Central Office:

• No. 8, 23rd St., Gandhi Ave., , • Zip Code: 1517936611 • P. O. Box: 15175-351 • Fax : +98 21 88777112 • Telephone : +98 21 88770138 +98 21 88778634 • Email : [email protected] • Website: www.iindco.com

2 Branch Office:

• Site 1, AZADI Street, Petrochemical Economic Special Zone, Bandar Imam Khomeini (MAHSHAHR), IRAN

• Fax: +98-652262-6194 • Phone: +98-652262-6315

3 Iran Industrial Networks Development Company (IIND) is a private joint stock company registered in Tehran on September 19th 1983.

. During the past decades IIND has been involved in numerous industrial projects, having a total capital investment of over 6.5 billion US Dollars. . Industrial works;IIND handles all categories of works which are required to install an industrial complex on EPC basis.

. IIND can participate in industrial projects in several ways such as: Lump- Sum Contracts, Sub-Contracts, Joint-Ventures, Turnkey and EPC Projects, Cost Plus, or even hourly rates for man power supply. We even recommend the most suitable type of contract to the clients by optimization of the economics of the project. . The quality of services rendered by IIND has always been the prime consideration of our management. Therefore to ensure superior quality and also to keep pace with the progress of technology as practiced by the well known contractors all over the world.

4 Services & Fields of Activities In Turn-Key Projects

• Feasibility Study of Industrial Plants

• Industrial Civil Building Works & their Utilities • Procurement and Inspection of Equipment (Mechanical, Electrical, Instrumentation, HVAC, etc.)

• Equipment Erection and Assembly

• Piping, Sandblast, Painting and Insulation

• Erection of Steel Structures

• Installation of Electrical Start - Up and Commissioning Activities

• Project Management and Staff Training

5 Equipment & Machinery

. Most of the equipment and tools which are utilized during the execution of our projects is owned by IIND, such as (for more detail see Equipment list at chapter 4) :

– High Capacity Crawler Cranes (205,160 Tons)

– Medium Size Cranes (20~80 Tons) – Small Size Cranes (3~10 Tons)

– Loaders

– Lift & Fork Lifts

– Compressor

– Diesel Generators

– Welding Machines

– Cars and Pick-ups

– Medium & Light transporting equipment

– Wrenches & Tools

– Portable Accommodation Facilities 6 7 Selected Reference Projects: At the beginning of this section a “List Of Selected Projects" is provided along with their Clients. A brief description of each project follows in the same order, after this list.

Dates Duration Item Code Subject MH Client Start End (Month)

South Pars Gas Development Phase 12 Under 1 K320 Apr. 2014 Ongoing 1,050,000 Petropars Co. (Metering Station) Process

South Pars Gas Development Phase 12 Under 2 K320 Sep. 2009 Ongoing 5,750,000 Petrpars Co. (EPC2) Process 3 K300 Isocyanate Project, Phase 1 Jun-04 Oct-07 40 4,290,000 Karoon Petrochemical Co. (NPC)

4 K290 PET2 Project Jul-03 Mar-07 44 7,500,000 Tondgooyan Petrochemical Co. (NPC)

5 K280 PTA2 Project May-03 Nov-05 30 4,600,000 Tondgooyan Petrochemical Co. (NPC)

6 K270 C2 Recovery, Gas Cracking Plant Aug-02 Nov-04 27 1,600,000 Marun petrochemical Co. (NPC)

7 K260 3rd Aromatic Production Plant Jul-01 Dec-04 42 7,900,000 Boualisina petrochemical Co. (NPC) Shahid Rajaei Combined Cycle Power 8 K240 May-00 Mar-03 35 1,600,000 Mapna Co. Plant Montazer Ghaem Combined Cycle 9 K230 Dec-99 Mar-01 15 350,000 Mapna Co. Power Plant 10 K220 Isfahan Poly-Acryl Expansion Jul-99 Oct-00 15 470,000 Poly acryl IRAN Bandar-Abbas Refinery (H-Naphtha, 11 K200 Jun-95 Jul-97 25 1,000,000 National Iranian Oil Co. (NIOC.) Hydro Cracker) 12 K190 Bandar-Abbas Refinery (Fired Heater) Nov-94 Jul-97 32 1,600,000 National Iranian Oil Co. (NIOC.) Bandar-Abbas Refinery (Kerosene 13 K180 Jun-95 Mar-97 21 900,000 National Iranian Oil Co. (NIOC.) Hydro Treated) 14 K170 Latif Paper Industry Nov-92 Jan-95 26 300,000 LATIF PAPER Co.

