RIVER ITHON BRIDGE A470 Cwmbach to Newbridge-on-Wye Client

Welsh Government

Location

Builth Wells

Date

2010-2011

Value

Project £36m

The £36m scheme comprised the construction of 6km of single carriageway between Cwmbach & Newbridge-on-Wye on the A470 trunk road, incorporating three significant structures over the existing A470, River Ithon and Central rail link. Nine multiplate arch culverts were provided as mammal underpasses.

Ithon Bridge The Ithon Bridge crosses the River Ithon just South of Newbridge-on-Wye, near . The structure comprises an 85m two span bridge, with reinforced concrete abutments at each end and one centrally located reinforced concrete pier. The over deck comprises a structural steelwork concrete composite construction.

The River Ithon is a designated Special Area of Conservation (SAC) being a tributary of the , which is located 1 mile downstream.

The north abutment and pier were constructed within a flood plain and

Alun Griffiths (Contractors) Ltd Waterways House · Llanfoist · Abergavenny · Monmouthshire · NP7 9LN Tel. 01873 857211 · Fax. 01873 857679 Email [email protected] · www.alungriffiths.co.uk

were founded upon the bed rock, which leant itself to the design of the spread foundations, minimising excavation depths and over dig. On the south side of the river the existing topography meant that to construct a conventional abutment would have required considerable excavation and increased safety and environmental risks. In conjunction with our designers the abutment was designed to be reversed, bringing works closer to the river and having the effect of minimising the excavation depth and extent.

With such environmentally sensitive conditions the works were very carefully planned and close co-ordination between all concerned parties ensured the bridge was successfully completed without incident.

The bridge deck used “Omnia” permanent formwork reducing the need for temporary works underneath the deck and over the River. The Omnia units were sealed prior to placing the concrete which avoided any risk of grout loss into the water or onto the ground below.

The remainder of the bridge used conventional construction methods for the parapets, waterproofing, surfacing and drainage elements. Careful consideration was given to the chemical composition of the construction materials used to avoid any which may prove harmful to the surrounding environment.