Yukon Energy Corporation

Total Page:16

File Type:pdf, Size:1020Kb

Yukon Energy Corporation YUKON ENERGY CORPORATION APPLICATION FOR APPROVALS REGARDING THE VGC GROUP POWER PURCHASE AGREEMENT INTERROGATORY RESPONSES FILED December 11, 2017 John Maissan (JM) Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-1 1 TOPIC: YEC-VGC PPA Application 2 3 REFERENCE: Page 1: VGC on-site diesel generation less than 5 MW 4 5 PREAMBLE: 6 7 QUESTION: 8 9 a) What number and sizes of diesel generators does Victoria Gold plan to install? 10 11 ANSWER: 12 13 (a) 14 15 VGC Group plans to install 3 units [1.65 MW for each unit]. December 11, 2017 Page 1 of 1 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-2 1 TOPIC: YEC-VGC PPA Application 2 3 REFERENCE: Page 2 and elsewhere: 4 5 PREAMBLE: 6 7 QUESTION: 8 9 a) Please explain why YEC is having VGC build the McQuesten substation – is it 10 because VGC can do it at lower cost or faster than YEC, has fewer contracting 11 constraints, has better access to capital, etc.? 12 13 b) The PPA Schedule B on page 5 (Appendix B1) indicates that VGC will be having 14 ATCO tender the long lead equipment. 15 i. Is the ATCO referred to here ATCO Electric Yukon, or ATCO Electric in 16 Alberta? 17 ii. Please explain the relationship between VGC and ATCO on this project. 18 iii. Please explain the relationship between YEC and ATCO on this project. 19 20 ANSWER: 21 22 (a) 23 24 YEC and VGC Group have worked together to finalize detailed design of the McQuesten 25 Substation and are continuing to work together, pursuant to the MOU and the PPA, on the 26 tendering, procurement, construction, commissioning and turnover of the substation to 27 YEC. 28 29 As the timing for completion of the substation is a key risk item for VGC Group to be able 30 to connect to the grid and receive grid power, and VGC Group is also responsible for 31 funding most of the McQuesten Substation capital costs, a decision was made for VGC 32 Group to undertake tendering and construction management pursuant to MOU terms. 33 VGC Group is able to proceed with these activities, as required to protect its in-service 34 schedule, prior to the YUB approval of PPA provisions as required under Section 3.1(a) 35 of the PPA. December 11, 2017 Page 1 of 2 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-2 1 (b) 2 3 Please see response to YUB-YEC-1-27(a). The ATCO referred to is ATCO Power Canada 4 Limited. 5 6 ATCO Power Canada Limited was selected through an RFP process and retained by VGC 7 Group to undertake detailed design of the substation and to provide Issued for 8 Construction (IFC) drawings and technical specifications for a construction RFP document 9 for tendering this work. As noted in the response to UCG-YEC-1-23 (a-b), Yukon Energy 10 funded 50% of these costs to ensure the McQuesten Substation was designed to operate 11 at the 138 KV standard required by YEC. 12 13 Pursuant to the MOU provided in Schedule B of the PPA, ATCO Power Canada Limited 14 and Yukon Energy have worked together with VGC Group to complete the required 15 substation design in order to advance the project towards the construction stage. December 11, 2017 Page 2 of 2 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-3 1 TOPIC: YEC-VGC PPA Application 2 3 REFERENCE: Page 5: VGC approximate 90 day period of reduced electrical 4 demand in winter between December 1 and March 31. 5 6 PREAMBLE: 7 8 QUESTION: 9 10 a) Is VGC to inform YEC of the dates for this reduced demand or will YEC set the 11 dates? 12 13 b) A 90 day period could well run from January 1 to March 31 leaving YEC to meet 14 peak system demands during November or December with the mine load at it high 15 level. For the November 1 to December 31 period of each of the years 2012 to 16 2016 and November 2017 please provide: 17 i. The peak load (in MW) each year, and 18 ii. The peak load in the November – December period. 19 20 c) If the VGC mine runs at full load during November and much of December is there 21 not a high probability that a substantial portion of their 10.4 to 13.3 MW normal 22 load would contribute to peak system loads? 23 24 d) What are the peak system loads projected by YEC for the 2019-2020 and 2020- 25 2021 winters? 