Initial Environmental Examination

Document Stage: Draft Project Number: 42486-018 June 2021

India: Urban Services Improvement Project – Additional Financing (Subproject of Water Supply Improvement in Kari, and Lidhora Khas)

Package No. MPUSIP-6H

Prepared by the Project Management Unit, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

CURRENCY EQUIVALENTS (As of 29th June 2021)

Currency unit – Conversion INR1.00 = $.0.013 $1.00 = INR 74.23

ABBREVIATIONS

ADB - Asian Development Bank EA - Executive Agency GOI - Government of GOMP - Government of Madhya Pradesh IA - Implementing Agency MPUDC - Madhya Pradesh Urban Development Company MPUSIP - Madhya Pradesh Services Improvement Project PHED - Public Health Engineering Department PIU - Project Implementation Unit PMC - Program Monitoring Consultant PMU - Program Management Unit PWD - Public works Department ROW - Right of Way RWA - Resident Welfare Associations RWRM - Raw Water Rising Main SPS - Safeguard Policy Statement UDHD - Urban Development and Housing Department ULBs - Urban Local Bodies WRD - Water Resource Department WSS - Water Supply Scheme WTP - Water Treatment Plant

WEIGHTS AND MEASURES

C Degree Celsius km kilometre lpcd litres per capita per day MCM Million Cubic Meter mm milli meter m metre MLD million litres per day mm millimetre Nos. Numbers sq. km Square Kilometre

NOTE

In this report, "$" refers to United States dollars.

This draft initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CONTENTS

I. INTRODUCTION 1 A. Background 1 B. Purpose of this IEE Report 2 C. Report Structure 2 II. DESCRIPTION OF THE PROJECT 3 A. Project Area 3 B. Existing Water Supply Situation 4 C. Proposed Project 5 III. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 18 A. ADB Policy 18 B. National Environmental Laws 18 IV. DESCRIPTION OF THE ENVIRONMENT 22 A. Methodology Used for Baseline Study 22 B. Baseline Environmental Profile 22 V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 45 A. Introduction 45 B. Pre-Construction Impacts – Design & Location 46 C. Water Source Sustainability & Impacts association with water abstraction 46 D. Construction Impacts 71 E. Operation and Maintenance Impacts 78 F. Project benefits 78 VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 79 A. Overview 79 B. Public Consultation 79 C. Information Disclosure 82 VII. GRIEVANCE REDRESS MECHANISM 84 A. Structure of GRM and its Functions 85 B. Process of Grievance Redress Mechanism 89 C. Monitoring and Evaluation systems of GRM 93 D. Action Plan for the formation of the GRM 94 VIII. ENVIRONMENTAL MANAGEMENT PLAN 94 A. Implementation Arrangements 94 B. Environmental Management Plan 95 C. EMP Compliance Responsibilities 115 D. Training Needs 117 E. Monitoring and Reporting 118 F. EMP Implementation Cost 119 IX. CONCLUSION AND RECOMMENDATIONS 121

LIST OF TABLES

Table 1: Details of existing water source & system 4

Table 2: Details of existing Distribution system 4 Table 3: Details of water source & system 5 Table 4: Proposed Water Supply Subproject Components 7 Table 5: Applicable Environmental Regulations 19 Table 6: WHO Ambient Air& Noise Quality Guidelines 21 Table 7: Baseline Environmental Profile of towns 23 Table 8: Site Environmental Features of Jeron Khalsa and GWSS 38 Table 9: Site Environmental Features of Kari WSS 42 Table 10: Existing Weirs/ Check Dams across Jamni River and distance from Origin of river & proposed weir (For Kari Town) & Existing Weir(Proposed for Jeron Khalsa & Lidhora Khas Towns GWSS) 48 Table 11: Base line information for Jamini Rivers for Jeron Khalsa & Lidhora khas Town 52 Table 12: Flow data analysis and Calculation for water availability based on Catchment area & Rainfall Analysis 52 Table 13 54 Table 14: Evaporation losses of Existing Weir Proposed for Group Jeron Khalsa & Lidhorakhas WSS 54 Table 15: Storage Capacity of Weir 55 Table 16: 59 Table 17: River water flow analysis Jamni River 65 Table 18: Calculation of Weir Capacity for Kari Town WSS 65 Table 19: Flow data analysis and Calculation for water availability based on Catchment Area & Rainfall Analysis 67 Table 20:: Summary of Consultation in Kari, Jeron Khalsa & Lidhora Khas Nagar Parishads 80 Table 21: Design Stage Environmental Management Plan 97 Table 22; Pre-Construction State Environmental Management Plan 98 Table 23: Construction Stage Environmental Management Plan 101 Table 24: Operation Stage Environmental Management Plan 111 Table 25: Construction Stage Environmental Monitoring Plan 112 Table 26: Operation Stage Environmental Monitoring Plan 114 Table 27: Outline Capacity Building Program on EMP Implementation 118 Table 28: Cost Estimates to Implement the EMP 119

LIST OF FIGURES

Figure 1: MP State Map with subprojects local towns 3 Figure 2: Key Plan of Jeron Khalsa and Lidhorakhas Group WSS 11 Figure 3: Google Map Showing Proposed Group WSS Components in Lidhora Khas & Jeron Khalsa Towns 12 Figure 4: Google Map Showing Proposed WSS Components in Lidhora Khas Town 13 Figure 5: Google Map Showing Proposed WSS Components in Jeron Khalsa Town 14 Figure 6: Key Plan of Kari WSS 15 Figure 7: Google Map Showing Proposed WSS Components in Kari Town Source to OHTs 16 Figure 8: Google Map Showing Proposed WSS Components in Kari Town 17 Figure 9: Site Environs of Jeron Khalsa and Lidhorakhas Town 36 Figure 10: Site Environs of Kari Town 37 Figure 11: Distance between existing Weir for Kari and Jeron khalsa is 39.8 km 47 Figure 12: Google Earth Map Showing Location of Existing Dams/Weirs across Jamni River on U/S & D/S w.r.t. Existing Weir (Proposed for Jeron Khalsa & Lidhora Khas GWSS 50 Figure 13: Google Map Showing location of Existing Weir (Proposed For Jeron Khalsa & Lidhora Khas Towns GWSS), Intake Well at Milanghat and location of nearest Existing Weir across Jamini River. 51 Figure 14: Catchment Area for proposed Weir for jeron Khalsa and Lidorkhas 53 Figure 15: Capacity curve of GWSS Jeron Khalsa & Lidhora Khas WSS 55 Figure 16: Submergence Area of Jamni River for Jeron Khalsa & Lidhorakhas Town weir. 57 Figure 17: Typical Cross section and Plan with and without gate for weir Lidhora Khas & Jeron Khalsa 58 Figure 18: Showing Origin & Destination Point and Existing Weirs on U/S & D/S across Jamini River From Proposed weir Kari Town WSS Near Aamghat 62 Figure 19: Google Map Showing location of proposed Weir, intake Well and location of nearest Existing Weir (D/S) at Aamghat for Kari Town WSS. 64 Figure 20: Capacity curve of GWSS Jeron Khalsa & Lidhora WSS 66 Figure 21: shows Catchment area of Jamni River w.r.t. Proposed Weir for Kari Town 67 Figure 22: Typical Cross section and Plan with and without gate for weir for Kari town. 69 Figure 23:Submergence Area Map of Proposed Weir Kari Town WSS 70 Figure 24: Work Flow Diagram on GRM 89 Figure 25: Structure and Process of GRC 93

APPENDICES

Appendix 1: REA Check list ...... 123 Appendix 2: National Ambient Air Quality Standards ...... 131 Appendix 3: Vehicle Exhaust Emission Norms ...... 132 Appendix 4: National Ambient Air Quality Standards In Respect Of Noise ...... 133 Appendix 5: Stakeholder Consultation ...... 134 Appendix 6: Extract From Construction & Demolition Management Rules, 2016 ...... 153 Appendix 7: Salient Features Of Major Labor Laws Applicable To Establishments Engaged In Construction Of Civil Works ...... 159 Appendix 8: Water Source Sustainability Report ...... 161 Appendix 9: Sample Grievance Registration Form ...... 171 Appendix 10: Sample Outline Spoils (Construction Waste) Management Plan...... 172 Appendix 11: Sample Outline Traffic Management Plan ...... 173 Appendix 12: Drinking Water Standards...... 180 Appendix 13: Sample Environmental Site Inspection Report ...... 184 Appendix 14: Quarterly Reporting Format For Assistant Safeguards Officer ...... 186 Appendix 15: Guideline for Construction Work about Safety from COVID-19 Pandemic ...... 191

EXECUTIVE SUMMARY

Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

The Project components are as follows:

Component 1: Improvements to water supply and sewerage services in identified towns

• Continuous, pressurized, safe and sustainable drinking water through private household metered connections in sixty-four towns in the State of Madhya Pradesh in Central India; and • Sewage and storm water collection and treatment services proposed initially in sixo (6) identified towns (Khajuraho and Rajnagar, Sanchi, Maihar, Dhamnod & Nagda) etc.

Component 2: Institutional Strengthening

• Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; • Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and • Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

The Subproject. Kari, Jeron Khalsa and Lidhorakhas are located in the District in the northern part of Madhya Pradesh state. These are small towns having the status of Municipal Council (Nagar Parishad) and population as per 2011 census was: Kari- 10409, Jeron Khalsa- 9426 and Lidhorakhas- 12978. Improvement of water supply in these three towns will be implemented under a single Design-Build-Operate (DBO) contract package. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery, providing 100% coverage with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes the following civil works.

• Proposed Jeron Khalsa and Lidhorakhas group water supply scheme works : (i) Increasing height of existing weir on Jamni river by 1.5 m (total height- 3.0+1.5= 4.5) and Intake well of 6 m diameter and 10.5 m height proposed at Khasra no. 29/30/31 on Jamni river, (ii) Water treatment plant with 3.25 MLD capacity at Khasra no.149/02, Sarsau ki toriya near Bajrang garh. (iii) Raw Water ii

Main of about 950 m length from intake well to WTP (iv) Two Over Head Tank (OHT) of capacity 200 KL each at ward no. 03 andward no. 09 for Lidhorakhas NP and one OHT with 100 KL capacity at ward no. 05 for Jeron Khalsa at khasra no. 1966/1/kha Ward no. 12. NP; (v) distribution network pipe laying 69255 m ; and (vi) 905 Nos. Domestic connection for Jeron khalsa and 1497 for Lidhorakhas. • Proposed Kari water supply scheme: (i) Weir of 160 m length and 3.5 m height at Aamghat on Jamni River and Intake well of 6 m dia and 14.37 m height,(ii) Raw water rising main of 10850 m long and 150 mm dia (ii) Water Treatment plant with 1.70 MLD capacityat ward no. 03, (iii) clear water feeder mains of about 1841 m length, (iv) Three GSR of capacity 110 KL, 170 KL and 200 KL; (v) distribution network pipe laying (31743 m); and (vi) 1120 Nos. of Domestic & 50 Nos. of Non-Domestic house service connections.

Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. As per the GoI EIA Notification, 2006, these subprojects do not require EIA study or environmental clearance. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely.

Aim of this IEE is to (i) provide critical facts, significant findings, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures.

Description of the Environment.

Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. While there is no natural habitat left within the town areas, the areas near river intakes are comparatively intact though most of the lands there too converted iii into agricultural use. There are no protected areas, like wildlife sanctuaries, national parks, nor there are any historically, archeologically protected areas in the vicinity. Towns are densely populated in the core/old town areas with narrow lanes, and small and closely built houses, while most of the areas are undeveloped and are still under agricultural use. Commercial areas are along the main roads, which are mostly congested with activities, pedestrians and traffic.

Jeron Khalsa and Lidhora Khas Towns WSS: The subproject components locations are in subproject towns Kari, Jeron Khalsa and Lidhorakhas towns and their surroundings. Jamini River is about 2.5 km far from Jeron Khalsa and about 28 Km from Lidhorakhas. There is a 276 m long and 3.0 m high existing stop dam built by WRD on the Jamni River near milanghat. The capacity of existing stop dam is 0.725 MCM. This capacity is not sufficient to fulfil the water demand of both the towns., Existing weir has been proposed for water storage after increasing the height of existing weir by 1.5m, so that its storage capacity should be sufficient to fulfil the water demand of group scheme for Lidhora Khas & Jeron Khalsa towns. This existing stop dam need to some repairing work to meet the functional requirement. A common intake well also proposed on the bank of Jamini River near existing dam at Bajrang garh to draw the total water demand 2.98 MLD of both of the towns. These facilities are located outside the town, and are mostly surrounded by agricultural lands, and river/reservoir. None of the component, however located on any forest land. Rest of the components – water tanks, distribution lines, connections etc., will be located within the urban areas.

A common WTP of capacity 3.25 MLD has been proposed near bajranggarh outside the town. Raw water will be pumped from Jamini River to proposed WTP through 950-meter-long DI K-9 pumping mains of dia 250mm along an existing main road within RoW. After treatment from WTP, clear water will be pumped to existing and proposed OHT of respective towns through HDPE PN-10 distribution line. 1 OHT of capacity 100 Kl is proposed at ward no.05, Jeron Khalsa and 02 different OHT of 200KL capacity is proposed at ward no.3 & Ward no. 9 of Lidorakhas town. To fill ESR’s of Lidhorkhas, intermediate pumping station has been proposed. ESR’s is proposed at Village Samdhua-Durana about 8 Km from Jeron Khalsa. The raw water transmission pipes, connecting intake and WTP, will be essentially outside the town, and clear water transmission pipes, from WTP to distribution reservoirs, will be partly outside and partly within the towns. Distribution networks will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. There are no trees along the roads, except in some colonies in the outer areas. In old town areas pipes will be laid in the middle of the road, which may affect the traffic.

Kari Town WSS: River Jamni flows about 11.5 Km away from the town Kari. In the Jamni River near Aamghat there is an existing weir which was constructed by WRD. The length of the existing Weir is 130 m and height is 2.5 m. This existing weir is deteriorating condition hence a new weir has been proposed upstream to this weir across Jamini River. An Intake well of 6m dia and 14.37 m height is proposed at the bank of Aamghat on Jamini River near proposed weir to draw the total water demand of 1.56 MLD for Kari Nagar Parishad. The distance between the weir proposed for group scheme Jeron Khalsa & Lidhora Khas WSS is about 39.8 km as shown in Fig 11. These facilities are located outside the town, and are mostly surrounded by agricultural lands, and rivers/reservoirs. None of the components however located on any forest land. Raw water rising main from Intake well to WTP is conveyed through proposed rising mains of 10850m long of 150mm Dia DI-K9 will be laid underground within RoW of existing main road.

A WTP is proposed of capacity 1.7 MLD at Viyogi ward No. 01. After treatment from WTP clear water will be convey by pumping mains to existing GSR of capacity 100 KL and 3 No proposed

iv

GSR having capacity 110 KL at ward no. 10, 170KL at ward no. 7 and 200KL at ward no. 13 respectively. The raw water transmission pipes, connecting intake and WTP, will be essentially outside the town, and clear water transmission pipes, from WTP to distribution reservoirs, will be partly outside and partly within the town. Rest of the components – water tanks, distribution lines, connections etc., will be located within the urban areas. Distribution networks will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. There are no trees along the roads, except in some colonies in the outer areas. In old town areas pipes will be laid in the middle of the road, which may affect the traffic.

Environmental impacts arise due to the project design or because of the locations chosen for the project components are not significant. The proposed water supply schemes include creation of new water sources with the nearest /feasible surface water body. Schemes include construction of a new weir and increasing height of existing weir (for group water supply scheme of Jeron Khalsa and Lidhorakhas Towns).

Both the weirs are proposed on Jamni River, and the distance between the weir proposed for group scheme of Jeron Khalsa- Lidhora khas WSS and Kari WSS is about 40 km (river length). Jamni River is not a perennial river, and flows mostly during monsoon and post monsoon, from early July to October. It carries high flows during the months of July and August, medium flows during September-October, after which flow reduces considerably, and river completely dry by the month of December / January. It runs dry until the onset of monsoon. No flow data is available as there is no gauging station on the river. To provide for low / no season period, raw water storage is necessary for provision of water supply to the subproject towns. For Jeron Khalsa- Lidhora khas scheme, there is an existing weir of 3.0 m high, and it is assessed to be not adequate to meet the ultimate demand of the scheme (2.98 MLD or 1.087 MCM per year), and therefore it is proposed to increase the height from 3.0 m to 4.5 m by installing gates over the existing weir after rehabilitation. For Kari scheme, there is an existing weir of 2.5 m high on Jamni River, which is in poor condition, and therefore it is proposed to construct a new weir of 3.5 m height to meet the ultimate demand of Kari Scheme (1.56 MLD or 0.569 MCM per year).

Total length of the river is 201 km, and is non-perennial and flows only during part of the year. It flows for about 4months, mostly during monsoon and winter seasons, from early July to October. No flow data is available as there is river no gauging station on the river. Weirs and storage reservoir required for the lean / no flow season. The water demand of Kari town is 1.56 MLD or 0.569 MCM per year, while total available water based on catchment area and rainfall analysis is 169 MCM. The abstraction is just about 0.34 % of water available. The proposed yearly water abstraction for combined scheme of Jaron Khalsa and Lidhora khas is 1.0877 MCM, which is just a fraction (about 0.3%) of total yearly water availability in the catchment (i.e.,357.80 MCM).

Considering this negligible proportion of water abstraction, no notable impacts are anticipated in the downstream due to reduction in flow. There are already existing several existing dams/weirs on the river. Construction of a new weir just upstream side of the existing weir and increasing the height will not significantly alter the existing flow regime. Given intermittent nature of river, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. At the proposed weir location, the riverbanks are higher than and the proposed weir height. Therefore, the water storage is confined to river course / flood plain, and there is no submergence of lands outside v the river. No negative impacts or acquisition of government of private or government lands anticipated.

As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after contract award. Water quality is good and there are no potential pollution sources in the vicinity that could affect the water quality. Necessary precautionary measures are suggested to avoid any impacts.

During the project construction phase, potential negative impacts may arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels are proposed here.

Environmental Management Plan. As a part of mitigate measures in order to achieve acceptable levels in the negative impacts, an environmental management plan (EMP) has been proposed. The EMP given here includes the design measures for (i) safe disposal of sludge coming out of wash water tanks from WTP to reduce effluent (ii) energy efficient pumping equipment and (iii) quick leak detection and rectification to save the resources, etc. During execution phase, the EMP includes mitigation measures such as (i) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts (ii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iii) provision of walkways and planks over trenches to ensure access will not be impeded; (iv) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (v) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vi) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non- detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv)

vi

budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the towns, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

Implementation Arrangements. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh is the Executing Agency and Madhya Pradesh Urban Development Company (MPUDC) is the Implementing Agency. Project Management Unit (PMU) attached to MPUDC is responsible for implementation and will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC), will support PMU & PIUs. Infrastructure will be designed, built, and operated by DBO contractor for 10 years, after which it will be transferred to ULBs. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks and will be supported by PMC. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

Conclusions and Recommendations. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require permission of Water Resources Department (WRD) for water abstraction from Jamni River, weir and intake construction, and consent of Madhya Pradesh Pollution Control Board (MPPCB) for WTP for both the schemes. These permissions/approvals shall be obtained prior to award of contracts.

This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

I. INTRODUCTION

A. Background

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project. A project management unit (PMU) created under MPUDC is implementing MPUSIP.

2. MPUSIP’s physical components include (a) improvements to water in 64 project towns, and (b) sewage and storm water collection and treatment services proposed in seven (6) identified towns namely Sanchi, Maihar, Dhamnod, Nagda and Khajuraho-Rajnagar under tranche II. The project also includes an institutional strengthening component and a project management and administrative support component.

3. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in six (6) identified towns (Khajuraho and Rajnagar, Sanchi, Maihar, Dhamnod & Nagda,) ;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

4. The Subproject. Kari, Jeron Khalsa and Lidhorakhas are located in the in the northern part of Madhya Pradesh state and improvement of water supply in these four towns is one of the subprojects proposed under MPUSIP. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost 2

recovery and conservation of precious water resources. The subproject envisages providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works (weir, raw and clear water transmission, overhead tanks, distribution network, consumer connections and flow meters), project implementation and management, and non-physical investments. A detailed description of the components is provided in Section III.

B. Purpose of this IEE Report

5. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Appendix 1). Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS’s requirements for environment category B projects.

6. This IEE is based on the preliminary engineering report prepared by the DPR consultant team namely, “BLG CONSTRUCTION SERVICES (P) LTD., JODHPUR.” and will be finalized during implementation stage by DBO contractor to reflect any changes and latest subproject designs. The IEE was based mainly on field reconnaissance surveys and secondary sources of information. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. Stakeholder consultation was an integral part of the IEE.

C. Report Structure

7. This Report contains the following nine (9) sections:

(i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Description of the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii) Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental management plan, and, (x) Conclusion and recommendation. 3

II. DESCRIPTION OF THE PROJECT

A. Project Area

8. Kari: Kari is a town located in Tikamgarh District of Madhya Pradesh State. Kari was declared as a Nagar Panchayat in 1984. In older times it was known with the name of "Chanderi". It lies in the vicinity of Tikamgarh City at a distance of 12.8 km. The town does not have any historical significance in particular.

9. Jeron Khalsa: Jeron Khalsa is a town and Nagar Parishad located in Tikamgarh district of Madhya Pradesh state. It is about 54 kms from the district headquarters Tikamgarh. In the ancient times, Jeron Khalsa was known by the name “Kashi Ka Tukda”. Radha Krishna temple, Khedapati mandir, Achrumata mandir, Neelkanth mandir are some nearby religious places to visit in Jeron Khalsa.

10. Lidhorakhas: Lidhorakhasis a town and Nagar Parishad located in Tikamgarh district of Madhya Pradesh state. It is about 40 kms from the district headquarters Tikamgarh. It belongs to sub-district. The town is of no ancient significance. Bhopal is the state capital, which is about 305 km far from here.

Figure 1: MP State Map with subprojects local towns

4

B. Existing Water Supply Situation

1. Kari

11. Water Supply is one of the important municipal services. The level of service for water supply has been assessed for source of water supply, quality of water, quantity of water, storage facilities, etc. as detailed out to the subsequent section. Presently the total water supply in the town is 0.41 mld through tube well.

12. The ground water is the main source of water for the town. The piped water is supplied through 2 tube wells. In addition to this, wells and hand pumps are other sources of water in the town. The water table in the area is going down years to years, due to which discharge of existing tube wells is going reduced. Table 1: Details of existing water source & system S. Ground Source Particulars Details No. 1. No. of Tube wells 2 nos. (working) 2. No. of Hand pumps 63 nos. 3. No. of GSRs 01 no. 1 Lakh Litre (not in good condition) 4. Per Capita Supply 32 LPCD considering losses. Source: Nagar Parishad Kari

10. The piped water is supplied directly from pumps through pipeline (5km). The entire Kari is being supplied from ground water source and has coverage of 40% of town area by distribution system. The present distribution system is with AC pipes having 80 mm to 100 mm diameter. Table 2: Details of existing Distribution system Rising main details Distribution network details 150 mm CI Pipe 80 mm to 100 mm AC Pipe

2. Jeron Khalsa

11. The ground water is the main source of water for the town. There are 7 nos. of tube wells in the town. The ground water map of Madhya Pradesh indicates that ground water table is declining in the district. The present water supply rate in Jeron Khalsa is 0.28 MLD @ 30 LPCD considering transmission losses. At present, water is supplied to an existing OHT of capacity 312 KL having staging height 4.6 m and then distributed to certain areas of the town through existing 12.0 km long AC pipeline having dia. 80 mm - 100 mm. This distribution line was laid about 35 years ago and is in poor condition. This pipeline has gone underneath the ground and also there are leakages at many points. Hence, this distribution line is not considered in this scheme. In the remaining parts of the town where distribution line is not laid, water is supplied through tractor tankers. Apart from tube wells, hand pumps are other source of water supply. About 100 hand pumps exists across the town.

5

Table 3: Details of water source & system S. No. Ground Source Particulars Details

1. OHT 312 KL; 4.6 m staging

2. Distribution System Length 12000 m, Dia. 80-100 mm Ac pipes, these pipes are dilapidated and below ground approximately 10 feet hence discarded. 3. No. of Tube wells 7 nos.; 4 are working

4. No. of Hand pumps 100 nos. (most of them gets dry during summer season) 5. Per Capita Supply 0.28 @ 30 LPCD considering losses.