15 K160 Latif Paper Industry Nov-92 Aug-94 21 500,000 LATIF PAPER Co.

16 K150 Arak Refinery Jun-92 Feb-94 20 450,000 TPL SPA

17 K140 Baft-Balooch Nov-91 Oct-93 23 12,000 Faragir Baft Balooch Co.

18 K130 Arak Refinery Aug-91 Mar-93 19 600,000 Saipem S.P.A.

19 K120 Ahwaz Carbon Black Aug-91 Nov-94 40 2,500,000 National Petrochemical Company

20 K110 Mobarakeh Steel ( Cold Rolling Mill) Jan-90 Jun-91 17 400,000 NUOVA CIMIMONTUBI (SPA)

21 K100 Mobarakeh Steel ( Hot Rolling Mill) Jan-90 Jun-91 17 400,000 NUOVA CIMIMONTUBI (SPA)

22 K90 Mobarakeh Steel ( Steel Making Unit) Jan-90 Jun-91 17 400,000 NUOVA CIMIMONTUBI (SPA)

23 K80 Arak HEPCO Jan-90 Sep-91 20 120,000 HEPCO (Heavy Industries)

24 K70 Mobarakeh Steel Complex Sep-89 May-92 32 1,200,000 Mobarakeh Steel Complex

25 K60 Karaj Rolling Mill Mar-87 May-88 14 120,000 Rolling Mill Co.

26 K50 Shahid Montazeri Power Plant Oct-86 Mar-89 29 100,000 Tavanir Co. Saveh Casting Complex (Second 27 K40 Jul-86 Jul-87 12 55,000 Iran Casting Industries Co. Contract) 28 K30 Saveh Casting Complex Nov-85 Jan-87 14 95,000 Iran Casting Industries Co.

29 K20 Alborz Coal Washing Plant Sep-84 Aug-89 60 600,000 Ministry Of Mines & Metals

30 K10 Tabriz Textile Dec-83 Jun-84 6 25,000 Tabriz Textile Mill Corp.

31 K00 Baft-Balooch Nov-81 Feb-84 27 600,000 Faragir Baft-Balooch Textile Mill Co. GRAND TOTAL 47,087,000

8 South Pars Gas Field Development Metering Station

SOUTH PARS GAS FIELD Project Name DEVELOPMENT – Phase 12 Metering Station

National Iranian Oil Owner Company

Client Petropars LTD.

Contractor IIND

Project Location Assaluyeh - Tombak

Start Date April 2014

First Export May 2015

Export Capacity of 2500 cubic meter/Hour each skid Up to 45 bar

Man Power 1,050,000 Consumption

Percentage of 99% 9 Progress South Pars Gas Field Development Phase 12 – EPC2 (On Shore) (K320)

SOUTH PARS GAS FIELD DEVELOPMENT Project Name PHASE-12 EPC2 ONSHORE FACILITIES

Owner National Iranian Oil Company

Client Petropars LTD.

DSKI Consortium Contractor (Daelim, Sazeh, Kayson, IIND)

Project Location Assaluyeh - Tombak

Starting Date September 2009

First Feb. 2014 Production

• Sweet Gas: 3,000 MMSCF/D Plant Capacity • Condensate: 120,000 (Phase 12) barrels/D • Sulfur: 750 tons/D

Man Power 5,750,000 Consumption

Percentage of 10 99% Progress Isocyanate Project, Phase1 (K 300) (Karoon)

Project Isocyanate Project, Phase 1

Client Karoon Petrochemical co.

