Infrastructure Library

METUNG

· LOCAL STRUCTURE PLAN

Adopted by Council on 14th December, 1993 .

711. 4099 00/06214 456 MET:T Metung : local structure plan CONTENTS

PREAMBLE

PART A: BACKGROUND

1 INTRODUCTION 1

2 BACKGROUND AND CONCEPT DEVELOPMENT 2

3 STRUCTURE PLAN OBJECTIVES 7

PARTB: RECOMMENDATIONS

4 LOCAL STRUCTURE PLAN CONCEPT 11

5 GUIDELINES 14

- GUIDELINES SUMMARY 27

6 STATUTORY IMPLEMENTATION 32

7 INDUSTRIAL LAND USE 35

8 BOAT SLIPPING FACILITIES 36

APPENDIX 1- INDIGENOUS PLANT SPECIES. APPENDIX 2 -TRAFFIC MANAGEMENT STUDY. APPENDIX 3 - BEACH ROAD CLOSURE REPORT. APPENDIX 4- BOAT SLIPWAY REPORT. PART A

BACKGROUND PREAMBLE

The preparation of a Local Structure Plan for Metung is a challenging exercise. There will be those who believe that the settlement's charm lies in its past and that recent development and proposals for the future do nothing but threaten that charm. In fact this view has been expressed to the consultants during the conduct of this study and is borne out in attitudes that have been expressed toward some of the preliminary ideas and previous proposals. There will be others, however, who see opportunities to enhance the area and to make it more accessible to a greater number of people.

The challenge, therefore, in the preparation of plans such as this, is to respect the views of all those who care about the area. Responsible planning must seek to find ways to maximise the use of the area, in a manner which does not threaten the very features that make the area .so attractive.

In undertaking this work, the Consultant team and the Council has sought to inject objective views about the settlement and its future.· It has attempted to do this in a manner which respects and enhances· the area's ll;llique character. PAGE 1

1 INTRODUCTION

The town of Metung offers a lakeside environment unique amongst urban settlements in the Lakes region. The undulating, well treed landscape is in sharp contrast to the generally flat alluvial plains which surround the Metung district and it is largely this unique landscape quality which has attracted settlement to the area.

Importantly, the protection of this landscape quality and the adjoining lakes will require the careful management of future development pressures at Metung. The Strategy (1990) and the Shire of Tambo's Draft Metung District Strategy (1987), both highlight the need to appropriately control new development within the existing township area. This Local Structure Plan acknowledges the limited capacity of the study area to absorb new development and sets down in detail the way in which this aim can be achieved.

The Local Structure Plan details development guidelines and planning scheme mechanisms to encourage site responsive development in Metung. It analyses the factors which contribute to the special character of Metung and recommends controls to protect and enhance that character. The document is not intended to be an inflexible or prescriptive blueprint of Metung's future. Clearly, such an approach would not be possible, nor appropriate. Rather, the Structure Plan aims to identify the preferred framework for the future planning of Metung and to encourage imaginative solutions to future planning issues within the guiding parameters of that framework.

Undoubtedly, the special attributes that attracted growth and development to Metung in the past will continue to generate new pressures in the future. Whilst some of this pressure for growth will be able to be directed to neighbouring areas such as Tambo Bluff and Storth Ryes, this Local Structure Plan will provide the planning mechanisms to guide and control any future development at Metung to ensure that it remains a unique settlement for residents and visitors alike. PAGE 2

2 BACKGROUND AND CONCEPT DEVELOPMENT

The background stages of the Metung Local Structure Plan study included site inspections, a review of relevant data, planning studies and policy, and discussions with representative of the local area ·(including residents, business operators and public authorities). These preliminary investigations highlighted a number of opportunities and constraints to future planning in Metung and provided the necessary information to enable a preliminary structure plan option to be prepared and presented to the Steering Committee in September, 1991.

Following discussions with the Committee and receipt of the Council's comments, the preliminary option was modified to arrive at the Local Structure Plan detailed in Part B of this report.

2.1 "Village Character''

The local community and visitors to Metung are generally agreed that the town environs have a unique quality that can perhaps best be described as its "village character". The concept may mean slightly different things to different people and some claim that this special quality has already been substantially lost due to recent development activities. However, the special local attributes enjoyed by residents and visitors to Metung will continue to attract attention to the town as a popular permanent and holiday destination. It is necessary, therefore, to identify the characteristics of the town responsible for this village atmosphere and to incorporate guidelines in the Metung Local Structure Plan to protect and enhance them.

Perhaps the most obvious influence is the position and topography of the town, being situated on a small peninsula of land formed by the waters of Lake King and Bancroft Bay. The Metung peninsula contains a series of ridges and valleys with a generous cover of native vegetation. Views from Metung to the lakes, and from the lakes to Metung, are both significant in aesthetic terms and in contributing to the special character of the town. PAGE 3·

In addition to its beautiful landscape setting, there are a number of additional factors which can be readily identified:

• · the water-based, maritime focus of the town centre;

.. the primarily residential nature of the town's land use;

.. the outlook and activity opportunities offered by the town centre "village green";

.. the ·generally clustered residential development nodes separated by significant stands of mature trees;

.. the generally high tree canopy;

.. the single "loop road" access to the town which effectively . distributes vehicle traffic without cross-town movements;

• · the town's undulating land form;

.. the "domestic" scale of buildings in the area; ·

the town's "isolated" location ..

These factors should generally be regarded as fortunate responses to the initial siting and historic growth of the town which, although not originally the result of deliberate planning decisions, should now be acknowledged, .protected and strengthened by planning policy guidelines for Me tung's future.

2.2 Topography

The topography of Metung has played a particularly important role in the towns development. The .settlement has developed incrementally over a long period, initially following ~ form of grid road layout which bears little relationship to the topography of the area. Simply, the town's roads reserves were drawn In a survey. office and are located in places ·where natural land grades often rendered their construction impractical. PAGE 4

Roads have only been constructed on those areas where development is possible with the perhaps fortunate consequence of creating a pattern of discreet residential clusters or precincts. separated by natural valleys. In many areas, significant stands of mature trees remain between developed precincts, further defining the major ridge lines and gUllies which subdivide the study area.

Parts of the Metung township area have topographic and environmental constraints that pose particular difficulties to building development. Land identified in Plan 1 as being "Class 5" in the Metung District Strategy present the most severe difficulties to new development works due to such factors as steep slopes, tree cover and poor soil capability.

A series of additional plans illustrating the existing conditions in the study area were prepared. They illustrate the physical constraints and opportunities to future development in Metung and include the general topography (Plan 2), significant tree cover (Plan 3) and road network (Plan 4), primary activity nodes, existing development and zoning. Together these plans present a picture of the suitability and capability of land in the town to be developed. Land which is generally free from the development constraints imposed by steep slopes, significant tree cover and so on, was then identified as "unencumbered land" and is illustrated on Plan 5.

2.3 Building Design

One of the most pleasing aspects of Metung is the quality and "character" of the design of much of its new development. There is a distinct feeling that many houses and uruts have been designed to respect their natural setting and. lakeside environment. This is not the case of all new development, but certainly is of much of the development which enjoys a "public exposure". __ ,..w ~-'­ 'io.oo--•••• ::-,:;-~-· lllllllllllllllllllllllllll ,.,.u,_,_ , .. t-UOMJ1 PERROTT LYON MATHIESON ·'· . "·. . .. ' .

. '. (

. . . . I ' r .~ '- •

• • f .• ' •

. :...... ; .·

... . ' .

\ .

' . ' ) . I • ' . ' . . ' .· ...... ' . . UNaOO SAl ...... 1 . .·,

. •' ~ • . ' ' r : '·.

> • ~ • ...... , . . ' . ~-· .,... ·. . ' - . ' . . . . . / .. ·. ' ; . ' ..'.. ... ,...... ' ~-...... 1/qk.f~~UO:~). . ' ' •• . . . . ' ..··' i' : ...... : ·. .' . . . . . I . . • . . . l.Akf KING • • '. : · · ' <' . • . • - . . .

.·- .' . I ~ •

I'

. ' , . . . '...... ~· ---~§~-~-~· _____,;.,__...... ____,;,_. _ ...... wwllllll.LIII1!J.LIIJ!IItiii!IIIIIWIIWLIIIIIIIIII~---·-·· __.:..___··___:_,· _· . ·· · · .· · · r=lJ &ANC101T M'f.

lAitt lUNG

1----______Tircca~E~_, _--...:..J..__,------+

-----L fT~fVGltDL5l~RCrntrrr&'\L5TQ ···-----~

llll~lllllllllllllllllllll PERROTT LYON MATHIESON l~Kf. KING

' ' - .. ~=-~~---·_·..._-·----_------_-- _-_·-=---·=-cJRCW~CATIOS~\~. ----~ ===------_-----. ___METWNG_IZXII:_5.11WcrQ(E_ec4N: STU£2!•. ------t

lllllllllllllllllllllllllll I---.. -

• • • r •

I .

. .

. '

:BANOOFT SA'(

I ' •

. •. . . '. . ' : . '. . -:rw- KING .. . .

• · • · · !IU!VIHG· . . • . . ' . . . I'OIMT ' . . 1-----~~--'--· __,__.·~. -'-;--.-.-- -- - . -- - . -. -~---- ~ _·. ~ _· -- . \ ..· . . . ' . ' !------'---~-. _·_·.· ·_· ~, __ . . :~NCR;M~fKfD___ · [~ND _____ ~Rf~5--.. -~. ·. ·. · _· _.- ~_:_- · · -·.

~--·'::------'------_ ~ JVlfTVOOGToacsT~m~E- rl& -c _ _- -- -

• ""'•-l-__ ,..,l .. ·.' ~=··~ .. :~:.::;:- - : lllmlllllllllllllllllllll - . .. rn. :!;![a:-.., . . . P E R R · 0 T T . L ·y 0 N M. A T H . I . E S 0 N · PAGE 5

Within some of the more "private" residential clusters, development sometimes competes for attention and scenic views, but generally it is of a good quality. This standard of design and construction assists to enhance Me tung's character and appeal.

There will be those who are critical of the design, location and density of some of this new development. However, Metung is particularly fortunate that its new development over recent years has generally been well designed with a character fast becoming "indigenous". It can be contrasted with the bland, low-cost development that characterises many waterfront communities in this State-and, in fact, some of the early development in Metung itself.

It must also be remembered that development opportunities at Metung are limited, whilst growth pressures are strong. It makes eminent sense, therefore, to identify and optimise those appropriate opportunities that do exist. The focusing of well designed development into suitable areas will assist to consolidate village character and is to be preferred over an endless outward spread of the settlement.

2.4 Public Spaces

One of the most important aspects of the settlement is the "village green" open space which has enormous potential to become a first rate community focus.

Also suffering a poor profile is the narrow peninsula of land to Shaving Point. This portion of the town accommodates some of Metung's older houses which enjoy private lakeside frontages. As a consequence, these properties turn their backs to the public side of the peninsula with the result that visitors are presented with an unattractive foreshore· strip devoid of landscaping and flanked by paling fences. However, they do serve a practical purpose as a wind break for those houses.

