Environmental Monitoring Report

Project Number: 39228 January 2010

PRC: Wastewater and Stormwater Management Project

Prepared by H&J, Inc. USA. & Wuhan Hongshan Environmental Monitoring Station Province, PRC

This report has been submitted to ADB by the Wuhan Municipal Government Project Management Office and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB. ADB FINANCED WUHAN WASTEWATER AND STORM WATER

MANAGEMENT PROJECT

Loan No. 2240-PRC

ENVIRONMENTAL MONITORING REPORT No.3

To be submitted to Asian Development Bank & Wuhan Urban Construction Utilization of Foreign Investment Project Management Office

H&J, Inc. USA. & Wuhan Hongshan District Environmental Monitoring Station

January 2010

Environmental Monitoring Report(2009-03) ADB WWSMP

CONTENTS

1. BACKGROUND OF PROJECT ...... 1

2. OBJECTIVE OF MONITORING...... 6

3. IMPLEMENTATION STATUS FOR ENVIRONMENTAL MITIGATION MEASURES DURING CONSTRUCTION...... 7

4. ENVIRONMENT PROTECTION TARGETS ...... 12

5. MONITORING DURING CONSTRUCTION...... 13

6. CONCLUSION AND RECOMMENDATION...... 20

APP1. MONITORING REPORT OF AMBIENT AIR QUALITY ...... 21

APP2. MONITORING REPORT OF ENVIRONMENTAL NOISE ...... 21

APP3. WEEKLY AND MONTHLY MONITORING REPORT DURING CONSTRUCTION SUBMITTED BY CONTRACTOR ...... 21

i Environmental Monitoring Report(2009-03) ADB WWSMP

ADB Loan No. 2240-PRC: Wuhan Wastewater and Stormwater Management Project Environmental Monitoring Report Environmental Monitoring Entity: Wuhan Hongshan District Environmental Monitoring Station (HDEMS) Consulting Firm: H&J, Inc. USA Project EA: Wuhan Municipal Project Management Office (WPMO) Period of Monitoring: May. 1 to Dec. 31, 2009 1 Background of Project Wuhan Municipal Government has obtained the loan from ADB for implementation of the Wastewater and Stormwater Management Project (WSMP) for achieving the objective of sustainable wastewater and stormwater management, as well as the water resource protection. The Project consists of five wastewater subprojects and four stormwater subprojects. See table 1 below in detail. Table 1 No. Subproject Scope of Subproject Erlangmiao WWTP Existing 180,000 m3/d (primary) WWTP to be 1 Expansion and upgraded and expanded to 240,000 m3/d (secondary) Upgrade Nantaizi Lake i) Existing 100,000 m3/d (secondary) WWTP to be WWTP Expansion 2 expanded to 200,000 m3/d (secondary); ii) 7.43 km of and Wastewater collection system; iii) Three pumping stations Collection System Huangpu Road i) Existing 100,000 m3/d (screening) WWTP to be 3 WWTP Upgrade upgraded to secondary Dongxihu i) 25.35 km of collection system; ii) Five pumping 4 Wastewater stations Collection System Caidian WWTP and i) New 50,000 m3/d (secondary) WWTP; ii) 4.59 km 5 Wastewater of Collection System collection system; iii) One pumping station Yangsigang i) 1.34 km of pipeline and 1.90 km of culvert; ii)One 6 Pumping Station and pumping station Drainage Dongxi Lake Three i) 3.91 km of culvert, 4.34 km of channel, ii) and 7 Gates Connection renovation of 4.48 km of existing channel.

1

Environmental Monitoring Report_No.3 ADB WWSMP

No. Subproject Scope of Subproject Changqing Pumping i) Existing pumping station to be increased by 135 8 Station Expansion m3/s Luojia Road i) 0.39 km of culvert and renovation of 8.81 km of Pumping Station existing 9 Expansion and channel; ii) Existing pumping station to be increased Drainage by 55 m3/s

