- Wetland Recharge will then recharge Upper Reclaimed Silver Springs Not Share/ DEP Not City of Ocala N/A S135 Underway 2019 29,000 N/A N/A $10,000,000 Not provided Park Floridan aquifer. Plants in Water Basin provided Springs Funding/ provided wetland area will City naturally uptake large portion of excess nutrients. This will potentially reduce nitrogen levels to near zero, along with notable reduction of all TN as well. Project objective is to design and construct Septic Tank Southwood Villas sanitary sewer system that Phase Out, and Silver Springs Not City of Ocala N/A S136 will remove from service Wastewater Planned 2021 TBD N/A N/A $1,500,000 City $1,500,000 N/A Sewer Expansion Basin provided 100 septic tanks from Service Area Project associated single-family Expansion residential lots.

Page 88 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number SJRWMD monitors SAV and algae annually on Silver River between April and June. WMD staff estimate SAV cover SJRWMD SAV Monitoring/ by species and algal cover Silver Springs Not SJRWMD N/A S137 and Algae Data Completed N/A N/A N/A N/A N/A SJRWMD Not provided N/A collectively, using 0.25- Basin provided Monitoring Collection square-meter quadrats and Braun-Blanquet cover scale. Separate worksheet has been added to file for map and more detail. November 2017 Lake County BOCC adopted enhanced fertilizer ordinance. Includes 15- Lake County foot application setback Regulations, Enhanced from waterbodies, 50 % Ordinances, Silver Springs Not Not Lake County N/A S138 Completed N/A N/A N/A N/A County Not provided N/A Fertilizer slow-release content and Basin provided provided Ordinance requirement, and summer Guidelines phosphorus and nitrogen application blackout period from June 1 to Sept. 30. WWTP includes anoxic CSU WWTP – basin for denitrification of Wastewater Villages Center Not Not Silver Springs Not Not CSU S139 Anaerobic NO , which reduces NO Nutrient Completed N/A N/A CSU Not provided N/A CDD 3 3 provided provided Basin provided provided Denitrification discharge in WWTP Reduction effluent Siver Springs Shores Subdivision was platted in early 1970s. Existing Provide Central subdivision has 3,000 Septic Tank Sewer Service to platted lots without access Phase Out, Marion County Not Not Silver Springs Not Not County Utility Not Not provided S140 Old Platted to centralized sewer Wastewater Planned N/A N/A Not provided Utilities provided provided Basin provided provided Funds/ Grants provided Subdivision system. Area was divided Service Area Served by Septic into 6 phases of 500 lots Expansion per phase. It is within Primary Protection Zone (PPZ) for Silver Springs. Retrofit Installation of Retention DEP – SkimBoss SkimBossTM Filtration BMP Retrofit DEP/ FY $328,000 Filtration System System with Bold and with Silver Springs Not Legislative FY Legislative City of Ocala DEP, State S141 Underway 2019 TBD TBD 167.0 $660,000 N/A – Chazal Park Gold™ Media for Lake Nutrient- Basin provided Appropriation/ Appropriation Pond Anderson, Yum Yum Reducing City – $250,000 Pond, and Heritage Pond. Media City – $82,000

Page 89 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Estimate O&M Funding Source Amount Number Construct 5,800 LF of 12- in force main, and 9,200 Provide Central Septic Tank LF of 16-in force main Sewer Service to Phase Out, Marion County along CR 464. Project Not Silver Springs County Utility Not provided S142 Major Wastewater Underway 2019 N/A N/A $6,424,210 $9,724 Not provided N/A Utilities will provide infrastructure provided Basin Funds/ Grants Commercial Service Area and capacity to connect Corridor Expansion future septic to sewer projects to SSS WWTF. For this phase, project consists of constructing force main though commercial corridor in Silver Springs, Silver River, and Upper Silver River Springshed. Proposed sewer force main will be 17,000 LF of 12-in PVC sewer force main connecting Spruce Creek Golf and Country Club (SCGCC) sewer Provide Central Septic Tank system to Stonecrest Sewer Service to Phase Out, Marion County sewer system. This is first Not Silver Springs County Utility Not provided S143 Major Wastewater Underway 2019 N/A N/A $1,791,600 $7,553 Not provided N/A Utilities project being constructed provided Basin Funds/ Grants Commercial Service Area with overall goal of Corridor Expansion making service available and providing opportunity for septic to sewer conversions in this corridor. By making connection to central sewer available in corridor, county can avoid additional septic tank installation in Silver Springs Springshed and possible conversion from septic to sewer in future. Enhance nutrient removal SSS WWTP capabilities to AWT Marion County Nutrient and standards and expand WWTF Silver Springs County Utility N/A S144 Underway 2020 TBD N/A N/A $6,424,210 $362,413 Not provided N/A Utilities Capacity capacity at SSS WWTF Upgrade Basin Funds/ Grants Improvement by 500,000 gallons per day (gpd).

Page 90 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Upper Wakulla River and Wakulla Springs BMAP

Background The BMAP basin encompasses an area of 848,445 acres, or 1,325 square miles (Figure B-5). The Upper Wakulla River and Wakulla Springs are designated as OFWs. The river and springs are a very dynamic groundwater and surface water–fed system. Wakulla Springs, designated as an OFS, is one of the deepest freshwater springs in the world and the primary source of water for the Wakulla River. In the Upper Wakulla River and Wakulla Springs Basin, the Cody Scarp generally separates the semiconfined geologic features to the north (soils characterized with lower potential for groundwater impacts) and areas of unconfined geologic features to the south (highly permeable karst areas with a high potential for groundwater impacts).

DEP determined that the Upper Wakulla River segment is impaired by nitrate; the biological community in the river is affected by excessive algal mats linked to elevated nitrate concentrations from anthropogenic sources. In 2012, DEP adopted the Upper Wakulla River TMDL to reduce nitrate inputs to the river and springs. The TMDL defined the nitrate target as composed of both nitrate and nitrite as nitrogen. The Upper Wakulla River and Wakulla Springs BMAP was adopted in October 2015 to implement the TMDL.

Status of Projects Through December 31, 2017, 116 projects have been completed. An additional 10 projects that are underway or planned have been added to the BMAP. The projects completed to date are estimated to achieve total reductions of 693,574 lbs/yr of TN.

As an OFS BMAP, additional information will be provided when the BMAP reaches its 5-, 10-, and 15-year milestones. If the milestones, or the 20-year target, will not be met, an explanation of possible causes and potential solutions will be provided. These milestones will be specified in a revised BMAP document. The revised Upper Wakulla River and Wakulla Springs BMAP is scheduled to be readopted by July 1, 2018, to meet the statutory requirements added by the 2016 Florida Legislature.

Page 91 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Figure B-5. Upper Wakulla River and Wakulla Springs BMAP area

Page 92 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Table B-5. Upper Wakulla BMAP Projects DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Fertilizer is not applied Fertilizer City of Gretna Not provided CG-001 No Fertilizer Use on any city-owned Completed N/A 0 N/A Outside N/A N/A N/A N/A N/A N/A Cessation property. City of City of Quincy WWTF Nutrient Not provided CQ-001 AWT at WWTF. Completed 2015 0 N/A Outside N/A Not provided Not provided Not provided Not provided N/A Quincy WWTF Reduction Ordinance that requires LDC – Watershed minimum stormwater Regulations, City of Not provided CQ-002 Conservation treatment levels and use Ordinances, and Completed N/A 0 N/A Outside N/A N/A N/A N/A N/A N/A Quincy Measures of BMPs including slow- Guidelines release fertilizers. Sweeping streets in south City of Not provided CQ-003 Street Sweeping side of city one week and Street Sweeping Completed N/A TBD N/A Outside N/A Not provided Not provided Not provided Not provided N/A Quincy north side next week. Upgrade to AWT to reduce nitrogen City of WWTF Upgrade to concentration by 75 % at WWTF Nutrient N/A COT-001 Completed 2012 170,232 N/A PFA1 N/A $227,000,000 $9,400,000 Not provided Not provided N/A Tallahassee AWT spray field near Tram Reduction Rd. and improve quality of reuse. Biosolids City of Eliminated biosolids WWTF N/A COT-002 Application Completed 2006 372,563 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee disposal in springshed. Management Elimination Assessment and Project consists of Sanitary Sewer City of Rehabilitation of assessment and N/A COT-003 and WWTF Completed 2011 N/A N/A PFA1 N/A $10,000,000 Not provided Not provided Not provided N/A Tallahassee Sewer Collection rehabilitation of sewer Maintenance System collection system. Standard fertilizer Fertilizer Use Regulations, City of ordinance credit from N/A COT-004 Ordinance (08- Ordinances, and Completed N/A 108 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee Education Credit 072AA Guidelines Workbook. Credit above and beyond standard credit for ordinances based on Fertilizer Use survey. Households that Regulations, City of N/A COT-004a Ordinance applied fertilizer (2007 Ordinances, and Underway N/A 177 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee (08-072AA vs. 2012) decreased Guidelines 49 %, level of nitrogen applied per household decreased 27 %. Public education using various media resources to promote behavioral Public Education for changes for individuals City of Stormwater, and businesses to Public Education N/A COT-005 Completed N/A 216 N/A PFA1 N/A $1,700,000 N/A N/A N/A N/A Tallahassee Fertilizer, and Pet conserve water and Efforts Waste reduce or eliminate pollution impacts to surface water and groundwater. Spray Field Eliminated fertilizer City of Fertilizer N/A COT-006 Fertilizer application on spray field Completed N/A 48,708 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee Cessation Application (in springshed).

Page 93 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Pet Waste 34 % of dog owners Regulations, City of N/A COT-007 Ordinance (Number began picking up after Ordinances, and Completed N/A 108 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee 10-0-15AA) their pets. Guidelines Stormwater Regional City of Conveyance Not N/A COT-008 Improvement Stormwater Completed 2012 8 N/A PFA1 $990,000 N/A N/A N/A N/A Tallahassee improvements. provided Projects Treatment Primary Springs Identifies PSPZ where Regulations, City of Protection Zone development must meet N/A COT-009 Ordinances, and Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee (PSPZ) Ordinance more stringent Guidelines (08-0-68AA) requirements. Comprehensive Plan Provisions Reduced allowed Regulations, City of N/A COT-010 (Conservation development in urban Ordinances, and Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee Element Policy fringe inside PSPZ. Guidelines 4.2.5) Study and develop preferred options for management alternatives to traditional OSTDS in unincorporated areas of Leon County, including PSPZ; identify preferred options for responsible Alternatives to City of COT- management entities, Leon County Sewer Solutions Study Planned 2019 N/A N/A PFA1 N/A Not provided N/A Not provided Not provided N/A Tallahassee 011/LC-029 including Study recommendations for financing and management structure for identified preferred options; identify other issues related to sewage treatment and disposal system financing. 79 stormwater projects citywide (outside PFA1) completed since 2004, Regional City of Stormwater Not N/A COT-012 examples include Lower Stormwater Completed 2015 Not provided N/A Outside $82,303,740 N/A Not provided Not provided N/A Tallahassee Treatment Projects provided CDD, Frenchtown Pond, Treatment and Emory Court, Weems Pond projects. Citywide street sweeping annually collects 2,000 City of N/A COT-013 Street Sweeping tons of material and Street Sweeping Completed 2015 283 N/A Outside N/A $1,500,000 Not provided Not provided Not provided N/A Tallahassee 2,000 lbs (942 kg) of TN removed. 5-minute video educates homeowners on local groundwater system and Public Education- City Water City of explains need to address Enhanced Public N/A COT-014 Wakulla Springs Completed N/A 0 N/A PFA1 N/A $27,000 N/A Resources Not provided N/A Tallahassee septic systems to restore Education Nitrate Video Engineering Wakulla Springs. Shared via social media and WCOT TV. Facilitating connection of City of NWFWMD/ DEP Septic Connection to Not DEP – NWFWMD- COT-015 130 properties currently OSTDS PhaseOut Underway 2019 1,177 N/A PFA1 $2,587,000 N/A $637,000 Tallahassee (Legislative Existing Sewer in provided Legislative 17-056 on OSTDS to existing

Page 94 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Projects Grant)/ Wakulla BMAP central sewer in Wakulla Projects City of Tallahassee Area BMAP PFA1. Grant/ City 2017–19 City of Tallahassee will produce OSTDS Reduction and distribute Outreach Initiative – educational PSAs, City of DEP FY 2015 319/ Outreach for City of billboards, and other Enhanced Public DEP 2015- COT-016 Underway N/A TBD N/A PFA1 N/A $170,000 N/A $100,000 NF022 Tallahassee City of Tallahassee Tallahassee's media, to encourage city Education 319/ City Connect Septic to residents who are on Sewer Project septic systems in PFA 1, to connect to existing central sewer. Development and implementation of plan DEP FY 2017 2017–20 Develop City of DEP FY 2017–20/ to educate residents Enhanced Public 319/ City COT-017 and Implement Planned N/A TBD N/A PFA1 N/A $50,000 N/A $25,000 Not provided Tallahassee City of Tallahassee about septic sewer and Education Submitted to Educational Plan impact on WS – EPA including PSAs. Interlocal Interlocal agreement for Agreement for Regulations, City of City of Tallahassee/ provision of sewer COT-018 Provision of Sewer Ordinances, and Planned N/A TBD N/A PFA1 N/A N/A N/A N/A N/A N/A Tallahassee Leon County service to Woodside Service to Woodside Guidelines Heights Subdivision. Heights Subdivision Update permits, as TN Requirements Regulations, needed, to incorporate DEP N/A FDEP-001 for WWTFs in Ordinances, and Completed N/A N/A N/A PFA1 N/A N/A N/A N/A N/A N/A new requirements to PFA 1 Guidelines WWTFs in PFA 1. Florida Agricultural Regulations, and N/A FAMU-001 NPDES MS4 Permit NPDES MS4 permit. Ordinances, and Completed N/A N/A N/A Outside N/A N/A N/A N/A N/A N/A Mechanical Guidelines University (FAMU) Eliminated fertilizer use for ongoing turf FDOT Fertilizer PFA1, Florida N/A FDOT-001 Fertilizer Cessation maintenance within Completed 2015 2,756 N/A N/A Not provided Not provided N/A N/A District 3 Cessation PFA2 Legislature entire basin, including areas outside PFAs. Contract for street sweeping of FDOT curb FDOT and gutter roads in Florida N/A FDOT-002 Street Sweeping Street Sweeping Completed 2015 169 N/A PFA1 N/A Not provided Not provided N/A N/A District 3 urbanized areas of Leon Legislature County and City of Tallahassee. Investigating use of Innovative Nitrogen innovative nitrogen FDOT PFA1, Florida N/A FDOT-003 Removal removal technologies as Study Canceled N/A N/A N/A N/A Not provided Not provided N/A N/A District 3 PFA2 Legislature Technologies part of present work program in PFAs. Avoid constructing Regulations, FDOT Avoidance of ponds directly over PFA1, N/A FDOT-004 Ordinances, and Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A District 3 Mapped Karst Caves mapped karst caves by PFA2 Guidelines providing 300-ft buffer. Federal Stormwater system Stormwater Not Correctional N/A FCI-001 NPDES MS4 Permit inspection and System Completed 2015 N/A N/A Outside N/A N/A N/A N/A N/A provided Institute maintenance. Rehabilitation

Page 95 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Federal Fertilizer is not applied Fertilizer Correctional N/A FCI-002 No Fertilizer Use Completed 2015 TBD N/A Outside N/A N/A N/A N/A N/A N/A on facility grounds. Cessation Institute Florida State Fertilizer Rule in Regulations, Fertilizer Rule in University N/A FSU-001 University Master Ordinances, and Completed N/A TBD N/A Outside N/A N/A N/A N/A N/A N/A University Master Plan. (FSU) Plan Guidelines Regulations, FSU N/A FSU-002 NPDES MS4 Permit NPDES MS4 permit. Ordinances, and Completed N/A N/A N/A Outside N/A N/A N/A N/A N/A N/A Guidelines Comprehensive Plan Policy 4.5.1 and Comprehensive Plan Regulations, Gadsden 5.2.11 in Policy 4.5.1 and 5.2.11 in N/A GC-001 Ordinances, and Completed N/A N/A N/A Outside N/A N/A N/A N/A N/A N/A County Infrastructure and Infrastructure and Guidelines Conservation Conservation Element. Element Comprehensive Plan Policy 5.2.4 and Comprehensive Plan Regulations, Gadsden N/A GC-002 5.2.11 in Policy 5.2.4 and 5.2.11in Ordinances, and Completed N/A N/A N/A Outside N/A N/A N/A N/A N/A N/A County Conservation Conservation Element. Guidelines Element Comprehensive Plan Regulations, Gadsden Comprehensive Plan N/A GC-003 Infrastructure Ordinances, and Completed N/A N/A N/A Outside N/A N/A N/A N/A N/A N/A County Infrastructure Element. Element Guidelines Section 3.4 Special Drainage Basins – Section 3.4 Special Water Quality Drainage Basins – Water Regulations, Gadsden (Pollution Quality (Pollution N/A GC-004 Ordinances, and Completed N/A N/A N/A Outside N/A N/A N/A N/A N/A N/A County Abatement) in Abatement) in Guidelines Storwmater Policies Stormwater Policies and and Procedures Procedures Manual. Manual Regulations, Gadsden Adoption of fertilizer N/A GC-005 Fertilizer Ordinance Ordinances, and Completed N/A 14 N/A Outside N/A N/A N/A N/A N/A N/A County ordinance. Guidelines County identified project in adopted sewer master plan and water and sewer interlocal agreement with city as targeted area for sewer. Funds for th NWFWMD/ project are available Leon County LC-001 Sewering in PSPZ OSTDS PhaseOut Planned Not provided TBD N/A PFA1 N/A $24,500,000 N/A Not provided Not provided N/A Blueprint through county's share of Blueprint Water Quality Funding supported by local infrastructure sales tax, subject to annual budget and appropriation. Wastewater system Woodside Heights expansion to provide OSTDS Phase NWFWMD, Leon County NWFWMD LC-001a Septic- to-Sewer service connections, Underway 2019 1,358 N/A PFA1 N/A $4,900,000 Not provided $2,450,000 N/A Out Blueprint Project eliminating over 150 OSTDS. Woodville Septic to Wastewater system NWFWMD/ Leon County NWFWMD LC-001b Sewer Project expansion design to OSTDS PhaseOut Underway 2019 TBD N/A PFA1 N/A $3,000,000 Not provided $1,500,000 N/A Blueprint Design provide service

