INITIAL ENVIRONMENTAL EXAMINATION

UPDATED

PROJECT NUMBER: 49107-006 NOVEMBER 2020

IND: DRINKING WATER SECTOR IMPROVEMENT PROJECT – BULK WATER SUPPLY FOR TWO BLOCKS IN (Package DWW/BK/01) – PART B

PREPARED BY PUBLIC HEALTH ENGINEERING DEPARTMENT, GOVERNMENT OF WEST BENGAL FOR THE ASIAN DEVELOPMENT BANK

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. will mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work.

289. The public participation processes undertaken during project design ensured that stakeholders were engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

290. The project’s grievance redress mechanism has provided the citizens with a platform for redressal of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

291. The EMP will assist the project agencies and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally-sound execution of the proposed project.

292. A copy of the EMP/approved SEMP is kept on-site during the construction period at all times. The EMP has been made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

293. Groundwater in these two blocks are contaminated with fluoride and water level is depleting. The project will benefit the general public by contributing to the long-term improvement of water supply system and community liability in the project blocks of Indpur and . The potential adverse environmental impacts are mainly related to the construction period, which can be minimized by the mitigating measures and environmentally-sound engineering and construction practices.

294. Therefore, as per ADB SPS, the project is classified as environmental Category B and does not require further environmental impact assessment. However, to conform to government guidelines WTP requires consent for establish (CTE) and consent for operate (CTO) from West Bengal Pollution Control Board. Consent to Establish (CTE) is already obtained from West Bengal Pollution Control Board.

295. This IEE shall be updated during implementation of the project to reflect any changes, amendments and will be reviewed and approved by PMU.

296. Recommendations. PMU, PIUs, and contractors to ensure that: (i) package wise details and evidences such as photographs/display board for grievance redress mechanism (GRM)/health and safety (H&S) measures taken at work sites due to COVID 19 pandemic are included in monthly monitoring report; and (ii) ensure that efficient implementation of the H&S Plan developed by the project in response to COVID-19 pandemic. Important protocols or measures in the H&S Plan are to ensure that the following are complied with at the offices and worksites of the project: (i) screening of employees and workers; (ii) record keeping of screening results; (iii) availability and use of appropriate PPEs; (iv) social distancing; (v) proper office set up reconfiguration to ensure social distancing; (vi) new office and work site meeting arrangements; and (vii) regular disinfection of work areas, vehicles and equipment; among others. PIU safeguards officer with the assistance of the safeguards experts of PMC/DSISCs and Contractors EHS officers of all districts are reminded to take precautions, provide continuous induction and continue conducting regular safeguards implementation trainings including implementation monitoring of regular usage of PPEs and COVID-19 related safety measures. Key reminders for the PMU, PIUs, contractors, and workers to comply with the

P a g e | 120

following occupational health and safety measures as stated in the agreed OHS Plan:

(i) Ensure project staff, consultants, contractors, and workers have in their mobile devices the Aarogya Setu App, which is a mobile application developed and recommended by the government to proactively reach out to and inform the users of the app regarding risks, best practices and relevant advisories pertaining to the containment of COVID-19; (ii) Mandatory isolation of the personnel or workers, either asymptomatic or showing symptoms, who have had direct contact with anyone tested positive for COVID- 19. Follow the isolation procedures issued by the government; (iii) Proper disposal of used PPE following guidelines and procedures issued by the government; (iv) Conduct daily briefing on the developments of COVID-19 in the state or country, either through emails, meetings or daily toolbox talks; (v) When possible, allow work from home arrangement based on the nature of jobs; (vi) If necessary, pick up and drop off facility be extended to staff (based on the distance of the staff residence from office and on availability of safe mode of transport); (vii) Avoid face to face meetings – critical situations requiring in-person discussion must follow social distancing. Do not convene in-person meetings of more than 10 people; (viii) If possible, conduct all meetings via conference calls. Recommend use of cell phones, texting, web meeting sites and conference calls for project discussions; (ix) Contractor to help its workers arrange a systematic procurement of all daily needs and groceries at worksites. This will avoid each and every worker going to shops for these daily needs; (x) Contractor to arrange for contactless payment of wages to workers, where possible; (xi) Allow distributed breaktimes for workers to maintain social distancing and reduce contact; (xii) Remind employees and workers to maintain good health by getting adequate sleep; eating a balanced and healthy diet, avoiding alcohol/smoking; and consuming plenty of fluids; and (xiii) Remind employees and workers to extend their adherence to the H&S protocols at their respective homes. Infection may happen beyond the borders of offices and work sites.

P a g e | 121

Appendix 1: Rapid Environmental Assessment Checklist Country / Project Title: / West Bengal Drinking Water Sector Improvement Project (WBDWSIP) Indpur and Taldangra Blocks of : Bulk Water Supply Sub-Project

Sector Division: Sub-Project Urban Development SCREENING QUESTIONS Yes No REMARKS Water Supply A. Project Siting Is the project area • Densely populated? √ Project area is not densely populated • Heavy with development √ Mostly rural area. No heavy development activity is activities? noticed • Adjacent to or within any √ No as such environmental sensitive areas nearby environmentally sensitive areas? • Cultural heritage site √ Few religious places are observed but no cultural heritage site is located nearby the project area • Protected Area √ No protected area nearby • Wetland √ No designated wetland within the project area • Mangrove √ • Estuarine √ • Buffer zone of protected area √ • Special area for protecting √ No Special area for protecting biodiversity biodiversity • Bay √ B. Potential Environmental Impacts √ Will the Project cause • Pollution of raw water supply √ Not expected as per site conditions. Water from upstream wastewater discharge surveillance program will be included to monitor the from communities, industries, agriculture raw water quality. and soil erosion runoff? • Impairment of historical / cultural √ No impact expected. No cultural monuments and monuments / areas and loss/ damage to historical sites near project locations. these sites? • Hazard of land subsidence √ Not applicable; subproject does not involve caused by excessive ground water groundwater abstraction. Water from the reservoir to pumping? be used and with no risk of land subsidence.

P a g e | 122

SCREENING QUESTIONS Yes No REMARKS • Social conflicts arising from √ Project does not involve land acquisition/ displacement of communities? displacement. No social conflicts envisaged • Conflicts in abstraction of raw √ Project involves new surface water source water for water supply with other development on reservoir which has beneficial water uses for surface and abundant quantity of water throughout the year, even ground waters? during the lean flow season (February to May). NOC for abstraction of 32 MLD water from the Mukutmanipur dam for this project has been obtained from IWD, rest 12 MLD under process. There is no ground water abstraction as a part of this sub project. • Unsatisfactory raw water supply √ Quality of raw water is in general, of acceptable quality (e.g. excessive pathogens or mineral and that can be used for potable purposes after constituents)? conventional treatment and disinfection. Water quality testing should be done before treatment and after treatment. • Delivery of unsafe water to √ Water will be treated and disinfected prior to supply distribution system? the water treatment plant will ensure all quality criteria set by CPCB for drinking water standards. • Inadequate protection of intake √ Water quality surveillance program will be included to works or wells, leading to pollution of monitor the raw water quality. water supply? • Over pumping of ground water, √ Not applicable; subproject does not involve leading to salinization and ground groundwater abstraction subsidence? • Excessive algal growth in √ Regular cleaning of storage tanks will be conducted storage reservoir? during operation • Increase in production of sewage √ Sanitation and sewerage system will be improved/ beyond capabilities of community developed in the project area facilities? • Inadequate disposal of sludge √ Appropriate provisions for sludge drying and disposal from water treatment plants? is included in the project • Inadequate buffer zone around √ Adequate buffer is available; all the pumping stations pumping and treatment plants to will be located in enclosed buildings with noise control alleviate noise and other possible walls to minimize noise propagation. nuisances and protect facilities? A green belt area will be developed surrounding the boundary wall of the water treatment plant. Trees with thick canopy will be planted in order to reduce the noise levels reaching the nearby surroundings. • Impairments associated with √ Temporary impairments are anticipated along the new transmission lines and access roads? transmission line routes during construction stage. • Health hazards arising from √ Measures for safe handling, storage and usage of inadequate design of facilities for chlorine are included. receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to √ Operation and Maintenance recommended by the workers from the management of manufacturers, and the existing norms and guidelines chlorine used for disinfection and other for ensuring the safety of workers will be followed. contaminants? Measures for safe handling, storage and usage of chlorine are included. • Dislocation or involuntary √ There is no resettlement of people for project resettlement of people implementation. • Social conflicts between √ The contractor will be utilizing the local labour force construction workers from other areas as far as possible; in case if it is unavoidable, labour and community workers? camps and facilities will be provided appropriately. No conflicts envisaged • Noise and dust from construction √ All the construction machineries employed will comply activities? with noise emission standards of Central Pollution Control Board (CPCB). Dust suppression measures such as water sprinkling will be employed

P a g e | 123

SCREENING QUESTIONS Yes No REMARKS • Increased road traffic due to √ Excavation and laying pipelines along public roads interference of construction activities? will interfere with the traffic. Construction material transport will increase traffic on the local roads. Proper traffic management and construction planning will be ensured to minimize the interference • Continuing soil erosion/silt runoff √ Construction work during monsoon shall be carried from construction operations? out with due care so that silt run off due to construction operation is prevented. No construction will be allowed during rains. • Delivery of unsafe water due to √ The Contractor shall prepare an O&M manual for poor O&M treatment processes approval of the Employer and training will be given to (especially mud accumulations in filters) the staff operating the plant to ensure proper O&M. and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution √ Not envisaged. system, which is corrosive due to Online monitoring of process water is proposed as inadequate attention to feeding of part of the subproject and ensured by the Contractor. corrective chemicals? Care should be taken during O&M period to ensure that corrosive chemicals are not entered in distribution networks. • Accidental leakage of chlorine √ There is risk that inappropriate handling, storage or gas? use of chorine may cause serious accidents due to leakage causing severe health risks. Measures for safe handling, storage and usage of chlorine are included • Excessive abstraction of water √ The Mukutmanipur reservoir stores enough water affecting downstream water users? throughout the year the year, and the water abstraction for the project is negligible even during lean seasons and hence extraction will not affect any downstream users. • Competing uses of water? √ Project involves new source development. Adequate capacity of raw water is already available. • Increased sewage flow due to √ Sanitation and sewerage need to be improved increased water supply • Increased volume of sullage √ Sanitation and sewerage need to be improved. (wastewater from cooking and washing) Additional wastewater and appropriate sludge and sludge from wastewater treatment treatment and disposal facility will be part of this plant subproject.

Climate Change and Disaster Risk Yes No Remarks Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks. Is the Project area subject to hazards √ As per local enquiries carried out during field visits and such as earthquakes, floods, landslides, from the vulnerability mapping of the district for flood tropical cyclone winds, storm surges, prone areas indicate that the subproject components are tsunami or volcanic eruptions and climate not located in the flood prone/tropical cyclone areas. changes? Entire Bankura district and the project are a fall in Zone III, which is classified as Moderate Damage Risk Zone in India. Could changes in temperature, √ Unlikely, as reservoir contains significant quantities of precipitation, or extreme events water; although there will be change in flow due to patterns over the Project lifespan these events, but may be insignificant. Water quality affect technical or financial sustainability surveillance program will be included to monitor the (e.g., changes in rainfall patterns disrupt raw water quality.