By the end of Dec 2009, five of the above subprojects had been commenced and are being constructed including subprojects of Erlangmiao WWTP_II, Dongxihu Three Gates Connection, Nantaizi Lake WWTP_II, Caidian WWTP and Dongxihu Wastewater Collection System. (1) Erlongmiao WWTP subproject is located in east of Xudong Road in , nearby Wuqing No. 4 Trunk Road. The construction period of the subproject is from third quarter of 2007 to the end of 2009. The construction activities include structures/building construction, demolishment and laying down of underground pipelines, replant trees and landscaping, etc. the treatment capacity of the WWTP will expand from 180,000 m3/day to 240,000 m3/day; and the treatment process will be updated from primary to secondary. The employer of the subproject is Wuhan Municipal Drainage Development Company. (2) Dongxihu Three Gates Connection subproject is located by the Jinyin Lake with the catchment area of 56.7km2. The construction scope includes 3.91 km of culvert, 4.34 km of channel, and renovation of 4.48 km of existing channel. After completion of the subproject, the sewer will drain to Hanxi WWTP and the stormwater will discharge into the Fuhe River. The construction has been completed by December 2009, and employer of the subproject is Wuhan Jianxing Urban Infrastructure Construction Company. (3) Nantaizi Lake WWTP Expansion subproject (phase II) is located at the site of 1000m of north of the Third Bridge of the Yangdze River. The area of the construction site is about 150mu (10ha); the capacity of the WWTP will reach to 100,000m3/d after completion of the subproject; the subproject will be completed by end of 2010. (4) Caidian WWTP is sited on east of Beijing-Zhuhai Expressway, north of Caihe Street and south of the . The service areas of the proposed subproject include Caidian downtown area and Caidian Eastern Development Zone. The short term capacity is 50,000m3/d, and will expand to 100,000m3/d according to the planning. The treatment capacity of the WWTP will be updated to 100,000 m3/d. The subproject has been completed by end of 2009. (5) Dongxihu Wastewater Collection System is sited at Jinshan Road and Jinyinhu area. A wastewater collection system of 25.35 km will be built.

2 Environmental Monitoring Report_No.3 ADB WWSMP

The subproject has been completed by December 2009. IA of this subproject is Caidian Branch of Wuhan Urban Drainage Development Company. The information of the contracts being constructed is shown in table 2. Table 2

Contr Supervision Completi Contract act Contractor Start Date Company on Date No. Site and foundation WW/C Wuhan Wuhan 2007-10 2007-12 preparation works 1.2 Municipal River for Erlangmiao Engineering Construction WWTP Group Supervision Co Civil works of WW/C NO. 4 Wuhan 2007-12 2008-12 Erlangmiao 1.1a Railway Zhongnan WWTP upgrading Construction Construction and expansion(I) Bureau Supervision Company Civil works of WW/C No. 4 China Wuhan Zhongnan 2007-12 2008-12 Erlangmiao 1.1b Railway Construction WWTP upgrading Construction Supervision and expansion(II) Bureau Company Dongxihu SW/C Hanyang Wuhan Municipal 2007-11 2008-5 Tri-Gates 8.1 Municipal Construction Connections Works Engineering Supervision (I) Company Company Dongxihu SW/C Wuhan Wuhan Zhongnan 2007-11 2008-5 Tri-Gates 8.2 Municipal Construction Connections Works Special Supervision (II) Construction Company Company Dongxihu SW/C Wuhan Gas Wuhan Jingcheng 2007-11 2008-5 Tri-Gates 8.3 & Heating Construction Connections Works Company Supervision (III) Company Dongxihu SW/C No. 4 China Wuhan Zhongnan 2007-11 2008-5 Tri-Gates 8.4 Railway Construction Connections Works Construction Supervision (IV) Bureau Company Dongxihu SW/C Wuhan Wuhan Municipal 2008-4 2008-9 Tri-Gates 8.5a Municipal Construction Connections Works Engineering Supervision (Va) Group Company

