Social Monitoring Report

Project Number: 46079-002 July 2020

PRC: Chaonan Water Resources Development and Protection Demonstration Project – External Monitoring and Evaluation Report on Resettlement, Social and Gender Development (No.12)

Prepared by Beijing Blue Angel Environmental Science and Technology Co., Ltd (Beijing, China) for the Project Management Office of Guangdong Chaonan Water Resources Development & Protection Demonstration Project

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

ADB-Financed Guangdong Chaonan Water Resources Development and Protection Demonstration Project NO. 3114-PRC

External Monitoring and Evaluation Report on Resettlement, Social and Gender Development

(NO.12)

Beijing Blue Angel Environmental Science and Technology Co., Ltd. Beijing, China

July, 2020

M&E on Resettlement, Social and Gender Development (3114- PRC)PRC)PPPPRC)PRC)

CONTENTS

ABBREVIATIONS ...... III

I. SUMMARY ...... 1

1.1 INTRODUCTION TO THE PROJECT ...... 1 1.1. Background ...... 1 1.1.2 Progress updated ...... 2 1.1.3 Resettlement Plan ...... 7 1.1.4 Feedback to the Previous Monitoring and Evaluation ...... 8 1.2 EXTERNAL RESETTLEMENT MONITORING & EVALUATION ...... 9 1.2.1 Scope of this M&E...... 10 1.2.2 Procedure and Methodology of this M&E ...... 10 1.2.3 Scope of this Report...... 11 1.2.4 Schedule of this M&E ...... 11

II. RESETTLEMENT IMPLEMENTATION ...... 12

2.1 COMPENSATION PAYMENT ON THE PERMANENT ACQUISITIONED COLLECTIVE LAND ...... 12 2.2 STATUS OF THE TWO AFFECTED HOUSEHOLDS ...... 12 2.2.1 Income Restoration Status...... 12 2.2.2 Resettlement Compensation Status ...... 14 2.2.3 Evaluation ...... 15 2.3 ENDOWMENT INSURANCE ...... 15 2.4 LAND USE PLAN FOR THE VILLAGE COLLECTIVE RESERVED LAND ...... 20 2.5 CONCLUSION ...... 21

III. SOCIAL DEVELOPMENT AND GENDER ACTION PLAN IMPLEMENTATION ...... 22

3.1 EMPLOYMENT STATUS OF CONTRACTORS ...... 22 3.2 TRAININGS ...... 28 3.3 PUBLIC CONSULTANCY ...... 32 3.4 Other social and gender actions ...... 32

IV. FINDINGS AND SUGGESTIONS ...... 34

4.1 FINDINGS ...... 34 4.2 SUGGESTIONS ...... 36 APPENDIX 1: SOCIAL ACTION PLAN IMPLEMENTATION ...... 38 APPENDIX 2: GENDER ACTION PLAN IMPLEMENTATION ...... 46

i

M&E on Resettlement, Social and Gender Development (3114-PRC)

Figure 1: The overall distribution of the Project

ii

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

ABBREVIATIONS

ADB Asian Development Bank AAOV Average Annual Output Value AH Affected Households CNY Chinese Yuan CFB Chaonan Finance Bureau CLRB Chaonan Land Resources Bureau CWAB Chaonan Water Affairs Bureau CWSC Chaonan Water Supply Company DI Design Institute EA Executing Agency GDP Gross Domestic Product FSR Feasibility Study Report HH Household IA Implementing Agency LAR Land Acquisition and Resettlement LARD Land Acquisition and Resettlement Division M&E Monitoring and Evaluation MLSSP Minimum Living Standard Security Program PMO Project Management Office PPTA Project Preparatory Technical Assistance PRC People’s Republic of China RP Resettlement Plan

TOR Terms of Reference WSP Water Supply Plant WWTP Wastewater Treatment Plant WSC Water Supply Company

iii

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

I. Summary

1.1 Introduction to the Project

1.1.1 Background

Chaonan Government won the Asian Development Bank (ADB) loan $100 million for the Guangdong Chaonan Water Resources Development and Protection Demonstration Project (Project). The project will protect water resources and improve water security in Chaonan District, Municipality, Guangdong Province of the People’s Republic of China (PRC). The project will ensure new or more reliable water supply for about 1.37 million (about 256,000 families) ① urban and rural inhabitants of Chaonan District by integrating urban–rural water supply systems and reducing water losses. Meanwhile, It will also support watershed management through reforestation, pollution prevention and, water quality monitoring, public awareness building, and institutional capacity development, etc. The project will not only have a favorable impact on the better health and life quality in Chaonan District; but also bring about the outcome of improved and equitable water supply services to urban and rural residents in Chaonan District. The project includes three outputs: Output 1: Improved water resources protection. This output comprises (i) public awareness and learning on environment and sanitation; (ii) water conservation reforestation of about 1,682 hectares (ha) in the catchments of Jinxi, Longxi, and Qiufeng reservoirs; (iii) a study on pollution prevention and control measures in the water source protection zone; and (iv) solid waste collection and treatment in Chengpo and Qiufeng villages. Output 2: Improved water supply infrastructure. This output comprises (i) expansion of the capacity of the Qiufeng water supply plant (WSP) from 70,000 m3/day to 142,000 m3/day, and construction of the sludge treatment facilities and water intake facilities; (ii) rehabilitation of the Jinxi WSP by constructing a pump station and the sludge treatment facilities; (iii) construction of the Longxi WSP with a capacity of 100,000 m3/day, including the sludge treatment facilities and a pump station; (iv) installation and upgrade of the water transmission and distribution pipelines in the district with a total length of about 1,000 kilometers; (v) establishment of a water quality monitoring center; (vi) installation of water meters for about 37,770 household; and (vii) provision of operation and maintenance equipment, including leakage detection equipment. Output 3: Strengthened institutional and staff capacity. This output comprises (i) provision of consulting services and relevant training programs, including study tours for project implementation; (ii) support for the establishment of a water supply control center with a remote monitoring and control system, a data transmission and dispatching center, and a communication network attached; (iii) support for the establishment of a management center of water resources and three preventions (flood, drought, and typhoon); (iv) preparation of an action plan regarding water resources protection and development to

① Data from Chaonan statistics in the 2014 Statistical Yearbook of Shantou 1

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) address issues concerning water safety, water allocation optimization, and water reuse and conservation; and (v) establishment of a project monitoring and evaluation system.

Table 1-1: Basic Information of the Project

Loan No. 3114-PRC Guangdong Chaonan Water Resources Development and Protection Project Demonstration Project Borrower People’s Republic of China Signing Date 30 May 2014 Effectivity Date 12 August 2014 Project Completion Date 31 Mar 2021 Closing Date 30 September 2021 Last ADB Mission 17-21 June 2019

Executing Agency( EA) Chaonan District Government

(1) Water Bureau of Chaonan District (2) Urban Management Bureau of Chaonan District Implementing (3) Agricultural Bureau of Chaonan District Agency( EA) (4) Education Bureau of Chaonan District (5) Environment Protection Bureau of Chaonan District (6) Chaonan Tap Water Company Proposed total project investment is $230.75 million, including $100 Investment and financing million from the ADB loan and the rest from domestic counterpart plan funding.

Of the three outputs, lands used for Output 1(improved water resources protection) will be the lands that are not currently cultivated or contracted to villagers for farming or planting economic forest; therefore, no land acquisition and resettlement will be involved. Output 2 (integrated urban and rural water supply system) has involved the land acquisition and resettlement. Output 2 consists of five sub-outputs: (i) expansion of the Qiufeng WSP in Gucuo Village, Liangying Town; (ii) reconstruction of the Jinxi WSP in Shenxi Village, Xiancheng Town; (iii) construction of the Longxi WSP in Dongbo Village, Longtian Town; (iv)installation of about 1,000 (km) of pipelines; and (v) establishment of a water quality monitoring center. Output 3 (strengthened institutional and staff capacity) does not involve land acquisition and resettlement.

1.1.2 Progress updated

There are altogether 14 construction contracts in this project now as Contract C5 has been combined into C3 as mutually agreed by ADB and PMO. 7 out of 17 contracts have been completed, as the rest seven contracts are still ongoing. Details are presented as below: Table 1-2:

2

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-3: Summary of Contract Award of ADB Financed Contracts and Implementation Status

Bid Date of Construction Completion Code Description Contractor Opening Contract Starting Date Date

Exhibition hall for water resource Gansu Yi’an Construction Technology C1 2019/6/14 2019/8/9 2019/9/10 2020/10/31 protection and bulletin boards Group Co., Ltd.

Water conservation reforestation C2 around the three major reservoir Shantou Nanyang Greening Co., Ltd. 2016/12/13 2017/3/22 2017/3/26 Completed1 areas

Civil works, installation, and Consortium of Guangdong Yaonan commissioning of water transmission Construction Company and pipelines for Shikeng to Yangfenchen Guangdong No.2 Hydroelectric C3 2016/4/8 2016/5/12 2016/7/23 Completed and Wugou reservoir to the Longxi Company water supply plant and for Shi-Jing section

Consortium of Guangdong No.2 Civil works, installation, and Construction Engineering Co. Ltd and C4 commissioning of the Longxi water Professional Water 2015/10/9 2015/10/28 2015/12/29 Completed supply plant Supply Construction and Installation Co. Ltd.

Water distribution pipelines in Shantou Sanling Civil Construction C6 2017/5/3 2017/6/26 2017/9/28 Completed Longtian township Company

Water distribution pipelines in C7 townships of Liangying and TASTOD Construction Group 2018/12/6 2019/4/25 2019/4/30 2020/12/31 Xiancheng

Consortium of Guangdong No.2 Expansion of Qiufeng water supply Construction Engineering Co. Ltd and C8 plant and reconstruction of Jinxi 2017/8/4 2017/9/7 2018/4/4 2021/02/28 Hydroelectirc Construction water supply plant Engineering Co. Ltd

Distribution pipelines in townships of Guangdong Dayu Water Conservancy C9 2017/5/3 2017/6/27 2017/8/25 Completed Chengtian and Jingdu Construction Co. Ltd.

Highway pipeline network of the water Shantou Sanling Civil Construction Almost C10 supply for each village in Chaonan 2013/06/20 2013/0710 2013/07/25 Company. completed District Phase I

Distribution pipelines in Lugang Guangdong Dayu Water Conservancy C11 2018/10/9 2018/12/9 2018/12/25 2020/10/31 township Construction Co. Ltd.

