Agenda Item no. 9 Appendix A Chanctonbury CLC 2008
1 Table 1. Progress on S106 funded schemes previously approved by the CLC for addition to the IWP
1.1 Storrington Town Centre Enhancement 2008/09
Funding allocated from the following source: Ref Development Amount DC/06/1991 Land at 2 New Town Cottages £1,462 DC/05/0621 and Charity Farm Pulborough Road Cootham £2,500 0625 Freeland Farm Barn DC/05/0699 Bog Common Pulborough £1,260 Nr Storrington DC/06/0723 Land at 5 New Town Cottages £1,463 Dc/05/1614 Abbotts Leigh Washington Road £1,800 DC/05/1696 High Timbers Fryern Road Storrington £2,400 Land between 2 and 3 New Town DC/06/0724 £2,926 Cottages Storrington DC/06/0625 The Pines, New Town Road Storrington £3,250 TOTAL £17,061 Scheme was completed in August 2008
1.2 Coldwaltham - Footpath adjacent to Church Lane
Funding allocated from the following source:
Ref Development Amount DC/05/1315 Bog Common Pulborough £1,260 DC/06/0191 Ashurst Farm Coldwaltham £1,666 DC/06/0061 Hardham Hill Business Park £3,843 TOTAL £6,789 Scheme was completed in 2007/08
1.3 Cowfold A281/230 new footway 2011/12
Funding allocated from the following source:
Ref Development Amount DC/04/1296 Hooklands Barn Picts Lane Cowfold £1,800 Scheme is programmed for 2011/12
1.4 Pulborough Railway Station Access improvements Design
Funding allocated from the following source:
Ref Development Amount DC/04/0577 Old Coach house £633 DC/2737/04 Stane Street Nurseries £780
PL/136/03 113 Lower Street £1,200 Land at Stane Street Hollow, Stane DC/2487/05 £1,300 Street, Codmore Hill DC/04/0275 1 The Poplars The Street Nutbourne £1,260 TOTAL £5,173 Work Programmed for 2009/10
1.5 Bus Quality on Route 86 Funding allocated from the following source:
Ref Development Amount Land north of White House, The Old DC/04/0217 Sussex Stud, Cowfold Road, West £1,200 Grinstead Programmed for 2009/10
1.6 Shermanbury Footway Mock Bridge to B2116
Funding allocated from the following source: Ref Development Amount Wood Barn Ewhurst Manor Dc/04/1885 £1,800 Shermanbury Oatlands house, Brighton Road Dc/04/1814 £1,200 Shermanbury TOTAL £3,000 Programmed for 2008/09
1.7 Ashington Lay by at local Shops
Funding allocated from the following sources: Ref Development Amount DC/04/1052 Redlynch Mill Lane Ashington £1,800 DC/05/2400 Post Horses London Road £1,950 Dc/05/0009 2 The Bungalows Rectory Lane £2,760 AS/5/98 East of London Road £6,138 DC/1100/06 Applegarth/Oak Tree Cotage £23,887 DC/1653/04 Land West of the White Cottage £1,200 TOTAL £37,735
The scheme cost estimate was originally reported to be £27278, but the scheme cost has risen to £34,000, due partly to the addition of the costs associated with providing a traffic regulation order (circa £2000). The TRO will help ensure that the lay by is reserved for its intended use rather than long term parking.
Horsham District Council is still trying to secure a variation to the agreement to allow the contribution from AS/5/98 to be used towards this project.
The CLC should note that the Co-op Store has agreed to pay £5000 towards the scheme upon completion of the works.
The CLC will be advised of any unspent contributions which will be made available for allocation to new schemes at a later date.
1.8 Passenger information near Parsonage Farm
Funding allocated from the following source:
Ref Development Amount HF/22/01 Parsonage Farm, Henfield £22,273 Programmed for 2009/10
1.9 Pulborough Transport Service centred around Medical Centre
Funding allocated from the following source:
Ref Development Amount PL/67/03 Former Spiro Gills London Road £96,000 Service has commenced Services consist of: Bus Route 72/73 Amberley to Pulborough costing £7000 a year. Transport Co-ordinator for the voluntary transport services serving the Medical Centre costing £5000 so far.
