Application for Environmental Clearance Form – I (I) Basic Information: S. No. Item No. Details 1 Name of the Project/s “Curo North Square” at Village Mullanpur Garibdass, Distt. SAS Nagar (), Punjab by M/s. Curo Pvt. Ltd. 2 S. No. in the schedule The project falls under S.No. 8(a) - ‘Building & Construction Project’ as the built-up area of the project is 1,25,237 sq.m. 3 Proposed capacity / area / length/ M/s. Curo India Pvt. Ltd. is coming up with a new tonnage to be handled / command area / Group Housing Project in the name of “Curo lease area / number of wells to drilled North Square” at Village Mullanpur Garibdass, Distt. SAS Nagar (Mohali), Punjab. The total plot area of the project is 41,197 sq.m (10.18 acres). The Project (comprising of residential and commercial) falls under the approved Master Plan of New (Mullanpur) and it falls in Mixed Land Use Zone. Copy of Master Plan is enclosed as Drawing 1. The Project will consists of 5 Residential Towers, one tower for retail & service apartments and one commercial tower.

The total plot area of the project is 10.18 acres out of 0.467 acre has already aquired by GMADA for front road widening. Thus the change of land use has been granted by Deptt. of Town & Country Planning, Punjab vide Memo no. 4233- CTP(PB)SP-432(m) dated 03.09.2015. Copy of the Change of land use is enclosed as Annexure 1. The land documents are attached at Annexure 2. The total cost of project is Rs. 582.12 Crores. The area details are given in Conceptual Plan.

Till date, no construction has been done at site. Site photographs are enclosed as Annexure 3.

The following documents are enclosed: A-1: Change of Land use A-2: Land documents A-3: Photographs of the Project site. A-4: Resolution for Authorized Signatory A-5A: Copy of receipt of application filed for NBWL clearance along with opinion from CWW. A-5B: Undertaking reg. no litigation A-6: NOC from Forest Department A-7: PERT/CPM chart A-8A: Letter from CGWA for abstraction of Ground water A-8B: NOC from GMADA for water supply, disposal of treated sewage & solid waste A-9: Demographic details A-10A: Test Reports A-10B: Field data sheets A-10C: E-mail copy stating intimation for monitoring A-11: Energy saving calculations A-12: Affidavit as per SEAC A-13: Memorandum of association

The following drawings are enclosed: D-1: Master Plan of Mullanpur showing Project site D-2: Location Plan D-3: Panoramic View showing 500 mt. radius D-4: Approved Plan D-5: Marked Layout Plan D-6: Combined Services Plan D-7: Basement Parking cum Traffic Movement Plan D-8: Contour/survey Plan D-9: Layout showing sampling locations

4 New/Expansion / Modernization New

5 Existing capacity / Area etc Not Applicable

6 Category of the project ‘ A’, ‘B’ , ‘C’ Category ‘B’ 7 Does it attract the general conditions? If No Yes, Please Specify. 8 Does it attract the specific conditions? If No Yes, Please Specify 9 Location The location plan showing the location of the project is attached at Drawing-2. The Topographic sheet is enclosed with the application. Panoramic view showing location of the project site is attached at Drawing-3. Plot/ Survey/Khasra No. Khasra Nos. 2236/1/1, 2237/1, 2238/1, 2239/1, 2248, 2249/1, 2250/2, 2239/2/1, 2246/2, 2247/2,2236/2,2236/1/2,2237/2, 2238/2 2249/2, 2250/1 & 2235/2. Change of Land use along with Land documents are attached at Annexure-1 & 2 respectively.