Shantou Sanling Civil Construction C12 Distribution pipelines in Xiashan 2018/9/21 2019/4/17 2019/4/28 2021/3/31 Company

Distribution pipelines in townships of Shantou Sanling Civil Construction C13 2018/12/21 2019/2/11 2019/5/13 2021/1/31 Chendian and Simapu Company

Civil works, installation, and Guangdong Dayu Water Conservancy commissioning of water transmission Construction Co,. Ltd. C14 2019/2/15 2019/4/12 2019/7/5 2020/12/31 pipeline for He-Yang, Si-gao, and Xia-Xin sections Main contractor: Shantou Chaoyang Civil works, installation, and C15 No.1 Construction & Installation 2019/2/15 2019/4/25 2019/5/20 Completed commissioning of water transmission Controlling Company; Member:

1 Completion acceptance on 29 November 2019. 3

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Bid Date of Construction Completion Code Description Contractor Opening Contract Starting Date Date pipeline for Donglan and Shan-He Shantou Chaoyang Construction sections Engineering Corp

Solid waste collection & transfer Hubei Daxin Automobile Equipment G1 trucks & equipment in Chengpo and Co., Ltd. 2017/9/8 2018/1/21 / Completed2 Qiufeng villages

The construction in progress is as follows:

C1 contract package (Exhibition hall for water resource protection and bulletin boards);): by the March 10, 2020, this package has been completed. C7 contract package (Water distribution pipelines in townships of Liangying and Xiancheng): the construction in this contract was started on Oct 30, 2019. By the first half of 2020, the total length of the pipeline has been 63.07 km, accounting for 65% of the total length of the pipeline, including trench excavation and foundation treatment, concrete pavement breaking, pipeline laying, pipe trench stone chip backfilling (including cushion), etc. It is expected to be completed on Dec. 31, 2020, and construction is continuing as planned. C8 contract package (expansion of Qiufeng water plant and reconstruction of Jinxi water plant): this construction was officially started on April 4, 2018. As of June 30, 2020, the main structure of the reconstruction project of Qiufeng water plant has been completed; the surroundings of each building is under construction; the operation equipment, lighting and security construction of various structures in the plant area are in progress; and the electrical instrument installation of various structures in the plant area is under construction. The main structure of Jinxi water plant renovation project has been basically completed; the plastering and facade construction of all structures have been completed; the water supply and drainage pipeline construction in the plant area has been completed; the concrete pouring and greening planting of road in the plant area have been completed; the operation equipment, lighting and security construction of all structures in the plant area have been completed; the electrical instrument installation of all structures in the plant area is expected to be completed on Feb. 28, 2021. The C11 contract package (Distribution pipelines in Lugang township): this contract was started on December 24, 2018. By the first half of 2020, 35.707km of water distribution network and 7.42km of Zhonggang River main pipeline have been installed and to be completed on Oct. 31, 2020. C12 contract package (Distribution pipelines in Xiashan): this contract was started on April 28, 2019, with a planned construction period of 12 months. By the first half of 2020, 380km has been completed, accounting for 55% of the project. At present, due to the COVID-19 the project is under construction according to the plan.. The C13 contract package (Distribution pipelines in Chendian township and Si Maipu township) was commenced in May 2019, and by the first half of 2020, the completed components are as follows: 1) the Chendian town pipeline project is in the process of pavement cutting, earth excavation, pipeline installation, etc., and it is estimated that 71% of

2 Completion acceptance on 22 May 2018. 4

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) the project have been completed. 2) Simapu town pipeline project is in the process of road cutting, earth excavation, pipeline installation and other works, which is estimated to have completed 63% of the project. C14 contract package (Civil works, installation, and commissioning of water transmission pipeline for He-Yang, Si-gao, and Xia-Xin sections): By the first half of 2020, the main construction contents of Xiaxin line include: open excavation of pipe trench earthwork, concrete pavement breaking, PE pipe laying, concrete pavement repair, steel pipe laying, stone chip backfilling, etc., and it is estimated that more than 80% of the project will be completed. (2) The main construction projects of the high-speed railway include: open excavation of pipe trench earthwork, concrete pavement breaking, PE pipe laying, concrete pouring, steel pipe laying, stone chip backfilling, etc., and it is estimated that more than 40% of the project will be completed. (3) The main construction projects of Heyang line include: pipe trench earthwork open excavation, concrete pavement breaking, PE pipe laying, concrete pouring, steel pipe laying, stone chip backfilling, etc., which is estimated to have completed more than 95% of this construction.

1.1.3 Resettlement Plan

Only Output 2 , which is the improved water supply infrastructure, involves land acquisition and resettlement (LAR) impacts, therefore, the PMO prepared a resettlement plan (RP) for the LAR during the project preparation. By far, the permanent land acquisition status of the three involved water plants is consistent with the effected scope in the original Resettlement Plan, all the relevant permanent land acquisition will be strictly conducted within the prescribed scope of Resettlement Plan. Therefore, there is no need to update the part of permanent land acquisition in Resettlement Plan. Chaonan PMO has effected the payments to the affected three villages in a total amount of RMB 6.0614 million CNY for acquiring a total of 79.33mu land. In the original Resettlement Plan, the second subproject still involves temporary occupation of 2271.16 mu of land for the purpose of laying pipelines, stacking building materials, temporarily stacking waste residue and building temporary access roads for civil works, specifically including: (i) 802.83 mu of temporarily occupied state-owned land (i.e., 112932 meters of the green belts of road), which is used as the work yard of installing all the water supply pipelines or as the storage yard for construction waste disposal. (ii) 1468.33 mu temporarily occupied collective land, which is used for other construction works disposal. According to the FSR, the construction waste residue area occupies an total land area of 1400 m2. It is located inside an industrial park of textile industry’s circular economy (the open lowland between Jingtian Road and Shenshan Road), construction waste residue. All land acquisition related resettlement has been finished in the economy industrial park’s project and there is no more charges required. The construction of the pipeline will be carried out section by section, and the timescale of occupation for each construction section will be reduced to approximately 1.25 years from the previous 5.15 years in the Resettlement Plan, and shall not exceed 1.5 years at most. The compensation standard for temporary occupation of collective land is: Average Annual Output Value* Occupation period+ Compensation for standing crops/trees. Table 1-2 is 5

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) a breakdown of compensation standards for temporary occupation of collective land.

6

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 1-2: Compensation Standard for Temporary Occupation of Collective Land

TTL Average Actual Original Compensation Annual Plant Original TTL Occupation Land Occupation fee by actual Output trees/compensation Compensation Time by Type Time (Year) Construction Value (yuan/mu) (Yuan/Mu) Construction Parts (yuan/mu) Parts (Year) (yuan/mu) Paddy 2,925 1,500 5.15 16,564 1.25 5,156 field Dry land 2,306 1,153 5.15 13,028 1.25 4,036 Orchard 2,306 6,000 5.15 17,875 1.25 8,883 Forest 415 4,089 5.15 6,225 1.25 4,608 land According to the compensation standard in the resettlement plan, the compensation standard formula calculated according to the occupation time is: compensation standard = average annual output value x occupation time + compensation for seedlings / trees Resource: Chaonan Water Supply Company and the RP Construction of water supply and distribution pipelines also needs to temporarily occupy certain state-owned land (green belts along the road). Compensation for temporary occupation of state-owned land and the trees thereon is shown in table1-3. Table 1-3: Compensation Standard for Temporary Occupation of State-owned Land

Influence Category Unit Compensation Standard Road/Highway (tax occupied) yuan/m 30 (diameter ≤30cm)A Road/Highway yuan/m2/day 3 (green belt occupied) Eucalyptus yuan/a 100 A: As for the pipe diameter which is above 30 cm, with an additional increase of 10 cm in diameter, compensation standard will be increased by 10%. Resource: Chaonan Water Supply Company and CSADI.

According to the construction design drawing, the project has a total of 4239.76 mu of temporary acquisition land. A total of 1020.25 mu of land has been temporarily acquired for output 2 during this report period. As of this period, the total accumulative amount of temporary land acquisition for the project is added up to 3431.88 mu. So far, the actual temporary land occupation in the construction stage has been carried out according to the construction design drawing . The area of the temporary land acquisition is consistent with the design scopes of the construction drawing. The project has not been completed, thus after the completion of the project, the relevant temporary occupied lands will be further updated when the land acquisition is completed. See Chapter 2.6 for details of temporary land occupation for construction of each subproject.

1.1.4 Feedback to the Previous Monitoring Evaluation:

(1) Continue to implement the positive measures for SDAP and ultimately achieve various indicators of the social development and gender action plan .

In this period of the project implementation, due to the COVID-19, there are fewer female employees, local and low-income people, which fails to reach the target value in the social and gender action plan. In particular, the proportion of female employees of Guangzhou Erjian and Huizhou Shuidian (contractors) is the lowest at only 2.7%. The overall completion rate is

7

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) still not reaching the targets. At the same time, due to the COVID-19, there was basically no public consultation for decision-making activities in the first half of this period. Consultants suggest that PMO should continue to vigorously promote positive action measures in the implementation of various contracts (especially newly signed contracts) in the future. Especially when the epidemic situation has been alleviated, we should try our best to increase work opportunities for local residents, poor residents and women, especially for women in technical work and management positions, and also continue to improve women's participation in training and public decision-making opportunities.

1.2 External Resettlement Monitoring & Evaluation

The external monitoring & evaluation (M&E) work of the resettlement and implementation of the SAP and the GAP is solely undertaken by an implementing agency known as Beijing Blue Angel (BBA) Environmental Science and Technology Co., Ltd, as engaged by Chaonan Water Supply Company.

1.2.1 Scope of the M&E in this report period

According to the implementation plan of the project, by the first half of 2020, the LAR of the project had been progressing in a fair, open and orderly manner and in line with the relevant laws and regulations of the PRC and the requirements of ADB’s "Safeguard Policy Statement" (2009) . Among them, the LAR for construction of three proposed water supply plants has been completed and a total of 79.33 mu of permanent land has been acquisitioned. The scope of this external M&E is based on the monitoring and evaluation of land acquisition and resettlement about this 79.33 mu permanently acquisitioned land and the construction waste residue area,. continuously tracking The resettlement, compensation and economic recovery for two affected HH swill be continuously followed up. At the same time, design institutes have made clear once again during this M&E period that the reconstruction of Longxi WSP, extension of Qiufeng WSP and reconstruction of Jinxi WPS do not involve any temporarily occupied land. The temporary land acquisition in this period has been updated for Liangying town and Xiancheng town pipeline project, Lugang town pipeline project, Chendian town and simapu town pipeline project, Xiaxin Sigao pipeline project and Heyang pipeline project, Xiashan Street pipeline project and Shanhe line and Donglan line pipeline project (basically completed).. According to the project implementation plan, by the first half of 2020, the SDAP and the GAP have also been carried out continuously, and this report also includes monitoring and evaluation on land acquisition and implementation of the social and gender action plan.

1.2.2 Procedure and Methodology of the M&E in this report period

This is the 12th external monitoring and evaluation. Our team has followed up the implementation of the LAR of various subprojects and compared the implementation of social and gender action and resettlement situation after the resettlement has arranged; and the previous findings have been reviewed again; and the newly discovered issues and the corresponding suggestions have also been put forward. The external M&E of the Project have

8

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) been conducted as per the following methods: (i) Follow-up interviews and field surveys. Discussions were held with affected townships/communities, village committees, villagers' representatives/residents' representatives and heads of households to be relocated, to understand the impact of the project, the needs and willingness of the affected HH with different incomes, public participation, compensation for LAR, and economic recovery. (ii) Survey on implementation of the GAP and the SAP. Regarding the projects or subprojects being implemented or the contract packages being executed, comparison and analysis of the workers employed and the gender proportion thereof have been carried out so as to make sure whether the target values in the SAP and the GAP have been reached . (iii) Processing and analysis of the data as collected from all the EAs and related agencies, e.g., the construction companies, the Social Security Bureau, etc. have been carried out. (iv) Report the monitoring and evaluation results. Due to the influence of the COVID-19, in the first half of this period, on-site field interviews were not able to be conducted. Instead, we conducted the online survey on the implementation agencies and contractors.

1.2.3 Scope of this Report

This report is the 12th independent external monitoring and evaluation report on Guangdong Chaonan water resources protection and utilization demonstration project , with the purpose of monitoring and summarizing the current progress on resettlement plan , the SAP and the GAP being implemented as of the first half of 2020; following up the resettlement, compensation and economy recovery of the HHs affected by the permanent land acquisition; monitoring the fulfillment of the target values in the SAP and the GAP, proposing corresponding countermeasures with respect to the existing problems, constructing a system of M&E, including the findings of, the countermeasures and suggestions on the monitoring and evaluation system, etc.

1.2.4 Schedule of the M&E in this report period

In July 2020, we have made data collection and necessary investigation for the external monitoring and evaluation of the resettlement,social and gender action plan of the project, and will submit the external monitoring report in August 2020.

