Railway Project

1.0 Month of Review : February’2011

2.0 Salient Feature

2.1 Name of the project: GAUGE CONVERSION OF LUMDING- (201.03 Km), ARUNACHAL-JIRIBAM (50.39 Km) BADARPUR-KUMARGHAT (117.82 Km)

2.2 Implementing Agency : N. F. Railway, Construction

2.3 Length of the Railway line : 368.1 Km

2.4 Estimated Cost : ` 3909.49 Crs.

2.5 Date of Commencement : 1996-97

2.6 Schedule date of completion : Dec’2013

2.7 Brief description of project : Gauge conversion of Lumding-Silchar, Arunachal- Jiribam, Badarpur-Kumarghat from Metre gauge line to Broad gauge. This involves earthwork 677.83 lac cum, major bridges (substructure 95 Nos., superstructure 130 Nos.), minor bridges 652 Nos. Tunneling 10650 RM.

Measurable Milestone for LMGLMG----SCLSCL (201.03 Km), ArunachalArunachal----JiribamJiribam (50.39 Km)BPPKm)BPP----KGTKGT (117.82 Km)

Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons Revised Bottleneck/Rema rks No (Days) Date of Date of Target Achieve - for delay date of (if any) . start finish up to ment up to completion Feb’2011 Feb’2011 1 Date of sanction of project 1996 -97 Dec’2013 2 Detailed project report (FLS) Completed Section wise 3 Regulatory clearance (if any) Not pending

4 Land acquisition (if involved) Out of 509.810 hect. 50 1.9 9 hect. Acquired. Section wise However, there is problem in doing work at acquired locations as per annexure. 5 Construction i. Earthwork 30.11.1 3 66 6.16 654.71 Law & progress (Lac cum) (98.28%) (96.59%) Order (section wise) ii . Major Bridges: 31.10.1 3 89 76 problem & Less due to continuous rain w.e.f. Sub-str.( No.) (93.68%) (80%) working March’2010 & very bad road condition. Major Bridges: Super 30.11.1 3 102 68 condition Less due to adoption of welding system for Structure: (No.) (78.72%) (52.31%) of Road & steel girders & very bad road & bridge Bridge on condition affecting transportation of fabricated NH-54-E discomponent. iii. Track linking (KM) 25. 12 .1 3 216.27 102.95 from Less due to continuous rain w.e.f. (57.13%) (27.20%) - March’2010. Difficulty in movement of Rail Lumding- panels, sleeper and ballast due to shortage of Silchar. MG BFRs, hoppers and Power. iv. Tunneling ( M) 30.11.1 3 7855.10 5726.60 Due to late finalization of Risk & Cost tender (73.76%) (53.77%) for Tunnel No10 & worsening condition of Roads & Bridge in N. C. hills (now Dimahasao, Distt. of ) v. Commissioning 31. 12 .1 3 - -

3.0 Financial Monitoring 3.1 Sanctioned Cost of the project `3909.49 Crs. (Revised) `1689.12 Crs. (original) 3.2 Cash-flow projections up to the month `2518.67 Crs. (up to Feb’11) 3.3 Actual Expenditure up to the month `2518.67 Crs. (up to Feb’11) 3.4 Variations (if any) NIL 3.5 Reasons for 3.4 above No variation. 3.6 Revised cost projects. Revised estimate amount `3909.49 Crs. sanctioned by Rly. Board. Annexure Reasons for delay in execution during the Quarter :-

(i) Worsening condition of Roads: Though the project of 4 laning of Lumding-Silchar (National Highway has been sanctioned, condition of the road in NC Hills area has become horrible. It is worthwhile to mention that most of the structural steel materials and reinforcement, cement, sand, aggregate etc. has to be brought from far flung area. With the present condition of the roads, which are not at all motorable, it will not be possible to move the heavy materials specially Bridge girder component etc. Immediate restoration and its continued sustenance of the road condition including the wooden bridge needs to be ensured for smooth movement of men and materials.

(ii) Divisional Forest Officer, NC Hills, , had advised regarding stopping of all the activities of construction of Br.127 & 129 and earthwork in the near by area stating that this land belongs to Forest Deptt. This land was acquired by Railway through NC Hill Council and accordingly work was in progress for last 3 years. It is pertinent to point out that bridge No.127 with PSC girder spans of 7x24.4m has already been progressed up to bed block level and only the superstructure with PSC girders is to be casted. Earthwork on both the sides have also been completed. Br. No.129 is 2 spans of 30.5 m PSC girders on pile foundation which is likely to take minimum 2 working season for construction. The matter was already brought to the notice of Principal Secretary to PMO during progress review meeting being held by him. Proposal for acquisition of Forest Land (3.6 Hect.) has been forwarded by State Govt. to CCF/Central, Shillong in the month of Feb’2011.

(iii) Land acquisition under Cachar and Karimganj District of Assam State requires to be expedited in connection with Gauge Conversion of Lumding-Silchar, Arunachal-Jiribam and Badarpur-Kumarghat section.