P a g e | 124

Climate Change and Disaster Risk Yes No Remarks Questions reliability of water supply; sea level rise creates salinity intrusion into proposed water supply source)? Are there any demographic or socio- √ No economic aspects of the Project area that are already vulnerable (e.g., high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)? Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

P a g e | 125

Appendix 2: National Ambient Air Quality Standards Concentration in Ambient Air Time Industrial, Pollutants Weighted Ecologically Method of Measurement Residential, Rural Average Sensitive Areas and Other Areas 1 Sulphur Dioxide Annual 50 20 Improved West and (SO2) microgram per 24 hours 80 80 Geake-Ultraviolet cubic meter (µg/m3) fluorescence 2 Nitrogen Dioxide Annual 40 30 Modified Jacob and (NO2) µg/m3 24 hours 80 80 Hochheiser (Na-Arsenite) Chemiluminescence 3 Particulate Matter Annual 60 60 Gravimetric (Size less than 10 24 hours 100 100 -TOEM µm) or PM10 µg/m3 -Beta attenuation 4 Particulate Matter Annual 40 40 Gravimetric (Size less than 2.5 24 hours 60 60 -TOEM µm) or PM2.5 µg/m3 -Beta attenuation 5 Carbon Monoxide 8 hours 02 02 Non-dispersive Infra-Red (CO) mg/m3 1 hours 04 04 (NDIR) Spectroscopy

P a g e | 126

Emission limits for New DG sets up to 800 KW (As per Environment (Protection) (Third Amendment) Rules, 2013)

P a g e | 127

Appendix 3: Vehicle Exhaust Emission Norms 1. Passenger Cars

Norms CO(g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles

Norms CO( g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10 Bharat Stage-IV 1.5 0.96 3.5 0.02

CO = Carbon Monixide, g/kmhr = grams per kilometer-hour, HC = Hydrocarbons, NOx = oxides of nitrogen, PM = particulates matter. Source: Central Pollution Control Board

P a g e | 128

Appendix 4: National Ambient Air Quality Standards in Respect of Noise Limit Area code Category of Area/Zone (dBA) Day time Night time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

P a g e | 129

Appendix 5: Extract from Construction and Demolition Management Rules, 2016

P a g e | 130

P a g e | 131

P a g e | 132

P a g e | 133

P a g e | 134

P a g e | 135

Appendix 6: Department of Environment’s Direction Under Air Act, 1981 For Control of Air Pollution from Construction Activities In West Bengal

P a g e | 136

P a g e | 137

Appendix 7: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works

1. Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

2. Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days’ wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

3. Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

4. Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

5. Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labour and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labour.

6. Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment. 7. Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

8. Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making disc

9. Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing ₹3,500/- per month or less. The bonus to be paid to employees getting ₹2,500/- per month or above up to ₹3,500/- per month shall be worked out by taking wages as ₹2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to

10 for the purpose of applicability of the Act.

10. Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

P a g e | 138

11. Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

12. Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

13. Child Labour (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

14. Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc.

15. The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

P a g e | 139

Appendix 8: Drinking Water Standards

Permissible Requirement limit in the Substance or Undesirable effect outside No. Desirable absence of Remarks characteristic the desirable limit alternate Source Essential Characteristic 1. Colour Hazen 5 Above 5, consumer 25 Extended to 25 only if Units, Max acceptance decreases toxic Substance are not suspect in absence of alternate sources 2. Odour Unobjecti - - a) test cold and when onable heated b) test are several dilutions 3. Taste Agreeable - - Test to be conducted only after safely has been established 4. Turbidity 5 Above 5, consumer 10 - (NTU) Max acceptance decreases 5. pH value 6.5 to 8.5 Beyond this range the No - water will after the relaxatio mucous membrane n and/or water supply system 6. Total 300 Encrustation in water 600 - Hardness supply structure and (mg/L) CaCO3 adverse effects on domestic use 7. Iron (mg/L, 0.3 Beyond this limit 1.0 - Fe) Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria 8. Chlorides 250 250 Beyond effects outside 1000 - (mg/L, Cl) the desirable limit Max 9. Residual free 0.2 - - To be applicable only Chlorine when water is (mg/L), Max chlorinated. Tested at customer end. When protection against viral infection is required, it should be min. 0.5 mg/L. Desirable Characteristics 10. Dissolved 500 Beyond this, palatability 2000 - solids mg/L. decreases and may Max cause gastrointestinal irritation. 11. Calcium 75 Encrustation in water 200 - (mg/L, Ca) supply structure and Max. adverse effects on

P a g e | 140

domestic use. 12. Magnesium 30 Encrustation in water 100 - (mg/L, Mg) supply structure and Max adverse effects on domestic use. 13. Copper (mg/L, 0.05 Astringent taste 1.5 - Cu) Max discolora- tion and corrosion of pipes fittings and utensils will be caused beyond this. 14. Manganese 0.1 Beyond this limit 0.3 - (mg/L, Mn) taste/appearance are Max affected, has adverse effect on domestic use and water supply structure 15. Sulphate 200 Beyond this causes 400 May be extended up to (mg/L, SO4) gastro intestinal irritation 400 provided Max. when magnesium or magnesium (as Mg) sodium are present does not exceed 30 16. Nitrate (mg/L, 45 Beyond this 100 - NO3) Max. methaemoglobinemia takes place. 17. Fluoride 1.0 Fluoride may be kept as 1.5 - (mg/L, F) Max. low as possible. High fluoride may cause fluorosis. 18. Phenolic 0.001 Beyond this, it may 0.002 - Compounds cause objectionable (mg/L taste and odour C6H5OH) Max. 19. Mercury (mg/L 0.001 Beyond this the water No To be tested when Hg) Max becomes toxic Relaxati pollution is suspected on. 20 Cadmium 0.01 Beyond this the water No To be tested when (mg/L, Cd) becomes toxic Relaxati pollution is suspected Max on. 21. Selenium 0.01 Beyond this the water No To be tested when (mg/L, Se) becomes toxic. Relaxati pollution is suspected Max on. 22. Arsenic 0.01 Beyond this the water No To be tested when (mg/L, As) becomes toxic Relaxati pollution is suspected Max. on 23. Cyanide 0.05 Beyond this the water No To be tested when becomes toxic Relaxati pollution is suspected on 24. Lead (mg/L 0.05 Beyond this the water No To be tested when Pb) Max. becomes toxic Relaxati pollution is suspected on 25. Zinc (mg/L, 5 Beyond this limit it can 15 To be tested when Zn) Max. cause astringent taste pollution is suspected and an opalescence in water

P a g e | 141

26. Anionic 0.2 Beyond this limit it can 1.0 To be tested when detergents cause a light froth in pollution is suspected (mg/L, MBAS) water Max 27. Chromium 0.05 May be carcinogenic - - (mg/L, Cr6+ above this limit 28. Polynuclear - May be carcinogenic - - Aromatic Hydrocarbons (mg/L, PAH) Max 29. Mineral oil 0.01 Beyond this limit, 0.03 To be tested when (mg/L) undesirable taste and pollution is suspected odour after chlorination takes place 30. Pesticides Absent Toxic 0.001 - (mg/L) max Radioactive materials 31. Alpha emitters - - 0.1 - Bq/L Max 32. Beta emitters - - 1.0 - Pci/L Max 33. Alkalinity 200 Beyond this limit, taste 600 - (mg/L,) Max becomes unpleasant 34. Aluminum 0.03 Cumulative effect is 0.2 (mg/L, Al) Max reported to cause dementia 35. Boron (mg/L) 1.0 - 5.0 - Max

P a g e | 142

Appendix 9: Guidelines for Safety during Monsoon/Heavy Rainfall

Excavation and refilling of earth are common activities, which, if not carefully executed may pose problems to the safety of works as well as passers-by and road users during the impending Monsoon.

Normal and heavy rainfall event affect our ongoing works, It should be our conscientious effort to ensure that such events do not prove to be problematic to people and structures in town. During monsoon PIU/DSISC should ensure that any further excavation work is taken up only after ensuring that the earlier work is in safe stage. It is desired that Construction Manager & Ex En PIU should inspect all sites during rains and take proactive actions.

Some of the precautions and mitigation measures to be taken are discussed below- 1. The execution of works having deep excavation in smaller lanes and congested areas should be completed well before monsoon. The works of deep excavation during monsoon should not be preferably taken up or extensive care should be taken for execution of such works. 2. The settlement in refilled trenches of sewerage and water supply lines may occur during monsoon. DSISC and PIU team should inspect all sites after a storm to identify such reaches and take immediate corrective action by proper refilling and compacting. It is responsibility of all engineers to look after this activity during monsoon and ensure corrective actions from Contractor’s side. 3. The contractor’s crew should be equipped with vehicle, gum boots, raincoats, torch etc. to tackle such situation during and after rains. Adequate quantities of earth, debris and gravel should be stacked at strategic places so that no time is lost in procuring such material. 4. In trenches where pipe laying has been done and duly tested and approved, refilling should be done and all surplus material relocated to safe disposal sites such that it does not obstruct traffic or waterways. 5. All open ends of WS pipelines should be firmly plugged to prevent debris from entering the pipeline. 6. Drains are primary or secondary carriers of storm water. Any unutilized construction material should be relocated to allow free passage of storm water. Surplus earth should be suitably and immediately be relocated to avoid earth from falling into the drain so that choking does not occur. 7. Overhead works should not be carried on in-weather conditions that threaten the safety of workers. More frequent checks on scaffold and bracings should be done during monsoon season. 8. Additional precautions should be taken of the power lines, ignorance and carelessness can cause major accidents and casualty. 9. Take preventive measures for water logging in working areas by providing dewatering pumps. Place bright and reflective warning signs. 10. Inspection should also be carried out before resumption of work after a shower/rain. 11. Storage of Construction Material: Steel & Cement are vital ingredients for quality construction work but in absence of proper storage, especially during monsoon, cement and steel may rapidly decline in quality and strength. Care should be taken to protect these materials and use of any exposed material should be allowed only after conducting fresh tests. Improper storage of such material should be reported to SE PIU/CM of DSISC and use of any apparently affected material should be done after permission of SE PIU//CM.

P a g e | 143

Additional Precautions

1. Adequate set up and resources such as dewatering pumps, electrical routings etc should be planned ahead. Water logging on main roads to be avoided, where construction works are going on.

2. Ensuring the monsoon specific PPE’s issued in adequate and are used during monsoon.

3. Use of electric extension box should be avoided; extension cables (if used) should not be wet and damaged. Cables connections should be only weatherproof/waterproof. Electrical and HSE personnel of contractor should visit permanent and running sites regularly. Transparent protective sheets/rain sheds should be placed for the power distribution boards.