9

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

II. Implementation of Resettlement

2.1 Compensation Payment on the Acquisitioned Land

As collective land for permanent acquisition in July 2014, Chaonan PMO has effected all the payment for the permanently acquisitioned land of 79.33mu in the affected three villages, in the total amount of 6,061,4000.00 CNY. See details in Table 2-1: Table 2-1: Land Acquisition Compensation Payment on the Three WSPs

(Unit:10,000 CNY)

Land The project using Overall Resettlement location Acquisition land compensation Fee Compensation Fee Area(Mu) Newly-built Dongbo Village, Longxi Water 44.33 354.64 15 Longtian Town Plan Expanded Gucuo Village, Qiufeng Water 25 192.5 0 Liangying Town Plant

Renovated Jinxi Shenxi Village, 10 59 0 Water Plan Xiancheng Town

Three Village Total 79.33 606.14 15 Committees

Resource: Chaonan PMO For the collective land requisitioned for temporary land occupation, Shantou Chaonan water supply Co., Ltd. has officially signed the compensation agreement for temporary land occupation for pipeline construction with the village committees along the line at the end of December 2018. The actual compensation standard is consistent with the compensation standard in the resettlement plan. According to the compensation standard in the resettlement plan, the compensation standard formula is: compensation standard = average annual output value x occupation time + compensation for seedlings / trees. See the table below for the comparison between the specific compensation standards and the standards actually implemented in the resettlement plan

10

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-2: Summary of Compensation for Temporarily Occupied Collective Land

Actual Compensation compensation Compensation Compensation standard of Compensa for temporary standard for Average resettlement plan tion for land occupation Average section temporary output value - converted seedlings / in RP (Project construction time occupation of per mu according to trees Period of 5.15 land for sectional 1.25-year Years) construction occupation time (yuan / mu)

(Yuan/mu Land (Yuan/mu) (Yuan/mu) (Year) (Yuan/mu) (Yuan/mu) ) Category paddy field 2,925 1,500 16,564 1.25 5,156 5,156 dry land 2,306 1,153 13,028 1.25 4,036 4,036 orchard 2,306 6,000 17,875 1.25 8,883 8,883 woodland 415 4,089 6,225 1.25 4,608 4,608 Data source: summary of Chaonan water supply company, RP and the IA

Figure 2-1: Compensation Agreement and Payment Voucher (part) for Temporary Land Acquisition

11

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

2.2 Status of the Two Affected Households

• 2.2.1 Income Restoration Status

According to the RP, this project needs to permanently acquisition a total of 79.33 mu of collective land; By the end of 2014, Guangdong Chaonan Water Resources Development and Protection Demonstration Project conducted land acquisition from three villages, and a total of 79.33 mu collective land has been permanently acquisitioned. The completion rate for permanent land acquisition is 100%. The IA of the project has acquisitioned 44.33 mu of permanent land for the construction of Longxi WSP from Dongbo Village, Shenxi Town. Compensation shall be paid to the two affected HHs as per the land lease agreement as signed between the two HHs and Dongpo Village Committee and the possible impact on the 2 HHs of the official commencement time of Longxi WSP . Currently, the project has started. Two affected HHs had received the land acquisition notification before the construction started, and decided not to rent the land as from 1 January 2015. According to one of the affected household (Zheng Yongxiong’s family), he leased 65 mu of arable land for a short term (including the 22.165 mu land to be acquisitioned, among which there is 19.33mu land to be permanently acquisitioned), which is used to plant orange. Besides, he also leased 7 mu of pond to feed fish. These two tracts of leasehold land bring them in about 120, 000 CNY every year. When the permanent land acquisition started at the beginning of 2015, the household got 20,000 CNY as the direct financial compensation for the permanently acquisitioned land as per the compensation agreement. There are totally 8 people in the family. The couple are in their 50s; their two sons are in their 20’s and both are married; and they also have two grandsons respectively at the age of 6 and 10, among whom, two of the HH take charge of

12

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) the pond’s operation and management. By far, 30,000 CNY has been ploughed into the expanded operations of the pond. And they also renewed the contract with the village committee for an additional 5 years’ contractual operation of the pond. The investment is expected to bring their annual income up 10,000 CNY from the previous period. and even more benefits will be brought about in later period. In addition, while their son and daughter- in-law were growing orange, they can earn an additional daily income of 100 CNY by taking odds jobs in local areas, such as doing temporary farm transport, working as motorcycle-taxi drivers or doing other local part-time jobs, , which can bring them an annual income of about 28,000 CNY. The two daughters-in-law help deal with household chores and take care of the two children. Moreover, Dongbo Village Committee has signed a five-year lease (2013-2018) contract with Zheng’s family regarding a tract of farmland of 58mu to be used for cultivating paddy. The village committee is planning to renew the contract with the household in 2019 and continue to rent the land to the household. This tract of land is suitable to cultivate paddy. An average paddy-planting subsidy of 160 CNY/ mu has been provided for the HH by the government. And all the harvested rice is purchased by the government so the income from planting paddy will be more stable compared with planting orange, which needs to be marketed by themselves and is susceptible to natural disaster and the damage caused by pests. In June 2019 and January 2020, external M&E experts has conducted follow-up monitoring by both site visit and made online interview in Dongbo Village again , and found that the whole year income of Zheng’s family in 2019 has increased by about 10% compared with that before land acquisition. The main increase comes from planting paddy and taking odd jobs. Meanwhile, the income from operating the pond also has increased. All the income increase can make up for the income loss of planting orange as caused by land acquisition. Therefore currently the household’s income has exceeded the income before land acquisition, and the income is coming from more reliable and sustainable sources. The monitoring results in this report period indicate that the income of this household remains stable and unchanged during the monitoring period. The annual income will be followed up again in the next report period. The permanent land acquisition produces no adverse impact on the household, and no complaints have been received as yet. The other affected household (Zheng Shufeng’s family) has totally leased 25 mu of unused arable land to operate and sell building materials (The land is used as the storage yard), which has brought the household an annual income of 300,000 CNY. There are 6 people in this family. The couple of Mr. and Mrs. Zheng are in their 50s (Mrs. Zheng is staying at home due to poor health).The son and the daughter-in-law are migrant workers at other places. They have two granddaughters. One granddaughter is still studying in college; and another adult granddaughter is staying at home to help with the business and household chores. The HH should have to pay for their younger granddaughter’s education in college. At the beginning of 2015 and during the permanent land acquisition, the family got 130,000 CNY as the direct financial compensation as per the compensation agreement. There are 6 people in the family, among whom, two people are responsible for operation and management of the construction material business. After being compensated, the family has signed the a contract with the Dongbo Village Committee for a vacant land of 7-8mu to continue their business of building materials, the cost of the new business premises is about 13

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) 100,000 CNY. With the expansion of their construction material business, the annual income is 50,000 CNY higher than that before land acquisition. Furthermore, in the transitional period of the HH after land acquisition, the balance of compensation is RMB 30,000 yuanCNY, which is enough to maintain the life quality of the HH at normal level. The monitoring and survey results in this report period indicate that Zheng’s family continue operating the transportation business of building materials with their 14 trucks, each with an capacity of 30 cubic meters . The site change has brought some inconvenience to their sand and stone business at the beginning, but with the development of their business, their income has not been affected since most of the materials are sold to the neighborhood people who are going to build houses for themselves. Since the second half of 2016, the affected household began to repair their own vehicles, reducing the cost of vehicle maintenance, and the revenue was in good and stable condition. In June 2019 and January 2020, the external monitoring experts followed up the investigation by visits and telephone interview, and found that the profit margin of the household in 2019 was basically at the same level as that of the same period of last year. Therefore, the monitoring results of this period show that the income of Mr. Zheng Shufeng's family is stable during the monitoring period, and the permanent land acquisition has no negative impact on the family, with no complaints. Due to the influence of COVID-19, field survey was not carried out in this period. Experts will visit Dongbo village for field survey byt the end of 2020.

2.2.2 Resettlement Compensation Status

On 1 December 2014, Dongbo Village Committee, Longtian Town signed the Land Acquisition Resettlement Compensation Agreement with the first affected household Zheng Yongxiong (planting fruit trees). After accounting and discussion, 20,000 CNY was determined to pay for the resettlement compensation, in compensation for the losses in their benefits of planting orange, banana, their family income and other planting benefits; the expenses for land leveling of the new planting site and investment into the planting again, which are all caused by the land acquisition for Longxi Water Plant construction. On 1 December 2014, Dongbo Village Committee, Longtian Township signed the Land Acquisition Resettlement Compensation Agreement with the second affected household Zheng Shufeng (construction material business). After accounting and discussion, 130,000 CNY was determined to pay for the resettlement compensation, in compensation for losses in business and family income, and for costs of handling the remaining materials, demolishing the existing structures, leveling the ground and erecting the buildings on new business premises, , etc., which are all caused by the land acquisition for Longxi Water Plant. The compensation payments respectively to these two families have both taken effect on 4 June 2015.

14

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

2.2.3 Resettlement Compensation Evaluation

Taking into full account the actual benefits of the two affected HHs, and the maximum compensation to them, the LAR personnel in Dongbo Village, Longtian Town have been implementing the resettlement compensation and helping the two affected households recover economy in the shortest possible time, and consequently reduced the losses of the two affected households. Land acquisition and relocation have been carried out in a friendly manner, which won the good comments of two affected households and the whole village. According to the previous M&E results, the two households’ living and production conditions have not been changed, and no reduction in the households’ income and no adverse impact on their living standard have been caused by the land acquisition. In the first half of this year, due to the impact of covid-19, field interview and survey for the actual situation of these two households has not been conducted. But the consulting experts will pay the field visit in the second half of the year for follow-up status.

2.3 Endowment Insurance

Table 2 - 3: Endowment Insurance for Affected Villagers in Three Water Supply Plants Endowment insurance Beneficiary Land use project Address premium (10000 yuan) number New Longxi water Long tian Dongbo 40.5 45 plant village Expansion of LIangying Guyan 20.7 23 Qiufeng water plant village Reconstruction of Xiancheng Shenqi 8.1 9 Jinxi water plant village Three village Total 69.3 77 committees Source: Chaonan PMO According to the resettlement plan of the project, the project shall provide endowment insurance for 77 villagers from three affected villages. On December 23, 2011 and October 30, 2012, the Financial Bureau of Chaonan district directly appropriated the endowment insurance expenses to the Social Security Bureau of Chaonan District, totaling CNY 693,000, to pay the 15-year endowment insurance for the farmers whose land has been acquisitioned. The payment standard is CNY 50 per month, and CNY 9,000 in total for each person. The endowment insurance payment of the affected villages has been completed, and the affected people have been compensated according to the resettlement plan, as follows: (1) Dongpo Village, Longtian Town: Mr. Zheng, the village head, of Dongbo Village said that the beneficiaries’ name list of 45 villagers are determined by the village committee; and the village committee is planning to put those who are poorest and who need the pension most on the name list. The list has been posted to the public before being submitted to the Social Security Bureau. According to the latest information provided by Chaonan Social Security Bureau, till the end of June 2018, there are 12 (3 females included) of the 45 villagers (22 females included) who has reached the age of 60 and started to get the pension from the account, 5 villagers (2 females included) more than those in the previous M&E report. In their

15

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) pension, 119.74 CNY/month is coming from the endowment insurance of 9000 CNY/person paid due to the land acquisition. Beneficiary’s name list and detailed pension information of Dongbo Village have been shown in Figure 2-2. Figure 2-2: Beneficiary’s Name List and Detailed Pension Information of Dongbo Village

(2) Gucuo Village, Liangying Town : On December 2, 2018, the Gucuo Village Committee once again convened a community resident congress (see Figure 2) to discuss the name list of pension compensation (see Figure 2-3 for details). There are altogether 25 mu land acquisitioned and 23 beneficiaries’ pension insurance available in Gucuo Village. The meeting discussed and decided the 23 beneficiaries on the name list who can receive the pension in compensation. They are all residents of the community who are over 59 years old. In October 2019, the village committee submitted the name list to the Social Security Bureau through the town government, and then the Social Security Bureau paid the corresponding security funds to their respective pension accounts. Therefore, the compensation in Gucuo Village paid by endowment insurance has been completed.

