Creating an Effective Alliance

Total Page:16

File Type:pdf, Size:1020Kb

Creating an Effective Alliance Feature PRACTICE Creating an effective alliance When London Waterloo station decided to boost peak-time capacity, five organisations had to learn how to work effectively together BY MARYNA LOSIEVA ondon Waterloo is currently Britain’s busiest Only a fully station and links the country’s most used railways. The Wessex Capacity Programme (WCP) collaborative is aimed to deliver a 30% boost in peak-time approach between capacity to and from Waterloo station. A number the client Lof works are being or have been carried out to achieve this, including rebuilding the former Waterloo International organisation, Terminal (WIT) and bringing Platforms 20-24 back into designers and use with modern facilities, new track and signalling, and a layout that meets the needs of thousands of passengers. contractors would Platforms 1-4 were extended to allow longer carriage trains allow the project (10 carriages as opposed to 8) further increasing capacity. This had to be accommodated by works to Platforms to be delivered 1-8 and associated track and signalling alterations. The successfully intention behind creating two additional staircases (entrances to London Underground) on Platforms 1-4 is to relieve congestion on the platforms during peak times. Vauxhall Station will also be upgraded as part of the works. This £602 million investment programme, involving 380 people daily and over 1000 people during peak construction, will be delivered by December 2018. The Waterloo Capacity Alliance (WCA) is a body that was procured in January 2015 by the client, Network Rail. The Alliance is made up of the client, designer 28 Enterprise Risk Reprinted courtesy of Enterprise Risk magazine and the Institute of Risk Management Image credit: Hatchapong Palurtchaivong / Shutterstock.com consultants (Mott MacDonald to deliver the programme: keep provided to maintain minimum and AECOM), building contractor the station operational and station operational requirements. (Skanska) and track and rail systems/ minimise disruption to services. Consequently, the old WIT platforms signalling contractor (Colas Rail). As the station could not be fully were demolished and reconstructed closed during construction, the (5 in total) to be operational before Why deliver as an alliance? only way to deliver the required the start of the Platform 1-10 main works was by partial closures of the possession. If WIT was not ready The works required to be undertaken railway track, known as possessions. before the main possession, then were very technically challenging The most significant possession, it would have had to have been and complex on a fast-track estimated to be a 24-day long one cancelled, which would have schedule. The programme includes (main possession), had to be booked 2 resulted in significant reputational multiple interfaces for overlapping years in advance. This was a closure impact on the client and Alliance design and construction phases of Platforms 1-10 to enable Platforms participants and extended the between numerous interlinked 1-4 to be extended and modifications programme by a full 12 months. disciplines such as civils, railway on Platforms 5-10. Major negotiations In addition, smaller possessions track, Mechanical, Electrical and with the train company operators were also required to carry out Public Health (MEP), railway systems and other stakeholders were required track renewals, civils enabling and power upgrades. There are and involved an extensive advertising works and signalling upgrades. also many stakeholders involved, campaign to make passengers aware To deliver the required work within eg train operators, passengers of the disruption. Closing 10 out of two years (up to August 2017) was and Network Rail maintenance the station’s 19 platforms was not described by WCA Commercial lead teams, whose requirements need acceptable as it would cause more Tim Ryall as being double that of a to be satisfied. There were two than half reduction to services, typical railway project over the same key stakeholder requirements hence extra platforms had to be time frame. Therefore, to manage all Spring 2018 29 Reprinted courtesy of Enterprise Risk magazine and the Institute of Risk Management Five different HIGH-LEVEL REPRESENTATION OF RISKS companies with possibly differing cultures and External Programme approaches to risk risks management do not participate Wider Network Rail collaboratively Programme risks and transparently straight away even though it is a contractual requirement Internal Alliance risks the above constraints and risks, only a collaboratively and transparently risks being managed proactively and fully collaborative approach between straight away even though it is a not assuming or relying on other the client organisation, designers contractual requirement! To build parties to manage project risks and contractors would allow the a genuine alliance environment, an which are outside of their contract (in project to be delivered successfully. understanding of each of their risk normal contractual arrangements). cultures “by their natural standing The reality is that it does not matter Alliance way of working in the construction industry” is how many risks you transfer to vital. Traditionally contractors were other parties; they are still project All the Alliance partners signed a perceived to be very clandestine, risks and, if we want the project to contract “Integrated Programme trying to transfer as many risks succeed, everyone needs to take Alliance Agreement” (IPAA) which as possible to the client or be paid responsibility for mitigating them. outlined key behaviours expected handsomely to take on the liability. In from each individual within contrast, consultancies usually worked Dedicated risk the Alliance. It asserted that all as part of the client team and aimed management team participants win or all participants to minimise the client’s expenditure lose, based on achieved project as these were the services they had To build a strong alliance takes a long outcomes. Risks and responsibilities been employed for. Designers were time, continuous education and lots are shared and managed collectively deemed to be risk averse and to of effort by everyone in the team. by the Alliance participants, quite often design a very expensive Having a dedicated risk management rather than allocated to individual but safe and proven solution. On the team who will be working closely companies. A shared spirit of co- other hand, contractors were prone to alongside the other project team operation and openness is a must. taking a more cost-effective approach members, firstly educating and Communication is to be open, to delivering a project but without then embedding alliance principles transparent and honest to enable compromising safety. These attitudes (all risks are shared), is crucial. informed decision making. In have become outdated but are still By adhering to Alliance risk addition, the agreement highlighted prevalent within some organisations. values, the WCA risk team was able that the members are to act at all Working as an alliance means to identify and assess effectively not times in a manner that is consistent forgetting about your parent company only the Alliance risks but also the with a “Best for Project” approach. attitude towards risk and to start client risks which could affect the However, you do not get five acting as one entity with a “Best for programme of works. Consequently, different companies with possibly Project” approach which ultimately, if the WCA risk team was given the differing cultures and approaches followed, will bring the best reward for responsibility of managing the client to risk management to participate everyone. This is due to all identified risks associated with the project 30 Enterprise Risk Reprinted courtesy of Enterprise Risk magazine and the Institute of Risk Management as well. This gave the project team the detailed design outcome. Late an effective way of escalating risks access requirement for Platform which are outside of their control 10 was approved. Key members but still needed to be managed. from throughout the rail industry Regular risks reviews/workshops (Network Rail, train operators, were held where the project team station management and others) would highlight a risk which was came together to mitigate the risk of outside of their control to deal with cancellation of the main possession. and discuss this with the client to find There was also the risk or the best solution to mitigate the risk. re-prioritisation for key plant, Key risks were managed eg KIROW cranes and tampers. collaboratively by the client and Nationally there is a limited number the Alliance members. Firstly, of certain plant’s availability there were access-related risks which is based on how critical the (cancellation or not approving project is. The required plant was required access). The majority of secured for all planned works. rail-related jobs are dependent on Several other key risks were the possibility of track line closures also faced. These included the in order to deliver scheduled works. risk of working with existing old Interdisciplinary This is usually considered to be infrastructure, which could introduce collaboration is a key risk for rail projects. WCA substantial additional scope. WCA essential to an had requested an extension of the work scope had interfaces with very 24-day main possession working old buffer stops (which potentially effective alliance area quite late due to results from needed to be replaced), Victorian CURRENT RISK MANAGEMENT SET-UP VERSUS TRADITIONAL RISK MANAGEMENT SET-UP Client Risks Client Risk team Client Risks Alliance Risk Alliance Risk team team Alliance Alliance Alliance Alliance Alliance Alliance Alliance Alliance risks for risks for ... risks for risks for risks for risks for ... risks for risks for Project 1 Project 2 Project N-1 Project N Project 1 Project 2 Project N-1 Project N (Note: Highlights that the process is much leaner and reduces additional layers of communication) Spring 2018 31 Reprinted courtesy of Enterprise Risk magazine and the Institute of Risk Management arches (which may not be able to take management.