Page 96 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number connections, eliminating 1,500 OSTDS. GIS inventory of all Septic Tank Leon County N/A LC-002 septic systems in Leon Study Completed 2013 N/A N/A PFA1 N/A $50,000 N/A Not provided Not provided N/A Inventory County. Proposed revision to septic tank ordinance to require repairs to have Regulations, Leon County N/A LC-003 Septic Tank Repairs minimum 24-in Ordinances, and Completed N/A N/A N/A PFA1 N/A N/A N/A N/A N/A N/A separation between Guidelines drainfield and seasonal high-water table. Pending results of FDOH evaluation of passive systems, as referenced in Section 381.0065(4)(x), F.S, county shall (1) review results of Florida study of nitrogen- reducing, performance- based OSTDS, including passive systems. (2) Identify passive systems regulated under Septic Tank Section 381.0065, F.S., Leon County NWFWMD LC-004 Nitrogen Removal that are approved by state Study Underway Not provided N/A N/A PFA1 N/A Not provided N/A Not provided Not provided N/A Requirements for permitting and appropriate for use in Leon County. (3) Evaluate factors such as cost and operational feasibility of such passive systems. (4) Develop proposed amendment to code of laws requiring use of appropriate systems for new construction in PSPZ. Passive Onsite Upgrade 37 OSTDS to NWFWMD/ Sewage Nitrogen AWT systems with OSTDS Leon County LC-004a Underway 2019 335 N/A PFA1 N/A $750,000 N/A NWFWMD $750,000 N/A FDOH/ DEP Reduction Pilot followup monitoring to Enhancement Project determine effectiveness. Add educational kiosks Septic Tank at Woodville Community Public Education Leon County N/A LC-005 Underway N/A N/A N/A PFA1 N/A $2,500 N/A N/A N/A N/A Education Center to explain how Efforts septic systems work. Enacted Requires commercial Regulations, Comprehensive applicators to follow set Leon County N/A LC-006 Ordinances, and Completed N/A 188 N/A PFA1 N/A N/A N/A N/A N/A N/A Fertilizer Ordinance of BMPs for application Guidelines (Number 09-34) of fertilizers. Consider modification to Regulations, Fertilizer Ordinance fertilizer ordinance to Leon County N/A LC-007 Ordinances, and Completed N/A N/A N/A PFA1 N/A N/A N/A N/A N/A N/A Modification reduce nitrogen Guidelines application rates below

Page 97 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Cody Scarp, if allowable by Florida law. Outreach through FYN, Illicit Discharge Education and Program, pamphlets, Public Education Leon County N/A LC-008 Completed N/A 377 N/A PFA1 N/A N/A N/A N/A N/A N/A Outreach presentations, Efforts workshops, and special events. Education program to Enacted Pet Waste promote cleanup of pet Public Education Leon County N/A LC-009 Ordinance (Number Completed N/A 188 N/A PFA1 N/A N/A N/A N/A N/A N/A waste as contributor to Efforts 11-21) surface water pollution. Adopted new minimum countywide Regulations, Land Development environmental Leon County N/A LC-010 Ordinances, and Completed N/A TBD N/A PFA1 N/A N/A N/A N/A N/A N/A Regulations regulations that exceed Guidelines state stormwater standards. Reduced allowable development in urban Comprehensive Plan fringe from up to 1 unit Provisions per ac to 1 unit per 3 ac. Regulations, Leon County N/A LC-011 (Conservation Transfer of density with Ordinances, and Completed N/A 1 N/A PFA1 N/A N/A N/A N/A N/A N/A Element Policy no net increase in Guidelines 4.2.5) dwelling units as allowed on future land use map permitted. Removed 15-ac nutrient sediment dam in 2002, Lake Munson stabilized Munson Hydrologic Leon County N/A LC-012 Erosion and Flood Slough to reduce erosion, Completed 2002 93,299 N/A PFA1 37,267 $7,200,000 N/A Not provided Not provided N/A Restoration Protection Upgrades and repaired dam for stabilization of lake hydroperiod. Develop LID incentives Regulations, to reduce nitrogen Leon County N/A LC-013 LID Ordinances, and Completed N/A N/A N/A PFA1 N/A N/A N/A N/A N/A N/A loading to surface waters Guidelines and groundwater. Contract for 821 mi of Leon County N/A LC-014 Street Sweeping street sweeping annually; Street Sweeping Completed 2015 38 90 PFA1 N/A N/A $75,000 N/A N/A N/A collects 124.75 tons/yr. Participation in FYN Program through Public Education Leon County N/A LC-015 FYN Program Completed N/A 1,131 N/A PFA1 N/A N/A $55,000 N/A N/A N/A Cooperative Extension Efforts Service. Regulations, Leon County N/A LC-016 Irrigation Ordinance Irrigation ordinance. Ordinances, and Completed N/A 188 N/A PFA1 N/A N/A N/A N/A N/A N/A Guidelines Regulations, Landscaping Leon County N/A LC-017 Landscaping ordinance. Ordinances, and Completed N/A 188 N/A PFA1 N/A N/A N/A N/A N/A N/A Ordinance Guidelines Study to determine areas Aquifer with most direct Leon County N/A LC-018 Vulnerability Study Completed 2007 0 N/A PFA1 N/A $73,000 N/A N/A N/A N/A connections to Wakulla Assessment Springs.

Page 98 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number In conjunction with City of Tallahassee and Wakulla County, compiled previous studies identifying nitrogen loading to Wakulla Springs, and City of Tallahassee/ identified treatment and Leon County LC-019 Lombardo Report Study Completed 2013 N/A N/A PFA1 N/A $60,000 N/A N/A N/A N/A Wakulla County management options, where central sewer is not available, for purpose of reducing nitrate loading to Wakulla Springs from septic systems in Leon and Wakulla Counties. Sampled 73 sites in 13 Water Quality Monitoring/Data Leon County N/A LC-020 lakes, 27 streams, and 2 Completed 2015 N/A N/A PFA1 N/A $250,000 N/A N/A N/A N/A Sampling Collection rivers. Preparing and publishing annual water quality Preparation of report to document Leon County N/A LC-021 Annual Water health of natural systems Study Completed 2015 N/A N/A PFA1 N/A N/A $15,000 N/A N/A N/A Quality Report and use for prioritization of water quality project needs. EPA grant to study 60- Woodville Recharge square-mi Woodville Leon County EPA LC-022 Aquifer Protection Recharge Basin for Study Completed 2007 N/A N/A PFA1 N/A $300,000 N/A EPA Not provided N/A Study flooding, water quality, and aquifer protection. Commitment to develop Annual Wakulla annual status report on Leon County N/A LC-023 Springs Status Study Completed 2014 N/A N/A PFA1 N/A N/A N/A N/A N/A N/A Wakulla Springs for Report BOCC. Enacted to establish defined area for Regulations, Established PSPZ Leon County N/A LC-024 enforcement for Ordinances, and Completed N/A N/A N/A PFA1 98,029 N/A N/A N/A N/A N/A (Number 09-12) additional water quality Guidelines protections in this zone. Acquisition of 132 ac immediately upstream of Not Leon County N/A LC-025 Eight Mile Pond Land Acquisition Completed 2010 TBD N/A PFA1 N/A N/A N/A N/A N/A Ames Sink to preserve/ provided protect sink. Aquifer Wellhead Regulations, Protection Includes Aquifer Leon County N/A LC-026 Ordinances, and Completed N/A TBD N/A PFA1 N/A N/A N/A N/A N/A N/A Ordinance (Number Protection Program. Guidelines 07-20) Maintain 2,316 mi of Litter Control Public Education Leon County N/A LC-027 rights-of-way, collecting Completed N/A TBD N/A PFA1 N/A N/A N/A N/A N/A N/A Program Efforts 78.4 tons of waste. Maintain 112 mi of Adopt-A-Road Public Education Leon County N/A LC-028 rights-of-way, collecting Completed N/A TBD N/A PFA1 N/A N/A N/A N/A N/A N/A Program Efforts 2.11 tons of trash.

Page 99 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Study and develop preferred options for management alternatives to traditional OSTDS in unincorporated areas of Leon County, including PSPZ; identify preferred options for responsible LC- Alternatives to management entities, Leon County Blueprint 029/COT- Sewer Solutions Study Underway Not provided N/A N/A PFA1 N/A N/A N/A N/A N/A N/A including 011 Study recommendations for financing and management structure for identified preferred options; identify other issues related to sewage treatment and disposal system financing. Constructed two Wet Detention Harbinwood Estates stormwater retrofit ponds Pond and Leon County NWFWMD/ FEMA LC-029 Completed 2008 30 N/A Outside 269 $2,980,000 N/A N/A N/A N/A Ponds and planted/stabilized Shoreline 1,200 LF of channel. Stabilization Constructed 10-ac Fuller Rd. Regional stormwater retrofit Leon County NWFWMD LC-030 STAs Completed 2010 58 N/A Outside 400 $800,000 N/A N/A N/A N/A Facility facility at I-10 and US Hwy. 27. Acquisition of 166 ac, Fred George Basin including Fred George Leon County N/A LC-031 Land Acquisition Completed 2012 TBD N/A Outside N/A $2,600,000 N/A N/A N/A N/A Acquisition Sink for preservation/ protection of sink. Wetland rehydration through grade restoration and construction of trash Fred George Basin racks at inflow points are Wetland Leon County N/A LC-032 Wetland Underway 2019 N/A N/A Outside 2,668 $1,000,000 N/A N/A N/A N/A planned to improve water Restoration Rehydration quality prior to runoff entering Fred George Sink. Tallahassee Fertilizer Community N/A TCC-001 Fertilizer Cessation Fertilizer cessation Completed 2012 1 N/A Outside N/A N/A N/A N/A N/A N/A Cessation College Talquin Oyster Bay WWTP Oyster Bay WWTP N/A TEC-001 WWTF Upgrade Completed 2016 610 N/A Outside 3 $750,000 N/A N/A N/A N/A Electric Abandonment abandonment Gadsden East WWTP – Construct treatment wetland by retrofitting 3 Talquin Gadsden East WWTF Disposal N/A TEC-002 existing rapid infiltration Completed 2016 1,882 N/A Outside 8 $200,000 N/A N/A N/A N/A Electric WWTP Site basins (RIBs) and building additional treatment cells. Sanitary Sewer Talquin N/A TEC-003 Hwy. 267 Sewer Hwy. 267 sewer. and WWTF Completed 2008 2 N/A Outside 3 $400,000 N/A N/A N/A N/A Electric Maintenance Sanitary Sewer Talquin Beech Ridge Trail N/A TEC-004 Beech Ridge Trail sewer and WWTF Completed 2004 2 N/A Outside 13 $40,000 N/A N/A N/A N/A Electric Sewer Maintenance

Page 100 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number Town of N/A TH-001 Street Sweeping Street sweeping Street Sweeping Completed 2015 0 N/A Outside N/A N/A Not provided N/A N/A N/A Havana Requires AWT for any Comprehensive Plan WWTF or spray field Regulations, Wakulla PFA1, N/A WC-001 Infrastructure Policy located in Wakulla Ordinances, and Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A County PFA2 1.3.6 Springs Special Planning Guidelines Area. Proposed upgrades and USDA Rural Otter Creek WWTP expansion to include Wakulla WWTF Nutrient Not Development N/A WC-002 Upgrade and contributing systems in Underway 5/12/2018 TBD N/A PFA2 $7,644,346 N/A N/A N/A County Reduction provided (RD) Capacity Expansion PFA2 to WWTF for Loan/Grant improved treatment. Provide citizens and officials with best available information for decision making Wakulla Public Education on Public Education PFA1, N/A WC-003 regarding use of OSTDS Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A County OSTDS Efforts PFA2 and decentralized wastewater systems to reduce nutrients in groundwater to springs. Requires nitrogen- reducing septic systems on parcels smaller than 5 ac in Wakulla Springs Special Planning Area; Comprehensive Plan Regulations, Wakulla within 150 ft of surface PFA1, N/A WC-004 Infrastructure Policy Ordinances, and Completed N/A TBD N/A N/A N/A N/A N/A N/A N/A County water, swallet, or other PFA2 1.3.7 Guidelines karst feature, or within 300 ft of first or second magnitude spring; and on all parcels less than 0.229 ac in size. Installation of central Legislative Wakulla Magnolia Gardens sewer and proper Not Springs NWFWMD WC-005 OSTDS PhaseOut Underway 2018 1,599 N/A PFA2 $2,300,000 N/A $2,300,000 Not provided County Sewer – Phase I abandonment of 159 provided Protection septic systems. Funds Installation of central Legislative Wakulla Wakulla Gardens sewer and proper OSTDS Phase Not Springs NWFWMD WC-006 Underway 2018 513 N/A PFA2 $2,300,000 N/A $2,300,000 Not provided County Sewer – Phase I abandonment of 51 Out provided Protection septic systems. Funds Greiner's Addition Planned central sewer Wakulla OSTDS Phase Not N/A WC-007 Central Sewer installation for Greiner's Planned TBD TBD N/A PFA2 N/A N/A N/A N/A N/A County Out provided Installation Addition neighborhood. Wakulla County will assume ownership and management of River Wakulla County Plantation Estates Wakulla Not N/A WC-008 WWTF – Plantation WWTP sewer system WWTF Upgrade Completed 2015 0 N/A PFA2 $4,900,000 N/A N/A N/A N/A County provided River Estates and WWTF. Project includes removal and replacement of existing facility. Wakulla Wakulla Springs Inspection and repair of OSTDS PFA1, Not N/A WC-009 Planned TBD TBD N/A $1,380,300 N/A N/A N/A N/A County Watershed old, damaged, and failing Enhancement PFA2 provided

Page 101 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number systems in Wakulla Springs Watershed. TIF District for Crawfordville area to Wakulla Crawfordville TIF Not N/A WC-010 fund improvements, OSTDS PhaseOut Completed 2015 0 N/A PFA2 N/A N/A N/A N/A N/A County District provided including basic infrastructure. Adopts model ordinance Regulations, Wakulla Fertilizer Use PFA1, N/A WC-011 on FFL fertilizer use on Ordinances, and Completed N/A 71 N/A N/A N/A N/A N/A N/A N/A County Ordinance 2010-1 PFA2 urban landscapes. Guidelines Fertilizer Education and outreach Regulations, Wakulla PFA1, N/A WC-012 Management to public about fertilizer Ordinances, and Completed N/A 143 N/A N/A N/A N/A N/A N/A N/A County PFA2 Education management. Guidelines Establishes special area plans for Bloxham Special Area Plan, Special Area Plan #2, and Spring Creek Hwy. Comprehensive Plan Special Area Plan in Future Land Use Regulations, Wakulla Wakulla Springs Basin. PFA1, N/A WC-013 Policies 1.2.10, Ordinances, and Completed N/A 13 N/A N/A N/A N/A N/A N/A N/A County Requires nitrate loading PFA2 1.2.10.3, Special Guidelines analyses for develop- Area Plans ment. Establish standards for stormwater, karst feature protections, landscaping, and open space. Wakulla County Modeling effort to Wakulla Aquifer PFA1, N/A WC-014 identify most vulnerable Study Completed 2009 Part of WC-10 N/A N/A N/A N/A N/A N/A N/A County Vulnerability PFA2 areas in county. Assessment Establishes standards for 606 ac in Wakulla Springs Basin. Requires no net increase in Comprehensive Plan nutrients or phosphorus Future Land Use loading to groundwater. Regulations, Wakulla Polity 1.2.9.1 – Sustainable community PFA1, N/A WC-015 Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County Northeast Wakulla standards established for PFA2 Guidelines Sustainable stormwater, Community groundwater, open space, and BMPs. Requires AWT standards for sanitary sewer service to site. Add karst buffers; require nitrate loading Ordinance 2006-58 study for proposed (Multiple Objectives development greater than and Policies in 1 ac; incorporate FYN Regulations, Wakulla PFA1, N/A WC-016 Comprehensive Plan practices and landscaping Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County PFA2 Conservation and standards that promote Guidelines Future Land Use native vegetation for new Elements) subdivisions; reduce nitrates from public facilities; and address

Page 102 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number stormwater, water conservation, wastewater facilities, treated wastewater reuse, and natural water flows. Develop solutions to restore health of Wakulla Springs by reducing Comprehensive Plan Regulations, Wakulla pollutants in groundwater PFA1, N/A WC-017 Conservation Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County and implementing PFA2 Objective 12.0 Guidelines policies for Wakulla Springs Special Planning Area. Establishes transfer of development rights policy to encourage development in Crawfordville with connection to sewer Comprehensive Plan Regulations, Wakulla service, "no net increase N/A WC-018 Conservation Ordinances, and Completed N/A 0 N/A PFA2 N/A N/A N/A N/A N/A N/A County in dwelling units above 2 Objective 12.1 Guidelines units per acre" allowed by future land use map in Wakulla Springs Special Planning Area, fertilizer restrictions based on FYN Program. County shall consider Comprehensive Plan expanding Wakulla Regulations, Wakulla PFA1, N/A WC-019 Conservation Springs Special Planning Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County PFA2 Objective 12.2 Area based on geologic Guidelines vulnerability. To protect functions of Comprehensive Plan Regulations, Wakulla groundwater recharge PFA1, N/A WC-020 Infrastructure Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County areas, springs, and PFA2 Objective 2.5 Guidelines springsheds. Requests NWFWMD establish minimum flows and levels for Wakulla Springs and requests Groundwater Regulations, Wakulla NWFWMD deny permits PFA1, N/A WC-021 Extraction Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County to transport water from PFA2 Ordinance Guidelines Wakulla Springs springshed and Ochlocknee and St. Marks Rivers. Prohibits litter and Litter Regulations. Regulations, Wakulla dumping along roadways PFA1, N/A WC-022 Code of Ordinances Ordinances, and Completed N/A 0 N/A N/A N/A N/A N/A N/A N/A County and waterways, and PFA2 Section 27.049 Guidelines establishes penalties. Installation of central Legislative Wakulla Wakulla Gardens sewer and proper Not Springs NWFWMD WC-023 OSTDS PhaseOut Underway 2018 1,820 N/A PFA2 $4,240,000 N/A $4,240,000 Not provided County Sewer – Phase II abandonment of 181 provided Protection septic systems. Funds Wakulla Magnolia Gardens Installation of central OSTDS Phase Not Legislative NWFWMD WC-024 Underway 2018 985 N/A PFA2 $1,560,000 N/A $1,560,000 Not provided County Sewer – Phase II sewer and proper Out provided Springs

Page 103 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Contract Project Project Completion Reduction Reduction Acres Cost Annual Funding Funding Agreement Lead Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Amount Number abandonment of 98 Protection septic systems. Funds Legislative Wakulla Wakulla Gardens Upgrades and rerouting OSTDS Phase Not Springs NWFWMD WC-025 Underway 2018 TBD N/A PFA2 $1,066,280 N/A $1,066,280 Not provided County Sewer – Phase III of 319 lift station. Out provided Protection Funds Nitrogen reduction – Wakulla WINCO WWTP Wastewater Not N/A WC-026 Northeast Wakulla Planned TBD TBD N/A TBD Not provided N/A TBD N/A N/A County Purchase Management provided County. Wakulla Learning in Florida's Annual environmental Public Education Springs State N/A WP-001 Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A Environment education program. Efforts Park Wakulla Project Learning Annual environmental Public Education Springs State N/A WP-002 Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A Tree education program. Efforts Park Wakulla Annual environmental Public Education Springs State N/A WP-003 Green Guide Class Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A education program. Efforts Park Wakulla Wakulla Wildlife Annual environmental Public Education Springs State N/A WP-004 Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A Festival education program. Efforts Park Wakulla Park Ranger Annual environmental Public Education Springs State N/A WP-005 Completed N/A 0 N/A PFA1 N/A N/A N/A N/A N/A N/A Programs education program. Efforts Park Agricultural Farm Enrollment and Agricultural FDACS N/A FDACS-01 Fertilizer BMP verification of BMPs by Underway 2023 25,158 N/A Inside TBD TBD TBD TBD TBD N/A BMPs Implementation agricultural producers. Agricultural Enrollment and Livestock Waste Agricultural FDACS N/A FDACS-02 verification of BMPs by Underway 2023 2,384 N/A Inside TBD TBD TBD TBD TBD N/A BMP BMPs agricultural producers. Implementation 10 % BMP credit on golf course load to Golf Course groundwater, assuming Golf Course Golf Courses TBD GC-01 Planned Not provided 4,013 N/A Inside TBD TBD TBD TBD TBD N/A Reduction Credits 100 % BMP BMPs implementation by golf course owners. 6 % BMP credit on sports field load to Sports Field groundwater, assuming Sports Fields TBD SF- 01 Sport Field BMPs Planned Not provided 136 N/A Inside TBD TBD TBD TBD TBD N/A Reduction Credits 100 % BMP implementation by sports field owners. Achieved by WWTF Wastewater WWTF Policy policy if implemented Wastewater TBD WU-01 Planned Not provided 2,097 N/A Inside TBD TBD TBD TBD TBD N/A Utilities Reductions BMAP-wide, achieving 3 Management or 6 mg/L.

