Agenda Item #6 Rail Update

Hampton Roads Transportation Planning Organization

Virginia Department of Rail and Public Transportation State Rail Plan Passenger and Freight Rail Initiatives

• Virginia’s 2013 State Rail Plan identifies passenger and freight rail improvements in various corridors • Phase 1 projects are funded in the state’s Six-Year Improvement Program (SYIP) • Total cost of planned improvements through 2040 exceeds $6.9 billion

Virginia Department of Rail and Public Transportation 2 Virginia Rail Projects

Virginia Department of Rail and Public Transportation 3 Rail 2015-2020 SYIP by Program ($ in millions)

FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 Total

Enhancement $41 $31 $34 $13 $12 $8 $139

Passenger 61 50 67 40 30 9 257

Preservation 14 13 5 4 2 1 39

Total $116 $94 $106 $57 $44 $18 $435

Virginia Department of Rail and Public Transportation 4 Passenger Rail Service In Virginia Present and Future

VA – Lynchburg, Richmond/Norfolk  Amtrak Regional – 2 Newport News, 2 Richmond  All go into  All same seat to  Amtrak Long Distance – Cardinal, , , , , Silver Star  Auto

Virginia Department of Rail and Public Transportation 5 Virginia Regional Amtrak Passenger Service Projected Population Areas

Virginia Department of Rail and Public Transportation 6 State Sponsored Conventional Speed Train Service

Lynchburg Service 2009 Richmond Service 2010

Up next: • Roanoke extension • Additional Norfolk Service • Train 2 to Lynchburg Norfolk Service 2012

Virginia Department of Rail and Public Transportation 7 IPROC Program Highlights • Intercity passenger rail operations and capital: $72.9 M • Based on existing 6 FY2015 – 2020 • Roanoke Amtrak service extension: $95.8 M • Norfolk Amtrak service: improvements to accommodate 2 more trains: $82.3 M • New Newport News Station: $20 M • Lynchburg to Alexandria Speed Improvements: $9.2 M

Virginia Department of Rail and Public Transportation 8 Southeast High Speed Rail • SYIP - funded – Tier II EIS from Richmond to DC - $55M – Arkendale to Powells Creek 3rd Main construction - $75M • Future Phases - unfunded – Tier II EIS from Richmond to Hampton Roads – Capacity improvements to initiate service

Virginia Department of Rail and Public Transportation 9 Arkendale to Powells Creek ARRA Funded Stimulus Project

• $75M 100% Federal ARRA Stimulus Funded Project • 11 Mile Third Track Design Build Project • CSX will construct for DRPT • Project completion 9/2017

Virginia Department of Rail and Public Transportation 10 Richmond to Washington

115 mile segment (approximately)

Extends from Centralia northward through Arlington along CSX’s RF&P line

Projects to increase operating speed to 90 mph:

• Construct additional main line • Station improvements • Signal improvements • Curve geometry • Acca Yard/Bellwood Subdivision

Potential improvement areas:

• CSX Peninsula Subdivision • Buckingham Branch Railroad • A combination of the CSX “A-line” and “S-line” to cross the James River and bypass Acca Yard

Virginia Department of Rail and Public Transportation 11 SEHSR Status Richmond to…

• Tier I Record of Hampton Decision 2012 Roads

• Tier II Kick-Off Potomac 2014 River

• Tier II Record of Decision

Kicking2020 off Raleigh Expected 2015

Virginia Department of Rail and Public Transportation 12 RAPS Tier I EIS Findings

RAPS Tier I EIS recommended an incremental development approach

• Minimize impacts by using existing rail infrastructure, corridor and railroad right-of-way • Reduce expected initial capital investment • Generate benefits of higher speeds in achievable timeframes • Add 4 new high-speed round trips to the corridor

Virginia Department of Rail and Public Transportation 13 How Fast We Plan to Go

Virginia Department of Rail and Public Transportation 14 Tier II EIS Analysis

Tier II early screening will consider potential alignments outside of current rail right-of-way

Much of the detailed alternatives analysis for Tier II will be conducted in 5 to 20 mile sub-sections

Designs speeds will be 90 mph maximum speeds for RAPS inside of the right of way.

Virginia Department of Rail and Public Transportation 15 Future Major Rail Capital Projects

Richmond to DC High Speed Rail Improvements

Purchase of the S-Line ROW Petersburg to NC Line

Roanoke Extension

Additional Service to Norfolk and Lynchburg

Richmond to Norfolk High Speed Rail

Richmond to Raleigh High Speed Rail

Newport News Station Terminal

Virginia Port Access Rail Infrastructure

Long Bridge Replacement

Virginia Department of Rail and Public Transportation 16 Thank You!

Virginia Department of Rail and Public Transportation 17