National Electric Power Regulatory Authority Islamic Republic of Pakistan
NEPRA Tower, Ataturk Avenue (East) G-5/1, Islamabad Ph: +92-51-9206500, Fax: +92-51-2600021 Registrar Web: www.nepra.org.pk, E-mail: [email protected]
No. NEPRA/R/LAG-23/ ‘84 — e 5— January 17, 2014
General Manager (Hydel) Operations Water and Power Development Authority (WAPDA) 186 - WAPDA House, Shahrah-e-Quaid-e-Azam, Lahore
Subject: Modification-HI in Generation Licence No. GL(Hydel)/05/2004, dated 03.11.2004 — WAPDA for its Hydel Power Stations
It is intimated that the Authority has approved "Licensee Proposed Modification" in Generation Licence No. GL(Hydel)/05/2004 (issued on November 03, 2004) in respect of Water and Power Development Authority (WAPDA) for its Hydel Power Stations pursuant to Regulation 10(11) of the NEPRA Licensing (Application & Modification Procedure) Regulations, 1999.
2. Enclosed please find herewith determination of Authority in the matter of Licensee Proposed Modification of WAPDA of its Hydel Power Stations along with Modification-III in the Generation Licence No. GL/(Hydel)/05/2004, as approved by the Authority.
Enel:/As above
(Syed SafeerMITiggan)
Copy to Director General, Pakistan Environmental Protection Agency, House No. 311, Main Margalla Road, F-11/3, Islamabad. ,0,14 ER R 4C)7' LL1'811( REWSTRAR National Electric Power Regulatory Authority NEPRA
Determination of Authority in the Matter of Licensee Proposed Modification (LPM) of Water and Power Development Authority (WAPDA)
January 08, 2014 Application No. LAG-23
(A). Background
(i). The Authority has granted a Generation Licence (No. GL (HYDEL) /05/2004, dated November 3, 2004) to WAPDA for a cumulative Installed Capacity of 6879.56 MW.
(ii). This above mentioned Generation Licence has been granted for eighteen (18) Hydel Power Stations, distinctly located across the country.
(B). Communication of LPM
(i). In accordance with Regulation-10 of the NEPRA Licensing (Application & Modification Procedure) Regulations, 1999 (the "Regulations"), WAPDA communicated an LPM on May 31, 2013 for inclusion of four (04) new Hydel Power Stations/Plants including (a) Tarbela 4th Extension Hydro Power Project (b) Keyal Khwar Hydro Power Project (c) Golen Gol Hydro Power Project and (d) Jabban Hydro Power Project.
(ii). WAPDA in the submitted "Text of Modification" statement informed that it plans to get included four (04) upcoming Hydro Power Projects, having total Installed capacity of 1668.00 MW. In the "Reason in Support of Modification" statement WAPDA submitted that it is actively pursuing its development program for Hydel Power Projects and for this purpose this request has been submitted to NEPRA in respect of near to completion and financial close development projects.
Page 1 of 4 (iii). Regarding the "Impact on Tariff", WAPDA submitted that a detailed analysis regarding projected impact in the matter, justifying that the inclusion of the above power plants has already been submitted through a separate Tariff Petition. About the "Quality of Service (QoS)" and "Performance", WAPDA submitted that the inclusion of the above power plants would improve the overall performance of WAPDA as relatively low priced electricity would be made available to National Grid.
(C). Processing of LPM
(i). After completion of all the required information as stipulated under the Regulation 10 (2) and 10 (3) of the Regulations by WAPDA, the Registrar accepted the LPM as required under the Regulation 10 (4) of the Regulations.
(ii). The Registrar in terms of Regulation 10 (4) of Regulations published on July 06, 2013 a notice about the LPM in one English and one Urdu daily newspapers, informing general public, stakeholders and interested affected parties about the same and invited for comments in favor or against the LPM.
(iii). Furthermore, separate notices were also sent to Experts, Government Ministries and Representative Organizations etc. for submitting their views and comments in the matter.
