Central Office:
• No. 8, 23rd St., Gandhi Ave., Tehran, IRAN • Zip Code: 1517936611 • P. O. Box: 15175-351 • Fax : +98 21 88777112 • Telephone : +98 21 88770138 +98 21 88778634 • Email : [email protected] • Website: www.iindco.com
2 Branch Office:
• Site 1, AZADI Street, Petrochemical Economic Special Zone, Bandar Imam Khomeini (MAHSHAHR), IRAN
• Fax: +98-652262-6194 • Phone: +98-652262-6315
3 Iran Industrial Networks Development Company (IIND) is a private joint stock company registered in Tehran on September 19th 1983.
. During the past decades IIND has been involved in numerous industrial projects, having a total capital investment of over 6.5 billion US Dollars. . Industrial works;IIND handles all categories of works which are required to install an industrial complex on EPC basis.
. IIND can participate in industrial projects in several ways such as: Lump- Sum Contracts, Sub-Contracts, Joint-Ventures, Turnkey and EPC Projects, Cost Plus, or even hourly rates for man power supply. We even recommend the most suitable type of contract to the clients by optimization of the economics of the project. . The quality of services rendered by IIND has always been the prime consideration of our management. Therefore to ensure superior quality and also to keep pace with the progress of technology as practiced by the well known contractors all over the world.
4 Services & Fields of Activities In Turn-Key Projects
• Feasibility Study of Industrial Plants
• Industrial Civil Building Works & their Utilities • Procurement and Inspection of Equipment (Mechanical, Electrical, Instrumentation, HVAC, etc.)
• Equipment Erection and Assembly
• Piping, Sandblast, Painting and Insulation
• Erection of Steel Structures
• Installation of Electrical Start - Up and Commissioning Activities
• Project Management and Staff Training
5 Equipment & Machinery
. Most of the equipment and tools which are utilized during the execution of our projects is owned by IIND, such as (for more detail see Equipment list at chapter 4) :
– High Capacity Crawler Cranes (205,160 Tons)
– Medium Size Cranes (20~80 Tons) – Small Size Cranes (3~10 Tons)
– Loaders
– Lift Trucks & Fork Lifts
– Tractors
– Compressor
– Diesel Generators
– Welding Machines
– Cars and Pick-ups
– Medium & Light transporting equipment
– Wrenches & Tools
– Portable Accommodation Facilities 6 7 Selected Reference Projects: At the beginning of this section a “List Of Selected Projects" is provided along with their Clients. A brief description of each project follows in the same order, after this list.
Dates Duration Item Code Subject MH Client Start End (Month)
South Pars Gas Development Phase 12 Under 1 K320 Apr. 2014 Ongoing 1,050,000 Petropars Co. (Metering Station) Process
South Pars Gas Development Phase 12 Under 2 K320 Sep. 2009 Ongoing 5,750,000 Petrpars Co. (EPC2) Process 3 K300 Isocyanate Project, Phase 1 Jun-04 Oct-07 40 4,290,000 Karoon Petrochemical Co. (NPC)
4 K290 PET2 Project Jul-03 Mar-07 44 7,500,000 Tondgooyan Petrochemical Co. (NPC)
5 K280 PTA2 Project May-03 Nov-05 30 4,600,000 Tondgooyan Petrochemical Co. (NPC)
6 K270 C2 Recovery, Gas Cracking Plant Aug-02 Nov-04 27 1,600,000 Marun petrochemical Co. (NPC)
7 K260 3rd Aromatic Production Plant Jul-01 Dec-04 42 7,900,000 Boualisina petrochemical Co. (NPC) Shahid Rajaei Combined Cycle Power 8 K240 May-00 Mar-03 35 1,600,000 Mapna Co. Plant Montazer Ghaem Combined Cycle 9 K230 Dec-99 Mar-01 15 350,000 Mapna Co. Power Plant 10 K220 Isfahan Poly-Acryl Expansion Jul-99 Oct-00 15 470,000 Poly acryl IRAN Bandar-Abbas Refinery (H-Naphtha, 11 K200 Jun-95 Jul-97 25 1,000,000 National Iranian Oil Co. (NIOC.) Hydro Cracker) 12 K190 Bandar-Abbas Refinery (Fired Heater) Nov-94 Jul-97 32 1,600,000 National Iranian Oil Co. (NIOC.) Bandar-Abbas Refinery (Kerosene 13 K180 Jun-95 Mar-97 21 900,000 National Iranian Oil Co. (NIOC.) Hydro Treated) 14 K170 Latif Paper Industry Nov-92 Jan-95 26 300,000 LATIF PAPER Co.