Mahshahr petrochemical Location free special economic zone

Starting Date Jun. 2004

Commissioning Date Oct. 2007

Mechanical installation of equipments, vessels, towers, steel structures, Scope Of Work piping, insulation and painting, electrical & instrument TDI 40,000 tons per year Nominal Plant MDI 40,000 tons per year Capacity HCL(33%)63,000 tons per year

Total Man Power 4,290,000 man-hour Consumption

Total Weight Of 6,835 metric tons Erection

Percent of Progress 100%

11 PET - Phase II Production Plant (K 290) (Tondgooyan) Project PET2

Shahid Tondgooyan Client Petrochemical co.

Mahshahr petrochemical Location free special economic zone

Starting Date Jul. 2003

Commissioning Date Mar. 2007

Mechanical installation of equipment, vessels, towers, Scope Of Work steel structures, piping, insulation and painting, electrical & instrument

132,000 T/Y Bottle grad Nominal Plant 132,000 T/Y Fiber grade Capacity 66,000 T/Y Poy 66,000 T/Y Staple

Total Weight Of 11,876 metric tons Erection

Total Man Power 7,500,000 man-hour Consumption

Percent of Progress 100% 12 PTA – Phase II Production Plant (K 280) (Tondgooyan)

Project PTA2

Shahid Tondgooyan Client Petrochemical co.

Mahshahr petrochemical free Location special economic zone

Starting Date May. 2003

Commissioning Nov , 2005 Date

Mechanical installation of equipments, vessels, towers, Scope Of Work steel structures, piping, insulation and painting, electrical & instrument

Nominal Plant Capacity 350,000 tons per year

Total Weight Of 9,649 metric tons Erection

Total Man Power 4,600,000 man-hour Consumption

Percent of Progress 100% 13 7th Olefin Project (K270) (Marun) th Project 7 OLEFIN PLANT

Client Marun petrochemical co.

Mahshahr petrochemical Location free special economic zone

Consultant Linde,EIED,sazeh

Starting Date Aug. 2002

Commissioning Nov. 2004 Date

Mechanical installation of equipment, vessels, towers, Scope Of Work steel structures, piping, insulation and painting, electrical & instrument

Nominal Plant 1,644,000 tons per year Capacity

Total Weight Of 20,727 metric tons Erection

Percent of 100% Progress

Total Man Power 1,600,000 man-hour Consumption

14 3rd Aromatic Project (K260) (Boualisina)

rd Project 3 AROMATIC PLANT

Client Boualisina petrochemical co.

Mahshahr petrochemical free Location special economic zone

PIDEC Consultant Managing contractor: engineers India limited

Starting Date Jul. 2001

Commissioning Date Dec. 2004

Mechanical installation of equipments, vessels, towers, steel structures, piping, Scope Of Work insulation and painting, electrical & instrument for para-xylene, orto-xylene and benzene production plant.

Nominal Plant Capacity 1,741,000 tons per year

Total Weight Of Erection 23,609 metric tons

Percent of Progress 100%

Total Man Power 7,900,000 man-hour Consumption

15 Montazer Ghaem & Shahid Rajaee Combined Cycle Power Plants (CCPP) (K 230) & (K 240)

Project Combined cycle power plant

Client Mapna

Montazer ghaem combined cycle power plant (Karaj – Location Iran)

Shahid Rajaee combine cycle power plant (Ghazvin – Iran)

Consultant Moshanir – Tehran -IRAN

M.G. Dec. 1999 – Sh.R. May Starting Date 2000

M.G. Mar. 2001 – Sh.R. Mar. Commissioning Date 2003

Mechanical installation of equipments, vessels, steel structures, piping, insulation Scope Of Work and painting, electrical and instruments works for the steam cycle of the power plant.