4. Welding machines, bar cutting machines etc. should be kept in dry conditions; should not stand in water logged area. Brakers and Drill machines should not be used when raining; dirt/mud should be scrubbed with cloth.

5. Special Trainings to all drivers and operators on safe practices and all vehicles/ equipment’s maintenance checks to be more frequent.

6. High boom equipment to be stopped during blowing of high-speed wind and rain storm. Arresting of parked vehicles, equipment during monsoon should be done.

7. All chemicals should be stored as per MSDS, chemicals to be protected from water ingress. Chemical waste should be disposed for preventing overflow of chemicals.

8. At labor camps following precautions should be taken:- • Maintaining hygiene & proper housekeeping. • Additional health check-up camp to identify seasonal diseases • Preventive measures on mosquito/parasite breeding mainly in work locations and camps • Frequent cleaning of toilets • To avoid water borne diseases, high level of cleanliness to be maintained, drinking water containers need to be cleaned and kept covered. Walk areas and pathways to be covered with Murom and soft rock particles (to avoid soft soil conditions). • Obstacle free approach to rest sheds, camp and toilets. • Proper illumination, provision of battery-operated emergency lights • No bonfires inside resting sheds. No use of wood.

SE–PIU and CM-DSISC should oversee the arrangements to effectively deal with the eventuality.

EHS officer of contractor should visit each site and camps more frequently. Contractor/EHS officer will also impart training on safe working methods during Monsoon and will keep a daily watch on weather conditions to share with site team to act accordingly.

Contractor should organize Monsoon Health Camps and Monitor Workmen Habitat and Hygiene.

P a g e | 144

Appendix 10: Photo Illustration of Recent Activity at Site

Project Information Board Construction Materials

Soil investigation at Intake site Soil investigation at WTP site

Site office & Labour camp area Before & After Construction

P a g e | 145

Appendix 11: Summary of Public Consultation A. Done Earlier Report period

Date Place No. of Participants Key Issues Discussed Photographs 28.08.17 Male :23 Public Health & Engineering Dept. Of West Bengal Govt. with the Gram Panchayat Female 29 Financial support of Asian Development Bank Is going to Office Total : 52 undertake a Water Supply Project in selected Districts of West Bengal. The project has been named as West Bengal Drinking Key Water Sector Improvement Project (WBDWSIP). Participants: Treated Surface Water will be supplied to every households of 1.Officials Asian the project area through separate pipe connection. The Project Development Bank aims to provide 70 litres per capita per day of potable water headed by Ms. through metered household connections on a 24/7 basis to each Neeta Pokhrel household. PHED district offices will be responsible for operating, 2. Superintend maintaining and monitoring the bulk water systems, whereas the Engineer, Gram Panchayat (GP) will operate and maintain the distribution Executive network. The Zilla Parishad (ZP), administrative body at the Engineer, Asst. district level, and Panchayat Samiti (PS), administrative body at Engineer & Sub the block level, will be involved in coordinating, technical support

Asst. Engineers of and monitoring role at the district and block level, respectively.

PHED Bankura Affordability of water tax has been a pertinent question raised Division both by the Gram Panchayat members and the community - however almost all agreed to pay the water charges if they get 3. Pradhan and the facility of household water connections. They agreed that it other Gram will help in reducing time taken for water collection as well health Panchayat expenditures. Members of The Gram Panchayat members expressed concern regarding the Bheduasole Gram adequacy/sufficiency of OHRs per Gram Panchayat; it was Panchayat headed clarified by PHED personnel present during the consultation that by the Panchayat as per the command zone/area it covers most of the part and the Pradhan rest will be covered by nearby OHRs of another Zone. On-time completion of the project was another concern of the Panchayat Members and it was told that the project work will not take longer than 3 years.

Creating job opportunities was the other question of the Gram Panchayat Members – it was mentioned that the existing PHE workers will be given first preference, further if there is requirement, then workers from the local community can be employed during the construction phase.

P a g e | 146

No. of Date Place Proposed Work Concerns / Issues Discussed Photographs

Participants 28.08.17 Mouza: Laying of 22 km Male: 10 Benefits and Importance of Treated Surface Hatirampur Transmission Female: 2 Water were discussed. Line from Water Total : 12 Door step water connection will be a great Treatment Plant relief for the village women as it will reduce their to Intermediate Time Poverty. Pumping Station The participants were said that if they face any at Gobindapur problem related to supply of water, they can inform the Gram Panchayat Office. In the question of affordability, the respondents said that, If all the people get better service then everyone will gladly pay the water tariff. Local tube wells are checked periodically through Panchayats and health dept. officials. But due to High Concentration of Iron it tastes poor. During Construction Phase access to road side shops will be assured through adequate measures. Steps will be taken to control traffic congestion

during pipe laying work in market areas

P a g e | 147

No. of Date Place Proposed Work Concerns / Issues Discussed Photographs

Participants 28.08.17 Village: Supur Laying of 22 km Male: 15 Local people were found aware about the Transmission Female: 3 upcoming water supply project in their area. Line from Water Total : 18 Role of ADB and PHED were discussed with Treatment Plant them. to Intermediate It was suggested by the participants that, door Pumping Station step Water Connection to be provided to each at Gobindapur household without any prejudice and local influence and no partiality or preferences should be allowed in this context. How the Arsenic / Fluoride contaminates the Ground Water was discussed with them. It was mentioned that, why treated surface water is safer than ground water in all respects. The participants were informed that, during construction phase any grievances will be mitigated on priority basis. It was said by the participants that, local people will extend their full support for successful implementation of the project.

P a g e | 148

P a g e | 149

P a g e | 150

Date Place Participants Key Issues Discussed Photographs 29 Proposed site of Land Sellers (7) Consultation with the land sellers revealed that, August GLSR ADB Officials (2) they are aware about the side effects of 2017 Gram PHED Engineers consuming untreated ground water. Local tube Panchayat: of Bankura Division wells are checked periodically through Bheduasole (2) Panchayats and health dept. officials. Yet, the Block: Indpur quality of the water is not satisfactory due to Mouza: Consultant (1) various reasons like high concentration of iron, Gobindapur salinity and poor taste. Upon consultation, all the land sellers said that, they are willing to sell their parcel of land at Govt. Price. They have not been forced rather they are happy for having the opportunity to be a part of the project. The proposed land is laid vacant for several

years, they do not have any income from the land. Cultivation was done this year after several years due to better monsoon. It is a rain-fed plot. All the land sellers have their own livelihood and a permanent place to live so they will not suffer if they are being compensated at actual Govt. Price of the land. It was further added that, the amount they will receive from the Govt. will enable them to secure their future They assure their full co-operation in land purchase process.

P a g e | 151

B. Consultation during Updation of IEE Summary of Current Public Consultations -11.10.2019 (Package- 01) OHR/GLSR Number of BLOCK MOUZA GP ZONE Concerned/ Issues discussed Photographs Participants

CODE Indpur Gobindapur Bheduasole Venue- Community Given brief description of the Block Mouza Gram Gobindapur people (35) project to the consumers. They Panchayat Village Male- 21 were very happy to listen about the (GLSR Site) Female-14 project and wanted to raise their Date- supporting hand. 11thOctober, Local people were found aware 2019 about the upcoming water supply project in their area. Collected information of total number of tube wells including working and non-working condition present in this GP. Most of the tube wells are in very bad condition. Role of ADB and PHED were discussed with them. Water borne diseases, fluoride contamination of ground water and benefits of treated surface water were discussed. Women of the villages said that door to door water connection will save their time. Availability of local labour during construction time was discussed. Sufficient amount of labours available in the villages. Discussed to villagers about willingness to pay for safe water. Most of them are very poor people and they will have facing problem for paying. Villagers also said that due to scarcity of water sanitation is not maintained properly. Collect information about drainage and sewerage problems of the villages. Collect information about the forest area. They said forest area situated

P a g e | 152

OHR/GLSR Number of BLOCK MOUZA GP ZONE Concerned/ Issues discussed Photographs Participants CODE 1.5 away from the project area. There is no man-animal conflict. Discussed about dust pollution, noise pollution, disturbance, road diversion (Traffic control) during construction time.

P a g e | 153

Appendix 12: Photograph of Public Consultation

P a g e | 154

P a g e | 155

P a g e | 156

P a g e | 157

PHOTOGRAPHS OF STAKEHOLDER CONSULTATIONS

P a g e | 158

Appendix 13: Sample Site Inspection Format Filled Up

P a g e | 159

P a g e | 160

Appendix 14: GRC Notification and Committee State & District Level Steering committee

P a g e | 161

P a g e | 162

P a g e | 163

P a g e | 164

P a g e | 165

P a g e | 166

PMU Level

P a g e | 167

P a g e | 168

PIU Level GRC - Bankura

P a g e | 169

P a g e | 170

GP Level GRC Notification

P a g e | 171

Appendix 15: Sample Grievance Registration Form

The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback.

Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Toxwn Project:

Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below: If included as attachment/note/letter, please tick here: How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed: Yes No Means of disclosure:

P a g e | 172

P a g e | 173

Appendix 16- Permission letter of water abstraction from IWD

P a g e | 174

Correspondence for 12 MLD additional water

P a g e | 175

Appendix 17: Intake substation and WTP land details Land possession certificate for Intake and Sub-station under BK/01

P a g e | 176

P a g e | 177

P a g e | 178

Inter-Departmental Land Transfer of WTP land under package- BK/01

P a g e | 179

P a g e | 180

P a g e | 181

P a g e | 182

P a g e | 183

P a g e | 184

Appendix 18: CTE from WBPCB

P a g e | 185

P a g e | 186

P a g e | 187

Appendix 19: Approved SEMP

P a g e | 188

DESIGN, CONSTRUCTION AND OPERATION-MAINTENANCE OF RAW WATER INTAKE WELL, WATER TREATMENT PLANT, RESERVOIR, TRANSMISSION MAIN FOR INDPUR AND TALDANGRA BLOCK IN BANKURA

Package No. WBDWSIP/DWW/NCB/BKP/01/2018-19

SITE-SPECIFIC ENVIRONMENT MANAGEMENT PLAN

1. INTRODUCTION Background Project Summary Project Description Scope of Work and Services Project Objective Project Location 2. DETAIL OF COMPONENTS Raw Water Intake Point Raw Water Transmission Mains Water Treatment Plant Clear Water Transmission Main 3. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

4. CONSTRUCTION PHASE ENVIRONMENT MONITORING PLAN

P a g e | 189

LIST OF ATTACHMENTS

Attachment 1- Details of Manpower Attachment 2- Details of construction Work sites Attachment 3- Details of construction camp site Attachment 4- List of Clearances & Statutory Requirements Attachment 5- Contractor’s EHS Policy & Organization Attachment 6- Utility shifting/relocation Attachment 7- Details of Construction Materials Attachment 8- Details of construction waste / debris / surplus soil Attachment 9- Spoil Management Plan (SMP) Attachment 10- Traffic Management Plan (TMP) Attachment 11- Consultation and Information Disclosure Attachment 12- Grievance Redress Mechanism (GRM)

LIST OF APPENDICES

Appendix 01- Tie up letter with local Hospital Appendix 02- Permission letter of water abstraction from DVRR Appendix 03- Intake substation and WTP land details Appendix 04 -Land Demarcation of WTP Area Appendix 05- Road cutting permission Appendix 06- Layout Map of WTP area Appendix 07- Various work permit system Appendix 08- WC policy Appendix 09- Labour License Appendix 10- All Risk Policy Appendix 11-CTE of WTP Appendix 12- Tool box talk

P a g e | 190

LIST OF ABBREVIATIONS

ADB Asian Development Bank

BS Boosting Station

DQWAP Drinking Water Quality Action Plan

EHS Environment, Health and Safety

EIA Environmental Impact Assessment

EMP Environmental Management Plan

MGD Million Gallon per Day

MLD Million Liter per Day

OHS Occupational Health and Safety

OHT Over Head Tank

PHED Public Health Engineering Department

PIU Project Implementation Unit

PMC Project Management Consultant

PMU Project Management Unit

WHO World Health Organization

WTP Water Treatment Plant

WBDWSIP West Bengal Drinking Water Sector Improvement Project

P a g e | 191

INTRODUCTION

The project of West Bengal Drinking Water Improvement Project (WBDWIP) aims to provide safe, reliable and continuous drinking water as per Government of India’s standard to about 2.6 million people in the Arsenic, Salinity and Fluoride affected selected areas of North 24 Parganas, South 24 Parganas, East Medinipur and Bankura districts of West Bengal.

