FORM -1 FOR ENVIRONMENTAL CLEARANCE OF EXPANSION OF “PARK BELLES” PROJECT BY CONSTRUCTING PROPOSED HOTEL FACILITIES ON MIXED LAND USE

AT SURVEY/KHASRA NO. 69 GHA, 80 KHA, 80 KA, PROPERTY NO. 178, VILLAGE SINOLA, PARWADOON, MUSSOORIE DIVERSION ROAD, DISTRICT , BY SARA EMINENT PREPARED BY:

ENVIRONMENT MANAGEMENT DIVISION M/S GLYCOLS LIMITED (AN ISO 9001, ISO 14001, OHSAS 18001 & ISO 50001 CERTIFIED CO.) A – 1, INDUSTRIAL AREA, BAZPUR ROAD, KASHIPUR, UTTARAKHAND

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

FORM- 1 (I) Basic Information

S. Item Details No. 1. Name of the Project Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed land use by Sara Eminent located at Survey/Khasra No. 69 Gha, 80 Kha, 80 Ka, Property No. 178, Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand. 2. Sr. No. in the Schedule Activity 8 (a), Category B2 Building & Construction Projects 3. Proposed Capacity/Area/Length/ Total Plot Area : 11323.911 Sqm Tonnage/to be handled/Command Net Plot Area : 11079.641 Sqm area/Lease area/number of Wells to be Group Housing drilled (Residential Facility – Existing Sanctioned by MDDA) Parameters Total (G+9) Ground Coverage (Sqm) 2168.196 (19.57 %) F.A.R. 15510.71 Built up Area including 24288.51 Basements (Sqm) (without EWS) Dwelling Units (No.) 72

Hotel Facility - Proposed Parameters Total (G+6) Proposed Ground Coverage 1193.121 (Sqm) (10.77 %) Proposed F.A.R. 7750.744 Proposed Built up Area 12194.804 including Basements (Sqm) Rooms (Nos.) 135 Proposed Bore well = 01 Nos. 4. New/Expansion /Modernization Expansion on mixed land use 5. Existing Capacity /Area etc. 11323.911 Sqm 6. Category of Project i.e. ‘A’ or ‘B’ Category “B” 7. Does it attract the General condition? If No (Construction Project) yes Please specify. 8. Does it attract the Specific condition? If No (Construction Project) yes Please specify 9. Location Mussoorie Diversion Road Dehradun.

SARA EMINENT 1

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

Central coordinates of the proposed Project Site are 30°23′06.40″N & 78°04′23.54″E Plot/Survey/ Khasra No. Survey/Khasra No. 69 Gha, 80 Kha, 80 Ka, Property No. 178 Village Sinola Tehsil Parwadoon District Dehradun State Uttarakhand 10. Nearest Railway Station/Airport along - 8.75 Km SW with Distance in Km Jolly Grant Airport- 24.0 Km SE (Source of information: Aerial Distance from Google Earth) 11. Nearest Town, City, District Headquarters Nearest City: Dehradun - 8.5 Km SW along with distance in Km Clock Tower: Dehradun - 7.4 Km SW District Headquarters - 8.5 Km SW 12. Villages Panchayats, Zilla Parishad, Mussoorie Dehradun Development Authority Municipal Corporation, Local body Head Office: (complete postal address with telephone Transport Nagar, road, Near ISBT, nos. to be given) Dehradun, Uttarakhand 248001 Phone No.: 0135 - 6603100 0135 - 6603150 Email: [email protected] Master Plan of Dehradun – 2025 (as amended) Enclosed as per Annexure-I-a 13. Name of the Applicant Mr. V. K. Dhawan 14. Registered address Sara Eminent A1/112, Safdarjung Enclave, New - 110029 15. Address for Correspondence: Name Mr. V. K. Dhawan Designation (Owner/Partner/CEO) C.M.D. Address - Dehradun Office 7/1, Pritam Road, Dehradun – 248001 Site Office Survey/Khasra No. 69 Gha, 80 Kha, 80 Ka, Property No. 178, Village Sinola, Parwadoon, Mussoorie Diversion Road, District Dehradun, Uttarakhand. Pin Code - 248001 E-mail - [email protected] [email protected] Telephone No - + 91 5947 269631 Mobile - 9837242463

