APPENDIX I (See paragraph – 6) FORM 1 (I) Basic Information Serial Item Details Number 1. Name of the project/s Proposed Grinding Unit of M/s MARCE CEMENT WORKS LIMITED 2. S. No. in the schedule As per the EIA Notification, 2006 & its amendments issued by MOEFCC Govt of , this project is categorized as Category B Project. 3. Proposed Cement Grinding Capacity: capacity/area/length/tonnage to be : 400x2 -800 TPD i.e 2,40,000 Tonne handled/command area/lease per Annum (PPC) area/number of wells to be drilled. Area : 1.133 Hectare 4. New/Expansion/Modernization New Project 5. Existing Capacity/Area etc. New Project 6. Category of project i.e. ‘A` or ‘B` B 7. Does it attract the general No, it is not covered under general condition? If yes, please specify. condition. 8. Does it attract the specific No, it is not covered under specific condition? If yes, please specify. condition. 9. Location Patana Plot/Survey/Khasra No Araji No. 683, 684/1,684/2,684/3, 685/1,685/2, 685/3, 685/4, 686/4, 686/5, 7112/2. Village Patana Tehsil Ramnagar District State

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 1 10. Nearest railway station/airport (i) Jeonathpur Railway Station along with distance in kms (approx. 0.5 Km towards South- West direction from the proposed industrial site) (ii) International Airport, (approx 31 km towards North- West direction from the proposed industrial site) 11. Nearest Town, city, District Nearest Town : Ramnagar Approx. 1.24 Headquarters along with distance km from the proposed industrial site in in kms. NNW direction. City: Chandauli at a distance of 20.20 Km towards North-East direction. District Headquarter: Chandauli at a distance of 20.20 Km towards North- East direction. 12. Village Panchayats, Zilla Parishad, Mauja- Patana, Pargana- Ralhupur Municipal Corporation, Local body Village: Patana, Industrial Area, (complete postal addressess with Ramnagar, Chandauli. telephone nos. to be given) Tel No: +91 7007927264 13. Name of the applicant Mr. Shailendra Kumar Singh 14. Registered address 294, Om Sai Kripa,Jain Mandir Road, Kailashpuri, Mughalsarai, Chandauli(UP) 15. Address for correspondence: 294, Om Sai Kripa,Jain Mandir Road, Kailashpuri, Mughalsarai, Chandauli(UP) Name Mr. Shailendra Kumar Singh Designation(Owner/Partner/CEO) Director

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 2 Address Head Office : 294, Om Sai Kripa,Jain Mandir Road, Kailashpuri, Mughalsarai, Chandauli(UP) Factory : Mauja- Patana, Pargana- Ralhupur Village: Patana, Industrial Area, Ramnagar, Chandauli. Pin Code 232101 E-mail [email protected], [email protected] Telephone No. +91 7007927264,09982170000 Fax No. --

16. Details of alternative sites No alternative site has been considered. examined, if any. Location of these sites should be shown in a topo sheet. 17. Interlinked Projects No 18. Whether separate application of No interlinked projects has been submitted? 19. If yes, date of submission No 20. If no, reason No 21. Whether the proposal involves No approval/clearance under: if yes, details of the same and their status to be given. (a) The forest (Conservation) Act, 1980? (b) The wildlife (Protection) Act, 1972?

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 3 (c) The C.R.G Notification, 1991? 22. Whether there is any Government No Order/Policy relevant/relating to the site? 23. Forest land involved (hectares) No 24. Whether there is any litigation No pending against the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Orders/direction of the court, if any and its relevance with the proposed project.

(II) Activity

1. Construction, operation or decommissioning of the Project involving action which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sl. Information/Checklist Yes/No Details thereof (with approximate No confirmation quantities/rates, wherever possible) with source of information data. 1.1 Permanent or temporary change Yes The 1.133 hectare dry barren & in land use, land cover or non fertile land will be under the topography including increase in industrial uses for the Grinding intensity of land use (with unit. respect to local land use plan) 1.2 Clearance of existing land, Yes Total Land is clear & plain so no vegetation and buildings? clearance of existing vegetation & buildings. 1.3 Creation of new land uses? No Not Applicable 1.4 Pre-construction investigations Yes The soil testing/investigation e.g. bore houses, soil testing? studies will be carried out before commencement of constructional activities.

