The presentation on EIA & EMP for Environmental Clearance of Konar Exp OCP (8.0 MTPA normative capacity/11.0 MTPA peak capacity & integrated non-coking coal washery of 7.0 MTPA) was made on 23.06.2016. The EAC, MOEF&CC noted following points/ raised queries.

SN Observation of EAC Reply/ Status 1. The proposal envisages  The TOR for Konar Expansion OCP amalgamation of Konar OCP and was issued with increase in project the Khasmahal OCP (sanctioned area from 520.93 Ha to 729.40 Ha. /granted individually earlier) followed by integration with the proposed  In the prescribed TOR, the EAC washery of 7 MTPA. That would desired that project proponent may involve correction in area from the explore the possibility of reducing present of 620.08 ha to 547.38 ha. forest land requirement by locating The documentation needs to be the washery & FBC plant in non- revised accordingly. forest land.

 The project area of Khasmahal OCP as per EC condition is 318.71 Ha & Konar OCP is 301.37 Ha. The combined area comes to 620.08 Ha. However, these project areas overlap with each other to accommodate the common external OB dump for the two mines (to the extent of 99.16 Ha).

 After deducting the common area, the net project area of Khasmahal OCP as per EC condition is 219.56 Ha & Konar OCP is 301.37 Ha. Accordingly net combined project area of existing project becomes 520.93 Ha not 620.08 Ha.

 In view of observations of EAC regarding reduced use of forest land to the extent possible, the project area was reworked including reduction in area required for future use & boundary rationalisation. This exercise led to reduction in proposed project area from 729.40 Ha (as per TOR) to 547.38 Ha (as given in submitted EIA & EMP).  The project area of 547.38 Ha, includes the common barrier

1 between Khasmahal & Konar quarries (26.94 Ha).  The present EIA & EMP document has been proposed with an area of 547.38 Ha. 2. The RO, MoEF&CC Bhubaneswar The copy of latest certified EC has inspected the Khasmahal Compliance report is enclosed at project on 23.08.2014 and Konar Annexure-I (Khasmahal) & Annexure- OCP on 04.09.2013. Another II (Konar). inspection for the Konar Expansion OCP was conducted on 17.06.2016. Certified EC Compliance report is awaited. 3. A large area has been occupied for The matter has been examined in light of external OBD and internal dump observations made by EAC. Please refer also of a height of 90 m above Annexure-III. ground level matching with a height of external OBD. Whereas, much area has been left as void of depth of 180 m. The Committee observed that the same needs to be re-worked with minimum land degradation for external OBD and in the form of mine void. 4. The washery proposal has been CCL Board has approved in its 437th tendered and the technology will be meeting on 20/21.02.2017 for setting up finalised as per the tender received. of 7.0 MTY Konar washery on Build-Own- The committee desired for Operate concept with freedom ofb submission of approval for the beneficiation technology i.e., technology to be submitted for dry/wet/combination of dry and wet. perusal of Committee. 5. The raw coal transportation from  Coking coal will be produced from mine will be as under:- seam-X & non-coking coal from seam VI/VII & VIII. (a) 1 million tonne coking coal from  CHP has been proposed near pit Konar washery by road approx. 8 km top to handle total coal production away. of this project. (b) 7 million tonne of non-coking coal  Non-coking coal @ 7.0 MTPA will from CHP to Konar washery by belt be fed into proposed CHP for conveyor and washed coal will be storage, reclamation and feeding to conveyed by belt conveyor to the non-coking coal washery. siding being made near the mine  The entire non-coking coal and would be loaded to railway produced from Konar Expansion OCP will be washed in proposed wagons through silo. The Committee 7.0 MTPA Konar washery. advised that the railway siding must  Washed non-coking coal from come up within 3 years i.e. matching Konar Washery will be conveyed by

2 with the production of the non-coking belt to railway loading silo at coal. proposed Konar siding.  RoM Coking coal @ 1.0 MTPA (- 100mm) will be transported to Kargali washery at about 9 km & washed coal despatch by rail from adjoining Kargali siding.

6. Action Plan along with the proposed The project will spend four crore towards budgetary allocation should be CSR this year for both Karo and Konar. submitted for issues during Public The action taken in respect of issues Hearing out of CSR Budget of Rs 400 raised in Public hearing is at Annexure- Lakhs as agreed. IV.

