Page 1 of 151

Minutes of the 134th Meeting of the State Expert Appraisal Committee, constituted for considering Environmental Clearance of Projects (B category) under Government of Notification dated 14.09.2006, held on 30th & 31st May, 2016 and 01st June, 2016 under the Chairmanship of Sh. G.R. Goyat, Chairman, SEAC at . ***** List of participants is annexed as Annexure-A. At the outset the Chairman, SEAC welcomed the Members of the SEAC and advised the Secretary to give brief background of this meeting. The minutes of the 133rd Meeting were discussed and approved without any further modification. It was further informed that in this meeting 31 number projects are to be taken up for scoping, appraisal and grading as per the agenda circulated and 08 cases are taken up as additional agenda item. After preliminary discussion, the following projects were taken up on case-to- case basis:- 134.01 Environmental Clearance for Commercial Project of “Spaze Corporate Park” at Sector-69-70, Village District by M/s Spaze Towers Pvt. Ltd.( M/s Wellworth Housing Pvt. Ltd.)

The project was submitted to the SEIAA, on 13.07.2012. The papers submitted were examined and certain shortcomings were noticed and conveyed to PP vide letter No. 180 dated 17.07.2012. The PP submitted the reply to the shortcomings on 10.09.2012. Thereafter this case was taken up for appraisal in the 73rd meeting of the SEAC held on 16.01.2013. During discussion, it was observed that out of two licenses i.e. License No. 27/2009 and No. 134/2008, the license No.134/2008 was renewed up to August, 2012. The project proponent informed that they have applied for renewal of license. The observations of the 73rd meeting of the SEAC were conveyed to the project proponent vide letter No. 1059 dated 25.01.2013. The project proponent submitted the reply of the shortcomings vide letter dated 03.06.2013. Thereafter this case was taken up for appraisal in the 87th meeting of the SEAC held on 22.07.2013. During discussions, it was informed by the Members that the project report of the case was not been delivered to three Members. Even the other Members received the project report of the case just one day before the date of meeting. Due to the above mentioned lapse on the part of Project Proponent, it was not possible for the Committee to process their case in this meeting. The Project Proponent and Consultant expressed their regret for the failure for providing the documents to the Members and they made a request that their project may be considered on the next meeting of SEAC due on 05.08.2013. The Committee agreed to the request and decided to process this case accordingly. The Project Proponent and Consultant were directed to ensure delivery of document concerning project report to the remaining 3 members before 28.07.2013. It was also informed to the Project Proponent that no separate letter will be issued. Thereafter this case was taken up for appraisal in the 88th meeting of the SEAC held on 05.08.2013. Page 2 of 151

After detailed discussions, the following shortcomings were concluded:

1. The PP will submit the landscape area details. 2. The PP will submit the surface parking area details. 3. The proponent of the building construction project required to submit risk assessment identifying the detailed/ hazards involved during construction phase and operation phase, causes of such hazards and their mitigating measures. 4. Prepare the complete ventilation plan of the building taking into account the building design features, ventilation techniques, Wind Rose , Solar Orientations and atmospheric stability factors (Lapse rate and inversion i.e. rate of change of wind speed and temperature with height of building), green house effect. Assessment should be done qualitatively and quantitatively i.e. in terms of Air changes per hour in the different parts of building like basements, generator rooms occupancies (rooms) toilets, kitchen, passages, ways and stair cases. 5. Prepare detailed lighting (Illuminance) plan, qualitatively and quantitatively (range in terms of lux i.e. lumen per mt. sq. and internal and external lighting power applications as a function of Lighting Power Density, (watt per sq mt.) taking into consideration building solar design and orientation, using energy efficient lighting equipment design, lighting control systems (manual and automatic) maintenance, provision of surface brightness, glare reduction and light distribution systems etc. in the building occupancies, toilets, kitchens, passages, ways, stairs, roads, landscape area. 6. Prepare complete risk assessment plan of the fire fighting systems (water sprinkling system, water hydrant system, chemical fire extinguishers systems, capacity and storage of water for fire fighting, man power for fire fighting and protective clothing for fire fighters and liaison with the district fire fighting teams and other district authorities for use ) in case of fire fighting and fire rescue system taking into account all the building design features with line diagrams of the fire fighting system and rescue systems indicating the codes, and standards and specification used with reference to NBC 2005 7. Give efficient ways and means and appliances for reduction of use of water (water saving) in the building construction phase and operation phase in kitchen, bathroom, flushing, air conditioning/ heating/ landscaping/ gardening/ and effluent treatment plant. 8. The PP will submit dispersion modeling in construction phase. The observations of 88th meeting of the SEAC were conveyed to the project proponent vide letter No. 582 dated 12.08.2013. The project proponent submitted the reply of the shortcomings vide letter dated 27.12.2013. Thereafter this case was taken up for appraisal in the 99th meeting of the SEAC held on 28.01.2014.

During discussion, it was revealed that project proponent has started construction work which amounts to violation of EIA Notification dated 14.09.2006. Project proponent was asked to submit an affidavit by a Director of the Company giving exact status of construction.

The observations of 99th meeting of the SEAC were conveyed to the project proponent vide letter No. 1042 dated 25.02.2014. The project proponent submitted the reply of the shortcomings vide letter dated 28.02.2014. Thereafter this case was taken up for appraisal in the 104th meeting of the SEAC held on 12.05.2014.

Further in order to assess the correct position at site, Committee decided to constitute a Sub-Committee consisting of the following which will inspect the site to verify the status of construction of the project:

1. Sh. I.J. Juneja, Chairman Page 3 of 151

2. Sh. R.S. Rana, Member

3. Dr. Surinder Singh Yadav, Member

Sh. R.S. Rana, Member shall coordinate with the project proponent and the consultant. On behalf of project proponent, Sh. Arvinder Dhingra, Director, shall coordinate with Sh. R.S. Rana, Member for deciding the date of the visit and other details. The sub- committee shall submit its report within 15 days from the issue of the letter by the Secretary.

The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 12.04.2016 after the reconstitution of SEIAA/SEAC on 21.08.2015.

Thereafter, the case was taken up in the 134th meeting of the SEAC held on 30.05.2016.

In order to assess the correct position at site, Committee decided to constitute a Sub-Committee consisting of the following which will inspect the site to verify the status of construction of the project:

1. Sh. R.K. Sapra, Member

2. Sh. A.K. Bhatia, Member (Coordinator)

3. Sh. S.N. Mishra, Member

Sh. A.K. Bhatia, Member shall coordinate with the project proponent and the consultant for deciding the date of the visit and other details. The sub-committee shall submit its report within 15 days from the issue of the letter by the Secretary.

134.02 Environmental Clearance for Revision and Expansion of Group Housing Colony located at Sector-112-113, Bajghera Road, District Gurgaon, Haryana by M/s Lemon Land and Developers Pvt. Ltd. Project Proponent : Sh. Anil Gupta, Authorised Signatory Consultant : Grass Roots Research and Creation India Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 01.09.2015. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The Terms of Reference was approved in the 126th meeting of the SEAC held on 27.01.2016 and conveyed to the project proponent vide letter No. 613 dated 10.02.2016. Further, the project proponent will submit the following at the time of appraisal: 1. The PP to submit the certified copy of report from Regional Director, MoEF regarding status of compliance of the conditions stipulated in the Environmental Clearance as contained in the MoEF circular dated 30.05.2012. 2. The PP to submit Status of compliance of the conditions and environmental safeguards stipulated in the earlier clearance letters. 3. The PP to submit Details of the court cases, if any, pending in any court of law against the project as well as any directions passed by the court relating to the project directly or indirectly. Page 4 of 151

4. The PP to submit Details of the notices, if any, given to the project under section 5 of the Environment (Protection) Act, 1986 and section 18 of the Air (Prevention and Control of Pollution) Act,1981. The project proponent further stated that they are already generating data from October, 2015 and requested to utilize the baseline data. The Committee after detailed deliberations accepted the request of the PP. The Committee after detailed deliberations accepted the request of the PP and it was decided that the PP will collect one month more baseline data and submit EIA report by incorporating the fresh data accordingly. The project proponent submitted the EIA/EMP report vide letter dated 01.04.2016. Thereafter, the case was taken up in the 134th meeting of the SEAC held on 30.05.2016. During presentation, the Committee was informed that it is a Revision and Expansion of Group Housing Colony Project at Village-Bajghera, Sector-112-113, District Gurgaon, Haryana. Environment Clearance was earlier granted by State Environment Impact Assessment Authority, Haryana vide letter No. SEIAA/HR/2013/962 dated 15-10-2013 for 85,161.03 Sq. Meters (21.0437 Acres) plot area and 2,06,029.404 Sq. Meters built-up Area. The project proponent proposes to Revise & Expand the Group Housing Colony for which an application was submitted to the SEIAA, Haryana on 01.09.2015. The estimated cost of the project is Rs. 893.55Crores. Total Plot area is 21.04375 Acres (85,161.03Sq. Meters). Total built up area after expansion will be approximately 2,08,228.36 Sq. Meters. The project will comprise of Residential building, Community Building, Convenient Shopping and Schools facility. The maximum height of the building is approx. 83.7 meters. It was also informed that the green area development has been kept as 25.5% (i.e. 21,741Sq. Meters approximately) of the total plot area.955.37 Sq. Meters of the total plot area would be earmarked for green belt in the project area.14277.17Sq. Meters of the total plot area would be earmarked forperiphery plantation and grass lawn green in the project area and 6509.38Sq. Metersof the total plot area under avenue plantation on either side of the road.The total water requirement for the project will be 1157 KLD (i.e. 243KLD of fresh water for plot-I&353 KLD of fresh water for plot-II, and 245 & 368 KLD of recycled treated water for Plot-I&Plot-II respectively). The wastewater generation will be 306 KLDin plot –I & 460 KLD in plot-II, which will be treated upto tertiary level in STP having total capacity of 440 KLD in plot-I& 548 KLD in plot-II. The STP treated water will be used for flushing, horticulture and other misc. purposes.

The Air quality data shows exceeding baseline in respect of PM10 and PM2.5 parameters which ranges approximately from 108.5-245.1 and 104.3-119.9respectively. Incremental air pollution in respect of PM is 0.15 g/s. PP has submitted special mitigative measures for controlling air pollution for construction phase and operation phase which includes 5 meters high barricade wall at the periphery, broad leafy trees would be planted as green belt, trees with heavy foliage would be planted on both side of carriage way, ultra-low Page 5 of 151

sulphur Diesel (0.005%) would be used as fuel in DG Sets, Stack height of DG set would be as per CPCB norms. These measures would minimize the impact on air environment. It was informed by the project proponent that the power requirement for the project will be 9.4 MVA. Parking requirement for the project as per Haryana Bye Laws is 1575 ECS but the parking proposed to be provided in the project is 1663 ECS. There will be total solid waste generation of 3343 Kg/day. Out of this the bio-degradable waste 2005.5 Kg/day will be composted in 3 nos. of Organic Waste Convertor provided within the project premises and the manure produced will be used for horticulture and green development. The calculations of the same are in accordance with the prescribed norms. It was pointed out that the required water for the project will be provided through HUDA. Detailed discussions were held about Solid Waste Management, rain water harvesting, fire fighting plan, noise and vibration plan, health and welfare of the laborers, electrical hazard plan, environment monitoring plan, energy conservation measures and environment management plan. There will be 18 numbers of rain water harvesting structures as approved by the Central Ground Water Authority (CGWA). The mitigation measures were found in order by the Committee. The brief details of the project is as under: Sr. Particulars Existing Revision and Total No. (EC Accorded) Expansion 1. Total Plot Area 21.0437 Acres ( 85161.03 Sq. Meters) 2. Built Up Area 2,06,029.404 2198.9 2,08,228.36 3. Estimated 4425 2703 7469 Population(fixed+floating) 4. Fresh Water Requirement 302 KLD 288 KLD 590 KLD 5. Solid Waste (Kg/day 1991 1352 3343 6. Electrical Load(MVA) 4.9 4.5 9.4 7. Power Back-up (DG Sets) 9050 kVA 605 kVA 9655KVA 8. No. of RWH pits proposed 21 -2 19 9. Parking Proposed (ECS) 1823 -160 1663 10. Number of DU  General 665 367 1032  EWS 117 66 183  Service Personnel 67 41 108 11. Project Cost (INR in Crore) 800 93.55 893.55 12. Permissible Ground Coverage 29,514.53 Nil 29,514.53 (@35%) 13 Total Proposed Ground 16,047.621 592.736 15,433.46 Coverage (@19.03%) Proposed Ground Coverage for 9199.681 592.736 9792.417 Plot-I 6847 Nil 5641.043 Proposed Ground Coverage for Plot-II 14 Permissible F.A.R @ 1.75 1,47,572.688 Nil 1,47,572.688 15 Proposed F.A.R (@1.726) 1,45,586.544 1299.916 1,46,117.23 Proposed F.A.R for Plot-I (including EWS, 62m419.714 1299.916 63,719.63 Community building, convenient shopping) 83,166.83 Nil 82,397.60 Page 6 of 151

Proposed F.A.R for Plot-II (including Community building /club) 16 Area for Schools (Nursery & 409.53 2188.8 2598.33 Primary)

After deliberations the Committee rated this project with “Gold Rating” and was of the unanimous view that this case for granting Environmental Clearance under EIA Notification dated 14.9.2006 issued by the Ministry of Environment and Forest, Government of India should be recommended to the SEIAA with the following stipulations: PART A- SPECIFIC CONDITIONS:- Construction Phase:- [1] “Consent for Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. [2] A first aid room as proposed in the project report shall be provided both during construction and operational phase of the project. [3] Adequate drinking water and sanitary facilities shall be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the laboures is strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. [4] All the topsoil excavated during construction activities shall be stored for use in horticulture/landscape development within the project site. [5] The project proponent shall ensure that the building material required during construction phase is properly stored within the project area and disposal of construction waste should not create any adverse effect on the neighboring communities and should be disposed of after taking necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. [6] Construction spoils, including bituminous material and other hazardous materials, must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. [7] The diesel generator sets to be used during construction phase shall be of ultra low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standards. [8] The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. [9] Ambient noise levels shall conform to the residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air pollution and noise level during construction phase, so as to conform to the stipulated residential standards of CPCB/MoEF. [10] Fly ash shall be used as building material in the construction as per the provisions of Fly Ash Notification of September 1999 and as amended on 27th August 2003. [11] Storm water control and its re-use as per CGWB and BIS standards for various applications should be ensured. [12] Water demand during construction shall be reduced by use of pre-mixed concrete, curing agents and other best practices. [13] In view of the severe constrains in water supply augmentation in the region and sustainability of water resources, the developer will submit the NOC from CGWA Page 7 of 151

specifying water extraction quantities and assurance from HUDA/ utility provider indicating source of water supply and quantity of water with details of intended use of water – potable and non-potable. Assurance is required for both construction and operation stages separately. It shall be submitted to the SEIAA and RO, MOEF, before the start of construction. [14] Roof must meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material. [15] Opaque wall must meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is desirable for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. [16] The approval of the competent authority shall be obtained for structural safety of the building on account of earthquake, adequacy of fire fighting equipments, etc. as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site, clearance under Forest Conservation Act shall be obtained from the competent Authority. [17] Overexploited groundwater and impending severe shortage of water supply in the region requires the developer to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency /savings measures as well as water reuse/recycling within 3 months and before start of construction to the SEIAA, Haryana and RO, MOEF, GOI, Chandigarh. [18] The Project Proponent as stated in the proposal shall construct total 10 rain water harvesting pits for recharging the ground water within the project premises. Rain water harvesting pits shall be designed to make provisions for silting chamber and removal of floating matter before entering harvesting pit. Maintenance budget and persons responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RWH pit. [19] The project proponent shall provide for adequate fire safety measures and equipments as required by Haryana Fire Service Act, 2009 and instructions issued by the local Authority/ Directorate of fire from time to time. Further the project proponent shall take necessary permission regarding fire safety scheme/NOC from competent Authority as required. [20] The Project Proponent shall obtain assurance from the DHBVN for supply of 7084.82 KVA of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. [21] Detail calculation of power load and ultimate power load of the project shall be submitted to DHBVN under intimation to SEIAA Haryana before the start of construction. Provisions shall be made for electrical infrastructure in the project area. [22] The Project Proponent shall not raise any construction in the natural land depression / Nallah/water course and shall ensure that the natural flow from the Nallah/water course is not obstructed. [23] The Project Proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Project. Levels of the other areas in the Projects shall also be kept suitably so as to avoid flooding. [24] Construction shall be carried out so that density of population does not exceed norms approved by Director General Town and Country Department Haryana. [25] The Project Proponent shall submit an affidavit with the declaration that ground water will not be used for construction and only treated water should be used for construction. [26] The project proponent shall not cut any existing tree and project landscaping plan should be modified to include those trees in green area. [27] The project proponent shall provide 3 meter high barricade around the project area, dust screen for every floor above the ground, proper sprinkling and covering of stored material to restrict dust and air pollution during construction. Page 8 of 151

[28] The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. [29] The project proponent shall provide proper rasta of proper width and proper strength for the project before the start of construction. [30] The project proponent shall ensure that the U-value of the glass is less than 3.177 and maximum solar heat gain co-efficient is 0.25 for vertical fenestration. [31] The project proponent shall adequately control construction dusts like silica dust, non- silica dust and wood dust. Such dusts shall not spread outside project premises. Project Proponent shall provide respiratory protective equipment to all construction workers. [32] The project proponent shall develop complete civic infrastructure of the Group Housing colony including internal roads, green belt development, sewerage line, Rain Water recharge arrangements, Storm water drainage system, Solid waste management site and provision for treatment of bio-degradable waste, STP, water supply line, dual plumbing line, electric supply lines etc. and shall offer possession of the units/flats thereafter. [33] The project proponent shall provide one refuge area till 24 meter and one till 39 meter each, as per National Building Code. The project proponent shall not convert any refuse area in the habitable space and it should not be sold out/commercialized. [34] The project proponent shall provide fire control room and fire officer for building above 30 meter as per National Building Code. [35] The project proponent shall obtain permission of Mines and Geology Department for excavation of soil before the start of construction. [36] The project proponent shall seek specific prior approval from concerned local Authority/HUDA regarding provision of storm drainage and sewerage system including their integration with external services of HUDA/ Local authorities beside other required services before taking up any construction activity. [37] The project proponent shall submit the copy of fire safety plan duly approved by Fire Department before the start of construction. [38] The project proponent shall discharge excess of treated waste water/storm water in the public drainage system and shall seek permission of HUDA before the start of construction. [39] The project proponent shall maintain the distance between STP and water supply line. [40] The project proponent shall ensure that the stack height is 6 meter more than the highest tower. [41] The project proponent shall ensure that structural stability to withstand earthquake of magnitude 8.5 on Richter scale. Operational Phase: [a] “Consent to Operate” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana. [b] The Sewage Treatment Plant (STP) shall be installed for the treatment of the sewage to the prescribed standards including odour and treated effluent will be recycled to achieve zero exit discharge. The installation of STP shall be certified by an independent expert and a report in this regard shall be submitted to the SEIAA, Haryana before the project is commissioned for operation. Tertiary treatment of waste water is mandatory. The project proponent shall remove not only Ortho-Phosphorus but total Phosphorus to the extent of less than 2mg/liter. Similarly total Nitrogen level shall be less than 2mg/liter in tertiary treated waste water. Discharge of treated sewage shall conform to the norms and standards of CPCB/ HSPCB, whichever is environmentally better. Project Proponent shall implement such STP technology which does not require filter backwash. The project proponent shall essentially provide two numbers of STPs preferably equivalent to 50% of total capacity or as per the initial occupancy as the case may be. [c] Separation of the grey and black water should be done by the use of dual plumbing line. Treatment of 100% grey water by decentralized treatment should be done ensuring that the re-circulated water should have BOD level less than 5 mg/litre and the recycled Page 9 of 151

water will be used for flushing, gardening and DG set cooling etc. to achieve zero exit discharge. [d] For disinfection of the treated wastewater ultra-violet radiation or ozonization process should be used. [e] Diesel power generating sets proposed as source of back-up power for lifts, common area illumination and for domestic use should be of enclosed type and conform to rules made under the Environment (Protection) Act, 1986. The location of the DG sets shall be in the open as promised by the project proponent with appropriate stack height above the highest roof level of the project as per the CPCB norms. The diesel used for DG sets shall be ultra low sulphur diesel (35 ppm sulphur), instead of low sulphur diesel. [f] Ambient Noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the Proposed Affordable Group Housing Project. [g] The project proponent as stated in the proposal should maintain at least 20.10% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species which can provide protection against noise and suspended particulate matter. The open spaces inside the project shall be preferably landscaped and covered with vegetation/grass, herbs & shrubs. Only locally available plant species shall be used. [h] The project proponent shall strive to minimize water in irrigation of landscape by minimizing grass area, using native variety, xeriscaping and mulching, utilizing efficient irrigation system, scheduling irrigation only after checking evapo-transpiration data. [i] Rain water harvesting for roof run-off and surface run-off, as per plan submitted should be implemented. Before recharging the surface run off, pre- treatment through sedimentation tanks must be done to remove suspended matter, oil and grease. The bore well for rainwater recharging shall be kept at least 5 mts. above the highest ground water table. Care shall be taken that contaminated water do not enter any RWH pit. The project proponent shall avoid Rain Water Harvesting of first 10 minutes of rain fall. Roof top of the building shall be without any toxic material or paint which can contaminate rain water. Wire mess and filters should be used wherever required. [j] The ground water level and its quality should be monitored regularly in consultation with Central Ground Water Authority. [k] A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about building materials & technology, R & U Factors etc and submitted to the SEIAA, Haryana in three months time. [l] Energy conservation measures like installation of LED only for lighting the areas outside the building and inside the building should be integral part of the project design and should be in place before project commissioning. Use of solar panels must be adapted to the maximum energy conservation. [m] The Project Proponent shall use zero ozone depleting potential material in insulation, refrigeration, air-conditioning and adhesive. Project Proponent shall also provide Halon free fire suppression system. [n] The solid waste generated should be properly collected and segregated as per the requirement of the MSW Rules, 2016 and as amended from time to time. The bio- degradable waste should be treated by appropriate technology (proposed OWC) at the site ear-marked within the project area and dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material. [o] The provision of the solar water heating system shall be as per norms specified by HAREDA and shall be made operational in each building block. [p] The traffic plan and the parking plan proposed by the Project Proponent should be adhered to meticulously with further scope of additional parking for future requirement. There should be no traffic congestion near the entry and exit points from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be used. Page 10 of 151

[q] The Project shall be operationalized only when HUDA/local authority will provide domestic water supply system in the area. [r] Operation and maintenance of STP, solid waste management and electrical Infrastructure, pollution control measures shall be ensured even after the completion of project. [s] Different type of wastes should be disposed off as per provisions of municipal solid waste, biomedical waste, hazardous waste, e-waste, batteries & plastic rules made under Environment Protection Act, 1986. Particularly E-waste and Battery waste shall be disposed of as per existing E-waste Management Rules 2011 and Batteries Management Rules 2001. The project proponent should maintain a collection center for E-waste and it shall be disposed of to only registered and authorized dismantler / recycler. [t] Standards for discharge of environmental pollutants as enshrined in various schedules of rule 3 of Environment Protection Rule 1986 shall be strictly complied with. [u] Water supply shall be metered among different users and different utilities. [v] The project proponent shall ensure that the of DG sets is more than the highest tower and also ensure that the emission standards of noise and air are within the CPCB latest prescribed limits. Noise and Emission level of DG sets greater than 800 KVA shall be as per CPCB latest standards for high capacity DG sets. [w] All electric supply exceeding 100 amp, 3 phase shall maintain the power factor between 0.98 lag to 1 at the point of connection. [x] The project proponent shall not use fresh water for HVAC and DG cooling. Air based HVAC system should be adopted and only treated water shall be used by project proponent for cooling, if it is at all needed. The Project Proponent shall also use evaporative cooling technology and double stage cooling system for HVAC in order to reduce water consumption. Further temperature, relative humidity during summer and winter seasons should be kept at optimal level. Variable speed drive, best Co-efficient of Performance (CoP), as well as optimal Integrated Point Load Value and minimum outside fresh air supply may be resorted for conservation of power and water. Coil type cooling DG Sets shall be used for saving cooling water consumption for water cooled DG Sets. [y] The project proponent shall ensure that the transformer is constructed with high quality grain oriented, low loss silicon steel and virgin electrolyte grade copper. The project proponent shall obtain manufacturer’s certificate also for that. [z] The project proponent shall ensure that exit velocity from the stack should be sufficiently high. Stack shall be designed in such a way that there is no stack down-wash under any meteorological conditions. [aa] The project proponent shall provide water sprinkling system in the project area to suppress the dust in addition to the already suggested mitigation measures in the Air Environment Chapter of EMP. [ab] The project proponent shall ensure proper Air Ventilation and light system in the basements area for comfortable living of human being and shall ensure that number of Air Changes per hour/(ACH) in basement never falls below 15. In case of emergency capacity for increasing ACH to the extent of 30 must be provided by the project proponent. [ac] The project proponent shall ensure drinking/ domestic water supply as per prescribed standards till treated water supply is made available by HUDA. [ad] The project proponent shall install solar panel for energy conservation. PART-B. GENERAL CONDITIONS: [i] The Project Proponent shall ensure the commitments made in Form-1, Form-1A, EIA/EMP and other documents submitted to the SEIAA for the protection of environment and proposed environmental safeguards are complied with in letter and spirit. In case of contradiction between two or more documents on any point, the most environmentally friendly commitment on the point shall be taken as commitment by project proponent. [ii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies Page 11 of 151

as well as by e-mail) to the northern Regional Office of MoEF, the respective Zonal Office of CPCB, HSPCB and SEIAA Haryana. [iii] STP outlet after stabilization and stack emission shall be monitored monthly. Other environmental parameters and green belt shall be monitored on quarterly basis. After every 3 (three) months, the project proponent shall conduct environmental audit and shall take corrective measure, if required, without delay. [iv] The SEIAA, Haryana reserves the right to add additional safeguard measures subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/MoEF. [v] The Project proponent shall not violate any judicial orders/pronouncements issued by any Court/Tribunal. [vi] All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (Protection) Act, 1972, Forest Act, 1927, PLPA 1900, etc. shall be obtained, as applicable by project proponents from the respective authorities prior to construction of the project. [vii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [viii] Under the provisions of Environment (Protection) Act, 1986, legal action shall be initiated against the Project Proponent if it was found that construction of the project has been started before obtaining prior Environmental Clearance. [ix] Any appeal against the this Environmental Clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010. [x] The project proponent shall put in place Corporate Environment Policy as mentioned in MoEF, GoI OM No. J-11013/41/2006-IA II (I) dated 26.4.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issuance of this letter. [xi] The fund ear-marked for environment protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO MOEF GOI under rules prescribed for Environment Audit. [xii] The project proponent shall ensure the compliance of Forest Department, Haryana Notification no. S.O.121/PA2/1900/S.4/97 dated 28.11.1997. [xiii] The Project Proponent shall ensure that no vehicle during construction/operation phase enter the project premises without valid ‘Pollution Under Control’ certificate from competent Authority. [xiv] The project proponent is responsible for compliance of all conditions in Environmental Clearance letter and project proponent can not absolve himself /herself of the responsibility by shifting it to any contractor engaged by project proponent. [xv] The project proponent shall seek fresh Environmental clearance if at any stage there is change in the planning of the proposed project. [xvi] Besides the developer/applicant, the responsibility to ensure the compliance of Environmental Safeguards/conditions imposed in the Environmental Clearance letter shall also lie on the licensee/licensees in whose name/names the license/CLU has been granted by the Town & Country Planning Department, Haryana. [xvii] The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same Page 12 of 151

periodically. It shall simultaneously be sent to the Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SOX NOX, Ozone, Lead, CO, Benzene, Ammonia, Benzopyrine, arsenic and Nickel. (Ambient levels as well as stack emissions) or critical sectoral parameters, indicated for the project shall be monitored and displayed at a convenient location near the main gate of the company in the public domain. [xviii] The environmental statement for each financial year ending 31st March in Form-V as is mandated to be submitted by the project proponent to the HSPCB Panchkula as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be put on the website of the company along with the status of compliance of the EC conditions and shall also be sent to the respective Regional Offices of MoEF by e- mail. [xix] The project proponent shall conduct environment audit at every three months interval and thereafter corrected measures shall be taken without any delay. Details of environmental audit and corrective measures shall be submitted in the monitoring report. [xx] Corporate Environment and Social Responsibility (CSER) shall be laid down by the project proponent (2% shall be earmarked) as per guidelines of MoEF, GoI Office Memorandum No. J-11013/41/2006-IA.II(I) dated 18.05.2012 and Ministry of Corporate Affairs, GoI Notification Dated 27.02.2014. A separate audit statement shall be submitted in the compliance. Environment related work proposed to be executed under this responsibility shall be undertaken simultaneously. The project proponent shall select and prepare the list of the work for implementation of CSER of its own choice and shall submit the same before the start of construction. 134.03 Environmental Clearance for the proposed Expansion of Group Housing Complex, Sector-3, Bahadurgarh by M/s Kashi Promoters Pvt. Ltd. Project Proponent : Sh. Asit Kumar Das, Director Consultant : Perfect Enviro Solutions Pvt. Ltd. The project proponent submitted the case for obtaining Environmental Clearance to the SEIAA, Haryana on 24.12.2014 as per check list approved by the SEIAA/SEAC. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter the case was taken up for appraisal in the 119th meeting of the SEAC held on 21.10.2015. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit ground water site specific hydrological details alongwith infiltration rate of recharge pit and resubmit recharge plan maintenance plan accordingly. 2. The PP should submit permission from Competent Authority for using Revenue Rasta for laying of services. 3. The PP should submit a detailed clarification from HUDA regarding availability of water in the area and corresponding summation of commitments made so far to be obtained by the PP from HUDA in the concerned area. 4. The PP should submit an undertaking for using low NOX DG sets. 5. The PP should submit detailed green belt plan viz: Page 13 of 151

(a) Width, length and area to be covered under the green belt; (b) Number of rows of trees to be planted; and (c) Tree species required to be planted and spacing to be maintained between them depending on the local climate and site conditions. (d) As the purpose of raising green belt is to reduce air/noise pollution, suitable plantation models may be evolved. The observations of 119th meeting were conveyed to the PP vide letter No. 141 dated 02.11.2015. The PP submitted the reply on 26.02.2016. Thereafter the case was taken up in the 130th meeting of the SEAC held on 29.03.2016. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit ground water site specific hydrological details alongwith infiltration rate of recharge pit and resubmit recharge plan maintenance plan accordingly. 2. The PP should submit detailed green belt plan viz: (a) Width, length and area to be covered under the green belt; (b) Number of rows of trees to be planted; and (c) Tree species required to be planted and spacing to be maintained between them depending on the local climate and site conditions. (d) As the purpose of raising green belt is to reduce air/noise pollution, suitable plantation models may be evolved. The observations of 130th meeting were conveyed to the PP vide letter No. 828 dated 08.04.2016. The PP submitted the reply on 12.04.2016. Thereafter the case was taken up in the 134th meeting of the SEAC held on 30.04.2016. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit ground water site specific hydrological details alongwith infiltration rate of recharge pit and resubmit recharge plan maintenance plan accordingly.

The PP is advised to submit the required information as detailed above within 30 days and it was also made clear to the PP that his project will be considered as received only after the receipt of complete information. In case of non-receipt of information in time; the case shall be recommended for rejection/ filing. 134.04 EC for Global Industrial Park at Sector- 72 and 73, District Faridabad, Haryana by M/s Vashisth Builders and Engineers Limited Project Proponent : Sh. Swantantar Keserwani, Authorized Signatory Consultant : Grass Roots Research and Creation India Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 15.04.2013. The papers submitted were examined by the Secretary, SEAC and certain shortcomings were noticed which were conveyed to project proponent vide letter No. 59 dated 15.04.2013. The PP submitted the reply of the shortcomings on 15.05.2013. This case was taken up for approval of Terms of Reference (ToR) in 86th meeting of the SEAC held on 09.07.2013. The Terms of Reference were approved and conveyed to the project proponent vide letter No. HR/SEAC/447/495 dated Page 14 of 151

15.07.2013. The project proponent submitted the EIA report on 03.09.2013 on the basis of Terms of Reference approved by the Committee.