M.G. 125 mw – Sh.R. 3 x 125 Nominal Plant Capacity mw

Total Weight Of M.G. 1,500 – Sh.R. 9,000 Erection metric tons

Total Man Power M.G. 350,000 – Sh.R. Consumption 1,600,000 man-hour 16 Percent Of Progress M.G. 100% – SH.R. 100% Polyacryl Expansion Project (K 220)

Project New acrylic plant

Client Poly acryl IRAN

Location Isfahan – IRAN

Consultant Noyvalesina – Italy

Starting Date Jul.1999

Commissioning Date Oct.2000

Mechanical installation of equipments, vessels, steel structures, piping, insulation, painting, Scope Of Work electrical, instruments and pre-commissioning & commissioning of Acrylic Plant.

Total Weight Of Erection 2,000 metric tons

Total Man Power 470,000 man-hour Consumption

Percent Of Progress 100% 17 Bandar Abbas Refinery H-Naphtha Hydro-Cracker & CCR (K 200)

Project Bandar Abbas Refinery

National Iranian Oil CO. Client (NIOC.)

Location Bandar Abbas - IRAN

Chiyoda - Snamprogetti Consultant (Joint Venture) Bandar Abbas - Iran

Starting Date Jun. 1995

Commissioning Date July, 1997

Mechanical installation of equipments, vessels, steel structures, piping, insulation and painting of Scope Of Work heavy naphtha hydro- cracker and continuous catalytic reformer (CCR) Units in Bandar abbas refinery .

Nominal Plant Capacity 36,000 BPSD

Total Weight Of Erection 3,500 METRIC TONS

Total Man Power 1,000,000 Man-Hour Consumption

Percent Of Progress 100% 18 Bandar Abbas Refinery Fired Heaters (K 190)

Bandar abbas Refinery Project fired heaters

National Iranian Oil Client Company (NIOC.)

Location Bandar Abbas - IRAN

Chiyoda - Snamprogetti Consultant (Joint Venture) Bandar Abbas - Iran

Starting Date Nov. 1994

Commissioning Date Jul. 1997

Mechanical installation of th 8 refinery fired heaters Scope Of Work in two areas B & C of bandar abbas refinery.

Total Weight Of 6,000 Metric Tons Erection

Total Man Power 1,600,000 Man-Hour Consumption

Percent Of Progress 100% 19 Bandar Abbas Refinery Kerosene Hydrotreater (K 180)

Project Bandar Abbas Refinery National Iranian Oil Client Company (N.I.O.C.) - Tehran-IRAN

Location Bandar Abbas - IRAN

Chiyoda - Snamprogetti Consultant (Joint Venture)

Starting Date Jun. 1995

Commissioning Date Mar. 1997

Mechanical installation of equipments, vessels, steel structures, piping, insulation and painting of Kerosene Scope Of Work hydrotreater, LPG recovery, LPG treater LPG splitter and Amine treater in bandar abbas refinery . Nominal Plant 25,000 BPSD Capacity Total Weight Of 2,000 METRIC TONS Erection Total Man Power 900,000 Man-Hour Consumption Percent Of Progress 100% 20 Latif Paper Mill (Factory Equipment Erection) (K 170)

LATIF Paper Production Project Factory Equipment Erection

LATIF PAPER CO. - Tehran - Client IRAN

HASHTGERD INDUSTRIAL CITY Location IRAN

TARH-E-SANAT Co. - Tehran - Consultant IRAN

Starting Date Nov. 1992

Commissioning Jan. 1995 Date Installation of machines of a paper production unit. Paper plant, control room, Scope Of Work laboratory, compressed air center, steam production unit, tanks and pumps for chemical process of paper plant. Nominal Plant 10,000 TPY Capacity

Total Weight Of 1,100 Metric Tons Erection

Total Man Power 300,000 Man-Hour Consumption

Percent Of 100% Progress 21 Latif Paper Mill (Utilities Equipment Supply & Erection) (K 160)

Project Latif paper company

Client Latif Paper Company - Tehran -IRAN

Location HASHTGERD INDUSTRIAL CITY IRAN

Consultant TARH-E-SANAT Co. - Tehran- IRAN

Starting Date Nov. 1992

Commissioning Date Aug. 1994

Installation of mechanical and electrical works of Scope Of Work utility buildings and cabling of production unit.