15 K160 Latif Paper Industry Nov-92 Aug-94 21 500,000 LATIF PAPER Co.
16 K150 Arak Refinery Jun-92 Feb-94 20 450,000 TPL SPA
17 K140 Baft-Balooch Nov-91 Oct-93 23 12,000 Faragir Baft Balooch Co.
18 K130 Arak Refinery Aug-91 Mar-93 19 600,000 Saipem S.P.A.
19 K120 Ahwaz Carbon Black Aug-91 Nov-94 40 2,500,000 National Petrochemical Company
20 K110 Mobarakeh Steel ( Cold Rolling Mill) Jan-90 Jun-91 17 400,000 NUOVA CIMIMONTUBI (SPA)
21 K100 Mobarakeh Steel ( Hot Rolling Mill) Jan-90 Jun-91 17 400,000 NUOVA CIMIMONTUBI (SPA)
22 K90 Mobarakeh Steel ( Steel Making Unit) Jan-90 Jun-91 17 400,000 NUOVA CIMIMONTUBI (SPA)
23 K80 Arak HEPCO Jan-90 Sep-91 20 120,000 HEPCO (Heavy Industries)
24 K70 Mobarakeh Steel Complex Sep-89 May-92 32 1,200,000 Mobarakeh Steel Complex
25 K60 Karaj Rolling Mill Mar-87 May-88 14 120,000 Rolling Mill Co.
26 K50 Shahid Montazeri Power Plant Oct-86 Mar-89 29 100,000 Tavanir Co. Saveh Casting Complex (Second 27 K40 Jul-86 Jul-87 12 55,000 Iran Casting Industries Co. Contract) 28 K30 Saveh Casting Complex Nov-85 Jan-87 14 95,000 Iran Casting Industries Co.
29 K20 Alborz Coal Washing Plant Sep-84 Aug-89 60 600,000 Ministry Of Mines & Metals
30 K10 Tabriz Textile Dec-83 Jun-84 6 25,000 Tabriz Textile Mill Corp.
31 K00 Baft-Balooch Nov-81 Feb-84 27 600,000 Faragir Baft-Balooch Textile Mill Co. GRAND TOTAL 47,087,000
8 South Pars Gas Field Development Metering Station
SOUTH PARS GAS FIELD Project Name DEVELOPMENT – Phase 12 Metering Station
National Iranian Oil Owner Company
Client Petropars LTD.
Contractor IIND
Project Location Assaluyeh - Tombak
Start Date April 2014
First Export May 2015
Export Capacity of 2500 cubic meter/Hour each skid Up to 45 bar
Man Power 1,050,000 Consumption
Percentage of 99% 9 Progress South Pars Gas Field Development Phase 12 – EPC2 (On Shore) (K320)
SOUTH PARS GAS FIELD DEVELOPMENT Project Name PHASE-12 EPC2 ONSHORE FACILITIES
Owner National Iranian Oil Company
Client Petropars LTD.
DSKI Consortium Contractor (Daelim, Sazeh, Kayson, IIND)
Project Location Assaluyeh - Tombak
Starting Date September 2009
First Feb. 2014 Production
• Sweet Gas: 3,000 MMSCF/D Plant Capacity • Condensate: 120,000 (Phase 12) barrels/D • Sulfur: 750 tons/D
Man Power 5,750,000 Consumption
Percentage of 10 99% Progress Isocyanate Project, Phase1 (K 300) (Karoon)
Project Isocyanate Project, Phase 1
Client Karoon Petrochemical co.