3 Environmental Monitoring Report_No.3 ADB WWSMP

Contr Supervision Completi Contract act Contractor Start Date Company on Date No. Dongxihu SW/C Wuhan Wuhan Municipal 2008-6 2008-12 Tri-Gates 8.6a Municipal Construction Connections Works Special Supervision (VIa) Construction Company Company Site and foundation WW/C Wuhan No.2 Wuhan Yangtze 2008-6-16 2009-2 preparation works 2.2 Municipal River for Nantaizi Lake Engineering Construction WWTP expansion Co. Supervision Co Civil works of WW/C Zhejiang Wuhan Nante 2008-11-25 2009-6 Caidian WWTP 4.1b Baoye Construction Construction Supervision Co. Co. Pipe works along WW/C Hongrun Huanlong 2009-4-10 209-12-31 Jinshan Road in 5.2 Constrution Supervision Firm Dongxihu (I) Group Corp., Ltd Pipe works along WW/C Qingshan Huanlong 2008-10-21 2009-6-30 Jinshan Road in 5.3 Municipal Supervision Firm Dongxihu (II) Co., Ltd Pipe works along WW/C Yitong Huanlong 2008-10-21 2009-6-28 Wuhuan Road in 5.4 Construction Supervision Firm Dongxihu Co., Ltd Pipe works along WW/C Huanlong 2008-10-21 2009-6-28 Shizhigou & 5.5 Construction Supervision Firm Machengnan Road Co., Ltd in Dongxihu Wastewater WW/C Wuhan Wuhan Municipal 2008-5-4 2008-10-14 collection system 5.6 Urban Supervision Firm along Jichang Construction River in Dongxihu Group Corp., -Box-culverts (I) Ltd. Wastewater WW/C No.4 Wuhan Wuhan Municipal 2008-7-8 2009-4-10 collection system 5.7 Municipal Supervision Firm along Jichang Construction River in Dongxihu Co., Ltd. -Box-culverts (II)

4 Environmental Monitoring Report_No.3 ADB WWSMP

Contr Supervision Completi Contract act Contractor Start Date Company on Date No. Wastewater WW/C Hanyang Wuhan Municipal 2009-9-17 2010-2-17 collection system 5..8 Municipal Supervision Firm along Jichang Engineering River in Dongxihu Company -Box-culverts (III) Wastewater WW/C Wuhan Wuhan Municipal 2009-9-17 2010-2-17 collection system 5.9 Urban Supervision Firm along Jichang Construction River in Dongxihu Group Corp., -Box-culverts (IV) Ltd. Site and foundation WW/C Wuhan Nante 2008-8-1 2008-10-12 preparation works 4.1a Pengxin Supervision Firm for Caidian WWTP Urban Construction Co., Ltd Supply and WW/M Beijing Nante 2009-9-25 2010-2-25 installation for 4.4 Zhonghui Supervision Firm Caidian WWTP Co., Ltd Dongxihu SW/C8 Wuhan Wuhan Municipal 2008-11-27 2009-6-20 Tri-Gates .8 Fengsheng Supervision Firm Connections Urban Works-Box Culvert Construction (VIII) Zonghe Development Co., Ltd Dongxihu SW/C8 Hanyang Wuhan Municipal 2008-7-24 2008-1-30 Tri-Gates .6b Municipal Supervision Firm Connections Engineering Works-Box Culvert Company (VII) Dongxihu SW/C8 Wuhan Feihong 2009-4-24 2009-12-30 Tri-Gates .6c Changfeng Supervision Firm Connections Municipal Works-Open Water Co., Channel (I) Ltd Dongxihu SW/C8 Wuhan Feihong 2009-4-24 2009-12-30 Tri-Gates .6d Urban Supervision Firm Connections Construction Works-Open Group Corp., Channel (II) Ltd.

5 Environmental Monitoring Report_No.3 ADB WWSMP

Contr Supervision Completi Contract act Contractor Start Date Company on Date No. Site and foundation WW/C Wuhan Yangtze River 2009-6-8 2010-4-30 preparation works 2.2 Urban Supervision Firm for Erlangmiao Construction WWTP Group Corp., Ltd. Supply and WW/M Hubei Zhongnan 2009-6-26 2010-4-30 installation for 1.3 Richstates Supervision Firm Erlangmiao Industry WWTP upgrading Investment and expansion Co.,Ltd.) 2 Objective of Monitoring Based on the requirements in the EIA of the Project, the objectives of the monitoring are: • to assess if the statuses of constructions satisfy the project performance indicators, as well as both ADB’s and China’s environmental policies and standards; • to evaluate extent and severity of environmental impacts compared with the predicted impacts; • to inspect contractors’ performance of the environmental impacts mitigation measures or compliance with related rules and regulations; • to answer and solve public complains; • to evaluate trends of impacts and overall effectiveness of the project’s Environmental Management Plan (EMP). Wuhan Hongshan District Environmental Monitoring Station (HDEMS) conducted the monitoring and the environmental inspections for the above mentioned subprojects (16 contracts) under the five subprojects during the period. • 20 May 2009 (Erlangmiao WWTP_II); • 28 October 2009 (Dongxihu Three Gates_VI); • 13 May 2009 (Caidian WWTP and Nantaizihu WWTP_II) • 30 October 2009 (Nantaizihu WWTP_II) • 28 October 2009 (Dongxihu Wastewater Collection System)

