Main works Modane – 2021

Torino - Modane Closure 300’ single track with 240’ total closure in nighttime – Modane for two nights every week (S/D, D/L) Jan – Dec 2021 Torino S. Paolo – Closure 240’ single track with 120’ total closure in nigthtime Bussoleno for five nights every week (L/M ÷ V/S) Single track (P) closure for 42 days (26/07 – 06/09/2021) for security works of and Serra galleries (one track). Torino - Modane No limitation for passengers trains. July – Sept – Exilles – Limitation for freight trains direction – France due to 2021 weight limitations . Freight train timetables changes and delays for passengers trains due to capacity restriction . Torino – Modane Jan 2021 – Apr N.12 single tack closure 240’ each week for 6 weeks for Chiomonte – Exilles – 2021 works on galleries before total closure in Summer Salbertrand Single track (D) for 48h for waterproofing bridge km 58+075 Torino – Modane – 58+ 916 – 58+368 – 60+529 – 60+695 Jun – Oct 2021 Chiomonte – Salbertrand Freight train timetables changes and delays for passengers trains due to capacity restriction .

Torino – Modane Total closure for 96h for waterproofing bridge km 8+807 July 2021 (10-14 /07/2021)

1 Main works – 2021

Total closure 240’ nighttime for 5 nights every week Genova – Ventimiglia Jan – Dec 2021 for maintenance, infrastructural/technological Savona – Ge. M. renewal works and works for gauge PC45 in galleries

Work on Ansaldo gallery with total closure for 5h for Genova – Ventimiglia Jan – Apr 2021 5 nights every weeks beetween Ge. Sestri and B. Ge Samp. – Ge Voltri M. Castelluccio.

Genova – Ventimiglia Total closure for 6h for one night for technological Dec 2021 Albenga – Loano renewal between Albenga and Loano.

Work of security galleries. Single track closure nightime for 8h + single track Genova – Ventimiglia closure for 48h during weekends between Jan – May 2021 Imperia – and Taggia Limitation for passengers trains and freight train timetables changes due to capacity restriction Total closure 240’ nightime for five nights every week for maintenance works. Genova – Ventimiglia Jan – Dic 2021 RFI is studying a new timetable for FUORIMURO trains in order to guarantee this capacity to work Total closure for 2 week end (June- July) / single Genova – Ventimiglia June – Dec 2021 track for 5 week end (Oct – Dec )for works on Ge Sestri P. – Ge. Voltri M. Branega Bridge related to Terzo Valico Project

RFI will verify the best period to

program this closure 2 Main works Modane – 2022

Torino - Modane Closure 300’ single track with 240’ total closure in Bussoleno – Modane nighttime for two nights every week (S/D, D/L) Jan – Dec 2022 Torino S. Paolo – Closure 240’ single track with 120’ total closure in Bussoleno nigthttime for five nights every week (L/M ÷ V/S) Single track (D) closure for 90 days for security works Torino - Modane of Exilles and Serra galleries (one track) and renewal Chiomonte – Exilles – Jun – Sep 2022 track works. Salbertrand Freight train timetables changes and delays for passengers trains due to capacity restriction . Total closure for 7h for 5 days a week for 3 weeks for Torino - Modane Mar – Oct 2022 works on Frejus gallery. – Modane EN 200 and 201 must circulate via Domo.

Possibility to program these total closures nighttime at the same time with SNCF-R total closures? (06/05 – 13/05/2022 and 28/20 – 01/11/2022)

3 Main works Ventimiglia – 2022

Genova – Ventimiglia Total closure 240’ nighttime for 5 nights every week Jan – Dec 2022 Savona – Ge. Voltri M. for gauge PC45 in galleries

Genova – Ventimiglia Total closure 240’ nightime for five nights every Taggia – Imperia Jun – Dic 2022 week for reneval track works. Taggia –

Genova – Ventimiglia Total closure 240’ nightime for five nights every Jan – Jun 2022 Savona – Finale week for reneval tracks

Total closure 240’ nightime for five nights every Genova – Ventimiglia Jan – Dic 2022 week for generic maintenance works.

4