Mahshahr petrochemical Location free special economic zone
Starting Date Jun. 2004
Commissioning Date Oct. 2007
Mechanical installation of equipments, vessels, towers, steel structures, Scope Of Work piping, insulation and painting, electrical & instrument TDI 40,000 tons per year Nominal Plant MDI 40,000 tons per year Capacity HCL(33%)63,000 tons per year
Total Man Power 4,290,000 man-hour Consumption
Total Weight Of 6,835 metric tons Erection
Percent of Progress 100%
11 PET - Phase II Production Plant (K 290) (Tondgooyan) Project PET2
Shahid Tondgooyan Client Petrochemical co.
Mahshahr petrochemical Location free special economic zone
Starting Date Jul. 2003
Commissioning Date Mar. 2007
Mechanical installation of equipment, vessels, towers, Scope Of Work steel structures, piping, insulation and painting, electrical & instrument
132,000 T/Y Bottle grad Nominal Plant 132,000 T/Y Fiber grade Capacity 66,000 T/Y Poy 66,000 T/Y Staple
Total Weight Of 11,876 metric tons Erection
Total Man Power 7,500,000 man-hour Consumption
Percent of Progress 100% 12 PTA – Phase II Production Plant (K 280) (Tondgooyan)
Project PTA2
Shahid Tondgooyan Client Petrochemical co.
Mahshahr petrochemical free Location special economic zone
Starting Date May. 2003
Commissioning Nov , 2005 Date
Mechanical installation of equipments, vessels, towers, Scope Of Work steel structures, piping, insulation and painting, electrical & instrument
Nominal Plant Capacity 350,000 tons per year
Total Weight Of 9,649 metric tons Erection
Total Man Power 4,600,000 man-hour Consumption
Percent of Progress 100% 13 7th Olefin Project (K270) (Marun) th Project 7 OLEFIN PLANT
Client Marun petrochemical co.
Mahshahr petrochemical Location free special economic zone
Consultant Linde,EIED,sazeh
Starting Date Aug. 2002
Commissioning Nov. 2004 Date
Mechanical installation of equipment, vessels, towers, Scope Of Work steel structures, piping, insulation and painting, electrical & instrument
Nominal Plant 1,644,000 tons per year Capacity
Total Weight Of 20,727 metric tons Erection
Percent of 100% Progress
Total Man Power 1,600,000 man-hour Consumption
14 3rd Aromatic Project (K260) (Boualisina)
rd Project 3 AROMATIC PLANT
Client Boualisina petrochemical co.
Mahshahr petrochemical free Location special economic zone
PIDEC Consultant Managing contractor: engineers India limited
Starting Date Jul. 2001
Commissioning Date Dec. 2004
Mechanical installation of equipments, vessels, towers, steel structures, piping, Scope Of Work insulation and painting, electrical & instrument for para-xylene, orto-xylene and benzene production plant.
Nominal Plant Capacity 1,741,000 tons per year
Total Weight Of Erection 23,609 metric tons
Percent of Progress 100%
Total Man Power 7,900,000 man-hour Consumption
15 Montazer Ghaem & Shahid Rajaee Combined Cycle Power Plants (CCPP) (K 230) & (K 240)
Project Combined cycle power plant
Client Mapna
Montazer ghaem combined cycle power plant (Karaj – Location Iran)
Shahid Rajaee combine cycle power plant (Ghazvin – Iran)
Consultant Moshanir – Tehran -IRAN
M.G. Dec. 1999 – Sh.R. May Starting Date 2000
M.G. Mar. 2001 – Sh.R. Mar. Commissioning Date 2003
Mechanical installation of equipments, vessels, steel structures, piping, insulation Scope Of Work and painting, electrical and instruments works for the steam cycle of the power plant.
