Major Projects: Work Programme 2020/21 Project Summary Current

Total Page:16

File Type:pdf, Size:1020Kb

Major Projects: Work Programme 2020/21 Project Summary Current Major Projects: Work Programme 2020/21 Project Summary Current Position Key Risks Prog completio Master Programme Status Report Initial baseline programme developed, going on to track and report and develop dashboard. n/a Programme Impact on Economy Overall, direct jobs 648 & 15 apprentices. Indirect impact could reach 4930 jobs & 51 apprentices. n/a CAPITAL PROJECTS Public Realm - £1.85m Re-paving Brook Street footway works continue with the Prospect Centre frontage on Prospect Street well advanced, works Delay to works in term of productivity incurring a claim for 2020 will start on the south of this area linking the new paving to the pedestrianised area of King Edwards Street. Works time and costs although this is being managed within the to the Maritime Steps are complete. project team and through the contract. Stoneferry Road Improvement corridor - £7m Construction continues. Phase 4 has commenced with works on the footways. Northern Power Grid are Time delays and cost inflation due to covid on both 2021 undertaking diversion works on Holwell Road and Chamberlain Road. Yorkshire Water are undertaking diversions material and labour supply. Being managed within the on West Carr Lane and Sutton Road contracts. Priory Park - £2.5m Contractor appointed, the option Reports continue to be developed and the topographical survey is underway. Time delays and cost inflation due to covid on both 2021 material and labour supply. Being managed within the contracts. Albion Square - £87m Significant mixed use Surveys continue at the rear of the mural to identify the extent of asbestos. Positive discussions have been held Significant time and cost risk around the scheme design 2023 regeneration scheme including ice arena, residential, with the bus companies regarding the highways proposals, and the principles for the scheme have been agreed to dependant upon the future of the 3 Ships Mural. Retention commercial, retail, multi-storey car park and further develop with all stakeholders as we move into more detailed design for the wider scheme. Engagement of the mural impacts on the viability of the scheme. Time associated public realm following demolition of with HCC’s residential partners continue and initial designs for the northern residential have been discussed with and cost delays due to covid on both material and labour BHS/Co-Op building. the planners. Options continue to be reviewed in line with progressing to RIBA 3. supply. A63 Castle Street Castle Street Improvement DfT have now signed off several aspects. Detailed design will continue through to November. HCC will continue to On going risks managed with highways agency 2026 Scheme be engaged during this process. Works have commenced at Lister Street, to construct a new access road.Trinity Burial Ground – a significant number of trees have been cleared from the site; sheet piles forming the alignment of the new slip road now installed.Modern Courts/High Street – site clearance is in progress. Works within the Holiday Inn site and Kingston Retail Park and at High Street will commence in the autumn. Albert Avenue Baths £4.5m Refitting & remodelling of The size of the new gymnasium and fitness suite has now been agreed and design work has begun. The size of Cost inflation due to covid on both material and labour 2022 Albert Avenue pools including the re-introduction of the new lido has also been agreed by HCC, HCAL and the Kayak Club. Site investigation surveys commnecing. supply alongside unknown costs that could be identified the outdoor pool as a new lido. Initial work has started on Planning Applications which are required for both the gym/fitness suite and the lido. as part of the detailed project development phase. Beverley Road Baths £2.94m Refitting & remodelling Roofing works underway. Internal refurbishment and redecoration works agreed with HCAL, and the necessary Potential delays on site as works progress due to COVID 2021 of Beverley Road Baths including roof works Planning Consent and LBC submitted. Designs for the external hoarding has been agreed will be in place shortly. outbreak.Listed Building Consent required to undertake internal refurbishment works.Unforeseen repair and maintenance works required which have not been captured during the original survey and feasibility phases. East Park Splash Pad £819k Upgrade and Slight internal redesign of the office layout and plant compound with the contractor to amend. Planning conditions Time delays and cost inflation due to covid on both 2021 refurbishment of the Water Play feature in East Park. also with the contractor for discharge. material and labour supply. Being managed within the contracts. 