26 27 e) At these peak loads what would be the anticipated contributions of hydro, LNG, 28 and diesel generation absent new renewable energy additions? 29 30 ANSWER: 31 32 (a) 33 34 Pursuant to Section 5.2 of the PPA, VGC Group will inform YEC of the specific 90-day 35 period for each year. December 11, 2017 Page 1 of 4 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-3 1 (b) 2 3 The 90-day period is expected to be from early December to early March each year. VGC 4 Group’s planning assumes that this occurs during the period of coldest temperatures. 5 6 System hourly peak load for the year and the November/December period over the 2012- 7 2016 period are presented in Table 1 below. Except for 2017 YTD (when December is not 8 yet over), the peak occurred in December of each of these years. 9 10 Table 1. Comparison of hourly peak load and the peak load over the November- 11 December period for a given year (2012-2017 YTD). NOVEMBER DECEMBER HOURLY HOURLY HOURLY YEAR PEAK LOAD PEAK LOAD PEAK LOAD [MW] [MW] [MW] 2012 82.24 79.45 82.24 2013 82.69 77.24 82.69 2014 76.52 73.52 74.17 2015 82.06 73.23 77.93 2016 87.51 74.33 87.51 2017YTD 85.21 83.07 77.12 12 13 (c) 14 15 As noted in response to (b) above, VGC Group is not expected to run at peak load during 16 the coldest periods in December. Yukon Energy does not forecast a high probability that 17 a substantial portion of the VGC Group normal peak load (i.e., materially more than 45% 18 to 50% of the 10.0 to 12.7 MW peak sales per Table 1 of PPA Application) will contribute 19 to winter peak system loads. 20 21 (d) 22 23 Although Yukon Energy has received forecast VGC Group loads for each of the first six 24 years of operation, the overall winter peak load impacts will be driven by the extent of 25 other industrial mine loads on the grid in each of these years – and YEC does not have 26 useful information today as to likely forecasts for each year for Minto or Alexco. December 11, 2017 Page 2 of 4 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-3 1 Table 2 below presents a scenario for the forecast peak demand for 2019-2020 and 2020- 2 2021 winters that is consistent with load assumptions for 2020 and 2021 as per Table 3 in 3 the PPA Application, broken down by major classes. 4 5 Table 2. Forecasted hourly Peak demand for 2019-2020 and 2020-2021 winters 2019‐2020 Winter 2020‐2021 Winter CLASS [MW] [MW] NON‐INDUSTRIAL 90.89 92.92 INDUSTRIAL 11.73 12.29 TOTAL 102.62 105.21 6 7 (e) 8 9 YEC can provide comment on the potential dependable capacity by different generation 10 sources in the winters of 2020/21 and 2021/22. This analysis does not assess the single 11 contingency (N-1) dependable capacity with the loss of 37 MW at Aishihik. 12 13 Based on the 2016 Resource Plan and current information, Table 3 below provides the 14 maximum dependable capacity available to meet the peak demand in these future years 15 based on existing YEC resources and including the 3rd LNG engine and ATCO Electric 16 Yukon thermal capacity. As noted in the 2016 Resource Plan, a number of changes that 17 may affect this maximum dependable capacity are being assessed under YEC’s ongoing 18 resource planning, including development of additional thermal capacity (new thermal 19 plant of up to 20 MW), the potential energy storage project, uprates and/or refurbishments 20 to existing hydro facilities (e.g., assume work carried out in summer and not affect winter 21 capacity), and the planned retirement of FD1 and WD3 diesel units (8.5 MW) at the end 22 of 2020. December 11, 2017 Page 3 of 4 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-3 1 Table 3. Maximum dependable capacity by generation source: 2020/21 and 2 2021/22 MAXIMUM GENERATION DEPENDABLE CAPACITY SOURCE [MW] HYDRO 70.5 THERMAL NATURAL GAS 13.2 THERMAL DIESEL 35.7 TOTAL 119.4 3 December 11, 2017 Page 4 of 4 Yukon Energy Corporation Application for Approvals regarding the VGC Group Power Purchase Agreement JM-YEC-1-4 1 TOPIC: YEC-VGC PPA Application 2 3 REFERENCE: Page 6 Section 4.2 1: 4 5 PREAMBLE: 6 7 QUESTION: 8 9 a) The second paragraph contains a reference to Minto and Alexco paying rates 10 under Rate Schedule 42, should this read Rate Schedule 39? 11 12 ANSWER: 13 14 (a) 15 16 Correct.
