Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. FORM-I (I) Basic Information

Sl. Item Details No. 1. Name of the projects/s The proposed project is development of a complex having residential flats, office spaces, retail areas, club and banquet along with rehabilitation of existing Charu Market by Muskan Highrise Pvt. Ltd 2. S. No. in the schedule 8(a) 3. Proposed capacity / area / length / tonnage to be The proposed project is the development of a handled / command area / lease area / number of complex having residential flats, office spaces, wells to be drilled retail areas, club and banquet along with rehabilitation of existing Charu Market. Area of land is 5,833.147 sq.m and owned by Muskan Highrise Pvt. Ltd. The proposed project comprises a single Basement + Ground + 22 storied building with community facilities. The entire basement will be utilized for car parking. Ground floor of the proposed project is solely utilized for commercial purpose. The lower and upper 1st floors will comprise office areas and car parking spaces. The 2nd floor is partially used for banquet. All the car parking floors have been accessed by ramps for smooth car movement at multi level parking areas. 2nd floor onwards, residential spaces will be erected. 8th and 9th floors will have community halls partially. 18th to 21st floors will have Club facilities partially. Project site is abutted by Deshpran Sasmal road laid along the west side of the site. The site is abutted by Charu Chandra Place (East) along north and Sultan Alam road along south. However, Deshpran Sasmal road is the main road abutting the project side and some part of the project site is occupied by the existing daily market sheds & structures and dwelling houses. Project site has a number of trees. Present landuse of the project site is compatible for residential use along with the office and retail usage. The same has also been mentioned in K.M.C. Assessment Book Records. Proposed number of residential flat is 117. Total built-up area of the proposed development will be 25,887.90 sq.m.

4. New / Expansion / Modernization New 5. Existing Capacity Nil 6. Category of Project i.e. ‘A’ or ‘B’ B 7. Does it attract the general condition? If yes, please No specify 8. Does it attract the specific condition? If yes, please No specify 9. Location Plot / Survey / Kharsa No. Premises No. 11, Deshpran Sasmal Road, K.M.C. Ward No. 89, Borough – X, P.O. – , P.S. – Charu Market, Kolkata – 700033 Village -

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 1 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. Tehsil - District Kolkata State 10. Nearest railway station / airport alongwith distance Railway Station – Tollygunge and New in kms Station (900m and 1.5km respectively), Airport – Netaji Subhas International Airport (20km approx.) 11. Nearest Town, City, District Headquarters alongwith Kolkata surrounding project site distance in kms 12. Village Panchayats, Zilla Parishad, Municipal Kolkata Municipal Corporation Corporation, Local Body (complete postal addresses with telephone nos. to be given) 13. Name of the Applicant Muskan Highrise Pvt. Ltd. 14. Registered Address 1 R.N. Mukherjee Road, Martin Burn Building, Mezzanine Floor, Room No. 7, Kolkata – 700001. 15. Address for Correspondence 1 R.N. Mukherjee Road, Martin Burn Building, Mezzanine Floor, Room No. 7, Kolkata – 700001. Name Mr. Amardeep Bhalotia Designation (Owner / Partner / CEO) Director Address Flat - 5A, 5th Floor, 16A Deshpran Sasmal Road, Tollygunge, Kolkata – 700033. Pin Code 700 033. E – mail [email protected] Telephone No. 033 – 2424 0231 Fax. No. 16. Details of Alternative Sites examined, if any. Not Applicable Location of these sites should be shown on a topo sheet 17. Interlinked projects No 18. Whether separate application of interlinked project Not Applicable has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves approval / clearance No under: if yes, details of the same and their status to be give. a) The Forest Conservation Act, 1980? b) The Wildlife Protection Act, 1972? c) The C.R.Z. Notification, 1991? 22. Whether there is any Government Order / Policy The land will be developed by Muskan Highrise relevant / relating to the site? Pvt. Ltd. No government order or policy is there related to the project site. 23. Forest land involved (hectares) Nil

24. Whether there is any litigation pending against the No project and / or land in which the project is propose to be set up? a) Name of the Court b) Case No. c) Orders / directions of the Court, if any and its relevance with the proposed project.

. Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.,)

(II) Activity

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 2 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, landuse, changes in water bodies, etc.)

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

1.1 Permanent or temporary change in No The project site is vacant with some existing market sheds landuse, land cover or topography and dwelling houses. Landuse of the site is residential including increase in intensity of cum commercial. Surroundings are primarily residential landuse (with respect to local with moderate inhabitancy along with considerable landuse plan) percentage of commercial establishments. Hence the proposed housing project is in agreement with the surroundings. Copies of land related documents of the project site are enclosed in Annexure-1.1.

1.2 Clearance of existing land, Yes Project site has some existing structures & few trees. vegetation and buildings? Hence existing structures will be dismantled. Also, some of the trees might get removed due to the proposed construction.

1.3 Creation of new landuses? No Existing landuse of project site is residential/commercial. Hence no new landuse has been created.

1.4 Pre-construction investigations e.g. Yes Necessary soil testing of the project site for assessment of bore houses, soil testing? bearing capacity of the soil has already been conducted. The derived result of the said testing will act as the guiding factor for the structural design of the project. A copy of soil test report is enclosed in Annexure – 1.4.

1.5 Construction works? Yes The total built up area of the proposed residential complex will be 25,887.90 sq.m. The complex will have 117 residential flats. Proposed ground coverage for the development is 2,142.692 sq.m (36.97% of the plot area).

1.6 Demolition works? Yes Existing dwelling houses and sheds of the existing market will be dismantled.

1.7 Temporary sites used for No Partial accommodation will be provided to the construction construction works or housing of workers by developing temporary sites within the construction workers? premises. However, majority of the construction workers will be locals commuting daily.

1.8 Above ground buildings, structures Yes Excavation of foundation and earthwork will be required or earthworks including linear for the backfilling of the proposed construction. structures, cut and fill or excavations? 1.9 Underground works including No No underground works other than construction of mining or tunneling? basement and underground reservoirs, etc. is required.

1.10 Reclamation works? No No reclamation work required.

1.11 Dredging? No No Dredging required.

1.12 Offshore structures? No No offshore structures required.

1.13 Production and manufacturing No No production/manufacturing process is involved, as it is a

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 3 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. processes? construction project.

1.14 Facilities for storage or goods or Yes Temporary storage space for the construction materials materials? will be created within the premises. Around 400 sq.m of area will be identified within the project site. Cement will be separately stored under cover in bales. Sand will be stacked with adequate care. Bricks and steel will be laid in open. No construction materials or waste will be stacked outside the premises.

1.15 Facilities for treatment or disposal Yes Solid Wastes: or solid waste or liquid effluents? Solid wastes generated will be 0.512 tonne/day of domestic nature. The wastes will be segregated into biodegradable and non-biodegradable wastes and collected in separate bins. The non-biodegradable wastes will be sold to recyclers and the biodegradable wastes will be collected at designated locations. Liquid Effluent: Liquid Effluent: During the construction phase, construction wastewater will be treated and reused. Domestic wastewater will be treated and disposed through septic tanks with soak pits. During the operation phase, domestic wastewater having volume of 90 kLD will be treated in STP. Treated waste water will be partially reused for toilet flushing & other secondary purposes and remaining will be discharged into road side drain. The domestic wastewater will be collected through vertical stack in building and conveyed to respective disposal points by underground pipes. The underground sewerage system will be designed 3 times of the average flow to carry domestic wastewater.

1.16 Facilities for long term housing for No The project is predominantly residential in nature, operational workers? although existing market establishments and dwelling houses will be rehabilitated. Moreover, office & retail spaces will be provided. However, during the operational stage, the complex will be accommodating the residents of the apartments only. No long term housing facilities for the operational workers or the commercial area employees will be available.