3 Annexure-III

Overburden Dump layout

As proposed in approved Project at the end of mining in 17th year of project life

NOTE

S L NO P A RT ICULAR SITE FOR FBC(30.00 Ha)

Acquisition under CBA

SITE FOR REJECTS (OVER OB DUMP) Proposed road diversion

+340 CHP LE GEND 9.2 Ha S L NO P ARTICULARS S Y M BOL

Godo Nala

Konar River

Konar River

Barkakana -Gom oh loop line REF. DRAWINGS

S L NO

Plate-IX

CENTRAL COALFIELDS LIMITED

4

As proposed in EIA & EMP after 18th year to 25th year.

2400W 2000W 1600W 1200W 800W 400W 0E 4 00E 8 00E 1200E 1600E 2 000E 2 400E 2 800E

3 600N 3 600N

NOTE

SL NO PARTICULAR SITE FOR FBC(30.0ha)

All values are in meters. 3 200N

Acquisition under CBA 3 200N + 310

+ 310 + 310 Proposed road diversion

PROPOSED S/S + 280

+ 250

2 800N 2 800N Ext Dump WASHERYWASHERY (+340) 19.0 Ha + 280 + 280

Internal Dump

W/S (+320) LEGEND 2 400N 2 400N SL NO PARTICULARS SYMBOL CHP + 250 1 BORE HOLE 2 GEOLOGICAL BLOCK BOUNDARY + 310 3 QUARRY SURFACE 4 SURFACE CONTOUR + 280 Godo Nala 5 FLOOR CONTOUR + 250 6 RAILWAY LINE + 220 + 280 7 SURFACE OF KHASMAHAL OCP

+ 250 + 310 8 NALA / RIVER 2 000N

+ 280 2 000N + 250 9

Railway acquired land + 190

Konar River + 310

+ 160 + 280

PROPOSED O.H. LINE FOR KONAR OCP-33KV 1600N

Konar River 1600N + 250

+ 220 Barkakana -Gomoh loop line REF. DRAWINGS + 190 + 130 SL NO PARTICULARS DRG NO + 160 1 PLAN SHOWING THE FINAL STAGE QUARRY POSITION RI-3/OC/001255 + 130 2 TOPOGRAPHICAL PLAN RI-3/OC/001249

3 PLAN SHOWING THE GEOLOGICAL MAP RI-3/OC/001218 1200N

1200N 4 LAND USE PLAN RI-3/OC/ 001261 5 WORKING PLAN SUPPLIED BY FIELD DATED 19/6/2014 5 EXISTING MINE PLAN FROM FIELD

Locati on of Silo Future Project

Approach/Coal transportation Road requirement

8 00N 8 00N

Plate-XVI

4 00N 4 00N

CENTRAL COALFIELDS LIMITED

RECAST OF KONAR EPR (8.00 MTY) J ob No.-341570

Landuse of corezone at the end of 18th year after rehandling 1:5000 1 of 1 2800W 2400W 2000W 1600W 1200W 800W 400W 0E 4 00E 8 00E 1200E 1600E 2 000E 2 400E 2 800E Regional Institute-III R 3 OC 0 0 1 2 5 4 1

5 As proposed after observations of EAC during meeting on 23.06.2016

NOTE

SL NO PARTICU LAR SITE FOR FBC(30.0ha) Al l val ues are in meters.

Acquisition under CBA

+ 310 + 310 Proposed road diversion

PRO PO SED S/S

+ 250

+ 280

+ 310 W ASHERY

+ 280

CHP LEGEND 9.2 Ha SL NO PARTICU LARS SYMBOL

1 BORE HO LE W /S 1.38 Ha 2 3 Q UARRY SURFACE Internal 4 SURF ACE CONTOUR Godo Nala 5 F LOOR CONTOUR 6 + 280 Dump 7 + 250 + 310 8 NALA / RIVER + 280 (+310) + 250 9

Konar River + 310

+ 280 PRO PO SED O .H. LINE F OR KONAR OCP-33KV Konar River + 250

+ 220 Barkakana -Gomoh loop line REF. DRAWINGS Internal SL NO PARTICU LARS D RG NO 1 PLAN SHOWING THE FINAL ST AG E QUARRY POSIT ION RI-3/O C/001255 2 T O PO G RAPHICAL PLAN Dump 3 RI-3/O C/001218 4 LAND USE PLAN RI-3/O C/ 001261 5 WO RKING PLAN SUPPLIED BY F IELD DATED 19/6/2014 (+220) 5