Recommended publications
  • Statement of Case Made by First MTR South Western Trains Limited 22Nd
    ADA49_SWR Statement of Claim Page 1 of 105 ADA49: Statement of Case made by First MTR South Western Trains Limited 22nd January 2020 22/1/20 ADA49_SWR Statement of Claim Page 2 of 105 1. DETAILS OF PARTIES 1.1 The names and addresses of the parties to the reference are as follows:- (a) First MTR South Western Trains Limited, a company registered in England under number 2904587 having its registered office at 4th Floor, Capital House, 25 Chapel Street, London, NW1 5DH (“SWR”) ("the Claimant")); and (b) Network Rail Infrastructure Limited, a company registered in England under number 2904587 having its registered office at 1 Eversholt Street, London NW1 2DN ("Network Rail") ("the Defendant")). (c) Correspondence details of SWR’s contacts are as follows: a) Dave Waldron, Current Performance Manager SWR, South Bank Central, 30 Stamford Street, London SE1 9LQ: [email protected] : 07585 405449; and b) David Rourke, Regulatory Access Manager SWR, South Bank Central, 30 Stamford Street, London SE1 9LQ: [email protected] : 07814 347296. 2 THE CLAIMANT’S’ RIGHT TO BRING THIS REFERENCE 2.1 This matter is referred to an Access Dispute Adjudication (“ADA”) for determination in accordance with Schedule 8 paragraph 16.1 of the Track Access Contract dated 20th May 2004 between SWR and Network Rail (“the Agreement”1). The clause in question, namely Schedule 8 paragraph 16.12, reads as follows: 2.2 Having followed the process outlined in Schedule 8 paragraph 16.1, above (including making a joint submission to the Delay Attribution Board, which was considered at a hearing on 19th November 2019, the conclusions arising from 1 This was the Track Access Contract that was in place, between the parties, at the time of each of the three incidents from which this Statement of Claim arises.
    [Show full text]
  • Wessex Capacity Alliance
    Project Waterloo Station upgrade Location London, UK Client Network Rail Expertise Rail systems, civil, structural, building services, geotechnical, environmental and fire engineering; security and ergonomic design International rescue Joined-up thinking and clever engineering have allowed a former international terminal to be brought back to life as part of a bigger, better Waterloo Station Waterloo Station upgrade I Mott MacDonald I 3 “ By signing up to the charter we are all pulling in the same direction, delivering value for money.” David Barnes Wessex Capacity Alliance deputy manager Britain’s Improving the passenger experience for the 99M people who use Waterloo Station every year involves busiest railway much more than the word ‘upgrade’ implies. There station, London is major viaduct reconstruction, a new connection to London Underground, demolition of some sections Waterloo, is of platforms and extension of others, construction undergoing a of a new roof and pedestrian bridge, and a huge amount of new railway infrastructure to be installed. £400M upgrade to increase Programmed around the normal working of the station and right under the public’s nose, the first nine months capacity. on site saw demolition taking place only a nibble at a time – a portion of track removed here or a new piece of infrastructure installed there – to limit disturbance. Waterloo Station is served by the South West Mainline, the Reading and Windsor lines and suburban lines connecting London with the South and South West of England. By 2043, the number of journeys made on the route is expected to increase by 40%. Anyone using the service at peak time will be familiar with how busy trains can become.
    [Show full text]
  • Dust Monitoring on the London Underground Network
    Report No. 4RS-APO-153196-R517226-Rev01 RESPIRABLE AIRBORNE DUST MONITORING AT VARIOUS LONDON UNDERGROUND STATIONS AND TRAIN LINES Prepared for: Mrs Louise Dearman Occupational Hygiene Adviser Tfl – RAIL and Underground 1st Floor Petty France London SW1H 0BD Issue Date: 22nd September 2016 Prepared by: Ms A. Popa Technologist Signature: .......................... Certified by: Mr J. Bailey Senior Consultant Signature: ............................ VAT Registration No: 691 5975 82 Registered Office: Unit 3, Metro Centre, Britannia Way, London, NW10 7PA Registered in England No: 3256863 Respirable Airborne Dust Monitoring At Various London Underground Stations And Train Lines CONDITIONS OF ISSUE OF REPORTS. THIS REPORT IS ISSUED IN CONFIDENCE AND SHALL NOT BE REPRODUCED, EXCEPT IN FULL, WITHOUT WRITTEN APPROVAL FROM 4-RAIL SERVICES. FURTHER INFORMATION. REQUESTS FOR ADDITIONAL INFORMATION ON THE SUBJECT OF THIS REPORT OR OTHER QUERIES SHOULD BE ADDRESSED TO THE AUTHOR. REPORT ISSUE DATE REVISION DETAILS REVISION INITIAL 8TH JULY 2016 ISSUED FOR COMMENT REV 01 22ND SEPTEMBER 2016 REPORT UPDATED TO INCLUDE A REPEAT OF THE DISTRICT LINE TRAIN CAB MONITORING, FOLLOWING DAMAGED FILTER RESULTS. 4-RAIL Services Report No. 4RS-APO-153196-R517226 - Rev01 Page 2 of 69 Respirable Airborne Dust Monitoring At Various London Underground Stations And Train Lines CONTENTS Page Executive Summary .................................................................................................................... 4 1.Introduction ..............................................................................................................................
