Search Results Recreational Program Project Database

Your search for projects in State: GA, Total Results : 354

State Project Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 1997 Truman Parkway Linear Park Trail Construction Trail Construction 1 Chatham $47,000 $154,000 $201,000

GA 1999 Altamaha Park Recreational Acquisition of land and trail construction 1 Glynn $68,160 $17,040 $85,200

Trail

GA 2002 Bill Morris Park Walking Renovations, signage 1 Wayne $59,500 $24,126 $83,626

Track and Nature Trail

GA 2003 McMillan Creek Greenway McMillan Creek Greenway Construct Trail 1 Wayne $100,000 $29,000 $129,000

Trail Trail

GA 2006 McMillan Creek Greenway McMillan Creek Greenway Construct new boardwalk and natural surface 1 Wayne $74,155 $19,488 $93,643

Trail Trail Phase 2 trail.

GA 2008 Hog Pen Bluff Trails Land Acquisition Acquire 2,100 acres and develop trailhead 1 Camden $1,039,000 $4,000,000 $5,039,000

and trails for motorized vehicles, equestrians,

and hikers.

GA 2008 Skidaway Island Multi-Use Trail Construction Construction of multi-use trail 1 Chatham $99,000 $31,000 $130,000

Trail

GA 2009 Towns Bluff River Park Trail Trail Construction and Construct a half-mile of new trail, renovate 1 Jeff Davis $47,800 $29,662 $77,462

Renovation existing trail, and install amenities.

GA 2009 McMillan Creek Greenway Construct Boardwalk, Phase Construct boardwalk trail about one-fifth of a 1 Wayne $100,000 $44,127 $144,127

Trail 3 mile long.

GA 2010 Lower Ogeechee Trails Lower Ogeechee Trails The recommended grant will assist the 1 Chatham $100,000 $30,870 $130,870

Project County with the constructing two miles of

trails that will lead hikers through a

bottomland hardwood forest.

GA 2010 Martha Frazier Fisher Park Fisher Park Trail At an existing park in Screven, the City plans 1 Wayne $81,000 $34,870 $115,870

Trail to build a nature walk featuring educational

opportunities on the plant life of the area, and

the grant will assist with the construction.

GA 2012 Historic Baptismal Trail Historic Baptismal Trail Acquire 11 acres and build 0.25 mile new trail 1 Liberty $100,000 $25,000 $125,000

Phase II

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2012 Woodbine Nature Trail Liza Rudolf Extension 1.5 miles paved trail and trailhead and 1 Camden $100,000 $37,350 $137,350

amenities

GA 2013 The Murphy Mile The Murphy Mile Construct 0.75 mile of trail, access points, 1 Bryan $100,000 $47,747 $147,747

parking, and trail amenities

GA 2013 Laura Walker Lake Trail Laura Walker Lake Trail Construct boardwalk adjacent to lake, and 1 Ware $100,000 $50,873 $150,873

Extension construct 2 miles of upland trail

GA 2014 Martin Luther King Jr. Martin Luther King Jr. Blvd 1 Glynn $100,000 $25,000 $125,000

Boulevard Trail Trail

GA 2014 Bill Morris Park Nature Trail Bill Morris Park Nature Trail 1 Wayne $100,000 $25,000 $125,000

GA 2015 Martin Luther King Jr. Martin Luther King Jr. Brunswick officials are working to install 1 Glynn $100,000 $25,000 $125,000

Boulevard Trail Boulevard Trail sidewalks and trails along city streets with the

goal of making it safer to walk from one area

of town to another.

GA 2015 Bill Morris Park Nature Trail Bill Morris Park Nature Trail 1 Wayne $100,000 $25,000 $125,000

GA 2018 Jaycee Landing Trails Jaycee Landing Trails, Jaycee Landing Trails, Phase I 1 Wayne $200,000 $40,000 $240,000

Phase I

GA 2007 Langdale-Riley Trail Boardwalk and Trailhead Construct new boardwalk trail and re-route 1, 2 Lowndes $51,982 $22,174 $74,156

Construction existing trail sections, construct picnic shelter

with amenities, and improve parking area.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2000 State Tools and Equipment Southern Off-Road Bicycle Purchase 6 tool trailers and equipment to 1, 2, 3, 4, 5, 6, 7, Appling, Atkinson,

Association (SORBA) Tool stock trailers for use building and maintaining 8, 9, 10, 11, 12, Bacon, Baker,

Trailers multi-use trails throughout the State 13, 14 Baldwin, Banks,

Barrow, Bartow, Ben

Hill, Berrien, Bibb,

Bleckley, Brantley,

Brooks, Bryan,

Bulloch, Burke, Butts,

Calhoun, Camden,

Candler, Carrol,

Catoosa, Charlton,

Chatham,

Chattahoochee,

Chattooga,

Cherokee, Clarke,

Clay, Clayton, Clinch,

Cobb, Coffee,

Colquitt, Columbia,

Cook, Coweta,

Crawford, Crisp,

Dade, Dawson,

Decatur, DeKalb,

Dodge, Dooly,

Dougherty, Douglas,

Early, Echols,

Effingham, Elbert,

Emanuel, Evans,

Fannin, Fayette,

Floyd, Forsyth,

Franklin, Fulton,

Gilmer, Glascock,

Glynn, Gordon,

Grady, Greene, Gwinnet, Habersham,

Hall, Hancock,

Haralson, Harris,

Hart, Heard, Henry,

Houston, Irwin,

Jackson, Jasper, Jeff

Davis, Jefferson,

Jenkins, Johnson,

Lamar, Lanier,

Laurens, Lee, Liberty,

Lincoln, Long,

Lowndes, Lumpkin,

Macon, Madison,

Marion, McDuffie,

McIntosh,

Meriwether, Miller,

Mitchell, Monroe,

Montgomery,

Morgan, Murray,

Muscogee, Newton,

Oconee, Oglethorpe,

Paulding, Peach,

Pickens, Pierce, Pike,

Polk, Pulaski,

Putnam, Quitman,

Rabun, Randloph,

Richmond, Rockdale,

Schley, Screven,

Seminole, Spalding,

Stephens, Stewart,

Sumter, Talbot,

Taliaferro, Tattnall,

Taylor, Telfair,

Terrell, Thomas, Tifft,

Toombs, Towns,

Treutlen, Troup,

Turner, Twigs, Union, Upson, Walker,

Walton, Ware,

Warren, Washington,

Wayne, Webster,

Wheeler, White, $35,821 $9,000 $44,821

Whitfield, Wilcox,

Wilkes, Wilkinson,

Worth

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 1993 Hard Labor Creek State Park Trail Construction 10 Morgan $13,500 $35,139 $48,639

Equestrian/Hiking Trail

GA 1993 Department of Trail Construction 10 Walton $9,045 $7,596 $16,641

Natural Resources

Educational Trail

GA 1996 Town Creek ATV Trail Trail maintenance, signage 10 Greene $23,986 $53,213 $77,199

GA 1997 Richard B. Russell State Trail Construction 10 Elbert $43,127 $45,000 $88,127

Park Trail

GA 1997 Town Creek ATV Trail Construction of new trail 10 Greene $20,000 $22,000 $42,000

GA 1999 Charlie Elliot Trail Construction of new trail 10 Newton $100,000 $25,000 $125,000

GA 2000 Jerrell Plantation Trail, Iron Trail restoration 10 Monroe $100,000 $25,000 $125,000

Hill Trail

GA 2000 Trailhead Trailhead facilities 10 Jasper $85,200 $21,300 $106,500

GA 2001 Town Creek ORV Trail Construct bridge and boardwalk to 10 Greene $62,000 $15,500 $77,500

rehabilitate poorly built trail sections

GA 2002 Jarrell Plantation Interpretive Phase II of trail rehabilitation 10 Jones $100,000 $25,000 $125,000

Trail

GA 2002 Victoria Bryant State Park Bridge 10 Franklin $100,000 $25,000 $125,000

Rice Creek Bridge

GA 2003 Salacoa Creek Americans Salacoa Creek Trail Construct Trail 10 Gordon $36,343 $14,896 $51,239

With Disabilities Act (ADA)

Trail

GA 2006 Locust Stake ATV Trail Locust Stake ORV Repairing trail tread, restoring grade dips and 10 Stephens $45,890 $11,485 $57,375

Maintenance erosion control devices, applying grass seed

and hay, installing silt fencing, closing illegal

trails, and enhancing sign system.