1 Major Projects: Work Programme 2020/21 Project Summary Current Position Key Risks Prog completio Pickering Park – Aviary £450k Extension to and George Rowntree drinking fountain has been removed by Lost Art and will be fully refurbished before being Time delays and cost inflation due to covid on both 2021 refurbishment of the existing aviary in Pickering Park relocated at the new extension. Additional vegetation and shrub removal to take place to allow an official start on material and labour supply. Being managed within the to create an Animal Education Centre, similar, albeit site early October. contracts. smaller, to the one at East Park. East Park Splash Boat £150k Refurbishment of the All contracural works complete. Once concrete repairs completed the basin will be refilled. Options to potentially Time delays and cost inflation due to covid on both 2021 Grade II listed splashboat and boat house to ensure fully automate the ride will be discussed with planning regarding LBC. material and labour supply. Being managed within the longevity of the attraction and ADIPS certification. contracts. Princes Quay Bridge The latest HE programme puts the completion timeframe to Autumn (early November). Hardscape works are Time delays and cost inflation due to covid on both 2020 progressing on both the north and south sides, with granite and York stone paving to the terracing and walkway material and labour supply. Being managed within the areas. Initial fill of planters and irrigation system is underway; 4 CCTV cameras installed w/c 14/9. contracts. HERITAGE ACTION ZONE Heritage Action Zone Enabling works for An expression of interest has been submitted to the Highways England Designated Funds scheme for £1m to Funding not yet confirmed which will mean project cannot 2024 regeneration of Hull Old Town (including South develop a visitor offer on the South Blockhouse site. Timescales for feedback on the Council’s expression of be delivered. Blockhouse) interest are to be confirmed by the funder. Humber High Street Challenge Fund £6m Decision records are currently being progressed to award £900k of funding for proposals on Whitefriargate and Process grant agreements in a timely manner to prevent 2021 Silver Street, with projects scheduled to start on site before the end of October. slippage of delivery timescales. High Street Heritage Action Zone £2.7 Target buildings for grant funding have now been confirmed with Trinity House. The Delivery Programme now Impact of COVID-19 on deliverability of community 2024 includes Community Engagement Plan for the four year programme. The first activity to be delivered comprises an engagement programme exhibition for Black History Month which links into a wider oral history research project that will uncover people’s memories of Whitefriargate. Future High Street Fund £22m Government has requested further clarification on benefit cost calculations (from all local authorities). Reponses in Funding not yet confirmed and Future High Street Fund is 2024 place. It is anticipated that the government will then announce funding awards the weeks following this clarification oversubscribe. exercise. HERITAGE LOTTERY SCHEME Pearson Park - £2.43 Refurbishment of Park inc, The contractor has completed the main works contract. The East Lodge is back in the possession of the Council Impact of Covid-19 on the delivery of the agreed NLHF 2023 conservatory, bridge, kiosk, lodge, bandstand and and snagging items in the conservatory are complete. outputs associated with the project's Activity Plan. landscaping 2 Major Projects: Work Programme 2020/21 Project Summary Current Position Key Risks Prog completio Beverley Road - £2.7m NLHF scheme to improve the Boundary treatments project contract has commenced. Several meetings with potential grantees have been held, Progression of Stage 2 applications for key sites and 2022 Beverely road frontages with some direct works, to provide assistance in the development of Stage 1 and Stage 2 applications. completion of delivery of the projects on site being grants and activities. completed within the NLHF grant deadline. Guildhall Time Ball - £282k Replacing the Guildhall The procurement of the main works contractor is at evaluation stage. Installation of the Time Ball will be delivered Installation of the Time Ball mechanism is dependent on 2022 time ball and associated activities alongside further repairs to the Guildhall roof. The Apprentice Clock Technician has created a prototype working the Guildhall roof repairs 2nd phase being successfully model of the Time Ball. Following testing of the mechanism, a final version of the model will be produced. delivered concurrently. National Picture Theatre £494k Refurbishment of RIBA stage 2 drawings approved. Draft of the Activity Plan has been completed. Both the drawings and Activity NHLF budget pressures due to Covid-19 making the 2022 theatre site with partners Plan will be presented to the NLHF monitor at the upcoming mid-term development review meeting. second round funding more competitive. Potential that second round funding may not be secured. Queens Gardens £4.3m Refurbishment of Queens The project team is working towards the completion of RIBA 4 designs. Pre-qualification procurement process Scope of works coming within budget may require value 2022 gardens and links to North End shipyard and underway. engineering or phased delivery approach. crossing at High St/Clarence St HYMC Project Hull: Yorkshire's Maritime City Project - The sites Historic Ships.