(D). Comments of Stakeholders
(i). In reply to the above, the Authority received comments from two (02) stakeholders. These included Ministry of Petroleum and Natural Resources (MoP&NR) and Ministry of Water and Power (MoW&P). The salient points of the comments offered by these stakeholders are summarized in the following paragraphs: -
(a). MoP&NR in comments stated that as no gas was required for utilization of the projects of WAPDA therefore, the Ministry has no objection on modification of Generation License of WAPDA; (b). MoW&P remarked that the LPM may be processed under the relevant Act/Rules for addition of four (04) upcoming Hydel Plants of 1660.00 MW. Further, WAPDA may confirm the completion dates of these projects and NEPRA may ensure their on-time completion.
(ii). The Authority in its Regulatory Meeting (RM-13-624), held on November 26, 2013 considered the comments/observations of the stakeholders and decided to proceed further in the matter as stipulated in the Regulation and NEPRA Licensing (Generation) Rules 2000 (the Rules).
(E). Approval of LPM
(i). The importance of electricity in the development of the economy of any country is of imperative nature. The Economic Growth of any country is directly linked with the availability of safe, secure, reliable and cheaper supply of electricity. In view of the said reasons, the Authority is of the considered opinion that for sustainable development all indigenous power generation resources including Coal, Hydel, Wind, Solar and other Renewable Energy (RE) resources must be developed on priority basis.
(ii). The existing energy mix of the country is heavily skewed towards the costlier thermal power plants, mainly operating on imported furnace oil. The continuously increasing trend in fuel prices is not only creating pressure on the precious foreign exchange reserves of the country but is also an environmental concern. Therefore, in order to achieve sustainable development it is imperative that all indigenous resources are given priority for power generation and their development is encouraged.
(iii). In view of the above, the Authority contemplates that the initiative of WAPDA for exploiting the hydro potential of the country for power generation as very encouraging and vital. This will help in overcoming the severe shortage of electricity in the country and will trigger Industrial growth thereby helping in jk
Page 3 of 4
raising the GDP of the country which is on the decline due to shortage of electricity.
(iv). Therefore, the Authority hereby approves the LPM, in the Generation Licence of WAPDA for addition of four (04) Hydro Power Plants including (a) Tarbela 4th Extension Hydro Power Project (b) Keyal Khwar Hydro Power Project (c) Golen Gol Hydro Power Project and (d) Jabban Hydro Power Project thereby increasing the total Installed Capacity of WAPDA (Hydel) to 8547.56 MW from 6879.56 MW.
(v). Accordingly, the already granted Generation Licence (No. GL (Hydel)/05/2004, dated November 3, 2004 in the name of WAPDA (Hydel) is hereby modified. The Fact Sheet indicating the required changes alongwith Modified/Revised Schedule-I & II of the Generation Licence are attached as Annexure to this determination. The grant of such a Licensee Proposed Modification would be subject to the provisions contained in the NEPRA Act and relevant rules framed there under.
Authorit
Habibullah Khilji Member
Maj. (R) Haroon Rashid Member
Khawaja Muhammad Naeem MemberNice Chairman
National Electric Power Regulatory Authority (NEPRA) Islamabad — Pakistan
GENERATION LICENCE GL(HYDEL)/05/2004
In exercise of the Powers conferred upon the National Electric Power Regulatory Authority (NEPRA) under Section-26 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 the Authority hereby modifies the Generation Licence granted to WAPDA (on November 03, 2004, Modification-I dated June 27, 2008, Modification-II dated June 20, 2011 and expiring on November 02, 2034,), to the extent of changes mentioned as here under:-
(i). Installed capacity mentioned in the Face Sheet may be read as 8547.56 MW instead of 6879.56 MW; (ii). Changes in Schedule-I attached as Modified/Revised Schedule-I; and (iii). Changes in Schedule-II attached as Modified/Revised Schedule-II.
