Visioning Bellaire Urban Design and Beautification Conceptual Master Plan December 2016 Introduction

The Urban Design and Beautification Conceptual Master Plan for the city of Bellaire is the result of an intensive planning effort. Recognizing that the quality of the physical environment has a tremendous influence on the image of the City, the Urban Design and Beautification Conceptual Master Plan serves as a foundation for shaping the City fabric in support of its vision to enhance the overall quality of life for its residents. At its very essence, the Conceptual Master Plan is an assemblage of powerful ideas. This Master Plan provides guidelines to maintain the inherent beauty and unique characteristics of the city while, at the same time, identifying opportunities for improvement of the quality of the living environment. Contents

01. Listening to the Community

02. Listening to the Land

03. Design Principles

04. Vision

05. Design Initiatives

i. Urban Elements

ii. Overhead Power Lines

iii. Neighborhood Streets

iv. West Loop Motor Courts

v. Connector Streets

vi. Major Thoroughfares

vii. Stormwater Management

viii. Bellaire Boulevard: The Heart of Bellaire

ix. Urban Village Downtown

x. City Gateways

xi. Coastal Prairie Park

xii. North Livable Center

06. Implementation

07. Appendix

08. Acknowledgements

LISTENING TO THE COMMUNITY FOUR RESULTS CATEGORIES RESULTS FOUR responses from the numerous filter were used to categories Four homes and neighborhoods, landscaping, survey: the citizens’ The planning. Triangle/Downtown and planning streetscape word as represented are graphically these categories of results the more the concept word, the The larger tag clouds. or clouds emphasized in the survey. or mentioned repeatedly was In an effort to enhance the visual and environmental quality quality and environmental visual to enhance the In an effort Bellaire a Beautiful Bellaire, the Citizens for of the city of that in a survey participate to residents invited organization 1,000 responses. received over launched movement, with the grass-roots coupled This survey, Bellaire. of the city vision for a long-term develop the need to acts as a guide vision that a consensus develop This plan aims to time. over initiatives design beautification implementing to Citizens’ Survey Citizens’ PARTICIPATION

6 LISTENING TO THE COMMUNITY IMAGES PROVIDED BY CBBPLANNING, Strengths Opportunities Weaknesses

LISTENING TO THE COMMUNITY 7 Outcome: September 2016 September Listening to the city and the city to Listening site perform community, analysis Alternatives Conceptual management Project Gathering Data Coordination Stakeholder Design Input Citizen Survey Design Advisory and Boards Council, Commissions During Design Input Meetings Community the During Design Input Alternatives Conceptual Workshop Listening to the City and and the City to Listening Meetings Community Alternatives Conceptual Workshop Consensus Conceptual Direction Conceptual Consensus » » » » » » » » » » » » » Terrain Studio Terrain » » » The City » » » Bellaire a Beautiful Citizens for » » » » » » » Milestones + Responsibilities Roles Step One: One: Step Alternatives Conceptual The Urban Design and Beautification Conceptual Master Plan has Master Conceptual and Beautification The Urban Design Through effort. and cooperative a collaborative been prepared as fluid idea-generation, listening, by characterized a design process the general workshops, and on-site involvement stakeholder and concerns their voice to the opportunity provided was public in the be considered issues to regarding make recommendations a long- The design team has developed Plan. Master Conceptual Bellaire addressing the physical, of the City for planning tool range in the face will which the City challenges, social, and sustainability and a near- both address to This Plan has been crafted future. interventions beautification implementing for strategy long-term vision. the consensus achieve required to Design Process

8 LISTENING TO THE COMMUNITY Draft Conceptual Master Plan Step Two: Roles +Responsibilities Milestones » » » Council, Boards andCommissions » » The City » » Advisory Group » » Terrain Studio » » » » » » » » » Draft Conceptual Master Plan Workshop Draft Conceptual Master Plan Conceptual Master Plan 75% Review of Draft workshop conceptual master plan Design input duringdraft Design Input Stakeholder Coordination Conceptual Master PlanPoint Design Input at 75% Draft Key Boards andCommissions for aBeautiful Bellaire,City, Representatives from Citizens Project Management Development Draft Conceptual Master Plan October 2016 Outcome: Final Conceptual Master Plan Step Three: Milestones Roles +Responsibilities » » » » Council, Boards andCommissions » » The City » » Advisory Group » » Terrain Studio » » » » » » » » » » Final Conceptual Master Plan Workshop Draft Conceptual Master Plan Master Plan 75% Review of Final Conceptual City Council Presentation Workshop Conceptual Master Plan Design Input During Final Design Input Stakeholder Coordination Conceptual Master PlanPoint Design Input at 75% Final Key Boards andCommissions for aBeautiful Bellaire,City, Representatives from Citizens Project Management Development Final Conceptual Master Plan November 2016 Outcome: Program Plan Step Four: Roles +Responsibilities Milestones » » Council, Boards andCommissions » » The City » » Advisory Group » » » Terrain Studio » » » » » » » » » Final Conceptual Master Plan 90% Review of Program Plan Approval Conceptual Master Plan Program PlanandFinal Program PlanInput Stakeholder Coordination Plan Point Design Input at 90%Program Key Boards andCommissions for aBeautiful Bellaire,City, Representatives from Citizens Project Management Final Conceptual Master Plan Program Plan December 2016 Program Plan Outcome:

LISTENING TO THE COMMUNITY 9

Bellaire Wonderful

History and Culture Neighborhoods and Schools Parks and Trees

LISTENING TO THE LAND Proximity DRIVE TIME TO DESTINATIONS:

HARDY TOLL ROAD 15 min. to DT (9 mi) INTERSTATE 45 INTERSTATE 6 min. to Uptown (3 mi)

WHITE OAK BAYOU 16 min. to TMC (10 mi)

US 59 / INTERSTATE 69 DRIVE TIME TO AIRPORTS:

30 min. to HOU (15 mi)

E RIV 50 min. to IAH (30 mi) . D IN M 30 HIGHWAY 290

INTERSTATE 610

VE RI . D INTERSTATE 10 IN M 20

Uptown BUFFALO BAYOU Houston Downtown E RIV . D Houston IN M 10

Texas Medical Center

BELLAIRE US 59 / INTERSTATE 69

BRAYS BAYOU

Hobby Airport HIGHWAY 288 HIGHWAY History the best placefor kidsto grow up. 1962: The BellaireParks +Recreation Department madeBellaire Outstanding Parks and Schools became thenew location of Community National Bank. block of BellaireBoulevard near South Rice. The First State Bank 1960: Pictured:First State Bankof Bellairelocated inthe5100 Architectural Style that Amegy Bankpurchasedtheshoppingcenter in2006. 1958: Pictured:Shopping center onBissonnet Street at 6thStreet Automobile-Orientated on South Rice Avenue. Bellaire Boulevard. This isthecurrent location of the Walgreens 1957: Pictured:Dugan DrugsShopping Center onSouth Rice at Strip Retail Entrance 1952: “Welcome to Bellaire, : A City of Homes”at City Signage Boulevard, connecting Bellaireto Houston’s MainStreet. 1909: A four-mile street car lineisbuilt, along with Bellaire Connectivity 23,000-acre Rice Ranch. It was envisioned to bea“Garden City”. 1908: City of Bellairefounded by William Baldwin aspartof the Urban Planning AUTOMOBILE ORIENTED IMAGES FROM “LIFE AND TIMES AROUND BELLAIRE, TEXAS: 1909-2013” BY J. MICHAEL MCCORKLE MICHAEL J. BY 1909-2013” TEXAS: BELLAIRE, AROUND TIMES AND “LIFE FROM IMAGES ARCHITECTURAL STYLE SIGNAGE URBAN PLANNING STRIP RETAIL CONNECTIVITY SCHOOLS AND PARKS

LISTENING TO THE LAND 15 Historically, Historically, focused development the car around Inhibits sustainable development of forms » » AUTO-ORIENTED DEVELOPMENT COMMERCIAL » » Average commute time commute Average 20 employment: to minutes for location Great community bedroom » » CONNECTED TO TO CONNECTED DESTINATIONS HOUSTON’S » » Safe neighborhoods Safe Good schools Good parks » » » GREAT NEIGHBORHOODS GREAT » » » Signage at city city at Signage gateways seen as City home commuter’s » » » » CAR-ORIENTED IDENTITY CAR-ORIENTED Everything, including Bellaire’s proximity to regional destinations, the city’s urban forest, urban forest, the city’s destinations, regional to proximity including Bellaire’s Everything, it is today. what City has made the development, and auto-oriented Key Components Key IMAGE FROM “LIFE AND TIMES AROUND BELLAIRE, TEXAS: 1909-2013” BY J. MICHAEL MCCORKLE

16 LISTENING TO THE LAND » » » AUTOMOBILE » » » social interaction Deters people from Historically important car access via City revolves around » » BELLAIRE ICONOGRAPHY » » iconography Mostly auto-oriented Signage assignature » FLOODING » existing infrastructure to location inregionand Frequent floodingdue » » » TREES » » » the community Appreciated by all in city’s beauty Major contributor to Strong treecanopy

LISTENING TO THE LAND 17 03. Natural Systems 03. Natural 02. Urban Fabric 01. Land-Use

18 LISTENING TO THE LAND 04. Cultural Systems design initiatives. include layers of information that helpestablish thedesignprinciplesandproposed beautification aremadeclear through aseries of analyses. These four chosen analyses Necessary efforts for an enhanced urban fabric, multi-modal connectivity, and Inventory + Analysis

LISTENING TO THE LAND 19 LEGEND: Residential Suburban Residential General Residential Lot Small Mix Residential-Office Mixed-Use Corridor Village Urban Office Suburban Park Business Government Area Redevelopment Parks Houston: 52% of land in public realm 52% of Houston: land in public of 17% Houston: Uptown realm Bellaire: 48.6% of land in public realm Bellaire: 48.6% of » » » » With the majority of urban design and of With the majority efforts occurring in the beautification relatively public realm and Bellaire’s the public to land dedicated of high ratio making capable of is fully realm, the City beauty, overall to the changes significant and sustainability. connectivity » » City Comparisons: City A crucial component of the city’s land- city’s the of component crucial A This allows public realm. use includes impact on its a significant make Bellaire to is included what of Examples community. are streetscapes, in the public realm spaces, civic accessible open publicly right-of-ways. and and facilities, buildings RATIO Land-Use

20 LISTENING TO THE LAND 0 5000 10,000 20,000 REGIONAL HIGHWAYS REGIONAL LEGEND: Neighborhood Street Street Connector Thoroughfare Major Highway Regional MAJOR THOROUGHFARES MAJOR STREET BISSONNET STREET BISSONNET + ROAD ROCK CHIMNEY DRIVE RENWICK connector streets also have narrower narrower also have streets connector making modifications widths, right-of-way possible, still more challenging, but modes of separated implement to efforts. and beautification transportation CONNECTOR STREETS CONNECTOR STREET NEWCASTLE FERRIS DRIVE STREET HOLLY Connector Streets: Connector such as Fournace streets, East-West thoroughfares major to Place, connect while, North-South Loop; West and the the beyond streets to connect streets these of Bellaire. Each limits of city Major Thoroughfares: Major have thoroughfares major The City’s significant to direct connections In the city. of outside destinations has true particular, Bellaire Boulevard on a local, street be a great to potential scale. However, regional, and national such in activating some challenges exist such as Chimney streets Firstly, potential. and Bissonnet Avenue, Rice Road, Rock limits, within the city’s are partially Street making portions non-accessible under This fragmentation control. the City’s to makes urban design efforts difficult Secondly, corridors. through continue who are those users frequent the most as a means to use these thoroughfares a destination. to not the city, through get design of This lessens the effectiveness for streets safe to create aim efforts that transportation. of forms all Regional Highways: Regional running through highway the major As better Loop West Bellaire, of the center The dividing it. versus the city, connects ample opportunities provides Loop West and local to get easily to residents for the city. of outside destinations regional Urban Fabric Urban STREET HIERARCHY STREET

22 LISTENING TO THE LAND 0 5000 10,000 20,000 LEGEND: Sidewalks Continuous Challenging Crossings Trail Newcastle Village Downtown Urban Park Evelyn’s STREET CHARACTERS STREET INCONSISTENT SIDEWALKS INCONSISTENT Neighborhood Streets: Neighborhood size makes walkable Bellaire’s beneficial very sidewalks implementing in the notice as one may residents, for can One page. on the far shown radii walk sidewalks continuous few that also notice streets. neighborhood along exist exist, sidewalks Where continuous and unmatched. broken are often they along wide sidewalks With continuous, with in conjunction neighborhood streets are able residents lighting, adequate city’s their utilize to and encouraged and comfortably. landscape safely, SIDEWALKS

24 LISTENING TO THE LAND . 4 N 0 I M M 0 IN 4 .

. 3 N 0 I M M 0 IN 3 .

. 2 N 0 I M M 0 IN 2 .

MIN. 10

1 0

M

I

N .

0 5000 10,000 20,000 LEGEND: Bellaire Potential of City Lane Bicycle “Planned” Houston of City Lane Bicycle STREET WITH BICYCLE LANE (CHIMNEY ROCK ROAD) ROCK LANE (CHIMNEY WITH BICYCLE STREET STREET WITHOUT BICYCLE LANE BICYCLE WITHOUT STREET The City of Houston has already begun begun has already Houston of The City master bicycle their efforts through in void is a clear there plan. However, bicycle-safe Bellaire’s of the planning from demand With the clear streets. survey, the community from residents and casual- avid- for accommodation to The approach is needed. cyclists around be focused should such facilities a physical using bicyclists separating barrier physical A when possible. barrier for transportation mode of a safe allows experience. of levels varying with cyclists streets on neighborhood facilities Bicycle the minimal due to necessary are not traffic regular and lack of right-of-way easy have Residents on these streets. and major connector to connectivity facilities. with dedicated thoroughfares BICYCLE LANES BICYCLE

26 LISTENING TO THE LAND 0 5000 10,000 20,000 28

LISTENING TOLAND THE Natural Systems

STORMWATER MANAGEMENT

Stormwater interventions are a necessity in future efforts as flooding is a reality of residents and business owners in the city of Bellaire. Drainage and infiltration problems persist throughout the entirety of the city’s land, particularly at the

northern sites. A large portion of flooding CITY LIMITS is due to Brays Bayou and local storm sewer systems not able to hold the extreme volume of incoming stormwater.

2015 MEMORIAL DAY FLOODING EVENT - FLOODING LOCATION INTENSITY MAP

LEGEND: 100 Year Floodplain 500 Year Floodplain Drainage Impeding A Redevelopment City of Bellaire Waste Water B Treatment Facility City of Houston Waste Water C Treatment Facility WESTPARK WATERSHED RIDGE LINE

A

REGIONAL DRAINAGE PATTERNS

BRAY’S BAYOU

B CYPRESS CREEK C (CITY OF HOUSTON) 0 5000 10,000 20,000 IMAGES FROM 2016 FLOOD FROM IMAGES IMAGES FROM 2015 FLOOD FROM IMAGES Approaches can be used: traditional traditional can be used: Approaches 斯城 Two巴 green infrastructure. or engineering, 1955: STREET FLOODING RESULTING FROM RAIN STORMS RAIN FROM RESULTING FLOODING 1955: STREET 2013” BY J. MICHAEL MCCORKLE 2001: THE AFTERMATH OF TROPICAL STORM ALLISON STORM TROPICAL OF AFTERMATH THE 2001: IMAGES FROM “LIFE AND TIMES AROUND BELLAIRE, TEXAS: 1909- One constant throughout Bellaire’s history history Bellaire’s throughout constant One have events flood Countless is flooding. its beginning. since in the city occurred land area has the impervious Overtime, land use as dramatically also increased ratio. built a higher has shifted to HISTORIC STORMWATER MANAGEMENT STORMWATER HISTORIC

30 LISTENING TO THE LAND Harris County’s Current Floodplain City of Bellaire 500 Year Floodplain 100 Year Floodplain LEGEND:

LISTENING TO THE LAND 31 CHINESE TALLOW CHINESE ASH CYPRESS RED OAK ELM LIVE OAK One proud asset of the community the community of asset proud One The city’s urban forest. is its strong encouraged was tree canopy beautiful corridors major along be developed to and major streets connector including thoroughfares. URBAN FOREST URBAN

32 LISTENING TO THE LAND LEGEND: Urban Forest

0 5000 10,000 20,000 LEGEND: Schools Churches Parks Mixed-Use Corridor Village Downtown Urban Complex Municipal HISTORIC TROLLEY, BELLAIRE, TEXAS BELLAIRE, TROLLEY, HISTORIC “OPEN THE DOOR” ART DOORS INSTALLATION, PASEO PARK, PARK, PASEO INSTALLATION, DOORS ART DOOR” THE “OPEN TEXAS BELLAIRE, UTILITY BOX PAINTING AT PASEO PARK, BELLAIRE , TEXAS BELLAIRE , PARK, PASEO AT PAINTING BOX UTILITY Parks are dynamic places that provide provide places that dynamic are Parks and in the social, economic role vital a cities and its residents. of welfare physical engagement community promote Parks individuals and civic pride and attract are Parks ages and backgrounds. all of city’s any of component an essential the many and because of infrastructure is high. on investment benefits, the return PARKS AND OPEN SPACE PARKS The citizens’ survey has demonstrated has demonstrated survey The citizens’ art and vibrant a more a deep desire for Bellaire has already design community. such as installations through made strides installation Art Door the “Open the Door” effort in the focused A Park. in Paseo for gives opportunity arts community Bellaire’s embrace to and artists residents depth. and cultural amazing historic ART AND HISTORY ART A critical component of a better Bellaire Bellaire a better of component critical A spaces social of the use is encouraging and parks. churches, such as schools, initiatives beautification Urban design and physically by this effort can help achieve destinations, to residents connecting pride. community while enhancing Cultural Resources Cultural SOCIAL SPACES SOCIAL

34 LISTENING TO THE LAND 0 5000 10,000 20,000 Historic Bellaire has a variety of architecture — architecture of variety a Bellaire has The and commercial. residential both community as a bedroom history city’s architecture, of types several provides auto-oriented with unique, along of palette This extensive architecture. Bellaire’s is one of styles architectural assets. greatest architecture mainstream of styles New urban in the also been introduced have years. in recent Loop West village and ARCHITECTURE

36 LISTENING TO THE LAND Residential Commercial Institutional

LISTENING TO THE LAND 37

DESIGN PRINCIPLES 40

DESIGN PRINCIPLES Design Principles

Through understandings gained from listening to the community and the land a set of design principles emerge that form the framework for urban design and beautification initiatives.