The case was taken up for appraisal in the 103rd meeting of the SEAC held on 24.04.2014. The case was appraised by the SEAC and recommended to the SEIAA for granting Environmental Clearance on 10.03.2014. The case was taken up by the SEIAA in the 72nd meeting held on 18.07.2014. The SEIAA referred back the case to SEAC with the advice to appraise this project as category 8(b) in the light of amendment to the Notification dated 26.02.2014 issued by the MoEF, GoI. The case was discussed in the 108th meeting of the SEAC held on 22.07.2014. It was unanimously decided that project proponent be directed to submit the revised EIA/EMP by incorporating one season baseline data. The observations of 108th meeting were conveyed to the project proponent vide letter No. 1541 dated 08.08.2014. The project proponent submitted the revised EIA report on 29.01.2015 on the basis of Terms of Reference approved by the Committee. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter, the case was taken up for appraisal in the 121st meeting of the SEAC held on 18.11.2015. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit the assurance of the supply of the water during construction phase from safe area through tankers and permission from CGWA for using the ground water of the existing borewells including permission from HUDA for supply of water during operation Phase with detailed clarification regarding availability of water in the area. 2. The PP should submit assurance from Electricity Department. 3. The PP should submit an undertaking that they shall not encroach MITC Canal land adjacent to their project site. 4. The PP should submit details of incremental pollution load from DG Sets alongwith mitigation measures. 5. The PP should submit detailed design calculations of STP alongwith dimension of each component and also submit unit wise reduction of BOD for STP. 6. The PP should submit revised plan of Rain Water Harvesting pits alongwith detail design and recharge capacity of recharge pit and should submit Rain water harvesting maintenance plan and should submit the detail computation of rainfall runoff generation from common areas not covered under the individual plots for rain water harvesting. 7. The PP should submit revised water requirement inclusive of water to be used by prospecting industries or submit an affidavit to the effect that there shall be no requirement of water for industrial purpose in the estate. 8. The PP should submit an affidavit that the Industrial Estate shall not have any category A or B industries and in that case the project would be considered as Category 7(c), if there is any Category A and B Industry that the PP should go for Public Hearing. 9. The PP should submit detailed green belt plan viz: Page 15 of 151

(a) Width, length and area to be covered under the green belt; (b) Number of rows of trees to be planted; and (c) Tree species required to be planted and spacing to be maintained between them depending on the local climate and site conditions. The observations of 121st meeting were conveyed to the PP vide letter No. 295 dated 01.12.2015. The PP submitted the reply on 12.04.2016. Thereafter the case was taken up in the 134th meeting of the SEAC held on 30.05.2016. During presentation, the Committee was informed that it is an Industrial Colony Project “Global Industrial Park” at Sector 72 and 73, District Faridabad, Haryana. The estimated cost of the project is Rs. 200 Crores. Total Plot area is 52.92 Acres (2,14,153.7Sq. Meters). Total built up area will be approximately 1,64,669.01 Sq. Meters. The maximum height of the building is approx. 30 meters. It was also informed that the green area development has been kept as 30.07% (i.e. 64,380.38 Sq. Meter approximately) of the total plot area. 2,14,153.7 Sq. Meters of the total plot area would be earmarked for grass lawn green in the project area. The total Greenbelt Plantation is 1179.34 Sq. Meters, Periphery Plantation is 8482.28 Sq. Meters, Avenue Plantation of 24660.17 Sq. Meters and Lawn is 30058.59 Sq. Meters. The total water requirement for the project will be 966 KLD (i.e. 493KLD of fresh water & 483 KLD of recycled treated water). The waste water generation will be 605 KLD which will be treated up to tertiary level in STPs having total capacity of 730(270 + 120 + 215 + 125) KLD. The STPs treated water will be used for flushing, horticulture and other misc. purposes. The project proponent further informed that the project will house non-polluting industries such as electrical and electronic item, manufacturing of shoe brush and wire brush, packing of powder milk, soft toy etc for which they have permission from Joint Director, District Industries Centre, Faridabad vide letter no.DIC/Fbd/Admn/RC 2307 Dated 09.03.2015. An affidavit was also submitted by the project proponent stating that the Industrial Estate shall not have any category A or B Industries.

The Air quality data shows exceeding baseline in respect of PM10 and PM2.5 parameters which ranges approximately from 63.1-111.4 and 57.3-81.7 respectively. Incremental air pollution in respect of PM is 2.06 g/s. PP has submitted special mitigative measures for controlling air pollution for construction phase and operation phase which includes 5 meters high barricade wall at the periphery, broad leafy trees would be planted as green belt, trees with heavy foliage would be planted on both side of carriage way, ultralowsulphur Diesel (5 ppm) would be used as fuel in DG Sets, Stack height of DG set would be as per CPCB norms. These measures would minimize the impact on air environment. It was informed by the project proponent that the power requirement for the project will be 11,423KVA and for power back up they will install 45 DG Sets of 8700KVA capacity. Parking space will be provided within the project site by individual plot owners. There will be total solid waste generation of 4012 Kg/day. Out of this the bio-degradable waste 2000 kg/day will be composted in 2 nos. of Organic Waste Convertor provided within the project Page 16 of 151

premises and the manure produced will be used for horticulture and green development. The calculations of the same are in accordance with the prescribed norms. It was pointed out that the required water for the project will be provided through HUDA Municipal supply. Detailed discussions were held about Solid Waste Management, rain water harvesting, firefighting plan, noise and vibration plan, health and welfare of the laborers, electrical hazard plan, environment monitoring plan, energy conservation measures and environment management plan. There will be 53 rain water harvesting structures as approved by the Central Ground Water Authority (CGWA). The mitigation measures were found in order by the Committee. After deliberations the Committee rated this project with “Gold Rating” and was of the unanimous view that this case for granting Environmental Clearance under EIA Notification dated 14.9.2006 issued by the Ministry of Environment and Forest, Government of India should be recommended to the SEIAA with the following stipulations: PART A- SPECIFIC CONDITIONS:- Construction Phase:- [1] “Consent for Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. [2] A first aid room as proposed in the project report shall be provided both during construction and operational phase of the project. [3] Adequate drinking water and sanitary facilities shall be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the laboures is strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. [4] All the topsoil excavated during construction activities shall be stored for use in horticulture/landscape development within the project site. [5] The project proponent shall ensure that the building material required during construction phase is properly stored within the project area and disposal of construction waste should not create any adverse effect on the neighboring communities and should be disposed of after taking necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. [6] Construction spoils, including bituminous material and other hazardous materials, must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. [7] The diesel generator sets to be used during construction phase shall be of ultra low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standards. [8] The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. [9] Ambient noise levels shall conform to the residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air pollution and noise level during construction phase, so as to conform to the stipulated residential standards of CPCB/MoEF. [10] Fly ash shall be used as building material in the construction as per the provisions of Fly Ash Notification of September 1999 and as amended on 27th August 2003. Page 17 of 151

[11] Storm water control and its re-use as per CGWB and BIS standards for various applications should be ensured. [12] Water demand during construction shall be reduced by use of pre-mixed concrete, curing agents and other best practices. [13] In view of the severe constrains in water supply augmentation in the region and sustainability of water resources, the developer will submit the NOC from CGWA specifying water extraction quantities and assurance from HUDA/ utility provider indicating source of water supply and quantity of water with details of intended use of water – potable and non-potable. Assurance is required for both construction and operation stages separately. It shall be submitted to the SEIAA and RO, MOEF, Chandigarh before the start of construction. [14] Roof must meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material. [15] Opaque wall must meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is desirable for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. [16] The approval of the competent authority shall be obtained for structural safety of the building on account of earthquake, adequacy of fire fighting equipments, etc. as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site, clearance under Forest Conservation Act shall be obtained from the competent Authority. [17] Overexploited groundwater and impending severe shortage of water supply in the region requires the developer to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency /savings measures as well as water reuse/recycling within 3 months and before start of construction to the SEIAA, Haryana and RO, MOEF, GOI, Chandigarh. [18] The Project Proponent as stated in the proposal shall construct total 10 rain water harvesting pits for recharging the ground water within the project premises. Rain water harvesting pits shall be designed to make provisions for silting chamber and removal of floating matter before entering harvesting pit. Maintenance budget and persons responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RWH pit. [19] The project proponent shall provide for adequate fire safety measures and equipments as required by Haryana Fire Service Act, 2009 and instructions issued by the local Authority/ Directorate of fire from time to time. Further the project proponent shall take necessary permission regarding fire safety scheme/NOC from competent Authority as required. [20] The Project Proponent shall obtain assurance from the DHBVN for supply of 7084.82 KVA of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. [21] Detail calculation of power load and ultimate power load of the project shall be submitted to DHBVN under intimation to SEIAA Haryana before the start of construction. Provisions shall be made for electrical infrastructure in the project area. [22] The Project Proponent shall not raise any construction in the natural land depression / Nallah/water course and shall ensure that the natural flow from the Nallah/water course is not obstructed. [23] The Project Proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Project. Levels of the other areas in the Projects shall also be kept suitably so as to avoid flooding. [24] Construction shall be carried out so that density of population does not exceed norms approved by Director General Town and Country Department Haryana. [25] The Project Proponent shall submit an affidavit with the declaration that ground water will not be used for construction and only treated water should be used for construction. Page 18 of 151

[26] The project proponent shall not cut any existing tree and project landscaping plan should be modified to include those trees in green area. [27] The project proponent shall provide 3 meter high barricade around the project area, dust screen for every floor above the ground, proper sprinkling and covering of stored material to restrict dust and air pollution during construction. [28] The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. [29] The project proponent shall provide proper rasta of proper width and proper strength for the project before the start of construction. [30] The project proponent shall ensure that the U-value of the glass is less than 3.177 and maximum solar heat gain co-efficient is 0.25 for vertical fenestration. [31] The project proponent shall adequately control construction dusts like silica dust, non- silica dust and wood dust. Such dusts shall not spread outside project premises. Project Proponent shall provide respiratory protective equipment to all construction workers. [32] The project proponent shall develop complete civic infrastructure of the Group Housing colony including internal roads, green belt development, sewerage line, Rain Water recharge arrangements, Storm water drainage system, Solid waste management site and provision for treatment of bio-degradable waste, STP, water supply line, dual plumbing line, electric supply lines etc. and shall offer possession of the units/flats thereafter. [33] The project proponent shall provide one refuge area till 24 meter and one till 39 meter each, as per National Building Code. The project proponent shall not convert any refuse area in the habitable space and it should not be sold out/commercialized. [34] The project proponent shall provide fire control room and fire officer for building above 30 meter as per National Building Code. [35] The project proponent shall obtain permission of Mines and Geology Department for excavation of soil before the start of construction. [36] The project proponent shall seek specific prior approval from concerned local Authority/HUDA regarding provision of storm drainage and sewerage system including their integration with external services of HUDA/ Local authorities beside other required services before taking up any construction activity. [37] The project proponent shall submit the copy of fire safety plan duly approved by Fire Department before the start of construction. [38] The project proponent shall discharge excess of treated waste water/storm water in the public drainage system and shall seek permission of HUDA before the start of construction. [39] The project proponent shall maintain the distance between STP and water supply line. [40] The project proponent shall ensure that the stack height is 6 meter more than the highest tower. [41] The project proponent shall ensure that structural stability to withstand earthquake of magnitude 8.5 on Richter scale. Operational Phase: [a] “Consent to Operate” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana. [b] The Sewage Treatment Plant (STP) shall be installed for the treatment of the sewage to the prescribed standards including odour and treated effluent will be recycled to achieve zero exit discharge. The installation of STP shall be certified by an independent expert and a report in this regard shall be submitted to the SEIAA, Haryana before the project is commissioned for operation. Tertiary treatment of waste water is mandatory. The project proponent shall remove not only Ortho-Phosphorus but total Phosphorus to the extent of less than 2mg/liter. Similarly total Nitrogen level shall be less than 2mg/liter in tertiary treated waste water. Discharge of treated sewage shall conform to the norms and standards of CPCB/ HSPCB, whichever is environmentally better. Project Proponent shall implement such STP technology which does not require filter backwash. The project Page 19 of 151

proponent shall essentially provide two numbers of STPs preferably equivalent to 50% of total capacity or as per the initial occupancy as the case may be. [c] Separation of the grey and black water should be done by the use of dual plumbing line. Treatment of 100% grey water by decentralized treatment should be done ensuring that the re-circulated water should have BOD level less than 5 mg/litre and the recycled water will be used for flushing, gardening and DG set cooling etc. to achieve zero exit discharge. [d] For disinfection of the treated wastewater ultra-violet radiation or ozonization process should be used. [e] Diesel power generating sets proposed as source of back-up power for lifts, common area illumination and for domestic use should be of enclosed type and conform to rules made under the Environment (Protection) Act, 1986. The location of the DG sets shall be in the open as promised by the project proponent with appropriate stack height above the highest roof level of the project as per the CPCB norms. The diesel used for DG sets shall be ultra low sulphur diesel (35 ppm sulphur), instead of low sulphur diesel. [f] Ambient Noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the Proposed Affordable Group Housing Project. [g] The project proponent as stated in the proposal should maintain at least 20.10% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species which can provide protection against noise and suspended particulate matter. The open spaces inside the project shall be preferably landscaped and covered with vegetation/grass, herbs & shrubs. Only locally available plant species shall be used. [h] The project proponent shall strive to minimize water in irrigation of landscape by minimizing grass area, using native variety, xeriscaping and mulching, utilizing efficient irrigation system, scheduling irrigation only after checking evapo-transpiration data. [i] Rain water harvesting for roof run-off and surface run-off, as per plan submitted should be implemented. Before recharging the surface run off, pre- treatment through sedimentation tanks must be done to remove suspended matter, oil and grease. The bore well for rainwater recharging shall be kept at least 5 mts. above the highest ground water table. Care shall be taken that contaminated water do not enter any RWH pit. The project proponent shall avoid Rain Water Harvesting of first 10 minutes of rain fall. Roof top of the building shall be without any toxic material or paint which can contaminate rain water. Wire mess and filters should be used wherever required. [j] The ground water level and its quality should be monitored regularly in consultation with Central Ground Water Authority. [k] A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about building materials & technology, R & U Factors etc and submitted to the SEIAA, Haryana in three months time. [l] Energy conservation measures like installation of LED only for lighting the areas outside the building and inside the building should be integral part of the project design and should be in place before project commissioning. Use of solar panels must be adapted to the maximum energy conservation. [m] The Project Proponent shall use zero ozone depleting potential material in insulation, refrigeration, air-conditioning and adhesive. Project Proponent shall also provide Halon free fire suppression system. [n] The solid waste generated should be properly collected and segregated as per the requirement of the MSW Rules, 2016 and as amended from time to time. The bio- degradable waste should be treated by appropriate technology (proposed OWC) at the site ear-marked within the project area and dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material. [o] The provision of the solar water heating system shall be as per norms specified by HAREDA and shall be made operational in each building block. Page 20 of 151

[p] The traffic plan and the parking plan proposed by the Project Proponent should be adhered to meticulously with further scope of additional parking for future requirement. There should be no traffic congestion near the entry and exit points from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be used. [q] The Project shall be operationalized only when HUDA/local authority will provide domestic water supply system in the area. [r] Operation and maintenance of STP, solid waste management and electrical Infrastructure, pollution control measures shall be ensured even after the completion of project. [s] Different type of wastes should be disposed off as per provisions of municipal solid waste, biomedical waste, hazardous waste, e-waste, batteries & plastic rules made under Environment Protection Act, 1986. Particularly E-waste and Battery waste shall be disposed of as per existing E-waste Management Rules 2011 and Batteries Management Rules 2001. The project proponent should maintain a collection center for E-waste and it shall be disposed of to only registered and authorized dismantler / recycler. [t] Standards for discharge of environmental pollutants as enshrined in various schedules of rule 3 of Environment Protection Rule 1986 shall be strictly complied with. [u] Water supply shall be metered among different users and different utilities. [v] The project proponent shall ensure that the of DG sets is more than the highest tower and also ensure that the emission standards of noise and air are within the CPCB latest prescribed limits. Noise and Emission level of DG sets greater than 800 KVA shall be as per CPCB latest standards for high capacity DG sets. [w] All electric supply exceeding 100 amp, 3 phase shall maintain the power factor between 0.98 lag to 1 at the point of connection. [x] The project proponent shall not use fresh water for HVAC and DG cooling. Air based HVAC system should be adopted and only treated water shall be used by project proponent for cooling, if it is at all needed. The Project Proponent shall also use evaporative cooling technology and double stage cooling system for HVAC in order to reduce water consumption. Further temperature, relative humidity during summer and winter seasons should be kept at optimal level. Variable speed drive, best Co-efficient of Performance (CoP), as well as optimal Integrated Point Load Value and minimum outside fresh air supply may be resorted for conservation of power and water. Coil type cooling DG Sets shall be used for saving cooling water consumption for water cooled DG Sets. [y] The project proponent shall ensure that the transformer is constructed with high quality grain oriented, low loss silicon steel and virgin electrolyte grade copper. The project proponent shall obtain manufacturer’s certificate also for that. [z] The project proponent shall ensure that exit velocity from the stack should be sufficiently high. Stack shall be designed in such a way that there is no stack down-wash under any meteorological conditions. [aa] The project proponent shall provide water sprinkling system in the project area to suppress the dust in addition to the already suggested mitigation measures in the Air Environment Chapter of EMP. [ab] The project proponent shall ensure proper Air Ventilation and light system in the basements area for comfortable living of human being and shall ensure that number of Air Changes per hour/(ACH) in basement never falls below 15. In case of emergency capacity for increasing ACH to the extent of 30 must be provided by the project proponent. [ac] The project proponent shall ensure drinking/ domestic water supply as per prescribed standards till treated water supply is made available by HUDA. [ad] The project proponent shall install solar panel for energy conservation. PART-B. GENERAL CONDITIONS: [i] The Project Proponent shall ensure the commitments made in Form-1, Form-1A, EIA/EMP and other documents submitted to the SEIAA for the protection of environment and proposed environmental safeguards are complied with in letter and spirit. In case of contradiction between two or more documents on any point, the most Page 21 of 151

environmentally friendly commitment on the point shall be taken as commitment by project proponent. [ii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Zonal Office of CPCB, HSPCB and SEIAA Haryana. [iii] STP outlet after stabilization and stack emission shall be monitored monthly. Other environmental parameters and green belt shall be monitored on quarterly basis. After every 3 (three) months, the project proponent shall conduct environmental audit and shall take corrective measure, if required, without delay. [iv] The SEIAA, Haryana reserves the right to add additional safeguard measures subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/MoEF. [v] The Project proponent shall not violate any judicial orders/pronouncements issued by any Court/Tribunal. [vi] All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (Protection) Act, 1972, Forest Act, 1927, PLPA 1900, etc. shall be obtained, as applicable by project proponents from the respective authorities prior to construction of the project. [vii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [viii] Under the provisions of Environment (Protection) Act, 1986, legal action shall be initiated against the Project Proponent if it was found that construction of the project has been started before obtaining prior Environmental Clearance. [ix] Any appeal against the this Environmental Clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010. [x] The project proponent shall put in place Corporate Environment Policy as mentioned in MoEF, GoI OM No. J-11013/41/2006-IA II (I) dated 26.4.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issuance of this letter. [xi] The fund ear-marked for environment protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO MOEF GOI under rules prescribed for Environment Audit. [xii] The project proponent shall ensure the compliance of Forest Department, Haryana Notification no. S.O.121/PA2/1900/S.4/97 dated 28.11.1997. [xiii] The Project Proponent shall ensure that no vehicle during construction/operation phase enter the project premises without valid ‘Pollution Under Control’ certificate from competent Authority. [xiv] The project proponent is responsible for compliance of all conditions in Environmental Clearance letter and project proponent can not absolve himself /herself of the responsibility by shifting it to any contractor engaged by project proponent. [xv] The project proponent shall seek fresh Environmental clearance if at any stage there is change in the planning of the proposed project. [xvi] Besides the developer/applicant, the responsibility to ensure the compliance of Environmental Safeguards/conditions imposed in the Environmental Clearance letter Page 22 of 151

shall also lie on the licensee/licensees in whose name/names the license/CLU has been granted by the Town & Country Planning Department, Haryana. [xvii] The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SOX NOX, Ozone, Lead, CO, Benzene, Ammonia, Benzopyrine, arsenic and Nickel. (Ambient levels as well as stack emissions) or critical sectoral parameters, indicated for the project shall be monitored and displayed at a convenient location near the main gate of the company in the public domain. [xviii] The environmental statement for each financial year ending 31st March in Form-V as is mandated to be submitted by the project proponent to the HSPCB Panchkula as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be put on the website of the company along with the status of compliance of the EC conditions and shall also be sent to the respective Regional Offices of MoEF by e- mail. [xix] The project proponent shall conduct environment audit at every three months interval and thereafter corrected measures shall be taken without any delay. Details of environmental audit and corrective measures shall be submitted in the monitoring report. [xx] Corporate Environment and Social Responsibility (CSER) shall be laid down by the project proponent (2% shall be earmarked) as per guidelines of MoEF, GoI Office Memorandum No. J-11013/41/2006-IA.II(I) dated 18.05.2012 and Ministry of Corporate Affairs, GoI Notification Dated 27.02.2014. A separate audit statement shall be submitted in the compliance. Environment related work proposed to be executed under this responsibility shall be undertaken simultaneously. The project proponent shall select and prepare the list of the work for implementation of CSER of its own choice and shall submit the same before the start of construction.

134.05 Environmental Clearance for the proposed construction of Affordable Group Housing, Sector-45, Village Uchana, District by M/s CHD Developers Ltd.

Project Proponent : Sh. Anil Rawal, Authorised Signatory Consultant : Perfect Enviro Solutions Pvt. Ltd. The project proponent submitted the case for obtaining Environmental Clearance to the SEIAA, Haryana on 15.12.2014 as per check list approved by the SEIAA/SEAC. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter the case was taken up for appraisal in the 119th meeting of the SEAC held on 20.10.2015. After detailed discussions, the following shortcomings were observed: 1. The PP should submit copy of permission from Central Ground Water Authority for water to be extracted and/or detailed clarification from HUDA regarding availability of water in the area and corresponding summation of commitments made so far to be obtained by the PP from HUDA in the concerned area. 2. The PP should submit site specific hydrological details alongwith detail design and infiltration rate of recharge pit and maintenance plan. Page 23 of 151

3. The PP should submit detailed design calculations of STP alongwith dimensions of each component alongwith ventilation plan showing exhaust of STP with elevation. 4. PP should submit surface/stilt/basement parking plan along with details of parking space provided for 2 wheelers & cars. 5. PP should submit revised site plan showing:  Electric panel room & other constructions within zoned area only.  Location of basement. 6. PP should submit ground excavation plan showing quantity of soil excavated & its disposal. 7. Revised Built-up Area Statement to include balconies in the Non F.A.R. areas which has not been taken into account. 8. The PP should submit detailed green belt plan viz: (a) Width, length and area to be covered under the green belt; (b) Number of rows of trees to be planted; and (c) Tree species required to be planted and spacing to be maintained between them depending on the local climate and site conditions. The observations of 119th meeting were conveyed to the PP vide letter No. 148 dated 02.11.2015. The PP submitted the reply on 20.04.2016. Thereafter the case was taken up in the 134th meeting of the SEAC held on 30.04.2016. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit copy of permission from Central Ground Water Authority for water to be extracted and/or detailed clarification from HUDA regarding availability of water in the area and corresponding summation of commitments made so far to be obtained by the PP from HUDA in the concerned area. 2. The PP should submit site specific hydrological details alongwith detail design and infiltration rate of recharge pit and maintenance plan. 3. The PP should submit ground excavation plan showing quantity of soil excavated & its disposal. 4. The PP should submit surface/stilt/basement parking plan along with details of parking space provided for 2 wheelers & cars. 5. The PP should submit detailed green belt plan viz: (a) Width, length and area to be covered under the green belt; (b) Number of rows of trees to be planted; and (c) Tree species required to be planted and spacing to be maintained between them depending on the local climate and site conditions. The PP is advised to submit the required information as detailed above within 30 days and it was also made clear to the PP that his project will be considered as received only after the receipt of complete information. In case of non-receipt of information in time; the case shall be recommended for rejection/ filing.

Page 24 of 151

134.06 Revision and Extension in Environment Clearance for Commercial Complex at Sector-19, village Kamaspur, Sonipat, Haryana by M/s TDI Infrastructure Ltd. The project was submitted to the SEIAA, Haryana on 20.04.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 134th meeting of the SEAC held on 30.05.2016.

The Project Proponent requested for adjournment and the same was discussed in the meeting. The Committee acceded to the request and decided to issue 30 days notice to the PP. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent.

134.07 EC for construction of IT Park/Unit (1.2 Acres) at Village Dundahera, Sector-19, District-Gurgaon, Haryana by M/s Pursarth Infrastructures Pvt. Ltd. Project Proponent : Sh. Ishad Ahmed, Authorised Signatory. Consultant : Vardan EnviroNet Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 26.11.2015. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. Thereafter the case was taken up in the 130th meeting of the SEAC held on 29.03.2016. The case was not heard as the project proponent failed to circulate the documents (Form 1, Form 1A and Conceptual Plan) to all the Members well in time. The project proponent had undertaken to circulate the documents to all the Members well in time and requested for considering their case for appraisal in the next meeting of the SEAC. It was unanimously decided by the Committee that the case will be considered in the next meeting of the SEAC to be held on 07th April, 2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC. The case was taken up in the 131st meeting of the SEAC held on 07.04.2016. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit contour sheet of the area alongwith demarcation of the project on the contour sheet. 2. The PP should submit detailed design calculations of STP alongwith dimension of each component and also submit unit wise reduction of BOD for STP. The observations of 131st meeting were conveyed to the project proponent vide letter No. 876 dated 20.04.2016. The PP submitted the reply vide letter dated 21.04.2016. Thereafter the case was taken up in the 134th meeting of the SEAC held on 30.05.2016.

During presentation, the committee was informed that it is a proposed construction of IT Park/Unit at Village Dundahera, Sector-19, District-Gurgaon, Haryana. The estimated cost of the project is Rs. 55 Crores. Total Plot area of the project is 7041.519 Sq. Meters (1.74 Acre) and net plot area is 4856.22 Sq. Meters (1.20 Acres). Total Built up area will be approx. 22673.25 Sq. Meters. The Project will comprise of three basements, IT offices & commercial area. The height of the building will be 37.55 meters. It is also informed that the green belt development area has been proposed as 25.43% (i.e. 1235.25 Sq. Meters) of the Plot area, out of which green belt is 414.54 Sq. Meters and area for plantation in the form of Page 25 of 151

peripheral green will be 179 Sq. Meters, 245.22 Sq. Meters) as lawn area and 396.49 Sq. Meters as Avenue plantation. The total water requirement for the project will be 92 KLD (i.e. 22 KLD of fresh water & 70 KLD of recycled treated water). The waste water generation will be 61 KLD which will be treated in STP having of capacity of 75 KLD. The STP treated water will be reused for Flushing, Gardening and Misc. purposes.

The Air quality data is respect of PM10 and PM2.5 parameters ranges approximately from 128-148 µg/m3 and 58-63.20 µg/m3 respectively. Incremental air pollution 3 in respect of PM10 is 0.069 µg/m . PP has submitted special mitigation measures for controlling air pollution for construction phase and operation phase which include 5-meter-high barricade wall at the periphery, broad leafy trees would be planted as green belt, trees with heavy foliage would be planted on both sides of carriage way, ultra-low Sulphur Diesel (0.025 ppm) would be used as fuel in DG Sets, Stack height of DG set would be as per CPCP norms. These measures would minimize the impact on air environment. It was informed by the project proponent that the power requirement for the project will be 1950 KVA and for power back up they will install DG sets of 04 (3 x 750+1 x 320 KVA)of 2570 KVA. Parking requirement for the project is 286 ECS but the proposed parking provision will be of 300 ECS. Fire and safety plan as per the National Building Code 2005 will be provided. There will be total solid waste generation of 305.70 Kg/day during operational phase. Out of this, quantity of bio-degradable waste is 137.68 KG will be processed through Organic Waste Convertor (02) before composting in the project premises and the manure produced will be used for horticulture and green development. It was pointed out that the required water for the project will be provided through the HUDA Municipal Supply. Detailed discussions were held about Solid Waste Management. Rainwater harvesting, fire fighting plan, noise and vibration plan, health and welfare plan of the laborers, electrical hazards plan and Environment monitoring plan. There will be 02 Number of rain water harvesting pits as approved by the Central Ground Water Authority(CGWA). The mitigation measures were found in order by the committee. After deliberations the Committee rated this project with “Gold Rating” and was of the unanimous view that this case for granting Environmental Clearance under EIA Notification dated 14.9.2006 issued by the Ministry of Environment and Forest, Government of India should be recommended to the SEIAA with the following stipulations: PART A- SPECIFIC CONDITIONS:- Construction Phase:- [1] “Consent for Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. [2] A first aid room as proposed in the project report shall be provided both during construction and operational phase of the project. [3] Adequate drinking water and sanitary facilities shall be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the laboures Page 26 of 151

is strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. [4] All the topsoil excavated during construction activities shall be stored for use in horticulture/landscape development within the project site. [5] The project proponent shall ensure that the building material required during construction phase is properly stored within the project area and disposal of construction waste should not create any adverse effect on the neighboring communities and should be disposed of after taking necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. [6] Construction spoils, including bituminous material and other hazardous materials, must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. [7] The diesel generator sets to be used during construction phase shall be of ultra low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standards. [8] The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. [9] Ambient noise levels shall conform to the residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air pollution and noise level during construction phase, so as to conform to the stipulated residential standards of CPCB/MoEF. [10] Fly ash shall be used as building material in the construction as per the provisions of Fly Ash Notification of September 1999 and as amended on 27th August 2003. [11] Storm water control and its re-use as per CGWB and BIS standards for various applications should be ensured. [12] Water demand during construction shall be reduced by use of pre-mixed concrete, curing agents and other best practices. [13] In view of the severe constrains in water supply augmentation in the region and sustainability of water resources, the developer will submit the NOC from CGWA specifying water extraction quantities and assurance from HUDA/ utility provider indicating source of water supply and quantity of water with details of intended use of water – potable and non-potable. Assurance is required for both construction and operation stages separately. It shall be submitted to the SEIAA and RO, MOEF, Chandigarh before the start of construction. [14] Roof must meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material. [15] Opaque wall must meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is desirable for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. [16] The approval of the competent authority shall be obtained for structural safety of the building on account of earthquake, adequacy of fire fighting equipments, etc. as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site, clearance under Forest Conservation Act shall be obtained from the competent Authority. [17] Overexploited groundwater and impending severe shortage of water supply in the region requires the developer to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency /savings measures as well as water reuse/recycling within 3 months and before start of construction to the SEIAA, Haryana and RO, MOEF, GOI, Chandigarh. Page 27 of 151

[18] The Project Proponent as stated in the proposal shall construct total 10 rain water harvesting pits for recharging the ground water within the project premises. Rain water harvesting pits shall be designed to make provisions for silting chamber and removal of floating matter before entering harvesting pit. Maintenance budget and persons responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RWH pit. [19] The project proponent shall provide for adequate fire safety measures and equipments as required by Haryana Fire Service Act, 2009 and instructions issued by the local Authority/ Directorate of fire from time to time. Further the project proponent shall take necessary permission regarding fire safety scheme/NOC from competent Authority as required. [20] The Project Proponent shall obtain assurance from the DHBVN for supply of 7084.82 KVA of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. [21] Detail calculation of power load and ultimate power load of the project shall be submitted to DHBVN under intimation to SEIAA Haryana before the start of construction. Provisions shall be made for electrical infrastructure in the project area. [22] The Project Proponent shall not raise any construction in the natural land depression / Nallah/water course and shall ensure that the natural flow from the Nallah/water course is not obstructed. [23] The Project Proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Project. Levels of the other areas in the Projects shall also be kept suitably so as to avoid flooding. [24] Construction shall be carried out so that density of population does not exceed norms approved by Director General Town and Country Department Haryana. [25] The Project Proponent shall submit an affidavit with the declaration that ground water will not be used for construction and only treated water should be used for construction. [26] The project proponent shall not cut any existing tree and project landscaping plan should be modified to include those trees in green area. [27] The project proponent shall provide 3 meter high barricade around the project area, dust screen for every floor above the ground, proper sprinkling and covering of stored material to restrict dust and air pollution during construction. [28] The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. [29] The project proponent shall provide proper rasta of proper width and proper strength for the project before the start of construction. [30] The project proponent shall ensure that the U-value of the glass is less than 3.177 and maximum solar heat gain co-efficient is 0.25 for vertical fenestration. [31] The project proponent shall adequately control construction dusts like silica dust, non- silica dust and wood dust. Such dusts shall not spread outside project premises. Project Proponent shall provide respiratory protective equipment to all construction workers. [32] The project proponent shall develop complete civic infrastructure of the Group Housing colony including internal roads, green belt development, sewerage line, Rain Water recharge arrangements, Storm water drainage system, Solid waste management site and provision for treatment of bio-degradable waste, STP, water supply line, dual plumbing line, electric supply lines etc. and shall offer possession of the units/flats thereafter. [33] The project proponent shall provide one refuge area till 24 meter and one till 39 meter each, as per National Building Code. The project proponent shall not convert any refuse area in the habitable space and it should not be sold out/commercialized. [34] The project proponent shall provide fire control room and fire officer for building above 30 meter as per National Building Code. [35] The project proponent shall obtain permission of Mines and Geology Department for excavation of soil before the start of construction. Page 28 of 151

