MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT PROGRAMME 2018-19 WATER SUPPLY & SANITATION

%age Physical Remarks (including detailed physical Funds Funds Sr. GS. No. Exp Upto Provision for utilization progress till progress) Name of Scheme District Type Approved Cost Released by utilized No. New June 2018 2018-19 on release current month (i) Date of Start of the Project F.D till 31.01.19 31.01.19 (%age) (ii) Date of completion of the Project

Ongoing Schemes On-going Scheme completed & handed over to CBO only 1 1604 R/W/S Scheme Dhamial Rawalpindi 181.407 164.389 5.673 2.255 0.837 37% 91% work for restoration of desmantled streets in Schemes progress. Construction of Road/Streets in Village Ghoon UC - Beor and Construction of Road/Streets & Hand On-going 2 1605 Rawalpindi 8.000 6.000 0.667 0.166 0.000 0% 75% Scheme completed in saving. Pumps in UC -Punjar & UC -Narar, District Schemes Rawalpindi Water Supply Scheme in Kahuta Town Tesil On-going 3 1606 Rawalpindi 8.000 2.143 1.952 1.464 0.976 67% 39% Work in Progress. Kahuta, District Rawalpindi Schemes P/I Tube Well in Latori Syedan & P/I Hand Pumps On-going 4 1607 in Dhok Naka and Village Matore UC -Matore, Rawalpindi 5.650 0.120 0.667 2.834 2.668 94% 49% Work in Progress. Schemes District Rawalpindi Rehabilitation & Augmentation &Ext of water On-going A.A Date 03.09.2015.T.S Date 23.09.2015. Date of 5 1608 Attock 43.515 41.514 0.667 0.500 0.334 67% 96% Start of Scheme 10.11.2015.Date of Completion of Supply Scheme for Village Dhullian Schemes Scheme 30.06.2019.Work is in progress.

Augmentation / Rehabilitation of Water Supply On-going A.A Date 10.09.2016. T.S Date 02.05.2017.Date of 6 1609 Attock 69.989 12.510 3.333 2.500 1.667 67% 20% Start of Scheme 16.06.2017.Date of Completion of Scheme Khour Tehsil Pindi Gheb District Attock Schemes Scheme 30.06.2019.Work is in progress.

Date of A.A 08.01.2015.Date of T.S 21.01.2015.Date of Start 20.04.2015.Date of completion .30.06.2019.Percolation well, Ground Rehabilitation of Rural water Supply Scheme On-going Storage Tank and Rising main completed. Work on 7 1610 Chakwal 25.000 18.475 2.175 0.543 0.000 0% 74% the scheme suspended due to loss of water Sarkalan Schemes in.ewly..eveloped.source as some blasting was done by Mining epartment. Revised Rough Cost Estimate submitted to D.C Chakwal vide T/O No.01/CH dated 01-01-2018 for according Revised A.A. Date of A.A 11.03.2015. Date of T.S 21.01.2015.Date of Start 20.03.2015..Date of Rehabilitation of Rural Water Supply Scheme On-going completion 30.06.2019 .Work suspended at site due 8 1611 Chakwal 1.620 0.719 0.300 0.075 0.000 0% 44% to sever conflicts among the CBO / community Dhoke Khour Tehsil Talagang, Chakwal. Schemes members. Community Development Unit trying to resolve the issues. Excessive funds surrendered through re-appropriation. Extension of water Supply scheme Khewra, Tehsil On-going Date of A.A 11-04-2016.Revised A.A 31-03- 9 1612 Jhelum 161.845 28.504 13.333 3.653 0.320 9% 18% 2017.Date of T.S 19-08-2016.Work awarded on 06- Pind Dadan Khan, District Jhelum Schemes 02-2017.Work in progress Authority to maintain & Regulate Naroomi Dhan On-going 10 1613 Jhelum 361.446 10.000 26.667 20.000 13.334 67% 6% Date of A.A 11/2017.Revised A.A 30-111-2017.• water Supply Scheme Tehsil P.D.Khan Schemes Work award on 16.02.2018.Work in progress Rural Water Supply Scheme Chal No 61/SB On-going 11 1614 Sargodha 15.000 0.039 3.333 2.500 1.913 77% 13% Work in progress. Sargodah Schemes Installation of 300 Hand Pumps Noushera On-going Date of AA 15-10-2015 Date of TS 09-11-2015 Date 12 1615 Khushab 132.000 111.498 1.833 1.375 1.370 100% 86% of award 05.01.2016 Date of completion 30.06.2019 Khushab Schemes Work is in progress. water Supply Scheme Jhunge Walan of UC On-going Date of AA 27.08.2016 Date of TS 03-09-2016 Date 13 1616 Khushab 24.058 14.550 3.167 2.375 2.145 90% 69% of Award 21.01.2017. Date of Completion Khabeki. Schemes 30.06.2019 Work is in progress. On-going Date of AA 27.08.2016 Date of TS 03-09-2016 Date 14 1617 water Supply Scheme Kalial UC Khura. Khushab 25.996 15.996 3.333 2.500 2.250 90% 70% of Award 24.01.2017 Date of Completion Schemes 30.06.2019 work is in progress. Date of AA 29.7.2017 Date of TS 04.09.2017 Date of award 14.12.2017 Date of completion 13.12.2019 Rehabilitation / Improvement of Water Supply On-going Tube Well 1 No. Pump House 1 No. Pumping 15 1618 Khushab 12.695 1.998 1.000 0.750 0.500 67% 20% Machinery 1 No. Rising Main 3640/19400 Rft The Scheme, Khoora UC Khoora, District Khushab Schemes Scheme remained unfunded in interim budget however it has been included in ADP 2018-19. work is in progress. Date of A.A. 13-01-2017, Date of T.S. 24-01-2017, Installation of Submersible Water Pumps, Tehsil On-going Date of Start of Work. 08-05-2017, Remarks 16 1619 Mianwali 50.000 37.423 3.387 2.540 1.688 66% 78% E.R.S=130/144, Trail Bore=6/6, T/Well boring= Isa Khel District Mianwali. Schemes 61/72, P/Machinery= 61/72, G.S.Tank= 7/72. Work is in progress. Date of A.A.27-08-2016, Date of T.S.15-10-2016, Provision of Submersible Pumps (UC Bani Afghan, On-going Date of Start of Work.03-12-2016, Remarks. 17 1620 Sawance, Ghundi, Chakrala, Ban Hafiz Gee, Mianwali 49.980 33.415 5.520 4.140 2.760 67% 72% E.R.S=35/50, T/Well boring= 87/110, Schemes Thamay Wali, Namal) P/Machinery=87/110, G.S.Tank=0/62-No. Work is in progress. Extension of Sewerage and water Supply, On-going "Date of A.A 25.08.2015 Date of T.S 11.11.2015 18 1621 Bhakkar 71.300 38.133 10.934 8.201 8.201 100% 65% Date of Commencement 28.12.2015 Date of Mankera. Schemes completion 30.06.2019 Construction of PCC in Different Streets in UC -64 On-going Date of A.A 05-08-2017. Date of T.S.05-09-2017. 19 1622 Faisalabad 5.000 2.000 1.000 0.750 0.500 67% 50% Work order issued on 31-10-2017. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19

Construction of PCC in Different Streets in UC -65 On-going Date of A.A 05-08-2017. Date of T.S.05-09-2017. 20 1623 Faisalabad 5.000 1.000 1.333 1.000 0.666 67% 33% Work order issued on 31-10-2017. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 &24.1.19

Construction of PCC in Different Streets in UC -66 On-going Date of A.A 05-08-2017. Date of T.S.05-09-2017. 21 1624 Faisalabad 5.000 2.000 1.000 0.750 0.500 67% 50% Work order issued on 31-10-2017. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19

Construction of PCC in Different Streets in UC -67 On-going Date of A.A 05-08-2017. Date of T.S.05-09-2017. 22 1625 Faisalabad 5.000 1.000 1.333 1.000 0.667 67% 33% Work order issued on 31-10-2017. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19

Construction of PCC in Different Streets in UC -72 On-going Date of A.A 05-08-2017. Date of T.S.05-09-2017. 23 1626 Faisalabad 5.000 1.000 1.333 1.000 0.667 67% 33% Work order issued on 31-10-2017. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19 Installation of Water Filetartion Plant in UC 463 On-going Case submitted for Change of Nomenclature UC- 24 1627 Faisalabad 3.000 0.000 1.000 0.000 0.000 #DIV/0! 0% 463 to Chak No. 463/GB vide SE No. 2414 dated Teshil Smundri District Faisalabad Schemes 07.08.2018. Rehab: of Rural Water Supply Scheme Chak No. On-going AA issued on 21.04.2017. Date of T.S 23.05.2017 25 1628 Faisalabad 87.765 84.043 1.000 0.750 0.390 52% 96% Work order issued on 11.05.2009. Work is in 215/RB Tehsil & Distt: Faisalabad Schemes progress. Funds released on 23.11.2018 & 24.1.19.

On-going AA issued on 20.10.2016. Date of T.S 24.10.2016 26 1629 Rural Water Supply Scheme at Chak No.84/JB Faisalabad 7.955 6.725 1.230 0.923 0.500 54% 91% Work order issued on 12.01.2017. Work is in Schemes progress. Funds released on 23.11.2018 & 24.1.19.

1-Date of A.A 20.10.2016 2- Date of T.S 21.10.2016 3-Date of invitation of tenders. 13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of Rehab. of rural water Supply scheme Chak No. On-going completion as per PC-I 30.06.2018 6- Date of work 27 1630 Toba Tek Singh 23.943 18.826 1.318 0.489 0.159 33% 79% order - 06.03.2017 7- Anticipated date of completion 343/GB T.T. Singh Schemes 30.06.2018 8- No. of Beneficiary - 5333 Persons 9- Funds Released by F.D 03.08.2018 & 24.01.2019 - 10-Re-appropriation of funds(+/-) Scheme completed in saving.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3-Date of invitation of tenders.13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of completion as per PC-I 30.06.2018 6- Date of work On-going order - 09.03.2017 7- Anticipated date of completion 28 1631 Rural water Supply Scheme Chak No.674/15/GB Toba Tek Singh 31.298 18.962 3.011 0.752 0.000 0% 61% Schemes 30.06.2018 8- No. of Beneficiary - 6390 Persons 9- Funds Released by F.D 03.08.2018 & 24.01.2019 - 10-Re-appropriation of funds(+/-) .Work could not be started due to site dispute in laying of distribution system. Progress will be achieved in next month.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3-Date of invitation of tenders.13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of completion as per PC-I 30.06.2018 6- Date of work On-going order - 09.03.2017 7- Anticipated date of completion 29 1632 Rural water Supply Scheme Chak No.675/16/GB Toba Tek Singh 28.057 20.000 2.686 1.205 0.533 44% 73% Schemes 30.06.2018 8- No. of Beneficiary - 3561 Persons 9- Funds Released by F.D 03.08.2018 & 24.01.2019 - 10-Re-appropriation of funds(+/-) Work could not be started due to site dispute in laying of distribution system. Progress will be achieved in next month. 1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3-Date of invitation of tenders.13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of completion as per PC-I 30.06.2018 6- Date of work On-going order - 04.03.2017 7- Anticipated date of completion 30 1633 Rural water Supply Scheme Chak No.685 26 GB Toba Tek Singh 21.024 16.243 0.508 0.127 0.000 0% 77% Schemes 30.06.2018 8- No. of Beneficiary - 3381 Persons 9- Funds Released by F.D 03.08.2018 & 24.01.2019 - 10-Re-appropriation of funds(+/-) - Work could not be started due to site dispute in laying of distribution system. Progress will be achieved in next month.

1-Date of A.A 10.09.2015 2- Date of T.S 25.02.2016 3-Date of Prequalification -07.03.2016 4-Date of invitation of tenders 18.03.2016 5- Date of Receipt Rural water Supply Scheme for Chak No.407/JB, On-going of tenders 26.03.2016 6- Date of work order - 31 1634 Toba Tek Singh 99.832 74.101 3.333 2.500 1.740 70% 76% 27.04.2016 7- Date of completion as per PC-I 409/JB, 410/JB & 411/JB Schemes 09.09.2017 8- Anticipated date of completion - 09.09.2017 9- No. of Beneficiary - 15516 Person 9- Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds(+/-) Work in progress.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3-Date of invitation of tenders. 13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of Rural water Supply Scheme, Chak No.709/GB completion as per PC-I 30.06.2018 6- Date of work On-going order - 09.03.2017 7- Anticipated date of completion 32 1635 and 710/GB, Tehsil Kamalia, District Toba Tek Toba Tek Singh 18.232 14.000 0.744 0.186 0.000 0% 77% Schemes 30.06.2018 8- No. of Beneficiary - 5867 Persons 9- Singh Funds Released by F.D 03.08.2018 & 24.01.2019 - 10-Re-appropriation of funds(+/-) Work could not be started due to site dispute in laying of distribution system. Progress will be achieved in next month.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3-Date of invitation of tenders.13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of Rural water Supply Scheme, Chak No.712/GB completion as per PC-I 30.06.2018 6- Date of work On-going order - 03.03.2017 7- Anticipated date of completion 33 1636 and Jamal Pahar, Tehsil Kamalia, District Toba Toba Tek Singh 22.981 17.000 1.994 0.499 0.000 0% 74% Schemes 30.06.2018 8- No. of Beneficiary - 4430 Persons 9- Tek Singh Funds Released by F.D 03.08.2018 & 24.01.2019 - 10-Re-appropriation of funds(+/-) Work could not be started due to site dispute in laying of distribution system. Progress will be achieved in next month.

1-Date of A.A 06.12.2014 2- Date of T.S 02.03.2015 3-Date of Rev: AA 28.05.2015 4-Date of Prequalification - 16.08.2016 5-Date of invitation of tenders 03.10.2016 6- Date of Receipt of tenders water Supply & Sewerage Scheme Rajana District On-going 34 1637 Toba Tek Singh 179.779 104.999 8.333 6.250 6.000 96% 62% 04.10.2016 7- Date of work order 27.10.2016 8- Toba Tek Singh Schemes Date of completion as per PC-I 26.10.2018 9- Anticipated date of completion 26.10.2018 10- No. of Beneficiary -21302 Person 11 -Funds Released by F.D 03.08.2018 & 24.01.2019 12-Re- appropriation of funds(+/-) Work in progress.

1-Date of A.A 28.12.2015 2- Date of T.S 25.02.2016 3-Date of Prequalification -07.03.2016 4-Date of invitation of tenders 06.03.2016 5- Date of Receipt Rural water Supply schemes Chak No.285/GB, On-going of tenders 26.03.2016 6- Date of work order - 35 1638 383/JB, 390/JB, 380/JB, 382/JB Feroz and Toba Tek Singh 90.000 69.965 3.333 2.500 2.200 88% 80% 28.04.2016 7- Date of Completion as per PC-I Schemes 336/GB, T.T. Singh 30.07.2017 8- Anticipated date of completion 30.07.2017 9- No. of Beneficiary - 37501 Person 10- Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds(+/-) Work in progress.

1-Date of A.A 14.11.2018 2- Date of T.S 20.11.2018 3-Date of Prequalification 4-Date of invitation of Installation of 02 No Water Filetration Plants in tenders 19.12.2018 5- Date of Receipt of tenders On-going 21.12.2018 6- Date of work order 7- Date of 36 1639 Chak no 771/GB & Mouza Akbar Sau & UC Jussa Toba Tek Singh 6.000 0.000 2.000 2.000 1.000 50% 17% Schemes completion as per PC-I 8- Anticipated date of tehsil Per Mehal District Toba Tek Singh completion 9- No. of Beneficiary -3233 Person 10- Funds Released by F.D 18.01.2019 11-Re- appropriation of funds (+/-) work in progress. Provision of Water Supply and Drainage Scheme On-going 37 1640 in Village Sher Garh UC Machiwal Tehsil & District Gujrat 49.971 0.400 3.333 2.500 1.667 67% 4% A.A Date =28.2.2018.work in progress Schemes Gujrat Construction of street / PCC / Soling / Nallian in Mandi On-going * A.A Date. 25.08.2017* T.S Date. 13.09.2017* Start 38 1641 150.000 69.978 3.333 5.150 4.317 84% 50% Date. 06.01.2018* Completion date various Ucs of District M.B.Din Bahauddin Schemes 05.01.2020*Work in progress. Rural water Supply & Drainage Scheme Village Mandi On-going * A.A Date. 19.03.2015* T.S Date. 02.04.2015* Start 39 1642 85.587 75.587 3.333 2.500 1.667 67% 90% Date 22.05.2015.* Completion date 30.06.2019.* Badshah Pur Tehsil Malikwal District M.B.Din Bahauddin Schemes Work in progress. Rural water Supply & Drainage Scheme Village Mandi On-going * A.A Date. 19.03.2015* T.S Date. 02.04.2015* Start 40 1643 62.780 57.780 1.667 0.650 0.234 36% 92% Date 22.05.2015.* Completion date 30.06.2019.* Tehsil & District M.B.Din Bahauddin Schemes Work in progress. Rural water Supply and drainage Scheme Mandi On-going * A.A Date. 28.04.2015* T.S Date. 19.05.2015* Start 41 1644 Bhaagowal & Noor Pur Peeran with adjecent 50.000 45.000 1.667 0.450 0.034 8% 90% Date 18.06.2015.* Completion date 30.06.2019.* Bahauddin Schemes abadies tehsil Mailk waal district mandi bahuddin Work in progress

Installation of 02 tubewells at Tahayat & Chandrai On-going Scheme completed. Funds are for the operation & 42 1645 Lahore 36.878 20.044 5.600 2.200 0.800 36% 57% Village, Green Town, Lahore Schemes maintenance of scheme. On-going Scheme completed. Funds are for the operation & 43 1646 Rural water Supply Scheme Mohlanwal Lahore 53.594 42.378 2.734 2.051 1.367 67% 82% Schemes maintenance of scheme. On-going Scheme completed. Funds are for the operation & 44 1647 Rural water Supply Scheme Sundar Lahore 24.475 22.331 0.715 0.536 0.358 67% 93% Schemes maintenance of scheme. On-going Scheme completed. Funds are for the operation & 45 1648 Rural water Supply Scheme Village Bath Lahore 39.469 29.475 3.331 2.498 1.666 67% 79% Schemes maintenance of scheme. On-going Scheme completed. Funds are for the operation & 46 1649 Rural water Supply Scheme Village Chah Tamoli Lahore 16.930 12.038 1.308 0.981 0.654 67% 75% Schemes maintenance of scheme. Establishment/ Construction of water Supply Scheme at UC 30, 31, 32 wanadala dial singh and On-going 47 1650 Sheikhupura 152.044 85.000 8.332 6.249 4.166 67% 59% Work in Progress dhaka nizampura tehsil feroz wala District Schemes Sheikhupura On-going 48 1651 Water Supply Scheme Pind burj Attari Sheikhupura 30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress Schemes Rural water Supply and Drainage Scheme Javed On-going 49 1652 Sheikhupura 198.903 72.367 6.667 5.000 3.334 67% 38% Work in Progress Nagar, District Sheikhupura Schemes Rural water Supply Drainage Scheme Iqbal Town On-going 50 1653 Sheikhupura 140.161 83.696 3.333 2.500 1.667 67% 61% Work in Progress District Sheikhupura Schemes Rural water Supply Drainage Scheme UC Kot On-going 51 1654 Sheikhupura 95.061 54.999 3.333 2.500 1.667 67% 60% Work in Progress Ranjeet Singh Sheikhupura Schemes Rural Warter Supply and Drainage P.C.C Scheme On-going 52 1655 Kasur 199.551 29.782 6.667 5.000 3.334 67% 17% Work in Progress Tibbi Kamboh, Mochi Pura, Kasur City. Schemes

Rural Water Drainage PCC Scheme Bhoojke, On-going 53 1656 Kasur 114.522 97.085 5.812 1.509 0.056 4% 85% Work in Progress Naike & Adjoining Abadies District Kasur. Schemes Rural water Supply & Drainage PCC Scheme at On-going 54 1657 Marali Hithar and Adjoining Abadies District Kasur Kasur 97.453 52.295 5.072 1.324 0.056 4% 54% Work in Progress Schemes (Revised) Rural water Supply & Drainage Scheme Chak On-going 55 1658 No.14 & Ghandhi Otar Tehsil Pattoki District Kasur 105.412 84.160 20.000 15.000 10.000 67% 89% Work in Progress Schemes Kasur. water Supply & Drainage Scheme They Kalay, Basti Balochi, Jhalar Qadir, Jhalar Rehmani, Jhalar On-going 56 1659 Kasur 119.701 83.750 3.333 4.600 3.767 82% 73% Work in Progress Choudhry & Jhalar Baglian Wali i/c Tubewell of Schemes Rao Tamkeen District Kasur. Water Supply and Drainage Scheme Gondy On-going 57 1660 Warha, Lambey Jagir, Dhaban, Sherpur, Lambey Kasur 82.108 78.345 1.254 0.314 0.000 0% 95% Work in Progress Schemes Mahtam & Fatey Wala. water Supply & Drainage Scheme Chak On-going 58 1661 No.31,32,33 Phullani, Dhoop Sarri & Saharankey Kasur 199.992 84.797 5.000 3.750 2.500 67% 44% Work in Progress Schemes District Kasur Rural water Supply and Drainage PCC Scheme at On-going 59 1662 Mandi Usmanwala and Adjoining Abadies District Kasur 158.978 138.348 6.877 8.279 6.560 79% 91% Work in Progress Schemes Kasur. Rural water Supply and Drainage PCC Scheme On-going 60 1663 Hardo Ban Bodla and Adjoining Abadies District Kasur 99.851 71.924 3.333 2.500 1.667 67% 74% Work in Progress Schemes Kasur. Rural water Supply and Drainage PCC Scheme On-going 61 1664 Maan Bhamni Wala and Adjoining Abadies District Kasur 178.985 170.646 2.778 0.695 0.000 0% 95% Work in Progress Schemes Kasur. Rural water Supply and Drainage PCC Scheme On-going 62 1665 Kasur 113.943 111.586 0.786 0.197 0.000 0% 98% Work in Progress Rajuwal and adjoining Abadies District Kasur. Schemes

Date of A.A 22-04-2017 Date of T.S 29.09.2016 Date of invitation of tenders 25-05-2017 Date of Rural Water Supply & Drainage Scheme, Qila On-going 63 1666 Okara 22.250 5.481 7.252 5.439 3.625 67% 41% Receipt of tenders 26-05-2017 Date of work order Dewan Singh Depaplur, Okara. Schemes 02-06-2017 Date of completion as per PC-I Anticipated date of completion 30-06-2018 No. of Beneficiary 11550 Person, Work is in progress. Date of AA 23.11.2016, Date of TS 07.12.2016, Date of receipt of tender 07.01.2017, Date of Work On-going 64 1667 water Supply Scheme Chak No.120/9.L Kameer. Sahiwal 105.498 91.699 4.599 3.449 3.100 90% 90% Order 08.02.2017, Date of completion as per PC-1 Schemes 31.01.2018, Anticipated date of completion 30.06.2019 subject to availablity of balance funds, Work in progress.

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3. Date of Pre-Qualification: - 4.Date of invitation of tender 04.03.2010 5.Date of Receipt of tenders On-going 65 1668 R/W/S/Scheme Gareywala, Nawabpur,Basti Nau Multan 70.476 52.661 2.333 1.750 1.167 67% 76% 06.03.2010 6.Date of work order 14.04.2010 7.Date Schemes of Completion as per PC-l 13.02.2013 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries 51946 Persons. Work is in Progress.

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3. Date of Pre-Qualification: - 4.Date of invitation of tender 06.02.2010 5.Date of Receipt of tenders R/W/S/Scheme Raja Pur, Siddiquebad, On-going 66 1669 Multan 77.962 64.018 0.667 0.500 0.334 67% 83% 08.02.2010 6.Date of work order 14.04.2010 7.Date Hirwat,Yere Wala Schemes of Completion as per PC-l 13.02.2013 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries 43334 Persons. Work is in Progress.

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3. Date of Pre-Qualification: - 4.Date of invitation of tender 06.02.2010 5.Date of Receipt of tenders On-going 67 1670 R/W/S/Scheme Taraggar. Multan 61.140 51.141 3.333 2.500 1.667 67% 86% 08.02.2010 6.Date of work order 18.06.2010 7.Date Schemes of Completion as per PC-l 17.06.2012 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10.No. of beneficiaries 20623 Persons. Work is in Progress.

1. Date of A.A: 17.09.2015 (28.05.2016) 2. Date of T.S: 08.06.2016 3. Date of Pre-Qualification: 11.06.2016 4. Date of Invitation of Tender: Rural Water Supply & Sewerage Scheme Nai On-going 18.07.2016 5. Date of receipt of Tender: 20.07.2016 68 1671 Multan 45.238 41.886 1.000 0.750 0.500 67% 94% 6. Date of Award: 22.07.2016 7. Date of Completion Wala Schemes as per PC-I: 16.09.2016 8. Anticipated date of completion 30.06.2018 9. Date of released of funds 23.11.2018. 24.01.2019 10. No. of Benificiary=6508 Persons. Work is in progress.

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: Sewerage Drainage Scheme Qasba Jalalpur Khaki On-going 02.11.2016 6. Date of Award: 12.11.2016 7. Date of 69 1672 Multan 46.177 43.912 1.000 2.015 1.490 74% 98% Shujabad Schemes Completion as per PC-I: 11.05.2018 8. Anticipated date of completion 30.06.2018 9. Date of released of funds 23.11.2018 10.No. of Benificiary= Persons. Work is in progress. 1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09- 2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt On-going of Tender: 15-11-2016 6. Date of Award: 03-12- 70 1673 water Supply / Sewerage Mouza Rawani. Lodhran 29.450 24.182 1.721 1.291 0.950 74% 85% 2016 7. Date of Completion as per PC-I: 31-12-2017 Schemes 8. Anticipated Date of Completion: 02-12-2017 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 8834 Persons. Work is in Progress.

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09- 2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt Rural water Supply Scheme Chak No.12/M & On-going of Tender: 15-11-2016 6. Date of Award: 08-12- 71 1674 14/M (East & West) Tehsil Dunyapur, District Lodhran 29.922 21.446 2.784 2.088 1.600 77% 77% 2016 7. Date of Completion as per PC-I: 31-12-2017 Schemes Lodhran 8. Anticipated Date of Completion: 07-12-2017 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 6980 Persons. Work is in Progress.

1. Date of A.A. 22-08-2015. 2. Date of T.S. 27-08- 2015 Rev. T.S 07-02-2017 3. Date of Pre- Qualification: 4. Date of invitation of tender 01-12- 2015 5. Date of Receipt of tenders 02-12-2015 6. Rural Water Supply Scheme Quatabpur Dunyapur, On-going Date of work order 16-12-2015. 7. Date of 72 1675 Lodhran 29.850 9.623 6.742 1.686 0.000 0% 32% Completion as per PC-l 21-08-2016 8. Anticipated Tehsil Dunyapur, District Lohdran Schemes date of completion 30-06-2017 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of beneficiaries 13535 Persons. Scheme completed & under test operation. Rs.1.686 million proposed for re-appropriation

1. Date of A.A (Amended) 04.04.2016 2. Date of T.S: 12.04.2016 3. Date of Pre-Qualification: 02.04.2016 4. Date of Invitation of Tender: 21.04.2016 5. Date of Receipt of Tender: Provision of water Supply Schemes in Chak No. On-going 73 1676 Khanewal 60.664 47.747 4.306 3.230 3.230 100% 84% 23.04.2016 6. Date of Work order: 30.04.2016 7. 135/10.R, District Khanewal. Schemes Date of Completion as per PC-I: 16.09.2017 8. Anticipated Date of completion: 31.12.2018 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11No. of beneficiaries 15048 Persons Work is in progress.

1. Date of A.A (Amended) 17.09.2015 2. Date of T.S: 07.03.2016 3. Date of Pre-Qualification: 02.04.2016 4. Date of Invitation of Tender: 21.04.2016 5. Date of Receipt of Tender: Provision of Water Supply Schemes in Chak No. On-going 74 1677 Khanewal 62.211 49.998 1.000 0.750 0.750 100% 82% 23.04.2016 6. Date of Work order: 30.04.2016 7. 136/10.R, District Khanewal. Schemes Date of Completion as per PC-I: 29.10.2016 8. Anticipated Date of completion: 31.12.2018 9. Date of released of funds 23.11.2018 24.01.2019 10. Reason of Slow Moving: _____ 11No. of beneficiaries 12907 Persons Work is in progress.

1. Date of A.A: 04.04.2017. 2. Date of T.S: 10.04.2017 3. Date of Pre-Qualification: 4. Date of Invitation of Tender: 08.05.2017 5. Date of Receipt Rural Sewerage / Drianage scheme chak No. On-going of Tender: 09.05.2017 6. Date of Work order: 75 1678 Vehari 18.710 8.742 3.319 4.149 1.820 44% 56% 25.11.2017 7. Date of Completion as per PC-I: 146/EB and Dalan, District Vehari Schemes 24.11.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= 20316 Persons Work is in progress. Provision of water Supply Scheme in Kundi Wala Dera Ghazi On-going 76 1679 50.325 38.936 3.789 2.842 2.132 75% 82% "• Date of A.A = 22.08.2015 UC shadan Lund Khan Schemes Provision of water Supply Scheme in Notak Dera Ghazi On-going 77 1680 47.463 29.182 5.834 4.376 3.107 71% 68% "• Date of A.A = 22.08.2015 Sakhani UC Kala Khan Schemes Provision of water Supply Scheme in Sabzani UC Dera Ghazi On-going 78 1681 36.579 28.136 2.556 1.917 1.438 75% 81% "• Date of A.A = 22.08.2015 Kala Khan Schemes Extension & Augmentation of water Supply Dera Ghazi On-going 79 1682 87.805 77.753 0.333 0.250 0.167 67% 89% "• Date of A.A = 16.12.2014 Scheme Sakhi Sarwar Khan Schemes Provision of Rural water Supply Scheme Nutkani, Dera Ghazi On-going 80 1683 82.680 59.914 7.577 5.683 4.149 73% 77% "• Date of A.A = 23.09.2016 District D.G. Khan Khan Schemes water Supply Scheme at Councilor Muhammad Ali Dera Ghazi On-going 81 1684 25.000 24.000 0.333 0.250 0.188 75% 97% "• Date of A.A = 23.09.2016 Basti Rojhani Sakhi Sarwar Khan Schemes Reheblitiation/Extension of Water Supply Scheme Tunga Menhal Phase-II (Basti Ouroo, Basti Jora, Dera Ghazi On-going 82 1685 20.000 4.844 5.051 3.788 2.841 75% 38% "• Date of A.A = 25.7.2017 Basti Rind, Basti Bun Dhola, Basti Gabolan, Basti Khan Schemes Manka & Basti Mahool jee) Rehabilitation of Water Supply in Pir Qatal PP-244 Dera Ghazi On-going 83 1686 10.000 4.998 1.667 1.250 0.913 73% 59% "• Date of A.A = 25.7.2017 District Dg Khan Khan Schemes Rehabilitation of Water Supply in Shehzada Sultan Dera Ghazi On-going 84 1687 10.000 4.000 2.000 1.500 1.125 75% 51% "• Date of A.A = 25.7.2017 Town PP-244 District Dg Khan Khan Schemes Rehabilitation of Water Supply in Mehboob Abad Dera Ghazi On-going 85 1688 10.000 4.999 1.667 1.250 0.888 71% 59% "• Date of A.A = 25.7.2017 PP-244 District Dg Khan Khan Schemes On-going 86 1689 Improvement of Rural water Supply Scheme Dajal Rajanpur 228.679 217.875 3.601 2.701 1.801 67% 96% "• Date of A.A = 23.12.2014 Schemes water Supply Schemes in Mouza Fateh Pur and On-going 87 1690 Muzaffargarh 70.000 18.680 4.173 3.130 2.087 67% 30% "• Date of A.A 22-09-2016 Ali Pur District Muzaffargarh Schemes Date of AA(DDWP) 06.10.2015. . Date of TS. 22-02- Provision of Fund for Restortaion of water Supply 2016. Date of invitation of tenders=28-01-2016. Scheme in his Constituency District Bahwalnagar Date of receipt of tenders = 02-03-2016. Date of On-going 88 1691 (i) RWSS Khattan,(ii) RWSS Jananay wala, (iii) Bahawalnagar 67.817 49.499 5.339 2.248 1.900 85% 76% award= 30-04-2016. Date of completion 29-04-2018. Schemes Date of receipt of funds by F.D. 20.07.2018 & RWSS Ghulab Ali,(iv) RWSS Bajak & Khamay 11.01.2019. Completed & handed over. Excess Wala funds Rs.1.756 million surrendered dated 19.10.2018. Date of A.A: 22-01-2015. . Date of T.S 26-01-2015. Date of revised T.S 12-01-2017. Date of receipt of Rehabilitation of Rural water Supply Scheme On-going tenders =15-04-2015 . Date of work order= 22-05- 89 1692 Chak No 62 4R Tehsil Haroonabad District Bahawalnagar 38.959 36.550 0.320 0.240 0.205 85% 94% 2015. Date of completion as per agreement= 21-11- Schemes Bahawalnagar 2015.Anticipated date of completion= 30-06- 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Completed Date of AA. 08.08.2016. Date of T.S. 21.10.2016. Tender received on 02.11.2016. Date of award. Rehabilitation of rural water Supply scheme chak On-going 25.11.2016. Date of completion 24.11.2017. 90 1693 Bahawalnagar 39.568 38.934 0.211 0.054 0.054 100% 99% Anticipated date of completion 31-12-2018. Date of no. 69/4-R, 80/1-L & Azafi Abadis Chak No. 85/5-R Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019.Scheme completed. Excess funds Rs.0.104 million surrendered dated 19.10.2018.

Date of AA. 19.08.2016. Date of T.S. 25.10.2016. Rehabilitation of Rural water Supply Schemes .Date of receipt of tenders= 14-12-2016 . Date of On-going 91 1694 Muga Chandna Mirdin Hakim Mirdin Mohib Ali Bahawalnagar 99.971 53.035 6.667 5.000 4.000 80% 57% award=29-12-2016. Date of completion=28-11- Schemes 2017. Anticipated date of completion 30-06-2019. Khazan Singh Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of AA(DDWP). 18-08-2015 . Date of TS. 06-10- 2015. Date of receipt of tenders = 20-10-2015 . Date of work order= 04.11.2015. . Date of completion as Rural water Supply Scheme Jand wala and Jand On-going per agreement= 03.11.16. .Anticipated date of 92 1695 Bahawalnagar 25.000 19.550 1.817 0.459 0.415 90% 80% wala sani Schemes completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Scheme Completed in saving & handed over. Excess funds Rs.0.904 million surrendered dated 19.10.2018.

Date of AA (DDSC). 15-10-2015. Date of TS. 22-02- 201`6. Date of prequalification on 22-03-2016. Date On-going of receipt of tenders = 07-04-2016. Date of work 93 1696 water Supply Scheme Doonga Boonga Bahawalnagar 174.252 120.139 6.667 5.000 4.300 86% 71% awarded 18.05.2016. Date of completion as per Schemes Agreement: 18.11.2017 .Anticipated date of completion 30-06-2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of AA. 19.08.2016. Date of T.S. 25.10.2016. Rural water Supply Schemes Mouza Janu Khan .Date of receipt of tender=14-12-2016. Date of On-going 94 1697 Basti Kapooran and kot Ganga Singh District Bahawalnagar 97.808 43.343 6.667 5.000 4.300 86% 49% award +19-01-2017. Date of completion+18-12- Schemes 2017. Anticipated date of completion 30-06-2019. Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of AA(DDWP). 06.10.2015. . Date of TS. 22- 02-2016. Date of receipt of tenders = 02-03-2016. On-going 95 1698 water Supply Scheme Noor Sar (New & Old) Bahawalnagar 72.817 42.617 3.333 2.500 2.050 82% 61% Date of work order=01-04-2016. Date of completion Schemes as per agreement= 30-10-2017.Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA. 08.08.2016. Date of T.S. 21.10.2016. Tender received on 02.11.2016. Date of award. 28.11.2016. Date of completion 27.11.2017. Rural water Supply scheme chak no. 128/6-R On-going Anticipated date of completion 30-06-2019. Date of 96 1699 Bahawalnagar 22.200 20.273 0.536 0.134 0.122 91% 92% including all adjoining abadies. Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Scheme completed in saving & handed over to CBO for O & M . Excess funds Rs.0.268 million surrendered dated 19.10.2018. 1. Date of AA = 15.12.2016 2. Date of TS = 23.12.2016 3.Date of Award of work . 19.05.2017 Rural water Supply Scheme, Kalowal Thathi Bala On-going 4.Dated of Released Funds 4. No. of Beneficiaries = 97 1700 Chiniot 13.322 6.430 2.297 1.723 0.800 46% 54% 5375 Persons Funds Released upto 24.01.2019 by Raja Tehsil Lalian District Chiniot Schemes the Chief Engineer (South) PHED Lahore and work is in progress. Target progress will be achieved in coming month. Rehabilitation and Repair of Sewerage Scheme On-going 98 1701 of Housing Scheme , Gujar Khan City, Tehsil Gujar Rawalpindi 29.980 15.158 3.333 3.500 2.667 76% 59% Work in progress. Schemes Khan, District Rawalpindi Drainage / Sewerage System in Village On-going A.A Date 03.09.2014.T.S Date 29.09.2014. Date of 99 1702 Ghourgushti (Phase II), Tehsil Hazro, District Attock 88.786 85.975 0.937 0.703 0.469 67% 97% Start of Scheme 16.12.2014.Date of Completion of Schemes attock Scheme 30.06.2019.Work is in progress. Drainage and Sanitation scheme in village On-going A.A Date 01.10.2013. T.S Date 27.01.2014. Date of 100 1703 Attock 44.134 26.243 5.960 1.490 0.000 0% 59% Start of Scheme 06.03.2014.Date of Completion of Hameed, Tehsil Hazro, District attock Schemes Scheme 30.06.2019. Dispute of land. Construction of Street Pavement in Village Kalu On-going A.A Date 23.01.2015. T.S Date 18.04.2015.Date of 101 1704 Kalan (Phase II), (PP 16) Tehsil Hazro District Attock 26.227 24.730 1.497 2.023 0.749 37% 97% Start of Scheme 05.06.2015.Date of Completion of Schemes attock Scheme 30.06.2019.Work is in progress. Extension of Rural Drainage Scheme in Villages On-going A.A Date 05.08.2016.T.S Date 15.08.2016. Date of 102 1705 Attock 60.055 46.834 4.405 3.304 2.203 67% 82% Start of Scheme 28.11.2016. Date of Completion of Haroon, Saleem Khan & Adalzai Schemes Scheme 30.06.2019.Work is in progress.

Rural Drainage Scheme in Villages Chachi, On-going A.A Date 12.04.2017. T.S Date 18.04.2017. Date of 103 1706 Attock 29.955 20.816 3.046 2.285 1.523 67% 75% Start of Scheme 10.06.2017.Date of Completion of Saiden, Yasin Schemes Scheme 30.06.2019.Work is in progress.

Rural drainage Scheme in Village Mirza Phase2 On-going A.A Date 05.08.2016.T.S Date 09.09.2016.Date of 104 1707 Attock 104.909 28.955 6.667 5.000 3.334 67% 31% Start of Scheme 16.03.2017. Date of Completion of Tehsil and District attock. Schemes Scheme 30.06.2019.Work is in progress.

Rural drainage scheme in villages Formli,haider On-going A.A Date 01.04.2016. T.S Date 22.04.2016. Date of 105 1708 Attock 55.840 42.497 4.448 3.336 2.224 67% 80% Start of Scheme 30.05.2016.Date of Completion of Mallah,District attock. Schemes Scheme 30.06.2019.Work is in progress.

Rural drainage scheme in villages Perzai, Muraria, On-going A.A Date 01.04.2016. T.S Date 09.09.2016.Date of 106 1709 Attock 29.604 26.725 0.602 0.882 0.731 83% 93% Start of Scheme 24.11.2016. Date of Completion of Pandak, District attock Schemes Scheme 30.06.2019.Work is in progress.

Rural drainage scheme in villages Ramu,Bhadar On-going A.A Date 01.04.2016. T.S Date 20.04.2016.Date of 107 1710 Attock 29.208 28.717 0.491 0.368 0.246 67% 99% Start of Scheme 31.05.2016.Date of Completion of Khan,District attock Schemes Scheme 30.06.2019.Work is in progress.

Rural drainage scheme in villages, Nartopa, On-going A.A Date 05.08.2016. T.S Date 15.08.2016.Date of 108 1711 Attock 55.106 26.472 3.333 3.670 2.837 77% 53% Start of Scheme 24.11.2016.Date of Completion of Khagwani, District attock Schemes Scheme 30.06.2019.Work is in progress. Date of A.A 17.09.2015. Date of T.S 08.10.2015. Const. of Sewerage & Drainage Scheme Kallar On-going ateof Start 18.03.2016.Date of completion 109 1712 Chakwal 98.759 47.426 3.333 4.325 3.492 81% 52% 31.12.2019.Woork is in progress. Funds to the tune Kahar Schemes of Rs.1.825 Million re-appropriated from other schemes to meetup the progress of work. Date of A.A 20.04.2017. Date of T.S On-going 110 1713 Rural Drainage Scheme Mangwal District Chakwal Chakwal 11.000 9.773 0.392 0.098 0.000 0% 89% 22.04.2017.Date of Start 12.06.2017.Date of Schemes scheme.completed.Excessive funds surrendered through reappropriation. Date of A.A 20.04.2017 .Date of T.S Rural Drainage Scheme UC Udherwal District On-going 111 1714 Chakwal 14.000 12.424 0.482 0.121 0.000 0% 89% 22.04.2017.Date of Start 10.06.2017.Date of Chakwal Schemes scheme completed. Excessive funds surrendered through re-appropriation. Date of A.A 20.04.2017. Date of T.S Rural Drainage Scheme UC Nara Mogla District On-going 112 1715 Chakwal 11.000 9.563 0.476 0.119 0.000 0% 87% 22.04.2017.Date of Start 08.06.2017.Scheme Chakwal Schemes completed. Excessive funds surrendered through re- appropriation. Date of A.A 24.08.2016. Date of T.S 01.11.2016. On-going 113 1716 Sewerage Scheme Lawa, District Chakwal Chakwal 78.169 49.975 3.333 2.500 1.667 67% 66% Date of Start 23.12.2016. Date of completion Schemes 31.12.2019.Full funds utilized. Scheme is short funded. On-going "Date of A.A 24.08.2016 . Date of T.S 114 1717 Rural Drainage Scheme Khanpur Chakwal 150.000 52.462 5.000 5.750 4.495 78% 38% 01.11.2016.Date of Start 16.01.2017.Date of Schemes completion 30.06.2020 Date of A.A 16-03-16.Date of T.S 28-03- Improvement/Rehabilitation of Sewerage System in On-going 2016.Revised T.S 18-10-2017.Date of 115 1718 Jhelum 29.800 27.764 0.676 0.169 0.000 0% 93% Bilal Town Tehsil & District Jhelum Schemes Commencement 07-05-2016.Scheme Completed in saving funds are reappropriated to other scheme. Rural drainage scheme Pinanwal, Tehsil Pind On-going 116 1719 Jhelum 100.000 19.985 3.333 2.500 1.667 67% 22% Date of A.A 26-08-2016.Date of T.S 15-12-2016.• Dadan Khan. Schemes Work awarded on 02-03-2017. • Work in progress. Date of A.A 27.08.2016, Date of T.S 03.09.2016, Date of Award 06.12.2016, Scheduled date of Completion on 05.12.2017, Date of Sewerage scheme Mouza Ahmaday Wala District On-going 117 1720 Sargodha 23.426 19.959 1.149 0.575 0.575 100% 88% Commencement, 06.12.2016, Funds released on Sargodha Schemes 30.07.2018, Funds on-lined on 30.07.2018.Sullage Carrier 3250-Rft & Drain 9841-Rft constructed. PCC Slab 18393-Cft & Soling 19458-Cft laid. Work in progress. "Date of A.A 27.08.2016, Date of T.S 03.09.2016, Sewerage/Sullage Carrier for Jalpana/Chak On-going Date of Award 08.12.2016, Scheduled date of 118 1721 Sargodha 30.000 20.807 2.795 2.096 1.548 74% 75% Completion on 07.12.2017, Date of Muzafarabad/Masar/Sardarpur etc. Schemes Commencement, 08.12.2016, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.

"Date of A.A 27.08.2016, Date of T.S 28.10.2016, RSD Scheme Chak No 4 SP Chak No 5 NB Chak On-going Date of Award 14.02.2017, Scheduled date of 119 1722 Sargodha 105.642 44.397 3.333 2.500 2.500 100% 44% Completion on 13.02.2018, Date of No 7 ML Chak No 65 SB Hujjan District Sargodha Schemes Commencement, 14.02.2017, Funds released on 30.07.2018, Funds on-lined on 30.07.2018. Date of A.A 27.08.2016, Date of T.S 07.11.2016, Date of Award 10.02.2017, Scheduled date of Completion on 09.02.2018, Date of Rural Sewerage / Drainage PCC Scheme for On-going 120 1723 Sargodha 100.000 34.967 3.333 2.500 2.500 100% 37% Commencement, 10.02.2017, Funds released on Jhawarian Schemes 30.07.2018, Funds on-lined on 30.07.2018. 6661- Rft, Nallah, Drain, 2866-Rft 01- No. collecting tank constructed. PCC slab 27375-Cft laid and Work in progress. "Date of A.A 27.08.2016, Date of T.S 28.10.2016, On-going Date of Award 31.01.2017, Scheduled date of 121 1724 Rural Sewerage / Drainage Scheme Bhagtanwala Sargodha 84.030 28.600 3.333 2.500 1.934 77% 36% Completion on 30.01.2018, Date of Schemes Commencement, 31.01.2017, Funds released on 04.08.2017, Funds on-lined on 04.08.2017. "The nomenclature of scheme is wrongly printed in Construction / Rehablitation of streets, Drains , On-going ADP as the correct nomenclature is “Construction / 122 1725 Nullah and Soling 2 Shummali, Village Lak Ditrict Sargodha 6.000 0.100 1.000 0.750 0.000 0% 2% Rehabilitation of Street Drains, Nallah and Soling 20 Schemes Sargodha Shumali, 61 Shumali, Village Lak District Sargodha."" Provision of Sewerage System and PCC Slabs in On-going Date of AA 18.08.2017 Date of TS 11.09.2017 Date 123 1726 Khushab 92.683 14.299 3.333 2.500 2.370 95% 18% of award 22.01.2018 Date of completion 30.06.2020 Village Roda. Schemes Work is in progress. Date of A.A.27-05-2016, Date of T.S.19-05-2017, Date of Start of Work. 10-05-2017, Remarks. E.R.S=3/3, Tube Well=1/1, Pump House=1/1, P/Machinery= Arranged/1, R/FMain= 6"i/d G.I Construction of Rural water Supply Scheme On-going 124 1727 Mianwali 13.500 12.707 0.256 0.192 0.128 67% 95% Pipe=1150/1200, 4"i/d G.I Pipe= 2250/2250, 3"i/d Marmandi Tehsil & District Mianwali Schemes G.I Pipe=3012/3020, 2"i/d G.I Pipe=1400/1400, 6"i/d PVC Pipe=1960/1900, 3"i/d PVC= 9633/9805, G.S. Tank 20000-Glns=1/1, T/Line= Demand Notice paid to Wapda Connection awaited/1. Work is in progress.

Date of A.A.27-08-2016, Date of T.S.09-12-2016, Date of Start of Work.03-02-2017, Remarks RCC Sewer=9"i/d=1240-Arrange/20356, 12"i/d=1130-Rft On-going Laid & 992-arranged /12812, 15"i/d=728-Rft Laid & 125 1728 Sewerage & Sanitation Scheme Daud Khel Mianwali 98.377 19.928 6.667 5.000 3.334 67% 24% 630-Arranged /6645, 18"i/d=1850-Rft Laid/3348, Schemes 21"i/d=832-Arranged/1768, 24"i/d=1573/4870, 27"i/d=3841/5505, 33"i/d=2294/3128, S/Carrier=0/200, PCC Slab=0/33597. Work is in progress. Date of A.A.27-08-2016, Date of T.S.06-10-2016, Date of Start of Work.22-12-2016, Remarks RCC On-going 126 1729 Sewerage & Sanitation Scheme Shahbaz Khel Mianwali 95.743 29.964 6.667 5.000 3.334 67% 35% Sewer=9" i/d=15294/33286, 12"i/d= 14502/21045, Schemes 15"i/d= 3381/3659, 21"i/d= 766/864, 24"i/d=2253/2445, PCC Slab= 0/62379. Work is in progress. Date of A.A.04-08-2015, Date of T.S.14-09-2015, Date of Start of Work 16-11-2015, Remarks RCC Sewerage / Drainage Scheme Mouch, District On-going 127 1730 Mianwali 100.000 46.431 7.856 5.892 3.928 67% 50% Sewer=9" i/d= 23007/35130, 12"i/d= 18238/12053, Mianwali Schemes 15"i/d= 3239/4564, 18"i/d=5720/4902, 21"i/d= 1608 /1126. Sullage Carrier= 230/2411. Work is in progress. Date of A.A.27-08-2016, Date of T.S.03-09-2016, On-going Date of Start of Work 03-12-2016 Remarks RCC 128 1731 Sewerage / Drainage Scheme UC Rokhari Mianwali 50.000 22.466 4.476 3.357 2.237 67% 49% Sewer=9" i/d=10551/13484, 12"i/d= 10290/7642, Schemes 15"i/d= 5982/6288, 18"i/d=1294/1299, Sullage Carrier= 0/200. Work is in progress.

Date of A.A. 27-08-2016, Date of T.S.09-12-2016, Date of Start of Work.27-01-2017, Remarks RCC Sewer=9"i/d=3200-Rft Arranged/19157,12"i/d=8504- Rft Arranged/8786,15"i/d=418-Rft Laid & 2374-Rft Arranged/2826,18"i/d=655-Rft & 945-Rft Rural Sewerage Scheme Harnoli Tehsil Piplan, On-going Arranged/1624, 21"i/d=1173-Laid & 183-Rft 129 1732 Mianwali 94.000 44.953 5.000 3.750 2.498 67% 50% Arranged/1356,24"i/d=900-Laid & 412-Rft Mianwali Schemes Arranged/1329, 30"i/d=380-Rft Laid/392, Screening Chamber =1/1, Collecting Tank 20'dia =1/1,Control Room= 1/1,Discharge Sump=0/1, P/Machinery=0/2, S/Carrier=0/1250, S/Drain= 600/4175, PCC Slab=111243/142412, Culvert=0/1, Electric T/Line=0/1. Work is in progress.

PCC Slab and Sewerage Scheme in Street Noon On-going Date of A.A 27.08.2016 Date of T.S 03.09.2016 130 1733 Bhakkar 48.600 29.681 3.333 2.500 2.500 100% 66% Date of Commencement 28.11.2016 Date of Dager UC Tehsil Kaloor Kot District Bhakkar Schemes completion 31.12.2019 PCC Slab and Sewerage Scheme Shahyan Wala On-going Date of A.A 27.08.2016 Date of T.S 03.09.2016 131 1734 U.C Noora Sharif Tehsil Kaloor Kot District Bhakkar 30.000 14.397 3.333 2.500 1.667 67% 54% Date of Commencement 09.11.2016 Date of Schemes Bhakkar completion 31.12.2019 Provision of Sewerage/Drainage/Nali UC Mullah On-going Date of A.A 10.08.2017 Date of T.S 21.10.2017 132 1735 Bhakkar 30.000 7.000 3.333 2.500 2.000 80% 30% Date of Commencement 03.11.2017 Date of Wali Schemes completion 30.06.2020 Provision of Sewerage/Drainage/Nali UC On-going Date of A.A 10.08.2017 Date of T.S 21.10.2017 133 1736 Bhakkar 30.000 10.000 6.667 5.000 4.334 87% 48% Date of Commencement 03.11.2017 Date of Peerashab Schemes completion 30.06.2020 Sewerage Drainage and PCC Slab and Drain in On-going Date of A.A 27.08.2016 Date of T.S 21.10.2016 134 1737 Town Punjgrain Tehsil Darya Khan District Bhakkar 100.000 46.648 6.667 5.000 5.000 100% 52% Date of Commencement 24.11.2016 Date of Schemes Bhakkar. completion 30.06.2020 Rural Sewerage Drainage Scheme PCC Slab and On-going Date of A.A 27.08.2016 Date of T.S 03.09.2016 135 1738 Bhakkar 49.998 18.599 3.333 2.500 2.161 86% 42% Date of Commencement 03.11.2016 Date of Brick Pavement in Behal City Schemes completion 30.06.2020 Rural Sewerage Drainage Scheme PCC Slab and On-going Date of A.A 27.08.2016 Date of T.S 03.09.2016 136 1739 Bhakkar 39.022 17.991 3.333 2.500 2.167 87% 52% Date of Commencement 28.11.2016 Date of Brick Pavement in Notak City Schemes completion 30.06.2020 Rural drainage Scheme inculding Tuff Tiles and Water Supply Lines for left over streets for Chak On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 137 1740 Faisalabad 10.000 5.000 1.667 1.250 0.520 42% 55% Work order issued on 31-10-2017. Work is in No 411/GB darbar Peer Kandhari tehsil Schemes progress. Funds released on 23.08.2018 & 24.1.19. Tandlianwala District Faisalabad Construction of Drainage Nala at Chak No. On-going Date of A.A 05-08-2017. Date of T.S.05-09-2017. 138 1741 197/RB Wahga Wala Tehsil Saddar, District Faisalabad 3.000 2.000 0.333 0.250 0.167 67% 72% Work order issued on 28-09-2017. Work is in Schemes Faisalabad progress. Funds released on 03.08.2018 & 24.1.19 Construction of Rural Drainage and PCC Road , On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 139 1742 Faisalabad 10.000 1.000 3.000 2.250 1.500 67% 25% Work order issued on 22-11-2017. Work is in UC 63 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19

Construction of Rural Drainage and PCC Road at On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 140 1743 Faisalabad 10.000 1.000 3.000 2.250 1.500 67% 25% Work order issued on 22-11-2017. Work is in U.C. 52 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19 Rehab: of Rural Water Supply Scheme Chak No. On-going AA issued on 14.04.2015. Date of T.S 18.10.2016 141 1744 228/GB Tehsil Sammundari Distt: Faisalabad Faisalabad 21.240 18.698 2.542 1.907 0.720 38% 91% Work order issued on 18.05.2015. Work is in Schemes (Court Case) progress. Funds relased 23.11.2018 & 24.1.19. Construction of sewerage drain at Chak On-going AA issued on 16.03.2017 Date of T.S 31.03.2017 142 1745 Faisalabad 59.879 42.328 1.000 0.750 0.470 63% 71% work order issued on 08.06.2017. Work is in No.469/GB, Samundri, District Faisalabad Schemes progress. Funds released on 23.11.2018 & 24.1.19 Construction of TST Road (2200 feet) at Chak No. On-going 143 1746 353/GB Kot Kabir, (Cahk No. 353/GB to New Faisalabad 4.000 1.000 1.000 0.750 0.750 100% 44% Funds transfer to xen Highway Divison Faisalabad. Schemes Abadi) at District Faisalabad Widening / improvement of at TST Road from 12 On-going 144 1747 feet to 20 feet Chak No.353 to 354 at District, Faisalabad 10.000 4.500 1.000 0.750 0.750 100% 53% Funds transfer to xen Highway Divison Faisalabad. Schemes Faisalabad Provision of Soling/Drainage at Kannal Awan and On-going AA issued on 15.11.2017. Funds received on 23-11- 145 1748 Faisalabad 2.500 0.479 1.000 0.750 0.500 67% 39% 2018. Work order issued on 13.12.2017 Work is in Abadies District Faisalabad. Schemes progress. Provision of Soling/Drainage at UC No. 50 Chak On-going AA issued on 15.11.2017.Funds received on 23-11- 146 1749 Faisalabad 2.000 1.000 1.000 0.750 0.500 67% 75% No.144/GB District Faisalabad Schemes 2018. Work order issued on 13.12.2017. Provision of Soling /Drainage at Bhaman Da Chak On-going AA issued on 15.11.2017. Funds received on 23-11- 147 1750 Faisalabad 2.000 1.000 1.000 0.750 0.500 67% 75% 2018. Work order issued on 13.12.2017. Work is in and Pathan Da Goth District Faisalabad. Schemes Progress.

Provision of Soling/Drainage Chak No.651/2 GB On-going AA issued on 15.11.2017. Funds received on 23-11- 148 1751 Faisalabad 1.000 0.499 0.501 0.376 0.250 66% 75% 2018. Work order issued on 13.12.2017. Work is in District Faisalabad Schemes Progress.Funds released on 23.11.2018 & 24.1.19 Provision of Soling /Drainage at Chak No.653/4 GB On-going AA issued on 15.11.2017. Funds received on 23-11- 149 1752 Abadies Karam Chand and abadi Plots District Faisalabad 2.500 0.998 1.502 1.127 0.750 67% 70% 2018. Work order issued on 13.12.2017. Work is in Schemes Faisalabad. Progress.Funds released on 23.11.2018 & 24.1.19 Provision of Soling/Drainage Chak No.652/3GB On-going AA issued on 15.11.2017. Funds received on 23-11- 150 1753 Faisalabad 1.000 0.500 0.500 0.375 0.250 67% 75% 2018. Work order issued on 13.12.2017. Work is in District Faisalabad Schemes Progress.Funds released on 23.11.2018 & 24.1.19 Construction of TST Road Jhangar Awan and On-going 151 1754 Faisalabad 5.000 1.500 1.000 0.750 0.750 100% 45% Funds transfer to xen Highway Divison Faisalabad. Abaedies District, Faisalabad. Schemes AA issued on 15.11.2017. Funds received on 23-11- Provision of Soling/Drainage Chak No.147/GB On-going 2018. Work order issued on 13.12.2017. Funds 152 1755 Faisalabad 1.000 0.471 0.529 0.397 0.260 65% 73% District Faisalabad Schemes could not be utilized due to site Problems. Work is in progress.Funds released on 23.11.2018 & 24.1.19

Provision of Soling /Drainage at Chak No.144/GB On-going AA issued on 15.11.2017. Funds received on 23-11- 153 1756 Faisalabad 2.000 0.500 1.500 1.125 0.690 61% 60% 2018. Work order issued on 13.12.2017. Work is in District Faisalabad. Schemes Progress.Funds released on 23.11.2018 & 24.1.19

Provision of Soling /Drainage at Chak No.145/GB On-going AA issued on 15.11.2017. Funds received on 23-11- 154 1757 Faisalabad 2.500 0.997 1.503 1.127 0.700 62% 68% 2018. Work order issued on 13.12.2017. Work is in District Faisalabad. Schemes Progress.Funds released on 23.11.2018 & 24.1.19

Provision of Soling/Drainage Chak No.459/GB On-going AA issued on 15.11.2017. Funds received on 23-11- 155 1758 Faisalabad 1.500 0.479 1.021 0.766 0.500 65% 65% 2018. Work order issued on 13.12.2017. Work is in Bhooli de Jhok District Faisalabad Schemes progress.Funds released on 23.11.2018 & 24.1.19

Provision of Soling/Drainage at UC No. 51 Pind On-going AA issued on 15.11.2017. Funds received on 23-11- 156 1759 Faisalabad 2.500 0.486 1.000 0.750 0.480 64% 39% 2018. Work order issued on 13.12.2017. Work is in Essa Faisalabad Schemes progress.Funds released on 23.11.2018 & 24.1.19

Provision of Soling /Drainage at Chak No.569/Gb On-going AA issued on 15.11.2017. Funds received on 23-11- 157 1760 Faisalabad 3.500 0.988 1.000 0.750 0.490 65% 42% 2018. Work order issued on 13.12.2017. work is in Abadi Abdullah Khan District faisalabad. Schemes progress.Funds released on 23.11.2018 & 24.1.19

Provision of Soling /Drainage at RosheShani On-going AA issued on 15.11.2017. Funds received on 23-11- 158 1761 Faisalabad 1.000 0.389 0.611 0.458 0.300 66% 69% 2018. Work order issued on 13.12.2017. Work is in Awana and Abadies District Faisalabad. Schemes progress.Funds released on 23.11.2018 & 24.1.19 Provision of Soling /Drainage at UC 45 Chak On-going AA issued on 15.11.2017. Funds received on 23-11- 159 1762 No.644/GB Abadi KaluKa Thatha and Saidpur Faisalabad 2.000 0.475 1.525 1.144 0.650 57% 56% 2018. Work order issued on 13.12.2017. Work is in Schemes District Faisalabad. progress.Funds released on 23.11.2018 & 24.1.19 Provision Main Drainage at Chak No.120/GB On-going AA issued on 15.11.2017. Funds received on 23-11- 160 1763 Faisalabad 1.497 0.994 0.503 0.377 0.240 64% 82% 2018. Work order issued on 13.12.2017. work is in District Faisalabad. Schemes progress.Funds released on 23.11.2018 & 24.1.19 Date of A.A 16.03.2017 Date of T.S 24.03.2017 Date of Receipt of tender 20.04.2017 Date of work Sewerage / Drainage Scheme Garh Mor, On-going 161 1764 Jhang 81.940 20.000 8.333 6.250 4.858 78% 30% order 07.07.2017. Date of Completion As per PC- Ahmedpur Sial Schemes I06.07.2019 Anticipated date of completion 06.07.2019 Agreement Amount 74.993-Million Work is in progress. 1-Date of A.A 20.10.2016 2- Date of T.S 11.11.2016 3-Date of Prequalification - 21.11.2016 4-Date of invitation of tenders 16.12.2016 5- Date of Receipt Sewerage Drainage and Street Pavement, On-going of tenders 17.12.2016 6- Date of work order - 162 1765 Toba Tek Singh 100.000 30.000 3.333 1.800 1.100 61% 31% 27.12.2016 7- Date of completion as per PC-I Sandhilianwali, District Toba Tek Singh Phase I Schemes 26.12.2018 8- Anticipated date of completion 26.12.2018 9- No. of Beneficiary - 33312 Person 10- Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds(+/-) Work in progress.

