Involuntary Resettlement Assessment and Measures

Resettlement Plan for AEP 3: 57 A, B and C (Gubbi–Pura–Beeragonahalli (NH-48)–Kowdley– ) Document Stage: Draft for Consultation Project Number: 42513 August 2010

IND: State Highway Improvement Project

Prepared by Public Works Department, Government of Karnataka.

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. ii

TABLE OF CONTENTS ABBREVIATIONS ……………………………………..iv EXECUTIVE SUMMARY ……………………………...... vi 1 CHAPTER I – PROJECT DESCRIPTION...... 1 1.1 BACKGROUND ...... 1 1.2 OBJECTIVES...... 1 1.3 PHYSICAL CHARACTERISTICS OF THE PROJECT AREA...... 4 1.4 PROJECT COMPONENTS ...... 4 1.5 ROAD CONFIGURATION:...... 4 1.6 REALIGNMENT /BYPASSES: ...... 4 1.7 BRIDGES AND OTHER CROSS DRAINAGE STRUCTURES:...... 4 1.8 ROAD SIDE DRAINAGE:...... 5 1.9 RAILWAY OVER BRIDGES (ROB’S): ...... 5 1.10 JUNCTIONS /INTERSECTION IMPROVEMENTS: ...... 5 1.11 SERVICE ROADS AND UNDERPASSES:...... 5 1.12 WAY SIDE AMENITIES /TOLL PLAZA /TRUCK PARKING, ETC.: ...... 5 1.13 MAGNITUDE OF IMPACTS...... 5 1.14 MINIMIZING IMPACTS...... 7 1.15 MITIGATION THROUGH REALIGNMENTS/BYPASSES AND DESIGN ALTERATION ...... 7 1.16 DESIGN CROSS-SECTIONS...... 8 1.17 MITIGATION THROUGH DESIGN CROSS SECTION...... 8 1.18 ROAD SAFETY AND TRAFFIC MANAGEMENT MEASURES ...... 9 1.19 MAGNITUDE OF IMPACTS CULTURAL PROPERTIES AND CPRS ...... 9 1.20 IMPACT OF THE PROJECT ...... 10 1.21 RIGHT OF WAY AND CORRIDOR OF IMPACT...... 10 2 CHAPTER 2 – METHODOLOGY FOR IMPACT ASSESSMENT...... 12 2.1 SOCIAL IMPACT ASSESSMENT ...... 12 2.2 APPROACH TO RESETTLEMENT PLANNING...... 12 2.3 CENSUS SOCIOECONOMIC SURVEY...... 13 2.4 METHODOLOGY AND DATABASE...... 13 2.5 SOURCES OF DATA...... 13 3 CHAPTER 3 – SOCIOECONOMIC INFORMATION AND PROFILE ...... 15 3.1 SOCIOECONOMIC PROFILE OF THE PROJECT AREA...... 15 3.2 SOCIOECONOMIC PROFILE OF DISPLACED POPULATION ...... 15 3.3 VULNERABLE GROUPS...... 19 3.4 GENDER ISSUES...... 20 3.5 INDIGENOUS PEOPLE...... 20 4 CHAPTER 4 – SCOPE OF LAND ACQUISITION AND RESETTLEMENT ...... 22 4.1 PROPOSED LAND ACQUISITION ...... 22 4.2 ESTIMATED TIME FOR LA ...... 23 4.3 MANAGING LAND ACQUISITION...... 23 4.4 STAFFING FOR LAND ACQUISITION WORK...... 23 4.5 NEGOTIATIONS COMMITTEE FOR LAND PRICE FIXATION AND DETERMINATION OF REPLACEMENT COST ...... 24 4.6 NEGOTIATION COMMITTEE ...... 24 4.7 METHOD OF PRICE FIXATION...... 24 4.8 FAILURE OF KHA AND APPELLATE COMMITTEE...... 25 4.9 VALUATION OF ASSETS...... 25 4.10 CUT-OFF DATE ...... 25 4.11 ESTIMATION OF LAND REQUIREMENT AND PREPARATION OF LAND ACQUISITION PLANS26 4.12 COMPENSATION PAYMENT PROCESS ...... 26 4.13 ADMINISTERING THE PAYMENT OF R&RASSISTANCE ...... 26 5 CHAPTER 5 – STAKEHOLDERS CONSULTATION AND PARTICIPATION ...... 27 5.1 CONSULTATION AND COMMUNITY PARTICIPATION...... 27 5.2 METHODOLOGY...... 27 5.3 KEY FINDINGS OF THE CONSULTATIONS ...... 27 5.4 LEVELS OF CONSULTATION ...... 32 5.5 CONSULTATIONS DURING IMPLEMENTATION...... 32 6 CHAPTER 6 – LEGAL FRAMEWORK...... 34 6.1 THE NATIONAL POLICY ON RESETTLEMENT AND REHABILITATION FOR PROJECT AFFECTED HOUSEHOLDS, 2007 ...... 34 6.2 THE LAND ACQUISITION (LA) ACT OF 1894 ...... 35 6.3 ASIAN DEVELOPMENT BANK’S SAFEGUARD POLICY ...... 35 6.4 INDIGENOUS PEOPLES...... 37 6.5 KARNATAKA HIGHWAY ACT 1964 ...... 37 6.6 COMPARISON OF NATIONAL AND STATE POLICIES WITH ASIAN DEVELOPMENT BANKS SPS -2009...... 37 7 CHAPTER 7 – ENTITLEMENTS, ASSISTANCE AND BENEFITS ...... 39 7.1 KSHIP POLICY...... 39 7.2 IMPACTS AND ENTITLEMENTS...... 39 7.3 CORRIDOR OF IMPACT ...... 39 7.4 TARGETED SUPPORT TO VULNERABLE GROUPS ...... 40 7.5 OPTION AND CHOICES ...... 40 7.6 PRINCIPLES...... 40 7.7 DEFINITIONS...... 40 7.8 ENTITLEMENTS...... 42 7.9 THE DPS WILL BE PROVIDED WITH THE FOLLOWING BENEFITS: ...... 42 7.10 ENTITLEMENT MATRIX ...... 46 8 CHAPTER 8 – RELOCATION OF HOUSING AND SETTLEMENTS...... 52 8.1 BASIC PROVISION FOR RELOCATION ...... 52 8.2 NEED FOR RELOCATION...... 52 8.3 DEVELOPMENT OF VENDOR MARKETS ...... 52 8.4 DEVELOPMENT OF RESETTLEMENT CENTERS...... 52 8.5 ENVIRONMENTAL ASPECTS...... 53 8.6 SOCIAL ASPECTS ...... 53 8.7 BASIC AMENITIES AND FACILITIES ...... 53 9 CHAPTER 9 – INCOME RESTORATION AND REHABILITATION...... 55 9.1 INCOME RESTORATION MEASURES ...... 55 9.2 IMPACT CATEGORIES AND IR SCHEMES ...... 55 9.3 IR ACTIVITIES...... 55 10 CHAPTER 10 – RESETTLEMENT BUDGET AND FINANCING ...... 57 10.1 BUDGET AND COSTS ...... 57 11 CHAPTER 11 – GRIEVANCE REDRESSAL MECHANISM...... 60 11.1 GRIEVANCE REDRESSAL COMMITTEE...... 60 12 CHAPTER 12 – INSTITUTIONAL MECHANISMS ...... 62 12.1 INSTITUTIONAL ARRANGEMENTS ...... 62 12.2 SOCIAL DEVELOPMENT AND RESETTLEMENT CELL (SDRC...... 62 12.3 SDRC AND STAFF DEPLOYMENT ...... 62 12.4 PROTECTION OF ROW...... 65 12.5 VALUATION OF OTHER STRUCTURES/ASSETS ...... 65 12.6 ROLES AND RESPONSIBILITIES OF OFFICIALS FOR RP IMPLEMENTATION...... 65 12.7 COMPETENT AUTHORITY FOR VARIOUS APPROVAL ...... 69 12.8 IMPLEMENTATION SUPPORT BY NGOS...... 70 12.9 DATABASE MANAGEMENT ...... 71 13 CHAPTER 13 – IMPLEMENTATION SCHEDULE ...... 72 13.1 COORDINATION WITH CIVIL WORKS AND CERTIFICATION ...... 72 13.2 IMPLEMENTATION SCHEDULE AND TIMING OF RESETTLEMENT...... 72

iv

13.3 CAPACITY BUILDING AND TRAINING ...... 73

14 CHAPTER 14 – MONITORING AND REPORTING...... 75 14.1 MONITORING ...... 75 14.2 INTERNAL MONITORING ...... 75 14.3 EXTERNAL MONITORING...... 75

LIST OF TABLES Table 1-1: Summary Tables on Impacts ...... 6 Table 2-1: Distribution of DHs...... 13 Table 3-1: Social Stratification ...... 15 Table 3-2: Religion...... 16 Table 3-3: Occupation Distribution...... 16 Table 3-4: Income Distribution ...... 16 Table 3-5: Age Classification ...... 17 Table 3-6: Literacy ...... 18 Table 3-7: Type of Structure ...... 19 Table 4-1: Land Acquisition Details ...... 24 Table 5-1: Key Issues: 57A...... 29 Table 5-3: Key Issues: 57C...... 31 Table 6-1: Comparison of gaps in various Acts and Policies with ADB’s SPS ...... 38 Table 7-1: Entitlement Matrix ...... 46 Table 9-1: Categories for Income restoration ...... 55 Table 10-1: Budget ...... 57 Table 10-2: Unit Costs for R & R ...... 58 Table 10-3: R & R Unit Costs...... 58 Table 12-1: Administrative and Financial Responsibilities of officials and Agencies for RP Implementation ...... 65 Table 12-2: Competent Authority for Approvals...... 69 Table 13-1: R & R Implementation Schedule...... 73 Table 14-1: Monitoring Indicators for Physical Progress ...... 76 Table 14-2: Financial Indicators for Progress ...... 76 Table 14-3: Monitoring Of GRC ...... 77

LIST OF FIGURES Figure 1-1: KSHIP Roads ...... 3

ANNEXURE ANNEX 1: Typical Road Cross Section ANNEX 2: Details of Affected Community Structures ANNEX 3: Census and Community Asset Survey Schedules ANNEX 4: Details of Those Losing Land ANNEX 5: Details of Those Losing Structures ANNEX 6: List of Participants For Consultation Meeting ANNEX 7: NGO ToR ANNEX 8: Monitoring and Evaluation Consultants ToR ACRONYMS ADB Asian Development Bank AC Assistant Commissioner ADSW Assistant Director Social Welfare APL above poverty line BP Bank Policy BPL below poverty line CAO Chief Administrative Officer CPO Chief Project Officer CPR Common Property Resources COI corridor of impact DC Deputy Commissioner DH displaced household DP displaced persons DPR detail project report EWS economically weaker section FGD focus group discussion GOI Government of GOK Government of Karnataka GRC Grievance Redressal Cell HPCFRRI High Power Committee for Redressal of Regional Imbalances HDM Highway Design Module ID identity card IPP Indigenous Peoples Plan IR income restoration ITI Industrial Training Institute KHA Karnataka Highways Act KSHIP Karnataka State Highways Improvement Project LAA Land Acquisition Act LAO Land Acquisition Officer LAP Land Acquisition Plan MRR Manager Rehabilitation and Resettlement NH National Highway NGO Nongovernment Organization NRRP National Resettlement and Rehabilitation Policy PSA Poverty and Social Assessment PA Project Authority PIU Project Implementation Unit PGB Project Governing Body PHC Primary Health Center PWD Public Works Department PU Pre-University RTC Record of Rights R&R Rehabilitation and Resettlement RP resettlement plan ROW right of way SIA Social Impact Assessment SDO Social Development Officer SDRC Social Development Resettlement Cell SWI Social Welfare Inspector SC Scheduled Caste

vi

SR Schedule of Rates ST Scheduled Tribes ToR Terms of Reference UR Upgrading ZP Zilla Panchayat EXECUTIVE SUMMARY E1. Project Description 1. The Public Works Department, Government of Karnataka is implementing Karnataka State Highways Improvement Project (KSHIP). Under this Project 615.03 km of State Highways roads have been identified for project assistance under Asian Development Bank. The 615.03 km of roads has been divided into nine packages. The aim of the project is to improve the performance of the State’s road transport network by improving road conditions and capacity, and to improve the State’s capacity to plan, develop and maintain the Karnataka roads network. This project is Package AEP 3 comprising of three links: 57 A (Gubbi – C S Pura - Beeragonahalli near Yediyur (NH48)) is 49.03 km in Tumkur District district and crosses Gubbi, Turuvekere and Kunigal taluks; 57 B (Beeragonahalli near Yediyur (NH48)-Kowdley) is 26.43 km in Tumkur and Mandya Districts, crosses Kunigal taluk and 57 C (Kowdley-Mandya) is 33.16 km in , covering Mandya and Maddur taluks. 2. The scope of work involves upgrading works of improving existing single-lane and intermediate lane roads to 12 m roadway with standard two lane seven meter carriageway and alignment improvements to relevant IRC standards and other associated road and bridge works including improvement of major and minor bridges, culverts, road intersections, drains, road geometrics and road furniture 3. The proposed project can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the project will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace which in turn increases the income of the region, and ultimately elevating their standard of living. Although various positive project impacts and benefits are expected from the proposed project as mentioned above, there will be some negative impacts on the people living in the immediate project area. 4. The aim of this Resettlement Plan (RP) is to mitigate negative impacts caused due to the project and resettle the displaced persons and restore their livelihoods. This Resettlement Plan has been prepared on the basis of census survey findings and consultation with various stakeholders. The plan complies with ADB Safeguard Policy Statement-2009. E2. Socioeconomic Information and Profile 5. In this project Scheduled Caste households account for 6.57 % of the population; Scheduled tribe households account for only 0.39 % of the total population; the remaining are from the general category. Among religious groups, Hindus dominate with 97.92%, the remaining are Muslims. Distribution of displaced persons (DPs) by occupation reveals that agriculture accounts for 72.14%; the other sector, which supports a large section of displaced households (DHs), is agriculture labour accounting for 12.41%; trade/commerce account for 6.67%. In spite of difficulties in getting reliable data on household income efforts were made to persuade the respondents to report as accurate data as possible. 43.35% of the general population has income less than Rs.26,000. Of the nine ST households seven households earn less than Rs.26,000. The income information has been segregated for ST,

viii

SC and general category. In the age classification 71.49% of the total DPs fall in the age group of 18-59. Since this happens to be the working age-group the mitigation measures as given in the entitlement matrix need to be carefully implemented with reference to 18-59 age groups. Illiterate population accounts for 16.34 % of the surveyed population. Just literate population accounts for 9.53 % of the total population; while primary accounts for 11.86 % of the total population; those with Middle school education account for 10.71 % of the total population; those with education upto secondary level accounts for 31.52 % of the total population. Graduates account for 5.47 %. Structure type indicates of the residential structure 74.68 % are pucca. Amongst commercial structures getting affected only 29.15 % of the structures are pucca. Loss of Commercial structures shows majority, that is, 18 of the commercial structures arepan/cigarette shops; followed by 16 tea stalls; seven grocery shops etc. Of the total residential structures getting affected 91% have electricity; while only 12% have access to piped water. Among household assets 46.53% of the households have television; 11.04% own two/four wheelers; 8.46 % having cooking gas; 7.30% have telephones and only 5.29 % have refrigerators. Amongst agricultural equipment 8.04% own tractors; 22.6% own bullock carts; and less than 1% own sprayers. 6. The vulnerable group includes persons such as disabled, widows, or persons above sixty years of age, who are not provided or cannot immediately be provided with alternative livelihood and who are not otherwise covered as part of a household. These persons are entitled to assistance to include in government pension schemes if not included, if eligible as per Government criteria (OR) Lump-sum amount of Rs. 25,000. There are some DPs that are in more than one vulnerable category. These DPs will be paid only once. There are 438 widows, 50 disabled persons and 1154 persons over 60 years. There are 348 women- headed household identified E3. Scope of Land Acquisition and Resettlement 7. Census socioeconomic surveys were conducted for a corridor of impact between 16 m and 22 m keeping in view the design requirements. Land acquisition for the project is estimated at 81.17 acres of private land which needs to be acquired. No government land is getting affected. According to the census survey there are 2590 DHs and 9156 DPs. The project will impact 257 community structures. There is no impact on archaeological sites. All community structures will be relocated by the project authorities before demolition. According to the Census survey 448 DHs are losing structure and 2081 owners are losing agricultural land. Physically displaced (relocation, loss of residential land, or loss of shelter) are 28 households; economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) are 2231 households, plus 20 persons who are losing their livelihood as employees. There are 150 households that are both physically and economically displaced, as thery are losing their total commercial structure. .The summary project impacts are presented below. Table E-1: Summary of Project Impacts Impacts No. 1 Land Acquisition 81.17 Acres 2 Total no. of owners losing land 2,081 households 3 Total no. of private structure affected 448 households 4 Total No. of CPRs 247 5 Total no. of DPs 9,156 persons 6 Total no of physically and economically displaced (those 150 households losing commercial structures totally) 7 Total no of economically displaced ( those whose incomes 2,231 households are affected but not physically displaced) 8 Total no. economically displaced persons ( employees) 20 persons 9 Total no. physically displaced ( those losing their 28 households residential structures) Source: Census Survey, KSHIP Project, April 2009-2010.

E4. Stakeholders Consultation and Participation

8. Consultations with various stakeholders were carried out during various phases of project preparation. People wanted to know how compensation for coconut and arecanut trees; they said project is providing for 30 ft by 40ft site for those losing residential structures ande wanted to know what arrangement the project is making to provide such sites; wanted to know how shops on government land will be compensated; some of the petty shop owners had taken loan – so if the project takes away the shop how will these people repay their loans; people wanted to know when compensation will be paid ; they wanted to know how affected bore wells will be replaced; they wanted to know whether the water pipelines and electric poles will be replaced; people wanted to know if 60 % of the house is affected, whether the project will take the remaining 40%; people asked for market value for land; people wanted the details of impacts and acquisition; they wanted to know whether the petty business can continue their shops after the construction of the road; if more than 25% of the house is going they want compensation for the whole structure; people wanted to know how the project will compensate for community structures getting affected. The people were about the entitlements and how to approach the problems raised. 9. To keep transparency in planning and for further active involvement of stakeholders the project information will be disseminated through disclosure of resettlement planning documents. The PA will submit the RP to ADB for disclosure on ADB’s website. 10. The PA will provide relevant resettlement information, in a timely manner, in an accessible place in to affected persons and other stakeholders. A Resettlement and Land Acquisition information leaflet containing information on compensation, entitlement and resettlement management adopted for the project will be made available in Kannada and distributed to DPs. E5. Legal Framework 11. The GOK will adopt a Resettlement and Rehabilitation (R&R) Policy for KSHIP to address the adverse impacts arising out of this project in the line with the National Resettlement and Rehabilitation Policy, 2007. The policy adopted for the project is consistent with the Asian Development Banks Safeguard Policy Statement. This RP is prepared in accordance with the stipulations and guide-lines provided in Public Works Departmental Code Government of Karnataka, and the project specific Resettlement and Rehabilitation: Principles and Policy Framework for the Karnataka State Highways Improvement Project, The National Resettlement and Resettlement Policy 2007 and The Asian Development Banks Safeguard Policy Statement SPS -2009. In addition to the above measures, realizing the need of infrastructure development like roads in timely manner, the PWD GOK has decided to acquire the land through the legislation called The Karnataka

x

Highways Act 1964 (KHA,1964). The KHA, 1964 provides the opportunity to acquire the land through consent award. It is expected that land acquisition under this Act will help the DPs to receive the market price/replacement cost of land as compensation. The GOK has already initiated the process of establishing the Negotiation Committee. The role of the committee will be to negotiate the price of land with the beneficiary. The guidance value of the land will be considered for negotiation. Minimum negotiated price for the Districts of Urban, Bangalore Rural, Chikkaballapur, Kolar, Ramnagaram, Mysore, Davangere, Belgaum and Dakshin Kannada will be one and half times the Guidance Value. For all the other districts other than those mentioned the minimum price will be twice the guidance value. E6. Entitlements, Assistance and Benefits 12. The Project Entitlement policy addresses the direct and indirect impacts of project construction and operation on displaced persons, households and communities. The most direct and immediate impacts are those associated with project construction, mainly land acquisition. Other losses include loss of shelter, and other assets within the project’s corridor of impact; as well as roadside structure, business establishments and public facilities. Mitigation is provided through compensation and assistance to project-displaced persons, households, and groups. All assistance will be given as one time grant. These social units are entitled to compensation and assistance on the basis of this policy framework adopted by the project. The policy provides mitigation for:  loss of assets, including land and house or work place;  loss of livelihood or income opportunities; and  Collective impacts on groups, such as loss of community assets, common property resources, and others. 13. Compensation eligibility is limited by a cut-off date. The cut off date for non- title- holders, is the date of the start of the census survey on a particular link. The cut-off date for the Link 57A is 14 February 2009, Link 57B is 16 February 2009, and 57C is 11 February 2009. The project Entitlement Matrix (Table E-2) identifies and lists various types of losses resulting out of the project and specific compensation and resettlement packages for each category. Table E-2 Entitlement Matrix No. Impact Entitlements Remarks Category I. Title Holders

(a) Loss of 1. Compensation as per the  Stamp duty and registration land principle of replacement cost charges are applicable for through direct negotiation as those who accept negotiation provided for in the Karnataka price. State Highway Act, 1964 + stamp duty and registration charges;

2. Compensation offered is  Minimum negotiated price for cash for land the Districts of Bangalore

Urban, Bangalore Rural, Chikkaballapur, Ramnagaram, and Corporation / Municipal limits of other district HQs will be 1.5 times the Guidance Value. For all other areas other than those mentioned above the minimum negotiated price will be 2 times the Guidance Value.1 OR average sales statistics, which ever is higher2

3. In case of severance of land an additional 25% compensation will be paid to the land loser if he retains the remaining plot OR if the remaining land is not viable and the land owner opts to surrender the entire plot to the project, compensation as given in No. 1 will be applicable;

4. Loss of perennial crops and non-perennial crops will be compensated in accordance with Horticulture department valuation process, which is the replacement cost.

5. A grant of Rs. 15,000 for replacement of Cattle shed;

6. Water yielding bores will be replaced in the location identified by the affected person in the remaining land holding subject to availability of water. In case water is not

1 Revised Guidance Value of the properties in Bangalore Urban, Bangalore Rural, Chikkaballpur, Ramanagaram and Corporation/Municipal limits is 2-3 times higher than the earlier Guidance Value. Hence 1.5 times the Guidance Value is proposed as minimum negotiated price. In other areas ratio of revision is reasonably low, hence 2 times the Guidance Value is proposed as minimum price. 2 The average Sales Statistics is in line with LA Amendment Bill. In the LA Amendment Bill there are different modalities in determining and assessing the market value, any one among them would be adopted wherein the land loser gets the maximum market value.  As per the NRRP-2007 the acquiring body has to provide rehabilitation grant equivalent to 750 days minimum agricultural wages. At present the minimum agricultural wages is Rs. 100/day. The NGO will ascertain the actual needs of the displaced persons and assist in creating assets.  Bagar Hukum lands are government lands which are unauthorisedly cultivated by persons without legal documents. Applications for regularization that are pending before the regularization committee.

xii

available replacement cost of the borewell at current PWD SR rates without depreciation charges and 30% solatium at replacement cost will be given.

7. In case of land owners who  Marginal farmer is defined as become landless or marginal those left with 1 hectare of farmers, the following non-irrigated or 0.50 hectare of additional entitlements will irrigation or combination of be offered: (a) subsistence both allowance of Rs. 30,000 for land less and marginal; and, (b) assistance for creating Income generation asset valued up to Rs.75,000;

8. Additional amount of Rs.  Narrow stretch of land is 20,000 will be restricted to defined as persons losing an those who lose narrow area that is up to 5 guntas of stretch of land as exgratia land. compensation in lieu of all other benefits.

9. For those becoming landless  The NGO engaged for the RP and all marginal farmers implementation will ensure training assistance will be linkages of the trained persons provided for income to ongoing programs, to generating vocational facilitate employment and training and skills marketing opportunities. upgrade options as per affected the displaced persons' choice;

10. Employment opportunity for affected the displaced persons as per his/her skills and the availability of suitable work in road construction work.

11. In case of Bagar hukum  Any Government land which  lands - 50% of is unauthorizedly occupied by compensation and other a person and such person has benefits as available for land applied for regularization of the owners which is equivalent same under the Karnataka to replacement value for this Land Revenue Rules under category. 108 C(1) is called Bagar Hukum land. Under Rule 108C section 94A, of the Karnataka Land Revenue Act,1966, the Tahsildar is the custodian of the records and he will issue the certification whether the application is pending before the Committee or not. Tahsildar is the Secretary of the Committee for regularization of unauthorized occupation of government land. (b) Loss of 1. Compensation at current  In case more than 25% of a Residential PWD scheduled rates house is affected and unviable structures without depreciation and for retaining, full compensation 30% solatium at will be paid replacement cost.  Resettlement colonies will be 2. Alternative houses in developed if more than 20 resettlement colony or households are displaced in 2 developed plot and km continuous stretch construction cost of Rs.  Plot size will be equivalent to 40,000 linked to construction size lost subject to a maximum progress. of 369 sqmt/1200sqft in rural 3. Additional 25% of current area and 184 sq. m /600 sq. ft. PWD SR rates without in urban areas. depreciation + 30% solatium  Displaced persons have a right for the affected portion as to salvage the affected compensation for partially materials. affected structures towards reconstruction 4. Shifting assistance of Rs. 10,000 5. Subsistence allowance of Rs. 30,000

(c) Loss of 1. Compensation at current  Shopping units with 100-150 commercial PWD scheduled rates sq.ft will be constructed if more structures without depreciation and than 20 shops are affected in a 30% solatium at continuous stretch of 2 km and replacement cost. the owners opt for a shop. 2. Alternative shop or  Displaced persons have a right assistance for income to salvage the affected generation asset valuated materials upto Rs. 75,000  Training for self employment 3. Additional 25% will be provided to one adult compensation for partially per household as needed affected structures 4. Shifting assistance of Rs. 10,000 5. Subsistence allowance of Rs. 30,000

(d) Loss of 1. Compensation at current  In case more than 25% of residential PWD scheduled rates house is affected and unviable cum without depreciation and for retaining, full compensation commercial 30% solatium at will be paid structures replacement cost.  Resettlement colonies will be 2. Alternative shop or developed if more than 20 assistance for income households are displaced in 2 generation asset valuated up km continuous stretch to Rs. 75,000  Plot size will be equivalent to 3. Additional 25% size lost subject to a maximum compensation for partially of 369 sq.m/1200sq. ft. in rural affected structures area and 184 sq. m. /600 sq. 4. Shifting assistance of Rs. ft. in urban areas. 10,000  Shopping units with 100-150 5. Subsistence allowance of sq. ft. will be constructed if Rs. 30,000 more than 20 shops are 6. Additional amount of Rs. affected in a continuous

xiv

25,000 as grant. stretch of 2 km and the owners opt for a shop.  Displaced persons have a right to salvage the affected materials  Training for self employment will be provided to one adult per household as needed

II. Tenants (a) Residential 1. Rental allowance for 6 months @ Rs. 500 per month in rural and Rs. 1000 in urban areas 2. Shifting assistance of Rs. 10,000 (b) Commercial 1. Rental allowance for 6 months @ Rs. 1,000 per month in rural and Rs. 1,500 in urban areas 2. Shifting assistance of Rs. 10,000 3. Assistance for income generation asset up to Rs. 75,000 (c) Loss of 1. Rental allowance for 6 residential months @ Rs. 1,000 per cum month in rural and Rs. 1,500 commercial in urban areas structures 2. Shifting assistance of Rs. 10,000 3. Assistance for income generation asset upto Rs. 75,000 III. Non-Title holders (a) Residential 1. House in resettlement 1. House plot size in resettlement Squatters colony or developed plot and colony to be minimum of 25 construction cost of Rs. sq.m./270 sq ft. Resettlement 40,000 linked to construction colony will be constructed if progress. more than 20 residential 2. Subsistence allowance of squatters are getting affected Rs.15,000. in a continuous stretch of 2 3. Shifting allowance of kms and opted for same. As Rs.5,000. per NRRP 2007. 2. Developed plot size will be allotted of 25 sqms/ 270 sqft in urban area and 33 sqms /350 sqft in rural area as per NRRP 2007.

(b) Commercial 1. Alternative shop of 100 sq. 3. Shopping units will be Squatters ft. or assistance for income constructed if more than 20 generation asset valuated up shops are affected in a to Rs. 30,000; continuous stretch of 2 km and 2. Subsistence allowance of opted for shop. Rs.15,000; 3. Shifting allowance of Rs.5000. (c) Encroachers 1. Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation 2. Compensation of crop loss or advance notice for harvesting crops IV. Loss of livelihood (a) Loss of 1. Subsistence allowance of Rs.  Training for self employment primary 15,000. will be provided to one adult source of 2. Training assistance will be per household as needed income provided for income generating vocational training and skills upgrade options as per the displaced persons' choice; 3. Employment opportunity for the displaced persons as per his/her skills and availability of suitable work in the road construction. V. Vulnerable People (a) Widows 1. Assistance to include in  This will be restricted to those Physically government pension schemes who have no or cannot be challenged if not included , if eligible as provided with alterative and those per Government criteria (OR) livelihood sources. aged above 2. Lumpsum amount of Rs.  Training for those above 60 60 years 25,000 years is not mandatory and will 3. Training assistance will be be provided for if the person provided for income generating opts for it and after the need is vocational training and skills assessed. upgrade options as per the displaced persons' choice

VI. Community Assets (a) Community 1. Reconstruction of affected Assets assets 2. Transfer to Local authorities for maintenance VII. Unidentified Impacts (a) Unidentified 1. Unforeseen impacts shall be Impacts documented and mitigated based on the principles provided in this policy

Note: All amounts in this entitlement matrix are fixed as of April 01, 2010. These will increased 10% annually on first day of April every year. The same will hold good for guidance value also if not revised by the GoK.

E7. Relocation of Housing and Settlements 14. Where ever there is a loss of residential structure the PA will provide for alternative house. The alternative house will be provided in consultation with the displaced person. The Project Authority will provide compensation for the affected structure without depreciation,

xvi adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. There are 23 titleholder houses and four non titleholder houses to be relocated through out the package. There are 134 nontitleholder commercial structures to be relocated. The land for relocation will be identified by the PIU in consultation with the DPs. 15. People prefer resettlement within the village to avoid disruption of community life and problem with host community. E8. Income Restoration and Rehabilitation 16. The DPs losing their livelihoods includes titleholders losing land, DPs having commercial structures and employees of the affected structures. In the case of economically displaced persons, the PA will compensate for the loss of income or livelihood sources. The PA will also provide assistance such as, training, and employment opportunities so that they can improve, or at least restore, their income-earning capacity, production levels, and standards of living to pre-displacement levels. There are 28 DHs who will be losing their commercial structures and will be provided with alternative shops to restore income; there are 20 employees who will be entitled to training other than short term assistance. Other categories where income has to be restored are those losing land and tenats losing commercial structure. 17. The entitlement proposed for the project has adequate provisions for restoration of livelihood of the affected communities. The focus of restoration of livelihoods is to ensure that the DPs are able to at least regain their previous living standards. To restore and enhance the economic conditions of the DPs, certain income generation and income restoration programs are incorporated in the RP. To begin with providing employment to the local people during the construction phase will enable them to benefit from the project and keep more of the resources spent on the project in the local economy. It will also give the local communities a greater stake and sense of ownership in the project. The implementing NGO will carry out need assessment and micro plan with training or linking to ongoing income generation training programs and assist in rehabilitation of DPs E9. Resettlement Budget and Financing Plan 18. The costs used for the budget estimates are based on information collected during the census socioeconomic surveys of DPs. The estimated total budget for the implementation of RP is Rs. 265.26. The resettlement cost estimate for this project includes eligible compensation and resettlement assistance. It does not include Operating Costs, NGO and Monitoring Consultant Costs as these costs are for the overall project( this has been estimated Rs. 20 million for the total project). The unit cost for land and other assets in this budget has been derived through consultation with SDRC/PIU. Contingency provisions have also been made to take into account variations from this estimate. A summary R & R cost is given in Table E-3. Table E-3 R & R Budget Item (in Rs) 1 Compensation for land 81,170,000.00 2 Alternative site cost 5,710,000.00 3 Compensation for private structure 53,585,830.00 4 R & R Assistance 100,688,300.00 5 Contingency (10%) 24115413.00 6 Total 265,269,543.00 E10. Grievance Redress Mechanisms 19. The project will establish a Grievance Redressal process, with district-level committees. Each District Grievance Redressal Committee will have representation from the local affected population and the NGOs involved in RP implementation. These committees will hear complaints and facilitate solutions; and the process, as a whole, will promote dispute settlement through mediation to reduce unnecessary litigation. The Deputy Commissioner will be the Chairman of the Grievance Redressal Committe; an Academician (To be selected by DC) will be Member; (iii) A representative of DP (To be selected by DC) will be Member and (iv)Executive Engineer of the concerned Division will be Convener . The GRC will be established at the district level with the primary objective of providing a mechanism to mediate conflict and cut down on lengthy litigation. It will also provide people, who might have objections or concerns about their assistance, a public forum to raise their objections and through conflict resolution, address these issues adequately. The GRCs will continue to function, for the benefit of the displaced persons, during the entire life of the project including the defects liability periods. 20. The Grievance Committees will meet regularly during implementation of the RP, at least once a month. The committees will suggest corrective measures at the field level itself and fix responsibilities for implementation of its decisions. However the NGOs will form the first level of intervention in resolving DP related grievances and attempt to motivate the DP to facilitate implementation of the R & R program. The option of contacting the project authorities is available to DPs at any time. The Deputy Commissioner will be the Appellate Authority. At the first level intervention the NGO will attempt to resolve the grievance; Next the CAO will attempt to address land related grievance and the ADSW will address the non- land related grievances; the next option will be to approach the Grievance Redressal Committee; followed by the Regional Commissioner who is the Appellate Authority; If all the above fails, the DPs can approach the court. It is the responsibility of the SDRC/NGO to inform the affected persons of the GRC, to make it effective. Taking grievances to Judiciary will be avoided as far possible and the NGO will make utmost efforts at reconciliation at the level of GRC. E11. Institutional Arrangements 21. KSHIP has a dedicated unit called the Social Development and Resettlement Cell (SDRC) within the Project Implementation Unit for the implementation of the RP. All aspects of resettlement and rehabilitation and the delivery of entitlements are managed by Social Development/Resettlement Cell (SDRC). The SDRC facilitates land acquisition and compensation, relocation and resettlement, distribution of assistance for the DPs. The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition. The RP will be implemented by the North Karnataka

xviii

(Hospet) division of PIU; Staffing is complete for the proposed institutional set up. The key SDRC officials are: 22. Special DC Land Acquisition - Special Deputy Commissioner will be the in charge of the overall land acquisition. He will be assisted by two Assistant Commissioners for Land Acquisition who is responsible for all activities related to land acquisition. One Assistant Commissioner will be stationed in the zonal office of North Karnataka (Hospet) and the other one would be stationed at PIU Office (South Zonal Office) in Bangalore. 23. Chief Administrative Officer –The CAO will be responsible for all resettlement and rehabilitation activities. The CAO will also be assisted by the Assistant Director Social Welfare (ADSW) who will be responsible for R & R work. On the land acquisition side CAO and the Assistant Commissioners will be responsible for fixing the negotiated price of the land along with the affected persons according to the Karnataka Highways Act, 1964, and disbursing the compensation. 24. The Assistant Director Social Welfare (ADSW) is responsible for shifting of project affected persons, coordination of disbursement of assistance such as shifting allowance disbursement of funds for income generating programmes, relief assistance, etc. 25. The Resettlement and Rehabilitation Manager will assist the ADSW and coordinate all the rehabilitation work of the SDOs. 26. The ADSW and the Resettlement and Rehabilitation Manager will be assisted by the Social Development Officer (SDO).The SDOs will be assisted by the Social Welfare Inspectors (SWI). The SWIs are supporting staff to SDOs to carry out the functions as per the directions of SDOs. 27. The SDRC will have a Data Management Specialist. The responsibility of this person will be to monitor and update the data of all the project affected persons; to highlight any discrepancy in compensation and paid disbursed; and coordinate the inputs of information from the North and South Divisions to the Central database at PIU at Bangalore. The PIU has already appointed the Consultants for database management. Information is ready to be transferred to the PIU for use in implementation. 28. Involuntary resettlement is a sensitive issue and strong experience in R & R matters along with community related skills will be required by the PIU in order to build a good rapport with the affected community and facilitate satisfactory R & R of the DPs. To overcome this deficiency, two experienced and well-qualified NGO in this field will be engaged to assist the PIUs in the implementation of the RP. The NGO would play the role of a facilitator and will work as a link between the PIU and the affected community. NGO will assist DP in income restoration by preparing micro plan and guiding to access into various ongoing government development schemes and agencies providing financial assistance and loan. Taking into account the significant role of the NGO in RP implementation, it is important to select NGO that are capable, genuine and committed to the tasks assigned in order to ensure the success of the Plan. E12. Implementation Schedule 29. Implementation of RP mainly consists of compensation to be paid for affected structures and rehabilitation and resettlement activities. The time for implementation of resettlement plan will be scheduled as per the overall project implementation. All activities related to the land acquisition and resettlement must be planned to ensure that compensation is paid prior to displacement and commencement of civil works. Public consultation, internal monitoring and grievance redress will be undertaken intermittently throughout the project duration. However, the schedule is subject to modification depending on the progress of the project activities. The civil works contract for each project will only be awarded after all compensation and relocation has been completed for project and rehabilitation measures are in place. The RP preparation and implementation schedule is presented below.

xx

Table E-4: R & R Implementation Schedule

Activity Progress (Year/Quarter) 2009 2010 2011 Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Project Preparation Stage Screen project impact ------Public Consultation on alignment ------Prepare Land Acquisition Plan ------Carry out Census Survey ------Prepare Resettlement Plan (RP) ------RP Implementation Stage Hiring of NGOs for RP Implementation ------Obtaining approval of RP from ADB ------Disclosure of RP ------Public consultation ------Preparation LAP ------Declaration of cut-off date (KHA Notification) ------Payment of compensation ------Taking possession of acquired land ------Handing over the acquired land to contractor ------Rehabilitation of DPs ------Monitoring and Reporting Period Internal monitoring and reporting ------External monitoring and reporting ------E13. Monitoring and Reporting 30. Monitoring involves periodic checking to ascertain whether activities are going according to the plan. It provides the feedback necessary for project management to keep the programmes on schedule. Monitoring provides both working system for project managers and a channel for the resettles to make known their needs and their reactions to resettlement execution. Monitoring exercise will be undertaken both internally and externally. 31. While SDRC/PIU on monthly basis will carry out the project’s internal monitoring and external agency will be appointed for third party monitoring. Monitoring is essentially an exercise in strategic learning that can and should be used for enhancing the quality of RP implementation. There are two types of monitoring being undertaken namely (a) Internal, which is normally carried out by the project authority itself and (b) external or independent monitoring by an external agency. 32. The internal monitoring is a conventional monitoring of government related to physical factors such as, number of households affected, resettled, assistance extended infrastructure facilities provided, etc. and other financial aspects, such as compensation paid, grant extended, etc. the internal monitoring must be simultaneous with the implementation of the Rehabilitation Plan (RP).The objectives of the internal monitoring are: (i) Daily Operations Planning; (ii) Management and Implementation and (iii) Operational Trouble shooting and Feedback. The periodicity of internal monitoring could be daily or weekly depending on the issues and level. 33. An external monitoring agency will be appointed to monitor R & R programmes on semi annaul basis. It should bring the difficulties faced by the DPs to the notice of PIU so as to help in formulating corrective measures. As a feedback to the PIU and other concerned, the external agency should submit semi annaul report report on progress made relating to different aspect of R & R. This will be disclosedon ADB website. The agency will also certify the completion of LA and R & R activities for issuing bid documents and award from LA and R & R point of view.

1 PROJECT DESCRIPTION

Background 1. This package has been selected, for up gradation with a seven meter carriage way. Upgrading will have direct /indirect impact on the population along the project corridor. Common property resources, residential structures, commercial structures are likely to be affected. Non-titleholders within the right of way (ROW) are likely to be displaced. This resettlement plan (RP) includes the baseline socioeconomic survey characteristics of the displaced persons, the Resettlement and Rehabilitation (R & R) Policy provisions and entitlements and outcome of the consultation held with displaced persons and communities. 2. This project is Package AEP 3 comprises of three links: 57 A (Gubbi to Beeragonahalli near Yediyur (NH48)) is 49.03 km in Tumkur District district and crosses Gubbi, Turuvekere and Kunigal taluks; 57 B (Beeragonahalli near Yediyur (NH48)) is 26.43 km in Tumkur and Mandya Districts, crosses Kunigal taluk and 57 C (Dobbespet- Koratagere) is 33.16 km in Mandya District, covering Mandya and Maddur taluks. According to the categorization of taluks given in the High Power Committee for Redressal of Regional Imbalances Report of 2002, package covers (i) two most backward taluk1 (Gubbi and Kunigal); (ii) one more backward taluk (Turuvekere); (iii) one backward taluk (Maddur) and (iv) one relatively developed taluk (Mandya). The location Map of the Project is given in Map 1.

Objectives 3. This RP is project specific, which outlines the extent of impacts due to road improvements on communities and the mitigation of the potential impacts. It details necessary implementation procedures for resettlement and rehabilitation. This RP is prepared in accordance with the stipulations and guide-lines provided in Public Works Departmental Code Government of Karnataka,2, and the project specific Resettlement and Rehabilitation: Principles and Policy Framework for the Karnataka State Highways Improvement Project, The National Resettlement and Resettlement Policy, 2007, and The Asian Development Bank’s Safeguard Policy Statement, 2009. Within this given background the objectives of the RP are:

1 The HPCFRRI report classified taluks in four categories on the basis of the Composite Development Index namely: i) Most backward taluka; ii) More backward taluka; iii) Backward Taluka; and iv) Relatively Developed Taluk A total of 35 relevant indicators covering 5 sectors viz., agriculture and allied; industry, trade and finance; infrastructure (economic); infrastructure (social) and population characteristics were considered for analysis in the report. This indicator was used to compute a Comprehensive Composite Development Index (CCDI) for each taluk. The Committee also attempted a study of imbalances from the deprivation end in respect of six important basic minimum needs to gain a qualitative understanding of the problem. Those six basic minimum needs are:1. Income deprivation - Percentage of households (rural) below poverty line.2.Unsafe deliveries - Percentage of deliveries not attended by trained health personnel. 3. Unsafe Drinking water - Percentage of habitations not fully covered by safe drinking water facility.4. Malnourished Children below age group 5 - Percentage of moderately and severely malnourished children. 5. Children out of school in the age group of 6-14 years- Percentage of children out of school in the age group of 6-14 years. 6. Gender Gaps in literacy- Literacy rate (Male-female)

2 PWD Departmental Code is in the process of being finalized. 2

a. to identify adverse impacts and determine how they could be overcome or substantially mitigated with the implementation of Karnataka State Highways Improvement Project II; b. to present the entitlements for the affected persons for payment of compensation and assistance for establishing the livelihoods and ; c. to present an action plan for the delivery of compensation and assistance in accordance with the policy adopted for the project. d. to prepare an action plan for the project affected people for improving or at least retaining the living standards in the post resettlement period. 3

Figure 1-1: KSHIP Roads

4

Physical Characteristics of the project area 4. This project passes over the Southern Karnataka Plateau which covers the districts of Bangalore, Bangalore Rural, Hassan, Kodagu, Kolar, Mandya, Mysore, Chamarajanagar and Tumkur. This region largely covers the area of the Cauvery basin lying in Karnataka. It is bounded by 600 meters contour and is characterized by a higher degree of slope. In the west and south it is enclosed by the ranges of Western Ghats and the northern part is an interrupted but clearly identifiable high plateau. In the east the valleys of the Cauvery and its tributaries open out to form undulating plains. The general elevation of the region varies from 600 to 900 meters. However residual heights of 1,500 to 1,750 meters are found in the Biligirirangan hills of Mysore district and the Brahmagiri range of Kodagu district. In these region major crops grown are Sugarcane, Paddy, Ragi, Coconut, Areca nut, Vegetables, Groundnut, Mulbury plants and Maize.

Project Components 5. As the existing ROW is not uniform the additional requirement varies for a minimum of 12m upto 30 m corridor of impact (COI). Key activities for road improvement involves (i) widening/strengthening of the road upto two lane divided carriageway configuration, (ii) improving road geometry, (iii) laying of embankment, (iv) rehabilitation and construction of new bridges and other cross drainage structures, (v) construction of side drains, (vi) construction of ROBs, (vii) junctions/intersections improvement, (viii) provision of service roads, underpasses and way side amenities, etc. The project activities are described below.

Road Configuration: 6. Link 57A is designed at three million standard axle (msa) and three msa for Bituminous and Granular respectively. Rural Cross Section with Earthern Shoulders (RCSES) is proposed for 44.26 km and Urban Cross Section (UCS) 1 for 4.77 km length. 7. Link 57B is designed at seven msa and 19 msa for Bituminous and Granular respectively. Rural Cross Section with Paved Shoulders (RCSPS) is proposed for 0.13 km, RCSES for 23.27 km and UCS1 for 3.03 km length. 8. Link 57C is designed at four msa and 10 msa for Bituminous and Granular respectively. RCSPS is proposed for 25.64 km and UCS1 for 7.52 km length.

Realignment / Bypasses: 9. Link 57A: There are six major realignments (1.35 km in total) proposed. 10. Link 57B: There are two major realignments (0.35 km in total) proposed. 11. Link 57C: There are 19 major realignments (4.21 km in total) proposed.

Bridges and other Cross Drainage structures: 12. Link 57A: Eight minor bridges and 54 culverts are proposed for reconstruction 13. Link 57B: One major bridge, seven minor bridges and 76 culverts are proposed for reconstruction. 5

14. Link 57C: One major bridge, six minor bridges and 92 culverts are proposed for reconstruction.

Road Side Drainage: 15. Link 57 A: Unlined drain is proposed in rural section and both covered / uncovered drains are provided in town and village sections. 16. Link 57 B: Unlined drain is proposed in rural section and both covered / uncovered drains are provided in town and village sections. 17. Link 57C: Unlined drain is proposed in rural section and both covered / uncovered drains are provided in town and village sections.

Railway over Bridges (ROB’s): 18. Link 57A: There are no ROB’s proposed. 19. Link 57B: There are no ROB’s proposed. 20. Link 57C: There are no ROB’s proposed.

Junctions / Intersection improvements: 21. Link 57A: There are four major and 16 minor junctions proposed for improvement. 22. Link 57B: There are two major and eight minor junctions proposed for improvement. 23. Link 57C: There are three major and 53 minor junctions proposed for improvement.

Service roads and underpasses: 24. Link 57A: There are no service roads and underpasses proposed. 25. Link 57B: There are no service roads and underpasses proposed. 26. Link 57C: There are no service roads and underpasses proposed

Way side amenities / Toll plaza / Truck parking, etc.: 27. Link 57A: There are 10 bus bays with passenger shelter proposed. 28. Link 57B: There are four bus bays with passenger shelter proposed. 29. Link 57C: There are 18 bus bays with passenger shelter proposed

Magnitude of impacts 30. The project will impact 9156 DPs and 2590 DHs. The total private land acquisition for the project is 18.17 acres.

6

Table 1-1: Summary Tables on Impacts Land Land Community Acquisition Transfer – Displaced Displaced Link List of villages Assets - Private Government households Persons (Nos) (Ac) ( Ac) 57A Ajjanahalli, 31.34 0.00 848 2,802 91 Amanakere Beeraganahalli, Beluru C S Pura, C S Pura A. Kere, Chikkonahalli Dodda Madure, Dodderi G , G. Doddari Gubbi, Gubbi Amanakere, Haruvesandra, Hemasagara, Hindisakere, Hindisakere Kaval, Jaladigere, Jannenahalli K G Temple, K Harivesandra, K Kallahalli, K S Palya Kallahalli, Kallur, Kattigenahalli, Kenchaveeranahalli, Kenchaveeranahalli Gate, Kodipalya Koppa, Koppa Cross, Kunala, Lenkanahalli Lingammanahalli, Nagegowdanapalya Narigehalli, Neralahalli Padugudi, Sheshapura Shettigondanahalli Surigenahalli, Surigenahalli Kaval

57B Amruthuru, Arjunahalli, 19.30 0.00 586 2,130 65 Benavara, Benavarakoppalu, Chakanahalli, Chikkanahalli, Chinavara, Hanchipura, Hanumanthapura, Hanumapura, Hosakere, Jinnagara, Mangala, Markenahalli, Sanaba, Shanuboganahalli, Sunnadapura, Tigaralapalya, Yachanahalli, Yadavani, Yediyur 7

Land Land Community Acquisition Transfer – Displaced Displaced Link List of villages Assets - Private Government households Persons (Nos) (Ac) ( Ac) 57C Anasosalu, 29.33 0.00 1156 4224 101 Ankannana Doddi Challanayakanahalli, Chandagalu,Chikkabal li Chikkabanasavadi, D Malligere, Dodda Banasavadi, G Hoshalli Hallegere, Honaganahalli, Hosagavi, Kalmaddi Doddi, Keregodu, Kommerahalli Kowdley, Mandya, Marilingana Doddi S I Kodihalli, Sathanuru TOTAL 81.17 0.00 2590 9156 257

Table 1-2: Categories of DHs and losses

Sl. Extent of Loss Titleholders Tenant Squatter Encroacher No. 123140Losing Total House 2Losing Total Com. Struc. 16 0 134 1 30000Losing Total House and Com. Struc. 405200Tenants Losing Total Livelihood 50000Losing Total Land 6Losing only Part of House 124 6 2 0 724150Losing Part of Com. Struc. Losing Part of House and Com. 84000 Structure. 913000Patrial Plot 10Total Boundary Wall 13 0 0 0 11Partial Boundary Wall 2 0 0 0 12Cattleshed 10 0 1 0 13Losing Partial Land 2081 0 0 0 14Others 67 0 0 6 Total 2377 60 146 7

Minimizing impacts 31. The following design alterations have been proposed to minimize the impacts of the Project.

Mitigation through realignments/bypasses and Design Alteration 32. There are a few built up places/villages/towns where the road improvement will have adverse impacts on structures and livelihood of the people. In such cases realignments have

8 been proposed. This design and planning measure has helped to reduce the negative impact on structures and livelihood of the people.

Design Cross-Sections 33. There are eleven types of typical road cross sections proposed for upgrading roads. Distinct design approaches have been followed to minimize negative impacts on the people. In this package there are 5 cross section used. The Typical road cross section for upgrading roads is given in Annex 1. (i) UR 1 A Rural Cross section: This has a 7.0 m paved carriage way, with 1.5 m paved shoulder and 1.0 m earthern shoulder on either side. (ii) UR 1 B Rural Cross section: This has a 7.0 mts paved carriage way, with 2.5 mts unpaved shoulder on either side. (iii) UR 2 Rural Cross section (through village): This has a 7.0 mts paved carriage way, with minimum 2.5 mts to a maximum of 4.5 mts paved shoulder and 1.0 mts uncovered drains on each side. (iv) UR 3 Urban Cross section in Built up area (with covered drain): This has a 7.0 mts paved carriage way, with minimum 2.5 mts to a maximum of 4.5 mts paved shoulder and 2.0 mts footpath on either side, with the drains below the foot path. (iv) UR 7 Rural Cross section in Cutting: This has a 7.0 mts paved carriage way, with 1.5 mts paved shoulder and 1.0 mts paver block shoulder on each side, beyond which there is 0.8mt concrete drain and 0.5 mts benching.

Mitigation through Design Cross Section 34. The changes that have been considered in the project through good designs to mitigate social impacts include: - Avoiding unnecessary displacement by modifying project alignments, reducing the width of the corridor of impact, or modifying design based on rural and urban cross sections. At built up/ village sections where the road width is insufficient for expansion, design alternatives include reduction of COI. In Yedavani a realignment has been proposed for 1.035 km to avoid the viallge. - Smoothening of curves and bends for better geometric design. In case where it affects settlements, alignment changes were done. - Minimal impact on residential and commercial structures thus minimising resettlement and loss of livelihood. - Paved shoulders to be maintained as far as possible to facilitate movement of non-motorised traffic. - Reducing design speed in built up areas; - Reducing impacts on existing shrines and worship places; - Providing suitable safety measures, such as speed reductions near schools and hospitals; 9

- Minimising the raising of roads in urban areas to prevent water seepage to the houses adjoining the roads and ; - Providing access to businesses and residential units that would be otherwise impacted by construction; and minimising losses of public and private property, such as tube wells, tree plantations and other common property resources within the ROW, by minimising the width to be cleared.

Road safety and Traffic Management measures 35. During the consultations safety of the roadside communities has been found to be a major concern. A number of measures have been proposed to reduce the risk of traffic accidents Traffic safety measures included: Conducting “Road safety Audits” has become a key responsibility as part of the Highway Designs. Various road safety appurtenances, which should be adopted as a part of improving the safety in the road design, are adopted in the project road designs: 36. Road furniture details include: road markings; cautionary, mandatory and informatory signs; KM stones and 200m stones; delineators and object markers; guard posts and crash barriers; road humps and rumble strips; reflective pavement markers (RPM) and Chevron signs and median and footpath barriers. In addition bus bays, parking bays, truck lay byes with rest areas and detailed improvements to major and minor intersections on the project road coupled with identification of black spots are being dealt with.

Magnitude of Impacts Cultural properties and CPRs 37. There are no sites of archaeological importance or sacred groves within the COI for this link. The project authorities would relocate cultural properties in alternative site such as places of worship which are getting totally affected. The identification of alternative site will be done by the NGO/ support agency in consultation with the local user population of that particular cultural property. The alternative site for construction will be provided by the GOK. In case government land is not available, the project authorities will have to buy land to replace the cultural property. If the cultural properties are partially affected the project authorities will compensate only the affected portion. 38. The project will impact 257 community structures. There are: five primary schools, where only the boundary wall s are getting affected, 29 temples, nine aralikatte, 16 bus shelters, 47 hand pumps, 36 mini water supply tanks, 52 bore wells, 22 water tanks, etc. There are some structures which are getting partially affected. The details of community structure are given in Annex 2. 39. All community assets getting affected need to be relocated before commencement of civil works. The broad timetable for relocation of community assets is given in the Implementation Schedule. The relocation of the community assets needs to be undertaken concurrently in all the contract packages. The project authority will be responsible for the construction of the affected community assets. The relocated community assets would be handed over to the local community/trust for maintenance. 40. All hand pumps getting affected will be located depending on availability and depth of water table. Water points, public taps and wells getting affected will also be similarly relocated. All affected aralikattes, will be built by the project authorities, and in sites identified

10 by the project-affected groups and the co-ordinating NGO/ support agency for implementation. The project authorities will relocate all the bus shelters getting affected by widening of the road. The location of the bus shelter were decided on the basis of the frequency of usage arrived through the consultative process of the users and design requirements.

Impact of the project 41. The proposed project can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the project will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace which in turn increases the income of the locals, and ultimately elevating their standard of living. The outcome of the project will include: (i) The project will serve villages with better access and enhanced mobility. Improved backward taluk connectivity will facilitate travel to taluk head quarters and other local government/development agencies. In places where the connectivity is poor the project will provide better access to amenities such as health, education, town/market and improved social networking. (ii) The project will improve the accessibility of the population along the project corridor to education, health, employment, trading opportunities and in the long run help towards poverty alleviation. (iii) The project will help to increase new economic and employment opportunities by providing improved linkages to markets, production centers and other areas of economic opportunities. Better and quicker transportation would help the rural population to transport their produce faster and get more profit margins instead of depending solely on local ‘markets’ and middlemen. (iv) Women will benefit, as their mobility will be facilitated both in terms of access to social services, as well as access to higher levels of schooling. Women’s access to higher levels of health care outside the village will also improve considerably. (v) Targeted assistance will be provided to vulnerable groups including below poverty line households, women-headed households, and handicapped persons, through the Resettlement Policy. 42. The likely adverse impacts of the project are: Potential adverse impacts associated with the project is (i) land acquisition; and (ii) loss of livelihood and overall the proposed project will bring in economic and social changes, which in turn would bring economic prosperity and would lead to poverty alleviation.

Right of Way and Corridor of Impact 43. The right of way is the lawfully acquired corridor of public land owned by the State Government and administered by the PWD for the transit of the existing road. Using available records with the PWD and the Revenue Department, the social team verified the boundaries of private properties within and in the vicinity of likely corridor of impact. The 11 preparation of the Land Acquisition Plan is being facilitated through the verification of land records, updated records for the ownership of land. 44. For this project, preparation of RP associated with displacement is limited to the corridor of impact. The COI is the width required for the actual construction of the road, including carriageway, shoulder, embankments and longitudinal drainage. Within this corridor there should be no structures or hindrances. The objective of social input to project design is to ensure that the corridor of impact is reduced, within acceptable design principles and standards, to minimize displacement and other project impacts. Those affected between the corridor of impact and right of way during the lifetime of the project will be assisted in line with this project Entitlement Policy, if they are required to be affected for any additional work required for this project.

12

2 METHODOLOGY FOR IMPACT ASSESSMENT

Social Impact Assessment 45. A Poverty and Social Assessment (PSA) was carried out for the project road. The PSA study looked into the likely impacts of road improvement on the communities, and the likely mitigation aspects of the impacts. It also looked into the impact of the project especially on the backward taluks through which the project road passes, and how the road project is likely to affect the impacted population. The study was based on extensive public consultations and stakeholders view. 46. The negative social impact identified by community members was the potential for loss of land to project interventions. However, according to a majority of stakeholders consulted, the benefits of the project outweigh impacts from minor losses of land. There was broad consensus in all these communities that dry land acquired by the project would not be a problem, people were reluctant to part with irrigated or garden lands. To overcome any resistance it was informed that according to the entitlement policy land losers will be given market value of land after negotiation under the KHA.1964. Recommendations for impact mitigation and enhancement entitlements were given by the stakeholders. The suggestions as feasible have been incorporated into the design.

Approach to Resettlement Planning 47. During the census survey it was seen that road widening and improvement will have some impact on residences, businesses, shrines, places of worship, agricultural land, community assets. Most of the infrastructure work planned for the project as far as possible will take place within the established ROW. In most cases, the land required for the project is immediately adjacent to the current carriageway. The additional land required by the project falls under several classifications: (i)Public land owned by the State Government and administered by other Departments such as Revenue; (ii) Public land owned by villages or other local governments; and (iii) Private land. 48. The RP is prepared to ensure that: a. The displaced persons are: (i) informed about their options and rights pertaining to resettlement; (ii) consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives; and (iii) provided prompt and effective compensation at full replacement cost for losses of assets attributable directly to the project; b. Displaced persons are: (i) provided assistance (such as shifting allowance, transition allowance, economic rehabilitation grant etc.) during relocation; and (ii) provided with residential housing, or housing sites, or, as required compensated for agricultural sites; c. To ensure that displaced persons are : i) offered support after displacement, for a transition period, to restore their livelihood and standards of living; (ii) provide with development assistance in addition to compensation measures, such as credit facilities, training, or job opportunities; and (iii) at least improving or retaining the living standards in the post resettlement period. 13

Census Socioeconomic Survey 49. As a part of the project a census survey of displaced households/persons (DHs and DPs) was carried out. The findings of the census survey provided the magnitude of social impacts on the DHs and DPs. In this section the survey outcomes are analysed. The census information helped to generate necessary data/input for the preparation of this Resettlement Plan. The Census Survey Schedule is given in Annex 3. The surveys provide a baseline measurement of potential impacts on displaced household/persons that form the eligibility criteria for entitlement as given in the R & R Policy of KSHIP. The objectives of the census verification were:(i) provide information regarding project impacts in order to facilitate designing of various components of the RP, especially R&R entitlement; (ii) minimise the influx of outsiders to the affected area; (iii) Identification of DPs by effect categories; and (iv) Enumeration of DPs assets and land holdings; 50. The project will impact the following persons: Table 2-1: Distribution of DHs Link Titleholder Tenant Squatter Encroacher 57A 796 7 45 0 57B 570 4 12 0 57C 1011 49 89 7 TOTAL 2377 60 146 7 Source: Census Socioeconomic Survey 2009 -2010.