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 4 1.5 Construction works? Yes Construction will be done for the installation of grinding Unit. 1.6 Demolition works? No No demolition works will be done 1.7 Temporary sites used for Yes Only temporary residential construction works or housing of facilities will be provided for the construction workers? workers. However, most of the workers engaged will be local labor from nearby villages. 1.8 Above ground buildings, Yes Limited excavation work will be structures or earthworks carried out for construction of the including linear structures, cut civil structures. Some amount of and fill or excavations. levelling / grading through cut and fill is required to make the land suitable for construction. Above ground structures include main plant, service buildings, storage etc 1.9 Underground works including No None mining or tunneling? 1.10 Reclamation works? No Not applicable as no reclamation works are involved. 1.11 Dredging? No Not applicable as no dredging is involved.

1.12 Offshore structures? No No offshore structures are applicable. 1.13 Production and manufacturing Yes Cement Manufacturing Process: processes? 1. Cement Manufacturing: The close circuit Ball Mill & high efficiency separator will be installed. Clinker and Gypsum will be ground in Ball Mill along with flyash. After final blending the quantity is stored into cement storage silos then it goes for packaging and there by its ready for sale 2. Packing & Loading System:

Cement from Cement Silo will be extracted and taken to Rotary Packer for automatic filling of

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 5 cement bags and will be loaded in trucks for dispatch. 1.14 Facilities for storage of goods or Yes Covered storage facilities/silos will materials? be provided within the proposed project site separately for storage of clinker, gypsum, fly ash and cement. (Project feasibility report Enclosed) 1.15 Facilities for treatment or Yes Dust collected in the pollution disposal of solid waste or liquid control equipments (Bag effluents? House/Bag Filters) will automatically be recycled in the process. Discharge from office toilets and canteen will be there which will be treated in septic tank. 1.16 Facilities for long term housing No The operational workers will be of operational workers? employed from nearby area, who may travel up and down daily from their residence for work so, that housing is not require at the site. 1.17 New road, rail, or sea traffic No The site is well connected by road. during construction or No addition construction of road operation? network required.

1.18 New road, rail, air waterborne or No No new transportation network is other transport infrastructure required; the proposed project site including new or altered routes is well connected by road. and stations, ports, airports etc? 1.19 Closure or diversion of existing No Not required as the site is transport routes or connected with road. infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission No No diversion of transmission lines lines or pipelines? or pipelines will be required. 1.21 Impoundment, damming, No There will be no change from the culverting, realignment or other proposed project. changes to the hydrology of watercourses or aquifers?

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 6 1.22 Stream crossings? No No stream is crossing the proposed project site. 1.23 Abstraction or transfers of water No The requirement of the water will from ground or surface waters? be met from borewell/tanker water supply. 1.24 Changes in water bodies or the No . There is no nallah or stream in land surface affecting drainage the area. Except Ganges River or run off? present with in 5 Km radius from the grinding unit. . After setting up the plant, drains will be made all around the plant to collect the rain water. There will be no outside discharge from the proposed unit. 1.25 Transport of personnel or Yes The site is well connected with NH materials for construction, -2 (approx. 1.60 KM in NW operation or decommissioning? direction from the proposed industrial site). Vehicle for the staff is provided. The raw materials and finished product will be transported by railway.