6 Environmental Monitoring Report_No.3 ADB WWSMP

Table 3 Environmental Inspection Contents during Construction

Item Inspection Contents Ambient Air Mitigation Measures for construction dust and vehicles emissions Noise Noise sources: reasonable layout of construction site; are advanced construction methods conducted? are low-noise equipment used? Are noised equipment far apart from residential areas? is noised construction stopped during night time? Are measures taken for avoiding controllable noise? If ban construction vehicles from sounding their horns to reduce noise impact; if try best to transport material during non traffic rush hours Ecology Properly arrange the construction time; backfills are taken as soon protection as possible after completion of the earth works; brick wall should be constructed for enclosure of open-air earth and material storage places; ecological restoration, such as re-vegetation and land leveling should be conduct after completion of the contraction; conduct ecological inspection along the pipeline rout. Environmental Environmental management plan: includes emergency response Management action plan; methods and regulations for solid wastes storage and Regulation disposal; personnel responsibilities for environmental mitigation.

3 Environmental Protection during Construction 3.1 Implementation Status for Environmental Mitigation Measures The Consultant, H&J, Inc. USA distributed standard firms for inner environmental monitoring to each of the contractors early in 2008 including weekly and monthly standard forms, which will be submitted to the consultant every month with the signatures of contractors and construction supervision engineers. The six (6) contractors of the sixteen (16) constructions set up and submitted the environmental management plans and their weekly and monthly environmental monitoring reports on schedule. Refer to the app. The emergency response action plans for environmental pollutions during construction are worked out by each of the contractors. And the environmental supervision organizations of the contractors were also established. 3.1.1 Erlangmiao WWTP_II Subproject The contractors of Erlangmiao WWTP_II Subproject have completed the following jobs: • Set up regulations for environmental protection issues during construction by each of the contractors • Set up the site environmental management plan, properly treatment and disposal of construction wastes;

7 Environmental Monitoring Report_No.3 ADB WWSMP

• The ecology restoration measures were conducted including ecological compensation and re-vegetation. The mitigation measures are listed in Table 4 according to the submitted forms. Table 4

Item Mitigation Measure Materials transport and Materials are covered during transportation to avoid dust hauling generation; Disposal and storage of Minimizing and proper storage of petroleum products, hazardous and petroleum hazardous, reactive, ignitable and flammable materials on materials site, to avoid impacts to soil, groundwater and surface. Erosion protection Measures have been taken Disposal of solid and Measures have been taken liquid wastes Wastewater discharge Measures have been taken Water collection basins N/A and sediment traps. Soil erosion on road Measures have been taken Culture conflicts N/A Protect trees nearby earth pits, and minimizing impact to Landscaping nature vegetations Re-vegetation in short period after completion of Re-vegetation constructions All construction drainage areas with water collection Constructions nearby basins and sediment traps. Oil separators are constructed river and other sensitive on all construction equipment wash-down areas to avoid areas contamination of the nearby rivers. Vibration Take anti-vibration measures Stability of slope Cover the slope with textile material Appropriate storage of petroleum products, hazardous Disposal of empty materials and wastes on an impermeable surface in a containers for hazardous secure, covered area; hazardous waste will be stored materials separately from non hazardous waste. Restore the site by contractors after completion of Restoration of sites constructions Surface soil Take proper measures Proper lay out of vehicle Take measures to ensure lands can be agriculturally used routs after completion of constructions Restoration of earth Follow the relevant regulations. Ban any arbitrarily taking taking pits earth Contractor’s temporary Designing temporary construction camps and storage land used areas to minimize land area required and impact on soil

8 Environmental Monitoring Report_No.3 ADB WWSMP

erosion. Properly store construction materials, and disposal rubbish following the regulations. Earth excavation Properly disposal residue earth and mud.