[36] The project proponent shall seek specific prior approval from concerned local Authority/HUDA regarding provision of storm drainage and sewerage system including their integration with external services of HUDA/ Local authorities beside other required services before taking up any construction activity. [37] The project proponent shall submit the copy of fire safety plan duly approved by Fire Department before the start of construction. [38] The project proponent shall discharge excess of treated waste water/storm water in the public drainage system and shall seek permission of HUDA before the start of construction. [39] The project proponent shall maintain the distance between STP and water supply line. [40] The project proponent shall ensure that the stack height is 6 meter more than the highest tower. [41] The project proponent shall ensure that structural stability to withstand earthquake of magnitude 8.5 on Richter scale. Operational Phase: [a] “Consent to Operate” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana. [b] The Sewage Treatment Plant (STP) shall be installed for the treatment of the sewage to the prescribed standards including odour and treated effluent will be recycled to achieve zero exit discharge. The installation of STP shall be certified by an independent expert and a report in this regard shall be submitted to the SEIAA, Haryana before the project is commissioned for operation. Tertiary treatment of waste water is mandatory. The project proponent shall remove not only Ortho-Phosphorus but total Phosphorus to the extent of less than 2mg/liter. Similarly total Nitrogen level shall be less than 2mg/liter in tertiary treated waste water. Discharge of treated sewage shall conform to the norms and standards of CPCB/ HSPCB, whichever is environmentally better. Project Proponent shall implement such STP technology which does not require filter backwash. The project proponent shall essentially provide two numbers of STPs preferably equivalent to 50% of total capacity or as per the initial occupancy as the case may be. [c] Separation of the grey and black water should be done by the use of dual plumbing line. Treatment of 100% grey water by decentralized treatment should be done ensuring that the re-circulated water should have BOD level less than 5 mg/litre and the recycled water will be used for flushing, gardening and DG set cooling etc. to achieve zero exit discharge. [d] For disinfection of the treated wastewater ultra-violet radiation or ozonization process should be used. [e] Diesel power generating sets proposed as source of back-up power for lifts, common area illumination and for domestic use should be of enclosed type and conform to rules made under the Environment (Protection) Act, 1986. The location of the DG sets shall be in the open as promised by the project proponent with appropriate stack height above the highest roof level of the project as per the CPCB norms. The diesel used for DG sets shall be ultra low sulphur diesel (35 ppm sulphur), instead of low sulphur diesel. [f] Ambient Noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the Proposed Affordable Group Housing Project. [g] The project proponent as stated in the proposal should maintain at least 20.10% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species which can provide protection against noise and suspended particulate matter. The open spaces inside the project shall be preferably landscaped and covered with vegetation/grass, herbs & shrubs. Only locally available plant species shall be used. [h] The project proponent shall strive to minimize water in irrigation of landscape by minimizing grass area, using native variety, xeriscaping and mulching, utilizing efficient irrigation system, scheduling irrigation only after checking evapo-transpiration data. Page 29 of 151

[i] Rain water harvesting for roof run-off and surface run-off, as per plan submitted should be implemented. Before recharging the surface run off, pre- treatment through sedimentation tanks must be done to remove suspended matter, oil and grease. The bore well for rainwater recharging shall be kept at least 5 mts. above the highest ground water table. Care shall be taken that contaminated water do not enter any RWH pit. The project proponent shall avoid Rain Water Harvesting of first 10 minutes of rain fall. Roof top of the building shall be without any toxic material or paint which can contaminate rain water. Wire mess and filters should be used wherever required. [j] The ground water level and its quality should be monitored regularly in consultation with Central Ground Water Authority. [k] A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about building materials & technology, R & U Factors etc and submitted to the SEIAA, Haryana in three months time. [l] Energy conservation measures like installation of LED only for lighting the areas outside the building and inside the building should be integral part of the project design and should be in place before project commissioning. Use of solar panels must be adapted to the maximum energy conservation. [m] The Project Proponent shall use zero ozone depleting potential material in insulation, refrigeration, air-conditioning and adhesive. Project Proponent shall also provide Halon free fire suppression system. [n] The solid waste generated should be properly collected and segregated as per the requirement of the MSW Rules, 2016 and as amended from time to time. The bio- degradable waste should be treated by appropriate technology (proposed OWC) at the site ear-marked within the project area and dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material. [o] The provision of the solar water heating system shall be as per norms specified by HAREDA and shall be made operational in each building block. [p] The traffic plan and the parking plan proposed by the Project Proponent should be adhered to meticulously with further scope of additional parking for future requirement. There should be no traffic congestion near the entry and exit points from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be used. [q] The Project shall be operationalized only when HUDA/local authority will provide domestic water supply system in the area. [r] Operation and maintenance of STP, solid waste management and electrical Infrastructure, pollution control measures shall be ensured even after the completion of project. [s] Different type of wastes should be disposed off as per provisions of municipal solid waste, biomedical waste, hazardous waste, e-waste, batteries & plastic rules made under Environment Protection Act, 1986. Particularly E-waste and Battery waste shall be disposed of as per existing E-waste Management Rules 2011 and Batteries Management Rules 2001. The project proponent should maintain a collection center for E-waste and it shall be disposed of to only registered and authorized dismantler / recycler. [t] Standards for discharge of environmental pollutants as enshrined in various schedules of rule 3 of Environment Protection Rule 1986 shall be strictly complied with. [u] Water supply shall be metered among different users and different utilities. [v] The project proponent shall ensure that the of DG sets is more than the highest tower and also ensure that the emission standards of noise and air are within the CPCB latest prescribed limits. Noise and Emission level of DG sets greater than 800 KVA shall be as per CPCB latest standards for high capacity DG sets. [w] All electric supply exceeding 100 amp, 3 phase shall maintain the power factor between 0.98 lag to 1 at the point of connection. [x] The project proponent shall not use fresh water for HVAC and DG cooling. Air based HVAC system should be adopted and only treated water shall be used by project proponent for Page 30 of 151

cooling, if it is at all needed. The Project Proponent shall also use evaporative cooling technology and double stage cooling system for HVAC in order to reduce water consumption. Further temperature, relative humidity during summer and winter seasons should be kept at optimal level. Variable speed drive, best Co-efficient of Performance (CoP), as well as optimal Integrated Point Load Value and minimum outside fresh air supply may be resorted for conservation of power and water. Coil type cooling DG Sets shall be used for saving cooling water consumption for water cooled DG Sets. [y] The project proponent shall ensure that the transformer is constructed with high quality grain oriented, low loss silicon steel and virgin electrolyte grade copper. The project proponent shall obtain manufacturer’s certificate also for that. [z] The project proponent shall ensure that exit velocity from the stack should be sufficiently high. Stack shall be designed in such a way that there is no stack down-wash under any meteorological conditions. [aa] The project proponent shall provide water sprinkling system in the project area to suppress the dust in addition to the already suggested mitigation measures in the Air Environment Chapter of EMP. [ab] The project proponent shall ensure proper Air Ventilation and light system in the basements area for comfortable living of human being and shall ensure that number of Air Changes per hour/(ACH) in basement never falls below 15. In case of emergency capacity for increasing ACH to the extent of 30 must be provided by the project proponent. [ac] The project proponent shall ensure drinking/ domestic water supply as per prescribed standards till treated water supply is made available by HUDA. [ad] The project proponent shall install solar panel for energy conservation. PART-B. GENERAL CONDITIONS: [i] The Project Proponent shall ensure the commitments made in Form-1, Form-1A, EIA/EMP and other documents submitted to the SEIAA for the protection of environment and proposed environmental safeguards are complied with in letter and spirit. In case of contradiction between two or more documents on any point, the most environmentally friendly commitment on the point shall be taken as commitment by project proponent. [ii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Zonal Office of CPCB, HSPCB and SEIAA Haryana. [iii] STP outlet after stabilization and stack emission shall be monitored monthly. Other environmental parameters and green belt shall be monitored on quarterly basis. After every 3 (three) months, the project proponent shall conduct environmental audit and shall take corrective measure, if required, without delay. [iv] The SEIAA, Haryana reserves the right to add additional safeguard measures subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/MoEF. [v] The Project proponent shall not violate any judicial orders/pronouncements issued by any Court/Tribunal. [vi] All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (Protection) Act, 1972, Forest Act, 1927, PLPA 1900, etc. shall be obtained, as applicable by project proponents from the respective authorities prior to construction of the project. [vii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Page 31 of 151

Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [viii] Under the provisions of Environment (Protection) Act, 1986, legal action shall be initiated against the Project Proponent if it was found that construction of the project has been started before obtaining prior Environmental Clearance. [ix] Any appeal against the this Environmental Clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010. [x] The project proponent shall put in place Corporate Environment Policy as mentioned in MoEF, GoI OM No. J-11013/41/2006-IA II (I) dated 26.4.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issuance of this letter. [xi] The fund ear-marked for environment protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO MOEF GOI under rules prescribed for Environment Audit. [xii] The project proponent shall ensure the compliance of Forest Department, Haryana Notification no. S.O.121/PA2/1900/S.4/97 dated 28.11.1997. [xiii] The Project Proponent shall ensure that no vehicle during construction/operation phase enter the project premises without valid ‘Pollution Under Control’ certificate from competent Authority. [xiv] The project proponent is responsible for compliance of all conditions in Environmental Clearance letter and project proponent can not absolve himself /herself of the responsibility by shifting it to any contractor engaged by project proponent. [xv] The project proponent shall seek fresh Environmental clearance if at any stage there is change in the planning of the proposed project. [xvi] Besides the developer/applicant, the responsibility to ensure the compliance of Environmental Safeguards/conditions imposed in the Environmental Clearance letter shall also lie on the licensee/licensees in whose name/names the license/CLU has been granted by the Town & Country Planning Department, Haryana. [xvii] The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SOX NOX, Ozone, Lead, CO, Benzene, Ammonia, Benzopyrine, arsenic and Nickel. (Ambient levels as well as stack emissions) or critical sectoral parameters, indicated for the project shall be monitored and displayed at a convenient location near the main gate of the company in the public domain. [xviii] The environmental statement for each financial year ending 31st March in Form-V as is mandated to be submitted by the project proponent to the HSPCB Panchkula as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be put on the website of the company along with the status of compliance of the EC conditions and shall also be sent to the respective Regional Offices of MoEF by e- mail. [xix] The project proponent shall conduct environment audit at every three months interval and thereafter corrected measures shall be taken without any delay. Details of environmental audit and corrective measures shall be submitted in the monitoring report. [xx] Corporate Environment and Social Responsibility (CSER) shall be laid down by the project proponent (2% shall be earmarked) as per guidelines of MoEF, GoI Office Memorandum No. J-11013/41/2006-IA.II(I) dated 18.05.2012 and Ministry of Corporate Affairs, GoI Notification Dated 27.02.2014. A separate audit statement shall be submitted in the compliance. Environment related work proposed to be executed under this responsibility shall be undertaken simultaneously. The project proponent shall select and prepare the list of the work for implementation of CSER of its own choice and shall submit the same before the start of construction. Page 32 of 151

134.08 EC for construction of IT Park/Unit (2.34 Acres) at Village Dundahera, Sector-19, District-Gurgaon, Haryana by M/s Pursarth Infrastructures Pvt. Ltd. Project Proponent : Sh. Ishad Ahmed, Authorised Signatory. Consultant : Vardan EnviroNet Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 26.11.2015. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. Thereafter the case was taken up in the 130th meeting of the SEAC held on 29.03.2016. The case was not heard as the project proponent failed to circulate the documents (Form 1, Form 1A and Conceptual Plan) to all the Members well in time. The project proponent had undertaken to circulate the documents to all the Members well in time and requested for considering their case for appraisal in the next meeting of the SEAC. It was unanimously decided by the Committee that the case will be considered in the next meeting of the SEAC to be held on 07th April, 2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC. The case was taken up in the 131st meeting of the SEAC held on 07.04.2016. After detailed discussions, the following shortcomings were concluded: 1. The PP should submit contour sheet of the area alongwith demarcation of the project on the contour sheet. 2. The PP should submit revised parking plan of basement taking into fire norms. 3. The PP should submit Aravali NOC from Deputy Commissioner, Gurgaon as the NOC submitted by the PP does not match the Khasra numbers of CLU. 4. The PP should submit detailed design calculations of STP alongwith dimension of each component and also submit unit wise reduction of BOD for STP. Th The observations of 131st meeting were conveyed to the project proponent vide letter No. 877 dated 20.04.2016. The PP submitted the reply vide letter dated 21.04.2016.

Thereafter the case was taken up in the 134th meeting of the SEAC held on 30.05.2016.

During presentation, the committee was informed that it is a proposed construction of IT Park/Unit (2.34 Acres) at Village Dundahera, Sector-19, District-Gurgaon, Haryana. The estimated cost of the project is Rs. 107 Crores. Total Plot area is 2.44 Acres (9874.314 Sq. Meters) and net plot area is 2.34 Acres (9469.64 Sq. Meters ). Total built up area will be 40655.59 Sq. Meters. The project will comprise of IT offices and commercial building. The maximum height of the building is approx. 41.40 Meters. It was also informed that the green area development has been kept as 25.28 % (i.e. 2394.86 Sq. Meters) of the net plot area. 900.73 Sq. Meters would be earmarked for plantation in the form of green belt and peripheral green, 324.12 Sq. Meters as Lawn area and 1170.01 Sq. Meters as Avenue Plantation. The total water requirement for the project will be 173 KLD (i.e. 56 KLD of fresh water & 117 KLD of recycled treated water). The waste water generation will be 105 KLD which will be treated up to Page 33 of 151

tertiary level in STP having total capacity of 130 KLD. The STP treated water will be used for flushing, DG cooling and horticulture purpose.

The Air quality data in respect of PM10 and PM2.5 parameters ranges approximately from 118.0-158.0 µg/m3 and 61.20-64.30 µg/m3 respectively. Incremental air 3 pollution in respect of PM10 is 0.050 µg/m . PP has submitted special mitigation measures for controlling air pollution for construction phase and operation phase which includes 5 meters high barricade wall at the periphery, broad leafy trees would be planted as green belt, trees with heavy foliage would be planted on both side of carriage way, ultra low sulphur Diesel (0.015%) would be used as fuel in DG Sets, Stack height of DG set would be as per CPCB norms. These measures would minimize the impact on air environment. It was informed by the project proponent that the power requirement for the project will be 2530 KVA and for power back up they will install DG sets of 04 (3 x 750 KVA + 1 x 380 KVA) of 2630 KVA. Parking requirement for the project is 559 ECS but the proposed parking provision will be of 575 ECS. Fire and safety plan as per the National Building Code 2005 will be provided. There will be total solid waste generation of 530 Kg/day during operational phase. Out of this, quantity of bio-degradable waste is 238.50 KG will be processed through Organic Waste Convertor(02) before composting in the project premises and the manure produced will be used for horticulture and green development. It was pointed out that the required water for the project will be provided through the HUDA Municipal Supply. Detailed discussions were held about Solid Waste Management. Rainwater harvesting, fire fighting plan, noise and vibration plan, health and welfare plan of the laborers, electrical hazards plan and Environment monitoring plan. There will be 03 Number of rain water harvesting pits as approved by the Central Ground Water Authority(CGWA). The mitigation measures were found in order by the committee. After deliberations the Committee rated this project with “Gold Rating” and was of the unanimous view that this case for granting Environmental Clearance under EIA Notification dated 14.9.2006 issued by the Ministry of Environment and Forest, Government of India should be recommended to the SEIAA with the following stipulations: PART A- SPECIFIC CONDITIONS:- Construction Phase:- [1] “Consent for Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. [2] A first aid room as proposed in the project report shall be provided both during construction and operational phase of the project. [3] Adequate drinking water and sanitary facilities shall be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the laboures is strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. [4] All the topsoil excavated during construction activities shall be stored for use in horticulture/landscape development within the project site. Page 34 of 151

[5] The project proponent shall ensure that the building material required during construction phase is properly stored within the project area and disposal of construction waste should not create any adverse effect on the neighboring communities and should be disposed of after taking necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. [6] Construction spoils, including bituminous material and other hazardous materials, must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. [7] The diesel generator sets to be used during construction phase shall be of ultra low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standards. [8] The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. [9] Ambient noise levels shall conform to the residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air pollution and noise level during construction phase, so as to conform to the stipulated residential standards of CPCB/MoEF. [10] Fly ash shall be used as building material in the construction as per the provisions of Fly Ash Notification of September 1999 and as amended on 27th August 2003. [11] Storm water control and its re-use as per CGWB and BIS standards for various applications should be ensured. [12] Water demand during construction shall be reduced by use of pre-mixed concrete, curing agents and other best practices. [13] In view of the severe constrains in water supply augmentation in the region and sustainability of water resources, the developer will submit the NOC from CGWA specifying water extraction quantities and assurance from HUDA/ utility provider indicating source of water supply and quantity of water with details of intended use of water – potable and non-potable. Assurance is required for both construction and operation stages separately. It shall be submitted to the SEIAA and RO, MOEF, Chandigarh before the start of construction. [14] Roof must meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material. [15] Opaque wall must meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is desirable for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. [16] The approval of the competent authority shall be obtained for structural safety of the building on account of earthquake, adequacy of fire fighting equipments, etc. as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site, clearance under Forest Conservation Act shall be obtained from the competent Authority. [17] Overexploited groundwater and impending severe shortage of water supply in the region requires the developer to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency /savings measures as well as water reuse/recycling within 3 months and before start of construction to the SEIAA, Haryana and RO, MOEF, GOI, Chandigarh. [18] The Project Proponent as stated in the proposal shall construct total 10 rain water harvesting pits for recharging the ground water within the project premises. Rain water harvesting pits shall be designed to make provisions for silting chamber and removal of floating matter before entering harvesting pit. Maintenance budget and persons Page 35 of 151

responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RWH pit. [19] The project proponent shall provide for adequate fire safety measures and equipments as required by Haryana Fire Service Act, 2009 and instructions issued by the local Authority/ Directorate of fire from time to time. Further the project proponent shall take necessary permission regarding fire safety scheme/NOC from competent Authority as required. [20] The Project Proponent shall obtain assurance from the DHBVN for supply of 7084.82 KVA of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. [21] Detail calculation of power load and ultimate power load of the project shall be submitted to DHBVN under intimation to SEIAA Haryana before the start of construction. Provisions shall be made for electrical infrastructure in the project area. [22] The Project Proponent shall not raise any construction in the natural land depression / Nallah/water course and shall ensure that the natural flow from the Nallah/water course is not obstructed. [23] The Project Proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Project. Levels of the other areas in the Projects shall also be kept suitably so as to avoid flooding. [24] Construction shall be carried out so that density of population does not exceed norms approved by Director General Town and Country Department Haryana. [25] The Project Proponent shall submit an affidavit with the declaration that ground water will not be used for construction and only treated water should be used for construction. [26] The project proponent shall not cut any existing tree and project landscaping plan should be modified to include those trees in green area. [27] The project proponent shall provide 3 meter high barricade around the project area, dust screen for every floor above the ground, proper sprinkling and covering of stored material to restrict dust and air pollution during construction. [28] The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. [29] The project proponent shall provide proper rasta of proper width and proper strength for the project before the start of construction. [30] The project proponent shall ensure that the U-value of the glass is less than 3.177 and maximum solar heat gain co-efficient is 0.25 for vertical fenestration. [31] The project proponent shall adequately control construction dusts like silica dust, non- silica dust and wood dust. Such dusts shall not spread outside project premises. Project Proponent shall provide respiratory protective equipment to all construction workers. [32] The project proponent shall develop complete civic infrastructure of the Group Housing colony including internal roads, green belt development, sewerage line, Rain Water recharge arrangements, Storm water drainage system, Solid waste management site and provision for treatment of bio-degradable waste, STP, water supply line, dual plumbing line, electric supply lines etc. and shall offer possession of the units/flats thereafter. [33] The project proponent shall provide one refuge area till 24 meter and one till 39 meter each, as per National Building Code. The project proponent shall not convert any refuse area in the habitable space and it should not be sold out/commercialized. [34] The project proponent shall provide fire control room and fire officer for building above 30 meter as per National Building Code. [35] The project proponent shall obtain permission of Mines and Geology Department for excavation of soil before the start of construction. [36] The project proponent shall seek specific prior approval from concerned local Authority/HUDA regarding provision of storm drainage and sewerage system including their integration with external services of HUDA/ Local authorities beside other required services before taking up any construction activity. Page 36 of 151

[37] The project proponent shall submit the copy of fire safety plan duly approved by Fire Department before the start of construction. [38] The project proponent shall discharge excess of treated waste water/storm water in the public drainage system and shall seek permission of HUDA before the start of construction. [39] The project proponent shall maintain the distance between STP and water supply line. [40] The project proponent shall ensure that the stack height is 6 meter more than the highest tower. [41] The project proponent shall ensure that structural stability to withstand earthquake of magnitude 8.5 on Richter scale. Operational Phase: [a] “Consent to Operate” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana. [b] The Sewage Treatment Plant (STP) shall be installed for the treatment of the sewage to the prescribed standards including odour and treated effluent will be recycled to achieve zero exit discharge. The installation of STP shall be certified by an independent expert and a report in this regard shall be submitted to the SEIAA, Haryana before the project is commissioned for operation. Tertiary treatment of waste water is mandatory. The project proponent shall remove not only Ortho-Phosphorus but total Phosphorus to the extent of less than 2mg/liter. Similarly total Nitrogen level shall be less than 2mg/liter in tertiary treated waste water. Discharge of treated sewage shall conform to the norms and standards of CPCB/ HSPCB, whichever is environmentally better. Project Proponent shall implement such STP technology which does not require filter backwash. The project proponent shall essentially provide two numbers of STPs preferably equivalent to 50% of total capacity or as per the initial occupancy as the case may be. [c] Separation of the grey and black water should be done by the use of dual plumbing line. Treatment of 100% grey water by decentralized treatment should be done ensuring that the re-circulated water should have BOD level less than 5 mg/litre and the recycled water will be used for flushing, gardening and DG set cooling etc. to achieve zero exit discharge. [d] For disinfection of the treated wastewater ultra-violet radiation or ozonization process should be used. [e] Diesel power generating sets proposed as source of back-up power for lifts, common area illumination and for domestic use should be of enclosed type and conform to rules made under the Environment (Protection) Act, 1986. The location of the DG sets shall be in the open as promised by the project proponent with appropriate stack height above the highest roof level of the project as per the CPCB norms. The diesel used for DG sets shall be ultra low sulphur diesel (35 ppm sulphur), instead of low sulphur diesel. [f] Ambient Noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the Proposed Affordable Group Housing Project. [g] The project proponent as stated in the proposal should maintain at least 20.10% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species which can provide protection against noise and suspended particulate matter. The open spaces inside the project shall be preferably landscaped and covered with vegetation/grass, herbs & shrubs. Only locally available plant species shall be used. [h] The project proponent shall strive to minimize water in irrigation of landscape by minimizing grass area, using native variety, xeriscaping and mulching, utilizing efficient irrigation system, scheduling irrigation only after checking evapo-transpiration data. [i] Rain water harvesting for roof run-off and surface run-off, as per plan submitted should be implemented. Before recharging the surface run off, pre- treatment through sedimentation tanks must be done to remove suspended matter, oil and grease. The bore well for rainwater recharging shall be kept at least 5 mts. above the highest ground water table. Care shall be taken that contaminated water do not enter any RWH pit. The Page 37 of 151

project proponent shall avoid Rain Water Harvesting of first 10 minutes of rain fall. Roof top of the building shall be without any toxic material or paint which can contaminate rain water. Wire mess and filters should be used wherever required. [j] The ground water level and its quality should be monitored regularly in consultation with Central Ground Water Authority. [k] A report on the energy conservation measures conforming to energy conservation norms finalized by Bureau of Energy Efficiency should be prepared incorporating details about building materials & technology, R & U Factors etc and submitted to the SEIAA, Haryana in three months time. [l] Energy conservation measures like installation of LED only for lighting the areas outside the building and inside the building should be integral part of the project design and should be in place before project commissioning. Use of solar panels must be adapted to the maximum energy conservation. [m] The Project Proponent shall use zero ozone depleting potential material in insulation, refrigeration, air-conditioning and adhesive. Project Proponent shall also provide Halon free fire suppression system. [n] The solid waste generated should be properly collected and segregated as per the requirement of the MSW Rules, 2016 and as amended from time to time. The bio- degradable waste should be treated by appropriate technology (proposed OWC) at the site ear-marked within the project area and dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material. [o] The provision of the solar water heating system shall be as per norms specified by HAREDA and shall be made operational in each building block. [p] The traffic plan and the parking plan proposed by the Project Proponent should be adhered to meticulously with further scope of additional parking for future requirement. There should be no traffic congestion near the entry and exit points from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be used. [q] The Project shall be operationalized only when HUDA/local authority will provide domestic water supply system in the area. [r] Operation and maintenance of STP, solid waste management and electrical Infrastructure, pollution control measures shall be ensured even after the completion of project. [s] Different type of wastes should be disposed off as per provisions of municipal solid waste, biomedical waste, hazardous waste, e-waste, batteries & plastic rules made under Environment Protection Act, 1986. Particularly E-waste and Battery waste shall be disposed of as per existing E-waste Management Rules 2011 and Batteries Management Rules 2001. The project proponent should maintain a collection center for E-waste and it shall be disposed of to only registered and authorized dismantler / recycler. [t] Standards for discharge of environmental pollutants as enshrined in various schedules of rule 3 of Environment Protection Rule 1986 shall be strictly complied with. [u] Water supply shall be metered among different users and different utilities. [v] The project proponent shall ensure that the of DG sets is more than the highest tower and also ensure that the emission standards of noise and air are within the CPCB latest prescribed limits. Noise and Emission level of DG sets greater than 800 KVA shall be as per CPCB latest standards for high capacity DG sets. [w] All electric supply exceeding 100 amp, 3 phase shall maintain the power factor between 0.98 lag to 1 at the point of connection. [x] The project proponent shall not use fresh water for HVAC and DG cooling. Air based HVAC system should be adopted and only treated water shall be used by project proponent for cooling, if it is at all needed. The Project Proponent shall also use evaporative cooling technology and double stage cooling system for HVAC in order to reduce water consumption. Further temperature, relative humidity during summer and winter seasons should be kept at optimal level. Variable speed drive, best Co-efficient of Performance (CoP), as well as optimal Integrated Point Load Value and minimum outside fresh air Page 38 of 151

supply may be resorted for conservation of power and water. Coil type cooling DG Sets shall be used for saving cooling water consumption for water cooled DG Sets. [y] The project proponent shall ensure that the transformer is constructed with high quality grain oriented, low loss silicon steel and virgin electrolyte grade copper. The project proponent shall obtain manufacturer’s certificate also for that. [z] The project proponent shall ensure that exit velocity from the stack should be sufficiently high. Stack shall be designed in such a way that there is no stack down-wash under any meteorological conditions. [aa] The project proponent shall provide water sprinkling system in the project area to suppress the dust in addition to the already suggested mitigation measures in the Air Environment Chapter of EMP. [ab] The project proponent shall ensure proper Air Ventilation and light system in the basements area for comfortable living of human being and shall ensure that number of Air Changes per hour/(ACH) in basement never falls below 15. In case of emergency capacity for increasing ACH to the extent of 30 must be provided by the project proponent. [ac] The project proponent shall ensure drinking/ domestic water supply as per prescribed standards till treated water supply is made available by HUDA. [ad] The project proponent shall install solar panel for energy conservation. PART-B. GENERAL CONDITIONS: [i] The Project Proponent shall ensure the commitments made in Form-1, Form-1A, EIA/EMP and other documents submitted to the SEIAA for the protection of environment and proposed environmental safeguards are complied with in letter and spirit. In case of contradiction between two or more documents on any point, the most environmentally friendly commitment on the point shall be taken as commitment by project proponent. [ii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Zonal Office of CPCB, HSPCB and SEIAA Haryana. [iii] STP outlet after stabilization and stack emission shall be monitored monthly. Other environmental parameters and green belt shall be monitored on quarterly basis. After every 3 (three) months, the project proponent shall conduct environmental audit and shall take corrective measure, if required, without delay. [iv] The SEIAA, Haryana reserves the right to add additional safeguard measures subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/MoEF. [v] The Project proponent shall not violate any judicial orders/pronouncements issued by any Court/Tribunal. [vi] All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (Protection) Act, 1972, Forest Act, 1927, PLPA 1900, etc. shall be obtained, as applicable by project proponents from the respective authorities prior to construction of the project. [vii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. Page 39 of 151

[viii] Under the provisions of Environment (Protection) Act, 1986, legal action shall be initiated against the Project Proponent if it was found that construction of the project has been started before obtaining prior Environmental Clearance. [ix] Any appeal against the this Environmental Clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010. [x] The project proponent shall put in place Corporate Environment Policy as mentioned in MoEF, GoI OM No. J-11013/41/2006-IA II (I) dated 26.4.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issuance of this letter. [xi] The fund ear-marked for environment protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO MOEF GOI under rules prescribed for Environment Audit. [xii] The project proponent shall ensure the compliance of Forest Department, Haryana Notification no. S.O.121/PA2/1900/S.4/97 dated 28.11.1997. [xiii] The Project Proponent shall ensure that no vehicle during construction/operation phase enter the project premises without valid ‘Pollution Under Control’ certificate from competent Authority. [xiv] The project proponent is responsible for compliance of all conditions in Environmental Clearance letter and project proponent can not absolve himself /herself of the responsibility by shifting it to any contractor engaged by project proponent. [xv] The project proponent shall seek fresh Environmental clearance if at any stage there is change in the planning of the proposed project. [xvi] Besides the developer/applicant, the responsibility to ensure the compliance of Environmental Safeguards/conditions imposed in the Environmental Clearance letter shall also lie on the licensee/licensees in whose name/names the license/CLU has been granted by the Town & Country Planning Department, Haryana. [xvii] The proponent shall upload the status of compliance of the stipulated EC conditions, including results of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The criteria pollutant levels namely; PM2.5, PM10, SOX NOX, Ozone, Lead, CO, Benzene, Ammonia, Benzopyrine, arsenic and Nickel. (Ambient levels as well as stack emissions) or critical sectoral parameters, indicated for the project shall be monitored and displayed at a convenient location near the main gate of the company in the public domain. [xviii] The environmental statement for each financial year ending 31st March in Form-V as is mandated to be submitted by the project proponent to the HSPCB Panchkula as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be put on the website of the company along with the status of compliance of the EC conditions and shall also be sent to the respective Regional Offices of MoEF by e- mail. [xix] The project proponent shall conduct environment audit at every three months interval and thereafter corrected measures shall be taken without any delay. Details of environmental audit and corrective measures shall be submitted in the monitoring report. [xx] Corporate Environment and Social Responsibility (CSER) shall be laid down by the project proponent (2% shall be earmarked) as per guidelines of MoEF, GoI Office Memorandum No. J-11013/41/2006-IA.II(I) dated 18.05.2012 and Ministry of Corporate Affairs, GoI Notification Dated 27.02.2014. A separate audit statement shall be submitted in the compliance. Environment related work proposed to be executed under this responsibility shall be undertaken simultaneously. The project proponent shall select and prepare the list of the work for implementation of CSER of its own choice and shall submit the same before the start of construction. Page 40 of 151

134.09 Environment Clearance for “NBCC Group Housing Complex” On MCF Land Plot No. 3,in the revenue Estate of Village Sarai Khawaja at Sector-41, Faridabad, Haryana by M/s National Building Construction Corporation Ltd. Project Proponent : Sh. M.S. Mehra, AGM Consultant : Perfect Enviro Solutions Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 28.03.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 133rd meeting of the SEAC held on 05.05.2016. The case was not heard as the project proponent failed to circulate the documents (Form 1, Form 1A and Conceptual Plan) to all the Members well in time. The project proponent had undertaken to circulate the documents to all the Members well in time and requested for considering their case for appraisal in the next meeting of the SEAC. It was unanimously decided by the Committee that the case will be considered in the 134th meeting to be held on 30.05.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC. The Project Proponent requested for adjournment and the same was discussed in the meeting. The Committee acceded to the request and decided to issue 30 days notice to the PP. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. 134.10 Environmental Clearance for the proposed Group Housing Colony (13.2118 Acres), Village Badshahpur, Sector-68, Gurgaon by M/s Hans Propcon Pvt. Ltd Project Proponent : Sh. Satpal Singh, Authorised signatory Consultant : Vardan Enviro Solutions The project was submitted to the SEIAA, Haryana on 09.01.2015. The project proponent submitted the case to the SEIAA as per checklist approved by the SEIAA/SEAC. The case was appraised in the 118th meeting of the SEAC held on 04.03.2015 and recommended to SEIAA for grant of Environmental Clearance. This case was taken up by the SEIAA in its 84th meeting held on 29.10.2015 and following observations were observed and conveyed to the project proponent vide letter No. SEIAA/HR/15/499 dated 19.11.2015. 1. Since the height of building is 94.20 meters hence clearance from the recognize institution like ITTES/PEC, Regional Engineering College/National Institute of Technology etc. regarding structural stability and for fire safety clearance from institute of Fire Engineers, Nagpur is required. The project proponent shall obtain the same and submit to the SEAC. 2. The SEAC shall ensure that the solid waste generation calculation and parking calculation is as per latest prescribed norms and shall also ensure that the project proponent has furnished details of appropriate technology to be adopted for treatment of bio- degradable waste. 3. As per point no. 31 (vi) of checklist, the project proponent is required to submit an undertaking stating that: “Provision for Helipad shall be made as the height of building is more than 60 meter. Provision of at least one Hydraulic ladder for high rise building shall also be made.” 4. The project proponent shall submit latest undertaking on non judicial stamp paper stating that no construction has been raised at site duly signed by the director. The project proponent shall also submit latest photograph of site. Page 41 of 151

SEIAA has returned the case on 19.11.2015 with the advice that the SEAC should reappraise the case and submit its recommendation on merits within stipulated period. The project proponent submitted the reply of the shortcomings vide letter dated 03.12.2015. Thereafter this case was taken up for in the 125th meeting of the SEAC held on 11.01.2016. The SEAC appraised the case in its 125th meeting and found the reply of the observations mentioned at Sr. No. 2, 3 and 4 are satisfactory. As far as the observation at Sr. No. 1 is concerned the project proponent so far has not submitted the compliance and the Committee is of the unanimous view that the PP should submit complete compliance of observation at Sr. No. 1 i.e. “Since the height of building is 94.20 meters hence clearance from the recognize institution like ITTES/PEC, Regional Engineering College/National Institute of Technology etc. regarding structural stability and for fire safety clearance from institute of Fire Engineers, Nagpur is required. The above mentioned shortcomings were conveyed to the project proponent vide letter No. 386 dated 24.12.2015. The project proponent submitted the reply vide letter dated 04.02.2016. Thereafter this case was reappraised by the SEAC in the 129th meeting held on 14.03.2016 and recommended the case to SEIAA for granting Environmental Clearance.