Village Mullanpur Garibdass Tehsil S.A.S. Nagar State Punjab 10. Nearest railway station / Airport along Kharar Railway station: 13 km; with Distance in kilometers. Chandigarh Airport: 14 km. 11 Nearest town/District headquarters along The project lies within Mohali. with distance in kilometers District Headquaters: SAS Nagar 12 Village Panchayat, Zilla Parishads, Municipal Corporation SAS Nagar, Municipal corporation, local Bodies Sector-68, Mohali. (Complete Postal address with telephone Contact No. : 5044907,5044910 No. to be given) Fax No. : 5044913 E-Mail : [email protected] 13 Name of the applicant A K Sharma (Authorized Signatory) Board of resolution for authorization is enclosed as Annexure 4. 14 Registered address M/s. Curo India Pvt. Ltd. SCO No. 50-51, Ist Floor, Madhya Marg, Sector-9 D, Chandigarh-160009 15 Address for correspondence : M/s. Curo India Pvt. Ltd. SCO No. 50-51, Ist Floor, Madhya Marg, Sector-9 D, Chandigarh-160009 Name : A K Sharma Designation(owner/ Partner/CEO) Authorized Signatory Address M/s. Curo India Pvt. Ltd. SCO No. 50-51, Ist Floor, Madhya Marg, Sector-9 D, Chandigarh Pin Code 160009 E- Mail [email protected] Telephone No. 0172-5044910 Fax No. - 16 Details of alternative Sites examined, if No any. Location of these sites should be shown on the topo Sheets. 17 Interlinked Projects No

18 Whether separate application of interlinked Not Applicable project has been submitted?

19 If Yes, date of submission. Not Applicable

20 If No, reason Not Applicable

21 Whether the Proposal involves approval / Application has been filed for NBWL clearance; copy Clearance under : If Yes , details of the of which is enclosed as Annexure-5A. same and their to be given . (a) The Forest Conservation , Act,1980 (b) the wild life Protection Act, 1972 (c) The C.R.Z Notification, 1991.

22 Either their is any government Order / Not Applicable. policy relevant / relating to the site? 23. Forest land Involved (hectare) Not Applicable 24. Whether there is any litigation pending There is no litigation pending against the project. against the project and /or land in which the Undertaking in this regard is attached at Annexure-5B. Projects is proposed to be set up? (a) Name of the court (b) Case no. (c) Orders / Directions of the Courts , if any and its relevance with the Project.

(b) I hereby give the Undertaking that the data and information given in the application and enclosure are true to the best of my knowledge and belief, I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.

Date: 22.4.2016 Place: Mohali

Signature of the applicant A K Sharma M/s. Curo India Pvt. Ltd. SCO No. 50-51, Ist Floor, Madhya Marg, Sector-9 D, Chandigarh-160009 (Project Proponent/Authorised Signatory)

NOTE:

1. The project involving clearance under Coastal Regulation zone Notification, 1991 shall submit with the application a C.R.Z map duly demarcated by one of the authorized agencies, showing the project activities, w.r.t. C.R.Z (at the stage of TOR) and the recommendation of the state coastal zone Management Authority (at the stage of EC). Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification, 1991 for the activities to be located in the CRZ. 2. The project to be located within 10 km of the National parks, Sanctuaries, Biophere Reserves, Migratory Corridors of wild Animals, the project proponent shall submit the map duly authenticated by chief wildlife warden showing these features vis-à-vis the project location and the recommendation or comments of the Chief wildlife warden thereon (at the stage of EC). 3. All correspondence with the Ministry of Environment & Forests including submission of application for TOR/Environmental Clearance, subsequent clarification, as may be required from time to time, participation in the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for the specific project. (II) Activity 1. Construction, Operation or Decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities /rates, wherever possible) with source of information data 1.1 Permanent or temporary change Yes M/s. Curo India Pvt. Ltd. is coming up with a in land use, land cover or new Group Housing Project in the name of topography including increase “Curo North Square” at Village Mullanpur in intensity of land use (with Garibdass, Distt. SAS Nagar (Mohali), Punjab. respect to local land use plan) The total plot area of the project is 41,197 sq.m (10.18acres). The Change of Land use has already been obtained from Department of Town & Country Plannng, Punjab; copy is attached as Annexure 1. The development will be done as per the approved layout plan which is attached at Drawing-4. 1.2 Clearance of existing land, No Vacant land. vegetation and buildings? 1.3 Creation of new land uses? No The change of land use has already been obtained from Department of Town & Country Planning, Punjab; copy of which is enclosed as Annexure 1. Master Plan of Mullanpur showing project site is enclosed as Drawing 1.