The contractors conduct noise-protection measures and use low-noise equipment during the construction for mitigation of noise impact; and for air pollution control, the contractor arrange 10 full-time workers for daily cleaning, water spraying and maintaining the construction site and nearby roads. 3.1.2 Dongxihu Three Gates Connection Subproject The contractor of the Subproject had worked out the regulations for environmental impacts mitigation during construction. The self environmental monitoring monthly report, as well as the weekly checks was conducted by the contractor. The mitigation measures are being taken are as follows: • Water spraying of transportation routes and materials handling sites where dust is being generated; • Al hazardous, or harmful construction materials including petroleum products were stored on an impermeable surface and managing these materials in such a way as to prevent spillage or leakage, which could spread and affect surface water or groundwater systems; • Protect trees nearby earth pits, and minimizing impact to nature vegetations; After pipe-laying construction, the trenches will be properly compacted and re-vegetated; • Take measures to protect surface soil from corrosion, to ensure the land can be agriculturally used after completion of the construction • Properly disposal residue earth and mud. • Noise Control:

i. Installed the noised machineries at proper location where far from residential areas;

ii. Arranged proper construction time, report the local EPB and got permission for night construction;

iii. Keep the equipment in good operation condition by strengthening maintenances;

iv. Covered and enclosed the noised equipment during construction • Air Pollution Control:

i. Stopped using Environmental non-compliance equipment;

9 Environmental Monitoring Report_No.3 ADB WWSMP

ii. Arranged specific workers for cleaning and water spaying construction site and routs 3.1.3 Caidian WWTP Subproject The contractor of the Subproject had submitted the monthly environmental monitoring report on schedule. According to the site inspection, the mitigation measures are being taken are as follows: • Set up regulations for environmental protection issues during construction by each of the contractors • Drew up the site environmental management plan, properly treatment and disposal of construction wastes; • The ecology restoration measures were issued including ecological compensation and re-vegetation. • For Noise Control, the contractor’s staff of the specifically appointed for monitoring noise along the borders of the site, and took quick measures for controlling the noise; • Took measures, such as covered the material and transport vehicles, spaying water on site, cleaning construction wastes timely, etc. for reducing the dust generation. 3.1.4 Nantaizihu WWTP Expansion

The contractors conduct the following measures for mitigating the environmental impacts: z Constructed temporary gateway and enclosure for isolation of the construction site; z Publicized environment protection surrounding the construction site; z Established a civilized construction team for maintaining clean construction sites; z Built a facility for vehicle washing, and wash the vehicles and construction machineries before out of the construction site; z Protect trees nearby earth pits, and minimizing impact to nature vegetations; After pipe-laying construction, the trenches will be properly compacted and re-vegetated; z To ensure the land can be agriculturally used after completion of the construction z Take measures to protect surface soil from corrosion; Properly disposal residue earth and mud.

10 Environmental Monitoring Report_No.3 ADB WWSMP

z Noise Control:

i) Arranged proper construction time;

ii) Installed the noised machineries at proper location where far from residential areas;

iii) Keep the equipment in good operation condition by strengthening maintenances;

iv) Covered and enclosed the noised equipment during construction z Air Pollution Control:

i) Conducted the construction section by section for reducing dust

ii) Properly stored the construction materials and disposed the construction wastes; z Arranged specific workers for cleaning and water spaying construction site and routs

All the contractors of the above subprojects have submitted their environmental management regulation and the implementation results to the local EPB and Wuhan Municipal Drainage Company. 3.2 Environmental Monitoring Training H&J, Inc. held three environmental monitoring trainings during January 2009 to December 2009 according to the implementation status. The trainings contents include:

z Objectives and requirements of EMP during construction;

z Contractors’ regulations and personnel for environmental protection during construction;

z Relevant environmental laws, regulations and standards;

z Major environmental impacts and corresponding mitigation measures;

z Detailed monitoring parameters and site environmental inspection;

z Requirements and explanation for filling-in the environmental daily and monthly reports After the training, the training materials and the standard tables were distributed to all