Projects proposed under the Project stem from a district-wide comprehensive water quality and sustainability planning and completion of the Drinking Water Quality Action Plan (DQWAP) for the concerned district.

The impact of the Project will be drinking water security ensured in selected districts of West Bengal (Vision2020, PHED and National Sub-mission for Fluoride Removal). The outcome will be inclusive, gender-responsive, and sustainable drinking water service delivered in Project districts.

The Project will ensure drinking water security through 24/7 piped water supply schemes in the areas covered and strengthen institutional structures and build capacities of stakeholders at all levels of service delivery for sustainable operation and maintenance and public health improvement.

Technofab Engineering- SN Envirotech JV has been awarded for the work of Design, Construction and Operation-Maintenance of Raw Water Intake Well, Water Treatment Plant, Reservoir, Transmission Main for Indpur and Taldangra block in Bankura.

The entire project has 5-year time frame including 3 Years for Design and Build & 2 years for Operation and maintenance with following components. • Intake Well cum pump house and Approach Bridge in Mukutmanipur Reservoir. • Raw water transmission main from Intake well (Mukutmanipur reservoir) to Water Treatment Plant (Lohadihi) • Water Treatment Plant of 44 MLD capacity (Lohadihi) • Clear water transmission main from Water treatment plant (Lohadihi) to Ground level service reservoir (Indpur). • Ground Level Service Reservoir of 2500KL Capacity (Indpur)

ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. Based on results of the assessment and ADB’s SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have any significant adverse environmental impacts. However, an initial environmental examination is required/advisable.

P a g e | 192

PROJECT SUMMARY

Package No. WBDWSIP/DWW/NCB/BKP/01/2018-19 under PIU Bankura

Package title Design, Construction and Operation-Maintenance of Raw Water Intake Well, Water Treatment Plant, Raw and Clear Water Transmission Main for Indpur and Taldangra Block Contractor Technofab Engineering- SN Envirotech JV

Issue of Notice to Proceed 24.01.2019

Date of particular works Component A- Intake Well/Sub Station/Approach Bridge/Raw water commencement Transmission Main -31.07.2020 Component B- WTP- 20.06.2020 Component C- Clear Water Transmission Main- 15.07.2020 Contract period Construction: 3 Years; O&M: 2 Years

SEMP Component WTP- 44 MLD Intake Well- 44 MLD Raw water transmission main- 2.9 K.M Clear water transmission main- 22 K.M Demolition Work No demolition activity involved

Project Area Indpur and Taldangra Block

Gram Panchayats WTP- Lohadihi Mouza, Gorabari (GP), Block. Intake Well- Satsole Mouza, Gorabari (GP), Khatra Block. Household Connection NA

Non-Household Connection NA

Indicative Budget for EMP Implementation for the INR 31,04,000/- entire package Amount Project Components As per project detailed design

P a g e | 193

PROJECT DESCRIPTION

The raw water for the proposed water supply project for Indpur and Taldangra blocks will be abstracted from surface water of resource of Mukutmanipur reservoir (also known as Kangsabati reservoir). It is located at approximately 3.2 km upstream of the confluence of River Kangsabati and River Kumari. In1956, a giant water dam/reservoir was constructed at Mukutmanipur, about 12km from Khatra within the district of Bankura, West Bengal.

The Irrigation and Waterways Department (IWD) has already given a permission of drawl of 44 MLD raw water for drinking water purpose under the Bankura water supply project.

The overall improvement plan is to tap the raw water from Mukutmanipur reservoir and treat the water at Water Treatment Plant close to the intake point. The proposed WTP land belongs to Irrigation and Water ways Department Government of West Bengal (IWD). The treated water will be pumped to GLSR located at Gobindopur mouza of Indpur block. The assessment of the alignment indicated that the length of the primary transmission main from WTP to GLSR is around 22km.

SCOPE OF WORK AND SERVICES

The contract scope for the present subject contract WBDWSIP/DWW/NCB/BKP/01/2018-19 comprises of the following components:

Component A: Design, build, supply, install and commission raw water intake well cum pumping station and approach bridge in Mukutmanipur reservoir and raw water transmission main from Intake well to WTP located near Gorabari GP (Satsole) in Khatra block, with all ancillary Civil, Mechanical, Electrical and Instrumentation works and SCADA all complete.

Component B: Design, build, supply, install and commission of Water Treatment Plant including clear water reservoir and pumping station, sub-station with all ancillary Civil, Mechanical, Electrical and Instrumentation works and SCADA all complete.

Component C: Design, supply, laying and commissioning of clear water transmission main including design and commissioning of the intermediate Ground level Storage reservoir and allied works near Gobindapur village in Indpur block with all ancillary Civil, Mechanical, Electrical and Instrumentation Works and SCADA all complete.

Component D: Operation and Maintenance of the Design-Built Works for a period of 2 years after successful commissioning as per the scope under this contract.

PROJECT OBJECTIVES

Presently, the demand of the rural areas within the fold of the selected 2 blocks of Indpur and Taldangra (henceforth referred as project area) is met from ground water and sub-surface sources. With increase in population and increase in ground water withdrawal (for agricultural and drinking water purposes), the ground water resources are getting depleted. Also, in select areas, the ground water is affected by fluoride contamination.

Primarily the prioritization and appraisal of the WS Scheme is based on the Preliminary Project Report prepared by the PHED, as a part of its endeavour to provide Piped Water Supply to the rural areas as per the plan outlined in “VISION-2020”. The selected 2 blocks have been

P a g e | 194

prioritized by PHED for comprehensive coverage with surface based WS Scheme and is proposed for implementation under the WBDWSIP funded by ADB. The objective of the subproject is to provide sustainable water supply at a rate 70 liters per capita per day (lpcd) to each household in all habitations in the Indpur and Taldangra blocks.

PROJECT LOCATION

The sub-project components are located in Indpur and Taldangra Community Development (CD) blocks Bankura district. Intake site located at Satsole Mouza of Khatra Block. WTP site is located at Lohadihi Mouza of Khatra Block.Clear water Transmission is located at Khatra, and Indpur Block & Ground level Service Reservoir is located Indpur Block, Bheduasole (GP). The project area Bounded by Taldangra and CD Block on the South, Raipur and CD block on the South, Ranibandh and Hirbandh CD block on the West. The area is having a gradual descent from the Chota Nagpur Plateau.

P a g e | 195

DETAIL OF COMPONENTS Sl. Infrastructure Function Description Location No. 1 Raw water intake Abstract water from the Intake well cum pump house and Latitude:220 57 ‘54“ N Longitude:86° 45’ 50”E Average with approach Mukutmanipur reservoir approach bridge. Mukutmanipur reservoir GL=134m Raw water source for the project is bridge and pump it to WTP has abundant water throughout the year. Mukutmanipur reservoir. The proposed intake site is Quality of river water is in general of located at Satsole Mouza of Khatra block. There are no acceptable quality, which can be used notable pollution sources near the intake. There are no for potable purposes after conventional waste water disposal points in the upstream vicinity of the treatment and disinfection. The Irrigation intake. and Waterways Department (IWD) has already given a permission of drawl of 44 MLD raw water. 2 Raw water main Raw water main will be The raw water main is proposed to follow Pipe supporting bridge Will be constructed wherever from Intake laid to supply raw water the shortest possible route, keeping in required as per site conditions for installation of raw water from intake to WTP with view the velocity considerations to avoid main to transmit raw water from intake to WTP. the help of raw water silting and other physical considerations. pumping machineries. Based on an assessed velocity (of minimum 1.2m/s and maximum 1.8m/s), the indicative pipe diameters ranging from700 mm to 800 mm.

3 Water Treatment Treatment of Raw 44 MLD capacity conventional WTP with The identified land for WTP is 2.9 km from the proposed Plant Water to meet the the following process: Alum coagulation intake point and belongs to IWD. The coordinate soft he drinking water standards. and flocculation Rapid gravity filtration, proposed WTP location is 220 58’ 0” N and 86047’ 6 ”E. Conventional water Disinfection with chlorination Wash water treatment is proposed to recovery Sludge lagoon Water quality The Topography is undulating and ground level of the site treat the raw water from testing laboratory miscellaneous and surroundings are about 140 m above the mean sea the Mukutmanipur infrastructure (Administrative Building, level. The land is connected by an approach road to the reservoir. Laboratory Building, Staff Quarters, Guard nearby villages. As per local enquiries carried out during Rooms, Internal roads and pathways, field visits, the site is not prone to flooding, and is barren Electrical Sub-station). Provision of land. The proposed WTP site is required to be developed SCADA (The operation of the entire i nc luding Proper drainage infrastructure considering the Water Treatment plant shall be fully undulating topography automated with PLC and SCADA system installed in place with provision of manual over riding) 4 Primary Primary Transmission The treated water from the WTP will be The Primary transmission main will be laid along the Transmission Main main of approximately 22 conveyed to GLSR. Since, the location of edge of the roads. The rising main is proposed to be km to transmit treated the Intake and WTP is on one side of the laid primarily through open cut method. However, the water from the WTP to Project area, a single transmission main laying of the rising main through open cut method may GLSR will be laid with progressively reduced not feasible at major road crossings and congested diameters is proposed to feed the market areas. About 50 m of the Primary transmission proposed GLSR. main out of total 22 km length is proposed to be laid by

P a g e | 196

Sl. Infrastructure Function Description Location No. trenchless methods in these stretches. 5 Ground Level Store treated water from GLSR - Reservoir storage capacity is GLSR Area= 5995.061 Sq. m. Average GL 109.40 M storage reservoir WTP for supply to OHRs 2500 KL above msl. through the pumping The identified site of GLSR- GLSR is at Gobindapur main. mouza of Indpur block and located on easily accessible by SH 2. The land of GLSR- is privately owned land and will be purchased from private owner(s). Overall, there are no notable sensitive environmental features in and around the site. The identified site of GLSR at Gobindopur mouza of Indpur block and located on easily accessible by SH 2. The land of GLSR is privately owned land and will be acquired from private owner(s). Overall, there are no notable sensitive environmental features in and around the site.