Construction of disposal Sewerage Drainage PCC On-going 163 1766 Scheme Morr Eminabad Sharqi UC Dhillanwali Gujranwala 199.920 117.216 6.667 5.000 3.334 67% 60% Work in progress Schemes Tehsil and Distt. Gujranwala

Construction of Drains / PCC and Sewerage On-going 164 1767 Gujranwala 67.393 17.393 6.667 5.000 3.334 67% 31% Work in progress Scheme at UC Bhikhu Pura, District Gujranwala Schemes

Construction of Drains / PCC and Sewerage On-going 165 1768 Gujranwala 64.261 19.260 5.000 3.750 2.500 67% 34% Work in progress Scheme at UC Shaheenabad, District Gujranwala Schemes PCC and Sewerage Schemes at Khiali Shahpur On-going 166 1769 Gujranwala 198.537 153.991 20.000 21.218 16.218 76% 86% Work in progress District Gujranwala. Schemes PCC Sewerage Drainage Scheme Disposal UC On-going 167 1770 City Ladhywala Warraich Qila Dedar Singh Madu Gujranwala 149.647 140.598 3.016 2.262 1.508 67% 95% Work in progress Schemes Khalil Ghakh Provision of Sewerage Drainage and water Supply On-going 168 1771 Gujranwala 196.624 138.865 6.667 5.000 3.334 67% 72% Work in progress scheme in Qila Dedar Singh Gujranwala Schemes Provision of Sewerage, New Disposal & PCC at On-going 169 1772 Kot Qazi & Mudhokhalil, Tehsil Saddar, Gujranwala 186.266 89.505 30.000 22.500 15.000 67% 56% Work in progress Schemes Gujranwala Provision of Sewerage, New Disposal & PCC at On-going 170 1773 Ladhay wala Warraich & Mughal Chak, Tehsil Gujranwala 195.240 100.000 30.000 22.500 15.000 67% 59% Work in progress Schemes Saddar, Gujranwala Provision of Drainage PCC Facilities at UC Artali On-going 171 1774 Gujranwala 30.000 19.958 3.335 2.501 1.668 67% 72% Work in progress Virkan Tehsil Nowshera Virkan District Gujranwala Schemes

Provision of Drainage PCC Facilities at UC Baddo On-going 172 1775 Gujranwala 30.000 19.870 3.334 2.501 1.667 67% 72% Work in progress Ratta Tehsil Nowshera Virkan District Gujranwala Schemes Provision of Drainage / PCC Schem at UC Chahal On-going 173 1776 Gujranwala 77.757 19.999 3.333 2.500 1.667 67% 28% Work in progress Kalan, District Gujranwala Schemes Drainage Sewerage and PCC UC atawa UC Rakh On-going 174 1777 Gujranwala 280.818 151.994 14.117 10.588 7.059 67% 57% Work in progress Kikran Wali Schemes PCC and Drainage Facility at Sadoki,Dargahapur On-going 175 1778 Gujranwala 158.153 84.945 3.333 2.500 1.667 67% 55% Work in progress and others in Tahsil Kamoki Schemes

Provision of PCC/Drainage Sewerage Schemes at On-going 176 1779 Gujranwala 131.295 110.646 6.883 1.720 0.000 0% 84% Scheme completed UC No 14, 15, 46, 50, 51, 52, 53 Gujranwala Schemes

Provision of PCC/Drainage/Sewerage Scheme at On-going 177 1780 Gujranwala 194.226 75.000 20.000 15.000 10.000 67% 44% Work in progress Municipal Committee, Ghakar Mandi Schemes Const. of disposal Sewerage Drainage PCC On-going 178 1781 Scheme Morr Eminabad Gharbi Audo Rai UC Gujranwala 178.291 99.864 6.667 5.000 3.334 67% 58% Work in progress Schemes Maraliwala Tehsil and Distt. Gujranwala Const. of Sewerage Drainage- PPC Soling in On-going 179 1782 UCs Tehsil Noshera Virkan including UCs No. Gujranwala 467.500 89.888 1.000 0.750 0.500 67% 19% Work in progress. Schemes Wala Jhatan wali & Sahran Chahta Rural Drainage and PCC Scheme at Wandala Virkan Taly Aali Badhay new Abadi Gaibi Lunj On-going 180 1783 Sharif Kolo wala, Matu Bhanake Al Ditta, Ratta Gujranwala 50.000 19.997 3.333 2.500 1.667 67% 43% Work in progress Schemes Goraya, Chak Poryan ana Paryan, Karyal Khan and and Adjoining Dera Jattan. Rural Drainage PCC Scheme Kot Nisar Shah On-going 181 1784 Boopara Khurd Dhairr Virkan Bhirri Shah Rehman Gujranwala 109.270 46.942 6.667 5.000 3.334 67% 46% Work in progress Schemes Dharoke Sadu Sewerage Scheme Kamoke of Leftover Area On-going 182 1785 Gujranwala 199.100 65.949 5.000 3.750 2.500 67% 34% Work in progress Gujranwala Schemes Imrovement of Sewerage, Solling, Drain Tatley Aali On-going 183 1786 Gujranwala 103.000 10.000 20.000 15.000 10.000 67% 19% Work in progress. Road Kamokay Schemes Provision of PCC/Sewerage/Drainage/Solling etc. On-going 184 1787 in village Chachoke Tehsil Noshera Virkan District Gujranwala 15.000 9.941 1.667 1.250 0.834 67% 72% Work in progress. Schemes Gujranwala Provision of PCC/Drainage Scheme in UC Kalaske, Kot Amar singh, Kot Shaira, Batla Janda On-going 185 1788 Gujranwala 197.800 19.996 30.000 22.500 15.000 67% 18% Work in progress Sigh, Uggu Chak Paponakha, UC 71 Khiyali # 14 Schemes MC Qila Didar Singh Provision of Clean Drinking Water/Sewerage On-going 186 1789 Scheme at Ldhay wala Waraich, Madhu Khalil, Gujranwala 199.779 50.000 30.000 22.500 15.000 67% 33% Work in progress. Schemes Chain Wala etc Provision of Sewerage / Drainage and PCC On-going 187 1790 Gujranwala 40.000 10.000 5.000 3.750 2.500 67% 31% Work in progress. facilities Qila didar singh Gujranwala Schemes Provision of Sewerage Drainage and PCC facilities On-going 188 1791 Gujranwala 40.000 10.000 5.000 3.750 2.500 67% 31% Work in progress. Gakhar City Gujranwala Schemes Sewerage and PCC Scheme for Bismillah Colony On-going 189 1792 Gujranwala 105.000 96.046 2.985 2.239 1.493 67% 93% Work in progress Wania and Adjacent Area Gujranwala Schemes RSD/ PCC Scheme UC Shamsa Dada UC Majju On-going 190 1793 Chak UC Bhoopra Kalan UC Argan UC Philloke Gujranwala 168.000 46.983 3.333 2.500 1.667 67% 29% Work in progress Schemes and UC Abidabad Gujranwala Rural Drainage/PCC Scheme in U.C. Garmula Virkan, U.C Budha Goraya, Dogranwala, U.C On-going 191 1794 Phama Sara, Kalsian Dhutran, Kot Bilal and Gujranwala 109.270 29.914 5.000 3.750 2.500 67% 30% Work in progress Schemes Madan Chak, Tehsil Nowshera Virkan, Dist. Gujranwala (Revised) Rural Drainage Scheme UC Kot Hassan Khan On-going A.A. 98.000(M) T.S.98.000 (M) work is in progress 192 1795 Hafizabad 98.000 10.000 3.333 2.500 1.667 67% 12% Kassoki Karyala & Allied Abbadies Schemes Fund release but not yet online. Rural Drainage Scheme UC Chak Chattha Sabir On-going 193 1796 Kalan Kallian Wala & Allied Abbadies, District Hafizabad 98.000 10.000 1.000 4.084 3.330 82% 14% A.A. 98.000(M) T.S.98.000 (M) work is in progress Schemes Fund release but not yet online. Hafizabad * Org. A.A Date. 03.10.2011* Rev. A.A Date. Drainage/Sewerage and water Supply Scheme of Mandi On-going 194 1797 102.080 73.238 3.333 2.600 2.600 100% 74% 23.02.2013* T.S Date. 18.11.2011* Start Date Mangat and Rasul Bahauddin Schemes 02.11.2011* Completion date 30.06.2019.* Work in progress. Construction of street, Drainage and Soling of Mandi On-going 195 1798 Kakka and Kot Jafar, Chak No.18 & 19, District 6.500 5.737 0.167 0.100 0.059 59% 89% * A.A Date. 09.03.2017* T.S Date. 10.03.2017* Start Bahauddin Schemes Date 12.04.2017 M.B.Din Construction of street, Drainage and Soling of Mandi On-going 196 1799 Khizar and Chak No.52, UC Chot Dheeran, District 13.000 10.726 0.644 0.433 0.272 63% 85% * A.A Date. 09.03.2017* T.S Date. 10.03.2017* Start Bahauddin Schemes Date 11.04.2017 M.B.Din Provision of Sewerage / Drainage / Pavement in Mandi On-going * A.A Date. 28.01.2015* T.S Date. 08.02.2015* Start 197 1800 50.000 48.643 0.252 0.189 0.126 67% 98% Halian & Ghanian, Tehsil Bahauddin Schemes Date 11.04.2015 Provision of Sewerage / Drainage / Pavement in Mandi On-going * A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start 198 1801 Jano Chak Khurd & Kalan , Basi Khurd & Kalan, 75.571 52.495 3.333 1.250 0.417 33% 70% Date 24.12.2016* Completion date 30.06.2019.* Bahauddin Schemes Channi Mast, Aado Sarwani. Work in progress. Provision of Sewerage / Drainage / Pavement in Mandi On-going 199 1802 64.664 50.171 4.824 1.668 0.462 28% 78% * A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start Narang / Saadullaha Pur / Khoosor Bahauddin Schemes Date 24.12.2016

Provision of Sewerage / Drainage / Pavement in Mandi On-going * A.A Date. 28.01.2015* T.S Date. 08.02.2015* Start 200 1803 Sarlay,Lasoori Kalan,Duggal, Phalia Boota (Incl. 50.000 44.765 1.579 0.594 0.200 34% 90% Date 11.04.2015* Completion date 30.06.2019.* Bahauddin Schemes THQ Hospital), Tehsil Pahila Work in progress. Rural Sewerage/Drainage scheme village Bosal, Mandi On-going * A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start 201 1804 90.500 79.269 3.744 2.808 1.872 67% 90% Date 17.12.2015* Completion date 30.06.2019.* Tehsil Malikwal, District M.B. Din Bahauddin Schemes Work in progress. Rrural/Sewerage/Drainage Scheme pindi Kalu Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 202 1805 50.000 14.942 11.667 11.750 8.834 75% 48% Date. 06.01.2018* Completion date 05.01.2019* Tehsil Phalian District Bahauddin Schemes Work in progress. * A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start Date 23.12.2016.* Completion date 30.06.2019.* Sewerage Drainage Scheme UC Dhok Kasib Mandi On-going 203 1806 20.000 19.500 0.166 0.104 0.062 60% 98% Scheme completed in saving.* A.A Date. Tehsil & District M B Din Bahauddin Schemes 23.09.2016* T.S Date. 24.09.2016* Start Date 23.12.2016.* Completion date 30.06.2019.* Scheme completed in saving. Sewerage & Drainage Scheme U.C Rasul Tehsil & Mandi On-going * A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start 204 1807 20.000 19.421 0.184 0.099 0.053 54% 97% Date 21.12.2016.* Completion date 30.06.2019.* District M.B.Din. Bahauddin Schemes Scheme completed in saving. Sewerage / Drainage of Village Rerka Mumdana, Mandi On-going * A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start 205 1808 41.684 24.326 5.753 3.415 1.977 58% 63% Date 29.12.2016* Completion date 28.12.2019.* Tehsil Malikwal Bahauddin Schemes Work in progress Rural Sewerage, Drainage/Soling & PCC Scheme Mandi On-going * A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start 206 1809 in Chak No. 20 With Abadies Tehsil Malikwal Distt. 50.000 45.999 1.334 1.001 0.667 67% 93% Date 19.11.2016* Completion date 30.06.2019.* Bahauddin Schemes M.B Din Work in progress Rural Sewerage, Drainage/Soling & PCC Scheme Mandi On-going * A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start 207 1810 in Villages Main Mandi Mona Depot 53.052 42.556 2.629 0.972 0.315 32% 81% Date 07.02.2017* Completion date 30.06.2019* Bahauddin Schemes Tehsil Malilwal District M.B.Din Work in progress Rural Sewerage / Drainage Scheme of Village Mandi On-going * A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start 208 1811 73.499 29.396 5.000 3.750 2.500 67% 43% Date 24.12.2016* Completion date 30.06.2019.* Bherowal Tehsil Phalia Distt. Mandi Bahauddin Bahauddin Schemes Work in progress

Rural Sewerage / Drainage Scheme of Village Khai Mandi On-going * A.A Date. 23.09.2016* T.S Date. 28.10.2016 * 209 1812 74.464 61.888 4.180 1.485 0.440 30% 84% Start Date 06.12.2016* Completion date and Bukkan Tehsil & Distt. M.B. Din Bahauddin Schemes 30.06.2019.* Work in progress Rural Sewerage / Drainage Scheme Village Mandi On-going * A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start 210 1813 55.150 45.574 3.192 1.079 0.281 26% 83% Date 17.12.2015* Completion date 30.06.2019.* , Tehsil & District M.B. DIN Bahauddin Schemes Work in progress Sewerage / Drainage Schemes in Adda Pharainwali, Sandhanwala, Haigerwala, , Mandi On-going * A.A Date. 06.09.2017* T.S Date. 24.10.2017* Start 211 1814 247.904 79.958 6.667 2.000 0.334 17% 32% Date. 08.01.2018* Completion date Dhall, Dhola, Chhani, Lakhia, Chak No. 38., and Bahauddin Schemes 07.01.2021*Work in progress. Ahdi in District M.B.Din Provision of PCC / Sewerage / Drainage and allied Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 212 1815 50.000 28.500 7.167 5.375 3.584 67% 64% Date. 06.01.2018* Completion date 05.01.2019* faiclities in PP-120, District M.B.Din Bahauddin Schemes Work in progress. Sewerage and Drainage scheme of and Mandi On-going * A.A Date. 25.08.2017* T.S Date. 07.09.2017* Start 213 1816 100.000 22.099 8.333 6.250 4.167 67% 26% Date. 06.01.2018* Completion date Khanana, District Mandi Baha Ud Din Bahauddin Schemes 05.01.2020*Work in progress. Construction of Brick Pavement PCC Street & Drain / Nullah U.C Mundeke, Ghuinke, Baddokey On-going 214 1817 Sialkot 50.000 29.900 1.667 1.250 0.834 67% 61% Work in progress. Cheema, Allomahar, Jamke Cheema, Tehsil Schemes Daska District Sialkot Construction of PCC, Solling & Drain / Nullah UCs Head Marala, Machrala, Gondal, Bolwanwala , On-going 215 1818 Pindi Punjorian, Kaman Wala Kundan pur, Sialkot 150.000 34.566 3.333 2.500 1.667 67% 24% Work in progress. Schemes Dallowali, Katchi Maund, Pholkin, Wadhgran Tehsil Sialkot District Sialkot

Construction of RCC Sewer & RCC from Zohara Memorial Hospital Chowk to Railway Crossing to On-going 216 1819 Sialkot 175.320 87.576 6.667 5.000 3.334 67% 52% Work in progress. Ajmal Garden to Shetab Garha to Adalat Pur road Schemes to Nullah Aik, Tehsil & District Sialkot Construction of Sewerage and Drainage Scheme On-going 217 1820 Sialkot 30.000 24.983 1.667 1.250 0.834 67% 86% Work in progress. Village Kapooro Wali Tehsil & District Sialkot Schemes Provision of PCC / Soling / Nallain /Streets at Baigo wali bsmulla kot marth ,kot muhmmad hussain ,pipli wala ,begowala adda ,bhola musa On-going 218 1821 Sialkot 80.000 34.470 3.333 2.500 1.667 67% 45% Work in progress. kotli bawarian, kot kuda yar ,kot qadar daad Schemes ,randeer ,bagrian ,chak kupa ,gulab garh, doburji chanda sing ,chowkey ,r Provision of PCC / Soling / Nallain /Streets Schemes at Malkhanwala Bshmula Wan, Pasia, On-going 219 1822 Firdospur, Bangla Nai Abadi, Chak Bassawa, Dhop Sialkot 80.000 34.000 3.333 2.500 1.667 67% 45% Work in progress. Schemes Sari, Hameed Colony, Mehlowal, Abdullah abad, Dera Roshan Gujjar, Amreekh pura District Sialkot

Provision of PCC / Soling / Nullah / Street Scheme at Khambranwala Bashamula, Dogree, Gorian, On-going 220 1823 Sialkot 60.000 34.403 3.333 2.500 1.667 67% 60% Work in progress. Sundar Pur, Bidar, Chak Simanwali etc., Tehsil Schemes Sambrial, District Sialkot [LO160068845]. Provision of PCC / Soling / Nullah / Street Scheme at Bakhray Wali Bashamula, Dogranwala, On-going 221 1824 Sialkot 55.000 19.960 1.667 1.250 0.834 67% 38% Work in progress. Kathiala, Habibpur etc., Tehsil Sambrial, District Schemes Sialkot [LO16006884]. Provision of PCC / Soling / Nullah / Street Scheme at Kulowal Bashamula , Aurtala Sharif, Chak On-going 222 1825 Mughal , Tika , Tambray, Gaghar. Baseer, Jay, Sialkot 100.000 19.980 3.333 2.500 1.667 67% 22% Work in progress. Schemes Ditowali, Chanigondal, etc., Tehsil Sambrial, District Sialkot Provision of PCC / Soling / Nullah / Street Scheme at Gohad Pur Bashamula, Handlapur, Korpur, Nawan Pind, Nangal, Ghiti Shekan, Kansarour, On-going 223 1826 Sialkot 399.852 29.955 3.333 2.500 1.667 67% 8% Work in progress. Tibbi, Arrian, Saleempur, Malkay, Kalan, Malkay Schemes Khurd, Olkh Awana etc., Tehsil & District Sialkot [LO16006880]. Provision of PCC / Soling / Nullah / Street Scheme at Kapurwali, Bashamula Ajjowali, Basant Pur, Dagaray, Malo Chak , Jorian Khurd / Kalan , On-going 224 1827 Sialkot 70.000 19.987 3.333 2.500 1.667 67% 31% Work in progress. Sukhnian, Bhindar, Olakh, Saidpur, Schemes Jatta,Dusri,Kala Ghumna,Khambranwala, Kansar Pur, Canday Wali etc., Tehsil & D Provision of PCC / Soling / Nullah / Street Scheme at Jaithi Kay Bashaula, Joluki, Maja Khurd, Haddokay, Kot Deena, Tibbi Inayat Shah, Deera On-going 225 1828 Sialkot 50.000 19.990 3.333 2.500 1.667 67% 43% Work in progress. Tibbi Inayat Shah, Deera Tarraran, Dra Gujjran, Schemes Dera Arrian, Karan Wali etc.,Teshil & District Sialkot Provision of PCC / Soling / Nullah / Street Scheme at Jassor Wala Bashamula, Chak Gillan Sharki, On-going 226 1829 Chak Gillan Magrabi, Pandorian, Muhammad Pura, Sialkot 50.000 20.000 1.667 1.250 0.834 67% 42% Work in progress. Schemes Gega, Addowali, Rajjokay etc.,Teshil & District Sialkot Provision of PCC / Soling / Nullah / Street Scheme Roras, Bashamula Mango Behram , Pidian, Kot On-going 227 1830 Bagaa, Chak Maluk, Chak Janta, Dhana Wali Sialkot 60.000 20.000 1.667 1.250 0.834 67% 35% Work in progress. Schemes Mehad Pur, Dadowali, Manair etc., Tehsil Sambrial, District Sialkot [LO16006879]. Provision of PCC Sewerage Schemes in UC On-going 228 1831 Dhuda Goraya, MaloMahay, Bogray SEO KE Sialkot 40.000 20.000 3.333 2.500 1.655 66% 54% Work in progress. Schemes District Sialkot Provision of Sewerage and Tuff Tile in Various UCs of District Sialkot, UCs, kotli Behram, Mubarik On-going 229 1832 pura, Miana pura, Model Town, Fateh Garh, Sialkot 120.000 75.000 3.333 2.500 1.667 67% 64% Work in progress. Schemes Muzafar pur, Haji pura, Ban, Haji pura-II, Imam Sahib, Shahab pura, Pacca Garha, Hamza Ghous.

Providing and Laying Tuff Tile RCC Sewer and Construction of Drain /Nullah Mohallah Shahab On-going 230 1833 Sialkot 35.000 31.000 1.333 0.333 0.225 68% 89% Work in progress. Pura Bajli Mohallah Darbar Shahab Shah U/C. Schemes Shahab pura Tehsil & District Sialkot

Construction of PCC Street Drain/ Nullah Providing and Laying of RCC Sewer and Tuff Tile On-going 231 1834 Sialkot 24.400 14.991 3.133 2.350 1.565 67% 68% Work in progress. U/C Water Works (Silver star road Mohallah Schemes Islamia Park) Tehsil & District Sialkot. Construction of PCC Street, Drain/ Nullah Providing and Laying of RCC Sewer and Tuff Tile On-going 232 1835 Sialkot 29.500 20.000 3.167 2.375 1.584 67% 73% Work in progress. U/C Duburj Arraian (Moh. Baba Bari, Habib pura) Schemes Tehsil & District Sialkot Construction of PCC Street, Drain/ Nullah Providing and Laying of RCC Sewer and Tuff Tile On-going 233 1836 Sialkot 28.600 19.938 2.867 2.150 1.434 67% 75% Work in progress. U/C Muhammad pura (Nishat park) Tehsil & Schemes District Sialkot Construction of PCC Street, Drain/ Nullah Providing and Laying of RCC Sewer and Tuff Tile On-going 234 1837 Sialkot 25.500 19.975 1.833 1.375 0.917 67% 82% Work in progress. U/C Water Works (Moh. Pak pura) Tehsil & District Schemes Sialkot Providing & Laying of RCC Sewer, Tuff Tile and Construction of Disposal Station Mohallah Water On-going 235 1838 Works to Abbot Road Phatak and along the Sialkot 50.000 8.000 5.000 1.450 0.964 66% 18% Work in progress. Schemes Railway line to Dara Arrian U/C Water Works, Tehsil & District Sialkot

Providing & Laying of RCC Sewer, Tuff Tile and Construction of Disposal Station Nasir Road Prem On-going 236 1839 Sialkot 50.000 10.000 5.000 2.350 1.450 62% 23% Work in progress. Nagar Road EIC School to Nullah Bhed U/C Model Schemes Town, Tehsil & District Sialkot

Providing and Laying of Tuff Tile RCC Sewer and Construction of Drain / Nullah Mohallah Kashmiri On-going 237 1840 Sialkot 32.000 25.933 2.000 0.700 0.468 67% 83% Work in progress. Sarray Bhabrian Alamgir Bazar Nikhas U/C. Imam Schemes Sahib Tehsil & District Sialkot Provision of PCC/Soling /Nalian/Streets Schemes at Bohalwala Bashamula Chak Kheena, Kotli On-going 238 1841 Nonaan, Kotli Nonaan, Dot Dharan Baddoke Sialkot 80.000 40.500 3.333 5.067 4.230 83% 56% Work in progress. Schemes Cheema, Kot Bhagat, Jalianwala Ahmadabad District Sialkot Provision of PCC/Soling/nalian/Streets Scehmes at Majra kalan, Chak Ekhtiar, Dingowal, Mahiwal, On-going 239 1842 rakh noshra ,kothy pardansing (islambad)khothay Sialkot 90.000 69.860 3.333 2.500 1.667 67% 79% Work in progress. Schemes chistian ,Dorarbe Malianwala Jattan & Arrian, Pano attari Hussain Pur, Jamal Pur District Sialkot Provision of PCC/Soling/Nalian/Streets Schemes at Barath Bhoth Bashamula Markiwal, Khorta On-going 240 1843 Sialkot 50.000 29.945 1.667 1.250 0.834 67% 62% Work in progress. Syedan, Ballanwala, Machi Khokhar, Gul Bahar Schemes Khurd, Gul Bahar Kalan Provision of PCC/Soling/Nalian/Streets Schemes On-going 241 1844 at Chaprar Bashamula Punowal, Najwal, Parwal, Sialkot 55.000 29.978 3.333 2.500 1.667 67% 58% Work in progress. Schemes Sagarpu, Medhi pur, Bagh pur, Sagri pur etc Provision of PCC/Soling/Nalian/Streets Schemes at Gojra Bashamula Thatha Lathi, Qila Tek Singh, On-going 242 1845 Sialkot 50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress. Bhonawali, Phangat, Dheera Sanda, Islam pura, Schemes Kotli wala, Kandan Sian Provision of PCC/Soling/Nalian/Streets Schemes On-going 243 1846 at Mandran Wala Bashamula Adamkay Cheema, Sialkot 75.000 49.601 3.333 2.500 1.667 67% 68% Work in progress. Schemes Nai Abadi, Provision of PCC/Soling/Nalian/Streets Schemes at Saidowali Bashamula Hambokay, Kot Mahraj, On-going 244 1847 Sialkot 70.000 20.000 3.333 2.500 1.667 67% 31% Work in progress. Merian Pindi, Lalaywali, Easa pur, Khorray, Suraj, Schemes Chak Hana etc

Provision of PCC/Soling/Nalian/Streets Schemes On-going 245 1848 at Shahuwala Bashamula Balo Chak, Nashtar Sialkot 28.000 19.920 2.667 2.000 1.334 67% 76% Work in progress. Schemes Abad, Zafarwali, Kamalpur, Manpur etc.

Provision of PCC/Soling/nalian/Streets Schemes at On-going 246 1849 Sheeni Bashamula Chaila, bjola, Muljhan, Sagar, Sialkot 90.000 77.698 3.333 2.500 1.667 67% 88% Work in progress. Schemes punwal ratwal ,chogpur District Sialkot

Provision of PCC/Soling/Nalian/Streets Schemes at Verowala Bashamula Wassankay, Magokaman, On-going 247 1850 Sialkot 50.000 19.925 3.333 2.500 1.667 67% 43% Work in progress. Nandpur, Baryar, Wan Garthal Umarkey Kalan, Schemes Umarkey Khurd, Ahmad abad, Veeramkay etc Const of Streets/drains & PCC in Village On-going 248 1851 Sialkot 60.000 12.990 1.667 1.250 0.834 67% 23% Work in progress. Partanwali Schemes Const of Streets/drains & PCC in Village Saidpur On-going 249 1852 Sialkot 65.000 16.490 3.333 2.500 1.660 66% 28% Work in progress. Kalan Schemes Const. of Nullah from Sublime Chowk to Uggoki On-going 250 1853 More to Sahowala Bridge to Syphonof Nullah Aik, Sialkot 394.111 244.942 16.667 12.500 8.334 67% 64% Work in progress. Schemes Sialkot On-going 251 1854 Const. of PCC Drains / Sewerage Sialkot Sialkot 90.000 62.984 3.333 7.700 6.867 89% 78% Work in progress. Schemes Provision of Sewerage & PCC Schemes in Pero On-going 252 1855 Sialkot 40.000 19.855 1.667 0.550 0.350 64% 51% Work in progress. Chak, Sego Wala, Adha Kanwamlit District Sialkot Schemes Provision of Sewerage & PCC Schemes UC On-going 253 1856 Sialkot 40.000 19.940 1.667 1.250 0.834 67% 52% Work in progress. Jharah Wala Salhoke, Bharlham Wala Schemes Provision of Sewerage / Drainage Scheme at UC On-going 254 1857 Dhodha Tehsil Pasrur District Sialkot (under Sialkot 165.000 90.000 1.673 4.555 4.137 91% 57% Work in progress. Schemes revision) "Date of A.A 25.01.2016, Date of T.S 30.01.2016, Construction of Drains, Soling / PCC and Sullage On-going Date of Award 25.01.2017, Scheduled date of 255 1858 Sialkot 18.164 15.000 1.055 0.791 0.611 77% 86% Completion on 30.06.2018, Date of Carrier of Ghughiat, District Sargodha Schemes Commencement, 25.01.2017, Funds released on 30.07.2018, Funds on-lined on 30.07.2018. Construction of PCC / Drain in Dhera Sardha On-going 256 1859 Sialkot 50.000 47.970 0.667 0.500 0.330 66% 97% Work in progress. District Sialkot Schemes Construction of PCC Drain / Tuff Tile Ward No. 1 to 30 Daska Kalan, Daska Kot, U. C Galotian On-going 257 1860 Kalan, Ranganwala, Moseywala, Gaga, Ladhey Sialkot 70.000 39.545 3.333 2.500 1.667 67% 59% Work in progress. Schemes Bhanbanwal, Thatha, Sukhar Nahar & Bhadeywala, Daska City, District Sialkot. Construction of Drain/Nullah for Diposal of On-going 258 1861 Sewerage at Bhadewal Tehsil Daska District Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Schemes Sialkot Reheblitiation of Sewerage/Drainage Scheme On-going 259 1862 Sialkot 20.000 10.000 3.333 7.500 6.667 89% 83% Work In Progress Mitranwali Tehsil Daska District Sialkot Schemes Sanitation Schemes in UCs, Gadgore, Khanawali, On-going 260 1863 Alhar, Jassoran, Baddiana and Chawinda, Tehsil Sialkot 40.000 26.000 4.667 3.500 2.334 67% 71% Work in progress. Schemes Pasrur Construction of PCC Streets, Drains,Tuff tiles and On-going 261 1864 Sialkot 30.000 14.935 5.000 3.750 2.500 67% 58% Work in progress. Soling in Adalat Garah, District Sialkot Schemes

Construction of PCC Streets, Drains,Tuff tiles and On-going 262 1865 Sialkot 6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress. Soling in Mahal Kingra & Dhanney, District Sialkot Schemes

Construction of PCC Streets, Drains,Tuff tiles and On-going 263 1866 Sialkot 5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress. Soling in Muzafar Pur, District Sialkot Schemes

Construction of PCC Streets, Drains,Tuff tiles and On-going 264 1867 Sialkot 5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress. Soling in Shatab Garah, District Sialkot Schemes Construction of PCC Streets, Drains,Tuff tiles and On-going 265 1868 Sialkot 5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress. Soling in Bonkam, District Sialkot Schemes Construction of PCC Streets, Drains,Tuff tiles and On-going 266 1869 Soling in Ganjianwali & Roheel Garah, District Sialkot 6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress. Schemes Sialkot Construction of PCC streets, Drains,Tuff tiles and On-going 267 1870 Soling in Chak Adil,Chitti Shikhan,Nawan Pind, Sialkot 10.000 5.000 1.000 0.834 0.834 100% 58% Work in progress. Schemes District Sialkot Construction of PCC Streets, Drains,Tuff tiles and On-going 268 1871 Sialkot 10.000 5.000 1.667 1.250 0.834 67% 58% Work in progress. Soling in Murad Pur, District Sialkot Schemes Construction of PCC Streets, Drains,Tuff tiles and On-going 269 1872 Sialkot 10.000 5.000 1.667 1.250 0.834 67% 58% Work in progress. Soling in Gohad Pur, District Sialkot Schemes Construction of PCC Streets, Drains,Tuff tiles and On-going 270 1873 Sialkot 5.000 2.500 1.000 0.750 0.500 67% 60% Work in progress. Soling in Dhanwali, District Sialkot Schemes Construction of PCC Streets, Drains,Tuff tiles and Soling in Village Monger to Nehar Upper Chanab & On-going 271 1874 Sialkot 6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress. Village Ranjhai to Burj Cheema Link Way, District Schemes Sialkot Construction of PCC Streets, Drains,Tuff tiles and On-going 272 1875 Soling in Monger Sofen to Barthanwala, District Sialkot 7.000 3.500 1.167 0.875 0.584 67% 58% Work in progress. Schemes Sialkot Construction of PCC Streets, Drains,Tuff tiles and On-going 273 1876 Sialkot 5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress. Soling in Hunter Pura, District Sialkot Schemes Drainage / PCC scheme for village Gorala On-going A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start 274 1877 Narowal 50.000 34.743 3.333 2.500 1.659 66% 73% Date 16.11.2016 *Completion date 30.06.2019 work Maanpur Schemes in progress. Funds not received on spending end yet PCC , Soling and Drainage Scheme in Village A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start On-going 275 1878 Babral, Kallah, Mahlo, Sahlo,Tehsil Shakargarh, Narowal 41.395 24.992 3.333 2.500 1.663 67% 64% Date 16.11.2016*Completion date 30.06.2019.work Schemes in progress. Funds not received on spending end District Narowal yet. PCC / Soling / Filtration Plant in Village Noor Kot On-going A.A. dated 3.08.17 *Start Date 276 1879 Manngri and Bagha Madan Thakrian Pagla, Narowal 46.000 18.730 1.000 0.750 0.480 64% 42% 16.11.2016*Completion date 30.06.2020 Work in Schemes District Narowal. progress. Fund not received on spending end yet. Construction of Nalian, Soling, PCC & Boundary Walls of Graveyard in UCs Nallah, Bua, Melo Salo, Kalah, Mainagty, Bara Manga, Kot Naina, Bahree, On-going A.A. dated 23.9.2016. T.S. dated 24.9.2016. *Start 277 1880 Narowal 85.000 49.192 3.333 2.500 1.659 66% 60% Date 16.11.2016*Completion date 30.05.2019.work Ikhras Pur, Jalala, Sujowal, Pehgwari, Malik Pur, Schemes in progress. Funds not received on spending end yet Fateh Pur Afghana, Sahari, Ghona, Ghumtala, Kanjror, Lang

"A.A. dated 03.05.2014 T.S. dated 23.05.2014 On-going 278 1881 Sewerage scheme for Ghaziwal, Narowal. Narowal 34.648 33.308 0.378 0.284 0.188 66% 97% *Start Date 18.09.2014 *Completion date Schemes 30.06.2019 work in progress. Fund not received on spending end yet Urban / Sewerage / PCC & Tuff Tile Scheme On-going A.A Date.23.9.2016.T.S Date*28.10.2016 Date of 279 1882 Narowal 174.705 84.160 6.667 5.000 3.321 66% 50% start 17.2.2017Date of completion 30.06.2019. Narowal City Schemes Work in progress. On-going "A.A. dated 03.05.2014 T.S. dated 23.05.2014 Start 280 1883 Sewerage scheme for Oncha Sadawala, Narowal. Narowal 49.284 47.265 0.611 0.458 0.305 67% 97% Date 18.09.2014 Completion date 30.06.2019 work Schemes in progress. Fund not received on spending end yet

On-going Physically scheme is completed, balance funds are 281 1884 PCC and Drainage Scheme in UC 197 at Dhalloki Lahore 100.082 91.500 2.861 2.146 1.431 67% 93% Schemes required to clear the contractor's liability. PCC and Drainage Scheme in UC 243 at attari On-going 282 1885 Lahore 130.989 90.510 6.667 5.000 3.334 67% 72% Work stopped due to awaiting funds. Saroba Pind Schemes PCC and Drainage Scheme in UC 246 at On-going Scheme Completed. Funds required to clear the 283 1886 Lahore 100.838 100.494 0.344 0.258 0.172 67% 100% Youhanabad Schemes contractor's liabilities against Price Variation. PCC and Drainage Scheme in UC 247 at Kahna On-going 284 1887 Lahore 201.357 130.000 6.667 7.500 5.834 78% 67% Work stopped due to awaiting funds. Kohna Schemes PCC and Drainage Scheme in UC 248 at On-going 285 1888 Lahore 151.603 128.300 7.201 5.401 3.601 67% 87% Work stopped due to awaiting funds. Shehzada and Pura Kahna Schemes PCC and Drainage Scheme in UC 249 at On-going Physically scheme is completed, balance funds are 286 1889 Lahore 80.384 70.070 3.438 2.579 1.719 67% 89% Kamahan Schemes required to clear the contractor's liability. On-going Physically scheme is completed, balance funds are 287 1890 PCC and Drainage Scheme in UC 252 at Pandoki Lahore 113.315 106.999 2.105 0.759 0.233 31% 95% Schemes required to clear the contractor's liability. On-going 288 1891 PCC and Drainage Scheme in UC 253 at Suraich Lahore 120.660 96.245 8.138 6.004 3.969 66% 83% Work stopped due to awaiting funds. Schemes PCC and Drainage Scheme in UC 254 Deo Khurd On-going 289 1892 Lahore 102.533 83.173 4.187 3.040 1.994 66% 83% Work stopped due to awaiting funds. and Kalan Schemes PCC and Drainage Scheme in UC 268 at Judho On-going 290 1893 Lahore 102.003 89.361 4.001 2.501 1.501 60% 89% Work stopped due to awaiting funds. Dheer Schemes PCC and Drainage Scheme in UC 271 at Jia On-going 291 1894 Lahore 103.300 100.032 1.086 4.815 4.543 94% 101% Scheme completed Bhagga and RO Plant at Jia Bhagga Schemes On-going Physically scheme is completed, balance funds are 292 1895 PCC and Drainage Scheme in UC191 at Gawind Lahore 100.000 92.500 2.500 1.875 1.250 67% 94% Schemes required to clear the contractor's liability. Construction of PCC Sewerage & Drainage On-going 293 1896 System at UC 262 Shamke Bhattian, District Lahore 30.000 18.497 3.833 2.875 1.917 67% 68% Work stopped due to awaiting funds. Schemes Lahore Construction of PCC Sewerage & Drainage On-going 294 1897 Lahore 30.000 14.521 5.160 2.370 1.080 46% 52% Work stopped due to awaiting funds. System at UC 267 Manak, District Lahore Schemes Disposal of Waste Water of Manga Mandi upto On-going Physically scheme is completed and put 295 1898 Lahore 161.107 125.649 6.667 8.463 6.797 80% 82% operational, balance funds are for O&M for 1st River Ravi Schemes Year.. PCC and Drainage Scheme in Khananapal Kangra On-going Physically scheme is completed, balance funds are 296 1899 Lahore 83.175 72.510 3.555 2.666 1.778 67% 89% Karyal Dhoondy Schemes required to clear the contractor's liability. PCC and Drainage Scheme in Nanghar Katcha On-going 297 1900 Lahore 93.775 81.140 4.212 1.309 0.256 20% 87% Scheme completed Tibba Katcha Islampura Halloki Sadhuke Schemes

PCC and Drainage Scheme in UC 145 Gajjumatta On-going Physically scheme is completed, balance funds are 298 1901 Lahore 200.014 185.659 4.785 3.589 2.393 67% 94% and Adjoining Abadies. Schemes required to clear the contractor's liability. PCC and Drainage Scheme in UC 176 at Awan On-going 299 1902 Lahore 70.128 43.914 8.737 6.553 4.369 67% 69% Work stopped due to awaiting funds. Dhaiwa Schemes On-going 300 1903 PCC and Drainage Scheme in UC 179 at Bhaseen Lahore 90.000 68.013 7.329 5.497 3.665 67% 80% Work stopped due to awaiting funds. Schemes On-going 301 1904 PCC and Drainage Scheme in UC 180 at Minhala Lahore 155.697 49.805 5.000 8.750 7.500 86% 37% Work stopped due to awaiting funds. Schemes On-going Physically scheme is completed, balance funds are 302 1905 PCC and Drainage Scheme in UC 181 at Narwar Lahore 45.000 43.000 0.667 0.500 0.334 67% 96% Schemes required to clear the contractor's liability. PCC and Drainage Scheme in UC 182 at Jallo On-going 303 1906 Lahore 56.817 31.060 8.585 2.339 0.193 8% 55% Work stopped due to awaiting funds. More & Batapur Lahore Schemes On-going 304 1907 PCC and Drainage Scheme in UC 190 at Hadiara Lahore 162.606 50.000 5.000 4.070 2.820 69% 32% Work stopped due to awaiting funds. Schemes On-going 305 1908 PCC and Drainage Scheme in UC 194 at Liddhar Lahore 101.739 63.707 6.667 5.000 3.334 67% 66% Work stopped due to awaiting funds. Schemes On-going 306 1909 PCC and Drainage Scheme in UC 195 at Hair Lahore 120.468 104.533 5.312 11.084 9.756 88% 95% Scheme completed Schemes On-going Scheme Completed. Funds required to clear the 307 1910 PCC and Drainage Scheme in UC 196 at Jaman Lahore 115.347 101.472 1.500 1.125 0.750 67% 89% Schemes contractor's liabilities against Price Variation. Provision of Sanitation Facilities including On-going 308 1911 Construction of Lift Station at Tahayat & Chandrai Lahore 94.210 81.441 4.254 3.191 2.127 67% 89% Work stopped due to awaiting funds. Schemes Village, Lahore Construction of PCC and Drainage at Adda On-going Physically scheme is completed, balance funds are 309 1912 Lahore 30.140 28.294 0.608 0.356 0.204 57% 95% Talaab Saral Schemes required to clear the contractor's liability. On-going 310 1913 Construction of PCC and Drainage at Chung Lahore 128.380 73.594 3.333 2.400 1.567 65% 59% Work stopped due to awaiting funds. Schemes On-going 311 1914 Construction of PCC and Drainage at Khurd Pur Lahore 74.249 28.893 3.333 2.500 1.667 67% 41% Work stopped due to awaiting funds. Schemes Construction of PCC and Drainage at Manga On-going 312 1915 Lahore 199.606 42.995 5.000 2.050 0.800 39% 22% Work stopped due to awaiting funds. Mandi Schemes On-going 313 1916 Construction of PCC and Drainage at Mohlanwal Lahore 52.966 52.184 0.261 0.996 0.931 93% 100% scheme completed Schemes Construction of PCC and Nallah from Hadyara On-going 314 1917 Lahore 29.345 18.612 3.577 2.683 1.789 67% 70% Work stopped due to awaiting funds. Drain to Dulam Village Schemes Construction of PCC Sewerage & Drainage On-going 315 1918 Lahore 30.000 12.371 5.876 3.107 1.638 53% 47% Work stopped due to awaiting funds. System at UC 260 Maraka, District Lahore Schemes Up Gradation of Streets PCC Flooring in Asif Town On-going 316 1919 Lahore 150.678 108.993 6.667 4.800 3.134 65% 74% Work stopped due to awaiting funds. I & II Galaxo Town and Adjoining abadies Schemes Rural Drainage Scheme Kamahan & Adjoining On-going 317 1920 Lahore 143.277 126.501 5.137 2.353 1.069 45% 89% Work stopped due to awaiting funds. Abadies Schemes Balance work of Sewerage, water Supply and On-going 318 1921 PCC Scheme Town Committtee Kot Abdul Malik, Sheikhupura 195.462 167.947 3.333 2.500 1.667 67% 87% Work in Progress Schemes District Sheikhupura Const and Rehabilitation of PCC Sewerage On-going 319 1922 Scheme of Ravi Rayan Mannu Abad and Nazar Sheikhupura 95.313 41.645 3.333 2.500 1.667 67% 45% Work in Progress Schemes Abad (Revised) Construction of Drainage & PCC Scheme at On-going 320 1923 Sheikhupura 25.000 20.000 1.667 1.250 0.834 67% 83% Work in Progress Mariam Abad District Sheikhupura Schemes Construction of Drainage & PCC Scheme at Mian On-going 321 1924 Sheikhupura 30.000 20.000 3.333 2.500 1.667 67% 72% Work in Progress Ali Dogran District Sheikhupura Schemes Construction of Drainage /PCC/Soling Scheme at On-going 322 1925 Sheikhupura 125.450 49.569 3.333 2.500 1.667 67% 41% Work in Progress Khanqah Dogran Safdarabad Schemes Construction of PCC, Drains, Soling in District On-going 323 1926 Sheikhupura 100.000 30.000 3.333 2.500 1.667 67% 32% Work in Progress Sheikhupura Schemes On-going 324 1927 Provision of PCC and draniage at Manawala Sheikhupura 30.000 20.000 3.333 2.500 1.667 67% 72% Work in Progress Schemes Construction of PCC, Drain/Soling & Nullah at UC On-going 325 1928 Sheikhupura 46.000 14.046 3.333 2.500 1.667 67% 34% Work in Progress 75, Kakar Gill, District Sheikhupura Schemes Construction of PCC, Drain/Soling & Nullah at UC On-going 326 1929 Sheikhupura 76.000 20.000 3.333 2.500 1.667 67% 29% Work in Progress 77, Ajnianwala, District Sheikhupura Schemes Construction of PCC, Drain/Soling & Nullah at UC On-going 327 1930 Sheikhupura 57.000 18.000 3.333 2.500 1.667 67% 35% Work in Progress 83, Jatri Kohna, District Sheikhupura Schemes Construction of PCC, Drain/Soling & Nullah at UC On-going 328 1931 Sheikhupura 58.000 27.000 3.333 2.500 1.667 67% 49% Work in Progress 84, Makki 460, District Sheikhupura Schemes Construction of PCC, Drain/Soling & Nullah at UC On-going 329 1932 Sheikhupura 40.000 15.000 3.333 2.500 1.667 67% 42% Work in Progress 85, Farooqabad, District Sheikhupura Schemes Construction of PCC, Drain/Soling & Nullah at UC- On-going 330 1933 Sheikhupura 15.000 11.509 1.000 0.750 0.582 78% 81% Work in Progress 97, Ferozwatuan-I, District Sheikhupura Schemes

Construction of PCC, Drain/Soling & Nullah at UC- On-going 331 1934 Sheikhupura 15.000 8.138 1.000 1.144 1.144 100% 62% Work in Progress 98, Ferozwatuan-II, District Sheikhupura Schemes

Construction of Soling / Sewerage & Drainage Scheme at UC Anjianwala, UC Jhabran, UC Kakar Gill, UC Gujiana Nau, UC Kot Sohnda, UC On-going 332 1935 Esserkay, UC Bahalikay, UC Jatri Kohna, UC Sheikhupura 100.000 20.000 3.333 4.167 3.334 80% 23% Work in Progress Schemes 85Farooqabad, UC Ghazi Minara, UC Buttar, UC Jhandian Wali, UC Warn, UC Kalokay

Const. and Rehabilitation of PCC / Sewerage On-going 333 1936 Scheme of City Muridke, District Sheikhupura Sheikhupura 96.536 61.500 5.000 3.750 2.500 67% 66% Work in Progress Schemes (Revised) Construction of PCC Tuff Tiles Sewerage On-going 334 1937 Sheikhupura 373.950 131.468 3.333 2.500 1.667 67% 36% Work in Progress Drainage Scheme in PP 163 District Sheikhupura Schemes On-going 335 1938 Rural Drainage & PCC Scheme U.C. Keelay Sheikhupura 48.000 20.000 1.667 1.250 0.834 67% 43% Work in Progress Schemes On-going 336 1939 Rural Drainage & PCC Scheme U.C. Kot Sonda Sheikhupura 45.000 24.000 3.333 2.500 1.667 67% 57% Work in Progress Schemes On-going 337 1940 Rural Drainage & PCC Scheme U.C. Muridke Sheikhupura 45.000 24.000 3.333 2.500 1.667 67% 57% Work in Progress Schemes On-going 338 1941 Rural Drainage & PCC Scheme U.C. Nookhar Sheikhupura 45.000 24.000 1.667 1.250 0.834 67% 55% Work in Progress Schemes On-going 339 1942 Rural Drainage & PCC Scheme U.C. Sacha Souda Sheikhupura 78.000 24.000 3.333 2.500 1.667 67% 33% Work in Progress Schemes On-going 340 1943 Rural Drainage & PCC Scheme UC Bhaianwala Sheikhupura 25.000 10.425 4.858 3.644 2.429 67% 51% Work in Progress Schemes On-going 341 1944 Rural Drainage & PCC Scheme UC Ghang Sheikhupura 20.000 16.000 1.333 1.000 0.667 67% 83% Work in Progress Schemes On-going 342 1945 Rural Drainage & PCC Scheme UC Mojoki Sheikhupura 28.000 23.000 1.667 1.250 0.834 67% 85% Work in Progress Schemes On-going 343 1946 Rural Drainage & PCC Scheme UC Warn Sheikhupura 25.000 10.510 4.830 3.623 2.415 67% 52% Work in Progress Schemes Rural Drainage & PCC scheme Union Council Burj On-going 344 1947 Sheikhupura 99.509 30.000 3.333 2.500 1.667 67% 32% Work in Progress attari, District Sheikhupura Schemes Rural Drainage & PCC scheme Union Council Kot On-going 345 1948 Sheikhupura 91.385 30.000 3.333 2.500 1.667 67% 35% Work in Progress Mehmood, District Sheikhupura Schemes Rural Drainage Construction of Street Scheme On-going 346 1949 Chak No 44,45 and Village Jair District Sheikhupura 199.486 74.950 3.333 2.500 1.667 67% 38% Work in Progress Schemes Sheikhupura Rural Drainage Construction Of Street Scheme On-going 347 1950 Dograi Gill Qadeem Dograi Gill District Sheikhupura 195.462 125.646 3.333 2.500 1.667 67% 65% Work in Progress Schemes Sheikhupura Rural Drainage Scheme UC Chapa Minera On-going 348 1951 Sheikhupura 87.910 54.975 3.333 2.500 1.667 67% 64% Work in Progress Sheikhupura Schemes Rural Drainage Scheme UC Chichoki Malian On-going 349 1952 Sheikhupura 85.423 48.694 3.333 2.500 1.667 67% 59% Work in Progress Sheikhupura Schemes On-going 350 1953 Rural Drainage Scheme UC Jahamke Sheikhupura Sheikhupura 94.134 54.999 3.333 2.500 1.667 67% 60% Work in Progress Schemes Rural Drainage Scheme UC Mallian Kalan On-going 351 1954 Sheikhupura 92.869 50.900 3.333 2.500 1.667 67% 57% Work in Progress Sheikhupura Schemes Rural Drainage Scheme Abdullah Pur Kolar Chak On-going 352 1955 Sheikhupura 50.000 10.000 3.333 2.500 1.667 67% 23% Work in Progress No 1/RB Tehsil Safdarabad District Sheikhupura Schemes Rural Sewerage Drainage System at Village Kot On-going 353 1956 Pindi Das Tehsil Ferozewala, Distt. Sheikhupura Sheikhupura 199.993 185.231 4.921 3.691 2.461 67% 94% Work in Progress Schemes (Revised) Rural Drainage PCC Scheme UC Dhamkey On-going 354 1957 Sheikhupura 199.308 88.690 3.333 2.500 1.667 67% 45% Work in Progress Sheikhupura Ferozwala Schemes Rural Drainage PCC Scheme UC Mahmood Kot, On-going 355 1958 Sheikhupura 180.146 78.279 3.333 2.500 1.667 67% 44% Work in Progress Sheikhupura , Sharqpur (Revised) Schemes Rural Drainage PCC Scheme UC Mandain Wala On-going 356 1959 Sheikhupura 191.008 10.687 3.333 2.500 1.667 67% 6% Work in Progress Sheikhupura , Sharqpur (Revised) Schemes Rural Drainage PCC Scheme UC Mhar On-going 357 1960 Sheikhupura 95.862 83.000 4.287 3.215 2.144 67% 89% Work in Progress Bhanguwan District Sheikhupura Schemes Rural Drainage PCC Scheme UC Quershian On-going 358 1961 Sheikhupura 87.395 66.200 3.333 2.500 1.667 67% 78% Work in Progress Sheikhupura , Sharqpur (Revised) Schemes Rural Drainage PCC Scheme, UC Sehjowal On-going 359 1962 Sheikhupura 93.090 74.136 3.333 2.500 1.667 67% 81% Work in Progress District Sheikhupura (Revised) Schemes Rural Drainage PCC Scheme, Wandala Dial Shah On-going 360 1963 Sheikhupura 144.546 142.456 0.697 0.523 0.349 67% 99% Work in Progress UC 24 District Sheikhupura (Revised) Schemes Rural Drainage PCC Tuff Tile Scheme UC On-going 361 1964 Sheikhupura 97.335 72.267 3.333 2.500 1.667 67% 76% Work in Progress Sharqpur, Sheikhupura Schemes Rural drainage scheme at UC Bhadro District On-going 362 1965 Sheikhupura 15.110 13.100 0.670 0.503 0.335 67% 89% Scheme Completed Sheikhupura Schemes On-going 363 1966 RSD Scheme Faizpur Khurd District Sheikhupura Sheikhupura 40.000 16.500 3.333 2.500 1.667 67% 45% Work in Progress Schemes Rural drainage & Const of streets scheme UC On-going 364 1967 Sheikhupura 134.768 81.863 3.333 2.500 1.667 67% 62% Work in Progress Khan pur Sheikhupura Schemes Rural drainage & Const of streets scheme UC On-going 365 1968 Sheikhupura 196.571 57.986 3.333 2.500 1.667 67% 30% Work in Progress Mandialy Sheikhupura (Revised) Schemes Rural drainage & Const of streets scheme UC Qila On-going 366 1969 Sheikhupura 182.244 72.431 3.333 2.500 1.667 67% 41% Work in Progress Sattar Shah Sheikhupura (Revised) Schemes Rural drainage & Const of streets scheme Zia On-going 367 1970 Sheikhupura 177.038 45.905 3.333 2.500 1.667 67% 27% Work in Progress abad Sheikhupura (Revised) Schemes On-going 368 1971 Rural Drainage & PCC Scheme U.C. Ajnianwala Sheikhupura 75.000 25.595 5.000 3.750 2.500 67% 37% Work in Progress Schemes On-going 369 1972 Rural Drainage & PCC Scheme U.C. Buttar Sheikhupura 57.000 39.000 1.667 1.250 0.834 67% 70% Work in Progress Schemes On-going 370 1973 Rural Drainage & PCC Scheme U.C. Easerkey Sheikhupura 38.000 25.000 2.667 2.000 1.334 67% 69% Work in Progress Schemes Rural Drainage & PCC Scheme U.C. Gujiana Nu On-going 371 1974 Sheikhupura 55.000 11.629 3.333 2.500 1.667 67% 24% Work in Progress District Sheikhupura Schemes On-going 372 1975 Rural Drainage & PCC Scheme U.C. Harchand Sheikhupura 35.000 11.629 2.333 1.750 1.167 67% 37% Work in Progress Schemes Rural Drainage Scheme Chak No 8/RB On-going 373 1976 Sheikhupura 75.000 17.987 3.333 2.500 1.667 67% 26% Work in Progress Sheikhupura Schemes Rural Drainage Scheme Faizpur Khurd IIc abadis, On-going 374 1977 Sheikhupura 152.400 74.217 3.333 2.500 1.667 67% 50% Work in Progress Tehsil Ferozewala Schemes Rural Drainage/PCC Scheme at Moran Wala On-going 375 1978 Sheikhupura 90.000 80.000 0.667 0.500 0.334 67% 89% Work in Progress District Sheikhupura Schemes Rural PCC & Drainage Scheme, UC Bhaiwala On-going 376 1979 Sheikhupura 29.000 22.000 2.333 1.750 1.167 67% 80% Work in Progress Kalan, District Sheikhupura. Schemes Beautification of Sharqpur Sharif, Provision of On-going 377 1980 PCC, Tufftiles, Fountains, Monuments, LED Street Sheikhupura 30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress Schemes lights and construction of roof of Main Bazar Rural Drainage & PCC Scheme UC Mirza Virkan On-going 378 1981 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress District Sheikhupura. Schemes Rural Drainage & PCC Scheme UC Chichoki On-going 379 1982 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Mallian District Sheikhupura. Schemes Rural Drainage & PCC Scheme Village Madar On-going 380 1983 Sheikhupura 10.000 5.000 1.667 1.250 0.834 67% 58% Work in Progress District Sheikhupura. Schemes Rural Drainage & PCC Scheme UC Mohallah On-going 381 1984 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Rehman Pura District Sheikhupura. Schemes Rural Drainage & PCC Scheme UC kot Ranjeet On-going 382 1985 Sheikhupura 10.000 7.500 0.833 0.625 0.417 67% 79% Work in Progress District Sheikhupura. Schemes Rural Drainage & PCC Scheme UC Kurlkey On-going 383 1986 Sheikhupura 10.000 5.000 1.667 1.250 0.834 67% 58% Work in Progress District Sheikhupura. Schemes Rural Drainage & PCC Scheme UC Mallian Kalan On-going 384 1987 Sheikhupura 15.000 7.500 2.500 1.875 1.250 67% 58% Work in Progress District Sheikhupura. Schemes Rural Water Supply & Drainage Scheme Murady On-going 385 1988 Sheikhupura 95.246 20.000 1.121 0.841 0.561 67% 22% Work in Progress Kalan, Shiekpura Schemes Construction of Sewerage and PCC at Bucheki On-going 386 1989 Nankana Sahib 195.998 164.782 3.333 2.500 1.667 67% 85% Work is in progress. Town. Schemes Provision of Sewerage System at Warburton Town On-going 387 1990 Nankana Sahib 130.000 61.000 3.333 2.500 1.667 67% 48% Work is in progress. Nankana Sahib. Schemes Provision of Rural Drainage / PCC Scheme for 16 On-going 388 1991 Nankana Sahib 50.000 32.599 3.333 1.500 0.667 44% 67% Work is in progress. Nos. of Union Councils in , District Sheikhupura Schemes PCC and drainage scheme Thieng More /Illah On-going 389 1992 Kasur 256.672 89.991 6.667 5.000 3.334 67% 36% Work in Progress abad, Tehsil Chunian, District Kasur Schemes Construction of Sullage Carrier at Chah On-going 390 1993 Kasur 88.300 36.983 6.667 5.000 3.334 67% 46% Work in Progress Kalalanwala, Tehsil Pattoki, District Kasur Schemes Const. of Soling Nullah, PCC etc. Union Council On-going 391 1994 Kasur 30.000 27.991 0.669 0.502 0.335 67% 94% Work in Progress Chirrawan, Tehsil & District Kasur Schemes Const. of Soling, Nullah PCC etc. Badian, Rai On-going 392 1995 Kalan, Khurd, Baddar Pur and adjoining abadies, Kasur 30.000 24.991 1.669 1.252 0.835 67% 86% Work in Progress Schemes Tehsil Kasur Const. of Soling, Nullah, PCC etc. Katlohi, Wadara On-going 393 1996 Kasur 30.000 24.999 1.667 1.250 0.834 67% 86% Work in Progress and adjoining abadies, Tehsil & District Kasur Schemes

Construction of PCC and Tuff Tile Phoolnagar On-going 394 1997 Kasur 188.416 30.350 10.000 7.500 5.000 67% 19% Work in Progress Phase-II, Tehsil Pattoki, District Kasur Schemes

Rural Drainage PCC Brick pavement Schemes On-going 395 1998 Rao Khan wala and Beroon Rao Khan Wala and Kasur 77.000 34.995 8.333 6.250 4.167 67% 51% Work in Progress Schemes Adjoining Abadies Tehsil & District Kasur Rural Drainage PCC Scheme Dholan District On-going 396 1999 Kasur 114.588 99.662 4.975 3.731 2.488 67% 89% Work in Progress Kasur. Schemes Rural Drainage Scheme Sarhali Kalan & Adjoining On-going 397 2000 Kasur 94.174 66.977 9.063 6.797 4.532 67% 76% Work in Progress Abadies, Tehsil & District Kasur. Schemes Water Supply & Drainage Scheme Nathey Jagir, On-going 398 2001 Lakhankay Abadies, Kamogill, Mega Jatt, Sardar Kasur 101.853 98.860 0.998 0.749 0.499 67% 98% Work in Progress Schemes Mill & Choudharian Wala. Provision of PCC & drainage Scheme Habib ababd On-going 399 2002 Kasur 99.000 20.000 5.000 3.750 2.500 67% 23% Work in Progress District Kasur Schemes Rural Drainage Scheme Baggiana, kamogil On-going 400 2003 Kasur 90.000 20.000 3.333 2.500 1.667 67% 24% Work in Progress Jahuggian, dhinasing & Baroon Abadies Schemes Rural Drainage Scheme Nathay Khasla Sardar On-going 401 2004 Kasur 90.000 20.000 6.667 5.000 3.334 67% 26% Work in Progress Mill, Garden Adda & Chohdry Jhlar & dhana Schemes Rural Drainage Scheme Khanko more Chakoki On-going 402 2005 Kasur 95.000 19.995 6.667 5.000 3.334 67% 25% Work in Progress Chak No 04, Madarkhai Schemes Rural Drainage PCC Scheme Theh Shaikham and On-going 403 2006 Kasur 97.400 90.282 2.371 1.778 1.186 67% 94% Work in Progress Adjoining Abadies District Kasur. Schemes

Rural Drainage & PCC Scheme Bhamba Kalan & On-going 404 2007 Kasur 95.000 77.499 5.834 4.376 2.917 67% 85% Work in Progress Khurd and Adjoining Abadies District Kasur. Schemes Rural Drainage & PCC Scheme Bohar and On-going 405 2008 Kasur 81.000 62.466 6.172 4.629 3.086 67% 81% Work in Progress Adjoining Abadies District Kasur. Schemes Rural Drainage & PCC Scheme Mudke UC District On-going 406 2009 Kasur 97.014 75.826 6.667 5.000 3.334 67% 82% Work in Progress Kasur. Schemes Rural Drainage Scheme Baroon Raja Jang & On-going 407 2010 Kasur 99.998 74.698 3.333 2.500 1.667 67% 76% Work in Progress Adjoining Abadies, Tehsil & District Kasur. Schemes Rural drainage Scheme Hanjray Kalan & Allied On-going 408 2011 Abadies, Khudian, Bhaseen, Dello Multani, Kasur 67.952 49.988 5.984 2.988 1.492 50% 76% Work in Progress Schemes Wander, Jagu Wal Tehsil Pattoki District Kasur Rural drainage scheme Hardo Sahari, District On-going 409 2012 Kasur 87.235 60.798 20.000 16.500 11.500 70% 83% Work in Progress Kasur Schemes On-going 410 2013 Rural Drainage Scheme Qadiwind Kasur 99.677 61.497 5.000 3.750 2.500 67% 64% Work in Progress Schemes Rural Drainage Scheme, Lakhankey, Tehsil & On-going 411 2014 Kasur 76.899 67.976 2.974 2.231 1.487 67% 90% Work in Progress District Kasur. Schemes Rural PCC & Drainage Scheme Green Kot and On-going 412 2015 Kasur 75.000 64.963 3.343 2.507 1.672 67% 89% Work in Progress Ibrahimabad & Adjoining Abadies District Kasur. Schemes

Rural PCC & Drainage Scheme Handal and Rawal On-going 413 2016 Kasur 69.000 60.768 2.741 0.685 0.000 0% 88% Work in Progress Jhangar & adjoining abadies District Kasur. Schemes Rural PCC & Drainage Scheme Khara and On-going 414 2017 Kasur 50.000 39.406 3.530 2.648 1.765 67% 82% Work in Progress Wadana & adjoining abadies District Kasur. Schemes Rural PCC & Drainage Scheme Ramthaman and On-going 415 2018 Kasur 74.724 65.000 3.241 0.810 0.000 0% 87% Work in Progress Matta & adjoining abadies District Kasur. Schemes Rural PCC & Drainage Scheme Zafarkey and On-going 416 2019 Kasur 50.000 47.306 0.898 0.674 0.449 67% 96% Work in Progress Ghanikey & adjoining abadies District Kasur. Schemes

Date of AA 06.03.2017, Date of TS 11.03.2017, Date of Invitation of Tender ,01.05.2017, Date of Laying of Tuff Tiles / Sewerage and Sullage Carrier On-going Receipt of Tender,02.05.2017, Date of work 417 2020 Okara 47.436 24.999 3.333 2.500 1.667 67% 56% Order.10.05.2017, Date of completion As per PC- in Left Over Streets in Ward No.1 to 50 City Okara Schemes I.30.06.2018 , Anticipated date of completion, 30.06.2019, Funds Release on 20-07-2018 Projected Population 409924 Person. Date of AA 23.03.2016, Date of TS 25.03.2016, Date of Invitation of Tender 16.05.2016, Date of Receipt of Tenders 17.05.2016 , ( No Tender Received), Date of Re-Invitation of Tender Drainage schemes and soling work at UC 103 On-going 11.06.2016, Date of Receipt of Tenders,13.06.2016, 418 2021 Okara 28.107 12.598 4.836 1.227 0.000 0% 45% Date of work Order 24.06.2016, Date of completion Depalpur District Okara Schemes As per PC-I. 18.06.2017, Anticipated date of completion,30.06.2019,Re-Appropreation (-) 2.400 Projected Population 51130 Person, Work is ini progress.(TPV Awaited) The scope of work has been completed in saving due to compitative rates.

Date of AA 23.03.2016, Date of TS 25.03.2016, Date of Invitation of Tender 16.05.2016, Date of Receipt of Tenders 17.05.2016 ,( No Tender Received), Date of Re-Invitation of Tender Drainage Schemes and soling work at UC 105 On-going 11.06.2016, Date of Receipt of Tenders,13.06.2016, 419 2022 Okara 27.990 21.521 1.080 0.270 0.000 0% 77% Date of work Order 18.06.2016, Date of completion Depalpur District Okara Schemes As per PC-I. 18.06.2017, Anticipated date of completion,30.06.2019, Re-Appropreation (-) 0.540 Projected Population 51398 Person, Work is ini progress.(TPV Awaited) The scope of work has been completed in saving due to compitative rates.

