APPENDIX I

FORM 1

Basic Information

Sr No. Item Details

1 Name of the project/s Proposed Residential Scheme at Sr. No. 12, Talegaon- Dabhade by Housing and area development board (MHADA)

2 S. No. in the schedule Sr. No. 12, Talegaon - Dabhade

3 Proposed capacity / area / length / Plot area :13097.00 m2 tonnage handled / command area / lease area / number wells to be Total FSI Area:30550.88 m2 drilled Non FSI Area :4746.83 m2

Total Construction area (FSI + Non FSI): 35297.71 m2

4 New/Expansion/Modernization New Building and Construction Project

5 Existing Capacity/Area etc. Not Applicable

6 Category of Project. e.' A' or 'B' Project category B2; Activity under Item 8 (b) of the EIA Notification dated 14th September 2006 as amended on 1st December, 2009 does not require scoping and public consultation

7 Does it attract general conditions? If Not Applicable yes, please Specify

8 Does it attract specific condition? If Not Applicable 'yes, please Specify

9 Location Latitude: 18 043’45.59” N

Longitude: 73 041’04.06” E

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 1

Plot/Survey/Khasra No. Sr. No. 12, Talegaon - Dabhade

Village Talegaon - Dabhade

Tehsil Mawal

District Pune

State

10 Nearest railway station/airport along Ghorawadi Railway Station- 1.44 km with distance in km. Bhegdewadi Railway Station- 4.00 kms

Pune Railway Station - 29.81km

Lohegaon Air port- 28.89 km

Refer Appendix 1_Location Map

11 Nearest Town, city, District Talegaon - Dabhade Nagarparishad, Talegaon - Headquarters along with distance in Dabhade, Pune kms.

12 Village Panchayats, Zilla Parishad Talegaon - Dabhade Nagarparishad, Municipal Corporation, Local body (complete postal addresses with Talegaon - Dabhade, Pune telephone nos. to be given)

13 Name of the applicant Mr. Ashok Kakade

14 Registered Address Maharashtra Housing & Area Development Authority (MHADA), Address:- Grihanirman Bhavan, Agarkar Nagar, Pune -411001

15 Address of correspondence Maharashtra Housing & Area Development Authority (MHADA), Address:- Grihanirman Bhavan, Agarkar Nagar, Pune -411001

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 2

Name Mr.Ashok Kakade

Designation(Owner/Partner/CEO) Developer

Address Maharashtra Housing & Area Development Authority (MHADA), Address:- Grihanirman Bhavan, Agarkar Nagar, Pune -411001

Pin Code 411001

E-mail [email protected]

Telephone No. 020-2612 8082

Fax No. ------

16 Details of Alternative Sites No alternative options have been examined. examined if any. Location of these sites should be shown on a toposheet.

17 Interlinked Projects Not Applicable

Whether separate application of Not Applicable interlinked project has been submitted

If yes, date of submission Not Applicable

If no, reason ------

18 Whether the proposal involves approval/ clearance under: if yes, details of the same and their status to be given:

(a) The Forest (Conservation) Act – a) Not Applicable 1980?

(b) The Wildlife (Protection) act –

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 3

1972? b) Not Applicable

(c) The C.R.Z. Notification, 1991?

c) Not Applicable

19 Whether there is any government No order/ policy relevant/ relating to the site?

20 Forest land involved (hectare) No forest land involved

21 Whether there is any litigation pending against the project and /or the land in which the project is proposed to be set up? Not Applicable (a)Name of the Court

(b)Case No.

(c) Orders/directions of the Court, if any and its relevance with the proposed project

Activity

Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S.No Information/Checklist Yes/ Details thereof (with approximate quantities /rates, confirmation wherever possible) with source of information data No

1.1 Permanent or temporary The site is located at residential zone and no agrictural change in land use, land land is involved. cover or topography NO including increase in intensity of land use (with respect to local

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 4

land use plan)

1.2 Clearance of existing NO Few trees exist on site. land, vegetation and buildings?

1.3 Creation of new land NO Not Applicable uses?

1.4 Pre - construction NO Not Applicable investigations e.g. bore houses, soil testing?

1.5 Construction works? YES General civil construction.

Project comprises of 5 residential buildings. Total Construction area:35297.71 m2

Type of Construction –RCC work & brick work

Refer Appendix 2-Master Layout

Appendix 3-Area Statement

1.6 Demolition works? NO Not Applicable

1.7 Temporary sites used YES Total No. of temporary workers = 100 nos for construction works or housing of Temporary labour camps shall be provided for the construction workers? construction workers.

1.8 Above ground YES Proposed project consist of 5 residential buildings A, B, buildings, structures or C, D & E having configuration P +7. earthworks including linear structures, cut The top soil layer of 200 mm shall be recovered during and fill or excavations excavation work and shall be used for landscaping.