P a g e | 197

The following Google Earth image (Figure 1) showing location of intake point, network of raw water transmission main, location of WTP and network of clear water transmission main.

P a g e | 198

Table 1: Details of Raw Water Transmission Main Name of the Name of the Total Width Dia of Length of Trench Ownership road gram length of of the pipe to the pipe width for (NOC required panchayat the road be laid laying (m) laying of from) pipeline (m) BT (mm) pipeline (km) (mm) KunarBohal (Village) to ------2.9 3 900 2900 1500 PMGSY Lohadihi (Gorabari)

Table 2: Land Details of Water Treatment Plant Name of Name of G P Ownership Present Land Status of NOC Total Area Mouza (Pvt./Govt.) use of the Plot (for pvt. land) of the Plot NOC / Handover letter for Govt. Land Component

WTP Lohadihi Gorabari IWD NA Possession letter 8-Acres has been received.

Source: PHED, Bankura

Table 3: Details of Clear Water Transmission Mains Name of the road Gram Width of Dia of pipe to Length of Trench Ownership Panchayat road(m) be laid (mm) the pipe width for (whether NOC BT laying (m) laying of required for pipeline laying of (mm) pipeline)

Near GLSR to 500 GobindpurSalibati Bheduasole 7.5 700 1300 PWD River Bridge Salibati River Bridge 3100 Baharamuri 7.5 700 1300 PWD to Pathardihi Pathardihi to 2800 Hirbandh 3.75 700 1300 PWD Rangamati Rangamati to Supur Supur 3.5 700 3400 1300 PWD Supur to Tilaboni Hirbandh 5.5 700 7500 1300 PWD Talaboni to 3700 Hirbandh 3.5 700 1300 PWD Sibarampur Sibarampur to WTP Gorabari 3.5 700 1000 1300 PMGSY

P a g e | 199

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) Utilities/ Telephone lines, • Locations and Operators of • The Pipe Contractor, PIU DSISC Project Infrastructure Electric poles and these utilities in the details design Laying work is observation cost and Services. wires, water lines documents to prevent unnecessary continuing without at site and within proposed disruption of services during this disturbing the existing document project area With activity. oil or water pipelines checking Pipe Lying. • Contingency plan has been and Electric Poles and developed by informing to Overhead HT Line. emergency services like WBSEDCL, • Spoil Telecommunication, local management plan for administration and police etc. WTP area and pipe • Water lines have been laying area have been found till date. First, we are digging prepared and attached the trial pit manually; if any in Attachment 9. obstruction arises the same is • Traffic removing as per direction of end Management plant user. prepared and will apply • Require contractors to as per requirement prepare spoils (waste) management (Attachment 10) plan and traffic management plan. Climate The nature and • Seasonal Climate variations • If Excavation Contractor, PIU DSISC Project intensity of rainfall will be taken into account during work is to be conducted observation cost events in an area, scheduling of construction in the during rainy season at site and has implications for area. then preventive document surface water • Excavation works during measure will be taken checking management. dry season and surface water have like dewatering from the been controlled as per method trench, during laying use approved by PMU. of Gumboot is a must. To avoid Slip, Trip and Fall, no within the barricading area. Sources of Extraction of • Obtain construction • All construction Contractor, PIU DSISC Project Materials materials can disrupt materials only from government materials will be observation cost natural land contours approved quarries with prior procured from at site and and vegetation approval of PIU government approved document resulting in • PIU to review, and ensure quarry sites. checking accelerated erosion, that proposed quarry sources have

P a g e | 200

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) disturbance in natural all necessary clearances/ drainage patterns, permissions in place prior to ponding and water approval. logging, and water • Contractor to submit to PIU pollution. on a monthly basis documentation on material obtained from each source (quarry/ borrow pit) • Avoid creation of new borrow areas, quarries etc., for the project; if unavoidable, contractor to obtain all clearances and permissions as required under law prior to approval by PIU Chlorine usage Chlorine handling & Provide the following measure at the • At the Contractor, PIU DSISC Project as disinfectant at application risk – chlorine application unit: chlorination room observation cost WTP health & safety risk to • Chlorine neutralization pit chlorine neutralization at site and workers and general with a lime slurry feeder pit & leakage detector document public • Chlorine absorption and provide for identification checking neutralization facility purpose. • Proper ventilation, lighting, • The adequate entry and exit facilities lighting, ventilation, • Visible and audible alarm proper access & egress facilities to alert chlorine gas leak provide at chlorination • Facility for isolation in the room. event of major chlorine leakage • The Eye wash, • Eye wash & shower facility Shower, PPEs, SCADA • Personal protection and & handling manual in safety equipment for the operators in local language will be the chlorine plant (masks, oxygen provide. cylinders, gloves, etc.,) • Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier • Supplier of Chlorinator equipment shall provide standard operating manual for safe operation

P a g e | 201

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) and as well as maintenance and repairs; preferably these shall be provided both in English and Bengali Languages. Layout plan of Tree cutting • Minimize removal of trees • No issues of Contractor, PIU DSISC Project WTP by adopting to site condition and with tree felling at the WTP observation cost appropriate layout design of WTP area and Intake point. at site and • Obtain prior permission for • Minimum tree document tree cutting felling may be required checking • Plant and maintain 5 trees at Transmission main for each tree that is removed pipeline area. Will take all necessary permission prior to construction activity after finalization of the design and before felling of trees (if any). Pre-Construction Stage Environmental Impacts & Mitigation Measures Construction Conflicts with local • Prioritize areas within or • The area Contractor, PIU DSISC Project work camps, community; nearest possible vacant space in the selected for construction observation cost stockpile areas, disruption to traffic project location. work camp is vacant at site and storage areas, flow and sensitive • If it is deemed necessary to govt. land and free from document and disposal receptors locate elsewhere, consider sites that any conflict. Sites for checking areas. will not promote instability and result construction work in destruction of property, vegetation, camps, hot mix plants, irrigation, and drinking water supply stockpile areas, storage systems. areas, and disposal • Do not consider residential areas. There is no areas. residential area or • Take extreme care in nearby water body for selecting sites to avoid direct the site selected for disposal to water body which will construction camp. inconvenience the community. Camp away from • For excess spoil disposal, sensitive location like ensure (a) site shall be selected lake/pond/ preferably from barren, infertile Mukutmonipur reservoir. lands. In case agricultural land • WTP area

P a g e | 202

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) needs to be selected, written situated in low land consent from landowners (not area. The excess earth lessees) will be obtained; (b) debris will be utilized for disposal site shall be at least 200 m backfilling. away from surface water bodies; (c) • All health no residential areas shall be located safety arrangement for within 50 m downwind side of the COVID 19 infection site; and (d) site is minimum 250 m needs to be made in away from sensitive locations like camp and which as per settlements, ponds/lakes or other H & S plan and SOP water bodies. specifically for COVID. Consents, Failure to obtain • Obtain all necessary • All necessary Contractor, PIU DSISC Project permits, necessary consents, consents, permits, clearance, NOCs, approval, NOC, observation cost clearances, permits, NOCs, etc. etc. prior to award of civil works. Clearance & permits at site and NOCs, etc. can result to design • Ensure that all necessary has been initiated for document revisions and/or approvals for construction to be safely execution of work checking stoppage of works obtained by contractor are in place at site and given under before start of construction Attachment 4. • Acknowledge in writing and provide report on compliance all obtained consents, permits, clearance, NOCs, etc. • Include in detailed design drawings and documents all conditions and provisions if necessary Asbestos Health risk due to • Obtain details on location of • Detailed Contractor, PIU DSISC Project Cement Pipes exposure to asbestos underground AC pipes construction drawings observation cost materials • Locate the new piper showing alignment of at site and carefully to avoid encountering AC AC pipes Ensured that document pipes AC pipes will leave in checking • Leave the AC pipes undisturbed mood in the undisturbed in the ground. ground. • Company’s Health and safety guideline followed (Attachment 5)

P a g e | 203

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) Construction Stage Environmental Impacts & Mitigation Measures EMP Irreversible impact to • Project manager and all key • Training on Contractor PIU and Project Implementation the environment, workers will be required to undergo EMP implementation, DSISC cost Training workers, and training on EMP implementation SOP, OHS including observation community including spoils/waste management, COVID 19 H & S at site and Standard operating procedures awareness for all document (SOP) for construction works; engaged workmen & checking occupational health and safety staff has already been (OHS), occupational health and done and will be safety (OHS) including COVID 19 H continued at a regular & S awareness, core labor laws, manner. applicable environmental laws, etc. Air Quality Emissions from For all construction works • Air Quality Contractor PIU and Project construction vehicles, • Comply with the Direction of monitoring has been DSISC cost equipment, and West Bengal Department of conducted at WTP and observation machinery used for Environment under the Air Act, 1981 GLSR area during pre- at site and installation of in controlling air pollution from construction phase and document pipelines resulting to construction activities as per plan will be checking dusts and increase in • Comply with the air continued during concentration of pollution / dust control measures for construction phase. vehicle-related construction activities stipulated by • Water sprinkler pollutants such as the “Direction of West Bengal is being used on a carbon monoxide, Department of Environment under regular manner at sulfur oxides, the Air Act, 1981 Direction No. stockpile area, particulate matter, EN/3170/T-IV-7 /001/2009 dated: 10 construction work site nitrous oxides, and December 2009” etc. to control dust hydrocarbons. • Damp down the soil and • Tarpaulin sheet any stockpiled material on site by is being used for water sprinkling; covering of material • Use tarpaulins to cover the during transportation loose material (soil, sand, aggregate and for stock piling. etc.,) when transported by trucks; • Access to work • Provide a dust screen area has been restricted around the construction sites at by application of GLSR and WTP work sites signage, safety tape and • Clean wheels and safety net. undercarriage of haul trucks prior to • Soil

P a g e | 204

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) leaving construction site/quarry stabilization done with • Control dust generation care at work site. while unloading the loose material Pipeline works (particularly aggregate, soil) at the • Safety signage, site by sprinkling water and safety tape/ hard unloading inside the barricaded area barricade will be used • Stabilize surface soils around the construction/ where loaders, support equipment excavated area. and vehicles will operate by using • Excavated water and maintain surface soils in a earth will be used for stabilized condition backfilling. • Use tarpaulins to cover the • Road loose material (soil, sand, aggregate restoration shall be etc.,) when transported by trucks. undertaken immediately. • Apply water and maintain soils in a visible damp or crusted condition for temporary stabilization • Apply water prior to levelling or any other earth moving activity to keep the soil moist throughout the process • Cover the soil stocked at the sites with tarpaulins • Control access to work area, prevent unnecessary movement of vehicle, public trespassing into work areas; limiting soil disturbance will minimize dust generation • Ensure that all the construction equipment, machinery is fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate Pipeline works • Barricade the construction