M.G. 125 mw – Sh.R. 3 x 125 Nominal Plant Capacity mw
Total Weight Of M.G. 1,500 – Sh.R. 9,000 Erection metric tons
Total Man Power M.G. 350,000 – Sh.R. Consumption 1,600,000 man-hour 16 Percent Of Progress M.G. 100% – SH.R. 100% Polyacryl Expansion Project (K 220)
Project New acrylic plant
Client Poly acryl IRAN
Location Isfahan – IRAN
Consultant Noyvalesina – Italy
Starting Date Jul.1999
Commissioning Date Oct.2000
Mechanical installation of equipments, vessels, steel structures, piping, insulation, painting, Scope Of Work electrical, instruments and pre-commissioning & commissioning of Acrylic Plant.
Total Weight Of Erection 2,000 metric tons
Total Man Power 470,000 man-hour Consumption
Percent Of Progress 100% 17 Bandar Abbas Refinery H-Naphtha Hydro-Cracker & CCR (K 200)
Project Bandar Abbas Refinery
National Iranian Oil CO. Client (NIOC.)
Location Bandar Abbas - IRAN
Chiyoda - Snamprogetti Consultant (Joint Venture) Bandar Abbas - Iran
Starting Date Jun. 1995
Commissioning Date July, 1997
Mechanical installation of equipments, vessels, steel structures, piping, insulation and painting of Scope Of Work heavy naphtha hydro- cracker and continuous catalytic reformer (CCR) Units in Bandar abbas refinery .
Nominal Plant Capacity 36,000 BPSD
Total Weight Of Erection 3,500 METRIC TONS
Total Man Power 1,000,000 Man-Hour Consumption
Percent Of Progress 100% 18 Bandar Abbas Refinery Fired Heaters (K 190)
Bandar abbas Refinery Project fired heaters
National Iranian Oil Client Company (NIOC.)
Location Bandar Abbas - IRAN
Chiyoda - Snamprogetti Consultant (Joint Venture) Bandar Abbas - Iran
Starting Date Nov. 1994
Commissioning Date Jul. 1997
Mechanical installation of th 8 refinery fired heaters Scope Of Work in two areas B & C of bandar abbas refinery.
Total Weight Of 6,000 Metric Tons Erection
Total Man Power 1,600,000 Man-Hour Consumption
Percent Of Progress 100% 19 Bandar Abbas Refinery Kerosene Hydrotreater (K 180)
Project Bandar Abbas Refinery National Iranian Oil Client Company (N.I.O.C.) - Tehran-IRAN
Location Bandar Abbas - IRAN
Chiyoda - Snamprogetti Consultant (Joint Venture)
Starting Date Jun. 1995
Commissioning Date Mar. 1997
Mechanical installation of equipments, vessels, steel structures, piping, insulation and painting of Kerosene Scope Of Work hydrotreater, LPG recovery, LPG treater LPG splitter and Amine treater in bandar abbas refinery . Nominal Plant 25,000 BPSD Capacity Total Weight Of 2,000 METRIC TONS Erection Total Man Power 900,000 Man-Hour Consumption Percent Of Progress 100% 20 Latif Paper Mill (Factory Equipment Erection) (K 170)
LATIF Paper Production Project Factory Equipment Erection
LATIF PAPER CO. - Tehran - Client IRAN
HASHTGERD INDUSTRIAL CITY Location IRAN
TARH-E-SANAT Co. - Tehran - Consultant IRAN
Starting Date Nov. 1992
Commissioning Jan. 1995 Date Installation of machines of a paper production unit. Paper plant, control room, Scope Of Work laboratory, compressed air center, steam production unit, tanks and pumps for chemical process of paper plant. Nominal Plant 10,000 TPY Capacity
Total Weight Of 1,100 Metric Tons Erection
Total Man Power 300,000 Man-Hour Consumption
Percent Of 100% Progress 21 Latif Paper Mill (Utilities Equipment Supply & Erection) (K 160)
Project Latif paper company
Client Latif Paper Company - Tehran -IRAN
Location HASHTGERD INDUSTRIAL CITY IRAN
Consultant TARH-E-SANAT Co. - Tehran- IRAN
Starting Date Nov. 1992
Commissioning Date Aug. 1994
Installation of mechanical and electrical works of Scope Of Work utility buildings and cabling of production unit.