Raw Material : Clinker available from MP & Rajasthan Flyash : available from Hindalco Renukoot, NTPC Bijpur Gypsum: Available from Rajasthan & Bhutan 1.26 Long term dismantling or No No dismantling / decommissioning decommissioning or restoration are involved. works? 1.27 Ongoing activity during No No decommissioning is involved. decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in Yes The influx of people will be either temporarily or permanently for job opportunity. permanently? 1.29 Introduction of alien spices? No Only native species are planted at the site. 1.30 Loss of native species or genetic No Local species are planted; hence no diversity? loss of genetic diversity or native species is anticipated. 1.31 Any other actions? No None

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 7 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply):

Sl. Information/Checklist Yes/No Details thereof (with approximate No confirmation quantities/rates, wherever possible) with source of information data 2.1 Land especially undeveloped or Yes Non fertile land. agricultural land (ha) 2.2 Water (expected source & Yes 5 KLD water will be required for competing users) unit: KLD domestic purpose only. No water will be required for industrial process. The requirement of the water will be met from underground water through bore wells/tanker water. Permission for the same will be obtained from respective authority. Gram Panchayat NOC enclosed as Annexure No. 2. 2.3 Minerals (MT) Yes Gypsum will be used as raw material. 2.4 Construction material – stone, Yes Construction material such as aggregates, sand/soil(expected sand, steel, concrete, aggregates source – MT) etc will be used, which are locally available. However, the quantification of the materials will be done during detailed engineering stage. 2.5 Forests and Timber (source – No Not required. MT) 2.6 Energy including electricity and Yes 1000kVA power will be required fuels(sources, competing users) for grinding unit which will be Unit: fuel (MT), energy (MW) sourced from Uttar Pradesh Power Corporation Ltd. (UPPCL). Letter for the same enclosed as Annexure No.3. 2.7 Any other natural resources (use No No such requirement. appropriate standard units) 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns actual or perceived risks to human health.

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 8 Sl.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, No No hazardous material will be which are hazardous (as per used. MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease No From the proposed project there or affect disease vectors (e.g. will be no change in occurrence of insect or water borne diseases) disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. No Direct and indirect employment by changing living conditions? opportunities generated due to the proposed project, which would improve the living standards of the local people. 3.4 Vulnerable group of people who No There will be no such adverse could be affected by the project affect from the proposed project. e.g. hospital patients, children, the elderly etc., From the proposed industries there will be only dust particulate matter will be generated which will be kept within the prescribed limit by implementing the proper environmental management as given below:- 1. High efficiency bag house for cement mill venting and bag dust collector at all material transfer points. 2. Storage of clinker and fly ash in silo and gypsum in covered storage yard. 3. Covered unloading hopper with de-dusting arrangement for unloading of all raw materials. 4. Covered conveyor belts for material transportation.

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 9 5. Concreted roads and sweeping by vacuum machine. 6. Green belt all around the plant premises. Direct and indirect employment avenues will be created due to project, which would improve the living conditions. 3.5 Any other causes No Not Envisaged

4. Production of solid wastes during construction or operation or decommissioning (MT/Month)

Sl.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine No Non fertile land used in the past wastes so no such problems reported. 4.2 Municipal waste (domestic and No Only domestic waste will be or commercial wastes) produced. 4.3 Hazardous wastes (as per No As it will be cement grinding unit Hazardous Waste Management so no question of Hazardous Rules) wastes. 4.4 Other industrial process wastes No Nil 4.5 Surplus product No No such extra product other than cement. 4.6 Sewage sludge or other sludge No No treatment required, because from effluent treatment. water will be used only for domestic purpose & water spraying. Sewage will be stored in a septic tank, and then will be released through panchayat drain. 4.7 Construction or demolition No Small amount of construction wastes waste will be generated during establishment stage whereas no demolition waste is envisaged. 4.8 Redundant machinery or No Not Applicable equipment 4.9 Contaminated soils or other No The land is non fertile. materials 4.10 Agricultural wastes No The land is clean and contains no waste.

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 10 4.11 Other solids wastes No Not found.

5. Release of pollutants or any hazardous, toxic or noxious substance to air (Kg/hr)

Sl.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data

5.1 Emissions from combustion of Yes The emission of PM10, SO2, NOx & fossil fuel from stationary or mobile sources. CO may be accounted due to use of diesel operated equipments for various activities. Several Mitigation measures will be adopted :

 PUC certified vehicles will be used.

 Plantation will be done at the periphery of the project site and along the road sides.

