PREFEASIBILITY REPORT

FOR

PROPOSED GRANITE QUARRY

Capacity: 4.0712 Ha

BY

M/S KABANI BLUENMETALS PVT. LTD.

Regd. Office: Chully House, Koratty East P.O., , - State - 680308

E-mail: [email protected]

Phone: 9947419588

Prefeasibility Report for Granite Quarry Mining <5 Ha Contents

Table of Contents 1. INTRODUCTION ...... 1 1.1 INTRODUCTION ...... 1 1.2 PROJECT SITE LOCATION ...... 1 1.3 PROJECT PROPONENT ...... 2 1.4 THE PROJECT ...... 2 1.5 SOCIAL INFRASTRUCTURE AROUND THE PROJECT SITE ...... 3 1.6 DISTANCE OF THE SITE FROM SENSITIVE LOCATIONS ...... 5 1.7 ACCESS ROAD ...... 5

2. PROJECT DESCRIPTION ...... 6 2.1 TYPE AND NEED FOR THE PROJECT ...... 6 2.2 MINE LEASE AREA ...... 6 2.3 PROPOSED METHOD OF MINING ...... 7 2.4 METHOD OF QUARRYING / MINING ...... 8 2.4.1 Method of Reserve Estimation...... 8 2.4.2 Exploration of Mineral Reserves ...... 8 2.4.3 Types of Reserves ...... 9 2.4.4 Insitu Reserves of Proposed Quarrying Area ...... 9 2.5 MINING ...... 9 2.5.1 Mineable reserves ...... 9 2.5.2 Year wise Production ...... 10 2.5.3 Conceptual Mining Plan ...... 11 2.5.4 Mode of Mining and Equipment Required ...... 11 2.5.5 Drilling and Blasting: ...... 11 2.5.6 Loading ...... 12 2.5.7 Storage of explosives ...... 13 2.5.8 Mining Drainage ...... 14 2.5.9 Storage of granite ...... 14 2.6 FIRE AND SAFETY PRECAUTIONS ...... 14 2.7 FIRST AID STATION ...... 14 2.8 ACCESS ROAD AND WIDTH TO THE PLOT ...... 15 2.10 POWER REQUIREMENT ...... 15 Prefeasibility Report for Granite Quarry Mining <5 Ha Contents

2.11 WORK FORCE REQUIREMENT ...... 15 2.12 WATER BALANCE ...... 16 2.13 PROJECT COST ...... 17

3. EXISTING ENVIRONMENTAL SCENARIO ...... 17 3.1 ENVIRONMENTAL BASELINE DATA DESCRIPTION ...... 17 3.2 CLIMATIC CONDITIONS ...... 18 3.2.1 Rainfall ...... 18 3.2.2 Temperature ...... 18 3.2.3 Relative Humidity ...... 19 3.2.4 Wind ...... 19 3.3 GEOMORPHOLOGY AND SOIL TYPES ...... 19 3.3.1 Geomorphology ...... 19 3.3.2 Soil ...... 20 3.3.3 Seismicity of the area ...... 20 3.4 GEOLOGY ...... 21 3.4.1 Physiography ...... 21 3.4.2 Regional Geology ...... 21 3.4.3 Geology of the Lease Area...... 22 3.5 RIVERS ...... 25 3.6 GROUNDWATER RESOURCES ...... 25 Source: Ground water Information booklet September 2008 ...... 26 3.6.1 Water Conservation and Artificial Recharge ...... 26 3.7 HYDROLOGY ...... 26 3.8 Land use ...... 29 3.9 BIODIVERSITY ...... 30 3.9.1 Objectives of the Study ...... 31 3.9.2 Methodology Adopted for the survey ...... 31 3.9.3 Flora ...... 33 3.10 AMBIENT AIR QUALITY STATUS...... 39 3.11 Water environment ...... 39 3.12 Noise level data ...... 41 3.13 Soil analysis...... 41

4 ENVIRONMENTAL MANAGEMENT PLAN ...... 43 Prefeasibility Report for Granite Quarry Mining <5 Ha Contents

4. ENVIRONMENTAL MANAGEMENT ...... 43 4.1 AIR QUALITY MANAGEMENT ...... 44 4.1.1 Controlling Dust Levels ...... 44 4.1.2 Controlling CO Levels ...... 45 4.1.3 Controlling NOx Levels ...... 45 4.1.4 Occupational Health & Safety Measure to Control Dust Inhalation ...... 45 4.2 NOISE POLLUTION CONTROL ...... 46 4.3 WATER ENVIRONMENT ...... 47 4.4 LAND ENVIRONMENT ...... 47 4.4.1 Rocks for landscaping ...... 48 4.4.2 Laying of the top soil ...... 48 4.5 WASTE DISPOSAL MANAGEMENT ...... 48 4.6 GREEN BELT DEVELOPMENT ...... 48 4.6.1 Criteria for selection of species ...... 49 4.6.2 Design of Green Development ...... 49 4.6.3 Programme for Afforestation ...... 50 Species ...... 50 Number...... 50 4.7 MEASURES TO CONTROL EROSION ...... 50 4.8 MEASURES FOR MINING EFFECT ON WATER ...... 50 4.9 CONTROL MEASURES FOR DISASTER ...... 51 4.10 SOCIO ECONOMIC ENVIRONMENT ...... 51 4.11 Mine closure ...... 52 4.11.1 Mine Closure Criteria ...... 52 4.12 ENVIRONMENT MONITORING PROGRAM ...... 56 4.13 REPORTING & DOCUMENTATION ...... 57 4.14 ORGANIZATIONAL SET-UP ...... 58 4.15 Budget provisions for EMP ...... 58 4.16 CORPORATE SOCIAL RESPONSIBILITY ...... 59 4.17 CONCLUSION ...... 60

Prefeasibility Report for Granite Quarry Mining <5 Ha Contents

LIST OF TABLES Table 1-1 Split up of Lease Area ...... 2 Table 1-2 List of Social Infrastructure around the site ...... 4 Table 1-3 Sensitive locations from Project Site ...... 5 Table 2-1 Split up of lease area

Table 2-2 Boundary Coordinates…………………………………………………………………………………………….. of the Site ...... 6 Table 2-3 Calculation of Reserves ...... 9 Table 2-4 Year wise Minable Reserves ...... 10 Table 2-5 Year wise Production ...... 10 Table 2-6 Land Use at the End of Life of the Project ...... 11 Table 2-7 Machineries to be deployed ...... 11 Table 2-8 List of Explosive to be used and the Quantity ...... 13 Table 2-9 Project cost Break up ...... 17 Table 3-1 Physiographic units in District ...... 19 Table 3-2 Stage of Groundwater Development ...... 26 Table 3-3 Showing land use pattern in in kerala ...... 30 Table 3-4 Vegetations of Ever Green Forest ...... 33 Table 3-5 Vegetations of Semi Ever Green forest ...... 36 Table 3-6 Regeneration status of endemic species ...... 38 Table 3-7 Regeneration status of endangered or threatened species ...... 38 Table 3 - 8 Ambient Air Quality sampling Locations

Table 3 - 9 Ambient Water Quality sampling Locations…………………………………………………

Table 3-10 Water Sampling Results ……………………………………………. 0

Table 3-11 Ambient Noise Levels in ……………………………………………………………………… Villages Day Time ...... 41

Table 3-12 Soil Quality Results ...... – 41 Table 4-1 Afforestation Programme ...... 50 Table 4-2 Time Scheduling For Abandonment and Cost Abandonment ...... 55 Table 4-3 Budget for Environmental Monitoring Plan Operation Phase ...... 56

Table 4-4 Environmental Monitoring Plan Post Operation– phase ...... 57 Table 4-5 EMP Budget Provisions ...... – 59 Table 4-6 CSR Budget Allocation ...... 60

Prefeasibility Report for Granite Quarry Mining <5 Ha Contents

LIST OF FIGURES Figure 1-1 Location map of the site ...... 1 Figure 2-1 Google image showing Site Boundary and approach Road ...... 7 Figure 2-2 Schematic diagram of opencast mining method ...... 8 Figure 2- ...... 14

Figure 2-4 ProposedWater balance Location chart of ...... Magzine N=° ’.”; E=°’.” 16 Figure 3-1 Photographs showing geology of the site ...... 24 Figure 3-2 Kannur District Map showing Hydrogeology ...... 28 Figure 3-3 Land Use Pattern in Kannur ...... 29 Figure 4-1 Environmental Management Cell ...... 58

Prefeasibility Report for Granite Quarry Mining <5 Ha

1. INTRODUCTION 1.1 INTRODUCTION

M/S KABANI BLUE METALS PVT LTD. proposes to set up a granite stone quarry unit at Survey Nos. 127/1 of Pulingome village, Taluka, Kannur District of Kerala State. The proposed quarry area for mining is 4.0712 Ha. The land documents are enclosed in Annexure-2.

1.2 PROJECT SITE LOCATION

The proposed site is located at Survey Nos. 127/1 of Pulingome village, Taliparamba Taluka, Kannur District of Kerala State. The land use classification of the project site is dry land/rock land. The location map of the site is given in Figure 1.

Figure 1-1 Location map of the site

1

Prefeasibility Report for Granite Quarry Mining <5 Ha

1.3 PROJECT PROPONENT

The project proponent is M/S KABANI BLUE METALS PVT. LTD., Mr. C. C. Anthony is the Managing Director and Authorized signatory of M/s. Kabana Blue Metals Pvt Ltd and authorized to submit application to statutory authorities like Department of Mining & Geology, SEIAA/DEIAA, Kerala, etc, Annexure – 1. Attested Copy of Photo ID of the Authorized Signatory also enclosed as Annexure- 8 ., Regd. Office: Chully House, Koratty East P.O., Thrissur District, Kerala - State 680308 E-mail:

[email protected] Phone : 9947419588 – 1.4 THE PROJECT

The proposed project is quarrying of granite rock with an area of 127/1 Ha. The site is at of Pulingome village, Thalasserry Taluka, Kannur District, and Kerala. The Surveys Nos. are 127/1. It is proposed to mine 23.66 TPD (67 cum) of granite stone from the site. Among total area, Survey No: 127/1 (4.0712 Ha). Table 1-1 Split up of Lease Area

S.No Proposed Survey No. Type of Land Area ( Ha) 1 4.0712 127/1 Private Land (patta land) Total 4.0712 Ha

Legal Background order dated 27.02.2012 in I.A. No. 12-13 of 2011 in SLP(C) No-19628-19629 of 2009 (Deepak Kumar etc vs. AccordingState of Haryana to Hon’ble and others)Supreme the Court prior ofEnvironmenta , as perl Clearance is mandatory for the issuance of license/permits for ensuring that quarry possess a valid Environmental Clearance. Kerala Minor Mineral Concession Rules 2015 also makes it mandatory to get environmental clearance for quarrying lease. It is hereby submitted that it is not necessary to obtain No Objection Certificate from any other Department/Agencies for applying Environmental Clearance from the Aditional 5th respondent.