SARA EMINENT 2

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

Fax No - 05947 – 275315, 275192 16. Details of Alternative Sites examined, if No alternative site is considered. any. Location of these sites should be shown on a Topo sheet 17. Interlinked Projects No 18. Whether Separate Application of No Interlinked Project has been submitted? 19. If yes, Date of Submission Not Applicable 20. If No, Reason Not Applicable 21. Whether the proposal involves No. Project site does not involve any forest land. approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z. Notification, 1991? 22. Whether there is any Government NBC Guidelines Order/Policy Relevant/relating to the Mussoorie Dehradun Development Authority site? (MDDA) Bye Laws (Project Drawings has been approved by MDDA. Copy of Screen shot is enclosed as per Annexure-I-b) 23. Forest Land involved (hectares) No 24. Whether there is any litigation pending No against the project and/or in which the project Is proposed to be set up? (a). Name of the court (b). Case No (c). Orders/directions of the Court, if any and its relevance with the proposed project.

(II) Activity

1. Construction, Operation or decommissioning of the Project involving actions, which would cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S. Information/Checklist Yes/ Details thereof (with approximate quantities No. confirmation No /rates, wherever possible) with source of information data 1.1 Permanent or temporary change in Yes The Proposed Site of Sara Eminent - Proposed land use, land cover or topography Hotel Project “Park Belles”) falls in Residential including increase in intensity of Zone as per Master Plan of Dehradun-2025 (as land use (with respect to local land amended). (Annexure-1-a) The terrain of the site is use plan) flat in nature with moderate depression in very few areas, which would be utilized during construction

SARA EMINENT 3

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

in line with natural topography/contour. Digital Topographical Survey for Land is enclosed as per Annexure – II.

Only some temporary impact will occur during construction phase, which will be properly mitigated. 1.2 Clearance of existing land, No No significant vegetation exists at the project site. vegetation and buildings? 1.3 Creation of new land uses? Yes The Land under reference is undeveloped Land which will be altered for proposed Hotel Project.

There would be no change in the land use pattern of the area in accordance with the Master Plan as stated in 1.1 Site Layout is enclosed as per Annexure-III 1.4 Pre-construction investigations e.g. Yes Pre-construction investigations and soil testing have bore holes, soil testing? been done. Structural Design Certificate for Hotel Project is enclosed as per Annexure-IV. 1.5 Construction works? Yes All construction activities will be confined within the project premises; there will be no physical changes outside the project boundary. Construction work will be carried out as per the Layout plan. Existing GH Project includes 02 Nos. of Towers i.e. Tower-A & Tower-B with Ground & 09 Nos. of Floors. Proposed Hotel Project includes Ground & 06 Nos. of Floors including 02 Nos. of Basements & Service Floor. Total Land Area = 11323.911 Sq. m Total Ground = 1193.121 Sq. m Coverage (10.77 %) Total Green Area = 2329.86 Sq. m (including existing (21.02%) Residential) 1.6 Demolition works? No Project site is an open land. Demolition is not required as not structure exists at the site. 1.7 Temporary sites used for Yes All the construction activity including stocking of construction works or Housing of raw materials will be confined within the project construction workers? site only. Temporary labour hutments will be provided. Septic tank/soak pits will be provided at project site. Most of the labors will be hired, few

SARA EMINENT 4

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

temporary labour hutments to be provided but will confine within the site. Sanitation facilities will be developed at site. Approx. number of construction workers will be 50 during initial period and 150 during peak period. 1.8 Above ground buildings, structures Yes Excavation will be carried out for foundation of or earthworks including linear buildings and basements. structures, cut and fill or The excavated soil will be used in landscape, excavations backfilling and other area development activities. 1.9 Underground works including Yes No underground works including mining/ mining or tunneling? tunneling is required except excavation of earth for basements. 1.10 Reclamation works? No N.A. 1.11 Dredging? No N.A. 1.12 Offshore structures? No N.A. 1.13 Production and manufacturing No No Production/Manufacturing process involved as processes? the project is a construction of Hotel project. 1.14 Facilities for storage of goods or Yes Raw material will be stored at site in a covered materials? area. Cement will be separately stored under cover in bales. Sand will be stacked neatly under tarpaulin cover. Bricks and steel will be laid in open. Facility shall be provided for storage of HSD for DG sets and DG Set shall be operated during Power failure only. 1.15 Facilities for treatment or disposal Yes During construction & operation phase solid as of solid waste or liquid effluents? well as liquid waste will be generated. Construction Phase: Waste Management Waste Material would be segregated materials like into recyclable, reusable and MS Rods, rejected fractions at the site itself. bricks, Recyclable material will be sold concrete, broken tiles, to authorize dealers. Re-usable wood pieces, material will be stored within cement bags project site for re-use. etc. Remaining rejects will be sent for disposal through government authorized vendors at designated locations. Excavated Soil will be excavated for Soil development of basements and foundations of the building. Top soil will be separated and stored