This case was again taken up by the SEIAA in its 90th meeting held on 22.04.2016 and following observations were observed and conveyed to the project proponent vide letter No. SEIAA/HR/16/346 dated 04.05.2016. 1. The proposed built up area of the project 149449.28 Sq. Meters. The SEAC is required to calculate the built up area as clarified in the MoEF OM F. No. 19- 127/2011-IA-III dated 02.04.2012 and thereafter re-appraise the project proposal as per procedure prescribed in the Notification if the proposed built up area found to be 15,0000 Sq. Meters or above. 2. The project proponent shall submit the detailed calculations of drinking water for construction workers along with source; waste water generation and its treatment scheme in the labour camp area during construction phase. Provision for STP in case the waste water generation is 10 KLD or above. 3. The Project proponent has proposed to supply 230 KLD to water tankers for construction purpose. The project proponent is required to justify the same specifically mentioning the requirement of number of tankers per day and the impact of the same on AAQ. Due to movement of tankers carrying vehicles and mitigation measures. SEIAA has returned the case on 04.05.2016 with the advice that the SEAC should reappraise the case and submit its recommendation on merits within stipulated period. The project proponent submitted the reply of the shortcomings vide letter dated 11.05.2016. Thereafter this case was taken up for in the 134th meeting of the SEAC held on 30.05.2016.

During discussions the project proponent informed that they have reduced the built-up area from 149640 Sq. Meters to 147170.83 Sq. Meters and also submitted the revised Form I, Form IA and Conceptual Plan.

The SEAC reappraised the case for all the observations made by the SEIAA and found that the compliance has been made by the Project proponent for all the observations. Page 42 of 151

In view of the above, the SEAC again recommends this case for environmental clearance subject to the compliance to the conditions as already recommended by the SEAC in the 118th meeting held on 04.03.2015.

134.11 EC for the “Revision and Expansion of Group Housing Colony” located at Village Chauma, Sector-110A & 111, Gurgaon, Haryana by M/s Puri Construction Pvt. Ltd. Project Proponent : Sh. T.S. Puri, Director Consultant : Grass Roots Research and Creation India Pvt. Ltd. The project proponent submitted the case for obtaining Environmental Clearance to the SEIAA, Haryana on 02.03.2015 as per check list approved by the SEIAA/SEAC. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. The Terms of Reference were approved in the 122nd meeting of the SEAC held on 27.11.2015 and conveyed to the project proponent vide letter No. 328 dated 09.12.2015. The project proponent submitted the EIA/EMP report vide letter dated 21.04.20146. Thereafter, the case was taken up for appraisal in the 134th meeting of the SEAC held on 31.05.2016. The Project Proponent requested for adjournment and the same was discussed in the meeting. The Committee acceded to the request and decided to issue 30 days notice to the PP. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. 134.12 Environment Clearance for proposed expansion of our IT/ITES Project, at plot NO.-20, Panchkula Technology Park, Sector-22, Panchkula, Haryana by M/s JSK Multi Projects Pvt. Project Proponent : Sh. Harpal Singh Consultant : EKO PRO Engineers Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 25.04.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 134th meeting of the SEAC held on 31.05.2016.

The Project Proponent requested for adjournment and the same was discussed in the meeting. The Committee acceded to the request and decided to issue 30 days notice to the PP. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent.

134.13 Environment Clearance for Draft Mining Plan & Progressive Mine Closure Plan for Pichopa Kalan Plot No. 3 Stone Mine along with Associated Minor Minerals (Minor Mineral ) for Bhiwani, Haryana by M/s Jai Dada Dohla Stone Mines. Project Proponent : Sh. Ishwar Dagar, Partner Consultant : Vardan Enviro Solutions Pvt. Ltd.

The project was submitted to the SEIAA, Haryana on 11.05.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for approval of Terms of Reference in the 134th meeting of the SEAC held on 31.05.2016. Page 43 of 151

The project proponent presented the case for proposed ToRs. The PP is directed to prepare the EIA by incorporating the following ToR: 1. Year-wise production details since 1994 should be given, clearly stating the highest production achieved in any one year prior to 1994. It may also be categorically informed whether there had been any increase in production after the EIA Notification, 1994 came into force w.r.t. the highest production achieved prior to 1994. 2. A copy of the document in support of the fact that the proponent is the rightful lessee of the mine should be given. 3. All documents including approved Mining Plan, EIA and Public Hearing should be compatible with one another in terms of the mine lease area, production levels, waste generation and its management and mining technology and should be in the name of the lessee. 4. All corner coordinates of the mine lease area, superimposed on a High Resolution Imagery /toposheet should be provided. Such an Imagery of the proposed area should clearly show the land use and other ecological features of the study area (core and buffer zone). Lease area should be precisely marked in survey of India Topo-sheet of 1:50000. 5. Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be spelt out in the EIA report with description of the prescribed operating process/procedures to bring into focus any infringement/deviation/violation of the environmental or forest norms/ conditions? The hierarchical system or administrative order to the Company to deal with the environmental issues and for ensuring compliance with the EC conditions may be given. The system of reporting of non- compliances/ violations of environmental norms to be Board of Director of the Company and /or shareholders or stakeholders at large may also be detailed in the EIA report. 6. Issues relating to Systematic Mine Development, Mine Safety and Stability in case of open cast working, blasting study etc. should be detailed. The proposed safeguard measures in each case should also be mentioned. Daily explosive consumption and its legitimate storage are to be assessed. Adequate mitigating measures based on scientific studies in respect of blast induced ground vibration flying fragment and air blast are to be taken alongwith requisite precaution. 7. The study area will comprise of 10 km zone around the mine lease from lease periphery and the data contained in the EIA such as waste generation etc. should be for the life of the mine/lease period. 8. Land use of the study area delineating forest area, agricultural land, grazing land, wildlife sanctuary, national park,, migratory routes of fauna, water bodies, human settlements and other ecological features should be indicated. Land use plan of the mine lease area should be prepared to encompass preoperational, operational and post operational phases and submitted. Impact, if any, of change of land use should be given. 9. Mineral resources and reserve in terms of UNFC are to be given duly supported by adequate representative plans and sections. Ultimately mineable limit should also be marked over geological plan and sector. Details of the land for any Over Burden Dumps outside the mine lease, such as extent of land area, distance from mine lease, its land use, R&R issues, if any, should be given. 10. A Certificate from the Competent Authority in the State Forest Department should be provided, confirming the involvement of forest land, if any, in the project area. In the event of any contrary claim by the Project Proponent regarding the status of forests, the site may be inspected by the State Forest Department along with the Regional Office of the Ministry to ascertain the status of forests, based on which, the Certificate in this regard as mentioned above be issued. In all such cases, it would be desirable for representative of the State Forest Department to assist the Expert Appraisal Committee. 11. Status of forestry clearance for the broken up area and virgin forestland involved in the Project including deposition of net present value (NPV) and compensatory afforestation (CA) should be indicate. A copy of the forestry clearance should also be furnished. 12. Implementation status of recognition of forest rights under the Scheduled Tribes and other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated. Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated. 13. The vegetation in the RF/PF area in the study area, with necessary details, should be given. 14. A study shall be got done to ascertain the impact of the Mining Project on wildlife of the study area and details furnished. Impact of the project on the wildlife in the surrounding and any other protected area and accordingly detailed mitigative, measures required, should be worked out with cost implications and submitted. Page 44 of 151

15. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Tiger/Elephant Reserves/lease should be clearly indicated, supported by a location map duly authenticated by Chief Wildlife Warden. Necessary clearance, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above, should be obtained form the State Wildlife Department/Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished. 16. A detailed biological study of the study area (core zone and buffer zone (10km radius of the periphery of the mine lease) shall be carried out. Details of flora and fauna, duly authenticated, separately for core and buffer zone should be furnished based on such primary field survey, clearly indicating the Schedule of the fauna present. In case of any scheduled-1 fauna found in the study area, the necessary pian for their conservation should be prepared in consultation with State Forest and Wildlife Department and details furnished. Necessary allocation of funds for implementing the same should be made as part of the project cost. 17. Proximity to Areas declared a Critically Polluted or the Project areas likely to come under the ‘Aravali Range’ (attracting court restrictions for mining operations), should also be indicated and where so required, clearance certifications from the prescribed Authorities, such as the SPCB or State Mining Dept. should be secured and furnished to the effect that the proposed mining activities could be considered. 18. R&R Plan/ compensation details for the Project Affected People(PAP) should be furnished. While preparing the R&R Plan, the relevant State/ National Rehabilitation & Resettlement Policy should be kept in view in respect of SCs /STs and other weaker sections of the society in the study area, a need based sample survey, family-wise, should be undertaken to assess their requirements, and action programmes prepared and submitted accordingly, integrating the sectoral programmes of line departments of the State Government. It may be clearly brought out whether the village located in the mine lease area will be shifted or not. The issues relating to shifting of village including their R & R and socio-economic aspects should be discussed in the report. 19. One season (non-monsoon) primary baseline data on ambient air quality (PM10, SO2 and NOx), water quality, noise level, soil and flora and fauna shall be collected and the AAQ and other data so compiled presented date wise in the EIA and EMP report. Site-specific meteorological data should also be collected. The location of the monitoring stations should be such as to represent whole of the study area and justified keeping in view the pre-dominant downwind direction and location of sensitive receptors. There should be at least one monitoring stations within 500 meters of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10, particularly for free silica, should be given. 20. Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take into account the impact of movement of vehicles for transportation of mineral. The details of the model used and input parameters used for modeling should be provided. The air quality contours may be shown on the location map clearly indicating the location of the site, location of sensitive receptors, if any, and the habitation. The wind roses shown pre-dominant wind direction may also be indicated on the map. This should also be complied with if the excavated material is stacked outside the mining lease area. 21. The water requirement for the Project, its availability and source should be furnished. A detailed water balance should also be provided. Fresh water requirement for the project should be indicated. 22. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the Project should be provided. 23. Description of water conservation measures proposed to be adopted in the Project should be given. Details of rainwater harvesting proposed in the Project, if any, should be provided. 24. Impact of the project on the water quality, both surface and groundwater should be assessed and necessary safeguard measures, if any required, should be provided. 25. Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed Hydro Geological Study should be undertaken and Report furnished. Necessary permission from /central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished. 26. Details of any stream, seasonal or otherwise, passing through the lease area and modification/ diversion proposed, if any, and the impact of the same on the hydrology should be brought out. Page 45 of 151

27. Information on site elevation, working depth, groundwater table etc. should be provided both in AMSL and BGL. A schematic diagram may also be provided for the same with detailed filed investigation. 28. A time bound Progressive Greenbelt Development plan shall be prepared in a tabular form (indicating the linear and quantitative coverage, plant species and time frame) and submitted, keeping in mind, the same will have to be executed up front on commencement of the project. 29. Impact on local transport infrastructure due to the Project should be indicated .Projected increase in truck traffic as a result of the Project in the present road network (including those outside the Project area) Should be worked out, indicating whether it is capable of handling the incremental load. Arrangement for improving the infrastructure, if contemplated (including action to be taken by other agencies such as State Government) should be covered. 30. Details of the onsite shelter and facilities to be provided to the mine workers should be included in the EIA report. 31. Conceptual Mining Plan post mining land use and Reclamation and Restoration of mined out areas (with plans and with adequate number of sections) should be given in the EIA report. 32. A time bound Progressive Mine Closure Plan shall be prepared in a tabular from (indicating the linear and quantitative coverage plant species and time frame) and submitted. Keeping in mind, the same will have to be executed up front on commencement of the project. Phase-wise plan of restoration of land degraded by mining and compensatory afforestation should be charted clearly indicating the area to be covered under plantation and the species to be planted. The details of plantation already done should be given. 33. Occupational Health impacts of the Project should be anticipated and the proposed preventive measures spelt out in detail. Details of pre-placement medical examination and periodical medical examination schedules should be incorporated in the EMP. 34. Public health implications of the Project and related activities for the population in the impact zone should be systematically evaluated and the proposed remedial measures should be detailed along with budgetary allocations. 35. Measures of socio economic significance and influence to the local community proposed to be provided by the Project Proponent should be indicated. AS far as possible, quantitative dimensions may be given with time frames for implementation. 36. Detailed environmental management plan to mitigate the environmental impacts which should inter-alia include the impacts of change of land use, loss agricultural and grazing land, if any, occupational health impacts besides other impacts specific to the proposed Project. 37. Public hearing points raised and commitment of the project proponent on the same along with time bound action plan to implement the same should be provided and also incorporated in the final EIA/EMP Report of the Project. 38. Details of litigation pending against the project, if any, with direction/order passed by any Court of law against the project should be given. 39. The cost of the project (capital cost and recurring cost) as well as the cost towards implementation of EMP should clearly be spelt out. 40. Details of Transportation of mined out materials as per the Indian Road Congress for both the ways (loaded as well unloaded trucks) load and its impact on Environment. 41. Details of excavation schedule & sequential mining plan to be indicated including depth of mining on year to year basis in terms of MSL. 42. River bed mining proposal should be in consonance with the sand mining guide line given by Ministry of Environment & forest of Climate Change of Govt. of India. Annual excavation proposed should never exceed the replenishment rate. 43. The base line data shall be collected so as to represent the whole mine lease area. 44. Letter from the State Govt. of Forests Department that the Mining Lease Area (MLA) does not fail under forests land category and Aravali Plantation. 45. Details of continuous monitoring stations for Ambient Air Monitoring to be carried out in each block in the core zone area. 46. Disaster management Plan. 47. Project Proponent shall furnish all the analysis/testing reports of water, air, soil, noise etc. using the MoEF/NABL accredited laboratories. All the original analysis/testing reports should be made available during appraisal of the project. Page 46 of 151

48. Details of outcome of the court case in CWP No. 27700 of 2013 before the Hon’ble High Court of Punjab & Haryana as mentioned in the LoI letter issued by the Mines & Geology Department of State Govt. of Haryana. 49. Impact of all existing mines on the present land use in the study area. 50. Details of other Associated minor minerals need to provided. 1. Besides the above, the below mentioned points are also be followed: a) All documents to be properly referenced with index and continuous page numbering. b) Where data are presented in the Report especially in Tables, the period in which the data were collected and the sources should be indicated. c) Project proponent shall enclose all the analysis/testing reports of water, air, soil, noise etc. using the MoEF & CC/NABL accredited laboratories. All the original analysis/testing reports should be available during appraisal of the project. d) Where the documents provided are in a language other than English, an English translation should be provided. e) The Questionnaire for environmental appraisal of mining projects as devised earlier by the Ministry shall also be filled and submitted. f) While preparing the EIA report, the instructions for the Proponents and instructions for the Consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the website of this Ministry, should be followed. g) Changes, if any made in the basic scope and project parameters (as submitted in Form-I and the PFR for securing the TOR) should be brought to the attention of MoEF&CC with reasons for such changes and permission should be sought, as the TOR may also have to be altered. Post Public Hearing changes in structure and content of the draft EIA/EMP (other modifications arising out of the P.H. process) will entail conducting the PH again with the revised documentation. h) As per the circular no. J-11011/618/2010-IA.II(I) dated 30.05.2012, certified report of the status of compliance of the conditions stipulated in the environment clearance for the existing operations of the project, should be obtained from the Regional Officer of Ministry of Environment, Forest and Climate Change, as may be applicable. i) The EIA report should also include (i) surface plan of the area indicating contours of main topographic features, drainage and mining area, (ii) geological maps and sections and (iii) sections of the mine pit and external dumps, if any, clearly showing the land features of the adjoining area. 2. The prescribed TORs would be valid for a period of two years for submission of the EIA/EMP reports, as per the O.M. No. J-11013/41/2006-IA.II(I) dated 22.03.2010. 3. After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will get the public hearing conducted and take further necessary action for obtaining environmental clearance in accordance with the procedure prescribed under the EIA Notification, 2006. 4. Detail calculation of water requirement for various purposes with permissions. 5. Permission of Competent Authority (DGMS) regarding mine safety. 6. Impact of vibration due to use of explosive on surround area alongwith mitigating measures. 7. No mining activity shall be conducted within 500 meters from any hydraulic structure, bridges, pumping station etc. 8. Impact of movement of transportation for carrying mined material on Ambient Air and surrounding area including traffic congestion on roads. 9. No mining activity shall be conducted within 250 meters from outer periphery of major district roads, national highway, state highway and defined village abadi. 10. Impact on Ambient Air and mitigative measures for the same alongwith appropriate plan. 11. Plan for controlling water pollution especially from domestic effluent. 12. Rain water harvesting proposal to be given in detail. 13. Replenishment study report in case of river sand gavel mining proposal. 14. Mining activity shall not change course of river/canal/other water bodies. 15. NOC from forest department for project site. 16. The PP shall comply with all guidelines of MOEF & CC and any orders passed by Hon’ble Supreme Court/High Court/ NGT. 17. NOC from wildlife. Page 47 of 151

18. Permission from Irrigation Department for sand mining from river /canal bed and bund area. 19. Width of Bench shall never be less than bench height. 20. No mechanized mining shall be done in river bed in view of orders of Hon’ble NGT. No mining shall be done in river bed during monsoon period. 21. PP shall not exceed the production of mineral than the production figures mentioned in approved mining plan. 22. Replenishment and drainage study from the reputed institution. 23. Impact of mining activity on adjacent agricultural land with particular reference to run off, soil erosion and loss of top soil due to change in topography. 24. Details of Transportation of mined out materials as per the Indian Road Congress for both the ways (loaded as well as unloaded trucks) load and its impact on Environment. 25. Impact of all existing mining on the present land use in the study area. 26. The PP should submit compliance of all the conditions of Letter of Intent issued by the Mines and Geology Department Haryana. 27. Details of excavation schedule & sequential mining plan. 28. Monitoring of water quality and ground water level. Project proponent further stated that they are already generating data from March, 2016 and requested to utilize the baseline data. The Committee after detailed deliberations not accepted the request of the project proponent and directed to prepare the baseline data from the date of approval of Terms of Reference. The PP will submit Environment Impact Assessment Report by incorporating the Terms of References (ToR) as approved by the Committee within a time schedule in compliance of EIA Notification dated 14.09.2006. It was also decided that their project will be considered as received only after receipt of complete information. 134.14 Environment Clearance for Draft Mining Plan & Progressive Mine Closure Plan for Pichopa Kalan Plot No. 2 Stone Mine along with Associated Minor Minerals (Minor Mineral ) for District Bhiwani, Haryana by M/s Pionerr Partners Project Proponent : Sh. Deepak Aggarwal Consultant : Vardan Enviro Solutions Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 11.05.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for approval of Terms of Reference in the 134th meeting of the SEAC held on 31.05.2016. The project proponent presented the case for proposed ToRs. The PP is directed to prepare the EIA by incorporating the following ToR: 1. Year-wise production details since 1994 should be given, clearly stating the highest production achieved in any one year prior to 1994. It may also be categorically informed whether there had been any increase in production after the EIA Notification, 1994 came into force w.r.t. the highest production achieved prior to 1994. 2. A copy of the document in support of the fact that the proponent is the rightful lessee of the mine should be given. 3. All documents including approved Mining Plan, EIA and Public Hearing should be compatible with one another in terms of the mine lease area, production levels, waste generation and its management and mining technology and should be in the name of the lessee. 4. All corner coordinates of the mine lease area, superimposed on a High Resolution Imagery / toposheet should be provided. Such an Imagery of the proposed area should clearly show the land use and other ecological features of the study area (core and buffer zone). Lease area should be precisely marked in survey of India Topo-sheet of 1:50000. 5. Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be spelt out in the EIA report with description of the prescribed operating Page 48 of 151

process/procedures to bring into focus any infringement/deviation/violation of the environmental or forest norms/ conditions? The hierarchical system or administrative order to the Company to deal with the environmental issues and for ensuring compliance with the EC conditions may be given. The system of reporting of non- compliances/ violations of environmental norms to be Board of Director of the Company and /or shareholders or stakeholders at large may also be detailed in the EIA report. 6. Issues relating to Systematic Mine Development, Mine Safety and Stability in case of open cast working, blasting study etc. should be detailed. The proposed safeguard measures in each case should also be mentioned. Daily explosive consumption and its legitimate storage are to be assessed. Adequate mitigating measures based on scientific studies in respect of blast induced ground vibration flying fragment and air blast are to be taken alongwith requisite precaution. 7. The study area will comprise of 10 km zone around the mine lease from lease periphery and the data contained in the EIA such as waste generation etc. should be for the life of the mine/lease period. 8. Land use of the study area delineating forest area, agricultural land, grazing land, wildlife sanctuary, national park,, migratory routes of fauna, water bodies, human settlements and other ecological features should be indicated. Land use plan of the mine lease area should be prepared to encompass preoperational, operational and post operational phases and submitted. Impact, if any, of change of land use should be given. 9. Mineral resources and reserve in terms of UNFC are to be given duly supported by adequate representative plans and sections. Ultimately mineable limit should also be marked over geological plan and sector. Details of the land for any Over Burden Dumps outside the mine lease, such as extent of land area, distance from mine lease, its land use, R&R issues, if any, should be given. 10. A Certificate from the Competent Authority in the State Forest Department should be provided, confirming the involvement of forest land, if any, in the project area. In the event of any contrary claim by the Project Proponent regarding the status of forests, the site may be inspected by the State Forest Department along with the Regional Office of the Ministry to ascertain the status of forests, based on which, the Certificate in this regard as mentioned above be issued. In all such cases, it would be desirable for representative of the State Forest Department to assist the Expert Appraisal Committee. 11. Status of forestry clearance for the broken up area and virgin forestland involved in the Project including deposition of net present value (NPV) and compensatory afforestation (CA) should be indicate. A copy of the forestry clearance should also be furnished. 12. Implementation status of recognition of forest rights under the Scheduled Tribes and other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated. Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated. 13. The vegetation in the RF/PF area in the study area, with necessary details, should be given. 14. A study shall be got done to ascertain the impact of the Mining Project on wildlife of the study area and details furnished. Impact of the project on the wildlife in the surrounding and any other protected area and accordingly detailed mitigative, measures required, should be worked out with cost implications and submitted. 15. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Tiger/Elephant Reserves/lease should be clearly indicated, supported by a location map duly authenticated by Chief Wildlife Warden. Necessary clearance, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above, should be obtained form the State Wildlife Department/Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished. 16. A detailed biological study of the study area (core zone and buffer zone (10km radius of the periphery of the mine lease) shall be carried out. Details of flora and fauna, duly authenticated, separately for core and buffer zone should be furnished based on such primary field survey, clearly indicating the Schedule of the fauna present. In case of any scheduled-1 fauna found in the study area, the necessary pian for their conservation should be prepared in consultation with State Forest and Wildlife Department and details furnished. Necessary allocation of funds for implementing the same should be made as part of the project cost. 17. Proximity to Areas declared a Critically Polluted or the Project areas likely to come under the ‘Aravali Range’ (attracting court restrictions for mining operations), should also be indicated and where so required, clearance certifications from the prescribed Authorities, such as the SPCB or State Mining Dept. should be secured and furnished to the effect that the proposed mining activities could be considered. Page 49 of 151

18. R&R Plan/ compensation details for the Project Affected People(PAP) should be furnished. While preparing the R&R Plan, the relevant State/ National Rehabilitation & Resettlement Policy should be kept in view in respect of SCs /STs and other weaker sections of the society in the study area, a need based sample survey, family-wise, should be undertaken to assess their requirements, and action programmes prepared and submitted accordingly, integrating the sectoral programmes of line departments of the State Government. It may be clearly brought out whether the village located in the mine lease area will be shifted or not. The issues relating to shifting of village including their R & R and socio-economic aspects should be discussed in the report. 19. One season (non-monsoon) primary baseline data on ambient air quality (PM10, SO2 and NOx), water quality, noise level, soil and flora and fauna shall be collected and the AAQ and other data so compiled presented date wise in the EIA and EMP report. Site-specific meteorological data should also be collected. The location of the monitoring stations should be such as to represent whole of the study area and justified keeping in view the pre-dominant downwind direction and location of sensitive receptors. There should be at least one monitoring stations within 500 meters of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10, particularly for free silica, should be given. 20. Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take into account the impact of movement of vehicles for transportation of mineral. The details of the model used and input parameters used for modeling should be provided. The air quality contours may be shown on the location map clearly indicating the location of the site, location of sensitive receptors, if any, and the habitation. The wind roses shown pre-dominant wind direction may also be indicated on the map. This should also be complied with if the excavated material is stacked outside the mining lease area. 21. The water requirement for the Project, its availability and source should be furnished. A detailed water balance should also be provided. Fresh water requirement for the project should be indicated. 22. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the Project should be provided. 23. Description of water conservation measures proposed to be adopted in the Project should be given. Details of rainwater harvesting proposed in the Project, if any, should be provided. 24. Impact of the project on the water quality, both surface and groundwater should be assessed and necessary safeguard measures, if any required, should be provided. 25. Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed Hydro Geological Study should be undertaken and Report furnished. Necessary permission from /central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished. 26. Details of any stream, seasonal or otherwise, passing through the lease area and modification/ diversion proposed, if any, and the impact of the same on the hydrology should be brought out. 27. Information on site elevation, working depth, groundwater table etc. should be provided both in AMSL and BGL. A schematic diagram may also be provided for the same with detailed filed investigation. 28. A time bound Progressive Greenbelt Development plan shall be prepared in a tabular form (indicating the linear and quantitative coverage, plant species and time frame) and submitted, keeping in mind, the same will have to be executed up front on commencement of the project. 29. Impact on local transport infrastructure due to the Project should be indicated .Projected increase in truck traffic as a result of the Project in the present road network (including those outside the Project area) Should be worked out, indicating whether it is capable of handling the incremental load. Arrangement for improving the infrastructure, if contemplated (including action to be taken by other agencies such as State Government) should be covered. 30. Details of the onsite shelter and facilities to be provided to the mine workers should be included in the EIA report. 31. Conceptual Mining Plan post mining land use and Reclamation and Restoration of mined out areas (with plans and with adequate number of sections) should be given in the EIA report. 32. A time bound Progressive Mine Closure Plan shall be prepared in a tabular from (indicating the linear and quantitative coverage plant species and time frame) and submitted. Keeping in mind, the same will have to be executed up front on commencement of the project. Phase-wise plan of Page 50 of 151

restoration of land degraded by mining and compensatory afforestation should be charted clearly indicating the area to be covered under plantation and the species to be planted. The details of plantation already done should be given. 33. Occupational Health impacts of the Project should be anticipated and the proposed preventive measures spelt out in detail. Details of pre-placement medical examination and periodical medical examination schedules should be incorporated in the EMP. 34. Public health implications of the Project and related activities for the population in the impact zone should be systematically evaluated and the proposed remedial measures should be detailed along with budgetary allocations. 35. Measures of socio economic significance and influence to the local community proposed to be provided by the Project Proponent should be indicated. AS far as possible, quantitative dimensions may be given with time frames for implementation. 36. Detailed environmental management plan to mitigate the environmental impacts which should inter-alia include the impacts of change of land use, loss agricultural and grazing land, if any, occupational health impacts besides other impacts specific to the proposed Project. 37. Public hearing points raised and commitment of the project proponent on the same along with time bound action plan to implement the same should be provided and also incorporated in the final EIA/EMP Report of the Project. 38. Details of litigation pending against the project, if any, with direction/order passed by any Court of law against the project should be given. 39. The cost of the project (capital cost and recurring cost) as well as the cost towards implementation of EMP should clearly be spelt out. 40. Details of Transportation of mined out materials as per the Indian Road Congress for both the ways (loaded as well unloaded trucks) load and its impact on Environment. 41. Details of excavation schedule & sequential mining plan to be indicated including depth of mining on year to year basis in terms of MSL. 42. River bed mining proposal should be in consonance with the sand mining guide line given by Ministry of Environment & forest of Climate Change of Govt. of India. Annual excavation proposed should never exceed the replenishment rate. 43. The base line data shall be collected so as to represent the whole mine lease area. 44. Letter from the State Govt. of Forests Department that the Mining Lease Area (MLA) does not fail under forests land category and Aravali Plantation. 45. Details of continuous monitoring stations for Ambient Air Monitoring to be carried out in each block in the core zone area. 46. Disaster management Plan. 47. Project Proponent shall furnish all the analysis/testing reports of water, air, soil, noise etc. using the MoEF/NABL accredited laboratories. All the original analysis/testing reports should be made available during appraisal of the project. 48. Details of outcome of the court case in CWP No. 27700 of 2013 before the Hon’ble High Court of Punjab & Haryana as mentioned in the LoI letter issued by the Mines & Geology Department of State Govt. of Haryana. 49. Impact of all existing mines on the present land use in the study area. 50. Details of other Associated minor minerals need to provided. 1. Besides the above, the below mentioned points are also be followed: a) All documents to be properly referenced with index and continuous page numbering. b) Where data are presented in the Report especially in Tables, the period in which the data were collected and the sources should be indicated. c) Project proponent shall enclose all the analysis/testing reports of water, air, soil, noise etc. using the MoEF & CC/NABL accredited laboratories. All the original analysis/testing reports should be available during appraisal of the project. d) Where the documents provided are in a language other than English, an English translation should be provided. e) The Questionnaire for environmental appraisal of mining projects as devised earlier by the Ministry shall also be filled and submitted. f) While preparing the EIA report, the instructions for the Proponents and instructions for the Consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the website of this Ministry, should be followed. Page 51 of 151

g) Changes, if any made in the basic scope and project parameters (as submitted in Form-I and the PFR for securing the TOR) should be brought to the attention of MoEF&CC with reasons for such changes and permission should be sought, as the TOR may also have to be altered. Post Public Hearing changes in structure and content of the draft EIA/EMP (other modifications arising out of the P.H. process) will entail conducting the PH again with the revised documentation. h) As per the circular no. J-11011/618/2010-IA.II(I) dated 30.05.2012, certified report of the status of compliance of the conditions stipulated in the environment clearance for the existing operations of the project, should be obtained from the Regional Officer of Ministry of Environment, Forest and Climate Change, as may be applicable. i) The EIA report should also include (i) surface plan of the area indicating contours of main topographic features, drainage and mining area, (ii) geological maps and sections and (iii) sections of the mine pit and external dumps, if any, clearly showing the land features of the adjoining area. 2. The prescribed TORs would be valid for a period of two years for submission of the EIA/EMP reports, as per the O.M. No. J-11013/41/2006-IA.II(I) dated 22.03.2010. 3. After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will get the public hearing conducted and take further necessary action for obtaining environmental clearance in accordance with the procedure prescribed under the EIA Notification, 2006. 4. Detail calculation of water requirement for various purposes with permissions. 5. Permission of Competent Authority (DGMS) regarding mine safety. 6. Impact of vibration due to use of explosive on surround area alongwith mitigating measures. 7. No mining activity shall be conducted within 500 meters from any hydraulic structure, bridges, pumping station etc. 8. Impact of movement of transportation for carrying mined material on Ambient Air and surrounding area including traffic congestion on roads. 9. No mining activity shall be conducted within 250 meters from outer periphery of major district roads, national highway, state highway and defined village abadi. 10. Impact on Ambient Air and mitigative measures for the same alongwith appropriate plan. 11. Plan for controlling water pollution especially from domestic effluent. 12. Rain water harvesting proposal to be given in detail. 13. Replenishment study report in case of river sand gavel mining proposal. 14. Mining activity shall not change course of river/canal/other water bodies. 15. NOC from forest department for project site. 16. The PP shall comply with all guidelines of MOEF & CC and any orders passed by Hon’ble Supreme Court/High Court/ NGT. 17. NOC from wildlife. 18. Permission from Irrigation Department for sand mining from river /canal bed and bund area. 19. Width of Bench shall never be less than bench height. 20. No mechanized mining shall be done in river bed in view of orders of Hon’ble NGT. No mining shall be done in river bed during monsoon period. 21. PP shall not exceed the production of mineral than the production figures mentioned in approved mining plan. 22. Replenishment and drainage study from the reputed institution. 23. Impact of mining activity on adjacent agricultural land with particular reference to run off, soil erosion and loss of top soil due to change in topography. 24. Details of Transportation of mined out materials as per the Indian Road Congress for both the ways (loaded as well as unloaded trucks) load and its impact on Environment. 25. Impact of all existing mining on the present land use in the study area. 26. The PP should submit compliance of all the conditions of Letter of Intent issued by the Mines and Geology Department Haryana. 27. Details of excavation schedule & sequential mining plan. 28. Monitoring of water quality and ground water level. Page 52 of 151

