Eastern Road and Kendall's Wharf
Total Page:16
File Type:pdf, Size:1020Kb
Anchorage Park - Complete • Construction of embankments using 56,000m3 of earth material. North Portsea Island • Placing of 21,000t of rock in front of the defences to protect against erosion. Construction Phasing • Extensive landscaping and replanting. Construction works have been split into distinct phases which will be delivered over a period of seven years. Phase 1 Anchorage Park COMPLETE Phase 3 September 2016 Tipner Lake Eastern Road UNDER CONSRUCTION completion in 2019 HILSEA PORTSMOUTH and Kendall’s Phase 4 EasternCopnor Rd Road & Kendall’s Wharf Phase 5 CONSTRUCTION Milton Common - Complete Ports Creek commence September CONSTRUCTION 2019 • A new coastal footpath and three new raised banks set 2023 - 2024 LANDPORT Wharf back in the common. Portsea Island • The demolition of Great Salterns Quay which gave back FRATTON Coastal Defence Scheme 2 2650m of habitat to the environmentally designated St Marys Rd MILTON COMMON harbour. Queen St Phase 2 Milton Rd • Construction of 750m of rock defences. Milton Common and Great Salterns Quay COMPLETE September 2016 Elm Grove Albert Rd Highland Rd Clarence Pier SOUTHSEA Clarence Parade Phase 1: Anchorage Park Phase 2: Milton Common Phase 3: Tipner Lake Phase 4: Eastern Road & Kendall’s Wharf Phase 5: Ports Creek Map of scheme area Tipner Lake – Almost Complete Drop in Exhibition Event Keep Updated Find out more about what the new • This phase of the work is from the Mountbatten Centre, For more information and to keep up to date with the progress defences will look like Twyford Avenue to the Ports Creek Roundabout and of the scheme please visit: formed Phase 3 of the North Portsea Island scheme • A 1.85km concrete seawall at 1.2m above the coastal www.escp.org.uk [email protected] The Great Salterns Mansion Harvester path. Eastern Rd, Portsmouth PO3 6QB • Construction started in April 2017, with completion /EasternSolent- Wednesday 14th August 13:00 - 19:00 @EasternSolentCP scheduled for Autumn 2019. CoastalPartnership /EasternSolentCP EasternSolentCP www.portsmouth.gov.uk Construction Site and Access How will I be affected? Zone 1 - September 2019 Temp diversion: 1st Sept • In order to build the defences safely, the area will Work starting at Kendall’s 2019 - 30th Oct 2020 Permanent diversion: 1st Morrisons Wharf April 2020 need to be closed to the public. This will include Why do we need new defences here? Footpath temp closed: 1st Sept 2019 - 1st April 2020 closing the coastal footpath between Milton Temp closure: 1st April • To reduce the risk of flooding from the sea over 2019 - end Oct 2020 Common and Anchorage Park for the duration of Construction compound areas the work. the next 100 years to over 4,000 homes, nearly Peter Cooper VW • The shared cycleway and footpath along the 500 businesses and key infrastructure. Marshall Zone 2 - April 2020 Mercedes-Benz Work starting on Temp diversion: 1st Sept • The existing seawall along this stretch of Eastern Road 2020 - 30th Oct 2022 Eastern Road will remain open for the duration of Temp closure: 1st April coastline is in poor condition. 2020 - 30th Oct 2022 the work. Construction compound • The current defence is too low to provide areas • Car parking will be limited during construction, adequate flood protection to the area behind. McDonald’s however businesses will remain open as usual. • Find out more about what to expect during • An extreme storm event could result in sea water Harbourside Park construction at the exhibition event. going over the top of defences, causing flooding. Harvester Golf Course What will it look like? • The wall will stand 1.2m above the new path level along the length of the frontage. • The new path will be a minimum width of 2m which Portsmouth College will connect to the existing Milton Common and Anchorage Park coastal paths. • Extra seating, viewing areas and planting will also Artist’s Impression - North of Sailing Club Artist’s Impression - South of Harvester be introduced to the frontage. Timeline of works • There is opportunity for enhancements such as a textured wall to encourage marine growth and 2019 2020 2021 2022 2023 habitation, tidal pools and an offshore bird island, creating important new habitats. Sprng Summer Kendall’s Wharf Winter Winter Spring Winter Spring Autumn Spring Summer Autumn Summer Autumn Summer Autumn Winter Spring Construction When will it happen? • Construction work on the road at Kendall’s Planting & Wharf, off the Eastern Road, is due to start reinstatement September 2019. This work is anticipated to Eastern Road take six months. Construction • Construction of the seawall is expected to commence in spring 2020. The seawall Planting & construction is currently programmed to take reinstatement three summers and be completed in autumn 2022. Planting and reinstatement will continue until spring 2023. • These works are subject to planning approval..