GA 2006 Oakey and Moates Oakey Mountain ATV Reshaping trail tread, reestablishing water 10 Habersham, Rabun $50,000 $12,500 $62,500

Knob ATV Areas Maintenance bars and dips, cleaning out wing ditches and

removing hazard trees, closing

environmentally sensitive area and

constructing replacement trail.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2006 Lake Russell Multi-Use Lake Russell Multi-Use Grading of trail tread, maintaining erosion 10 Stephens $28,098 $7,025 $35,123

Complex Trail Complex Trail Maintenance control devices, clearing trail corridor and

other non-routine maintenance.

GA 2007 Clarkesville Greenway Trail Trail Construction Construct 1.5 miles of trail and install 10 Habersham $100,000 $309,302 $409,302

signage.

GA 2007 Fort Yargo Trail Trail Accessibility Resurface wheelchair-accessible trail, 10 Barrow $100,000 $25,000 $125,000

Enhancements replace Braille signs, construct new multi-use

trail, and improve general signage.

GA 2007 Dauset-Indian Springs Trail and Trailhead Construct 1.5 miles of multi-use trail and 10 Butts $100,000 $25,000 $125,000

Multi-Use Trail Construction trailheads.

GA 2007 Fears Road Park Trail Trail and Trailhead Construct multi-use nature trail and picnic 10 Morgan $100,000 $245,910 $345,910

Construction area, shelter, restroom, parking area, signage

and other amenities.

GA 2007 Town Creek ATV Trail Trail Renovation and Perform non-routine maintenance on trail 10 Greene $185,000 $46,250 $231,250

Construction tread, construct and place puncheons and

boardwalks, remove old boardwalk, and

perform non-routine maintenance on

trailheads.

GA 2008 Cornelia City Park Trail Trail Renovation and Conduct trail system assessment, perform 10 Habersham $76,983 $34,404 $111,387

Trailhead Construction non-routine maintenance, and install

trailhead.

GA 2008 Tugaloo Corridor Hiking Trail Trail Construction Construction of trailhead and trail 10 Stephens $89,536 $48,264 $137,800

GA 2009 Cornelia City Park Trail Trail and Trailhead Renovate existing trail, construct wheelchair 10 Habersham $97,825 $37,699 $135,524

Renovation and Accessibility accessible trail and trailhead, and install

Improvements, Phase II interpretive signage.

GA 2009 Lake Loop Trail Trail Construction and Construct trailhead and trail about 4,250 feet 10 Rabun $26,865 $12,971 $39,836

Trailhead Improvements long.

GA 2009 Tri-County Wellness Park Trail Construction and Construct trailhead and about 2 miles of trail. 10 Hart, Franklin $98,400 $127,305 $225,705

Trailhead Improvements

GA 2011 Trail System Canal Trail System Signage The Authority was selected to improve the 10 Richmond $91,500 $29,796 $121,296

system of information and way-finding that

trail visitors use to get the most from the

trails.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2012 Clarkesville Greenways Greenways Expansion Add 0.5 miles unpaved nonmotorized trail; 10 Habersham $100,000 $55,400 $155,400

Expansion Phase II acquire 1 acre

GA 2012 Briar Patch Trail Briar Patch Trail Restore 14.79 acres; Add 0.25 miles of new 10 Putnam $100,000 $124,995 $224,995

unpaved nonmotorized trail and trailhead

GA 2012 Cupid Falls Park Addition Cupid Falls Park Addition Acquire 11 acres and build 1 mile non paved 10 Towns $100,000 $33,400 $133,400

trail

GA 2013 Frady Branch Trail Frady Branch Trail Re-Route Close portion of equestrian/mountain-bike 10 Stephens $100,000 $26,032 $126,032

trail and create replacement route.

GA 2013 A.H. Stephens State Park Park Trail System Construction of 10 miles of trails for 10 Taliaferro $61,295 $14,462 $75,757

Trail System equestrian and other uses

GA 2013 Founders' Trail Founders' Trail Construct 0.4 mile trail with interpretive 10 Morgan $100,000 $65,230 $165,230

signage in historic district

GA 2014 Fishing Creek Community Fishing Creek Community 10 Baldwin $99,985 $24,996 $124,981

Trail Trail

GA 2014 Ocmulgee Bluff Equestrian Ocmulgee Bluff Equestrian 10 Jasper $100,000 $25,000 $125,000

Trail Trail

GA 2014 Town Creek ATV Trail Town Creek ATV Trail 10 Greene $130,950 $32,737 $163,687

Maintenance

GA 2014 War Hill Trail The War Hill Trail 10 Wilkes $76,220 $15,244 $91,464

GA 2015 Fishing Creek Community Fishing Creek Community 10 Baldwin $100,000 $25,000 $125,000

Trail Trail

GA 2015 Ocmulgee Bluff Equestrian Ocmulgee Bluff Equestrian 10 Jasper $100,000 $25,000 $125,000

Trail Trail Maintenance

GA 2015 Town Creek ATV Trail Town Creek ATV Trail 10 Greene $131,000 $32,750 $163,750

Maintenance

GA 2015 War Hill Trail - 1779 Battle of War Hill Trail - 1779 Battle of 10 Wilkes $77,000 $19,250 $96,250

Kettle Creek Kettle Creek

GA 2016 Fishing Creek Community Fishing Creek Community Natural surface trail (1 mi) 10 Baldwin $100,000 $20,000 $120,000

Trail Trail: Campus Connector

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2016 Firefly Trail Firefly Trail Construction of 2.1 miles of new trail with 10 Oglethorpe $100,000 $112,390 $212,390

roadside parking made of asphalt. Land

acquisition of approximately 6 acre parcel

with signage, trash bins, benches and

lighting.

GA 2017 Firefly Trail City of Union Point Firefly New trail construction of 1.2 miles, land 10 Greene $100,000 $130,040 $230,040

Trail acquisition of 2.2 miles

GA 2018 Jackson Trail Jackson Trail Construct trail 10 Butts $200,000 $40,000 $240,000

GA 2018 Orange and White Trail Orange and White Trail Orange and White Trail Enhancement and 10 Clarke $155,200 $31,040 $186,240

Enhancement and Realignment at State Botanical Garden

Realignment at State

Botanical Garden

GA 2007 Butler Creek Nature Trail and Trailhead Construct 2.6 miles of trail and install 10, 12 Richmond $100,000 $56,200 $156,200

Corridor-Lombard Mill Pond Construction trailhead amenities.

Trail

GA 2008 Augusta Canal Trail System Trail Assessment and Conduct trail system assessment and provide 10, 12 Richmond $35,672 $10,088 $45,760

Maintenance Training field-based maintenance training.

GA 2013 Canal Trail Trailhead at Lake Olmstead Construct trailhead to serve historic Canal 10, 12 Richmond $100,000 $58,500 $158,500

Trail

GA 2016 Sandy Run Creek Trail Sandy Run Creek Trail .34 miles of 10 feet wide new trail 10, 12 Columbia $100,000 $118,213 $218,213

Phase II construction with, bridge connecting to

neighborhoods, grassing and silt fencing

GA 2001 Little Mulberry Park Trail Construct multi-use trail 11 Gwinnett $100,000 $86,644 $186,644

GA 2003 Milam Farm/ Etowah River Blue Trail Construct Trail 11 Bartow $100,000 $81,781 $181,781

Trailway

GA 2003 Chattahoochee Greenway District Construct Trail 11 Heard $95,000 $27,600 $122,600

Trail Motorized Trail Maint.

GA 2006 Pine Log-Beasley Gap Trail Trail and Trailhead Construct 4.3 miles of trail and parking area. 11 Bartow $65,728 $16,433 $82,161

Construction

GA 2007 Pine Mountain-Cooper's Trail Construction Construct 2,044 feet of trail. 11 Bartow $39,542 $9,886 $49,428

Furnace Trail Linkage

GA 2007 Downtown Connector Trail Trail Construction Construct trail 2,200 feet long. 11 Floyd $100,000 $200,000 $300,000

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2008 Pettit Creek Trail Land Acquisition and Trail Acquire easement and develop 1 mile of trail. 11 Bartow $100,000 $197,931 $297,931

Construction, Phase II

GA 2008 Iron Hill Trail Trail Construction, Phase 4 Construction of multi-use trail 11 Bartow $100,000 $25,000 $125,000

GA 2009 Heritage Riverways Trail Accessible Trailhead Install wheelchair accessible trailheads and 11 Floyd $40,114 $15,000 $55,114

Construction rest areas.