SARA EMINENT 5

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

in covered condition at the site for landscaping purpose. Excavated soil can be used within the site for filling and leveling purpose. Remaining excavated soil, if any can be disposed off through government authorized vendors. Domestic Majorly local labour will be Waste hired for construction phase thus generated by there will be no or minimum labour labour hutments. Accordingly domestic waste generation by labour at site will be insignificant. During construction phase, sewage will be disposed through mobile toilets/septic tank. Operational Phase: Solid waste: The solid waste generated from proposed project will be mainly domestic in nature, and the quantity of the waste generated from proposed Hotel Project 151.35 kg/day (including landscape waste – 8.55 kg/day). Solid waste generated will be segregated into biodegradable (waste vegetables, foods etc.) and recyclable (papers, cartons, thermocol, plastics, glass etc.) components and collected in separate bins. The biodegradable organic wastes will be treated inside the premises through organic waste converter. Recyclable and non recyclable wastes will be disposed through local approved agency. Construction and Demolition Waste Management Rules, 2016 will be followed. Liquid effluents from Hotel During operation phase, sewage (76.4 KLD) will be treated and recycled. STP (85.0 KLD Capacity with FAB Technology) will be installed and the treated sewage will be reused for toilet flushing, horticulture & other purposes. Dewatered/dried sludge generated from the STP plant will be used as manure for green belt development after stabilization.

SARA EMINENT 6

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

Surplus treated effluent will be supplied to agricultural fields through Tankers for irrigation purpose, Supply to nearby construction site or Discharge to sewer line aligned by competent authority. 1.16 Facilities for long term Housing No Local labors will be hired from nearby areas during Operational workers? construction phase and temporary hutments will be provided. It is a Hotel project and no operational workers will be involved. Housekeeping and maintenance staff will be kept on shift basis. 1.17 New road, rail or sea traffic during No The site has good connectivity through existing construction or operation? road network. Only internal roads; paths will be developed for vehicular movement as per site Lay- Out for parking facility for Guests. (Annexure – III) 1.18 New road, rail, air waterborne or No Project site is accessible and is well connected via other transport infrastructure network of rail & road. Mussoorie diversion Road including new or altered routes is 210 meters away towards East. and stations, ports, airports etc? N.H. 72 : 8.8 Km S S.H. 57 : 34.0 Km W 1.19 Closure or diversion of existing No No closure or diversion of existing transportation transport routes or infrastructure route or infrastructure will be required. leading to changes in traffic movements. 1.20 New or diverted transmission lines Yes There will not be any new/diverted transmission or pipelines? lines or pipelines around the project. Internal Electrical lines would be installed as per requirements.

Proposed Hotel Facility: Connected Load for Proposed Hotel will be 1586 KW. Maximum demand for the project will be 1206 KW. Power will be supplied by UPCL. Power will be supplied by UPCL.

By Taking the Power factor 0.85 & loading factor 90%, the required capacity of the Transformer shall be 1600.0 KW. To meet this requirement it is proposed to provide 02 No. of Transformer (800 KVA capacity each). One control room shall be constructed for this purpose from where electricity shall be supplied to the end users. 1.21 Impoundment, damming, No No impoundment, damming, culverting,

SARA EMINENT 7

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

converting, realignment or other realignment or other changes to the hydrology is changes to the hydrology of proposed. watercourses or aquifers? 1.22 Stream crossings? No There are no streams running across the site. 1.23 Abstraction or transfers of water Yes During construction phase, water will be obtained from ground or surface waters? from private tankers. During operation phase, source of water supply will be Municipal Corporation as well as from bore wells.

Proposed Hotel Facility: Total water requirement is approx. 110.0 KLD, out of which domestic water requirement is 89.0 KLD. Fresh water requirement is approx. 63.0 KLD.

