Form 1A: New District Jail , Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad,

APPENDIX II (See paragraph 6)

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary Attach explanatory notes with the Form and submit along with proposed Environmental management plan & monitoring programme) 1. LAND ENVIRONMENT 1.1 Will the existing land use get The project is proposed on a plot area of 254952.99 m2, significantly altered from the in the vacant land owned by Naini Central Jail at project that is not consistent with Allahabad U.P. It will be called as New District Jail of the surroundings? (Proposed land Allahabad U.P. which is easily approachable by roads (NH use must conform to the approved 76 & NH 27) and railway routes (Naini is an important Master Plan / Development Plan of station on Delhi – Howrah and Howrah – Allahabad – the area. Change of land use if any Mumbai). A Green belt is proposed in about 67625.64 m2 and the statutory approval from the area. The project is proposed to have total ground coverage competent authority are submitted). of 11475.44 m2 with a built up area of 16018.63m2. Attach Maps of (i) Location map of the project site is enclosed in (i) Site location, Conceptual Plan. (ii) Surrounding features of the (ii) 5.0 Km radius map of the site including micro proposed site (within 500 meters) level features is enclosed in Conceptual Plan. (iii) The site (indicating levels & contours) to appropriate scales. If (iii) Conceptual Plan and layout Plan is enclosed. not available attach only conceptual plans.

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 1

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

1.2 List out all the major project requirements in terms of the Land area, Total Plot Area- 254952.99 m2 (63Acres) Built up area Built up - 16018.63 m2 Water consumption, Water Consumption – 604.60 KLD Power requirement, Transformer – 630 KVA Connectivity, The proposed project is well connected by NH-76 & NH-27 and rail routes. The proposed project has Community facilities, adequate housing, parking and community facilities with sufficient spaces for landscape and green belt Parking needs etc. development as per requirement. Required Parking Area = 2898 m2. Provided Parking Area = 3000 m2 1.3 What are the likely impacts of the This project is proposed with a Green Belt area proposed activity on the existing equivalent to 26.53 % of the total plot area. facilities adjacent to the proposed  The entire project area will be developed to cater to site? the needs and demand of institutional building and (Such as open spaces, community no induced development is foreseen due to the facilities, details of the existing proposed project. Also the proposed development land use and disturbance to the shall be carried out as per the defined building by- local ecology). laws; hence no adverse impact is envisaged due to the proposed development.  Moreover this proposed project will provide a value added features to the existing infrastructure. Further, during the construction as well as operation stage of the project, direct and indirect employment opportunities for a large section of society will be generated. The employment will have positive impact thereby increasing the quality of life of nearby dwellers. 1.4 Will there be any significant land Soil Type: The major position of district is occupied disturbance resulting in erosion, by soils locally known as “Bhur” or “Silty Sand” on the subsidence & instability? ridges. “Matiyar or Clayey soils” occur along the (Details of soil type, slope analysis, topographic lows and “Dumat or Loamy soils” in the vulnerability to subsidence, level lands. Clay is dominant in the areas where “Reh” seismicity etc may be given). (Usar) prevails. Along the river valleys, a very fertile soil called “Dumat” is present. Erosion / Subsidence: Proper greening & paving of area will not cause any soil erosion problem and