Nominal Plant Capacity 10,000 TPY

Total Man Power 500,000 Man-hour Consumption

Percent Of Progress 100%

22 Arak Refinery (Insulations) (K 150)

Project 7'TH REFINERY ARAK

Client TPL SPA

Location Arak -IRAN

TPL SPA Consultant Tehran - IRAN

Starting Date Jun. 1992

Commissioning Date Feb. 1994

Insulation works of tanks, Scope Of Work vessels, piping, pumps and instruments .

Nominal Plant 150,000 BPD Capacity

Total Weight Of 100,000 SQUARE METER OF Erection INSULATION

Total Man Power 450,000 Man-Hour Consumption

Percent Of Progress 100%

23 Baft Balooch Textiles Dying Unit (K 140)

Baft Balooch Textile Complex Project (Drying Unit)

Faragir Baft Balooch Co. Client Tehran-IRAN

Iranshahr-Bampoor Road Location (Km5), IRAN

Technical office of the client - Consultant Tehran -IRAN

Starting Date Nov. 1991

Commissioning Date Oct. 1993

Erection / installation and commissioning of mechanical, electrical, Scope Of Work instrumentation, piping, painting and running test of the plant.

Total Weight Of Over 1,000 Metric Tons Erection

Total Man Power 12,000 Man-Hour Consumption

Percent Of Progress 100%

24 Arak Refinery (K 130)

Project 7'th Refinery Arak

Client Saipem S.P.A.

Location Arak - IRAN

Consultant T.P.L S.P.A.

Starting Date Aug. 1991

Commissioning Date Mar. 1993

off - site piping including above ground, under Scope Of Work ground, steam tracing piping and installation of tanks and vessels.

Nominal Plant Capacity 150,000 Bpd

Total Weight Of Erection 3,000 Metric Tons

Total Man Power 600,000 Man-Hour Consumption

Percent Of Progress 100%

25 Ahwaz Carbon Black Plant (K 120)

Project Ahwaz Carbon Black Extension

National Petrochemical Client Company (Subsidiary Of Ministry Of )

Location Ahwaz-Mahshahr Road Km 4th

Petrochemical Industries Design Consultant & Engineering Company (PIDEC) - Shiraz - IRAN

Starting Date Aug. 1991

Commissioning Date Nov. 1994

Completion of the plant on A turn key basis including civil, mechanical, electrical, recycling of industrial sewage system, Scope Of Work fabrication of vessels and steel structures, piping, instrumentation works together with pre- commissioning and commissioning.

Nominal Plant Capacity 21,000 Ton / Year

Total Weight Of 2,500 Metric Tons Erection

Total Man Power 2,500,000 Man-Hour Consumption

Percent Of Progress 100%

26 10 Mobarakeh Steel Complex P. U. 53 (Cold Rolling Mill) (K 110)

Mobarakeh Steel Complex Project (Cold rolling mill)

NUOVA CIMIMONTUBI Client (S.P.A.)

75km.South West Of Location Isfahan-IRAN

Iran International Consultant Engineering (IRITEC) Co.

Starting Date Jan. 1990

Commissioning Date Jun. 1991

Installation of industrial piping from 1 up to 16 inches in elevations from +00 to +45 meters for Scope Of Work distribution of fluids in pu53 (cold rolling mill plant of mobarakeh steel complex).

Total Weight Of 3700 Metric Tons Erection

Total Man Power 400,000 Man-Hour Consumption

Percent Of Progress 100% 27 Mobarakeh Steel Complex P. U. 51 (Hot Rolling Mill) (K 100)

Mobarakeh Steel Complex (Cold Project rolling mill)

Client NUOVA CIMIMONTUBI (SPA)

Location 75km.South West Of Isfahan-IRAN

Iran International Engineering Consultant (IRITEC) Co.

Starting Date Jan. 1990

Commissioning Date Jun. 1991

Installation of industrial piping from 1 up to 16 inches in elevations from +00 to +45 meters Scope Of Work for distribution of fluids in pu07 (steel mill plant of mobarakeh steel complex).