During operation phase, water will be provided by Municipal water supply. In case water supply not available at the time of completion of construction, Ground water shall be used after taking prior permission from CGWA. 1.24 Changes in water bodies or the No Runoff will increase due to increased paved surface. land surface affecting drainage or However, increased runoff will be managed within runoff? the site through a well-designed storm water drainage network. Rain water would be used to recharge the ground water and excess water would flow through storm water drains to the main city storm water line. So no extra load is envisaged in existing water bodies. Detailed Rainwater Harvesting Plan is attached as per Annexure - V 1.25 Transport of personnel or materials Yes Transport of personnel or materials would be for construction, operation or required during Construction phase. During the decommissioning? construction phase, about 4 – 6 trucks are estimated per day. During Occupancy there would be influx/ out flux of Guests, House keeping Staffs and Other Service Peoples. Such would be made with minimal disturbance to existing traffic and all constructional material transportation would be covered and sprinkled with water to minimize fugitive dust. Adequate parking space (Open area & Basement) will be provided for operational phase to the Guests/visitors of the premises.

SARA EMINENT 8

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

1.26 Long-term dismantling or No No long term dismantling or decommissioning or decommissioning or restoration restoration works is involved. works? 1.27 Ongoing activity during No None decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either Yes Proposed Hotel Facility: temporarily or permanently? Local laborers from nearby area will be employed during the construction phase. It has been estimated that the total population would be approx. 312 including the Staff/Visitors. In the operation phase, only hotel guests are expected at the site. No permanent influx of people is expected at the site. 1.29 Introduction of alien species? No The landscaping will be carried out with mainly local species with a few ornamental varieties of flora that are well suited to the local conditions. 1.30 Loss of native species or genetic No There will be no significant impact on the native diversity? species or genetic diversity. 1.31 Any other actions? No Not Applicable.

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply)

S. Information/checklist Yes/ Details thereof (with approximate quantities No. confirmation No /rates, wherever possible) with source of information data 2.1 Land especially undeveloped or Yes Project site lies in Village Sinola, Parwadoon, agricultural land (ha). Mussoorie Diversion Road, District Dehradun, Uttarakhand. As per the Master Plan the land falls in “R” Zone. (Annexure - I-a) 2.2 Water (expected source & Yes During Construction Phase the total water competing users) unit: KLD consumption is estimated to be 30.0 KLD which will be obtained from private tankers. Proposed Hotel Facility: Total water requirement is approx. 110.0 KLD, out of which domestic water requirement is 89.0 KLD. Fresh water requirement is approx. 63.0 KLD. During operation phase, water will be provided by Municipal water supply. In case water supply not available at the time of completion of construction, Ground water shall be used after taking prior

SARA EMINENT 9

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

permission from CGWA. Water balance for proposed Hotel Project is attached as per Annexure- VI 2.3 Minerals (MT) Yes Minerals such as sand and aggregates will be required during the construction phase. 2.4 Construction material-stone, Yes Stone, cement, sand bricks, marble, paints, tiles, aggregates, sand/ soil (expected Electric-wires, sanitary ware, and glass will be source-MT) required for the construction and development works. All materials for construction will be arranged through select suppliers. It will be stored temporarily at the site. Cement (Bags) :0.45 Lac Bricks (No) : 852525 Steel (MT) : 817.0 Course Sand : 4715.0 (CUM) 2.5 Forests and timber (source– MT) Yes Steel/aluminum/PVC frames shall be maximized to minimize the use of timber. 2.6 Energy including electricity and Yes Hotel: fuels (source, competing users) Connected Load for Proposed Hotel will be 1586.0 Unit: fuel (MT), energy (MW) KW. Maximum demand for the project will be 1206 KW. Power will be supplied by UPCL.