Project proponent further stated that they are already generating data from March, 2016 and requested to utilize the baseline data. The Committee after detailed deliberations not accepted the request of the project proponent and directed to prepare the baseline data from the date of approval of Terms of Reference. The PP will submit Environment Impact Assessment Report by incorporating the Terms of References (ToR) as approved by the Committee within a time schedule in compliance of EIA Notification dated 14.09.2006. It was also decided that their project will be considered as received only after receipt of complete information. 134.15 Environment Clearance for proposed “Stone Along with Associated Minor Mineral” Mines of “Kalyana Plot No. 2”under Category B 1, Tehsil-Dadri, District-Bhiwani, Haryana having area of 29.50 Ha. by M/s SBIPL Projects Ltd. Project Proponent : Sh. Vineet Aggarwal Consultant : Vardan Enviro Solutions Pvt. Ltd. The project was submitted to the SEIAA, Haryana on 11.05.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for approval of Terms of Reference in the 134th meeting of the SEAC held on 31.05.2016. The project proponent presented the case for proposed ToRs. The PP is directed to prepare the EIA by incorporating the following ToR: 1. Year-wise production details since 1994 should be given, clearly stating the highest production achieved in any one year prior to 1994. It may also be categorically informed whether there had been any increase in production after the EIA Notification, 1994 came into force w.r.t. the highest production achieved prior to 1994. 2. A copy of the document in support of the fact that the proponent is the rightful lessee of the mine should be given. 3. All documents including approved Mining Plan, EIA and Public Hearing should be compatible with one another in terms of the mine lease area, production levels, waste generation and its management and mining technology and should be in the name of the lessee. 4. All corner coordinates of the mine lease area, superimposed on a High Resolution Imagery /toposheet should be provided. Such an Imagery of the proposed area should clearly show the land use and other ecological features of the study area (core and buffer zone). Lease area should be precisely marked in survey of India Topo-sheet of 1:50000. 5. Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be spelt out in the EIA report with description of the prescribed operating process/procedures to bring into focus any infringement/deviation/violation of the environmental or forest norms/ conditions? The hierarchical system or administrative order to the Company to deal with the environmental issues and for ensuring compliance with the EC conditions may be given. The system of reporting of non- compliances/ violations of environmental norms to be Board of Director of the Company and /or shareholders or stakeholders at large may also be detailed in the EIA report. 6. Issues relating to Systematic Mine Development, Mine Safety and Stability in case of open cast working, blasting study etc. should be detailed. The proposed safeguard measures in each case should also be mentioned. Daily explosive consumption and its legitimate storage are to be assessed. Adequate mitigating measures based on scientific studies in respect of blast induced ground vibration flying fragment and air blast are to be taken alongwith requisite precaution. 7. The study area will comprise of 10 km zone around the mine lease from lease periphery and the data contained in the EIA such as waste generation etc. should be for the life of the mine/lease period. 8. Land use of the study area delineating forest area, agricultural land, grazing land, wildlife sanctuary, national park,, migratory routes of fauna, water bodies, human settlements and other ecological features should be indicated. Land use plan of the mine lease area should be prepared Page 53 of 151

to encompass preoperational, operational and post operational phases and submitted. Impact, if any, of change of land use should be given. 9. Mineral resources and reserve in terms of UNFC are to be given duly supported by adequate representative plans and sections. Ultimately mineable limit should also be marked over geological plan and sector. Details of the land for any Over Burden Dumps outside the mine lease, such as extent of land area, distance from mine lease, its land use, R&R issues, if any, should be given. 10. A Certificate from the Competent Authority in the State Forest Department should be provided, confirming the involvement of forest land, if any, in the project area. In the event of any contrary claim by the Project Proponent regarding the status of forests, the site may be inspected by the State Forest Department along with the Regional Office of the Ministry to ascertain the status of forests, based on which, the Certificate in this regard as mentioned above be issued. In all such cases, it would be desirable for representative of the State Forest Department to assist the Expert Appraisal Committee. 11. Status of forestry clearance for the broken up area and virgin forestland involved in the Project including deposition of net present value (NPV) and compensatory afforestation (CA) should be indicate. A copy of the forestry clearance should also be furnished. 12. Implementation status of recognition of forest rights under the Scheduled Tribes and other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated. Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 should be indicated. 13. The vegetation in the RF/PF area in the study area, with necessary details, should be given. 14. A study shall be got done to ascertain the impact of the Mining Project on wildlife of the study area and details furnished. Impact of the project on the wildlife in the surrounding and any other protected area and accordingly detailed mitigative, measures required, should be worked out with cost implications and submitted. 15. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Tiger/Elephant Reserves/lease should be clearly indicated, supported by a location map duly authenticated by Chief Wildlife Warden. Necessary clearance, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above, should be obtained form the State Wildlife Department/Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished. 16. A detailed biological study of the study area (core zone and buffer zone (10km radius of the periphery of the mine lease) shall be carried out. Details of flora and fauna, duly authenticated, separately for core and buffer zone should be furnished based on such primary field survey, clearly indicating the Schedule of the fauna present. In case of any scheduled-1 fauna found in the study area, the necessary pian for their conservation should be prepared in consultation with State Forest and Wildlife Department and details furnished. Necessary allocation of funds for implementing the same should be made as part of the project cost. 17. Proximity to Areas declared a Critically Polluted or the Project areas likely to come under the ‘Aravali Range’ (attracting court restrictions for mining operations), should also be indicated and where so required, clearance certifications from the prescribed Authorities, such as the SPCB or State Mining Dept. should be secured and furnished to the effect that the proposed mining activities could be considered. 18. R&R Plan/ compensation details for the Project Affected People(PAP) should be furnished. While preparing the R&R Plan, the relevant State/ National Rehabilitation & Resettlement Policy should be kept in view in respect of SCs /STs and other weaker sections of the society in the study area, a need based sample survey, family-wise, should be undertaken to assess their requirements, and action programmes prepared and submitted accordingly, integrating the sectoral programmes of line departments of the State Government. It may be clearly brought out whether the village located in the mine lease area will be shifted or not. The issues relating to shifting of village including their R & R and socio-economic aspects should be discussed in the report. 19. One season (non-monsoon) primary baseline data on ambient air quality (PM10, SO2 and NOx), water quality, noise level, soil and flora and fauna shall be collected and the AAQ and other data so compiled presented date wise in the EIA and EMP report. Site-specific meteorological data should also be collected. The location of the monitoring stations should be such as to represent whole of the study area and justified keeping in view the pre-dominant downwind direction and location of sensitive receptors. There should be at least one monitoring stations within 500 meters of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10, particularly for free silica, should be given. Page 54 of 151

20. Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take into account the impact of movement of vehicles for transportation of mineral. The details of the model used and input parameters used for modeling should be provided. The air quality contours may be shown on the location map clearly indicating the location of the site, location of sensitive receptors, if any, and the habitation. The wind roses shown pre-dominant wind direction may also be indicated on the map. This should also be complied with if the excavated material is stacked outside the mining lease area. 21. The water requirement for the Project, its availability and source should be furnished. A detailed water balance should also be provided. Fresh water requirement for the project should be indicated. 22. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the Project should be provided. 23. Description of water conservation measures proposed to be adopted in the Project should be given. Details of rainwater harvesting proposed in the Project, if any, should be provided. 24. Impact of the project on the water quality, both surface and groundwater should be assessed and necessary safeguard measures, if any required, should be provided. 25. Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed Hydro Geological Study should be undertaken and Report furnished. Necessary permission from /central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished. 26. Details of any stream, seasonal or otherwise, passing through the lease area and modification/ diversion proposed, if any, and the impact of the same on the hydrology should be brought out. 27. Information on site elevation, working depth, groundwater table etc. should be provided both in AMSL and BGL. A schematic diagram may also be provided for the same with detailed filed investigation. 28. A time bound Progressive Greenbelt Development plan shall be prepared in a tabular form (indicating the linear and quantitative coverage, plant species and time frame) and submitted, keeping in mind, the same will have to be executed up front on commencement of the project. 29. Impact on local transport infrastructure due to the Project should be indicated .Projected increase in truck traffic as a result of the Project in the present road network (including those outside the Project area) Should be worked out, indicating whether it is capable of handling the incremental load. Arrangement for improving the infrastructure, if contemplated (including action to be taken by other agencies such as State Government) should be covered. 30. Details of the onsite shelter and facilities to be provided to the mine workers should be included in the EIA report. 31. Conceptual Mining Plan post mining land use and Reclamation and Restoration of mined out areas (with plans and with adequate number of sections) should be given in the EIA report. 32. A time bound Progressive Mine Closure Plan shall be prepared in a tabular from (indicating the linear and quantitative coverage plant species and time frame) and submitted. Keeping in mind, the same will have to be executed up front on commencement of the project. Phase-wise plan of restoration of land degraded by mining and compensatory afforestation should be charted clearly indicating the area to be covered under plantation and the species to be planted. The details of plantation already done should be given. 33. Occupational Health impacts of the Project should be anticipated and the proposed preventive measures spelt out in detail. Details of pre-placement medical examination and periodical medical examination schedules should be incorporated in the EMP. 34. Public health implications of the Project and related activities for the population in the impact zone should be systematically evaluated and the proposed remedial measures should be detailed along with budgetary allocations. 35. Measures of socio economic significance and influence to the local community proposed to be provided by the Project Proponent should be indicated. AS far as possible, quantitative dimensions may be given with time frames for implementation. 36. Detailed environmental management plan to mitigate the environmental impacts which should inter-alia include the impacts of change of land use, loss agricultural and grazing land, if any, occupational health impacts besides other impacts specific to the proposed Project. Page 55 of 151

37. Public hearing points raised and commitment of the project proponent on the same along with time bound action plan to implement the same should be provided and also incorporated in the final EIA/EMP Report of the Project. 38. Details of litigation pending against the project, if any, with direction/order passed by any Court of law against the project should be given. 39. The cost of the project (capital cost and recurring cost) as well as the cost towards implementation of EMP should clearly be spelt out. 40. Details of Transportation of mined out materials as per the Indian Road Congress for both the ways (loaded as well unloaded trucks) load and its impact on Environment. 41. Details of excavation schedule & sequential mining plan to be indicated including depth of mining on year to year basis in terms of MSL. 42. River bed mining proposal should be in consonance with the sand mining guide line given by Ministry of Environment & forest of Climate Change of Govt. of India. Annual excavation proposed should never exceed the replenishment rate. 43. The base line data shall be collected so as to represent the whole mine lease area. 44. Letter from the State Govt. of Forests Department that the Mining Lease Area (MLA) does not fail under forests land category and Aravali Plantation. 45. Details of continuous monitoring stations for Ambient Air Monitoring to be carried out in each block in the core zone area. 46. Disaster management Plan. 47. Project Proponent shall furnish all the analysis/testing reports of water, air, soil, noise etc. using the MoEF/NABL accredited laboratories. All the original analysis/testing reports should be made available during appraisal of the project. 48. Details of outcome of the court case in CWP No. 27700 of 2013 before the Hon’ble High Court of Punjab & Haryana as mentioned in the LoI letter issued by the Mines & Geology Department of State Govt. of Haryana. 49. Impact of all existing mines on the present land use in the study area. 50. Details of other Associated minor minerals need to provided. 1. Besides the above, the below mentioned points are also be followed: a) All documents to be properly referenced with index and continuous page numbering. b) Where data are presented in the Report especially in Tables, the period in which the data were collected and the sources should be indicated. c) Project proponent shall enclose all the analysis/testing reports of water, air, soil, noise etc. using the MoEF & CC/NABL accredited laboratories. All the original analysis/testing reports should be available during appraisal of the project. d) Where the documents provided are in a language other than English, an English translation should be provided. e) The Questionnaire for environmental appraisal of mining projects as devised earlier by the Ministry shall also be filled and submitted. f) While preparing the EIA report, the instructions for the Proponents and instructions for the Consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the website of this Ministry, should be followed. g) Changes, if any made in the basic scope and project parameters (as submitted in Form-I and the PFR for securing the TOR) should be brought to the attention of MoEF&CC with reasons for such changes and permission should be sought, as the TOR may also have to be altered. Post Public Hearing changes in structure and content of the draft EIA/EMP (other modifications arising out of the P.H. process) will entail conducting the PH again with the revised documentation. h) As per the circular no. J-11011/618/2010-IA.II(I) dated 30.05.2012, certified report of the status of compliance of the conditions stipulated in the environment clearance for the existing operations of the project, should be obtained from the Regional Officer of Ministry of Environment, Forest and Climate Change, as may be applicable. i) The EIA report should also include (i) surface plan of the area indicating contours of main topographic features, drainage and mining area, (ii) geological maps and sections and (iii) sections of the mine pit and external dumps, if any, clearly showing the land features of the adjoining area. Page 56 of 151

2. The prescribed TORs would be valid for a period of two years for submission of the EIA/EMP reports, as per the O.M. No. J-11013/41/2006-IA.II(I) dated 22.03.2010. 3. After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will get the public hearing conducted and take further necessary action for obtaining environmental clearance in accordance with the procedure prescribed under the EIA Notification, 2006. 4. Detail calculation of water requirement for various purposes with permissions. 5. Permission of Competent Authority (DGMS) regarding mine safety. 6. Impact of vibration due to use of explosive on surround area alongwith mitigating measures. 7. No mining activity shall be conducted within 500 meters from any hydraulic structure, bridges, pumping station etc. 8. Impact of movement of transportation for carrying mined material on Ambient Air and surrounding area including traffic congestion on roads. 9. No mining activity shall be conducted within 250 meters from outer periphery of major district roads, national highway, state highway and defined village abadi. 10. Impact on Ambient Air and mitigative measures for the same alongwith appropriate plan. 11. Plan for controlling water pollution especially from domestic effluent. 12. Rain water harvesting proposal to be given in detail. 13. Replenishment study report in case of river sand gavel mining proposal. 14. Mining activity shall not change course of river/canal/other water bodies. 15. NOC from forest department for project site. 16. The PP shall comply with all guidelines of MOEF & CC and any orders passed by Hon’ble Supreme Court/High Court/ NGT. 17. NOC from wildlife. 18. Permission from Irrigation Department for sand mining from river /canal bed and bund area. 19. Width of Bench shall never be less than bench height. 20. No mechanized mining shall be done in river bed in view of orders of Hon’ble NGT. No mining shall be done in river bed during monsoon period. 21. PP shall not exceed the production of mineral than the production figures mentioned in approved mining plan. 22. Replenishment and drainage study from the reputed institution. 23. Impact of mining activity on adjacent agricultural land with particular reference to run off, soil erosion and loss of top soil due to change in topography. 24. Details of Transportation of mined out materials as per the Indian Road Congress for both the ways (loaded as well as unloaded trucks) load and its impact on Environment. 25. Impact of all existing mining on the present land use in the study area. 26. The PP should submit compliance of all the conditions of Letter of Intent issued by the Mines and Geology Department Haryana. 27. Details of excavation schedule & sequential mining plan. 28. Monitoring of water quality and ground water level. Project proponent further stated that they are already generating data from March, 2016 and requested to utilize the baseline data. The Committee after detailed deliberations not accepted the request of the project proponent and directed to prepare the baseline data from the date of approval of Terms of Reference. The PP will submit Environment Impact Assessment Report by incorporating the Terms of References (ToR) as approved by the Committee within a time schedule in compliance of EIA Notification dated 14.09.2006. It was also decided that their project will be considered as received only after receipt of complete information.

Page 57 of 151

134.16 Environment Clearance for proposed River Bed Minor Mineral Mining Project “Mandlai 1 Block/Panchkula B 21” Village-Mandlai, Tehsil-Raipur Rani, District- Panchkula, Haryana area 13.20 Ha. by M/s Shri Ranbir Singh S/o Sh. Mohinder Singh Project Proponent : Sh. Ranbir Singh Consultant : ENVIRTA Sustainable The project was submitted to the SEIAA, Haryana on 23.02.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 133rd meeting of the SEAC held on 05.05.2016.

After detailed discussions, the following shortcomings were observed: 1. The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim. 2. The PP should submit the plan for conservation of flora and fauna to the wildlife warden. 3. The PP should submit revised CSR plan and revised Environment Management Plan. 4. The PP should submit disaster management plan. 5. The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. 6. The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. 7. The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. 8. The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. 9. The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. The project proponent had undertaken to submit compliance of above points within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 31.05.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 31.05.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 31.05.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 31.05.2016.

During discussions, Project Proponent informed the Committee that it is a proposed River Bed Boulder, Gravel and Sand (Minor Mineral) Mining Project and area of 13.20 Ha. Mandlai 1 Block/PKL B21, Khasra Number 83 Min in Tehsil Raipur Rani, District Panchkula, Haryana having production capacity 5,94,000 MTPA. The mine lease area13.20 Ha. lies in Village Mandlai. The land use of the lease area is River bed (Sangrel River)/ Government land (Gar, Mumkin, Nadi, Nala). The LOI of mining lease was granted to M/s Sh Ranbir Singh, S/o Sh Mohinder Singh by Mines & Geology department, Haryana vide Memo No. DMG/Hy/Cont/Mandlai 1 Block/PKL B 21/2015/3675 Page 58 of 151

dated 09.06.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter No. DMG/HY/MP/PKL-21/ 8948 to 8951 dated 18/11/2015. The Latitudes and Longitudes of MLA North 30° 34' 18.288" and 30° 34' 14.150” and East 77° 6' 25.770" and 77° 6' 29.909" on Survey of India toposheet (OSM) numbers H43K13. The Project is located in Seismic Zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is less than 25 Ha. and no another lease area within 500 m radius hence, the project falls under B2 category. Method of mining is Open-cast semi mechanized method. The total water requirement is 13.11 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto three meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 10-15 m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that there is no any Wildlife Sanctuary or National Park towards as shown on toposheet (SoI). The capital cost of the project is Rs. 70 Lakhs; for CSR Rs. 2 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 7 Lakhs. Budget for Occupational Health and Safety is Rs. 1 Lakhs. The project proponent will deposit 10% of the due contract money along with monthly installments towards the ‘Mines and Minerals Development, Restoration and Rehabilitation Fund’.

There is no lease area within 500m radius from this mining Stone Block, hence this mine block falls under category B2. A certificate in this regard was issued by Mining Officer, Panchkula vide letter No. MO/PKL B21/249 dated 25.01.2016. In view of the MOEF&CC OM dated 24.12.2013 and MoEF&CC notification dated 15.01.2016 this mining project was appraised under category B2. The Committee unanimously decided to appraise the case under B2 category project on the basis of Ministry of Environment, Government of India, Office Memorandum dated 24.12.2013, and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 5,94,000 TPA. The ultimate depth of Mining will be 3 meter. The alivation range of mine site is 349-353 amsl. The Corner Coordinates of the leased area are: Corners Latitudes Longitudes A. 77° 6' 25.770" E 30° 34' 18.288" N B. 77° 6' 37.992" E 30° 34' 4.815" N C. 77° 6' 40.783" E 30° 33' 38.735" N D. 77° 6' 37.223" E 30° 33' 34.982" N Page 59 of 151

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 1980 Mt/day @ 66 Trips/day (30 Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages.. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. Page 60 of 151

[20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 7 lakhs as capital cost & Rs 10.5 Lakhs as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of Rs. 2.0 Lakhs shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 1 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours.. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. Page 61 of 151

[35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. Page 62 of 151

[xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

134.17 Environment Clearance for proposed Boulder, Gravel and Sand Minor Mineral, at Village-Gorakhnath, Tehsil & District- Panchkula, State Haryana area 12.94 Ha. by M/s Shri Nasib Singh Project Proponent : Sh. Nasib Singh Consultant : ENVIRTA Sustainable The project was submitted to the SEIAA, Haryana on 23.02.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 133rd meeting of the SEAC held on 05.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [10] The PP should submit revised clearance from forest department for non applicability of forest area in Khasra number 28 min or should submit an affidavit that they will not do mining in Khasra number 28 min. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the Page 63 of 151

SEAC to be held on 31.05.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 31.05.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 31.05.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 31.05.2016. During discussions, Project Proponent informed the Committee that it is a proposed River Bed Boulder, Gravel and Sand (Minor Mineral) Mining Project and area of 12.94 Ha. Gorakhnath Block/PKL B1 & 2, Khasra Numbers: 172 Min, 214 Min (Gorakhnath), 28 Min, 50/2 Min (Lehrondi),129 Min,186 Min (Khuda Bax Bahnoi) in Tehsil & District Panchkula, Haryana having production capacity 5,82,300 MTPA. The mine lease area 12.94 Ha. lies in Village Gorakhnath. The land use of the lease area is River bed (Maharanwali River & Ramnagar river)/ Government land (Gar, Mumkin, Nadi, Nala. The LOI of mining lease was granted to M/s Sh Nasib Singh, S/o Sh Hardeep Singh. by Mines & Geology department, Haryana vide Memo No. DMG/Hy/Cont/G.Nath Block/PKL B1 & B2/2015/3669 dated 09.06.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter No. DMG/HY/MP/PKL B B1 & B2/8956 - 8959 dated 18/11/2015. The Latitudes and Longitudes of MLA North 30° 54' 6.610" N and 30° 52' 54.338" N and East 76 ° 48' 21.641" E and 76° 53' 32.455" E on Survey of India toposheet (OSM) numbers H43/L2. The Project is located in Seismic Zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is less than 25 Ha. and no another lease area within 500 m radius hence, the project falls under B2 category. Method of mining is Open-cast semi mechanized method. The total water requirement is 15 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto three meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 10-15 m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that there is no any Wildlife Sanctuary or National Park towards as shown on toposheet (SoI). The capital cost of the project is Rs. 75 Lakhs; for CSR Rs. 2 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 7 Lakhs. Budget for Occupational Health and Safety is Rs. 1 Lakhs. The project proponent will deposit 10% of the due contract money along with monthly installments towards the ‘Mines and Minerals Development, Restoration and Rehabilitation Fund’. There is no lease area within 500m radius from this mining Stone Block, hence this mine block falls under category B2. A certificate in this regard was issued by Mining Officer, Panchkula vide letter No. MO/PKL/B1 & 2 /250 dated 25.01.2016. In view of the MOEF&CC OM Page 64 of 151

dated 24.12.2013 and MoEF&CC notification dated 15.01.2016 this mining project was appraised under category B2. The Committee unanimously decided to appraise the case under B2 category project on the basis of Ministry of Environment, Government of India, Office Memorandum dated 24.12.2013, and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 5,82,300 TPA. The ultimate depth of Mining will be 3 meter. The alivation range of mine site is 400-600 amsl. The Corner Coordinates of the leased area are: Corners Longitudes Latitudes A. 76 ° 48' 21.641" E 30° 54' 6.610" N B. 76° 48' 26.922" E 30° 54' 2.536" N C. 76° 48' 20.132" E 30° 54' 2.687" N D. 76° 48' 29.034" E 30° 53' 55.294" N

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 1941 Mt/day @ 65 Trips/day (30 Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. Page 65 of 151

[13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. Page 66 of 151

[29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 7 lakhs as capital cost & Rs 10.5 Lakhs as cost for implementing various environmental protection measures including recurring expenses per year.. [30] A sum of Rs. 2.0 Lakhs shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 1 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. Page 67 of 151

[viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

134.18 Environment Clearance for proposed Boulder, Gravel and Sand Minor Mineral, at Village – Kiratpur and Paploha, Tehsil – & District – Panchkula, State Haryana area 13.40 Ha. by M/s Barwala Royality Company Project Proponent : Sh. Kushal Kumar Consultant : ENVIRTA Sustainable The project was submitted to the SEIAA, Haryana on 23.02.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 133rd meeting of the SEAC held on 05.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. Page 68 of 151

[4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 31.05.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 31.05.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 31.05.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 31.05.2016.

During discussions, Project Proponent informed the Committee that it is a proposed River Bed Boulder, Gravel and Sand (Minor Mineral) Mining Project and area of 13.40 Ha. Kiratpur Block/PKL B 5 & 6, Khasra Numbers 75 Min, 157 Min,137 Min,126 Min,102 Min (Kiratpur), 18/43/3 (Paploha) in Tehsil Kalka & District Panchkula, Haryana having production capacity 6,03,000 MTPA. The mine lease area 13.40 Ha. lies in Village Kiratpur & Paploha. The land use of the lease area is River bed (Kiratpur River)/ Government & Private land (Gar, Mumkin, Nadi, Nala). The LOI of mining lease was granted to M/s M/s Barwala Royalty Company. by Mines & Geology department, Haryana vide Memo No. DMG/Hy/Cont/K.Pur Block/PKL B 5 & B6/2015/3671 dated 09.06.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter No. DMG/HY/M Plan/K.Pur/PKL B 5 & 6/2015/8795-98 dated 05/11/2015. The Latitudes and Longitudes of MLA in village Kiratpur is North 30°50'48.22" and 30°50'41.63" and East 76°52'12.0" to 76°52'44.17" & in Village Paploha is North 30°51'12.00" to 30°51'11.30" and East 76°54'2.20" to 76°54'12.89" on Survey of India toposheet (OSM) numbers H43K13. The Project is located in Seismic Zone- IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is less than 25 Ha. and no another lease area within 500 m radius hence, the project falls under B2 category. Page 69 of 151

Method of mining is Open-cast semi mechanized method . The total water requirement is 13 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto three meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 10-15 m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that there is no any Wildlife Sanctuary or National Park towards as shown on toposheet (SoI). The capital cost of the project is Rs. 72 Lakhs; for CSR Rs. 2 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 7 Lakhs. Budget for Occupational Health and Safety is Rs. 1 Lakhs. The project proponent will deposit 10% of the due contract money along with monthly installments towards the ‘Mines and Minerals Development, Restoration and Rehabilitation Fund’. There is no lease area within 500m radius from this mining Stone Block, hence this mine block falls under category B2. A certificate in this regard was issued by Mining Officer, Panchkula vide letter No. MO/PKL/K.Block/PKL B5 &6/276 dated 02.02.2016. In view of the MOEF&CC OM dated 24.12.2013 and MoEF&CC notification dated 15.01.2016 this mining project was appraised under category B2. The Committee unanimously decided to appraise the case under B2 category project on the basis of Ministry of Environment, Government of India, Office Memorandum dated 24.12.2013, and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 6,03,000TPA. The ultimate depth of Mining will be 3 meter. The alivation range of mine site is 490-510 amsl. The Corner Coordinates of the leased area are: Block Latitude Longitude

Kiratpur 30°50'48.22"N 76°52'12.0"E

30°50'41.63"N 76°52'44.17"E

Paploha 30°51'12.00"N 76°54'2.20"E

30°51'11.30"N 76°54'12.89"E

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records Page 70 of 151

maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 2010 Mt/day @ 67 Trips/day (3Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. Page 71 of 151

[24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 7 lakhs as capital cost & Rs 10.5 Lakhs as cost for implementing various environmental protection measures including recurring expenses per year. . [30] A sum of Rs. 2.0 Lakhs shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 1 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. Page 72 of 151

[38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made.

[iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests Page 73 of 151

with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

134.19 Environment Clearance for “Bir Tapu YNR B-07 Sand Mine (Minor Mineral )” at Village –Birtapu, Tehsil –Jagadhari, District-Yamuna Nagar, Haryana of area 14.45 Ha. by M/s Routes & Journeys Project Proponent : Sh. Iqbal Khan Consultant : MANTEC The project was submitted to the SEIAA, Haryana on 31.03.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 133rd meeting of the SEAC held on 05.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [10] The PP should submit revised clearance from forest department for non applicability of forest area in Khasra number 17/25 of village Birtapu or should submit an affidavit that they will not do mining in Khasra number 17/25 of village Birtapu. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 31.05.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be Page 74 of 151

considered in the next meeting to be held on 31.05.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 31.05.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 31.05.2016.

During discussions, it was informed that it is a proposed mining of sand (Minor Mineral) Mining Project with production capacity of 6.15 Lakh MTPA ( Khasra No:- 17//1/1,1/2,2 to 14, 15/1,15/2, 16 min, 20,21, 25 min, 18//3 min, 4, 5, 6, 7, 8, 9 min, 12 min 13 to 19, 20 min, 21 min, 22 to 25, Area – 14.45ha). The Mine is located at Village Birtapu, Tehsil: Jagadri, District- Yamunanagar, Haryana. The geographical extents of mining lease area are: Latitudes: N 300 06’ 46” to N300 06’ 56” E 770 23’ 40” to E770 24’06”. This is a category ‘B2’ project. The Letter of Intent of mining lease was granted by Director, Mines & Geology department, Chandigarh, Haryana on 19/06/2015, vide memo No. DMG/HY/Cont/ B.Tapu Block/YNR B 7/2015/3921 for the period of 07 years to M/s Routes & Journeys' Through Sh. Sanjay Kumar S/o Sh. Ram Kishore Singh. The Mining Plan was approved by Director General, Mines and Geology Department, Govt. of Haryana vide letter No. DMG / HY/ MP / Birtapu/UNR B-7/2015 dated 08.01.2016 for Mining of“ Sand minor minerals” in Birtapu over an area of 14.45 hectares in Tehsil- Jagadri, District- Yamunanagar, Haryana for a period of 7 Years. Method of mining will be done as per the NGT Orders. The total geological reserves are 9,50,000 MT. Total water requirement for the project will be 15.0 KLD which will be used about 2.0 KLD for the drinking & domestic purpose, 3.0 KLD for the green area development and 10 KLD for dust suppression and sourced from Tanker supply. Hence, Mining will not intersect groundwater table. There is no National Park, Wild Life sanctuaries, Biosphere Reserves, Tiger Reserves, Wild life Corridors etc. within 10 km radius. The PP also submitted the Wildlife NOC from Haryana Forest Department. The cost of the project is Rs. 19 Crore and Environment Protection Cost is Rs. 64 Lakh and CSR cost is Rs. 33 Lakh for 5 years. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is less than 25 Ha. and no another lease area within 500 m radius hence, the project falls under B2 category.

The project proponent further informed the Committee that they submitted the Conservation Plan for schedule I & II species and is under process of approval. The Committee unanimously decided to appraise the case under B2 category project on the basis of Ministry of Environment, Government of India, Office Memorandum dated 24.12.2013, and recommended for grant of Environmental Clearance to SEIAA with the following conditions:

A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 6, 15, 000 TPA. The ultimate depth of Mining will be 3 meter. The alivation range of mine site is 269 amsl to 270 amsl. The Corner Coordinates of the leased area are: Page 75 of 151

Corners Latitudes Longitudes A 30°6.857"N 77°23.639" N B 30°6.676"N 77°23.432" N C 30°6.821"N 77°23.898" N D 30°6.681"N 77°23.878" N

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 2050 Mt/day @ 82 Trips/day (25 Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. Page 76 of 151

[16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 64 lakhs (five year paln) as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of Rs. 33 lakhs shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the Page 77 of 151

nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 3.5 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made.

[iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. Page 78 of 151

[ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution. 134.20 Environment Clearance for “Extraction of Dolomite and Beryte, along with associated minor mineral (Road Metal & Mahendergarh, Haryana of area 4.80 Ha. by M/s Xandy Mines & Minerals Project Proponent : Sh. Ashwani Khurana Consultant: Mantech The project was submitted to the SEIAA, Haryana on 31.03.2016. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit contour sheet of the area. [4] The PP should submit detailed rain water harvesting plan for lease area. [5] The PP should submit the detail calculation of water requirement for various uses. Page 79 of 151

[6] The PP should submit plan for green area development. [7] The PP should submit revise CSR plan. [8] The PP should submit monitoring data of ambient air, water quality and noise monitoring data. [9] The PP should submit clarification regarding non applicability of provisions of EIA Notification as per condition No. 5 of LOI. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 31.05.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 31.05.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 31.05.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 31.05.2016.