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work 420 2023 Okara 19.075 18.063 0.326 0.245 0.163 67% 96% Order.02.06.2017, Date of completion As per PC- Scheme, Behlolpur, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Anticipated date of completion, 30-06- 2019 Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work 421 2024 Scheme, Arrora Mian Khan, Tehsil Depalpur, Okara 28.303 22.499 1.934 1.451 0.967 67% 83% Order.02.06.2017, Date of completion As per PC- Schemes Okara. I.31.12.2017, Anticipated date of completion, 30.06.2019, Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work Order 422 2025 Okara 15.441 11.056 1.460 1.095 0.730 67% 76% 02.06.2017, Date of completion As per PC- Scheme, Bhai Rao Key, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Anticipated date of completion, 31.12.2019, Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender,25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders, 26.05.2017, Date of work 423 2026 Okara 25.728 19.496 2.076 1.557 1.038 67% 80% Order.02.06.2017, Date of completion As per PC- Scheme, Bhukan, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Anticipated date of completion, 30.06.2019, Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work 424 2027 Okara 25.728 22.607 1.039 0.779 0.520 67% 90% Order.02.06.2017, Date of completion As per PC- Scheme, Jhunjh Kalan, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Aniticipated date of completion, 30-06- 2019 Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work Order 425 2028 Scheme, Kot Shah Mushtaq, Tehsil Depalpur, Okara 22.049 21.029 0.340 0.255 0.170 67% 96% 02.06.2017, Date of completion As per PC- Schemes Okara. I.31.12.2017, Anticipated date of completion, 30-06- 2019 Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA- 08.03.2017, Date of TS-20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work 426 2029 Okara 21.017 18.798 0.398 0.299 0.199 67% 90% Order.02.06.2017, Date of completion As per PC- Scheme, Lalay Wala, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Anticipated date of completion, 31.12.2019, Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work 427 2030 Scheme, Phularwa Wazirkey, Tehsil Depalpur, Okara 23.747 18.351 1.797 1.348 0.896 66% 81% Order.02.06.2017, Date of completion As per PC- Schemes Okara. I.31.12.2017, Anticipated date of completion, 31.12.2019 Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work Order 428 2031 Okara 19.862 18.978 0.294 0.221 0.147 67% 96% 02.06.2017, Date of completion As per PC- Scheme, Shah Pur, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Anticipated date of completion, 31.12.2019, Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Rural water Supply & Sewerage Drainage On-going Receipt of Tenders 26.05.2017, Date of work Order 429 2032 Okara 16.746 14.842 0.633 0.475 0.317 67% 91% 02.06.2017, Date of completion As per PC- Scheme, Shinwal, Tehsil Depalpur, Okara. Schemes I.31.12.2017, Anticipated date of completion, 31.12.2019, Funds Release on 20-07-2018 Projected Population 24422 Person. Date of AA 03.08.2016, Date of TS 20.03.2017, Date of Invitation of Tender 11.10.2016, Date of Rural water Supply and Drainage Scheme, On-going Receipt of Tenders 13.10.2016, Date of work Order 430 2033 Okara 20.215 19.350 0.288 0.216 0.144 67% 96% 17.11.2016, Date of completion As per PC- Jaithpur Depalpur Schemes I.31.12.2017, Anticipated date of completion, 31.12.2019, Funds Release on 20-07-2018 Projected Population 10309 Person Rural Drainage Scheme Tuff Tiles PCC Date of AA 31.08.2016, Date of TS 22.11.2016, Date of Invitation of Tender 09.12.2016, Date of Sewerage and Soling, 3SP, 43SP, Khurpy 44SP On-going Receipt of Tenders 10.12.2016, Date of work 431 2034 Waltoya Matan Wala Amliya Key Suhag, Nihal Okara 97.984 95.372 0.868 0.651 0.433 67% 98% Order.05.01.2017, Date of completion As per PC- Schemes Muhar, Mahlo sheikhu, Mahant Darshan Nama I.30.06.2018 , Anticipated date of completion, 30.06.2019, Funds Release on 20-07-2018 Jindida, District Okara Projected Population 24422 Person. Date of AA 22.02.2017, Date of TS 24.02.2017, Date of receipt of tender 20.03.2017, Date of Work On-going 432 2035 Sewerage Scheme in Sahiwal City Sahiwal 27.844 22.271 0.748 0.561 0.500 89% 82% Order 03.04.2017 , Date of completion as per PC-1 Schemes 30.06.2018 , Anticipated date of completion 30.06.2019 subject to availablity of balance funds, Work in progress. Date of AA 10.01.2017, Date of TS 03.03.2017, Date of Pre-qualification 11.04.2017 , Date of receipt of tender 17.04.2017, Date of Work Order Sewerage Scheme Sahiwal City, City Bund Road, On-going 433 2036 Sahiwal 167.605 74.784 10.000 7.500 7.000 93% 49% 15.05.2017, Date of completion as per PC-1 LBDC, High Street & Girls College Road Schemes 30.06.2019 , Date of completion as per agreement 30.06.2019, Anticipated date of completion 30.06.2019 subject to availablity of balance funds, Work in progress. Date of A.A= 31.08.2016, Date of T.S= 09.09.2016, Date of Prequalification = 05.01.2017, Date of receipt of tenders = 23.01.2017, Date of work Provision of Sewerage / Drainage / Street order= 30.01.2017, Date of completion as per PC- On-going 434 2037 Pavements, etc in Chak No. 147/EB Tehsil Pakpattan 72.933 50.997 4.155 3.116 2.852 92% 74% 1= 30.06.2018, Date of completion as per Schemes agreement= 30.06.2018, No. of beneficiaries= Arifwala District Pakpattn 14050 persons, Funds released by FD = 03.08.2018,Funds online = 13.08.2018,Disposal station completed and made functional and handed over to CBO.Work in progress.

Date of A.A= 16.03.2017, Date of T.S= 20.03.2017, Date of invitation of tenders=16.05.2017, Date of receipt of tenders = 20.05.2017, Date of work Provision of Sewerage / Drainage Scheme Chak On-going order= 24.05.2017, Date of completion as per PC- 435 2038 Pakpattan 36.218 26.920 3.099 2.324 2.100 90% 80% No. 64/EB, Arifwala, District Pakpattan. Schemes 1= 30.06.2018, Date of completion as per agreement= 30.06.2018, No. of beneficiaries= 5749 persons, Funds released by FD = 03.08.2018,Funds online = 13.08.2018,Work in progress.

Date of A.A= 13.10.2016, Date of T.S= 25.10.2016, Date of invitation of tenders=18.11.2016, Date of receipt of tenders = 10.12.2016, Date of work On-going order= 02.01.2017, Date of completion as per PC- 436 2039 Rural Sewerage/Drainage Scheme 38/EB Arifwala Pakpattan 32.095 13.986 3.333 2.500 1.667 67% 49% 1= 30.06.2018, Date of completion as per Schemes agreement= 30.06.2018, No. of beneficiaries= 14825 persons, Funds released by FD = 03.08.2018 ,Funds online = 13.08.2018,Scheme made functional. Work in progress. 1. Date of AA 09.03.2015 (16.05.2016) 2. Date of T.S 15.05.2015 3. Dated of Prequalification __ 4. Date of invitation of tender 24.03.2015 5. Date of Receipt of tenders 25.03.2015 6. Date of work order Rural Drainage Nizam Wala Nawab Pur Road On-going 437 2040 Multan 19.295 14.295 1.667 0.416 0.000 0% 74% 29.05.2015 7. Date of Completion as per PC-l District Multan Schemes 08.03.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries 2768 persons. Scheme completed. Rs. 0.416 million proposed for re-appropriation. 1.Date of AA 09.03.2015 2.Date of T.S 21.04.2015 3.Dated of Prequalification 28.01.2015 4.Date of invitation of tender 27.04.2015 5.Date of Receipt of Rural Drainage Scheme Sewra Chok Adjoining On-going 438 2041 Multan 99.890 89.890 3.333 2.500 1.667 67% 92% tenders 02.05.2015 6.Date of work order 02.06.2015 Abadies Mouza Mubarak Pur Taj Pur Sandila Schemes 7.Date of Completion as per PC-l 08.03.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 46964 persons. Work is in progress

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: Sewerage Drainage Scheme Matotli Qaiserpur On-going 02.11.2016 6. Date of Award: 10.11.2016 7. Date of 439 2042 Multan 46.000 35.000 3.667 2.750 1.834 67% 80% Shujabad Schemes Completion as per PC-I: 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress

1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of Prequalification 12.03.2016 4.Date of invitation of tender 07.04.2016 5.Date of Receipt of tenders Rural Sewerage Drainage Scheme Chah Rattay On-going 09.04.2016 6.Date of work order 27.05.2016 7.Date 440 2043 Multan 28.800 22.792 1.667 1.250 0.834 67% 82% wala Mouza Jangal Barirah District Multan Schemes of Completion as per PC-l 26.11.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 8253 Persons. Work is in progress

1. Date of A.A: 27.10.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: On-going 02.11.2016 6. Date of Award: 18.11.2016 7. Date of 441 2044 Rural Sewerage Drainage Scheme Mill Sadiqabad Multan 87.080 75.000 4.027 3.020 3.012 100% 90% Schemes Completion as per PC-I: 17.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 10.No. of Benificiary= 23659 Persons. Work is in progress

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3.Dated of Prequalification - 4.Date of invitation of tender 30.01.2010 5.Date of Receipt of tenders Rural Sewerage Drainage Scheme Mouza On-going 15.03.2010 6.Date of work order 20.03.2010 7.Date 442 2045 Multan 46.400 41.400 1.667 1.250 0.834 67% 91% Jahangirabad Multan Schemes of Completion as per PC-l 08.03.2013 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 2250 persons. Work is in progress

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 09.11.2016 5. Date of Receipt of Tender: Rural Sewerage Drainage Scheme Pakkay Wala On-going 10.11.2016 6. Date of Award: 16.12.2016 7. Date of 443 2046 Multan 29.930 25.833 1.167 0.875 0.584 67% 88% Anayat Pur Mahota Tehsil and District Multan Schemes Completion as per PC-I: 15.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress

1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of Prequalification 12.03.2016 4.Date of invitation of tender 07.04.2016 5.Date of Receipt of tenders Rural Sewerage Drainage Scheme Saddiqabad On-going 09.04.2016 6.Date of work order 01.06.2016 7.Date 444 2047 Multan 22.840 20.937 0.515 0.386 0.258 67% 93% Hirawat and Yaray wala District Multan Schemes of Completion as per PC-l 31.11.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 25285 Persons. Work is in progress

1.Date of AA 25.03.2017 2.Date of T.S 01.04.2017 3.Dated of Prequalification - 4.Date of invitation of tender 20.04.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Chah Sunna Wala On-going 21.04.2017 6.Date of work order 23.05.2017 7.Date 445 2048 Multan 13.360 8.887 1.490 1.118 0.745 67% 72% Multan. Schemes of Completion as per PC-l 22.07.2017 8. Anticipated date of completion 30.04.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4648 persons. Work is in progress

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: On-going 02.11.2016 6. Date of Award: 10.11.2016 7. Date of 446 2049 Rural Sewerage Schemes Ambala Multan 50.000 44.336 1.714 1.286 0.857 67% 90% Schemes Completion as per PC-I: 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress 1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender 15.05.2017 5. Date of Receipt of tenders Rural Drainage, Sewerage, Solding and Tuff Tiles 16.05.2017 6. Date of work order 31.05.2017 7. On-going 447 2050 Scheme Gardezpur, Dhandho, Bagrain Ghangi, Multan 7.000 3.635 1.078 0.270 0.000 0% 52% Date of Completion as per PC-l 30.07.2017 8. Schemes Anticipated date of completion 30.06.2019 9. Date Amanullah Shah Wains & Marha, District Multan of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving. Rs. 0.270 million proposed for re-appropriation. 1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender 15.05.2017 5. Date of Receipt of tenders Rural Drainage, Sewerage Scheme Mithu Shrqi, 16.05.2017 6. Date of work order 31.05.2017 7. On-going 448 2051 Basti Mithu Gharbi, Basti Dad Shah Moosa Multan 7.000 3.921 1.012 0.271 0.018 7% 56% Date of Completion as per PC-l 30.07.2017 8. Schemes Anticipated date of completion 30.06.2019 9. Date Muqeempur, District Multan of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving. Rs. 0.253 million proposed for re-appropriation. 1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender 15.05.2017 5. Date of Receipt of tenders 16.05.2017 6. Date of work order 31.05.2017 7. Rural Drainage, Sewerage Scheme Basti On-going 449 2052 Multan 6.000 3.464 0.802 0.201 0.000 0% 58% Date of Completion as per PC-l 30.07.2017 8. Dodwpur, Basti Shahpur, District Multan Schemes Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving. Rs 0.201 million proposed for re-appropriation. 1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: On-going 02.11.2016 6. Date of Award: 12.11.2016 7. Date of 450 2053 Rural Sewerage Scheme Basti Laar Multan 50.000 35.000 1.000 0.750 0.500 67% 71% Schemes Completion as per PC-I: 11.05.2018 8. Anticipated Date of Completion: 30.06.2018 9.Date of released of funds 23.11.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress.

1. Date of A.A: 27-08-2016. 2. Date of T.S: 26-09- 2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt Sewerage, Tuff Tiles in Remaining Portion of Gaily On-going of Tender: 15-11-2016 6. Date of Award: 08-12- 451 2054 Lodhran 62.170 28.077 6.667 5.000 3.800 76% 51% 2016 7. Date of Completion as per PC-I: 31-12-2017 Wal City. Schemes 8. Anticipated Date of Completion: 10-03-2018 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 32835 Persons. Work is in Progress

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09- 2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt of Tender: 15-11-2016 6. Date of Award: 24-11- Tuff Tiles & Sewerage Scheme for remaining On-going 2016 7. Date of Completion as per PC-I: 30-06-2017 452 2055 Lodhran 45.795 32.717 4.359 2.269 1.112 49% 74% 8. Anticipated Date of Completion: 23-01-2018 portion of Gogran City. Schemes 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 16528 Persons. Scheme is functional & handed over to the community. Rs. 1.157 million proposed for re-appropriation

1. Date of A.A: 27.08.2016 2. Date of T.S: 25.10.2016 3. Date of Pre-Qualification: 22.10.2016 4. Date of Invitation of Tender: 29.11.2016 5. Date of Receipt of Tender: 05.12.2016 6. Date of Work Provision / Laying of Sewer Lines in Missing Areas On-going 453 2056 Khanewal 100.000 55.895 6.667 5.000 4.769 95% 61% order: 15.12.2016 7. Date of Completion as per PC- of Khanewal City including new and old Azafi Abad Schemes I: 30.06.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 379227 Persons Work is in progress.

1. Date of A.A: 25.04.2017 2. Date of T.S: 04.05.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 03.06.2017 5. Date of Provision of Drains, Soling Culverts etc to different On-going Receipt of Tender: 05.06.2017 6. Date of Work 454 2057 Khanewal 40.000 22.000 6.000 4.500 4.029 90% 65% order: 07.06.2017 7. Date of Completion as per PC- abadies of PP-212, Tehsil Kabirwala, Khanewal Schemes I: 30.06.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 10. Reason of Slow Moving: ------11 No. of beneficiaries 7819 Persons Work in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Drainage Scheme Chak No.88/10-R District On-going 455 2058 Khanewal 10.000 3.000 2.333 1.750 1.319 75% 43% order: 09.11.2017 7. Date of Completion as per PC- Khanewal Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5120 Persons Work is in progress. 1. Date of A.A: 21.02.2017 2. Date of T.S: 25.02.2017 3. Date of Pre-Qualification: 4. Date of Invitation of Tender: 20.05.2017 5. Date of Receipt Provision of Tuff Pavement in Gaggo Mandi / On-going of Tender: 22.05.2017 6. Date of Work order: 7. 456 2059 Vehari 49.970 28.688 3.333 2.500 1.870 75% 61% Date of Completion as per PC-I: 21.05.2019 8. Dharian / Chak No. 187/EB Schemes Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of beneficiaries 13005 Persons Work is in progress.

1. Date of A.A: 27-08-2016 2. Date of T.S: 02.09.2016 3. Date of Pre-Qualification: ____ 4. Date Invitation of Tender: 06.12.2016 5. Date of Rehabilitation of Sewerage & Drainage Scheme On-going Receipt of Tender: 07.12.2016 6. Date of Award: 457 2060 Vehari 22.396 19.450 0.982 0.737 0.670 91% 90% 22.12.2016 7. Date of Completion as per PC-I: Machiwal, Tehsil and District Vehari. Schemes 21.12.2017 8. Anticipated Date of Completion: 30.06.2018 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11 No. of beneficiaries 11435 Persons Work is in progress.

1. Date of A.A: 21.01.2013 2. Date of T.S: 22..01.2013 3. Date of Pre-Qualification: 4. Date Invitation of Tender: 14.02.2013 5. Date of Receipt Execution of Forty (40) Misc. Development On-going of Tender: 16.02.2013 6. Date of Award: 26.02.2013 458 2061 Vehari 27.500 21.681 1.000 0.750 0.570 76% 81% 7. Date of Completion as per PC-I: 26.05.2013 8. Schemes in NA-167, District Vehari Schemes Anticipated Date of Completion: 30.06.2013 9.Date of released of funds 23.11.2018 24.01.2019 10. Reason of Slow Moving: - 11. No. of Beneficiary= Persons Work is in progress. On-going 459 2062 Provision of Sewerage & Tuff Tiles for Dajal City Rajanpur 120.100 34.990 28.367 21.275 14.184 67% 41% "• Date of A.A = 05.11.2016 Schemes Construction of Drain, Brick Pavement Sullage On-going 460 2063 Carrier Culverts, Tuff Tile Muhammad Pur Dewan Rajanpur 29.990 25.694 1.000 0.750 0.000 0% 86% "• Date of A.A = 17.12.2014 Schemes Rajanpur Construction of Drain, Brick Pavement Sullage On-going 461 2064 Rajanpur 50.000 25.952 1.000 0.750 0.500 67% 53% "• Date of A.A = 17.12.2014 Carrier Culverts, Tuff Tile Fazilpur Rajanpur Schemes

Comprehensive Sewerage / Drainage / Soling / On-going 462 2065 PCC / Tuff Tile scheme at Sanawan Town, District Muzaffargarh 25.000 22.152 0.949 0.712 0.425 60% 90% "• Date of A.A 22-09-2016 Schemes Muzaffargarh (Remaining Portion) Construction of Drain Brick Pavement, RCC On-going 463 2066 Culverts, VR Bridge and Sullage Carrier in UC Muzaffargarh 42.270 10.000 10.757 8.068 5.279 65% 36% Date of AA 31.7.2017 Schemes Wainse No. 76 Tehsil Jatoi Construction of Drain Brick Pavement, RCC On-going 464 2067 Culverts, VR Bridge and Sullage Carrier in UC Muzaffargarh 43.350 10.000 11.117 8.338 5.300 64% 35% Date of AA 31.7.2017 Schemes Bairband No. 84 Tehsil Jatoi Construction of Drain Brick Pavement, RCC On-going 465 2068 Culverts, VR Bridge and Sullage Carrier in UC Muzaffargarh 43.730 10.000 11.243 8.432 5.400 64% 35% Date of AA 31.7.2017 Schemes Kotla Gamoon No. 77 Tehsil Jatoi Sewerage / Drainage Scheme for Rangpur On-going 466 2069 Muzaffargarh 241.100 48.442 56.667 42.500 27.450 65% 31% "• Date of A.A 22.9.2016 Muzaffargarh Schemes Funds received on 12.11.2018 (Rs.0.500 M) On-going Balance funds of Rs.4.540 M released on 467 2070 Rural Sewerage / drainage scheme Shah Jamal Muzaffargarh 68.504 63.220 1.000 0.500 0.000 0% 92% 10.12.2018 for clearance of liabilities of the Schemes contractor as per Court Order which is under process. Rural Sewerage/Drainage Scheme Dhori Adda & On-going 468 2071 Adoining Abadies Chak No. 426AB & 438/TDA Layyah 198.000 63.732 25.010 18.758 12.505 67% 39% • Date of AA = 25.10.2014 Schemes (Revised) Rural Drainage/Sewerage & Nallian Mosan Shah, On-going 469 2072 Mongarh, Ahsin & Waddeh wali UC Wara Sehran Layyah 30.000 10.000 6.667 5.000 3.334 67% 44% • Date of AA = 29.07.2017 Schemes Tehsil Karoor Lal Essen District Layyah Sewerage scheme Chak No. 110/TDA, Tehsil On-going 470 2073 Layyah 30.000 20.395 3.202 2.402 1.600 67% 73% • Date of AA = 22-09-2016 Karor, District Layyah Schemes Sewerage scheme Chak No. 229/TDA, Tehsil On-going 471 2074 Layyah 30.000 15.000 5.000 3.750 2.500 67% 58% • Date of AA = 22-09-2016 Karor, District Layyah Schemes Sewerage scheme Chak No. 251/TDA, Tehsil On-going 472 2075 Layyah 30.000 14.952 5.016 3.762 2.505 67% 58% • Date of AA = 22-09-2016 Karor, District Layyah Schemes Construnction of soling & drain/Nallian in UC On-going 473 2076 Layyah 30.000 17.200 4.267 3.200 2.134 67% 64% • Date of AA = 29.07.2017 Baseera Tehsil Karoor District Layyah NA-181 Schemes

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. Tender received on 14-11-2016. Date of award-03- On-going 01-2017. Date of completion=02-12-2017. 474 2077 Construction of Sewerage chak no. 63,DB. Bahawalpur 18.845 14.803 1.340 1.455 1.100 76% 84% Anticipated date of completion 30-06-2019. Date of Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.0.450 million provided through re- appropriation dated 19.10.2018.Work is in progress.

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. Provision of Sewerage / Tuff Tile in Basti Jhangara .Tender received on 14-11-2016. Date of award-03- Sharqi, Mouza Jhangara Sharqia, Union Council On-going 475 2078 Bahawalpur 29.895 26.878 1.003 0.752 0.500 66% 92% 01-2017. Date of completion=02-12-2017. Bahawalpur Ghalvan, Tehsil Ahmedpur Sharqia, Schemes Anticipated date of completion 30.06.2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. District Bahawalpur. Work is in progress.

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Date of receipt of Tender 14.11.2016. Date of On-going 476 2079 Sewerage & Tuff Tile Jamalpur Bahawalpur 29.526 22.718 2.269 1.702 1.130 66% 81% award 30.11.2016. Date of completion 29.10.2017. Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A= 18-08-2015. Date of T.S= 28-08-2015. Date of receipt of tenders = 08-03-2016. Date of On-going work order= 18.04.2016. . Date of completion as per 477 2080 Sewerage / Drainage Scheme, Chak No. 110/DB Bahawalpur 29.725 27.964 0.133 0.100 0.067 67% 94% agreement=17.04.2017. Anticipated date of Schemes completion = 30.06.2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Date of receipt of tender 14-11-2016. Date of award 15-12-2016. Date of completion 14-11-2017. Sewerage Scheme Chak no. 15/Ford wah, Tehsil On-going Anticipated date of completion 30-06-2019. Date of 478 2081 Bahawalpur 15.616 8.287 1.855 0.891 0.428 48% 56% Hasilpur. Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.0.500 million surrendered vide Chief Engineer(S),PHED Lahore No.72-78/B(4) dated 10.01.2019.Work is in progress.

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. Date of Receipt of tender 14.11.2016. Date of award 15.12.2016. Date of completion 14.11.2017. On-going Anticipated date of completion 30-06-2019. Date of 479 2082 Rural Sewerage Scheme 17/F.W Bahawalpur 25.000 13.450 3.833 2.075 1.110 53% 58% Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.0.800 million surrendered vide Chief Engineer(S),PHED Lahore No.72-78/B(4) dated 10.01.2019.Work is in progress.

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Date of Receipt of tender 14.11.2016. Date of On-going 480 2083 Rural Sewerage Scheme Basti Chohan Bahawalpur 21.500 10.625 3.510 2.633 1.750 66% 58% award 15.12.2016. Date of completion 14.11.2017/. Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. . .

Date of AA. 21.10.2016. Date of T.S. 26.10.2016. Construction of Sewerage Drainage Schemes Date of Tender 12.12.2016. Funds released by FD Abadi Jodheka QasimKa Chak Sarkari Bagar Wala On-going 04-07-2017 & 06-10-2017.Date of receipt of tender 481 2084 Bahawalnagar 99.996 29.990 23.335 17.501 15.000 86% 45% 14-12-2016 . Date of award 19-01-2017. Date of Khoo Chavek, Toba Balochan Tehsil & Distt. Schemes completion 18-12-2017. Anticipated date of Bahawalnagar completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA. 15-10-2015 . Date of TS. 22-02-2016. Prequalification of the contractor=22-03-2016. Date of invitation of tenders=24-03-2016. Date of receipt Sewererage and Drainage Scheme Maroot Tehsil On-going of tenders = 07-04-2016. Date of award= 30-04- 482 2085 Bahawalnagar 120.980 52.857 22.665 16.999 16.990 100% 58% Fortabbas District Bahawalnagar Schemes 2016. Date of completion as per agreement=29-04- 2018.Expected date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of AA. 08.02.2011. Date of T.S. 08.02.2011. Comprehensive Urban / Draiange Sewerage On-going Date of award. 11.03.2011. Date of completion 483 2086 Bahawalnagar 72.683 69.236 1.000 0.500 0.500 100% 96% 30.06.2012. Anticipated date of completion 30-06- Scheme Doonga Boonga Schemes 2019. Funds released by FD on 12-11-2018 & 11.01.2019 .Work is in progress. Date of AA(DDWP)=28-10-2016..Date of T.S. 13.02.2017..Tenders received on 13-03-2017 .. Provision of water Supply /Sewerage scheme for Rahim Yar On-going Date of work awarded .25-04-2017. .Date of 484 2087 121.000 32.590 29.466 22.100 14.700 67% 39% completion 30-06-2019. .Date of receipt of funds by MC Tranda Saway Khan, Tehsil & District RYK Khan Schemes F.D. 20.07.2018 & 11.01.2019..Funds of 3rd Quarter is not credited/onlined to the District Accounsts office RYK..Work is in progress. Date of A.A= 26-02-2016.Date of T.S= 05-05- 2016.Date of prequalification. 03-08-2016..Date of Construction of Sewerage Open Drain in Rahim Yar On-going tender received on 10-10-2016.Date of award= 16- 485 2088 97.240 52.148 14.698 11.024 8.847 80% 63% 11-2016.Date of completion= 15-04-2018.Expected Chachran Sharif Khan Schemes date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA =17-09-2016.Date of TS=23-11- 2016.Prequalification of contractors 05-01-2017. Urban water Supply / Sewerage Scheme for City Rahim Yar On-going Date op receipt of Tenders 06-02-2017..Date of 486 2089 121.750 49.980 23.917 17.938 13.989 78% 53% work awarded 17.03.2017..Date of completion Tranda Muhammad Pannah Khan Schemes 16.09.2018..Expected date of completion. 30-06- 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA. 24.10.2016..Date of T.S. 29.11.2016. Tenders received on 16-01-2017 .Date of work Sewerage & Tuff tiles in UC 36, 37, 38, 40, 41, 42 Rahim Yar On-going 487 2090 35.000 20.000 1.000 0.750 0.601 80% 59% awarded 08-02-2017. Date of completion 07-08- and 71 under Rahim Yar Khan Khan Schemes 2017. Anticipated date of completion 30-06- 2019.Funds released by FD on 11.01.2019. Work is in progress. Date of A.A= 30-12-2015..Date of RAA= 23-09- 2016.Date of T.S. 30.09.2016..Date of prequalification= 03-08-2016.Date of tender= 21-10- Sewerage Scheme R.Y.Khan City with Treatment 2016.Date of work awarded=19-12-2016.Date of Plant-Construction of Intermediate Pumping Rahim Yar On-going 488 2091 481.825 421.239 2.000 1.500 1.187 79% 88% completion=18-05-2017.Anticipated date of Station Near Niazi Colony & Installation of Force Khan Schemes completion: 30.06.2019.Funds released by FD on 11.01.2019. The scheme is completed and Main functional. Libility of Contractor is yet to be cleared. Estimate submitted to Chief Engineer(S), PHED Lahore for revised A.A from the P&D Department. 1. Date of AA = 20.10.2016 2. Date of TS = 25.10.2016 3.Date of Award of work 17.12.2016 Provision of Sewerage in Chak No 141JB On-going 489 2092 Chiniot 31.350 25.000 2.117 1.588 1.059 67% 83% 4.Dated of Released Funds 5. No. of Beneficiaries = Khokhran Tehsil & District Chiniot Schemes 1891 Persons Funds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 19.09.2017 2. Date of TS = Sewerage Scheme, PCC Slab Soling in Bhowana On-going 25.10.2017 3. Date of Work Order = 09.12.2017 490 2093 Chiniot 77.000 20.363 8.333 6.250 4.100 66% 32% 4.Dated of Released Funds 03.11.2017 Funds city Chiniot Schemes Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Bulk water Supply Project from River Jhelum to On-going 491 2094 Rawalpindi 4,254.770 1,068.566 1.000 0.750 0.000 0% 25% Work in Progress. Murree Schemes water Supply Scheme Fazaiya Housing Colony On-going Work suspended at site due to change of intake site 492 2095 Rawalpindi 373.073 338.322 11.584 8.688 5.792 67% 92% by SPD Department, now NOC granted by SPD and Turnol Tehsil & District Rawalpindi Schemes revised estiamte under process of approval. Improvement of Water Supply System in Murree On-going 493 2096 under PPP Rehabilitate, Operate and Transfer Rawalpindi 24.500 14.500 3.333 2.500 0.000 0% 59% Funds Released by FD on 31st July 2018. Schemes (ROT Mode). Installation of water Supply scheme for residents On-going A.A Date 21.10.2014.T.S Date 10.11.2014.Date of 494 2097 Attock 469.913 400.994 10.000 7.500 5.000 67% 86% Start of Scheme 22.01.2015.Date of Completion of of Fateh Jang attock Schemes Scheme 30.06.2019.Work is in progress. Rehabilitation of Urban water Supply Scheme On-going Date of A.A 17.09.2015. Date of T.S.Date of Start 495 2098 Chakwal 73.390 61.987 3.801 2.851 1.901 67% 87% 11.02.2016.Date of completion 30.06.2019.Full Kallar Kahar District Chakwal Schemes funds utilized. Scheme is short funded. Date of A.A 17.09.2015 .Date of T.S On-going 496 2099 Est. of W.S. Scheme Talagang Chakwal 94.580 82.608 3.931 2.948 1.966 67% 89% 07.10.2015.Date of Start 26.01.2016.Date of Schemes completion 30.06.2019.Full funds utilized. Scheme is short funded. "Date of A.A 03.04.2014.Date of T.S 16.04.2014.Date of Start 30.05.2014.Date of completion 30.06.2021.Phase i of the scheme has water Supply Scheme Chakwal Based on Khai On-going been completed. 2 Cusec water from Khai Dam is 497 2100 Chakwal 1,018.160 341.465 33.333 9.488 0.506 5% 34% Dam Schemes being supplied to M.C Chakwal since 01-2018. The amended A.A has been submitted in P&D for according approval. The tendering process of Phase- II will be started after getting amended approval. Date of A.A 21.11.2017. Date of T.S Installation of 02 no. of Tubewells in choa Saiden On-going 23.11.2017.Date of Start 12.01.2018. Date of 498 2101 Chakwal 18.460 17.730 0.730 0.548 0.365 67% 98% completion 30.06.2018.Work completed. However Shah, District Chakwal Schemes further funds are required to clear the liability against the above rates of awarded work. Water Suplly Scheme based on Naroomi Dhan On-going "A.A: 10-04-14.T.S: 16-4-14 .Date of 499 2102 Jhelum 298.854 286.982 3.953 2.965 1.977 67% 97% Commencement 24-10-2014.Work is in Progress. Spring Phase II Schemes Scheme is partially operational. Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Lying of water Supply Pipelines in D Block Old On-going Completion is 30.06.2018, Date of Commencement, 500 2103 Sargodha 5.386 4.139 0.416 0.312 0.312 100% 83% 22.02.2017, Funds released on 30.07.2018, Funds Satellite Town & Millat Abad Sargodha City Schemes on-lined on 30.07.2018. R/Main / D-System 9395- Rft laid. P.C.C Slab 3128-Cft laid. RCC Sewer 12" i/d 531-Rft laid. Work in progress.

Date of A.A 28.02.2014, Date of T.S 30.04.2014, Date of Award 28.06.2014, Scheduled date of Completion is 30.06.2017, Date of Commencement, 28.06.2014, Funds released on 30.07.2018, Funds Augmentation of water Supply Scheme Sargodha On-going on-lined on 30.07.2018. 21-No. tube wells 501 2104 Sargodha 268.210 197.713 16.667 12.500 9.628 77% 77% completed out of provision 22-No. 21-No. Pump based on Canal water Supply Sargodha Phase I Schemes Houses 90% completed out of provision 22-No. 31- Sets of Pumping machinery arranged. R/Main / D- System 122534-Rft laid out of provision 125047-Rft. 5-No. GSTs 90% completed out of 05-No. 05-No. Staff Quarter 85% completed. Work in progress.

Date of A.A 11.08.2015, Date of T.S 14.10.2015, Date of Award 16.01.2016, Scheduled date of Completion on 30.06.2017, Date of Commencement, 16.01.2016, Funds released on water Supply Scheme for Farooq Colony, On-going 502 2105 Sargodha 98.971 65.957 6.667 5.000 5.000 100% 72% 30.07.2018, Funds on-lined on 30.07.2018. 06-No. Imtiazabad Abad Sargodha City Schemes trial bore, tube well bore & pump house completed out of provision 06-No. 08-Sets of Pumping machinery arranged. R/Main / D-System 40803-Rft laid & 360-Rft arranged out of provision 112510-Rft. 02-No. GSTs 90% completed. Work in progress. Date of A.A 08.10.2009 Date of T.S 05.11.2009 Comprehensive Urban water Supply and On-going 503 2106 Khushab 358.444 342.647 5.261 2.946 2.940 100% 96% Date of award 06.01.2010. Date of completion Sewerage Scheme Khushab City Schemes 30.06.2019 Scheme is functional and handed over to Municipal Committee Khushab.v Date of A.A 08.10.2009 Date of T.S 05.11.2009 Date of award 11.08.2010 Date of completion 30.6.2019 All 10 No. Tubewell with pump house, Comprehensiver Urban water Supply and On-going 504 2107 Khushab 586.987 462.440 33.333 26.000 19.500 75% 82% pumping machinary and GST 800000 Gln Sewereage Scheme Jauharabad Schemes completed. Work of laying of water supply pipe line is in Progress. All 3 Nos disposal works completed and functional. Work lying lataral sewer is in progress. Replacement of Old water Supply Pipeline in On-going Date of AA 27.08.2016 Date of TS 01.11.2016 Date 505 2108 Khushab 90.000 21.943 3.333 2.500 1.870 75% 26% of award 06.02.2017 Date of Completion 30.06.2020 Jauharabad. Schemes Work is in progress. Replacement of Old water Supply Pipeline in On-going Date of AA 27.08.2016 Date of TS 01.11.2016 Date 506 2109 Khushab 130.000 44.202 16.667 12.500 9.800 78% 42% of award 06.02.2017 Date of Completion. Khushab City. Schemes 30.06.2020 Work is in progress. Revised Date of A.A. 16-01-2014 Date of Revised T.S.08-08-2014, Date of 2nd Revised A.A. 04-11- 2015, Date of 2nd Revised T.S.10-12-2015, Date of Start of Work.03-12-2009, Remarks. Tube- Well=8/8, Pump House=8/8, Pumping Machinery=9/9, Rising Feeding Main=12"i/d A.C= 921/940, 10" i/d A.C= 11959 /11960, 8" i/d Comprehensive water Supply Sewerage Scheme On-going 507 2110 Mianwali 494.444 462.274 6.667 4.300 2.634 61% 94% PVC=26535 /26541, 6"i/d PVC= 30244 /30591,4"i/d Mianwali Schemes PVC= 40592/40583, 3"i/d PVC= 137262/137106, OHR = 3/3, Chlorinator = 8/8, T/Line 5/8, RCC Sewer=42"i/d= 480/480, 36"i/d =8385/8385, 30"i/d =2159/2159, 27"i/d= 8694/8694, 24"i/d=12415 /12415, 21"i/d= 14020/14020, 18"i/d= 23255/23357, 15"i/d= 28803 /29337, 12"i/d=137955 /137918, 9"i/d=31456/31456, Sullage Carrier=8500/8500, Oxidation Pond=2/2. Work is in progress.

Date of A.A. 11-08-2015, Date of T.S. 15-08-2015, Date of Start of Work 28-10-2015, Remarks. Rising Water Supply Scheme Iskandarabad, District On-going Main=4"i/d PVC= 1960/1960, D/System=4"i/d G.I= 508 2111 Mianwali 4.498 1.509 0.996 0.273 0.024 9% 34% 0/50, 3"i/d PVC=6000/6000, 4"i/d PVC= 400/400, Mianwali. Schemes 6"i/d PVC 1900/1900, O.H.R=1/1 , Repair of P/Machinery, R/F Main old=1/1. Scheme completed in saving Fund proposed to be surrendered.

1-Date of A.A 16.10.2014 2- Date of T.S 28.11.2014 3-Date of Prequalification 08.12.2014 4-Date of invitation of tenders 07.12.2014 5- Date of Receipt of tenders 23.12.2014 6- Date of work order Comprehensive water Supply Scheme Kamalia On-going 509 2112 Toba Tek Singh 426.211 307.725 25.000 18.750 13.450 72% 75% 31.12.2014 7- Date of completion as per PC-I City Schemes 15.10.2017 8- Anticipated date of completion 30.12.2017 9- No. of Beneficiary - 298364 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019. 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 01.01.2016 2- Date of T.S 30.03.2016 3-Date of Prequalification -31.03.2016 4-Date of invitation of tenders 17.04.2016 5- Date of Receipt of tenders 25.04.2016 6- Date of work order - On-going 510 2113 Urban water Supply Scheme Gojra Phase II Toba Tek Singh 532.942 125.000 33.333 25.000 16.600 66% 27% 18.05.2016 7- Date of completion as per PC-I Schemes 11.11.2018 8- Anticipated date of completion 11.11.2018 9- No. of Beneficiary - 393651 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019. 11- Re-appropriation of funds(+/-) .Work in progress. 1-Date of A.A 23.10.2017 2- Date of T.S 17.11.2017. 3-Date of Prequalification 4-Date of Provision of Brick Pavements, Drains, Tuff Tiles, invitation of tenders 05.12.2017 5- Date of Receipt Water Supply, Play Grounds, Public Parks, etc., in On-going of tenders 07.12.2017 6- Date of work order 511 2114 Toba Tek Singh 245.000 120.000 16.667 12.500 8.200 66% 52% 12.12.2017 7- Date of completion as per PC-I 8- the Rural and Urban Areas of Tehsil Kamalia and Schemes Anticipated date of completion 30.06.2018.9- No. of Tehsil Pir Mehal District T.T. Singh Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. A.A Date =5.9.2014.T/Well installed=4 Provision of water Supply and Drainage Scheme On-going Nos.functional= 3 Nos .PVC Pipe Laid=170825 512 2115 Gujrat 197.050 138.416 10.000 7.500 5.000 67% 73% Rft.PCC= 156462 Cft. S.C=7719 Rft. Soling=6069 for Dinga City Distt Gujrat. Schemes sft, Tuff paver=19570 sft.1 No OHR 50000 Gln completed.Work in porgress. A.A Date =10.02.2009.17 Nos Tube wells are functional and Handed over to M.C Gujrat .3 Nos On-going 513 2116 Construction of water Supply System Gujrat Gujrat 742.379 487.503 33.333 10.000 1.667 17% 66% OHR's are functional. 763906 Rft pipes laid & Schemes functional.House Connection= 2155 Nos. 2 Nos contracts are rescinded while 1 No has been reinstated. A.A Date =23.9.2014.T/Well installed= 3 Nos Extension of Urban water Supply and drainage On-going 514 2117 Gujrat 122.416 79.911 5.000 3.750 2.500 67% 67% Functional= 2 Nos.PVC Pipe Laid=36194 scheme Azafi Abadies in Kharian City Schemes Rft.PCC=104022 Cft. S.C=5986 Rft.Tuff Paver= 74392 Sft Work in porgress. Extension of Urban water Supply and drainage On-going A.A Date =23.9.2014.T/Well installed= 2 Nos.PVC 515 2118 Gujrat 159.603 122.667 8.432 11.324 9.216 81% 83% Pipe Laid=77073 Rft.PCC= 328408 Cft. S.C=550 scheme Sarai Alamgir City. Schemes Rft.Work in porgress. On-going Drain Type-I=23952 Rft. PCC. 1:2:4=91393 516 2119 water Supply & Sewerage Scheme in PP 114 Gujrat 47.981 22.984 8.332 6.249 4.166 67% 57% Schemes Cft.Work in progress. On-going A.A Date =23.02.2017.3 T/Well installed.Pipe 517 2120 water Supply scheme Lalamusa and Rural Areas Gujrat 197.321 40.000 5.000 3.750 2.500 67% 22% 8"=400 Rft, 4"=2000 Rft, 3'=1000 rft. Work in Schemes porgress. Improvement / Extension of Urban water Supply Mandi On-going * A.A Date. 25.03.2016* T.S Date. 29.03.2016* Start 518 2121 345.995 114.976 16.667 14.700 10.534 72% 36% Date 24.04.2016* Completion date 23.04.2019. * Sewerage & Drainage Scheme M.B.Din City Bahauddin Schemes Work in progress.

Improvement / Extension of Urban water Supply Mandi On-going * A.A Date. 07.01.2016* T.S Date. 15.01.2016.* 519 2122 197.956 102.347 5.000 3.750 2.500 67% 53% Start Date 01.03.2016* Completion date Sewerage & Drainage Scheme Malikwal City Bahauddin Schemes 28.02.2019. * Work in progress. Mandi On-going * A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start 520 2123 water Supply Scheme Chot Dhirian, M.B.Din 75.000 64.263 3.333 1.100 0.267 24% 86% Date 17.12.2015.* Completion date 30.06.2019.* Bahauddin Schemes Work in progress Rehabilitation / Augmentation of Urban water On-going A.A Date.30.9.2014T.S Date.10.11.2014*Start Date 521 2124 Narowal 185.411 98.401 13.333 3.733 0.395 11% 53% 23.12.2014*Completion date 30.06.2019.Work in Supply Scheme Narowal City Schemes progress. Fund not received on spending end yet Urban water Supply Scheme Kahna Phase I and On-going Scheme in nearing completion, 2-Nos. Tube wells 522 2125 Lahore 199.405 126.661 6.667 4.500 2.834 63% 65% are put operational. Balance funds are required to II Schemes complete the scheme Provision of Open water Supply Scheme On-going 523 2126 Sheikhupura 175.524 125.000 3.333 2.500 1.667 67% 72% Work in Progress Ferozwala Schemes On-going 524 2127 Urban water Supply Scheme Muridkey Sheikhupura 450.000 219.000 16.667 12.500 8.334 67% 51% Work in Progress Schemes On-going 525 2128 water Supply Scheme Chunian Amended Kasur 228.855 220.454 2.672 1.534 0.866 56% 97% Work in Progress Schemes Urban water Supply and Sewerage/ Drainage On-going 526 2129 Kasur 475.472 468.331 2.380 1.185 0.590 50% 99% Work in Progress Scheme Phool Nagar Schemes water Supply, Drainage & PCC Scheme Outside On-going 527 2130 Kasur 176.173 172.172 1.334 1.001 0.667 67% 98% Work in Progress Khudian District Kasur Schemes Date of A.A (Revised) 22.01.2013, Date of T.S (Revised) 28.01.2013, Date of Prequalification 11.09.2012, Date of invitation of tenders Extension / Improvement of water Supply Scheme On-going 16.02.2013, Date of Receipt of tenders 16.02.2013, 528 2131 Okara 864.000 701.498 26.667 20.000 13.334 67% 83% Date of work order 21.02.2013, Date of completion Southern City, Okara. Schemes as per PC-I 13.05.2015, Anticipated date of completion 30.06.2019, No. of Beneficiary - 69380 Person, Funds Release on 20-07-2018 Work is in progress. 1. Date of AA 05.12.2016 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender Provision and Installation of six (06) Water 01.02.2017 5. Date of Receipt of tenders Purification Plants at Matotli Qaisarpur, Shah Mosa 03.02.2017 6. Date of work order 11.02.2017 7. On-going 529 2132 Shah Pipulwala, Basti Mahram Rukn Hatti, Chak Multan 10.722 4.461 2.087 1.007 0.486 48% 46% Date of Completion as per PC-l 10.06.2017 8. Schemes Anticipated date of completion 30.06.2019 9. Date No.13- Faiz, Chak Sardarpur & Basti Nawan of released of funds 03.08.2018. 24.01.2019 10. No. Shehar, Tehsil Shujabad, District Multan of beneficiaries=111527 persons. Scheme completed in saving. Rs 0.521 million proposed for re-appropriation. 1. Date of A.A: 17.09.2015 2. Date of T.S: 09.11.2015. 3. Date of Pre-Qualification: 18.01.2016 4. Date of Invitation of Tender: 16.02.2016 5. Date Rehabilitation of water Supply and Sewerage On-going of Receipt of Tender: 17.02-2016 6. Date of Work 530 2133 Khanewal 106.963 68.841 6.667 5.000 4.519 90% 69% order: 05.03.2016 7. Date of Completion as per PC- Schemes in Tulamba City. Schemes I: 16-09-2017 8. Anticipated Date of completion: 30- 06-2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11 No. of beneficiaries 53394Persons Work is in progress.

1. Date of A.A: 05.09.2014 2. Date of T.S: 28.10.2014 3. Date of Pre-Qualification: 18.12.2014 4. Date of Invitation of Tender: 19.01.2015 5. Date of Receipt of Tender: 20.01.2015 6. Date of Work Urban water Supply & Sewerage Scheme On-going 531 2134 Khanewal 191.232 147.091 14.714 11.036 10.971 99% 83% order: 18-02-2015 7. Date of Completion as per PC- Khanewal City Schemes I: 04-09-2016 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 358569 Persons Work is in progress. 1. Date of A.A: 11.01.2016. 2. Date of T.S: 25.02.2016 3. Date of Pre-Qualification: 11.04.2015 4. Date of Invitation of Tender: 24.03.2016 5. Date Comprehensive water Supply & Sewerage On-going of Receipt of Tender: 02.04.2016 6. Date of Work 532 2135 Vehari 99.982 78.470 6.970 5.228 3.885 74% 82% order. 14.04.2016 7. Date of Completion as per PC- Scheme for Luddan City District Vehari. Schemes I: 10.01.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary 20316 Persons Work is in progress. 1. Date of A.A: 11.04.2016. 2. Date of T.S: 29.04.2016. 3. Date of Pre-Qualification: 11.04.2015. 4. Date of Invitation of Tender: 18.05.2016. 5. Date of Receipt of Tender: Comprehensive water Supply & Sewerage On-going 28.05.2016. 6. Date of Award: 15.06.2016 G-I. 533 2136 Vehari 332.198 308.130 8.000 6.000 4.540 76% 94% 17.06.2016 G-II 7. Date of Completion as per PC-I: Scheme for Vehari city. Schemes 14.06.2018 8. Anticipated Date of completion: 30.06.2018 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11. No. of Beneficiary= 140193 Persons Work is in progress. Comprehensive water Supply Scheme Taunsa Dera Ghazi On-going 534 2137 195.973 149.673 15.433 11.575 8.218 71% 81% "• Date of A.A = 12.12.2014 Sharif Khan Schemes Rehabilitaion of Urban water Supply Scheme Fort Dera Ghazi On-going 535 2138 257.064 243.790 4.397 3.298 1.154 35% 95% "• Date of A.A =01.04.2015 Minroe Khan Schemes Comprehensive Extension/Rehab. of Urban water On-going 536 2139 Rajanpur 49.569 25.000 8.190 6.143 4.095 67% 59% "• Date of A.A = 22.09.2016 Supply Scheme Rojhan and adjoining abadies Schemes Enhancement of Supply of Water for Rojhan City On-going 537 2140 Rajanpur 30.000 20.000 3.333 2.500 1.667 67% 72% "• Date of A.A = 22.09.2016 District Rajanpur Schemes Urban water Supply On-going 538 2141 Muzaffargarh 419.689 398.484 4.110 3.083 2.054 67% 95% "• Date of A.A 10.11.2008 Scheme,Muzaffargarh(Ammended) (PSDP) Schemes Date of AA :29-11-2006. Date of TS :08-01-2007. Date of RAA: 17-04-2014. Date of RTS. 17-04- 2014. Date of receipt of tender.14-02-2007. Date of work order:17-03-2007. Date of completion as per agreement 16-03-2008.Anticipated date of Rehabilitation and Agumentation of water Supply On-going completion 30-06-2019.Date of receipt of funds by 539 2142 Bahawalpur 282.533 254.014 3.805 1.654 0.700 42% 90% Scheme, Bahawalpur Schemes F.D 20.07.2018 & 11.01.2019.Funds Rs.1.200 million surrendered vide Chief Engineer(S),PHED Lahore No.72-78/B(4) dated 10.01.2019 Three out of four portions are completed and handed over to TMA on 30-04-2014. Balance one portion at trust colony, Model Town-B is under test operation. Date of AA(DDWP)=24-10-2016. Date of TS=19-01- 2017. Prequalification of the contractors=05-01- On-going 2017. Date of receipt of tender 27-02-2017 . Date of 540 2143 Urban water Supply Scheme for Hasilpur Bahawalpur 100.000 76.466 7.844 5.883 3.900 66% 80% award=03-03-2017. Date of completion. 02-03-2018. Schemes Expected date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA. 08.08.2016. Date of T.S. 27.09.2016. water Supply Scheme of Chak Sarkari and Date of receipt of tender 02.11.2016. Date of award. On-going 541 2144 Adjoining Abadies Tehsil Minchinabad District Bahawalnagar 10.827 9.283 1.544 1.158 1.060 92% 96% 30.11.2016. Date of completion 29.07.2017. Schemes Anticipated date of completion 30-06-2019. Funds Bahawalnagar released by FD on 12-11-2018 & 11.01.2019.Work is in progress.

Date of AA 09.03.2010. Date of T.S 13.03.2010. Date of award 14.05.2010. Date of completion Water Supply Scheme Doonga Boonga, District On-going 13.05.2011. Anticipated date of completion 30-04- 542 2145 Bahawalnagar 11.168 0.915 3.418 0.891 0.820 92% 16% 2019. Scheme remained unfunded during 2011-12. Bahawalnagar. Schemes Funds released on 20-07-2018 & 11.01.2019. Scheme completed in saving. Excess funds Rs.1.673 million surrendered dated 19.10.2018. Date of AA 11.08.2009. Date of T.S 31.10.2009. Date of award 13.01.2010. Date of completion Replacement & Up-Gradation of Urban Water On-going 30.06.2014. Scheme remained unfunded during 543 2146 Bahawalnagar 214.155 211.310 0.947 0.441 0.441 100% 99% 2013.14. Date of receipt of funds by F.D. Supply Scheme Bahawalnagr Schemes 20.07.2018 & 11.01.2019. Scheme completed in saving. Excess funds Rs.0.269 million surrendered dated 19.10.2018. A.A issued on 12-05-2014. .Date of T.S. 26-05- 2014. .Date of prequalification=21-07-2014.Date of receipt of tenders = 22-12-2014. .Date of work water Supply Scheme Sadiqabad, Tehsil Rahim Yar On-going order= 03-01-2015..Date of completion as per 544 2147 692.527 454.150 67.779 50.834 40.405 79% 71% Sadiqabad, District R.Y. Khan. Khan Schemes agreement 30.06.17.Anticipated date of completion 30.06.2019.No. of beneficiaries=405864 persons.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017. Urban Water Supply Scheme Bismillah Town, .Date of receipt of Tender: 07.09.2017..Date of Rahim Yar On-going 545 2148 Thalli Road, Near Madrassa Kulyat ul Islam City 30.000 9.949 6.667 5.000 3.760 75% 46% award: 31.10.2017..Date of completion: Khan Schemes 31.1.2018..Anticipated date of completion 30-06- Rahim Yaar Khan 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA 18.08.2015..Date of T.S 14.09.2015. .Date of award 07.01.2016..Date of completion Const. of Water Supply Scheme Tranda Sway, Rahim Yar On-going 546 2149 2.610 0.603 0.669 0.252 0.252 100% 33% 30.06.2016..Scheme remained unfunded during R.Y.Khan. Khan Schemes 2016-17..2018. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Scheme completed & put in to operation. Urban Sewerage / Drainage & PCC for Fateh Jang On-going A.A Date 09.01.2016.T.S Date 22.01.2016.Date of 547 2150 Attock 99.948 80.231 5.341 5.006 3.671 73% 84% Start of Scheme 09.03.2016.Date of Completion of City, Tehsil Fateh Jhang, District attock. Schemes Scheme 30.06.2019.Work is in progress.

Urban Sewerage / drainage scheme for Hassan On-going A.A Date 28.08.2014.T.S Date 01.09.2014.Date of 548 2151 Attock 195.317 167.071 8.336 7.232 5.148 71% 88% Start of Scheme 26.01.2015.Date of Completion of Abdal City, Hassan Abdal, District attock Schemes Scheme 30.06.2019.ork is in progress.

Providing / laying of Sewerage, Construction / Date of A.A 29.03.2016 (2nd Rev). Date of T.S Rehabilitation of storm water channel in Choa On-going 549 2152 Chakwal 239.300 225.507 2.429 1.822 1.215 67% 95% 07.04.2016 (Rev).Date of Start 21.02.2014.Date of Saiden Shah District Chakwal (Phase-I) (3rd Schemes completion 30.06.2019.Date of scheme almost completed only contractor liabilities are to be clear. Revised) On-going Date of A.A 22.01.2015 (3rd Rev).Date of T.S 550 2153 Urban Sewerage Scheme, Talagang City. Chakwal 99.667 80.853 5.067 2.800 1.530 55% 83% 06.02.2015.Date of Start 13.04.2015.Date of Schemes completion 30.06.2019.Work is in progress. Construction of Sewerage and Drianage Scheme On-going Date of A.A 26-08-2016.Date of T.S 30-09- 551 2154 Jhelum 30.000 17.456 4.167 3.125 2.084 67% 65% 2016.Work awarded on 24-01-2017.Work in Sohawa City Schemes progress "Date of A.A .14-09-2009.Date of Revise A.A 29-03- 2016.Date of T.S 24-10-2009.Date of Revis T.S 31- Urban Sewerage Scheme Jhelum with Treatment On-going 552 2155 Jhelum 539.592 382.102 33.333 25.000 16.667 67% 74% 05-2016.Date of Commencement 17-08-2016.Date Plant District Jhelum Schemes of Completion 15-08-2018.Scheme has been Revised and Administratively approved vide. No.SO(PH-S)9-16/2015 (Jhelum) Date of A.A 25.06.2009, Revised Date of A.A 31.01.2014, 2nd Revised Date of A.A 19.09.2016, Date of T.S 29.06.2009, Date of 2nd Revised T.S 30.09.2016, Date of Award 24.11.2009 & Comprehensive Urban Sewerage Scheme Bhalwal On-going 04.12.2009, Scheduled date of Completion on 553 2156 Sargodha 232.641 216.687 4.972 1.757 0.513 29% 93% 12.2010, Revised date of Completion 30.06.2018, Colonies Schemes Date of Commencement, 24.11.2009 & 04.12.2009, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.Scheme completed in saving, operational and handed over to Municipal Committee Bhalwal.

Date of A.A 27.08.2016, Date of Revised A.A 15.06.2017, Date of T.S 10.10.2016, Date of Award 16.11.2016, Scheduled date of Completion is Rehabilitation of Sewerage Scheme Kot Momin On-going 15.11.2017, Date of Commencement, 16.11.2016, 554 2157 Sargodha 152.397 32.809 3.333 0.893 0.059 7% 22% District Sargodha Schemes Funds released on 30.07.2018, Funds on-lined on 30.07.2018. Drain Type-I, II & III 4807-Rft, constructed. Land acquisition for construction of disposal works is in process. Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Construction of Sewerage PCC Soling Resoling On-going Completion is 30.06.2018, Date of Commencement, 555 2158 Sargodha 5.177 4.283 0.298 0.224 0.224 100% 87% 22.02.2017, Funds released on 30.07.2018, Funds Bashir Colony Sargodha City Schemes on-lined on 30.07.2018. RCC Sewer 12" to 24" i/d 1845-Rft laid, PCC Slab 2257-Cft laid. Work in progress Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Costruction of Sewerage / PCC / soling / Sullage On-going Completion is 30.06.2018, Date of Commencement, 556 2159 Sargodha 5.927 4.376 0.500 0.375 0.375 100% 80% 22.02.2017, Funds released on 30.07.2018, Funds Carrier Mulsim Town, Usman Park, Shiraz Park, Schemes on-lined on 30.07.2018. Sullage Carrier 1653-Rft constructed Soling 1639-Cft laid. RCC Sewer 12" i/d 961-Rft laid Work in progress

Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Construction of Sewerage PCC Soling in Nawab On-going 557 2160 Sargodha 5.430 4.789 0.214 0.161 0.161 100% 91% Completion is 30.06.2018, Date of Commencement, Colony Aziz Colony and Ghani Park Sargodha City Schemes 22.02.2017, Funds released on 30.07.2018, Funds on-lined on 30.07.2018. RCC Sewer 12" i/d 1504-Rft laid, PCC Slab 11550-Cft laid. Work in progress

Date of A.A 27.08.2016, Date of T.S 28.10.2016, Date of Award 14.02.2017, Scheduled date of Completion on 13.02.2018, Date of Urban Drainage / PCC Flooring Scheme Miani On-going Commencement, 14.02.2017, Funds released on 558 2161 Sargodha 93.181 35.964 5.000 3.750 3.750 100% 43% District Sargodha Schemes 30.07.2018, Funds on-lined on 30.07.2018. 01-No. Collecting tank completed, Sullage Carrier 23424- Rft & Drain 2546-Rft constructed. P.C.C 27147-Cft & Tuff Tile 22857-Sft laid Work in progress.

Date of A.A 09.06.2015, Date of T.S 17.06.2015, Urban Sewerage Scheme for (Islam Pura, Zafar Date of Award 31.07.2015, Scheduled date of Completion is 30.07.2017, Date of Commencement, Colony, Qartaba Town, Jauhar Colony, Sultan 31.07.2015, Funds released on 30.07.2018, Funds Town, Shirazi park, Mujhid Colony, Ali Town, On-going 559 2162 Sargodha 389.887 213.660 16.667 12.500 12.500 100% 58% on-lined on 30.07.2018.02-No. screening chamber, Gilwala Including Adjacent Colonies) & Abadies of Schemes collecting tank, pumping chamber 90% completed. 08-Sets Pumping Machinery out of 14-sets & 02- (Yousaf park, Aziz Colony, Bashir Colony, Nawab Sets Generator arranged at site. RCC Sewer 1958- Colony Rft laid. RCC Box Channel 9139-Rft constructed. Work in progress. Date of A.A 25.08.2015, Date of T.S 14.10.2015, Date of Award 15.01.2016, Scheduled date of Completion on 30.06.2017, Date of Sewerage and Drainage Scheme at Chak No.60 On-going 560 2163 Sargodha 60.000 49.976 3.334 2.501 2.500 100% 87% Commencement, 15.01.2016, Funds released on Shamali Khizarabad Ghosia Mehria Colony Schemes 30.07.2018, Funds on-lined on 30.07.2018.Drain 34406-Rft & Sullage carrier 8212-Rft constructed, Soling 4484-Cft & PCC Slab 114865-Cft laid. work in progress. "Date of A.A 02.01.2018, Date of T.S 13.02.2018, Rural Drainage Scheme U.C Bhabra, U.C Halal On-going Date of Award 20.03.2018, Scheduled date of 561 2164 Pur, U.C Takhat Hazara and Adjoining Abadies Sargodha 10.000 4.985 1.667 1.250 0.968 77% 60% Completion on 30.06.2019, Date of Schemes Tehsil Kot Momin District Sargodha Commencement, 20.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.

"Date of A.A 02.01.2018, Date of T.S 13.02.2018, Rural Drainage Scheme U.C Mouzamabd, U.C On-going Date of Award 24.03.2018, Scheduled date of 562 2165 Jalla Makhdoom, U.C Mateela including Adjoining Sargodha 10.000 5.000 1.667 1.251 0.946 76% 59% Completion on 30.06.2019, Date of Schemes Abadies Tehsil Kot Momin District Sargodha Commencement, 24.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.

"Date of A.A 02.01.2018, Date of T.S 13.02.2018, Rural Drainage Scheme U.C Ghula Pur, U.C Chak On-going Date of Award 17.03.2018, Scheduled date of 563 2166 No.11/SB, U.C Garhi Kala and Adjoining Abadies Sargodha 10.000 4.989 1.667 1.250 1.021 82% 60% Completion on 30.06.2019, Date of Schemes Tehsil Kot Momin District Sargodha Commencement, 17.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.

"Date of A.A 02.01.2018, Date of T.S 13.02.2018, Rural Drainage Scheme U.C Mela, U.C Naseer On-going Date of Award 20.03.2018, Scheduled date of 564 2167 Pur Kalan, U.C Mustafa Abad and Adjoining Sargodha 10.000 4.957 1.667 1.250 1.159 93% 61% Completion on 30.06.2019, Date of Schemes Abadies Tehsil Kot Momin District Sargodha Commencement, 20.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.

Rural Drainage Scheme U.C Dodha, U.C Gurna, "Date of A.A 02.01.2018, Date of T.S 13.02.2018, U.C Jan Muhammad Wala, U.C Laksian, U.C On-going Date of Award 20.03.2018, Scheduled date of 565 2168 Sargodha 10.000 4.989 1.667 1.251 0.981 78% 60% Completion on 30.06.2019, Date of Miana Kot and Adjoining Abadies Tehsil Kot Schemes Commencement, 20.03.2018, Funds released on Momin District Sargodha 30.07.2018, Funds on-lined on 30.07.2018.

"Date of A.A 02.01.2018, Date of T.S 13.02.2018, Rural Drainage Scheme U.C Bucha Kalan, U.C On-going Date of Award 20.03.2018, Scheduled date of 566 2169 Wan Miana, U.C Midh Ranjha and Adjoining Sargodha 10.000 4.984 1.667 1.250 1.155 92% 61% Completion on 30.06.2019, Date of Schemes Abadies Tehsil Kot Momin District Sargodha Commencement, 20.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018. Date of A.A. 05-09-2014, Date of T.S.03-10-2014, Date of Start of Work,08-11-2014, , Remarks. RCC Sewer=9" i/d=13629 /15205, 12"i/d= 3959/4960, 15"i/d= 8037/8695, 18"i/d= 3678/3675, 21"i/d=184/200, 24"i/d= 485/500, 27"i/d= 585/600, 30"i/d= 1106/1250, 33"i/d= 3232/3330, Screening Urban Sewerage / Drainag Scheme, Kamar On-going 567 2170 Mianwali 190.611 117.953 16.667 12.500 8.320 67% 66% Chamber=1/1, Collecting Tank 25'dia= 2/2, Mushani, Mianwali. Schemes P/Machinery=0/4, Suction Delivery=1/1, Discharge Sump=1/1, Generator Room=1/1, Staff Quarter=1/1, Generator Set=1/1, Boundary Wall=1/1, S/Carrier= 3120/4675, Out fall Structure=0/1, S/Drain= 14933/51760, PCC Slab= 174131/294164, Electric T/Line=0/1. Work is in progress. Provision of PCC Slab and Sewerage Scheme in On-going Date of A.A 27.08.2016 Date of T.S 30.09.2016 568 2171 Bhakkar 68.340 48.098 3.333 2.500 2.500 100% 74% Date of Commencement 28.11.2016 Date of Municipal Committee Dullay wala Schemes completion 30.06.2020 Date of A.A 15.08.2017 Date of Amended A.A 16.12.2017 Date of T.S 07.02.2018 Date of Urban Sewerage/Drainage scheme, PCC Slab & On-going 569 2172 Bhakkar 833.933 39.633 50.000 37.500 25.000 67% 8% commencement 24.03.2018 Date of completion Brick Pavement in Bhakkar City Schemes 30.06.2021 Work at Disposal Station is in progress. Payment for land acquisition has been made. Target will be acheived in the coming month.

Provision of Sewerage in Tandlianwala City District On-going Date of A.A 20-10-2016. Date of T.S.31-10-2016. 570 2173 Faisalabad 100.000 69.988 9.366 7.025 4.683 67% 75% Work order issued on 17-12-2016. Work is in Faisalabad Phase 1 Schemes progress. Funds released on 03.08.2018 & 24.1.19 Construction of Carpet Road (2200 feet) at Chak On-going 571 2174 Faisalabad 4.000 1.000 1.000 0.750 0.750 100% 44% Funds transfer to xen Highway Divison Faisalabad. No. 353/GB, District Faisalabad Schemes Construction of Boundary Wall of at Football On-going 572 2175 Faisalabad 1.500 0.500 1.000 0.750 0.750 100% 83% Funds transfer to xen Building Divison Faisalabad. Ground at Chak No.144/GB District Faisalabad. Schemes Construction of Boundary Wall of Graveyard at On-going 573 2176 Chak No. 630/GB Abadi Rairoo, District Faisalabad 2.099 0.500 1.000 0.750 0.750 100% 60% Funds transfer to xen Building Divison Faisalabad. Schemes Faisalabad. Provision of Soling /Drainage at Chak No.568/GB On-going AA issued on 15.11.2017. Funds received on 23-11- 574 2177 Faisalabad 2.000 0.485 1.515 1.136 0.700 62% 59% 2018. Work order issued on 13.12.2017. work is in Abadi Ahmad Khan District Faisalabad. Schemes progress.Funds released on 23.11.2018 & 24.1.19 AA issued on 15.11.2017. Tenders received on Provision of Soling /Drainage at Abadi Bahadur On-going 575 2178 Faisalabad 3.000 0.997 1.000 0.000 0.000 #DIV/0! 33% 28.11.2017. Funds received on 27-01-2018. Work Khan District Faisalabad. Schemes order issued on 13.12.2017. work is in progress. Funds not yet been relased uptill now. Provision of Soling /Drainage at UC- 51 District On-going AA issued on 15.11.2017. Funds received on 23-11- 576 2179 Faisalabad 1.000 0.499 0.501 0.376 0.250 66% 75% 2018. Work order issued on 13.12.2017. work is in Faisalabad. Schemes progress.Funds released on 23.11.2018 & 24.1.19 Construction of TST Road 12 feet wide4 at Abadi On-going 577 2180 Faisalabad 5.000 1.000 1.000 0.750 0.750 100% 35% Funds transferred to XEN High Way Division FSD. Hayyat Ullah, District Faisalabad. Schemes Provision Main Drainage at UC 35 Chak On-going AA issued on 15.11.2017. Funds received on 23-11- 578 2181 Faisalabad 5.000 0.998 1.000 0.750 0.490 65% 30% 2018. Work order issued on 13.12.2017. work is in No.119/GB, District Faisalabad. Schemes progress.Funds released on 23.11.2018 & 24.1.19 Repair of Road (4400 feet) 01-KM at Bhagi Dhal to On-going 579 2182 Faisalabad 3.000 0.600 1.000 0.750 0.750 100% 45% Funds transfer to xen Highway Divison Faisalabad. Purana Wasiran, District Faisalabad. Schemes Construction of TST Road at Chak No.119/GB, On-going 580 2183 Faisalabad 6.000 1.000 1.000 0.750 0.750 100% 29% Funds transfer to xen Highway Divison Faisalabad. District Faisalabad. Schemes Rehabilitation / Carpeting of Road (Length 4.00 On-going 581 2184 KM) at Lahore Road Pull Sal to Dulchian Road to Faisalabad 21.715 5.000 1.000 0.750 0.750 100% 26% Funds transfer to xen Highway Divison Faisalabad. Schemes Daand Gali, District Faisalabad.