    [Show full text]
  • 156 Wimbledon – Clapham Junction – Vauxhall
    156 Wimbledon – Clapham Junction – Vauxhall 156 Mondays to Fridays WimbledonSirCyrilBlackWay 0530 0545 0600 0615 0627 0639 0649 0659 0709 0719 0825 1905 1917 1929 WimbledonStation 0532 0547 0602 0617 0629 0641 0651 0701 0711 0721 Then 0828 Then 1908 1920 1932 WimbledonParkTheWoodman 0539 0554 0610 0625 0637 0649 0701 0712 0722 0732 about 0841 about 1919 1931 1943 SouthfieldsCommunityCollege 0542 0557 0613 0628 0640 0654 0706 0717 0727 0737 every8-9 0846 every10 1923 1935 1947 WandsworthBuckholdRoad 0546 0601 0618 0633 0645 0701 0713 0724 0734 0744 minutes 0853 minutes 1930 1942 1954 ClaphamJunctionStJohn'sHill 0554 0611 0628 0643 0657 0713 0725 0736 0746 0756 until 0905 until 1943 1955 2007 BatterseaParkStation 0601 0620 0638 0657 0712 0729 0741 0752 0802 0812 0921 1955 2007 2019 VauxhallStationBusStation 0608 0627 0645 0704 0720 0737 0749 0800 0810 0820 0928 2003 2015 2027 WimbledonSirCyrilBlackWay 1941 1953 2005 2017 2029 2041 2053 2105 2117 2129 2141 2153 ##05 ##17 ##29 0005 WimbledonStation 1944 1956 2007 2019 2031 2043 2055 2107 2119 2131 2143 2155 ##07 ##19 ##31 0007 WimbledonParkTheWoodman 1955 2007 2018 2028 2040 2052 2104 2116 2128 2140 2152 ##04 ##15 ##27 ##38 Then 0014 SouthfieldsCommunityCollege 1959 2010 2021 2031 2043 2055 2107 2119 2131 2143 2155 ##07 ##18 ##30 ##41 every12 0017 WandsworthBuckholdRoad 2006 2016 2026 2036 2048 2100 2112 2124 2136 2148 ##00 ##12 ##23 ##34 ##45 minutes 0021 ClaphamJunctionStJohn'sHill 2018 2028 2038 2048 2059 2109 2121 2133 2145 2157 ##09 ##20 ##31 ##42 ##53 until 0029 BatterseaParkStation
    [Show full text]
  • South London Sub-Regional Transport Plan
    1 2 Contents Mayoral foreword 2 London Councils foreword 2 Executive summary 3 Chapter 1: Introduction 7 Chapter 2: Supporting economic development and population growth 27 Chapter 3: Enhancing the quality of life for all Londoners 61 Chapter 4: Improving the safety and security of all Londoners 79 Chapter 5: Improving transport opportunities for all Londoners 85 Chapter 6: Reducing transport‟s contribution to climate change & 91 improving its resilience Chapter 7: Supporting delivery of London 2012 Olympic and 95 Paralympic Games and its legacy Chapter 8: Key places in north sub-region 96 Chapter 9: Delivery of the Plan and sustainability assessment 105 Chapter 10: Next steps 108 Appendices Appendix 1: Implementation Plan 113 Appendix 2: Roles and responsibilities for managing London‟s strategic road corridors 118 1 Mayoral foreword London Councils‟ foreword Following my election in 2008, I set out my desire for TfL to “listen and learn Boroughs play a key role in delivering the transport that London needs and deserves. from the boroughs...help them achieve their objectives and... negotiate However, there are many transport issues that cross borough boundaries and this is solutions that will benefit the whole of London” (Way to Go, November 2008). where the Sub-regional Transport Plans (SRTPs) are particularly important. The SRTPs TfL thus embarked on a new collaborative way of working based on sub-regions. fill the gap between the strategic policies and proposals in the Mayor‟s Transport Strategy (MTS) and the local initiatives in boroughs‟ Local Implementation Plans (LIPs). As well as better collaboration, the sub-regional programme has led to an We have very much welcomed the GLA and TfL‟s willingness to engage with London improved modelling and analytical capability, that has enabled changes within Councils and the boroughs on the development of the SRTPs over the last couple of the sub-regions to be better understood and provided for.