By Taking the Power factor 0.85 & loading factor 90%, the required capacity of the Transformer shall be 1600.0 KW. To meet this requirement it is proposed to provide 02 No. of Transformer (800 KVA capacity each). One control room shall be constructed for this purpose from where electricity shall be supplied to the end users. Apart from that 03 No. Green Insulated DG sets 500 KVA each for Park Belles (Sara Eminent Hotel Project) would be provided. 2.7 Any other natural resources (use No Not Applicable appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S. Information/Checklist Yes/ Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, Yes Diesel for DG sets will be stored in drums in which are hazardous (as per earmarked locations. It shall also be handled as per

SARA EMINENT 10

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

MSIHC rules) The Manufacture, Storage and Import of Hazardous Chemical Rules, 1989 and Material Safety Data Sheet. Spent Oil will be sold to authorized dealers. 3.2 Changes in occurrence of disease No Suitable drainage and waste management measures or affect disease vectors (e.g. insect (with frequent spray of insecticides etc.) will be or water borne diseases) adopted in both the construction and operational phase so that there will be no stagnation of water or accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors. 3.3 Affect the welfare of people e.g. by Yes It is a Hotel Project. Socio-economic standard of changing living conditions? people will improve due to increased employment opportunities and better facility provided by this project. This will also set a standard for future developments in the area. 3.4 Vulnerable groups of people who No Impacts of this type are not expected. could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No No other causes identified.

4. Production of solid wastes during construction or operation or decommissioning (MT/month). S. Information/Checklist Yes/ Details thereof (with approximate quantities/ No. confirmation No rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine wastes No No spoil, overburden or mine waste will be generated. 4.2 Municipal waste (domestic and or Yes Solid wastes would be mainly biodegradable commercial wastes) kitchen wastes; Waste paper, few non- biodegradable wastes like plastics, hazardous wastes like used batteries, etc. Biodegradable and Non-biodegradable wastes would be collected in separate bins and would be disposed as per UEPPCB norms. Hotel: Domestic waste would be 151.35 Kg/Day including Landscape waste i.e. 8.55 kg/day. Bio-degradable waste shall be processed, treated and disposed off through Composting & further utilized for Green belt development. The residual waste will be given to the waste collectors or agency as directed by the local body. Solid Waste

SARA EMINENT 11

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

(Management) Rules 2016 will be followed. 4.3 Hazardous wastes (as per Yes The hazardous waste along with other wastes in the Hazardous Waste Management project will be used oil from DG sets, which is Rules) classified as per Hazardous Waste Schedule – 1, Category 5.1 (Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016). Spent Oil will be stored in HDPE drums in isolated covered facility. This Spent Oil will be sold to authorized recyclers. Suitable care will be taken so that spills/leaks of Spent Oil from storage are avoided. Spent Oils from DG sets, would be 500 Liters/Annum approx. 4.4 Other industrial process wastes No N.A. 4.5 Surplus product No N.A. 4.6 Sewage sludge or other sludge Yes Sludge generated from STP would be used as from effluent treatment manure after stabilization for horticultural activities. 4.7 Construction or demolition wastes Yes The construction waste for the project will consist of excess earth and construction debris along with cement bags, steel bits and pieces, insulating and packaging materials, etc. Recyclable waste construction materials will be sold to recyclers. Top Soil will be stacked separately & will be used for Green belt development. 4.8 Redundant machinery or No N.A. equipment 4.9 Contaminated soils or other No N.A. materials 4.10 Agricultural wastes Yes Landscape waste of approx. 8.55 kg/day will be generated & shall be composted for making organic manure. 4.11 Other solid wastes No N.A.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr).

S. Information/Checklist Yes/ Details thereof (with approximate quantities/ No. confirmation No rates, wherever possible) with source of information data 5.1 Emissions from combustion of Yes The project does not envisage any major air fossil fuels from stationary or pollution sources except vehicular traffic and mobile sources operation of DG sets during power failure. We will use HSD for DG sets.

SARA EMINENT 12

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

5.2 Emissions from production No No production processes involved. processes 5.3 Emissions from materials handling Yes Dust emissions are envisaged during transport and including storage or transport handling of construction materials. Such emissions will be temporary and controlled by the use of sprinkling of water and other viable techniques like covering of loose material. 5.4 Emissions from construction Yes This will be restricted to the construction site only. activities including plant and Barricading will be done all along the project equipment boundary. Vehicular movement will be restricted to 20 kmph, etc. 5.5 Dust or Odours from handling of Yes Dust is anticipated during loading and unloading of materials including construction construction material and excavation of upper earth materials, sewage and waste surface. These will however be temporary in nature, which will be controlled by employing water sprinklers. Tarpaulin cover will be provided on stored loose materials to reduce the dust emission. 5.6 Emissions from incineration of No No incineration of waste would be done. waste 5.7 Emissions from burning of waste No Open burning of biomass/other material will be in open air (e.g. slash materials, prohibited on site. construction debris) 5.8 Emissions from any other sources No Not Applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat.