Date of A.A 20.10.2016 Date of T.S 24.11.2016 Date of Invitation of tenders 15.12.2016. Date of Receipt of tender 24.12.2016 Date of work order Comprehensive Sewerage/ Drainage scheme AP On-going 582 2185 Jhang 100.000 30.000 6.667 5.000 4.010 80% 34% 28.12.2016 Date of Completion As per PC-I Sial (Urban) Schemes 19.10.2019 Anticipated date of completion. 27.12.2019 No of Baneficiary 12731-Persons Agreement Amount 96.709-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 583 2186 Soling at Ward NO. 1,2,3,4,5&6 and adjoining Jhang 6.000 4.000 0.667 0.500 0.390 78% 73% 07.09.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. abadies urban area Jhang 06.07.2018 No of Baneficiary 12731-Persons Agreement Amount 4.961-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 584 2187 Soling at Ward NO. 13,14,15,16,17 & 18 and Jhang 6.000 3.900 0.667 0.500 0.401 80% 72% 28.09.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. adjoining abadies urban area Jhang 06.07.2018 No of Baneficiary 12709-Persons Agreement Amount 5.006-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & On-going Receipt of tender 20.04.2017 Date of work order 585 2188 Soling at Ward NO. 19,20,21,22,23 & 24 and Jhang 6.000 4.000 0.667 0.500 0.395 79% 73% 07.09.2017 Date of work order 07.09.2017 Date of Schemes adjoining abadies urban area Jhang Completion As per PC-I 19.10.2018 No of Baneficiary 12709-Persons Agreement Amount 5.491-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 586 2189 Soling at Ward NO. 25,26,27,28,29 & 30 and Jhang 6.000 3.998 0.667 0.500 0.405 81% 73% 07.09.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. adjoining abadies urban area Jhang 06.07.2018 No of Baneficiary 112173-Persons Agreement Amount 5.494-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 587 2190 Soling at Ward NO. 31,32,33,34,35 & 36 and Jhang 6.000 3.993 0.667 0.500 0.398 80% 73% 08.08.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. adjoining abadies urban area Jhang 07.05.2018 No of Baneficiary 11596-Persons Agreement Amount 4.920-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 588 2191 Soling at Ward NO. 37,38,39,40,41,42, & 43 and Jhang 7.000 5.000 0.667 0.500 0.418 84% 77% 07.09.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. adjoining abadies urban area Jhang 06.07.2018 No of Baneficiary 13260-Persons Agreement Amount 6.191-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 589 2192 Soling at Ward NO. 44,45,46,47,48,49, & 50 and Jhang 7.000 4.963 0.667 0.500 0.412 82% 77% 08.08.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. adjoining abadies urban area Jhang 07.05.2018 No of Baneficiary 13015-Persons Agreement Amount 6.084-Million Work is in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders 18.04.2017. Date of Construction of Sewerage, PCC Slab, Drain & Receipt of tender 20.04.2017 Date of work order On-going 590 2193 Soling at Ward NO. 7,8,9,10,11&12 and adjoining Jhang 6.000 3.906 0.667 0.500 0.415 83% 72% 07.09.2017 Date of Completion As per PC-I Schemes 19.10.2018 Anticipated date of completion. abadies urban area Jhang 06.07.2018 No of Baneficiary 12768-Persons Agreement Amount 5.416-Million Work is in progress. 1-Date of A.A 12.11.20152- Date of T.S 25.02.20163-Date of Prequalification -07.03.20164- Date of invitation of tenders 18.03.20165- Date of Extension Rehabilitation of Urban Sewerage On-going Receipt of tenders 26.03.20166- Date of work odder 591 2194 Toba Tek Singh 488.756 239.700 33.333 25.000 23.000 92% 54% -29.04.20167- Date of completion as per PC-I Scheme Karnalia City Phase II Schemes 11.11.20188- Anticipated date of completion 11.11.2018 9- No. of Beneficiary - 306625 Person10- Funds Released by F.D 03.08.2018 & 24.01.2019 11-Re-appropriation of funds(+/-) Work in progress. 1-Date of A.A 12.11.20152- Date of T.S 26.02.20163-Date of Prequalification -07.03.20154- Date of invitation of tenders 18.03.20165- Date of Extension/Rehabilitation of Urban Sewerage On-going Receipt of tenders 26.03.20166- Date of work odder 592 2195 Toba Tek Singh 400.000 224.900 16.667 12.500 10.000 80% 59% -18.04.20167- Date of completion as per PC-I Scheme Gojra Schemes 11.11.20188- Anticipated date of completion 11.11.20189- No. of Beneficiary -393651 Person 10- Funds Released by F.D 03.08.2018 & 24.01.2019. 11-Re-appropriation of funds(+/-) Work in progress. 1-Date of A.A 16.10.20142- Date of T.S 03.12.20143-Date of Prequalification 08.12.20144- Date of invitation of tenders 08.12.20145- Date of Receipt of tenders 23.12.20146- Date of work order On-going 593 2196 Urban Sewerage and Drainage Scheme Pir Mehal Toba Tek Singh 290.000 230.000 6.667 5.000 5.000 100% 81% 31.12.20147- Date of Completion as per PC-I Schemes 15.10.20178- Anticipated date of completion 30.12.2018 9- No. of Beneficiary - 139496 Person 10-Funds Released by F.D 03.08.2018 1& 24.01.2019 1-Re-appropriation of funds(+/-) Work in progress. 1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Improvement of Street / Roads of Rajana Town, On-going work order 22.11.2017 7- Date of completion as per 594 2197 Toba Tek Singh 25.000 7.939 1.667 1.250 0.900 72% 35% District T.T Singh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Provision of Laying Tuff Tile, Sewerage and On-going work order 22.11.2017 7- Date of completion as per 595 2198 Toba Tek Singh 150.000 75.000 8.333 6.250 4.167 67% 53% Nullahs in Gojra, District T.T.Singh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-). Work in progress. Construction of Sewerage Drainage Tuff tiles in On-going 596 2199 Gujranwala 208.986 25.000 3.333 2.500 1.667 67% 13% Work in progress Noshera Virkan Schemes Const of Sewerage Drainage PCC Scheme Sodhra On-going 597 2200 Gujranwala 120.754 84.455 5.306 3.980 2.653 67% 72% Work in progress Talwara Tehsil Wazirabad Schemes Provision of Sewerage & water Supply Scheme at On-going 598 2201 Ghakhar & Ladhaywala, District Gujranwala Gujranwala 199.871 130.786 30.000 22.500 15.000 67% 73% Work in progress Schemes (Revised) Sewerage / Drainage & PCC / RCC Scheme at On-going 599 2202 Rahwali including Adjoining Abadies etc, Gujranwala 392.400 100.600 20.000 21.218 16.218 76% 30% Work in progress. Schemes Gujranwala. Provision of Drainage / PCC Scheme at Tehsil On-going 600 2203 Noshera Virkan & UC Sharan Kalan, District Gujranwala 77.000 16.846 3.333 2.500 1.667 67% 24% Work in progress. Schemes Gujrnawala Provision of Sanitation / Drainage in City Pindi On-going A.A 167.781 Date 04/04/2016 T.S. 167.77 date 16- 601 2204 Hafizabad 167.781 109.933 10.000 6.300 3.800 60% 68% 05-2016 work in progress Fund release but not yet Bhattian Schemes online. The work was alloted to the contractor on dt: 26-11- 2016 and contractor started the work at site .A.A 141.240 Date 06/09/2016 T.S. 142.374 date 30-09- 2016 Drain 140910 Rft, Sullage Carrier /storm water Provision of Sanitation facilities in City Sukhike On-going 602 2205 Hafizabad 141.332 129.643 3.796 2.847 1.897 67% 93% 1.5x1.5=2225 Rft 2.0x2.0=1350 Rft 2.0x2.5=2350 Mandi Schemes Rft 3.0x3.0=5878 Rft Tuff tile 60mm thick=17292 Sft 80mm thick =3200 Sft Brick Pavement/Soling = 37645 Cft, PCC 3" thick= 69726 Cft,4" thcik=56945 Cft,thick=82872 Cft, work in progress.Fund release but not yet online. The work was alloted to the contractor on dt: 26-11- On-going 2016 and contractor started the work at site .A.A 603 2206 Urban Drainage Scheme Jalapur Bhattian Hafizabad 96.640 84.870 3.884 2.913 1.940 67% 90% 141.240 Date 06/09/2016 T.S. 142.374 date 30-09- Schemes 2016 Drain 140910 Rft,Sullage Carrier /storm Fund release but not yet online. Urban Sewerage / Drianage Scheme Eastern Side On-going 604 2207 Hafizabad 219.535 141.081 10.000 7.500 5.000 67% 67% work in progress Fund release but not yet online. Ghari Awan & Allied Abadies Hafizabad City Schemes R.A.A Date =3.05.2017R.T.S date=29.9.2017.1 Nos Screening Chamber, 1 Nos Collecting Tank 20' Dia Construction of Two Pumps Station at Old On-going 6set Machinery, Force main pipe i/d Dia 10"=50 605 2208 Gujrat 108.440 66.578 13.928 10.446 6.964 67% 68% Rft,12"=100 Rft, 16"=3300 Rft, 18"=400 Rft Drain G.T.Road Drain Gujrat. Schemes type-I=2862 Rft Sullage Carrier= 2500 Rft RCC Sewer 15'=300 Rft,18"=346 Rft, 24"=1664 Rft PCC=7568 Cft .work in progress Mandi On-going * A.A Date. 09.10.2014* T.S Date. 22.12.2014 * 606 2209 Sewerage & water Supply Tank for Bhiki Sharif 116.314 90.745 8.522 6.392 4.261 67% 82% Start Date 16.02.2015* Completion date Bahauddin Schemes 30.06.2019. * Work in progress. Sewerage / Drainage Scheme Malikwal City, Mandi On-going * A.A Date. 06.01.2016* T.S Date. 15.01.2016* Start 607 2210 237.200 62.105 8.333 5.350 3.267 61% 28% Date 11.03.2016* Completion date 10.03.2019.* Distt.M.B.Din Bahauddin Schemes Work in progress. Urban Sewerage/ Drainage PCC and Tuff Tiles in Mandi On-going * A.A Date. 06.09.2017* T.S Date. 24.10.2017* Start 608 2211 270.500 27.095 10.000 7.500 5.000 67% 12% Date. 07.01.2018* Completion date City Phalia Tehsil Phalia District M.B.Din Bahauddin Schemes 06.01.2021.Work in progress.

Provision of Sewerage/PCC Streets/ Drain/Tuff Mandi On-going * A.A Date. 25.08.2017* T.S Date. 06.09.2017* Start 609 2212 75.000 55.000 6.667 5.000 3.337 67% 78% Date. 06.01.2018* Completion date 05.01.2020* Tiles/Park and Janazgah District M.B.Din Bahauddin Schemes Work in progress. Provision of PCC / Soling / Nullah / Street Scheme at Adalat Garah Bashamula, Muzaffarpura, On-going 610 2213 Dhanay, phabarainawala, Gujayanwala, Ravail Sialkot 200.000 25.000 3.333 2.500 1.667 67% 13% Work in progress. Schemes pura, Stabgary, Burj / Butter etc.,Teshil & District Sialkot Provision of Sewerage Drainage and and Tuff Tile On-going 611 2214 Sialkot 100.000 30.000 3.333 2.500 1.667 67% 32% Work in progress. at Daska City Schemes Construction of Street PCC / Tufff Tiles Drains & On-going 612 2215 Nullah Fazal Pura & adjoining Streets Sambrial Sialkot 80.000 49.845 3.333 2.500 1.667 67% 64% Work in progress. Schemes City Construction of Street PCC / Tufff Tiles Drains & On-going 613 2216 Nullah in Mandi Samrial and old Sambrial Tehsil Sialkot 80.000 44.945 3.333 2.500 1.667 67% 58% Work in progress. Schemes Sambrial Construction of Street PCC/Tuff Tiles Drains & On-going 614 2217 Nullah in Mohallah Rasoolpur & More Sambrial, Sialkot 80.000 44.992 3.333 2.500 1.667 67% 58% Work in progress. Schemes Tehsil Sambrial Construction of Streets (Drains, PCC) Mohallah On-going 615 2218 Sharif Pur, Habib Pura, Bashir Pura, Nazir Abad Sialkot 90.000 49.918 3.333 2.500 1.667 67% 57% Work in progress. Schemes Colony and others. Construction of Urban Drainage Scheme Pasrur On-going 616 2219 Sialkot 99.827 24.992 3.333 2.500 1.667 67% 27% Work in progress. City, Tehsil Pasrur, District Sialkot. Schemes Construction of Nallah Around Road from Uggoki On-going 617 2220 to Rai Pur Abba Baigowala Ganda Nallah Railway Sialkot 199.826 69.726 5.000 3.750 2.500 67% 36% Work in progress. Schemes Station etc. Tehsil Sambrial ,District Sialkot Removal of ponds / construction of Pull and On-going 618 2221 establishment of Park at Moza Bahlor Tehsil Sialkot 36.043 20.643 5.133 1.283 0.000 0% 57% Scheme completed Schemes Pasrur, District Sialkot. Const of PCC / Tuff tiles of City Package Zafarwal On-going *Date of A.A 9.4.2016 *Date of T.S 19.4.2016 *Start 619 2222 Narowal 69.569 49.569 6.667 5.000 3.324 66% 76% Date 6.6.2016 *Completion date 30.06.2019.Work in City Schemes progress. Sewerage scheme for Talwandi Bhindran, On-going A.A Date.3.5.2014 T.S Date.23.5.2014 *Start Date 620 2223 Narowal 109.876 105.797 1.360 1.020 0.677 66% 97% 25.08.2014*Completion date 30.06.2019.Work in Narowal. Schemes progress. Fund not received on spending end yet. Provision of clean drinking water Sewerage system On-going 621 2224 PCC and allied facilities in Chung Mohlanwal Lahore 200.742 171.650 9.697 11.073 8.649 78% 90% Physically scheme is completed, balance funds are Schemes required to clear the contractor's liability. Manak Provision of clean drinking water, Sewerage On-going 622 2225 system, PCC and allied facilities in Babo Mehar Lahore 200.012 171.650 9.454 7.091 4.727 67% 88% Physically scheme is completed, balance funds are Schemes required to clear the contractor's liability. Town, Lidhar, Bedian Road and adjoining abadies Provision of clean drinking water, Sewerage On-going 623 2226 system, PCC and allied facilities in Jallo More, Lahore 509.268 219.523 26.667 20.000 13.334 67% 46% Work stopped due to awaiting funds. Schemes Batapur PCC and drainage Scheme in UC 117 Mansoora On-going 624 2227 Lahore 202.567 128.019 5.000 3.750 2.500 67% 64% Work stopped due to awaiting funds. Lahore. Schemes Construction of PCC, Nallah at Maraka UC-122, Shamke Bhattian, Chahram & mal, Manga Mandi On-going 625 2228 Lahore 24.200 7.634 5.522 2.642 1.261 48% 37% Physically scheme is completed, balance funds are Sunder, Kot Fateh Muahammad Athul, District Schemes required to clear the contractor's liability. Lahore Construction of PCC Sewerage & Drainage On-going 626 2229 System at UC-272 Raiwind Kalan & UC-273 Lahore 8.000 5.581 0.806 0.202 0.000 0% 70% scheme completed Schemes Raiwind City, District Lahore Katcha Storm / Sullage Water Channel in District On-going 627 2230 Sheikhupura 199.813 139.520 5.000 3.750 2.500 67% 71% Work in Progress Sheikhupura Schemes Provision of Sewerage Scheme Burjwala, Saleem On-going 628 2231 Sheikhupura 174.527 165.000 3.176 2.382 1.588 67% 95% Work in Progress Kot, Housing Colony, City Sheikhupura Schemes Provision of Sewerage system in mohllah ghareeb On-going 629 2232 Sheikhupura 157.452 155.000 0.817 0.613 0.409 67% 99% Work in Progress abad etc City Sheikhupura Schemes Provision of Open water Supply Scheme On-going 630 2233 Sheikhupura 199.210 82.664 3.333 2.500 1.667 67% 42% Work in Progress Ferozwala. Schemes Provision Of Sewerage and PCC Scheme Pir On-going 631 2234 Bahar Shah, Qazi Park Ramgarah & Purana Sheikhupura 175.000 95.000 3.333 2.500 1.667 67% 55% Work in Progress Schemes Shehar City Sheikhupura Urban Sewerage / Drainage Scheme Sharqpur On-going 632 2235 Sheikhupura 183.441 89.027 3.333 2.500 1.667 67% 49% Work in Progress Seikhupura , Sharqpur Schemes Urban Sewerage Scheme Ferozwala New Sewer On-going 633 2236 Sheikhupura 199.330 184.330 5.000 3.750 2.500 67% 94% Work in Progress Lines District Sheikhupura Schemes Urban Drainage & PCC Scheme Northn Side of On-going 634 2237 Sheikhupura 96.319 48.319 5.000 3.750 2.500 67% 53% Work in Progress Railway Track City Sheikhupra Schemes Providing and laying of sewerage at Ghaloria On-going 635 2238 Colony Farooq Nagar Shah Colony District Sheikhupura 97.683 47.683 5.000 3.750 2.500 67% 51% Work in Progress Schemes Sheikhupura Execution of Sanitation Sector Development On-going 636 2239 Nankana Sahib 50.000 23.600 3.333 4.500 3.667 81% 55% Work is in progress. scheme Shah Kot City District Nankana Sahib Schemes Const. of Storm Water Channel / Ext. & On-going 637 2240 Improvement Urban Sewerage / Drainage Scheme Nankana Sahib 119.138 99.756 6.461 4.846 3.231 67% 86% Work is in progress. Schemes Shahkot Phase-II Augmentation / Rehabilitation of Urban Sewerage On-going 638 2241 Nankana Sahib 264.253 130.000 5.000 3.750 2.500 67% 50% Work is in progress. Scheme, Nankana Sahib Schemes Construction of Sullage Carrier for Ultimate On-going 639 2242 Disposal of Phoolnagar City, Tehsil Pattoki, District Kasur 337.971 18.614 20.000 15.000 10.000 67% 8% Work in Progress Schemes Kasur Provision of Sewerage & Drainage System in On-going 640 2243 Kasur 99.011 76.401 20.000 16.520 11.520 70% 89% Work in Progress Chunian City, Kasur Schemes On-going 641 2244 Urban Drainage Scheme Kasur city District kasur Kasur 99.827 34.999 20.000 16.389 11.389 69% 46% Work in Progress Schemes Urban Drainage, PCC & Brick Pavement scheme On-going 642 2245 Kasur 457.681 407.681 16.667 12.500 8.334 67% 91% Work in Progress Kasur city District Kasur Schemes Urban PCC & Drainage Scheme Kot Radha On-going 643 2246 Kasur 112.887 104.597 2.758 0.690 0.000 0% 93% Work in Progress Kishan District Kasur. Schemes Urban Sewerage Drainage Scheme, Pattoki On-going 644 2247 Kasur 680.017 657.032 6.294 1.621 0.047 3% 97% Work in Progress (Revised) Schemes Sewerage Drainage Scheme Kangan Pur District On-going 645 2248 Kasur 161.161 122.346 3.333 2.500 1.667 67% 77% Work in Progress Kasur. Schemes Drainage P.C.C. & Brick pavement in Mustafabad, On-going 646 2249 Kasur 246.400 196.400 16.667 4.977 0.811 16% 80% Work in Progress Kasur. Schemes Date of AA 03.03.2014, Date of TS 05.03.2014, Complete Repair and renovation of Sewerage Date of Pre-qualification.05.05.2014, Date of Receipt of Tenders,20.05.2014, Date of work Order. system including PCC, Drains, water channels, On-going 647 2250 Okara 184.048 172.023 4.006 3.005 1.926 64% 95% 30.05.2014, Date of completion As per PC-I. soling, tuff tiles etc. in M.C. Mandi Ahmed Abad, Schemes 30.06.2016, Anticipated date of completion.30.06.2019, Projected Population 66950 District Okara. Person, Funds Release on 20-07-2018 Release of Funds 02.08.2017. Date of AA 02.04.2014, Date of TS 14.04.2014, Date of Pre-qualification.10.04.2014, Date of Invitation of Tender 05.05.2014, Date of Receipt of Construction of Sewerage Scheme Renala Khurd On-going Tenders 05.05.2014, Date of work Order 648 2251 Okara 327.480 296.423 10.352 7.764 5.176 67% 92% 13.05.2014, Date of completion As per PC-I. City, District Okara Schemes 30.06.2016., Anticipated date of completion,30.06.2019, Funds Release on 20-07- 2018 Projected Population 119573 Person, Release of Funds 02.08.2017. Date of AA 09.04.2010 ( Original), Date of Revised AA 31.10.2014 , Date of TS 18.08.2010 (Phase -I), Date of Revised TS 05.03.2015 , Date of Pre- qualification,20.03.2015, Date of Invitation of On-going 649 2252 Sewerage Scheme Depal Pur City District Okara Okara 300.355 269.408 3.620 2.715 1.810 67% 90% Tender 09.05.2015, Date of Receipt of Tenders Schemes 10.05.2015, Date of work Order 20.06.2011 & 03.09.2015, Date of completion As per Revised PC- I. 31.12.2017, Anticipated date of completion,30.06.2019, Funds Release on 20-07- 2018 Projected Population 229210 Person, Date of AA 16.05.2014, Date of TS 28.06.2014, Date of Pre-qualification 17.06.2014, Date of Invitation of Tender 30.06.2014, Date of Receipt of On-going 650 2253 Sewerage Scheme Shergarh Renala Khurd Okara Okara 99.224 94.810 1.424 1.068 0.841 79% 96% Tenders 30.06.2014, Date of work Order Schemes 17.09.2014, Date of completion As per PC- I.14.09.2016 , Anticipated date of completion,30.06.2019, Funds Release on 20-07- 2018 Projected Population 26497 Person. Extension, Improvement Complete Repair, Date of A.A 30-11-2017 Date of T.S 24-01-2018 Date of Prequalification 13-09-2017 Date of Renovation of Sewerage and and Water Supply On-going invitation of tenders 22-02-2018 Date of Receipt of 651 2254 System alongwith Provision of Strom Water Okara 398.910 59.545 6.667 5.000 3.587 72% 16% tenders 22-02-2018 Date of work order 22-03-2018 Schemes Channels, Street Lights and Tuff Tiles in Hujrah Date of completion as per PC-I 22-03-2021 Anticipated date of completion 30-06-2021 No. of Shah Muqeem, District Okara Beneficiary 47415 Person Work is in progress. Date of AA 13.10.2016 , Date of TS 07.12.2016, Date of Pre-qualification 08.02.2017, Date of receipt Rehabilitation/Augmentation of Sewerage System On-going of tender 18.02.2017 , Date of Work Order 652 2255 Sahiwal 78.583 56.389 7.398 5.549 5.000 90% 78% 22.03.2017 , Date of completion as per PC-1 at Harrappa City Schemes 30.06.2018 , Date of completion as per agreement 30.06.2018, Anticipated date of completion 30.06.2019, Work in progress.

1.Date of AA 11.04.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Provision / Rehablitation / Improvement of water tender 27.09.2017 5.Date of Receipt of tenders Supply in Urban U/Cs-12 & 13 and Construction of On-going 18.10.2017 6.Date of work order 06.11.2017 7.Date 653 2256 Multan 6.000 4.000 0.667 0.166 0.000 0% 67% of Completion as per PC-l 05.05.2018 8. Anticipated Drain, Tuff Tiles, Sewerage in Urban U/Cs- Schemes date of completion 30.06.2019 9. Date of released 23,24,26 & 41 Multan City of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4648 persons. Scheme completed.Rs 0.166 million proposed for re-appropriation.

1. Date of A.A. 15.01.2014 (21.04.2016) 2. Date of T.S. 22.01.2014 (05.08.2016) 3. Date of Prequalification 27.01.2014 4. Date of Invitation of Tender 12.02.2014 5. Date of Receipt of Tenders Extension of Urban Sewerage Scheme Jalalpur On-going 654 2257 Multan 196.830 158.627 12.289 9.217 6.145 67% 84% 24.02.2014 6. Date of work order Pirwala, District Multan (Revised) Schemes 10.03.2014/18.11.2016 7. Date of Completion as per PC-l 14.01.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. No. of beneficiaries= 170275 persons. Work is in progress. 1. Date of AA 26.08.2014. 2. Date of T.S 15.10.2014. 3. Dated of Prequalification 11.08.2014. 4. Date of invitation of tender 23.10.2014. 5. Date of Receipt of tenders 24.10.2014. 6. Date of work Sewerage Water Disposal from North South On-going order 08.11.2014. 7. Date of Completion as per PC-l 655 2258 Multan 145.222 118.112 8.989 2.247 0.000 0% 81% 25.08.2016 8. Anticipated date of completion Shujabad City Multan Schemes 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving and handed over to TMA Shujabad.Rs 2.247 million proposed for re-appropriation.

1. Date of A.A: 12.02.2015 2. Date of T.S: 05.03.2015. 3. Date of Pre-Qualification: 11.08.2014. 4. Date of Invitation of Tender: 23.10.2014. 5. Date of Receipt of Tender: Rehabilitation / extension of Sewerage / drainage On-going 656 2259 Khanewal 306.616 254.224 17.464 13.098 12.388 95% 87% 24.10.2014 6. Date of Work order: 05.11.2014 7. system of Mian Channu City Schemes Date of Completion as per PC-I: 25.08.2016 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 200428 Persons Work is in progress. 1. Date of A.A: 27.08.2016 2. Date of T.S: 25.10.2016 3. Date of Pre-Qualification: 26.10.2016 4. Date of Invitation of Tender: 03.12.2016 5. Date of Receipt of Tender: 05.12.2016 6. Date of Work Revamping of Jahanian Sewerage System, On-going 657 2260 Khanewal 199.359 97.866 16.667 12.500 11.213 90% 55% order: 15.12.2016 7. Date of Completion as per PC- Jahanian Schemes I: 30.09.2019 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 65206Persons Work is in progress. 1. Date of A.A: 18.11.2017 2. Date of T.S: 08.12.2017 3. Date of Pre-Qualification: 06.09.2017 4. Date of Invitation of Tender: 30.01.2018 5. Date of Receipt of Tender: 31.01.2018 6. Date of Work Provision of Urban sewerage Scheme at Kabirwala On-going 658 2261 Khanewal 99.676 49.676 10.000 7.500 6.719 90% 57% order: 10.02.2018 7. Date of Completion as per PC- City, District Khanewal. Schemes I: 31.03.2019 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 56299 Persons Work is in progress.

1. Date of A.A: 29.12.2014. 2. Date of T.S: 12.03.2015 3. Date of Pre-Qualification: 13.03.2015 4. Date of Invitation of Tender: 10.04.2015 5. Date of receipt of Tender: 11.04.2015 6. Date of Award: Provision of drainage / Sewerage, soling & water On-going 659 2262 Vehari 358.775 233.686 16.667 12.500 11.250 90% 68% 20.04.2015 7. Date of Completion as per PI: Supply in Municipal Area of Burewala City. Schemes 28.12.2016 8. Anticipated Date of Complion: 30.06.2018 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiaries 226016 Persons. Work is in progress. Comprehensive Sewerage / Drainage Scheme Dera Ghazi On-going 660 2263 Taunsa Sharif including Tuff Tilling of Streets - 485.406 214.529 33.333 25.000 6.428 26% 46% • Date of A.A = 12.02.2015 Khan Schemes InActive Construction of Nali Soling in UC Basti Jaam, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Ara Jafar, Dera Ghazi On-going 661 2264 21.500 10.747 3.583 2.687 1.935 72% 59% "• Date of A.A = 04.10.2017 Construction Of Nali Soling,Tough Tiles Khan Schemes Drainage,Culverts And Qulabas U/C Kotla Ahmad Khan, District D.G. Khan. Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas Muza Chak Masso Dera Ghazi On-going 662 2265 U/C Nawan Shumali, Construction Of Nali 6.000 2.973 1.000 0.750 0.548 73% 59% "• Date of A.A = 04.10.2017 Khan Schemes Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Jakhar Imam Shah, District D.G. Khan. Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 663 2266 Drainage,Culverts And Qulabas U/C Haji Kamand, 9.000 4.442 1.500 1.125 0.844 75% 59% "• Date of A.A = 04.10.2017 Khan Schemes District D.G. Khan. 10930 Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Khan Pur Janobi, Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 664 2267 33.700 16.843 5.617 4.213 2.991 71% 59% "• Date of A.A = 04.10.2017 Drainage,Culverts And Qulabas U/C Nawan Khan Schemes Shumali, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C N

Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Aali Wala, Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 665 2268 52.000 25.955 8.667 6.500 4.875 75% 59% "• Date of A.A = 04.10.2017 Drainage,Culverts And Qulabas U/C Jalbani, Khan Schemes Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Basti Malana,

Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Tibbi Kharak, Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 666 2269 130.000 64.993 6.000 4.500 3.375 75% 53% "• Date of A.A = 04.10.2017 Drainage,Culverts And Qulabas U/C Chabri Khan Schemes Zareen, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Kot, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Darahma, Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 667 2270 Drainage,Culverts And Qulabas U/C Samina, 29.000 14.485 4.833 3.625 2.719 75% 59% "• Date of A.A = 04.10.2017 Khan Schemes Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Chorahatta, Dist Construction of Nali Soling V/C Aliwala C/O Fateh Muhammad Bazgir, Construction of Nali Soling, Dera Ghazi On-going 668 2271 10.000 4.978 1.667 1.250 0.888 71% 59% "• Date of A.A = 04.10.2017 Tuff Tiles, Drainage, Culverts and Qulabas U/C Khan Schemes Mana Ahmadani, District D.G. Khan. Construction of Nali Soling, Tuff Tiles, Drainage, Dera Ghazi On-going 669 2272 Culverts and Qulabas U/C Notak Mahmeed, 11.000 5.474 1.833 1.375 1.045 76% 59% "• Date of A.A = 04.10.2017 Khan Schemes District D.G. Khan. Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Darkhast Jamal Khan Darmiani, Construction Of Nali Dera Ghazi On-going 670 2273 10.000 5.000 1.667 1.250 0.938 75% 59% "• Date of A.A = 04.10.2017 Soling,Tough Tiles Drainage,Culverts And Qulabas Khan Schemes U/C Darkhast Jamal Khan Janobi, Construction Of Nali Soling,Tough Tiles Drainage, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Jhoke Utra, Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 671 2274 Drainage,Culverts And Qulabas U/C Hazara, 47.500 23.731 3.333 2.500 1.825 73% 54% "• Date of A.A = 04.10.2017 Khan Schemes Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Haider Quresh Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Khan Pur Janobi, Construction Of Nali Soling,Tough Tiles Dera Ghazi On-going 672 2275 40.000 20.000 1.000 3.334 2.809 84% 57% "• Date of A.A = 04.10.2017 Drainage,Culverts And Qulabas U/C Nawan Khan Schemes Shumali, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C N Construction of Urban Sewerage Drainage Earth On-going 673 2276 filling brick pavement and Tuff Tile scheme for Rajanpur 61.369 55.200 1.000 0.750 0.500 67% 91% " Date of A.A = 24.4.2015 Schemes Rojhan Urban drinage/Sewerage/tuff tile scheme in Jampur City (replacement of outlived sewer and On-going 674 2277 Rajanpur 365.753 195.169 33.333 25.000 16.667 67% 58% "• Date of A.A = 23.12.2014 new sewer system in Faisal Colony, Shah Jamal Schemes Colony and Tattar Wala) Rural Drainage Sewerage PCC and Tuff Tile On-going 675 2278 flooring Rajan Pur City and Adjoining Abadies UC Rajanpur 40.500 25.600 4.967 3.725 2.484 67% 69% "• Date of A.A = 24.4.2015 Schemes Rajan Pur Construction of drain, brick pavement sullage On-going 676 2279 carrier culverts & tuff tile flooring scheme of fazilpur Rajanpur 50.000 25.000 8.333 6.250 0.000 0% 50% "• Date of A.A = 17.12.2014 Schemes tehsil & district rajanpur Open Drainage & Tuff Tile Scheme in Remaining On-going 677 2280 Muzaffargarh 49.850 32.404 5.815 4.361 2.908 67% 71% "• Date of A.A 22-09--2016 Portion of Kot Addu City Schemes Sewerage System for Recep Tayyip Erdogan On-going 678 2281 Muzaffargarh 191.449 78.700 1.000 0.750 0.000 0% 41% Part-I is Completed Hospital Muzaffargarh Expansion Project Schemes Comprehensive Sewerage Scheme alongwith Tuff On-going 679 2282 Layyah 199.995 105.377 16.667 12.500 8.300 66% 57% • Date of AA = 22-09-2016 Tiles in City Chowk Azam Schemes On-going 680 2283 Urban Sewerage / Drainage Scheme Chowk Azam Layyah 147.290 138.871 1.000 0.750 0.500 67% 95% "• Date of AA(Original) = 10-09-2007 Schemes On-going 681 2284 Urban Sewerage Scheme for Kot Sultan Layyah 191.440 152.935 6.667 5.000 3.334 67% 82% • Date of AA = 24-02-2009 Schemes

Date of AA :26-02-2014. Date of TS :05-03-2014. Date of RAA=12-05-2016. Date of pre-qualification: 07-03-2014. . Date of receipt of tenders. 02-04- 2014. Date of work order :29-04-2014. Date of completion as per agreement:28.04.2016. Anticipated date of completion=30-06-2019. Date of Sewer Line from Bahawalpur Victoria Hospital to On-going receipt of funds by F.D. 20.07.2018 & 11.01.2019. 682 2285 Bahawalpur 172.906 139.513 11.131 8.348 5.560 67% 84% Work is in progress. Date of AA :26-02-2014. Date Disposal Lal Bagh Tehsil & District Bahawalpur. Schemes of TS :05-03-2014. Date of RAA=12-05-2016. Date of pre-qualification: 07-03-2014. . Date of receipt of tenders. 02-04-2014. Date of work order :29-04- 2014. Date of completion as per agreement:28.04.2016. Anticipated date of completion=30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 04.05.2016. Date of T.S 26-05-2016. Date Awarded 11.06.2016. Date of completion 11- Sewerage / Tuff Tile in Choti Karana Tehsil & On-going 09-2017. Expected date of completion 30-06-2018. 683 2286 Bahawalpur 1.288 0.883 0.135 0.033 0.000 0% 69% Funds released by FD 20.07.2018 & 11.01.2019. . District Bahawalpur. Schemes Work completed during 2017-2018. Liability of the contractor cleared.Excess funds Rs. 0.068 million surrendered dated 19.10.2018. Date of AA 19.03.2015. Date of T.S 18.04.2015. Date of award 18.05.2015. Date of completion 17.09.2015. Expected date of completion 30-06- Construction of Tuff Tile in Main Street Gillani City On-going 2018. Funds released by FD 20.07.2018 & 684 2287 Bahawalpur 3.089 0.801 0.763 0.190 0.000 0% 26% 11.01.2019. . Scheme remained unfunded during Uch Sharif Tehsil Ahmed Pur East, Bahawalpur. Schemes 2016-2017. Remaining work has been executed/completed by Local Government due to which funds not required. Excess funds Rs. 0.0382 million surrendered dated 19.10.2018. Date of AA: 11.01.2014. Date of TS: 17.01.2014. Date of RTS 23-11-2016. Date of pre-qualification: 28.02.2014. Date of receipt of tenders = 19-03- Laying of Tuff Paver and provision of water Supply On-going 2014. Date of work order=11.04.2014. Date of 685 2288 Bahawalnagar 70.000 49.812 4.922 3.692 3.000 81% 75% completion as per agreement=10.04.16. Anticipated Pipelines in City Bahawalnagar. Schemes date of completion=30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. . Original scope of work is completed. Revised scope of work is in progress. Date of AA = 29-09-2016(DDSC). Date of T.S. 08.02.2017. Funds released by FD= 04-07-2017 . Provision of Sewerage Scheme Zone A with Tuff On-going Prequalification of the contractor 26-01-2017. 686 2289 Bahawalnagar 399.587 138.058 50.000 50.000 50.000 100% 47% Tender received on 22.03.2017 . Date of work Paver at Bahawalnagar Schemes awarded.03-05-2017. . Date of completion 02-05- 2019. . Date of receipt of funds by F.D. 20.07.2018 and 19-12-2018. Work is in Progress.

Date of A.A 25.05.2014 . . Date of T.S. 21-07-2014. Date of Prequalification. 21-07-2014. Date of receipt of tenders =12-08-2014. Date of work order= 16-09- Sewerage Scheme Chishtian City Uplift Package On-going 2014. Date of completion as per agreement= 687 2290 Bahawalnagar 916.110 672.765 33.333 25.000 21.500 86% 76% Chishtian Schemes 15.09.2017.Anticipated date of completion = 30.06.2019 .No. of beneficiaries=342309 persons. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(PDWP) 19-01-2017.Date of T.S 16.02.2017.. Prequalification of the contractor 15.03.2017..Date of receipt of tender:- 03.04.2017. Rahim Yar On-going 688 2291 Mega Sewerage Scheme Liaqatpur City 500.000 49.996 66.667 50.000 33.200 66% 17% .Date of award 24.07.2017 Date of completion. 23- Khan Schemes 07-2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019..Funds of 3rd Quarter is not credited/onlined to the District Accounsts office RYK..Work is in progress. Date of AA. 23-09-2014. Date of TS.. 27-11-2014. Date of prequalification. 08-12-2014. Date of receipt Request for provision of Sewerage Scheme of Rahim Yar On-going of tenders = 31-12-2014. Date of work order=10-2- 689 2292 199.970 160.769 13.063 9.797 8.150 83% 84% 15. Date of completion as per agreement 09-8-16. Feroza Town, Tehsil Liaqat Pur Khan Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of AA. 09-10-2014. .Date of TS. 21-11- 2014.Rev: TS 28.10.2016..Date of prequalification. 08-12-2014..Date of receipt of tenders = 31-12- 2014..Date of work order= 10-01-2015..Date of Rahim Yar On-going 690 2293 Rehabilitation of Sewerage City Sadiqabad 70.326 52.373 5.984 1.688 0.192 11% 75% completion as per agreement= 09-01- Khan Schemes 2016.Anticipated date of completion=30-06-2018. Scheme completd in saving. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Funds not required during 2018-2019. Excess funds Rs. 1.496 million proposed to Re-appropriate. Date of AA 19-12-2017.Date of T.S 15-02- Laying of Soling, Water Supply, Sewerage Line Rahim Yar On-going 2018.Tenders received on 13-03-2018 .Date of 691 2294 40.000 19.958 6.667 5.000 3.888 78% 60% award 18.04.2018..Date of completion and Tuff Tiles in City Sadiq Abad. Khan Schemes 12.04.2019..Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA 19-12-2017.Date of T.S 15-02- 2018.Date of receipt of tenders 13-03-2018 .Date of Laying of Soling, Water Supply, Sewerage Line Rahim Yar On-going 692 2295 35.000 17.468 5.833 4.375 3.501 80% 60% work awarded 30-03-2018.Date of completion 29-06- and Tuff Tiles in Rural Area Tehsil Sadiq Abad. Khan Schemes 2019..Anticipated date of completion 30-06- 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA 19-12-2017.Date of T.S 16-02- Laying of Soling, Water Supply, Sewerage Line 2018.Date of receipt of tenders 13-03-2018 .Date of Rahim Yar On-going 693 2296 and Tuff Tiles in Chak No. 148/P Tehsil Sadiq 8.000 3.984 1.333 1.000 0.799 80% 60% work awarded 07-04-2018.Date of completion 06-06- Khan Schemes 2019..Anticipated date of completion 30-06- Abad. 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA 19-12-2017.Date of T.S 16-02- 2018.Tenders received on 13-03-2018..Dated of Construction of Sewerage Line and Soling Wahid Rahim Yar On-going 694 2297 5.000 2.471 0.833 0.625 0.493 79% 59% award 11.05.2018..Date of completion Bux Mahar Tehsil Sadiq Abad. Khan Schemes 26.06.2018..Anticipated date of completion 30-06- 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA =05.03.2014.Date of TS=05.03.2014.Date op receipt of Tenders Rehabilitation / Augmentation of Sewerage Rahim Yar On-going 25.03.2014.Date of work awarded 14.04.2014..Date 695 2298 scheme Khan Pur city Phase-II District Rahim Yar 452.844 432.844 2.000 1.500 1.211 81% 96% of completion 13.04.2016..Scheme remained Khan Schemes Khan unfunded. Funds released by FD on 12-11-2018 & 11.01.2019. Scheme completed. Liability of the contractor Rs. 20.00 Million is yet to be cleared. 1. Date of AA =02.05.2016 2. Date of TS = 19.08.2016 . 3. Date of work order= 22.10.2016. 4. Comprehensive Sewerage scheme Chenab Nagar On-going Date of Completion as per PC-I = 3 Ye.5. 696 2299 Chiniot 719.952 164.999 66.667 50.000 32.750 66% 27% Anticipated Date of Comp = 30.06.2019 6. No. of Chiniot Schemes Beneficiaries= 116058.Funds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. 1. Date of AA =15.09.2014. 2. Date of TS =28.11.2014 3. Date of Pre-qualification =06.12.2014 4. Date of inviting Tenders=20.12.2014 New urban Sewerage scheme for Mohallah Fateh On-going 5. Date receipt of Tenders= 20.12.2014 6. Date of 697 2300 Abad Rashida Osmanaabad paris road Moazam Chiniot 199.694 103.971 16.667 12.500 12.500 100% 58% work order= 01.01.2015 7.Date of Completion as Schemes Shah Shahbaal per PC-I =2 Year 8. No. of Beneficiaries 94630 Funds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drain, Pulian Hajiabad, Muradwala, On-going 698 2301 Chiniot 4.998 0.800 1.000 0.750 0.500 67% 26% 26.08.2017 3.Date of Award of work 31.10.2017 Sabowala,Colony, Sabowala, District Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 02.08.2017 2. Date of TS = Construction of PCC / Soling / Drain, in Town On-going 699 2302 Chiniot 10.000 9.410 0.590 0.443 0.295 67% 97% 26.08.2017 3.Date of Award of work 31.10.2017 Committee Lalian, District Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 24.12.2012 2. Date of TS = Extension Rehabilitation Sewerage Scheme On-going 700 2303 Chiniot 212.366 209.621 1.000 0.750 0.500 67% 99% 29.10.2013 (Revised) 3.Date of Award of work Chiniot City. Schemes 31.01.2013. Work completed. Liability of the contractor is pending. Construction of PCC / Soling / Drain,Pullian Mouza 1. Date of AA = 02.08.2017 2. Date of TS = On-going 701 2304 Colony Mohammad Wala, Muhammad Wala, Chiniot 4.000 2.539 1.461 1.096 0.731 67% 82% 26.08.2017 3.Date of Award of work 31.10.2017 Schemes Work completed. Liability of the contractor is Mamola, District Chiniot pending. 1. Date of AA = 31.07.2015 2. Date of TS = Construction of Sewerage Disposal Harsa Sheikh On-going 702 2305 Chiniot 28.493 22.230 1.000 0.750 0.500 67% 80% 27.08.2015 3.Date of Award of work 31.10.2015. Lahore road Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 02.08.2017 2. Date of TS = Construction of PCC / Soling / Drain,Mouza Burj On-going 703 2306 Chiniot 4.000 2.957 1.043 0.782 0.522 67% 87% 26.08.2017 3.Date of Award of work 31.10.2017 Babal , District Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs / UC No.35 On-going 704 2307 Chiniot 5.000 4.729 0.271 0.203 0.136 67% 97% 26.08.2017 3.Date of Award of work 31.10.2017 Tehsil Bhowana District Chiniot in PP-76, Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs / Mc On-going 705 2308 Chiniot 10.000 7.409 1.000 0.750 0.500 67% 79% 26.08.2017 3.Date of Award of work 31.10.2017 Bhowana District Chiniot in PP-76, Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs /Uc No.34 On-going 706 2309 Chiniot 4.000 3.804 0.196 0.147 0.098 67% 98% 26.08.2017 3.Date of Award of work 31.10.2017 Tehsil Bhowana District Chiniot PP- 76, Chiniot Schemes Work completed. Liability of the contractor is pending. 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs / UC No.33 On-going 707 2310 Chiniot 5.000 2.669 1.000 0.750 0.500 67% 63% 26.08.2017 3.Date of Award of work 31.10.2017 Tehsil Bhowana District Chiniot in PP-76, Chiniot Schemes Work completed. Liability of the contractor is pending. Capacity Strenghthening of Design Cell of On-going 708 2311 Punjab 180.278 62.397 8.333 25.850 23.767 92% 48% In Progress HUD&PHED for project Schemes Construction of Residential Buildings at Lahore On-going 709 2312 Punjab 277.000 81.706 10.000 7.500 5.000 67% 31% In Progress Head Quarter for officers BS 16 to BS 18 PHED Schemes Improvement and Extension of the Water Testing On-going 710 2313 Punjab 260.000 19.590 50.000 12.500 0.000 0% 8% In Progress Laboratories Phase I Schemes On-going 711 2314 Renovation of PHED Head Quarter Building. Punjab 95.000 38.500 0.833 0.625 0.417 67% 41% In Progress Schemes Establishment of Management Information System On-going 712 2315 and Monitoring & Evaluation (MIS & ME) For Punjab 175.000 30.000 11.667 14.750 10.860 74% 23% In Progress Schemes Capacity Building Establishment of PMU for WASH (Water, On-going 713 2316 Punjab 35.000 4.200 3.267 4.850 3.710 76% 23% In Progress Sanitataion & Hygiene) Schemes Establishment of regional design cell at each civil On-going 714 2317 Punjab 19.043 1.443 3.333 0.900 0.000 0% 8% In Progress division / Circle level Schemes Preparation of Water Quality Survey & Sewerage On-going 715 2318 Master Plan/Development Plan of Districts, Tehsil Punjab 18.235 12.435 1.650 1.238 0.000 0% 68% In Progress Schemes and Urban Area On-going 716 2319 Survey & investigation of water source Punjab 9.436 0.456 2.993 0.845 0.000 0% 5% In Progress Schemes Third Party Validation for Quality Control of the On-going 717 2320 Punjab 39.847 2.301 4.182 3.137 2.091 67% 11% In Progress New Initiatives through out Punjab Schemes Upgradation / Strengthening of Existing On-going 718 2321 Punjab 390.000 93.500 50.000 37.500 20.754 55% 29% In Progress Laboratories at District Head Quarter Schemes Multi Sectoral Nutrition Strategy for WASH On-going 719 2322 Including Water Supply, Sanitation, Hygiene, Punjab 1,013.037 100.000 166.667 125.000 75.524 60% 17% Work in Progress Schemes Waste Water Rehabilitation of 781 dysfunctional Rural Water On-going 720 2323 Punjab 9,015.746 0.480 333.333 206.667 0.000 0% 0% Work in Progress Supply Schemes Schemes Combined PC-II of Water Quality Survey, Identification of outlived pipes, outsourcing of On-going 721 2324 water Supply schemes, Rationalization of staff in Punjab 327.683 30.600 33.333 25.000 16.667 67% 14% In Progress Schemes WASAs, MC & PHED and pre qualification of contractors and manufacturers

Rehabilitation of need based (identified through On-going 722 2325 Punjab 1,146.048 707.664 66.667 50.000 14.816 30% 63% In Progress TPV) Dysfunctional Rural water Supply Schemes Schemes Scaling up Approach for Total Sanitation On-going 723 2326 Punjab 399.705 287.317 16.667 12.500 7.500 60% 74% In Progress (PATS) in Punjab (ODF) Schemes AA issued on 05.08.2017. Funds released on Construction of PCC in Different Streets in UC -77 On-going 724 2327 Faisalabad 5.000 3.808 1.192 0.894 0.650 73% 89% 23.11.2017. Work order issued on 13.12.2017. District Faisalabad Schemes Work is in progress.Funds released on 23.11.2018 & 24.1.19 Construction of Gallian Nallian PCC Soling and On-going 725 2328 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Dheer Bain Schemes Construction of Gallian Nallian PCC Soling and On-going 726 2329 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Kotli Nawab Schemes Construction of Gallian Nallian PCC Soling and On-going 727 2330 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Wando Schemes Construction of Gallian Nallian PCC Soling and On-going 728 2331 Gujranwala 10.000 4.807 1.667 0.416 0.000 0% 48% Scheme completed. Tuff Tile in UC Kali Suba Schemes Construction of Gallian Nallian PCC Soling and On-going 729 2332 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Sohawa Dhalwan Schemes Construction of Gallian Nallian PCC Soling and On-going 730 2333 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Nangal Dona Singh Schemes Construction of Gallian Nallian PCC Soling and On-going 731 2334 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Gona Osar Schemes Construction of Streets and Drainage at Ward No.1 On-going 732 2335 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed. District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 733 2336 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed. No.2, District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 734 2337 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed. No.3, District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 735 2338 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed. No.4, District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 736 2339 Gujranwala 5.650 3.150 0.833 0.208 0.000 0% 56% Scheme completed. No.5, District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 737 2340 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed No.6, District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 738 2341 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed. No.7, District Gujranwala Schemes Construction of Streets and Drainage at Ward On-going 739 2342 Gujranwala 5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed. No.8, District Gujranwala Schemes Provision of PCC / Sewerage / Drainage / Soling On-going 740 2343 etc. in Village Jajoki, Teshil Nowsehra Virkan, Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Schemes District Gujranwala Rehabilitatin Improvement of Streets in Village Pir On-going 741 2344 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Kot Tehsil Wazirabad, District Gujrnawala Schemes Construction of PCC, Sewerage/Drains at UC 63 On-going 742 2345 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. District Gujranwala Schemes Construction of Gallian Nallian PCC Soling and On-going 743 2346 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Nadala Sindhowan Schemes Construction of Gallian Nallian PCC Soling and On-going 744 2347 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Mandiala Tabsa Schemes Construction of Gallian Nallian PCC Soling and On-going 745 2348 Gujranwala 10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed. Tuff Tile in UC Chak Ram Daas Schemes Construction of PCC Tuff Tile & Draiange at On-going 746 2349 Railway Road, Salamat Pura, Kamoki, District Gujranwala 6.755 3.930 0.942 0.236 0.000 0% 58% Scheme completed. Schemes Gujranwala Construction of PCC & Drainage at Street Nos.13,14,15,16,17 and St. Masjid-E-Shuhda, Ahl- On-going 747 2350 Gujranwala 40.000 10.000 1.126 0.282 0.000 0% 25% Scheme completed. E-Hadith, Tibba Muhammad Nagar, Kamoki, Schemes District Gujranwala Installation of Water Filteration Plant at Village On-going Filtration Plant already installed in village Class 748 2351 Lahore 5.350 2.833 0.839 0.229 0.020 9% 53% Mari during F.Y 2017-18, this is duplicate scheme, Class Marri Lahore. Schemes required to be deleted for ADP. Filtration Plant already installed in village Gallian Installation of Water Filteration Plant at Village On-going 749 2352 Lahore 5.350 0.886 1.488 0.416 0.044 11% 17% Khuda Bakhsh under IPOR Package NA-130 during Gallian Khuda Bakhsh Lahore. Schemes F.Y 2017-18, this is duplicate scheme, required to be deleted for ADP. Due to change in political scenario, conflict with On-going 750 2353 Installation of filteration Plant Naseebabad Lahore 5.350 0.950 1.466 0.400 0.033 8% 18% community, site is not available for installation of Schemes filtration plant, scheme need to be dropped from ADP. Construction of PCC, Soling, Drain and Nallah in Chak No. 11, 8, 7, 6, 18, 16, 15, 14 GB and Chak On-going 751 2354 Nankana Sahib 30.000 15.000 3.333 1.700 0.867 51% 53% Work is in progress. No 01 (Khoti Wala) Nizam Pura District Schemes nankanasahib 1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Dera Dogran Bhutta Colony Rukn On-going of Tender: 04-01-2018 6. Date of Award: 10-02- 752 2355 Lodhran 39.263 9.986 9.754 7.316 5.300 72% 39% 2018 7. Date of Completion as per PC-I: 28-02-2018 Deen Pur, District Lodhran Schemes 8. Anticipated Date of Completion: 08-02-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 3821 Persons. Work is in Progress

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Scheme Kotli Wajjwah, District On-going of Tender: 04-01-2018 6. Date of Award: 07-02- 753 2356 Lodhran 37.175 9.977 9.058 6.794 5.200 77% 41% 2018 7. Date of Completion as per PC-I : 28-02- Lodhran Schemes 2018 8. Anticipated Date of Completion: 04-02-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 5367 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Scheme Haifzaabad Dunyapur On-going of Tender: 04-01-2018 6. Date of Award: 06-02- 754 2357 Gharbi Remainig Portion Dunyapur Sharqi, District Lodhran 49.805 9.900 13.268 14.322 8.953 63% 38% 2018 7. Date of Completion as per PC-I: 28-02-2018 Schemes Lodhran 8. Anticipated Date of Completion: 04-02-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 4731 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Scheme in Chak No.359/Wb District On-going of Tender: 04-01-2018 6. Date of Award: 06-02- 755 2358 Lodhran 19.309 9.896 3.103 2.327 1.850 80% 61% 2018 7. Date of Completion as per PC-I: 28-02-2018 Lodhran Schemes 8. Anticipated Date of Completion: 04-02-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 4235 Persons. Work is in Progress 1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Scheme in Chak No.358/Wb District On-going of Tender: 04-01-2018 6. Date of Award: 10-02- 756 2359 Lodhran 26.334 9.992 5.445 4.084 3.100 76% 50% 2018 7. Date of Completion as per PC-I: 28-02-2018 Lodhran Schemes 8. Anticipated Date of Completion: 08-02-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 4881 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Scheme in Chak No.311/Wb District On-going of Tender: 04-01-2018 6. Date of Award: 30-03- 757 2360 Lodhran 36.605 9.855 8.868 6.651 5.150 77% 41% 2018 7. Date of Completion as per PC- I: 28-02- Lodhran Schemes 2018 8. Anticipated Date of Completion: 28-03-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 2996 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12- 2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt Water Supply Scheme in Chak No.13/M District On-going of Tender: 04-01-2018 6. Date of Award: 10-02- 758 2361 Lodhran 28.934 9.927 6.311 4.733 3.650 77% 47% 2018 7. Date of Completion as per PC-I: 28-02-2018 Lodhran Schemes 8. Anticipated Date of Completion: 08-02-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 1934 Persons. Work is in Progress. Construction of Nali Soling Tuff Tile & Culverts UC Dera Ghazi On-going 759 2362 7.000 2.000 1.000 0.750 0.548 73% 36% "• Date of A.A = 13.1.17 Shero Dasti Dg Khan Khan Schemes Construction of Nali Soling Tuff Tiles On The West Dera Ghazi On-going 760 2363 of Mana Ahmadani Town Ship + Basti Budhan Dg 10.000 2.000 1.000 0.750 0.000 0% 20% "• Date of A.A = 13.1.17 Khan Schemes Khan Rehabilitation of Water Supply in Fareed Abad PP- Dera Ghazi On-going 761 2364 10.000 7.000 1.000 0.750 0.548 73% 75% "• Date of A.A = 25.7.2017 244 District Dg Khan Khan Schemes Rehabilitation of Water Supply in Gharib Abad PP- Dera Ghazi On-going 762 2365 10.000 5.000 1.000 0.750 0.555 74% 56% "• Date of A.A = 25.7.2017 244 District Dg Khan Khan Schemes Rehabilitation of 10 Rural Water Supply Schemes On-going 763 2366 Rawalpindi 34.830 9.787 3.333 2.500 1.667 67% 33% Work in Progress. Tehsil Murree & Kotli Sattian, District Rawalpindi Schemes Const. of 02 Nos. Filtration Plants in each Ward of Chaklala Cantt Ward No.5 to 10& Const. of 0.2 MG On-going 764 2367 Rawalpindi 50.000 19.500 4.667 3.500 2.334 67% 44% Work in Progress. capacity UGT at Sarwar Park LalKurti, District Schemes Rawalpindi Const. of Bridge / Drain at Rawal Town, Tench Road/Adra Bridge/ Kacha Stop under Railway On-going 765 2368 Rawalpindi 50.000 20.000 6.667 9.000 7.334 81% 55% Work in Progress. Track/Aliabad/Dk. Banaras/ Ahmadabad, District Schemes Rawalpindi Const. of Road / Sewerage at each Ward No.1 to On-going 766 2369 10 of Rawalpindi Cantt and Ward No.5 to 10 & Rawalpindi 50.000 20.909 6.667 7.500 5.834 78% 53% Work in Progress. Schemes Minority Member, District Rawalpindi Construction of streets in UCs PP-03 including On-going 767 2370 Rawalpindi 150.000 35.897 6.667 9.329 7.663 82% 29% Work in Progress. Gujar Khan City, District Rawalpindi Schemes Laying of 4’’ Dia Water Supply Pipe Line Ward On-going 768 2371 No,1 to Ward No,10 Rawalpindi Cantonment Rawalpindi 40.000 10.000 10.000 7.500 5.000 67% 38% Work in Progress. Schemes Board ., District Rawalpindi Const. of 02 Nos. Filtration Plants in each Ward of Rawalpindi Cantt Ward No.1 to 10 and Const. of On-going 769 2372 Rawalpindi 50.000 20.000 10.000 7.500 5.000 67% 50% Work in Progress. 0.2 MG capacity UGT at Dk. Gujran Ward No.10, Schemes District Rawalpindi Construction of Under Ground Water Tank On-going Only payment of WAPDA Demand Notice pending 770 2373 Rawalpindi 25.000 21.156 1.114 0.836 0.557 67% 87% which will be paid after issuance of Demand Notice Rawalpindi Cantonment Board, District Rawalpindi Schemes by WAPDA. Water Supply Scheme at Dhala, District On-going 771 2374 Rawalpindi 10.200 5.000 1.733 1.300 0.867 67% 58% Work is in progress. Rawalpindi Schemes Construction of PCC link road Wasla to Dhoke On-going 772 2375 Bhattian, length=2.00 Km UC Sui Chemian, Tehsil Rawalpindi 12.815 5.000 2.605 0.651 0.000 0% 39% Work is in progress. Schemes Gujar Khan, District Rawalpindi Construction of PCC link road Sattal to Sabah Sher On-going 773 2376 and Dhoke Phugoo, length=2.00 Km, Tehsil Gujar Rawalpindi 12.881 5.000 2.627 0.656 0.000 0% 39% Work is in progress. Schemes Khan, District Rawalpindi Construction of PCC road Dhoke Khumbail, Phase- On-going 774 2377 I, length=1.5 Km, UC Sui Chemian, Tehsil Gujar Rawalpindi 10.569 5.000 1.856 0.464 0.000 0% 47% Work is in progress. Schemes Khan, District Rawalpindi Constt. Of PCC link Road Mohri Barsal uc Jero On-going 775 2378 Rawalpindi 14.000 8.969 1.677 1.258 0.839 67% 70% Work is in progress. Ratial., District Rawalpindi Schemes Constt. Of PCC link Road Paka Khanpur UC On-going 776 2379 Rawalpindi 14.000 4.917 3.000 0.750 0.000 0% 35% Work is in progress. Bhadana., District Rawalpindi Schemes Constt. Of PCC link Road Dhoke Rajgan UC On-going 777 2380 Rawalpindi 12.000 5.000 2.333 1.750 1.167 67% 51% Work is in progress. Qazian., District Rawalpindi Schemes Constt. Of PCC link Road Dhoke fateh Paharian On-going 778 2381 Rawalpindi 11.000 4.500 2.000 1.500 1.000 67% 50% Work is in progress. UC Qazian., District Rawalpindi Schemes Constt. Of PCC link Road Dhoke Channi Dakhali On-going 779 2382 Sohawa Mirzian, Islam Pura Jabbar / Bewal., Rawalpindi 11.000 5.000 2.000 1.500 1.000 67% 55% Work is in progress. Schemes District Rawalpindi Construction of PCC link road Jhawan to Kountrila On-going 780 2383 UC Kountrila, length=1.70 Km, Tehsil Gujar Khan, Rawalpindi 10.530 4.773 1.843 0.460 0.000 0% 45% Work is in progress. Schemes District Rawalpindi Construction of PCC link road Kanyal to Dhoke On-going 781 2384 Jeaven, length=1.70 Km UC Mohra Noori, Tehsil Rawalpindi 10.170 4.995 1.723 0.430 0.000 0% 49% Work is in progress. Schemes Gujar Khan, District Rawalpindi Drainage scheme at Noorpur and Lundi, Tehsil On-going A.A Date 02.08.2017. T.S Date 13.09.2017.Date of 782 2385 Attock 26.139 9.977 5.380 1.535 1.090 71% 42% Start of Scheme 29.01.2018.Date of Completion of Hazro, District Attock Schemes Scheme 30.06.19.Work is in progress.

Drainage scheme at Khudlathi and Sarwana, On-going A.A Date 02.08.2017.T.S Date 13.09.2017.Date of 783 2386 Attock 28.306 9.977 6.102 4.577 3.051 67% 46% Start of Scheme 07.12.2017.Date of Completion of Tehsil Hazro, District Attock Schemes Scheme 30.06.19.Work is in progress.

Drainage scheme at Musa and Sherani, Tehsil On-going A.A Date 02.08.2017.T.S Date 13.09.2017.Date of 784 2387 Attock 26.931 14.976 3.977 2.983 1.989 67% 63% Start of Scheme 27.11.2017.Date of Completion of Hazro, District Attock Schemes Scheme30.06.19.Work is in progress.

Rural drainage scheme in village Shakardara On-going A.A Date 02.08.2017. T.S Date 13.09.2017.Date of 785 2388 Attock 32.394 9.980 3.333 2.500 1.667 67% 36% Start of Scheme 09.12.2017.Date of Completion of Phase-II, District Attock Schemes Scheme 30.06.2019.Work is in progress.

Rural draiange scheme in village Ghourgushti On-going A.A Date 02.08.2017. T.S Date 13.09.2017.Date of 786 2389 Attock 19.313 9.914 3.104 2.328 1.552 67% 59% Start of Scheme 09.12.2017.Date of Completion of Phase-II, Tehsil Hazro, District Attock Schemes Scheme 30.06.2019.Work is in progress. Construction of PCC road from Kohat road On-going A.A Date 02.08.2017. T.S Date 13.09.2017.Date of 787 2390 Bhandar to Dhok Sanakhi UC Langar Tehsil Jand Attock 28.500 9.979 6.167 4.625 3.084 67% 46% Start of Scheme 06.12.2017.Date of Completion of Schemes District Attock Scheme 30.06.19.Work is in progress. Water Supply scheme of village Ferozwali UC On-going A.A Date 02.08.2017. T.S Date 13.09.2017.Date of 788 2391 Attock 22.500 7.961 4.833 3.625 2.417 67% 46% Start of Scheme 10.01.2018.Date of Completion of Gareebwal Tehsil Pindigheb District Attock Schemes Scheme 30.06.2019.Work is in progress.

Drainage / sewerage scheme in village Painda, On-going A.A Date 16.09.2017.T.S Date 11.10.2017.Date of 789 2392 Attock 61.838 25.999 3.333 2.500 1.667 67% 45% Start of Scheme 06.11.2017.Date of Completion of Daman, Jalalia, District Attock Schemes Scheme 30.06.2019.Dwork is in progress.

Drainage / sewerage scheme in village Shadi Khan On-going A.A Date 16.09.2017.T.S Date 10.10.2017. Date of 790 2393 Attock 54.788 19.972 3.333 3.500 2.667 76% 41% Start of Scheme 09.12.2017.Date of Completion of Phase-II, District Attock Schemes Scheme 30.06.2019.Work is in progress.