1.10 Pulborough: Traffic calming at St Mary's School
Funding allocated from the following source:
Ref Development Amount PL/99/97 Laburnum Cottage Hill Farm Lane £1,200 PL/49/00 The Red Lion, 145 Lower Street, £1,634 DC/06/2097 3 and 4 London Road £4,288 PL/67/03 Former Spiro Gills London Road £20,000 TOTAL £27,122 Scheme completed in 2007/08
1.11 Shermanbury Realtime information and Low Floor Bus on Route 17 Funding allocated from the following source:
Ref Development Amount SH/14/99 Shermanbury Grange Shermanbury £70,049 The contribution was taken for Public Transport serving the site. (Route 17 is an hourly service Mon to Sat and 2 hourly on Sundays). The scheme was approved in principle. The CLC has asked that a business case be worked up and that the detail be submitted for approval at a later date. The scheme is being looked at as part of the wider Horsham Real- time Information project and we are still committed to producing a business case for approval by the Local Member and CLC Chairman. Works programmed for 2009/10
1.12 Small Dole: Gateway signs and Markings
Funding allocated from the following source:
Ref Development Amount Land adjoining the Post Office UB/6/04 £2,520 Henfield Road Small Dole 2007/08 slipped to 08/09. It is intended that this scheme will be designed in-house and will be installed in 2008/09
1.13 Storrington VAS and Gateway, Amberley Road Funding allocated from the following source:
Ref Development Amount SR/106/02 Sandown Amberley Road Storrington £10,000 Sr/19/02 New Town Road Storrington £11,144 TOTAL £21,144 Completed in 2008/09
1.14 Thakeham. Speed Management on B2113 at Crays Lane/Peacock Lane Junctions Funding allocated from the following source:
Ref Development Amount Building H Crays Court Crays Lane T/65/03 £6,500 Goose Green Thakeham Programmed for 2008/09. It is intended that this scheme will be designed in-house and will be installed in 2008/09
1.15 Steyning: Surfacing the Twitten from Coombe Drove to the Bostal,
Funding allocated from the following source:
Ref Development Amount Dc/05/0044 The Bungalow Castle Lane Bramber £1,200 DC/06/0816 The Castle Hotel Bramber £1,260 FORMER TOTAL £2,460 REDUCTION -£1,240 NEW TOTAL £1,220 Completed January 2008 by the Parish Council costing £1220
1.16 Partridge Green Safer Route to School; Jolesfield Primary School Funding allocated from the following source:
Ref Development Amount West Winds Church Road Partridge DC/06/0558 £1,463 Green Former Dairy Shermanbury Place SH/1/04 £1,260 Shermanbury Shermanbury Barn Ewhurst manor DC/04/0814 £3,060 Shermanbury Place
DC/364/05 CBF Garden Centre Littleworth Lane £1,269 FORMER TOTAL £7,052 ADDITIONS £1,560 NEW TOTAL £8,612 Programmed under general item for 2009/10 See Table 3 for source of additional funding
1.17 Bramber Road Crossing Funding allocated from the following source:
Ref Development Amount Railway Cottage, Kings Barn Lane, DC/06/1326 £976 Steyning DC/06/0932 York Cottage 136 High Street £1,203 DC/04/0574 Highfield Barn Bostal Road £1,260 DC/04/2358 Rear of 93 High Street £1,800 DC/06/1465 6 Kings Barn Lane £1,950 DC/05/2178 51 High Street £2,820 DC/04/1914 Marylands Penlands Close £5,040 DC/04/1914 Marylands Penlands Close £1,200 DC/04/0826 48 Goring Road Steyning £1,800 ST/4/04 Griggs Garage Tanyard Lane £1,350 The Bothy College Wood Farm DC/04/541 £1,200 Spithandle Lane Wiston DC/06/1815 82 High Street £3,000 FORMER TOTAL £23,599 ADDITION +£10,783 NEW TOTAL £34,382 Scheme programmed for 2009/10 subject to the receipt of sufficient funds. See Table 3 for details of new funds towards this project
1.18 Henfield. Safety Improvements on B2116 between A281 and Hurstpierpoint. (Development in Woodmancote Parish)
Funding allocated from the following source:
Ref Development Amount DC/06/1968 Firsland Park Estate, Henfield Road £5,000 Was originally programmed in 07/08, delivery has slipped to 08/09. Survey work has been completed. The Parish Council is being consulted on the scheme detail.
1.19 Provision of Street Light at The Pike; Washington Village entrance Funding allocated from the following source:
Ref Development Amount 16/17 Chanctonbury Close DC/05/1605 £1,260 Washington £240 Dc/04/1872 Washington Garage
FORMER TOTAL £1,500 ADDITION +£200 NEW TOTAL £1,700 Programmed for 2008/09
Increase value by £200 to allow for higher spec street light by reducing the value assigned to the traffic management scheme below
1.20 Traffic Management at The Pike/A283 Funding allocated from the following source:
Ref Development Amount Church Barn Church House The Street WS/50/03 £2,400 Washington Dc/04/1872 Washington Garage £2,772 FORMER TOTAL £5,172 REDUCTION -£200 NEW TOTAL £4,972 Programmed for 09/10 – Reduce value by £200 to allow for higher spec street light above
1.21 Cowfold, Crossing on A272
Funding allocated from the following source:
Ref Development Amount DC/04/2206 The Olde House The Street Cowfold £600 DC/04/2184 Ellerslie and Laurel Bank Cowfold £1,260 DC/05/1646 Chalvington Barns South Leas £6,240 Henfield Road Cowfold TOTAL £8,100 Refuge island added to works programme for delivery in 2009/10. Insufficient funds for other schemes
1.22 Travel Plan/ Safer Routes to School at St Peters Primary School Funding allocated from the following source:
Ref Development Amount DC/06/2058 Ivy House Henfield £488 DC/04/1394 The Studio Park Road Henfield £1,200* 1 & 2 Annetta Cottages Church DC/04/0345 £1,260* Street Henfield Dc/05/0680 Hollinger Albourne Road Henfield £1,800 Blackstone Grange Farm Henfield (in DC/06/0979 £2,000 Woodmancote Parish) DC/06/1686 Dears Farm, West End Lane, Henfield £2,275 Brookside Farm Dagbrook Lane DC/05/0332 £1,187 Henfield Brookside Farm Dagbrook Lane DC/05/0332 £1,813* Henfield Dc/05/0740 Lancesters, West End Lane, Henfield £3,150 PREVIOUS £15,173 TOTAL REDUCTION -£2,000 NEW TOTAL £13,273 SRTS Scheme is programmed for 2010/11. – There are insufficient funds available for other schemes
The Parish Council has provided footpath improvements using the contributions marked with a * totalling £4273.
It is recommended that the scheme budget be reduced by £2000, as the Blackstone Grange Farm development is a non-residential development outside of Henfield Village, and therefore the need for the proposed improvement cannot be linked to the traffic impact of the paying development, which is in a separate Parish to the proposed improvement. These funds are included in table 2 for reallocation.
The total funding remaining for the scheme is £9000
2 Table 2. Proposals to reallocate funds allocated by the CLC previously to schemes that can not now progress