1.4 Pre-construction investigations Yes The Pre-construction investigations have been e.g. bore houses, soil testing? done at the site. Soil report is enclosed at Annexure-10A. 1.5 Construction works? Yes The construction shall be as per proposed land use plan and details of the same are mentioned in Conceptual Plan. PERT/CPM is enclosed as Annexure 7. 1.6 Demolition works? No Not Applicable 1.7 Temporary sites used for Yes The manpower required during construction construction works or housing period shall be around 200. The most of the of construction workers? workers shall be local or from nearby areas. Only 50 workers shall reside at the site during peak construction period of 30 months. Temporary hutments and sanitation facilities shall be provided for these workers within the project site. 1.8 Above ground buildings, Yes Excavation will be done out for the foundation structures or earthworks of building & basements. Soil excavated will including linear structures, cut be 2,39,000 m3 which will be stored within and fill or excavations project site & will be used for cutting & filling and landscaping. 1.9 Underground works including Yes Only mining work will be done for basement. mining or tunneling? 1.10 Reclamation works? No Not Applicable 1.11 Dredging? No Not Applicable 1.12 Offshore structures? No Not Applicable 1.13 Production and manufacturing No Not Applicable processes? 1.14 Facilities for storage of goods Yes Cement and other construction materials shall or materials? be stored at site for which temporary sheds shall be constructed. 1.15 Facilities for treatment or Yes The total design population of the project is disposal of solid waste or liquid 8778 persons [residential population will be effluents? 2458 and floating population will be 6320]. The water will be abstracted from tubewell as well as GMADA supply. Permission from CGWA in this regard has already been obtained and letter submitted to CGWA for extension in NOC is attached at Annexure-8A & NOC from GMADA for water supply is attached at Annexure-8B. The water requirement as per Manual on Water Supply & Treatment, Government of India @ 200 lpcd for residential and @ 45 lpcd for floating will be approx. 596 KLD. Drawing showing Water supply plan & sewer layout plan is shown in combined services Plan which is attached at Drawing-6.

477 KLD of sewage will be generated from the project. This wastewater will be treated in STP of 500 KLD at the site. The water balance diagrams for 3 different seasons i.e. Summer, Winter & Monsoon season is shown in Figure 1, 2 & 3 respectively in the Conceptual Plan Page Nos. 5 to 6.

Solid waste of about 2246 kg/day will be generated (@ 0.4 kg/capita/day for residential and @ 0.2 kg/capita/day for floating population). A separate area is earmarked for segregation of solid waste within the site. Drawing showing solid waste segregation area within the project site is attached at Drawing- 5. 1.16 Facilities for long term housing No Local labourers will be hired from nearby of operational workers? areas during construction phase. Therefore, there is no need to create permanent facilities for long term housing of operational workers.

1.17 New road, rail or sea traffic Yes During construction phase, movement of 10- during construction or 12 vehicles shall be there. During operation, operation? the gestation period for occupation will 5-8 years. The vehicles as four/two wheelers shall be used by the occupants. 1.18 New road, rail, air waterborne No No new infrastructure for this purpose shall be or other transport infrastructure required. The site has well connected roads. including new or altered routes Only internal circulation road to be made. and stations, ports, airports etc 1.19 Closure or diversion of existing No There is no need of diversion of existing transport routes or transport routes. infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission No There are no new or diverted transmission lines or pipelines? lines. 1.21 Impoundment, damming, No No Impoundment, damming, culverting, culverting, realignment or other realignment or other changes to the hydrology changes to the hydrology of of watercourses or aquifers is proposed. watercourses or aquifers? 1.22 Stream crossings? No There is no stream running across the site. 1.23 Abstraction or transfers of Yes During Construction period, a Water demand water form ground or surface of 179 KLD (@ 30% of the demand during waters? operation) may be there depending upon phases of construction. This will include domestic demand for 200 workers during peak period @ 17 KLD (150 X 45 LPCD + 50 X 200 LPCD)

Rainwater recharging will be done from roof top area which be used to recharge aquifer. For the roof top area @ 7106 sq.m. with peak hourly rainfall of 45 mm and assuming run off coefficient 0.8, total runoff available will be 255.816 cum/hr. The ground water shall be recharged by providing 5 no. of rain water recharging pits to recharge water from rooftop area. Site plan showing 5 recharge pits is enclosed as Drawing-6.

