Environmental Clearance for Proposed “Engracia” at Pimple Gurav,

APPLICATION FOR ENVIRONMENTAL

CLEARANCE

For

“ENGRACIA”

At S.No.24 (P), Plot no. 2, CTS no. 625(P), Pimple Gurav,

Dist.: Pune,

Project Proponent

M/s Jagtap Patil Promoters & Builders

Submitted by-

SGM Corporate Consultants Pvt. Ltd.

QCI –NABET Accredited

1

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

APPENDIX – I FORM – 1 (I) Basic Information: Sr. No. Item Details 1. Name of the Project/s “Engracia” 2. S. No. in the Schedule 8 (a) 3. Proposed capacity/area/length/tonnage to Plot Area : 6300.99 m2 be handles/command area/lease FSI Area – 10075.99 m2 area/number of wells to be drilled Non FSI Area – 14601.41 m2 Total construction area: 24677.40 m2 4. New/Expansion/Modernization New 5. Existing Capacity/Area etc. NA 6. Category of Project i.e. ‘A’or ‘B’ Category ‘B’ 7. Does it attract the general condition? If Not Applicable yes, please specify 8. Does it attract the specific condition? If Not Applicable yes, please specify 9. Location Plot/Survey/Khasra No. S.No. 24(P), Plot no. 2, CTS no. 625 (P) Village Pimple Gurav Tehsil Haveli District Pune State Maharashtra 10. Nearest railway station/airport with Nearest Railway station: Pune – distance in kms. railway station- 3.3 km Nearest Airport: - 14.3 km 11. Nearest Town, city, District Headquarters City : Pune –11.0 km along with distance in kms. District: Pune 12. Village Panchayat, Zilla Parishad, Municipal Corporation Municipal Corporation, Local body (PCMC) (complete postal addresses with telephone nos. to be given) 13. Name of the applicant Mr.Shankar Pandurang Jagtap 14. Registered Address S.no. 24(P), Plot no. 2, CTS no. 625 (P), Pimple Gurav, Tal. Haveli, Dist. Pune. 15. Address for Correspondence S.no. 24(P), Plot no. 2, CTS no. 625 (P), Pimple Gurav, Tal. Haveli, Dist. Pune. Name Mr.Shankar Pandurang Jagtap Designation (Owner/Partner/CEO) Owner Address S.no. 24(P), Plot no. 2, CTS no. 625 (P), Pimple Gurav, Tal. Haveli, Dist. Pune. Pin Code 411061 Telephone no. -- Fax No. -- 16. Details of Alternative sites examined if any Not Applicable location of these sites should be shown on a toposheet

2

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. No. Item Details 17. Interlinked Projects Not Applicable 18. Whether separate application of interlinked Not Applicable project has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. Not Applicable a. The Forest (Conservation) Act, 1980? b. The Wildlife (Protection) Act, 1972? c. The C.R.Z Notification, 1991? 22. Whether there is any Government Not Applicable order/Policy relevant/relating to the site? 23. Forest land involved (hectares) Not Applicable 24. Whether there is any litigation pending Not Applicable against the project and /or land in which the project is propose to be set up? Name of the court Case No. Orders/directions of the court, if any and its relevance with the proposed project.

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ No confirmation rates, wherever possible) with source of information data 1.1 Permanent or temporary change Yes The developer has proposed construction is in in land use, land cover or conformity with the DC rule. topography including increase in intensity of land use (with respect to local land use plan) 1.2 Clearance of existing Yes Land: The plot is a having gentle slope. Land, vegetation and building? Vegetation: No Existing Trees. 1.3 Creation of new land uses? Yes Proposed construction is in conformity with the development permission from PCMC. 1.4 Pre-construction investigation Yes The pre-construction investigation is done. e.g. borehole, soil testing? 1.5 Construction works Yes The proposed construction project is consisting of construction of 3 no. of Residential Building. However developer has constructed (FSI + Non FSI) : 16634.1 m2