Plate-XVI

CENTRAL COALFIELDS LIMITED

RECAST OF KONAR EPR (8.00 MTY)

Landuse of corezone at the end of 18th year after rehandling

1 of 1 Regional Institute-III R3 OC 00 1 2 54 Dump rehandling at different stages

SN Stage Level with respect to Remarks adjoining ground RL 1 In 17th year at RL of dump at 340 m No re-handling. the end of at the end of mining mining (30 to 80 m above ground level). 2 In 18th to 25th RL of dump reduced 8.1 mmc OB removed from internal year as from 340 to 320 m dump to pack the eastern part of void. proposed in the after mining with EIA & EMP rehandling (5 to 70 m above ground level).

Reduction in void area from 105 Ha to 60.11 Ha. 3 In 18th to 25th RL of dump reduced Additional 8.2 mmc of OB removed from year as desired from 340 m to 310 m internal dump. by EAC after mining & 100 % 23.21 mmc OB removed from external rehandling of external dump. dump.(0 to 50 m 61.44 Ha of area earlier covered by above ground level) external dump becomes completely free with an average RL ranging from 320 m to 250 m (0 to 5 m above ground level).

6 Annexure-IV

Action Plan along with the proposed budgetary allocation for meeting the commitments on issues raised during Public Hearing

SN Name Question Asked Reply Action taken

1 Vikash Singh, All facilities should All facilities will be Employment to 93 land Village be given to raiyat provided to raiyat losers already given. who have given who have gave their Another 17 in process as Thermal their land. Cases land as per CIL R&R Policy. filed against provision of Facilities like water Lodharbeda company. All supply, street lighting, Villagers should be pollution control road connectivity, withdrawn. measures will be educational & medical All the measures definitely followed. facilities provided under for pollution control Respective CSR. described in department will do Yearwise CSR booklet should be inspection from expenditure:- followed. time to time. 2013-14: Rs 171.58 Lakhs 2014-15: Rs 224.30 Lakhs 2015-16: Rs 157.03 Lakhs All pollution control measures as per EIA & EMP will be followed. 2 Shri Sujit All the standard All pollution control Action taken for kumar pollution control measures standard tendering of four 28 kl Ghosh, measures will be implemented mobile mist type Gandhinagar mentioned in the and from time to sprinklers for dust booklet provided time its inspection suppression. during public will be done by Regular monitoring of hearing should be competent conditions of compliance followed. authority. will be done. Last inspection was done on 17.06.2016 by MoEFCC, Ranchi Regional Office. 3 Shri Proposed washery All new technique Wet processing with zero Bhagirath construction should will be used in discharge/ dry technology Prasad be in the form of proposed washery. will be implemented. Basic problems of Sharma, model washery. New washery would villagers like water Gobindpur Basic problem of be developed as supply, road. Health & panchayat villagers should not model washery.

7 be neglected. Villager’s rights will educational facilities etc not be neglected. will be provided under CSR scheme. Direct & indirect employment through contractual jobs & skill development programs have been initiated. 4 Shri Anant Verification work is Verification work of Employment to 93 land Lal Mahto, pending. First raiyat land is almost losers already given. Narayanpur verification work completed. Till now Another 17 in process as should be 81 jobs have been per CIL R&R Policy. completed. Job and given in lieu of Authentication of 13.18 compensation verified land. 12 Acres of 9 tenants by the should be given. other people have State Govt is in final After then only got placement. stage. Employment & mine expansion Verification work of compensation will be and washery Gair Majura land is given after construction work under process. authentication. should be started. There are many Otherwise we will claimant of single protest. land. There is delay in identification of original raiyat. But raiyats will surely get justice. 5 Shri Dashrath There should be Transportation of Separate road bypassing Ram Dhasi, separate road for coal from above residential area has been East, coal transportation. proposed coal identified for coal panchayat Local people are washery will be transport in short term. suffering from through conveyor The quantum of road many types of belt. Therefore, it transport of coal is diseases due to will cause almost expected to be reduced pollution. There negligible air to about 1 MTPA from should be pollution. present 2.7 MTPA. arrangement for Arrangement of Coal transport @ 7 MTPA appropriate treatment of local is proposed by belt treatment of them. people is ensured in conveyor and rail. CCL hospital. 6 Shri dilip Konar project Facilities of all types Employment to 93 land Yadav, opened in 2012 but are being given to losers already given. Jaridih Bajar still displaced, villagers nearby the Another 17 in process as

