<<

Introduction: Recent Structures in India

In anticipation of the forthcoming IABSE Symposium in southern-most continent, Antarctica. Back on the Indian Kolkata in September 2013, this special issue of Structural subcontinent and aboveground, the last two present Engineering International presents a series of projects in or a light-weight, double layered cable-net roof system for the related to India. As varied as the country itself, the follow- retrofit of a swimming facility, as well as a 10 km-long infra- ing eight technical papers present structures ranging from an structure project in the technology hub of Bangalore. underground cavern to a research station in Antarctica. The Indian Group of IABSE is looking forward to welcom- In the first —and highlighted on the front cover—the ing delegates to the 36th IABSE Symposium, in Kolkata from new terminal of the Mumbai airport is described, 24 to 27 September 2013 entitled “Long Span Bridges and including the elaborate roof and wall system. This is followed Roofs—Development, Design and Implementation”. More by two projects in and around New Delhi: a new signature information on this symposium, as well as other upcoming cable-stayed bridge with its backwardly inclined pylon and IABSE events can be found on the IABSE website under the addition of a cable roof system for the retrofit of a sta- www.iabse.org/Events. dium. A brief history of landmark bridges constructed over major rivers in India and the challenges faced in their con- B. C. Roy, Vice-President of IABSE, Chair of Scientific Committee struction is then elaborated. Next, the of one of 2013 IABSE Symposium in Kolkata of the world’s deepest caverns for the storage of liquefied petroleum gas in Visakhapatnam is detailed, followed by a Ann Schumacher, Editorial Board, description of the new Indian research station on the world’s International

Chhatrapati Shivaji International Airport—Integrated Terminal Building

Charles Besjak, SE, PE, Director; Preetam Biswas, PE, Associate Director; Alexandra Thewis, PE; Raymond Sweeney; Damayanti Chaudhuri, PE; Skidmore, Owings & Merrill LLP, New York, NY 10005, USA. Contact: [email protected] DOI: 10.2749/101686613X13363929988296

Abstract an overall truss depth of only 4 m. In and domestic operations at one of the response to site constraints and prox- busiest airports in India in order to The new Integrat ed Terminal Building imity of the existing operational ter- achieve 24-h utilization. This 410 000 m2 a t Mumbai’s Chhatrapati Shivaji minal building, the mega-columns are terminal building is being constructed International Airport combines inter- also designed to serve as hoist mecha- at the location of the existing terminal national and domestic operations at nisms s uch that the entire roof can be with minimal disruption to its opera- one of the busiest airports in India. constructed without tower cranes. The tions. An international consultant with 2 The 410 000 m building, being con- Terminal Building also includes the vast experience in designing airport structed at the site of the existing largest and longest cable wall system terminals around the globe was chosen terminal, will achieve a capacity of in the world. The structural studies as the principal and engineer 40 million passengers per annum upon completed include solid finite element for the new building. One of the largest completion in 2014. analysis of connections to optimize construction firms in India was chosen The primary design feature of the efficiency. Furthermore, the as the local designer and general con- building is a long-span roof covering a structural design prioritizes modular tractor for the project. The Terminal total of 70 000 m2 over various func- construction for economy and facili- Building is being constructed in phases tional requirements, making it one of tation of an accelerated construction where Phase 1 includes c onstruction of the largest roofs in the world without schedule. the western pier, and Phase 2 includes an expansion joint. The Headhouse Keywords: airport terminal; long-span c onstruction of the Headhouse zone. Roof, supported by only 30 columns roof; unidirectional cable wall; struc- Upon completion of Phases 1 and 2, spaced at 64 m in the North–South tural efficiency; phased construction. the building will become operational direction and at 34 m in the East–West and Phase 3 will commence, which direction, produces a large column- Introduction consists of the of the exist- free space ideal for an airport. By ing terminal building and the construc- increasing the depth of the trusses near Mumbai International Airport Limited, tion of the easte rn pier. Following the the columns and running trusses in owner-operator of Chhatrapati Shivaji completion of Phase 3 in 2014, the new both an orthogonal grid and a 45° grid, International Airport at Mumbai, is cur- terminal, shown in Fig. 1, will serve large spacing and cantilevers of 40 m rently building a new Integrated Termi- approximately 40 million passengers along the perimeter are achieved with nal Building that combines international annually.