Source: Nagar Parishad Jeron Khalsa

12. At present, water is drawn from 7 municipal tube wells located across the town. Each bore well is fitted with 20 HP submersible pumps. Apart from these tube wells about100 hand pumps exists across the town. Most of these hand pumps gets dry during summer season.

13. At present, there is only 1 Over Head Tank (OHT) of capacity of 312KL and staging height 4.6 m is constructed on hillock in ward no. 1. It is structurally good and has been considered in this scheme.

14. The piped water is supplied directly from pumps through 12 km long AC pipeline having dia. 80 mm - 100 mm. The entire Jeron Khalsa is being supplied from ground water source and has coverage of 50% of town area by distribution system.

3. Lidhora khas

15. The ground water is the main source of water for the town. There are 6 nos. of tube wells in the town. The ground water map of Madhya Pradesh indicates that ground water table is declining in the district. The present water supply rate in Lidhorakhas is 0.40 MLD @ 28 LPCD. At present, water is supplied through the tube wells to an existing 150 KL OHT of 10 m height and then distributed to certain areas of the town through existing AC distribution pipeline having dia. 80 mm - 100 mm. This pipeline is in poor condition and has been discarded in this scheme. Apart from tube wells, tractor tankers and hand pumps are other sources of water supply. About 235 hand pumps exist in Lidhorakhas. During summer, town faces acute drinking water scarcity.

16. At present, water is drawn from 6 nos. of municipal tube wells located across the town. Each tube well is fitted with 20 HP submersible pumps. Apart from these tube wells, an about 235 hand pump exists across the town. Most of these hand pumps gets dry during summer season.

C. Proposed Project

17. As the water table is depleting all over, therefore, now it is not a reliable source for a permanent scheme in all the towns. As part of this project, it is proposed to develop comprehensive water supply schemes in the project towns. A separate scheme for Kari town, and a combined water supply scheme for Jeron Khalsa and Lidhorakhas towns proposed

6

considering the techno economic feasibility. Proposals include new reliable water sources, water treatment plants, overhead tanks, energy efficient pumping machinery, raw & clear water transmission mains and distribution network covering the whole town. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency.

18. Following Table 4 shows the proposed water supply systems along with nature and size of components in subproject towns. Figure 2 to Figure 8 show the proposed water systems, component layouts etc. 7

Table 4: Proposed Water Supply Subproject Components S. No. Particulars Kari Jeron Khalsa Lidhorakhas i. Water demand i. Water demand 1 Commissioning 0.98 MLD 2.07 MLD Year (2020) 2 Intermediate 1.25 MLD 2.56 MLD year (2035) 3 Design year 1.56 MLD 2.98 MLD (2050) ii. Source ii. Source 1 Alternatives 1. Ground Water 1. Ground Water 1. Ground Water

2. Jamni River 2. Jamni River 2. Jamni River 3. Deep Sagar pond 2 Selected Jamni River Jamni River Jamni River source iii. Proposed System iii. Proposed System 1 From source Raw water abstraction from Jamni Common water supply scheme for tows of Jeron Khalsa and Lidhorakhas to consumer river → raw water transmission Raw water abstraction from Jamni river → raw water transmission supply (pumping) → treatment → clear water (pumping) → treatment → clear water transmission (pumping) → storage transmission (pumping) → storage → → distribution → house connections with meters distribution → house connections with meters iv. Proposed Components iv. Proposed Components 1 Weir / water Weir: 160 m long and 3.5 m height Rehabilitation and increase of height of existing weir across Jamni River intake across Jamni River is proposed for near Milanghat storing 0.70 MCM of raw water for the -Repair and rehabilitation to meet its functional requirements. 8 month requirement of the town -Increasing height of existing weir by 1.5 m, from 3.0 m to 4.5 m

-Intake well: 6m diameter and 10.8 m height, in the bank of Jamni River Intake well: 6m diameter and 14.37 m near Bajrangarh, height RCC well to collect and lift

water up to treatment works. In the bank of Jamni River 8

2 Raw water 10850 m long 150 mm dia. DI K9 from 950 m long 250 mm dia. DI K9 from proposed Intake well to proposed Rising Main proposed Intake well to proposed WTP. WTP.

3 Water Capacity 1.70 MLD considering 22 Capacity 3.25 MLD considering 22 hour pumping Treatment hour pumping. Plant (WTP) Process/components (same for all Process/components (same for all towns): Coagulation & flocculation, towns): Coagulation & flocculation, sedimentation, rapid gravity filtration, chlorination, wash water recovery, sedimentation, rapid gravity filtration, sludge drying beds, tube settlers, Laboratory& miscellaneous infra chlorination, wash water recovery, (compound wall, landscaping, lighting, rest rooms etc) sludge drying beds, tube settlers, Laboratory& miscellaneous infra (compound wall, landscaping, lighting, rest rooms etc) Location: On a government land Location: On a government land 4 Reservoirs 3 Ground level service reservoirs One overhead tank (OHT) of 100 KL Two OHTs with 15 m staging (GLSRs) capacity with 5 m staging height. height. GSR-1 - 110 KL capacity in Ward No. Location: In ward no. 5 on a OHT-1 200 KL: Ward no. 09 10 government land. OHT-2 200 KL: Ward no. 03 GSR-2 - 170 KL capacity in Ward No. All the OHTs proposed in 07 government land. GSR-3 - 200 KL capacity in Ward No. 13 All the three GSRs proposed on Government Land 5 Clear water 1841 m long and 100 to 150 mm DI K- 13,825 m long and 100 to 250 mm DI 25,846 m long and 100 to 150 mm transmission 9 pipe. K-9 pipe. DI K-9 pipe. Location: Transmission pipelines will Diameter Length(m) Pipe Diameter Length Pipe be mostly laid along the main roads (mm) Material (mm) (m) material from WTP to reservoirs. Pipes will be 100 254 DI K-9 100 253 DI K-9 laid underground. 150 1022 DI K-9 150 2107 DI K-9 9

200 7776 DI K-9 200 23486 DI K-9 250 4773 DI K-9 TOTAL 25846 m TOTAL 13825 m Location: Transmission pipelines will be mostly laid along the main Location: Transmission pipelines will roads. Pipes will be laid be mostly laid along the main roads. underground. Pipes will be laid underground. 6 Distribution 31,743 m length of diameter 110 mm 48,970 m length of diameter 110 mm 20,285 m length of diameter 110 network to 250 mm HDPE PN 10 pipe. to 250 mm HDPE PN 10 pipe. mm to 250 mm HDPE PN 10 pipe. Pipe Dia. (mm) Length (m) Pipe Dia. Length Pipe Dia. Length 110 28769 (mm) (m) (mm) (m) 140 1085 110 42644 110 17945 160 1322 140 580 180 116 140 2445 160 521 200 450 160 1319 180 416 Total 31743 180 362 200 690 Location: Along the public roads in the 250 132 entire town 200 281 Total 20285 250 1919 Location: Along the public roads in Total 48970 the entire town. Location: Along the public roads in the entire town. 7 Bulk flow Electromagnetic Bulk flow meter will be installed to monitor the bulk flow in Electromagnetic Bulk flow meter will meters the main components i.e. at the inlet of the raw water mains to know the be installed to monitor the bulk flow in quantity of water coming to the WTP, outlet of the clear water sump to the main components i.e. at the inlet know the quantity of water going for the distribution, outlet of the service of the raw water mains to know the reservoirs to know the quantity of water going in the distribution zone or quantity of water coming to the WTP, DMA. This will help in maintaining the UFW in the limit and also equitable outlet of the clear water sump to know distribution of the water. the quantity of water going for the distribution, outlet of the service reservoirs to know the quantity of water going in the distribution zone or DMA. This will help in maintaining the

10

UFW in the limit and also equitable distribution of the water. 8 House Domestic: 1120 Domestic: 905 Domestic: 1497 Connection Non-domestic: 50 11

Figure 2: Key Plan of Jeron Khalsa and Lidhorakhas Group WSS

12

Figure 3: Google Map Showing Proposed Group WSS Components in Lidhora Khas & Jeron Khalsa Towns

13

Figure 4: Google Map Showing Proposed WSS Components in Lidhora Khas Town

14

Figure 5: Google Map Showing Proposed WSS Components in Jeron Khalsa Town 15

Figure 6: Key Plan of Kari WSS

16

Figure 7: Google Map Showing Proposed WSS Components in Kari Town Source to OHTs

17

Figure 8: Google Map Showing Proposed WSS Components in Kari Town

18

III. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

19. ADB requires the consideration of environmental issues in all aspects of ADB’s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments. “MPUDC/PMU will adhere to necessary protocols in response to emerging infectious diseases such as the corona virus disease, 2019 (COVID-19) consistent with the guidelines of relevant government healthcare agencies and the World Health Organization. “

20. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

21. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

22. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) Environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws

23. Environmental Assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC 19 must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject.

24. Applicable environmental regulations. Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 5. Table 5: Applicable Environmental Regulations Law Description Requirement Madhya Pradesh Prepared in accordance with the National Water Permission of WRD, State Water Policy, it states that “for environmental balance, GoMP: Policy, 2003 skillful and planned management of all types of • Construction of Weir developmental activities, economic use on and Intake well on equitable basis and in view of the prime Jamni River for Kari importance of water for all human and other living town at Aamghat. beings, an effective and sound water policy is • Rehabilitation and necessary”. repair work on Policy is detailed in 17 sections dealing with existing weir at different aspects of water resources. No. 7 deals Milanghat for Group with Water Allocation Priorities, and according to Water supply scheme which drinking water supply shall have the highest of Jeron Khalsa and priority followed by irrigation, power, tourism, etc. Lidhora khas towns Water Resource Department is nodal department Application have been for permitting different uses of water resources. submitted to the WRD Policy also states that “clear provision for reservation of drinking water shall be made in irrigation projects” Water (Prevention Act was enacted to provide for the prevention and MPPCB consent for WTP and Control of control of water pollution and the maintaining or will be obtained during Pollution) Act of restoring of wholesomeness of water, by Central detailed design phase, 1974, Rules of and State Pollution Control Boards and for prior to start of 1975, and conferring and assigning to CPCB/SPCBs powers construction and CFO amendments &functions relating to water pollution control. (prior to start of operation) from MPPCB. Control of water pollution is achieved through administering conditions imposed in consent Application has to be issued under to this Act. These conditions submitted online at regulate the quantity and quantity of effluent, the http://www.mppcb.nic.in/x location of discharge and the frequency of gn.html monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution

20

Law Description Requirement Control Board (MPPCB) Environment Emissions and discharges from the facilities to be Appendix 2 provides (Protection) Act, created or refurbished or augmented shall comply applicable standards for 1986 and CPCB with the notified standards ambient air quality. Environmental Appendix 3 provides Standards. vehicular emission norms

Noise Pollution Rule 3 of the Act specifies ambient air quality Appendix4 provides (Regulation and standards in respect of noise for different applicable noise Control) Rules, areas/zones. standards. 2000 amended up to 2010. Municipal Solid Rules to manage municipal solid waste Solid waste generated at Wastes generated; provides rules for segregation, proposed facilities shall be Management storage, collection, processing and disposal. managed and disposed in Rules, 2016 accordance with the MSWM Rules Construction & Rules to manage construction & to waste resulting Construction & demolition Demolition Waste from construction, remodeling, repair and waste generated from the Management demolition of any civil structure. Rules define C&D project construction shall Rules, 2016 waste as waste comprising of building materials, be managed and debris resulting from construction, re-modeling, disposed as per the rules repair and demolition of any civil structure. (Appendix 6) Forest Act, 1927 Acts empower the government to declare forest None of the project and Forest area (reserve, protected and village forest area) components comes under (Conservation) and regulation of activities within the forests. Use forest area. Act, 1980, of forest land for any non- forest purpose and amended 1988 forest land conservation will follow the guidelines for “Diversion of forest lands for non-forest purpose” under Forest (Conservation) Act 1980 Labor Laws The contractor shall not make employment Appendix 7 provides decisions based upon personal characteristics applicable labor laws unrelated to job requirements. The contractor including amendments shall base the employment relationship upon issued from time to time equal opportunity and fair treatment, and shall not applicable to discriminate with respect to aspects of the establishments engaged employment relationship, including recruitment in construction of civil and hiring, compensation (including wages and works. benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

25. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized 21 standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines1 and Sector Specific [Water and Sanitation] Guidelines)2 These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below: Table 6: WHO Ambient Air& Noise Quality Guidelines

1 https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 2 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

22

IV. DESCRIPTION OF THE ENVIRONMENT

A. Methodology Used for Baseline Study

26. Data collection and stakeholder consultations. Focused Group Discussion, field visits, site surveys and social surveys were conducted through the different wards covering every section of society was conducted and data collected and analyzed accordingly with respect to the proposed subproject sites and the with respect to the need of water supply in all the six towns here.

27. The survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical experts of design consultant team. (ii) Discussions with technical experts, municipal authorities and relevant government agencies like WRD, Revenue Department, Forest Department, MPPCB, etc. (iii) Secondary data from previous project reports & published articles, if any, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic, and planning documents collected from Government agencies and websites.

28. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Baseline Environmental Profile

29. Following table 7, details presents the baseline environmental profile of subproject towns of Package 6H. It is organized in terms of physical, ecological, economical, and socio-cultural resources.

23

Table 7: Baseline Environmental Profile of towns Baseline Kari Jeron Khalsa Lidhorakhas characteristic Location Kari town of Tikamgarh district is located Jeron Khalsa is located about 54 km Lidhorakhas is located in Tikamgarh in the northern part of Madhya Pradesh. from the district headquarters District in the north east direction of the It lies on the plateau Tikamgarh. It is located at co-ordinates state. It is located at co-ordinates between the Jamni, a tributary of Betwa 2507’17” N & 780 39’7” E. 2504’25” N & 780 52’05” E. and Dhasan rivers. The city is located at 24°50' N latitude and 78°52' E longitudes at an altitude of 337 m above mean sea level. The town is bounded by district to the east, Lalitpur district () to West, to North and Sagar to South. The Western and Eastern boundaries are formed by two big rivers. Connectivity Roads play a significant role in linking Jeron Khalsa is linked to other areas by Lidhorakhas is linked to other areas by Kari to other towns and cities in the road network only. The nearest railway road network only. The nearest railway country. The State Highway No. 37 station is Niwari, which is nearly 38 km station is Niwari, which is nearly 44 km connects the town with Tikamgarh city from the town and accessible via road from the town and accessible via road and nearby towns. The town is connected network. The nearest airport is network. The nearest airport is Khajuraho to via this route only. The Khajuraho airport, which has daily flights airport, which has daily flights to and from distance from Kari to Tikamgarh City is to and from the National Capital. the National Capital. Chhatarpur, 12.8 km and 299 km far from the state Chhatarpur, Tikamgarh, Jhansi and Tikamgarh, Jhansi and Sagar are the capital Bhopal. Sagar are the nearby Cities to Jeron nearby Cities to Lidhorakhas. The town is not connected by Railway. Khalsa. Lalitpur railway station is the nearest railway station from the Kari. Area & The area of the town is spread over in 8.8 The area of the town is spread over in Lidhorakhas Nagar Parishad (GNP) Population Sq Km as per 2011 data and mainly 17 Sq Km as per 2011. As per census comprises 15 wards having an area of 32 divided in 15 wards. Population of town data of 2011, the total population of the sq. km. The study area covers within the as per 2011 census was 10409. town is 9426. Nagar Parishad limits. Population of town as per 2011 census was 12978. Topography • The town is situated on a flat terrain The topography of the town is mainly The topography of the town is having flat slope. The town normally 24

Baseline Kari Jeron Khalsa Lidhorakhas characteristic slopes towards eastern side. Storm hilly. Main settlement is surrounded by undulating. Storm water through water easily percolates into ground due hillocks. The general slop of Jeron natural slope and a natural Kucha to good permeability of soil. Kari and its Khalsa is towards South-West and all Nallah passes by the Bhuteshwer hinterland are located at an elevation of the storm water collects into the local Temple and drains into agricultural 300.450 m mean sea level. drains /Nallahs which eventually drains fields.There are two major Nallahs in • Town naturally drains towards the pond into Sanera Taal, River Jamini and the town, which originates from the in eastern side of town in the fields some water bodies in the town. The western part of the town and then however there no Proper drainage main reason for this is the topography flows towards east and to the outer system in town. Storm water is drained of the town which is mainly hilly. The areas of the town. The major nallah is naturally towards east direction. growth of the town is restricted by a hill one which flows from eastern • Kari and its hinterland are situated on located at the south side of the main periphery near the temple and PHC to Pleistocene Geological formations. The town and a water body at the North- east. The other major Nallah flows Pleistocene is the geological epoch west of the town. Storm water easily from area near bus stand and flows to which lasted from about 2,588,000 to percolates into ground due to good the Chopdain front of the fort 11,700 years ago spanning the world's permeability of soil. Jeron Khalsa town recent period of repeated glaciations and its hinterland is located at an elevation of 288 m above mean sea level. Soils & The lands of Kari primarily hold mixed red The soil in Jeron Khalsa is mixed red The soil in Lidhorakhas is mixed red and geology and black type soils, falling under the and deep black soil. It supports deep black soil. It supports agriculture. world soil classification of Brown earths. agriculture. The geology of the area is The geology of the area is characterized Kari and its hinterland are situated on characterized by what is known as the by what is known as the Bundelkhand Pleistocene Geological formations. The Bundelkhand Gneiss in geological Gneiss in geological terms. The Pleistocene is the geological epoch which terms. The Bundelkhand Gneiss is a Bundelkhand Gneiss is a hard greyish lasted from about 2,588,000 to 11,700 hard greyish pink granitoid rock of pink granitoid rock of simple composition, years ago spanning the world's recent simple composition, which is traversed which is traversed by conspicuous quartz period of repeated glaciations by conspicuous quartz fields that are fields that are integral part of this integral part of this formation. These formation. These rocks are found in the rocks are found in the form of sheets form of sheets and dykes across the and dykes across the district. district. Climate Like other part of India, it has three major Like other part of India, it has three Like other part of India, it has three major seasons: Summer, Manson, Winter but major seasons: Summer, Manson, seasons: Summer, Manson, Winter but 25

Baseline Kari Jeron Khalsa Lidhorakhas characteristic duration varies. Winter but duration varies. duration varies. Temperature: During Summer (March- Temperature: During Summer (March- Temperature: During Summer (March- June) the temperate in the town is above June) the temperate in the town is above June) the temperate in the town is above 22°C. The Humidity is relatively very low 17°C. The Humidity is relatively very low 15°C. The Humidity is relatively very low May was the hottest month of Kari during In Jeron Khalsa town, the recorded In Lidhorakhas town, the recorded period 2006-10. Mean Maximum minimum and maximum temperature minimum and maximum temperature Temperature during this month was throughout the year are 3.80 C and 450 throughout the year are 3.80 C and 450 C 41.02 °C. Coldest month was January C receptively. receptively. during 2006-10, mean minimum temperature in this month during the Rainfall: The average rainfall in Jeron Rainfall: The average rainfall in period was 3.81 °C. The normal Khalsa is approximately 844 mm. The Lidhorakhas is approximately 844 mm. maximum temperature received during rains usually break in the month of June, The rains usually break in the month of the month of May is 41.8° C and with the maximum number of rainy days June, with the maximum number of rainy minimum during the month of January is experienced during the months of July days experienced during the months of 7.0°C. The normal annual means and August. July and August maximum and minimum temperatures of Tikamgarh district are 32.4°C & 17.5°C Wind Direction: Average wind speed is Wind Direction: Average wind speed is respectively. 4.1 km per hour. Maximum wind speed 4.1 km per hour. Maximum wind speed is is during May- June and minimum wind during May- June and minimum wind Rainfall: The average rainfall in Kari is speed is during December- January. speed is during December- January. approx. 840 mm. The rains usually break Seasonal wind direction in the are as Seasonal wind direction in the are as in the month of mid-June, with the follows: follows: maximum number of rainy days Summer- West to East Summer- West to East experienced during the months of July Rainy- South West to North West Rainy- South West to North West and august. Winter- North East to South West Winter- North East to South West

Wind Direction: The wind velocity is higher during the pre-Manson period as compared to post Manson period. The max. wind velocity is 9.3km/h observed during the month of December. The average normal annual wind velocity of Tikamgarh district is 5.6Km/hr.

26

Baseline Kari Jeron Khalsa Lidhorakhas characteristic Surface water Deep Sagar Pond: Deepsagar Talab is Sanera Taal: Sanera Taal is located in Madera Talab: Madera Talab is located located in Ward No. 11, having front of ULB Office Jeron Khalsa. It is in Ward no. 05 & ward no. 06.Total area catchment area approx. 80 ha. It is used spread over an area of approx. 800 of Madera Talab is about 4.935 hectare for irrigation of the surrounding hectares owned by Irrigation owned by Nagar Parishad Lidhora Khas agricultural fields. It never gets filled up to Department, GoMP. Pond water is under survey no. 867.No utilization of full reservoir level. Most of the Kari storm mostly utilized for irrigation of pond water as a source of water supply water naturally drains towards east side surrounding agricultural fields. There is or irrigation. Madera Talab almost run dry in Deepsagar Talab. A major no fishing in this pond. Pond water is not during summer season. environmental issue for the town relates used for drinking purposes. to the pollution of water bodies. Lacking a Goyra Talab: Goyra Talab is located in proper waste management mechanism, Old Chandeli Talab: Old Chandeli Ward no. 03. Total area of Goyra Talab is in Kari collected garbage and sewerage Talab is located in in ward no.5, Jeron about 42.378 hectare owned by Nagar being dumped along the water bodies. Khalsa. It is spread over an area of Parishad Lidhora Khas under survey no. This not only leads to severe pollution of approx. 50 hectares owned by Nagar 1306.No utilization of pond water as a water bodies but also leads Parishad Jeron Khalsa. Pond almost run source of water supply or irrigation. contamination of ground water in long dry throughout the year. No utilization of Madera Talab almost run dry during run. The ponds which are also one of the this pond. summer season. landscaping elements in the town can be Jamni River: Jamni river is about 2.5 Dudhera Stop Dam: It is located in ward conserved as the town recreational km far from Jeron Khalsa. There is a no. 1 near Bhuteshwer temple. It is a spaces. These ponds can be beautified 285 m long and 3.5 m high existing weir small stop dam for collecting rainy landscaped and can be developed as built by WRD on the bank of Jamni river water.There are two major Nallahsin the major attractions for the town. As per the near milanghat.. town, which originates from the western information available from various part of the town and then flows towards sources and discussions with concerned east and to the outer areas of the town. officials the water quality as per the The major nallah is one which flows from standards is not fit and sufficient for eastern periphery near the drinking. Bhuteshwertemple and PHC to east. The other major Nallah flows from area near Baodi Talab: Baodi Talab is located out of municipal boundary of Kari town near Jamni river is about 2.5 km far from Jeron ward no. 1. It is also used for irrigation Khalsa. purposes of the surrounding fields. Half 27

Baseline Kari Jeron Khalsa Lidhorakhas characteristic of the Kari storm water and sewage naturally drains towards west side in Baodi Talab. Lacking a proper waste management mechanism, collected garbage and sewage being dumped along the water bodies. This not only leads to severe pollution of water bodies but also leads contamination of ground water in long run. As per the information available from various sources and discussions with concerned officials the water quality as per the standards is not fit and sufficient for drinking.