Page 104 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Wekiva River, Rock Springs Run, and Little Wekiva Canal BMAP

Background The Wekiva River system (including the main stem of the Wekiva River and Rock Springs Run) is designated by the state as an OFW, the Wekiva River and portions of its tributaries are designated as a state Aquatic Preserve worthy of special protection because of their natural attributes, and the river is also designated by the federal government as a Wild and Scenic River. The BMAP area includes the Wekiva River surface water basin, a large portion of the springshed for the group of springs that contributes flow (and nutrients) to the system, the Little Wekiva Canal Basin, and the surface water basin of the and Blackwater Creek. The BMAP area is 513 square miles (Figure B-6).

DEP determined that the Wekiva River and Rock Springs Run is impaired by elevated TP and nitrate-nitrogen, based on evidence of an imbalance in aquatic flora. The Little Wekiva Canal was verified as impaired for DO and nutrients based on elevated levels of chlorophyll-a and was subsequently verified as impaired for DO attributable to elevated TN and BOD. In 2008, DEP adopted the nutrient TMDLs for the Wekiva River, Wekiwa Springs, and Rock Springs Run (nitrate and TP), as well as the nutrient and DO TMDLs for the Little Wekiva Canal. The Wekiva River, Rock Springs Run, and Little Wekiva Canal BMAP was adopted in October 2015 to implement nitrate, TN, TP, and BOD reductions to achieve the TMDLs.

Status of Projects Through December 31, 2017, 264 projects have been completed. An additional 53 projects that are underway or planned have been added to the BMAP. The projects completed to date are estimated to achieve total reductions of 138,874 lbs/yr of TN.

Additional information will be provided when the OFS BMAP reaches its 5-, 10-, and 15-year milestones. If the milestones, or the 20-year target, will not be met, an explanation of possible causes and potential solutions will be provided. These milestones will be specified in a revised BMAP document. The revised Wekiva River, Wekiwa Springs, and Rock Springs Run BMAP is scheduled to be readopted by July 1, 2018, to meet the statutory requirements added by the 2016 Florida Legislature.

Page 105 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Figure B-6. Wekiva River, Rock Springs Run, and Little Wekiva Canal BMAP area

Page 106 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

Table B-6. Wekiva BMAP projects DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number City paved and City of Lester Rd. Stormwater System Not Not Inside Not Not Not provided A-01 improved stormwater Completed 2014 $30,288,140 Not provided Not provided Not provided Apopka Improvement Rehabilitation provided provided Springshed provided provided collection system. Improve existing drainage system and dry retention pond to Shopke-Lester Rd. increase inflow mass City of Online Retention Not Inside Not Not Not provided A-02 Pond Expansion and and reduce outflow Completed 2010 1 Not provided Not provided Not provided Not provided Apopka BMP provided Springshed provided provided Improvement mass; pollutant removal efficiency increased from 75 % to 93 %. City Streets Dept. City of swept total of 1,700 mi Inside Not Stormwater Not provided A-03 Street Sweeping Street Sweeping Completed N/A 72 305 ~1,200 Not provided Not provided N/A Apopka in 2017 with total of Springshed provided Service Fees 844,540 lbs collected. City worked in cooperation with Orange County Environmental Protection Dept. City of Chalet North Mobile Inside Not Not provided A-04 (OCEPD) and park to WWTF Upgrade Completed 1992 22,224 9,644 N/A Not provided Not provided Not provided Not provided Apopka Home Park Springshed provided decommission package WWTF and effluent percolation pond and connect to city collection system. Dr. Philip Trinh Dental Office (place existing septic on city wastewater collection system); Honey Transport Inc. (abandon existing septic and place business on city collection system); City of Individual Septic-to- Inside Not Not provided A-05 United Pentecostal Septic Phase Out Completed 2015 735 557 N/A Not provided Not provided Not provided Not provided Apopka Sewer Projects Springshed provided Church (work with church to abandon existing septic system during its expansion and connect to city collection system); Robinsons Restaurant (work with restaurant to transfer wastewater effluent treatment from

Page 107 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number septic system to city collection system). Expand Rock Springs Rd. and Kelly Park Rd. collection system, Kelly Park Rd. at allowing city to City of Rock Springs Inside Not Not provided A-06 connect Orange Septic Phase Out Completed 2010 282 213 N/A Not provided Not provided Not provided Not provided Apopka (Orange County Springshed provided County's Kelly Park Park) recreation area to city collection system and abandon septic Install 1,250 ft of 8-in force main along east end of Kelly Park Rd.; allows Orange County's Kelly Park to City of Kelly Park Rd. connect to city Not Not Inside Not Not provided A-07 Septic Phase Out Completed 2009 N/A Not provided Not provided Not provided Not provided Apopka 8-in Force Main collection system and provided provided Springshed provided abandon septic; also allows for future septic connections near Wekiwa and Rock Springs area. Extend city wastewater collection system by installing 12,236 ft of 12-in force main to Jones Ave., making City of US Hwy. 441 Force Wastewater Service Not Not Inside Not Not provided A-08 connections to Zellwin Completed 2007 N/A Not provided Not provided Not provided Not provided Apopka Main Extension Area Expansion provided provided Springshed provided Farms and Zellwood Elementary School), and providing availability for future connections in area. City installed 5,375 ft of 10-in force main and lift station that allowed Zellwood City of Yothers Rd. and Mobile Home Park to Decommissioned Inside Not Not provided A-09 Completed 2006 13,424 5,825 N/A Not provided Not provided Not provided Not provided Apopka Zellwood Station decommission its WWTF Springshed provided package WWTF and effluent percolation pond, reducing effluent load to basin. City is in design stage of receiving Sanlando City of Sanlando Utilities Utilities Corp. Inside Not Not provided A-10 Reclaimed Water Completed 2013 1,732 4,566 N/A $3,800,000 Not provided Not provided Not provided Apopka Corp. Reuse to City reclaimed water that is Springshed provided currently being discharged into Little

Page 108 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Wekiva, starting at 1 mgd; this will also reduce groundwater withdrawal from city. Constructed 120- million-gallon (mg) lined reclaimed storage pond; pond also collects stormwater Northwest from 300-ac northwest City of Reclaimed/ Not Not Inside Not Not provided A-11 recreation facility that Reclaimed Water Completed 2007 N/A $750,000 Not provided Not provided Not provided Apopka Stormwater Storage provided provided Springshed provided is filtered and Pond distributed for irrigation; this will also reduce groundwater withdrawal. Construction of 21-mg lined reclaimed storage pond; pond also collects stormwater Northwest from 300-ac northwest City of Reclaimed/ recreation facility that Not Not Inside Not Not provided A-12 Reclaimed Water Completed 2016 N/A $1,587,000 Not provided Not provided Not provided Apopka Stormwater Storage is filtered and provided provided Springshed provided Pond B distributed for irrigation; this will also reduce groundwater withdrawal. Construction of 68-mg lined reclaimed storage pond; pond also collects stormwater Northwest from 300-ac northwest City of Reclaimed/ recreation facility that Not Not Inside Not Not provided A-13 Reclaimed Water Underway 2005 N/A $1,380,000 Not provided Not provided Not provided Apopka Stormwater Storage is filtered and provided provided Springshed provided Pond C distributed for irrigation; this will also reduce groundwater withdrawal. Altamonte is in construction stage of sending 3.5 mgd of City of Altamonte Springs to Not Not Inside Not Not provided A-14 reuse water to Apopka Reclaimed Water Completed 2016 N/A Not provided Not provided Not provided Not provided Apopka Apopka provided provided Springshed provided with potential to discharge to Little Wekiva River.

Page 109 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number City is in design stage for receiving 3 mgd of reclaimed water that is City of Orange County currently going to Inside Not Not provided A-15 Reclaimed Water Completed 2013 2,308 6,088 N/A $490,000 Not provided Not provided Not provided Apopka Reuse to City Orange County RIBs; Springshed provided will also reduce groundwater withdrawal from city. Rehabilitate lift station Sanitary Sewer wet well because Collection System City of Lift Station 9 and Not Not Inside Not Not provided A-16 hydrogen sulfide is Rehabilitation, Completed 2008 N/A $41,945 Not provided Not provided Not provided Apopka 10 Wet Wells provided provided Springshed provided dissolving concrete Maintenance, or walls. Replacement Manholes (Alabama Sanitary Sewer Reline manholes with and 8th St.; Little St. Collection System City of supercoat spray to Not Not Inside Not Not provided A-17 and 9th St.; Park Rehabilitation, Completed 2011 N/A $28,420 Not provided Not provided Not provided Apopka prevent leaking provided provided Springshed provided Ave; Charleston Park Maintenance, or between bricks. Subdivision) Replacement Sanitary Sewer Victoria Plaza, Collection System City of Reline to correct Prior to Not Not Inside Not Not provided A-18 Forest Ave., 3rd St., Rehabilitation, Completed N/A $200,591 Not provided Not provided Not provided Apopka leaking joints. 2015 provided provided Springshed provided Park Ave. Maintenance, or Replacement City is in design stage WWTP Expansion of upgrading existing City of WWTF Nutrient Not Inside Not Not provided A-19 and Nutrient treatment plant and Underway 2019 TBD N/A $63,000,000 Not provided Not provided Not provided Apopka Reduction provided Springshed provided Removal expanding capacity to 8 mgd. Drainage easement located off Harry St. in Apopka has become dumping ground. City is removing all City of Not Not Inside Not Stormwater Not provided A-20 Harry St. Project garbage, debris, and BMP Clean Out Underway 2018 ~0.5 $26,000 $26,000 N/A Apopka provided provided Springshed provided Service Fees litter; installing new fence to protect retention area; and sodding hill slope to prevent erosion. Six lakes connected to major outfalls are being sampled monthly. This monthly sampling will set City of Monitoring/ Not Not Inside Not Not Stormwater Not provided A-21 MS4 Lake Sampling baseline of yearly Underway 2018 $6,000 $6,000 N/A Apopka Data Collection provided provided Springshed provided provided Service Fees fluctuations in nutrients and parameters. Marshall Lake, monitored under TMDL Program, is

Page 110 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number sampled quarterly to monitor nutrient loading and parameters. City has adopted Orange Fertilizer Ordinance. Grounds Dept. only fertilizes Regulations, City of twice annually instead Not Inside Not provided A-22 Fertilizer Reduction Ordinances, and Completed N/A 278 ~8 N/A N/A N/A N/A N/A Apopka of quarterly on all city- provided Springshed Guidelines owned and maintained (not recreational nor sports areana) landscapes. City / City of SJRWMD/ Little Wekiva River Install structural Shoreline Inside Altamonte Seminole AS-01 Erosion Management controls to provide Completed 2000 25 17 N/A $350,000 $1,000 Not provided 350,000 N/A Stabilization Springshed Springs County/ Projects (1, 2, and 3) riverbank stabilization. Orange County City / Riverbend City of SJRWMD/ Install structural Apartments Shoreline Inside Altamonte Seminole AS-02 controls to provide Completed 2004 11 8 N/A $250,000 $500 Not provided 250,000 N/A Shoreline Stabilization Springshed Springs County/ riverbank stabilization. Stabilization Orange County City of Stimmell Tract Land Conservation project – Inside Altamonte N/A AS-03 Preservation purchase 268 ac of Land Preservation Completed 2004 N/A N/A 268 $398,444 N/A N/A $398,444 N/A Springshed Springs (Audubon Society) land for preservation. Construct 20,602- square-ft retail/restaurant building with attendant Altamonte Springs parking and site City of Private Shopping Center utilities, plus Inside Altamonte N/A AS-04 Stormwater BMP Completed 2010 0 0 2 N/A N/A Development N/A N/A (Crossroads) stormwater facilities, Springshed Springs – unknown Development on 2.06-ac site, providing higher level of stormwater treatment as result of city ordinance. Phase 3 of Lake Lotus City of Private Brantley Terrace Club, multifamily Not Inside Altamonte N/A AS-05 Stormwater BMP Completed 2002 1 15 N/A N/A Development N/A N/A Condo condominium provided Springshed Springs – unknown development. Stormwater management system City of Gateway Clinic and Private with online dry Inside Altamonte N/A AS-09 Gateway Crossing Stormwater BMPs Completed 2006 6 11 34 N/A N/A Development N/A N/A retention/detention Springshed Springs Development – unknown area, providing higher level of stormwater

Page 111 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number treatment as result of city ordinance.

Spring Oaks, San City of Sebastian, and River Install 39 inlet Inside Stormwater Altamonte N/A AS-13 Catch Basin Inserts Completed 2006 1 1 91 $23,890 $1,000 23,890 N/A Run Inlet Skimmer skimmer baskets. Springshed Utility Fund Springs Baskets Identified area does not contribute to Wekiva River; West Altamonte City of however, closed basin Public Works Operations and Inside Altamonte N/A AS-14 was not removed from Closed Basin Completed 2008 26 24 29 $8,000,000 $500 Capital Project 8,000,000 N/A Administration Springshed Springs consideration in Fund Center TMDL because of potential influence on springshed. Street sweeping occurs City of daily; total swept = Inside $480,000 Stormwater $480,000 Altamonte N/A AS-15 Street Sweeping 5,000 mi/yr – Split Street Sweeping Completed N/A 518 N/A 245 $100,000 N/A Springshed ($240,000/sweeper) Utility Fund ($240,000/sweeper) Springs between springshed and surface. Citywide Pollutant City is contracting City of Loading Model/ with consultants to Inside Stormwater Altamonte N/A AS-16 Hydrologic and complete citywide Study Planned TBD N/A N/A N/A $200,000 N/A TBD N/A Springshed Utility Fund Springs Hydraulic (H&H) pollutant model and Study H&H study. City contracted with consultants to determine phosphorus Lake Orienta, and nitrogen loadings City of Adelaide, and to Lakes Orienta, Inside Stormwater Altamonte N/A AS-17 Florida Hydrologic/ Study Completed 2009 N/A N/A N/A $105,000 N/A TBD N/A Florida, and Adelaide; Springshed Utility Fund Springs Nutrient Budgets and best pollutant load Management Plans reduction options recommended based on study results. Collection, treatment, and reuse of Altamonte Springs- stormwater from FDOT Integrated Cranes Roost Basin DEP/ $1,500,000 City of City/ FDOT/ Reuse and (including I-4 Inside FDOT/ $4,500,000 Altamonte SJRWMD/ AS-23 Stormwater Reuse Completed 2016 TBD TBD 1,931 $12,500,000 TBD S0651 Stormwater widening) and Springshed SFRWMD/ $3,500,000 Springs DEP/ Apopka Treatment elimination of 2 direct City $3,000,000 (A-FIRST) wastewater discharge points to Little Wekiva River.

Page 112 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Contract with consultant to evaluate City of Citywide Inflow & Public Works city's sewer system to Inside Altamonte N/A AS-25 Infiltration (I&I) Study Underway TBD N/A N/A N/A $80,000 N/A Capital Project 80,000 N/A identify areas prone to Springshed Springs Study Fund I&I and develop schedule for repair. City of Regulations, Fertilizer ordinance Inside Altamonte N/A AS-26 Fertilizer Ordinance Ordinances, and Completed N/A 33 N/A 6187 N/A N/A N/A N/A N/A adopted citywide. Springshed Springs Guidelines Enrollment and Agricultural Farm Agricultural Farm FDACS- verification of BMPs Inside FDACS N/A Fertilizer BMP Fertilizer BMP Underway 2023 16,513 N/A TBD TBD TBD TBD TBD N/A 01 by agricultural Springshed Implementation Implementation producers. Agricultural Enrollment and Agricultural FDACS- Livestock Waste verification of BMPs Livestock Waste Inside FDACS N/A Underway 2023 832 N/A TBD TBD TBD TBD TBD N/A 02 BMP by agricultural BMP Springshed Implementation producers. Implementation Agricultural Enrollment and Agricultural FDACS- Nurseries Fertilizer verification of BMPs Nurseries Fertilizer Inside FDACS N/A Underway 2023 5,364 N/A TBD TBD TBD TBD TBD N/A 03 BMP by agricultural BMP Springshed Implementation producers. Implementation SR 438: Treatment Basin 2 (Ponds 2A, 2B, and 2C) and Wet FM: 239289 FDOT FDOT- Detention Pond 4 Wet Detention Inside Not Not Florida N/A (2 Treatment Completed 2004 13 9 Not provided Not provided N/A District 5 02 providing treatment for Pond Springshed provided provided Legislature Projects) runoff generated from existing and proposed pavement. FM: 239289 FDOT FDOT- SR 438: Treatment Wet Detention Inside Not Not Florida N/A (2 Treatment Completed 2004 N/A N/A Not provided Not provided N/A District 5 02b basin – Pond 2B. Pond Springshed provided provided Legislature Projects) FM: 239289 FDOT FDOT- SR 438: Treatment Inside Not Not Florida N/A (2 Treatment Dry Retention Pond Completed 2004 N/A N/A Not provided Not provided N/A District 5 02c basin – Pond 2C. Springshed provided provided Legislature Projects) FM: 239289 FDOT FDOT- SR 438: Wet detention Wet Detention Inside Not Not Florida N/A (2 Treatment Completed 2004 N/A N/A Not provided Not provided N/A District 5 02d – Pond 4. Pond Springshed provided provided Legislature Projects) SR 50: from Avalon Rd. to SR 429/ Western Beltway; Wet FDOT FDOT- Detention Pond L-4, Stormwater BMP Inside Not Florida N/A FM: 410983-1 Completed 2014 59 42 6.6 Not provided Not provided N/A District 5 07 L-7, M-10/11, and N- Retrofit/Expansion Springshed provided Legislature 2/2A providing treatment for existing and new pavement. SR 50: from Avalon FDOT FDOT- Stormwater BMP Inside Not Florida N/A FM: 410983-1 Rd. to SR Wet Completed 2014 N/A N/A 6.6 Not provided Not provided N/A District 5 07b Retrofit/Expansion Springshed provided Legislature Detention Pond L-4,

Page 113 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number L-7, M-10/11, and N- 2/2A providing treatment for existing and new pavement. SR 50: from Avalon Rd. to SR 429/Western Beltway; Wet FDOT FDOT- Detention Pond L-4, Stormwater BMP Inside Not Florida N/A FM: 410983-1 Completed 2014 N/A N/A 6.6 Not provided Not provided N/A District 5 07c L-7, M-10/11, and N- Retrofit/Expansion Springshed provided Legislature 2/2A providing treatment for existing and new pavement. SR 50: from Avalon Rd. to SR 429/Western Beltway; Wet FDOT FDOT- Detention Pond L-4, Stormwater BMP Inside Not Florida N/A FM: 410983-1 Completed 2014 N/A N/A 6.6 Not provided Not provided N/A District 5 07d L-7, M-10/11, and N- Retrofit/Expansion Springshed provided Legislature 2/2A providing treatment for existing and new pavement. SR 50: from Avalon Rd. to SR 429/ Western Beltway; Wet FDOT FDOT- Detention Pond L-4, Stormwater BMP Inside Not Florida N/A FM: 410983-1 Completed 2014 N/A N/A 6.6 Not provided Not provided N/A District 5 07e L-7, M-10/11, and Retrofit/Expansion Springshed provided Legislature N-2/2A providing treatment for existing and new pavement. 10 % BMP credit on golf course load to Golf Golf Course groundwater, assuming Golf Course Inside TBD GC-01 Planned TBD 7,408 N/A 2,412 TBD TBD TBD TBD N/A Courses Reduction Credits 100 % BMP Reduction Credits Springshed implementation by golf course owners. Enhanced fertilizer Regulations, Lake ordinance above model Inside Not N/A LC-13 Fertilizer Ordinance Ordinances, and Completed N/A 8 N/A N/A Not provided Lake County Not provided Not provided County ordinance Springshed provided Guidelines requirements. 2.96-ac project; proposed surface water management system City of ABC Fine Wine and Inside Not N/A O-01 will retain and recover Stormwater BMPs Completed 2008 0 1 2.96 Not provided Not provided Not provided N/A Ocoee Spirits Store # 52 Springshed provided 3 in of runoff from increase in impervious area; sewered area.