2

Prefeasibility Report for Granite Quarry Mining <5 Ha

1.5 SOCIAL INFRASTRUCTURE AROUND THE PROJECT SITE

The proposed site is surrounded by various places like schools, Hospitals, residences etc. The same is given in Table 1-2. The 10 Km radius map of the site with the infrastructure is enclosed as Plate -9. The Area Survey plan approved by Village officer is enclosed in Annexure-11.

Table 1-2 List of Social Infrastructure around the site

S. No. Places Dist. from Project Site (Km) Schools & Colleges 1. Snehagiri convent 4.90 Km 2. Palavayal LP school 7.57 Km 3. GVHSS 6.15 Km 4. GHSS 3.92 Km Residences 1 Kozichal 2.60 Km 2 Rajagiri 0.56Km 3 Pulingome 6.20 Km 4 Palavayal 7.52 Km 5 Odakolly 5.95 Km 6 Theyyeni 9.13 Km 7 6.82 Km 8 Prapoyil 9.55 Km 9 Tabore 3.87 Km 10 Thalipara 3.42 Km 11 Ariviranjapoil 2.84 Km 12 Josegiri 1.40 Km 13 Santhipuram 3.62 Km 14 Udayagiri 5.04 Km 15 6.25 Km

3

Prefeasibility Report for Granite Quarry Mining <5 Ha

S. No. Places Dist. from Project Site (Km) 16 Parappa 6.78 Km Hospitals 1. Koyili Hospital 45.30 Km 2. District Hospital Kannur 48.15 Km 3. Vasan Eye care 47.56 Km

1.6 DISTANCE OF THE SITE FROM SENSITIVE LOCATIONS

The sensitive locations from the project site are given in Table 1-3. Table 1-3 Sensitive locations from Project Site

Sr. no. places Distance from project site

1 St. Augustine church 1.23 Km 2 St. George Church 3.25 Km 3 St. Sebastian Church 2.65 Km 4 3.25 Km

5 St. JosephMary’s ChurchOrthodox Church 1.12 Km 6 Thrikkannapuram Siva temple 2.44 Km 7 Chattivayal Temple 4.27 Km 8 Mother Theresa Church 5.00 Km 9 5.19 Km

10 St. Jude’s Shrine 4.72 Km St. Mary’s ChurchSensitive Places 1 Bheemanadi Reserve Forest 20.78Km NW

Rivers –

1. Thejaswini River 7.30 Km W

2. Kuppam River 6.06 Km S

4

Prefeasibility Report for Granite Quarry Mining <5 Ha

1.7 ACCESS ROAD

The site will have access through the existing tar road (Kozichal-Rajagiri-Josegiri Road). This road passes ~0.10Km away from the site in the North-west direction. The proposed site is well connected to Rajagiri, Josegiri by the tar road. This is the public road which will be used for transportation of rocks through trucks during mining operations. The surface plan with mine lease area and the approach road is enclosed as Plate-2.

2. PROJECT DESCRIPTION

2.1 TYPE AND NEED FOR THE PROJECT The proposed project is mining of granite rock within proposed area of 4.0712 Ha. The proposed project is Category B2, S. No. 1 a since the proposed mining area <5 Ha. It is proposed to mine 67 cum of rock / Day. Granite is one of the primary building materials. The proposed mining activity is the backbone for all construction and infrastructure projects, as the raw material for construction is available only from such mining.

2.2 MINE LEASE AREA The proposed area for mining is 4.0712 Ha. The details of split up of proposed area are given below in Table 2-1. The surface plan showing the lease applied boundary, mine approach road, contour etc is enclosed as plate -2. Table 2-1 Split up of Lease Area

S.No Proposed Survey No. Type of Land Area ( Ha) 1 4.0712 127/1 Private Land Total 4.0712 Ha

The said quarry lease falls between the geographical co-ordinates of the extreme boundary pillars are shown below in Table 2-2. Table 2-2 Boundary Coordinates of the Site

5

Prefeasibility Report for Granite Quarry Mining <5 Ha

Latitude (N) Longitude BP-1 12°17'8.31" 75°28'24.95" BP-2 12°17'11.37" 75°28'26.78" BP-3 12°17'9.28" 75°28'29.95" BP -4 12°17'9.60" 75°28'30.22" BP-5 12°17'7.71" 75°28'32.30" BP-6 12°17'8.40" 75°28'33.06" BP-7 12°17'7.16" 75°28'33.82" BP-8 12°17'5.07" 75°28'35.14" BP-9 12°17'2.96" 75°28'31.63" BP-10 12°17'4.04" 75°28'30.14" BP-11 12°17'4.53" 75°28'29.71" BP-12 12°17'3.58" 75°28'28.65"

Figure 2-1 Google image showing Site Boundary

2.3 PROPOSED METHOD OF MINING Open cast method of mining on single shift basis is proposed to excavate the rock to gradually achieve the production target. Loosening of the hard rock mass will be effected through blasting. Blasting will be done by using Hydraulic jackhammer. Rock breaker will be used to break down large bolder to small sized bolder. Excavators will be used for excavation & loading of the blasted materials in to

6

Prefeasibility Report for Granite Quarry Mining <5 Ha

tippers/trucks. The rock waste materials if generated it will be used for mine closure.

Drilling

Blasting

Bench formation

Excavation

Loading into Tippers

Transportation to

crushers

Figure 2-2 Schematic diagram of opencast mining method

2.4 METHOD OF QUARRYING / MINING Based on the mode and method so adopted and taking geological parameters of the ore body into consideration, the quarry pit is designed such that the height of the bench will be kept about 5.00 m max., and width will be at least 5.00 m.

7

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.4.1 Method of Reserve Estimation The insitu reserves of recoverable reserves are worked out in proposed mining area for 5 years by taking section lines considering the area of influence and specific gravity of Granite. 2.4.2 Exploration of Mineral Reserves The nearby area has escarpment. (>20 m) and wells which shows the presence of lava flows which more than 20 m. Therefore, as such the exploration is not required in this area. The Deccan Traps has thickness over 2000m in the west which gradually reduces to 60m towards East (Geology and Mineral Resources of Kerala 2000, Govt. of Kerala, June 2000, pp. 09)

2.4.3 Types of Reserves The in situ and recoverable reserves have been estimated separately. Three section lines are drawn to calculate reserves with existing pit as the base. Assuming 25m depth from top surface level, working will be done in first phase and after excavation of this area prospecting will be done in future for further investigation of hard rock formation, up to depth of 25m below the average level of the present quarry level. The working pit plan showing the section line and year wise working for five years is enclosed in Plate-4 and 4A. 2.4.4 Insitu Reserves of Proposed Quarrying Area The sample quantity of Basalt is available in the lease area. The reserves are calculated by proposing two section lines namely A A`, B B` and C-C`. The section

lines are shown in the Geological plan enclosed in plate-3– and– 3A. The reserves are calculated and shown in the Table 2-3. Table 2-3 Calculation of Reserves

SECTIONAL AREA INFLUENCE VOLUME Bulk density TONNAGE

A-A` 6470 75 485286 2.5 1213217

B-B` 10022 100 1002295 2.5 2505738.5

C-C` 8175 70 572302 2.5 1430756

TOTAL 24669 2059884 5149711

8

Prefeasibility Report for Granite Quarry Mining <5 Ha

Possible minor mineral extraction from the available area would be 5149711Metric Ton  Considering 50000 MT per year production,

2.5 MINING 2.5.1 Mineable reserves Average production per year is proposed to be about 50,000 tones. The way excavation will be made in ensuing five years will be based on the following calculations as given in Table 2-4.

Table 2-4 Year wise Minable Reserves

Year Section Level Sectional Influence Volume in Production in metric area cu m tonnes

100 I B-B` 140/135 49 4900 12250 135/130 73 100 7300 18250 130/125 22 100 2200 5500 C-C` 135/130 27 75 2025 5062.5 130/125 48 75 3600 9000 50062.5 II B-B` 130/125 70 100 7000 17500 125/120 76 100 7600 19000 C-C 125/120 72 75 5400 13500 50000 III B-B` 125/120 42 100 4200 10500 120/115 106 100 10600 26500 120/115 70 75 5250 13125 50125 IV B-B` 120/115 45 100 4500 11250 115/110 82 100 8200 20500 C-C` 120/115 28 75 2100 5250 115/110 70 75 5250 13125 50125 V A-A' 110/105 62 75 4650 11625 B-B` 115/110 80 100 8000 20000 110/105 30 100 3000 7500 C-C` 115/110 58 75 4350 10875 50000

9

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.5.2 Year wise Production The year wise production is proposed as follows Table 2-5 Year wise Production

Sr.No. Year Cubic meter Tones 1 I 20025 50062.5 2 II 20000 50000 3 III 20050 50125 4 IV 20050 50125 5 V 20000 50000

Thus excavation to be made in next five years would be to the tune of 250312.5M3 at the rate of yearly production of 50,000 tones.