Nominal Plant Capacity 10,000 TPY
Total Man Power 500,000 Man-hour Consumption
Percent Of Progress 100%
22 Arak Refinery (Insulations) (K 150)
Project 7'TH REFINERY ARAK
Client TPL SPA
Location Arak -IRAN
TPL SPA Consultant Tehran - IRAN
Starting Date Jun. 1992
Commissioning Date Feb. 1994
Insulation works of tanks, Scope Of Work vessels, piping, pumps and instruments .
Nominal Plant 150,000 BPD Capacity
Total Weight Of 100,000 SQUARE METER OF Erection INSULATION
Total Man Power 450,000 Man-Hour Consumption
Percent Of Progress 100%
23 Baft Balooch Textiles Dying Unit (K 140)
Baft Balooch Textile Complex Project (Drying Unit)
Faragir Baft Balooch Co. Client Tehran-IRAN
Iranshahr-Bampoor Road Location (Km5), IRAN
Technical office of the client - Consultant Tehran -IRAN
Starting Date Nov. 1991
Commissioning Date Oct. 1993
Erection / installation and commissioning of mechanical, electrical, Scope Of Work instrumentation, piping, painting and running test of the plant.
Total Weight Of Over 1,000 Metric Tons Erection
Total Man Power 12,000 Man-Hour Consumption
Percent Of Progress 100%
24 Arak Refinery (K 130)
Project 7'th Refinery Arak
Client Saipem S.P.A.
Location Arak - IRAN
Consultant T.P.L S.P.A.
Starting Date Aug. 1991
Commissioning Date Mar. 1993
off - site piping including above ground, under Scope Of Work ground, steam tracing piping and installation of tanks and vessels.
Nominal Plant Capacity 150,000 Bpd
Total Weight Of Erection 3,000 Metric Tons
Total Man Power 600,000 Man-Hour Consumption
Percent Of Progress 100%
25 Ahwaz Carbon Black Plant (K 120)
Project Ahwaz Carbon Black Extension
National Petrochemical Client Company (Subsidiary Of Ministry Of Petroleum)
Location Ahwaz-Mahshahr Road Km 4th
Petrochemical Industries Design Consultant & Engineering Company (PIDEC) - Shiraz - IRAN
Starting Date Aug. 1991
Commissioning Date Nov. 1994
Completion of the plant on A turn key basis including civil, mechanical, electrical, recycling of industrial sewage system, Scope Of Work fabrication of vessels and steel structures, piping, instrumentation works together with pre- commissioning and commissioning.
Nominal Plant Capacity 21,000 Ton / Year
Total Weight Of 2,500 Metric Tons Erection
Total Man Power 2,500,000 Man-Hour Consumption
Percent Of Progress 100%
26 10 Mobarakeh Steel Complex P. U. 53 (Cold Rolling Mill) (K 110)
Mobarakeh Steel Complex Project (Cold rolling mill)
NUOVA CIMIMONTUBI Client (S.P.A.)
75km.South West Of Location Isfahan-IRAN
Iran International Consultant Engineering (IRITEC) Co.
Starting Date Jan. 1990
Commissioning Date Jun. 1991
Installation of industrial piping from 1 up to 16 inches in elevations from +00 to +45 meters for Scope Of Work distribution of fluids in pu53 (cold rolling mill plant of mobarakeh steel complex).
Total Weight Of 3700 Metric Tons Erection
Total Man Power 400,000 Man-Hour Consumption
Percent Of Progress 100% 27 Mobarakeh Steel Complex P. U. 51 (Hot Rolling Mill) (K 100)
Mobarakeh Steel Complex (Cold Project rolling mill)
Client NUOVA CIMIMONTUBI (SPA)
Location 75km.South West Of Isfahan-IRAN
Iran International Engineering Consultant (IRITEC) Co.
Starting Date Jan. 1990
Commissioning Date Jun. 1991
Installation of industrial piping from 1 up to 16 inches in elevations from +00 to +45 meters Scope Of Work for distribution of fluids in pu07 (steel mill plant of mobarakeh steel complex).