Page 114 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number 98.52-ac project; construct 157 single- family residential subdivision with 4 dry retention ponds; City of surface water Online Retention Inside Not N/A O-02 Arden Park South Completed 2013 0 1 98.52 Not provided Not provided Not provided N/A Ocoee management system to BMP Springshed provided store and recover pre- vs. post-development runoff volume from 25-yr, 96-hr event; sewered area. Cambridge Village is 8.97-ac single-family residential subdivision located southeast of intersection of White City of Cambridge Village Online Retention Inside Not N/A O-03 Rd. and Clarke Rd. in Completed 2002 0 0 8.97 Not provided Not provided Not provided N/A Ocoee Subdivision BMP Springshed provided Ocoee; surface water management system includes 30 lots, associated road, and 1 dry retention system. 3 dry retention ponds City of Forest Trails to serve 51.8-ac single- Online Retention Inside Not N/A O-04 Completed 2004 0 0 51.80 Not provided Not provided Not provided N/A Ocoee Subdivision family residential BMP Springshed provided development. 4.26-ac project served City of by stormwater Online Retention Inside Not N/A O-05 Hackney Prairie Park Completed 2015 0 0 4.26 Not provided Not provided Not provided N/A Ocoee treatment retention BMP Springshed provided system; sewered area. 11.47-ac residential site, single lots, with stormwater system; 2 City of Ingram Estates Online Retention Inside Not N/A O-06 dry retention systems; Completed 2007 0 1 11.47 Not provided Not provided Not provided N/A Ocoee Subdivision BMP Springshed provided recharge volume to be recovered within 72 hrs; sewered area. Construct and operate surface water management system serving 61 single- City of family lots on 34.57-ac Inside Not N/A O-07 Oak Trail Reserve Stormwater BMPs Completed 2017 1 2 34.57 Not provided Not provided Not provided N/A Ocoee residential Springshed provided development located in Wekiva River Protection Basin; sewered area. City of 1.79-ac car wash Inside Not N/A O-08 Ocoee Carwash Septic Phase Out Completed 2009 2 4 1.79 Not provided Not provided Not provided N/A Ocoee facility, Lake Lotta Springshed provided

Page 115 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Watershed; sewered area. 21.2-ac commercial and public development, including Walgreens City of Olympia Planned Inside Not N/A O-09 store and public Stormwater BMPs Completed 2001 1 1 21.20 Not provided Not provided Not provided N/A Ocoee Unit Development Springshed provided library; one wet detention system and one dry retention system constructed. Orchard Park Phase III – 30.7-ac subdivision is located west of Lake Addah, on south side of Clarcona-Ocoee Rd., in west Orange County; site is located in Wekiva River Hydrologic Basin, south of SR 436, within Most Effective City of Orchard Park Phase Recharge Area, but Online Retention Inside Not N/A O-10 Completed 2001 0 0 30.70 Not provided Not provided Not provided N/A Ocoee III Subdivision does not contain any BMP Springshed provided portions of Riparian Habitat Protection Zone (RHPZ); project consists of construction of 65-lot single-family residential subdivision and dry retention pond; applicant does not propose any development. Construct and operate dry retention system (retrofit) of BMPs to Peach Lake Manor City of serve 60-ac residential Online Retention Inside Not N/A O-11 Drainage Underway 2014 TBD 24 60.00 Not provided Not provided Not provided N/A Ocoee subdivision with no BMP Springshed provided Improvements conventional stormwater treatment; sewered area. Construct surface water management system to serve 42-ac City of Online Retention Inside Not N/A O-12 Prairie Lake Reserve residential subdivision Completed 2007 0 0 42.00 Not provided Not provided Not provided N/A Ocoee BMP Springshed provided (townhomes); 3 retention ponds permitted.

Page 116 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number 140-lot single-family Remington Oaks City of 49.5-ac subdivision Online Retention Inside Not N/A O-13 Phase I and II Completed 1999 0 0 49.50 Not provided Not provided Not provided N/A Ocoee with 2 dry retention BMP Springshed provided Subdivision ponds. City applied for government modification in accordance with Paragraph 40C- 42.024(2)(c), F.A.C.; city requested permission to perform construction activities in existing channel system that connects to Lake Lotta within Wekiva Recharge Protection Basin, but does not lie in Basin; construction activities include removing and replacing concrete Sabinal Ct. and stormwater junction Geneva St. Drainage box, removing City of Baffle Boxes – Inside Not N/A O-14 Improvements – segment of 30-in Completed 2011 TBD 4 45.20 $76,500 City Not provided N/A Ocoee 2nd Generation Springshed provided Prima Vista reinforced concrete Subdivision pipe (RCP), installing 18-in RCP, installing 42-in RCP to replace 30-in RCP, installing 2nd-generation baffle box, pipe end treatments, repairing and regrading channel side slopes, and installing stabilization matting; proposed improvements will alleviate flooding, improve safety, and improve water quality in subdivision that has no permitted stormwater management treatment system. 8.92-ac project; City of construct 52- Wet Detention Inside Not N/A O-15 Villa Roma Completed 2011 1 1 8.92 Not provided Not provided Not provided N/A Ocoee townhome subdivision Pond Springshed provided to be served by wet

Page 117 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number detention system; project will provide 100-yr compensating storage, sewered area. Construct 2 dry retention ponds to City of Villages of West Online Retention Inside Not N/A O-16 serve 33-lot, single- Completed 2000 0 0 5.50 Not provided Not provided Not provided N/A Ocoee Oak Subdivision BMP Springshed provided family, 5.5-ac subdivision. Construct surface City of Wellington Place water management Inside Not N/A O-17 Stormwater BMPs Completed 2003 0 0 14.00 Not provided Not provided Not provided N/A Ocoee Subdivision system to serve 14-ac Springshed provided residential subdivision. Construct 6.95-ac City of West Colonial commercial Inside Not N/A O-18 Stormwater BMPs Underway 2015 1 0 6.95 Not provided Not provided Not provided N/A Ocoee Property development; sewered Springshed provided area. Streets are swept daily; all debris collected from street sweeping and pollution boxes is City City of stockpiled and sent to Inside Not Not N/A O-19 Street Sweeping Street Sweeping Completed N/A 87 368 Not provided Stormwater Not provided N/A Ocoee landfill; length = 82 Springshed provided provided Fund mi; road length swept = 3,500 mi/yr; 600 tons of debris removed annually. Existing lift station at end of life cycle and experiencing Sanitary Sewer operational issues; Lift Station #7 Collection System City of relocate replacement Not Inside Not N/A O-20 Rehabilitation and Rehabilitation, Completed 2015 N/A N/A $1,901,067 City Not provided N/A Ocoee station north 900 ft, provided Springshed provided Relocation aintenance, or provide new generator Replacement set, provide bypass pumping, and increase pump horsepower. Construct surface water management system to serve 86- City of Inside Not N/A O-21 Willows on the Lake unit, single-family, Stormwater BMPs Completed 2001 1 1 15.18 Not provided Not provided Not provided N/A Ocoee Springshed provided 15.18-ac subdivision and 9.99-ac Publix shopping center. Bluford Ave. and Project consists of Orlando Ave, retrofitting area with City City of Inside Not N/A O-22 Storwater no stormwater Stormwater BMPs Completed 2016 TBD 3 23.7 $1,425,549 Stormwater Not provided N/A Ocoee Springshed provided Improvements collection and Fund Project treatment.

Page 118 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Project consists of revitalizing downtown Downtown area of city with Regional City of Redevelopment Not Not Inside Not City Funding N/A O-23 retrofitting with Stormwater Planned TBD 100.0 $50,000,000 Not provided N/A Ocoee Master Plan – provided provided Springshed provided and Bond regional storwater Treatment Bluford Ave. Area collection and treatment. Retrofitting Public Public Works City City of Works Complex with Wet Detention Inside Not N/A O-24 Complex Stormwater Completed 2016 TBD 10 7.5 $147,041 Stormwater Not provided N/A Ocoee stormwater Pond Springshed provided Management System Fund management system White Rd. Retrofitting road with City City of Inside Not N/A O-25 Stormwater exfiltration system Exfiltration Trench Completed 2017 TBD 3 1.6 $405,960 Stormwater Not provided N/A Ocoee Springshed provided Improvements design. Fund 310-ac site with construction of 7 dry retention ponds (2 of which are interconnected) for future construction. Runoff will be conveyed to master system for required treatment volume and City of Arden Park North Online Retention Inside Not N/A O-26 attenuation and Completed 2016 N/A N/A 310.0 Not provided Not provided Not provided N/A Ocoee Phase 2 BMP Springshed provided discharge as in predevelopment condition. Master system has been designed for future buildout condition of 595 single-family lots, roadways, storm sewer system, clubhouse, and school. Project consists of 133 single-family lots, roadway, storm sewer system, extending portion of Clark Rd. and 1 dry retention pond. Runoff from site City of will be conveyed to Online Retention Inside Not N/A O-27 McCormick Reserve Completed 2016 N/A N/A 38.1 Not provided Not provided Not provided N/A Ocoee dry retention pond for BMP Springshed provided required treatment volume and attenuation and discharge to match predevelopment condition. O&M for portion of Clark Rd. to

Page 119 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number be constructed under application is City of Ocoee. Major modification to existing permit known as Whispering Pines Subdivision because of project name change, ownership change, product change, layout change and associated changes to drainage patters and infrastructure. Ocoee Pines is proposed single-family City of development that will Stormwater BMP Inside Not N/A O-28 Forest Lake Estates Completed 2016 N/A N/A 97.7 Not provided Not provided Not provided N/A Ocoee consist of 278 single- Retrofit/Expansion Springshed provided family homes and community amenity center located in City of Ocoee on both east and west side of Clarcona-Ocoee Rd. There will be expansion to existing pond previously permitted with Clarcona-Ocoee Rd. under ERP 40-095- 70576-6. Proposed project is single-family subdivision, and system includes 79 single-family lots, City of roads, storm sewer Online Retention Inside Not N/A O-29 Spring Lake Reserve Completed 2016 N/A N/A 17.4 Not provided Not provided Not provided N/A Ocoee system, and 3 dry BMP Springshed provided retention ponds (2 interconnected). Project is located in Wekiva River Hydrologic Basin. Proposed modification Flewelling Ave. consists of retrofitting Unknown City of Ocoee City of Stormwater Baffle Boxes – Inside N/A O-30 113-ac watershed with Underway 2018 TBD 10 113.7 $340,000 at this Stormwater $1 N/A Ocoee Treatment System 2nd Generation Springshed 2nd-generation baffle time Utility Fund Project box

Page 120 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Fertilizer Ordinance Fertilizer managament Regulations, City of – Orange County Inside N/A O-31 ordinance – Ordinances, and Completed N/A 135 N/A N/A N/A N/A N/A N/A N/A Ocoee Ordinance No. 2017- Springshed countywide. Guidelines 14 Regulations, City of Local Landscaping Inside N/A O-32 Landscaping ordinance Ordinances, and Completed N/A 135 N/A N/A N/A N/A N/A N/A N/A Ocoee Ordinance Springshed Guidelines Information City of pamphlets, IDDE Public Education Inside N/A O-33 PSAs Completed N/A 270 N/A N/A N/A N/A N/A N/A N/A Ocoee training, and Efforts Springshed pamphlets. Install depressional retention on all new Individual Single-Family infill single-family Town of Online Retention Prior to Inside Not Not property OAK-01 Residential Infill residences in old part Completed N/A N/A Not provided Not provided Not provided Not provided Oakland BMP 2015 Springshed provided provided owners Depressions of town to increase recharge and decrease surface flow. Drainage conveyance maintenance in established neighborhood to enable proper Town of Town of Southern Oaks – Stormwater System Inside approx. Not OAK-02 treatment of Completed 2017 N/A N/A $30,000 Not provided Not provided Not provided Oakland Oakland Phase 1 and 2 Rehabilitation Springshed 15 ac provided stormwater flows. Lack of maintenance had caused sheet flows to bypass existing treatment ponds. Construct earthen berm to intercept sheet flows from Speer Park and adjacent streets. Town of Town of Speer Park Improvements provide Not Not Inside approx. Not OAK-03 Stormwater BMPs Completed 2016 $15,000 Not provided Not provided Not provided Oakland Oakland Stormwater attenuation and provided provided Springshed 5 ac provided treatment of stormwater flows to reduce pollutant loading and erosion. Construct new stormwater collection system comprising DEP/EPA biofilteration retention 319(h)/ Design Cost – Stormwater/Drainage ponds, storm pipes and DEP #NF008 Town of SJRWMD/ Inside unknown Not OAK-04 Improvements – inlets, and swales in Stormwater BMPs Underway 2018 8 10 39 Not provided Not provided SJRWMD Oakland DEP TMDL/ Springshed Construction Cost provided Mid-Town – Phase 1 town's Lower Basin #28782 Town of – Phase 1 $579,787 (Phase 1). Three Oakland existing retention ponds will be modified and will use Bold and

Page 121 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Gold™ bioabsorption material. Drainage conveyance maintenance in established Town of Town of Townwide Drainage Stormwater System Inside 2017 – $20,000 OAK-05 neighborhoods to Completed 2017 N/A N/A TBD TBD TBD Town N/A Oakland Oakland Maintenance Rehabilitation Springshed 2018 – $20,000 enable proper treatment of stormwater flows. Creation of centralized wastewater system to enable "zero growth" Town of Town of Oakland Sewer Wastewater Service Inside OAK-06 of septic systems and Completed 2016 N/A N/A N/A N/A Oakland Oakland Master Plan Area Expansion Springshed to allow for conversions of existing septic systems. Construction of regional sewage lift Town of Oakland Sanitary station and force main Wastewater Service Inside Not DEP OAK-07 Completed 2017 N/A N/A $700,000+- TBD DEP $250,000 LP4803I Oakland Sewer – Phase 1A that conveys sewage to Area Expansion Springshed provided Clermont for treatment. Expansion of wastewater system to Design cost – Oakland Sanitary Town of eliminate existing Wastewater Service Inside Not $85,000 (est.) DEP OAK-08 Sewer – Phase 1B Underway 2018 N/A N/A TBD DEP $1,000,000 LP4803J Oakland septic systems and Area Expansion Springshed provided Construction cost – and 1C allow new growth $1,300,000 (est.) without septic. Acquisition of 35 ac of Town of Town of Hull Island wetlands and 2 ac of Inside Oak-09 Land Acquisition Underway 2018 N/A N/A 37 $500,000 N/A N/A N/A N/A Oakland Oakland Development upland along south Springshed shore of Lake Apopka. Installation of cenralized sewer in existing industrial area Design cost – Town of Oakland Sewer (Industrial Extension) Wastewater Service Inside Not $85,000 (est.) DEP Oak-10 Underway 2019 N/A N/A TBD DEP $1,000,000 LP4803L Oakland Expansions – 2017 and improvements to Area Expansion Springshed provided Construction cost – serve areas east of SR $1,300,000 (est.) 50 and Turnpike interchange. Construction of sanitary sewer force Turnpike Force Main Design cost – main under SR 50 and Town of and Longleaf at Wastewater Service Inside Not $40,000 Pulte Homes Oak-11 Florida Turnpike Underway 2018 N/A N/A TBD Pulte Homes $5,000,000 N/A Oakland Oakland Area Expansion Springshed provided Construction cost – interchange, and sewer Development $5,450,000 network to serve 200 residential units.

Page 122 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Construct regional sewage lift station and Design cost – Railroad Ave. Town of Town of associated gravity Wastewater Service Inside Not $35,000 Oak-12 Sanitary Sewer Lift Underway 2018 N/A N/A TBD Town $430,000 N/A Oakland Oakland sewer to allow for Area Expansion Springshed provided Construction cost – Station future septic system $400,000 abandonments. Erosion protection of Little Wekiva River; Orange Shoreline Prior to Inside Not Not provided OC-01 Elba Way install gabions, grade Completed 24 35 N/A $1,000,000 Not provided Not provided Not provided County Stabilization 2015 Springshed provided control structures, river reshaping. Remove existing triple aluminum pipes along Little Wekiva River at Gusty Lane Dr. and Orange replace with control Prior to Inside Not Not provided OC-02 Gusty Lane Control Structure Completed 5 8 N/A $132,000 Not provided Not provided Not provided County structure using rip-rap 2015 Springshed provided and gabion materials; install pipe and inlet for existing ditch adjacent to canal. Erosion protection of Orange NRCS Riverside Little Wekiva river Shoreline Prior to Inside Not Not provided OC-03 Completed 7 11 N/A $650,000 Not provided Not provided Not provided County Acres bank, install rip-rap; Stabilization 2015 Springshed provided project length = 287 ft. Erosion protection of Little Wekiva Orange NRCS Riverside Shoreline Prior to Inside Not Not provided OC-04 riverbank, install rip- Completed 4 6 N/A $350,000 Not provided Not provided Not provided County Park Ave. Stabilization 2015 Springshed provided rap; project length 150 ft. Replace existing 1,750 ft of pipe-arch pipe in Riverside Acres Orange Riverside Acres Subdivision with open Hydrologic Prior to Not Not Inside Not Not provided OC-05 Completed N/A $5,000,000 Not provided Not provided Not provided County Arch Pipe channel section and Restoration 2015 provided provided Springshed provided restore to reflect original river configuration. Banks in main stem of river and into Lake Lovely Outfall Canal, including grade control Orange Shoreline Prior to Inside Not Not provided OC-06 Riverside Park Rd. structure; project Completed 25 38 N/A $600,000 Not provided Not provided Not provided County Stabilization 2015 Springshed provided includes gabions, Reno mattress, and riprap channel bottom and side bank protection.