Methodology and Database 51. Census covers 100% of the potentially affected population within the likely COI. It provides a demographic overview of the population served by the RP and profiles household assets and main sources of livelihood. During census survey, legal boundaries of affected properties were verified. The census registered all household members and individuals within the potential COI their assets and income, and demographic and social information to determine whether project affected persons were to be categorised as vulnerable groups with special entitlements under the project. Private land owners, tenants, squatters and encroachers within the COI were covered. Structures, trees and other assets were also recorded. 52. Data was collected at the following levels: (i) household level interviews with each affected household were undertaken. Each of the households surveyed and the structure/agricultural land likely to be affected by the project has been numbered, documented and photographed; (ii) village level public consultations were conducted. 53. A database has been created for the census information. The information has been stored and analysed using Visual Basic and MS-Access. This program is easily convertible to Oracle platform. The superimposition of the survey data on the final engineering designs will provide the actual number of DPs. Only these DPs within the final COI will be considered eligible for support under the project.

Sources of Data 54. Data was collected was collected from the following secondary sources: (i) Revenue records at local/village level - with regard to land particulars for acquisition of properties;(ii) Census records for demographic information; (iii) PWD for ROW/COI, estimates of the cost

14 of infrastructure development etc.; (iii) Development agencies to get information on various developmental programs for specific sections of population like landless, marginal and small farmers etc. tribal, SCs etc.; and (iv)Local organisations’ including NGO’s in order to involve them and integrate their activities in the economic development programs of the displaced population. 15

3 SOCIOECONOMIC INFORMATION AND PROFILE

Socioeconomic profile of the project area 55. The road connects two National Highways and the Bangalore-Mysore road and serves a population of 2, 27,586 persons. The total female population varies between 49 % in Link 57 A to 51 % Link 57 B. In Link 57 A, Gubbi town accounts for 40% of the total population of the link. In Link 57 C, the town of Mandya accounts for 78.7 % of the total population. The Schedule Caste population varies from 12 % of the total population in Link 57 A to 15 % in Link 57 B. The female Schedule Caste population to the total female population also follows the same trend. The overall Scheduled tribe population in the corridor is low, it varies from 0.8 % in Link 57 C to 3 % Link 57A. The female Schedule tribe population to the total female population is the same. This corridor passes through the districts of Tumkur and Mandya where the overall literacy levels are at 67 % and 61 % respectively. The literacy rate in the corridor varies from 56 % in Link 57 B to 68 % in Link 57 C. The female literacy level varies from a low of 47 % in Link 57 B to 62 % in Link 57 C. The overall work force participation rate in this corridor varies from 36% in Corridor 57 C to 48.9 % in Link 57 B. The female workforce participation rate varies from a low of 17 % in Link 57 C to 38 % in Link 57 B. Links 57 B and C is dry agricultural belt. Unirrigated area varies from 51 % in Link 57 A to 27 % in both Links B and C. In Link 57 C, towards Mandya, sugarcane and paddy is grown. 56. Accessibility to primary schools is poor with only two villages in the corridor having access within 5 km. Access to Middle schools, is marginally better with 8 villages having access within 5 kms. Access to basic health facilities and other facilities is average. Majority of the villages have to nearest towns, which are beyond 10 kms. The nearest towns in Link 57 A are Gubbi, Turuvekere and Kunigal. G.dodderi village, in Link 57 A is 28 kms away from the nearest town Turuvekere. The nearest towns in Link 57 B are Kunigal, Aimanagala and Maddur. The nearest accessible town to Kowdley village is Maddur which is 32 kms away. The nearest towns in Link 57 C are Maddur and Mandya

Socioeconomic profile of displaced population 57. The key socioeconomic characteristics of the displaced population are discussed below. 58. Social Stratification: Scheduled Caste households account for 6.57 % of the population; Scheduled tribe households account for only 0.39 % of the total population; the remaining are from the general category. Table 3-1: Social Stratification Link SC ST General Total No. No. % No. % No. % No. 57A 36 6.75 5 0.94 492 92.31 533 57B 35 8.54 0 0.00 375 91.46 410 57C 46 5.48 2 0.24 791 94.28 839 Total 117 6.577 0.39 1658 93.04 1782 59. Religious Group: Among religious groups, Hindus dominate with 97.92%, the remaining are Muslims.

16

Table 3-2: Religion

Link Hindu Muslim Christian Jain Total No. No. % No. % No. % No. % No. 57A 500 93.81 33 6.19 0 0.00 0 0.00 533 57B 408 99.51 2 0.49 0 0.00 0 0.00 410 57C 837 99.76 2 0.24 0 0.00 0 0.00 839 Total 1745 97.92 37 2.08 0 0.00 0 0.00 1782

60. Occupation: Distribution of DPs by occupation reveals that agriculture accounts for 72.14%; the other sector, which supports a large section of DHs, is agriculture labour accounting for 12.41%; trade/commerce account for 6.67%. Table 3-3: Occupation Distribution Allied HH Link Agriculture Agri. Agriculture % % % Service % Indust % No. Labour Activitie ries s 57A 738 70.89 174 16.71 0 0.00 15 1.44 3 0.29 57B 649 78.95 86 10.46 0 0.00 13 1.58 0 0.00 57C 1078 69.37 164 10.55 2 0.13 43 2.77 0 0.00 Total 2465 72.14 424 12.41 2 0.06 71 2.08 3 0.09 Cont.. Link Commerce/ Profess Skilled Artisa Other % % % % % Total No. Trade ional Labour ns s

57A 61 5.86 3 0.29 2 0.19 0 0.00 45 4.32 1041 57B 24 2.92 0 0.00 0 0.00 0 0.00 50 6.08 822 57C 143 9.20 2 0.13 1 0.06 0 0.00 121 7.79 1554 Total 228 6.67 5 0.15 3 0.09 0 0.00 216 6.32 3417 61. Income level: In spite of difficulties in getting reliable data on household income efforts were made to persuade the respondents to report as accurate data as possible. 43.35% of the general population has income less than Rs.26,000. Of the nine ST households seven households earn less than Rs.26,000. The income information has been segregated for ST, SC and general category. Table 3-4: Income Distribution Schedule Caste

Link 5000 - 11501 - 16001 - 26001 - 40001 - 75001 - Above Total No. %%%%% %% 11500 16000 26000 40000 75000 100000 100000 SC

57A 30 44.12 4 5.88 21 30.88 7 10.29 3 4.41 2 2.94 1 1.47 68 57B 24 32.43 3 4.05 18 24.32 11 14.86 16 21.62 2 2.70 0 0.00 74 57C 21 21.43 8 8.16 30 30.61 16 16.33 6 6.12 3 3.06 14 14.29 98 Total 75 31.25 15 6.25 69 28.75 34 14.17 25 10.42 7 2.92 15 6.25 240 17

Cont… Schedule Tribe 5000 1150 Link 16001 26001 - 1 - 40001 - 75001 - Above Tot_ No. % % - % - % % % % 1150 1600 75000 100000 100000 ST 26000 40000 0 0 57A 0 0.00 0 0.00 1 33.33 0 0.00 2 66.67 0 0.00 0 0.00 3 57B 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 57C 1 16.67 5 83.33 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 6 Total 1 11.11 5 55.56 1 11.11 0 0.00 2 22.22 0 0.00 0 0.00 9

Cont… General

Abov Link 11501 16001 26001 40001 5000 - 75001 - e Tot_ No. % - % - % - % - % % % 11500 100000 1000 O 16000 26000 40000 75000 00

57A 103 16.45 38 6.07 138 22.04 122 19.49 144 23.00 40 6.39 41 6.55 626 57B 48 10.34 22 4.74 162 34.91 85 18.32 114 24.57 19 4.09 14 3.02 464 57C 83 9.67 39 4.55 215 25.06 175 20.40 225 26.22 58 6.76 63 7.34 858 Total 234 12.01 99 5.08 515 26.44 382 19.61 483 24.79 117 6.01 118 6.06 1948 62. Age Classification: 71.49% of the total DPs fall in the age group of 18-59. Since this happens to be the working age-group the mitigation measures as given in the entitlement matrix need to be carefully implemented with reference to 18-59 age groups. Table 3-5: Age Classification Link Below 18 18-60 Above 60 Total No. No. % No. % No. % No. 57A 486 17.34 1940 69.24 376 13.42 2802 57B 331 15.54 1509 70.85 290 13.62 2130 57C 639 15.13 3097 73.32 488 11.55 4224 Total 1456 15.90 6546 71.49 1154 12.60 9156 63. Literacy: Illiterate population accounts for 10.05 % of the surveyed population. Just literate population accounts for 8.86 % of the total population; while primary accounts for 10.00 % of the total population; those with Middle school education account for 13.00 % of the total population; those with education upto secondary level accounts for 28.00 % of the total population. The detail education table with gender wise break up is given below. Graduates account for 8.00 %.

18

64. Table 3-6: Literacy Illiterate Just Literate Primary Middle Link Tot Tot Tot Tot No. M % F % M % F % M % F % M % F % _Ill _JL _P _M 17 33 65.8 14 14 50.8 15 47.9 16 52.0 21 56.2 16 43.7 34.19 503 49.14 291 323 377 57A 2 1 1 3 8 6 5 9 8 1 2 3 5 7 13 24 64.3 10 12 53.0 12 58.0 41.9 13 55.7 10 44.2 35.62 379 46.96 230 91 217 244 57B 5 4 8 8 2 4 6 6 4 6 4 8 6 21 40 65.4 10 15 59.5 17 49.5 17 50.4 28 54.2 24 45.7 34.57 619 40.47 257 343 533 57C 4 5 3 4 3 3 0 6 3 4 9 2 4 8 52 98 150 35 42 54.3 45 51.0 43 48.9 63 55.2 51 44.8 115 Total 34.71 196 45.63 778 883 1 0 1 5 3 7 1 8 2 2 7 0 7 0 4

Cont… Secondary Intermediate Graduate PostGraduate Link No. Tot Tot Tot_P M % F % M % F % Tot_IM M % F % M % F % _S _G G 39. 65.4 63.1 36.8 57A 438 60.08 291 729 180 95 34.55 275 89 52 141 27 77.14 8 22.857 35 92 5 2 8 36. 62.6 68.1 31.8 57B 370 63.57 212 582 149 89 37.39 238 94 44 138 11 84.62 2 15.38 13 43 1 2 8 46. 111 64.2 21 24 61.7 38.2 600 53.67 518 382 35.80 595 ## 397 66 62.26 # 37.74 106 57C 33 8 0 3 5 1 9 42. 242 64.1 39 42 63.3 Total ### 57.97 ### 711 35.83 1108 ## 107 676 ## 224 # 75.978 154 03 9 7 7 8 1

Cont… Link ITI/Diploma Engineer/Doctor Others Total No. M % F % Tot_I/D M % F % Tot_E/D M % F % Tot_O M % F % Tot 57A 17 0.00 1 0 18 1 #### 0 0.00 1 20 00 2 1436 53.28 1259 46.72 2695 57B 6 85.71 1 0 7 2 66.67 1 33.33 3 10 00 1 1138 55.46 914 44.54 2052 57C 35 85.37 6 1 41 18 75.00 6 25.00 24 21 31 5 2125 52.63 1913 47.37 4038 Total 58 171.1 8 1 66 21 75.00 7 58.3 28 5 63.0 3 37.0 8 4699 53.5 4086 46.5 8785 19

65. Structure Type: Of the residential structure 74.68 % are pucca. Amongst commercial structures getting affected only 29.15 % of the structures are pucca. Table 3-7: Type of Structure Residential Link Semi No. Pucca % % Kutcha % Tot_Residential Pucca 57A 23 67.65 11 32.35 0 0.00 34 57B 57 79.17 10 13.89 5 6.94 72 57C 35 72.92 5 10.42 8 16.67 48 Total 115 74.68 26 16.88 13 8.44 154 Cont… Commercial Link Semi No. Pucca % % Kutcha % Tot_Commercial Pucca 57A 9 16.07 3 5.36 44 78.57 56 57B 4 18.18 7 31.82 11 50.00 22 57C 52 35.86 10 6.90 83 57.24 145 Total 65 29.15 20 8.97 138 61.88 223 66. Loss of Commercial structures: Majority, that is, 18 of the commercial structures arepan/cigarette shops; followed by 16 tea stalls; seven grocery shops etc. 67. Access to utilities: Of the total residential structures getting affected 91% have electricity; while only 12% have access to piped water. 68. Household Assets: Among household assets 46.53% of the households have television; 11.04% own two/four wheelers; 8.46 % having cooking gas; 7.30% have telephones and only 5.29 % have refrigerators. Amongst agricultural equipment 8.04% own tractors; 22.6% own bullock carts; and less than 1% own Sprayers.

Vulnerable Groups 69. Those falling within this category include persons such as disabled, widows, or persons above sixty years of age, who are not provided or cannot immediately be provided with alternative livelihood and who are not otherwise covered as part of a household. These persons are entitled to Assistance to include in government pension schemes if not included, if eligible as per Government criteria (OR) Lump-sum amount of Rs. 25,000. There are some DPs that are in more than one vulnerable category. These DPs will be paid only once. There are 438 widows, 50 disabled persons and 1154 DPs over 60 years. Households by gender are given below. Table 3-8: Affected Households by Gender

Link Male Female Total Category No. No. % No. % No. Head of HH 434 82.35 93 17.65 527 57A DPs 2305 82.26 49717.74 2802 Head of HH 318 79.10 84 20.90 402 57B DPs 1657 77.47 48222.53 2139 Head of HH 655 79.49 169 20.51 824 57C DPs 3267 77.16 96722.84 4234

20

Gender Issues 70. There 348 women-headed household. The proposed upgrading of roads under KSHIP is expected to open up new economic opportunities for women to upgrade their skills and also better accessibility to educational and health facilities. The improved road was perceived to help reduce travel time, as an immediate benefit. Women as a segregated class are not involved in any economic activity, which demands attention for their special needs. However, in the village level consultations the women said improved roads were a danger especially in the built up area. Increased speed of traffic makes it difficult for women and children to cross the roads. It also leads to increased accidents as children in villages areas tend to play near the roads. In some links the improved road will lead to the movement of heavy vehicles carrying ore and goods; this was not welcome in the village limits. To ensure that women are secure in receiving payments all benefits will be provided in joint account where the woman will be the first beneficiary accounts. Where ever title is provided it should be provided with joint title with women as the first beneficiary.

Indigenous People 71. In Karnataka, Schedule Tribes (ST) account for 6.55% (3.46 million) of the total State population. Bellary district has the highest concentration of STs in Karnataka. There are 50 major tribes with 109 sub-tribes in the State (as of March 2005), according to the notified Schedule under Article 342 of the Constitution of India. In Karnataka there are fourDistricts which fall under the Integrated Tribal Development Project. These are Mysore, Kodagu, Dakshin Kannada and Chikmagalur. Integrated Tribal Development Projects (ITDPs) are contiguous large areas of the size of one or more Development Block in which the ST population is 50% or more of the total population. Primitive Tribal Groups are found in Chamarajnagar District. The Government of Karnataka has identified (i) Jenu Kuruba; and (ii) Koraga tribes as primitive groups (PTGs). Primitive Tribal Groups (PTGs) are identified isolated communities among the STs characterized by a low rate of population, a pre- agricultural level of technology and extremely low levels of literacy. 72. Jenu Kuruba tribes are originally from Mysore, Chamarajanagar and Kodagu districts and Koraba tribes are from Udupi and Dakshin Kannada districts. In Chamarajanagar district, only Kollegala Taluk has PTG areas. PTGs constitute the most vulnerable among the all notified tribes. 73. None of the ITDP districts nor the PTG district fall within this project road. The Director of Tribal Welfare GoK, has indicated through a letter No: DSTW : TSP:OSCR 12/2010-11 dated 26.04.2010, that no village in the State of Karnataka has been designated as tribal village; and that the project roads are not passing through any ITDP areas. Tribal are living in the villages along the project roads along with other communities. Based on the information provided by the Tribal Department and the Census surveys IPP will not be required 74. There are 9 Scheduled Tribe households getting affected in this package. The Tribal households found in the project area no longer maintain any of the distinctive characteristic mentioned above. During the consultations held there were no specific issues raised by tribal persons/groups. According to the detailed socio economic survey carried out for the poverty and social assessment and the census survey carried out for the preparation of the RPs, the 21

STs identified in the links do not exhibit any of the following characteristics (i) self- identification as members of a distinct indigenous cultural group and recognition of this identity by others; (ii) collective attachment to geographically distinct habitats or ancestral territories in the project area and to the natural resources in these habitats and territories; (iii) customary cultural, economic, social, or political institutions that are separate from those of the dominant society and culture; and (iv) a distinct language, often different from the official language of the country or region. Besides all the STs are predominantly maintaining the similar standards of living which is comparable to the other sections of the community.

22

4 SCOPE OF LAND ACQUISITION AND RESETTLEMENT

Proposed Land Acquisition 75. Land acquisition will be done under the Karnataka Highways Act (KHA), 1964. Under KHA land acquisition will be entrusted to a designated Highway Authority with delegated powers, so that the entire acquisition proceedings will be carried out under centralized agency i.e. Highway Authority with dedicated officials for the purpose of land acquisition, instead of involving many officials of the revenue department. Acquisition under consent award as given under Section 27 of KHA, 1964 will be applicable. This will help in arriving at a mutually agreed rate of compensation with the land owners, which will eliminate resentment from the land owners regarding rate of compensation thus reduce the scope for approaching the civil courts for higher compensation. Section 27 read with Section 26 provides payment of compensation to individuals who are losing land. No other section in the Act deals with payment of compensation determined by way of agreement. Under the KHA in this project the Negotiation Committee after negotiation with the land losers in clusters arrive at a price agreeable to the land losers. Once the price is agreed for individual survey numbers accordingly an agreement will be executed with the land losers. Subsequently the land will be taken possession of. In this process no award is passed. Generally this process is termed consent award. 76. The summary and main features on comparison between LAA and KHA are: 1. Time taken under ideal situation for land acquisition under KHA,1964 is 63 weeks as against 94 weeks for LA Act 1894; 2. The Project Director is designated as “Highway Authority” and in charge of LA. However, the land acquisition under LA Act, 1894 needs to pass through a set of departmental procedure and officials who are often busy with their primary departmental duties. 3. The proposal of land acquisitions under LAA 1894 needs to pass through six offices i.e. the acquiring body, the Tahlisdar, the Assistant Commissioner, the Deputy Commissioner, the survey department and finally the Government which is not only time consuming but also a tedious process. It is also relevant to mention here that even for small clarifications the file has to go through all these offices which cause unavoidable delay in file processing. Under KHA, 1964 the Project will have dedicated officers designated solely for this task, as a result of which the LA process will be faster and better streamlined. The land acquisition under KHA, 1964 would involve two agencies namely the Highway Authority” and “Government”. 77. The process of Land Acquisition under KHA, 1964 is as follows: 1. On the recommendations of the “Highway Authority”, the “State Government” will issue a notification for acquisition of the required land, which will be published in the Gazette (Section 15). 2. After publication of notification Under Section 15 of KHA, 1964, the Highway Authority will cause the land to be measured (Section 16). 23

3. Under Section 17 of KHA, 1964, public notice will be issued to all the interested persons to file their claim for compensation within 15 days from the date of receipt of notice. 4. At any time after the publication of notification under section 15(on receiving report from the Highway Authority), the State Government. may direct that the lands specified in the notification shall be taken possession of, from such date as may be specified in the direction. From such date, the said land vest absolutely in the State Government. free from all encumbrances (Section 19). This process would take place only after completion of awards in every case. 5. Consequent to notification under section 15 and after obtaining documents from the land losers the “Highway Authority” will proceed to pass award on consent basis if there is consensus for a mutually agreed rate for consent award (section 27). 6. In default of consensus the “Highway Authority” will proceed to fix the compensation on general award basis (Section 28). 7. There is also provision for making reference against the award of the “Highway Authority” before the court of law (Section35).

Estimated time for LA 78. From the issue of Section 15 the time taken to complete the land acquisition process is 6 months. Anticipated time to be taken for each stage of acquisition proceedings under KHA 1964 is as follows: 1. Section 15: After issue of section 15 notification, 45 days is given for filing claims. 2. Section 17: public notice and notice to individual land losers to file his claims within a specific date mentioned therein the notice. 3. Framing of award: Framing of award under section 27, 28 and taking possession of land -12 weeks 4. Section 19: From section 15 notification to issue of direction under section 19 for taking possession of the land – 24 weeks

Managing Land Acquisition 79. The GOK has designated the Project Director (PD) as Highway Authority under Section 6 of KHA, as per GO Order No.PWD 49 EAP 2008 dated 02.12.2008. 80. The Special DC Land Acquisition (LA) and the Project Director are the award approving authority. The Special DC LA can approve award up to Rs.50 lakhs. Above Rs.50 lakhs and upto Rs.One crore the authority rests with the Project Director.

Staffing for Land Acquisition Work 81. The Special DC Land Acquisition will be in charge of Land Acquisition. To execute the LA work efficiently the GoK has issued orders for the appointment of supporting staff for LA. 82. The Special DC LA will be assisted by two Assistant Commissioners.

24

Negotiations Committee for Land Price Fixation and determination of Replacement Cost 83. Under the KHA, 1964 the negotiation of compensation is the most important task. The determination of replacement cost is the foundation for the purpose of compensation by agreement or consent award. Replacement Cost of land for consent award will be determined through negotiations between the land losers and the Negotiation Committee. The price of land has generally been seen more than the market value derived adopting the procedure land down in the LA Act 1894. Since land acquisition proceedings are quasi judicial proceedings offering a minimum price before the award can be passed will not be a fair act for the proceedings. The composition of the committee is given below.

Negotiation Committee  Assistant Commissioner of the concerned Sub Division Chairman  Assistant Commissioner of KSHIP Secretary  Jurisdictional Executive Engineer Member  Zilla Panchayat Member of the concerned jurisdiction Member 84. The Guidance Value as per the Department of Stamps and Registration for the different categories of land, for the villages along the project road will be obtained from concerned District Registrars. This guidance value will be referred to by the Negotiation Committee. 85. At this stage it is not possible to identify the exact owner of the land getting affected. Surveys has been done for all households in the given survey number going to get affected. This will be known after Section 19 Notification under KHA is complete. The details of those losing land are given in Annex 4. Table 4-1: Land Acquisition Details Government Private land Total Land Link Details Land (Acres) (Acres) (Acres) Gubbi- Beeragonahalli near 57A 31.34 0.00 31.34 Yediyur (NH 48) Beeragonahalli near Yediyur 57B 19.30 0.00 19.30 (NH 48) to Kowdley 57C Kowdley to Mandya 29.33 0.00 29.33 TOTAL 81.17 0.00 81.17

Method of Price fixation 1. The concerned Land Acquisition officer who is the member secretary of the Negotiation Committee will call for a meeting; 2. Dates for price negotiation will be given village wise. Negotiation will be conducted village wise calling all the land losers together for negotiation. This is to ensure transparency. 3. The PIU will provide information on the guidance value of the land to land losers before negotiations. 4. For the Districts of Bangalore Urban, Bangalore Rural, Chikkaballapur, Kolar, Ramnagaram, Mysore, Davangere, Belgaum and Dakshin Kannada the minimum 25

negotiation price will be one and half times the Guidance Value. For all the other districts other than those mentioned the minimum price will be twice the guidance value. 5. The Negotiation Committee will negotiate the price with the landlord; 6. Based on the decision of the Negotiation Committee the Special Land Acquisition Officer will give the compensation. 7. Compensation will be given within 30 days of taking possession and receiving all the necessary documents1 by the Special LA officer. In case of delay a 9% interest will be given to the beneficiary upto a period of one year after which it will be increased to15% thereafter. (This is as per the provisions of the LA Act). 8. On approval of the award by the Special DC or PD, the Special Land Acquisition Officers will make the payments accordingly. 9. Possession of Land will be taken vide Section 19, which will be only after the payment of compensation.

Failure of KHA and Appellate Committee 86. In the event the land lord does not agree with the rate negotiated by the Negotiation Committee the award will be passed in the traditional general LA method and the amount will be deposited with the court. The provisions of the Amendment Bill will be followed as necessary.

Valuation of Assets 87. The valuation of structures and other assets will be carried out by Government approved valuators appointed by the PIU. Valuation will be done on the basis of current PWD Schedule of Rates, without depreciation, which is at replacement cost. Based on the valuation another 30 % will be given as top up. Trees will be valued by the Horticulture/Forest department.

Cut-Off Date 88. The cut off date for those who have legal title is the date of Notification under Section 15 of Karnataka Highway Act 1964. The date of census is the cut-off date for those who do not have legal standing for eligibility of assistance under the project. People moving into the COI after this cut-off date will not be entitled to support. It is the responsibility of the PWD to ensure that the COI is maintained free of squatters and encroachers. 89. It is recognised that there will be a margin of error in the census, and any person who was not enumerated but can show documentation or evidence that he/she is rightfully an entitled person will also be included. The Project Implementation Unit is responsible for such verification. A cut off date slip was issued to the non titled people surveyed. The cut off date for non- title-holders, is the date of the start of the census survey on a particular link. The cut-off date for link 57 A is 14.02.2009, for 57B it is 16.02.2009 and for 57C it is 11.02.2008.

1 Documents to be furnished include Phani (RTC), Mutation Extract, Vamsha Ruksha (Geneological Tree) and if the interest of land holder is subject to a court decree, a certified copy of such a decree.

26

The details of displaced persons whose structure/assets are getting as on the cut off date are given in Annex 5.

Estimation of land requirement and Preparation of Land Acquisition Plans 90. The Land Acquisition Plan (LAP) for the link road is under preparation. Coordination with revenue department is in progress. The likely time table for procurement for land acquisition is placed in the implementation schedule. 91. The preparation process of LAP includes: a. From the Land Record office Village map, tippany, hissa tippany, akar band is collected. b. RTC records is collected from the Taluk Office c. Based on the above documents and spot inspection sketches for LA are made d. Calculation of land acquisition requirement in a particular survey number is arrived based on the akarband ; e. Field verification of RoW is done from PWD notifications; f. Identify and Stakeout on ground of the areas beyond RoW where private land needs to be acquired as per approved proposed alignment designs; g. Measurement of land proposed to be acquired to be done along with the Revenue Department. This is done in coordination with Project Consultants, PIU staff and revenue officials. h. After field verification land particulars are transferred to each survey sketch; i. The LA plans have to be finally signed by the Surveyor, Supervisor, Tahsildar and; KSHIP AE, KSHIP AEE and Project Consultants.

Compensation Payment Process 92. The compensation payment process includes: a. Compensation to be finalized by the Negotiation Committee with the consent of displaced person. b. The award will be approved by the Special DC LA or Project Director depending on the award amount. c. Cheque payment will be done. The SDRC will assist beneficiaries to open a Bank account incase they do not have Bank Account.

Administering the payment of R & R Assistance  All Entitlements to be provided will be verified against losses incurred by the NGO;  Information will be updated in the database,  Bank accounts are to be opened for all beneficiaries;  The CAO will authorize payment of R & R assistance.  All payments will be made through Cheque, directly to the DPs. DPs who are in more than one vulnerable category will be paid only once. 27

5 STAKEHOLDERS CONSULTATION, PARTICIPATION AND DISCLOSURE

Consultation and Community Participation 93. Public consultations were held in Hindigere in 57 A, in Jinnagara in 57 B and Chandagal in 57 C, focusing on areas of impact due to widening, at places congestion with impacts on buildings and where major common property resources are getting affected- such as any religious structures etc. The out come of the consultations were used for analysis of alternatives and minimising negative impact of the project.

Methodology 94. The methodology followed for public consultations was: 1) Group meetings and one to one consultations were held with the displaced persons. 2) Informing all the likely affected persons regarding the meeting including DPs and at village level. Panchayat leaders, gram sabha members, officers from PWD sub divisions and any local NGOs were also informed about the meetings. 3) The minutes of the meetings have been recorded, list of participants for each of the meeting along with the signature have been obtained and the photographs of consultations have also been taken. The list of participants and photographs has been provided in Annex 6. 95. During the consultation the people were informed about: (i)KSHIP, including a background on KSHIP Phase A project; (ii)The rural and urban design cross sections of the roads; (iii) The people were informed about KSHIP Resettlement policy and the compensation and assistance provided therein and asked suggestion for improvement so that their suggestions can be incorporated by the project authority for KSHIP; (iv) Proposed safety measures for the road; and (v)The likely impacts of the road, both positive and negative. The Consultations elicited from the people: (i) Their views on the project especially the likely adverse impacts; (ii) Possible mitigation measures in case of adverse impacts; (iii) Means of better delivery of compensation and assistance;(iv)The assurance from the project authority not to marginalize people by depriving them from their livelihood; and (v) Provision of infrastructure such as drinking water and toilets. 96. As a part of the public empowerment through public consultations the stakeholders have written to the Project authority regarding their views on the impact of the project, and the anticipated adverse impacts. These issues have been addressed and responses have been provided. 97. As meaningful consultations in the project is a regular and continuous process, more in-depth consultations will be organized by the implementation NGOs throughout the project cycle.

Key Findings of the Consultations 98. The consultations have helped in not only achieving the social assessment objectives, but also assisted in gathering suggestions for mitigation of adverse impacts, improvement in designs and facilitating inputs for the resettlement plan preparation and

28 implementation. The consultations for the links were held at Hindigere in 57 A, Jinnagara in 57 B and Chandagal in 57 C on 18 July 2010. There were 33 participants for link 57A meeting; 52 participants for link 57B meeting and 44 participants for link 57C meeting. 99. The issues discussed and the outcome has been given below: 29

Table 5-1: Key Issues: 57A Name Sex Profession Issues discussed Response Chikkegowda M Farmer He wanted to know how All tress affected will be compensation will be paid for compensated according to cocnut and arecanut trees. He Horticulture department said he has four guntas of land. valuation process. For any He wants more compensation. land acquired compensation will be based on negotiation according to the KHA Act. Nagesh M Farmer He said the project is providing The project will provide for 30 ft by 40ft site for those alternative site on losing residential structures. He available government wanted to know what land. If such land is not arrangement the project is available, then the project making to provide such sites. will purchase and make it available for the beneficiaries. Marimalliah M Farmer He said he owns 10 guntas of It was explained for any land. He is losing a part of his land acquired land and his house. He wants compensation will be more compensation for his loss. based on negotiation according to the KHA Act. For loss residential structure alternative site/structure on other government land will be provided by the project. H.C. M Farmer He wanted to know how shops on It was told that all squatter Chandrashek government land will be shops will be provided ariah compensated. with alternative shop by the project. Narayana M Farmer He wanted to know how shops on It was told that all squatter government land will be shops will be provided compensated. He also said some with alternative shop by of the petty shop owners had the project. taken loan – so if the project takes away the shop how will these people repay their loans. Rajanna M Farmer He wanted compensation to be It was explained that it is paid before the start of the project principle to construction. ensure that all compensation is paid before the start of construction. Balraj M Farmer He wanted to know how affected It was explained that the bore wells will be replaced. PA will replace the bore well by digging a bore well in place identified by the person losing the bore well. In case there is no water found then the project will compensate by giving the replace cost of the bore well. Shadak M Bill He wanted to know whether the It was told that all utilty Sharaiah Collector water pipelines and electric poles lines will be shifted by the will be replaced. project and replaced by the PA.

30

Table 5-2: Key Issues: 57B

Name Sex Profession Issues discussed Response Naganna M Farmer He wanted to know when It was explained that the compensation will be paid – project will ensure that all before or after starting the work. compensation is paid before the start of construction. He wanted to know if 60 % of the It was explained that if the house is affected, whether the structure is not usable the project will take the remaining project will compensate 40%. for the whole structure, even if they do not acquire the total structure. It depends on the person whether he wants to retain the remaining part or give it to the project. Ramegowda M Farmer He is losing his arecanut trees. All trees affected will be He wanted to know how compensated according to compensation will be paid. Horticulture department valuation process. For any He said in the village more than land acquired 20 houses will get affected. He compensation will be wanted constructed houses for based on negotiation all the 20 houses in the one according to the KHA Act. place. It was explained that project will ensure minimum impact to the houses, in case there are more than 20 houses getting affected then then a resettlement colony will be build. G.P M Farmer He said the government rate for For any land acquired Puttegowda land is less, he wanted market compensation will be value for his land. based on negotiation according to the KHA Act.

C. Kumar M Farmer He wanted to know he more tha It was explained if the 25% of his house is going the whole house is damaged walls will be damaged. He the project will pay for te wanted compensation for the total structure and provide whole structure. for alternative house. He also wanted to know when It was explained that the compensation will be given. project will ensure that all compensation is paid before the start of construction.

J.T M Farmer He said since a number of It was explained that Puttegowda houses are likely to get affected, project will ensure the project should find another minimum impact to the alignment, bypassing the village. houses. For any realignment the technical He also wanted to know the feasibility has to be looked 31

acquisition and impact details into. It was told all project details can be accessed from the KHSIP office or from the implementating NGO. Chandra M Farmer He wanted to know whether th It was explained that this road will be taken up by the was GoK - PWD work. government or a private agency. Ramesh M Farmer He wants the project to maintain It was explained that the the existing road. He said curve aim of the project was to straightening will impact a minimise impacts. number of houses. However designs are based on technical feasibility.

Table 5-3: Key Issues: 57C

Name Sex Profession Issues discussed Response Thimmaiah M Farmer He wanted to know the road It was explained that the width details. He also said road width varies from compensation should be based 12m in the urban ares on market rates. upto 30 m in the rural areas. For any land acquired compensation will be based on negotiation according to the KHA Act. Thammego M Farmer He said in one house there are The project will wda 2-3 brothers residing- if the compensate the person in house is affected how the project whose name the property will assist all of them. is in. If the property is in the name of more than one person the compensation will be equally divided. Suresh M Farmer He wanted to know whether the It was explained that no petty business can continue their activity will be permitted shops after the construction of inside the cleared COI. the road. The sqautters will be He also wanted to know for new provided with alternative shops what compensation will be shops where they have to given. continue their activity. For all squatters, alternative shops will be provided regardless of whether it is a new of old structure. Thammiah M Farmer He said if more than 25% of the It was explained if the Anniaha house is goiung he wants whole house is damaged compensation for the whole the project will pay for te structure. total structure and provide for alternative house.

Venakat M Farmer He wants market value for It was explained for any Rammana affected land. land acquired Shetty compensation will be based on negotiation

32

according to the KHA Act. Thammiah M Farmer He wanted to know how the It was expaliend that project will compensate for community assest will be community structures getting replaced by the Project on affected. alternative land identified by the community. If during project implementation PIU KSHIP or implementation NGO come across any case where affected persons have not been timely paid during previous land acquisition (for the same road) such cases will be dealt on the case to case basis and PIU KSHIP will facilitate the acquiring body to make payment to the affected persons through GRC and this will be documented.

Levels of Consultation 100. The consultation program is tiered and conducted at several levels that included, among others: (i) Heads of households/members likely to be impacted; (ii) Villagers and Village Panchayats; (iii) and Implementing Agency and line Departments.

Consultations during implementation 101. Several additional DP consultations will be conducted during RP implementation. As a follow-up of the local-level DP consultations held during project preparation, further consultations will be conducted by the NGO during implementation. In the first round of consultations information on RP and Entitlement policy and options will be disseminated. This will involve explaining the Entitlement Framework and resettlement options to the DPs and soliciting their support and cooperation. This will help finalize agreement on the various entitlements provided in the entitlement framework. Next round of consultation involves agreements on compensation and assistance options and entitlements with DPs and completion of DP identity card indicating the accepted entitlement package. The next round of DP consultations will occur when compensation and assistance are provided and actual resettlement begins and the NGO has to facilitate relocation.

Disclosure 102. In order to make the RP implementation process transparent, a series of FGDs/ meetings etc will be held with all stakeholders for dissemination of information regarding rehabilitation process and entitlement framework. The RP and entitlements will be disclosed in public meeting. The salient features of RP and the R & R policy will be translated in Kannada and disclosed through public consultations to be held in taluka head quarter of each districts through which the particular link pass through. It will also be disclosed through the PWD, Government of Karnataka Website. In addition brochure of the Land Acquisition and the R & R Policy will also be provided. All copies will be kept in: (i) State Government Library at Bangalore; (ii) - District libraries of the project; and (iii) in the Panchayat offices along the project roads. The RP document will also be disclosed on ADBs website as per the disclosure requirements. 103. A Public Consultation and Disclosure Plan will be prepared by PIU/NGO for each of the projects as per the format below: 33

104. Table 5-4: Disclosure Plan Timing Agencies Activity Task (Date/ Remarks Period) Stakeholder Mapping of the identification project area Project information Distribution of dissemination information leaflets to dispalced persons (DPs) Consultative Discuss potential meetings with APs impacts of the during scoping project phase Public Notification Publish list of affected lands/sites in a local newspaper; establish eligibility cut-off date Socio-economic Collect socioeconomic survey information on DP’s perception on the project Consultative Discuss meetings on entitlements, resettlement compensation mitigation rates, grievance measures redress mechanisms Publicize the Distribute leaflets resettlement plan or booklets in local (RP) language

Full disclosure of Distribute RP in the RP to APs local language to DPs Internet disclosure RP posted on ADB of and/or EA website the RP Consultative Face to face meetings during meetings with DPs detailed measurement survey(DMS) Disclosure after Disclose updated DMS RP to DPs

Internet disclosure Updated RP of posted on ADB the updated RP and/or EA website

34

6 LEGAL FRAMEWORK 105. This chapter provides an overview of the applicable Policies and Acts for the Project.

The National Policy on Resettlement and Rehabilitation for Project Affected Households, 2007 106. Until recent time, in India, there was no safeguard policy to deal with resettlement and rehabilitation of displaced persons. There was no uniform approach adopted by states towards the displaced persons. In the absence of central policies, ad hoc administrative instructions, in conformity with the land acquisition act was in practice. In 2007 the GOI developed a National social safe guard policy. This was developed taking into the consideration the safeguard policies of international development bodies like the World Bank, Asian Development Bank etc. The National Policy on Resettlement and Rehabilitation for Project Affected Households, 2007 (NRRP) came into effect in October 2007. The salient feature and the statements of the NRRP policy are as followings: (i) SIA shall be mandatory for all projects involving displacement of four hundred or more households en masses in plain areas, or two hundred or more households en masses in tribal or hilly areas etc. Coordination with EIA in the context of the public hearing done in the project affected area for EIA shall also cover issues related to SIA. (ii) Consultations with affected people and disclosure of relevant information to them at various stages of resettlement planning; (iii) Affected people without legal rights also need to be assisted (affected people categorized landless agricultural workers, forest dwellers, tenants and artisans who are critically dependent on the acquired assets for their subsistence/ livelihoods); (iv) Prepare resettlement plans that are disclosed to the affected people in draft form, and reviewed and approved by competent authorities; (v) Collection of socioeconomic base line for project affected households; (vi) Project displaced persons (whose entire land is taken) will receive land in lieu of his loss. In addition to their loss cash assistance will be paid for regaining livelihood; (vii) Vulnerable project affected people will get extra cash/kind assistance; (viii) Purchase of land from any project affected persons would be through consent award (negotiation of rate between land owner and project authority); (ix) The Grievance Redressal Cell shall have representatives of women, Schedule Castes Schedule tribes residing in the affected zone. The Cell shall have the power to consider and dispose of all complaints relating to resettlement and rehabilitation against the decision of the Administrator/R & R Committee at Project level; (x) A monitoring cell should be constituted under the Project. (xi) Each Project affected household comprising of rural artisan/small trader and self employed person shall get one-time financial assistance for construction of working shed/shop for livelihood support. 35

The Land Acquisition (LA) Act of 1894 107. The Land Acquisition (LA) Act of 1984 is commonly used for acquisition of land for any public purpose. It is used at the State level with State amendments made to suit local requirements. Expropriation of and compensation for land, houses and other immovable assets are carried out under the Land Acquisition (Amendment) Act, 1984. The Act deals with compulsory acquisition of private land for public purpose. The procedures set out include: (i)Preliminary notification(Section 4); (ii)Declaration of Notification (Section 6); (iii)Notice to persons interested (Section 9); (iv)Enquiry and award (Section 11); (v)Possession (Section 16). 108. The 1984 amendments to the LA Act addressed the matter of compensation and delays in payment. As regards, the level of compensation, the rate of solatium was increased from 15 % to 30 %. For delays, the amendment requires that: (i) A time of one year was fixed for completing all formalities between the issuance of Section 4 and Section 6; and (ii) The compensation award must be determined within two years of the issuing of section 6 notification. Interest is payable at a rate of 12 per cent per year from the date of preliminary notification to the date of dispossession. These changes apply to cases before the Civil Courts even for awards made before the enactment of the amendments.

Asian Development Bank’s Safeguard Policy 109. The ADB’s Safeguard Policy Statement 2009, recognizes and addresses the R&R impacts of all the affected persons, irrespective of their titles, and requires the preparation of RP in every instance where involuntary resettlement occurs. The ADB policy requirements are: (a) avoid involuntary resettlement wherever possible; (b) to minimize involuntary resettlement by exploring project and design alternatives; (c) to enhance, or at least restore, the livelihoods of all displaced persons2 in real terms relative to pre-project levels; (d) improve the standards of living of the displaced poor and other vulnerable groups. 110. The main policy principles of the SPS are:  Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks. Determine the scope of resettlement planning through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks.

2 In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

36

 Carry out meaningful consultations with affected persons, host communities, and concerned non-government organizations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and reporting of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the affected persons’ concerns. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.  Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.  Provide physically and economically displaced persons with needed assistance, including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.  Improve the standards of living of the displaced poor and other vulnerable groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing.  Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status.  Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets.  Prepare a resettlement plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule. 37

 Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to affected persons and other stakeholders. Disclose the final resettlement plan and its updates to affected persons and other stakeholders.  Conceive and execute involuntary resettlement as part of a development project or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.  Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation.  Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

Indigenous Peoples 111. Indigenous Peoples (IP) are defined by ADB’S Indigenous Peoples Policy as those having distinct social, cultural, economic, and political traditions and institutions compared with the mainstream or dominant society. IP generally share the following characteristics: (i) descent from a population living in an area before current national territories were defined; (ii) maintenance of cultural and social identities separate from those of dominant societies; (iii) self-identification and identification by others as being part of a distinct cultural group; (iv) linguistic identity different from that of dominant society; (v) political traditions and institutions distinct from dominant culture; (vi) economic systems oriented more toward traditional production systems; and (vii) unique ties and attachments to traditional habitats and ancestral territories.

Karnataka Highway Act 1964 112. In addition to the above measures, realizing the need of infrastructure development like roads in timely manner, the PWD GOK has decided to acquire the land in KSHIP through the “The Karnataka Highways Act 1964”(KHA,1964) instead of using the Land Acquisition Act of 1894.

Comparison of National and State Policies with Asian Development Bank’s SPS -2009 113. The National Rehabilitation and Resettlement Policy of 2007 (NRRP-2007) , represents a significant milestone in the development of a systematic approach to address resettlement issues in India and closes significantly the gap between Indian national policies and those of ADB’s. The Land Acquisition Act (LAA) of 1894 (as amended in 1984) gives directives for the acquisition of land in the public interest and provides benefits only to titleholders. The LAA also does not provide replacement cost for the loss of land and assets. By contrast, the NRRP recognizes non-titleholders, although the basic requirement is for the non-titleholder to have been in the project-affected area at least three years prior to the

38 declaration of the area as an affected area. In Karnataka there are various project level R & R Policies. The KSHIP policy tries to address any gaps in the existing policies which are relevant for the project. Table 6-1: Comparison of gaps in various Acts and Policies with ADB’s SPS LA NRRP-2007 ADB SPS KSHIP Policy Cut off Date 3 years prior to Date of survey will Date of survey will be for Assistance date of survey for be considered as considered as cut off for Non titleholders cut off for Non Non titleholders and the and the date of titleholders and the date of section 15 section 15 date of section 15 notification for notification for notification for titleholder. titleholders. titleholder. Social Impact Mandates SIA Requires a Poverty A Poverty and Social Assessment survey for 400 or and Social Assessment study has more getting Assessment study been done for this displaced no minimum project. enmasse in plain threshold area or more than prescribed. 200 households in hilly area Replacement No Provides for Provides for Provides for Cost of land replaceme alternative lands; replacement cost replacement cost nt cost of where not possible of land (compensation)of land land monetary through negotiations as compensation per KHA Assistance to No direct mention This is covered. Provides assistance to tenants losing of assistance to tenants losing commercial tenants losing commercial and and residential commercial and residential structures. structures residential structures 39

7 ENTITLEMENTS, ASSISTANCE AND BENEFITS

KSHIP Policy 114. The National, State and Departmental Code provides for the framework for resettlement and rehabilitation activities. However, within the context of the above mentioned policy frameworks a project specific Resettlement Policy has been prepared. The project policy has been evolved through a number of discussions by PIU. Good practices of the other States have also been taken into consideration in addition to considering the relevant policy provisions and entitlements under each category of loss mentioned in National Policy for Resettlement and Rehabilitation 2007.

Impacts and Entitlements 115. This policy addresses the direct and indirect impacts of project construction and operation on displaced persons, households and communities. The most direct and immediate impacts are those associated with project construction, mainly land acquisition. Other losses include loss of shelter, and other assets within the project’s corridor of impact; as well as roadside structure, business establishments and public facilities. Mitigation is provided through compensation and assistance to project-displaced persons, households, and groups. All assistance amount will be paid as one time grant. These social units are entitled to compensation and assistance on the basis of this policy framework adopted by the project. The policy provides mitigation for:  loss of assets, including land and house or work place;  loss of livelihood or income opportunities; and  Collective impacts on groups, such as loss of community assets, common property resources, and others. 116. Loss of assets and livelihood are impact categories that represent direct project impacts on an identified population. The people likely to be affected will be surveyed and registered, and project monitoring and evaluation will compare long-term impact against baseline socioeconomic data. Collective impacts on groups represent direct and indirect impacts, where group members need not be individually registered. Group-oriented gains and losses in this category are less quantifiable in terms of impacts on the individual. Mitigation and support mechanisms are collectively oriented, and the monitoring of these efforts will examine the impact and benefits for the groups involved. The GOK from time to time will make amendments in this policy as and when required.

Corridor of Impact 117. The ROW is the lawfully acquired corridor of public land owned by the State Government and administered by the PWD for the transit of the existing road. Using available records with the PWD and the Revenue Department, the project will verify the boundaries of the legal right of way as well as boundaries of private properties within and in the vicinity of the likely Corridor of Impact. Displacement under the project will be limited to the corridor required for the road and its safety zone. This corridor is referred to as the Corridor of Impact. Within this corridor, there should be no structures or other hindrances. The advantage of this approach is that such a corridor is easier to maintain free of

40 encumbrances than the full ROW. Where the COI is beyond the RoW land acquisition will be required.

Targeted support to vulnerable groups 118. The project will develop target assistance for groups such as women-headed households, disabled, widow and persons above the age of 60 years. Attention will be given on a case by case basis, with regard to their rehabilitation, livelihood, educational opportunities, vocational training, etc.

Option and Choices 119. The project will provide options and choices among different entitlements to the affected population. As part of the project consultation and participation mechanisms, people will be informed and consulted about the project and its impacts, and their entitlements and options. The affected population will be counselled so that they are able to make informed choices among the options provided.

Principles 120. This policy is based on the principle that the population affected by the project will be assisted to improve their former living standards. The policy emphasizes that involuntary resettlement will be avoided or minimized where possible by exploring other alternative project designs. Where displacement is unavoidable, people loosing assets, livelihood or other resources shall be assisted in improving their former living standards. The policy document describes the details of entitlements and type of assistance to be extended to the affected persons, which will become the basis for preparing a detailed and time bound Resettlement Plan (RP). The RP will contain the implementation details on how to ensure that principles and provisions of this policy can be implemented. The Resettlement Plan will describe the approach to be followed in minimizing and mitigating negative social and economic impacts caused by the project, including displacement. 121. This policy identifies categories of expected project impacts, including loss of property and assets, loss of livelihood, and other social and economic impacts on groups and roadside communities. All people, households and groups adversely affected by the project would be registered and support will be given in accordance with these policy provisions.

Definitions a. Agricultural land means lands being used for the purpose of :(i) agriculture or horticulture; (ii) raising of crops, grass or garden produce; and (iii) land used by an agriculturist for the grazing of cattle, but does not include land used for cutting of wood only; b. Assistance refers to the support provided to displaced persons in the form of ex-gratia payments, loans, asset services, etc. in order to improve the standard of living and reduce the negative impacts of the project. c. Bagar Hukum land is any Government land which is unauthorizedly occupied by a person and such person has applied for regularization of the same under 41

the Karnataka Land Revenue Rules under 108 C(1) is called Bagar Hukum land. d. Below poverty line or BPL Household means below poverty line households as defined by the Planning Commission of India, from time to time, and those included in the State BPL list in force. e. Compensation refers to the amount paid under The Karnataka Highways Act, 1964 and The Karnataka Highways Rules, 1965, for private property, structures and other assets acquired for the project. It refers to the amount as given in the Entitlement Matrix for the project. f. Cutoff Date is the date of Notification under Section 15 of Karnataka Highways Act, 1964 will be the cutoff date where the land acquisition will be required. For Non titleholders the date of socioeconomic survey will be considered as the cutoff date. g. Displaced household (DH) means (i) a household whose primary place of residence or other property or source of livelihood is adversely affected by the acquisition of land for a project or involuntary displacement due to any other reason; (ii) any tenure holder, tenant, lessee or owner of other property, who on account of acquisition of land (including bagar Hukum or other property) in the affected area of otherwise, has been involuntary displaced from such land or other property; (iii) any agricultural or non-agricultural labourer, landless person (not having homestead land or agricultural land) rural artisan, small trader or self-employed person; who has been residing or engaged in any trade, business, occupation or vocation in the affected area, and who has been deprived of earning his livelihood or alienated wholly or substantially from the main source of his trade, business, occupation or vocation because of the acquisition of land in the affected area or being involuntarily displaced for any other reason; h. Displaced Persons (DPs), any persons who have economic interests or residence within the project impact corridor and who may be adversely affected directly by the project. Project displaced persons include those displaced, those losing commercial or residential structures in whole or part, those losing agricultural land or homesteads in whole or part, and those losing income sources as a result of project action. i. Encroachers are those persons who have extended their building, business premises or work places into government lands. Assistance will be provided to these persons, based on their loss. j. Household includes a person, his or her spouse, minor sons, unmarried daughters, minor brothers, unmarried sisters, father, mother and other relatives residing with him or her and dependent on him or her for their livelihood; and includes “nuclear household” consisting of a person, his or her spouse and minor children; k. Government refers to the Government of Karnataka l. Land acquisition or acquisition land means acquisition of land under the Karnataka Highways Act, 1964;

42

m. Marginal farmer means a cultivator with an unirrigated land holding up to one hectare or irrigated land holding up to half hectare; n. Minimum Wages: The minimum wage of a person for his/her services/labour is Rs. 100 per day as per Government Notification NoLD96 LMW 2005 dated 30.07.2007. o. Non-Perennial Crop: Any plant species, either grown naturally or through cultivation that lives for a season and perishes with harvesting of its yields has been considered as a non-perennial crop in the project. For example, paddy, sugarcane, groundnut, etc. p. Notification means a notification published in the Gazette of India, or as the case may be, the Gazette of State; q. Perennial Crop: Any plant species that live for years and yields its products after a certain age of maturity is a perennial crop. Generally trees, either grown naturally or by horticultural and yield fruits or timber have been considered as perennial crop in the project. For example, tamarind, coconut, mango, teak, neem etc. are perennial crops. r. Replacement Cost of the acquired assets and property is the amount required for the affected house hold to replace/reconstruct the lost assets through purchase in the open market. Replacement cost will be calculated at PWDs current Schedule of Rates without depreciation. Replacement cost will be in line with the provisos of the Entitlement Matrix of the project. s. Severance of Land can be defined of a land holding divided into two or more pieces due to acquisition of land mainly for laying new project alignment, such as a bypass or a re-alignment. t. Small farmer means a cultivator with an un-irrigated land holding up to two hectares or with an irrigated land holding up to one hectare, but more than the holding of a marginal farmer. u. Squatter means those persons who have illegally occupied government lands for residential, business and or other purposes. v. Tenants are those persons having bonafide tenancy agreements, written or unwritten, with a private property owner with clear property titles, to occupy a structure or land for residence, business or other purposes. w. Vulnerable groups: persons such as disabled, widows, or persons above sixty years of age. x. Women-headed Household is a household that is headed by a woman and does not have a male earning member. This woman may be a widowed, separated or deserted person.

Entitlements 122. The DPs will be provided with the benefits described in the succeeding paragraphs. 123. Loss of Land: This includes all those who have legal title to land. They will be provided with Compensation as per Replacement Cost through direct negotiation as per 43

Karnataka State Highway Act, 1964 + stamp duty and registration charges. Stamp duty and registration charges are applicable for those who accept negotiation price. Minimum negotiated price for the Districts of Bangalore Urban, Bangalore Rural, Chikkaballapur, Ramnagaram, and Corporation / Municipal limits of other district HQs will be one and half times the Guidance Value. For all other areas other than those mentioned above the minimum negotiated price will be twice the Guidance Value.3 OR average sales statistics, whichever is higher4. In case of severance of land an additional 25 % compensation will be paid to the land loser if he retains the remaining plot OR if the remaining land is not viable and the land owner opts to surrender the entire plot to the project, compensation as given earlier will be applicable; Loss of perennial crops and non-perennial crops will be compensated in accordance with Horticulture department valuation process; A grant of Rs. 15,000 for replacement of Cattle shed; Water yielding bores will be replaced in the location identified by the affected person in the remaining land holding subject to availability of water. In case water is not available replacement cost of the borewell at current PWD SR rates with 30 % which is at replacement cost will be given. In case of land owners who become landless or marginal farmers, the following additional entitlements will be offered: (a) subsistence allowance of Rs.30,000 for land less and marginal; and, (b) assistance for creating Income generation asset valued upto Rs.75,000; Additional amount of Rs.20,000 will be restricted to those who loose narrow stretch of land as exgartia compensation in lieu of all other benefits(Narrow stretch of land is defined as persons losing upto five guntas of land). For those becoming landless and all marginal farmers training assistance will be provided for income generating vocational training and skills upgrading options as per affected persons choice .The NGO will ensure linkages of the trained persons to ongoing programmes, to facilitate employment and marketing opportunities; Employment opportunity for displaced persons as per his skills and availability of suitable work in road construction work; In case of Bagar hukum lands - 50 % of compensation and other benefits as available for land owners. Bagar Hukum land losers are those whose application is pending for disposal with Competent Authority (Tahsildar) and are cultivating the affected lands at the time of acquisition. A certification from Tahsildar is required for such applicants to receive applicable entitlements 124. Loss of residential structures: These persons with legal titles losing their residential structures. They will get compensation at current PWD scheduled rates without depreciation and 30 % solatium which is at replacement cost; Alternative houses in resettlement colony or developed plot and construction cost of Rs. 40,000 linked to construction progress; Additional 25 % compensation for partially affected structures towards reconstruction; shifting assistance of Rs. 10,000; Subsistence allowance of Rs. 30,000. In case more than 25 % of house is affected and unviable for retaining, full compensation will be paid; Resettlement colonies will be developed if more than 20 households are displaced in 2 Kms continuous stretch; Plot size will be equivalent to size lost subject to a maximum of

3 Revised Guidance Value of the properties in Bangalore Urban, Bangalore Rural, Chikkaballpur, Ramanagaram and Corporation/Municipal limits is 2-3 times higher than the earlier Guidance Value. Hence 1.5 times the Guidance Value is proposed as minimum negotiated price. In other areas ratio of revision is reasonably low, hence 2 times the Guidance Value is proposed as minimum price. 4 The average Sales Statistics is in line with LA Amendment Bill. In the LA Amendment Bill there are different modalities in determining and assessing the market value, any one among them would be adopted wherein the land loser gets the maximum market value.

44

369 sqmt/1200sqft in rural area and 184 sqm /600 sqft in urban areas; People have right to salvage the affected materials. 125. Loss of commercial structures: These are persons with legal titles who will loose their commercial structures. They will get compensation at current PWD scheduled rates without depreciation and 30% solatium which is at replacement cost; Alternative shop or assistance for income generation asset valuated upto Rs. 75,000; Additional 25% compensation for partially affected structures; Shifting assistance of Rs. 10,000; Subsistence allowance of Rs. 30,000; Shopping units with 100-150 sq.ft will be constructed if more than 20 shops are affected in a continuous stretch of two kms and opt for shop. People have right to salvage the affected materials; Training for self employment will be provided to one adult per household as needed. 126. Loss of residential cum commercial structures: These are persons who loose their commercial cum residential structures. They will get the following entitlements: Compensation at current PWD scheduled rates without depreciation and 30% solatium which is at replacement cost; Alternative shop or assistance for income generation asset valuated upto Rs. 75,000 or Alternative houses in resettlement colony or developed plot and construction cost of Rs. 40,000 linked to construction progress ; Additional 25% compensation for partially affected structures; Shifting assistance of Rs. 10,000 ; Subsistence allowance of Rs. 30,000 ;Additional amount of Rs. 25,000 as grant. In case more than 25% of house is affected and unviable for retaining, full compensation will be paid ; Resettlement colonies will be developed if more than 20 households are displaced in two Kms continuous stretch;Plot size will be equivalent to size lost subject to a maximum of 369 sq. m/1200sq. ft in rural area and 184 sq. m /600 sqft in urban areas; Shopping units with 100-150 sq.ft will be constructed if more than 20 shops are affected in a continuous stretch of two kms and opt for shop ; People have right to salvage the affected materials; Training for self employment will be provided to one adult per household as needed. 127. Tenants losing residential structure: These are persons who are residing as tenants. They will be eligible for Rental allowance for 6 months at Rs. 500 per month in rural and Rs. 1000 in urban areas; Shifting assistance of Rs. 10,000. 128. Tenants losing commercial structure: These are persons who are carrying out commercial activities as tenats. They will be eligible for Rental allowance for 6 months at Rs. 1,000 per month in rural and Rs. 1500 in urban areas; Shifting assistance of Rs. 10,000; Assistance for income generation asset upto Rs. 75,000. 129. Tenants losing residential cum commercial structure: These are tenants who reside and carry out commercial activity in the same structure. These persons will be entitled to Rental allowance for 6 months at Rs. 1000 per month in rural and Rs. 1500 in urban areas; Shifting assistance of Rs. 10,000; Assistance for income generation asset upto Rs. 75,000. 130. Non titleholders – residential squatters: These are persons without legal title who are residing on government property. These persons will be asiisted with House in resettlement colony or developed plot and construction cost of Rs. 40,000 linked to construction progress; Subsistence allowance of Rs.15,000; Shifting Allowance of Rs.5,000. House size in resettlement colony to be minimum of 25 sqm/270 sqft. Resettlement colony will be constructed if more than 20 residential squatters are getting affected in a continuous 45 stretch of two km and opted for same; Developed plot size will be allotted of 25 sqms/270 sqft in urban area and 33 sqm /350 sqft in rural area. 131. Non titleholders – commercial squatters: These are persons without legal title who are carrying out commercial activity on government property. These persons will be assisted with 132. Alternative shop of 100 sq.ft or assistance for income generation asset valuated upto Rs. 30,000; Subsistence allowance of Rs.15,000; Shifting Allowance of Rs.5,000. Shopping units will be constructed if more than 20 shops are affected in a continuous stretch of 2 km and opted for shop. 133. Encroachers: These are persons whose structures have encroached on government land. These persons will be provided Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation and compensation of Crop loss or advance notice for harvesting crops 134. Loss of primary source of income: Those persons who are working as employees or agricultural labours that depend upon an existing activity getting affected. These persons will be entitled to Subsistence allowance of Rs. 15,000. Training assistance will be provided for income generating vocational training and skill upgrading options as per affected persons choice; Employment opportunity for affected persons as per his skills and availability of suitable work in road construction work will be provided. Training for self employment will be provided to one adult per household as needed 135. Vulnerable groups – Widows, the physically challenged and those aged above 60 years: These persons will be entitled to Assistance to include in government pension schemes if not included , if eligible as per Government criteria (OR) Lump-sum amount of Rs. 25,000 ; Training assistance will be provided for income generating vocational training and skill upgrading options as per choice; This will be restricted to those who have no or cannot be provided with alterative livelihood sources. 136. Community Assets getting affected will be reconstructed and be transferred to Local authorities for maintenance 137. Unidentified Impacts: Unforeseen impacts shall be documented and mitigated based on the principles provided in this policy 138. All amounts in this entitlement matrix are fixed as of April 01, 2010. These will be increased 10% annually on first day of April every year. The same will hold good for guidance value also if not revised by the GoK.