NORTH LIVABLE CENTER

URBAN VILLAGE EVELYN’S “ONE” DOWNTOWN PARK

CITY NDC + EVERGREEN PARKS

01. “One” City 02. Brand Clarity 03. Destinations 04. Connectivity 05. GreenInfrastructure 06. The Social Landscape

DESIGN PRINCIPLES 41 “ONE” CITY

0 5000 10,000 20,000 as quality andreal property value for all. elevate theoverall quality of life,as well Bellaire’s unity. Bellaire’s brand can should establish abrand that reinforces design andbeautification improvements West Loop, it’s still “ONE”city. Urban Although thecity issubdividedby the 01.”One” City

DESIGN PRINCIPLES 43 unique placeto live. will help definethecity asaunitedand the publicrealmandurbanhardware cohesive brand. Focusing thebrand on language, Bellairecanbuild aclear, Through apeople-oriented design 02. Brand Clarity

DESIGN PRINCIPLES 45 NORTH LIVABLE CENTER

URBAN VILLAGE DOWNTOWN EVELYN’S PARK

NDC + EVERGREEN PARKS

0 5000 10,000 20,000 URBAN VILLAGE DOWNTOWN NORTH LIVABLE CENTER NDC +EVERGREENPARKS EVELYN’S PARK vision of agreat city. strong advantage insupportingitsoverall close proximity of destinations serveasa urban andgreendestinations. Bellaire’s of gravity” within thecity, creating both center andEvelyn’s Park actas“centers throughout thecity. The city’s town the automobile to get to destinations rely onmodesof transportation besides modes of transportation, residents can With proper accommodation for all 03. Destinations

DESIGN PRINCIPLES 47 families. alternatives to thecar particularly for walking andbikingassafe, pleasant streets that linkdestinations andpromote A major goal isto create multi-modal 04. Connectivity

DESIGN PRINCIPLES 49 conscious community. set Bellaireapartasanenvironmentally infrastructure solutions. These solutions management, isto employ proven, green to tacklingissues,suchasstormwater Throughout Bellaire,akey component 05. GreenInfrastructure

DESIGN PRINCIPLES 51 a great additionto Bellaire. that isaregional attraction could alsobe small. Establishing anannual civicevent spaces for gatherings, both largeand efforts can focus around creating social component inbettering Bellaire. These and to know one’s neighbor isakey people to socialize,to meet onthestreet Creating apublicrealmthat allows 06. The Social Landscape

DESIGN PRINCIPLES 53

THE VISION Urban design and beautification improvements will happen incrementally over decades, these small pieces should aggregate into a clear vision unique to Bellaire a vision rooted in Bellaire's history. Renewing the 1908 Vision for Bellaire

1908

Bellaire founded by William Baldwin as part of the 23,000 acre Rice Ranch. It was envisioned to be a “GARDEN CITY” Bellaire’s Brand

THE NEW GARDEN CITY a harmonious, family-oriented community balancing the best of town and country

Beautiful Sustainable Connected/Social Bellaire’s Strength

THE BEST PLACE TO LIVE IN HOUSTON

Beautiful Sustainable Connected/Social Public Investment Strategy

each $ yields

Beautification + Functionality + Property Value Creation

DESIGN INITIATIVES ONE CITY CLARITY BRAND DESTINATIONS CONNECTIVITY GREEN INFRASTRUCTURE LANDSCAPES SOCIAL LEGEND: Bellaire Boulevard Thoroughfares Major Streets Connector Neighborhood Streets Easements Gateways City Village Downtown Urban Center North Livable DESIGN PRINCIPLES: DESIGN Overhead Power Lines Overhead Power Urban Elements Connectivity Management Stormwater Bellaire Boulevard Village Downtown Urban Gateways City Easements Center North Livable

Design Initiatives Design 01. 02. 03. 04. 05. 06. 07. 08. 09. PROJECTS: These design initiatives aim to achieve achieve aim to initiatives These design a “Garden Bellaire as vision of the grand through represented initiative, Each City”. icons graphic principles’ the design the more of one or utilizes (see right), Some initiatives design principles. overall while city, the entire throughout resonate solutions. on site-specific focus others

62 DESIGN INITIATIVES 0 5000 10,000 20,000

PLANTER

STREET LIGHT WITH WITH LIGHT STREET SIGNAL

OPTIONAL FIXTURE OPTIONAL

TRAFFIC + PEDESTRIAN PEDESTRIAN + TRAFFIC

PEDESTRIAN SIGNAL PEDESTRIAN

SIGN

SIGNAL WITH STREET STREET WITH SIGNAL TRAFFIC + PEDESTRIAN PEDESTRIAN + TRAFFIC OPTIONAL FIXTURE OPTIONAL PREFERRED FIXTURE Family Elements Urban Street Urban Elements in factor key are a Urban elements language aesthetic a common reinforcing alternations Bellaire. Some throughout such location, specialty happen in may an village downtown, as the urban However, etc. corner, street important include the should urban elements all and the unique mast, same pole fixture, funding and As bottom. ellipse-shaped lights the newer allows, reconstruction fixtures. light can replace existing be will lights 7,000 new 4,000 to Roughly This can potentially time. over installed lighting local the Centerpoint, warrant proposed add Bellaire’s to provider, options. available of suite to their fixture

64 DESIGN INITIATIVES NEIGHBORHOOD INTERSECTION WITH URBAN ELEMENTS FAMILY

STREET LIGHT

STREET + PEDESTRIAN LIGHT WITH BANNER

PEDESTRIAN LIGHT

BOLLARD WITH LIGHT

DOUBLE BANNER STREET FIXTURE

BANNER FIXTURE

PEDESTRIAN FIXTURE DOUBLE BANNER

DOUBLE STREET SIGN

STOP SIGN

STREET SIGN

PARK SIGN 5 FT. 10 FT. 15 FT. 20 FT. 25 FT.

DESIGN INITIATIVES 65 66

DESIGN INITIATIVES Typical Street Sign

Street Name Sign and Shield INE EE Bellaire

10’ Height Tapered Pole: Charcoal Gray 5.5” Diameter Base 67

Typical Traffic Signal with Street Sign and Pedestrian Signal DESIGN INITIATIVES DESIGN

17’-0” Signal Head and Shield BELLAIE Illuminated Street Name Sign BLD 14’-6”

26’ Height Tapered Pole: Charcoal Gray Pedestrian Crossing Signal 14” Diameter Base Visually Impaired Actuator Button WEST LOOP WEST LEGEND: Fronting Lines Overhead Power Streets BELLAIRE BLVD Above-Ground Line Locations Line Above-Ground Dependability of service of Dependability Public safety quality Visual 01. Overhead Power Lines Power Overhead Bellaire of the city for initiative An overall the overhead portion of a bury is to up bring the city to lines in order power standard This standards. contemporary to three ideas: helps achieve 02. 03. standards such of Implementation with street can happen in association burying for locations Key reconstruction. overhead where locations at be would visible. Other lines are extremely power as funding allows. can happen locations

68 DESIGN INITIATIVES Before

After EXAMPLE OF SIDEWALK IMPROVEMENTS AT INTERSECTIONS AT IMPROVEMENTS SIDEWALK EXAMPLE OF Implementation of sidewalks of Implementation bellaire intersections of Creation an art component) without, or (with, gardens Bio-retention component. Urban elements Neighborhood Streets Neighborhood The proposed typical street section section street typical The proposed takes into street a neighborhood for factors: several consideration 01. IMPLEMENTATION OF SIDEWALKS OF IMPLEMENTATION 02. 03. 04. Bellaire of streets the Overall, fabric. street the city’s 88% of consume be made are to overall Improvements footprint street within the existing This way. the right-of well-within and property. private minimizes disruption to in the voiced and demands The concerns sidewalks that proved survey community neighborhood on all are necessary neighborhood The proposed streets. to the right-of-way use more of streets and bio- footprints maximize sidewalk sidewalks Specifically, gardens. retention feet and a half four are a minimum of Overall passing room. allow to width in are the streetscape to improvements provide they as residents all for beneficial and streets connector to connection as improve well as thoroughfares, major aesthetic. street when is considered durability Long-term are Sidewalks placing the sidewalks. to an effort the curb in from placed away itself, the sidewalk, of enhance durability driveways. at and connections

70 DESIGN INITIATIVES 71

Typical Section: Neighborhood Street DESIGN INITIATIVES DESIGN

6 FT 4.5 FT 6 FT 27 FT 6 FT 4.5 FT 6 FT R.O.W

DRIVE & PARALLEL PARKING GARDEN GARDEN SIDEWALK SIDEWALK

BIO-RETENTION 60 FT BIO-RETENTION

R.O.W 72

DESIGN INITIATIVES Neighborhood Streets (cont’d)

CREATION OF BELLAIRE INTERSECTIONS

Since Bellaire is a grid-city, everyone experiences intersections. This creates opportunity to enhance the common factor among residents through physical enhancements and create common identity within the city.

The enhanced intersections seamlessly take care of several conflicts: connects the neighborhood sidewalks that are pulled back from the curb; takes care of grade change; provides ample space for safe crosswalks insuring accessibility; and, provides ample space for seating and art elements. These intersections encourage social interaction in the landscape while creating an opportunity for a public art program.

TYPICAL INTERSECTION WITH SPECIAL CORNERS

LEGEND:

Enhanced Intersection Location 0 5000 10,000 20,000 74

DESIGN INITIATIVES Typical Street Corner (With Art and Mural Wall)

02 RESIDENCE 01

VIEW 1

08 03 05 VIEW 1 VIEW 2 06 04 07

02

08

LEGEND VIEW 2

01. Bio-retention Garden 02. Street Light 03. The”Bellaire Bench” 04. Curb Ramp 05. Corner Plaza 06. Stop Sign 07. Corner Garden Planter 08. Art Crosswalk

VIEW OF INTERSECTION 75

Typical Street Corner (Without Art and Mural Wall)

02 RESIDENCE 01 INITIATIVES DESIGN

VIEW 1

07 04 VIEW 1 VIEW 2 05 03 06

02

07

LEGEND VIEW 2

01. Bio-retention Garden 02. Street Light 03. Curb Ramp 04. Corner Plaza 05. Stop Sign 06. Corner Garden Planter 07. Art Crosswalk

VIEW OF INTERSECTION LEGEND: Locations Garden Bio-retention EXCAVATION AROUND EXISTING AND PROTECTIVE WRAPPING OF OF WRAPPING AND PROTECTIVE EXISTING AROUND EXCAVATION TEXAS HOUSTON, HERMANN PARK, TREE ROOTS, BAGBY STREET, HOUSTON, TEXAS HOUSTON, STREET, BAGBY Stormwater Management and Management Stormwater Infiltration Environment Beautiful Creates Appeal Curb Improves Located against the sidewalk between between sidewalk the against Located gardens curb, bio-retention the street being the a few benefits, several have following: 01. 02. 03. preserve large trees along To is care special neighborhood streets, process. implementation taken during the roots tree wrapping of example One includes excavating the right) to (shown within tree roots existing boring under or these gardens. BIO-RETENTION GARDENS BIO-RETENTION Neighborhood Streets (cont’d) Streets Neighborhood

76 DESIGN INITIATIVES BIO-RETENTION GARDENS:

1,275,000 Cubic Feet of Detention

0 5000 10,000 20,000 TYPICAL CONSTRUCTION DETAIL OF BIO-RETENTION GARDEN BIO-RETENTION OF DETAIL CONSTRUCTION TYPICAL COST BENEFIT OF STORMWATER MANAGEMENT INFRASTRUCTURE FROM “DESIGNING FOR IMPACT GUIDE FOR GOVERNMENTS” BY BY GOVERNMENTS” GUIDE FOR IMPACT FOR “DESIGNING FROM INFRASTRUCTURE MANAGEMENT STORMWATER OF BENEFIT COST COUNCIL AREA HOUSTON-GALVESTON Bio-retention gardens improve water water improve gardens Bio-retention pollutants, filtering through quality capturing impacts through reduce flood and also on-site, water and retaining (Designing habitats wildlife new create Governments, Impact Guide for For Along Area Council). Houston-Galveston be not shall trees neighborhood streets, because gardens placed in bio-retention tree canopy. existing the strong, of gardens new species for plant Common species sun. Plants in full best also grow have to and shown also be robust should landscapes in the succeeded in other area. Houston BIO-RETENTION GARDEN IMPACTS GARDEN BIO-RETENTION Neighborhood Streets (cont’d) Streets Neighborhood

78 DESIGN INITIATIVES Bio-Retention Garden Examples

DESIGN INITIATIVES 79 ASIAN JASMINE ASIAN TRACHELOSPERMUM ASIATICUM LANTANA LANTANA LANTANA CAMARA IRIS LOUISIANA IRIS SER. HEXAGONAE 02. City Approach 02. City by created be would team garden A specialize in would This team the city. in bio-retention the plants maintaining the city. throughout gardens 01. Residential Approach 01. Residential native, circumstances, of variety Given a is typically maintenance plant naturalized lawn. than traditional maintain to easier guides to be given could Residents their to closest the gardens maintain This gardens. house and maintain the high due to is suggested approach the to given maintenance of amount residents current by right-of-way existing in the city. Bio-retention gardens are to be built with with be built to are gardens Bio-retention plants Specifically, material. plant robust material plant naturalized be native, are to area. Houston in well do to proven that’s the for duties maintenance Regarding two gardens, bio-retention proposed are suggested: approaches BIO-RETENTION GARDEN GARDEN BIO-RETENTION MAINTENANCE

80 DESIGN INITIATIVES LIRIOPE MUSCARI LIRIOPE GIANT BLUE LIRIOPE TENUISSIMA NASSELLA MEXICAN FEATHER GRASS ROSA KNOCKOUT ROSES ‘DOUBLEKNOCK OUT’ SALVIA RHAPHIOLEPIS INDICA RHAPHIOLEPIS INDIAN HAWTHORN CAPILLARIS MUHLENBERGIA GULF COAST MUHLY GRASS OFFICINALIS SALVIA OPHIOPOGON JAPONICUS OPHIOPOGON MONKEY GRASS +OPHIOPOGON RADIATA LYCORIS SPIDER LILY ‘KATIE’ SIMPLEX RUELLIA KATY RUELIA

DESIGN INITIATIVES 81 WEST LOOP WEST BELLAIRE BLVD Converted Motor Court Locations Court Motor Converted The current connection to the West West the to connection The current an makes for roads frontage Loop’s a family-oriented for environment unsafe of volume the high due to community intersections These traffic. commuter far to image shown (such as the “Before” to door front an undesirable create right), wall. abutment Loop West the the disconnect that Design initiatives could court a motor create to street The advantages. of variety a provide spaces and promote social create closing activities. neighborhood safe, certain with closing challenge One is the impact on current intersections for potential and the flow traffic for study traffic A elsewhere. congestion encouraged. is heavily this initiative keep their to want may Certain residents concerns. personal open due to street street of the selection for An alternative study with a traffic in conjunction closings block their volunteer be residents might the frontage from be disconnected to road. MOTOR COURTS MOTOR West Loop Motor Courts Motor Loop West

