<<

1 Section 1: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Right-of-way clearing activities • Continue to progress permits and • Coastal GasLink is hosting ongoing for permitted areas (total approvals. community open houses and right-of-way currently approved for • Continue right-of-way clearing job fairs between September clearing in Section 1 is approximately activities for permitted areas. and October 2019. Section 1 64 kilometres). • Continued establishment open houses are complete - Visit • Access road brushing, and road and of Chetwynd workforce CoastalGasLink.com for upcoming bridge upgrades ongoing. accommodation site, with open houses and jobs fairs. • Establishment of Chetwynd anticipated first occupancy workforce accommodation site April 2020. ongoing. • Continue access road brushing, and road and bridge upgrades. • Commence controlled blasting activities as required.

Section 1 Location: East of Dawson Creek to South of Chetwynd Groundbirch Length: 92 kilometres ay 97 Prime Contractor: Surerus Murphy Joint Venture hw Hig Workforce Accommodations: One Workforce Accommodation – Chetwynd Chetwynd

Project Right of Way (Section 1) Workforce Accommodation Site Laydown Area (Where sections of pipe are stored and staged for assembly) Stockpile Site (Where sections of pipe Highway 52 will be stored until ready for construction)

d a o R e ic v r H e ig S hw

t a s y e r 2 o 9 F r e iv

R

a

k

n u

k Base map source © Mapbox, © OpenStreetMap

u S Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston 27 Kitimat 7 4 8 6 5 Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 2 Section 2: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Right-of-way clearing activities • Continue to progress permits and • Coastal GasLink is hosting ongoing for permitted areas approvals. community open houses and (total right-of-way currently • Continue right-of-way clearing job fairs between September approved for clearing in Section 2 is activities for permitted areas. and October 2019. Section 2 approximately 36 kilometres). • Continued establishment of Sukunka open houses are complete - Visit • Establishment of Sukunka workforce workforce accommodation site, with CoastalGasLink.com for upcoming accommodation site ongoing. anticipated first occupancy planned open houses and jobs fairs. • Access road brushing, and road and for mid-October 2019. bridge upgrades. • Continue access road brushing, and road and bridge upgrades. • Commence controlled blasting activities as required.

Section 2 Location: South of Chetwynd to West of West Bear Lake Length: 48 kilometres Prime Contractor: Surerus Murphy Joint Venture BURNT RIVER S u k u Workforce Accommodations: Two Workforce n k a

Accommodations – Headwall, Sukunka River R i v e r

F o r e s Project Right of Way (Section 2) t

S e r H v i i g Workforce Accommodation Site c h e w

R a o a y Laydown Area (Where sections of pipe d 29 are stored and staged for assembly) Stockpile Site (Where sections of pipe SUKUNKA will be stored until ready for construction) RIVER

Base map source © Mapbox, © OpenStreetMap Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 3 Section 3: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • B.C. Oil and Gas Commission (OGC) • Additional right-of-way clearing • Coastal GasLink is hosting recently provided approval for anticipated to commence week of community open houses and supplemental stream crossings in October 7, 2019 between KP 224 and job fairs between September Section 3, which allowed clearing to KP 215, northwest of Davie Lake, and October 2019. Visit commence between KP 172 and KP pending receipt of permits and CoastalGasLink.com for upcoming 215 near Parsnip Multi Use Site. internal compliance approvals. open houses and jobs fairs in your • Right-of-way clearing commenced • Delivery of pipe anticipated early community. September 27 between KP 172 November 2019 at stockpile and and KP 183, with additional areas laydown sites (7A, 12 and Log Lake). commencing pending internal compliance approvals. • Parsnip Workforce Accommodation complete and currently housing 187 workers.