I7h 1- This Modification-Ill is given under my hand this I of January Two
Thousand & Fourteen
Registrar Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore
SCHEDULE-I (Modified/Revised)
The Location, Size (i.e. Capacity in MW), Type of Technology, Interconnection Arrangements, Technical Limits, Technical/Functional Specifications and other details specific to the Generation Facilities of the Licensee are described in this Schedule.
Page 1 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAP DA) Wapda House Lahore Hydel Power Station Tarbela
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
VPage 2 of 51 of Modified/Revised Schedule —I (Modification-Ill) • Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Tarbela Flvdel Power Station
PLANT DETAILS
On Right Bank, of River Indus at Tarbela in Distt. 1. Location Abbottabad, in the province of Khyber Pakhtunkhwa (KPK).
Type Total Capacity No. of Units 2. Plant Storage 3478 MW 14
Maximum Minimum 3. Head 440 ft 190 ft
4. Technology Francis Turbines Tunnel No. Length Diameter At At Total No. of Tunnel 5 - Intake Penstock
5. I‘ No. of Power Ti, T2 = 2400 ft. T3 45.0 3 " 43.5 ft. `I1' Tunnels = 2700 ft. ft.
In No. of Irrigation T4 = 2700 ft T5 = 45.0 2 36.0 ft. `11/ * Tunnels 3675 ft ft.
Minimum Expected 6. Useful Life of the 50 Years Generation Facility Generally during High Flow Period, the plant is Peaking/Base 7. operated for base load where as during Low Flow Operation Period, it is utilized for peaking purpose.
Units (1-10) = 13.8 KV Generator Voltage Units (11-14) = 18.0 KV
8. Plant Characteristics Units (1-4) = 0.85
Power Factor Units (5-10) = 0.95
Units (11-14) = 0.90
Page 3 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Frequency 50 Hz
Automatic Yes Generation Control
Voltage CCT Length (KM) (KV)
Tarbela-Gatti-I 500 329.69
Tarbela-Gatti-II 500 321.00 Tarbela-Sheikh 500 113.07 Muhammadi Interconnection Arrangements (CCT Tarbela-Rawat 500 110.89 details, length of 9. Transmission Line, Tarbela-Burhan-I 220 035.01 voltage level details etc.) Tarbela-Burhan-II 220 035.01
Tarbela-Burhan-Ill 220 035.04
Tarbela-Sangjani-IV 220 062.05
Tarbela-Mardan-I 220 067.00
Tarbela-Mardan-II 220 067.00
Page 4 of 51 of dified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hyde! Power Station Mangla
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
Page 5 of 51 of Modified vised Schedule —I REGiSTRAR Modification-II l)
PLANT DETAILS
On River Jhelum at Mangla near Mirpur, Azad Jammu 1. Location & Kashmir.
Type Total Capacity No. of Units 2. Plant Storage 1000 MW 10
Maximum Minimum 3. Head 363 ft 192 ft
4. Technology Francis Turbines
Tunnel No. Length Diameter Total No. of At 5 At Intake Tunnel Penstock No. of 5. (i). Power 5 1560 ft. each 30 ft. 26 ft. Tunnels No. of (ii). Irrigation - - - - Tunnels Minimum Expected Useful 6. Life of the 50 Years Generation Facility
Plant is operated for base load generally during High Peaking/Base 7. Flow Period, where as during Low Flow Period, it is Operation utilized for peaking.