Considerable opportunities exist for improvement to landscaping of the foreshore strip. PAGE ·6

2.5 · Eng4leering Services •

Metung is serviced by power, ·water and tele:phone services ~nd has recently been provided with a. reticulated sewerage· system. The sewenl.ge system will help to protect' the lake. environtrtent ~rid will . undoubt~dly e~courag.e development propo~als for larid previo.usly · constrained·~y servicing restrictions. Advice from the Tamb~ Water· Board .~dicates that the new sewerage system is able to cater for. a significantly higher. population. than.currently exists. fu Metung. - .·. Should the need ever arise, the system's capacity could be· expanded · as required. The system·is capable ot'inclliding the propo~ed'Storth .Ryes development and the Tambo Bluff Estate;

.' '. ,. ·. PAGE 7

3 STRUCTURE PLAN OBJECTIVES

The preparation of this Loc.al Structure Plan has been undertaken to meet the following goals and oJ:?jectives for future growth at Metung. These goals and objectives provide the descriptive framework for the future planning of Metung. They are the measure against which the implementation of the detailed planning guidelines outlined in Section 5 and 6 should be assessed.

3.1 Overall Goal$

maintain the village/retreat character of Metung and the environment enjoyed by residents and visitors to the area;

... recognise the attractions of the area and provide for an enjoyable visitor experience;

protect the natural environment as much as possible;

maintain and strengthen exsiting landscape quality;

provide for limited new growth, mainly of an infill nature, where appropriate;

... ensure that new development contributes to the strengthening of Metung's existing character and built form;

ensure that new development is ·sensitive to the town's high landscape quality;

enable growth to take place which poses no threat to the existing character of the area to which it was attracted;

limit town growth to within its present crown to~nship boundaries; PAGE 8

* assist implementation of the recommendations of the Gippsland Lakes Strategy;

* provide the Council with a management tool to guide the location and nature of future development in Metung;

* ensure that development responds to the land capability constraints and opportunities of the land.

3.2 Land Use and Development

* ensure that Metung remains a predominantly residential settlement;

* limit commercial land uses to those necessary to support a small local population and visitors to the area, including those necessary to pr~vide short term accommodation for visitors;

* locate limited new residential development (mainly of an infill nature) and associated commercial uses in precincts or clusters already set aside for development;

* ensure that new infrastructure services are provided in advance of development activities taking place;

* enhance the entry to the town commercial centre;

* retain a compact pedestrian orientated town commercial centre;

* encourage development which maximises the opportunities offered by the limited areas available to accommodate it;

* encourage new development to be sited to minimise impact on the natural landscape and to enable maximum protection of existing remnant vegetation; PAGE 9

ensure that new development is connected to the reticulated sewerage system;

enhance the town centre in keeping with its lakeside "village" character;

ensure that new development does not alter the special character of Metung which has been responsible for attracting that new development.

.. on-site carparking to be provided for all new developments .

3.3 Traffic and Circulation

.. retain existing road network skeleton;

.. introduce minimum road construction standards (as per Victorian Code for Residential Development) as modified by Council where appropriate in new residential areas;

.. provide easy access around the settlement whilst improving access to the town centre;

.. limit the opportunities for non-residential traffic to filter through residential precincts;

.. maximise the opportunities for pedestrian and cyclist movement around the foreshore and between residential precincts;

.. introduce pedestrian and cyclist links between residential nodes and to public facilities and activity nodes;

3.4 Recreation and Open Space

.. provide an open space network that links the residential areas, the foreshore, the town centre and any other activity node. This network will also act and be managed as a nature conservation corridor; PAGE 10

... recognise the recreation needs of visitors to the area;

... ensure easy access to recreation facilities and open space areas;

... recognise the water based orientation of recreation activities and the need to facilitate access to the water;

... upgrade the Lake King beach area;

... protect and enhance the "village green" as an attractive an usable central community and visitor focus;

... provide for long term public access to foreshore areas subject to them not being intrusive to private/residential properties.

3.5 Landscape and Design

... create a settlement of high amenity, strong character and good design;

... encourage site responsive design, with particular regard to a site's environmental capacity for development;

* protect remaining native vegetation from disturbance or removal;

* protect ridgelines and significant stands of tre~s;

* encourage building design which will enhance the general character of the area and the village character of the town centre;

* introduce planting indigenous to the area;

* recognise the importance of views to the lakes as well as views to the settlement from the lakes.

- ----·------~------; ------:------:--,------,------,------,------...

. PARTB ·

. . . . RECOMMENDATIONS

...

. n

' ...

. . . '' ·. -· .

. . ..

.. ~ . ..

. . ., I' ' ''t t •

. ,·

.: " . PAGE 11

4 LOCAL STRUCTURE PLAN CONCEPT

The Local Structure Plan draws together the elements and planning objectives detailed in the preceding sections and illustrates the conceptual future development pattern of the study area. The following notes summarise the overall concept of the Local Structure Plan and should be read in conjunction with Plan 6 and which illustrate in detail the individual elements of the Structure Plan recommendations. Section 5 and 6 of this report outline specific guidelines to assist implementation of the Structure Plan recommendations.

Having regard to the pattern of existing development and the constrairits imposed by topography and tree cover, the Local Structure Plan · acknowledges the limited capacity of the study area to absorb new · development It also acknowledges the desirability of preserving lands between areas of residential development· in order to protect steep topography and significant vegetation.

To achieve these aims, Councils. has adopted a residential subdivision density of 1 allotment per 700m2 with a minimum lot size of 450m2. Multi­ unit development will be permitted to be subdivided below 450m2.

Accordingly, new development at Metung should be restricted to those areas already designated for development and opportunities for future growth should be limited to "infill" growth. In this way the available land for conditional development can be optimised for residential use (including multi-unit development subject to building design and siting guidelines as outlined in Section 5) and sensitive land areas can be protected.

Alternatively, new development should be channelled into the adjacent Storth Ryes/Tambo Bluff area where greater scope for growth exists .. The fact that much of the demand for new housing in the area can be satisfied adjacent to Metung, rather than within it, provides a unique opportunity to protect the qualities of Metung that give it its character. PAGE 12

Plan 6 outlines areas of conditional development land which may be suitable to accommodate new housing. These areas are considered the "preferred" areas for any new residential development in Metung. Plan 6 also outlines areas of no development. These areas are of a more sensitive nature due to slope and/ or tree cover and therefore require a development approach that is particularly sensitive to individual site conditions. "No development" means that Council will not approve any subdivision proposal.

A network of pedestrian walkways should be established through the study area to link residential development clusters and to provide access to the town centre and foreshore areas.

The Local Structure Plan illustrates the way in which the town centre has developed. The existing town centre has been under pressure for change by the incremental spread of land uses. · The aim of this plan is to ensure the consolidation of future demands for tourist/ commercial land uses to locate within the town centre. Plan 7 illustrates the broad arrangement of existing town centre land uses.

In general, the area around the village green and the nearby lake King beach should be upgraded to enhance the amenity and character of the area. Improvements to traffic management, public car parking, urban· design, landscaping of public areas, foreshore access and beach . regeneration should aim to reflect a consistent "village" lakeside design theme representative of Metung.

The study team has noted some of the designs already being introduced into Metung which have a particular character and appeal about them. These buildings have a "public" face, being located adjacent to the main access roads or foreshore areas. Infrastructure Library ,' I

·METUNG N.T.S.

[].. NO DEVELOPMENT (Council will not approve . any subdivision proposal)

CONDITIONAL 0 DEVELOPMENT

LOCAL COMMERCIAL ZONE

SHIRE OF PHONE (OS t )55.3 t 00 TAMBO f'AX (OSt)SS.3t21 ·,

. • ' I ! I

.. J

;-

. . .BANCROFT . BAY

• . ,r.

'1fi7. VAlZt .'{riwAI ~7':1t.e CMCa.­ .--sHIRE·· ··asMJtDIIDD O,I!;_~C/Nt:..r ~N ,UICDDmWICI...... ·-oF . . &MD~~ . ' ..... (1111)SU100 .. TAMBO- ." DX COS1)UJ1ZI PAGE 13

Promotion of a consistent design theme, particularly· in public buildings, will assist to strengthen the special "village" character of Metung and will generally encourage good design throughout the area.

The Shaving Point peninsula currently has tourist accommodation facilities available. However, the majority of the land is in private ownership with restricted public access to the eastern foreshore.

The existing Metung Road/Stirling Road primary access route identified on Plan 4, operates as the distributor road to the town's residential areas and as the access to the town centre. A Traffic Managem~nt Study prepared by the Shire's Engineering Department states that a one-way traffic movement system along Metung Road is feasible and recommends further investigation and public consultation. (Plan 14 illustrates the proposed traffic movement in Metung).

, A further report prepared by the Engineering Department discusses the future of Beach Road. It is recommended by Council that Beach Road be closed to vehicular traffic. A copy of both reports are included as Appendix 2 and 3 respectively. Plan 14 illustrates both recommendations from the report.

The Local Structure Plan outline summarised above and illustrated on the accompanying plans will provide the Council and community with a greater degree of planning certainty as to the future development of Metung. Guidelines for the implementation of the Local Structure Plan are detailed in Sections 5 and 6.

) ------

PAGE 14

5 GUIDELINES

The Local Structure Plan indicat~s the· broad framework within which future development in Metung should be set. The detail of how this can be achieved is described in the following guidelines for the design, siting and provision of buildings, roads, landscaping, utility services, and public facilities and spaces.

The guidelines have been prepared to meet the Local Structure Plan goals and objectives outlined in Section 3. When assessing permit applications for new use and development in Metung, the Council (as Responsible Authority) will measure the merits of each proposal against its achievement of the Structure Plan goals and objectives. Compliance with the following guidelines will assist to ensure that the stated goals and objectives are met and will consequently facilitate approvals. However, original and innovative development solutions are to be encouraged where it can be demonstrated that these will achieve the relevant aims of the Local· Structure Plan.

The guidelines which follow are discussed and described in general, and are then summarised in Section 5.7.

5.1 Building Development Guidelines

In order to maintain the built character of Metung, it will be important to encourage any new development to meet appropriate design guidelines. Metung's lakeside location, boating focus and spectacular landscape backdrop, impart both a maritime and a rural­ village character to the town environs. New development should be encouraged to express this character through building style, proportions and materials.

Existing buildings in Metung comprise a variety of styles and ages. However, it is possible to identify ·a number of building features . . which apply with a degree of consistency throughout the town and contribute to the particular character of the area. · PAGE 15 ,·

In order that new·dev~lopment migh_t as·sist to .strengthen Met~~s . . . bi.rilt character,· rather: ~han erode it, the following building I development guidelines have also been prepared ~o meet the overall I I goal of . ensuring that riew development co~tributes ·:'to . the I strengthe!ling of. Me-tung's exis~g-~harader ~nd ·built form:·

* · Bi.rildi~gs. should be designed to reflect their setting and -the- · · surrol;ll1ding land form; ~ ' . .

* . Materials and colours of bt,rildi.J:lgs ~nd roofs shoUld be selected to-_ .. refl~ct the natUral environment arid lakeside' setting;

,. ..· . ,. . . * Bi.rildings up to a .heig}lt _of 6 metres do not require a planning \- · __ -. per~t based on heighf(r,efer tb Plan 8); · ·

* _Bllilq.ings up to a height of between 6 and 7.5- metres will require a pl~nning .permit (refer to _.Plan 8); . . . - .

* :BUildings over 7.5 metres ~eight will' hot b~ approved.

·* Bi.rildings should be 'sited t? minimise disturqance to l~md and signifi~ant natural vegetation;

Roof design should be. in sympathy with' . the· undulati~g topograp~y' and. in keeping . with. the predominant forin _· in Me tung; - • - J \.