16

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Figure 2-3:The Gucuo Village Committee Convened a Resident Congress on Beneficiaries of Land Acquisition Compensation on December 2, 2018

17

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Figure 2-4:The List of 23 Beneficiaries of Pension in Gucuo Village

Figure 2-5: Land Acquisition Compensation Personnel Information of Endowment Insurance in Gucuo Village (23 people)

(3) Shenxi village, Xiancheng Town: according to Director Liu of Shenxi village, Xiancheng Town, Shenxi village has a large population and more than 2000 people have already received endowment insurance. The acquired land belongs to collective land and is used by the collective. The project of Jinxi Water Plant has acquisitioned 10 mu land from Shenxi village. According to the original plan of endowment insurance compensation, 9 persons should be selected from the villagers for compensation. The number of persons for compensation is too small but the total number of people in the whole village is too large, so the village committee founds it difficult to 18

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) distribute them fairly. So in 2014, through the approval procedure of the Shenxi village villagers' congress, the endowment insurance which benefits 9 persons in this project , together with the 18 persons who could be provided by the land requisition of other projects in the village, were changed into the endowment insurance evenly shared by all the 2025 elder villagers who are receiving the endowment insurance .In November 2014, the scheme was officially approved by the HumanRresources and Social Security Bureau of Chaonan district (as shown in Figure 2-6). So far, the compensation issuein Shenxi village committee of Xiancheng town has been solved.

Figure 2-6: Official Approval On Land Acquisition Endowment Insurance

19

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

2.4 Land Use Plan for the Village Collective Reserved Land

According to the RP, the three affected villages have all marked out a total of 11.66mu reserved land (see the details in Table 2-3) according to the area of acquisitioned land and a particular proportion. Chaonan PMO has completed all the procedures to change the farmland into the homestead, and has paid off all the related taxes and charges. During this period the external monitoring experts did not visit the three villages, but according to the communication results of the two villagesthrough the PMO’s focal staff, the specific situation of each village has not changed compared with that of the previous period, and there is no updated information as yet, specific details are shown as follows: (1) According to Mr. Zheng, Director of Dongpo Village, Dongpo Village is planning to build 7 11-storied apartment buildings on a tract of land with a combined total of 27.34 mu, which includes the 6.65 mu village collective reserved land as obtained from the project, a 17.5 mu existing homestead and a 3.19 mu newly applied plot to be approved of. The project of 7 11- storied buildings will provide apartments for villagers who cannot afford a homestead, and will eventually benefit 400 peasant HHs once completed. Currently, the plan is still under review, and the increased land area has not yet been approved of by the government. (2) According to Mr. Liu, Director of Shenxi Village, their village committee has decided to merge together the 1.5mu reserved land and another tract of land with an area of 3.0mu② into a combined land for developing collective economy. (3) Again according to Mr. Zhong in Gucuo Village, the director of the village committee, due to the land acquisition for this project, they have already been allocated 3.51mu reserved land, plus another 20mu homestead, as allocated due to the land acquisition for a highway construction project and a power reconstruction project, currently they have a total of 23.51mu homestead③, on which apartment buildings are to be used for villagers. Since the existing 23.51 mu homestead has been divided into two tracts of land by the overhead high-voltage wire, and after the overhead high-voltage wire is relocated, the nature of the land below is still agricultural land. Therefore it is necessary to apply to change the nature of the land. In 2018, the village has applied for a new tract of 34.5 mu land (including 6 mu land below the existing overhead high-voltage wire and another tract of 28.5 mu land) so as to form a stretch of homestead with a combined total of 58 mu by joining together the existing 23.51 mu homestead and the newly applied 34.5 mu homestead, which will be used for building the apartment buildings in a unified way, so as to solve the housing problems for all villagers who have not been allocated the homestead. At present, the newly applied 34.5 mu homestead remains to be approved of by the district government. According to Mr Zhong, the land use application in Shantou City is being strictly controlled by the district government, and it still takes a relatively long period of time for the land use application to be approved of. Since the area of the reserved land obtained from the project for the three villages is too small to meet the demand of land planning of the village collective, each village needs to combine their existing reserved land with other reserved land so as to form a combined plot

20

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) ② Undeveloped collective land remained in the village. ③ Previous reserved land for land acquisition.

21

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

to meet their needs of unified planning. Therefore, a large proportion of the plot, as needed in the land plan being applied for by each village, does not fall within the scope of this project, and need to be applied for and obtained through other projects’ land acquisition. And the monitoring of this project cannot cover the specific schedule of other projects’ land plans. However, procedures of this project for all the 11.66 mu reserved land in the three affected villages have been fully completed, and related taxes of the reserved land (the land nature has been changed from cultivated land to homestead) have all been paid off by Chaonan Water Supply Company as per the requirements in the RP through the Land and Resources Bureau.

Table 2-4:Land Use Plan for Reserved Lands

Reserved Land area Total area under Land Used Project Address (Mu) application / approval Land Status Use Plan (mu) Dongbo Newly-built Longxi Village 6.65 27.34 House Site Farmer's Water Plan Committee, Apartment Longtian Town Gucuo Village Expanded Qiufeng Committee, 3.51 58 House Site Farmer's Water Plant Liangying Apartment Town Shenxi Village Renovated Jinxi Committee, 1.5 4.5 House Site Collective Water Plan Xiancheng Town Economic Entity Collective 89.84 House Site Total 3 village committees 11.66 Economic Entity

2.5 Conclusion of Permanent Land Acquisition and Resettlement

Through interviews and workshops with related agencies during site visits, and literature reviews on the relative documents such as compensation policies and agreements, financial records, social security records, etc., external M&E experts have drawn the conclusion that: by the end of December 2019, the permanent land acquisition and resettlement work in this project have all been completed in compliance with the requirements of the RP; the land compensation is implemented in accordance with the principles and standards in the RP, and the payment procedures is open, transparent, and effective; all compensation payments have been paid to the affected villages and related individuals in full amount and in time. There is no complaint and compensation claim about land acquisition and resettlement; and the progress of land acquisition and resettlement can meet the requirements of the construction. The monitoring results of this period indicate that the list of endowment insurance personnel in Gucuo village has also been submitted to the Social Security Bureau, and then the Social Security Bureau have started to pay for the villagers who meet the insurance claim conditions; all the procedures and payments of endowment insurance as land acquisition compensation in the three affected villages have been completed in accordance with the requirements of the resettlement plan.The transfer application

22

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) procedures and payment of various taxes and fees required for the development and construction of the reserved land have also been handled by the Chaonan project office. However, area of land reserved for the three villages in this project is too small to make any plan, , so the specific completion time for the land’s plan, design or establishment cannot be determined only by the reserved areas from this project by far. 2.6 Temporary Land Occupation According to the preliminary design of the construction drawing, the project is estimated to have a total of 4239.76 mu of temporary land. A total of 1020.25 mu of land has been temporarily acquired in this period. As of this period, the total amount of temporary land acquisition for the project is accumulatively 3431.88 mu. Among all the contract packages under construction, no temporary land occupation is involved in the contract C1 and C8 of the exhibition hall and water plant under construction in this phase, while the pipeline engineering C7, C11, C12, C13, C14 and C15 involve temporary land acquisition. The details of the temporary land acquisition of the project are shown in the table below.

Table 2-5: Temporary Land Use of the Project - Comparison with design and real construction(C7)

C7(Pipeline engineering of Liangying town and Xiancheng town)

Water Temporary Item Unit Each Temporary Waste transmission soil Subtotal construction construction disposal and storage area road area distribution yard pipeline 1.Temporary mu 331.81 7.50 4.20 320.11 land use (1)Cultivated mu 0.00 land ①paddy field mu 0.00 ②dry land mu 0.00 (2)garden plot mu 0.00 ①orchard mu 0.00 (3)Forest land mu 0.00 ①woodland mu 0.00 (4)Industrial and mining mu 11.70 7.50 4.20 storage land ①Industrial mu 11.70 7.50 4.20 land (5)Land for mu 320.11 320.11 transportation ①Road land mu 320.11 320.11 ②Rural road mu 0.00 land 2.Total floor area of water 381.76 transmission

23

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) and distribution pipeline of contract pipeline (MU) 3.Completion 87% proportion 4. temporary land area in 458.68 7.50 91.20 359.99 development design 5.Temporary land area in 381.76 7.50 4.20 370.06 construction drawing

24

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-6: Temporary land use of the project - comparison table of design and construction area(C11)

C11(Pipeline engineering in Lugang town)

Water Item Unit Temporary Each Temporary Waste transmission soil Subtotal construction construction disposal and storage area road area distribution yard pipeline 1.Temporary mu 301.77 4.50 2.04 295.23 land use (1)Cultivated mu 0.00 land ①paddy field mu 0.00 ②dry land mu 0.00 (2)garden plot mu 0.00 ①orchard mu 0.00 (3)Forest land mu 0.00 ①woodland mu 0.00 (4)Industrial and mining mu 6.54 4.50 2.04 storage land ①Industrial mu 6.54 4.50 2.04 land (5)Land for mu 296.23 295.23 transportation ①Road land mu 296.23 295.23 ②Rural road mu 0.00 land 2.Total floor area of water transmission and distribution 301.07 pipeline of contract pipeline (MU) 3.Completion 100% proportion 4. temporary land area in 234.64 4.50 48.60 181.54 development design 5.Temporary land area in 301.07 4.50 2.04 294.53 construction drawing

25

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-7: Temporary land use of the project - comparison table of design and construction area(C12)

C12(Xiashan Street pipeline project)

Water Item Unit Temporary Each Temporary Waste transmission soil Subtotal construction construction disposal and storage area road area distribution yard pipeline 1.Temporary mu 846.53 6.00 0.68 839.85 land use (1)Cultivated mu 0.00 land ①paddy field mu 0.00 ②dry land mu 0.00 (2)garden plot mu 0.00 ①orchard mu 0.00 (3)Forest land mu 0.00 ①woodland mu 0.00 (4)Industrial and mining mu 6.68 6.00 0.68 storage land ①Industrial mu 6.68 6.00 0.68 land (5)Land for mu 839.85 839.85 transportation ①Road land mu 839.85 839.85 ②Rural road mu 0.00 land 2.Total floor area of water transmission and distribution 2416.26 pipeline of contract pipeline (MU) 3.Completion 35% proportion 4. temporary land area in 1065.58 6.00 33.90 1025.68 development design 5.Temporary land area in 2416.26 6.00 0.68 2409.58 construction drawing

Note:The reasons for the increase of the temporary occupied land area of C12 package are as follows: 1) Pipelines with pipe diameter above DN 25 are only included in the preliminary design stage, so the total length is only 477 km. However, in the detailed construction design stage, pipelines with pipe diameter below DN 25 are also included resulting in the total length of 778

26

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) kilometers, which cause an increase of 301 kilometers, so the temporary occupied land area is increased correspondingly. 2) The ground occpation space width of the pipeline with pipe diameter below DN100 was not well designed in the preliminary design stage as its width was changed from 1.2 meters to 2.0 meters according to the construction requirements during the construction design. And the temporary occupied land area has to be also increased because of this.