Drainage / Sewerage System in village Barazai, On-going A.A Date 16.09.2017.T.S Date 10.10.2017. Date of 791 2394 Attock 15.450 9.346 1.817 1.363 0.909 67% 66% Start of Scheme 09.12.2017.Date of Completion of Tehsil Hazro, District Attock Schemes Scheme 30.06.2019.Work is in progress. Rural drainage scheme and water supply On-going Date of A.A 31.07.2017. Date of T.S 08.08.2017 792 2395 Chakwal 18.000 10.000 2.667 2.600 1.934 74% 66% .Date of Start 18.10.2017.Date of completion Oudherwal and Mohallah Islam Pura Chakwal Schemes 30.06.2019.Work is in progress. Date of A.A 31.07.2017.Date of T.S Rural drainage scheme and Water Supply in UC On-going 793 2396 Chakwal 24.000 10.000 4.667 5.031 3.865 77% 58% 08.08.2017.Date of Start 18.10.2017.Date of Dub, District Chakwal Schemes completion 30.06.2019.Full funds utilized. Scheme is short funded. Urban sewerage and drainage scheme in Chakwal On-going 794 2397 Chakwal 30.000 10.000 3.333 2.500 1.667 67% 39% "Date of A.A 31.07.2017.Date of T.S City, Ward No.1 to Ward No.12, District Chakwal Schemes 08.08.2017.Date of Start 19.10.2017

Date of A.A 31.07.2017. Date of T.S Urban Drainage & Sewerage scheme of Chakwal 08.08.2017.Date of Start 19.10.2017 .Date.of On-going 795 2398 City from Ward No.13 to Ward No.23, District Chakwal 30.000 16.000 4.667 11.900 10.732 90% 89% fcompletion.30.06.2019.Allocated funds were Schemes utilized. utilized. Additional funds Rs.8.4 M provided Chakwal through .reappropriation in Dec.2018 and will be consumed during next month. Urban Drainage & Sewerage scheme of Chakwal Date of A.A 31.07.2017. Date of T.S 08.08.2017. On-going 796 2399 City from Ward No.28 to Ward No.37, District Chakwal 30.000 9.970 3.333 2.500 1.667 67% 39% Date of Start 19.10.2017.Date of completion Schemes 30.06.2020.Full funds utilized. Scheme is short Chakwal funded. Date of A.A 31.07.2017. Date of T.S 08.08.2017.Date of Start 23.10.2017.Date of Rural drainage scheme and retaining wall and On-going 797 2400 Chakwal 27.000 13.000 4.667 7.000 5.834 83% 70% completion 30.06.2019.Allocated funds were Cause Way in MC Bhaun, District Chakwal Schemes utilized. utilized. Additional funds Rs.3.5 M provided through reappropriation in Dec.2018 and will be consumed during next month. Date of A.A 31.07.2017. Date of T.S Rural Drainage Scheme and Retaining wall and On-going 798 2401 Chakwal 25.000 13.999 3.667 2.750 1.834 67% 63% 08.08.2017.Date of Start 25.10.2017.Date of Cause way in UC Mureed, District Chakwal Schemes completion 30.06.2019.Full funds utilized. Scheme is short funded. Date of A.A 31.07.2017.Date of T.S Rural Drainage Scheme and Retaining wall and On-going 799 2402 Chakwal 20.000 9.997 3.333 2.500 1.667 67% 58% 08.08.2017.Date of Start 26.10.2017.Date of Cause way in UC Jand Awan, District Chakwal Schemes completion 30.06.2019.Full funds utilized. Scheme is short funded. Rural drainage and water supply village Tatral, On-going Date of A.A 31.07.2017. Date of T.S 800 2403 Chakwal 20.000 10.000 3.333 0.969 0.136 14% 51% 08.08.2017.Date of Start 26.10.2017 ..Date of District Chakwal Schemes completion 30.06.2019.Work is in progress. Date of A.A 31.07.2017. Date of T.S Rural Drainage scheme and Retaining wall in UC On-going 801 2404 Chakwal 17.000 9.996 2.333 1.150 0.567 49% 62% 08.08.2017.Date of Start 26.10.2017.Date of Mulhal Mughllan, District Chakwal Schemes completion 30.06.2019.Full funds utilized. Scheme is short funded. Date of A.A 31.07.2017 .Date of T.S 08.08.2017.Date of Start 26.10.2017 .Date of Rural draiange scheme & Retaining wall and On-going 802 2405 Chakwal 13.000 8.000 1.667 3.750 3.333 89% 87% completion 30.06.2019.Allocated funds were causeway in UC Chak Umara, District Chakwal Schemes utilized. utilized. Additional funds Rs.8.4 M provided through reappropriationin in Dec.2018 and will be consumed during next month. Rural drainage scheme UC -Jaswal, Tehsil & On-going Date of A.A 31.07.2017 .Date of T.S 08.08.2017. 803 2406 Chakwal 20.000 9.997 3.333 1.900 1.067 56% 55% Date of Start 26.10.2017 .Date of completion District Chakwal Schemes 30.06.2019.Work is in progress. Rural drainage scheme Nichandi & , Tehsil On-going "Date of A.A 31.07.2017 .Date of T.S 08.08.2017 804 2407 Chakwal 20.000 10.000 3.333 2.500 1.667 67% 58% & District Chakwal Schemes .Date of Start 27.10.2017 Date of A.A 09.08.2017. Date of T.S 02.10.2017 Construction of PCC, Streets, Drain & Water On-going 805 2408 Chakwal 147.248 29.998 3.333 2.500 1.667 67% 22% .Date of Start 17.11.2017 .Date of completion Supply at Talagang, District Chakwal Schemes 30.06.2020.Full funds utilized. Scheme is short funded. Date of A.A 09.08.2017.Date of T.S 08.08.2017 Construction of PCC, Streets, Drain & Water On-going 806 2409 Chakwal 98.166 24.920 3.333 2.500 1.667 67% 27% .Date of Start 21.11.2017 . Date of completion Supply at Tehsil Lawa PP-23, District Chakwal Schemes 30.06.2020.Full funds utilized. Scheme is short funded. Restoration / Flood Rains Damages vented causeway on Dhermond to Dk. Fateh Shah Road, On-going Date of A.A 31.07.2017.Date of T.S 807 2410 Chakwal 14.239 10.000 1.413 1.060 0.707 67% 75% 08.08.2017.Date of Start 27.10.2017.Date of Vented causeway Darot & street / drains village Schemes completion 30.06.2019.Scheme completed. Wanhar, Tehsil Talagang, District Chakwal

Provision of sewerage at Ward No.36 Tehsil & On-going A.A Date 27-07-2017.T.S Date 09-08-2017.Date of 808 2411 Jhelum 15.000 4.480 2.333 1.750 1.167 67% 38% District Jhelum, District Jehlum Schemes Work Award 09-09-2017.Work in progress Provision of Sewerage system at UC Kotla Faqeer, On-going A.A Date 27-07-2017.T.S date 09-08-2017.Date of 809 2412 Jhelum 30.000 10.000 3.333 9.185 4.445 48% 48% Tehsil & District Jhelum Schemes Work Award 09-09-2017.Work in progress Provision of Water Supply at Pind Sawika, Tehsil & On-going A.A Date 27-07-2017.T.S date 09-08-2017.Date of 810 2413 Jhelum 15.000 7.988 2.333 1.750 1.167 67% 61% District Jhelum Schemes Work Award 16-09-2017.Work in progress Provision of Water supply at village Kundal, District On-going A.A Date 27-07-2017.T.S date 09-08-2017.Date of 811 2414 Jhelum 21.747 9.941 3.916 2.937 1.958 67% 55% Jhelum Schemes Work Award 13-09-2017.Work in progress Water supply scheme at Chak No.165 Shumali, On-going 812 2415 Sargodha 10.673 4.947 1.891 1.418 1.411 100% 60% Work in progress. Sillanwali, District Sargodha Schemes Construction of road Drain / Soling / Re-Soling / On-going 813 2416 PCC / Tuff Pavers / Sullage Carrier in Chak No Sargodha 20.000 9.979 3.333 2.500 1.899 76% 59% Work in progress. Schemes 45/SB Tehsil and District Sargodha

Construction of road Drain / Soling / Re-Soling / On-going 814 2417 PCC / Tuff Pavers / Sullage Carrier in Chak No Sargodha 20.000 9.977 3.333 2.500 2.226 89% 61% Work in progress. Schemes 46/Sb tehsil and District Sargodha

Construction of road Drain / Soling / Re-Soling / On-going 815 2418 PCC / Tuff Pavers / Sullage Carrier in Chak No Sargodha 20.003 9.920 3.334 2.501 2.120 85% 60% Work in progress. Schemes 107/Sb Tehsil and District Sargodha

Construction of road Drain / Soling / Re-Soling / On-going 816 2419 PCC / Tuff Pavers / Sullage Carrier in Chak No Sargodha 10.004 6.036 1.323 0.993 0.993 100% 70% Work in progress. Schemes 85/NB tehsil and District Sargodha

Construction of road Drain / Soling / Re-Soling / On-going 817 2420 PCC / Tuff Pavers / Sullage Carrier in Chak No Sargodha 10.008 4.972 1.669 1.252 1.009 81% 60% Work in progress. Schemes 84/NB Tehsil and District Sargodha Water supply scheme at Chak No.129 Janobi, On-going 818 2421 Sargodha 23.594 7.000 4.531 3.398 3.364 99% 44% Work in progress. Sillanwali, District Sargodha Schemes Water supply scheme at Chak No.119 Janobi, On-going 819 2422 Sargodha 17.002 10.000 2.334 1.751 1.671 95% 69% Work in progress. Sillanwali, District Sargodha Schemes Water supply scheme at Chak No.111/107 On-going 820 2423 Sargodha 17.193 10.000 2.398 1.799 1.624 90% 68% Work in progress. Shumali, Sillanwali, District Sargodha Schemes Water supply scheme at Chak No.140 Janobi, On-going 821 2424 Sargodha 12.961 5.997 2.320 1.740 1.353 78% 57% Work in progress. Sillanwali, District Sargodha Schemes Construction of Drain / PCC / Soling / Sullage On-going 822 2425 Carrier at Midh Pergana Islam Pure More, Tehsil Sargodha 16.130 10.000 2.043 1.532 1.204 79% 69% Work in progress. Schemes Bhera. District Sargodha Construction of PCC / Soling / Sewerage / Nullah On-going 823 2426 Dera Abdul Sattar jhamat Chak No. 19 Shumali L= Sargodha 20.000 9.972 3.333 2.500 1.889 76% 59% Work in progress. Schemes 2800 Feet, District Sargodha Construction of PCC / Soling / Sewerage / Chabar Balooka Dera Mehar Muhammad Akhtar Lak and On-going 824 2427 Sargodha 20.000 10.000 3.333 2.500 1.947 78% 60% Work in progress. PCC / Soling Mehar Qadir Yat Lak, UC Sakisar Schemes Baar, District Sargodha Constructio of Soling / Sewerage / PCC, Dera Jaat via Mehar Shahid Akram Lak, Ghulam Ahmed On-going 825 2428 Sargodha 20.000 10.000 3.333 2.500 2.026 81% 60% Work in progress. Kamrana, Ahmed Yaar Gondal, Haji Muhammad Schemes Sher, UC Mardi Lak, District Sargodha

Construction of Soling / PCC / Nullah / Dera Mahar Nasar Hayat Lak and Soling Lak More to Bonga On-going 826 2429 Minhas Colony, Dera Jaat Mahar Muhammad Sargodha 20.000 10.000 3.333 2.500 1.901 76% 60% Work in progress. Schemes Bakhsh Lak, Mahar Abdul Rehamn Lak, Salah Muhammad Sipra, UC Lak More, District Sargodha Construction of Soling / PCC / UC Chak No. 58 On-going 827 2430 Sargodha 20.000 9.978 3.333 2.500 1.977 79% 60% Work in progress. Shumali, District Sargodha Schemes Construciton of Soling Dera Jaat Badle Wala and On-going 828 2431 PCC / Sewerage and repair of road Chak No. 53 Sargodha 20.000 10.000 3.333 2.500 1.898 76% 59% Work in progress. Schemes Shumali, District Sargodha Rural Drainage scheme for Chak No 9/SB, District On-going 829 2432 Sargodha 29.294 11.100 3.333 2.500 2.241 90% 46% Work in progress. Sargodha Schemes Rural Drainage scheme for Chak No.18/SB & On-going 830 2433 Sargodha 25.885 13.609 3.333 2.500 1.967 79% 60% Work in progress. Colonies, District Sargodha Schemes Rural Drainage scheme Chak No.2/NB, District On-going 831 2434 Sargodha 30.261 9.966 3.333 2.500 2.352 94% 41% Work in progress. Sargodha Schemes On-going 832 2435 Rural Drainage Scheme Abdal, District Sargodha Sargodha 25.667 10.885 3.333 2.500 1.923 77% 50% Work in progress. Schemes Construciton of Drainage / Soling, Adjoining On-going 833 2436 Abadies of Mouza Ahmaday wala, District Sargodha 15.000 5.000 3.333 2.500 2.069 83% 47% Work in progress. Schemes Sargodha Rural drainage scheme UC No.64, Dharema, On-going 834 2437 Sargodha 19.991 8.500 3.330 2.498 1.891 76% 52% Work in progress. Sargodha, District Sargodha Schemes Rural drainage scheme UC No.77, Hyderabaad On-going 835 2438 Sargodha 19.927 9.995 3.309 2.482 1.916 77% 60% Work in progress. Town, District Sargodha Schemes Rural drainage scheme UC No.76, Chak On-going 836 2439 Sargodha 19.955 10.000 3.318 2.489 2.033 82% 60% Work in progress. No.71/NB, District Sargodha Schemes Rural drainage scheme UC No.74, Chak On-going 837 2440 Sargodha 19.987 10.000 3.329 2.497 1.978 79% 60% Work in progress. No.79/NB, District Sargodha Schemes Drainage scheme at Chak No.132/136, Janobi, On-going 838 2441 Sargodha 29.657 11.993 3.333 2.500 2.139 86% 48% Work in progress. Sillanwali, District Sargodha Schemes Drainage scheme at Chak No.125/129 Shumali, On-going 839 2442 Sargodha 32.611 10.000 3.333 2.500 2.500 100% 38% Work in progress. Sillanwali, District Sargodha Schemes Drainage scheme at Chak No.128/130 Janobi, On-going 840 2443 Sargodha 33.563 12.999 3.333 2.500 2.252 90% 45% Work in progress. Sillanwali, District Sargodha Schemes Construction of road Drain / Soling / Re-Soling / On-going 841 2444 PCC / Tuff Pavers / Sullage Carrier in Chak No 23- Sargodha 15.000 10.000 1.667 1.251 1.211 97% 75% Work in progress. Schemes ASB Tehsil and District Sargodha.

Construction of road Drain / Soling / Re-Soling / On-going 842 2445 PCC / Tuff Pavers / Sullage Carrier in Chak No Sargodha 15.002 10.000 1.667 1.251 0.963 77% 73% Work in progress. Schemes 73/SB Tehsil and District Sargodha Urban Sewerage & Drainage Scheme in M.C-04 On-going 843 2446 Sargodha 50.000 19.981 3.333 2.500 2.500 100% 45% Work in progress. Sargodha City. Schemes Urban Sewerage & Drainage Scheme in M.C-19 On-going 844 2447 Sargodha 40.000 19.788 3.333 2.500 2.104 84% 55% Work in progress. Sargodha City. Schemes Urban Sewerage & Drainage Scheme in On-going 845 2448 Sargodha 50.000 20.675 3.333 2.500 2.500 100% 46% Work in progress. Cantonment Ward No. 01 to 05 Sargodha City. Schemes

Urban Sewerage & Drainage Scheme in On-going 846 2449 Sargodha 50.000 21.099 3.333 2.500 2.500 100% 47% Work in progress. Cantonment Ward No. 06 to 10 Sargodha City. Schemes

Urban Sewerage & Drainage Scheme / Water On-going 847 2450 Supply Pipeline including Disposal Station Gillwala Sargodha 50.000 19.917 3.333 2.500 1.973 79% 44% Work in progress. Schemes and Tiwana Park Sargodha City.

Urban Sewerage & Drainage Scheme / Water Supply Pipeline including Disposal Station M.C No. On-going 848 2451 Sargodha 50.000 22.600 3.333 2.500 1.888 76% 49% Work in progress. 07 Street No. 01, 02, 03, 04 & 05 to Rehman Pura Schemes Chowk via Pistool Marka Gali Sargodha City.

Urban Sewerage & Drainage Scheme / Water On-going 849 2452 Sargodha 40.000 20.000 3.333 2.500 2.500 100% 56% Work in progress. Supply Pipeline in M.C No. 08 Sargodha City. Schemes

Urban Sewerage & Drainage Scheme / Water On-going 850 2453 Supply Pipeline including Renovation of Disposal Sargodha 45.000 19.996 3.333 2.500 2.500 100% 50% Work in progress. Schemes Station Eid Gah M.C No. 09 Sargodha City. Urban Sewerage & Drainage Scheme / Water On-going 851 2454 Supply Pipeline M.C No. 11 & M.C No. 13 Sargodha 50.000 21.260 3.333 2.500 2.030 81% 47% Work in progress. Schemes Sargodha City Urban Sewerage & Drainage Scheme / Water Supply Pipeline including Disposal Station Iqbal On-going 852 2455 Sargodha 50.000 13.000 3.333 2.500 2.500 100% 31% Work in progress. Colony and at Girls Degree College to Block No. Schemes 16 Sargodha City Urban Sewerage & Drainage Scheme / Water Supply Pipeline Madina Town, New Madina Town, On-going 853 2456 Sargodha 50.000 20.309 3.333 2.500 2.500 100% 46% Work in progress. Muhammadi Colony including Disposal Station and Schemes Main Water Works Chowk / Road Sargodha City. Urban Sewerage & Drainage Scheme / Water On-going 854 2457 Supply Pipeline M.C No. 22 with Road Election Sargodha 50.000 21.488 3.333 2.500 2.500 100% 48% Work in progress. Schemes Commission Sargodha City. Urban Sewerage & Drainage Scheme / Water On-going 855 2458 Supply Pipeline M.C No. 20 M.C No. 21 Sargodha Sargodha 40.000 19.969 3.333 2.500 2.142 86% 55% Work in progress. Schemes City. Urban Sewerage & Drainage Scheme / Water Supply Pipeline Hameed Town, Society Colony On-going 856 2459 Sargodha 45.000 19.994 3.333 2.500 2.168 87% 49% Work in progress. including Renovation of Main Disposal Works Schemes Sillanwali Road Sargodha City. Urban Sewerage & Drainage Scheme in M.C-01 On-going 857 2460 Sargodha 50.000 24.739 3.333 2.500 1.897 76% 53% Work in progress. Sargodha City. Schemes Urban Sewerage & Drainage Scheme in M.C-02 On-going 858 2461 Sargodha 30.000 14.684 3.333 2.500 1.932 77% 55% Work in progress. Sargodha City. Schemes Urban Sewerage & Drainage Scheme in M.C-03 On-going 859 2462 Sargodha 30.000 9.580 3.333 2.500 1.901 76% 38% Work in progress. Sargodha City. Schemes Rehabilitation water supply scheme Bhera Town, On-going 860 2463 Sargodha 80.000 33.978 3.333 4.472 4.472 100% 48% Work in progress. District SargodhaPhase-I Schemes Urban Water Supply Scheme Distribution System Factory Area, Essa Nagar, Istaqlalabad, Hameed On-going 861 2464 Town, Corporation Town, Society Colony and Sargodha 30.000 14.911 3.333 2.500 1.986 79% 56% Work in progress. Schemes Nallah including Slab Karkhana Bazar Sargodha City. Additional Water Supply pipeline in Cheema Colony, Kalyar Town, Rehmat Park, Pir On-going 862 2465 Sargodha 30.000 15.000 3.333 2.500 1.893 76% 56% Work in progress. Muhammad Colony & Adjoining Colonies Schemes Sargodha City. Rehabilitation of Water Supply Scheme New On-going 863 2466 Sargodha 50.000 20.000 3.333 2.500 2.003 80% 44% Work in progress. Satellite Town Sargodha City Schemes Providing / Fixing Ultra Filtration Plants U.F / R.O On-going 864 2467 Sargodha 40.000 25.000 3.333 2.500 1.899 76% 67% Work in progress. in Wards / M.Cs in PP-34 Sargodha City 10-No. Schemes Up-gradation of Disposal Works in New Satellite Town & Ghani Park and laying of Distribution On-going 865 2468 Sargodha 48.000 27.221 3.333 2.500 2.500 100% 62% Work in progress. System in New Satellite Town & adjoining abadies Schemes Sargodha City Water supply scheme at Sobaga, Sillanwali, On-going 866 2469 Sargodha 23.195 9.943 3.333 2.500 2.108 84% 52% Work in progress. District Sargodha Schemes Construction of PCC Tuff Tiles / Tuff Pever road Liaqat Shaheed road to Merydal School & Suger On-going 867 2470 Mil road to Lalazar Colony road & Merydal School Sargodha 20.000 10.000 3.333 2.500 2.500 100% 63% Work in progress. Schemes to Sail Nallah & Pathan Wala road, Street Masjid Wali, Bhalwal, District Sargodha Construciton of Sewerage Scheme, Tehsil On-going 868 2471 Sargodha 50.000 29.250 3.333 2.500 2.500 100% 64% Work in progress. Sahiwal, District Sargodha Schemes Construciton of Sewerage Scheme Farooqa, On-going 869 2472 Sargodha 50.000 20.000 3.333 2.500 1.991 80% 44% Work in progress. District Sargodha Schemes Construciton of Sewerage Scheme Vijh, Tehsil On-going 870 2473 Sargodha 30.000 8.200 3.333 2.500 1.894 76% 34% Work in progress. Sahiwal, District Sargodha Schemes Construciton of Sewerage Scheme Nehong, Tehsil On-going 871 2474 Sargodha 40.000 14.992 3.333 4.807 4.793 100% 49% Work in progress. Sahiwal, District Sargodha Schemes Date of AA 29.7.2017 Date of award 09.12.2017 Extension of Rural Water Supply Scheme, Malwal, On-going 872 2475 Khushab 24.530 9.979 4.843 3.632 3.630 100% 55% Date of completion 30.06.2019 Tube Well 1 No. District Khushab Schemes Pump House 1 No. Rising Main 9000/9000 Rft D/System 5700/7970 Rft Work is in progress. Date of AA 29.07.2017 Date of TS 5.9.2017 Date of Provision of 100 Hand Pumps at Mahar Area, On-going award 23.12.2017 Date of completion 30.06.2020 873 2476 Khushab 30.000 9.991 3.333 2.500 2.000 80% 40% District Khushab District Khushab Schemes Hand Pump 23/34 Nos. Bore with submersible pump 13/29 Nos. G.S Tank 500 Glns 5/29 Nos. Date of AA 29.07.2017 Date of TS 04.9.2017 Date Extension / Improvement of Water Supply Scheme, On-going of award 18.12.2017 Date of completion 30.06.2020 874 2477 Khushab 21.225 3.000 3.333 2.500 2.250 90% 25% Tube Well 1 No. Pump House 1 No. Pumping Kuradhi UC Uchhali, District Khushab Schemes Machinery 1 No. Rising Main 3240/28525 Rft Work is in progress. Rehabilitation / Improvement of Water Supply Date of AA 29.07.2017 Date of TS 15.8.2015 Date On-going 875 2478 Scheme, Fateh Pur Maira UC Gunjial Shumali, Khushab 12.400 5.595 2.133 1.600 1.440 90% 57% of award 08.01.2018 Date of completion 30.06.2019 Schemes Rising Main 9600/11500 Rft D/System 1800/2355 District Khushab Rft Work is in progress. Date of AA 29.07.2017 Date of TS 5.9.2017 Date of Rehabilitation of Water Supply Scheme, Warcha On-going award 23.12.2017 Date of completion 30.06.2020 876 2479 Khushab 25.000 9.999 3.333 2.500 2.250 90% 49% Tube Well 1 No. Pump House 1 No. Pumping UC Warcha, District Khushab Schemes Machinery 1 No. Rising Main 11880/17875 Rft D/System 0/1320 Rft Work is in progress. Date of AA 29.07.2017 Date of TS 5.9.2017 Date of Rehabilitation of Water Supply Scheme, Kufri UC On-going award 16.12.2017 Date of completion 30.06.2020 877 2480 Khushab 15.230 8.750 1.743 1.307 1.180 90% 65% Tube Well 1 No. Pump House 1 No. Pumping Kufri, District Khushab Schemes Machinery 1 No. Rising Main 12800/12807 Rft Work is in progress. Date of AA 29.07.2017 Date of TS 4.9.2017 Date of Construciton of Water Supply Scheme of Rehman On-going award 11.12.2017 Date of completion 30.06.2020 878 2481 Khushab 30.000 15.000 3.333 2.500 2.250 90% 58% Colony MC Hadhali, District Khushab Schemes Tube Well 6/6 Set. Pumping Machinery 6 Nos. Rising Main 50800/53196 Rft Work is in porgress.

Date of AA 29.07.2017 Date of TS 4.9.2017 Date of Construciton of Water Supply Scheme of Zaman On-going award 11.12.2017 Date of completion 30.06.2019 879 2482 Khushab 30.000 15.999 4.667 3.500 2.980 85% 63% Colony MC Hadhali, District Khushab Schemes Tube Well 6 Nos. Pumping Machinery 6/6 Set. Rising Main 49480/52184 Rft Work is in progress . Date of AA 16.10.2017 Date of TS 15.8.2015 Date Provision of sewerage scheme Roda, District On-going 880 2483 Khushab 100.000 23.486 3.333 2.500 1.870 75% 25% of award 04.01.2018 Date of completion 30.06.2020 Khushab Schemes RCC Sewer 0/1500 Rft. PCC Slab 28522/293128 Cft Work is in progress. Date of AA 29.07.2017 Date of TS 5.9.2017 Date of Provision of Drainage System in MC Mitha Tiwana, On-going award 08.12.2017 Date of completion 30.06.2020 881 2484 Khushab 49.900 14.997 3.333 2.500 1.875 75% 34% District Khushab Schemes PCC Slab 60101/89202 Cft Surface Drain 0/19550 Rft Sullage Carrier 0/10715 Rft Work is in progress.

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of Provision of Drainage System in MC QuaidaAbad, On-going award 08.12.2017 Date of completion 30.06.2020 882 2485 Khushab 49.831 16.993 3.333 2.500 1.880 75% 38% District Khushab Schemes RCC Sewer 5786/18305 Rft PCC Slab 40186/76862 Cft Surface Drain 0/3000 Rft work is in progrss .

Provision of Drainage System in UC Ukhli Mohla, On-going Date of AA 29.07.2017 Date of TS 05.09.2017 Date 883 2486 Khushab 18.025 9.998 2.675 2.006 1.500 75% 64% of award 09.12.2017 Date of completion 30.06.2019 District Khushab Schemes PCC Slab 27608/54740 Cft work is in progress. Date of AA 29.07.2017 Date of TS 04.09.2017 Date Construction of Drainage / Sewerage scheme, On-going of award 09.12.2017 Date of completion 30.06.2020 884 2487 Khushab 32.000 9.999 3.333 2.500 1.870 75% 37% RCC Sewer 7320/8700 Rft PCC Slab 17510/39304 Rehman Colony, MC Hadhali, District Khushab Schemes Cft Surface Drain 4401/6000 Rft Work is in progress. Date of AA 29.07.2017 Date of TS 04.09.2017 Date Construction of Drainage / Sewerage scheme, On-going of award 09.12.2017 Date of completion 30.06.2020 885 2488 Khushab 30.000 10.000 3.333 2.500 1.879 75% 40% PCC Slab 24015/27284 Cft Surface Drain 513/5000 Zaman Colony, MC Hadhali, District Khushab Schemes Rft Sullage Carrier 1800/15540 Rft Work is in progress. Date of AA 29.7.2017 Date of TS 05.09.2017 Date Construction of PCC Derajat, UC Uttra, District On-going 886 2489 Khushab 20.000 9.998 3.333 2.500 1.880 75% 59% of award 07.12.2017 Date of completion 30.06.2019 Khushab Schemes PCC Slab 46175/66532 Cft Surface Drain 0/1470 Rft Work is in progress . Date of AA 29.07.2017 Date of TS 05.09.2017 Date Construction of PCC Slab, UC Gunjial, District On-going of award 11.12.2017 Date of completion 30.06.2020 887 2490 Khushab 30.000 9.929 3.333 2.500 1.990 80% 40% Khushab Schemes RCC Sewer 0/860 Rft Surface Drain 0/5000 Rft PCC Slab 25515/63069 Cft Work is in progrss. Date of AA 29.7.2017 Date of TS 05.09.2018 Date Construction of PCC Slab, UC 14 MB, District On-going 888 2491 Khushab 20.000 10.000 3.333 2.500 2.020 81% 60% of award 11.12.2017 Date of completion 30.06.2019 Khushab Schemes PCC Slab 42293/66326 Cft Surface Drain 900/1600 Rft Work is in progress. Date of AA 11.08.2015 Date of TS 15.8.2015 Date Construction of Sewerage in, MC Mitha Twana, On-going of award 28.03.2018 Date of completion 30.06.2020 889 2492 Khushab 100.000 15.490 3.333 2.500 1.870 75% 17% PCC Slab 16620/78190 Cft Surface Drain District Khushab Schemes 2661/18230 Rft Sullage Carrier 0/29400 Rft work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Date of Start of Work 29-10-2017, Remarks.RCC Pipe Sewer 9"i/d=2900-Arranged/2957, 12"i/d=2800- Provision of Sewerage and Sanitation at village On-going Arranged/2878, 15"i/d=1100-Arranged/1175, 890 2493 Mianwali 20.000 1.996 3.333 2.500 1.667 67% 18% 18"i/d=800-Arranged/828, 21"i/d= 900- Dhoranka City, UC Namal, District Mianwali Schemes Arranged/978, 24"i/d=0/942, Surface Drain=0/430, PCC Slab=0/9035, Sullage Carrier (1.25'x1.5')=0/100, (1.50'x2')=0/500, (2.50'x4')=0/1400. Work is in progress.

Date of A.A. 18-08-2017, Date of T.S. 13-11-2017, Date of Start of Work 19-01-2018, Remarks. RCC Sewer=9" i/d=0/6890, 12"i/d= 482-Laid & 5214- Arranged/23310, 15"i/d= 6416-Arranged /6595, Provision of Integrated Sewerage Scheme for Wan On-going 18"i/d=2536-Arranged/2590, 21"i/d=0/150, 891 2494 Mianwali 75.000 11.995 3.333 2.974 2.141 72% 19% 24"i/d=1600-Arranged/1635, 27"i/d=1656- Bhachran Town, District Mianwali Schemes Arranged/1690, 30"i/d=1704-Arranged/1740, 33"i/d=407/510, Surface Drain= 0460, PCC Slab= 19713/98880, Sullage Carrier= 0/500, 0/150, Screening Chamber=0/1, P/Machinery=0/1, T/Line=0/1. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Date of Start of Work 29-10-2017, Remarks.RCC Provision of Sewerage and Sanitation at UC Mari, On-going Pipe Sewer 9"i/d=0/980, 12"i/d=0/2532, 892 2495 Mianwali 20.000 12.997 2.333 1.750 1.165 67% 71% 15"i/d=0/1418, 18"i/d=0/930, Surface Drain=0/1040, District Mianwali Schemes PCC Slab= 55632/28106, Sullage Carrier (1.25'x1.5')=0/430, (1.50'x2') =0/1850, (2.50'x4') =0/100 Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Date of Start of Work 29-10-2017, Remarks.RCC Provision of Sewerage and Sanitation at UC Kalon On-going Pipe Sewer 12"i/d=372-Arranged/ 2393, 893 2496 Mianwali 20.000 12.495 2.500 1.875 1.250 67% 69% 15"i/d=0/868, 18"i/d=0/636, Surface Wala, District Mianwali Schemes Drain=700/4535, Sullage Carrier=0/955, PCC Slab= 47095/33241, Brick Pavement=0/51000. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017-, Provision of Sewerage and Sanitation at UC On-going Date of Start of Work 29-10-2017, Remarks. RCC 894 2497 Mianwali 20.000 12.495 2.500 1.875 1.247 67% 69% Pipe Sewer 12"i/d=0/536, 24"i/d=0/257, Surface Manda Khel / Jalal Pur, District Mianwali Schemes Drain=491/3130, Sullage Carrier=350/850, PCC Slab= 40772/56009. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Installation of Submersible Pumps in PP-43 , On-going Date of Start of Work 29-10-2017, Remarks. 895 2498 Mianwali 50.000 21.998 3.333 2.500 1.667 67% 47% ERS=116/116, Trial Bore=06/11, Tube Well = District Mianwali Schemes 28/58, Pumping Machinery= 28/58, G.S.Tank 500- Glns=0/58. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, PCC Slab / Drainage Scheme UC Kot Chandna, On-going Date of Start of Work 29-10-2017, Remarks. PCC 896 2499 Mianwali 20.000 12.499 2.500 1.875 1.250 67% 69% Tehsil Isa Khel, District Mianwali Schemes Slab= 53864/ 59483, Surface Drain=1630/2900, Sullage Carrier=0/350 Work is in progress.

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Date of Start of Work 29-10-2017, Remarks. RCC Pipe Sewer 12"i/d= 785/1284, 24"i/d =280/330, Urban sewerage drainage scheme Isa Khel, On-going Surface Drain= 1261/4540, Sullage Carrier= 897 2500 Mianwali 20.000 9.999 3.333 2.500 1.662 66% 58% District Mianwali Schemes 540/1335, PCC Slab= 23154/28996, Tuff Tiles= 3238 /3564, Replacement of Rising Main 8"i/d PE=2000/3335, 6"i/d PVC=0/60, 4"i/d PVC = 0/60, 3"i/d PVC= 0/660. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, On-going Date of Start of Work 29-10-2017, Remarks. PCC 898 2501 PCC Slab at U.C Khaglanwala, District Mianwali Mianwali 20.000 10.000 3.333 2.500 1.666 67% 58% Slab=44695 /53023, Surface Drain=984/9255, Schemes Sullage Carrier=150/150, RCC Sewer 12" = 318/335. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, On-going Date of Start of Work 29-10-2017, Remarks. PCC 899 2502 PCC Slab at U.C Vanjari, District Mianwali Mianwali 20.000 9.999 3.333 2.500 1.667 67% 58% Schemes Slab= 44443 /63118, Surface Drain=0/1055, Sullage Carrier=0/120. Work is in progress.

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, On-going Date of Start of Work 29-10-2017. Remarks. PCC 900 2503 PCC Slab at U.C Chapri, District Mianwali Mianwali 20.000 9.998 3.333 2.500 1.661 66% 58% Schemes Slab= 41949/59804, Surface Drain= 0/4235, Sullage Carrier=0/600. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017 PCC Slab at U.C Paka Kamar Mushani, District On-going Date of Start of Work 29-10-2017, Remarks. RCC 901 2504 Mianwali 20.000 6.999 3.333 2.500 1.665 67% 43% Pipe Sewer 12"i/d=862/1530, Surface Mianwali Schemes Drain=0/1720, Sullage Carrier=400/400, PCC Slab=40973/57767. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Construction of PCC Slab & Drain Kala Bagh Lari On-going Date of Start of Work 29-10-2017, Remarks. 902 2505 Mianwali 15.250 6.999 2.750 2.063 1.370 66% 55% Surface Drain=0/7230, Sullage Carrier=0/100, PCC Adda, District Mianwali Schemes Slab=24252/35699, Tuff Tiles=0/15800. Work is in progress. Date of A.A. 01-08-2017, (Rev)Date of T.S.08-03- 2018, Date of Start of Work 29-10-2017, Remarks. Sewerage and Sanitation for Paki Shah Mardan On-going RCC Pipe Sewer 9"i/d=0/938, 12"i/d=590/4320, 903 2506 Mianwali 30.000 9.991 3.333 2.500 1.661 66% 39% 15"i/d=1314/1276, 18"i/d= 2504/3950, District Mianwali Schemes 21"i/d=1812/1664, 24"i/d=1291/2062, Surface Drain=0/120, PCC Slab=0/4600, Sullage Carrier=350/1060. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, Date of Start of Work 29-10-2017, Remarks.RCC PCC Slab / Drainage Scheme UC vanjari, Tehsil On-going 904 2507 Mianwali 20.000 9.994 3.333 2.500 1.667 67% 58% Pipe Sewer 12"i/d=2592-Arranged/2595, 15"i/d=480- Isa Khel, District Mianwali Schemes Arranged/480, Surface Drain=0/4535, Sullage Carrier=0/955, PCC Slab= 35812/44680. Work is in progress. Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, PCC Slab / Drainage Scheme UC Pacca Kama On-going Date of Start of Work 29-10-2017, Remarks. RCC 905 2508 Mianwali 40.000 20.000 6.667 5.000 3.330 67% 58% Pipe Sewer 12"i/d=2550/2785, 15"i/d=0/660, Mushani, Tehsil Isa Khel, District Mianwali Schemes Surface Drain=0/1270, Sullage Carrier=0/350, PCC Slab= 77311/107505 Work is in progress.

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017, PCC Slab / Drainage Scheme UC Sultan Khel, On-going Date of Start of Work 29-10-2017, Remarks. PCC 906 2509 Mianwali 20.000 9.996 3.333 2.500 1.660 66% 58% Thesil Isa Khel, District Mianwali Schemes Slab= 41269/59297, Surface Drain 0/5945, Sullage Carrier=0/200 Work is in progress.

Construction of Sewerage / Drainage scheme i/c On-going "Date of A.A 10.08.2017 Date of T.S 13.09.2017 907 2510 PCC Pavement in Street village Hussasin Shah, Bhakkar 64.920 10.000 3.333 2.500 2.500 100% 19% Date of Commencement 08.12.2017 Date of Schemes Tehsil Darya Khan District Bhakkar completion 30.06.2020 Construction of sullage carrier, surface drain, brick pavement, PCC Slab, RCC Sewer and Disposal On-going "Date of A.A 10.08.2017Date of T.S 18.08.2017 908 2511 Bhakkar 48.600 10.500 3.333 2.500 2.500 100% 27% Date of Commencement 31.10.2017 Date of Station in Sara-e-Mohajir, Chak No.250/TDA, Schemes completion 30.06.2020 District Bhakkar. Construction of sullage carrier, surface drain, brick On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 909 2512 pavement, PCC Slab, RCC Sewer and Disposal Bhakkar 48.600 15.500 3.333 2.500 2.500 100% 37% Date of Commencement 02.11.2017 Date of Schemes Station in Chak No.67/ML, District Bhakkar. completion 30.06.2020 Construction of sullage carrier, surface drain, brick pavement, PCC Slab, RCC Sewer and Disposal On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 910 2513 Bhakkar 47.255 18.000 3.333 2.500 2.167 87% 43% Date of Commencement 31.10.2017 Date of Station in Sara-e-Mohajir Chak No.71/ML, District Schemes completion 30.06.2020 Bhakkar. Construction of sullage carrier, surface drain, brick pavement, PCC Slab, RCC Sewer and Disposal On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 911 2514 Bhakkar 49.833 18.000 3.333 2.500 2.267 91% 41% Date of Commencement 31.10.2017 Date of Station at Adda Jahan Khan, Chak No.45/TDA, Schemes completion 30.06.2020 District Bhakkar. Rural sewerage, drainage, PCC Slab / brick On-going "Date of A.A 10.08.2017 Date of T.S 06.11.2017 912 2515 pavement scheme in UC Katchi Shahani, Tehsil & Bhakkar 57.023 17.500 3.333 2.500 2.500 100% 35% Date of Commencement 31.10.2017 Date of Schemes District Bhakkar completion 30.06.2020 Rural sewerage, drainage, PCC Slab / brick On-going "Date of A.A 10.08.2017 Date of T.S 06.11.2017 913 2516 pavement scheme in UC Sial, Tehsil & District Bhakkar 59.573 20.000 3.333 2.500 2.500 100% 38% Date of Commencement 13.12.2017 Date of Schemes Bhakkar completion 30.06.2020 PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian / and soling scheme UC Fazal, UC Chak No. 40/ML On-going "Date of A.A 10.08.2017 Date of T.S 18.18.2017 914 2517 Bhakkar 30.000 10.000 6.667 5.000 3.934 79% 46% Date of Commencement 31.10.2017 Date of UC Chak No. 63/DB, Tshil Kallur Kot, District Schemes completion 30.06.2019 Bhakkar PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian / and soling scheme UC Dali Namdar UC Ghulaman On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 915 2518 Bhakkar 40.000 15.000 3.333 2.500 1.667 67% 42% Date of Commencement 31.10.2017 Date of No.1, UC Ghulaman No.2, Tehsil Kallur Kot, Schemes completion 30.06.2020 District Bhakkar PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian / and soling scheme UC Haitthu, UC Kalul, UC On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 916 2519 Bhakkar 50.000 18.000 3.333 2.500 2.500 100% 41% Date of Commencement 31.10.2017 Date of Maibal, UC Kanjan and UC Noon Dagar, Tehsil Schemes completion 30.06.2020 Kallur Kot, District Bhakkar Provision of PCC Pavement / Slab, Sewerage, On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 917 2520 Culverts and Soling in UC Khaawar kala, Majoka, Bhakkar 46.563 23.500 3.333 2.500 1.667 67% 54% Date of Commencement 31.10.2017 Date of Schemes Lak Kalan, tehsil Darya Khan District Bhakkar completion 30.06.2020 Provision of PCC Pavement / Slab, Sewerage, Culverts and Soling in UC Dullaywala Rural, On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 918 2521 Bhakkar 46.904 20.000 3.333 2.500 1.661 66% 46% Date of Commencement 31.10.2017 Date of Jhammat Shumali, Barranga, Tehsil Darya Khan Schemes completion 30.06.2020 District Bhakkar Provision of PCC Pavement / Slab, Sewerage, Culverts and Soling in UC Daggar Qureshi, On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 919 2522 Bhakkar 36.304 15.000 3.333 2.500 1.660 66% 46% Date of Commencement 31.10.2017 Date of Wahwara, Barkatwala, Tehsil Darya Khan District Schemes completion 30.06.2020 Bhakkar. Provision of PCC Pavement / Slab, Sewerage, On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 920 2523 Culverts and Soling in UC Angra Daggar, Chak No Bhakkar 49.827 10.000 3.333 2.500 1.661 66% 23% Date of Commencement 31.10.2017 Date of Schemes 6/TDA, Gadai Tehsil Darya Khan District Bhakkar. completion 30.06.2020

Provision of PCC Pavement / Slab, Sewerage, On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 921 2524 Culverts and Soling in UC Punjigrain Daggar and Bhakkar 32.268 10.000 3.333 2.500 1.667 67% 36% Date of Commencement 31.10.2017 Date of Schemes Nasheb, Tehsil Darya Khan District Bhakkar. completion 30.06.2020

Construction of Sewerage / Drainage scheme i/c On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 922 2525 PCC Pavement in Street village Sukha Shah, Bhakkar 15.040 8.495 2.180 1.635 1.247 76% 65% Date of Commencement 03.11.2017 Date of Schemes Tehsil Darya Khan District Bhakkar completion 30.06.2019

Construction of Sewerage / Drainage scheme On-going "Date of A.A 10.08.2017 Date of T.S 18.18.2017 923 2526 Bhakkar 49.760 15.000 3.333 2.500 2.500 100% 35% Date of Commencement 02.11.2017 Date of Baranga Tehsil Darya Khan, District Bhakkar Schemes completion 30.06.2020

Construction of Sewerage / Drainage scheme i/c On-going "Date of A.A 10.08.2017 Date of T.S 18.18.2017 924 2527 PCC Pavement in Street village Londi Nasheeb, Bhakkar 27.650 10.000 3.333 2.500 2.500 100% 45% Date of Commencement 31.10.2017 Date of Schemes Tehsil Darya Khan, District Bhakkar completion 30.06.2020 Rural Drainage scheme UC Goharwala and On-going "Date of A.A 10.08.2017 Date of T.S 18.08.2017 925 2528 Bhakkar 28.345 15.000 4.448 3.336 3.336 100% 65% Date of Commencement 03.11.2017 Date of Khansar., District Bhakkar Schemes completion 30.06.2019 Construction of sewerage / Drainage scheme in On-going Date of A.A 10.08.2017 Date of T.S 18.08.2017 926 2529 Bhakkar 36.766 10.000 3.333 2.500 2.267 91% 33% Date of Commencement 02.11.2017 Date of Chak No. 49/TDA Tehsil and District Bhakkar Schemes completion 30.06.2020

Construction of sewerage / Drainage scheme in On-going Date of A.A 10.08.2017 Date of T.S 18.08.2017 927 2530 Bhakkar 45.685 5.000 3.333 2.500 2.500 100% 16% Date of Commencement 02.11.2017 Date of Chak No. 47/TDA Tehsil and District Bhakkar Schemes completion 30.06.2020 Extension of Sewerage / Drainage Scheme and On-going Date of A.A 10.08.2017 Date of T.S 18.08.2017 928 2531 PCC pavement in left over streets Darya Khan Bhakkar 50.000 22.499 3.333 2.500 2.060 82% 49% Date of Commencement 31.10.2017 Date of Schemes City, Tehsil Darya Khan District Bhakkar. completion 30.06.2020 Sewerage scheme Kotla Jam, Tehsil & District On-going Date of A.A 10.08.2017 Date of T.S 18.08.2017 929 2532 Bhakkar 48.611 4.000 3.333 2.500 1.660 66% 12% Date of Commencement 31.10.2017 Date of Bhakkar Schemes completion 30.06.2020 PCC Slab and Sewerage scheme MC jandanwala, On-going Date of A.A 10.08.2017 Date of T.S 18.08.2017 930 2533 Bhakkar 30.000 10.000 3.333 2.500 1.667 67% 39% Date of Commencement 31.10.2017 Date of Tehsil Kallut Kot, District Bhakkar Schemes completion 30.06.2020 PCC Slab and Sewerage scheme MC Kallut Kot, On-going Date of A.A 10.08.2017 Date of T.S 18.08.2017 931 2534 Bhakkar 50.000 21.500 3.333 2.500 2.500 100% 48% Date of Commencement 31.10.2017 Date of District Bhakkar Schemes completion 30.06.2020 Construction of PCC, Soling & drains schemes in On-going Date of A.A 29-09-2017. Date of T.S.05-09-2017. 932 2535 Chak No.409 GB, 420 GB, 410 GB, 405 GB, 407 Faisalabad 15.500 10.000 1.833 1.375 0.917 67% 70% Work order issued on 31-10-2017. Work is in Schemes GB, 424 GB District Faisalabad progress. Funds released on 03.08.2018 & 24.1.19.

Construction of PCC, Soling & drains schemes in On-going Date of A.A 29-09-2017. Date of T.S.05-09-2017. 933 2536 Chak No. 430 GB, 422GB, 423 GB, 427 GB, 428 Faisalabad 12.500 7.000 1.833 1.375 0.917 67% 63% Work order issued on 31-10-2017. Work is in Schemes GB, 425 GB, 404 GB District Faisalabad progress. Funds released on 03.08.2018 & 24.1.19. Construction of PCC, soling & drainage and boundary walls of graveyards in Pindi Sheikh On-going Date of A.A 29-09-2017. Date of T.S.16-09-2017. 934 2537 Musa, Mobarik Pura, Chak No.451 GB, 429 GB, Faisalabad 17.000 5.889 2.333 1.750 1.167 67% 42% Work order issued on 31-10-2017. Work is in Schemes 400 GB, 408 GB & Nazir Colony District progress. Funds released on 03.08.2018 & 24.1.19. Faisalabad On-going ate of A.A 04-10-2017. Date of T.S.14-12-2017. 935 2538 Rural Drainage Scheme of Villages in NA-76 Faisalabad 150.000 39.926 6.667 5.000 3.334 67% 29% Work order issued on 01-03-2018. Work is in Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Construction of Rural Drainage and PCC Road UC On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 936 2539 Faisalabad 15.000 5.000 3.333 2.500 1.667 67% 44% Work order issued on 19-01-2018. Work is in 30, 194/RB, District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Construction of Rural Drainage and PCC Road On-going ate of A.A 04-10-2017. Date of T.S.14-12-2017. 937 2540 Faisalabad 15.000 5.000 3.333 2.500 1.667 67% 44% Work order issued on 01-03-2018. Work is in ,UC 60 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Construction of Rural Drainage and PCC Road , On-going ate of A.A 04-10-2017. Date of T.S.14-12-2017. 938 2541 Faisalabad 15.000 5.000 3.333 2.500 1.667 67% 44% Work order issued on 01-03-2018. Work is in UC 71 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Construction of Rural Drainage and PCC Road at On-going ate of A.A 04-10-2017. Date of T.S.14-12-2017. 939 2542 Faisalabad 15.000 3.495 2.667 2.000 1.330 67% 32% Work order issued on 01-03-2018. Work is in U.C. 62 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Construction of Rural Drainage and PCC Road at On-going ate of A.A 04-10-2017. Date of T.S.14-12-2017. 940 2543 Faisalabad 15.000 2.049 1.667 1.250 0.834 67% 19% Work order issued on 01-03-2018. Work is in U.C. 65 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Construction of Rural Drainage and PCC Road at On-going ate of A.A 04-10-2017. Date of T.S.14-12-2017. 941 2544 Faisalabad 15.000 4.928 1.667 1.250 0.834 67% 38% Work order issued on 01-03-2018. Work is in U.C. 67 District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19. Provision of Sewerage/ Drainage Facilities in PP- On-going Date of A.A 27-10-2017. Date of T.S.28-10-2017. 942 2545 57, District Faisalabad Faisalabad 50.000 19.297 3.333 2.500 1.667 67% 42% Work order issued on 30-11-2017. Work is in Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Drainage Scheme for Muncipal committee On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 943 2546 Faisalabad 49.888 29.937 3.333 2.500 1.667 67% 63% Work order issued on 19-01-2018. Work is in Samundri District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Drainage Scheme for Samundri District On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 944 2547 Faisalabad 50.000 20.000 3.333 2.500 1.667 67% 43% Work order issued on 19-01-2018. Work is in Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Drainage Scheme at Chak No. 263/RB, On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 945 2548 Faisalabad 30.000 10.000 3.333 2.500 1.667 67% 39% Work order issued on 19-01-2018. Work is in Dijkot Town Committee Tehsil ,District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19. Rural Water Supply Scheme chak No. 203\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 946 2549 Faisalabad 23.880 10.000 4.627 3.470 2.314 67% 52% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 199\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 947 2550 Faisalabad 13.434 10.000 1.145 0.859 0.573 67% 79% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 208\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 948 2551 Faisalabad 20.359 10.000 3.453 2.590 1.727 67% 58% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

PCC / Seewrage etc. Scheme Jaranwala City in On-going Date of A.A 02-10-2017. Date of T.S.02-11-2017. 949 2552 Faisalabad 100.000 20.877 6.667 5.000 3.334 67% 24% Work order issued on 01-03-2018. Work is in NA-76 Schemes progress.Funds released on 03.08.2018& 24.1.19.

Provision of Solling / Nalian / Drainage in Tandlianwala City , Mamu kanjan City, UC's On-going Date of A.A 09-10-2017. Date of T.S.02-11-2017. 950 2553 76,77,78,79,80,81,82,83,84,85,86,87, 88, 89, 90, Faisalabad 126.000 24.631 6.667 5.000 3.334 67% 22% Work order issued on 01-02-2018. Work is in Schemes 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102, progress. Funds released on 03.08.2018 & 24.1.19. 103, 104, Tehsil Tandlianwala District Faisalabad

Rural Water supply Scheme chak no. 209\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 951 2554 Faisalabad 19.412 10.000 3.137 2.353 1.569 67% 60% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 212\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 952 2555 Faisalabad 12.439 10.000 0.813 0.610 0.407 67% 84% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 207\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 953 2556 Faisalabad 26.341 10.000 3.333 2.500 1.667 67% 44% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 211\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 954 2557 Faisalabad 11.338 6.000 1.779 1.334 0.890 67% 61% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 202\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 955 2558 Faisalabad 12.378 6.000 2.126 1.595 1.063 67% 57% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Rural Water supply Scheme chak no. 200\GB On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 956 2559 Faisalabad 11.850 6.000 1.950 1.463 0.975 67% 59% Work order issued on 31-10-2017. Work is in Tehsil Samundari District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19. Construction of Soling, Nallian, Pullian, Nallah and On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 957 2560 Water Supply at Chak No. 5 GB Kamal Pur UC Faisalabad 37.222 15.000 3.333 2.500 1.667 67% 45% Work order issued on 31-10-2017. Work is in Schemes 168 in District Faisalabad progress.Funds released on 03.08.2018 & 24.1.19. Construction of Soling, Nallian, Pullian, Nallah and On-going Date of A.A 05-08-2017. Date of T.S.16-09-2017. 958 2561 Water Supply at Chak No. 52 GB malal Pur UC Faisalabad 22.692 10.000 4.231 3.173 2.116 67% 53% Work order issued on 31-10-2017. Work is in Schemes 166 in District Faisalabad progress. Funds released on 03.08.2018 & 24.1.19. Construction of PCC different streets UC-4 UC-6 On-going AA issued on 05.08.2017. Date of T.S 16.09.2017 959 2562 Faisalabad 40.000 18.000 1.000 0.750 0.500 67% 46% Work order issued on 23.11.2018. Work is in UC-7 UC-8 in District Faisalabad Schemes progress. Funds released on 12.06.2018 & 24.1.19.

Construction of PCC different streets UC-9 UC-10 On-going AA issued on 05.08.2017. Date of T.S 16.09.2017 960 2563 Faisalabad 30.000 15.000 1.000 0.750 0.500 67% 52% Work order issued on 13.06.2018. Work is in UC-11UC-12 in District Faisalabad Schemes progress. Funds released on 23.11.2018 & 24.1.19.

Construction of PCC different streets UC-14 UC-15 On-going AA issued on 05.08.2017. Date of T.S 16.09.2017 961 2564 Faisalabad 20.000 10.000 1.000 0.750 0.500 67% 53% Work order issued on 12.06.2018. Work is in UC-17 in District Faisalabad Schemes progress. Funds released on 23.11.2018 & 24.1.19.

On-going Date of A.A 02-10-2017. Date of T.S.01-11-2017. 962 2565 Construction of PCC Streets in District Faisalabad Faisalabad 75.000 25.000 6.667 5.000 3.334 67% 38% Work order issued on 08-02-2018. Work is in Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Sewerage Sheme in 240GB and additional On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 963 2566 Faisalabad 30.000 20.000 3.333 2.500 1.960 78% 73% Work order issued on 19-01-2018. Work is in Abadies Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Provision of PCC / Sewerage / Drainage / Tuff Tile On-going Date of A.A 29-08-2017. Date of T.S.05-09-2017. 964 2567 Faisalabad 50.000 25.000 3.333 2.500 1.667 67% 53% Work order issued on 19-01-2018. Work is in and etc in PP-53, District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19. Water Supply Schemes in Constitutency NA-80, On-going Date of A.A 19-09-2017. Date of T.S.20-11-2017. 965 2568 Faisalabad 122.000 35.000 6.667 5.000 3.334 67% 31% Work order issued on 01-02-2018. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19.

Provision of Installation of New Water Plant in On-going Date of A.A 02-10-2017. Date of T.S.17-11-2017. 966 2569 Faisalabad 75.000 34.862 6.667 5.000 3.334 67% 51% Work order issued on 03-03-2018. Work is in District Faisalabad Schemes progress. Funds released on 03.08.2018 & 24.1.19. Soling / Drains / Culverts / PCC Slabs / UC No.1 to On-going Date of A.A 01.08.2017 Date of T.S 06.09.2017 967 2570 Jhang 13.000 6.996 2.000 1.500 1.166 78% 63% Work order issued on 31.10.2017 Work is in UC No.8 Tehsil & District Jhang Schemes progress. On-going Date of A.A 01.08.2017 Date of T.S 06.09.2017 968 2571 Drainage Scheme Chak no. 479/JB District Jhang. Jhang 16.749 6.991 3.250 2.438 1.935 79% 53% Work order issued on 31.10.2017 Work is in Schemes progress. On-going Date of A.A 01.08.2017 Date of T.S 06.09.2017 969 2572 Drainage Scheme Chak no. 482/JB District Jhang. Jhang 20.489 4.982 3.333 2.500 1.943 78% 34% Work order issued on 31.10.2017 Work is in Schemes progress. On-going Date of A.A 01.08.2017 Date of T.S 06.09.2017 970 2573 Drainage Scheme Chak no. 493/JB District Jhang. Jhang 30.614 11.999 3.333 2.500 1.999 80% 46% Work order issued on 31.10.2017 Work is in Schemes progress. Construction of Soling, Drains, PCC and Sullage at On-going Date of A.A 01.08.2017 Date of T.S 06.09.2017 971 2574 Sammunduana, Tehsil Ahmad Pur Sial District Jhang 14.354 9.855 1.451 1.088 0.846 78% 75% Work order issued on 31.10.2017 Work is in Schemes Jhang. progress. Rural Drainage Scheme at Different Villages, 18 On-going Date of A.A 01.08.2017 Date of T.S 13.09.2017 972 2575 Jhang 40.000 19.996 3.333 2.500 2.010 80% 55% Work order issued on 23.12.2017. Work is in Hazari, in District Jhang Schemes progress. Water Supply Scheme Chak No. 412 Cheemia Wali, Tehsil Shorkot, District Jhang and On-going Date of A.A 01.08.2017 Date of T.S 13.09.2017 973 2576 Jhang 20.303 9.990 3.434 2.576 2.150 83% 60% Work order issued on 23.11.2017 Work is in Construction of Tank for Water Supply Scheme Schemes progress. Chak No. 412 Cheemia Wali. Provision of Water Supply at Chak No. 498 Tehsil On-going Date of A.A 01.08.2017 Date of T.S 13.09.2017 974 2577 Jhang 22.000 9.993 4.000 3.000 2.433 81% 56% Work order issued on 23.11.2017 Work is in Shorkot, District Jhang. Schemes progress. Provision of Sewerage & drainage At UC-46 On-going Date of A.A 01.08.2017 Date of T.S 06.09.2017 975 2578 Jhang 15.000 6.899 2.667 2.000 1.554 78% 56% Work order issued on 31.10.2017 Work is in Rustam Sargana Tehsil shorkot. Schemes progress. Sewerage / Drainage Scheme for Tehsil On-going Date of A.A 19.09.2017 Date of T.S 09.10.2017 976 2579 Headquartar Ahmad Pur Sial District Jhang Phase- Jhang 100.000 39.962 6.667 5.000 3.900 78% 44% Work order issued on 17.01.2018 Work is in Schemes 2. progress. Hazrat Peer Abdur rehman Sewerage Scheme On-going Date of A.A 19.09.2017 Date of T.S 28.09.2017 977 2580 Jhang 70.000 24.580 6.667 5.000 3.886 78% 41% Work order issued on 13.01.2018 Work is in District Jhang. Schemes progress. Provision of 16 nos. Water Filtration Plants in On-going Date of A.A 18.10.2017 Date of T.S 31.10.2017 978 2581 Jhang 40.000 0.600 3.333 2.500 2.001 80% 7% Work order issued on 13.08.2018. Work is in Tehsil 18 Hazari, District Jhang. Schemes progress. 1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Drainage and Soling and Replacement tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 979 2582 / new Water Supply Pipelines in UC 18 District T.T. Toba Tek Singh 13.000 7.465 1.833 1.375 1.200 87% 67% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Drainage and Soling and Replacement tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 980 2583 / new Water Supply Pipelines in UC 34 District T.T. Toba Tek Singh 12.500 6.225 2.083 1.562 1.042 67% 58% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 28.09.2017 2- Date of T.S 19.10.2017 3-Date of Prequalification 4-Date of invitation of Laying of Soling, Resoling, Drain, Repair of Roads tenders 5- Date of Receipt of tenders 6- Date of On-going work order 22.11.2017 7- Date of completion as per 981 2584 and Piplelines Water and Sewerage in District Toba Tek Singh 315.000 65.000 3.333 2.500 1.900 76% 21% Schemes PC-I 8- Anticipated date of completion 9- No. of T.T.Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3-Date of Prequalification 4-Date of invitation of Laying of PCC, Tuff Tiles, Soling and Resoling, tenders 5- Date of Receipt of tenders 6- Date of On-going 982 2585 Drain, Repair of Roads and Pipelines of water and Toba Tek Singh 85.000 34.899 1.000 1.667 1.650 99% 43% work order 22.11.2017 7- Date of completion as per Schemes PC-I 8- Anticipated date of completion 9- No. of Sewerage in District T.T.Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 Rehablitation of Rural Water Supply Scheme Chak 3-Date of Prequalification 4-Date of invitation of # 148/ GB, 149/GB, 151/GB ,153/GB, Balgn, tenders 5- Date of Receipt of tenders 6- Date of On-going work order 22.11.2017 7- Date of completion as per 983 2586 294/JB, 350/GB, Rural Water Supply Scheme Toba Tek Singh 185.086 40.000 3.333 2.500 2.000 80% 23% Schemes PC-I 8- Anticipated date of completion 9- No. of Chak # 258/GB Noor Mahal and 292/GB Bara Beneficiary 7006 Person 10-Funds Released by F.D Rasla in District T.T.Singh. 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3-Date of Prequalification 4-Date of invitation of Rehabalitation of Rural Water Supply Scheme tenders 5- Date of Receipt of tenders 6- Date of Chak # 402/JB Virkan348/GB Bajra, 296/GB, On-going work order 22.11.2017 7- Date of completion as per 984 2587 Toba Tek Singh 178.792 68.399 3.333 3.000 2.167 72% 39% 297/GB, 299/GB, 290/GB, 349/GB, and 351/GB in Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary -4383 Person 10-Funds Released by District T.T.Singh. F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Water Supply Scheme in Chak no. 374/JB, 387/JB, On-going work order 31.10.2017 7- Date of completion as per 985 2588 Toba Tek Singh 35.000 11.964 3.333 2.500 2.000 80% 40% 385/JB, District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary -3360 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Drainage/Soling and Water Supply and Road On-going work order 31.10.2017 7- Date of completion as per 986 2589 Toba Tek Singh 12.000 6.000 2.000 1.500 0.980 65% 58% Repair UC No. 26 in District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Drainage/Soling and Water Supply and Road On-going work order 31.10.2017 7- Date of completion as per 987 2590 Toba Tek Singh 12.000 5.956 2.000 1.500 0.985 66% 58% Repair UC No. 28 in District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Drainage/Soling and Water Supply and Road On-going work order 31.10.2017 7- Date of completion as per 988 2591 Toba Tek Singh 12.000 6.000 2.000 1.500 0.970 65% 58% Repair UC No. 32 in District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Drainage/Soling and Water Supply and Road On-going work order 31.10.2017 7- Date of completion as per 989 2592 Toba Tek Singh 12.000 5.984 2.000 1.500 0.967 64% 58% Repair UC No. 30 in District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

Rural Water Supply Scheme Chak No. 321/GB 1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Khumanwala Tehsil Pirmahal District Toba Tek tenders 5- Date of Receipt of tenders 6- Date of Singh, Chak No. 700/42 GB Pir Kadhiana – On-going work order 31.10.2017 7- Date of completion as per 990 2593 Toba Tek Singh 49.970 17.999 5.000 3.750 3.500 93% 43% Christian Colony Tehsil Pirmahal District Toba Tek Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary -5847 Person 10-Funds Released by Singh, Chak No. 294/GB azafi abadi Tehsil & F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation District Toba Tek Singh. of funds (+/-) Work in progress. Rehabilitation of Rural Water Supply Scheme 1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3-Date of Prequalification 4-Date of invitation of Chak No. 301/GB azafi abadi – New Chak Tehsil & tenders 5- Date of Receipt of tenders 6- Date of District Toba Tek Singh, Chak No. 303/GB azafi On-going 991 2594 Toba Tek Singh 72.396 20.000 3.333 2.500 1.665 67% 30% work order 22.11.2017 7- Date of completion as per abadi Tehsil & District Toba Tek Singh, Chak No. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 333/GB, District Toba Tek Singh, Chak No. 03.08.2018 & 24.01.2019 - 11-Re-appropriation of 341/GB Tehsil & District funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Extension / Rehabilitation Rural Water Supply tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 992 2595 Scheme Chak No.325 and 326/ GB, District T.T Toba Tek Singh 24.600 19.000 1.867 0.600 0.400 67% 79% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - 13647 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No. 671/12- On-going work order 31.10.2017 7- Date of completion as per 993 2596 Toba Tek Singh 21.500 15.000 2.167 2.425 2.000 82% 79% GBDistrict T.T. Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - 4716 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No.711/GB On-going work order 31.10.2017 7- Date of completion as per 994 2597 Toba Tek Singh 15.400 7.000 2.800 0.795 0.095 12% 46% PC-I 8- Anticipated date of completion 9- No. of District T.T. Singh. Schemes Beneficiary -5309 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work could not be started due to site problem. 1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No.662/3-GB On-going work order 31.10.2017 7- Date of completion as per 995 2598 Toba Tek Singh 29.500 10.000 3.333 2.500 1.667 67% 40% District T.T. Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - 8625 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No706/GB. On-going work order 31.10.2017 7- Date of completion as per 996 2599 Toba Tek Singh 27.300 11.998 5.100 3.825 2.500 65% 53% District T.T. Singh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - 6164 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No.720/GB On-going work order 31.10.2017 7- Date of completion as per 997 2600 Toba Tek Singh 24.750 17.000 2.583 1.937 1.500 77% 75% District T.T. Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary -11853 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No.721/GB On-going work order 31.10.2017 7- Date of completion as per 998 2601 Toba Tek Singh 25.700 14.799 3.633 2.725 1.800 66% 65% District T.T. Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary -8765 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Water Supply Scheme Chak No.722/GB On-going work order 31.10.2017 7- Date of completion as per 999 2602 Toba Tek Singh 23.500 13.999 3.167 0.885 0.094 11% 60% PC-I 8- Anticipated date of completion 9- No. of District T.T. Singh Schemes Beneficiary -6826 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work could not be started due to site problem. 1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018 3-Date of Prequalification 4-Date of invitation of Water Supply Scheme Chak No. 317/JB and tenders 05.03.2018 5- Date of Receipt of tenders On-going 06.03.2018 6- Date of work order 27.03.2018 7- 1000 2603 Installation of Filtration Plant in Chak No.401/JB Toba Tek Singh 24.587 10.000 4.862 3.647 3.200 88% 54% Schemes Date of completion as per PC-I 8- Anticipated date District T.T.Singh of completion 9- No. of Beneficiary -.. Person 10- Funds Released by F.D 03.08.2018 & 24.01.2019 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018 3-Date of Prequalification 4-Date of invitation of Rehabilitation / Improvemnet of Rural Draiange tenders 05.03.2018 5- Date of Receipt of tenders On-going 06.03.2018 6- Date of work order 03.04.2018 7- 1001 2604 Scheme Chak no. 402/GB Virkan Tehsil and Toba Tek Singh 35.000 3.999 1.667 1.250 0.834 67% 14% Schemes Date of completion as per PC-I 8- Anticipated date District T.T.Singh of completion 9- No. of Beneficiary -.. Person 10- Funds Released by F.D 03.08.2018 & 24.01.2019 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Soling / Re-Soling Nali / Sewerage / tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 1002 2605 PCC and Tuff Tile Schemes in City Kamalia In Toba Tek Singh 20.000 9.998 3.333 2.500 2.200 88% 61% Schemes PC-I 8- Anticipated date of completion 9- No. of District T.T.Singh Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S 12.10.2017 3-Date of Prequalification 4-Date of invitation of Soling Drainage Khalla Nalli and Pullian in UC 57, tenders 5- Date of Receipt of tenders 6- Date of On-going work order 18.11.2017 7- Date of completion as per 1003 2606 58, 59, 60, 61, 62, 63, 66, 68, Chak No. 735/GB in Toba Tek Singh 60.000 20.000 3.333 2.500 2.000 80% 37% Schemes PC-I 8- Anticipated date of completion 9- No. of Tehsil Kamalia District T.T.Singh Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Tuff Tile PCC Soling / Drainage / Sewerage in On-going work order 31.10.2017 7- Date of completion as per 1004 2607 Toba Tek Singh 40.000 13.662 1.667 1.250 0.834 67% 36% Kamalia City Tehsil Kamalia District T.T.Singh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Tuff Tile PCC Soling / Re-soling Drainag, On-going work order 31.10.2017 7- Date of completion as per 1005 2608 Toba Tek Singh 40.000 14.999 1.667 1.250 1.000 80% 40% Sewerage etc for Kamalia City Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Construction of PCC / Tuff tile/Soling/Resoling On-going work order 31.10.2017 7- Date of completion as per 1006 2609 Toba Tek Singh 25.000 10.000 5.000 3.750 3.000 80% 52% Pirmahal City in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Drainage and Soling and Replacement tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 1007 2610 / new Water Supply Pipelines in UC 17 District T.T. Toba Tek Singh 32.000 12.000 1.667 1.250 1.000 80% 41% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-). Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Provision of Tuff Paver and Drains in Kamalia City, On-going work order 31.10.2017 7- Date of completion as per 1008 2611 Toba Tek Singh 40.000 15.000 1.667 9.451 9.451 100% 61% District T.T.Singh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Provision of Tuff Paver and Drains in Pir Mahal On-going work order 31.10.2017 7- Date of completion as per 1009 2612 Toba Tek Singh 40.000 15.000 1.667 0.483 0.300 62% 38% City, District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Drainage and Soling and Replacement tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 1010 2613 / new Water Supply Pipelines in UC 14 District T.T. Toba Tek Singh 15.000 7.500 2.500 1.875 1.250 67% 58% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Drainage and Soling and Replacement tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 1011 2614 / new Water Supply Pipelines in UC 15 District T.T. Toba Tek Singh 31.000 20.000 3.333 2.500 1.667 67% 70% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4-Date of invitation of Provision of Drainage and Soling and Replacement tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 1012 2615 / new Water Supply Pipelines in UC 16 District T.T. Toba Tek Singh 13.000 7.500 1.833 1.375 0.912 66% 65% Schemes PC-I 8- Anticipated date of completion 9- No. of Singh. Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1013 2616 Toba Tek Singh 3.000 1.455 0.500 0.375 0.249 66% 57% 672/13 GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of Rural Drainage/Brick Pavement/Resoling Chak No. tenders 5- Date of Receipt of tenders 6- Date of On-going work order 31.10.2017 7- Date of completion as per 1014 2617 673/14/GB Harisabad & azafi abadi in District Toba Tek Singh 3.000 1.422 0.500 0.375 0.250 67% 56% Schemes PC-I 8- Anticipated date of completion 9- No. of T.Tsingh Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1015 2618 Toba Tek Singh 3.000 1.500 0.500 0.375 0.250 67% 58% 675/16/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) .Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1016 2619 Toba Tek Singh 3.000 1.498 0.500 0.375 0.250 67% 58% 676/17/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Mouza On-going work order 31.10.2017 7- Date of completion as per 1017 2620 Toba Tek Singh 3.000 1.000 0.667 0.500 0.334 67% 44% Shahpur & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Mouza On-going work order 31.10.2017 7- Date of completion as per 1018 2621 Toba Tek Singh 3.000 0.997 0.667 0.500 0.334 67% 44% Nakrari & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Mouza On-going 1019 2622 Toba Tek Singh 2.500 0.952 1.548 1.161 0.700 60% 66% work order 31.10.2017 7- Date of completion as per Bub & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 23.11.2018 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Provision of Sewerage / Drainage / Tuff Tiles etc in On-going work order 18.11.2017 7- Date of completion as per 1020 2623 Toba Tek Singh 199.924 99.996 5.000 3.750 2.500 67% 51% District T.T.Singh. Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Plot-A & On-going work order 31.10.2017 7- Date of completion as per 1021 2624 Toba Tek Singh 3.000 1.500 0.500 0.375 0.250 67% 58% azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1022 2625 Toba Tek Singh 3.000 1.499 0.500 0.375 0.250 67% 58% 718/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1023 2626 Toba Tek Singh 3.000 1.500 0.500 0.375 0.250 67% 58% 719/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1024 2627 Toba Tek Singh 3.000 1.478 0.500 0.375 0.247 66% 58% 720/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1025 2628 Toba Tek Singh 3.000 1.500 0.500 0.375 0.244 65% 58% 722/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1026 2629 Toba Tek Singh 3.000 1.020 0.500 0.375 0.245 65% 42% 741/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1027 2630 Toba Tek Singh 3.000 0.595 0.500 0.375 0.246 66% 28% 747/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1028 2631 Toba Tek Singh 2.500 1.204 0.417 0.313 0.200 64% 56% 757/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1029 2632 Toba Tek Singh 3.000 1.500 0.500 0.375 0.248 66% 58% 759/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) .Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1030 2633 Toba Tek Singh 2.500 1.250 0.417 0.313 0.203 65% 58% 760/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1031 2634 Toba Tek Singh 3.000 1.500 0.500 0.375 0.250 67% 58% 764/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Chak No. On-going work order 31.10.2017 7- Date of completion as per 1032 2635 Toba Tek Singh 3.000 1.500 0.500 0.375 0.250 67% 58% 660/1/GB & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3-Date of Prequalification 4-Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of Rural Drainage/Brick Pavement/Resoling Mouza On-going work order 31.10.2017 7- Date of completion as per 1033 2636 Toba Tek Singh 3.000 1.500 0.500 0.375 0.250 67% 58% Inayat Shah & azafi abadi in District T.Tsingh Schemes PC-I 8- Anticipated date of completion 9- No. of Beneficiary - Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) . Work in progress.