GA 2010 County Canoe Trail Canoe Trail The County plans to establish a canoe trail 11 Haralson $51,150 $27,500 $78,650

along the , grant will assist

with the construction of five canoe launches

and related access areas along the river.

GA 2011 Oothcalooga Creek Nature Oothcalooga Creek Nature The grant will help build a new trail along 11 Bartow $100,000 $46,504 $146,504

Trail Trail Oothcalooga Creek and around City Lake

GA 2011 Little Tallapoosa Park Trail Little Tallapoosa Park Trail The County will use the grant to build about 11 Carroll $100,000 $25,000 $125,000

two miles of trail in this park located north of

Carrollton.

GA 2011 Etowah River Blue Trail Etowah River Blue Trail at The City proposed to build a canoe and 11 Bartow $32,924 $12,550 $45,474

Lake Mounds kayak launch for the Etowah River water trail.

GA 2011 Village Historic Trail Village Historic Trail The City will build a trailhead and trail that will 11 Bartow $100,000 $60,592 $160,592

provide for outdoor recreation in the

surroundings of a tradition-rich town.

GA 2011 Church Trail Whispering Lake - Church This is one of Multiple phases of a trail that 11 Cobb $100,000 $42,980 $142,980

Trail connects neighborhoods to the Big Shanty

Historic District and downtown Kennesaw.

GA 2012 Heritage Riverways Trail Heritage Riverways Trail Construct 15 rest areas for the disabled along 11 Floyd $53,905 $15,200 $69,105

Phase II existing trail

GA 2013 Village Historic Trail Village Historic Trail Phase II Construct 1.5 miles of trail, including bridges, 11 Bartow $100,000 $104,000 $204,000

in historic district

GA 2013 Lower Chattooga River Canoe/Kayak Trail Construct 3 canoe/kayak launches with 11 Chattooga $99,700 $42,475 $142,175

Canoe/Kayak Trail trailhead amenities

GA 2013 Willow Springs Trail Willow Springs Trail Construct 0.25 mile boardwalk trail to connect 11 Chattooga $100,000 $25,000 $125,000

two historic parks

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2016 Etowah River Water Trail Etowah River Water Trail at 6 miles of water trail with boat launch for 11 Bartow $100,000 $43,731 $143,731

Hardin Bridge canoes and kayaks, paved parking area for

50+ vehicles, one trailhead, landscaping,

picnic tables and directional signage

GA 2018 Mountain Bike Park at North Mountain Bike Park at North Mountain Bike Park at North Cooper Lake 11, 13 Cobb $200,000 $40,000 $240,000

Cooper Lake Park Cooper Lake Park, Phase I Park, Phase I

GA 1996 New New Bartram Trail Trail construction, bike lane, handicap ramps, 12 Richmond $29,775 $30,000 $59,775

parking, trail head facilities, signage

GA 2006 Sands Greenway Trailhead Construction Acquire parcel and construct trailhead 12 Bulloch $100,000 $57,000 $157,000

including restroom, parking area, and

information shelter.

GA 2008 S&S Greenway Land Acquisition and Acquire 1 acre and develop trailhead. 12 Bulloch $100,000 $64,640 $164,640

Trailhead Construction,

Phase II

GA 2008 Partin Park Nature Trail Nature Trails Construct nature trail about 1,500 feet long. 12 Toombs $25,000 $41,603 $66,603

GA 2008 James Morgan Nature Park Trail and Trailhead Construct about a half-mile of trail and a 12 Emanuel $100,000 $31,024 $131,024

Leisure Trail Construction trailhead

GA 2010 Ohoopee Dunes Trail & Ohoopee Dunes Interpretive Construction of a new trail and trailhead. 12 Emanuel $100,000 $54,464 $154,464

River Launch Trail & River Access

GA 2010 Lower Fishing Creek Trail Fishing Creek Trail The Authority envisions a trail of over nine 12 Baldwin $100,000 $83,810 $183,810

miles in length to connect trail users with the

Oconee River on one end and a recreation

complex on the other, and the grant will

assist with the first phase of the trail.

GA 2010 Luetta Moore Trail Luetta Moore Trail Phase I Grant will assist with the design and 12 Bulloch $100,000 $139,096 $239,096

construction of the first phase of a trail that

will connect parks and neighborhoods on the

northwest side of the city. A substantial

portion of this first phase will pass through an

existing park.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2010 Vidalia Recreational Trail City Recreational Trail The City is developing a recreation facility on 12 Toombs $42,588 $28,264 $70,852

the eastern municipal boundary that is

planned to include fields and a swimming

pool. The grant will assist with the design and

construction of a nature trail on the property.

GA 2012 Rail Bed Trail Rail Bed Trail Phase II Add 4,000 feet of paved multi-use trail 12 Chatham $100,000 $25,005 $125,005

GA 2012 Ebenezer Greenway Ebenezer Greenway 0.6 unpaved non motorized trail; acquire 12 Effingham $70,000 $17,500 $87,500

28.15 acres for trail construction

GA 2014 Little Ohoopee River Blue Little Ohoopee River Blue 12 Emanuel $79,500 $19,875 $99,375

Trail Trail

GA 2015 Little Ohoopee River Blue Little Ohoopee River Blue The proposed Little Ohoopee River Blue Trail 12 Emanuel $80,000 $20,000 $100,000

Trail Trail will be 5 miles in length and is located in

close proximity to the Ohoopee Dunes

Wildlife Management Area and the Nature

Conservancy's Ohoopee Dunes Preserve.

The water trail will include the development...

GA 2016 Lyons Environmental Lyons Environmental .75 Miles of new trail construction, trailheads 12 Toombs $99,982 $53,400 $153,382

Education Trail Education Trail with signage, water fountains, benches, and

1.5 miles of trail maintenance

GA 2017 Pump Station Trailhead Pump Station Trailhead Construct a new entrance and parking area 12 Richmond $100,000 $105,436 $205,436

to provide public access to the wooden

bridge leading to Raw Water Pumping Station

and bike Trail. Gravel parking lot, wooden

fence, landscape screening, wooden guard

rail barriers, stone screenings walking...

GA 2007 Windham Creek Greenway Trail Construction Construct 1,500 feet of trail, and install 13 Fulton $100,000 $30,865 $130,865

Trail amenities and signs.

GA 2016 Chattahoochee Hills Trails Trails of Chattahoochee Hills Purchase and install a prefabricated 13 Rockdale $100,000 $25,000 $125,000

pedestrian/bike bridge, 4 miles of sustainable

trail and the Cochran Mill Nature Center,

maintain existing trailheads

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2016 Mayor's Park Trail Mayor's Park Trail New Trail Construction of 0.5 miles of trail, 13 Clayton $95,040 $79,000 $174,040

restroom facilities and maintenance of 0.7

miles of existing trail, benches and trash

recepticles

GA 1993 Simms Mountain Trail Property acquisition and trail construction 14 Floyd $16,748 $3,350 $20,098

GA 1993 Crockford-Pigeon Mountain Trail maintenance/rehabilitation & relocation 14 Walker $6,000 $3,800 $9,800

Wildlife Mgmt Area Trails

GA 1996 Trail Trail Construction 14 Polk $19,871 $19,871 $39,742

GA 2000 Rome-Floyd Heritage Trailhead facilities 14 Floyd $100,000 $25,000 $125,000

Riverway

GA 2000 Pinhoti Trail Construct trail and trailhead facilities 14 Gilmer, Fannin $66,600 $16,650 $83,250

GA 2000 Silver Comet Trail CSX overpass shelter 14 Polk $55,000 $13,750 $68,750

GA 2007 Ringgold Nature Trail Trail Construction Construct nature trail 4,340 feet long with 14 Catoosa $51,126 $27,529 $78,655

amenities and signs.

GA 2008 Black Branch Multi-Use Trail Land Acquisition and Trail Acquire easement and construct paved trail 14 Catoosa $100,000 $111,035 $211,035

Phase II Construction about 1,500 feet long.

GA 2009 Black Branch Multi-Use Trail Acquire Easement and Acquire easement and construct paved trail 14 Catoosa $100,000 $131,407 $231,407

Construct Paved Trail and and trailhead.