1.6 Demolition work Yes There is no any demolition of work.

3

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ No confirmation rates, wherever possible) with source of information data 1.7 Temporary sites used for Yes There will be temporary housing facility for the construction works or housing of construction workers and temporary sheds will be construction workers? used for storage of the construction goods or materials. 1.8 Above ground buildings, Yes The proposed construction project is consisting of structures or earthworks construction of 3 nos. of residential buildings. including linear structures, cut Sr.No. Building name No. of floors and fill or excavations 1 Bldg A 2P+11 2 Bldg B 2P+11 3 Bldg C 2P+11 4 Club house G+1

Earthwork will include excavation for creation of foundation. The approximate quantity of earthwork will be approx. 2140.5 cum 1.9 Underground works including No Not Applicable mining or tunneling? 1.10 Reclamation works? No Not Applicable 1.11 Dredging? No Not Applicable 1.12 Offshore structures? No Not Applicable 1.13 Production and manufacturing No Not Applicable processes? 1.14 Facilities for storage of goods or Yes Temporary sheds will be constructed for storage materials? of construction materials 1.15 Facilities for treatment or Yes Construction Phase: disposal of solid waste or liquid Temporary sanitation facility will be provided for effluents? construction workers by regular toilets with septic tank.

Operation Phase: The site will have sewage treatment plant (STP) for treatment & treated water will be reuse. The organic waste to be treated by mechanical- composting on site and inorganic waste will be disposed to municipal solid waste management system. Please refer Annexure – II for Solid Waste Management  Wastewater will be treated in Sewage Treatment Plant with MBBR technology  Treated water will reused for flushing & gardening. Please refer Annexure III for Water Supply and Wastewater Management . 1.16 Facilities for long term housing of No Not Applicable operational workers?

4

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ No confirmation rates, wherever possible) with source of information data 1.17 New road, rail or sea traffic Yes Construction Phase during construction or There will be temporary increase in traffic due to operation? transport of construction material. Operation Phase There will be minor increase due to residents /visitors commuting to the commercial areas from outside. 1.18 New road, rail, air waterborne or Yes Internal roads will be constructed as a part of the other transport infrastructure project plan. including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No Not Applicable transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission No Not Applicable lines or pipelines? 1.21 Impoundment, damming, No Not Applicable culverting, realignment or other changes to the hydrology of watercourses or aquifers? 1.22 Stream crossing? No Not Applicable 1.23 Abstraction or transfers of water No Not Applicable from ground or surface waters? 1.24 Changes in water bodies or the No Not Applicable land surface affecting drainage or run-off? 1.25 Transport of personnel or Yes Construction Phase: materials for construction, Construction materials will be transported to the operation or decommissioning? site. Transport of workers employed for construction. Operation Phase: The persons in residential and commercial areas during operation phase will use public transportation facilities & their own vehicles. 1.26 Long-term dismantling or No Not Applicable decommissioning or restoration works? 1.27 Ongoing activity during No Not Applicable decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in Yes Construction phase: either temporarily or Temporary and minor influx of construction permanently? labour due to employment opportunities generated during construction phase.

5

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ No confirmation rates, wherever possible) with source of information data Operation Phase: This is a proposed construction project. There will be a permanent influx of the people. 1.29 Introduction of alien species? No Not Applicable 1.30 Loss of native species or genetic No Not Applicable diversity? 1.31 Any other actions? No Not Applicable

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply):

Sr. Information/checklist Yes/ Details thereof (with approximate quantities/ rates, No. confirmation No wherever possible) with source of information data 2.1 Land especially undeveloped Yes The developer has obtained NA permission. or agricultural land (ha) 2.2 Water (expected source & Yes Construction phase: competing users) unit: KLD Source: Tanker water

Requirement: Total = 50 m 3/day

Operation phase: Source: Tanker water for drinking and domestic use and recycled water from STP for flushing, gardening purpose.