82 DESIGN INITIATIVES After Before

DESIGN INITIATIVES 83 LEGEND: Streets Connector NEWCASTLE STREET: 60’ RIGHT OF WAY WIDTH WAY OF RIGHT 60’ STREET: NEWCASTLE FOURNACE PLACE: 75’ RIGHT OF WAY WIDTH WAY OF RIGHT PLACE: 75’ FOURNACE Connector streets are generally narrow narrow are generally streets Connector neighborhood than more traffic and have to people allow still they However, streets. and their destinations local to safely get has similar street The connector homes. as the neighborhood streets, elements lane bicycle a dedicated of instead but neighborhood Like safety. promote to touch do not streets connector streets, Bellaire’s and contain property private These family. urban elements proposed on tree treatment receive street streets the street. sides of both TYPICAL STREET SECTION STREET TYPICAL Connector Streets Connector

84 DESIGN INITIATIVES FOURNACE CHIMNEY ROCK NEWCASTLE

EVERGREEN

0 5000 10,000 20,000 86

DESIGN INITIATIVES Typical Section: Newcastle Street

Key Map:

9 FT 10 FT 5 FT 5 FT R.O.W

EXISTING TRAFFIC LANES GARDEN EXISTING EXISTING PARKWAY SIDEWALK SIDEWALK & SIDEWALK BICYCLE LANE BICYCLE

BIO-RETENTION 75 FT

R.O.W. 87

Typical Section: Evergreen DESIGN INITIATIVES DESIGN

Key Map: P

9 FT 6 FT 6 FT 5 FT 27 FT 6 FT 5 FT R.O.W

TRAVEL LANES GARDEN PARKWAY PARKWAY SIDEWALK SIDEWALK BICYCLE LANE BICYCLE

BIO-RETENTION 60 FT

R.O.W LEGEND: Thoroughfares Major Chimney Rock can include the same the same can include Rock Chimney residential given its but functions required. parking is not parallel character as Bellaire’s is envisioned Bissonnet variety wide the allowing urban street gain to Bissonnet front land-uses that of and bike access vehicular, pedestrian coffee for space while creating it from businesses and other shops, restaurants sidewalks. generous onto out spill to by created space is sidewalk Additional “chicken lane” in the existing removing while maintaining the street the middle of two (2) in each traffic, (4) lanes of four the “chicken lane” direction. Recently was Shepherd of east Westheimer on with much higher a corridor removed, through demands than Bissonnet traffic can Bissonnet that Bellaire, a model emulate. South Rice is the north/south heart of of heart is the north/south Rice South with lined a civic street is It Bellaire. the schools, parks, residences, churches, businesses. It and Complex Municipal to neighborhoods Bellaire’s of many links within and destinations these and other limits. the city beyond Rock and Chimney Rice South Both right-of-way 90’ within a generous exist “green” become to these streets allowing and sustainable in character streets can include Rice South functionality. lanes with two connectivity multi-modal wide sidewalks, in each direction, traffic of green bike lanes, parkway dedicated and a gardens space, Bio-retention wide When needed 7’ median. planted with can be paved Gardens Bio-retention parallel accommodate to pervious paving parking. Major Thoroughfares Major

88 DESIGN INITIATIVES BISSONNET CHIMNEY ROCK S RICE AVE

0 5000 10,000 20,000 EXAMPLE AT WESTHEIMER STREET AND SHEPARD STREET OF OF STREET AND SHEPARD STREET WESTHEIMER AT EXAMPLE SIGNIFICANTLY WITHOUT BE REMOVED MIDDLE LANE CAN HOW TRAFFIC CONGESTING MULTI-MODAL STREET EXAMPLES STREET MULTI-MODAL Key Map: Key This corridor not only slides through slides through only not This corridor varying also has but downtown, Bellaire’s is also width The right-of-way land-uses. it the wide, making feet seventy only Bellaire. of in the city corridor one urban its stretch to Bellaire allows Bissonnet and is a great the city, through urbanity can elements where urban of example poles, etc.). on banners (e.g. pots, vary along elements streetscape Unique beds and include infiltration Bissonnet beds These infiltration trees in tree grates. stormwater of amount a significant allow infiltration. street this two-way changes to Major the middle rid of be getting would A turns. right left and allows lane that Westheimer this is of example successful the right). in image to (shown Shepard at the allows The middle lane removal widened. be to sidewalks BISSONNET STREET: BISSONNET

90 DESIGN INITIATIVES 91

Typical Section: Bissonnet Street DESIGN INITIATIVES DESIGN

7 FT 6 FT 22 FT 22 FT 6 FT 7 FT R.O.W

TRAVEL LANES TRAVEL LANES PLANTER PLANTER SIDEWALK SIDEWALK INFILTRATION INFILTRATION INFILTRATION 70 FT

R.O.W Key Map: Key Chimney Rock Road has vastly different different vastly has Road Rock Chimney Boulevard, Rice than South land-uses in its the same treatment carries still but right-of-way. ninety-foot similar CHIMNEY ROCK ROAD: ROCK CHIMNEY

92 DESIGN INITIATIVES 93 Typical Section: Chimney Rock Street DESIGN INITIATIVES DESIGN

6 FT 4 FT 4 FT 7 FT 22 FT 4 FT 22 FT 7 FT 4 FT 4 FT 6 FT R.O.W

TRAVEL LANES TRAVEL LANES MEDIAN PARKING PARKING PARKWAY PARKWAY SIDEWALK SIDEWALK PERMEABLE PERMEABLE BICYCLE LANE BICYCLE BICYCLE LANE BICYCLE

BIO-RETENTION/ 90 FT BIO-RETENTION/

R.O.W 94

DESIGN INITIATIVES Typical Section: South Rice Boulevard (Without Street Parking)

6 FT 4 FT 4 FT 7 FT 22 FT 4 FT 22 FT 7 FT 4 FT 4 FT 6 FT R.O.W

TRAVEL LANES TRAVEL LANES MEDIAN GARDENS GARDENS PARKWAY PARKWAY SIDEWALK SIDEWALK BICYCLE LANE BICYCLE BICYCLE LANE BICYCLE

BIO-RETENTION 90 FT BIO-RETENTION

R.O.W

Key Map: SOUTH RICE BOULEVARD (NO PARKING): South Rice Boulevard exists as one of the 03. Seven-foot continuous bio- major streets in the city of Bellaire. There retention gardens that are made are several aspects that make it a unique to accommodate parallel parking street: widths in parts of the corridor that 01. Able to create sidewalks on both require street parking sides for walkability 04. Two, eleven-foot lanes that allow 02. Dedicated bicycle lanes with for a vegetated median to help physical barriers separating one- establish beautiful streetscape way bicycle lanes on both traffic 05. Streetscape is able to create a directions garden street that enables all modes of transportation and ample green infrastructure 95

Typical Section: South Rice Boulevard (With Street Parking) DESIGN INITIATIVES DESIGN

6 FT 4 FT 4 FT 7 FT 22 FT 4 FT 22 FT 7 FT 4 FT 4 FT 6 FT R.O.W

TRAVEL LANES TRAVEL LANES MEDIAN PARKING PARKING PARKWAY PARKWAY SIDEWALK SIDEWALK PERMEABLE PERMEABLE BICYCLE LANE BICYCLE LANE BICYCLE

BIO-RETENTION/ 90 FT BIO-RETENTION/

R.O.W

SOUTH RICE BOULEVARD (PARKING):

White continuing down South Rice Boulevard, portions of the bio- retention gardens will be eliminated to accommodate parking. This parking accommodates parking portion of the street adjacent to civic buildings. LEGEND: Gardens Bio-retention Planters Infiltration Swales Easement Detention Shared CUMULATIVE DETENTION BENEFITS DETENTION CUMULATIVE “green infrastructure” In aggregate will initiatives management stormwater of 3, 111,705 cubic feet of a total store 71.43 acre- to This equates stormwater. (71.43 acres detaining storage of feet 12” deep). water of amount the to This is equivalent 20’x40’x3’ typical within 1,300 held water pools. swimming residential At easements, there lies a perfect easements, At swales bio-retention create to opportunity topography. undulating with the proposed stormwater impact on The significant while utilizing Bellaire for management beneficial. is extremely this application EASEMENT SWALES EASEMENT Infiltration planters are specified for for are specified planters Infiltration its urbanity because of Street Bissonnet right-of- With the small as a corridor. stormwater incorporating width, way priority. a primary is still management INFILTRATION PLANTERS INFILTRATION Throughout the entire city of Bellaire, bio- of city the entire Throughout be placed on all shall gardens retention streets, connector neighborhood streets, of The impact thoroughfares. and major throughout gardens placing bio-retention impact on has an enormous the city infiltration. stormwater overall Stormwater Management Stormwater GARDENS BIO-RETENTION

96 DESIGN INITIATIVES BIO-RETENTION GARDENS:

1,275,000 Cubic Feet of Detention

INFILTRATION PLANTERS:

11,976 Cubic Feet of Detention

EASEMENT SWALES:

1,630,278 Cubic Feet of Detention

SHARED DETENTION:

194,460 Cubic Feet of Detention

0 5000 10,000 20,000 98 DESIGN INITIATIVES CITY LIMITS

Bellaire Boulevard: The Heart of Bellaire CHIMNEY ROCK RD ROCK CHIMNEY

As the corridor running through the heart of the city, it links destinations such as the Urban Village Downtown, Evelyn’s Park, and the municipal complex. BISSONNET Bellaire Boulevard plays a crucial role in connecting pedestrians and bicyclists to the remainder of the city. 120’ 240’ Similar to other proposed streetscapes throughout the city of Bellaire, Bellaire Boulevard’s edges keep the same treatment of multi-modal accommodation and bio-retention gardens within the 5TH ST 5TH existing right-of-way. A double allee of 3RD ST FERRIS ST S RICE AVE S RICE live oak trees will be planted, one row living in the bio-retention gardens. These bio-retention gardens should include shade tolerant species. 240’

3RD ST

2ND ST

1ST ST

S AVENUE B 150’

NEWCASTLE ST

BALDWIN

Urban Village Paseo Park Office Bellaire Boulevard East LEGEND: CITY LIMITS CITY

DESIGN INITIATIVES 99 100

DESIGN INITIATIVES BELLAIRE BOULEVARD WEST

At the west end of this central corridor, Bellaire’s city limits weave into the fabric A1 of the city of Houston. So, a city gateway opportunity is best recognized at the intersection of Bissonnet Street and Bellaire Boulevard. The streetscape treatment from Chimney Rock Street to South Rice Boulevard is similar to South Rice Boulevard, but has the ability to utilize the median as a bio-retention 13 12 swale and extending eight-foot sidewalks, 11 parkway green space, a double allee of Live Oak Trees and six-foot wide dedicated bike lane to Chimney Rock. 11 12 13 A CHIMNEY ROCK CHIMNEY 11 12 13 11 12

BISSONNET 13 07. 06. 05. 04. 03. 02. 01. LEGEND:

Annual/Perennial Display Connector Plazas Metro Transit Stop Public Art Art Terrace Shops Park Architecture /Cafe’s /Coffee Decomposed Granite The Paseo –20’ Wide with FERRIS B 11 02 11 10 08 13. 12. 11. 10. 09. 08.

8’ Sidewalk Dedicated Bicycle Lane Live Oak Allee Existing Trees to Remain Bellaire Weekend Farmers Market Bellaire Water Gardens B1

DESIGN INITIATIVES 101 102

DESIGN INITIATIVES Bellaire Boulevard West: Section A-A1

6 FT 4 FT 6 FT 6 FT 32 FT 14 FT

TRAVEL LANES MEDIAN LEFT TURN LANE GARDEN PARKWAY SIDEWALK BICYCLE LANE BICYCLE

BIO-RETENTION 120 FT.

R.O.W LEFT TURN MEDIAN LANE 14 FT TRAVEL LANES 32FT

BIO-RETENTION 6 FT GARDEN 6 FT BICYCLE LANE 4 FT PARKWAY 6 FT SIDEWALK R.O.W

DESIGN INITIATIVES 103 104

DESIGN INITIATIVES PASEO PARK WEST

At the west end of the Paseo Park, a large intersection at Bissonet and Bellaire Boulevard provides opportunity for a welcoming water garden that emphasizes the entrance into the “Garden City” around B

a new traffic circle. Visitors then enter FERRIS the extension of Paseo Park to the west. This portion of the streetscape holds the existing location for the Metro Station. 11 The widening of Paseo Park in the west section allows sidewalks to be adjacent 08 to developments on the north and south sides of Bellaire Boulevard. Paseo park 02 itself helps activate necessary north- 11 12 13 south connections. 10

11

B1

BISSONNET

URBAN VILLAGE DOWNTOWN 05 04 C 03 C1 02 02 06

FIFTH ST 05 PASEO PARK WEST 11 11 09 09 URBAN VILLAGE DOWNTOWN 07. 06. 05. 04. 03. 02. 01. LEGEND:

BELLAIRE BLVD Annual/Perennial Display Connector Plazas Metro Transit Stop Public Art Art Terrace Shops Park Architecture /Cafe’s /Coffee Decomposed Granite The Paseo –20’ Wide with 05 03 04 12 02 02 13 01 12 11 13. 12. 11. 10. 09. 08. 8’ Sidewalk Dedicated Bicycle Lane Live Oak Allee Existing Trees to Remain Bellaire Weekend Farmers Market Bellaire Water Gardens 07 06 SOUTH RICE 07

DESIGN INITIATIVES 105 106

DESIGN INITIATIVES Paseo Park West: Section B - B1

8 FT 4 FT 6 FT 5 FT 32 FT

TRAVEL LANES PASEO PARK PARKWAY PARKWAY SIDEWALK BICYCLE LANE BICYCLE PASEO PARK PASEO TRAVEL LANES 32 FT 5 FT PARKWAY 6 FT BICYCLE LANE 4 FT PARKWAY 8 FT SIDEWALK R.O.W

DESIGN INITIATIVES 107 108

DESIGN INITIATIVES Paseo Park West: Section C - C1

8 FT 4 FT 6 FT 5 FT 32 FT

TRAVEL LANES ROUND ABOUT PARKWAY PARKWAY SIDEWALK BICYCLE LANE BICYCLE ROUND ABOUT TRAVEL LANES 32FT 5 FT PARKWAY 6 FT BICYCLE LANE 4 FT PARKWAY 8 FT SIDEWALK R.O.W

DESIGN INITIATIVES 109 110

DESIGN INITIATIVES PASEO PARK WEST

Without Metro Station METRO transit serves patrons by bus stops at street corners along the new Bellaire Boulevard

BISSONNET

M M M BELLAIRE BLVD FERRIS

M M M FIFTH ST SOUTH RICE

LEGEND:

M METRO Transit Stop 111

With Metro Station METRO transit station is reconstructed within the new Paseo Park and designed to accommodate longer articulated busses. DESIGN INITIATIVES DESIGN

BISSONNET

BELLAIRE BLVD FERRIS

METRO TRANSIT STATION FIFTH ST SOUTH RICE 112

DESIGN INITIATIVES PASEO PARK EAST D

13 14 12

11

10 09 05 08 07 05 07 02 04 09

13 06 11 13 12 D1 THIRD ST SOUTH RICE 113 E DESIGN INITIATIVES DESIGN

12 BELLAIRE BLVD

11 PASEO PARK EAST 09 05 09 03 04 15 07 07 02 03 09 09 06 11 11

06 12 E1 FIRST ST FIRST SECOND ST SECOND

LEGEND: 08. Community Gardens

01. West Loop Gateway 09. Weekend Farmers Market 02. The Paseo – 20’ Wide with 10. Trolley Pavilion Decomposed Granite 11. Existing Trees to Remain 03. Teas Legacy Rose Garden 12. Live Oak Allee 04. Art Terrace 13. Dedicated Bicycle Lane 05. Public Art 14. 6’ Sidewalk 06. Connector Plazas 15. Founders Fountain 07. Annual/Perennial Display 114

DESIGN INITIATIVES Paseo Park East: Section D - D1

PASEO

6 FT 4 FT 6 FT 6 FT 32 FT

TRAVEL LANES PASEO PARK GARDEN PARKWAY SIDEWALK BICYCLE LANE BICYCLE BIO-RETENTION PASEO PARK PASEO TRAVEL LANES 32 FT

BIO-RETENTION 6 FT GARDEN 6 FT

BICYCLE LANE 4 FT PARKWAY 6 FT SIDEWALK R.O.W

DESIGN INITIATIVES 115 116

DESIGN INITIATIVES Paseo Park East: Section E - E1

PASEO

6 FT 4 FT 6 FT 6 FT 32 FT

TRAVEL LANES PASEO PARK GARDEN PARKWAY SIDEWALK BICYCLE LANE BICYCLE BIO-RETENTION PASEO PARK PASEO TRAVEL LANES 32 FT 6 FT BIO-RETENTION GARDEN 6 FT BICYCLE LANE 4 FT PARKWAY 6 FT SIDEWALK R.O.W

DESIGN INITIATIVES 117 118

DESIGN INITIATIVES BELLAIRE BOULEVARD MIDDLE

Rebuilding the street to have contemporary vehicular lane widths gives twelve feet for additional green space, as well as space for wider sidewalks and bicycle facilities. The special paving at intersections helps embrace identity in the city and acts as a traffic calming 10 device along Bellaire Boulevard’s busy 14 13 corridor.