S. Information/Checklist Yes/ Details thereof (with approximate quantities/ No. confirmation No rates, wherever possible) with source of information data. 6.1 From operation of equipment e.g. Yes Noise would be generated during construction engines, ventilation plant, crushers activity & it will be well maintained in order to minimize noise level to the acceptable limit. Source of noise in the operational phase will be from backup DG sets (which will be in operation only during power failure) and pumps & motors. All the machinery will be of highest standard of reputed make and will comply with applicable standards i.e. The DG set sound pressure level will be maintained to be 75 dB(A) at 1 m meter from enclosed surface as per E (P) Act, GSR 371 (E) and its amendments for DG sets less than 1000 KVA. The DG set room will be provided with acoustic enclosure to have minimum 25 dB(A) insertion loss

SARA EMINENT 13

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

or for meeting the ambient noise standard whichever is on higher side as per E (P) Act, GSR 371 (E) and its amendments if DG sets are more than 1000 KVA. Therefore, no significant impact due to operation of machinery is anticipated. 6.2 From industrial or similar No No industrial processes will be carried out in the processes project. 6.3 From construction or demolition Yes Due to various construction activities, there will be short-term noise impacts in the immediate vicinity of the project site. The construction activities will include the following noise generating activities: . Concreting, mixing & operation of DG sets. . Construction plant and heavy vehicle movement. Control measures: . PPE’s will be provided to construction labors . Adequate exhaust mufflers will be provided as per norms to limit the noise. 6.4 From blasting or piling No No blasting or mechanized piling will be done. 6.5 From construction or operational Yes During Construction Phase: traffic There will be transport of material for work. Precaution will be taken to reduce the impact of the vehicular movement such as vehicular trips will not be at peak traffic hours. During Operational phase: The proposed Project is a Hotel Project, the source of air & noise pollution is vehicular movement only. The vehicular parking will be restricted only in the adequate parking area which would help in reducing air & noise pollution due to vehicular movement.

The Project Proponent will follow Traffic management and Tree Plantation which will also help to reduce the noise level & enhance air quality. 6.6 From lighting or cooling systems No N.A. 6.7 From any other sources No N.A.

7. Risk of Contamination of Land or Water from Release of Pollutants in to the Ground or in to Sewers, Surface Waters, and Ground Water, Coastal Waters or the Sea.

S. Information/Checklist Yes/ Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source

SARA EMINENT 14

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

of information data. 7.1 From handling, storage, use or No The Spent Oil from DG sets will be carefully stored spillage of hazardous materials in HDPE drums at isolated storage, and periodically sold to authorized recyclers. All precautions will be taken to avoid spillage from storage as per the Hazardous & Other Waste (Management & Transboundary Movement) Rules, 2016. 7.2 From discharge of sewage or other No There will be no discharge of untreated sewage on effluents to water or the land land or into water bodies. (expected mode and place of Proposed Hotel: discharge) Sewage Treatment Plant (85.0 KLD FAB Process) is proposed for treating the domestic effluent to be generated. It is expected that the project will generate approx. 76.4 KLD of sewage. Treated sewage will be reused for Flushing & gardening purposes with in the premises. Surplus treated effluent will be Supplied to agricultural fields through Tankers for irrigation purpose, Supply to nearby construction site or Discharge to sewer line aligned by competent authority. 7.3 By deposition of pollutants emitted No The DG Sets will be provided with adequate stack to air into the land or into water height as per CPCB norms. Hence, dispersion will be achieved and avoid deposition of pollutants in significant concentration at a single location. 7.4 From any other sources No N.A. 7.5 Is there a risk of long term buildup No N.A. of pollutants in the environment from these sources?

8. Risk of Accidents during Construction or Operation of the Project, which could affect Human Health or the Environment.

S. Information/Checklist Yes/ Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, fires etc No To deal with any fire related accident, fire-fighting from storage, handling, use or facility will be provided as per NBC norms. OHT of production of hazardous appropriate capacities will be provided for Hotel substances facility. Fire Fighting Plan is attached in Annexure - VII. 8.2 From any other causes No N.A.

SARA EMINENT 15

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

8.3 Could the project be affected by No The project falls under seismic active Zone IV natural disasters causing indicating high damage risk zone. The buildings environmental damage (e.g. will be designed as earthquake resistant and comply Floods, Earthquakes, Landslides, with the required IS specifications. Cloudburst etc)?