1.17 New road, rail or sea traffic during No Not Applicable construction or operation?

1.18 New road, rail, air, waterborne or No Not Applicable other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No There will not be any requirement for closure or diversion transport routes or infrastructure of existing transport routes along the abutting road due to leading to changes in traffic following reasons: movements? i) No construction material will be stacked outside the project site. ii) The unloading of construction materials will be done according to the instruction of the regulatory authority.

1.20 New or diverted transmission lines No Not Applicable

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 4 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. or pipelines?

1.21 Impoundment, damming, culverting, No No Impoundment, damming, culverting, realignment or realignment or other changes to the other changes to the hydrology of surface watercourse is hydrology or watercourses or proposed. aquifers? 1.22 Stream crossings? No No stream of natural watercourse passes through the project site.

1.23 Abstraction or transfers of water No Required fresh water requirement during construction as form ground or surface waters? well as operational phase will be met through K.M.C. supply.

1.24 Changes in water bodies or the No Surface drainage will not be affected. land surface affecting drainage or run-off? 1.25 Transport of personnel or materials Yes Transport of personnel / material during the construction for construction, operation or and operation phase is envisaged. In the construction decommissioning? phase, movement of few trucks is envisaged daily. During operational phase, parking space for around 234 cars will be provided. Break up for car parking facilities are as follows:

Car Parking Provided: 234 (basement = 140, 1st floor = 17, 2nd floor = 17, Ground Open = 60). Adequate parking area for service vehicles will also be provided.

1.26 Long-term dismantling or No Not Applicable decommissioning or restoration works? 1.27 Ongoing activity during No Not Applicable decommissioning or restoration works? 1.28 Influx of people to an area in either Yes Construction workers will be temporarily staying at the temporarily or permanently? project site during the construction period. During operational stage, about 626 persons will be residing in the apartments within the complex.

1.29 Induction of alien species? Yes The landscaping and plantation programme will guide about the exotic as well as native species to be planted within the project site.

1.30 Loss of native species or genetic Yes Few trees within site might be removed with prior diversity? permission from the concerned authority.

1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

2.1 Land especially undeveloped or No An area of 5,833.147 sq.m of land has been chosen for agricultural land (ha) the development of the project. The land is developed.

2.2 Water (expected source & Yes Water Reqd. during construction phase = 19 kLD. competing users) unit: KLD Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 5 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. Water Reqd. during operational phase: No. of daily user: Occupancy Type No. of Occupants Residents 626 persons Residential Floating 63 persons Retail Area Employee 77 persons Retail Area Floating 309 persons Office Area Employee 55 persons Club Users 283 persons Banquet Users 109 persons Service Staff 20 persons Total Occupants 1542 persons

Break up of Water Consumption: Activity Water Consumption Domestic 112 kLD Car Cleaning 5 kLD Landscaping 13 kLD Internal road cleaning 1 kLD Total 131 kLD

Source of Water: Domestic freshwater requirement will be catered by K.M.C. supply. Treated wastewater from the S.T.P will be partially utilized for toilet flushing and other secondary activities like landscaping, internal road cleaning etc. Another source of water will be rooftop rainwater to be utilized for car cleaning (after purification).

2.3 Minerals (MT) No Not Applicable

2.4 Construction material – stone, Yes Cement = 6,230 ton aggregates, and / soil (expected Sand = 15,620 cum source – MT) Stonechip = 13,036 cum Brick = 26,45,708 pieces Steel = 1,587 ton Steel and cement will be sourced from authorized vendors. Sand & aggregate will be sourced from local material supplier. 2.5 Forests and timber (source – MT) No Required timber will be supplied by local vendors.

2.6 Energy including electricity and Yes Daily power requirement for the proposed residential fuels (source, competing users) complex is assessed as around 600 kW. Connected load Unit: fuel (MT), energy (MW) will be 720 kVA. CESC will be the supply agency.