Page 123 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Erosion protection of Little Wekiva River Orange bank; install gabion Shoreline Prior to Inside Not Not provided OC-07 Sherry Dr. Completed 10 15 N/A $600,000 Not provided Not provided Not provided County block and Reno Stabilization 2015 Springshed provided mattress; project length = 400 ft. Little Wekiva Slope Eliminate bank erosion Orange Shoreline Prior to Inside Not Not provided OC-08 Stabilization by using steel sheet Completed 32 49 N/A $700,000 Not provided Not provided Not provided County Stabilization 2015 Springshed provided West/East Banks pile. Previous land use = agriculture; management focus = Orange Lake Lucie Prior to Inside Orange County OC-09 scrub habitat and water Land Use Change Completed 9 11 166 $4,397,800 N/A N/A Inside Springshed N/A County Conservation Area 2015 Springshed resource, passive recreational; ac = 166.22. DEP, SJRWMD, Orange OOCEA, and Lake and County/ Orange Counties SJRWMD/ partnered to buy land Orlando- and put into Orange County Orange conservation; previous Prior to Inside Central Florida OC-10 Neighborhood Lakes Land Acquisition Completed N/A N/A 498 $7,000,000 N/A Not provided Not provided N/A County land use = agriculture; 2015 Springshed Expressway management focus = Authority water resource, (OOCEA)/ passive; ac = 1,584 Lake County/ (498 ac in Orange TIF County). Previous land use = agriculture; Orange Prior to Inside Orange County OC-11 Pine Plantation management focus = Land Use Change Completed 0 0 40 $1,000,000 N/A N/A N/A N/A County 2015 Springshed passive recreation, preservation; ac = 40. Previous land use = agriculture; Orange Prior to Inside Orange County OC-12 Sandhill Preserve management focus = Land Use Change Completed 7 8 83 $3,320,000 N/A N/A N/A N/A County 2015 Springshed water resource, sandhill; ac = 83.03. Inspect private/public stormwater ponds for Orange Stormwater Pond Stormwater BMP Prior to Inside Not Not provided OC-13 compliance with Completed N/A N/A N/A Not provided Not provided Not provided Not provided County Inspection Inspections 2015 Springshed provided performance and permit conditions. Project will reduce Orange Tree Planting at Elba Prior to Inside Not Not provided OC-14 temperature of water Tree Planting Completed N/A N/A N/A $55,000 Not provided Not provided Not provided County Way/Riverside Park 2015 Springshed provided and improve SCI. New stormwater Orange 11th and 12th St. Prior to Inside Not Not Not provided OC-15 treatment to serve 11th Stormwater BMP Completed 12 69 Not provided Not provided Not provided Not provided County Improvement 2015 Springshed provided provided and 12th Sts.; 8.8 ac.

Page 124 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Four-lane road improvement; existing Orange Clarcona Ocoee East 2 lanes do not have Not Inside Not Not Not provided OC-16 Stormwater BMP Underway 8 47 Not provided Not provided Not provided Not provided County and West Segments stormwater treatment; provided Springshed provided provided project length = 2.5 mi. Four-lane road improvement; existing Orange Prior to Inside Not Not Not provided OC-22 Rock Spring Rd. 2 lanes do not have Stormwater BMPs Completed 7 39 Not provided Not provided Not provided Not provided County 2015 Springshed provided provided stormwater treatment; project length = 2 mi. Pave .3-ac dirt road; Grass Swales with Orange treatment with open Prior to Inside Not Not Not provided OC-23 11th Ave. Swale Blocks or Completed 0 2 Not provided Not provided Not provided Not provided County swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave .5-ac dirt road; Grass Swales with Orange treatment with open Prior to Inside Not Not Not provided OC-24 13th Ave. Swale Blocks or Completed 1 4 Not provided Not provided Not provided Not provided County swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave .3-ac dirt road; Grass Swales with Orange treatment with open Prior to Inside Not Not Not provided OC-25 15th Ave. Swale Blocks or Completed 0 2 Not provided Not provided Not provided Not provided County swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave .6-ac dirt road; Grass Swales with Orange treatment with open Prior to Inside Not Not Not provided OC-26 17th Ave. Swale Blocks or Completed 1 5 Not provided Not provided Not provided Not provided County swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave .12-ac dirt road; Grass Swales with Orange Lake Pleasant Rd. treatment with open Prior to Inside Not Not Not provided OC-27 Swale Blocks or Completed 0 1 Not provided Not provided Not provided Not provided County Improvement swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave 0.3-ac dirt road; Grass Swales with Orange Quenton Ave. and Prior to Inside Not Not Not provided OC-28 treatment with open Swale Blocks or Completed 0 2 Not provided Not provided Not provided Not provided County Range Dr. 2015 Springshed provided provided swale and ditch blocks Raised Culverts Pave 1-ac dirt road; Grass Swales with Orange Ridge Terrace and Prior to Inside Not Not Not provided OC-29 treatment with open Swale Blocks or Completed 1 9 Not provided Not provided Not provided Not provided County Roan Rd. 2015 Springshed provided provided swale and ditch blocks. Raised Culverts Pave 0.6-ac dirt road; Grass Swales with Orange Prior to Inside Not Not Not provided OC-30 New Hampshire treatment with open Swale Blocks or Completed 1 6 Not provided Not provided Not provided Not provided County 2015 Springshed provided provided swale and ditch blocks. Raised Culverts Pave 1.1-ac dirt road; Grass Swales with Orange treatment with open Prior to Inside Not Not Not provided OC-31 Sadler Rd. Swale Blocks or Completed 2 9 Not provided Not provided Not provided Not provided County swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave 98.93-ac dirt Alternative Surface Grass Swales with Orange road; treatment with Prior to Inside Not Not Not provided OC-32 Program – Group Swale Blocks or Completed 140 780 Not provided Not provided Not provided Not provided County open swales and ditch 2015 Springshed provided provided IIIA Projects Raised Culverts blocks.

Page 125 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Pave 61.53-ac dirt Alternative Surface Grass Swales with Orange roads; treatment with Prior to Inside Not Not Not provided OC-33 Program – Group Swale Blocks or Completed 87 485 Not provided Not provided Not provided Not provided County open swales and ditch 2015 Springshed provided provided IIIB Projects Raised Culverts blocks. Pave 0.9-ac dirt road; Grass Swales with Orange Boxwood Dr. and treatment with open Prior to Inside Not Not Not provided OC-34 Swale Blocks or Completed 1 7 Not provided Not provided Not provided Not provided County Bull Run Rd. swales and ditch 2015 Springshed provided provided Raised Culverts blocks. Pave 1.5-ac dirt road; Hereford Rd., Grass Swales with Orange treatment with open Prior to Inside Not Not Not provided OC-35 Highland St., and Swale Blocks or Completed 2 12 Not provided Not provided Not provided Not provided County swales and ditch 2015 Springshed provided provided Holly St. Raised Culverts blocks. Streets are swept every Orange Inside Not Not Not provided OC-36 Street Sweeping 6 wks; 481,128 lbs/yr Street Sweeping Completed N/A 29 121 Not provided Not provided Not provided N/A County Springshed provided provided of material removed. Study to evaluate Lake Gandy Orange hydrologic conditions Prior to Inside Not Not provided OC-37 Hydrologic and Study Completed N/A N/A N/A Not provided Not provided Not provided N/A County and nutrient loadings 2015 Springshed provided Nutrient Study to Lake Gandy. Install 1,200 ft of 4-in force main; new force main expected to prevent wastewater leakage; All American Blvd. from Clarcona Ocoee to Kennedy; force main from Avalon Rd. to Hiawassee Rd. 7,600 LF 36-in force main; 760 LF 30-in force main; and 1,200 LF 12-in force main. Sanitary Sewer Many parcels near 35- Collection System Orange Force Main/Gravity Inside Not Not provided OC-39 21-28-0000-00-150; Rehabilitation, Underway TBD N/A N/A N/A $10,494,000 Not provided Not provided Not provided County Replacement Springshed provided install 4,500 LF of 12- Maintenance, or in force main. New Replacement force main expected to prevent wastewater leakage. Clarcona Ocoee Rd. from Ingram to Clarke; install 11,000 LF of force main from Indian Hill Rd. to PS #3411. New force main will prevent wastewater leakage. North Pine Hills Rd. at Indian Hill Rd. and Clarcona

Page 126 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Ocoee Rd.; relocate 710 LF 4-in force main 1,280 LF 16-in force main; and 710 LF 8-in gravity main. Many parcels near 30-21-29- 0521-00-010.

Sanitary Sewer Pump Station Collection System Orange Replace multiple pump Prior to Inside Not Not provided OC-40 Removal/Relocation Rehabilitation, Completed N/A N/A N/A $13,263,500 Not provided Not provided Not provided County stations. 2015 Springshed provided (R/R) Maintenance, or Replacement Combine cured in place pipe (CIPP) and point repairs to restore 10,000 LF of 8-in gravity sanitary sewer, including lining or coating 40 manholes. Sanitary Sewer Near 20-22-29-4552- Orange Collection System Force Main/ Gravity 08-001; in addition to Inside Not County Not provided OC-41 Rehabilitation, Underway 2016 TBD TBD N/A $1,780,000 Not provided Not provided Not provided Sewer Rehabilitation upsized storm pipes Springshed provided (Utilities) Maintenance, or that go to Lake Robin, Replacement project includes replacing force main, gravity line, and manhole; replacement of force main will reduce leakage of sewage. Near 24-22-

Page 127 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number 28-7573-15-250; remove and relocate Pump Station #3045, plus remove existing force main and install 800 ft of gravity sewer., 29-21-29- 4940-00-230.

Orange Stormwater treatment BMP Treatment Inside Not Not Not provided OC-42 Little Wekiva STA Planned 2021 TBD TBD $5,000,000 County Not provided Not provided County train. Train Springshed provided provided Orange Stormwater treatment BMP Treatment Inside Not Not provided OC-43 Lake Gandy BMP Canceled N/A N/A N/A 150 $1,000,000 County Not provided Not provided County train. Train Springshed provided Project consists of design and construction of new physical, biological and chemical treatment facilities for raw sewage. WRF will be upgraded from 7.5 to 11.25 mgd and nitrogen will be OCU Capital Orange County Orange Northwest WRF reduced to less than 3 WWTF Nutrient Inside $31,000,000/ Not Improvements Utilities OC-45 Completed 2012 TBD 45,000 N/A Not provided N/A County Phase III Expansion mg/L. Pretreatment Reduction Springshed Capital Dollars provided Program (OCU) structural Budget improvements, additional biological nutrient removal basins, modification of clarifier equipment, addition of cloth filtration, additional chlorine contact facilities. Install 180 CIBs Orange Inside Not provided OC-46 Little Wekiva CIBs around Little Wekiva Catch Basin Inserts Completed 2017 11 18 N/A $196,899 22,000 County Not provided Not provided County Springshed Basin. Septic upgrade to Orange Trimble Park Office Septic Inside Not OCEPD OC-47 passive nitrogen Completed 2018 TBD 1 N/A $0 Vendor Not provided Not provided County Septic Enhancement springshed provided treatment.

Page 128 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Conversion of park Orange Magnolia Park Inside Not Facilities/Parks OC-48 facilities from septic to Septic Phase Out Underway 2018 TBD 86 N/A $400,000 DEP $250,000 Appropriation County Sanitary Connection springshed provided sanitary. Conversion of park Orange Camp Joy Sanitary Inside Not Facilities/Parks OC-49 facilities from septic to Septic Phase Out Underway 2019 TBD 4 N/A Not provided County Not provided Not provided County Connection springshed provided sanitary. Orange County North Orange Conversion of Orange Library Inside Not OC-50 Branch Sanitary facilities from septic to Septic Phase Out Underway 2018 TBD 22 N/A $105,832 OCLS Not provided Not provided County System springshed provided Connection sanitary. (OCLS) Treatment train Orange consisting of activated Inside Not OCEPD OC-51 Lake Gandy BMP Other Planned 2020 TBD 9 N/A $1,000,000 County Not provided Not provided County media beds, modular springshed provided wetlands. Inspect annually all 233 commercial, single-family, and multifamily systems in basin for functionality; systems include, but are not limited to, Compliance City/ Streets retention and detention City of Inspections of Stormwater BMP Inside Not and Not provided ORL-01 ponds, underdrains, Completed 1989 N/A N/A N/A Not provided Not provided Not provided Orlando Private Stormwater Inspections Springshed provided Stormwater exfiltration, and Systems Division underground vaults; by maintaining ponds at design criteria, city is ensuring optimal level of pollutant removal efficiency is being achieved. Inspection and perform routine maintenance on 13 ponds and 31 City/ Streets ditches in basin to City of Stormwater System Stormwater BMP Inside Not and Not provided ORL-02 ensure systems are Completed 1970 N/A N/A N/A Not provided Not provided Not provided Orlando Inspections Inspections Springshed provided Stormwater maintained at optimal Division pollutant removal efficiency (and flood prevention). Install (2006) 2 inlet City /Streets baskets in Lake Daniel City of Two Inlet Baskets Inside Not and Not provided ORL-03 Basin; 1.89 cubic Catch Basin Inserts Completed N/A 0 2 N/A $1,500 Not provided Not provided Orlando Around Lake Daniel Springshed provided Stormwater yds/yr of material Division collected. Install (2008) 22 inlet City /Streets 22 Inlet Baskets baskets in Lake City of Inside Not and Not provided ORL-04 Around Lake Orlando Basin; 47.29 Catch Basin Inserts Completed N/A 11 45 22 $7,770 Not provided Not provided Orlando Springshed provided Stormwater Orlando cubic yds/yr of Division material collected.

Page 129 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Streets are swept every City /Streets City of 2 wks; 5,023.2 cubic Inside Not Not and Not provided ORL-12 Street Sweeping Street Sweeping Completed N/A 23 98 Not provided Not provided N/A Orlando yds/yr of material Springshed provided provided Stormwater collected. Division Little Wekiva River Nutrient reduction – Preliminary projects in Little City /Streets Engineering Wekiva River City of ORL- Inside and Not provided Evaluation Lake Watershed, using Study Completed 2008 N/A N/A N/A $49,900 N/A Not provided N/A Orlando 13a Springshed Stormwater Lawne, Center of suggested drainage Division Commerce, and Lake improvements from Orlando Sites CDM report. Improve sanitary sewer, drainage, and roadway; install new sanitary force main, lift station (#65), and Sanitary Sewer gravity pipes in area Collection System City /Water City of Fairview Shores – with septic tanks to Not Not Inside Not Not provided ORL-15 Rehabilitation, Completed 2008 N/A $4,522,401 Reclamation Not provided Not provided Orlando North Service Area reduce nutrient provided provided Springshed provided Maintenance, or Division seepage into Replacement groundwater table; install 2 Stormceptors™ to capture pollutants before they reach lake. Install variable frequency drives that will extend life of Sanitary Sewer City of Lift Station #85 pump motors, Collection System City of Prior to Not Not Inside Not Orlando/Water Not provided ORL-20 Variable Frequency preventing potential Rehabilitation, Completed N/A N/A Not provided Not provided Orlando 2015 provided provided Springshed provided Reclamation Drive overflows; will also be Maintenance, or Division more energy efficient Replacement at future cost savings to city. Relocate and completely rebuild lift Sanitary Sewer station with new, Collection System City /Water City of Lift Station #93 Not Not Inside Not Not provided ORL-21 upgraded equipment, Rehabilitation, Completed 2001 N/A $767,632 Reclamation Not provided Not provided Orlando Improvements provided provided Springshed provided including generator not Maintenance, or Division present at previous Replacement location. Updated WWTF infrastructure to achieve lower nutrient Water Conserv II concentrations – DEP State City of WWTF Nutrient Not Inside Not DEP ORL-28 Treatment Replaced aging Completed 2016 69,436 1,160 12,500,000 Revolving $11,700,000 WW480400 Orlando Reduction provided Springshed provided Improvements blowers and diffusers; Fund (SRF) added internal recycle and big bubble mixing. rebuilt secondary

Page 130 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number clarifiers with spiral scrapers and clarifier inlet.

Identify and inventory OSTDS areas with in city service area and OSTDS Wekiva Overlay Identification, City /Water City of District; Develop Inside N/A ORL-30 Assessment and Study Underway 2018 N/A N/A N/A 112,000 N/A Reclamation $112,000 N/A Orlando ranking criteria and Springshed Alternatives Division cost estimates for Development Study retrofit of OSTDS; Prioritize areas for retrofit consideration. Increase water quality treatment resonance Sweetwater Cove time through water Dredging and quality treatment pond Drainage expansion, construct Seminole Stormwater BMP Inside Not Not provided SC-01 Improvements and online sedimentation Completed 2010 396 68 2,181 $2,700,000 Not provided Not provided Not provided County Retrofit/Expansion Springshed provided Sweetwater basin; carry out Tributary Erosion erosion control Project measures along Sweetwater Creek; area served = 2,181 ac. Reduce sediment loads through bank stabilization and river Seminole Grade Control Shoreline Inside Not Not provided SC-02 grade control Completed 2001 26 18 N/A $300,000 Not provided Not provided Not provided County Structures 6 and 7 Stabilization Springshed provided structures in Little Wekiva River; area served = >5,000 ac. Reduce sediment loads through bank stabilization along Spring Lake outfall, Horse Lovers Lane Seminole tributary to Little Shoreline Inside Not Not provided SC-03 Erosion Control Completed 2004 17 12 N/A $700,000 Not provided Not provided Not provided County Wekiva River; use Stabilization Springshed provided Project gabions and grade control structures plus replace culverts; area served = >1,000 ac. Reduce sediment loads North Western Seminole through bank Shoreline Inside Not Not provided SC-04 Erosion Control Completed 2004 5 3 N/A $950,000 Not provided Not provided Not provided County stabilization along Stabilization Springshed provided Project Little Wekiva River;

Page 131 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number area served = >5,000 ac. Reduce sediment loads through bank Weathersfield Seminole stabilization along Shoreline Inside Not Not provided SC-05 Erosion Control Completed 2001 4 3 N/A $750,000 Not provided Not provided Not provided County Little Wekiva River; Stabilization Springshed provided Project area served = >5,000 ac. Exotics removal/ revegetation with native species. Seminole Exotic Vegetation Not Not Inside Not Not provided SC-10 Mirror Lake Accomplished using Completed 2010 N/A $75,000 Not provided Not provided Not provided County Removal provided provided Springshed provided in-house staff, residents, and volunteers. Provide water quality treatment to existing roadway and Seminole Bear Lake Rd. subdivision through Inside Not Not Not provided SC-14 Stormwater BMPs Completed 2008 14 32 $2,200,000 Not provided Not provided Not provided County Reconstruction increased wet retention Springshed provided provided and use of existing dry retention pond; area served = 32 ac. Provide treatment to untreated roadway through construction of new wet retention Seminole Inside Not Not Not provided SC-15 Bunell Rd. Widening basin and exfiltration Stormwater BMPs Completed 2010 5 9 $3,200,000 Not provided Not provided Not provided County Springshed provided provided trench; designed to hold treatment volume plus 50 %; area served = 7.5 ac. Provide treatment to untreated roadway through exfiltration, Seminole Inside Not Not Not provided SC-16 Eden Park Rd. installation of CDS Stormwater BMPs Completed 2010 9 14 $3,500,000 Not provided Not provided Not provided County Springshed provided provided units, and new wet retention basin; area served = 10.6 ac. Construct wet detention pond and provide ecological restoration on drainage Seminole Triangle Dr. Wet Detention Inside Not Not Not provided SC-19 parcel near Triangle Canceled N/A 34 146 $800,000 Not provided Not provided Not provided County Treatment Pond Pond Springshed provided provided Dr. prior to draining into Lake Brantley; area served = 372 ac.