During discussions, Project Proponent informed that it is a proposed “Extraction of Dolomite and Beryte, along with associated minor mineral (Road Metal & Mahendergarh, Haryana of area 4.80 Ha. (Khasra Number 109 min)) having coordinates Latitude: 27o 50’ 15” N to 27o 50’ 36” N, Longitude: 76o 02’ 42” E to 76o 02’ 58”E. This is a category ‘B2’ project. The Letter of Intent has been issued to M/s Xandy Mines and Minerals by Director General, Mines and Geology, Haryana vide memo number-GLG/HY/E-2612/3912 dated 28.08.2014.

The Mining Plan was approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. GLG/HY/E-2612 dated 30.12.2015 for Mining of “Dolomite and Baryte along with associated Minerals(Minor)” of 4.8 hectares in Village- Donkhera, Tehsil- Narnaul, District-Mahendergarh, Haryana for a period of 20 Years. Method of mining will be opencast, mechanized with drilling and blasting. The total mineable reserves are 4778250 MT. Life of mine is 20 years. Total water requirement for the project will be 4 KLD which will be used about 1.0 KLD for the drinking purpose, 1.0 KLD for the green area development and 2.0 KLD for dust suppression and sourced from Tanker supply. Ultimate working depth is at 385 mRL. Ground water table of lease area is at 40-50 mtrs. Hence, Mining will not intersect ground water table. There is no National Park, Wild Life sanctuaries, Biosphere Reserves, Tiger Reserves, Wildlife Corridors etc. within 10 km radius. The cost of the project is Rs. 19 Crores and Environment Protection Cost is Rs. 7.6 Lakh and CSR cost is Rs. 15 Lakh for 5 years. The project proponent further informed the Committee that they have obtained clarification from the Mining Officer, Narnaul regarding no other operational mine falling within the 500 meters periphery and does not exceed 25 hectares. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is less than 25 Ha. and no another lease area within 500 m radius hence, the project falls under B2 category. Page 80 of 151

The Committee unanimously decided to appraise the case under B2 category project on the basis of Ministry of Environment, Government of India, Office Memorandum dated 31.05.2016, and recommended for grant of Environmental Clearance to SEIA A with the following conditions:

A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for Production of Stone along with Associated Minerals as per below mentioned figures. Year Bench mrl Production(MT) First 364 and 358 3,21,650 Second 364,358 and 352 3,25,250 Third 370,364,358 and 352 3,25,250 Fourth 370,364,358 and 352 3,25,100 Fifth 352 and 346 3,25,100

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from HSPCB and effectively implement all the conditions stipulated by the HSPCB. [3] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [4] The project proponent shall ensure that the mining operations shall not intersect groundwater table and the mining operation should be restricted at least 3 meter above the ground water table. [5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be kept unutilized for a period more than three years; it shall be used for land reclamation and plantation in mined out areas. [6] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [7] The over burden generated shall be stacked at earmarked dump site (s) only and it shall not be kept active for long period of time. The maximum height of the already existing waste dumps shall not exceed 5 meter in single terraces and the slope angle shall not exceed 28o as per norms. [8] The dumping site selected and proposed shall be used for OB dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [9] The benches height and slope shall be maintained as per approved mining plan. [10] Waste dump shall be terraced. The height of the dump and its slope shall not exceed as suggested in the approved mining plan. A retaining wall shall be constructed at the toe of the dump. [11] Garland drains shall be constructed to prevent the flow of the water in the dumps. [12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of fines to low lying areas during rains. [13] The total waste generated in the present plan period shall be as envisaged, which shall be accommodated in old dumpsite in addition to the waste already dumped. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self sustaining. Compliance status shall be submitted to HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases. [14] Drills shall either be operated with dust extractors or equipped with water injection system. [15] The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area. Page 81 of 151

[16] Catch drains and siltation ponds of appropriate size shall be constructed for the working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The water so collected shall be utilized for watering the mine area, roads, green belt development etc. The drains shall be regularly de-silted, particularly after monsoon and maintained properly. [17] Garland drains; septing tanks and check dams of appropriate size, gradient and length shall be constructed both around the mine pit and over burden dumps and sump capacity shall be designed keeping 50% safety margin over and above peak sudden rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity shall also be provided and Adequate pits shall be constructed at the corners of the garland drains and de-silted. [18] Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation shall be based on the rainfall data. [19] Plantation shall be raised in a 7.5 meter wide green belt in the safety zone around the mining lease, backfilled and reclaimed area, around water body, along the roads etc. by planting the native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha. Greenbelt shall be developed all along the mine lease area in a phased manner and shall be completed within first five years. [20] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [21] The project authority shall implement suitable conservation measures to augment ground water resources in the area in consultation with the Regional Director, Central Ground Water Board. [22] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [23] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/Government approved lab. [24] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [25] Blasting operation shall be carried out only during the daytime. Controlled blasting shall be practiced. The mitigation measures for control of ground vibrations and to arrest fly rocks and boulders shall be implemented. [26] The blasting operation will be carried out as per the norms of Director (Mines & Safety), Gaziabad. Take all safety measures as per the various mining regulations. [27] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved by the Chief Wildlife Warden of the State before start of mining operation. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months. [28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 7.6 Lacs as cost for implementing various environmental protection measures including recurring expenses per year. [29] A sum of Rs. 15 Lacs shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, Page 82 of 151

health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [30] Budgetary provision of Rs. Rs 3.5 Lacs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012. [32] The water reservoir, which would be created/available during post closure (all pits), shall be provided with suitable benches and fencing to provide the access to the water body and safety. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure that all measures are taken simultaneously for safeguard and maintenance of the health of the workers. [37] The project proponent shall ensure supply of drinking water through RO. [38] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [39] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. GENERAL CONDITIONS: [i] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [ii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5, SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [iv] Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in operations of HEMM etc. shall be provided with earplugs/muffs. [v] Waste water (workshop and waste water from the mine) shall be properly collected & treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease trap shall be installed before discharge. [vi] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vii] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. Page 83 of 151

[viii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [ix] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any of the stipulated conditions and/or to revoke the clearance if implementation of any of the condition stipulated by SEIAA, Haryana or any other competent authorities is not satisfactory. [xi] Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of Environment (Protection) Act, 1986. [xii] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [xiii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xiv] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xv] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xvi] Any area which have been banned by any authority/courts shall not be used for mining activity. 134.21 Environment Clearance for Mining of Balu/Sand with Annum over an area of 35’00 Ha’ in Village-Gyaspur-Rasulpur’ Production Capacity-12,67,200 Tons per Tehsil-Ganaur, District Sonipat (HR) by M/s Ultimate Group, Service Road Project Proponent : Sh. Amandeep Singh Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF in its 35th meeting held on 24th -26th June, 2015 and conveyed to the project proponent vide letter No. J-11015/179/2015-IA.II(M) dated 19.08.2015. The project proponent submitted the EIA/EMP to the SEIAA on 20.04.2016. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: Page 84 of 151

[1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [10] The PP should submit consent letter from Sh. Surender Singh for using 5 acre of land and from Sh. Pala Ram for using 2 acre of land for mining or will submit an undertaking that PP will not do any mining activity in the said areas. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussions, it was informed by the Project Proponent that it is a proposed Mining of “Sand” (Minor Mineral) at Gyaspur Rasulpur Sand Unit over an area of 35.00 Ha. in Tehsil- Ganaur, District-Sonipat, Haryana having production capacity 12,67,200 TPA. The mine lease area 35.00 Ha. lies in Village Gyaspur and Rasulpur, Tehsil- Ganaur, District-Sonipat, Haryana (Khasra Numbers Gyaspur: 16//25/1, 25/2. 17//3, 4, 5, 9, 11, 12, 19, 20, 21. 18//1, 10, 11, 20, 21. 19//4, 5, 6, 7, 8, 13, 14, 15, 16, 17, 18, 19, 22, 23, 24, 25. 34//2, 3, 4, 5, 6, 7/1, 8, 9, 12/1, 12/2, 13, 14, 15, 16, 17, 18, 19, 22, 23/1, 23/2, 24, 25. 35//1, 10, 11, 20, 21, 36//1. 37//5 Rasulpur: 1//23, 24. 3//10, 11, 20. 4//2, 3, 4, 5, 6, 7, 8/1, 8/2, 14, 15 Area- 23.60 Ha. for River bed and Khasra Numbers Gyaspur 24//21, 22, 23, 24. 25//25. 28//5, 6/1, 6/2, 15, 16, 25. 29//1, 2, 3, 4, 7, 8, 9, 10/1, 10/2, 11/1, 11/2, 12, 13, 14, 17, 18/1, 18/2. 29//19/1, 19/2, 20, 21/1, 21/2, 22, 23/1, 23/2, 24 Area 11.40 Ha. outside River bed and total Mine lease Area- 35.00 ha). The land use of the lease area is Yamuna River (Gair Mumkin Nadi, Nala) and Pvt. land. No forest land is involved. The Letter of Intent of mining lease was granted to M/s. Ultimate Group by Mines & Geology Department, Haryana vide memo no. DMG/Hy/Cont/Gyaspur-Rasulpur/2015 /2128 dated 21.04.2015. The Mining Plan is approved by Page 85 of 151

Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/Hy/M. Plan/SNP/Gyaspur-Rasulpur/7141 dated 22.07.2015. The Latitudes and Longitudes of MLA (Riverbed) North N 29°05‟59” and N 29°06‟27” and East E 77°07‟50” and E 77°08‟14”. The Latitudes and Longitudes of MLA (Outside riverbed) North N 29°05‟59” and N 29°06‟11”and East E 77°06‟43” and E 77°06‟56”. on Survey of India toposheet (OSM) numbers H43R4. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is more than 25 Ha hence the project falls under B1 category. Method of mining is opencast method (Semi-mechanized in river bed and mechanized in outside river bed). The total water requirement is 47 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 3 meters bgl for riverbed and 9 meter bgl for outside riverbed; no ground water interception during the mining operations is envisaged as ground water table is 5-10 m bgl for riverbed and 15-20m bgl for outside riverbed. Hence, the ground water table will not be intersected by mining operation. Project proponent reported that there is no national Park/Wildlife Sanctuary within 10 Km radius. The capital cost of the project is Rs. 8.50 Crores; for CSR Rs. 25.00 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 34.00 Lakhs. Budget for Occupational Health and Safety is Rs. 15.0 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 61.32 Lakhs per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 Category and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 12,67,200 TPA (River bed – 10,62,000 TPA and outside river bed- 2,05,200 TPA). The ultimate depth of Mining will be 3 meters in river bed and 9 meters in outside river bed. The alivation range of mine site is 212 m-217 m armsl. The Corner Coordinates of the leased area are: Corners Latitudes Longitudes

River bed

A N 29°05’59” E 77°07’50”

B N 29°06’27” E 77°08’ 14”

Outsie River bed A N 29°05’59” E 77°06’43”

B N 29°06’11” E 77°06’56”

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. Page 86 of 151

[3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 4223 Mt/day @ 200 Trips/day (25 Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. Page 87 of 151

[20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 34.0 lakh as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of Rs. 25.0 lakh shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 15.0 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. Page 88 of 151

[34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made.

[iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Hon’ble Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. Page 89 of 151

[xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution. 134.22 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Bailgarh South Block/YNR B2” over an area of 28.00 Ha. Falling in Village- Bailgarh, Tehsil-, District Yamuna Nagar, Haryana by M/s Mubarikpur Royalty Company Project Proponent : Sh. Kumar Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/234/ 2015-IA.II(M) dated 07.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 09.03.2016 at 11.00 AM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. Page 90 of 151

[8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussions, Project Proponent informed that it is a proposed Mining of “Boulder, Gravel and Sand” (Minor Mineral) at “Bailgarh South Block/YNR B-2”over and tentative area of 28.00 Ha (Khasra Numbers 54//2, 9/1, 9/2, 11, 12, 19, 20, 21. 53//16, 25. 56//5, 6, 7, 14, 15, 16, 17, 23, 24, 25. 55//1, 10, 11, 20. 72//3, 4/1/1, 4/1/2, 4/2, 5, 7, 8, 13, 14, 18, 19, 22, 23. 73//1, 2, 9, 10, 11, 12/1, 12/2, 20, 21. 74//15, 16/1/1, 16/1/2, 16/2, 17, 24, 25. 85//3, 4/1, 4/2, 5, 7, 8, 9, 11, 12/1, 12/2, 13, 14, 18, 19,20,21,22. 84//25 86//1/1, 1/2, 2, 10. 87//4, 5, 6/1, 6/2, 7, 13, 14, 15, 17, 18, 22/1, 22/2, 23/1, 23/2. 93//2, 10, 11.) in Tehsil Chhachhrauli, District Yamuna Nagar, Haryana having production capacity 13,00,000 TPA. The mine lease area 28.00 Ha. lies in Village Bailgarh, Tehsil Chhachhrauli, Distt- Yamuna Nagar (Haryana). The land use of the lease area is River bed (Yamuna River)/Government land (Gar, Mumkin, Nadi, Nala). The LOI of mining lease was granted to M/s Mubarikpur Royalty Company by Mines & Geology department, Haryana vide memo no. DMG/HY/Cont/ B. Garh South Block/YNR B2 /2015/3913 dated 19/06/2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/HY/MP/Bailgarh South Block/YNR B-2/2015-16/1261 dated 23.02.2016. The Latitudes and Longitudes of MLA North N 30°13'33.428”, N 30°13'41.174”, N 30°12'34.295” and N 30°13'2.697”and East E 77°29'37.324”, E 77°30'18.045”, E 77°29'27.68” and E 77°29'12.409” on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11, H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is more than 28.00 Ha. And less than 50 Ha., hence, the project falls under B1 category. Method of mining is opencast method (Semi-mechanized). The total water requirement is 43 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 3 meters bgl; no ground water interception during the mining operations is envisaged as ground Page 91 of 151

water table is 05-10m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that Project area is falling under Kalaser Wildlife Sanctuary 10.6 Km, towards North as shown on toposheet (SoI). As per S.O. 1485 (E) of MoEF & Climate Change, in its Gazette Notification dated 22.04.2016, the eco-sensitive boundary of Kalesar Wildlife Sanctuary has been delineated and it is 1900 m from the boundary of and Kalesar Wildlife Sanctuary within the State of Haryana and lease area is not falling in this eco-sensitive area or notified area. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 8.50 Crores; for CSR Rs. 20.0 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 29.0 Lakhs. Budget for Occupational Health and Safety is Rs. 10.00 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 1,96,35,000 per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 category and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 13,00,000 TPA. The ultimate depth of Mining will be 3 meter. The alivation range of mine site is 297 to 296 armsl. The Corner Coordinates of the leased area are: Corners Latitudes Longitudes A 30°13'33.428"N’ 77°29'37.324"E B 30°13'41.174"N 77°30'18.045"E C 30°12'34.295"N 77°29'27.68"E D 30°13'2.697"N 77°29'12.409"E

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 4334 Mt/day @ 174 Trips/day (25Mt/Trip). Transport of minerals shall be done either by Page 92 of 151

dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of Page 93 of 151

mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 29.0 lakh per annum as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of Rs. 20.0 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 10.00 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically Page 94 of 151

sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

Page 95 of 151

134.23 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Kohliwala Block/YNR B-21 & 22” over an area of 13.59 Ha. Falling in Village- Kohliwala, Tehsil-Chhachhrauli, District Yamuna Nagar, Haryana by M/s Delhi Royalty Company Project Proponent : Sh. Bhupinder Singh Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/239/ 2015-IA.II(M) dated 07.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 11.03.2016 at 11.00 AM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan and revised restoration and reclamation plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [7] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [8] The PP should submit impact of heavy traffic on air quality of surrounding area alongwith mitigation plan thereof and submit Water Quality, Air Quality and Noise Data. [9] The PP should submit revised clearance from forest department for non applicability of forest area in B21 block Khasra Number 4/8, 9/1, 9/2, 12/1/1, 12/1/2, 12/2 and 13/2 or should submit an affidavit that they will not do mining in B21 block Khasra Number 4/8, 9/1, 9/2, 12/1/1, 12/1/2, 12/2 and 13/2. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussion, Project Proponent informed the Committee that it is a proposed Mining of “Boulder, Gravel and Sand” (Minor Mineral) at “Kohliwala Block/YNR B 21 and 22” over an area of 13.59 Ha. (Khasra Numbers- Kohliwala YNR B 21-4//1, 2/1, 2/2, 10, 11, 5//6/1/1, 6/1/2, 6/2, 7/1, 7/2, 14/1/1, 14/1/2, 14/2, 15, 16, 17 Kohliwala YNR B 22- 10//1, 2, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 23/1, 23/2, 24, 25. 11//21, 14//3, 4, 5, 6, 7, 8. ) in Tehsil Chhachhrauli, District Yamuna Nagar, Haryana having production capacity 2,50,000 TPA. Page 96 of 151

The mine lease area 13.59 Ha. lies in Village Kohliwala, Tehsil Chhachhrauli, Distt- Yamuna Nagar (Haryana). The land use of the lease area is outside riverbed /Private agricultural land. The LOI of mining lease was granted to M/s Delhi Royalty Company by Mines & Geology department, Haryana vide memo no. DMG/HY/Cont/Kohliwala Block/YNR B 21and 22/2015 /3931 dated 19.06.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/Hy/M. Plan/Kohliwala Block / YNR B- 21&22/2015-16/1276 dated 23.02.2016. The Latitudes and Longitudes of MLA 1). Kohliwala YNR B 21- North N 30° 15’34.8’’, N 30° 15´ 42.1’’, N 30° 15´ 38.2’’ and N 30° 15’34.6’’ and East E 77° 30’ 08.1’’, E 77° 30’17.0’’, E 77° 30’19.8’’ and E 77° 30’ 13.0’’ and MLA 2). Kohliwala YNR B 22 North N 30° 15’32.0’’, N 30° 15’26.3’’, N 30° 15’18.2’’ and N 30° 15’26.5’’ and East E 77° 30’ 25.4’’, E 77° 30’ 38.2’’, E 77° 30’ 37.0’’ and E 77° 30’ 25.3’’on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11, H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project falls under B1 category. Method of mining is opencast method (mechanized). The total water requirement is 25 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 9 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 15-20m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that Project area is falling under Kalaser Wildlife Sanctuary 6.5 Km, towards NE as shown on toposheet (SoI). As per S.O. 1485 (E) of MoEF&CC, in its Gazette Notification dated 22.04.2016, the eco-sensitive boundary of Kalesar Wildlife Sanctuary has been delineated and it is 1900 m from the boundary of Kalesar National Park and Kalesar Wildlife Sanctuary within the State of Haryana and lease area is not falling in this eco-sensitive area or notified area. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 7.00 Crores; for CSR Rs. 20.00 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 24.0 Lakhs. Budget for Occupational Health and Safety is Rs. 5.00 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 73.75 Lakhs per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for Production of Stone along with Associated Minerals as per below mentioned figures. Page 97 of 151

Year Bench mrl Production First 298-289 m amsl 2,50,000

Second 298-289 m amsl 2,50,000

Third 298-289 m amsl 2,50,000

Fourth 298-289 m amsl 2,50,000

Fifth 298-289 m amsl 2,50,000

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from HSPCB and effectively implement all the conditions stipulated by the HSPCB. [3] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [4] The project proponent shall ensure that the mining operations shall not intersect groundwater table and the mining operation should be restricted at least 3 meter above the ground water table. [5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be kept unutilized for a period more than three years; it shall be used for land reclamation and plantation in mined out areas. [6] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [7] The over burden generated shall be stacked at earmarked dump site (s) only and it shall not be kept active for long period of time. The maximum height of the already existing waste dumps shall not exceed 5 meter in single terraces and the slope angle shall not exceed 28o as per norms. [8] The dumping site selected and proposed shall be used for OB dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [9] The benches height and slope shall be maintained as per approved mining plan. [10] Waste dump shall be terraced. The height of the dump and its slope shall not exceed as suggested in the approved mining plan. A retaining wall shall be constructed at the toe of the dump. [11] Garland drains shall be constructed to prevent the flow of the water in the dumps. [12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of fines to low lying areas during rains. [13] The total waste generated in the present plan period shall be as envisaged, which shall be accommodated in old dumpsite in addition to the waste already dumped. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self sustaining. Compliance status shall be submitted to HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases. [14] Drills shall either be operated with dust extractors or equipped with water injection system. [15] The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area. [16] Catch drains and siltation ponds of appropriate size shall be constructed for the working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The water so collected shall be utilized for watering the mine area, roads, green belt development etc. The drains shall be regularly de-silted, particularly after monsoon and maintained properly. [17] Garland drains; septing tanks and check dams of appropriate size, gradient and length shall be constructed both around the mine pit and over burden dumps and sump capacity shall be designed keeping 50% safety margin over and above peak sudden Page 98 of 151

rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity shall also be provided and Adequate pits shall be constructed at the corners of the garland drains and de-silted. [18] Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation shall be based on the rainfall data. [19] Plantation shall be raised in a 7.5 meter wide green belt in the safety zone around the mining lease, backfilled and reclaimed area, around water body, along the roads etc. by planting the native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha. Greenbelt shall be developed all along the mine lease area in a phased manner and shall be completed within first five years. [20] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [21] The project authority shall implement suitable conservation measures to augment ground water resources in the area in consultation with the Regional Director, Central Ground Water Board. [22] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [23] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/Government approved lab. [24] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [25] Blasting operation shall be carried out only during the daytime. Controlled blasting shall be practiced. The mitigation measures for control of ground vibrations and to arrest fly rocks and boulders shall be implemented. [26] The blasting operation will be carried out as per the norms of Director (Mines & Safety), Gaziabad. Take all safety measures as per the various mining regulations. [27] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved by the Chief Wildlife Warden of the State before start of mining operation. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months. [28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 24.0 Lakhs per annum as cost for implementing various environmental protection measures including recurring expenses per year. [29] A sum of Rs. 20.00 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [30] Budgetary provision of Rs. 5.00 Lakhs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, Page 99 of 151

crèche for infants should be made and submitted to HSPCB at the time of CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012. [32] The water reservoir, which would be created/available during post closure (all pits), shall be provided with suitable benches and fencing to provide the access to the water body and safety. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure that all measures are taken simultaneously for safeguard and maintenance of the health of the workers. [37] The project proponent shall ensure supply of drinking water through RO. [38] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [39] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. GENERAL CONDITIONS: [i] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [ii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5, SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [iv] Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in operations of HEMM etc. shall be provided with earplugs/muffs. [v] Waste water (workshop and waste water from the mine) shall be properly collected & treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease trap shall be installed before discharge. [vi] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vii] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [viii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [ix] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any of the stipulated conditions and/or to revoke the clearance if implementation of any of the Page 100 of 151

condition stipulated by SEIAA, Haryana or any other competent authorities is not satisfactory. [xi] Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of Environment (Protection) Act, 1986. [xii] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [xiii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xiv] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xv] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xvi] Any area which have been banned by any authority/courts shall not be used for mining activity. 134.24 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Bhood Majra Block/YNR B-20” over an area of 9.95 Ha. Falling in Village-Bhood Majra, Tehsil-Chhachhrauli, District Yamuna Nagar, Haryana by M/s Ganga Yamuna Mining Co. Project Proponent : Sh. Virender Sharma Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/231/ 2015-IA.II(M) dated 07.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 11.03.2016 at 02.00 PM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan and revised restoration and reclamation plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. Page 101 of 151

[6] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [7] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [8] The PP should submit impact of heavy traffic on air quality of surrounding area alongwith mitigation plan thereof and submit Water Quality, Air Quality and Noise Data.

The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussion, Project Proponent informed the Committee that it is a proposed Mining of “Boulder, Gravel and Sand” (Minor Mineral) at Bhood Majra Block/YNR B-20 over and tentative area of 9.95 Ha.( Khasra Numbers- 26//1, 18, 19, 20, 21, 22, 23. 27//5, 6, 14/2, 15/1, 15/2, 16, 17, 24, 25/1, 25/2, 25/3. 29//4, 5, 6, 7, 15.30//1, 2, 9, 10, 11, 12, 13.) in Tehsil Chhachhrauli, Distt- Yamuna Nagar, Haryana having production capacity 2,00,000 TPA. The mine lease area 9.95 Ha. lies in Village Bhood Majra, Tehsil Chhachhrauli, Distt- Yamuna Nagar (Haryana). The land use of the lease area is Private land (Outside Riverbed). No forest land is involved. The LOI of mining lease was granted to M/s Ganga Yamuna Mining Co. by Mines & Geology department, Haryana vide memo no. DMG/Hy/Cont/B.Majra Block/YNR B-20/2015/3929 dated 19/06/2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/Hy/M.Plan/B.Kalan/YNR B- 20/2015/10690-10693 dated 23.12.2015. The Latitudes and Longitudes of MLA North N 30°15’06.1”, N 30°15’05.8”, N 30°14’50.1” and N 30°15’00.2”and East E 77°28’ 43.8”, E 77°28’ 46.4”, E 77°28’ 50.6” and E 77°28’ 38.6” on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11, H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project falls under B1 category. Method of mining is opencast method (mechanized). The total water requirement is 20 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 9 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 15-20 m bgl. Hence, the ground water table will not be intersected by mining operation. Page 102 of 151

Project Proponent reported that Project area is falling under Kalaser Wildlife Sanctuary 8.7 Km, towards North and the Clearance from NBWL was also applied on dated 14.12.2015. As per S.O. 1485 (E) of MoEF&CC, in its Gazette Notification dated 22.04.2016, the eco-sensitive boundary of Kalesar Wildlife Sanctuary has been delineated and it is 1900 m from the boundary of Kalesar National Park and Kalesar Wildlife Sanctuary within the State of Haryana and lease area is not falling in this eco-sensitive area or notified area. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 3.5 Crores; for CSR Rs. 15.0 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 24.0 Lakhs. Budget for Occupational Health and Safety is Rs. 5.0 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 29,35,000 Lakhs to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for Production of Stone along with Associated Minerals as per below mentioned figures. Year Bench mrl Production First 297-288 m amsl 2,00,000 Second 297-288 m amsl 2,00,000 Third 297-288 m amsl 2,00,000 Fourth 297-288 m amsl 2,00,000 Fifth 297-288 m amsl 2,00,000

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from HSPCB and effectively implement all the conditions stipulated by the HSPCB. [3] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [4] The project proponent shall ensure that the mining operations shall not intersect groundwater table and the mining operation should be restricted at least 3 meter above the ground water table. [5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be kept unutilized for a period more than three years; it shall be used for land reclamation and plantation in mined out areas. [6] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [7] The over burden generated shall be stacked at earmarked dump site (s) only and it shall not be kept active for long period of time. The maximum height of the already existing waste dumps shall not exceed 5 meter in single terraces and the slope angle shall not exceed 28o as per norms. [8] The dumping site selected and proposed shall be used for OB dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [9] The benches height and slope shall be maintained as per approved mining plan. [10] Waste dump shall be terraced. The height of the dump and its slope shall not exceed as suggested in the approved mining plan. A retaining wall shall be constructed at the toe of the dump. [11] Garland drains shall be constructed to prevent the flow of the water in the dumps. Page 103 of 151

[12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of fines to low lying areas during rains. [13] The total waste generated in the present plan period shall be as envisaged, which shall be accommodated in old dumpsite in addition to the waste already dumped. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self sustaining. Compliance status shall be submitted to HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases. [14] Drills shall either be operated with dust extractors or equipped with water injection system. [15] The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area. [16] Catch drains and siltation ponds of appropriate size shall be constructed for the working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The water so collected shall be utilized for watering the mine area, roads, green belt development etc. The drains shall be regularly de-silted, particularly after monsoon and maintained properly. [17] Garland drains; septing tanks and check dams of appropriate size, gradient and length shall be constructed both around the mine pit and over burden dumps and sump capacity shall be designed keeping 50% safety margin over and above peak sudden rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity shall also be provided and Adequate pits shall be constructed at the corners of the garland drains and de-silted. [18] Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation shall be based on the rainfall data. [19] Plantation shall be raised in a 7.5 meter wide green belt in the safety zone around the mining lease, backfilled and reclaimed area, around water body, along the roads etc. by planting the native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha. Greenbelt shall be developed all along the mine lease area in a phased manner and shall be completed within first five years. [20] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [21] The project authority shall implement suitable conservation measures to augment ground water resources in the area in consultation with the Regional Director, Central Ground Water Board. [22] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [23] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/Government approved lab. [24] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [25] Blasting operation shall be carried out only during the daytime. Controlled blasting shall be practiced. The mitigation measures for control of ground vibrations and to arrest fly rocks and boulders shall be implemented. [26] The blasting operation will be carried out as per the norms of Director (Mines & Safety), Gaziabad. Take all safety measures as per the various mining regulations. Page 104 of 151

[27] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved by the Chief Wildlife Warden of the State before start of mining operation. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months. [28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 24.0 Lakh per annum as cost for implementing various environmental protection measures including recurring expenses per year. [29] A sum of Rs. 15.0 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [30] Budgetary provision of Rs. Rs. 5.0 Lakhs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012. [32] The water reservoir, which would be created/available during post closure (all pits), shall be provided with suitable benches and fencing to provide the access to the water body and safety. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure that all measures are taken simultaneously for safeguard and maintenance of the health of the workers. [37] The project proponent shall ensure supply of drinking water through RO. [38] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [39] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. GENERAL CONDITIONS: [i] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [ii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5, SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so Page 105 of 151

collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [iv] Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in operations of HEMM etc. shall be provided with earplugs/muffs. [v] Waste water (workshop and waste water from the mine) shall be properly collected & treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease trap shall be installed before discharge. [vi] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vii] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [viii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [ix] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any of the stipulated conditions and/or to revoke the clearance if implementation of any of the condition stipulated by SEIAA, Haryana or any other competent authorities is not satisfactory. [xi] Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of Environment (Protection) Act, 1986. [xii] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [xiii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xiv] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xv] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xvi] Any area which have been banned by any authority/courts shall not be used for mining activity.

Page 106 of 151

134.25 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Devdhar Block/YNR B-24” over an area of 31.87 Ha. Falling in Village-Devdhar, Tehsil-Chhachhrauli, District Yamuna Nagar, Haryana by M/s Northern Royalty Company Project Proponent : Sh. Virender Sharma Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/235/2015-IA.II(M) dated 07.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 10.03.2016 at 02.00 PM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan and revised restoration and reclamation plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [7] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [8] The PP should submit impact of heavy traffic on air quality of surrounding area alongwith mitigation plan thereof and submit Water Quality, Air Quality and Noise Data. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussions, Project Proponent informed the committee that it is a proposed the Mining of “Boulder, Gravel and Sand” (Minor Mineral) at “Devdhar Block/YNR B- 24” over and tentative area of 31.87 Ha (Khasra Numbers-23//11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22/1, 22/223/1, 23/2, 24, 25, 22/21, 24//12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 25//16, 23, 24/124/2, 25, 30//3, 4/1, 4/2, 5, 6, 7/1, 7/2, 8, 13, 14, 15, 16, 17, 18, 31//1, 2, 3, 31//4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 32//1, 2/1, 2/2, 3, 4, 5, 6, 7, 8, 9/1, 9/2, 32//10/1, 10/2, 11, 12, 13, 14, 19, 20.) in Tehsil Chhachhrauli, Distt- Yamuna Nagar, Haryana having production capacity 5,10,000 TPA. Page 107 of 151

The mine lease area 31.87 Ha. lies in Village Devdhar, Tehsil Chhachhrauli, Distt- Yamuna Nagar (Haryana). The land use of the lease area is Outside riverbed/Private land. The LOI of mining lease was granted to M/s Northern Royalty Company by Mines & Geology Department, Haryana vide memo no. DMG/HY/Cont/ Devdhar Block/YNR B 24/2015/3933 dated 19.06.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/HY/MP/Devdhar Block/YNR B-24/2015/29 dated on 01.01.2016. The Latitudes and Longitudes of MLA North N 30° 15’03.0’’, N 30° 15´ 02.7’’, N 30° 14’49.6’’ and N 30° 14’49.9’’and East E 077° 28’ 06.0’’, E 077° 28’31.3’’, E 077° 28’ 25.2’’and E 077° 27’ 57.7’’on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11, H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is more than 25 Ha. And less than 50 Ha., hence, the project falls under B1 category. Method of mining is opencast method (mechanized). The total water requirement is 42 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 9 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 15-20m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that Project area is falling under Kalaser Wildlife Sanctuary 9.0 Km, towards North as shown on toposheet (SoI). As per S.O. 1485 (E) of MoEF&CC, in its Gazette Notification dated 22.04.2016, the eco-sensitive boundary of Kalesar Wildlife Sanctuary has been delineated and it is 1900 m from the boundary of Kalesar National Park and Kalesar Wildlife Sanctuary within the State of Haryana and lease area is not falling in this eco-sensitive area or notified area. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 8.00 Crores; for CSR Rs. 15.00 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 29.00 Lakhs. Budget for Occupational Health and Safety is Rs. 10.00 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 87.05 Lakhs per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 Category and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for Production of Stone along with Associated Minerals as per below mentioned figures.