Trailhead, Phase III

GA 2014 Chattooga River Greenway Chattooga River Greenway 14 Walker $100,000 $25,000 $125,000

Trail Trail (Phase1)

GA 2014 Park Avenue Trail Park Avenue Trail 14 Chattooga $100,000 $25,000 $125,000

GA 2014 Conasuaga Ranger District Conasuaga Ranger District 14 Murray $78,000 $19,500 $97,500

Motorized Trails Motorized

GA 2015 Chattooga River Greenway Chattooga River Greenway 14 Walker $100,000 $25,000 $125,000

Trail Trail

GA 2015 Park Avenue Trail Park Avenue Trail 14 Chattooga $100,000 $25,000 $125,000

GA 2015 Conasauga Ranger District Conasauga Ranger District 14 Murray $78,000 $19,500 $97,500

Motorized Trails Motorized Trail Maintenance

GA 2017 Silver Comet Trail Silver Comet Accessibility Accessibility improvements for disabled users 14 Polk $100,000 $27,644 $127,644

Improvements and and maintenance of trail.

Maintenance Project

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2018 Rivers to Ridge-Model Mile Rivers to Ridge-Model Mile Construct Trail 14 Gordon $200,000 $40,000 $240,000

Trail Trail

GA 2018 Silver Comet Trail Church Street Trailhead Trailhead 14 Polk $95,500 $19,100 $114,600

GA 2018 Blue Devil Family Park Jackson Trail Blue Devil Construct trail 14 Harlalson $200,000 $40,000 $240,000

Walking Trail Family Park Walking Trail

GA 1996 North Riverwalk Trail construction 2 Muscogee $58,608 $73,600 $132,208

GA 1999 Reed Bingham Trail Trail reconstruction 2 Cook $95,000 $25,000 $120,000

GA 1999 Greenway Trail Construction 2 Dougherty $100,000 $159,000 $259,000

GA 2003 Leesburg Central Park Trails Leesburg Central Park Trail Construct Trail 2 Lee $80,000 $28,000 $108,000

GA 2006 Cherokee Park Trail Trail Construction Construct 1.3 mile trail, lake-crossing, and 2 Thomas $200,000 $63,500 $263,500

low-impact lighting.

GA 2008 North Peach Park Trail Trail Extension Construct about 6,800 feet of trail, and install 2 Peach $100,000 $203,850 $303,850

amenities.

GA 2009 Georgetown Recreational Trail Construction and Construct trailhead and about 0.5 miles of 2 Quitman $98,856 $28,552 $127,408

Trail Trailhead Improvements trail.

GA 2011 River Walk River Walk The City plans build a trail to connect several 2 Decatur $100,000 $721,000 $821,000

recreation facilities in the vicinity of the Earle

May Boat Basin and the Flint River.

GA 2011 Brown's Mill Battlefield Brown's Mill Battlefield The grant will help fund a portion of a larger 2 Coweta $100,000 $101,608 $201,608

Recreational Trails Recreational Trails trail system that is planned for the battlefield

site as the County seeks to highlight its rich

history.

GA 2013 Cochran Mill Park Trail Cochran Mill Park Trail Repair trail tread in 10-mile stretch of existing 2 Chattahoochee $100,000 $196,900 $296,900

trails. Construct 8 miles of new trail. Expand

trailhead parking

GA 2014 Byron's Cemetery Trail and Byron's Cemetery Trail & 2 Peach $67,590 $16,820 $84,410

Park Trail Park Trail

GA 2014 Festival Park Trail Festival Park Trail 2 Peach $100,000 $25,000 $125,000

GA 2014 South Peach Park Trail South Peach Park Trail 2 Peach $69,965 $17,491 $87,456

Extension

GA 2015 Byron's Cemetery Park Trail Byron's Cemetery Park Trail 2 Peach $70,000 $17,500 $87,500

GA 2015 Festival Park Trail Festival Park Trail 2 Peach $100,000 $25,000 $125,000

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2015 South Peach Park Trail South Peach Park Trail 2 Peach $70,000 $17,500 $87,500

Extension

GA 2016 Amerson Water Works Anderson Water Works and Construction of a new concrete paved short 2 Bibb $100,000 $453,000 $553,000

Ocmulgee Heritage Trail Ocmulgee Heritage Trail trail connector.

Connector Connector

GA 2016 Lee County Rails to Trails Lee County Rails to Trails Mulch trail (1 mi) and 3 trailheads 2 Lee $100,000 $20,000 $120,000

Trailheads

GA 2017 Whitewater Creek Trail Whitewater Creek Trail Canoe/kayak launch, flyover for dam, Mulch 2 Macon $100,000 $20,000 $120,000

System System trail (6.8 mi.)

GA 2018 Radium Springs Trail Radium Trailhead Develop trailhead 2 Dougherty $200,000 $40,000 $240,000

GA 2018 Sasser Trailhead Sasser Trailhead Develop trailhead 2 Terrell $100,000 $20,000 $120,000

GA 2007 Brasstown, Toccoa Purchase Trail Maintenance Purchase light machine and perform 2, 8, 9, 10, 14 Banks, Catoosa, $25,107 $6,276 $31,383

Equipment non-routine maintenance on trail tread and Chattooga, Dawson,

related areas. Fannin, Floyd,

Gilmer, Gordon,

Greene, Habersham,

Jasper, Jones,

Lumpkin, Monroe,

Morgan, Murray,

Oconee, Oglethorpe,

Putnam, Rabun,

Stephens, Towns,

Union, Walker, White,

Whitfield

GA 2003 Rock Hawk - Lawrence Lawrence Shoals Trail Maintenance, Construct Trail 3 Putnam $95,000 $68,230 $163,230

Shoals Trail

GA 2006 West Point Chattahoochee Trail and Trailhead Construct 2,000 linear feet of paved trail with 3 Harris $100,000 $25,000 $125,000

River Greenway Construction parking area and trailhead amenities.

GA 2007 Hogansville Water tower Concrete Trail Construction Design and construct 2,000 linear feet of 3 Troup $100,000 $25,930 $125,930

Trail concrete trail with interpretive signage.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2007 Bowdon-Creek Trails Land Acquisition and Acquire 9 acres and construct trail system to 3 Carroll $92,017 $63,431 $155,448

Trailhead Construction include paved path, hiking path, and

mountain-biking path, along with parking area

and trail amenities.

GA 2009 Chattahoochee River East Perform non-routine maintenance on 5 miles 3 Harris, Troup $100,000 $59,700 $159,700

National Water Trail Bank Park Connector of trail, acquire land and develop trailhead,

and construct canoe/kayak launch.

GA 2011 Water Tower Trail Water Tower Trail Phase II The City will use the grant to build a trail and 3 Troup $100,000 $67,934 $167,934

trailhead connecting to an earlier phase of

trail that is directly adjacent to the City's

historic water tower.

GA 2011 Pyne Road Park Trails Pyne Road Park The County was selected to receive a grant 3 Troup $100,000 $25,000 $125,000

for the development of hiking,

mountain-biking, and equestrian trails.

GA 2012 Greenbelt Lake Carroll Trail Greenbelt Lake Carroll Trail Add 800 feet of paved multi-use trail and 3 Carroll $100,000 $54,000 $154,000

trailhead and renovate landscape

GA 2012 Water Tower Trail Water Tower Trail Phase II Construct 0.07 miles of new trail and a 20 by 3 Troup $100,000 $35,124 $135,124

20 foot observation deck

GA 2013 Carrollton Greenbelt Carrollton Greenbelt, Spur to Construct concrete spur trail and bridge 3 Carroll $100,000 $39,100 $139,100

Elementary School connecting school to Greenbelt

GA 2014 Granger Park Trail Granger Park Trail & Park 3 Troup $100,000 $25,000 $125,000

Expansion

GA 2014 Lake Meriwether Trail Lake Meriwether Trail 3 Meriwether $100,000 $25,000 $125,000

GA 2015 Granger Park Trail Granger Park Trail 3 Troup $100,000 $25,000 $125,000

GA 2015 Lake Meriwether Trail Lake Meriwether Trail 3 Meriwether $100,000 $25,000 $125,000

GA 2016 Street Trialhead Alabama Street Trialhead Construct 150 LF of 12 ft. wide concrete path, 3 Henry $98,000 $19,600 $117,600

a small pocket park with shrubs and trees,

signage canoe launch, trailhead parking with

20 regular spaces + 2 ADA spaces. 25 ft. of

access drive from Alabama St. to site

GA 2017 Quarry's Edge Hike and Bike Quarry's Edge Hike and Bike Trail (4.2 mi.), trailhead, trailhead facility 3 Spalding $100,000 $20,000 $120,000

Trail at Dundee Park Trail at Dundee Park

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2017 Bush Head Shoals State Bush Head Shoals State Native soil trails (14.1 mi.) 3 Heard $1,103,526 $22,070 $1,125,596

ATV Park ATV Park

GA 2017 North Forty Trail North Forty Trail, Phase I Construction of two segments of trail phase I 3 Henry $92,608 $23,840 $116,448

totaling 0.60 miles, reconstruction of 0.25

miles of trail to paved trail. 6 trailheads.