Better maintenance of machines and vehicles will be done to reduce emission. 5.2 Emissions from production Yes The emission of Particulate processes. matter (dust) will be generated from the mill vent, which will be maintained < 50 mg/Nm3 by installation of Bag Houses. 5.3 Emission from materials Yes Fugitive emissions are envisaged handling including storage or during material handling and transport. transportation. At all points of material handling and material transfer bag filters shall be provided 5.4 Emission from construction Yes Fugitive dust emissions are activities including plant and envisaged from the construction equipment. activities apart from gaseous emissions from the vehicles and construction machineries. But this will be temporary.

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 11 5.5 Dust or odours from handling of Yes The construction activities may materials including construction cause increase in SPM levels materials, sewage and waste. locally. The impact will be reversible, marginal and temporary in nature. However, there will be no odour generating substances. 5.6 Emission from incineration of No No waste material will be waste incinerated in the proposed project. 5.7 Emission from burning of waste No Not Applicable in open air (e.g. slash materials, construction debris) 5.8 Emission from any other No Nil sources. 6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl.No. Information/Checklist Yes/No Details thereof (with confirmation approximate quantities/rates, wherever possible) with source of information data 6.1 From operation of equipment Yes . Due to operation of e.g. engines, ventilation plant, machinery and vehicles crushers there may be some increase in noise normally between 75-85 dB (A). . To combat such noise levels PPE will be provided to operators/ workers. . Green belt has been developed around the surrounding area to restrict noise. . Regular Maintenance of machineries will be done. 6.2 From industrial or similar Yes There will be generation of processes noise due to running of machinery. Proper mitigation measures will be taken for the reduction of noise levels by facilitating acoustic enclosures. Personal protective equipment will also be

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 12 provided. 6.3 From construction or demolition Yes During construction period noise will be generated due to handling of plant machineries The constructional noise will be in the range of about 65-75 dB (A). 6.4 From blasting or piling No Not applicable 6.5 From construction or Yes The noise generation will be operational traffic very low as limited quantity of raw materials and products will be transported. During operation of traffic movement, it is likely to be in the range of 64 – 68 dB (A) only as it is an intermittent / slow process. 6.6 From lighting or cooling systems No Not envisaged 6.7 From any other sources No Nil

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea

Sl.No. Information/Checklist Yes/No Details thereof (with confirmation approximate quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No In the grinding unit, there will spillage of hazardous materials be no use / handling of hazardous material except during annual oil change period, which will be handled in closed containers. 7.2 From discharge of sewage or Yes Water will be used only for other effluents to water or the domestic purpose. land(expected mode and place of Municipal Waste Water/ discharge) Sewage will be stored in a septic tank. 7.3 By deposition of pollutants Yes There is likely hood of increase emitted to air into the land or in SPM level due to the into water proposed grinding unit. But proper mitigating measures such as

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 13  Silo for material storage  High efficiency bag- filters  Concreted roads & better house-keeping Periodical monitoring will be done and results will be analyzed for corrective actions if any. 7.4 From any other sources No None

7.5 Is there a risk of long term build No None up of pollutants in the environment from these sources?

8. Risk of accident during construction or operation of the Project, which could affect human health or the environment.

Sl.No. Information/Checklist Yes/No Details thereof (with confirmation approximate quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, fires No No chance of accident on account etc. from storage, handling, use of explosion, spillage, fire or or production of hazardous substances hazardous substances. Proper maintenance of plant machineries, leakage proof condition of all plant machineries, good house- keeping, implementation of all required safeguards, use of personnel protective equipments availability of fire extinguishers/ tender and Proper training of all persons will ensure smooth and accident free operation of the unit. 8.2 From any other causes No Not possible.

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 14 8.3 Could the project be affected by No No cases are reported so far as natural disaster causing the area is free from any seismic environmental damage (e.g. activity & no such records of floods, earthquakes, landslides, seismic activities are available cloudburst etc.)? in the area.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality.

