Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

PRE-FEASIBILITY REPORT 1. SUMMARY

Project Murrum Quarry

Name of Company / Mine Owner Harish Sahu

Location Village Pond

Taluka Gariaband State

1 Mining Lease Area & Type of Private land is 0.72ha. The area is almost flat terrain land with devoid of vegetation. It is non forest, non agriculture area.

2 Geographical Boundary Latitude Longitude co-ordinates point A 20°45'53.47"N 81°56'34.94"E B 20°45'53.31"N 81°56'38.48"E C 20°45'51.12"N 81°56'37.82"E D 20°45'50.07"N 81°56'35.07"E

3 Name of Pairi river about 2km west of the area. Rivers/Nallahs/Tanks/Spring/ Lakes etc

4 Name of Reserve Forest(s), No forest surrounding the lease area Wild life Sanctuary/ National parks etc.

1 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

5 Topography of the area The area is almost flat terrain with devoid of vegetation. The maximum elevation is about 318 m from M.S.L

6 Project Proposal Maximum 4995 m3 per year

7 Name of Mineral mined Murrum

8 Rate of Production (in tons) Based on 200 working days, average production per day is 24.97 m3 per day

3 9 Mineral Reserve in Million The estimated geological reserve in the area is 21600m 3 Tons Mineable reserve is 15000 m

10 Life of mine 2 years

11 Drilling/ Blasting Not required

12 Mining method Quarrying method is a type of manual Open- cast quarry by a system of benches.

13 Ground water table No ground water pollution will be there as the rock or intersection waste/soil dump of this deposit does not contain any harmful ingredients, which could leach down to the water table that is much below the lowest quarrying bench level.

14 Drainage pattern/ water Pairi river about 2km west of the area. courses Drainage pattern is dendritic to sub dendritic.

2 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

15 Break-up of Land Utilization The total area is 0.72ha Pattern This is Private land. Area under excavation –0.474 ha. Area for soil dumping –0.246 (along lease boundary) Plantation–0.246(along lease boundary)

16 Water requirement & Source As much as about 1 KLPD Water will be required for mining operations including dust suppression along haul road / mine faces, cleaning, washing, drinking as well as plantation. Energy/power is not required as the quarrying activities are carried out in day time only.

17 Solid waste/Tailings Only about 25% waste materials will be generated. This material is nothing but the broken pieces of murrum.

18 IBM approval : Date Not applicable

19 Cost of project Cost of the project: (Rs. Lakhs] About 2 lakhs/-

20 Any Other (specify) Not required

Name and address of the company Harish Sahu Village - Pond Tehsil – Chura Dist. – Gariaband (C.G.) Mine office Village - Pond Tehsil – Chura Dist. – Gariaband (C.G.) Email - Prospecting Agency Prospecting is not required as the area is less than 5 ha. Type of Activity Manual open-cast Utilities (Power, water Requirement) No. water, power required for quarry purpose. Manpower Requirement Skilled person - 01 Unskilled labour -10

2. INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION

3 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

(i) Identification of Project and Project Proponent. Name of the Project: Murrum Quarry at Village Pond Tehsil Gariaband and District Gariaband Chhattisgarh – 493445.

Project Proponent Collector, Gariaband was granted Murrum Quarry of Village Pond District- Gariaband to Harish Sahu for the quarrying of Murrum for Temporary permit for 2 year as per rule 58 of Chhattisgarh Minor mineral Rules, 2015 (as amended)..