Recommended publications
  • Passionate for Hull
    Drypool Parish, Hull October 2015 WANTED Drypool Team Rector / Vicar of St Columba’s Passionate for Hull Parish Profile for the Team Parish of Drypool, Hull 1/30 Drypool Parish, Hull October 2015 Thank you for taking the time to view our Parish profile. We hope that it will help you to learn about our community of faith and our home community; about our vision for the future, and how you might take a leading role in developing and taking forward that vision. If you would like to know more, or visit the Parish on an informal basis, then please contact any one of the following Revd Martyn Westby, Drypool Team Vicar, with special responsibility for St John’s T. 01482 781090, E. [email protected] Canon Richard Liversedge, Vice-chair of PCC & Parish Representative T. 01482 588357, E. [email protected] Mrs Liz Harrison Churchwarden, St Columba’s T. 01482 797110 E. [email protected] Mr John Saunderson Churchwarden, St Columba’s & Parish Representative T. 01482 784774 E. [email protected] 2/30 Drypool Parish, Hull October 2015 General statement of the qualities and attributes that the PCC would wish to see in a new Incumbent We are praying and looking for a priest to join us as Rector of Drypool Team Parish and vicar of St Columba’s Church. We seek someone to lead us on in our mission to grow the Kingdom of God in our community, and these are the qualities we are looking for. As Team Rector The ability to: Embrace a call to urban ministry and a desire to develop a pastoral heart for the people of the various communities in the Parish Be Strategic and Visionary Work in partnership with existing Team Vicar and Lay Leadership Developing and empowering Lay Leadership further Respect the uniqueness of each congregation and continue unlocking the sharing of each others strengths Be organised and promote good organisation and communication Someone who can grow to love this community as we love it.
    [Show full text]
  • Draft Hull Old Town Conservation Area Character Appraisal July 2020
    Draft Hull Old Town Conservation Area Character Appraisal July 2020 0 1 Contents 1. Summary ........................................................................................................................... 2 2. Introduction and background ............................................................................................. 3 3. General history and development ..................................................................................... 5 4. Topography ..................................................................................................................... 14 5. Archaeology .................................................................................................................... 14 5.5 Public archaeology ................................................................................................... 15 6. Streets, public spaces and art ......................................................................................... 17 6.1 Streetscape .............................................................................................................. 17 6.2 Street furniture and signs ......................................................................................... 19 6.3 Public spaces ........................................................................................................... 20 6.4 Public art .................................................................................................................. 29 7. Greenery ........................................................................................................................