Jamni River: River Jamni flows about 11.50 km away from the town Kari. Jamni River which originates in the district of Sagar in Madhya Pradesh is primarily rain fed and Ephemeral River.As a result, it swells up during the monsoon season and the water level falls down during the summer months. It is one of the important sources of water in the dry areas of Bundelkhand region of Madhya Pradesh. It is a main tributary of the Betwa River and enters Lalitpur District near Madanpur village. This inter-state river flows through Sagar in Madhya Pradesh to enter the district of Lalitpur in Uttar Pradesh and finally crosses over to Tikamgarh again in Madhya Pradesh and meets the Betwa near the town of .It cuts through Sagar to enter the district of Lalitpur flowing through the forest near the village of Madapur and flows northward direction for the next 45 km and then takes north-easterly bend or turns to the north-east for 6km after leaving the town of Mahroni on the right. For the next 60 km, the river forms the boundary of the district and receives all the west-bound drain of the Tikamgarh district. It finally meets Betwa within Tikamgarh district only The confluence of Jamni and Betwa is at the historical town of Orchha. The Jamni takes care of the irrigation of a large area in this district. Jamni has been dammed with Lalitpur district. Total catchment area in Madhya Pradesh is 1235 km² and total length is 201 km. In Madhya Pradesh the river flows for 29 km, for 85 km river makes boundary between Madhya Pradesh and Uttar Pradesh and last 87 km flows in Uttar Pradesh

Important Tributaries of Jamini River are Sajnam, Shahzad and Bargi Rivers. While Sajnam joins it at Chandrawali, Shazad joins it near Hazira village and Bargi river joins it near Bajrangarh. These streams drains enormous volume of water during rains while in other seasons they shrink to narrow channel.

28

Baseline Kari Jeron Khalsa Lidhorakhas characteristic

Shahzad an important river flowing by the side of Lalitpur town, has been dammed to make Gobind Sagar reservoir near Lalitpur. Shahzad Dam is located in the outskirts of Lalitpur in Uttar Pradesh. Built in 1992 across the Shahzad River, a tributary of the Jamini River, this dam is a major source for irrigation in Lalitpur District. A main canal of 44 km has been constructed to provide irrigation. It took about 19 years for the completion of this dam. 18 m high and 4160 m long, Shahzad Dam is a major tourist attraction in the region. The famous Govind Sagar Dam is the nearby attraction.

Sajnam has been dammed in Lalitpur district. Sajnam Dam, 13 m high, is constructed across the River Sajnam, a tributary of the Jamni. Situated close to Chandawali in Lalitpur District, this dam is a major irrigation source for the people in this region. Built in 1990, the dam has a length of 4525 m and comes under the earthen group of dams. In order to provide irrigation to about 50 km, a major canal of 38 km has been constructed by the government of Uttar Pradesh. Shahzad Dam is the nearby attraction. The nearest airport is at Gwalior.

Bargi river flowing by the side of Tikamgarh district from Nadanwada Bhata from Nadanwara Talab approx. 5 km away from Lidhora Khas town and meets Jamni River at Bajrangarh just about a distance of 200 m away on upstream side of common weir site proposed for Jeron Khalsa and Lidhora Khas towns WSS. Nandanwara Talab in Jatara tahsil, created by placing a small dam across Bargi river as it passes through two hills, is also built by Bir Singh Dev. In its vastness, Nandanwara is said to be second only to the Bada Talab of Bhopal.

Ground Water Dynamic ground water resources of the Water supply in Jeron Khalsa is based Water supply in Lidhorakhas is based on district have been estimated for base on ground water. There are 7 tube wells ground water. There are 6 tube wells in year -2008/09 on block-wise basis. There in the town out of which 4 in working the town out of which 4 in working are eight number of assessment units condition. Water is drawn from these condition. Water is drawn from these tube (block) in the district which fall under tube wells. Water supply to the is made wells. Water supply to the is made by none-command (96%) and command by these tubes well located at different these tubes well located at different part (3%) sub units. All blocks of the district in part of city. Present water supply rate is of city. Present water supply rate is 0.4 command area are categorized as safe 0.28 MLD at the rate of 30 LPCD. Yield MLD at the rate of 28 LPCD. Yield of blocks. , Gaurihar and Loundi of these tube well reduced considerably these tube well reduced considerably blocks in non-command sub units are during summer. Hence ground water during summer. Hence ground water safe. Badamalhara, , source is not suitable. As per hydro source is not suitable. As per hydro Chhatarpur, Nowgaon and Rajnagar are geomorphologic map of the area is geomorphologic map of the area is under semi critical highest stage of prepared by National remote sensing prepared by National remote sensing 29

Baseline Kari Jeron Khalsa Lidhorakhas characteristic ground water development is computed Agency, department of space gov. of Agency, department of space gov. of as 93 % for Chhatarpur Block. The net India, Hyderabad, the recharge condition India, Hyderabad, the recharge condition ground water availability in the district in the area is moderate. Rocks are in the area is moderate. Rocks are 68,567 hacm and ground water draft for plateau weather type. plateau weather type. all uses is 45,054.66 ham, making stage of ground water development 66 % as a Ground Water Quality: Groundwater Ground Water Quality: Groundwater whole for district. quality in Tikamgarh district is accessed quality in Tikamgarh district is accessed annually by CGWB on the basis of annually by CGWB on the basis of Quality of Ground Water for Drinking samples collected from 14 numbers of samples collected from 14 numbers of Purpose: The pH value of water samples hydrograph stations in the district. On hydrograph stations in the district. On the shows slight alkaline in nature and within the basis of examination of data for the basis of examination of data for the year permissible limit (6.5 to 8.5) as described year 2011, the water quality is described 2011, the water quality is described as by BIS (1991). The salinity of the water is as follows. The Electrical Conductivity follows. The Electrical Conductivity represented by the electrical conductivity. ranges from 713 to 2040 micromhos per ranges from 713 to 2040 micromhos per The electrical conductivity depends upon cm at 25°C. The fluoride ranges from cm at 25°C. The fluoride ranges from the concentration of dissolved inorganic 0.26 mg/l to 0.82 mg/l. The nitrate 0.26 mg/l to 0.82 mg/l. The nitrate ranges salts in the water. The EC values in ranges from 0.75 mg/l to 212 mg/l from 0.75 mg/l to 212 mg/l district were within BIS limit (1000 μS/cm2) and found to be in the ranges between 375 - 2160 μS/cm2 at 25°CThe concentration of NO3 The nitrate concentration in the district ranges 2 to 288 mg/l. The fluoride concentration in the district ranges between 0.14 to 1.78 mg/l. There is no problem of excess fluoride in the shallow ground water of the district. As per the Dynamic Ground Water Resource Assessment (2013), the net ground water availability in the district is 521.72 MCM and ground water draft for all uses is 380.58 MCM, resulting the stage of ground water development to 72.95% as a whole. The Tikamgarh

30

Baseline Kari Jeron Khalsa Lidhorakhas characteristic district falls under semi critical category. 5 semi critical out of 6 Blocks having stage of development ranging between 70.62% in Jatara to 81.11% in Tikamgarh block. block falls under Safe category having stage of development 56.21 %. . Air Quality There is no data on ambient air quality in project towns, which are not subject to monitoring by the Madhya Pradesh Pollution Control Board (MPPCB) as there are no major industries. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. Ecological Lidhorakhas and Jeron Khalsa: There is no forest within the 10 km of project area. Kotigulenda Reserve Forest is located at about 20 km from the Jeron Khalsa on the South-east direction, which is a dense mix forest mainly teak. Nathikhear Reserve forest is located about 15 Km from the Jeron Khalsa town, it is a fairly mix forest mainly Khair. Kari: There is a Forest area touching the boundary of Ward 07 of Kari Nagar Parishad which is known as Paniyara Khera Reserved Forest under the Belgaon Beat which is Beat No. P-35, C-34. None of the proposed components of Kari town WSS are located in the forest area or in forest land. All the proposed component is located on government owned barren lands within the municipal area of Kari Nagar Parishad which are not comes under Paniyara Khera Reserved forest. Flora: The forest cover around Paniyara Khera Reserved Forest is mainly classified as southern tropical dry deciduous forest and is fairly dense forest. The Paniyara Khera Reserved Forest has teak and Kardhi as prime species growing with other species like haldu, Sejna, Arjun, Saja, Bija, Kasi, Reunjha, Shisham, Tendu, Palas, Khair, Achar and Mahua. Among trees, Palash, Bel, Kewnch, Ratti, Ghunchi, and Satawar are commonly seen. Fauna: In the Paniyara Khera Reserved Forest the fauna comprises spotted deer, Blue bull, Peacock, Wild pig, Monkey, Jackal, rabbit etc. Besides these, bovine population is also adequately distributed in the region. Economic The major economic activities in the town The city has a mixed economy based on Lidhorakhas has 37% (4835) population development a agriculture and farming. As per 2011 engaged in either main or marginal re agriculture and trade/comers. Kari is census, the total working population of works. 50% male and 24% female Land use an important market for sale and main workers is 45.6 % of the total population are working population. 46% purchase of agricultural products in the population. of total male population is main (full time) Agriculture & region. Kari's hinterland has developed workers and 4% are marginal (part time) industry rich agriculture productivity. Main crops workers. For women 17% of total female 31

Baseline Kari Jeron Khalsa Lidhorakhas characteristic grown in town is Soya bean and Til. population is main and 7% are marginal Kari is a popular town in the region workers. Farming is the main occupation. famous for its market area or bazaar. People from surrounding areas come to Kari for shopping for daily needs household and other items. There are around 50 HH involved in the Bidi making mostly employing women and girls are in this business. Small retails shops also existed on the main road along State Highway. Sewerage, Towns naturally drains towards the pond Drainage System: There are no Drainage System: If we talk about sanitation & in eastern side of the town in the fields, major Nallahs in the town. The town storm water,road side drains serve drainage however there is no proper drainage has drain along the roads that carry the purpose. Otherwise storm water system in the town. Storm water is storm water through. The water through natural slope and a natural drained naturally towards east direction. flows through few small channels Kucha Nallah passes by the As far as drainage system of the city is and meets the Sanera Taal and Bhutesher Temple (It’s a beautiful concerned, there are number of small some water bodies in the town. The ancient temple, it needs to be water channel that discharge run off from main reason for this is the conserved and can further be the surrounding areas. The town does topography of the town which is developed as a picnic spot) and not have an effective drainage system. mainly hilly. The growth of the town drains into agricultural fields. Water Kari storm water naturally drains towards is restricted by a hill located at the from road side drains ultimately east side in Deepsagar Talab and half of south side of the main town and a drains into main nallah and then the city water drains towards west side in water body at the North-west of the augments in Chopda in front of the Baodi Talab. Natural drainage system is town.Main settlement is surrounded fort (This is an old fort called as very efficient due to more than gentle by hillocks, thus at the time of rains, LidhoraKhas fort constructed by slope. the soil drains off and gets collected Maharaj Hate Singh. It still stands in Sewerage System: At present there is no into the road side drains and block a good condition. Presently, a school sewage system in the town. The sewer them. The storm water flows into is operable in here and being used finds its way into the drains and finally Sanera Taal and Jamini River. The as school building, which damages goes into the water bodies and Nallahs, general slop of Jeron Khalsa is the structure and thus, it needs to be thus polluting them. This also leads towards South-West and all the conserved). It is under the jurisdiction unhygienic conditions and unhealthy storm water collects into the local

32

Baseline Kari Jeron Khalsa Lidhorakhas characteristic environment in the town. The untreated drains /Nallahs which eventually of LidhoraKhas Nagar Parishad. or semi treated sewage is disposed into drains into River Jamni. Filthy There are two major Nallahsin the the storm water drains especially in the Nallahs / drains run across almost town, which originates from the core area of the town. Most of the houses whole length and breadth of the western part of the town and then in the town have their own flush type town, thus contributing to unhygienic flows towards east and to the outer latrine with septic tank system. There is living condition. According ULB areas of the town. The major nallah no treatment for grey water discharged length of drains present in the town is one which flows from eastern from kitchens. This water is disposed in is about 13.2 km.It was observed periphery near the temple and PHC open fields or ponds. Due to absence of that in most of the areas local to east. The other major Nallah flows sewage system, city is facing various residents dump their household from area near bus stand and flows problems such as open defection, waste in the drains contributing to to the Chopda. The majority length of unhygienic conditions etc. as the chocking of nallahs during monsoon. the nallah is kutcha. residents drain effluents into open The maintenance is poor and at It was observed that in most of the areas grounds or streets. some places, smaller nallahs have local residents dump their household been encroached upon. This waste in the drains contributing to prevents cleaning and maintenance chocking of nallahs during monsoon. The of the nallahs causing waterlogging maintenance is poor and at some places, mainly during monsoon. smaller nallahs have been encroached Apart from these, the town has about upon. This prevents cleaning and 13.2 km of storm water road side drains. maintenance of the nallahs causing water Though there is no detailed survey data logging mainly during monsoon. available, but through visual survey it can be noted that storm water drains in Apart from these, the town has about 18 Jeron Khalsa main town are generally km of of storm water road side drains. pucca drains with lesser % of Kuchha Though there is no detailed survey data drains but in the remaining parts almost available, but through visual survey it can 50% of the drains are pucca and 50% of be noted that storm water drains in them are kutcha. LidhoraKhas town are generally pucca drains with lesser % of Kucchha drains Existing Sewerage System: The city but in the remaining parts almost 50% of does not have an underground sewage the drains are pucca and 50% of them system. Also there is no separate are kutcha. 33

Baseline Kari Jeron Khalsa Lidhorakhas characteristic sewerage and storm water network in the city. Due to unavailability of Existing Sewerage System: The city does sewerage lines, households have not have an underground sewage individual septic tanks, over flowsinto system. Household have their individual these road side drains. In the main septic tanks and their overflow drains into settlements, most of the households road side drains, which is not a very have individual toilets whereas in fringe hygienic practice. Areas around lakes areas, most of the household don’t. and at the periphery have very less no. of Sewage is dumped directly without any individual and community toilets and treatment into the lake or and practice open defection majorly.Water surrounding agricultural fields from drain does not flow into lake but depression areas, thereby degrading population from settlements around their quality.Domestic waste generated practice open defection here and hence in the locality flows into the open drains, pollute it. Considering the whole due to the improper gradient and faulty population of the town, less than 40% of design sewage gets accumulated and the households have individual toilets. leads to the water born and viral Also there is no separate sewerage and diseases. Chocking of drains is yet storm water network in the city. In the another problem which can be seen older residential areas, traditional clearly. Apart from the faulty design at methods of sewage disposal are still most of the places, links of open drains practiced. In the newly developed are missing which also aggravates the residential areas, individual septic tanks problem. In the older residential areas, are being constructed but the sewage traditional methods of sewage disposal from the septic tanks is released in the are still practiced. In the newly open drains which results in air pollution developed residential areas, individual and generation of dirt. The general slop septic tanks are being constructed of LidhoraKhas is towards East and all the waste water collects into the local drains /Nallahs which eventually drains

34

Baseline Kari Jeron Khalsa Lidhorakhas characteristic into River Jamini on the downstream of the existing weir Solid waste There is no proper solid waste management system in the towns. Respective municipal councils are responsible for SWM management services in their areas. Waste generated in the towns are collected and disposed by crude open dumping method in the outskirts of the towns. Power supply: Thermal power is the main source of energy in Madhya Pradesh, contributing nearly 90% of the electricity, compared to hydropower, which produces the remainder. Power supply situation. Demographic According to the census, the population Population of the town as per 2011 Lidhora Khas is a Nagar Panchayat city characteristic of Kari was 10409 in 2011, increased census was 9426 increased from 8298 in district of Tikamgarh, Madhya Pradesh. from 8689 in 2001, which shows an in 2001. The Lidhora Khas city is divided into 15 increase of 20 % over the decade. Jeron Khalsa is a Nagar Panchayat city wards for which elections are held every As per 2011 Census, the sex ratio in district of Tikamgarh, Madhya 5 years. The Lidhora Khas Nagar (Female Population pa 1000 Male Pradesh. The Jeron Khalsa city is Panchayat has population of 12,974 of Population) of the town is 901. The sex divided into 15 wards for which elections which 6,704 are males while 6,270 are ratio of the city is more than the State are held every 5 years. The Jeron females as per report released by (898) and district (886) figures. Khalsa Nagar Panchayat has population Census India 2011. According to the Census 2011, the of 9,426 of which 5,027 are males while literacy rate of Kari has been 45 4,399 are females as per report released Population of Children with age of 0-6 is percentage, which is lower than district by Census India 2011. 2040 which is 15.72 % of total population (66%). Population of Children with age of 0-6 is of Lidhora Khas (NP). In Lidhora Khas Schedule Caste (SC) constitutes 19.44 % 1458 which is 15.47 % of total Nagar Panchayat, Female Sex Ratio is of while Schedule Tribe (ST) were 5.41 % of population of Jeron Khalsa (NP). In 935 against state average of 931. total population in Kari (NP). Jeron Khalsa Nagar Panchayat, Female Moreover Child Sex Ratio in Lidhora Out of total population, 4,791 were Sex Ratio is of 875 against state Khas is around 963 compared to Madhya engaged in work or business activity. Of average of 931. Moreover Child Sex Pradesh state average of 918. Literacy this 2,824 were males while 1,967 were Ratio in Jeron Khalsa is around 839 rate of Lidhora Khas city is 69.45 % females. In census survey, worker is compared to Madhya Pradesh state higher than state average of 69.32 %. In defined as person who does business, job, service, and cultivator and labour average of 918. Literacy rate of Jeron Lidhora Khas, Male literacy is around activity. Of total 4791 working population, Khalsa city is 62.65 % lower than state 78.48 % while female literacy rate is 62.05 % were engaged in Main Work average of 69.32 %. In Jeron Khalsa, 59.75 % while 37.95 % of total workers were Male literacy is around 73.36 % while Lidhora Khas (NP) of Tikamgarh has engaged in Marginal Work. female literacy rate is 50.51 substantial population of Schedule Caste.

35

Baseline Kari Jeron Khalsa Lidhorakhas characteristic %. Schedule Caste (SC) constitutes Schedule Caste (SC) constitutes 28.30 % 13.57 % while Schedule Tribe (ST) were while Schedule Tribe (ST) were 1.25 % of 4.07 % of total population in Jeron total population in Lidhora Khas (NP). Khalsa (NP). Out of total population, 4,835 were Out of total population, 4,294 were engaged in work or business activity. Of engaged in work or business activity. Of this 3,335 were males while 1,500 were this 2,680 were males while 1,614 were females. In census survey, worker is females. In census survey, worker is defined as person who does business, defined as person who does business, job, service, and cultivator and labour job, service, and cultivator and labour activity. Of total 4835 working population, activity. Of total 4294 working 85.60 % were engaged in Main Work population, 69.80 % were engaged in while 14.40 % of total workers were Main Work while 30.20 % of total engaged in Marginal Work. workers were engaged in Marginal Work. History, There are no protected or notable There are no protected or notable There are no protected or notable culture & historical, cultural or tourism places in the historical, cultural or tourism places in historical, cultural or tourism places in the tourism town. the town. town. There is an old fort constructed by Maharaj Hate Singh. It still stands in a good condition. Presently it is used as school building, and a school is operable in here. It is under the jurisdiction of LidhoraKhas Nagar Parishad. There are no ASI protected or state protected monument in or near the towns.

36

Figure 9: Site Environs of Jeron Khalsa and Lidhorakhas Town

37

Figure 10: Site Environs of Kari Town

38

Table 8: Site Environmental Features of Jeron Khalsa and Lidhorakhas GWSS Infrastructure Location & Environmental Features Site Photograph Weir and Intake Weir and Intake well cum pump house will be Well built in the Jamni River, under the control of Water Resources Department, GoMP.

The Jamini River originates from Jamini reservoir near Pahadi Kalan Temple in Tikamgarh District. Proposed weir located at 164.5 km from the origin, Jamini River is a small river, and therefore the details of tributaries are not available. Weir site is situated on Jamini River at Milanghat about 4Km away from Jeron Khalsa Town. There is no major tributaries up to the proposed site. As per local enquiry there is no existing major weir within 10 Km U/S & D/S of existing weir.

Intake well is proposed just U/S of existing

weir

As per information gathered from the local people, since the river is non-perennial there is no aquatic life found in the river. It is clearly scene from the figure 5, that there is no forest area in the downstream of the proposed weir. Raw water pipeline will be laid underground from the intake well to WTP site along an existing road.

39

Raw Water Rising 950 m long RWRM has proposed for group Main water supply scheme, which is proposed along an earthen road, which comes under jurisdiction of Rural department. Raw water rising main will be laid along the main road. Pipes will be laid Underground. The RWRM leading to Intake well to WTP, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission of ULB. There is no forest land within the prescribed limit of the town.

WTP site WTP is proposed about 1.5 Km from the WTP proposed intake well site. There is Kachcha N250, 05.868’ E0780, 40.329’ Sarsau ki toriya near Bajrang Khirak road up to the WTP site. The nearest house is just adjacent to the site. The proposed WTP site is in the Bajrangarh Panchayat. Site is currently vacant, and covered with shrubs and bushes. Land in under Revenue Department. There are no tree cutting issue.

40

OHT at Jeron One OHT of 100 KL capacity is proposed in OHT (100KL) 0 0 Khalsa ward no. 5. N25 , 05.868’ E078 , 40.329’ Mudera, Ward No. 05 Site is almost plain & approachable. No tree

cutting will be required, nearest house about 100m. There is Nagar Parishad community hall adjacent to the site.

OHTs at Lidhora Two OHTs of 200 KL capacity each are Khas proposed for town. OHT at ward no 3: Site is almost plain and approachable. No tree cutting will be required. Nearest house about 200m. There is Shamshan Ghat adjacent to the site. OHT at ward no. 9 Selected site is located on a hillock adjacent to the residential area in the town. Site is currently vacant; and owned by ULB.

Transmission pipelines will be mostly laid Transmission & Transmission main; along the main roads of the town. Pipes will distribution be laid underground. network

Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. Roads in the old part of the town are quite narrow (~3m), and in the rest of the town roads are wider. Roads are lines both sides with open drains. There are no trees along the roads, except in some new colonies in the outer areas. In old town areas 41 pipes will be laid in the middle of the road, which may affect the traffic.

Distribution Networks

42

Table 9: Site Environmental Features of Kari WSS Infrastructure Location & Environmental Features Site Photograph Intake Well Weir and Intake well cum pump house will be built in the Jamni River, under the control of Water Resources Department, GoMP.

Proposed Weir site is situated on Jamini River at Aamghat about 10Km away from Kari Town. The Jamini River originates from Jamini reservoir near Pahadi Kalan Temple in Tikamgarh District. There is no major tributaries up to the proposed site. As per local enquiry there is no existing major weir with in 10Km U/S & D/S of existing weir.

As per information gathered from local people, since the river is non- perennial, there is no aquatic life found in the river. Raw Water Out of total length (10850m), initial Rising Main 1 Km stretch of RWRM has earthen road, which comes under jurisdiction of Rural department. Rest 9 km RWRM laid along the State Highway road comes under jurisdiction of PWD department. Raw water rising main will be laid along the main road. Pipes will be laid Underground. The RWRM leading to Intake well to WTP, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission of ULB. There is no forest land within the prescribed limit of the town. 43

WTP site WTP site is located in ward no .13; WTP WTP is proposed in the Ward No.- N240,49.660’ E0780, 51.786’ 13 of Kari Town. The nearest Viyogi, Ward 13 habitation/houses is about 100m away. The site is proposed on small hillock & approach is available up to the root of the hill

GSRs Three GSRs proposed for the town. GSR-1: 110 KL capacity is proposed at Ward No.10, proposed site is vacant; and under possession of Kari Nagar Parishad.

GSR-2: 170 KL capacity is GSR (170KL) proposed at Ward No.7, Proposed 0 0 on small hillock. Road is available N24 , 59.579’ E078 , 52.232’ up to the root of the hill. No tree Near Hanuman Temple, Dr Ambedkar Ward No. 07 cutting will be required. Nearest house at about 150m. There is Temple near the site.

44

GSR-3: GSR (200KL) N240, 59.660’ E0780, 51.786’ 200 KL OHT is proposed at Ward no Viyogi, Ward No. 13 13, Site is vacant. Site is located within the town. Site is covered with rock out crops. There are small trees in the site.

Transmission WTP site is located in the Kari town, & distribution hence Transmission pipelines will be network mostly laid along the main roads of the town. Pipes will be laid underground.

Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. Roads in the old part of the town are quite narrow (~3m), and in the rest of the town roads are wider. Roads are lines both sides with open drains. There are no trees along the roads, except in some new colonies in the outer areas. In old town areas pipes will be laid in the middle of the road, which may affect the traffic.

45

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. Introduction

30. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

31. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

32. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

33. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

34. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE.

35. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability; (iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The proposed project components locations are belonging to the government property and existing roads, hence land acquisition and encroachment on private property will not happen in this case.

46

B. Pre-Construction Impacts – Design & Location

36. Design of the Proposed Components. Technical design of the (i) Weir and intake well, (ii) water treatment plant; (iii) raw water and clear water transmissions mains (iv) overhead tanks, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

(i) Recovering backwash water from treatment process. (ii) Treatment and disposal management of sludge from treatment process. (iii) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (iv) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage (v) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies (vi) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (vii) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (viii) Using low-noise and energy efficient pumping systems

C. Water Source Sustainability & Impacts association with water abstraction

1. Jeron Khalsa and Lidhorakhas

37. Source Identification: Jamni River as a water source is identified for proposed water supply scheme for Jeron Khalsa and Lidhorakhas towns.

38. Jamni River: Jamni River is Ephemeral River and the nearest water body for Jeron khalsa and Lidhorakhas towns. Jamni River is a river in northern India. It is a main tributary of the Betwa River and enters Lalitpur District near Madanpur village. It meets Betwa River

near Orchha.

47

Figure 11: Distance between existing Weir for Kari and Jeron khalsa is 39.8 km

39. Jamni River is the only surface source of water which can be considered as a dependable source to fulfil the present and future demand of the town. Jamni River is about 2.5 km far from Jeron Khalsa. As there is no other reliable source in the vicinity of both Jeron Khalsa & Lidhorakhas, hence a group water supply scheme from Jamni River has been planned for both the towns. There is a 276 m long and 3.0 m high existing weir built by WRD on the bank of Jamni River near milanghat. Jamni river has sufficient flow up to 4 months (July to October) and since the flow diminishes after rainy season, some storage will be required for the remaining period (November to July). Hence, this existing weir has been considered as a storage structure for the non-rainy season. The capacity of the weir need to be increased so that it can store sufficient water to meet the total ultimate water demand (2.98 MLD) of both Jeron Khalsa and Lidhorakhas towns. This can be achieved by increasing the height of the weir by 1.5 m. This existing stop dam needs some repairing work to meet its functional requirements. Gates i.e. shutters need to be installed in the weir, i.e. Existing Weir (proposed for Jeron Khalsa & Lidhora Khas GWSS will be provided with low level sluice gates (just above the dam sill level at the river bed) to allow release of water as and when required. Sluice gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows as shown in drawings annexed as Figure 30 to Figure 31, below. Final water source for Jeron Khalsa & Lidhorakhas WSS Is Jamni River, there is no alternative and reliable source other than Jamni River. Aquatic life is not affected by proposed Weir. Details of existing weirs/dams across River Jamni w.r.t. Existing Weir (Proposed for Jeron Khalsa & Lidhora Khas GWSS are given in the Table 10, below.

48

Table 10: Existing Weirs/ Ceck Dams across Jamni River and distance from Origin of river & proposed weir (For Kari Town) & Existing Weir(Proposed for Jeron Khalsa & Lidhora Khas Towns GWSS) Distance from Distance from Capacity Height Type origin (approx.) Existing Weir (MCM) (m) No. of Location Kms for Jeron Existing Dams Khalsa & Lidhora Khas Origin (Jamni 24° 6'51.98"N, 0 155.77 River) 78°39'57.19"E Lalitpur Jamni 24° N, 53.1 102.67 92.89 19.18 Earthen Reservoir 22.205’ 78°41.088’ E 24°40'9.26"N, U1 98.52 57.25 - - - 78°45'20.85"E 24°42'51.62"N, U2 105.34 50.43 - - - 78°46'37.31"E 24°46'1.60"N U3 111.71 44.06 - - - 78°46'16.00"E 24°48'9.04"N U4 116.71 39.06 - - - 78°47'15.42"E 24°48'49.90"N U5 118.15 37.62 - - - 78°47'10.07"E 24°49'9.11"N U6 118.92 36.85 - - - 78°46'55.33"E Proposed Weir 24°50'59.04"N for Kari town 122.5 33.27 3.5 RCC 78°46'28.02"E WSS 24°51'5.38"N U7 122.7 33.07 - 2.5 RCC 78°46'25.53"E

24°52'0.46"N U8 126.04 29.73 - - - 78°45'0.03"E

24°52'11.49"N U9 127.22 28.55 - - - 78°44'27.56"E

24°52'51.39"N U10 129.99 25.78 - - - 78°43'5.71"E

24°53'14.15"N U11 131.82 23.95 - - - 78°42'17.87"E

24°53'37.56"N U12 142.32 22.77 - - - 78°41'44.13"E

24°53'56.39"N U13 135.09 20.68 - - - 78°40'36.04"E

24°56'2.70"N U14 139.28 16.49 - - - 78°39'48.41"E

25° 1'58.34"N U15 151.04 4.73 - - - 78°39'12.47"E 49

Distance from Distance from Capacity Height Type origin (approx.) Existing Weir (MCM) (m) No. of Location Kms for Jeron Existing Dams Khalsa & Lidhora Khas (Proposed Weir for Jeron 25° 4'20.37"N Khalsa & 155.77 0 0.725 3.0 RCC 78°38'21.40"E Lidhora Khas Town GWSS) 25° 5.602'N D1 160.62 4.85 - - - 78°36.115'E

25° 6.696'N D2 162.51 6.74 - - - 78° 36.308'E Destination (Jamni River 25°12'47.22"N, meets Betwa 174.81 19.04 - - - 78°33'50.33"E River at Orchha)

(Left/Right) Contributing Runoff side of Jamni Tributary River Jeron Khalsa Weir Kari Weir Left Sajnam River No Yes Left Shahzad River No Yes Right Chandokha Nala No Yes Left Kantoran Nala Yes Yes Right Manpasar Nala Yes Yes Right Banbayar Nala Yes Yes Left Kenar Nala Yes Yes Right Jamrar River Yes Yes Left Lilji Nala Yes Yes Right Not River Yes Yes Right Pateriya Nala Yes Yes Right Malandu Nala Yes Yes Left Sukarwa Nala Yes Yes Right Bargi River No Yes

50

Figure 12: Google Earth Map Showing Location of Existing Dams/Weirs across Jamni River on U/S & D/S w.r.t. Existing Weir (Proposed for Jeron Khalsa & Lidhora Khas GWSS

51

Figure 13: Google Map Showing location of Existing Weir (Proposed For Jeron Khalsa & Lidhora Khas Towns GWSS), Intake Well at Milanghat and location of nearest Existing Weir across Jamini River.

52

Table 11: Base line information for Jamini Rivers for Jeron Khalsa & Lidhora khas Town Name Location Total Length of List any River flow characteristics (in the period below, mention of length river dams/weirs week/month to which week/month, there can be more than river of from u/s of one period for type of flow)) river origin to proposed Ephemeral Flows Complete Very Medium Low – proposed weir site / Perennial periods dry high - flow very low weir site (indicate period high period flow in an flow period area period when river flows) Jamni At 175 155.77 Jamni Ephemeral July to January July & November January Milanghat KM km reservoir October to June August to to December February Source: DPR Consultant

Table 12: Flow data analysis and Calculation for water availability based on Catchment area & Rainfall Analysis Calculation for total runoff Jeron khalsa & Lidhorakhas weir at Jamni River

Sr No 1 Catchment area (A) = 2353.97 Sq Km

2 Average rain fall (Maximum) (I) = 950 mm

3 Average rain fall (Minimum)(I) = 760 mm

4 Run off coefficient (R) =

0.2 =

5 Formula = AIR

I Maximum rainfall = 2353.97X1000X1000X0.95X0.2 cum

= 447254300 cum

= 447.25 MCM

Ii Minimum rainfall = 357803440 cum Total Available water = 357.80 MCM

Source: DPR Consultant

40. The proposed yearly water abstraction is 1.0877 MCM, which is just a fraction (about 0.3%) of total yearly water availability in the catchment (i.e.,357.80 MCM). This abstraction is negligible and not likely to have any impacts downstream. There are also no notable water abstraction points or users in the immediate downstream of the proposed weirs. With the construction of proposed weir with a small storage capacity with a fraction of total water 53 availability in the river as stated above, there will be any notable changes in the flow regime is not going to change this flow regime post construction.

Figure 14: Catchment Area for proposed Weir for jeron Khalsa and Lidorkhas

54

Table 13: Area Capacity Calculation of Existing Weir Proposed for Group Jeron Khalsa & Lidhorakhas WSS

Table 14: Evaporation losses of Existing Weir Proposed for Group Jeron Khalsa & Lidhorakhas WSS

0 55

Table 15: Storage Capacity of Weir

Figure 15: Capacity curve of GWSS Jeron Khalsa & Lidhora Khas WSS

Source: DPR Consultant

56

41. Source Sustainability for Group water supply scheme (GWSS) for Jeron Khalsa and Lidhorakhas towns: Source is River Jamni. This river is not a perennial river; it is Ephemeral River. As per information gathered from the local authority, the flows for about 4 months, mostly during monsoon and winter seasons, from early July to October. Flow is considerable high during the months July and August; flow is considerably medium in month of September and October; flow reduces significantly in November, and river gets completely dry in January and up to the onset of next monsoon in June. No flow data is available as there is no gauging station on the river. Catchment area for Weir on Jamni River is 2353.97 Sq. Km. Water availability based on catchment area and rainfall analysis is 357.80 MCM. Since flow finishes after the rains, hence a storage reservoir is required for remaining 8 months of the year so that Ultimate demand for both the towns can be fulfilled. The Ultimate Demand of Jerone Khalsa & Lidhora Khas town is 2.98 mld or 1.0877 MCM per year. After looking above facts for selection of water source for group scheme of both the towns, as there is no other reliable source except Jamni River in the vicinity of both Jeron Khalsa & Lidhorakhas, hence a group water supply scheme from Jamni river has been planned for both the towns. There is a 276 m long and 3.0 m high existing weir built by WRD on the bank of Jamni river near milanghat. Jamni river has sufficient flow up to 4 months (July to October) and since the flow diminishes after rains, some storage is required for the remaining period (November to July). Hence, this existing weir has been considered as a storage structure for the non-rainy season. The capacity of the weir need to be increased so that it can store sufficient water to meet the total ultimate water demand (2.98 MLD) of both Jeron Khalsa and Lidhorakhas towns. This can be achieved by increasing the height of the weir by 1.5 m. Gates i.e., shutters need to be installed in the weir. This existing stop dam needs some repairing work to meet its functional requirements. After survey and investigation, it is clear that the total ultimate water demand (2.98 MLD) or 1.087 MCM of both the towns can be fulfilled by increasing the height of the existing weir by 1.5 m and it can be adopted as a common storage reservoir for both the towns. The capacity of the existing weir after increasing its height is 1.169 mcm and it will last upto 31st July at the ultimate stage demand of 1.087 MCM. Hence capacity of weir is sufficient to fulfill the ultimate demand.

42. The water demand for the combine town Jeron Khalsa and Lidorakhas is 2.98 MLD or 1.0877 MCM, while total available water 357.80 MCM (minimum rainfall), based on catchment area and rainfall analysis as shown in Table 12 above. The total requirement is just about 0.3% of the estimated water yield. The above (Table 13 to table 15 & Figure 15) show the data calculation of weir at jamini river for Jeron Khalsa and Lidhorakhas town.

43. Impact on D/S & U/S due to Increasing Height of Existing Weir: The height of weir proposed to meet the water storage requirement, and also considering the height of river banks so as to limit the water storage / submergence to river course (in below figure blue contour line shows the river bed and green shows the submergence area). Therefore, there are no impacts due to submergence. Given the small storage compared to the total volume of water available in the river, no significant impacts envisaged on downstream. Given intermittent nature of rivers, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. Existing Weir proposed for GWSS (Jeron Khalsa & Lidhora Khas towns) will be provided with low level sluice gates (just above the dam sill level at the river bed) to allow release of water as and when required. Sluice gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows as shown in drawings annexed as Figure 17, below. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract. Water quality is good and there are no potential pollution sources in 57 the vicinity that could affect the water quality. Necessary precautionary measures are suggested to avoid any impacts.

Figure 16: Submergence Area of Jamni River for Jeron Khalsa & Lidhorakhas Town weir.

58

Figure 17: Typical Cross section and Plan with and without gate for weir Lidhora Khas & Jeron Khalsa

Typical Cross-Section of Weir

59

2. Kari Town WSS

44. Source Identification: Jamni River as a water source is identified for proposed water 1supply scheme for Kari Town.

45. Jamni River: Jamni River is Ephemeral River and the nearest water body for Kari town. Jamni River is a river in northern India. It is a main tributary of the Betwa River and enters Lalitpur District near Madanpur village. It meets Betwa River near Orchha. The Jamni River which originates in the district of Sagar in Madhya Pradesh is primarily rain fed. As a result it swells up during the monsoon season and the water level falls down during the summer months. It is one of the important sources of water in the dry areas of Bundelkhand region of Madhya Pradesh. This inter-state river flows through Sagar in Madhya Pradesh to enter the district of Lalitpur in Uttar Pradesh and finally crosses over to Tikamgarh again in Madhya Pradesh and meets the Betwa near the town of Orchha. It cuts through Sagar to enter the district of Lalitpur flowing through the forest near the village of Madapur. For the next 45km, it flows in the northward direction and turns to the north east for 6km after leaving the town of Mahroni on the right. For the next 60 km, the river forms the boundary of the district and at places it flows close to the Betwa River but does not merge in to it. The Jamni takes care of the irrigation of a large area in this district.

(i) River Jamni flows about 11.50 km away from the town Kari. It has sufficient flow up to end of October and mid of November month. Since flow finishes after the rains, hence a storage reservoir is required for remaining 8 months of the year so that Ultimate demand of the town can be fulfilled. The Ultimate Demand of Kari is 1.56 mld. There is an existing weir at Aamghat which was constructed by WRD. The length and height of Weir are 130 m and 2.5 m respectively. This weir has leakages. Under piping is also visible at 3 to 4 points. Banks are also not stable. Outflanking is imminent. Concrete quality is also not good. Hence this weir is not suitable for the scheme. In this season the whole water leaked through it and it became dry in the month of February. After the survey decided to propose a new Weir approximately 200 m up stream of the present weir. At this section ground elevation is 2 - 3 m higher than the existing weir. The length of the proposed Weir is 160 m and height is 3.5 m. Details of existing weirs/dams across jamni River w.r.t. proposed weir Kari town WSS are given in the Table 16, below.

Table 16: Existing Weirs/ Check Dams across Jamni River and distance from Origin of river & Proposed weir For Kari Town WSS Distance from Distance Capacity Height Type origin (approx.) from (MCM) (m) No. of Existing Location Kms Proposed Dams Weir Kari Town U/S Dams From Proposed Weir Kari Town WSS Origin (Jamni 24° 6'51.98"N, 0 122.5 River) 78°39'57.19"E Lalitpur Jamni Reservoir 24°22.205’ N, 53.1 69.4 92.89 19.18 Earthen 78°41.088’ E 24°40'9.26"N, U1 98.52 23.98 - - - 78°45'20.85"E U2 24°42'51.62"N, 105.34 17.16 - - -

60

Distance from Distance Capacity Height Type origin (approx.) from (MCM) (m) No. of Existing Location Kms Proposed Dams Weir Kari Town 78°46'37.31"E 24°46'1.60"N U3 111.71 10.79 - - - 78°46'16.00"E 24°48'9.04"N U4 116.71 5.79 - - - 78°47'15.42"E 24°48'49.90"N U5 118.15 4.35 - - - 78°47'10.07"E 24°49'9.11"N U6 118.92 3.58 - - - 78°46'55.33"E D/S Dams From Proposed Weir Kari Town Proposed Weir 122.5 0 24°50'59.04"N for Kari town 78°46'28.02"E WSS 24°51'5.38"N D1 122.7 0.2 - 2.5 RCC 78°46'25.53"E

24°52'0.46"N D2 126.04 3.54 - - - 78°45'0.03"E

24°52'11.49"N D3 127.22 4.72 - - - 78°44'27.56"E

24°52'51.39"N D4 129.99 7.49 - - - 78°43'5.71"E

24°53'14.15"N D5 131.82 9.32 - - - 78°42'17.87"E

24°53'37.56"N D6 142.32 10.5 - - - 78°41'44.13"E

24°53'56.39"N D7 135.09 12.59 - - - 78°40'36.04"E

24°56'2.70"N D8 139.28 16.78 - - - 78°39'48.41"E

25° 1'58.34"N D9 151.04 28.54 - - - 78°39'12.47"E D10 (Proposed Weir for Jeron 25° 4'20.37"N 155.77 33.27 0.725 3.0 RCC Khalsa & 78°38'21.40"E Lidhora Khas Town GWSS) 25° 5.602'N D11 160.62 38.12 - - - 78°36.115'E 61

Distance from Distance Capacity Height Type origin (approx.) from (MCM) (m) No. of Existing Location Kms Proposed Dams Weir Kari Town 25° 6.696'N D12 162.51 40.01 - - - 78° 36.308'E Destination (Jamni River 25°12'47.22"N, 174.81 52.31 - - - meets Betwa 78°33'50.33"E River at Orchha)

(Left/Right) Contributing Runoff side of Jamni Tributary River Jeron Khalsa Weir Kari Weir Left Sajnam River No Yes Left Shahzad River No Yes Right Chandokha Nala No Yes Left Kantoran Nala Yes Yes Right Manpasar Nala Yes Yes Right Banbayar Nala Yes Yes Left Kenar Nala Yes Yes Right Jamrar River Yes Yes Left Lilji Nala Yes Yes Right Not River Yes Yes Right Pateriya Nala Yes Yes Right Malandu Nala Yes Yes Left Sukarwa Nala Yes Yes Right Bargi River No Yes

62

Figure 18: Showing Origin & Destination Point and Existing Weirs on U/S & D/S across Jamini River From Proposed weir Kari Town WSS Near Aamghat

63

64

Figure 19: Google Map Showing location of proposed Weir, intake Well and location of nearest Existing Weir (D/S) at Aamghat for Kari Town WSS.

65

Table 17: River water flow analysis Jamni River Origin of River: Near sagar (M.P.) Destination of River: The River meets the Betwa river near town of Orchha. Basin: Ganga Basin Aquatic life is not affected by proposed Weir Note: Catchment area of Existing dam is not included for scheme

Nam Location Total Lengt List River flow characteristics (in the period below, mention e of length h of any week/month to which week/month, there can be more than one river of river dams period for type of flow) river from /weirs origin u/s of Ephemeral Flows Complet Very Medium Low to propo – periods e dry high - flow very propo sed / Perennial (indicate period high period low sed weir in an area flow flow weir site when period period site river flows) Jamn At 175 122.5 Jamni Ephemeral July & January July & Novembe January i Aamghat KM km reserv October to June August r to to oir Decembe Februar r y

Source: DPR Consultant

Table 18: Calculation of Weir Capacity for Kari Town WSS

66

Source: DPR Consultant

Figure 20: Capacity curve of GWSS Jeron Khalsa & Lidhora WSS 67

Table 19: Flow data analysis and Calculation for water availability based on Catchment Area & Rainfall Analysis Calculation for total runoff Kari weir at Jamni River

Sr No 1 Catchment area (A) = 1112 Sq Km 2 Average rain fall (Maximum) (I) = 950 Mm 3 Average rain fall (Minimum)(I) = 760 Mm 4 Run off coefficient (R) = 0.2 =

5 Formula = AIR i Maximum rainfall = 1112X1000X1000X0.95X0.2 cum = 211280000 cum = 211 MCM ii Minimum rainfall = 169024000 cum Total Available water = 169 MCM Source: DPR Consultant

Figure 21: shows Catchment area of Jamni River w.r.t. Proposed Weir for Kari Town

68

46. The source Sustainability for of the water supply scheme (WSS) for Kari town is River Jamni. This river is not a perennial river; it is Ephemeral River. As per information gathered from the local authority, the flows for about 4months, mostly during monsoon and winter seasons, from early July to October. Flow is considerable high during the months July and August; flow is considerably medium in month of November to January; flow reduces significantly in January & February months, and river gets completely dry February and up to the onset of next monsoon in June. No flow data is available as there is river no gauging station on the river. Since flow finishes after the rains, hence a storage reservoir is required for remaining 8 months of the year so that Ultimate demand of the town can be fulfilled. The Ultimate Demand of Kari is 1.56 mld or 0.569 MCM per year and water availability based on catchment area and rainfall analysis is 169 MCM. After looking above facts for selection of water source for Kari WSS, there is no alternative and reliable source other than Jamni River. Existing weir at Aamgaht on Jamni river is not in good condition & cannot be used for storage purpose during non-rainy period. Hence a new weir approximately 200 m upstream of the existing weir; 160 long and 3.5 m high is proposed. The capacity of the proposed weir is 0.70 mcm and it will last upto 31st july at the ultimate stage demand of 0.569 MCM. Hence capacity of weir is sufficient to fulfill the ultimate demand.

47. The water demand of Kari town is 1.56 MLD or 0.569 MCM per year, while total available water based on catchment area and rainfall analysis is 169 MCM. The abstraction is just about 0.34 % of water available. There are 14 natural streams/rivers (tributaries) that join Join River in the upstream of proposed Weirs (Refer Table 16, above). All these streams are the natural drains/ small rivers that carry the runoff generated by the rainfall in this catchment area.

48. In the Jamni River at Aamghat there is an existing anicut which was constructed by WRD. The length of the existing Anicut is 130 m and height is 2.5 m. This existing anicut is in deteriorating condition hence a new anicut has been proposed upstream to this anicut.

49. There are several dams and weirs across Jamni River, both upstream and downstream side of the proposed weir. There are 6 (Refer Table 16, above) water retaining structures (existing dams) constructed across Jamni River upstream of the proposed weir sites, and the storage capacities of each of these water retaining structures is not more than 1 MCM except Jamni Reservoir constructed by WRD for irrigation purpose. Storage capacity of this earthen dam / reservoir is 93 MCM with a dam height of 19.18 m. This dam is located about 70 km upstream of proposed weir for Kari, and about 100 km upstream of proposed weir combined scheme of Jaron Khalsa and Lidhorakhas.

50. There are 8 small weirs / check dams between proposed Kari weir and Jaronkhalsa / Lidhrakhas weir, and another 2 weirs downstream of Jaron Khalsa/ Lidhorakhas weir. These are also small structures, and the storage capacities of each of these water retaining structures is not more than 1 MCM

51. Water source sustainability analysis is given in Appendix 8. it is also worthwhile to be mentioned that “water source finalization committee of MPUDC, GoMP has approved the proposed raw water in its 9th meeting held on dated august 31, 2018. This committee is a highest level Apex Body of GoMP comprised of senior level members including hydrologists from Jal Nigam and water Resources Deptt. of govt. of Madhya Pradesh.” The copy of MoM of the said meeting is enclosed in Appendix 8. For NoC from WRD Application has been submitted and it is under process.

69

52. Impact on D/S & U/S due to Weir Construction: The height of weir proposed to meet the water storage requirement, and also considering the height of river banks so as to limit the water storage / submergence to river course (in below figure blue contour line shows the river bed and red shows the submergence area). Therefore, there are no impacts due to submergence. Given the small storage compared to the total volume of water available in the river, no significant impacts envisaged on downstream. Given intermittent nature of rivers, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. Weir will be of solid concrete structure, and will be provided with low level sluice gates (just above the dam sill level at the river bed) to allow release of water as and when required. Sluice gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows as shown in drawings annexed as Figure 22, below. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract. Water quality is good and there are no potential pollution sources in the vicinity that could affect the water quality. Necessary precautionary measures are suggested to avoid any impacts.

Figure 22: Typical Cross section and Plan with and without gate for weir for Kari town.

70

Figure 23: Submergence area (0.231 Sq.Km.) of proposed Weir

71

53. Similarly proposed works in the riverbed (for intake) may damage the river bed, lead to degradation of water quality due to increase in turbidity and contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life. Measures are included in the EMP to avoid, minimize these impacts.

54. Removal of trees and vegetation will be minimize by best alignment and layout planning of facilities, however, this cannot be avoided fully. Appropriate measures in terms of compensatory tree plantation are included in the EMP.

55. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will be required to implement appropriate measures. These are given in the EMP.

56. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas. Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will

57. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

58. Sensitive project locations. There are forest areas around the towns, however, none of the components located in or close to the forest area. This will be further verified and ensured during the detailed design phase. However, as the pipelines are aligned along RoW of roads, there is no need for tree cutting and/or removal of vegetation. During the construction phase, presence of work, vehicles and equipment may create disturbance / damage to the forest areas and wildlife. Measures will be required to avoid any impacts during construction activities near forests. These are given in EMP (Table 9).

D. Construction Impacts

59. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of all the towns are very narrow and congested with pedestrians and vehicles (mainly 2-wheelers), while the roads in outer areas are wide.

60. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m.. Sufficient care will be taken

72

while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This excel soil shall be used for construction.

61. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. The following are anticipated impacts, which are temporary and for short duration:

(i) Dust and air emissions from construction activities and equipment / vehicles affecting the ambient air quality (ii) Impacts on natural drainage, surface water bodies due to disposal of construction waste and silt / chemical laden run off from work areas (iii) Impacts on river eco-system due to river bed construction (iv) Impacts due to disposal of surplus soil, construction waste, debris etc., (v) Impacts due to noise and vibration from consultation activities (vi) Impacts due to collection of groundwater in trenches & disposal of the same (vii) Impact/public inconvenience/ accessibility issues due to excavation on public roads (narrow old town roads), movement of trucks carrying construction material (viii) Impacts on business, activities, people due to loss/restricted access to public/private/business/sensitive areas (schools, hospitals), etc., (ix) Occupation health and safety impacts on workers (x) Health Impacts due to removal of existing AC (asbestos cement) pipes (xi) Community health and safety impacts due to construction in an urban area (xii) Impacts due to establishment/operation of temporary construction camps

62. Construction of weir and intake well in the river Jamni may lead to degradation of water quality due to increase in turbidity and chemical contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life, silting/chocking of spill ways/ canals etc., Jamni River is a non-perennial river and almost run dry during summer season. Though there are no notable aquatic life, to ensure that any negative impacts are mitigation, the contractor will be required to:

o Select a construction methodology that is least disturbing, and appropriate for the in-situ soil condition o Schedule the construction works during low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; confirm with concerning authorities on release of water; avoid scheduling the works during water release period. o Erect temporary barriers to form enclosed construction area with least disturbance o Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden 73

water should be pumped to a silt pond o Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage o Clean up the area after the completion & prior to the onset of monsoon flow

63. Generation of Construction Wastes. Solid wastes generated from the construction activities are excess excavated earth (spoils), discarded construction materials, cement bags, wood, steel, oils, fuels and other similar items. Domestic solid wastes may also be generated from the workers’ camp. Improper waste management could cause odor and vermin problems, pollution and flow obstruction of nearby watercourses and could negatively impact the landscape. The following mitigation measures to minimize impacts from waste generation shall be implemented by the contractor:

o Prepare and implement a Construction Waste Management Plan o Stockpiles, lubricants, fuels, and other materials should be located away from steep slopes and water bodies; o Avoid stockpiling any excess spoils. Excess excavated soils should be dispose to approved designated areas; o Domestic solid wastes should be properly segregated in biodegradable and non- biodegradable for collection and disposal to designated solid waste disposal site; o Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed in disposal sites approved by local authorities; o Prohibit burning of construction and domestic waste; o Ensure that wastes are not haphazardly dumped within the project site and adjacent areas. o Get approval of PIU in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

64. Noise and Vibration Levels. Except water intake and WTP, all the construction works will be conducted at selected sites and along the roads in all the six towns’ urban area and surroundings, where there are houses, schools and hospitals, religious & historical places and small-scale businesses. The sensitive receptors are the general population in these areas. Increase in noise level may be caused by excavation, particularly breaking of cement concrete or bitumen roads, operation of construction equipment like concrete mixers, and the transportation of equipment, materials, and people. Vibration generated from construction activity, for instance from the use of pneumatic drills, will have impact on nearby buildings and monuments. This impact is negative but short-term, and reversible by mitigation measures. The construction contractor will be required to:

o Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance; o Horns should not be used unless it is necessary to warn other road users or animals of the vehicle’s approach; o Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimize sound impact to surrounding sensitive receptor; and o Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s.

74

o Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;

65. Surface and Groundwater Quality. Another physical impact that is often associated with excavation is the effect on drainage and the local water table if groundwater and surface water collect in the voids. In all the towns groundwater is deeper than the proposed excavation depths, and rains are limited to short duration during monsoon. However, to ensure that water will not pond in pits and voids near project location, the construction contractor will be required to conduct excavation works in non-monsoon season to the maximum extent possible.

66. Accessibility. Excavation along the roads, hauling of construction materials and operation of equipment on-site can cause traffic problems. Roads in the core/old town area is very narrow. However, most of the roads are used by pedestrians and two wheelers, and four wheelers vehicles are very limited. Potential impact is negative but short term and reversible by mitigation measures. The construction contractor will be required to:

o Confine work areas along the roads to the minimum possible extent; all the activities, including material & waste/surplus soil stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across for people and vehicles; o Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; o Schedule transport and hauling activities during non-peak hours; o Locate entry and exit points in areas where there is low potential for traffic congestion; o Keep the site free from all unnecessary obstructions; o Drive vehicles in a considerate manner; o Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours o Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.

67. Wherever road width is minimal, there will be temporary loss of access to pedestrians and vehicular traffic including 2 wheelers during the laying of pipes. Under those circumstances, contractor shall adopt following measures:

o Inform the affected local population 1-week in advance about the work schedule 75

o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access.

68. Socio-Economic – Income. The project components will be located in government land and there is no requirement for land acquisition or any resettlement. Construction works will impede the access of residents to specific site in limited cases. The potential impacts are negative and moderate but short-term and temporary. The construction contractor will be required to: o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across for people and vehicles; o Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; o Consult businesses and institutions regarding operating hours and factoring this in work schedules; and o Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/complaints. o Notify community/ water users in advance about likely interruptions in water supply. o Provide alternate sources of clean water until water supply is restored.

69. Socio-Economic – Employment. Manpower will be required during the 24-months construction stage. This can result in generation of temporary employment and increase in local revenue. Thus, potential impact is positive and long-term. The construction contractor will be required to:

o Employ at least 50% of the labour force, or to the maximum extent;

70. Occupational Health and Safety. Workers need to be mindful of the occupational hazards which can arise from working in height and excavation works. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to:

o Comply with all national, state and local labour laws (see Appendix 10); o IFC’s General EHS Guidelines3 and Sector Specific (Water and Sanitation) Guidelines4

3https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 4 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

76

o Develop and implement site-specific occupational health and safety (OH&S) Plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use personal protective equipment; (c) OH&S Training5 for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; o A detailed guidance for Safety from COVID-19 Pandemic during construction works is provided in Appendix 15 - Guideline for Construction work about safety from COVID-19 Pandemic (SOP – Health & Safety Plan). o Ensure that qualified first-aid is provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; o Provide medical insurance coverage for workers; o Secure all installations from unauthorized intrusion and accident risks; o Provide supplies of potable drinking water; o Provide clean eating areas where workers are not exposed to hazardous or noxious substances; o Provide H&S orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; o Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; o Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; o Ensure moving equipment is outfitted with audible back-up alarms; o Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and o Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

5 Some of the key areas that may be covered during training as they relate to the primary causes of accidents include (i) slips, trips and falls; (ii) personal protective equipment; (iii) ergonomics, repetitive motion, and manual handling; (iv) workplace transport; and (v) legislation and responsibilities. Training can provide the foundations of competence but it does not necessarily result in a competent worker. Therefore, it is essential to assess staff competence to ensure that the training provided is relevant and effective. Supervision and monitoring arrangements shall be in place to ensure that training has been effective and the worker is competent at their job. The level of supervision and monitoring required is a management decision that shall be based on the risks associated with the job, the level of competence required, the experience of the individual and whether the worker works as part of a team or is a lone worker. 77

71. Asbestos Materials. Existing water distribution network is mostly asbestos cement (AC) pipes, and because of the health risks these will be left in situ and replaced by new pipes. Plan pipeline alignments carefully to avoid any conflict or damage.

72. Community Health and Safety. Hazards posed to the public, specifically in high- pedestrian areas may include traffic accidents and vehicle collision with pedestrians. Potential impact is negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

o Plan routes to avoid times of peak-pedestrian activities. o Liaise with PIU in identifying risk areas on route cards/maps. o Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. o Provide road signs and flag persons to warn of on-going trenching activities.

73. Work Camps. Operation of work camps can cause temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants. Potential impacts are negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

o Consult PIU before locating project offices, sheds, and construction plants; o Minimize removal of vegetation and disallow cutting of trees; o Provide drinking water, water for other uses, and sanitation facilities for employees; o Ensure conditions of liveability at work camps are maintained at the highest standards possible at all times; o Prohibit employees from poaching wildlife and cutting of trees for firewood; o Train employees in the storage and handling of materials which can potentially cause soil contamination; o Recover used oil and lubricants and reuse or remove from the site; o Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; o Remove all wreckage, rubbish, or temporary structures which are no longer required; and o Confirm to PMU report in writing that the camp has been vacated and restored to pre-project conditions before acceptance of work.

74. Debris disposal. Prior to the commencement of works, contractor shall identify a debris disposal site in consultation with the PIU and adhering to following criteria:

o The site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, top-soil stripping, stacking and

78

preservation should be undertaken prior to initiation of any activities. o Debris disposal site shall be at least 200 m away from surface water bodies6. o No residential areas shall be located within 100 m downwind side of the site. o The site is minimum 250 m. away from sensitive locations like hospitals, religious places, ponds/lakes or other water bodies. The local governing body and community shall be consulted while selecting the site

75. The above impacts are typical for construction in urban areas, and therefore are common to all the six subproject towns. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP applicable to all six towns.

E. Operation and Maintenance Impacts

76. Operation and Maintenance of the water supply system will be carried out by the DBO Contractor for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30 years for mechanical/civil components),it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

77. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

78. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable

F. Project benefits

79. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the

6 In the absence of site meeting the stipulated criteria, an alternate site can be selected specifying the reasons. In such a case, the construction camp management plan should incorporate additional measures specific to the site as suggested by the Construction Manager. 79 operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

80. The citizens of Package 6H towns will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview

81. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

82. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in all the six towns ,WRD,) and MPPCB, etc.,. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB.

B. Public Consultation

83. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

84. Institutional consultations were conducted with the relevant Governmental Departments such as WRD, PHED, MPPCB etc. The subproject proposals are formulated in consultation with all the Six Nagar Parishad to suit the requirements of the respective towns.

85. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted

80

during visits to the project sites. Formal town-level consultation meetings were conducted in June 2018 in all the subproject towns. Besides, several other meetings also conducted at ward- level with communities, and at market with street vendors and hawkers. The details of consultation are provided in Appendix 5.

Consultation in Jeron Khalsa and Lidhorakhas 30th June 2018 Kari Town: 22nd June 2018 Table 20: Summary of Consultation in Kari, Jeron Khalsa & Lidhora Khas Nagar Parishads Town No. of Number of Summary of comments Response from project team name consultatio participants feedback by ns (total, male and stakeholders conducted female) Kari 6 Total- 124 • The Elected Project team ensure a Representatives of the sustainable water supply Male-105 ULB expressed need for scheme for the town the project and willingness to take itup; Female-19 • The prime concern & Project team brief the apprehensions of stakeholders about their share Elected Representatives on loan. was regarding the project – whether it will be a financial burden to the The proposed water supply Nagar Parishads. scheme has metered • Operation and connections, so tariff is as per maintenance of the the supply. facilities developed under the project and community participation; • During discussion, Elected Representatives also complained about poor water supply in town. Some people even don’t have water supply connection in their home. • Some Elected Representatives also showed their apprehension about water tariff after new water supply scheme. • Jeron 5 Total-79 • The area has in After the proposed WSS the Khalsa sufficient and in town gets 70 LPCD and treated Male-58 adequate drinking water. water supply . Water from tube Female-21 wells is presently The proposed water supply supplied the scheme has metered area/community. The connections, so the user area face severe charges is as per the supply. water crisis during the summer season when the ground water level drops. 81

• The community welcomed the project and expressed need for it. However, they were apprehensive that their economic condition would prevent them from paying water user charges. • Community members ho w t h e i r willingness to take water connections but demanded relaxation in user charges. • People were briefed about the complaint redress mechanism

People says that on bus stand heavy traffic and dusty area. Lidhora 2 Total- 37 • Presently water supply in • Background of water supply khaas Kari is not adequate. subproject, Environmental, Social, Male- 24 • Most of the household GRM, traffic safety issue, does not have water Temporary disruption of accesses connection. Female- 13 and benefits from the project were • People also concerned explained to the Stakeholders. about the employment during construction work. • Status of Existing Water Supply at Overall, people express • town. their gratitude for upcoming water supply project and promise to • Proposed subproject components. support the project. • Some people also • Environment, Social and community requested to minimize the impact during operation work water tariff • Impact on health by proposed Few people willing to get project training for employment opportunity • Willing to take new Water connection

• Location of components of proposed water Supply scheme has been finalized with identification of government land.

• Potential positive and negative

82

impacts due to project implementation Ensuring no income loss

• Attention of stakeholders drawn to the EMP, and explained to them how dust, and other construction issues will be managed.

It was informed that night work will be explored during construction but may not be possible, however all measures will be taken by contractor to avoid/minimize construction disturbances

86. The people are willing to extend their cooperation as the activities are proposed to improve the water supply service levels and the living standards. Stakeholder expressed their concern regarding water charges, affordability, disturbance and loss of business due to the work in market area (dust, road closure etc.). The project team explained the proposed mitigation measures to mitigate / minimize such issues.

2. Consultation during construction

87. Prior to start of construction, ULB and PIU with the assistance of PMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

88. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. Information Disclosure

89. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

90. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public. 83

91. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

84

VII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

92. Grievance Redress Mechanism (GRM) is a part of project management that is likely to increase accountability and responsiveness among service providers and provide a friendly environment to the beneficiaries of the project. GRM is considered a tool to measure efficiency and effectiveness of the project as it provides important feedback on the project management. Effectively addressing public grievances is a core component of managing risks under Asian Development Bank (ADB) projects according to the Safeguard Policy Statement (Safeguard Requirement 2: Involuntary Resettlement, Pages 49-50, June 2009) – “The borrower/client will establish a mechanism to receive and facilitate the resolution of affected persons’ concerns and grievances about physical and economic displacement and other project impacts, paying particular attention to the impacts on vulnerable groups. The grievance redress mechanism should be scaled to the risks and adverse impacts of the project. It should address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no costs and without retribution. The mechanism should not impede access to the country’s judicial or administrative remedies. The borrower/client will inform affected persons about the mechanism”. The statement allows the formation of grievance redress committee in the project areas to facilitate the concerns of affected people under the project areas.

93. Purpose of the GRM Manual:

(i) This document describes the procedure that shall be followed by the Madhya Pradesh Urban Development Company Limited (MPUDCL) under Madhya Pradesh Urban Services Improvement project (MPUSIP) to address complaints or concerns shared by people affected due to project related interventions. (ii) The present document intends to provide clarity to project stakeholders on the grievance redress mechanism procedures to be followed under the project. The document provides clarity on how the complaint shall be received, registered, sorted, assessed, resolved and monitored under MPUSIP. This also includes action plans to be followed for effective implementation. Principles: (i) The GRM is based on the following principles and the same shall be used to assess the GRM performance:

(a) Accessibility

94. The GRM shall be accessible to all people residing in the project area. It shall be available and provide assistance to all project affected people irrespective of language, literacy level, or cost. Project affected people shall access the GRM without fear of reprisal. Information on the GRM will be disseminated using various means to ensure people know about GRC, its members and procedures.

(b) Predictability 95. The GRM shall offer clear procedures with time frames for each stage and clarity on the type of results it can and cannot deliver. 85

(c) Transparency 96. The GRM shall operate in such a way that it is easy for others to see what actions are being performed. This will be undertaken through disclosure of all information to the public and affected people.

(d) Credibility 97. The performance of the GRM shall enable affected people to accept and believe that the mechanism works, delivers results and is trustworthy.

(e) Fairness 98. The GRM procedures shall be perceived as fair, especially in terms of access to information, and opportunities for meaningful participation in the final decision. Its outcome should be consistent with applicable national standards and should not restrict access to other redress mechanisms.

(f) Feedback 99. The GRM shall serve as a means to channel citizen feedback to improve project outcomes for the people.

100. It is difficult to avoid Grievances totally but much can be done to minimize and manage complaints in order to reduce impacts.

Nature and scope of Grievance Redress Mechanism under MPUSIP

(ii) GRM aims to address complaints of local affected people because of project interventions in the selected towns (64 towns) of MPUSIP during the project period. (iii) MPUSIP predicts public complaints because of the nature of the project during the design, implementation and operation & maintenance stage of the project. In the design phase, people are expected to raise inconveniences with regards to land acquisition, compensation amount, compensation procedure and environmental issues. During project implementation, grievances may come from individuals or a particular group of people in relation to construction related inconveniences such as dust, noise, blocking drainage, damage roads, walls/boundaries of property and its impact on their daily lives in addition to land acquisition, and compensation. Issues related to corruption shall not be considered by the Grievance Redress Committee (GRC). Corruption related issues shall be forwarded to the State GRC (PMU) directly by the Chairperson of town level GRC at the time of sorting of grievances. The structure, functions of GRC, monitoring & evaluation systems and action plan of its implementation is described below:

A. Structure of GRM and its Functions

(i) The GRM will have a three- tier decision making process. The first tier which is at the town level aims to resolve all construction related grievances which require quick and efficient action. The second tier which is at the project implementation

86

unit (PIU) will handle complaints that could not be resolved by the first- tier level and/or grievances related to land acquisition and compensation. The third tier which is at the project management unit (PMU) or state level will handle complaints which are over and above the scope for the first and second tier and/or complaints which could not be resolved by the first and second tier levels. (ii) Contact numbers of GRC Chair-person and members, CDO and contractor’s focal person will be placed at appropriate locations like construction sites, ULB office etc. (iii) The three-tier Grievance Redress Mechanism under MPUSIP is described below:

1st tier (At Town Level):

Composition of the Grievance Redress Committee (GRC): • A representative of Chief Municipal Officer associated with Urban Local Body, Chairperson; • CDO of ULB designated/nominated by ULB. • Field Engineer of Project Management Consultants; • Focal person (GRC Person) of DBO contractor of respective town; • Field Engineer of concerned ULB designated by the respective PIU, Secretary;

Major Functions: The major functions of town level GRC is as follows: • Registration of Grievances by the Local person (GRC Person) of DBO contractor of respective town Sorting of Grievances by Focal person (GRC Person) of DBO contractor of respective town and Chairperson; • Forwarding grievances to concerned authorities i.e. Site Engineer for resolution; • Information to the complainant on the decision taken to address registered complaint and expected time to resolve issue; • Resolution of issues emerged due to construction; • Feedback to the complainant on action completed against registered complaint and seeking complainant feedback on level of satisfaction; • Closure of grievances by CDO-ULB or forwarding of complaint to PIU GRC if grievance remains unresolved.

2nd Tier {At PIU Level}:

Composition of the PIU level GRC: • Project Manager, associated with Project Implementation Unit (PIU) of Madhya Pradesh • Urban Development Company Limited - Chairperson • An elected member nominated by Mayor in Council/ President in Council of associated • Urban Local Body (ULB). • A Social Worker nominated by Mayor in Council/ President in Council of associated Urban • Local Body 87

• Commissioner of associated Urban Local Body/Chief Municipal Officer or Community • Development Officer/Community Organizer of Urban Local Body. • Community Development Officer CDO-PIU - Secretary

Major Functions: The following functions will be performed by the PIU level GRC: • Registration of complaints by CDO-PIU from the 1st tier GRC and/or affected people; • Eligibility assessment of grievances by the GRC Chairperson; • Information to the complainant about eligibility of the complaint; • Grievance Redress Committee meetings to discuss grievances and action required; • Ensuring collection of detailed information about the eligible complaint; • Assessment of complaint, draw conclusion from discussions and make recommendations; • Develop action plan outlining activities required to implement the recommendations; • Ensuring implementation of recommendations by stakeholders or concerned authorities; • Monitoring actions of the recommendations in view of timeline; • Feedback to the complainant on action completed against registered complaint and seeking complainant feedback on level of satisfaction; • Closure of grievances by CDO-PIU or forwarding of complaint to PMU GRC if grievance remains unresolved.

3rd Tier {At PMU-State Level} Composition of State Level GRC: • Engineer in Chief, MPUDC – Chairperson • Deputy Project Director (T) • Deputy Project Director (A) (Secretary) • Project Officer • Community Development Officer CDO-PMU • PMC TL or representative Advisor

Major Functions: The state level GRC will be responsible to perform the following functions: • Registration of complaints received from GRC PIU and/or affected people; • Information to the complainant about eligibility of the complaint; • Eligibility assessment of grievances by the GRC PMU chairperson with support of the • Secretary of state GRC- – whether grievance is eligible for consideration or not at the state level; • Ensuring collection of required information about the eligible complaint;

88

• Assessment of complaint to draw conclusion from discussions and make recommendations; • Develop action plan outlining activities required to implement the recommendations; • Ensuring implementation of recommendations by stakeholders or concerned authorities; • Monitoring actions of the recommendations in view of timeline; • Closing complaint after all actions taken as per recommendations and feedback to the complainant. • Advise to complainants about approach /appeal to the concerned department in case the complainant is not satisfied or complaint is beyond the scope of the GRC PMU.

89

Figure 24: Work Flow Diagram on GRM

Step 8: Appeal to the Step 1: Receiving Grievances / State Level GRC Complaints and its Registration at town level (24 hours)

Step 2: Review of Grievances, Sorting, Information and

Forwarding (1

Closure of the Closure

: : Step 7 Grievance Redress

Mechanism

: Eligibility Preparation andEligibility :

for Days) Meeting GRC (3

Monitoring and Monitoring and

Step 3

: :

Reporting (Monthly) Step 6

Step 5: Implementation of Step 4: Assessment of the Action Grievance, Meeting and Plan of

B. Process of Grievance Redress Mechanism

101. The following process shall be adopted for receiving complaints and addressing received complaints:

Step 1: Receiving Grievances/ Complaints and its Registration at town Level • All grievances, complaints, concerns shall be submitted verbally or in writing to CDO contractor’s focal person or any GRC members – by filling the Complaint Registration Slip and putting into the complaint box placed at construction sites or ULB office. • Received complaints shall be recorded, compiled and Registered (Grievance Number) in a register (database) placed at the ULB by CDO with support of the contractor’s focal person on a daily basis (24 hours). Each grievance shall be given a number to track status.

90

Step 2: Review of Grievances, Sorting, Information and Forwarding (24 hours) • Registered grievances shall be reviewed by the CDO with support of the contractor’s focal person. • Based on type of grievances, CDO shall sort out grievances with support of the contractor’s focal person. • CDO (ULB) shall inform the GRC Chairperson about all grievances either by phone or in writing. At that time, CDO may suggest grievances can be managed by the site engineer to the GRC Chairperson; • GRC Chairperson will determine eligibility of the complaints. Inconveniences caused by minor construction related issues shall be referred to the site engineer to resolve immediately or within 24 hours. For example -site engineer shall be instructed to resolve grievances associated with construction at the town such as restoration of road, obstruction in accessing house/shop or any place due to dumping of construction materials, dust etc. Site engineer will be responsible to respond to the complaints immediately. On the other hand, issues which cannot be resolved by the site engineer and if it is complex in nature shall be referred to GRC. • CDO shall receive acknowledgement from concerned authorities (site engineer) on receipt of the grievances shared with them. CDO shall inform complainants regarding eligibility of their complaint and action to be taken by the concerned authority (site engineer/ GRC) within (24 hours). If the grievance is ineligible, complainants should be informed of the reasons;

Step 3: Eligibility and Preparation for GRC meeting (3 days) • GRC Chairperson shall receive eligible complaints (copy of written complaint document or verbally recorded messages) from the CDO (ULB) and review details; GRC Chairperson may ask to collect baseline information about the grievances registered, if required. • GRC Chairperson shall share list of documents with the GRC Secretary to collect baseline information on selected grievances to be addressed. • The GRC Secretary shall arrange all documents with the help of CDO-ULB, CDO- PIU or the contractor’s focal person in a proper way to present in front of GRC. • GRC Chairperson shall call a meeting as per convenient date and time of the committee members.