GA 2018 THREAD-LaGrange College THREAD-LaGrange College Trail construction 3 Troup $200,000 $40,000 $240,000

Connector Connector

GA 2018 Water Tower Trail Hogansville Water Tower Hogansville Water Tower Trail Phase V 3 Troup $200,000 $40,000 $240,000

Trail Phase V

GA 2018 Carrollton Greenbelt Carrollton Greenbelt, Construct concrete spur trail 3 Carroll $200,000 $40,000 $240,000

Southside Spur

GA 2018 Harris County Rails to Trails Harris County Rails to Trails Harris County Rails to Trails Project 3 Harris $200,000 $40,000 $240,000

Project Project

GA 2006 McDonough InTown Trail Construction Construct two tenths mile of paved trail. 3, 13 Henry $74,157 $43,193 $117,350

Bike/Ped Connectivity

GA 2007 Anneewakee Creek Land Acquisition and Trail Acquire parcel for trailhead, construct 3, 13 Douglas $100,000 $85,800 $185,800

Greenway Construction trailhead, and construct one fourth mile of

trail.

GA 2003 Trail Arabia Mtn Trail Bridge 4 DeKalb $100,000 $55,000 $155,000

GA 2007 Pine Lake/Snapfinger Creek Trail and Boardwalk Construct boardwalk trail 3,065 feet long, and 4 DeKalb $99,136 $24,784 $123,920

Wetlands Walk Construction restore 1,280 feet of existing lakeside trail.

GA 2009 Camp Creek Greenway Lions Club/ Camp Creek Construct paved trail about 0.3 mile long trail. 4 Gwinnett $100,000 $395,000 $495,000

Greenway Connector

GA 2012 Black Shoals Scenic Trail Black Shoals Scenic Trail 1.8 miles of new unpaved, nonmotorized trail 4 Rockdale $100,000 $46,900 $146,900

and trailhead

GA 2013 Vaughters Farm Trailhead State Park Construct trailhead parking area with 4 Rockdale $100,000 $25,000 $125,000

restroom facilities

GA 2014 Browns Bridge Launch Browns Bridge Launch 4 Newton $80,000 $16,000 $96,000

GA 2015 Water Trail Yellow River Water Trail 4 Newton $80,000 $20,000 $100,000

Browns Bridge Launch

GA 2017 South Rockdale Community Shared Use Trails of South Shared use trail construction of 6.35 miles in 4, 13 Rockdale $100,000 $65,878 $165,878

Park Trails Rockdale Community Park 6 trail segments connecting to the Rockdale

River Trail.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2008 Harbins Park Trail System Trail Construction and Construct about 16 miles of hiking, 4, 6, 7, 10 Gwinnett $100,000 $1,000,000 $1,100,000

Renovation equestrian and mountain bike trails, and

perform non-routine maintenance on existing

trails.

GA 2006 Mulberry Riverwalk Trail Construction Construct 1.7 mile multi-use trail along 4, 6, 7, 9, 10 Jackson, Barrow, $100,000 $175,000 $275,000

Mulberry River, linking with Phase 1 at Gwinnett, Hall

Liberty Church Road and a proposed park on

Highway 124.

GA 2006 George Pierce Trail Trail Construction Construct two miles of new trail, trailhead 4, 7 Gwinnett $100,000 $1,000,000 $1,100,000

facility, and slope stabilization, and install

signs.

GA 2007 Ivy Creek Greenway Trail and Bridge Construction Construct pedestrian bridge, and construct 4, 7 Gwinnett $100,000 $275,000 $375,000

trail leading from bridge to environmental

education center.

GA 2007 Rogers Bridge Greenway Trail Construction Construct trail 2,700 feet long, with trail 4, 7 Gwinnett $100,000 $103,391 $203,391

Trail amenities and signs.

GA 1993 Cochran Shoals Trails Trail maintenance & restoration, trailhead 5 Fulton $7,000 Unknown $7,000

facilities, signage & parking

GA 2011 Sykes Park Recreational Sykes Park Recreational The City will use the grant to build a 1.5 mile 5 Fulton $80,000 $61,154 $141,154

Trail Trail trail and trail access points at an existing

community park.

GA 2013 Zonolite Park Trails Zonolite Park Trails Construct trailhead and .4 mile of unpaved 5 DeKalb $83,000 $45,140 $128,140

trail

GA 1999 Wild Horse Trail Trail Construction 6 Cobb $100,000 $45,087 $145,087

GA 2001 Pinhoti Trail Construction of a new trail to existing trails 6 Fannin, Gilmer $42,000 $10,500 $52,500

and a parking lot, installation of 1 SST toilet

(ADA)

GA 2008 Garland Mountain Trails Purchase Trail Maintenance Purchase trail-building machine and develop 6 Cherokee $75,000 $108,560 $183,560

Equipment and Trail 11.5 miles of equestrian and hiking trails.

Construction

GA 2009 Holly Springs Downtown Acquire Easement and Acquire easement and construct trail about a 6 Cherokee $100,000 $25,000 $125,000

Trail Construct Trail half-mile long.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2011 Brook Run Park Trail Brook Run Park Trail The City plans to restore an older trail system 6 DeKalb $100,000 $30,810 $130,810

in this 102-acre park.

GA 2012 Brook Run Park Trail Brook Run Park Trail Phase Add 1 mile of new trail and 1 mile of trail 6 DeKalb $100,000 $29,310 $129,310

II maintenance

GA 2012 Lost Corner Preserve Trail Lost Corner Preserve Trail Acquire 22 acres and construct a 0.84 mile 6 Fulton $90,000 $31,840 $121,840

unpaved trail

GA 2013 Heritage and Boling Heritage and Boling Acquire land access and construct 1 mile trail 6 Cherokee $100,000 $609,049 $709,049

Connector Trail Connector Trail

GA 2014 Old Mill Park Trail Old Mill Park Trail Phase 3 6 Fulton $100,000 $25,000 $125,000

GA 2015 Old Mill Park Trail Project Old Mill Park Trail Project 6 Fulton $100,000 $25,000 $125,000

Phase III Phase III

GA 2017 Briarwood Park Nature Trail Briarwood Park Nature Trail .5 miles of single-use trail, .5 miles of trail 6 DeKalb $100,000 $61,700 $161,700

restoration with environmental and

educational signage and removal of invasive

species throughout

GA 2018 Trails at Providence Park Trails at Providence Park Trails at Providence Park 6 Fulton $200,000 $40,000 $240,000

GA 2007 Kennesaw Community Trail Trail Construction Design and construct 4,200 linear feet of trail 6, 11 Cobb $100,000 $362,560 $462,560

with amenities.

GA 2007 Old Mill Park Trail Trail Renovation and Renovate existing trail and construct new trail 6, 11 Fulton $100,000 $266,588 $366,588

Construction 1,350 feet long, and install interpretive and

educational signage.

GA 2008 Community Trail Land Acquisition and Trail Acquire easements and construct trail about 6, 11 Cobb $100,000 $53,754 $153,754

Construction, Phase III 1,300 feet long.

GA 2007 Island Ford Trail Trail Construction Construct two miles of trail and install 6, 7, 11 Fulton $100,000 $61,315 $161,315

amenities and signs.