1.24 Changes in water bodies or the No Not Applicable. land surface affecting drainage or run-off? 1.25 Transport of personnel or Yes During construction phase, movement of 10- materials for construction, 12 vehicles shall be there. operation or decommissioning? During operation phase, 1238 ECS of parking space will be provided within the project site. Further parking proposed & required is given in Table.1. The vehicles as four/two wheelers shall be used by the occupants. Parking Plan is enclosed as Drawing-7. TABLE-1 PARKING DETAILS

PARKING REQD.:

As per PUDA Rules, 2013: S.No. Particulars No.of DU’s/ Area ECS Required/ Unit Total ECS RESIDENTIAL Unit area less than 1. 66 1.5 99 1200 sq.ft Unit area b/w 1200- 2. 330 2 660 3000 Unit area above 3. 6 3 18 3000 sq.ft Visitor’s Parking 4. 77 @10% COMMERCIAL 5. Studio & shopping 12,955 sq.m. 2 ECS/100 sq.m. 259 3 ECS/100 sq.m. + 6. Multiplex 3,066 sq.m. 30% of total covered 120 area TOTAL PARKING REQD. 1,233

PARKING PROPOSED:

Area reqd. Parking Parking Area Parking Area S. No. Particulars for 1 ECS proposed (in Sq.ft.) (in Sq.mt.) (in Sq.mt.) (in ECS) Basement Parking 1. 1,82,642.03 16,851 32 527 01 Basement Parking 2. 1,55,581.56 14,547 32 455 02 3. Surface Parking 63,377.9 5,888 23 256

Total Parking Proposed 1,238 1.26 Long-term dismantling or No Not Applicable decommissioning or restoration works? 1.27 Ongoing activity during No Not Applicable decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in No There shall be no influx but routine either temporarily or movement of people. The maximum permanently? number of workers engaged in construction at any time shall not be more than 200. Out of these more than half of the work force shall be local and only about 50 workers shall reside at site.

The expected population of the Project on full occupation will be 8,768 persons. This will also have a gestation period of atleast 5-8 years after the construction is over. So, there will be no sudden influx but gradual occupation. 1.29 Introduction of alien species? No Not Applicable

1.30 Loss of native species or No There will be no significant impact on the genetic diversity? loss of native species or genetic diversity.

1.31 Any other actions? No Not Applicable 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): Details thereof (with approximate quantities Information/Checklist Yes/ S.No. /rates, wherever possible) with source of confirmation No information data 2.1 Land especially undeveloped or No The Change of Land use has been obtained agricultural land (ha) from Deptt. of Town & Country Planning, Punjab; copy of which is enclosed as Annexure 1.

2.2 Water (expected source & Yes During operation phase, water supply will be competing users) unit: KLD met through tubewell as well as GMADA supply. The total water requirement will be 596 KLD.

2.3 Minerals (MT) Yes Minerals such as sand & aggregates will be required during the construction phase.

2.4 Construction material – stone, Yes These materials shall be procured from aggregates, sand/s oil (expected authorized outlets in and around Mohali. source – MT) Approximate usage of Reinforced Cement concrete - Reinforcement steel TMT bars - 8300 MT, Cement PPC/OPC -610000 bags, Stone aggregate 20mm / 10mm size - 59700 cum, Coarse sand - 38200 cum, Hollock wood in scantling - 285 cum.

2.5 Forests and timber (source – Yes The Project involved minimum use of timber MT) during construction purpose. All material required for shuttering purpose shall be that of mild steel. During construction, a mix of MDF (e.g. For Cupboards and Door Panels), aluminium (for window shutters) shall be used to make minimum use of wood. At the most chowkets may be of wood.

2.6 Energy including electricity and Yes Total Power requirement of 3864 KVA to be fuels (source, competing users) provided by Punjab State Power Corporation Unit: fuel (MT), energy (MW) Limited. Total 4 DG Sets (3 x 1500 KVA + 1 x 500 KVA) are proposed for standby use for operating lifts & other emergency purposes, etc.