As per Environment Impact Assessment (EIA) Notification, 2006 (as amended) requires mining projects (new projects, expansion or modernization of existing projects as also at the stage of renewal of quarry lease) all the mining projects (new projects, expansion or modernization of existing projects as also at the stage of renewal of mine lease) irrespective of the lease area requires to be obtained prior environment clearance under the provisions thereof. Mining projects with lease area up to 50 ha are categorized as category ‘B’. Category ‘B’ projects are considered by the respective State Level Environment Impact Assessment Authority, notified by MoEF under the EIA Notification, 2006. Supreme Court of in Special leave petition (C) dated 27th February 2012 directs that “leases of minor mineral" is including their renewal for an area up to 25 ha or less be granted by the states/UTs only after getting environment clearance from the MoEF. Further Government of India, Ministry of Environment and Forest issued guidelines dated 24th Dec 2013 and amendments are made regarding categorization of ‘B’ category projects as “B1” and “B2”. Further Government of India, Ministry of Environment and Forest constituted district level Environment Impact Assessment Authority (DEIAA) and District level Expert Appraisal Committee (DEAC) as per their notification dated 15. 01. 2016 to issue clearness for mining of Minor Minerals of 5 hectares and less under category “B2”. (ii) Brief Description of Nature of the Project

This is a small quarry project for exploiting murrum. The method of quarrying will be opencast manually for excavation of murrum and loading for transportation.

4 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

(iii) Need for the Project and its importance to the country and or region Murrum has the great importance in constructions of building, as it has the property of taking good polish. This polished murrum have a very good demand in the market. The raw murrumalso has market to be used as “Road Material”. Hence small scale mining of murrumis a good source of earning specially for local villagers for their livelihood. (iv) Demand Supply Gap

The demand of murrum is huge. The raw murrumalso has market to be used as “Road Material”. To fill up the demand, the murrum mined out from the quarry lease area will be supplied in the open market in raw form.

(v) Demand Supply Analysis

The Murrum“Road Material” have great demand in the market but the supply is limited. To fulfill the demand of market the mined out murrums will be supplied in the market.

(vi) Employment Generation (Direct and Indirect) due to the Project

Unskilled 10 labors will be required for loading the mined out murrums on trucks etc and skilled 1 people will be required for supervision purpose, maintain the record of production and shipment etc.

3. PROJECT DESCRIPTION

(i) Type of Project (including interlinked and interdependent project, if any)

This project is a small quarry project.

Location (map showing general location, specific location and project boundary & project site-specific layout) with coordinates

The murrum quarry lease area is situated near Village Pond in Tehsil Gariaband and District Gariaband of Chhattisgarh State. The area falls in survey of India Toposheet No. 64 H/13

The detail of the area is as under:

District : Gariaband

5 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

Tehsil : Chura Village : Pond Area (ha) : 0.72ha The coordinates of the area are:

BP. No. LATITUDE LONGITUDE A 20°45'53.47"N 81°56'34.94"E

B 20°45'53.31"N 81°56'38.48"E

C 20°45'51.12"N 81°56'37.82"E

D 20°45'50.07"N 81°56'35.07"E Location Map and Google Map showing coordinates of the lease area is attached herewith.

(ii) Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted

No alternate site is considered as the quarry lease is a site specific activity. In the present case, the collector has granted the quarry lease to the owner for the quarry of murrum. As for as the environmental considerations are concerned the area is away from the human habitation, in the Private land, free from forest. This quarry activity does not affect the water table of the area. Limited machinery will be required for mining of murrum and limited transport vehicles are needed for shipment of produced material.

(iii) Size or Magnitude of operation

The quarry lease area 0.72ha in which the working area is 0.071 ha and the average rate of production of murrum is about 24.97 m3 per day. Hence the size or magnitude of operation is very small.

(iv) Project Description with Process details (a schematic diagram/ Flow chart showing the project layout, components of the project etc. should be given

The murrum quarrying will be carried out mainly by manual with the use of quarrying equipments and finally transported through trucks, tippers etc. to the end users.

Drilling:

6 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

Drilling is not required Blasting:

Blasting is not required.

Type of explosives used / to be used

Not applicable. Storage of explosive (like capacity and type of explosive magazine)

Not required.