Working pit plan and working section for five years are shown in plate No. 4 and Plate No. 4A respectively (Annnexure-11) 2.5.3 Conceptual Mining Plan The following factors have been considered to design ultimate conceptual plan. i. Overall composite shape and lease area available for mining. ii. Relief of the area, iii. Ultimate closing bench geometry is as given below: Bench Width : 5.00 meter Bench Height : 5.00 meter Pit slope :

Stone being very compact massive rock and˚ it is stable as such above geometry is reasonable safe. iv. Conceptual plan is shown in Plate No. 5 Table 2-6 Land Use at the End of Life of the Project

Sl.no Particulars Extent in Ha End of mine life# 1 Mine area 3.0334 Ha 2 Road 0.3000 Ha 3 Afforestation 0.7378 Ha 4 Unmined area - Total area 4.0712 Ha

2.5.4 Mode of Mining and Equipment Required The list of machine to be used in quarry operations is given in Table2-7 below.

10

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 2-7 Machineries to be deployed

S.No. Machinery Capacity Numbers 1 Hydraulic excavator 1.2 m3 1 2 Compressor 2 3 Jack Hammer - 2 4 Tipper 10 T 6 5 Water tanker cum sprinkler 5 KL 1

2.5.5 Drilling and Blasting: Since the quarry is being worked by mechanized means and the benches are kept at 5.0 m height and the Charnockite is the material which is hard to medium hard in nature, drilling and blasting is required to exploit the same. On an average about 67 CUM of material required to be drilled and blast daily. The broad blasting parameters are determined for the blasting pattern and blast design, which are as follows: Since the bench height needs to be maintained 5.0 m, two sub benches will be created of 2.50 m height each and both the benches will be joined / merged together to form 5.00 m height. Blast hole will be preferably by jack hammer where the diameter is normally 32 mm and the depth of hole is 3 8 ft. Blasting pattern is generally square or

rectangle or staggered with burden– ranging from 0.75 to 1.00 m and spacing of 1.00 to 1.20 m. Usually single / double row of holes is blasted along free to achieve optimum powder factor, best fragmentation and minimizing adverse impact on account of blasting. Maximum numbers of holes will be blasted at a time in a round are generally limited to 20 to 30 with normal delay detonators to mitigate adverse impacts such as air blast, throw and the ground vibration. Holes are electrically detonated using electric detonators. Nitrate mixture types of explosives will be used for blasting with 20 to 25 percent, proportion of primer/booster cartridges and rest as column charge. About 1 to 1.5 kgs of explosives are loaded in 32 mm diameter holes. And powder factor ranging between 5.0 to 7.0 tonnes per kgs of explosives is achieved. Lessee is having the Explosive license.

11

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.5.6 Loading Subsequent to the drilling and blasting, the material so dislodged/fragmented/loosened from the rock mass, the boulders so generated subsequent to blasting will be crushed or broken with the help of the rock breakers to the required size. There after the materials is loaded into trucks/tipper of 5.0 tones capacity with the help of the excavator. The loaded materials is transported to the Client destination/or other crushing and screening units for further process. Regular water spraying on haulage roads during transportation of excavated material by water sprinklers. Transfer points shall be provided with appropriate hoods/chutes to prevent dust emissions.

2.5.7 Storage of explosives There will be provision for storage of explosives like Nitrate mixture, Ordinary detonator, electric detonator, safety fuse at site. The quantity of explosives to be used is given in table below. Table 2-8 List of Explosive to be used and the Quantity

S.No Description Class Division Quantity to be used Possessed at per day To be any one time used in month 1 Nitrate 2 - 100 Kg 12 Kg 300 kg Mixture 2 Ordinary 6 1 2000 mt. 96 Nos 2400 detonator Nos 3 Electric 6 3 2000 Nos. 96 Nos. 2400 detonator Nos 4 Safety Fuse 6 3 2000 Mtr 180mtr 4400 Mtr

The storage magazine is proposed in the western side of the lease. The distance of the site from storage premises is 98 m. Log book will be maintained to enter the amount of explosives used per day and the stock. Proper safety measures shall be followed for safe storage of explosives. Copy of explosive license is enclosed as Annexure-12.

12

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.5.8 Mining Drainage The lease applied area is on the plateau terrain with overall slope in the direction of South. There are no perennial water courses in and around the lease area. During monsoon surface water will flow following the natural relief of the area. Before the onset of monsoon, drains will be cut along toe of the quarry faces to divert the surface run off. Garland drain is provided at the quarry top to regulate monsoon water to direct the same to the settling ponds / quarry pit to contain the quarry wash off and to avoid the same joining the adjoining surface water bodies / water courses. It also helps to avert eventual collapses and damages to the quarry faces. The pit will be fenced by barbed wire, such that no habitats can enter the pit and watch and ward is provided round the clock.

2.5.9 Storage of granite Normally the aggregate produced will be dispatched immediately after production. In case it is to be stored there will be sufficient space on both sides of the mine road and also open space will be available in lease area for storage. Open cast quarrying method shall be adopted for extraction.

2.6 FIRE AND SAFETY PRECAUTIONS As per the Mine Act, the entire quarry will be carried out following the DGMS safety regulation. Fire fighting systems like extinguishers will be provided in the explosive storage area and the workers will be taught about the usage of extinguishers. Also mock drills will be conducted to the staff as to how to respond during fire. The emergency phone nos. of nearby fire station, hospital will be made available at site. The staff working at site will be provided with safety shoes, goggles, ear plugs during blasting operations, safety masks etc.

2.7 FIRST AID STATION First aid room, first aid kit and also the experts of first aiders will be maintained as per guideline of the DGMS and MMR 1961. First aid station will be provided with all necessary medical kit. All staff will be trained in first-aid treatment to take care of any emergency.

13

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.8 ACCESS ROAD AND WIDTH TO THE PLOT The access road width is being maintained with 7.0 m for the movement.

2.10 POWER REQUIREMENT Since the project is granite rock excavation, there is no power requirement for the proposed project. Diesel driven compressor of 30 HP will be used for drilling purpose.

2.11 WORK FORCE REQUIREMENT There will be nine people working at site during the operational stage. The workers will be hired from nearby villages and proper drinking water and sanitation facilities will be provided for them at site.

14

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.12 WATER BALANCE Water will be used only for drinking and other mining activity purpose. Bore well will be drilled by the proponent and permission will be taken from the concerned authorities. Detailed water balance is given below in Figure2-3.

Total water consumption

11 KDL

Other purpose Human Consumption 9 KLD 0.5 KLD

Greenbelt Development Dust Suppression Soak pit 3 KLD 6.5 KLD

Figure 2-4 Water balance chart

15

Prefeasibility Report for Granite Quarry Mining <5 Ha

2.13 PROJECT COST The Total cost of the project is proposed as Rs. 59.0 lakhs. The cost break up is given in table below Table 2-9 Project cost Break up

S.No. Details Cost (In Lakhs) 1 Land cost 10.00 2 Machinery 12.00 3 Vehicles 15.00 4 Cost towards EMP 12.00 5 Insurance and CSR 10.00 Total Cost 59.00

4. EXISTING ENVIRONMENTAL SCENARIO

3.1 ENVIRONMENTAL BASELINE DATA DESCRIPTION The main objectives of environmental baseline study are I. To assess present environmental quality and the environmental impacts and II. To identify environmentally significant factors that could preclude project development. The chapter contains information on existing environmental scenario for the following parameters. 1. Climatic conditions 2. Air Environment 3. Noise Environment 4. Soil Environment 5. Water Environment 6. Land Environment 7. Biological Environment 8. Socio-economic Environment

16

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.2 CLIMATIC CONDITIONS

3.2.1 Rainfall

Kannur district receives a total annual rainfall of around 3438 mm. District experiences heavy rainfall during the South West monsoon season followed by North East monsoon. South West monsoon during June to September contributes 70 % of the total rainfall of the year. The northeast monsoon contributes only about 30%. The distribution of rainfall during year 2006 to 2011 is shown in Table 1. Rainfall is considerably less during the period from January to May.

Table 1: Monthly rainfall in Kannur district (Period 2006-2011)

Year Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec Total

2006 0.0 0.0 16.0 5.0 617.0 735.0 674.0 491.0 570. 267.0 97.5 2.0 3475.0 0 2007 0.1 0.2 0.0 45.4 213.4 949.8 1115.9 783.8 595. 315.1 72.3 0.2 4091.8 6 2008 0.0 0.6 250.2 23.7 56.6 725.8 483.6 480.3 396. 392.5 3.0 9.8 2822.5 4 2009 0.0 0.0 9.3 97.2 169.6 625.3 1456.2 299.5 320. 200.3 306.8 48.7 3533.4 5 2010 19.1 0.0 9.4 65.3 137.0 843.9 959.6 511.0 269. 342.3 338.1 2.3 3497.3 3 2011 0.0 0.0 0.0 90.3 44.3 1093.8 852.5 647.5 436. 214.5 91.4 0.5 3471.2 4

The year to year variability of annual rainfall is around 28.2%. In general, the rainfall increases from the coast to the eastern hilly regions. Kannur district falls

under wet type of climate based on Thornthwaite’s climatic classification. 3.2.2 Temperature The temperature is more during the months of March to May and is less during December and January. The average mean monthly maximum temperature ranges

0 0 from 28.4 to 36.9 C and minimum temperature ranges from 19.7 to 23.9 C.

17

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.2.3 Relative Humidity

Relative humidity is more during south west monsoon season (ie June to September). It is more during morning hours and is less during evening hours. Humidity ranges from 77 to 88 % in the district.

3.2.4 Wind Wind speed ranges from 2.1 to 3.3 km per hour with mean speed of 2.6 km/hr. The wind speed is high during the period from March to June and low during the period from September to December

GEOMORPHOLOGY AND SOIL TYPES

3.2.5 Geomorphology

Kannur district can be divided physiographically into three distinct geomorphologic units viz the coastal plains and lowlands in the western part, the central undulatory terrain comprising the midland region and eastern highland region. (Table 3-2).