Sl.No. Information/Checklist Yes/No Details thereof (with confirmation approximate quantities/rates, wherever possible) with source of information data 9.1 Lead to development of No Proposed project will result in supporting. further growth of the Facilities, ancillary development surrounding areas by increased or development stimulated by direct and indirect employment the project which could have opportunities in the region impact on the environment e.g. including ancillary development. Residential . Supporting infrastructure facilities will be provided to the (roads, power supply, waste staff. water treatment, etc.) There will not be any impact on . housing development existing housing facilities of . extractive industries surrounding villages. Power . supply industries supply will be available from . other state grid. Therefore there will be no negative impact on existing infrastructure of surrounding community. Employment opportunities will increase due to the requirement of workers for the proposed project. Local people will be preferred for employment. This will contribute in raising the socio- economic status and standard of living of the nearby villagers. 9.2 Lead to after-use of the site, No Not possible as special care will which could have an impact on be taken. the environment 9.3 Set a precedent for later No Not required. developments

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 15 9.4 Have cumulative effects due to Yes Other existing or planned proximity to other existing or projects within proximity to the planned projects with similar proposed plant are of small effects sizes. No significant cumulative effects are expected. (III) Environmental Sensitivity

Sl.No. Areas Name/Identity Aerial distance (within 15kms.) Proposed project location boundary 1 Areas protected under Kachhua Wild Approx. 6.00 km towards international conventions, Life Sanctuary, North-West direction from national or local legislation Varanasi for their ecological, the proposed industrial site. landscape cultural or other related value 2 Areas which are important Ganga River Approx. 3.25 km in West or sensitive for ecological direction from the proposed reasons – Wetlands, watercourses or other water industrial site. bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, Kachhua Wild Approx. 6.00 km towards important or sensitive Life Sanctuary, North-West direction from species of flora or fauna for Varanasi the proposed industrial site. breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or No No such area nearby. underground waters 5 State, National boundaries No Not State or national boundaries within 15 km radius of the study area.

6 Routes or facilities used by NH 2 Approx. 1.60 Km towards the public for access to NW direction from the recreation or other tourist, proposed industrial site. pilgrim areas SH-97 Approx. 0.65 Km towards West direction from the proposed industrial site. 7 Defense installations Yes Approx. 13.0 km towards NW direction from the proposed industrial site. 8 Densely populated or built- Ramnagar Approx. 1.24 km from the

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 16 up area (Population: proposed industrial site in 49,132) Source: NNW direction. Census 2011 9 Areas occupied by sensitive School- Manas Approx. 8.70 km in NE man-made land Convent direction from the proposed uses(hospitals, schools, School,Alinagar industrial site. places of worship, community facilities) Hospital – Approx. 7.69 km in NW Heritage direction from the proposed Hospital, industrial site. Varanasi

Peace Points Approx. 9.11 km in NNW Hospitals Pvt. direction from the proposed Ltd., Varanasi industrial site.

Place of worship– Shri Approx. 9.8 km in NW Kashi direction from the proposed Vishwanath industrial site. Temple 10 Areas containing important, No The area is not containing high quality or scarce any important, high quality resources (ground water or scarce resources. resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to No No such area nearby. pollution or environment damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural No The project site falls under hazard which could cause Low Damage Risk Zone, i.e. the project to present Zone III. environmental problems Source: NDMA (National (earthquakes, subsidence, Disaster Management landslides, erosion, flooding Authority) or extreme or adverse climatic conditions)

(IV). Proposed Terms of Reference for EIA studies :

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 17 As per the EIA Notification, 2006 & its amendments issued by MOEFCC Govt of India, this project is categorized as Category B Project, therefore we are submitting the proposed ToR.

UNDERTAKING

“I hereby given undertaking the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.”

Date: 14/02/2017

Place: Chandauli Signature of the applicant

With Name and Full Address

(Project Proponent/ Authorized Signatory)

Mr. Shailendra Kumar Singh

294, Om Sai Kripa,Jain Mandir Road, Kailashpuri, Mughalsarai, Chandauli(UP)

Fulgro Environmental & Engineering Services India Pvt. Ltd., Jaipur 18