    [Show full text]
  • Long Leasehold Vacant Possession Investment Opportunity
    1 Long Leasehold Vacant Possession Investment Opportunity Exceptional commercial opportunities within the prestigious Nine Elms neighbourhood in Battersea VISUAL OF THE COMMERCIAL ACCOMMODATION WELCOME TO 2 Nine Elms represents a beautiful new riverside neighbourhood with some fantastic 3 bars and restaurants, flourishing from the influx of new quality residential and office accommodation. Lexington Gardens forms part of the Nine Elms development, sitting alongside complementary mixed use developments including Embassy Gardens and the new US Embassy. The investment into the public realm of Nine Elms has resulted in a truly unique, tranquil place to live and work, despite the proximity to London’s West End. Please read on to explore the commercial opportunity, whether that be for an office, gym, restaurant, wellness, healthcare or café, we welcome all Use Class E & F occupiers. We hope you enjoy! Computer generated image of the railway arches along Ponton Road. A CITY ON YOUR DOORSTEP The American The Embassy Residence Nine Elms Chelsea Harvey Nichols London Waterloo Underground Station Vauxhall Eye Station (Completion 2021) Station Battersea Underground Station Knightsbridge Harrods Hyde Park Mayfair Battersea Vauxhall (Completion 2021) Power Station Pimlico St James's Park Westminster Bridge The City The Shard Royal Hospital Chelsea Thames Clipper Marylebone Victoria Station 4 5 Computer generated image. CONNECTIVITY THE BRAND NEW BILLION-POUND NORTHERN LINE EXTENSION PUTS THE WEST AND THE CITY ON YOUR DOORSTEP KING’S CROSS/ST. PANCRAS Lexington Gardens is a 3 minute walk from the new Nine Elms Underground station (completion 2021), connecting you to London Bridge in 9 minutes and the City in 11 minutes.
    [Show full text]
  • Keybridge House, Vauxhall SW8 a Brand New Apartment to Let in Keybridge House, Vauxhall, SW8 Through Knight Frank Battersea & Nine Elms
    Keybridge House, Vauxhall SW8 A brand new apartment to let in Keybridge House, Vauxhall, SW8 through Knight Frank Battersea & Nine Elms. Located on the fifth floor with lift and offering 570 sq ft of living space, this apartment comprises of one double bedroom with Firstbuilt inparagraph, storage, one editorial bathroom style, and short, an open considered plan kitchen headline / benefitsreception ofroom. living here. One or two sentences that convey what you would say in person. The property additionally benefits from two forms of outside Secondspace, including paragraph, a private additional northeast details facing of note balcony about theleading off property.from the livingWording / kitchen to add area value and and offering support views image of Vauxhallselection. Park Temand avolum spacious is solor and si secure aliquation private rempore roof terrace, puditiunto perfect qui utatisfor adit,entertaining animporepro friends experit and family et dolupta in the ssuntio summer mos months. apieturere There are ommostifloor to ceiling squiati windows busdaecus throughout cus dolorporum the apartment volutem. flooding the property with natural light. Third paragraph, additional details of note about the property. WordingResidents to in add Keybridge value and House support further image benefit selection. from a Tem24-hour volumconcierge is solor and si residents aliquation gym. rempore puditiunto qui utatis adit, animporepro experit et dolupta ssuntio mos apieturere ommostiAvailable tosquiati let through busdaecus Knight cus Frank dolorporum on a furnished volutem. basis. EPC. B XXX1 1 1 X GreatKeybridge Missenden House 1.5 is locatedmiles, London along Lambeth Marlebone Road, 39 minutes, located next Amershamto Vauxhall 6.5 Park miles, and M40 is only J4 0.5 10 miles,miles from Beaconsfield Vauxhall 11Station.