GA 1997 Silver Comet Trail Trail Construction Trail Construction 7 Paulding $50,000 $51,000 $101,000

GA 1997 Iron Horse Trail Trailhead Construction Trailhead construction 7 Polk $50,000 $50,000 $100,000

GA 1999 Silver Comet Trail Pumpkin Vine Creek bridge 7 Paulding $159,000 $39,750 $198,750

GA 1999 Silver Comet Trail Trailhead construction 7 Polk $80,000 $20,000 $100,000

GA 1999 Etowah River Trail Trail construction and bridge rehabilitation 7 Bartow $100,000 $60,117 $160,117

GA 2000 Iron Hill Trail Construction of new trail 7 Bartow $100,000 $25,000 $125,000

GA 2000 Pinhoti Trail Trailhead facilities 7 Chattooga $47,200 $11,800 $59,000

GA 2001 Etowah River Trail Develop bike trail to link 2 existing bike trails 7 Bartow $76,000 $19,000 $95,000

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2001 Silver Comet Trail Construction of full service trailhead for the 7 Paulding $45,000 $11,250 $56,250

Silver Comet Trail

GA 2001 Pinhoti Trail Construct a new trailhead for Pinhoti Trail to 7 Chattooga $80,000 $20,000 $100,000

include restroom, kiosk, and parking area

GA 2001 Iron Hill Bike Trail Construction of phase II of the trail 7 Bartow $100,000 $25,000 $125,000

GA 2001 Silver Comet Trail Construction of abutments and 12 foot wide 7 Polk $100,000 $25,000 $125,000

prefabricated metal bridge over Euharlee

Creek

GA 2002 Iron Hill Bike Trail Phase III of trail construction 7 Bartow $100,000 $25,000 $125,000

GA 2002 Silver Comet Trail Bridge 7 Polk $88,000 $25,000 $113,000

GA 2014 Tribble Mill Greenway Tribble Mill Greenway 7 Gwinnett $100,000 $25,000 $125,000

Connections Connections

GA 2015 Tribble Mill Greenway Tribble Mill Greenway 7 Gwinnett $100,000 $25,000 $125,000

Connection Connection

GA 2006 Laurel Trail Sawnee Mountain Preserve, Construct one fourth mile of paved trail and 7, 9 Forsyth $74,155 $207,295 $281,450

Laurel Trail three fourths mile of natural surface trail, with

signage, parking area and related amenities.

GA 1997 Ocmulgee Greenway Trailhead Construction Trailhead facilities 8 Bibb $50,000 $639,000 $689,000

GA 1999 Ocmulgee Greenway Trailhead construction 8 Bibb $100,000 $29,642 $129,642

GA 1999 Ocmulgee Greenway Trailhead construction 8 Bibb $100,000 $25,000 $125,000

GA 2000 Ocmulgee Greenway Trail Construction 8 Bibb $127,249 $552,656 $679,905

GA 2000 Ocmulgee Greenway Trail Construction 8 Bibb $100,000 $579,905 $679,905

GA 2000 Bay Gall Creek Greenway Trail Construction 8 Houston $100,000 $25,000 $125,000

GA 2001 Ocmulgee Greenway Trailhead facilities 8 Bibb $100,000 $25,000 $125,000

GA 2001 Jean Gillis Memorial Park Acquire 3 acres of land to construct a walking 8 Treutlen $45,000 $11,250 $56,250

Trail and fitness trail

GA 2002 Helena Community Park Community Park Walking Construct Trail 8 Telfair $27,262 $6,816 $34,078

Walking Trail Trail

GA 2007 Big Indian Creek Multi-Use Big Indian Creek Waterway Construct one mile of multi-use trail with 8 Houston $100,000 $50,000 $150,000

Trail Project signage.

GA 2008 Remerton Mill Trails Land Acquisition and Trail Acquire over 2 acres and develop trailhead 8 Lowndes $100,000 $133,064 $233,064

Construction and trail

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2009 Ocmulgee River Equestrian Equestrian Trail Perform non-routine maintenance on 8 Jasper $100,000 $125,000 $225,000

Trail Maintenance Maintenance equestrian trail and trailhead.

GA 2009 Tom White Linear Park Park Restoration and Design and construct toddler educational 8 Colquitt $100,000 $48,119 $148,119

Restoration and Expansion Expansion trail, repair existing asphalt trail, and install

amenities.

GA 2009 Big Indian Creek Waterway Trail Construction Construct paved trail about 0.4 miles long. 8 Houston $100,000 $57,500 $157,500

Trail #2

GA 2010 Arrowhead Park Multi-Use Arrowhead Park Multi-Use Help build new trails at site. 8 Bibb $91,500 $51,100 $142,600

Trail Trail

GA 2011 Riverwalk Trail Riverwalk Trail The City will use the grant for the design and 8 Pulaski $100,000 $31,700 $131,700

construction of a boardwalk trail on the

riverfront at Veteran's Memorial Park.

GA 2011 Camellia Gardens Trail Camellia Gardens Trail The City proposed to build a trail through the 8 Bibb $100,000 $25,000 $125,000

recently acquired Camellia Gardens and

connecting to Jackson Springs Park and the

Ocmulgee Heritage Trail.

GA 2012 Arrowhead Park Multi-Use Arrowhead Park Multi-Use This is the second year in a row that the 8 Bibb $97,200 $107,600 $204,800

Trail Trail County has been selected to receive a grant

for Arrowhead Park at Lake Tobesofkee. The

Park is home to a burgeoning trail system

that is cared for in part by mountain bikers.

GA 2012 Yellow River Park Trail Yellow River Park Trail Construct 0.5 mile new paved trail and 8 Newton $98,976 $39,300 $138,276

Phase II trailhead sign and canoe launch

GA 2013 Charleston Park Trails Charleston Park The County's park located on will 8 Forsyth $52,700 $13,175 $65,875

soon be home to a new 6-mile trail system an

the grant will be used to build a trailhead with

parking spaces.

GA 2016 Big Indian Creek Waterway Big Indian Creek Waterway Construction of a 0.97 mile of concrete trail 8 Houston $100,000 $98,965 $198,965

Trail Trail Phase IV along Big Indian Creek

GA 2017 Half Moon Walking Trails Half Moon Walking Trails Develop and enhance .84 miles of trail 8 Wilcox $99,980 $22,330 $122,310

construction and assessment. Clearing,

grubbing, equip. rental, grading, drainage,

asphalt and engineering

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2018 Lanier County Parks and Lanier County Parks and Nature Trail in Lakeland 8 Lanier $104,356 $20,871 $125,227

Recreational Nature Trail Recreational Nature Trail

GA 2007 Oconee Riverwalk Park Trail Oconee Riverwalk Park Trail Construct 2,100 linear feet of paved trail. 8, 10 Baldwin $100,000 $54,050 $154,050

North Extension

GA 2006 Oconee Riverwalk Park Trail Trail Construction Construct 1,700 linear feet of paved trail and 8, 12 Baldwin $100,000 $54,050 $154,050

2,700 linear feet of soft surface trail.

GA 1993 Amicalola Falls State Park Trail Construction 9 Dawson $23,518 $81,482 $105,000

Nimberwill Ridge Trail

GA 1993 Bull Mountain Trail Trail maintenance/rehabilitation & relocation, 9 Lumpkin $9,000 Unknown $9,000

parking lot, and signage

GA 1996 Whissenhunt ORV Trail Trail maintenance, trailhead facilities, signage 9 Lumpkin $28,502 $28,502 $57,004

System

GA 1996 Houston Valley ATV Trail Trail maintenance, restroom, ADA accessible 9 Whitfield $27,000 $27,000 $54,000

ramp

GA 1996 Locust Stake ATV Trail Repair trail stream crossings, signage 9 Stephens $11,100 $11,100 $22,200

GA 1996 Beasley Knob ORV Trail Trail maintenance/rehabilitation, parking 9 Union $115,110 $15,450 $130,560

area, signage

GA 1996 Fort Mountain State Park Trail Construction 9 Murray $49,000 $56,540 $105,540

Trail

GA 1996 Jake Mountain Multi-Use Trail construction & restoration, parking, 9 Lumpkin $35,416 $33,920 $69,336

Trail bridges

GA 1996 Iron Mountain Trail Trail construction/maintenance/rehabilitation, 9 Fannin, Murray $6,000 $10,000 $16,000

signage, ADA view platform

GA 1996 Tallulah Gorge Access Trail Trail Construction 9 Rabun $25,000 $125,000 $150,000

GA 1997 Chicopee Woods Trails Trail Signage and educational programs 9 Hall $20,046 $20,152 $40,198

GA 1997 Keown Falls Trail Trail maintenance 9 Walker, Rabun $6,800 $6,916 $13,716

GA 1997 Beasley Knob OHV Trails, Trailhead renovation and trail maintenance 9 Union, Murray $12,500 $12,506 $25,006

Davenport OHV Trails

GA 1997 Whissenhunt ATV Trails Trail maintenance and construction 9 Lumpkin $21,000 $21,000 $42,000

GA 1997 Houston Valley ATV Area Trail maintenance 9 Whitfield $23,000 $23,000 $46,000

GA 1997 Locust Stake ATV Trails, Trail maintenance 9 Habersham, $19,600 $34,710 $54,310

Moates Knob ATV Trails Stephens

GA 1999 Chicopee Woods Bike Trail Restoration of trailhead 9 Hall $87,417 $21,854 $109,271

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 1999 Cohutta Motorized Trails Trail maintenance and trailhead facilities 9 Murray $64,000 $16,000 $80,000