2.7 Any other natural resources (use No Not Applicable appropriate standard units) 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S.No. Information/Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible) with source of information data 3.1 Use of substances or materials, No Project involves construction of residential which are hazardous (as per complex of Residential dwelling units 402 and MSIHC rules) to human health 224 studio apartments. The project will not use or the environment (flora, fauna, any hazardous substances/ chemicals except for and water supplies) the used Oil from DG set (Hazardous Waste category 5.1). The same shall be stored in HDPE tanks and will be sold to the authorized recyclers in the region. 3.2 Changes in occurrence of No Not Applicable disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. Yes The project shall provide improved living by changing living conditions? facility to local people. It shall also provide employment during construction period as well as later in activities like shops, multiplexes, security, operation and maintenance of pollution control equipments, landscaping etc. 3.4 Vulnerable groups of people No Not Applicable who could be affected by the project e.g. hospital patients, children, the elderly etc. 3.5 Any other cause No Not Applicable

4. Production of Solid Wastes during construction or operation or decommissioning (MT/month) S.No. Information/Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine No The project area is plain thus not much of the wastes land will be excavated. 4.2 Municipal waste (domestic and Yes The construction waste will be used in making or commercial wastes) the internal roads/floors. About 2,246 kg/day of solid waste will be generated. The solid waste shall be duly segregated into biodegradable and non- biodegradable components. The recyclable waste shall be sold to resellers. Separate area is earmarked for handling biodegradable waste including segregation. Biodegradable waste will be composted by using Mechanical composter. 4.3 Hazardous wastes (as per Yes Category 5.1, used oil from DG sets. Hazardous Waste Management Rules) 4.4 Other industrial process wastes No Not Applicable 4.5 Surplus product No Not Applicable 4.6 Sewage sludge or other sludge Yes STP sludge will be generated as sewage will be from effluent treatment treated in house STP of 500 KLD capacity. 4.7 Construction or demolition Yes The construction waste consists of excess earth wastes & construction debris along with cement bags, steel in bits & pieces, including insulating & packaging materials, etc. Recyclable waste construction materials will be sold to recyclers. Unusable and excess construction debris will be disposed at designated places in tune with the local norms. 4.8 Redundant machinery or No Redundant machinery will not be generated. equipment 4.9 Contaminated soils or other No Contaminated soils or other materials will not materials be generated. 4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No Not Applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No. Information/Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible) with source of information data 5.1 Emissions from combustion of Yes The unit shall install 4 DG Sets (3 X 1500 KVA fossil fuels from stationary or + 1 X 500 KVA capacity) which shall run on mobile sources Diesel. These are to be used only as Standby & shall comply with emission limits as given in G.S.R. 520(E), EPA Rules 2003 at the manufacturing stage itself. DG sets shall be procured from agencies complying the noise emission standards at manufacturing stage itself as per G.S.R. 371(E), The Environment (Protection) second Amendment Rules, 2002. 5.2 Emissions from production No No production processes involved. Hence, there processes will be no such emissions. 5.3 Emissions from materials No Not Applicable handling including storage or transport 5.4 Emissions from construction Yes Dust may be generated during activities as activities including plant and excavation of foundation, the foundation shall equipment be excavated in a minimum time as per PERT and CPM Chart using machines. PERT/ CPM chart is attached as Annexure 7. The vehicles which carry construction material as sand will be covered from top and made wet before movement and thus no dust will be generated. 5.5 Dust or odours from handling Yes The construction material involved shall not of materials including provide any odour. A green belt is further construction materials, sewage proposed along the boundary and Solid Waste and waste Segregation Area to mitigate crossover of odours if any. 5.6 Emissions from incineration of No No incineration of waste is proposed. waste 5.7 Emissions from burning of No Not Applicable waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No Not Applicable sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat: S.No. Information/Checklist Yes/No Details thereof (with approximate quantities confirmation /rates, wherever possible) with source of information data 6.1 From operation of equipment Yes Unit shall install 4 DG Sets (3 X 1500 KVA + 1 e.g. engines, ventilation plant, X 500 KVA capacity) for standby use. The DG crushers sets shall be with in-built acoustic enclosure as approved by CPCB and conforming to MoEF Notification, GSR 371 (E). 6.2 From industrial or similar No Not Applicable processes 6.3 From construction or No Normal construction will be there without using demolition any heavy machinery. No construction at night shall be there. No demolition is involved. 6.4 From blasting or piling No Not Applicable 6.5 From construction or Yes The traffic during construction phase may be operational traffic around 10-12 vehicles/day. This shall not have any significant impact. During the operational phase, only personnel vehicles as cars/ two wheelers i.e. 1,238 ECS shall be used by the flat owners. In addition, adequate green area i.e. 10,416 sq.m will be provided. 6.6 From lighting or cooling No Not Applicable systems 6.7 From any other sources No - 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: S.No. Information/Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible) with source of information data 7.1 From handling, storage, use No Not Applicable or spillage of hazardous materials 7.2 From discharge of sewage or Yes About 477 KLD of sewage shall be generated other effluents to water or the from the project which will be treated in STP of land (expected mode and 500 KLD based on SBR technology. Treated place of discharge) water shall be recycled for the purpose of irrigation on green area within the project premises, flushing in toilets & HVAC cooling and remaining will be discharged to GMADA sewer. 7.3 By deposition of pollutants No Not Applicable emitted to air into the land or into water 7.4 From any other sources No Not Applicable