Page 132 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Construct 2 interconnected sedimentation ponds to Wekiva Springs Rd. provide additional Seminole Online Retention Inside 2 square Not Not provided SC-20 at Wekiva Springs water quality treatment Completed 2005 25 50 $220,000 Not provided Not provided Not provided County BMP Springshed mi provided State Park for 2 square mi of residential development; area served = 2 square mi. Provide water quality Wekiva Springs Rd. treatment to existing Grass Swales with Seminole Inside Not Not Not provided SC-21 Hunt Club to Fox roadway through Swale Blocks or Completed 2008 8 9 $1,800,000 Not provided Not provided Not provided County Springshed provided provided Valley swales; area served = Raised Culverts 7 ac. Construct wet detention pond and provide ecological restoration on drainage Seminole West Wekiva Tr. Wet Detention Inside Not Not Not provided SC-22 parcel north of West Underway TBD 17 74 $900,000 Not provided Not provided Not provided County Treatment Pond Pond Springshed provided provided Wekiva Tr. prior to discharge into Wekiva River; area served = 220 ac. Provide water quality treatment for new impervious portions of Wekiva Springs Rd. Seminole roadway improve- Inside Not Not Not provided SC-24 – SR 434 to Sabal Exfiltration Trench Completed 2008 2 3 $6,900,000 Not provided Not provided Not provided County ments through Springshed provided provided Point construction of online exfiltration trench; area served = 3.4 ac. Street sweeping in Big Seminole Inside Not Not Not provided SC-25 Street Sweeping Wekiva and Little Street Sweeping Completed N/A 3 14 Not provided Not provided Not provided N/A County Springshed provided provided Wekiva Basins. Detailed nutrient and hydrologic study, identifying and quantifying all nutrient sources, including Bear Lake Chain-of- internal loading, Lakes Hydrology/ groundwater, surface Seminole Prior to Inside Not Not provided SC-26 Nutrient Budget and water, precipitation, Study Completed N/A N/A N/A Not provided Not provided Not provided N/A County 2015 Springshed provided Water Quality etc.; management plan Management Plan includes potential structural and nonstructural improvements that can be made to protect and enhance water quality.

Page 133 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Detailed nutrient and hydrologic study, identifying and quantifying all nutrient sources, including Spring Lake/Spring internal loading, Lake Watershed groundwater, surface Seminole Hydrology/Nutrient Inside Not Not provided SC-27 water, precipitation, Study Underway TBD N/A N/A N/A Not provided Not provided Not provided N/A County Budget and Water Springshed provided etc.; management plan Quality Management includes potential Plan structural and nonstructural improvements that can be made to protect and enhance water quality. Preliminary analysis of nitrogen transport into and out of retention Wekiva Basin pond/groundwater, and Stormwater Pond Seminole follow-up analysis of Inside Not Not provided SC-28 Enhancement Study Underway TBD N/A N/A N/A Not provided Not provided Not provided N/A County improvements made to Springshed provided Feasibility Study for groundwater discharge Nitrogen Transport after addition of Bold and Gold™ amendment to pond bottom. Countywide assessment of all water quality data, monitoring programs, regional ponds, CIP Seminole County Seminole projects, etc., to Inside Not Not provided SC-29 Water Quality Study Underway TBD N/A N/A N/A Not provided Not provided Not provided N/A County improve efficiency and Springshed provided Master Plan effectiveness of existing programs and identify additional structural/nonstructural improvement projects. Sanitary Sewer Collection System Seminole Prior to Inside Not Not provided SC-31 Bridgewater Dr. Manhole sealing. Rehabilitation, Completed N/A N/A N/A $16,179 Not provided Not provided Not provided County 2015 Springshed provided Maintenance, or Replacement Seal wet well and rehabilitate lines at lift Sanitary Sewer stations (Wilson Collection System Seminole Lift Station School, Breckenridge, Prior to Inside Not Not provided SC-33 Rehabilitation, Completed N/A N/A N/A $324,353 Not provided Not provided Not provided County Rehabilitation Stockbridge, Lake 2015 Springshed provided Maintenance, or Forest #5, Replacement Buckingham, Retreat at Wekiva, Aster

Page 134 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Farms, Bel-Aire #3, Bel-Aire #1, Heathrow Master). Bear Lake Drainage Regional stormwater Regional Seminole Not Not Inside Not Not provided SC-35 Improvements facility (RSF) for Bear Stormwater Underway 2018 23 $1,150,000 Not provided Not provided Not provided County provided provided Springshed provided (Hamilton Pond) Lake, Little Bear Lake. Treatment Modify existing stormwater pond to Seminole Alton Dr. increase treatment Wet Detention Not Not Inside Not Not Florida Not provided SC-37 Underway 2019 Not provided Not provided Not provided County Stormwater Pond efficiency and reroute Pond provided provided Springshed provided provided Legislature untreated stormwater into existing pond. Mechanical removal of vegetative material and Seminole Lake Asher Aquatic Vegetation Not Not Inside Not Florida Not provided SC-39 associated organic Completed 2017 N/A $285,000 Not provided Not provided County Restoration Harvesting provided provided Springshed provided Legislature matter. Shoreline planting with natives. Planted native aquatic Sweetwater Cove Seminole vegetation along Creating/Enhancing Not Not Inside Not Not provided SC-43 Shoreline Completed 2017 N/A Not provided Not provided Not provided Not provided County individual homeowner Living Shoreline provided provided Springshed provided Restoration shorelines. Planted native aquatic Lake Brantley Seminole vegetation along Creating/Enhancing Not Not Inside Not Not provided SC-44 Shoreline Completed 2017 N/A Not provided Not provided Not provided Not provided County individual homeowner Living Shoreline provided provided Springshed provided Restoration shorelines. Planted native aquatic Mirror vegetation along Creating/Enhancing Not Not Inside Not Not provided SC-45 Shoreline Completed 2017 N/A Not provided Not provided Not provided Not provided County individual homeowner Living Shoreline provided provided Springshed provided Restoration shorelines. Planted native aquatic Seminole Bear Lake Shoreline vegetation along Creating/Enhancing Not Not Inside Not Not provided SC-46 Planned TBD N/A Not provided Not provided Not provided Not provided County Restoration individual homeowner Living Shoreline provided provided Springshed provided shorelines. Seminole Sweetwater Cove Macroalgal Not Not Inside Not Not provided SC-47 Harvesting of lyngbya. Completed 2017 N/A Not provided Not provided Not provided Not provided County Lyngbya Harvesting Harvesting provided provided Springshed provided Seminole Nutrient Filter Pilot Not Not Inside Not Not Not provided SC-48 Not provided. TBD Planned TBD Not provided Not provided Not provided N/A County Project provided provided Springshed provided provided Sanitary Sewer Seal and coat 5 Lynwood Gravity Collection System Seminole manholes; CIPP lining Not Not Inside Not Not Not provided SC-52 Main and Manhole Rehabilitation, Completed 2017 $57,000 Not provided Not provided Not provided County of 1,445 LF of 8-in provided provided Springshed provided provided Repairs Maintenance, or gravity main. Replacement Rehabilitation Sanitary Sewer including 2 new Flygt, Foxwood Pump Collection System Seminole new pump base plates Not Not Inside Not Not Not provided SC-53 Station Rehabilitation, Completed 2017 $48,000 Not provided Not provided Not provided County and elbow; new 4-in provided provided Springshed provided provided Rehabilitation Maintenance, or stainless steel Replacement discharge piping.

Page 135 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Altamonte/ Reduction of nitrogen Ad Valorem $28,000 Annual Casselberry/ and phosphorus Regulations, Seminole Seminole County Not Inside Taxes and City Cost-Share Lake Mary/ SC-54 sources, through Ordinances, and Completed N/A 1,736 14,267 150,000 65,000 NF034 County Fertilizer Ordinance provided Springshed FFL Cost- Total/ $37,000 Longwood/ public education and Guidelines Share County Portion Oviedo restrtictions on usage. Additional credits from Seminole County ordinance outside of standard 6 %. Ordinance is more restrictive than state model as follows: 15- foot setback from waterbodies; no nitrogen fertilizer during rainy season (June 1 to Sept. 30); at least 50 % slow- Altamonte/ release nitrogen (SRN) Ad Valorem $28,000 Annual Casselberry/ Seminole County outside rainy season, Regulations, Seminole Not Inside Taxes and City Cost-Share Lake Mary/ SC-54a Ordinance and increasing to 65 % Ordinances, and Planned TBD TBD 14,267 150,000 65,000 NF034 County provided Springshed FFL Cost- Total/$37,000 Longwood/ Education Credits SRN after 3 yrs. Guidelines Share County Portion Oviedo Seminole County is working on quantifying reductions attributed to ordinance through multipronged assessment of Wekiva Subbasin, including educational outreach, behavioral surveys, and nutrient studies. Estimated nitrogen reductions are based on leaching calculations. Retrofit existing inlet Seminole Spring Lake Baffle Baffle Boxes – Not Inside Not Not provided SC-55 as pollutant removal Planned TBD 21 55 200,000 Not provided Not provided Not provided County Box 2nd Generation provided Springshed provided structure. Excavate and recontour outfall canal Muck Removal/ Seminole Spring Lake Outfall to remove existing Not Not Inside Not Not Not provided SC-56 Restoration Planned TBD 580,000 Not provided Not provided Not provided County Canal Excavation acumulations of provided provided Springshed provided provided Dredging organic muck and vegetation debris. Rehabilitate weir in Spring Lake Hills Seminole Spring Lake Hills Not Inside Not Not Not provided SC-57 Outfall Weir Control Structure Underway 2018 108 15,000 Not provided Not provided Not provided County wetland to maximize provided Springshed provided provided Rehabilitation retention time.

Page 136 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Small pumping station at Sunset Rd. and Hibiscus Lane Balmy Beach Dr. to Seminole Not Not Inside Not Not Not provided SC-58 Stormwater Pump pump discharges Other Planned TBD 400,000 Not provided Not provided Not provided County provided provided Springshed provided provided Station through drainage system into existing treatment pond. Improved treatment process that results in Sanlando Wekiva WWTF increased reliability Not Not Inside Not Sanlando Utilities Not provided SUC-02 Reclaimed Water Underway 2018 N/A $1,837,324 N/A N/A Rehabilitation and consistency in provided provided Springshed provided Utilities Corp. producing reuse quality effluent. Improved treatment process that results in Sanlando Wekiva Filter Media increased reliability Not Not Inside Not Sanlando Utilities Not provided SUC-03 Reclaimed Water Completed 2016 N/A $85,747 N/A N/A Replacement and consistency in provided provided Springshed provided Utilities Corp. producing reuse quality effluent. Shadow Hills WWTF is in secondary zone of Wekiva Protection Area, uses perolation ponds for disposal. Sanlando Shadow Hills Project will divert all Not Not Inside Not Sanlando Utilities Not provided SUC-04 Reclaimed Water Underway 2018 N/A $7,781,739 N/A N/A WWTF Diversion plant flow to Wekiva provided provided Springshed provided Utilities Corp. Hunt Club, treated to reuse standards, and thus reduce nutrient load on surficial aquifer. Roadway; 3 in treated Turnpike Widen Turnpike, Online Retention Inside Not provided TP-01 in dry retention; Completed 2016 62 53 223 $82,632,000 $41,855 Not provided Not provided Not provided Enterprise Beulah to SR 50 BMP Springshed recovered in 72 hrs. Roadway; 1.25 in Turnpike Widen Turnpike, treated in dry Online Retention Inside Not provided TP-02 Completed 2016 158 151 279 $55,248,000 $37,628 Not provided Not provided Not provided Enterprise Gotha to Beulah retention, recovered in BMP Springshed 72 hrs No fertilizer on rights- Turnpike of-way; educational Not Not Inside N/A TP-04 Education Efforts Fertilizer Cessation Completed N/A N/A N/A N/A N/A N/A N/A Enterprise signage; illicit provided provided Springshed discharge training Street sweeping mile Turnpike Inside Not Not N/A TP-05 Street Sweeping post (MP) (265-274) Street Sweeping Completed N/A TBD 70 Not provided Not provided Not provided N/A Enterprise Springshed provided provided 600 lane mi/yr. City purchased 208 ac City of of agricultural land to Not Inside Winter Not provided WG-01 Tucker Ranch Land Use Change Completed 2016 302 208 $2,100,000 N/A N/A N/A N/A convert to primitive provided Springshed Garden campground/park.

Page 137 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Project is part of permitting process for new city hall in Winter City of Dillard Street Pond Garden; modify storm Stormwater BMP Not Inside Not Not Winter Not provided WG-02 Completed 2009 41 Not provided Not provided Not provided Not provided Expansion sewer system adjacent Retrofit/Expansion provided Springshed provided provided Garden to pond to treat previously untreated runoff. Project involves widening Plant St., including blowing out City of intersection of West Stormwater BMP Not Inside Not Not Winter Not provided WG-03 Plant St. Segment 1 Crown Point Rd. in Completed 2016 38 Not provided Not provided Not provided Not provided Retrofit/Expansion provided Springshed provided provided Garden Winter Garden; no stormwater treatment for this section of road prior to widening. Streets are swept weekly; total swept = 12,266 mi/yr. Catch City of basins vacuumed Inside Not Winter Not provided WG-04 Street Sweeping quarterly. Total Street Sweeping Completed N/A 202 838 14,868 Not provided Not provided Not provided N/A Springshed provided Garden material collected was 1,772,000 lbs split between sweeping and BMP clean outs. Replace city utilities because of widening of Sanitary Sewer City of SR 50; project Collection System SR 50 Utility Not Not Inside Not Winter Not provided WG-05 includes replacement Rehabilitation, Completed 2012 N/A Not provided Not provided Not provided Not provided Relocation provided provided Springshed provided Garden of 5,210 LF of 24-in Maintenance, or clay pipe and 2,650 LF Replacement of 18-in clay pipe. Berming of 2 direct- discharge canals to DEP – $750,000 City of Stormwater Capture SJRWMD/ Lake Apopka and treat Inside Not City/ DEP/ SJRWMD – Winter WG-06 and Reuse and Stormwater Reuse Completed 2018 TBD 2,794 980.0 $3,360,000 28432 DEP stormwater to reuse Springshed provided SJRWMD $750,000 Garden Recharge standards to be put into City – $1,860,000 distribution system. Previous land use = agriculture; Management focus = Wekiwa groundwater recharge, Prior to Not Not Inside Not provided WSP-01 Pine Plantation Land Use Change Completed 345 Not provided N/A N/A Inside Springshed N/A State Park natural community 2015 provided provided Springshed restoration and preservation; ac = 344.73. Remove Wekiva Wekiwa Not Not Inside Not Not provided WSP-02 State Park from Four-phase plan. Septic Phase Out Underway TBD N/A $1,616,775 Not provided Not provided Not provided State Park provided provided Springshed provided Septic

Page 138 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Achieved by WWTF Wastewater WWTF Policy policy if implemented WWTF Policy Inside TBD WU-01 Planned TBD 54,754 N/A N/A TBD TBD TBD TBD N/A Utilities Reductions BMAP-wide, Reductions Springshed achieving 3 or 6 mg/L. Orange Not Not Not provided OC-44 Kathleen Dr. Erosion control. Erosion Control Underway 2018 TBD TBD 1,000 $514,000 County Not provided Not provided County provided provided Redevelop commercial site and expand City of Private Cracker Barrel existing exfiltration Outside Altamonte N/A AS-06 Exfiltration Trench Completed 2002 1 0 2 N/A N/A Development N/A N/A Development system, raising level of Springshed Springs – unknown treatment to current city standards. Construct 92-room Fairfield Suites Hotel to replace commercial development City of constructed prior to Private Fairfield Marriot Outside Altamonte N/A AS-07 stormwater Stormwater BMP Completed 2000 4 1 3 N/A N/A Development N/A N/A Suites Development Springshed Springs development rules, – unknown raising level of water quality treatment onsite to meet city standards. Proposed development is for construction of 6,000 square-ft worship center, City of Private Florida Hospital associated paved Outside Altamonte N/A AS-08 Stormwater BMP Completed 2005 12 1 31 N/A N/A Development N/A N/A Development parking, and upgrades Springshed Springs – unknown to existing stormwater management system to replace existing parking lot. Redevelop 1.46-ac commercial site and City of Maitland Ave. expand existing Private Outside Altamonte N/A AS-10 Walgreens exfiltration system, Exfiltration Trench Completed 2002 6 1 1 N/A N/A Development N/A N/A Springshed Springs Development raising level of – unknown treatment to current city standards. Demolish and remove existing impervious area for construction of new 4,479-square-ft City of Private Panera Bread (SR restaurant; replace Outside Altamonte N/A AS-11 Stormwater BMP Completed 2007 1 0 1 N/A N/A Development N/A N/A 434) Development existing commercial Springshed Springs – unknown building and residential areas; raise level of treatment to meet city standards.

Page 139 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number City of River Run South Enlarge existing Online Retention Outside Stormwater Altamonte N/A AS-12 Pond 23 Completed 2004 2 1 4 $100,000 $1,000 100,000 N/A retention pond. BMP Springshed Utility Fund Springs Improvement Project Street sweeping occurs City of daily; total swept = Outside $480,000 Stormwater $480,000 Altamonte N/A AS-15a Street Sweeping 5,000 mi/yr – Split Street Sweeping Completed N/A 3,413 4,440 245 $100,000 N/A Springshed ($240,000/sweeper) Utility Fund ($240,000/sweeper) Springs between springshed and surface. Conservation project – Restore 20 ac of Stormwater City of Wekiva GeoPark wetlands in Wekiva Wetland Outside Utility Altamonte N/A AS-18 Completed 2000 N/A N/A N/A $387,500 N/A 387,500 N/A Restoration Project Basin GeoPark; Restoration Springshed Fund/Capital Springs includes removal of Projects logging roads. Remove 5 septic systems within 200 City of Adventist Health Private meters of receiving Outside Altamonte N/A AS-19 System Headquarters Septic Phase Out Completed 2011 72 13 N/A N/A N/A Development N/A N/A waterbody by Springshed Springs Development – unknown connecting them to city sanitary system. Remove 7 septic Spring St., Central systems within 200 City of Private St., Marker St., and meters of receiving Outside Altamonte N/A AS-20 Septic Phase Out Completed 2011 101 18 N/A N/A N/A Development N/A N/A Campello St. Septic waterbody by Springshed Springs – unknown System Removal connecting them to city sanitary system. Remove 1 septic system within 200 City of 640 Jasmine Ave. Private meters of receiving Outside Altamonte N/A AS-21 Septic System Septic Phase Out Completed 2011 15 3 N/A N/A N/A Development N/A N/A waterbody by Springshed Springs Removal – unknown connecting it to city sanitary system.

Storage and DEP-permitted storage City of Retrieval of and retrieval of Outside Altamonte N/A AS-22 Reclaimed Water Completed 2002 3,827 1,481 N/A $152,284 N/A N/A N/A N/A Reclaimed Water in reclaimed water in Springshed Springs Cranes Roost RSF Cranes Roost in 2002.

Central Parkway Sanitary Sewer City of Force Main Collection System Public Works Replace 1,230 LF of Outside Altamonte N/A AS-24 Replacement from Rehabilitation, Completed 2007 5 4 N/A $245,133 N/A Capital Project 245,133 N/A failing 8-in force main. Springshed Springs Lift Station 54 to Maintenance, or Fund Montgomery Rd. Replacement Retention for area City of along Bates Ave. Online Retention Not Not Outside Not Not Not provided E-01 Cardinal Pond Completed 2015 $300,000 Not provided Not provided Not provided Eustis between Glover St. BMP provided provided Springshed provided provided and Wall St.