Recommended publications
  • Yukon and Alaska Circle Tour Introduce Yourself to Northern Culture and History in Whitehorse, Then Relive Dawson City’S Gold Rush by Panning for Gold
    © Government of Yukon Yukon and Alaska Circle Tour Introduce yourself to northern culture and history in Whitehorse, then relive Dawson City’s gold rush by panning for gold. Learn about First Nations culture from Aboriginal people. Drive a highway at the roof of the world, paddle and raft remote rivers, hike, catch a summer festival or relax in hot springs under the Midnight Sun. Approx. distance = ALASKA 1 Whitehorse 9 Boundary 9 1073 mi (1728 km) 10 (Alaska) 8 YUKON 2 Braeburn 11-12 days 11 10 Chicken (Alaska) 3 Carmacks 12 7 11 4 Pelly Crossing Tok (Alaska) 5 6 4 12 Beaver Creek 5 Stewart Crossing 13 3 13 Destruction Bay 2 6 Mayo 14 NORTHWEST 14 Haines Junction 7 Keno 1 TERRITORIES Whitehorse 1 Whitehorse 8 Dawson City NUNAVUT Start: DAY 1-2 – Whitehorse Yukon International Storytelling Festival Northern Lights Tours Celebrate the North’s rich storytelling tradition under the Midnight Mid-August through April, experience brilliant displays of the Aurora Sun annually. Listen to performers from circumpolar countries and Borealis. Several tour operators offer excursions to see these beyond. In October. celestial night shows when multi-colored streamers of light shimmer overhead while you watch from a secluded log cabin or while MacBride Museum of Yukon History soaking in natural mineral waters at Takhini Hot Springs pools. Learn about the Klondike gold rush and the development of the Canadian north. Check out displays of First Nations traditions, the Muktuk Adventures legacy of Canadian poet Robert Service, and the Mounted Police Get to know sled dogs and puppies at a kennel and B&B.
    [Show full text]
  • CHON-FM Whitehorse and Its Transmitters – Licence Renewal
    Broadcasting Decision CRTC 2015-278 PDF version Reference: 2015-153 Ottawa, 23 June 2015 Northern Native Broadcasting, Yukon Whitehorse, Yukon and various locations in British Columbia, Northwest Territories and Yukon Application 2014-0868-3, received 29 August 2014 CHON-FM Whitehorse and its transmitters – Licence renewal The Commission renews the broadcasting licence for the Type B Native radio station CHON-FM Whitehorse and its transmitters from 1 September 2015 to 31 August 2021. This shortened licence term will allow for an earlier review of the licensee’s compliance with the regulatory requirements. Introduction 1. Northern Native Broadcasting, Yukon filed an application to renew the broadcasting licence for the Type B Native radio station CHON-FM Whitehorse and its transmitters CHCK-FM Carmacks, CHHJ-FM Haines Junction, CHOL-FM Old Crow, CHON-FM-2 Takhini River Subdivision, CHON-FM-3 Johnson’s Crossing, CHPE-FM Pelly Crossing, CHTE-FM Teslin, VF2024 Klukshu, VF2027 Watson Lake, VF2028 Mayo, VF2035 Ross River, VF2038 Upper Liard, VF2039 Carcross, VF2049 Dawson City, VF2125 Takhini River Subdivision, VF2126 Keno City, VF2127 Stewart Crossing, VF2128 Tagish, VF2147 Destruction Bay, VF2148 Whitehorse (Mayo Road Subdivision), VF2311 Lower Post and VF2414 Faro, Yukon; VF2306 Atlin and VF2353 Good Hope Lake, British Columbia; VF2354 Aklavik, and VF2498 Tsiigehtchic (Arctic Red River), Northwest Territories, which expires on 31 August 2015. The Commission did not receive any interventions regarding this application. Non-compliance 2. Section 9(2) of the Radio Regulations, 1986 (the Regulations) requires licensees to file an annual return by 30 November of each year for the broadcast year ending the previous 31 August.
    [Show full text]
  • Inventory to the Herta Richter Fonds Held at the Yukon Archives, March 2008
    Inventory to the HERTA RICHTER FONDS held at the Yukon Archives March 2008 Last updated: 2008-08-05 Inventory to the HERTA RICHTER FONDS Yukon Archives March 2008 Cover photographs: Yukon Archives: Herta Richter fonds, (collage of images of Herta Richter in various stages of her nursing career, clockwise from top left) Graduation 1955 (93/149 #1172), holding baby Herta Margaret (93/149 #1176), posed with a baby in a Peigan Indian decorated cradleboard, 1957 (93/149 #1174 ), relaxing on top of Crow Mountain in Old Crow, looking Southeast (93/149 # 697) and wearing a traditional parka “needed for her work” (93/149# 260). TABLE OF CONTENTS FONDS DESCRIPTION.............................................................................................................................. 1 SERIES DESCRIPTIONS........................................................................................................................... 3 SERIES 1: NURSING CAREER. —1950-1992 ........................................................................................ 3 SERIES 2: PERSONAL FILES. —1923, 1945-1987................................................................................. 7 SERIES 3: MISCELLANEOUS. —1961-1990 ......................................................................................... 9 SERIES 4: PHOTOGRAPHS. —1898, 1961-1993.................................................................................. 11 [Original Photographs] .....................................................................................................................