27

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-8: Temporary land use of the project - comparison table of design and construction area(C13)

C13(Pipeline engineering of Chendian town and simapu town)

Water Item Unit Temporary Each Temporary Waste transmission soil Subtotal construction construction disposal and storage area road area distribution yard pipeline 1.Temporary mu 244.67 3.00 3.13 238.54 land use (1)Cultivated mu 0.00 land ①paddy field mu 0.00 ②dry land mu 0.00 (2)garden plot mu 0.00 ①orchard mu 0.00 (3)Forest land mu 0.00 ①woodland mu 0.00 (4)Industrial and mining mu 6.13 3.00 3.13 storage land ①Industrial mu 6.13 3.00 3.13 land (5)Land for mu 238.54 238.54 transportation ①Road land mu 238.54 238.54 ②Rural road mu 0.00 land 2.Total floor area of water transmission and distribution 414.27 pipeline of contract pipeline (MU) 3.Completion 59% proportion 4. temporary land area in 482.00 4.50 91.48 386.02 development design 5.Temporary land area in 414.27 3.00 3.13 408.14 construction drawing

28

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-9: Temporary land use of the project - comparison table of design and construction area(C14)

C14(Xia Xin Si Gao and he Yang pipeline project)

Water Item Unit Temporary Each Temporary Waste transmission soil Subtotal construction construction disposal and storage area road area distribution yard pipeline 1.Temporary mu 104.34 4.05 1.73 98.56 land use (1)Cultivated mu 1.63 1.63 land ①paddy field mu 1.63 1.63 ②dry land mu 0.00 (2)garden plot mu 0.00 ①orchard mu 0.00 (3)Forest land mu 0.00 ①woodland mu 0.00 (4)Industrial and mining mu 5.78 4.05 1.73 storage land ①Industrial mu 5.78 4.05 1.73 land (5)Land for mu 96.93 96.93 transportation ①Road land mu 96.93 96.93 ②Rural road mu 0.00 land 2.Total floor area of water transmission and distribution 132.83 pipeline of contract pipeline (MU) 3.Completion 79% proportion 4. temporary land area in 342.50 4.05 50.69 287.76 development design 5.Temporary land area in 132.83 4.05 1.73 127.05 construction drawing

29

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 2-10: Temporary land use of the project - comparison table of design and construction area(C15)

C15(Shanhe line and Donglan pipeline project)-basically completed

Water Item Unit Temporary Each Temporary Waste transmission soil Subtotal construction construction disposal and storage area road area distribution yard pipeline 1.Temporary mu 37.67 2.40 1.11 34.16 land use (1)Cultivated mu 4.78 4.78 land ①paddy field mu 4.78 4.78 ②dry land mu 0.00 (2)garden plot mu 0.00 ①orchard mu 0.00 (3)Forest land mu 0.00 ①woodland mu 0.00 (4)Industrial and mining mu 3.51 2.40 1.11 storage land ①Industrial mu 3.51 2.40 1.11 land (5)Land for mu 29.38 29.38 transportation ①Road land mu 29.38 29.38 ②Rural road mu 0.00 land 2.Total floor area of water transmission and distribution 37.67 pipeline of contract pipeline (MU) 3.Completion 100% proportion 4. temporary land area in 55.96 2.40 17.85 35.71 development design 5.Temporary land area in 37.67 2.40 1.11 34.16 construction drawing

30

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

III. Social Development and Gender Action Plan Implementation

As of the first half of 2020, with the project proceeding, PMO has gradually initiated Social Development Action Plan (SDAP) and Gender Action Plan (GAP) to ensure social safeguards during project implementation. The subprojects related to land acquisition include: (1) The temporary occupation of 802.83 mu of state-owned land (i.e. 112932m roadside green belt) is used for the installation of all main water transmission and distribution pipelines or waste disposal sites along the existing roads; (2) the temporary occupation of 1468.33 mu of collective land is used for temporary stacking of earthwork and other water distribution pipeline construction projects in three water plants. In addition, 483400 square meters of waste disposal site has been temporarily requisitioned, which is located in the textile industry circular economy industrial park of Longtian town (the open and low-lying land between the mine field highway and the Shantou Expressway)..

Social Impact. This project has brought positive social effect and impact to the local society, especially to direct beneficiaries, including local workers, public consultation participators (mainly students and women), low-income groups, project management personnel etc., in the following respects: 1) Employment in project construction stage: As of 1st half of 2020, there are totally 5206 persons newly employed by the project, among which: (1) 965 workers from low-income families, accounting for 17.8% of all employees; (2) 1,501 females, accounting for 28.83% of all employees; (3) 3,291 local residents have been employed to work for this project, accounting for 63.22% of all employees; 2) Employment in project operation stage: As of 1st half of 2020, (1) 30 workers are working as for forest nursery and replantation in conservation forestation subproject of output 1, among which 10 are females (33%); (2) 45 staffs are now working in Longxing WSC of output 2, among which 16 are females (36%); 3) Public participation in activities on environment protection, water supply and water safetl, traffic safety, etc.: (1) the project has well stimulated development of environment protection awareness in students of primary and middle schools. As of 1st half of 2020, 300 schools (including primary and middle schools) have conducted regular education programs and activities about environment protection, water conservation, and water resource protection, with around 240 thousand student participants; (2) 88 thousand female residents have participated in public awareness building activities in communities and schools on environment protection and sanitation management, accounting for 80% of all participants; (3) around 20 thousand local residents of Chaonan District have participated in the public consultation and programs related traffic safety, with 10 thousand (50%) females; 4) Capacity building: As of 1st half of 2020, (1) 3,951 employees of contractors have been trained during the project construction stage, with 1132 females (28.65%); (2) 246 administrative personnel from PMO, IAs, and related government personnel have participated in the training and workshops related project management, SAP and GAP implementation, and leadership capacity building, with 78 females (32%); 5) Local material utilization: In order to stimulate the local economy, the project has make efforts to utilize local construction materials as much as possible. As of 1st half of 2020, all

31

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) the local materials used for construction have been added up to about RMB 170 million; 6) Public hearing: In 2019, public hearing has been conducted in Chaonan in compliance with the government stipulated procedures for the water tariff adjustment. As per requirement on social inclusiveness and gender equality of SAP and GAP, among the 32 representative participants of the hearing, 10 persons are female (31%), 7 persons are poor group representatives (22%).

3.1 Employment Status of Contractors

3.1.1 the situation of construction work

In the first half of 2020, there are 7 construction projects under construction, and the construction tasks are undertaken by 6 contractors, as follows: 1) The contractor of the construction project of Exhibition hall for water resource protection and bulletin boards (C1) is Gansu Yian Construction Technology Group Co., Ltd. (hereinafter referred to as Gansu Yian); 2) The contractor of Water distribution pipelines in townships of Liangying and Xiancheng (C7) is Taitong Construction Group Co., Ltd; 3) The contractor of expansion of Qiufeng water plant and reconstruction of Jinxi water plant (C8/G4) is the joint venture of Guangdong No.2 Construction Engineering Co., Ltd. and Huizhou Hydropower Construction Engineering Co., Ltd., but Guangdong No.2 construction is the main contractor (hereinafter referred to as Guangdong No.2 construction); 4) the contractor of Distribution pipelines in Lugang township (C11) is Guangdong Dayu Water Conservancy Construction Co., Ltd. (hereinafter referred to as Guangdong Dayu); 5) The contractor of Distribution pipelines in Xiashan (C12) is Shantou Sanling Municipal Construction Co., Ltd. (hereinafter referred to as Sanling); 6) The contractor of Distribution pipelines in Chendian township and Si Mapu township (C13) is Shantou Sanling Municipal Construction Co., Ltd. (hereinafter referred to as Sanling); 7) Guangdong Dayu Water Conservancy Construction Co., Ltd. (hereinafter referred to as Guangdong Dayu) is the contractor of Civil works, installation, and commissioning of water transmission pipeline for He-Yang, Si-gao, and Xia-Xin sections(C14/G5);

In the above projects, according to the requirements for measures proposed in gender and social security sections in the project management manual, all construction units have implemented relevant actions in accordance with the social development action plan and gender action plan. See Appendix 1 for details of employment.

3.1.2 Employment status among construction work

The project has created 382 direct employment opportunities in the first half of 2020, including 18.32% for women, 12.57% for labors from low-income families and 62.57% for local people. The details are as follows:

1) Details of employment 32

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) According to the statistical data regularly collected by the contractors in the first half of 2020, the employment in this period is as follows:

Table 3-1: Employment of Construction Project of Exhibition Hall for Water Resource Protection and Bulletin Boards - The First Half of 2020

Contractor: Gansu Yian Construction Technology Group Co., Ltd Contract Code: C1 Category Item Unit QTY % Male (person) 10 90.91% Gender

Non Female (person) 1 9.09%

- technical Labor technical Minority (person) 0 / Nationality Han Majority (person) 11 100%

Low income labor (person) 20 0% Poor

General labor (person) 11 100% Local labor (person) 7 63.64% Citizen Non-local labor (person) 4 36.36%

Table 3-2: Employment of Water Distribution Pipelines in Townships of Liangying and Xiancheng - The First Half of 2020

Contractor: Taitong Construction Group Co., Ltd Contract Code: C7 Category Item Unit QTY % Male (person) 34 80.95% Gender ( ) Non Female person 8 19.05%

-

technical Labor technical Minority (person) 0 0%

Nationality Han Majority (person) 42 /

Low income labor (person) 0 0%

Poor Non-poor labor (person) 42 100% Local labor (person) 14 33.33% Citizen Non-local labor (person) 28 66.67%

Table 3-3:Employment of Qiufeng water plant and reconstruction of Jinxi water plant - The First Half of 2020

Contractor: Guangdong No.2 Construction Engineering Co., Ltd. and Huizhou Hydropower Construction Engineering Co., Ltd Contract Code: C8/G4

33

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Category Item Unit QTY %

Male (person) 72 97.30% Gender

Non Female (person) 2 2.7%

- technical Labor technical Minority (person) 10 13.51% Nationality

Han Majority (person) 64 86.49%

Low income labor (person) 19 25.68% Poor Non-poor labor (person) 55 74.32%

Local labor (person) 44 59.46% Citizen Non-local labor (person) 30 40.54%

34

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

Table 3-4: Employment of Distribution Pipelines in Lugang Township - The First Half of 2020

Contractor: Guangdong Dayu Water Conservancy Construction Co., Ltd Contract Code: C11 Category Item Unit QTY % Male (person) 64 84.21% Gender ( ) Non Female person 12 15.79%

-

technical Labor technical Minority (person) 0 /

Nationality Han Majority (person) 76 /

Low income labor (person) 0 0%

Poor Non-poor labor (person) 76 100% Local labor (person) 54 71.05% Citizen Non-local labor (person) 22 28.95%

Table 3-5: Employment of Distribution Pipelines in Xiashan - The First Half of 2020

Contractor: Shantou Sanling Municipal Construction Co., Ltd Contract Code: C12 Category Item Unit QTY % Male (person) 79 73.83% Gender Female ( ) Non person 28 26.17%

-

technical Labor technical Minority (person) 7 /

Nationality Han Majority (person) 100 /

Low income labor (person) 13 12.15%

Poor Non-poor labor (person) 94 87.85% Local labor (person) 72 67.29% Citizen Non-local labor (person) 35 32.71%

35

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

Table 3-6: Employment of Distribution Pipelines in Chendian Township and Si Mapu Township -The First Half of 2020

Contractor: Shantou Sanling Municipal Construction Co., Ltd Contract Code: C13 Category Item Unit QTY % Male (person) 30 76.92% Gender Female (person) 9 23.08%

Non

- ( ) technical Labor technical Minority person 0 /

Nationality Han Majority (person) 39 /

Low income labor (person) 10 25.64%

Poor Non-poor labor (person) 29 74.36% Local labor (person) 26 66.67% Citizen Non-local labor (person) 13 33.33% Table 3-7: Employment of Civil Works, Installation, and Commissioning of Water Transmission Pipeline for He-Yang, Si-gao, and Xia-Xin Sections - The First Half of 2020

Contractor: Guangdong Dayu Water Conservancy Construction Co., Ltd Contract Code: C14/G5 Category Item Unit QTY % Male (person) 23 69.7% Gender Female (person) Non 10 30.3%

-

te Minority (person) 0 /

chnical Labor chnical Nationality Han Majority (person) 33 /

Low income labor (person) 6 18.18%

Poor Non-poor labor (person) 27 81.82% Local labor (person) 22 66.67% Citizen Non-local labor (person) 11 33.33%

36

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) 2) Summary and Analysis on Employment in This Report Period

The project created 382 new jobs in the first half of 2020. Compared with the previous period, the total number of employment showed a downward trend. Female employment decreased by 8.06%, the proportion of poor employment decreased by 1.07%, and the proportion of local employment decreased by 2.34%. According to the requirements of the social and gender action plan, the corresponding targets were not met in the current period. The labor situation of each project in this period is summarized as follows:

37

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) Table 3-8: Summary of Project Employment - The First Half of 2020

Summary of Project Employment Contract Code: C1, C7,( C8、 G4) ,C11,C12, C13, (C14、G5) Category Item Unit QTY % Male (person) 312 81.68% Gender Female (person) Non 70 18.32%

-

technical Labor technical Minority (person) 17 4.45%

Nationality Han Majority (person) 365 95.55%

Low income labor (person) 48 12.57%

Poor Non-poor labor (person) 334 87.43% Local labor (person) 239 62.57% Citizen Non-local labor (person) 143 37.43% In summary, In the first half of 2020, the employment indicators of the project in social and gender action are as follows:

(1) Female employment: a total of 70 female employees were recruited, accounting for 18.32% of the current employment, 8.62% lower if compared with 26.94% of the previous period, and the current period did not reach the target value of 30% in the gender action plan. Among them, the associated contractor of Guangdong Erjian and Huizhou Shuidian have the lowest proportion of female employment in C8 contract package of Jinxi water plant expansion project, which is only 7.8%. The proportion of female employment decreased in this period mainly because of the impact of the COVID-19 in the first half of this year, for which most of the schools in China have not openedl, and then many women who originally worked as migrants had to stay at home to take care of their children. ;

(2) Local employees: there are 239 in total, accounting for 62.57% of the current employment, with 3.09% decrease compared with 65.66% of the previous period, and the overall proportion has reached 65% as the requirements of the SDAP; The main reason for the substandard employment situation in this period is also the outbreak of the COVID-19, and the number of local laborspreferred not to going out as that in previous years.