* Ro(?rhs · within roof profiles (and complying with building . regulations). are acceptable;- - ' . . .

* New commer~iai b~iidings in the town centre should. incorporate. posted verandahs to offer weather~ptotectionto pedestrians and

'· to- reWorce the pedestrian scale of the· precinct;

* Buildings should be located· to minimise ~eir impact on the amenity ofthe-riaturai'envircminent; _ ... The p.rovi~ion ofadvertis~g signs should h~ve regard-to th~ Shire . of Tambo's_- "Gui~elines for O~tdoor Advertising Si~s". _J' ---J-H!J I :;flfl _ . /::uv/(7-?J'J'lf?·

. .

...-. ~ .. O·t)

. .r.;;;;v~w . . . _5;·~ . :,...... -. ---·' ' ~

. . \ . ~' ~ . -;~~ ~o ~f~tj ~~~- ~IV/;J?j/ 0// ~.

--~

.•

·---·-··· ,..,.----·---,-- P.-vJ ... . . --~· . . ... -,!. .J';:V~ 0·~· _y .;_./ ·< -~ ' ;./

. '. ~ ' PAGE 16

• · Buil~gs should be ~ited to respect. the ame_nity and privacy of.· . . . ~ neighbours;

'. Residential buildings should be located in "clusters" or "precincts'';.

·,e. On Shaving·Point oniy one house p~r te~ement will be permitted.

5.2 FutUre Subdivision Guidelines

Any future subdivi~ion of land into residential housing lots should be restrfcted t~ the conditional develop~ent land areas shown on · Plan 6. No dear-felling of forested brciadacre land should :be· permitted for residential purposes .

. The Council · has adopted · the · Victofian Cc)de . for Residential - Oeyeiopment ("The Code") as ·a gtrlde for .re~idential development. · However, the Council has als·o adopted va~ious inodificatio:Qs to. th~ Code. These moq.ificatio~s ·are summarised as follows:

• •Subdivision density. of -per 2 . o~e allotme~t. 700~. ;

· * AbilitY to subdivide · for· units/ flats less . tha~ 450m2 ·at . a· · develqpinent: densitr -of: one. flat p~r 320m2 . simllar· ·to the:· ·proposed provisions for the Reside)j.tial B zone under the· Flat Code;

* Building . setbacks rem~in at 4.5 metres from road. frontage . boundary and below this setback subject .to_ the_· g~anting of ~ ·planning permit;

. . . * Side road boimdary setback at ·2.0 metres;·

,.. · Side and rear. boundarles.s~tback a·irunimum 1.2 metres or less subject to· the. granting -of aplanning permit; bu{ otherwise simila.r . to the Building Regulations;

.·. PAGE 17

Minimum road reserve widths of 15.0 metres;

.. Minimum road width of 5.0 metres between face of kerbs (this allows a car to pass a. parked car or a moving car);

.. No off pavement parking areas required.

This Code incorporates guidelines which are responsive to individual 2 site conditions. By providing for lots with a.rlunimum area of 450m .. and a density of 1 lot per 700m2 coupled with appropriate design guidelines, sensitive land areas (such as those with steep slopes or heavy tree cover) can be protected and developable land can be utilised more ef~ectively .. Plan 9 illustrates a preferred subdivision approach and benefits.

Demonstration of the suitability of a site for residential development should be the responsibility of the proponent. There should be no assump.tion made that any particular parcel of unsubdivided residentially zoned land in Metung is a sure candidate for development. Rather, the merits of the proposal and the capabilities of the land area to accommodate new development must be demonstrated. Accordingly, residential subdivision proposals should be accompanied by detailed plans which include the following information:

.. the location, size and contours of the subject site;

.. existing. significant vegetation and the location of any vegetation proposed to be removed to accommodate development;

.. building envelopes;

.. details of utility service installation requirements;

.. site access and road construction details;

* . proposed landscaping details; ...... I .· ~s;!!;¥/c2 ~ . _...... ·.: . . . EllVATION_._~~~~r~t!b.u-~.

.· · ~1ANDAIW ;U80/VISION ·

MET~~O OCAL. • ·. . ·......

.· .. ~T~WCTW~t PLAN ... ~f~IDfNTIAL. ~W~OIVI~ION I

~:-· .. · · tllltm1~1111111111111111 MATHIES 0 N . ' . . ·.~ PAGE 18

. Areas designated as "No Develop~ent." means that Co~cil Will not· approve of any sul?.~ivision proposal. . However. the subdiyi~ion ·of · de~elopments, eg, ~~that· exist prior. to' 15th June, 1993 maybe p~rmitted·having regar:d to ~e merits of the proposal.· . . ' ";· ' . .

~xistirtg ,curren.t planriing perrilits ·for qevelopment in the: 'No · -Development" are still-valid and can be acted upo:.;t. However; one~ permits ~xpire ·and an extension time requ~sted, Council will. look at . the metit' of the p~opo.sal measurmg' ~gainst the . ~bjectives· of this • .>, . • strategy.

- 5.~ · -Landscapmg Guidelines_

The visu~l quality arid character of Metung -is to a significant extent . . . ·derived from' its undulating: topography and natural vegetation~ The _ Local Structure- Plc:m recognises that maint~~ance of the .toWn~s unique iands~ape -s~tting is critical tb retaining the- town's.. speci~ :charact~rartdits reside~tial and_ touris~ appeaL -

.. The landscaping guidelines have been prepa!ed in accorda~ce .with the overall goal of mamtaining a~d ~rihancing the ex!s~irtg-ian~scape quality. They· have particular regard to the protection of ridgelmes and views .and .to th~ planting _of app~opi-iate tree species to· reinforce · ·

remaining :vegetation. The particular -objectiv~s of the ·landscaping· .·•. ·: guidelin~s desiiD":ed.toachleve 'that-overall goal ar~ that: . . '• ' . ' '

* there should be ..minimal dist-w:bance to:existing vegetati~:m;· · ~ .,. ne\Y planting should _compl~~ent e~sting' v~getation and include species_indigenous·to the area;: '· ' ~ . . ..

new pl~nting should enhance public spaces and provide shadE7; . * . . - .

. *. new-planting should be used to sc_r'eeri facilities, builqings q,nd car parking areas.

, . ~------·------

PACE 19

The following guidelines apply to both public and private sector development initiatives. They will be enforced for developments which require planning approvals and will be made available as guidelines to residents who may wish to refer to them when seeking guidance on general landscaping principles for the area.

Importantly, the successful implementation of these landscape guidelines will largely be dependant on the development and maintenance of public areas. The theme established with parks, pedestrian areas, and so on, will offer direction and momentum to private development works.

Landscape Theme

Having regard to the overall objective of "maintaining and enhancing the existing landscape quality" of Metung, the planting of exotic themes based on species which are indigenous to other distinct regions is not encouraged.

The Metung town environs are characterised by a variety of tree species, some of which occur naturally in the area and some of which have been introduced over a period of many years. The use of these species will allow for variety in detailed planting design whilst facilitating the integration of new landscape works with the existing landscape character of the area.

This policy is not intended to prevent the use of other "non-local" species in landscaping works. Rather1it is to encourage a thoughtful and sensitive approach to landscape design which will ensure that local species remain and are reinforced as the dominant planting elements in the Metung landscape.·

With the assistance of the Department of Conservation and Natural Resources, a plant guide has been appended which identifies a range of local species considered to be appropriate. Selections from the schedule should be incorporated in landscape plans, but may be supplemented by other complementary species which may not be native to the area. PAGE 20

Landscape Design

New development in the town centre should have due regard for the impact on overall streetscape. The development of an attractive streetscape can be assisted by the integration of the various landscape elements on private development sites with those in public spaces. New development should be seen as an opportunity to co-ordinate public and private works to transform the streetscape and enhance the town centre's appeal. Appropriate street planting and improvements, when combined with the landscaping of private development, can assist to create a sense of unification, as well as a sense of place.

The subdivision and development of new residential lots can have a significant impact upon existing vegetation. However, it also provides an opportunity to create pleasant and attractive residential environments through the retention of established . stands and corridors of trees. This can be reinforced with appropriate street tree planting where necessary, as illustrated on Plan 10.

The outlook to and from a site can be enhanced by the careful grouping of trees to frame views, as shown in Plan 11. The clustered planting of new trees, to reinstate a continuous canopy, will be encouraged in any new residential development.

The use of pergolas, planter boxes, sleeper walls, and other landscape structural works is encouraged in combination with appropriate planting. Concrete retaining structures, such as crib walls, are generally not desirable as the materials do not integrate well with the natural vegetation, as do timber and stone. It can also take considerable time to soften concrete structures with landscaping. Plan 12 illustrates the preferred type and use of retaining structures, and the opportunity to upgrade the verge to Metung Road which functions as the primary visitor and scenic access to the town. . . . '

I'' i

.-- . . .· .· .MET~W ~...... ,_..~~ .. :· ·. · · •.. · · 5TR~CTW 0/ST~ffT UIE~~C"T4 LAND~CArE .. . - . . . ' ...._ ..... " .....,.._P'I:tl.M ~ ...... ·-a-.-.~ _ . ~···..,!111·­ . )1 U6t)~J T...... ' 111 KWUJ~C'O ,._,,._\1)• ..\1 .UI ' , : p E R R 0 T T ·... L ~m"~"''''~''''' M A T H . I E S 0 N ~ fi'.IffltMD

~lOGE DEV£lOrMENT. · . · .' ......

. MET wN G L C ~-~~~- ~~a~r:ri\Lil[/'r

5T~~CT~~E PLAN ., LAND5CAPE - EE rLANTING I

mmmtlllllllllllllllll 1--+--!Z'J"\l ,_~=:. \\ ------~------

" .· ., -- --- . .. .-,'· i .. · ~! ,: 1==,"_~~ ~ .: - :i . I'=='=..-======~==~ . '•1: ·_ . ;i ::I===·======-= . I :i' MATIC:N 5lEffft WfJl. SEC11~

. . . . IfI

. '• . --- GA~m BI.OX llfJ.L ~ ·

~l~HCTH~E fLAN "' tfT41~1NG \VALLS -~~~~LA~~~-

, .. ,.L,... ~,,u • .... __ ...... ,.. ·~.- :~1!J--y...,._ . 11111""~"'1111111111111 ronul~ , .. t(I'J/!.).4""·" P E R R 0 T T L Y 0 N MATHIES 0 N PAGE 21

· Lan.dscape Plans .

.New·. development ·(including. shops, ·multi-unit developments, subdiyisions,. and . so . on). ·requiring. approval' under .the Planning Scheme wilrrequire the submission of detailed landscape pla~~; The pla~s· should be prepared· in suffi~ient det~il t~. enable· the .~ouncil 'tb assess the proposed "landscaping form and effect. This· should. ' - include, as appropriate:

* .: the lo~ation, size. and species or type of existing 'pla~ting;

.... tree~ proposed to be -retained;

* · trees· proposed to be re~oved; ·

* the existing: contoUrs of the subject l~nd;

* the· proposed finished surface .~evels;.

* 'details of Underground arid overhead serviCes; ·. • • • 4 < •

- - . ~ * d~tails of-proposed new. planting! mduding specie~~, location and detail~ oftl:te mi:itimU?'size at plantmg; · ·

·* . .details of any proposed ·pav:ing, walls, fences· o'r other structures; · ...... - . ' - . . . . , .· ..