7.5 Is there a risk of long term No Not Applicable build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S.No. Information/Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible) with source of information data 8.1 From explosions, spillages, fires No Not Applicable etc from storage, handling, use or production of hazardous substances 8.2 From any other causes No The Building shall comply with the requirements of National Building Code towards Fire Safety for multistory structures. 8.3 Could the project be affected by Yes The Building is designed against Earthquakes natural disasters causing for Zone-IV requirements as laid down in environmental damage (e.g. NBC. Risk assessment plan is enclosed with floods, earthquakes, landslides, the application. cloudburst etc)? 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S.No. Information/Checklist Yes/ Details thereof (with approximate quantities confirmation No /rates, wherever possible) with source of information data 9.1 Lead to development of Yes The project is upcoming residential cum supporting. utilities, ancillary commercial project that will provide high end development or development facilities to the population and isn’t likely to stimulated by the project which impact the environment adversely in any could have impact on the manner. The related impacts are discussed. environment e.g.: There shall not be any further consequential •Supporting infrastructure cumulative impacts. (roads, power supply, waste or waste water treatment, etc.) • housing development • extractive industries • supply industries • other 9.2 Lead to after-use of the site, No Not Applicable which could have an impact on the environment 9.3 Set a precedent for later No Not Applicable developments 9.4 Have cumulative effects due to No Not Applicable proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity

S.No. Areas Name/ Aerial distance (within 15 Identity km.) Proposed project location boundary 1 Areas protected under international Sukhna Lake Approx. 7 km conventions, national or local legislation for their ecological, landscape, cultural or other Patiala Ki rao Approx. 1.6 km related value Reserve Forest 2 Areas which are important or sensitive for Sukhna Lake Approx. 7 km ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, Jainti Devi ki Approx. 1.2 km mountains, forests rao 3 Areas used by protected, important or sensitive Sector 21(A) Approx. 6.8 km species of flora or fauna for breeding, nesting, Bird Sanctuary foraging, resting, over wintering, migration Sukhna Approx. 5.4 km Wildlife Sanctuary 4 Inland, coastal, marine or underground waters No -- 5 State, National boundaries Punjab- Approx. 1 km Chandigarh Boundary 6 Routes or facilities used by the public for Madhya Marg, Adjacent to project site access to recreation or other tourist, pilgrim Chandigarh areas (- Chandigarh Road) 7 Defense installations No - 8 Densely populated or built-up area Yes The demographic details is attached as Annexure 9. 9 Areas occupied by sensitive man-made land Punjab Approx. 2.5 km uses (hospitals, schools, places of worship, University community facilities) PGI, Sector-15 Approx. 3 km

Bajwa Institute Approx. 2 km 10 Areas containing important, high quality or -- -- scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or No The area is not subjected to environmental damage. (those where existing any environmental damage. legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which -- The area has not faced any could cause the project to present natural hazard so far. environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

(IV) Proposed Terms of Reference for EIA studies

Not Applicable as project comes under category 8(a).