Table 3-1 Physiographic units in Kannur District

Sl. Physiographic Unit Arial extent (Km2) Elevation No. (mamsl) 1 Coastal plain 82 <5 2 Mid land 700 5-80 3 Hill ranges 1950 80-1500

The coastal plains occurs as a narrow belt of alluvial deposits running parallel to the coast with a maximum width of about 15 km. Midland region forms a plateau land at certain places covered by a thick cover of laterites. The hilly tract in the eastern part consists of highly rugged terrains. The peak (259.69m) with the characteristic N-S alignment is a distinct physiographic unit in the coastal plains. Minor cliffs of laterite generally rising to an elevation of 50 to 60 m above mean sea level are found at Mahe, Thalasserry and Bekal coast. The midland region presents a plateau land covered by a thick cover of laterite. 18

Prefeasibility Report for Granite Quarry Mining <5 Ha

This is immediately to the east of the coastal strip, rising from 40 to 100 m above msl. The valleys in the plateau are gorge like and V shaped cut by youthful streams. The hilly tract along the eastern part of the district constitutes the highland region and is highly rugged.

3.2.6 Soil There are mainly four types of soil observed in the district.

(1) Lateritic soil

(2) Brown hydromorphic soil

(3) Coastal and river alluvium

(4) Forest Loamy soil

(1) Lateritic soil The predominant soil in the district is lateritic soil, which is the weathered product derived under humid tropical conditions. It occurs mainly in the– midland and hilly areas characterized by rugged topography. They range from sandy loam to red loam.

(2) Brown hydromorphic soil These are confined to the valleys between undulating topography in the midlands and in the low lying areas of the coastal strip in the district. These– soils are brown in colour and the surface texture varies from sandy loam to clay. They have been formed as a result of transportation and deposition of materials from adjoining hill slopes and also through deposition by rivers.

(3) Coastal and river alluvium The coastal alluvium is seen in the western coastal tract of the district. The coastal plain is characterized by secondary soils, which are sandy and– sterile with poor water holding capacity. The width of the zone is more in the central part i.e., in the Kannur area and it is almost narrow in both north and southern areas of the district. The marshy soil in the coastal plain supports mangrove vegetation and is found at the estuaries and backwater extending inland along their courses. The soil is composed of recent deposits predominantly marine with some fluvial sediment along the coastline. These soils are immature with high sand content. River alluvium is found along river valleys cutting across the extensive lateritic soils. The soil is very deep with surface texture ranging from sandy loam to clay. It is fertile, having water holding 19

Prefeasibility Report for Granite Quarry Mining <5 Ha

capacity and plant nutrients which are regularly replenished during floods.

(4) Forest Loamy soil These soils are found in the eastern hilly areas of

the district and are characterised– by a surface layer rich in organic matter. They are generally acidic and are dark reddish brown to black in colour with loam to silty loam texture.

3.2.7 Seismicity of the area Many parts of the Indian subcontinent have historically high Seismicity. Seven catastrophic earthquakes of magnitude greater than 8 (Richter scale) have occurred in the western, northern and eastern parts of India and adjacent countries in the past 100 years. By contrast, peninsular India is relatively less seismic, having suffered only infrequent earthquakes of moderate strength. The main seismogenic belts are associated with the collision plate boundary between the Indian and Eurasian plates. The project site as well as study area lies in Zone- III of Seismic Zoning Map, and thus can be said to be located in an area of moderate seismic hazard by national standards. Hence the risk of earthquake at the site persists though there has to be no incident in the near past.

3.3 GEOLOGY

3.3.1 Physiography

Kannur district can be divided physiographically into three distinct geomorphologic units viz the coastal plains and lowlands in the western part, the central undulatory terrain comprising the midland region and eastern highland region. (Table 3-2).

Table 3-1 Physiographic units in Kannur District

Sl. Physiographic Unit Arial extent (Km2) Elevation No. (mamsl) 1 Coastal plain 82 <5 2 Mid land 700 5-80 3 Hill ranges 1950 80-1500

20

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.3.2 Regional Geology The coastal plains occurs as a narrow belt of alluvial deposits running parallel to the coast with a maximum width of about 15 km. Midland region forms a plateau land at certain places covered by a thick cover of laterites. The hilly tract in the eastern part consists of highly rugged terrains. The Ezhimala peak (259.69m) with the characteristic N-S alignment is a distinct physiographic unit in the coastal plains. Minor cliffs of laterite generally rising to an elevation of 50 to 60 m above mean sea level are found at Mahe, Thalasserry and Bekal coast. The midland region presents a plateau land covered by a thick cover of laterite. This is immediately to the east of the coastal strip, rising from 40 to 100 m above msl. The valleys in the plateau are gorge like and V shaped cut by youthful streams. The hilly tract along the eastern part of the district constitutes the highland region and is highly rugged.

3.3.3 Geology of the Lease Area Geologically the tract has four types of rock formations viz. Laterite brown hydromorphic, coastal and river alluvium and forest loamy soil

(1) Lateritic soil The predominant soil in the district is lateritic soil, which is the weathered product derived under humid tropical conditions. It occurs mainly in the– midland and hilly areas characterized by rugged topography. They range from sandy loam to red loam.

(2) Brown hydromorphic soil These are confined to the valleys between undulating topography in the midlands and in the low lying areas of the coastal strip in the district. These– soils are brown in colour and the surface texture varies from sandy loam to clay. They have been formed as a result of transportation and deposition of materials from adjoining hill slopes and also through deposition by rivers.

(3) Coastal and river alluvium The coastal alluvium is seen in the western coastal tract of the district. The coastal plain is characterized by secondary soils, which are sandy and– sterile with poor water holding capacity. The width of the zone is more in the central part i.e., in the Kannur area and it is almost narrow in both north and southern areas of the district. The marshy soil in the coastal plain supports mangrove vegetation and is found at the estuaries and backwater extending inland along their courses. The soil is composed of recent deposits predominantly marine 21

Prefeasibility Report for Granite Quarry Mining <5 Ha

with some fluvial sediments along the coastline. These soils are immature with high sand content. River alluvium is found along river valleys cutting across the extensive lateritic soils. The soil is very deep with surface texture ranging from sandy loam to clay. It is fertile, having water holding capacity and plant nutrients which are regularly replenished during floods.

(4) Forest Loamy soil These soils are found in the eastern hilly areas of the

district and are –characterised by a surface layer rich in organic matter. They are generally acidic and are dark reddish brown to black in colour with loam to silty loam texture.

22

Prefeasibility Report for Granite Quarry Mining <5 Ha

Figure 3-1 Photographs showing geology of the site

3.4 RIVERS Kannur district is endowed with a fine river system. Except for a few minor ones, most of the rivers are perennial and provide good scope for irrigation and for controlling floods through minor irrigation projects.

The river is the longest river in the district, originates from the Ghats located about 15km north of (in ) passes through the villages of , Edakkunnam, Perumanna, and and joins the Lakhshadeep sea about 10km north of Kannur. It has

23

Prefeasibility Report for Granite Quarry Mining <5 Ha

a total catchment area of 1191 sqkm of which 528 sq km in state. The main tributaries of are Valiapuzha and puzha.

The Kuppam river originates from Padinalkkad Ghat Reserve Forest in the of Karnataka State and flows westwards through Thadikkadavu, Kuveri And Taliparamba and joins the Valapattanam River. It has a catchment area of 536 sq km. The River originates from Kannoth forests in Thalasseri taluk and passes through , Kadamkunnu and Vemmanal before it joins the Lakhshadeep Sea. It has a catchment area of 113 sq km.

The Mahe river also known as Mayyazhippuzha originates from Wayanad Ghats and passes through Mananthavadi taluk of Wayanad district, Vadakara taluk of Kozhikkodedistrict and Thalaseri taluk before it joins the Lakhadeep Sea at Mahe about 6 km south of Thalasseri. It has a cathment area of about 233 sq km.Most of the rivers are navigable. The Valapattanam River has the longest navigable length followed by the river Anjarakkandy.

Rivers Length Water Resources Kariyangode 64 937mm3 Perumba,Ramapura 51,19 603mm3 Kuppamm 82 786 Valapattanam 110 1828 Anjarakkandy 49 503 Thalasseri 28 122 Mahe River 54 445 Table 3.4. Major rivers in Kannur district 3.5 GROUNDWATER RESOURCES Based on the stage of groundwater development, the blocks of the country are categorized as safe, semi-critical, critical and over-exploited (Figure 4). The stage of development in Kannur district is 63.58%. Maximum development is seen in Thalasserry block (150.79%) and minimum in Irikkur block (30.19%). All the blocks are under safe category in the district except two are categorized into critical category.

24

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 3-2 Stage of Groundwater Development

Assessment Net Annual Ground Existing Gross Ground Water Stage of ground Categoriz Unit/Block Water Availability Draft for all uses water development ation

Safe Payyannur 130.62 48.54 37.16

Taliparamba 90.03 41.31 45.88 Safe 40.04 26.93 67.26 Safe Kannur 19.96 12.69 63.58 Safe Irikkur 105.92 31.98 30.19 Safe Iritty 59.57 23.67 39.73 Safe Semi Thalasserry 18.41 27.76 150.79 Critical Semi Kuthuparam 30.73 29.71 96.68 bu Critical Peravur 45.34 18.60 41.01 Safe

Source: Ground water Information booklet September 2007

3.5.1 Water Conservation and Artificial Recharge Watershed management practices should be given utmost importance which in turn will help to conserve the groundwater and supplement the recharge. Roof- top rain water harvesting can be practiced in areas like Chamberi, Poyilur and Thalasserry where all the dug wells go dry during summer. Bore wells can be recharged using rain water especially in semi critical blocks like Thalasserry and Kuthuparambu. In coastal areas of the district like Azhikode, Azhikkal, Edakkad, Dharmadam, Muzhapilangad, , Mahe and , rainwater harvesting schemes can be practiced to avoid more stress on the shallow aquifer. Contour bunding, trenching, nalla bunding, check dams, percolation tanks and subsurface practices like recharge shaft, dug well recharge and water conservation structures like sub-surface dyke are suitable for midland areas of Kannur district.