BELLAIRE BOULEVARD EAST 15 03

The portion of Bellaire Boulevard East 06 13 of West Loop has a 150-foot right- 11 14 of-way that, after a “road diet”, could provide space for a large median. A large median in Bellaire Boulevard East has the potential to be a significant space for stormwater infiltration using bio-retention swales. FIRST ST FIRST 13 13 10 11 11

01 WEST LOOP WEST 07. 06. 05. 04. 03. 02. 01. LEGEND:

Annual/Perennial Display Connector Plazas Public Art Art Terrace Teas Legacy Rose Garden Decomposed Granite The Paseo –20’ Wide with West Loop Gateway WEST LOOP WEST 03

WHITE DR 13 13

F 14 F1 15. 14. 13. 12. 11. 10. 09. 08. 14 Founders Fountain 6’ Sidewalk Dedicated Bicycle Lane Live Oak Allee Existing Trees to Remain Trolley Pavilion Weekend Farmers Market Community Gardens

BELLAIRE CT TEAS NURSERY SITE 11 11 PREVIOUS

DESIGN INITIATIVES 119 120

DESIGN INITIATIVES Bellaire Boulevard East: Section F - F1

Key Map:

6 FT 4 FT 6 FT 6 FT 32 FT 38 FT

TRAVEL LANES MEDIAN

GARDEN PARKWAY SIDEWALK BICYCLE LANE BICYCLE

BIO-RETENTION 150 FT

R.O.W MEDIAN 150 FT 38 FT TRAVEL LANES 32 FT

BIO-RETENTION 6 FT GARDEN 6 FT BICYCLE LANE 4 FT PARKWAY 8 FT SIDEWALK R.O.W

DESIGN INITIATIVES 121 122 DESIGN INITIATIVES

Urban Village Downtown

Acting as a major destination in the city of Bellaire, the urban village downtown functions as a “center of gravity”. The idea of this small mixed-use village focuses on 01 DASHWOOD local needs and businesses, rather than 02 03 attracting regional or national businesses. The area that encompasses the urban downtown village has great access, visibility and demographics. However, 06 two major challenges exist: parking and stormwater infiltration detention. These requirements become barriers to renewal 05 and redevelopment for the areas small 02 03 parcels and local businesses.

LEGEND: 01 01. Urban Village Complete Streets 06 (500 Spaces) ROCK CHIMNEY 02. Angled Parking; Pervious Paving; Shared Parking District BELLAIRE BLVD 03. Detention and Water Harvesting below Angled Parking 04. Parallel Parking 06 05. Structured Parking; 4 to 5 Levels; Shared Parking District 05

06. Renewal or Redevelopment Parcel BISSONNET 07. Urban Paseo 08. Dedicated Bicycle Lane

09. 6’ Sidewalk FERRIS 10. Transition Alley 11. Proposed Private Property 123

06 06 07 06 05 06

02 03 01 SPRUCE ST DESIGN INITIATIVES DESIGN PROPOSED HEB 06

06 06

06

01 CEDAR ST

02 03 06 05 01 06 05 06 06

04

11 BELLAIRE BLVD

PASEO PARK WEST

07 06 06 01

10

06 02 03 THIRD ST SOUTH RICE

LINDEN FIFTH ST R.O.W

5 FT WALKWAY 5.5 FT TREES STREET STREET 33 FT TRAVEL LANES TRAVEL 60 FT PARKING PARKING TREES 16 FT

METERED PARKING (PERVIOUS PAVING) (PERVIOUS STREET STREET LIGHTS WALKWAY

5.5 FT R.O.W 5 FT Typical Urban Village Downtown Streetscape, Section View Section Streetscape, Village Downtown Urban Typical SHARED STORMWATER DETENTION ZONES SHARED STORMWATER To overcome these the challenges in the the challenges these overcome To can utilize city the downtown, existing establishing by right-of-way the public burdensome offset that streets complete as building well as parking requirements, city within strategically parking structures blocks. include would streets These complete detention water parking and shared street with along via pervious paving, zones efforts. connectivity and beautification INCENTIVIZE DEVELOPMENT INCENTIVIZE Urban Village Downtown (cont’d) Downtown Village Urban

124 DESIGN INITIATIVES Typical Urban Village Downtown Streetscape, Plan View 03 07 04 06 06 02 01 08 05 06 07 06 06 09 09. 08. 07. 06. 05. 04. 03. 02. 01.

Pervious Paving Parking Trees Street Trees Future Mixed-Use Development Street Lights Walkways Bicycle Lane Metered Parking Travel Lanes LEGEND 06 06

DESIGN INITIATIVES 125 138,075 SF 138,075 SF 138,075 690 SP 252 SP 78 SP 48% 84,440 SP 84,440 SP 422 SP 132 SP SP 74 49% 155,288 SP 155,288 SF 776 SP 196 SP 195 SP 50% Development Area Development Area Development Development Area Development Area Ratio 1.0 Floor 5/1,000SF Spaces: Parking (84 ea.) 3 Levels Garage: Parking Street % Parking Shared Area Ratio 1.0 Floor Spaces: 5/1,000SF Parking (44 ea.) 3 Levels Garage: Parking Street % Parking Shared Area Ratio 1.0 Floor Spaces: 5/1,000SF Parking (49 ea.) 4 Levels Garage: Parking Street % Parking Shared Shared Parking Zone 4 Zone Parking Shared 5 Zone Parking Shared 6 Zone Parking Shared 315,100 SF 315,100 SF 1,576 SP SP 750 0 SP 48% 198,508 SF 198,508 SF 993 SP 396 SP SP 74 47% 436,035 SF 436,035 SF 2,180 SP 960 SP 96 SP 48% Development Area Development Area Ratio 1.0 Floor Spaces: 5/1,000SF Parking (150 ea.) 5 Levels Garage: Parking Street % Parking Shared Area Development Area Ratio 1.0 Floor Spaces: 5/1,000SF Parking ea.) (66 6 Levels Garage: Parking Street % Parking Shared Development Area Development Area Ratio 1.0 Floor 5/1,000SF Spaces: Parking (240 ea.) 4 Levels Garage: Parking Street % Parking Shared Shared Parking Zone 01 Zone Parking Shared 2 Zone Parking Shared 3 Zone Parking Shared Developable Area: 1.0 Floor Area Ratio Area: 1.0 Floor Developable 1,000 per 5 spaces Parking: Required square feet in Street Parking Shared roughly in Garages, Parking Shared five level within the 50% Required Parking Public Realm » » » » » Urban Village Downtown (cont’d) Downtown Village Urban » SHARED PARKING ZONE SUMMARY ZONE PARKING SHARED » » » »

126 DESIGN INITIATIVES Shared Parking Zone Summary 02 01 04 03 Buffer Alley Urban Paseos Access Alleys Shared Parking Garages Complete/Parking Streets LEGEND 05 06

DESIGN INITIATIVES 127 Alley Street Minimum 50’ Build Depth; Build Minimum 50’ Width Building Minimum 100’ Office/ for Windows Large Units Residential Height; Floor First 12-17’ Building Multi-Level Encouraged

Primary Street Parking Located at Rear of Building of Rear at Located Parking Bio-retention Gardens in Parking Lot Parking in Gardens Bio-retention

R.O.W. Typical Development in Commercial Mixed-Use District Mixed-Use in Commercial Development Typical Guidelines for architecture within within architecture for Guidelines are Village Downtown the Urban a comprehensive through recommended An additional the downtown. plan of is guidelines these establishing of method where a “build- code a form-based from Urban (see “Typical line is established to” Section Streetscape, Village Downtown example). for View” ARCHITECTURAL GUIDELINES ARCHITECTURAL Urban Village Downtown (cont’d) Downtown Village Urban

128 DESIGN INITIATIVES Urban Village Downtown Character IMAGE COURTESY OF BUTLERPLANNING

DESIGN INITIATIVES 129 Urban Village Downtown Character Downtown Village Urban IMAGE COURTESY OF BUTLER PLANNING OF IMAGE COURTESY

130 DESIGN INITIATIVES IMAGE COURTESY OF BUTLERPLANNING

DESIGN INITIATIVES 131 132

DESIGN INITIATIVES Urban Village Downtown (cont’d) Typical Transition Alley, Section View

URBAN PASEO ALLEYWAYS CYPRESS TREES

Alleyways occurring between GREEN FENCE developments in the Urban Village Downtown can be utilized as small PLANTING

park-like spaces such as “urban paseos”. R.O.W PERVIOUS PAVING Property owners can utilize these alleys as public space.

BACK YARD FENCE TRANSITION ALLEYWAYS 9.0 7.0 COMMERCIAL Alleyways can be utilized as transition RESIDENTIAL alleys that aid in shifting the landscape of GARAGE one type of zoning to another. 0.00

WATER HARVESTING TANKS FOR PASEO IRRIGATION 8 IN

10 FT 3 FT 12 FT

25 FT 133

Typical Transition Alley, Plan View DESIGN INITIATIVES DESIGN

04 02 06

01

03

05 06

LEGEND

01. Planting 02. Cypress Trees 03. Pervious Paving 04. Residential Building 05. Residential Garage 06. Commercial Building LEGEND: Gateway City Loop West Gateway City Perimeter — Gardens Water Bellaire Gateway City West City Gateway Locations Gateway City A theme of landscaped columns and landscaped columns theme of A the perimeter to continue would lanterns gardens Rose the east. at gateways could Teas Nursery the of in memory medians and throughout also continue end, the west the At edges. planted Bellaire Boulevard at gardens water act as a beautiful Street and Bissonnet Bellaire. of the city entering statement PERIMETER CITY GATEWAYS: PERIMETER CITY Instead of shying away, the city can the city away, shying of Instead West the underpasses of the embrace are the chance These underpasses Loop. give an that moment an iconic have to as an well as elegance, architectural is lighting Additionally, art. for opportunity in these spaces, as it important extremely comfortable a gateways makes the new and night. — day pedestrians space for the to facade wrap-like adding a Through from away floats that structure existing and columns lanterns wall, Loop West the a form to can landmark the threshold civic architecture. piece of elegant WEST LOOP GATEWAYS LOOP WEST City Gateways City

134 DESIGN INITIATIVES 135

Perimeter City Gateway

Before DESIGN INITIATIVES DESIGN

After 136

DESIGN INITIATIVES West Loop Gateway Option

Before

After, Alternate #1 137

After, Alternate #2 DESIGN INITIATIVES DESIGN

After, Alternate #3 03 02 04 LEGEND Park Memorial Park Bayou Buffalo Green Discovery Hermann Park Open Space Bayou Brays 01. 02. 03. 04. 05. 05 01 EXISTING CENTERPOINT EASEMENTS CENTERPOINT EXISTING The landscape is elevated as both a as both The landscape is elevated of and string destination recreational undulating through swales bio-retention and shared-use trails. topography have would and pedestrians Bicyclists at points connection access to direct, safe Discovery edge, the Nature east Bellaire’s Park. and Evelyn’s Center, are possible that connections Other require but the easements, through are the Houston of with the city working Bellaire, North Livable north edges of Park and Hermann Park, Memorial Center, Bayou). Brays bridge over (via CONNECTIVITY A game-changing opportunity to create create to opportunity game-changing A side the east lies at Park Prairie a Coastal easements. Bellaire - the Centerpoint of used for lawn open spans of These long an affordable create: towers electricity and infiltration stormwater detail to way needed (see Heat it’s where’s detention and regional local Map, page 28); provide the to and, reconnect connections; ecosystem. prairie coastal historic region’s CREATING OPPORTUNITIES CREATING Coastal Prairie Park Prairie Coastal

138 DESIGN INITIATIVES EASEMENT SWALES:

1,630,278 Cubic Feet of Detention

A A1

B B1

C C1

0 5000 10,000 20,000 CHARACTER IMAGERY CHARACTER

140 DESIGN INITIATIVES DESIGN INITIATIVES 141 CITY OF BELLAIRE OF CITY 12 FT 120 FT PEDESTRIAN PATH PEDESTRIAN SHARED BIKEWAY AND SHARED BIKEWAY CENTER POINT EASEMENT CENTER POINT Coastal Prairie Park: Section A - A1 - A Section Park: Prairie Coastal

142 DESIGN INITIATIVES CENTER POINT EASEMENT 120 FT CITY OF HOUSTON RAILROAD EASEMENT 100 FT 30 FT SOUTHSIDE PLACE

DESIGN INITIATIVES 143 CITY OF BELLAIRE OF CITY 8 FT PEDESTRIAN PATH PEDESTRIAN 9 FT BIKEWAY 120 FT CENTER POINT EASEMENT CENTER POINT BELLAIRE Coastal Prairie Park: Section B - B1 Section Park: Prairie Coastal

144 DESIGN INITIATIVES CENTER POINT EASEMENT 120 FT CITY OF BELLAIRE CITY OF HOUSTON RAILROAD EASEMENT 100 FT CITY OF HOUSTON 30 FT SOUTHSIDE PLACE

DESIGN INITIATIVES 145 205 FT CENTER POINT EASEMENT CENTER POINT 90 FT RAILROAD EASEMENT RAILROAD CITY OF HOUSTON OF CITY CITY OF BELLAIRE OF CITY BELLAIRE Coastal Prairie Park: Section C - C1 Section Park: Prairie Coastal

146 DESIGN INITIATIVES CENTER POINT EASEMENT 205 FT PEDESTRIAN PATH 8 FT BIKEWAY 9 FT 55 FT SOUTHSIDE PLACE

DESIGN INITIATIVES 147 WEST LOOP CONNECTION TO TO CONNECTION STORMWATER LINE TRUNK

ANDERSON STREET

TO WESTPARK AVENUE WESTPARK TO TO S. RICE AVENUE RICE S. TO The intent of the North Livable Center is Center Livable the North of The intent encourages area that vibrant a create to focused development economic dynamic opportunities play and work, live, around retail, types; development with a mix of and residential. hospitality, office, of a range plan includes The concept reflect changing that options residential squares, streets, Design of lifestyles. open spaces and other plazas, parks, pedestrian civic spaces emphasize connectivity. on the Plan’s easement The Centerpoint as an utilized edge has been southern between zone transition environmental and the North Livable residential existing — a feature The environmental Center. as functions that Park Prairie Coastal hike-and-bike catchment, water storm conditions edge and buffers connectivity, center the livable to value maximizing development. North Livable Center North Livable

148 DESIGN INITIATIVES ANDERSON LN. P P EASEMENT PARK OFFICE + RETAIL OFFICE

WEST PARK

RETAIL + RESIDENTIAL RETAIL + RESIDENTIAL EASEMENT OVERHEAD CENTER POINT COMMERCIAL COMMERCIAL DETENTION PARK + OFFICE HOTEL PLAZA KIOSK FOOD KIOSK FOOD COASTAL PRAIRIE PARK EASEMENT RETAIL OFFICE

RETAIL + RESIDENTIAL EASEMENT EXTENSION STORM LINE PARK EXISTING EXISTING RETAIL EXISTING EXISTING MEDICAL MEDICAL EXISTING P P CENTER POINT OVERHEAD EASEMENT

DESIGN INITIATIVES 149

IMPLEMENTATION

Initiatives and Implementation Strategies 154

IMPLEMENTATION Urban Elements - Branding Bellaire

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bellaire Street Lighting

STEP ONE - BELLAIRE URBAN ELEMENTS DETAILED DESIGN X H YR 1 $100,000 • ENERGY EFFICIENCY AND LAMP LONGEVITY (LIGHTING, SIGNALIZATION AND SIGNAGE) IMPROVED THROUGH LED AND NEW TECHNOLOGY STEP TWO - BEGIN WITH NEWCASTLE TRAIL LIGHTING X H YR 1 TBD • MAINTENANCE BY CENTERPOINT PAID FOR BY THE CITY OF BELLAIRE THROUGH TARIFF STEP THREE - IMPLEMENT ALONG NEIGHBORHOOD STREETS H YRS 1-5 TBD CHARGES. NOT PLANNED FOR RECONSTRUCTION • A CUSTOM DESIGN WILL MEAN STOCKING AND REPLACING FABRICATED COMPONENTS STEP FOUR - IMPLEMENT AS PART OF FUTURE STREET H YRS 1-20 TBD RECONSTRUCTION

Bellaire Traffic Signalization

STEP ONE - BEGIN WITH BELLAIRE BOULEVARD AT SOUTH RICE X H YR 1 $120,000 • MINIMIZED THROUGH NEW TECHNOLOGIES, BUT A CUSTOM DESIGN WILL MEAN STEP TWO - BELLAIRE BOULEVARD AT CHIMNEY ROCK, WEST M YRS 5-10 $420,000 STOCKING AND REPLACING FABRICATED LOOP AND NEWCASTLE COMPONENTS