    [Show full text]
  • Wilberforce Court
    WILBERFORCE COURT ALFRED GELDER STREET • HULL • HU1 1NE OVERVIEW 04 - 05 THE VISION 06 - 07 THE LIFESTYLE 08 - 11 EASILY ACCESSIBLE 12 - 13 KINGSTON UPON HULL 14 - 17 DISTINGUISHED THE PROPERTY 18 - 23 THE INTERIORS 24 - 33 LIVING IN THE FINISHES 34 - 37 OUTSTANDING IDEALLY CONNECTED 38 - 39 OWNERSHIP MADE EASIER 40 - 41 SURROUNDINGS FLEXIBLE OWNERSHIP 42 - 43 THE DEVELOPER 44 - 45 SUMMARY 46 - 47 WILBERFORCE COURT 04 05 The result of a visionary £14 million redevelopment project, Wilberforce Court is set to produce some of the most desirable residential units in Hull’s city centre. Originally built as high-end offices, the building is now witnessing an OVERVIEW internal transformation. The work, which will be completed in two phases with the first phase completing Q1 2023, will create light, beautifully equipped apartments over four levels, all built over secure on-site parking. Standing at the eastern side of the city centre, immediately adjacent to the historic ‘Old Town’ museum quarter, this is a property that boasts character, convenience and exceptional quality. AT A GLANCE A lavish multimillion pound redevelopment Attractive pre-market prices Phase one comprises of a mix of 112 studio, single-bedroom and two-bedroom units CHARACTER, An outstanding specification CONVENIENCE AND EXCEPTIONAL Secure, light and energy efficient QUALITY Exceptionally convenient city-centre location Phase one completion Q1 2023 ELEGANT LIVING 06 07 THE VISION Featuring four residential storeys rising above private undercroft parking, Wilberforce Court offers a rare combination of convenience, modernity and seclusion. The private residents’ courtyard affords an area for quiet retreat, yet the property itself is situated close to all the amenities of the city centre.
    [Show full text]
  • Briefing Paper to the Riverside Area Committee
    Briefing Paper to the Riverside Area Committee Wards: Newington and Gypsyville, 11 th September 2020 St Andrews and Docklands, Drypool Riverside Regeneration Projects Briefing Paper of the Assistant Director, Major Projects and Infrastructure 1. Purpose of the Paper and Summary The purpose of this briefing paper is to update Members of Riverside Area Committee on the regeneration projects delivered by the Major Projects & Infrastructure Team. 2. Background 2.1 Regeneration activities across the city are focused in the Council’s priority renewal areas. These areas include Newington and St Andrew’s, the Holderness Road Corridor, Orchard Park and North Bransholme. 2.2 This briefing paper outlines the progress made within the Riverside area, including an update on developments currently on site and new programmes being brought forward as a result of successful funding bids. 3. Issues for Consideration City Centre & Gateways Albion Square 3.1 The asbestos removal works are now complete with residual asbestos content still present within structural elements of the building. Detailed structural survey investigatory works have been undertaken to inform on the condition of the mural and the anticipated life expectancy of the overall structure. In addition to this further asbestos surveys have been undertaken to better inform the costs associated with the potential demolition works, should this be the route that is agreed. The overarching report around structural integrity of the mural, demolition methodology and option appraisals is expected mid-September. The Asbestos Risk does not change. 3.2 Work continues with the contractor to develop firm costs for the scheme with a number of design options under review regarding the potential outcomes for the future of the mural.