    [Show full text]
  • Yukon Energy State of Play Updated 24DEC18
    Yukon Energy State of Play Submitted to: Yukon Energy, Mines and Resources Energy Branch 206 Lowe Street Whitehorse, Yukon Y1A 1W5 Submitted by: Paul Kishchuk, MA 203 – 301 Hawkins Street Whitehorse, Yukon Y1A 1X5 www.vectorresearch.ca [email protected] 867.668.3164 6 February 2018 Updated 24 DecemBer 2018 Yukon Energy State of Play Table of Contents Introduction ........................................................................................................................................................................................................... 1 Yukon Energy Overview ........................................................................................................................................................................................ 1 Energy Balance of Trade ....................................................................................................................................................................................... 6 Energy Transportation Infrastructure ................................................................................................................................................................... 7 Yukon Energy Capacity ........................................................................................................................................................................................ 10 Yukon Energy Production ...................................................................................................................................................................................
    [Show full text]
  • YEC-1-1 REVISED the Proposed Mayo Hydro Enhancement Project (Mayo B)
    UTILITIES CONSUMERS’ GROUP (UCG) Application for an Energy Project Certificate and Yukon Energy Corporation an Energy Operation Certificate Regarding UCG-YEC-1-1 REVISED the Proposed Mayo Hydro Enhancement Project (Mayo B) 1 TOPIC: 2 3 REFERENCE: 4 5 Application, page 1 6 7 YEC indicates that “the planned in-service date for Mayo B of late 2011 reflects 8 requirements of Yukon Energy’s funding agreement with the federal government for 9 Mayo B and Stage 2 of the Carmacks-Stewart Transmission Project (CSTP) connecting 10 the Mayo-Dawson (MD) and Whitehorse-Aishihik-Faro (WAF) grids. The timing for Mayo 11 B also reflects the opportunity to displace diesel generation energy requirements 12 associated with growing power loads on both grids”. 13 14 QUESTION: 15 16 a) Please explain the requirements of the funding agreement with the Federal 17 government that are determining the construction schedule of this Yukon 18 infrastructure project. 19 20 b) What efforts have been taken to extend the funding agreement timeframes to 21 allow for a more complete and thorough review of this project? Please provide all 22 correspondence related to these efforts. 23 24 ANSWER: 25 26 (a) 27 28 Section 3 of the Federal Funding Agreement sets out the obligations of the parties; 29 section 3.1 notes the contribution to be paid by Canada is subject to the Terms and 30 Conditions of the agreement, including Schedule B. Section 3.1(a) states that Canada 31 will not pay more than 50% of the Eligible Costs (up to $71 million) during the three 32 Fiscal Years starting in 2009-2010 and ending in 2011-2012.