Step 4: Assessment of the Grievance, Meeting and Plan of Action (7 days) • If necessary the GRC shall consult and seek relevant information about complaint from the concerned parties. • On basis of the collected evidences, GRC shall draw conclusions and make recommendations for a solution. • GRC Secretary shall keep record of the proceedings and decisions taken by GRC members to further track the status as per decided time line. • The GRC shall agree on the action plan required to be implemented according to the recommendations made. The action plan shall include detailed activities along with timeline. 91

• GRC Secretary shall inform to the complainant about the decisions taken by the committee members and expected date of resolution of the grievance. • If the complaint is complex, the GRC may request for additional time and resolution after proper assessment or refer the complaint to the GRC-PMU Level.

Step 5: Implementation of Action (30 days) • The concerned parties shall be responsible to implement action plan according to recommendations of the GRC. • The GRC members may arrange field trip and interact with the concerned persons, if needed before reaching the conclusion.

Step 6: Monitoring and Reporting (Monthly) • CDO (ULB) shall be responsible to track and record status of all complaints - whether forwarded to site engineer or GRC in the database as follows – Grievance registered Grievance in process to be resolved, Grievance addressed and closed, and Grievance forwarded to concerned authorities. • CDO (ULB) shall be responsible to report/inform status of the complaints (received, addressed and forwarded) to the contractor for further reporting to respective PIU. • Overall GRC chairperson shall be responsible for effective management of complaints at the town level.

Step 7: Closure of the Complaint • GRC Secretary shall prepare a summary of the findings and share with GRC members. • On agreement of all GRC members, GRC Secretary shall provide information to the complainant about decisions taken in writing/verbal on the registered complaint and seek feedback of the complainant about the decisions taken. A copy of the letter shall be kept as record with GRC Secretary and CDO (ULB). • Complaint shall be considered closed if all actions have been taken and the complainant satisfied with the resolution. • GRC Secretary shall prepare a closure report of the grievances handled by GRC members and the closure shall be documented by the CDO (ULB) in his register.

Step 8: Appeal to the State level GRC • In the event that GRC PIU cannot make a decision on how to resolve the complaint, or if a complainant is not satisfied with the actions taken to resolve the complaint by the GRC (PIU), an appeal can be made to state level GRC (PMU) either by the GRC Chairperson (PIU) or complainant directly. • GRC Chairperson (PIU) or complainant shall submit an appeal in writing to the state level GRC established at PMU. • The state GRC Secretary shall register the case in consultation with Chairperson and provide a number of the grievances to be tracked. • The state GRC Secretary shall acknowledge the registration of the grievance to the complainant in writing.

92

• The Secretary of the GRC shall review the registered grievances and collect required evidences from relevant parties to present case to the GRC. • The state GRC Chairperson shall call a GRC meeting to review the complaint. GRC members shall get information about the meeting in advance to ensure their availability in the meeting. • The state GRC shall draw conclusions and recommendations based on the evidence in the meeting. At the same time an action plan shall be developed for implementation with a timeline. • The state GRC Secretary shall communicate decisions of the State GRC to the complainant in writing. The copy of the communication shall be kept with the state GRC Secretary as record. • The recommendations shall be implemented immediately • Upon completion of the recommended actions, the state GRC Secretary shall prepare a report on the closure of the complaint which will be signed by the complainant and state GRC Chairperson. A copy of the same shall be kept for record.

102. The structure and process of GRM is presented below for detailed understanding 93

Figure 25: Structure and Process of GRC

C. Monitoring and Evaluation systems of GRM

103. All grievances, concerns and complaints received shall be recorded by concerned authorities to be tracked. The status of the grievances shall be discussed in the review meetings organized at PIU and PMU level. The following indicators shall be monitored and recorded - Number and type of complaints received; - Number and % of complaints that have been resolved; - Number and % of complaints that are unresolved;

104. The State GRC shall review grievance related data on monthly basis to evaluate the functionality of the system, as well as to note the followings: • Failures to follow GRM procedures; • Delays in complaint resolution, particularly those that can affect project construction; • Most frequent types of grievances and complaints; • Location(s) producing the most grievances and complaints;

94

D. Action Plan for the formation of the GRM

S. No Action Plan Time Line A Action required at PMU/PMC A1 Letter for formation of GRC and follow up Pre -construction A2 Development of GRM Manual Pre -construction A3 Orientation of GRC members by integrating with Construction training/workshops/meetings A4 Integration of GRC topic in BCC – like availability of GRC Construction and its procedure A5 Review of functioning of GRC by integrating with meetings Construction and visits B Action at Town level B1 Formation of GRC at town level and inform to the PMU/PMC Pre -construction B2 Information to All ULB Officials/Public about existence of Construction GRC, its committee members and their function B3 Orientation of all GRC members during visit of PMU and Construction PMC officials B4 Tracking of complaint registered and its status Construction B5 Sharing status of grievances with PIUs with the help of GRC Construction person B6 Training of selected women to maintain grievances at Construction customer service center (Educated Prerak (Motivator) may be considered) B7 Complaint management Operation and maintenance phase

VIII. ENVIRONMENTAL MANAGEMENT PLAN

A. Implementation Arrangements

105. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with flexibility to redeployment depending upon the implementation requirements.

106. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

107. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno-economic 95 feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

108. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build-operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

109. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

110. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

B. Environmental Management Plan

111. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

112. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

113. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

114. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

96

115. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

116. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring. 97

Table 21: Design Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Implementation Funds Design of Unsustainable • Discontinuation of current unsustainable ground water source/Untreated These measures are Part of project costs water supply source; water supply system and creating new water system based on a nearest already included in the system resource & surface water source; Jamni River for Jeron Khalsa and Lidhora Khas preliminary designs. energy use GWSS and for Kari WSS the same River is used as a water source at different intake location. DBO Contractor • Recovering wash water from treatment process (DBOC)to follow, • Treatment and reuse of sludge from treatment process enhance where • Minimizing water losses from pipelines by perfect jointing and alignments possible. using appropriate techniques

• Designing the entire system to maintain optimal flow and terminal pressure, PMU to ensure and optimizing the overall energy usage compliance. • Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies • Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor • Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections • Using low-noise and energy efficient pumping systems • During the design, construction, and operation of the project, apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines7 and Sector Specific (Water and Sanitation) Guidelines8). Water Project • Obtain permission from Water resources department, GoMP PMU & respective No costs; scope of IA o Jeron Khalsa and Lidhora Khas GWSS- permission / water

7https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 8 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

98

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Implementation Funds abstraction sustainability & allocation for water abstraction from Jamni River and construction of Nagar Parishads from Jamni water use intake with Increasing height of existing weir by 1.5 m at Jamni River (process already River for Both conflicts near milanghat is proposed. initiated) o Kari WSS permission / water allocation for water abstraction from Scheme – Jamni and construction of weir and intake. Waste Environmental • Obtain consent from MPPCB for both WTPs for Jeron Khalsa and PMU / Nagar No costs; scope of IA generation pollution Lidhorakhas GWSS, Kari WSS prior to start of construction Parishad; DBOC to & DBO from WTPs prepare application, operations and assist as required Chlorine Chlorine • Provide the following measure at the chlorine application unit: These measures are Project Costs usage as handling & o Chlorine neutralization pit with a lime slurry feeder already included in the disinfectant at application risk o Proper ventilation, lighting, entry and exit facilities preliminary designs. WTPs – health & o Facility for isolation in the event of major chlorine leakage (if needed) safety risk to o Personal protection and safety equipment for the operators in the DBOC to follow, workers and chlorine plant enhance where general public o Provide training to the staff in safe handling and application of chlorine; possible. this shall be included in the contract of Chlorinator supplier o Supplier of Chlorinator equipment shall provide standard operating PMU to ensure manual for safe operation and as well as maintenance and repairs; compliance. preferably these shall be provided both in English and Hindi Languages

Table 22: Pre-Construction State Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds EMP Implementation Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator (among DBO contractor Cost for & reporting compliance to EMP the technical staff) in each town implementation • Ensure that all pre-construction activities are complete prior to start of of mitigation construction work measures • Ensure timely submission of monitoring reports responsibility of • Updated IEE / site specific EMP will be submitted contractor. • “Works cannot be commenced until the contractor submits Site-

99

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds specific Health and Safety Plan including Health and Safety COVID- 19 Plan (HSCOVID 19) and PIU/PMU approves” Utilities Damage/ • Identify and include locations of utilities in the detailed DBOC with PIU Project costs – disturbance to designs/drawings to prevent unnecessary disruption of services collaboration. general telephone lines, • Prepare a contingency plan to include actions to be taken in case of PMU to ensure construction electric lines, water unintentional interruption of services. compliance practice lines in project area Construction works Disturbance / • No construction material storage/ancillary works shall be conducted in DBOC with PIU Project costs – near forest areas damage to forest the forest area; this shall be limited to actual construction area and collaboration. general areas, wildlife the access roads construction • No labour camps shall be located near forests (maintain minimum PIU/ PMU to practice 1km buffer) ensure • Limit the work to daylight hours only; no work after sunset compliance • No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals • Create awareness among workers on environment & safety • No high noisy works shall be conducted • Barricade the construction area properly so that no wild animals entre the work area Construction works on Degradation of river • Do not disturb river bed except the actual work area; no equipment, DBOC to follow Project costs – river bed (weir and course and machinery shall be operated outside the work area general intake well) pollution • Avoid use of fuels, chemicals & lubricants; ensure no spillage PIU/ PMU to construction • Clean up the area after the completion & prior to the onset of ensure practice monsoon flow compliance Construction work Conflicts with local • Prioritize barren, waste, infertile, vacant lands within the area, DBOC to identify Part of project camps, stockpile community; • Shall not be located in productive agricultural lands, water bodies, locations following costs areas, storage areas disruption to traffic natural drainage channels, flood plains & groundwater recharge the criteria and waste disposal flow and sensitive areas, forests, vegetative lands, etc. areas receptors • Locate at sites that will not promote instability, flooding and result in PIU to ensure compliance and

100

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds destruction of natural drainage, vegetation, irrigation, & drinking water approve supply; • For private lands, obtain land owner’s (not lessees) written consent; indicate the requirement for reinstatement to original • Site should have a minimum buffer of 0.5 – 1 km from all socially, environmentally sensitive areas (eg., residential, socio-cultural areas & water bodies (0.5 km), forests (1km), etc.,) • Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. • Document site’s pre-project conditions Sources of Materials Extraction of • Obtain material only existing borrow sites/quarries already permitted DBOC to identify Part of project materials can by the Department of Mines and Geology; sources that have costs disrupt natural land • If new quarries sites/quarries are necessary, contractor shall be all permits, if contours and obtain all necessary permissions as per the law in force. required, obtain vegetation resulting • Contractor to obtain construction materials only after written permits, and in accelerated permission / approval of PIU for respective sources submit to PIU erosion, • Maintain a construction material register at the site disturbance in PIU to check and natural drainage approve patterns, ponding and water logging, and water pollution.

Consents, permits, Failure to obtain • Obtain all necessary consents, permits, clearance, NOCs, etc PMU / PIU to Part of project clearances, NOCs, necessary required for the project prior to award of contact or start of civil works, obtain project costs etc. consents, permits, as necessary. clearances; DBOC NOCs, etc. can to provide result to design • Include in detailed designs, drawings and documents all regulatory necessary revisions and/or conditions and provisions, where required assistance stoppage of works • Contractor to identify & obtain all necessary approvals, including in

101

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds compliance with labour laws, before start of construction;

• Contractor to acknowledge in writing to PIU and provide copies of all DBOC to obtain obtained permits, clearance, NOCs, etc. construction permits & PIU to ensure

Health risk due to • Obtain details from PHED/NPs on location of underground AC pipes DBOC in Part of project Asbestos Cement exposure to • Locate the new piper carefully to avoid encountering AC pipes coordination with costs Pipes asbestos materials • Leave the AC pipes undisturbed in the ground. PIU and ULB

Table 23: Construction Stage Environmental Management Plan Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation EMP Implementation Irreversible impact to • Project manager and all key workers will be DBOC Cost of EMP Implementation Training the environment, required to undergo training on EMP Orientation Training to workers, and implementation including spoils/waste PMC Construction contractor is responsibility of community management, Standard operating procedures and Environmental PMU. (SOP) for construction works; occupational Specialists to conduct health and safety (OH&S), core labor laws, the training Other costs responsibility of applicable environmental laws, etc. contractor. Air Quality Emissions from • Control dust by water sprinkling on exposed DBO Contractor Cost for implementation of construction vehicles, soil, stock stockpiled material on site mitigation measures equipment, and • Barricade area, provide wind sheets responsibility of contractor. machinery used for • Use tarpaulins to cover sand and other loose installation of pipelines material when transported by trucks; Air quality monitoring costs are resulting to dusts and • Clean wheels and undercarriage of haul trucks included in the EMP costs of increase in prior to leaving construction site project concentration of • Prevent entry of traffic, public in construction vehicle-related area

102

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation pollutants such as • Fit all heavy equipment, and machinery with air carbon monoxide, sulfur pollution control devices which are operating oxides, particulate correctly; all the vehicle shall meet the emission matter, nitrous oxides, norms and shall have valid pollution under and hydrocarbons. control (PUC) certificate. • Conduct air quality monitoring as per the monitoring plan. Surface water quality Mobilization of settled • Avoid earthworks during the rainy season DBO Contractor Cost for implementation of silt materials, and • Avoid stockpiling of earth fill especially during mitigation measures chemical contamination the monsoon season unless covered by responsibility of contractor. from fuels and tarpaulins or plastic sheets; lubricants during • Reuse excess spoils & materials in the Water quality monitoring costs installation of pipelines construction as far a possible are included in the EMP costs can contaminate nearby • Identify disposal sites prior to construction & of project surface water quality. dispose construction waste only at designated areas • Install temporary silt traps basins along the drainage leading to the water bodies; • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Conduct surface quality inspection according to the Environmental Management Plan (EMP). Weir & Intake setup works Pollution of River/dams • Select a construction methodology that is least DBO contractor Cost for implementation of in Jamni River for Jeron due to weir and Intake disturbing, and appropriate for the in-situ soil mitigation measures Khalsa, Lidhora Khas & well condition, and able to complete the construction responsibility of contractor. Kari towns work prior to onset of monsoon • Schedule the construction works in river bed Water quality monitoring costs during summer where there is no flow / low are included in the EMP costs water level period – late winter months to pre of project monsoon (February – June/July); ensure that works are completed during the same period to

103

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation prior to onset of monsoon; confirm with dam authorities on release of water; avoid scheduling the works during water release period. • Do not disturb river bed except the actual work area; no equipment, machinery shall be operated outside the work area • Erect temporary barriers to form enclosed construction area with least disturbance • Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond • Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage • Clean up the area after the completion & prior to the onset of monsoon flow Noise Levels Increase in noise level • Conduct noise generating activities (eg, cc road DBO Contractor Cost for implementation of due to earth-moving cutting) during day time mitigation measures and excavation • Minimize noise from construction equipment (by responsibility of contractor. equipment, and the using vehicle silencers, fitting jackhammers transportation of with noise-reducing mufflers, and use portable equipment, materials, street barriers to minimize sound impact to and people surrounding sensitive receptor; • Maintain maximum sound level not exceeding 80 decibels (DBA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; • Consult local communities in advance to avoid

104

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation working at sensitive times, such as religious and cultural festivals. Landscape and aesthetics Impacts due to excess • Stockpiles, lubricants, fuels, and other materials DBO Contractor Cost for implementation of excavated earth, should be located away from steep slopes and mitigation measures excess construction water bodies; responsibility of contractor. materials, and solid • Avoid stockpiling any excess spoils; dispose waste such as removed immediately to designated areas concrete, wood, • Domestic solid waste generated at construction packaging materials, camps and work sites shall be properly empty containers, managed (collected, segregated, disposed spoils, oils, lubricants, properly); waste should not burned and other similar items. • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed through approved recyclers • Environmentally restore the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Resources – Loss of vegetation and • Avoid removal of vegetation / tree cutting DBO Contractor Cost for implementation of Terrestrial tree cover • If unavoidable, minimize as far as possible, and mitigation measures obtain tree-cutting permit responsibility of contractor. • Plant 10 trees for every one cut Land use Environmental Issues • The impact due to change in land use is Not applicable Not applicable due to land use change negligible due to this project. Accessibility Traffic problems and • Confine work areas along the roads to the DBO Contractor Cost for implementation of conflicts near project minimum possible extent; all the activities, mitigation measures locations and haul road including material & waste/surplus soil stocking responsibility of contractor. should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately remove from site/ or brought to the as and when required

105

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; • Schedule transport and hauling activities during non-peak hours; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids • Notify affected area by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. • For works in very narrow roads o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio-Economic – Impede the access of • Schedule the construction activities in areas DBO Contractor Cost for implementation of

106

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation Income. residents and where weekly market is organized in discussion mitigation measures customers to nearby with the local body so that work is not responsibility of contractor. shops conducted on those days, and sites are cleared in the area before the weekly market • Do not obstruct access; provide temporary access, by leaving spaces in excavation, provide walkways and metal sheets for people and vehicles where necessary to continue business • Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules Socio-Economic – Generate temporary • Employ local persons in construction work if DBO Contractor Cost for implementation of Employment employment and manpower is available mitigation measures increase in local responsibility of contractor. revenue Occupational Health and Occupational hazards • Comply with all national, state and local core DBO Contractor Cost for implementation of Safety which can arise during labor laws (see Appendix 7 of this IEE) mitigation measures work • Following internationally recognized health and responsibility of contractor. safety standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines9 and Sector Specific (Water and Sanitation) Guidelines10). • A detailed guidance for Safety from COVID-19 Pandemic during construction works is provided in Appendix 15 - Guideline for Construction

9https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 10 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

107

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation work about safety from COVID-19 Pandemic (SOP – Health & Safety Plan). • Develop and Implement site-specific occupational health and safety (OH&S) plan which will include measures, such as the following; • Provided personal protective equipment (PPE) to workers(like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used • Conduct OH&S training workers/staff • Do no employ ad-hoc work procedures, follow best & acceptable work practices • Document work-related accidents • Provide qualified & easily accessible first-aid facilities all times at all sites • Secure all installations from unauthorized intrusion and accident risks; • Provide potable drinking water; • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers; • Ensure that visitor/s do not enter hazard areas unescorted • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;

108

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • Ensure moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively. COVID 19 Response Spread of infection, • In view of the prevailing COVID-19 pandemic, DBO Contractor & Contractor costs adverse impact on the contractors and workers shall need to take Monitoring of health of workers, staff additional measures to avoid the spread of the Mitigation by PIU and community disease and shall follow various guidelines/guidance notes issued by the national/state governments and international organizations such as WHO, ILO, etc., from time to time. • Contractor shall prepare a site-specific Health and Safety COVID-19 Pan (HS COVID-19 Plan) in accordance with the government policy, legislation and regulatory requirements on COVID-19 prevention and control. In the absence thereof, the HS COVID-19 Plan should be updated in accordance with international good practice guidelines issues by agencies like World health organization (WHO), International Labour Organization, etc.,

109

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • The HS COVID-19 Plan must be approved by the PMU prior to commencement of works. Appendix 15 provides a basic COVID-19 health and safety plan. • The contractor shall submit a fortnightly monitoring and progress report to PIU on implementation of HS COVID-19 Plan. Community Health and Traffic accidents and • Plan routes to avoid times of peak-pedestrian DBO Contractor Cost for implementation of Safety. vehicle collision with activities and high risk areas. mitigation measures pedestrians during • Prevent public entry in to work areas through responsibility of contractor. material and waste barricading and security guards transportation • Maintain regularly the vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities. • In very narrow streets, conduct work section- wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) Work Camps and Temporary air and • Establish camps only after site approval DBO Contractor Cost for implementation of worksites noise pollution from • Avoid cutting of trees/ clearing bushes mitigation measures machine operation, • Provide adequate drinking water, water for responsibility of contractor. water pollution from other uses, and sanitation facilities storage and use of • Ensure conditions of livability at work camps fuels, oils, solvents, and are maintained at the highest standards lubricants possible at all times; • Prohibit employees from poaching wildlife and Unsanitary and poor cutting of trees for firewood; living conditions for • Train employees in the storage and handling of workers materials which can potentially cause soil

110

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas; • Ensure unauthorized persons specially children are not allowed in any worksite Post-construction clean- Damage due to debris, • Remove all spoils wreckage, rubbish, or DBO Contractor Cost for implementation of up spoils, excess temporary structures (such as buildings, mitigation measures construction materials shelters, and latrines) which are no longer responsibility of contractor. required • All excavated roads shall be reinstated to original condition. • All disrupted utilities restored • All affected structures rehabilitated/compensated • The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regressed • The contractor must arrange the cancellation of all temporary services. • Restore the work sites to pre-project conditions; PIU to approve in writing that site is restored

111

Table 24: Operation Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds Check for blockage and Loss of water, increased • Effective leak detection and water auditing to DBO Contractor PIU and Operating leakage problems demand and reduce the water losses respective Nagar costs reducing the water inconvenience to Parishads of losses consumers & general Package 6H public Water contamination – Impacts on public health • Ensure protection of water source quality Respective Nagar PMU in Operating raw water (Jamni), any entry of wastewater into the river Parishads of coordination with costs contamination at source upstream of sites should be prevented. Package 6G WRD and treated water • Contamination of treated water during during transmission transmission and distribution should be DBO Contractor PIU and prevented by quickly identifying, isolating and respective Nagar repairing the leak section. Develop a system of Parishads of leak detection and rectification. Package 6H • Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 12) Discharge the Pollution of streams • Backwash water will be recirculated so no DBO Contractor PIU and Operating impurities and other /drains wastewater generated from WTPs respective Nagar costs solids collected due to • Maintain the mechanical parts as per the Parishads of filtration and back wash maintenance plan to avoid any hazards Package 6H

Sludge generation Land and water • Collect the sludge from WTP units, dry in sludge DBO Contractor PIU and Operating pollution, impacts on drying beds, and reuse / dispose safely as per respective Nagar costs health & environment the design Parishads Increased in sewage Water pollution, and • Sanitation facilities needs to be improved at Respective Nagar PMU To be generation impacts on public health community level and at the town level to meet Parishads of identified - and environment the increased sewage demand Package 6G respective NPs Generation of waste Impacts on public health • Collect solid wastes and dispose to approved DBO Contractor PIU and Operating

112

Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds materials and environment disposal yards respective Nagar costs Parishads Occupational health Health, social and • Provide appropriate PPE to workers & training DBO Contractor PIU and Operating and safety economic impacts on the on its proper use respective Nagar costs workers • Use fall protection equipment when working at Parishads of heights. Package 6H • Maintain work areas to minimize slipping and tripping hazards. • Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures. • Prepare escape plans from areas where there might be a chlorine emission. • Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. • Prohibit eating, smoking, and drinking except in designated areas.