    [Show full text]
  • London Underground Limited
    Background Paper 1 Developing the Network 1 Introduction 1.1 Bus use has increased by over two-thirds since 1999, driven by sustained increases in the size and quality of the network, fares policy and underlying changes in London’s economy. The bus network is constantly evolving as London develops and the needs and aspirations of passengers and other stakeholders change. Enhancements take place not only to the service pattern but across all aspects of the service. • Capacity. The level of bus-km run has increased by around 40 per cent over the same period. Network capacity has increased by a faster rate, by around 55 per cent, with increases in average vehicle size. Additionally, much improved reliability means that more of the scheduled capacity is delivered to passengers. • Reliability. Effective bus contract management, in particular the introduction of Quality Incentive Contracts, has driven a transformation of reliability. This has been supported by bus priority and by the effects of the central London congestion charging scheme. Service control has been made more efficient and effective by iBus, TfL’s automatic vehicle location system. 4.0 3.5 3.0 2.5 2.0 1.5 Excess Wait Time (mins) 1.0 0.5 0.0 1977 1979 1981 1983 1985/86 1987/88 1989/90 1991/92 1993/94 1995/96 1997/98 1999/00 2001/02 2003/04 2005/06 2007/08 2009/10 2011/12 2013/14 Figure 1: Excess Waiting Time on high-frequency routes – since 1977 • Customer service. All bus drivers must achieve BTEC-certification in customer service and other relevant areas.
    [Show full text]
  • Tfl Investment Programme Report – Second Quarter 2013/14
    Agenda Item 4 Transport for London Projects and Planning Panel Subject: TfL Investment Programme Report – Second Quarter 2013/14 Date: 13 November 2013 1 Purpose 1.1 The Investment Programme report for the second quarter of 2013/14 (23 June – 15 September 2013) is attached to inform the Panel of TfL’s Investment Programme performance. 2 Recommendation 2.1 The Panel is asked to note this report. 3 Contact 3.1 Contact: Steve Allen, Managing Director, Finance Number: 020 7126 4918 Email: [email protected] Investment Programme Report Second Quarter June – September 2013/14 Table of Contents 1. Programme Highlights and Key Concerns............................................................................. - 3 - 2. Projects (over £50m) and Programmes (over £10m per annum) ............................................ - 5 - Sub-Surface Railway (SSR) Upgrade ................................................................................. - 6 - Track Renewal (BCV/SSR) .............................................................................................. - 12 - Civils (BCV/SSR) ............................................................................................................ - 14 - Track (JNP) ................................................................................................................... - 16 - Cooling the Tube Programme ....................................................................................... - 18 - SSR Major Power Works (Signalling)..............................................................................
    [Show full text]
  • Vauxhall Nine Elms Battersea Opportunity Area Planning Framework
    Vauxhall Nine Elms Battersea Opportunity Area Planning Framework March 2012 Copyright Acknowledgements Greater London Authority Project Team Colin Wilson March 2012 Tava Walton Claire O’Brien Lee Campbell Published by Yogesh Patil Jasper den Boeft Greater London Authority Far more people than it is possible to City Hall thank individually have contributed to the The Queen’s Walk production of the framework. They include the major landowners and their planning, More London transport and design teams; officers of Transport for London, Design for London London SE1 2AA and English Heritage; consultants who have contributed to the various technical studies and reports; the design review team Enquiries 020 7983 4100 at Design Council CABE; and many others. Without them, neither the framework nor the Minicom 020 7983 4458 progress that has already been made towards its implementation would have been possible. www.london.gov.uk Special thanks go to present and past officers and members of Lambeth and Wandsworth Cover photograph © Colin Wilson Councils for their continuing hard work and commitment to the project; and to Urban Graphics and Z Mapping for their assistance with the production of the document itself. Vauxhall Nine Elms Battersea Opportunity Area Planning Framework March 2012 i Vauxhall Nine Elms Battersea Opportunity Area Planning Framework Mayor’s foreword I am delighted to introduce this Opportunity homes and 20-25,000 jobs, supported in developers, under the guidance of the Area Planning Framework for Vauxhall Nine transport terms by a two-station extension Strategy Board. Sir Simon Milton was an Elms Battersea. of the Northern line from Kennington to integral part of this process until his untimely Battersea via Nine Elms.
