Lincoln Gap Local Business Briefing Session

Thursday, 19 April 2018 Introduction

 Project Overview  Project Organisational Chart  Stakeholders  Nexif Energy Australia  Australia  Timeline and Key Milestones  Opportunities for Business  Supplier engagement process  NACAP  CPP

 Questions

2 Project overview

• 59 wind-turbines • 10 MW grid scale battery storage • Located approximately 15km to the west of • Connect to a 275kV grid line managed by ElectraNet, running to the south of the project. • Operational in ~ 18 months • Lifetime of at least 25 years. • Will employ around 110 -130 people, and power around 155,000 homes.

• Stage 1: • 35 x 3.6M140 Senvion turbines • 126 megawatts generating capacity

3 Project Organisational Chart

Nexif Energy Australia Pty Ltd Lincoln Gap Wind Farm Pty Ltd

Principal Contractor Senvion Australia Pty Ltd

WTG Installation Transportation Balance of Plant (BoP) Contractor Contractor NACAP/CPP TBC TBC

4 Traditional owners – The Barngarla People

5 Stakeholders

. Land Owners and Land Managers . Local Community (with special attention to project neighbours, community living along construction routes and special interest groups) . Local Industry (manufacturers and suppliers) . Port Augusta Shire Council . Local State Member: Dan van Holst Pellekaan MP . Local media . Work Safe SA . ICN Gateway . ElectraNet Electricity Distribution . Civil Aviation Authority . Project Contractors and their Subcontractors , Project Consultants . Government Authorities such as Office of Environment & Heritage SA Environmental Protection Agency

6 Nexif Energy

• Nexif Energy is an independent “It’s important to us to have power producer (IPP) with power meaningful interaction with plants throughout South East Asia surrounding communities and and Australia to help create as many • Locations opportunities for involvement • Global head office in Singapore and education as possible.” • Australian business run out of Melbourne office • Site office in Port Augusta • Lincoln Gap Wind Farm is a first for Nexif: • First wind farm • First battery • First power plant in Australia • First large-scale power plant

7 Senvion

• Senvion is a leading global manufacturer of onshore and offshore wind turbines. With approximately 4,500 employees worldwide, the company makes use of the experience gained from the manufacture and installation of more than 7,500 wind turbines around the world. • Senvion Australia has been delivering wind energy solutions since 2002. Our people have the skills and expertise to safely design, build, operate and maintain wind farms. • The Australian team is also responsible for Senvion's presence in the Asia Pacific region, and has been active in the Japan market since 2003.

8 Senvion – global footprint

9 Footprint in Australia – since 2002

Total fleet 14 wind farms 367 turbines Over 900 MW operating or under Project Turbines Status

construction Coober Pedy (hybrid micro grid) 2 x MM92 Installed 2017

Lincoln Gap Stage 1 35 x 3.6M140 Under construction

NSW Project Turbines Status

VICTORIA Cullerin 8 x MM82 Installed 7 x MM92 2009 Project Turbines Status

Wonthaggi 6 x MM82 Installed 2005

Cape Bridgewater (Portland Stage 2) 29 x MM82 Installed 2008

Cape Nelson (Portland Stage 3) 22 x MM82 Installed 2009

Hepburn 2 x MM82 Installed 2011

Mt Mercer 64 x MM92 Installed 2014

Bald Hills 52 x MM92 Installed 2015

Chepstowe 3 x MM92 Installed 2015

Cape Sir William Grant (Portland Stage 4) 10 x MM82 Installed 2015 13 x MM92

Yaloak South 14 x MM92 Under construction

Crowlands 39 x MM92 Under construction

Murra Warra Stage 1 61 x 3.7M144 Under construction 10 Senvion Technology - 3.6M140 Strong performance and low noise impact

New Electrical • High flexibility to adjust to System future grid requirements

Proven • Evolution of proven drive- technology train from MM and 3XM

• New aero-acoustic add- Low noise ons

Efficient • Highly efficient 68 m blade

• Advanced management Advanced and control engineering control features

• Operational lifetime of 25 Long life years

11 Key milestones and timeline

Milestone Dates ENET Bench Jan – Feb 2018 Access Tracks Feb – July 2018 O&M Facility May – Oct 2018 275kV OHL May – Oct 2018 Generator (WTG) Installation August 2018 Energisation October 2018 Facility PC June 2019

12 Opportunities for businesses

 Cleaning and waste removal services  Support to Cranage and installation services  Fencing and landscaping services  Security services  Supply of materials for civil works  Survey and topographic services  Transportation

13 Supplier engagement process

• Register supplier details via ICN Gateway • Senvion Supply Chain Management (SCM) to contact supplier about available work packages • The scope of work will depend which process to follow • Smaller work packages, we will gather relevant information through our Supplier Engagement Questionnaire: • Supplier’s capabilities • Quality, safety and environmental compliance • Procedures for management review • ABN details • Larger work packages we require pre-qualification with CM3

Contact: Senvion Australia Supply Chain Management 03 8660 6555

14 LINCOLN GAP WIND FARM

LOCAL BUSINESS OPPORTUNITIES Agenda

• About Nacap • Local Business Work Packages • Vendor Assessment Qualification • Site Specific Considerations • Contact

About Nacap

• Leading Australian pipeline and civil construction contractor • Award winning safety systems • All projects delivered on time, within budget • Owned by Quanta Services - global infrastructure contractor & largest in Northern America

Local Business Work Packages

• Steel fixing • Concrete placement • Concrete pump supply • Cranage supply • Seeding

Vendor Assessment Qualification (VAQ)

All vendors will be assessed across 4 areas:

Area

Historical performance, system, process & Safety & Environment accreditation

Ability to supply materials/undertake works to Quality required technical standards

Ability to meet schedule requirements & HR Production outcomes incl. IR and employment Site Specific Considerations

• Experience working on large civil construction projects • Ability to work 11/3 roster including weekends

About Consolidated Power Projects • Industry leader in high voltage infrastructure • Design, construct and commission • We constructed the first grid connected wind farm in Australia

• Since then we’ve built more than 35 windfarms • 180 employees

21 What we do We partner with Australia’s largest renewable and power transmission utility companies to deliver large scale projects including:  Wind Farms  Battery Storage Systems  Solar Farms and,  High Voltage transmission substations

22 Work with us at Lincoln Gap Windfarm  Experience in large electrical infrastructure and civil construction environments  Work safely in a team  Work an 11/3 roster

23 Local Business Work Packages

 Cleaning and waste removal  Cranage and installation services  Electrical labour  Survey and topographic  Light transportation [email protected]

24 Contact

Jessica Kenny HR & Logistics Lincoln Gap Wind Farm Nacap [email protected] Questions?