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 5

Excavated material shall be used for back filling, road leveling, and filling during site development.

1.9 Underground works NO The proposed development work does not include any including mining or mining or tunneling. tunneling?

1.10 Reclamation works? NO Not applicable

1.11 Dredging? NO Not applicable

1.12 Offshore structures? NO Not applicable

1.13 Production and NO Not applicable manufacturing processes?

1.14 Facilities for storage of YES During construction the building materials will be goods or materials? temporarily stored within site premises.

Covered storage shall be provided for materials susceptible to fugitive dust emissions.

1.15 Facilities for treatment YES Construction Phase: or disposal of solid waste or liquid Solid wastes such as empty bags, packaging material, effluents? will be properly segregated and will be sent to authorize recyclers.

Operation Phase:

The solid waste generated will be treated through on-site organic waste converter system.

Sewage will be treated through on-site sewage treatment plant.

1.16 Facilities for long term NO The proposed development shall have temporary housing of operational workers during construction phase only. workers?

1.17 New road, rail or sea NO All the traffic related to the construction will make use traffic during of existing service roads. construction or operation?

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 6

1.18 New road, rail, air NO Not Applicable. waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

1.19 Closure or diversion of NO Not Applicable. existing transport routes or infrastructure leading to changes in traffic movements?

1.20 New or diverted NO Not Applicable transmission lines or pipelines?

1.21 Impoundment, NO Not Applicable damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

1.22 Stream crossings? NO Not Applicable

1.23 Abstraction or transfers NO Water requirement in the construction phase will be of water form ground or supplied from private water tankers. surface waters? Source of water for occupants during operational phase: Talegaon - Dabhade Nagarparishad, Talegaon-Dabhade, Pune

1.24 Changes in water NO No change in the water bodies or the land use surface bodies or the land affecting natural drainage ways. The site development surface affecting and hard areas on site shall generate run-off. The storm drainage or run-off? water management plan has been designed accordingly.

1.25 Transport of personnel YES Road traffic of the area will increase temporary during or materials for construction and permanently during operation phase construction, operation

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 7

or decommissioning? Construction Phase:

Transportation of material will be undertaken within the site through lorries/dumpers.

Transportation of labour will be undertaken on the site through transport vehicles.

Operational Phase:

Road traffic of the area will increase permanently during operation phase.

1.26 Long-term dismantling NO Not Applicable or decommissioning or restoration works?

1.27 Ongoing activity during NO Not Applicable decommissioning which could have an impact on the environment?

1.28 Influx of people to an YES There will be temporary influx of labours during the area in either construction phase and influx of commercial users temporarily or during the operational phase. permanently?

1.29 Introduction of alien NO Proposed landscape plan includes native & local trees species? only

1.30 Loss of native species NO Not applicable or genetic diversity?

1.31 Any other actions? NO Not applicable

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 8

S.No Information/checklist Yes/No Details there of (with approximate quantities /rates, . confirmation wherever possible) with source of information data

2.1 Land especially NO Plot area (sq. m.) : 13097.00 m 2 undeveloped or Non FSI Area : 4746.83 m2 agricultural land (ha) Total Construction area (FSI + Non FSI): 35297.71 m2

2.2 Water (expected source Construction Phase:- & competing users) Source: Authorized private water tankers. unit: KLD Total water requirement for construction activity =4.37 kld

Labour water consumption = 4.5 kld

Operational Phase:-

Source: Talegaon -Dabhade Nagarparishad. Total Water Requirement: 494.04 m 3/day (Including landscape)

• Fresh water: 321.75 m3/day

• Waste water generation : 434.37 m 3/day

• Treated water from STP for reuse: 390.93 m 3/day

• Flushing water requirement:160.88 m 3/day

• Landscape water - 11.42 m 3/day

Treated waste water from STP shall be used for landscaping & flushing.

Refer Appendix 4- Water Balance Chart

2.3 Minerals (MT) NO No minerals will be used for the construction purpose.

2.4 Construction material – YES Construction materials such as cement, steel, metal stone, aggregates, sand sand and bricks will be procured from authorized / soil (expected source dealers.

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 9

– MT)

2.5 Forests and timber NO Not Applicable (source – MT)

2.6 Energy including YES Connected Load :1140 KW electricity and fuels (source, competing Demand load :1710 KW users) Unit: fuel (MT), Backup power energy (MW) DG set of125 kvA X 2 capacity will be provided

• Type of fuel used: Diesel

Source : - Maharashtra State Electricity Distribution Company Limited (MSEDCL)

2.7 Any other natural NO No other natural resources will be used for the resources (use construction purpose. appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S.No. Information/Checklist Yes/No Details thereof (with approximate quantities/rates, confirmation wherever possible) with source of information data

3.1 Use of substances or NO Not Applicable materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

3.2 Changes in occurrence NO All the waste generated will be managed properly and of disease or affect no conditions will prevail to affect epidemiology. disease vectors (e.g. insect or water borne

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 10

diseases)

3.3 Affect the welfare of YES There will be economic growth and improved quality people e.g. by of life with additional employment. The project will changing living not have any negative impact on human welfare. conditions? Amenities will get better developed due to this kind of development.