46

Entitlement Matrix 139. The entitlement matrix will guide to offer compensation and assistance to those persons affected by the project. The detailed entitlement matrix for the project is given in Table 7-1. Table 7-1: Entitlement Matrix No. Impact Entitlements Remarks Category I. Title Holders (a) Loss of land 1. Compensation as per the  Stamp duty and registration principle of replacement cost charges are applicable for through direct negotiation as those who accept negotiation provided for in the Karnataka price. State Highway Act, 1964 + stamp duty and registration charges;  Minimum negotiated price for 2. Compensation offered is cash the Districts of Bangalore for land Urban, Bangalore Rural, Chikkaballapur, Ramnagaram, and Corporation / Municipal limits of other district HQs will be 1.5 times the Guidance Value. For all other areas other than those mentioned above the minimum negotiated price will be 2 times the Guidance Value.5 OR average sales statistics, which ever is higher6

5 Revised Guidance Value of the properties in Bangalore Urban, Bangalore Rural, Chikkaballpur, Ramanagaram and Corporation/Municipal limits is 2-3 times higher than the earlier Guidance Value. Hence 1.5 times the Guidance Value is proposed as minimum negotiated price. In other areas ratio of revision is reasonably low, hence 2 times the Guidance Value is proposed as minimum price. 6 The average Sales Statistics is in line with LA Amendment Bill. In the LA Amendment Bill there are different modalities in determining and assessing the market value, any one among them would be adopted wherein the land loser gets the maximum market value. 47

No. Impact Entitlements Remarks Category

3. In case of severance of land an additional 25% compensation will be paid to the land loser if he retains the remaining plot OR if the remaining land is not viable and the land owner opts to surrender the entire plot to the project, compensation as given in No. 1 will be applicable;

4. Loss of perennial crops and non-perennial crops will be compensated in accordance with Horticulture department valuation process, which is the replacement cost.

5. A grant of Rs. 15,000 for replacement of Cattle shed;

6. Water yielding bores will be replaced in the location identified by the affected person in the remaining land holding subject to availability of water. In case water is not available replacement cost of the borewell at current PWD SR rates without depreciation charges and 30% solatium which is replacement cost will be given.  Marginal farmer is defined as those left with 1 hectare of 7. In case of land owners who non-irrigated or 0.50 hectare become landless or marginal of irrigation or combination of farmers, the following both additional entitlements will be offered: (a) subsistence allowance of Rs. 30,000 for land less and marginal; and, (b) assistance for creating Income generation asset  valued up to Rs.75,000 ;  Narrow stretch of land is defined as persons losing an 8. Additional amount of Rs. area that is up to 5 guntas of 20,000 will be restricted to land.

 As per the NRRP-2007 the acquiring body has to provide rehabilitation grant equivalent to 750 days minimum agricultural wages. At present the minimum agricultural wages is Rs. 100/day. The NGO will ascertain the actual needs of the displaced persons and assist in creating assets.

 Bagar Hukum lands are government lands which are unauthorisedly cultivated by persons without legal documents. Applications for regularization that are pending before the regularization committee.

48

No. Impact Entitlements Remarks Category those who lose narrow stretch of land as exgratia compensation in lieu of all other benefits.  The NGO engaged for the RP implementation will 9. For those becoming landless ensure linkages of the and all marginal farmers trained persons to ongoing training assistance will be programs, to facilitate provided for income generating employment and marketing vocational training and skills opportunities. upgrade options as per displaced persons' choice;

10. Employment opportunity for affected the displaced persons as per his/her skills and the availability of suitable work in road construction work.  Any Government land which  11. In case of Bagar hukum lands is unauthorizedly occupied - 50% of compensation and by a person and such person other benefits as available for has applied for regularization land owners which is of the same under the equivalent to replacement Karnataka Land Revenue value for this category. Rules under 108 C(1) is called Bagar Hukum land. Under Rule 108C section 94A, of the Karnataka Land Revenue Act, 1966, the Tahsildar is the custodian of the records and he will issue the certification whether the application is pending before the Committee or not. Tahsildar is the Secretary of the Committee for regularization of unauthorized occupation of government land.

(b) Loss of 1. Compensation at current PWD  In case more than 25% of a Residential scheduled rates without house is affected and structures depreciation and 30% solatium unviable for retaining, full at replacement cost. compensation will be paid 2. Alternative houses in  Resettlement colonies will be resettlement colony or developed if more than 20 developed plot and households are displaced in construction cost of Rs. 40,000 2 km continuous stretch linked to construction progress.  Plot size will be equivalent to 3. Additional 25% of current PWD size lost subject to a SR rates without depreciation + maximum of 369 30% solatium for the affected sqmt/1200sqft in rural area portion as compensation for and 184 sq. m /600 sq. ft. in partially affected structures urban areas. towards reconstruction  Displaced persons have a 4. Shifting assistance of Rs. right to salvage the affected 10,000 materials. 5. Subsistence allowance of Rs. 49

No. Impact Entitlements Remarks Category 30,000

(c) Loss of 1. Compensation at current PWD  Shopping units with 100-150 commercial scheduled rates without sq.ft will be constructed if structures depreciation and 30% solatium more than 20 shops are at replacement cost. affected in a continuous 2. Alternative shop or assistance stretch of 2 kms and the for income generation asset owners opt for a shop. valuated upto Rs. 75,000  Displaced persons have a 3. Additional 25% compensation right to salvage the affected for partially affected structures materials 4. Shifting assistance of Rs.  Training for self employment 10,000 will be provided to one adult 5. Subsistence allowance of Rs. per household as needed 30,000  Displaced persons have a right to salvage the affected materials

(d) Loss of 1. Compensation at current PWD  In case more than 25% of residential scheduled rates without house is affected and cum depreciation and 30% solatium unviable for retaining, full commercial at replacement cost. compensation will be paid structures 2. Alternative shop or assistance  Resettlement colonies will be for income generation asset developed if more than 20 valuated up to Rs. 75,000 households are displaced in 3. Additional 25% compensation 2 km continuous stretch for partially affected structures  Plot size will be equivalent to 4. Shifting assistance of Rs. size lost subject to a 10,000 maximum of 369 5. Subsistence allowance of Rs. sq.m/1200sq. ft. in rural area 30,000 and 184 sq. m. /600 sq. ft. in 6. Additional amount of Rs. urban areas. 25,000 as grant.  Shopping units with 100-150 sq. ft. will be constructed if more than 20 shops are affected in a continuous stretch of 2 km and the owners opt for a shop.  Displaced persons have a right to salvage the affected materials  Training for self employment will be provided to one adult per household as needed II. Tenants (a) Residential 1. Rental allowance for 6 months @ Rs. 500 per month in rural and Rs. 1000 in urban areas 2. Shifting assistance of Rs. 10,000

50

No. Impact Entitlements Remarks Category (b) Commercial 1. Rental allowance for 6 months @ Rs. 1,000 per month in rural and Rs. 1,500 in urban areas 2. Shifting assistance of Rs. 10,000 3. Assistance for income generation assistance up to Rs. 75,000 (c) Loss of 1. Rental allowance for 6 months residential @ Rs. 1,000 per month in rural cum and Rs. 1,500 in urban areas commercial 2. Shifting assistance of Rs. structures 10,000 3. Assistance for income generation assistance upto Rs. 75,000 III. Non-Title holders (a) Residential 1. House in resettlement colony  House plot size in Squatters or developed plot and resettlement colony to be construction cost of Rs. 40,000 minimum of 25 sq.m./270 sq linked to construction progress. ft. Resettlement colony will 2. Subsistence allowance of be constructed if more than Rs.15,000. 20 residential squatters are 3. Shifting Allowance of Rs.5000. getting affected in a continuous stretch of 2 kms and opted for same. As per NRRP 2007.  Developed plot size will be allotted of 25 sqms/ 270 sqft in urban area and 33 sqms /350 sqft in rural area as per NRRP 2007.

(b) Commercial 1. Alternative shop of 100 sq. ft.  Shopping units will be Squatters or assistance for income constructed if more than 20 generation asset valuated up shops are affected in a to Rs. 30,000; continuous stretch of 2 km 2. Subsistence allowance of and opted for shop. Rs.15,000; 3. Shifting Allowance of Rs.5,000. (c) Encroachers 1. Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation 2. Compensation of crop loss or advance notice for harvesting crops IV. Loss of livelihood (a) Loss of 1. Subsistence allowance of Rs.  Training for self employment primary 15,000. will be provided to one adult source of 2. Training assistance will be per household as needed income provided for income generating vocational training and skills upgrade options as per the displaced persons' choice; 3. Employment opportunity for the displaced persons as per his/her 51

No. Impact Entitlements Remarks Category skills and availability of suitable work in the road construction. V. Vulnerable People (a) Widows 1. Assistance to include in  This will be restricted to Physically government pension schemes if those who have no or cannot challenged not included , if eligible as per be provided with alterative and those Government criteria (OR) livelihood sources. aged above 2. Lump-sum amount of Rs. 25,000  Training for those above 60 60 years 3. Training assistance will be years is not mandatory and provided for income generating will be provided for if the vocational training and skills person opts for it and after upgrade options as per the the need is assessed. displaced persons' choice

VI. Community Assets (a) Community 1. Reconstruction of affected Assets assets 2. Transfer to Local authorities for maintenance VII. Unidentified Impacts (a) Unidentified 1. Unforeseen impacts shall be Impacts documented and mitigated based on the principles provided in this policy

Note: All amounts in this entitlement matrix are fixed as of April 01, 2010. These will increased 10% annually on first day of April every year. The same will hold good for guidance value also if not revised by the GoK.

52

8 RELOCATION OF HOUSING AND SETTLEMENTS

Basic Provision for Relocation 140. The PA will provide adequate and appropriate replacement land and structures or cash compensation for lost land and structures, adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The PA will compensate to the non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land. The entitlements to the non- titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date.

Need for Relocation 141. Efforts have been made to minimize the resettlement. There are 23 houses (titleholder) and four non titlholder houses through out the package that are likely to be affected. Majority of the structures (134) getting affected are nontitleholder commercial structures. All efforts are made through various provisions in this RP to mitigate negative social impacts on displaced persons and communities by supporting relocation of affected households and by restoration of pre-project levels of income.

Development of Vendor markets 142. Shopping units with 100-150 sq.ft will be constructed if more than 20 shops are affected in a continuous stretch of two kms and opt for shop. In this package there is no requirement for vendor markets

Development of Resettlement Centers  Resettlement Centers will be developed if more than 20 households are displaced in a continuous stretch of two kms and wish to relocate to the resettlement center.  SDO and SWI along with NGO staff will identify the site and inform to the R & R Manager. R & R Manger will examine the site and make a proposal and submit to the Executive Engineer at the Division level. After the approval of EE it will be sent to the PD for financial approval.  Alternative houses will be provided in resettlement colony if the beneficiary opts for the same or developed plot and construction cost of Rs. 40,000 linked to construction progress.  Plot size will be equivalent to size lost subject to a maximum of 369 sqmt/1200 sq. ft in rural area and 184 sq. m /600 sq. ft in urban areas.  House of up 832 sq. m/ 300sq. ft in rural areas and 75 sq. m/250 sq. ft in urban area. 143. In this package there is no requirement for Resettlement centers. 144. Resettlement site selection involve the following steps : a. Site selection - Site selection is to be done based on available land, maps and data available for evaluating potential sites. Site selection should be 53

discussed with the DPs, their representatives and local officials prior to being finalised. b. Feasibility studies - Detailed studies to determine the technical and economic feasibility of the proposed activities is to be carried out and should include land development and cost estimates. Sites not found economically viable or environmentally unsuitable should be rejected. c. Detailed designs and land purchase - The DPs final agreement on site development needs to be obtained along with the host community’s acceptance of resettlement arrangements. Care should be taken to purchase contiguous plots of land to reduce costs of infrastructure development. d. Final Design and Constructions - Housing for DHs and provision of basic infrastructure activities are pre-requisites to the movement of DHs e. Movement of DHs - Moving should take place only when the sites are ready with the minimal basic amenities. Food distribution is necessary during the transport period and few days following the arrival at new site. f. Organization of community life and support services – Initial training of resettlement staff, extension workers and DP representatives should start prior to the actual movement of the people

Environmental Aspects 145. Some of the criteria to be considered are: (i) Lands notified, as water body should be avoided; (ii) Irrigated agriculture lands should be avoided; (iii) Lands notified, as forest should be avoided including forests coming under Panchayat; (iv) Resettlement sites nearer to the water bodies (including ponds and canals) are to be avoided to prevent water borne diseases;(v) Lands under plantation are to be avoided; and (vi) the resettlement sites should be at least 10 km away from ecologically sensitive areas.

Social Aspects 146. Lands owned by the vulnerable communities should be avoided for resettlement sites. This includes SC/ST, women-headed households and households below poverty line, lands owned by small and marginal farmers should not be acquired for resettlement sites. DPs and host community should be consulted for mutual acceptance of the presence of each other.

Basic amenities and facilities a. Proposed site should be close to the existing site and should not be more than 500m away from the end of the settlement. b. Electricity and drinking water sources should be available with in 500 m distance from the proposed site. c. Propose d resettlement site should have an access road at least earthen road/car track d. Primary school should be close to the existing site.. e. Nearest bus stop should be within 500 m from the meeting point of main road with access road.

54

f. Proposed resettlement site should be within one km from main road. g. Only 50% of the total area is for residential and commercial use. The remaining area is for other use. h. Approach road to be 60 feet wide, with internal roads at widths of 40 feet and 30 feet. i. Surface drains and masonry culverts are provided to all roads. j. Roadsides, parks and open areas for future use to be planted with trees. k. Commercial and industrial areas to be earmarked appropriately l. Sites to be demarcated and numbered m. Provisions to be made for : Primary School / High School ; Shopping Complex; Samaja Mandira / Anganawadi; Temple / Masjid / Church; Water supply / open wells / borewells / cisterns; Ration Shops; Burial/cremation ground; Primary Health Unit (depending on the size of the unit );Street light; Bus shelter; Public toilets 147. As far as possible RC’s are to be located close to grazing lands and main roads. 25 % additional sites earmarked for future development. The construction of all public buildings, internal roads, demarcation of sites will be undertaken by the Project. The project will undertake all water supply works, distribution of lines construction of storage tanks etc., and will also execute all electrification works. The SDRC will be responsible for the overall coordination of the work. 148. Preference will be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based. These strategies may include resettlement on public land, or on private land acquired or purchased for resettlement. Whenever replacement land is offered, displaced persons are provided with land for which a combination of productive potential, locational advantages, and other factors is at least equivalent to the advantages of the land taken. If land is not the preferred option of the displaced persons, or sufficient land is not available at a reasonable price, non-land-based options built around opportunities for employment or self-employment should be provided in addition to cash compensation for land and other assets lost.

Reconstruction of affected community structures The project authorities will replace and reconstruct all community assets before demolition. For shifting of community assets the NGO will (i) consult with the community along with the SDO and identify alternative land- the land identified has to be government land wherever possible, or given as donation in some cases; (iii) owner consent letter has to be signed by the donor /owner in the prescribed format prepared by the NGO (name, place, survey nos., site measurement); (iv) the reconstruction will be carried out by the local contractors; (iv) the KSHIP Assistant Executive Engineer of the division will be responsible for monitoring the work; and(v) the cost for the relocation and reconstruction will be paid by the project 55

9 INCOME RESTORATION AND REHABILITATION

Income restoration measures 149. The basic objective of income restoration activities is that no project-affected person shall be worse off than before the project. Restoration of pre-project levels of income is an important part of rehabilitating individuals, households, and socioeconomic and cultural systems in affected communities. Income restoration schemes will be designed in consultation with affected persons so as to benefit them. Based on the information collected on IR activities from the census socioeconomic surveys, the implementing NGO will identify suitable IR programme for the affected persons.

Impact Categories and IR Schemes 150. Project-induced displacement may lead to loss or diminished income for Displaced Person (DPs). The main categories of impacts expected as a result of project land and property acquisition include: (a) Loss of agriculture land in part or full; (b) Loss of commercial establishments (c) Loss of livelihood as employees and (v) tenants losing their livelihood 151. Table 9-1: Categories for Income restoration Loss No. DPs/ DHs 1 Partial loss of agriculture 2081 2 Loss of commercial structures 28 3 Loss of livelihood as employees 20 4 Tenants losing livelihood 52 152. The economic rehabilitation assistance money will be deposited in bank accounts to be released only for the purchase of income generating assets. Women-headed households will be assisted in identifying alternative space in adjacent areas for continuing their trade or vocations. These households will have to be given preference in disbursement of assistance. The SDRC will use its good offices with local authorities to facilitate early rehabilitation of these women-headed households. DPs losing their livelihood as employees will be provided only relief assistance.

IR Activities 153. There are two types of IR activities, i.e. short term and long term. Short term IR activities mean restoring DPs’ income during periods immediately before and after relocation. For this, the support NGO shall ensure that: compensation and R & R assistance as provided in the entitlement matrix is provided. Other works include work in the project construction activities and other allied activities such as work on resettlement sites etc. Long Term IR Activities include provision of shops for those losing their total livelihood, to re- establish their commercial activities. Shopping units with 100-150 sq.ft will be constructed if more than 20 shops are affected in a continuous stretch of two kms and opt for shop. It also includes purchase of income generating assets upto Rs. 75,000. In case the amount used is less than this, the beneficiary will get the remaining amount after one year of successful completion of the activity, which will be monitored by the NGO. 154. The steps to be followed for income restoration include:

56

155. Step 1: Identification of Target Groups – NGOs need to identify the affected persons; 156. Step 2: Identification of IR Activities - Prepare a list of possible and feasible income restoration options. While identifying IR options, the following factors shall also be considered: (i) Education level of DPs; (ii) Skill possession;(iii)Likely economic activities in the post displacement period; (iii) Extent of land left; (iii) Suitability of economic activity to supplement the income; (iv)Market potential and marketing facilities. Based on socioeconomic characteristics and options preferred by DPs, the NGO may have to re- assign trades to DPs. Options include (i) petty trade (iii) skill related schemes and loans for pumps, bore wells, bullock carts etc to increase productivity. The NGO will assist DPs in identifying appropriate alternative economic rehabilitation schemes through counselling and consultation. 157. Step 3: Training: Option for training for skill enhancement for those losing their livelihood has been provided in the Entitlement Matrix for owners losing commercial structure and employees losing their livelihood. 158. Step 4: Identification of Trainers / Training Institutes: Based on trades selected, NGO shall have to identify master trainer and/or training institute for different trades / activities who can provide on the job training. 159. Step 5: Training Arrangement: NGO shall make different groups of DPs as per trades selected and make all the arrangements such as fixing the venue etc. 160. Step 6: Monitoring of DPs: After training the NGO shall monitor the DPs in order to take mid-term correction measures, if required. 57

10 RESETTLEMENT BUDGET AND FINANCING

Budget and Costs 161. The costs used for the budget estimates are based on information collected during the census socioeconomic surveys of DPs. The estimated total budget for the implementation of RP is Rs. 265.26 million. This does not include Operating Costs, NGO and Monitoring Consultant Costs as these costs are for the overall project which is estimated at Rs. 20 million. The unit costs and detailed budget are given below: Table 10-1: Budget Sl. Cost per Category Total Unit Total cost No. Unit LAND ACQUISITION 1 Agriculture land (Acres) 81.17 1,000,000 81,170,000 Sub Total 81,170,000 ALTERNATIVE SITE COST 2 Residential site (owner) 23 30,000 690,000 3 Commercial site (owner) 16 50,000 800,000 4 Commercial site (squatter) 134 30,000 4,020,000 5 Residential site (squatter) 4 50,000 200,000 Sub Total 5,710,000 STRUCTURE COST 6 RCC - Pucca housing (Sq ft.) 53251.88 800 42,601,504 7 Dry stone masonary (Sq ft.) 12588.77 600 7,553,262 8 Mud mortar (Sq ft.) 9803.04 350 3,431,064 Sub total 53,585,830 R&R ASSISTANCE EWS House construction(Non 9 40,000 Titleholder) 4 160,000 10 House construction (owners) 23 40,000 920,000 Shifting Allowance(Non 11 10,000 titleholders) 138 1380000 Subsistence Allowance (Non 12 15,000 titleholders) 138 2,070,000 Subsistence Allowance 13 30,000 (Owners) 39 1,170,000 Additional assistance for land 14 20,000 losers 2081 41,620,000 Shifting 15 10,000 Allowance(Titleholders) 39 390,000 Economic generating 17 75,000 asset(owner/tenant) 68 5,100,000 Economic generating asset 18 30,000 (squatter) 134 4,020,000 19 Rental Value Commercial 52 9,000 468,000 20 Rental Value Residential 1 60,00 6,000 21 Relief Assistance 20 15,000 300,000 22 Training for DP 16 15,000 240,000

58

Sl. Cost per Category Total Unit Total cost No. Unit 23 Vulnerable groups 1642 25,000 41,050,000 24 Cattle shed 11 15,000 165,000 25 Group Entitlement 108.62 15,000 1,629,300 Sub Total 100,688,300 Total 241,154,130 10% Contingency 24,115,413 OVERALL TOTAL 265,269,543 Table 10-2: Unit Costs for R & R Sl. Category Estimates (in Rs) No. 1 Agricultural Land per ha Rs.2,470,000 2 Non Agricultural Land per ha Rs.3,705,000 3 Pucca house 800 per sq. ft 4 Semi pucca house 600 per sq. ft 5 Kutcha house 350 per sq ft. 6 Construction cost for house in Resettlement site 40,000 per structure 7 EWS Housing 40,000 per unit Training for DP for income generation schemes and 15,000 (Rs.5000 per month for 3 8 vocational training months) 9 NGO assistance for implementation 8,500,000 10 Evaluation Consultants 3,000,000 11 SDRC and associated staff training 1,500,000 lump sum 12 Group entitlements 15,000 per km Office equipment (including Rs. 500,000 each for 2,000,000 lump sum 13 setting up office of LAO in North and South Karnataka 14 Vehicle cost ( Rs.800,000 per vehicle) 8 vehicles 5,600,000 162. In accordance with the policy provisions, all grants and benefits shall be indexed annually at 10 % on the first of April. These include subsistence allowance, shifting allowance, relief assistance, amounts for income generating asset, cost for the provision of sites to squatters and rental allowance. Table 10-3: R & R Unit Costs Sl. Category Proposed Amount No. 1 Purchase Commercial site for Rs.30,000 (10’x10’) Urban Rs 15,000 Rural area squatters 2 Purchase Commercial site for Rs.50,000 (10’x15’) Urban Rs 25,000 Rural area Titleholders 3 Purchase Residential site for Rs. 30,000 Urban Rs 20,000 Rural area squatter 4 Purchase Residential site for Rs. 70,000 Urban Rs 30,000 Rural area Titleholders 5 Shifting allowance for Titleholders Rs.10,000 as one time payment 6 Subsistence allowance for Rs. 30,000 Titleholders 7 Subsistence allowance for squatters Rs.15,000 as one time payment 8 Shifting assistance for squatters Rs.5,000 as one time payment 9 construction cost for Residential Rs.40,000 squatters 10 IGA assistance to commercial Rs.30,000 for income generating asset squatter 59

Sl. Category Proposed Amount No. 11 Shifting allowance for Bagar Hukum Rs.5,000 as one-time Payment House holders 12 Subsistence allowance for those Rs.15,000 as one-time payment who are losing Bagar Hukum Lands 13 Additional assistance for those Rs.20,000 as one-time payment. losing land 14 Income generating Grant for Title Rs.75,000 as one-time payment holder who loose entire land /Business 15 Rental allowance for commercial Rs. 1,500 for urban and Rs. 1,000 for rural per Tenant month for 6 months. 16 Rental allowance for residential Rs.1,000 for urban and Rs. 500 for rural per Tenant month for 6 months 17 Relief assistance for loss of Rs.15,000 lump sum payment employment of agriculture and Non agriculture. 18 Assistance to Vulnerable groups Rs. 25,000 lump sum payment In the R & R budget, allocation has not been made for replacement of affected community structures. Any community assets that are getting impacted and which need to be replaced or relocated, is being undertaken separately by PIU KSHIP field division offices.

60

11 GRIEVANCE REDRESSAL MECHANISM

Grievance Redressal Committee 163. The project will establish a Grievance Redressal process, with district-level committees. Each District Grievance Redressal Committee will have representation from the local affected population and the NGOs involved in RP implementation. These committees will hear complaints and facilitate solutions; and the process, as a whole, will promote dispute settlement through mediation to reduce unnecessary litigation. 164. The following persons will constitute the District Level Grievance Redressal Cell :  Deputy Commissioner Chairman  Academician (To be selected by DC) Member  Representative of DP (To be selected by DC) Member  Executive Engineer of Concerned Division Convener 165. The main functions of the GRC will be: a. to provide support to DPs on problems arising out of eligibility for RP-provided entitlements and assistance provided; b. to record the grievances of the DPs, and categorize, prioritize and solve them within one month; c. to inform PIU of serious cases within one week; and d. to report to the aggrieved parties about the developments regarding their grievance and decisions of the PIU, within one month. 166. The Grievance Committees will meet regularly during implementation of the RP, at least once a month. The committees will suggest corrective measures at the field level itself and fix responsibilities for implementation of its decisions. However the NGOs will form the first level of intervention in resolving DP related grievances and attempt to motivate the DP to facilitate implementation of the R & R program. The option of contacting the project authorities is available to DPs at any time. The Deputy Commissioner will be the Appellate Authority. The steps in the GRC are: a. At the first level intervention the NGO will attempt to resolve the grievance; b. Next the CAO will attempt to address land related grievance and the ADSW will address the non-land related grievances; c. The third step will be to approach the Grievance Redressal Committee; d. Next they can Approach the Regional Commissioner who is the Appellate Authority; e. If all the above fails, the DPs can approach the court. 167. It is the responsibility of the SDRC/NGO to inform the affected persons of the GRC, to make it effective. The NGO shall make DPs aware of the grievance mechanism set out in the RP and shall assist PDPs who have grievances to pursue a suitable remedy. The NGO shall help the DPs to file a grievance application. 168. The NGO shall record the grievance and bring the same to the notice of the Grievance Redressal Committees (GRC) within seven days of receipt of the grievance from 61 the DPs. It shall submit a draft resolution with respect to the particular grievance of the DP, suggesting solutions, if possible, and deliberate on the same in the GRC meeting through the NGO representative in the GRC. 169. The NGO shall assist in the GRC process whenever necessary.

Figure 11-1: Grievance Redressal

62

12 INSTITUTIONAL MECHANISMS

Institutional Arrangements 170. KSHIP has a dedicated unit called the Social Development and Resettlement Cell (SDRC) within the Project Implementation Unit for the implementation of the RP. All aspects of resettlement and rehabilitation and the delivery of entitlements are managed by Social Development/Resettlement Cell (SDRC).

Social Development and Resettlement Cell (SDRC) 171. The SDRC facilitates land acquisition and compensation, relocation and resettlement, distribution of assistance for the DPs. The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition. The responsibilities of SDRC include: i. responsible for all land acquisition activities; ii. liaison with State and District levels Departments to facilitate DP access and take advantage of services and programs already in place; iii. evolve mechanisms for coordinating the delivery of the compensation and assistance to entitled persons; iv. review and provide social development perspectives and inputs to on-going project design and implementation by working closely with project planners, contractors, and construction supervision consultants; v. link the project with state government agencies, provide liaison with PWD field units and impacted communities, coordinate with district-level committees regarding social development and resettlement operations in the field, mobilize assisting NGO partners, and support the organisation of local community representing DPs; and vi. engage required training services, oversee a grievance redressal process, actively monitor RP implementation, and cooperate with planned project evaluations.

SDRC and Staff Deployment 172. The RP will be implemented by the North Karnataka (Hospet) division of PIU; Staffing is complete for the proposed institutional set up.Figure 12.1 shows the institutional set up. The key SDRC officials are: 173. Special DC Land Acquisition - Special Deputy Commissioner in the cadre of KAS will be the in charge of the overall land acquisition. He will be assisted by two Assistant Commissioners for Land Acquisition who is responsible for all activities related to land acquisition. One Assistant Commissioner will be stationed in the zonal office of North Karnataka(Hospet) and the other one would be stationed at PIU Office (South Zonal Office) in Bangalore. 174. Chief Administrative Officer –The CAO in the cadre of KAS will be responsible for all resettlement and rehabilitation activities. The CAO will also be assisted by The Assistant Director Social Welfare (ADSW) who will be responsible for R & R work. On the land 63 acquisition side CAO and the Assistant Commissioners will be responsible for fixing the negotiated price of the land along with the affected persons according to the Karnataka Highways Act, 1964, and disbursing the compensation. 175. The Assistant Director Social Welfare (ADSW) is responsible for shifting of project affected persons, coordination of disbursement of assistance such as shifting allowance etc., disbursement of funds for income generating programmes, relief assistance, etc. The ADSW needs to have relevant experience of at least five years in resettlement projects, with a minimum educational qualification of Masters in Social Science. 176. The R & R Manager will assist the ADSW and coordinate all the rehabilitation work of the SDO’s. The R&R Manager has to have experience in resettlement projects with minimum experience of three years, with a minimum educational qualification of Masters Degree in Social Sciences. 177. The ADSW and the Resettlement and Rehabilitation Manager will be assisted by the Social Development Officer (SDO). It is suggested that four SDOs be stationed in the Assistant Commissioners Office to be located on North zone and PIU –South in Bangalore (already appointed). The responsibility of SDO includes: support to resettlement and rehabilitation related work pertaining to RP implementation, like issue and the verification of ID cards, identification of local income generation potential, monitoring rehabilitation works, providing assistance to vulnerable groups, co-ordinating with NGOs etc. The SDO has to have a Masters degree in Social Sciences. 178. The SDOs will be assisted by the Social Welfare Inspectors (SWI). The SWI’s are supporting staff to SDOs to carry out the functions as per the directions of SDOs. 179. The SDRC will have a Data Management Specialist. The responsibility of this person will be to monitor and update the data of all the project affected persons; to highlight any discrepancy in compensation and paid disbursed; and coordinate the inputs of information from the North and South Divisions to the Central database at PIU at Bangalore. The Data Management Specialist is to be supported by additional staff. The PIU has already appointed the Consultants for database management. Information is ready to be transferred to the PIU for use in implementation.

64

180. Figure 12.1: Institutional Set up

CHIEF PROJECT OFFICER

PROJECT CAO (SPECIAL DC) SPECIAL DIRECTOR AT PIU HQsc DC(LA)

AC-LAO-GRP I NORTH KARNATAKA ASSISTANT DIRECTOR (Office at Dharwad - AC-LAO-GRP I SOUTH (SOCIAL W ELFARE) tentatively KARNATAKA AT HQ s

DEPUTY TAHSILDAR R &R MANAGER DEPUTY TAHSILDAR

FIRST DIV REVENUE COMPUTER SOCIAL DEVELOPMENT SDO - NORTH KARNATAKA SDO - SOUTH SURVEYOR (4) FIRST DIV REVENUE COMPUTER ASSISTANT INSPECTOR (4) OPERATOR/STENO 1 SURVEYOR (4) OFFICER (1) PIU (2) KARNATAKA (2) ASSISTANT (2) INSPECTOR (4) OPERATOR/STENO 2

GROUP D (4) GROUP D (4) SOCIAL W ELFARE INSPECTOR (1) SOCIAL W ELFARE INSPECTOR (6) SOCIAL WELFARE VEHICLE 1 INSPECTOR (6) DRIVER 1 VEHICLE 1 DRIVER 1 COMPUTER OPERATOR 1; STENO 1

VEHICLE 4, DRIVER 4 MONITORING DBMS NGO NORTH NGO SOUTH CONSULTANTS SPECIALIST GROUP D (2) 181. 65

Protection of RoW 182. Section 5 of the KHA mentions the Highway Authority will exercise power and discharge duties in accordance with provisions of the KHA for restriction of ribbon development along the highways and for prevention and removal of encroachments. The Highway Authority under Section 7 has power to fix boundary of building and control lines of highways. Section 21 mentions prevention of unauthorized occupation of highway. Thus the onus of protecting the COI/RoW lies with the Project Authority. Once the COI/Row has been identified and frozen, the COI/RoW has to be clearly marked with boundary stones. Any new encroachment into the area will be monitored the Division PWD, this has to be done through bi-monthly site inspection by the Divisional Engineer in charge. Those Non-titleholders already identified by the project will be provided by Identity Cards issued by the PIU. The bi- monthly site inspection will help to prevent further encroachments.

Valuation of other structures/assets 183. The valuation of structures and other assets, which have not been covered by the LAPs will be carried out by Government approved valuators appointed by the PIU. Valuation will be done on the basis of current PWD Schedule of Rates, without depreciation which will be at replacement cost. Based on the valuation another 30% will be given. However, this will be approved and verified by the concerned Executive Engineer. It will be forwarded to the PD for approval. Trees will be valued by the Horticulture/Forest department.

Roles and responsibilities of officials for RP implementation 184. The Administrative roles and responsibilities and financial powers - existing and to be delegated of the SDRC officials are given below. Delegations of financial powers have to done through a Government Order. Table 12-1: Administrative and Financial Responsibilities of officials and Agencies for RP Implementation Personnel/Ag Administrative Roles and Responsibilities Financial Powers ency PIU Chief Project  In charge of the overall project activities.  Will be authorized to Officer  To decide on all policy matters regarding make any additional LA and R & R. changes without  Participate as a member secretary in the having to refer to the State level Committees to facilitate land Steering committee, acquisition, pre-construction activities, and provided the amount implementation of R & R activities. is within the budget  Authorized to take decision in financial matters within the provided budget.

66

Personnel/Ag Administrative Roles and Responsibilities Financial Powers ency Project  Overall in charge of day to day activities of  To approve awards Director LA and R & R. above Rs.50 lakhs  Participate in State and District level to Rs. One Crore. meetings to facilitate LA and R & R  To approve of Rand activities. R assistance above  Responsible for contracting NGOs and One lakh. Monitoring consultants.  Periodic appraisal of progress and reporting to the Asian Development Bank and the Government on monthly basis. SDRC Chief  Responsible for all R & R activities  To approve Administrative  Coordinate the implementation of R & R payments for R & R Officer activities with PIU, field staff, engineering assistance upto Rs. and revenue officials. One lakh per  Approve of micro plans prepared by the individual. NGOs for implementing RP.  Monitor the progress of R & R activities and LA carried out by the NGO and Monitoring Consultants.  Hold periodic meetings on R & R implementation and report to the PD and CPO.  Provide advisory support to PIU for monitoring of RP implementation. Assistant  Assist CAO in the implementation of R & R  No financial powers Director Social activities. Welfare  Coordinate training for PIU and NGOs for capacity building to implement R & R.  Facilitate development of resettlement sites and agriculture land.  Participate in the allotment of residential and commercial plots to the DPs.  Liaison with district administration and line departments for dovetailing government schemes for income generating activities to DPs.  Participate in the meetings of Grievance Redressal Committee. Manager R &  Coordinate implementation of R & R  No financial powers R activities with PIU and field staff.  Facilitate the appointment of external agency for monitoring activities to be taken up by the implementing NGO.  Assist CAO to perform R & R activities.  Review the work in finalization of resettlement site development.  Prepare monthly progress report for the SDRC and Land Acquisition.  Monitor the R & R report and submit to CAO and PD. 67

Personnel/Ag Administrative Roles and Responsibilities Financial Powers ency LAND Special DC  Coordinate Land acquisition process with  To approve awards ACQUIS Land Tahsildar at field. upto Rs.50 lakhs, ITION Acquisition  Prepare guidelines and procedures to be adopted for land acquisition.  Interact with District officials and other stakeholders to speed up the land acquisition process.  Monitor land acquisition and report progress to CPO and PD. Assistant  Assist CAO and Sp. DC LA to perform R &  No financial powers Commissioner R and Land Acquisition activities. - LAO  Make budgetary provisions Tahsildar  Overall responsible for land acquisition as  No financial powers land acquisition officer.  Coordinate the preparation of Land Plan Schedules with Consultants and monitor the same.  Facilitate the preparation and submission of Section 15 notification under KHA for land acquisition.  Prepare progress report on physical and financial monitoring of LA and submit to DC LA. FIELD Executive  Participate in District level meetings.  No financial powers UNIT Engineer  Oversee the process of implementation of RP in the field.  Ensure the preconstruction work is done before handing over site to contractor.  Oversee the process of land acquisition, shifting of CPRs and other assets in the field.  Scrutinize and certify the structures valuation report submitted by the valuators.  Coordinate selection of resettlement site.  Conduct periodic review with staff  Submit monthly progress reports to PD on R & R activities. Assistant  Responsible for pre construction work in  No financial powers Executive his jurisdiction. Engineer  Finalization and demarcation of COI.  Coordinate with NGO/Monitoring consultants and SDO to carry out R & R activities.  Coordinate with valuers for preparations of estimates.  Support SDO/NGO for selection of resettlement site. Social  Overall responsible for R & R activities in No financial powers Development the field Officer  Liaison with District administration and line departments for dovetailing government schemes.  Make budget provision for R & R activities  Participate in allotment of sites to DPs.

68

Personnel/Ag Administrative Roles and Responsibilities Financial Powers ency  Coordinate with NGO/Monitoring consultants for implementation of R & R.  Facilitate opening of Joint Accounts for DPs for transfer of R & R assistance through cheque.  Coordinate to disseminate the R & R policy in local language.  Facilitate public consultation on R & R Policy with NGO/ Revenue/ PWD officials.  Organize meetings with NGOs to review progress at district level and submit to R & R Manager and CAO at PIU. Social Welfare  Responsible for maintaining the R & R  No financial Inspectors work at division wise. powers  Assist NGO for selection of resettlement site.  Assist Monitoring Consultants /NGO to conduct training for DP on IGA  Coordinate with SDO/EE at field level for disbursement of R & R assistance.  Ensure all eligible DPs are awarded compensation.  Attend monthly meeting at district level and submit monthly progress report to R & R Manager and ADSW. DATAB Data  Responsible for maintaining the database  No financial ASE Management of the DPs. powers Specialist  Responsible for maintaining the database of overall physical and financial progress.  Coordination of the database for SDRC.  The implementation of R & R activities by NGOs to be maintained.  Provide necessary formats for collection of field information.  Coordinate with SDRC to prepare and maintain the progress report.  Maintain the records of grievance redressal committee.  Coordinate the inputs of data from North and South Divisions.  Identify discrepancies in disbursement. EXTER NGOs (2)  Responsible for providing PIU support for  No financial NAL implementation of RP. powers AGENCI  Verification of DPs. ES  Distribution of ID cards.  Preparation of micro plans.  Dissemination of information.  Assist to DPs to avail R & R assistance and compensation.  Identify site for relocation for CPRs.  Identify resettlement /vendor market sites.  Identify training needs and provide the same.  Facilitate in opening joint accounts. 69

Personnel/Ag Administrative Roles and Responsibilities Financial Powers ency  Enable DPs to identify alternate sites for house/shop  Assist DPs to relocate.  Provide monthly progress reports on implementation Monitoring  Conduct monitoring of RP implementation  No financial Consultants activities. powers  Conduct internal, external and concurrent monitoring.  Provide early alert to PIU to redress any potential problems.  Monitor target achievements and slippages.  Certification of readiness from LA and R & R view at the time of issuing bid documents and award of contract. Grievance  Support DPs in resolving issues related to  No financial Redressal R & R and LA. powers Committee.  Record grievance and resolve them within stipulated time.  Inform PIU about any serious cases.  Report to the aggrieved parties about the decisions of the PIU. Negotiation  Negotiate the consent price of land  No financial Committee. powers

Competent Authority for various approval 185. The table below identifies the competent Authority for various approvals during implementation. Table 12-2: Competent Authority for Approvals Approvals Required Competent Authority Approval for LA awards Special DC LA and PD, PIU; Notification by Government Approval for Roles and Responsibilities for SDRC Steering Committee officials and staff R & R Policy/ Entitlements and amendments to Policy Government RP and Budget Steering Committee Changes in R & R Policy/RP implementation and Government entitlements Consultants/NGOs output CAO Fixing compensation rate Price Negotiation Committee – District level Approval for issue of ID cards CAO PIU jointly by Engineers/ Revenue /NGO. Approval of disbursement of Assistance CAO; PD Approval for structure valuation with land Preparation By Divisional EE/ valuators and approval by PD and Special DC LA Approval for structure valuation without land Preparation By Divisional EE/ valuators and approval PD Approval for shifting and relocation of community Estimate preparation by Divisional EE and assets approval by PD Approval for requirement of Resettlement site , vendor CAO, PD market for DHs

70

Approvals Required Competent Authority Approval for any grievance related to R & R Grievance Redressal Committee

Implementation support by NGOs 186. The work of the NGO will include consultations and counseling of DPs, encouraging DPs for productive utilization of compensation and rehabilitation grants, facilitating DP access to income generating assets, increasing the social acceptability, ensuring effectiveness of training programs organized for DPs electing participation in self employment schemes etc., The SDRC has to ensure that the NGO has sufficient experience in implementation of resettlement project, especially in Karnataka and it has to have adequate manpower. Two NGOs will be selected, one for North Karnataka and one for South Karnataka. 187. The NGO will work as a link between the PIU - SDR Cell and the affected community. They will educate the DPs on the need to implement the Project, on aspects relating to LA and R & R measures and ensures proper utilization of various compensations extended to the DPs under the R & R entitlement package. The tasks of the NGO will be to facilitate the resettlement process. Its broad objectives will be: 1. Identification, verification and updating of DP Census, Includes verification of properties of DPs and estimation of their type and level of losses for the preparation micro plans and ID Cards. 2. Develop micro plans in consultation with the DPs and PIU staff. . 3. Educate DPs on their rights, entitlements, and obligations under the RP; Assist the DPs to identify suitable alternate land for resettlement purposes; 4. Preparation and Distribution of Entitlement cum Identity Card. All eligible project displaced households will be issued Identity Cards, giving details of the type of losses and type of entitlements. 5. Ensure that DPs receive their full entitlements; Where options are available, the NGO will provide advice to DPs on benefits of each option; Assist the DPs in getting benefits from various government development programs; 6. Rehabilitation of Affected Households and restoration of Income and Livelihood. The NGO will help the communities derive maximum benefits out of the project without loosing their livelihoods and the least impact on socio-cultural aspects of their lives. 7. Assist DPs on grievance redressal through the established system; and 8. Will relocate DPs. Assist PIU in making arrangements for the smooth relocation of the DPs; No Physical relocation from agriculture land, residential units, commercial establishments or other immovable properties will begin before alternate arrangements are made. 9. Any other responsibility that may be assigned by the PIU for the welfare of the affected communities. 188. In order to carry out the above tasks, NGO staff will be stationed in the site offices. Besides contacting the DPs on an individual basis to regularly update the baseline information, group meetings and village-level meetings will be conducted by the support agency on a regular basis. The frequencies of such meetings will depend on the requirements of the DPs but should occur at least once a month. The support agency will 71 have to encourage participation of individual DPs in such meeting by discussing their problems regarding LA, R & R and other aspects relating to their socioeconomic lives. Such participation will make it easier to find a solution acceptable to all involved. The ToR for the NGO is given in Annex 7.

Database Management 189. A census Database has been created by the consultants. This database will be transferred to the SDRC, for upgrading and further use. The main purpose of the database and use will be to (i) track progress of R & R implementation (ii) for determining the entitlements to be paid; (iii) track pending entitlements and amounts; (iv)organizing outputs for periodical reports and other project requirements; and (v) establishing input formats . The Database consultants will be responsible for (i) modifying the input/ output formats to the project requirements;(ii) Training of SDRC staffs and other field level staffs; (iii) aid the NGO in finalizing the entitlements of each DPs and DHs; (vi) provide for decision making at the PIU; (vii) Monitor and regulate the land acquisition, distribution of compensation and assistance, grievance redressal and financial progress. In which the SDRC will hire database management consultants for the management, monitoring and updating of the data. The database consultants will need to depute data entry operators in the offices of the Assistant Commissioner. The data in the HQ will be updated based on the information sent by the division office. The database will be developed to suit the requirements of implementation and monitoring payments. The database Information will be made web enabled (based on consultation with SDRC).

72

13 IMPLEMENTATION SCHEDULE

Coordination with civil works and certification 190. The resettlement program will be co-coordinated with the timing of civil works. The required coordination has contractual implications, and will be considered in procurement and bidding schedules, award of contracts, and release of cleared COI sections to project contractors. The project will provide adequate notification, counseling and assistance to affected people so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation. The implementation schedule provides the key benchmarks of implementing the RP. All other activities related to implementation and land acquisition will be undertaken simultaneously. 191. Actions to be completed before prior to bid and award of contract include: (i) Resettlement Plan should have been approved by the GoK and Bank for respective roads; (ii) the RP should have been disclosed in the web site and other public places accessible to the local people ;(iii) the first notification for private land acquisition should have been issued; (iv) the issue of identity cards to eligible project affected households should have been completed. The actions to be completed prior to handing over of the first milestone stretches to the contractor includes: (i) The private land acquisition should have been completed and compensation offered to the land owners for Section 1; (ii) The Government land should have been transferred or no objection should have been obtained from the land owning agency for Section I; (iii) The community assets should have been replaced in Section 1 and (v) the remaining land acquisition, R & R assistance and relocation of community assets for second milestone should be completed within 6 months of award of contract and prior to handing of the site to the contractor. 192. It is the responsibility of the PIU to ensure that the RP is successfully implemented in a timely manner. The implementation schedule needs to be updated periodically and monitored judiciously. The completion of R & R activities will be certified by the MandE consultants. Resettlement and Rehabilitation is complete only when the following criteria are met: a. All legal compensation both for land and structure must be paid; b. 100% must have received compensation; c. All eligible DPs must have alternative house and economic rehabilitation must be complete; d. At least 80% of all eligible DPs must have started their new economic activity; e. All project affected common property resources must be replaced and re- established. f. Implementation of the remedial measures arising out of impact evaluations must be complete.

Implementation Schedule and Timing of Resettlement 193. During project implementation, the resettlement program will be co-coordinated with the timing of civil works. The required coordination has contractual implications, and will be considered in procurement and bidding schedules, award of contracts, and release of 73 cleared COI sections to project contractors. The project will provide adequate notification, counseling and assistance to affected people so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation. This provides the key benchmarks of implementing the RP. All other activities related to implementation and land acquisition will be undertaken simultaneously. After signing of contract the contractor will start his works in Section I, followed by Section II. 194. The proposed consideration of time to be taken for Land Acquisition under the KHA, after the issue of Section 15 notification is 6 months. 195. The time taken for the implementation for the RP will be two years. Resettlement planning and updating of studies will be a continuous process throughout the project. The PIU will coordinate these efforts to assure that RP implementation and phasing is appropriately sequenced with designs and civil works. 196. The resettlement process must be completed before the start of civil works. PIU has clear the COI and resettle DPs located within the COI, before the civil work starts on any section of the project road. DPs will be given at least three months notice to vacate their property before civil works starts. The civil works schedule needs to be dovetailed into the land acquisition and resettlement implementation schedule. The LA and R andR Implementation schedule is given below: Table 13-1: R & R Implementation Schedule

Activity Progress (Year/Quarter) 2009 2010 2011 Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Project Preparation Stage Screen project impact ------Public Consultation on alignment ------Prepare Land Acquisition Plan ------Carry out Census Survey ------Prepare Resettlement Plan (RP) ------RP Implementation Stage Hiring of NGOs for RP Implementation ------Obtaining approval of RP from ADB ------Disclosure of RP ------Public consultation ------Preparation LAP ------Declaration of cut-off date (KHA Notification) ------Payment of compensation ------Taking possession of acquired land ------Handing over the acquired land to contractor ------Rehabilitation of DPs ------Monitoring and Reporting Period Internal monitoring and reporting ------External monitoring and reporting ------

Capacity Building and Training 197. The capacity building and training of the PIU/SDRC is important for successful and timely implementation of RP. To enhance capabilities, the SDRC staff will be given in house training periodically (once in six months at least). All SDRC officers and staff have to attend

74 training programmes. Training will cover techniques in conducting participatory rural appraisal for micro-planning, conducting census socioeconomic surveys, dissemination of information, community consultation and progress monitoring and evaluation. In house training will be carried out by professional identified by the PIU. Local institutes such as the Indian Institute of Management, Institute for Social and Economic Change and private consultants can be identified for training. Table 13-2: In house Training programme Staff Training Module PIU CAO; DC LA; ADSW; R & R Policy, National State, Asian Development Banks; R & R Manager; SDO; Socioeconomic and Census Survey ; Checklist for R & SWI R; Implementation Schedule ; Training Needs Assessment ;Monitoring indicators; Dissemination of information ; Preparation of RP, LAP, Disbursement method, disclosure of documents; Best practices of other R & R projects FIELD EE; AEE; Revenue Measurement of structures; Valuation procedures; Resettlement site selection; Minimizing resettlement; preparation of LAPs, Disbursement method.; Shifting of CPRs EXTERNAL NGOs; Monitoring Government schemes; Disbursement methods; public Consultants consultation; income generating activities. 75

14 MONITORING AND REPORTING

Monitoring 198. Monitoring involves periodic checking to ascertain whether activities are going according to the plan. It provides the feedback necessary for project management to keep the programmes on schedule. Monitoring provides both working system for project managers and a channel for the resettles to make known their needs and their reactions to resettlement execution. Monitoring exercise will be undertaken both internally and externally. 199. While SDRC/PIU on monthly basis will carry out the project’s internal monitoring and external agency will be appointed for third party monitoring. Indicators, which will be monitored during the project, may be divided into two categories.  Process and output indicators or internal monitoring  Outcome/impact indicators or external monitoring 200. Monitoring is essentially an exercise in strategic learning that can and should be used for enhancing the quality of RP implementation. There are two types of monitoring being undertaken namely (a) internal, which is normally carried out by the project authority itself and (b) external or independent monitoring by an external agency.

Internal monitoring 201. The internal monitoring is a conventional monitoring of government related to physical factors such as, number of households affected, resettled, assistance extended infrastructure facilities provided, etc. and other financial aspects, such as compensation paid, grant extended, etc. the internal monitoring must be simultaneous with the implementation of the Rehabilitation Plan (RP). 202. The objectives of the internal monitoring are: (i) Daily Operations Planning; (ii) Management and Implementation and (iii) Operational Troubleshooting and Feedback. The periodicity of internal monitoring could be daily or weekly depending on the issues and level.

External monitoring 203. An external monitoring agency will be appointed to monitor R & R programmes on semi annaul basis. It should also bring the difficulties faced by the DPs to the notice of PIU so as to help in formulating corrective measures. As a feedback to the PIU and other concerned, the external agency should submit semi annaul reports on progress made relating to different aspect of R & R. The reports will be disclosed on ADB website. The agency will also certify the completion of LA and R & R activities for issuing bid documents and award from LA and R & R point of view. 204. The objectives of the external monitoring are:  To track resettled and host population over time in order to document the restoration of incomes and standard of living.  Determine remedial action if required.  If income and standard of living of the DPs has at least been restored and has not declined.