Generator Voltage Units (1-10) = 13.2 KV
Power Factor Units (1-10) = 0.8
Plant 8. Frequency 50 Hz Characteristics Automatic Load Automatic Generation Frequency Control is trot installed on Units 3, 4, "0 ER Recb, 7&8 Page 6 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore I Voltage Length CCT (KV) (KM) Mangla-Ghakhar-I 220 111.09 Mangla-Ghakhar Express 220 113.07 -II Mangla-Ghakhar-III 220 113.07 Mangla — KSK-I 220 170.06 Mangla — KSK-II 220 170.06 Mangla — KSK-III 220 172.09 Mangla — New Rawat-I 220 79.09 Interconnection Arrangements Mangla — New Rawat-II 220 79.09 (CCT details, Mangla — Jhelum-New length of 132 123.91 9. Rawat-I Transmission Mangla — Gujar Khan-New 132 88.36 Line, voltage Rawat-I level details Mangla — Gujar Khan-New 132 88.36 etc.) Rawat-Il Mangla — Old Rawat-I 132 90.00 Mangla — Old Rawat-II 132 90.00 Mangla — Rajar-Kharian-I 132 61.00 Mangla-Kharian-II 132 61.00 Mangla-Kharian-III 132 61.00 Mangla-Scarp-I 132 189.06 Mangla-Scarp — II 132 109.03 Mangla-Mirpur 132 8.00
Page 7 of 51 of Modified/Revised Schedule —I (Modification-II l) REGSTRAR Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Warsak
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
Page 8 of 51 of Modified evised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Warsak Hydel Power Station
PLANT DETAILS
located on River Kabul at about 30 KMs from 1. Location Peshawar in Khyber Pakhtunkhwa (KPK)
Type Total Capacity No. of Units 2. Plant Storage 242.5 MW 6
Maximum Minimum 3. Head 150 ft 130 ft
4. Technology Francis Turbine
Tunnel No. Length Diameter At Total No. of Tunnel 1 - At Intake Penstock 5. No. of Power 1 365 ft. 39 ft. 39 ft. (I). Tunnels No. of (ii). Irrigation - - - - Tunnels Minimum Expected 6. Useful Life of the 25 Years after completion of rehabilitation. Generation Facility Peaking/Base Mostly the plant runs as base load, with delivery of 7. Operation peak load for minimum time period during evening. Generator Voltage Units (1-6) = 13.2 KV Units (1-4) = 1.0 Power Factor Plant Units (5-6) = 0.85 8. Characteristics Frequency 50 Hz Automatic Generation No Control Length CCT Voltage (KV) Interconnection (KM) Arrangements Warsak-Peshawar 132 24.1 (CCT details, Cantt.-I 9. length of Warsak-Jamrud-II 132 27.69 Transmission Line, voltage level details Warsak-Shahi Bagh-I 132 25.91 etc.) Warsak-SiattiBagh-I I 132 25.91
Page 9 of 51 of Modified/Revised Schedule —I Lid (Modification-Ill) REGiSTRAR Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Ghazi Barotha
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
,c01ER L'(//
Page 10 of 51 of REGiSTRAR (\A./Modified/Re ssed Schedule —I odification-I II) ...-, Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Ghazi Barotha Hydel Power Station
PLANT DETAILS
Near Village Barotha 63 KM downstream of Tarbela 1. Location about 10 KM West of Attock City, Punjab Total Type No. of Units Capacity Run off the canal 2. Plant with small 1450 MW 5 storage for peak Hours.
Maximum Minimum 3. Head 74 meter 69 meter 4. Technology Francis Turbine 5. Tunnel -
Minimum Expected 6. Useful Life of the 50 Years Generation Facility
Peaking/Base 7. Peak Load Operation Operation Generator Voltage Units (1-5) = 18 KV
Power Factor Units(1-5) = 0.95 Plant 8 Characteristics Frequency Frequency = 50 Hz Automatic Generation Yes Control
CCT Voltage (KV) Length (KM) Two circuit Interconnection Tarbela- 500 156 Arrangements (CCT Barotha- details, length of 9. Rawat Transmission Line, voltage level details Two circuit etc.) 500 KV 500 80 KM Tarbela- Barotha-Gatti
N —asa1P.— Page 11 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Chashma
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
Page 12 of 51 of Modified/Revised Schedule —I (Modification-Ill)
Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Chashma Hydel Power Station
PLANT DETAILS
On Right abutment of Chashma Barrage in Dist. 1. Location Mianwali, Province of Punjab. Type Total Capacity No. of Units 2. Plant Run of the 184 MW 8 River
Maximum Minimum 3. Head 13.8 meter 3 meter
4. Technology Bulb type Turbine
The Power House is fed through 1000 meter long and 5. Tunnel 136 meter wide Headrace water channel. Minimum Expected Useful 6. Life of the 60 Years. Generation Facility
Peaking/Base It is run off the river plant and loading generally 7. Operation depends upon the water releases available.