(3) Employment of low-income families: there are 48 people from low-income families in this period,3accounting for 12.57% of the total employees, a little bit decease compared with the previous period of 13.64%. The main reason for the low completion rate of this indicator in this period is that the employment of low-income workers in Guangdong Erjian and Taitong construction is 0% in this period but other all contractors has reached the requirement of 15% in the SDAP;

3 Because the Chinese government is committed to relieve poverty by 2020, and has taken a series of effective measures and actions, the number of low-income families and poverty-stricken familieshina has decreased dramatically, most of whom are those who have lost their ability to work. In view of this, the project will include labors from families with the lowest 20% income level into the low-income families. 38

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) (4) Monthly average wage of male and female employees: All contractors achieved equal pay for equal work in this period. From the statements provided by the contractor, the average wage of female workers is averagely 500 yuan / month less than that of men, but the average wages of men and women in Gansu Yi'an construction (C1) contract are the same with each other..According to the results of the field survey, women employees are mainly engaged in carpentry, bricklayers, auxiliary workers, medium-level labors, greening, logistics and cleaning, many of which are seasonal temporary jobs, while the front-line jobs are mainly for male. The difference in the nature of work results in different wage levels, but the same type of work achieves equal pay for equal work. This kind of heavy labor position usually pays higher wages, which leads to the gap between the average wage level of men and women in the current period ; Employment in the operation stage: 1) Longxi Water Plant: in the operation stage, 45 direct employment opportunities have been created in Longxi Water Plant, including 16 women (all managerial and skill positions) , accounting for 35% of the employed population. This period meets the target set in the gender action plan 2) Forest maintenance labors for Output 1: There are totally 30 new labors employed for operation stage of forestation, among which 10 are females, but no females for managerial and skill positions. So this has only reached the target of female employment rate (30%), but not reached the target of managerial and skill positions among females (50%).Due to the COVID-19, the employment indicators in the first half of 2020 are not very satisfactory. The proportion of female employees is 8.94% lower than that of last year, the proportion of local employees is 4.43% lower than that of last year, and the proportion of low-income family employees is 1.07% lower than that of last year. These indicators do not meet the requirements of the social and gender action plan. It is expected that in the second half of the year, the overall number of employees and the proportion of women, local employees and poor groups will be increased due to the alleviation of the epidemic situation. The PMO still needs to strengthen the supervision on the situation of the Contractor's employment in the construction stage of the project, especially the employment of women and low-income family workers, so as to expand the employment channels and give priority to the employment of women and workers from low-income families.

39

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) 3.2 Training

1) Conduct Training for PMO and PIU Since the project management consulting firm (HJI) was mobilized into the construction site in July 2016, the social and gender development specialists have provided trainings on social safeguard, social and gender actions for contractors, IAs and relevant agencies and stakeholders to enhance awareness of social and gender development and concern for vulnerable groups, and better protect the interests of women, local residents and vulnerable groups. As of this period, no training has been conducted due to the COVID-19. 2) Training carried out by the Contractor: In the first half of 2020, contractors conducted 12 on-the-job trainings for the employees of the project under construction, including health and disease prevention and control, labor law, safety, and skills, as follows:

Table 3-9:Training Status in the 1st Half of 2020

QTY of QTY of QTY of Proportion of Proportion of Contractor Female Trainings Trainees Females Females Trainees Trainees

GYYA 1 11 1 9.09% 100%

TTJT 2 42 8 19.05% 100%

GDEJ 2 60 2 7.8% 100%

GDDY 3 105 20 19.05% 91%

STSL 4 129 26 20.15% 70.27%

Total: 12 347 57 16.43% 81.43%

Figure 3-1: COVID-19 prevention training - Gansu Yi’an Construction Technology Group Co., Ltd. - first half year of 2020

40

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

Figure 3-2: Internal training on labor law and safety - Taitong Construction Group Co., Ltd. - the first half of 2020

41

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC)

3.3 Public Consultation

In the process of permanent land acquisition, the PMO has actively conducted various kinds of publicity campaigns on various issues concerned with the project. All agencies involved have been making concerted efforts and cooperating with each other in showing concern for all stakeholder groups of the society, especially the vulnerable groups. Assemblies of villagers’ representatives have been convened by the PMO at village committees of affected villages, and various policies relating to permanent land acquisition have been fully explained and publicized. Moreover, more and more females have been prompted and encouraged to participate as per relevant requirements of the ADB. Participating females usually account for averagely about 25%. The project of water supply pipeline network connecting all villages involves the village pipelines, alley-way pipelines and household pipelines and temporary land use in all villages, communities and sub-districts along the pipeline routes. The PMO has not only conducted extensive publicity campaigns as per the corresponding measures and requirements in the RP、SAP and the GAP; but also fully listened to and respected various opinions from all stakeholder groups. Before the finalization of working drawings for each pipeline section and the commencement of construction, public consultation and public option have been conducted for the affected communities, sub-districts, village committees and other relevant agencies in written form, through public notice or informal discussion, consequently being widely understood, supported and advocated by residents and villagers along the pipeline routes. During the reporting period, the construction sections, all along the municipal roads under the jurisdiction of the Highway Bureau, have not affected the villages, communities or streets alongside. The client (Chaonan water supply company) has asked officially for opinions from all relevant departments, streets and communities along the line before construction, and appealed the construction information as required in complaint and appeal mechanism. No complaints have been received so far during the construction of the project by far. As of this report, public consultations have been conducted for all the projects that have been constructed before the commencement of the construction, and there is no new construction started in this period.

3.4 Other Actions

Apart from the above, some other activities conducted as per the framework of the SAP and the GAP are as follows; (1) Utility of local materials: local materials are widely used in the construction, including the cement, earth, gravels, aggregate chips, steel bars, etc., which have brought good economic benefits to Chaonan District. By the end of June 2020, the value of local building materials used for the project has added up to CNY 168.56 million, among which a cumulative amount of about CNY 12.62 million is used in this monitoring period;

42

M&E on Resettlement, Social and Gender Development (3114-PRC) (3114)PRC) (2) Trainings in safety awareness of both traffic and construction have been conducted, and the safety of construction labors has been guaranteed; (3) Bulletin boards respectively of safety instructions, civilized construction, etc. have been established on the construction sites, and the roads have been recovered timely during construction to guarantee the travel safety of residents from communities nearby. No safety accidents have occurred since the construction started.

Figure 3-8: Safety training for civil engineering and installation of main pipeline works of Xiaxin line, Sicheng high speed railway and Heyang line

Figure 3-9: Safety training of pipeline construction in Liangying town and Xiancheng town

43

M&E on Resettlement, Social and Gender Development (3114- PRC)

IV. Findings and Suggestions

4.1 Findings

(1) Implementation of the action plan proposed by external monitoring experts

In the previous 10 reports, experts put forward some positive suggestions and measures to help better implement the resettlement action plan (RAP for short). The implementation of the proposed resettlement action plan by the end of June 2020 has been shown in Table 4-1.

Table 4-1: Follow-up of the Implementation of Resettlement Action Plan (RAP)

Responsible Progress/ No. Task Objective Follow-up Department Deadline

Implementation of the resettlement plan 1

Under active implementation. The detailed survey of

temporarily occupied land

will be carried out upon

completion of the detailed design of water supply 2271.16 mu land pipeline routes. The (Used as the storage yard for storage yard for construction waste residue Chaonan Water pipelines, covers an area of 1400 m2. Temporarily Supply construction The land acquisition has occupied Company, materials, been approved of by the 1.1 land and Chaonan June 2020 construction waste local government through pipeline District residue, etc. and the Economic & Industrial routes Government, the work yard for Park Project of Chaonan Design Institute building temporary District. Therefore the plot construction roads, can be directly used in this etc.) projectwith no land acquisition required.

Relevant Chaonan Water formalities Supply Completed 1.2 Same as the above December for approval Company, 2019 of temporary Chaonan

34

M&E on Resettlement, Social and Gender Development (3114- PRC)

Responsible Progress/ No. Task Objective Follow-up Department Deadline

land District occupation Government, Design Institute 2 Adopt friendly resettlement compensation measures

Keeping tracking of compensatio Chaonan Water n for land Supply acquisition Company, Compensation has already and Chaonan been paid. The living and economy 2 affected District Being production conditions of 2.1 restoration households Government, followed up local residents keep of 2 Village normal, with no decline in affected committee of living standards. households Dongbo Village in Dongbo Longtian Town Village Longtian Town

3 Strengthen the institutional capacity, improve the system of documentation control Chaonan Related District PMO, training in IAs responsible

land for temporary By the end acquisition Information land Under active 3.1 of June and building communication acquisition, implementation 2020 the each village institutional committee and capacity neighborhood committee, etc.

The documentation system

is divided into three parts,

which are all in the charge Documentati Establishment of of the focal person as on control on Chaonan Water By the end the land acquisition assigned by the PMO. The 3.2 resettlement Supply of June documentation specialists have provided and land Company 2020 system relevant suggestions for acquisition the local document control staff through a variety of workshops and meetings..

(2) Continuously implement the social development plan and the gender action plan, and promote social inclusiveness and gender equality.