8 Technical Report Structural Engineering International 1/2013 In order to create one of the largest roofs in the world without an expan- Future development sion joint, the roof mega-columns and roof structure were kept com- pletely independent from the base Arrivals structures below. Large forecourt openings in the concrete base struc- Headhouse: ture allow the mega-columns to pass departure, arrivals, immigration through as well as create architec- and baggage claim tural design features. This allows the Concourse, retail and Headhouse Roof structure to move baggage handling independently in response to loads, particularly expansion and contraction caused by temperature variation. This Pier gates thermal gradient is applied to the steel in the structural analysis model and accounted for in the design of the roof members. In response to the functional require- ment of the space below the roof, the entire Headhous e Roof is supported on just 30 composite mega-columns. Following requests from the client, the design team sought to minimize the number of columns in the depar- ture halls. However, the final design surpassed this constraint and resulted in a departure hall entirely free of columns through the use of com- posite mega-columns spaced 64 m in one direction and 34 m in the per- Fig. 1: Architectural renderings (clockwise from top left) plan view of integrated terminal pendicular direction. The structural building; approach roadway at departu re level; check-in con course; aerial view of system for the Headhouse Roof is integrated terminal building akin to a two-way flat slab system. Increasing the depth of the trusses near the columns and running trusses in an Owing to the scale and project occu- Long-Span Structural Steel orthogonal grid as well as along a 45° pancy, the client directive was to meet Headhouse Roof grid results in an overall truss depth of the requirements of the Indian codes 4 m for the roof system. The greater as well as satisfy requirements of the The primary design feature of the truss depths near the columns create International and American codes. Terminal Building is a long-span roof “column pod” areas which seamlessly This was achieved by evaluation of the covering the departures roadway, integrate into the pyramidal skylights most stringent conditions at all stages check-in hall, security, and passport that serve as major architectural fea- control functions. The architectural of design and analysis. Early in the tures. All of these aspects of the cladding of the roof and ceiling fea- design process, an evaluation of local Headhouse Roof can be seen in the tures a molded surface and sky- construction techniques, available structural model in Fig. 2 as well as in lights over the column locations and construc tion and availabil- the construction photographs of Fig. 4. ity of skilled labor played an impor- throughout the terminal ceiling, allow- tant role in the choice of the building ing natural light to flood into the main The lateral system for the Head hall. The Headhouse Roof, covering Roof comprises steel moment-resisting materials. Concrete was selected as 2 the primary building material for the 70 000 m and spanning over seven frames consisting of com posite mega- individual concrete base structures, is columns and long-span ste el roof base building, while steel was used for supported by only 30 composite mega- trusses. Frame action is achieved the structural of the roof in columns. Beyond typical gravity and between the primary roof trusses and order to achieve a lightweight system seismic loads on the roof, special load- the composite mega-columns in the with large column-free spaces. The ing considerations were taken for the North–So uth direction and between construction site of the new terminal cable wall which applies a significant the secondary roof trusses and the building is located within close prox- wind load to the roof structure and composite mega-columns in the Ea st– imity of the existing terminal that had whose cables are pre-stressed against West direction. Additional trusses to remain operatio nal during construc- the roof trusses at the northern end running at 45° to the orthogonal grid tion, which resulted in an elongated of the terminal. The wind loading also provide additional stability and dia- X-shaped plan utilizing repetitive, presented challenges as a significant phragm stiffness. The weaving of the modular designs that accommodate portion of the Headhouse Roof is orthogonal and diagonal trusses, in construction phasing and permit rapid open to the outdoors and behaves as addition to ensuring diaphragm action construction. a canopy. of the roof, was also extremely useful

Structural Engineering International 1/2013 Technical Report 9 (a) and von Mises stress gradients were obtained and studied to verify that no part of the connection exceeded the steel yield stress (Fig. 3b). The behavior of the 40 m tall canti- levered composite mega-columns was studied using nonlinear buckling anal- yses for each individual mega-column.

34 m The composite mega-columns consist Span of a built-up steel cruciform shape encased in 2,7 m diameter of concrete for the majority of its height. Once the column reaches the height of the column pod bottom chord connection, 64 m it transforms into a bare steel cruci- Span form shape and tapers to the column pod top chord connection (Fig. 4). 40 m Cantilever The P–M (axial-moment) interaction curve and stability analysis was per- formed for each segment of the col- (b) 4 m Truss depth 9 m Truss depth umn as well as for the overall stability of the complete mega-column system. These analyses were deemed neces- Waffle slab Roadway sary, because the code-prescribed design methods do not accurately