8 unemployed projects. CCL has CIL R&R Policy. youngsters did not made arrangement Authentication of 13.18 get anything. We for different types Acres of 9 tenants by the oppose expansion of training and State Govt is in final of project and education to stage. Employment & washery unemployed youth. compensation will be construction. First, given after people should get authentication. their rights Direct & indirect thereafter washery employment through construction and contractual jobs & skill project expansion development programs should be done. have been initiated. 7 Md. Hayat In lieu of land, 81 Jobs was given and Employment to 93 land Ansari, people have been proposed to only losers already given. Barwabeda placed and those people whose Another 17 in process as employment will be land have been per CIL R&R Policy. given to 110 verified. If more Authentication of 13.18 people. This is land is verified, then Acres of 9 tenants by the unjustified. CCL is jobs will also State Govt is in final cheating us. increase. stage. Employment & compensation will be given after authentication. Major part of project area is forest land, so scope of employment is limited. 8 Shri Amrit Survey work is According to As per Companies Act, Mahato, under process in company provisions, 2% of retained profit or Baidkaro Baidkaro. CCL jobs & Rs 2/tonne production of Basti should give 10% of compensation are previous year is spent their profit to being given to under CSR activities. raiyat. raiyat. 9 Shri Chedi Earlier, in phase-II Job was given with Employment to 85 land Mahato, 14 people were different rules in losers was given in Ph-II Govindpur given employment different time. Now under one time without verification verification process agreement in 1980. of land. But we are has become Besides this, employment asked for necessary. to 93 land losers already verification of land According to given in K. Another 17 in is necessary to get company provisions process as CIL R&R

9 job. How many job is provided to Policy. local people will get one people for two Authentication of 13.18 job after washery acres. Acres of 9 tenants by the construction? It State Govt is in final should be disclosed stage. Employment & first. compensation will be given after authentication. Major part of project area is forest land, so scope of employment is limited. 10 Shri Thakur Assurances were Jobs can not be Employment to 93 land Mahato, given to us earlier given for land losers already given. Kurpaniya also. Raiyat are falling outside mine Another 17 in process as Basti wandering here lease area. Jobs will per CIL R&R Policy. and there due to be provided against Authentication of 13.18 pending only that verified Acres of 9 tenants by the verification. Our land which will be State Govt is in final agricultural land use by company in stage. Employment & has become the coming next five compensation will be unfertile due to years. given after Konar project. CCL authentication. authority said that Major part of project area all those land does is forest land, so scope of not come under employment is limited. our leasehold area. Job can not be given for that land. 11 Smt. Sugiya From many years In the year of 2009 Employment to 85 land Devi Harijan our ancestors are losers was given in Ph-II tola, Jaridih doing agriculture government issued under one time Basti on this land for a letter according to agreement in 1980. their livelihood. But which if any family Besides this, employment forest department has been using any to 93 land losers already claims their right land for their given in Konar Exp OCP. on that land. In livelihood for 30 Another 17 in process as this way we will not years and if papers CIL R&R Policy. get jobs. Our of that land is Authentication of 13.18 problems should available with raiyat Acres of 9 tenants by the also be considered. then that land can State Govt is in final be recognized as stage. Employment & raiyat land after compensation will be

10 investigation from given after additional district authentication. collector committee. Major part of project area is forest land, so scope of employment is limited. 12 Shri Basudev It should be Ownership right of If Mahato, clarified whether notified land is with verification/authentication Lodarbheda Gairmajrua land of forest department. of Gairmajrua khas, aam, Kurpaniya, Jaridih, If verification and jungle jhadi is in Lodarbheda process of favour of raiyat then villages belongs to Gairmajrua khas, ownership rights of land raiyat, state aam, and jungle belongs to raiyat. government or jhadi is in favor of CCL gives employment & CCL. raiyat then compensation against ownership rights of authenticated land @ 1 land belong to employment for every 2 raiyat. CCL can use Acres. only transferred land for coal mining. 13 Shri Jugal Raiyat have not got Documents related Employment to 85 land Kishore anything in lieu of to acquired land losers was given in Ph-II Mahato. earlier acquired should be submitted under one time Bermo Basti land. Bokaro in regional office. If agreement in 1980. colliery hospital all documents found Besides this, employment was converted into true, then job and to 93 land losers already school. compensation will given in K. Another 17 in Unemployed be given as per process as CIL R&R people are not company law. Policy. getting Authentication of 13.18 employment. Acres of 9 tenants by the State Govt is in final stage. Employment & compensation will be given after authentication. Major part of project area is forest land, so scope of employment is limited. 14 Md. Mine should be After land Jobs and compensation Kamaluddin, expanded. Coal verification jobs and will be given as per CIL