STEP THREE - IMPLEMENT TOGETHER WITH FUTURE STREET M YRS 1-20 TBD TBD RECONSTRUCTION

Bellaire Regulatory and Community Facility Signage

STEP ONE - IMPLEMENT ALONG STREETS NOT PLANNED FOR X M YRS 1-5 TBD • A CUSTOM DESIGN WILL MEAN STOCKING RECONSTRUCTION AND REPLACING FABRICATED COMPONENTS

STEP TWO - IMPLEMENT AS PART OF FUTURE STREET M YRS 5-20 TBD TBD TBD RECONSTRUCTION

Urban Street Elements Family

25 FT.

20 FT.

15 FT.

10 FT.

5 FT. 155

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bury Overhead Power Lines

STEP ONE - INTERSECTION OF BELLAIRE BOULEVARD AND X H YRS 1 $1,368,000 • POWER OUTAGES WILL BE REDUCED SOUTH RICE (200’ EACH DIRECTION) RESULTING FROM STORM EVENTS AND/ OR DOWNED LINES PUBLIC SAFETY AND IMPLEMENTATION STEP TWO - BELLAIRE BOULEVARD, SOUTH RICE, CHIMNEY H YRS 5-10 $7,725,000 MAINTENANCE ARE IMPROVED ROCK AND BISSONNET

STEP THREE - NEWCASTLE, FOURNACE, EVERGREEN, FERRIS, H YRS 10-15 $11,550,000 AVE B

STEP FOUR - REMAINING OVERHEAD POWER LINES FRONTING H YRS 10-20 TBD STREETS ON CONCRETE POLES

Above-Ground Line Locations Typical Example: South Rice Avenue and Bellaire Boulevard

Before

BELLAIRE BLVD

After WEST LOOP WEST

LEGEND:

Overhead Power Lines Fronting Streets 156

IMPLEMENTATION Neighborhood Streets

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

General

STEP ONE - DETAILED URBAN DESIGN STANDARDS AND X H YR 1 $250,000 • PRIVATE PROPERTY RELATED DAMAGE ENGINEERING REPAIRED BY PRIVATE PROPERTY OWNER

STEP TWO - NEIGHBORHOOD STREET PROTOTYPICAL BLOCK X H YR 1 $756,509 (600’ + 2 INTERSECTIONS)

Sidewalks

STEP ONE - IMPLEMENT AS PART OF FUTURE STREET H YRS 1 -10 $87 $87 • PRIVATE PROPERTY RELATED DAMAGE RECONSTRUCTION (PER LINEAR FOOT) REPAIRED BY PRIVATE PROPERTY OWNER

STEP TWO - IMPLEMENT ALONG EXISTING STREETS (PER H YRS 10-20 $107 $107 LINEAR FOOT)

Typical Section: Neighborhood Street Street Locations

6 FT 4.5 FT 6 FT 27 FT 6 FT 4.5 FT 6 FT R.O.W LEGEND: DRIVE & PARALLEL PARKING Neighborhood Streets GARDEN GARDEN SIDEWALK SIDEWALK

BIO-RETENTION 60 FT BIO-RETENTION

R.O.W 157 Neighborhood Streets (cont’d)

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bellaire Intersections with, w/o Art

STEP ONE - IMPLEMENT AS PART OF FUTURE STREET H YRS 1 -10 $29,000 $29,000 • OCCASIONAL REPAIR OF PAVERS IF USED RECONSTRUCTION (EACH) • ART ELEMENTS CLEANING AND REPAIR IMPLEMENTATION

STEP TWO - IMPLEMENT ALONG EXISTING STREETS (EACH) H YRS 10-20 $29,000 $2,900

Typical Street Corner (With Art and Mural Wall) Typical Sidewalk Improvements at Intersections 158

IMPLEMENTATION Neighborhood Streets (cont’d)

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bio-Retention Gardens

STEP ONE - IMPLEMENT AS PART OF FUTURE STREET H YRS 1 -5 $230 $230 • TWO VIABLE STRATEGIES; RECONSTRUCTION (PER LINEAR FOOT) 1) PRIVATE PROPERTY MAINTAINED 2) CITY GARDEN TEAM MAINTAINED STEP TWO - IMPLEMENT ALONG EXISTING STREETS (PER H YRS 5-20 $282 $282 LINEAR FOOT)

Typical Construction Detail of Bio-retention Garden

DETENTION: 2,917,254 Cubic Feet = 67 Acre-Feet

67 ACRE FEET 159 Connector Streets

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Newcastle

STEP ONE - BELLAIRE INTERSECTIONS, SIDEWALKS, STREET H YRS 1-5 $9,081,245 TREES, LIGHTING, PLANTING, BIO-RETENTION GARDENS IMPLEMENTATION

Fournace

STEP ONE - BELLAIRE INTERSECTIONS, SIDEWALKS, BIKE LANES, H YRS 5-10 $4,272,072 STREET TREES, LIGHTING, PLANTING, BIO-RETENTION GARDENS

Evergreen

STEP ONE - BELLAIRE INTERSECTIONS, SIDEWALKS, BIKE LANES, H YRS 10-15 $9,980,904 STREET TREES, LIGHTING, PLANTING, BIO-RETENTION GARDENS

Ferris

STEP ONE - BELLAIRE INTERSECTIONS, SIDEWALKS, BIKE LANES, H YRS 15-20 $7,050,192 STREET TREES, PLANTING, BIO-RETENTION GARDENS

Typical Section: Newcastle Typical Section: Evergreen 160

IMPLEMENTATION Bellaire Boulevard and Paseo Park

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bellaire Boulevard West (West of Bissonnet to South Rice)

STEP ONE - AGREEMENT WITH METRO X H YR 1 TBD • REMOVAL OF METRO STATION AVOIDS A PUBLIC SAFETY CONCERN STEP TWO - NEW STREET, BELLAIRE CIRCLE, SIDEWALKS, BIKE H YRS 1-5 $9,378,682 • SEE ITEMS UNDER NEIGHBORHOOD & LANES, STREET TREES, LIGHTING, PLANTING, BIO-RETENTION CONNECTOR STREETS GARDENS • EXPANDED PASEO PARK WILL REQUIRE ADDED PARK MAINTENANCE STEP THREE - CREATE PASEO PARK WEST H YRS 5-10 $4,425,530 • MAINTAIN SPECIAL PAVERS “TRAFFIC CALMING” IN STREET

Bellaire Boulevard West 161

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bellaire Boulevard (South Rice to West Loop)

STEP ONE - CONSTRUCT SIDEWALKS, BIKE LANES, STREET H YRS 5-10 $5,036,914 • SEE ITEMS UNDER NEIGHBORHOOD & TREES, LIGHTING, PARKWAY PLANTING & BIO-RETENTION CONNECTOR STREETS IMPLEMENTATION GARDENS • DESIGN WILL REDUCE MOWING AND IRRIGATION DEMAND STEP TWO - IMPROVE PASEO PARK H YRS 5-10 $3,423,960

Bellaire Boulevard 162

IMPLEMENTATION Bellaire Boulevard and Paseo Park (cont’d)

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bellaire Boulevard East (West Loop to Railroad Tracks)

STEP ONE - CONSTRUCT STREET, SIDEWALKS, BIKE LANES, M YRS 10 $5,911,738 • SEE ITEMS UNDER NEIGHBORHOOD & STREET TREES, LIGHTING, PARKWAY PLANTING & BIO- -20 CONNECTOR STREETS RETENTION GARDENS • INCREASED MEDIAN MAINTENANCE

Typical Section: Bellaire Boulevard East

6 FT 4 FT 6 FT 6 FT 32 FT 38 FT 32 FT 6FT 6 FT 4 FT 6 FT

TRAVEL LANES MEDIAN GARDENS PARKWAY SIDEWALK BICYCLE LANE BICYCLE

BIO-RETENTION 150 FT

R.O.W 163 South Rice Avenue

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

South Rice - South (Bellaire Blvd to Cypress Ditch)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANES, STREET H YRS 5-10 $16,974,926 • SEE ITEMS UNDER NEIGHBORHOOD & TREES, LIGHTING, PLANTING, BIO-RETENTION GARDENS CONNECTOR STREETS IMPLEMENTATION • INCREASED MEDIAN MAINTENANCE

South Rice - North (Fournace to Bellaire Blvd)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANES, STREET M YRS 10-15 $7,534,154 • SEE ITEMS UNDER NEIGHBORHOOD & TREES, PLANTING, BIO-RETENTION GARDENS CONNECTOR STREETS • INCREASED MEDIAN MAINTENANCE

Typical Section: South Rice Boulevard (Without Street Parking)

Key Map:

6 FT 4 FT 4 FT 7 FT 22 FT 4 FT 22 FT 7 FT 4 FT 4 FT 6 FT R.O.W

TRAVEL LANES TRAVEL LANES MEDIAN GARDENS GARDENS PARKWAY PARKWAY SIDEWALK SIDEWALK BICYCLE LANE BICYCLE BICYCLE LANE BICYCLE BIO-RETENTION 90 FT BIO-RETENTION

R.O.W 164

IMPLEMENTATION Chimney Rock Road

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Chimney Rock - South (Evergreen to Cypress Ditch)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANES, STREET M YRS 10-15 $8,529,775 SEE ITEMS UNDER NEIGHBORHOOD & TREES, LIGHTS, PLANTING, BIO-RETENTION GARDENS CONNECTOR STREETS; INCREASED MEDIAN MAINTENANCE

Chimney Rock - North (Dashwood to Bissonnet)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANES, STREET L YRS 15-20 $3,897,286 • SEE ITEMS UNDER NEIGHBORHOOD & TREES, LIGHTING, PLANTING, BIO-RETENTION GARDENS CONNECTOR STREETS • INCREASED MEDIAN MAINTENANCE

Typical Section: Chimney Rock Street

Key Map:

6 FT 4 FT 4 FT 7 FT 22 FT 4 FT 22 FT 7 FT 4 FT 4 FT 6 FT R.O.W

TRAVEL LANES TRAVEL LANES MEDIAN PARKING PARKING PARKWAY PARKWAY SIDEWALK SIDEWALK PERMEABLE PERMEABLE BICYCLE LANE BICYCLE BICYCLE LANE BICYCLE

BIO-RETENTION/ 90 FT BIO-RETENTION/

R.O.W 165 Bissonnet Street

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Bissonnet - Middle (Chimney Rock to the West Loop)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANE, STREET H YRS 5-10 $14,850,066 • SIDEWALKS, TREES TO BE MAINTAINED BY TREES, BIO-INFILTRATION THE CITY, PAVER • STOCKING AND REPLACEMENT REQUIRED. IMPLEMENTATION PRIVATE PROPERTY • COMPENSATES CITY FOR DAMAGE

Bissonnet - East (West Loop to Rail Road Tracks)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANES, STREET M YRS 10-15 $12,363,192 • SIDEWALKS, TREES TO BE MAINTAINED BY TREES, BIO-INFILTRATION THE CITY, PAVER • STOCKING AND REPLACEMENT REQUIRED. PRIVATE PROPERTY • COMPENSATES CITY FOR DAMAGE

Bissonnet - South (Alder to Renwick)

STEP ONE - NEW STREET, SIDEWALKS, BIKE LANES, STREET L YRS 15-20 $3,974,460 • SIDEWALKS, TREES TO BE MAINTAINED BY TREES, BIO-INFILTRATION THE CITY, PAVER • STOCKING AND REPLACEMENT REQUIRED. PRIVATE PROPERTY • COMPENSATES CITY FOR DAMAGE

Key Map: Typical Section: Bissonnet Street

7 FT 6 FT 22 FT 22 FT 6 FT 7 FT R.O.W

TRAVEL LANES TRAVEL LANES PLANTER PLANTER SIDEWALK SIDEWALK

INFILTRATION INFILTRATION 70 FT INFILTRATION

R.O.W 166

IMPLEMENTATION West Loop Motor Courts

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

West Loop Motor Courts - General

STEP ONE - TRAFFIC IMPACT STUDY & DEDICATION OF ACCESS X M YR 1 TBD • MAINTAIN MOTOR COURT SURFACES LIKE A EASEMENTS STREET • IS MAINTAINED, MAINTAIN POCKET PARKS STEP TWO - EAST SIDE OF THE WEST LOOP M YRS 5-10 $1,590,758 IN THE • CENTER OF MOTOR COURTS, IRRIGATION BY STEP THREE - WEST SIDE OF THE WEST LOOP M YRS 10-15 $1,391,914 ADJACENT PRIVATE • PROPERTY

Converted Motor Court Locations Typical Example: Converted Motor Court WEST LOOP WEST BELLAIRE BLVD 167 The Coastal Prairie Park

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Coastal Prairie Park - General

STEP ONE - COASTAL PRAIRIE PARK PRELIMINARY DESIGN X H YR 1 TBD • AS NATIVE PRAIRIE LANDSCAPE THE PARK SHOULD BE DESIGNED IMPLEMENTATION • TO REQUIRE MINIMAL MAINTENANCE, STEP TWO - JOINT DEVELOPMENT AGREEMENTS WITH X H YR 1 TBD IRRIGATION CENTERPOINT, HCFCD, COH, COWU • FOR ESTABLISHMENT OF PLANT MATERIALS (2 YRS), • GRASSES MOWN ONCE A YEAR, NO FERTILIZATION OR EDGING

Coastal Prairie Park - South (Brays Bayou to Bellaire)

STEP ONE - GRADING, DETENTION, PLANTING, HIKE AND BIKE H YRS 1-5 $4,996,800 • BOTTOM OF DETENTION SWALES MAY NEED TRAILS, NEIGHBORHOOD CONNECTIONS SEDIMENT • REMOVAL EVERY TEN (10) TO TWENTY (20) STEP TWO - PEDESTRIAN BRIDGE AT BRAYS BAYOU / M YRS 5-10 $1,500,000 YRS. CONNECTION TO HERMANN PARK

Coastal Prairie Park - North (Bellaire to Westpark)

STEP ONE - GRADING, DETENTION, PLANTING, HIKE AND BIKE H YRS 10-15 $2,712,240 TRAILS, NEIGHBORHOOD CONNECTIONS

STEP TWO - ADVOCATE FOR CONNECTION TO RICHMOND / X H YRS 5-10 TBD MEMORIAL PARK WITH COH

Typical Section: Coastal Prairie Park Existing Centerpoint Easements

SECTION C - C1 168

IMPLEMENTATION North Livable Center

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Planning

STEP ONE - DEVELOP AN URBAN DESIGN MASTER PLAN WITH X H YR 1 TBD STAKEHOLDER INPUT

STEP TWO - UPDATE COMPREHENSIVE PLAN TO INCENT MIXED- X H YR 1 TBD USE HIGH DENSITY DEVELOPMENT

STEP THREE - UPDATE COMPREHENSIVE PLAN REQUIRING X H YR 1 TBD EXTENSION OF ANDERSON ST NORTH FROM FOURNACE TO WESTPARK

STEP FOUR - UPDATE COMPREHENSIVE PLAN EXTENDING X H YR 1 TBD LEHIGH ST WEST TO SOUTH RICE

STEP FIVE- UPDATE COMPREHENSIVE PLAN TO DEDICATE X H YR 1 TBD NORTHPARK

STEP SIX- JOINT DEVELOPMENT AGREEMENTS WITH X H YR 1 TBD CENTERPOINT, HCFCD, COH, TXDOT

Proposed North Livable Center Conceptual Plan Infrastructure Parks andOpenSpace INITIATIVES &IMPLEMENTATION STRATEGIES A CONNECTOR STREET, WEST TO SOUTHRICE STEP THREE - ADVOCATE CONSTRUCTION OF LEHIGHSTREET, STREET, BETWEENFOURNACE AND WESTPARK STEP TWO -CONSTRUCT ANDERSON STREET, A CONNECTOR LEHIGH STREET STEP ONE-EXTEND WEST LOOP BOX CULVERT NORTH TO STEP TWO -BUILDNORTHPARK CENTERPOINT EASEMENT STEP ONE-BUILD THE NORTH COASTAL PRAIRIE PARK WITHIN

ANDERSON LN. P P EASEMENT PARK OFFICE + RETAIL OFFICE

WEST PARK

RETAIL + RESIDENTIAL RETAIL + RESIDENTIAL EASEMENT OVERHEAD CENTER POINT COMMERCIAL COMMERCIAL DETENTION PARK + OFFICE HOTEL PLAZA KIOSK FOOD KIOSK FOOD COASTAL PRAIRIE PARK EASEMENT RETAIL OFFICE

RETAIL + RESIDENTIAL EASEMENT EXTENSION STORM LINE PARK EXISTING EXISTING RETAIL EXISTING EXISTING MEDICAL MEDICAL EXISTING P P

LOW HANGING FRUIT CENTER POINT OVERHEAD EASEMENT H H H H H BANG FOR THE BUCK YRS 1-5 YRS 5-10 YRS 5-10 YRS 10-15 YRS 5-10 (YRS) FRAME TIME YRS 1-5 COSTS CAPITAL TBD

