PUTNAM COUNTY Public Works Department Projects For Additional Information Call Public Works at PH 386-329-0346 ROADWAY IMPROVEMENT PROJECTS

ESTIMATED Funding/Designer/C ESTIMATED START COMPLETION ontractor LOCATION PROJECT DESCRIPTION CURRENT STATUS OF CONSTRUCTION DATE CR 216 From SR 100 to US 17, FDOT CIGP Addendum to Five Points Desgin Contract TBD TBD project. in process of currently being generated. FDOT -TRIP/TBD/TBD Meeting to be conducted with GP to finalize scope on 11/18/15. Pomona Park SCOP Roads Feagle Ave (Resurface), Keown Grant app submitted 8/17/2015. Still TBD TBD (Resurface), Lake Street (Resurface), May waiting for offical determination from SCOP Requested Street (Dirt to Pave) FDOT. Moody Rd/St. Johns Re- Intersection to be modified such that In the process of receiving cost proposals TBD TBD Alignmnet Moody Rd traverses in a straight alignmnet from design consultant to present to TBD/CHW/TBD BOCC. Moody Road Road resurfacing and turn lane with Eminent domain for Spells property TBD TBD TBD/PCPW/TBD sidewalk to SR 20 approved by BOCC 10/13/2015. Forest Roads to Fort Gates Dirt to pave from SR 19 to Ft Gates Ferry Will be going out with RFP to hire April-17 January-18 Ferry and Mt Royal Avenue to Ft Gates Ferry consultant to design the improvments. FDOT-SCOP/Stone Estimated start dates and completion dates Engineering /TBD may be impacted. Holloway Road Dirt to pave from SR 100 to Tinsley Road Design contract awarded to Civil Nov-16 December-17 FDOT- SCOP/CSI Ali Construction Services Inc. 30% design Najafi/TBD drawings due next week. 2016 Dirt to Pave - PCPW Filmore to Azaela In house survey completed. In house TBD TBD Design design to be completed by early January. BPP/TBD/TBD

2016 Dirt to Pave - Design St Johns Riverside Estates - Paradise Pt, Mittauer design to be complete Early TBD TBD Contracted to Mittauer Paradise Circle, Fisherman Rd, Creekside January 2016 BPP/Mittauer/TBD Rd, Edgewater Rd Louis Broer Extension Terminate East River Rd @ Putnam Revising the plans to include a stormwater TBD TBD County Rd and add parking lot. Modify best management practice for the parking culvert and ditch adjacent to Putnam area or a compensating area for submission PCPW/PCPW/PCPW County Blvd. Extend W Louis Broer Rd to to FDOT for approval. Putnam County Blvd. 2015 Dirt To Pave Roads Roads to be paved. Contract has been executed with NFE. January-16 August-16 BPP/PCPW/NFE 2015 Resurfacing Project Roads to be resurfaced. Contract has been executed with Art November-15 February-16 BPP/PCPW/Walker & Walke and Whitehurst. Whitehurst East Pinellas Road The road is to be paved from SR 19 to Corrections in the punchlist that have been Underway December-15 BPP & Impact Fees/Jones Stokes Landing Road generated are being process. Edmonds/Coleman

Page 1 of 5 November TC Meeting PUTNAM COUNTY Public Works Department Projects For Additional Information Call Public Works at PH 386-329-0346 CR 209 Roadway The resurfacing will improve roadway Construction is underway. 90% complete. - Underway December-15 Resurfacing pavement from Palmetto Bluff Rd to US Contract Extended for Railing - Currently FDOT - SCOP/Infrastructure 17 working on railing and FDOT puchlist Engineering/Halifax

Dunns Creek - FDEP Project Dirt to Pave of existing trail Presently triple chip sealing approved August-15 December-15 DEP -FDOT LAP Agreement- portions of road bed. /PCPW/North Emulsions- Jeff King 2014 Dirt to Pave Roads Punch List Phase. Corrective work in Progress for west Underway December-15 BPP/PCPW/NFE Hillsborough

WATER AND WASTEWATER UTILITIES PROJECTS

ESTIMATED Funding/Designer/C ESTIMATED START COMPLETION ontractor LOCATION PROJECT DESCRIPTION CURRENT STATUS OF CONSTRUCTION DATE East Palatka - Gilbert Road New Wastewater Treatment Plant for East Phase I - Anticipated to be on-line Underway November-15 Palatka and San Mateo area approximately mid November. PCI & Jones Edmunds Public Works compound anticipated completion in mid December. US 17 in East Palatka Relocation of the Waterline Notice to Proceed was issued by FDOT to August-15 February-16 relocate existing water facilities on Jones Edmunds 4/16/2015.