25

Prefeasibility Report for Granite Quarry Mining <5 Ha

26

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.6 HYDROLOGY There are no perennial water courses / bodies within the proposed area. Apart from this the water source in the area is mainly storm and ground water. Entire storm water flows through the minor watercourses and joins the adjoining seasonal nallah. The drainage pattern in this area is dendritic in nature. The ground water table in this area is about 5 m below the general ground level during summer season and around 10 m during monsoon. Since the quarry falls on the hillock, none of the quarry workings will touch the water table

Figure 3-2 Kannur District Map showing Hydrogeology

27

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.7 Land use The main contribution for the economy of the district comes from agriculture. Majority of the population of the district directly or indirectly depend on agriculture for their livelihood. About 75% people are dependent on this sector. Rubber is the most important crop, with its plantations covering over 215921 hectares (2159.21 sq km). The hilly terrain coupled with high humidity makes the region suitable for rubber plantations. Paddy is the most important crop cultivated in the wet lands. Tapioca and pulses are the important dry land crops. Other major crops are coconut, banana, pepper and ginger. In certain areas cashew, pineapple, sugarcane, cocoa and other tree spices are cultivated. The land available for cultivation is less since sizeable area of the district is reserve forest. The land use Pattern of the District is given in Figure Below

Figure 3-3 Land Use Pattern in Kannur

28

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 3.3 Showing land use pattern in Kannur District in Kerala

Area LULC Class (in Ha) Forest area 65240

Barren land 3076

Grazing land 011.7

Tree crops 1121

Cultivated waste 4524

Fallow land 2680

Current fallow 3538

Net area sown 215921

3.8 BIODIVERSITY A natural ecosystem is a structural and functional unit of nature. It has a number of components which exist in harmony and survive by inter dependency. Ecosystem has self sustaining ability and control the number of organisms at any level by cybernetic rules to sustain ecological balance. A biological survey of the study area was conducted particularly with reference to listing of species and assessment of existing baseline ecological (terrestrial and aquatic) conditions in the study area. Considering the rich biodiversity of organisms, their role in productivity and their importance in human livelihood, it is vital to protect and safeguard these dynamic systems. The impacts on ecosystems are wide spread. Removals of forest cover, sand mining, industrialization, soil erosion are major reasons for the impacts. These would directly affect the biological diversity of the environment and the species. Development activities lead to habitat fragmentation, affecting the species and their survival, it when the energy transfer between the species and the biological cycles get destroyed; it periodically leads to the loss destruction. Environmental changes have dramatically increased the intensity of ecosystem destruction. Environmental changes have large impact on the habitats and the recourses. Land use patterns in Kerala changed significantly in past two decades due to urbanization. Modern agricultural practices, the major reasons for the land degradation and the land use changes have made adverse changes on the biological diversity. Anthropogenic conversion of natural habitats presents one of the greatest threats to biodiversity. 29

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.8.1 Objectives of the Study The objectives of the present study were selected with a view to understand the biogeochemical status of the ecosystems on the following lines:

 Generate baseline data from field observations;  Compare the data so generated with authentic (obtained from Govt., semi-govt. and private agencies) past records to understand changes;  Characterize the environmental components like land, water, flora and fauna;  Understand the present biodiversity;  Identify susceptible sensitive and critical areas (Environmental hotspots);  Understand impact of industrial activities on the flora and fauna;  Predict changes, as a result of impact, in the composition and functioning of components of ecosystem.

3.8.2 Methodology Adopted for the survey The area for the ecological studies covers 10 km radius and 0.5 KM on either side of the over ground cross country pipeline from the proposed project site. To accomplish above objectives, a general ecological survey covering the study area was carried out.

The survey includes:

 Reconnaissance survey for the selection of sampling site;  Compilation of secondary data  Generation of primary data to understand baseline ecological status, important floristic and faunal elements, sensitive habitats and rare species  Generation of data from local villagers for importance and status of plants and animals and  Observation of symptoms and assessment of impacts. Kannur has tropical biodiversity with forest, plantations, rivers and fertile land. Fifty percent of the district is covered with forest, providing rich flora and fauna.

30

Prefeasibility Report for Granite Quarry Mining <5 Ha

The district has a variety of plants including medicinal, spices, tuber crops and those yielding fruits and fiber. Aromatic plants and spices such as pepper, ginger, cardamom and turmeric are cultivated on a large scale. Trees such as timber, teak, rosewood, jack tree, manjakadambu, anjili, pala can be found in abundance.

31

Prefeasibility Report for Granite Quarry Mining <5 Ha

3.8.3 Flora The vegetations of evergreen & Semi evergreen forest near the project location are given in the following tables.

Table 3-4 Vegetations of Ever Green Forest

S.No Trees Saplings Seedling Shrubs Herbs Climber 1 Syzigium sp. Xanthophyllum Knema attenuata Strobilanthes sp. Dracaena Calamus arnottianum terniflora thwaitesii 2 Knema attenuata Cinnamomum sp. Drypetes elata Pandanus thwaitesii Pellionia Pothos heyneana scandens 3 Drypetes elata Diospyros paniculata Myristica dactyloides Chassalia Costus speciosus Piper sp ophioxyloides 4 Antiaris toxicaria Myristica dactyloides Xanthophyllum Ventilago Dracaena Smilax arnottianum bombaiensis terniflora zeylanica 5 Aglaia barberi Donella roxburghii Aglaia barberi Leea sp. Oplismenus Raphidophora compositus pertusa 6 Terminalia bellirica Hopea parviflora Cinnamomum sp. Chassalia curviflora Stachyphrynium Sarcostigma spicatum kleinii 7 Myristica Dipterocarpus Garcinia spicata Boehmeria Strychnos dactyloides indicus glomerulifera colubrina 8 Holigarna grahamii Mangifera indica Donella roxburghii Ixora sp. Erythropalum scandens 9 Hopea parviflora Holigarna grahamii Baccaurea Thottea siliquosa Jasminum courtallensis azoricum 10 Artocarpus hirsutus Rinorea benghalensis Holigarna grahamii Mallotus beddomei Coscinium fenestratum 11 Elaeocarpus Diospyros Diospyros paniculata Jasminum sp. tuberculatus bourdillonii 12 Ficus sp. Flaucortia montana Syzygium sp. Myxopyrum smilacifolium 13 Xanthophyllum Antiaris toxicaria Dipterocarpus Ancistrocladus 32

Prefeasibility Report for Granite Quarry Mining <5 Ha

S.No Trees Saplings Seedling Shrubs Herbs Climber arnottianum indicus heyneanus 14 Vateria indica Vateria indica Actinodaphne Cissus discolor bourdillonii 15 Cinnamomum sp. Strombosia ceylanica Olea dioica Diploclisia glaucescens 16 Kingiodendron Hopea parviflora Toddalia pinnatum asiatica 17 Olea dioica Pterygota alata 18 Dipterocarpus Chionanthus mala- indicus elengi 19 Baccaurea Polyalthia coffeoides courtallensis 20 Nothopegia Kingiodendron racemosa pinnatum 21 Diospyros Nothopegia paniculata racemosa 22 Garcinia spicata Vateria indica 23 Persea macrantha Artocarpus hirsutus 24 Canarium strictum Diospyros bourdillonii 25 Chionanthus mala- Dimocarpus longan elengi 26 Vitex altissima Hopea ponga 27 Ixora brachiata Strombosia ceylanica 28 Polyalthia Antidesma menasu coffeoides 29 Dimocarpus longan Atalantia racemosa 30 Spondias indica Hydnocarpus pentandra 31 Donella roxburghii Reinwardtiodendron

33

Prefeasibility Report for Granite Quarry Mining <5 Ha

S.No Trees Saplings Seedling Shrubs Herbs Climber anamalaiense 32 Calophyllum Turpinia malabarica polyanthum 33 Strombosia Vitex altissima ceylanica 34 Otonephelium Artocarpus stipulaceum hetrophyllus 35 Diospyros Calophyllum bourdillonii polyanthum 36 Croton malabarica Diospyros buxifolia 37 Turpinia malabarica Persea macrantha 38 Artocarpus Elaeocarpus hetrophyllus tuberculatus 39 Hopea ponga Ixora brachiata 40 Sageraea laurifolia Mallotus philippensis 41 Antidesma menasu Otonephelium stipulaceum 42 Reinwardtiodendro Sageraea laurifolia n anamalaiense 43 Flaucortia montana Croton malabarica 44 Casearia ovata 45 Pterygota alata 46 Mallotus philippensis

34

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 3-5 Vegetations of Semi Ever Green forest

S.No Tree Saplings Seedlings Shrubs Herbs Climbers 1 Chionanthus mala- Chionanthus mala- Oplismenus Pothos Holigarna grahamii elengi elengi Chassalia curviflora compositus scandens 2 Smilax Aporusa lindleyana Madhuca neriifolia Mallotus philippensis Strobilanthes sp. Dracaena terniflora zeylanica 3 Hydnocarpus Chassalia Xylia xylocarpa pentandra Xylia xylocarpa ophioxyloides Costus speciosus Piper longum 4 Dillenia pentagyna Mallotus philippensis Aporusa lindleyana Pavetta sp. Cyathula prostrata Jasminum sp. 5 Lagerstroemia Stachyphrynium reginae Vateria indica Olea dioica Helicteres isora spicatum Acacia caesia 6 Kingiodendron Glycosmis Anamirta pinnatum Ardisia solanacea Cinnamomum sp. pentaphylla cocculus 7 Chionanthus mala- Myxopyrum elengi Mangifera indica Vateria indica Ixora sp. smilacifolium 8 Lagerstroemia Strychnos Mallotus philippensis Holigarna grahamii reginae Leea sp. colubrina 9 Hydnocarpus Ancistrocladus pentandra Polyalthia coffeoides Hopea parviflora Pandanus thwaitesii heyneanus 10 Terminalia Actinodaphne Calamus paniculata Olea dioica bourdillonii thwaitesi 11 Lagerstroemia Baccaurea Naravelia microcarpa Alstonia scholaris courtallensis zeylanica 12 Hydnocarpus Asparagus Persea macrantha Atalantia racemosa pentandra racemosus 13 Coscinium Dimocarpus longan Cinnamomum sp. Naringi crenulata fenestratum 14 Naringi crenulata Xylia xylocarpa Dimocarpus longan Entada rheedei 15 Tetrameles nudiflora Ficus hispida Gnetum ula