76

 In case of host population, whether income and standard of living of host population have not declined due to influence of resettlers.  Whether resettlers and host population has reintegrated with each other. Table 14-1: Monitoring Indicators for Physical Progress % against Implement Revised Cumul Progres Revised Monitoring Indicators ation Implemen ative Sl. No. s This Implemen for Physical Progress Target tation Progre Month tation (Nos) Target ss Target 1 Land Acquired- private 18.17 Land transferred – 2 0 Government Compensation for loss 3 of Commercial 16 structure to title holder. Shifting assistance to 4 Title holder for 16 commercial Subsistence allowance for 5 16 commercial structures for titleholder. Alternative shop/or 6 IGA for commercial 16 structure (owner) Commercial tenants to 8 be paid rental 52 allowance Shifting assistance for 9 52 tenants Income generating 10 Assets for Commercial 52 tenants. Commercial Structure 11 134 for squatters Shifting allowance for 12 134 commercial squatters Commercial squatter 13 134 for shop or IGA Subsistence allowance 14 for commercial 138 squatters 15 Vulnerable groups 1642 16 Cattle Shed 11

Table 14-2: Financial Indicators for Progress Sl Total Progress . Monitoring Indicators for Implementation Unit Cost Cost This N Physical Progress Target (in Rs.) Month o. Rs. 1 Land Acquired- private 18.17 2,470,000.0 0 per ha. 2 Land transferred – 0.00 77

Sl Total Progress . Monitoring Indicators for Implementation Unit Cost Cost This N Physical Progress Target (in Rs.) Month o. Government Allowance for those losing 3 2081 20,000.00 land 4 Commercial site (owner) 16 50,000 Pucca housing (Area in Sq 5 800 ft.) 53251.88 6 Semi Pucca (Area in Sq ft.) 12588.77 600 7 Kutcha (Area in Sq ft.) 9803.04 350 8 Commercial site (squatter) 134 30,000 EWS House 9 4 40,000 construction(Non Titleholder) 10 House construction (owners) 23 40,000 Shifting Allowance(Non 11 138 10,000 titleholders) Subsistence Allowance (Non 12 138 11,000 titleholders) Subsistence Allowance 13 39 30,000 (Owners) Shifting 14 39 10,000 Allowance(Titleholders) Economic generating 15 68 75,000 asset(owner/tenant) Economic generating asset 16 134 30,000 (squatter) Rental Value for Commercial 17 52 9,000 tenant Rental Value for Residential 18 1 6,000 tenant. Training for DP(commercial 19 36 15,000 owner , employee) 20 Vulnerable groups 1642 25,000 21 Group Entitlement (kms) 108.62 15,000 Table 14-3: Monitoring Of GRC Sl. 1st 2nd 3rd 4th Particulars No. Quarter Quarter Quarter Quarter 1 No. of cases referred to GRC 2 No. of cases settled by GRC 3 No. of cases pending with GRC 4 Average time taken for settlement of cases 5 No. of GRC meetings 6 Number of DPs moved to court 7 No. of pending cases with the court 8 No. of cases settled by the court 9 No. of GRC meetings

78

Annex 1: Typical Road Cross Section 79

80 81

Annex 2:Community Asset Details

Community Asset details of Link 57A (Gubbi-C S Pura-Beeragonahalli near Yediyur (NH-48))

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 1 0.020 RHS Gubbi Others Arch Pvt. Trust 96.00 18.00 2 0.125 RHS Gubbi Others Bore Hole Panchayat 10.50 2.25 3 0.205 RHS Gubbi Temple Community 20.00 16.00 4 0.52 LHS Gubbi Temple Community 55.00 15.00 5 0.535 RHS Gubbi Others Bore Hole Panchayat 7.50 2.25 6 0.600 RHS Gubbi Others Bore Hole Panchayat 13.50 2.25 0.7 LHS Water 20.00 4.00 7 Gubbi Others Panchayat Tank 0.720 RHS Hand 12.00 2.25 8 Gubbi Panchayat Pump 9 0.73 LHS Gubbi Temple Community 84.00 21.00 10 1.42 LHS K S Palya Aralikatte Community 40.00 16.00 1.700 RHS Mini 9.00 2.25 Water 11 K S Palya Panchayat Supply Tank 1.72 LHS Hand 12.00 2.25 12 K S Palya Panchayat Pump 13 1.845 RHS K S Palya Temple Community 49.00 35.00 14 2.24 LHS Chikkonahalli Temple Community 20.00 4.00 3.495 RHS Water 16.00 4.00 15 G Hosahalli Others Panchayat Tank 16 4.420 RHS G Hosahalli Others Bore Hole Panchayat 15.00 2.25 4.540 RHS Pump 15.00 2.25 17 G Hosahalli Others House & Panchayat Bore Hole 18 4.66 LHS G Hosahalli Aralikatte Community 25.00 10.00 5.030 RHS Primaty 70.00 100.00 19 G Hosahalli Government School 5.28 LHS Water 18.00 2.25 20 G Hosahalli Others Panchayat Tank 6.635 RHS Mini 18.00 4.00 Water 21 Thotasagar Panchayat Supply Tank 6.655 LHS Bus 50.00 10.00 22 Thotasagar Panchayat Stand 23 6.710 RHS Thotasagar Others Bore Hole Panchayat 15.00 2.25 24 8.200 RHS Koppa Temple Community 55.00 10.00 8.808 LHS Mini 7.50 2.25 Water 25 Suraganahalli Panchayat Supply Tank 8.835 LHS Hand 10.50 2.25 26 Suraganahalli Panchayat Pump 10.170 RHS Mini 13.50 3.00 Water 27 Neralakatte Palya Panchayat Supply Tank 11.096 LHS Water 10.00 8.00 28 Kadab Cross Others Panchayat Tank 29 12.210 RHS K G Temple Mini Panchayat 9.00 2.25

82

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) Water Supply Tank 12.276 RHS Mini 12.00 4.00 Water 30 K G Temple Panchayat Supply Tank 31 13.077 RHS K G Temple Others Bore Hole Panchayat 17.25 0.75 13.275 LHS Water 56.00 14.00 32 Lingammanahalli Others Panchayat Tank 13.538 RHS Hand 7.50 2.25 33 Lingammanahalli Panchayat Pump 13.887 RHS Pump 12.00 2.25 34 Ningammanahalli Others House & Panchayat Bore Hole 35 14.020 RHS Ningammanahalli Others Bore Hole Panchayat 12.00 2.25 14.535 RHS Hand 9.00 1.50 36 Kunnal Panchayat Pump 14.545 RHS Water 15.00 6.00 37 Kunnal Others Panchayat Tank 38 14.710 RHS Kunnal Others Bore Hole Panchayat 9.75 2.25 14.725 LHS Water 21.00 7.00 39 Kunnal Others Panchayat Tank 16.239 RHS Kenchanaveeranahalli Bus 30.00 20.00 40 Panchayat Gate Stand 17.017 LHS Hand 16.50 2.25 41 Haruvesandra Panchayat Pump 17.995 RHS Pump 16.50 2.25 42 Haruvesandra Others House & Panchayat Bore Hole 18.185 RHS Pump 9.75 2.25 43 Hindisigere Others House & Panchayat Bore Hole 18.5 LHS Mini 9.00 2.25 Water 44 Hindisigere Panchayat Supply Tank 18.655 LHS Mini 9.00 2.25 Water 45 Hindisigere Panchayat Supply Tank 19.572 RHS Mini 13.50 2.25 Water 46 Hindisigere Panchayat Supply Tank 20.018 LHS Hand 15.00 2.25 47 Chikkonahalli Panchayat Pump 48 20.465 RHS C S Pura Temple Community 18.00 4.00 49 20.935 RHS C S Pura Temple Community 24.00 4.00 20.976 LHS Bus 45.00 3.00 50 C S Pura Panchayat Stand 21.714 RHS Compound 1040.00 40.00 51 C S Pura Others Government Wall 21.860 RHS Compound 600.00 30.00 52 C S Pura Others Government Wall 21.866 RHS Water 30.00 6.00 53 C S Pura Others Panchayat Tank 83

Total Affected Sl. Typeof Other Owner ChainageSide Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 22.41 LHSWater 18.00 6.00 54 Padagudi Others Panchayat Tank 55 22.639RHS Padagudi Temple Community 5.00 2.00 22.658 RHS Mini 9.00 2.25 Water 56 Padagudi Panchayat Supply Tank 23.04 LHSPump 7.50 2.25 57 Padagudi OthersHouse & Panchayat Bore Hole 23.25 LHSVenkategowdana Bus 90.00 40.00 58 Panchayat Palya Stand 26.515 LHSPump 24.00 2.25 59 Kalur OthersHouse & Panchayat Bore Hole 60 28.585 LHS K Kallahalli Temple Community 80.00 40.00 28.605 RHS Hand 12.00 2.25 61 K Kallahalli Panchayat Pump 28.65 RHS Mini 5.25 2.25 Water 62 K Kallahalli Panchayat Supply Tank 28.97 LHSMini 15.00 2.25 Water 63 K Kallahalli Panchayat Supply Tank 31.8 LHSBus 30.00 20.00 64 Ajjenahalli Panchayat Stand 65 32.21 LHS Nagegowdanapalya Others Bore Hole Panchayat 7.50 2.25 32.33 RHS Pump 12.00 2.25 66 Nagegowdanapalya OthersHouse & Panchayat Bore Hole 32.925 RHS Pump 10.50 2.25 67 Nagegowdanapalya OthersHouse & Panchayat Bore Hole 36.315 LHSMini 22.00 4.00 Water 68 Shettgowdanahalli Panchayat Supply Tank 36.335 LHSCompound 315.00 17.50 69 Shettegowdanahalli Others Government Wall 37.45 RHS Hand 8.25 2.25 70 Dodderi Panchayat Pump 37.455 LHSMini 7.50 2.25 Water 71 Dodderi Panchayat Supply Tank 37.51 RHS Mini 10.50 2.25 Water 72 Dodderi Panchayat Supply Tank 37.54 RHS Water 28.00 8.00 73 Dodderi Others Panchayat Tank 42.69 LHSMini 7.50 2.25 Water 74 Ammanahatti Palya Panchayat Supply Tank

84

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 42.98 LHS Compound 225.00 25.00 75 Ammanahatti Others Government Wall 44.56 LHS Compound 330.00 30.00 76 Dodda Madure Others Government Wall 44.795 LHS Hand 9.00 2.25 77 Dodda Madure Panchayat Pump 44.805 LHS Water 32.00 8.00 78 Dodda Madure Others Panchayat Tank 79 44.887 LHS Dodda Madure Aralikatte Community 32.00 8.00 46.34 RHS Chikkamadure Palya Bus 32.00 16.00 80 Panchayat Gate Stand 81 47.88 RHS Jaladagere Others Bore Hole Panchayat 9.00 2.25 82 47.93 RHS Jaladagere Temple Community 48.00 48.00 83 47.96 LHS Jaladagere Temple Community 180.00 840.00 84 48.045 LHS Jaladagere Others Bore Hole Panchayat 7.50 2.25 48.115 LHS Water 18.00 8.00 85 Jaladagere Others Panchayat Tank 86 48.24 RHS Jaladagere Temple Community 72.50 7.50 48.345 RHS Water 14.00 8.00 87 Jaladagere Others Panchayat Tank 48.715 RHS Water 14.00 4.00 88 Jaladagere Others Panchayat Tank 89 48.716 RHS Jaladagere Temple Community 42.00 12.00 49.085 RHS Hand 9.00 2.25 90 Beeraganahalli Panchayat Pump 49.25 LHS Hand 8.25 2.25 91 Beeraganahalli Panchayat Pump

Community Asset Details of link 57B (Beeragonahalli near Yediyur(NH-48) - Kowdley)

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 1 0.020 LHS Yediyur Mini Water Panchayat 15.00 2.25 Supply Tank 2 0.020 LHS Yediyur Others Compound Government 2000.00 100.00 Wall 3 1.550 RHS Yediyur Mini Water Panchayat 13.50 2.25 Supply Tank 4 4.240 LHS Mogal Others Pump Panchayat 16.50 2.25 House & Bore Hole 5 4.560 RHS Mogal Others Arch Panchayat 144.00 12.00 6 4.880 LHS Parvathachikkana Others Pump Panchayat 9.00 2.25 halli House & Bore Hole 7 4.910 LHS Parvathachikkana Others Pump Panchayat 10.50 2.25 halli House & Bore Hole 8 5.310 RHS Markonahalli Others Compound Government 20.00 5.00 Wall 9 5.580 LHS Markonahalli Others Post Office Panchayat 30.00 10.00 10 5.600 RHS Markonahalli Others Water Panchayat 35.00 7.00 House 85

Total Affected Sl. Typeof Other Owner ChainageSide Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 11 5.650RHS Markonahalli Hand Panchayat 10.50 2.25 Pump 12 5.970RHS Markonahalli Others Pump Panchayat 9.00 2.25 House & Bore Hole 13 6.3 LHS Tigalarapura Aralikatte Community 28.00 20.00 14 8.515RHS Hanumapura Mini Water Panchayat 9.00 2.25 Supply Tank 15 8.625 LHS HanumapuraMini Water Panchayat 7.50 2.25 Supply Tank 16 8.76 LHS Hanumapura OthersPump Panchayat 7.50 2.25 House & Bore Hole 17 8.830RHS Hanumapura Primaty Government 80.00 36.00 School 18 8.845 LHS HanumapuraHand Panchayat 15.00 2.25 Pump 19 8.91 LHS HanumapuraMini Water Panchayat 15.00 2.25 Supply Tank 20 8.94 LHS Hanumapura Others Bore Hole Panchayat 16.50 2.25 21 9.48 LHS Hanumapura Bus Stand Panchayat 20.00 16.00 22 10.36 LHS Yalchanahalli Temple Community 30.00 9.00 23 10.4 LHS Yalchanahalli OthersWater Panchayat 50.00 10.00 Tank 24 10.860RHS Amruthur Others Water Panchayat 4.00 4.00 Tank 25 11.400RHS Amruthur Temple Community 16.00 16.00 26 11.660RHS Amruthur Hand Panchayat 18.00 2.25 Pump 27 11.7 LHS AmruthurMini Water Panchayat 15.00 2.25 Supply Tank 28 11.79 LHS AmruthurHand Panchayat 7.50 2.25 Pump 29 12.030RHS Amruthur Hand Panchayat 7.50 2.25 Pump 30 13.2 LHS Amruthur OthersPump Panchayat 30.00 9.00 House, Bore Hole & Water Tank 31 14.08RHS Amruthur Others Pump Panchayat 15.00 2.25 House & Bore Hole 32 15.818RHS Hosakeri Others Pump Panchayat 10.50 2.25 House & Bore Hole 33 15.850RHS Hosakeri Hand Panchayat 6.75 2.25 Pump 34 15.940RHS Hosakeri Hand Panchayat 6.75 2.25 Pump 35 15.942RHS Hosakeri Others Water Panchayat 8.00 3.00 Tank

86

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 36 16.010 RHS Hosakeri Mini Water Panchayat 7.50 2.25 Supply Tank 37 16.140 RHS Hosakeri Temple Community 16.00 10.00 38 16.266 LHS Hosakeri Well Panchayat 32.00 16.00 39 17.265 LHS Jinnagara Mini Water Panchayat 12.00 2.25 Supply Tank 40 17.655 RHS Jinnagara Hand Panchayat 6.00 2.25 Pump 41 17.680 RHS Jinnagara Mini Water Panchayat 7.50 2.25 Supply Tank 42 18.56 LHS Jinnagara Community Public Trust 200.00 110.00 Hall 43 18.603 LHS Jinnagara Well Panchayat 55.00 12.50 44 19.272 LHS Sonaba Hand Panchayat 13.50 2.25 Pump 45 19.28 LHS Sonaba Mini Water Panchayat 13.50 2.25 Supply Tank 46 19.360 RHS Sonaba Others Over Tank Panchayat 36.00 16.00 47 19.445 LHS Sonaba Hand Panchayat 5.25 2.25 Pump 48 19.47 LHS Sonaba Others Milk Diary Panchayat 56.00 4.50 49 19.485 LHS Sonaba Temple Community 36.25 3.75 50 19.535 LHS Sonaba Hand Panchayat 6.00 2.25 Pump 51 21.270 RHS Benavarda Mini Water Panchayat 12.00 2.25 Koppalu Supply Tank 52 21.780 RHS Benavarda Bus Stand Panchayat 28.00 16.00 Koppalu 53 21.950 RHS Benavarda Mini Water Panchayat 12.00 2.25 Koppalu Supply Tank 54 22.8 LHS Hanchipura Others Well & Panchayat 24.00 8.00 MWS 55 22.87 LHS Hanchipura Mini Water Panchayat 7.50 2.25 Supply Tank 56 22.9 LHS Hanchipura Hand Panchayat 6.75 2.25 Pump 57 22.92 LHS Hanchipura Mini Water Panchayat 7.50 1.50 Supply Tank 58 22.922 LHS Hanchipura Others Flag Pole Panchayat 4.00 1.00 59 23.405 LHS Hanchipura Others Pump Panchayat 15.00 2.25 House & Bore Hole 60 23.440 RHS Hanchipura Temple Community 180.00 7.50 61 23.510 RHS Hanchipura Others Bore Hole Panchayat 12.00 2.25 62 23.54 LHS Hanchipura Bus Stand Panchayat 32.00 24.00 63 26.340 RHS Arjunahalli Mini Water Panchayat 15.00 2.25 Supply Tank 87

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 64 26.400 RHS Arjunahalli Hand Panchayat 12.00 2.25 Pump 65 26.780 RHS Arjunahalli Others Pump Panchayat 10.50 2.25 House & Bore Hole

Community Asset Details of link 57C (Kowdley - Mandya)

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 1 0.64 RHS Kowdley Others Water Tap Panchayat 3.25 0.25 2 0.86 RHS Kowdley Others Water Tap Panchayat 4.25 0.25 0.97 RHS Bus 58.50 37.50 3 Kowdley Panchayat Stand 1.020 LHS Hand 10.80 2.25 4 Kowdley Panchayat Pump 1.140 LHS Hand 12.90 2.25 5 Kowdley Panchayat Pump 6 1.390 LHS Kowdley Aralikatte Community 37.45 49.00 7 1.410 LHS Temple Community 23.00 20.00 2.230 LHS Mini 17.00 4.00 Water 8 Kowdley Panchayat Supply Tank 2.260 LHS Water 27.90 3.00 9 Kowdley Others Community Tank 2.350 LHS Water 27.00 3.00 10 Kowdley Others Community Tank 2.410 LHS Mini 11.00 4.00 Water 11 Kowdley Panchayat Supply Tank 3.72 RHS Hand 9.00 2.25 12 Kowdley Panchayat Pump 6.100 LHS Hand 24.00 2.25 13 D Malligere Panchayat Pump 14 6.32 RHS D Malligere Aralikatte Community 42.00 32.00 6.480 LHS Hand 8.25 2.25 15 D Malligere Panchayat Pump 6.485 LHS Water 42.00 15.00 16 D Malligere Others Community Tank 6.52 RHS Overhead 54.00 36.00 17 D Malligere Others Water Panchayat Tank 18 6.670 LHS D Malligere Temple Community 47.50 25.00 19 6.75 RHS D Malligere Others Water Tap Panchayat 2.25 0.25 20 6.76 LHS D Malligere Others Milk Dairy Panchayat 43.88 30.00 21 6.76 RHS D Malligere Others Statue Community 16.75 3.25 22 6.765 RHS D Malligere Others Flag Pole Community 8.40 4.00 6.78 RHS Hand 15.75 2.25 23 D Malligere Panchayat Pump 24 6.92 RHS D Malligere Others Water Tap Panchayat 1.75 0.25 6.925 RHS Primaty 130.00 10.00 25 D Malligere Government School 26 8.235 RHS Hosagavi Bus Panchayat 40.25 24.50

88

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) Stand 8.280 LHS Hand 11.25 2.25 27 Hosagavi Panchayat Pump 8.320 LHS MWS & 18.75 6.25 28 Hosagavi Others Panchayat Bore Well 11.19 RHS Hand 9.00 2.25 29 G Hosalli Panchayat Pump 11.195 RHS Water 18.00 4.50 30 G Hosalli Others Community Tank 31 12.460 LHS Chandagalu Others Water Tap Panchayat 2.50 0.25 32 12.465 RHS Chandagalu Others Flag Pole Community 6.00 2.25 12.55 RHS Hand 6.75 2.25 33 Chandagalu Panchayat Pump 34 12.59 RHS Chandagalu Others Water Tap Panchayat 2.50 0.25 12.640 LHS Primaty 175.00 12.50 35 Chandagalu Government School 12.720 LHS Hand 10.05 2.25 36 Chandagalu Panchayat Pump 12.960 LHS Chandagalu Bus 41.60 26.00 37 Panchayat (Challanayakanahalli) Stand 13.160 LHS Chandagalu 14.00 4.00 38 Shrine Community (Challanayakanahalli) 13.180 LHS Chandagalu 60.75 6.75 39 Aralikatte Community (Challanayakanahalli) 13.240 LHS Chandagalu MWS & 8.75 6.25 40 Others Panchayat (Challanayakanahalli) Bore Well 14.1 RHS MWS & 11.25 6.25 41 Hallegere Others Panchayat Bore Well 42 14.52 RHS Hallegere Temple Community 94.88 172.50 43 14.69 RHS Hallegere Temple Community 73.88 8.63 44 14.900 LHS Hallegere Temple Community 102.50 6.25 16.760 LHS Mini 11.25 6.25 Water 45 Anasosalu Panchayat Supply Tank 46 17.090 LHS Anasosalu Others Flag Pole Community 23.75 6.25 17.095 LHS Overhead 81.60 36.00 47 Anasosalu Others Water Panchayat Tank 48 17.120 LHS Anasosalu Temple Community 55.00 52.25 17.200 LHS Hand 11.25 2.25 49 Anasosalu Panchayat Pump 19.100 LHS Bus 30.45 21.00 50 Kalmaddi Doddi Panchayat Stand 19.105 LHS Hand 9.00 2.25 51 Kalmaddi Doddi Panchayat Pump 52 19.390 LHS Kalmaddi Doddi Others Water Tap Panchayat 4.50 1.00 53 19.720 LHS Ankannana Doddi Others Flag Pole Community 9.00 4.00 19.74 RHS Water 9.30 2.25 54 Ankannana Doddi Others Community Tank 19.85 RHS Hand 6.75 2.25 55 Ankannana Doddi Panchayat Pump 19.860 LHS Primaty 484.50 25.50 56 Ankannana Doddi Government School 20.045 LHS Mini 14.00 4.00 57 Keregodu Water Panchayat Supply 89

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) Tank 20.055 LHS Compound 454.50 22.50 Wall 58 Ankannana Doddi Others Government Police Station 59 20.060 LHS Ankannana Doddi Shrine Community 5.00 1.00 60 20.37 RHS Keregodu Others Bore Well Panchayat 3.15 0.25 61 20.58 RHS Keregodu Hospital Government 118.40 8.00 20.59 RHS Compound 280.00 20.00 62 Keregodu Others Wall PWD Government Office 63 20.85 LHS Keregodu Temple Community 16.00 16.00 64 20.97 LHS Keregodu Temple Community 43.23 12.03 65 20.98 LHS Keregodu Temple Community 46.81 5.89 66 21.2 LHS Keregodu Others Graveyard Community 300.00 30.00 21.56 LHS MWS & 10.50 6.25 67 Keregodu Others Panchayat Bore Well 22.03 LHS Matha 32.40 16.00 Guru 68 Marilingana Doddi Others Community Shankar Mata 22.04 RHS MWS & 15.50 6.25 69 Marilingana Doddi Others Panchayat Bore Well 70 22.045 RHS Marilingana Doddi Temple Community 78.00 65.00 71 22.05 LHS Marilingana Doddi Shrine Community 7.50 2.25 72 22.18 LHS Marilingana Doddi Others Water Tap Panchayat 2.20 0.25 22.4 RHS Hand 15.00 2.25 73 Marilingana Doddi Panchayat Pump 22.61 LHS Pump 43.05 21.00 74 Marilingana Doddi Others Panchayat House 75 22.62 RHS Marilingana Doddi Shrine Community 12.00 4.00 22.64 RHS Hand 8.25 2.25 76 Kommerahalli Panchayat Pump 22.71 LHS Hand 6.45 2.25 77 Marilingana Doddi Panchayat Pump 25.76 LHS Bus 46.25 20.00 78 Hulivana Panchayat Stand 79 26.42 RHS Hulivana Others Water Tap Panchayat 3.70 0.25 80 26.93 LHS Hulivana Shrine Community 9.90 2.25 27.14 LHS MWS & 10.00 6.25 81 Hulivana Others Panchayat Bore Well 27.285 RHS MWS & 11.25 6.25 82 Hulivana Others Panchayat Bore Well 27.36 RHS Hand 12.90 2.25 83 Hulivana Panchayat Pump 27.485 RHS Mini 13.60 4.00 Water 84 Honaganahalli Panchayat Supply Tank 27.78 RHS Hand 24.00 2.25 85 Honaganahalli Panchayat Pump 27.785 RHS Bus 74.25 22.00 86 Honaganahalli Panchayat Stand 87 27.79 RHS Honaganahalli Aralikatte Community 54.00 64.00 88 27.79 RHS Honaganahalli Hospital Government 310.00 10.00 89 29.06 LHS Kommerahalli Others Flag Pole Community 6.75 2.25

90

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq.m) (Sq.m) 29.095 LHS Hand 9.45 2.25 90 Kommerahalli Panchayat Pump 29.52 LHS MWS & 11.25 6.25 91 Kommerahalli Others Panchayat Bore Well 92 30.4 LHS Sathanur Aralikatte Community 13.50 9.00 93 30.42 RHS Sathanur Others Water Tap Panchayat 2.25 0.25 31.04 RHS Hand 13.20 2.25 94 Mandya Panchayat Pump 31.05 RHS MWS & 11.25 6.25 95 Mandya Others Panchayat Bore Well 96 31.185 RHS Mandya Others Water Tap Panchayat 2.25 0.25 31.2 LHS MWS & 13.75 6.25 97 Mandya Others Panchayat Bore Well 31.26 RHS Hand 11.70 2.25 98 Mandya Panchayat Pump 31.49 LHS High 1659.00 70.00 99 Mandya Government School 31.52 LHS Bus 50.38 26.00 100 Mandya Panchayat Stand 31.76 RHS Hand 9.00 2.25 101 Mandya Panchayat Pump 91

Annex 3: Census and Community Asset Survey Schedules

Census Survey Schedules

PART 1

ASSET INFORMATION 

T-T

Name of the Investigator: ______Date: ______

1.0 GENERAL IDENTIFICATION

1.1 Corridor Name 1.2 Corridor No

1.3 Link Name

1.4 Link No

1.5 Chainage

1.6 Side (LHS/RHS)

1.7 i) District

ii) Taluk

iii) Village/Town

1.8 Name of the owner

1.9 Name of the Respondent

1.10 Type of likely loss

1. Residential 2. Commercial 3. Residential cum Commercial

4. Office 5. Cattle Shed 6. Agricultural land 7. Farm House 8. Boundary Walls 9. Water bodies 10. Institutions 11. Livelihood / Income 12. Others (sp.)

Location: 1.Rural 2.Semi Urban 3.Town 4.City 5. Industrial

92

2.0 STRUCTURE IDENTIFICATION

2.1 Sl.No. of the Structure : ______

2.2 Address of the Structure : ______

2.3 Status of Occupier (Tick in the appropriate box)

Owner Legal Non-title holders Vacant Tenant

Squatter Encroacher

2.4 Ownership (Tick under appropriate type and enter the no. of households under the same)

Private Government Trust Community

Type of ownership

2.5 Do you have legal document of

Structure 1. Yes 2. No RTC No. Sub No.

Agricultural land 1. Yes 2. No RTC No. Sub No.

(to be asked only to the owner) (If yes, ask for the legal document and check it with the Village Accountant)

3.0 PROOF OF RESIDENCE

3.1 Do you own a ration card? 1. Yes 2. No

Green Red Yellow (Please verify the category of card: APL/BPL/ Others ______) 3.2 If yes, Card No. ______

3.3 If Yes, since how long (only year) ______93

4.0 TYPE OF CONSTRUCTION

4.1 MEASUREMENT OF THE STRUCTURE

(In Sq.m)

OFFSET FROM EXISTING OFFSET FROM EDGE OF ASSET UP CENTRAL LINE TO AREA GETTING AFFECTED

LAND STRUCTURE LAND STRUCTURE Starting Metre Ending Metre Width Total Area (in sq. m)

4.2 STRUCTURE DETAILS Plinth Area Total Area being Sl.No Type of structure Length Width affected (in Sq.m) 1 Type A (With RCC roof/ Stone/Brick work in Cement Mortar and plastered with cement mortar, Class II woodwork with fixtures, Mosaic/Polished slab flooring with water supply, sanitary and electrical works. 2 Type B (With RCC roof, Stone/Brick work in Cement Mortar and plastered with cement mortar/ Class II wood work with fixtures, cement concrete flooring with water supply, sanitary and electrical works. 3 Type C with Mangalore tile roof, Stone/Country Brick work in Cement Mortar and plastered with cement mortar, ordinary woodwork fixtures. Flooring …………..(specify) with water supply sanitary and electrical work. 4 Type D with AC/GI sheet roof, Stone/Country Brick work in Mud Mortar and plastered with Cement Mortar, ordinary wood work fixtures flooring……………….(specify) with water supply sanitary and electrical work. Type E with Stone/Country Brick/Mud 5 walls ordinary slab flooring with ordinary wood work doors, roofing with slab/sheets 6 Type F with stone slab/GI sheet for walls with Mud flooring, Thatched roof 94

Plinth Area Total Area being Sl.No Type of structure Length Width affected (in Sq.m) 7 Type G with Tatti walls with thatched roof mud flooring 8 Type I Wooden Box 9 Type J only Basement 10 Type K Upto lintel level

4.3 SITE MEASUREMENT

Sl. Width Total Area Area Length No. (in Sq. m) 1 Built up area 2 Open Space 3 Total Area

4.4 BOUNDARY WALL DETAILS

Sl. Boundary/Compound wall Width Total Area No. Length (in Sq. m) 1 Barbed wire fencing 2 Stone Masonry 3 Brick/Stone Masonry 4 Mud Wall 5 Others (Specify)

4.5 GATE DETAILS

Sl. Length (in m) Height (in m) No. 15 Type of Gate 1 M.S 2 Wooden 3 Others

4.6 Diagram of the Structure (Rough diagram with dimension – Not to Scale)

4.7 No. of Floors

Ground Ground+1 Others Total Floor Area (all floors) (Sq. m)

4.8 DETAILS OF STRUCTURE IN ROW Give the following details

Sl.No. TYPE OF STRUCTURES IN ROW* 95

* 1. Pucca 2. Semi-Pucca 3. Kutcha

5.0 WATER SOURCES GETTING AFFECTED

Sources (in No.) User (use code)* Units to be acquired Dug Wells Tube Wells LI Points *[1. Domestic 2. Agriculture 3. Industrial 4. Others (to be specified)]

6.0 TREES COMING WITHIN LAND AREA TO BE ACQUIRED

Trees to be acquired Species - Type (In nos.) Fruit bearing Fodder Fuel wood

205. (PHOTOGRAPH TO BE ATTACHED – STRUCTURE ALONG WITH HEAD OF HOUSEHOLD/ RESPONDENT)

96

PART – II

HOUSE HOLD SCHEDULE (FOR OWNERS, SQUATTERS, ENCROACHERS)

1.0 HOUSEHOLD IDENTIFICATION

1.1 Name of the head of the HH: ______1.2 Name of the Respondent: ______

2.0 SOCIAL GROUP PARTICULARS

2.1 Religious Group

1. Hindu 2. Muslim 3. Sikh

4. Christian 5. Jain 6.Others (specify)______

2.2 Social Stratification:

1.SC 2.ST 3.Others (General)

2.3 Caste ______

3.0 Indebtedness Please indicate your borrowings during last one year

Source Reason for Amount Borrowed Borrowing (in Rs.) Bank Private Money Lender

Friends/Relatives

Others (Specify)

4.0 DETAILS OF HOUSEHOLD ASSETS OWNED Do you own any of the following?

1. Colour TV 1.Yes 2. No.

2. Refrigerator 1.Yes 2. No.

3. 2-Wheeler/4-Wheeler 1.Yes 2. No.

4. Cooking gas (LPG) 1.Yes 2. No.

5.Telephone 1.Yes 2. No. 97

5.0 DETAILS OF AGRICULTURAL EQUIPMENTS OWNED

Do you own any of the following?

1. Tractor 1.Yes 2. No.

2. Bullock carts 1.Yes 2. No.

3. Harversters 1.Yes 2. No.

4. Sprayer 1.Yes 2. No.

5. Others (Specify) 1.Yes 2. No.

6.0 DETAILS OF HOUSEHOLD MEMBER(S) WITH DISABILITY

Name of the household Sl.No. Sex Age Nature of Disability member

98

7.0 HOUSEHOLD PARTICULARS

7.1 Kindly provide the following details.

Sex Relation Total Income (Rs.) Income (Rs.) Sl. Name of the household (Male/ Marital Educatio Occupation with Head of Age No. members Femal Status n Subsidiar Subsidiar Within Outside HH Main Main e) y y COI* COI* 1 2 3 4 5 6 7 8 9 10 11 12 * Corridor of Impact (COI) (Please ensure that the respondent is above 18 yrs

99

Code for Relation with Head of Household

1. Self 2. Son 3. Brother 4. Son-in-law 5. Brother-in-law 6. Cousin 7. Daughter 8. Wife 9. Daughter-in-law 10. Sister 11. Sister-in-law 12. Mother 13. Mother-in-law 14. Grand Son 15. Grand Daughter 16. Grand Daughter-in-law 17. Grand Son-in-law 18. Niece

19. Nephew 20. Father 21. Others

Code for Marital Status

1. Married 2. Unmarried 3. Divorced 4. Separated 5. Widow 6. Widower 7. Deserted

Code for Education

1. Illiterate 2. Just literate 3. Primary (upto 4th) 4. Middle (5th, 6th, 7th) 5. Secondary (8th, 9th, 10th 6. Intermediate (12th pass) pass) 7. Graduate 8. Post Graduate 9. ITI/ Diploma

10. Engineer 11. Doctor 12. Others (specify)

Code for Occupation

1. Agriculture 2. Agriculture labour Allied agriculture activities (e.g. dairy, poultry, goatery, piggery, sheep rearing etc.) Service HH industries (specify) Commerce/Trade Professional (doctor, engineer, etc.) Skilled labor (welders, fitters, turner, plumber, electrician, mechanic, mason, etc.) Artisans (cobbler, etc.) Others (Specify)

8.0 LAND UTILISATION

8.1 Kindly give the details of landholding (applicable in case of acquisition of land) Kindly check up the ownership of land with the land records available with the respondents.

100

(Unit in Sq. m) Wet Type Dry Land Garden Land Total Land 1. Total land owned

2. Land Proposed to be acquired

3. Remaining land

8.2 AFFECTED CATEGORY (Tick the appropriate category)

1 Title Land 2 Tenancy Land 3 Encroached Land 4 Bagar Hukum

8.3 LAND UTILISATION FOR AGRICULTURAL ENCROACHERS

Total area of encroached land

Type of crop grown

8.4 MARKET VALUE

Please provide the current market value of the land likely to be affected.

8.5 CROPPING PATTERN (Only in Case of Bypasses and Realignments) Kindly give the following details Area Cultivated Income from Crop Yield Rate (in land which is Season Sl.No. Name Irrigated Dry (Qtls/Acre) Rs./Qtls) likely to be acquired Kharif 1 2

3 Rabi 1 2

3 Summer 1

2

3 101

16 PART-III

FOR OWNERS and SQUATTERS (Only in case of the total loss of the structure)

1.0 STRUCTURE

RESIDENTIAL

1.1 Is your house electrified 1. Yes 2. No

1.2 Do you have piped water connection? 1. Yes 2. No

1.3 If no, what is your source of drinking water?

a) Open Well b) Bore Well c) Piped Water d) Others (Specify) ______

COMMERCIAL

1.4 What type of business you are doing?

1. Tea Stall 2. Grocery 3. Garments 4. Cloth Shop 5. Medical Store 6. Auto repair 7. Auto spare parts 8. Sweet Stall 9. Eatery (Dhaba) 10. Fruits and 11. Only fruits 12. Only vegetable Vegetable 13. Snacks 14. Pan/Cigarette 15. Bicycle repair 16. Tyre repairing 17. Tailoring 18. General Merchant 19. Clinic 20. School/College 21.Motel/Hotel 22. Electrical goods 23. Barber 24. Bakery 25. Others (specify)

1.5 Do you have any assistants/employees to help in the business? 1. Yes 2. No

1.6 If yes, how many? (in nos.) ______

1.7 What is your net income/year ? Rs. ______

102

PART IV

17 FOR TENANTS

1.0 RESIDENTIAL

1.1 Name and Address of the Owner ______

1.2 Name and Address of the Tenant ______

1.3 How long are you residing in this place (in years)? ______

1.4 How much rent you pay (in Rs.)? ______

1.5 Do you have a Rental Agreement ? 1. Yes 2. No

COMMERCIAL

1.6 Name and Address of the Owner ______

1.7 Name and Address of the Tenant ______

1.8 From how long you are running business in this structure (in years)? ______

1.9 How much rent do you pay/month? Rs. ______

1.10 Do you have a Rental Agreement ? 1. Yes 2. No

1.11 Do you have any helping hand? 1. Yes 2. No

1.12 If yes, how many (in Nos.)? ______103

1.13 What type of business you are doing? ______

1. Tea Stall 2. Grocery 3. Garments 4. Cloth Shop 5. Medical Store 6. Auto repair 7. Auto spare parts 8. Sweat Stall 9. Eatery (Dhaba) 10. Fruits and 11. Only fruits 12. Only vegetable Vegetable 13. Snacks 14. Pan/Cigarette 15. Bicycle repair 16. Tyre repairing 17. Tailoring 18. General Merchant 19. Clinic 20. School/College 21.Motel/Hotel 22. Electrical goods 23. Barber 24. Bakery 25. Others (specify)

1.14 Usage of structure? 1.Shop 2.Godown 3.Workshop 4.Office

1.15 Turnover per month? Rs. ______

104

PART – V EMPLOYEES IN COMMERCIAL ESTABLISHMENTS Employee No.1 1. Name ______

2. Address ______

3. Age (years) ______

4. Sex M F

5. Working Full time Part-time

6. Education ______

7. Income (Rs.) ______

8. Any other source (specify) ______

9. Any other income generating skill known ______

Employee No.2 1. Name ______

2. Address ______

3. Age (years) ______

4. Sex M F

5. Working Full time Part-time

6. Education ______105

7. Income (Rs.) ______

8. Any other source (specify) ______

9. Any other income generating skill known ______

Employee No.3 1. Name ______

2. Address ______

3. Age (years) ______

4. Sex M F

5. Working Full time Part-time

6. Education ______

7. Income (Rs.) ______

8. Any other source (specify) ______

9. Any other income generating skill known ______

106

PART VI

18 EXTENT OF LOSS

(NOT TO BE ASKED BUT TO BE ASSESSED BY THE INVESTIGATOR)

1. Losing Total House 2. Losing Partial House 3. Losing Total House and part of Plot (Aangan or Courtyard) 4. Losing Total Plot and Total House 5. Losing Total Plot and Partial House 6. Losing Partial Plot 7. Losing Total Commercial Structure 8. Losing Partial Commercial Structure 9. Losing Total Commercial Structure and Partial Plot 10. Losing Total Commercial Structure and Total Plot 11. Losing Partial Commercial Structure and Total Plot 12. Losing Total House and Total Commercial Structure 13. Losing Total House, Total Commercial Structure and Total Plot 14. Losing Total House, Total Commercial Structure and Part of Plot 15. Losing Total House, Partial Commercial Structure and Part of Plot 16. Losing Partial House, Partial Commercial Structure and Part of Plot 17. Losing Total House and Partial Commercial Structure 18. Losing Total Commercial Structure and Part of House 19. Losing Total Boundary Wall 20. Losing Partial Boundary Wall 21. Losing Total Agricultural Land 22. Losing Partial Agricultural Land 23. Losing Total Cattle Shed 24. Losing Part of Cattle Shed 25. Losing Water bodies 26. Losing Total Livelihood for Commercial Tenant 27. Others (Specify) 107

In case the tenancy/ownership is under dispute (legal or otherwise) please make a short note below

Field Supervisor:______Date: ______

Endorsed by:

Revenue Officer:______Date: ______

PWD Officer: ______Date: ______

108

Community Asset Schedule

Q.No.: ______

Name of Investigator: ______Date : ______

1.0 GENERAL IDENTIFICATION

1.1 Corridor Name

1.5 Corridor No

1.6 Link Name

1.7 Link No

1.9 Chainage

1.10 Side ((LHS/RHS)

1.11 i) District

ii) Taluk

iii) Village/Town

1.12 Name of the owner

1.9 Name of the Respondent

2.0 STRUCTURE IDENTIFICATION 2.1 Sl. No. of the structure :______

2.2 Address of the structure: ______

2.3 Tick the relevant community asset affected:

Primary High school Anganavadi Samadhi College (C ) Mosque (M) school (PS) (HS) (A) (S) Temple (T) Shrine (SH) Primary Health Community Aralikatte Hospital (H) Center Hall/Club (CH) (AK) (PHC/PHU) Bus stand Grazing land Well (W) Handpump (HP) Irrigation (IP) Pond (P) (BS) (GL) Points Mini Water Others Supply tank including (MWS) cultural properties (SPECIFY) 109

2.4 Type of Ownership Tick the relevant box

Private Government Panchayat Pvt. Trust Public Trust Community

2.5 Measurement of the structure

OFFSET FROM EXISTING OFFSET FROM EDGE OF ASSET CENTRAL LINE (in Sq.m) UP TO AREA GETTING AFFECTED (in Sq.m)

LAND STRUCTURE LAND STRUCTURE

Starting Metre Ending Metre Width Total Area (in sq. m)

2.6 What is the approximate location of the community asset?

1. In the beginning 2. Central part 3. Towards End

2.7 Diagram of the structure

2.8 Please attach a photograph of the structure with the assigning number.

110

Annex 4: Details of Land Acquisition

Affected Land/Area Details for 57A Area in Acre- Gunta

% of Affected Total Sl. No. Village Survey No. OwnerName Affected Area Area Area

Dasegowda S/o Kavalugara 1 Ajjanahalli 3/4P1,3/4P2 0.00 10.80 Dasegowda

2 Ajjanahalli 16,17 Ramakrishna 0.32 14.10 2.27 3 Ajjanahalli 16,17 Rangaramaiah 4 Ajjanahalli 16,17 Basavaraja S/o Rangappa 5 Ajjanahalli 16,17 Puttaiah 6 Ajjanahalli 19/1,18 Puttegowda S/o Nagaiah 0.07 1.20 5.83 7 Ajjanahalli 20 Gomala 0.30 18.04 1.66 8 Ajjanahalli 20 Graveyard 9 Ajjanahalli 20 Puttegowda S/o Nagaiah 10 Ajjanahalli 21 Gomala & Gundu Thopu 0.27 52.25 0.52 11 Ajjanahalli 21/P2 Kehcnaiah S/o Nagaiah

Savithramma S/o 12 Ajjanahalli 21/P4 Narasimhaiah

Hucchamma W/o 13 Ajjanahalli 40 0.08 12.32 0.65 Thimmegowda

14 Ajjanahalli 40/3 Gomala 15 Ajjanahalli 40,43,38 Kalyanamma W/o Krishnaiah

Lakshmamma W/o 16 Ajjanahalli 43 0.00 6.14 Hattigowda

17 Ajjanahalli 43 Nagaraju S/o Hattegowda 18 Ajjanahalli 43 Nagaiah S/o Hattegowda

Narasimhayya S/o Late 19 Amanakere 49/3B karigerinarasayya

20 Amanakere 49/2 Narayannappa S/o Basayya 0.04 0.16 25.00

Hogabattibasavaraja S/o 21 Amanakere 55/4B,48/2B 0.04 1.01 3.96 Hogebatti ramayya

22 Amanakere 55/2 Sidhappa S/o Nagappa

G R Narayanappa S/o L R 23 Amanakere 55/1 Ramayya

G K Kumbanarashayya S/o 24 Amanakere 393/1 0.00 2.08 0.00 Kumbhayya

G K Chikkanarasayya S/o 25 Amanakere 393 Kumbhayya 111

Doddaramayya S/o 26 Amanakere 395/2 0.00 0.22 0.00 Chennayya

Rangaswamy S/o 27 Amanakere 394 0.05 0.40 12.50 Govindhappa

Mullakattayya S/o Lt 28 Amanakere 47 0.01 1.06 0.94 doddahucchayya

29 Beluru 66 Karabu 0.02 6.02 0.33

Mudduhanumayya S/o Late 30 Beluru 64 0.12 6.26 1.92 Doddahanumaiah

31 Beluru 63/5 Channamma W/o Ranganna 0.00 3.02 0.00 32 Beluru 63/3 B T Muniyappa S/o Thimayya 33 Beluru 63/2,63/1 B T Muniyappa S/o Thimayya 34 Beluru 63/1 Ganganna S/o Rangayya

K S Rangegowda S/o 35 Beluru 62 0.04 211.22 0.02 Sannarongegowda

36 C S Pura 12/2 Narasimhayya u Gundayya 0.00 5.26 37 C S Pura 12/1 District health and 38 C S Pura 9/2 VeregowdaS/o Bora 0.00 1.20

C R Yogesh S/0 Late 39 C S Pura 8/4 0.00 3.08 Narasimharaju u Rajanna

C R Yogesh S/0 Late 40 C S Pura 8/2 Narasimharaju u Rajanna

C R Narashimjeyar S\o Late 41 C S Pura 8/1 Sampathayya

42 C S Pura 8/3 T Thimayya S/o Venkatayya

Gangadarayya S/o Late 43 C S Pura 7/5 0.00 5.00 Badregowda

Kempamma S/o 44 C S Pura 7/3 Kempalingayya

C T Govindayya S/o 45 C S Pura 7/3 Thimmegowda

Kempegowda S/o Late 46 C S Pura 6/5,6/6 0.00 3.28 Badregowda

N Renukamba W/o 47 C S Pura 6/1 Rameshrao

48 C S Pura 6/1 Nanjappa S/o Veeregowda

Ganganarasimhayya S/o 49 C S Pura 22/5-P1,49/15B 0.00 0.32 Narasihayya

50 C S Pura 22/7 Puttayya S/o Late rangayya 51 C S Pura 22/6 Srinivasa S/o Bhimaiah 52 C S Pura 22/2 Narasimayya S/o Narasayya 53 C S Pura 22/2 Narasayya S/o Narasayya

112

54 C S Pura 22/2 Venkatamma S/o Nanjappa 55 C S Pura 22/2 Rangayya S/o Narassayya

Narassa S/o 56 C S Pura 21/3 0.00 5.12 Narassabuddakambana

G N Nagarathna S\o D 57 C S Pura 21/3 Narasimhamurthy

58 C S Pura 21/1 Ningegowda S/o Andanayya 59 C S Pura 22/1 Ningegowda S/o Andanayya 0.00 0.14

Yagna Narayana Shasthri 60 C S Pura 19/1 0.00 4.34 S/o Narasimhashastri

61 C S Pura 17/5B Road N A 0.00 5.38 62 C S Pura 17/5B Varadaraju S/o Ganganna 63 C S Pura 17/4A Chekkegowda S/o Dodayya 64 C S Pura 17/4A Hucchayya S/o Dodayya 65 C S Pura 17/2,17/6 Hucchayya S/o Kempayya

Hanumanthaiah S/o 66 C S Pura 53/2B1 0.02 0.34 5.88 Chikkarangaiah

Govindaiah S/o Katari 67 C S Pura 52/5 0.00 2.25 0.00 Thimmaiah

68 C S Pura 52/1B Road 69 C S Pura 52/2A Nanjaiah S/o Kempamma

Ramanjanaiah S/o 70 C S Pura 52/3A Kalanathimmaiah

Nanjamma W/o 71 C S Pura 51/2 0.01 2.02 0.50 Channaveeraiah

Susheelamma W/o Late 72 C S Pura 51/4 Ramegowda Narasimaha S/o 73 C S Pura 50/3 0.01 1.02 0.98 Doddanarasa Narasimhaiah U. Gundaiah 74 C S Pura 50/1A S/o Doddaiah

50/1B,52/2B,53/1B,53/2B2- 75 C S Pura Road p2,52/3B,53/2B,-p1,51/1B

Kalaboregowda S/o 76 C S Pura 49/13 0.00 2.14 Kempegowda

Kalana Thimmaiah S/o 77 C S Pura 49/1A Kempamma

78 C S Pura 49/2A Doddamma W/o Hanumaiah 79 C S Pura 49/3A Srinivasa S/o Bhimaiah 113

80 C S Pura 49/9A Shivanna 81 C S Pura 45/3 J P Basavaraju Puttaiah 0.01 1.04 0.96

82 C S Pura 43,49,39,16,17,19,49,43,45,49 Road 0.01 1.00 1.00

Vijaya Lakshmma W/o 83 C S Pura 43/1A Thimmappagowda

84 C S Pura 39/2A Govindaiah S/o Doddaiah 0.03 1.02 2.94 85 C S Pura 39/2B Road 86 C S Pura 39/1A1 Govindaiah S/o Doddaiah 87 C S Pura 39/1A1 Hucchamma U. Kamalamma 88 C S Pura 39/1A1 Bharathibai W/o Shimojirao 89 C S Pura 39/1A1 Srinivasaiah S/o Rangappa

Mahadevaiah S/o 90 C S Pura 39/1A2 Siddaramaiah

C K Umesha S/o Late 91 C S Pura 39/1A3 Kempaiah

Prasannakumara 92 C S Pura 39/1A4 Doddalingappa

N R Jagadish S/o V R 93 C S Pura 23/6 0.01 6.11 0.16 Ramachandraiah

Shanthamma W/o M B 94 C S Pura 23/6 Mahalingaiah Hanumanthaiah S/o 95 C S Pura 23/8 Siddappa 96 C S Pura 23/2C Kemppaiah S/o Doddabora

K S Honnachar S/o 97 C S Pura 23/1A1 Shivalingachar

98 C S Pura 23/3A1 Kalaiah 99 C S Pura 23/3A2 Boregowda 100 C S Pura 23/1A2-p1 Honnachar 101 C S Pura 23/1A2-p2 Thirumalaiah W/o Doddaiah

N M Shivanna S/o Late 102 C S Pura 23/3A1-p1 Mariyappa

Gattaiah S/o 103 C S Pura 23/3A1-p2 Chikkavenkataiah

Satyabhama W/o Late C S 104 C S Pura 23/2Ap Premojirao

105 C S Pura 23/7A3 Gottilla 106 C S Pura 3/1 Thote Inam 0.00 3.24 107 C S Pura 3/2 for Police Quarters 108 C S Pura 189/2B C L Gangadhar 0.06 1.14 5.26

114

109 C S Pura 189/2A B V Lakshmanagowda Cheluvaiah S/o 110 C S Pura 188/2 0.04 4.20 0.95 Chennegowda 111 C S Pura 188/1A N A Kharabhu 112 C S Pura 188/1B B Bairaiah S/o Boregowda 113 C S Pura 181/4,181/3 Boregowda S/o Thathaiah 0.02 1.36 1.47 114 C S Pura 186/4 Kempaiah S/o Muddegowda 0.08 0.22 36.36

Gangadaraiah S/o 115 C S Pura 184,186/2,185/1 0.04 1.32 3.03 Veeregowda

116 C S Pura A. Kere 364/2A Nanjappa S/o Chikkegowda 0.17 0.28 60.71

117 C S Pura A. Kere 365/2 Cheluvaraya S/o Singaiah 0.25 2.38 10.50

Rangashyamaiah S/o 118 C S Pura A. Kere 365366 Tirumalaiah

Alamelamma W/o 119 C S Pura A. Kere 365/1 Muddurangamma

Bhuthaiah U. Dasegowda S/o 120 C S Pura A. Kere 361/p 0.24 2.20 10.91 Paligowda

121 Dodda Madure Kharabhu 0.10 25.25 0.40

Erannagowda S\o 122 Dodda Madure 213/1 0.15 2.16 6.94 Lakkanagowda

123 Dodda Madure 213/3 Narassama s\o Lakkanna 124 Dodda Madure 213/5 Rammanna S\O Eranna 125 Dodda Madure 213/7 Huchamma W/0 Hallaya

D L Chennagowda S/O M 126 Dodda Madure 231227 0.07 0.16 43.75 Lakkannagowda

127 Dodda Madure 228 Lakanna S\o Giriya 0.05 0.32 15.63

Badagi Divakarachari S/o 128 Dodda Madure 229,69 0.10 2.06 4.85 Puttalingacharya

129 Dodda Madure 230/2 Arunkumar S/O Kanthasheeti 0.05 0.10 50.00

Nanjegowda S/O 130 Dodda Madure 67/4 0.07 1.22 5.74 Appajigowda

131 Dodda Madure 231/5A Lakkamma W/o Muddayya 0.00 0.03 0.00 132 Dodda Madure 235 Vijayamma W/o D Lakkanna 0.19 1.09 17.43

S Gangaiah S/o 133 Dodda Madure 235 0.00 Srigangegowda

134 Dodda Madure 235 Eranna 0.00 135 Dodda Madure 236/2L Kempayya S/o Kempegowda 0.17 0.06 283.33

Kempayya urf kariyanna S/O 136 Dodda Madure 70/6 0.17 1.38 12.32 Kempagowda

137 Dodda Madure 213/4 Gajjamma W/o Ranggaya 0.16 0.30 53.33 115

Channaya S/o Lakkanna uf 138 Dodda Madure 4/3 0.08 3.19 2.51 Yajamannaya

139 Dodda Madure 4/10A,4/4 Hombalamma W/o Rangayya 140 Dodda Madure 4/6 Lakkanna S/o Erannagowda 141 Dodda Madure 4/7 Thimmamma W/o Veeranna

Lakkanagowda S/o 142 Dodda Madure 4/1 Chennigayya

143 Dodda Madure 4/8A Srinivasa S/o Mudalagiri

Lakkannagowda S/o 144 Dodda Madure 4/10B Chennegowda

D R Basavaraju S/o Late 145 Dodda Madure 4/12 Rangayya

146 Dodda Madure 4/8B Thirukayya S/o Konayya

D K Nanjundayya S/o 147 Dodda Madure 72/4 0.04 1.20 3.33 Kappayya

148 Dodda Madure 72,62 Shivanna S/o Channayya

D N Muniraju S/o 149 Dodda Madure 72/15 Nanjegowda

150 Dodda Madure 71/1 M Gangayya S/o Andanayya 0.03 2.26 1.33 151 Dodda Madure 71/2 Lakkanna S/o Lakkamma 152 Dodda Madure 71/4A Modlayya S/o Thimayya

Gangayya S/o 153 Dodda Madure 71/10,72/11 Channaborayya

154 Dodda Madure 71/13 Andannayya S/o Borayya

155 Dodda Madure 70/80A D M Modlayya S/o Kariyanna

D G Padmanabayya S/o 156 Dodda Madure 70/9A 0.09 2.14 4.21 Gangayya

157 Dodda Madure 70/10 Sakamma W/o Bhadrayya 158 Dodda Madure 70/11 Modlayya S/o Thimmayya

D B Hucchegowda S/o 159 Dodda Madure 70/12 Borayya

160 Dodda Madure 70/13 Gangayya S\o Borayya

161 Dodda Madure 70/1A,70/2A Gangayya S\o Korlayya

162 Dodda Madure 70/1A,70/2A Shivalingayya S/o Borayya

Gangayya S/o 163 Dodda Madure 61/7,69/15,71/6 0.00 1.38 0.00 Channaborayya

164 Dodda Madure 69/7 Lakkamma D/o Hattamma 0.00 1.36 0.00 165 Dodda Madure 69/4 Hombamma W/o Nanjayya 166 Dodda Madure 69/9 Erayya S/o Maduregowda

116

167 Dodda Madure 69/14 Mayanna S/o Nanjayya

Lakamma W/o 168 Dodda Madure 69/22C Channaborayya

Nanjamma W/o Late 169 Dodda Madure 69/24 lakkanna

Madurangayya S/o 170 Dodda Madure 69/8 Sannananjegowda

Kempayya u Kariyanna S/o 171 Dodda Madure 68/6 0.03 3.14 0.96 Kempegowda

172 Dodda Madure 68/5 Gangayya S/o Borayya

Erayya S/o Late 173 Dodda Madure 67/3 0.00 6.20 0.00 maduregowda

D L Chennegowda S/o M 174 Dodda Madure 67/1B 0.00 Lakannagowda

D C Gangadara S/o 175 Dodda Madure 67/5P1,67/5P2 0.00 chennegowda uf kalurayya

176 Dodda Madure 67/7A,61/8 Borayya S/o Marihuchayya 0.00

Borayya u kurlayya S\o 177 Dodda Madure 67/7B-P2 0.00 Huchchegowda

178 Dodda Madure 67/4-P1 Nanjundayya S/o Najegowda 0.00 179 Dodda Madure 67/4-P Channappa S/o Channappa 0.00 Sannamma W/o 180 Dodda Madure 66/1 0.01 2.12 0.47 Chennamma 181 Dodda Madure 66/5 Lakkanna S/o Channayya 182 Dodda Madure 66/5 E Channegowda S/o Eranna 183 Dodda Madure 66/5 Hattamma W/o channayya

Lakkannagowda S/o 184 Dodda Madure 66/6 Madhurayya

Lakshmanmma W/o 185 Dodda Madure 65/1B 0.02 2.02 0.99 sannayya

D H Lakkannagowda S/o 186 Dodda Madure 65/3 Erannagowda

Channayya S\o 187 Dodda Madure 64/4,234 0.03 2.40 1.25 Lakkannagowda

Lakkannagowda S/o 188 Dodda Madure 62/1,4/5A 0.00 2.28 0.00 Channigayya

189 Dodda Madure 89 Shivanna S/o Madurappa 0.17 0.36 47.22 190 Dodda Madure 28 Sarkari Kere Angala 0.16 161.34 0.10

Chennigaiah S/o 191 Dodda Madure 60/7 0.19 2.30 8.26 Madhuregowda

D K Nanjundayya S/o 192 Dodda Madure 61/6,62/4 Kappayya 117

Lakkanna Mai. Ga. Thayi 193 Dodda Madure 61/1 0.23 3.34 6.89 Lakkamma

Ningamma W/o 194 Dodda Madure 61/2 Hucchegowda

195 Dodda Madure 61/3 Kapanaiah S/o Lingegowda 196 Dodda Madure 61/3 Eranna

D.L Chennegowda S/o M 197 Dodda Madure 61/4 Lakkanagowda

198 G Hosahalli 54/2B Kiramkansab 0.22 0.14 157.14

199 G Hosahalli 24/1B,24/2B Road 0.13 4.26 3.05

200 G Hosahalli 24 R Palakshayya S/o Rudrayya R sadashivayya S/o 201 G Hosahalli 24/2C Rudrayya R Sadashivayya S/o 202 G Hosahalli 23 0.29 0.28 103.57 Rudrayya

R Sadashivayya S/o Mysore 203 G Hosahalli 22 0.08 0.10 80.00 Rudrappa

Rangayya B S/o 204 G Hosahalli 20/1 0.06 1.00 6.00 Sannarangegowda

205 G Hosahalli 20/2B Murudappa S/o Bashettappa 206 G Hosahalli 4/1A H D Kantharajaarasu 0.10 6.16 1.62

R Sadashivayya S/o 207 G Hosahalli 4/1A Rudrayya

208 G Hosahalli 4/1A H D Verappaji Urs

P Thothappajji aras S/o 209 G Hosahalli 4/1B Doddakannappajji aras

S Chendrashekarayya S/o 210 G Hosahalli 4/2P Siddananjappa

211 G Hosahalli 2/P1,2/P2 Gomala 0.15 1.34 11.19

Huccharangayya S/o 212 G Hosahalli 1/1 0.02 4.36 0.46 Getirangayya

Gangamma W/o 213 G Hosahalli 1/1 Rangaswamy

Swayamprabha W/o 214 G Hosahalli 1/2A Honnappa

Sarojamma W/o H C 215 G Hosahalli 1/2A Chandrashekar

216 G Hosahalli 34/1D2 Hemavathi Nale 0.01 0.10 10.00

M Basavyaa S/o late 217 G Hosahalli 36/5 0.07 0.08 87.50 Malayya

Ramakrishnaiah S/o 218 G. Doddari 89/2 0.06 0.14 42.86 Dasegowda

118

Hucchamma S/o Kunnayya 219 G. Doddari 90/3 0.25 6.04 4.14 U. Dasappa

Hucchanna S/o Late 220 G. Doddari 90/4 Thimmaiah

221 G. Doddari 90/1A Chikkegowda S/o Rayappa 222 G. Doddari 50/5,90/1B Rangamma W/o Thimmaiah 0.02 2.08 0.96

223 G. Doddari 89/1,51/1,51/5 Dasegowda S/o Dasegowda 0.06 2.18 2.75

224 G. Doddari 51/8,51/2 Sannaboraiah S/o Kempaiah 0.29 0.12 241.67 225 G. Doddari 38 Gomala 0.17 29.29 0.58

Thimmegowda S/o 226 G. Doddari 37/6,37/p5 0.15 4.24 3.54 Thimmegowda

227 G. Doddari 32/2 Kariyanna S/o Hattaiah 1.38 3.10 44.52 228 G. Doddari 32/1,32/3 Hattaiah S/o Narasegowda

Shivakumarayya S/o 229 Gubbi 129D Puttarangappa

Rangaswamy S/o 230 Gubbi 129C Muddurangayya

231 Gubbi 129B Srinivasa S/o Puttarangappa 232 Gubbi 129 J T Ganganna S/o Thimayya

Narasamma W/o 233 Gubbi 129 0.05 0.24 20.83 Dodarangappa

234 Gubbi 357/2 N A Karabu 235 Gubbi 357/1 B K Abdhulla jabbar 0.01 0.04 25.00

Chikkanarashayya S/o 236 Gubbi 91 0.01 3.08 0.32 Narasiyappa

Kumbinarashayya S/o 237 Gubbi 91 Chikkanarashayya

Doddanarashayya S/o 238 Gubbi 91 Naraseyappa

239 Gubbi 95 Shappi ahamed 0.01 3.22 0.31 240 Gubbi 95 Kharabu

Abdhull sathare S/o 241 Gubbi 95 Abdulljabbar

Shree chennakeshava 242 Gubbi 96/1 0.01 0.32 3.13 swamy temple

Chennbasaveshwaraswamy 243 Gubbi 96/1 temple

244 Gubbi 96/2 Affijayana

Shree Gubbiyappanavara 245 Gubbi 97,103,101,124,102' 1.10 11.14 9.87 Hoo Thota 119

G C Raju S/o 246 Gubbi 145 0.09 0.26 34.62 Chikkanarashayya

247 Gubbi Amanakere 395/1 Junjaaya S/o Chennayya 0.01 0.16 6.25

248 Hindisakere 159/2B Govt road

Lakshmamma W/o 249 Hindisakere 159/2A Thimmayya

250 Hindisakere 159/2A Kadara mahadina 0.02 2.29 0.87

Rangayya S/o K 251 Hindisakere 139/3A allanathimayya

252 Hindisakere 139/3A Govindayya S/o Thimayya

B RamegowdaS/o 253 Hindisakere 139/2A Boregowda

C G Krishnamurthy S/o 254 Hindisakere 139/3A Venkatadasayya

255 Hindisakere 139/1B,2B,3B Road karabu 0.05 3.09 1.62

C M Huchayya S/o 256 Hindisakere 130/1C Mallekattegowda

257 Hindisakere 130/3B Govt road 258 Hindisakere 130/1A2 Govt road 259 Hindisakere 130 Rajanna S/o Buddegowda

Doddaramayya S/o 260 Hindisakere 130/2 Chikkaerayya

261 Hindisakere 130/2 Rajanna S/o Buddegowda 262 Hindisakere 130/3 Lakanna S/o Kalasegowda 0.22 4.04 5.45

H D Mariyappa S/o 263 Hindisakere 141/1B Duddalagowda

H D Mariyappa S/o 264 Hindisakere 141/2B Duddalagowda

Doddegowda S/o 265 Hindisakere 141/2 0.03 3.38 0.89 Doddelegowda

H S Manjunath 266 Hindisakere 142/5B S/oShivaramayya

Mariyallamma W/o 267 Hindisakere 142/5 Chikkayallegowda

Mariyallaiah S/o 268 Hindisakere 142/4 Chikkayallegowda

269 Hindisakere 142/3 Yallayya S/o Chekyallayya

H C Manjunatha S\o 270 Hindisakere 142/2 Shivaramayya

120

Chikkayallayya S/o 271 Hindisakere 142/3 Mariyanna

272 Hindisakere 142/1,143/3 Sitaramayya S/oRamayya 0.00 5.29 0.00

Mariyallaiah W/o 273 Hindisakere 143/2 Chikkayallegowda

H D Nagraju S/o 274 Hindisakere 143 Doddayallegowda

275 Hindisakere 143/4 Thimayya S/o Kariyanna 276 Hindisakere 143/2 Yallayya S/o Chikkayallayya 0.07 2.11 3.32 277 Hindisakere 144 H Y Krishnappa S/o Yallayya

H D Yallappa S/o 278 Hindisakere 144 0.05 4.26 1.17 Duddalayappa

279 Hindisakere 145 Badagi inam 0.04 3.34 1.20

H D Yallappa S/o 280 Hindisakere 146/3B Duddalayappa

Mariyappa S/o 281 Hindisakere 146/3B Chikkayallayya

Parashuramayya S/o 282 Hindisakere 146/3B Pathayya

H K Govindaraju S/o 283 Hindisakere 146/5 Kempegowda

H K Venkatachallayya S/o 284 Hindisakere 146/5 Kempegowda

Bagyamma W/o H Y 285 Hindisakere 146/4 Ramakrishnayya

286 Hindisakere 146/4 Rajanna S/O Doddayya 287 Hindisakere 146/4 H Y Rajanna S/o Yarayya

288 Hindisakere 146/4 H Y Govindaraju S/o Yarayya

289 Hindisakere 146/2 H P Nagaraja S/o Puttayya 290 Hindisakere 146/2 Thimayya S/o Kempayya 0.05 1.25 4.00 291 Hindisakere 38126 Karabu

Hucchanna S/o 292 Hindisakere 38/1 Chikkakempayya

Shivashankarayya S/o 293 Hindisakere 38/1 Shivaramayya

294 Hindisakere 38/1 Eranna S/o Kadappa 295 Hindisakere 39/1 Veranna S/o Chennaverappa Rudrappa S/o 296 Hindisakere 38/1 Chennaverappa 297 Hindisakere 38/1 Veranna 298 Hindisakere 38/1 Prakasha S/o Ganganna 0.03 3.15 0.95 121

H S Manjunath 299 Hindisakere 39/4C S/oShivaramayya

Kemparangayya S/o 300 Hindisakere 39/2C Rangayya

H C Manjunatha S\o 301 Hindisakere 39/4A,39/3C Shivaramayya

302 Hindisakere 39/1C Kumarashetty S/o Byattappa

H S Manjunath 303 Hindisakere 39/1C S/oShivaramayya

304 Hindisakere 39 Karabu 305 Hindisakere 39/2A Mayanmma W/o Lingachar

H B Narayana S/o Late 306 Hindisakere 39/3A Bytarangappa

307 Hindisakere 39/1A Kumarashetty S/o Byattappa 0.06 2.32 2.59

N Chikkarangappa S/o 308 Hindisakere 40/3,40/4 Chikkaranganna

309 Hindisakere 40/2 Karabu H G Srinivasa S/o 310 Hindisakere 40/1 Gereyappa H Rangappa S/o 311 Hindisakere 40/1 0.13 8.34 1.56 Venkattappa 312 Hindisakere 36 Kere 0.05 34.32 0.15 313 Hindisakere 235 Thammaiah U. Thimmaiah 0.01 0.14 7.14 314 Hindisakere 45 School 0.03 1.02 2.94 315 Hindisakere 126/1A2 Government Road 0.15 1.02 14.71