* .·details· of any slope stabilisation measures .proposed;

· ~ · details ~f any irrigation and ~rainage methops proposed.

The landscape plans wo·uld be assessed ha'{ing regard to the · desirability ofretention of eXisting·~egetation, the potentiaUmpact of th~ loss of vegetat~o~ a'nd . the ·principles· included ~ithin this · guideline.

_Landscaping Will generaliy be required to be completed, prioi to the · · commencement of the associated use and its continuing. maintenance .. ' . - .. .will be an ongoing ~equirement. I I ·I

I PAGE 22

5.4 Traffic and Circulation Guidelines

The existing constructed road pattern in Metung comprises only part of the original network of government roads shown on the survey plans for the town. The undulating topography of the area has prevented much, of the original road layout from being formally constructed on the ground.

As a result, the existing road network comprises a single distributor "loop road" from the north with branches accessing the commercial and residential areas. There is, therefore, v~ry little opportunity for cross-town traffic or through-traffic intrusions into residential clusters. This pattern should be reinforced in any new development.

However, an opportunity does exist to investigate a one-way traffic movement system in Metung Road linking with a two-way system in Stirling Road. The Shire's Engineering Department has prepared a report on the feasibility of such a traffic movement system. Plan 14 illustrates the proposal. A copy of the report is included in Appendix 2 to the Local Structure Plan.

The recoll).mendations of the report are:

1. That detailed cost estimates of the proposal be undertaken for inclusion on Council's five year Works Program. ·

2. A further rep~rt be prepared on parking within Metung Township.

3. That further consultation with relevant authorities and the public be undertaken regarding the proposal.

--ooOoo":'- ~~---·. • • • 0 • •

~0 AD VA 'f. R=Rmm+H

MET~ NG LOCAL . 5T~~CT~~E PLAN • PFOE~T~IAN Cl05~ OVf~~

'"'<'~~ l,... ~--,,l .. .,..,_...... ---·"'···· .. :l'(lh-~..­ So .. Mt ~\IJ • • • m m ' T ll I E s O N - - . - 0 ~.~~~111111!!11111111 " 4 E3ij PROPOSED METUNG TRAFFIC MOVEMENTS N.T.S. PROPOSED PUBLIC CARP ARK AREA - ONE WAY TRAFFIC ONLY - TWO WAY TRAFFIC SHARED FOOTWAY CLOSED TO VEHICLES REFER APPENDIX

LANE CLOSURE

CMC c:oml£ e.s 1'.-u~D!S RCW) SHIRE lNCD ENTRANCE ".o.eox eo OF lNCD ENTRANCE 3101

PttOHE (~1~100 TAMBO . F~ (~1)553121 \4------·~--

PAGE 23

The town centre should be deliberately oriented toward pedestrian use. Although motor vehicle traffic should be able to enter, park or travel through the town centre, there should be no doubt left in the motorists minds that they have entered an area of pedestrian priority. This can be achieved by the introduction of segmented paving materials, pedestrian crossings, town entry and direction signage, appropriate street furniture and similar devices. Plan 13 illustrates a design of a type of pedestrian cross-over.

The guidelines which follow aim to strengthen the existing road network profile:

New roads should be limited to residential accessways only and not provide opportunities for vehicle linkages through other residential precincts;

Residential roads should be constructed to standards as set down in the Victorian Code for Residential Development (as modified by Council where appropriate);

The main · distributor road in Metung should be maintained, .. landscaped and signposted to enhance the visitor experience;

Adopt the traffic movement system for Metung and Stirling Road. as detailed in the Traffic Management Report including the provision of two-way traffic along Stirling Road extending to Beach Road.

New roads should generally attempt to follow contours and avoid the need to disturb existing significant vegetation;

Investigate the provision of paved pedestrian crossings across Metung Road, in the· town centre, to reinforce the pedestrian oriented focus of the precinct and to facilitate pedestrian movement between the Lake King beach and Bancroft Bay. PAGE 24

Investigate with any road construction proposal the possibility of providing shared walkways/bicycle paths.

Investigate closure of Beach Road.

5.5 Utility Services Guidelines

Having regard to the objectives to protect and enhance the landscape environs of Metung, the provision of new utility service infrastructure must be carried out in an environmentally sensitive manner. Accordingly, the guidelines set out below should be followed where new service provision is required:

\ Require new development to connect to the reticulated sewerage system;

Co-ordinate service provision to minimise the number of easements;

New development should install underground power where possible;

Locate any new above ground power lines to minimise the need for the harsh pruning of vegetation;

Reinstate the landscape following new service installation, where possible. Investigate the provision of boat laun.ching facilities in the Buffalo Patch area, as a means of alleviating possible traffic movement problems along Mairburn Road. PAGE 25

5.6 Public Areas Guidelines

Metung has a number of potentially high quality public areas. Shaving Point, the "Village Green", Patterson Park, the Lake King beach and the Hot P<:>ols, in particular, offer unique opportunities to establish first-rate public facilities for the community's enjoyment. Furthermore, the generally compact nature of the town environs facilitates pedestrian movement between these various public precincts.

The Local Structure Plan recommends that existing public areas in Metung be upgraded and, where practicable, linked by public walkways. The provision of a public board-walk along the foreshore from th~ yacht club to the residential properties to the south would alleviate the pedestrian/fishing and vehicular conflict along that section of Metung Road. A concept for a board-walk is depicted on Plan 15. Council wishes to emphasise that no board-walk would be proposed for foreshore areas abutting houses. The implementation of a one-way traffic movement system along Metung Road would also assist in removing the pedestrian and vehicular conflict. (Refer to the Traffic Management Study- Appendix 2).

The closure of Beach Road to vehicular traffic would also provide a valuable pedestrian/ cycling link to the town centre. The closure would also have the ability to provide additional car parking in close proximity to the Metung beach. Beach Road would still be available for emergency vehicles (Refer report- Appendix 3).

The "Village Green" should be protected as a key area of public open space in Metung and should be tidied-up in a manner commensurate with its "public face" and importance. It not only provides a focal point for public gatherings and passive recreation in the town centre but preserves a key visual link and vista to the lakes. The installation of sensitive perimeter landscaping (designed so as to protect rather than close-off views across the park) and upgraded park furniture will significantly remedy the existing situation without great expense and with immediate results. However, the open recreation space must be maintained. ------=---..·. . .. ·- ··-. - Ylt\V Act.OSS TE.tMHJATIOH Of WAW\VA~ TO 8ANC~OFT'JA'( . & A ».C. it. 0 F .T I ta 1

- . . - METHNG . · ·... ·· .· · ·. ·· .. · . ·.· ·.·. .· .·.·. ·. .· ~T~HCT~~t P AN • aoA~O\VALK P~Or054L ...· · ', ,.,_L,.. . )lb(--"'·u.___.....¥.n.. -a.-.- . lllllfffrtlllllllllllllllll . - . . . ~~'1.!';eott ·•·· ... 1~ . tOJJUl~ P E R R. 0 T .L Y · 0 N M A T _: H .I E . S 0 N . • ·-­,wtClliU

Plan 16 iliustrates a thel.Ilatic design style for future street furniture installation in public spaces ill Mehmg. The _-use of c~nsistent post . . . . · and infil\ design eleme:nts in street furnitl,lre fixtures will assist to strengthe~ and 1,1Ilify the.built charact~r.of ~he town.· .

·. · The. Public Area guidelines also include the. following . ad~tional elements:

.. .Attempt . !O achieve :Fniblfc access linkage~ throughbut · the settleme~t· and particul~rly .al(?ng the·· foreshore. Council :will prepa~e .a map of these.. linkages .to assist. cou:ndl's :decision . makirig when dealing. with planning applications~· .. .

..... Public ~ccess linkages should be desigil.edand located so as to be · · non-intrusive to private propertieS; ·. * :Improve the qU:ality of landscaping and design _pf f'!-cilith~s in the village green;

.. Reinstate tre.e planting and other landscaping improvements . . . ~. along the -public foreshore, as app:r;-opriate; .

·.. ·use· materiC;lls and ·landscaping which have low maintenance ~ . ' ' . ;. .. requU:ements;

* Introduce "the~es" in planting and design to. create a distinctly .. .· ¥etung character; <.

.. Council has colifirmed its SUpf>Ort for ~ Metung community hall . .:wit~ expanded youth recreational facilities;

.. .Upgrade· andmafntain the i.'ake King beach;

.. Upgrade car parking and .traffic, circulation facilities at Shaving· · . Point and impr6ve the public picnic-facilities. fLAtUEit.

.51GH&OAR.OS SEATING

rMCIHCT LIGHT ~ f>OLLA"D &IN SlATINC MET~NO LOCAL 5T~HCTW~t PL4N , 5TI\EET fHKNIT~~E ,.,_L,...... _ ... ,u...... ,__ ~- ,_:~::- 11111mrtlllllllllllllllll IUIW- PER R 0 T T LY 0 N MATHIES 0 N \b PAGE 71 .

5.7 ·Guideline~ ~ummary

_The principle. elemE:mts of each.of the .prece.ding Local_Structure Plan · · guidelinesjs suinmarised for quick reference. ~ . ' ~ ..

(i). ~uilding Development

_Design~ . ·muted co loUt tones

maximum· 7.5 .metres ·building height :above natural ground level . , .

. - . use ofbrick and/ or l;imber

vertical pro:portionirig ·preferred

' rooms wiUUn roof space at:e appropriate

minimi,se flat, blank fa~ades·

. - commercial buildings in ~OWn centres should· . ·incorporate. :posted vera~d~hs

.· o~e hou~e per ten:e~ent on Shaving Point '. have regard to· the Shire of Tambp'suGuidelines for Outdoor Advertis.ing Signs". .. .· . . . .

· Siting· - · · respect ·neighbouring dwellings amenity and , priyacy

minimal distUrbance to' established significant v~getati_on ..

cluster residential_development

- . · · ori~ritate for energy effiCiency PAGE 28

(ii) Subdivision:

Design- generally in accordance with the Victorian Code for Residential Development as amended by Council

minimum road construction standards for local residential access ways

cluster residential subdivision layout

incorporate pedestrian linkages

Residential subdivision proposals are to be accompanied by detailed plans which induae the following information: ·

* the location, size and contours of the subject site;

* existing significant vegetation and the location of any vegetation proposed to be removed to accommodate 'development;

* building envelopes

* details of utility service installation requirements;

* site access and road construction details;

* proposed landscaping details:

(iii) Landscaping

Theme- primarily indigenous species

retain existing significant vegetation

protect existing trees defining ridgelines PAGE 29·

" . Design- · integrate private.and.public landscaping where appropriate. . · . . . · . . ·

·'I ,. I · reinstate continuous ca.nopy planting i :. frame (rC\ther than. block) views ·

use timber and stone retaining structUres

. ., . . D~tailed landscape plans ·are to include the Jollowing InformatiOn: . ·· · ,

.... trees proposed to be retained;.

* . trees proposed.to be removed;

* :the existing contours of the subject l~nd; .

. . . .,. the proposed fhushed surface lev'els;· . . . . ' .

* details of underground and overhead seryices; '·

deta~s ·of pr~posed ·_new .. Planting, i~cl~ding sp~cres, l~c~tion and details of th·e nurumum s1ze at planting; ...... ·. . . · . · · ·.' * . details of any proposed paving, walls~ ·fences or other structures; .