2.7 Any other natural resources (use No Not Applicable appropriate standard units) 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

3.1 Use of substances or materials, No There will be no storage of hazardous materials or which are hazardous (as per chemicals within the complex. MSIHC rules) to human health or the environment (flora, fauna and water supplies)

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 6 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. 3.2 Changes in occurrence of disease No Suitable drainage and waste management measures will or affect disease vectors (e.g. insect be adopted in both construction and operational phase, or water borne diseases) which will prevent stagnation of water or accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors.

3.3 Affect the welfare of people e.g. by Yes The construction of the proposed project will engage changing living conditions? approx. 100 local labours. Full occupancy of the proposed residential complex may accommodate about 626 residents. The management of the proposed complex will involve about 77 persons as retail area employee and 55 office employees. Moreover, the complex will be required of around 20 service staff. Hence, 252 direct employment opportunities will be generated. Domestic help required by the residents may generate another 117 indirect employment opportunities for the local women. Thus, a positive impact on the living conditions of these people is expected.

3.4 Vulnerable groups of people who No Proper mitigative measures for the minimization of could be affected by the project e.g. degradation of various environmental parameters like hospital patients, children, the noise abatement, traffic management etc., will be adopted elderly etc., during the post-construction stage of the proposed complex. Moreover, the difficulties will only be limited to the construction phase as operational phase will not pose any such difficulty.

3.5 Any other causes No --

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

4.1 Spoil, overburden or mine wastes No Not Applicable

4.2 Municipal waste (domestic and or Yes During the operational period, solid waste will be generated commercial wastes) from different residential apartments as well as from the daily users and visitors. Solid waste will also be generated from site cleaning and maintenance activities. The daily generated quantity of such waste has been primarily assessed as 512.1 kg/day or 0.512 tonne. Breakup of the quantity is as follows: Type of User Per capita solid No. of Solid waste waste Users Generation generation Residents 0.5 kg/cap/day 626 313.0 kg/day Residential 0.1kg/cap/day 63 6.3 kg/day Floating Retail Area 0.3 kg/cap/day 77 23.1 kg/day Employee Retail Area 0.1kg/cap/day 309 30.9 kg/day Floating Office Area 0.3 kg/cap/day 55 16.5 kg/day Employee Club Users 0.3kg/cap/day 283 28.3 kg/day

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 7 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. Banquet 0.3kg/cap/day 109 10.9 kg/day Users Service Staff 0.3kg/cap/day 20 6.0 kg/day Site 0.05kg/cap/da 1542 77.1 kg/day Maintenance y Total 512.1 kg/day or 0.512 tonne/day Generated solid waste will be collected as House to House (HTH) basis from designated locations & segregated into reusable waste and non-reusable waste by agency dealing in collection and disposal of garbage. The segregated non- usable solid waste will be disposed into K.M.C. waste disposal area. Adequate number of collection bins, separates for biodegradable and non-biodegradable waste will be provided as per Municipal Solid Waste (Management and Handling) Rule, 2000. Waste from such bins will be collected separately on daily basis. All the collection bins will be properly maintained on regular basis. Arrangement will be made with collection agencies for providing garbage station or transfer point, from where all wastes collected from bins will be disposed off for further disposal by the K.M.C. authorities.

4.3 Hazardous wastes ( as per No There will be no storage of hazardous waste within the Hazardous Waste Management complex except little amount of spent oil from D.G. Sets, Rules) which will be either reused or disposed off to an authorized collection agencies.

4.4 Other industrial process wastes No Not Applicable

4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other sludge from Yes The sludge generated from the S.T.P. and Inspection Pits of effluent treatment the Sewer Line will be periodically disposed to the K.M.C. collection agency.

4.7 Construction or demolition wastes Yes Construction waste will be reused for site development activities. 4.8 Redundant machinery or equipment No Not Applicable

4.9 Contaminated soils or other materials No Not Applicable

4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 8 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. 5.1 Emissions from combustion of fossil No The operation of proposed project does not envisage any fuels from stationary or mobile major air pollutant generating sources except DG sets (3 sources X 150 kVA) and vehicular movement.