    [Show full text]
  • Latter-Day Saint Scandinavian Migration Through Hull, England, 1852-1894
    BYU Studies Quarterly Volume 41 Issue 4 Article 3 10-1-2002 Latter-day Saint Scandinavian Migration through Hull, England, 1852-1894 Fred E. Woods Nicholas J. Evans Follow this and additional works at: https://scholarsarchive.byu.edu/byusq Part of the Mormon Studies Commons, and the Religious Education Commons Recommended Citation Woods, Fred E. and Evans, Nicholas J. (2002) "Latter-day Saint Scandinavian Migration through Hull, England, 1852-1894," BYU Studies Quarterly: Vol. 41 : Iss. 4 , Article 3. Available at: https://scholarsarchive.byu.edu/byusq/vol41/iss4/3 This Article is brought to you for free and open access by the Journals at BYU ScholarsArchive. It has been accepted for inclusion in BYU Studies Quarterly by an authorized editor of BYU ScholarsArchive. For more information, please contact [email protected]. Woods and Evans: Latter-day Saint Scandinavian Migration through Hull, England, 18 latter day saint scandinavian migration through hull england 1852 1894 fred E woods and nicholas J evans nearlyearly one hundred thousand latter day saints made the journey N across the atlantic during the nineteenth century both contemporary commentators and mormon historians alike have described these ocean crossings extensively yet the journey from liverpool to america was but one segment in the much longer gathering process for over twenty four thousand scandinavian cormonsmormons who migrated to utah during this period scandinavians represented the second largest ethnic group of saints gathering to zion between 1852and1852 and
    [Show full text]
  • Hull Welcomes All Seafarers
    PLACES OF WORSHIP SEAFARERS’ PORT HULL SEAFARERS’ CENTRE Roman Catholic: Sacred Heart, Southcoates Lane INFORMATION LEAFLET www.sacredhearthull.uk 01482 376 332 Anglican: Hull Minster, Market Place Open 24hrs a day / 7 days a week www.hullminster.org 01482 224 460 HULL Danish Seamen’s Church: 104 Osborne Street www.danchurchhull.co.uk 01482 225 469 WELCOMES ALL via access code C634XY SEAFARERS Internet Café • Free Wi-Fi Out of hours Emergency No: 07906 661 633 SEAFARERS’ INTERNET HULL SEAFARERS’ CENTRE DATA & SIM CARDS United House, King George Dock West, Hull, HU9 5PR Telephone cards are also available for purchase at the Hull Seafarers’ Tel: 01482 376 322 Centre and from Ship Welfare Visitors representing the centre. Seafarers Email:[email protected] are strongly advised to purchase telephone cards only from official Hull Seafarers’ Centre representatives or a Port Chaplain. SHIP WELFARE VISITING ORGANISATIONS Apostleship of the Sea SEAFARERS’ TELEPHONE HELPLINES Port Chaplain +44 (0) 7906 661 633 SeafarerHelp....the lifeline for seafarers The Mission to Seafarers 07387 022 375 wwww.seafarerhelp.org (All seafarers) +44 20 7323 2737 Port Chaplain A seafarer making use of the Wi-Fi in the Hull Seafarers’ Centre. Seafarer Support Referral Helpline Fishermen’s Mission +44 (0) 1482 323 440 PORT OFFICE & SECURITY www.seafarersupport.org (UK seafarers only) 0800 121 4765 07917 754 527 ABP House 01482 327 171 Danish Seamen’s Church 01482 225 469 Port Security (24hr service) 01482 781 867 LOCAL PORT HEALTH AUTHORITY Nautilus International 020 8989 6677 Hull & Goole Port Health Authority 01482 324 776 RMT 020 7387 4771 [email protected] Produced by the Merchant Navy Welfare Board, registered as a charity No.212799 in England & Wales, and No.SC039669 in Scotland.
    [Show full text]
  • Hull: Yorkshire's Maritime City: the People's Choice Competition
    Hull: Yorkshire’s Maritime City: The People’s Choice Competition Resources and activities for primary schools taking part in the Hull: Yorkshire’s Maritime City Project’s People’s Choice Competition. For Primary School Years 4-6 Contents This booklet contains the following: 1. The People’s Choice Competition 2. How to take part 3. Object Short list 4. Ideas and Activities for Pupils 5. Competition Resources 1. The People’s Choice Competition Hull: Yorkshire’s Maritime City (HYMC) is a multi-million pound project which seeks to connect local people with Hull’s unique maritime history. This will be achieved through the redevelopment of five historic sites: the Hull Maritime Museum, Dock Office Chambers, the North End Shipyard, the Arctic Corsair and the Spurn Lightship. Between March and June 2020, we are inviting Hull’s primary schools to choose 14 objects – from a short list of 35– to go on display at the Hull Maritime Museum as part of our People’s Choice Competition. The competition will run between March and Friday 19th June. In the People’s Choice Competition pupils, in Years 4-6, will be asked to select their favourite object from the short list and write a label about it. The Hull Maritime Museum This label should tell the reader a story about the object. The story could be based on fact or be one that is completely made-up! Pupils can decide to use prose, illustrations or a mixture of both to tell their story. Members of the HYMC team will judge the submitted labels and select 14 winners.
