Anchorage Park - Complete • Construction of embankments using 56,000m3 of earth material. North Portsea Island • Placing of 21,000t of rock in front of the defences to protect against erosion. Construction Phasing • Extensive landscaping and replanting. Construction works have been split into distinct phases which will be delivered over a period of seven years. Phase 1 Anchorage Park COMPLETE Phase 3 September 2016 Tipner Lake Eastern Road UNDER CONSRUCTION completion in 2019 HILSEA PORTSMOUTH and Kendall’s Phase 4 EasternCopnor Rd Road & Kendall’s Wharf Phase 5 CONSTRUCTION Milton Common - Complete Ports Creek commence September CONSTRUCTION 2019 • A new coastal footpath and three new raised banks set 2023 - 2024 LANDPORT Wharf back in the common. Portsea Island • The demolition of Great Salterns Quay which gave back FRATTON Coastal Defence Scheme 2 2650m of habitat to the environmentally designated St Marys Rd MILTON COMMON harbour. Queen St Phase 2 Milton Rd • Construction of 750m of rock defences. Milton Common and Great Salterns Quay COMPLETE September 2016 Elm Grove Albert Rd Highland Rd Clarence Pier SOUTHSEA Clarence Parade Phase 1: Anchorage Park Phase 2: Milton Common Phase 3: Tipner Lake Phase 4: Eastern Road & Kendall’s Wharf Phase 5: Ports Creek Map of scheme area Tipner Lake – Almost Complete Drop in Exhibition Event Keep Updated Find out more about what the new • This phase of the work is from the Mountbatten Centre, For more information and to keep up to date with the progress defences will look like Twyford Avenue to the Ports Creek Roundabout and of the scheme please visit: formed Phase 3 of the North Portsea Island scheme • A 1.85km concrete seawall at 1.2m above the coastal www.escp.org.uk
[email protected] The Great Salterns Mansion Harvester path.