Constructoin of Drains PCC / RCC in UC Qila Mian On-going 1034 2637 Gujranwala 50.000 13.000 5.000 3.750 2.500 67% 31% Work in progress Singh Uggu Chak District Gujranwala Schemes Sewerage PCC Drainage in UC Wahndo / UC On-going 1035 2638 Gujranwala 60.000 19.991 6.667 5.000 3.334 67% 39% Work in progress Chak Ramdas in District Gujranwala Schemes Construction of PCC and Sewerage at Y-Block Peoples Colony, X-Block Behari Colony, Shadman On-going 1036 2639 Gujranwala 20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress Town, Green Town Ahsan Town, Hassan Town Schemes District Gujranwala Construction of PCC and Sewerage at Kot Abdullah, Kangni Wala, Rana Colony, Saddique On-going 1037 2640 Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress Colony, Nabi Pura, Illama Iqbal Town in District Schemes Gujranwala Provision of Sewerage, PCC, Street, Drain, Tuff On-going 1038 2641 Tile, Water Supply in City Wazirabad, Sodra, Gujranwala 200.000 75.000 3.333 2.500 1.667 67% 38% Work in progress Schemes District Gujranwala Drainage and PCC Soling in UCs Nokhar, On-going 1039 2642 Pheloke, Udowali, in Saharan Chatha District Gujranwala 88.947 19.901 3.333 2.500 1.667 67% 24% Work in progress Schemes Gujranwala Drainage and PCC Soling in UCs Noi wala, Jattan On-going 1040 2643 wali, Bheri Shah Rehman, Jhallan in District Gujranwala 89.034 17.820 3.333 2.500 1.667 67% 22% Work in progress Schemes Gujranwala Drainage and PCC Soling in UCs Phama Sara, On-going 1041 2644 Arghan, Chak Chaudhary, Kot Ladha, in District Gujranwala 89.776 20.000 3.333 2.500 1.667 67% 24% Work in progress Schemes Gujranwla Construction of PCC Streets and Drainage in Botala Sharam Singh / Akbarian, Sansera Goraya and Muslim Chack, Attawa, Therri Sansi and Chand da Qila, Kotli Dianat Raye and Sheray wala, On-going 1042 2645 Gujranwala 50.000 20.000 30.000 22.500 15.000 67% 70% Work in progress Nangray Dadan, Dera Bhaghat Singh and Dera Schemes Hakam Singh, Chddiala Kalan and Khurd, Murali wala and Khuwasra, Dhillian wali, Chianwall, Kot Shera and Sahnaya wala

Construction of PCC and Sewerage at sarfaraz On-going 1043 2646 Colony, Hashimi Colony, Gulshan Adeel, Mumtaz Gujranwala 40.000 15.000 1.667 1.250 0.834 67% 40% Work in progress Schemes Colony, Karmabad District Gujranwala

Construction of PCC and Sewerage at Asghar On-going 1044 2647 Colony, Salamat Pura, Allah Bukhsh Colony, Gujranwala 40.000 15.000 1.667 1.250 0.834 67% 40% Work in progress Schemes Nawaz Colony, Faisal Colony District Gujranwala Construction of PCC and Sewerage at Jinnah Colony, Rehman Colony, Ali Pura, Bukhari Colony, On-going 1045 2648 Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress Sanat Road, Jamia Muhammadiya District Schemes Gujranwala Construction of PCC and Sewerage at Rasheed On-going 1046 2649 Colony, Ismail Pura, Abdullah Colony, W Block Gujranwala 20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress Schemes Peoples Colony District Gujranwala Construction of PCC and Sewerage at Z- Block On-going 1047 2650 Peoples Colony, X-Block Peoples Colony District Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress Schemes Gujranwala Construction of PCC and Sewerage at Chamra Mandi, Wahdat Colony, Chaman Shah Road, Taj On-going 1048 2651 Gujranwala 20.000 9.910 3.333 2.500 1.667 67% 58% Work in progress Colony, Arfat Colony, Ferozwala Road in District Schemes Gujranwala Construction of PCC and Sewerage at Arfat On-going 1049 2652 Colony, Islam Pura, Haidry Road in District Gujranwala 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress Schemes Gujranwala Construction of PCC and Sewerage at Mujahid On-going 1050 2653 Pura, Camp No. 4, Saithy Palaza, Faisal Colony, Gujranwala 15.000 9.999 1.667 1.250 0.834 67% 72% Work in progress Schemes in District Gujranwala Construction of PCC and Sewerage at Galla On-going 1051 2654 Ghulam Thakedar Wala, Galla Mehar Noor Wala, Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress. Schemes Islam Pura, Muslim Road in District Gujranwala Drainage and PCC at UC, 31,40,46 at District On-going 1052 2655 Gujranwala 150.000 29.998 5.000 3.750 2.500 67% 22% Work in progress Gujranwala Schemes Construction of PCC/ Tuff Tile, Drainage and Allied On-going 1053 2656 Gujranwala 50.000 29.987 3.333 2.500 1.667 67% 63% Work in progress Facilities etc in NA-96, District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 48 On-going 1054 2657 Gujranwala 25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 49 On-going 1055 2658 Gujranwala 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 50 On-going 1056 2659 Gujranwala 15.000 9.948 1.667 1.250 0.834 67% 72% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 51 On-going 1057 2660 Gujranwala 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 52 On-going 1058 2661 Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 53 On-going 1059 2662 Gujranwala 20.000 9.920 3.333 2.500 1.667 67% 58% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 54 On-going 1060 2663 Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 57 On-going 1061 2664 Gujranwala 20.000 9.982 3.333 2.500 1.667 67% 58% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 58 On-going 1062 2665 Gujranwala 25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 59 On-going 1063 2666 Gujranwala 20.000 9.954 3.333 2.500 1.667 67% 58% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 60 On-going 1064 2667 Gujranwala 25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress District Gujranwala Schemes Construction of PCC, Sewerage/Drains at UC 62 On-going 1065 2668 Gujranwala 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress District Gujranwala Schemes Provision of Sewerage, Drainage and PCC On-going 1066 2669 Scheme UC Aroop, UC Butteranwali, District Gujranwala 200.000 40.000 3.333 2.500 1.667 67% 21% Work in progress Schemes Gujranwala, Phase-I Provision of Sewerage, Drainage and PCC On-going 1067 2670 Scheme for Area Rahwali Sharqi, Kot Shahan And Gujranwala 100.000 30.000 3.333 2.500 1.667 67% 32% Work in progress Schemes Trigri District Gujranwala Construction of PCC/RCC/Drainage at On-going 1068 2671 Gujranwala 30.000 7.992 20.000 15.000 10.000 67% 60% Work in progress Shaheenabad, Gujranwala Schemes Construction of PCC/RCC/Drainage at Pasban On-going 1069 2672 Gujranwala 50.000 15.000 3.333 2.500 1.667 67% 33% Work in progress Colony, Gujranwala Schemes Construction of PCC/RCC/Drainage at Samnabad, On-going 1070 2673 Gujranwala 50.000 15.000 3.333 2.500 1.667 67% 33% Work in progress Gujranwala Schemes Construction of PCC/RCC/Drainage at On-going 1071 2674 Gujranwala 30.000 7.000 3.333 2.500 1.667 67% 29% Work in progress Gondalwala, Gujranwala Schemes Construction of PCC/RCC/Drainage at Aminpur, On-going 1072 2675 Gujranwala 30.000 7.989 3.333 2.500 1.667 67% 32% Work in progress Gujranwala Schemes Construction of PCC/RCC/Drainage at Badoki On-going 1073 2676 Gujranwala 30.000 8.000 3.333 2.500 1.667 67% 32% Work in progress Gusaian, Gujranwala Schemes Construction of PCC/RCC/Drainage at On-going 1074 2677 Gujranwala 30.000 8.000 3.333 2.500 1.667 67% 32% Work in progress Dingranwali, Gujranwala Schemes Provision of PCC / Sewerage schemes near On-going 1075 2678 Bypass Surrounding Abadies of Timber Market, Gujranwala 190.600 40.000 30.000 22.500 15.000 67% 29% Work in progress Schemes District Gujranwala Constructoin of Drains PCC / RCC in UC Kalaskay, On-going 1076 2679 Gujranwala 50.000 13.000 5.000 3.750 2.500 67% 31% Work in progress Banka, Ladheywala Cheema District Gujranwala Schemes Construction of Drains, PCC/RCC and Sullage On-going 1077 2680 Carrier in Villages of U.C Chianwali in District Gujranwala 30.000 9.848 8.333 6.250 4.167 67% 47% Work in progress Schemes Gujranwala Construction of Drains, PCC/RCC and Sullage On-going 1078 2681 Carrier in Villages of U.C Ladhaywala Goraya in Gujranwala 30.000 9.970 20.000 15.000 10.000 67% 67% Work in progress Schemes District Gujranwala Sewerage PCC Drainage in UC Malkay / UC Mari On-going 1079 2682 Gujranwala 80.000 23.483 5.000 3.750 2.500 67% 32% Work in progress Thakran / UC Ghoma in District Gujranwala Schemes Sewerage PCC Drainage in UC Talwandi MK / UC On-going 1080 2683 Gujranwala 60.000 29.963 5.000 3.750 2.500 67% 54% Work in progress Jandiala in District Gujranwala Schemes Water Supply / PCC / Drainage Facility in Sodhrar On-going 1081 2684 Gujranwala 134.586 18.000 20.000 26.218 21.218 81% 29% Work in progress Town, Tehsil Wazirabad, District Gujranwala Schemes Construction of Streets and Drainage at UC Marri On-going 1082 2685 Gujranwala 30.000 9.975 3.333 2.500 1.667 67% 39% Work in progress Thakran, District Gujranwala Schemes Construction of Streets and Drainage at UC Akbar On-going 1083 2686 Gujranwala 30.000 9.972 3.333 2.500 1.667 67% 39% Work in progress Ghanoke, District Gujranwala Schemes Construction of Streets and Drainage at UC On-going 1084 2687 Gujranwala 30.000 9.988 3.333 2.500 1.667 67% 39% Work in progress Ghaniya District Gujranwala Schemes Construction of Streets and Drainage at UC Guna On-going 1085 2688 Gujranwala 30.000 9.947 3.333 2.500 1.667 67% 39% Work in progress Aur District Gujranwala Schemes Construction of Streets and Drainage at UC On-going 1086 2689 Gujranwala 30.000 9.997 6.667 5.000 3.334 67% 44% Work in progress Ghoma/Harpoki District Gujranwala Schemes Construction of Streets and Drainage at UC On-going 1087 2690 Gujranwala 30.000 9.958 3.333 2.500 1.667 67% 39% Work in progress Machrala District Gujranwala Schemes Construction of Streets and Drainage at UC Sadoki On-going 1088 2691 Gujranwala 30.000 10.000 3.333 2.500 1.667 67% 39% Work in progress District Gujranwala Schemes Provision of Clean Water Facility in NA-95, District On-going 1089 2692 Gujranwala 200.000 66.995 5.000 3.750 2.500 67% 35% Work in progress Gujranwala Schemes Constructoin of Drains PCC / RCC in UC Botal On-going 1090 2693 Gujranwala 32.000 12.500 1.667 1.250 0.834 67% 42% Work in progress Jhanda Singh District Gujranwala Schemes Sewerage PCC Drainage in UC Mokhal / UC On-going 1091 2694 Gujranwala 80.000 23.412 3.333 2.500 1.667 67% 31% Work in progress Nadala / UC Feroz wala in District Gujranwala Schemes Sewerage PCC Drainage in UC Nangal Dona / UC On-going 1092 2695 Gujranwala 80.000 23.345 3.333 2.500 1.667 67% 31% Work in progress Machrala in District Gujranwala Schemes Sewerage PCC Drainage in UC Sohawa / UC Kali On-going 1093 2696 Gujranwala 60.000 19.898 3.333 2.500 1.667 67% 36% Work in progress Suba in District Gujranwala Schemes Sewerage PCC Drainage in UC Sadhoki / UC On-going 1094 2697 Gujranwala 80.000 23.473 5.000 3.750 2.500 67% 32% Work in progress Gunaur / UC Mandiala Tega in District Gujranwala Schemes Construction of Drains,PCC Sullage Carrier UC On-going 1095 2698 Budha Graya Tehsil Nowshera Virkan District Gujranwala 20.000 9.953 3.333 2.500 1.667 67% 58% Work in progress Schemes Gujranwala Construction of Drains,PCC Sullage Carrier UC On-going 1096 2699 Boopra Kalan Tehsil Nowshera Virkan District Gujranwala 20.000 9.897 3.333 2.500 1.667 67% 58% Work in progress Schemes Gujranwala Construction of Drains,PCC Sullage Carrier UC On-going 1097 2700 Tatlay Aali Tehsil Nowshera Virkan District Gujranwala 20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress Schemes Gujranwala Construction of Drains,PCC Sullage Carrier UC On-going 1098 2701 Matto Bbajme Tehsil Nowshera Virkan District Gujranwala 20.000 9.858 3.333 2.500 1.667 67% 58% Work in progress Schemes Gujranwala Construction of Drains,PCC Sullage Carrier UC On-going 1099 2702 Karyl Kalan Tehsil Nowshera Virkan District Gujranwala 20.000 9.997 3.333 2.500 1.667 67% 58% Work in progress Schemes Gujranwala Provision of PCC / Sewerage / Drainage /Tuff Tiles On-going 1100 2703 and allied facilities etc. in NA-101, District Gujranwala 100.000 28.000 5.000 3.750 2.500 67% 31% Work in progress Schemes Gujranwala Provision of Water Filtration Plant / Drainage On-going 1101 2704 System Chak Chatha U/C no. 15, District Hafizabad 30.860 10.000 3.333 2.500 1.667 67% 38% A.A.30.860 (M) T.S. 30.860 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Constrcutinn of Drain / Nallah / PCC / Soling On-going 1102 2705 Bateray, Kotli Amir Singh, Kallairwala, Muradian Hafizabad 50.000 19.999 3.333 2.500 1.667 67% 43% A.A. 50.000 (M)T.S. 50.000 (M) work is in progress Schemes Fund release but not yet online. U/C Sagar Khan, no. 12, District Hafizabad

Constrcutinn of Drain / Nallah / PCC / Soling U/C On-going A.A. 50.000 (M) T.S. 50.000 (M) work is in progress 1103 2706 Hafizabad 50.000 20.000 3.333 2.500 1.667 67% 43% No. 5, District Hafizabad Schemes Fund release but not yet online. Constrcutinn of Drain / Nallah / PCC / Soling U/C On-going A.A. 50.000 (M) T.S. 50.000 (M) work is in progress 1104 2707 Hafizabad 50.000 19.810 3.333 4.167 3.334 80% 46% No. 14, District Hafizabad Schemes Fund release but not yet online. Constrcutinn of Drain / Nallah / PCC / Soling and On-going 1105 2708 Sewer in village Vanike Tarar U/C No. 3, District Hafizabad 50.000 20.000 3.333 2.500 1.667 67% 43% A.A. 50.000 (M) T.S. 50.000 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Rural Drainage Scheme Herdo Sagar, Dhnoi On-going 1106 2709 Dogran, Praim Kot, Batairay, Wingay and Hafizabad 25.005 10.000 5.002 2.352 1.090 46% 44% A.A. 25.002 (M) T.S. 25.002 (M) work is in progress Schemes Fund release but not yet online. Bashmolajat District Hafizabad Rural Drainage Scheme Dhunni, Jaidkey, Chak On-going 1107 2710 Chatha, Dahranwali, Thatha, Kharian, Peer Koot Hafizabad 25.002 9.999 5.001 3.751 2.490 66% 50% A.A. 25.002 (M) T.S.25.002 (M) work is in progress Schemes Fund release but not yet online. and Bashmolajat District Hafizabad

Construction of Streets Drains PCC/ Soling and On-going 1108 2711 Hafizabad 20.000 10.000 3.333 4.000 1.667 42% 58% A.A. 20.000 (M) T.S. 20.000 (M)work is in progress Nallah In Vilaage Kassesy District Hafizabad Schemes Fund release but not yet online.

Construction of Streets Drains PCC/ Soling and On-going 1109 2712 Hafizabad 20.000 9.925 3.333 2.500 1.660 66% 58% A.A. 20.000 (M) T.S. 20.000 (M) work is in progress Nalla In Village Tibba Shah Balol District Hafizabad Schemes Fund release but not yet online.

Construction of Streets Drains PCC/ Soling and On-going 1110 2713 Hafizabad 20.000 9.978 3.333 2.500 1.660 66% 58% A.A. 20.000 (M)T.S.20.000 (M) work is in progress Nallah In Village Kot Khush hall District Hafizabad Schemes Fund release but not yet online. Construction of Streets Drains PCC/ Soling and On-going 1111 2714 Nallah In Village Tali Goraya and Jasso ke District Hafizabad 25.000 9.763 5.000 3.750 2.490 66% 49% A.A. 25.000 (M) T.S. 25.000 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Construction of Streets Drains PCC/ Soling and On-going 1112 2715 Nallah In Village Narowal Dera Jaat District Hafizabad 20.000 10.000 3.333 2.500 1.660 66% 58% A.A. 20.000 (M) T.S. 20.000 (M) work in progress. Schemes Fund release but not yet online. Hafizabad Construction of Streets Drains PCC/ Soling and On-going 1113 2716 Hafizabad 15.000 10.000 1.667 1.250 0.830 66% 72% A.A. 15.000 (M) T.S. 15.000 (M) work is in progress Nallah In Village Chak No. 474 District Hafizabad Schemes Fund release but not yet online.

Construction of Streets Drains PCC/ Soling and On-going 1114 2717 Hafizabad 15.000 9.719 1.667 0.750 0.330 44% 67% A.A. 15.000 (M) T.S. 15.000 (M) work is in progress Nallah In Village Matay Ke District Hafizabad Schemes Fund release but not yet online.

Construction of Streets Drains PCC/ Soling and On-going 1115 2718 Hafizabad 15.000 9.942 1.667 1.250 0.830 66% 72% A.A. 15.000 (M) T.S.15.000 (M) work is in progress Nallah In Village Badr Ali District Hafizabad Schemes Fund release but not yet online.

Construction of Streets Drains PCC/ Soling and On-going 1116 2719 Hafizabad 15.000 9.959 1.667 2.284 1.034 45% 73% A.A. 15.000 (M) T.S.15.000 (M) work is in progress Nallah In Village Mustafa Abad District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going 1117 2720 Hafizabad 36.585 11.209 3.333 2.500 1.660 66% 35% A.A. 36.585 (M) T.S.36.585 (M) work is in progress System Kolo Tarar U/C no. 8, District Hafizabad Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going 1118 2721 System Kot Said Muhammad U/C No. 1, District Hafizabad 31.854 11.999 3.333 2.500 1.667 67% 43% A.A. 31.854 (M) T.S.31.854 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Provision of Water Filtration Plant / Drainage On-going 1119 2722 Hafizabad 27.539 13.000 4.846 3.635 2.423 67% 56% A.A. 27.539 (M) T.S.27.539 (M) work is in progress System, Kot Ishaq U/C No. 2, District Hafizabad Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going 1120 2723 Hafizabad 61.830 20.000 6.667 5.000 3.330 67% 38% A.A. 61.830 (M) T.S.61.830 (M) work is in progress System Vanike Tarar U/C No. 3, District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going 1121 2724 Hafizabad 38.225 15.920 3.333 2.500 1.660 66% 46% A.A. 38.225 (M) T.S.38.225 (M) work is in progress System Alaudinkey U/C no. 4, District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going 1122 2725 Hafizabad 33.136 11.907 3.333 2.500 1.667 67% 41% A.A. 33.136(M) T.S.33.136 (M) work is in progress System Sooianwala U/C No. 5, District Hafizabad Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going 1123 2726 SystemRamke Chatha U/C no. 6, District Hafizabad 31.145 12.000 3.333 2.500 1.667 67% 44% A.A. 31.145(M) T.S.31.145 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Provision of Water Filtration Plant / Drainage On-going 1124 2727 System Dhiranke Lalke U/C no. 7, District Hafizabad 42.320 20.000 3.333 2.500 1.667 67% 51% A.A. 42.320(M) T.S.42.320 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Provision of Water Filtration Plant / Drainage On-going 1125 2728 System Sandhwan Tarar U/C no. 9, District Hafizabad 32.850 12.000 3.333 2.500 1.667 67% 42% A.A. 32.850(M) T.S.32.850 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Provision of Water Filtration Plant / Drainage On-going 1126 2729 Hafizabad 30.049 10.000 3.333 2.500 1.667 67% 39% A.A. 30.049(M) T.S.30.049 (M) work is in progress System Pind Bawray U/C no. 10, District Hafizabad Schemes Fund release but not yet online Provision of Water Filtration Plant / Drainage On-going 1127 2730 System Sagar Kalan U/C No. 12, District Hafizabad 28.414 10.000 6.138 4.604 3.069 67% 46% A.A. 32.850(M) T.S.32.850 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Provision of Water Filtration Plant / Drainage On-going 1128 2731 Hafizabad 34.675 11.996 3.333 0.833 0.000 0% 35% A.A. 34.675(M) T.S.34.675 (M) work is in progress System Dhunni U/C No. 14, District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going 1129 2732 Hafizabad 29.334 12.000 5.778 2.684 1.280 48% 45% A.A.29.334(M) T.S.29.334 (M) work is in progress System Kalianwala U/C no. 11, District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going 1130 2733 Hafizabad 28.045 12.000 5.348 7.061 5.724 81% 63% A.A. 28.045(M) T.S.28.045(M) work is in progress System Karyala U/C no. 19, District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going 1131 2734 Hafizabad 34.935 12.000 3.333 2.500 1.660 66% 39% A.A. 34.935(M) T.S.34.935 (M) work is in progress System kassoke U/C no. 20, District Hafizabad Schemes Fund release but not yet online.

Provision of Water Filtration Plant / Drainage On-going A.A. 27.257(M) T.S.27.257 (M) work is in progress 1132 2735 Hafizabad 27.257 10.000 5.752 4.314 2.876 67% 47% System Vinni U/C no. 16, District Hafizabad Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going 1133 2736 System Solangi Awan U/C no. 17, District Hafizabad 29.376 10.000 3.333 2.500 1.660 66% 40% A.A. 29.376(M) T.S.29.376 (M) work is in progress Schemes Fund release but not yet online. Hafizabad Provision of Water Filtration Plant / Drainage On-going A.A. 47.862(M) T.S.47.862 (M) work is in progress 1134 2737 Hafizabad 47.862 19.864 3.333 2.500 1.667 67% 45% System Kot Nakka Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going A.A. 29.486(M) T.S.29.486 (M) work is in progress 1135 2738 Hafizabad 29.486 9.971 3.333 2.500 1.660 66% 39% System Khana Bhattian Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going A.A. 35.920(M) T.S.35.920 (M) work is in progress 1136 2739 Hafizabad 35.920 14.993 3.333 2.500 1.667 67% 46% System Thata Jhaid Amirwala Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going A.A. 32.026(M) T.S.32.026 (M) work is in progress 1137 2740 Hafizabad 32.026 11.910 3.333 2.500 1.660 66% 42% System North Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going A.A. 53.655(M) T.S.53.655 (M) work is in progress 1138 2741 Hafizabad 53.655 20.000 3.333 2.500 1.650 66% 40% System Kot Sarwer Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going A.A. 25.650(M) T.S.25.650 (M) work is in progress 1139 2742 Hafizabad 25.650 10.000 5.217 3.913 2.600 66% 49% System Mowan Bhattian Schemes Fund release but not yet online. Provision of Water Filtration Plant / Drainage On-going 1140 2743 Hafizabad 30.000 10.000 3.333 2.500 1.667 67% 39% A.A. 30.000(M) T.S.30.000 (M) work is in progress System Jalal Pur Bhattian in District Hafizabad Schemes Fund release but not yet online. Construction of PCC Street/ Drain, Soling and On-going 1141 2744 Nullah in UC Fatta Band Tehsil Kharian District Gujrat 20.027 10.000 3.342 2.507 1.671 67% 58% A.A Date =28.7.2017.Drain Type-I=6937 Rft. PCC. Schemes 1:2:4=1000 Cft.Soling= 2741sft .Work in progress. Gujrat Construction of PCC Street/ Drain, Soling and Nullah in U.C's Mirza Tahir, Nona Wali, Bumali, Kolian Shah Hussain, Jora Kamana, Haji On-going A.A Date =28.8.2017.Drain Type-I=6359 Rft. PCC. 1142 2745 Gujrat 69.000 19.985 3.333 2.500 1.667 67% 31% 1:2:4=43123 Cft.Soling= 8900 sft.Nullah 2x2=400 Muhammad, Sikaryali, Chakori Bhailwal, Schemes Rft.Work in progress. Warraichanwala, Nagranwala, Ali Chak, Kulewa, Taplyala, Chak Pind in Tehsil Kharian Provisino of Sewerage / Drainage / Soling etc in On-going A.A Date =28.8.2017.Drain Type-I=4629 Rft. PCC. 1143 2746 Gujrat 50.000 25.000 1.667 1.250 0.834 67% 52% 1:2:4=46666 Cft.Soling= 15646 sft .Nullah Various UC's in PP-113, District Gujrat Schemes 2'x2'=100.Work in progress. Exten: Construction of PCC Street / Drain, Soling, A.A Date =28.8.2017.1 Nos T/Well installed. Pipe On-going 1144 2747 Nullah and Eten: of Water Supply Scheme Fath Gujrat 81.151 22.000 3.333 2.500 1.667 67% 29% 6"=10384 Rft, 4"=5678 Rft, 3'=14560 rft. Schemes Soling=34508 sft, Nullah 2'x2'=1019 Rft. Work in Bhand Tehsil Kharian District Gujrat porgress. Rural Water Supply and Drainage Scheme Morala On-going 1 Nos T/Well installed.PVC Pipe of dias 3" =8032 1145 2748 Gujrat 30.000 9.748 3.333 2.500 1.667 67% 38% Rft,4"= 5789 Rft,6"= 3074 Rft.PCC 6581 Cft. Work Tehsil Kharian District Gujrat Schemes in porgress. Construction of PCC Street / Drain, Soling and Nullah in U.C Gunjah, Thekarian Matwanawala, Miana Chak, Punjan Khasana, Khawaspur, On-going A.A Date =28.8.2017.Drain Type-I=9351 Rft. PCC. 1146 2749 Gujrat 60.990 20.000 3.333 2.500 1.667 67% 36% 1:2:4=41644 Cft.Soling= 17354 sft .Tuff Bhaddhar, Kotla Qasim Khan, Chakor Sher Ghazi, Schemes paver=4727. Work in progress. Deona Mandi, 1 & 2 Dinga, Addowal, Saroki, Machiana in Tehsil Kharian Distric Construction of PCC Street / Drain, Soling and On-going A.A Date =28.7.2017.Drain Type-I= 1919 Rft. PCC. 1147 2750 Nullah in U.C 1 to 4 Lalamusa City Tehsil Kharian Gujrat 18.400 10.000 2.800 2.100 1.400 67% 62% 1:2:4=18061 Cft .Tuff paver=16112. Work in Schemes District Gujrat progress. Construction of PCC Street/ Drain, Soling and Nullah in Bagrianwala, Baho Ghaseet Pur, Sheikh On-going 1148 2751 Gujrat 27.604 15.000 3.333 2.500 1.667 67% 60% A.A Date =28.7.2017.Drain Type-I=8360 Rft. PCC. Sukha, Sabowal, Amra Kalan, Chak Jani in Tehsil Schemes 1:2:4=28683 Cft.Work in progress. Kharian District Gujrat Provision of Streets and Drains in UC's Chak Sada, Mandhiyala, Thatha Musa, Chopala, Bharaj, On-going A.A Date =28.8.2017.Drain Type-I=11013 Rft. PCC. 1149 2752 Thim Ke, Manju Chak, Ikhlas Garh, Fateh Pur, Gujrat 60.000 22.000 3.333 5.000 4.167 83% 44% 1:2:4=52773 Cft.Sullage Carriar=1470 Rft.Work in Schemes Daulta Nagar, Alam Garh, Doga, Chachian, Jaura progress. Jalalpur and Dhuma Malka District Gujrat Sewerage Scheme Jail Chowk to Bhimber Nullah, On-going 1150 2753 Gujrat 249.994 49.952 3.333 2.500 1.667 67% 21% A.A Date =17.3.2018.work in progress Gujrat City District Gujrat Schemes Construction of Nallahs in city Sarai Alamgir On-going 1151 2754 Gujrat 82.600 22.195 3.333 1.580 0.747 47% 28% PCC.1:2:4=63195 Cft.Work in progress. District Gujrat Schemes A.A Date =29.12.2017.Drain Type-I=17111 Rft. Provision of Sewerage / Drainage and streets / Tuff On-going 1152 2755 Gujrat 480.000 44.979 6.667 13.420 11.754 88% 12% PCC. 1:2:4=95620Cft.Tuff paver= 53179 sft .Nullah Tiles etc in various UCs, District Gujrat Schemes 1.5'x1.5'=1078.RCC pavement=13422 cft.Work in progress. Sewerage / Drainage / PCC & Brick Pavement Scheme in villages Adda PharIanwall, HaIgher Khurd,Haslanwala,pindl Kalu,Loha Tibba ,Chak Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 1153 2756 30.000 11.977 3.333 4.500 3.667 81% 52% Date. 06.01.2018* Completion date 05.01.2019* Jano Khurd, Thatha Hast, Luk, Thatha Pheray, Bahauddin Schemes Work in progress. Rajoa, Baghanwala,kot Sattar Duborji, Kotli Qazl, Sandanwala, Charranwala a Sewerage / Drainage / PCC & Brick Pavement Scheme in villages kailu, tuggal, channi syedian, Ratoo, bahri, Chak Kamal, Melu Mahi Gheran, Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 1154 2757 30.000 9.021 3.333 2.500 1.667 67% 36% Date. 06.01.2018* Completion date 05.01.2019* Aghroa, Kotha Bhola, Maseetwali Komokay, Chak Bahauddin Schemes Work in progress. Mitha, Heigherwala, Kot Phollay shah, Chak Zahir, Bahu, Manga, Arzani, S

Construction of Street Drains, Soling and PCC in Village Gajjan, Slianman, Kot Hamid Shah, Jhanda Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 1155 2758 Chohan, Rasul Pur, Chicheranwali, Bhinder Kalan, 23.000 8.494 4.333 3.250 2.167 67% 46% Date. 06.01.2018* Completion date 05.01.2019* Bahauddin Schemes Bhinder Khurd, Chakora, Thatha Alia and Thatha Work in progress. Naik District M B Din

Construction of Street Drains, Soling and PCC in Village Bhagat, Thathi Mureed Sahnpal, Channi Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 1156 2759 26.500 14.991 3.833 3.375 2.417 72% 66% Date. 06.01.2018* Completion date 05.01.2019* Sahnpal, Ranaml, Sharif Channi Mahram, Qila Bahauddin Schemes Work in progress. Attar Singh, Ghagoki and Sarang District M B Din Construction of Street Drains, Soling and PCC in Village Narrang, Saad Ullah Pur, Kot Pejo, Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 1157 2760 26.000 9.541 5.333 5.390 4.057 75% 52% Date. 06.01.2018* Completion date 05.01.2019* Karamawala, Dhudra, Long Charrhkey, Khoosar Bahauddin Schemes Work in progress. and Pindi Dotharan District M B Din Construction of Street Drains, Soling and PCC in Village Dhaul, Kotly Khurd, Khiyyan, Chak Jano Mandi On-going * A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start 1158 2761 New Abadies, Addu Sarwani, Sheikh Alipur, 31.500 9.595 7.167 9.825 8.034 82% 56% Date. 06.01.2018* Completion date 05.01.2019* Bahauddin Schemes Ransikey, , Sainthal and saida Saghar Work in progress. District M B Din Construction of PCC / Drainage, UC Chobara On-going 1159 2762 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. District Sialkot Schemes Construction of PCC / Drainage, US Kingra District On-going 1160 2763 Sialkot 20.000 10.000 3.333 1.000 0.698 70% 53% Work in progress. Sialkot Schemes Construction of PCC / Drainage, UC Dogri District On-going 1161 2764 Sialkot 15.000 7.500 2.500 1.875 1.250 67% 58% Work in progress. Sialkot Schemes Construction of PCC / Drainage, UC Balagan On-going 1162 2765 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. District Sialkot Schemes Construction of PCC / Drainage, UC Malipur On-going 1163 2766 Sialkot 20.000 10.000 3.333 1.500 0.987 66% 55% Work in progress. District Sialkot Schemes Construction of PCC / Drainage, UC Talawandi, On-going 1164 2767 Sialkot 20.000 9.100 3.333 2.000 1.568 78% 53% Work in progress. District Sialkot Schemes Construction of PCC / Drainage, UC Chacharwali On-going 1165 2768 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. District Sialkot Schemes Construction of PCC / Drainage, UC Klasswala, On-going 1166 2769 Sialkot 20.000 10.000 3.333 1.000 0.689 69% 53% Work in progress. District Sialkot Schemes Construction of PCC / Drainage, UC Jodhala, On-going 1167 2770 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. District Sialkot Schemes Construction of PCC, Street Drain/ Nullah Village Kundan Pur Bashmola Tahthi Minderwal, Chan, On-going 1168 2771 Sialkot 48.000 18.000 3.333 2.500 1.667 67% 41% Work in progress. Khany Chak, Kajlewal, Mahal Tajer, Ossomata and Schemes Khurra Construction of PCC, Street Drain/ Nullah Village Chakrala Bashmula Machrala, Nandpurn Rang On-going 1169 2772 Sialkot 49.000 20.000 3.333 2.500 1.667 67% 44% Work in progress. Khokhran, Lalian, Gaiat, Bahadur and Madina Schemes Town. Construction of PCC, Streets Drains, Tuff Tiles and On-going 1170 2773 Sialkot 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress. Soling in UC Marakiwall in District Sialkot. Schemes Construction of PCC, Streets Drains, Tuff Tiles and On-going 1171 2774 Sialkot 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress. Soling in UC Berth in District Sialkot Schemes

Construction of PCC, Streets Drains, Tuff Tiles and On-going 1172 2775 Sialkot 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress. Soling in UC Booth in District Sialkot Schemes

Construction of PCC, Streets Drains, Tuff Tiles and On-going 1173 2776 Sialkot 12.000 9.000 1.000 0.750 0.500 67% 79% Work in progress. Soling in UC Machranal in District Sialkot Schemes Construction of Streets / Drain / Nullah / Soling / On-going 1174 2777 Tuff Tiles / PCC at UC Dhilum Balagon, District Sialkot 25.000 8.000 1.667 1.250 0.834 67% 35% Work in progress. Schemes Sialkot Construction of Streets / Drain / Nullah / Soling / Tuff Tiles / PCC at Fardaus Pura, Nand Garh, On-going 1175 2778 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Wan, Dhoop Sarri, Kotli Miani, Malkhanwala, Schemes District Sialkot Construction of Streets / Drain / Nullah / Soling / On-going 1176 2779 Tuff Tiles / PCC at UC Bhopalwala Tehsil Sialkot 50.000 19.399 3.333 2.500 1.667 67% 42% Work in progress. Schemes Sambrial, District Sialkot Construction of Streets / Drain / Nullah / Soling / On-going 1177 2780 Sialkot 20.000 7.000 1.667 1.250 0.834 67% 39% Work in progress. Tuff Tiles / PCC at UC Alleali, District Sialkot Schemes Construction of Streets / Drain / Nullah / Soling / Tuff Tiles / PCC at Villages Mundair Syedian, On-going 1178 2781 Sialkot 25.000 8.000 1.667 1.250 0.834 67% 35% Work in progress. Mundair Khothay, Roras, Sohowala, Kharolian etc., Schemes District Sialkot Construction of Streets / Drain / Nullah / Soling / On-going 1179 2782 Tuff Tiles / PCC at UC Berowala Tehsil Daska, Sialkot 40.000 12.000 3.333 2.500 1.667 67% 34% Work in progress. Schemes District Sialkot Construction of Streets / Drain / Nullah / Soling / On-going 1180 2783 Sialkot 20.000 7.000 1.667 1.250 0.834 67% 39% Work in progress. Tuff Tiles / PCC at UC Bagowala , District Sialkot Schemes

Construction of Streets / Drain / Nullah / Soling / On-going 1181 2784 Sialkot 149.892 20.000 3.333 2.500 1.667 67% 14% Work in progress. Tuff Tiles / PCC at UC Ghuinke, District Sialkot Schemes

Construction of Streets / Drain / Nullah / Soling / On-going 1182 2785 Sialkot 40.000 12.000 3.333 2.500 1.667 67% 34% Work in progress. Tuff Tiles / PCC at UC Bharokey, District Sialkot Schemes Construction of sewerage, Nallah, PCC at UC On-going 1183 2786 Sialkot 20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress. Prochak and Alo Mahr District Sialkot. Schemes Construction of Streets / Sewerage / Tuff Tile/ On-going 1184 2787 Sialkot 100.000 29.967 3.333 2.500 1.667 67% 32% Work in progress. PCC/ Soling in Rural UC's of NA-113 Schemes Construction of PCC, Soling / Drains in Villages of On-going 1185 2788 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. UC in Ghutalian District Sialkot Schemes Construction of PCC, Soling / Drains in Villages of On-going 1186 2789 Sialkot 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress. UC in Chichar wali District Sialkot Schemes Construction of PCC, Soling / Drains in Villages of On-going 1187 2790 Sialkot 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress. UC in Pejoke Qila Kalarwala District Sialkot Schemes Construction of Streets, Nullah, PCC, Soling at villages Jasso Wali Pun, Sahn Gill, pajokay, Mehmand Wali, Rata jathool, Baso Panu, alawal On-going 1188 2791 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. Pur, Loharan Wali, Jhangi Shah Khaki, Jhans, Schemes Sodian, Bhuda, Peera Baryar, Charwind, Deehr, Bhojo, Alkry, Kala Pahar, Construction of PCC, Soling / Drains in Villages of On-going 1189 2792 Sialkot 25.000 12.000 1.667 1.250 0.834 67% 51% Work in progress. UC Sokan Wind District Sialkot Schemes Construction of Streets, Drains PCC/ Soling / Tuff Tiles in Villages of UC's Kanwanlit, Adamkey On-going 1190 2793 Cheema, Raja Gamman, Galotian Kalan, Galotian Sialkot 120.000 45.000 3.333 2.500 1.667 67% 39% Work in progress. Schemes Khurd, Goindkey, Banbanwala, Bharokey and Mitranwali Tehsil Daska District Sialkot Constructon of Streets / Drain / Nullah / Soling at On-going 1191 2794 UC, Moongar, Baqarpur, Pindi Khokharn etc., Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. Schemes District Sialkot Constructon of Streets / Drain / Nullah / Soling at, On-going 1192 2795 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. UC Kapoor Wali and Khamberwala District Sialkot Schemes Constructon of Streets / Drain / Nullah / Soling at On-going 1193 2796 Village Satab Garah, Butter, Dhanney, Ganjaniwali Sialkot 30.000 10.000 3.333 2.500 1.667 67% 39% Work in progress. Schemes etc. District Sialkot Construction of Street / Swerage / Tuff Tile ETC in On-going 1194 2797 Sialkot 50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress. City Daska District Sialkot Schemes Construction of PCC/Streets/Nalian at U.C. On-going 1195 2798 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Syedanwali District Sialkot Schemes Construction of PCC/Streets/Nalian at U.C.Pargpur On-going 1196 2799 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. District Sialkot Schemes Construction of PCC/Streets/Nalian at U.C. Vario On-going 1197 2800 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. District Sialkot Schemes Construction of PCC/Streets/Nalian at U.C On-going 1198 2801 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Rasoolpur Balian District Sialkot Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1199 2802 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Kotli Barham Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1200 2803 Sialkot 30.000 15.000 1.667 1.250 0.834 67% 53% Work in progress. Lines in UC Paka Garh Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1201 2804 Sialkot 30.000 15.000 1.667 1.250 0.834 67% 53% Work in progress. Lines in UC Maina Pura Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1202 2805 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Muzafar Pur Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1203 2806 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Fathegarh Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1204 2807 Sialkot 20.000 9.995 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Haji Pura Ban Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1205 2808 Sialkot 20.000 9.986 3.333 1.000 0.660 66% 53% Work in progress. Lines in UC Imam Saheb Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1206 2809 Sialkot 20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Mubarik Pura Schemes Provision of PCC / Sewerage / Tuff Tiles / On-going 1207 2810 Drainage and allied facilities in PP-122, District Sialkot 100.000 44.992 3.333 2.500 1.667 67% 47% Work in progress. Schemes Sialkot Provision of PCC / Sewerage / Tuff Tiles / On-going 1208 2811 Drainage and allied facilities in PP-123, District Sialkot 199.950 100.000 3.333 2.500 1.667 67% 51% Work in progress. Schemes Sialkot Construction of PCC, Street Drain/ Nullah Village Jallian Wala Bashamula Moma Khurd, Kalan On-going 1209 2812 Sialkot 47.000 18.000 3.333 2.500 1.667 67% 42% Work in progress. Virkan, Dulchikay, Lodhary Dogranwala and Rai Schemes Pur. Construction of PCC, Street Drain/ Nullah Village On-going 1210 2813 Ghari Gondal Bashmula Ahmal Pur, Sarhall, Sialkot 47.000 17.936 1.667 1.250 0.834 67% 40% Work in progress. Schemes Hadali, Minal Pathan, Bazpur and Romal Juttan. Construction of PCC, Street Drain/ Nullah Village On-going 1211 2814 Baghwal Awan Bashmula Harar, Noul, Dumbola Sialkot 46.000 17.956 5.000 1.350 0.903 67% 41% Work in progress. Schemes and Dogran. Construction of sewerage, Nallah, PCC at UC On-going 1212 2815 Sialkot 20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress. Jaranwala and Barthanwala, District Sialkot Schemes

Construction of sewerage, Nallah, PCC at UC On-going 1213 2816 Sialkot 20.000 10.938 3.000 2.250 1.500 67% 62% Work in progress. Salhokay and Bhuda Gorya, District Sialkot Schemes

Construction of sewerage, Nallah, PCC at UC On-going 1214 2817 Sialkot 20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress. Mundekay Gorya and Malomay, District Sialkot Schemes Construction of sewerage, Nallah, PCC at UC On-going 1215 2818 Sialkot 20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress. Boghray and Seo Ke, District Sialkot. Schemes Construction of sewerage, Nallah, PCC at UC On-going 1216 2819 Sialkot 20.000 12.000 2.667 2.000 1.334 67% 67% Work in progress. Adha and Sehjo Kala District Sialkot. Schemes Construction of sewerage, Nallah, PCC at UC On-going 1217 2820 Sialkot 15.000 9.941 1.667 1.250 0.834 67% 72% Work in progress. Ghuainkey and Badoke Cheema, District Sialkot. Schemes

Construction of sewerage, Nallah, PCC at UC On-going 1218 2821 Sialkot 15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress. Jamkay Cheema and Kanwanliq, District Sialkot. Schemes Construction Street Drain PCC / and Nullah U/C On-going 1219 2822 Sialkot 20.000 10.000 3.333 4.534 3.701 82% 69% Work in progress. Jaithke Schemes Construction of Street Drain PCC / and Nullah U/C On-going 1220 2823 Sialkot 20.000 9.920 3.333 2.500 1.667 67% 58% Work in progress. Kopra Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1221 2824 Sialkot 40.000 14.963 3.333 2.500 1.667 67% 42% Work in progress. Lines in UC Dalowali Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1222 2825 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Lines in UC Talwara Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1223 2826 Sialkot 20.000 9.968 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Pindi Arian Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1224 2827 Sialkot 30.000 9.920 1.667 1.250 0.834 67% 36% Work in progress. Lines in UC Hamza Ghous Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1225 2828 Sialkot 20.000 9.987 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Naika Pura Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1226 2829 Sialkot 20.000 9.937 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Duborji Arian Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1227 2830 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Lines in UC Ahmed Pura Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1228 2831 Sialkot 20.000 9.970 3.333 2.500 1.667 67% 58% Work in progress. Lines in UC Pura Hiran Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1229 2832 Sialkot 40.000 15.000 3.333 2.500 1.667 67% 42% Work in progress. Lines in UC Rangpura Schemes Providing & Laying of Tuff Tile PCC and Drainge On-going 1230 2833 Sialkot 20.000 9.700 3.333 2.500 1.667 67% 57% Work in progress. Lines in UC Islam Abad Schemes Construction of Street Drain PCC/ and Nullah UC On-going 1231 2834 Sialkot 30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress. Majra Kalan Schemes Construction of Street Drain PCC / and Nullah U/C On-going 1232 2835 Sialkot 20.000 10.000 3.333 7.500 6.667 89% 83% Work in progress. Village Srankey Schemes Construction of Street Drain PCC/ and Nullah On-going 1233 2836 Sialkot 80.000 30.000 1.667 1.250 0.834 67% 39% Work in progress. U/C’s Verowala, Halewai, Habibpur Schemes Construction of sewerage, PCC, Tuff Tile, District On-going 1234 2837 Sialkot 50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress. Sialkot Schemes Construction of PCC & Drains in Village Chobara On-going 1235 2838 Sialkot 15.000 5.000 3.333 2.500 1.667 67% 44% Work in progress. U/C Chobara District Sialkot Schemes Construction of Drainage System, PCC and Brick On-going "A.A. dated 07.08.2017 T.S. dated 08.08.2017 Start 1236 2839 Pavement in Villages of UC Rupo Chak Tehsil Narowal 12.000 4.993 2.000 1.500 0.999 67% 50% Date 28.09.2017 *Completion date 30.06.2019work Schemes Zafarwal District Narowal in progress. Fund not received on spending end yet. "A.A. dated 03.08.2017 T.S. dated 12.08.2017 *Start Date 27.10.2017 *Completion date 30.06.2019 work in progress. "A.A. dated Provision of Drains/Soling and PCC in UCs, On-going 03.08.2017 T.S. dated 12.08.2017 *Start Date 1237 2840 Datewal, Mangolay, Hallowal, Dhrug Miana and Narowal 30.000 12.308 3.333 2.500 1.659 66% 47% 27.10.2017 *Completion date 30.06.2019 work in Schemes Ghota Fateh Garh District Narowal progress. "A.A. dated 03.08.2017 T.S. dated 12.08.2017 *Start Date 27.10.2017 *Completion date 30.06.2019 work in progress.Fund not recived on spending end yet Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated 12.08.2017 On-going 1238 2841 Talwandi Bhindran, Giddan, Niddokay, Kot Lakha Narowal 30.000 9.960 3.333 2.500 1.661 66% 39% *Start Date 27.10.2017 *Completion date Schemes 30.06.2019 Work in progress. Fund not receive on Singh and Domala, District Narowal spending end yet. "A.A. dated 03.08.2017 T.S. dated 12.08.2017 *Start Date 27.10.2017 *Completion date 30.06.2019 Work in progress. "A.A. dated Provision of Drains/Soling and PCC in UCs, Khan On-going 03.08.2017 T.S. dated 12.08.2017 *Start Date 1239 2842 Kassa, Dongian, Bubak Murali, Sadowala Uncha Narowal 30.000 9.871 3.333 2.500 1.664 67% 38% 27.10.2017 *Completion date 30.06.2019 Work in Schemes and Falezpur District Narowal progress"A.A. dated 03.08.2017 T.S. dated 12.08.2017 *Start Date 27.10.2017 *Completion date 30.06.2019 Work in progress. Funds not received on spending end yet. Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated 12.08.2017 On-going 1240 2843 Ahmadabad, Depokey, Jestiwala, Uncha, Lala and Narowal 30.000 9.940 3.333 2.500 1.659 66% 39% *Start Date 27.10.2017 *Completion date Schemes 30.06.2019 Work in progress. Funds not received Nonar, District Narowal on spending end yet Provision of Drains/Soling and PCC in UCs, Mehlu "A.A. dated 03.08.2017 T.S. dated 12.08.2017 On-going 1241 2844 Wala, Dhamthal, Langarkay, Tapiala and Narowal 30.000 9.940 3.333 2.500 1.663 67% 39% *Start Date 27.10.2017 *Completion date Schemes 30.06.2019 Work in progress. Funds not received Sankhtara District Narowal on spending end yet Provision of PCC/Streets/Nalian at Bado Malihi, Chandarkay, Ransiwal, Manak, Qayampur, Agrian, On-going "A.A. dated 19.10.17 T.S. dated*Start Date 1242 2845 Narowal 130.000 34.991 6.667 5.000 3.320 66% 29% 18.10.2017 *Completion date 30.06.2019 Work in Pungarian, Salukay, Dawod, Chundowal, Klass Schemes progress. Funds not received on spending end yet. Gorya, Muhammad Rana Wala District Narowal

Provision of Tuff Tile from Zafarwal bypass to On-going "A.A Date.03.08.2017 T.S Date*18.09.2017 Start 1243 2846 Narowal 22.000 9.965 4.000 3.000 1.994 66% 54% Date 28.09.2017*Completion date 30.06.2019 Work Chowk Ghas Mandi, District Narowal Schemes in progress. Funds not received on spending end yet Construction of Drainage System, PCC and Brick On-going "A.A. dated 03.08.17T.S. dated 08.08.2017*Start 1244 2847 Pavement in Villages of Jandiala Tehsil Zafarwal Narowal 15.000 4.993 3.333 2.500 1.661 66% 44% Date 18.08.2017*Completion date 30.06.2019 Work Schemes District Narowal in progress. Fund not received on spending end yet. "A.A. dated 03.08.17 T.S. dated 08.08.2017 *Start Provision of PCC / Sewerage / Drainage etc. in PP- On-going 1245 2848 Narowal 25.000 9.812 1.667 1.250 0.831 66% 43% Date 18.08.2017 *Completion date 30.06.2019 133, District Narowal Schemes Work in progress. Funds not received on spending end yet. PCC & Drainage & Sewerage System at UC-273, On-going 1246 2849 Lahore 50.000 38.992 3.667 5.090 4.174 82% 86% Work stopped due to awaiting funds. Raiwind City, Lhr Schemes PCC & Drainage & Sewerage System at UC-112, On-going 1247 2850 Lahore 50.000 39.986 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. Mustafa Town, Schemes Provision of PCC & Drainage Facilities in Attari & On-going 1248 2851 Lahore 50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed allied abadies. Schemes Provision of PCC & Drainage Facilities in On-going 1249 2852 Youhanabad, Dhullu Kalan & Khurd & allied Lahore 50.000 39.987 3.333 3.400 2.567 76% 85% Work stopped due to awaiting funds. Schemes abadies. Provision of PCC & Drainage Facilities in On-going 1250 2853 Lahore 50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed Gajjumatta & allied abadies. Schemes Provision of PCC & Drainage Facilities in Bhallar & On-going 1251 2854 Lahore 50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed allied abadies. Schemes Provision of PCC & Drainage Facilities in Dhalloki On-going 1252 2855 Lahore 50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed & allied abadies. Schemes Provision of PCC & Drainage Facilities in Jhulkey On-going 1253 2856 Lahore 50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed & allied abadies. Schemes Provision of PCC & Drainage Facilities in Jaman On-going 1254 2857 Lahore 50.000 40.000 3.333 2.500 1.667 67% 83% Scheme completed and Gawind & allied abadies. Schemes Provision of PCC & Drainage Facilities in On-going 1255 2858 Lahore 50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed Shahzada & allied abadies. Schemes Provision of PCC & Drainage Facilities in Jia On-going 1256 2859 Lahore 50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed Bhagga & allied abadies. Schemes Provision of PCC & Drainage Facilities in Pandoki On-going 1257 2860 Lahore 50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed & allied abadies. Schemes Provision of PCC & Drainage Facilities in Hair & On-going Work stopped due to awaiting funds. Revised PC-I 1258 2861 Lahore 73.000 54.100 3.333 0.900 0.067 7% 74% allied abadies. Schemes is under review with DDWP. Construction of Sewerage and Disposal Manawan On-going 1259 2862 Lahore 50.000 20.000 3.333 2.500 1.667 67% 43% Work stopped due to awaiting funds. Sky Land & Abadies Schemes Construction of PCC/Sewerage and Link Streets On-going 1260 2863 Lahore 50.000 34.992 5.000 3.750 2.500 67% 75% Work stopped due to awaiting funds. UC-147 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1261 2864 Lahore 50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. UC-148 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1262 2865 Lahore 50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. UC-149 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1263 2866 Lahore 50.000 39.992 3.333 2.300 1.467 64% 83% Work stopped due to awaiting funds. UC-150 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1264 2867 Lahore 50.000 39.538 3.333 2.400 1.567 65% 82% Work stopped due to awaiting funds. UC-151 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1265 2868 Lahore 50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. UC-152 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1266 2869 Lahore 50.000 29.984 3.333 2.500 1.667 67% 63% Work stopped due to awaiting funds. UC-174 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1267 2870 Lahore 50.000 39.991 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. UC-175 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1268 2871 Lahore 50.000 39.991 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. UC-183 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going 1269 2872 Lahore 50.000 34.968 5.000 3.750 2.500 67% 75% Work stopped due to awaiting funds. UC-108 Lahore. Schemes Construction of PCC/Sewerage and Link Streets On-going Scheme completed physically, funds are required to 1270 2873 Lahore 100.000 75.000 5.000 3.750 2.500 67% 78% Bhangali Lahore. Schemes clear the contractor liabilities. PCC & Drainage & Sewerage System at UC-110, On-going 1271 2874 Lahore 50.000 39.977 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. Niaz Baig Lahore Schemes PCC & Drainage & Sewerage System at UC-111, On-going 1272 2875 Lahore 50.000 39.273 3.573 2.680 1.787 67% 82% Work stopped due to awaiting funds. Hunjarwal, Lahore Schemes PCC & Drainage & Sewerage System at UC-109, On-going 1273 2876 Lahore 50.000 39.493 3.500 2.625 1.750 67% 82% Work stopped due to awaiting funds. Margzaar Colony, Lahore. Schemes PCC & Drainage & Sewerage System at UC-117, On-going Scheme completed physically, funds are required to 1274 2877 Lahore 50.000 45.000 1.667 1.250 0.834 67% 92% Shahpur Kanjran, Lahore. Schemes clear the contractor liabilities. PCC & Drainage & Sewerage System at UC-262, On-going 1275 2878 Lahore 50.000 29.989 1.667 1.050 0.634 60% 61% Work stopped due to awaiting funds. Shamke Bhattian, Lahore. Schemes PCC & Drainage & Sewerage System at UC-255, On-going 1276 2879 Lahore 50.000 31.995 1.667 5.250 4.834 92% 74% Work stopped due to awaiting funds. Sattu Kattla, Lahore Schemes PCC & Drainage & Sewerage System at UC-256, On-going 1277 2880 Lahore 50.000 39.556 3.333 2.500 1.667 67% 82% Work stopped due to awaiting funds. Ali Raza Abad, Lahore Schemes PCC & Drainage & Sewerage System at UC-272, On-going Physically scheme is completed, balance funds are 1278 2881 Lahore 50.000 40.000 3.333 5.000 4.167 83% 88% Raiwind Kalan, Lahore Schemes required to clear the contractor's liability Provision of PCC & Drainage in Streets UC-176 On-going 1279 2882 Lahore 50.000 39.800 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. Awan Dhai Wala Lahore. Schemes Provision of PCC & Drainage in Streets UC-190 On-going 1280 2883 Lahore 50.000 39.620 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. Hadiara Lahore. Schemes Provision of PCC & Drainage in Streets UC-180 On-going 1281 2884 Lahore 50.000 39.599 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. Minhala Kallan Lahore. Schemes Provision of PCC & Drainage in Streets UC-181 On-going 1282 2885 Lahore 50.000 39.977 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds. Wahga Lahore. Schemes Provision of PCC & Drainage in Streets UC-194 On-going 1283 2886 Lahore 50.000 40.000 3.333 0.870 0.037 4% 80% Scheme completed Lidhar Lahore. Schemes Provision of clean drinking water, sewerage On-going 1284 2887 system, PCC and allied facilities in Manga Mandi, Lahore 300.000 137.599 8.333 6.250 4.167 67% 47% Work stopped due to awaiting funds. Schemes Raiwind Village and adjoining Abadies. Construction of PCC, Soling, Drain & Nallah at On-going 1285 2888 Sheikhupura 15.000 2.500 1.667 1.250 0.834 67% 22% Work in Progress Tibbi Humbo, UC 64, District Sheikhupura Schemes Provision of PCC, Drain, Soling, Nallah & culvert at On-going 1286 2889 Sheikhupura 20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress UC 87 Farooqabad , District Sheikhupura Schemes Provision of PCC, Drain, Soling, Nallah & culvert at On-going 1287 2890 Sheikhupura 20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress UC Ghung, District Sheikhupura Schemes Provision of PCC, Drain, Soling, Nallah & culvert at On-going 1288 2891 Sheikhupura 20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress UC Nokhar Nau, District Sheikhupura Schemes

