APPENDIX 1

Project Owner Project Name Details of Scheme Status Project Comments DISTRICT FLOOD MITIGATION PROJECTS 2018-2019 Environment Wick RevetmentFlood Defence Repairs Maintenance Design and Repairs to approx. 60m of Awaiting tender returns under Agency feasibility stage concrete block revetment, framework including construction of new toe and extension of revetment where saltings have eroded away. Environment Rolls Farm Flood Defence Maintenance Design and repairs to approx. 150m of Minor revetment repairs (upto 2m x Agency revetment, feasibility stage concrete block revetment, 2m) are being completed by land Tollesbury with new toe to be owner. EA awaiting tender returns constructed in some places. under framework for large scale works.

Environment Skinners Wick, Flood Defence Maintenance Design and patchwork repairs in 3 Agency Highams Farm, feasibility stage separate locations along the Lauristons north bank of the Revetment Blackwater Repairs Environment Bradwell Flood Defence Maintenance Design and Patchwork repairs Agency waterside feasibility stage Environment Stokes Hall, Flood Defence Maintenance Design and Revetment repairs and In final stages of design and feasibility Agency feasibility stage embankment repairs Environment Salcott Walls Slip Flood Defence Maintenance Design and Embankment reconstruction Awaiting tender returns under Agency repairs feasibility stage to repair slips in defence. framework

Environment Abbotts Hall Flood Defence Maintenance Design and removal of self set Planning stage ahead of Autumn Agency vegetation feasibility stage vegetation to allow working period removal inspection of asset Environment Bay Flood Defence Maintenance Design and removal of self set Planning stage ahead of Autumn Agency vegetation feasibility stage vegetation to allow working period removal inspection of asset Environment Riverside Flood Defence Maintenance Design and removal of self set Planning stage ahead of Autumn Agency Industrial Estate feasibility stage vegetation to allow working period vegetation inspection of asset removal Environment Woodrolfe Road Flood Defence Maintenance Design and reconditioning crest of Aim to deliver in house. Agency Embankment feasibility stage embankment where heavy improvements footfall leads to erosion Environment Creek Flood Defence Maintenance Planning and repairs to revetment and confirmed to proceed to construction Agency Revetment construction proection to toe stage. repairs stage Environment Mill Beach Sea Flood Defence Maintenance Design and patchwork repairs to Agency wall repairs feasibility stage concrete block revetment Environment Bounds Farm, Flood Defence Maintenance Design and Revetment replacement Aim to deliver in house. Agency feasibility stage work in two locations. revetment repairs Environment Mundon Wash Flood Defence Maintenance Design and replacement of penstocks Agency Penstock feasibility stage replacement Environment Maylandsea Flood Defence Maintenance Design and repairs to toe of Aim to deliver in house. Agency revetment feasibility stage embankment repairs Environment Bridgemarsh Flood Defence Maintenance Design and repairs to minor scour of Aim to deliver in house. Agency Creek feasibility stage embankment Embankment Repairs Environment Holliwell and Flood Defence Maintenance Design and replacement of approx. 50m Awaiting tender returns under Agency Redward feasibility stage of revetment and new toe framework revetment constuction. repairs Environment Grange Outfall Flood Defence Maintenance Design and desilt of high level Aim to deliver in house. Agency overhaul feasibility stage watercourse, flood embankment surveying and asset inspection Environment Burnham Flapped Flood Defence Maintenance Design and Replacement of flapped Awaiting tender returns under Agency outfall feasibility stage drainage outfalls framework replacements Environment West Flood Defence Maintenance Design and repairs to minor scour of Aim to deliver in house. Agency embankment feasibility stage embankment repairs County Maldon Central Essex Capital scheme Design and Flood Storage potentially in We are still trying to resolve post Council feasibility stage Brickhouse Farm Maldon construction asset adoption issues. APPENDIX 1

Project Owner Project Name Details of Scheme Status Project Comments Essex County The Causeway Essex Flood Management initial Exploring Detailed Flood Risk The initial assessment has been Council assessment Funding Appraisal Study are all completed and it has been agreed that Oportunities sources of flooding. The there would be no viable scheme. study will examine the flood However funding is being sought for risk from all sources while detailed study of flood risk in this taking into consideration location as part of The Causeway Strategies, Plans and Masterplan Assessments from past documents such as Catchment Flood Management Plans, Shoreline Management Plans, Surface Water Management Plans and River Basin Management Plans. In addition, the study will seek to outline the effects of the interaction between different flood risk sources and the impacts on Essex County Burham Proprty Level Resillience 3 Completed, 1 Measures installed on 4 applications received from Station people and property. Council outstanding Properties Road, Burnham on Crouch. 3 PLR installations have been completed and 1 is still outstanding. Essex County Heybridge Proprty Level Resillience Completed Measures installed on 2 applications received and both Council Properties properties have had installations completed Essex County Maldon Proprty Level Resillience Completed Measures installed on 3 applications received and the Council Properties properties have had installations completed ECC/MDC/Anglia Tollesbury Potential Flood Alleviation Scheme In discussion Design not confirmed Partners engaging with AW to explore n Water details to be confirmed. with Partners awaiting further discussion how this matter can be resolved. A number of Residents and Proprietors completed DG5 forms (AW) awaiting outcome. Wickham Flood Alleviation Scheme potentially In discussion Details to be confirmed Bishops through ECC CIF with Partners PC/Private Landowners