P a g e | 205

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) area using hard barricades (of 2 m height) on both sides and provide dust/wind screen (such geo textile fabric) up to 3 m height (1m above the hard barricading) • Initiate site clearance and excavation work only after barricading of the site is done • Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the barricaded area • Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area • Undertake the work section wise: 100 – 200 m section should be demarcated and barricaded • Conduct work sequentially - excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done. • Remove the excavated soil of first section to the disposal site; as the work progresses sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. • Backfilled trench at any completed section after removal of

P a g e | 206

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately. Surface water Mobilization of settled • All earthworks be • The surface Contractor, PIU DSISC Project quality silt materials, and conducted during the dry season to water (Reservoir Water) observation cost chemical prevent the problem of soil run-off monitoring for baseline at site and contamination from during monsoon season. data has not been document fuels and lubricants • Avoid stockpiling of earth fill conducted till now at checking during construction especially during the monsoon intake point area & can contaminate season unless covered by tarpaulins remaining will conduct nearby surface water or plastic sheets; as per plan before and quality. • Prioritize re-use of excess during construction. spoils and materials in the • Earthwork, Ponding of water in construction works. If spoils will be stockpiling, filling will be the pits / foundation disposed, only designated disposal plan during dry season excavations areas shall be used; only. • Install temporary silt traps • storage areas or sedimentation basins along the for fuels and lubricants drainage leading to the water bodies; will be away from any • Place storage areas for drainage/ water body fuels and lubricants away from any and the area will be drainage leading to water bodies. constructed with • Store fuel, construction impervious floor. chemicals etc., on an impervious • Temporary floor, also avoid spillage by careful drainage channel handling around the work site will • Dispose any wastes be constructed to trap generated by construction activities the rain water of upper in designated sites; and area. • Conduct surface quality inspection according to the Environmental Management Plan (EMP). • Create a temporary

P a g e | 207

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) drainage channel around the work area to arrest the entry of runoff from upper areas into the work area • Pump out the water collected in the pits / excavations to a temporary sedimentation pond; dispose of only clarified water into drainage channels/streams after sedimentation in the temporary ponds • Consider safety aspects related to pit collapse due to accumulation of water Noise Levels Increase in noise • Plan activities in • Noise Contractor PIU and Project level due to earth- consultation with PIU so that monitoring has been DSISC cost moving and activities with the greatest potential conducted at WTP, and observation excavation to generate noise are conducted intake point. Remaining at site and equipment, and the during periods of the day which will will be conduct as per document transportation of result in least disturbance. plan before and during checking equipment, materials, • Horns should not be used construction and people unless it is necessary to warn other • Construction road users or animals of the equipment, machinery vehicle’s approach. and vehicles will be • Minimize noise from maintained in good construction equipment by using condition to minimize vehicle silencers, fitting the noise generation. jackhammers with noise-reducing • Local mufflers, and use portable street community will be priory barriers to minimise sound impact to informed before surrounding sensitive receptor; and commencement of work • Maintain maximum sound to avoid sensitive time/ levels not exceeding 80 decibels inconvenience. (dBA) when measured at a distance • Public of 10 m or more from the vehicle/s. consultation has been • Identify any buildings at risk conducted to discuss from vibration damage and avoiding the various issues like any use of pneumatic drills or heavy noise pollution, air

P a g e | 208

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) vehicles in the vicinity pollution and water • Consult local communities pollution. Consultation in advance of the work to identify report has been and address key issues, and avoid attached in Attachment working at sensitive times, such as 11. religious and cultural festivals. Landscape and Impacts due to • Prepare and implement a • Waste material Contractor PIU and Project aesthetics – excess excavated Construction Waste Management like concrete is utilized DSISC cost waste generation earth, excess Plan for reuse and filling observation construction • As far as possible utilize the purpose. Also, other at site and materials, and solid debris and excess soil in solid waste like cement document waste such as construction purpose, for example bags collect and in checking removed concrete, for raising the ground level or room/place and then wood, packaging construction of access roads etc., shift to our go down. materials, empty • Stockpiles, lubricants, fuels, • For material containers, spoils, and other materials should be storage care has been oils, lubricants, and located away from steep slopes and taken as per EMP. other similar items. water bodies. • Burning of • Avoid stockpiling any waste is strictly excess spoils at the site for long prohibited in site. time. Excess excavated soils should Construction camp, be disposed of to approved labor hutment will be designated areas immediately. provided with sufficient • If disposal is required, the number of dustbins. site shall be selected preferably from barren, infertile lands; site should locate away from residential areas, forests, water bodies and any other sensitive land uses • Domestic solid wastes should be properly segregated in biodegradable and non- biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at workers camp sites for disposal of biodegradable waste; non-

P a g e | 209

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) biodegradable / recyclable material shall be collected separately and sold in the local recycling material market • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed of in disposal sites approved by local authorities/WBPCB. • Prohibit burning of construction and/or domestic waste. • Ensure that wastes are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper collection bins and create awareness to use the dust bins. • Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate Existing Disruption of service • Prepare a list of affected • At present, Contractor PIU and Project Infrastructure and damage to utilities and operators if any. there is no any DSISC cost and Facilities existing infrastructure • Prepare a contingency plan disruption of service and observation at specified project to include actions to be done in case damage the existing at site and location of unintentional interruption of infrastructure. document service checking Accessibility Traffic problems and Hauling (material, waste/debris • Haul road Contractor PIU and Project conflicts near project and equipment) activities prepared for DSISC cost locations and haul • Plan transportation routes transportation of observation road so that heavy vehicles do not use material for WTP site. at site and narrow local roads, except in the Road is under document immediate vicinity of delivery sites construction for intake checking • Schedule transport and point, which is used for hauling activities during non-peak transportation of

P a g e | 210

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) hours. material and for • Locate entry and exit points communication of in areas where there is low potential villagers and traffic. for traffic congestion. Adequate signage, • Drive vehicles in a safety steward will be considerate manner implemented during • Notify affected public by construction. Local public information notices, providing villagers will be informed sign boards informing nature and in advance to avoid the duration of construction works and inconvenience. contact numbers for concerns/complaints. Pipeline works • Traffic Pipeline works management plan has • Confine work areas along been attached in the roads to the minimum possible Attachment 10. extent; all the activities, including • Local people material & waste/surplus soil will be informed in stocking should be confined to this advance in every case. area. Proper barricading should be Construction work will provided; avoid material/surplus soil be limited by stocking in congested areas – considering the immediately removed from site/ or convenience of local brought to the as and when required people. • Leave spaces for access • Public between mounds of soil to maintain consultation will be access to the houses / properties conducted weekly basis • Provide pedestrian access during the pipeline in all the locations; provide works activity. wooden/metal planks over the open • Continuous trenches at each house to maintain monitoring will be done the access. for avoid material/ • Inform the affected local surplus soil stocking in population 1-week in advance about congested areas – the work schedule immediately removed • Plan and execute the work from site. in such a way that the period of • Barricading

P a g e | 211

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) disturbance/ loss of access is and safety signage will minimum. be used properly at • Keep the site free from all traffic congested area. unnecessary obstructions. • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours Socio-Economic Generation of • Employ local labour force • Will ensure the Contractor, PIU PIU and Project - Employment temporary as far as possible same. DSISC cost employment and • Comply with labor laws observation increase in local at site and revenue document checking Occupational Occupational hazards • Comply with all national, • Company’s Contractor PIU and Project Health and which can arise state and local core labor laws Health and safety DSISC cost Safety during work • Develop and implement guideline is followed observation & also site-specific occupational health and (Attachment 5). at site and Health Hazard from safety (OHS) Plan which will include • HSE induction document COVID 19 pandemic measures such as: (a) excluding and training has made checking public from the site; (b) ensuring all mandatory for all new workers are provided with and use workers. personal protective equipment like • Workers are helmet, gumboot, safety belt, gloves, covered under nose musk and ear plugs; (c) OHS accidental insurance. Training for all site personnel; (d) • Separate first documented procedures to be aid register is followed for all site activities; and (e) maintained at each site. documentation of work-related • Workers are accidents; provided sufficient • Ensure that qualified first number of safety aid can be provided at all times. equipment, high visibility Equipped first-aid stations shall be vests etc. they are easily accessible throughout the site. provided safe drinking • Provide medical insurance water, in-site toilet

P a g e | 212

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) coverage for workers. facility, clean eating • Provide supplies of potable area. drinking water. • Medical test of • Provide clean eating areas every workers will be where workers are not exposed to arranged before start of hazardous or noxious substances. the work. • Provide H&S orientation • Noise training to all new workers to ensure monitoring will be that they are apprised of the basic conducted as per IEE. site rules of work at the site, Supplementary H & S personal protective protection, and plan for COVID 19 preventing injuring to fellow workers. prepared which cover, • Provide visitor orientation if • General visitors to the site can gain access to instruction to follow to areas where hazardous conditions or prevent the spread of substances may be present. Ensure COVID-19 in also that visitor/s do not enter hazard construction workplace areas unescorted. ➢ Detail (step-by- • Ensure the visibility of step) work procedure to workers through their use of high getting the workplace visibility vests when working in or ready under COVID-19 walking through heavy equipment situation operating areas. ➢ Worksite • Ensure moving equipment prevention practiceat is outfitted with audible back-up work site, office, during alarms. meeting, travelling, etc. • Mark and provide sign ➢ Precaution boards for hazardous areas such as taken at workmen energized electrical devices and habitat/ camp lines, service rooms housing high ➢ Control voltage equipment, and areas for measures taken for storage and disposal. Signage shall deploying new workmen be in accordance with international at site standards and be well known to, and • Use of PPEs: face easily understood by workers, mask – hand gloves, visitors, and the general public as maintaining social appropriate; and distancing, disinfection,

P a g e | 213

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) • Disallow worker exposure requirement of to noise level greater than 85 dBA awareness covered for a duration of more than 8 hours under the H & S plan. per day without hearing protection. The use of hearing protection shall (Separate H & S plan for be enforced actively. COVID 19 as • Development of supplementary Supplementary H & S plan for document developed COVID 19 and implementation of and kept as standalone that plan document) Work Camps and Temporary air and • As far as possible located • Have maintained the Contractor PIU and Project work sites noise pollution from the camp site within the work sites safe distance for camp DSISC cost machine operation, (at GLSR and WTP sites); if any as per guideline. All observation water pollution from camp to be established outside conditions will be at site and storage and use of these, then select a camp site away fulfilled as per document fuels, oils, solvents, from residential areas (at least 50 m management plan. checking and lubricants buffer shall be maintained) • Work site office will Unsanitary and poor • Avoid tree cutting for setting be constructed at vacant living conditions for up camp facilities land of the site and workers • Ensure that a proper approval will be compound wall is provided, and collected from PIU. erect a wind/dust screen around • Drinking water facility • Camp site shall not be and Toilet will be located near (100 m) water bodies, available at site. flood plains flood prone/low lying • Wood will not be areas, or any ecologically, socially, used for cooking archeologically sensitive areas purpose. DSISC have • Separate the workers living instructed to use the gas areas and material storage areas for cooking purpose. clearly with a fencing and separate • Camp should be entry and exit protected from COVID • Provide proper temporary 19 pandemic. All Health accommodation with proper and safety procedure materials, adequate lighting and during staying, cooking, ventilation, appropriate facilities for eating, use of toilet to winters and summers; ensure follow (H & S plan for conditions of liveability at work COVID 19 will be used