TO S. RICE AVENUE $6,081,134 $1,542,240 $593,184 YRS 5-10 COSTS CAPITAL $2,090,400 YRS 10-15 COSTS CAPITAL TO ANDERSON STREET

TO WESTPARK AVENUE YRS 10-20 COSTS CAPITAL • • O&M IMPLICATIONS ADDITIONAL PARKS MAINTENANCE SEE COASTAL PRAIRIE PARK

STORMWATER TRUNK LINE CONNECTION TO WEST LOOP WEST

IMPLEMENTATION 169 170

IMPLEMENTATION Urban Village Downtown

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

Planning

STEP ONE - CREATE A UVD REDEVELOPMENT MASTER PLAN X H YR 1 TBD WITH STAKEHOLDER INPUT, SITE PLANNING AND DESIGN GUIDELINES

STEP TWO - DEVELOP A SHARED PARKING ORDINANCE / X H YR 1 TBD • IF PARKING IS METERED FUND REQUIRED DISTRICT SUPPORT STAFF

STEP THREE - DEVELOP A SHARED DETENTION ORDINANCE X H YR 1 TBD

STEP FOUR - UPDATE COMPREHENSIVE PLAN ESTABLISHING A X H YR 1 TBD “BUILD-TO LINE” INCENTING ADAPTIVE RE-USE/ DENSITY

Complete / Parking Streets and Shared Detention

STEP ONE - BUILD TRANSITION ALLEY BETWEEN FERRIS AND X H YRS 1 • SIDEWALKS, TREES TO BE MAINTAINED BY 5TH (SOUTH OF BELLAIRE) THE CITY, PAVER • STOCKING AND REPLACEMENT REQUIRED. STEP TWO - BUILD COMPLETE STREETS - SPRUCE, CEDAR, H YRS 1-5 PRIVATE PROPERTY FERRIS AND 5TH (NORTH OF BELLAIRE) • COMPENSATES CITY FOR DAMAGE. SHARED DETENTION CELLS STEP THREE - BUILD COMPLETE STREETS - DASHWOOD AND H YRS 5-10 • SEDIMENT REMOVAL EVERY TEN (10) TO 5TH (SOUTH OF BELLAIRE) TWENTY (20) YRS

Typical Urban Village Downtown, Plan View

IMAGE COURTESY OF BUTLER PLANNING IMAGE COURTESY OF BUTLER PLANNING 171 City Gateways

TIME CAPITAL CAPITAL CAPITAL CAPITAL FRAME COSTS COSTS COSTS COSTS LOW HANGINGBANG FOR THE INITIATIVES & IMPLEMENTATION STRATEGIES FRUIT BUCK (YRS) YRS 1-5 YRS 5-10 YRS 10-15 YRS 10-20 O&M IMPLICATIONS

West Loop Gateways

STEP ONE - BELLAIRE BOULEVARD @ WEST LOOP X H YRS 1-5 • PAY FOR POWER AND MAINTENANCE OF COLUMNS AND ART UPLIGHTING IMPLEMENTATION • INCREASE SUPPLEMENTAL MAINTENANCE OF UNDERPASSES TO A STEP TWO - BISSONNET @ WEST LOOP M YRS 5-10 • QUARTERLY BASIS, CLEAN ART WALLS AS NEEDED, SHEAR GREEN WALLS/COLUMNS • TWICE ANNUALLY, MAINTAIN SPECIAL STEP THREE - FOURNACE PLACE @ WEST LOOP H YRS 1-5 PAVING AND ANNUALS • IRRIGATE GREEN WALLS AND PLANTINGS

STEP FOUR - EVERGREEN @ WEST LOOP M YRS 5-10

Perimeter Gateways

STEP ONE - BELLAIRE BOULEVARD @ RR TRACK X H YRS 1-5 • PAY FOR POWER AND MAINTENANCE OF COLUMNS AND GREEN WALLS UPLIGHTING • QUARTERLY BASIS, SHEAR GREEN WALLS/ STEP TWO - SOUTH RICE @ CYPRESS DITCH H YRS 1-5 COLUMNS • SHEAR GREEN WALLS/COLUMNS TWICE STEP THREE - BISSONNET @ RR TRACK H YRS 5-10 ANNUALLY • MAINTAIN SPECIAL PAVING IN STREET STEP FOUR - CHIMNEY ROCK @ CYPRESS DITCH M YRS 10-15 • IRRIGATE GREEN WALLS AND PLANTINGS • MEDIAN PLANTINGS LANDSCAPE STEP FIVE- FERRIS @ CYPRESS DITCH L YRS 15-20 MAINTENANCE

Key Map: After

Before

LEGEND:

West Loop City Gateway Perimeter City Gateway Bellaire Water Gardens — West City Gateway

Initiative Cost Estimates REMARKS REMARKS REMARKS $5,400,000 $9,625,000 $1,925,000 $11,550,000 $1,300,000 $6,437,500 $1,287,500 $7,725,000 $4,225,000 $5,137,500 $5,050,000 $5,975,000 $6,050,000 $650,000 $1,140,000 $228,000 $1,368,000 SUB-TOTAL $4,625,000 SUB-TOTAL $2,425,000 SUB-TOTAL $490,000 $500 $500 $500 $500 $500 $500 $500 $500 $/UNIT $500 $/UNIT $500 $/UNIT $500 LF LF LF LF LF LF LF LF UNIT LF UNIT LF UNIT LF 10800 2600 8450 10275 10100 11950 12100 1300 QTY 9250 QTY 4850 QTY 980 HARD COSTS TOTAL HARD COSTS @20% COSTS SOFT COST PROJECT TOTAL HARD COSTS TOTAL HARD COSTS @20% COSTS SOFT COST PROJECT TOTAL B Ave Ferris, Evergreen, Newcastle, Three - Fournace, Step B AVE CHIMNEY ROCK CHIMNEY FERRIS SOUTH RICE EVERGREEN HARD COSTS TOTAL HARD COSTS @20% COSTS SOFT COST PROJECT TOTAL Rock Chimney Rice, South Bissonnet, - Bellaire Blvd, Two Step BISSONNET NEWCASTLE ITEM FOURNACE SOUTH RICE POWER LINES SOUTH RICE POWER BELLAIRE BLVD ITEM BELLAIRE POWER LINES BELLAIRE POWER Step One - Bellaire @ South Rice Intersection Rice - Bellaire @ South One Step ITEM Initiative: Bury Overhead Power Lines Power Overhead Bury Initiative:

174 IMPLEMENTATION Initiative: NeighborhoodStreets SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN TOTAL PROJECT COST NUMBER OF CORNERS TOTAL COST EACHCORNER SOFT COSTS @20% HARD COSTS TOTAL BELLAIRE SIGNAGE PLANTING AND IRRIGATION BACK EDGECURB SIDEWALK CURBRAMPS CORNER PLAZA PAVERS DETECTABLE PAVERS NEW CURB AND GUTTER ADJUST UTILITY BOXES TO GRADE REMOVE /RELOCATE EXIST SIGNAGE REMOVE EXIST PAVING /LANDSCAPE REMOVE EXISTING CURB AND GUTTER ITEM CONCRETE SIDEWALKS ITEM Sidewalks (200’ Segment) REPAIR ADJACENT LANDSCAPE Bellaire Intersection without Art (1Corner) COST PERFOOT TOTAL PROJECT COST SOFT COSTS @20% HARD COSTS TOTAL 300 1 255 32 2 195 18 98 1 1 800 54 QTY 900 QTY 800 LS SF LF EA LF SF LF LS LS SF LF UNIT SF UNIT SF $3,000 $8 $18 $1,000 $18 $10 $18 $1,500 $500 $3 $5 $/UNIT $11 $/UNIT $10 $5,390,100 $17,967 $2,995 $14,973 $3,000 $2,040 $576 $2,000 $3,413 $180 $1,764 $1,500 $500 $2,400 $270 SUB-TOTAL $9,900 SUB-TOTAL $8,000 $107 $21,480 $3,580 $17,900 REMARKS RETENTION GARDENS 4.5’ WIDE WINDOW PANE FINISH, TURNDOWN EDGE AT BIO- REMARKS LANDSCAPE, WALKS, DRIVES,

IMPLEMENTATION 175 WOOD OR WROUGHT IRON WROUGHT OR WOOD REMARKS CONCRETE PRE-CAST TILE OVER 42” HIGH - MOSAIC $2,000 $576 $2,040 $3,000 $33,273 $6,655 $39,927 $11,978,100 $3,600 SUB-TOTAL $270 $2,400 $500 $1,500 $1,764 $180 $3,413 $14,700 $1,000 $18 $8 $3,000 $200 $/UNIT $5 $3 $500 $1,500 $18 $10 $18 $75 EA LF SF LS LF UNIT LF SF LS LS LF SF LF SFF 2 32 255 1 300 18 QTY 54 800 1 1 98 18 195 196 SIDEWALK CURB RAMPS SIDEWALK EDGE CURB BACK AND IRRIGATION PLANTING BELLAIRE SIGNAGE TOTAL HARD COSTS @20% COSTS SOFT EACH CORNER COST TOTAL CORNERS NUMBER OF COST PROJECT TOTAL BENCH REMOVE EXISTING CURB AND GUTTER CURB EXISTING REMOVE Bellaire Intersection with Art (1 Corner) with Bellaire Intersection ITEM REMOVE EXIST PAVING / LANDSCAPE PAVING EXIST REMOVE SIGNAGE EXIST / RELOCATE REMOVE GRADE TO BOXES UTILITY ADJUST AND GUTTER CURB NEW PAVERS DETECTABLE PAVERS PLAZA CORNER WALL ART THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3M PER MILE FOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2 LANE SECTION. SIDEWALKS, PARKWAY GREEN PARKWAY SIDEWALKS, 2 LANE SECTION. A PER MILE FOR AND $3.8M 3-LANE SECTION A $4.3M PER MILE FOR OF COST A AT AND UTILITIES THE STREET OF RECONSTRUCTION INCLUDES THIS ESTIMATE COSTS LOWERING DRAMATICALLY THE STREET RE-CONSTRUCTING WITHOUT BE IMPLEMENTED BIO-RETENTION GARDENS CAN BIKE LANES, DEDICATED SPACES, Initiative: Neighborhood Streets (cont’d) Streets Neighborhood Initiative:

176 IMPLEMENTATION SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN GRAVEL BACKFILL DRIVEWAY APRON PRE-CAST CONCRETE SLOTTED CURB CIP CONC GUTTER WITH TURN DOWN EDGE 4” PERFORATED PIPEINBRG(3) CATCH BASIN &OVERFLOW PIPE EXCAVATE SOIL TO SUB-GRADE ADJUST UTILITY BOXES TO GRADE REMOVE /RELOCATE EXIST SIGNAGE REMOVE EXIST PAVING /LANDSCAPE REMOVE EXISTING CURB AND GUTTER ITEM Bio-Retention Gardens (200’ Segment -Existing Street) TOTAL PROJECT COST LINEAL FEET OF BIO-RETENTIONGARDENS COST PERFOOT TOTAL PROJECT COST SOFT COSTS @20% HARD COSTS TOTAL IRRIGATION ADJUSTMENTS PLANTING, MULCH,FINEGRADING PREPARED SOIL 111 200 144 200 600 1 178 1 1 1200 200 QTY 212,500 1200 1200 67 CY LF SF LF LF EA CY LS LS SF LF UNIT SF SF CY $30 $15 $18 $30 $8 $2,500 $15 $3,000 $500 $3 $5 $/UNIT $1 $8 $50 $3,330 $3,000 $2,592 $6,000 $4,800 $2,500 $2,670 $3,000 $500 $3,600 $1,000 SUB-TOTAL $60,106,050 $282.85 $56,570 $9,428 $47,142 $1,200 $9,600 $3,350 2.5’ DEEP,GRADATED WRAPPED INFILTER FABRIC REMARKS

IMPLEMENTATION 177 REMARKS WIDE 4.5’ STREET OF SIDES BOTH REMARKS FABRIC IN FILTER WRAPPED DEEP, GRADATED 2.5’ $238,067 $59,892 $133,088 $27,500 $50,000 $605,207 $151,302 $756,509 $3,782.54 SUB-TOTAL $96,660 SUB-TOTAL $3,600 $1,246 $2,500 $4,800 $4,000 $1,728 $3,000 $3,330 $3,350 $9,600 $1,200 $38,354 $7,671 $46,025 $230.12 $48,901,350 $236 $14,973 $33,272 $5,500 $50,000 $/UNIT $90 $/UNIT $3 $7 $2,500 $8 $20 $12 $15 $30 $50 $8 $1 LF EA EA EA LS UNIT LF UNIT SF CY EA LF LF SF LF CY CY SF SF 1010 4 4 5 1 QTY 1080 QTY 1200 178 1 600 200 144 200 111 67 1200 1200 212,500 BIO-RETENTION GARDENS ART WITHOUT BELLAIRE INTERSECTIONS ART WITH BELLAIRE INTERSECTIONS O.C.) (120’ LIGHTING STREET SIGNAGE TOTAL HARD COSTS @25% COSTS SOFT COST PROJECT TOTAL PER FOOT COST ITEM SIDEWALK REMOVE EXIST PAVING / LANDSCAPE PAVING EXIST REMOVE COST PROJECT TOTAL Bio-Retention Gardens (200’ Segment - New Street) - New Segment (200’ Gardens Bio-Retention ITEM EXCAVATE SOIL TO SUB-GRADE TO SOIL EXCAVATE PIPE & OVERFLOW BASIN CATCH PIPE IN BRG (3) 4” PERFORATED EDGE TURN DOWN WITH GUTTER CONC CIP CURB SLOTTED CONCRETE PRE-CAST APRON DRIVEWAY BACKFILL GRAVEL SOIL PREPARED PLANTING, MULCH, FINE GRADING ADJUSTMENTS IRRIGATION TOTAL HARD COSTS @20% COSTS SOFT COST PROJECT TOTAL PER FOOT COST BIO-RETENTION GARDENS OF FEET LINEAL intersections) Two Block, Length, One (600’ Neighborhood Street - Prototypical Two Step THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3M PER MILE FOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2 LANE SECTION. SIDEWALKS, PARKWAY GREEN PARKWAY SIDEWALKS, 2 LANE SECTION. A PER MILE FOR AND $3.8M 3-LANE SECTION A $4.3M PER MILE FOR OF COST A AT AND UTILITIES THE STREET OF RECONSTRUCTION INCLUDES THIS ESTIMATE COSTS LOWERING DRAMATICALLY THE STREET RE-CONSTRUCTING WITHOUT BE IMPLEMENTED BIO-RETENTION GARDENS CAN BIKE LANES, DEDICATED SPACES, Initiative: Neighborhood Streets (cont’d) Streets Neighborhood Initiative:

178 IMPLEMENTATION Initiative: Connector Streets SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE BIO-RETENTION GARDEN PLANTING AND IRRIGATION TREES DRIVEWAY REPLACEMENTS SIDEWALKS ADJUST UTILITY BOXES TO GRADE REMOVE /RELOCATE EXIST SIGNAGE DEMOLITION ITEM Streetscape Elements Newcastle (200’ prototype) COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE BIO-RETENTION GARDEN PLANTING AND IRRIGATION TREES DRIVEWAY REPLACEMENTS BIKE LANE SIDEWALKS ADJUST UTILITY BOXES TO GRADE REMOVE /RELOCATE EXIST SIGNAGE DEMOLITION ITEM Streetscape Elements Fournace, Ferris,Evergreen (200’ prototype) 1 200 1000 10 480 900 1 1 4000 QTY 1 200 2400 10 480 1200 1800 1 1 6600 QTY LS LF SF EA SF SF LS LS SF UNIT LS LF SF EA SF SF SF LS LS SF UNIT $5,000 $345 $3 $450 $10 $10 $1,500 $500 $3 $/UNIT $5,000 $282 $3 $450 $10 $12 $10 $1,500 $500 $3 $/UNIT $546.50 $109,300 $109,300 $5,000 $69,000 $3,000 $4,500 $4,800 $9,000 $1,500 $500 $12,000 SUB-TOTAL $660.50 $132,100 $132,100 $5,000 $56,400 $7,200 $4,500 $4,800 $14,400 $18,000 $1,500 $500 $19,800 SUB-TOTAL 200 REMARKS 200 REMARKS