35

Prefeasibility Report for Granite Quarry Mining <5 Ha

S.No Tree Saplings Seedlings Shrubs Herbs Climbers 16 Sarcostigma Bombax insigne Macaranga peltata kleinii 17 Spatholobus Grewia tiliiifolia Polyalthia coffeoides parviflorus 18 Artocarpus hetrophyllus Pterygota alata 19 Atalantia racemosa Dillenia pentagyna 20 Vateria indica Sterculia guttata 21 Xanthophyllum Cinnamomum sp. arnottianum 22 Polyalthia coffeoides Holigarna grahamii 23 Lagerstroemia Strychnos nuxvomica microcarpa 24 Hopea parviflora Madhuca neriifolia 25 Ficus hispida Garcinia spicata 26 Kingiodendron Olea dioica pinnatum 27 Gmelina arborea Ardisia solanacea 28 ereospermum colais Artocarpus hirsutus 29 Archidendron monadalphum Atalantia racemosa 30 Flaucortia montana Flaucortia montana 31 Baccaurea courtallensis Strychnos nuxvomica 32 Actinodaphne bourdillonii Syzigium sp. 33 Madhuca neriifolia Terminalia paniculata 34 Persea macrantha 35 Sterculia villosa

36

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 3-6 Regeneration status of endemic species

Sl.No Species Ecological Status Regeneration

1 Derris benthamii Seen in evergreen forests Deficient

2 Gluta travancorica do Fair

3 Hopea erosa do Fair

4 Litsea laevigata do Moderate

5 Nothopegia Shades of banks of Moderate travancorica streams

6 Syzygium mundagam Seen in evergreen forests, Fair along banks of streams

7 Turraea villosa Seen in dense evergreen Moderate forests

Table 3-7 Regeneration status of endangered or threatened species

SL. No Species Ecological Status Regeneration

1 Adenostemma latifolium Evergreen forests Deficient

2 Aspidopterys canarensis do Fair

3 Chilocarpus malabaricus do Deficient

4 Cyanotis cerifolia Rocky slopes near Fair streams of evergreen forests

5 Entada rheedi Evergreen forests Fair

6 Epipogum roseum do Moderate

7 Goniothalamus Dense evergreen forests Fair wynadensis

8 Impatiens acaulis do Moderate

9 Impatiens dasysperma Moist zones of plains. Fair

10 Indigofera constricta Evergreen forests Deficient

11 Litsea laevigata do Deficient

12 Memecylon talbotianum do Fair

37

Prefeasibility Report for Granite Quarry Mining <5 Ha

13 Phaeanthus malabaricus do Deficient

14 Saprosma fragrans do Fair

15 Stachyphrynium spicitum do Fair

16 Tetrastigma canarense do Fair

3.9 AMBIENT AIR QUALITY STATUS Air pollution can cause significant effects on human beings, animals, vegetation and materials. Air environment monitoring covers the parameter for which National Ambient Air Quality standards have been defined by the Ministry of Environment and Forests. Accordingly, parameters monitored were Particulate Matter (PM 2.5), Oxides of

Nitrogen (NOx), Carbon Monoxide (CO), and Sulphur Dioxide (SO2).

(I) Ambient Air Quality:

Two air sampling locations were selected for air quality study. The details of the locations are given below:

Table 3 - 8 Ambient Air Quality sampling Locations

LOCATION CODE LOCATION

ESA1 Rajagiri Village

ESA2 Josegiri Village

From the report it is seen that in the ambient air, the PM 10 values were in the range of 51.0 to 68 µg/m3 PM2.5 values were in the range of 20.0 to 29 µg/m3 SO2 levels were ⧠ in the range from 8.0 to 11.0 µg/m3. NO2 levels were ranging from 6.4 to 8.2 µg /m3.

While comparing with the NAAQ Norms, all monitored PK°, PM2 5, S02, NO2 values were found to be well within the respective limit values of 100 µg/m3, 60 µg /m3, 80 µg /m3 & 80 µg /m3. All AAQ stations have reported values to be well within prescribed limits.

3.10 Water environment (II)Water Quality:

3 ground water samples were collected at the following locations:

38

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 3 - 9 Ambient Water Quality sampling Locations

Station name Station Code

ESW1 Well water, Rajagiri

ESW2 Well water, Josegiri

ESW3 Kozichal, Surface Water

Table 3-10 Water sampling results

The summary of the Water sampling results are given below.

Parameters Unit ESW1 ESW2 ESW3 IS* Is Permissible limits Total mg/I 44.0 43 40 500 2000 Dissolved Solids Total mg/I 16.9 6.0 15.0 200 600 Hardness as CaCO3 Chloride as mg/I 13.2 15.2 11.7 250 1000 CI- Free mg/I BDL BDL BDL 0.2 1.0 Residual Chlorine as (D.L. (D.L. (D.L. CI- 0.2) 0.2) 0.2) Iron as Fe mg/I 0.02 – 0.02 – 0.12 – 0.3 No relaxation Fluoride as mg/I BDL 0.16 0.13 1.0 1.5 F Total MPN/100m1 <2 <2 <2 Shall not be detected in Coliformi 100ml sample E.Coli2 MPN/100m1 <2 <2 <2

(iii) Noise:

Noise measurements were carried out using Lutron SL 4001 sound level meter. From the report it is observed the existing noise level in the core zone location (ESN1) for day & night equivalent is 51.72 dB(A) which is below the work zone exposure limit of 90 dB(A),In the buffer zone, the day equivalent values ranged between 49.5 to 54.5 dB(A).

(IV) Soil

39

Prefeasibility Report for Granite Quarry Mining <5 Ha

The soil is reddish brown and Sandy Loam. The iron content is 33,780 mg/kg to 20,690 mg/kg.

(e) Climatic Conditions:

The district has a humid climate with an oppressive hot season from March to the month of May. This is followed by the South-West monsoon which continues till the end of September. The temperature is more during the months of April & May, the mean daily minimum temperature is about 35°C and is less during December and January, and the minimum temperature is about 20°C. The total annual average rainfall of the district is and 3500 mm.

3.11 Noise level data The noise level measurements were carried out at different locations. The observed values of noise levels in the Pulingome village at different locations are found to be in the range of 50 to 70 dB (A).

Table 3-11 Ambient Noise Levels in Pulingome Villages – Day Time Sl. no. Sampling Location Noise Levels [dB(A)]

1 Pulingome Village site 44.4

3.12 Soil analysis

Keeping in view the proposed activities at the site, the baseline data related to nature & quality of soil in impact zone are collected through field survey and available data sources including project proponents. To assess existing soil quality, five locations were identified within 5 km radial distances around the project site. Representative soil samples at each site were collected from (0-20 cm) depth. Standard methods have been followed for analyzing the samples for physico-chemical, characteristics and parameters related to agriculture productivity.

Table 3-12 Soil Quality Results

S.No Parameters Units Sample-1 Sample-2 1 pH (at 25°C) @ - 6.48 4.60 10% Solution

40

Prefeasibility Report for Granite Quarry Mining <5 Ha

2 Electrical 38.0 224.0

Conductivity μS/cm 3 Bulk density gm/cc 1.49 1.14

4 Sodium mg/kg 18.0 85.0 5 Available mg/kg 5.0 34.0

Potassium 8 Organic Matter % 0.22 0.78 9 Available Nitrogen mg/kg 526.40 761.60

as N 12 Available mg/kg 21.85 21.18 Phosphorus

13 Zinc mg/kg 52.38 48.18 14 Manganese mg/kg 210.66 302.87 15 Cadmium mg/kg 0.74 0.64

16 Copper as Cu mg/kg 43.53 27.35

17 Boron mg/kg BDL (DL0.1) BDL (DL0.1)

18 Iron mg/kg 21230.55 37495.63 20 Moisture % 7.32 16.19

21 Soil Texture % 74.23 77.52 i) Sand 22 Soil Texture % 1.08 1.67

ii) Silt 23 Soil Texture % 24.69 20.81

iii) Clay

41

Prefeasibility Report for Granite Quarry Mining <5 Ha

4 ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT The awareness of environment has led to the development of Environmental Management Plan including minor development projects, wherein anticipated impact are assessed and the management plan to mitigate these impacts has been stipulated in advance. The Environmental Management Plan (EMP) is a site specific plan developed to ensure that the project is implemented in an environmental sustainable manner. EMP also ensures that the project implementation is carried out taking appropriate mitigative actions to reduce adverse environmental impacts. Environmental management plan includes protection/mitigation/enhancement measures as well as suggesting post project monitoring programme. It has been found that the study area has not been affected adversely as there are no major polluting industries in the study area and likely to get economical fillip. The management action plan aims at controlling pollution at the source level to the possible extent with the available and affordable technology followed by treatment measures before they are discharged.

Fully conscious towards environmental responsibility towards the coal beneficiation process, the proponent mainly focuses, apart from other relevant concerns, on the following important aspects,

a) Dust suppression measures by water sprinkling and

b) Proper maintenance of vehicles and equipment.

The different environmental components that are identified in the assessment chapter are dealt hereunder with necessary environmental management plan.

42

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.1 AIR QUALITY MANAGEMENT The proposed mining activity would result in the increase of SPM concentrations due to fugitive dust. Frequent water sprinkling in the vicinity would be undertaken and will be continued as there is possibility for dust generation due to truck mobility. It will be ensured that vehicles are properly maintained to comply with exhaust emission requirements. Dust emissions and particulate emissions will be controlled by water spraying through sprinklers at all the sources of dust formation and corresponding mitigative measures are elaborated as follows:

 Proper blasting pattern will be followed for effective rock fragmentation and generation of minimal fine dust to open atmosphere.  Regular water sprinkling at dust emanating sources viz., drilling, blasting and transportation through haulage roads, etc will be carried out.  Periodic maintenance of transport vehicles and equipment will be carried out to check emission levels.  Greenbelt will be developed that will act as a pollution sink.  Overloading of trucks will be avoided and carrying the rocks in covered trucks will be taken up to minimize pollution level  Regular ambient air quality monitoring shall be carried out to ensure the air pollutants are kept under permissible limits always.