Page 108 of 151

Year Bench mrl Production First 293-284 m amsl 5,10,000

Second 293-284 m amsl 5,10,000 Third 293-284 m amsl 5,10,000 Fourth 293-284 m amsl 5,10,000 Fifth 293-284 m amsl 5,10,000

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from HSPCB and effectively implement all the conditions stipulated by the HSPCB. [3] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [4] The project proponent shall ensure that the mining operations shall not intersect groundwater table and the mining operation should be restricted at least 3 meter above the ground water table. [5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be kept unutilized for a period more than three years; it shall be used for land reclamation and plantation in mined out areas. [6] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [7] The over burden generated shall be stacked at earmarked dump site (s) only and it shall not be kept active for long period of time. The maximum height of the already existing waste dumps shall not exceed 5 meter in single terraces and the slope angle shall not exceed 28o as per norms. [8] The dumping site selected and proposed shall be used for OB dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [9] The benches height and slope shall be maintained as per approved mining plan. [10] Waste dump shall be terraced. The height of the dump and its slope shall not exceed as suggested in the approved mining plan. A retaining wall shall be constructed at the toe of the dump. [11] Garland drains shall be constructed to prevent the flow of the water in the dumps. [12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of fines to low lying areas during rains. [13] The total waste generated in the present plan period shall be as envisaged, which shall be accommodated in old dumpsite in addition to the waste already dumped. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self sustaining. Compliance status shall be submitted to HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases. [14] Drills shall either be operated with dust extractors or equipped with water injection system. [15] The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area. [16] Catch drains and siltation ponds of appropriate size shall be constructed for the working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The water so collected shall be utilized for watering the mine area, roads, green belt development etc. The drains shall be regularly de-silted, particularly after monsoon and maintained properly. [17] Garland drains; septing tanks and check dams of appropriate size, gradient and length shall be constructed both around the mine pit and over burden dumps and sump capacity shall be designed keeping 50% safety margin over and above peak sudden Page 109 of 151

rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity shall also be provided and Adequate pits shall be constructed at the corners of the garland drains and de-silted. [18] Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation shall be based on the rainfall data. [19] Plantation shall be raised in a 7.5 meter wide green belt in the safety zone around the mining lease, backfilled and reclaimed area, around water body, along the roads etc. by planting the native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha. Greenbelt shall be developed all along the mine lease area in a phased manner and shall be completed within first five years. [20] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [21] The project authority shall implement suitable conservation measures to augment ground water resources in the area in consultation with the Regional Director, Central Ground Water Board. [22] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [23] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/Government approved lab. [24] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [25] Blasting operation shall be carried out only during the daytime. Controlled blasting shall be practiced. The mitigation measures for control of ground vibrations and to arrest fly rocks and boulders shall be implemented. [26] The blasting operation will be carried out as per the norms of Director (Mines & Safety), Gaziabad. Take all safety measures as per the various mining regulations. [27] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved by the Chief Wildlife Warden of the State before start of mining operation. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months. [28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 29.00 Lakhs per annum as cost for implementing various environmental protection measures including recurring expenses per year. [29] A sum of Rs. 15.00 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. Page 110 of 151

[30] Budgetary provision of Rs. 10.00 Lakhs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012. [32] The water reservoir, which would be created/available during post closure (all pits), shall be provided with suitable benches and fencing to provide the access to the water body and safety. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure that all measures are taken simultaneously for safeguard and maintenance of the health of the workers. [37] The project proponent shall ensure supply of drinking water through RO. [38] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [39] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. GENERAL CONDITIONS: [i] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [ii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made.

[iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5, SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [iv] Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in operations of HEMM etc. shall be provided with earplugs/muffs. [v] Waste water (workshop and waste water from the mine) shall be properly collected & treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease trap shall be installed before discharge. [vi] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vii] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. Page 111 of 151

[viii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [ix] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any of the stipulated conditions and/or to revoke the clearance if implementation of any of the condition stipulated by SEIAA, Haryana or any other competent authorities is not satisfactory. [xi] Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of Environment (Protection) Act, 1986. [xii] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [xiii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xiv] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xv] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xvi] Any area which have been banned by any authority/courts shall not be used for mining activity. 134.26 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Pobari Block/YNR B-11” over an area of 23.05 Ha. Falling in Village-Pobari, Tehsil-Radaur, District Yamuna Nagar, Haryana by M/s Development Strategies India Pvt. Ltd. Project Proponent : Sh. Virender Sharma Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/342/ 2015-IA.II(M) dated 03.12.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 10.03.2016 at 11.00 AM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. Page 112 of 151

After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussions, Project Proponent informed the Committee that it is a proposed Mining of “Sand” (Minor Mineral) at Pobari Block/YNR B-11 over an area of 23.05 Ha. (Khasra Number Pobari (River bed) 14//5, 15//1min, 2min, 3min, 6min, 7/1,7/2, 8, 9,10,12,13,14,15,16,17,18,25, 16//6/2 min, 7 min, 8 min, 9 min, 10 min, 11/1, 11/2, 12, 13, 14, 15, 16,17, 18, 19, 20/1, 20/2, 21 min, 22 min, 23, 24, 25, 17//3 min, 8, 9, 10 min, 11, 12, 13, 18, 19, 20/1, 20/2, 21, 22, 23 and Nakom 2//15, 16 min, 3//11, 19, 20, 21 min, 22, 23, 6//2 min , 3 min, 4 min, 5min, 6, 7, 8min, 14 min, 15 min, 5//10 , 11, 12, 18, 19, 20 min, 22 min, 23, 24, 25, 14//4 min, 5 min, 15//1 min, 2 min) in Tehsil Radaur, Distt- Yamuna Nagar, Haryana having production capacity 11,00,000 TPA. The mine lease area 23.05 Ha. lies in Village Pobari, Tehsil Chhachhrauli, Distt- Yamuna Nagar (Haryana). The land use of the lease area is Gair Mumkin Nadi nallah. No forest land is involved. The LOI of mining lease was granted to M/s Development Strategies India Pvt. Ltd. by Mines & Geology Department, Haryana vide memo no. DMG/HY/Cont/Pobari Block/YNR B 11/2015/3924 dated 19.06.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/HY/M. Plan/YNR B-11/2015/1522- 1525 dated 09.03.2016. Page 113 of 151

The Latitudes and Longitudes of MLA North N 30°0’12.942”, N 30°0’4.75”, N 30°0’16.79” and N 30°0’22.25” and East E 77°15’44.055”, E 77°16’4.75”, E 77°16’13.82” and E 77°15’54.19”on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11, H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project falls under B1 category. Method of mining is opencast open cast and semi-mechanized. The total water requirement is 48.00 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 3 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 5-10 m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that Project area is 43.0 Km away from Kalaser Wildlife Sanctuary. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 5.50 Crores; for CSR Rs. 21.25 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 34.00 Lakhs. Budget for Occupational Health and Safety is Rs. 10.00 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 38.30 Lakhs per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 Category and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 11,00,000 TPA. The ultimate depth of Mining will be 3 meter. The elevation range of mine site is 261.5 m amsl to 262 m amsl. The Corner Coordinates of the leased area are:

Corners Latitudes Longitudes ° ° A N 30 0’12.942” E 77 15’44.055” ° ° B N 30 0’4.75” E 77 16’4.75” ° ° C N 30 0’16.79” E 77 16’13.82” ° ° D N 30 0’22.25” E 77 15’54.19”

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and Page 114 of 151

necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 3667 Mt/day @ 150 Trips/day (25 Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon Page 115 of 151

(April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 34.0 lakh as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of Rs. 21.25 lakh shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 10.0 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: Page 116 of 151

[i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. Page 117 of 151

[xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

134.27 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Mandewala Block/YNR B-38” over an area of 15.00 Ha. Falling in Village- Mandewala, Tehsil-Chhachhrauli, District Yamuna Nagar, Haryana by M/s Saharanpur Mines Management Services Pvt. Ltd.. Project Proponent : Sh. Mohd. Jawed Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/237/ 2015-IA.II(M) dated 07.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 05.04.2016 at 11.30 AM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan and revised restoration and reclamation plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [7] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [8] The PP should submit impact of heavy traffic on air quality of surrounding area alongwith mitigation plan thereof and submit Water Quality, Air Quality and Noise Data.

The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussions, Project Proponent informed the Committee that it is a proposed Mining of “Boulder, Gravel and Sand” (Minor Mineral) at Mandewala Block/YNR B- 38over and tentative area of 15.00 Ha. (Khasra Numbers-11//13, 17, 18, 23/1, 23/2, 24, 25/1, 25/2, 15//1, 35/1, 9, 10, 11/1, 11/2, 12, 19, 20/1, 20/2, 21/8, 14//3/1, 3/2, 4/1, 4/2, 5/1, 5/2, Page 118 of 151

6/1, 6/2, 7, 8, 13, 14, 15/1, 15/2, 16/1, 16/2, 17, 18, 19, 20/1, 20/2, 21, 22, 23, 24/1, 24/2, 25/1, 25/2, 20//4/1, 4/2, 5/1, 5/2, 6, 7,19//1) in Tehsil Chhachhrauli, District Yamuna Nagar, Haryana having production capacity 2,40,000 TPA. The mine lease area 15.00 Ha. lies in Village Mandewala, Tehsil Chhachhrauli, Distt- Yamuna Nagar (Haryana). The land use of the lease area is Private land (Outside Riverbed). No forest land is involved. The LOI of mining lease was granted to M/s Saharanpur Mines Management Services Pvt. Ltd. by Mines & Geology department, Haryana vide memo no. DMG/HY/Cont/Mandewala Block /YNR B 38/2015/3937 dated 19/06/2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/HY/YNR-38/2015/1533 dated 10.03.2016. The Latitudes and Longitudes of MLA North 30° 15’57.4’’N, 30° 15’46.2’’N, 30° 15’41.9’’N, 77° and 30° 15’41.5’’N and East 30’ 31.7’’E, 77° 30’ 32.1’’E, 77° 30’ 25.9’’E and 77° 30’ 38.4’’E on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11,H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project falls under B1 category. Method of mining is opencast method (mechanized). The total water requirement is 26 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 9 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 15-20 m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that area is falling under Kalesar Wildlife Sanctuary 6.0 Km towards North and the Clearance from NBWL was also applied on dated 26.12.2015. As per S.O. 1485 (E) of MoEF&CC, in its Gazette Notification dated 22.04.2016, the eco-sensitive boundary of Kalesar Wildlife Sanctuary has been delineated and it is 1900 m from the boundary of Kalesar National Park and Kalesar Wildlife Sanctuary within the State of Haryana and lease area is not falling in this eco-sensitive area or notified area. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 7.00 Crores; for CSR Rs. 15.0 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 26.0 Lakhs. Budget for Occupational Health and Safety is Rs. 5.0 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs.1,65,55,000 to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 Category and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for Production of Stone along with Associated Minerals as per below mentioned figures. Page 119 of 151

Year Bench mrl Production First 30° 15’57.4’’N 77° 30’ 31.7’’E

Second 30° 15’46.2’’N 77° 30’ 32.1’’E

Third 30° 15’41.9’’N 77° 30’ 25.9’’E

Fourth 30° 15’41.5’’N 77° 30’ 38.4’’E

Fifth 30° 15’57.4’’N 77° 30’ 31.7’’E

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from HSPCB and effectively implement all the conditions stipulated by the HSPCB. [3] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [4] The project proponent shall ensure that the mining operations shall not intersect groundwater table and the mining operation should be restricted at least 3 meter above the ground water table. [5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be kept unutilized for a period more than three years; it shall be used for land reclamation and plantation in mined out areas. [6] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [7] The over burden generated shall be stacked at earmarked dump site (s) only and it shall not be kept active for long period of time. The maximum height of the already existing waste dumps shall not exceed 5 meter in single terraces and the slope angle shall not exceed 28o as per norms. [8] The dumping site selected and proposed shall be used for OB dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [9] The benches height and slope shall be maintained as per approved mining plan. [10] Waste dump shall be terraced. The height of the dump and its slope shall not exceed as suggested in the approved mining plan. A retaining wall shall be constructed at the toe of the dump. [11] Garland drains shall be constructed to prevent the flow of the water in the dumps. [12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of fines to low lying areas during rains. [13] The total waste generated in the present plan period shall be as envisaged, which shall be accommodated in old dumpsite in addition to the waste already dumped. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self sustaining. Compliance status shall be submitted to HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases. [14] Drills shall either be operated with dust extractors or equipped with water injection system. [15] The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area. [16] Catch drains and siltation ponds of appropriate size shall be constructed for the working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The water so collected shall be utilized for watering the mine area, roads, green belt development etc. The drains shall be regularly de-silted, particularly after monsoon and maintained properly. Page 120 of 151

[17] Garland drains; septing tanks and check dams of appropriate size, gradient and length shall be constructed both around the mine pit and over burden dumps and sump capacity shall be designed keeping 50% safety margin over and above peak sudden rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity shall also be provided and Adequate pits shall be constructed at the corners of the garland drains and de-silted. [18] Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation shall be based on the rainfall data. [19] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. The green belt should be developed in the safety zone around the mining lease by planting the native species around ML area, OB dumps, backfilled and reclaimed around water body, road etc. in consultation with the local DFO/ Agriculture Department. [20] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [21] The project authority shall implement suitable conservation measures to augment ground water resources in the area in consultation with the Regional Director, Central Ground Water Board. [22] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [23] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/Government approved lab. [24] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [25] Blasting operation shall be carried out only during the daytime. Controlled blasting shall be practiced. The mitigation measures for control of ground vibrations and to arrest fly rocks and boulders shall be implemented. [26] The blasting operation will be carried out as per the norms of Director (Mines & Safety), Gaziabad. Take all safety measures as per the various mining regulations. [27] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved by the Chief Wildlife Warden of the State before start of mining operation. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months. [28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 26.00 Lakhs/annum as cost for implementing various environmental protection measures including recurring expenses per year. [29] A sum of Rs. 15.0 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in Page 121 of 151

the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [30] Budgetary provision of Rs. 5.0 Lakhs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012. [32] The water reservoir, which would be created/available during post closure (all pits), shall be provided with suitable benches and fencing to provide the access to the water body and safety. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure that all measures are taken simultaneously for safeguard and maintenance of the health of the workers. [37] The project proponent shall ensure supply of drinking water through RO. [38] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [39] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. GENERAL CONDITIONS: [i] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [ii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made.

[iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5, SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [iv] Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in operations of HEMM etc. shall be provided with earplugs/muffs. [v] Waste water (workshop and waste water from the mine) shall be properly collected & treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease trap shall be installed before discharge. [vi] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vii] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. Page 122 of 151

[viii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [ix] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any of the stipulated conditions and/or to revoke the clearance if implementation of any of the condition stipulated by SEIAA, Haryana or any other competent authorities is not satisfactory. [xi] Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of Environment (Protection) Act, 1986. [xii] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [xiii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xiv] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xv] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xvi] Any area which have been banned by any authority/courts shall not be used for mining activity. 134.28 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Gumthala North Block/YNR B-16” over an area of 44.62 Ha. Falling in Village- Gumthala, Tehsil-Radaur, District Yamuna Nagar, Haryana by M/s Jogender Singh. Project Proponent : Sh. Jogender Singh Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/238/2015-IA.II(M) dated 07.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 04.04.2016 at 02.00 PM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. Page 123 of 151

After detailed discussions, the following shortcomings were observed: [1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose.

The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. During discussions, Project Proponent informed the Committee that it is a proposed Sand Mining at Yamuna River, Gumthala North Block/YNR B-16”over and tentative area of 44.62 Ha. (Khasra Numbers-45//21, 46//12 min, 13 min, 14, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25,47//16 min, 17 min, 18 min, 21 min, 22 min, 23 min, 24, 25,66//15, 16 min, 24 min, 25,67//3, 4/1, 4/2, 5, 6, 7, 8 min, 9min, 10 min, 11 min, 12, 13/1,67//13/2, 14, 15, 16 min, 17, 18/1, 18/2, 19, 20, 21, 22/1, 22/2, 23 min, 24 min,69//1, 2, 3, 4, 5, 8, 9, 10, 11min,70//1, 2, 9 min, 10 min,83//1/1, 1/2, 2/1, 2/2, 2/3, 3/1, 8,9, 10, 11, 12, 13 min, 18 min, 19,20, 21, 22, 23/1min, 23/2min,84/4, 5, 6/1, 6/2, 6/3, 7min, 14/2,14/3, 14/4, 14/5, 15/1, 15/2, 16/1,84//16/2, 17min, 25/2,99//4min, 5/1, 5/2, 5/3, 6,7/1min, 7/2 min, 14, 15, 16,17min, 24min, 25,100//1, 2/1, 2/2, 3 min, 8 min, 9/1, 9/2, 10, 11, 12, 13 min, 18 min, 19, 20, 21, 22, 23 min,113//1/1, 1/2, 2, 3 min, 8 min, 113//9, 10, 11, 12, 13 min, 18 min, 19, 20, 21, 22,) in Tehsil Radaur, District Yamuna Nagar, Haryana having production capacity 21,00,000 TPA. The mine lease area 44.62 Ha. lies in Village Gumthala, Tehsil Radaur, Distt- Yamuna Nagar (Haryana). The land use of the lease area is River bed (Yamuna River)/ Government land (Gair Mumkin, Nadi, Nala). The LOI of mining lease was granted to Sh. Page 124 of 151

Jogender Singh S/o Sh. Mahinder Singh by Mines & Geology Department, Haryana vide memo no. DMG/HY/Cont/Gumthala N. Block/YNR B 16/2015/3925 dated 19/06/2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/Hy/M. Plan/Gumthala North Block/YNR B-16/2015-16/911 dated 15.02.2016. The Latitudes and Longitudes of MLA North N29°57’22.187”, N29°56’46.1”,N 29°57'35.106"” and N 29°56'49.929"”and East E 77°12’43.538””, E 77°12’ 42.2””, E 77°13'8.801"and E 77°12'56.757"” on Survey of India toposheet (OSM) numbers H43L4, H43L8, H43R1, H43R5. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is more than 25 Ha. and less than 50 Ha., hence, the project falls under B1 category. Method of mining is opencast method (Semi-mechanized). The total water requirement is 99 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 3 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 05-10m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that Project area is located 50 Km away from Kalaser Wildlife Sanctuary as shown on toposheet (SoI). Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 9.0 Crores; for CSR Rs. 30 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 34.0 Lakhs. Budget for Occupational Health and Safety is Rs. 10.00 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 74.15 Lakhs per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 Category and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 21,00,000 TPA. The ultimate depth of Mining will be 3 meter. The elevation range of mine site is 259 mRL to 256.7 mRL. The Corner Coordinates of the leased area are: Corners Latitudes Longitudes A N 29°57’22.187” E 77°12’43.538” B N 29°56’46.1” E 77°12’ 42.2”

C N 29°57'35.106" E 77°13'8.801" D N 29°56'49.929" E 77°12'56.757"

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. Page 125 of 151

[4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 7000 MT/Day Mt/day @280 Trips/day (25Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. Page 126 of 151

[23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 34.0 Lakhs/annum as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of 30 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. 10.00 Lakhs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. Page 127 of 151

[38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: [i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. Page 128 of 151

[xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. [xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

134.29 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Nandgarh Block/YNR B-36” over an area of 29.60 Ha. Falling in Village- Nandgarh, Tehsil- Chhachhrauli, District Yamuna Nagar, Haryana by M/s Apar Mines Management Services Pvt. Ltd.. Project Proponent : Sh. Mohd. Jawed Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/253/ 2015-IA.II(M) dated 10.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 04.04.2016 at 11.30 AM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed:

[1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan and revised restoration and reclamation plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [7] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [8] The PP should submit impact of heavy traffic on air quality of surrounding area alongwith mitigation plan thereof and submit Water Quality, Air Quality and Noise Data. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. The project proponent submitted the compliance and thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. Page 129 of 151

During discussions, Project Proponent informed the Committee that it is a proposed Mining of “Boulder, Gravel and Sand” (Minor Mineral) at Nandgarh Block/YNR B-36 over and tentative area of 29.60 Ha. (Khasra Numbers-4//9/1, 9/2, 12, 18/1, 18/2, 19, 21/1, 21/2, 22, 23/1, 23/2, 24/1, 24/2. 11//5, 6, 7, 12, 13, 14, 15/1, 15/2, 16, 17, 18/1, 18/2, 19, 20/1, 20/2, 21, 22, 23, 24/1, 24/2, 25. 12//1, 2, 3, 4, 5, 6/1, 6/2, 7, 8, 9, 10/1, 10/2, 11, 12, 13, 14, 15/1, 15/2, 17, 18, 19, 20, 21, 22, 23/1, 23/2. 13//10. 15//1, 2, 9, 10, 11. 16//1, 2, 3/1, 3/2, 4, 5, 6, 7, 8, 9, 10, 11, 12/1, 12/2, 13, 14, 15, 16, 17, 18, 19, 20/1, 20/2, 23, 24. 23//3) in Tehsil Chhachhrauli, District Yamuna Nagar, Haryana having production capacity 5,77,000 TPA. The mine lease area 29.60 Ha. lies in Village Nandgarh,, Tehsil Chhachhrauli, Distt-Yamuna Nagar (Haryana). The land use of the lease area is Private land (Outside Riverbed). No forest land is involved. The LOI of mining lease was granted to M/s Apar Mines Management Services Pvt. Ltd. by Mines & Geology department, Haryana vide memo no. DMG/HY/cont/Nandgarh Block/YNR B-36/2015/7088 dated 20.07.2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/HY/M.Plan/Nandgarh Block/YNR B-36/2015/1526-1529 dated 10.03.2016. The Latitudes and Longitudes of MLA North 30°12’59” N, 30°12’47” N , 30°12’29” N, and 30°12’45” N and East 77°25’16” E, 77°25’28” E , 77°25’8.5” E and 77°24’59” E on Survey of India toposheet (OSM) numbers H43L8, H43L7, H43L11, H43L12. The Project is located in Seismic zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016 the project is more than 25 Ha. hence, the project falls under B1 category. Method of mining is opencast method (mechanized). The total water requirement is 27.00 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 9 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 15-20 m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that Project area is falling 15.4 Km towards North from Kalaser Wildlife Sanctuary. Hence, No Wildlife Clearance required from NBWL in this case. The capital cost of the project is Rs. 11.00 Crores; for CSR Rs. 20.0 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 29.00 Lakhs. Budget for Occupational Health and Safety is Rs. 5.0 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 84.65 Lakhs per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case under B1 Category and recommended for grant of Environmental Clearance to SEIAA with the following conditions:

A SPECIFIC CONDITIONS: Page 130 of 151

[1] This Environment Clearance is granted for Production of Stone along with Associated Minerals as per below mentioned figures. Year Bench mrl Production First 273-283 amsl 5, 77,000 TPA

Second 273-283 amsl 5, 77,000 TPA Third 273-283 amsl 5, 77,000 TPA

Fourth 273-283 amsl 5, 77,000 TPA

Fifth 273-283 amsl 5, 77,000 TPA

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from HSPCB and effectively implement all the conditions stipulated by the HSPCB. [3] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [4] The project proponent shall ensure that the mining operations shall not intersect groundwater table and the mining operation should be restricted at least 3 meter above the ground water table. [5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be kept unutilized for a period more than three years; it shall be used for land reclamation and plantation in mined out areas. [6] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [7] The over burden generated shall be stacked at earmarked dump site (s) only and it shall not be kept active for long period of time. The maximum height of the already existing waste dumps shall not exceed 5 meter in single terraces and the slope angle shall not exceed 28o as per norms. [8] The dumping site selected and proposed shall be used for OB dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [9] The benches height and slope shall be maintained as per approved mining plan. [10] Waste dump shall be terraced. The height of the dump and its slope shall not exceed as suggested in the approved mining plan. A retaining wall shall be constructed at the toe of the dump. [11] Garland drains shall be constructed to prevent the flow of the water in the dumps. [12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of fines to low lying areas during rains. [13] The total waste generated in the present plan period shall be as envisaged, which shall be accommodated in old dumpsite in addition to the waste already dumped. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self sustaining. Compliance status shall be submitted to HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases. [14] Drills shall either be operated with dust extractors or equipped with water injection system. [15] The higher benches of excavated void/mining pit shall be terraced and plantation done to stabilize the slopes. The slope of higher benches shall be made gentler for easy accessibility by local people to use the water body. Peripheral fencing shall be carried out along the excavated area. [16] Catch drains and siltation ponds of appropriate size shall be constructed for the working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The water so collected shall be utilized for watering the mine area, roads, green belt development etc. The drains shall be regularly de-silted, particularly after monsoon and maintained properly. Page 131 of 151

[17] Garland drains; septing tanks and check dams of appropriate size, gradient and length shall be constructed both around the mine pit and over burden dumps and sump capacity shall be designed keeping 50% safety margin over and above peak sudden rainfall (based on 50 years data) and maximum discharge in the area adjoining the mine site. Sump capacity shall also be provided and Adequate pits shall be constructed at the corners of the garland drains and de-silted. [18] Dimension of the retaining wall at the toe of dumps and OB benches within the mine to check run-off and siltation shall be based on the rainfall data. [19] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. The green belt should be developed in the safety zone around the mining lease by planting the native species around ML area, OB dumps, backfilled and reclaimed around water body, road etc. in consultation with the local DFO/ Agriculture Department. [20] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. [21] The project authority shall implement suitable conservation measures to augment ground water resources in the area in consultation with the Regional Director, Central Ground Water Board. [22] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [23] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/Government approved lab. [24] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [25] Blasting operation shall be carried out only during the daytime. Controlled blasting shall be practiced. The mitigation measures for control of ground vibrations and to arrest fly rocks and boulders shall be implemented. [26] The blasting operation will be carried out as per the norms of Director (Mines & Safety), Gaziabad. Take all safety measures as per the various mining regulations. [27] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved by the Chief Wildlife Warden of the State before start of mining operation. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months. [28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 29.00 Lakhs/annum as cost for implementing various environmental protection measures including recurring expenses per year. [29] A sum of Rs. 20.0 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in Page 132 of 151

the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [30] Budgetary provision of Rs. 5.0 Lakhs per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012. [32] The water reservoir, which would be created/available during post closure (all pits), shall be provided with suitable benches and fencing to provide the access to the water body and safety. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure that all measures are taken simultaneously for safeguard and maintenance of the health of the workers. [37] The project proponent shall ensure supply of drinking water through RO. [38] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [39] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. GENERAL CONDITIONS: [i] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [ii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made.

[iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5, SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [iv] Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in operations of HEMM etc. shall be provided with earplugs/muffs. [v] Waste water (workshop and waste water from the mine) shall be properly collected & treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease trap shall be installed before discharge. [vi] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vii] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. Page 133 of 151

[viii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [ix] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any of the stipulated conditions and/or to revoke the clearance if implementation of any of the condition stipulated by SEIAA, Haryana or any other competent authorities is not satisfactory. [xi] Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of Environment (Protection) Act, 1986. [xii] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [xiii] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xiv] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xv] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xvi] Any area which have been banned by any authority/courts shall not be used for mining activity. 134.30 EC for Mining of Boulder, Gravel and Sand (Minor Minerals) Mines namely “Lapra Block/YNR B-10” over an area of 34.28 Ha. Falling in Village-Lapra, Tehsil- Jagadhari, District Yamuna Nagar, Haryana by M/s Apar Mines Management Services Pvt. Ltd.. Project Proponent : Sh. Mohd. Jawed Consultant : Vardan EnviroNet The project was submitted to the MoEF, Government of India. The Terms of Reference were approved by the EAC, MoEF and conveyed to the project proponent vide letter No. J-11015/251/ 2015-IA.II(M) dated 10.09.2015. The project proponent submitted the EIA/EMP to the SEIAA on 25.04.2016. The public hearing was held on 05.04.2016 at 02.00 PM on the site under the Chairmanship of District Magistrate. Thereafter, the case was taken up for appraisal in the 133rd meeting of the SEAC held on 06.05.2016. Page 134 of 151

After detailed discussions, the following shortcomings were observed:

[1] The PP should submit an affidavit from the Director that the Mining shall be carried out in compliance of Hon’ble NGT interim orders. [2] The PP should submit the plan for conservation of flora and fauna to the wildlife warden. [3] The PP should submit revised CSR plan and revised Environment Management Plan. [4] The PP should submit disaster management plan. [5] The PP should submit feasibility of proposed scale of production with respect to replenishment rate and the restriction imposed by Hon’ble NGT. [6] The PP should submit contour sheet of the area alongwith longitudinal section of the river bed for entire lease area and cross-section for 100 meters on either side of the lease area and justify the proposed scale of production. [7] The PP should submit an undertaking that outside river bed area, slope of the sides shall not be less than natural angle of repose. The PP should submit an undertaking to ensure stability of such banks by suitable measures before conclusion of mining operations. [8] The PP should submit consent of the Irrigation Department w.r.t. safety of river protection works inside the river and of protection bundhs. The PP should submit an undertaking that no mining shall be done in flowing river. [9] The PP should submit an undertaking regarding source of adequate water arrangement for operational purpose. [10] The PP should submit the list of Directors. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016. During discussions, Project Proponent informed the Committee that it is a proposed Sand Mining at Yamuna River, Lapra Block/YNR B-10 over and area of 34.28 Ha. (Khasra Numbers- 5//2min, 3 min, 7 min, 8min, 9 min, 10, min, 11min, 12 to 14, 15 min, 16 to 19, 20 min, 21 min, 22 to 25,16//1min, 2 to 20, 21, 22,23,24,25/1,25/2,15//6/1min, 15 min, 16, 24 min, 25 min, 4//11 min, 18 min, 19 min, 20to 23, 24 min, 25 min,18//1 min, 2 min, 7 min, 8 min, 9 min, 10 to13, 14 min, 17 min, 18 min, 19, 20, 21, 22 min, 23 min,17//1to 20, 21, 22, 23, 24, 25) in Tehsil Jagadhari, Distt-Yamuna Nagar, Haryana having production capacity 15,30,000 TPA. The mine lease area 34.28 Ha. lies in Village Lapra, Tehsil jagadhari, Distt- Yamuna Nagar (Haryana). The land use of the lease area is River bed (Yamuna River)/ Government land (Gar, Mumkin, Nadi, Nala). The LOI of mining lease was granted to M/s Apar Mines Management Services Pvt. Ltd. by Mines & Geology department, Haryana vide memo no. DMG/HY/Cont/ Lapra Block/YNR B 10/2015 /7082 dated 20/07/2015. The Mining Plan is approved by Director General, Mines and Geology Department, Govt. of Haryana; vide letter no. DMG/ HY/MP/Lapra Block/YNR B-10 /2015-16/1518 dated 09.03.2016. Page 135 of 151

The Latitudes and Longitudes of MLA North N30°05’28”, N30°05’18”, N30°05’12” and N30°05’12”and East E 77°22’02”, E77°22’30””, E77°22’22"and E77°21’53”on Survey of India toposheet (OSM) numbers H43L4, H43L8, H43R1, H43R5. The Project is located in Seismic Zone-IV. As per the notification from Ministry of Environment & Forest, New Delhi dated 14.09.2006 and MoEF circular dated 24.12.2013, and the MoEF&CC notification dated 15.01.2016, the project is more than 25 Ha. and less than 50 Ha., hence, the project falls under B1 category. Method of mining is opencast method (Semi-mechanized). The total water requirement is 56 KLD including water demand for domestic purpose, dust suppression and plantation development which shall be met by hired tanker. The working is proposed only upto 3 meters bgl; no ground water interception during the mining operations is envisaged as ground water table is 05-10m bgl. Hence, the ground water table will not be intersected by mining operation. Project Proponent reported that there is no any Wildlife Sanctuary or National Park towards as shown on toposheet (SoI). The capital cost of the project is Rs. 15.50 Crores; for CSR Rs. 20.0 Lakhs/annum will be allocated and cost for Environmental Protection is Rs. 29.00 Lakhs. Budget for Occupational Health and Safety is Rs. 10.00 Lakhs. The project proponent will deposit 10% of the annual contract money i.e. Rs. 1 Crore 36 Lakhs 60 Thousand per annum to the Mines and Minerals Development, Restoration and Rehabilitation Fund. The Committee unanimously decided to appraise the case and recommended for grant of Environmental Clearance to SEIAA with the following conditions: A SPECIFIC CONDITIONS: [1] This Environment Clearance is granted for the proposed production for the five years @ 15,30,000 TPA. The ultimate depth of Mining will be 3 meter. The alivation range of mine site is 268.40-269.80 amsl. The Corner Coordinates of the leased area are: Corners Latitudes Longitudes A N 30°05’28” E 77°22’02”

B N 30°05’18” E 77°22’30”

C N 30°05’12” E 77°22’22”

D N 30°05’12” E 77°21’53”