3.4 Vulnerable groups of NO Not Applicable people who could be affected by the project e.g. hospital patients, children, the elderly etc.,

3.5 Any other causes NO Not Applicable

4. Production of solid wastes during construction or operation or decommissioning

S.no. Information/Checklist Yes/No Details thereof (with approximate quantities/rates, confirmation wherever possible) with source of information data

4.1 Spoil, overburden or NO No mine waste involved as this is Residential mine wastes project. Excavated material shall be reused for back filling purposes on site.

4.2 Municipal waste YES Construction Phase (domestic and or commercial wastes) Total expected labors = 100 nos. Total Municipal Solid Waste Generation: 20 kg/ day

Organic: 12 kg/day

Inorganic: 8 kg/day

Operational Phase:

Total generation of Municipal Solid Waste: 1787.5 kg/day

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 11

Organic : 1072.5 kg/day

Inorganic: 715 kg/day

E-Waste: 7.15 kg/day

Refer Appendix 5- Solid Waste Management Plan.

4.3 Hazardous wastes (as NO Not Applicable per Hazardous Waste

Management Rules)

4.4 Other industrial NO Not applicable as the proposed development is a process wastes Residential Development.

4.5 Surplus product NO Not Applicable

4.6 Sewage sludge or YES Sludge generated from STP will be used as manure other sludge from on site. Sludge drying beds shall be provided on site. effluent treatment

4.7 Construction or YES Construction waste will be generated on site during demolition wastes construction and it will be reused on site for refilling.

4.8 Redundant machinery NO Not Applicable or equipment

4.9 Contaminated soils or NO Not Applicable other materials

4.10 Agricultural wastes NO Not Applicable

4.11 Other solid wastes NO Not Applicable

5.Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 12

S. Information/Checklist Yes/No Details thereof (with approximate quantities/rates, No confirmation wherever possible) with source of information data

5.1 Emissions from YES Vehicular movement and DG sets will be point combustion of fossil sources of air pollution. fuels from stationary or mobile sources

5.2 Emissions from NO Not Applicable production processes

5.3 Emissions from YES Storage and handling of material will cause emissions materials handling of fugitive dust during construction. including storage or transport

5.4 Emissions from YES Dust will be generated from excavation and other construction activities construction activities. Measures will be taken to including plant and reduce/ control the emissions. equipment

5.5 Dust or odors from YES Dust will be generated during transport and handling of materials including construction Handling of material. Measures will be taken to materials, sewage and reduce/ control the emissions. waste

5.6 Emissions from NO No incineration activities are involved in the incineration of waste proposed development.

5.7 Emissions from NO No material will be burnt within the project premises. burning of waste in open air (e.g. slash materials, construction debris)

5.8 Emissions from any NO Not Applicable. No other activities apart from other sources construction & transportation are involved which would generate emissions.

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 13

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.N Information/Checklist Yes/No Details thereof (with approximate quantities/rates, o confirmation wherever possible) with source of information data with source of information data

6.1 From operation of YES Construction phase equipment e.g. engines, ventilation The machinery, equipments and vehicles used during plant, crushers construction activities will generate noise. Appropriate control measures will be undertaken to reduce the noise during construction phase.

Operation phase

This phase will involve noise generation due to the use of equipments, vehicular traffic and DG sets.

Appropriate control measures will be undertaken to reduce the noise during construction and operation phase.

6.2 From industrial or NO Not applicable similar process’s

6.3 From construction or YES Construction will involve noise generation. Measures demolition will be taken to minimize the impacts of the noise.

6.4 From blasting or YES There will be temporary and intermittent noise piling generation from drilling activity during foundation.

6.5 From construction or YES Temporary noise influx during construction phase due operational traffic to vehicles like trucks, tractors, lorries etc. and during construction activities.