In the implementation of the project, the project actively provides employment opportunities 35

M&E on Resettlement, Social and Gender Development (3114- PRC) for local residents, women, local personnel and the poor. As of the first half of 2020, 5,206 labors were employed with 1,501 women and 925 poor labors. The completion rate of employment-rate has declined compared with the previous period due to the impact of COVID-19, and the proportion in women and low-income workers have not reached the required target. The project has provided equal opportunity for women in employment, training and public participation. However, up to June 2020, the targets of SDAP and GAP have not reached in female employment and participation. Chaonan PMO has attached great importance to the SDAP & the GAP during the project implementation and has attached the SDAP and the GAP as official appendices as well as integral parts of the contract. The PMO has assigned a focal staff to be responsible for the implementation of the SDAP and the GAP, and one female staff to be in charge of the gender-related affairs. Moreover, during this M&E period, PMO has actively provided trainings in gender and social development for contractors, and integrated the social security requirements with the construction works so as to urge contractors to make great progress during this M&E period in terms of both awareness and action. (3) In general, SAP and GAP have been well implemented, however, there are still actions not to be started yet as details set out below: • Leadership capacity development: Workshops on social inclusion and equitable access to the new economic achievements (particularly for the poor and farmers in the transitional period), and workshops on urban expansion and employment (labor opportunities for the poor and rural areas) have not been conducted so far. PMO has scheduled to develop the action plan to conduct at least one workshop by end of the project. Detailed plan will be presented in the next report for 2nd half of 2020; • Project outcome for women’s benefit in water supply: It is indicated in GAP that workload on women will be reduced as a result of the improved and equitable water supply service, in particular for rural females. But since the pipeline construction in rural areas has not been completed yet, the rural households cannot have tap water supply connected until end of 2020. PMO has scheduled to collect data and make analysis for this indicator in the 2nd half of 2021. • Evaluation of the quality of water supply service: This task has not been conducted yet by far, but has been scheduled by PMO to develop the survey plan with questionnaire by end of 2020, and then the survey and evaluation will be conducted upon the completion of the pipeline completion. More details are to be presented in the next report. • Managerial and skill positions for females in water conservation subproject (output 1): The construction of this subproject has been completed by end of 2019. In 1st half of 2020, there are 30 workers serving for forest nursery and replant with 10 females, but there are no females working for managerial and skill positions. PMO has urged forestation bureau to enhance the gender awareness, and provide more managerial and skill job opportunities.

36

M&E on Resettlement, Social and Gender Development (3114- PRC)

4.2 Suggestions

(1) Taking measures and enhance social development plan to achieve targeted indicators in the SAP and GAP

In this report phase, the completion proportion in employment has all declined, especially the employment in women and low-income. 1) Female employment. According to the requirements of the GAP, women's employment account for 30% of the total , and 50% of the positions women taken should be managerial and/or skill positions. But by the end of June 2020, the status of women's employment : (i) total female employees in construction phase only accounts for 28.83% of the total, and that in Output 2 only accounts for 25.36% of the total; (ii) women who have taken managerial and skill jobs only accounts for 10.03% of all women employees, not reaching the target of 50%; (iii) Females participating in contractors' trainings only occupies 28.65% of the total trainees, while female participants in institutional capacity strengthen trainings only accounts for 32%,both not meet the target (40%) required by the gender action plan.

Although the employment status has been greatly impacted by COVID-19, but the consist failure in the required target of female employment and training reflected the necessity to enhance the capability building on social inclusiveness and gender sensitiveness of IAs and contractors. . 2) Low-income employees. The employment proportion of low-income labors has accumulatively added up to17.77%, reaching the target of 15% from SDAP, but only 12.57% in this period, 2.43% lower than the target required in the social action plan. The main reason is that Gansu Yian construction, Taitong construction and Guangzhou Dayu have no labors employed from low-income households, even though all the other contractors have reached the target in this period. In view of the above problems, experts suggest that: as of this period, the implementation of the social and gender action plan of the project is basically good, except women's employment and participation in trainings. Therefore, we should continue to vigorously promote positive action measures in the implementation before the completion of the project to improve gender equality. In the case of the alleviation of the new coronavirus epidemic situation, we should make more efforts to increase the job opportunities for local residents, low-income residents and women, expand the channels of employment information transmission and training by all means including network and smart phones, and improve the quality of jobs provided to women for more skill and management positions, and continue to improve women's participation in training and public consultations. PMO needs to continue to actively promote and coordinate the implementation of social and gender actions as always before project completion, strengthen the training on gender sensitivity, social development action plan and implementation of gender action plan of all implementing units, and monitor the implementation of SDAP and GAP in a timely manner.

37

M&E on Resettlement, Social and Gender Development (3114- PRC)

Appendix 1: SDAP and implementation monitoring status of monitoring framework

Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source A. ENHANCEMENT MEASURES (Responsibilities of the Implementing and Operating Agencies) • 3291 local workers were employed (63.22% of the total number of workers); • No. of local 655 full-time 1. Employment Priority to Local people employed • 1501 female employees, positions People During Project Implementation Estimated total (disaggregated by 28.83% of the total; during project • Priority to local labor, women PMO,IAs, CB, CNY17.1mill sex, skilled and/or • 1649 skilled workers; construction unskilled, and and poor labors Contractors, Ionis include d • The average wage of local ➢ 65% local local town ship 2014–2019 in project civil poverty status) • Use of local construction workers is RMB 3935.67/ month; the labor in civil work governments, works cost and materials, e.g., rock, gravels, clay, • Wages(disagree average wage of women is CAB paid by cement ➢ 30% women gated by sex) paid to RMB3759.89/ month; for labor in contractors local people • As required in bidding landscaping and • 925 unskilled workers from poor • Value of documents, local labors shall be civil work families ; construction preferentially hired and local qualified • The total value of construction ➢ 15% poor for materials supplied materials shall be preferentially used materials provided locally is by contractors, unskilled labor in locally landscaping and ¥ 168.5629 million; • Training shall be provided for all civil work • Training of local workers in labor law, HSE, sanitation, • 3951 people were trained in the ➢ 100% workers workers skills, etc. by contractors labor force accounting for 75.89% of get training (disaggregated by total employments, including 1132 sex) women (28.65% of the total number of trainees, 75.42% of the total number of female workers). 269 full-time 2. Employment Priority to Local positions • No. of local People During Project Operation Estimated during project PMO, IAs, people employed • Priority to local labor in NY0.565 Million • In the operation stage of Longxi operation local Town (disaggregated by (i)conservation of forests, solid waste annually is Water Plant, 45 staffs in total with 16 ➢ 30% women governments, 2015–2019 sex, skilled and/or management, and water supply plant included in women, accounting for 36%; for labor in(i) labor bureau, and onwards unskilled, and operation and maintenance; (ii)operation project • Other subprojects to be and CAB CDG 2020 poverty status) of exhibition building; and ➢ 50% women operation cost monitored during project operation and CWSC (iii)environmental protection awareness for labor in (ii) and paid by the Wages (disaggregated by gender) paid to local Training all workers in labor law, safety, ➢ 60% women IAs sanitation, and skills to be provided by the for labor in (iii) 15% people

45

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source IAs poor for labor in(i) • raining of local • About 44 workers, who will be laid workers (disaggregate off due to closure of the three water ➢ 100% workers ed by gender) treatment plants—Chengtian, Jindu, and get training Tianxin, will be absorbed into the • No. of the workforce necessary for operating the ➢ 44 workers retrenched workforce project facilities. from the three being re-employed WWTPs

B. MITIGATIONMEASURES (Responsibility of the PMO and IAs)

3. Practices protecting local communities from construction disturbances and ensuring safety in • No. and construction resolution of • Complaint: None; complaints • Public facility rehabilitation: road • Prohibit nighttime construction (disaggregated by has been rehabilitated fort 920.42 km in and adhere to proposed noise IAs, Included in ➢ 100% residents sex) construction; standards and students around contractors, project 2014–2019 • Number of public • Accident on temporary construction • Reconstruct and restore the public project sites are and local cost(refer to facilities(% recovery) road: None; facility systems, such as road, poles and aware of or alerted governments EMP) transformers during pipe installation to the construction • Accidents on  roads laying pipes • Enhance construction safety, • Accidents on project site • Accident in project construction site: be included in the bidding documents ➢ 100% project Costs of the • No. of manuals, IAs, 2014–2019 • Local CDPC will provide training to construction publicization posters, and picture None; Number of brochures and posters contractors, and training albums distributed No. distributed: 3862 HSE managers on the construction site workers local CDPCs, activities for of training sessions • There were 36 training meetings, 2089 ➢ 100% service and local • HSE manager will provide training to all workers are and trainees in total, 723of whom were workers, managers and vendors and 100% governments included in communities within trainees(disaggregate women, accounting for 34.64% of the subcontractors contract costs. ed by gender) total participants; • HIV/AIDS and STI counseling the project area Local CDPCs • No. of tests and program and voluntary testing by health costs are HIV/AIDS/STI cases agencies for workers included in (disaggregated by local health • Provide manuals, posters, and gender) picture albums Bureau’s 46

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source budget

• C. ENHANCEMENTMEASURES (Responsibility of Participating Local Governments) Local 2015–2019 • No. of schools • Environment protection education, government • No. of outdoor activities; symposiums, etc. 5. Practices and education 232 primary and 63 budget about Strengthening public middle participants have been conducted on a regular basis environmental protection (disaggregated by at all primary and middle schools in schools (2012), awareness gender) Chaonan District as per the textbook Public environmental protection and 900, 000 (including primary school exhibitions, etc.) project area HB, IAs, and middle school),, with a total of 300 ➢ 100% primary schools participated; Education about public health and local town schools and middle • Students in Chaonan District management in residential schools in DPA governments communities of DPA (posters, picture involved in the publicization and ➢ 70% local education activities, such as blackboard exhibitions, etc.) residents-35% news, billboards, wired radio education, Establish a solid waste ➢ 50% female morning dissemination during flag raising management system to be participants-80% ceremony, which covered the students managed by local villagers in aged between 6 and 18, in the total Chengpo village and Quifeng number of 236,766, including 114,515 village female students, accounting for 48.37% of the total number. • In the first half of 2020, due to the outbreak of COVID-19, no new activities were conducted.

47

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source 6. Government subsidies for Local Local 2018 water tariff and solid waste treatment government, government • No. of total HHs • Monitoring will be done at the end of tariff ➢ 100% poor EAs budget onwards in villages, No. of 2020 • Provide subsidy about solid and low income HHs with subsidies, waste HHs in Chengpo average subsidies treatment tariff for poor and and Qiufeng per HH villages low-income HHs in Chengpo and • No. of total poor Qiufeng villages ➢ 100 % poor and low income HHs • Provide household connection to and low-income in the plain area the water supply system for poor and households in the connected to the low-income households in the plain DPA district’s water supply area with high-fluorine water system

Local • Chapter 2, “Protect the Source of government • No. of schools Life “in the textbooks participants (in primary school and middle school), is • School workshops on public schools (2012), (disaggregated by used to provide comprehensive and prevention of endemic fluorosis and 900, 000 gender) fundamental education for students. (lectures or picture exhibitions, etc.) residents in direct Various ways of education will be • Education about safe drinking project areas; Local EB, EPB, HB, adopted, such as picture exhibitions and water in residential communities of ➢ 100% primary extracurricular activities on protection of DPA (posters, picture exhibitions, and middle IAs, and local • No. of community water resource, including the water in etc.) schools in DPA town governments meetings daily life, save on water, pollution on • Community meeting will be held ➢ 70% water, sewage treatment, etc.; • No. of on the exhibition content about and the local comments and • No. of various kinds of health comments on the exhibition hall, and residents- suggestions awareness education activities as any suggestion from the community 35% (disaggregated by conducted by all primary and middle will ➢ 50% female gender) schools amounts to 113 in total, with all be attached great importance to. participants- students participated; 80% • No. of primary schools and middle schools participating in the health awareness education activities amounts 48

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source to 300; • Total number of students participating in the activities amounts to 236,766; of which 114,515 are females, accounting for 48.37% of the total; parents of these students in communities of project areas have also been educated through the publicization and education activities in schools; • According to the dental fluorosis education proposal sponsored by Chaonan CDC (Centers for Disease Control and Prevention), the awareness rate among students above grade 5 in primary schools together with their parents in Chaonan District been reached over 80% on health knowledge in prevention and control of endemic diseases. • In the first half of 2020, due to the outbreak of COVID-19, no new activities were conducted.