P a g e | 214

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) camps are maintained at the highest as ref. document); standards possible at all times. • Maintain of • Consult PIU before locating housekeeping, project offices, sheds, and disinfection of camp as construction plants. per SOP of COVID 19 • Ensure good living conditions at work camps are maintained at the highest standards possible at all times; living quarters and construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be allowed as accommodation for workers • Camp shall be provided with proper drainage, there shall not be any water accumulation • Provide drinking water, water for other uses, and sanitation facilities for employees • Prohibit employees from cutting of trees for firewood; contractor should be providing proper facilities including cooking fuel (oil or gas; firewood not allowed) • Train employees in the storage and handling of materials which can potentially cause soil contamination • Recover used oil and lubricants and reuse or remove from the site • Manage solid waste

P a g e | 215

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for bio- degradable waste, and non- biodegradable/recyclable waste shall be collected and sold in local market • Remove all wreckage, rubbish, or temporary structures which are no longer required • At the completion of work, camp area shall be cleaned and restored to pre-project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site Submission of Unsatisfactory • Appointment of EHS • EHS Contractor PIU and Project EMP compliance to EMP Supervisor to ensure EMP supervisor has been DSISC cost implementation implementation appointed at site. observation report • Timely submission of • All formats at site and monitoring reports including pictures have given to the EHS document supervisor, report will be checking submitted at the time of construction. Post- Damage due to • Remove all spoils • During the Contractor PIU and Project construction debris, spoils, excess wreckage, rubbish, or temporary construction period any DSISC cost clean-up construction structures (such as buildings, type of damage due to observation materials shelters, and latrines) which are no debris, spoils, excess at site and longer required; and construction materials document • All excavated roads shall be occurs we will properly checking reinstated to original condition. dispose, reuse or • All disrupted utilities recycle & proper restored housekeeping maintain • All affected structures at project site. rehabilitated/compensated • The area that previously housed the construction camp is to

P a g e | 216

Design Stage Environmental Impacts & Mitigation Measures Cost Responsibility of Monitoring and Field Anticipated Impacts Mitigation Measures Action Taken/Status Implementation of Mitigation Source (1) (2) (3) (4) (5) (6) found (7) be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regressed using the guidelines set out in the revegetation specification that forms part of this document. • The contractor must arrange the cancellation of all temporary services. • Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.

P a g e | 217

CONSTRUCTION STAGE ENVIRONMENT MONITORING PLAN Monitoring Cost as per budget Monitoring Field Monitoring Parameters Frequency Locations* Location (in Rs.) Ambient air 2/3 locations PM10, PM2.5, NO2, SO2, CO Once before start of construction. WTP Area at Lohadihi and 1,80,000/- quality (WTP and Yearly 3- times except monsoon GLSR Area at Gobindpur GLSR/pipe line period during construction (3-year Monitoring has been Sites) period considered) conducted. Rest will be done during construction Ambient noise 4 locations Day time and night time noise Once before start of construction. WTP Area at Lohadihi and 54,000/- (Intake, WTP and levels (24 hours) Yearly 3- times except monsoon GLSR Area at Gobindpur and GLSR, pipeline) period during construction (3-year Intake Area at Kunal bhal period considered) Monitoring will be continued before and during construction Reservoir water 1 location pH, TDS, Oil and Once before start of construction. Not yet conducted. 200000/- quality (Reservoir grease, Cl, F, NO3, TC, Yearly 12 times during intake point) FC, Hardness, Turbidity construction (3-year construction BOD, COD, DO, Total period considered) Alkalinity

P a g e | 218

Figure- 02: Locations of Environmental Monitoring Point

P a g e | 219

LIST OF ATTACHMENTS

Attachment 1: - Details of Manpower Attachment 2: Details of construction Work sites Attachment 3: Details of construction camp site Attachment 4- List of Clearances & Statutory Requirements Attachment 5- Contractor’s EHS Policy &Organization Attachment 6- Utility shifting/relocation Attachment 7- Details of Construction Materials Attachment 8- Details of construction waste / debris / surplus soil Attachment 9- Spoil Management Plan (SMP) Attachment 10- Traffic Management Plan (TMP) Attachment 11- Consultation and Information Disclosure Attachment 12- Grievance Redress Mechanism (GRM)

P a g e | 220

Attachment 1: - Details of Manpower

Details of contractors on-site-personnel and workers Project Manager Mr. S. HAJRA M-9732531325 Site Engineer WTP site- Punish Bansal Mobile No: -9928082421

Intake area- Raju Maity Mobile No: -8348915567 Pipe laying site-A. Rama Rao Mobile No: - 8639389478 Site Supervisor WTP site-Bhairab Das Intake Area- Deep DebnathMOBILE NO: -8420736189 Pipelaying area- - Lal Mohan DasMOBILE NO: -7076717197 EHS Engineer PRASANTA PANDA M-7684097086 Archeological supervisor NA Skilled / semi-skilled workers WTP- 25 skilled and 15 semi-skilled

Intake Point- 25 skilled and 15 semi-skilled Pipe laying site- 10 skilled and 15 semi-skilled Unskilled workers WTP-15 Intake Point- 15 Pipe laying site- 15 Women workers Nil Workers – local / migrant WTP-Local-25 / Migrant-30 (From other districts of West Bengal) Intake Point- Local-25/ Migrant-30 (From other districts of West Bengal) Pipe laying site- Local-40 / Migrant-0

P a g e | 221

Attachment 2: Details of construction Work sites

WTP area site Intake Well site Pipe laying work Location- Lohadihi Mouza, Location- Satsol Mouza, Location- Indpur and Gorabari (GP) Khatra Block Taldangra Block 1 Material storage • Cement • Steel • Fine Aggregate • Shuttering Material

2 Plant & Machinery • Needle Vibrator – 3 Nos • Steel Cutter – 2Nos • Concrete Mixer – 2 Nos 3 Site office – Under progress 4 Laboratory – Under progress 5 Security cabin – Under progress 6 Labor welfare facilities: under progress • Toilets • Drinking water • First Aid Box • Fire Extinguisher 7 Site layout Plan (WTP)

8 Site photographs

P a g e | 222

phs Photogra

Original site WTP Site Before Construction Intake Point

Soil investigation at Intake site Construction Materials

photos Work area photos Work Project Information display board at GLSR site Construction of labour camp at WTP area Site

P a g e | 223

Soil Investigation at WTP area

P a g e | 224

Attachment 3: Details of construction camp site Labour camp at WTP site Camp for Intake point Site Location- – Lohadhi, Gorabari -GP Location- Satsole Mouza, Khatra-Block 1 Accommodation for 30 No's. construction workers Accommodation for 30 nos. construction workers No women / families in the camp No women / families in the camp Facilities provided at camp site Facilities provided at camp site • Separate cooking area • Separate cooking area • Cooking gas • Cooking gas • Drinking water • Drinking water • Bath rooms • Bath rooms • Toilets • Toilets • Drainage system • Drainage system • First aid box • First aid box 2 Camp Site photograph

photographs Labour camp for WTP under construction

Original site Camp

(Before) Labour Hutment at WTP Area

P a g e | 225

Attachment 4- List of Clearances & Statutory Requirements Sl. No. Project related Status A Construction/work related 1 Land details Obtained (Appendix 03) 2 Notice to Proceed from PIU Available B Labour Safety / Welfare Related 1 Labour license Obtained (Appendix 09) 2 Workmen Compensation Obtained (Appendix 08) 3 Risk Policy Under Process C Safety / liability safety related 1 Medical Insurance Tie-up with local hospital made (Appendix 01) D Others 1 Fitness certificate for vehicles, equipment used in Not available construction 2 Pollution under control (PUC) certificates for vehicles and Collection under process equipment 3 Driving licenses for drivers Collection under process 4 Insurance for vehicles / equipment, as required Collection under process

P a g e | 226

Attachment 5- Contractor’s EHS Policy & Organization 1 Contractor agency has a OHS policy Yes/ No A If yes, provide policy details

1. Policy statement: Yes 2. EHS organization & responsibilities: Yes

A List safety risks anticipated in the project Area works (WTP) Area Works (Pipelaying works) Area Works (Intake site) • Trips and falls • Excavation Hazard • Confined Space • Head injury from falling • Slip & Trip during pipe shifting. • Height Work- Fall from height objects • Collapse of side wall of trench. • Excavation Hazard • Height Work • Trap during pipe jointing • Electric hazard • Excavation side wall • Separate health risk from • Materials Handling slip/trip collapse COVID 19 situation • Hot work Fire hazard. Accidents from open • Separate health risk from excavations COVID 19 situation • Separate health risk from COVID 19 situation

C List personal protection equipment provided to workers

• Boots- 55 Pair's. • Boots- 40 Pair's. • Boots- 55 Pair's. • Gloves- 55 • Gloves- 40 Pair’s. • Gloves- 55 Pair’s. Pair’s. • Helmet- 40 No's. • Helmet- 55 No's. • Helmet- 55 No's. • Safety jacket- 40 No's. • Safety jacket- 55 No's. • Safety jacket- 55 • Goggles- 40 No's. • Goggles- 55 No's. No's. • Gum-boots- 40 Pair's. • Gum-boots- 55 Pair's. • Goggles- 55 • Nose mask – 40 nos • Nose mask – 55 nos No's. • Face mask – 40 nos. • Face mask – 55 nos. • Gum-boots- 55 Pair's. • Nose mask – 55 nos • Face mask – 55 nos. D Preventive Measures • Orientation of all workers on OHS and specifically COVID Yes 19 risks and mitigation • Work permit system Yes – for work at height • Toolbox/safety meetings (how often will this be conducted, Twice Weekly what are the minimum topics) on work at height, firefighting, first-aid, housekeeping, health risk covering COVID 19 risk etc Safety signages Displayed on site, including COVID 19 IEC document, posters Barricade Provided 2 Contractor emergency procedure A • In case of accident, first aid treatment to injured labour/person shall be provided. • In case hospitalization is required, concerned site in-charge will immediately take necessary action for hospitalization and he will inform to our Project Manager. • Details of accident shall be reported in accident register and the same shall be informed to client also. • Emergency plan for tackling COVID 19 situations (ref. H & S plan for COVID 19 pandemic). Identification of Emergency Response Team (ERT) B Contact information, staff and responsibilities for emergency situations