64 m Truss span 40 m Cantilever correspond to the behavior of these columns. Fig. 2: (a) Three-dimensional structural model of Headhouse Roof framing; (b) section through Headhouse Roof Unidirectional Cable Wall System in reducing the system depth for the multiple trusses. Nonlinear, solid finite entirely cantilevered perimeter zone of element analysis was carried out for Another unique feature of this pro- the Headhouse Roof. This resulted in the design of major connections for ject is the cable wall exterior clad- up to 40 m cantilevers at certain loca- optimum use of materials. The meshed ding system. The Terminal Buildin g tions with a truss depth of only 4 m. three-dimensional geometry of the features two separate cable wall sys- connections (Fig. 3a) was loaded at tems totaling over 1 km in length The orientation of the steel wide- 2 flange members of the trusses along the connection work point with forces and 11 000 m in area, making it the the orthogonal grid were rotated 90° directly obtained from the overall longest and largest cable wall in the such that flanges were aligned verti- Headhouse Roof analysis model. Rigid world. It includes a number of unique cally, while the steel members of the link elements from the work point features that create various challenges trusses along the diagonal grid were transfer the load to the connection in the design and detailing of the aligned with the flanges horizontally end faces (where the steel members structure. Both cable walls comprise for simplification of connections with are attached to columns, beams, etc.), unidirectional cables spanning verti- cally between two levels of the termi- nal structure. At the Departure Level, (a) (b) the use of unidirectional cables was necessitated by the fact that the cable roof completely envelops the terminal Headhouse, eliminating the possibil- ity of any horizontal anchorage points. In addition, as the cable wall circles 3D Von mises stress Contour plot the Headhouse, it crosses four inde- Element stresses Simple average pendent base structures and reduces 3,500E+05 in height from 15 to 6 m. Expansion 3,150E+05 2,756E+05 joints were installed in locations where 2,363E+05 the cable wall crossed separate struc- 1,969E+05 1,575E+05 tures to allow individual segments of 1,181E+05 7,875E+04 the wall to move independently. On 3,938E+04 the east and west sides, the cable wall 0,000E+00 No result spans to the cantilevered edge of the Max = 4,023E+05 (Global 374172) Headhouse Roof, up to 40 m from Min = 2,390E+03 (Global 383417) the nearest mega-column. The large Fig. 3: Three-dimensional solid finite element analysis model of column pod top node cantilevers result in significant deflec- connection: (a) three-dimensional finite element mesh of column pod top node; (b) fi nite tion at the roof edge, which proved element von Mises stress results of column pod top node (N/m2) to be a challenging situation. With

10 Technical Report Structural Engineering International 1/2013 the cables anchored to the roof, large roof deflections would cause a loss of pretension in the cables and failure of the system. As a result, a back-up sys- tem has been introduced consisting of composite columns cantilevered from the base structure below and intercon- nected with structural steel girders at the top and bottom of the wall. The cables span between these girders, and the top of the back-up system is later- ally supported by the Headhouse Roof above with dampers at composite column locations. This system allows for differential movements between the edge of the Headhouse Roof and the base structure without the loss of cable pretension. The various cable support conditions are highlighted in Fig. 5a and can be seen in the construc- tion photographs in Fig. 6. In addition to its size and length, the cable wall includes a number of fea- tures rarely seen in cable wall struc- tures. A large portion of the wall follows the curvature of the plan of the Headhouse Roof, a feature only achievable because the cable wall consists solely of vertical cables. At the two ends of the north portion of Fig. 4: Headhouse Ro of construction photographs: top, terminal buil ding panorama; the wall, there are absolute corners. Headhouse roof to left, May 2012; middle, Headhouse Roof over departure level road- The allowable deflection typical of way, February 2012; bottom, stages of column pod installation cable walls would have caused the two portions of the walls to collide

(a) 330 m at this location. To prevent this from occurring, the corner cables are rein- forced with horizontal stiffener plates Cable wall corner Expansion Expansion Cable wall corner connected between the cable and the condition joint joint condition 15 M High cable wall corner column of the back-up sys- with vestibules tem. Variations in height, changes in anchoring conditions, and the inclu- sion of corners, curves, and entrance

170 m 170 m vestibules all worked to necessitate a very prec ise design of cable preten- sion. Owing to the shape and scale of Variable height cable Variable height cable wall with backup system Expansion Expansion wall with backup system the Headhouse Roof and the cable joint joint wall, a wind tunnel study (Fig. 5b) was carried out to accurately determine Curved cable wall the cable wall cladding pressures as as clearstory well as the structural roof loads for 155 m the Headhouse Roof. After establish- ing the appropriate gravity and wind (c) loads, a finite element analysis model, as shown in Fig. 5c, was built includ- (b) ing the cables and support structure. Through a geometrically nonlinear static analysis, the deflection and axial force of each cable was determined. In locations where deflections exceeded L/50, the pretension force in the cable was increased, and cable diameters were selected to meet the axial force demands. A primary concern dur- ing the design of the cable wall was Fig. 5: (a) Cable wall plan and support conditions; (b) Headhouse Roof and cable wall preventing warping of the cable wall wind tunnel study model; (c) cable wall structural analysis model with back-up systems insulated glass units (IGUs). Warping