49

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source 8. Leadership development • Local government • Workshops on social inclusion • In the first half of 2020, due to the and equitable access to the new officials and representatives of • No. of outbreak of COVID-19, no new activities economic achievements (particularly included in the workshops communities PMO, IAs, were conducted. for the poor and farmers in the budget of and local • No. of transitional period) ➢ Female capacity governments participants • Workshops on urban participants development expansion and employment (labor shall account 2015–201 • No. of female for 30%. decision makers opportunities for the poor and rural 7 areas) ➢ At least one workshop per • Case studies on the social year impacts of the water supply project

Resident representatives in

project areas IAs, local FB, ➢ Female 9. Public hearings for water tariff PB, WSPs representatives shall account for and WWTPs, • No. of • • Hearings have been held in • Public hearings for water tariff No budget need 30%; and participants accordance with the procedure in communities (disaggregated by 2019, and the new water price will be ➢ Representative gender) s of poor and implemented 2015 low-income families • • Women (10) accounted for 31% of the 32 hearing representatives, and shall account for onwards 15%; poor and low-income representatives (7) for 22% • • No new activities in the first half of 2020

50

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source • The Contractor's construction plan and 10. Participation and consultation actual operation have included the • Researches on water measures to the daily life of residents;

source conservation Representatives In the HH survey of ecological compensation • Construction scheme to be from residents and mechanism in water resources prepared by contractors, including protection and research and in the schools in project IAs, WAB, EB, • No. of outreach the mitigation measures for areas WSPs, and consultation of villages around the residents’ daily activities programs reservoir, 33% of the HH survey and ➢ Female communities No budget need • No. of consultation representatives are women. • Public awareness education representatives participants plan for sanitation, environment shall account for 2014 (disaggregated by protection and health improvement 30%. gender) • Evaluation of the quality of onwards water supply service

51

M&E on Resettlement, Social and Gender Development (3114- PRC) 11. Reduction of dental fluorosis • According to the survey results of 8-12- • Investigation of dental fluorosis has • Total No. of primary year-old pupils in Yiying village, Xiashan been carried out in selected three Two villages in the IAs, HB, EPB 30, 000 CNY school students affected area street, Zhilan village, Longtian town and villages, baseline time of of Project (disaggregated by 2016, Xinqing village, Lugang town: investigation is ➢ Primary survey budget gender and age) students aged 1) Yi Ying Village: in 2015, 355 male the year of 2016 or 1 year before the 2024 WSP was put into operation, and between 8 and 12 • No. of primary students and 330 female students were impact time of investigation is 2024 or shall account for school students with investigated, the incidence rate of dental 8 years after the WSP was put into 100%. dental fluorosis fluorosis was 5.25%, and 477 male operation. (disaggregated by students and 460 female students were gender and age) investigated in 2016, the incidence rate of dental fluorosis was 2.24%. 2) Chi Lan village: in 2015, 145 male students and 161 female students were investigated, the incidence rate of dental fluorosis was 0, and 125 male students and 143 female students were investigated in 2016, the incidence rate of dental fluorosis was 0. 3) Xin Qing village: in 2015, 82 male students and 91 female students were investigated, the incidence rate of dental fluorosis was 7.5%, and 69 male students and 94 female students were investigated in 2016, the incidence rate of dental fluorosis was 2.25%. 4)No new survey conducted in the first half of 2020.

52

M&E on Resettlement, Social and Gender Development (3114- PRC) Agencies Funding Accumulative Implementation Status Proposed Actions Target Group(s) Timing Monitoring Indicators Involved Needs and by the first half of 2020 Source 12. Promote non-agricultural By first half of 2020: employment and improve livelihood Labor residents in CEWLG, IAs, Local • No. of jobs Publicize the information of and the DPA local labor government created 5206 jobs were created; promote the trainings on non- farming bureau, CAB, ➢ female training budget No. of new migrant jobs for local laborers and migrant and PADO 2015–2018 1915 migrant workers, 1501 women participants laborers workers 28.83%); laborers; shall account (disaggregated by • Train migrant laborers in a for 40 gender) 3951 trained workers, 1132 women variety of issues like labor law, participants (28.65%), 925 poor participants contract, safeguard of legal rights, of poor • No. of employees (17.77%) etc. families shall involved

account for • No. of migrant 15% laborers trained (disaggregated by gender)

53

M&E on Resettlement, Social and Gender Development (3114- PRC) Appendix 2: Gender Action Plan Implementation Monitoring

By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date Outcome: Improved and equitable water supply services to urban and rural residents in Chaonan District Workload on women will be (After the About 4,000 The water reduced as a completion of women will supply for rural result of the the project, be released HHs is currently improved and 0% 100.00% Statistics at project completion In progress women began from fetching relying on ( ) equitable water to benefit from water during carrying water supply service, the installation dry season by themselves. in particular for of tap water) rural females Output 1:Improved Water Resources Protection Research on Ensure females’ In April 2019, Water participation in the research Resource the 0.64 million project of Protection consultations female drinking water Qiufeng with the general At least 30% residents source Reservoir Area public and the of in protection in Solid waste decision-making participants Chaonan the reservoir Treatment process, such are females District 1,000 area Reservoir area as on the control female conducted field afforestation over the use of A record of 110% 30.00% 10 3 0 0 Completed residents investigation environment fertilizer and women’s in and case visit and health pesticide, on views and Qiufeng Village for ecological public management of opinions 2,000 female compensation awareness solid waste, on shall be residents in the reservoir teaching organization and kept. in area, and 33% materials, implementation reservoir areas of the permanent of planting respondents publicity conservation were women. board, "Letter forest, etc.

4 Progress = the number or proportion of achievements/the number or proportion of goals 5 In accordance with the GUIDANCE for ADB gender Action plan training, the status of operation implementation refers to whether the operation has been initiated, is in progress, has been completed, has been delayed or has been cancelled. 54

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date to Parents" on By the end of environmental 2019, a total of protection and 770 women health were management employed, Total positions teacher accounting for created: 169 training and 33% of the full-time community 110% 30.00% 2324 770 0 0 Completed total. This positions during education output has project Ensure females’ Women been construction participation in make up completed in the 30% of all 2019, and no consultations employers new with the general employment in public and the this period. decision-making There are 30 process, such workers of as on the control conservation 23 posts during over the use of 110% 30% 30 10 30 10 In progress forest operation state fertilizer and maintenance pesticide, on and 10 female management of workers. solid waste, on During the organization and construction implementation period, there of planting were 75 female conservation Construction 770(all female 75(management management 19.48% 50% 0 0 In progress forest, etc. 50% of period staffs) positions) posts, women's accounting for positions are 9.74% of managerial female or technical employees

No managerial Operating 0% 50.00% 0 0 0 0 In progress technical period position

55

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date Ensure females’ Participation in the Consultations with the General public and the decision-making process, such as the design and Among them, compiling of 48.37% of the textbooks, All activities 0.61 million students bulletin boards, have at least females participated in 121% 40.00% 236766 114524 0 0 Completed the composing of 40% female Residents in the the a letter to participants plain area environmental parents, the protection preparation of activities, Training materials, a nd Community publicization and education on Environmental protection and sanitation management, etc. Ensure About 110000 participation in All activities people all activities have at least 0.61million participated in related to 50% females the 160% 50.00% 110000 88000 0 0 Completed enhancement of fem residents in the environmental public ale plain area protection and awareness on participants health activities environmental organized by

56

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date protection and the school, sanitation 88000 of them management, were women, most of them were female parents, and the participation rate was 80%. Output 2: Improved Water Supply Infrastructure By the first half Ensure the of 2020:1) 10 participation of women, women in public accounting for decision-making Female 30%, processes, such participants 0.61 million participated in females the public as water plant shall 100% 30.00% 33 10 0 0 In progress design, account for residents in the consultation in the design installation of at least 30% plain area stage of water Extension of water pipes, of the total. Qiufeng WSP preparation of plant and water construction supply pipe Reconstruction plans, etc. network of Jinxi WSP project; Ensure females’ Construction Participation in of Longxi WSP the consultations ·Water price

with the general adjustment has Installation of public and the Female been approved water pipelines decision-making 0.61 million participants and process, such as female implemented; shall 107% 30.00% 32 10 0 0 Completed the design of residents in the ·In 2019, WSPs account for plain area 31% of the installation of at least 30% hearing water supply of the total. representatives pipelines, were women. preparation of construction schedules, etc.

57

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date By the first half During the of 2020, the construction total number of period, female jobs in women this output has 84.55% 30.00% 2882 731 382 70 In progress account for reached 731, 30% of the accounting for total labor 25.36% of the force total employment; Total number of There are 164 jobs generated: female 486 full-time managerial jobs during the technical 50% of the construction positions in this total female period of the project, and 89 Ensure females’ employment project female participation in in managerial the public construction 24.35% 50.00% 731 89 70 21 In progress technical hearings about is positions are water tariff and management produced for wastewater or technical output 2, treatment tariff work accounting for 12.18% of female employees Women account for Women make 30% of the up 30% of the 118.5% 30.00% 45 16 45 16 In progress Longxi water total workforce, plant has been employment put into during the operation; Jinxi operation water plant is period, and 50% of the jobs still under 50% of the were 100% 50% 16 16 16 16 In progress construction positions are managerial or managerial technical or technical

58

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date There are 3,951 trainees in this project, 28.65% of whom are At least 40% female. 512 of of women the trained participated 59.62% 40.00% 2147 512 347 57 In progress staff in this in the output are training women, accounting for 23.85% of the total trained staff. In May 2020, under the organization of various traffic Provide job police opportunities departments, and appropriate judicial offices, training communities preferentially for At least 40% and other women during of departments, and after project participants Chaonan More implementation in the About District carried Representatives than and ensure seminars, 10000 out 247 special of 125% 40.00% Completed \ 20000 In progress equal pay for workshops people legal publicity communities person equal work; in and (50%) activities of times addition, it shall meetings are "100 day be laid down in female action" for the bidding residents traffic safety documents that improvement in local females 232 villages shall be hired (communities), preferentially. organized 212 special lectures on the rule of law, distributed

59

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date more than 50000 "letter to Chaonan traffic participants" and publicity materials to the masses, produced 20 courseware and pushed propaganda There are more than 30000 wechat messages, 12 of which have been publicized on LED screens of the law firms in Chaonan District, and more than 20000 person times have been publicized to the masses by entering villages and households. More than 50% of women participated. Output 3: Strengthened Institutional and Staff Capacity

60

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date Ensure female s’ participation in (i) seminars, workshops, and meetings, as conducted to discuss the design and implementation of water supply project, water safety and As of this health, and period, 246 traffic safety At least 40% employees during of from relevant construction; (ii) participants There are 50 departments the news in the female staff have briefings and the seminars, members in 79.27% 40.00% 246 78 0 0 In progress participated in trainings in non- workshops relevant the farming jobs so and institutions competency as to make them meetings are training, of either locally female which 78 employed or go residents (32%) are out to work as a women. migrant worker;(iii) the training and education programs about a variety of issues like labor law, contract, and safeguard of legal rights, etc. as tailored for migrant workers.

61

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date Ensure females’ participation in training programs concerning leadership At least one development, to female staff improve their has been capabilities of The assigned to managing a implementation manage the variety of issues 100% 100.00% 246 78 1 1 In progress unit has a GAP work in like integrated female the EAs and water supply employee the PMO, service in urban and each and rural areas, IAs. environmental protection, sanitation, employment, and public participation, etc. 1) The project It is required that owner the EAs and IAs Chaonan water should assign supply focal staff to company and work on the project office have implementation No. of special of the GAP. The trainings and Completed (as 100% 100.00% \ 0 0 In progress personnel in assigned staff the topics remarks) charge of the shall have to go covered women's through the action plan; 2) necessary the consulting training experts programs in conducted 4 safeguard and training gender impacts sessions for

62

M&E on Resettlement, Social and Gender Development (3114- PRC) By the first half 0f 2020 January to June, 2020 Accumulative Outcome Task Indicator Beneficiares Accumulative Action Progress4 Objective female to Total Female Remarks to date status 5 date by relevant the project consulting implementation experts. agencies, including the project office, the owner, the contractor and the supervision unit. 3) Experts from the consulting company held 7 training sessions on project environmental management, project construction management, project implementation supervision and construction, gender action plan and project progress payment for the project office, construction contractor and construction supervision company.

63