Total Weight Of 400 Metric Tons Erection

Total Man Power 400,000 Man-Hour Consumption

Percent Of Progress 100% 28 Mobarakeh Steel Complex P. U. 07 (Steel Mill Plant) (K 90)

Mobarakeh Steel Complex Project (Cold rolling mill)

Client NUOVA CIMIMONTUBI (SPA)

75km.South West Of Isfahan- Location IRAN

Iran International Engineering Consultant (IRITEC) Co.

Starting Date Jan. 1990

Commissioning Date Jun. 1991

Installation of industrial piping from 1 up to 16 inches in elevations from +00 to +45 Scope Of Work meters for distribution of fluids in pu07 (steel mill plant of mobarakeh steel complex).

Total Weight Of 400 Metric Tons Erection

Total Man Power 400,000 Man-Hour Consumption

Percent Of Progress 100%

29 HEPCO Machine Plant (K 80)

HEPCO Machine Project Manufacturing

HEPCO Client (A Subsidiary Of Ministry Of Heavy Industries)

Arak Industrial Area Location IRAN

Bahleh And Stama Consultant (German Company)

Starting Date Jan. 1990

Commissioning Date Sep. 1991

Erection / installation of machinery, equipment, mechanical, Scope Of Work electrical, instrumentation systems, piping and commissioning. .

Total Weight Of Erection Over 1,000 Metric Tons

Total Man Power 120,000 Man-Hour Consumption

Percent Of Progress 100% 30 Mobarakeh Steel Complex (Raw Material Handling Yard) (K 70)

Mobarakeh Steel Complex Project (Raw Material Handling)

Mobarakeh Steel Complex Client (A Subsidiary Of Ministry Of Mines And Metals)

75km.South West Of Isfahan- Location IRAN

Iran International Engineering Consultant (IRITEC) Co.

Starting Date Sep. 1989

Commissioning May. 1992 Date Erection / installation and commissioning of machinery, equipment, mechanical, electrical, instrumentation Scope Of Work systems and utilities, piping, fabrication works, painting, sand blasting and running tests. . Total Weight Of 12,500 Metric Tons Erection

Total Man Power 1,200,000 Man-Hour Consumption

Percent Of 100% Progress

31 Karaj Rolling-Mill Plant (K 60)

Project Karaj Rolling Mill

Rolling Mill Co.(A Client subsidiary of the Ministry Of Heavy Industries)

Old Tehran-Karaj Road Location km18 - Iran

Starting Date Mar. 1987

Commissioning Date May. 1988

Installation of furnaces, moulding line consisting of machinery, equipment, Scope Of Work mechanical, electrical, instrumentation systems, piping, fabrication works and running tests. .

Total Weight Of Erection 300 Metric Tons

Total Man Power 120,000 Man-Hour Consumption

Percent Of Progress 100%

32 Isfahan Shahid Montazeri Power Plant (K 50)

Shahid Montazeri Project Power Plant

Client Tavanir Company

Location Isfahan – Iran

Consultant Moshanir Company

Starting Date Oct. 1986

Commissioning Mar. 1989 Date

Installation and commissioning of instrumentation, domestic Scope Of Work power distribution system, cooling tower internal lighting, fire fighting system and cabling.

Nominal Plant 800 MVA Capacity

Total Man Power 100,000 Man-Hour Consumption

Percent Of 100% Progress

33 Saveh Casting Plant (Dust Collection) (K 40)

Project Title Saveh Casting Plant

Iran Casting Industries Company - Client Tehran Kaveh Industrial City - Saveh - Location IRAN George Fischer Company- Consultant Schaffausen - Switzerland

Starting Date Jul. 1986

Commissioning Jul. 1987 Date

Dust collection system consisting of machinery and equipment, Scope Of Work mechanical, electrical, instrumentation installations and running test

Total Weight Of 500 Metric Tons Erection

Total Man-Power 55,000 Man-Hour Consumption

Percent Of 100% Progress

34 Saveh Casting Plant (Moulding) (K 30)

Project Title Saveh Casting Plant

Iran Casting Industries Company - Client Tehran

Location Kaveh Industrial City - Saveh - IRAN

George Fischer Company Consultant Schaffhausen – Switzerland

Starting Date Nov. 1985

Commissioning Jan. 1987 Date

Installation and running test of sand preparation line supplied by Erich (Germany) and moulding line supplied by Kunkel Wagner (Germany) consisting of Scope Of Work machinery and equipment, mechanical, electrical, instrumentation systems, piping, sand blasting, painting and fabrication works .