Page 140 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Wet detention for downtown area; 32.4- ac drainage basin; project will provide City of Downtown Master Wet Detention Not Not Outside Not Not Not provided E-02 pollutant reduction of Completed 2015 $4,000,000 Not provided Not provided Not provided Eustis Stormwater Project Pond provided provided Springshed provided provided 64.5 % TN and 40 % TP; small eastern portion of new lines falls in springshed. Eastern WWTP is currently being City and City of Eastern WWTP Not Not Outside Not SJRWMD E-03 upgraded to 1.3 mgd to WWTF Upgrade Underway TBD 767.0 $7,500,000 SJRWMD Not provided Not provided Eustis Expansion provided provided Springshed provided serve new Funded developments in area. Eustis code sec. 115-5. Eustis stormwater Regulations, City of Stormwater Design rules for new Not Not Outside Not provided E-04 Ordinances, and Completed N/A N/A N/A N/A N/A N/A N/A Eustis Rules development are more provided provided Springshed Guidelines stringent than state or SJRWMD rules. SR 44: Swales and ditch blocks providing Grass Swales with FDOT FDOT- FM: 238406 (1 treatment for runoff Outside Not Not Florida N/A Swale Blocks or Completed 2002 15 2 Not provided Not provided N/A District 5 01 treatment project) generated from Springshed provided provided Legislature Raised Culverts existing and proposed pavement. SR 423: Add lanes from Shader Rd. to SR FM: 239496-2 424 (Edgewater Dr.). FDOT FDOT- Wet Detention Outside Not Florida N/A (2 Treatment Wet Detention Pond Completed 2016 156 17 20 Not provided Not provided N/A District 5 03 Pond Springshed provided Legislature Projects) 100 and Pond 200 providing treatment for JYP. SR 423: Add lanes from Shader Rd. to SR FM: 239496-2 FDOT FDOT- 424 (Edgewater Dr.). Wet Detention Outside Not Florida N/A (2 Treatment Completed 2016 N/A N/A 20 Not provided Not provided N/A District 5 03b Wet Detention Pond Pond Springshed provided Legislature Projects) Pond 200 providing treatment for JYP. Add lanes to SR 434: from SR 414, Lotus Landing Blvd., then to FM: 240231-2 SR 436: Dry Detention (7 Treatment Pond 1N-1, 1N-2 2N, FDOT FDOT- Stormwater BMP Outside Not Not Florida N/A Projects) Dry P, Wet Detention Completed 2008 60 7 Not provided Not provided N/A District 5 04 Retrofit/Expansion Springshed provided provided Legislature Detention Pond IN- WTC Ponds 1 and 2; 1/ Pond IN-2 Exfiltration System 4N-1 and 5N providing treatment for runoff generated from

Page 141 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number existing and proposed pavement.

Add lanes to SR 434: from SR 414, Lotus Landing Blvd., then to SR 436: Dry Detention Pond 1N-1, 1N-2 2N, FM: 240231-2 P, Wet Detention FDOT FDOT- (Seven Treatment Stormwater BMP Outside Not Not Florida N/A WTC Ponds 1 and 2; Completed 2008 N/A N/A Not provided Not provided N/A District 5 04b Projects) Wet Retrofit/Expansion Springshed provided provided Legislature Exfiltration System Detention Pond 2N 4N-1 and 5N providing treatment for runoff generated from existing and proposed pavement. Add lanes to SR 434: from SR 414, Lotus Landing Blvd., then to SR 436: Dry Detention Pond 1N-1, 1N-2 2N, FM: 240231-2 P, Wet Detention FDOT FDOT- (Seven Treatment Stormwater BMP Outside Not Not Florida N/A WTC Ponds 1 and 2; Completed 2008 N/A N/A Not provided Not provided N/A District 5 04c Projects) Exfiltration Retrofit/Expansion Springshed provided provided Legislature Exfiltration System System 4N-1 and 5N providing treatment for runoff generated from existing and proposed pavement. Add lanes to SR 434: from SR 414, Lotus Landing Blvd., then to SR 436: Dry Detention Pond 1N-1, 1N-2 2N, FM: 240231-2 P, Wet Detention FDOT FDOT- (Seven Treatment Stormwater BMP Outside Not Not Florida N/A WTC Ponds 1 and 2; Completed 2008 N/A N/A Not provided Not provided N/A District 5 04d Projects) WTC Pond Retrofit/Expansion Springshed provided provided Legislature Exfiltration System 1/ WTC Pond 2 4N-1 and 5N providing treatment for runoff generated from existing and proposed pavement. FDOT FDOT- FM: 238314-1 (Dry SR 500: Dry Retention Online Retention Outside Not Not Florida N/A Completed 2008 218 20 Not provided Not provided N/A District 5 05 Retention Pond 2) Ponds 2, 4, 6; Wet BMP Springshed provided provided Legislature

Page 142 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Detention Ponds 3E, 5 A/B; Ponds 3B, 3C, 3D; French drain providing treatment for runoff generated from existing and proposed pavement. SR 500: Dry Retention Ponds 2, 4, 6; Wet Detention Ponds 3E, 5 A/B; Ponds 3B, 3C, FDOT FDOT- FM: 238314-1 (Wet Online Retention Outside Not Not Florida N/A 3D; French drain Completed 2008 N/A N/A Not provided Not provided N/A District 5 05b Detention Pond 3E) BMP Springshed provided provided Legislature providing treatment for runoff generated from existing and proposed pavement. SR 500: Dry Retention Ponds 2, 4, 6; Wet Detention Ponds 3E, 5 A/B; Ponds 3B, 3C, FDOT FDOT- FM: 238314-1 (Dry Online Retention Outside Not Not Florida N/A 3D; French drain Completed 2008 N/A N/A Not provided Not provided N/A District 5 05c Retention Pond 4) BMP Springshed provided provided Legislature providing treatment for runoff generated from existing and proposed pavement. SR 500: Dry Retention Ponds 2, 4, 6; Wet Detention Ponds 3E, 5 FM: 238314-1 (Wet A/B; Ponds 3B, 3C, FDOT FDOT- Online Retention Outside Not Not Florida N/A Detention Pond 3D; French drain Completed 2008 N/A N/A Not provided Not provided N/A District 5 05d BMP Springshed provided provided Legislature 5a/5b) providing treatment for runoff generated from existing and proposed pavement. SR 500: Dry Retention Ponds 2, 4, 6; Wet Detention Ponds 3E, 5 A/B; Ponds 3B, 3C, FDOT FDOT- FM: 238314-1 (Dry Online Retention Outside Not Not Florida N/A 3D; French drain Completed 2008 N/A N/A Not provided Not provided N/A District 5 05e Retention Pond 6) BMP Springshed provided provided Legislature providing treatment for runoff generated from existing and proposed pavement. SR 500: Dry Retention Ponds 2, 4, 6; Wet FM: 238314-1 Detention Ponds 3E, 5 FDOT FDOT- Online Retention Outside Not Not Florida N/A (Frenth Drain A/B; Ponds 3B, 3C, Completed 2008 N/A N/A Not provided Not provided N/A District 5 05f BMP Springshed provided provided Legislature System) 3D; French drain providing treatment for runoff generated from

Page 143 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number existing and proposed pavement.

SR 50: Add lanes from east ramps of Turnpike to Avalon Rd.; Wet FDOT FDOT- Detention Ponds A and Wet Detention Outside Not Florida N/A FM: 239535-2 Completed 2016 391 42 62.9 Not provided Not provided N/A District 5 06 B providing treatment Pond Springshed provided Legislature for runoff from existing and proposed pavement. SR 50: Add lanes from east ramps of Turnpike to Avalon Rd.; Wet FDOT FDOT- Detention Ponds A and Wet Detention Outside Not Florida N/A FM: 239535-2 Completed 2016 N/A N/A 62.9 Not provided Not provided N/A District 5 06b B providing treatment Pond Springshed provided Legislature for runoff from existing and proposed pavement. Street sweeping occurs FDOT FDOT- Outside Not Florida Not provided Street Sweeping monthly; total swept = Street Sweeping Completed N/A 28 18 N/A Not provided Not provided N/A District 5 08 Springshed provided Legislature 2,247 mi/yr. Reduction of bulk FDOT FDOT- Outside Not provided Fertilizer Cessation fertilizer use on state Fertilizer Cessation Completed N/A 1,098 0 N/A N/A N/A N/A N/A N/A District 5 09 Springshed roadways in basin. 60 ac of mature sand pine scrub community with wetlands in Northeast Lake Lake southeast; adjacent to Outside Not provided LC-01 County Scrub Land Acquisition Completed 2008 N/A N/A 60 $950,000 N/A Not provided Not provided N/A County ; Springshed Preserve protection of land; no change in land use; thus no load reduction. 136 ac of remnant Lake citrus, xeric oak Outside Not provided LC-02 Lake May Reserve Land Acquisition Completed 2008 N/A N/A 136 $6,200,000 N/A Not provided Not provided N/A County hammock and 20- ac Springshed Lake May. Property consists of 184 ac of lake bottom Lake Outside Not provided LC-03 Mt. Plymouth Lakes and associated uplands Land Acquisition Completed 2007 N/A N/A 184 Not provided N/A Not provided Not provided N/A County Springshed in plat of Mt. Plymouth.

Page 144 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Part of multiagency acquisition (DEP, SJRWMD, OOCEA, and Lake and Orange Lake Outside Not provided LC-04 Neighborhood Lakes Counties) totaling Land Acquisition Completed 2007 N/A N/A 1,584 $5,000,000 N/A Not provided Not provided N/A County Springshed 1,584 ac; Lake County partnered with SJRWMD to purchase 210 ac. Reserve consists of 2 adjoining properties totaling 128 ac, Lake South Pine Lakes consisting of scrub, Outside Not provided LC-05 Land Acquisition Completed 2008 N/A N/A 128 $985,250 N/A Not provided Not provided N/A County Reserve scrubby flatwoods, Springshed herbaceous marsh; bear habitat, possible sandhill crane nesting. Project goals are to provide teacher workshops and educational outreach to Grades K-12, provide exposure to various environmental careers to middle/high school students, increase number of volunteer water quality sample sites, and create Lake Sumter community project State College; North Lake County showcase site using Umatilla Community Lake native shoreline Public Education Outside Not Chamber of LC-06 Environmental Completed N/A N/A N/A N/A $30,868 Not provided Not provided Not provided County vegetation; project Efforts Springshed provided Commerce, Stewardship partners include City Lake County Program of Umatilla, Umatilla Schools Chamber of Commerce, Lake- Sumter Community College, Florida Lake Management Society, North Lake Newspaper, Altoona Charter School, Umatilla Elementary School, Umatilla High School, and private citizens.

Page 145 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Project includes removing concrete flumes in right-of-way Lake County and piping area to 2 Water new dry retention Authority ponds; what cannot be Lake County – Lake (LCWA) – Wolfbranch Outside Lake County/ LC-07 treated in ponds will Stormwater BMPs Completed 2016 66 9 13.5 $1,530,000 $2,200 $1,300,000 Not provided County $200,000 Drainage Retrofit Springshed LCWA be captured in CDS LCWA – $200,000 construction unit in right-of-way, reimbursement and compensating grant treatment for this area will be treated in Pond B. Nutrient load reductions for 25 mi of Grass Swales with Lake Dirt Roadway road segments that Outside Not Not Not provided LC-08 Swale Blocks or Completed 2011 223 122 Not provided Not provided Not provided Not provided County Paving were paved and Springshed provided provided Raised Culverts improved with ditch blocks. Flood analysis, Royal Trails pollutant loading Lake Drainage and Water Outside Not Not provided LC-09 model, and conceptual Study Completed 2010 N/A N/A N/A $394,101 Not provided Not provided N/A County Quality Springshed provided project priorities are Improvements completed. Paving of dirt road and Lake County construction of Grass Swales with Lake Firethorn Dirt Rd. Outside Not Special Lake County LC-10 roadside swales for Swale Blocks or Completed 2016 10 2 3.0 $238,000 Not provided Not provided County Paving and Drainage Springshed provided Assesment for drainage and Raised Culverts road paving treatment. Lake County staff has become certified to instruct on DEP Sedimentation and DEP Nonpoint Erosion Control Lake Erosion Control Outside Not Source LC-11 Inspector's Erosion Control Underway TBD N/A N/A N/A Not provided Lake County Not provided Not provided County Inspector Training Springshed provided Program certification program. County hosts annual class and exam free to local contractors and municipal employees. Removal of sediments Lake Pipe and Catch Basin and nutrients from Outside Not N/A LC-12 BMP Clean Out Completed 2017 82 50 N/A $6,500 Lake County Not provided N/A County Cleaning roadside catch basins Springshed provided and stormwater pipes. Streets are swept twice a month; roadway City of Outside Not Not Not provided M-01 Street Sweeping length swept = 23.86 Street Sweeping Completed N/A 4 15 Not provided Not provided Not provided N/A Maitland Springshed provided provided mi/ 2 wks; total swept = 572.64 mi/yr.

Page 146 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Install 3 36-in City of Mt. 5th and McDonald diameter exfiltration Prior to Not Not Outside Not Not Not provided MD-01 Exfiltration Trench Completed Not provided Not provided Not provided Not provided Dora Parking Lot pipes under new 2015 provided provided Springshed provided provided parking lot. Install StormTech Hwy. 441 and Hwy. system – 100 LF inline City of Mt. Prior to Not Not Outside Not Not Not provided MD-02 46 StormTech arrangement with Exfiltration Trench Completed Not provided Not provided Not provided Not provided Dora 2015 provided provided Springshed provided provided Installation "isolator rows" at each end for maintenance. Install StormTech system: 2 50-LF rows St. Johns St. with "isolator rows" City of Mt. Prior to Not Not Outside Not Not Not provided MD-03 StormTech for maintenance; Exfiltration Trench Completed $18,000 Not provided Not provided Not provided Dora 2015 provided provided Springshed provided provided Installation regraded and paved road to improve drainage. Install Suntree NSBB at 5th Ave. and 5th Ave. and City of Mt. Rossiter discharge into Baffle Boxes – Prior to Outside Not Not Not provided MD-04 Rossiter NSBB Completed 64 26 Not provided Not provided Not provided Not provided Dora Lake Franklin, which 2nd Generation 2015 Springshed provided provided Installation is isolated spring-fed lake. Reline existing corrugated metal pipe (CMP) with high- City of Mt. 1552 Hilltop Dr. density polyethylene Prior to Not Not Outside Not Not provided MD-05 Erosion Control Completed N/A $13,000 Not provided Not provided Not provided Dora Pipe Relining (HDPE) to eliminate 2015 provided provided Springshed provided sinkhole formation and erosion into Lake Nettie. Remove accumulated sediment and debris 5th Ave. and from retention pond; City of Mt. McDonald St. install new inlet pipe Prior to Not Not Outside Not Not provided MD-06 BMP Clean Out Completed N/A $3,000 Not provided Not provided N/A Dora Retention Pond to prevent erosion; 2015 provided provided Springshed provided Restoration replace erosion protection around inlet pipes. Headwall broke away from pipe; water Donnelly St. and City of Mt. undermining Donnelly Stormwater System Prior to Not Not Outside Not Not provided MD-07 Lincoln Ave. Pipe Completed N/A $35,000 Not provided Not provided Not provided Dora St.; installed drop Rehabilitation 2015 provided provided Springshed provided Repair structure and extend pipeline 140 LF. Replace crushed section of 36x54 CMP City of Mt. Pine and Jackson Stormwater System Prior to Not Not Outside Not Not provided MD-08 to allow proper Completed N/A $3,000 Not provided Not provided Not provided Dora Pipe Repair Rehabilitation 2015 provided provided Springshed provided drainage of northeast area of city.

Page 147 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Streets are swept 15 times/yr; length of City of Mt. Outside Not Not Not provided MD-09 Street Sweeping streets swept = 69 mi; Street Sweeping Completed N/A 1,304 2,033 Not provided Not provided Not provided N/A Dora Springshed provided provided total swept = 1,035 mi/yr. Lake John is part of greater Lake Gertrude Basin project; wetland was excavated to remove excess City of Mt. Lake John Wetland Prior to Not Not Outside Not Not provided MD-10 sediment and exotic Completed N/A $1,200,000 Not provided Not provided Not provided Dora Rehabilitation Restoration 2015 provided provided Springshed provided vegetation; stepwise drainage reestablished between 3 ponds, and new vegetation planted. Extend 8-in sewer main and install 4 laterals to connect 4 City of Mt. Prior to Not Not Outside Not Not provided MD-11 CBDG duplexes to city sewer Septic Phase Out Completed N/A $63,000 Not provided Not provided Not provided Dora 2015 provided provided Springshed provided on 11th Ave.; abandon existing septic systems. Sanitary Sewer Lift Station #10 Replace 602 ft of Collection System City of Mt. Prior to Not Not Outside Not Not provided MD-12 Piping Replacement 8-in pipe and 2 Rehabilitation, Completed N/A Not provided Not provided Not provided Not provided Dora 2015 provided provided Springshed provided (Pine Ave.) manholes. Maintenance, or Replacement 2007 – Line 7,094 ft of 8-in sewer main on Clayton and Liberty Sts. 2008 – Line 8,040 ft of 8- and 10-in sewer main (Grandview, Sanitary Sewer Pipe Lining 2007, Alexander, Tremain, Collection System City of Mt. Prior to Not Not Outside Not Not provided MD-13 2008, 2009, and Baker, Lake Dora Rd, Rehabilitation, Completed N/A $705,907 Not provided Not provided Not provided Dora 2015 provided provided Springshed provided 2010 Pine Ave., and Maintenance, or Donnelly St.). 2009 – Replacement Line 3,746 ft of 8-in pipe on Old Eustis Rd. and Donnelly St. 2010 – Line 1,500 ft of 21- in pipe along Lake John. Lift Stations #1, 2, 3, 7, 9, 10, 11, 12, 13, City of Mt. Sanitary Sewer Prior to Outside Not Not provided MD-14 14, 15, 16, 17, 20, Clean and inspect pipe. Completed N/A N/A N/A $21,000 Not provided Not provided Not provided Dora Inspections 2015 Springshed provided 22, 25, 27, 28, 30, 31, and 34 Piping

Page 148 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Install concrete storm pipe as follows: 753 ft of 36 in, 466 ft of 30 City of Mt. LCWA/ DEP Outside Not DEP/ LCWA/ MD-15 7th Ave. Stormwater in, 1,431 ft of 24 in, STAs Completed 2015 125 20 34 $1,500,000 $1,470,651 S0649 Dora TMDL Springshed provided City 425 ft of 18 in and stormwater treatment system. Expand size of 0.8-ac existing treatment Orange Stormwater BMP Prior to Not Outside Not Not Not provided OC-17 Riverside Pond pond to 1.6 ac and add Completed 4,533 $766,918 Not provided Not provided Not provided County Retrofit/Expansion 2015 provided Springshed provided provided aeration to address DO impairment. Provide treatment for 2 drainage basins Bay Lake Advanced Orange totaling 91.7 ac Prior to Outside Not Not Not provided OC-18 Stormwater Engineered Completed 14 1 $260,000 Not provided Not provided Not provided County (Modular Wetlands 2015 Springshed provided provided Improvement Project Wetland with Bold and Gold™ media). Online wet detention Orange Lake Lawne with irrigation system Outside Not Not provided OC-19 Stormwater Reuse Underway 2018 721 229 650 $2,500,000 Not provided Not provided Not provided County Stormwater for reuse on adjacent Springshed provided sports fields. Install (2016) 49 curb/grate inlet baskets Orange Outside Not Not provided OC-20 Lake Weston CIBs on storm drains and Catch Basin Inserts Completed 2016 20 5 500 $160,000 Not provided Not provided Not provided County Springshed provided apply storm drain markers. North Lake Lawne Install 120 curb/grate Orange Stormwater inlet baskets on storm Outside Not Not Not provided OC-21 Catch Basin Inserts Completed 2016 46 13 $196,899 Not provided Not provided Not provided County Treatment Project drains and apply storm Springshed provided provided (C-7) drain markers. Streets are swept every Orange Prior to Outside Not Not Not provided OC-36a Street Sweeping 6 wks; 481,128 lbs/yr Street Sweeping Completed 21 13 Not provided Not provided Not provided N/A County 2015 Springshed provided provided of material removed. Study to evaluate Lake Lawne Orange hydrologic conditions Prior to Outside Not Not provided OC-38 Hydrologic and Study Completed N/A N/A N/A $120,000 Not provided Not provided N/A County and nutrient loadings 2015 Springshed provided Nutrient Study to Lake Lawne. Inspect annually all 233 commercial, single, and multifamily systems in basin for Compliance functionality; systems City/ Streets City of ORL- Inspections of include, but are not Stormwater BMP Outside Not and Not provided Completed 1989 N/A N/A N/A Not provided Not provided Not provided Orlando 01a Private Stormwater limited to, retention Inspections Springshed provided Stormwater Systems and detention ponds, Division underdrains, exfiltration, and underground vaults; by maintaining ponds at

