Tender: N.I.T. No. 12 /BSD of 2019- 20 by A.E./BSD 1. General Information

Type NIT Category Works Mode Method

District Inviting Authority Assistant Engineer, Bankura Sadar Sub- Division

76 / BSD dated Tender Id N.I.T. No. 12 /BSD of 2019- 20 by A.E./BSD Memo No Memo Date 12-02-2020 12/02/2020

Description N.I.T. No. 12 /BSD of 2019- 20 by A.E./BSD

Estimated Work Value -

2. EMD (Earnest Money Deposit) Details

Executive Engineer, Exempted? No Fee Type Payable To Bankura Division, Payable At Bankura P.H.E. Dte.

3. Critical Dates

Tender Publish Date 24-02-2020 05:10 PM Sale/Submission Start Date

Download Start Date Sale/Download End Date 06-03-2020 04:30 PM

Last Date of Application 03-03-2020 05:00 PM Last Date of Permission 05-03-2020 03:00 PM

Last Date of Submission 06-03-2020 04:30 PM Tech Bid Opening Date 06-03-2020 05:00 PM

Tech Bid Uploading Date Fin Bid Opening Date Time

Uploading Bid Date Time

4. Pre-bid Meeting Details

Date Venue Address

5. Work Details

Sl No Description Estimated Cost (Rs.) Completion Time EMD (Rs.)

Sinking of 1 no. 200 mm dia. X 6.0 Mtr. depth Horizontal River Bed Tube Well at of BHARA Water Supply Scheme under Bankura Sadar Sub- 1 453959.00 45 Day's 9079.00 Division, of Bankura Division, PHE Dte. (Flood damage fund / Emergency Fund ) (T/W -1)

Laying distribution system of UPVC pipe line at Fulberia Village & Bypass 2 arrangement of new CWR of pump house to rising main Under 495081.00 60 Day's 9902.00 Beliatore W/S Scheme of Bankura Division, P.H.E. Dte.

Construction of S.S.P including laying of P.V.C& UPVC pipe at Kusbona 3 Junior Vidyalaya to Kusbona kakurdanga village of G.P of - 270007.00 60 Day's 5400.00 W/S Scheme under BQA (HQ) of Bankura Division P.H.E. Dte.

Restoration & renovation 100 mm dia connecting line carring structure including all related works under Salma Water Supply Scheme under 4 424766.00 45 Day's 8495.00 Bankura Sadar Sub-Division, of Bankura Division, P.H.E. Dte. (Flood Damage Fund / Emergency Fund)

Construction of S.S.P including laying of UPVC pipe at different Places of 5 Mejia under Mejia PH II W/S Scheme of Bankura Sadar Sub- Division of 406375.00 60 Day's 8128.00 Bankura Division P.H.E. DteDivision P.H.E. Dte.

Replacement of UPVC pipe line for distribution system from Hatasuria more to Sorali with new pipe including Supplying, Laying, Fitting, Fixing and 6 Jointing due to widening & Strenghtening of Raagamati - Asuria - Dejuri 484774.00 60 Day's 9695.00 Road by PWD High way Division, Bankura under Bankura Division PHE Dte. (Emergency / Special Repairing Fund)

Drinking water supply connection (North ) coal mines Power Development Corporation Ltd. Barjora, Bankura of Barjora, 7 44667.00 45 Day's 1117.00 & II W/S Scheme under Bankura Sadar Sub- Division of Bankura Division, P.H.E. Dte. (Deposite Fund)

Extension of UPVC pipe line for distribution system Supplying, Laying, Fitting, Fixing and jointing from Talanjuri to Kendbedya under Talanjuri 8 OHR & Shifting of Rising Main (150 mm dia.) for Dadhimukha OHR due to 498789.00 60 Day's 9976.00 widening & strengthing of PMGSY Road under Bankura- I, II & Barjora W/S Scheme of Bankura Division, P.H.E. Dte.