. * details. of any slope· stabilisation· measures proposed; ,

•. V" • . ' details of any irrigation and drainage· methods . proposed.· · .. . · . · · · · (iv) . Traffic and Circulation

·Adopt the ·principles . outlined. ·in ·· the Metung/Stirlihg . Road tra_ffic manage:me;nt ·_system as detailed in Council report · ..

no through-traffic residert~alintrusions

adopt Victorian · Code · for Residential Development residential road ·standards.; as amended by Council .J

new road iocations to respect. topography ·and . significant vegetation . .· . .

investigate town centre traffic manageir{ent an:d signage works . . . . . · · . · .

facili~ate pedestrian-movement~ town cen~e

investig~te clos~r~ of Beach Road

investigate ·the proVislons of two-way traffic along Stirling Road extending to Beach Road. · .

'' ' . (v) - Utility Services·

-. _· all new development to· connect .~o· ·sewerage· .· ·system

"" . new development to instali underground power.

remstate·landscape aftei: service ~stallation'

underground the. power supply -to Shaving Point

. investigate the.· provision of boat~ lau,n~ng· · facilities in the BUffalo Pat<;h area. · · . ·. ' . PAGE 31

· (vi) Public. Areas

link public focal points by walk tracks

·investigate foreshore board-walk between Metung Yacht Club .and residential properties .. to sou~ .in conjun,ction with o~e~way. Me tung Road proposal

-maintain charact~r ·of _the. ''Yillage Green"·.

underground -power · . on Shaving·. Point ~pproach ,road

reir\st~te appropriate. tree . planting . along foreshore areas · ·

continue to upgrade Lake King beach. · . . .' .

upgrade Shaving Point car parking and public p1cnic facilities _ . :- · .

use street ftirniture and· fixture of a consistent' design

Couricil · confir~s · support for . a . ¥e_tung co~unio/ hall .

·•. PAGE 32

6 STATUTORY IMPLEMENTATION

The Metung Local Structure Plan is inten~ed· to present a clear statement of planning objectives and a consistent body of guidelines to encourage and assist the orderly future growth of the town. The implementation of the Structure Plan recommendations will be achieved in part by planning scheme controls and in part by providing the incentive to encourage appropriate action on the part of the community and developers.

The planning scheme controls will define the land use framework within which appropriate development can locate and take place. They will then require prospective developers to argue the development case in terms of how it meets the stated Local Structure Plan objectives. In response, the exercise of a degree of flexibility will be necessary in determining planning approval applications to allow for innovation in design.

6.1 Preliminary Actions

As a prelude to statutory implementation, the Metung Local Structure Plan shoulq be presented for public exhibition and consultation. Comments from the local community, relevant public authorities, and other interested persons and organisations should be invited. Following completion of the exhibition process, any submissions received should be considered and the Structure Plan should be refined where appropriate.

. The Local Structure Plan should then be formally adopted by Council resolution and should be implemented with consistency to encourage support from the local community, the development industry and the Administrative Appeals Tribunal. ,PAGE 33

-,·.. •' . 6.2· · ·Planning ~chem~_ ~endmerits :

The following am:end~ents-are tecq~ende~·to the existi:D.g T-ambo . - -Pla~g Sch~me to 'facflitate_ impl~mentatlo~ ~f t~e M~tung Lo~al: . . . Structure Plan, · · ._.

· * Include the Victorian Code ·for- Residential. Developm~nt .as. an .: · ' . ' . . ~- ~ , . Incorporat~cf rioc~ent · in ... the · Tambo · Planrrlng · Sch~me, ' . . ' including .the variations to the Code. adopted> b)t'Coundl; ._ . . .

. ' * . includethe fol19~ing new.~ub-cl~~se'in Chapter·2; .. " . . . . '

· the provisi~ns.· of the· _Mehu:lg· ,Local Structure Plan 1992. .

.. .

G-Uidelines for Pern;tit · ·- ... _, r • ..- • · :· .. -Befor_e deciding-on an application. to subdiv~de land . the . R~~ponsible · Authori.ty · _m'ust · consider~ in · particular:. .. . . < .·

.·. (i)_ . ~e a~ailabi.lity '.or_- setvice.s. iricluding sew:e:r:age, ·.drainage,_ wa:ter,- electricity, .telephone; . ··' ·. ·.

·.(ii) ·.: · :-.the a~ailability ~f vehiCle acc.~ss to the site; .. .-_ , · ·, ' . '

{iii) · . ·if applic~ble, the provisi~ns of the Metung· .- _. tocai Structur~ Plan 1992~ · ·

....

·,' PAGE 34

(b) · Before deciding on an .application • to construct .. buildings or. carry out "works, the Responsible Authority must·consider, ~n particular:

(i) the effect .on the amenity. of adjoiriipg or adja~ept properties; .

. (ii) , if applicabl~, the provisi~ns of th~ Metung. ·Local Structure Plan 1992.

(4) · Clause 12.6 'Guidelines· for Permit

B~fore deddi~g on an application to subdi~i~e land, con~truct buil~ngs . or carry - out w~r~s, the Responsible Authority must consider the provisions . . . ~ . ·of the Me tung Local Structure· Plan 199~. · ··

·* Incorpor~te the. "No Dev~lopment'' and "Conditional Developrhent" conceptinto the planning ~ontrols~

* -I!'vestigate·: the ,inclusion of l~w,..key ~ t~urist uses. into. the · Residential Zone:.;. · .. eg, restaurant c"fe bed and-breakfast gu~sthouse · arts and craft

. * . Introduce b¢lding height controls . . . . ·, * Introc!-uce pla~rtg contr.ols to allow oruy one hduSe per tenement . on Shaving Point. .

' '·. PAGE 35

7 INDUSTRIAL LAND USE

As an adjunct to the investigation and preparation of a Local Structure Plan for Metung, the consultants were asked to give consideration to the provision of a local light industrial precinct to serve the town. Whilst it is not the function of the Local Structure Plan to nominate a specific parcel of land for rezoning to accommodate industrial land use, a number of conclusions and guidelines can be drawn to assist proponents and the Council in the selection and consideration of suitable sites, should the need arise.

Very little provision is currently made for any form of industrial land use within Metung. However, whilst the major focus of maritime and industrial facilities on the Lakes is to be directed to Lakes Entrance and Paynesville (under the policy guidelines of the Gippsland Lakes Strategy 1990) it is reasonable_ to expect that some of the demand which might arise for local needs could be satisfied by .facilities located within closer proximity to Metung.

Metung township is primarily a residential and family-based holiday centre. It accommodates a relatively small permanent population and has a "retreat" holiday character. Accordingly, land use in the town is typified by residential and tourist accommodation and supporting commercial services. Given the residential and holiday retreat character of the town, its siting on an environmentally sensitive lakeside peninsula and its location at some distance from major through-road links, it is not considered appropriate that an industrial precinct be established within the Metung town perimeter itself. Any industrial development should be subject to:

* the provision of appropriate road access to and from the site;

* the availability of adequate land area to accommodate .on-site car parking needs;

* the treatment and disposal of all waste material, by-products and effluent within the subject site and without detriment to the environment or amenity of surrounding areas;

* the effective landscaping of the site to soften the visual impact of buildings and works to surrounding areas. PAGE 36

8 BOAT SLIPPING FACILIJIES

Council having regard tot~e boating actj.vity·-in·M~tung, believes thai-boat slipping facilities should be provided in Metung. .

A· report was :p~esen~ed. to Council _c~nsidering various lo:cation.in the Me tung area for ·a ~lipway facility; viz:. ·

* .Metl:ffig .Marina~.

* Buffalo Patch;

* ·. · ' N ungurner_j etty;

' ' * Chinainans Creek.

. J'he prefer~ed opti.on by Council i!~: the 1\t~etung Marina site.· The report is att~ched as App~ndix_4 to the Local StructUre Plan.

In. addition, Council has ·also. recommended -th~lt fishing platforms be . _in~orporated 'withht any area .set aside. for reclamation for. any propos~d slipway facility ..

,~ ' . APPENDIX 1

lnfiastructure Library . LocAL STRUCIVRB PIAN

INDIGENOUS PLANT SPECIES SUITABLE FOR USE IN LANDSCAPING AND REVEGETATION WORKS ATMETUNG

CLIFFS AND RIDGETOP Trees Eucalyptus tereticomis Forest Red Gum Eucalyptus pryoriana Rough-barked Manna Gum Eucalyptus baueriana Blue Box Eucalyptus bosistoana Coast Grey Box Eucalyptus melliodora Yellow Box Eucalyptus sideroxylon Red Ironbark Acacia melanoxylon Blackwood Banksia integrifolia Coast Banksia

Small Trees Acacia caerulescens Limestone Blue Wattle (a threatened species, but available in horticulture). Acacia dealbata Silver Wattle Acacia mearnsii Black Wattle Acacia pycnantha Golden Wattle Acacia sop horae Coast Wattle Allocasuarina littoralis Black Sheoke Pittosporum undulatum Sweet Pittosporum Rapanea howittiana Muttonwood Myoporum insulare Boobialla

Shrubs Bursarla spinosa var. macrophylia Sweet Bursaria Bursarla spinosa var. spinosa Sweet Bursaria Hymenanthera dentata Tree Violet Melaleuca parvistaminea Rough Paperbark Rhagodia candolleana Seaberry Saltbush MEIUNG

• i Creepers Tet~agonia implexicoma Bower Spinach

WETLAND

Shrubs · Callistemon citrinus Crimson Bottlebu5h · Callistemon pallidus ·Lemon Bottlebrush: . ' . Callistemon subulatus Dwarf Bottlebrush · Melale1,1ca ericifolia: Swamp Paperbark . . ,

. _,

... ·,

'.

- ,- . .. ; .

. '

. ' .. APPENDIX·. 2 . E Mtt ungTh'S

j - • ...

f'~ .· !.. L.. ·.· . . . . t ::· . ~ I •. ~ . .· . ' I . . . ~ . ' f . !~ . .. - .-. -

':>' • • J SHIRE OF TA-Mso . - .· :. -. ' I•, • • : ( • I .' ·~· · ' ' .. - .. l i:-: ...... : r - . . . "' . . . ;; -

- . ~; .

. . . . ~: . .;. ~ . . . . - ~~ "

. 1:; . ~:.....:..:.-=.....:..=...,,..:.=..:.:...~=--=:..=::.:..::..:..::~--=-=-....;::;_=.-=-

.·_ :1.. · -· . . _ . . . . . _ ~_1_! . . . II! .. . I' . . . . I . i . ' .. --- 1 .