P a g e | 227

(Separate responsibility matrix is prepared for COVID emergency situation, included in supplementary H & S plan) Designation Staff name & contact Emergency responsibility Site Engineer WTP Site-PUNISH BANSAL Site Engineer shall be responsible for arranging of first aid Mob:9928082421 treatment and other necessary action required in case of Intake Area- RAJU MAITY emergency. Mob: He will also be responsible for informing to EHS Supervisor. Pipe laying area- A. RAMA RAO Mob: 8639389478 EHS Engineer. Name-PRASANTA PANDA EHS Supervisor should assess the emergency situation and Mob: 7684097086 accordingly instruct the Site Engineer of appropriate actions. Depending on the gravity of the situation, he should also inform Project Manager Representative. Project Name- Mr. S. HAJRA Project Manager Representative shall be responsible for taking Manager Mob: 9732531325 all necessary action and decisions. Representative C Reporting procedure in case of work accidents Yes • Details of accidents shall be recorded in accident register. • Copy of accident register shall be submitted to client at the end of every month. • In case of any major accident client shall be informed immediately. D Mandatory Reporting to Authorities Yes E Prohibited Acts and Penalties for Violations Yes

Attachment 6- Utility shifting/relocation

List work sites that require utility shifting, relocation, Sl. No. Remarks temporary shut off 1 Area work sites {WTP; Lohadhi, Khatra (Block)}, Bankura LT Line shifting is required at • Administrative Building WTP area Permission is under • Chemical House Extension process. • Inlet Chamber

Attachment 7- Details of Construction Materials Indicate if source has Sl. Approximate quantity all necessary Material Source No required for project government Clearances 1 Steel 1500 MT Tata Steel, SAIL & RINL Yes

2 Cement 100000 Bags Ultratech, Nuvoco, ACC Yes

3 Sand 7500 M3 Kangsabati River Yes

4 Aggregate 10000 M3 Rampurhat, Pachami Yes

P a g e | 228

Attachment 8- Details of construction waste / debris / surplus soil Indicate whether it will be In case of disposal, Sl. Waste likely be Type of debris / Approximate reused indicate disposal site No. generated waste quantity /disposed off name & location 1 Construction Steel, Shuttering N/A Scrap steel shall be sold, N/A waste / debris Plates, Bamboos, shuttering plate, bamboo, Ply etc. ply etc. shall be reuse 2 Surplus soil Excavated earth 51,165 cum Good earth Shall be used PHED land to fill up the low land area inside the premises and balance shall be disposed at designated area shown by PHED. To soil will be preserved and re-laid on top of fill area. 3 Hazardous (oils, lubricants, N/A N/A N/A waste, if any chemicals), if any (as only preparatory construction activities are in progress)

P a g e | 229

Attachment 9- Spoil Management Plan (SMP)

P a g e | 230

1. INTRODUCTION OF SMP:

SMP is to describe how the project will manage the spoil generated and reuse related to design and construction works. This is an integral part of EMP. The objective of SMP is to reuse of spoil from works.

2. SCOPE:

This Spoil Management Plan developed for WTP, Intake and Pipeline laying works. We do not anticipate any excess Spoil for disposal as all excavated material will be reuse at site only.

3. LEGAL AND OTHER REQUIREMENTS:

In this project, there is no legal litigation at site for land and working area or site. Disposal of spoil will be confirming the Environmental Protection Rules and Regulations of Govt. of India and the State Govt.

4. ROLES AND RESPONSIBILITY:

SITE ENGINEER: • Will strictly work as per drawing. • Will stay at site during activity is going on. • Will see excess earth is kept at a particular place after completion of backfilling. • Will ensure quality of the work by discussing daily about the type of activity on that day with the workmen. • Will check site drain outlets are not blocked due to excavated earth on the drain.

SAFETY PERSONNEL: • Will constant Job specific Tool Box Talk with Supervisor and Workmen. • Will check excavated earth kept away from top. • Will check if any underground pipeline is there or live electric cable there water should be sprayed to avoid dust hazard from excavation. • Necessary Safety signage, Cones& FRP Barricading Board to be used. • Vehicles reverse horn etc. to be checked will ensure zero tolerance in safety.

WORKER: • They will start activity only after Tool Box Talk done. • They will wear job specific safety items before start of work. • During working inside the excavated trench, they should use ladder for easy access. • They should barricade the area of activity with Safety barricading tape. • Worker should be skilled to carry out the work.

It is the responsibility of the Engineers and all department head to implement this procedure and ensure that delegated staff and worker under their supervision carry it out in this project. Major roles and responsibilities are mentioned below: • Excavated earth should be utilized like refilling at site only. • Traffic movement should not be obstructed by dumping soil during the work. • No low land, pond, ditch etc. will be filled up by extra soil outside the work place.

P a g e | 231

• Ensuring no accident occurs during rainy season by excavated earth during or finished the work. • All the drains, outlet should be free from excavated earth.

5. IDENTIFICATION AND ASSESSMENT OF SPOIL ASPECTS AND IMPACTS:

In this project, places will be identified jointly along with design engineer for utilization. Main places where the excavated earth can be utilized are the trench of pipes and backfilling location.

6. SPOIL VOLUMES AND CHARACTERISTICS:

In this zone, Generation of excavated earth will be approx. 51,165cum. There is no excess earth in this project as the same earth is to be used to fill the low land area.

7. SPOIL REUSES OPPORTUNITIES, IDENTIFICATION AND ASSESMENT:

In this project, there is no excess quality of excavated earth; total excavated earth should be reuse as per plan.

8. ON SITE SPOIL MANAGMENT APPROACH:

In this project, no need of the approach as there is no extra soils for disposal.

9. SPOIL TRANSPORTATION METHODOLOGY:

In this project, no need for spoil transport as there is no extra soils for disposal.

10. MONITORING, REPORTING, REVIEW AND IMPROVEMENTS:

Monitoring, Reporting and all necessary improvements will be done as per requirements.

P a g e | 232

Spoil Details- FOR WTP

Sl. No. Excavation Name of Structure Total Quantity (C.U.M) 1. Boundary wall 1324

2 Inlet System 503

3 Flocculator and Inclined Plate Settler 780

4 Chlorinator room, Chlorine Toner Room 195

5 Chemical House & Sludge Pump House 1150

6 Gravity Sand Filter 3430

7 Clariflocculator 5735

8 Sludge and Wash Water Collection Sump Cum Pump house 3590

9 Clear Water Reservoir, Pump House, Sump & Inlet Chamber 3036

10 Backwash Tank 721

11 Sludge Lagoon 3250

12 Electrical Substation Building 648

13 Transformer/ DG Set Yard 935

14 Staff Quarter, Guard Room, Admin Building & Open parking 1242

Approx. generated total Spoil 26442

FOR PIPELINE LAYING Sl. Día Length(m) Width(m) Depth(m) Total (cum) 1 900 2900 1.5 1.9 8265 2 700 22000 1.3 1.7 42900 Approx. generated total Spoil = 51165

P a g e | 233

Attachment 10- Traffic Management Plan (TMP)

P a g e | 234

1. PURPOSE

Main purpose is to prevent accident between vehicles, pedestrians and employees and also minimize inconvenience to the vehicle. To stop property damage and prevent injury to persons arising from site traffic and site transport.

2. SCOPE

The procedure is applicable for HDPE/DI pipe laying area.

3. RESPONSIBILITY

It is the responsibility of the Engineers and all department head to implement this procedure and ensure that delegated staff under their supervision carries it out.

4. LEGAL REQUIREMENT

The Building and Other Construction Workers (Regulations of Employment and Conditions of Service) Act 1996 and Central Rule 1998 Rule 48, 88 and 95, Motor Vehicle Act 1988.

5. REQUIREMENTS

5.1 General

• All road works create inconvenience and are a potential hazard to the safety of all road users and those employed in carrying out the work. • All the effects should be reduced to the minimum, and to ensure that the works are properly guarded, lighted and signed. • A clear and early warning of any obstruction to all road users should be provided. • All areas where work is going on should be clearly demarcated by proper barricading and entry into these areas should be restricted to only authorize personnel. • Site access for local people.

5.2 Planning Stage

Particular attention should be given to:

P a g e | 235

• Traffic signs • Cones • Barriers • FRP Barricading Board • Road hazard warning lights • Information boards and • Site lighting • Site access for local people • Consider necessity to traffic control systems such as temporary traffic lights or Stop/Go boards. • Access should be planned to eliminate dangerous movements of site traffic (e.g. reversing of vehicles) and personnel (e.g. crossing dual carriageways). • Provision of adequate lighting while working at night. • All persons working on the road shall wear high visibility jackets.

5.3 On Site

The working space shall be defined and “A PLACE FOR EVERYTHING AND EVERYTHING IN ITS PLACE’’ to be follow. 5.4 Operators/Drivers o Only Experienced operators and drivers with valid licensed has been appointed. o One copy of license has been collected. o Refreshment training conducted for all operators and drivers. o Operators/Drivers authentication and validation to operate the particular machinery displayed in the machine/vehicles.

5.5 Equipment

• Drivers undertake a daily visual inspection of their vehicles include steering, brakes, mirrors, lights, horn, tyre’s and windshield wipers. • Safety Department along with Plant and machinery department shall check the vehicles as a monthly basis. • All vehicles have reverse horns and it is in working properly. • All vehicles, preventive maintenance schedule has to be followed strictly.

5.6 Roads

For safe operation we are following the below safety measure: • Safe width of road has been provided. • Flag man deployed at every traffic point to control the vehicles and pedestrians. • Speed limits 10km/hr. within the working area. • Caution board has been placed in every location within the site. • Workers are working with reflective jacket as well as required PPE’s. • Road for use of pedestrian has been identified. • Reverse horn used in vehicles. • While reverse vehicles ensuring Banks man. • Do’s and Don’ts displayed at site office.

P a g e | 236

5.7 Loading and Unloading

• Only authorized persons were engaging loading/unloading. • Materials loaded within the permitted safe weight limit (as per RTO) for the truck. • Ensuring Soil and Sand loaded trucks are covered with tarpaulin while transporting • During Toolbox talk’s intimation has been delivered to all drivers/operators that when the drivers leave the driving seat, the engine of the truck shall be switched off, the gear engaged and parking brakes applied. On slopes, wheel blocks shall be applied. • Helper has been provided with all vehicles. • After unloading, the banks man ensuring that the tipper is lowered before moving. • Turn buckle and side stoppers used while transporting as required.

5.8 Working Area

• The working area has been restricted from unauthorized entry. • The working space has been defined. • Particular attention has been taken in working area: • Traffic signs • Cones • Barriers • Information boards, and • Site lighting • Adequate lighting has been provided at working area at night. • All persons wear high visibility jackets.

P a g e | 237

Traffic Management Plan (Drawing)

P a g e | 238

Attachment 11- Consultation and Information Disclosure

• Local population is informed through community leaders as well as by visiting individual households of the locality. • Information board is placed at construction site • Stakeholder consultation carried out at Gram Panchyat level and work details including time period is informed. Consultation report is attached below----

P a g e | 239