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 2

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

subsidence. Seismicity: The area under study falls in zone-III, according to the Indian Standard Seismic Map. Suitable seismic coefficients in horizontal and vertical directions will be adopted while designing the structures. 1.5 Will the proposal involve alteration The proposed project will not cause any alternation of of natural drainage systems? the existing natural drainage system. (Give details on a contour map showing the natural drainage near the proposed project site) 1.6 What are the quantities of During construction phase, some excavation is earthwork involved in the envisaged in order to provide foundation and basement. construction activity-cutting, This excavated soil will be properly stacked within the filling, reclamation etc? site under tarpaulin cover and will be reused for (Give details of the quantities of backfilling purpose. The top fertile soil will be stacked earthwork involved, transport of and preserved separately and which will be used only for fill materials from outside the site landscaping purposes later on. Hence, no adverse impact etc.) on the land environment is envisaged. 1.7 Give details regarding water Water Supply: During Construction and operation supply, waste handling etc during stage, water will be sourced primarily through 3 Nos. of the construction period. tube well. Waste Generation / Handling: Soil excavated will be reused for backfilling and the fertile top soil will be reused for horticultural purpose. Spillage of oil from the machinery or cement residual from concrete mixer plants will be properly collected and reused in construction site. For construction laborers, proper sanitary facilities & wash areas will be constructed and good hygienic conditions will be maintained. 1.8 Will the low lying areas & No low lying and wetlands area are there within the wetlands get altered? proposed site or in the immediate surroundings of the (Provide details of how low lying project site. and wetlands are getting modified from the proposed activity) 1.9 Whether construction debris & The construction debris generated from the construction waste during construction cause project will not cause any health hazard to the health hazard? (Give quantities of associates and nearby population. The construction various types of wastes generated debris will be used for leveling the land / backfilling and

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 3

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

during construction including the landscaping according to its composition. Waste construction labor and the means of concrete will be reused as aggregate in construction disposal) process. Metal wastes will be recycled. Approx. 150 labors will be engaged during the construction period. Proper sanitary facilities will be provided to construction laborers. Good hygienic conditions will be maintained.

2. WATER ENVIRONMENT 2.1 Give the total quantity of water Source: Ground Water requirement shall be fulfilled requirement for the proposed through 3 nos. tube wells. project with the breakup of The break up is as follows requirements for various uses. Total Water Requirement 604.60 KLD Total Domestic Water Requirement 191.94 KLD Water requirement for hospital 110.70 KLD How will the water requirement Gardening 67.62 KLD met? Flushing 129.70 KLD

The water requirement shall be met from 3 nos. of Tube State the sources & quantities and well. furnish a water balance statement. Total water demand for the recreational and green areas excluding fire fighting water demand and losses is calculated to be 6.04 KLD. An STP of 2 MLD will treat 258.32 KLD of domestic waste water. The treated water of 198.100 KLD will be reutilized for gardening, Flushing and D.G. Set cooling purposes. The surplus treated water 69.48 KLD shall be diverted from the storm water pit. An ETP of 110 KLD will be required to treat 88.56 KLD of hospital effluents. The treated effluents water shall be used for cleaning floors, roads and drains etc. A detailed water balance statement and flow diagram has been given in the report on pages 24 & 25. 2.2 What is the capacity (dependable The water demand will be met by 3nos. of proposed flow or yield) of the proposed Tube well within the project site. This supply will meet source of water? the requirement of 604.60 KLD water. 2.3 What is the quality of water Supply of water during operation phase will be from required, in case, the supply is not Tube wells. (With permission from CGWB). The

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 4

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

from a municipal source? (Provide required water quality at the project site will be within physical, chemical, biological prescribed limits of IS: 10500-2012 Specification. Details characteristics with class of water enclosed in Conceptual Plan. quality) 2.4 How much of the water Total waste water generation 258.32 KLD from which requirement can be met from the 129.70 KLD is black water which will be disposed in the recycling of treated wastewater? STP of 2 MLD capacities. Grey water of about 128.62 KLD from domestic use shall also be diverted to the (Give the details of quantities, proposed STP of 2 MLD. The hospital effluents of sources and usage) 88.560 KLD shall be diverted to the ETP of 110 KLD capacity for treatment 2.5 Will there be diversion of water There will not be any substantial effect on water demand from other users? of this region. No diversion of water from other users is (Please assess the impacts of the anticipated. project on other existing uses and quantities of consumption) 2.6 What is the incremental pollution The domestic waste of grey and black water generation load from wastewater generated is estimated to be 258.32 KLD which will be treated in from the proposed activity? the proposed STP of 2 MLD and the hospital effluents are estimated to be around 88.560 KLD which will be (Give details of the quantities and treated in an ETP of 110 KLD capacity, so no excessive composition of wastewater pollution load from waste water is envisaged. The treated generated from the proposed water shall be reused. The composition of waste water activity) would be as follows: Characteristics Values BOD 250-300 mg/l COD 400-500 mg/l TSS 150 mg/l Oil & Greases <20 mg/l 2.7 Give details of the water The rain water from terraces and other open area will be requirements met from water collected through rainwater down take pipes and harvesting? Furnish details of the connected to the 3Nos. Rain Water Harvesting Pit. The facilities created. rain water from open areas shall be considered for rain water recharge only after approval from CGWB. Rainwater Harvesting will recharge the Ground water table. For collecting storm water, storm water drainage