Generator Voltage Units (1-8) = 11 KV Power Factor Plant Units (1-8) = 0.90 8. Characteristics Frequency 50 Hz Automatic Generation No Control CCT Voltage (KV) Length (KM) Chashma- Interconnection Wanbuchran- 132 33.357 Arrangements (CCT-1) (CCT details, Chashma- length of Wanbuchran- 132 33.357 9 Transmission (CCT-2) Line, voltage Chashma Left 132 1.71 level details Bank- (CCT-1) etc.) Chashma Left Bank- (CCT- 132 1.71 2)
Page 13 of 51 of Modified/Revised Schedule —I (Modification-II l)
j
Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hyde! Power Station Renala
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (D. Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
Page 14 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Renala Hyde! Power Station
PLANT DETAILS
located on Lower Bari Doad Canal near Renala Town 1. Location Distt. Okara. Type Total Capacity No. of Units 2. Plant Run of Canal 1.1 MW 5 Maximum Minimum 3. Head 10 ft 7 ft 4. Technology Francis Turbine (Horizontal Shaft) Diameter Penstock No. Length Internal 5 ' Total No. of Nil Penstock Minimum Expected Useful 6. Life of the 15 Years Generation Facility Peaking/Base Meant for local load of Lift Irrigation Pumping Stations. Operation Length of CCT Voltage (KV) Length (KM) Transmission Line (Radial 11 KV feeder 8' feeder for Lift 11 60 Irrigation EHKL System) Generator Voltage Units (1-5) = 3.3 KV Power Factor Units (1-5) = 0.8 Plant 9' Characteristics Frequency 50 Hz Automatic Generation No Control Interconnection CCT Voltage (KV) Length (KM) Arrangements (CCT details, length of 10. 11 KV feeder Transmission 11 60 Line, voltage EHKL level details etc.)
Page 15 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAP DA) Wapda House Lahore Hydel Power Station Chichoki
(a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation
Page 16 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore
Chichoki Hvdel Power Station
PLANT DETAILS
On Upper Chenab Canal (UCC) near village 1. Location Joyanwala about 20 KMs from Sheikhupura.
Type Total Capacity No. of Units 2. Plant Run of Canal 13.2 MW 3
Maximum Minimum 3. Head 27.7 ft 22.3 ft
4. Technology Kaplan Turbine
Penstock No. Length Diameter Internal 5 ' Total No. of N.A Penstock Minimum Expected Useful 6. Life of the 30 Years. Generation Facility Peaking/Base Operated as base load according to the water share 7. Operation in the upper Chenab Canal.