[2] The project proponent shall carry out mining activity strictly as per the approved Mining Plan. [3] Environmental Clearance is subject to obtaining clearance, under the Wildlife (Protection) Act, 1972 from the National Board of Wildlife, as applicable to the project. [4] No mining activities will be allowed in forest area, if any, for which the Forest Clearance is not available. [5] The Project proponent shall obtain consent to Operate from the State Pollution control Board, Haryana and effectively implement all the conditions stipulated therein. [6] Project Proponent shall appoint an Occupational Health Specialist for Regular and Periodical medical examination of the workers engaged in the project and records maintained; also, Occupational health check-ups for workers having some aliments like Page 136 of 151

BP, diabetes, habitual smokers, etc. shall be undertaken once in six months and necessary remedial/preventive measures taken accordingly. Recommendations of National Institute for labour for ensuring good occupational environment for mine workers would also be adopted. [7] Project Proponent shall appoint a Monitoring Committee to monitor the replenishment study, traffic management, levels of production, River Bank erosion and maintenance of Road etc. [8] The number of trips of the trucks shall not exceed the estimated quantity of 5100 MT/Day Mt/day @ 205 Trips/day (25Mt/Trip). Transport of minerals shall be done either by dedicated road or it should be ensured that the trucks/dumpers carrying the mineral should not be allowed to pass thought the villages. [9] Project Proponent shall ensure that the road may not be damaged due to transportation of the mineral; and transport of minerals will be as per IRC Guidelines with respect to complying with traffic congestion and density. [10] Excavation will be carried out up to a maximum depth of 3 meters from surface of river bed one meter above from the ground water level of the River channel whichever is reached earlier. [11] The pollution due to transportation load on the environment will be effectively controlled & water sprinkling will also be done regularly. Vehicles with PUCC only will be allowed to ply. The mineral transportation shall be carried out through covered trucks only and the vehicles carrying the mineral shall not be overloaded. Project should obtain ‘PUC’ certificate for all the vehicles from authorized pollution testing centre. [12] Washing of all transport vehicles should be done inside the mining lease. [13] Permanent pillars has to be constructed to demarcate width of extraction of Reserve of Minerals leaving 25% of River width from the bank with depth of 1.5m below the ground and 1.2 m above the ground to observe its stability. [14] There shall be planning, developing and implementing facility of rainwater harvesting measures on long term basis in consultation with Regional Director, Central Groundwater Board and implementation of conservation measures to augment ground water resources in the area in consultation with Central Ground Water Board. [15] The Project Proponent shall also take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted in the study area. [16] Main haulage road in the mine should be provided with permanent water sprinklers and other roads should be regularly wetted with water tankers fitted with sprinklers. [17] Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structures to be removed after the completion of the project. [18] No River sand mining shall be allowed in flowing water and no mining is allowed in rainy season. [19] The project proponent shall submit annual replenishment report certified by an authorized agency. In case the replenishment is lower than the approved rate of production, then the mining activity/ production levels shall be decreased/ stopped accordingly till the replenishment is completed. [20] The project proponent shall ensure that no natural water course/water body shall be obstructed due to any mining operations. [21] The dumping site selected and proposed shall be used for over burden dump at the designated site within the lease area as per the approved mine plan. In no case the overburden should be dumped outside the lease area. [22] Garland drains shall be constructed to prevent the flow of the water in the dumps. [23] Green belt should be developed as per the proposed plantation as given in the proposal. Plantation should be carried out in phased manner. [24] Regular water sprinkling shall be carried out in critical areas prone to air pollution and having high levels of SPM and RPM such as haul road, loading and unloading point and transfer points. It shall be ensured that the Ambient Air Quality Parameters conform to the norms prescribed by the CPCB. Page 137 of 151

[25] Regular monitoring of ground water level and quality shall be carried out in and around the mine lease. The monitoring shall be carried out four times in a year-pre monsoon (April-May), monsoon (August), post monsoon (November); winter (January) and the data thus collected may be sent regularly to MOEF Regional Office, Chandigarh and Regional Director CGWB. [26] Data on ambient air quality and stack emissions shall be submitted to Haryana Pollution Control Board once in six months carried out by MOEF/NABL/CPCB/ Government approved lab. [27] Vehicular emissions shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicles used in mining operations and in transportation of mineral. The vehicles shall be covered with a tarpaulin and shall not be overloaded. The project proponent shall ensure that the vehicle must have pollution under control certificate. [28] The project proponent shall take all precautionary measures during mining operations for conservation and protection of endangered fauna, if any, spotted in the study area. A plan for conservation shall be drawn and got approved from the Chief Wildlife Warden of the State before start of mining operations. Necessary allocation of funds for implementation of the conservation plan shall be made and the funds so allocated shall be included in the project cost. All the safeguard measures brought out in the wildlife conservation plan so prepared specific to the project site shall be effectively implemented. A copy of action plan may be submitted to the HSPCB and MOEF, Regional Office, Chandigarh within 3 months.. [29] As envisaged, the Project Proponent shall invest at least an amount of Rs. 29.00 Lakhs/annum as cost for implementing various environmental protection measures including recurring expenses per year. [30] A sum of Rs. 20.0 Lakhs/annum shall be earmarked by the Project proponent for investment as CSR on socio economic up-liftment activities of the area particularly in the area of habitat, health or education, training programme of rural women & man provide the kit for employment generation. The proposal should contain provision for monthly medical camps, distributions of medicines and improvement in educational facilities in the nearby schools. Details of such activity along with time bound action plan be submitted to HSPCB/SEIAA Haryana before the start of operation. [31] Budgetary provision of Rs. Rs. 10.00 lakh per year earmarked for the labours working in the Mine for all necessary infrastructure facilities such as health facility, sanitation facility, fuel for cooking, along with safe drinking water, medical camps and toilets for women, crèche for infants should be made and submitted to HSPCB at the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided for mining labours. [32] A Final Mine Closure Plan along with details of corpus fund shall be submitted to the SEIAA well within the stipulated period as prescribed in the minor mineral concession rules 2012.. [33] The project proponent shall ensure that the EC letter as well as the status of compliance of EC conditions and the monitoring data are placed on company’s website and displayed at the project site. [34] The project proponent shall ensure that loading in Trucks do not exceed the norms fixed by the Transport Department as per relevant rules. [35] The project proponent shall ensure approach roads are widened and strengthened as per requirements fixed by PWD and district administration before the start of the work. [36] The project proponent shall ensure supply of drinking water through RO. [37] The project proponent shall comply with all the conditions of mining as provided in the Notification dated 15.01.2016 issued by the Ministry of Environment, Forest and Climate Change, Government of India. [38] The project proponent shall strictly comply with the orders passed by the Hon’ble NGT dated 18.02.2016 and 01.06.2016 and also comply with the Comprehensive Mining Plan/Recommendations prepared by the High Powered Committee constituted by the Hon’ble NGT. [39] The project proponent shall carry out mining in semi mechanized manner using manpower, tractor, trucks, JCB and excavator for king transportation. GENERAL CONDITIONS: Page 138 of 151

[i] Concealing factual data or submission of false/fabricated data and failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract action under the provisions of the Environment (Protection) Act, 1986. [ii] Any change in mining technology/scope of working shall not be made without prior approval of the SEIAA. [iii] Any change in the calendar plan including excavation, quantum of mineral and waste shall not be made. [iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring shall be decided in consultation with the Haryana State Pollution Control Board (HSPCB). Six monthly reports of the data so collected shall be regularly submitted to the HSPCB/CPCB including the MOEF, Regional office, Chandigarh. [v] Personnel working in dusty areas shall wear protective respiratory devices they shall also be provided with adequate training and information on safety and health aspects. [vi] Occupational health surveillance program of the workers shall be undertaken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed. [vii] The funds earmarked for environmental protection measures shall be kept in separate account and shall not be diverted for other purpose. Year wise expenditure shall be reported to the HSPCB and the Regional office of MOEF located at Chandigarh. [viii] The project proponent shall also submit six monthly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) to the northern Regional Office of MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana. [ix] The above conditions will be enforced, inter alia, under the provision of the Water (Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act 1991 (all amended till date) and rules made hereunder and also any other orders passed by the Honb’le Supreme Court of India/High Court of Haryana and other Court of law relating to the subject matter. [x] The Project proponent should inform the public that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the Haryana State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. [xi] All the other statutory clearances such as the approvals for storage of diesel from the Chief Controller of Explosives, Fire department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be obtained, as may be applicable, by Project proponent from the competent authority before the start of mining operation. [xii] That the grant of this EC is issued from the environmental angle only, and does not absolve the project proponent from the other statutory obligations prescribed under any other law or any other instrument in force. The sole and complete responsibility, to comply with the conditions laid down in all other laws for the time being in force, rests with the industry/unit/project proponent. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of National Green Tribunal Act, 2010. [xiii] The methodology of mining shall be strictly as per orders passed by Hon’ble NGT/ Hon’ble Supreme Court from time to time. [xiv] The PP shall not disturb/damage the position of studs in river bed and also not to damage the river banks and not to degrade the river bed in any manner. [xv] Any area which have been banned by any authority/courts shall not be used for mining activity. Page 139 of 151

[xvi] Distance of mining to be maintained from Pucca Hydraulic structure/ Bridges shall be as per approved mining plan/ guideline issued by MoEF & CC/ Court Orders. [xvii] Quantum mining allowed in the river will be actual replenishment or mining allotted whichever is less. [xviii] Any area which has been banned by any authority will be out of bound of mining. [xix] The PP should set the Probable replenishment checked from the reputed institution.

134.31 Environmental Clearance for the proposed mining of Minor Minerals “Road Metal & Masonry Stone” at Village Mukundpura, District Mohindergarh, Haryana by M/s Satish Kumar Garg Project Proponent : Sh. Satish Kumar Garg, Director Consultant : Vardan Enviro Solutions The project was submitted to the SEIAA, Haryana on 09.01.2015. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for approval of Terms of Reference in the 118th meeting of the SEAC held on 03.03.2015. During discussions the project proponent has placed on record the copy order dated 15.01.2015 whereby Hon’ble National Green Tribunal upheld their earlier order dated 28.03.2014 and ordered that the Office Memorandum issued by MoEF dated 24.12.2013 as “operative regarding the categorization of mining project for the appraisal of State Level Expert Appraisal Committee as category B1 to B2". The case was appraised in the 118th meeting of the SEAC held on 03.03.2015 and recommended to SEIAA for grant of Environmental Clearance. This case was taken up by the SEIAA in its 84th meeting held on 29.10.2015 and following observations were observed and conveyed to the project proponent vide letter No. 504 dated 19.11.2015. 1. The project proponent has not submitted NOC from the Forest Department. The project proponent on 29.10.2015 submitted letter issued by Mines and Geology Department indicating that the mine leased area is not a Forest land. The SEAC should examine the same. 2. The SEAC in its recommendation has given different figures of production. The lease period is for remaining three years whereas in the conditions the production 18 figures have been given of year wise up to 5 years and sum of production for the next five years. 3. The mine lease has been granted for 20 years w.e.f. 20.07.1999 up to 10.07.2019. Therefore the mine is in operation and it is not a new project. 4. The project proponent shall submit an undertaking stating that they have kept amount (figures to be given) for reclamation of excavated mine lease area and shall also ensure that all the environmental safe-guards shall be adopted for closure of mine. SEIAA has returned the case on 19.11.2015 with the advice that the SEAC should reappraise the case and submit its recommendation on merits within stipulated period. The project proponent submitted the reply of the shortcomings vide letter dated 18.12.2015. Thereafter this case was taken up for in the 125th meeting of the SEAC held on 11.01.2016. The SEAC reappraised the case in its 125th meeting and found that as far as the reply of the observation at Sr. No. 1 is concerned the project proponent so far has not Page 140 of 151

submitted the compliance and the Committee is of the unanimous view that the PP should submit complete compliance of the following observation within 30 days. 1. The PP should submit the NOC from the Forest. 2. The PP should submit reclamation, rehabilitation and final closure plan. The observations of 125th meeting were conveyed to the project proponent vide letter No. 529 dated27.01.2016. The PP submitted the reply vide letter dated 26.04.2016. Thereafter the case was taken up in the 133rd meeting of the SEAC held on 06.05.2016. After detailed discussions, the following shortcomings were observed: 1. The PP should submit NOC from Forest Department. The project proponent had undertaken to submit compliance of above point within 10 days and requested for considering their case for appraisal in the next meeting of the SEAC to be held on 01.06.2016. It was unanimously decided by the Committee that in case the PP submits the reply on the above mentioned observations within 10 days, this case will be considered in the next meeting to be held on 01.06.2016. It was also made clear to the Project Proponent that no separate letter will be issued for attending the meeting of the SEAC to be held on 01.06.2016.. Thereafter the case was taken up in the 134th meeting of the SEAC held on 01.06.2016. The Project Proponent requested for adjournment and the same was discussed in the meeting. The Committee acceded to the request and decided to issue 30 days notice to the PP. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent.

134.31(S1) Environmental Clearance for the Warehouse Project at Village Pathrari, District Gurgaon by M/s Sunsat Infotech Private Limited The project proponent submitted the application for obtaining Environmental Clearance to the SEIAA, Haryana on 30.08.2013. Observations were conveyed to the project proponent vide letter No. 637 dated 30.08.2013 for the submission of reply within 30 days. The project proponent submitted the reply of the observations on 03.09.2013. Thereafter the case was taken up for the appraisal in the 92nd meeting of SEAC held on 07.10.2013 and some observations were observed which were conveyed to the PP vide letter No. 764 dated 14.10.2013. The reply to the observations was not received.

Final opportunity was given to the Project Proponent vide letter No. 1482 dated 17.07.2014 for the submission of reply within 15 days failing which it will be presumed that PP is no more interested in obtaining EC and case will be recommended for filing without giving any further opportunity. No reply was received from the project proponent inspite of issuance of final notice. The matter was placed before the SEAC in its 112th Meeting held on 19.09.2014 and it was unanimously decided that the case be sent to SEIAA for de-listing as the project Page 141 of 151

proponent failed to comply with the observations within a period of six months as per the directions of MoEF. SEIAA has returned the case on 07.11.2014 with the remarks that the SEAC should visit the site to check status of construction if any and submit its recommendation on merits alongwith the inspection report within stipulated period. The matter was discussed in the State Expert Appraisal Committee in its 117th Meeting held on 18.02.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. I.J. Juneja, Chairman, SEAC 2. Sh. Azad Singh Hooda, Member, SEAC ( Coordinator) The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter, the case was taken up in the 119th meeting of the SEAC held on 20.10.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. G.R. Goyat, Chairman, SEAC 2. Sh. Hitender Singh, Member, SEAC (Coordinator)

The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case be referred to the SEIAA for initiating further necessary legal action. The case under consideration is recommended to be prosecuted. 134.31(S2) Extention of Environmental Clearance for “ Parasvnath Mall” Commercial Complex at Sector-8, Near Tau Park, District Sonipat, Haryana by M/s Parsvnath Developer Ltd.

Applicant proposes to set up Commercial Complex “Parasvnath Mall” at Sector-8, Near Tau Devi Lal Park, District Sonipat, Haryana. The project proponent submitted application for Extension of validity of Environmental Clearance to SEIAA on dated 07.04.2014 and was forwarded to SEAC on dated 05.06.2014. The Environmental Clearance to the project proponent has already been granted by the SEIAA, Haryana vide letter No. 161 dated 16.04.2009 for five years i.e. upto 15.04.2014. Page 142 of 151

The provisions of the Environment Impact Assessment Notification, 2006, for extension is reproduced as under: “9. Validity of Environmental Clearance(EC) The “Validity of Environmental Clearance” is meant the period from which a prior environmental clearance is granted by the regulatory authority, or may be presumed by the applicant to have been granted under sub paragraph (iv) of paragraph 7 above, to the start of production operations by the project or activity, or completion of all construction operations in case of construction projects (item 8 of Schedule), to which the application for prior environmental clearance refers. The prior environmental clearance granted for a project or activity shall be valid for a period of ten years in the case of River Valley projects (item 1(c) of the Schedule), project life as estimated by Expert Appraisal Committee or State Level Expert Appraisal Committee subject to a maximum of thirty years for mining projects and five years in the case of all other projects and activities. However, in the case of Area Development Projects and Townships [item 8(b)], the validity period shall be limited only to such activities as may be the responsibility of the applicant as a developer. This period of validity may be extended by the regulatory authority concerned by a maximum period of five years provided an application is made to the regulatory authority by the applicant within the validity period, together with an updated Form I, and Supplementary Form 1A, for Construction projects or activities (item 8 of the Schedule). In this regard the regulatory authority may also consult the Expert Appraisal Committee or State Level Expert Appraisal Committee as the case may be.” The validity period of EC was elapsed on dated 15.04.2014 and the project proponent has submitted the application well within the stipulated period as per the provisions of EIA Notification, 2006. The case was discussed in the 107th meeting of the SEAC held on 01.07.2014. It was unanimously decided that further action may be taken on the basis of the documents available in the case file when the Environmental Clearance was originally granted and compliance report submitted by the project proponent to the Regional Director, Ministry of Environment and Forest, Government of India with copy to SEIAA. SEIAA has returned the case on 26.11.2014 with the remarks that the SEAC should visit the site to check status of construction if any and submit its recommendation on merits alongwith the inspection report within stipulated period. The matter was discussed in the State Expert Appraisal Committee in its 117th Meeting held on 18.02.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. Sultan Singh, Member, SEAC ( Coordinator) 2. Dr. Surinder Singh Yadav, Member, SEAC It was decided by the Committee that an internal meeting of SEAC will be convened/conducted by the Chairman, SEAC at his level on 05.03.2015 at Bay No. 55-58, Paryatan Bhawan, Sector-2, District Panchkula for finalization of Sub-Committee report. The decisions taken in the internal meeting will be conveyed to the SEIAA directly by the Committee. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the Page 143 of 151

MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter the case was taken up in the 123rd meeting of the SEAC held on 11.12.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. G.R. Goyat, Chairman 2. Sh. Hitender Singh, Member (Coordinator) The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case may be placed for appraisal in the 135th meeting of the SEAC to be held on 27.06.2016. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. 134.31(S3) Environmental Clearance for the proposed Expansion of Model Economic Township at Jhajjar, Haryana by M/s Reliance Haryana SEZ Ltd. The project was submitted to the SEIAA, Haryana on 09.01.2015. The project proponent submitted the case to the SEIAA as per check list approved by the SEIAA/SEAC. The case was taken up for approval of Terms of Reference in the 118th meeting of the SEAC held on 03.03.2015. During discussions, it was informed by the project proponent that the Environmental Clearance was granted by the Ministry of Environment and Forest, Government of India vide letter dated 16.08.2012. In the Environmental Clearance, Part A-Specific Conditions- During construction phase Sub-Condition 1(v), it was stipulated that “the Monitoring station at drain which was agreed in the Public Hearing shall be installed by the PP.” Even after the expiry of 2 years 7 months, the PP has not initiated any action in this regard. The Northern Regional Office, Chandigarh in its monitoring report dated 20.01.2015 in the Column of compliance has recorded “Assure to Comply”. The SEAC does not agree for the expansion of the project until this condition is complied with. The observations of the 118th meeting were conveyed to the project proponent vide letter No. 2048 dated 10.03.2015. In response to the observations made in the 118th meeting of the SEAC, project proponent submitted the an application for withdrawal of their case vide letter dated 15.09.2015. Thereafter, the case was taken up for consideration in the 127th meeting of the SEAC held on 15.02.2016. During discussions Committee decided to constitute a Sub-Committee consisting of the following to inspect the site of the project:

1. Sh. G.R. Goyat, Chairman Page 144 of 151

2. Sh. R.K. Sapra, Member 3. Sh. Hitender Singh, Member (Coordinator) The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total. The Committee after detailed discussion is of the unanimous view that the case be referred to the SEIAA for delisting. 134.31(S4) EC for the proposed Expansion of Ware House Project at Village Behrampur, District Gurgaon by M/s P.D. Enterprises The project was submitted to the SEIAA, Haryana on 07.06.2013 as per check list approved by the SEIAA/SEAC. The case was taken up for appraisal in the 89th meeting of the SEAC held on 26.08.2013 and recommended to the SEIAA for grant of Environmental Clearance. SEIAA has returned the case on 19.02.2015 with the remarks that the SEAC should visit the site to check status of construction, if any, and submit its recommendation on merits alongwith the inspection report within stipulated period. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter, the case was taken up in the 119th meeting of the SEAC held on 20.10.2015. The Project proponent vide their letter dated 09th October, 2015 requested that their case for exemption in response to the amendment in Notification dated 22.12.2014. Further they have informed that they have started the construction for expansion of their Warehouse after the publication of Notification dated 22.12.2014, since they were exempted from obtaining Environmental Clearance. The Committee went through the Notification No. S.O. 3252(E) dated 22.12.2014 and Office Memorandum dated 09.06.2015 and observed that definition of Industrial Shed implies building (whether RCC or otherwise) which is being used for housing plant and machinery of industrial units and shall include godowns and buildings connected with production related and other associated activities of the unit in the same premises. The matter was discussed in detail and it was observed that it is not an industrial shed and is not covered under the notification dated 22.12.2014. The project proponent has started the construction activity in the proposed warehouse vide their letter dated 09.10.2015. Therefore, it is recommended that SEIAA may seek clarification on the subject from the MoEF & CC, GoI as to whether the Environmental Clearance is required or not. Page 145 of 151

The SEIAA on dated 28.12.2015 has returned the file with the remarks that SEAC should inspect the site and submit report. Thereafter this case was taken up in the 129th meeting of the SEAC held on 14.03.2016. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. R.K. Sapra, Member, SEAC (Coordinator) 2. Sh. A.K. Bhatia, Member, SEAC 3. Sh. S.C. Mann, Member, SEAC The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case be referred to the SEIAA for initiating further necessary legal action. The case under consideration is recommended to be prosecuted. 134.31(S5) Environmental Clearance for the proposed expansion of Residential Plotted Colony Project “Jindal Global City” District Sonipat, Haryana by M/s Jindal Realty Private Limited. The project was submitted to SEIAA, Haryana on 08.08.2014. The papers submitted were examined by the Secretary, SEAC and certain shortcomings were noticed and conveyed to PP vide letter No.1581 dated 21.08.2014. The PP submitted the reply to the shortcomings on 30.09.2014. The case was taken up for approval of Terms of Reference in the 115th Meeting of the SEAC held on 10.11.2014. The Terms of Reference were approved and conveyed to the project proponent vide letter No. 09 dated 11.12.2014 with the following conditions. 1. Table 2 of the project document on page 37 shows reduction in area of sector road, green belt and undetermined area. It should be clarified as the development area is increased. 2. The PP should submit the land schedule from DTCP in respect of License No. 24/2014. 3. The PP should submit the detail Rain Water Harvesting proposal from the remaining area not covered under big plots along with design as per HUDA norms and as approved by Central Ground Water Authority (CGWA) for zero runoff discharge fro. 4. The PP should submit the proper assurance for water availability and sewage disposal from the Competent Authority. The project proponent submitted the EIA report on 12.02.2015 on the basis of Terms of Reference approved by the Committee. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on Page 146 of 151

21.08.2015. Thereafter, the case was taken up in the 121st meeting of the SEAC held on 19.11.2015. Project proponent informed that they have collected the baseline data for the months of October, November and December, 2014, wherein the Terms of Reference were approved by the SEAC in the 115th meeting held on 10.11.2014. The matter was discussed in detail and it was unanimously decided that the PP will collect one month more baseline data and submit EIA report by incorporating the fresh data accordingly. The observations of the 121st meeting were conveyed to the PP vide letter No. 298 dated 1.12.2015. The PP submitted the reply vide letter dated 08.02.2016. Thereafter, the case was taken up for appraisal in the 129th meeting of the SEAC held on 14.03.2016 as additional agenda item. During discussion, it revealed that project proponent has started the construction work which amounts to violation of Environmental Protection Act, 1986 in compliance of EIA Notification dated 14.09.2006. Further in order to assess the correct position at site, Committee decided to constitute a Sub-Committee consisting of the following to inspect the site to verify and report the status of construction of the project: 1. Sh. R.K. Sapra, Member 2. Sh. A.K. Bhatia, Member (Coordinator) 3. Sh. Hitender Singh, Member The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case may be placed for appraisal in the 135th meeting of the SEAC to be held on 27.06.2016. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. 134.31(S6) Extension & Revision in Environmental Clearance for Residential Colony “TDI City” Sector-58, 59, 60, 61, 63 & 64 Sonepat-Kundli, Haryana Environmental Clearance was expired on 01.11.2012. The application for EC was submitted on 28.08.2014 which is after the expiry of validity period. The request for extension of validity period of EC is not covered under the instruction given as under: “9. Validity of Environmental Clearance(EC) The “Validity of Environmental Clearance” is meant the period from which a prior environmental clearance is granted by the regulatory authority, or may be presumed by the applicant to have been granted under sub paragraph (iv) of paragraph 7 above, to the start of production operations by the project or activity, or completion of all construction operations in case of construction projects (item 8 of Schedule), to which the application for prior environmental clearance refers. The prior environmental clearance granted for a project or activity shall be valid for a period of ten years in the case of River Valley projects (item 1(c) of the Schedule), project life as estimated by Expert Appraisal Page 147 of 151

Committee or State Level Expert Appraisal Committee subject to a maximum of thirty years for mining projects and five years in the case of all other projects and activities. However, in the case of Area Development Projects and Townships [item 8(b)], the validity period shall be limited only to such activities as may be the responsibility of the applicant as a developer. This period of validity may be extended by the regulatory authority concerned by a maximum period of five years provided an application is made to the regulatory authority by the applicant within the validity period, together with an updated Form I, and Supplementary Form 1A, for Construction projects or activities (item 8 of the Schedule). In this regard the regulatory authority may also consult the Expert Appraisal Committee or State Level Expert Appraisal Committee as the case may be.” The case was discussed in the 112th meeting of the SEAC held on 18.09.2014. The Committee is of the unanimous view that this case may be decided at the level of SEIAA for considering his request as per conditions given as per EIA Notification. SEIAA has returned the case on 26.11.2014 with the remarks that the SEAC should visit the site to check status of construction if any and submit its recommendation on merits alongwith the inspection report within stipulated period. The case was taken up in the 117th meeting of the SEAC held on 18.02.2015. The SEAC could not hold any meeting from 25th November, 2014 upto January, 2015 due to absence of Secretary, SEAC which was appointed by the Government on 19th January, 2015. Now there is no time left with the SEAC for detailed consideration of this case as it cannot be included in the agenda at the feg end of the tenure of SEAC. Therefore, the Committee has unanimously decided to refer back the case to SEIAA for taking appropriate action at their level. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter the case was taken up in the 123rd meeting of the SEAC held on 11.12.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. G.R. Goyat, Chairman 2. Sh. A.K. Bhatia, Member (Coordinator) The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case may be placed for appraisal in the 135th meeting of the SEAC to be held on 27.06.2016. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. Page 148 of 151

134.31(S7) Extension of EC for Group Housing Complex “Parikarma” at Sector-20, Village Kundli, Panchkula, Haryana by M/s Santur Developer Pvt. Ltd.

This case was taken up in the 81st meeting of SEIAA held on 18.02.2015; wherein it was noticed that the environmental clearance to this project was accorded by MOEF GOI vide letter dated 23.07.2007. The validity of EC letter was up to 22.07.2012. The project proponent vide letter dated 24.12.2014 submitted the application for extension of validity of environmental clearance letter two years late. The project proponent informed that 70% of civil construction has been achieved. The project proponent submitted certified copy of compliance report, copy of valid license updated Form-I, Form-IA and photographs showing status of construction but failed to give justified reply for late submission of application for extension of validity. It was also not clear whether the project proponent has raised any construction after the expiry of Environmental Clearance. SEIAA has returned the case on 09.03.2015 with the remarks that the SEAC should visit the site to check status of construction if any and submit its recommendation on merits alongwith the inspection report within stipulated period. The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015.Thereafter the case was taken up in the 123rd meeting of the SEAC held on 11.12.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. R.K. Sapra, Member 2. Sh. Hitender Singh, Member (Coordinator) The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case may be placed for appraisal in the 135th meeting of the SEAC to be held on 27.06.2016. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. 134.31(S8) Extention of Environmental Clearance for Township Project “ Parsvnath City, Dhaurhera”, Sector 1, 1B and 2B, Near Village Kharkhera, District , Haryana by M/s Parsvnath Developer Ltd.,

Applicant proposes to set up Township Project “ Parsvnath City, Dhaurhera”, Sector 1, 1B and 2B, Near Village Kharkhera, District Rewari, Haryana. The project proponent Page 149 of 151

submitted application for Extension of validity of Environmental Clearance to SEIAA on dated 29.04.2014 and was forwarded to SEAC on dated 05.06.2014. The Environmental Clearance to the project proponent has already been granted by the SEIAA, Haryana vide letter No. 474 dated 26.05.2009 for five years i.e. upto 25.05.2014. The provisions of the Environment Impact Assessment Notification, 2006, for extension is reproduced as under: “9. Validity of Environmental Clearance(EC) The “Validity of Environmental Clearance” is meant the period from which a prior environmental clearance is granted by the regulatory authority, or may be presumed by the applicant to have been granted under sub paragraph (iv) of paragraph 7 above, to the start of production operations by the project or activity, or completion of all construction operations in case of construction projects (item 8 of Schedule), to which the application for prior environmental clearance refers. The prior environmental clearance granted for a project or activity shall be valid for a period of ten years in the case of River Valley projects (item 1(c) of the Schedule), project life as estimated by Expert Appraisal Committee or State Level Expert Appraisal Committee subject to a maximum of thirty years for mining projects and five years in the case of all other projects and activities. However, in the case of Area Development Projects and Townships [item 8(b)], the validity period shall be limited only to such activities as may be the responsibility of the applicant as a developer. This period of validity may be extended by the regulatory authority concerned by a maximum period of five years provided an application is made to the regulatory authority by the applicant within the validity period, together with an updated Form I, and Supplementary Form 1A, for Construction projects or activities (item 8 of the Schedule). In this regard the regulatory authority may also consult the Expert Appraisal Committee or State Level Expert Appraisal Committee as the case may be.” The validity period of EC was elapsed on dated 25.05.2014 and the project proponent has submitted the application well within the stipulated period as per the provisions of EIA Notification, 2006. The case was discussed in the 107th meeting of the SEAC held on 01.07.2014. It was unanimously decided that further action may be taken on the basis of the documents available in the case file when the Environmental Clearance was originally granted and compliance report submitted by the project proponent to the Regional Director, Ministry of Environment and Forest, Government of India with copy to SEIAA. SEIAA has returned the case on 26.11.2014 with the remarks that the SEAC should visit the site to check status of construction if any and submit its recommendation on merits alongwith the inspection report within stipulated period. The matter was discussed in the State Expert Appraisal Committee in its 117th Meeting held on 18.02.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. Sultan Singh, Member, SEAC ( Coordinator) 2. Dr. Surinder Singh Yadav, Member, SEAC It was decided by the Committee that an internal meeting of SEAC will be convened/conducted by the Chairman, SEAC at his level on 05.03.2015 at Bay No. 55-58, Paryatan Bhawan, Sector-2, District Panchkula for finalization of Sub-Committee report. The decisions taken in the internal meeting will be conveyed to the SEIAA directly by the Committee. Page 150 of 151

The case could not be taken up in the SEAC as the term of SEIAA/SEAC was elapsed on 21.03.2015. Therefore, the case was transferred to Ministry of Environment and Forest, Government of India in the month of March, 2015. This case could not taken up by the MoEF and was again transferred to SEIAA on 31.08.2015 after the reconstitution of SEIAA/SEAC on 21.08.2015. Thereafter the case was taken up in the 123rd meeting of the SEAC held on 11.12.2015. It was decided to constitute a Sub-Committee for site visit: The sub-committee will consist of the following: 1. Sh. G.R. Goyat, Chairman 2. Sh. A.K. Bhatia, Member (Coordinator) The site has since been visited and Sub-Committee had submitted its report on 01.06.2016. The report of the Sub-Committee was placed before the Committee in the 134th meeting of the SEAC held on 01.06.2016. The Sub-Committee report was read out to all the Members of the Committee and deliberated in detail. The Committee has accepted the report of the Sub-Committee in total.

The Committee after detailed discussion is of the unanimous view that the case may be placed for appraisal in the 135th meeting of the SEAC to be held on 27.06.2016. Accordingly the notice will be issued by the Secretary, SEAC to the Project Proponent. The meeting ended with the vote of thanks to the Chair. Page 151 of 151

Annexure-‘A’ List of Participants

1. Shri Raj Kumar Sapra, IFS(Retd.) Member House No. 601, Angel Apartment Society No. 12, Sector-24, Panchkula

2. Shri S.C. Mann, Member House No. 544, Sector-12-A, Panchkula Haryana

3. Shri A.K. Bhatia, Member House No. 679, Sector-8, Panchkula, Haryana

4. Shri Hitender Singh, Architect, Member Department of Architecture, Haryana

5. Dr. S.N. Mishra, Member House No. 220, First Floor, Sector-14, , Haryana

6. Sh. S.K. Gupta, Special Invitee Mining Expert

7. Sh. S. Narayanan, IFS Secretary Member Secretary, Haryana State Pollution Control Board, Panchkula