Laying of UPVC pipe from NH-60 to post Office & Korar Bouri para including 9 construction S S P at G Ghati W/S Scheme of Bankura Division P.H.E. Dte. 321089.00 60 Day's 6422.00 (Maintenance Fund)

Laying distribution system of UPVC pipe line at Baguli more to Petrol pump of Molbona more , Indurjua more &Lowra boni more . One no Stand post 10 359059.00 60 Day's 7181.00 connection Barjora more to Santi maharaj house Under Barjora, Bankura I & II W/S Scheme (BRGF Ph - I) of Bankura Division P.H.E. Dte.

Distribution system of UPVC pipe line & installation of stand post including const. of platform and drain With all allied works from Near Heavy more 11 opposite site of Pettrol pump to Eye Hospital (Lions Club Bankura welfare 224393.00 60 Day's 4488.00 trust)& nearHeavy more Roy para , Bauri para under Bikhna W/S Scheme under Bankura Sadar Sub Division of Bankura Division PHE Dte.

Installation of stand post including const. of platform and drain, Croosing, interconnection With all allied works at Sanbandha (Sansad no. VIII & IX) & 12 499234.00 60 Day's 9985.00 Bejgram( Sansad no. X), Charbagpally under Ektesear (Zone - II) W/S Scheme under Bankura Sadar Sub-Division of Bankura Division, P.H.E.Dte. Construction of chlorin room & plinth protection for installation of gaseous chlorination systam at CWR-I, Godwn Side for improvement of 13 363797.00 60 Day's 7276.00 Bankura Sammilani Medical College & Hospitail Water Supply Scheme under Bankura Sadar Sub-Division of Bankura Division , PHE Dte.

Repair & renovation of laying distribution system of pipe line from Lokepur to Pharmacist college of Bankura Sammilani Medical College & Hospitai 14 Piped Water Supply Scheme due to 250 mm dia. DI pipe line laying from 165996.00 60 Day's 3320.00 Bankura Municipality under Bankura Sadar Sub-Division of Bankura Division , PHE Dte.

Construction of S.S.P including laying of PVC pipe at different Places of 15 Mejia under Mejia PH II W/S Scheme under Bankura Sadar Sub- Division of 459251.00 60 Day's 9185.00 Bankura Division P.H.E. Dte.

Laying of UPVC pipe line at Mejia Hospital Road includingt Culvert crossing 16 by M S Work & other allied work of Mejia (PH-II) Water Supply Scheme 489040.00 60 Day's 9781.00 under Bankura Sadar Sub-Division, of Bankura Division, P.H.E. Dte.

Installation of stand post including const. of platform and drain With all allied works for different habitation (Debipur Pry. School, Uparsole, Hir Village & Kapista) of Anchuri G.P. & Tentuldanga, Derua Village of Jagdalla 17 498797.00 60 Day's 9976.00 G.P. under Bankura - I Block under Bankura I, II & Barjora W/S Scheme (BRGF Ph -I Project) under Bankura Sadar Sub-Division of Bankura Division, P.H.E.Dte.

Interconnection with D.I. rising main to UPVC pipe line for main distribution OHR site , Zone -III OHR site, Zone -IB rising main OHR site , ,Zone -IV OHR site, Near BDO office Barjora & replacing D.I. rising main & distribution 18 system by new pipe including Supplying,Laying, Fitting, Fixing and Jointing, 483344.00 60 Day's 9667.00 including construction of sluice valve chamber, due to widening & Strenghtening of Road. under BARJORA W/S Scheme (Left out mouzas OF Barjora Block under BRGF phase-I for Zone-IA, I

Renovation and Repair of distribution pipe line from Barjora Charigora to Jagdaburi khota gora, Barjora central bank to Barjora BDO Office, Near Dejuri more, Dejuri village, Hatasuria Mansa Mandarboni, Hatasuria 19 Kotgram, Harirampur gram. due to damage of pipe line construction of 499517.00 60 Day's 9990.00 concrete road & laying of cable line under BARJORA W/S Scheme (Left out mouzas OF Barjora Block under BRGF phase-I under Bankura Sadar Sub Division of Bankura Division P.H.E. Dte.