Table 25: Construction Stage Environmental Monitoring Plan Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & Source of Funds location

113

Construction disturbances, All work sites Implementation of dust Regularly as required Supervising staff Part of TOR of PIU, PMC and nuisances, public & worker control, noise control, traffic during construction; and safeguards PMU safety management, & safety checklist to be filled specialists measures. monthly once Site inspection checklist to review implementation is appended at Appendix 13

Ambient air quality 5 locations • PM10, PM2.5 NO2, SO2, Once before start of DBO Contractor Cost for implementation of (1locations in CO construction monitoring measures each town at Quarterly (yearly 4-times) responsibility of contractor distribution work during construction (45 samples x 5000 per sample site: and at WTP (2year period =225,000) site) considered)

Ambient noise 5 locations • Day time and night time Once before start of DBO Contractor Cost for implementation of (1locations in noise levels (24 hours) construction monitoring measures each town and one Quarterly (yearly 4-times) responsibility of contractor at WTP) during construction (45 samples x 1500 per sample (2year period =67500) considered) Surface water quality 4 locations • pH, Oil & grease, Cl, F, Once before start of DBO Contractor Cost for implementation of (upstream and NO3, TC, FC, construction and monitoring measures down Stream of Hardness, Turbidity monthly during responsibility of contractor work site in Jamni BOD, COD, DO, Total construction (12 months (52 samples x 4000 per sample = River for both the Alkalinity period considered) 208,000) group schemes and Kari WSS)

114

Table 26: Operation Stage Environmental Monitoring Plan Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & location Source of Funds Source water quality Near intake point pH, Cl, F, NO3, TC, FC, Hardness, Turbidity Yearly DBO O&M costs in Jamni river (for BOD, COD, DO, Total Alkalinity twice (pre & Contractor both Schemes) heavy metals & pesticides post monsoon) Monitoring of quality Consumer end- pH, Nitrite, Nitrate, Turbidity, Total Alkalinity, Monthly DBO O&M costs of water supplied to random sampling Total coliform and Feacal coliform once Contractor consumers in all zones Sludge quality and WTP Analysis for concentration of heavy metals and Yearly once DBO O&M costs suitability as manure confirm that values are within the following limits Contractor (all units are in mg/kg dry, except pH) • Arsenic - 10.00, • Cadmium - 5.00 • Chromium - 50.00 • Copper - 300.00 • Lead - 100.00 • Mercury - 0.15 • Nickel - 50.00 • Zinc - 1000.00 • PH - 5.5-8.5

115

C. EMP Compliance Responsibilities

117. PMU Responsibilities. PO (Environment) supported by PMC, which staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this sub project include the following: Bidding stage:

(i) Prior to invitation of bids for civil works contract, ensure that

a. Water Resources Department (WRD) permission is obtained for sourcing water from Jamni River. b. Consent for establishment (CFE) is obtained from MPPCB for WTP construction.

(ii) Ensure that EMP is included in bidding documents and civil works contracts. (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labour laws and core labour standards including:

a. Labour welfare measures and provision of amenities b. prohibition of child labour as defined in national legislation for construction and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labour; e. The requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP is included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirements to the bidders

Construction stage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained 116

(vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

Operation stage:

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

118. PIU Responsibilities. PIU headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU given additional responsibilities of safeguard tasks and designated as Assistant Environmental Officer (ASO). ASO supported by PMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following: (i) Provide necessary support to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way (iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timely manner as per the EMP

Contractor’s responsibilities. Bidding stage:

(ii) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,) (iii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design stage:

(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals.

117

(v) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.

Construction stage:

(i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work. (ii) Mobilize EHS officer prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit: a. Construction waste management (CWM) plan b. Traffic management (TM) plan (v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation stage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report

D. Training Needs

119. The following Table 27 presents the outline of capacity building program to ensure EMP implementation. The estimated cost is Rs. 275,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC.

118

Table 27: Outline Capacity Building Program on EMP Implementation Description Target Participants& Estimate Cost and Source Venue (INR) of Funds 1. Introduction and Sensitization to All staff and - Included in the Environmental Issues (1 day) consultants involved in overall program - ADB Safeguards Policy Statement the project cost - Government of India and Madhya Pradesh applicable safeguard laws, regulations and At PMU, Bhopal policies including but not limited to core (combined program for labor standards, OH&S, etc. all subprojects) - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning 2. EMP implementation (1/2 day) All PIU staff, - Part of overall - EMP mitigation & monitoring measures contractor staff and program costs – -Roles and responsibilities consultants involved in PMC will conduct - Public relations, - Consultations the Package 6H towns at PIU office - Grievance redress subproject - Monitoring and corrective action planning Part of scope of - Reporting and disclosure At PIU work of PMU, PIU, - Construction site standard operating PMC & DBOC procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers (1/2 Once before start of - Contractors cost day) work, and thereafter - Environment, health and safety in project regular briefing every construction month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

E. Monitoring and Reporting

120. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs.

121. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works.

119

122. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 14). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

123. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi-annual (6-monthly) Environmental Monitoring Reports (EMR). Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites. 124. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB’s monitoring and supervision activities will be commensurate with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

F. EMP Implementation Cost

125. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 31.50 million, which are to be covered by contractor costs. Table 28: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs Number (INR) (INR) Covered By A Implementation . staff 1 EHS Supervisor Constructio per 24 50,000 1,200,000 DBO n month contract Subtotal (A) 12,00,000 B Mitigation . Measures 1 Consent for Pre- Lump 150,000 Project establishments & constructio sum costs consent for n operation from MPPCB 2 Provision for tree Constructio Per 100 1,000 100,000 DBO cutting & n tree contract compensatory plantation measures

120

Particulars Stages Unit Total Rate Cost Costs Number (INR) (INR) Covered By 3 Traffic Constructio Lump - - 900,000 DBO management at n sum – contract work sites 6 towns (Pavement Markings, Channelizing Devices, Arrow Panels and Warning Lights) Subtotal (B) 11,50,000 C Monitoring . Measures 1 Air quality Constructio / 81 5,000 DBOC monitoring n sample 225,000 2 Noise levels Constructio / 81 1,500 DBOC monitoring n sample 67500 3 Surface water Constructio / 39 4,000 DBOC monitoring n sample 208000 4 Water and Operation LS / yr - - 300,000 DBO sludge Subtotal (C) 800,500 Subtotal (D) - Total (A+B+C) INR 31,50,500

121

IX. CONCLUSION AND RECOMMENDATIONS

126. The process described in this document has assessed the environmental impacts of all elements of the Package 6H town’s water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

127. Potential impacts were identified in relation to location, design, construction and operation of the improved infrastructure. Environmental impacts as being due to the project design or location are not significant. The proposed two water supply schemes (one combined scheme for Jaron Khalsa and Lidhorakhas and the other for Kari town) includes design of new water source with nearest surface water body, that include construction of a new weir across River Jamni for Kari town, just upstream of existing weir, and increase of height of existing weir across Jamni River for the combined scheme. Jamni River is identified as nearest feasible and sustainable source for water supply of project towns. Considering good water availability and very small demand, it is assessed to be unlikely to have any significant issue of source sustainability.

128. Existing weir height is proposed to be increased from 3.0 m to 4.5 m to storage adequate water to meet the demand of two towns of Jaron Khalsa and Lidhorakhas. For Kari town, the existing weir of 2.5 m high is not in good condition and therefore proposed to construct a new weir of height 3.5 m just upstream of the existing weir.

129. Total length of the river is 201 km, and is non-perennial and flows only during part of the year. It flows for about 4months, mostly during monsoon and winter seasons, from early July to October. No flow data is available as there is river no gauging station on the river. Weirs and storage reservoir required for the lean / no flow season. The water demand of Kari town is 1.56 MLD or 0.569 MCM per year, while total available water based on catchment area and rainfall analysis is 169 MCM. The abstraction is just about 0.34 % of water available. The proposed yearly water abstraction for combined scheme of Jaron Khalsa and Lidhorakhas is 1.0877 MCM, which is just a fraction (about 0.3%) of total yearly water availability in the catchment (i.e.357.80 MCM).

130. Considering this negligible proportion of water abstraction, no notable impacts are anticipated in the downstream due to reduction in flow. There are already existing several existing dams/weirs on the river. Construction of a new weir just upstream side of the existing weir and increasing the height will not significantly alter the existing flow regime. Given intermittent nature of river, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. At the proposed weir location, the riverbanks are higher than and the proposed weir height. Therefore, the water storage is confined to river course / flood plain, and there is no submergence of lands outside the river. No negative impacts or acquisition of government of private or government lands anticipated.

131. Project area mostly comprises urban areas, agricultural areas of Kari, Jeron Khalsa and Lidhorakhas. None of the project components are located in the forest areas. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the 122 disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in rive, there is a risk of water contamination, river bed damage, etc.. Appropriate measures are suggested.

132. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period.

133. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

134. The project’s grievance redress mechanism will provide the citizens with a platform to redress of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

135. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

136. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

137. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community liability in Package 6G towns.

138. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction from Jamni River, and; (ii) Consent for Establishment (CFE) and Consent for Operation (CFO) for WTPs from MPPCB. These permissions/approvals shall be obtained.

139. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

123

Appendix 1: REA Check list

Instructions: ❑ This checklist is to be prepared to support the environmental classification of a project. It is to be attached to the environmental categorization form that is to be prepared and submitted to the Chief Compliance Officer of the Regional and Sustainable Development Department. ❑ This checklist is to be completed with the assistance of an Environment Specialist in a Regional Department. ❑ This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB checklists and handbooks on (i) involuntary resettlement, (ii) indigenous peoples planning, (iii) poverty reduction, (iv) participation, and (v) gender and development. ❑ Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.

A) Country/Project Title: India / Madhya Pradesh Urban Services Improvement Program – Jeron Khalsa and Lidhorakhas Group WSS- Package 6H towns Water Supply Subproject Sector Division: Urban Development

SCREENING Yes No REMARKS QUESTIONS Water Supply A. Project Siting is the project area… ▪ Densely  Subproject activities extend to the entire towns including the densely populated? populated areas. There are no major negative impacts envisaged, because pipeline will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses, and commercial establishments. In narrow streets, disruption to road users is likely, and measure like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. ▪ Heavy with  - development activities? ▪ Adjacent to or  within any environmentally sensitive areas? • Cultural heritage  site • Protected Area  • Wetland  • Mangrove  • Estuarine  • Buffer zone of  protected area • Special area for  protecting biodiversity • Bay  124

B. Potential Environmental Impacts Will the Project cause… • Pollution of raw water supply  There are no significant water pollution sources in the catchment. from upstream wastewater Raw water quality is tested and found that it is suitable for discharge from communities, domestic use industries, agriculture, and soil erosion runoff? • Impairment of  Not applicable historical/cultural monuments/areas and loss/damage to these sites? • Hazard of land subsidence  Not applicable; subproject does not involve groundwater caused by excessive ground abstraction water pumping? • Social conflicts arising from  Project does not involve land acquisition /displacement. No social displacement of conflicts envisaged communities? • Conflicts in abstraction of  No; the water will be abstracted only with due permission of raw water for water supply government and allocation of water from Jamni River for water with other beneficial water supply of Group WSS. uses for surface and ground waters? • Unsatisfactory raw water  Raw water quality is tested and found that it is suitable for supply (e.g. excessive domestic use. pathogens or mineral constituents)? • Delivery of unsafe water to  Water will be treated and disinfected prior to supply distribution system? • Inadequate protection of  Water is abstracted from Jamni River. There are no major intake works or wells, polluting sources in the catchment. leading to pollution of water supply? • Over pumping of ground  - water, leading to salinization and ground subsidence? • Excessive algal growth in  Regular cleaning of storage tanks will be conducted during storage reservoir? operation • Increase in production of  Sewerage system is also being planned for project towns under sewage beyond capabilities different schemes. of community facilities? • Inadequate disposal of  Appropriate provisions for sludge drying and disposal is included sludge from water treatment in the project plants? • Inadequate buffer zone  - around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?

125

• Impairments associated with  - transmission lines and access roads? • Health hazards arising from  Measures for safe handling of chlorine are included inadequate design of facilities for receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to  Measures for safe handling of chlorine are included workers from the management of chlorine used for disinfection and other contaminants? • Dislocation or involuntary  There is no resettlement of people for project implementation. resettlement of people • Social conflicts between  The contractor will be utilizing the local labour force as far as construction workers from possible; in case if it is unavoidable, labour camps and facilities other areas and community will be provided appropriately. No conflicts envisaged workers? • Noise and dust from  All the construction machineries employed will comply with noise construction activities? emission standards of Central Pollution Control Board. Dust suppression measures such as water sprinkling will be employed • Increased road traffic due to  Excavation and laying pipelines along public roads will interfere interference of construction with the traffic. Construction material transport will increase activities? traffic within city. Proper traffic management and construction planning will be ensured to minimize the interference • Continuing soil erosion/silt  Construction work during monsoon shall be carried out with due runoff from construction care so that silt run off due to construction operation is operations? prevented. No construction will be allowed during rains. • Delivery of unsafe water due  No; appropriate O&M will conducted to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to  Not envisaged distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of  Measures for safe handling of chlorine are included chlorine gas? • Excessive abstraction of  Water abstraction will be limited to the allocated quantity for water affecting downstream Group WSS water users? • Competing uses of water?  Water abstraction will be limited to the allocated quantity for

126

Group WSS • Increased sewage flow due  Water Demand calculation of all the town are taken as 70 LPCD. to increased water supply • Increased volume of sullage  Water Demand calculation of all the town are taken as 70 LPCD. (wastewater from cooking and washing) and sludge from wastewater treatment plant

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Is the Project area subject to hazards such as earthquakes, floods, √ Semi-arid zone, unreliable landslides, tropical cyclone winds, storm surges, tsunami or rainfall, less vegetation cover. volcanic eruptions and climate changes? Promote more efficient use of water by reducing losses and wastage to counter increased demands due to higher temperatures. Could changes in temperature, precipitation, or extreme events √ Reduction in rainfall may patterns over the Project lifespan affect technical or financial affect the water availability sustainability (e.g., changes in rainfall patterns disrupt reliability of from river/dam. Given the water supply; sea level rise creates salinity intrusion into proposed priority for drinking water water supply source)? supply, dead storage will be utilized in case of low rain fall years

Are there any demographic or socio-economic aspects of the √ No Project area that are already vulnerable (e.g.,high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)?

Could the Project potentially increase the climate or disaster √ No vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

127

B) Country/Project Title: India / Madhya Pradesh Urban Services Improvement Program – Kari WSS- Package 6H towns Water Supply Subproject Sector Division: Urban Development

SCREENING QUESTIONS Yes No REMARKS

Water Supply

A. Project Siting Is the project area…

▪ Densely populated?  Subproject activities extend to the entire towns including the densely populated areas. There are no major negative impacts envisaged, because pipeline will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses, and commercial establishments. In narrow streets, disruption to road users is likely, and measure like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. ▪ Heavy with development  - activities?

 ▪ Adjacent to or within any environmentally sensitive areas?

• Cultural heritage site 

• Protected Area 

• Wetland 

• Mangrove 

• Estuarine 

• Buffer zone of protected area   • Special area for protecting biodiversity

• Bay 

128

B. Potential Environmental Impacts Will the Project cause… • Pollution of raw water supply  There are no significant water pollution sources in the catchment. from upstream wastewater Raw water quality is tested and found that it is suitable for discharge from communities, domestic use industries, agriculture, and soil erosion runoff? • Impairment of  Not applicable historical/cultural monuments/areas and loss/damage to these sites? • Hazard of land subsidence  Not applicable; subproject does not involve groundwater caused by excessive ground abstraction water pumping? • Social conflicts arising from  Project does not involve land acquisition /displacement. No social displacement of conflicts envisaged communities? • Conflicts in abstraction of  No; the water will be abstracted only with due permission of raw water for water supply government and allocation of water from Jamni River for water with other beneficial water supply of Group WSS. uses for surface and ground waters? • Unsatisfactory raw water  Raw water quality is tested and found that it is suitable for supply (e.g. excessive domestic use. pathogens or mineral constituents)? • Delivery of unsafe water to  Water will be treated and disinfected prior to supply distribution system? • Inadequate protection of  Water is abstracted from Jamni River. There are no major intake works or wells, polluting sources in the catchment. leading to pollution of water supply? • Over pumping of ground  - water, leading to salinization and ground subsidence? • Excessive algal growth in  Regular cleaning of storage tanks will be conducted during storage reservoir? operation • Increase in production of  Sewerage system is also being planned for project towns under sewage beyond capabilities different schemes. of community facilities? • Inadequate disposal of  Appropriate provisions for sludge drying and disposal is included sludge from water treatment in the project plants? • Inadequate buffer zone  - around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with  - transmission lines and

129

access roads? • Health hazards arising from  Measures for safe handling of chlorine are included inadequate design of facilities for receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to  Measures for safe handling of chlorine are included workers from the management of chlorine used for disinfection and other contaminants? • Dislocation or involuntary  There is no resettlement of people for project implementation. resettlement of people • Social conflicts between  The contractor will be utilizing the local labour force as far as construction workers from possible; in case if it is unavoidable, labour camps and facilities other areas and community will be provided appropriately. No conflicts envisaged workers? • Noise and dust from  All the construction machineries employed will comply with noise construction activities? emission standards of Central Pollution Control Board. Dust suppression measures such as water sprinkling will be employed • Increased road traffic due to  Excavation and laying pipelines along public roads will interfere interference of construction with the traffic. Construction material transport will increase activities? traffic within city. Proper traffic management and construction planning will be ensured to minimize the interference • Continuing soil erosion/silt  Construction work during monsoon shall be carried out with due runoff from construction care so that silt run off due to construction operation is operations? prevented. No construction will be allowed during rains. • Delivery of unsafe water due  No; appropriate O&M will conducted to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to  Not envisaged distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of  Measures for safe handling of chlorine are included chlorine gas? • Excessive abstraction of  Water abstraction will be limited to the allocated quantity for water affecting downstream Group WSS water users? • Competing uses of water?  Water abstraction will be limited to the allocated quantity for Group WSS • Increased sewage flow due  Water Demand calculation of all the town are taken as 70 LPCD.

130

to increased water supply • Increased volume of sullage  Water Demand calculation of all the town are taken as 70 LPCD. (wastewater from cooking and washing) and sludge from wastewater treatment plant

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Is the Project area subject to hazards such as earthquakes, floods, √ Semi-arid zone, unreliable landslides, tropical cyclone winds, storm surges, tsunami or volcanic rainfall, less vegetation cover. eruptions and climate changes? Promote more efficient use of water by reducing losses and wastage to counter increased demands due to higher temperatures. Could changes in temperature, precipitation, or extreme events √ Reduction in rainfall may patterns over the Project lifespan affect technical or financial affect the water availability sustainability (e.g., changes in rainfall patterns disrupt reliability of from river/dam. Given the water supply; sea level rise creates salinity intrusion into proposed priority for drinking water water supply source)? supply, dead storage will be utilized in case of low rain fall years

Are there any demographic or socio-economic aspects of the Project √ No area that are already vulnerable (e.g., high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)?

Could the Project potentially increase the climate or disaster √ No vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

131

Appendix 2: National Ambient Air Quality Standards

Sl Pollutants Time Concentration in ambient air Method of No: weighted Industrial, Ecologically measurement average Residential, Sensitive Rural & Other Areas Areas 1 Sulphur Dioxide Annual 50 20 Improved West and (SO2) 24 hours 80 80 Geake-Ultraviolet µg/m3 fluorescence 2 Nitrogen Dioxide Annual 40 30 Modified Jacob 3 (NO2) µg/m 24 hours 80 80 &Hochheiser (Na-Arsenite) Chemiluminescence 3 Particulate Matter Annual 60 60 Gravimetric (Size less than 10 24 hours 100 100 -TOEM µm) or PM10 -Beta attenuation µg/m3 4 Particulate Matter Annual 40 40 Gravimetric (Size less than 2.5 24 hours 60 60 -TOEM µm) or PM2.5 -Beta attenuation µg/m3 5 Carbon Monoxide 8 hours 02 02 Non Dispersive Infra Red (CO) mg/m3 1 hours 04 04 (NDIR) Spectroscopy

132

Appendix 3: Vehicle Exhaust Emission Norms 1. Passenger Cars Norms CO(g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles Norms CO(g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10 Bharat Stage-IV 1.5 0.96 3.5 0.02 Source: Central Pollution Control Board CO = Carbon Monixide; g/kmhr = grams per kilometer-hour; HC = Hydrocarbons; NOx = oxides of nitrogen; PM = Particulates Matter

133

Appendix 4: National Ambient Air Quality Standards In Respect Of Noise

Area code Category of area/zone Limit in dB (A) Day time Night time

A Industrial area 75 70

B Commercial area 65 55

C Residential area 55 45

D Silence zone 50 40

134

Appendix 5: Stakeholder Consultation Summary of Consultation in Kari Town Location No. of Participants Topics Discussed Issues Participants

Office of Total=28 Elected • Briefing on project • The Nagar Parishad not have ULB on representatives, objectives probable capacity or resource to be party in 22/06/2018 Male =26 Local Leaders, implementation sharing the loan repayment. Community procedures • The Elected Representatives of the Members and Present drinking water ULB expressed need for the project Female =02 • shopkeepers supply source and its and willingness to take itup; condition • The prime concern & • Potential positive and apprehensions of Elected negative impacts due to Representatives was regarding the project implementation project – whether it will be a financial burden to the Nagar • Land use and area to be Parishads. covered under the project Operation and maintenance of the Consultant • • facilities developed under the representatives visited project and community Kari Nagar Parishad for participation; explaining concept report and site visit for • During discussion, Elected finalization of source and Representatives also complained land availability details for about poor water supply in town. preparation of Detailed Some people even don’t have Project Report of Water water supply connection in their Supply Scheme home. • Some Elected Representatives also showed their apprehension about water tariff after new water supply scheme. • Possibility of exempting the poor and vulnerable from user charge payment. Bus Stand Total=14 Community • Status of existing drinking • The area has in sufficient and in Near Pond Members water supply system; adequate drinking wat er On dated M=14 • Need for improvements to supply . Water from tube 22/06/2018 present system; wells is presently supplied the area/community. The area • Relevant information of face severe water crisis during

the upcoming project the summer season when the and benefits of the ground water level drops. project. • The community welcomed the • Ensuring no income loss project and expressed need for it. However, they were apprehensive that their economic condition would prevent them from paying water user charges. • Community members h ow t h e i r willingness to take water connections but demanded relaxation in user charges. • People were briefed about the complaint redress mechanism

135

• People says that on bus stand heavy traffic and dusty area. Market Total=36 Shopkeeper’s • Background of water • Presently water supply in Kari is not supply subproject, adequate. 23/06/2018 M=36 Community Environmental, Social, • Most of the household does not have Members GRM, traffic safety issue, water connection. Temporary disruption of • People also concerned about the accesses and benefits employment during construction from the project were work. explained to the • Overall, people express their Stakeholders. gratitude for upcoming water supply project and promise to support the project. Status of Existing Water • • Some people also requested to Supply at town. minimize the water tariff • Few people willing to get training for • Proposed subproject employment opportunity components.

• Environment, Social and community impact during operation work

• Impact on health by proposed project

• Willing to take new Water connection

• Location of components of proposed water Supply scheme has been finalized with identification of government land.

• Potential positive and negative impacts due to project implementation Ensuring no income loss

• Attention of stakeholders drawn to the EMP, and explained to them how dust, and other construction issues will be managed.

• It was informed that night work will be explored during construction but may not be possible, however all measures

136

will be taken by contractor to avoid/minimize construction disturbances

Ward No. 1 Total=10 Community • Briefing on project • None of the people knew about Members objectives probable the proposed project. On learning 10/5/2018 M=05 implementation about the project, they expressed procedures that they were happy that the • Potential positive and entire community would be F=05 negative impacts due to benefited from the upgraded water project implementation supply. • Experiences sharing on - • Willingness to connect to piped livelihood activities, drinking water supply; Resettlement and Rehabilitation, women • Subsidy to the poor; whether empowerment, tribal community taps would be development, health, provided; education, convergence • Community participation in project with existing government implementation; social security schemes • Implementing agency; and better etc. /improved service. • People were briefed about the complaint redress mechanism Ward No. 2 Total=21 Community • Existing status of • The area has insufficient and Members drinking water supply, inadequate drinking water Near OHT M=12 need for project and resource. Water supply to the area demand from the is done through two tube wells that community; supplies water to the community 11/5/2018 F=09 • Existing drinking water people. The area faces severe supply quality by District water crisis during the summer Water Supply and season when the ground water Sanitation Sub-division level drops. Office; • The community willingly accepted • Upfront cash collection; the project. The community members expressed that their Area covered by the • economic situation would prevent project; them from paying water user • Status of existing charges. drinking water supply None of the people knew about the system; • proposed project. On learning • Need for improvements about the project, they expressed to present system; that they were happy that the entire • Potential positive and community would be benefited from negative impacts project the upgraded water supply. implementation; • Probable commencement of project • Local community’s work and duration –12 months response to the project including rainy season • Slum dwellers showed willingness to take water connections but demanded relaxation in user charges. • People were briefed about the complaint redress mechanism

137

Market Place Total=15 Shopkeepers and • Operation and • Shop keepers assured their full Community maintenance of the support to the Project and Ward No. 21 M=12 Members facilities developed assured full cooperation during under the project and the construction phase Street community participation; vendors and small shop owners 11/5/2018 F=03 • Possibility of exempting got agreed on temporary shifting the poor and vulnerable of Haats (to other road side were from user charge alignment is not proposed) during payment. excavation • The community willingly • It should be ensured that their accepted the project. business is not closed for the civil The community works ensuring no income loss members expressed that • The shop owners indicated that their economic situation they are willing to accept the would prevent them from project which is ultimately for the paying water user benefit of the community people; charges. (The men work • On learning about the project, as daily Labourer’s and they expressed that they were the women as happy that the entire community housewives).None of the would be benefited from the people knew about the upgraded water supply proposed project. On learning about the • People were briefed about the project, they expressed complaint redress mechanism. that they were happy • construction work can be put on that the entire hold on weekly market days community would be benefited from the upgraded water supply.