Total Weight Of 400 Metric Tons Erection
Total Man Power 400,000 Man-Hour Consumption
Percent Of Progress 100% 28 Mobarakeh Steel Complex P. U. 07 (Steel Mill Plant) (K 90)
Mobarakeh Steel Complex Project (Cold rolling mill)
Client NUOVA CIMIMONTUBI (SPA)
75km.South West Of Isfahan- Location IRAN
Iran International Engineering Consultant (IRITEC) Co.
Starting Date Jan. 1990
Commissioning Date Jun. 1991
Installation of industrial piping from 1 up to 16 inches in elevations from +00 to +45 Scope Of Work meters for distribution of fluids in pu07 (steel mill plant of mobarakeh steel complex).
Total Weight Of 400 Metric Tons Erection
Total Man Power 400,000 Man-Hour Consumption
Percent Of Progress 100%
29 HEPCO Machine Manufacturing Plant (K 80)
HEPCO Machine Project Manufacturing
HEPCO Client (A Subsidiary Of Ministry Of Heavy Industries)
Arak Industrial Area Location IRAN
Bahleh And Stama Consultant (German Company)
Starting Date Jan. 1990
Commissioning Date Sep. 1991
Erection / installation of machinery, equipment, mechanical, Scope Of Work electrical, instrumentation systems, piping and commissioning. .
Total Weight Of Erection Over 1,000 Metric Tons
Total Man Power 120,000 Man-Hour Consumption
Percent Of Progress 100% 30 Mobarakeh Steel Complex (Raw Material Handling Yard) (K 70)
Mobarakeh Steel Complex Project (Raw Material Handling)
Mobarakeh Steel Complex Client (A Subsidiary Of Ministry Of Mines And Metals)
75km.South West Of Isfahan- Location IRAN
Iran International Engineering Consultant (IRITEC) Co.
Starting Date Sep. 1989
Commissioning May. 1992 Date Erection / installation and commissioning of machinery, equipment, mechanical, electrical, instrumentation Scope Of Work systems and utilities, piping, fabrication works, painting, sand blasting and running tests. . Total Weight Of 12,500 Metric Tons Erection
Total Man Power 1,200,000 Man-Hour Consumption
Percent Of 100% Progress
31 Karaj Rolling-Mill Plant (K 60)
Project Karaj Rolling Mill
Rolling Mill Co.(A Client subsidiary of the Ministry Of Heavy Industries)
Old Tehran-Karaj Road Location km18 - Iran
Starting Date Mar. 1987
Commissioning Date May. 1988
Installation of furnaces, moulding line consisting of machinery, equipment, Scope Of Work mechanical, electrical, instrumentation systems, piping, fabrication works and running tests. .
Total Weight Of Erection 300 Metric Tons
Total Man Power 120,000 Man-Hour Consumption
Percent Of Progress 100%
32 Isfahan Shahid Montazeri Power Plant (K 50)
Shahid Montazeri Project Power Plant
Client Tavanir Company
Location Isfahan – Iran
Consultant Moshanir Company
Starting Date Oct. 1986
Commissioning Mar. 1989 Date
Installation and commissioning of instrumentation, domestic Scope Of Work power distribution system, cooling tower internal lighting, fire fighting system and cabling.
Nominal Plant 800 MVA Capacity
Total Man Power 100,000 Man-Hour Consumption
Percent Of 100% Progress
33 Saveh Casting Plant (Dust Collection) (K 40)
Project Title Saveh Casting Plant
Iran Casting Industries Company - Client Tehran Kaveh Industrial City - Saveh - Location IRAN George Fischer Company- Consultant Schaffausen - Switzerland
Starting Date Jul. 1986
Commissioning Jul. 1987 Date
Dust collection system consisting of machinery and equipment, Scope Of Work mechanical, electrical, instrumentation installations and running test
Total Weight Of 500 Metric Tons Erection
Total Man-Power 55,000 Man-Hour Consumption
Percent Of 100% Progress
34 Saveh Casting Plant (Moulding) (K 30)
Project Title Saveh Casting Plant
Iran Casting Industries Company - Client Tehran
Location Kaveh Industrial City - Saveh - IRAN
George Fischer Company Consultant Schaffhausen – Switzerland
Starting Date Nov. 1985
Commissioning Jan. 1987 Date
Installation and running test of sand preparation line supplied by Erich (Germany) and moulding line supplied by Kunkel Wagner (Germany) consisting of Scope Of Work machinery and equipment, mechanical, electrical, instrumentation systems, piping, sand blasting, painting and fabrication works .