4.1.1 Controlling Dust Levels Dust would be generated during mining, and during handling and transportation of the material. The suggested control measures are:

4.1.1.1 Mines  Dust suppression systems (water spraying) to be adopted at Faces/sites while loading  Use of sharp teeth for shovels  Dust extraction systems to be used in drill machines  Use of sharp drill bits for drilling holes and drills with water flushing systems (wet drilling), to reduce dust generation.

43

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.1.1.2 Haulage

 Regular water spraying on haulage roads during transportation of excavated material by water sprinklers.  Transfer points shall be provided with appropriate hoods/chutes to prevent dust emissions.

4.1.2 Controlling CO Levels The concentration of CO in the ambient air was below detectable limits at all the air quality monitoring locations. Expected increase in the CO concentration is very low as CO emissions from mining operations are less compared to other pollutants. Heavy and light vehicles are the major sources of CO in the mine. All vehicles and their exhausts would be well maintained and regularly tested for pollutants concentration.

4.1.3 Controlling NOx Levels

NOx emissions in the mine mainly occur during blasting operations. The main

reasons for NOx emissions are

 Poor quality of explosives having large oxygen imbalance. This may be due to :  Manufacturing defect;  Use of expired explosives in which ingredients have disintegrated.  Incomplete detonation, which may be due to low Primer to column ratio.

4.1.4 Occupational Health & Safety Measure to Control Dust Inhalation All the above precautions would be adopted to prevent dust generation at site and to be dispersed in the outside environment. However, for the safety of workers at site, engaged at the strategic locations/dust generation points like drills, loading & unloading points, crushing etc, dust masks would be provided. Dust masks would prevent inhalation of RPM thereby reducing the risk of lung diseases and other respiratory disorders.

44

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.2 NOISE POLLUTION CONTROL The ambient noise level monitoring carried out in and around the proposed mine shows that the ambient noise levels are well within the stipulated limits of CPCB. Within an operational mine, major noise sources are blasting, operation of mine machineries and equipment, crushing units and belt conveyor. Noise generation may be for an instant, intermittent or continuous periods, with low to high decibels. To keep noise generation in control, latest sophisticated technology and equipment have been considered. Drills, loaders, dumpers etc with larger capacities possibly will be acquired to reduce the number of operational units at a time, thereby reducing the noise generating sources. The equipment systems will include cabins to ensure that the operators and other work persons, in and around the operating equipment, have comfortable work stations. To keep the ambient noise levels within the permissible limits of 75 dB (A), the following measures should be adopted  Personal who are exposed to critical locations in the quarry will be provided with PPEs  Innovative approaches of using improvised plant and machinery designs, with in-built mechanism to reduce sound emissions like improved silencers, mufflers and closed noise generating parts.  Effective blast design so that there will be minimal noise and ground vibrations during blasting,  Procurement of drill, loaders and dumpers and other equipment with

 noiseConfining proof the system equipment in operator’s with heavy cabin. noise emissions in sound proof cabins, so that noise is not transmitted to other areas.  Regular and proper maintenance of noise generating machinery including the transport vehicles and belt conveyors, to maintain the noise levels.  Provision would be made for noise absorbing pads at foundations of vibrating equipment to reduce noise emissions.

45

Prefeasibility Report for Granite Quarry Mining <5 Ha

 Provision of protective devices like ear muffs/ear plugs to workers who cannot be isolated from the source of high intensity noise, e.g. blasting

4.3 WATER ENVIRONMENT As this is an open cast mining method it will not generate any wastewater as there is no mineral processing involved. The mining of rock does not involve any treatment or beneficiation by using water. Therefore, the question of disposal of water will not arise. Moreover, mining activity much above the ground water

However,level doesn’t in orderlead to to any mitigate ground any water likely contamination. impacts the following management for control of water pollution is proposed.

 In anticipation of seasonal streams and runoff in the core zone, channels and bunds would be constructed and maintained to avoid any erosion and contamination.  Garland drains will be constructed around the boundary of the mine lease area outside the boundary wall to divert rainwater away from the site.  The mine pit water collected due to rains will be utilized for water spraying on the haul roads and for watering plantation.  This water will be harvested for utilization in plantation watering, spraying on the haulage roads and waste dumps.

4.4 LAND ENVIRONMENT The mined out pit area will be backfilled and developed for stabilization and plantation of native species will be carried out. The top soil will be utilized for plantation of trees in the area. This would not only make the area aesthetically beautiful but also check on the soil and land erosion.

46

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.4.1 Rocks for landscaping After the quarrying activities are over, these sites will be splattered with the leftovers of rocks and boulders. These boulders and rocks can support the growth of mosses and lichens, which will act as ecological pioneers and initiate the process of succession and colonization. The boulders of moderate size will be used to line the boundary of a path.

4.4.2 Laying of the top soil The depressions/craters filled up with rock aggregates will be covered with top soil. Fungal spores naturally present in top soil will aid plant growth and natural plant succession. The top soil will be further enriched by organic manure and Vesicular-arbuscular mycorrhizal (VAM) fungi. This will help in the process of soil Reclamation and early establishment of seedlings.

4.5 WASTE DISPOSAL MANAGEMENT Since the proposed project is mining of rock, there will not be much of waste generated due to mining. After the quarrying activities are over, these sites will be splattered with the leftovers of rocks and boulders. The boulders of moderate size will be used to line the boundary of a path. The disintegrated rock will be used as sand material for road making. The overburden waste is in the form of soil. Initially it will be temporarily stacked at safe place. It will be re handled later to be backfilled in the exhausted portion of the pit.

4.6 GREEN BELT DEVELOPMENT The area surrounding the site is dense with plantation. Planting a suitable combination of trees that can grow fast and also have good leaf density shall be adopted to develop the green belt. It will act like a buffer to trap the airborne dust and also reduce the noise levels. From the aesthetic point of view also, this will have a positive impact.

47

Prefeasibility Report for Granite Quarry Mining <5 Ha

It is proposed to develop a green belt along the periphery of the mining lease area. The green belt shall be developed in consultation with the local forest authorities for selection of site, specific species, seedling management, and plantation techniques and to up keep by deweeding, manuring and regular watering. The Environment Management Plan is enclosed in Plate-8.

4.6.1 Criteria for selection of species Species to be selected should fulfil the following specific requirements of the area

 Availability of seed material  Tolerance to specific conditions or alternatively wide adapts ability to eco physiological conditions.  Rapid growth  Capacity to endure water stress and climatic extremes after initial establishment  Differences in height, growth habits  Pleasing appearance  Providing shade  Ability of fixing atmospheric Nitrogen  Improving waste lands.

4.6.2 Design of Green Development The greenbelt shall be developed around the plant to act as a sink for pollutants, attenuation of noise levels and improvement in aesthetic quality of the plant. The following criteria shall be adopted in the design of greenbelt:

 Generally fast growing trees will be planted.  Trees growing up to 10 m or more in height with thick perennial foliage will be planted around the plant.  Trees will be planted in patches along the periphery to work as an indicator of pollution.

48

Prefeasibility Report for Granite Quarry Mining <5 Ha

 Trees shall be planted staggered in each row (minimum three rows encircling the perimeter of the plant).

4.6.3 Programme for Afforestation Afforestation will be carried out to increase the green cover and create harmony with nature. The area will be afforested with variety of local sapling. This will help to have polyculture. The details of afforestation program are given below.

Table 0-1 Afforestation Programme

Year Area and Extent in Species Number Hectare I General Surface Pongamiapinnata L., Haevia 178 0.1476 brasiliensis L. II General Surface Pongamia pinnata L. 178 0.1476 III General Surface Pongamia pinnata L., Haevia 178 0.1476 brasiliensis L., Odinawodier Roxb. IV General Surface Cassia chinensisJacq., Tectona 178 0.1476 grandis L V General Surface Cassia chinensisJacq., 178 0.1476 Tectonagrandis L

4.7 MEASURES TO CONTROL EROSION The Granite rock is hard, compact massive rock and there is no erosion. However trenches and pits will be made at various places to guide the rainwater to the settling tank. This will reduce the erosion on the soil mass.

4.8 MEASURES FOR MINING EFFECT ON WATER Kuppam river is located in the southern side of the lease area and is about 6.06Km away from the Quarry. No wet processing is adopted. Proposed workings area is of shallow depth and mostly carried out in dry season. Drains will be made at key places to guide rainwater so that erosion is avoided.

49

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.9 CONTROL MEASURES FOR DISASTER  Entry of unauthorized persons shall be prohibited;  Fire fighting and first aid provisions in the mining Area;  Provision of all the safety appliances such as safety boots, helmets, goggles etc. would be made available to the employees and regular check to ensure the use;  Training and refresher courses for all the employees working in the hazardous premises;  Handling of explosives, charging and blasting shall be carried out by competent persons only;  Provision of magazine at safe place with fencing and necessary security arrangement;  Suppression of dust on the haulage roads;  Awareness on safety and disaster to the staff.

4.10 SOCIO ECONOMIC ENVIRONMENT The company management shall give preference to local people  It will provide ample opportunity to the locals to uplift their living standards by organizing events that propagate mutual benefits to all, such as health camps, awareness campaigns, donations to poorer sections of society and downtrodden.  Educational needs of the region will be improved by encouraging the workers to allow their children to attend schools.  Sufficient funds shall be allocated for these and other emergency needs.  Adequate supply of potable water to the workers will be made during the working hrs.  The working personnel will be provided with face masks, ear plugs, safety helmets and goggles in order to reduce health hazards. Other safety equipments shall be used according to the nature of job involved.

50

Prefeasibility Report for Granite Quarry Mining <5 Ha

 Adequate space will be provided for construction of temporary sheds for construction workers.  The proponent will supply potable water for the workers.