    [Show full text]
  • City Centre Briefing Paper
    Briefing Paper for City Centre Task and Finish Wards: St Panel Andrews and Docklands 10 September 2018 Early Evening / Night Time Economy in the City Centre – Briefing Paper 2 Briefing Paper of the Director of Regeneration 1. Purpose of the Paper and Summary This paper provides information on and about the early evening/ night time economy in the city centre. The growth in city centre activities resulting from recent Council-led investment provides scope to further improve and diversify the early evening/ night time economy across the whole of the city centre. Information is provided on the objectives for the City Centre Task and Finish Panel, as agreed by the Council, to assist member investigations into how the city centre can become more vibrant after 5pm. 2. Analysis of city centre connectivity 2.1 Local Transport Plan The Council’s Local Transport Plan (LTP) sets out the vision and aims for transport in Hull and also sets the transport priorities for the Local Plan. The LTP’s vision is “to provide and develop a safe and efficient transport system that contributes to the social, environmental and economic wellbeing of the residents, businesses and visitors to the city.” The LTP aims to have a city committed to a low carbon future, which has a transport network and mobility culture that positively contributes to a thriving economy and the health and wellbeing of its citizens, and where sustainable travel is the option of choice The continued dominance of the car, often at the expense of other transport modes, presents a major challenge to transport planning in Hull.
    [Show full text]
  • U DEW Archives of Ellerman's Wilson Line 1825-1974
    Hull History Centre: Archives of Ellerman’s Wilson Line U DEW Archives of Ellerman's Wilson Line 1825-1974 Historical Background Hull might be considered an unsuitable location for what at one time was the largest privately owned shipping company in the world, with its awkward 27 mile approach up the Humber from the North Sea. Nevertheless, here was founded the firm of Thomas Wilson Sons & Co. (TWSC), later Ellerman's Wilson Line (EWL), but known for most of its life and now remembered as the Wilson Line. Furthermore, the activities of this single company helped to make Hull Britain's third largest port by the beginning of the twentieth century. In March 1904 TWSC owned some 99 vessels, most of which had been built by the local firm of Earle's Shipbuilding and Engineering Company Limited, which had itself been bought by TWSC shortly before. Thomas Wilson, the founder of the firm, was born in Hull on 12 February 1792. He went to sea as a boy but then became a clerk with Whitaker, Wilkinson & Co., importers of Swedish iron ore, later becoming their commercial traveller in the Sheffield area. On 1 September 1814 he married Susannah John West and they eventually had 15 children. The story goes that, with a growing family, he asked his employers for a rise, was refused, and in 1820 chose to set up in business for himself, relying on various partners for the provision of capital. The first of these in 1822 was John Beckington, a merchant and iron importer from Newcastle. The firm of Beckington, Wilson & Co.