STORMWATER IMPROVEMENT PROJECTS Page 2 of 5 November TC Meeting PUTNAM COUNTY Public Works Department Projects For Additional Information Call Public Works at PH 386-329-0346

ESTIMATED ESTIMATED START COMPLETION Funding/Designer/C LOCATION PROJECT DESCRIPTION CURRENT STATUS OF CONSTRUCTION DATE ontractor Front Street in Welaka The project is to improve the cross culvert Addendum 2 for Stone Engineering to TBD TBD HMGP- FEMA /Stone and reduce flooding (HGMP) provide CM services to be on the BOCC engineering - Paul Ina/TBD Agenda 11/24/15. Towles Road Outfall The project is to improve drainage in the Phase 1 study completed and processing TBD TBD surrounding areas. (HGMP) Phase 1 the designers final payment. FEMA HGMP - FEMA/King drainage analysis and studies for North of currently reviewing Phase 2 plans for Engineering/TBD Eddire Vreen on Old Jacksonville hwy approval. south to Towles Rd. Browns Landing/Macon Rd HGMP reopended to address Lori Malhoit Currently 36k in contingency money from Pending FDEM Approval TBD HMGP- FEMA/Stone drainage issue. (HGMP) the initial HGMP. Have reopened it and engineering - Paul Ina/TBD submitted design for approval. Dog Branch Creek Cleaning Dog Branch Creek Ayres contract executed by BOCC on TBD TBD TBD/TBD/TBD 11/17/15. CR 309C Road Ditch Piping The project is to repair damage and Project is currently at 50% complete. Underway December-15 HMGP FEMA/Five Points Project provide future road ditch erosion Design Group- Nancy protection. (HGMP) Buchannon/CIC

MULTI-USE TRAIL AND SIDEWALK PROJECTS

Page 3 of 5 November TC Meeting PUTNAM COUNTY Public Works Department Projects For Additional Information Call Public Works at PH 386-329-0346 ESTIMATED Funding/Designer/C ESTIMATED START COMPLETION ontractor LOCATION PROJECT DESCRIPTION CURRENT STATUS OF CONSTRUCTION DATE Sun Avenue Sidewalk The project to install sidewalk from Sun This project was to be completed in Pending FDOT Approval December-21 Avenue on SR 20 through Interlachen phases. Funding for FY-2020 construction Lake Estates to CR 315 has been withdrawn by FDOT due to reduction in available funds. A new application under the Transportation PCPW/NA/PCPW Alternatives Program will be submitted for consideration for funding in FY-2021. - PCPW US 17 to SJRWMD Office Palatka Multi-Use Trail along SR 100 with The right-of-way acquisition is scheduled Pending FDOT Action December-20 Segment 1 a crossing of SR 19 to begin this year. Possible construction FDOT - LAP/Ayres/TBD could begin in 2019. - FDOT

Main Street Multi-Use Trail Crescent City Multi Use Trail (FDOT) 100% Phase 1V plans submitted 9/18/15 to Jan-16 July-16 LAP Agreement CC/CSI Ali FDOT. Funding not avaialable to start. Najafi/TBD

FERRY PROJECTS

ESTIMATED Funding/Designer/C ESTIMATED START COMPLETION ontractor LOCATION PROJECT DESCRIPTION CURRENT STATUS OF CONSTRUCTION DATE Fort Gates Ferry Landing Build new ferry landing facilities and Taaylor Engineering is proceeding forward TBD TBD FDOT/Taylor replace old structures with the design. Engineering/TBD Ferry Build new ferry landing facilities and Project taken over by FDOT due to FDOT TBD TBD Landing replace old structures and upgrade ferry acquiring additional funds. NA

OTHER CURRENT PUBLIC WORKS PROJECTS

Page 4 of 5 November TC Meeting PUTNAM COUNTY Public Works Department Projects For Additional Information Call Public Works at PH 386-329-0346

ESTIMATED Funding/Designer/C ESTIMATED START COMPLETION ontractor LOCATION PROJECT DESCRIPTION CURRENT STATUS OF CONSTRUCTION DATE West Bannerville Rd Repair and mediate road washout and road Have recevied the proposal to fix the road TBD TBD bed damage reulting from multiple springs to FDOT standards and the total came to in road bed. Extend culvert over creek for $1.3M. Value Engineered option has been roadway and widen roadway such that received and totaled $334k. PCPW TBD/TBD/TBD drainage can effectively occur without Engineering performing further review to damaging roadway. reduce costs.

Dunn & Riverside Repair and Mediate road washout at Currently acquiring a drainage easement to TBD TBD BPP/PCPW/TBD intersection of Dunn and Riverside relocate cross culvert. Intersection of East Peniel & Install additional barricades for resident to 8/17/2015 observations have been made. Underway TBD Stokes Landing mitigate potential accident from oncming Transportation has been directed to place traffic on Stokes Landing. Regrade and barricades at locations referenced and if adjust culverts to promote drainage for not advise why not. Further analysis is PCPW/PCPW/PCPW resident on right hand side of intersection being conducted to address drainage. approaching Stokes Landing.

Moody Road Cross Culvert The project is to install new cross culverts The major work is complete. Headwall Underway TBD Failure Replacements needs to be installed. PCPW/PCPW/PCPW

Brick Road Repairs Turner Road and other East Palatka brick Work is expected to begin on Turner Road TBD TBD PCPW/PCPW/PCPW roads in the fourth quarter of 2015.

Page 5 of 5 November TC Meeting