GA 1999 Beasley Knob OHV Trails, Trail restoration and trailhead construction 9 Union $104,000 $26,000 $130,000

Davenport OHV Trails

GA 1999 Houston Valley ORV Trails Trail maintenance 9 Whitfield $89,000 $22,250 $111,250

GA 1999 Oakey Mountain and Moates Trail maintenance and trailhead facilities 9 Rabun, Habersham $119,000 $29,750 $148,750

Knob ATV Areas

GA 1999 Willis Knob Trail Trail renovation and maintenance 9 Rabun $97,000 $24,250 $121,250

GA 1999 Toccata River Construction of a canoe take-out facility 9 Fannin $52,000 $13,000 $65,000

GA 2000 Houston Valley ATV Trail restoration 9 Whitfield $78,860 $15,772 $94,632

GA 2000 Sitton Gulch Trail Construction of new trail 9 Walker $100,000 $25,000 $125,000

GA 2000 Lake Russell Trails Trail Construction 9 Stephens, $150,000 $37,000 $187,000

Habersham

GA 2001 Sitton Gulch Trail Phase II of Sitton Gulch Trail at Cloudland 9 Walker $100,000 $25,000 $125,000

Canyon

GA 2001 Black Branch Multi-Use Trail Trail Construction 9 Catoosa $100,000 $25,000 $125,000

GA 2001 Cove Park Trail and Construct a trailhead, parking lot, and 2.4 9 Pickens $75,000 $18,833 $93,833

Trailhead miles of walking/hiking trail

GA 2001 White County Interpretive Construction of 10,000 linear feet 9 White $71,000 $17,750 $88,750

Trail interpretive/hiking trail and 4,000 linear feet

sidewalk/fitness trail

GA 2001 Anderson Creek ORV Trail Construct new motorized trails for connector 9 Gilmer $32,000 $8,000 $40,000

loops

GA 2001 Houston Valley ORV Trail Spot gravel 8 miles of trail; (re)construct 9 Whitfield $26,000 $6,500 $32,500

earthen water bars along 17 miles of trail

GA 2001 Whissenhunt ORV Trail Construct handicap ADA access ramp and 9 Lumpkin $26,000 $6,500 $32,500

concrete pad in parking lot and crosstie

loading ramp

GA 2002 Sitton Gulch Trail Phase III of trail construction 9 Dade $100,000 $25,000 $125,000

GA 2002 Windermere Windermere Trail Construct Trail 9 Forsyth $100,000 $25,000 $125,000

GA 2002 Lumpkin County Park Lumpkin Co. Park Construct trail, restrooms, shelters 9 Lumpkin $100,000 $50,000 $150,000

GA 2002 Williams Mill Greenspace Williams Mill Greenspace Construct Trail 9 Hall $65,000 $25,100 $90,100

Trail Trail

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2003 Davenport Mountain ATV ATV Trails Trail Maintenance 9 Union $65,000 $16,250 $81,250

Trails, Beasley Knob

GA 2003 Locust Stake ATV Trails ATV Trails Trail Maintenance 9 Stephens $34,000 $8,500 $42,500

GA 2003 Curry Creek Greenway Trail Curry Creek Greenway Trail Construct Trail 9 Jackson $100,000 $37,614 $137,614

GA 2003 Chicopee Woods Trails Chicopee Woods Trail Improvements, bridge 9 Hall $100,000 $31,693 $131,693

GA 2003 Bear Hair Trail Bear Hair Trail Construct Trail 9 Union $35,000 $9,492 $44,492

GA 2003 Nottley River Trail Nottley River Trail Construct Trail 9 Union $100,000 $105,565 $205,565

GA 2003 Sitton Gulch Trail Sitton Gulch Trail Construct Trail 9 Dade $100,000 $25,000 $125,000

GA 2003 Yahoola Creek Trail Yahoola Creek Trail Construct Trail 9 Lumpkin $99,000 $108,720 $207,720

GA 2006 Armuchee-Cohutta District Armuchee-Cohutta District Reshaping and repairing trail tread, 9 Whitfield, Murray $34,430 $8,608 $43,038

Motorized Trail Motorized Trail Rehab constructing and maintaining erosion control

dips, repairing and improving stream

crossings, closing illegal trails, spot graveling,

installing vault toilet at trailhead, and

improving signage.

GA 2006 Beasley Knob OHV Trail Beasley Knob/Davenport Replacing visitor information boards and 9 Union $70,730 $17,733 $88,463

Mountain OHV Maintenance trash cans, repairing trail tread, constructing

and maintaining erosion control dips, closing

illegal trails, spot graveling, installing silt

fencing and hay bales, and seeding and

mulching disturbed soil...

GA 2006 Whissenhunt OHV Trail Whissenhunt OHV Replacing visitor information boards and 9 Lumpkin $53,323 $13,331 $66,654

Maintenance trash cans, repairing trail tread, improving

stream crossings, closing illegal trails,

replacing silt fencing, and seeding disturbed

soil outside the travelways.

GA 2006 Amicalola River Access Trail Accessible Trail Construct one half mile of new, wheelchair 9 Dawson $53,581 $24,746 $78,327

Improvements accessible trail, and repair damage to

existing trail.

GA 2006 Gainesville Midtown Trail Construction Construct one half mile of paved trail with 9 Hall $99,732 $47,470 $147,202

Greenway crosswalks, signage and amenities.

GA 2006 Chicopee Woods Mountain Trail Renovation and Construct over 6 miles of new mountain bike 9 Hall $126,240 $31,560 $157,800

Bike Trails Re-route trail, and re-route certain existing trail.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2006 Byron Herbert Reece Trail and Bridge Construction Construct pedestrian bridge and trail at 9 Union $74,155 $18,539 $92,694

Trailhead historic site.

GA 2007 Saul Raisin Wood Mountain Trail and Trailhead Construct over 5 miles of mountain bike trail, 9 Whitfield $51,899 $18,860 $70,759

Bike Park Construction parking area and latrine.

GA 2007 Crawfish Springs Nature Trail Construction Construct trail from wetland area to Coke 9 Walker $40,000 $64,600 $104,600

Trail Ovens Park, including signage.

GA 2007 Durham Trail Rail-Trail Development Construct 2.3 miles of trail on former railroad 9 Walker $100,000 $100,276 $200,276

bed.

GA 2009 Beasley Knob ORV Trail Beasley Knob Trail Conduct trail system assessment to 9 Union $50,000 $12,500 $62,500

Assessment determine repair needs.

GA 2009 Conasauga Ranger District Motorized Trail Maintenance Perform non-routine maintenance on over 48 9 Whitfield, Murray $65,170 $16,293 $81,463

Motorized Trails miles of motorized trail.

GA 2010 Cloudland Connector Trail Connector Trail Several entities are pursuing the 9 Dade $96,960 $55,580 $152,540

Section 2 development of a network of trails in and

adjacent to Cloudland Canyon State Park.

This will assist with the construction of a

connecting trail, a series of mountain bike

trails, and two trailheads.

GA 2010 Harrison Memorial Park Memorial Park Trails The City intends to build trails on a park sire 9 Gilmer $100,000 $42,200 $142,200

Trails adjacent to the , grant will assist

with design and construction.

GA 2011 OHV Trail Maintenance Blue Ridge District OHV Trail For maintenance of off-highway vehicle trails 9 Dawson, Fannin, $43,600 $10,900 $54,500

Maintenance in the Blue Ridge District Gilmer, Lumpkin,

Towns, Union

GA 2011 Chattooga River Trail Chattooga River District For maintenance of off-highway vehicle trails 9 Banks, Stephens, $94,581 $23,645 $118,226

Maintenance Motorized Trail Maint. in the Chattooga River District. Habersham, Rabun,

White

GA 2011 Houston Valley Motorized Houston Valley-Cohutta For maintenance of off-highway vehicle trails 9 Whitfield $72,300 $18,075 $90,375

Trails Motorized Trail Maintenance in the Houston Valley and Cohutta areas.

GA 2011 Mount Rachel Multi-Use Trail Mount Rachel Multi-Use Trail The City proposed to build about five miles of 9 Whitfield $100,000 $28,850 $128,850

hiking and mountain biking trails.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2011 Amicalola Access Parking Amicalola Access Green This river access point, popular with 9 Dawson $70,420 $19,471 $89,891

Lot Parking Lot paddlers, swimmers and anglers, will get a

make-over of its trailhead.