11 barwabeda washery should be compensation will R&R Policy/ company constructed but be given according rules after land raiyat should get to provisions of verification. their right. company. Direct & indirect employment through contractual jobs & skill development programs have been initiated. 15 Shri Idrish We don’t have any Land verification is Jobs and compensation Ansari, problem from under process. After will be given as per CIL Barwabeda washery land verification R&R Policy/ company construction but jobs and rules after land raiyat should get compensation will verification. theirs right. Jobs be given to raiyat. Direct & indirect should be given employment through after land contractual jobs & skill verification. development programs have been initiated. 16 Md. Lateef In school no fees CCL established CCL establishes schools & Ansari, relaxation is given school have quota also gives aid to schools, Govindpur to rural children. for rural and poor in which there is quota panchayat No treatment is children. There is for rural and poor given to poor provision under CSR children. people in hospitals. for treatment of There is provision under All facilities should poor villagers. CSR for treatment of poor be given to local There is separate villagers. There is villagers. room for it in separate cell in the hospital. hospital for this purpose. Medical camps are also held in rural areas in which free consultation & medicines are supplied. Expenditure on medical services during 2014-15 was Rs 8.94 Lakhs & in 2015-16 Rs 4.19 Lakhs under CSR. 17 Smt. Farhat We want expansion List of 1060 Only 2 villages namely Bano, of mine. But all displaced people is Barwabera & mukhiya, villagers should get prepared from five Basti are proposed to Bermo west their right. List of villages. It will be rehabilitated in which 685

12 panchayat displaced people is checked again and families will be shifted for not correct. It if any family left which provision of Rs should be rectified. then it will be added 63.18 Crore has been to list. kept. Identity cards are being issued to PAFs for this purpose. 18 Md. Ahmad Job and All documents Job & compensation to Hussain, compensation to related to above the raiyats is provided as Bermo Basti. raiyat was not land with per the authentication by given for 12.5 acre application should State Govt including GM land in Khata no 65 be submitted in land. and 50 Decimal regional office and Identity cards are being land in Khata no should be sent to issued to displaced 35. It is told that Circle officer office families. above land is for verification The land will be Gairmajrua as purpose. CCL is reclaimed after mining survey was not making identity card period of 17 years and done here. Mining for displaced people thereafter handed over to should be of Konar. Govt as per prevailing expanded and statute. washery should be constructed but we should get our rights. After mining land should be reclaimed and should be returned to raiyat. Displaced people should get displacement certificate. 19 Md. Liyakat Documents of All documents Employment to 85 land ansari, Muri Govindpur provided by raiyat losers was given in nagar displaced people have been sent to Govindpur. Any further are deposited with circle office for claim will be considered CCL. They should verification. After after verification. get jobs and verification we will compensation. start process for Verification process giving jobs and should be compensation. completed soon.

13 Raiyat should get their right. 20 Smt Chinta For the Jobs and All pollution control devi. Zila development of compensation is measures as per EIA & parshad country mine given to displaced EMP will be followed. member should be raiyat as per Regular monitoring of number-7 expanded and provision of the conditions of compliance washery should be company All will be done. Last constructed. standard pollution inspection was done on Displaced people control measures 17.06.2016 by MoEFCC, should get mentioned will be Ranchi Regional Office. compensation in followed perfectly. lieu of land. All It will also be standard pollution inspected from time control measures to time. mentioned should be followed perfectly. 21 Shri Kashi Whoever is present Verification work is Job & compensation to Nath Kevat, in public hearing getting delayed. the raiyats is provided as Chalkari basti don’t want to One of the reasons per the authentication by oppose for delay in State Govt including GM construction of verification work is land, which sometimes washery, expansion that since last 6 gets delayed. of mine but earlier months’ circle Presently, the rate of displaced people officer was not compensation has been didn’t get their posted in Bermo enhanced & current rate right yet. district. Work was is Rs 8.0 to 9.0 Lakh per Verification work is managed by giving Acre. pending. Circle charge. Apart from officer should visit this many claimants villages for had come through expediting the fake documents for verification a single land. process. Cases on Inspection is being Lodharbeda raiyat done carefully so should be that any legitimate withdrawn. The claimant not left ownership rights behind and should be given to illegitimate not get general category the benefit. This raiyat and tribal work will take time.