(v) Raw Material/ Consumables Required along with estimated quantity, likely source, marketing area of final product, mode of transport of raw material and finished product No any raw material/ consumables are required. The murrum produced from the mine and transported through trucks, tippers etc. to the end users. (vi) Availability of water, its source, Energy/power requirement and source should be given As much as about 1 KLPD Water will be required for mining operations including dust suppression along haul road / mine faces, cleaning, washing, drinking as well as plantation. Energy/power is not required as the mining activities are carried out in day time only. (vii) Quantity of wastes to be generated (liquid and solid) and scheme for their management/ disposal About 25% sub grade materials will be generated. This sub grade material is nothing but the broken pieces of flag stone. Hence it is proposed to stack this sub grade material in a suitable place. (viii) Selection of Dumping Site: The stacking of the sub grade material generated during quarrying is proposed in the mine area itself at a suitable place.

4. SITE ANALYSIS

(i) Connectivity

The area is about 13 km from District HQ Gariaband. The nearest railway station Belsonda is about 5.5 km.

(ii) Land Form, and Land Ownership

7 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

The land on which this quarry lease sanctioned is 0.72ha on Private land in Khasra No 1044/1, 1044/2 covering an area of 0.72ha shown in the map.

(iii) Topography along with maps

The quarry area under study falls in Survey of India Toposheet No. 64 H/13. The area is about 0.5 km from the village Pond in the south west direction. The maximum elevation is about 318 m from M.S.L. The area is almost flat terrain with devoid of vegetation.

(iv) Climatic data from Secondary Sources

The climate is sub-tropical, semi arid, continental and monsoon type. Thus, it has hot summers, cool winters and small rainy season.

(v) Social infrastructure available

There is no social infrastructure existing at/or in the near vicinity of 1.0 Km radius of the quarry area. 5) PLANNING IN BRIEF

(i) Planning Concept (type of industries, facilities, transportation etc) town and country Planning / Development authority classification: The murrum quarrying activity has no other concept except quarrying and transportation of mined out material to end-users.

(ii) Population Projection: Since there will be hardly any influx of people from outside in the region, hence there will not by any impact on the population projection of the region accept the normal increase in population.

(iii) Land Use Planning Area of murrum quarrying is 0.72ha. The area under excavation will be only 0.474 ha while for stacking surface soil and waste dump in 0.245ha along lease boundary and plantation the required area will be 0.245 ha along lease boundary. It is non forest; Private land situated near Village pond thinly populated village.

8 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

(iv) Assessment of Infrastructure Demand (Physical & Social): Since there will not be any major influx of people from outside, in this region because of the project, no adverse effect on physical and social infrastructure like roads, electricity, water supplies etc are anticipated.

6. PROPOSED INFRASTRUCTURE

(i) Industrial Area (Processing Area)

There is no proposal for any infrastructure development.

(ii) Residential

There is no plan for development of residential area in the region.

(iii) Green Belt

Plantation will be carried preferably on the lease boundary, on dump area, on overburden stack and along the road used for transportation.

Approx 200 saplings of the local species will be planted in the proposed area in 1st and 2nd year during first five year production period.

(iv) Social Infrastructure

It is expected that the project will lead to much needed employment opportunities in the villages which will contribute to the socio-economic development of this area.

(v) Drinking Water Management (Source and Supply of Water)

Small quantity of water is required for drinking purpose which will be meet out from the bore well/river nearby.

(vi) Sewerage System

In view of the personals engaged in the project the movable type of sewerage system may be installed /deployed nearby the mine area. This may avoid polluting the land / water / air of the area.

(vii) Industrial Waste Management

No industrial waste will be generated hence management not required.

(viii) Power Requirement & Supply / Source.

9 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

Not required.

7. Rehabilitation and Resettlement (R & R) Plan

Not required as the area is away from village and free from habilitation.

8. Project Schedule and Cost Estimates

Total expenses estimated about 2lakh /-

10 Pre Feasibility Report of Laterite, Village Pond, Area- 0.72 ha District – Gariaband (C.G.)

Recommendations

The quarry of murrum and allied activities has no impacts on the surrounding environment. Moreover based on development of this project certain positive impact will be there on the nearby village population in terms of employment generation etc. Hence this project may be cleared and clearances accorded.

Signature of Project Proponent

11