    [Show full text]
  • The Iron Road Book and Railway Companion from London to Birmingham, Manchester, and Liverpool
    LIB R.AHY OF THE U N I VLR.S ITY OF ILLINOIS 385!0942 C&si 1838 I'll V, WATFORD •STATION Bushev <rvove bJlxtr<r Bey/tie i jfhtir i' tLuTon Jmu Benton ''f'Boisdon Hbnwev, BaiLBoads Canals. Turnpike Bonis irossBoads County Hound™■ THE IRON ROAD BOOK AND <smasmsra<i>sf FROM LONDON TO BIRMINGHAM, MANCHESTER, AND LIVERPOOL, CONTAINING AN Account of the Towns, Villages, Mansions, fyc. ON EACH SIDE OF THE LINE ; Times of Arrival and departure of the Trains AT THE SEVERAL STATIONS, Coaches and Omnibuses to the Towns in the Vicinity, WITH TABLES OF DISTANCES AND FARES FROM STATION TO STATION &C. &C. JUustratetr toitfj JRaps ot tf)e entire Htne. v Bv FRANCIS COGHLAN, : Author of Guides to * Paris,’ ‘St. Petersburgh, * The Rhine,’ * Belgium, ‘ Switzerland,’ * London,’ &c. HonDon: A H. BAILY & Co., 83, Cornhill. 1838. cur i* INTRODUCTION. LONDON £LN& BZIUVIZNGHAIVZ RAILWAY. J . The Act of Parliament for forming this great undertaking was obtained in May 1833, and the works were commenced in June 1834. 1 In July 1837, 24£ miles of the line, adjoining London, were opened to the public. Seventy-seven miles are now opened (viz. forty-eight from the London end, and twenty-nine from the Birmingham end) and in the ensuing autumn the whole of the line ; will be completed. Embankments, &c. v A level line for the Railway was obtained by cutting through the hills, and using the earth therefrom to form embankments. The country throughout is of ^ an undulating character, so that there is scarcely a *s mile throughout the whole length in which cuttings or embankments were not necessary.
    [Show full text]
  • Transport for London Briefing for the Construction Sector 27 July 2020 Introduction
    Transport for London briefing for the construction sector 27 July 2020 Introduction In line with the Government’s easing of lockdown measures, we are working You can help us get more of the to get London back to work safely and construction sector moving and sustainably. This toolkit sets out our working safely, sustainably and latest travel advice for the construction as quickly as possible by: sector as more of its workforce returns to sites across the Capital. • Enabling and encouraging your workforce to walk 1. Our plan and cycle all or part of their journey 2. Help us to help you – what we ask of the construction sector • Helping your workforce to travel at quieter times on the 3. Travel advice for your workforce network by changing your operating hours or staggering 4. Annex – travel advice for your your shifts workforce in Vauxhall Nine Elms, Westminster, The City, • Reducing and retiming the Canary Wharf and Stratford goods and services to and from your site See page 5 for further details of how you can help. 1. Our plan We are implementing our plan to get • To support social distancing and London moving and working again, as help ensure the safety of your safely and sustainably as possible: workforce and others travelling on London’s streets, we have launched • Safety is always our number one the Streetspace for London plan. priority and so our services now Delivered in partnership with London’s must operate differently to enable boroughs, the plan includes new social distancing cycle lanes, widened footways and other changes to London’s streets.
    [Show full text]