Total Water Requirement = 144 m3/day (Fresh Water: 95 m3/day and Recycled Water: 49 m3/day) Please refer Annexure III for Water Supply and Wastewater Management . 2.3 Minerals (MT) Yes The proposal pertains to the construction activity only. Raw materials like cement, sand segregate, gypsum will be used during construction. 2.4 Construction material – Yes Raw material requirement for construction: stone, aggregates, sand / soil Raw Material Requirement (expected source – MT) Material Unit Quantity Cement Ton 18936.00 Steel Ton 3369.00 Metal Cu. M 21127.00 Sand Cu. M 56337.00 Bricks Nos 5676.61 Stone Brass -- Material shall be procured from local dealers. 2.5 Forests and timber (source – No Not Applicable MT)

6

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information/checklist Yes/ Details thereof (with approximate quantities/ rates, No. confirmation No wherever possible) with source of information data 2.6 Energy including electricity Source: - MSEDCL and fuels (source, competing  Construction Phase: 75 KW users) Unit: fuel (MT),  Operation phase- Yes energy (MW) Connected load-847 KW  D. G. Sets: 125 KVA

2.7 Any other natural resources No Not Applicable (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sr. Information/Checklist Yes/ Details thereof (with approximate quantities/ rates, No. confirmation No wherever possible) with source of information data

3.1 Use of substances or materials, No Not Applicable which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of No Not Applicable disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people Yes Living Conditions of local people are expected to e.g. by changing living improve. conditions? 3.4 Vulnerable groups of people No Not Applicable who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No Not Applicable

4. Production of solid wastes during Construction or Operation or Decommissioning (MT/month)

Sr. Information/Checklist Yes/ Details thereof (with approximate quantities/ rates, No. confirmation No wherever possible) with source of information data 4.1 Spoil, overburden or mine No Not Applicable wastes 4.2 Municipal waste (domestic and Yes Construction Phase : or commercial wastes) Approximately 0.5 - 0.75 MT/day debris will be generated during construction. Excavation quantity = approx. 20,226 cum Operation Phase: Municipal Solid waste = 483 kg/day

7

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information/Checklist Yes/ Details thereof (with approximate quantities/ rates, No. confirmation No wherever possible) with source of information data Biodegradable: = 290 kg/day Non-biodegradable: = 193 kg/day Please refer Annexure – II for Solid Waste Management. 4.3 Hazardous wastes (as per No NA Hazardous Waste Management Rules) Other industrial process No Not Applicable 4.4 wastes 4.5 Surplus product No Not Applicable Yes Operation Phase: Sewage sludge or other sludge 4.6 About 10 kg of sludge will be generated during from effluent treatment operation phase. 4.7 Construction or demolition Yes Construction Phase: wastes Approximately 0.5 - 0.75 MT/day debris will be generated during construction phase. Excavation quantity = approx. 2140.5 cum Redundant machinery or No Not Applicable 4.8 equipment Contaminated soils or other No Not Applicable 4.9 materials 4.10 Agricultural wastes Yes Organic wastes generated will be treated in the proposed on-site Organic Waste Converter & the compost from the same will be reused on site.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

Sr. Information/Checklist Details thereof (with approximate quantities/ Yes/ No. confirmation rates, wherever possible) with source of No information data 5.1 Emissions from combustion of Yes Vehicular pollution during construction and fossil fuels from stationary or operation phase. Use of DG sets as emergency mobile sources power back-up will add to slight emission of air pollutants. 5.2 Emissions from production No Not applicable. processes 5.3 Emissions from materials Yes During the construction phase, there will be some handling including storage or dust generation due to handling of raw material and transport movement of vehicles carrying raw material. 5.4 Emissions from construction Yes There will be minor emissions from construction activities including plant and equipment & dust generation during construction equipment activity & raw material handling 5.5 Dust or odors from handling of Yes During the construction phase, there will be some materials including dust generation due to handling of raw material and construction materials, sewage movement of vehicles carrying raw material. and waste

8

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information/Checklist Details thereof (with approximate quantities/ Yes/ No. confirmation rates, wherever possible) with source of No information data 5.6 Emissions from incineration No Not applicable. of waste 5.7 Emissions from burning of No Not applicable. waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No Not applicable. sources 6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Details thereof (with approximate Sr. Information / Checklist Yes / quantities/rates, wherever possible) with source No. confirmation No of information data 6.1 From operation of equipment Yes Construction phase: e.g. engines, ventilation plant, Minor increase in noise is anticipated due to the crushers ongoing construction activity, construction equipments / machines and vehicles carrying construction materials. The construction activity will be restricted to day time only. Operation phase: Noise will be generated due to DG set (only in case of power failures) and vehicular traffic From industrial or similar No Not applicable. 6.2 processes 6.3 From construction or Yes Noise will be generated from the construction demolition activity. 6.4 From blasting or piling No Not applicable. 6.5 From construction or Yes Construction phase: operational traffic Noise will be generated due to transport of trucks carrying the raw material/debris. Operation phase: During operation phase, traffic noise will be generated due to vehicles. However; adequate measures will be taken to curb the noise pollution at the site. 6.6 From lighting or cooling No Noise and vibrations generated by lighting or systems cooling systems will be controlled and eliminated by adopting appropriate measures and acoustic treatment. 6.7 From any other sources No D.G. set will be enclosed in acoustic enclosures as prescribed by CPCB to mitigate noise while in operation phase during power failure.