    [Show full text]
  • 2019 Annual Report
    2019 annual report Our Whitehorse Rapids Generation Station – Archbould.com ii table of contents Who we are ............................................................ 2 Mission .............................................................. 2 Values ............................................................... 2 Vision ................................................................. 2 Message to Yukoners ............................................ 4 President’s Welcome ............................................. 6 2019 At a Glance ................................................... 8 2019–2024 Strategic Priorities and Performance .................................................10 2019 Corporate Goals and Performance ...........12 Health, Safety and Environment ..........................14 Customers, Community and Partnerships ..........16 Management Discussion and Analysis .............22 Financial Statements ............................................28 1 who we are Established in 1987, Yukon Energy is a publicly owned electrical utility that operates as a business, at arms-length from the Yukon government. We are the main generator and transmitter of electrical energy in Yukon. We work with our parent company, Yukon Development Corporation, to provide Yukoners with sustainable, cost-effective and reliable electricity. There are over 21,000 electricity consumers in the territory. Yukon Energy directly serves over 2,200 of these customers, most of whom live in and around Mission Dawson City, Mayo and Faro. Indirectly, we provide
    [Show full text]
  • August 28Th, 2018 1
    AUGUST 28TH, 2018 1. INTRODUCTION On June 20th and June 21st, an important gathering took place in the Yukon. For the 127-year-old Canadian Electricity Association (CEA), it was the first Board of Directors meeting in Canada’s North. The meeting also came at an important juncture in Canadian history—one defined by the pursuit of reconciliation with Indigenous peoples and prosperity for all Canadians. On the first day, CEA, together with two of our member companies that operate in the North — Yukon Energy and ATCO — hosted a symposium addressing the energy needs of the North, in Carcross, on the traditional territory of the peoples of Carcross / Tagish First Nation. Despite this backdrop of promise and commitment, Canada’s remote and northern communities suffer from a significant level of “energy inequality”, where the cost of electricity in many communities is estimated to be over ten times higher than the Canadian average. This lack of access to affordable power has limited their economic potential and stifled the region’s economic development and prosperity. It also impacts their social fabric. Yet, within the challenge of addressing this inequality lies the opportunity for industry, Indigenous peoples, communities, and all levels of government to work in partnership to invest in clean energy, spur economic development, address environmental challenges, and power tomorrow’s low-carbon economy. That is why CEA brought leaders from industry, governments, Indigenous organizations, academia and other community leaders to Carcross for a symposium entitled, “Powering the Future: Partnering in Energy Development”, to discuss the unique challenges and opportunities that exist in Canada’s North and how we can all work together to build a cleaner, more prosperous future for all.
    [Show full text]
  • ·. Yukon·2000 , ·
    .·. YUKON·2000 , · ~Table of Contents FOREWORD .................................. 2 BACKGROUND ................................ 4 DEFINITIONS .................................. 6 PROCESS .................................... 8 OBJECTIVES .................................. 9 COMPONENTS . 10 PRINCIPLES ................................. 12 ORGANIZATIONAL STRUCTURE ................. 14 PROGRAMS .................... ............. 15 INFORMATION ............................... 20 Like other Canadians, Yukoners need to keep in touch with each ot her, with the rest of Canada and with the world. The provision of high quality and affordable communications links within the Yukon and between the Yukon and other reg ions is essential if we are to survive in an information-based society. The Government has responded to Yukoners demands for better communi­ cations services by developing a communications policy specifically tailored to the needs of the territory. We have a rather special situation here in the Yukon where great distances exist between sparsely populated areas making distance com­ munications one of our greatest chall enges. We have therefore made accessibility, reliability and affordability the by-words of our policy. We heard from many Yukoners throughout the policy development process. The results clearly indicate that Yukoners want their government to play a more active ro le in communications matters. A major overriding concern is the need for a strong, effective voice in federal communications policy-making and regulatory forums. This is not surprising when you realize that it is these forums that decide the costs for and level of communications services in the Yukon. Another major concern was the inequity in service levels throughout the ter­ ritory, particularly in respect to the CBC television and radio signals. Under the new policy, the Government will replace the mountaintop rebroadcast television trans­ lator equipment with satellite receive antenna.
    [Show full text]
  • Leading Edge Projects
    John Maissan 219 Falcon Drive, Whitehorse Yukon, Y1A 0A2 Phone: (867) 668-7774 Email: [email protected] IN THE MATTER OF YUKON ENERGY CORPORATION – VICTORIA GOLD CORPORATION GROUP POWER PURCHASE AGREEMENT Before the YUKON UTILITIES BOARD November - December, 2017 REPLY ARGUMENT OF JOHN MAISSAN Reply Argument introductory comments In this written reply argument, the Yukon Utilities Board is referred to as the “Board”, Yukon Energy Corporation as Yukon Energy, and Victoria Gold Corporation Group as VGC. Interrogatory responses (IR) will be referenced by their identifying numbers. In this reply argument I address issues discussed in the Utilities Consumers Group (UCG) and Yukon Energy final arguments which I feel need some additional comment. My silence on issues not addresses is not to be interpreted as agreement with, or disagreement with, the stated positions. I leave these matters to the Board to address based on all the information on the record. I remain of the view that it is appropriate for Yukon Energy to be providing power service to VGC through the YIS. UCG Final Argument matters 1. No Cost of Service (COS) study UCG notes in some detail the concerns that it has with the absence of a Board accepted COS study. This should be of concern to all parties including the Board. I would like to see the Board take whatever steps it considers necessary to rectify this situation as it affects not just this PPA but also other Yukon Energy and ATCO Electric Yukon matters that come before the Board. 2. Potential cost impacts on other ratepayers UCG contends that there are risks and costs that potentially affect all ratepayers that have not been fully or properly quantified by Yukon Energy.