    [Show full text]
  • EYLHS Newsletter 18 Winter / Spring 2008
    EYLHS Newsletter 18 Winter / Spring 2008 newsletter of the East Yorkshire Local History Society Front cover: The Kingston Enamelled Slate and Marble Steam Works factory site on Park Road By F.S. Smith [KINCM:1981.415.78] (Hull Museums) Contributions Based in Hull it is not always easy to keep track of events in other parts of the Riding; news that members could contribute on their town or village should be sent to the editor. Short articles, illustrated or unillustrated, news on libraries, archives, museums, societies or education, queries other people may be able to answer, etc. for inclusion in future news- letters should also be sent to the editor. Newsletter edited by Christopher Ketchell 47 Clumber Street, Hull, HU5 3RH Telephone 01482 346125 published by the East Yorkshire Local History Society Secretary David Smith 114 Telford Street, Hull, HU9 3DY Telephone 01482 706902 e-mail [email protected] printed by Kall Kwik, Hull News from the Society The experimental A5 size of the last Time: 2.15pm newsletter proved popular, therefore Cost: £4 future editions will be that size. Maximum 40 people Tea and coffee provided Apologies for the slightly late appear- Limited parking available onsite. On- ance of this edition; due to ‘circum- street parking available in Pryme Street, stances beyond our control’, etc. Anlaby. Talk - will outline the work of the Hull Programme Jewish Archives group in preserving the archival legacy of the Jewish com- As usual, the Society has arranged a full munity in Hull and showcase some of programme of lectures and excursions the historical collections gathered to for 2007.
    [Show full text]
  • Hull Local Plan to 2030 Preferred Options October/November 2015 Consultation Statement
    Hull Local Plan to 2030 Preferred Options October/November 2015 Consultation Statement Introduction This document provides a summary of the Preferred Options consultation that Hull City Council undertook in 2015 as part of the process of preparing a new Local Plan. Background Hull City Council is preparing a new Local Plan that will help shape the city over the next 15 years. This will identify land for different types of use and set out policies that will be used to determine planning applications. Once adopted, the Local Plan will be used to guide development in the city up to 2032. Consultation on Issues and Options was carried out in 2014 and full details can be found in the Report on Consultation on that stage of the plan. Consultation on the Preferred Options is the second stage in the new Local Plan’s preparation. It sets out the draft planning policies and potential site allocations that the Council believes are appropriate. It also sets out the other potential options the Council considered and the reasons why they were not chosen. Preferred Options Consultation The Preferred Options consultation took place in October and November 2015 in accordance with Regulation 18 and the Council’s Statement of Community Involvement. As part of the consultation process, the following public events were held: • ‘Local Plan Forum’ on Wednesday 5 November • Ward Forums • Drop in sessions • Tuesday 20th October am: Hull History Centre • Thursday 22nd October pm: Hull History Centre • Thursday 22nd October evening: Hull Central Library To publicise the consultation and the events listed above, Hull City Council did the following: • Wrote directly to everyone on the Local Plan consultation database.
    [Show full text]
  • Hull 2017 HLF Outcomes Evaluation
    Evaluation Report Creating the Past: An Evaluation of Cultural Programming Inspired by Heritage within Hull UK City of Culture 2017 Hull UK City of Culture 2017 In 2017, OVER THREE-QUARTERS of local residents attended a museum, gallery or other historic attraction INTRODUCTION ART & HERITAGE IN NUMBERS As holders of the UK City of Culture title in 2017, Hull • 365 days of transformative culture rose to the challenge, using art to explore history, heritage and untold stories within its 365 day • Presenting the city’s heritage from the 18th programme of transformative culture. Century to the present day • 93% of audiences agreed using art-based Levels of participation amongst residents reached approaches to present the history and 95% through attendance at over 2,000 events and heritage of Hull made it more interesting activities at 250 venues. The percentage of local people who were proud to live in Hull at the end of • 66% of Hull residents and 74% of East Riding 2017 rose to 75%, an all time high. residents said their knowledge of the history and heritage of Hull had increased Heritage was positioned as a cornerstone of the year with museums, galleries, archives and historic • 95% of residents attended or experienced a buildings playing a crucial role in achieving the wider cultural event or activity as part of the UK’s aims and ambitions. City of Culture 2017 • By the end of 2017 there had been over 2,000 The evaluation of activities inspired by and involving activities at over 250 venues the history and heritage of the city demonstrates the successful delivery of key outcomes for heritage, for people and for communities.
    [Show full text]