GA 2011 Doris Washington Park Trails Doris Washington Park Trails The grant will assist the City in developing 9 Pickens $100,000 $52,600 $152,600

the first link in a plan to connect parks,

neighborhoods and the downtown district with

a greenway.

GA 2011 USDA Forest Service Trail Systemwide Non-Motorized Trail assessment of the 9 Multiple Counties $0 Unknown $0

Assessment Trail Assessment Chattahoochee-Oconee National Forests

non-motorized trails

GA 2012 Beasley Knob OHV Trail Beasley Knob OHV Trail 4.3 miles of unpaved trail, 11.6 miles of trail 9 Union $508,949 $128,600 $637,549

Maintenance maintenance

GA 2012 Pinhoti Trail Pinhoti Trail Re-route 2.4 miles unpaved trail, renovate existing 9 Banks, Catoosa, $65,000 $16,250 $81,250

trail, install directional signs Chattooga, Dawson,

Fannin, Floyd,

Gilmer, Gordon,

Greene, Habersham,

Jasper, Jones,

Lumpkin, Monroe,

Morgan, Murray,

Oconee, Oglethorpe,

Putnam, Rabun,

Stephens, Towns,

Union, Walker, White,

Whitfield

GA 2012 Mineral Springs Trail Mineral Springs Trail Add 0.5 miles of new trail; 0.5 mile trail 9 Fannin $100,000 $25,000 $125,000

maintenance; Acquire 13.98 acres; construct

benches, picnic tables

GA 2012 Stekoa Park Trail Stekoa Park Trail Add 0.3 miles of unpaved, nonmotorized trail 9 Clayton $30,424 $15,317 $45,741

GA 2012 West Chickamauga Creek West Chickamauga Creek Construct 0.3 miles of new paved non 9 Catoosa $100,000 $101,500 $201,500

Multi-Use Trail Multi-Use Trail motorized trail

GA 2013 Historic Rex Village Trails Historic Rex Village The grant will help the County to acquire 9 Clayton $100,000 $25,000 $125,000

historic property for future trail development.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2013 Whissenhunt OHV Trail Whissenhunt OHV Trail Motorized trail assessment and maintenance 9 Lumpkin $242,000 $66,000 $308,000

Assessment

GA 2013 Cohutta Motorized Trail Houston Valley-Cohutta Motorized trail system maintenance 9 Whitfield, Murray $78,900 $20,025 $98,925

Motorized Trail Maintenance

GA 2013 Trail of Tears National Trail of Tears Construct 0.5 mile paved trail with interpretive 9 Catoosa $100,000 $55,800 $155,800

Historic Trail signage and scenic creek overlook

GA 2013 Don Carter State Park Trails State Park Trails Network Construct 22 miles of new trail, bridges, 9 Hall $138,000 $34,500 $172,500

Network signage, and trailheads as well as

canoe/kayak launch

GA 2014 Hart County Trail Hart County Trail 9 Hart $57,636 $14,409 $72,045

GA 2014 Chicopee Woods Bridge Chicopee Woods Bridge 9 Hall $100,000 $25,000 $125,000

Project

GA 2014 Nature Trails at Maysville Nature Trails at Maysville 9 Banks, Jackson $100,000 $25,000 $125,000

City Park City Park

GA 2014 Chattooga River Ranger Chattooga River Ranger 9 Banks, Stephens, $119,220 $29,805 $149,025

District OHV Trails District OHV Habersham, Rabun,

White

GA 2014 Duncan Ridge Trail 9 Union $86,976 $21,744 $108,720

Improvement

GA 2014 Panther Creek Trail Panther Creek Trail & 9 Habersham $77,000 $19,250 $96,250

Trailhead

GA 2014 Yonah Preserve Multi-Use Yonah Preserve Multi-Use 9 White $94,640 $23,660 $118,300

Trail Trail Phase 1

GA 2014 Pittard Park Trails Pittard Park Trails 9 Clarke $69,860 $17,465 $87,325

GA 2015 Chicopee Woods Bridge Chicopee Woods Bridge The funding will go toward replacing bridges 9 Hall $100,000 $25,000 $125,000

in the mountain bike trail system in the

Walnut Creek area north of Interstate 985

and a Walnut Creek tributary.

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2015 Hart County Trail Hart County Trail A walking trail through the botanical gardens, 9 Hart $60,000 $15,000 $75,000

but it will actually provide a paved path

through the botanical gardens. It will come

out behind the botanical gardens, and go

around the ball fields. It will circle around,

and, then, there will be...

GA 2015 Maysville City Park Nature Nature Trails at Maysville 9 Banks, Jackson $100,000 $25,000 $125,000

Trails City Park

GA 2015 Byron Herbert Reece Byron Herbert Reece 9 Union $100,000 $25,000 $125,000

Connector Trail Connector Trail

GA 2015 Chattooga River Ranger Chattooga River Ranger 9 Banks, Stephens, $120,000 $30,000 $150,000

District OHV Trails District OHV Trail Habersham, Rabun,

Maintenance White

GA 2015 Duncan Ridge Trail Duncan Ridge Trail 9 Union $87,000 $21,750 $108,750

Improvement

GA 2015 Panther Creek Trail Panther Creek Trail & 9 Habersham $77,000 $19,250 $96,250

Trailhead Maintenance

GA 2015 Yonah Preserve Multi-Use Yonah Preserve Multi-Use 9 White $95,000 $23,750 $118,750

Trail Trail

GA 2015 Pittard Park Trails Pittard Park Trails 9 Clarke $70,000 $17,500 $87,500

GA 2016 Main Street Park Trail Main Street Park Trail .94 miles of new trail construction with 3 9 Dawson $100,000 $58,655 $158,655

(7'x6') treated lumber/metal roof, parking,

signage and picnic tables

GA 2016 Trail of Tears National Trail of Tears Phase II 0.2 miles of multi-use trail, Handicap 9 Catoosa $100,000 $44,200 $144,200

Historic Trail accessible Trailhead to include parking lot

GA 2016 Yonah Preserve Multi-Use Yonah Preserve Multi-Use Construction of approximately 3 miles of 9 White $100,000 $53,432 $153,432

Trail Trail Phase II multi-use trail. Project will include an

assessment to determine if a portion of trail

system can be constructed to meet design

requirements for use by persons with

disabilities. A site assessment of the...

GA 2017 Lake Toccoa Recreational Lake Toccoa Recreational Concrete trail with boardwalk (.7 mi.) 9 Stephens $100,000 $20,000 $120,000

Trail Trail Project

State Project Trail Name Project Name Description Cong. District(s) County(s) RTP Funds Other Funds Total Funds

Year

GA 2017 Helton Creek Falls Trail Helton Creek Falls Provide more stable and improved tread and 9 Union $100,000 $20,000 $120,000

Rehabilitation Trail Project step improvements, trail re-routing, new stair

section, boardwalks, hand rails, parking,

bridging, signage and tree removal.

GA 2017 Lula Nature Trails Project Nature Trails Project Construction of a single-use asphalt trail .6 9 Hall $79,000 $31,810 $110,810

mi.

GA 2018 Yahoola High Trestle Trail Yahoola High Trestle Trail Construct Trail 9 Lumpkin $134,502 $26,900 $161,402

GA 2018 Blue Ridge Ranger District Motorized Trail Maintenance Perform non-routine maintenance 9 Union, Lumpkin $199,998 $40,000 $239,998

Motorized Trails

GA 2018 Buzzards Roost/Grant Farm Buzzards Roost/Grant Farm Buzzards Roost/Grant Farm Mountain Bike 9 Whitfield $200,000 $40,000 $240,000

Mountain Bike Trail Mountain Bike Trail and Trail and Parking Facilities

Parking Facilities

GA 2008 Dry Creek Trail System Trail and Trailhead Perform non-routine maintenance on existing 9, 11 Chattooga, Walker $81,000 $21,500 $102,500

Construction trail, build new loop trail, and construct new

amenities and equestrian trailhead.

GA 2017 Conasauga Ranger District Conasauga Ranger District Trail maintenance of 48.6 miles of trail, 4 9, 14 Whitfield, Murray $70,000 $17,540 $87,540

Motorized Trails OHV Trail Maintenance trailhead facilities, 1.0 of new trail

2017-2019 construction. Environmental restoration.

GA 2018 Conasauga Ranger District Motorized Trail Maintenance Perform non-routine maintenance on over 48 9, 14 Whitfield, Murray $48,600 $9,720 $58,320

Motorized Trails miles of motorized trail.

Grand $33,480,674 $24,792,788 $58,273,462

Totals

(all results)