09/12/2013

Paul Hesk

Regional Manager – Middle East, India and Africa

Van Oord Offshore bv

Dredging for Oil and Gas

CEDA UK Seminar Dredging for the Offshore Industries ICE London, 3 December 2013

Offshore and EPC Contractors

Text small (build up) including image

Recent Investments

Company Profile

Leading international contractor, specialising in:

• Dredging and Reclamation • Offshore Oil and Gas

• Marine

• Offshore Wind Farms • Infrastructure

• Soil Improvement

Offshore and EPC Contractors

1 09/12/2013

Oil and Gas Sector Related Activities • Dredging and Reclamation

• Trenching and Backfilling

• Pipeline (and Cable) Installation

• SPM System Installation

• Subsea Rock Installation • Protection and Stabilisation of Pipelines, Cables and Structures • Ballasting of Structures

• Scour Protection

• GBS Installation

Offshore and EPC Contractors

In presentation-modus:

Click on the logo to go back to menu

Dredging and Reclamation

Das Island, United Arab Emirates

• New platform for airport extension and accommodation

• 160 km offshore

• 16 million m3 (including soil improvement by vibro-compaction)

• 7 km of revetment

• 3.5 million tonnes Rock • 140,000m3 Concrete

• 39,000 No. X-blocks

Offshore and EPC Contractors © Copyright Van Oord | 2012 4

2 09/12/2013

In presentation-modus:

Click on the logo to go back to menu

Trenching and Backfilling

Typical Equipment Types:

• Trailing Suction Hopper Dredgers

• Cutter Suction Dredgers

• Backhoe Dredgers

Selection Criteria: Shallow to Deep Water

• Soil Properties • Water Depth

• Disposal Area

• Environmental Considerations

Near Shore

Offshore and EPC Contractors © Copyright Van Oord | 2012 5

Full image

Pipeline Installation

Offshore and EPC Contractors © Copyright Van Oord | 2012 6

3 09/12/2013

Text (large) including image

On-bottom Pull

The pipeline is pulled from an onshore stringing yard into the water with the aid of Linear Pulling Winches mounted on an offshore .

Offshore and EPC Contractors

Full image

Pipeline Installation – Bottom pull

© Copyright Van Oord | 2012 8

4 09/12/2013

Text (large) including image

Pipe Lay

In the near shore area, the pipeline is pulled from a Shallow Water Lay Barge moored offshore to the shore with the aid of Linear Pulling Winches. In deeper water, the pipeline is installed on the seabed by a Shallow Water Pipe Lay Barge.

Offshore and EPC Contractors © Copyright Van Oord | 2012 9

In presentation-modus:

Click on the logo to go back to menu

Shallow Water Pipe Lay Barge

• Shallow water applications (up to 100m) • 6” to 60” diameter pipe

• 7 Stations:

• 3 Welding • 1 Non Destructive Testing

• 3 Field Joint Coating

Offshore and EPC Contractors © Copyright Van Oord | 2012 10

5 09/12/2013

In presentation-modus:

Click on the logo to go back to menu

Single Point Mooring (SPM) System Installation

• Pipe Line End Manifold (PLEM) Installation

• CALM Buoy Installation:

• Subsea and Floating Hoses (including Umbilicals)

• Anchor and Chains

• Mooring Hawser

Offshore and EPC Contractors © Copyright Van Oord | 2012 11

Full image

Subsea Rock Installation

• Stabilisation

• Free-span Support

• Pre-lay • Post-Lay

• Crossings

• Upheaval Buckling Mitigation

• Protection

• Anchors • Dropped Objects

• Spudcan Pugmark Filling

• GBS Related Applications

Offshore and EPC Contractors © Copyright Van Oord | 2012 12

6 09/12/2013

Full image

From the Archive……..

Offshore and EPC Contractors © Copyright Van Oord | 2012 13

Full image

Offshore and EPC Contractors © Copyright Van Oord | 2012 14

7 09/12/2013

Full image

Flexible Fall Pipe Vessels

• DP-2

• Highly accurate installation

• Large capacity (up to 28,000 tonnes)

• Installation in water depths of up to 1,200m • Ability to close to live structures

Offshore and EPC Contractors © Copyright Van Oord | 2012 15

Full image

Offshore and EPC Contractors © Copyright Van Oord | 2012 16

8 09/12/2013

Full image

Side Stone Dumping Vessels

• DP-2

• Accurate installation in water depths of up to 50m • Ability to work close to……

Offshore and EPC Contractors © Copyright Van Oord | 2012 17

Full image

Side Stone Dumping Vessels

…… or under live structures

Offshore and EPC Contractors © Copyright Van Oord | 2012 18

9 09/12/2013

Full image

Offshore and EPC Contractors © Copyright Van Oord | 2012 19

Full image

Pipeline Stabilisation

Offshore and EPC Contractors © Copyright Van Oord | 2012 20

10 09/12/2013

Full image

Trench Backfilling

Offshore and EPC Contractors © Copyright Van Oord | 2012 21

Full image

Thermal Insulation

Offshore and EPC Contractors © Copyright Van Oord | 2012 22

11 09/12/2013

Full image

Free-span Correction

Offshore and EPC Contractors © Copyright Van Oord | 2012 23

Full image

Pre and Post Lay Installation

Offshore and EPC Contractors © Copyright Van Oord | 2012 24

12 09/12/2013

Full image

Crossings

Offshore and EPC Contractors © Copyright Van Oord | 2012 25

Full image

Upheaval Buckling Mitigation

Offshore and EPC Contractors © Copyright Van Oord | 2012 26

13 09/12/2013

Full image

Anchor Protection

Offshore and EPC Contractors © Copyright Van Oord | 2012 27

Full image

Dropped Objects

Offshore and EPC Contractors © Copyright Van Oord | 2012 28

14 09/12/2013

Full image

Infill of Spudcan Pugmarks

Offshore and EPC Contractors © Copyright Van Oord | 2012 29

Full image

Gravity Based Structure (GBS) installations • Sea Bed Preparation

• Tow Out

• Sinking • Ballasting

• Scour Protection

Offshore and EPC Contractors © Copyright Van Oord | 2012 30

15 09/12/2013

Full image

Seabed Preparation

Offshore and EPC Contractors © Copyright Van Oord | 2012 31

Full image

Tow-Out and Sinking

Offshore and EPC Contractors © Copyright Van Oord | 2012 32

16 09/12/2013

Full image

Ballasting

Offshore and EPC Contractors © Copyright Van Oord | 2012 33

Full image

Scour Protection

Offshore and EPC Contractors © Copyright Van Oord | 2012 34

17 09/12/2013

Chapter title

Thank you for your attention

Are there any questions?

Offshore and EPC Contractors

18