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 5

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

network has been provided during the design stage as per the guidelines defined by the municipal authorities. In the project design, it shall be ensured that no mixing of the storm water with waste effluent takes place. All the storm water will be diverted to rain water-harvesting network proposed in the complex. The oil grit and silt will be trapped before discharge into the harvesting pits. Rainwater at peak rainfall intensity of 25 mm in the region will be recharged to first aquifer. 2.8 What would be the impact of the No impact land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well It will not aggravate the problems of flooding or water as qualitative) of the area in the logging as the existing drainage slopes will be retained. post construction phase on a long- It is proposed to maintain & utilize the existing course of term basis? natural drainage system with only minor re-alignments Would it aggravate the problems of for the disposal of main storm water runoff from the flooding or water logging in any proposed site conditions. way? 2.9 What are the impacts of the As the proposed project will encourage the recharging of proposal on the ground water? ground water through rain water harvesting, therefore (Will there be tapping of ground ground water extraction shall be substantiated water; give the details of ground simultaneously. water table, recharging capacity, and approvals obtained from competent authority, if any) 2.10 What precautions/measures are During the construction phase, runoff from the taken to prevent the run-off from construction site shall not be allowed to go into the construction activities polluting roadside. Adequate measures shall be taken to land & aquifers? channelize such run off and the same shall be disposed (Give details of quantities and the off through existing storm water drainage network. measures taken to avoid the All Strom water drainage will be channelized to adverse impacts) Rainwater pit. 2.11 How is the storm water from The storm water is channelized to ground water through within the site managed? 3 nos. of Rainwater recharge pit after oil & grease trap. (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 6

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

with a site layout indication contour levels) 2.12 Will the deployment of Temporary arrangements for civic amenities shall be construction laborers particularly provide on the site. Soak pits & septic tank shall also be in the peak period lead to provided. unsanitary conditions around the project site (Justify with proper explanation) 2.13 What on-site facilities are provided Hospital effluents and Domestic waste water 88.56 for the collection, treatment & safe KLD) and 258.32 KLD, total will be treated in the disposal of sewage? proposed ETP of 110 KLD capacity and in the S.T.P of (Give details of the quantities of 2 MLD respectively. All the wastewater shall be wastewater generation, treatment channelized to STP based on FAB Technology, where it capacities with technology & shall be treated. Sludge from STP shall be used as facilities for recycling and manure in Garden & the treated water shall be reused in disposal). Flushing and Gardening. 2.14 Give details of dual plumbing Dual Plumbing system is being provided the detail have system if treated waste used is used been in the project's conceptual plan. for flushing of toilets or any other use.

3. VEGETATION 3.1 Is there any threat of the project to the Study is conducted within 15 km radius from project site. biodiversity? Project site / core zone is devoid of any shrub and herb, patches of local grasses and trees are seen. The area (Give a description of the local covers Ganga & river. The Ganga is home to ecosystem with its unique features, if fish species. river shark (Glyphis gangeticus), any) Ganges soft-shell turtle (Nilssonia gangeticus), gharials (Gavialis gangeticus) and several species of endemic freshwater crabs were found. The impacts of increased population growth, industrial development, urbanization, deforestation and construction of dams and barrages as well as embankments have adverse impacts on ecological health of the river including water quality, fisheries and other biodiversity in the past. A steady decline has been seen in populations of prized carp and Tenualosa ilisha (hilsa) fishes, as well as minnows after commissioning of the Farakka Barrage. The construction of Farakka Barrage

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 7

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

(commissioned in 1975) had a significant impact on fisheries as far up as Allahabad. The Pisciculture is neither practiced on large scale nor undertaken in organized manner in the area. However, the entire river stretch and tributaries is being utilized for fishing in unorganized manner. The most prevalent aquatic plant in River Yamuna is the water hyacinth , mostly found near barrages.