Consultation at kari town

138

Consultation Meeting With Nagar Parishad, Kari

Meeting With SC/ST Community in Ambedkar & Balmiki ward No. 07 & 08

139

Consultation with shopkeepers Market ward No. 04

Consultation Nagar Parishad Kari

140

Consultation with SC ST Ward 07,08, Abedkar Nagar

141

Summary of Consultation in Jeron Khalsa Town Location No. of Participants Topics Discussed Issues Participants Office of Total=24 Elected • Briefing on project • The Nagar Parishaddo not have ULB objectives probable capacity or resource to be party in Male 22 representatives, of implementation sharing the loan repayment. JeronKhalsa ULB, procedures • The Chairmanofthe ULB Present drinking water on Female 02 • expressed need for the project 30/06/2018 supply source and its and willingness to take it up; Community condition Members The prime concern & Potential positive and • • apprehensions of Elected negative impacts due to Representatives has regarding the project implementation project – whether it will be a • Land use and area to be financial burden to the Nagar covered under the project Parishads. • Consultant • Operation and maintenance of the representatives visited facilities developed under the JeronKhalsaNagar project and community Parishad for explaining participation; concept report and site • During discussion, Elected visit for finalization of Representatives also complained source and land about poor water supply in town. availability details for Some people even don’t have preparation of Detailed water supply connection in their Project Report of Water home. Supply Scheme • Some Elected Representatives also showed their apprehension about water tariff after new water supply scheme. • Possibility of exempting the poor and vulnerable from user charge payment Ward no.14 Total=20 Community • Status of existing drinking • The area has insufficient and Members water supply system; inadequate drinking water supply. Jeron M=18 F=02 • Need for improvements to Water from tube wells is KhalsaOn present system; presently supplied to the area/community. • Relevant information of The area faces ever water crisis 29/06/2018 the upcoming project • and benefits of the during the summer season when project. the ground water level drops. • The community welcomed the • Ensuring no income loss project and expressed need for it. However, they were apprehensive that their economic condition would prevent them from paying water user charges. • Community members showed their willingness to take water connections but demanded relaxation in user charges. • People were briefed about the complaint redress mechanism

142

Market Total=19 Shop Keepers • Background of water • Presently water supply in supply subproject, JeronKhalsais not adequate. 29/06/2018 M=07 Community Environmental, Social, • Most of the household does not Members GRM, traffic safety issue, have water connection. F=12 Temporary disruption of • People also concerned about the accesses and benefits employment during construction from the project were work. explained to the • Overall, people express their Stakeholders. gratitude for upcoming water supply project and promise to support the project. Status of Existing Water • • Some people also requested to Supply at town. minimize the water tariff • Few people willing to get training • Proposed subproject for employment opportunity components.

• Environment, Social and community impact during operation work

• Impact on health by proposed project

• Willing to take new Water connection

• Location of components of proposed water Supply scheme has been finalized with identification of government land.

• Potential positive and negative impacts due to project implementation Ensuring no income loss

• Attention of stakeholders drawn to the EMP, and explained to them how dust, and other construction issues will be managed. It was informed that night work will be explored during construction but may not be possible, however all measures will be taken by contractor to avoid/minimize construction disturbances

143

Ward No. 5 Total=10 Community • Briefing on project • None of the people knew about Near OHT Members objectives probable the proposed project. On learning M=05 implementation about the project, they expressed 10/5/2018 procedures that they were happy that the entire community would be F=05 • Potential positive and negative impacts due to benefited from the upgraded water project implementation supply. Willingness to connect to piped • Experiences sharing on - • livelihood activities, drinking water supply; Resettlement and • Subsidy to the poor; whether Rehabilitation, women community taps would be empowerment, tribal provided; development, health, • Community participation in project education, convergence implementation; with existing government Implementing agency; and better social security schemes • /improved service. etc. • People were briefed about the complaint redress mechanism Ward No. 2 Total=06 Community • Existing status of • The area has insufficient and Members drinking water supply, inadequate drinking water Near WTP M=06 need for project and resource. Water supply to the area demand from the is done through two tube wells that community; supplies water to the community 11/5/2018 • Existing drinking water people. The area faces severe supply quality by District water crisis during the summer Water Supply and season when the ground water Sanitation Sub-division level drops. Office; • The community willingly accepted • Upfront cash collection; the project. The community members expressed that their Area covered by the • economic situation would prevent project; them from paying water user • Status of existing charges. drinking water supply None of the people knew about the system; • proposed project. On learning • Need for improvements about the project, they expressed to present system; that they were happy that the entire • Potential positive and community would be benefited from negative impacts project the upgraded water supply. implementation; Local • Probable commencement of project community’s response to work and duration –12 months the project including rainy season • Slum dwellers showed willingness to take water connections but demanded relaxation in user charges • People were briefed about the complaint redress mechanism

144

Consultation in Ward No. 05

Consultation Meeting With Nagar Parishad,Jeron Khalsa

145

Meeting With SC/ST Community in Aadivasi Muhalla,Bhagat Singh ward No. 14

Meeting With Shopkeepers, Marchents in Market

146

Consultation with shopkeepers Market ward No. 04

Consultation Nagar Parishad Kari

147

Consultation in ward no. 14 BhagatSingh ward

148

Summary of Consultation in Lidorakhas Town Location No. of Participants Topics Discussed Issues Participants

Market Place Total=17 Shopkeepers and • Operation and • Shop keepers assured their Community maintenance of the full support to the Project LidhoraKhas M=11 Members facilities developed under and assured full the project and cooperation during the community participation; construction phase Street 28/06/2018 F=06 • Possibility of exempting vendors and small shop the poor and vulnerable owners got agreed on from user charge temporary shifting of Haats payment. (to other road side were alignment is not proposed) • The community willingly during excavation accepted the project. The community members • It should be ensured that expressed that their their business is not closed economic situation would for the civil works ensuring prevent them from no income loss paying water user • The shop owners indicated charges. (The men work that they are willing to as daily Labourer’s and accept the project which is the women as ultimately for the benefit of housewives).None of the the community people; people knew about the • On learning about the proposed project. On project, they expressed that learning about the they were happy that the project, they expressed entire community would be that they were happy that benefited from the the entire community upgraded water supply would be benefited from the upgraded water • People were briefed about supply. the complaint redress mechanism. • construction work can be put on hold on weekly market days Ward no. 9 Total=20 Community • Briefing on project • The area has insufficient and Lidhora Members objectives probable inadequate drinking water Khas M=13 implementation procedures resource. Water supply to the • Present drinking water area is done through two tube wells that supplies water to the 28/06/2018 F=07 supply source and its condition community people. The area faces severe water crisis during Need of improvement of • the summer season when the the present situation ground water level drops. • Potential positive and • The community willingly negative impacts due to accepted the project. The project implementation community members • Land use and area to be expressed that their economic covered under the project situation would prevent them Drinking water user charge from paying water user charges. • None of the people knew about the proposed project.

List of Participants in Lidhorakhas 149

Consultation in ward No. 14

Consultation Meeting With Community in ward no. 09 & Market

150

151

152

153

Appendix 6: Extract From Construction & Demolition Management Rules, 2016

154

155

156

157

158

159

Appendix 7: Salient Features Of Major Labor Laws Applicable To Establishments Engaged In Construction Of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or 160

above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter- state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

161

Appendix 8: Water Source Sustainability Report The sustainability of source lies in its liableness to cater the yearly demand of the water supply system. It is attempted here to establish with following rationale in its support:

Baseline characteristics: for Kari Water Supply Project Weir Location Latitude - 24°50'59.04"N / Longitude -78°46'28.02"E across River Jamni. River name Jamni River Basin Betwa sub-basin, Ganga basin Catchment area 1112 sq.km. Catchment area Attached as Figure 1, below map Catchment area Predominant Agricultural land with sandy Loam and Loamy clay soil Characteristics Rainfall data Tikamgarh rainfall data referred (Attached as Annexure – 1)

Catchment yield Dicken’s rational formula = Q = C*A^3/4 assessment Constant (C) Constant value for central zone of India (‘C’ lies from 11 to 19) Yield of catchment 2118.22 cum/s (For details Refer Table 1, below) area calculated Water demand 0.57 MCM or 1.56 MLD or 0.018 cum/s Weir Capacity 0.7 MCM

Baseline characteristics: Jeron Khalsa and Lidhora Khas Water Supply Project Weir Location Latitude - 25° 4'20.37"N / Longitude - 78°38'21.40"E across river Jamni. River name Jamni River Basin Betwa sub-basin, Ganga basin Catchment area 2353.97 sq.km. Catchment area Attached as Figure 2, below map Catchment area Predominant Agricultural land with sandy Loam and Loamy clay soil Characteristics Rainfall data Tikamgarh rainfall data referred (Attached as Annexure – 1) Catchment yield Dicken’s rational formula = Q = C*A^3/4 assessment Constant (C) Constant value for central zone of India (‘C’ lies from 11 to 19) Yield of catchment 3717.43 cum/s ((For details Refer Table 2, below) area calculated Water demand 1.087 MCM or 2.98 MLD or 0.035 cum/s Weir Capacity 1.17 MCM

Discussion on Source Sustainability

Availability of sufficient data, to workout the quantity of runoff generated is one of the biggest constraints. The actual rainfall data of the catchment area is not available and there is no rain gauge stations in the said catchment of proposed weirs at Jamni River for Kari water supply project and Jeron Khalsa & Lidhora Khas Group water supply Project. Without time series data on rainfall and its intensity, it is difficult to workout runoff quantity.

Proposed weirs for Kari and Jeron Khalsa & Lidhora Khas Water Supply Projects have 1112 sq.km. and 2353.97 Sq. km. respectively. In the up-streams of both the catchments have 06nos. and 15nos. water 162 retaining structures respectively on Jamni river and the storage capacities of each of these water retaining structures is about 1 MCM which is insignificant looking to the vast catchment area of both the said proposed weirs and may not affect their filling. As per the interactions with the local residents it is informed that all the existing weirs get filled and overflow in every monsoon. Rainfall data available for 44 years for Tikamgarh district which is in the vicinity to the proposed weir catchments of Kari and Jeron Khalsa & Lidhora Khas Water Supply Projects indicate that this region gets 995.8 mm average annual rainfall through which it is inferred that good runoff is generated which may fill proposed weirs in every monsoon and ‘since the annual water demand is very low (0.70 MCM and 1.17 MCM) so, it is inferred that both the proposed weirs will be capable enough to cater the annual demand.’

For sake of an assessment of yield generation in the catchment, Dicken’s rational formula is used with recommended constant’s value for central Zone of India (‘C’ lies from 11 to 19) and it is estimated that the peak discharge of 2118.22cum/sec will be generated in proposed Kari weir catchment and 3717.43 Cum/sec in Jeron Khalsa & Lidhora Khas weir catchment. The values of these peak discharges are huge and looking to the rainfall pattern in the vicinity of the region, feasibility of filling of proposed weirs is very fair.

In continuation to above information, it is also worthwhile to be mentioned that “water source finalization committee of MPUDC, GoMP has approved the proposed raw water in its 9th meeting held on dated august 31, 2018. This committee is a highest level Apex Body of GoMP comprised of senior level members including hydrologists from Jal Nigam and water Resources Deptt. of govt. of Madhya Pradesh.” The copy of MoM of the said meeting is enclosed herewith as Annexure – 2 (Refer S. No. 5, 6 & S. No. 7) for ready reference. For NoC from WRD Application has been submitted and it is under process.

Due to the unavailability of information and data of other water retaining structures situated in the catchment region, due to the different ownerships of various other department, it is difficult to give precise calculations but in perception to above mentioned information and discussion, it is inferred that the said Raw Water Sources, of Kari and Jeron Khalsa & Lidhora Khas Water Supply Projects is sustainable and reliable.

Table 1: Water Availability/ Yield Assessment based on Catchment Area at Proposed Weir Site (Kari Town WSS)

Calculation for Total Runoff w.r.t. Proposed Weir Site at Jamni River For Kari Town Water Supply Scheme S. No. 1 Catchment area (A) = 2353.97 Sq. Km 2 Catchment yield assessment by Dicken’s rational = C*A^3/4 Cum/s formula (Q) Constant (C) value for central zone of India lies from = 11 (11 to 19) = 11*1112^0.75 Cum/s 3 Yield (Q) Calculated = 2118.22 cum/s = 0.7 MCM 4 Proposed Weir Capacity (Kari Town WSS) = 1.9 MLD = 0.022 cum/s = 0.018 cum/s 5 Ultimate Year Water Demand For Kari Town = 1.56 MLD = 0.57 MCM

163

Table 2: Water Availability/ Yield Assessment based on Catchment Area at Proposed Weir Site (Jeron Khalsa & Lidhora Khas Towns WSS)

Calculation for Total Runoff w.r.t. Proposed Weir Site at Jamni River For Jeron Khalsa & Lidhora Khas Towns Water Supply Scheme S. No. 1 Catchment area (A) = 2353.97 Sq. Km 2 Catchment yield assessment by Dicken’s rational = C*A^3/4 Cum/s formula (Q) Constant (C) value for central zone of India lies from = 11 11 to 19) = 11*2353.97^0.75 Cum/s 3 Yield (Q) Calculated = 3717.43 cum/s = 1.17 MCM 4 Proposed Weir Capacity (Kari Town WSS) = 3.20 MLD = 0.037 cum/s = 0.035 cum/s Ultimate Year Water Demand For Jeron Khalsa & 5 = 2.98 MLD Lidhora Khas Towns = 1.087 MCM

Figure 1: Catchment Area Map w.r.t. to Proposed Weir Location for Kari Town (Catchment Area = 1112 Sq.km)

164

Figure 2: Catchment Area Map w.r.t. to Proposed Weir Location for Jeron Khalsa & Lidhora Khas Towns (Catchment Area = 2353.97 Sq.km)

165

Tikamgarh District Rainfall Details

Source: (i) http://www.mpwrd.gov.in/rainfall; (ii)http://www.mpwrd.gov.in/ganga-basin

166

Copy of Minutes of Meeting of Water Source Finalization Committee of MPUDC (MPUSIP)

167

168

169

170

171

Appendix 9: Sample Grievance Registration Form

(To be available in Hindi and English)

The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project: Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

If included as attachment/note/letter, please tick here: How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken: Whether action taken disclosed: Yes No 172

Appendix 10: Sample Outline Spoils (Construction Waste) Management Plan

• The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan. • The contractor, in consultation with the PIU, has to find out appropriate location/s for the disposal of the excess soil generated. The spoils should be deposited only at these sites. • Further precautions need to be taken in case of the contaminated spoils • The vehicle carrying the spoil should be covered properly. • The spoils generating from each site should be removed on the same day or immediately after the work is complete. The site / road should be restored to the original condition.

I. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc.

II. Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, d) Suggested reuse of disposal of the spoil

III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

173

Appendix 11: Sample Outline Traffic Management Plan

A. Principles for TMP around the Water Pipes Construction Sites

1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues: (i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone; (ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) addressing issues that may delay the project.

B. Operating Policies for TMP

2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment. (i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance. (ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic control zones. (vi) Train all persons that select, place, and maintain temporary traffic control devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents, businesses, emergency services, railroads, commercial vehicles, and transit operations.

3. Figure A2 to Figure A12illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads.

C. Analyze the impact due to street closure

4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps:

(i) approval from the ULB/Public Works Department (PWD) to use the local streets as detours;

174

(ii) consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction; (iii) determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents; (iv) determining if additional traffic control or temporary improvements are needed along the detour route; (v) considering how access will be provided to the worksite; (vi) contacting emergency service, school officials, and transit authorities to determine if there are impacts to their operations; and (vii) developing a notification program to the public so that the closure is not a surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion.

5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period.

Figure A1: Policy Steps for the TMP

D. Public awareness and notifications

175

6. As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works. 7. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

8. The PIU will also conduct an awareness campaign to educate the public about the following issues:

(i) traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.); (ii) defensive driving behaviour along the work zones; and (iii) reduced speeds enforced at the work zones and traffic diversions.

9. It may be necessary to conduct the awareness programs/campaigns on road safety during construction.

10. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose:

(i) explain why the brochure was prepared, along with a brief description of the project; (ii) advise the public to expect the unexpected; (iii) educate the public about the various traffic control devices and safety measures adopted at the work zones; (iv) educate the public about the safe road user behaviour to emulate at the work zones; (v) tell the public how to stay informed or where to inquire about road safety issues at the work zones (name, telephone, mobile number of the contact person; and (vi) indicate the office hours of relevant offices.

176

E. Install traffic control devices at the work zones and traffic diversion routes

11. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

• Signs • Pavement Markings • Channelizing Devices • Arrow Panels • Warning Lights

12. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such, the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However, regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary “STOP” and “GO”).

13. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics: • Work on shoulder or parking lane • Shoulder or parking lane closed on divided road • Work in Travel lane • Lane closure on road with low volume • Street closure with detour

14. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones.

15. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/

177

personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time.

16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

178

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

179

Figure A6: Street closure with detour

180

Appendix 12: Drinking Water Standards

No Substance or Requireme Undesirable effect Permissible Remarks . characteristic nt outside the desirable limit in the Desirable absence of limit alternate Source Essential Characteristic 1. Colour Hazen 5 Above 5, consumer 25 Extended to 25 Units, Max acceptance decreases only if toxic Substance are not suspect in absence of alternate sources 2. Odour Unobjectio - - a) test cold and nable when heated b) test are several dilutions 3. Taste Agreeable - - Test to be conducted only after safely has been established 4. Turbidity (NTU) 5 Above 5, consumer 10 - Max acceptance decreases 5. pH value 6.5 to 8.5 Beyond this range the No - water will after the relaxation mucous membrane and/or water supply system 6. Total 300 Encrustation in water 600 - Hardness supply structure and (mg/L) adverse effects on CaCO3 domestic use 7. Iron (mg/L, Fe) 0.3 Beyond this limit 1.0 - Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria 8. Chlorides 250 250 Beyond effects 1000 - (mg/L, Cl) Max outside the desirable limit

181

9. Residual free 0.2 - - To be applicable Chlorine only when water is (mg/L), Max chlorinated. Tested at customer end. When protection against viral infection is required, it should be min. 0.5 mg/L. Desirable Characteristics 10 Dissolved 500 Beyond this, 2000 - . solids mg/L. palatability decreases Max and may cause gastrointestinal irritation. 11 Calcium (mg/L, 75 Encrustation in water 200 - . Ca) Max. supply structure and adverse effects on domestic use. 12 Magnesium 30 Encrustation in water 100 - . (mg/L, Mg) supply structure and Max adverse effects on domestic use. 13 Copper (mg/L, 0.05 Astringent taste dis 1.5 - . Cu) Max coloration and corrosion of pipes fittings and utensils will be caused beyond this. 14 Manganese 0.1 Beyond this limit 0.3 - . (mg/L, Mn) taste/appearance are Max affected, has advers effect on domestic use and water supply structure 15 Sulphate 200 Beyond this causes 400 May be extended . (mg/L, SO4) gastro intestinal upto 400 provided Max. irritation when magnesium (as magnesium or sodium Mg) does not are present exceed 30 16 Nitrate (mg/L, 45 Beyond this 100 - . NO3) Max. methaemoglobinemia takes place.

182

17 Fluoride (mg/L, 1.0 Fluoride may be kept 1.5 - . F) Max. as low as possible. High fluoride may cause fluorosis. 18 Phenolic 0.001 Beyond this, it may 0.002 - . Compounds cause objectionable (mg/L taste and odour C6H5OH) Max. 19 Mercury (mg/L 0.001 Beyond this the water No To be tested when . Hg) Max becomes toxic Relaxation. pollution is suspected 20 Cadmium 0.01 Beyond this the water No To be tested when (mg/L, Cd) becomes toxic Relaxation. pollution is Max suspected 21 Selenium 0.01 Beyond this the water No To be tested when . (mg/L, Se) Max becomes toxic. Relaxation. pollution is suspected 22 Arsenic 0.05 Beyond this the water No To be tested when . (mg/L, As) becomes toxic Relaxation pollution is Max. suspected 23 Cyanide 0.05 Beyond this the water No To be tested when . becomes toxic Relaxation pollution is suspected 24 Lead (mg/L 0.05 Beyond this the water No To be tested when . Pb) Max. becomes toxic Relaxation pollution is suspected 25 Zinc (mg/L, Zn) 5 Beyond this limit it can 15 To be tested when . Max. cause astringent taste pollution is and an opalescence in suspected water 26 Anionic 0.2 Beyond this limit it can 1.0 To be tested when . detergents cause a light froth in pollution is (mg/L, MBAS) water suspected Max 27 Chromium 0.05 May be carcinogenic - - . (mg/L, Cr6+ above this limit 28 Polynuclear - May be carcinogenic - - . Aromatic Hydrocarbons (mg/l, PAH) Max 29 Mineral oil 0.01 Beyond this limit, 0.03 To be tested when . (mg/L) undesirable taste and pollution is odour after suspected

183

chlorination takes place 30 Pesticides Absent Toxic 0.001 - . (mg/L) max Radioactive materials 31 Alpha emitters - - 0.1 - . Bq/L Max 32 Beta emitters - - 1.0 - . Pci/L Max 33 Alkalinity 200 Beyond this limit, taste 600 - . (mg/L,) Max becomes unpleasant 34 Aluminum 0.03 Cumulative effect is 0.2 . (mg/L, Al) Max reported to cause dementia 35 Boron (mg/L) 1.0 - 5.0 - . Max

184

Appendix 13: Sample Environmental Site Inspection Report

Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Design Stage Implementation Pre-Commissioning Guarantee Period

Monitoring Items Compliance Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential areas

185

Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off

______Name Name Position Position

186

Appendix 14: Quarterly Reporting Format For Assistant Safeguards Officer

1. Introduction • Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

Status of Sub-Project No Sub-Project List of Progress Desig Pre- Construction Operational . Name Works of Works n Construction Phase            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Action Required Requirements Compliance

3. Compliance status with environmental loan covenants No. (List schedule Covenant Status of Compliance Action Required and paragraph number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan • Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. • There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries;

187

o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed.

188 Summary Monitoring Table Impacts Mitigation Parameters Method of Location Date of Name of (List from Measures Monitored (As a Monitoring of Monitoring Person IEE) (List from minimum those Monitoring Conducted Who IEE) identified in the Conducted IEE should be the monitored) Monitoring Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub-Project EMP/ CEMP CEMP/ EMP Status of Action Name Part of Being Implementation Proposed and Contract Implemented (Excellent/ Satisfactory/ Additional Documents (Y/N) Partially Satisfactory/ Measures (Y/N) Below Satisfactory) Required

5. Approach and methodology for environmental monitoring of the project • Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels) • Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used

189

• Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below.

Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Parameters (Monitoring Results) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Water Quality Results Parameters (Government Standards) Site Date of Sampling Site Location pH Conductivity BOD TSS TN TP No. µS/cm mg/L mg/L mg/L mg/L

Parameters (Monitoring Results) Site Date of Sampling Site Location pH Conductivity BOD TSS TN TP No. µS/cm mg/L mg/L mg/L mg/L

Noise Quality Results LA (dBA) (Government Standard) Site No. Date of Testing Site Location eq Day Time Night Time

LA (dBA) (Monitoring Results) Site No. Date of Testing Site Location eq Day Time Night Time

7. Summary of key issues and remedial actions

190 • Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes • Photos • Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report • Other

191 Appendix 15: Guideline for Construction Work about Safety from COVID-19 Pandemic (SOP – Health & Safety Plan)

192

193

194

195

196

197

198