Section 3 Location: West of Macleod Lake to Northeast of McLeod Prince George Lake Length: 104 kilometres Highway 97 Prime Contractor: SA Energy Group Workforce Accommodations: One Workforce ANZAC 7A Stockpile Accommodation – Parsnip RIVER

Project Right of Way (Section 3) Laydown 12 Workforce Accommodation Site Laydown Area (Where sections of pipe PARSNIP RIVER are stored and staged for assembly) Stockpile Site (Where sections of pipe will be stored until ready for construction)

Bear Lake

Log Lake Stockpile Base map source © Mapbox, © OpenStreetMap Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 4 Section 4: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Continue to progress permits and • Right-of-way clearing anticipated • Coastal GasLink is hosting approvals for right-of-way clearing, to commence mid-November 2019, community open houses and therefore no construction activities pending receipt of permits and job fairs between September at this time. internal compliance approvals. and October 2019. Visit • Access road and site development • Delivery of pipe anticipated early CoastalGasLink.com for upcoming completed for permitted areas. November 2019 at stockpile and open houses and jobs fairs in your • Continue to work with local laydown sites (Stockpile 9A and community. municipality and regional district Clear Creek). to progress permits for Vanderhoof • Vanderhoof Workforce workforce accommodation site. Accommodation first occupancy is expected in January 2020.

Highway 27 H

i

g h

w

a y

9

7 Bear Lake

Fort St. James Stockpile 9A Section 4 Location: Northeast of Prince George to North of Vanderhoof Length: 93 kilometres Prime Contractor: SA Energy Group Workforce Accommodations: One Workforce Accommodation - Vanderhoof

Project Right of Way (Section 4) Workforce Accommodation Site Clear Creek Laydown Nukko Laydown Area (Where sections of pipe Lake are stored and staged for assembly) Stockpile Site (Where sections of pipe Highway 16 will be stored until ready for construction)

Base map source © Mapbox, © OpenStreetMap Vanderhoof Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 5 Section 5: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Ongoing clearing and site • Lejac Workforce Accommodation • Coastal GasLink is hosting preparation for the establishment of first occupancy expected community open houses and job Lejac workforce accommodation. October 2019. fairs between September and October 2019. Section 5 open houses are being held as follows: • October 29 – Fraser Lake, Fraser Lake Recreation Complex

Section 5

H i Location: North of Vanderhoof to South of Burns Lake gh

w Length: 82 kilometres a y 2 7 Prime Contractor: Macro Spiecapag Joint Venture (MSJV) Workforce Accommodations: One Workforce Accommodation - Lejac

Project Right of Way (Section 5) Workforce Accommodation Site Laydown Area (Where sections of pipe are stored and staged for assembly) Stockpile Site (Where sections of pipe will be stored until ready for construction)

Endako FRASER LAKE Fort Fraser Fraser Lake Highway 16

FRANÇOIS LAKE Base map source © Mapbox, © OpenStreetMap Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 6 Section 6: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Environmental field studies for pre- • Continue to progress permits and • Coastal GasLink is hosting construction ongoing. approvals for early works activities, community open houses and • Continued preparation for early- including clearing. job fairs between September work activities, pending completion • Pending permits and approvals, and October 2019. Visit of environmental field studies and commence early works activities at CoastalGasLink.com for upcoming receipt of permits and approvals. Laydown 28 and 7 Mile Road site. open houses and jobs fairs in your • Occupancy of the 7 Mile Road site is community. expected January 2020.

Highway 16

Houston

Section 6 Highway 16 Location: South of Burns Lake to South of Houston Project Right of Way (Section 6) Length: 80 kilometres Workforce Accommodation Site Prime Contractor: Pacific Atlantic Pipeline Laydown Area (Where sections of pipe Construction Inc. (PAPC) are stored and staged for assembly) Workforce Accommodations: One Workforce Stockpile Site (Where sections of pipe Burns Lake Accommodation – 7 Mile Road will be stored until ready for construction) H ig h w

a y

3 5

TCHESINKUT LAKE

François Lake FRANÇOIS LAKE Southbank Base map source © Mapbox, © OpenStreetMap Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 7 Section 7: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Environmental field studies for pre- • Continue to progress permits and • Coastal GasLink is hosting construction ongoing. approvals for early works activities, community open houses and • Continued preparation for early- including clearing. job fairs between September work activities, pending completion • First occupancy of Huckleberry and October 2019. Visit of environmental field studies and workforce accommodation site CoastalGasLink.com for upcoming receipt of permits and approvals. expected July 2020. open houses and jobs fairs in your community.