    [Show full text]
  • Yukon Energy Corporation Independent Power Producers
    Yukon Energy Corporation Independent Power Producers Interconnection Technical Guide Revision: 04b Release Date: 2019 01 24 Disclaimer This report was prepared under the supervision of Teshmont Consultants LP (“Teshmont”), whose responsibility is limited to the scope of work as shown herein. Teshmont disclaims responsibility for the work of others incorporated or referenced herein. Revision History Revision Number Date Released Prepared by Reviewed by Comments Robyn Tarrant, PEng David King, PEng 00 May 14, 2018 First Draft Dwayne Aming, PEng Robert Baker, PEng Robyn Tarrant, PEng 01 May 30, 2018 David King, PEng Second Draft Dwayne Aming, PEng Robyn Tarrant, PEng Third Draft. Incorporated 02 June 5, 2018 David King, PEng Dwayne Aming, PEng YEC Comments. Robyn Tarrant, PEng Fourth Draft. Incorporated 03 June 18, 2018 David King, PEng Dwayne Aming, PEng YEC Comments. Robyn Tarrant, PEng Fifth Draft. Incorporated 04 September 17, 2018 David King, PEng Dwayne Aming, PEng YEC Comments. i Independent Power Producers Interconnection Technical Guide | 2019 01 Contents Executive Summary ....................................................................................................................................... 6 1. Introduction and Scope ......................................................................................................................... 7 1.1. Purpose ........................................................................................................................................... 7 1.2. Limitations .....................................................................................................................................
    [Show full text]
  • Presentation-Yecpresentation E.Pdf
    Good morning, Chairman Neufeld and committee members. Thank you for the invitation to present to you on Yukon Energy’s business and the issues facing us. I will refer you to the slide presentation which I believe you have a copy of. I am now turning to slide 2. 1 I’ll address three general topics in my presentation: 1. Firstly. I’ll provide an overview of Yukon Energy, our asset profile, our recent project history, and our current status. 2. Next, I’ll discuss the options that we are focusing on for new supplies of energy 3. And finally, I’ll touch on some of the challenges that we face. After my formal remarks, I’ll be happy to take any questions that you have. Moving now to slide 3. 2 Yukon Energy is one of two regulated utilities in the Yukon. We are responsible for the majority of electricity generation in the Territory, including 3 hydro facilities and a fleet of back‐up diesel generators. We also own and operate the majority of the electrical grid in the Territory. We distribute electricity to residential and commercial customers in a few of the grid‐connected communities outside of Whitehorse, including Dawson City, Mayo and Faro. We do not serve any remote off‐grid communities. ATCO Electric Yukon is the other regulated utility in the Yukon –they distribute power to residential and commercial customers here in Whitehorse, and they also provide power to a number of off‐grid communities, including Burwash Landing, Destruction Bay, Beaver Creek, Old Crow and Watson Lake.
    [Show full text]
  • Yukon Heritage Attractions
    GUIDEBOOK Yukon Heritage Attractions 2017 EDITION Welcome. The heritage attractions listed here reveal the inside stories that represent the difference between simply seeing and truly knowing your destination. They include museums, cultural centres and other places that bring to life the territory’s rich and diverse heritage. Most of these attractions are part of the Government of Yukon Gold Explorer’s Passport Program. This annual contest begins June 1 and ends August 31. Collect stamps and numbers at all participating sites listed inside the Explorer’s Passport for a chance to win a prize of Klondike placer gold. Passports are available at Visitor Information Centres and participating heritage attractions. Attractions and communities are listed in alphabetical order within each region. Unless otherwise indicated, all facilities are wheelchair accessible. Many facilities offer pull-through parking; please phone for more information. Many of the attractions listed here offer discounts for groups, seniors or children, and are available for rent for functions and events. Please contact the facility directly for more information. For more information about any of the places listed here, and to discover additional attractions, please visit heritageyukon.ca, go to your local Visitor Information Centre or call Tourism Yukon at 1-800-661-0494. Unless otherwise noted, all photos courtesy Government of Yukon. Abbreviations ph phone f fax e e-mail fb Facebook in Instagram tw Twitter w website m mailing address Front cover: Clan poles in front of the Teslin Tlingit Heritage Centre. Background, inside cover: The Whitehorse riverfront. Back cover, top: Andrew Cruikshank and Claude Tidd, members of the Dawson City Orchestra, 1926.
    [Show full text]