Provision of PCC, Drain, Soling, Nallah & culvert at On-going 1289 2892 Sheikhupura 20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress UC Sucha Sauda, District Sheikhupura Schemes Provision of PCC, Drain, Soling, Nallah & culvert at On-going 1290 2893 Sheikhupura 20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress UC Hardev, District Sheikhupura Schemes Construction of soling, PCC, Drain & Nallah UC On-going 1291 2894 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Mojoki Mallian, District Sheikhupura Schemes Construction of soling, PCC, Drain & Nallah UC On-going 1292 2895 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Jhamkay, District Sheikhupura Schemes Construction of soling, PCC, Drain & Nallah UC On-going 1293 2896 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Kalokay, District Sheikhupura Schemes Construction of soling, PCC, Drain & Nallah UC On-going 1294 2897 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Rakh Hiran Minara District Sheikhupura Schemes Construction of soling, PCC, Drain & Nallah UC On-going 1295 2898 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Ghang District Sheikhupura Schemes Construction of soling, PCC, Drain & Nallah UC On-going 1296 2899 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Warn Dera Bhikhi Ana District Sheikhupura Schemes Rural drainage & PCC Scheme UC Jhabran, On-going 1297 2900 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress District Sheikhupura Schemes Rural drainage & PCC Scheme UC Ghazi Minara, On-going 1298 2901 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress District Sheikhupura, Schemes Rural drainage & PCC Scheme UC Hardev, On-going 1299 2902 Sheikhupura 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress District Sheikhupura Schemes Construction of PCC, Drain / Soling & Nallah at UC On-going 1300 2903 Sheikhupura 11.000 5.000 2.000 1.500 1.000 67% 55% Work in Progress Kakar Gill, District Sheikhupura Schemes Construction of PCC, Drain / Soling & Nallah at UC On-going 1301 2904 Sheikhupura 14.000 5.000 3.000 2.250 1.500 67% 46% Work in Progress 83 Jatri Kohna, District Sheikhupura Schemes Construction of PCC, Drain / Soling & Nallah at UC On-going 1302 2905 Sheikhupura 12.000 5.000 2.333 1.750 1.167 67% 51% Work in Progress 79 Harchand, District Sheikhupura Schemes Construction of PCC, Drain / Soling & Nallah at UC On-going 1303 2906 Sheikhupura 16.000 5.000 3.667 2.750 1.834 67% 43% Work in Progress 81 Sucha Sauda, District Sheikhupura Schemes Construction of PCC, Drain / Soling & Nallah at UC On-going 1304 2907 Sheikhupura 14.000 5.000 3.000 2.250 1.500 67% 46% Work in Progress 80 Esherke, District Sheikhupura Schemes Construction of PCC, Drain / Soling & Nallah at UC- On-going 1305 2908 85, 86 & 87 Farooqabad City & Muridke village UC- Sheikhupura 55.000 20.000 3.333 2.500 1.667 67% 39% Work in Progress Schemes 70, District Sheikhupura Construction of PCC, Drain, Soling & Nallah Kala On-going 1306 2909 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Khatai UC-9, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1307 2910 Sheikhupura 30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress Khatiala Virkan UC-18, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1308 2911 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Sheikhupura Bedad UC-15, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1309 2912 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Nangal Kaswala UC-14, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1310 2913 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Dharor Muslim UC-13, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1311 2914 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Ahdian UC-7, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1312 2915 Sheikhupura 12.000 5.000 2.333 1.750 1.167 67% 51% Work in Progress Lambray UC-10, District Sheikhupura Schemes Construction of PCC, Drain, Soling & Nallah On-going 1313 2916 Sheikhupura 20.000 5.000 1.667 1.250 0.834 67% 29% Work in Progress Nangal Sahdan UC-11, District Sheikhupura Schemes Rural Drainage and Construction of Streets On-going 1314 2917 Sheikhupura 30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress Scheme at UC Barth District Sheikhupura. Schemes Rural Drainage and Construction of Streets On-going 1315 2918 Sheikhupura 30.000 19.000 3.667 2.750 1.834 67% 69% Work in Progress Scheme at UC Chak No.22 District Sheikhupura. Schemes

Rural Drainage and Construction of Streets On-going 1316 2919 Sheikhupura 35.000 19.000 1.667 1.250 0.834 67% 57% Work in Progress Scheme at UC Faizpur Khurd District Sheikhupura. Schemes

Rural Drainage and Construction of Streets On-going 1317 2920 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Scheme at UC Luban Wala District Sheikhupura. Schemes

Rural Drainage and Construction of Streets On-going 1318 2921 Sheikhupura 30.000 19.000 3.667 2.750 1.834 67% 69% Work in Progress Scheme at UC Faizpur Kalan District Sheikhupura. Schemes

Rural Drainage and Construction of Streets On-going 1319 2922 Sheikhupura 25.000 10.000 1.667 1.250 0.834 67% 43% Work in Progress Scheme at UC Buraj Attari District Sheikhupura. Schemes

Rural Drainage and Construction of Streets On-going 1320 2923 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Scheme at UC Moran Wala District Sheikhupura. Schemes

Rural Drainage and Construction of Streets On-going 1321 2924 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% scheme Completed Scheme at UC Rana Bhati District Sheikhupura. Schemes Rural Drainage and Construction of Streets Scheme at UC Kashmir Town/Rana Town/ Galkxy On-going 1322 2925 Sheikhupura 50.000 1.750 3.333 2.500 1.667 67% 7% Work in Progress Block/ Kot Hadayat/ Haider Road District Schemes Sheikhupura. Rural Drainage and PCC at villages Samolana, Mada Treda, Pherianwala, Khanni, Jalalpur, On-going 1323 2926 Sheikhupura 30.000 15.000 1.667 1.250 0.834 67% 53% Work in Progress Nizampura, Kukripur, Sikhanwala, Jogiwala and Schemes adjoinging abdies, District Sheikhupura Construction of PCC, Drains and Nallah at UC-37 On-going 1324 2927 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Chak 575 GB District Sheikhupura Schemes Construction of Rural Draiange PCC & Tuff tiles On-going 1325 2928 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress scheme UC 27, District Sheikhupura Schemes Construction of Rural Draiange PCC & Tuff tiles On-going 1326 2929 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress scheme UC 28, District Sheikhupura Schemes Construction of Rural Draiange PCC & Tuff tiles On-going 1327 2930 Sheikhupura 15.000 10.000 1.667 1.250 0.834 67% 72% Work in Progress scheme UC 29, District Sheikhupura Schemes Construction of Rural Draiange PCC & Tuff tiles On-going 1328 2931 Sheikhupura 15.000 10.000 1.667 1.250 0.834 67% 72% Work in Progress scheme UC 30, District Sheikhupura Schemes Construction of Rural drainage PCC & Tuff tiles On-going 1329 2932 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress scheme UC Rana Bhatti, District Sheikhupura Schemes

Construction of Rural drainage PCC & Tuff tiles On-going 1330 2933 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress scheme UC Mandianwala, District Sheikhupura Schemes Construction of Rural drainage PCC & Tuff tiles On-going 1331 2934 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress scheme UC Dhamkay, District Sheikhupura Schemes

Construction of Rural drainage PCC & Tuff tiles On-going 1332 2935 Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress scheme UC Chak No.22, District Sheikhupura Schemes Urban Drainage and Sewerage Scheme Narang On-going 1333 2936 Sheikhupura 220.000 30.000 1.000 0.750 0.500 67% 14% Work in Progress Mandi, District Sheikhupura Schemes Urban Sewerage, Drainage & PCC Scheme MC On-going 1334 2937 Ferozewala, Tehsil Ferozewala, District Sheikhupura 160.000 20.000 5.000 3.750 2.500 67% 14% Work in Progress Schemes Sheikhupura Construction of PCC, Drain & Nallah Muridke City, On-going 1335 2938 Sheikhupura 100.000 25.000 3.333 2.500 1.667 67% 27% Work in Progress District Sheikhupura Schemes Construction of PCC, Drain & Nallah Narang City, On-going 1336 2939 Sheikhupura 30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress District Sheikhupura Schemes Provision of water supply and sewerage / drainage On-going 1337 2940 Sheikhupura 450.000 17.500 16.667 12.500 8.334 67% 6% Work in Progress scheme city Sheikhupura Schemes Urban Sewerage, Drainage & PCC Scheme MC On-going 1338 2941 Kot Adbul Malik, Tehsil Ferozewala, District Sheikhupura 140.000 15.000 3.333 2.500 1.667 67% 12% Work in Progress Schemes Sheikhupura Urban Sewerage, Drainage & PCC Scheme UC On-going 1339 2942 Momin Pura, Tehsil Ferozewala, District Sheikhupura 20.000 5.427 4.858 3.644 2.429 67% 39% Work in Progress Schemes Sheikhupura Urban Sewerage, Drainage & PCC Scheme UC On-going 1340 2943 Sheikhupura 100.000 9.254 3.535 2.651 1.768 67% 11% Work in Progress Shamkay, Tehsil Ferozewala, District Sheikhupura Schemes Urban Sewerage, Drainage & PCC Scheme UC On-going 1341 2944 Qilla Sattar Shah, Tehsil Muridkay, District Sheikhupura 20.000 10.000 3.333 2.500 1.667 67% 58% Scheme completed Schemes Sheikhupura Provision of PCC and Tuff Tiles in City On-going 1342 2945 Sheikhupura 180.000 140.000 3.333 2.500 1.667 67% 79% Work in Progress Sheikhupura PP-167, District Sheikhupura Schemes Construction of PCC, Drains and Nallah at UC-57 On-going 1343 2946 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Jevanpura, District Sheikhupura Schemes Construction of PCC, Drains and Nallah at UC-58 On-going 1344 2947 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Kadlathi, District Sheikhupura Schemes Construction of PCC, Drains and Nallah at UC-80 On-going 1345 2948 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Khariyanwala. District Sheikhupura Schemes Construction of PCC, Drains and Nallah at UC-81 On-going 1346 2949 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Bhikhi. District Sheikhupura Schemes Construction of PCC, Drains and Nallah at UC-82 On-going 1347 2950 Sheikhupura 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Tibbi Hambo. District Sheikhupura Schemes Construction of sewerage, drains, tuff tiles, PCC & On-going 1348 2951 LED Street lights at Wandala Dial Shah & Dhaka Sheikhupura 30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress Schemes Nizam Pura, District Sheikhupura Construction of drain / soling / PCC / Nullah and Pulyat at vilalge Rato Ana, Kot Ghulam Rasool and On-going 1349 2952 Nankana Sahib 29.500 10.000 3.333 2.500 1.667 67% 40% Work is in progress. village Sheedi Kot UC Kot Hussain Khan, District Schemes Nankana Sahib Construction of PCC / Soling & Nallah at UC On-going 1350 2953 Nankana Sahib 30.000 10.000 3.333 4.200 3.367 80% 45% Work is in progress. Buchoke Pur Distirct Nankana Sahib Schemes Construction of Drain / Nullah / Culverts / PCC and On-going 1351 2954 Soling at UC Kari Wala i/c Mashmoola Jat, Tehsil Nankana Sahib 15.000 10.000 1.667 0.450 0.034 8% 67% Work is in progress. Schemes Shah Kot, District Nankana Sahib Construction of drain / soling / PCC / Nullah and Pulyat at village Nathowala 180/RB, Chak On-going 1352 2955 Nankana Sahib 29.700 10.000 3.333 2.500 1.667 67% 39% Work is in progress. No.181/RB, Kari Wala and Chak No.182/RB, UC Schemes Nathowala, District Nankana Sahib Construction of drain / soling / PCC / Nullah and Pulyat at village Chak No.184/RB Kot Nizam Din On-going 1353 2956 Nankana Sahib 29.300 10.000 3.333 2.500 1.667 67% 40% Work is in progress. and Chak No.186/RB Ghandran UC Kot Nizam Schemes Din, District Nankana Sahib Construction of Drain / Soling / Nallah at UC On-going 1354 2957 Nankana Sahib 30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress. Saleem Pur Pakka, District Nankana Sahib Schemes Construction of Drain / Soling / Nallah at UC On-going 1355 2958 Nankana Sahib 30.000 10.000 3.333 4.200 3.367 80% 45% Work is in progress. Mangtanwala, District Nankana Sahib Schemes Construction of Drain / Soling / Nallah at UC On-going 1356 2959 Nankana Sahib 30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress. Chachke Gill, District Nankana Sahib Schemes Construction of Drain / Soling / Nallah at UC Haft On-going 1357 2960 Nankana Sahib 30.000 10.000 3.333 3.000 2.167 72% 41% Work is in progress. Madar, District Nankana Sahib Schemes Construction of Drain / Soling / Nallah in left over On-going 1358 2961 Nankana Sahib 30.000 10.000 3.333 4.100 3.267 80% 44% Work is in progress. area of UC Ganaish Pur, District Nankana Sahib Schemes

Construction of Drain / Soling / Nallah in left over On-going 1359 2962 Nankana Sahib 40.000 13.000 3.333 1.100 0.267 24% 33% Work is in progress. area of UC Jawahar Pur, Distirct Nankana Sahib Schemes

Construction of Drain / Soling / Nallah in left over On-going 1360 2963 Nankana Sahib 30.000 10.000 3.333 1.100 0.267 24% 34% Work is in progress. area of UC Jogaykot, Distirct Nankana Sahib Schemes Construction of Drain / Soling / Nullah at UC jalal On-going 1361 2964 Nankana Sahib 15.000 10.000 1.667 1.250 0.834 67% 72% Work is in progress. Nau, District Nankana Sahib Schemes Construction of Drain / Soling / Nullah at Village On-going 1362 2965 Balaqian, Dodhay, Chora, Mat Kalayian and Nankana Sahib 20.000 10.000 3.333 2.500 1.667 67% 58% Work is in progress. Schemes Dharian, District Nanakana Sahib

Provision of sewerage, PCC & Nullah at Mouza On-going 1363 2966 Nankana Sahib 30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress. Khiyaray Kalan, Tehsil & District Nankana Sahib Schemes Provision of water supply sanitation and drainage On-going 1364 2967 facilities at Chak No.168/RB Machar Wali District Nankana Sahib 112.768 23.200 3.333 2.500 1.667 67% 22% Work is in progress. Schemes Nankana Sahib Construction of Nullah / Drain and PCC at Bucheki City and at Chak No.22/75, Chak No.18/71, Chak On-going 1365 2968 Nankana Sahib 50.000 40.000 3.333 0.850 0.017 2% 80% Work is in progress. No.16/69, Chak No.641 Bohty Wala, Lurka Jangly, Schemes District Nankana Sahib

Construction of PCC / Drain / Nullah at Burala, Maddo Ladoana, Juggian Nolan, Warra Narain On-going 1366 2969 Singh, Jahana Nool, Peeray Wali, Chak Wattowan, Nankana Sahib 30.000 13.000 3.333 1.400 0.567 41% 45% Work is in progress. Schemes Nodhan, Sikhanwali, Kawanwali, Nizam Pura, Baghoor, District Nankana Sahib Construction of Soling, Drains & PCC at village Nathowala, Nizampura, Nodha, Fareedabad, On-going 1367 2970 Nankana Sahib 50.000 33.000 3.333 2.500 1.667 67% 69% Work is in progress. Kheokay Bhattian, Madu, Purana Syed wala , Schemes District Nankana Sahib Construction of PCC, Soling & Nullah at UC On-going 1368 2971 Machrala i/c Bhagor, Wakeel Wala, Adampura & Nankana Sahib 30.000 10.000 3.333 4.000 3.167 79% 44% Work is in progress. Schemes Dolatpura, Distirct Nankana Sahib Construction of PCC, Soling & Nullah at UC On-going 1369 2972 Nankana Sahib 25.000 10.000 3.333 3.150 2.317 74% 49% Work is in progress. Mustafaabad / Jislani, Distirct Nankana Sahib Schemes Construction of PCC, Soling & Nullah at UC On-going 1370 2973 Nankana Sahib 25.000 10.000 3.333 0.850 0.017 2% 40% Work is in progress. Meeranpur, Distirct Nankana Sahib Schemes Construction of PCC, Drains and Nallah at UC-51 On-going 1371 2974 Nankana Sahib 15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress. Khiarraey Kalan District Nankana Sahib. Schemes Construction of PCC, Drains and Nallah at UC-52 On-going 1372 2975 Nankana Sahib 15.000 5.000 3.333 0.950 0.117 12% 34% Work is in progress. Chokian Wala District Nankana Sahib. Schemes Construction of PCC, Nallah, Drains at Syed Wala, On-going 1373 2976 Nankana Sahib 50.000 40.000 3.333 0.850 0.017 2% 80% Work is in progress. District Nankana Sahib Schemes Construction of PCC, Drains and Nallah at UC-48 On-going 1374 2977 Nankana Sahib 15.000 5.000 3.333 0.950 0.117 12% 34% Work is in progress. Rehanwala District Nankana Sahib. Schemes Construction of PCC, Drains and Nallah at UC-36 On-going 1375 2978 Nankana Sahib 15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress. Mashrala District Nankana Sahib. Schemes Construction of PCC, Drains and Nallah at UC-39 On-going 1376 2979 Nankana Sahib 15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress. Meeranpur District Nankana Sahib. Schemes Construction of PCC, Drains and Nallah at UC-50 On-going 1377 2980 Nankana Sahib 15.000 5.000 3.333 3.400 2.567 76% 50% Work is in progress. Ganaishpur District Nankana Sahib. Schemes Construction of PCC, Drains and Nallah at UC-38 On-going 1378 2981 Nankana Sahib 15.000 5.000 3.333 4.500 3.667 81% 58% Work is in progress. Warbutton District Nankana Sahib. Schemes Construction of PCC, Drains and Nallah at UC-40 On-going 1379 2982 Nankana Sahib 15.000 5.000 3.333 4.500 3.667 81% 58% Work is in progress. Shareen Jhangaar District Sheikhupura Schemes Rural Drainage PCC Brick pavement Schemes On-going 1380 2983 Beroon Mustafa Abad and Adjoining Abadies, Kasur 20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress Schemes Tehsil & District Kasur Rural Drainage PCC Brick pavement Schemes On-going 1381 2984 Weghal and Adjoining Abadies, Tehsil & District Kasur 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Schemes Kasur Rural Drainage PCC Brick pavement Schemes On-going 1382 2985 Badar Pur, Ray, Badian and Adjoining Abadies, Kasur 15.000 4.966 3.333 2.500 1.667 67% 44% Work in Progress Schemes Tehsil & District Kasur Rural Drainage PCC Brick pavement Schemes On-going 1383 2986 Matta and Adjoining Abadies, Tehsil & District Kasur 20.000 9.957 3.333 2.500 1.667 67% 58% Work in Progress Schemes Kasur Rural Drainage PCC Brick pavement Schemes On-going 1384 2987 Khara and Adjoining Abadies, Tehsil & District Kasur 15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress Schemes Kasur Const. of Soling Drains, PCC, Culverts U.C On-going 1385 2988 Kasur 30.000 11.467 1.667 3.620 3.204 89% 49% Work in Progress Handal, Tehsil KRK, District Kasur Schemes Rural drainage scheme U.C Bhedian, District On-going 1386 2989 Kasur 30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress Kasur Schemes Rural drainage scheme U.C Sheikhum, District On-going 1387 2990 Kasur 25.000 9.993 5.000 3.750 2.500 67% 50% Work in Progress Kasur Schemes Rural drainage scheme U.C Fathe Pur, District On-going 1388 2991 Kasur 30.000 9.981 1.967 1.475 0.984 67% 37% Work in Progress Kasur Schemes Rural drainage scheme U.C Hussain Khan Wala, On-going 1389 2992 Kasur 30.000 10.000 6.667 6.000 4.334 72% 48% Work in Progress District Kasur Schemes Construction of Sewerage / Drainage / PCC On-going 1390 2993 Kasur 199.860 34.999 20.000 26.303 21.303 81% 28% Work in Progress Scheme Kot Radha Kishan City, District Kasur Schemes Construction of Soling, Nallah, PCC & Drain at On-going 1391 2994 Kasur 15.000 4.992 3.333 2.500 1.667 67% 44% Work in Progress Satoki, District Kasur. Schemes Construction of Soling, Nallah, PCC & Drain at UC On-going 1392 2995 Kasur 15.000 4.996 3.333 2.500 1.667 67% 44% Work in Progress Cheena Arla and Nathoki, District Kasur Schemes Construction of Soling, Nallah, PCC & Drain at UC On-going 1393 2996 Kasur 15.000 4.980 3.333 2.500 1.667 67% 44% Work in Progress Pemar, District Kasur Schemes Construction of soling / drains / PCC roads in Chak On-going 1394 2997 Kasur 3.000 2.500 0.167 0.125 0.084 67% 86% Work in Progress No.38, District Kasur Schemes Construction of soling / drains / PCC roads in On-going 1395 2998 Kasur 3.000 2.457 0.167 0.125 0.084 67% 85% Work in Progress village Chugian & Marathiwala, District Kasur Schemes Construction of soling / drains / PCC roads in On-going 1396 2999 Kasur 3.000 2.500 0.167 0.125 0.084 67% 86% Work in Progress village Chaku , District Kasur Schemes Construction of Urban Sewerage, Drainage, PCC On-going 1397 3000 Kasur 360.000 35.000 10.090 7.568 5.045 67% 11% Work in Progress Scheme Khudian Phase-II, District Kasur Schemes Construction of Urban Sewerage, Drainage, PCC On-going 1398 3001 Kasur 150.026 29.977 5.000 3.750 2.500 67% 22% Work in Progress Scheme, Kanganpur, District Kasur Schemes Urban Water supply scheme, Kasur City, District On-going 1399 3002 Kasur 70.526 20.000 5.000 3.750 2.500 67% 32% Work in Progress Kasur Schemes Construction of drain, PCC, Tuff Tile, Culverts, Sullage Carrier and Brick Pavement Sheikham, On-going 1400 3003 Kasur 144.500 27.996 5.000 3.750 2.500 67% 21% Work in Progress Kacha Pakka, Padhana, Bath Kalan and Tara Schemes Garh, Tehsil Pattoki, District Kasur

Construction of drain, PCC, Tuff Tile, Culverts, Sullage Carrier and Brick Pavement Balloki, On-going 1401 3004 Kasur 149.000 28.000 5.000 3.750 2.500 67% 20% Work in Progress Sandhu Kalan, Sarai Mughal, Beharwal and Schemes Bhonikey, Tehsil Pattoki, District Kasur Rehabilitation & Re-construction of sullage carrier On-going 1402 3005 Kasur 10.451 7.000 1.150 2.363 2.075 88% 87% Work in Progress at Waan Adhan, District Kasur Schemes Construction of Drain, Brick Pavement & PCC in On-going 1403 3006 Ghummankey and adjoining abadies, Tehsil Kasur 69.298 20.000 20.000 15.000 10.000 67% 43% Work in Progress Schemes Pattoki, District Kasur Construction of Drain, Brick Pavement & PCC in On-going 1404 3007 Bonga Balochan and adjoining abadies, Tehsil Kasur 66.879 20.000 20.000 14.500 9.500 66% 44% Work in Progress Schemes Pattoki, District Kasur Construction of Drainage, Brick Pavement, PCC On-going 1405 3008 and Sullage Carrier Scheme in Blair, Masradass i/c Kasur 50.000 18.000 3.333 2.500 1.667 67% 39% Work in Progress Schemes adjoining abadies, Tehsil Pattoki, District Kasur

Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09-2017 Date of Rural Sewerage / Drainage Scheme Chak On-going invitation of tenders 26.09.2017, Date of Receipt of 1406 3009 Okara 14.330 9.993 1.000 0.750 0.500 67% 73% tenders 27.09.2017, Date of work order ,12.10.2017 No.18/GD, District Okara Schemes Date of completion as per PC-I ,30.06.2018 Anticipated date of completion ,30.06.2018 No. of Beneficiary - 9878 Person, Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Sahbay On-going tenders 11.10.2017, Date of work order 16-11-2017, 1407 3010 Okara 20.840 9.992 3.613 2.710 1.806 67% 57% Wala, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 9822 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Bhakho On-going tenders 11.10.2017, Date of work order 16-11-2017, 1408 3011 Okara 20.510 7.993 4.170 3.128 1.849 59% 48% Shah, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 6316 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Dhool On-going tenders 11.10.2017, Date of work order 16-11-2017, 1409 3012 Okara 20.325 7.992 4.108 3.081 0.539 17% 42% Choor, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 9804 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Aman On-going tenders 11.10.2017, Date of work order 16-11-2017, 1410 3013 Okara 19.930 9.991 3.310 2.483 1.325 53% 57% Wala, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 4246 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Dhol On-going 1411 3014 Okara 17.400 7.987 3.133 2.350 1.523 65% 55% tenders 11.10.2017, Date of work order 16-11-2017, Gehla, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 3302 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Mehro On-going 1412 3015 Okara 17.190 7.500 3.230 2.423 1.060 44% 50% tenders 11.10.2017, Date of work order 16-11-2017, Kalan, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 6277 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Somian On-going 1413 3016 Okara 17.660 9.972 2.553 1.915 1.262 66% 64% tenders 11.10.2017, Date of work order 16-11-2017, Bholon, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 3678 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Roori, On-going 1414 3017 Okara 15.520 9.991 1.840 1.380 0.920 67% 70% tenders 11.10.2017, Date of work order 16-11-2017, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 3005 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Mali On-going 1415 3018 Okara 17.900 7.912 3.300 2.475 1.613 65% 53% tenders 11.10.2017, Date of work order 16-11-2017, Singh, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 3813 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Khan On-going 1416 3019 Okara 25.790 9.970 5.263 3.947 2.916 74% 50% tenders 11.10.2017, Date of work order 16-11-2017, Bahadar, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 5319 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 07-12-2017 Date of Receipt of Rural Water Supply & Drainage Scheme, Kalia On-going 1417 3020 Okara 22.970 4.992 5.990 4.493 2.234 50% 31% tenders 08-12-2017 Date of work order 14-12-2017 Ibrahim, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 2866 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, On-going 1418 3021 Okara 19.710 10.000 3.237 2.428 1.615 67% 59% tenders 11.10.2017, Date of work order 16-11-2017, Shamaskay, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, A nticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 2619 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Subhan On-going 1419 3022 Okara 22.450 9.995 4.150 3.113 1.841 59% 53% tenders 11.10.2017, Date of work order 16-11-2017, Shah, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 5870 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Bothana, On-going 1420 3023 Okara 21.110 9.999 3.703 2.777 1.852 67% 56% tenders 11.10.2017, Date of work order 16-11-2017, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 5652 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, On-going 1421 3024 Okara 21.510 11.000 3.503 2.627 1.774 68% 59% tenders 11.10.2017, Date of work order 16-11-2017, Sahniwal, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary 4724 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Chak no. On-going tenders 11.10.2017, Date of work order 16-11-2017, 1422 3025 Okara 17.270 9.993 2.423 1.817 1.163 64% 65% 7/D Rakh Dharma, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 3781 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 07-12-2017 Date of Receipt of Rural Water Supply & Drainage Scheme, On-going tenders 08-12-2017 Date of work order 12-12-2017 1423 3026 Okara 18.500 9.992 2.833 2.125 1.413 66% 62% Kandowal Sarai, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 6281 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Chak no. On-going tenders 11.10.2017, Date of work order 16-11-2017, 1424 3027 Okara 18.330 9.997 2.777 2.083 1.923 92% 65% 19/D, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 4604 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Sarai On-going tenders 11.10.2017, Date of work order 16-11-2017, 1425 3028 Okara 21.320 9.998 3.773 2.830 1.792 63% 55% Amar Singh, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 6642 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Chak On-going tenders 11.10.2017, Date of work order 16-11-2017, 1426 3029 Okara 21.650 9.999 3.883 2.912 1.907 65% 55% Kamboh, Depal Pur Schemes Date of completion as per PC-I 30.06.2018,, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 5441 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 10.10.2017, Date of Receipt of Rural Water Supply & Drainage Scheme, Doola On-going tenders 11.10.2017, Date of work order 16-11-2017, 1427 3030 Okara 19.930 9.986 3.310 2.483 1.645 66% 58% Mustakim , Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 3942 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 07-12-2017 Date of Receipt of Rural Water Supply & Drainage Scheme, Bonga On-going tenders 08-12-2017 Date of work order 14-12-2017 1428 3031 Okara 21.580 9.992 3.860 2.895 1.874 65% 55% Saleh, Depal Pur Schemes Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 7909 Person, Work is in progress.

Date of A.A 11.08.2017, Date of T.S 15.08.2017, Date of Prequalification 13-09-2017, Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 08.10.2017, Date of Receipt of On-going tenders 09.10.2017, Date of work order 18-11-2017, 1429 3032 Carrier, Tuff Tile, PCC in District Okara Chak no. Okara 64.454 7.800 3.333 2.500 0.735 29% 13% Schemes Date of completion as per PC-I 30.06.2019, 38-GD Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary -14313 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 31-07-2017, Date of Prequalification 13-09-2017, Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 27.10.2017, Date of Receipt of On-going 1430 3033 Carrier, Tuff Tile, PCC in District Okara Chak no. Okara 25.000 9.999 3.333 2.500 1.297 52% 45% tenders 28.10.2017, Date of work order ,07-02-2018 Schemes Date of completion as per PC-I 30.06.2018, 4/GD Anticipated date of completion 30.06.2019, Funds Release on 20-07-2018 No. of Beneficiary - 10018 Person, Date of A.A 26.07.2017, Date of T.S 31-07-2017, Date of Prequalification ,13.09.2017 Date of Soling / Sewerage and Drainage of Chak No. On-going invitation of tenders 18-12-.2017, Date of Receipt of 1431 3034 Okara 20.000 9.999 3.333 2.500 1.667 67% 58% tenders 19-12-2017, Date of work order 19-01-2018 53/2L, 54/2L, 55/2L, District Okara Schemes Date of completion as per PC-I , Anticipated date of completion, 30-06-2019 Funds Release on 20-07- 2018 No. of Beneficiary - 51657 Person, Date of A.A 08.08.2017, Date of T.S 10.08.2017 Date of Prequalification ,13.09.2017 Date of invitation of tenders 27.10.2017, Date of Receipt of Provision of Soling and Drainage Scheme at U.C. On-going 1432 3035 Okara 14.000 6.986 2.333 1.750 0.875 50% 56% tenders 28.10.2017, Date of work order 31-09-2017 No.42/3R, District Okara Schemes Date of completion as per PC-I , Anticipated date of completion , 30-06-2019 Funds Release on 20-07- 2018 No. of Beneficiary - 49251 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 02-08-2017 Date of Prequalification ,13.09.2017 Date of Provision of Soling and Drainage Scheme at U.C. On-going invitation of tenders 27.10.2017, Date of Receipt of 1433 3036 Okara 20.000 10.000 3.333 2.500 1.667 67% 58% tenders 28.10.2017, Date of work order 12-12-2017 No.35/2RA, District Okara Schemes Date of completion as per PC-I , Anticipated date of completion, 30-06-2019 Funds Release on 20-07- 2018 No. of Beneficiary - 33832 Person, Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification ,13.09.2017 Date of invitation of tenders 27.10.2017, Date of Receipt of Provision of Tuff Tiles Soling, PCC, and Drainage On-going 1434 3037 Okara 48.940 18.295 3.333 2.500 1.660 66% 41% tenders 28.10.2017, Date of work order 20-11-2017 Schemes at Haveli Lakha and Adjoining Abadies Schemes Date of completion as per PC-I , Anticipated date of completion, 30-06-2019 Funds Release on 20-07- 2018 No. of Beneficiary 42300 Person, Work is in progress. Date of A.A 11.08.2017, Date of T.S 27.09.2017, Installation of LED Street Light 120/W, 50/W Date of Prequalification 19-09-2017 Date of invitation of tenders 03.11.2017, Date of Receipt of including Pools, Construction of Sullage Carrier / On-going 1435 3038 Okara 74.312 38.998 3.333 2.500 1.667 67% 55% tenders 03.11.2017, Date of work order 09-11-2017 sewerage & Construction of Tuff Paver different Schemes Date of completion as per PC-I , Anticipated date of completion, 30-06-2019 Funds Release on 20-07- places at Okara City approx. District Okara 2018 No. of Beneficiary 215982 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09-2017 Date of invitation of tenders 27.10.2017, Date of Receipt of Construction of Tuff Tiles / Sewerage and On-going 1436 3039 Okara 40.000 14.957 3.333 2.500 1.762 70% 42% tenders 28.10.2017, Date of work order 17-11-2017 Drainage of Ward no. 1 to 50, District Okara Schemes Date of completion as per PC-I , 30-06-2018 Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary -640401 Person, Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09-2017 Date of City Package Renala Khurd Tuff Tile and invitation of tenders 27.10.2017, Date of Receipt of On-going 1437 3040 Sewerage Androon City Gilyat Renala Khurd In Okara 35.000 15.584 3.333 2.500 1.667 67% 49% tenders 28.10.2017, Date of work order 07-11-2017 Schemes Date of completion as per PC-I 30-06-2018 District Okara Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - 64595 Person, Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017 Date of Sewerage Scheme at Mohallah Shakoor Abad, On-going invitation of tenders 27.10.2017, Date of Receipt of 1438 3041 Mohallah Eid Gah, Mohallah Masjid Basharat, Okara 49.934 22.496 3.333 2.500 1.665 67% 48% tenders 28.10.2017, Date of work order 18-11-2017 Schemes Akhter Town, Haveli Lakha, City. Date of completion as per PC-I ,30-06-2018 Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - Person, Date of A.A 28-09-2017 Date of T.S 16-11-2017 Date of Prequalification 18-11-2017 Date of invitation of tenders 13-12-2017 Date of Receipt of On-going 1439 3042 Water supply Schemes for NA-145 Okara 300.000 74.642 20.000 20.990 20.990 100% 32% tenders, 13-12-2017 Date of work order 23-12-2017 Schemes Date of completion as per PC-I 23-12-2020 Anticipated date of completion, 30-06-2020Re- Appropreation (+)5.990 No. of Beneficiary 900043 Person, Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017 Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 27.10.2017, Date of Receipt of On-going 1440 3043 Carrier, Tuff Tile, PCC in District Okara:in Mouza Okara 23.299 11.494 3.333 2.500 1.669 67% 56% tenders 28.10.2017, Date of work order 25-01-2018 Schemes Date of completion as per PC-I ,25-01-2019 Jaboka Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - 14607 Person, Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09-2017 Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 27.10.2017, Date of Receipt of On-going 1441 3044 Carrier, Tuff Tile, PCC in District Okara Mouza Okara 49.895 17.413 3.333 2.500 1.713 69% 38% tenders 28.10.2017, Date of work order 25-01-2018 Schemes Date of completion as per PC-I 25-01-2019 Lasharian Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - 17695 Person, Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09-2017 Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 18-12-.2017, Date of Receipt of On-going 1442 3045 Carrier, Tuff Tile, PCC in District Okara Mouza Okara 26.331 4.996 3.333 2.500 1.705 68% 25% tenders 19-12.2017, Date of work order 19-01-2018 Schemes Date of completion as per PC-I 19-01-2019 Kohla Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - 21476 Person, Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09-2017 Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 27.10.2017, Date of Receipt of On-going 1443 3046 Carrier, Tuff Tile, PCC in District Okara Mouza Okara 18.346 13.991 1.282 0.962 0.682 71% 80% tenders 28.10.2017, Date of work order 18-11-2017 Schemes Date of completion as per PC-I 30-06-2018 Bama Bala Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - 12896 Person, Work is in progress. Date of A.A 08.08.2017, Date of T.S 12.08.2017, Date of Prequalification 13-09-2017 Date of Construction of Drain, Brick Pavement, Sullage invitation of tenders 27.10.2017, Date of Receipt of On-going 1444 3047 Carrier, Tuff Tile, PCC in District Okara Mouza Okara 27.702 14.999 4.234 3.176 2.059 65% 62% tenders 28.10.2017, Date of work order 23-12-2017 Schemes Date of completion as per PC-I 30-06-2018 Maroula Sharif Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary - 09561 Person, Date of A.A 12-09-2017 Date of T.S 16-09-2017 Date of Prequalification 13-09-2017 Date of invitation of tenders 27.10.2017, Date of Receipt of Provision of Drainage, Sewerage and Tuff Till On-going 1445 3048 Okara 20.000 5.377 4.833 3.625 2.467 68% 39% tenders 28.10.2017, Date of work order 20-11-2017 Scheme at Civil Area Okara Cantt, District Okara Schemes Date of completion as per PC-I 30-06-2018 Anticipated date of completion, 30-06-2019 Funds Release on 20-07-2018 No. of Beneficiary 98441 Person, Work is in progress. Providing of Tuff Tile & Sewerage / Drainage in On-going 1446 3049 Basirpur and Mandi Ahmad Abad Town, District Okara 26.398 9.999 3.333 4.167 0.816 20% 41% Work is in progress. Schemes Okara Water Supply / Sewerage / Filtration Plants in 13 On-going Date of AA 06.12.2017 , Date of receipt of tender 1447 3050 Sahiwal 150.000 34.996 16.667 12.500 10.100 81% 30% 28.03.2018 , Work order 18.04.2018 , Work in UCs of PP-221, Sahiwal Schemes progress. Date of AA 19.08.2017, Date of Pre-qualification , On-going 1448 3051 Water Supply Scheme for Chak No. 78/5L Sahiwal Sahiwal 30.000 10.000 6.667 5.000 5.000 100% 50% Date of Work Order 23.12.2017 , Anticipated date of Schemes completion 30.06.2019 subject to availablity of balance funds, Work in progress. Construction of Drain / Soling Sewerage Nala Date of AA 01.08.2017 , Date of receipt of tender On-going 20.11.2017 , Date of Work Order 02.12.2017 , 1449 3052 Chak no. 50/12L, 105/12L, 106/12/L, District Sahiwal 15.000 5.000 3.333 2.500 2.000 80% 47% Schemes Anticipated date of completion 30.06.2019 subject Sahiwal to availablity of balance funds, Work in progress. Construction of Drain / Soling Sewerage Nala Date of AA 01.08.2017 , Date of receipt of tender On-going 09.11.2017 , Date of Work Order 24.11.2017 , 1450 3053 Chak no.38/14L,39/14L/40/14L, 41/14L , District Sahiwal 15.000 4.998 3.333 2.500 1.660 66% 44% Schemes Anticipated date of completion 30.06.2019 subject Sahiwal to availablity of balance funds, Work in progress. Construction of Drain / Soling Sewerage Nala Date of AA 01.08.2017 , Date of receipt of tenders On-going 09.11.2017 , Date of Work Order 24.11.2017 , 1451 3054 Chak no. 40/12L, 109/12L, Ghulshan Colony, Sahiwal 15.000 4.977 3.333 2.500 2.000 80% 47% Schemes Anticipated date of completion 30.06.2019 subject District Sahiwal to availablity of balance funds, Work in progress. Construction of Drain / Soling Sewerage Nala Date of AA 01.08.2017 , Date of receipt of tender On-going 20.11.2017 , Date of Work Order 02.12.2017 , 1452 3055 Chak no. 118/12L, 117/12L, Ada Kassowal, District Sahiwal 15.000 7.488 2.500 1.875 1.500 80% 60% Schemes Anticipated date of completion 30.06.2019 subject Sahiwal to availablity of balance funds, Work in progress. Contruction of Drain / Soling Sewerage Nala Chak Date of AA 01.08.2017, Date of receipt of tender On-going 09.11.2017, Date of Work Order 24.11.2017, 1453 3056 no. 119/7DR, 120/7ER, 121/7ER, 122/7ER, Sahiwal 15.000 7.495 2.500 1.875 1.600 85% 61% Schemes Anticipated date of completion 30.06.2019 subject 117/7DR, District Sahiwal to availablity of balance funds, Work in progress. Date of AA 01.08.2017, Date of receipt of tender Construction of Drain / Soling Sewerage Nala On-going 09.11.2017, Date of Work Order 1454 3057 Chak no. 114/7R, 115/7CR, 116/7CR Sahwa, Sahiwal 15.000 7.499 2.500 1.875 1.600 85% 61% 24.11.2017,Anticipated date of completion Schemes Dharma, District Sahiwal 30.06.2019 subject to availablity of balance funds, Work in progress. Date of AA 01.08.2017 , Date of receipt of tender Construction of Drain / Soling Sewerage Nala On-going 09.11.2017 , Date of Work Order 1455 3058 Chak no. 112/7r, 113/7r, Purani Chichawatni, Sahiwal 15.000 7.497 2.500 1.875 1.700 91% 61% 02.12.2017,Anticipated date of completion Schemes Sheikh Tayyab, District Sahiwal 30.06.2019 subject to availablity of balance funds, Work in progress, Date of AA 01.08.2017, Date of receipt of tender Installation of Filtration Plant at 60/5L in District On-going 11.09.2017, Date of Work Order 31.10.2017, Date 1456 3059 Sahiwal 3.000 1.500 0.500 0.375 0.250 67% 58% Sahiwal Schemes of Completion 30.06.2019 , Scheme completed. Balance funds will be re-appropriated.

Date of AA 01.08.2017, Date of receipt of tender Installation of Filtration Plant at 79/5R in District On-going 11.09.2017, Date of Work Order 31.10.2017, Date 1457 3060 Sahiwal 3.000 1.500 0.500 0.375 0.072 19% 52% Sahiwal Schemes of Completion 30.06.2019 , Scheme completed in saving. Balance funds will be re-appropriated. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Water Supply Scheme ChakNo. 20/SP On-going Date of receipt of tenders = 24.08.2017, Date of 1458 3061 Pakpattan 31.190 9.000 7.397 5.548 4.498 81% 43% work order= 23.09.2017, Funds released by FD = Tehsil and District Pakpattan Schemes 03.08.2018,Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Water Supply Scheme Kumari Wala Tehsil On-going Date of receipt of tenders = 24.08.2017, Date of 1459 3062 Pakpattan 34.670 14.978 5.223 3.917 2.612 67% 51% work order= 31.10.2017, Funds released by FD = and District Pakpattan Schemes 03.08.2018,Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Water Supply Scheme Chak No. 67/D Tehsil On-going Date of receipt of tenders = 24.08.2017, Date of 1460 3063 Pakpattan 32.440 8.700 7.813 5.860 4.120 70% 40% work order= 23.09.2017, Funds released by FD = and District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017. Date of T.S= 04.08.2017. Rural Water Supply Scheme Dhupai Tehsil and On-going Date of receipt of tenders = 24.08.2017. Date of 1461 3064 Pakpattan 29.980 16.000 4.660 3.495 2.330 67% 61% work order= 18.09.2017. Funds released by FD = District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Water Supply Scheme Chak No. 29/KB in On-going Date of receipt of tenders = 24.08.2017, Date of 1462 3065 Pakpattan 19.978 10.000 3.326 2.495 1.750 70% 59% work order= 31.10.2017, Funds released by FD = District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Water Supply Scheme Chak No. 111/EB in On-going Date of receipt of tenders = 24.08.2017, Date of 1463 3066 Pakpattan 29.412 8.000 7.137 5.353 4.270 80% 42% work order= 31.10.2017, Funds released by FD = District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Drainage Scheme Chak No. 74/D Tehsil and On-going Date of receipt of tenders = 24.08.2017, Date of 1464 3067 Pakpattan 27.671 15.000 4.224 3.168 2.112 67% 62% work order= 23.09.2017, Funds released by FD = District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Drainage Scheme 8/EB Tehsil and District On-going Date of receipt of tenders = 24.08.2017, Date of 1465 3068 Pakpattan 23.979 13.979 3.333 2.500 1.667 67% 65% work order= 31.10.2017, Funds released by FD = Pakpattn Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Drainage Scheme 90/D Tehsil and District On-going Date of receipt of tenders = 24.08.2017, Date of 1466 3069 Pakpattan 29.303 19.000 3.434 2.576 1.850 72% 71% work order= 23.09.2017, Funds released by FD = Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Rural Drainage scheme in Various UCs of PP-228 On-going Date of receipt of tenders = 21.10.2017, Date of 1467 3070 Pakpattan 74.312 25.000 8.333 6.250 4.356 70% 40% work order= 13.11.2017, Funds released by FD = District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Provision of Sewerage/ Tuff Tile / PCC / Soling / On-going Date of receipt of tenders = 21.10.2017, Date of 1468 3071 Nallian in Various UC's of PP-228 in District Pakpattan 74.312 25.000 16.437 12.328 8.450 69% 45% work order= 13.11.2017, Funds released by FD = Schemes Pakpattan 03.08.2018Funds online = 15.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Sewerage / Drainage Scheme Jamman On-going Date of receipt of tenders = 24.08.2017, Date of 1469 3072 Pakpattan 37.413 6.000 10.471 7.853 6.756 86% 34% work order= 31.10.2017, Funds released by FD = Shah in District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Sewerage / Drainage Scheme Chak No. On-going Date of receipt of tenders = 24.08.2017, Date of 1470 3073 Pakpattan 31.582 20.000 1.304 0.978 0.652 67% 65% work order= 23.09.2017, Funds released by FD = 123/EB in District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Rural Sewerage / Drainage Scheme Chak On-going Date of receipt of tenders = 24.08.2017, Date of 1471 3074 Pakpattan 36.230 27.376 2.610 1.958 1.770 90% 80% work order= 23.09.2017, Funds released by FD = No.211/EB in District Pakpattan Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Amended A.A issued on 27.01.2018.Tender received on 07.02.2018 and Additional performance Provision of Drainage/ Sewerage Schemes at security received on 13.02.2018 and Work order Chak No. 161/E.B and Union Council NO.35 On-going issued on 17.02.2018.Funds released by FD = 1472 3075 Pakpattan 35.785 12.976 6.762 5.072 0.000 0% 36% (Headquarters 13/EB) Tehsil Arifwala District Schemes 03.08.2018Funds online = 13.08.2018,Work in progress. Contractor liability amounting to Rs.2.500 Pakpattan million stands. The case submitted to P&D Department Lahore for correction of project code.

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Provision of PCC / Sewerage / Drainage / Tuff tiles On-going Date of receipt of tenders = 21.10.2017, Date of 1473 3076 Pakpattan 150.000 33.142 8.333 6.250 6.250 100% 26% work order= 13.11.2017,Funds released by FD = etc. in PP-227, District Pakpattan Schemes 03.08.2018Funds online = 15.08.2018,Work in progress.

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Provision of PCC / Sewerage / Drainage / Tuff tiles On-going Date of receipt of tenders = 21.10.2017, Date of 1474 3077 Pakpattan 148.624 34.998 16.667 12.500 9.250 74% 30% work order= 13.11.2017,Funds released by FD = etc. in NA-165, District Pakpattan Schemes 03.08.2018Funds online = 15.08.2018,Work in progress.

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Provision of PCC / Sewerage / Drainage / Tuff On-going Date of receipt of tenders = 21.10.2017, Date of 1475 3078 Pakpattan 148.624 31.997 8.333 6.250 5.150 82% 25% work order= 13.11.2017,Funds released by FD = Tiles etc. in PP-231 Schemes 03.08.2018Funds online = 15.08.2018,Work in progress.

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of Rural Water Supply and Drainage Scheme Basti invitation of tender 02.12.2017 5.Date of Receipt of On-going tenders 05.12.2017 6.Date of work order 10.01.2018 1476 3079 Nazak Nagar, Tehsil Jalapur Pirwala, District Multan 49.180 14.982 11.393 8.545 5.697 67% 42% Schemes 7.Date of Completion as per PC-l 30.06.2018 8. Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4578 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage / Sewerage Scheme Basti Bahadur On-going tenders 05.12.2017 6.Date of work order 22.12.2017 1477 3080 Multan 48.970 14.960 11.323 8.492 5.652 67% 42% Pur Tehsil Jalalpur Pirwala District Multan Schemes 7.Date of Completion as per PC-l 21.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage / Sewerage Scheme Shujat Pur On-going tenders 05.12.2017 6.Date of work order 23.12.2017 1478 3081 Multan 49.070 15.000 11.357 8.518 5.657 66% 42% Tehsil Jalalpur Pirwala District Multan Schemes 7.Date of Completion as per PC-l 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries - persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Chak No.55/M and On-going 18.10.2017 6.Date of work order 03.11.2017 7.Date 1479 3082 Multan 14.000 4.947 3.000 2.250 1.500 67% 46% 56/M District Multan Schemes of Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4572 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Chak No.71, 72 & On-going 18.10.2017 6.Date of work order 27.11.2017 7.Date 1480 3083 Multan 21.000 9.834 3.667 2.750 1.832 67% 56% 73/M District Multan Schemes of Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6354 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Chak No.76, 77 and On-going 18.10.2017 6.Date of work order 27.11.2017 7.Date 1481 3084 Multan 21.000 9.949 3.667 2.750 1.832 67% 56% 78/M District Multan Schemes of Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4687 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Chak No.79, 80 & On-going 18.10.2017 6.Date of work order 27.11.2017 7.Date 1482 3085 Multan 21.000 9.853 3.667 2.750 1.834 67% 56% 81/M District Multan Schemes of Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6554 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Rural Water Supply Scheme Mouza Obvra tender 27.09.2017 5.Date of Receipt of tenders On-going 1483 3086 Shumali Saray Khara and Jungle Ameer Hussain Multan 14.000 6.840 2.333 1.750 1.167 67% 57% 18.10.2017 6.Date of work order 03.11.2017 7.Date Schemes of Completion as per PC-l 02.05.2018 8. Anticipated District Multan date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12354 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Sewerage Scheme Basti Nandla North & On-going 1484 3087 Multan 45.000 14.990 3.333 2.500 2.459 98% 39% tenders 05.12.2017 6.Date of work order 19.01.2018 South District Multan Schemes 7.Date of Completion as per PC-l 18.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11358 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Sewerage Scheme Adda band Bosan, Roye On-going 1485 3088 Multan 40.600 9.919 3.333 2.500 1.667 67% 29% tenders 05.12.2017 6.Date of work order 01.01.2018 Hatti & Mattay Hatti District Multan Schemes 7.Date of Completion as per PC-l 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13474 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Ghousabad, District On-going 1486 3089 Multan 37.000 8.690 3.333 2.500 1.667 67% 28% 18.10.2017 6.Date of work order 29.12.2017 7.Date Multan Schemes of Completion as per PC-l 28.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 14879 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Chah On-going 18.10.2017 6.Date of work order 23.12.2017 7.Date 1487 3090 Multan 14.970 9.995 1.657 1.243 0.829 67% 72% Bananwala District Multan Schemes of Completion as per PC-l 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 9476 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of Rural Sewerage Scheme Taj Pur Sandila, invitation of tender 02.12.2017 5.Date of Receipt of On-going tenders 05.12.2017 6.Date of work order 29.12.2017 1488 3091 Dhareeban Thahti Sandila Faiz Town UC 95 Multan 49.980 14.980 3.333 2.500 1.667 67% 33% Schemes 7.Date of Completion as per PC-l 28.06.2018 8. Tehshil & District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4658 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Qasim Bela, Basti On-going 18.10.2017 6.Date of work order 28.12.2017 7.Date 1489 3092 Multan 32.410 13.975 3.333 2.500 1.667 67% 48% Langrial Tehsil and District Multan Schemes of Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4789 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Sewerage Scheme Mouza Ajwani / Sharif On-going tenders 05.12.2017 6.Date of work order 05.01.2018 1490 3093 Multan 96.500 29.998 3.333 2.500 1.667 67% 33% District Multan Schemes 7.Date of Completion as per PC-l 04.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6589 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage, Soling and Tuff Tile Scheme in On-going tenders 05.12.2017 6.Date of work order 17.01.2018 1491 3094 Multan 50.000 19.949 3.333 2.500 1.667 67% 43% Union Council Bagrian District Multan Schemes 7.Date of Completion as per PC-l 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage, Soling and Tuff Tile Scheme in On-going tenders 05.12.2017 6.Date of work order 27.12.2017 1492 3095 Multan 50.000 19.973 3.333 2.500 1.667 67% 43% Union Council Hilal Wajah District Multan Schemes 7.Date of Completion as per PC-l 26.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage, Soling and Tuff Tile Scheme in On-going tenders 05.12.2017 6.Date of work order 23.12.2017 1493 3096 Multan 50.000 19.981 3.333 2.500 1.667 67% 43% Union Council Gardez Pur District Multan Schemes 7.Date of Completion as per PC-l 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage / Sewerage Scheme Kotla Chakar On-going tenders 05.12.2017 6.Date of work order 28.12.2017 1494 3097 Multan 50.000 20.000 3.333 2.500 1.667 67% 43% Jalalpur Pirwala District Multan Schemes 7.Date of Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4587 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Basti Mithu On-going 1495 3098 Multan 30.000 9.850 3.333 2.500 1.667 67% 38% 18.10.2017 6.Date of work order 10.11.2017 7.Date Gharbi District Multan Schemes of Completion as per PC-l 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13254 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Muqeempur On-going 1496 3099 Multan 33.000 11.974 3.333 2.500 1.667 67% 41% 18.10.2017 6.Date of work order 21.12.2017 7.Date District Multan Schemes of Completion as per PC-l 20.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13546 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Munshi Wala On-going 1497 3100 Multan 39.000 11.994 3.333 2.500 1.667 67% 35% 18.10.2017 6.Date of work order 10.01.2018 7.Date District Multan Schemes of Completion as per PC-l 09.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12144 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Lal Wah On-going 1498 3101 Multan 25.000 9.931 3.333 2.500 1.667 67% 46% 18.10.2017 6.Date of work order 11.12.2017 7.Date District Multan Schemes of Completion as per PC-l 10.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 14456 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Obara On-going 1499 3102 Multan 30.000 11.699 3.333 2.500 1.667 67% 45% 18.10.2017 6.Date of work order 10.11.2017 7.Date Shumali District Multan Schemes of Completion as per PC-l 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11243 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Drainage / Sewerage Scheme Jagoo Wala On-going tenders 05.12.2017 6.Date of work order 01.02.2018 1500 3103 Multan 50.000 9.976 3.333 2.500 1.667 67% 23% District Multan Schemes 7.Date of Completion as per PC-l 30.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 3547 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Sewerage / Drainage Scheme Kotla Abdul On-going 18.10.2017 6.Date of work order 28.12.2017 7.Date 1501 3104 Multan 20.000 9.990 3.333 2.500 1.667 67% 58% Fateh District Multan Schemes of Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6547 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Rural Drainage Scheme Basti Kothy Wala, New tender 27.09.2017 5.Date of Receipt of tenders On-going 18.10.2017 6.Date of work order 19.02.2018 7.Date 1502 3105 Kothy Wala, Basti Utar Wali and Haroo Wala Multan 30.000 9.994 3.333 2.500 1.667 67% 39% Schemes of Completion as per PC-l 18.08.2018 8. Anticipated Mouza Kothy Wala District Multan date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries - persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders On-going 18.10.2017 6.Date of work order 28.01.2018 7.Date 1503 3106 Rural Drainage Scheme UC 18/MR, District Multan Multan 26.000 9.521 3.333 2.500 1.667 67% 43% Schemes of Completion as per PC-l 27.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries - persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Mouza Matotli and On-going 1504 3107 Multan 14.000 6.962 2.333 1.750 1.167 67% 58% 18.10.2017 6.Date of work order 03.11.2017 7.Date Qaiser Pur District Multan Schemes of Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 10452 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Mouza Sha Musa and On-going 1505 3108 Multan 14.000 6.942 2.333 1.750 1.167 67% 58% 18.10.2017 6.Date of work order 03.11.2017 7.Date Muqeem Pur District Multan Schemes of Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11365 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Rural Water Supply Scheme Mouza Adu Wali, tender 27.09.2017 5.Date of Receipt of tenders On-going 18.10.2017 6.Date of work order 14.12.2017 7.Date 1506 3109 Inayat Pur, Mochi Panhuwah, Basti Bairar District Multan 21.000 9.849 3.667 2.750 1.834 67% 56% Schemes of Completion as per PC-l 13.06.2018 8. Anticipated Multan date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 9878 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Water Supply Scheme Mouza Obvra Janubi, On-going 18.10.2017 6.Date of work order 03.11.2017 7.Date 1507 3110 Multan 15.000 6.844 2.667 2.000 1.334 67% 55% Basti Lang and Nauraja Bhutta District Multan Schemes of Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 7458 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of Rural Sewerage/ Drainage scheme Katcha Talla, invitation of tender 02.12.2017 5.Date of Receipt of On-going 1508 3111 ict Munirabad, Kot Shehbaz Pull 18-Kassi Bhdhla Multan 44.530 15.000 9.843 7.382 4.922 67% 45% tenders 05.12.2017 6.Date of work order 13.01.2018 Schemes 7.Date of Completion as per PC-l 30.06.2018 8. Road Tehsil & district Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11354 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of Rural Sewerage Scheme 18-Kassi Ghareeb Abad invitation of tender 02.12.2017 5.Date of Receipt of On-going tenders 05.12.2017 6.Date of work order 28.12.2017 1509 3112 and Adjoining Abadies UC Jhok Lashkar Pur Multan 44.470 14.956 9.823 7.367 4.912 67% 45% Schemes 7.Date of Completion as per PC-l 27.06.2018 8. District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4687 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Asghar Pur and Munir On-going 18.10.2017 6.Date of work order 23.12.2017 7.Date 1510 3113 Multan 15.000 10.000 1.667 1.250 0.834 67% 72% Abad, UC Jhok Lashkar Pur District Multan Schemes of Completion as per PC-l 22.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4589 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage Scheme UC Kot Rab Nawaz, UC On-going 18.10.2017 6.Date of work order 14.12.2017 7.Date 1511 3114 Multan 15.000 10.000 1.667 1.250 0.834 67% 72% 120 District Multan Schemes of Completion as per PC-l 13.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage Scheme UC 123 Jalal Abad On-going 18.10.2017 6.Date of work order 28.12.2017 7.Date 1512 3115 Multan 15.000 9.962 1.667 1.250 0.834 67% 72% Shumali District Multan Schemes of Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage Scheme UC 131 Chatha District On-going 18.10.2017 6.Date of work order 03.11.2017 7.Date 1513 3116 Multan 20.000 9.997 3.333 2.500 1.667 67% 58% Multan Schemes of Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage Scheme UC 134 Kiri Tamak On-going 18.10.2017 6.Date of work order 21.11.2017 7.Date 1514 3117 Multan 20.000 9.910 3.333 2.500 1.667 67% 58% District Multan Schemes of Completion as per PC-l 20.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Basti Beat Wala Ajwain On-going 1515 3118 Multan 11.540 4.982 2.180 1.635 1.090 67% 53% 18.10.2017 6.Date of work order 28.12.2017 7.Date Sharif Tehsil & District Multan Schemes of Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries= 12358 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Sewerage Scheme Tiab Masood Pur, Tehsil On-going tenders 05.12.2017 6.Date of work order 23.12.2017 1516 3119 Multan 33.470 12.346 3.333 2.500 1.667 67% 42% 7.Date of Completion as per PC-l 22.06.2018 8. & District Multan Schemes Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =14356 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Sharif Pura New On-going 1517 3120 Multan 38.080 10.625 3.333 2.500 1.662 66% 32% 18.10.2017 6.Date of work order 19.01.2018 7.Date Shalimar Tehsil & District Multan Schemes of Completion as per PC-l 18.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =10358 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Rural Sewerage Scheme Gareen Town Deen Pur On-going tenders 05.12.2017 6.Date of work order 14.02.2018 1518 3121 Multan 41.960 7.499 3.333 2.500 1.664 67% 22% 7.Date of Completion as per PC-l 13.08.2018 8. & Jarran Wala District Multan Schemes Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =12548 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Sewerage Scheme Zakaria Town Phase-III District On-going 1519 3122 Multan 16.500 9.908 2.167 1.625 1.084 67% 67% 18.10.2017 6.Date of work order 27.11.2017 7.Date Multan Schemes of Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =14225 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Main Sewerage Line for Farrukh Town & Raja Pur, On-going tenders 05.12.2017 6.Date of work order 04.01.2018 1520 3123 Multan 49.990 25.000 3.333 2.500 1.660 66% 53% 7.Date of Completion as per PC-l 03.06.2018 8. District Multan Schemes Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =11658 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders On-going 1521 3124 Water Purification Plants 10 District Multan Multan 20.000 9.940 3.333 2.500 1.667 67% 58% 18.10.2017 6.Date of work order 14.12.2017 7.Date Schemes of Completion as per PC-l 13.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =14212 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders Rural Drainage Scheme UC-Khan Pur maral, On-going 18.10.2017 6.Date of work order 30.01.2018 7.Date 1522 3125 Multan 13.000 9.967 1.000 0.750 0.500 67% 81% District Multan Schemes of Completion as per PC-l 29.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Funds for drain/sewerage and soling for UC 95 & On-going tenders 05.12.2017 6.Date of work order 05.01.2018 1523 3126 Multan 80.000 26.735 3.333 8.884 8.783 99% 44% 96 City Shujabad. District Multan Schemes 7.Date of Completion as per PC-l 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 10.No. of beneficiaries 5587 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Funds for drain/sewerage, soling from Raja Ram, On-going 1524 3127 Multan 40.000 16.976 3.333 2.500 1.665 67% 47% tenders 05.12.2017 6.Date of work order 23.12.2017 Bagrain and Shahpur. District Multan Schemes 7.Date of Completion as per PC-l 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries= 6987 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 Rural Sewerage and Drainage Scheme, Tuff Tile 3.Dated of Prequalification - 4.Date of invitation of Pavement in Basti Ado Wali, Basti Adam Wali, tender 27.09.2017 5.Date of Receipt of tenders On-going 1525 3128 Basti Dhando, Basti Hayat Pur, Basti Balocha, Multan 28.000 14.999 4.333 3.250 2.167 67% 61% 18.10.2017 6.Date of work order 21.11.2017 7.Date Schemes of Completion as per PC-l 20.05.2019 8. Anticipated Wach Sandela, Basti Ali Pur Sadat and Basti Gull date of completion 30.06.2018 9. Date of released Wala UC Ali Pur Sadat District Multan of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =15325 persons. Work is in progress

Rural Sewerage and Drainage Scheme, Tuff Tile Pavement in Basti Brar, Basti Pathan Wala, Basti 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Ahmad Wali, Basti Daya, Basti Barzawah, Basti tender 27.09.2017 5.Date of Receipt of tenders Lohar, Basti Inayat Pur, Basti Sial, Basti Saif Ullah On-going 18.10.2017 6.Date of work order 29.11.2017 7.Date 1526 3129 Multan 30.000 9.972 6.667 5.000 3.334 67% 44% Shah, Basti Gakhar, Basti Bagh Arain Wali, Basti Schemes of Completion as per PC-l 28.05.2019 8. Anticipated date of completion 30.06.2018 9. Date of released Miani, Basti Ranojha, Basti Saich Wali, Basti of funds 30.08.2018 24.01.2019 10.No. of Deewan Wali and Basti Mochian Wali UC Inayat beneficiaries 16358 persons. Work is in progress Pur District Multan 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 Rural Sewerage and Drainage Scheme, Tuff Tile 3.Dated of Prequalification - 4.Date of invitation of Pavement in Basti Radal Pur, Basti Lutaf Pur, tender 27.09.2017 5.Date of Receipt of tenders On-going 1527 3130 Chak Numberabad, Molvi Wala, Basti Cut Wala, Multan 30.000 9.800 3.333 2.500 1.667 67% 38% 18.10.2017 6.Date of work order 28.12.2017 7.Date Schemes of Completion as per PC-l 27.06.2019 8. Anticipated Tibbi Qasian, Basti Balochan Wala UC Radal Pur date of completion 30.06.2018 9. Date of released District Multan of funds 30.08.2018 24.01.2019 10.No. of beneficiaries 14325 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Rural Sewerage and Drainage Scheme, Tuff Tile tender 27.09.2017 5.Date of Receipt of tenders Pavement in Basti Mari Noon, Basti Godar, Basti On-going 1528 3131 Multan 30.000 11.997 3.333 2.500 1.667 67% 46% 18.10.2017 6.Date of work order 28.12.2017 7.Date Dogran, Basti Khokhran, Basti Ghous Pur UC Mari Schemes of Completion as per PC-l 27.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released Noon District Multan of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12442 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 09.09.2017 3.Dated of Prequalification - 4.Date of invitation of Rough Cost Estimates for replacement of Old tender 27.09.2017 5.Date of Receipt of tenders Sewer Lines at Muhalla Sharif Pura UC 65 Piran On-going 1529 3132 Multan 12.450 8.334 0.817 0.613 0.409 67% 70% 18.10.2017 6.Date of work order 20.11.2017 7.Date Ghaib II in Sub Division New Multan Sewerage Schemes of Completion as per PC-l 19.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released Central Division WASA Multan of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13225 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of Ext. of Rual Drainage / Sewerage Scheme Chah tender 27.09.2017 5.Date of Receipt of tenders On-going 1530 3133 Muhammad Hussain wala & Adjoining Ababdies Multan 29.510 12.478 3.333 2.500 1.667 67% 48% 18.10.2017 6.Date of work order 22.11.2017 7.Date Schemes of Completion as per PC-l 21.05.2018 8. Anticipated District Multan date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12455 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of Scheme / Drainage Scheme Kotli Nijabat District On-going 1531 3134 Multan 69.500 21.924 3.333 2.500 1.667 67% 34% tenders 05.12.2017 6.Date of work order 05.01.2018 Multan Schemes 7.Date of Completion as per PC-l 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 15654 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of On-going tenders 05.12.2017 6.Date of work order 03.03.2018 1532 3135 Sewerage System in UC-90 District Multan Multan 65.000 4.958 3.333 2.500 1.667 67% 10% Schemes 7.Date of Completion as per PC-l 02.08.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 9876 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of On-going 1533 3136 Sewerage System in UC-82 District Multan Multan 65.000 22.996 3.333 2.500 1.667 67% 38% tenders 05.12.2017 6.Date of work order 20.02.2018 Schemes 7.Date of Completion as per PC-l 19.02.2020 8. Anticipated date of completion 30.06.2020 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 15775 persons. Work is in progress