IMPLEMENTATION 179 REMARKS REMARKS REMARKS REMARKS SUB-TOTAL $4,435,704 $972,000 $2,160,000 $7,567,704 $1,513,541 $9,081,245 SUB-TOTAL $5,997,420 $720,000 $1,600,000 $8,317,420 $1,663,484 $9,980,904 SUB-TOTAL $3,845,160 $630,000 $1,400,000 $5,875,160 $1,175,032 $7,050,192 SUB-TOTAL $3,096,060 $144,000 $320,000 $3,560,060 $712,012 $4,272,072 $/UNIT $546 $18,000 $40,000 $/UNIT $660 $18,000 $40,000 $/UNIT $660 $18,000 $40,000 $/UNIT $660 $18,000 $40,000 UNIT LF EA EA UNIT LF EA EA UNIT LF EA EA UNIT LF EA EA QTY 8124 54 54 QTY 9087 40 40 QTY 5826 35 35 QTY 4691 8 8 INTERSECTIONS W/O ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST ITEM ELEMENTS STREETSCAPE ITEM ELEMENTS STREETSCAPE INTERSECTIONS W/O ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST Ferris ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST Newcastle ITEM ELEMENTS STREETSCAPE STREETSCAPE ELEMENTS ELEMENTS STREETSCAPE Fournace ITEM INTERSECTIONS W/O ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST Evergreen Initiative: Connector Streets (cont’d) Streets Connector Initiative:

180 IMPLEMENTATION Initiative: BellaireBoulevard SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE BIO-RETENTION GARDEN PLANTING AND IRRIGATION TREES DRIVEWAY REPLACEMENTS BIKE LANE Bellaire Blvd MiddleStreet /Streetscape Elements (200’ prototype) COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE BIO-RETENTION GARDEN PLANTING AND IRRIGATION TREES DRIVEWAY REPLACEMENTS BIKE LANE SIDEWALKS STREET EDGERECONSTRUCTION ITEM SIDEWALKS STREET RECONSTRUCTION ITEM Bellaire Blvd West Street /Streetscape Elements (200’ prototype) 1 400 2400 10 480 2400 1 400 2400 10 480 2400 2400 2400 QTY 3200 400 QTY LS LF SF EA SF SF LS LF SF EA SF SF SF SF UNIT SF LF UNIT $5,000 $230 $3 $450 $10 $12 $5,000 $230 $3 $450 $10 $12 $10 $20 $/UNIT $10 $815 $/UNIT $5,000 $92,000 $7,200 $4,500 $4,800 $28,800 $5,000 $92,000 $7,200 $4,500 $4,800 $28,800 $1,071.50 $214,300 $214,300 $2,501.50 $500,300 $500,300 $24,000 $48,000 SUB-TOTAL $32,000 $326,000 SUB-TOTAL NARROWER LANES RE-STRIPPED 6’ ONEDGEORROADS REMOVED, INLETS ADJUSTED, REMARKS BASED ON4.3MPERMILE REMARKS

IMPLEMENTATION 181 REMARKS EACH SIDE 1920 SF EACH CROSSING 320 SF REMARKS BIO-RETENTION REMARKS ON 4.3M PER MILE BASED 3 LANE STREET $24,000 $28,800 $4,800 $4,500 $7,200 $92,000 $5,000 $492,300 $492,300 $2,461.50 SUB-TOTAL $7,666,128 $138,240 $11,200 $0 $0 $7,815,568 $1,563,114 $9,378,682 SUB-TOTAL $1,950,000 $1,000,000 $487,942 $250,000 $3,687,942 $737,588 $4,425,530 SUB-TOTAL $326,000 $10 $12 $10 $450 $3 $230 $5,000 $/UNIT $2,502 $18 $18 $18,000 $40,000 $/UNIT $12 $1,000,000 $383 $250,000 $/UNIT $815 SF SF SF EA SF LF LS UNIT LF SF SF EA EA UNIT SF LS LF LS UNIT LF 2400 2400 480 10 2400 400 1 QTY 3064 7680 640 0 0 QTY 162500 1 1274 1 QTY 400 PAVER INTERSECTIONS PASEO INTERSECTIONS PAVER ART W/O INTERSECTIONS ACTIVATORS AND ARTS PARK DEVELOPMENT PARK ITEM STREETS - STREETSCAPE ELEMENTS ELEMENTS - STREETSCAPE STREETS SIDEWALKS BIKE LANE REPLACEMENTS DRIVEWAY TREES AND IRRIGATION PLANTING BIO-RETENTION GARDEN BELLAIRE SIGNAGE TOTAL HARD COSTS TOTAL COST PER FOOT COST Rock) - Chimney Rice (South / Streetscape Streets West Bellaire ITEM TYPICAL INTERSECTIONS PAVER ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST West Park Paseo GARDENS WATER BELLAIRE ROCK CHIMNEY TO MEDIAN BISSONNET TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST STREET EDGE RECONSTRUCTION STREET Bellaire Blvd East Street / Streetscape Elements (200’ prototype) (200’ Elements / Streetscape Street East Bellaire Blvd ITEM THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3M PER MILE FOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2 LANE SECTION. SIDEWALKS, PARKWAY GREEN PARKWAY SIDEWALKS, 2 LANE SECTION. A PER MILE FOR AND $3.8M 3-LANE SECTION A $4.3M PER MILE FOR OF COST A AT AND UTILITIES THE STREET OF RECONSTRUCTION INCLUDES THIS ESTIMATE COSTS LOWERING DRAMATICALLY THE STREET RE-CONSTRUCTING WITHOUT BE IMPLEMENTED BIO-RETENTION GARDENS CAN BIKE LANES, DEDICATED SPACES, Initiative: Bellaire Boulevard (cont’d) Boulevard Bellaire Initiative:

182 IMPLEMENTATION TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL ARTS AND ACTIVATORS MEDIAN BISSONNET TO CHIMNEY ROCK BELLAIRE WATER GARDENS PARK DEVELOPMENT ITEM Paseo Park West COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART PAVER INTERSECTIONS PASEO PAVER INTERSECTIONS TYPICAL STREETS -STREETSCAPE ELEMENTS ITEM Bellaire West Streets /Streetscape (South Rice -Chimney Rock) COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE BIO-RETENTION GARDEN PLANTING AND IRRIGATION TREES DRIVEWAY REPLACEMENTS BIKE LANE SIDEWALKS STREET EDGERECONSTRUCTION ITEM Bellaire Blvd East Street /Streetscape Elements (200’ prototype) 1 1274 1 162500 QTY 0 0 640 7680 3064 QTY 1 400 2400 10 480 2400 2400 400 QTY LS LF LS SF UNIT EA EA SF SF LF UNIT LS LF SF EA SF SF SF LF UNIT $250,000 $383 $1,000,000 $12 $/UNIT $40,000 $18,000 $18 $18 $2,502 $/UNIT $5,000 $230 $3 $450 $10 $12 $10 $815 $/UNIT $4,425,530 $737,588 $3,687,942 $250,000 $487,942 $1,000,000 $1,950,000 SUB-TOTAL $9,378,682 $1,563,114 $7,815,568 $0 $0 $11,200 $138,240 $7,666,128 SUB-TOTAL $2,461.50 $492,300 $492,300 $5,000 $92,000 $7,200 $4,500 $4,800 $28,800 $24,000 $326,000 SUB-TOTAL BIO-RETENTION REMARKS 320 SF EACHCROSSING 1920 SF EACHSIDE REMARKS 3 LANESTREET BASED ON4.3M PERMILE REMARKS SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART MEDIAN LANDSCAPE PAVER INTERSECTIONS TYPICAL Bellaire East Streets /Streetscape Loop -RR /Medians (West Tracks) COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL MEDIAN 1ST STREET TO WEST LOOP ART / ACTIVATORS Paseo Park Middle COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART PAVER INTERSECTIONS TYPICAL STREETS -STREETSCAPE ELEMENTS ITEM PARK DEVELOPMENT ITEM STREETS -STREETSCAPE ELEMENTS ITEM Bellaire MiddleStreets /Streetscape (South Rice - West Loop) 7 7 148160 30800 7350 1 6 6 59370 2594 QTY 207875 QTY 2594 QTY EA EA SF SF SF LS EA EA SF LF UNIT SF UNIT LF UNIT $40,000 $18,000 $8 $18 $8 $300,000 $40,000 $18,000 $18 $1,072 $/UNIT $12 $/UNIT $1,072 $/UNIT $280,000 $126,000 $1,185,280 $554,400 $58,800 $300,000 $240,000 $108,000 $1,068,660 $5,911,738 $985,290 $4,926,448 $3,423,960 $570,660 $2,853,300 $5,036,914 $839,486 $4,197,428 $2,780,768 SUB-TOTAL $2,494,500 SUB-TOTAL $2,780,768 SUB-TOTAL RR TACKS, NEWCASTLE, AVE. B 1920 SF EACHSIDE REMARKS REMARKS REMARKS

IMPLEMENTATION 183 25% OF STREET LENGTH STREET 25% OF 4’ WIDE ROSES 4’ WIDE ROSES 4’ 75% OF STREET LENGTH STREET OF 75% REMARKS ANDERSON DITCH 200’, PINE, EVERGREEN, / CYPRESS GATEWAY CITY REMARKS ELM REMARKS / LF = $720 2 LANES $5,000 $438,700 $438,700 $2,193.50 $468,000 $1,000,000 $14,145,772 $2,829,154 $16,974,926 $162,000 $360,000 $6,278,462 $1,255,692 $7,534,154 $14,000 $185,520 $85,720 $24,000 $19,200 $4,800 $4,500 $7,200 $72,000 SUB-TOTAL $12,282,012 $210,240 SUB-TOTAL $5,623,222 $47,520 SUB-TOTAL $288,000 $5,000 $18,000 $40,000 $18,000 $40,000 $140 $40 $40 $10 $12 $10 $450 $3 $240 $/UNIT $2,194 $18 $/UNIT $2,194 $18 $/UNIT $720 LS EA EA EA EA LF LF LF SF SF SF EA SF LF UNIT LF SF UNIT LF SF UNIT LF 1 26 25 9 9 100 4638 2143 2400 1600 480 10 2400 300 QTY 5598 11,680 QTY 2563 2,640 QTY 400 BELLAIRE SIGNAGE TOTAL HARD COSTS COST TOTAL PER FOOT COST Ditch) - Cypress (Bellaire Blvd / Streetscape - Streets - South Rice South INTERSECTIONS W/O ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST (Elm- Bellaire Blvd) / Streetscape - North - Streets Rice South ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST PERVIOUS PAVING PARALLEL PARKING PARALLEL PAVING PERVIOUS MEDIAN PLANTING MEDIAN PLANTING SIDEWALKS BIKE LANE REPLACEMENTS DRIVEWAY TREES AND IRRIGATION PLANTING BIO-RETENTION GARDEN STREETS - STREETSCAPE ELEMENTS ELEMENTS - STREETSCAPE STREETS ITEM STREETS - STREETSCAPE ELEMENTS ELEMENTS - STREETSCAPE STREETS ITEM TYPICAL INTERSECTIONS PAVER TYPICAL INTERSECTIONS PAVER South Rice Street / Streetscape Elements (200’ prototype) (200’ Elements / Streetscape Street Rice South ITEM RECONSTRUCTION STREET NEW THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3M PER MILE FOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2 LANE SECTION. SIDEWALKS, PARKWAY GREEN PARKWAY SIDEWALKS, 2 LANE SECTION. A PER MILE FOR AND $3.8M 3-LANE SECTION A $4.3M PER MILE FOR OF COST A AT AND UTILITIES THE STREET OF RECONSTRUCTION INCLUDES THIS ESTIMATE COSTS LOWERING DRAMATICALLY THE STREET RE-CONSTRUCTING WITHOUT BE IMPLEMENTED BIO-RETENTION GARDENS CAN BIKE LANES, DEDICATED SPACES, Initiative: South Rice Avenue Rice South Initiative:

184 IMPLEMENTATION Initiative: Chimney Rock Road SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART MEDIAN PLANTING Chimney Rock -NorthStreets /Streetscape (Dashwood -Bissonnet) COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART MEDIAN PLANTING PAVER INTERSECTIONS TYPICAL Chimney Rock -South -Streets /Streetscape (Evergreen -Cypress Ditch) COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE BIO-RETENTION GARDEN PLANTING AND IRRIGATION TREES DRIVEWAY REPLACEMENTS BIKE LANE STREETS -STREETSCAPE ELEMENTS ITEM STREETS -STREETSCAPE ELEMENTS ITEM SIDEWALKS NEW STREET RECONSTRUCTION ITEM Chimney Rock Street /Streetscape Elements (200’ prototype) 0 0 1277 3 3 2589 5,400 1 400 2400 10 480 1600 1457 QTY 3069 QTY 2400 400 QTY EA EA LF EA EA LF SF LS LF SF EA SF SF LF UNIT LF UNIT SF LF UNIT $40,000 $18,000 $40 $40,000 $18,000 $40 $18 $5,000 $240 $3 $450 $10 $12 $2,194 $/UNIT $2,194 $/UNIT $10 $720 $/UNIT $0 $0 $51,080 $120,000 $54,000 $103,560 $97,200 $5,000 $96,000 $7,200 $4,500 $4,800 $19,200 $3,897,286 $649,548 $3,247,738 $8,529,775 $1,421,629 $7,108,146 $2,243.50 $448,700 $448,700 $3,196,658 SUB-TOTAL $6,733,386 SUB-TOTAL $24,000 $288,000 SUB-TOTAL 4’ WIDE ROSES 4’ WIDE ROSES EVERGREEN REMARKS REMARKS 2 LANES =$720 /LF REMARKS

IMPLEMENTATION 185 PAVERS ON STREET OC 25’ OC 25’ REMARKS REMARKS WIDE 44’ X LONG 200’ REMARKS / LF = $720 2 LANES $78,000 $0 $4,800 $7,200 $0 $48,000 $5,000 $431,000 $431,000 $2,155.00 SUB-TOTAL $12,027,055 $108,000 $240,000 $12,375,055 $2,475,011 $14,850,066 SUB-TOTAL $9,680,260 $158,400 $144,000 $320,000 $10,302,660 $2,060,532 $12,363,192 SUB-TOTAL $288,000 $15 $12 $10 $450 $3 $3,000 $5,000 $/UNIT $2,155 $18,000 $40,000 $/UNIT $2,155 $18 $18,000 $40,000 $/UNIT $720 SF SF SF EA SF LF LS UNIT LF EA EA UNIT LF SF EA EA UNIT LF 5200 0 480 16 0 16 1 QTY 5581 6 6 QTY 4492 8800 8 8 QTY 400 BIKE LANE REPLACEMENTS DRIVEWAY AND IRRIGATION PLANTING BELLAIRE SIGNAGE ART W/O INTERSECTIONS ITEM ELEMENTS - STREETSCAPE STREETS STREETS - STREETSCAPE ELEMENTS ELEMENTS - STREETSCAPE STREETS SIDEWALKS TREES PLANTERS INFILTRATION TOTAL HARD COSTS TOTAL COST PER FOOT COST Loop) West - Rock (Chimney / Streetscape - Middle - Streets Bissonnet ITEM ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST Tracks) (West - RR Loop / Streetscape - Streets - East Bissonnet GATEWAY CITY AT IN STREET PAVERS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST NEW STREET RECONSTRUCTION STREET NEW Bissonnet Street / Streetscape Elements (200’ prototype) (200’ Elements / Streetscape Street Bissonnet ITEM THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3M PER MILE FOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2 LANE SECTION. SIDEWALKS, PARKWAY GREEN PARKWAY SIDEWALKS, 2 LANE SECTION. A PER MILE FOR AND $3.8M 3-LANE SECTION A $4.3M PER MILE FOR OF COST A AT AND UTILITIES THE STREET OF RECONSTRUCTION INCLUDES THIS ESTIMATE COSTS LOWERING DRAMATICALLY THE STREET RE-CONSTRUCTING WITHOUT BE IMPLEMENTED BIO-RETENTION GARDENS CAN BIKE LANES, DEDICATED SPACES, Initiative: Bissonnet Street Bissonnet Initiative:

186 IMPLEMENTATION TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART STREETS -STREETSCAPE ELEMENTS ITEM Bissonnet -South -Streets /Streetscape (Alder -Renwick) 1 1 1510 QTY EA EA LF UNIT $40,000 $18,000 $2,155 $/UNIT $40,000 $18,000 $3,974,460 $662,410 $3,312,050 $3,254,050 SUB-TOTAL REMARKS