In 10 Km radius trees found are Neem (Azadirachta indica), Aswath (Ficus benganesis), Ber (Zyziphus mauritiana), Amaltash (Cassia fistula), Peepal (Ficus religiosa), Gulmohar (Delonix regia), and Siris (Albizia lebbek). The ecology of the study area is not very rich in diversity or high in endemism, which may be primarily accounted for the scattered distribution of poor quality and quantity of fodder. The major mammalian fauna of the project influenced area involve common languor, mongoose (Herpestris edwardii) etc. Avifauna is primarily represented by common crow (Corvus splendens), House Sparrow (Passer domesticus), blue rock pigeon (Columba livia) and finches. Common peacock (Pavo cristatus) is known to be present in the area. Small, reptiles, like lizards, chameleons, poisonous and non- poisonous snakes are also found in the study area. No migratory birds breed in the study area. Except Egrets Sps. Is locally found. 3.2 Will the construction involve extensive Project site is devoid of any shrub and herb. Patches of clearing or modification of vegetation? local grasses are seen. Hence construction will not (Provide a detailed account of the trees & involve extensive clearing or modification of vegetation. vegetation affected by the project) The preexisting natural vegetation shall be preserved. Vegetation provided erosion control, storm water detention, bio filtration, and aesthetic values to a site during and after construction activities. A site map would be prepared with the locations of trees and boundaries environmentally sensitive areas and buffer zone to be preserved.

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 8

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

3.3 What are the measures proposed to be There will not be any kind of impact of this project on site taken to minimize the likely impacts on features. The green area will mitigate the adverse impact important site features of pollution. Total Landscape area including green belt of (Give details of proposal for tree 67625.64 m2 for the development of site, ornamental plantation, landscaping, creation of water herbs/ shrubs: lawns. It will be ensured that 100% of the bodies etc along with a layout plan to an trees are native species. Since the proposed area does not appropriate scale) have any tree, nothing shall be uprooted. Landscape details are given in Conceptual Plan.

4. FAUNA 4.1 Is there likely to be any The proposed site is an open land and this place is not displacement of fauna- both the habitat for local fauna. So, there will not be any type terrestrial and aquatic or creation of of displacement or any other effect on the local fauna barriers for their movement? due to proposed project activities. Provide the details. 4.2 Any direct or indirect impacts on the Within the proposed project site, proper landscaping has avifauna of the area? Provide been planned to provide a clean, healthy and beautiful details. green environment for the population. Common native variety of trees and ornamental flowering species will be planted in the green space. Landscaping can have direct positive impact on the local avifauna, as this will provide shelter to local birds. 4.3 Prescribe measures such as These measures are not applicable for this project. corridors, fish ladders etc to mitigate adverse impacts on fauna

5. AIR ENVIRONMENT 5.1 Will the project increase The project activities are in large area with green spaces atmospheric concentration of gases therefore no increase in concentration of gases or heat & result in heat islands? island effect expected.

(Give details of background air quality levels with predicted values No regular air emissions sources are there. based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions) 5.2 What are the impacts on generation Air Pollution Dispersion Relationship with

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 9

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

of dust, smoke, odorous fumes or Meteorology other hazardous gases? Give details in relation to all the meteorological The measurement of wind speed and direction, parameters. temperature, humidity, rainfall and solar radiation are important parameters used in the study of air quality monitoring results and to further understand the chemical reactions that occur in the atmosphere.