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2018 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme Chak No.7/9-R District On-going 1534 3137 Khanewal 12.000 6.000 2.000 1.500 1.169 78% 60% order: 24.10.2017 7. Date of Completion as per PC- Khanewal Schemes I: (6) months 8. Anticipated Date of completion: 31.12.2018 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6340 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Construction of Drainage Scheme Chak No.93/10- On-going 1535 3138 Khanewal 12.000 2.000 3.333 2.500 2.385 95% 37% order: 09.11.2017 7. Date of Completion as per PC- R District Khanewal Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5788Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme Chak No.92/10-R District On-going 1536 3139 Khanewal 18.000 10.000 2.667 2.000 1.891 95% 66% order: 09.12.2017 7. Date of Completion as per PC- Khanewal Schemes I: (8) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 8140 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme UC No. 48 Tehsil Mian On-going 1537 3140 Khanewal 11.000 5.000 2.000 1.500 1.500 100% 59% order: 24.10.2017 7. Date of Completion as per PC- Channu Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 8265 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme UC No. 51 Tehsil Mian On-going 1538 3141 Khanewal 12.000 6.000 2.000 1.500 1.125 75% 59% order: 09.12.2017 7. Date of Completion as per PC- Channu Schemes I: (5) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6568 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme UC No. 55 Tehsil Mian On-going 1539 3142 Khanewal 12.000 7.000 1.667 1.250 1.019 82% 67% order: 24.10.2017 7. Date of Completion as per PC- Channu Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 65619 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme UC No. 56 Tehsil Mian On-going 1540 3143 Khanewal 11.000 6.000 1.667 1.250 0.937 75% 63% order: 17.11.2017 7. Date of Completion as per PC- Channu Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5790 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme UC No. 62 Tehsil Mian On-going 1541 3144 Khanewal 12.000 6.000 2.000 1.500 1.119 75% 59% order: 24.10.2017 7. Date of Completion as per PC- Channu Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5689 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Rural Drainage Scheme Chak No.134/16-L and On-going 1542 3145 Khanewal 12.000 6.000 2.000 1.500 1.211 81% 60% order: 24.10.2017 7. Date of Completion as per PC- Adjoining Abadies Tehsil Mian Channu Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6132 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Rural Drainage Scheme Chak No 20/8-BR, 1/8-R, Receipt of Tender: 29.09.2017 6. Date of Work On-going 1543 3146 2/8-R, 3/8-R, 4/8-R and Adjoining Abadies Tehsil Khanewal 12.000 7.000 1.667 1.250 0.949 76% 66% order: 24.10.2017 7. Date of Completion as per PC- Schemes I: (6) months 8. Anticipated Date of completion: Mian Channu 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6443 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work On-going 1544 3147 Drainage & Soling 122/15-L District Khanewal Khanewal 3.000 2.385 0.167 0.125 0.100 80% 83% order: 24.10.2017 7. Date of Completion as per PC- Schemes I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1936 Persons Scheme Completed in saving. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work On-going 1545 3148 Drainage & Soling 53/15-L District Khanewal Khanewal 3.000 2.500 0.167 0.125 0.094 75% 86% order: 24.10.2017 7. Date of Completion as per PC- Schemes I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1876 Persons Scheme Completed in saving. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work On-going 1546 3149 Drainage & Soling 58/15-L District Khanewal Khanewal 3.000 2.500 0.167 0.125 0.100 80% 87% order: 24.10.2017 7. Date of Completion as per PC- Schemes I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1916 Persons Work is in Progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work On-going 1547 3150 Drainage & Soling 117/15-L District Khanewal Khanewal 3.000 2.500 0.167 0.125 0.106 85% 87% order: 19.10.2017 7. Date of Completion as per PC- Schemes I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 2065 Persons Scheme Completed in Saving. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work On-going 1548 3151 Drainage & Soling 42/15-L District Khanewal Khanewal 3.000 2.500 0.167 0.125 0.094 75% 86% order: 24.10.2017 7. Date of Completion as per PC- Schemes I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1837 Persons Scheme Completed in Saving. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work On-going 1549 3152 Drainage & Soling 135/16-L District Khanewal Khanewal 3.000 2.500 0.167 0.125 0.105 84% 87% order: 24.10.2017 7. Date of Completion as per PC- Schemes I: (5) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1926 Persons Work is in Progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Drainage & Soling Pakka Haji Majeed District On-going 1550 3153 Khanewal 3.000 1.700 0.433 0.325 0.277 85% 66% order: 24.10.2017 7. Date of Completion as per PC- Khanewal Schemes I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1966 Persons Work is in Progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 20.09.2017 3. Date of Pre-Qualification: 05.09.2017 4. Date of Invitation of Tender: 09.11.2017 5. Date of Receipt of Tender: 11.11.2017 6. Date of Work Rehabilitation of Sewerage Scheme Tulamba City On-going 1551 3154 Khanewal 49.990 15.000 3.333 2.500 2.258 90% 35% order: 23.11.2017 7. Date of Completion as per PC- in missed area Tehsil Mian Channu Schemes I: (12)months 8. Anticipated Date of completion: 31.12.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 2690 Persons Work is in progress. 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work Drainage & Soling Chak No.8-9/8-AR District On-going 1552 3155 Khanewal 3.000 2.500 0.167 0.125 0.112 90% 87% order: 24.10.2017 7. Date of Completion as per PC- Khanewal Schemes I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1896 Persons Scheme Completed in Saving. 1. Date of A.A: 19.08.2017 2. Date of T.S: Constructino of Soling, Drains, Sullage Carrier, 22.09.2017 3. Date of Pre-Qualification: 05.09.2017 RCC Culverts in Union Councils Salar Wahan, 4. Date of Invitation of Tender: 09.11.2017 5. Date of Receipt of Tender: 11.11.2017 6. Date of Work Thull Najeeb, Man Kot, Chak Norang Shah, Boota On-going order: 26.12.2017 7. Date of Completion as per PC- 1553 3156 Singh, Mari Sahu Ibrahim Pur, Mubarak Pur, 5- Khanewal 199.990 72.900 16.667 12.500 11.919 95% 42% I: 31.12.2018 8. Anticipated Date of completion: Schemes Kassi, Mula Pur, Nabi Pur, Chak Haider Abad & 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 Monga Wala Tehsil Kabirwala in PP-213 District No. of beneficiaries 11356 Persons Work is in Khanewal Progress. Rs. 118.765 Million are required to complete the scheme.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Water Supply Scheme Chak No.126/WB, 128/WB On-going of Tender: 24.10.2017 6. Date of Award: 11.12.2017 1554 3157 Vehari 28.966 9.995 6.322 4.742 3.570 75% 47% 7. Date of Completion as per PC-I: 10.12.2018 8. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rehabiliation of Water Supply Scheme Chak On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1555 3158 Vehari 15.000 7.443 1.667 1.250 0.930 74% 56% 7. Date of Completion as per PC-I: 24.11.2018 8. No.96/WB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019+ 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Provision of Water Supply / Filtration Plants & On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1556 3159 Sewerage Scheme Chak No.233/EB District Vehari 17.639 3.877 2.546 1.910 1.390 73% 30% 7. Date of Completion as per PC-I: 24.11.2018 8. Schemes Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Provision of Water Supply / Filtration Plants & On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1557 3160 Sewerage Scheme Chak No.249/EB District Vehari 24.842 5.246 4.947 3.710 2.778 75% 32% 7. Date of Completion as per PC-I: 24.11.2018 8. Schemes Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Provision of Water Supply / Filtration Plants & On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1558 3161 Sewerage Scheme Chak No.251/EB District Vehari 23.451 6.682 4.484 3.363 2.450 73% 39% 7. Date of Completion as per PC-I: 24.11.2018 8. Schemes Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress. 1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Provision of Water Supply / Filtration Plants & On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1559 3162 Sewerage Scheme Chak No.243/EB District Vehari 20.663 3.934 3.554 2.666 1.980 74% 29% 7. Date of Completion as per PC-I: 24.11.2018 8. Schemes Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Sewerage / Drainage & Water Supply On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1560 3163 Vehari 31.617 9.998 3.333 2.500 1.890 76% 38% 7. Date of Completion as per PC-I: 24.11.2018 8. Scheme Chak No.65/WB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: Construction of Water Filtration Plants 16-No in 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Chak No.05/WB, 18/WB, 22/WB, 65/WB, 59/WB, On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1561 3164 93/WB, 97/WB, 56/Wb, 34/WB, Pull-48, Pull Vehari 48.000 13.853 11.000 8.250 5.990 73% 41% 7. Date of Completion as per PC-I: 24.11.2018 8. Schemes Mohsin Shah, 63/WB, 24/WB, 26/WB, Noor Shah Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Melsi, Shittab Garh Melsi. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Water Supply Scheme 176/WB On-going of Tender: 24.10.2017 6. Date of Award: 20.11.2017 1562 3165 Vehari 25.171 9.833 5.057 3.793 3.450 91% 53% 7. Date of Completion as per PC-I: 19.11.2018 8. Baghbanpura District Vehari Schemes Anticipated Date of Completion: 30.06.2019. 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Water Supply Scheme Chak No.182/WB On-going of Tender: 24.10.2017 6. Date of Award: 22.11.2017 1563 3166 Vehari 16.073 9.999 2.024 1.518 1.150 76% 69% 7. Date of Completion as per PC-I: 19.11.2018 8. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: --- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Water Supply Scheme Chak No.184/WB On-going of Tender: 24.10.2017 6. Date of Award: 25.11.2017 1564 3167 Vehari 28.673 9.991 6.224 4.668 3.388 73% 47% 7. Date of Completion as per PC-I: 24.11.2018 8. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Water Supply Scheme Chak No.161/WB On-going of Tender: 24.10.2017 6. Date of Award: 20.11.2017 1565 3168 Vehari 18.426 10.000 2.809 2.107 1.560 74% 63% 7. Date of Completion as per PC-I: 19.11.2018 8. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Water Supply Scheme Chak No.163/WB On-going of Tender: 24.10.2017 6. Date of Award: 20.11.2017 1566 3169 Vehari 31.485 9.960 7.162 5.372 4.980 93% 47% 7. Date of Completion as per PC-I: 19.11.2018 8. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress. 1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt Rural Water Supply Scheme Chak No.159/WB On-going of Tender: 24.10.2017 6. Date of Award: 20.11.2017 1567 3170 Vehari 17.583 9.978 2.528 1.896 1.450 76% 65% 7. Date of Completion as per PC-I: 19.11.2018 8. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: --- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 21.08.2017 2. Date of T.S: 19.10.2017 3. Date of Pre-Qualification: 27.10.2017 4. Date Invitation of Tender: 29.11.2017 5. Date of Rural Water Supply Scheme Chak No.50/WB On-going Receipt of Tender: 30.11.2017 6. Date of Award: 1568 3171 Vehari 123.590 34.755 16.667 12.500 9.370 75% 36% 27.12.2017 7. Date of Completion as per PC-I: Dahlu Hari Chand and 52 Sharqi District Vehari Schemes 26.12.2019 8. Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: --- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Sewerage Schemes Chak No.5/WB, 24/WB, 88/ On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1569 3172 Vehari 40.000 8.323 3.333 2.500 1.870 75% 25% 7. Date of Completion as per PC-I: 24.11.2018 8. WB and 90/WB. District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Drainage Sewer Scheme Chak No.110/WB District On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1570 3173 Vehari 20.000 9.999 3.333 2.500 1.840 74% 59% 7. Date of Completion as per PC-I: 24.11.2018 8. Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling, Drainage & Culverts UC 46- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1571 3174 Vehari 15.000 6.917 2.500 1.875 1.430 76% 56% 7. Date of Completion as per PC-I: 24.11.2018 8. 173/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling, Drainage & Culverts UC 53- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1572 3175 Vehari 15.000 7.165 2.500 1.875 1.410 75% 57% 7. Date of Completion as per PC-I: 24.11.2018 8. 275/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: - 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: Construction of Soling, Drainage & Culverts UC 40- On-going 28.10.2017 6. Date of Award: 25.11.2017 7. Date of 1573 3176 Vehari 15.000 9.807 1.667 1.250 0.945 76% 72% Completion as per PC-I: 24.11.2018 8. Anticipated 128/EB District Vehari Schemes Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling, Drainage & Culverts UC 44- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1574 3177 Vehari 15.000 9.967 1.667 1.250 0.940 75% 73% 7. Date of Completion as per PC-I: 24.11.2018 8. 199/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress. 1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling, Drainage & Culverts UC 45- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1575 3178 Vehari 15.000 7.499 2.500 1.875 1.420 76% 59% 7. Date of Completion as per PC-I: 24.11.2018 8. 175/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling , Drainage & Culverts UC49- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1576 3179 Vehari 25.000 12.285 4.167 3.125 2.341 75% 59% 7. Date of Completion as per PC-I: 26.11.2018 8. 233/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling , Drainage & Culverts UC47- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1577 3180 Vehari 25.000 12.500 4.167 3.125 2.325 74% 59% 7. Date of Completion as per PC-I: 24.11.2018 8. 215/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 07.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Construction of Soling , Drainage & Culverts UC48- On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1578 3181 Vehari 15.000 12.499 0.833 0.625 0.460 74% 86% 7. Date of Completion as per PC-I: 24.11.2018 8. 187/EB District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt Rural Sewerage / Drainage Scheme Chak No. On-going of Tender: 28.10.2017 6. Date of Award: 25.11.2017 1579 3182 Vehari 15.000 6.915 2.667 2.000 1.740 87% 58% 7. Date of Completion as per PC-I: 24.11.2018 8. 57/WB Tehsil & District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of receipt Rural Sewerage / Drainage Scheme Chak No. On-going of tender: 28.10.2017 6. Date of Award: 25.11.2017 1580 3183 Vehari 16.000 7.999 2.667 2.000 1.780 89% 61% 7. Date of Completion as per PC-I: 24.11.2018 8. 53/WB Tehsil & District Vehari Schemes Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 06.09.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: 27.10.2017 4. Date Invitation of Tender: 29.11.2017 5. Date of Rehabilitation and Extension of Water Supply & On-going receipt of tender: 30.11.2017 6. Date of Award: 1581 3184 Sewerage Schemes Mailsi and Adjoining Abadies. Vehari 279.804 74.459 33.333 25.000 18.570 74% 33% 19.01.2018 7. Date of Completion as per PC-I: Schemes District Vehari 18.01.2021 8. Anticipated Date of Completion: 18.01.2021 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

Construction of Nali Soling Tuff Tile & Culverts UC Dera Ghazi On-going 1582 3185 11.500 4.955 2.167 1.625 1.203 74% 54% "• Date of A.A = 13.1.17 Kot Mubarak, Shero Satal and Yaroo DG Khan Khan Schemes Construction of Nali Soling Culverts and Tuff Tile Dera Ghazi On-going 1583 3186 20.000 9.975 3.333 2.500 1.875 75% 59% "• Date of A.A = 13.1.17 U/C Palgah Chak NO.3 DG Khan Khan Schemes Construction of Nali Soling & Culverts UC Dagar Dera Ghazi On-going 1584 3187 13.000 6.999 2.000 1.500 1.140 76% 63% "• Date of A.A = 13.1.17 Chitt. DG Khan Khan Schemes Construction of Nali Soling Tuff Tile of Basti Foja Dera Ghazi On-going 1585 3188 14.000 6.643 2.333 1.750 1.313 75% 57% "• Date of A.A = 13.1.17 and Darkhast Jamal Janubi DG Khan Khan Schemes Construction of Nali Soling Tuff Tiles in UC Basti Dera Ghazi On-going 1586 3189 13.610 6.617 2.203 1.652 1.206 73% 57% "• Date of A.A = 13.1.17 Malana DG Khan Khan Schemes Construction of Sewerage Nali Soling & Culverts / Dera Ghazi On-going 1587 3190 11.000 4.986 2.000 1.500 1.065 71% 55% "• Date of A.A = 13.1.17 Bridge UC Khakhi. DG Khan Khan Schemes Construction of Nali Soling Tuff Tile & Culverts UC Dera Ghazi On-going 1588 3191 12.000 4.985 2.333 1.750 1.260 72% 52% "• Date of A.A = 13.1.17 Kala DG Khan Khan Schemes Construction of Nali Soling Tuff Tile & Culverts UC Dera Ghazi On-going 1589 3192 14.000 6.000 2.667 2.000 1.460 73% 53% "• Date of A.A = 13.1.17 Shadan Lund DG Khan Khan Schemes Construction of Nali / Drainage Tuff Tile Choti City Dera Ghazi On-going 1590 3193 40.000 14.264 8.333 6.250 4.500 72% 47% "• Date of A.A = 13.1.17 and Colonies DG Khan Khan Schemes Water Supply Scheme City Choti Zereen District Dera Ghazi On-going 1591 3194 50.000 14.999 11.667 8.750 6.388 73% 43% "• Date of A.A = 25.7.2017 DG Khan Khan Schemes Rehabilitation and Augmentation of Water Supply Dera Ghazi On-going 1592 3195 30.000 4.999 3.333 2.500 1.800 72% 23% "• Date of A.A = 25.7.2017 Scheme of Choti Zareen Khan Schemes Rural Water Supply Scheme Nutkani District DG Dera Ghazi On-going 1593 3196 80.000 29.999 10.000 7.500 5.325 71% 44% "• Date of A.A = 16.09.2017 Khan Khan Schemes Construction of PCC Drainage / Tuff Tile in NA-171 Dera Ghazi On-going 1594 3197 155.000 26.295 33.333 25.000 18.000 72% 29% "• Date of A.A = 16.09.2017 DG Khan Khan Schemes Rehabilitation of Water Supply in Block Churatta Dera Ghazi On-going 1595 3198 20.000 9.964 3.333 2.500 1.850 74% 59% "• Date of A.A = 25.7.2017 District DG Khan Khan Schemes Rehabilitation of Water Supply in Union Gaddai Dera Ghazi On-going 1596 3199 20.000 9.999 3.333 2.500 1.825 73% 59% "• Date of A.A = 25.7.2017 District DG Khan Khan Schemes Construction of Nali Soling Tuff Tiles & Culverts Dera Ghazi On-going 1597 3200 3.000 2.354 0.167 0.125 0.088 70% 81% "• Date of A.A = 25.7.2017 UC Shero Satai DG Khan Khan Schemes Construction of Nali Soling Culverts Jhok,Uttra DG Dera Ghazi On-going 1598 3201 3.000 2.438 0.167 0.125 0.091 73% 84% "• Date of A.A = 25.7.2017 Khan Khan Schemes Construction of Nali Soling in Jukharr Imam & Dera Ghazi On-going 1599 3202 3.000 2.474 0.167 0.125 0.093 74% 86% "• Date of A.A = 25.7.2017 Sherru Qasbas Khan Schemes Sewerage and Tuff Tiles in PP-244 District DG Dera Ghazi On-going 1600 3203 90.000 49.000 6.667 5.000 3.500 70% 58% "• Date of A.A = 16.09.2017 Khan Khan Schemes Rehabilitation of Rural Water Supply Scheme in On-going 1601 3204 Thul Sirak & Thul Jaman Tehsil Jampur, District Rajanpur 15.000 10.000 1.667 1.250 0.834 67% 72% "• Date of A.A = 09.01.2018 Schemes Rajanpur. Provision of Sewerage & Tuff Tile Kot Tahir City On-going 1602 3205 Rajanpur 20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017. District Rajanpur Schemes Installation of 1000 Nos. Deep Hand Pumps at On-going 1603 3206 Rajanpur 35.000 12.000 7.667 5.750 3.834 67% 45% "• Date of A.A = 04.08.2017. Pachad Area, District Rajanpur. Schemes Rehabilitation of water supply in scheme Basti On-going 1604 3207 Rajanpur 16.000 8.000 2.667 2.000 1.334 67% 58% "• Date of A.A = 04.08.2017. Tuski in District Rajan Pur Schemes Water supply scheme in Veeni Khosa to Hajoo Via On-going 1605 3208 Basti Riaz hambae UC-Wah Lashari in District Rajanpur 13.000 5.993 2.333 1.750 1.167 67% 55% "• Date of A.A = 04.08.2017. Schemes Rajanpur On-going 1606 3209 Deep Hand Pump in Pachad Area 200No Rajanpur 50.000 16.000 11.333 8.500 5.667 67% 43% "• Date of A.A = 04.08.2017. Schemes Rural drainage / sewerage, PCC & Tuff Tile On-going 1607 3210 Flooring Rajanpur City of left over area District Rajanpur 20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017. Schemes Rajanpur Construction of Tuff Tile, Soling, Sewerage, On-going 1608 3211 Rajanpur 25.000 10.000 5.000 3.750 2.500 67% 50% "• Date of A.A = 04.08.2017. Drainage and Street etc Rajan Pur City Schemes Construction of Street, Soling, Sewerage, On-going 1609 3212 Rajanpur 25.000 10.000 5.000 3.750 2.500 67% 50% "• Date of A.A = 04.08.2017. Drainage, Tuff tiles in District Rajan Pur City Schemes Provision of Sewerage & Tuff Tile at Basti Cheena, On-going 1610 3213 Rajanpur 30.000 10.000 6.667 5.000 3.334 67% 44% "• Date of A.A = 04.08.2017. Basti Talai Wala U/C Kot Janu. Disrict Rajan Pur Schemes Provision of Sewerage & Tuff Tile Noshera Gharbi. On-going 1611 3214 Rajanpur 20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017. Disrict Rajan Pur Schemes Provision of Sewerage and Tuff Tile Kotla On-going 1612 3215 Rajanpur 30.000 9.990 6.667 5.000 3.334 67% 44% "• Date of A.A = 04.08.2017. Mughlan. Disrict Rajan Pur Schemes Construction of Soling and Drain UC Jhugi Wala On-going 1613 3216 Muzaffargarh 20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 31.7.2017 District Muzaffargarh Schemes Construction of Soling, Tuff Tiles & Drain UC On-going 1614 3217 Muzaffargarh 20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 31.7.2017 Seetpur District Muzaffargarh Schemes Provision of Soling Tuff Tiles & Drains in Union On-going 1615 3218 Muzaffargarh 20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018 Council Alludewall, District Muzaffargarh (Revised) Schemes Construction of Soling Tuff Tiles & Drains in Union On-going 1616 3219 Council Meeran Pur, District Muzaffargarh Muzaffargarh 20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018 Schemes (Revised) Construction of Soling Tuff Tiles & Drains in Union On-going 1617 3220 Council Usman Koria, District Muzaffargarh Muzaffargarh 20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018 Schemes (Revised) Construction of PCC/ Drainage and Tuff Tiles On-going 1618 3221 Muzaffargarh 90.000 25.000 6.667 5.000 3.200 64% 31% Date of A.A 06.9.2017 District Muzaffargarh Schemes Provision of Tuff Tile, Sewerage and Drainage in On-going 1619 3222 Urban Area Municipal Committee Chowk Sarwar Muzaffargarh 40.000 10.000 30.000 22.500 10.450 46% 51% • Date of AA 5.8.2017 Schemes Shaheed District Muzaffargarh Construction of Soling and Driange work in UC- On-going 1620 3223 Dammar Wala and Kotla Gmaoon, District Muzaffargarh 25.000 10.000 5.000 3.750 2.500 67% 50% Date of AA 31.7.2017 Schemes Muzaffargarh Construction of Soling and Driange work in Calor On-going 1621 3224 Wali Qadir Pur and Damar Wali, District Muzaffargarh 25.000 10.000 5.000 3.750 2.500 67% 50% Date of AA 31.7.2017 Schemes Muzaffargarh Construction of Soling and Driange work in Janda On-going 1622 3225 Wali Aluda Wali and Mahal Khakhi, District Muzaffargarh 15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017 Schemes Muzaffargarh Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1623 3226 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Kotla Gamon District Muzaffargarh Schemes Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1624 3227 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Kotla Lal Shah District Muzaffargarh Schemes Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1625 3228 Muzaffargarh 30.000 13.250 3.333 2.500 1.667 67% 50% Date of AA 31.7.2017 Shehr Sultan District Muzaffargarh Schemes Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1626 3229 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Vains District Muzaffargarh Schemes Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1627 3230 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Jhalarin District Muzaffargarh Schemes Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1628 3231 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Bair Bund District Muzaffargarh Schemes Const: of Soling Drain Tuff Tile VR Bridges UC On-going 1629 3232 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Binda Ishaq District Muzaffargarh Schemes Drainange / Soling / Tuff Tile / Culverts Gul Wala, On-going 1630 3233 Muzaffargarh 30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017 Khanpur Fazil Kalroo District Muzaffargarh Schemes

Construction of Soling and Driange work in UC- On-going 1631 3234 Muzaffargarh 15.000 5.000 3.333 2.500 1.667 67% 44% Date of AA 31.7.2017 Vains and Basti Arif Wala, District Muzaffargarh Schemes Construction of Soling and Driange work in Jatoi, On-going 1632 3235 Rampur, Nichrani, Baber, Azam Khan and Kasir Muzaffargarh 15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017 Schemes Gazlani, District Muzaffargarh Construction of Soling and Driange work in Rohilan On-going 1633 3236 Wali, Binday Wali and Khakhi, District Muzaffargarh 15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017 Schemes Muzaffargarh Construction of Soling and Driange work in Miyan On-going 1634 3237 Sawar Mochi Wala Ganga and Khakhi, District Muzaffargarh 15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017 Schemes Muzaffargarh Construction of Soling and Driange work in Baily On-going 1635 3238 Wala and Bait Umar Draz and Bindi Pitafi, District Muzaffargarh 15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017 Schemes Muzaffargarh Cosntruction of Soling / Drainage and Culverts Tuff On-going 1636 3239 Tiles Municipal Committee Daira Deen Panah Muzaffargarh 20.000 9.000 3.333 2.500 2.167 87% 56% Date of AA 31.7.2017 Schemes District Muzaffargarh Drainage / Soling / UC Thath Gurmani, U/C Gurmani Sharqi, U/C Sheikh Umar, U/C Daya On-going 1637 3240 Muzaffargarh 100.000 33.500 6.667 5.000 3.300 66% 37% Date of A.A 06.9.2017 Jokha Sharqi, U/C Gujrat U/C Allud District Schemes Muzaffargarh Muzaffargarh City Sewerage Scheme Soling / On-going 1638 3241 Muzaffargarh 50.000 20.000 3.333 2.500 1.667 67% 43% Date of AA 31.7.2017 Drainage, Tuff Tiles District Muzaffargarh Schemes Construction of Soling / Drainage Tuff Tiles Union On-going 1639 3242 Muzaffargarh 30.000 10.000 3.333 2.500 1.667 67% 39% Date of AA 31.7.2017 Council Taleri Doaba District Muzaffargarh Schemes

Construction of Soling / Drainage Tuff Tiles Union On-going 1640 3243 Muzaffargarh 30.000 10.000 3.333 2.500 1.640 66% 39% Date of AA 31.7.2017 Council Bhutta Pur District Muzaffargarh Schemes

Drainage / Soling / Tuff Tiles / Culverts K.D Qurehi, On-going 1641 3244 Gulqaim Mastoi, Budh, Wanpitafi, Sharif Chujra, Ali Muzaffargarh 50.000 20.000 3.333 2.500 1.667 67% 43% Date of AA 31.7.2017 Schemes Dah, Dawna, Mehmood Kot District Muzaffargarh Construction of Soling / Drainage Tuff Tile Culverts sullage Carrier Pull Pullet PPC Allied Work etc Qureshi Aabwala Rahim Ali Mulan Walidad On-going 1642 3245 Muzaffargarh 60.000 20.000 3.333 2.500 1.667 67% 36% Date of AA 31.7.2017 Mazhay wala Tibbi Godar Chowk Sanwai Syed Schemes Hassan Shah Bakhsh Wala Jada Chandai District Muzaffargarh Const: of Soling/ Sewerage Drain UC Jhanday On-going 1643 3246 Wali UC Manikpur UC Darien UC Shahjamal UC Muzaffargarh 30.000 10.000 3.333 2.500 1.650 66% 39% Date of AA 31.7.2017 Schemes Alludeywali District Muzaffargarh Construction of PCC/Drainage and Tuff Tile in On-going 1644 3247 Muzaffargarh 65.000 25.000 6.667 5.000 3.334 67% 44% Date of A.A 06.9.2017 NA179 and PP-258 District Muzaffargarh Schemes Construction of Tuff Tile Drainge Sewerage Soling On-going 1645 3248 PCC Slab and different work PP-262 District Layyah 100.000 35.000 6.667 5.000 3.334 67% 38% • Date of AA = 15.08.2017 Schemes Layyah Construction of Tuff Tile Drainage Sewerage On-going 1646 3249 Soling PCC Slab and different work PP-263 District Layyah 120.000 30.000 10.000 7.500 5.000 67% 29% • Date of AA = 15.08.2017 Schemes Layyah Construction of Tuff Tile Drainage Sewerage On-going 1647 3250 Soling PCC Slab and different work PP-264 District Layyah 100.000 30.000 16.667 12.500 8.334 67% 38% • Date of AA = 15.08.2017 Schemes Layyah Comprehensive sewerage / Drainage scheme On-going 1648 3251 Layyah 100.000 30.000 23.333 17.500 11.667 67% 42% • Date of AA = 15.08.2017 along with tuff Tile in Choubara city District Layyah. Schemes On-going 1649 3252 Swerage Drainge / Tuff Tiles for Layyah city Layyah 300.000 75.000 50.000 37.500 25.000 67% 33% • Date of AA = 06.09.2017 Schemes Construction of Sewerage/Drains and Laying of On-going 1650 3253 Tuff Tiles/Soling in UC, Sirishta Thal District Layyah 143.137 10.000 21.297 15.973 10.643 67% 14% Administrative Approval issued on dated. 08-01- Schemes 2018. Layyah Rural Sewerage/ Drainage / Brick Pavement / Tuff On-going 1651 3254 Tiles in Union Council 164-A / TDA and Adjoining Layyah 20.000 10.000 3.333 2.500 1.660 66% 58% • Date of AA = 29.07.2017 Schemes Abadies Tehsil District Layyah Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of tender; 12-10-2017. Date of award:-26-10- Const. of Road, Sewerage & tuff Tile Chak On-going 1652 3255 Bahawalpur 11.889 5.990 1.963 1.472 0.980 67% 59% 2017. Date of completion. 25-10-2018. Anticipated No.5/BC District Bahawalpur Schemes date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 12-10-2017. Date of Rehabilitation of water supply schemes in Chak On-going 1653 3256 Bahawalpur 20.488 9.994 3.496 2.622 1.740 66% 57% award:-31-10-2017. Date of completion. 30.07.2018. no.5/DNB Tehsil Yazman District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 23-10-2017. Date of Rehabilitation of water supply schemes in Chak On-going 1654 3257 Bahawalpur 20.802 14.939 1.934 1.451 0.967 67% 76% award:-31-10-2017. Date of completion. 30.07.2018. no.14/DNB Tehsil Yazman District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 23-10-2017. Date of Rehabilitation of water supply schemes in Chak On-going 1655 3258 Bahawalpur 17.490 8.396 2.497 1.873 1.245 66% 55% award:-31-10-2017. Date of completion. 30.07.2018. no.76/DNB Tehsil Yazman District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 23-10-2017. Date of Rehabilitation of water supply schemes in Chak On-going 1656 3259 Bahawalpur 21.552 9.997 3.851 2.888 1.925 67% 55% award:-31-10-2017. Date of completion. 30.07.2018. no.24/DNB Tehsil Yazman District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Rehabilitation of water supply schemes in Chak On-going Date of receipt of tender: 23-10-2017. Date of 1657 3260 Bahawalpur 46.980 25.000 3.333 2.500 1.660 66% 57% award:-31-10-2017. Date of completion. 30.01.2019. No.44/DB Tehsil Yazman, District Bahawalpur. Schemes Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 23-10-2017. Date of Rehabilitation of water supply schemes in Chak On-going 1658 3261 Bahawalpur 22.680 14.996 2.560 1.920 1.280 67% 72% award:-31-10-2017. Date of completion. 30.07.2018. No.143/DB Tehsil Yazman, District Bahawalpur. Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of tender; 23-10-2017. Date of award:-31-10- Water Supply Scheme in Chak No.115/DB Kachi On-going 1659 3262 Bahawalpur 20.000 9.928 3.333 2.500 1.660 66% 58% 2017. Date of completion. 30-07-2018. Anticipated Tehsil Yazman District Bahawalpur. Schemes date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 23-10-2017. Date of On-going 1660 3263 Water Supply scheme of Chak No.114/DNB Bahawalpur 18.000 8.698 2.667 2.000 1.334 67% 56% award:-31-10-2017. Date of completion. 30.07.2018. Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA = 27-07-2017. Date of T.S 29.09.2017. . Date of receipt of tender: 12-10-2017. Date of Const. of Road, Sewerage & Tuff Tile Basti On-going 1661 3264 Bahawalpur 15.000 5.954 3.000 2.250 1.500 67% 50% award: 31.10.2017. Date of completion: 30.07.2018. Hansarah District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. P/L of Sewerage and Tuff Tile Basti Inayati Tehsil On-going Date of receipt of tender: 16-10-2017. Date of 1662 3265 Bahawalpur 29.000 14.991 4.667 3.500 2.330 67% 60% award:-31-10-2017. Date of completion. 30.01.2019. Khairpur Tamewali District Bahawalpur Schemes Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 12-10-2017. Date of P/L of Sewerage and Tuff Tile Basti Bohran Tehsil On-going 1663 3266 Bahawalpur 15.300 4.974 3.433 2.575 1.710 66% 44% award:-31-10-2017. Date of completion. 30.07.2018. Khairpur Tamewali District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 08.08.2017 . Date of T.S=08-08-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in On-going Date of receipt of tender: 16-10-2017. Date of 1664 3267 Bahawalpur 22.000 9.999 4.000 3.000 2.000 67% 55% award:-31-10-2017. Date of completion. 30.01.2019. 189/Murad adjoining Abadies District Bahawalpur Schemes Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 08.08.2017 . Date of T.S=08-08-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in On-going Date of receipt of tender: 16-10-2017. Date of 1665 3268 147/Murad and adjoining Abadies District Bahawalpur 35.000 9.990 3.333 2.500 1.660 66% 33% award:-31-10-2017. Date of completion. 30.01.2019. Schemes Bahawalpur Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 08.08.2017 . Date of T.S=08-08-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in On-going Date of receipt of tender: 16-10-2017. Date of 1666 3269 179/Murad and adjoining Abadies District Bahawalpur 35.100 14.341 3.333 2.500 1.660 66% 46% award:-31-10-2017. Date of completion. 30.01.2019. Schemes Bahawalpur Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 08.08.2017 . Date of T.S=08-08-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in On-going Date of receipt of tender: 16-10-2017. Date of 1667 3270 Bahawalpur 35.100 14.999 3.333 2.500 1.660 66% 47% award:-31-10-2017. Date of completion. 30.01.2019. 160/Murad Adjoining Abadies, District Bahawalpur Schemes Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 16-10-2017. Date of Const. of Sewarage & Tuff Tile Basti Kori Wala, On-going 1668 3271 Bahawalpur 20.000 9.989 3.333 2.500 1.660 66% 58% award:-31-10-2017. Date of completion. 30.07.2018. Hoot Wala District Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S= 31.07- Rehabilitation of Sewerage Scheme/Drainage and 2017. Date of tender; 12-10-2017. Date of award:- On-going 1669 3272 Tuff Tiles City Noor Pur Noranga District Bahawalpur 12.086 8.999 1.029 0.772 0.514 67% 79% 26-10-2017. Date of completion. 25-09-2018. Schemes Anticipation date of completion.30-06-2019. Date of Bahawalpur receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. P/L Sewerage /Tuff Tile City Hathaiji Mouza On-going Date of receipt of tender: 16-10-2017. Date of 1670 3273 Bahawalpur 50.000 19.998 10.000 7.500 5.000 67% 50% award:-31-10-2017. Date of completion. 30.01.2019. Hathaiji Tehsil Ahmadpur East District Bahawalpur Schemes Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=09-08-2017. P/L Sewerage /Tuff Tile Mubrakpur City Tehsil On-going Date of receipt of tender: 16-10-2017. Date of 1671 3274 Bahawalpur 40.000 6.903 3.333 2.500 1.659 66% 21% award:-31-10-2017. Date of completion. 30.01.2019. Ahmadpur East District Bahawalpur Schemes . Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A (DDSC). 28-09-2017. Date of T.S. 17- 10-2017. Prequalification completed on 06-11-2017. Rehabilitation of Sewerage, City Yazman District On-going Date of receipt of tender from Prequalified 1672 3275 Bahawalpur 300.000 59.999 33.333 25.000 16.500 66% 25% contractors on 05-12-2017 .Date of award. 01-01- Bahawalpur Schemes 2018. Date of completion. 31-12-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 16-10-2017. Date of Sewerage Scheme Chak No.86/DB District On-going 1673 3276 Bahawalpur 19.359 8.000 3.786 2.840 1.890 67% 51% award:-31-10-2017. Date of completion. 30.07.2018. Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 16-10-2017. Date of Sewerage Scheme Chak No.53/DB District On-going 1674 3277 Bahawalpur 20.588 8.999 3.863 2.897 1.927 67% 53% award:-31-10-2017. Date of completion. 30.07.2018. Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=08-08-2017. Date of receipt of tender: 12-10-2017. Date of Sewerage Scheme Chak No.68/DB District On-going 1675 3278 Bahawalpur 16.397 4.998 3.799 2.849 1.900 67% 42% award:-31-10-2017. Date of completion. 30.07.2018. Bahawalpur Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of AA= 27-07-2017. . Date of T.S=09-08-2017. Provision of Tuff Tile & Sanitation Scheme in Hatiji On-going Date of receipt of tender: 16-10-2017. Date of 1676 3279 Bahawalpur 40.000 14.995 3.333 2.500 1.667 67% 42% award:-31-10-2017. Date of completion. 30.01.2019. Tehsil Ahmadpur East Ditrict Bahawalpur Schemes Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Provision of Water supply Chak No. 202-206/M, 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1677 3280 128-132/M, 133-134/M, 176/M, 60/4/R District Bahawalnagar 50.000 14.992 6.667 5.000 5.000 100% 40% work award. 22-09-2017. Date of completion. 31-12- Schemes 2018. Anticipation date of completion 30-06-2019. Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Provision and laying of water supply schemes 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1678 3281 Chak No.53/F alongwith allied basties District Bahawalnagar 25.000 10.000 5.000 3.750 3.750 100% 55% work award. 22-09-2017. Date of completion. 31-12- Schemes 2018. Anticipation date of compltion.30-06-2019. Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- 2017. Date of receipt of tender. 11-09-2017. Date of Rehabilitation of water supply schemes Chak On-going 1679 3282 Bahawalnagar 15.000 9.984 1.667 1.250 1.250 100% 75% work award. 22-09-2017. Date of completion. 30-09- No.45/F Jattan wali District Bahawalnagar Schemes 2018. Anticipation date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Rehabilitation of Rural Water Supply Scheme 2017. Date of receipt of tender. 11-09-2017. Date of Chak No. 82/5-R &138-139/6-R Including All On-going 1680 3283 Bahawalnagar 40.000 14.997 8.333 6.250 5.150 82% 50% work award. 22-09-2017. Date of completion. 31-12- Adjoining Abadies Tehsil Haroonabad District Schemes 2018. Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & Bahawalnagar 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Rehabilitation of Rural Water Supply Scheme 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1681 3284 Chak No. 53/4-R & 137/6-R Including All Adjoining Bahawalnagar 44.000 15.652 9.447 7.085 5.750 81% 49% work award. 22-09-2017. Date of completion. 31-12- Schemes 2018. Anticipated date of completion 30-06- Abadies Tehsil Haroonabad District Bahawalnagar 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Rural Water Supply Scheme/ Sewerage/ Drainage Date of A.A 09-08-2017. . Date of T.S. 12.10.2017. . scheme Sri Ram Pura, Khair Shah, Bhaluka, Puna, prequalification of the contractors. 31.10.2017. Date Habibka, Allah Buksh Lalika, Bunga Machi Murad On-going of receipt of Tender from prequalified contractors on 1682 3285 Bahawalnagar 80.000 34.980 8.333 6.250 6.250 100% 52% 16-11-2017 .Date of award. 30-12-2017.Date of Wala, Musa Bhota Jhulan Arrain, Sanateka, Schemes completion. 29-12-2018.Anticipated date of Jurana Basti, Kup Quraishian, Chak Jodheka, completion 30-06-2019. Date of receipt of funds by Bhaluka, Chakmadrass, Distr F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Construction of Soling / Water Supply in Union Date of A.A 09-08-2017. Date of T.S. 12.10.2017. Councils Islam Pura, Fateh Kot, Malik Pura, Sawae prequalification of the contractors completed on On-going 1683 3286 Wala, Muhammad Pur, Koryanwala, Denan, Bahawalnagar 100.000 29.963 10.000 7.500 7.496 100% 37% 31.10.2017. Date of receipt of tender. 16-11-2017 . Schemes Date of work awarded. 11-12-2017. Date of Sondha, Gulaab Ali, Barah Sajwad Khan, Teko completion. 10-12-2018. Date of receipt of funds by Raam, Donga Bonga District Bahawalnagar F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. . Date of receipt of tender 11-09-2017. Date of work Rural Water supply scheme of Khiraaj Pura and On-going 1684 3287 Bahawalnagar 15.000 6.996 2.667 2.000 2.000 100% 60% awarded 31.10.2017. Date of completion Goband Pur District Bahawalnagar Schemes 30.10.2018. Anticipated date of completion 30-06- 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. . Date of receipt of tender received 27.11.2017. Date Rural Water supply scheme of Maakhe wali, On-going 1685 3288 Bahawalnagar 15.000 6.960 2.667 2.000 2.000 100% 60% of work awarded. 30-11-2017. Date of completion Mohan Pura, Jeeto, Jhugyan District Bahawalnagar Schemes 29-12-2018 . Anticipated date of completion 30-06- 2019Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. . Date of receipt of tender 11-09-2017. Date of work Rural water supply scheme of Taalya and Dhaban On-going 1686 3289 Bahawalnagar 15.000 6.886 2.667 2.000 2.000 100% 59% awarded 31.10.2017. Date of completion District Bahawalnagar Schemes 30.10.2018. Anticipated date of completion 30-06- 2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Rehabilitation of Rural Water Supply Scheme 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1687 3290 Chak No. 143/6-R including all Adjoining Abadies Bahawalnagar 28.807 9.944 6.269 4.702 3.800 81% 48% work award. 22-09-2017. Date of completion. 31-12- Schemes 2018. Anticipated date of completion 30-06-2019. Tehsil Haroonabad District Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 03-08-2017. Date of T.S. 08.08.2017. . Date of receipt of tender 11-11-2017. Date of work Rural Water Supply Scheme Chak No. 196/HB On-going 1688 3291 Bahawalnagar 25.000 9.999 5.000 3.750 3.090 82% 52% award. 16-11-2017. Anticipated date of completion Tehsil Fortabbas District Bahawalnagar Schemes 30-06-2019. Date of completion 15-11-2018. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Rehabilitation of Rural Water Supply Scheme 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1689 3292 Chak No. 70/4-R & 84/5-R Including All Adjoining Bahawalnagar 50.000 19.949 10.000 7.500 6.300 84% 52% work award. 22-09-2017. Date of completion. 31-12- Schemes 2018. Anticipated date of completion 30-06-2019. Abadies Tehsil Haroonabad District Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Rural Water Supply Scheme Chak No. 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1690 3293 237,238,239/9R & 239/HB Including All Adjoining Bahawalnagar 40.000 14.999 8.333 6.250 5.550 89% 51% work award. 02-10-2017. Date of completion. 31-12- Schemes 2018. Anticipated date of completion 30-06-2019. Abadies Tehsil Fortabbas. District Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. Construction of Sewer Lines and Tuff Tiles in City Date of tender receipt 11-09-2017. Date of award On-going 1691 3294 Area Haroonabad Tehsil Haroonabad District Bahawalnagar 18.000 9.990 2.667 1.400 1.400 100% 63% 31.10.2017. Date of completion 31.10.2018. Date of Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Bahawalnagar Work is in progress. Excess funds Rs.0.600 million surrendered dated 19.10.2018. Date of A.A. 09-08-2017. Date of T.S. 04.10.2017. . Construction of Tuff Paverment urban area City On-going Tender received on 10-01-2018. Date of award: 1692 3295 Bahawalnagar 100.000 29.999 16.667 12.500 10.000 80% 40% 23.01.2018. Date of completion 30.06.2019. Date of Chistian Ward No.1 to 36 District Bahawalnagar Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Provision of Soling, Drainage system, Erection of 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1693 3296 Tuff Tiles in Mandi Sadiq Gunj city. District Bahawalnagar 44.000 16.998 3.333 2.500 2.500 100% 44% work award. 02-10-2017. Date of completion. 31-12- Schemes 2018. Anticipated date of completion 30-06-2019. Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- Provision of Soling, Drainage System, Erection of 2017. Date of receipt of tender. 11-09-2017. Date of On-going 1694 3297 Tuff Tiles in Macloed Gunj city. District Bahawalnagar 50.000 19.985 3.333 2.500 2.498 100% 45% work award. 28-10-2017. Date of completion. 31-12- Schemes 2018. Anticipated date of completion 30-06-2019. Bahawalnagart Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- 2017. Date of receipt of tender. 11-09-2017. Date of Provision of Soling, Drainage System Erection of On-going 1695 3298 Bahawalnagar 21.000 9.996 3.667 2.750 2.530 92% 60% work award. 28-10-2017. Date of completion. 31-12- Tuff Tiles in Madhaniwal District Bahawalnagar Schemes 2018. Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. . Date of Tender receipt 11-09-2017. Date of award Provision of Soling, Drainage System, Erection of On-going 1696 3299 Bahawalnagar 45.000 21.853 3.333 8.424 8.422 100% 67% 31.10.2017. Date of completion 30.01.2019. Date of Tuff Tiles in Hasil Sarrhu. District Bahawalnagar Schemes receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Rs.5.924 million provided through re-appropriation dated 19.10.2018.

Date of A.A 03-08-2017. . Date of T.S 05.08.2017. . Date of tender receipt 11-09-2017. Date of award Provision of Soling, Tuff Tile, Drainage in Mouza On-going 1697 3300 Bahawalnagar 12.000 9.998 0.667 0.500 0.500 100% 87% 31.10.2017. Date of completion 30.10.2017. Muharram Cheena. District Bahawalnagar Schemes Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Scheme completed in saving.

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08- 2017. Date of receipt of tender. 11-09-2017. Date of Provision of Soling, Tuff Tile, Drainage in Mouza On-going 1698 3301 Bahawalnagar 21.000 9.999 3.667 2.750 2.600 95% 60% work award. 02-10-2017. Date of completion. 31-12- Hassanwala. District Bahawalnagar Schemes 2018. Anticipated date of completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Sewerage / drainage scheme Sri Ram Pura, Khair Date of A.A 09-08-2017. . Date of T.S. 12.10.2017. . Shah, Bhaluka, Puna, Habibka, Allah buksh Lalika, prequalification of the contractors. 31.10.2017. . Bunga Machi Murad wala, Musa Bhota Jhulan On-going Date of receipt of Tender from prequalified 1699 3302 Bahawalnagar 150.000 43.484 6.667 5.000 5.000 100% 32% contractors on 16-11-2017 . Date of award. 30-12- Arrain, Sanateka, Jattu wal Deen Pure, Chak Schemes 2017. Date of completion 29-03-2019. Date of Hotyana and Jurana Hafizabad District receipt of funds by F.D. 20.07.2018 & 11.01.2019. Bahawalnagar Work is in progress. Date of A.A 09-08-2017. Date of T.S 06-11-2017. Providing and laying sewerage schemes Chak On-going Date of receipt of tender: 10-01-2018. Date of 1700 3303 No.98/F, Bakhshan Khan, Chak 54/F, 105/F, Bahawalnagar 100.000 29.859 10.000 7.500 7.500 100% 37% award: 23.01.2018. Date of completion 30.06.2019. Schemes 10/FW, 174/M District Bahawalnagar Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. The scheme Provision of Soiling, Tuff Tile, Drainage in Mouza Muharram Cheena District Bahawalnagar reflected in ADP-2017-18 was substituted by Standing Committee of the Cabinet on Finance & Development in its meeting held on 20-09-2017 as proposed by Mian Fida Hussain Provision of Soling, Drainage System Eraction of Watto EX-MPA PP-277 and minutes of meeting Tutt Tiles in BhainiSikandarJassoka and On-going 1701 3304 Bahawalnagar 3.000 2.500 0.167 0.209 0.125 60% 88% issued vide S&GAD No.SO(CAB-II)1-2/2017(Fin- MouzaShamonJassoka Tehsil Minchanabad Schemes 170) dated 06-10-2017. Scheme approved on 02-11- 2017 by DDC. . Work awarded on 29-12-2017 but District Bahawalnagar work not started due to non availability of funds during 2017-2018. Now funds have been released by FD on 12-11-2018 & 11.01.2019. Date of completion dated 28-03-2018. Anticipated dated of competition 30-06-2019 Amended A.A is issued from DC, office on 11-12-2018. Work in progress.

Scheme approved on 02-11-2017 by DDC. Tender Provision of Soling Drainage System Erection of received on 27-11-2017 .Date of receipt of funds by Tuff Tile in Moti Pur, Qadir Pur, Munshi Other, FD.05-03-2018. Date of award. 29-12-2017. Date of On-going completion 26-06-2018. Anticipated date of 1702 3305 Basti Shah Bharamka, Manzoor Kot, Chak Saroo, Bahawalnagar 15.000 9.999 1.667 0.900 0.899 100% 73% Schemes completion. 25.10.2018. Date of receipt of funds by Chak Saroo, Chak Tehsil Minchanabad District F.D. 20.07.2018 & 11.01.2019. Scheme completed Bahawalnagar in saving. Excess funds Rs.0.350 million surrendered dated 19.10.2018.

Date of A.A(DDC) 03-08-2017. . Date of T.S. 08-08- 2017. . Date of receipt of tender.12-09-2017. Date of work award. 22-09-2017. Date of completion. 21- Construction of Sewer Lines and Tuff Tiles in Faqir On-going 12-2018. Anticipated date of completion 30-06- 1703 3306 Bahawalnagar 40.000 14.367 3.333 5.000 4.142 83% 46% 2019. Date of receipt of funds by F.D. 20.07.2018 & Wali Tehsil Haroonabad District Bahawalnagar Schemes 11.01.2019. Funds Rs.2.500 million Provided through re-appropriation vide Chief Engineer(S),PHED Lahore No.72-78/B(4) dated 10.01.2019.Work is in progress.

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017. .Date of receipt of Tender: 07.09.2017..Date of Constuction PCC Draiinge / Soling in NA-193 Rahim Yar On-going 1704 3307 40.013 12.987 3.333 2.500 1.951 78% 37% award: 31.10.2017..Date of completion: District Rahim Yar Khan Khan Schemes 28.02.2018..Anticipated date of completion 30-06- 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress..

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017. .Date of receipt of Tender: 07.09.2017..Date of Construction of laying Sewerage, Water Supply & Rahim Yar On-going 1705 3308 30.000 26.419 1.192 0.894 0.699 78% 90% award: 31.10.2017..Date of completion: Tuff Tiles City Sadiqabad District Rahim Yar Khan Khan Schemes 31.06.2018..Anticipated date of completion 30-06- 2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A. 09-08-2017. .Date of T.S 26-10- 2017.Date of receipt of Tenders from prequalified Mega Sewerage Scheme Roads & Tuff Tile Rahim Yar On-going 1706 3309 100.000 14.996 16.667 12.500 9.989 80% 25% contractors 27-12-2017..Date of award 21-02- Kotsamaba Khan Schemes 2018..Date of completion 20-10-2019. .Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017. Providing / Lying of Tuff Tiles Both Sides of Road .Date of receipt of Tender: 07.09.2017..Date of Rahim Yar On-going 1707 3310 from Attock Petrolium to Chowk Din Pur Sharif 31.500 9.999 3.333 2.500 2.156 86% 39% award: 31.10.2017..Date of completion: Khan Schemes 31.01.2018..Anticipated date of completion 30-06- Length: 1.50 KM District Rahim Yar Khan 2019.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Rural Drainage Scheme / PCC Slab For Mouza On-going 26.08.2017 3.Date of Award of work 31.10.2017 1708 3311 Chiniot 29.995 7.498 3.333 2.500 1.550 62% 30% 4.Dated of Released Funds 30.10.2017 Funds Rao Bagh Tehsil and Distt. Chiniot Schemes Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Construction of PCC / Soling / Drainage / Street and Tuff Tiles in Mohallah Adda Road Haidry 1. Date of AA = 02.08.2017 2. Date of TS = Chowk Lalian, Baldia Road Al Qaim Medical Store On-going 28.08.2017 3.Date of Award of work 31.10.2017 1709 3312 Chiniot 14.993 10.000 1.664 1.248 0.832 67% 72% 4.Dated of Released Funds 30.10.2017 Funds Afzal Bhatti Mehar Sikandar Lali Chowk, Gala Schemes Released upto 24.01.2019 by the Chief Engineer Mandi Paka Bazar Abadi Bil Muqabil Baldiya office (South) PHED Lahore and work is in progress. Aqab Abadi Police Construction of PCC / Soling / Drainage / Street and Tuff Tiles in Mohallah Afzal Bhatti Doctor 1. Date of AA = 02.08.2017 2. Date of TS = Bashir Road Heli Chowk Laliyan, beli Chowk On-going 28.08.2017 3.Date of Award of work 31.10.2017 1710 3313 Chiniot 23.000 8.496 4.333 3.250 2.150 66% 46% 4.Dated of Released Funds 30.10.2017 Funds Laliyan, Beli Chowk to soling/ Sheikh Muhammad Schemes Released on 03.08.2018 by the Chief Engineer Hussain Airan Store Jhang Road via Hujra Mor, (South) PHED Lahore and work is in progress. Beli/ Hujra Road to Construction of PCC / Soling / Drainage / Street and Tuff Tiles in Mohallah Ahmadabad Chowk 1. Date of AA = 02.08.2017 2. Date of TS = Bazar Kocha Bandi Ward no. 10, Chongi no. 5 to On-going 28.08.2017 3.Date of Award of work 31.10.2017 1711 3314 Chiniot 17.907 10.000 2.636 1.977 1.257 64% 63% 4.Dated of Released Funds 30.10.2017 Funds Jamia Mosque Chowk Bangla Road,Bangla Road Schemes Released upto 24.01.2019 by the Chief Engineer to Chowk Bazar, Kot Muhammad Yar- Nawab (South) PHED Lahore and work is in progress. Chowk Aqeeb Baldiya Office Mo

Construction of PCC / Soling / Drainage / Street and Tuff Tiles in Mohallah Jamiya Mosque Bangla 1. Date of AA = 02.08.2017 2. Date of TS = Road Nawab Chowk Imtiaz Lali Chowk, Old Eid On-going 28.08.2017 3.Date of Award of work 31.10.2017 1712 3315 Chiniot 26.900 4.938 3.333 2.500 1.667 67% 25% Funds Released upto 24.01.2019 by the Chief gah Changran - Wark No 3, Ghulam Schemes Engineer (South) PHED Lahore and work is in Mustafabad Ward no 4, Dera Mehar Imtiaz Lali to progress. Haidery Chowk Police

Construction of PCC / Soling / Drainage / Street 1. Date of AA = 02.08.2017 2. Date of TS = and Tuff Tiles in Mohallah Allah Chowk to On-going 28.08.2017 3.Date of Award of work 31.10.2017 1713 3316 Chiniot 25.500 4.420 3.333 2.500 1.667 67% 24% Funds Released upto 24.01.2019 by the Chief Sargodha Road, Station Noorpur Ward no. 2, Schemes Engineer (South) PHED Lahore and work is in Ward no. 5 Laliyan, Tariqabad Ward no. 6 Lalian progress.

Construction of PCC / Soling / Drainage / Street and Tuff Tiles in Mohallah Jamia Mosque ward no 1. Date of AA = 02.08.2017 2. Date of TS = 7 Laliyan, Imtia Town New Eidgah Umerabad ward On-going 28.08.2017 3.Date of Award of work 31.10.2017 1714 3317 Chiniot 21.499 4.850 3.333 2.500 1.650 66% 30% Funds Released upto 24.01.2019 by the Chief no. 11 Phase I, Imtiaz Town New Eidgah Schemes Engineer (South) PHED Lahore and work is in Umerabad ward no 11 Phase II, including Bangla progress. Road to Pir Qatbi Shah

Construction of PCC / Soling / Drainage / Street 1. Date of AA = 02.08.2017 2. Date of TS = and Tuff Tiles in Mohallah Dars Colony Bashir 28.08.2017 3.Date of Award of work 31.10.2017 Colony Jaly Dar Dakhli Laliyan, Miana Thatha On-going Funds Released upto 24.01.2019 by the Chief 1715 3318 Chiniot 15.500 4.663 3.500 2.625 1.023 39% 37% Engineer (South) PHED Lahore. Work stopped by Zahoor Colony Dakhli Laliyan, Mouza oilywala Schemes the contractor and Notice issued from this office as Hujra Hujra Colony Abadi near Petrol Pump Dakhli well as S.E PHE Circle Faisalabad Office to the Laliyan,Mouza Bhais contractor for restart the work.

Construction of PCC / Soling / Drainage / Street 1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work 31.10.2017 and Tuff Tiles in Mohallah Pulliyan Abadi Rana On-going Funds Released upto 24.01.2019 by the Chief 1716 3319 Colony Soling remaining Portion sargodha road to Chiniot 31.100 2.850 3.333 2.500 0.972 39% 12% Engineer (South) PHED Lahore. Work stopped by Schemes Rana Colony Dakhli Laliyan, Soling, Mouza Wala, the contractor and Notice issued from this office as well as S.E PHE Circle Faisalabad Office to the Mouza Thathi Bala Raja, Mouza Kalu wal. contractor for restart the work. Construction of PCC / Soling / Drainage / Street 1. Date of AA = 02.08.2017 2. Date of TS = and Tuff Tiles Pullian Mouza Ahmad Nagar, On-going 28.08.2017 3.Date of Award of work 31.10.2017 1717 3320 Carpet City Ladhiyan Phase-I, Carpet City Chiniot 32.000 9.816 3.333 2.500 1.562 62% 36% Funds Released upto 24.01.2019 by the Chief Schemes Ladhiyan Phase-II, and alongwith Road Mouza Engineer (South) PHED Lahore and work is in progress. Changarwala. 1. Date of AA = 02.08.2017 2. Date of TS = P/L Tuff Tile, Sewer Line PCC and Street Lights in On-going 28.08.2017 3.Date of Award of work 31.10.2017 1718 3321 Mohallah Rehmanabad, Karamabad, Moqeet Town Chiniot 40.827 8.900 3.333 2.500 1.667 67% 26% Funds Released upto 24.01.2019 by the Chief Schemes and Sagheer Colony in Tehsil and District Chiniot Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile On-going 28.08.2017 3.Date of Award of work 31.10.2017 1719 3322 /Brick Pavement including all allied works of UC Chiniot 49.988 10.000 3.333 2.500 1.667 67% 23% Funds Released upto 24.01.2019 by the Chief Schemes 11, District Chiniot Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile On-going 28.08.2017 3.Date of Award of work 31.10.2017 1720 3323 /Brick Pavement including all allied works of UC Chiniot 49.990 14.200 3.333 2.500 1.667 67% 32% Funds Released upto 24.01.2019 by the Chief Schemes 12, District Chiniot Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile On-going 28.08.2017 3.Date of Award of work 31.10.2017 1721 3324 /Brick Pavement including all allied works of UC Chiniot 49.982 15.000 3.333 2.500 2.500 100% 35% Funds Released upto 24.01.2019 by the Chief Schemes 13, District Chiniot Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile On-going 28.08.2017 3.Date of Award of work 31.10.2017 1722 3325 /Brick Pavement including all allied works of UC Chiniot 49.982 13.000 3.333 2.500 1.650 66% 29% Funds Released upto 24.01.2019 by the Chief Schemes 14, District Chiniot Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile On-going 28.08.2017 3.Date of Award of work 31.10.2017 1723 3326 /Brick Pavement including all allied works of UC Chiniot 49.986 20.000 5.000 3.750 2.500 67% 45% Funds Released upto 24.01.2019 by the Chief Schemes 15, District Chiniot Engineer (South) PHED Lahore and work is in progress. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile 28.08.2017 3.Date of Award of work 31.10.2017 On-going 1724 3327 /Brick Pavement including all allied works of UC Chiniot 49.990 10.000 5.000 3.750 1.789 48% 24% Funds Released upto 24.01.2019 by the Chief Schemes Engineer (South) PHED Lahore and work is in 21, District Chiniot progress. Target progress will be achieved in coming month. 1. Date of AA = 02.08.2017 2. Date of TS = Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile On-going 28.08.2017 3.Date of Award of work 31.10.2017 1725 3328 /Brick Pavement including all allied works of UC Chiniot 49.980 15.000 5.000 3.750 3.750 100% 38% Funds Released upto 24.01.2019 by the Chief Schemes 22, District Chiniot Engineer (South) PHED Lahore and work is in progress. 1725 Total Ongoing 127182.789 59312.981 8408.757 6297.326 4256.283 68% 50% New Schemes "1-Date of A.A 07.12.2018 2- Date of T.S 12.12.2018 3-Date of Prequalification 4-Date of invitation of tenders 08.01.2019 5- Date of Receipt Reheblitiation of Rural Water Supply Scheme 1 3329 Toba Tek Singh New 28.997 0.000 2.000 0.000 0.000 #DIV/0! 0% of tenders 09.01.2019 6- Date of work order 7- Date 394/JB Tehsil & Distt Toba Tek Singh of completion as per PC-I 8- Anticipated date of completion 9- No. of Beneficiary -4536-Person 10- Funds Released by F.D 11-Re-appropriation of funds (+/-) Rural water supply scheme Saho Chak, Badi Pur & 2 3330 Gurdanpur U/C Ghurri Tehsil & District Sialkot Sialkot New 27.900 0.000 1.000 1.000 0.000 0% 0% Tender under process (Court Direction) Rural Drainage Sewerage Scheme of UC Rasulpur 3 3331 Sialkot New 5.000 0.000 1.000 0.000 0.000 #DIV/0! 0% Tender under process Bhallian Construction of Sewerage System & Rehabilitation Rough Cost Estimate of the scheme is under Rahim Yar 4 3332 of Roads, Municipal Committee Zahir Pir Tehsil New 357.877 0.000 5.000 0.000 0.000 #DIV/0! 0% preparation by Consultant. Consultant has been Khan asked for early submission of rough Cost Khanpur, Distric R.Y.Khan estimate/PC-1 of the scheme. Construction of Waste Water Treatment Plant at 5 3333 Mianwali New 468.000 0.000 5.000 0.000 0.000 #DIV/0! 0% unapproved Mianwali. Sewerage Drianage Scheme in 05 No. colonies of 6 0.000 Estimate submitted for technical vetting to C.E (N). 3334 chak No. 79/NB including desilting of exisitng Sargodha New 69.638 5.000 0.000 0.000 #DIV/0! 0% Funds yet not released. sewer lines, Sargodha (Court Direction) Rehabilitaion / Improvement Sewerage system Date of A.A 18.10.2017 Date of T.S 31.10.2017 7 3335 Jhang New 700.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Work order issued on 13.08.2018. Work is in Jhang, Phase-I progress. Sewerage / Drianage scheme adjacent abadies of 8 3336 Lahore New 150.000 0.000 2.500 0.000 0.000 #DIV/0! 0% AA awaited. ada Mohlanwal Water, Sanitation and Hygiene (WASH) Programme under stunting reduction programme in 9 3337 Punjab New 3,086.564 0.000 8.743 0.000 0.000 #DIV/0! 0% Funds not Released by FD. 11 Districts of Multan, Bahawalpur and D.G.Khan Civil Divisions Feasibility Study for provision of surface water and 10 3338 Punjab New 200.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. treatment of waste water across Punjab 11 3339 Funding for Clearance of liablities Punjab New 40.000 0.000 40.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. Public Awareness Campaign and strengthening of 12 3340 communicty development & communication unit of Punjab New 100.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. PHED 13 3341 Clean Water for Healthy Life Punjab New 5,000.000 0.000 5000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. 14 3342 Rural sewerage & drainage schemes Punjab New 3,500.000 0.000 2000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. Water Quality testing Labortary at Township 15 3343 Punjab New 395.000 0.000 1.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. Lahore (PPP Mode) Establishment of Project Support Unit for Clean 16 3344 Punjab New 500.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. Water for Healthy Life Insaaf Program for Water Supply and Sanitation in 17 3345 Punjab New 5,000.000 0.000 5000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD. Rural Areas 17 Total New 19628.976 0.000 12091.243 1.000 0.000 0.000 0% 1742 Total Ongoing + New 146811.765 59312.981 20500.000 6298.326 4256.283 68% 43%