IMPLEMENTATION 187 20’ X 40’ X 20’ 40’ X 20’ REMARKS $8,100 $500 $1,500 $1,764 $80,500 $2,000 $12,000 $24,000 $40,440 $3,000 $165,704 $33,141 $198,845 $1,391,914 SUB-TOTAL $1,000 $3 $500 $1,500 $18 $18 $1,000 $15 $200 $8 $3,000 $/UNIT $5 SF LS LS LF SF EA SF LF SF LS UNIT LF 2700 1 1 98 4600 2 800 120 5055 1 7 QTY 200 REMOVE / RELOCATE EXIST SIGNAGE EXIST / RELOCATE REMOVE GRADE TO BOXES UTILITY ADJUST AND GUTTER CURB NEW PAVERS PLAZA COURT MOTOR CURB RAMPS SIDEWALK PARK POCKET AND GATE WALL COURT AND IRRIGATION PLANTING BELLAIRE SIGNAGE TOTAL HARD COSTS @20% COSTS SOFT EACH COST TOTAL COURTS NUMBER OF TOTAL PROJECT COST PROJECT TOTAL REMOVE EXIST PAVING / LANDSCAPE PAVING EXIST REMOVE REMOVE EXISTING CURB AND GUTTER CURB EXISTING REMOVE West Loop Motor Court West Court Motor Loop West ITEM THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3M PER MILE FOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2 LANE SECTION. SIDEWALKS, PARKWAY GREEN PARKWAY SIDEWALKS, 2 LANE SECTION. A PER MILE FOR AND $3.8M 3-LANE SECTION A $4.3M PER MILE FOR OF COST A AT AND UTILITIES THE STREET OF RECONSTRUCTION INCLUDES THIS ESTIMATE COSTS LOWERING DRAMATICALLY THE STREET RE-CONSTRUCTING WITHOUT BE IMPLEMENTED BIO-RETENTION GARDENS CAN BIKE LANES, DEDICATED SPACES, Initiative: West Loop Motor Courts Motor Loop West Initiative:

188 IMPLEMENTATION SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN TOTAL PROJECT COST NUMBER OF COURTS TOTAL COST EACH SOFT COSTS @20% HARD COSTS TOTAL BELLAIRE SIGNAGE PLANTING AND IRRIGATION COURT WALL AND GATE POCKET PARK SIDEWALK CURBRAMPS MOTOR COURT PLAZA PAVERS NEW CURB AND GUTTER ADJUST UTILITY BOXES TO GRADE REMOVE /RELOCATE EXIST SIGNAGE REMOVE EXIST PAVING /LANDSCAPE REMOVE EXISTING CURB AND GUTTER ITEM West Loop Motor Court East 8 1 5055 120 800 2 4600 98 1 1 2700 200 QTY LS SF LF SF EA SF LF LS LS SF LF UNIT $3,000 $8 $200 $15 $1,000 $18 $18 $1,500 $500 $3 $5 $/UNIT $1,590,758 $198,845 $33,141 $165,704 $3,000 $40,440 $24,000 $12,000 $2,000 $80,500 $1,764 $1,500 $500 $8,100 $1,000 SUB-TOTAL 20’ X 40’ 20’ X 40’ REMARKS

IMPLEMENTATION 189 BRAYS TO BELLAIRE TO BRAYS BRAYS TO BELLAIRE; 150 LF AVG. +RR X-ING +RR AVG. BELLAIRE; 150 LF TO BRAYS BRAYS TO BELLAIRE; 10’ WIDE BELLAIRE; 10’ TO BRAYS TRAILS ALONG BELLAIRE; TO BRAYS OC 75’ BRAYS TO BELLAIRE TO BRAYS REMARKS BELLAIRE TO BRAYS WIDE BELLAIRE; 6’ TO BRAYS AREA OF BELLAIRE; 1/3 TO BRAYS $30,000 $300,000 $750,000 $12,000 $550,000 $4,164,000 $832,800 $4,996,800 $50,000 $30,000 UNIT TOTAL $1,200,000 $450,000 $792,000 $30,000.00 $100,000.00 $100.00 $0.06 $5,500.00 $50,000.00 $30,000.00 $/UNIT $0.50 $60.00 $0.44 LS EA LF SF EA LS LS UNIT SF LF SF 1 3 7,500 200,000 100 1 1 QTY 2,400,000 7,500 1,800,000 PAINT/MARKINGS/SIGNAGE N’HOOD CONNECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST PED LIGHTING 10’ BIKE LANE 10’ BERMUDA SEED - COMMON EARTHWORK SITE FURNISHINGS ALLOWANCE LIGHTING & SITE FURNISHINGS DRAINAGE PLANTING & IRRIGATION MIX TRAIL SEED - NATIVE HARDSCAPE WALK CONCRETE 6’ DEMOLITION & GRADING DEMOLITION South ITEM Initiative: Coastal Prairie Park Prairie Coastal Initiative:

190 IMPLEMENTATION SITE FURNISHINGS SITE FURNISHINGS FURNISHINGS SITE ALLOWANCE DRAINAGE SEED -NATIVE TRAIL MIX IRRIGATION & PLANTING 6’ CONCRETE WALK HARDSCAPE DEMOLITION &GRADING ITEM North EARTHWORK EARTHWORK TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL PEDESTRIAN LIGHTING SEED -COMMON BERMUDA 10’ BIKELANE N’HOOD CONNECTIONS PAINT/MARKINGS/SIGNAGE 1 1 530,000 6,500 723,000 QUANTITY 65 50,000 6,500 2 1 LS LS SF LF SF UNIT SF LF EA LS 5500 $20,000.00 $25,000.00 $0.44 $60.00 $0.50 COST UNIT $0.06 $100.00 $100,000.00 $20,000.00 $2,712,240 $452,040 $2,260,200 $357,500 $20,000 $25,000 $233,200 $390,000 $361,500 TOTAL UNIT $3,000 $650,000 $200,000 $20,000 BELLAIRE TO WESTPARK BELLAIRE TO WESTPARK BRAYS TO BELLAIRE;6’ WIDE BELLAIRE TO WESTPARK REMARKS BELLAIRE TO WESTPARK; ALONG TRAILS BRAYS TO BELLAIRE;10’ WIDE BELLAIRE TO WESTPARK; 150LF AVG. +RR X-ING BELLAIRE TO WESTPARK

IMPLEMENTATION 191 REMARKS 200 REMARKS AN GLENMONT BEGIN ON REYTECH BID, BASED WIDE CORRIDOR 12’ SUB-TOTAL $5,067,612 $5,067,612 $1,013,522 $6,081,134 SUB-TOTAL $882,000 $100,800 $201,600 $100,800 $1,285,200 $257,040 $1,542,240 $/UNIT $1,474 $/UNIT $1,050 $10 $20 $10 UNIT LF UNIT LF SF SF SF QTY 3438 QTY 840 10080 10080 10080 HARD COSTS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST ITEM ELEMENTS / STREETSCAPE STREET 9’ X 7’ R C BOX CULVERT R C BOX 7’ X 9’ Extend West Lop Box Culvert Box Lop West Extend ITEM MISC TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST Park)West to (Fournace Street Anderson Extend DEMO SURFACE CONDITION SURFACE RESTORE Initiative: North Livable Center Livable North Initiative:

192 IMPLEMENTATION Initiative: NorthLivable Center (cont’d) TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL PEDESTRIAN LIGHTING ITEM EARTHWORK SEED -COMMON BERMUDA PAINT/MARKINGS/SIGNAGE 10’ BIKELANE TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL PARK DEVELOPMENT NORTHPARK BUILD SITE FURNISHINGS FURNISHINGS SITE ALLOWANCE DRAINAGE SEED -NATIVE TRAIL MIX IRRIGATION & PLANTING 6’ CONCRETE WALK HARDSCAPE DEMOLITION &GRADING ITEM Coastal Prairie Park QTY SF LS LF 87100 LS LS SF LF SF UNIT 5500 UNIT $0.06 $20,000.00 $100.00 SF $20,000.00 $25,000.00 $0.44 $60.00 $1.00 $/UNIT $593,184 $98,864 $494,320 $77,000 $/UNIT $960 $20,000 $80,000 $20 $20,000 $25,000 $63,360 $48,000 $160,000 SUB-TOTAL SUB-TOTAL $2,090,400 $348,400 $1,742,000 $1,742,000 REMARKS BELLAIRE TO WESTPARK; ALONG TRAILS BELLAIRE TO WESTPARK BRAYS TO BELLAIRE;10’ WIDE BELLAIRE TO WESTPARK BELLAIRE TO WESTPARK BRAYS TO BELLAIRE;6’ WIDE REMARKS

IMPLEMENTATION 193 IMAGE COURTESY OF BUTLER PLANNING OF IMAGE COURTESY

194 IMPLEMENTATION Initiative: Urban Village Downtown SPACES, DEDICATED BIKE LANES, BIO-RETENTION GARDENSCAN BE IMPLEMENTED WITHOUT RE-CONSTRUCTING THE STREET DRAMATICALLY LOWERING COSTS THIS ESTIMATE INCLUDES RECONSTRUCTION OF THE STREET AND UTILITIES AT A COST OF $4.3MPER MILEFOR A 3-LANE SECTION AND $3.8M PER MILE FOR A 2LANE SECTION. SIDEWALKS, PARKWAY GREEN TOTAL COST COST TOTAL SOFT COSTS @20% HARD COSTS TOTAL INTERSECTIONS W/ ART INTERSECTIONS W/O ART MEDIAN PLANTING PAVER INTERSECTIONS TYPICAL STREETS -STREETSCAPE ELEMENTS ITEM South Rice -South -Streets /Streetscape (BellaireBlvd -Cypress Ditch) COST PERFOOT COST TOTAL HARD COSTS TOTAL BELLAIRE SIGNAGE/FURNISHINGS LIGHTING BETTERMENTS PLANTING AND IRRIGATION TREES SUB-GRADE DETENTIONCELLS PERVIOUS PAVING PARALLEL PARKING DRIVEWAY REPLACEMENTS PAVER SIDEWALKS NEW STREET RECONSTRUCTION ITEM Complete Street /Streetscape Elements (200’ prototype) 25 26 4638 11,680 5598 QTY 1 18 240 12 200 3200 480 2200 200 QTY EA EA LF SF LF UNIT LS LS SF EA LF SF SF SF LF UNIT $40,000 $18,000 $40 $18 $2,194 $/UNIT $10,000 $5,500 $8 $750 $240 $18 $10 $10 $690 $/UNIT $16,974,926 $2,829,154 $14,145,772 $1,000,000 $468,000 $185,520 $210,240 $12,282,012 SUB-TOTAL $1,951.60 $390,320 $390,320 $10,000 $99,000 $1,920 $9,000 $48,000 $57,600 $4,800 $22,000 $138,000 SUB-TOTAL REMARKS 10’ WIDE 3’ DEEP 3 LANES REMARKS

IMPLEMENTATION 195 REMARKS REMARKS SUB-TOTAL $3,451,162 $3,437,998 $2,362,938 $2,119,404 $288,000 $640,000 $12,299,502 $2,459,900 $14,759,402 SUB-TOTAL $3,451,162 $3,437,998 $2,362,938 $2,119,404 $288,000 $640,000 $12,299,502 $2,459,900 $14,759,402 $/UNIT $2,194 $2,194 $2,194 $2,194 $18,000 $40,000 $/UNIT $2,194 $2,194 $2,194 $2,194 $18,000 $40,000 UNIT LF LF LF LF EA EA UNIT LF LF LF LF EA EA QTY 1573 1567 1077 966 16 16 QTY 1573 1567 1077 966 16 16 ITEM ELEMENTS - STREETSCAPE - STREETS SPRUCE ELEMENTS - STREETSCAPE - STREETS CEDAR ELEMENTS - STREETSCAPE FERRIS - STREETS ELEMENTS STREETSCAPE - - STREETS STREET 5TH ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST SPRUCE - STREETS - STREETSCAPE ELEMENTS ELEMENTS - STREETSCAPE - STREETS SPRUCE Step Two - Complete Streets - Spruce, Cedar, Ferris and 5th (North of Bellaire Blvd) Bellaire (North of Spruce, Cedar, Ferris and 5th - Streets - Complete Two Step ITEM CEDAR - STREETS - STREETSCAPE ELEMENTS ELEMENTS - STREETSCAPE - STREETS CEDAR ELEMENTS - STREETSCAPE FERRIS - STREETS ELEMENTS - STREETSCAPE - STREETS STREET 5TH ART W/O INTERSECTIONS ART W/ INTERSECTIONS TOTAL HARD COSTS @20% COSTS SOFT TOTAL COST Bellaire Blvd) - Spruce, Cedar, Ferris and 5th (North of Streets - Complete Two Step Initiative: Urban Village Downtown (cont’d) Downtown Village Urban Initiative:

196 IMPLEMENTATION Initiative: Paseo Park: BellaireBoulevard Middle TOTAL PROJECT COST SOFT COSTS @20% HARD COSTS TOTAL AVE B FERRIS EVERGREEN NEWCASTLE ALLOWANCES ITEM BELLAIRE CONCRETE PAVER ITEM DG PAVING, 3”DEPTH X 20’ WIDTH ITEM Step x-Paseo Park, BellaireBlvd; First St. to South Rice Intersection 100’ Width Typical Step x-Objects, Art, Features TOTAL PROJECT COST SOFT COSTS @20% HARD COSTS TOTAL CROSSWALK STRIPING STEEL EDGE GENERAL LANDSCAPING Step x-BellaireBlvd, Intersections at Paseo Park TOTAL PROJECT COST SOFT COSTS @20% HARD COSTS TOTAL 10800 8450 10100 12100 3 QTY 15000 QTY 1 QTY 180 1 1 LF LF LF LF LS UNIT SF UNIT LF UNIT LF LF LF $500 $500 $500 $500 $7,500 $/UNIT $17 $/UNIT $100 $/UNIT $6 $10 $160 $11,550,000 $1,925,000 $9,625,000 $5,400,000 $4,225,000 $5,050,000 $6,050,000 $22,500 SUB-TOTAL $255,000 SUB-TOTAL $100 SUB-TOTAL $307,296 $51,216 $256,080 $1,080 $10 $160 $324 $54 $270 REMARKS PAVER ON VEHICULAR CONCRETE REMARKS 20SF X $5.00SF REMARKS 3/16” STEEL EDGE@$5.00 LF PLANTING, SOIL IMPRVTS, IRRIGATION

IMPLEMENTATION 197

First Steps

BUILD NEWCASTLE STREET LIGHTING $185,000 AND URBAN ELEMENTS 1 DETAILED DESIGN

BUILD ONE BLOCK NEIGHBORHOOD STREET PROTOTYPE $756,500 2 AND URBAN ELEMENTS DETAILED DESIGN

BUILD CITY GATEWAY BELLAIRE BOULEVARD $852,720 3 AT RAILROAD TRACKS

BUILD CITY GATEWAY BELLAIRE BOULEVARD $1,674,000 4 AT WEST LOOP

BUILD COASTAL PRAIRIE PARK SOUTH AND $5,000,000 5 STORMWATER DETENTION

BUILD BELLAIRE BOULEVARD $13,804,212 6 AND PASEO PARK

APPENDIX On-Going/Parallel Efforts

In preparing the Conceptual Master Plan, the planning team reviewed and incorporated many recently completed studies and City plans, including the following: »» City Of Houston Bicycle Master Plan, 2016 »» City Of Bellaire Municipal Buildings Plan, 2008 »» City Of Bellaire Parks Master Plan 2015-2025 »» Evergreen Park Master Plan, 2016 »» City Of Bellaire Comprehensive Plan,2015 »» City Of Bellaire, Economic Development Workshop, 2012 »» City Of Bellaire, Framework For Desirable Growth, 2005

CITY OF HOUSTON BICYCLE MASTER PLAN, 2016

CITY OF BELLAIRE COMPREHENSIVE PLAN, 2015 CITY OF BELLAIRE MUNICIPAL BUILDINGS PLAN, 2008 CITY OF BELLAIRE PARKS MASTER PLAN 2015-2025 EVERGREEN PARK MASTER PLAN, 2016

CITY OF BELLAIRE, ECONOMIC DEVELOPMENT WORKSHOP, 2012 CITY OF BELLAIRE, FRAMEWORK FOR DESIRABLE GROWTH, 2005

ACKNOWLEDGEMENTS

ACKNOWLEDGMENTS: In addition to the 1,021 residents who responded to the Citizens for a Beautiful Bellaire’s Citizen’s Survey and the many who participated in the nine (9) workshops and presentations conducted during the planning and design process as well as members of City of Bellaire Boards and Commissions we would like to recognize the contributions of the following individuals to this plan:

CITY COUNCIL CITY OF BELLAIRE STAFF

City of Bellaire Mayor Andrew S. Friedberg City Manager Paul Hofmann City of Bellaire Council Members Roman F. Reed Public Works Director Brant Gary Trisha S. Pollard Parks, Recreation & Facilities Director Karl Miller Gus Pappas Parks, Recreation & Facilities Assistant Director Cheryl Bright Pat McLaughlan Parks, Recreation & Facilities Director Michelle Jordan Michael Fife Development Services Director John McDonald David Montague CITIZENS FOR A BEAUTIFUL BELLAIRE

Citizen Volunteer John Monday Citizen Volunteer Christopher Butler

TERRAIN STUDIO

Principal, Beautification and Urban Design Lead Scott Slaney, FASLA Principal Minhui Li, ASLA Associate, Project Manager and Landscape Architect Brad Cowan, ASLA Associate and Landscape Designer Junyi Li, ASLA Associate and Landscape Designer Jiae Lee Landscape Designer Rebekah Dye Landscape Designer Lana Merrill Landscape Designer Bei Zhang Landscape Designer Dongwan Xie Landscape Designer Yuening Pu landscape architecture - planning - urbanism

San Francisco, California

Houston, Texas