14 raiyat who have Original raiyat will occupied land from get their rights. more than 75 years Compensation is and 25 years fixed by respectively. 30-40 government. thousand per acre of land compensation is very less. Compensation amount should be increased. 22 Shri Manoj Here raiyat are Land verification Employment to 85 land Singh Pawar, facing two types of work is under losers was given in Ph-II Gandhinagar problems. One is of progress. under one time land verification Instruction have agreement in 1980. and another is of been given to CCL Besides this, employment pollution. It should executives for to 93 land losers already be taken care off. pollution control. given. Another 17 in Pollution control process as per CIL R&R measures will be Policy. followed strictly. Authentication of 13.18 Acres of 9 tenants by the State Govt is in final stage. Employment & compensation will be given after authentication.

Major part of project area is forest land, so scope of employment is limited. 23 Shri Suraj There should be One job is given for Issue of identity cards Mahato, clear description of every two acre of has started. Pichri forest department land. Employment Employment to 85 land Panchayat land and raiyat will be given to losers was given in 1980. land in Konar every village as per Besides this, employment project. land acquired from to 93 land losers already Clarification should village after all land given. Another 17 in be given about owners are being process as per CIL R&R number of jobs identified. This is Policy. village wise. Case one of the Authentication of 13.18

15 on Lodarbheda important reason of Acres of 9 tenants by the villagers should be delay in verification State Govt is in final withdrawn. Physical process. Process of stage. Employment & verification of land issuing identity compensation will be should be done in cards to displaced given after presence of persons of Konar authentication. villagers so that has begun. . original owner of land can be identified. Konar project may be expanded but tenants must also get their due. 24 Shri Verification of Verification work is Issue of identity cards Dhaneswar earlier acquired under progress. has started. Mahto, land is still Instructions have Financial provision of Rs Jaridih Basti pending, it should been issued to CCL 27.28 Crore has been be done. Pollution management for made for pollution control level has increased decreasing measures. Tender for in the area. pollution. All purchase of equipment Pollution control pollution control already initiated. measures should measures will be Separate road bypassing be implemented. strictly followed. residential area has been Due to absence of identified for coal Nallah near transport. roadside all dust The quantum of road particles are transport of coal is getting deposited expected to be reduced in our field with to about 1 MTPA from water. present 2.7 MTPA. Balance coal transport is proposed by belt conveyor to washery & beyond by rail. 25 Md. Villagers are Konar project Issue of identity cards Saffiuruddin, getting benefited expansion and has started. Barwabeda due to start of washery Employment to 178 land Khasmahal project construction will losers was given in past. but benefit has not definitely give direct Another 17 is in process reached to all or indirect as per CIL R&R Policy. villagers. Forest employment to Authentication of 13.18

16 department is nearby villagers. Acres of 9 tenants by the making their claims Land is getting State Govt is in final on land which was verified. It will be stage. Employment & used by our established after compensation will be ancestors from verification whether given after many years. land is of forest authentication. Washery should be department or constructed, mine raiyat. If it is found should be to be of raiyat then expanded, but we job and villagers should get compensation will justice. be given to them as per provisions of the company. 26 Shri Kamlesh Pain of displaced is There is definitely Issue of identity cards Tiwari, clearly reflected in delay in verification has started. MP nominee. public hearing. process. Verification Employment to 85 land There is anger in work has to be losers was given in 1980. them due to done as per rules Besides this, employment pending verification and within the to 93 land losers already of earlier acquired boundaries of law. given. Another 17 in land. Konar project Multiple claimants process as per CIL R&R expansion, washery of single land and Policy. construction is lack of manpower in Authentication of 13.18 necessity of the departments Acres of 9 tenants by the country but feeling dealing with State Govt is in final of displaced person verification process stage. Employment & should be are main cause of compensation will be respected. They this delay. Still full given after should not be effort is being made authentication. deprived of their with available rights; it should be resources for early taken care off. completion of Verification work verification process. should be It is also ensured completed within that injustice should time so as to give not be done to job and anybody and rights compensation to are given to raiyat as everybody everybody. who is present in public hearing is in

17 favor of project expansion and washery construction.

*******

18