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

9

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Details thereof (with approximate Sr. Information / Checklist Yes / quantities/rates, wherever possible) with source No. confirmation No of information data 7.1 From handling, storage, use No Not applicable. or spillage of hazardous materials 7.2 From discharge of sewage or No Construction Phase: The regular toilets will be other effluents to water or the constructed by using septic tank system for land (expected mode and place wastewater treatment and disposal. of discharge) Operation Phase: Wastewater will be treated in Sewage Treatment Plant. Treated water will reuse for flushing & gardening purpose. Please Refer Annexure – III for Water Supply and Wastewater Management . 7.3 By deposition of pollutants No Not applicable. emitted to air into Dust particles generated during construction will be the land or into water settled continuously by spraying water. STP will be provided for wastewater treatment. 7.4 From any other sources No Not applicable. 7.5 Is there a risk of long term build No Not applicable. up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment:

Details thereof (with approximate Sr. Information/Checklist Yes / quantities/rates, wherever possible) with No. confirmation No source of information data 8.1 From explosions, spillages, No Not applicable. fires etc from storage, handling, use or production of hazardous substances 8.2 From any other causes No Not applicable. 8.3 Could the project be affected No N. A. by natural disasters causing Pune lies in Seismic Zone - IV and the design environmental damage (e.g. and construction will be done as per Indian floods, earthquakes, landslides, Standards for Zone-IV Seismic category. cloudburst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned a activities in the locality:

Sr. Information / Checklist confirmation Yes Details thereof (with approximate No. / No quantities / rates, wherever possible) with source of information data

10

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

Sr. Information / Checklist confirmation Yes Details thereof (with approximate No. / No quantities / rates, wherever possible) with source of information data 9.1 Lead to development of supporting. Yes New Proposal facilities, ancillary development or The proposed construction project is development stimulated by the project consisting of construction of residential which could have impact on the building. environment e.g.: - Supporting infrastructure (roads, Infrastructure proposed includes: power supply, waste or waste water  STP for treatment and recycling of treatment, etc.) waste water generated on site. - Housing development  Organic waste generated will be - Extractive industries treated in Organic waste Convertor - Supply industries unit on site. - Other  Rain Water Harvesting  Adequate parking space  Common amenity areas etc. 9.2 Lead to after-use of the site, which could No Not Applicable. have an impact on the environment 9.3 Set a precedent for later developments No Not Applicable. 9.4 Have cumulative effects due to No Not Applicable. proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity: Sr. Areas Name / Aerial distance (within 15 No. Identity km.) Proposed project location boundary 1 Areas protected under international None Not Applicable conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for None Not Applicable ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, important or None Not Applicable sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or underground None Not Applicable waters 5 State/ National boundaries None Not Applicable 6 Routes or facilities used by the public for None Not Applicable access to recreation or other tourist, pilgrim areas 7 Defense installations No Not Applicable 8 Densely populated or built-up area No The proposed project is located at outskirt of Pune.

11

Environmental Clearance for Proposed “Engracia” at Pimple Gurav, Pune

9 Areas occupied by sensitive man-made land No Not Applicable uses (hospitals, schools, places of worship, community facilities) 10 Areas containing important, high quality or No Not Applicable scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or None Not Applicable environmental damage. (Those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which No Pune lies in Seismic Zone - IV could cause the project to present and the design and construction environmental problems (earthquakes, will be done as per Indian subsidence, landslides, erosion, flooding or Standards for Zone-IV Seismic extreme or adverse climatic conditions) category.

I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

12