Generator Voltage Units (1-3) = 3.3 KV
Power Factor Units (1-3) = 0.8 Plant 8. Characteristics Frequency 50 Hz
Automatic Generation No Control Interconnection CCT Voltage(KV) Length(KM) Arrangements (CCT details, 9. length of Chichokimallian- 66 18 Transmission Attabad-Shaikhpura Line, voltage level details etc.) ...e (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Pag- 18 of 51 of Modified/Revised S 'edule —I (Modifica •n-III) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Nandipur Hydel Power Station PLANT DETAILS On Upper Chenab Canal (UCC) about 10 KMs from 1. Location Gujranwala on Gujranwala Sialkot Road. Type Total Capacity No. of Units 2. Plant Run of Canal 13.8 MW 3 Maximum Minimum 3. Head 24.4 ft 19.5 ft 4. Technology Kaplan Turbine Diameter Penstock No. Length 5 Internal Total No. of N.A Penstock Minimum Expected Useful 6. Life of the 30 Years. Generation Facility Peaking/Base Operated as base load according to the water share Operation in the upper Chenab Canal. Generator Voltage Units (1-3) = 3.3 KV Power Factor Units (1-3) = 0.8 Plant 8. Characteristics Frequency 50 Hz Automatic Generation No. Control Interconnection CCT Voltage (KV) Length (KM) Arrangements (CCT details, Nandipur-Daska 66 20 9. length of Transmission Nandipur- 66 10 Line, voltage level Gujranwala details etc.) Page 19 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Shadiwal (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation d7o04\ R <57,, P. se 20 of 51 of Modified/Revised chedule —I (Modi tion-III) REGiSTRAR r- Off;' 11\Z"''‘I Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Shadiwal Hydel Power Station PLANT DETAILS On Upper Jhelum Canal (UJC) about 133 KMs Down 1 Location Stream of Mangla and about 7 KMs from Gujrat Type Total Capacity No. of Units 2. Plant Run of 13.5 MW 2 Canal Maximum Minimum 3. Head 24.5 ft 17 ft 4. Technology Kaplan Turbines Penstock No. Length Diameter Internal 5. Total No. of N.A Penstock Minimum Expected Useful 6. Life of the 30 Years. Generation Facility Peaking/Base Operated as base load according to the water share 7 Operation in the upper Jhelum Canal. Generator Voltage Units (1-2) = 11KV Power Factor Units (1-2) = 0.9 Plant 8. Characteristics Frequency 50 Hz Automatic Generation No. Control Interconnection Voltage CCT Length (KM) Arrangements (KV) (CCT details, 9. length of Transmission Shadiwal-Gujrat 132 9.6 Line, voltage level details etc.) ro\N ER Rk. G Page 21 of 51 of AS-=‘, Modified/Revised Schedule —I cy" (Modification-Ill) FREGSTRAR l> Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Rasul (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation ,--- ci7:0,NER R ( 41) Page 22 of 51 of Modifie. Revised Schedule —I Lu REGiSTRAR (Modification-Ill) ).\.,%..\. Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Rasul Hvdel Power Station PLANT DETAILS On Upper Jhelum Canal (UJC) about 74 KMs Down 1 Location Stream of Mangla. Type Total Capacity No. of Units 2. Plant Run of Canal 22 MW 2 Maximum Minimum 3. Head 85.05 ft 80.35 ft 4. Technology Kaplan Turbine Diameter Penstock No. Length Internal 5. Total No. of 2 281 ft. 21 ft. Penstock Minimum Expected Useful 6. Life of the 30 Years. Generation Facility Peaking/Base Operated as base load according to the water share 7. Operation in the Canal. Generator Voltage Units (1-2) = 11KV Power Factor Units (1-2) = 0.88 Plant 8. Characteristics Frequency 50 Hz Automatic Generation No Control Interconnection CCT Voltage (KV) Length(KM) Arrangements Rasul-Malikwal 66 38.4 _ (CCT details, Rasul-Malikwal-ll 66 38.4 9. length of Rasul-Kharian (D/C 132 42.0 Transmission Bundled) Line, voltage level details etc.) Rasul-Kharian (Bundled) 132 42.0 Page 23 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAP DA) Wapda House Lahore Hydel Power Station Dargai (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Page 24 of 51 of Mo. fied/Revised Schedule —I (Modification-Ill) ., Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Dargai Hydel Power Station PLANT DETAILS On Upper Swat Canal in Malakand Agency near 1. Location Dargai Distt. Malakand Agency. Type Total Capacity No. of Units 2. Plant Run of 20 MW 4 Canal Maximum Minimum 3. Head 243 ft 239 ft 4. Technology Francis Vane Turbine (Horizontally Mounted) Penstock No. Length Diameter Internal 5 ' Total No. of N.A Penstock Minimum Expected Useful 6. Life of the 25 Years. Generation Facility Peaking/Base 7. Runs on base load. Operation Generator Voltage Units (1-4) = 11 KV Power Factor Units (1-4) = 0.85 Plant 8. Characteristics Frequency 50 Hz Automatic Generation No Control Interconnection Voltage Length CCT Arrangements (KV) (KM) (CCT details, Dargai-Mardan 132 59.27 9. length of Transmission Dargai-Jabban 66 5.51 Line, voltage level details etc.) Dargai-Chakdara 132 30.07 Page 25 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Chitral (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Page 26 of 51 of Modifi /Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Chitral Hydel Power Station PLANT DETAILS On Lutko River, Garam Chashma Road 7 KMs East 1. Location of Chitral Town Total Type No. of Units 2. Plant Capacity Run of Canal 1 MW 4 Maximum Minimum 3. Head 110 ft 106 ft Units 1 & 2 OSS BERGER (Cross Flow) 4. Technology Units 3 & 4 Francis (Horizontal) Penstock No. Length Diameter 5. Total No. of N.A Penstock Minimum Expected Useful 6. Life of the 25 Years. Generation Facility Chitral Hydel Power House is not synchronized with Peaking/Base National Grid directly feeds a separate 11 KV line 7. Operation according to considerable variation in load during routine and peak hours. Generator Voltage Units (1-4) = 415 V Plant Power Factor Units (1-4) = 0.96 8. Characteristics Frequency 50 Hz Automatic Generation No Control Interconnection Voltage Length CCT Arrangements (KV) (KM) (CCT details, 11 KV Feeders. - 9. length of Feeding consumers Transmission - - directly Line, voltage level Without Grid Station details etc.) - c 5,NER R UG Page 27 of 51 of Modified/Revised Schedule —I (Modification-II l) REGiSTRAR :EPRA Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Kurram Garhi (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Re "REGiSTRAR age 28 of 51 of Mod ied/Revi d Schedule —1 (Ms •ification-Ill) Generation Licence Water & Power Development Authority (WAP DA) Wapda House Lahore Kurram Garhi Hyde! Power Station PLANT DETAILS Kurram Garhi On River Kurram at a distance of Power Station 12 KMs in West North of Bannu No. 1 City. 1. Location Kurram Garhi On River Kurram at a distance of Power Station 8 KMs in West North of Bannu No. 2 City. Type Total Capacity No. of Units 2. Plant Run of Canal 4MW 4 Maximum Minimum 3. Head 60 ft 60 ft 4. Technology Francis Turbine Tunnel No. Length Diameter Total No. of At - - At Intake 5. Tunnel Penstock No. of Power Penstock length - 1650 mm Tunnel 29.7 Meters Minimum Expected Useful 6. Life of the 30 Years. Generation Facility Peaking/Base 7. Base Load. Operation Generator Voltage Units (1-4) = 11 KV Power Factor Units (1-4) = 0.80 Plant 8. Characteristics Frequency 50 Hz Automatic Generation No Control Interconnection CCT Voltage (KV) Length (KM) Arrangements (CCT details, 9. length of Kurram Garhi- 66 16.37 Transmission Bannu Line, voltage level details etc.) .,+'r ERR,._ Page 29 of 51 of M d d/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Gomal Zam (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Page 30 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAP DA) Wapda House Lahore Gomal Zam Hydel Power Station PLANT DETAILS Right Bank of Gomal River at Khajuri Kach in South 1. Location Waziristan Agency about 60KM/ West of District Tank in Khyber Pakhtunkhwa (KPK). Type Total Capacity No. of Units 2. Plant Storage 17.4 MW 2 Maximum Minimum Design 3. Head 113.0 m 74.24m 100.0 m 4. Technology Vertical Francis