Dust storms may leads to the build-up of particulate matter in the atmosphere. 5.3 Will the proposal create shortage of Surface, Parking provision has been made within the parking space for vehicles? Furnish project at Project site. Open Area car parking facility details of the present level of shall be provided. The parking plan for this transport infrastructure and construction project would follow all the standards and measures proposed for improvement norms of Allahabad Development Authority. including the traffic management at The proposed project site is well connected by Bus the entry & exit to the project site. routes through N27 & NH-76. Traffic management is enclosed in the Environment Report. 5.4 Provide details of the movement In the proposed project proper arrangement has been patterns with internal roads, bicycle made for smooth traffic movement. Adequate tracks, pedestrian pathways, lightening arrangement tapping will be provided footpaths etc., with areas under each covering all corners. category. 5.5 Will there be significant increase in It is envisaged that the only sources of noise pollution is traffic noise & vibrations? Give vehicular movement and the operation of D.G. sets details of the sources and the which will not generate significant noise level. measures proposed for mitigation of Plantation of trees both sides of all roads as well as the the above. green belt shall be developed for noise attenuation. 5.6 What will be the impact of DG sets There would not be any impact on the ambient air & other equipment on noise levels & quality The noise emission from D.G. Sets (is not vibration in & ambient air quality proposed) will meet the noise level as per CPCB around the project site? Provide guidelines. details.

6. AESTHETICS 6.1 Will the proposed constructions in The land allotted for the proposed project is in any way result in the obstruction of proximity to the present Naini Central Jail. Any a view, scenic amenity or obstruction of a view, scenic amenity of landscape is

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 10

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

landscapes? out of question because this allotted land is a piece of Are these considerations taken into open land where in future an extensive development account by the proponents? and landscaping of the area is going to contribute to its scenic beauty, hence no adverse impacts are envisaged. 6.2 Will there be any adverse impacts No adverse impacts are anticipated from this new from new constructions on the construction project on the existing surrounding of the existing structures? What are the area. considerations taken into account? However, the proposed project will definitely improve the aesthetics and scenic view of the area. 6.3 Whether there are any local There are no local consideration of urban forms & urban considerations of urban form & design influencing the design criteria. urban design influencing the design The proposed Project will develop within the designated criteria? They may be explicitly site as per the defined building by-laws of NBC-2016. spelt out. Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

7. SOCIO-ECONOMIC ASPECTS 7.1 Will the proposal result in any The operation of the project shall provide value addition changes to the demographic to the existing infrastructure with improved living structure of local population? standards. Provide the details. The proposed project will provide indirect job facilities in the form of house keeper & maintenance staff. During construction phase about 150 Nos. of skilled and unskilled work force will be required per day. This workforce will be hired locally, which generate employment to the local people. 7.2 Give details of the existing social The project site lies within Naini township which is infrastructure around the proposed situated in Yamuna paar area almost adjacent and near project. the NH – 27 And NH – 76 roads. Hospital, Institutes and Schools, some places of worship. Police Chauki and Fire station etc are situated within the 10 km radius of

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 11

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

the proposed site. 7.3 Will the project cause adverse The project will be constructed within the designated effects on local communities, site as per the defined building by-laws of government disturbance to sacred sites or other authority. There is no sacred site or cultural heritage site cultural values? What are the within the vicinity of the proposed project; hence no safeguards proposed? adverse impacts are envisaged.