Total Weight Of 1,500 Metric Tons Erection
Total Man-Power 95,000 Man-Hour Consumption
Percent Of 100% Progress
35 Central Alborz Coal Washing Plant (K 20)
Project Titlez Central Alborz Coal Washing
Client Ministry Of Mines & Metals, Iran
Tehran-Ghaemshahr Road (km185) Location Azadmehr-IRAN
Consultant National Iranian Steel Co. (NISCO)
Starting Date Sep.1984
Commissioning Date Aug. 1989
A Turnkey Project, Consisting Of Erection /Installation Of Machinery And Equipment, Mechanical, Instrumentation, Scope Of Work Piping, Steel Structure, Fabrication Works, Civil Works, Commissioning And Running Tests.
Nominal Plant 110 Tons Of Concentrated Coal Per Capacity Hour
Total Weight Of 7,800 Metric Tons Erection
Total Man-Power 600,000 Man-Hour Consumption
Percent Of Progress 100%
36 Tabriz Textile Mill Complex (K10)
Project Title Tabriz Textile Mill Complex
Tabriz Textile Mill Corp. Client: Tehran - IRAN
Location Tabriz - IRAN
Tabriz Textile Corp. Technical Consultant Office
Starting Date Dec. 1983
Commissioning Jun. 1984 Date
Erection/Installation Of Machinery, Equipment, Electrical, Instrument Scope Of Work Works & commissioning, Running Tests & Product Quality Control.
Total Weight Of 250 Metric Tons Erection
Total Man-Power 25,000 Man-Hour Consumption
Percent Of Progress 100%
37 Faragir Baft-Balooch Textile Complex (K 00)
Faragir Baft-Balooch Textile Project Title Complex
Faragir Baft-Balooch Co. Client: Tehran-IRAN
Iranshahr-Bampoor Road Location (Km5), IRAN
Consultant Technologue Co. - Tehran-IRAN
Starting Date: Nov. 1981
Commissioning Date Feb. 1984
Erection/Installation and commissioning of Mechanical, Electrical, Instrumentation. Piping, Scope Of Work Painting, Sandblasting. Running test of the plant and quality control of the products.
Nominal Plant Capacity 29 Metric Tons of Yarn per Day
Total Weight Of 3,500 Metric tons Erection
Total Man-Power 600,000 Man-Hour Consumption
Percent Of Progress 100%
38 IIND’s Standby Forces
Item Description Staff Temporary
1 Management 21 18
2 Engineer 70 186
3 Technician 22 330
4 Skilled Workers 0 1720
Administration, 5 25 420 Financial & Logistic
6 Other 12 160
Sub Total 150 2850
Grand Total 3200
• Depending on the size of a project and their time - schedule, task force groups will be selected and assigned to meet the client's needs. Based on the man-power requirements of these task force groups, new employees will be hired for the duration of the project.
39 World Wide Clients IIND has associated itself with a number of reputable international firms and is registered in their international general contractors lists, these companies are such as:
Daelim (South Korea) Kunkel Wanger Snamprogetti (Italy)
Chiyoda (Japan) JGC (Japan) Linde (Germany)
Saipem (Italy) J.M.Voith (Austria) George Fischer
Italimpianti (Italy) MHI (Japan) TPL (Italy) Nuova Cimimontubi (Italy)
IIND is also in the process of investigating potential opportunities in the Middle East and newly established Commonwealth Independent States in central Asia. 40 Local Clients
• IIND has accepted the responsibility of implementation of sizeable projects for several clients in Iran during the past decade, some of which are listed as follows:
– The Ministry of Petroleum and affiliated companies (NIOC , NPC, NIGC)