.. i,i.:i_,•... · ·. · · · : :. r

. : ::!:. . . . .·· ...... - . . _· -'1..··'·_!..'1 __··'.·...... I . l I · · ·- · I ·_. L· ·· · · · t ...... __,r_,:.~_,.· . . ;~~=

. . . ..=~_:i_.'~.:~ . . . ·-·: ' . ' . .~t.~ . . . - . ~ ~ m . . . , t . ..- . . ::: :::::::;.;-:-:-:-:-:-:-:-::;.;.;:;.;-:-:-:-:=:-:-:-:-:-:-:-:-:·:-:·:·:·:·:·:-:-:-:-:-:-:-:-:-::;.;:;.;.;:;.;.;-:-::::;.;::-:-:-:-:-:-:-::;:;.;.;.;:;.;-:-:-::;:;.;:;:;:;.;-:-:-:-:-:=:=:-:-:-:-:-:-:-:-::;.;.;:;.;.;:;.;-:-:-:-:-:-:-:-:-:.:-:·:·:=:-:-:-:-:-:-::::;.:-:-:-:-:-:-:-:-:-::;:;.:-:-:-:-:-:-:·:·:·:·:·:-:-:·:-:-:-:-:-:-:-:-:-:·:·:·:·:-:-:-:-:-:-:-:-:·:·:·:-:-:-:-:-:-:-:-:-:·:·:·:·:·:·:·:·:-:-:-:-:-:-:-:-:-:-:-:-:-:·:·:,·:·:=:-:-:·:-:-:·:·:-:-:·:-:-:·::-:-:·:·:..:·:·:-"":·:·:-»:·:..=::·

...... ' E. Mtt ungTM)

SHIRE OF TAMBO METUNG TRAFFIC MANAGEMENT STUDY

PREAMBLE

This report is presented as a consequence of the meeting of the Metung Strategy Plan Committee held on 22nd October, 1992. The committee requested ·"A report from the Manager Engineering on a Traffic Management Plan incorporating one­ way traffic movement along Metung Road and two-way along Stirling Road".

INTRODUCTION

The objectives of the Draft Metung Local Structure Plan in relation to traffic and circulation are in part:- 1. Retain existing road network skeleton. 2. Provide easy vehicular access around the settlement via a single distribution loop-road. 3. Limit the opportunities for non-residential traffic to filter through residential precincts. 4. Maximise the opportunities for pedestrian movement around the foreshore and between residential precincts.

While the Traffic and Circulation Guidelines of the same plan state in part "... the road network essentially comprises a single distributor "loop road" from the north with branches accessing the commercial and residential areas. There is, therefore, very little opportunity for cross-town traffic or through-traffic intrusions into residential clusters. This pattern should be reinforced in any new development. New roads should be limited to residential accessways only and not provide opportunities for vehicle linkages through other residen_tial precincts. The main distributor road in Metung should be maintained, landscaped and signposted to enhance the visitor experience. "

This report will therefore consider the Traffic Management Plan in light of the above objectives and guidelines together with other matters considered relevant to or affected by the proposal. E. Mtt ungThS

- 2 - EXISTING CONDITIONS

(a) Metung Road- this road is classified as a declared Tourist Road, it is an arterial road and consequently attracts State funding through Vic Roads' allocations for the ongoing maintenance of the roadway. Works funded by Council are also undertaken on this roadway within the township. The section of roadway under consideration (as explained later) is that from the intersection with Nicholas Avenue (formerly Wood Street North) to the intersection with Essington Close (formerly Woo'd Street South) being approximately 1.5km in length.

The roadway has a 6.2m seal width and generally high embankments on the western side and varying (although usually narrow) shoulder widths on the eastern, or Bancroft Bay side.

During long weekends and school holidays, in particular the Christmas holidays, a conflict arises between vehicular traffic, pedestrians and fishermen. Vehicular traffic along this section of Metung Road increases dramatically over these periods and generally travels at or near the 60kph speed limit that applies. Due to the embankment on the western side and also the attractive vista available on the eastern side, the pedestrian traffic, which also increases dramatically, uses the eastern side of the roadway. However, due to the narrow nature of the shoulder and the closeness of the seawall to the edge of the road, these pedestrians are placed in close proximity to the vehicular traffic while walking in the same direction as that traffic. To further complicate this situation, fisherman park their vehicles along the eastern side of the roadway while they fish from the seawall adjacent. This then forces the pedestrians to walk on, or nearer to, the roadway to gain access past these vehicles. Obviously, a dangerous and undesirable situation.·

Recent traffic counts revealed that for the period of 25/11/92 to 14/12/92, an average of 1,077 vehicles per day used Metung Road compared with an average of 2,106 vehicles per day for the period 4/1/93 to 11/1/93, an increase of 96%. E. Mit ungThS

- 3- (b) Stirling Road - This road is a local collector road and as such relies on Council funded works for its ongoing maintenance and development together with possibl.e Federal funds granted through the Victorian Grants Commission and assigned by Council, eg proposed improvement and realignment of Stirling Road/Metung Road intersection.

Recently, seal widening and kerb and channel construction have been undertaken on the eastern side in conjunction with an adjacent subdivision (Fell Place).

Stirling Road is kerb and channelled on both sides from Kurnai Avenue to immediately south of King Street. From there it becomes a 6.2m wide sealed roadway with gravel shoulders (except for the previously mentioned section of kerb and channel adjacent to Fell Place), to Metung Road.

Stirling Road passes through an intensely developed residential area from Kurnai Avenue to Wood Street (formerly Reserve Road), then through a developing residential area to Metung Road.

The roadway has many intersecting streets (over which it has priority) and a school crossing serving the adjacent Metung Primary School.

Kingscote Drive, serving Leighton Bay Drive and ultimately the Storth Ryes development in addition to traffic generated by the proposed Metung Community Hall and development within Kingscote Drive itself, will become a significant intersection with Stirling Road. Consequently this intersection will require considerable upgrading irrespective of the outcome of this study.

The roadway is currently coping with existing traffic conditions subject to routine maintenance by Council. Recent traffic counts revealed that for the period of 25/11/92 to 14/12/92 an average of 578 vehicles per day used Stirling Road compared with an average of 953 vehicles per day for the period 4/1/93 to 11/1/93, an increase of 65%. E. Mit ungTM3

-4- (c) Howitt Avenue and Kurnai Avenue- These local roads provide links to Stirling Road from Metung Road. Funding for ongoing maintenance of these roads is as for Stirling Road. Both roads are fully constructed being sealed and kerb and channelled on both sides. Howitt Avenue would be considered the primary link between Stirling and Metung Roads .and ·as such would therefore be defined as a local collector road.

THE PROPOSAL

The proposal as requested for the committee's consideration would be to create Metung Road as a one way road, with traffic .travelling southwards (towards the town centre), from the Nicholas Avenue intersection, for a distance of approximqtely 1.5km, to the Essington Close intersection.

These locations have been selected to reduce the impact of the one-way road system on the residential nodes accessing Metung Road from: (a) Nicholas Avenue (62 properties from Bossie Court, Jamieson Avenue, Nicholas Avenue, The Anchorage, etc) who may wish to travel northwards towards Swan Reach; and (b) Essington Close (16 properties from Essington Close and Tara Street), who may wish to travel to and from the Town Centre.

The southwards direction of travel was selected as being the most obvious and scenic route for tourists and non-locals to travel to various destinations such as Terrazzas del Lago, Riviera Nautic, McMillan's Holiday Village, Metung Marina, Yacht Club, Bowling Club Tennis Courts, etc.

To have the traffic travelling in the other direction (northwards), would require this traffic to come in towards the town centre via Stirling Road and Howitt Avenue then find its way back along Metung Road to their destination.

Local traffic would be unaffected no matter which direction was selected as it would have to complete the Metung Road/Stirling Road loop to return to its origin. E. Mtt ungTh5

- 5 - The proposal would require traffic management devices to be constructed at the Metung Road/Nicholas Avenue and Metung Road/Essington Close intersections. The roadway would be reduced to a single lane with indented parking made available on the eastern side at regular intervals as space allowed. Finally, a shared walkway would be created/defined on the eastern side to provide access along the lake's edge for pedestrians and cyclists. (See Plan "A") Return traffic would be encouraged by the appropriate use of signs and traffic islands to travel via Howitt Avenue and Stirling Road back to Metung Road, these remaining as two-way roads.

Based on the previously stated "average vehicles per day" figures, it is anticipated that for the non-holiday periods, traffic along Metung Road and Stirling Road would become 539 and 1,117 vehicles per day respectively, while for holiday periods these figures would become 1053 vehicles per day for Metung Road and 2006 vehicles per day for Stirling Road.

With this increase in traffic along Stirling Road, consideration will need to be given to upgrade the section of that road between King Street and northwards to Metung Road by constructing kerb and channel and/or seal widening to cater for such additional traffic.

The section of Stirling Road and Howitt Avenue from Metung Road (at the Town Centre) northwards to King Street is fully constructed and considered satisfactory to cater for the additional traffic. However, it will be necessary to ensure safe pedestrian access is provided along the Stirling Road, Road Reserve by the construction of appropriate walkways.

POSSIBLE CROSSLINKS FROM STIRLING ROAD TO METUNG ROAD

Council at its meeting of the 1/12/92 requested that the feasibility of a vehicular link from Stirling Road to Metung Road along Park Road be investigated.

This has been done and the link is not feasible due to the steep nature of the land in the Park Road reserve between Stirling Road and Wood Street and the cliff that exists at the Park Road/Metung Road intersection point. Also investigated was the possibility of a link from Wood Street to Reserve Road in the vicinity of the Tennis Courts. This was also found not to be feasible due to the steep land that would have to be transversed to gain access to Reserve Road. E. Mit ungThS

-6- lt should be noted that such vehicular crosslinks would be contrary to the guidelines of the Draft Metung Local Structure Plan as referred to in the introduction of this report.

PARKING

Council has also requested that the feasibility of providing landfill to create a carparking area and associated facilities in the area of Chinaman's Creek be investigated.

The construction· of a carparking area by filling into Chinaman's Creek is possible. However, it would be expensive to achieve, would require the removal of a significant stand of vegetation and the project may have some difficulty gaining the necessary approvals from the Department of Conservation and Natural Resources, the Coastal Management Co-ordination Committee and the Department of Planning and Development.

However, by "squaring up" the Rosherville Road/Metung Road intersection by moving Rosherville Road westwards, a 20 space carpark area could be created between Chinaman's Creek and Rosherville Road. This could be achieved with minimal disturbance to the adjacent vegetation and without the need for filling into Chinaman's Creek. (See Plan "B")

It is felt that the parking needs of Metung should be further considered in total and addressed in a separate report. However, with the creation of the parking area referred to above and the additional parking· proposed to be created along Metung Road as a result of this study, the parking problems existing within Metung would be eased slightly. With the limited parking available within the Town Centre the parking areas to be created along Metung Road will act as "overflow" parking for special events and peak holiday periods.

ROAD LENGTHS

For the Metung Road/Stirling Road loop the following distances apply:­ Metung Road from Nicholas Avenue to Essington Close - 1.5km. Essington Close/Metung Road, Howitt Avenue, Stirling Road, Metung Road/Nicholas Avenue - 2.4km. Total Loop Length: 3.9km. E. l'kt ungTM:l

- 7 - CONSULTATION

Initial consultation has been held with Officers of Vic Roads. They advised that Vic Roads would offer no formal objection to the proposal and Metung Road would retain its status as a Tourist Road. However, Vic Roads funding would not be available to implement the proposals as detailed in this report for either Metung Road or Stirling Road.

PREVIOUS INVESTIGATION REGARDING PEDESTRIAN ACCESS

Council has previously investigated the cost of establishing a walkway along Metung Road from Rosherville Road to Howitt Avenue.

The investigation involved the use of three different types of construction to achieve the overall link, these being; 1 . Standard concrete footpath 2. Timber boardwalk 3. Road shoulder widening and sealing and placing of timber bollards to separate pedestrians and vehicles.