8. BUILDING MATERIALS 8.1 May involve the use of building The major materials required for construction of the materials with high-embodied proposed project will be steel, cement, bricks, flooring energy. tiles / stones, sanitary and hardware items, electrical Are the construction materials fittings, water, etc. produced with energy efficient Energy efficient process will be used in the proposed processes? project. (Give details of energy Energy Conservation measures with “U” & “R” values conservation measures in the material will be proposed. selection of building materials and their energy efficiency 8.2 Transport and handling of materials Mitigation Measures for Air Pollution During during construction may result in construction stage: pollution, noise & public nuisance. All the loose material either stacked or transported shall What measures are taken to be provided with suitable covering such as tarpaulin, minimize the impacts? etc. Water sprinkling shall be carried out at regularly at locations where dust generation is anticipated. To minimize the occupational health hazard, proper personal protective gears i.e. mask shall be provided to the workers who are engaged in dust generation activity. Mitigation Measures for Noise Pollution during Construction stage: Administrative as well as engineering control of noise will be implemented. Isolation of noise generation sources and temporal differentiation of noise generating activities will ensure minimum noise at receiver’s end. To prevent any occupational hazard, ear muff/ earplug shall be provided to the workers during working hours around the operating plants and machinery emitting high noise levels. Use of such plant and machinery shall not be allowed during night hours. Careful planning of

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 12

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

machinery operation and the scheduling of operations shall be exercised to minimize the impacts.

8.3 Are recycled materials used in As there is no availability of recyclable building roads and structures? material in the vicinity of proposed project site therefore State the extent of savings the use of recyclable materials is not envisaged in the achieved? construction process. If such recyclable materials are made available at reasonable prices then they can be definitely used. 8.4 Give details of the methods of The quantity of Solid Waste Generation during collection, segregation & disposal operation phase will be 2500.75 Kg/day. of the garbage generated during the As per the manual of municipal solid waste prescribed operation phases of the project. in Central Public Health and Environmental Organization (CPHEEO), the solid waste disposal method shall be adopted. The solid waste will comprise of biodegradable waste e.g. domestic waste, food waste, horticultural waste etc. and recyclable waste, like plastic, paper, tin, glass etc. This solid waste would be disposed off as per Municipal solid waste management and handling norms.

Municipal Solid Waste Management Plan: In the proposed project, adequate number of collection bins separately for biodegradable and non- biodegradable waste shall be provided as per Municipal Solid Waste (Management and Handling Rules, 2016). Waste from such bin shall be collected separately on daily basis. Separate colored bins will be provided for biodegradable and non-biodegradable wastes. The solid waste will be collected and taken to a separate centralized collection facility. Final segregation of solid waste into biodegradable, non-biodegradable and inert fraction into the centralized collection fraction would be made. Arrangements will be made with authorized agency, for

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 13

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

providing the garbage station or transfer point, where all wastes collected from collection bins shall be disposed off for further disposal by the authorities. Horticulture waste (leaves, grass and vegetation parts) shall be collected at the secured location such that it shall not hinder daily activity schedule or washed away by the surface run off causing choking of drains, etc. and will be separately disposed off along with biodegradable waste.

9. ENERGY CONSERVATION 9.1 Give details of the power Power Requirement & Source of Power: requirements, source of supply,  UPSEB will provide necessary power through backup source etc. 630 KVA transformers. What is the energy consumption Energy Conservation Measures: assumed per square foot of built-up  In the operational phase, appropriate energy area? conservation measures & management plan will How have you tried to minimize be adopted in order to minimize the energy consumption? consumptions of non-renewable fuel. The following measures are suggested to adopt:- Compact fluorescent lamps will be used in place of incandescent halogen lamps in all common areas. Lighting and switching shall be designed by keeping in mind day light integration. After testing the viability, solar energy can also be used to meet electricity requirement as it would reduce dependency on non-renewable sources of energy and make environment cleaner. Using solar photovoltaic cells, which convert solar energy into DC electricity directly, can trap solar energy. For the electricity back up during power failures 2 Nos. Generators of 25 KVA and 62.5 KVA capacities have been provisioned. 9.2 What type of, and capacity of, Not envisaged in the project power back-up to you plan to provide? 9.3 What are the characteristics of the Glass of 10 mm thickness shall be used. glass you plan to use? Provide specifications of its

