PARKS REPLACEMENT BOND Annual Report 2017-2018 Wednesday – August 8, 2018

Commissioner Amanda Fritz | Interim Director Kia Selley Bond Report Year 3

✓BACKGROUND BOND YEAR 3 ✓PERFORMANCE ▪Program Overview 2014 Parks ▪Scope Replacement Bond ▪Schedule $68 million for repairs and ▪Budget replacements ✓INVESTMENTS ✓TRANSPARENCY Background Year 3

PROJECT DELIVERY Bond & SDC Investments Phases 1 & 2 Performance Overview

St. Johns Community Center Roof Performance - Scope

Colonel Summers Park Loo & Splashpad Performance - Schedule

Lents Park Playground

Investments

Ventura Park Playground Transparency

✓ PUBLIC INVOLVEMENT Transparency

✓ BOND OVERSIGHT COMMITTEE ▪ Demonstrate effectiveness of outreach efforts Audit

✓ AUDITS

▪ Performance

Mary Rieke Soccer Field Going Well

• Projects well received • Exceeding D/M/W/ESB Utilization • Majority on schedule/scope • On budget except for Grant Pool • Tracking tools well utilized • High performing team

Forest Park: Lower Macleay Trail Project Highlights

• Mt. Tabor Park • Argay Park • • Glenwood Park

Mt. Tabor Park Summit Restroom Project Highlights

Kenton Park • Playground • Rieke Field • Project Highlights

• Irving Park Play Piece Renovation Looking Ahead

• Couch Park Loo • Couch Park Playground • Restroom • Fernhill Park Water Supply • Kenton Park Playground • Mt. Tabor Park Handrails • Playground • Raymond Park Loo • Kitchen Roof • Pool Ventura Park Playground THANK YOU!

Robin Laughlin Lauren McGuire Assets & Development Division City of Portland Robin Laughlin 971.940.5567 [email protected]

Argay Park Tennis Courts