<<

C DS

R. E. Randall Bauer Professor of Dredging Director, Center for Dredging Studies Ocean Engineering/Department of Texas A&M C DS

OVERVIEW  Dredging Equipment  Dredge Production  Dredged Material Placement  Open water  Confined (Upland)  Beneficial use  Environmental Laws  Summary

Presentation for Lone Star Safety Committee 2 C DS DREDGING EQUIPMENT

DREDGE

MECHANICAL HYDRAULIC

Dipper Bucket Ladder HopperSidecastingPipelineAgitation

ClamshellDraglineBackhoeBucket-LadderPlain SuctionCutterheadBucket WheelDustpan

Presentation for Lone Star Harbor Safety Committee 3 C DS HOPPER DREDGE

Presentation for Lone Star Harbor Safety Committee 4 C DS HOPPER DREDGE (GLDD LIBERTY ISLAND & MURDEN SPLIT HULL HOPPER DREDGE)

Presentation for Lone Star Harbor Safety Committee 5 C DS

MECHANICAL CLAMSHELL DREDGE

Presentation for Lone Star Harbor Safety Committee 6 C DS PIPELINE DREDGES AND SLURRY  Typical pipeline diameters range from 15 to 92 cm (6 to 36 in)  Pipes are commonly constructed with steel or a composite material such as high density polyethylene  Pipelines may be submerged, floating, or placed on the shore.  Floating pipelines may be supported by pontoons or flotation material.  Length of the pipelines varies from short distances such as several hundred feet to several miles.

Presentation for Lone Star Harbor Safety Committee 7 C DS CUTTER SUCTION DREDGE & CUTTERS

Presentation for Lone Star Harbor Safety Committee 8 C DS

ADVANCING

WITH FIXED α α SPUDS

Presentation for Lone Star Harbor Safety Committee 9 C DS

BOOSTER PUMP, UNLOADER, SPIDER

Presentation for Lone Star Harbor Safety Committee 10 C DS PRODUCTION EQUATION  CU YD/HR = GPM x AVE % SOLIDS x 0.297

 CU YD/HR = D^2 x V x (SG-1) x 0.661

 Example: 20 in (0.508 m) dredge, V=15.12 ft/s(14,805 GPM), SG=1.25 (Cv=0.2273 or 22.73 % solids by volume)

 P=GPM(Cv)(0.297)=14805(0.2273)(0.297)=999 cu yd/hr

 P=D2(V)(SG-1)(0.661)=202(15.12)(1.25-1)(0.661)=999 cu yd/hr

Presentation for Lone Star Harbor Safety Committee 11 C DS

DREDGED MATERIAL PLACEMENT OPTIONS

 Open Water Placement  Confined Disposal Facility (CDF)  Beneficial Use

Presentation for Lone Star Harbor Safety Committee 12 C DS OPEN WATER PLACEMENT

Presentation for Lone Star Harbor Safety Committee 13 C DS

CONCEPTIAL CONFINED PLACEMENT FACILITY

Presentation for Lone Star Harbor Safety Committee 14 C 50 YEAR PLAN FOR BENEFICIAL USE OF DREDGE MATERIAL DS ( OF HOUSTON, COURTESY OF D. CASEBEER)

Presentation for Lone Star Harbor Safety Committee 15 C DS ATKINSON

Presentation for Lone Star Harbor Safety Committee 16 C DS

SEASONAL RESTRICTIONS ON DREDGING (DREDGING WINDOWS)  The dredging window refers is that period during which dredging activity is permitted  Windows are placed on the dredging to protect a biological resource from impact of the dredging activity  Dredging windows  Provide protection to the resources  Complicates scheduling of funding, contracting and conduct of  Increases the costs due to constrained time period  Increases operational hazards if windows coincides with adverse weather  Causes inefficient use of the dredge fleet

Presentation for Lone Star Harbor Safety Committee 17 C DS

GULF INTRACOASTAL IN TEXAS

Presentation for Lone Star Harbor Safety Committee 18 C DS DREDGING COSTS

Actual Dredging Costs (1993‐2013) Average Dredging Cost/Cubic Yard $1.60 $7.50 $1.50 $7.00 $1.40 $6.50 $6.00 $1.30 $5.50 $1.20 ($/CY)

$5.00 $1.10 $4.50 $1.00 Dollars) $4.00

$0.90 Cost $3.50 $0.80 $3.00 $0.70 $2.50 $0.60 $2.00 $1.50

(Billion $0.50 $1.00

$0.40 Average $0.50 $0.30 $0.00

Cost $0.20 $0.10 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 2013 $0.00 Fiscal Year 2011 2013 2012 1993 2001 2010 1995 1997 1994 1998 1996 1999 2003 2005 2002 2007 2004 2000 2008 2006 2009 Fiscal Year

http://www.navigationdatacenter.us/dredge/dredge.htm

Presentation for Lone Star Harbor Safety Committee 19 C DS SUMMARY

 Dredging is used to maintain and deepen channels, GIWW, & , other waterways.  Dredging equipment includes: cutter suction, hopper, & mechanical dredges, , pumps, instrumentation.  Dredged material is placed in open water, confined (upland) placement areas, and used beneficially.  Dredging is used for the environmental clean up of rivers, lakes, bays, and oceans.  Environmental laws regulate dredging activities  Dredging windows protect certain marine life  Total US dredging costs $1.1 billion and average cost/cubic yard was $5.81  Texas GIWW requires ~ 11 million cubic yards of dredging

Presentation for Lone Star Harbor Safety Committee 20 C DS QUESTIONS

Presentation for Lone Star Harbor Safety Committee 21