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 14

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

characteristics related to both short wave and long wave radiation? 9.4 What passive solar architectural Building design and envelope has been optimized features are being used in the through selection of appropriate wall and roof building? construction and through adoption of solar passive Illustrate the applications made in measures after studying the sun path analysis. the proposed project. 9.5 Does the layout of streets & Yes, the layout of buildings has been designed to buildings maximize the potential maximize the potential for solar energy devices. After for solar energy devices? testing the viability, solar energy will also be used for Have you considered the use of street lighting, emergency lighting & solar heating. street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details. 9.6 Is shading effectively used to Passive solar architectural measures have been adopted reduce cooling/heating loads? to provide shading devices for windows and roof, which What principles have been used to would effectively reduce heating up of building maximize the shading of Walls on envelope. the East and the West and the Roofs will be painted with reflective aluminum based Roof? How much energy saving paints with solar reflectance ranging from 0.3-0.6. This has been effected? will result in less absorption of sunlight causing 40 % back reflection and less heating of building structure during summer season. This will effectively reduce the heat load of the building envelope. 9.7 Do the structures use energy- The space-heating load will be minimized using passive efficient space conditioning, solar structure and suitable buildings envelop material. lighting and mechanical systems? Uses of incandescent lamp and halogen lamps have Provide technical details. been avoided and energy efficient compact fluorescent Provide details of the transformers and fluorescent lamps have been used for all and motor efficiencies, lighting common areas and in parking areas. intensity and air-conditioning load No CFC & HCFC free chillers are proposed to be assumptions? installed at proposed project. Are you using CFC and HCFC free chillers? Provide specifications 9.8 What are the likely effects of the The proposed construction will be carried out within the building activity in altering the designated site as per the defined building by-laws. So micro-climates? there will neither be any significant effects on the

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 15

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

Provide a self assessment on the surrounding environment nor any heat island effect have likely impacts of the proposed been envisaged. construction on creation of heat island & inversion effects? 9.9 What are the thermal The thermal characteristics are: characteristics of the building envelope? (a) roof; (b) external U Value R Value walls; and (c) fenestration? Roof 0.12 8.33 Give details of the material used External wall 0.38 2.63 and the U-values or the R values of Fenestration (Glass) 1.10 0.91 the individual components. 9.10 What precautions & safety Fire Fighting arrangement will be installed as per the measures are proposed against fire provisions of the National Building Code (SP7: 1993 hazards? Furnish details of Part IV amendment No. 3 of January, 1977). emergency plans. Fire fighting Plan is enclosed in the Conceptual Plan. 9.11 If you are using glass as wall Glass with a low emissive coating will be used. material provides details and Windows manufactured with low –E coating reduce specifications including emissive energy loss by as much as 30-50%. Different type of and thermal characteristics. low –E coatings has been designed to allow for higher solar gain, moderate solar gain, or low solar gain. Typical thermal conductivity (U-values) will range between 1.2-1.4 W-m2 –K as compare to 1.5-1.7W-m2- K range for normal glass. 9.12 What is the rate of air infiltration Proper arrangement for Indoor air quality monitoring into the building? shall be made. Provide details of how you are mitigating the effects of infiltration. 9.13 To what extent the non- After testing the viability, solar energy will be used as a conventional energy technologies source of non-conventional energy. This source can are utilized in the overall energy fulfill the electricity requirements. consumption? Provide details of the renewable energy technologies used.

10. ENVIRONMENT MANAGEMENT PLAN 10.1 The Environment Management The Environmental Management Plan consists of the set Plan would consist of all mitigation of mitigation measures, management practices,

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 16

Form 1A: New District Jail Allahabad, Land Under Central Jail Possession, at Naini, Tehsil: Meja, District Allahabad, Uttar Pradesh

measures for each item wise monitoring and institutional measures etc. that are to be activity to be undertaken during the taken during implementation and operation phase to construction, operation and the eliminate adverse environmental impacts, to offset them entire life cycle to minimize or to reduce them to acceptable levels. adverse environmental impacts as a result of the activities of the project. It would also delineate the Detailed Environmental Management Plan enclosed in environmental monitoring plan for Conceptual Plan. compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

Environmental Consultant- M/s Sawen Consultancy Services Pvt. Ltd., Lucknow 17