The investigation was ·based on two way vehicular traffic rema1nrng along the adjacent section of Metung Road. The estimated cost for the walkway was $355,300.00 and Council resolved that a further report be presented to Council of the basis of staged construction of the walkway. That further report has been held in abeyance pending the committee's consideration of this study. The provision of a walkway would be considerably cheaper as a result of the proposal discussed in this report as sufficient space would be created between the seawall and the through vehicular traffic lane to allow the walkway to be constructed/defined without the use of expensive timber boardwalks over the water adjacent to the seawall.

SUMMARY .)

A total of 92 properties will be directly affected by the proposal, these being 62 properties entering Metung Road via Nicholas Avenue, 16 properties entering Metung Road via Essington Close and 14 properties directly abutting Metung Road or gaining access via Reserve Road.

Also affected is access to the facilities at the Metung Recreation Reserve and adjacent Marina.

,·rr.. .1 ·~ f"1'r.

.D1 :J [~::0 [3! I 1j] •

·;

METUNG ROAD PLAN

500 2000 4800 3700

SECTION. A-A

CMC COII'II£ asP~ IKW) SHIRE lNCD omwa: P.O..:JX eo . OF· &NCES omwa ~ TAMBO A I I ··i

{. .. '·',

I -' . .' .f

I

\ ~

\ ' \ '­\ \ . \

\t\,·

- CMC camt£ a5 PAUIERS R

PHOHE (~1)Ml100 TAMBO- f'AX (051)5Sl128 --, E. ~rungn.s •

,. . :a-. . i · · · The pro~o~al.- by reducing th~ through traffic to a- single lane width, -~ould allow_ the · · · - provisio~ of ·parallel parking along Metu'ng Road; enable a review to occur ·ot: ttle -. · · - parking layout associated:· with -Metung- Marina and. R~reation. Reserve and - . _improve pedestrian and cyclist facilities along both Metung Roa~ and Stirli~g- Road· once completed~ ' ·- . . - . ' ~.-· __ . .

' .' " ·. The- proposal will require. a· ~onimitment by Coun~iFt9 progressively upgrade Stirling· ·_RQad and Metung ·Road ... -· -· - ·" ' • I ,, • ! '

CONCLUSION.

·'. '· :A em~ way traffic r:novern~rit ~long'Met~ng Road i~'feasible a~d would satis~ .traffic . and circulation ~bjectiv~s -( 1) arid (4)- of the Metung \ocal ;Strudure 'Plan in that it -,- . ~ould ret~in thf3 ~~isting ·road- netWork. skeletcl'n ·and maximi~e ~ped~strian· ac~es~ ·along the .foreshore and betwe~n. residential precinCts~ 'It' ~ould also satisfy ·the · ~-~traffic ·and Circu.lation guidelines· of.. the ~ame.pian by:~, ·.- - · · (a)· -_ Reinforcing: the· .sing_le distributo·r ·~loop -r~ad" netWork- a_~d. riot' c~eat"ing . ~ . ' . ~ . , .· vehicl~. linkages through other residential precincts.- - · . · ~- (b).- . - Enhancing the main .distrlbuto·i road in .Metung for.visit~rs to the" area...... ' ...... ~

- . -. - 1 • •! - ,. • . • ' . ~ • • • • However,. it ,could_ be argued thatjraffiG ~md circulation ·objectiv~_s (2) and_ (3) would... _ - -not be satisfied ~.s v.ehicularaccess aro~_nd -Meiung -- . would be more difficult'du$ : ' ·. to the· ~ingle. direction thaftraffic .would b~ torcecLtti follow and with retu·rn- t~affic·'. '.. ,• ' . _:.'-~having -t<;> use Stirlin9· 'Road,· non-resid~ntial- t~~ffic· ~o~ld be tray~Hing throt..ig~ . · existing and developing res-idential 'precincts. _ . - · · · . · . , · · · . . . . - . . . . . ~ . ·. . - . •. ~ .. .; :'· '' .._ However, prior to. making a· ·final decision,· furth.er· consultation \vifh .-relevant · . - A~t.horiti~·s · ~nd ne¢e~siu:y. public· consultation re~arding th~: proposal will be·_ -. ' . ' . ' ., . . . .., . . .required;,. :. ~ \ ..

... .·,,

''. E. Mit ungThS

- 9 - . ·RECOMMENDATIONS

(1) That detailed cost estimates of the proposal be undertaken for ·inclusion o~ cou·ncU's five year works Program .

.· (2) .. · A further report be prepared on parking· within_Me~~ng.township: . . ~ .

· ·· (3) · · That further consultatic;m with relevant ·Authorities arid the public be undertaken re_garding ·the proposal.

. · MICHAEL ELLIS· Manager_Engineering/Shire Engineer.

' . . . . •''

. - .. ~..

'· : APPENDIX 3 2213/1993

METUNG STRATEGY PLAN COMMITTEE MEETING

BEACH ROAD. ROAD CLOSURE. METUNG PREAMBLE

This report is presented at the request of the Metung Strategy Plan Committee at its meeting of the 20th January, 1993 where it resolved •That the Manager Engineering report back to the committee on the effects of closing Beach Road together with an estimate of liability and costs/savings associated with closing Beach Road and increasing potential traffic flows along Mairbum Road and the need to make provision for emergency vehicle and pedestrian access along Beach Road. Such report shall also look at the viability of parking areas at each end of any Beach Road closure." Also, Council at its meeting of 1st October, 1992 resolved that an application be made to Vic Roads detailing proposed road narrowings seeking to have a 40 kph speed restriction established for Beach Road. INTRODUCTION

Referring to the "Metung Foreshore Studyu prepared by Tract Consultants in November, 1986, the section of Beach Road to be considered by this report is located within Zones 3 and 4 of that Study. The Study states for the two Zones:- "Zone 3- Metung Town Beach" (Zone extends from a point just south of Kurnai Avenue to a point approximately midway along Beach Road to Mairburn Road.) "Site Analysis - Functioning as the main beach it is an area of major use offering an attractive beach primarily for family recreational use. The area adjacent to the beach is largely exposed with little vegetation. Provision for carparking is limited and largely undirected.... " "Recommendations" (In part) "(i) Develop the e)(isting beach area primarily as Metung Town and family beach.

(ii) Car parking should be planned in groups and shaded among the foreshore plantings." "Zone 4- Conservation/Pedestrian Area" (Zone extends from the midway point northwards to just south of Mairburn Road). "Site Analysis - an attractive, relatively undisturbed area creating a distinctly tranquil and natural atmosphere. The foreshore, backed by a densely native vegetated escarpment offers limited vehicle access to the small pebble beaches. The process of longshore drift prohibits large amounts of sand accretion in this area without the use of additional large groynes. The waters are inhabited by a variety of waterbirds, including black swans, while the undisturbed escarpment vegetation provides a suitable habitat for black cockatoos and other native birds .... 11

(Cont. over) 2213/1993

METUNG STRATEGY PLAN COMMITTEE MEETING

BEACH ROAD. ROAD CLOSURE. METUNG (Cont.)

"Recommendations" (in part) 11(i) .. .remnant ·coastal vegetation should be complemented with both native and exotic species as is already established to form· a corridor attractive to passive recreational uses. (ii) Access for fishing should be developed.... (iii) The feasibility of developing Beach Road as a traffic route for cars and boat trailer traffic is negligible without serious detrimental effects on the present qualities of the area. II "Traffic Management Policv" "Options: t. Total closure to vehicles .....

2. Create a one-way system south-north limiting speed II In light of the recommendations of the Metung Foreshore Study and the differing resolutions of the Metung Strategy Plan Committee and Council, two options will be explored by this report:-

(i) The closure of Beach Road to all vehicular traffic except emergency vehicles;

(ii) Creating Beach Road as a one-way roadway with limited speed capability. EXISTING CONDITIONS

(a) Beach Road- this road is a local road and as such relies on Council funding for its on-going maintenance and development. The section of Beach Road under consideration is that between Kurnai Avenue and Mairburn Road having a length of approximately 950 metres and a 5.0 metre wide formed gravel road pavement.

For the length of roadway under consideration there are no intersecting streets and none of the abutting properties have vehicular access to the roadway. · Pedestrian access to the roadway from Adsal Court is provided via a Janeway. Being"a gravel roadway the road requires regular maintenance (approximately four times a year at an estimated cost of $8,300 per annum).

(Cont. over) 22/3/1993

METUNG STRATEGY PLAN COMMITTEE MEETING

BEACH ROAD. ROAD CLOSURE. METUNG (Cont.) Recent traffic counts revealed that over the Australia Day weekend, an average of 337 vehicles per day used Beach Road compared with an average of 164 vehicles per day since then. A rising sewer main is located within the road formation at an average depth of 1.0 metres below the existing road level. (b) Mairburn Road- this road is also a local road and similarly relies on Council funding for its on-going maintenance. Mairburn Road is fully constructed, being sealed and kerb and channelled on both sides having a width of 8.2 metres between back of kerbs. The roadway is currently coping with existing traffic conditions subject to routine maintenance by Council. Recent traffic counts reveal that an average of 166 vehicles per day use Mairburn Road. ·

THE PROPOSALS 1. The Closure of Beach Road to all Vehicular Traffic This could. be simply achieved by the use of bollards and a gate or chain to allow emergency vehicles to enter .if required. The locations for the road closures would be 100 metres north of Kurnai Avenue and 20 metres south of Mairburn Road. The southern road closure in the vicinity ·of Kurnai Avenue would allow the creation of a carparking area for approximately 30 cars depending on the extent of landscaping undertaken. The northern road closure in the vicinity of Mairburn Road lacks area for an extensive carparking area, however, 3 or 4 car spaces could be created to service the needs for people living in that vicinity. Both car parking areas should be fully constructed and sealed. To provide pedestrian access along the foreshore following the road closure, a 3.0 metres wide gravel and sealed shared footway should be constructed. This would minimise Council's ongoing maintenance obligations, provide safe pedestrian access and would also provide a roadway for use by emergency vehicles. The proposal would require only line marking and signing at both the Kurnai Avenue/Beach Road and Mairburn Road/Beach Road intersections. Based on the "average vehicles per day" figures, it is anticipated that the traffic along Mairburn Road would increase from 166 vehicles per day to 330 vehicles per day which is well within the capabilities ot the existing Mairburn Road, roadway. However, consideration may need to be given to the construction of footpaths along Mairburn Road for improved pedestrian safety. (Cont. over) 2213/1993

METUNG STRATEGY PLAN COMMITTEE MEETING

BEACH ROAD. ROAD CLOSURE. METUNG (Cont.) Indicative costs for this proposal are:- Road closures (including signs and linemarking)- $2,500.00 Construction. of Carparking areas - $25,200.00 Construction of shared footway - $45,500.00

2. Creating Beach Road as a One-Way Roadway This proposal would require the construction of a 4.0 metres wide gravelled and sealed road pavement with frequent" road narrowings (by means of landscaping "islands~~). to widths of 3.0 metres to ensure vehicular speeds are kept to a maximum of 40 kph. The roadway would become a joint pedestrian, cyclist and vehicular precinct with the low vehicular speeds allowing safe use of the roadway by non-vehicular traffic. As in the first proposal, a sealed carparking area in the vicinity of Kurnai Avenue could be created for 30 cars. This carparking area would allow two way vehicular movement, becoming one-way (south to north) from a point 100 metres north of Kurnai Avenue. No car parking could ·be created in the vicinity of· Mairburn Road under this proposal.