5.2 Emissions from production No Not Applicable as no production process is involved with processes this project

5.3 Emissions from materials handling Yes This will be restricted to the construction phase and to the including storage or transport construction site only.

5.4 Emissions form construction Yes This will be restricted to the construction phase and to the activities including plant and construction site only. equipment 5.5 Dust or odours from handling or Yes Certain amount of dust particulate might be generated materials including construction during the handling of construction materials, excavation & materials, sewage and waste earthworks, construction activities etc. But, proper control measures will be taken to minimize the generated volume of dust and dirt.

5.6 Emissions from incineration of No No incineration of waste will take place within the waste premises both during the construction as well as operational period.

5.7 Emissions from burning of waste in No Open burning of biomass/other material will be avoided. open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No -

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

6.1 From operation of equipment e.g. Yes During construction, the machinery used for construction engines, ventilation plant, crushers will be of required standard and of reputed make and will adhere to national standards, which will take care of noise pollution control/ vibration control and air emission control. Hence, insignificant impacts due to construction machinery are envisaged. Apart from this, construction activities will be restricted to daytime only. Noise in the operational phase might be from DG sets only. DG sets will operate during power failure and will generate noise level below 75 dB (A) each as they will be of silent in nature.

6.2 From industrial or similar processes No Not Applicable

6.3 From construction or demolition Yes Due to various construction activities, there will be short- term noise impacts in the immediate vicinity of the project site. The construction activities will include the following noise generating activities: . Operation of DG sets, concreting and mixing . Demolition of Existing Structures . Excavation activities . Construction of structures and running of construction equipments like Mixer Machine, Vibrators, Earth

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 9 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. Cutting Machines, Pay Loader etc. It has been assessed that the average noise level will be around 80-85 dB(A) during peak construction hours. But this will be confined within the project site and within construction period only.

6.4 From blasting or piling Yes No scope of blasting is involved in the proposed development, but piling work will be done. While conducting the piling works, D.M.C. piles will be used. Hence, the magnitude of generated noise and vibration will be minimized.

6.5 From construction or operational Yes During the construction and operational stage of the traffic project, traffic movement will be inside the project site resulting in low generation of noise in the surroundings. But, due to adoption of good traffic management practices, generated impacts, if any, will be minimized.

6.6 From lighting or cooling systems No -

6.7 From any other sources No -

7. Risks or contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 7.1 From handling, storage, use or No There will be no storage of hazardous materials or spillage of hazardous materials chemicals within the complex.

7.2 From discharge of sewage or other No During the construction period of the project, generated effluents to water or the land domestic sewage from the labourers’ daily use will be (expected mode and place or treated in the temporarily built septic tanks within the discharge) complex and the treated wastewater will be finally discharged into roadside drain. The construction wastewater will be collected into a couple of Sediment Trap within the project site and after the sedimentation process it will be discharged into roadside drain. Sediment traps will have half an hour retention periods and their approximate size will be 2.5m (L) X 2.5m(W) X 0.75m (D). During the operational period, the generated wastewater will be treated and reused then discharged into roadside drain.

7.3 By deposition of pollutants emitted No No pollutants in terms of emission, effluent or solid waste to air into the land or into water will be emitted or discharged into the air, land or the surface water.

7.4 From any other sources No Not Applicable

7.5 Is there a risk of long term build up No Not Applicable or pollutants in the environment form these sources?

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 10 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. 8. Risk of accidents during construction or operation of the Project, which could affect human health of the environment

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

8.1 From explosions, spillages, fires etc No This is basically a construction project and does not from storage, handling, use or involve major hazardous construction activity. Hence, production or hazardous chances of explosions, spillages, fires are minimal. substances During construction, all the labourers will be provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Training and awareness about the safety norms will be provided to all supervisors and labours involved in construction activity. No major hazardous waste is being stored within the project site. No industrial or process activity is involved in this project hence chances of chemical hazards and accidents are minimal. However, suitable fire-fighting measures recommended by the fire department of Govt. of West Bengal will be adopted.