Ramakrishnaiah S/o 316 Hindisakere 126/1B1,126/1A1 Lakshaiah

317 Hindisakere 126/1B2 N Z K Kharab Road

Chakkalamma W/o K N 318 Hindisakere 127 0.18 5.14 3.50 Narasimhaiah

Buddegowda S/o 319 Hindisakere 127/5 Chatepathaiah

320 Hindisakere 127/3 Rajaiah S/o Hucchaiah

Jagadamba S/o 321 Hindisakere 127/4 Venkatalakshmma

Doddanarasamma S/o 322 Hindisakere 130/1B 0.22 3.38 6.51 Padiyappa

Gangamma W/o 323 Hindisakere 130/1B Puttadoddaiah

Kempanarasaiah S/o 324 Hindisakere 130/1B Doddanarasaiah

D S Ravishankar S/o 325 Hindisakere 130/1B Shivappa

122

326 Hindisakere 131 Thimmakka W/o Singashetty 0.02 27.36 0.07

D S Ravishankar - B N 327 Hindisakere 131 Shivappa

Bettaiah B N Cheluvaiah U. 328 Hindisakere 131 Singashetty

Narasimhamurthy S/o 329 Hindisakere 131 Cheluvaiah

330 Hindisakere 138/1B,2B,3B,4B N A K Kharab Road 0.04 2.10 1.90

331 Hindisakere 138/4A Mullakattegowda S/o Eraiah

Lalithamma W/o H D 332 Hindisakere 138/1A,2A Mariyappa

H D Yellappa S/o 333 Hindisakere 138/3A Doddellegowda

Pathanna B W/o 334 Hindisakere Kaval 75/1 0.01 3.26 0.31 Mahamedsab

Sarthajja ahamed S/o Late 335 Hindisakere Kaval 75/3 AhameDHere

336 Hindisakere Kaval 75/4 Noorahmed S/o Ahmed peer

Bangalorappa U 337 Hindisakere Kaval 75/6,75/2 Bangalorappa S/o Late puttayya

Fathimabi W/o Syed hussan 338 Hindisakere Kaval 72/1 0.06 8.18 0.73 sha

339 Hindisakere Kaval 72,72/2 Fada

G Shek majir kalim S/o G H 340 Hindisakere Kaval 73/1 0.00 4.18 0.00 Shek

341 Hindisakere Kaval 73/2 N A Karab road

G Shek majir kalim S/o 342 Hindisakere Kaval 86/1 0.02 4.24 0.47 Shekabdhulla

343 Hindisakere Kaval 86/2 N A K Karab

Nasir ahemad S/o Mahamed 344 Hindisakere Kaval 86/3 yasin

345 Hindisakere Kaval 90/2 Karab road 0.03 3.22 0.93

Mahamad jamil S/o 346 Hindisakere Kaval 90/3 Mahamad kasimsab 123

347 Hindisakere Kaval 109 Govt. 0.05 3.14 1.59

348 Hindisakere Kaval 110 Karab 0.01 17.11 0.06

349 Hindisakere Kaval 63 Belu 0.01 3.01 0.33

Chikka Rangayya S/o 350 Hindisakere Kaval 25/5 0.08 2.18 3.67 Pathiyappa

351 Hindisakere Kaval 25/1 Karibasayya S/o kempanna

352 Hindisakere Kaval 25 Somashekar S/o Kempayya

353 Jaladigere 40/1 Jayamma D/o Hombamma 0.08 10.02 0.80 354 Jaladigere 40/2 Thamanna S/o Dasamesthri

Narassamma W/o 355 Jaladigere 40/6,40/4,126/3A Dasegowda

Kkamallamma W/o T 356 Jaladigere 40/5 Betayya

357 Jaladigere 40/3B Lakkamma W/o Kariyappa

Kempamma U Sakamma 358 Jaladigere 34/2 0.00 1.02 0.00 W/oJavarayya

359 Jaladigere 33/3A Chikamma W/o Geriyappa 0.03 0.33 9.09

360 Jaladigere 33/2B,33/3B Sarkari kere

Thimmarayyappa S/o 361 Jaladigere 31/7 0.02 0.02 100.00 Venkatayya

J V Venkatesh S/o Late 362 Jaladigere 32, 86,91,31 0.16 6.37 2.51 Venkateshagowda

Venkatesha S/o P 363 Jaladigere 32/5 Byategowda

364 Jaladigere 32 Sarkari kere

J R Venkatesh S/o J G 365 Jaladigere 16/3 0.02 3.26 0.61 Ramanna J R Govindaraju S/o 366 Jaladigere 16/3A Ramanna G V Dasappa S/o 367 Jaladigere 13/1A 0.03 7.10 0.42 Venkategowda

Pujari Thimayya S/o Pujari 368 Jaladigere 13/1B Hucchegowda

Sannathimmayya U 369 Jaladigere 90/7Gowdayya S/o Thimayya U 0.19 1.24 15.32 Mayanna

370 Jaladigere 90/8 Govt.

124

371 Jaladigere 90/10,90/12 J V Rajanna S/o Venkatayya 372 Jaladigere 90,86 Thimayya S/o Venkatayya

J V Ramegowda S/o Late 373 Jaladigere 90/11 Venkatayya & Venkategowda

J V Gangaraju S/o 374 Jaladigere 90/15 Venkatayya U Venkatagowda

375 Jaladigere 90/6B,90/5B Alination

Sowbagyamma W/o T 376 Jaladigere 88 0.01 1.34 0.75 Ramesh

G Krishnappa S/o 377 Jaladigere 1,16,9 Chikkagiriyapa

Thimmegowda S/o 378 Jaladigere 1/11,1/12 0.01 3.38 0.30 Buddegowda

J T Venkatesh Kumar S/o 379 Jaladigere 1/17,31/6 Thimmappa

380 Jaladigere 22/1' Gopalaiah S/o Lakkamma 0.00 0.05 0.00

PuttaThimayya S/o Thimayya 381 Jaladigere 5/12' 0.01 0.13 7.69 U Buddakenchayya

382 Jaladigere 5/17' Byattayya S/o Dasappa

Lakshmma W/o B N 383 Jaladigere 41/1, 2 0.09 2.28 3.95 Shankaralingegowda

Kodli Thimmaiah S/o 384 Jaladigere 42/3 0.08 2.32 3.45 Dasegowda

385 Jaladigere 42/4 Giriyappa S/o Byadegowda

J V Venkateshaiah S/o 386 Jaladigere 42/5 Venkataiah U. Muddaiah

387 Jaladigere 42/7B,9B,8B,6B Sarkari Kere

Shivalingaiah S/o 388 Jaladigere 42/9A Chennagiraiah

Nanjamma W/o Late 389 Jaladigere 86/8,42/2,42/6A 0.00 2.20 0.00 Dasegowda

390 Jaladigere 43/3B,6,5B,7,8,2B,4B Sarkari Kere 0.03 4.24 0.71

391 Jaladigere 126/1,2B,3B Sarkari Kere 0.02 2.18 0.92

Gangadaraiah S/o 392 Jaladigere 126/4 Motegowda

K Krishnappa S/o 393 Jaladigere 127/1 0.04 3.18 1.26 Karithimmaiah 125

K Krishnappa S/o 394 Jaladigere 127/4 Karithimmaiah

395 Jaladigere 127/4 K Byataiah S/o Karigowda 396 Jaladigere 127/4 Dasegowda S/o Karigowda

Karithimmaiah S/o 397 Jaladigere 127/4 Karigowda

398 Jaladigere 127/4 K Shivanna S/o Karigowda 399 Jaladigere 127/2A Doddamma S/o Bhiraiah

Mudibyatanagowda S/o 400 Jaladigere 127/5A Byategowda

J D Manjunatha S/o 401 Jaladigere 32/8,127/3A 0.04 1.02 3.92 Doddagiriyappa J S Prakasha S/o 402 Jaladigere 128/1 0.07 6.26 1.12 Srinivasaiah Venkataramaiah S/o 403 Jaladigere 128/1 Puttaswamaiah

B Lalithamma W/o 404 Jaladigere 128/2 Basavaraju

J S Prakasha S/o Late 405 Jaladigere 128/3 Srinivasaiah

406 Jaladigere 91/1 Venkategowda 0.07 0.35 20.00

J N Narendrakumar S/o Late 407 Jaladigere 91/12,10,9,13 K Nagaraju

408 Jaladigere 91/19 Venkataiah

Thimmaiah S/o Sanna 409 Jaladigere 91/20 Venkataiah

410 Jaladigere 86/3 Venkataiah S/o Giriyappa 0.16 1.12 14.29 411 Jaladigere 86/5 J J Giriyappa Rangaswamy S/o 412 Jaladigere 86/5 Dasegowda 413 Jaladigere 86/6 Thimmaiah S/o U. Mayanna 414 Jaladigere 86/7 Muddaiah S/o Thimmaiah

Kodli Thimmaiah S/o 415 Jaladigere 86/9 Dasegowda

416 Jaladigere 86/10 Byataiah S/o Venkataiah

Paddamma W/o 417 Jaladigere 6/1 0.00 0.08 0.00 Thimmegowda

418 Jannenahalli 8/1AP Lakkamma 0.08 1.18 6.78

Ramalinganayka S/o 419 Jannenahalli 9/1,8/2B,8/1B 0.03 7.16 0.42 Nanjamma

420 Jannenahalli 9/2 Lakkanna S/o Lakkanna 421 Jannenahalli 45/-p1 Gomala 1.03 33.07 3.11

126

Sundaramma W/o 422 Jannenahalli 45/-p3 Venkatappa

Chikkegowda S/o 423 Jannenahalli 45/-p7 Lakshmanagowda

424 Jannenahalli 45/p-p7 Thimmegowda S/o Malaiah 425 Jannenahalli 45/p17 Doddaiah S/o Gurulingappa

426 K Harivesandra 13 Gomala 0.14 40.20 0.35

427 K Harivesandra 13A Graveyard

Thirumalegowda S/o 428 K Harivesandra 11 0.06 3.18 1.89 Lakkegowda

Muniyappa S/o D 429 K Harivesandra 10/2 0.05 0.34 14.71 Kempegowda

430 K Harivesandra 9/1 Pathiyappa S/o Kempayya 0.06 1.34 4.48

431 K Harivesandra 9/3 Rangappa S/o Rangappa

P Muniyappa S/o D 432 K Harivesandra 1/1 0.08 0.10 80.00 Kempegowda

Guddhappachar S/o 433 K Harivesandra 1/3 Chennabasavachar

434 K Harivesandra 59 Karab honi 0.08 1.32 6.06

435 K Harivesandra 58/2 Boregowda S/o Kempayya 0.08 2.23 3.59

436 K Harivesandra 58/1A3 Gaganana S/o Chikka gowda

437 K Harivesandra 56/1 Aakkannagowda 0.10 5.32 1.88

438 K Harivesandra 56/2,52/3 Karirangayya S/o guddaya

Govindhappa S/o 439 K Harivesandra 52/3p 0.00 0.80 0.00 Thirumalegowda

Govindagowda S/o 440 K Harivesandra 46/1 0.10 3.04 3.29 Deriramma

Narasegowda S/o 441 K Kallahalli 138/3 0.26 3.36 7.74 Hattegowda U. Buddaiah

Ramakrishnaiah S/o 442 K Kallahalli 138/4 Rangegowda

Thimmegowda S/o 443 K Kallahalli 138/5 Rangegowda 127

Chikkanna U. Sannaiah S/o 444 K Kallahalli 138/7 Chikka Kempaiah

K R Rangaramaiah S/o 445 K Kallahalli 138/8,138/2 Rangaiah

K Siddalingaiah S/o 446 K Kallahalli 137/1A,138/10 0.05 1.20 4.17 Kengaiah

Lakshmanaiah S/o 447 K Kallahalli 136138 0.00 16.30 0.00 Rangegowda

Lakshmanaiah S/o 448 K Kallahalli 136/4 Rangegowda

Hallamma W/o Sanna 449 K Kallahalli 136/4 Puttaiah

450 K Kallahalli 136/3P Krishnegowda S/o Nagaiah 451 K Kallahalli 136/3P Shivanna S/o Narasaiah 452 K Kallahalli 135/1 Rangaiah S/o Thimmanna 0.06 4.32 1.39

Narasimhaiah S/o 453 K Kallahalli 135/2 Kenchegowda

K N Hattegowda S/o 454 K Kallahalli 134/2,136/2 0.03 3.12 0.96 Narasegowda

455 K Kallahalli 133 Talavarike 0.05 5.38 0.93

Ramakrishnaiah S/o 456 K Kallahalli 132A 0.00 0.30 0.00 Narasegowda

457 K Kallahalli 131/5,132 Krishnegowda S/o Nagaiah 0.03 5.06 0.59 458 K Kallahalli 131/2 Ameerbee W/o Abdulla 459 K Kallahalli 131/5,138/6 Shivanna S/o Narasegowda 460 K Kallahalli 131/1A Aritamma W/o Nagalingaiah 461 K Kallahalli 129/2 Ameerbee W/o Raheemsab 0.03 0.16 18.75

Rangegowda S/o 462 K Kallahalli 38/P11 0.20 1.16 17.24 Chikkarangegowda

L K Shivanna S/o 463 K Kallahalli 70/2 0.07 0.10 70.00 Kariyanagowda

464 K Kallahalli 77/1B Govinadarao S/o Narasojirao 0.03 0.03 100.00

Gangaiah S/o Dodda 465 K Kallahalli 84/1,84/1-p1,80/2A 0.02 1.24 1.61 Anjinappa

466 K Kallahalli 81 Jeenath Unnis S/o Amirsab 0.02 0.30 6.67 467 K Kallahalli 81 Gangaiah S/o Anjanappa 468 K Kallahalli 86/1 Ramojirao S/o Narasimharao 0.02 1.22 1.64

Ramachandrarao S/o 469 K Kallahalli 86/4 Balajirao

470 K Kallahalli 85/6 Nagegowda S/o Hattegowda 0.02 0.22 9.09

128

Narasimharao S/o 471 K Kallahalli 86/9,114/11,86/3,86/6,86/7 0.11 2.12 5.19 Govindarao

472 K Kallahalli 86/8 Ramojirao S/o Annojirao 473 K Kallahalli 86/10 Ranibai W/o Late Govindarao

Cheluvaiah S/o 474 K Kallahalli 85/1A 0.00 1.02 0.00 Mudlagiriyappa

Mohammadpeer S/o 475 K Kallahalli 114/4 0.11 5.08 2.17 Khadarmohammadeen

476 K Kallahalli 114/4 Nagegowda S/o Hattegowda

Chikkamma W/o 477 K Kallahalli 114/2,7,8 Thirumalagiraiah

Nagaiah U. Gundaiah S/o 478 K Kallahalli 114/9 Hattegowda

479 K Kallahalli 114/9 Lakkamma

480 K Kallahalli 117/1,117/4,129/1 Karisiddaiah S/o Siddaiah 0.10 31.00 0.32

481 K Kallahalli 117/3,117/2 Basavaiah S/o Siddaiah 482 Kallur 5 Kere angala 1.14 452.13 0.25 483 Kallur 161/3 Gangamma W/o Betayya 484 Kallur 161/4 Maribasavayya S/o Nanjappa 0.03 0.36 8.33

Parvathamma W/o 485 Kallur 152/1,161/5 0.25 0.18 138.89 Shivalingayya

486 Kallur 223 Sarakari amruthmahal kaval 1.01 0.38 265.79 487 Kallur 219 Gomalla 0.28 0.03 933.33 488 Kallur 80/1 Muddarangaiah 0.09 0.24 37.50

K G Nagarajaiah S/o 489 Kallur 76 1.09 0.28 389.29 Gangaiah Mestri

490 Kallur 74/1 B Shankaraiah S/o Kalasaiah 0.03 0.20 15.00

K T Chikkavenkatappa S/o 491 Kallur 68/1,68/2,57/1 0.20 1.38 14.49 Thimmarayappa

Govindaiah S/o 492 Kallur 63 0.10 0.38 26.32 Karithimmaiah

Ranganayakamma W/o K V 493 Kallur 57/2 1.04 0.28 371.43 Ramakrishnaiah

494 Kallur 54/2 Bhimaiah S/o Sanjeevaiah 0.39 1.30 30.00 495 Kallur 54/3,4,5A Gangamma W/o Anjinappa 496 Kallur 54/1A Bhima

Sharadamma D/o 497 Kallur 54/5B Sampigamma

Mohammad Yusuf S/o 498 Kallur 142/6,2,5A2,3B,3A,1 0.17 3.20 5.31 Alyesallam 129

Puttaraju S/o Late K S 499 Kallur 142/9 Chowdayya

Puttaraju S/o Late K S 500 Kallur 142/9 Chowdayya

501 Kallur 142/7A Ramesha 502 Kallur 143/2 Lenkegowda S/o Hanumaiah 0.14 4.16 3.37 503 Kallur 148/1 Mayanna S/o Sannayya 0.12 1.12 10.71 504 Kallur 148/2 Babyjan W/o Mohammadbab

Siddalingaiah S/o Shetty 505 Kallur 222 0.17 0.14 121.43 (Kengana)

K C Puttamma W/o K S 506 Kallur 218/2 0.10 0.05 200.00 Nagaraju

507 Kattigenahalli 57 Govt land 0.28 24.15 1.16 508 Kattigenahalli 57/2 Govt

Deviramma W/o Late 509 Kattigenahalli 57 Nanjappa

510 Kattigenahalli 57/1C Ganganna S/o Basayya 511 Kattigenahalli 57/P Govt land

Parvathamma W/o Late 512 Kattigenahalli 167/P1 0.10 1.20 8.33 Basanna

Gangabasappa S/o late 513 Kattigenahalli 168 0.08 1.26 6.35 Lingappa

514 Kattigenahalli 184 Mahesh S/o Borayya 0.04 4.18 0.96 515 Kattigenahalli 184A Siddalingappa S/o Lingappa 516 Kattigenahalli 184 H Manjhayya S/o Lingappa 517 Kattigenahalli 64 Gomala 0.12 34.03 0.35 518 Kattigenahalli 64/1 Shivakumar S/o Shivanna

Chennabashayya S/o 519 Kattigenahalli 64/1P2 Lingappa

520 Kattigenahalli 64/2P Jagadisha S/o Nanjundhayya

T L Shivaganghayya S/o Late 521 Kattigenahalli 64/3P Lingappa

Somashekar S/o 522 Kattigenahalli 64/5P siddhalinghappa

523 Kattigenahalli 67 Kere Angala 0.19 23.13 0.82 524 Kattigenahalli 68 Gomala 0.19 23.13 0.82

Guru sangappa S/o 525 Kattigenahalli 68 Chennabashayya

526 Kattigenahalli 68/P4 T S Shivanna S/o Shivanna 527 Kattigenahalli 69 Gomala 0.08 120.17 0.07

Chikkaranghayya S/o 528 Kattigenahalli 69/p2 Huccharanghayya

130

529 Kattigenahalli 69/P25 Huchayya S/o Hattighayya

530 Kenchaveranahalli 24 Boramma W/o Siddegowda

Jayalakshmamma W/o 531 Kenchaveranahalli 24 0.11 2.02 5.45 Nanjegowda

Mahadevayya S/o 532 Kenchaveranahalli 22/P Basavayya

533 Kenchaveranahalli 22/P Shreekantayya S/o Ugrayya

534 Kenchaveranahalli 22/P1 Gomala

Ramayya S/o 535 Kenchaveranahalli 22/2 Sannarangayya

536 Kenchaveranahalli 22/1 Ningayya S/o Kempayya 0.16 6.24 2.56

Siddabasamma W/o 537 Kenchaveranahalli 68/3 0.00 1.04 0.00 Siddalingayya

Ramachandrayya S/o 538 Kenchaveranahalli 62,63 0.03 4.02 0.75 Chennagowda

Mahadevayya S/o 539 Kenchaveranahalli 65 0.00 1.34 0.00 Basavayya

540 Kenchaveranahalli 66 Gowramma W/o Kempamma

541 Kenchaveranahalli 66 Ramanna S/o Nanjappa 0.05 1.34 3.73

Kempparangayya S/o 542 Kenchaveranahalli 67/1 0.02 0.30 6.67 Thirumallayya

Therumalegowda S/o 543 Kenchaveranahalli 21 0.04 1.38 2.90 Akkannagowda

Thimmegowda S/o 544 Kodipalya 5/1,3/3,2/5 0.04 8.32 0.48 Thimmegowda

Rajamma W/o Late 545 Kodipalya 5/2 Hattegowda

Kempamma W/o Late 546 Kodipalya 2/4 0.02 3.38 0.59 Tirumalegowda

547 Kodipalya 2/6,2/2 Sakamma W/o Thimmaiah

Sanna Thimmaiah S/o 548 Kodipalya 2/5 Banaiah

Thimmegowda S/o Late 549 Kodipalya 2/5 Thimmegowda

Chikkanna S/o Sanna 550 Kodipalya 2/5 Thimmaiah 131

M Rajanna S/o 551 Kodipalya 2/8 Muddurangaiah

Ramanna S/o Late 552 Kodipalya 2/9 Venkatappa

553 Kodipalya 17 Gomala 0.34 45.04 0.75

Konegowda U. Rajanna S/o 554 Kodipalya 17/P1,2/3 Konegowda

Puttaiahshetty S/o 555 Kodipalya 17/P Lakkanashetty

Thimmappa S/o Late 556 Kodipalya 17/P Thimmaiah

Narayanashetty S/o 557 Kodipalya 17/p2p Lakshmaiahshetty

Shivalingamma W/o 558 Kodipalya 17/p-p3 Hucchaiah

559 Kodipalya 17/p-p5 Halappa S/o Late Devaraiah

Chikkanna S/o Sanna 560 Kodipalya 17/p-p6 Thimmaiah

561 Kodipalya 18 Kempamma W/o Ganganna 0.10 5.20 1.92 562 Kodipalya 18/p-p1 Deviraiah S/o Kariyanna 563 Kunala 167187 A Gunisab 0.00 5.02 0.00 564 Kunala 167/2 Kharabu 565 Kunala 178/2 Kharabu 0.00 0.20 0.00 566 Kunala 177/1B Kharabu road 0.00 9.38 0.00 567 Kunala 177186187 Don’t know 568 Kunala 186 Mahammad Baba sab 0.00 3.16 0.00 569 Kunala 187/1B Kharabu road 0.00 1.38 0.00 570 Kunala 187/1B Kharabu road Sufiyabi W/o Late 571 Kunala 187/1A2 Rahimkhan 572 Kunala 187/3B Kharabu 573 Kunala 187/3 Modin S/o Abdul Aziz 574 Kunala 187/3 KSD K

Syed sakevara W/o 575 Kunala 187/3 Syedbasha

Abdul salam S/o Late Abdhull 576 Kunala 187/3 kasim

Mahammed mahid S/o 577 Kunala 187/2A1 Hanifsab

578 Kunala 187/2A1 Makaburabi S/o Khadar

Narasayya S/o 579 Lenkanahalli 17 0.27 2.20 12.27 Doddanarasayya

132

580 Lenkanahalli 9/1 Narasimaiah S/o Kadaraiah 0.00 0.18 0.00

Subadrabai S/o 581 Lenkanahalli 16/7 0.10 1.10 9.09 Ramachandrarao

582 Lenkanahalli 16/10 Naganna S/o Nagagowda 583 Lenkanahalli 18 Sarkari Gundu Thopu 0.07 1.00 7.00 Hattegowda S/o 584 Lenkanahalli 20 0.10 2.16 4.63 Doddegowda 585 Lenkanahalli 20 L K Doddagowda 586 Lenkanahalli 23/5,16/1 Venkatarao S/o Mukundarao 0.23 3.12 7.37 587 Lenkanahalli 23/6 Rajappa S/o Rajobakodam 588 Lenkanahalli 24 Nanjudaaiah S/o Hanumaiah 0.01 1.18 0.85

589 Lingammanahalli 67/1 Rangaswamayya 0.05 0.14 35.71

590 Lingammanahalli 76 Munaffa

591 Lingammanahalli 76 Graveyard

592 Lingammanahalli 76B Karimsab S/o Balandarsab

593 Lingammanahalli 76 Gomala 0.01 2.04 0.49

594 Lingammanahalli 78,76 Abdulla karimsab 0.00 1.00 0.00

595 Lingammanahalli 79/1C Abdulsab

596 Lingammanahalli 79 Babajain S/o Karimsab

597 Lingammanahalli 79/2B A L N 0.02 2.23 0.90

598 Lingammanahalli 78,6,4,67,76,74,79,79 Karabu 0.02 2.34 0.85

599 Lingammanahalli 7/3 Chikkamma W/o Puttayya

Shekh Hydar S/o 600 Lingammanahalli 7/2C Noorahamad

601 Lingammanahalli 7/1B,7/2B Road

G R Kumar S/o G M 602 Lingammanahalli 7/1A 0.12 6.02 1.99 Rangappa

603 Lingammanahalli 8 Gomala 0.06 16.15 0.37

Shree Kalagattammana 604 Lingammanahalli 10 0.01 4.30 0.23 Temple 133

Govt higher primary school 605 Lingammanahalli 11 ,nagasandra

606 Lingammanahalli 11 K P T C L Gubbi

607 Lingammanahalli 11 Gomala 0.01 15.02 0.07

608 Narigehalli 18/2 Nagaraja S/o Hattegowda 0.37 1.30 28.46 609 Narigehalli 21,18 Gomala 0.16 12.34 1.30

Lakkanna U.. Maiyanna S/o 610 Narigehalli 21/3 Block Lakkanna

611 Narigehalli 22 Gomala 0.20 33.02 0.61 612 Narigehalli 22/1 Jayamma W/o Nanjundaiah 613 Narigehalli 22/2-p2 Nanjegowda S/o Puttegowda 614 Narigehalli 20 Gomala 0.08 3.08 2.60 615 Narigehalli 33 Forest Department 0.14 33.16 0.42 616 Narigehalli 34 Kharabhu 0.03 8.20 0.37

Narasegowda S/o 617 Narigehalli 35/1 0.20 13.36 1.50 Nagegowda

Narayanappa S/o 618 Narigehalli 35/1 Hattegowda

619 Narigehalli 35/1 Gopalaiah Shivanna S/o N 620 Narigehalli 35/1 Sannanagaiah Krishnappa S/o 621 Narigehalli 35/1 Sannanagaiah 622 Narigehalli 35/1 Naganna

Nanjegowda S/o 623 Narigehalli 35/2,3,4 Kurilakkappa

Hombaiah S/o 624 Narigehalli 36/1 0.14 1.28 10.94 SannaHattanaiah

625 Narigehalli 36/4,5,7 Prakasha S/o Lakkanna

Hanumanthegowda S/o 626 Padugudi 64,79 0.08 6.04 1.32 Kempegowda

Krishnegowda S/o 627 Padugudi 64,79 Kempegowda

Lakkamma W/o Late 628 Padugudi 75/8 Yallakkigowda

H Krishnagowda S/o 629 Padugudi 75/6 Hanumanthayya

Keshavagowda 630 Padugudi 75/3 S/oYallakkigowda

Narayanna S/o 631 Padugudi 75/3,75/4 Yallakkigowda

134

632 Padugudi 75/3,75/5 Nanjegowda S/o Andanayya 633 Padugudi 75/2 B Borayya S/o Boregowda 634 Padugudi 75/1,5,7 Nanjegowda S/o Andanaiah 0.04 4.16 0.96 Bettegowda S/o 635 Padugudi 70/1A 0.00 3.12 0.00 Narasimappa 636 Padugudi 70/1A Ramesha S/o Narasimappa

B Hanumanthegowda S/o 637 Padugudi 76/5 0.17 1.08 15.74 Beluregowda

Mayamma W/o B 638 Padugudi 76/5 Ramegowda

639 Padugudi 28 Shepebeg S/o Late Vajidbeg 0.00 3.18 0.00

C Beluregowda S/o 640 Padugudi 70/2A, 28/1 0.07 10.34 0.68 Chennakeshavagowda

C Yallakkigowda S/o 641 Padugudi 70/2A,28/1 Chennakeshavagowda

C L Gangadharaiah S/o 642 Padugudi 31/1 0.07 0.30 23.33 Lingaiah

643 Padugudi 29/2 Narasamma W/o Andanaiah 0.18 0.34 52.94

C L Gangadharaiah S/o 644 Padugudi 29/2 Lingaiah

645 Padugudi 29/2 For C S Pura VSSN

C Beluregowda S/o 646 Padugudi 3 0.80 1.00 80.00 Chennakeshavagowda

C Yalakkigowda S/o 647 Padugudi 3 Chennakeshavagowda

648 Padugudi 76 Sarkari Gomala 0.17 5.26 3.23 649 Padugudi 76/6 Keshavaiah S/o Gundaiah

Yalakkigowda S/o 650 Padugudi 84 0.02 0.32 6.25 Yalakkigowda

651 Padugudi 63 Sarkari Gomala 0.30 23.07 1.30 652 Padugudi 61 Gomala 0.01 12.18 0.08 653 Padugudi 62 Sarkari Gundu Thopu 0.06 3.12 1.92 654 Sheshapur 33 Kapanigowda S/o Dhulaiah 0.10 0.20 50.00

Kapanigowda S/o Kapanaiah 655 Sheshapur 3 0.06 5.10 1.18 U. Dhulaiah

Chennaiah U. Haravaiah S/o 656 Sheshapur 3 Chennaiah U. Kariyappa

Eranna S/o Chennaiah U. 657 Sheshapur 3 Kariyappa

658 Sheshapur 2/1 Erannagowda S/o Nanjayya 0.02 1.10 1.82 659 Sheshapur 2/2 Gangayya S/o Lingegowda 135

Chennagowdru S/o 660 Sheshapur 1/1 0.14 9.06 1.55 Chennaiah

Kempathannaiah S/o 661 Sheshapur 1/2 Sannananjaiah

662 Sheshapur 1/3 Shivanna S/o Chennaiah

D.C Naveenkumar S/o D H 663 Sheshapur 1/4 Chennagowda

M Vijayalakshimi W/o 664 Sheshapur 19/5 0.26 9.26 2.81 Mahadeva

Lingaiah Shetty S/o Bettaiah 665 Sheshapur 19/6 Shetty

D C Venkatesha S/o D L 666 Sheshapur 19/7 Chennegowda D R Gangaiah S/o 667 Sheshapur 19/4,40/1 Ramanaika Chennaiah S/o Chennagaiah 668 Sheshapur 40/2 0.17 1.20 14.17 U. Haravaiah

Savitramma W/o Late 669 Sheshapur 40/7 Madhurappa

D V Lakkanna S/o Late 670 Sheshapura 38 0.04 4.36 0.92 Erannagowda

671 Shettigondanahalli 94/1 Narasayya S/o Sanjeevaiah 0.17 12.38 1.37

672 Shettigondanahalli 94/P1 Narasigowda S/o Nagaiah

Nagaish S/o Chikka 673 Shettigondanahalli 94/P7 Hattegowda

Kempegowda S/o 674 Shettigondanahalli 63/2 0.24 3.30 7.27 Narasimhegowda

675 Shettigondanahalli 63/4 Narasimhaiah S/o Nagaiah

676 Shettigondanahalli 63/6 Kempaiah S/o Thimmaiah

677 Shettigondanahalli 63/9 Boramma D/o Lakkamma

678 Shettigondanahalli 63/7 M Govindaiah S/o Marigowda

Sanna Thimmaiah S/o 679 Shettigondanahalli 63/8B Kalegowda

680 Shettigondanahalli 62 Hatte S/o Chikkanna 0.13 4.14 3.14

681 Shettigondanahalli 61/1,63/8B Kempaiah S/o Kalegowda 0.05 2.00 2.50

136

682 Surigenahalli 67/1 Nalluramma W/o Modlayya 0.00 10.30 0.00

S L Narasimhayya K 683 Surigenahalli 32 Lakhanna U 0.20 10.12 1.98 Lakshminarasimhayya

K Lakshmana U 684 Surigenahalli 32,35 lakshminarasayya S/o Kadarayya

685 Surigenahalli 35/1 Dodayya S/o Nallurayya 0.00 10.00 0.00

686 Surigenahalli Kaval 28/3 Lingappa S/o Ramanna 0.05 0.18 27.78

Modalagirigowda S/o 687 Surigenahalli Kaval 34/4 Govindappa

688 Surigenahalli Kaval 34/3 Hanumayapujari 0.05 2.40 2.08

689 Surigenahalli Kaval 35 Era S/o Erajja 0.05 8.18 0.61

690 Surigenahalli Kaval 35,36,28,47 Road

K T Rathnamma W/oLate 691 Surigenahalli Kaval 35,36 Lakkorappa

Lakshminarasegowda N L U 692 Surigenahalli Kaval 36,47,44,5 S/o Late 0.04 8.32 0.48 Lakshminarasegowda

A Mahamad ukbala S/o 693 Surigenahalli Kaval 44/4 0.00 2.28 0.00 Sayed ahamed

694 Surigenahalli Kaval 45,44,34,51,46 Road 0.05 9.12 0.55

Jayaramayya S/o Late 695 Surigenahalli Kaval 45/4,45/5 Dasegowda U nanjappa

Krishanappa S/o Dasegowda 696 Surigenahalli Kaval 45 U nanjappa

697 Surigenahalli Kaval 44,45 Govt Fada

Krishnappa S/o Late 698 Surigenahalli Kaval 46/5 Dasegowda U nanjappa

Dasegowda S/o Late 699 Surigenahalli Kaval 46/3 Dasegowda U Nanjappa

Dasegowda S/o Late 700 Surigenahalli Kaval 46/1 0.01 3.11 0.32 Dasegowda U Nanjappa

Jylabuddin S/o Late Abdulla 701 Surigenahalli Kaval 47/5 kalim sab 137

702 Surigenahalli Kaval 47/1 Narasegowda S/o Ganganna 0.01 2.14 0.47

703 Surigenahalli Kaval 51/1A Balojirao S/o Bondojirao 0.10 5.00 2.00

704 Surigenahalli Kaval 54/P Gomala

N M Puttaraju S/o 705 Surigenahalli Kaval 54/1 0.02 4.18 0.48 Maylarrappa

706 Surigenahalli Kaval 56 Gururangayya S/o Thippayya

707 Surigenahalli Kaval 56 Gangappa S/o Yallayya 0.01 5.20 0.19

Krishnamurthy S/o 708 Surigenahalli Kaval 58 Rangaswamayya

Nagarajayya S/o 709 Surigenahalli Kaval 58 Rangaswamayya

Muddurangayya S/o 710 Surigenahalli Kaval 58 Rangaswamayya

Chikkarangayya S/o 711 Surigenahalli Kaval 58 Rangayya

712 Surigenahalli Kaval 58 Rangaswamayya 0.11 2.14 5.14

Ranganathayya S/o 713 Surigenahalli Kaval 58 Rangaswamayya

714 Surigenahalli Kaval 67/1 Narasimhayya S/o Kodappa 0.02 1.08 1.85

715 Surigenahalli Kaval 61 Govt Karabu 0.16 24.00 0.67

Deputy Commissior officer 716 Surigenahalli Kaval 59/2 0.07 6.24 1.12 Tumkur

717 Surigenahalli Kaval 59/3 S Raju S/o Shrinivasa

718 Surigenahalli Kaval 59/1p2 Yashodabai S/o Rajarav

719 Surigenahalli Kaval 59/1P3 M Rajaram S/o Murojirav

720 Surigenahalli Kaval 1 Grama Niveshana 0.05 2.04 2.45

721 Surigenahalli Kaval 225/1A Mahadoji S/o Munnoji 0.01 1.16 0.86

D GangadharaS/o 722 Surigenahalli Kaval 53/1 0.06 1.36 4.41 Doddathimayya

138

723 Surigenahalli Kaval 53/3 Limboji S/o Venkoji

724 Surigenahalli Kaval 52/2 Yashodabai W/o M Rajurav 0.01 5.24 0.19

S Herebhai W/o M S 725 Surigenahalli Kaval 52/1A Krishnamurthy

726 Surigenahalli Kaval 13 Ganganna S/o Doddhayya 0.03 6.20 0.48

Badhramma W/o Late 727 Surigenahalli Kaval 14/1 0.01 2.14 0.47 Lingappa

728 Surigenahalli Kaval 27/B Nanjundappa S/o Mudlayya 0.03 0.02 150.00

Affected Land/Area Details for 57B Area in Acre-Gunta

% of Sl. Affected Total Village Survey No. OwnerName Affected No. Area Area Area

1 Amruthuru 423/2 Gooligowda S/o Gooligowda 0.11 0.12 91.67 2 Amruthuru 427/9,374/3 Police station 0.01 0.34 2.94

3 Amruthuru 427/1 Jayalakshvavva W/o Eshwarachari

4 Amruthuru 427/1 Gangachari 5 Amruthuru 427 Puttamma W/o Papachari 6 Amruthuru 429,13 Graviyard 0.05 3.08 1.62 7 Amruthuru 400 Gramatana 0.00 2.30 0.00 8 Amruthuru 99376 Govt road 0.04 0.14 28.57 9 Amruthuru 375 Masid 0.03 0.12 25.00 10 Amruthuru 374/1 Nalini W/o Gangegowda 0.04 0.12 33.33

Chandrakanthamma W/o 11 Amruthuru 373/12 0.06 3.14 1.91 Chikkanna shetty

K Narayanashetty S/o 12 Amruthuru 373,374,113,375' Kalyanagowda

13 Amruthuru 295 K Venkatesh S/o Kalegowda 0.01 3.22 0.31

Kalaboregowda S/o Chikka 14 Amruthuru 291,292,293,294' 0.09 4.24 2.12 boregowda

Krishnappa S/o Chikkagoolayya, 15 Amruthuru 291 Nagaraja S/o Chikkagali

A R Venkateshayya S/o Late 16 Amruthuru 289 0.02 0.22 9.09 Ramanna gowda 139

Chikkathamayya S/o 17 Amruthuru 286 0.01 0.14 7.14 Hucchathimmegowda

18 Amruthuru 281/1 Rajanna S/o Lingayya 0.04 1.04 3.85 19 Amruthuru 281/1 Sudha W/o Murthy 20 Amruthuru 286/3 Sudha W/o A S Murthy 0.01 0.14 7.14

21 Amruthuru 184 N N Boregowda S/o Late Ningayya 0.01 0.32 3.13

22 Amruthuru 188/1 N Chikkanna S/o Nanjundha shetty 0.05 1.16 4.31

C N Subbalaxmi W/o Late A R 23 Amruthuru 213/2 0.01 0.26 3.85 Ramamurthy

24 Hosakere 100107 Chandhrashekara S/o Late Byrappa 0.02 1.25 1.60

25 Hosakere 100/5 Kalegowda S/o Chikkathimayya

26 Hosakere 100/6 H R Ramesh S/o H M Rudrappa

27 Hosakere 99106 Boregowda S/o Nanjegowda 0.06 1.16 5.17 28 Hosakere 53106 Lingayya S/o Kalegowda 1.10 0.22

29 Hosakere 53/16 H R Ramesh S/o H M Rudrappa 0.14 0.08

30 Hosakere 52107 Sreekantagowda S/o Doddborayya 0.33 0.38 86.84

31 Hosakere 52/3 Nanjundhayya S/o Lingayya 0.11 1.11 9.91

32 Hosakere 52/5 Gangaboramma W/o Late Ningayya

33 Hosakere 52/6 H P Gangayya S/o Putayya

34 Hosakere 52/9 Kariyamma W/o Late Narasagowda

35 Hosakere 52/10 Narashimayya S/o Late Chikayya

36 Hosakere 52,53 H B Boregowda S/o Borayya

H C Byrappa S/o Late 37 Hosakere 52107 Chikkaboregowda

38 Hosakere 52/20 H K Chikkaborayya S/o Kenghayya

39 Hosakere 52/11 H P Gangapathi S/o Borayya

40 Hosakere 51/2 Siddayya U Mariyappa Siddayya 0.03 0.20 15.00

H N Boregowda S/o Ningayya U 41 Hosakere 106,51 0.31 2.34 13.25 Byrappa

42 Hosakere 96100106 Nanjundhayya S/o Rangayya 0.33 4.31 7.66

140

43 Hosakere 98/1 H G Puttegowda S/o Gaviyappa 0.02 0.24 8.33

44 Hosakere 98/2 Linghayya S/o Puttegowda

45 Hosakere 106 Nanjundhayya S/o Nanjegowda 0.28 2.12 13.21

H C Vasudevayya S/o 46 Hosakere 106/4 Chikkaboregowda

47 Hosakere 106/8 H C Shankar S/o Chikkayya

H N Sree kantayya S/o Late 48 Hosakere 107106 0.29 3.20 9.06 nanjayya

49 Hosakere 107/7A H J Bimanna S/o Late Javaregowda

50 Hosakere 107/8 Chikkaborayya Byrappa

51 Hosakere 107/10 N Kusuma W/o B K Ramanna

Chandrayya S/o Late 52 Hosakere 107/5,98/2 Chikkarangayya

53 Hosakere 107/2BA Hucchamma W/o Lt Gavigowda

54 Hosakere 107/30 Borayya S/o Boralingayya

Lingegowda S/o Madura 55 Hosakere 106107 boregowda

56 Hosakere 107/13 Shivanna S/o Pathappa

H K Jayalakshmamma W/o H B 57 Hosakere 107/19A Kadayya

58 Hosakere 107/20A Giriyamma W/o Javarayya 59 Hosakere 107/21B Shivanna S/o Byrappa

60 Hosakere 107/21C Hanumegowda S/0 Karigowda

Borayya S/o Javarayya U 61 Hosakere 107 Yallamma

Kempalingegowda S/o 62 Hosakere 107/27A Kariboregowda

Shivamma W/o Shrinivasayya U 63 Hosakere 107/27A Mooshappa

Bangiboregowda S/o 64 Hosakere 107,51 Chikkaboregowda

65 Hosakere 107,51 Boregowda Tantiborayya

66 Hosakere 107/39B Mariyanna S/o DoddaBorayya

67 Hosakere 107/39B H G Byrappa S/o Gangadarayya 141

68 Hosakere 35/1 L Boregowda S/o Lingegowda 0.02 0.36 5.56

69 Benavara 53/1B Kempegowda S/o Nanjegowda 0.06 13.34 0.45

70 Benavara 53/1C Sanabada nanjegowda patela

Savithramma W/o 71 Benavara 61/3 0.00 0.22 0.00 Vishwagnanachar U puttachar

72 Benavara 62/11 Kencha S/o Kenchayya 0.16 0.26 61.54 73 Benavara 62/16C Sidayya S/o Pojayya

B S Gangadarayya S/o Sidayya 74 Benavara 62/17 alias madurayya

75 Benavara 62/19 Fada 76 Benavara 80/2 Borayya S/o Late Siddayya 0.04 0.04 100.00

77 Benavara 80/2 Chikkasiddayya S/o Late Siddayya

78 Benavara 80/2 Rajayya S/o Late Siddayya

Savithramma W/o 79 Benavara 83 0.15 0.10 Vishwagnanachari

80 Benavara 84/1 Chikkasiddayya 0.08 0.15 53.33 81 Benavara 84/1,95/3 Siddayya S/o Pojayya

82 Benavara 85/1 Yalavayya U S/o Hombigowrayya 0.02 5.21 0.38

83 Benavara 85/1 Giriyappa U Urvashigudayya 84 Benavara 85/1 Yalakayya 85 Benavara 85/1 Govindayya 86 Benavara 85/1 Gangayya

87 Benavara 85/1 Gundayya S/o Late chikkagiriyappa

88 Benavara 85/2 Kajjigiriya S/o Chikkagiriya

89 Benavara 86 Kavaramma W/o Late srinivasayya 0.03 1.10 2.73

90 Benavara 97 Borayya 0.03 6.34 0.47 91 Benavara 97 Chikkanna S/o Bettegowda 92 Benavara 99 Honnegowda S/o Bettegowda 0.03 1.22 2.46

93 Amruthuru 110 Goolagowda S/o Kempagooligowda 0.14 0.14 100.00

94 Amruthuru 111/1 Mohan S/o Thapasegowda 0.09 0.26 34.62

Chikkanna shetty U M S/o 95 Amruthuru 111/3 0.00 0.28 0.00 Kempayya shetty

96 Amruthuru 112/4 Ramanna S/o Kempegowda 0.05 0.16 31.25

142

B S Prabavathi W/o Late G 97 Amruthuru 112/3A 0.00 0.10 0.00 Ramayya

98 Amruthuru 121/1 Venkataramayya S/o Maridimayya 0.05 0.28 17.86

99 Amruthuru 121/3A Chikamma W/o Venkataramayya 0.00 1.12 0.00

A R Annapurnamma S/o A 100 Amruthuru 212/1 0.13 0.28 46.43 Ramaswami ayar

101 Arjunahalli 3/1 Mayamma W/o Late Nanjegowda 0.21 2.38 8.82

Ningamma W/o Nanjayya U 102 Arjunahalli 3/4A Mullappa

103 Arjunahalli 3/7 Manchamma W/o Kenchamma

A G Nanjayya S/o Late 104 Arjunahalli 4/1 0.08 4.11 1.95 Gundegowda

105 Arjunahalli 4/4 Kapanayya S/o Late Nanjayya

106 Arjunahalli 4/8 A S Boregowda S/o A N Siddayya

107 Arjunahalli 4/9 Sharadhamma W/o Channayya

108 Arjunahalli 4/12 A K Shivaramayya 109 Arjunahalli 4/15 Nanjayya S/o Huccha

Nanjundayya S/o Late 110 Arjunahalli 4/16 Doddananjegowda

111 Arjunahalli 4/17A Nacharamma 112 Arjunahalli 4/17A Nanjayya U Buddegowda 113 Arjunahalli 4/17A Kenchappa 114 Arjunahalli 4 Don’t know 115 Arjunahalli 4,5,3 Don’t know 116 Arjunahalli 4/21 A C Kapanayya

A N Sundaresh S/0 A N 117 Arjunahalli 4/21 Nanjegowda

118 Arjunahalli 4/25 A H Kapanayya S/o Hucchegowda

119 Arjunahalli 4/6A Nanjayya S/o Late Kenchegowda

120 Arjunahalli 7/4 Nanjundayya S/o Late Nanjundayya 0.00 0.28 0.00

121 Arjunahalli 7/8 Ninghayya S/o Chikkathayamma 143

122 Arjunahalli 7/11B Shivaraja S/o Kanthappa

123 Arjunahalli 8/1 Puttaswamayya S/o Devarayya 0.00 0.07 0.00

124 Chakanahalli 25/1 Venkata S/o Nelayya 0.12 15.18 0.79

125 Chakanahalli 25/2 Hemavathi nala valaya Tumkur

Shanthamma W/o Late 126 Chakanahalli 25/3 Narayanappa

127 Chakanahalli 26 M Ganghadarayya S/o S Mallayya 0.05 8.10 0.62

Narasamma W/o late M 128 Chakanahalli 26/1 Puttamallayya

129 Chakanahalli 26/2 Shivayya S/o Gangayya 130 Chakanahalli 30/1 Dashappa S/o Rangayya 0.09 7.16 1.26 131 Chakanahalli 30/2 Mallayya S/o Ramayya 132 Chakanahalli 30/3 Milarayya S/o Eramallayya 133 Chakanahalli 30/4 Ramayya S/o Rangayya 134 Chakanahalli 30/5 Narasimhayya S/o Rangayya 135 Chakanahalli 30/6 Rangaswamy S/o Rangayya 136 Chakanahalli 31/2 Malamma W/o Rangayya 0.10 4.14 2.42

137 Chakanahalli 31/1 Rangadhamayya S/o Rangayya

Umashankar S/o Myga 138 Chakanahalli 31/1 Akkamahalakshmi

139 Chakanahalli 31/3 Mallayya S/o Ramayya 140 Chakanahalli 31/4 Mylarayya S/o Eramallayya

141 Chakanahalli 31/5,31/6 H Narayana S/o C Hanumanthappa

K N Thmayya S/o 142 Chakanahalli 35/2 0.09 10.38 0.87 Latepatalanarayana gowda

143 Chakanahalli 35/3 Kempalakkamma W/o Lingayya

C C Shankaralingayya S/o 144 Chakanahalli 35/4 Chennamallagowda

M Shrinivasa S/o Late Y V 145 Chakanahalli 35 Munipapagowda

146 Chikkanahalli 14 Gomala 0.26 71.26 0.36 147 Chikkanahalli 14 Channayya S/o Nanjappa

148 Chikkanahalli 14/P-P1 C N Krishnamurthy S/o Nanjappa

149 Chikkanahalli 14/P-P4 Nanjegowda S/o Nanjayya

144

150 Chikkanahalli 14/P-P6 Siddalingayya S/o Mallegowda

151 Chikkanahalli 14/P-P7 Nanjappa S/o Gidhayya

H C Girimallayya S/o 152 Chikkanahalli 14/P-P7 Chinnamallayya

153 Chikkanahalli 14/P-P7B Gangadharayya S/o Ganganna

P Ramayya S/o Late Topayya U 154 Chikkanahalli 14 Puttayya

P Kappinayya S/o Late thopayya U 155 Chikkanahalli 14 Puttayya

156 Chikkanahalli 15 C K Krishnagowda S/o Channayya 0.05 1.20 4.17

157 Chikkanahalli 16 Mayamma M S Ramachandrappa 0.06 6.10 0.98

158 Chikkanahalli 16/7 Bomayya S/o Nanjayya 159 Chikkanahalli 16 Kempegowda S/o Bomayya 160 Chikkanahalli 16 Bomayya S/o Bomayya 161 Chinavara 54 B S Gangadarayya 0.06 0.14 42.86 162 Chinavara 80,54,87 Sidda U Poojayya 0.14 1.26 11.11

163 Chinavara 88/2 Chikkasiddayya S/o Lt Siddayya 0.07 3.30 2.12

164 Chinavara 88/4 Marisiddayya 165 Chinavara 88/5 B S Gangadarayya

166 Chinavara 88/7 Chikkamma W/o Lt Chaluvayya

167 Chinavara 88/6,88/1 Sidda S/o Kempa 168 Chinavara 114/2 Siddappa S/o Bora 0.01 2.14 0.47 169 Chinavara 113/1 Varadhayya S/o Varadhayya 0.01 1.16 0.86 170 Chinavara 113/2 Mayamma W/o Kariyappa 171 Chinavara 112/1 Kelaradha betayya 0.01 1.10 0.91 172 Chinavara 112/5 Venkatappa 173 Chinavara 112/15 Thimmegowda 174 Chinavara 112/16 Nanjappa 175 Chinavara 112/17 Annemayiga S/o Thimayya 176 Chinavara 111 Pattadha govinda 0.01 0.16 6.25 177 Chinavara 110/3,62/2 Varada S/o Gateyappa 0.03 6.24 0.48 178 Chinavara 110/4B Thimamma U Doddathayi

179 Chinavara 110,62 Thimayya S/o Bandari thimayya

180 Chinavara 109 Kempajjamma W/o Kenchayya 0.01 2.10 0.48 145

181 Chinavara 108/3 Geriyappa S/o Borayya 0.03 23.27 0.13 182 Chinavara 108/4 Amasethimayya 183 Chinavara 108/5 Venkatayya S/o Kullayya 184 Hanchipura 14/1 Ramalingayya 0.03 0.13 23.08 185 Hanchipura 14/1 Suresha S/o H D Govindayya 186 Hanchipura 16/3 Thimayya S/o Ramayya 0.01 0.04 25.00

187 Hanchipura 17/2 Shasharju S/o Chikkachanayya 0.01 2.03 0.49

188 Hanchipura 17/10 H R Sitaramayya

H K Sitaramayya S/o 189 Hanchipura 17/11,100 Mesekempayya

190 Hanchipura 18/2A K Channayya S/o Kuntegowda 0.01 0.37 2.70

191 Hanchipura 18/2B Chennamma W/o Chikkanna 192 Hanchipura 18/5B H P Byregowda S/o Papanna 193 Hanchipura 18/4A1B T Siddalingayya

Lingamma U Doddathayamma W/o 194 Hanchipura 18 Betayya

H K Chikkaborayya S/o 195 Hanchipura 18/5A1 Kempalingayya

Bettagowda S/o Late U 196 Hanchipura 19/2A 0.03 2.03 1.48 Kempaboregowda

Thirumalayya S/o Modlagilindra 197 Hanchipura 19,6/1 gowda

198 Hanchipura 19/3A2 Thimayya S/o Thavasegowda 199 Hanchipura 20 Channayya S/o Gundegowda 0.02 0.11 18.18 200 Hanchipura 20/1A1 Gangadarayya

Chikka thapashayya W/o 201 Hanchipura 20/1A1 Thimmegowda

202 Hanchipura 21/1 H T Chikkegowda S/o Timmayya 0.03 1.06 2.83

203 Hanchipura 35/2 H M Jayanna S/o Maridimayya 0.06 0.07 85.71

204 Hanchipura 34 Byregowda S/o Kempaboregowda 0.02 1.28 1.56

205 Hanchipura 34 Ramayya S/o Kalasayya 206 Hanchipura 33/1 Sarojamma 0.04 3.27 1.22 207 Hanchipura 33/5 T mahesh S/o Thimmayya

208 Hanchipura 29/1 Shusilamma W/o Ramalingayya 0.02 2.24 0.89

209 Hanchipura 30/1 Kempamma U Huchamma 0.15 2.00 7.50

146

Maridimayya S/o Mudlagiriyappa 210 Hanchipura 11 0.01 0.09 11.11 Rachayya

211 Hanchipura 13/1 Lakshmamma W/o Lt Govindhayya 0.01 0.09 11.11

A N Nanjegowda S/o D 212 Hanchipura 153/2 0.00 0.18 0.00 Nanjegowda

213 Hanumanthapura 104/1 Govindagowda S/o Govindagowda 0.27 1.16 23.28

214 Hanumanthapura 104/2 Muddamma W/o Govindappa

215 Hanumanthapura 104/4 Chikkalingayya S/o Chennayya

216 Hanumanthapura 105/2 Javarayya S/o Doddachannayya 0.11 0.05

217 Hanumanthapura 105/3 Chikkayya U shivalingayya

218 Hanumanthapura 107 Govt Karabu 0.02 0.24 8.33

219 Hanumanthapura 53/2 H B Gurupathi S/o Byattayya 0.04 1.07 3.74

H G Thirumallayya S/o Govinde 220 Hanumanthapura 53/2 gowda

221 Hanumanthapura 53/6 Mudhayya S/o Huchayya

Lakshmidevamma W/o 222 Hanumanthapura 53/10 Jayaramayya

Doddagangayya W/o H B 223 Hanumanthapura 53/11 Kenchayya

224 Hanumanthapura 54/3 Javarayya S/o Chennagirayayya 0.08 0.28 28.57

225 Hanumanthapura 58/1 S ranadheera singh S/o Shivasingh 0.01 0.28 3.57

226 Hanumapura 21/2 Mudhayya S/o Huchayya 0.03 0.07 42.86 227 Hanumapura 21/5 H J Hanumayya B Javarayya

228 Hanumapura 21/6 Gereyappa S/o Hanumay gowda

Mayamma W/o Late Geriyappa U 229 Hanumapura 21/6 Badakappa

230 Hanumapura 108 Govt Karabu 0.12 0.03 231 Hanumapura 3 Gomala 0.04 1.14 3.51

232 Hanumapura 52 H G Venkataramu S/o Govindhayya 0.02 1.32 1.52 147

233 Hanumapura 52A Siddamma W/o Govindayya

234 Hanumapura 51/5 Magadamma W/o Hanumegowda 0.05 0.14 35.71

Venkatalakshmamma W/o 235 Hanumapura 51/5A Geriyappa

236 Hanumapura 50/1,50/2 0.03 3.06 0.98

J D Kempagooligowda S/o 237 Jinnagara 269 0.03 1.20 2.50 Dodanna

238 Jinnagara 269/2B Mayamma W/o Ramakrishnayya

239 Jinnagara 272/1 J K Kempagoolayya S/o Kempayya 0.02 1.14 1.75

240 Jinnagara 272/4 Ramayya S/o Goolayya U Bajayya

241 Jinnagara 272/4 Ramayya S/o Goolayya U Bajayya

Sitaramayya S/o Horakere 242 Jinnagara 274/3,274/9 0.07 5.18 1.35 Kempegowda

Horakere ramashayya S/o 243 Jinnagara 274 Horakere kempegowda

Ramashayya S/o Horakere 244 Jinnagara 274/4,274/8 Kempayya

G J Ramanna S/o Horakere 245 Jinnagara 274/11A guligowda

Kempagulayya U Papanna 246 Jinnagara 274/14 kenchayyana guligowda

247 Jinnagara 274 K Nataraja S/o Late G Kempayya

248 Jinnagara 1/3A,1/2B J J ramayya S/o Javarayya 0.08 5.06 1.58 249 Jinnagara 1/4B Golayya S/o Late Chikkayya 250 Jinnagara 1/6A Kempayya S/o Kempegowda

251 Jinnagara 1/8A Guligowda S/o Kempaguligowda

252 Jinnagara 1/8B,272/6 K Srinivas S/o hottekempayya 253 Jinnagara 1/1A2 Don’t know

Hucchappakalegowda S/o 254 Jinnagara 1/11C Kempayya

255 Jinnagara 1/12A Ramayya S/o Pukkannagoolayya

256 Jinnagara 1/14A2 Govt Karabu

257 Jinnagara 1/15 Mahi kempaguli hivathujana jinta

148

258 Jinnagara 2/4A Chikkaramayya S/o Thimayya 0.01 3.02 0.33 259 Jinnagara 2/7C J J Nagaraju S/o Jogayya

260 Jinnagara 2/8A Chikkalingayya S/o Gerigowda

G H Kempayya S/o Hucchappanna 261 Jinnagara 2/20A kempayya

262 Jinnagara 2/20A Goolayya S/o Gooligowda

263 Jinnagara 2/14 G Huchayya S/o Thimmegowda

264 Jinnagara 2/15A TAPCMS 265 Jinnagara 2/15C Govt Karabu

266 Jinnagara 2/15D Seregoolayya S/o Seregoolayya

267 Jinnagara 2/15A Not found 268 Jinnagara 2/15F NAK 269 Jinnagara 2/153 ALN

Gooligowda S/o Muddammanna 270 Jinnagara 2/18A gooligowda

Lakshmamma U Karakamma W/o 271 Jinnagara 2/18B Doddathimmegowda

Kempegowda S/o Hucchappa 272 Jinnagara 2/20A kempayya

J H Kempayya S/o Hucchappana 273 Jinnagara 2/20A kempaya

Huchayya S/o Hucchappanna 274 Jinnagara 2/20A Kempayya

Karigoolayya S/o Huchappanna 275 Jinnagara 2/20A kempayya

Goolayya S/o Chikkayyanna 276 Jinnagara 60/9 0.01 0.03 33.33 hucchayya

Kempagoolayya S/o Papanna 277 Jinnagara 56/8 0.02 0.01 kenchayyana gooligowda

278 Jinnagara 105/7 Krishna U Chikkayya 0.24 0.38 63.16 279 Jinnagara 105106 G K Bagurayya S/o Kullayya

G S Bagurayya S/o Sidayya U 280 Jinnagara 105106 Savalayya

M K Shrinivas Ayangar S/o Shilpa 281 Jinnagara 108 0.12 11.36 1.06 narayana ayangar

282 Jinnagara 56/10 Kariyappa S/o Kundurgooligowda 0.02 1.11 1.80

J G Rameshayya S/o Kunduru 283 Jinnagara 56/5,2/16A2 gooligowda 149

284 Jinnagara 56,1 H L Bharathi W/o J T Ramayya

285 Jinnagara 276/2 Goolayya S/o Pukkannagoolayya 0.04 1.16 3.45

286 Jinnagara 276/1B Ramanna S/o Horakere Kempayya

287 Jinnagara 276/2B Kharabhu 288 Jinnagara 276/4B N A Karbu 289 Jinnagara 275 Taluk Health Doctor 0.07 2.20 3.18 290 Jinnagara 60/6 Serigoolayya 0.01 0.18 5.56

Thimayya U Kenghayya S/o 291 Jinnagara 60/8B Dodamunna hucchayya

292 Jinnagara 66/1 Savandashetty S/o Nanjashetty 0.04 1.02 3.92

293 Jinnagara 66/3A Kariyappa S/o Savandi 294 Jinnagara 66/3B Kempayya S/o Chennayya 295 Jinnagara 54/18 FADA 0.23 0.28 82.14 296 Jinnagara 54/12 Nanjamma W/o Thimayya