Appropriate signing would be required together with a traffic management device constructed at the Mairburn Road/Beach Road intersection. Based on the .. Average Vehicles Per Day .. figures, traffic along Mairburn Road would increase from 166 vehicles per day to 248 vehicles per day again well within the capabilities of that roadway. Indicative costs for this proposal are:- Construction of roadway from Kurnai Avenue to Mairburn Road - $97,000.00 Construction of car parking area at Kurnai Avenue - $15,500.00

For comparison purposes, the estimated cost to construct Beach Road to a 5.6 metres sealed standard with 900mm shoulders suitable for two way traffic from Kurnai Avenue to Mairburn Road is . - $119,200.00. Funding

Council has previously applied for funding to upgrade Beach Road through VicRoads and by seeking tourist grants through the Victorian Tourist Commission both without success.

Therefore, the funding for the proposal selected would have to be by Council and therefore should be included in Council's 5 year Capital Works Programme. (Cont. over) 2213/1993

METUNG STRATEGY PLAN COMMITTEE MEETING

BEACH ROAD. ROAD CLOSURE. METUNG (Cont.) SUMMARY

A total of 112 properties would be affected by both proposals, these being 68 properties west of Mairburn Road and 44 properties within Mairbum Road, Lake King Place and Kings Court. Both proposals are considered feasible and both would complement the Metung Traffic Management Study previously presented to the committee and the soon to be prepared Metung Parking Study. The two proposals seek to reduce the conflict between pedestrians, cyclists and motor vehicles relating to road safety and dust with the road closure proposal obviously being the most effective in this regard. CONCLUSION

It is felt that the first proposal, that is to close Beach Road to vehicular traffic, best . meets the aims of the Metung Foreshore Study and effectively removes the pedestrian/cyclist/vehicular conflict that currently exists. It is also the least expensive of the two proposal~ considered. . However, this may be the least palatable option for those property owners who regularly use Beach Road for vehicular access to the town centre and the Mairbum Road property owners who will face a substantial increase in traffic on their roadway. This increase in traffic on Mairburh Road may also require Council to construct separate pedestrian facilities for the length of that road sometime in the future. However, prior to making a final decision, necessary public consultation regarding the two proposals will be required together with discussions with affected authorities.

--ooOoo-- APPENDIX. 4

(METUNG STRATEGY PLAN MEETING 20/1/1993)

BOAT SLIPWAY. METUNG

This report considers a number of options for the provision of a slipway in Metung to service boats with some 300 boats in the Bancroft Bay area requiring slipping facilities. Extensive facilities· are provided at both Paynesville and Lakes Entrance for taking boats out of the water for cleaning and maintaining, however this entails a trip of approximately one hour for boats berthed in Bancroft Bay. For smaller boats this trip may not be feasible in poor weather conditions and for keen racers the time and cost involved in going to Paynesville makes underwater fine tuning unattractive. There are currently two slipways in Metung, one at the Bulls Cruises site, the other a private slipway on the north east shore of Bancroft Bay. Indications are the Bulls Cruiser fleet will use their slipway for some 30 weeks of the year and allowing for bad weather, the remaining 22 weeks will not cater for the local demand or requirements for a slip. The scale of operation of Bury's slipway will only have a marginal influence on local slipping demands. The Gippsland Lakes Strategy states in relation to boating that "new facilities at Lakes Entrance, Metung and Loch Sport will be of a lesser scale than at Paynesville and provide only minimal subsidiary service functions. Paynesville will be the location for regional boating and service centre with marine industries such as boat construction, servicing and hire. • The Strategy also recognises that •new facilities at Metung will include wet storage and only minor maintenance slipping facilities•. Listed below are a number of locations considered for the provision of a slipway in the Metung area. (i) Metung Marina Restect Consultams Pty Ltd were commissioned by Council to investigate the technical feasibility of providing a suitable boat lift/slip at the Metung Marina. Their study examines 5 different concepts and provides cost estimates for each options, these being:- (a) Elevating boat lift platform attached to the jetty. (b) Crane on floating pontoon near roadway. (c) Crane on fixed platform near roadway south of rock. (d) Crane on fixed platform near carpark reclamation. (e) Slipway running from carpark reclamation in a south east direction. (f) Crane on fill near carpark reclamation with transfer capability. The Consultants were given the following designed parameters:- Maximum Boat Length 9 metres Maximum Beam 3 metres Maximum Draft 1.5 metres Maximum Weight 4tonne Both the Metung Marina/Chinamans Creek Advisory Committee and the Metung Yacht Club supported the recommendation of a rock fill slipway at the Marina using a tractor with winch, instead of a fixed winch to pull the boats up the ramp. The tractor would winch the trailer/cradle up the underwater portion of the ramp and once above water, the tractor could be direct coupled to the trailer to enable transport of boats away from the slip. Cont. over... -2- BOAT SLIPWAY. METUNG (Cont.}

The total cost of this slipway is estimated at $186,584 including provision of water, power, sewerage and a concrete surface bunded area on which to undertake boat maintenance. From a planning perspective the Marina is an existing non-conforming use. The land component is zoned Residential and Special Investigation Area and a slipway is a prohibited use in this zone. However a planning permit application process may be possible for a slipway adjacent and ancillary to the existing Marina as a change of prohibited use under Clause 5.3 of the Planning Scheme.

The advantage of this proposal is that the · slipway wo~d operate within the. confines of the Marina thereby reducing the level of opposition to the construction of the facility. The major disadvantage in locating a slipping facility at the Marina is the limited area available on shore to store or maintain vessels. This facility would exacerbate· the existing parking problems associated with the Metung Marina and therefore consideration should be given to better utilisation of the parking area surrounding the Metung Yacht Club. (ii) Buffalo Patch Site The area referred to as the Buffalo Patch is at the western extremity of Beach road past the intersection with Archibald drive. A slip in this location would provide good boating access when north easterly winds are blowing, reasonable access during periods of southerly winds, but unsatisfactory for use during strong westerly winds. Due to the exposed nature of the site it would be desirable to relocate the slip into the foreshore to provide some protection if the minimum water depth of 2 metres can be achieved. · The difficulty with the Buffalo Patch Site is the limited width of crown land foreshore available past the existing residential development. The width varies between 10 metres and 25 metres which is inadequate for the construction of a slipway. The abutting land is part of the Storth Ryes site and is zoned Special Use for medium density residential development. A meeting was held with the landowners and they advised they are not prepared to allow any of their land abutting the foreshore to be used for the development of a slipway. They have in mind to develop this land as part of the overall tourist complex. • The width of the crown land foreshore increases significantly to the east in front of the residences however, this area is heavily vegetated and would be unsuitable for a slipping facility due to the proximity of surrounding development. A number of tracks have been cut through the vegetation to give adjoining residents access to the beach, however these have limited width and would be unsatisfactory for a slipway. ,

The development of a slipping facility in the Buffalo Patch area would necessitate the upgrading of Beach Road from Archibald Drive preferably to a sealed standard, the extension of the 1OOmm water main from the last dwelling, provision of reticulated sewerage requiring the construction of a pumping station and the extension of SEC power to the site. The cost to provide these services would be significant.

Cont. over ... ------

-3- BOAT SLIPWAY. METUNG (Cont.) (iii) Chlnamans Creek Another site considered for.the construction of a slipway is in Chinamans Creek. The upper reaches of Chinamans Creek are well protected from all weather conditions and conveniently located for boats moored in the creek or Bancroft Bay. A major restriction to any development in the upper reaches of Chinamans Creek is the inability to gain suitable access. A gravel track off Rosherville Road currently accesses this locality, however it is totally inadequate and unsafe to be used as a means of access to a slipway. The valley in which Chinamans Creek flows is too steep to consider any alternative access from either Rosherville Road or Cantrills Road. Even if a suitable means of access could be established to the upper reaches of Chinamans Creek water depth in the creek at this location is limited. A minimum water depth of 2.0 metres is required to slip boats with a 1.5 metre draft which is common for many cruisers. A substantial channel would need to be dredged or excavated prior to constructing a slipway and an analysis of sediment movement in the creek bed would need to be undertaken to ensure the channel would not continually silt up. SEC power is available to the area with a water main extension required from the 1OOmm diameter main in Rosherville Road. The provision of reticulated sewerage would be expensive given that the line terminates at the Hot Pools. Environmental considerations would have a major impact if the upper reaches of Chinamans Creek were to be used for the slipping, servicing and maintenance of boats. The retention of as much natural vegetation especially the Maleucas surrounding the creek would be paramount in any development consideration. A slipway at the head of Chinamans Creek would require land acquisition from the property immediately to the north and zoned Rural B "Special Investigation Areau. There is inadequate foreshore reserve to accommodate a slip and associated hard stand areas. Under the provisions of the planning scheme, a slipway is prohibited in this zone as an industry, and would require a rezoning or site-specific amendment to proceed. (iv) Nungurner Jetty Located some 8 kilometres from the Metung township, this protected inlet at the end of Nungurner Jetty Road has potential for redevelopment and upgrading. There currently exists a public jetty, boat ramp, picnic area and adjacent car parking. The shallow water depth limits the usage of the boat ramp to small craft and any consideration of slipping facilities within this area would require the realignment of the seawall into the lake, achieving the required minimum depth of 2 metres. Foreshore reclamation associated with realignment of the seawall would enable expansion of the existing car park and would also provide an area for necessary land based activities associated with the slip.

If a slip were to be constructed in this vicinity it would be preferable to locate it on the north western shore of the inlet, well away from the residential development in Loop Road. This area is well protected from prevailing winds by Bell Point and Cont. over... -4- BOAT SLIPWAY. METUNG (Cont.) Flannigan Island and would only be affected by strong easterly winds along Reeves Channel. The land surrounding Nungurner Jetty is zoned Rural 8 and Special Investigation Area. A slipway is prohibited as an industry in this zone and would require a re­ zoning or site specific amendment to the planning scheme before proceeding.Nungurner Jetty has reasonable access via a sealed road although realignment and reconstruction of the last section would be desirable. SEC power is available, however there is no reticulated water or sewerage which would be essential for the development of an acceptable standard slipping facility. Summary

Each of the 4 ar~as considered as possible sites for a slipway have limitations. The Buffalo Patch site which initially seemed desirable is no longer feasible due to the limited width of foreshore reserve and the inability to secure abutting private land for a slipping facility. The Chinamans Creek area is well protected, however problems arise when considering the environmental nature of the creek as well as water depth, poor access, provision of services and the need to implement a planning scheme amendment for any development of this nature. Nungurner Jetty has the potential for upgrading of its existing boating facilities and a well designed slipway could complement the boat ramp and jetty. Development at this site would also require a planning scheme amendment and could not proceed until such time as reticulated water and sewerage were available. Of the options considered in this report the Metung Marina site seems the most suitable, given the availability of services, and no environmental constraints in terms of foreshore fragility due to the existing marina use. Under the planning scheme there is the ability to apply for a planning permit rather than being required to utilise a planning scheme amendment process as required for the other options. The major restriction with the marina site is the limited area available for the storage of boats on the lake side of Metung Road and further consideration may need to be given to extending the reclaimed area to the north. The boat storage area will govern the size of any slip operation at the marina site, restricting it to an appropriate level. A revision of the designed parameters for a slipway and (boat length 9 metres, maximum weight 4 tonne) should be undertaken now that a crane is not considered a viable option. -ooOoo-