Structural Engineering International 1/2013 Technical Report 11 deck slabs in-filled between concrete moment frame systems. At all locations, the regular grid system has resulted in the repetitive use of concrete and economy in construction. Along the perimeter of the terminal, security requirements mandated cer- tain clearances between the build- ing and aircraft, as well as a vertical separation of departing and arriving passengers. To provide this separa- tion at the terminal while maintaining a single point of aircraft entry, steel fixed bridges connect the terminal to the aerobridges. The fixed bridges utilize a truss system along the edges with a minimal number of touchdown locations to provide maximum flexibil- ity below for airside traffic movement. Owing to the constraints of the site, the layout of the Terminal Building is such that areas with internal functions occur in the levels below the departures roadways adjacent to the Arrivals Hall. The roadway system therefore had to be isolated from the Terminal Building structural framing below to minimize vibration and to maintain acceptable acoustic levels in the occupied spaces Fig. 6: Cable wall construction photographs (clockwise from top left) varying-height cable below. The structural system for the wall with steel column back-up system; cable wall at entrance vestibule; departure level roadways consists of reinforced con- cable wall with column pod beyond; curved cable wall along cleresto ry zone; departure crete moment-resisting frames of the level cable wall connected directly to Headhouse Roof base building below in conjunction with pre-stressed, pre-cast reinforced occurs when the four joints of the provided optimal use of space for the concrete long-span I-beams supported rectangular glass units do not lie in baggage handling facilities. Meanwhile, on isolation pads. A cast-in-place rein- the same plane, and it can cause the the grid utilized for the Gate Zone forced concrete slab i nterconnects 2 the I-beams and acts as a diaphragm. seal between IGUs to break. Based was a 9 × 11 m continuous linear and Given that the roadway slab is exposed on the allowable shear deformation radial grid along the periphery of the to the elements, it was designed to of the IGUs, the out-of-plane deflec- building. allow for movement due to tempera- tion was limited to L/100, where L is The concrete base structure of the ture changes; the pre-cast I-beams are the shorter length of the rectangular Terminal Building employs three fixed at one end and free to slide at the unit. To prevent warping of the IGUs, distinct structural floor systems in other end. The roadway is exposed to the largest values of pretension are response to functional zon es with the elements and large temperature required in areas with sharp geometric varying optimal clear-span require- changes, but with interior space below changes, such as the vestibules and at ments. In the linear and radial Gate the roadway, expansion joints in the the wall corners. Based on these con- Zone, a regular, repetitive one-way roadway slab had to be water-tight. ditions, cable diameters vary from 25 concrete beam and slab system has To meet this requirement, these joints to 37 mm and pretension values range been utilized. At locations which gen- were located at 17 m intervals to mini- from 150 to 400 kN. erate heavy passenger congestion such mize the width of the joint. as the Baggage Claim Hall, functional Multiple System Concrete Base requirements called for a relatively The design of the parking structure Structure column-free space. This was achieved brought along a number of aesthetic by placing columns within the bag- and functional challenges. Designers The Terminal Building is divided gage claim belts and having a clear did not want an imposing structure, into the Pier and Gate Zone, Retail span between belts resulting in struc- but difficult geological conditions lim- Zone, Headhouse Roof Zone, and tural framing bays of 17 × 16 m2 and ited the depth of excavation. Working the Frontage Road Zone. Despite its employing a waffle slab system for within these constraints, the parking immense size, the Terminal Building the floor framing above. In the Retail structure utilizes a shallow floor fram- requires only two grid systems to cover Zone, where maximum flexibility for ing system with two-way concrete flat the entire footprint of the building. An floor openings and future renova- plate with concrete shear walls for lat- orthogonal 8,5 × 8 m2 grid was adopted tions was desired, the floor system eral support. The compact nine-level for the entire central facility, which utilizes steel framing with composite parking garage meets all of its parking

12 Technical Report Structural Engineering International 1/2013 requirements within the stipulated the phased construction was an height so that its roof aligns with the important consideration in select- SEI Data Block Departure Level and serves as a green ing the building’s structural systems. Owner and operator: roof for the visitor area. Construction of Phase 1 began in 2008 Mumbai International Airport Limited and was completed in early 2012. By Concluding Remarks Architect, , and MEP November 2013, both Phases 1 and 2 engineer: The design of the Terminal Building of the Terminal Building are expected Skidmore, Owings & Merrill LLP to be fully operational, and at that placed a high priority on material effi- Local designer and general contractor: time the remaining portion of the ciency and ease of construction. All Larson and Toubro Limited parts of the building utilized repeti- exis ting termina l is to be demolished tive, modular designs that accommo- and construction will begin on Phase Steel (t): Approximately 22 000 date construction phasing and permit 3, the gate areas on the eastern pier. Concrete (m3): Approximately 520 000 rapid construction. Ensuring the sta- Upon completion in 2014, the termi- Estimated cost (USD million): 1200 bility of the individual portions of nal will serve 40 million passengers the Terminal Building throughout per annum. Service date: November 2013

Structural Engineering International 1/2013 Technical Report 13