Highway 16 Section 7 Location: South of Houston to South of Hazelton Length: 83 kilometres Houston Prime Contractor: Pacific Atlantic Pipeline Construction Inc. (PAPC) Workforce Accommodations: One Workforce Accommodation – Huckleberry

Project Right of Way (Section 7) Workforce Accommodation Site Laydown Area (Where sections of pipe are stored and staged for assembly) Stockpile Site (Where sections of pipe will be stored until ready for construction)

MORICE RIVER

PARROTT LAKES

MORICE LAKE Base map source © Mapbox, © OpenStreetMap Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink 8 Section 8: Construction Update

Construction Update October 3, 2019

Current construction: Upcoming construction: Other activities: • Ongoing right-of-way clearing, • Continue to resume clearing along • Coastal GasLink is hosting stripping and grading, with blasting right-of-way in Section 8, pending community open houses and as required. full compliance and necessary job fairs between September • Ongoing fence setup and parking approvals. and October 2019. Section 8 work at Kitimat Meter Station. • Continue cable crane preparation. open houses are complete – • Ongoing anchor preparation work at • Continue grubbing, stripping and Visit CoastalGasLink.com for Cable Crane Hill. grading, including controlled upcoming open houses and jobs • Sitka Lodge currently houses blasting where necessary. fairs. approximately 310 workers. • Controlled blasting planned near • Hunter Creek workforce laydown areas 31 and 32, and along accommodation currently houses right-of-way near KP 651. No impact approximately 70 workers. to public traffic anticipated. • Main 9A workforce accommodation • Pioneer 2 workforce accommodation currently houses approximately first occupancy is expected January 105 workers. 2020, and Icy Pass workforce accommodations are expected in Spring 2020.

Base map source © Mapbox, © OpenStreetMap

Section 8 Location: South of Hazelton to Kitimat Length: 84 kilometres Prime Contractor: Macro Spiecapag Joint Venture (MSJV) Workforce Accommodations: Six Workforce Accommodations – Sitka Lodge, Hunter Creek, Icy Pass 1, Icy Pass 2, Pioneer 2, Main 9A

Project Right of Way (Section 8) Workforce Accommodation Site Laydown Area (Where sections of pipe are stored and staged for assembly) Stockpile Site (Where sections of pipe will be stored until ready for construction)

H

i

g

h

w

a y

3 Kitimat 7

Kitamaat Village MORICE LAKE Project Overview

About the Project The Coastal GasLink Project is a 670-kilometre provincially regulated pipeline that will safely deliver natural gas from the eastern part of B.C. near Dawson Creek to the LNG Canada facility in Kitimat, B.C. The project is designed to meet some of the strictest environmental and safety standards in the world.

Fort St. John Proposed Coastal GasLink Metering Facility Taylor Proposed Coastal GasLink Compression & Metering Facility Hudson’s Hope Potential Future Coastal GasLink Compression Facilities (TBD) Dawson Creek LNG Canada Facility (3rd party) Chetwynd 1 97

Mackenzie 37 29 2 Tumbler Ridge ALASKA 16

Smithers BRITISH COLUMBIA Telkwa

Terrace 16 3 ALBERTA Prince Rupert Fort St. James 37 Houston Burns Lake 27 Kitimat 7 4 8 6 5 Fraser Lake Prince George Vanderhoof 16

97

Construction activities overview (subject to change)

2019–2020: Site preparation 2020–2022: Mainline construction 2022–2023: Post-construction • Improve access / upgrade roads • Clearing, grading, and removal of • Clean up, land restoration and • Establish workforce topsoil reclamation of right-of-way accommodation sites • Excavation of trenches and • Anticipated in service (2023) • Land clearing placement of pipe next to trench • Site preparation for pipe (stringing) laydown areas • Welding, inspection and coating • Pipe arrives at laydown areas • Lowering-in and completion of final welds • Back-fill and cover • Pressure-testing for safe operation

We’d like to hear from you If you have any questions or comments about the project, please reach out.

1.855.633.2011 (toll free) facebook.com/coastalgaslink CoastalGasLink.com twitter.com/coastalgaslink