Total Weight Of 1,500 Metric Tons Erection

Total Man-Power 95,000 Man-Hour Consumption

Percent Of 100% Progress

35 Central Alborz Coal Washing Plant (K 20)

Project Titlez Central Alborz Coal Washing

Client Ministry Of Mines & Metals, Iran

Tehran-Ghaemshahr Road (km185) Location Azadmehr-IRAN

Consultant National Iranian Steel Co. (NISCO)

Starting Date Sep.1984

Commissioning Date Aug. 1989

A Turnkey Project, Consisting Of Erection /Installation Of Machinery And Equipment, Mechanical, Instrumentation, Scope Of Work Piping, Steel Structure, Fabrication Works, Civil Works, Commissioning And Running Tests.

Nominal Plant 110 Tons Of Concentrated Coal Per Capacity Hour

Total Weight Of 7,800 Metric Tons Erection

Total Man-Power 600,000 Man-Hour Consumption

Percent Of Progress 100%

36 Tabriz Textile Mill Complex (K10)

Project Title Tabriz Textile Mill Complex

Tabriz Textile Mill Corp. Client: Tehran - IRAN

Location Tabriz - IRAN

Tabriz Textile Corp. Technical Consultant Office

Starting Date Dec. 1983

Commissioning Jun. 1984 Date

Erection/Installation Of Machinery, Equipment, Electrical, Instrument Scope Of Work Works & commissioning, Running Tests & Product Quality Control.

Total Weight Of 250 Metric Tons Erection

Total Man-Power 25,000 Man-Hour Consumption

Percent Of Progress 100%

37 Faragir Baft-Balooch Textile Complex (K 00)

Faragir Baft-Balooch Textile Project Title Complex

Faragir Baft-Balooch Co. Client: Tehran-IRAN

Iranshahr-Bampoor Road Location (Km5), IRAN

Consultant Technologue Co. - Tehran-IRAN

Starting Date: Nov. 1981

Commissioning Date Feb. 1984

Erection/Installation and commissioning of Mechanical, Electrical, Instrumentation. Piping, Scope Of Work Painting, Sandblasting. Running test of the plant and quality control of the products.

Nominal Plant Capacity 29 Metric Tons of Yarn per Day

Total Weight Of 3,500 Metric tons Erection

Total Man-Power 600,000 Man-Hour Consumption

Percent Of Progress 100%

38 IIND’s Standby Forces

Item Description Staff Temporary

1 Management 21 18

2 Engineer 70 186

3 Technician 22 330

4 Skilled Workers 0 1720

Administration, 5 25 420 Financial & Logistic

6 Other 12 160

Sub Total 150 2850

Grand Total 3200

• Depending on the size of a project and their time - schedule, task force groups will be selected and assigned to meet the client's needs. Based on the man-power requirements of these task force groups, new employees will be hired for the duration of the project.

39 World Wide Clients IIND has associated itself with a number of reputable international firms and is registered in their international general contractors lists, these companies are such as:

Daelim (South Korea) Kunkel Wanger Snamprogetti (Italy)

Chiyoda (Japan) JGC (Japan) Linde (Germany)

Saipem (Italy) J.M.Voith (Austria) George Fischer

Italimpianti (Italy) MHI (Japan) TPL (Italy) Nuova Cimimontubi (Italy)

IIND is also in the process of investigating potential opportunities in the and newly established Commonwealth Independent States in central Asia. 40 Local Clients

• IIND has accepted the responsibility of implementation of sizeable projects for several clients in Iran during the past decade, some of which are listed as follows:

– The Ministry of Petroleum and affiliated companies (NIOC , NPC, NIGC)