4.11 Mine closure Mine closure plan is the most important environmental requirement in mineral mining projects. The mine closure plan should cover technical, environmental, social, legal and financial aspects dealing with progressive and post closure activities. The closure operation is a continuous series of activities starting from the decommissioning of the project. Therefore, progressive mine closure plan should be specifically dealt with in the mining plan and is to be reviewed every five years in the scheme of mining. As progressive mine closure is a continuous series of activities, it is obvious that the proposals of scientific mining have included most of the activities to be included in the closure plan. While formulating the closure objectives for the site, it is important to consider the existing or the pre-mining land use of the site; and how the operation will affect this activity. Some operations such as mining in agricultural areas have clearly defined this objective of returning the land to viable agricultural purposes or for bringing the land for economically viable productive purposes. The primary aim is to ensure that the following broad objectives along with the abandonment of the mine can be successfully achieved:  To create a productive and sustainable after-use for the site, acceptable to mine owners, regulatory agencies, and the public.  To protect public health and safety of the surrounding habitation.  To minimize environmental damage.  To conserve valuable attributes and aesthetics.  To overcome adverse socio-economic impacts.

4.11.1 Mine Closure Criteria The criteria involved in mine closure are discussed below:

51

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.9.1.1 Physical Stability All anthropogenic structures, which include mine workings, waste dumps, buildings, etc., remaining after mine decommissioning should be physically stable. They should present no hazard to public health and safety as a result of failure or physical deterioration and they should continue to perform the functions for which they were designed. The design periods and factors of safety proposed should take full account of extreme events such as floods, hurricane, winds or earthquakes, etc. and other natural perpetual forces like erosion, etc.

4.9.1.2 Chemical Stability The solid wastes on the mine site should be chemically stable. This means that the consequences of chemical changes or conditions leading to leaching of metals, salts or organic compounds should not endanger public health and safety nor result in the deterioration of environmental attributes. If the pollutant discharge likely to cause adverse impacts is predicted in advance, appropriate mitigation measures like settling of suspended solids or passive treatment to improve water quality as well as quantity, etc. could be planned. Monitoring should demonstrate that there is no adverse effect of pollutant concentrations exceeding the statutory limits for the water, soil and air qualities in the area around the closed mine.

4.9.1.3 Biological Stability The stability of the surrounding environment is primarily dependent upon the physical and chemical characteristics of the site, whereas the biological stability of the mine site itself is closely related to rehabilitation and final land use. Nevertheless, biological stability can significantly influence physical or chemical stability by stabilizing soil cover, prevention of erosion/wash off, leaching, etc. A vegetation cover over the disturbed site is usually one of the main objectives of the rehabilitation programme, as vegetation cover is the best long-term method of stabilizing the site. When the major earthwork components of the rehabilitation programme have been completed, the process of establishing a stable vegetation community begins. For

52

Prefeasibility Report for Granite Quarry Mining <5 Ha

revegetation, management of soil nutrient levels is an important consideration. Additions of nutrients are useful under three situations.

 Where the nutrient level of spread topsoil is lower than material in-situ e.g. for development of social forestry.  Where it is intended to grow plants with a higher nutrient requirement than those occurring naturally e.g. planning for agriculture.  Where it is desirable to get a quick growth response from the native flora during those times when moisture is not a limiting factor e.g. development of green barriers. The mine closure plan should be as per the approved mine plan. Stage wise mine closure plan with budget available financial / manpower should be prepared and implemented. Such plan with the approval of the competent regulatory authority should be made available to the concerned State authority giving the environmental clearance. The Mine closure plan is enclosed in Annexure-7.

53

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 0-2 Time Scheduling For Abandonment and Cost Abandonment

Items Details /yearwise Area Quantity Expenditure Proposed Proposed (Rs.) Proposed (A) (i) Backfilling (within the lease Reclamation & as per PMCP) Rehabilitation (ii) Afforestation on the mined of mined out out area pit and area I 6066m2 606sap. 8000 II 6066m2 606sap 8000 III 6066m2 606sap 8000 IV 6066m2 606sap. 8000 V 6066m2 606sap 8000 (iii) Others (Please specify) e.g Afforestation on exhausted benches. – – – (iv) Pisciculture (v) Converting into water reservoir – – – (vi) Picnic spot – – – (B) (i) Terracing Stabilization & (ii) Pitching – – – Rehabilitation (iii) Construction of Parapet – – – of dumps Walls. – – – (within lease) I 50m 10 lab. 5000 II 50m 10 lab. 5000 III 50m 10 lab. 5000 IV 50m 10 lab. 5000 V 50m 10 lab. 5000 (iv) Construction of Check Dams. (v) Construction of settling – – – ponds (drains etc) (vi) Desilting of settling ponds, – – – channels. (vii) Afforestation on dumps – – – (viii) Others (Please specify)

(C) (i) Afforestation on barren land Rehabilitation I of barren area II 0.1476 m2 178 sap. 6000 (within lease) III 0.1476 m2 178 sap. 6000 IV 0.1476 m2 178 sap. 6000 V 0.1476 m2 178 sap. 6000 0.1476 m2 178 sap. 6000

TOTAL - - 95,000

54

Prefeasibility Report for Granite Quarry Mining <5 Ha

4.12 ENVIRONMENT MONITORING PROGRAM Environmental monitoring program is a vital process of any management plan of the development project. This helps in signaling the potential problems resulting from the proposed project and will allow for prompt implementation of effective corrective measures. Environmental monitoring will be required for the operation and closure of mining operations.

The main objectives of environmental monitoring are

 To assess the changes in environmental conditions,  To monitor the effective implementation of mitigation measures,  Warn significant deteriorations in environmental quality for further Prevention action.

The environmental attributes to be monitored as part of the monitoring programme are Air Quality, Noise Levels, Surface and Ground water quality and Soil quality. The monitoring program are presented in Table 25 & 26

Table 0-3 Budget for Environmental Monitoring Plan – Operation Phase

S.No. Item Parameters Frequency Unit cost Sampling Cost/Year (Rs.) /Year (Rs.)

1 Ambient PM10, PM2.5, SO2 & Monthly 2800 36 100800 Air NOx Quality 2 Noise Equivalent Noise Monthly 500 36 18000 Level Level 3 Ground Physical, Chemical Monthly 1800 24 43200 Water and Bacteriological 4 Soil General Monthly 5000 36 180000 Parameters Total 342000

55

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 0-4 Environmental Monitoring Plan – Post Operation phase S.No. Item Parameters Frequency Unit cost Samples Cost/Year (Rs.) /Year (Rs.)

1 Air PM10, PM2.5, Quarterly 2800 12 33600 Quality SO2 & NOx 2 Noise Equivalent Quarterly 500 12 6000 Level Noise Level 4 Ground Physical, Quarterly 1800 8 14400 Water Chemical and Analysis Bacteriological 6 Soil General Quarterly 5000 12 60000 Quality parameters Total 114000

4.13 REPORTING & DOCUMENTATION All the necessary reports and documents shall be prepared to comply the statutory rules & regulations. Proper and due care shall be taken to adhere to the laid down rules and regulations by the government.

Regular and periodic record shall be kept in order to ensure easier, comparable and brisk review and projection of past, present and future performances. Also, the management shall ensure to prepare separate records for water, wastewater, solid waste, air, emission, soil & manure regularly and periodically in order to provide better and smooth vigilance.

The management shall look into the fact that as soon as the report is prepared, it shall be forwarded to the concerned authority with due care for the purpose of reviewing.

Adhering to the rules and regulations the management shall ensure that the outcome of the reports and the conclusions drawn shall be prepared as per the laid down regulations and procedures. No breach of any convention shall be availed.

These reports/documents shall be regularly and periodically reviewed and any changes/discrepancies found in mitigation measures/ operation/ management/

56

Prefeasibility Report for Granite Quarry Mining <5 Ha

Shall be brought into notice instantaneously and all possible corrective actions shall be taken.

4.14 ORGANIZATIONAL SET-UP The Mines Manager at the project site will be directly responsible for various environmental activities. The Managing Director will co-ordinate and oversee the environmental activities and propose effective implementation as per the guidelines in the EMP. Organization chart of the Environmental cell is given in Figure 4-1.

MANAGING DIRECTOR

MINES MANAGER

MINING PERSONNEL LABORERS

Figure 0-1 Environmental Management Cell 4.15 Budget provisions for EMP It is proposed to take up protective measures like construction of retaining walls near the toes of the dumps. The haul roads both within the lease and outside the mining lease including roads leading to the crushing plant will be watered and good drainage system would be maintained. The project authorities propose to undertake the following environmental works to achieve the environmental quality as desired.

Adequate budgetary provision has been for execution of Environmental Management Plan. The detail of budget is given Table 4-3.

57

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 0-5 EMP Budget Provisions

Capital cost in Annual recurring cost S. No. Lakhs in Lakhs 1 Pollution Control Dust Collector 0.5 0.1 Water Sprayer 1.5 2.15 Plantation on dumps 0.5 0.1 Drains along Roads 0.75 0.04 Green belt development 1.5 0.26 2 Pollution Monitoring - 3.43 3 Fire fighting 1.5 0.3 Occupational Health 4 0.75 0.3 and safety 5 Reclamation / 1.00 0.2 Rehabilitation of mined out area Grand Total 8 6.7

4.16 CORPORATE SOCIAL RESPONSIBILITY As a part of CSR activity, the proponent has planned to distribute Computers, books etc. Provide learning assistance to the nearby schools and skill development among rural underprivileged youth. The cost estimate for the same is given below.

58

Prefeasibility Report for Granite Quarry Mining <5 Ha

Table 0-6 CSR Budget Allocation

S.No. CSR Activity Capital Cost Operation (Lakhs) Cost(Lakhs) 1 Computer Assisted Learning Programs 0.5 0.5

2 English and work readiness skills to rural youth 0.5 0.5 3 Training and creating Employment among the 1 0.5 Rural 4 Educational assistance to culture and religious 0.5 0.5 function (yearly) 5 Educational scholarship from 1st std 5th std 0.5 0.5 (yearly) – Total 3 2.5

4.17 CONCLUSION The proponent will take all precautions to control dust emissions during material handling, crushing and transportation. Also noise levels will be controlled by plantation wherever possible.

It can thus be concluded that the project is environmentally compatible, financially viable and would be in the interest of construction industry thereby indirectly benefiting the masses.

59