11 Environmental Monitoring Report_No.3 ADB WWSMP the contractors. H&J required the contractors to commit all the mitigation measures, and incorporated all the environmental regulations into their QA/QC systems. 3.3 Routine Supervision and Inspection All the contractors submitted the tables/forms on schedule based on the Consultant’s requirements. During the period from January to December 2009, eighteen (18) forms had been received. Wuhan Hongshan District Environmental Monitoring Station, entrusted by the Consultant, conducted the monitoring for air, water and noise, as well as the sites inspections for contractors’ environmental management and implementation of the mitigation measures during the period from January to December 2009. 3.4 Environment Management of Construction Sites All the contractors has assigned full time staff for environment management, and the environmental mitigation measures were listed as an issue of construction implementation plan; the notice boards were erected on all construction sites, on which the construction schedules, the contractors, the construction supervision companies, telephone numbers for environmental complaints, etc. were publicized. Before constructions, training were held to workers of the contractors for learning environmental knowledge, laws and regulations, as well as the EMP and the mitigation measures. 4 Environment Protection Targets The environment protection areas for the two subprojects are listed in Table 5 and Table 6 below according to the Environmental Management Plan. Table 5. Environment Protection Targets of Erlangmiao WWTP Subproject

Protection Item Environment Protection Area Direction Distance Grade Water intake at Yu-jia-tou Surface (Wuhan section of Yangtze 400m Ⅲ water River) Zijingyuan Northwest 110m Xinshiji Garden C area North 50m Ambient Xinmeilvdi North 40m II Second Brigade of Hubei No. 1 Division Northeast 240m of Armed Police Noise Pengcheng Garden West 35m 2 Xinshiji Garden B area West 35m Aijia Guoji Huacheng East 80m

Table 6. Environment Protection Targets of Caidian WWTP Subproject

12 Environmental Monitoring Report_No.3 ADB WWSMP

Distance to Site Protection Item Environment Sensitive Point (m) Grade No. 3 and No. 5 groups of 500 Shiyang Village Grade II (Air) WWTP Grade 2 (Noise) No. 4 group of Shiyang Village 450

5 Monitoring during Construction HDEMS conducted the environmental monitoring and inspections for the four subprojects based on the EIA and actual construction processes. 5.1 Monitoring Period Covered completed construction process, emphasize environmental sensitive areas and key points nearby the construction sites. 5.2 Monitoring Parameters

Ambient air: TSP, PM10;Wastewater: pH, SS, CODcr, BOD5, NH3-N and Oil;Noise: Leq(A) 5.3 Monitoring Personnel Pei Hong(senior engineer); Weng Ming(engineer); Wang Zhimin(engineer) 5.4 Monitoring Point The monitoring points include residential area and schools nearby the construction sites. In addition to the points indicated in the EIAs, monitoring points at some construction sites, pumping stations and pipeline routes were also selected. Due to construction process, some points indicated in the EIAs were not included, which will be included in next monitoring. The monitoring and inspections were conducted on April 1, 2009 and December 31, 2009 by HDEMS. The monitoring parameters include TSP, PM10.and Noise. 5.5 Monitoring of Ambient Air Quality

5.1.1 Monitoring parameter: TSP、PM10, detect wind direction, wind speeds, air pressure and temperature while sampling; 5.1.2 Monitoring points are listed in Table 7 and Fig. 1 and Fig.2; 5.1.3 Monitoring Frequency: 3 times/day for TSP and PM10, 45minuts/time, for a day.

13 Environmental Monitoring Report_No.3 ADB WWSMP

Table 7 Monitoring Points for Ambient Air Quality

Monitoring No. Project Monitoring Point Parameter

1○ Office area Erlangmiao 1 2○ Construction Site WWTP_II 3○ Xinlvmeidi 1○ Dushijiari Dongxihu Three 2 Gates Connection 2○ Construction Site 3○ Construction Site TSP, PM10 1○ Construction Site 3 Caidian WWTP 2○ Construction Site 3○ Construction Site 1○ Construction Site Nantaizihu 4 2○ Construction Site WWTP_II 3○ Construction Site

5.6 Noise Monitoring at boundary of Construction Site and Sensitive Areas 1)Monitoring Parameter: Leq(A) 2)Monitoring points are listed in Table 8 and Fig 1 and Fig.2 3)Monitoring frequency: each during both daytime and nighttime for a whole day for the four subprojects