9. Factors which should be considered (Such as Consequential Development) which could lead to Environmental effects or the Potential for Cumulative Impacts with other Existing or Planned Activities in the Locality.

S. Information/Checklist Yes/ Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of Yes Appropriate infrastructure like roads, power supply, supporting. Facilities, ancillary waste management and waste water treatment will development or development be developed within the project site. stimulated by the project which could have impact on the environment e.g.: Proposed Project is well planned with complete  Supporting infrastructure infrastructure of water supply, Solid waste, Sewage (roads, power supply, waste or Disposal, electricity & communication networks waste water treatment, etc.) Fire Fighting system, Parking bay, Security &  Housing Development House- keeping Services.  College development  Extractive industries  supply industries  other 9.2 Lead to after-use of the site, which No No Environment impacts envisaged. could have an impact on the environment 9.3 Set a precedent for later Yes The project will provide good infrastructure and developments better life style which will set an example for later developments in the area. 9.4 Have cumulative effects due to No Not anticipated proximity to other existing or planned projects with similar effects

(III). Environmental Sensitivity

S. Areas Name / Aerial distance (within 15 Km.) Proposed No. Identity Project location boundary.

SARA EMINENT 16

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

1. Areas protected under None There are no such areas at a distance of 15 km International conventions, from the project site. National or local legislation for their ecological, landscape, cultural or other related value. 2. Areas which are important or None There are no such areas at a distance of 15 km sensitive for ecological reasons- from the project site. Wetlands, watercourses or other water bodies, coastal zone, : 16.0 Km S biospheres, mountains, forests 3. Areas used by protected, important None -- or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4. Inland, coastal, marine or No Ganga River : 37.5 Km SE underground waters Seasonal Nalla: 480 m W The ground water level in the area is approx. 25.0 meters BGL. 5. State, National boundaries No N.A. 6. Routes or facilities used by the Yes N.H. 72 : 8.8 Km S public for access to recreation or S.H. 57 : 34.0 Km W other tourist, pilgrim areas Railway Station : 8.75 Km SW Bus Stand (ISBT) : 8.5 Km SW 7. Defense installation IMA : 9.37 Km SW 8. Densely populated or built-up area Yes The Project is situated at Village Silola, Mussoorie Road Dehradun. 9. Areas occupied by sensitive man- Yes Community facility at nearby area such as made land uses (hospitals, schools, School, College, Garden, Hotel, Talkies & places of worship, community Mandir etc. are easily available. facilities). 10. Areas containing important, high No -- quality or scarce resources ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas already subjected to No There are no such areas within 15 km which are pollution or environmental subjected to pollution or environmental damage. damage (those where existing legal environmental standards are exceeded)

SARA EMINENT 17

Expansion of “Park Belles” Project by Constructing Proposed Hotel facilities on mixed Form – 1 land use by Sara Eminent located at Village Sinola, Parwadoon on Mussoorie Diversion Road, District Dehradun, Uttarakhand.

12. Areas susceptible to natural hazard Yes The site falls under the zone IV as per the which could cause the project to Seismic Zone Map of India. Adequate measures present Environmental Problems will be taken during designing of the project as Earthquakes, Subsidence, per IS norms. Landslides, Erosion, Flooding or Extreme or Adverse Climatic Buildings shall be designed as per Seismic Zone Conditions) –V.

Terms of Reference for EIA studies: Not applicable for 8 (a) Category Project

"I hereby give undertaking that the data and information application and enclosures given in the are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given if any to the project will be revoked at our risk and cost”.

Date : August, 31, 2018 Signature of the Applicant

Place : Dehradun

(P. K. Dhawan) Authorized Signatory

NOTE:

 The projects involving clearance under Coastal Regulation Notification, 1991 shall submit with the application a C.R.Z. map duly demarcated by one of the authorized agencies, showing the project activities, w.r.t. C.R.Z ( at the stage of EC). Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification, 1991 for the activities to be located in the CRZ.

 The projects to be located within 10 km the National Parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-a-vis the project location and the recommendations or comments of the Chief Warden “thereon (at the stage of EC)”.

 All correspondence with the Ministry of Environment & Forest including submission of application for TOR / Environment Clearance, subsequent clarification, as may be required from time to time, participation in the EAC Meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for specific project”