Turbines No. Length Diameter 5. Tunnel 1 390 m 3 m The plant will be used for peak load (17.4 MW) as Peak/Base Load 6. well as base load (8.7 MW) depending on the Operation availability of water. Expected Date of 7. Commissioning of January 15, 2012 the Latest Unit Minimum Expected Useful 8. Life of the 50 years Generation Facility Generator Voltage Units (1-2) = 11 KV Power Factor 0.85 Plant 9. Characteristics Frequency 50 Hz Automatic Generation Yes Control Interconnection Voltage Length CCT Arrangements (KV) (KM) (CCT details, 10. length of Gomal Zam Power Transmission House -Tank Grid 132 55 Line, voltage level Station details etc.) ./,arR—Fis Page 31 of 51 of Modified/Revised Schedule —I (Modification-Ill) p• Generation Licence Water & Power Development Authority (WAP DA) Wapda House Lahore Hydel Power Station Jinnah Hydel (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (O. Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Page 32 of 51 of Modified/Revised Schedule —I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Jinnah Hydel Power Station PLANT DETAILS On the Indus River on the right side of the Jinnah Barrage as a bypass arrangement, approximately 5 1. Location KM downstream of Kalabagh Town in District Mianwali. Type Total Capacity No. of Units 2. Plant Run of River 96 MW 08 Maximum Minimum 3. Head 6.2 m 3.2 m 4. Technology Francis Vertical Turbine Tunnel No. Length Diameter 5. 1800 m Total No. of 1 including Bed Width = 133 m Channel Tailrace Peak/Base Load 6. Base load operation. Operation Expected Date of 7. Commissioning of March 31, 2012 the Latest Unit Minimum Expected Useful 8. Life of the 50 years Generation Facility Generator Voltage Units (1-2) = 11 KV Plant Power Factor 0.90 9. Characteristics Frequency 50 Hz Automatic Generation Yes Control Interconnection Arrangements CCT Voltage (KV) Length (KM) (CCT details, 10. length of JHPP-I 132 KV 5 KM Transmission Line, voltage level JHPP-II 132 KV 5 KM details etc.) _...... -...... _ Page 33 of 51 of Modified/Revised Schedule --I (Modification-Ill) Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore Hydel Power Station Allai Khwar (a). Location (location maps, site map) (b). Plant: run of the river, storage, veir (c). Head: minimum, maximum (d). Technology: Francis, Pelton, etc. size, number of units (e). Tunnel(s) if existing: length, diameter (f). expected life (g). Interconnection with national grid company, length of transmission line(s) (h). Peaking/base load operation (i). Plant characteristics: generation voltage, power factor, frequency, automatic generation control, ramping rate, control metering and instrumentation Page 34 of 51 of Modified/Revised Schedule —I (Modification-Ill) r• Generation Licence Water & Power Development Authority (WAPDA) Wapda House Lahore AIIai Khwar Flyclel Power Station PLANT DETAILS On left bank tributary of the River Indus at Besham in 1. Location Distt. Battagram in Khyber Pakhtunkhwa (KPK). Type Total Capacity No. of Units 2. Plant Storage 121 MW 2 Maximum Minimum 3. Head 697 m 687 m 4. Technology Pelton Wheel Vertical Shaft Turbines Tunnel No. Length Diameter Total No. of At 1 At Intake Channel Penstock Power 5. (i). Tunnels 1 2366 m 2.2 m - (Headrace) 00. TIrruignanteiolsn Nil Generally during High Flow Period, the plant will be Peak/Base Load 6. operated for base load whereas during Low Flow Operation Period, it will be utilized for peaking. Expected Date of 7. Commissioning of October 31, 2011 the Latest Unit Minimum Expected Useful 8. Life of the 50 years Generation Facility Generator Voltage Units (1-2) = 11 KV Power Factor 0.85 Plant 9. Characteristics Frequency 50 Hz Automatic Generation Yes Control CCT Voltage(KV) Length(KM) Interconnection Arrangements AKHP-DKHP 132 50.5 (CCT details, AKHP-KKHP 132 16.5 10. length of AKHP-NEW 220 83.3 Transmission MANSEHRA Line, voltage level NEW MANSEHRA- details etc.) 220 100.5 40,:v-rii-ilt&AMA