14 Environmental Monitoring Report_No.3 ADB WWSMP

Table 8 Monitoring Points at Sensitive Areas

Monitoring No. Project Monitoring Point Parameter time Zijingyuan 1 Xinshiji Garden C 1 Xinlvmeidi 1 Armed Police Hubei 1 Erlangmiao No.1 Brigade 1 WWTP Pengcheng Garden 1 Xinshiji Garden B 1 Aijia Guoji 1 Huacheng Boundary of site 7 Leq(A) Donggxihu Dushijiari 1 2 Three Gates Tianhe Airport Road 2 Connection Machi Bridge 3 No.3 Group of Shiyang 1 Village Caidian 3 No.5 Group of Shiyang WWTP 1 Village Boundary of site 5 Nantaizihu 4 Boundary of site 8 WWTP

15 Environmental Monitoring Report_No.3 ADB WWSMP

Xinshiji Garden C

Zijingyuan 13△ Xilvmeidi 3○ 1▲ 12△ Transformer Gate Erlan Station Armed gmia 10△ Police No. 1 Xishiji 2▲ o Brigade Garden WW 4▲ 9△ 11△ Office Area TP 1○ 8△

Phase II Construction ▲ 3

Gardon Pengcheng 14△ SITE 5▲ 2○ 6▲

7▲

Fig 1 Monitoring Points for Ambient air and Noise at Construction Site of Erlangmiao WWTP

1○ 5▲ Airport Changqing Garden Road 4▲

Construction 2○

6▲

Jinshan Avenue Jinshan Avenue

1▲ Construction Dongfangma City 3▲ 2▲ 3○

Fig 2 Monitoring Points for Ambient air and Noise at Construction Site of Dongxihu Three Gates Connection

16 Environmental Monitoring Report_No.3 ADB WWSMP

Riverbank

3▲ Jing-Zhu 4▲ 1▲ Expressway

Groupo. 2○ 1○ No.3 of Construction site 7▲ Shiyang Village

5▲ Group.N 3○ 200m o4 of Shiyang 6▲ Village 2▲

Groupo.No.5 of Shiyang Village

Note: 4▲、5▲ Noise impact from the expressway

Fig 3 Monitoring Points for Ambient air and Noise at Construction Site of Caidian WWTP

5▲ 4▲

6▲ 3▲ Constructi on Site of Phase_I Jiangdi 3○ WWTP Village Area 7▲ Industrial Construction Site Zone 2○ 2▲

○ 8▲ 1 1▲

Dunkou Road

Fig 4 Monitoring Points for Ambient air and Noise at Construction Site of Nantaizihu WWTP_II 5.7 Wastewater Monitoring

17 Environmental Monitoring Report_No.3 ADB WWSMP

The Contractor Purchase commercial ready-mixed concrete without using water at the sites, therefore, there is no wastewater discharge. 5.8 Monitoring Methods and Evaluation Standard Based on the National Specifications, the standard methods of monitoring are listed in Table 9, and the evaluation standards of the monitoring for the proposed construction sites are shown in table 10 according to the environmental functional layout of Wuhan Municipality and the EIAs of the subprojects. Table 9 Examination Methods of Monitoring

Item Parameter Standard Methods TSP GB/T15432-95

Ambient Air PM10 GB6921-86

NO2 GB/T15435-95 Environmental Noise GB/T14623 Leq(A) Site Noise GB12349

Table 10 Evaluation Standard

Item Parameter Standards Standard Sources Daily average TSP 0.30mg/m3 Daily average 0.15 GB3095-1996《Ambient Air Ambient Air PM 10 mg/m3 Quality Standard 》Grade II Hourly average 0.24 NO 2 mg/m3 Environmental Daytime 60dB(A) GB3096-2008《 Noise Nighttime 50 dB(A) Noise Standard 》Grade II GB12348-2008《Noise Leq(A) Daytime 60dB(A) Standard at Boundary of Site Noise Nighttime 50 dB(A) Industrial corporation》Grade II