297 Jinnagara 54/4 P Kallegowda S/o Muddigooligowda

298 Jinnagara 54/9B Lingamma W/o Dasegowda

299 Jinnagara 54 Ramayya S/o Kariguli kundhayya

300 Jinnagara 1,53,54 J K gooligowda S/o Kempegowda 1.11 0.16

301 Jinnagara 53/2A Bagyamma W/o S N Chanappa 0.21 2.17 9.68

302 Jinnagara 53/4 Bagyamma W/o S N Chanappa

303 Jinnagara 53/2B Bagyamma W/o S N Chanappa

304 Mangala 73 Geriyamma W/o Geriyappa 0.06 1.20 5.00 305 Mangala 72,25 Gomala 0.07 39.21 0.18

M Venkatalakshmamma W/o 306 Mangala 71/1A 0.08 6.30 1.27 Narayannappa

307 Mangala 71/2B Byregowda S/o Hucchagowda

Thimmegowda S/o Gururayana 308 Mangala 71/3A venkatagowda

309 Mangala 71/2C Kempajamma W/o Gerigowda

310 Mangala 67/1 Nanjamma W/o Dasagowda 0.09 8.30 1.08

150

311 Mangala 67/1 Maggirangayya S/o Dasegowda

312 Mangala 67/2A Masthigowda S/o Bommegowda

Mangalagowramma W/o Late 313 Mangala 67/2B Andanayya

Mangalagowramma W/o Late 314 Mangala 67/2B2 Andanayya

315 Mangala 43 Lakshmamma w/o Thopayya 0.12 1.26 9.52

316 Mangala 43 Yogesha S/o M M Bommegowda

317 Mangala 43 Nagaraja S/o Niranjanayya

318 Mangala 43 Shankarappa S/o Basavarajayya

319 Mangala 43/E M S Shivakumara S/o Shivanna

320 Mangala 41 Adress not found 0.12 22.09 0.54

Thimayya S/o Geriyayyana 321 Mangala 25 0.36 2.12 16.98 hendathi Gangamma

322 Mangala 25 S Rajeshwari S/o Siddalingayya

323 Mangala 25 Chikkasiddayya S/o Siddayya 324 Markenahalli 53 Suryanarayanna S/o Hanuma 0.05 1.12 4.46 325 Markenahalli 53 Hanumayya S/o Dokayya

326 Markenahalli 53C Hanumanthayya S/o Hanumayya

327 Markenahalli 22/4 Mayanna S/o Modlayya 0.14 2.32 6.03 328 Markenahalli 22 Dodamma W/o Thimayya 329 Markenahalli 22/19 Kempegowda S/o Mayanna 330 Markenahalli 28 Shrinivasadevaru 0.11 6.13 1.79

331 Markenahalli 28 Thimayya S/o Honnagirigowda

332 Markenahalli 50 Kariyappa S/o Chikkacheluvayya 1.11 6.20 17.90

333 Sanaba 210/3 Thirumalayya S/o Kadale 0.06 1.02 5.88

334 Sanaba 210/4,166/18A Mayamma W/o Chennegowda

335 Sanaba 210/5 Muddi kempana chikka chenna

336 Sanaba 211/3 Busigowda Dasegowda

Thimayya S/o Dasagowda 337 Sanaba 211/4 0.04 0.15 26.67 naragegowda 151

338 Sanaba 211/5 Thimayya S/o Chenna

339 Sanaba 214/1 Puttananjayya S/o Hottechannayya 0.04 3.39 1.18

340 Sanaba 214/8 Mayamma S/o Kempayya

341 Sanaba 214 Nilamma W/o Late S N Nanjappa

S N Shivananjayya S/o 342 Sanaba 214/11 Doddananjayya

Nanjamma W/o Kempayya 343 Sanaba 214/13,94 papanna

344 Sanaba 214/4A Nanjegowda S/o Nanjagowda

Jayalakshmamma W/o S C 345 Sanaba 214/4D,165/2A Nanjegowda

346 Sanaba 214/5A Devaraj S/o Nanjayya 347 Sanaba 214/5B Nanjayya S/o Kapanigowda

348 Sanaba 214 S T Dasappa S/o Thimmegowda

349 Sanaba 166/7 Thimamma W/o Chennathimayya 0.06 1.12 5.36

350 Sanaba 166/22 J L Ramayya S/o Lingegowda 0.00

S K Kadalayya S/o 351 Sanaba 166/26,166/14 0.00 Doddakadalagowda

352 Sanaba 166 G L Ramayya S/o Lingegowda 0.00

353 Sanaba 166/28 Nanjayya S/o Chikkapapanna 0.00

354 Sanaba 166/29 Chikkananjayya U Chikkapapayya 0.00

355 Sanaba 166/30 Nanjayya S/o Nanjegowda 0.00

356 Sanaba 166/32C G L Ramayya S/o Lingegowda 0.00

357 Sanaba 165/3 S N Shivananjayya 0.20 2.20 9.09

L C Nanjegowda S/o 358 Sanaba 165/2B Chinnamallegowda

S C Sreekantayya S/o 359 Sanaba 165/2E Hottechannayya

360 Sanaba 165/2F,119/5 Huchayya S/o Bhadrayya

361 Sanaba 165/2C S H Vasudeva S/o Hucchayya

362 Sanaba 123/1,165/2F S H Vasudeva S/o Hucchayya 0.29 1.22 23.77

152

363 Sanaba 119/5,165/2F Lakshmamma W/o Puttachanayya 0.20 0.34 58.82

364 Sanaba 96/15,96/2 S N Shivanna S/o Chikkananjayya 0.16 2.08 7.69

365 Sanaba 96 Gundayya S/o Badalinganaborayya

366 Sanaba 96 Bagyamma W/o Borayya 367 Sanaba 96 Kempayya S/o Badalingayya 368 Sanaba 96 Kempayya S/o Badalingayya 369 Sanaba 150/3 S T Srinivasayya 0.06 0.39 15.38

Nanjegowda U Devayya S/o 370 Sanaba 146150 0.08 9.04 0.88 Nanjegowda

Kempayya S/o Nanjegowda U 371 Sanaba 146/4,150/5 Doddahudugegowda

372 Sanaba 93 Puttegowda S/o Chikkananjegowda

373 Sanaba 93 S K Chikkananjayya 0.00 1.18 0.00

374 Sanaba 119/5 Pettechannayya S/o Channagowda 0.04 0.34 11.76

375 Sanaba 123/2 S H Vasudeva S/o Lt Huchayya 0.09 1.28 7.03

Jayalajshmamma W/o Lt S C 376 Sanaba 129165149 0.30 1.08 27.78 Nanjegowda

377 Sanaba 149/1 V M Krishna S/o V S Mariyappa 0.04 6.06 0.66

378 Sanaba 149,129,165,209' Chandramma W/o Chikkananjayya

379 Sanaba 146 S N Appegowda S/o Nanjegowda 0.02 5.12 0.39

380 Sanaba 146 S K Nangegowda S/o Kempegowda

P Nanjegowda S/o 381 Sanaba 146150 Doddahudugegowda

Nanjamma W/o Kempayya 382 Sanaba 146/9 papanna

Narayanashetty S/o 383 Shanuboganahalli 29/1 0.06 2.00 3.00 Chikkannashetty

Chikkamurugamma W/o 384 Shanuboganahalli 29/1 Siddalinghayya

385 Shanuboganahalli 31/1 Ramanna S/o Kempegowda 0.03 2.06 1.46 153

386 Shanuboganahalli 31/2 Sidhayya murugayya

387 Shanuboganahalli 31/4 Gangadharayya S/o Mugurayya

388 Shanuboganahalli 31/4 Y B Borayya S/o Mugurayya

389 Shanuboganahalli 31/5 Mayamma W/o Sidhayya

390 Shanuboganahalli 31 Shivalingayya

391 Shanuboganahalli 31 Shivalinghayya S/o Muguru meshtri

392 Shanuboganahalli 31/8 Gangadharayya S/o Mugurayya

393 Shanuboganahalli 38,37 Adress not found 0.01 0.38 2.63

394 Sunnadapura 3/2' Halavayya S/o Kulagowda 0.04 5.18 0.77 395 Sunnadapura 3/3' Gangamma W/o Thimayya

396 Sunnadapura 3/4' M M Ramanna S/o Mayannagowda

397 Sunnadapura 3/1A Krishnappa S/o Channayya 398 Sunnadapura 3/1B Sakamma W/o Channayya

399 Sunnadapura 3/1B Basavaraja S/o Kempamaigowda

400 Sunnadapura 3/1B Bagyamma W/o Krishnappa 401 Sunnadapura 2 Adress not found 0.17 12.22 1.39 402 Sunnadapura 36/1 Kenga S/o Kenga 0.19 5.00 3.80

Yallakamma W/o Thirumallayya U 403 Sunnadapura 36/2 Papa

404 Sunnadapura 36/2 Thimayya S/o Nanjayya 405 Sunnadapura 19/5 Giriyappa S/o Giriyappa 406 Sunnadapura 19/5 Giriyappa S/o Hanumagowda

Mayamma Late Giriyappa U 407 Sunnadapura 19/5 Badakappa

H H Hanumayya S/o 408 Sunnadapura 19/5 Hanumayegowda

409 Sunnadapura 20/2 Giriyappa S/o Hanumegowda 0.08 1.00 8.00

Ninghamma W/o Thimayya U 410 Sunnadapura 21 0.06 3.18 1.89 Kenchayya

Hanumayya U Sanayya S/o Late 411 Sunnadapura 21 Hanumegowda

154

412 Sunnadapura 21 H J Hanumayya S/o Late Javarayya

413 Sunnadapura 22 Mayamma S/o Giriyappa 0.02 1.39 1.44 414 Sunnadapura 22 Giriyappa S/o Hanumegowda

415 Sunnadapura 24/1A Hanumamma W/o Hanumayya 0.12 2.04 5.88

416 Sunnadapura 24/2A Adress not found

417 Sunnadapura 24/2B Thirumallayya S/o Hanumegowda

418 Sunnadapura 24/2C Adress not found 419 Yachanahalli 14 Haravva W/o Dodayya 0.09 1.28 7.03

A P Gopalakrishna S/o 420 Yachanahalli 14/8 Puttarangashetty

421 Yachanahalli 10/26 Chinamma W/o Chikkanna 0.06 0.25 24.00 422 Yachanahalli 10 Eramma W/o Anamahi 423 Yachanahalli 30,29 Thimamma W/o Wyermudi 0.04 1.30 3.08

424 Yachanahalli 27/1A Shivalingayya S/o Muguramesthri 0.08 0.22 36.36

425 Yachanahalli 24/2 Sidda S/o Muttanasidda 0.09 4.00 2.25 426 Yachanahalli 24 Borayya S/o Mullayya

427 Yachanahalli 22 A D Narayanaswamy S/o Dasappa 0.11 3.24 3.40

428 Yachanahalli 22/4 A T Ranganatha S/o Thirumalayya

429 Yadavani 18,19 Y S Subbegowda S/o Subbegowda 0.05 3.22 1.55

430 Yadavani 18 M S Gangayya S/o Subbegowda

431 Yadavani 255/1 Hucchamma W/o Lata Siddappa 0.14 0.26 53.85

432 Yadavani 257,256,117,247' Karabu 0.19 2.20 8.64

433 Yadavani 254,257,255,' Alumelamma W/o S Shivaramayya 0.19 10.06 1.89

434 Yadavani 251/5,252/3 K L Jayamma W/o B C Channayya 0.28 2.06 13.59

435 Yadavani 251/8 Shivaramayya S/o Beligowda 436 Yadavani 251/10 Manchayya S/o Nanjayya 437 Yadavani 251/12B Huchayya S/o Hucchamasthri

438 Yadavani 251/20 Boramma W/o Late Chikkanna 155

Y N Sree Kantayya S/o 439 Yadavani 251 Nirvaninanjayya

440 Yadavani 251/24 Y N Sree Kantayya S/o Nanjayya

Shivananjamma S/o 441 Yadavani 251/25 Puttaswamayya

Y N Chikkamanchayya S/o 442 Yadavani 251 Nanjayya

443 Yadavani 251/32,251/34 Y N Shivananjayya S/o Nanjayya

444 Yadavani 251/33 B Shivashankara S/o S Borappa

445 Yadavani 252/4 Lingayya S/o Kullegowda 0.00 0.02 446 Yadavani 250/3 Masthayya 0.23 0.08 447 Yadavani 247/1 Sidda S/o Puravanalinga

Y M Shivananjayya S/o 448 Yadavani 247251250 masthigowda

449 Yadavani 247/6 Nanjamma W/o Subbayya 1.07 1.03

450 Yadavani 247/6 Nanjamma W/o Late Rudrayya

451 Yadavani 247/9 Y N Ramanna 452 Yadavani 247/10 Kunigowda S/o Lingegowda 453 Yadavani 247/8 Lakshmamma W/o Kullayya

Y C Huccha masthigowda S/o 454 Yadavani 247/12 Channayya

455 Yadavani 241/4 Shivanna S/o Mugurayya 1.27 3.06 41.50 456 Yadavani 247241 Dalayya S/o Dallegowda 457 Yadavani 241 Y N Nanjayya S/o Nanjayya 458 Yadavani 241 Dalayya S/o Dallegowda 459 Yadavani 115/1 0.26 6.10 4.26

Kallegowda S/o 460 Yadavani 154 0.00 0.09 Chennamasthagowda

461 Yadavani 161169 A H Kapanayya S/o Hucchegowda 0.00 2.30

462 Yadavani 164161 A K Nanjundayya S/o Kenchayya 0.00 1.06

463 Yadavani 161/8 Jogi S/o Sidda 0.00 0.26

Chikkachennamma W/o 464 Yadavani 162/1 0.00 1.04 Nanjundayya

465 Yadavani 163/2 Parvathamma W/o Chennayya 0.00 0.36

156

Byregowda S/o Myga Thata 466 Yadavani 163162 chennayya Gangadarayya

467 Yadavani 163/4 Shivamma S/o Channayya 468 Yadavani 164 Kapanayya S/oMariyappa 0.00 7.00 469 Yadavani 169 Kapanayya S/o Kenchayya 0.00 0.24

Affected Land/Area Details for 57C Area in Acre- Gunta

% of Sl. Affected Total Village Survey No. OwnerName Affected No. Area Area Area

1 Challanayakanahalli 72/1C C L Ramesha S/o Lingegowda 0.01 1.09 0.92

2 Challanayakanahalli 72/1C C B Suresh S/o Boregowda

3 Challanayakanahalli 72/2 Chikkegowda S/o Bommegowda

C S Sathish S/o Late 4 Challanayakanahalli 72/6,72/1A,57/5B Shivalingegowda

B K Puttalingamma W/o Late 5 Challanayakanahalli 54 0.10 1.20 8.33 Lingegowda

C L Shankare gowda S/o Late BC B 6 Challanayakanahalli 54/1E Lingegowda

7 Challanayakanahalli 54/4 Boregowda S/o Mogegowda S

8 Challanayakanahalli 54/8,54/10 Lingamma S/o Linga U Kallugute

56/2B,56/2C,57/1 9 Challanayakanahalli Jayamma W/o Karigowda 0.00 0.20 0.00 B

10 Challanayakanahalli 77 H Papanna So Boregowda 0.00 4.09 0.00

11 Challanayakanahalli 77/1A K Panchegowda S/o Karigowda

12 Challanayakanahalli 77/6B Lingegowda S/o Late Kempegowda

Puttaswamy gowda 13 Challanayakanahalli 77/7 S/oChikkakempegowda

Jayaramu S/o Lingegowda U 14 Challanayakanahalli 77/1A Karishetty

15 Challanayakanahalli 77/1A Rathnamma W/o Kemegowda

Chikkathayamma W.o Late 16 Challanayakanahalli 77/8 Lingegowda Nathegowda 157

Thimannagowda S/o Lingegowda U 17 Challanayakanahalli 77/8B Karishetty

Boregowda S/o Lingegowda U 18 Challanayakanahalli 77/8B Karishetty

Patela Chikkaboregowda S/o 19 Challanayakanahalli 77/9 Chikkaboregowda

20 Challanayakanahalli 77 Lingegowda S/o Channegowda

Chikkahydhayya S/o Gande 21 Challanayakanahalli 53/A 0.01 1.14 0.88 Cheluvayya

22 Challanayakanahalli 53/B Dodda Chaluvayya S/o Mariyayya

23 Challanayakanahalli 53/C Kundasingri S/o Doddachaluvayya

24 Challanayakanahalli 53/D Kunisinghrayya S/o Mothayya 25 Challanayakanahalli 53/L Chaluvayya S/o Mothayya

26 Challanayakanahalli 53/H Manghalamma W/o Javarayya

Padhmamma W/o Late C L 27 Challanayakanahalli 54/1A,77/8A 0.10 1.25 8.00 Lingegowda

C L Lingaraju S/o Lingegowda U 28 Challanayakanahalli 54 Nathegowda

D Jayarama S/o 29 Challanayakanahalli 54/14,54/1D Doddathimmagowda

30 Challanayakanahalli 54/2A K Borayya S/o Karigowda 31 Challanayakanahalli 54/2D Boregowda S/o Nathegowda

32 Challanayakanahalli 54/2E T Boregowda S/o Thimmegowda

C T Boregowda S/o Chikka 33 Challanayakanahalli 54/10 Thimmegowda

D Jayarama S/o 34 Challanayakanahalli 54/13 Doddathimmagowda

Thimamma W/o Mysore Karigowda 35 Challanayakanahalli 56/1 0.02 1.16 1.72 Lingegowda

36 Challanayakanahalli 56/5 Boregowda S/o Subbegowda

37 Challanayakanahalli 57/1A Kemegowda S/o K Kempegowda 0.22 1.24 17.74

38 Challanayakanahalli 57/4B Ningegowda S/o Lingegowda

39 Challanayakanahalli 57/5A Kempamma W/o Jallu Boregowda

Shombhugowda U Gundegowda 40 Chandagalu 51/1A,51/2B 0.07 0.32 21.88 S/o Thamayya

158

41 Chandagalu 52 Venkatayya S/o Dasayya 0.02 0.38 5.26

42 Chandagalu 57 Cheluvarajashetty S/o Puttashetty 0.01 1.26 0.79

43 Chandagalu 57/1-P2 Motegowda S/o Mullure gowda

44 Chandagalu 57/1-P3 Nagamma W/o Marigowda 45 Chandagalu 57,50 Bridge

C M Thimmannagowda S/o 46 Chandagalu 57 Mottegowda

47 Chandagalu 57 M Shankaragowda S/o Mottegowda

48 Chandagalu 57/8B,57/4F Shumbhuva U Minne

Shambuva U Khajanigowda S/o 49 Chandagalu 57 Karigowda

50 Chandagalu 57/11B Shivalinge Gowda S/o Karigowda

Ningegowda S/o Sunaganahalli 51 Chandagalu 57/12 Ningegowda

52 Chandagalu 57/19A Thimamma W/o Chikkalingegowda

53 Chandagalu 57/22C Shanthamma S/o Javaregowda

54 Chandagalu 57/24 Mottegowda S/o Kenchegowda

55 Chandagalu 57/26 B Shankare Gowda S/o Budigowda

56 Chandagalu 37/1A Hottnegowda S/o Chikkalingegowda 0.01 2.13 0.47

M Shankare Gowda S/o 57 Chandagalu 37,51,57 Mottegowda

58 Chandagalu 37/6B K Shambhanna Late Karigowda

59 Chandagalu 37/8E K Shambhanna Late Karigowda

C K Shambhanna S/o 60 Chandagalu 36/1A 0.01 0.25 4.00 Kurilingegowda

61 Chandagalu 36/1A Shivalingayya S/o Karigowda

S Boregowda S/o Chikka 62 Chandagalu 47 0.00 6.12 0.00 Boregowda

63 Chandagalu 47/2 Rajanna S/o Karigowda 64 Chandagalu 48/1,37/4D T Thamayya S/oThamayya 0.06 2.36 2.54 159

C N Thammannagowda S/o 65 Chandagalu 50/7B,50/2 0.04 3.10 1.29 Mottegowda

Ramalingayya s/o 66 Chandagalu 50/7A Chikkahydegowda

Rajanna S/o Shambhuvva U 67 Chandagalu 51,37 0.07 5.24 1.34 Magegowda

Sharadhamma W/o Late S 68 Chandagalu 51,47,53 Shankaregowda

69 Chandagalu 51/2A C K Nagaraju S/o Kengashetty

70 Chandagalu 52 Kalamma W/o Late Govindhayya 0.02 2.38 0.84

71 Chandagalu 52 Thimayya S/o Dasayya 72 Chandagalu 52 Venkatesha S/o Kariyayya

K Puttaswamy gowda S/o 73 Chandagalu 53/1 0.01 0.10 10.00 Karigowda

74 Chandagalu 37/8D Sakamma W/o Nanjegowda 0.01 0.10 10.00

75 Chandagalu 37/11A Chanamma W/o C K Papegowda

76 Chandagalu 36/A Kullegowda S/o Mottegowda 0.01 14.06 0.07 77 Chandagalu 36/1A Rajegowda S/o Nanjegowda

Puttaswamy Gowda S/o 78 Chandagalu 36/2A Lingegowda U Kuntegowda

Chikkathayamma W/o Late 79 Chandagalu 36/2A Lingegowda unathegowda

80 Chandagalu 36 C L Ramesha S/o C B Lingegowda

81 Chandagalu 36/4 C L Lingaraju

82 Chikkaballi 230/1 S Ashok S/o Late P Shivaramayya 0.36 2.14 16.82

83 Chikkaballi 230/1 J P Chandrika W/o K Shivanna

84 Chikkaballi 230/1 K Shivanna S/o Kallegowda

Nirmala W/o Late 85 Chikkaballi 230/1 parashuramegowda

Chikkamanjegowda U Kariyappa 86 Chikkaballi 230/3 S/o Kallegowda

87 Chikkaballi 230/4 S Aravindha S/o Shankaregowda

88 Chikkaballi 230/4 A G Virupakshi S/o Gowdhayya

160

89 Chikkaballi 168/1 K Devakumara S/o L Krishnayya 0.00 2.04 0.00

90 Chikkaballi 168/2 Sannalingegowda S/o manjegowda

L Ramalingegowda S/o 91 Chikkaballi 168/4 Kenchanalingegowda

M Thammanna gowda S/o L 92 Chikkaballi 168/8 Manjegowda

A M Shankaregowda S/o K 93 Chikkaballi 168/10 Manchegowda

94 Chikkaballi 168/11A S Krishnegowda S/o Sannegowda

95 Chikkaballi 168/11B A S Rajanna S/o Sannegowda

96 Chikkaballi 169/2 S Shivagowda S/o Sannegowda 0.01 1.03 0.97

M Shivashankara S/o 97 Chikkaballi 169/2B Manchegowda

98 Chikkaballi 169/2 B Lingegowda

M Shivashankara S/o 99 Chikkaballi 169/2 Manchegowda

100 Chikkaballi 169/4 P Shivalingegowda

A P Prakasha S/o Puttaswamy 101 Chikkaballi 169/4 gowda

102 Chikkaballi 228/1 A G Virupakshi S/o Gowdayya 0.00 2.39 0.00

103 Chikkaballi 228/7 Chanamma W/o Ningegowda

B Lingegowda S/o 104 Chikkaballi 228/8A,228/4 Buddelingegowda

105 Chikkaballi 228/9 K Ramesh S/o Late Karisiddegowda

106 Chikkaballi 227/1 K Ramesh S/o Late Karisiddegowda 0.10 1.33 7.52

Chikkamanjegowda S/o 107 Chikkaballi 227/3 Sannegowda

Puttaswamy Gowda S/o 108 Chikkaballi 227/4 Lingegowda

B Lingegowda S/o 109 Chikkaballi 227/6B Buddelingegowda

110 Chikkaballi 227/8,227/10 Jayamma W/o Lingegowda

111 Chikkaballi 227 Nagamma W/o C L Shankaregowda 161

1st Revanna S/o Javaregowdhna 112 Chikkaballi 226/1B 0.04 1.23 3.25 Lingegowda

113 Chikkaballi 226/1 Shiva Rathnamma W/o Manchayya

114 Chikkaballi 226/3A A S Rajanna S/o Sannegowda

A M Manchegowda S/o 115 Chikkaballi 226/2B Manchegowda Donnegowda

Chikkathayamma W/o 116 Chikkaballi 226/5 Chikkamanchegowda

117 Chikkaballi 224/1 Somashekar S/o Kallegowda 0.05 1.06 4.72

118 Chikkaballi 224/3A Chikkathayamma W/o Machegowda

Kempegowda S/o 119 Chikkaballi 224/10 Chikkalingegowda

Shivalingegowda S/o Puttaswamy 120 Chikkaballi 211/1,224/7 0.01 2.12 0.47 gowda

A M Manchegowda S/o 121 Chikkaballi 211/2 Manchegowda Donnegowda

122 Chikkaballi 211/2 Shankaregowda S/o Donnegowda

123 Chikkaballi 67/1A,67/7 D Shankara S/o Dhayamayya 0.01 3.28 0.30

124 Chikkaballi 67/2A Chikkamanchegowda U Kariyappa

L Rukminiyamma W/o Late D 125 Chikkaballi 81/1,230/1 0.22 1.26 17.46 Annegowda

126 Chikkaballi 81/3 Chandrashekarayya S/o Ramayya

127 Chikkaballi 98/A Ramanna S/o Lingegowda 0.04 0.03 133.33

128 Chikkaballi 101/1 Karigowda S/o Doddalinganagowda 0.11 0.20 55.00

K Shivalingegowda S/o 129 Chikkaballi 101/2 Kempegowda

130 Chikkaballi 100/2 Kamalamma W/o T Ramegowda 1.14 0.24 475.00

131 Chikkaballi 100/7 Rajanna S/o Thimmegowda

K A Lakshmamma W/o Late 132 Chikkaballi 167 0.22 0.10 220.00 Nagaraja

Chikkamarigowda S/o 133 Chikkaballi 171/13 0.14 0.28 50.00 Chikkalingegowda

134 Chikkaballi 171/14 C Marigowda S/o Chikkamarigowda

162

N Kariyappa S/o Ningegowda U 135 Chikkaballi 171/16 Yadachegowda

136 Chikkaballi 205/2 C Marigowda S/o Chikkamarigowda 0.05 0.28 17.86

137 Chikkaballi 205/2 C Marigowda S/o Chikkamarigowda

138 Chikkaballi 205/2,227/11 C M Yoga S/o Marigowda

139 Chikkaballi 205 Putamma W/o Late Ramegowda

140 Chikkaballi 205/15 B Lingegowda S/o Beligowda

Chikkalingegowda S/o 141 Chikkaballi 205/20 Chikkamarigowda

142 Chikkaballi 209/5 Gowramma S/o Lingegowda 0.01 1.20 0.83

143 Chikkaballi 209/6 Karigowda S/o Manchegowda

144 Chikkaballi 209/7 Chikkathamayya S/o Lingegowda

145 Chikkaballi 209/18 Sharadhamma W/o B A Nanjappa

Sannamariyamma W/o Late 146 Chikkabanasavadi 96 0.01 1.00 1.00 Javaregowda

H S Prasanakumar Myga Thaie 147 Chikkabanasavadi 65/2E 0.01 0.22 4.55 Prema

148 Chikkabanasavadi 67/A,67/A M Thimayya S/o Chunchanagiri 0.03 5.14 0.58

J C Boregowda S/o 149 Chikkabanasavadi 67 Chikkaboregowda

G D Yogananda gowda S/o G 150 Chikkabanasavadi 67 Dollegowda

151 Chikkabanasavadi 67/E G C Suresha S/o Chikkaboregowda

152 D Malligere 22,23 Beligowda S/o Doddamariyya 0.00 0.37 0.00 153 D Malligere 22/9 Thimayya S/o Basavegowda

Thimmegowda S/o Magadi 154 D Malligere 24/7 0.03 3.07 0.98 Thimmegowda

Nanjundegowda S/o Kajasegowda 155 D Malligere 24/9 Nanjegowda

Ramanna S/o Mariyya U 156 D Malligere 24/12,24/4 Hottegowda

157 D Malligere 24/13 Marigowda S/o Marigowda 158 D Malligere 24/17 Thimayya S/o Basavayya 163

C Chenappa S/o Pallallli 159 D Malligere 24/15 chekkegowda

160 D Malligere 27/5 M T Narayana S/o Thimayya 0.04 0.18 22.22

161 D Malligere 86/4 Nanja S/o Nanja U Appegowda 0.11 1.37 8.03

162 D Malligere 86/6,86/2 Shivananjayya S/o Chikkegowda

163 D Malligere 86/23 Masthayya S/o Kullegowda 164 D Malligere 86/24 Channappa S/o Ningayya 165 D Malligere 86/29 Manchayya S/o kenchegowda 166 D Malligere 86/16,86/19 Narayana S/o Mudligowda

167 D Malligere 86/38 H Puttaswamy S/o Hulegegowda

168 D Malligere 85/3 Nanjamma W/o Boregowda 0.08 4.14 1.93

Boramma W/o Nanjayya U 169 D Malligere 85/12-P1 Nathayya

170 D Malligere 85 Channappa S/o Ningegowda 171 D Malligere 85/9 Thimayya S/o Bettayya

172 D Malligere 34/1 Nanjayya S/o Late Chikkegowda 0.00 3.37 0.00

173 D Malligere 34/5 Dodda Biliyayya S/o Marigowda

Nanjayya S/o Kalasegowda 174 D Malligere 34/6,24/8 Nanjayya

Shankaregowda S/o Late 175 D Malligere 34/8 Nanjundegowda

Chikka Thimayya S/o Gullebettanna 176 D Malligere 22/2,86/36 0.00 1.02 0.00 Borayya

177 D Malligere 23/8A Narayana S/o Mudligowda 0.16 1.28 12.50 178 D Malligere 23/12,86/35 Hucchappa S/o Hucchappa

179 D Malligere 23,27 Masthi Gowda S/o Marigowda

180 D Malligere 23/17 Betta U Gundhayya

Chikka Thimmegowda S/o Magadi 181 D Malligere 23/20A3 Karigowda

Nagaraju S/o Thimayya Late 182 D Malligere 30/1 0.16 1.16 13.79 Bettegowda

183 D Malligere 30/6C Borayya S/o Kariborayya

184 D Malligere 83,85,27 Karigowda S/o Late Bettegowda 0.03 0.38 7.89

185 Dodda Banasavadi 14 B Siddegowda S/o Huchegowda 0.12 8.38 1.43

164

186 Dodda Banasavadi 14 T Narayanaswamy S/o Borayya

187 Dodda Banasavadi 14/A22 Armuga S/o Sannayya 188 Dodda Banasavadi 14 Mugayanna Kalayya

Lingamma W/o Buyegowdna 189 Dodda Banasavadi 14/C1 Thammegowda

190 Dodda Banasavadi 14/C2 K Boregowda S/o Late Kariyappa

K B Puttaswamy S/o 191 Dodda Banasavadi 14 Rateboregowda

192 Dodda Banasavadi 14 K B Prakasha S/o Rateboregowda

193 Dodda Banasavadi 119/1 Dhavayya S/o Dollaboregowda 0.00 1.14 0.00

194 G Hoshalli 75/4A Boregowda S/o Chanayya 0.38 0.14 271.43

195 G Hoshalli 52,53 Anandegowda S/o Nanthegowda 0.00 2.22 0.00

S Somashekarayya S/o H B 196 G Hoshalli 49/1A 1.10 14.07 7.82 Shambhu lingayya

197 G Hoshalli 49/1A C N Venkataramana Shetty

198 G Hoshalli 49/2B K Shambhanna S/o Late Karigowda

Shivalingayya S/o 199 G Hoshalli 49/1A Shumbhulingayya

200 G Hoshalli 49 Surendhra S/o Shumbhulingayya

201 G Hoshalli 49/2A2 Puttaligamma W/o H B Ramayya

202 G Hoshalli 49/1B K N Dhrakshayani W/o Nanjayya

S Boregowda S/o Chikka 203 G Hoshalli 49/2A1 Boregowda

204 G Hoshalli 49/1A2 Raju S/o Shumbhulingayya

205 G Hoshalli 49/2A Gowramma W/o S Puttaswamy

T Thimmegowda S/o 206 G Hoshalli 49/1C Bhachappanna Thimmegowda

Kenchegowda S/o Kuntha Channi 207 G Hoshalli 49/1A Kempegowda

208 G Hoshalli 49/2B Nagamma W/o Marigowda 165

Betayya S/o Shambhayya U 209 G Hoshalli 49/1a Dollappa

210 G Hoshalli 49 Nanjegowda S/o Nanjegowda

211 G Hoshalli 49 Padhmamma W/o Omalingegowda

212 G Hoshalli 49 Chamayya S/o Shambulingayya

Ningegowda S/o Sunaganahalli 213 G Hoshalli 49 Ningegowda

214 G Hoshalli 71/E Lakshmamma W/o Ramalingayya 0.06 1.28 4.69

Shiva Basamma W/o B 215 G Hoshalli 71 Kempalingayya

Krishnagowda S/o Lingegowda U 216 G Hoshalli 52/4A,52/3A 0.38 3.02 12.58 Mhyadegowda

G T Thimmegowda S/o 217 G Hoshalli 52 Doddathimmegowda

Ramakrishnayya S/o Kempayyanna 218 G Hoshalli 52 Chikka kempegowda

219 G Hoshalli 52/4E T Puttaswamy S/o Thimmegowda

220 G Hoshalli 45/3A Nagamma W/o Marigowda 1.04 7.10 14.65

Shivalingegowda S/o Kalammana 221 G Hoshalli 45/3B Karigowda

Shambhuva U Kajarigowda S/o 222 G Hoshalli 45/3C,45/3D Karigowda

C H Kullegowda S/o Ningegowda U 223 G Hoshalli 45 Hottnegowda

Dodda Hydegowda S/o 224 G Hoshalli 45,71 Ningegowda U Hottnegowda

C M Thimmannagowda S/o 225 G Hoshalli 45/2B Mottegowda

226 Hallegere 40 C L Ramesha S/o Lingegowda 1.20 1.00 120.00

227 Hallegere 44/1 Chanamma W/o Chikkajogigowda 0.08 2.26 3.54

228 Hallegere 44/2 Chanamma W/o Chikkajogigowda

229 Hallegere 44/3 H J Borayya S/o Chikkajogigowda

166

230 Hallegere 44 H L Yashoda W/o H J Borayya

Nanjegowda S/o 231 Hallegere 51 0.06 1.18 5.08 Hanumanthegowda

232 Hallegere 51/2A Boramma W/o Kurisiddegowda

233 Hallegere 50 Graveyard 0.01 0.14 7.14 234 Hallegere 21 Kereanghalla 1.26 202.25 0.62

Siddegowda S/o Kullegowda U 235 Hallegere 9/3B 0.01 0.27 3.70 Bokkegowda

236 Hallegere 9/13,4/1A L S C S

237 Hallegere 8/1' H M Ramegowda S/o Muddegowda 1.02 2.10 48.57

238 Hallegere 8/3 M S C O 239 Hallegere 8/4,8/9,9/1 M S C O 240 Hallegere 8/5 H S Krishnegowda 241 Hallegere 8/6 M S Co 242 Hallegere 8/7 Marisiddegowda 243 Hallegere 8/11 H C Shivarama

P J Adilakshmi W/o Late H M 244 Hallegere 7,8/11,9/3A 0.00 1.16 0.00 Boregowda

Marigowda S/o Late Siddegowda U 245 Hallegere 27/1,38/2 0.05 1.00 5.00 Sannegowda

Rajegowda S/o Siddegowda U 246 Hallegere 27,38 Sannegowda

Boramma W/o H S 247 Hallegere 39/4B 0.06 10.20 0.59 Ramasubbegowda

Ramakrishna W/o 248 Hallegere 39/5A Puttachennegowda

H S Ramalingayya S/o Late 249 Hallegere 38/2,27/1 0.08 0.14 57.14 Siddegowda U Sannegowda

250 Hallegere 53/3 Gandegowda S/o Nanjegowda 0.01 0.01 100.00

251 Hallegere 4/5 V P Chairman 0.01 2.22 0.45

Late Siddegowda Kullegowda U 252 Hallegere 4/8A Bookagowda

253 Hallegere 4/8A Rathna W/o Ramakrishna

254 Hallegere 4/9,4/18 Jayamma W/o Chikkamarigowda

H C Vijayandhra S/o 255 Hallegere 4/9 Chikkasiddegowda

256 Hallegere 4/21 L S C S 167

Siddaraju My Ga Thaiyye 257 Hallegere 4/25A Chowdamma

H N shashikumara S/o Late 258 Hallegere 4/25C Siddegowda

259 Hallegere 4/26A Jagadisha S/o Late Siddegowda

260 Hallegere 4/26B,5/4,5/5 V P Halligere

261 Hallegere 4,5,6 H B Rajegowda S/o B Borayya

262 Hallegere 4/28A Jayappa S/o Doddajawaregowda

Shushilamma W/o Late H S 263 Hallegere 5/5K 0.07 1.02 6.86 Siddegowda

264 Hallegere 5/8,5/9A Grama panchayath 265 Hallegere 5/9A Karisiddegowda

Boregowda S/o Dhandana 266 Hallegere 5,9,4 Boregowda

267 Hallegere 6/1 Ramaswamy S/o Thamayya 0.11 1.07 10.28

Ningamma W/o Late Borayya U 268 Hallegere 6/6A,6/6 Doddaboregowda

H K Doddalingayya S/o Late 269 Hallegere ,6/12 Kempegowda

31/1B,31/3A3,31/ 270 Honaganahalli Jayarama S/o H K Chowdegowda 0.05 2.38 2.10 1A2,31/1A1

271 Honaganahalli 31/3A1 Ananda Thayi Savitramma

272 Honaganahalli 31/3A2 H C Shivaramu S/o Chowdaiah

H P Jayaramu S/o Panchaiah U 273 Honaganahalli 31/2-P Dollaiah

H B Krishnegowda S/o H M 274 Honaganahalli 31/2-P-p3 Boregowda

Sannammana Kalachowdegowda 275 Honaganahalli 30/1 0.01 0.27 3.70 S/o Chowdegowda

H M Puttaswamy S/o R I 276 Honaganahalli 30/5 Marijogigowda

277 Honaganahalli 30/7-p1 H C Puttaswamy S/o Chikkaiah

278 Honaganahalli 30/2B H C Nagaraju S/o Chowdaiah

279 Honaganahalli 29/2,29/3,29/4 Government 0.00 1.24 0.00

168

280 Honaganahalli 29/16 Lingaiah S/o Javanimuddaiah

H P Jagadeesha S/o H C 281 Honaganahalli 4/1,29/6 0.01 2.08 0.48 Puttegowda

41/5,4/1,30/8,112 H P Rajashekar S/o H C 282 Honaganahalli /-p3 Puttegowda

Chikkathayamma W/o Late H C 283 Honaganahalli 3/2 0.01 1.30 0.77 Puttegowda

284 Honaganahalli 3/1A Gramathana

285 Honaganahalli 112/-p4,112/-p1 PHC 0.09 62.17 0.14

286 Honaganahalli 94/1 Pankajamma W/o H Shyamanna 0.07 1.06 6.60

H P Nagaraja S/o Panchaiah U. 287 Honaganahalli 94/2 Dollaiah

288 Honaganahalli 94/3 H C Chowdaiah S/o H K Chikkanna

289 Honaganahalli 94/4,94/5 Thimmaiah S/o Bhukarithirumalaiah

290 Honaganahalli 101/1 Sumitramma W/o C N Acchutarao 0.00 0.10 0.00

291 Honaganahalli 105/1 Devamma W/o P. Chikkalingaiah 0.00 0.34 0.00

292 Honaganahalli 105/2 H T Javaregowda S/o Siddegowda

293 Honaganahalli 106/1,106/5 H S Raju S/o K Siddaiah 0.00 0.30 0.00

H Puttaswamy S/o 294 Honaganahalli 106/4 Doddatammegowda

295 Honaganahalli 107/1,107/2 H S Rajesh S/o K Siddaiah 0.01 1.02 0.98

Nityananda Mai. Ga. Thayi 296 Honaganahalli 107/3A Sarojamma

297 Honaganahalli 108/1 H T Javaregowda S/o Siddegowda 0.01 1.32 0.76

298 Honaganahalli 108/2,109/1 H C Shivarama S/o H C Chowdaiah

H S Kantharaju S/o Siddaiah U 299 Honaganahalli 109/4 0.01 0.10 10.00 Seethaiah

H T Poornima S/o D.. H L 300 Honaganahalli 110/1 0.00 2.08 0.00 Puttaswamy

H P Shantamma W/o Late N 301 Honaganahalli 110/2 Puttaiah

302 Honaganahalli 38/3 Kamalavva W/o Chowdayya 0.08 0.12 66.67 169

303 Honaganahalli 38/2A Jayarama S/oH K Chowdegowda

304 Honaganahalli 38/2A Ananda S/o Savithramma 305 Honaganahalli 39,38/1 Betnaboe S/o Kariyabhoee 0.02 1.00 2.00 306 Honaganahalli 40/A Vyramudi S/o Putnabhoyi 0.04 3.00 1.33 307 Honaganahalli 40/B Chaluvayya S/o bettabhoyi 308 Honaganahalli 40/1 Mariya S/o Puttnabhoyi

H P Manjunatha S/o Late H C 309 Honaganahalli 41/1,112,42 0.11 1.04 10.58 Puttnegowda

310 Honaganahalli 42/1 Jayamma W/o H P Shivalingayya 0.11 1.30 8.46

311 Honaganahalli 42,41,4,3 Kamalamma W/o Appajigowda

312 Honaganahalli 90/4 C Hemavathi W/o H S Raju 0.02 0.05 40.00

K Rajamma W/o Late H V 313 Honaganahalli 92,36,37 0.02 3.00 0.67 Thirumalayya

H C Sowbagya W/o H C 314 Honaganahalli 84 0.07 3.00 2.33 Chowdayya

315 Honaganahalli 84 H A Shruthi S/o Bagya 316 Honaganahalli 84,83/6 H T Ashoka

317 Honaganahalli 83/5 K P Shankarayya S/o Kempegowda 0.04 1.16 3.45

318 Honaganahalli 83/5B K M Nataraja S/o Late Manchayya

319 Honaganahalli 83/5B K Sathish S/o Myga Thayi Laxmi

320 Hulivana 389 D Krishna S/o Doddalingaia 0.02 1.00 2.00 321 Hulivana 415/-p1 Gomala 0.09 4.28 2.10 322 Hulivana 415/-p2 Somamma W/o Jogaiah

H S Shivaramu S/o 323 Hulivana 415/P-p2 Mishansingegowda

324 Hulivana 415/p3 Dollaiah S/o Kenchegowda

H B Manchaiah S/o Late Boraiah W 325 Hulivana 415/-p4 Motaiah

Bettaiah U Chikkaramu - S/o 326 Hulivana 415/-p6 Mishansingegowda

327 Hulivana 415/-p7 Jayamma W/o Dollaiah

H B Nagesh S/o Late Bettaiah U 328 Hulivana 395/2 0.05 0.28 17.86 Chikkaramu

Singarigowda S/o 329 Hulivana 395/3 Mishansingegowda

170

H C Ramachandra S/o Late 330 Hulivana 396 0.06 1.18 5.08 Chikkathammaiah

331 Hulivana 396 Bettegowda S/o Bettaiah

Shivarathnamma W/o H N 332 Hulivana 398/A 0.07 0.38 18.42 Siddappa

333 Hulivana 41/2 N A Kharab 0.06 0.36 16.67

41/15C,41/18,41/ Manchegowda S/o Kivudana 334 Hulivana 20B-p2 Manchaiah

41/20B- Byregowda S/o Kivudana 335 Hulivana p1,41/20A- Manchaiah p2,398/A-p2

336 Hulivana 24/2,24/3A Boraiah U Oranna S/o Madegowda 0.09 1.10 8.18

337 Hulivana 24/3A H M Suresha S/o Madegowda

Madegowda S/o Boraiah U. 338 Hulivana 24/4 Nathaiah

H M Puttaswamy S/o Madaiah U. 339 Hulivana 24/8 Chikkonu

340 Hulivana 24/9,24/10 Mangalagowri W/o H S Madegowda

341 Hulivana 23/1 Ramalingaiah S/o Lingaiah 0.03 2.03 1.48

Chikkalingaiah S/o 342 Hulivana 23/1 Chikkaputtegowda

343 Hulivana 23/1 C Lingappa S/o Chikkaputtegowda

344 Hulivana 23/1 Doddalingaiah S/o Dollaiah

345 Hulivana 23/2,23/3,23/5 Ramalingaiah S/o Lingaiah

346 Hulivana 23/2A Dolla S/o Lingegowda

Boraiah S/o Devaragudda 347 Hulivana 23/4 Madegowda

H B Manchaiah S/o Late Boraiah W 348 Hulivana 13/1B 0.00 2.02 0.00 Motaiah

349 Hulivana 13/1-p1 Boregowda S/o Byregowda

350 Hulivana 13/1-p2,14/1-p1 H M Boraiah S/o Kadimanjegowda

351 Hulivana 13/1P-p2 Muddalingu S/o Kurimanchaiah

352 Hulivana 13/1-p3 Mahadevu S/o Kurimanchaiah 171

353 Hulivana 13/1-p4 D Geetha W/o H S Shankaraiah

354 Hulivana 13/1-p5 Siddappa S/o Boregowda (Kadi)

Shivarathnamma W/o H S 355 Hulivana 13/1-p8 Shivaramu

Doddalingaiah S/o 356 Hulivana 13/1C Kadimanchegowda

Kalaiah U. Nathaiah S/o 357 Hulivana 13/1-p50 Kurisiddegowda

13/2A-p2,13/1A- Manchegowda S/o 358 Hulivana p1 Kadimanchegowda

359 Hulivana 14/1-P Boregowda S/o Byregowda 0.08 0.26 30.77 360 Hulivana 14/1-p3 Siddappa S/o Boregowda

Doddalingaiah S/o 361 Hulivana 14/3 Kadimanchegowda

Kalaiah U. Nathaiah S/o 362 Hulivana 14/1-p50 Kurisiddegowda

363 Hulivana 9 Graveyard 0.07 3.00 2.33 364 Hulivana 8/4-p1 C Latha W/o Ramalingaiah 0.04 0.14 28.57

365 Hulivana 8/4-p2 D Geetha W/o H S Shankaraiah

Shivarathnamma W/o H S 366 Hulivana 8/4-p3 Shivaramaiah

Shri Kalabaireshwara Education 367 Hulivana 6/-p2,6/-p1 0.02 1.16 1.72 Trust

368 Hulivana 351/9A-p1 Ningegowda S/o Muddegowda 0.03 0.35 8.57

369 Hulivana 351/12 Lohit S/o Nagaraja 370 Hulivana 351/17 N A Kharab

Ningegowda S/o 371 Hulivana 349/2A 0.01 0.05 20.00 Kovemanchegowda

372 Hulivana 349/2A H N Sudha W/o D Keshava

373 Hulivana 262/1 H D Ramesha S/o Kovedevaiah 0.00 1.09 0.00

374 Hulivana 262/1 Lingamma W/o H B Siddappa

H M Siddaiah S/o Dattu Thayi 375 Hulivana 262/2 Dhanavinahatti Devamma

376 Hulivana 262/3 H M Annapurna D/o Manchaiah

377 Hulivana 261/1 Siddaramaiah S/o Kalegowda 0.00 0.28 0.00

172

378 Hulivana 261/2 Muddaiah S/o Lingaiah 379 Hulivana 257/1 B Siddaiah S/o Byregowda 0.01 0.24 4.17

380 Hulivana 257/1 H S Marisiddappa S/o Siddegowda

260/2C- 381 Hulivana Ningegowda S/o Muddegowda 0.00 0.32 0.00 p1,260/2B-p1

H Byregowda S/o 382 Hulivana 60 0.09 0.34 26.47 Kovemanchegowda

383 Hulivana 60 Naganna S/o Manchegowda 384 Hulivana 39/1A,41/6 H N Siddappa S/o Borayya 0.00 4.22 0.00

H Madegowda S/o Kivudana 385 Hulivana 39/1C Manchegowda

386 Hulivana 39/1C Shivanna S/o Kivudana Manchayya

387 Hulivana 39/1C Ramesha S/o Kivudana Manchayya

388 Hulivana 39/2 H R Boregowda S/o H B Rajegowda

Borayya S/o Yammne Bornegowda 389 Hulivana 27/2A 0.05 1.37 3.65 Kalayya

Chikkaboregowda S/o Udupi 390 Hulivana 27/2B Chikkaboregowda

B Krishna S/o Borayya U 391 Hulivana 27/3,17/3A Allummegowda

Boregowda S/o Borayya U 392 Hulivana 27/5 allumegowda

Kadimanchegowda S/o 393 Hulivana 20/3 0.30 3.33 9.01 Manchegowda

394 Hulivana 20/3 Ningamma W/o Kuriborayya

395 Hulivana 20/3 Marisiddu S/o Sulleri Manchayya

H M Shivanna S/o Sulleri 396 Hulivana 20/3 Manchayya

Doddalingayya S/o 397 Hulivana 18/4B 0.02 1.02 1.96 Kadimanchegowda

Borayya U Mothayya S/o 398 Hulivana 18/4B2,14/2 Kadimanchegowda

Kadimanchegowda S/o 399 Hulivana 19 0.06 0.07 85.71 Manchegowda

400 Hulivana 14/1 Kadimanchegowda 0.08 1.10 7.27 173

H M Shivashankragowda S/o 401 Hulivana 14/1,18/4,13/1A Kadimanchegowda

402 Hulivana 2 Hospital 0.19 55.17 0.34 403 Hulivana 7 N A Karabu 0.00 1.20 0.00

H B Shivanna S/o Late Borayya U 404 Hulivana 254/1 0.00 0.07 0.00 Motayya

405 Hulivana 259 Jayarama S/o Dollegowda 0.08 0.38 21.05 406 keregodu 220 Lingegowda S/o Devegowda 0.09 3.04 2.96

407 keregodu 220213 Krishnegowda S/o Lingegowda

408 keregodu 220/7,220/9 K L Menakshi S/o Lingegowda

409 keregodu 220/14 K L Krishnegowda S/o Lingegowda

219/1,219/4,219/ 410 keregodu Marilingegowda S/o Marilingegowda 0.00 2.06 0.00 1A

411 keregodu 219/5 Siddegowda S/ Lingegowda

412 keregodu 216/4B Puttalingamma W/o Kendegowda 0.22 0.10 220.00

413 keregodu 214,226/1 T Anandha Lakshmi W/o Shivaji 0.06 1.00 6.00

414 keregodu 213/2,213/2 M Lingegowda S/o Lingegowda 0.10 3.32 3.01

415 keregodu 213/2C C Savitha W/o Kumar 416 keregodu 213219215 Ramesha S/o L Lingegowda 417 keregodu 213/5A Lingegowda 418 keregodu 231 Ramanna S/o Karigowda 0.07 3.36 2.08

419 Keregodu 145 Ramegowda S/o Chikkahydegowda 0.14 0.36 38.89

420 Keregodu 145 Ramagowda S/o Chikkahydegowda

421 Keregodu 856 C Nagaraju S/o Chikkalingegowda 0.05 3.36 1.49

Panchalingegowda S/o Lingegowda 422 Keregodu 8.56218E+11 Kallmante Doddi

423 Keregodu 216217218 Kumara S/o Karilingegowda 0.02 2.14 0.93

424 Keregodu 217/2,217/4 B Lingappa S/o Karilingegowda 0.13 2.06 6.31

425 Keregodu 215/4A Ningamma S/o Sanayya 0.12 1.00 12.00

426 Keregodu 215/5 K T Prakasha S/o Thamannagowda

174

427 Keregodu 215/5 K S Shivanna S/o Sannegowda

428 Keregodu 213216218 Sannegowda S/o Siddegowda 0.10 1.20 8.33

429 Keregodu 229 Puttalingamma S/o Manchegowda 0.00 0.00

430 Keregodu Krishnagowda S/o Hendegowda 0.00 0.00

431 Keregodu 145/-p1 Government Land 0.14 35.35 0.40

K H Ramegowda S/o 432 Keregodu 232/4 0.06 0.28 21.43 Hanumagowda

Shivalingegowda S/o Late 433 Keregodu 232/7,232/13-p2 Thammegowda

434 Keregodu 232/10 K Shivamma W/o Ramanna

435 Keregodu 232/20 Basavegowda S/o Marilingegowda

436 Keregodu 232/21 Lingegowda S/o Devegowda 437 Keregodu 232/27 Lingaraja S/o Karigowda

Chikkaramegowda S/o 438 Keregodu 234/1C 0.06 2.09 2.87 Chikkamugegowda

Shivalingaiah S/o 439 Keregodu 234/A-p2 Chikkamugegowda

440 Keregodu 234/1E-p-p1 Kumara S/o Karilingegowda 441 Keregodu 234/2B Channamma W/o Karigowda 442 Keregodu 234/3B1 Government Land

443 Keregodu 234/3C2 Shivalingegowda S/o Sannegowda

234/3D, 234/3E- 444 Keregodu Ramesha S/o Thammannagowda P1

445 Keregodu 237/1 Lingegowda S/o Kalegowda 0.08 1.25 6.40

446 Keregodu 237/2-p2, 237/5 M Lingegowda S/o Muddegowda

447 Keregodu 237/2-p3 Lingegowda S/o Lingegowda

Lingegowda B Motegowda S/o 448 Keregodu 237/4 Puttalingegowda

449 Keregodu 237/6-p1 Nagamma S/o Karilingegowda

450 Keregodu 237/6-p2 K L Puttaswami S/o Lingegowda

451 Keregodu 237/8 Kalingegowda S/o Kalingegowda

Chanumegowda S/o Late 452 Keregodu 237/9 Polisalingaiah 175

Lingamma U. Chikkatayamma W/o 453 Keregodu 237/10/A Chikkanna

454 Keregodu 237/10/B Lingamma W/o Marigowda

Lingegowda U. Motegowda S/o 455 Keregodu 237/11 Lingegowda U Nathegowda

456 Keregodu 313/1 Siddegowda S/o Chikkasiddegowda 0.01 2.04 0.49

457 Keregodu 313/2-P-p2 Puttaswamigowda S/o Siddegowda

Nataraja S/o Siddegowda U. 458 Keregodu 313/2-P-p5 Motegowda

Panchalingegowda S/o Lingegowda 459 Keregodu 189/1A 0.01 3.28 0.30 U. Karigowda

460 Keregodu 189/1A-p1 Shivalingegowda S/o Panchegowda

461 Keregodu 189/2A-p2 Ramegowda S/o Chikkalingegowda

462 Keregodu 189/1B-p1 Ningegowda S/o Ningegowda

Kivuda Lingegowda S/o 2 ne maga 463 Keregodu 189/1B-p2 Chennaiah

189/2A-p3, 464 Keregodu Lingegowda S/o Kempegowda 189/2B-p3

465 Keregodu 189/2A-p5 Shivalingegowda S/o Panchegowda

466 Keregodu 189/1Ee Lingegowda S/o Kempegowda

467 Keregodu 189/1E-p2 Lingegowda S/o Chamegowda

188/2-p2,188/1- 468 Keregodu Siddalingaiah S/o Siddegowda 0.03 4.14 0.72 p1,188/A

188/2-p1,188/1- 469 Keregodu S Shankar S/o Siddegowda p2

K V Vijayalakshmi W/o Late S 470 Keregodu 188/3 Lingegowda

471 Keregodu 188/1D Lingegowda S/o Lingegowda

472 Keregodu 186 Sumathi W/o K Maralingegowda 0.04 0.26 15.38

473 Keregodu 186/A,187/1A-p1 K Shivalingaiah S/o Chikkalingaiah

176

Puttaswamigowda S/o 474 Keregodu 186/P-p1 Chikkalingegowda

186/P,187/1A-P- K C Shivaramu S/o 475 Keregodu p3 Chikkalingegowda

476 Keregodu 187/3A Jayamma W/o L Puttaswamigowda 0.06 2.06 2.91

K Maralingegowda S/o Late 477 Keregodu 187/1B Kundegowda

478 Keregodu 187/3B L Shankaregowda S/o Lingegowda

Puttaswamigowda S/o 479 Keregodu 187/1A-P-p1 Chikkalingegowda

187/1A-P- Krishnegowda S/o 480 Keregodu p2,186/P-p2 Chikkalingegowda

481 Keregodu 185 Government Land 0.07 1.30 5.38 482 Keregodu 18/1P-p3 S Naganna S/o Shivalingaiah 0.01 1.24 0.81

A C Shankara S/o Late 483 Keregodu 18/2P Chikkalingaiah

484 Keregodu 18/6 Shivalingaiah S/o Channaiah 485 Keregodu 18/6-P M N Sudha D/o Shivalingaiah 486 Keregodu 18/8 Gowramma W/o Chandrappa