– The Ministry of Industries, Mines & Trade
– The Ministry of Energy and affiliated companies
– Mapna Group
– Petropars Company
– National Iranian Steel Company
41 This section, introduces general and professional equipment and tools of IIND.
42 Heavy Cranes
NO. DESCRIPTION CAPACITY QTY 1 LIEBHERR 250 TONS 1 2 AMERICAN 205 TONS 1 3 TADANO 160 TONS 2 4 CRANE TADANO TG-800R 80 TONS 1 5 CRANE LIEBHERR 70 TONS 1 6 CRANE TADANO TR-500M 50 TONS 3 7 CRANE SUNNY 80 TONS 1
43 Cranes
NO. DESCRIPTION CAPACITY QTY
1 CRANE TADANO TR-350M 35 TONS 1
2 CRANE TADANO TL-300M 30 TONS 1
3 CRANE TADANO TR-300E 30 TONS 1
4 CRANE TADANO TR-250M 25 TONS 3
5 CRANE P&H TRK-250 25 TONS 1
6 CRANE TADANO TR-250E 25 TONS 1
7 CRANE TADANO TR-230E 23 TONS 1
8 CRANE TADANO TR-200M 20 TONS 1
9 CRANE P&H TR-K200 20 TONS 1
10 CRANE VOLVO F12 STS 10 TONS 1
11 CRANE (OVERHEAD) SHOP 10 TONS 1
12 TRUCK ESCANIA 6 TONS 1
13 TRUCK BENZ 6 TONS 1
14 TRUCK DAF 2300 6 TONS 1
15 TRUCK DAF TURBO 1900 5 TONS 1
16 TRUCK-CRANE DAF 2300 4.88 TONS 1
17 TRUCK DAF 2300 4.45 TONS 1
18 TRUCK-CRANE DAF 1900 3 TONS 1
44 NO. DESCRIPTION CAPACITY QTY 1 MINI LOADER BOBCAT 963 3 TON 1 2 MINI LOADER BOBCAT 753 2 TON 1 3 BACKHOE JCB 1 4 FORKLIFT IVECO 3.5 TON 2 5 TRACTOR ITM285 7 6 MIXER 500 ~ 1000 LITTER 11
NO. DESCRIPTION CAPACITY QTY 1 BUS BENZ 3 2 MINI BUS HYUNDAI-HISE 7 3 TRUCK IVECO -VOLVO F12 3 4 MOBILE TANKER HYUNDAI 2 5 MOBILE Maintenance Vehicle MITSUBISHI 1 6 TRAILER 2 ~ 12 M 24
NO. DESCRIPTION CAPACITY QTY 1 SEDAN 9 2 Pick - UP 0.5 ~ 2.5 TONS 13 3 AMBULANCE GMC 1
45 Tools
NO. DESCRIPTION CAPACITY QTY
1 GENERATOR 40-350 KVA 33
2 LIGHTING TOWER STAMFORD 7.5 KVA 4
3 DIESEL WELDING 25
4 WELDING RECTIFIER 292
5 PLATE COMPACTOR 1
6 WELDING STATION MILER 2
7 COMPRESSOR 375 ~ 1300 CFM 16
8 WATER STORAGE TANK 51
9 FUEL STORAGE TANK 24
10 BENDER 1.5"~6" 4
11 TEST PUMP 13
12 WATER PUMP 5 M3/H - HEIGHT 30M 5
13 SANDBLASTING 8
14 FLAME CUTTER MACHINE 5
15 VIBRATOR 3
16 RE.BAR CUTTER &BENDING MACHINE 5
17 DRILLING MACHINE MANUAL &AUTOMATIC-25MM 165
18 MILLING + GRINDING MACHINE 420
19 WINCH MACHINE & MOTORIZED 16
20 ELECTRODE HEATERS 30
21 THEODOLITE SURVEYING 15
140 22 (INSTRUMENT + ELECTRICAL + MECHANICAL) TOOL BOX
23 AIRLESS SPRAY PAINTING INSTRUMENT 10
24 CONNEX 70
25 CONTAINER 64
26 Damper 1 46 This section, introduces some of our awards & certificates of IIND.
47 48 49 50 51 52 53
54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77