Page 149 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number design criteria, city is ensuring optimal level of pollutant removal efficiency is being achieved. Conduct proactive inspections and perform routine maintenance on 13 City/ Streets ponds and 31 ditches City of ORL- Stormwater System Stormwater BMP Outside Not and Not provided in basin to ensure Completed 1970 N/A N/A N/A Not provided Not provided Not provided Orlando 02a Inspections Inspections Springshed provided Stormwater systems are being Division maintained at optimal pollutant removal efficiency (and flood prevention). Install (2006) 2 inlet City/ Streets baskets in Lake Daniel City of ORL- Two Inlet Baskets Outside Not and Not provided Basin; 1.89 cubic Catch Basin Inserts Completed N/A 0 3 N/A $1,500 Not provided Not provided Orlando 03a Around Lake Daniel Springshed provided Stormwater yds/yr of material Division collected. Capture gross pollutants and reduce levels of nitrogen City/ Streets entering basin by City of Three Baffle Boxes Baffle Boxes – Outside Not and Not provided ORL-05 removing leaves and Completed 2006 27 11 26 $7,800 Not provided Not provided Orlando on Ardsley 1st Generation Springshed provided Stormwater clippings before they Division enter Lake Silver; 13.25 cubic yds/yr of material collected. Install (2006) 3 inlet City/ Streets baskets in Lake Sarah City of Four Inlet Baskets Outside Not and Not provided ORL-06 Basin; 10.89 cubic Catch Basin Inserts Completed N/A 17 10 4 $2,250 Not provided Not provided Orlando Around Lake Sarah Springshed provided Stormwater yds/yr of material Division collected. Install (2004) 4 inlet City/ Streets City of Four Inlet Baskets baskets in Lake Silver Outside Not and Not provided ORL-07 Catch Basin Inserts Completed N/A 10 6 15 $3,000 Not provided Not provided Orlando Around Lake Silver Basin; 6.5 cubic yds/yr Springshed provided Stormwater of material collected. Division Lake Silver Install CDS unit to City/ Streets City of Treatment Structure capture gross Not Outside Not Not and Not provided ORL-08 CDS Unit Completed 2000 19 $565,702 Not provided Not provided Orlando (Westmoreland Dr. pollutants before they provided Springshed provided provided Stormwater CDS Unit) enter Lake Silver. Division

Page 150 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Expand 5 wet detention ponds and create 10 additional wet detention ponds in golf course; construct 15 ponds in series of 3 interconnected systems; all systems eventually discharge to DEP/ Little Lake Fairview adjacent wetland, City/ Streets SJRWMD/ Restoration and City of except during high Wet Detention Not Outside Not and FDOT/ ORL-09 Dubsdread Golf Completed 2008 265 422 $9,000,000 Not provided TBD Orlando flows, when runoff Pond provided Springshed provided Stormwater Diocese of Course Renovation discharges to drainwell Division Orlando Project or ditch routed to Little Lake Fairview; restores hydroperiod of wetland and improves wetland functions; also raises drainwell elevation to allow for more treatment before discharge. Install 20-ft pipe to City/ Streets capture debris in City of Outside Not Not and Not provided ORL-10 Palomar Exfiltration separate chamber Exfiltration Trench Completed 2006 6 3 $30,000 Not provided Not provided Orlando Springshed provided provided Stormwater before stormwater Division percolates into ground. City/ Streets Remove 300 cubic yds Muck Removal/ City of Sandbar Removal on Not Not Outside Not and Not provided ORL-11 of sediment from Lake Restoration Completed 2006 N/A $20,000 Not provided Not provided Orlando Lake Sarah provided provided Springshed provided Stormwater Sarah. Dredging Division Streets are swept every City/ Streets City of ORL- 2 wks; 5,023.2 cubic Outside Not Not and Not provided Street Sweeping Street Sweeping Completed N/A 6,312 4,048 Not provided Not provided N/A Orlando 12a yds/yr of material Springshed provided provided Stormwater collected. Division Little Wekiva River Nutrient reduction – Preliminary projects in Little City of Engineering Wekiva River Orlando/ City of Outside Not provided ORL-13 Evaluation Lake Watershed, using Study Completed 2008 N/A N/A N/A $49,900 N/A Streets and Not provided N/A Orlando Springshed Lawne, Center of suggested drainage Stormwater Commerce, and Lake improvements from Division Orlando Sites CDM report. Install 1,200 ft of City of gravity lines in area Orlando/ City of Arthur Ave. Sewer with septic tanks to Wastewater Service Not Not Outside Not Not provided ORL-14 Completed 1998 N/A $53,977 Water Not provided Not provided Orlando Line reduce nutrient Area Expansion provided provided Springshed provided Reclamation seepage into Division groundwater table.

Page 151 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Install sanitary sewer in area with septic City/ Water City of Wastewater Service Not Not Outside Not Not provided ORL-16 Lynx Facility tanks to reduce Completed 2007 N/A Not provided Reclamation Not provided Not provided Orlando Area Expansion provided provided Springshed provided nutrient seepage into Division groundwater table. Install gravity lines in area with septic tanks City/ Water City of Rio Grande Sanitary Wastewater Service Not Not Outside Not Not provided ORL-17 to reduce nutrient Completed 2000 N/A $1,622,124 Reclamation Not provided Not provided Orlando Sewer Area Expansion provided provided Springshed provided seepage into Division groundwater table. Install sanitary sewer in area with septic City/ Water City of West Lake Fairview Wastewater Service Prior to Not Not Outside Not Not provided ORL-18 tanks to reduce Planned N/A N/A Reclamation Not provided Not provided Orlando Sanitary Sewer Area Expansion 2015 provided provided Springshed provided nutrient seepage into Division groundwater table. Lift station is one of oldest in city; wet well is made of brick and starting to fail; replace lift station with precast Sanitary Sewer concrete with liner and Collection System City/ Water City of Lift Station #37 Not Not Outside Not Not provided ORL-19 bigger capacity; install Rehabilitation, Completed 2009 N/A $1,400,000 Reclamation Not provided Not provided Orlando Improvements provided provided Springshed provided new pumping station Maintenance, or Division and associated Replacement components, along with standby generator; also replace gravity pipes in area. Line sewers to prevent untreated sewage from Sanitary Sewer escaping through Collection System City/ Water City of West Lake Silver Prior to Not Not Outside Not Not provided ORL-22 cracks and joints; Rehabilitation, Completed N/A N/A Reclamation Not provided Not provided Orlando Phase I and II 2015 provided provided Springshed provided project will reduce Maintenance, or Division nutrient seepage into Replacement groundwater table. Sanitary Sewer Collection System City/ Water City of Mercy Dr. Sewer Install lift station in Not Not Outside Not Not provided ORL-23 Rehabilitation, Completed 2002 N/A $878,400 Reclamation Not provided Not provided Orlando Rehabilitation new commercial area. provided provided Springshed provided Maintenance, or Division Replacement Replace force main on Sanitary Sewer Mercy Dr. from south Collection System City/ Water City of Regent Ave. Force of Princeton to Lift Not Not Outside Not Not provided ORL-24 Rehabilitation, Completed 2010 N/A $2,000,000 Reclamation Not provided Not provided Orlando Main 2613 Station #45; connect or provided provided Springshed provided Maintenance, or Division replace new sanitary Replacement pipe to existing pipes.

Page 152 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Conduct proactive inspections and perform routine maintenance on lift stations and sanitary lines; identify problem Sanitary Sewer areas and increase Collection System City/ Water City of Sanitary System maintenance frequency Not Not Outside Not Not provided ORL-25 Rehabilitation, Completed N/A N/A Not provided Reclamation Not provided Not provided Orlando Inspections or perform repairs to provided provided Springshed provided Maintenance, or Division prevent overflows Replacement from occurring; also assist with Sunshine State One-Call of Florida ("Call Before You Dig"/Line Locater). City/ Water City of Lift Station #45 Not Not Outside Not N/A ORL-26 Replace lift station. WWTF Upgrade Planned 2020 N/A 6,000,000 Reclamation 6,000,000 N/A Orlando Improvements provided provided Springshed provided Division Maintenance of sanitary line will WWTF and City/ Water City of Mercy Dr. Sewer prevent SSOs from Not Not Outside Not N/A ORL-27 Sanitary Sewer Underway 2018 N/A 300,000 Reclamation 300,000 N/A Orlando Cleaning occurring in basin that provided provided Springshed provided Maintenance Division negatively impact water quality in lake. Lift station City/ Water City of Lift Station 8, 30, 47, replacement (only #47 Not Not Outside Not N/A ORL-29 WWTF Upgrade Planned 2019 N/A 1,500,000 Reclamation 1,500,000 N/A Orlando and 77 Replacements and #77 in Wekiva provided provided Springshed provided Division Basin). Partner with Edgewater High Baffle Boxes – City City of Orange County School (EHS) to Outside Not ORL-31 Lake Silver Shores 2nd-Generation Planned 2020 24.3 3 20 800,000 Stormwater 800,000 N/A Orlando Public Schools design and create joint Springshed provided with Media Utility wet pond on EHS property. Upgrade 3 existing 1st-generation baffle Baffle Boxes – City City of Ardsley Baffle Box Outside Not N/A ORL-32 boxes to 2nd- 2nd-Generation Planned 2019 191.2 28 42 450,000 Stormwater 450,000 N/A Orlando Retrofits Springshed provided generation baffle with Media Utility boxes with media` Reduce sediment loads through bank Little Wekiva Grade stabilization and Seminole Control – construction of 2 river Shoreline Outside Not Not provided SC-06 Completed 2011 298 31 N/A $850,000 Not provided Not provided Not provided County Montgomery Rd. to grade control Stabilization Springshed provided SR 434 structures in Little Wekiva River; area served = >5,000 ac.

Page 153 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Reduce sediment loads Wekiva Park Dr. Seminole through grade control Shoreline Outside Not Not provided SC-07 Erosion Control Completed 2010 37 4 N/A $350,000 Not provided Not provided Not provided County structures; area served Stabilization Springshed provided Project = 400 ac. Exotics removal/ revegetation with native species. Seminole Exotic Vegetation Not Not Outside Not Not provided SC-08 Lake Mobile Accomplished using Completed 2009 N/A $25,000 Not provided Not provided Not provided County Removal provided provided Springshed provided in-house staff, residents, and volunteers. Exotics removal/ revegetation with native species. Seminole LWR @ Springs Exotic Vegetation Not Not Outside Not Not provided SC-09 Accomplished using Completed 2010 N/A $10,000 Not provided Not provided Not provided County Landing Bridge Removal provided provided Springshed provided in-house staff, residents, and volunteers. Exotics removal/ revegetation with native species. Seminole Exotic Vegetation Not Not Outside Not Not provided SC-11 Spring Lake Accomplished using Completed 2009 N/A $75,000 Not provided Not provided Not provided County Removal provided provided Springshed provided in-house staff, residents, and volunteers. Previous land use = natural land; Seminole Black Bear management focus = Outside Not provided SC-12 Land Acquisition Underway 2015 N/A N/A 1,650 Not provided N/A Not provided Not provided N/A County Wilderness Area preservation, passive Springshed recreation; ac = 1,650. Previous land use = Yankee Lake Scrub natural land; Seminole Prior to Outside Not provided SC-13 Jay Preservation management focus = Land Acquisition Completed N/A N/A 300 Not provided N/A Not provided Not provided N/A County 2015 Springshed Area preservation, passive recreation; ac = 300. Provide water quality treatment for Markham Woods additional traffic lane Seminole Rd. Widening from Outside Not Not Not provided SC-17 through construction Exfiltration Trench Completed 2003 32 4 $1,400,000 Not provided Not provided Not provided County SR 434 to Springs Springshed provided provided of new exfiltration Landing Blvd. trench; area served = 12.4 ac. Markham Woods Provide water quality Rd. Widening from treatment to existing Seminole Outside Not Not Not provided SC-18 Lane Springs roadway through Exfiltration Trench Completed 2006 46 8 $2,300,000 Not provided Not provided Not provided County Springshed provided provided Landing Blvd. to EE exfiltration trench; Williamson Rd. area served = 9.2 ac.

Page 154 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Pave dirt road and install 2nd-generation Seminole Palm Springs Rd. baffle box to provide Baffle Boxes – Outside Not Not Not provided SC-23 Completed 2003 1 0 $255,000 Not provided Not provided Not provided County Paving and Drainage water quality 2nd-Generation Springshed provided provided treatment; area served = 0.4 ac. Street sweeping in Big Seminole Outside Not Not Not provided SC-25a Street Sweeping Wekiva and Little Street Sweeping Completed N/A 410 264 Not provided Not provided Not provided N/A County Springshed provided provided Wekiva Basins. Detailed nutrient and hydrologic study, identifying and quantifying all nutrient sources, including Spring Lake/Spring internal loading, Lake Watershed groundwater, surface Seminole Hydrology/Nutrient Outside Not Not provided SC-27a water, precipitation, Study Underway TBD N/A N/A N/A Not provided Not provided Not provided N/A County Budget and Water Springshed provided etc.; management plan Quality Management includes potential Plan structural and nonstructural improvements that can be made to protect and enhance water quality. Countywide assessment of all water quality data, monitoring programs, regional ponds, CIP Seminole County Seminole projects, etc., to Outside Not Not provided SC-29a Water Quality Study Underway TBD N/A N/A N/A Not provided Not provided Not provided N/A County improve efficiency and Springshed provided Master Plan effectiveness of existing programs and identify additional structural/nonstructural improvement projects. Sanitary Sewer Collection System Seminole Apple Valley Lift Relocate and build Prior to Outside Not Not provided SC-30 Rehabilitation, Completed N/A N/A N/A $351,975 Not provided Not provided Not provided County Station brand new lift station. 2015 Springshed provided Maintenance, or Replacement Lateral repair – 1512 Cherry Rdg., 2067 North Umbria, 169 Sanitary Sewer Killarney Ct., Collection System Seminole Gravity Main Prior to Outside Not Not provided SC-32 Shadowmoss. Gravity Rehabilitation, Completed N/A N/A N/A $401,878 Not provided Not provided Not provided County Testing and Repairs 2015 Springshed provided main repair – 844 Maintenance, or Preserve Terr., Replacement International Dr. and CR 46A, Lake Rena

Page 155 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Dr. Smoke test and seal laterals – Alaqua Lakes, Heathrow Woods # 1 and 2 lift stations, Lake Forest 1 and 2, Lake Forest 1 and 2. Additional work – Lake Forest 3 and 4, Aster Farms. Seal wet well and rehabilitate lines at lift stations (Wilson School, Breckenridge, Sanitary Sewer Stockbridge, Lake Collection System Seminole Lift Station Prior to Outside Not Not provided SC-33 Forest #5, Rehabilitation, Completed N/A N/A N/A $324,353 Not provided Not provided Not provided County Rehabilitation 2015 Springshed provided Buckingham, Retreat Maintenance, or at Wekiva, Aster Replacement Farms, Bel-Aire #3, Bel-Aire #1, Heathrow Master). Pond retrofit with soil Seminole amendment aimed at Stormwater BMP Not Not Outside Not Not Not provided SC-34 Douglas Ave Pond Underway TBD $105,000 Not provided Not provided Not provided County reducing nitrate Retrofit/Expansion provided provided Springshed provided provided loading to groundwater Spring Lake Hills Construction retrofit Seminole Not Not Outside Not Not provided SC-36 Outfall Weir project, replace Control Structure Completed 2016 537 $4,500 Not provided Not provided Not provided County provided provided Springshed provided Rehabilitation existing failing weir Spring Lake Municipal Seminole Spring Lake Alum In-lake alum Not Not Outside Not Spring Lake Service SC-38 Alum Injection Underway TBD 85 $120,000 Not provided Not provided County Treatment treatment. provided provided Springshed provided MSBU Benefit Unit (MSBU) Planted native aquatic Spring Lake Seminole vegetation along Creating/Enhancing Not Not Outside Not Not provided SC-40 Shoreline Completed 2017 N/A Not provided Not provided Not provided Not provided County individual homeowner Living Shoreline provided provided Springshed provided Restoration shorelines. Planted native aquatic Spring Wood Lake Seminole vegetation along Creating/Enhancing Not Not Outside Not Not provided SC-41 Shoreline Completed 2017 N/A Not provided Not provided Not provided Not provided County individual homeowner Living Shoreline provided provided Springshed provided Restoration shorelines. Planted native aquatic Lake Destiny Canal Seminole vegetation along Creating/Enhancing Not Not Outside Not Not provided SC-42 Shoreline Completed 2017 N/A Not provided Not provided Not provided Not provided County individual homeowner Living Shoreline provided provided Springshed provided Restoration shorelines. Convey runoff into Wilson's Landing Seminole bioretention area prior Not Not Outside Not Not Not provided SC-49 Stormwater Bioretention Planned 2019 Not provided Not provided Not provided Not provided County to discharge into provided provided Springshed provided provided Bioretention Area Wekiva River.

Page 156 of 157 Florida Statewide Annual Report on Total Maximum Daily Loads, Basin Management Action Plans, Minimum Flows or Minimum Water Levels, and Recovery or Prevention Strategies, June 2018

DEP Estimated TN TP Cost Contract Lead Project Project Completion Reduction Reduction Acres Annual Funding Agreement Entity Partners Number Project Name Project Description Project Type Status Date (lbs/yr) (lbs/yr) Location Treated Cost Estimate O&M Source Funding Amount Number Sanitary Sewer Seal and coat 10 Apple Valley Collection System Seminole manholes; CIPP lining Not Not Outside Not Not Not provided SC-51 Subdivision Gravity Rehabilitation, Completed 2017 $108,000 Not provided Not provided Not provided County of 2,700 LF of 8-in provided provided Springshed provided provided Main Rehabilitation Maintenance, or gravity main. Replacement Camera-inspect Sanitary Sewer Sweetwater I&I sanitary collection Sanlando Collection System Investigation and system in Sweetbrier Prior to Outside Not Sanlando Utilities Not provided SUC-01 Rehabilitation, Completed N/A N/A N/A $1,553,000 N/A N/A Collection System Subdivision and 2015 Springshed provided Utilities Corp. Maintenance, or Repairs correct noted Replacement deficiencies. Five dry retention Turnpike Minneola Online Retention Not Not Outside Not Not N/A TP-03 ponds and 3 treatment Completed N/A $27,866,200 Not provided Not provided Not provided Enterprise Interchange BMP provided provided Springshed provided provided swales. No fertilizer on rights- Turnpike of-way, educational Not Not Outside N/A TP-04 Education Efforts Fertilizer Cessation Completed N/A N/A N/A N/A N/A N/A N/A Enterprise signage, illicit provided provided Springshed discharge training. Street sweeping MP Turnpike Outside Not Not N/A TP-05a Street Sweeping (265-274) 600 lane Street Sweeping Completed N/A 144 70 Not provided Not provided Not provided N/A Enterprise Springshed provided provided mi/yr.

Page 157 of 157