– The Ministry of Industries, Mines & Trade

– The Ministry of Energy and affiliated companies

– Mapna Group

– Petropars Company

– National Iranian Steel Company

41 This section, introduces general and professional equipment and tools of IIND.

42 Heavy Cranes

NO. DESCRIPTION CAPACITY QTY 1 LIEBHERR 250 TONS 1 2 AMERICAN 205 TONS 1 3 TADANO 160 TONS 2 4 CRANE TADANO TG-800R 80 TONS 1 5 CRANE LIEBHERR 70 TONS 1 6 CRANE TADANO TR-500M 50 TONS 3 7 CRANE SUNNY 80 TONS 1

43 Cranes

NO. DESCRIPTION CAPACITY QTY

1 CRANE TADANO TR-350M 35 TONS 1

2 CRANE TADANO TL-300M 30 TONS 1

3 CRANE TADANO TR-300E 30 TONS 1

4 CRANE TADANO TR-250M 25 TONS 3

5 CRANE P&H TRK-250 25 TONS 1

6 CRANE TADANO TR-250E 25 TONS 1

7 CRANE TADANO TR-230E 23 TONS 1

8 CRANE TADANO TR-200M 20 TONS 1

9 CRANE P&H TR-K200 20 TONS 1

10 CRANE VOLVO F12 STS 10 TONS 1

11 CRANE (OVERHEAD) SHOP 10 TONS 1

12 ESCANIA 6 TONS 1

13 TRUCK BENZ 6 TONS 1

14 TRUCK DAF 2300 6 TONS 1

15 TRUCK DAF TURBO 1900 5 TONS 1

16 TRUCK-CRANE DAF 2300 4.88 TONS 1

17 TRUCK DAF 2300 4.45 TONS 1

18 TRUCK-CRANE DAF 1900 3 TONS 1

44 NO. DESCRIPTION CAPACITY QTY 1 MINI BOBCAT 963 3 TON 1 2 MINI LOADER BOBCAT 753 2 TON 1 3 BACKHOE JCB 1 4 FORKLIFT IVECO 3.5 TON 2 5 ITM285 7 6 MIXER 500 ~ 1000 LITTER 11

NO. DESCRIPTION CAPACITY QTY 1 BUS BENZ 3 2 MINI BUS HYUNDAI-HISE 7 3 TRUCK IVECO -VOLVO F12 3 4 MOBILE TANKER HYUNDAI 2 5 MOBILE Maintenance Vehicle MITSUBISHI 1 6 TRAILER 2 ~ 12 M 24

NO. DESCRIPTION CAPACITY QTY 1 SEDAN 9 2 Pick - UP 0.5 ~ 2.5 TONS 13 3 AMBULANCE GMC 1

45 Tools

NO. DESCRIPTION CAPACITY QTY

1 GENERATOR 40-350 KVA 33

2 LIGHTING TOWER STAMFORD 7.5 KVA 4

3 DIESEL WELDING 25

4 WELDING RECTIFIER 292

5 PLATE COMPACTOR 1

6 WELDING STATION MILER 2

7 COMPRESSOR 375 ~ 1300 CFM 16

8 WATER STORAGE TANK 51

9 FUEL STORAGE TANK 24

10 BENDER 1.5"~6" 4

11 TEST PUMP 13

12 WATER PUMP 5 M3/H - HEIGHT 30M 5

13 SANDBLASTING 8

14 FLAME CUTTER MACHINE 5

15 VIBRATOR 3

16 RE.BAR CUTTER &BENDING MACHINE 5

17 DRILLING MACHINE MANUAL &AUTOMATIC-25MM 165

18 MILLING + GRINDING MACHINE 420

19 WINCH MACHINE & MOTORIZED 16

20 ELECTRODE HEATERS 30

21 THEODOLITE SURVEYING 15

140 22 (INSTRUMENT + ELECTRICAL + MECHANICAL) TOOL BOX

23 AIRLESS SPRAY PAINTING INSTRUMENT 10

24 CONNEX 70

25 CONTAINER 64

26 Damper 1 46 This section, introduces some of our awards & certificates of IIND.

47 48 49 50 51 52 53

54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77