487 Keregodu 18/9 K C Yogesha S/o A Lingegowda

488 Keregodu 22/1-P,22/1-P-p5 Shivakumara S/o Madappa 0.07 4.24 1.65

22/1P- 489 Keregodu K M Mahadevaswami S/o Madappa p7,p3,p1,p4,p6

490 Keregodu 22/1P-p2,p8,p11 K Mahadevaswami

491 Keregodu 22/1P-p8 Marabasappa S/o Madappa 492 Keregodu 22/1P-p9 Annapurna W/o Shivananda

493 Keregodu 22/2A Jayamma W/o Puttaswamygowda L

494 Keregodu 22/2B Channamma W/o Lingegowda

495 Keregodu 22/2A Shanthamma W/o Mariyachari

496 Keregodu 22/2A-P Jayamma D/o Cheluvamma

497 Keregodu 22/2F-P Chennammanni W/o K Honnappa

498 Keregodu 22/2G-P Mariyachari S/o Narasachari 177

499 Keregodu 22/3-p2 PWD 500 Keregodu 22/3-p3 Hospital

Padmavathamma W/o Late K 501 Keregodu 22/3-p4 Gopalrao

502 Keregodu 2/16P-p1 K M Shivaram S/o M Munigowda 0.06 0.17 35.29

2/4,2/3A-p1,2/3A- M P Shankaralingu S/o M L 503 Keregodu p2 Panchegowda

P Sureshkumara S/o L 504 Keregodu 630/A-p1 0.08 1.00 8.00 Puttaswamygowda

K C Somegowda S/o C 505 Keregodu 645/2 0.03 0.33 9.09 Chikkalingegowda

506 Keregodu 645/3-p1 N Veerabadrappa

507 Keregodu 645/3-p2 K V Nagaraju S/o Veerabadrappa

645/5A,5B,5C,63 508 Keregodu Krishnegowda S/o Marigowda 5/1C

509 Keregodu 642/1 K Anantharamaiah S/o Surappa 0.06 0.30 20.00

510 Keregodu 642/4 Lingegowda S/o A Lingegowda

511 Keregodu 642/4 K P Prabhudeva S/o Panchegowda

512 Keregodu 675 Hullu binni 0.06 0.16 37.50 513 Keregodu 663/1 Siddalingaiah S/o Maradibora 0.05 1.38 3.62

K P Prabhudeva S/o K 514 Keregodu 663/2 Panchegowda

515 Keregodu 663/3 Mahadevaswamy S/o Madappa

516 Keregodu 663/3B,663/5 Sakamma W/o Marigowda

K M Ravikumara S/o k 517 Keregodu 663/6,663/4/1 Mariswamygowda

518 Keregodu 663/5 Sakamma W/o Marigowda 519 Keregodu 645/4 Shri Kotedariswamy Temple 0.00 0.21 0.00

520 Keregodu 645/5B Krishnegowda S/o Marigowda

521 Keregodu 665/2 M L Panchegowda S/o Lingegowda 0.02 0.28 7.14

522 Keregodu 665/5 H C Shivanna S/o Chikkegowda

Chikkegowda S/o Chikkegowda U. 523 Keregodu 665/8 Hottegowda

178

524 Keregodu 711 Jayamma W/o Muddegowda 0.01 1.00 1.00 525 Keregodu 711/13-p4 Shivanna S/o Thimmegowda

526 Keregodu 711/17 H C Prashurama S/o Chekkegowda

H S Avinash Mai Ga Thayi B N 527 Keregodu 711/17 Sarojamma

528 Keregodu 711/17 H C Prashiva S/o Chekkegowda

529 Keregodu 711/19-p2 H Puttaswamy S/o Lingegowda

711/19- 530 Keregodu M C Shivanna S/o Karigowda p1,711/20A-p2

Chikkegowda S/o Jopani 531 Keregodu 711/20C Lingegowda

532 Keregodu 711/20D Hucchegowda S/o Halavegowda

533 Keregodu 711/21 Shivanna S/o Thimmegowda

534 Keregodu 711/21 Prakasha Mai. Ga. Thayi Jayamma

535 Keregodu 711/22 Sarojamma W/o Thammegowda

Panchaligegowda S/o Late 536 Keregodu 711/23 Lingegowda

537 Keregodu 705/2A Thammaiah S/o Modegowda 0.12 1.04 11.54

538 Keregodu 705/2A M L Pancha S/o Bundegowda

539 Keregodu 705/3 Karilingegowda S/o Honnegowda

M P Krishnegowda S/o M R 540 Keregodu 705/7E Panchegowda

541 Keregodu 705/7E-P Veena W/o Ravi Maralingadoddi

542 Keregodu 705/7E Susheelamma W/o Swamychari

543 Keregodu 705/7-p2 Shankaregowda S/o Bunegowda

544 Keregodu 705/8 M Boraiah S/o Kalegowda

Chowdamma W/o Chandagalu 545 Keregodu 705/9 Siddaiah

546 Keregodu 705/11A-p1 Lingamma W/o Thammaiah 179

T Panchalingaiah S/o 547 Keregodu 704/4 0.09 1.00 9.00 Thimmegowda

548 Keregodu 704/4P-p1 T Shivanna S/o Thammegowda

M C Basavaraju S/o Late 549 Keregodu 704/9,704/15 Chikkegowda

550 Keregodu 704/16 Karigowda S/o Hottechikkegowda

551 Keregodu 702,704/5 M L Shivaraju S/o Lingegowda 0.02 1.08 1.85

M L Shivalingegowda S/o 552 Keregodu 702,704/5 Lingegowda A Jongegowda

553 Keregodu 678/2E L Ramalingegowda S/o Lingegowda 0.01 0.15 6.67

H C Lalithamma W/o M L 554 Keregodu 678/2A,678/3A Panchegowda

555 Keregodu 628/6 L Shankaragowda S/o Lingegowda 0.24 0.22 109.09

Lingegowda S/o 556 Keregodu 674/5-p2 0.16 0.37 43.24 Busigowdnalingegowda

Lingegowda S/o Karichikka 557 Keregodu 674/9 Muddegowda

558 Keregodu 674/15 Shivarathnamma W/o H B Nagaraju

M J Panchalingegowda S/o 559 Keregodu 674/14 Javaregowda

560 Keregodu 680/-p1 Ramegowda S/o Byrappagowda 1.28 2.20 58.18

561 Keregodu 680/-p13 C Lingegowda S/o Chikkagowda

562 Keregodu 680/-p2-p1 Panchalingeshwara Temple & PHC

M J Panchalingegowda S/o 563 Keregodu 680/-p20 Javaregowda

980/- 564 Keregodu Sannamma W/o Chikkegowda 0.00 0.26 0.00 p19,711/20B

565 Keregodu 691/1 C Muddaiah S/o Chikkegowda 0.16 4.06 3.94

566 Keregodu 691/1 Dharmaja S/o Siddegowda

567 Keregodu 691/6 C Muddaiah S/o Chikkegowda

180

568 Keregodu 691/6 Thayamma W/o Late Siddegowda

569 Keregodu 691/9B,691/4 H C Shivanna S/o Chkkegowda

570 Keregodu 232/5 Krishna gowda S/o Lingegowda 0.07 1.12 6.25

571 Keregodu 232/5 Linge gowda S/o Devegowda

K C Peashantha babu S/o H 572 Keregodu 232/9 Chikkalingegowda

573 Keregodu 232/17 Lingamma W/o Late Lingegowda

574 Keregodu 234/2A Sannegowda S/o Sannegowda 0.06 0.05 120.00 575 Keregodu 234/3E Chikka puttegowda 576 Keregodu 239 Hullakatte 0.05 0.28 17.86 577 Keregodu 238/3-P1 Lingegowda S/o Kallegowda 0.01 1.14 0.88 578 Keregodu 238/1,238/1 Lingegowda S/o Kallegowda

579 Keregodu 254/1 K L Ramalingayya S/o Lingegowda 0.01 1.23 0.81

580 Keregodu 254/1 K L Ramalingayya S/o Lingegowda

K B Mahalingegowda S/o Late 581 Keregodu 254/2 Basavegowda

582 Keregodu 254/2 K Shivalingayya S/o Karigowda

583 Keregodu 255/3 M Lingegowda S/o Muddegowda 0.02 0.25 8.00

584 Keregodu 255/4 Shivarama S/o Lingegowda

K L Channakeshava S/o 585 Keregodu 255/4 Lingegowda

P Lingegowda U Bojegowda S/o 586 Keregodu 256/1 0.07 1.28 5.47 Panchegowda

K L Ramakrishnegowda S/o Appaji 587 Keregodu 256/2 gowda

588 Keregodu 256/D Channamma W/o Bettalingegowda

589 Keregodu 256/4D C Nagaraja S/o chikka nathegowda

590 Keregodu 256/4D Manchamma W/o P Krishnegowda

591 Keregodu 256/4D Chandra S/o Boregowda

H Chikkalingegowda S/o 592 Keregodu 193/1 0.01 2.29 0.44 Mollegowda 181

593 Keregodu 193122 M Sudha S/o Manchegowda

K Shivanna S/o Guligowda U 594 Keregodu 193 Thammegowda

Thammana gowda S/o Guligowda U 595 Keregodu 193 Thammegowda

596 Keregodu 193/2 K Krishnagowda S/o Kendegowda

597 Keregodu 193/2B Sanayya S/o Gendegowda

598 Keregodu 193/E Puttalingamma W/o K Lingegowda

599 Keregodu 193/2 K Krishnagowda S/o Kendegowda

Shivarama S/o Chikka Puttnegowda 600 Keregodu 193/2E Guligowda

Shankaregowda S/o hikka 601 Keregodu 193/2E Puttnegowda Guligowda

602 Keregodu 193/2E Puttalingamma W/o K Lingegowda

603 Keregodu 193/3 Kariyappa S/o Chikanna

604 Keregodu 193/3B Balashankara S/o Manchegowda

605 Keregodu 193/22,193/2-P3 K S Shivanna S/o Sannegowda

606 Keregodu 329 Govt Land 0.03 0.26 11.54

A L Umesha S/o Lingayya U 607 Keregodu 330/5A 0.04 1.14 3.51 Bokappa

D Naganna S/o Late Lingayya U 608 Keregodu 330 Dodda thamayya

K S Nagandraprasad S/o K 609 Keregodu 330/8 Shivaramegowda

610 Keregodu 331 Govt Land 0.00 1.28 0.00 611 Keregodu 331/-P2 Guest house 612 Keregodu 16 Shivananda S/o Muddappa 0.00 7.26 0.00

613 Keregodu 16/1B2 M Shivanna S/o M Mahadevappa

614 Keregodu 16/1 Basamanne W/o Puttaswamayya

615 Keregodu 16/1B2 M Putanna S/o M Mahadevappa

616 Keregodu 16 K C Boregowda S/o Channegowda

182

K Gopalkrishnachar S/o K 617 Keregodu 16 Subrayachar

618 Keregodu 16/2A Sarojamma W/o K M Shivanna

Madhu gopalashetty S/o Thabala 619 Keregodu 16/2 Ninga sheety

620 Keregodu 16/2 Mallamma W/o Shivarudrappa

621 Keregodu 16/2 Mahadevayya S/o Ganganna

622 Keregodu 16/2 K P Nagaraju S/o S Veerabadrappa

623 Keregodu 16/2 K V Nagaraju S/o S Veerabadrappa

624 Keregodu 16/4 Linga shetty S/o Lingappa

625 Keregodu 16/5 K L Annaswamy S/o Lingappa

626 Keregodu 16/6 Govt Land 627 Keregodu 16/6,22/3 Govt Land 628 Keregodu 16/6 Lingappa S/o Annegowda

K C Gangadara S/o Late C 629 Keregodu 16/9 Chikkalingegowda

630 Keregodu 16/10 Sudha W/o P Panchegowda

631 Keregodu 16/10 K L Nagaraju S/o S Veerabadrappa

P Veeragowda S/o 632 Keregodu 16/11 Doodannegowda

633 Keregodu 14/A L Shankaregowda S/o Lingegowda 0.00 1.36 0.00

634 Keregodu 14 K M Jayarama S/o Munigowda

635 Keregodu 14 K Ravi S/o Late Krishnegowda

636 Keregodu 3/1,3/16 Road 0.10 3.18 3.14 637 Keregodu 3/2 Booswadhindikari

Lingegowda S/o Kagge 638 Keregodu 3/3 Panchegowda

C S Vijayamma W/o 639 Keregodu 3/3 Shankaregowda

640 Keregodu 3/4,3/5 K M Ramakrishnegowda

K L Panchalinga S/o Late 641 Keregodu 3/5,3/4 Lingegowda 183

642 Keregodu 3/4 P Raja laxmi W/o K Thammegowda

643 Keregodu 3/4 C B Puttasway S/o Borayya

Lingegowda S/o Minne 644 Keregodu 3/4 Panchegowda

Lingegowda U Mottegowda S/o 645 Keregodu 3/5,3/3A Hottelingegowda

646 Keregodu 3/6 K Panchegowda S/o Annegowda

647 Keregodu 3/7 Meenakshi W/o Lingegowda

Chanamma W/o 648 Keregodu 3/7A Chikkamuddegowda

Krishna gowda C S/o 649 Keregodu 3/7A,628/3B Chikkamuddegowda

K L krishna S/o Lingegowda U 650 Keregodu 3/7A3 Dodda mugegowda

651 Keregodu 3/8,3/3,3/E K Thammegowda S/o Annegowda

652 Keregodu 3/9 K Lingegowda S/o Muddegowda

K S Ragunandana S/o 653 Keregodu 3/9A Shankaregowda

654 Keregodu 3/9 Annegowda S/o Lingegowda

655 Keregodu 3/11-P1 B Puttaswamy S/o Basavachari

656 Keregodu 3/12A Kalingayya S/o Muddegowda

K C Prabha W/o Late K N 657 Keregodu 3/13 Shivaramu

K B Jagadisha S/o Late 658 Keregodu 3/13 Buyyegowda

659 Keregodu 3/14A,3/14E K Shashidara S/o A Annegowda

660 Keregodu 3/15A T S Sushila W/o K Shivaramu

661 Keregodu 627 T L Bagya S/o T K Lingegowda 0.01 0.22 4.55

662 Keregodu 635/1C Krishnegowda S/o Marigowda 0.14 0.25 56.00

Chikka Karigowda S/o 663 Keregodu 635/1D Chikkaydegowda

664 Keregodu 635/3,635/2A Annegowda S/o Doddalingagowda

184

665 Keregodu 641/2 Veerabadrappa S/o K V Nagaraju 0.05 1.29 3.88

666 Keregodu 641/2,641/1 K V Nagaraju S/o S Veerabadrappa

K P Prabhudeva S/o K 667 Keregodu 641/3,641/4 Kenchegowda

668 Keregodu 641/4 Mudamma W/o Lingegowda 669 Keregodu 664/2 Shivamma W/o Marichikayya 0.02 0.35 5.71 670 Keregodu 664/2 C Nagalingayya S/o Chikayya 671 Keregodu 664/3 K Basayya 672 Keregodu 664/4 Kalamma

S Manchegowda S/o K Siddegowda 673 Keregodu 664/5 Maralinganadoodi

674 Keregodu 665/6 Lingamma W/o Thamayya 0.02 0.20 10.00

Lingegowda S/o Chikkegowda U 675 Keregodu 665/9,665/7 Nagegowda

K Shankare gowda S/o 676 Keregodu 665/10B Kenchegowda

677 Keregodu 709/4 Basavegowda S/o Pothaigowda 0.01 0.02 50.00

678 Keregodu 706/1A Narasimhachari 0.03 0.05 60.00 679 Keregodu 706/4A Ningamma W/o Bettegowda

680 Keregodu 676/1 Sannegowda S/o Kenchegowda 0.14 1.37 10.22

681 Keregodu 676/4 L Ramalingegowda S/o Lingegowda

682 Keregodu 676/4 M L Nagaraju S/o Lingegowda

J Panchalingegowda S/o 683 Keregodu 676/5B4 Javaregowda

684 Keregodu 676/5A M Borayya S/o Kalegowda 685 Keregodu 676/5B

M J Panchalingegowda S/o 686 Keregodu 676/6 Javaregowda

M J Panchalingegowda S/o 687 Keregodu 676/7 Javaregowda

Panchalingegowda S/o 688 Keregodu 701/3 0.06 0.32 18.75 Lingegowda

689 Keregodu 701/6 Sannegowda W/o Muddegowda 185

J Panchalingegowda S/o 690 Keregodu 678/1A 0.01 1.11 0.90 Javaregowda

691 Keregodu 678/1A2 C Chikkegowda S/o Ckikkegowda

692 Keregodu 678/1B Karilingegowda S/o Honnegowda

693 Keregodu 678/2 M L Nagaraju S/o Lingegowda

694 Keregodu 678/3A L Ramalingegowda S/o Lingegowda

K B Krishnegowda S/o 695 Kommerahalli 13/1A2 0.04 0.10 40.00 Chowdegowda

696 Kommerahalli 12/2A Gopalaiah S/o B Boraiah 4.36 1.14 382.46

697 Kommerahalli 12/2B Narasimhamurthy S/o Manchaiah

698 Kommerahalli 12/1A2-p1 K B Papegowda S/o Boregowda

699 Kommerahalli 3/-p1 Narasimhamurthy S/o Manchaiah 0.16 0.26 61.54

700 Kommerahalli 3/-P2 Srinivasa S/o K S Narasimhaiah

701 Kommerahalli 181 Government Land 0.17 26.10 0.65

702 Kommerahalli 122/3 Nityananda Mai. Ga. Sarojamma 0.14 3.18 4.40

703 Kommerahalli 122/5,6,7,8,9,10 Ashraya Yojane

704 Kommerahalli 122/11 K B Krishna S/o Boregowda

705 Kommerahalli 122/12 Kamalamma W/o Late Gurunatha

122/1A,1C,2C,2A 706 Kommerahalli Ashrama -p1,2A-p2

707 Kommerahalli 116/1Aa-P Annegowda S/o Manchaiah 0.28 2.26 12.39

116/1Aa-P- p1,116/1Aa- 708 Kommerahalli K S Vedhavathi W/o S K Srinivasa p1,116/1Ba1- p2,116/1Ba1-p3

116/1Aa- Puttanarasamma W/o 709 Kommerahalli p2,116/1Aa/Aa- Chennahegde U. Guppahegde p2

186

116/2BaP- 710 Kommerahalli Swamy S/o Kambaiah p1,116/2Ba1P-p2

116/1AaP- 711 Kommerahalli Chikkaramu S/o Mastichennahegde p1,116/2A4-p1

712 Kommerahalli 116/1AaP-p2 Yashoda W/o Boregowda

P Doddahucchaiah S/o 713 Kommerahalli 116/1Ba/P-p3 Doddahucchahegde

S J Shivaramu S/o Masti 714 Kommerahalli 116/1AaP-p4 Jayarayahegde

116/1AaP- 715 Kommerahalli Kariyappa S/o Guddaiah p5,116/1AaP-p3

716 Kommerahalli 116/1AaP-p7 S Manchegowda S/o Siddaiah

717 Kommerahalli 116/2A-p9 Rangappa S/o Late Dasappa 718 Kommerahalli 116/2A3/2 P S Puttaiah S/o Puttegowda

116/2A1,116/1Ba ,116/2A- 719 Kommerahalli Government Gramathana p1,116/2A- p2,116/2A3/4

720 Kommerahalli 19/A K C Krishna S/o Chowdegowda 0.03 1.36 2.21

721 Kommerahalli 19/B K B Appaji S/o Boregowda 722 Kommerahalli 19/B K B Shivanna S/o Boregowda 723 Kommerahalli 19/B K B Ravikumara 724 Kommerahalli 19/B K B Krishna S/o Boregowda 725 Kommerahalli 18/1 Puttalingamma W/o Sanayya 0.03 2.13 1.41

Doddathayamma U Chowdayya 726 Kommerahalli 18/1 W/o Choudagowda

Ramalingayya S/o 727 Kommerahalli 18/11 Ningegowda

Puttamma W/o Late Marigowda, 728 Kommerahalli 18/2B Kariputtaiah

729 Kommerahalli 18/2C Kulayya U Sothayya 730 Kommerahalli 18/C3 M Shankara S/o Dollegowda

Sannegowda S/o Dyavana gudanna 731 Kommerahalli 18/2A1 Chowdegowda 187

732 Kommerahalli 18/2A2 Ningamma W/o Late K C nagaraju

Chowdayya S/o Dyavaragowda 733 Kommerahalli 18/2C4 Karigowda

K C Krishnegowda S/o 734 Kommerahalli 12/1A 0.14 0.28 50.00 Chowdegowda

735 Kommerahalli 4/1A Puttaboramma W/o chowdegowda 0.01 5.13 0.19

736 Kommerahalli 4/1B Borayya S/o Kenchegowda

737 Kommerahalli 4/1C Giriyamma W/o Annappagowda

738 Kommerahalli 4/1D Shivarathnamma W/o Sanappa

S K Shivaprakasha S/o 739 Kommerahalli 4/3B Chikkakariyappa

740 Kommerahalli 4/3C Vijaya S/o Gudhayya 741 Kommerahalli 120 Devara inam 0.05 1.08 4.63

742 Kommerahalli 119 Narasimamurthy S/o Manchayya 0.01 0.12 8.33

743 Kommerahalli 117/14 K Putayya S/o Manchegowda 0.00 6.19 0.00 744 Kommerahalli 117/1B Prema W/o Late Subramanya 745 Kommerahalli 117/1C Revamma W/o Ramayya

746 Kommerahalli 117/1A,117/1F T Shivanna S/o Thamayya

747 Kommerahalli 117 K V Nagaraju S/o Eregowda

748 Kommerahalli 117/2A A Manjunatha S/o Late K Annayya

749 Kommerahalli 117/2B K B Appaji S/o Boregowda 750 Kommerahalli 117/2B K B Shivanna S/o Boregowda

751 Kommerahalli 117/2B K B Ravikumara S/o Boregowda

752 Kommerahalli 117/2B K B Krishna S/o Boregowda

753 Kommerahalli 115/1 Srinivasa S/o K S Narasimayya 0.08 2.31 3.46

Chandrashekarayya S/o 754 Kommerahalli 115/2 Manchayya

755 Kommerahalli 115/3 Narasimmurthy S/o Manchayya

756 Mandya 561/2 Nanjamma W/o Police Boregowda 0.07 0.20 35.00

188

548/1,548/2A,548 1ne Ramaiah U. Doddaida S/o 757 Mandya 0.24 2.24 10.71 /2B,548/3-p1 Maralliramaiah

758 Mandya 548/1A 3ne Boraiah S/o Maralliramaiah

759 Mandya 548/7 Rajkumara S/o Mahendrapal

Ningappa S/o Ningappana 760 Mandya 548/7 Ramegowda

761 Mandya 548/7 G V Kempagulaiah S/o Veeraiah

Chikkalingaiah S/o 762 Mandya 548/5A Bodaregoregowda

763 Mandya 548/8C Susheelamma W/o Late Naganna

764 Mandya 548/9 Kalamma Temple

Ramaiah S/o Late 765 Mandya 548/5B-p1 Bodareboregowda

766 Mandya 548/6A-p2 S P Shivananjappa S/o K Puttaiah

767 Mandya 548/6A-p3 Kamalamma W/o Shivalingaiah

Ramaiah S/o Late Kullaiah U. 768 Mandya 548/8Aa-p2 Ramaiah

769 Mandya 548/8Ae-p2 Shivarama S/o Ramaiah U. Sottaiah

770 Mandya 550/4P Ramanna S/o Late B Lingaiah 0.07 0.06 116.67

771 Mandya 507/p1 Government 0.34 121.87 0.28 772 Mandya 507/p1 Revenue Department

Maniben Arjun Patel C/d Valji Khanji 773 Mandya 507/p1 Patel

774 Mandya 507/p1 Khim G H Patel B/o Lalji Hirji Patel

775 Mandya 507 KHB

776 Mandya 698/3P,698/4B Hyamaiah S/o Varadegowda 0.00 0.20 0.00

777 Mandya 780/1 Chennamma W/o Andanigowda 0.06 0.03 200.00

778 Mandya 784,784/A Ningamma W/o Ningaiah 0.01 0.11 9.09

M B Ashwathnarayana S/o M 779 Mandya 784/A Basavaiah

780 Mandya 784 Puttaswamy S/o Boraiah 189

781 Mandya 561 Putamma W/o Doddabasavegowda 0.07 1.14 6.14

782 Mandya 561/A Graveyard 783 Mandya 549/1 Kallamanna Temple 0.14 3.02 4.64

784 Mandya 549550 C R Siddaramayya S/o Ramegowda

Kamalamma W/o Doddabusi 785 Mandya 549/3 gowdna Siddegowda

786 Mandya 549/3 K Naganna S/o Kadegowda 787 Mandya 549/4B Sarojamma W/o Ramu

Mahendhra kumar S/o C R 788 Mandya 550/5 0.07 0.28 25.00 Shivalingayya

789 Mandya 565 Mudigowda S/o Chanayya 0.01 0.20 5.00 790 Mandya 581/2C Swamy Myga Jayadevayya 0.23 2.22 10.36

C J Pradeep kumar S/o Late 791 Mandya 581/1 Jaykumar

C B Shankaregowda S/o C B 792 Mandya 581/1 Borayya

793 Mandya 581/2E,581/2D Jayadevayya S/o Doddedevegowda

C S Shivaramu S/o Late Poojari 794 Mandya 693 0.01 2.16 0.46 Siddaramayya

Shivasankar S/o Late Poojari 795 Mandya 693 Siddaramayya

M R Ashokananda S/o M K 796 Mandya 694/2,694/3 0.17 2.26 7.52 Ramalingegowda

M S Nithyananda S/o M K 797 Mandya 694/1A,694/1B shivananjappa

798 Mandya 695/1 Boregowda S/o Manchegowda 0.15 1.25 12.00

799 Mandya 695/3 Hy Munisa W/o Noorkhan M

800 Mandya 695/2 Gowramma W/o Late C K Devayya

801 Mandya 695/2 Chikkadevayya S/o Karigowda

802 Mandya 696 Hy Munisa W/o Noorkhan M 0.00 1.20 0.00 803 Mandya 698/2 Hy Munisa W/o Noorkhan M 0.00 1.22 0.00

804 Mandya 698/4A,698/3A Rajanna

Madhusudhana U Mahadeva Myga 805 Mandya 698/4C Thayi Bagyamma

190

Varadegowda S/o Dymnegowdna 806 Mandya 699 0.00 1.16 0.00 Kalegowda

807 Mandya 699698 Somashekara S/o Late Hemayya

808 Mandya 700 M B Ramesha S/o M H Borayya 0.03 1.14 2.63

809 Mandya 700 M B Ramesha S/o M H Borayya

810 Mandya 701/1 M L Prakasha S/o M C Lingayya 0.05 1.12 4.46

Chandrushekarayya S/o M C 811 Mandya 701/2 Lingayya

812 Mandya 744/1 Kempamma W/o M C Lingayya 0.13 1.10 11.82

813 Mandya 744/2 M D Swamy S/o Late Dollegowda

814 Mandya 745/3,745/4 M D Swamy S/o Late Dollegowda 0.04 0.19 21.05

Channegowda S/o 815 Mandya 745/2 Chikkathammaya

Channegowda S/o 816 Mandya 747/1 0.21 1.00 21.00 Chikkathammaya

817 Mandya 747/2 M S ko

M S Athmananda S/o M K 818 Mandya 748 0.16 0.34 47.06 Shivananjappa

819 Mandya 749/1 Lilamma W/o M K Shivananjappa 0.04 0.26 15.38

820 Mandya 749/2 A C Ravikirana S/o A C Chowdayya

A C Chandrashekarayya S/o Late A 821 Mandya 749/5 C Chowdayya

Shanthamma W/o Late M S 822 Mandya 749/6 Shivappa

823 Mandya 781/1 Boramma W/o Siddimanchayya 0.00 1.20 0.00

824 Mandya 781/1A,781/2Ac Doreraju S/o Basavayya

C Siddaramaiah S/o 825 S I Kodihalli 10/2A 0.01 0.30 3.33 Hanchahalliboregowdnachannaiah

K B Channegowda S/o 826 S I Kodihalli 10/2B Hanchahalliboraiah 191

K C Puttaswamy S/o 827 S I Kodihalli 10/2C Hanchallibornachennaiah

K S Boraiah S/o Boraiah U 828 S I Kodihalli 11/1-p1,20/1 0.00 3.02 0.00 Chikaidegowda

Siddaiah U Nathaiah S/o 829 S I Kodihalli 11/2,10/2D,20/2B Ratesiddegowda

830 S I Kodihalli 11/3A Government Land

831 S I Kodihalli 20/Aa K Boregowda S/o Late Kariyappa 0.06 1.04 5.77

832 S I Kodihalli 20/3 Chennamma W/o Kemporaiah

Kempaiah S/o Jogigowda U. 833 S I Kodihalli 21/1A-p1,21/1 0.14 4.17 3.36 Lingegowda

834 S I Kodihalli 21/1A-p2 Kempaiah S/o Jogigowda

L Channaiah S/o Jogigowda U 835 S I Kodihalli 21/1B,21/1C Lingegowda

Siddalingaiah S/o Jogigowda U. 836 S I Kodihalli 21/1D Lingegowda

21/2,21/3- 837 S I Kodihalli p5021/5-p2,21/5- Boramma W/o Chikkaputtaiah p3

K N Devarajubabu S/o K N 838 S I Kodihalli 21/2A-p1 Nagaraju

H B Shivanna S/o Boraiah U 839 S I Kodihalli 21/2A-p2,21/2A Motaiah

21/3-p1,21/4- 840 S I Kodihalli B Barat S/o Late Boraiah p3,21/5-p1

841 S I Kodihalli 21/3-p2 Boramma W/o Jogaiah 842 S I Kodihalli 21/A-p1 K L Shivanna S/o Lingaiah

21/4-p4,21/4- 843 S I Kodihalli Sarojamma W/o B Siddaiah p5,21/4-p2

844 S I Kodihalli 23 Channamma W/o Kemporaiah 0.06 1.02 5.88

845 S I Kodihalli 23/1 Boramma W/o Jogaiah 846 S I Kodihalli 22 B Bharatha S/o Late Borayya 0.11 1.00 11.00

847 S I Kodihalli 22 Boramma W/o Chikkaputayya

848 S I Kodihalli 22 Chanamma W/o Kemporayya 849 S I Kodihalli 22 Boramma W/o Jogayya 850 Sathanuru 35/4A V Venkataiah S/o Boraiah 0.02 0.38 5.26

851 Sathanuru 36/A S Vijay S/o Late T Shankaraiah 0.04 1.14 3.51

192

852 Sathanuru 37/AP-p1 S K Lakkappa S/o Kempalakkaiah 0.02 0.03 66.67

853 Sathanuru 41/1A,41/2B-p1 Shivanna S/o Chikkaningaiah 0.01 0.28 3.57

854 Sathanuru 41/1A,41/2B-p1 Lakshmma W/o Ramegowda

10/2P-p1,10/2P- 855 Sathanuru Rathnamma W/o Puttaiah 0.03 3.17 0.95 p2,10/5

10/3A,10/4A,10/4 856 Sathanuru S Ramakrishna S/o Siddaiah B

857 Sathanuru 10/2 Padma D/o Annegowda 858 Sathanuru 9/A Gramathana 0.01 1.12 0.89

S M Ramakrishna S/o Late 859 Sathanuru 8/1A,8/2,8/1B 0.00 1.26 0.00 Manchegowda

860 Sathanuru 5/2 Chikkaboramma W/o Eeri Bojjaiah 0.00 0.12 0.00

861 Sathanuru 42 Govt 0.00 5.14 0.00 862 Sathanuru 7/3 S K Shivaprakasha 0.03 0.32 9.38

863 Sathanuru 7/1A Nagarajachari s/o Chikkabettachari

864 Sathanuru 7/1A1 Govindhachari S/o Chikkabettachari

865 Sathanuru 7/2E,7/2E S N Narasayya S/o S N Narasayya

866 Sathanuru 1/1 Venkatayya B S/o Boregowda 0.03 0.29 10.34

867 Sathanuru 1/2 Jayalakshmamma W/o Krishna S L

868 Sathanuru 6/1,6/2 Chandra mohan S/o Siddayya 0.00 2.11 0.00 869 Sathanuru 6/1,6/2 Chikanna S/o Kempegowda

Naganarasimhegowda S/o 870 Sathanuru 6/1,6/2 Motegowda

871 Sathanuru 6/6 Chikanna S/o Kempayya 872 Sathanuru 6/9 Mahesh S/o Kalayya 873 Sathanuru 6/7A Mahesh S/o Kalayya

874 Sathanuru 6/7A S Nandibasappa S/o N shankappa

875 Sathanuru 6/7A T Thanuja W/o Nagesh

876 Sathanuru 6/7A Manchamma W/o Sheshegowda 193

Rathnamma W/o Late S T 877 Sathanuru 6/7A Ramalingayya

878 Sathanuru 6/7B P Mahesh S/o Late Parvathayya

879 Sathanuru 6/7B P Ananda S/o late Parvathayya

Nagarathnamma W/o 880 Sathanuru 6/7B Shambhulingayya

881 Sathanuru 6/7BC,6/8 Sheshegowda S/o Borayya

882 Sathanuru 6/7B S T Ramalingayya S/o Thamayya

883 Sathanuru 37414 S Narasayya S/o Narasahegede 0.00 0.11 0.00

194

Annex 5: Structure Details

DHs Structure details of link 57A (Gubbi - Beeragonahalli near Yediur (NH-48) ` Str. % of Total Affecte Str. Sl. Chain Occu. Loss Structu Str. Area Side Village Name d Area Getting No. age Status Type re Type (in (in Affecte Sq.m) Sq.m) d

Venkata Hanumaiah Cattle 1 0.565 RHS Gubbi S/o Owner Pucca 16.00 32.00 50.00 Shed Venkataramanappa

Rajanna S/o Commer 2 0.675 LHS Gubbi Squatter Kutcha 4.00 4.00 100.00 Channagirappa cial

K S Basavaraj S/o Late Commer 3 1.560 RHS Squatter Kutcha 2.00 4.00 50.00 Palya Hosa Hallaiah cial

K S Byatamma W/o Residenti 4 1.700 LHS Owner Pucca 12.00 15.00 80.00 Palya Narasimhappa al

K S Nagarathna W/o Cattle 5 1.706 LHS Owner Kutcha 16.00 20.00 80.00 Palya Narasimhamurthy Shed

K S Narasamma W/o Commer Semi 6 1.740 LHS Owner 8.00 20.00 40.00 Palya Narasimhaiah cial Pucca

K S Kenchamma W/o Residenti Semi 7 1.740 LHS Owner 10.50 15.00 70.00 Palya Narasimhaiah al Pucca K S Commer 8 1.850 LHS Ramappa Squatter Pucca 9.00 9.00 100.00 Palya cial Residenti Chikkona Lakshmana S/o 9 2.000 LHS Owner al/Comm Pucca 14.00 42.00 33.33 halli Hanumanthaiah ercial Chikkona Srinivasa S/o Commer 10 2.070 LHS Squatter Kutcha 4.00 4.00 100.00 halli Chandrappa cial

G Marithimmaiah S/o Residenti 11 3.950 RHS Owner Pucca 48.00 120.00 40.00 Hosahalli Shyamaiah al (O) G Palakshaiah S/o 12 4.120 RHS Owner Pump Pucca 10.00 16.00 62.50 Hosahalli Rudrappa House G Dayananda S/o Commer 13 4.582 LHS Squatter Kutcha 4.00 4.00 100.00 Hosahalli Honnappa cial

G Siddaramanna S/o Commer 14 4.585 LHS Squatter Kutcha 4.00 4.00 100.00 Hosahalli Boranna cial G Legal Commer 15 4.600 LHS Rajanna Kutcha 4.00 4.00 100.00 Hosahalli Tenant cial G Commer 16 4.600 RHS Manjanna Squatter Kutcha 2.00 4.00 50.00 Hosahalli cial G Commer 17 4.610 RHS Chandranna Squatter Kutcha 2.00 4.00 50.00 Hosahalli cial G Anusuyamma W/o Commer 18 4.650 RHS Squatter Kutcha 4.00 4.00 100.00 Hosahalli Rajanna cial

G Rathnamma W/o Late Commer 19 4.655 RHS Squatter Kutcha 4.00 4.00 100.00 Hosahalli Rangaswamaiah cial

G Rajanna S/o Residenti 20 4.830 LHS Owner Pucca 40.00 64.00 62.50 Hosahalli Rangaiah al 195

G Rajanna S/o Cattle 21 4.840 RHS Owner Kutcha 12.00 18.00 66.67 Hosahalli Ranganna Shed

G Anusuyamma W/o Residenti 22 4.862 RHS Owner Pucca 15.00 36.00 41.67 Hosahalli Rajanna al

G Eranna S/o Commer 23 4.980 LHS Squatter Kutcha 4.00 4.00 100.00 Hosahalli Chikkiraiah cial

Thotasag Sangamesha S/o Commer 24 6.640 LHS Squatter Kutcha 4.00 4.00 100.00 ar Gurusiddappa cial Thotasag Commer 25 6.645 LHS Manju S/o Lingaraju Squatter Kutcha 3.00 4.00 75.00 ar cial Thotasag Halumma W/o Residenti Semi 26 6.650 LHS Squatter 10.00 25.00 40.00 ar Revanna al Pucca Thotasag Commer 27 6.660 LHS Dayanna Squatter Kutcha 4.00 4.00 100.00 ar cial Thotasag Venkatesha S/o Commer 28 6.665 RHS Squatter Kutcha 4.00 4.00 100.00 ar Kalaiah cial

Koppa Basavaraj S/o Commer 29 8.220 RHS Squatter Kutcha 4.00 28.00 14.29 Cross Puttaswamachar cial

Koppa Commer 30 8.230 LHS Girisha S/o Seenappa Squatter Kutcha 4.00 4.00 100.00 Cross cial Residenti 31 8.497 RHS Koppa Locked Owner Pucca 32.50 58.50 55.56 al Surigena Venkatarangaiah S/o Residenti 32 9.095 LHS Owner Pucca 20.25 45.00 45.00 halli Venkatappa al

Surigena Ranganatha S/o Residenti 33 9.098 RHS Owner Pucca 52.00 130.00 40.00 halli Gangarangaiah al

Surigena Raja S/o Residenti Semi 34 9.215 RHS Owner 12.00 48.00 25.00 halli Chikkarangaiah al Pucca

Neralaha Lakshminarasaiah S/o Residenti Semi 35 10.258 RHS Owner 10.00 55.00 18.18 lli Narasaiah al Pucca

K G Mudalagirigowda S/o Commer 36 12.175 RHS Owner Pucca 4.50 45.00 10.00 Temple Govindappa cial

K G Ganganna S/o Legal Commer Semi 37 12.235 LHS 1.50 6.00 25.00 Temple Govindappa Tenant cial Pucca K G Commer 38 12.330 RHS Manohar Squatter Kutcha 4.00 4.00 100.00 Temple cial K G Channamma W/o Residenti 39 12.465 RHS Owner Pucca 4.50 30.00 15.00 Temple Late Rangappa al

K G Shivanna S/o Legal Commer Semi 40 12.480 RHS 3.75 9.00 41.67 Temple Kalegowda Tenant cial Pucca

K G Makbal Unnissa Khan Legal Commer 41 12.520 RHS Pucca 1.50 24.00 6.25 Temple W/o Rayasuddin Tenant cial

K G Manjamma W/o Residenti Semi 42 12.530 RHS Owner 1.40 32.00 4.38 Temple Basavaraj al Pucca K G Commer 43 12.550 RHS Rajanna Squatter Kutcha 4.00 4.00 100.00 Temple cial K G Gowramma W/o Commer 44 12.568 LHS Squatter Kutcha 1.00 4.00 25.00 Temple Karegowdru cial

K G Govindaiah S/o Commer 45 12.572 LHS Squatter Kutcha 1.00 4.00 25.00 Temple Arasaiah cial

196

K G Siddaramakka W/o Commer 46 12.592 LHS Squatter Kutcha 1.00 4.00 25.00 Temple Huccha Kariyappa cial

K G Chikkabairaiah S/o Commer 47 12.635 LHS Squatter Kutcha 3.00 4.00 75.00 Temple Gangappa cial

K G Puttaiah S/o Residenti Semi 48 12.778 LHS Owner 4.00 80.00 5.00 Temple Chikkamma al Pucca

K G G R Kumar S/o G M Commer 49 12.810 RHS Owner Pucca 15.00 400.00 3.75 Temple Rangappa cial Lingamm Residenti 50 13.257 RHS Abeeb S/o Chotasab Owner Pucca 25.00 100.00 25.00 anahalli al Lingamm Commer 51 13.278 LHS Kammar S/o Ullisab Squatter Kutcha 4.00 4.00 100.00 anahalli cial Lingamm Makbal Ahmad S/o Residenti Semi 52 13.289 LHS Owner 2.00 40.00 5.00 anahalli Bashasab al Pucca

Lingamm Muneera W/o Semi 53 13.470 LHS Owner (O) Toilet 4.00 8.00 50.00 anahalli Yahubsab Pucca

Abdul Salam S/o Residenti 54 14.388 LHS Kunala Owner Pucca 7.50 75.00 10.00 Abdulbai al

Munna S/o Sadiad Commer 55 14.418 RHS Kunala Squatter Kutcha 1.00 4.00 25.00 Husain Shah cial Commer 56 14.432 RHS Kunala Hithiyaz S/o Alifsab Squatter Kutcha 1.00 4.00 25.00 cial Rafi S/o Abdul Commer 57 14.435 LHS Kunala Squatter Kutcha 1.00 4.00 25.00 Sukursab cial

Commer 58 14.436 RHS Kunala Syed S/o Syed Basha Squatter Kutcha 1.00 4.00 25.00 cial

Iqbal Ahmad S/o Residenti 59 14.445 RHS Kunala Owner Pucca 5.00 100.00 5.00 Kareemsab al

Irshad S/o Residenti 60 14.465 RHS Kunala Owner Pucca 10.00 100.00 10.00 Kareemsab al

Haruves Boregowda S/o Commer 61 17.025 RHS Owner Pucca 1.25 12.50 10.00 andra Kunnaiah cial

Haruves Boregowda S/o Residenti 62 17.030 RHS Owner Pucca 0.50 40.00 1.25 andra Chinnaiah al

Hindisak Yashodhamma W/o Commer 63 18.410 LHS Squatter Kutcha 4.00 4.00 100.00 ere Late Nagaraja Shetty cial

Hindisak Ningamma W/o Commer 64 18.710 LHS Squatter Kutcha 2.00 4.00 50.00 ere Nagaraj cial

Hindisak Somashekhar S/o Commer 65 18.715 LHS Squatter Kutcha 2.00 4.00 50.00 ere Chikkappaiah cial Hindisak Commer 66 18.720 LHS Kampashetty Squatter Kutcha 1.00 4.00 25.00 ere cial Hindisak Rathnamma W/o Commer 67 18.725 LHS Squatter Kutcha 2.00 4.00 50.00 ere Rajanna cial

Hindisak Sannappachar S/o Commer 68 18.730 LHS Squatter Kutcha 2.00 4.00 50.00 ere Kempappachar cial Hindisak Legal Residenti 69 18.730 LHS Neelakantachar Pucca 0.75 64.00 1.17 ere Tenant al Hindisak Narasimhaiah S/o Commer 70 18.735 LHS Squatter Kutcha 2.00 4.00 50.00 ere Rangappa cial

Hindisak M C Chandrashekhar Commer 71 18.738 LHS Squatter Kutcha 2.00 4.00 50.00 ere S/o Channaveerappa cial 197

Hindisak Ramesh S/o Residenti 72 18.770 LHS Owner Pucca 3.00 60.00 5.00 ere Rangappa al

Hindisak T Nanjappa S/o Residenti 73 18.855 LHS Owner Pucca 10.50 105.00 10.00 ere Thimmaiah al

Hindisak Krishnappa S/o Legal Residenti 74 18.942 LHS Pucca 2.00 20.00 10.00 ere Yallaiah Tenant al

Hindisak Mariyanna S/o Gadi Commer 75 18.950 LHS Owner Pucca 8.00 160.00 5.00 ere Yallappa cial

Hindisak Commer 76 18.980 LHS Pathaiah S/o Yallaiah Squatter Kutcha 1.00 4.00 25.00 ere cial

Hindisak H M Parashuramaiah Commer 77 18.985 LHS Squatter Kutcha 1.00 4.00 25.00 ere S/o Mariyappa cial

Hemasa Dodda Yallaiah S/o Commer 78 18.993 LHS Squatter Kutcha 1.00 4.00 25.00 gara Mariyanna cial

Hindisak Parashuram S/o Residenti Semi 79 19.106 RHS Owner 20.00 120.00 16.67 ere Pathaiah al Pucca

Hemasa Vijayalakshmamma Residenti 80 20.652 LHS Owner Pucca 40.00 150.00 26.67 gara W/o Mahadevappa al Commer 81 21.121 RHS C S Pura Raju S/o Rangaiah Squatter Kutcha 4.00 4.00 100.00 cial Ankarama W/o Residenti 82 21.232 RHS C S Pura Owner Pucca 3.00 60.00 5.00 Hydersab al

Kempaiah S/o Chikka Legal Commer 83 21.865 LHS C S Pura Pucca 24.00 120.00 20.00 Kempaiah Tenant cial

Gowramma W/o Residenti 84 22.625 LHS Padugudi Owner Pucca 3.00 36.00 8.33 Narasimhaiah al

Mohammad Anwar Residenti Semi 85 28.210 LHS Kallahalli Owner 67.50 70.00 96.43 S/o M Azam al Pucca

Dodda Narasimhaiah Residenti Semi 86 28.568 LHS Kallahalli Owner 42.00 120.00 35.00 S/o Dodda Narasaiah al Pucca

K N Rangaramaiah Residenti 87 28.648 RHS Kallahalli Owner Pucca 12.00 12.00 100.00 S/o Narasaiah al

Shettigon Commer 88 36.270 RHS Lakshmi W/o Ramesh Squatter Kutcha 4.00 4.00 100.00 danahalli cial

Shettigon Govindaraju S/o Commer 89 36.295 RHS Squatter Kutcha 4.00 4.00 100.00 danahalli Chikka Muniyappa cial

Rangamma W/o Commer 90 37.500 LHS Dodderi Squatter Kutcha 4.00 4.00 100.00 Donaiah cial

Dodda Annegowda S/o Residenti 91 44.670 RHS Owner Pucca 54.00 120.00 45.00 Madure Ramaiah al

Dodda Residenti Semi 92 44.720 RHS Gayathramma Owner 52.00 80.00 65.00 Madure al Pucca

Dodda Lakshmamma W/o Cattle 93 44.840 RHS Owner Kutcha 24.00 120.00 20.00 Madure Nanjegowda Shed

Dodda Dodda Malle Residenti 94 44.850 RHS Owner Pucca 18.00 72.00 25.00 Madure Channaiah al

Dodda Ganganna S/o Commer 95 44.885 LHS Squatter Kutcha 4.00 4.00 100.00 Madure Doddaiah cial

198

Dodda Varadaraj S/o Cattle Semi 96 44.905 RHS Owner 12.00 60.00 20.00 Madure Doddaiah Shed Pucca

Beeraga Semi 97 49.254 LHS Locked Owner (O) Toilet 14.00 28.00 50.00 nahalli Pucca

Beeraga Nalina W/o Shiva Commer 98 49.255 LHS Owner Pucca 12.00 32.00 37.50 nahalli Kumar cial

Beeraga Nalina W/o Shiva Commer 99 49.280 LHS Owner Pucca 10.00 100.00 10.00 nahalli Kumar cial

DHs Structure details of link 57B (Beeragonahalli near Yediur (NH-48) - Kowdley)

Str. Total Affecte % of Str. Sl. Chaina Occu. Loss Structu Str. Area Side Village Name d Area Getting No. ge Status Type re Type (in (in Affected Sq.m) Sq.m) (O) Shanthamma W/o Semi 1 0.002 RHS Yediyur Owner Projectio 24.00 40.00 60.00 Narayanappa Pucca n Commer 2 0.003 LHS Yediyur Vacant Shop Squatter Kutcha 4.00 4.00 100.00 cial Shanthamma W/o Residenti 3 0.040 RHS Yediyur Owner Pucca 59.50 204.00 29.17 Late Narayanappa al

Markena Rangamma W/o Late Residenti 4 5.520 RHS Owner Pucca 32.50 130.00 25.00 halli Muniswamappa al Markena Legal Commer 5 5.620 RHS Mayamma Temple Pucca 4.50 36.00 12.50 halli Tenant cial Markena Thimmaiah S/o Residenti 6 5.670 RHS Owner Pucca 10.50 56.00 18.75 halli Kempegowda al

Markena Boramma W/o Commer 7 5.680 RHS Squatter Kutcha 4.00 4.00 100.00 halli Rudrappa cial Tigaralap Residenti 8 6.276 RHS Kondamma Owner Pucca 30.00 40.00 75.00 alya al Tigaralap Siddaiah S/o Late Residenti 9 6.287 RHS Owner Pucca 35.00 35.00 100.00 alya Thimmaiah al Tigaralap Commer 10 6.290 LHS Kondaiah Squatter Kutcha 4.00 4.00 100.00 alya cial Tigaralap Thimmappa S/o Residenti 11 6.310 RHS Owner Pucca 13.50 30.00 45.00 alya Venkataiah al

Tigaralap Thimmakka W/o Kari Residenti Semi 12 6.582 RHS Owner 24.00 28.00 85.71 alya Rangaiah al Pucca

Hanuma Gangadharappa S/o Residenti 13 8.430 RHS Owner Kutcha 20.00 24.00 83.33 pura Channigaiah al

Hanuma Govindaraj S/o Residenti 14 8.430 RHS Owner Pucca 19.50 104.00 18.75 pura Sannappa al

Hanuma Venkataramappa S/o Residenti 15 8.440 LHS Owner Pucca 40.00 80.00 50.00 pura Govindaiah al

Amruthur Residenti Semi 16 11.600 RHS Muddagowda Owner 27.00 36.00 75.00 u al Pucca

Amruthur Ramakrishna S/o Residenti 17 11.640 LHS Owner Pucca 31.50 70.00 45.00 u Venkataramaiah al 199

Amruthur Legal Commer Semi 18 11.660 LHS Gangachar 27.00 42.00 64.29 u Tenant cial Pucca

Amruthur Legal Residenti Semi 19 11.670 RHS Muddegowda 7.50 9.00 83.33 u Tenant al Pucca

Amruthur Shekhar S/o Commer Semi 20 11.670 LHS Owner 10.50 18.00 58.33 u Venkatachar cial Pucca

Amruthur Ramakrishna S/o Residenti Semi 21 11.680 LHS Owner 31.50 90.00 35.00 u Venkataramaiah al Pucca

Amruthur Ramacharya S/o Commer Semi 22 11.680 LHS Owner 21.00 36.00 58.33 u Krishnachar cial Pucca

Amruthur Gooligowdru S/o Residenti Semi 23 11.690 RHS Owner 32.00 56.00 57.14 u Gooligowdru al Pucca

Amruthur Marigowdru S/o Residenti 24 11.710 RHS Owner Pucca 48.00 72.00 66.67 u Kenchagooli Gowdru al

Amruthur Gangachari S/o Commer 25 11.722 LHS Squatter Kutcha 4.00 4.00 100.00 u Brahmachari cial

Amruthur Chandramma W/o Residenti 26 11.730 LHS Owner Kutcha 17.50 35.00 50.00 u Chikkanna Shetty al Amruthur Residenti 27 11.820 LHS Subbalakshmamma Owner Pucca 15.00 120.00 12.50 u al Amruthur Krishnappa S/o Commer 28 12.380 LHS Owner Pucca 3.25 30.00 10.83 u Chikkagulaiah cial Amruthur Commer 29 12.900 LHS Lacchi Squatter Kutcha 16.00 16.00 100.00 u cial Amruthur Commer 30 12.920 RHS Shaffir Ahmad Squatter Kutcha 4.00 4.00 100.00 u cial Amruthur Shekh Ali Mulla S/o Commer Semi 31 12.990 LHS Owner 24.00 60.00 40.00 u Shekh Munnar cial Pucca

Amruthur Kalachar S/o Residenti Semi 32 13.000 LHS Owner 14.00 48.00 29.17 u Eshwarchar al Pucca

Hosaker Boregowda S/o Residenti 33 15.720 LHS Owner Pucca 120.00 150.00 80.00 e Yamannappa al

Hosaker Boraiah S/o Residenti Semi 34 15.780 LHS Owner 35.00 100.00 35.00 e Boralingaiah al Pucca

Hosaker Ganganna S/o Cattle 35 15.820 LHS Owner Pucca 24.00 48.00 50.00 e Lingappa Shed

Hosaker Boregowda S/o Residenti 36 15.960 RHS Owner Pucca 22.00 55.00 40.00 e Muddegowda al

Hosaker Shankarappa S/o Commer 37 16.040 RHS Squatter Kutcha 2.00 4.00 50.00 e Bangiranga cial

Hosaker Byrapppa S/o Dodd Cattle 38 16.050 LHS Owner Kutcha 10.00 50.00 20.00 e Byregowda Shed

Hosaker Shivanna S/o Residenti 39 16.070 LHS Owner Kutcha 7.50 24.00 31.25 e Byrappa al Residenti Hosaker H C Byrappa S/o 40 16.090 RHS Owner al/Comm Kutcha 9.00 18.00 50.00 e Chikka Boregowda ercial Hosaker Sathish S/o Residenti 41 16.100 LHS Owner Pucca 12.00 24.00 50.00 e Narasimhaiah al

Hosaker Gangaiah S/o Late Residenti 42 16.120 RHS Owner Pucca 12.00 24.00 50.00 e Byrappa al

200

Hosaker Gangaiah S/o Dodda Residenti 43 16.120 LHS Owner Pucca 4.00 28.00 14.29 e Siddaiah al

Hosaker Boregowda S/o Late Residenti 44 16.127 RHS Owner Kutcha 10.00 15.00 66.67 e Byrappa al Residenti Hosaker Narayana S/o Mudla 45 16.128 LHS Owner al/Comm Pucca 10.00 30.00 33.33 e Giriyaiah ercial Hosaker Shivanna S/o Late Residenti 46 16.150 RHS Owner Pucca 12.00 36.00 33.33 e Patattigowda al

Hosaker Lakshmamma W/o Residenti 47 16.156 RHS Owner Pucca 10.00 30.00 33.33 e Kencha Boregowda al

Hosaker H D Krishnappa S/o Farm 48 16.430 RHS Owner Pucca 70.00 100.00 70.00 e Boregowda House

Jinnagar Thimmamma W/o Residenti 49 17.240 LHS Owner Pucca 24.00 72.00 33.33 a Late Kenchaiah al

Jinnagar Gundaiah S/o Residenti 50 17.270 LHS Owner Pucca 13.50 42.00 32.14 a Hucchaia al

J G Partha S/o Residenti 51 17.360 LHS Sanaba Owner Pucca 15.00 60.00 25.00 Gundaiah al

Jinnagar Chandrashekhar S/o Legal Commer 52 17.362 RHS Pucca 2.00 6.00 33.33 a Ramalingaiah Tenant cial Jinnagar Commer 53 17.380 RHS Srinivasaiah Squatter Kutcha 2.00 8.00 25.00 a cial Jinnagar Sakamma W/o Residenti 54 17.440 RHS Owner Pucca 12.00 96.00 12.50 a Ramashetty al

Jinnagar Kumar S/o Late Residenti 55 17.475 RHS Owner Pucca 10.00 30.00 33.33 a Bajjaiah al

Jinnagar Akkamma W/o Residenti 56 17.480 RHS Owner Pucca 4.00 24.00 16.67 a Ramaiah al

Jinnagar Khaji Khan S/o Late Commer 57 17.485 RHS Owner Pucca 12.00 56.00 21.43 a Abdul Majid Khan cial

Jinnagar Lakshmidevamma Commer Semi 58 17.492 RHS Owner 12.00 32.00 37.50 a W/o Rajanna cial Pucca

Jinnagar Commer Semi 59 17.500 RHS Kumar S/o Bajjigowda Owner 12.00 32.00 37.50 a cial Pucca

Jinnagar Jagadish S/o Residenti 60 17.510 RHS Owner Pucca 12.50 30.00 41.67 a Rameshaiah al

Jinnagar Seethramaiah S/o Residenti 61 17.515 RHS Owner Pucca 10.00 20.00 50.00 a Rameshaiah al

Jinnagar Rameshaiah S/o Residenti 62 17.519 RHS Owner Pucca 18.00 48.00 37.50 a Kundura Gooligowda al

Venkatesha S/o Residenti 63 19.150 LHS Sanaba Owner Pucca 14.00 56.00 25.00 Thimmaiah al

Jayaramaiah S/o Cattle 64 19.180 LHS Sanaba Owner Pucca 15.00 48.00 31.25 Ramaiah Shed

Puttamma W/o Late Residenti 65 19.190 LHS Sanaba Owner Pucca 22.00 88.00 25.00 Chikka Gulaiah al

S M Kadlaiah S/o Residenti 66 19.250 RHS Sanaba Owner Pucca 60.00 60.00 100.00 Mariyappa al

Narabhishaiah S/o Residenti 67 19.280 RHS Sanaba Owner Pucca 50.00 100.00 50.00 Maralasiddappa al 201

Chandramma W/o Residenti 68 19.280 LHS Sanaba Owner Pucca 39.00 90.00 43.33 Kenchegowda al

Dasappa S/o Late Residenti 69 19.318 LHS SanabaBoosigowdara Owner Pucca 25.00 80.00 31.25 al Dasegowda

Kempaiah S/o Kaddi Residenti 70 19.320 RHS Sanaba Owner Pucca 32.00 80.00 40.00 Chennaiah al

S T Dasegowda S/o Residenti 71 19.380 LHS Sanaba Owner Pucca 60.00 150.00 40.00 Thimmaiah al

Maridimmaiah S/o Residenti 72 19.430 RHS SanabaNaregegowdana Owner Pucca 6.00 36.00 16.67 al Thimmaiah

Jayaram S/o Residenti 73 19.435 RHS Sanaba Owner Kutcha 12.00 48.00 25.00 Thimmaiah al

S T Gangaiah S/o Residenti 74 19.560 RHS Sanaba Owner Pucca 2.00 32.00 6.25 Thimmaiah al Residenti Venkataramaiah S/o 75 19.570 RHS Sanaba Owner al/Comm Pucca 16.25 91.00 17.86 Late Sannaiah ercial Kempaiah S/o Residenti 76 19.600 RHS Sanaba Owner Pucca 11.00 24.00 45.83 Gulaiah al

Hotte Channaiah S/o Residenti 77 19.780 RHS Sanaba Owner Pucca 300.00 750.00 40.00 Kantappa al

Lakshmamma W/o Residenti 78 19.860 RHS Sanaba Owner Pucca 36.00 108.00 33.33 Hire Channaiah al

Benavar B S Gangadharaiah Residenti 79 21.730 RHS Owner Pucca 130.00 260.00 50.00 akoppalu S/o Siddaiah al

Benavar Marisiddaiah S/o Residenti 80 21.750 RHS Owner Pucca 19.50 24.00 81.25 akoppalu Buduraiah al

Benavar Kulla Chikkamma W/o Residenti 81 21.756 RHS Owner Pucca 6.25 30.00 20.83 akoppalu Byraiah al

Benavar Gangaiah S/o Late Commer 82 21.770 RHS Squatter Kutcha 4.00 4.00 100.00 akoppalu Siddaiah cial

Benavar Siddagangaiah S/o Residenti 83 21.782 RHS Owner Pucca 21.00 48.00 43.75 akoppalu Siddaiah al

Benavar Chikkasiddaiah S/o Residenti 84 21.790 RHS Owner Pucca 28.00 56.00 50.00 akoppalu Siddaiah al

Benavar (O) Bore 85 22.000 LHS Mayanna Owner Pucca 36.00 56.00 64.29 akoppalu Well

Benavar Bettaswamy S/o Residenti Semi 86 22.070 LHS Owner 20.00 48.00 41.67 akoppalu Chikkanna al Pucca

Hanchipu Chikkamma W/o Late Residenti 87 22.880 RHS Owner Pucca 27.00 126.00 21.43 ra Channegowda al

Hanchipu Ramanna S/o Dodda Residenti 88 22.900 RHS Owner Pucca 9.00 42.00 21.43 ra Petegowda al Residenti Hanchipu Byregowda S/o Semi 89 22.920 RHS Owner al/Comm 8.00 48.00 16.67 ra Papanna Pucca ercial Hanchipu Chikkaboraiah S/o Residenti Semi 90 22.930 RHS Owner 4.00 20.00 20.00 ra Kenchalingaiah al Pucca Hanchipu Residenti 91 22.960 RHS Madhu Thimmaiah Owner Pucca 12.00 16.00 75.00 ra al

202

Hanchipu Marithimmaiah S/o Residenti 92 22.990 RHS Owner Pucca 42.00 96.00 43.75 ra Rachappa al

Hanchipu Bettegowda S/o Patil Residenti 93 23.000 LHS Owner Pucca 66.50 114.00 58.33 ra Kempu Boregowda al

Hanchipu Tirumalaiah S/o Residenti 94 23.010 RHS Owner Pucca 17.50 80.00 21.88 ra Rachappa al Hanchipu Residenti 95 23.300 RHS Rajamma Owner Pucca 7.50 40.00 18.75 ra al Hanchipu Shivaramaiah S/o Residenti 96 23.310 RHS Owner Pucca 14.00 42.00 33.33 ra Boraiah al

Hanchipu Sakamma W/o Residenti Semi 97 23.320 RHS Owner 8.00 24.00 33.33 ra Bislaiah al Pucca

Hanchipu Venkatesha S/o Commer 98 23.540 LHS Squatter Kutcha 4.00 4.00 100.00 ra Shivaramu cial

Hanchipu Shivaramaiah S/o Commer 99 23.542 RHS Squatter Kutcha 4.00 4.00 100.00 ra Chennappa cial

Arjunahal A N Virupakshagowda Residenti 100 26.350 RHS Owner Pucca 31.50 90.00 35.00 li S/o Nanjegowda al

Arjunahal Boregowda S/o Residenti 101 26.360 LHS Owner Pucca 45.50 56.00 81.25 li Siddaiah al

Arjunahal Sharadhamma W/o Residenti 102 26.366 LHS Owner Pucca 30.00 40.00 75.00 li Boregowda al

Arjunahal Marigowda S/o Commer Semi 103 26.370 RHS Owner 59.50 76.50 77.78 li Hucchegowda cial Pucca Residenti Arjunahal Nanjundagowda S/o al, 104 26.371 LHS Owner Pucca 60.00 100.00 60.00 li Ramachandraiah Boundar y Wall Arjunahal Nanjaiah S/o Commer 105 26.400 RHS Squatter Kutcha 4.00 4.00 100.00 li Nanjaiah cial

Arjunahal Shivalingamma W/o Residenti 106 26.430 RHS Owner Pucca 11.25 90.00 12.50 li Mariyappa al

DHs Structure details of link 57C (Kowdley - Mandya)

Str. Total Affecte % of Str. Sl. Chaina Occu. Loss Structu Str. Area Side Village Name d Area Getting No. ge Status Type re Type (in (in Affected Sq.m) Sq.m) Boundar Nanjundappa S/o y Semi 1 0.350 LHS Kowdley Thimmaiah Owner 87.50 87.50 100.00 Wall,(O) Pucca Marigowda Godown Umesh S/o Commer 2 0.680 LHS Kowdley Squatter Kutcha 22.50 22.50 100.00 Mahadevappa cial