Distribution system of UPVC pipe line from Sarali to Hat Ashuria Jilani Bag Jamia Islamia Education & Social Welfare Society & installation of stand post including const. of platform and drain With all allied works for 20 162017.00 60 Day's 3240.00 BARJORA (LEFT OUT MOUZAS OF BARJORA BLOCK UNDER BRGF PHASE-I) & its adjoining mouzas W/S Scheme within Barjora Block under Bankura Sadar Sub-Division of Bankura Division , PHE Dte. (Zone-III)

By- pass arrangement of D.I. rising main and distribution system and other allied work OHR & CWR of Zone -IV Under BARJORA (LEFT OUT MOUZAS OF 21 BARJORA BLOCK UNDER BRGF PHASE-I) & its adjoining mouzas W/S Scheme 427325.00 20 Day's 8547.00 within Barjora Block under Bankura Sadar Sub-Division of Bankura Division , PHE Dte.

Laying & fitting fixing of MS pipe line for By- pass arrangement of D.I. rising main and other allied interconnection work at Barjora Head work site 22 & Kadasole more under BARJORA W/S Scheme (Left out mouzas OF Barjora 309302.00 20 Day's 6186.00 Block under BRGF phase-I) for Zone-IA, IB, III & IV under Bankura Sadar Sub Division, Bankura Division P.H.E.Dte.

Laying & fitting fixing of MS pipe line for interconnection of D.I. rising main and other allied work for drain . crossing near Dena bank under BARJORA 23 W/S Scheme ( Left out mouzas of Barjora Block under BRGF phase -I) for 275803.00 20 Day's 5516.00 Zone-IA, IB, III & IV under Bankura Sadar Sub Division ,Bankura Division P.H.E.Dte.

Laying & fitting fixing of MS pipe line for interconnection of D.I. rising main and other allied work near Barjora traffic more under BARJORA W/S 24 260828.00 20 Day's 5217.00 Scheme (Left out mouzas of Barjora Block under BRGF phase-I) for Zone-IA, IB, III & IV under Bankura Sadar Sub Division, Bankura Division P.H.E.Dte.

Laying & fitting fixing of MS pipe line for drain crossing near Mohan pur village under BARJORA W/S Scheme (Left out mouzas OF Barjora Block under BRGF phase-I ) for bridge, culvert &drain crossing Under BARJORA 25 262947.00 20 Day's 5259.00 (LEFT OUT MOUZAS OF BARJORA BLOCK UNDER BRGF PHASE-I)& its adjoining mouzas W/S Scheme within Barjora Block under Bankura Sadar Sub- Division of Bankura Division, PHE Dte. (Zone - IA)

Supply laying & fitting fixing of MS pipe line for drain crossing near Ticor Gram village under BARJORA W/S Scheme (Left out mouzas OF Barjora Block under BRGF phase-I ) for bridge, culvert & drain crossing Under 26 323430.00 20 Day's 6469.00 BARJORA (LEFT OUT MOUZAS OF BARJORA BLOCK UNDER BRGF PHASE-I) & its adjoining mouzas W/S Scheme within Barjora Block under Bankura Sadar Sub-Division of Bankura Division , PHE Dte.(Zone - IA)

Installation of stand post including const. of platform and drain With all 27 allied works of Bankura -II Block under Bankura Sadar Sub-Division of 483535.00 60 Day's 9671.00 Bankura Division, PHE Dte.

Installation of stand post including const. of platform and drain With all 28 allied works of Barjora Block under Bankura Sadar Sub-Division of Bankura 482558.00 60 Day's 9651.00 Division, PHE Dte.

Guarding of Govt. materials by engaging guards for 24 hours of Office of 29 the Bankura Sadar Sub-Division, Bankura Division & PIU Circle Bankura PHE 493768.00 214 Day's 9875.00 Comlex, Bankura with effect from 01/04/2020 to 31/10/2020 (07 months) Sinking of 1 no. 200 mm dia. X 6.0 Mtr. depth Horizontal River Bed Tube Well at Bhara of BHARA Water Supply Scheme under Bankura Sadar Sub- 30 453959.00 45 Day's 9079.00 Division, of Bankura Division, PHE Dte. (Flood damage fund / Emergency Fund ) (T/W -2)

6. Attachments

Sl No File Name

1 Schedule (01 to 30).pdf

2 WBF_2911_28_Pages.pdf

3 Notice.pdf

4 Annexure- I.pdf