5.9 Result and Assessment of Monitoring The monitoring data of ambient air quality are shown in Table11

18 Environmental Monitoring Report_No.3 ADB WWSMP

Table 11. Monitoring Data of Ambient Air Quality

TSP PM10 Monitoring Project Point Time Time Time Time Time Time 1 2 3 1 2 3 1○ 0.240 0.281 0.205 0.161 0.152 0.127 Erlangmiao WWTP 2○ 0.249 0.293 0.215 0.182 0.176 0.114 3○ 0.197 0.188 0.192 0.158 0.155 0.102 1○ 0.192 0.209 0.212 0.176 0.184 0.188 Dongxihu Three 2○ 0.329 0.357 0.351 0.183 0.194 0.207 Gates Conection 3○ 0.342 0.333 0.325 0.177 0.182 0.179 1○ 0.255 0.260 0.266 0.167 0.144 0.154 Caidian WWTP 2○ 0.261 0.269 0.263 0.150 0.149 0.161 3○ 0.259 0.253 0.260 0.155 0.142 0.149 1○ 0.183 0.190 0.189 0.132 0.140 0.142 Nantaizihu WWTP_II 2○ 0.222 0.241 0.253 0.157 0.160 0.157 3○ 0.177 0.186 0.182 0.143 0.149 0.140 Standards (mg/m3) 0.30 0.15

During the air quality monitoring, due to dust impact generated by passing vehicles, TSP and PM10 at some points exceeds the Grade II of national standard of GB3095-1996. The monitoring data of noise are as Table 12 below Table12 Monitoring Data of Noise at Construction Boundary and Sensitive Points

Monitoring Monitoring Data during Data during Project Standard Date Point Daytime Nighttime Erlangmiao 2009-05-20 1▲ 51.5 49.8 Daytime WWTP 2▲ 50.6 47.6 60/70dB(A) Dongxihu 3▲ 48.1 45.4 Nighttime Three 4▲ 49.3 46.6 50 dB(A) Gates 5▲ 50.2 48.5 Conection 6▲ 50.8 49.3 Caidian 7▲ 51.4 45.0 WWTP 8△ 52.4 48.0 Nantaizihu △ WWTP_II 9 50.9 47.6 Erlangmiao 10△ 48.8 49.3 WWTP 11△ 49.9 48.8 12△ 52.7 48.9 13△ 51.4 48.6

19 Environmental Monitoring Report_No.3 ADB WWSMP

14△ 49.5 48.9 1△ 57.5 - Dongxihu 2▲ 63.3 - Three 3▲ 64.8 - Gates 2009-10-28 4▲ 65.5 - Conection 5▲ 66.2 - Caidian WWTP 6▲ 63.9 -

1ᇞ 54.5 -

Nantaizihu WWTP_II 2009-5-13 2ᇞ 47.2 - Erlangmiao WWTP 3▲ 59.5 - 4▲ 59.7 - 5▲ 58.3 - 6▲ 49.0 - 7▲ 57.2 - 1▲ 57.4 - 2▲ 52.7 - Dongxihu 3▲ 48.6 - Three 4▲ 47.5 - 2009-10-30 Gates 5▲ 45.8 - Conection 6▲ 48.1 - 7▲ 51.8 - 8▲ 58.0 -

Based on the monitoring results in Table 12, the noise at the points nearby Jinshan Avenue of Dongxihu Three Gates Connection Project, and the point nearby Jingzhu Expressway of Caidian WWTP Project exceed the national standard during day time due to traffic noise, but other points meet the standard (Grade II) during both daytime and nighttime. 6 Conclusion and Recommendation The main reason for TSP and PM10 exceeded the standards is the dust caused by material and construction wastes transport vehicles, which also caused the noise. The mitigation measures for environment protection have been generally implemented by the contractors. The monitoring results indicated that the

20 Environmental Monitoring Report_No.3 ADB WWSMP

environmental impacts due to the constructions are acceptable. The PMO and the construction supervision companies should stake measures to strength the supervision to contractors’ environmental management, and enforce the contractors taking the following measures: 1) Go on with implement the environmental management plan, reasonably lay out the construction equipment and schedule for mitigating the environmental impacts; 2) Using low-noise equipment, ban construction vehicles from sounding their horns to reduce noise impact; 3) Increase water spraying of transportation routes and materials handling sites where dust is being generated; Particular attention will be paid to dust suppression adjacent to sensitive receptors such as schools or residential areas; 4) All wastes (hazardous and non-hazardous) will be removed from sites to approved waste disposal sites with the proper credentials following the appropriate standards for mitigating impacts. App1. Monitoring Report of Ambient Air Quality App2. Monitoring Report of Environmental Noise App3. Weekly and Monthly Monitoring Report during Construction submitted by contractor

21