8.2 From any other causes No Not Applicable

8.3 Could the project be affected by No The area under study falls in Zone-III according to the natural disasters causing Indian Standard Seismic Zoning Map. Suitable seismic environmental damage (e.g. floods, coefficients in horizontal and vertical directions earthquakes, landslides, cloudburst respectively, have to be adopted while designing the etc)? structures. There are no chances of floods and landslide.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data

9.1 Lead to development of supporting Yes The local landuse of the area is predominantly residential. facilities, ancillary development Landuse along the abutting road is also predominantly stimulated by the project which residential in nature. The locality has high population could have impact on the density. The drainage & sewerage network of the area is environment e.g.: laid along the abutting road. CESC supplies electricity in the entire area. Thus, while developing the project, the Supporting infrastructure (roads, surrounding areas have been adequately considered so power supply, waste or waste water that the cumulative impact on the surrounding treatment etc.) environment can be minimized.

Housing development No The project itself accommodates housing.

Extractive industries No Not Applicable

Supply industries No Not Applicable

Other No Not Applicable

9.2 Lead to after-use of the site, which No Not Applicable could have an impact on the environment 9.3 Set a precedent for later No Not Applicable developments

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 11 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd.

9.4 Have cumulative effects due to Yes Similar types of residential projects already exist in the proximity to other existing or surrounding area. planned projects with similar effects

(III) Environmental Sensitivity

Sl. Areas Name / Aerial distance (within 15 km) No. Identity Proposed project location boundary 1. Areas protected under international None - conventions, national or local legislation for their ecological, landscape, cultural or other related value 2. Areas which are important or sensitive for None - ecological reasons – Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3. Areas used by protected, important or None - sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4. Inland, coastal, marine or underground waters None No coastal or marine areas within 15 km radius of the site. 5. State, National boundaries None -

6. Routes or facilities used by the public for No Not applicable. access to recreation or other tourist, pilgrim areas 7. Defense installation No Not applicable.

8. Densely populated or built-up area Yes The project site comes under Ward No. 89 of Kolkata Municipal Corporation. The site is surrounded by low to medium rise houses. The population density in the area is high. 9. Areas occupied by sensitive man-made land Yes Ranging from 1.0 km to 10 km from the uses (hospitals, schools, places of worships, project site. community facilities) 10. Areas containing important, high quality or None Not applicable scarce resources (groundwater resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas already subjected to pollution or No The ambient air quality results show that environmental damage, (those where existing the pollutants, like SPM, RPM, SO2 and legal environmental standards are exceeded) NOX, are well within the permissible limits of the NAAQS standards prescribed by CPCB. 12. Areas susceptible to natural hazard which None could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 12 Proposed Residential Building at Premises No. 11, Deshpran Sasmal Road, Borough – X, P.S. - Charu Market, Kolkata - 700033 Form – I Developer – Muskan Highrise Pvt. Ltd. (IV) Proposed Terms of Reference for EIA studies: Not applicable

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Date:………………..

Place: KOLKATA………. (Signature of the Applicant) Name : Amardeep Bhalotia Designation: Director Muskan Highrise Pvt. Ltd. 1 R.N. Mukherjee Road, Martin Burn Building, Mezzanine Floor, Room No. 7, Kolkata – 700001. Note: a. The projects involving clearance under Coastal Regulation Zone Notification 1991 shall submit with the application a C.R.Z. map duly demarcated by one of the authorized agencies, showing the project activities w.r.t. C.R.Z. and the recommendations of the State Coastal Zone Management Authority. Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z. Notification, 1991 for the activities to be located in the C.R.Z.

b. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves, Migrating Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden thereon (at the stage of E.C.).

c. All correspondence with the Ministry of Environment & Forest including submission of application for TOR/Environmental Clearance, subsequently clarifications, as may be required from time to time participation in the EAC Meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for the specific project.

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 13