Permanent marginal noise disturbance due to traffic during operational stage

6.6 From lighting or NO Not applicable cooling systems

6.7 From any other sources NO Not applicable

7. Risks of contamination of land or water from releases of pollutants into the ground or into Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 14

sewers, surface waters, groundwater, coastal waters or the sea:

S.No Information/Checklist Yes/No Details thereof (with approximate quantities/rates, . confirmation wherever possible) with source of information data

7.1 From handling, NO Not Applicable storage, use or spillage

of hazardous materials

7.2 From discharge of NO Sewage generated within the project will be treated sewage or other within the project premises. The recycled water will effluents to water or be reused for landscaping and flushing. the land (expected mode and place of Operation Phase: discharge) Expected waste water from proposed Project = 434.37 m3/day Total waste water recovered for reuse from proposed buildings = 390.93 m3/day (@ 95% STP treatment efficiency)

Treatment of the waste water generated –

One STP Proposed of 460 m3/day

Use of treated water for flushing purpose in proposed project =160.88 m3/day

Use of treated water for landscaping purpose =11.42 m3/day

Quantity of treated waste water to be disposed of to PMC sewer drains = 230.05 m3/day

Refer Appendix 4 Water Balance Chart

7.3 By deposition of NO Not applicable pollutants emitted to air into the land or into water

7.4 From any other NO Not applicable sources

7.5 Is there a risk of long NO Not applicable

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 15

term build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could

affect human health or the environment

S.No Information/Checklist Yes/No Details thereof (with approximate quantities/rates, confirmation wherever possible) with source of information data

8.1 From explosions, NO spillages, fires etc from storage, handling, use or production of hazardous substances

8.2 From any other causes NO Not applicable

8.3 Could the project be YES The project area falls under Zone III as per Map affected by natural showing Seismic Zones of . Zone III is of disasters causing moderate Seismic Intensity. The building design environmental damage has been planned accordingly. (e.g. floods, earthquakes, landslides, cloudburst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

S. Information/Checklist Yes/No Details thereof (with approximate quantities/rates, No. confirmation wherever possible) with source of information data

9.1 Lead to development of YES Proposed project is a Residential development supporting utilities, project. ancillary development Infrastructure that accompanies proposed Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 16

or development development include: stimulated by the project which could STP for treatment and recycling of waste water have impact on the generated on site. environment e.g.: Provision for treatment of organic waste generated on site by OWC.

• Supporting Landscaping infrastructure (roads, Rainwater harvesting system power supply, waste or waste water treatment, Use of Renewable energy as Solar PVs and DG Sets etc.) for backup.

a. Housing development Proposed supporting infrastructure would lead to development of sustainable habitat. b. Extractive industries

c. Supply industries

d. Other

9.2 Lead to after-use of the NO Not applicable site, which could have an impact on the environment

9.3 Set a precedent for later NO Not Applicable. developments

9.4 Have cumulative effects NO Not applicable due to proximity to other existing or planned projects with similar effects

(II) Environmental Sensitivity

S.No Areas Name/ Aerial distance . (within 15 km.) Identity Proposed project

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 17

location boundary

1 Areas protected under NO Not Applicable international conventions, national or local legislation for their ecological, landscape, cultural or other related value

2 Areas which are 3.00 km important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests

3 Areas used by NO Not applicable protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

4 Inland, coastal, marine NO Not applicable or underground waters

5 State, National NO Not applicable boundaries

6 Routes or facilities NO Not applicable used by the public for access to recreation or other tourist, pilgrim areas

7 Defense installations NO Not applicable

8 Densely populated or NO The site is not built-up area located in densely populated or built- Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 18

up area.

9 Areas occupied by Educational Facilities: Schools sensitive man-made land uses (hospitals, High Vision English Medium School 3.42 km schools, places of Jain Englisgh Medium School 1.46 km worship, community facilities) Swami Vivekanand School 1.06 km

Hutchings High School 0.97 km

St. Anna's High School 2.53 km

Heritage School By Pearson 3.77 km

Educational Facilities: College

Indrayani College Talegaon 0.76 km

Nutan Maharashtra Institute of 2.10 km Engineering And Technology

Maeer's Physiotherapy College 1.48 km

Mimer Medical College 1.30 km

D. Y. Patil College of Engineering , 3.60 km Ambi

Meinerva College of Architecture 4.00 km

Dr. D. Y. Patil Educational Federational 2.10 km Hospitals: 2.70 km Pioneer Hospital Morya Speciality Hospital 1.48 km

Layans Bhandari Hospital 1.25 km

Mouli Hospital 0.6 km Talegaon General Hospital 1.20 km

Pawar Hospital 0.90 km 1.50 km

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 19

Sevadham Hospital 1.97 km Athrva Accident Hospital Harneshwar Hospital 2.18 km 0.61 km Shushrut E N T hospital & Dr. Khans Reaserch Centre

Markets:

Laxmi super market 0.41 km

Shree Gurudatta Super market 0.90 km 10 Areas containing NO Not applicable important, high quality or scarce resources

(ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

11 Areas already subjected NO Not applicable to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

12 Areas susceptible to NO Earth Quake Zone natural hazard which III could cause the project to present environmental Therefore, all problems (earthquakes, relevant design subsidence, landslides, parameters as per erosion, flooding or zone III have been extreme or adverse considered for RCC climatic conditions) design of the buildings.

Form 1 -Proposed Residential Development at Sr. No. 12, Talegaon - Dabhade by MHADA, PUNE 20