Putta Tayamma W/o Commer 3 0.850 RHS Kowdley Owner Kutcha 3.00 3.00 100.00 Late Kariyappa cial

Putta Tayamma W/o Legal Commer 4 0.853 RHS Kowdley Kutcha 3.50 3.50 100.00 Late Kariyappa Tenant cial 203

Prakash S/o Late Commer 5 0.856 RHS Kowdley Owner Kutcha 3.50 3.50 100.00 Kariyappa cial

Putta Tayamma W/o Legal Commer 6 0.860 RHS Kowdley Kutcha 3.00 3.00 100.00 Late Kariyappa Tenant cial

Varadaraj S/o Appa Commer 7 0.880 RHS Kowdley Squatter Kutcha 6.25 6.25 100.00 Shetty cial

Shivananja S/o Commer 8 0.885 LHS Kowdley Squatter Kutcha 16.00 16.00 100.00 Nanje Gowda cial Commer 9 0.910 LHS Kowdley Nagaraj S/o Manikya Squatter Kutcha 16.00 16.00 100.00 cial (O) Vishakanta Gowda Semi 10 0.930 RHS Kowdley Owner Projectio 33.00 33.00 100.00 S/o Nanje Gowda Pucca n Jayalakshmi W/o Commer 11 0.945 RHS Kowdley Owner Pucca 3.75 3.75 100.00 Kala Mutthaiah cial

Legal Commer Semi 12 0.950 RHS Kowdley Narayana Gowda B 12.00 12.00 100.00 Tenant cial Pucca Residenti Semi 13 0.953 RHS Kowdley Narayana Gowda B Owner al/Comm 26.13 26.13 100.00 Pucca ercial Residenti 14 0.960 RHS Kowdley Bettaswamy Owner Pucca 36.00 36.00 100.00 al K N Rangaswamy Commer 15 0.980 RHS Kowdley Squatter Kutcha 4.00 4.00 100.00 S/o Nagaiah cial Commer 16 0.980 RHS Kowdley M Mari Gowda Owner Pucca 7.00 7.00 100.00 cial Legal Commer 17 0.983 RHS Kowdley M Mari Gowda Pucca 7.00 7.00 100.00 Tenant cial Legal Commer 18 0.987 RHS Kowdley M Mari Gowda Pucca 7.00 7.00 100.00 Tenant cial Legal Commer 19 1.000 RHS Kowdley M Mari Gowda Pucca 7.00 7.00 100.00 Tenant cial Legal Commer 20 1.003 RHS Kowdley M Mari Gowda Pucca 9.75 9.75 100.00 Tenant cial Owner Not Available Residenti 21 1.040 LHS Kowdley Owner Pucca 10.00 10.00 100.00 during survey al Residenti T Rajappa S/o 22 1.070 LHS Kowdley Owner al/Comm Pucca 32.50 32.50 100.00 Thimme Gowda ercial Residenti T Thimme Gowda 23 1.090 LHS Kowdley Owner al/Comm Pucca 26.25 26.25 100.00 S/o Thimmaiah ercial Rajappa S/o Kulla Residenti 24 1.100 LHS Kowdley Owner Pucca 10.50 10.50 100.00 Hombale Gowda al Residenti Honne Gowda S/o Semi 25 1.120 LHS Kowdley Owner al/Comm 5.25 5.25 100.00 Ninge Gowda Pucca ercial Chenne Gowda S/o (O) Saw Semi 26 1.200 RHS Kowdley Owner 20.00 20.00 100.00 Male Gowda Mill Pucca

Jogi Gowda S/o Residenti Semi 27 1.820 RHS Kowdley Owner 3.50 3.50 100.00 Sanna Mari Gowda al Pucca

Karadaiah S/o Residenti 28 2.220 LHS Kowdley Owner Pucca 153.00 153.00 100.00 Hombaiah al

Prakasha S/o Residenti 29 2.220 LHS Kowdley Owner Pucca 22.50 22.50 100.00 Karadaiah al

Mariswamy Gowda (O) Semi 30 2.540 LHS Kowdley Owner 32.50 32.50 100.00 S/o Jogigowda Godown Pucca

204

D Chandramma W/o Legal Residenti 31 6.500 RHS Pucca 7.50 7.50 100.00 Malligere Siddarama Tenant al

D Putta Ningamma Residenti 32 6.510 RHS Owner Pucca 7.00 7.00 100.00 Malligere W/o Late Ramanna al

D Ramaiah S/o Cattle 33 6.650 LHS Owner Pucca 17.50 17.50 100.00 Malligere Hucche Gowda Shed

Chikka Thimmamma D Cattle 34 6.660 LHS W/o Late Chikka Squatter Kutcha 25.00 25.00 100.00 Malligere Shed Thimmaiah

D Channappa S/o Cattle 35 6.720 LHS Owner Pucca 31.25 31.25 100.00 Malligere Ningappa Shed

D Parvathamma W/o Residenti 36 6.735 LHS Owner Pucca 14.40 14.40 100.00 Malligere Late Nanjaiah al

D Mariyappa S/o Papu Residenti 37 6.741 LHS Owner Pucca 14.40 14.40 100.00 Malligere Nanjaiah al

D Biliyappa S/o Commer Semi 38 6.760 LHS Owner 16.13 16.13 100.00 Malligere Nanjunde Gowda cial Pucca

D Lakshmamma W/o Legal Commer Semi 39 6.770 LHS 5.60 5.60 100.00 Malligere Srikante Gowda Tenant cial Pucca

D Nanje Gowda S/o Commer 40 6.774 LHS Squatter Kutcha 4.00 4.00 100.00 Malligere Kempaiah cial

D Hucche Gowda S/o Commer Semi 41 6.870 LHS Owner 7.80 7.80 100.00 Malligere Mudle Gowda cial Pucca

Ramanna S/o Nathe Commer 42 8.230 RHS Hosagavi Squatter Kutcha 4.00 4.00 100.00 Gowda cial

Chandag Shambu Gowda S/o Residenti Semi 43 12.375 LHS Owner 3.68 3.68 100.00 alu Kari Gowda al Pucca

Chandag Shambu Gowda S/o Residenti 44 12.380 RHS Owner Pucca 11.20 11.20 100.00 alu Khajani Gowda al

Chandag Shambu Gowda S/o Residenti 45 12.390 LHS Owner Pucca 14.00 14.00 100.00 alu Kari Gowda al

Chandag Rani W/o Late Residenti 46 12.390 RHS Owner Pucca 11.90 11.90 100.00 alu Ramakrishna al

Chandag Ramesh S/o Residenti 47 12.394 RHS Owner Pucca 13.50 13.50 100.00 alu Puttaswamy Gowda al

Chandag Gowramma W/o Residenti 48 12.410 LHS Owner Pucca 8.00 8.00 100.00 alu Kulle Gowda al

Chandag Mote Gowda S/o Residenti 49 12.415 LHS Owner Pucca 1.95 1.95 100.00 alu Mullure Gowda al

Doddhyde Gowda Chandag Residenti 50 12.430 LHS S/o Dodda Putte Owner Pucca 6.08 6.08 100.00 alu al Gowda

Chandag Sidde Gowda S/o Commer 51 12.430 RHS Owner Kutcha 2.10 2.10 100.00 alu Siddaiah cial

Thammanna Gowda Chandag Residenti 52 12.460 LHS S/o Chikka Linge Owner Pucca 14.40 14.40 100.00 alu al Gowda Residenti Chandag Rajamma W/o Late Semi 53 12.460 RHS Owner al/Comm 3.00 3.00 100.00 alu Cheluvaraja Shetty Pucca ercial 205

Chandag Ravi S/o Commer 54 12.465 LHS Squatter Kutcha 4.00 4.00 100.00 alu Thammanna Gowda cial

Venkataramana Chandag Commer 55 12.470 RHS Shetty S/o Neela Owner Kutcha 4.00 4.00 100.00 alu cial Shetty

Chandag Shankare Gowda Residenti 56 12.490 LHS Owner Pucca 3.33 3.33 100.00 alu S/o Mote Gowda al

Chandag Cheluvaraju S/o Commer 57 12.500 LHS Owner Kutcha 7.50 7.50 100.00 alu Vaikunta Shettaru cial

Puttaswamy Gowda Chandag Residenti Semi 58 12.510 LHSS/o Chikka Linge Owner 11.50 11.50 100.00 alu al Pucca Gowda

Chandag Kulle Gowda S/o Residenti 59 12.520 LHS Owner Kutcha 8.50 8.50 100.00 alu Chikka Linge Gowda al

Chikka Tayamma (O) Chandag 60 12.530 LHSW/o Late Kari Owner Basemen Kutcha 12.15 12.15 100.00 alu Gowda t (O) Chandag Bili Gowda S/o 61 12.530 RHS Owner Projectio Kutcha 1.75 1.75 100.00 alu Kenche Gowda n Chandag Ramalingaiah S/o Commer 62 12.540 RHS Squatter Kutcha 4.00 4.00 100.00 alu Bili Gowda cial

Lakshmamma W/o Chandag Residenti 63 12.550 LHSLate Puttaswamy Owner Pucca 21.75 21.75 100.00 alu al Gowda

Chandag Putta Tayamma W/o Residenti 64 12.558 LHS Owner Pucca 3.38 3.38 100.00 alu Nage Gowda al

Sanna Acharya S/o Chandag Residenti 65 12.595 LHSDodda Owner Kutcha 21.00 21.00 100.00 alu al Venkatacharya

Appacharya S/o Chandag Residenti 66 12.603 LHSDodda Owner Kutcha 21.00 21.00 100.00 alu al Venkatacharya

Chandag Bore Gowda S/o Commer 67 12.625 LHS Squatter Kutcha 16.00 16.00 100.00 alu Siddalinge Gowda cial

Chandag Ganesh S/o Linge Commer 68 12.870 RHS Squatter Kutcha 4.00 4.00 100.00 alu Gowda cial

Chandag Venkata Shetty S/o Commer 69 12.910 LHS Squatter Kutcha 25.00 25.00 100.00 alu Govinda Shetty cial

Chandag Nathe Gowda S/o Commer 70 12.910 RHS Squatter Kutcha 9.00 9.00 100.00 alu Gulle Bore Gowda cial

Chandag Kenche Gowda S/o Residenti 71 12.913 RHS Owner Kutcha 1.50 1.50 100.00 alu Badda Linge Gowda al

Chandag Shivarathna W/o Commer 72 12.915 LHS Squatter Kutcha 4.00 4.00 100.00 alu Bore Gowda cial

Chandag Kariya S/o Mari Residenti Semi 73 13.060 LHS Owner 8.80 8.80 100.00 alu Kuntaiah al Pucca

Chandag Linge Gowda S/o Residenti 74 13.120 LHS Owner Pucca 21.85 21.85 100.00 alu Mallu Gowda al

206

Halleger Ramakrishna S/o Cattle 75 14.790 RHS Owner Pucca 12.00 12.00 100.00 e Late Buke Gowda Shed

Vijayendra S/o Commer Halleger 76 14.830 LHS Chikka Sidde Squatter cial,Boun Kutcha 16.00 16.00 100.00 e Gowda dary Wall

Halleger Jayappa S/o Dodda Residenti 77 14.840 LHS Owner Pucca 12.90 12.90 100.00 e Javare Gowda al

Halleger Chikka Boraiah S/o Commer 78 14.850 LHS Squatter Kutcha 16.00 16.00 100.00 e Siddaiah cial

Halleger Aathik Ahmad S/o Commer 79 14.854 LHS Squatter Kutcha 16.00 16.00 100.00 e Babajaan cial

H N Halleger Commer 80 14.915 LHS Narasimhacharya Squatter Pucca 9.00 9.00 100.00 e cial S/o Narasimhachari

Halleger Gowramma W/o Commer 81 14.918 LHS Squatter Pucca 9.00 9.00 100.00 e Late Shankarappa cial

Venkataramana Halleger Commer 82 14.921 LHS Shetty S/o Squatter Pucca 9.00 9.00 100.00 e cial Cheluvappa Shetty

Halleger H P Krishna S/o Commer 83 14.924 LHS Squatter Pucca 9.00 9.00 100.00 e Papanna cial

Halleger Subbe Gowda S/o Commer 84 14.960 LHS Squatter Pucca 12.00 12.00 100.00 e Javare Gowda cial

Halleger Muralidhara S/o Commer 85 14.963 LHS Squatter Pucca 12.00 12.00 100.00 e Nanjundappa cial

Halleger H C Siddaraju S/o Commer 86 14.966 LHS Squatter Pucca 24.00 24.00 100.00 e Chikka Mari Gowda cial

Halleger H B Shankar S/o (O) Stare Stair 87 14.990 RHS Owner 0.75 0.75 100.00 e Bore Gowda Case Case

H C Shivaramu S/o Halleger Legal Commer 88 14.995 RHS Chikka Javare Pucca 4.00 4.00 100.00 e Tenant cial Gowda

H C Shivaramu S/o Halleger Legal Commer 89 14.999 RHS Chikka Javare Pucca 4.00 4.00 100.00 e Tenant cial Gowda

H C Shivaramu S/o Halleger Legal Commer 90 15.003 RHS Chikka Javare Pucca 4.00 4.00 100.00 e Tenant cial Gowda

H C Shivaramu S/o Halleger Legal Commer 91 15.006 RHS Chikka Javare Pucca 4.00 4.00 100.00 e Tenant cial Gowda

Commer Halleger Legal 92 15.009 RHS H C Shivaramu cial,Boun Pucca 8.00 8.00 100.00 e Tenant dary Wall

Halleger Chowde Gowda S/o Commer 93 15.030 LHS Owner Pucca 2.00 2.00 100.00 e Panne Gowda cial

Halleger Rajanna S/o Legal Commer 94 15.035 LHS Pucca 16.80 16.80 100.00 e Papanna Tenant cial Halleger Legal Commer 95 15.040 RHS H C Shivaramu Pucca 30.40 30.40 100.00 e Tenant cial 207

Halleger Legal (O) 96 15.042 LHS Owner Not Available Pucca 28.00 28.00 100.00 e Tenant Godown Residenti Halleger Rajanna S/o 97 15.055 LHS Owner al,(O) Pucca 82.50 82.50 100.00 e Papanna Godown Residenti Halleger Rajanna S/o 98 15.055 LHS Owner al,(O) Pucca 82.50 82.50 100.00 e Papanna Godown Anasosal Radhakrishna S/o A Residenti 99 16.940 RHS Owner Pucca 138.38 138.38 100.00 u M Ramanna al

Anasosal Mahendra S/o A M Residenti 100 16.953 RHS Owner Pucca 143.00 143.00 100.00 u Ramanna al

Anasosal Mahendra S/o A M Commer 101 17.010 RHS Owner Pucca 17.50 17.50 100.00 u Ramanna cial

Anasosal A R Radhakrishna Commer 102 17.013 RHS Owner Pucca 17.50 17.50 100.00 u S/o Ramanna cial

Ankanna Suresh S/o Legal Commer 103 17.015 RHS Pucca 12.00 12.00 100.00 na Doddi Kariyappa Tenant cial

Ankanna Suresh S/o Residenti 104 17.019 RHS Owner Pucca 96.00 96.00 100.00 na Doddi Kariyappa al

Rame Gowda S/o Ankanna Residenti 105 17.060 LHSSheddu Manche Owner Pucca 13.30 13.30 100.00 na Doddi al Gowda

Pape Gowda S/o Ankanna Residenti 106 17.070 LHSShedda Manche Owner Pucca 25.30 25.30 100.00 na Doddi al Gowda

P Shivalinge Gowda Ankanna Encroache Commer 107 17.075 RHS S/o Puttaswamy Kutcha 6.88 6.88 100.00 na Doddi r cial Gowda

Ankanna Chikkanna S/o Residenti 108 17.230 RHS Squatter Kutcha 48.00 48.00 100.00 na Doddi Chikka Narasaiah al

Kalmaddi K H Rame Gowda Commer 109 19.100 RHS Squatter Kutcha 6.25 6.25 100.00 Doddi S/o Hanume Gowda cial

Kalmaddi Shivanna S/o Ganji Commer 110 19.105 RHS Squatter Kutcha 7.50 7.50 100.00 Doddi Lingaiah cial Residenti Kalmaddi Sakamma W/o 111 19.107 LHS Owner al/Comm Pucca 11.55 11.55 100.00 Doddi Puttaswami Gowda ercial Kalmaddi Kumar S/o Shankare Commer 112 19.110 RHS Squatter Kutcha 7.50 7.50 100.00 Doddi Gowda cial Residenti Kalmaddi Mahadeva S/o 113 19.113 LHS Owner al/Comm Pucca 13.30 13.30 100.00 Doddi Channe Gowda ercial Commer Kalmaddi Nagaraj S/o 114 19.150 LHS Owner cial,Boun Pucca 13.60 13.60 100.00 Doddi Chikkanathe Gowda dary Wall

Kalmaddi Shivanna S/o Commer 115 19.150 RHS Owner Kutcha 10.50 10.50 100.00 Doddi Basave Gowda cial

Kalmaddi Manteswamy S/o Commer 116 19.390 LHS Squatter Kutcha 36.00 36.00 100.00 Doddi Guru Basavachari cial

Kalmaddi D Puttaswamy S/o Commer 117 19.435 LHS Squatter Pucca 25.00 25.00 100.00 Doddi Dase Gowda cial

208

Kalmaddi Bili Gowda S/o Ere Commer 118 19.440 RHS Squatter Kutcha 12.25 12.25 100.00 Doddi Gowda cial Boundar y Ankanna Shankara S/o Sidde 119 19.900 RHS Owner Wall,(O) Pucca 5.00 5.00 100.00 na Doddi Gowda Open Plot (O) Keregod Prakash S/o 120 20.440 RHS Owner Projectio Kutcha 19.55 19.55 100.00 u Honnappa n Keregod Mahadevappa S/o Commer 121 20.550 LHS Squatter Kutcha 4.00 4.00 100.00 u Ganganna cial

Keregod Ramesh S/o Commer 122 20.555 LHS Squatter Kutcha 6.25 6.25 100.00 u Puttaswamy Gowda cial Keregod Commer 123 20.558 LHS M Siddappa Squatter Kutcha 6.25 6.25 100.00 u cial Keregod Nagaraja S/o Commer 124 20.675 LHS Squatter Kutcha 4.00 4.00 100.00 u Chandrachar cial Keregod Legal Commer 125 20.685 LHS Jayaswamy K L Pucca 4.20 4.20 100.00 u Tenant cial Keregod Commer 126 20.690 LHS Vacant Shop Squatter Kutcha 4.00 4.00 100.00 u cial Keregod Commer 127 20.695 LHS Siddamma W/o Ravi Squatter Kutcha 18.00 18.00 100.00 u cial Keregod Iqbal Pasha S/o Commer 128 20.700 LHS Squatter Kutcha 10.50 10.50 100.00 u Munnavar Pasha cial Keregod Commer 129 20.703 LHS Vacant Shop Squatter Kutcha 4.00 4.00 100.00 u cial Keregod Shankare Gowda (O) Stare Stair 130 20.715 LHS Owner 6.60 6.60 100.00 u S/o Ganesha Gowda Case Case (O) Keregod K N Nagaraja S/o Encroache 131 20.720 LHS Projectio Kutcha 14.00 14.00 100.00 u Nage Gowda r n (O) Keregod K Anne Gowda S/o Encroache 132 20.740 LHS Projectio Kutcha 12.25 12.25 100.00 u Doddhyde Gowda r n Residenti Keregod Sadashiva Murthy 133 20.745 RHS Owner al/Comm Pucca 7.00 7.00 100.00 u S/o Shivarudrappa ercial (O) Keregod Ramesh S/o H S Encroache 134 20.750 LHS Projectio Kutcha 9.00 9.00 100.00 u Rajashekaraiah r n (O) Keregod Shankar S/o Late T Legal 135 20.752 RHS Projectio Kutcha 5.00 5.00 100.00 u K Linge Gowda Tenant n (O) Keregod Shankare Gowda Encroache 136 20.753 LHS Projectio Kutcha 36.00 36.00 100.00 u S/o Linge Gowda r n Keregod Ramakrishna S/o C Legal Commer 137 20.790 RHS Pucca 2.80 2.80 100.00 u Chikka Linge Gowda Tenant cial

Ramakrishna S/o K Keregod Legal Commer 138 20.793 RHS C Chikkalinge Pucca 6.13 6.13 100.00 u Tenant cial Gowda

K C Ramakrishna Keregod Legal Commer 139 20.797 RHS S/o C Chikkalinge Pucca 10.80 10.80 100.00 u Tenant cial Gowda

Keregod Jayamma W/o Legal Commer 140 20.820 RHS Pucca 12.00 12.00 100.00 u Venkata Shetty Tenant cial 209

Residenti Keregod Jayamma S/o 141 20.820 RHS Owner al/Comm Pucca 12.00 12.00 100.00 u Venkata Shetty ercial Keregod Jayamma W/o Legal Commer 142 20.823 RHS Pucca 9.00 9.00 100.00 u Venkata Shetty Tenant cial

Keregod Jayamma W/o Legal Commer 143 20.823 RHS Pucca 12.00 12.00 100.00 u Venkata Shetty Tenant cial

Keregod Shivaswamy S/o Legal Commer 144 20.825 RHS Pucca 9.45 9.45 100.00 u Patel Chikkanna Tenant cial

Keregod Shivaswamy S/o Legal Commer 145 20.829 RHS Pucca 18.90 18.90 100.00 u Patel Chikkanna Tenant cial

Keregod Shivaswamy S/o Legal Commer Semi 146 20.833 RHS 8.10 8.10 100.00 u Patel Chikkanna Tenant cial Pucca

Keregod Anne Gowda S/o Legal Commer 147 20.836 RHS Pucca 12.00 12.00 100.00 u Doddalinge Gowda Tenant cial

Keregod Anne Gowda S/o Legal 148 20.836 RHS Office Pucca 30.00 30.00 100.00 u Doddalinge Gowda Tenant

Keregod Kempira Shetty S/o Commer 149 20.840 LHS Squatter Kutcha 6.25 6.25 100.00 u Kempira Shetty cial

Keregod Anne Gowda S/o Legal Commer 150 20.840 RHS Pucca 12.00 12.00 100.00 u Doddalinge Gowda Tenant cial

Keregod Vijay Kumar S/o Commer 151 20.843 LHS Squatter Kutcha 6.25 6.25 100.00 u Mari Gowda cial

Keregod Anne Gowda S/o Legal Commer 152 20.844 RHS Pucca 12.00 12.00 100.00 u Doddalinge Gowda Tenant cial

Keregod Ramu S/o Commer 153 20.846 LHS Squatter Kutcha 6.25 6.25 100.00 u Chikkalingaiah cial

K M Yashodhamma Keregod Legal Commer 154 20.848 RHS W/o Late K L Pucca 14.70 14.70 100.00 u Tenant cial Krishne Gowda

K M Yahsodhamma Keregod Legal Commer 155 20.851 RHS W/o Late K L Pucca 16.80 16.80 100.00 u Tenant cial Krishne Gowda

K M Yashodhamma Keregod Legal Commer 156 20.855 RHS W/o Late K L Pucca 16.80 16.80 100.00 u Tenant cial Krishne Gowda

Keregod Nagamma W/o Bore Legal Commer 157 20.860 RHS Pucca 20.00 20.00 100.00 u Gowda Tenant cial

Keregod Nagamma W/o Bore Legal Commer 158 20.864 RHS Pucca 24.80 24.80 100.00 u Gowda Tenant cial

Keregod Nagamma W/o Bore Legal Commer 159 20.868 RHS Pucca 17.50 17.50 100.00 u Gowda Tenant cial

K S Mruthyunjaya Residenti Keregod 160 20.872 RHS Swamy S/o K M Owner al/Comm Pucca 83.70 83.70 100.00 u Shivanna ercial

K S Mruthyunjaya Residenti Keregod 161 20.872 RHS Swamy S/o K M Owner al/Comm Pucca 83.70 83.70 100.00 u Shivanna ercial

210

K S Mruthyunjaya Residenti Keregod 162 20.872 RHS Swamy S/o K M Owner al/Comm Ground 83.70 270.00 31.00 u Shivanna ercial

K S Mruthyunjaya Residenti Keregod Ground 163 20.872 RHS Swamy S/o K M Owner al/Comm 83.70 270.00 31.00 u +1 Shivanna ercial

Keregod K S Mruthyunjaya Legal Commer Semi 164 20.885 RHS 12.00 12.00 100.00 u S/o K M Shivanna Tenant cial Pucca

Keregod P Krishne Gowda Commer Semi 165 20.960 LHS Owner 11.93 11.93 100.00 u S/o Panche Gowda cial Pucca Keregod Legal Commer 166 20.977 LHS Mujarayi Ilake Pucca 4.50 4.50 100.00 u Tenant cial Keregod Meenakshi W/o Commer 167 21.000 LHS Squatter Pucca 9.00 9.00 100.00 u Ramakrishna cial Keregod Commer 168 21.003 LHS Vacant Shop Squatter Kutcha 18.00 18.00 100.00 u cial Keregod Commer 169 21.009 LHS Vacant Shop Squatter Kutcha 6.25 6.25 100.00 u cial Keregod Jagadheesh S/o Commer 170 21.020 RHS Squatter Kutcha 12.00 12.00 100.00 u Buye Gowda cial

Krishne Gowda S/o Keregod Legal Residenti 171 21.080 LHS Chikka Mudde Pucca 24.50 24.50 100.00 u Tenant al Gowda

Krishne Gowda S/o Keregod Legal Residenti 172 21.083 LHS Chikka Mudde Pucca 21.00 21.00 100.00 u Tenant al Gowda

Marilinga Puttaswamy S/o 173 22.100 LHS Owner (O) Toilet Kutcha 3.00 3.00 100.00 na Doddi Kajji Ninge Gowda

Marilinga Cheluva Shetty S/o Commer 174 22.185 RHS Owner Kutcha 24.00 24.00 100.00 na Doddi Thammaiah Shetty cial

Marilinga M S Baire Gowda Commer 175 22.190 LHS Squatter Kutcha 4.00 4.00 100.00 na Doddi S/o Sidde Gowda cial

Marilinga Narayana S/o Mari Commer 176 22.200 RHS Squatter Kutcha 6.25 6.25 100.00 na Doddi Gowda cial

Marilinga Chennachari S/o Commer 177 22.225 RHS Squatter Kutcha 12.00 12.00 100.00 na Doddi Mayachari cial

Marilinga Anil Kumar S/o K Commer 178 22.230 RHS Squatter Kutcha 9.00 9.00 100.00 na Doddi Linge Gowda cial

Marilinga Umesh S/o H Chikke Commer 179 22.235 RHS Squatter Kutcha 4.00 4.00 100.00 na Doddi Gowda cial

Marilinga M L Nagaraju S/o Residenti 180 22.240 RHS Owner Pucca 32.20 32.20 100.00 na Doddi Linge Gowda al

Marilinga K Mari Gowda S/o Residenti 181 22.520 RHS Owner Pucca 18.06 18.06 100.00 na Doddi Kari Gowda al

Krishna S/o Chikka Commer 182 25.765 LHS Hulivana Squatter Kutcha 9.00 9.00 100.00 Siddappa cial

Harinarayana S/o Residenti 183 26.140 RHS Hulivana Owner Pucca 99.75 99.75 100.00 Bellada Siddappa al

Lakshmi W/o Commer 184 26.370 LHS Hulivana Squatter Kutcha 6.25 6.25 100.00 Ganesh cial 211

H M Puttaswamy S/o Commer 185 26.390 RHS Hulivana Owner Pucca 7.36 7.36 100.00 H S Manchaiah cial

H C Ramachandra Commer 186 26.400 LHS Hulivana S/o Chikka Squatter Kutcha 6.25 6.25 100.00 cial Thammaiah

H S Shankarappa 187 26.440 LHS Hulivana Owner (O) Toilet Pucca 3.75 3.75 100.00 S/o Sidde Gowda

H B Nagaraj S/o Legal Commer 188 26.440 RHS Hulivana Pucca 2.25 2.25 100.00 Dodda Bore Gowda Tenant cial

H B Nagaraj S/o Legal Commer 189 26.444 RHS Hulivana Pucca 2.70 2.70 100.00 Dodda Bore Gowda Tenant cial

H B Rajanna S/o Commer Semi 190 26.450 LHS Hulivana Owner 4.38 12.25 35.71 Gowdnar Boraiah cial Pucca

Umesh S/o Commer 191 26.454 LHS Hulivana Squatter Kutcha 1.60 4.00 40.00 Krishnappa cial

Siddamma W/o Commer 192 26.465 RHS Hulivana Squatter Kutcha 5.00 5.00 100.00 Manchaiah cial

Lohith Kumar S/o Commer 193 26.470 RHS Hulivana Squatter Kutcha 12.00 12.00 100.00 Nagaraj cial

Prakash S/o Commer 194 26.480 RHS Hulivana Owner Kutcha 1.50 6.25 24.00 Piddappa cial

Seema W/o Commer 195 26.483 RHS Hulivana Squatter Kutcha 4.00 4.00 100.00 Lakshmana cial

Papanna S/o Commer 196 26.485 RHS Hulivana Kenchappana Sidde Squatter Kutcha 4.00 4.00 100.00 cial Gowda Commer 197 26.495 RHS Hulivana Owner Not Available Squatter Kutcha 4.00 4.00 100.00 cial Naganna S/o Bore Legal Commer 198 26.540 LHS Hulivana Pucca 6.40 32.00 20.00 Gowda Tenant cial

Baire Gowda S/o Commer 199 26.590 RHS Hulivana Squatter Kutcha 9.00 9.00 100.00 Honi Kencha cial

Mangalamma W/o Commer 200 26.600 RHS Hulivana Squatter Kutcha 4.00 4.00 100.00 Jayarama cial

H D Shankare Gowda S/o Commer 201 26.620 RHS Hulivana Squatter Kutcha 6.25 6.25 100.00 Panchayyana Dase cial Gowda

Murthy S/o Commer 202 26.630 LHS Hulivana Squatter Kutcha 4.00 4.00 100.00 Govindaiah cial

Chandru S/o Chikka Commer 203 26.690 LHS Hulivana Squatter Kutcha 6.25 6.25 100.00 Poraiah cial

Manche Gowda S/o Commer 204 26.720 LHS Hulivana Squatter Kutcha 4.00 4.00 100.00 Boraiah cial

Shivamma W/o Commer 205 26.730 LHS Hulivana Squatter Kutcha 4.00 4.00 100.00 Madiwali Ramanna cial

Commer H B Javare Gowda Semi 206 26.740 LHS Hulivana Owner cial,Boun 11.20 11.20 100.00 S/o Baire Gowda Pucca dary Wall

212

Gendera Krishna Commer 207 26.750 RHS Hulivana Squatter Kutcha 4.00 4.00 100.00 S/o Nathe Gowda cial Commer 208 26.760 RHS Hulivana Vacant Shop Squatter Kutcha 4.00 4.00 100.00 cial Residenti Honagan Kamalamma W/o al,(O) 209 27.415 LHS Owner Pucca 9.20 12.00 76.67 ahalli Chowdaiah Poultry Farm Residenti Honagan Kamalamma W/o al,(O) 210 27.415 LHS Owner Pucca 9.20 9.20 100.00 ahalli Chowdaiah Poultry Farm Honagan Naganna S/o Residenti 211 27.440 RHS Owner Pucca 5.85 42.25 13.85 ahalli Kalachavade Gowda al

Honagan H K Mahesh S/o Residenti 212 27.447 RHS Owner Pucca 9.38 9.38 100.00 ahalli Kala Chowdaiah al

Honagan Thimmamma W/o Residenti 213 27.770 RHS Squatter Kutcha 21.00 21.00 100.00 ahalli Eraiah al

Honagan Kumar S/o Ninge Commer 214 27.782 RHS Squatter Kutcha 4.00 4.00 100.00 ahalli Gowda cial

Kommer Lakshmamma W/o Residenti Semi 215 29.080 LHS Squatter 22.50 45.00 50.00 ahalli Gopalaiah al Pucca Residenti Kommer Pape Gowda S/o al,(O) 216 29.090 LHS Owner Pucca 8.30 99.60 8.33 ahalli Bore Gowda Open Plot Kommer Ramesha S/o Sanna Commer 217 29.120 LHS Squatter Kutcha 6.25 6.25 100.00 ahalli Lingaiah cial

Kommer Gayathri W/o Late Commer 218 29.125 LHS Squatter Kutcha 3.75 6.25 60.00 ahalli Bhimaraju cial

Kommer Ramesh S/o Commer 219 29.180 RHS Squatter Kutcha 4.00 4.00 100.00 ahalli Ramaiah cial Kommer Commer 220 29.200 RHS Raju Squatter Kutcha 4.00 4.00 100.00 ahalli cial Kommer Kempaiah S/o Residenti 221 29.225 RHS Squatter Kutcha 36.00 36.00 100.00 ahalli Thimmaiah al

Kommer Sidda Shetty S/o Residenti 222 29.235 RHS Squatter Kutcha 20.00 20.00 100.00 ahalli Sidda Shetty al Kommer Legal Commer 223 29.440 RHS Dodda Ramanna Pucca 18.00 18.00 100.00 ahalli Tenant cial Kommer Legal Residenti 224 29.446 RHS Chikkaram Pucca 19.20 19.20 100.00 ahalli Tenant al Residenti Kommer 225 29.540 RHS Vacant House Owner al/Comm Pucca 5.25 5.25 100.00 ahalli ercial Nagarathnamma (O) Sathanur Encroache 226 30.440 RHS W/o Late Projectio Kutcha 4.20 4.20 100.00 u r Shambulingaiah n Residenti Sathanur S V Gopal S/o Semi 227 30.680 LHS Owner al/Comm 27.50 50.00 55.00 u Venkataiah Pucca ercial Sathanur Chenne Gowda S/o Commer 228 30.690 RHS Squatter Kutcha 4.00 4.00 100.00 u Ramanna cial

Sathanur Ravi S/o Commer 229 30.700 LHS Owner Pucca 4.20 9.00 46.67 u Narasimhaiah cial 213

Sathanur Chenne Gowda S/o Commer 230 30.700 RHS Squatter Kutcha 4.00 4.00 100.00 u Chikka Kari Gowda cial

Sathanur Sridhar S/o Commer 231 30.750 RHS Squatter Kutcha 6.25 6.25 100.00 u Ramachandra cial

Prathap S/o Rame Commer 232 31.525 LHS Mandya Squatter Kutcha 6.25 6.25 100.00 Gowda cial

Shivashankar Pujari Commer 233 31.730 LHS Mandya S/o Siddaramaiah Owner Pucca24.00 90.00 26.67 cial Pujari

Shivashankar S/o Commer 234 31.755 LHS Mandya Squatter Kutcha 6.25 6.25 100.00 Sannappa cial

C B Shankare Legal Commer Semi 235 31.765 LHS Mandya Gowda S/o C B 61.65 135.00 45.67 Tenant cial Pucca Boraiah

Commer Pradeep Kumar S/o 236 31.840 LHS Mandya Owner cial,Boun Pucca38.50 38.50 100.00 Patel Jaya Kumar dary Wall

Swamy S/o Commer Semi 237 31.990 LHS Mandya Owner 52.25 57.00 91.67 Javadevaiah cial Pucca Commer 238 32.980 RHS Mandya Vacant Shop Squatter Pucca 36.00 36.00 100.00 cial Commer 239 33.020 RHS Mandya Aruna S/o Shivanna Squatter Kutcha 4.00 4.00 100.00 cial Commer 240 33.025 RHS Mandya Ashok S/o Annappa Squatter Kutcha 4.00 4.00 100.00 cial Kumar S/o Late Commer 241 33.030 RHS Mandya Squatter Kutcha 6.25 6.25 100.00 Srinivas cial

H D Shankare (O) Encroache Semi 242 33.040 RHS Mandya Gowda S/o Dase Projectio 6.00 6.00 100.00 r Pucca Gowda n

Jayamma W/o Commer 243 33.070 LHS Mandya Squatter Kutcha 1.25 6.25 20.00 Jayaram cial

214

Annex 6 : List of Participants for Meeting and Photographs List of Participants for Meeting – 57A, 57B and 57C 215

216 217

218 219

220 221

222

Consultation Meetings

Meeting at Hindisakere village on 18.07.2010 Meeting at Hindisakere village on 18.07.2010 – Link 57A – Link 57A

Meeting at Jinnagara village on 18.07.2010 – Meeting at Jinnagara village on 18.07.2010 – Link 57B Link 57B

Meeting at Chandagalu village on 18.07.2010 Meeting at Chandagalu village on 18.07.2010 – Link 57C – Link 57C 223

Annex 7 TERMS OF REFERENCE FOR NGO CONSULTANCY FOR IMPLEMENTATION OF RESETTLEMENT PLAN I. BACKGROUND OF THE PROJECT 1. The aim of the project is to improve the performance of the State's road transport sector. The KSHIP Stage I roads have been selected based on the Feasibility Study of State Roads for proposed KSHIP. The PWD has carried out a Poverty and Social Assessment study for 615.03 kms of roads and prepared a Resettlement Plan . Keeping in view the impact to the people due to the implementation of the project, the PIU will require to appropriately resettle and rehabilitate the DPs in accordance with the RP proposed for the purpose. For the implementation of the RP, the PIU will require to appoint local NGO who not only have the experience in carrying out such activities, but also have a better access with the people at the grassroots for effective implementation. II. TASKS 2. The NGO shall play a role of secondary stakeholder in implementation of the RP and in mitigating the adverse effects of the project. The NGO shall remain responsible for the development of a comprehensive livelihood system to facilitate the project affected persons DPs to take advantages of the options available as per the RP. The NGO shall assist PWD in ensuring social responsibilities of the KSHIP, such as, compliance with labour laws, prohibition of child labour, HIV/AIDS and gender issues. The main tasks of the NGO thus appointed will be: 1. Verification 3. All Verification has to be conducted jointly with local SDRC offices 4. The NGO shall undertake joint verification of the project affected persons and shall update the database on the eligible DPs and Displace households (DHs). The NGO shall verify the information already contained in the RP and the individual losses of the DPs and validate the same and make suitable changes if required. 5. During the identification and verification of the eligible DPs/DHs, the NGO shall ensure that each of the DPs are contacted and consulted. The NGO shall ensure consultation with the women from the DP households especially women-headed households. 6. Verification exercise shall include actual measurement of the extent of total property loss/damage, and valuation of the loss/damage/affect along with the SDO. The NGO shall display the list of eligible DPs in prominent public places like Panchayat Offices, Taluk and District Headquarters. 7. The NGO has to identify any DP, DH or community asset coming within the Right of Way after the cut-off date, and notify the same to the local SDRC office. The NGO shall through consultation remove the DP, DH or community structure from the ROW, and inform them that any project benefits do not apply to them.

224

2. Distribution of Identity Cards 8. After verification the NGO shall distribute Identity Cards to all Project affected persons. The identity card should include a photograph of the DP, the extent of loss suffered due to the project, and the choice of the DP with regard to the mode of compensation and assistance, with necessary household details. The Identity Cards are to be signed by the local Social Development office counter signed by the Assistant Director Social Welfare at PIU. 3. Consultation 9. The NGO shall educate the DPs on their rights, entitlements and obligations under the RP. It shall disseminate information to the DPs on the possible consequences of the project on the communities' livelihood systems and the options available, so that they do not remain ignorant. It shall explain to the DPs the need for land acquisition, the provisions of the policy and the entitlements under the RP. This shall include communication to the roadside squatters and encroachers about the need for their eviction, the timeframe for their removal and their entitlements as per the RP. 4. Prepare Micro Plan 10. The NGO shall prepare Micro plans indicating category of entitlement; alternate livelihood options; land identification; skill up gradation and institutions responsible for training. A separate plan has to be prepared for shifting of community assets. 5. Training and Support for income restoration 11. In addition to providing assistance given in the entitlement package, the NGO shall be responsible for training and assisting the DPs to establish linkages with government programmes. 12. The NGO shall train DPs losing their livelihood, in suitable income restoration programmes, depending on the skills and interest of the DPs. The NGO shall prepare individual Income Restoration Plan, as a part of the Micro Plan for all DPs whose livelihoods are getting affected. The NGO shall explore the potential of employment opportunities with the local contractors, and where ever possible ensure suitable employment with the contractors. This will include providing the list of people wiling to work under contractors and to facilitate these types of jobs to PDPs and local people; 13. NGO shall assist the DP to establish linkage with Financial institutions for facilitating access to credit. 14. Assist the DP to establish linkages with Government departments, district administration, etc., to ensure that the DPs are included in the development schemes, as applicable especially with reference to vulnerable groups such as pension schemes for Senior citizens, schemes for women for women-headed household households, widow pensions, schemes for handicapped persons etc. 15. Link up DPs to Training institutes for imparting skill and management training for enterprise creation and development. For those DPs who are interested in skill upgrading or training for economic generation programmes. 225

6. Disbursement of Assistance and delivery of entitlements 16. The NGO shall ensure that DPs obtain their full entitlements under the RP; to ensure benefits due to the DPs under the R & R policy and RP are provided to the DPs. Where options are available, the NGO shall provide advice to DPs on the relative benefits of each option. 17. The NGO shall assist the project authorities in ensuring a smooth transition helping the DPs to take salvaged materials and shift with proper notices. In close consultation with the DPs, the NGO shall inform the SDRC about the shifting dates agreed with the DPs in writing and the arrangements desired by the DPs with respect to their entitlements. 18. The NGO shall assist the DPs in opening bank accounts explaining the implications, the rules and the obligations of a joint account and how he/she can access the resources s/he is entitled to. 19. Ensure proper utilization by the DPs of various grants available under the R & R package. The NGO will be responsible for advising the DPs on how best to use any cash that may be provided under the RP. Emphasis should be placed on using such funds in a sustainable way e.g. purchasing replacement land for that acquired 20. The NGO shall ensure proper utilisation of the R & R budget available for each of the packages. It shall identify means and advise the SDO to disburse the entitlements to the eligible persons/households in a transparent manner and shall report to the SDRC/PIU on the level of transparency achieved in the project. 7. Grievance Redressal 21. The NGO shall make DPs aware of the grievance mechanism set out in the RP and shall assist PDPs who have grievances to pursue a suitable remedy. The NGO shall help the DPs to file a grievance application. 22. The NGO shall record the grievance and bring the same to the notice of the Grievance Redressal Committees (GRC) within 7 (seven) days of receipt of the grievance from the DPs. It shall submit a draft resolution with respect to the particular grievance of the DP, suggesting solutions, if possible, and deliberate on the same in the GRC meeting through the NGO representative in the GRC. 23. The NGO shall assist in the GRC process when ever necessary. 8. Identification of sites 24. As part of the RP, eligible AFs will receive alternative sites for residential and commercial structures getting affected. The NGO will identify with PIU and the Revenue Department suitable government land and assist in negotiating its transfer to the DP. Where suitable government land is not available, the NGO will assist the DP to locate a land owner willing to sell his land and will assist in the negotiation of the purchase price. 25. The NGO has to identify the need for Resettlement Centres in consultation with the project affected persons, according to the R & R Policy. In case the need arises, the NGO shall identify suitable site for the same. The NGO will have to develop Self Help Groups and impact skill training to the affected persons.

226

9. Coordination between DPs and the SDRC 26. The NGO shall develop rapport between the DPs and the SDRC. This will be achieved through regular monthly meeting with both the SDRC representatives and the DPs. All meetings and decisions taken are to be documented. 10. Conduct Public information campaign 27. The NGO shall assist the SDRC to undertake public information campaign at the commencement of the project to inform the affected communities of the project RP, the R & R policy and the entitlement package. 11. Conduct Gram Sabhas 28. The NGO shall ensure that gram sabhas (village level meetings) are held in every village. Besides contacting DPs on an individual basis to regularly update the baseline information, Gram Sabhas will be conducted by the NGO on a regular basis. The frequency of such meetings will depend on the requirements of the DPs, to allow the PDPs to remain up to date on project developments. NGO will encourage participation of individual PDPs in such meetings by discussing their problems regarding LA, R & R and other aspects relating to their socioeconomic lives. Such participation will make it easier to find a solution acceptable to all involved. 12. Report the Status of PDPs after shifting 29. The NGO shall submit a status report of the PDPs after shifting to the SDRC. 30. 13. Road Safety Awareness 31. The NGO shall conduct Road Safety Awareness to the children of schools and community at large in the villages located along the Project Roads by way of training, distribution of pamphlets and fixing of posters. 14. Assist the PWD in Actions to HIV/AIDS Awareness/prevention Campaigns/Gender/Child Labour 32. Information campaign/advertisement in collaboration with line agencies (such as National AIDS Control Organisation, State AIDS Control Organisation etc.) including provision of signage/hoardings at suitable locations, distribution of vechicle stickers and provision of condom vending machines at suitable locations (rest areas, truck parking lay-byes etc. The NGO shall assist the PWD to implement these measures including collaborating with line agencies. 33. The NGO shall ensure in collaboration with Engineer that Medical facilities and health checkups which may include detecting STD/AIDS for the workers are provided at the construction camps. 34. The NGO shall assist PWD to ensure that the Contractors comply with applicable labour laws (including prohibition of child labour) and gender issues. 227

III. CONDITION OF SERVICES 35. Two NGOs will be selected for implementation. One for North Karnataka and one for South Karnataka. No NGO should submit for more than one package. 36. The roads for RP implementation will provided to the NGO in a staggered manner. The time line for each of the links for RP implementation will be provided by the PIU. However, the ultimate end date remains the same 1.e two years from the start of signing of the contract. 37. The NGO shall ensure that the RP is implemented in an effective and proper manner. The prime responsibility of the NGO shall be to ensure that each and every eligible PDPs receive appropriate and due entitlement (within the Entitlement Framework). Additionally the NGO shall help the SDRC/PIU in all other matters deemed to be required to implement the RP in its spirit and entirety including activities involving some financial implications. 38. All documents created, generated or collected during the period of contract, in carrying out the services under this assignment will be the property of the SDRC/PIU. No information gathered or generated during and in carrying out this assignment shall be disclosed by the NGO without explicit permission of the SDRC/PIU. 1. Location of NGO 39. 35. In order to carry out the above tasks, employees of NGO are to be stationed in each division as identified by the PIU. Each division office shall have one key person along with support staff. 2. Reporting 40. Reports will have to be submitted, as well as photographs, videotapes etc., taken during the assignment shall be submitted in support of the reports, along with an electronic copy of the documents. All reports should be in English language only. The following documentation have to be submitted. (i) Inception Report 41. The NGO shall submit to the PIU/SDRC an inception report-detailing plan of action, manpower deployment, time schedule, and detailed methodology within 21 days of the commencement of the assignment. (ii) Monthly progress Reports 42. The NGO should also submit monthly progress reports on the activities carried out during that month and proposed activities for the coming month. The monthly progress reports will include data on input and output indicators as required by the SDRC, with work charts as against the scheduled timeframe of RP implementation. All progress reports shall include data on input and output indicators as required by the SDRC. 43. The NGO shall document in full details, the consultation/counselling processes, the process of identification of the resettlement sites, and a full description of the training imparted (or facilitated) as part of the assignment. The progress achieved in land acquisition as per

228 entitlements have to be documented. This documentation shall be submitted to the SDRC as a part of the monthly progress report. 44. Copies of the monthly report have to be submitted to (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC. (iii) Final Report 45. Submit a completion report at the end of the contract period summarizing the actions taken during the project, the methods and personnel used to carry out the assignment, and a summary of supports/assistance given to the DPs. (iv) Records of Meetings 46. All minutes of the meetings for GRC, gram sabhas, between SDRC and DPs etc have to be recorded and submitted to (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC. (v) Record of Grievances 47. All grievances have to recorded and the process of redressal documented and submitted to (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC on a monthly basis. (vi) Submission of Micro Plans 48. All micro plans have to be submitted, with the status of disbursement and payment of compensation, on a monthly basis. Where changes occur during the project requiring changes to the micro level plans, the NGO will update the relevant plans and resubmit them to the (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC.

3. Data, Services and Facilities to be provided by the Client 49. The SDRC/PIU will provide to the NGO copies of the RP, Social Assessment Report , DP database, land acquisition details, and any other relevant reports/data prepared by the Project Preparation Consultants. All facilities required in the performance of the assignment, including office space, office stationery, transportation and accommodation for staff of the NGO etc., shall be arranged by the NGO. 4. Time Schedule 50. It is estimated that the NGO services will be required initially for two years for participating in the implementation of RP. The NGO shall carry out all assigned tasks based on the milestones as set out by the SDRC. 5. Payment 51. All payments will be linked to the completion of tasks as per milestones. As the implementation will be done in a staggered manner, payment will be linked to the completion of links/contract packages, based on the timeline provided by PIU. 52. The payment schedule will be made against outputs as given below. Output Payment Schedule 1. After unequivocal acceptance of Letter of 10% Total Contract value. At the Award and submission of inception report end of 1st month form should be completed within 1st Month. commencement of the services. 229

With Bank Guarantee of 10% of Contract value. 2. a) Joint verification of Assets within Corridor 15% Total Contract Value. of Impact of all Packages information, dissemination and distribution of R & R Policy b) Issue of Identity card for eligible DPs should be completed within 6th Month 3. a) submission of Micro plan for Title Holders/ 20% Total Contract Value. Non Title Holder approval b) Disbursements for 50% of total PAHs. c) Final Data Analysis Report containing additional and or missing Census details. d) Identification of Relocation sites for shifting of DHs/CPRS. Should be completed within 12th Month 4. a) Submission of Micro plan for Title Holders/ 25% Total Contract Value. Non Title Holder approval b) Disbursement of entitlements for 50% of total DHs. Should be completed within 16th Month 5. c) Training and need assessment for income 15% Total Contract Value. restoration. d) submission of monitoring and evaluation schedule of DPs on the implementation of RP Should be completed within 20th Month 6. a) on approval of final report summarizing 15% Total Contract Value. the action taken and other resettlement works to be fulfilled by NGO b) Should be completed within 24th Month 53. Bank Guarantee of 10% Contract Value shall be valid up to time period specified in C 1.2.3 of Special Conditions of contract.

6. Team for the Assignment 54. The NGO shall depute a team of professionals to the site. The constitution of the team and the qualification for the team members is given below: Sl. No. Of No Position Qualification Positions . 1. Team Leader 1 The Team Leader should be a post-graduate, preferably in social sciences. S/he should have about 10 years experience in implementation of R & R and rural development works. S/he should have held responsible position in the previous assignments should possess participatory management skills. Knowledge of local language is a necessary qualification. The team leader must have been with the NGO for at least 2 years. In case of Joint Ventures the

230

Sl. No. Of No Position Qualification Positions . Team Leader must be from the lead partner 2. Key 5 Should be a post-graduate in social sciences. S/he Professionals should have about 5 years of working experience of which about 2 years in R & R or rural development projects. Should have sound understanding of the land acquisition process and experience in participatory management. Knowledge of local language is a necessary qualification. One key professional has to have a minimum qualification of Diploma in Civil Engineering. One key professional has to be a woman. One key professional should have about 10 years experience of working in community development and community awareness projects. Should have about 5 years experience in the field of HIV/AIDS. 3. Sub 1 for Should be graduate or equivalent in social sciences professionals every with at least two years field experience. Knowledge of 100 local language and experience of working in the region major desired, One – third must be women. impacted househol ds 4. Other support One support staff to be provided to each key Personnel professional 231

Annex 8

TERMS OF REFERENCE FOR MONITORING & EVALUATION CONSULTANTS FOR THE IMPLEMENTATION OF THE RESETTLEMENT PLAN

I. BACKGROUND

1.1. The aim of the project is to improve the performance of the State’s road transport sector. The KSHIP Stage II roads have been selected based on the Feasibility Study of State Roads for proposed KSHIP. The Asian Development Bank Assisted programme covers 650 kms of roads covering 20 links of 9 contract packages spread over in 15 districts. The up gradation and bypasses of roads will have direct /indirect impact on the population along the project corridor. Common property resources, residential structures, commercial structures are likely to be affected. Non-Titleholders within the ROW are likely to be displaced.

1.2. The proposed road improvement involves land acquisition, appropriation of structures and resettlement of squatters. The affected persons on account of the road improvements are covered under the Resettlement Plan (RP). All possible steps have been taken to minimize land acquisition and demolition of structures so as to reduce adverse affect on people settled along the road. Among others, the RP stipulates involvement of a consulting agency for monitoring and evaluation (M&E) of implementation of the RP, and compliance with the targets given in the RP.

1.3. It is in the background that the PIU/KSHIP intends to hire the services of a qualified and experienced external consultant to monitor and evaluate implementation of the RP being carried out by the PIU with the support of the NGO/s deployed.

II. OBJECTIVES OF THE ASSIGNMENT a. The objectives of the M&E consultancy services are (a) to assess the implementation of the RP; (b) to monitor the schedules and the achievement of targets; (c) to evaluate whether the outcomes of social development objectives of the project are being achieved.

III. SCOPE OF SERVICES

3.1. The CA will undertake to do the following assignments:

3.2 Undertake the supervision of RP implementation to ensure the delivery of entitlements to Project Displaced Persons/ Project Affected Persons in accordance with the provisions and procedures provided for in the Resettlement Plans.

3.3 Advise and guide the NGOs to implement the RP in accordance with their Terms of Reference; 3.4 To monitor the effectiveness and efficiency of PIU and NGO in the RP implementation.

232

3.5 To assess whether resettlement objectives, particularly livelihoods and living standards of the Displaced Persons ( DPs) have been restored or enhanced.

3.6 To assess the efforts of the PIU and NGO in ensuring 'Community Participation' with particulatr attention on participation of vulnerable groups namely a) those who are below the poverty line ( BPL);b) those who belong to scheduled castes ( SC), scheduled tribes ( ST); c) female headed households (FHH); d) elderly and e) disabled persons.

3.7 To assess resettlement efficiency, effectiveness, impact and sustainability, drawing both on policies and practices and to suggest any corrective measures if necessary.

3.8 To review the project impacts on Indigenous People and groups if any and assess the effectiveness of the mitigation measures adopted.

3.9 Assist the PIU and field units to oversee the implementation of RP;

3.10 Participate in periodical meetings held between PIU and NGOs/district administration to assist the PIU for successful outcomes of the meetings;

3.11 Undertake reviews on behalf of PIU of all documents and reports related to land acquisition and resettlement received from the NGOs and consultants and advise the PIU for taking appropriate decisions on such reports;

3.12 Assist the PIU to respond to the ADB on any matters related to the implementation of RP and related matters;

3.13 Provide certification prior to invitation of bid and at the time of handing over of the milestone stretches to the contracts confirming the completion of land acquisition, payment of compensation, mitigation of resettlement impacts and reconstruction of community properties in the respective stretches;

3.14 Ensure synchronization of R&R implementation with civil works time table to avoid time and cost over runs. This should be done in close co- ordination with the construction supervision consultants;

3.15 Assist PIU in reviewing any additional reports submitted by the consultants or NGOs during the implementation;

3.16 Prepare annual reports on the implementation of RP including land acquisition and payment of compensation;

3.17 Organization of periodical training in the implementation of RP and delivering of entitlements, consultations etc. to PIU staff and NGOs as necessary. 233

3.18 The consultant will carry out limited impact assessment twice during the contract period, one at the end of 15 months of the contract period and another at the end of 21 months of the contract period. Each evaluation will cover all Project Displaced Persons/ Project Affected Persons who have spent more than 6 months after receiving compensation or assistance or both.

3.19 For concurrent Impact Evaluation, the M& E Consultant shall:

Develop specific monitoring indicators for undertaking monitoring implementation of Resettlement Plans.

3.20 Review results of internal monitoring and verify through random checking at the field level to assess whether the objectives of resettlements have been realized, particularly the changes in the in the living standards;

3.21 Identify the strengths and weaknesses of the resettlement objectives and approaches and implementation strategies.

3.22 Review and verify the progress in resettlement implementation on the sample basis and prepare quarterly reports for the EA/ PIU and ADB.

3.23 Evaluate and assess the adequacy of compensation/ assistances given to the DPs/ PAPs and the livelihood opportunities and incomes as well as the quality of life of DPs/ PAPs after the project induced changes.

3.24 To evaluate and assess the adequacy and effectiveness of the consultative process with the affected DPs/ PAPs, particularly those vulnerable including the adequacy and effectiveness f grievance procedures and legal redress available to the affected parties, and dissemination of information about these.

234

3.25 Impact assessment is to be compared with the baseline values for key socioeconomic as given in the RP. If such information is not available information based on the same time of survey, has to be collected on recall basis;

3.26 to assess whether the compensation is adequate to replace the lost assets;

3.27 to assess how the compensation has been utilized;

3.28 assess the perceived benefits and losses of resettlement;

3.29 Assess the level of satisfaction of the various assets provided as part of R&R implementation;

3.30 Based on the impact assessment, suitable remedial measure are to be proposed for any shortcomings and;

3.31 Remedial measure if Project Displaced Persons/ Project Affected Persons are not able to improve their living standards.

IV REPORTING

The qualified and experienced external monitoring consultant will be responsible for monitoring of the R&R activities carried out by the EA/PIU and will submit quarterly review directly to ADB and determine whether resettlement goals have been achieved more importantly whether livelihoods and living standards have been restored/ enhanced and suggest suitable recommendations for improvement.

4.1 The CA shall submit the following reports: Inception Report with mobilisation details Quarterly Monitoring Reports Evaluation Reports (2)

Annual progress Reports Final Completion Report (containing implementation, experience and lessons learned).

All reports should be submitted in hard copy and soft copy in MS Word for easy transmission.

V METHODOLOGY

5.1 As a part of the proposal, the consultants will propose the methodology to carry out the assignment.

VI TIME LINE 235

6.1 The CA shall be hired for the period of project implementation that is 2 years.

VII BUDGET AND LOGISTICS

The proposal both technical and financial should be submitted and budget should include all costs and any other logistics details necessary for resettlement monitoring. Additional expense claims whatsoever outside the budget will not be entertained.

VIII QUALIFICATIONS

The qualified and experienced external monitoring consultants should have significant experience in resettlement policy analysis and RP implementation.

Proposals shold be submitted with relevant information concerning previous experience on monitoring of resettlement implementation and preparation of reports. In case of experts detailed CVs should be submitted providing the detils of the previous experience in monitoing and resettlement related activities.

IX TEAM FOR ASSIGNMENT

9.1 The CA shall deploy a team of which the positions and minimum qualification are stated in the following, with least one woman professional:

9.2Team Leader: S/he should be a post-graduate in social sciences with at least 10 years of experience in the field of social development and projects requiring land acquisition. (Experience in land Acquisition is mandatory) S/he should have monitoring and evaluation experience of more than 5 projects, and should have held responsible positions in the previous assignments including as team leader. S/he should have adequate managerial skill and should be conversant with the region and the regional language.

9.3 Sub-Professional I: S/he should be a graduate in social sciences with at least 7 years of experience in the field of social development and participating rural appraisal. S/he should

236

adequate knowledge of computers and should be conversant with the region and the regional language.

9.4 Sub-Professional S/he should be a graduate in statistics with II: good knowledge of computerized database development and management and should be conversant with the region and the regional language.

9.5 Sub-Professional S/he should be a graduate in civil III: engineering with at least 7 years of experience in construction/maintenance of National/State Highways. S/he should good knowledge of land measurement and should be conversant with the region and the regional language.

9.6 Support Staff: There should be an adequate number of support staff. They should be able to perform as asked be the members of the team. There should be a good mix of women and men.

9.7 Location of office The CA is required to have an office in Bangalore and in the field.

X. PAYMENT SCHEDULE

10.1 The payment schedule will be made against outputs as given below:

Sl. Output Payment No. Schedule 1. Inception Report : 20%

2. After submission of 2nd : 20% quarterly Report

3. After submission of 2nd : 30% Evaluation Report after 15 months

4. After submission and : 30% approval of Final Completion Report 237

Note1: In the Road Development Projects taken up by the KSHIP, Project Affected Households/ Persons will be more when compared to Project Displaced Persons as the affected people will be mainly Title Holders, Squatters, Encroachers, Tenants & workers & that the affected structures & lands will also be partial. Hence PAPs (Project Affected Persons) are included along with PDPs (Project Displaced Persons).

2. Serial numbers have been changed taking into consideration of the suggestions made